Role of Court in ensuring climate justice in Bangladesh
-
Upload
independent -
Category
Documents
-
view
1 -
download
0
Transcript of Role of Court in ensuring climate justice in Bangladesh
Role of Domestic Court and International Arbitration in ensuring climate justice
in Bangladesh
Barrister Tapas K. Baul1
Umme Wara2
Abstract:
In this article, the authors have analysed the Niko case to show that presently in
Bangladesh climate viz-a-viz environment victims, both an individual and Bangladesh, as
a state, can go to two forums, i.e., the national court and the international arbitration
centres. The authors have also discussed briefly on the pros and cons of both the forums,
i.e., the national court and the international arbitration. In the later part of this article, the
authors have discussed why international bodies, e.g., Niko, prefer arbitration as a dispute
resolution mechanism rather than litigation. The authors have also presented other case
studies to show in which situations arbitrations are better solutions than litigation and
where not. In conclusion, the authors wished that Bangladesh should build up a legal
regime to have a better justice system for the environment cum climate victims.
1. Introduction
Recently, an international Arbitration Tribunal, International Centre for Settlement of
Investment Disputes (ICSID), has decided in favour of the ‘climate victims’ of
Bangladesh against a ‘giant’ international gas extracting company ‘NIKOi’ and due to
that decision, now it will be possible for the domestic courts of Bangladesh to hear the
pending money suit on compensation. The fact of the suit was that in a Gas Mine of
Magurchara two gas explosions took place on 2005 resulting into an environmental
disaster in the surrounding area.ii The explosion also had disastrous effects on the lives
of all living beings, including the human beings, in the neighbouring forests, fields, water
bodies, low lands and villages.iii NIKO was the company in charge of excavating and
supplying gas from that reservoir and it is claimed that the disaster took place due to
their negligence.iv Subsequently, in 2006v, Bangladesh Environmental Lawyers
1 Prosecutor, International Crimes Tribunal, Bangladesh and Advocate, Supreme Court of Bangladesh.
2 Assistant Professor of Law, Jagannath University, Dhaka, Bangladesh.
Association (BELA) filed a public interest litigation in the High Court Division of the
Supreme Court of Bangladesh against the government, Bangladesh Petroleum
Exploration and Production Company Limited (BAPEX), Bangladesh Oil, Gas and
Mineral Corporation (Petrobangla) and Nikovi and subsequently got an injunction order
that barred Petrobangla from paying gas bills to the company until the compensation
was settledvii. Later, on 27 May 2008 Petrobangla served on Niko legal notice claiming
TK 746.50 crore as damages for the blowoutsviii and filed the above-mentioned money
suit in the environment court of Dhaka. Finally on 2010, Niko formally requested for
arbitration to ICSID against Bangladesh and others.ix Now in this outset, it has become
pertinent to have a critical look towards the role of the courts of Bangladesh in ensuring
climate justice.
In this chapter, we will evaluate the avenues available to the climate victims of
Bangladesh to get justice for the wrongs done against them. To do so, we will not get
limited within the national mechanisms alone, we will evaluate the international
components of justice as well. It will be relevant to evaluate the performance of the
actors, both direct and indirect, who have some role to play one way or the other in
ensuring access to justice to the climate victims of Bangladesh. So first, we should find
the existing avenues, or forums, available under our judicial system in Bangladesh for
the climate victims.
2. Laws and Forums for the environmental and climate victims
The main sources of environmental law in Bangladesh are: the Constitution, statutory
laws and by-laws, customs, traditional perceptions and practices, international
conventions, treaties and protocols.x There are 187 environment related laws which can
be compartmentalized into land use and administration, water resources, fisheries,
forestry, energy and mineral resources, pollution and conservation, wildlife and
domestic animals, displacement, vulnerable groups, relief and rehabilitation, local
government, rural and urban planning and protection.xi The procedural rules for the
Courts to administer these laws would be derived mostly from the existing procedural
codes, i.e., the Civil Procedure Code, 1908, the Criminal Procedure Code, 1889 and the
Evidence Act, 1872.xii
Regarding forums, there are three forums to address environment and climate injustice,
i.e., by filing a suit in the environment court, by filing public interest litigation in the
form of writ petition under Article 102 of the Constitution of the People’s Republic of
Bangladesh and by filing a complaint before the international bodies subject to the
question of jurisdiction and presence of such provision in the agreement signed
between the parties. We will start our discussion with the power of the environment
court to ensure climate justice and while doing so we will also highlight on the pros and
cons of the relevant act, i.e., Poribesh Adalat Ain, 2000 (Environment Court Act, 2000).
3. Poribesh Adalat Ain (Environment Court Act, 2000) and Poribesh Adalat
(Environment Court)
Within 3 years of UN Conference on Environment and Development (UNCED), 1992xiii in
Rio de Janeiro of Brazil, Bangladesh as a signatory state to the Rio Declaration, took its
first step towards fulfilling its international commitment by enacting Poribesh
Songrokkhon Ain, 1995 (Environment Conservation Act, 1995). Since commitments
recorded in the Rio Declaration call for legal and judicial activismxiv and subsequent
National Environmental Policy of 1992, government finally enacted Poribesh Adalat Ain,
2000. Although this piece of enactment has given opportunity to both environmental
and climate victims to access the judicial process and opportunity for the national
courts to exercise international principles, like: sustainable developmentxv,
intergenerational equityxvi, the precautionary principlexvii, polluter pays principlexviii
etc., lacunas have been identified.
Lacunas of the law which are related with the environment court as well, at a glance,
are:
There are only two environmental courts, i.e., one in Dhaka and
another one in Chittagong for the whole countryxix, even though
there was supposed to be one environmental court for each
division, which means there should have been at least seven
environmental courts in the countryxx.
As per the law, the environmental courts should have been headed
by a judge of the status of the Joint District Judgexxi, however, in
reality Assistant Judges play the role of a judge in the
environmental courtsxxii.
According to section 4 of the Environmental Courts Act, the judges
of the environment courts should have dealt with the
environmental cases alone, however, in reality they deal with
heap of other cases and practically, they hear other cases and
occasionally hear environmental cases.
The major objection regarding the Act of 2000 lies with sub-
section 3 of section 5. As per this sub-section, the environmental
courts will have no jurisdiction over any complaint, unless and
until the Inspectorxxiii of the Directorate of Environment submits
his written report to the Court. This means, primarily the judicial
mechanism has to be triggered by an executive. This is wrong in
so many levels. First, this is against the principles of separation of
power. Secondly, if the concerned officer is a corrupted person,
which is very common in Bangladesh, then it is quite possible that
he will submit a polluter-friendly report, moreover, he may not
submit any report or may cause delay, since initially no time limit
to submit the written report was included in the Act of 2000.
However, a checking procedure has been introduced by
amendmentxxiv, and now if the Inspector fails to submit the report
within 60 days then the Judge may take the case into cognizance
without the written report subject to opportunity to the Inspector
to come up with a reasonable explanation for not submitting the
report.
Even though the environment court enjoys the exclusive
jurisdiction for trial of an offence or for compensation falling
under the Environment Conservation Act and other
environmental laws, however the government is yet to declare
the other laws which are to be dealt with by the environment
court.xxv In addition, the government has not yet framed
necessary procedural rules for the smooth functioning of the
court.xxvi
Again under section 7 of the Environmental Conservative Act, the
Director General of the Department of Environment has the
authority to impose compensation upon the polluter if it appears
to him that any act or mission is causing harm to the ecosystem,
however, neither the Act nor the Rules of 1997 is yet to spell out
the procedure in which to calculate environmental damage for the
purpose of paying compensation.xxvii
Section 12 of the Bangladesh Environment Conservation Act, 1995
imposes restriction upon free establishment of industrial unit or
project without environmental clearance certificate under section
7 from the local government authority, however, till today neither
the Act nor the Rules provides any procedure to be followed by
the local government authority in issuing such no objection
certificates and due to absence of procedures this provision of
public hearing has not yet been incorporated in the
environmental conservation Act or rules.xxviii In addition, it is yet
to be reviewed that whether local government authority has that
capacity or not.
Questions can also be raised regarding the jurisdiction of the court.
Which types of polluters are the subject-matters of this court?
Initially, we have two types of polluters, i.e., national polluters
and international polluters. National polluters can also be divided
into categories, i.e., citizens or national enterprises and foreigners
or international enterprises living and working in Bangladesh
through their local branch, like – Niko. International polluters can
also be divided into two categories, i.e., private individuals or
enterprises and other states. By the term ‘state’, from the climate
/ environmental perspective, we can consider all the states
irrespective of their proximity since the polluter / responsible
state can be thousand miles away from Bangladesh but causing
significant damage to the victims by destroying their climate and
/ or environment. After a plain reading of the Preamble and long
title of the Act of 2000 together with section 5 of the Act, it can be
stated that the environment court of Bangladesh can exercise
their jurisdiction over the national polluters be it a citizen or a
foreign element. The proceeding against Niko is a good example
of this proposition. However, foreign elements are not within the
jurisdiction of this court. Hence, these courts do not have any
power over foreign elements and the climate / environmental
victims.
4. International arbitration: its jurisdiction and procedure
This article has started with Bangladesh’s ongoing legal attempt against the oil
company, i.e., NIKO, and as it has been suggested Bangladesh is fighting against NIKO in
two fronts, one – the District Court of Dhaka and another – in ICSID, where a dispute
will be settled through Arbitration. Therefore, in this part of the article, we will start
with simple questions, like – what is arbitration? what are the procedures that are
followed in an arbitration? how can it help to ensure the justice for the climate or
environmental disaster victims of Bangladesh? etc.
Arbitration is a consensual method of dispute resolution outside the court system by
one or more (usually three) independent and neutral arbitrators which the parties
agreed voluntarily. The arbitral award is final and binding and is enforceable as a
court’s decree. If the country where the award is given is a contracting state of the
Convention on the Recognition and Enforcement of Foreign Arbitral Awards, 1958 (also
known as the New York Arbitration Convention), it may be enforced in any of the 148
countries that are members either through an adhoc arbitration or an Institutional one ;
Bangladesh Institute for International Arbitration (BIAC).
Since Bangladesh is a party to the New York Convention and the ICSID Convention 1965
(Convention on the Settlement of Investment Dispute between States and Nationals of
Other States) and the Arbitration Act 2001 provides for enforcement of foreign arbitral
awards in accordance with the New York Convention, Bangladesh has entered into over
20 bilateral investment treaties (BITs) with other states, most of which contain specific
dispute resolution provisions for the settlement of disputes between investors and
Bangladeshxxix. But to initiate arbitration, it is good to have a relevant clause while the
agreement is signed between the parties mentioning if any dispute arises which is an
arbitrable one shall be resolved by arbitration. According to section 9(2) of Arbitration
Act of 2001, an arbitration agreement shall be in writing. An arbitration agreement shall
be deemed to be in writing if it is contained in- (a) a document signed by the parties; (b)
an exchange of letters, telex, telegrams, fax, e-mail or other means of telecommunication
which provide a record of the agreement; or (c) an exchange of statement of claim and
defence in which the existence of the agreement is alleged by one party and not denied
by the other. Thus any party can resolve their disputes through arbitration which is
different than a litigation in few ways.
5. Arbitration vs. Litigation:
Litigation is a lawsuit, heard and adjudicated in court by judge(s). Arbitration, on the
other hand, is the outcome of an agreement between two or more parties to a contract
to resolve a dispute through a specific process outside of the courts. In arbitration, the
disputant parties nominate one (or, three) neutral and independent arbitrator(s). It is
responsibility of arbitrator/ arbitrators to examine claims and counter claims, to hear
witnesses, to peruse evidence and to arrive at a decision known as an arbitral award.
Unlike in litigation, the rights of appeal are limited in arbitration. Arbitral award is
enforceable as a decree of court if the time for making an application to set aside the
arbitral award under section 42 of the Arbitration Act 2001 has expired, or such
application having been made has been refused (section 44 of the Arbitration Act 2001).
The basic purpose of arbitration is to resolve certain types of disputes speedily, with
confidentiality and by the parties’ chosen arbitrator(s). Almost all types of civil disputes
can be arbitrated. This includes contractual disputes, shareholder disputes, commercial
disputes, family disputes, tort, etc. In some countries, a few categories of criminal cases
are also resolved through arbitration. It is always advisable to check with your counsel
to determine if the case is suitable for arbitration.
Arbitration provides distinct advantages over court litigation. Arbitration is a private
method of settling disputes; parties can tailor the arbitration proceeding in the manner
they choose. For example, parties involved in arbitration can agree to limit the number
of witnesses each side will present, set parameters on the amount and type of evidence
that will be presented, and pre-determine what issues the arbitrator’s award should
cover. Another important advantage of arbitration is that in arbitration the parties can
choose their arbitrator(s) having experience in the subject matter of the dispute. If the
parties had gone to court, it is uncertain if the judge dealing with their case would have
expertise or experience in areas/ matters of the dispute. The arbitrator’s knowledge
allows for a quick, in-depth analysis of the issues, which in turn saves time and expense.
Unless parties decide otherwise, arbitration hearings are confidential and the decisions
reached are generally not matters of public knowledge. On the other hand, court
proceedings are generally in the public domain. The companies involved may not want
the public to be aware of the details of their business dealings. Arbitration Award is final
and binding on both the parties. A party may challenge an Arbitration Award on very
limited grounds. Usually, courts have very limited scope to set aside an Arbitral Award.
Finally, unlike court’s order, Arbitration Award is enforceable in 148 countries around
the world, if the place of arbitration occurs within a country which is signatory to New
York Conventionxxx.
In arbitration, parties must ensure that all the required documents, evidences and
witnesses are submitted; otherwise, their case may suffer. Secondly, an arbitration
award is very difficult to set aside on appeal. This can be a serious problem for a party
that is not prepared for a decision against it. Arbitration can sometimes be as expensive
as court litigation. However, since the parties are in control of the arbitration process,
they may design it in a way to prevent lengthy extensions and also contain costs.
Case Study: Saipem S.p.A. v. The People’s Republic of Bangladeshxxxi (“Saipem v.
Bangladesh”)
i) Background and the ICC Arbitration:
Saipem S.p.A., an Italian oil & gas company, and Petrobangla (Bangladesh Oil, Gas &
Mineral Corporation), a Bangladeshi public entity, entered into an agreement on
February 14, 1990, to build a natural gas pipeline in Bangladesh. This contract was
governed by the laws of Bangladesh and set forth an arbitration clause. Such clause
referred any dispute between the parties to the Rules of Conciliation and Arbitration of
the International Chamber of Commerce (ICC) and established Dhaka, Bangladesh as the
venue of the arbitration. The whole project was significantly delayed because of strong
opposition by the local population. Although the parties agreed on extending the
completion date, they could not reach an agreement regarding compensation and
additional costs as a consequence of such delay.xxxii Also, a controversy arose in relation
to a warranty bond and retention monies. In accordance with the original contract’s
arbitration clause, Saipem initiated an ICC arbitration tribunal seeking outstanding
payments owed under both the original contract and the subsequent extension
agreement.
During the ICC arbitration, Petrobangla brought before the ICC tribunal various
procedural requests.xxxiii Since the ICC tribunal denied such requests, Petrobangla
brought an action before the First Court of the Subordinate Judge of Dhaka seeking the
revocation of the ICC Tribunal’s authority. The grounds of this action were an alleged
misconduct of the arbitrators and a breach of the parties’ procedural rights when
deciding the above-mentioned procedural requests made by Petrobangla.
Additionally, Petrobangla filed an action in the High Court Division of the Supreme
Court of Bangladesh to stay all further proceedings of the ICC arbitration. A week later,
an injunction restraining Saipem from proceeding with the ICC arbitration was issued
by the Supreme Court of Bangladesh. Subsequently, Saipem filed an objection to the
injunction restraining it from proceeding with the ICC arbitration. Thereafter, on April
5, 2000, a decision revoking the authority of the ICC arbitration Tribunal was issued by
the First Court of the Subordinate Judge of Dhaka. Even though this last decision was
subject to two degrees of appeals, Saipem decided not to do so. According to Saipem,
“the latter decided not to file an appeal because any expectations to succeed appeared
unsustainable under the circumstances.”xxxiv
Despite the decision revoking the authority of the ICC tribunal rendered by the
Bangladeshi courts, the ICC tribunal decided to resume proceedings. Subsequently,
Petrobangla secured various injunctions from the High Court Division of the Supreme
Court of Bangladesh restraining the continuance of the ICC arbitration tribunal.xxxv
Nevertheless, on May 9, 2003, the ICC arbitration tribunal issued a final arbitration
award holding inter alia that Petrobangla had breached its contractual obligation to
compensate Saipem for the time extension and additional works.
In order to set aside the arbitration award, Petrobangla filed an action before the High
Court Division of the Supreme Court of Bangladesh under Sections 42(2) and 43 of the
Bangladeshi Arbitration Act 2001. This court denied the petition on April 21, 2004
stating that it was “misconceived and incompetent inasmuch as there is no Award in the
eye of the law, which can be set aside…A non-existent award can neither be set aside
nor can it be enforced.”xxxvi According to this decision, the ICC award was rendered non-
existent and was unenforceable in Bangladesh. Nonetheless, Saipem did not appeal this
decision.
ii) The ICSID Arbitration
Saipem, on October 5, 2004, filed a request for arbitration with the International Centre
for Settlement of Investment Disputes (ICSID). The parties in the ICSID arbitration were
Saipem and the Government of Bangladesh and the claims were based on the breach of
the Bilateral Investment Treaty (BIT) between Italy and Bangladesh.xxxvii The basis of
Saipem’s claims was the undue intervention of the Bangladeshi courts in the ICC
arbitration, which precluded the enforcement of the ICC award in Bangladesh or
elsewhere. According to Saipem, those acts constituted an expropriation and deprived
Saipem of any compensation. Thus, Saipem in its request for arbitration sought inter
alia a declaration that Bangladesh expropriated Saipem of its investments without
compensation and that Bangladesh breached its obligations under the BIT.
On June 30, 2009, the ICSID Tribunal rendered the final award. The Tribunal considered
that the expropriated “property” consisted of “Saipem´s residual contractual rights
under the investment as crystallized in the ICC Award.”xxxviii Also, the ICSID Tribunal
concluded that the actions of the Bangladeshi courts were not a direct expropriation,
but “measures having similar effects” within the meaning of Article 5(2) of the BIT.xxxix
These actions deprived Saipem of the benefit of the ICC Award.xl The decision of the
Supreme Court of Bangladesh that the ICC Award was a nullity “is tantamount to a
taking of the residual contractual rights arising from the investments as crystallized in
the ICC Award. As such, it amounts to an expropriation within the meaning of Article 5
of the BIT”.xli
The ICSID Tribunal concluded that the revocation of the arbitrators’ authority by the
Bangladeshi courts was contrary to international law, specifically to the principle of
abuse of rights and the New York Convention and, therefore, such revocation
constituted an expropriation within the meaning of Article 5 of the BIT.
The ICSID Tribunal concluded that courts of Bangladesh abused their rights when
exercising supervisory jurisdiction over the ICC arbitration process. Although national
courts have discretion to revoke an arbitrator´s authority in cases of misconduct, they
cannot use this discretion to revoke the authority of arbitrators based on reasons
wholly unrelated to such misconduct. In addition, the ICSID Tribunal determined that
the actions of the courts of Bangladesh were against the New York Convention,
specifically Article II (1), which imposes on Contracting States the obligation of
honoring arbitration agreements. Furthermore, the ICSID Tribunal deemed that “the
expropriation of the right to arbitrate the dispute in Bangladesh ... corresponds to the
value of the award rendered without the undue intervention of the court of
Bangladesh.”xlii Thus, the ICSID Tribunal established that Saipem was entitled for relief,
which was equivalent to the amount awarded in the ICC award plus interest.
In sum, the circumstances of this case were unique and it is very unlikely that they will
happen again. According to previous ICSID awards, an investor should exhaust local
remedies in order to initiate investment arbitration based on acts of the judiciary. The
ICSID Tribunal in this case found that this condition is not applicable in the case of
expropriation, with no further explanation. Therefore, the ICSID Tribunal’s holding
in Saipem v. Bangladeshseems to be restricted in such a way that most likely will not be
applied in future cases. It is a learning for us also not to misuse any of the power
ensured by the Arbitration Act and concerned Arbitration Rules. If these rules and
regulations are exercised with a bonafide intention to resolve a dispute between the
parties especially from different countries within shortest possible time, arbitration is
the best option for it.
6. Last few words:
Presently, on the one hand, lots of local and foreign investors prefer Bangladesh for
investment in the rising industrial sectors as well as in the gas mines and in the oil
reserves and on the other hand, national debates are taking place on government-
private initiative to set up a coal based power plant around Sundarban and a uranium
based power plant in Rupganj and their environmental aspects. These kinds of
dilemmas have triggered the old debate between the right to development and the right
to have a sustainable environment. Within all these confusions, the government and the
members of the civil society should not forget about necessity of having a strong dispute
resolution system for the environment and the climate victims, since forums, like – the
court or the arbitration, national or international, will finally decide about the fate of the
victims, who are entitled to their right to life, which depends both on the right to have a
healthy environment and right to development. Therefore, at the end, we wish
Bangladesh should build up a legal regime to have a better justice system for the
environment cum climate victims.
i ‘NIKO loses to Bangladesh’, www.natunbarta.com/english/national/2013/08/21/8078, accessed on
16.09.2013. ii ibid No. 1
iii ibid
iv Niko Resources (Bangladesh) Ltd. v. People’s Republic of Bangladesh and Others, ICSID Case No.
ARB/10/11 and ICSID Case No. ARB/10/18, Date of decision: 19 August, 2013, paragraph Nos. 94-97. v ‘Bangladesh no longer a party to Niko arbitration: ICSID’, New Age, 21 August, 2013,
http://newagebd.com/detail.php?date=2013-08-21&nid=61927, accessed on 16.09.2013 vi ibid No. 5, paragraph Nos. 98.
vii ibid No. 6
viii ibid No. 5, paragraph No. 100
ix ibid No. 5, paragraph No. 105
x Justice Mainur Reza Chowdhury, ‘Legal and Institutional Framework: Promoting Environmental Management
in Bangladesh’, 13(3), viewed on 17 September 2013 from
www.unep.org/delc/Portals/119/publications/Speeches/Bangladesh.pdf xi
ibid No. 11 xii
ibid No. 11 xiii
Informally known as the Earth Summit. For more, see: www.un.org/geninfo/bp/enviro.html xiv
‘Rio Declaration in Principle 11 requires the states to enact effective environmental legislation and standards,
access to judicial and administrative review process becomes relevant[..]
to uphold people’s right that such laws
would endure. Right to participation and access to environmental decision making process[...]
need express legak
recognition that the judiciary can safeguard in appropriate instance’ [footnotes deleted], ibid No. 11, 13(1). xv
FAP-20 case, (1997) 49 DLR (AD) 1 xvi
‘This implies that we have a duty to defend and improve the environment for present and future generations
and to use natural resources in a manner that ensures the preservation of the eco-system for the benefit of
present and future generation.’ Jona Razzaque, ‘Access to environmental justice: Role of Judiciary in
Bangladesh’, 13(5), viewed on 01.10.2013, from www.biliabd.org/.../jona%20.pdf xvii
‘... provides guidance in the development and application of international environmental law where there is
scientific uncertainty. The purpose is to encourage the decision makers to consider harmful effects of their
activities on the environment before they pressure those activities. ibid No. 17 xviii
‘... is used to prevent, control and reduce environmental harm. This principle expects polluters to bear the
costs of measures carried out by the public authorities with respect to potential and actual environmental
damage.’ ibid No. 17, 13(6) xix
Ministry of Law, Justice and Parliamentary Affairs, Letter dated 16.10.2001, Memo. No. 1273-bichar-4/5c-
4/2000, “Regarding the establishment of two Divisional Environmental Courts in two Divisions, i.e., Dhaka and
Chittagong and the establishment of one Environmental Appellate Court in Dhaka” (translated by the authors),
signed by Senior Assistant Secretary, Law, Justice and Parliamentary affairs. xx
Section 4 of the Environmental Courts Act, 2000 xxi
ibid No. 21 xxii
ibid No. 20 xxiii
For definition, see: sec. 2(kha) of the Environment Courts Act 2000 xxiv
The original sub-section 3 was replaced by section 5 of Act No. 10 of 2002
xxv Salahuddin M. Aminuzzaman, 2010, ‘Environmental Policy of Bangladesh: A Case Study of an Ambitious
Policy with Implementation Snag’, 18(11), viewed 12 October 2013, from:
www.monash.edu.au/research/.../paper_salahuddin_aminuzzaman.pdf xxvi
ibid No. 26 xxvii
ibid No. 26 xxviii
ibid No. 26
xxix
Bhuiya, sharif & Jahan, Karishma, Dr. Kamal Hossain and Associates, Global Arbitration Review, The
International Journal of Public and Private Arbitration, 2008, p 15
xxx <www.biac.org.bd> last accessed on 10.11.13
xxxi Saipem v Bangladesh (ICSID Case No.ARB/05/7) Unreported award June 20, 2009.
xxxii De Roa, Felipe Suescun, Comments on the ICSID Award Saipem v. Bangladesh: Would its Rationale be
Applicable in Future Cases?, International Institute for Conflict Prevention and Resolution
<http://www.cpradr.org/Resources/ALLCPRArticles/tabid/265/ID/714/Comments-on-the-ICSID-Award-
Saipem-v-Bangladesh-Would-its-rationale-be-applicable-in-future-cases-2011-Writing-Contest-Winner.aspx>
last accessed on 08.11.13
xxxiii “In particular (i) a request to strike from the record the witness statement of Mr. Clark [a key witness on
behalf of Saipem], (ii) a request that all witnesses be allowed to be present in the hearing room during the entire
hearing, (iii) a request that a letter from Petrobangla which was not on record be filed during cross-examination
of a witness, (iv) a request to strike from the record a “draft aide-mémoire” of the World Bank and certain cost
calculations prepared by Saipem, and (v) a request that transcripts be made of the tape recordings of the
hearing.”Saipem v Bangladesh Unreported June 20, 2009, at 31 xxxiv
“Because of the hostile climate in Bangladesh and because we were firmly convinced that the revocation of
the authority of the Arbitral Tribunal was completely illegal by all standards, we knew that we had no
alternative but to proceed with the arbitration. Our Indian counsel advised us that an appeal against the
injunction against the continuation of the arbitration was possible in theory, but unsustainable in substance. It
was clear that we would not be in a position to defend ourselves before the local courts and that the climate was
incompatible with a fair trial. As is confirmed by the witness statement of Mr. Nassauto, our witnesses,
including the members of the arbitral tribunal, would have risked being in physical danger had they come to
testify in Dhaka. Clearly the members of the ICC Tribunal would have been key witnesses in those proceedings.
The testimony of the Arbitrators would have been crucial, since the only reason for the revocation of the
authority of the ICC tribunal was the alleged misconduct of the proceedings imputed to the Arbitrators. They
could have demonstrated that no misconduct had ever been committed by them and that they had properly
conducted the arbitration proceedings pursuant to the ICC Rules and even to the provisions of the Bangladeshi
Arbitration Act.” Saipem v Bangladesh Unreported June 20, 2009, at 43. xxxv
Petrobangla filed an action in the First Court of the Subordinate Judge of Dhaka in order to set aside the ICC
tribunal’s decision to resume the proceedings. In addition, Petrobangla filed a request seeking a declaration that
the ICC Arbitration Tribunal was unlawful based on the decision of the Dhaka Subordinate Judge that revoked
the authority of the ICC Tribunal. Also, Petrobangla asked for an interim and a permanent injunction against the
continuance of the ICC Arbitration Tribunal, which was refused the same day. On May 27, 2001, Petrobangla
appealed this decision before the High Court Division of the Supreme Court. Within the same day, the High
Court Division issued an injunction restraining Saipem from pursuing the ICC Tribunal. Thereafter, this
injunction was confirmed by several decisions of the High Court Division of the Supreme Court. xxxvi
Saipem v Bangladesh Unreported June 20, 2009, at 50. xxxvii
Agreement of 20 March 1990 between Government of the Republic of Italy and Government of the
People's Republic of Banglaesh on the Promotion and Protection of Investments. The treaty entered into force
on 20 September 1994. xxxviii
Saipem v Bangladesh Unreported June 20, 2009, at 128. xxxix
Article 5 defines expropriation as follows: “(1) The investments to which this Agreement relates shall not
be subject to any measure which might limit permanently or temporarily their joined rights of ownership,
possession, control or enjoyment, save where specifically provided by law and by judgments or orders issued by
Courts or Tribunals having jurisdiction. (2) Investments of investors of one of the Contracting Parties shall not
be directly or indirectly nationalized, expropriated, requisitioned or subjected to any measures having similar
effects in the territory of the other Contracting Party, except for public purposes, or national interest, against
immediate full and effective compensation, and on condition that these measures are taken on a non-
discriminatory basis and in conformity with all legal provisions and procedures.” Agreement of 20 March 1990
between Government of the Republic of Italy and Government of the People's Republic of Bangladesh on the
Promotion and Protection of Investments. The treaty entered into force on 20 September 1994. xl
Saipem v Bangladesh Unreported June 20, 2009, at 129. xli
Saipem v Bangladesh Unreported June 20, 2009, at 129; Accord “[t]he taking away or destruction of rights
acquired, transmitted and defined by a contract is as much a wrong, entitling the suffer to redress, as the taking
away or destruction of tangible property”. Rudloff Case (Interlocutory), American-Venezuelan Commission, IX
United Nations Reports of International Arbitral Awards (Recueil des Sentences Arbitrales) 250. In Ruth
Teitelbaum. “Case Report on Saipem v. Bangladesh”. xlii
Saipem v Bangladesh Unreported June 20, 2009, at 204.