ii
PREFACE
Water is a prime natural resource, a basic human need without which life
cannot sustain. With the advancement of economic development and the rapid
growth of population, water, once regarded as abundant in Kerala is becoming more
and more a scarce economic commodity. Kerala has 44 rivers out of which none are
classified as major rivers. Only four are classified as medium rivers. All these rivers
are rain-fed (unlike the rivers in North India that originate in the glaciers) clearly
indicating that the State is entirely dependent on monsoon. Fortunately, Kerala
receives two monsoons – one from the South West and other from the North East
distributed between June and December. Two-thirds of the rainfall occurs during
South West monsoon from June to September. Though the State is blessed with
numerous lakes, ponds and brackish waters, the water scenario remains paradoxical
with Kerala being a water –stressed State with poor water availability per capita.
The recent landslides and devastating floods faced by Kerala emphasize the
need to rebuild the state infrastructure ensuring climate resilience and better living
standards. The path to be followed to achieve this goal might need change in
institutional mechanisms in various sectors as well as updation in technology.
Irrigation Design and Research Board with its functional areas as Design, Dam
Safety, Hydrology, Investigation etc., plays a prominent role in the management of
Water Resources in the State. The development of reliable and efficient Flood
Forecasting and Early Warning System integrated with Reservoir Operations, access
to real time hydro-meteorological and reservoir data and its processing, etc. have
become inevitable to ensure climate resilience. Being an organization that
continuously strives in pursuit of excellence in the field of quality design and
innovative research for water resources management of the State, capacity building
of the technical resource in Irrigation Design and Research Board (IDRB) is of prime
importance to achieve these goals. This documentation summarizes the strategy for
performance improvement of IDRB to complement the efforts taken by Water
Resources Department to rebuild the State in line with the goals envisaged by
various Government/International agencies.
iii
The document suggests specific short-term goals and targets for each wing
under IDRB so as to ensure overall development of the organization in the long-run.
The various goals are being set with a view to develop climate resilient infrastructure
and new major development projects that ensures people and their assets are able
to withstand the onslaught of future disasters. Some of the major achievements of
IDRB are also included. This document is prepared with a view to clearly lay down
the path for performance betterment and is hoped to serve as an evaluation tool.
I wish to place on record my heartfelt thanks to Hon’ble Minister for Water
Resources, Government of Kerala Sri. K Krishnankutty for his extraordinary support
and encouragement. I also wish to place on record my sincere gratitude to Sri. T K
Jose IAS, Additional Chief Secretary, Home & Water Resources Department for his
intellectual inputs and being the visionary, whose relentless follow-up has paved way
in formulating this document. I thank Sri. Pranab Jyothi Nath IAS, Special Secretary,
Water Resources for his advice and offer in supporting the document so as to realize
the goals envisioned in this document. I also thank various other staff in the
Government as well as State Planning Board for their offer of support in ensuring the
ideals should this document be published.
I thank all the Joint Directors (Smt. Subhalekshhmi R, Canals, Smt. Bindhu K P,
Design Manual, Smt. Manju S, Dam Safety, Smt. Ranjitha C N, Dams, Smt. Sandhya
S G, Hydrology and Investigation) and all Deputy Directors (especially Smt. Priji S S,
Deputy Director, Dams, IDRB) of IDRB whose sincere comments along with their
intervention by timely provision of details enabled to publish the document in
stipulated time. I also appreciate the support offered by Finance Officer and
Administrative Assistant of IDRB in their own means to achieve the goals envisaged.
Special thanks needs to be conveyed to the officers for their painstaking efforts
for designing and drafting this document within shortest time viz. Smt. Anugeetha B,
Assistant Director, Canals, Smt. Priya B S, Assistant Director, Dam Safety, Smt.
Soumya R. Chandran, Assistant Director, Hydrology, Sri Arun C, JWR Section,
Meenakshipuram (now under the orders of transfer to Dam Safety, IDRB), Smt. Suja
K, Assistant Director, Dams, Smt. Krishnendu R, Assistant Engineer, Investigation,
Smt. Nandini S Nair, Assistant Director, Dam Safety, Smt. Athulya Das A S,
iv
Assistant Director, Canals, Smt. Nazreen S, Assistant Director, Dams, Smt Devika S
L, Assistant Director, Hydrology, Sri. Rohith R D, Assistant Director, Hydrology, Sri
Anandababu S P, Junior GIS Technician. Final thanks to Sri. Priyesh R, Director,
IDRB for coordinating the entire assignment and offering valuable suggestions so as
to achieve the intended spirit of the document. I hope this document will act as a
guideline in developing IDRB as an institute of excellence in its mandated field.
Regards
D. Biju
Chief Engineer
Investigation & Design (IDRB)
Thiruvananthapuram
Contact No: - 04712784001
Email: - [email protected]
20th November 2020.
v
CONTENTS
LIST OF FIGURES ............................................................................................. viii
LIST OF TABLES .................................................................................................. ix
1. INTRODUCTION ........................................................................................... 1
2. ROLE, RESPONSIBILITIES AND FUNCTIONS OF IDRB ............................ 3
2.1 Vision ...................................................................................................... 9
2.2 Mission ................................................................................................... 9
2.3 Goals ...................................................................................................... 9
3. THE TEAM IDRB ............................................................................................ 12
3.1 Chief Engineer, IDRB ........................................................................... 12
3.2 Director (IDRB) ..................................................................................... 13
3.3 Joint Director (Canals) & Joint Director (Dams) .................................... 13
3.4 Joint Director (Dam Safety) .................................................................. 15
3.5 Joint Director (Hydrology and Investigation) ......................................... 16
3.6 Joint Director (Design Manual) ............................................................. 18
3.7 Other facilities ....................................................................................... 21
3.8 Team Vision (Division-Wise) ................................................................. 22
3.9 Goals and Timeframe ........................................................................... 22
3.10 Project- Year wise details ..................................................................... 25
4. HISTORY EVOLUTION AND CURRENT STATUS OF IDRB ......................... 26
4.1 Details of Completed Projects .............................................................. 26
4.2 Details of Ongoing Projects (2020-21) .................................................. 26
5. DETAILS OF CATEGORY-WISE PROJECTS................................................ 27
5.1 Plan Funds 2020-2021 ......................................................................... 27
5.2 Externally aided projects....................................................................... 32
5.3 National Hydrology Project ................................................................... 36
vi
5.4 Rebuild Kerala Initiative (RKI) Projects ................................................. 37
5.5 Kerala Irrigation Infrastructure Fund Board (KIIFB) Projects ................ 37
5.6 State Disaster Response Fund (SDRF) ................................................ 37
6. COLLABORATION WITH OTHER INSTITUTIONS ........................................ 38
6.1 Academic Institutions ............................................................................ 38
6.2 Research Institutions ............................................................................ 39
6.3 Research Projects ................................................................................ 40
6.4 Problems faced for research activities .................................................. 41
6.5 Collaboration with Kerala Engineering Research Institute (KERI) ........ 41
7. WEBSITE IMPROVEMENT ............................................................................ 43
7.1 Present status of website development ................................................ 43
7.2 Scope for future improvement .............................................................. 43
8. TRAINING AND CAPACITY BUILDING ISSUES ........................................... 45
9. PROBLEMS FACED BY IDRB ........................................................................ 47
10. WAY FORWARD .......................................................................................... 50
11. MONITORING AND REVIEW ....................................................................... 52
11.1 Officer in charge ................................................................................... 52
11.2 Monitoring methods .............................................................................. 52
12. SUCCESS STORIES .................................................................................... 53
12.1 Women Empowerment ......................................................................... 53
12.2 Major accomplishments under DRIP .................................................... 54
12.3 International/National Conferences ...................................................... 57
12.4 Others ................................................................................................... 58
vii
APPENDICES
Appendix I Details of Completed Projects…………………………......... 60
Appendix II Details of Ongoing Projects (2020-21)…………………....... 77
Appendix IIII Details of Works under Plan Schemes.…………………..... 101
Appendix IV Details of Works under RKI Projects.…………………........ 142
Appendix V Details of Works under KIIFB.…………………................... 144
Appendix VI Details of Works under SDRF…………………................... 148
viii
LIST OF FIGURES
Figure 2.1: Location of Dams and Barrages under Irrigation Department .................. 4
Figure 2.2: Hydro-met Network under IDRB (River Gauge Stations- 90 nos.) ........... 5
Figure 2.3: Hydro-met Network under IDRB (Rain Gauge Stations- 163 nos.) .......... 6
Figure 2.4: Hydro-met Network under IDRB (Tidal Stations- 32 nos.) ........................ 7
Figure 2.5: Various types of structures for which design consultancy services is
provided by IDRB .................................................................................... 8
Figure 3.1: Thaneermukkom bund ........................................................................... 15
Figure 3.2: Pattissery Dam- Construction in progress .............................................. 15
Figure 5.1: Plan Progress of IDRB: 2019-20 ............................................................ 34
Figure 5.2: Plan Progress of IDRB: 2020-21 (as on October 2020) ......................... 34
Figure 12.1: Women engineers at Malankara Dam, Kerala ...................................... 53
Figure 12.2: Moolathara Regulator at Palakkad- Renovated under DRIP ................ 55
Figure 12.3: New Bridge at Bhoothathankettu for diverting traffic over old barrage
constructed under DRIP ...................................................................... 55
Figure 12.4: Rip rap reconstructed under DRIP at Malankara Dam ......................... 56
Figure12.5: River Training wall constructed at Malankara dam ................................ 56
Figure 12.6: Turfing at Malankara Dam .................................................................... 57
ix
LIST OF TABLES
Table 5.1: Proposed Outlay for 2021-22 ....................................................................................... 35
Irrigation Design and Research Board, Kerala
Performance Progression Policies 1
1. INTRODUCTION
“In the wake of cognitive revolution, gossip helped Homo Sapiens to form
larger and more stable bands. Sociological research has shown that the
maximum ‘natural’ size of a group bonded by gossip is about 150 individuals.
Most people can neither intimately know, nor gossip effectively about, more
than 150 human beings”- Yuval Noah Harari from ‘Sapiens – A Brief History
of Humankind’
Kerala is blessed with rich endowment of water resources. However, the water
situation in the State remains contrary. As per the estimates, all 44 rivers in State
together yield 77.9 BCM (Billion Cubic Meter) of water, out of which about 70.2 BCM
is available in the State with an utilizable yield of 42.7 BCM (Source: Water
Resources of Kerala, 1974). The rest of the water is lost as run-off. Also, the Storage
capacity of major reservoirs in the State is only 5.8 BCM. Hence, only 13.5% of the
total utilizable water could be stored. Moreover, the projected need by the State for
the year 2031 is 44 BCM (Perspective Plan 2030-Kerala Vol III by Kerala State
Planning Board).
Recent floods and droughts have taught us that Kerala cannot be complacent
about its water resources and that the path to be followed mandates change in
institutional mechanisms as well as updation in technology. The Sustainable
Development Goals, 2030 (SDGs) of the United Nations targets the implementation
of safe and drinking water for all by 2030. Moreover, the National Water Policy
(2012) lays down importance of tackling flood and drought through both structural as
well as non-structural measures. It is under these circumstances the relevance of
Irrigation Department particularly the role of IDRB comes into play.
The Kerala Irrigation department investigates, designs, construct, operate and
maintain, Minor, Medium and Major Irrigation Projects, Flood control works on river
banks, coastal protection works, inland navigation works, hydrological information
system collection, drainage works, salinity extrusion and land reclamation works,
engineering research, coastal engineering, field studies etc., in the state based on
suitable budget provisions. The design of major structures related to these
construction activities under Irrigation department are carried out by the IDRB.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 2
Monitoring the health status of dams under Irrigation department is another
major activity under IDRB. This organisation plays a major role in ensuring that the
dams and reservoirs under Irrigation department are designed and operated in the
most effective and sustainable way, and that they are safe during their entire
lifespan, from construction to decommissioning. After facing 2018 and 2019 floods,
the potential for dam safety incidents, possibly resulting in an uncontrolled or
catastrophic release of stored water has become one of the biggest concerns of our
state. The recent floods have also highlighted the need for implementation of a Flood
Forecasting and Early Warning System integrated with Reservoir Operations (a
major challenge considering the peculiar topography of the State wherein lead time
for any warning system is significantly less). All these in turn require access to
detailed systematic information on real time hydro-meteorological and reservoir data
and its scientific analysis/ processing. Hence, it is in this context that the activities
under Irrigation Design and Research Board require critical evaluation and highlight
the need to develop a definite strategy towards performance betterment.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 3
2. ROLE, RESPONSIBILITIES AND FUNCTIONS OF IDRB
The Irrigation Design and Research Board (IDRB), headquartered at Vikas
Bhavan, Thiruvananthapuram is the Central Design and Research Organization of
Irrigation Department, Government of Kerala. The organisation is headed by the
Chief Engineer (Investigation and Design) and the functional domains include
Design, Research, Dam Safety, Quality Control, Coastal Erosion Studies,
Hydrological studies and Investigation works. This organisation of the Irrigation
department is specialised in the design of structures such as Dams and its
Appurtenances, Canals, Regulators, Salt Water Extrusion barriers, Barrages, Check
Dams, Vented Cross Bars, Cross Drainage works, Boat Terminals, Navigational
Locks etc. The organisation also facilitates investigation & preparation of DPR of the
major and medium irrigation projects. The works related to dam safety, the collection
and assimilation of hydrological data are some of the other focus areas of IDRB.
Kerala Engineering Research Institute (KERI) Peechi, a sub-unit of IDRB is engaged
in Research activities and Quality control. Field Studies Circle (FSC) Thrissur,
another subunit of IDRB, is engaged in the hydrological and meteorological
collection of data and Coastal Zone Management. IDRB also oversees two major
World Bank Funded projects viz. Dam Rehabilitation Improvement Project (DRIP)
and National Hydrology Project (NHP). IDRB regularly imparts technical training to
staff of the Irrigation department on various topics related to Water Management by
its own as well as through collaboration with various other agencies. The
organization continuously strives in pursuit of excellence in the field of quality design
and innovative research for water resources management of the State. IDRB is on
the endeavour to modernize its activities, keeping pace with latest developments in
the field of Information Technology by introducing e-office, online monitoring of
dams, online submission of design indents, online design drawings, development of
Water Resources Information System (WRIS), technical discussions through blogs
etc.
The Location of dams and barrages, river gauge stations, rain gauge stations
etc under Irrigation department are given in Figure 2.1 to Figure 2.5.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 4
Figure 2.1: Location of Dams and Barrages under Irrigation Department
Irrigation Design and Research Board, Kerala
Performance Progression Policies 5
Figure 2.2: Hydro-met Network under IDRB (River Gauge Stations- 90 nos.)
Irrigation Design and Research Board, Kerala
Performance Progression Policies 6
Figure 2.3: Hydro-met Network under IDRB (Rain Gauge Stations- 163 nos.)
Irrigation Design and Research Board, Kerala
Performance Progression Policies 7
Figure 2.4: Hydro-met Network under IDRB (Tidal Stations- 32 nos.)
Irrigation Design and Research Board, Kerala
Performance Progression Policies 8
Dams and Appurtenances Regulators
Barrages Navigation Locks
Check dam Vented Cross Bar
Boat Terminals Canal System
Figure 2.5: Various types of structures for which design consultancy services is
provided by IDRB
Irrigation Design and Research Board, Kerala
Performance Progression Policies 9
2.1 Vision
Towards a dynamic centre, striving continuously in pursuit of excellence in
the field of quality design and innovative research for water resources
management of the State
2.2 Mission
To enhance the capabilities of the State for Water Conservation, Planning
and Sustainable Irrigation Management and also to tackle the fury of
Climate-Induced Disasters to a reasonable degree.
To offer best design solutions that are environmentally friendly,
operationally efficient, long term sustainable and economically viable to
Government and Semi Government organisations inside the state of
Kerala within the least possible delivery time.
Improve the condition and safety of dams under Irrigation department
through State and Central Dam Safety programs/schemes and foster a
unified dam safety community
To keep abreast with the latest developments and enhance the capabilities
of the State in Integrated Water Resources Management to build resilience
to climate-induced disasters through Flood and Drought forecasts
integrated with Reservoir Operations.
To facilitate in conduct of proper investigation for major projects under the
Irrigation Department considering both financial implication and technical
feasibility
2.3 Goals
2.3.1 Design
To be positioned as the first port of call for any design requirements in
irrigation structures, coastal protection and flood control for any entity
within the state of Kerala.
To acquire and retain skills sets that can provide best designs to our
clients and to adopt best practices that will enable efficient delivery of the
projects in the least possible time
Irrigation Design and Research Board, Kerala
Performance Progression Policies 10
To create an environment of continuous improvement through investing in
cutting edge tools, trainings and Research and Development (R&D)
To create benchmarks to measure efficiency and quality of delivery of
design solutions that are at par with global standards with the assistance
from a Permanent Technical Committee.
To create additional revenue to the department by offering design
consultancy services to other Government and Semi Government
organisations.
2.3.2 Dam Safety
To direct, coordinate and develop policies and technical standards in the
area of dam safety for the Department.
Sustainable development, upgrading the existing basic dam safety
facilities maintenance of quality and efficient dam management of Dams/
Barrages to match with the new modern innovative technique
Increase public awareness of the role of dams in society, the risks that
they present and the importance of both dam safety and preparedness for
dam failures to Improve Safety and Operational performance of dams.
Institutional Strengthening and Capacity building in Dam Safety
and Instrumentation of Dams.
Promote innovative approaches to receive funding from external agencies
viz. World Bank for dam rehabilitation.
Initiate proposals for government programs to improve the safety of dams
and the public living in the downstream
Ensure effective collection and management of asset and health data
for all dams and barrages
Support and strengthen a co-ordinated effort between field offices and
monitoring offices to improve the safety of dams
2.3.3 Hydrology
To ensure Real Time Hydro-meteorological Data Availability
To develop a Comprehensive Water Resources Database and Decision
Support System
Irrigation Design and Research Board, Kerala
Performance Progression Policies 11
To develop Flood Forecasting and Early Warning System integrated with
Reservoir Operations
2.3.4 Investigation
To implement projects in the state in a technically feasible way after proper
investigation so as to ensure structural stability, minimize expenditure and
avoid unnecessary delays.
To minimize the Wrong choice of site or designs based on incorrect or
insufficient data can result in considerable avoidable expenditure and
delays.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 12
3. THE TEAM IDRB
The Chief Engineer (Investigation & Design) is the Chairman cum Secretary of
the Irrigation Design and Research Board. Other members of the board include all
Chief Engineers in the Irrigation Department, Executive Director, Centre for Water
Resources Development and Management, Director, Centre for Earth Science
Studies, Additional Secretary to Government (Finance Department), Two prominent
engineers not in service with extensive field experience in Irrigation (not below the
rank of Chief Engineer), Joint Secretary to Government (Irrigation). The Design,
Research, Quality Control, Coastal Erosion Studies, Dam Safety, Hydrological
studies and Investigation wings of the Irrigation Department are under the control of
the Chief Engineer (Investigation and Design), IDRB.
3.1 Chief Engineer, IDRB
The Irrigation Design and Research Board is headed by the Chief Engineer
(Investigation and Design). The Chief Engineer is also the Member Secretary of
Kerala Dam Safety Authority (KDSA) and the Chairman of the State Dam Safety
Organisation. Other members of State DSO are Chief Engineer (Projects-I), Chief
Engineer (Projects-II), Chief Engineer (Mechanical), Director (IDRB) and Joint
Director (Dam Safety) (Convenor).
Chief Engineer (Investigation and Design) is assisted by three Superintending
Engineers and they are designated as:
Director (Irrigation Design and Research Board)
Director (Kerala Engineering Research Institute) and
Superintending Engineer (Field Studies Circle)
Irrigation Design and Research Board, Kerala
Performance Progression Policies 13
3.2 Director (IDRB)
The Director (IDRB) assists the Chief Engineer (I&D) in all technical activities.
The Director (IDRB) is one of the members of the State Dam Safety Organisation.
There are five divisions under Director (IDRB) each headed by a Joint Director.
3.3 Joint Director (Canals) & Joint Director (Dams)
The designs of all major projects under the Irrigation Department, Government
of Kerala are carried out by the two design divisions of IDRB i.e. Canals and Dams.
Design of structures are done based on the hydraulic particulars, soil investigation
report and other mandated data furnished as per the Design Indent for each
structure published in the website. These wings also undertake design consultancy
works for other departments/ semi-government/ private firms upon request. Other
important functions of design wing include assessing the stability of existing dams
Irrigation Design and Research Board, Kerala
Performance Progression Policies 14
and providing technical expertise for the rehabilitation of dams under DRIP,
inspecting existing hydraulic structures and recommending suitable rectification
works etc.
Canals Division designs structures such as canals, regulators, checkdams,
vented cross bars, cross drainage works, boat terminals, navigational locks,
buildings etc whereas Dams Division designs structures such as dams,
appurtenances, regulators, salt water extrusion barriers, barrages, navigational
locks, buildings etc.
Joint Director (Canals) is assisted by 4 Deputy Directors and 9 Assistant
Directors & Joint Director (Dams) is assisted by 3 Deputy Directors and 7 Assistant
Directors.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 15
Some of the prestigious projects recently done by the Design wing under IDRB
includes the design of Thanneermukkam Bund, Pattissery dam, Preliminary design
of Attappady Valley Irrigation Project (Preliminary design) etc.
Figure 3.1: Thaneermukkom bund
Figure 3.2: Pattissery Dam- Construction in progress
3.4 Joint Director (Dam Safety)
Dam Safety wing under IDRB is the point of contact with the Dam Safety
Organisation of Central Water Commission. The Dam Safety Wing functions as the
State Project Management Unit (SPMU) for Dam Rehabilitation and Improvement
Project (DRIP) funded by World Bank. The Dam Safety wing also assists the Dam
Safety Organisation of the State headed by Chief Engineer, IDRB as Chairman and
Chief Engineer (Projects-I), Chief Engineer (Projects-II), Chief Engineer
Irrigation Design and Research Board, Kerala
Performance Progression Policies 16
(Mechanical), Director (IDRB) as Members and Joint Director (Dam Safety) as
Member & Convener. Other important functions of the Dam safety wing are:
Pre-monsoon and Post-monsoon inspections of dams by Dam Safety
Organisation
Verification of Quarterly Inspection Report of dams submitted by Dam
Engineers
Preparation of Health Status report of Dams.
Updating data in Dam Health and Rehabilitation Monitoring Application
(DHARMA) portal maintained by Central Water Commission
Preparation of Emergency Action Plans and Operation and Maintenance
Manual of Dams
Consolidation of Water Levels in reservoirs and reporting the same to the
Government and State Disaster Management Authority (SDMA).
Hydrological review to check the adequacy of the design flood.
Interaction with Central Dam Safety Organisation of Central Water
Commission.
Organising Training Programs related to Dam Safety.
Joint Director (Dam Safety) is assisted by 2 Deputy Directors and 6 Assistant
Directors.
3.5 Joint Director (Hydrology and Investigation)
The Hydrology Wing of IDRB, being one of the core components of the
department, is responsible for collection, validation and distribution of all the water-
Irrigation Design and Research Board, Kerala
Performance Progression Policies 17
related historic and real-time data of the water resources of the State. For this, a
number of gauging stations have been installed in the rivers of the State. All the field
data, which are validated by the offices concerned, are compiled by the
Superintending Engineer, Field Studies Circle, Thrissur along with field execution.
The important functions of the Hydrology wing are:
Collection, tabulation and processing of daily reservoir level and storage
volumes from the various completed irrigation projects.
Flood discharge assessment of Irrigation structures, Peak flood estimation
and Water Balance studies of river basins.
Preparation of comments related to State Water Policy, National Water
Policy.
Preparation of State-Specific Action Plan under National Water Mission
Implementation of the National Hydrology Project
Publication of Surface Water Year Book for each year incorporating river
gauge and rain gauge data in four volumes
With regard to investigation, all major projects under the Irrigation Department,
Government of Kerala are carried out with the concurrence of Investigation wing of
IDRB. The important functions of the investigation wing are:
Empanelling of Contractors/Consultants for taking up Investigation works
To guarantee that every work is properly investigated and all relevant data
are collected and correlated before finalizing the design and estimate for
the work. Wrong choice of site or designs based on incorrect or insufficient
data can result in considerable avoidable expenditure and delays.
To ensure that the financial implication of each proposal is looked into and
the most economical one is finally recommended without sacrificing the
technical feasibility.
To ensure that the benchmarks and survey reference points shall be
carefully selected and properly established so that there is no likelihood of
these being missed when the work is taken up for execution and that, the
benchmarks are connected to the nearest permanent Mean Sea Level (M.
S. L.) Bench Mark.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 18
Vetting of investigation reports submitted by field officers and to scrutinize
whether it is in accordance with the provisions contained in the relevant
codes and practices
Vetting of Prefeasibility/ Feasibility Report/DPR of Water resources
schemes, submitted by subordinate offices before submission to
Government
Joint Director (Hydrology & Investigation) is assisted by 2 Deputy Directors
(Hydrology), 1 Assistant Executive Engineer, 4 Assistant Directors and 2 Assistant
Engineers.
3.6 Joint Director (Design Manual)
The etymology of this division is different from the works being carried out. The
Design manual wing deals with the preparation of Annual Plan proposals and
Modernization proposals for onward submission to Planning Board. Works related to
the technical matters for the activities under Kerala Engineering Research Institute
(KERI), Peechi Irrigation Project and Coastal Engineering Field Studies (CEFS)
Division, Thrissur are also dealt by this wing. Maintenance of Library in IDRB and its
administration is also under the control of this division.
The other important functions of the design manual wing are
Scrutinizing documents for Pre-qualification Committee meeting.
Formulating periodic proposals for the modernization and upgradation of
computer facilities
Works related to the implementation of e-office in IDRB.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 19
Works related to IT & Website updation for IDRB (New Website being
managed by Hydrology Division)
Activities related to Right to Information Act and Right to Service Act.
Answering to the Legislative Assembly Interpellation, Parliament
questions, L. A. Assurance.
Joint Director (Design Manual) is assisted by 2 Deputy Directors and 6 Assistant
Directors.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 20
The organogram of the staff in the headquarters of Irrigation Design and Research
Board is shown below:
Irrigation Design and Research Board, Kerala
Performance Progression Policies 21
3.7 Other facilities
3.7.1 GIS Lab
Irrigation Design and Research board has a full-fledged Geographic Information
System (GIS) lab in the headquarters. This lab is equipped with Arc GIS, Surface
Water Data Entry system (SWDES), Intergraph (Photogrammetric suit) software. The
GIS lab is being run on contract basis and consists of a Data Analyst, a Senior GIS
Technician, a Junior GIS Technician and an Accountant. The expenditure towards
these consultancy services is met from the National Hydrology Project. Major
activities related to NHP under GIS lab are:
1. Provide technical contributions to integration of data collection, analysis and
results
2. Conduct data collection and analysis to support systematic monitoring and
reporting
3. Ensure that data collection, analysis and results communication are
systematically integrated
4. Coordinate with all Hydrology offices to validate the quality of data collected
from the field
5. Preparation of submission reports (daily/weekly/biweekly/monthly)
6. Provide training to officials of hydrology wing in data analysis.
Apart from these, this wing also renders services to other wings under IDRB/
offices under Irrigation department in preparing necessary maps for various projects,
canal mapping, determination of terrain slope for flood discharge calculation, storage
calculation.
3.7.2 Library
IDRB has a well-established library with good collection of technical books,
journals, periodicals, publications, conference proceedings, project reports etc.
Library is currently in the process of digitising library catalogues and library register.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 22
3.8 Team Vision (Division-Wise)
Design
To provide the highest quality, most dependable and economical creative
solutions to improve the irrigation, coastal protection and flood control
infrastructure of Kerala and transforming into a state-of-the-art excellence
centre in Irrigation Design.
Dam safety
A future in which the public safety, economic strength, environment and
security of the State are not threatened by the risk from dam failure, by
ensuring that dams are structurally, seismically and hydrologically safe.
Hydrology
To be recognized as an innovative and distinguished centre focused on
quality hydro-meteorological research to establish an effective Water
Database for effective decision making resulting in Sustainable Water
Resources development of the State.
Investigation
To ensure that every proposal shall be properly investigated and all
relevant data collected and correlated before finalizing the design and
estimate thus enabling the executing agency to reduce time-lag thereby
ensuring timely completion of work.
3.9 Goals and Timeframe
Team Goals Time frame
Dams &
Canals
Formation of a Permanent Technical Committee
subjected to orders from Government 1 Month
Development of a design studio with latest
versions of the relevant design and drafting
software and completion of training
6 Months
Irrigation Design and Research Board, Kerala
Performance Progression Policies 23
Digital design library for the safe custody of
design and drawings for future reference 1 Year
Consultancy services to external agencies 1 Year
Revision of Design Manual for Design of
Irrigation Structures 1 Year
Dam safety
Ensuring Hydrologic Safety of Major
dams/barrages by conducting design flood
review
6 Months
Calculating Revised MWLs and checking
freeboard as per IS provisions using latest area
capacity curve and tail water rating curve.
(subjected to availability of field data from the
Chief Engineer concerned)
1 Year
Carrying out stability analysis using site specific
seismic parameters and considering revised
MWL and tail water, in association with Design
Wing , IDRB (subjected to availability of field
data from the Chief Engineer concerned)
8 Months
Instrumentation of dams under DRIP 6 Months
Providing surveillance system for all dams and
central control system under DRIP 1 Year
Incidental Revenue generation for sustainable
operation and maintenance of dams under
DRIP (Policy decision required from Govt)
2 Years
Hydrology
and
Investigation
Ensuring Real Time Hydro-meteorological data
availability by establishing Real Time Data
Acquisition System
6 Months
Development of Kerala Water Resources
Information System (Kerala-WRIS)
Phase I: January 2021
Phase II: January 2022
Flood Forecasting and Early Warning System
integrated with Reservoir Operations (Pilot January 2022
Irrigation Design and Research Board, Kerala
Performance Progression Policies 24
Investigation
In the Investigation Division, goals are fixed in a case to case basis and
timeframe is fixed accordingly as IDRB’s roles are limited in issuing Financial
Sanction to various proposals to be executed by other Chief Engineers. However,
when major projects are undertaken by the department, IDRB facilitates the same.
Some of the works undertaken are:
Attappady Irrigation Project
The work of Environment Impact Assessment study (EIA) has been awarded to
M/s Mantec Consultants Pvt. Ltd. The firm had completed third season baseline
study and also submitted draft EIA report. The revised DPR of Attappady Irrigation
Project has been submitted through ePAMS software of CWC on 16/09/2020 for
approval. Investigation division of the IDRB is only involved in assisting and
supporting with available data in implementation of the above project which is under
the purview of Chief Engineer Projects I.
New Mullaperiyar Dam
Construction of new dam to replace existing Mullaperiyar dam, requires
statutory clearances from MoEFCC including the clearance from the Hon. Supreme
Court. MoEF& CC has approved the ToR for EIA study conditionally. EIA study is
progressing through M/S Pragathi Lab & Consultants and also revised DPR is under
Preparation. Again, Investigation division of the IDRB is only involved in assisting
project for Periyar Basin)
Design
Manual
Implementation of e-office in IDRB 1 Year
Upgradation of IDRB Library 1 Year
Implement facility to record and webcast
trainings and seminars conducted in IDRB
Conference hall to all engineers under
department.
1 Year
Irrigation Design and Research Board, Kerala
Performance Progression Policies 25
and supporting with available data in implementation of the above project which is
under the purview of Chief Engineer, Irrigation & Administration.
Bench marking of Irrigation Projects
For the financial year 2020-21 an amount of Rs. 50 Lakh is the budget
provision for benchmarking of Irrigation Systems under the head of account 4701-80-
800-81 (Benchmarking of Irrigation schemes). Though no action was taken during
previous financial years, necessary steps have been taken to carry out the study as
per the mandated guidelines jointly with CWRDM. Peechi and Malampuzha projects
are proposed to be taken. Terms of references have been exchanged. An MoU in
this regard is expected to be entered within 2 weeks.
3.10 Project- Year wise details
Detailed in Section 5.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 26
4. HISTORY EVOLUTION AND CURRENT STATUS OF IDRB
The Irrigation Design and Research Board, Kerala was formed in the year 1986
vide GO (Ms). No 24/86/Irrgn dated 14/08/86 and subsequently started functioning
under the Chief Engineer IDRB vide G.O. (MS) No. 7/1987/Irrgn. dated 24/03/1987.
The quorum of the board was seven with Chief Engineer (Design and Research) as
the Chairman-cum-Secretary. Other members at the time of formation included all
Chief Engineers in the Irrigation Department, Executive Director, Centre for Water
Resources Development and Management, Director, Centre for Earth Science
Studies, Additional Secretary to Government (Finance Department), Two prominent
engineers not in service with extensive field experience in Irrigation (not below the
rank of Chief Engineer), Joint Secretary to Government (Irrigation). At the time of
formation, there were three Joint Directors under Director (Design) i.e., Joint Director
(Designs), Joint Director (Dam Safety), Joint Director (Investigation and Planning).
At present, there are five Joint directors - Joint Director (Canals), Joint Director
(Dams), Joint Director (Dam Safety), Joint Director (Design Manual) and Joint
Director (Hydrology and Investigation).
4.1 Details of Completed Projects
The detailed lists of completed projects are included in Appendix I
4.2 Details of Ongoing Projects (2020-21)
The detailed lists of ongoing projects (including spill over works) are included in
Appendix II
Irrigation Design and Research Board, Kerala
Performance Progression Policies 27
5. DETAILS OF CATEGORY-WISE PROJECTS
5.1 Plan Funds 2020-2021
The various plan schemes under IDRB are detailed below
5.1.1 Modernization of Hydrology Information System (2701-80-005-92)
Objectives:
In order to have a realistic assessment of water resources of Kerala, IDRB is in
the process of modernizing existing Hydrology Information System with Real Time
Data Acquisition System (RTDAS), which include Hydro Meteorological data
collection, Procurement of equipments and Trainings etc.
The scheme envisages Hydro Meteorological data collection from gauging
stations, established across Kerala River Basins, works related to maintenance of
existing gauging stations and establishing new stations if found necessary,
Procurement of equipments for data collection, maintenance of infrastructure
facilities for data validation, dissemination and publication of documents, studies for
Integrated River Basin Management, Capacity Building Programs such as in-house
trainings and workshops etc.
Establishing Flood Early Warning System (FEWS) under Modernization of Hydrology
Information System:
IDRB has proposed to develop ‘Real Time Operation of Reservoirs integrated
with Flood Forecasting and Warning System for Periyar basin’ utilizing the available
allocation of Rs 225 Lakhs under World Bank funded National Hydrology Project and
the proposal is currently in tendering stage. However, for receiving an accurate
forecast and issuing a fairly good warning, real time information of the upstream
rainfall and discharge through the stream is inevitable so as to ensure streamlining of
emergency response and crisis management strategies. But the accuracy of the
forecasts mainly depends up on the real time hydro-met data received and quality of
topographical features preserved, which strengthens the need for establishing more
number of Real Time Hydro-Met stations and availability of high resolution (1m to
5m) DEMs. Nevertheless, for the procurement of these state-of-the–art technologies,
sufficient funds are not available under NHP. Hence, action has been taken to
Irrigation Design and Research Board, Kerala
Performance Progression Policies 28
procure DEM of 1m resolution the same of which has been cleared by Working
group. Discussions are being made with National Remote Sensing Centre (NRSC),
Hyderabad.
5.1.2 Modernization of Design Wing (2701-80- 005-93)
Objectives:
The scheme mainly envisages the physical infrastructure upgradation of IDRB
and its sub-ordinate offices. The physical infrastructure plays a pivotal role in
creating a conducive atmosphere for designs to be made and submitted within the
most appropriate time limit. As part of modernization, Software development which
shall include both design and CAD drawings, upgradation of technical library,
enhancing internet connectivity for implementation of e-office and online design
indent submissions, invitation for consultancy services for design upgradation as per
latest cutting-edge technology and its ensuing training programs are proposed.
The scheme also envisages the modernization of Quality Control Wing/labs
under the Irrigation Department. Quality Control wing of the department checks the
quality of works undertaken by various execution divisions of the Department across
the state. Hence, purchase of modern equipments for material testing labs in quality
control wing is proposed which will bridge the gap for being full-fledged laboratories.
Since the works are spread across the State and that there is no shortage in
department vehicles, the scheme shall also be used for hiring of vehicles. This will
also help to conduct surprise inspections as and when needed.
5.1.3 Dam safety Organization and Dam Safety Measures (2701-80-800-92) (Site
Visit &Training)
Objectives:
This scheme envisages meeting expenses towards inspection of dams for the pre
and post monsoon periods, exposure and technical visits to various dam sites across
the country and for conducting and attending training programs/webinars etc.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 29
5.1.4 Mullaperiyar Project - Dam and appurtenant works (4700-29-800-97)
Objectives:
Government of Kerala has decided to construct a new dam in the place of
century old Mullaperiyar dam based on the detailed study conducted about the
security of existing dam.
The Ministry of Environment Forest and Climatic Change (MOEF&CC) has
approved Terms of Reference (ToR) for Environment Impact Assessment (EIA)
study for the New Mullaperiyar dam conditionally on 14.11.2018. EIA study is being
under progress through Pragathi Lab & Consultants. Since the earlier DPR was
prepared in 2011, the same needs to be revised. As approved DPR is necessary for
EIA, action has been taken to revise the DPR prepared earlier.
5.1.5 Investigation of Irrigation Schemes (4700-80-005-99-02-V)
Objectives:
The main objective of this scheme is to conduct investigation works for minor
and major structures proposed to be undertaken across the State under the
jurisdiction of all the Chief Engineers of Irrigation Department. The scheme shall also
be used to carry out investigation works for study and research purposes. The major
works involves works like Soil investigation works, De-siltation study of dams,
Sedimentation study of various reservoirs etc. These Studies give critical data for
maintaining major irrigation structures and investigations for construction of new
structures. Since more number of multi-purpose water storage structures are needed
to cater the rising demands of drinking water, irrigation and flushing of salinity, the
scheme also envisages investigation of new irrigation projects, preparation of project
reports and also for revision of project reports of all projects under Irrigation
Department.
5.1.6 Dam safety Organization and Dam Safety Measures (4700-80-800-97)
Objectives:
The funds are to be utilized for urgent maintenance works of 16 dams and 4
barrages under Irrigation department and for the safety works recommended by Dam
Irrigation Design and Research Board, Kerala
Performance Progression Policies 30
Safety Organization and Kerala Dam Safety Authority (KDSA) during their
inspections. Funds are allotted as per the priority of maintenance works which
include Civil, Mechanical and Electrical component. All works except for those under
Peechi dam are being executed through Executive Engineers under Chief
Engineers, Projects-I, Projects-II and Mechanical.
5.1.7 Bench marking of Irrigation Systems (4701-80-800-81)
Objectives:
Benchmarking is a management tool helping in the evaluation of an individual
irrigation system and suggesting methods to improve the system. It is used to
compare the processes with the best practice and to adopt suitable ones. In the
irrigation system, this would improve the efficiency of the system and result in
savings in water usage. Bench marking for effective irrigation management is
introduced with the objective of identifying the best management practices,
prioritizing and evaluating rehabilitation and re-modelling of projects with an objective
to improve irrigation efficiency. For benchmarking exercise, key performance
indicators would be derived. Benchmarking the irrigation systems in Kerala would go
a long way in increasing the efficiency of the system. Interventions for repairs
rectifications and improvements would be prioritized based on the report of the
benchmarking exercise. It is intended to bring all the completed irrigation projects
under benchmarking process in a phased manner. It is proposed to take Peechi and
Malampuzha projects for the study jointly with CWRDM.
5.1.8 Formation of River Basin Organization (4701-80-800-88 -00-00)
Objectives:
The scheme envisages basin wise development of rivers across the State. The
work includes demarcation of rivers, taking longitudinal and cross sections of rivers
based on needs, river protection works, assessing carrying capacity, works related to
pollution abatement in rivers. Since catchment area treatment forms an integral part
of rejuvenation of river, it is proposed to take up rectification of streams, ponds which
contribute significantly to maintain the flows during lean seasons. It is proposed to
take up data collection of coastal areas and its connected activities under this
Irrigation Design and Research Board, Kerala
Performance Progression Policies 31
scheme. The data collection includes conducting field studies and collection of data
on coastal erosion for the year 2021-22.
5.1.9 Post Facto Evaluation Study (PFES) (4701-80-800-96)
Objectives:
The scheme envisages conduct of Post Facto Evaluation Study of all
completed major and medium irrigation Projects. Through the study, the socio-
economic background of the beneficiaries and benefits from the irrigation projects
under study will be analysed in detail. The study outlays the suggestions from the
cultivator’s point of view on the major renovations and modifications for the existing
canal network of the project. The study provides an insight into the defects of the
irrigation projects as well as suggestions for improvements. Pothundy and
Chalakkudy Irrigation projects are selected for Post Facto Evaluation Study during
the Financial Year 2021-22.
5.1.10 Kerala Engineering Research Institute (KERI), Peechi Development
stage -II (4701-80-800-00-34-03)
Objectives:
The Kerala Engineering Research Institute (KERI), Peechi was formed in the
year 1960. It is the only research institute under Water Resources Department for
conducting research activities on project design and Irrigation systems. The KERI,
Peechi in mostly involved with routine testing, investigation and consulting work
However, for the past years, research works are at minimal. The institute needs to
keep up with the changing technologies in the field of civil engineering which is
mainly concentrated to field tests and its analysis. Hence, the proposal involves
development focusing on procurement and upgradation of equipment’s that are
needed for investigation and testing of construction materials. The works being
carried out under KERI are investigation and study works including Soil investigation
works for the proposed irrigation/water storage structures, fundamental studies on
seismic refraction survey for subsurface profile investigation, seismic tomography
study on Dams, sedimentation study of various reservoirs etc. The scheme also
envisages rectifying its existing facilities so as to continue works being done
previously ie., improvements to rating tank so as to calibrate current meters.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 32
Hence, the overall objective is improvement of the infrastructure of the labs there by
establishing smooth and efficient functioning of all the labs which shall enhance the
capacity of study and research works in water sector. Increase in revenue generation
through testing of materials is also envisaged.
5.2 Externally aided projects
5.2.1 Dam Rehabilitation and Improvement Project (4701-80-800-77)
Objectives:
A large number of dams have been built over the years for the development of
water resources for irrigation, water supply power generation and other benefits.
Many of these dams are in urgent need of strengthening and rehabilitation to ensure
their safety and to improve their performance. Dam Rehabilitation and Improvement
Project (DRIP) is a World Bank Aided Project with the objective to improve the safety
and operational performance of selected dams and associated appurtenances. As
such, major works for the selected dams under Irrigation Department have been
undertaken under this scheme.
DRIP Phase I
The project is to improve the safety and operational performance of selected
dams and associated appurtenances which include civil, mechanical and electrical
works. The project has become effective from 18.04.2012. It has three components
viz. 1) Dam Rehabilitation works 2) Institutional Strengthening 3) Project
Management. Rehabilitation of 16 dams have been undertaken under DRIP Phase-I.
(Malampuzha, Neyyar, Peechi, Walayar, Kuttiyadi, Kanjirapuzha, Chimoni,
Malankara, Kallada, Pothundy, Vazhani, Meenkara, Chulliyar, Pazhassi barrage,
Bhoothathankettu barrage and Moolathara regulator).
World Bank has revised the project cost for DRIP phase I to Rs 327
crores, after surrendering the unutilized amount of Rs 33Cr for avoiding
commitment charges for the unspent amount.
The funding pattern of 80:20 (80% World Bank loan and 20% State share)
for the initial allotment of Rs 202 Crores has been revised to 70:30 for
additional financing of Rs158 Crores.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 33
Original DRIP has been closed in June 2020 and Additional Financing has
been extended by additional 9 months i.e. up to March 2021, to facilitate
implementing agencies to complete the remaining works which are
affected due to lock down period owing to COVID 19.
DRIP Phase II
Considering the success and achievements in DRIP, Government of India has
initiated next phases, DRIP Phase II and Phase III of the project with World Bank
support. The duration of Project is ten years, to be implemented in two Phases, each
of six years duration with two years overlapping. The funding pattern is 70:30 (70%
World Bank loan and 30% State share).
The project will include the following components
1. Rehabilitation and Improvement of Dams and Associated Appurtenances
2. Dam Safety Institutional Strengthening
3. Risk-informed Asset Management and Innovative Financing for Sustainable
Operation and Maintenance of Dams
4. Project Management
5. Contingent Emergency Response Component (“CERC”)
Kerala Water Resources Department (KWRD) has obtained in principle
approval for DRIP Phase II & III for Rs 165.9 crores which include rehabilitation of 16
dams/barrages viz Malampuzha, Neyyar, Walayar, Kuttiyadi, Kanjirapuzha, Chimoni,
Malankara, Kallada, Pothundy, Meenkara, Chulliyar, Pazhassi, Bhoothathnkettu
barrage Pampa, Karapuzha and Mangalam. State of Kerala has met the 30% Project
Readiness Criteria to participate in the Loan Negotiation with World Bank and
accordingly participated in the negotiation meeting held on 10/11/2020. Government
has accorded Administrative Sanction for an amount of 24000 Lakhs and has
allocated the same head of account of DRIP Phase I for DRIP Phase II.
Plan progress of IDRB during 2019- 20 and 2020-21 (as on October 2020) is shown
in Figure 5.1 and Figure 5.2. Proposed outlay for various head of account for the
Financial Year 2021-22 is given in Table 5.1.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 34
Figure 5.1: Plan Progress of IDRB: 2019-20
Figure 5.2: Plan Progress of IDRB: 2020-21 (as on October 2020)
Irrigation Design and Research Board, Kerala
Performance Progression Policies 35
Table 5.1: Proposed Outlay for 2021-22
Sl No. Head of Account Proposed Outlay
(in Lakhs)
1 2701-80-005-92-00-00-00-P-V Modernisation of Hydrology Information System
200
2 2701-80-005-93-00-00-00-P-V Modernisation of Design Wing
200
3 2701-80-800-92-00-00-00-P-V Dam Safety Organisation & Dam Safety Measures
15
4 4700-29-800-97-00-00-00-PV Dam and Appurtenant works – Mullaperiyar Project
200
5 4700-80-005-99-02-00-00-P-V Investigation of Irrigation Schemes - Works
250
6 4700-80-800-97-02-00-00-P-V Dam Safety Organisation & Dam Safety Measures - Works
250
7 4701-80-800-81-00-00-00-P-V Bench Marking of Irrigation System
50
8 4701-80-800-88-00-00-00-P-V Formation of River Basin Organization
150
9 4701-80-800-96-00-00-00-P-V Post Facto Evaluation Studies
5
10 4701-80-800-99-00-34-03 Development of Kerala Engineering Research Institute - Stage II
250
11 4701-80-800-77-00-00-00-P-V Dam Rehabilitation and Improvement Project (DRIP)
6500
TOTAL 8070
The details of works under plan schemes are included as Appendix III
Irrigation Design and Research Board, Kerala
Performance Progression Policies 36
5.3 National Hydrology Project
National Hydrology Project (NHP) is a 100% Central Sector Scheme
implemented in the state by Ministry of Water Resources, River Development &
Ganga Rejuvenation (MoWR, RD & GR) with World Bank assistance. The project
period is 8 years. The project objectives are to improve the extent, quality and
accessibility of water resources information, and to strengthen the capacity of
water resources management institutions in India.
Major Activities conducted/going on
Establishment of Real Time Data Acquisition System (RTDAS). 99 nos of
Tipping Bucket Rain Gauges (TBRGs), 56 nos of Radar Level Sensors (RLSs)
and 13 nos of Automatic Weather Stations (AWSs) are proposed under this
work.
Preparation of detailed project report for Rejuvenation of five rivers namely,
Meenachil, Periyar, Pamba, Kallayi & Valapattanam.
Development of Real Time Operation of Reservoirs integrated with Flood
Forecasting and Early Warning System for Periyar basin in the State of Kerala
under National Hydrology Project.
Development of Kerala Water Resources Information System (Kerala-WRIS),
a web enabled platform for integration of all data related to water and its allied
sectors which otherwise is scattered amongst various departments.
Establishment of Integrated Command and Control Centre (ICCC) for
bringing the set of aforesaid specialised tasks like Flood Early Warning
Systems, Integrated Reservoir Operations Management, Development of
Master plans for river basins and its Integrated Water Resources
Management etc under one roof, by incorporating cutting edge technology,
National and International water experts and the talents within the department
to cater optimum policy decision support in an effective manner.
Purpose Driven Studies: Two studies progressing with CWRDM as
Consultant
o Study on Saline Ingression in Kadalundi, Anjarakkandi and Pallikkal rivers
o Assessment of water quality in Thrissur Corporation.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 37
5.4 Rebuild Kerala Initiative (RKI) Projects
The detailed list is included as Appendix IV
5.5 Kerala Irrigation Infrastructure Fund Board (KIIFB) Projects
The detailed list is included as Appendix V
5.6 State Disaster Response Fund (SDRF)
The detailed list is included as Appendix VI
Irrigation Design and Research Board, Kerala
Performance Progression Policies 38
6. COLLABORATION WITH OTHER INSTITUTIONS
6.1 Academic Institutions
Present Scenario:
Usually, officers avail the opportunities for training from reputed technical
institutions like NITs, IITs, NWA, NIOT etc only when a nomination is requested by
these institutions as per their training calendar. Technical consultation/ guidance for
solving hurdles faced during the any of the stage of projects are only sought from the
experts in the field from such institutions as and when required.
However, with the launching of DRIP, Central Water Commission (CWC) who is
also the Central Project Management Unit (CPMU) has associated with premier
academic and research institutions in the country like IIT Roorkie, IISc Bangalore,
NIT Calicut, IIT Chennai, College of Engineering, Thiruvananthapuram (CET), to
impart various training programmes to assist with the development of appropriate
skills and modern tools to adequately operate and maintain dams and for enhancing
the capacities in guiding the dam safety activities.
Trainings attended by officers from these premier institutions have helped in
achieving in-house capacity in addressing various technical issues. Design Flood
Review of Dams is an example to be highlighted.
Proposed Activity:
Though significant trainings are being arranged by the various institutes
mentioned above, sufficient trainings are not imparted to officers to develop the
managerial aspects mandated for projects. It is strongly observed the lack of
leadership skills among the officers which have been pointed out by Government
during several occasions.
Considering the above, it is decided that a training programme on leadership
skills and management is to be imparted to the officers. Accordingly, discussions
have been held with Mr. Subin Sudhir, Assistant Professor
(https://iimidr.irins.org/profile/90653), Indian Institute of Management (IIM), Indore for
initiating the same. IIM-I has expressed their willingness in imparting the same. It has
been strongly suggested that physical training at the institute shall be done rather
Irrigation Design and Research Board, Kerala
Performance Progression Policies 39
than through video conferencing. Programmes lasting from 3 to 10 days can be
imparted as per the requirement. It has also been informed that if travel restrictions
owing to COVID-19 is an hurdle, the training can be conducted at Kozhikode i.e., at
IIM-K. Concept note for the same is being prepared. It is expected that training can
be conducted in mid-February 2021.
6.2 Research Institutions
Officers in the design wing are currently availing the training opportunities
offered by the research institutions like from CWPRS, IITs, CWRDM on the subjects
related to design of water retaining structures, design of coastal structures and flood
routing analysis. It is envisaged to use the facilities and expertise available in such
institutions to conduct research works in various fields such as efficiency analysis of
different types of irrigation methods that can be adopted in upcoming major projects.
Initially, discussions have been made with Prof. Albert Thomas
(https://www.civil.iitb.ac.in/~albert/), Assistant Professor, Indian Institute of
Technology (IIT), Bombay to explore the possibilities of collaboration of IDRB with
IIT-B for matters pertaining to Water Resources Management. IIT-B has offered
complete support for any of the initiations. The subjects that need to be taken up with
IIT-B needs to be catalogued before and MoU can be entered.
Discussions have also been made with Smt. Sriramya Duddukuri, Assistant
Professor (https://www.cee.cornell.edu/faculty-directory/sriramya-duddukuri-nair),
Cornell University, USA for the possibility of having significant interactive sessions
(online) so as to understand the various developments in the field of research and
the latest research methodologies that needs to be adopted. She has agreed for the
same subjected to the condition that there are high chances of postponing
committed sessions owing to rigorous research at her current institution. It is also
worth pointing out that IDRB is already in touch with IIT, Chennai, NIT, Calicut and
CET as they are the research partners for DRIP. Since State of Kerala has already
been engaged in the negotiations for DRIP Phase-II, it is expected that
collaborations with these institutes can be continued.
During the present financial year 2020-21, it has been proposed to purchase
Digital Elevation Models (DEM) of resolution 1m so as to enable to predict more
Irrigation Design and Research Board, Kerala
Performance Progression Policies 40
accurate flow patterns on a particular hydrological event. Government has already
accorded sanction to purchase the same. The estimate was arrived as a result of
having numerous discussions by IDRB with National Remote Sensing Centre
(NRSC), Hyderabad. Also, the Space Application Centre (SAC), Indian Space
Research Organisation (ISRO) has offered technical support towards building
Kerala-WRIS in Geospatial and Remote Sensing Data Access and Analysis of
Hydrological Models being developed.
IDRB has also been associated with institutions like CWPRS, Pune, for building
in-house capacity of design of coastal structures since the same at present is being
done through IIT Chennai and CWPRS, Pune. Based on the training to selected
officers of IDRB, a sample design for coastal structure is being prepared and is
expected to be completed soon.
As part of NHP, it has been decided to prepare of Decision Support System
(DSS) for Bharathapuzha Basin. IDRB have had constant interaction with IIT,
Palakkad to whom the work is proposed to be entrusted. The Terms of Reference
initially prepared by IDRB, checked by IIT Palakkad and concurred by National
Project Management Unit (NPMU) i.e., CWC, New Delhi is being negotiated. It is
proposed to enter a MoU with IIT Palakkad soon.
6.3 Research Projects
Real projects of the department may be chosen as research projects by the
officers sent on deputation for higher studies from department. Alternate methods of
analysis and design can be explored and feasible ones can be adopted for practice.
Accordingly, research papers can be published after identifying the faculties having
high index (making them as co-authors).
Opportunities can be given to graduate / post graduate students from reputed
education institutions to carry out research on ongoing projects of the department
initially free of cost until establishing as a research organisation or till publishing of
sufficient technical papers.
Once established as a research organisation, internships can be provided with
fees to both Undergraduate and Post-Graduate students of various
Irrigation Design and Research Board, Kerala
Performance Progression Policies 41
institutes/organisations the revenue of which can be used to sponsor leading
conferences like, International Geological Conference (IGC), International Union of
Laboratories and Experts in Construction Materials, Systems and Structures (Rilem),
American Society of Civil Engineers (ASCE) etc.
6.4 Problems faced for research activities
Streamlining of all the data available with the department.
Acceptance as guides by renowned experts in the technical field to co-author
papers.
Funding for particular research project/ attending conferences and seminars
involving substantial fees if sufficient funds are not allotted in plan schemes.
Dividing time between Full-time research and daily routine works as the same
involves substantial reading of journals.
Meeting deadlines for paper publishing as urgent works, preparation of replies
to legislative committees, court cases, audit paras etc. may pop up.
Lack of flexibility for travel of officers doing research to attend various
conferences/seminars/paper presentations across the country. Air journey
may be sanctioned specially by Government for the travel of all the officers for
the above purposes (Note: Many of the research officers will be of Assistant
Engineer, Assistant Executive Engineer category who are not eligible for air
travel)
6.5 Collaboration with Kerala Engineering Research Institute (KERI)
Since administrative control of KERI comes under IDRB, no special
collaboration needs to be made. However, in case of serious research activities
involving various field tests, KERI and IDRB can execute the same hand in hand.
The activities now being carried out by KERI involves sub-soil investigations, Model
Studies, Survey works, Mix design etc for department projects etc. KERI also does
sedimentation studies for all the dams under Irrigation Department as well as those
under KSEBL when requested upon. Research works on alternate methods for shore
protection, canal lining, soil stabilisation etc can be initiated by KERI by increasing
the infrastructure of the institute. However, in-house capacity of the officers needs to
be increased. It is worth pointing out that many of the major investigation works are
Irrigation Design and Research Board, Kerala
Performance Progression Policies 42
currently being executed by KERI. For e.g., the survey and soil investigation work for
the Rehabilitation and Improvement works of Karapuzha Dam under DRIP Phase-II
are being done with the expertise of KERI.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 43
7. WEBSITE IMPROVEMENT
The existing website of IDRB (www.idrb.kerala.gov.in) was developed in 2013
with the requirements as per the assessment during that period. Considering that the
website requires updations in case of functional and aesthetic aspects along with
better options for content management, it was decided to revamp the existing
website to an informative and interactive web portal, with more features to invoke
viewers’ interest. Accordingly, a new website is under development and would be
subjected to security auditing for hosting the same in the Government server with the
same address.
7.1 Present status of website development
The new website is under development, by incorporating all the information and
services IDRB has to offer for the department officials as well as the general public in
a clean, well-structured and easy to access layout. The new website has the
following functionalities:
A clean and elegant website without compromising the functionality.
Dedicated pages for each of the detailed functional domains of IDRB, viz.
Hydro-Met Data Management, Dam Safety & Reservoir Management,
Investigation & Design of Structures and Externally Aided Projects.
Detailed Organogram of all offices and complete mapping of all officers from
AE/AD and above, including photos and contact details.
Modules for obtaining daily reservoir level data and rainfall data of all the
stations under the department.
Physical progress and expenditure monitoring module for state fund as well as
externally aided projects.
Displaying information on activities including forthcoming meetings, events, site
visits of Chief Engineer and his/her team of engineers.
7.2 Scope for future improvement
Portals for submission of requests for designs, along with, status tracking,
clarifications and finalisation.
Modules for submission and tracking of RTI applications.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 44
Application submission and online payment portal for buying Hydro-Met data by
the public.
Development of the new website is scheduled to be completed by December
2020. Upon completion, it will undergo security audit from a certified audit agency to
identify the security vulnerabilities. After completing the security audit fixes, the
website will be hosted in the State Data Centre by replacing the existing website of
IDRB under the same address (www.idrb.kerala.gov.in)
Irrigation Design and Research Board, Kerala
Performance Progression Policies 45
8. TRAINING AND CAPACITY BUILDING ISSUES
For the overall improvement and awareness of officers of IDRB under various
Divisions and to increase the research potential among officers, the following
trainings are proposed to be imparted.
Project management and leadership skills training for Deputy Directors and
above from leading management institutes like IIMs.
Training on importance of Indian Constitution including its established
institutions like Finance Commission, Comptroller and Auditor General, relevant
Acts like the Environment Protection Act, Forest Act, Kerala Irrigation and
Water Conservation Act, various policies like the National and State Water
Policies, understanding of India’s commitment on various international
platforms like the United Nations on Climate Change, Sustainable Development
Goals and importance of Panchayathi Raj institutions in Governance.
Focussed and hands on design for bridge design especially T-beam and slab
bridge with focus on deck design (for span more than 25m)
Special training for foundation design (Pile foundation- Friction type on various
soil conditions) based on detailed analysis of soil investigation report.
Training on design of multi-storeyed buildings using STAAD-Pro & E-tabs
Training on design of steel structures (with special reference to lifting bridges)
Continuous training for design of irrigation structures especially navigational
lock and barrages with emphasis on latest developments in design
Training on Design flood estimation with GIS tools and Hydrograph/ Critical
sequencing method as per CWC guidelines
Workshop on catchment area delineation and slope determination.
Training Programme on operation and maintenance regarding Hydro
Mechanical aspects and control system in a Dam. The Training Programme
needs to address the following modules
o General Operation & Maintenance issues for dams
o Operation & Maintenance of mechanical part of dams: Spillway Gates/Under
Sluice Gates/Outlets
o Operation & Maintenance control system for dams: SCADA and Automation
Irrigation Design and Research Board, Kerala
Performance Progression Policies 46
Training programme on National Competitive Bidding (NCB) conditions of
World Bank for the agreement authorities and executing officials
Training on Flood routing and Reservoir operation
Training programme on modern techniques for dam rehabilitation especially for
block joint treatment, reaming of porous & foundation drains, spillway
treatment, pier rehabilitation etc
Training on basic finance viz. Financial Code, Budget Manual etc.
Online training related to implementation of medium and major projects in
various river basins may be considered
Irrigation Design and Research Board, Kerala
Performance Progression Policies 47
9. PROBLEMS FACED BY IDRB
Sl No.
Problems Suggested Solution
1 The Design wing is equipped with
qualified professionals. However,
the non-proficiency and non-
exposure to the latest
technological developments / non-
availability of sufficient number of
software in the design wing is one
of the major issues in the design
wing.
New software shall be purchased
and necessary trainings may be
imparted. Capacity building
programmes by experts in the field/
reputed institutions at regular
intervals shall equip the officers with
the requisite knowledge upgrade in
the field.
All newly posted engineers in the
design wing must be given training
in the existing design practices by
the experienced hands in the design
wing itself before handing over major
design works.
2 The promotion, transfer and
posting of experienced officers
without proper time for knowledge
transfer.
Frequent knowledge sharing
sessions by experienced/retired
officers on periodical basis will
ensure that the system is not people
dependent. Admissible honorarium
can be given to retired officials for
which a particular amount can be set
apart under the scheme
“Modernisation of Design Wing”
Officers having PhDs shall be
retained at IDRB for better
knowledge dissemination.
3 Receiving incomplete design
indent (lack of mandatory data
like boreholes) from field offices.
Strict adherence to the data
mandated in the design indent by
the field officer concerned.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 48
4 Inadequate infrastructure and lack
of training for officers (Draftsman)
under the design divisions.
Imparting suitable training along with
providing sufficient computers with
AutoCAD software.
5 DRIP being a World Bank aided
project, National Competitive
bidding document is being used
for procurement of works under
this scheme. Some of the World
Bank conditions are contradictory
to State Government conditions.
These conditions have favoured
the contractors and led to
Arbitration cases.
Government of Kerala may issue
guidelines / directions as to whether
state rules are to be followed in the
World Bank agreed DRIP works.
Also, since several arbitrations are
being filed, a suitable officer to
advice in matters pertaining to Law
needs to be assigned.
6
Difficulty in taking up electrical
works: There is inordinate delay in
procedures regarding estimates
done from electrical wing of PWD,
since the start of DRIP Phase-I
due to lack of officials in their wing
as reported by Chief Engineer,
Electrical
Government may initiate steps to
formulate a separate Electrical wing
for dealing with electrical works of
Irrigation department.
7 Increasing capacity of Overseers
to effectively manage daily routine
activities under Hydrology and
filling vacant posts in field offices
across the State.
Providing necessary trainings for
Overseers to effectively manage
daily routine activities.
Urgently posting officers to vacant
posts.
8 Delay in implementation of
investigation projects since the
major projects for which sanction
to investigation works given by
Proper monitoring of projects by
both IDRB and the concerned Chief
Engineer of the project.
Strict adherence to the data
Irrigation Design and Research Board, Kerala
Performance Progression Policies 49
IDRB are under the purview of
other Chief Engineers. Lack of co-
ordination and adequate support
from field engineers for proper
follow up of the project is a
problem faced by IDRB.
Non-adherence to the circular
issued by Chief Engineer, IDRB
while submitting estimates for
investigation.
mandated in the design indent by
the field officer concerned.
9 Limited no. of officers in design
divisions (20 Nos) should IDRB
take actions for revenue
generation through designs.
Shifting officers from offices wherein
there is excess manpower.
10 Inability to take up works by KERI,
Peechi due to non-release of
funds by Treasury
Appropriate action to be taken by
Water Resources Department with
Finance Department.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 50
10. WAY FORWARD
The following targets are also expected to be achieved in the next two years.
This year
Management/Leadership skill training for selected officers
Procurement of necessary software (STAAD Pro, Etabs,
Autocad) and computers for setting up the design lab
Hoisting new website for IDRB
Launching of K-WRIS
Procurement of computers for the tender already floated
Expenditure of Plan schemes by at least 80%
Initiation of re-establishing e-office
Completion of designs for which all field data are available by
fixing priority
To complete the ongoing works under DRIP Phase-I so as to
achieve the physical target for completion of rehabilitation
works of the proposed 16 dams/ barrages.
To complete the construction of Dam Safety head Quarters
building at Thiruvananthapuram under DRIP which will house
the central control room of surveillance system in all dams
and many offices
To complete preparatory activities of DRIP Phase II &III and
to tender rehabilitation works of Kuttiyadi, Karapuzha,
Kanjirapuzha and Malankara
To complete instrumentation of dams/barrages arranged
under DRIP
Next year
Completion of preliminary design and drawings for planned
Projects in Cauvery basin
Completion of final design and drawings for AVIP
Finalisation of DPR of New Mullaperiyar Dam
Initiation of setting up a design lab and training of officers
Setting up of a Secured digital library for designs
Irrigation Design and Research Board, Kerala
Performance Progression Policies 51
Establishing Real Time Data Acquisition System
To obtain approval for Project Screening Template (PST) of
Neyyar, Kallada, Maniyar, Bhoothathankettu barrage and
Walayar dam and arrange the rehabilitation works under
DRIP phase II
Completion of EIA study of Mullaperiyar dam.
Establishing research centre by collaborating with
institutes/guides for co-authoring research papers.
3 Research Papers to be published in any of the established
journals
Next Two
years
Fully functional Design lab with 2 computers installed with
software for design and drafting like STAAD Pro, ETABS,
AutoCAD etc., Plotter, Printer cum scanner (A3& A4) and
digital library facility
Out of rehabilitation of all 15 dams/ Barrages proposed under
DRIP Phase-2 remaining works will be carried out including
other components, viz, Tourism, Institutional Strengthening
which includes training, construction of buildings and
procurement of equipment.
Implementation of Surveillance system in dams
Benchmarking of Peechi and Malampuzha dams.
Fully functional research division in collaboration with leading
research institutes.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 52
11. MONITORING AND REVIEW
11.1 Officer in charge
Chief Engineer (IDRB) is in charge of technical as well as administrative
matters of IDRB. Director (IDRB) assists the Chief Engineer in technical matters. All
Joint Directors assist them in the process.
11.2 Monitoring methods
Regular review meetings are conducted by Joint Directors on weekly basis to
evaluate the progress of activities under each wing. Necessary feedback and
corrective measures are also suggested by Joint Directors to subordinates to keep
up the timelines. Chief Engineer along with Director, IDRB convenes bi-weekly
review meetings of Joint Directors to co-ordinate and evaluates the overall progress.
Chief Engineer offers decisions to overcome any shortfalls/ bottlenecks during these
review meetings. The same is followed in case of KERI also.
The progress of the works are updated regularly on IDRB website. The same is
represented both through bar charts and graphically inorder to have a quick glance.
The Chief Engineer and Director regularly monitors the same to ensure that
unnecessary delays are avoided. Site visits to important project sites are conducted
by officers concerned as and when needed.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 53
12. SUCCESS STORIES
12.1 Women Empowerment
The Central Project Management Unit (CWC) and World Bank have been in
association with this dept for past 7 years since KWRD became an implementing
agency of DRIP. Since then, many of our dam engineers have been associated with
them directly or indirectly on many occasions. It is a great privilege that our dept has
a handful of lady engineers successfully managing dams unlike other implementing
agencies country wide. Having women in positions of responsibility in a field that is
not traditionally associated with them is not unusual in Kerala where women
engineers of the irrigation department are managing dams and building and
maintaining canals which channel water downstream for irrigation and domestic use.
This has always been a pride and pleasure to CWC and World Bank, which they
have mentioned in many of our official meetings. They have published a storyline on
“Women participation in this sector" in the official website of World
Bank. (https://www.worldbank.org/en/news/feature/2020/04/20/kerala-women-
engineers-empowerment-break-gender-norms?cid=EXT_WBEmailShare_EXT)
Figure 12.1: Women engineers at Malankara Dam, Kerala
Irrigation Design and Research Board, Kerala
Performance Progression Policies 54
12.2 Major accomplishments under DRIP
Rehabilitation works including civil, mechanical and electrical works of 16
dam/barrages/regulators are carried out under DRIP. Major achievements under
DRIP are
Seepage problems in some of the dams could be abridged by conducting
cement grouting & slurry grouting, pointing of upstream face and treatment
of contraction joints using hydrophilic compounds.
Mechanical works carried out under DRIP, facilitated proper shutter operation
during 2018 &2019 floods.
A new bridge constructed at Bhoothathankettu barrage aided to divert heavy
traffic over the barrage.
Moolathara regulator, which was damaged during 2009 flood, has been
renovated and additional vents provided for discharging revised flood.
Electrical works carried out helps to improve gallery & dam top lighting.
Other rehabilitation works such as dam profile correction & turfing, riprap
reconstruction, reaming of porous drains & foundation drains, fencing and
boundary demarcation, compound wall, reconstruction access roads were
also carried out.
Inspection Bungalows in some of the projects were renovated.
Instrumentation of 16 dams are also in progress.
Under Institutional Strengthening, Dam Safety Headquarters building at
Thiruvananthapuram and ISW hub at Palakkad is under construction.
Emergency Action Plans (EAP) of 14 dams/barrages and Operation &
Maintenance manual for 15 dams/barrages has been prepared.
A web-based software package to support the effective collection and
management of Dam Safety data, Dam Health and Rehabilitation Monitoring
Application (DHARMA) is being updated.
Under Institutional Strengthening of DRIP, various capacity building trainings
were imparted to the officials in collaboration with academic institutions.
14 nos. of vehicles has been procured under DRIP for the use in various
projects.
Irrigation Design and Research Board, Kerala
Performance Progression Policies 55
Some of the prestigious projects undertaken by IDRB are shown below:
Figure 12.2: Moolathara Regulator at Palakkad- Renovated under DRIP (designed
by IDRB)
Figure 12.3: New Bridge at Bhoothathankettu for diverting traffic over old barrage
constructed under DRIP (designed by IDRB)
Irrigation Design and Research Board, Kerala
Performance Progression Policies 56
Figure 12.4: Rip rap reconstructed under DRIP at Malankara Dam
Figure12.5: River Training wall constructed at Malankara dam
Irrigation Design and Research Board, Kerala
Performance Progression Policies 57
Figure 12.6: Turfing at Malankara Dam
12.3 International/National Conferences
12.3.1 First International Dam Safety Conference 2018
The first International Dam Safety Conference-2018 was held in Kovalam,
Thiruvananthapuram (Kerala) from January 23-24, 2018. This Conference is fourth in
series organized under aegis of ongoing Dam Rehabilitation and Improvement
Project (DRIP). It was organized jointly by Central Water Commission (CWC), Kerala
Water Resources Department (KWRD), Kerala State Electricity Board (KSEB),
National Institute of Technology, Calicut (NITC), and College of Engineering,
Trivandrum (CET). As many as 550 delegates from over 20 countries, including US,
Switzerland, Spain and Australia took part in the conference. Moreover, dam safety
Irrigation Design and Research Board, Kerala
Performance Progression Policies 58
manuals developed under DRIP were also released for implementation during the
conference.
12.3.2 National Conference – Kerala FloodCon 2020- Policies and Strategies
for Flood Management: Kerala Scenario
A National Conference on Flood management in Kerala Scenario has been
conducted during 23rd & 24th January 2020 at Thiruvananthapuram, which provided a
platform for practitioners, policy makers, engineers, natural and social scientists,
disaster managers and researchers to come together to exchange ideas and
experiences. This conference helped to provide an interactive platform for
brainstorming and sharing new concepts or methods for improving flood risk
management practice in order to better cope with this kind of uncertainties.
12.4 Others
Urgent annual repair/maintenance works of dams are carried out under Dam
Safety Organisation head of account
20 nos. of satellite phones were distributed to all dams/barrages/regulator for
effective communication.
GIS lab of IDRB provided maps for many of the Panchayath Watershed
plans/Block level master plans prepared under Haritha Keralam Mission.
Chief Engineer IDRB received ICI- Ultra Tech Award-2018 for Outstanding
Concrete Structure of Kochi Centre (Category: Infrastructure) for
Thanneermukkom Barrage (3rd Stage Work) (Architectural & Structural
Consultant)
(Thannermukkom Barrage (1450m long) partitions the Vembanad wetland into a fresh water lake on
south and a brackish lagoon on north & is the largest mud regulator in India. This regulator cum
bridge is intended to prevent the impact of tidal action and intrusion of salt water from sea to the lake.
Since this part of the lake forms part of National Waterway III, navigational locks are also provided in
the structure. The first and second phase works of the bund were completed in 1965 and 1975 and
the barrage was made operational in 1976. The construction of the third phase commenced in July
2016 and the bridge was opened to public during July 2018. The design of this prestigious project was
undertaken by IDRB.)
Irrigation Design and Research Board, Kerala
Performance Progression Policies 59
OUTLOOK
“Design is a way of life, a point of view involving talent-
ability- skill & technical knowledge”.
“There is still much to go ahead, but we believe –
Nothing is beyond the moon”
“We believe that IDRB can fly its wings higher with team
work to achieve heights of excellence in- Technology
Management”
60
Appendix I- Completed Projects
A. Completed Designs under Dams Division
Sl No
Name of Work Financial
Year
Date of approval of
design Description
1
NABARD-RIDF-XXIII-Saline Ingress prevention by Construction of regulator at Munayam across Karuvannur River
2020-2021 09-11-2020 Revision work of Regulator cum Bridge.
2
Regulator cum bridge across Bharathapuzha at Koottakkadavu in Anakkara Panchayath - Revision
2020-2021 23-10-2020 Revision of pier and abutment
3
Construction of Regulator near Nambranikadavu across Kadalundi River in Malappuram District/
2020-2021 05-10-2020
Structure- Regulator Length-60m Storage height-4.3m No of spans-5 With Bridge-No With Footridge-No Purpose-Water Supply
4 Pattissery dam - Revised Design of Left Bank Non-overflow Section
2020-2021 07-08-2020 Revision of Left Bank Earthdam Non-over flow section to Concrete Non-Overflow Section
5 Construction of RCB across Shiriya river at Bambrana in Kasargod district
2020-2021 15-07-2020
Structure- Regulator cum bridge with check dam of 2 m height.Above check dam a VCB of 1 m height with FRP shutters. River-Shiriya Length-118 m Total storage height-3 m No of vents for VCB-41 With bridge-Y; 5 span Deck slab bridge of 22m span each 1 score vents having steel shutter of span 8.5 m operated electrically in the Left bank
6 Maintenance of Goolikkadavu Chittor road- Design of retaining wall
2020-2021 10-06-2020 Reconstruction of damaged retaining wall
61
7 Construction of regulator cum bridge across Thoothappuzha d/s of kaladikunnu
2020-2021 13-05-2020
River -Thoothappuzha Length - 110 m No of spans -8 With Foot Bridge- Y With Lock -N Storage height -3 m For irrigation
8 Rectification of apron and construction of retaining wall at Thrithala
2019-2020 18-03-2020 Rectification design of the damaged apron of the RCB
9 Reconstruction of retaining wall at left bank d/s side of RCB at Thrithala near Velliyankallu
2019-2020 29-02-2020 Reconstruction of damaged retaining wall at left bank d/s of RCB.
10
Construction of Salt Water Extrusion Regulator cum bridge across Kariangodu river at Palayi Valavu in Hosdurg Taluk - Kasaragod dist- Revision
2019-2020 12-02-2020 Revision of bridge deck girders
11 Construction of bridge across Varattar river at Anayar Chappathu
2019-2020 10-01-2020
Structure- Concrete Bridge River- Varattar Length - 30 m No.of spans - 2 Width of road - 7.5 m (double lane)
12
Construction of Regulator cum bridge acros Venniyode river at Malankara in Panamaram Panchayath - Revision
2019-2020 10-01-2020 Revision of Abutment
13
Construction of Regulator cum bridge across Kariangode river at Chemmaramkayam in West-Eleri grama panchayath in Kasargod district
2019-2020 20-12-2019
Structure: Regulator cum Bridge River - Kariangodu Length - 82m No. of spans - 6 (12m clear) Storage height - 4.0 m
14
Construction of VCB across Karamanthodu at Varambatta in Vellamunda Panchayath of Wayanad district
2019-2020 10-12-2019
River: Kabani Length of VCB- 34.20m Storage height-2.50m No. of vents- 12 With foot bridge-Y
62
15
DRIP- Dam Safety Headquarters building at PMG campus Thiruvananthapuram- Block 1
2019-2020 10-12-2019
Struture: Building No. of Blocks-3 , 10317sqm Block 1(Guest House)- B+G+1; 540sqm Block 2(Office Block)- B+G+5; 8157sqm Block 3(Auditorium Block)- B+G+5; 1620sqm
16
Construction of Regulator across Kuppam river upstream side of Kuppam bridge in Pariyaram Panchayath-Design of Counterfort retaining wall and end retaining wall
2019-2020 02-11-2019 Side protection works: counterfort retaining wall on left bank and right bank
17 Upstream left bank protection wall of Bavikkara Regulator
2019-2020 20-09-2019 Retaining wall on upstream at left bank of the regulator
18
Construction of regulator across Pampa river on the downstream side of intake well of UIDSSMT of Alappuzha and adjoining palaces at Pannai Kadavu in Thiruvalla Constituency - Revision
2019-2020 19-09-2019 Revision of Lock Shutter pier
19 Attapadi Valley Irrigation Project-Zoning of concrete
2019-2020 07-09-2019
Poposed dam across Siruvani river; Purpose-Irrigation and Wtaer Supply;Ayacut-4323Ha; Tentative drawings issued for preparing DPR
20
Construction of RCB across Ummenchira river at Chekkupalam in Pinaray Grama Panchayath
2019-2020 05-09-2019 The structure is regulator cum bridge .The bridge is two lane with footpath.
21 Attapadi Valley Irrigation Project-Overflow section of dam
2019-2020 19-08-2019
Poposed dam across Siruvani river; Purpose-Irrigation and Wtaer Supply;Ayacut-4323Ha; Tentative drawings issued for preparing DPR
22 Attapadi Valley Irrigation Project-General arrangement
2019-2020 22-07-2019
Poposed dam across Siruvani river; Purpose-Irrigation and Wtaer Supply;Ayacut-4323Ha; Tentative drawings issued for preparing DPR
23 Attapadi Valley Irrigation Project-Non-overflow section of dam
2019-2020 22-07-2019
Poposed dam across Siruvani river; Purpose-Irrigation and Wtaer Supply;Ayacut-4323Ha; Tentative drawings issued for preparing DPR
63
24 Re-Construction of lock gate and bidge at Payyoli canal
2019-2020 18-07-2019
Two lane bridge with footpath of clear span 14m and a lock gate with radial shutter. Purpose : Widening of canal
25
Construction of Regulator across Olavilam Pathikkal in Chokli Grama Panchayath in Kannur dist
2019-2020 27-06-2019
River -Palazhi thodu Length - 14 m No of spans -2 With Bridge- Y With Lock -N Storage height -2.7 m For preventing salt water intrusion
26
Cconstruction of a bridge across Varattar at Puthukulangara of Eraviperoor Grama Panchayath
2019-2020 07-06-2019
Structure- Concrete Bridge River- Varattar Length - 30 m No.of spans - 2 Width of road - 7.5 m (double lane)
27 Retaining wall near Thrithala Regulator
2019-2020 07-05-2019 Reconstruction of left bank retaining wall at d/s of the RCB
28
Construction of Regulator cum, bridge across Palupuzhakkadavu in Annamanada Panchayath in Thrissur District
2019-2020 06-05-2019
Structure: Regulator cum bridge River - Chalakkudy Length - 134.0 m No of spans - 6 (12 m clear) Storage height - 4.5m
29
Construction of Regulator across Kuppam river upstream side of Kuppam bridge in Pariyaram Panchayath
2019-2020 20-04-2019
River -Kuppam Length - 122 m No of spans -9 With Foot bridge- Y With Lock -Y Storage height -4.9 m For preventing salt water intrusion
64
B. Completed Designs under Canals Division
Sl No
Name of Work Financial
Year
Date of approval of design
Description
1
DRIP - Kuttyadi Dam - Strengthening of dam on downstream - Design of Canal mouth
2018-19 03.04.2018
Type of structure: Canal section Project:Kuttiyadi Irrigation Project Purpose: To demolish the existing canal structure at the mouth portion and rebuilding with the same dimensions in concrete
2
Construction of Regulator across Chittur Puzha at Valavupalam in Nallepilly grama panchayath in Palakkad District
2018-19 09.04.2018 Regulator
3
DRIP - Rehabilitation and Improvement of Basic facilities of Chimony Irrigation Project construction of flat type Quarters Building - Revision1
2018-19 13.04.2018 Type of structure:Two storied building with stair room
4
KIIFB - Construction of Regulator Cum Bridge across Chittoorpuzha at Vadakarappalli, Perruvemb Gramapanchayath, Palakkad.
2018-19 16.04.2018
River/Stream- Chitturpuzha Length=144.4 m Storage height =5 m, No: of shutters= 12 m, Storage purpose.
5
Construction of vented cross bar cum bridge across Karichalkadavu in Kattampal Gramapanchayath in Thrissur Distict - Revision
2018-19 17.05.2018
River/Stream- Nooradithodu, Type of structure- VCB with bridge without footpath, Width of river=30 m, Length of structure= 89 m, Storage height=2.5 m, Carriage way width=5.5 m, Purpose- Create storage and provide vehicular access, No: of vents=12, Ayacut-456 Ha
6
Construction of a VCB Cum Bridge across Punnapuzha at Arampulickal in Chungathara Panchayath in Malappuram District - (Balance)
2018-19 18.05.2018
River/Stream:Punnapuzha, Type of Structure:Checkdam cum bridge, Width of river:55m, Length of Bridge: 49.8m, Height of check dam:2m
7
Construction of Regulator with lock across Konothupuzha at Puthenkavu in Udayamperoor Gramapanchayath in Ernakulam District.
2018-19 21.05.2018
River/Stream: Konothupuzha, Type of structure: regulator with lock, Length : 33 m, Purpose: As the existing old regulator is not operational, a new regulator is proposed, With lock : Y, Length of lock:9 m
8
Construction of weir Across Thootha River at Kalikkadavu in Aliparambu Panchayath in Malappuram District - Revision 1
2018-19 30.04.2018 River- Thootha, length of structure= , Storage height= 2.7 m, no: of vents- 6 Scour vent and 5 vents
9 Construction of Road Bridge across T.S Canal in Thekke Arayathuruthu at Chirayinkeezh
2018-19 09.07.2018 River/Stream- T S Canal, Length- 24.79 m, Purpose- Transportation,
65
Panchayath. Width of carriage way-6 m
10
Construction of Road bridge and retaining wall across T.S. Canal at Thekke Arayathuruthu in Chirayinkeezh Panchayath.
2018-19 13.07.2018
Type of structure- Cantilever Retaining wall, Length:12.00 m, Height:6.820 m
11 DRIP - Rehabilitation and Improvement of Basic facilities of Moolathara Regulator - reg.
2018-19 09.08.2018 Type of structure- Canal head regulator
12
Boat Terminal at Mavilakadappuram in Valia paramba Panchayath in Kasargod District.
2018-19 08.10.2018
Type of structure: Boat Terminal, Number of berths: 2, Length of walkway: 51.3, Width of walkway: 4.8 m
13 PyIP - Rectification of breached portion of main canal at Ch :1300 m
2018-19 22.09.2018 Breach rectification. Aqueduct and counterfort abutment
14
Construction of VCB Cum Foot Bridge across Pallathadka River at Kuduppamkuzhi in Badiadka Panchayath - Revision -1
2018-19 12.11.2018
River/Stream:Pallathada River, Type of Structure: VCB cum foot bridge, Width of river:44.5m, Height of Storage:3m, width of foot bridge: 1.2m
15 Construction of weir cum bridge at Bheemanadi across Chaithravahini River
2018-19 31.10.2018 River/Stream- Chithravahini, Length= 65 m, Storage height= 3m, No: of vents- 5
16
IIP - Constructing LBC from ch: 10490 -10599 including MC road crossing and allied works (Through --)
2018-19 29.11.2018 Type of structure- Cut and cover (push Through), Length =35 m (Cut and cover)
17
Kuttiyadi Irrigation Project Reconstruction of demolished aqueduct at Vallikkadu in Azhiyoor Branch Canal between 6/500 and 7/200 Km in Cherodu Panchayath.
2018-19 11.06.2018 Type of structure- Pipe aqueduct D.I. Pipes Length : 700.00m, diameter 1.10 m
18
Construction of a vented weir across Panathur river at Kottody in Kallar Panchayath, Kasargod District.
2018-19 20.06.2018
River/Stream :Panathur river, Type of structure: Check dam, Storage height: 2 m, Width of river: 60 m, Purpose: For conserving water during summer season and for irrigation purpose, With bridge: N
19 DTPC Kollam - Construction of Punarjani Eco Park, Kollam
2018-19 31.07.2018 Design of stone column for soil improvement
20 Retaining wall for the damaged Shanghumugham road
2018-19 17.08.2018
Type of structure: Coastal protection work, Purpose: To protect the airport road from the sea attack, Length: 400 m
21
Development of Kottappuram houseboat Terminal in Neeleshwaram Municipality in Kasargode District.
2018-19 17.08.2018
Type of structure: Boat Terminal, Number of berths: 3, Length of walkway: 145.8, Width of walkway: 4.8 m
22
Constructing Salinity Barrier across Pulikeezhu river at Mahadevikadu in Karthikappaly Panchayath in Harippad Constituency
2018-19 3.10.2018
River/Stream- Pulinkeezhu, Structure- Regulator, length= 36 m, Storage height=3.5 m, Purpose- To arrest intrusion of saline water from Kayamkulam Kayal, no: of vents=3, Ayacut=5000 Ha
66
23
Construction of check dam across Manimala river at Kulathoormuzhi in Vellavoor panchayath - Revision
2018-19 01.10.2018
River/Stream :Manimala, Type of structure: Check dam, Storage height: 1.5 m, Width of river: 80 m, Purpose: For conserving water during summer season and for irrigation purpose,
24
KIIFB - Construction of regulator cum foot bridge across Meenachil river at Thazhathangadi Bhagom in Arpookkara Panchayath in Kottayam District
2018-19 04.12.2018
River/Stream- Meenachil, Type of structure- Regulator with foot bridge, length= 58 m, Storage height= 4.7 m, Purpose- Preventing salt water entry in dry season, No: of vents-5
25 Construction of regulator across Kallada river downstream of bridge at Njankadavu.
2018-19 24.10.2018
River/Stream- Kallada, Length=96 m, Storage height= 7.6 m, Type of structure and Purpose- Storage regulator for drinking water project of KWA to Kollam Corporation, No: of vents=7
26
Construction of Check Dam Cum Bridge across Panathoor river at Kareeladukkam in Kallar Panchayath.
2018-19 22.12.2018 River- panathur, Length of structure= , Storage height= 2m, No: of vents=4.
27
Construction of Counterfort retaining wall at Right Bank of Regulator across Kadalundi River - Puzhankavu in Manjeri Municipality in Malappuram District.
2018-19 14.01.2019 Type of structure- Counterforte Retaining wall, Length=52.50 m, Height= 8.20 m
28 Construction of land span for damaged portion of approach road of Perumpuzhakadavu
2018-19 02.08.2018 Approach road with single lane bridge
29
Construction of weir cum bridge across Kurumanpuzha at Peruvambadam - Malappuram
2018-19 15.12.2018
River/Stream- Kurumanpuzha, Length=42 m, Storage height= 1.5 m, No: of vents- 4, Storage purpose
30 Construction of bridge across Irood River
2018-19 01.01.2019 River -Irood River, Type of structure-Single lane Bridge, Road width=4.5 m, Number of span=4, Span length=15m
31 Kuttanad Package - Flood Management protecting outerbund of C and D Block
2018-19 13.03.2019
River/Stream/ Waterbody- Tharasukayal,Structure- Pile and slab (RCC piles upto 12 m and Precast slabs) for bund protection (Regulation of flood water in Kayal area near C&D Block and Ranni and Chithira Block)
32 Construction of regulator across Kallada River at downstream of Njankadavu - Revision-1
2018-19 02.11.2018
River/Stream- Kallada, Length=96 m, Storage height= 7.6 m, Type of structure and Purpose- Storage regulator for drinking water project of KWA to Kollam Corporation, No: of vents=7
33
Construction of SWE/VCB Cum Tractor Path across Poorapuzha at Parayil in Parappanangadi Municipality in Malappuram District.
2018-19 01.01.2019
River/Stream- Poorappuzha,Length=22.8 m, Storage height= 2.5 m, Type of structure and Purpose- VCB cum foot bridge to prevent saline water intrusion, No: of vents=8, Ayacut=400 Ha
67
34
Construction of SWE/VCB Cum tractor Path across Poorappuzha at Parayil in Parappanangadi Municipality in Malappuram District - Revision 1
2018-19 10.02.2019
River/Stream- Poorappuzha,Length=22.8 m, Storage height= 2.5 m, Type of structure and Purpose- VCB to prevent saline water intrusion, No: of vents=8, Ayacut=400 Ha
35
Constructing Salinity Barrier across Pulikeezhu Aru at Mahadevikadu in Karthikappaly Panchayath in Harippad Constituency - Revision 1
2018-19 12.12.2018
River/Stream- Pulinkeezhu, Structure- Regulator, length= 36 m, Storage height=3.5 m, Purpose- To arrest intrusion of saline water from Kayamkulam Kayal, no: of vents=3, Ayacut=5000 Ha
36
Construction of Stream Water Drain beyond the boundary of Kannur International Airport - KIAL - Drain 2 A Drain 3 A
2018-19 02.02.2019 Length Drain 2 A : 159.00 m, Drain 3A : 1310.11 m
37
Construction of Regulator Cum Bride aross Panamaram river at Kuruvilamkode in Panamaram Panchayath, Wayanad - Design of retaining wall for approach road.
2018-19 22.01.2019 Type of structure- Cantilever Retaining Wall, Length=172 m
38
Modernization of Irrigation Quality Control Lab at Kottarakara Reinforcement details of Roof slab and Beam
2019-20 29.04.2019 Plinth Area- 161.68 sqm, Single floor
39
Reconstruction of St. Andrews Bridge and approach road at Ch: 24.230 Km in Kadinamkulam Panchayath
2019-20 31.05.2019
Type of structure- Bridge without footpath, Length -30 m,Width of carriage way= 11.23 m, Counterfort retaining wall
40
Reconstruction of St. Andrews Bridge and approach road at Ch: 24.230 in Kadinamkulam Panchayath - Construction of Retaining wall for approach road
2019-20 31.05.2019 Cantilever Reatining wall of length= 65 m
41 Construction of check dam at District Farm House at Neryamangalam
2019-20 22.07.2019 Length of structure= 12 m, Storage height= 2.6 m, Purpose- Irrigation
42
Construction of Regulator cum Bridge at Kankakkadavu across Bharathapuzha in Kuttippuram Panchayath (Revision -1)
2019-20 14.08.2019 River/Stream- Bharathapuzha, Length=418 m, Storage height= 2.80m, No: of shutters= 30 m
43
Construction of a weir Cum Bridge across Moorikadavu river at Cheekadavu in Udayagiri Panchayath
2019-20 06.09.2019 River/Stream- Moorikadavu, length=42 m, Storage height= 2 m, No: of vents= 4 m
44 MVIP - Urgent rectification to the breached portion of Kadappoor Distributory - 1410 m to 1505 m
2019-20 19.09.2019 Rectification of damaged portion of 95 m length
45
Construction of check dam across Ithikara river at Mannayamkadavu in connection with Water Supply Scheme to Kalluvathukkal, Paripally and Velinalloor Villages at Kalluvathukkal Panchayath of Kollam District
2019-20 10.7.2019
River/Stream : Ithikara River Length :90m Storage Height : 1.5m Pupose : Augumenting source for drinking water purpose Nature of Structure : Checkdam
68
46
Chalakudy River Reversion Scheme Damage of LBMC between Ch. 0/200 and 0/500 Km construction of counterfort retaining wall
2019-20 01.03.2019 Type of structure- Counterfort Retaining wall, Height=11.6 m
47
Construction of VCB Cum Tractor way across Peruvai river at Balloor Ottappadap in Paivalikae Panchayath in Kasargode District - Revision 1
2019-20 03.09.2019 River/Stream- Peruvai, Length= 25 m, Storage height= 3 m, No: of vents= 4, Ayacut= 70.8 Ha
48
Construction of Check dam across Kannimala river in Munnar Panchayath, Idukki District.
2019-20 07.05.2019
River/Stream :Kannimala Type of structure: Check dam Storage height: 3.0 m Length of check dam: 23 m Purpose: For conserving water during summer season and for irrigation purpose With bridge: N
49
Construction of check damcum bridge and canal at Chempakakundu across Kaloorpuzha near Mathamangalam Anganavady in Noolpuzha Panchaytah (Wynad)
2019-20 03.12.2019
River/Stream : Kaloorpuzha Length :22.5m Storage Height : 2.5m Pupose : Storing water for lift irrigation Nature of Structure : VCB cum Tractorway Width of Tractorway : 3.5m No. of vents : 2 Ayacut : 150Ha
50
Karappuzha Irrigatip Project- Design proposal for the structure proposed at Ch 4800m of left bank main canal breached during flood 2018
2019-20 16.12.2019
Type of structure Aqueduct Project Karapuzha Irrigation Project Purpose of structure Restoring the breached portion of the Left bank main canal length of aqueduct 96 m Span length 21 m
51
Construction of SWECB at Kanchikkatte at Kumbla river in Kumbla Panchayath, Manjeswaram constituency in Kasargd district
2019-20 07.02.2020
River/Stream: Kumbla, Type of structure: Regulator with bridge,Length : 68.3, Purpose: To prevent salt water extrusion to the upstream side as the existing structure is in a dilapidated condition
52
PyIP- Flood damages 2019- Rectification of breach in UT at Ch 12/325 km in Kara in Mattannur Municipality
2019-20 20.12.2019 Type of structure: Undertunnel L=73 m, Twin box B X H=2 X 3 m
53
Construction of Vented weir cum bridge across Panathur river at Chirankadavu at Panathdy Panchayath
2019-20 01.11.2019 River- Panathur, length of structure=60 m,Storage height=2 m,No: of vents=4
54
Construction of check dam at Mannthikadavu across Thoothapuzha at Cherplassery Municipality in Palakkad district
2019-20 29.02.2020 River/Stream- Thootha, L= 91 m, Storage height= 2 m, No: of vents=4,
55
Construction of vented weir cum bridge across Manatty river at Manatty in Chapparapadavu panchayath in Kannur district
2019-20 16.03.2020 River- Manatty, Length=42 m, Storage height= 2m, No: of vents=4
56 Flood relief work 2018-19: Reconstruction of Poomala Dam
2019-20 16.03.2020 Type of structure - Aqueduct, LocationPoomala dam canal, Purpose
69
Canal breach of structure Reconstruction of breached portion of canal of Poomala dam,
57
Tractor Bridge across Puthenthodu between ward no 6 and 7 at Pulincunnu Gramapanchayath, Alappuzha District
2019-20 20.03.2020 Type of structre- Tractor way, length -20 m ,Span length -10 m
58 KIAL- Design of Drains 6B and 6B1
2019-20 20.03.2020 Length Drain 6B : 132.00 m,Drain 6B1 : 100.15 mWidth: 1.60m
59
Construction of weir across Kadalundy river near Anappara- Pottammal Kadavu in Koottilangady panchayath in Malappuram district- Revision 1
2020-21 06.05.2020 River- Kadalundy, Width of river= 66.2 m, Length of structure= 66.2 m, Storage height=2.5 m,No: of vents= 5
60
Construction of RCB at Keezhthadilam across Wadakkanchery river at Thalappilly Taluk, Thrissur district
2020-21 25.05.2020 River/Stream- Wadakkanchery, length=40m, Storage purpose, No: of vents=3
61
KIIFB- Construction of Regulator cum bridge at Muttickal- Attathara road- Wadakkanchery river, Thrissur district
2020-21 27.05.2020
River/Stream : Wadakkanchery River Length : 22m Storage Height : 2m Pupose : Protection of Wadakkanchery river from Kanjirakkod to Pathramamngalam Nature of Structure : Regulator cum Bridge Carriageway of Bridge : 4.25m No. of vents : 2
62
Construction of check dam at Veettiyoor in Puthur Gramapanchayath at Attappady in Palakkad district
2020-21 09.06.2020
River/Stream- Bhavani,Length-60 m,Storage height-1.7 m,Purpose- irrigation,No: of vents4,With tractorwayAyacut-80 Ha
63 Storage dams in the upstream of Thumboormuzhi weir at Kannankuzhi
2020-21 River/Stream- Chalakkudy, Length of
structure= 222 m, Storage height= 4 m, Storage purpose, No: of vents= 16
64
Construction of checkdam across Manimala river D/s of Kavanadi palam in Kanjirappally Panchayath
2020-22 15.04.2020
River/Stream- Manimala, length = 60 m, Storage height= 2m, Purpose- Storage for drinking water
65 Construction of ISW (Inter State Water) Hub at Palakkad
24.06.2020
Type of structure: Buiding Purpose of structure: Hub for the Inter state waters Software used: Staad
66 Peechi Irrigation Project- LBMC-Proposed aqueduct between Ch:19/600 km and 20/600 km
18.06.2020
Type of structure - Aqueduct, LocationPeechi dam canal, Purpose of structure Reconstruction of breached portion of canal of Peechi dam length of aqueduct -60 m ,Span length -12 m
67 Construction of Check dam cum bridge across Mullaringadu river near Mullaringadu Temple junction in Vannapuram panchayath.
2020-21 06.08.2020 River/Stream- Mullaringad, length= 20 m, Storage height= 1.6 m, purpose- irrigation, No: of vents= 2,
70
68 Re-Construction of Kallupalam Bridge across TS Canal A Kollam
2020-21 06.08.2020 River/Stream- TS Canal, Length= 21.75 m, Purpose- Transportation, Width of carriage way=7.5 m
69
Construction of BOX CULVERT (2 Nos.) in Chainages 7000.000 &7211.000 across MVIP- KURAVILANGAD Major Distributory (for KSEB)
2020-21 11.08.2020
River- major distributory, Lenth= 50m & 20m Purpose-Providing Transportation facility for the construction of 400KV substation by the side of MDC, Width of the culvert-4.2m each
70
Reconstruction of box culvert at Ambanattuchira road near Chilavanoor in Ernakulam District- Revision 1
2020-21 27.08.2020
Stream- Ambanattuchira thodu, 7 Celled Box culvert with shutters for salt water exclusion, Length=26.15 m, Purpose- Vehicular traffic, Width of carriage way=4.75 m
71
BSP- Padinjarathara Branch canal- Construction of Syphon between Ch:543.30 to Ch:568.30
2020-21 12.10.2020
Pressure syphon with inlet and outlet wells of inside dia 3m and height 11m and horizontal barrel of size 18*1.6*17.2(L)
71
C. Completed works under Dam Safety Organisation
Sl.no Name of work
1 Urgent Repairs to LBMC valve of Peechi dam
2 PVIP-Dam Safety- Providing Roofing and side covering with GI grill for Generator Set of Barrage Bhoothathankettu.
3 Survey work for conducting model study of Kuttiyadi dam as part of DRIP
4 PyIP- Flood damages 2019- Refixing partially damaged scale for reading water level in the reservoir of Pazhassi barrage
5 Dam Safety- MALAMPUZHA- Painting the Spillway gate & Replacement of existing Rubber seals of Spillway shutters
6 KPIP-Urgent jungle clearance and cleaning of Gallery in Kanhirapuzha.
7 Emergency Maintenance of 3rd & 4th gate of Maniyar Barrage (PIP) at Pathanamthitta District
8 Rain and Flood damages - P. I. P. Head works at Maniyar-urgent rectification works to the guide walls and spillway of barrage.
9 PIP Head Works - Protection Works at offtake of Main canal
10 PVIP - Dam safety - Side protection works to Right bank of main canal near check dam.
11 PyIP- Urgent removal of trees and branches stucked in the reservoir on the upstream side of Pazhassi barrage.
12 Supply of Digital Elcometer , Ultra Sonic Thickness Guage& Laser Distance Meter for 6 Irrigation Mechanical Subdivisions in Irrigation department
13 NIP-Dam Safety Works-Providing MS Cable Trays and allied works at Dam Top
14 KIP- Dam Safety works -Removal of calcination, painting and lettering in the inspection gallery of Reservoir
15 NIP- Dam Safety works- Urgent Jungle clearance at the saddle dams
72
D. Completed works under State Hydrology
Sl No Name of Work
1 MHIS – Procurement of Current Meter with accessories, Sedimentation Sampler (Panjab Type) and filtration unit for Attappady Valley Irrigation Project (AVIP)
2 MHIS- Maintenance of DWLR Including replacing battery at Manakkadavu under hydrology section Palakkad
3 MHIS – Maintenance of Hydrology Complex, Thrissur
4 MHIS – Supply and Erecting Gauge Post at various Seasonal River Gauge Stations under Hydrology Section, Kottayam for 2019-20.
5 MHIS – Modernisation of Hydrology Information System, Estimate for Steel Structural roofing, repainting and repair works in Hydrology Division Office, Chengannur
73
E. Completed works under Investigation
Sl No. Name of Work
1 2020/3654/IA-Investigation for the construction of protection walls for the proposed regulator across Chitturpuzha at Valavupuram in Nallepilly Panchayat in Palakkad
2 2020/322/P1-Kabani Sub Basin-Taking fly levels and marking FRL in the reservoir area of Thondar Irrigation Project
3 2020/131/IDRB-Soil investigation for the proposed RCB at kanurchira,Nadathara G.P Thrissur District
4 2020/148/IDRB-Soil Investigation at Ch.17Km at KIP Main Canal,Pathanapuram,Kollam
5 2020/153/IDRB-Investigation for the rectification of Existing regulators at Enamakkal and Idiyanchira Thrissur District
6 2020/355/P1-RKI-AIP-Goolikkadavu-Chittoor Road-Construction of retaining wall- Investigation Work
7 2020/3205/IA-Putting up temperory bund for Enamakkal and Idiyanchira for Investigation works
8 2016/2954/IA_Investigation works for the construction of a check dam at the U/S of Karyanikkadavu across Chalakkudy river in between Meloor and Paryaram Panchayats
9 2018/5779/IA-Investigation works to RCB across Anjarakandy puzha at Kakvapara in Chittariparamba Panchayat Kannur Dist
10 2019/11505/IA-Investigation work for the constructioin of RCBacross cherupuzha at Kalpallikkadavu in Koduvally Municipality
11 2020/23/P2-Topographic survey for construction of Regulator cum bridge across Meenachil river at Koottanal Kadavu in Bharananganam Panchayat in Kottayam District
12 2020/154/IDRB-Fundemental Studies using Smart Station for the year 2020-21-Topographical survey for Seetharkundu Water Falls-Stage-II
13 2020/3849/IA-Investigation for check Dam Cum Tractor Bridge Construction in njaviroor kadavu across Ithikkara river in Chathanoor Constituency
14 2020/3121/IA-Investigation for the construction of Thumpaman Thazham-Mankkadavu bridge across Achencoil river in Kulanada Panchayat
15 2020/3096/IA-Investigation of Azhakapara LIS in Thiruvengara Panchayat of Palakkad District
74
F. Completed works under NHP
Sl No Name of Work
1 NHP –The Supply, Installation, Testing, Training, Commissioning, Operation and maintenance of ADCP for discharge measurements in Kerala.
2 Procurement of Echo Sounder
3 Procurement Of Handheld Multi Parameter Water Quality Meter
75
G Completed works under DRIP
Sl.no Name of Dam /Barrage/
Regulator Name of Work
1 Bhoothathankettu Barrage
Rehabilitation and Improvement of Basic Facilities of Bhoothathankettu Barrage in Periyar Valley Irrigation Project-
Construction of new bridge for diversion of traffic for safety of old barrage (at Bhoothathankettu)
Renovation of Mechanical Structures
Renovation of electrical installation of Bhoothathankettu barrage
2 Chimoni
Rehabilitation and Improvement of basic facilities of Chimoni Irrigation Project- Civil Works-
Rehabilitation and Improvement of Basic facilities of Chimony Irrigation Project- Chimony dam (Mechanical Works)
Electrical Works of Chimoni Irrigation Project- Renewal of damaged fitting of dam top lighting and gallery lighting and providing Generator at Chimoni dam, Thrissur
3 Chulliyar DRIP- Rehabilitation and improvement of basic facilities of Chulliyar Irrigation Project (Civil,Mechanical,Electrical)
4 Kallada
Rehabilitation and Improvement of Basic Facilities of Parappar dam in Kallada Irrigation Project (Civil works)
Rehabilitation and Improvement of BasiFacilities of Parappar dam in Kallada Irrigation Project (Mechanical Works)
5 Kanhirapuzha
Rehabilitation and Improvement of Basic Facilities of Kanhirapuzha Irrigation Project (Civil works)
Rehabilitation and Improvement of Basic Facilities(Hydro-Mechanical works) of Kanhirapuzha dam
Rehabilitation and Improvements to Electrical installation of KPIP – Kanhirapuzha Dam
6 Kuttiyadi
Rehabilitation and Improvement of Basic Facilities of Kuttiyadi Irrigation Project (Mechanical works)
Electrical Works of Kuttiyadi Irrigation Project – KyIP Peruvannamuzhi- Renovation of Electrical Installation
Construction of Inspection Bungalow (Annex) and Control Room building at Peruvannamoozhi Dam site
7 Malampuzha Rehabilitation and Improvement of Basic Facilities of Malampuzha Irrigation Project
8 Malankara
DRIP-Rehabilitation and improvements of Basic facilities of Muvattupuzha Valley Irrigation Project(Civil works)
Construction of river training wall at the left side downstream of Malankara Dam
Rehabilitation and Improvements to the Electrical installation of Malankara Dam-Electrification of Police Aid Post, Rest Room and Site Office
DRIP-Rehabilitation and improvements of Basic facilities of Muvattupuzha Valley Irrigation Project - Construction of Comfort Station , Jet washing of dam, Providing hand rail at river training wall , Improvements of perumattom to Dam road.
9 Meenkara Rehabilitation and Improvement Of Basic facilities of Meenkara Irrigation Project Civil Works
76
Rehabilitation and Improvement Of Basic facilities of Meenkara Irrigation Project (Mechanical Works)
Rehabilitation and improvement of basic facilities of Meenkara Irrigation Project (Electrical Works)
10 Moolathara Rehabilitation and Improvement of Basic Facilities of Moolathara Regulator
11 Neyyar Rehabilitation and Improvement Of Basic facilities of Neyyar Irrigation Project-Neyyar Dam (Mechanical Works)
12 Pazhassi
Rehabilitation and Improvements of Basic Facilities of Pazhassi Irrigation Project (Civil Works)
Rehabilitation and Improvement of basic facilities of Pazhassi Irrigation Project- Mechanical works
13 Peechi
Rehabilitation and Improvements of Basic Facilities of Peechi Irrigation Project (CivilWorks)-Total Station Survey and demarcating boundaries, Construction of control room, administrative offices and Information Centre
Rehabilitation and Improvement of Basic facilities of Peechi Irrigation Project (Mechanical Works)
14 Pothundy
Rehabilitation and Improvement Of Basic facilities of Pothundy Irrigation Project (Civil works)
Rehabilitation and Improvement Of Basic facilities of Pothundy Irrigation Project- Pothundy dam(Mechanical Works)
15 Vazhani
Rehabilitation and improvement of Basic facilities of Vazhani Irrigation Project-Civil works-
Rehabilitation and Improvement Of Basic facilities of Vazhani Irrigation Project(Mechanical Works
Rehabilitation and improvement of Basic facilities of Vazhani Irrigation Project (Electrical works)
16 Walayar DRIP- Rehabilitation and improvement of basic facilities of Walayar Irrigation Project(Civil, Mechanical, Electrical)
77
Appendix II- Ongoing Projects 2020-21
A. Ongoing Design projects under Dams Division
Sl No. Name of Work Present Status Description
1
Construction of checkdam cum bridge at Payyavukadavu across Kaliyar river connecting Paigottoor &Kumaramangalam Panchayath in Idukki District
Design under scrutiny. Checkdam cum Bridge
2
Construction of RCB at Chullikkaattukara across Iruvanchipuzha in Kodenchery Panchayath in Kozhikode district
Design under scrutiny. Regulator cum Bridge
3 Reconstruction of Pattissery dam
Site inspection done on 14/11/2020. PMC meeting convened on 16/11/2020.
Reconstruction of Pattissery Dam
4 Pattissery Dam in Pambar basin - Design of Saddle dam
Site inspection done on 14/11/2020. PMC meeting convened on 16/11/2020.
Saddle dam at Pattissery
5
KIIFB - Constructiopn of Regulator cum bridge across Muvaattupuzha river at Poothotta in Chembu Panchayath in Kottayam District
Additional details called for from site for proceeding with the design.
Regulator cum Bridge
6
KIIFB - Constructiopn of Regulator cum bridge across Muvaattupuzha river at Ithipuzha in Vaikom Constituency in Kottayam District
Additional details called for from site for proceeding with the design.
Regulator cum Bridge
7
KIIFB - Construction of SWE Regulator on u/s of old Chithari- SWE Regulator cum bridge across Chithari river in Kasargod district (Lock cum regulator)
Design in progress. Salt Water Extrussion
Regulaor
8 Construction of bridge at d/s of Bavikkara Regulator in Kasargod district
Additional details called for from site for proceeding with the design.
Bridge
9
Construction of check dam cum footbridge across Bharathapuzha at the u/s of Pattambi cause way in Pattambi Municipality
Additional details called for from site for proceeding with the design.
Checkdam
10 Construction of Bridge across Varattar River at Mampattakadavu
Additional details called for from site for proceeding with the design.
Bridge
11
Construction of Bridge across Varattar River at Prayattakadavu in Kuttur and Thiruvandoor Garamapanchayath
Additional details called for from site for proceeding with the design.
Bridge
12
Construction of Bridge across Varattar River at Nannadu Chapath in Thiruvanvandoor Gramapanchayth
Additional details called for from site for proceeding with the design.
Bridge
78
13
Construction of Bridge across Varattar River at Vanchimoottilpady in Thiruvanvandoor Gramapanchayath
Additional details called for from site for proceeding with the design.
Bridge
14 Construction of Regulator in the downstream of Enamakkal at Kolumadu
Additional details called for from site for proceeding with the design.
Regulator for Water Supply scheme.
15 Construction of Double lane skew Bridge without footpath across Varattar River at Thrikkayyilkadavu
Work outsourced- Good for construction drawings received.Design and drawings to be approved by technical committee.
Skew Bridge
16 Construction of Arch bridge at Vanchipottilkadavu across Varattar River
Work outsourced- General Arrangement Drawings received. Additional details required from field.
Arch Bridge
17
NABARD-RIDF-XXV-CSIND-Construction of a lock cum bridge in Ch:316.728km of west coast canal in Veliyamcode in Ponnani Taluk in Malappuram district
Design in progress with available details. Pile load test values at BH4 and near BH7 points requested from site officers.
The structure is lock cum bridge .Span of bridge-25
m.length of lock-70 m.Width-14 m
18
Rebuild Kerala Initiative- Rectification works of Enamakkal & Idiyanchira Regulators in Kole Lands -Thrissur
Site inspected. Awaiting site investigation details from KERI.
Rectification works of Regulator cum Bridge
19 Construction of Dam Safety Head Quarters at PMG. Thiruvananthapuram
Consultant is appointed for the revision of design with maximum FAR utilization.
Design verification and issue of good for
construction drawings to Dam Safty Wing
20 Construction of dam at lower Chatta Munnar
Site inspection completed. Additional details required for design received- under scrutiny.
Dam
21 Physical Model Study of Pattissery dam
College of Engineering, Trivandrum is entrusted with the study. Study of spillway and energy dissipation strcutures. completed. Canal sluice study to be completed.
Physical model study of Pattissery dam
22 Seismic Study of Attapady Valley Irrigation Project
Site specific seismic study of Attapady Valley Irrigation project is being entrusted to CWPRS.
Site specific Seismic study of Proposed Attapady
Valley Irrigation Project Site.
23
Regulator cum bridge across Bharathapuzha at Koottakkadavu in Anakkara Panchayath - Design of retaining wall
Design in progress. Retaining wall
79
B. Ongoing Design projects under Canals Division
Sl No. Name of Work Work status
Type of structure
1 Karappuzha Project- Padinjaraveedu Branch Canal ch.1110m to 1210 m- Design of canal and protection wall.
Design and drawing submitted for review and approval
Aqueduct
2 BSP-VBC-Construction of Branch Canal From Chainage 2390M to 2680 M Incuding CD Works
Design and drawing completed and submitted for review
Covered flume
3 BSP-VBC-Construction of Branch Canal From Chainage 2045M to 2390 M Incuding CD Works
Design and drawing completed and submitted for review
Covered flume
4
Construction of check dam across Thoothapuzha at Thonikadavu in Vilayur panchayath of Palakkad district
Design and drawings completed and submitted for
review Checkdam cum
Foot Bridge
5
Construction of check dam across Thoothapuzha at Mundorssikadavu in Sreekrishnapuram panchayath of Palakkad district
As directed by CE changes are made in the design and again submitted to Director for review
Check dam
6
KIIFB -Construction of REGULATOR CUM FOOTBRIDGE WITH LOCK across Meenachil River at Thazhathangadi bhagam (Kottayam)
Joint site inspection to be conducted for selecting alternate site.
Regulator cum footbridge with
lock
7
NABARD-XXIII- Construction of check dam across Karimpuzha river at Poosalikadavu in Karimpuzha panchayath in Palakkad district
Details awaited. Check Dam
8 Check dam at Thanissery, KaralamPanchayat, Thrissur
Details awaited from EE, LSGD Division, Thrissur Panchayath
Check Dam
9
Construction of Regulator cum Bridge at Kankakkadavu across Bharathapuzha in Kuttipuram Panchayath- Revision 1
NCR of Kiifb and TAR from CE ( I& A) with proposal for revision not recieved.
Regulator cum bridge
10 KIP(RB) Main canal earth slippage at Ch.17000m
Investigation report not received
Side protection of canal bund
11
KIIFB-Kerala forest Department-Elephant Rehabilitation centre project,KottoorConstruction of Check Dams in Neyyar Reservoir
Design of two checks dams to be carried out.According to the proposal, now design of one check can be taken up.Certain clarifications are required. Letter to CE PII forwarded
Concrete Check Dam
80
12 Steel sheet pile check Dam, Mannanur at Palakkad dist
Damages occured during 2018 flood,and as per the letter received from KIIDC renovation is to be carried out. It is intimated to take necessary arrangements by KIIDC itself
Steel sheet pile check dam
13
Construction of a Check Dam across Payaswini River at ADHUR Chonampalam Karadka Panchayath in Kasrgode District
Design ongoing. Since the site is located on the curved portion of the river, clarification sought from CE(I&A).
Check Dam
14 Urgent coastal protection work at Chellanam - bazar, Chalakkadavu and Cheriyakadavu
Design completed. Action taken for vetting the same from National Institute of Ocean Technology through CE(I&A)
Coastal Protection
15 BSP:Venniyode branch Canal: Construction of Aqueduct: Ch 1715m to ch 2045m
Design in progress Aqueduct
16
Construction of Regulator cum bridge across Muvattupuzha river in Murinjapuzha in Vaikom Constituency in Kottayam District
Details awaited. RCB with Lock
17
Neeleswaram-Bakel Navigation routeConstruction of Lock cum bridge across diversion canal at Nambiarkal i Kanhanged Muncipality in Kasargod district
Additional details called for. Lock cum bridge
18
KDP- Construction of tractorway across Kariangad river at Puliyannur in Kayoor Chemani panchayath in Kasargod district
Design in progress Tractorway
19
KDP- Construction of tractorway across Kariangad river at Chariyakkara in Kayoor Chemani panchayath in Kasargod district
Details recieved through mail. Design of Deck slab ongoing.
Tractorway
20 Check Dam across Gayathripuzha of Anappara Chundekkad in Kavassery Panchayath in Palakkad
Advance copy from KERI Peechi received. Details Awaited
Check Dam
21 CRD Scheme- Construction of Check dams at Upstream side of Thumburmuzhy weir- Vettilappara
Kept on hold as per minutes of IIP- Technical committee meeting dated 03/01/2020. SE, Project Circle Piravom has also reported to keep the design of the structure in abeyance vide letter dated 09.09.20
Check Dam
22 Proposed Irrigation Complex at Thalassery, Kannur Awaiting revised plan Building
81
C. Works under Dam Safety Organisation
Sl.no Name of work
1 Dam safety:- Chimoni- Rectification works to the toe drain of the earthen dam for the year 2019-20
2 Dam safety:- KPIP-Urgent rectification and maintenance of seepage gallery.
3 NIP- Providing partitions inside the Irrigation Museum at Neyyar Dam, Maintenance and Conveyance of items to be displayed
4 Repair,maintenance and painting of spillway shutters of Chulliyar Dam at Palakkad district
5 Dam Safety- Malampuzha Dam- Installation of new Hand rail and Platform on dam top, replacement of sluice well plaatform and other miscellaneous works
6 Dam Safety- Overhauling and painting of canal sluice shutter and providing new ladder for the sluice well in Meenkara dam in Palakkad District
7 Dam Safety- Providing electric motors and overhauling and painting of spillway shutters of Meenkara dam in Palakkad District
8 KRP-DRIP Phase II- Soil test for reviewing the stability analysis of Existing earth dam
9 Conducting topographical investigations in connection with the rectification works of Karapuzha Irrigation Project under DRIP Phase-II-Appendices A & L of Part A
10 Clearing Jungle, Floating Materials, De-rooting plants from Peruvannamuzhi Dam
11 Electrical works - Rewiring and repairs to EI in Inspection Banglow Kanjirapuzha
12 MVIP- Malankara Dam -Removal of calcination and cleaning the pressure release valves of the Inspection Gallery
Details are given in Appendix III
D. Works under State Hydrology
Sl.no Name of Work
1 MHIS- Civil work for Establishing Bench mark in River Gauge stations under Hydrology Section, Kasaragod 2020-21
2 MHIS - Maintenance of Meteorological stations under Hydrology Section, Payyannur for the year 2020-21
3 MHIS - civil works for establishing Bench marks in all river gauge sites under Hydrology Section, Thalassery 2020-21
4 MHIS - civil works for establishing Bench marks in all the river gauge sites under Hydrology Section, Payyannur 2020-21
5 Modernization of Hydrology: Maintenance of River gauge stations of Shiriya U/S & D/S under Hydrology section Kasaragod for the year 2020-21
6 Modernization of Hydrology :Maintenance of river gauge station at Uppala under Hydrology section Kasaragod for the year 2020-21
7 Repai and maintenance of Vanimel river gauge cableway station - Mechanical work
8 Renovation of Kollikkal River gauging station under Hydrology Section, Kozhikode
9 Renovation of Panamaram River gauging station under Hydrology Section, Mananthavady, Kozhikode
10 Renovation of Koodathai River gauging station under Hydrology Section, Kozhikode
11 MHIS - Maintenance of Raingauge station at Teekoy under Hydrology Section Mundakkayam - 2020-21
12 MHIS - Shifting of Manimala River Gauge Station under Hydrology Section Mundakkayam -2020-21
13 MHIS - Renovation of Teekoy River Gauge Station under Hydrology Section Mundakkayam - 2020-21
14 MHIS-Maintenance of Office Building-Hydrology Section,Aluva-2020-2021
82
15 MHIS-Shifting of Marthandavarma River Gauge Station-Hydrology Section-Aluva-20202021
16 MHIS-Renovation of Pala River Gauge Station,under Hydrology Section,Kottayam for 2020-21
17 Maintenance of Hydrology Subdivision, Kozhikode
18 MHIS- Reconstruction of damaged portion of compound wall construction of hump at entrance and exit gates of Jala Vijnjana Bhavan, Thriuvananthapuram.
19 MHIS- Connecting MSL and establishing BM stones at Kalleli gauging station
20 MHIS- Connecting MSL and establishing BM stones at Punalur and Anayadi gauging station
21 MHIS - Supplying and installation of Manual observation equipments for the proposed Fully Climatic Station at Kozha under Hydrology Section , Kottayam.
22 MHIS- Civil work for proposed Fully Climatic Station at Kozha under Hydrology Section , Kottayam for 2020-21
23 Modernization of hydrology- Maintenance of river gauge stations of Madhur and Padiyanthadukka under Hydrology section Kasaragod
SPILL OVER WORKS
24 Modernisation of HIS-Urgent maintenance work to the existing weir and installation of RLS at Kalkandiyoor
25 MHIS – Urgent maintenance works at Vithinassery (CGO) River Gauge Station 26 MHIS – Urgent Repair Works to Vandazhi (CGO) River Gauge Station 27 MHIS – Urgent maintenance works to Chittady (CGO) River Gauge Station 28 MHIS – Maintenance of Hydrology Complex, Thrissur
29 MHIS-Procurement of Automatic Weather Station (AWS) at Chittoor – Attappady including chain link fencing to Attapapady Valley Irrigation Project (AVIP)
30 MHIS – Construction of equipment room of size 3.00 X 4.00 at Chittoor for Attappady Valley Irrigation Project
31 MHIS – Procurement of Current Meter with accessories, Sedimentation Sampler (Panjab Type) and filtration unit for Attappady Valley Irrigation Project (AVIP)
32 MHIS -Civil works for shifting of RLS from Karuvannur river gauge station to Palakkadavu CWC Station
33 MHIS -Maintenance of AWS station at Cheerakuzhy 34 MHIS -Maintenance of AWS station at Vazhani
35 MHIS- Maintenance of DWLR Including replacing battery at Manakkadavu under hydrology section Palakkad
36 MHIS- Civil work for cable way at Manali river gauge station under Hydrology Section, Thrissur.
37 MHIS – Construction of new river gauge station at Thonikadavu under Hydrology Section, Mananthavadi
38 MHIS – Construction of new rivr gauge station at Pulpally under Hydrology Section, Mananthavadi
39 Construction of steps and walk way at Ambittanpotty river gauge Station under Hydrology section Manjeri.
40 MHIS-Repair works of Perinthalmanna, Pandikkad and Edakkara rain gauge stations under Hydrology section Manjeri, 2019
41 Urgent repair of Punnapuzha river gauge station after flood under hydrology section Manjeri
42 MHIS-Procurement of manual equipments for FCS stations under Hydrology section, Manjeri.
43 MHIS - Instruments procurement for Mangattuparamba FCS 44 MHIS -Procurement of bridge outfit at Kannavam
45 MHIS -Procurement of manual observation instruments for replacing obsolete instruments at FCS Vidyanagar
46 MHIS -Supply and installing manual instruments at FCS Sheni
83
47 MHIS -Civil work for installing FCS manual instruments at Sheni
48 Urgent rectification to the hindrances to the shutter operation of the Pazhassi reservoirCutting removal and conveyance of damaged pipe and protection cage of DWLR installed at Pazhassi reservoir under Hydrology Section Thalassery for the year 201920.
49 Urgent repair works at Kakkadavu river gauge station under hydrology section Payyannur for the year 2019 -20
50 Urgent repair works at Bheemanady river gauge station under hydrology section Payyannur for the year 2019 - 20
51 Urgent repair works at Vellur river gauge station under hydrology section Payyannur for the year 2019 -20
52 Urgent repair works at Mangara river gauge station under hydrology section Payyannur for the year 2019 - 20
53 MHIS- Shifting of Mangattuparamba FCS to new location under Hydrology section, Thalassery 2019-20
54 MHIS – Supply and Erecting Gauge Post at various Seasonal River Gauge Stations under Hydrology Section, Kottayam for 2019-20.
55 MHIS – Procurement of Manual Observation Equipments for Kalady Temperature Stations, under Hydrology Section, Aluva for the period 2019-20.
56 MHIS – Procurement of Manual Observation Equipment for the proposed FCS Bhoothathankettu under Hydrology Section, Aluva for the period 2018-19.
57 MHIS – Procurement of Manual Observation Equipment for the Malankara FCS Station under Hydrology Section, Muvattupuzha for the period 2018-19
58 MHIS – Maintenance of CGO (State Fund) Stations under Hydrology Section No.2, Chengannur
59 MHIS – Maintenance of CGO Stations under Hydrology Section No.1, Chengannur
60 MHIS – Connecting MSL of stations under Hydrology Section No.1, Chengannur
61 MHIS – Modernisation of Hydrology Information System, Estimate for Steel Structural roofing, re-painting and repair works in Hydrology Division Office, Chengannur
62 MHIS –Maintenance of Anayadi River Gauge (CGO) Station under Hydrology Section, Adoor
63 MHIS – Maintenance of Punalur River Gauge (CGO) Station under Hydrology Section, Adoor for the Financial Year 2019-20
64 MHIS – Modernisation of Vamanapuram gauging stations – State Fund
Details are given in Appendix III
84
Details are given in Appendix III
E. Works under Investigation
Sl.no Name of Work
1 2020/3654/IA-Investigation for the construction of protection walls for the proposed regulator across Chitturpuzha at Valavupuram in Nallepilly Panchayat in Palakkad
2 2020/322/P1-Kabani Sub Basin-Taking fly levels and marking FRL in the reservoir area of Thondar Irrigation Project
3 2020/131/IDRB-Soil investigation for the proposed RCB at kanurchira,Nadathara G.P Thrissur District
4 2020/148/IDRB-Soil Investigation at Ch.17Km at KIP Main Canal,Pathanapuram,Kollam
5 2020/153/IDRB-Investigation for the rectification of Existing regulators at Enamakkal and Idiyanchira Thrissur District
6 2020/355/P1-RKI-AIP-Goolikkadavu-Chittoor Road-Construction of retaining wall- Investigation Work
7 2020/3205/IA-Putting up temperory bund for Enamakkal and Idiyanchira for Investigation works
8 2016/2954/IA_Investigation works for the construction of a check dam at the U/S of Karyanikkadavu across Chalakkudy river in between Meloor and Paryaram Panchayats
9 2018/5779/IA-Investigation works to RCB across Anjarakandy puzha at Kakvapara in Chittariparamba Panchayat Kannur Dist
10 2019/11505/IA-Investigation work for the constructioin of RCBacross cherupuzha at Kalpallikkadavu in Koduvally Municipality
85
F Ongoing works under RKI
Sl.no Name of Work
1 Development of Kerala Water Resources Information System
The details are given in Appendix IV
G Ongoing works under NHP
Sl.no Name of Work
1 NHP –The Supply, Installation, Testing, Training, Commissioning, Operation and maintenance of ADCP for discharge measurements in Kerala.
2 NHP –The Supply, Installation, Testing, Training, Commissioning, Operation and maintenance of RTDAS for Kerala River Basins
3 Establishment of Inegrated Command and Control Center
4 Procurement of IT Equipment for Integrated Command and Control Center
5 Consultancy for Preparation of DPR for rejuvenation of 5 rivers
6 Establishment and Operation of Forecasting System in flood prone areas
7 Installing Video Conferencing solution at three locations
8 Upgradation of Training Centre, Thrissur
9 Assessment of Water Quality status (Surface water) and evolving mitigation measures to improve the Water Quality in Thrissur Corporation_ Consultancy
10 Assessment of Water Quality status (Surface water) and evolving mitigation measures to improve the Water Quality in Thrissur Corporation_ Operational
11 Studies on saline ingression in selected river basins of Kerala and the impact/extend of sea water intrusion in the coast of Kerala state_ Consultancy
12 Studies on saline ingression in selected river basins of Kerala and the impact/extend of sea water intrusion in the coast of Kerala state_ Operational
13 Procurement of Current meter with Accessories -Cup type
The details of these ongoing works under NHP are as follows:
86
General details
Name of Work NHP –The Supply, Installation, Testing, Training, Commissioning, Operation and maintenance of ADCP for discharge measurements in Kerala.
Division Hydrology Division
Administrative Sanction Order No, date, Amount
G.O (Ms) No.54/2016/WRD, Thiruvananthapuram dtd 1.08.2016. for an amount of Rs.42 crores.
Technical Sanction Order No, date, Amount
DM-AD11/3/2019 –IDRB dated 10.06.2019 of CE (I&D), IDRB, Thiruvananthapuram for an amount of RS.41,73,000/-
Agreement No and date 09/SE/FSC/TSR/2019-2020 dtd 10.12.2019
Agreed Amount(In Rs) Rs.32,49,720/-
Name of contractor M/S A&S Creation,15/19, East Punjabi Bagh, New Delhi -110026.
Site Handover Date 10/12/2019
Period of completion
90 days for the supply of equipments and 120 days for the installation from the date of signing of contract. 3 years comprehensive AMC after expiry of warranty period of 2 years. Training as per the training schedules.
Description
An Acoustic Doppler current profiler (ADCP) is a hydroacoustic current meter, used to measure current velocities over a depth range using the Doppler effect of sound waves scattered back from particles within the water column . In rivers, the ADCP is used to measure the discharge, velocity profile and for cross sectional profiling estimated after adjustment for left and right bank areas. The discharge can be calculated as the dot product between the vector track and the current velocity. Single instrument was procured during the last financial year and measurements were taken during PDS studies, and various other gauging stations under Chenganoor division. Also discharge measurements were taken during resent flood at thottappally spillway. Bid document for purchase of another ADCP during this financial year for Thrissur division is under preparation.
Officer in charge and contact details
Sindhu K.K Executive Engineer, Hydrology Division, Chenganoor 9446512742
Present progress
Name of Work NHP –The Supply, Installation, Testing, Training, Commissioning, Operation and maintenance of ADCP for discharge measurements in Kerala.
Date 12/09/2020
Physical Status Stage in % 100% (Procurement completed)
Financial Status Stage in % 50% (Part payment made )
Description of Current status Measurement of velocity discharge and cross sections are conducting at various gauging stations
Expected date of completion Warranty expires on 09.12.2021 AMC expires on 09.12.2024
87
General Details
Name of Work NHP –The Supply, Installation, Testing, Training, Commissioning, Operation and maintenance of RTDAS for Kerala River Basins
Division Hydrology Division
Administrative Sanction Order No, date, Amount
Order No. GO(MS)No.54/2016/WRD/ Thiruvananthapuram dated 01-082016. For an amount of 42 crores.
Technical Sanction Order No, date, Amount
DM –AD11/4/2019 –IDRB dated 11.07.2019 for an amount of Rs. 10,22,00,000/-
Agreement No and date 12/SE/FSC/ TSR/2019-2020 dated 27/01/2020
Agreed Amount(In Rs) 10, 92, 96,320/- (Rupees Ten Crore Ninety-Two Lakhs Ninety-six Thousand Three hundred and twenty).
Name of contractor M/s Obel Systems Private Limited NO.7, Ground floor, Jaya Mansion, 126Parklane, SD Road, Secunderabad.
Site Handover Date
Period of completion Nine months from the date of signing of contract for equipment and its installation.
Description
Water Resources Management including flood monitoring requires data on real time basis. This activity aims at installing 99 ARG, 13AWS, 56AWLR across Kerala for Real Time Assessment of the Water Resources of the State so as to provide early flood warning. Data will be received at ground station at Thrissur and also to Kerala WRIS.
Officer in charge and contact details
Sudha M.S Superintending Engineer, Field Studies Circle, Thrissur. 9446402882
Present Progress
Name of Work NHP –The Supply, Installation, Testing, Training, Commissioning, Operation and maintenance of RTDAS for Kerala River Basins
Date 15.10.2020
Physical Status Stage in % Site survey progressing
Financial Status Stage in %
Description of Current status
Site survey report of 65 stations submitted, remaining stations are in progress
Expected date of completion 31/12/2020
88
General details
Name of Work Establishment of Inegrated Command and Control Center
Division Hydrology division, IDRB
Administrative Sanction Order No, date, Amount GO (Rt) No. 464/2020/WRD dated 16.07.2020
Technical Sanction Order No, date, Amount -
Agreement No and date -
Agreed Amount(In Rs) Estimate under preparation
Name of contractor -
Site Handover Date -
Period of completion
Description Establishing Integrated Command and Control Centre (ICCC)
Officer in charge and contact details
Sandhya SG, Joint Director,Hydrology (In-Charge) IDRB. 9446595509
Present progress
Name of Work Establishment of Inegrated Command and Control Center
Date 12/09/2020
Physical Status Stage in % -
Financial Status Stage in % -
Description of Current status
Work entrusted to Habitat Technology Group, which is a GoK accredited agency. Estimate under preparation
Expected date of completion 31/03/2021
89
General details
Name of Work Procurement of IT Equipment for Integrated Command and Control Center
Division Hydrology division, IDRB
Administrative Sanction Order No, date, Amount -
Technical Sanction Order No, date, Amount -
Agreement No and date -
Agreed Amount(In Rs) -
Name of contractor -
Site Handover Date -
Period of completion 3 months
Description
Procurement of IT equipments for Kerala-WRIS Centre, Integrated Command and Control Center and setting up Video Conferencing Facility
Officer in charge and contact details
Sandhya SG, Joint Director,Hydrology (In-Charge) IDRB. 9446595509
Present progress
Name of Work Procurement of IT Equipment for Integrated Command and Control Center
Date 12/09/2020
Physical Status Stage in % 10
Financial Status Stage in % 0
Description of Current status
Quotations invited from Accredited agencies in IT sector under Government of Kerala.
Expected date of completion 31/03/2021
90
General details
Name of Work Consultancy for Preparation of DPR for rejuvenation of 5 rivers
Division Hydrology division, IDRB
Administrative Sanction Order No, date, Amount NHP
Technical Sanction Order No, date, Amount DM-AD11/2/2019-IDRB dated 26/07/2019
Agreement No and date DM-AD11/2/2019-IDRB dated 22/07/2020
Agreed Amount(In Rs) Rs 2,24,20,000/- (Rupees Two crores twenty four lakhs twenty thousand only)
Name of contractor
M/s Voyants Solutions Pvt Ltd, Grandiose, 7th floor No 136/2&4,Opposite Rolling Hills, Gachibowli,Hyderabad 500032
Site Handover Date 12.08.2020
Period of completion 10 months
Description
Hiring of Consultancy Services for preparation of detailed project report for Rejuvenation of five rivers namely, Meenachil, Periyar, Pamba, Kallayi&Valapattanam
Officer in charge and contact details
Sandhya SG, Joint Director,Hydrology (In-Charge) IDRB. 9446595509
Present progress
Name of Work Consultancy for Preparation of DPR for rejuvenation of 5 rivers
Date 12/09/2020
Physical Status Stage in % 5%
Financial Status Stage in % 0
Description of Current status Agreement signed with Voyants solutions Pvt. Ltd. Preliminary data collection progressing
Expected date of completion 11.06.2021
91
General Details
Name of Work Development of Flood Forecasting and Early Warning System in Periyar basin
Division Hydrology division, IDRB
Administrative Sanction Order No, date, Amount -
Technical Sanction Order No, date, Amount HYD-AD3/1/2020-IDRB dated 06.05.2020
Agreement No and date -
Agreed Amount(In Rs) -
Name of contractor -
Site Handover Date -
Period of completion
Description To develop a system for Flood Forecasting and Early warning system integrated with Reservoir Operation
Officer in charge and contact details
Sandhya SG, Joint Director,Hydrology (In-Charge) IDRB. 9446595509
Present Progress
Name of Work Development of Flood Forecasting and Early Warning System in Periyar basin
Date 25-11-2020
Physical Status Stage in % 0
Financial Status Stage in % 0
Description of Current status
Request for Proposal soon to be published
Expected date of completion June 2022
92
Details of Completed works
Name of Work Installing Video Conferencing solution at three locations
Parliamentary Constituency -
LA Constituency
Financial Year 2020-21
Administrative Sanction Order No, date, Amount
Technical Sanction Order No, date, Amount HYD/AD2/2/2020-IDRB dated 17-03-2020
Agreement No and date 20-03-2020
Agreed Amount(In Rs) Rs. 25,01,077/-
Name of contractor Kerala State Industrial Enterprices Ltd.
Site Handover Date 20-03-2020
Date of completion 05-09-2020
Description
Installing Video Conferencing solution at three locations viz. (1) Office of the Chief Engineer, IDRB, Vikas Bhavan, Trivandrum, (2) Office of the Chief Engineer, Projects-I, Kozhikode and (3) Office of the Superintending Engineer, Field Studies Circle, Thrissur under NHP
Officer in charge and contact details
Sandhya SG, Joint Director,Hydrology (In-Charge) IDRB. 9446595509
Present progress
Name of Work Installing Video Conferencing solution at three locations
Date 12/09/2020
Physical Status Stage in % 90%
Financial Status Stage in % 0%
Description of Current status Installation complete
Expected date of completion 15-09-2020
93
General details
Name of Work Upgradation of Training Centre, Thrissur
Division Hydrology division, IDRB
Administrative Sanction Order No, date, Amount
Order No. GO(MS)No.54/2016/WRD/ Thiruvananthapuram dated 01-08-2016
Technical Sanction Order No, date, Amount
No. 2018-2019/2017/89/IDRB dated:18-05-2018 for Rs.50,00,000/-
Agreement No and date 08/SE/FSC/TSR/2018-19 dtd 11/01/2019
Agreed Amount(In Rs) Rs. 52,45,489.20
Name of contractor
Sri. Rajesh P.N, M/s Fins Engineers & Contractors Pvt. Ltd, N P Towers, Ist Floor, Poonkunnam Road, west Fort, Thrissur, Kerala
Site Handover Date 15/01/2019
Period of completion 9 months
Description
This work indend to upgrade the existing Training centre at Irrigation Compound, Thrissur to a Centre of Excellence par A State of Art . The work also includes to provide Multumedia facilities for online meetings, accomodation facilities to the trainees and trainers across the state to attend various training activities.
Officer in charge and contact details
Jiji M O, Executive Engineer, Hydrology Divivsion Thrissur 9446106634
Present progress
Name of Work Upgradation of Training Centre, Thrissur
Date 12/09/2020
Physical Status Stage in % 70%
Financial Status Stage in % 20%
Description of Current status Electrification, plumping and finishing work is pending
Expected date of completion 30/11/2020
94
General details
Name of Work Assessment of Water Quality status (Surface water) and evolving mitigation measures to improve the Water Quality in Thrissur Corporation_ Consultancy
Division Hydrology division, IDRB
Administrative Sanction Order No, date, Amount
Order No. GO(MS)No.54/2016/WRD/ Thiruvananthapuram dated 01-082016
Technical Sanction Order No, date, Amount
F.No. X-63016/1/2017-NHP/7426-7427 of Govt. of India MOWR NHP dated 04/12/2017
Agreement No and date 01/SE,FSC/TSR/2018-19 dated 25/04/2018
Agreed Amount(In Rs) 5,00,000
Name of consultant Centre for Water Resourse Devolopment and Management ( CWRDM) Calicut
Duration of study 2018-2020
Period of completion 3 Years
Description
The study is proposed to assess both surface water and well water quality status of the administrative divisions of Thrissur Corporation in the District of Thrissur, Kerala State. The study also focused on proposing most appropriate mitigation measures to improve the quality of both surface and ground water to ensure safe drinking water to the public. In addition the project also envisaged to assess the irrigation suitability of water in Kole wet lands as well. Planners and Decision makers can make use of this information for effective and sustainable management of water resources across the corporation area. The information will also help to develop reliable and more accurate scientific methods/technologies for planning the mitigation measures.
Officer in charge and contact details
Sudha M.S Superintending Engineer, Field Studies Circle, Thrissur. 9446402882
Present progress
Name of Work Assessment of Water Quality status (Surface water) and evolving mitigation measures to improve the Water Quality in Thrissur Corporation_ Operational
Date 12/09/2020
Physical Status Stage in %
Financial Status Stage in %
Description of Current status
Duration of study is 2018-2020. Vide minutes of the meeting of 8th R&D Session sub committee hasn't granted extension of the period of the study and informed to submit the final report. Hence the same is under preparation
Expected date of completion
95
General details
Name of Work
Assessment of Water Quality status (Surface water) and evolving mitigation measures to improve the Water Quality in Thrissur Corporation_ Operational
Division Hydrology division, IDRB
Administrative Sanction Order No, date, Amount
Order No. GO(MS)No.54/2016/WRD/ Thiruvananthapuram dated 0108-2016
Technical Sanction Order No, date, Amount
F.No. X-63016/1/2017-NHP/7426-7427 of Govt. of India MOWR NHP dated 04/12/2017
Agreement No and date -
Agreed Amount(In Rs) 30,00,000
Name of contractor -
Duration of study 2018-2020
Period of completion 3 Years
Description
The study is proposed to assess both surface water and well water quality status of the administrative divisions of Thrissur Corporation in the District of Thrissur, Kerala State. The study also focused on proposing most appropriate mitigation measures to improve the quality of both surface and ground water to ensure safe drinking water to the public. In addition the project also envisaged to assess the irrigation suitability of water in Kole wet lands as well. Planners and Decision makers can make use of this information for effective and sustainable management of water resources across the corporation area. The information will also help to develop reliable and more accurate scientific methods/technologies for planning the mitigation measures.
Officer in charge and contact details
Sudha M.S Superintending Engineer, Field Studies Circle, Thrissur. 9446402882
Present progress
Name of Work
Assessment of Water Quality status (Surface water) and evolving mitigation measures to improve the Water Quality in Thrissur Corporation_ Operational
Date 12/09/2020
Physical Status Stage in % 70%
Financial Status Stage in % 36%
Description of Current status
Duration of study is 2018-2020. Vide minutes of the meeting of 8th R&D Session sub committee hasn't granted extension of the period of the study and informed to submit the final report. Hence the same is under preparation
Expected date of completion March 2020
96
General details
Name of Work
Studies on saline ingression in selected river basins of Kerala and the impact/extend of sea water intrusion in the coast of Kerala state_ Operational
Division Hydrology division, IDRB
Administrative Sanction Order No, date, Amount
Order No. GO(MS)No.54/2016/WRD/ Thiruvananthapuram dated 01-08-2016
Technical Sanction Order No, date, Amount
F.No. X-63016/1/2017-NHP/1384-1395 of Govt. of India MOWR NHP dated 03/04/2018
Agreement No and date 01/SE,FSC/TSR/2019-20 dated 24/05/2019
Agreed Amount(In Rs) 1250000
Name of consultant Centre for Water Resourse Devolopment and Management ( CWRDM) Calicut
Site Handover Date -
Period of completion 3 years
Description
This project aims to study sea water intrusion in cost of Kerala State - Assessment of Impact and extend of Sea Water intrusion along 3 rivers of Kerala namely Kadalundi, Anjarakandi and Pallickal. Main objectives of the study are 1. Saline ingress study in the river system to identify the intensity, propagation of salinity during different months and extent of affected areas - Collection of water quality data from river at various points. 2.To identify suitable location for saline control structures and 3. To develop suitable River basin models using effective GIS software based on extent and intensity of saline ingress.
Officer in charge and contact details
Sudha M.S Superintending Engineer, Field Studies Circle, Thrissur. 9446402882
Present progress
Name of Work
Studies on saline ingression in selected river basins of Kerala and the impact/extend of sea water intrusion in the coast of Kerala state_ Operational
Date 12/09/2020
Physical Status Stage in %
97
Financial Status Stage in %
Description of Current status The study is progressing. 2 set of sampling completed
Expected date of completion 31/09/2022
98
General details
Name of Work
Studies on saline ingression in selected river basins of Kerala and the impact/extend of sea water intrusion in the coast of Kerala state_ Operational
Division Hydrology division, IDRB
Administrative Sanction Order No, date, Amount
Order No. GO(MS)No.54/2016/WRD/ Thiruvananthapuram dated 01-08-2016
Technical Sanction Order No, date, Amount
F.No. X-63016/1/2017-NHP/1384-1395 of Govt. of India MOWR NHP dated 03/04/2018
Agreement No and date -
Agreed Amount(In Rs) -
Name of contractor -
Site Handover Date -
Period of completion 3 years
Description
This project aims to study sea water intrusion in cost of Kerala State - Assessment of Impact and extend of Sea Water intrusion along 3 rivers of Kerala namely Kadalundi, Anjarakandi and Pallickal. Main objectives of the study are 1. Saline ingress study in the river system to identify the intensity, propagation of salinity during different months and extent of affected areas - Collection of water quality data from river at various points. 2.To identify suitable location for saline control structures and 3. To develop suitable River basin models using effective GIS software based on extent and intensity of saline ingress.
Officer in charge and contact details
Sudha M.S Superintending Engineer, Field Studies Circle, Thrissur. 9446402882
Present progress
Name of Work
Studies on saline ingression in selected river basins of Kerala and the impact/extend of sea water intrusion in the coast of Kerala state_ Operational
Date 12/09/2020
Physical Status Stage in % 20
Financial Status Stage in % Nil
Description of Current status The study is progressing. 2 set of sampling completed
Expected date of completion 2021
99
General details
Name of Work Procurement of Current meter with Accessories -Cup type
Division Hydrology division, Thrissur
Administrative Sanction Order No, date, Amount
Order No. GO(MS)No.54/2016/WRD/ Thiruvananthapuram dated 01-08-2016
Technical Sanction Order No, date, Amount -
Agreement No and date -
Agreed Amount(In Rs) -
Name of contractor -
Site Handover Date -
Period of completion -
Description
The work intented for the procurement of current meter which is used for measuring water velocity and thus discharge measurements in rivers and canals. It may be used in wading or suspended mode.
Officer in charge and contact details
Jiji M O, Executive Engineer, Hydrology Divivsion Thrissur 9446106634
Present progress
Name of Work Procurement of Current meter with Accessories -Cup type
Date 12/09/2020
Physical Status Stage in % LOA issued
Financial Status Stage in % Nil
Description of Current status LOA issued
Expected date of completion 31/12/2020
100
H Ongoing works under DRIP
Sl.no Name of Work
1 Construction of dam safety head quarters in PMG Trivandrum
2 Enabling ISW Hub in Palakkad with data interpretation centre and dam safety training facility phase I Interior furnishing ,landscaping ,setting up data interpretation centre ,ISW museum ,ISW documents library & archives
3 Enabling ISW Hub in Palakkad with data interpretation centre and dam safety training facility phase II-Construction of first floor and furnishing interior with necessary amenities
4 Rehabilitation and Improvement of basic facilities of Kanhirapuzha Irrigation Project - sub estimate for block joint treatment and spillway pier rehabilitation
5 Rehabilitation and Improvement of basic facilities of Kuttiyadi Irrigation Project- Civil Works
6 Rehabilitation and Improvement Of Basic facilities of Neyyar Irrigation Project (Civil Works)control room construction, renovation of stilling basin and internal roads,
7 DRIP - Supply Installation Testing Commissioning of instrumentation,software monitoring by dam along with required acessoriesand data collection for 5 years the comprehensive operation and maintenance with warranty of instrumentation for 16 dams under Irrigation department
8 DRIP- Electrical - Providing street lights in new bridge at Bhoothathankettu
9
Balance Civil Works - Rehabilitation and Improvement of Basic
Facilities of Parappar dam in Kallada Irrigation Project (Epoxy plastering , road work and applying tack coat )
Details are given in Appendix III
-
101
Appendix III- Details of Works under Plan Schemes
Abstract of Weekly Progress of H/A: 2701-80-005-92-00-00-00-P-V Modernisation of Hydrology Information System
1 Budget Allocation (Rs Lakhs) 350
2 Number of FS Issued 24
3 Total FS Amount (Rs Lakhs) 307.29
4 Number of AS Issued 23
5 Total AS Amount (Rs Lakhs) 212.79
6 Number of TS Issued 23
7 Total TS Amount (Rs Lakhs) 212.19
8 Number of Works Tendered 18
9 Total Tendered Amount (Rs Lakhs) 45.27
10 Number of Works Awarded 2
11 Total Tendered Awarded (Rs Lakhs) 4.40
12 Number of Completed Works 0
13 Number of Ongoing Works 2
14 Expenditure for 2020-21 (Rs Lakhs) 0.000
15 % Expenditure for 2020-21 w.r.t allocation for 2020-21 0
16 Total Expenditure up to date (including spillover) (Rs Lakhs) 0.753
17 % Expenditure up to date (including spillover) w.r.t allocation for 2020-21 0.22
102
Annual Plan 2020-21 - Weekly Progress Report
H/A:-
2701-80-005-92-00-00-00-P-V Modernisation of Hydrology Information System
Allocation of Rs 350 Lakhs
Sl. No.
Name of the Work/ Project
FS Amount/ Project Cost
(Rs. Lakhs)
AS Accorded
(Y/N) Date of AS
AS Amount*
(Rs. Lakhs)
TS Accorded
(Y/N) Date of TS
TS Amount*
(Rs. Lakhs)
Tendered or not (Y/N)
Date of Tender
Tendered Amount*
(Rs. Lakhs)
Awarded or not (Y/N)
Date of Awarding work
Awarded Amount* (Rs. Lakhs)
Stage of work
Completed (C) or
Ongoing (OG)
Expenditure* (Rs. Lakhs)
Expenditure %
Target date of
completion Remarks
Spill over works
1
Modernisation of HIS-Urgent maintenance work to the existing weir and installation of RLS at Kalkandiyoor
36.500 Y 02.12.2014 36.5 Y 18.10.2016 39 Y 18.10.2016 36.281115 Y 16.09.2019 36.28 OG
28.02.2021
The AS for the subject work was issued vide order No. 5032/2014/IDRB/INV/As/I&D1 Dated 2/12/2014 for an amount of Rs 36.50 Lakhs. The work was tendered and retendered but found no response. Subsequently the estimate was revised as per the prevailing cost index at that time and the work was retendered again vide e tender No01/S E/FSC/TSR/2016 dated 18.10.2016. Five bidders were responded and one of the bidder was not submitted the required EMD as he claims he is exempted from paying EMD as he is registered under National Small Scale Corporation Limited. The department was not convinced with his claim and not admitted his bid. The contractor challenge the same in the hon. High court and the judgement was honored in favour of the dept on 20.08.2019. Then the work was awarded to the lowest bidder on 16.09.2019. In Bhavani river lean flow is observed from Jan-May. Due to spill from Upper Bhavani dam and Covid 19, the work could not be done as per schedule. Now Work not yet started due to heavy flow in the Bhavani River
2 MHIS – Urgent maintenance works at Vithinassery (CGO) River Gauge Station
0.170 Y 17.07.2019 0.17 Y 17.07.2019 0.17 Y 25.09.2020 0.17 Y 04-11-20 0.15 OG
31.12.2020 Agreement Executed
3 MHIS – Urgent Repair Works to Vandazhi (CGO) River Gauge Station
0.170 Y 17.07.2019 0.17 Y 17.07.2019 0.04 Y 02.06.2020 0.04 Y 22.09.2020 0.04 C 0
29.09.2020 Work completed. Payment pending (Bill under preparation)
4 MHIS – Urgent maintenance works to Chittady (CGO) River Gauge Station
0.170 Y 17.07.2019 0.17 Y 17.07.2019 0.16 Y 25.09.2020 0.16 Y 04-11-20 0.14 OG
31.12.2020 Agreement Executed
5 MHIS – Maintenance of Hydrology Complex, Thrissur
19.100 Y 04.10.2019 19.1 Y 02.12.2019 19.1 Y 07.01.2020 19.1 Y 04-03-2020 15.88 C 0
22.10.2020 Work completed. Bill under preparation
6
MHIS-Procurement of Automatic Weather Station (AWS) at Chittoor – Attappady including chain link fencing to Attapapady Valley Irrigation Project (AVIP)
18.020 Y 17.08.2019 18.02 Y 09.01.2020 18.02 Y 24.07.2020 18.02 N
0.00
31.01.2021
Bid Evaluation. (Bid Opened on 27.08.2020, Three bids were received, Since the quoted amount is beyond the delegation of powers of this office, submitted to SE, FSC, TSR for approval.)
7
MHIS – Construction of equipment room of size 3.00 X 4.00 at Chittoor for Attappady Valley Irrigation Project
1.650 Y 18.07.2019 1.65 Y 18.07.2019 1.65 Y 02.06.2020 1.65 N
0.00
31.12.2020 It is informed that the euipments can be temporarily stored in the departmental office.
8
MHIS – Procurement of Current Meter with accessories, Sedimentation Sampler (Panjab Type) and filtration unit for Attappady Valley Irrigation
0.760 Y 18.07.2019 0.87 Y 18.07.2019 0.87 Y 07.11.2019 0.87 Y 07.01.2020 0.53 C 0.525 100
Completed.
9
Project (AVIP)
MHIS -Civil works for shifting of RLS from Karuvannur river gauge station to Palakkadavu CWC Station
0.700 Y 18.03.2020 0.7 Y 18.03.2020 0.7 Y 03.09.2020 0.7 N
0.00
0
31.12.2020 Work tendered several times, no response,
10 MHIS -Maintenance of AWS station at Cheerakuzhy
0.330 Y 18.03.2020 0.33 Y 18.03.2020 0.33 Y 03.09.2020 0.33 Y 15-10-2020 0.30 C 0
15.12.2020 Work completed. Bill under preparation
11 MHIS -Maintenance of AWS station at Vazhani
0.480 Y 18.03.2020 0.48 Y 18.03.2020 0.48 Y 03.09.2020 0.48 Y 19-10-2020 0.45 OG 0
30.10.2020 Agreement Executed.
103
12
MHIS- Maintenance of DWLR Including replacing battery at Manakkadavu under hydrology section Palakkad
0.230 Y 19.03.2020 0.23 Y 20.03.2020 0.23 Y 22.07.2020 0.23 Y 04.08.2020 0.22848 C 0.22848 100 03.09.2020 Work completed. Bill paid.
13
MHIS- Civil work for cable way at Manali river gauge station under Hydrology Section , Thrissur.
3.560 Y 20.03.2020 3.56 Y 6-11-2020 3.56 Y 6-11-2020 3.56 N
0.00
0
31.12.2020 Work Tendered on 6-11-2020,opening dt.1-12-2020.
14
MHIS – Construction of new river gauge station at Thonikadavu under Hydrology Section, Mananthavadi
3.150 Y 18.07.2019 3.15 Y 09.08.2019 3.15 Y 20.08.2020
( 8th attempt )
3.15 Y 20-10-2020 3.01 OG 0
31-1-2021 Agreement Executed.
15
MHIS – Construction of new rivr gauge station at Pulpally under Hydrology Section, Mananthavadi
3.850 Y 18.07.2019 3.85 Y 16.08.2019 2.9 Y 20.08.2020
( 7th attempt )
2.9 Y 20/10/2020 2.74 OG 0
31-01-2021 Agreement executed.
16
Construction of steps and walk way at Ambittanpotty river gauge Station under Hydrology section Manjeri.
2.500 Y 18.02.2020 2.5 Y 05.03.2020 2.5 Y 10.08.2020 2.5 Y
2.17
0
28.02.2021
Notice issued to the contractor L1 informing forfeitment of EMD and related procedures asper mannual if he is not executing the work.The work will be rearranged immediatly based on the response from L1.
17
MHIS-Repair works of Perinthalmanna, Pandikkad and Edakkara rain gauge stations under Hydrology section Manjeri, 2019
0.400 Y 18.03.2020 0.4 Y 19.03.2020 0.4 Y 26.08.2020 0.4 N
0.00
0
31.12.2020
No response from bidders till the 5th attempt. Now it will be executed with Kudumbasree units. Since the work is in 3 different panchayaths disscussion with the concerned agencies are in progress
18
Urgent repair of Punnapuzha river gauge station after flood under hydrology section Manjeri
4.970 Y 18.03.2020 4.97 Y 24.03.2020 4.97 Y 26.08.2020 4.97 Y 13.10.2020 4.36 OG 0
28.02.2021 Agreement executed on 13-10-2020 .work will commence immediately when water level subsides.
19
MHIS-Procurement of manual equipments for FCS stations under Hydrology section, Manjeri.
0.750 Y 24.03.2020 0.75 Y 15.07.2020 0.75 Y 10.08.2020 0.75 Y
0.58 OG 0
31.01.2021 Supply order issued on 03/11/2020.
20 MHIS - Instruments procurement for Mangattuparamba FCS
2.000 Y 14.02.2020 2 Y 04.03.2020 1.21 Y 15-07-2020
1.21 Y 07.09.2020 0.61
0
30.10.2020 Supply order issued to M/s Air Flow, Thiruvananthapuram, delay in transportation due to Covid 19 pandemic.
21 MHIS -Procurement of bridge outfit at Kannavam
0.700 Y 17.02.2020 0.7 Y 02.03.2020 0.7 Y 15-07-2020
0.7 Y 07.10.2020 0.57 OG 0
15.11.2020 Agreement executed
22
MHIS -Procurement of manual observation instruments for replacing obsolete instruments at FCS Vidyanagar
2.300 Y 14.02.2020 2.3 Y 04.03.2020 0.83 Y 15-07-2020
0.83 Y 07.10.2020 0.48 OG 0
30.10.2020 Agreement executed
23 MHIS -Supply and installing manual instruments at FCS Sheni
2.700 Y 14.02.2020 2.7 Y 14.07.2020 1.04 Y 15-07-2020
1.04 Y 07.10.2020 0.56 OG 0
30.10.2020 Agreement executed
24
MHIS -Civil work for installing manual instruments at FCS Sheni
1.900 Y 17.02.2020 1.9 Y 02.03.2020 1.9 Y 07.8.2020 1.9 N
0.00
0
31.12.2020 Bid Evaluation.
25
Urgent rectification to the hindrances to the shutter operation of the Pazhassi reservoir-Cutting removal and conveyance of damaged pipe and protection cage
0.150 Y 20.03.2020 0.15 Y 20.03.2020 0.15 Y 07.8.2020 0.15 Y 17-09-2020
0.11 C 0
15.10.2020 Bill for the amount of 13614/-is under scrutiny.
of DWLR installed at Pazhassi reservoir under
26
Urgent repair works at Kakkadavu river gauge station under hydrology section Payyannur for the year 2019 20
0.070 Y 20.03.2020 0.07 Y 20.03.2020 0.07 Y 13.08.2020 0.07 Y 17-09-2020
0.04 C 0
15.10.2020 Bill for the amount of 4810/- is under scrutiny.
27
Urgent repair works at Bheemanady river gauge station under hydrology section Payyannur for the year 2019 - 20
0.070 Y 20.03.2020 0.07 Y 20.03.2020 0.07 Y 13.08.2020 0.07 Y 17-09-2020
0.03 C 0
15.10.2020 Bill for the amount 4836/-is under scrutiny.
28
Urgent repair works at Vellur river gauge station under hydrology section Payyannur for the year 2019 20
0.050 Y 20.03.2020 0.05 Y 20.03.2020 0.05 Y 13.08.2020 0.05 Y 17-09-2020
0.03 C 0
15.10.2020 Bill for the amount 3212/-is under scrutiny.
29
Urgent repair works at Mangara river gauge station under hydrology section Payyannur for the year 2019 20
0.050 Y 20.03.2020 0.05 Y 20.03.2020 0.05 Y 13.08.2020 0.05 N
0.00
0
Supply order issued.
104
30
MHIS- Shifting of Mangattuparamba FCS to new location under Hydrology section, Thalassery 2019-20
5.500 Y 20.03.2020 5.5 Y 20.03.2020 5.5 Y 13.08.2020 5.5 N
0.00
0
31.12.2020 Bid Evaluation.
31
MHIS – Supply and Erecting Gauge Post at various Seasonal River Gauge Stations under Hydrology Section, Kottayam for 2019-20.
0.146 Y 29-07-2019 0.1462 Y 06-08-2019
0.1462 Y 31.01.2020 0.1462 Y 05-03-2020
0.15 OG 0
31.03.2021 Work is not yet completed due to high water level. Scales can be fixed only after water level recedes.
32
MHIS – Procurement of Manual Observation Equipments for Kalady Temperature Stations, under Hydrology Section, Aluva for the period 2019-20.
0.106 Y 29-07-2019 0.106 Y 06-08-2019
0.106 Y 29.09.2020 0.106 N
0.00
0
31.03.2021
Work tendered thrice, no responses. Quotation was invited for which single tendered was received but cancelled as the quoted rate is 35% above than the estimate amount. Quotation invited on 29.09.2020.But no response from contractors.Re tender will be invited soon.
33
MHIS – Procurement of Manual Observation Equipment for the proposed FCS Bhoothathankettu under Hydrology Section, Aluva for the period 2018-19
1.621 Y 29-07-2019 1.621 Y 06-08-2019
1.621 Y 03.03.2020 1.621 N
0.00
0
31.03.2021 Selection notice cancelled
34
MHIS – Procurement of Manual Observation Equipment for the Malankara FCS Station under Hydrology Section, Muvattupuzha for the period 2018-19
1.621 Y 22/08/2019, 1.621 Y 24-08-2019
1.621 Y 03.03.2020 1.621 N
0.00
0
31.03.2021 Selection notice cancelled
35
MHIS – Maintenance of CGO (State Fund) Stations under Hydrology Section No.2, Chengannur
0.056 Y 22/08/2019, 0.056 Y 28-09-2020
0.04797 Y 30.10.2020 0.04646 N
0.00
0
31.03.2021 Retendered on 30.10.2020,opening date 12.11.2020. No response
36
MHIS – Maintenance of CGO Stations under Hydrology Section No.1, Chengannur
0.250 Y 22/08/2019, 0.25 Y 28-09-2020
0.21936 Y 30.10.2020 0.21885 N
0.00
0
31.03.2021 Retendered on 30.10.2020,opening date 12.11.2020. No response
37 MHIS – Connecting MSL of stations under Hydrology Section No.1, Chengannur
0.953 Y 19-07-2019 0.953 Y 21-08-2019
0.83124 Y 30.10.2020 0.83124 N
0.00
0
31.03.2021 Work tendered thrice. Re-Quotation invited on 30.10.2020. opening date 12.11.2020. No response
38
MHIS – Modernisation of Hydrology Information System, Estimate for Steel Structural roofing, repainting and repair works in Hydrology Division Office,
12.500 Y 12-03-2019 12.5 Y 13-12-2019
12.5 Y 19.02.2020 12.5 Y 23/3/2020 12.25 C 0 100
Work completed. Bill submitted
Chengannur
39
MHIS –Maintenance of Anayadi River Gauge (CGO) Station under Hydrology Section, Adoor
0.337 Y 12-03-2019 0.319 Y 21-08-2019
0.2775 Y 14.10.2020 0.2775 N
0.00
0
31.03.2021 Single Quatation received
40
MHIS – Maintenance of Punalur River Gauge (CGO) Station under Hydrology Section, Adoor for the Financial Year 2019-20
0.354 Y 12-03-2019 0.336 Y 21-08-2019
0.29275 Y 30.10.2020 0.29275 N
0.00
0
31.03.2021 Work tendered thrice. Re-Quotation invited on 30.10.2020. opening date 12.11.2020. No response
41 MHIS – Modernisation of Vamanapuram gauging stations – State Fund
7.105 Y 18-07-2019 7.105 Y 25-02-2020
6.485 Y 28.09.2020 4.45074 N
0.00
0
31.03.2021 Work tendered several time.Re tendered on 28.09.2020.But no response from contractors .Re tender will be invited soon
Total 137.999 41
138.073 41
134.698 41
129.943 22
81.66 10 0.753
Completed
Works of 2020-21
1
Modernization of Hydrology :Maintenance of river gauge station at Uppala under Hydrology section Kasaragod for the year 2020-21
0.340 Y 10.08.2020 0.340 Y 25.08.2020 0.340 Y 17.09.2020 0.340 N
31.03.2021 work retendered on 04.11.20, opening 13.11.2020. No response from contractors
2
MHIS - Maintenance of River gauge stations of Shiriya U/S & D/S under Hydrology section
0.310 Y 10.08.2020 0.310 Y 25.08.2020 0.310 Y 17.09.2020 0.310 N
31.03.2021 work retendered on 04.11.20, opening 13.11.2020. No response from contractors
105
Kasaragod for the year 2020-21
3
MHIS- Civil works for establishing Bench marks in all the river gauge sites under Hydrology Section, Payyannur 2020-21
0.240 Y 25.08.2020 0.240 Y 25.08.2020 0.240 Y 17.09.2020 0.24 N
31.03.2021 work retendered on 04.11.20, opening 13.11.2020. No response from contractors
4
MHIS- Civil work for Establishing Bench mark in River gauge stations under Hydrology Section, Kasaragod for the year 2020-21
0.360 Y 24.08.2020 0.360 Y 25.08.2020 0.360 Y 17.09.2020 0.36 N
31.03.2021 work retendered on 04.11.20, opening 13.11.2020. No response from contractors
5
MHIS- Maintenance of Meteorological stations under Hydrology Section, Payyannur for the year 2020-21
0.350 Y 25.08.2020 0.350 Y 25.08.2020 0.350 Y 17.09.2020 0.35 N
31.03.2021 work retendered on 04.11.20, opening 13.11.2020. No response from contractors
6
MHIS - Repair and Maintenance of Vanimel river gauge Cable way station - Mechanical work
8.960 Y 16-09-2020 8.960 Y 29.09.2020 8.780 N
0 N
31.03.2021
TS obtained for the work from AEE, Irrigation Mechanical Sub Division Kannur.Tendering will be done after lifting model code of conduct.
7
MHIS - civil works for establishing Bench marks in all river gauge sites under Hydrology Section, Thalassery 2020-21
0.310 Y 25.08.2020 0.310 Y 25.08.2020 0.310 Y 17.09.2020 0.31 N
31.03.2021 work retendered on 04.11.20, opening 13.11.2020. No response from contractors
8
Modernization of Hydrology: Maintenance of River gauge stations of Madhur and Padiyathadukka under Hydrology section Kasaragod for the year 2020-21
1.120 Y 15-10-2020 1.120 Y 04.11.20 1.120 N
0 N
TS issued .Tendering will be done after lifting model code of conduct.
9
MHIS- Renovation of Kollikkal river gauge station under Hydrology Section Kozhikode -Hydrology subdivision Kozhikode
8.200 Y 16.09.2020 8.200 Y 23.09.2020 8.2 Y 6-10-2020 8.2 N
Selection notice issued on 09-11-2020.Execution of Agreement will be done after lifting model code of conduct.
10
MHIS- Renovation of Panamaram river gauge station under hydrology section Mananthavady - Hydrology sub division Kozhikode
14.000 Y 16.9.2020 14.000 Y 23.09.2020 14 Y 8-10-2020 14 N
Etender extended to 13-11-2020 with opening dt.19-11-2020.
11
MHIS- Renovation of Koodathai river gauge station under Hydrology section Kozhikode
11.570 Y 16.9.2020 11.570 Y 23.09.2020 11.570 Y 8-10-2020 11.57 N
Bid evaluation
12 MHIS- Renovation of Hydrology sub division Data centre Kozhikode
43.000 N
N
N
N
Application for permission of construction rejected by Kozhikode Corporation, revised estimate will be submitted within one week.(Estimate for Electrical and furniture supply to be obtained from PWD and SIDCO respectively)
13
MHIS - Maintenance of Raingauge station at Teekoy under Hydrology Section Mundakkayam - 2020-21
0.140 Y 12.09.2020 0.140 Y 18.09.2020 0.140 Y 28.10.2020 0.12242 N
31.03.2021 Retender Notice Published on 28.10.2020 with opening date on 13/11/2020 No response.
14
MHIS - Shifting of Manimala River Gauge Station under Hydrology Section Mundakkayam -2020-21
0.225 Y 12.09.2020 0.225 Y 18.09.2020 0.225 Y 28.10.2020 0.20022 N
31.03.2021 Retender Notice Published on 28.10.2020 with opening date on 13/11/2020 No response.
15
MHIS - Renovation of Teekoy River Gauge Station under Hydrology Section Mundakkayam - 2020-21
1.820 Y 12.09.2020 1.82 Y 01.10.2020 1.61 Y 28.10.2020 1.61169 N
31.03.2021 Retender Notice Published on 28.10.2020 with opening date on 13/11/2020 No response.
16 MHIS-Maintenance of Office Building-Hydrology Section,Aluva-2020-2021
3.110 Y 12.09.2020 3.11 Y 18.09.2020 3.11 Y 18.09.2020 2.77655 Y 09.10.2020 2.77 OG
31.03.2021 agreement excecuted, Agreement No.21/AEE/KTM/202021,Dated:23/10/2020
17
MHIS-Shifting of Marthandavarma River Gauge Station-Hydrology Section-Aluva-2020-2021
1.830 Y 12.09.2020 1.83 Y 18.09.2020 1.83 Y 18.09.2020 1.63005 Y 09.10.2020 1.63 OG
31.03.2021 Work started.
106
18
MHIS- Renovation of Pala river gauge under Hydrology section, Kottayam for 2020-21
1.250 Y 12.09.2020 1.25 Y 01.10.2020 1.04 Y 28.10.2020 1.04 N
31.03.2021 Retender Notice Published on 28.10.2020 with opening date on 13/11/2020 No response.
19
MHIS- Reconstruction of damaged portion of compound wall construction of hump at entrance and exit gates of Jala Vijnjana Bhavan, Thriuvananthapuram.
5.600 Y 16.10.2020 5.600 Y 16.11.2020 5.600 N
0.00 N
TS issued on 16-11-2020.
20 MHIS- Connecting MSL and establishing BM stones at Kalleli gauging station
0.300 Y 23-10-2020 0.30 Y 28-10-2020
0.30 Y 02.11.2020 0.21547 N
Tendered on 02.11.2020 , Opening date 13.11.2020 No response.
21
MHIS- Connecting MSL and establishing BM stones at Punalur and Anayadi gauging station
0.670 Y 23-10-2020 0.67 Y 28-10-2020
0.67 Y 02.11.2020 0.49469 N
Tendered on 02.11.2020 , Opening date 13.11.2020 No response.
22
MHIS - Supplying and installation of Manual observation equipments for the proposed Fully Climatic Station at Kozha under Hydrology Section , Kottayam.
1.900 Y 15-10-2020 1.90 Y 12-11-2020
1.90 N
0.00 N
TS issued on 12-11-2020.
23
MHIS- Civil work for proposed Fully Climatic Station at Kozha under Hydrology Section , Kottayam for 2020-21
1.680 Y 15-10-2020 1.68 Y 06-11-2020
1.68 Y 06-11-2020
1.49958 N
Tendered on 06.11.2020 , Opening date 24.11.2020
24
Procurement of high-resolution Digital Elevation Model (DEM) and Real Time Hydro-Met equipments for establishing an effective Flood Forecasting & Early Warning System (FFEWS) for Periyar River Basin
200.00 Y 21-10-2020 148.50 Y 28-10-2020
148.50 N
0.00 N
Procurement of high resolution Digital Elevation Model for Rs 148.5 lakhs (exclusive of taxes). AS accorder vide G.O.(Rt)No.663/2020/WRD dt 21/10/2020. TS issued on 28-102020. Procurement of DEM will be initiated under the guidance of NRSC, Hyderabad.
Total 307.285 23
212.785 23
212.188 18
45.272 2
4.40 0 0.000
Grand Total of 2019-20 and 2020-21
445.284 64
351 64
347 59
175 24
86 10 0.75 0.15
Abstract of Weekly Progress of H/A: 2701-80-005-93-00-00-00-P-V Modernisation of Design Wing
1 Budget Allocation (Rs Lakhs) 150
2 Number of FS Issued 21
3 Total FS Amount (Rs Lakhs) 26.76
4 Number of AS Issued 18
5 Total AS Amount (Rs Lakhs) 91.01
6 Number of TS Issued 8
7 Total TS Amount (Rs Lakhs) 5.87
8 Number of Works Tendered 8
9 Total Tendered Amount (Rs Lakhs) 0.33
10 Number of Works Awarded 4
11 Total Tendered Awarded (Rs Lakhs) 41.71
12 Number of Completed Works 2
13 Number of Ongoing Works 4
14 Expenditure for 2020-21 (Rs Lakhs) 20.05
15 % Expenditure for 2020-21 w.r.t allocation for 2020-21 80.98
16 Total Expenditure up to date (including spillover) (Rs Lakhs) 42.20
17 % Expenditure up to date (including spillover) w.r.t allocation for 2020-21 39.34
108
H/A:-
2701-80-005-93-00-00-00-P-VM odernisation of Design Wing Allocation of Rs 150 Lakhs
Sl. No.
Head of Account/ Name of the Project
FS amount/Project Cost ( Rs. Lakhs)
AS Accorded
(Y/N)
Date of AS
AS Amount*
(Rs Lakhs)
TS Issued (Y/N)
Date of TS TS
Amount* (Rs Lakhs)
Tendered or not
(Y/N)
Date of Tender
Tendered Amount*
(Rs Lakhs)
Work Awarded
(Y/N)
Date of Awarding work
Awarded Amount* (Rs Lakhs)
Work Status:
Completed (C) or
Ongoing (OG)
Expenditure* (Rs Lakhs)
Expenditure % Target date
of completion
Remarks
WORKS OF 2020-2021
IDRB office
1
Office activities in IDRB ( Maintenance of Computer, printer photocopier etc. training and seminar, purchase of software, electrification and furniture for library)
0.00 Y 22.07.2020 53.6 TS not required
NA 0 NA NA 0 NA NA 12.65 OG 12.65 23.60 31.03.2021 Order No.DM-AD2/5/2015-IDRB dtd 22.07.2020.Payment as per the bill
2 Electrification -Renovation of library and ladies rest room in IDRB
0.00 Y 08.10.2020 7.4 Deposit work
NA 0 NA NA 0 NA NA 7.4 C 7.4 100 31.03.2021
Order No.DM-AD6/25/2019/IDRB dtd 08.10.2020.An amount of Rs.7.4 lakhs deposited to AEE,PWD,electrical wing as per the estimate submitted.
Capacity Building for Design Engineers
3
Consultancy service for issuing structural design and drawings for the construction of double lane skew bridge without footpath across Varattar river at Thrikkayyilkadavu
0.00 Y 06.09.2019 4.5 NA NA 0 Y 03.03.2020 4.5 Y 27.05.2020 4.5 OG 0 0 31.03.2021
Order No.DAMS-AD1/1/2019-IDRB dtd 29.06.2020.An amount of Rs.4.5 lakhs awarded to Associated Structural Consultants,'Souparnika,Kochi
4
Consultancy services for issuing structural design and drawings for the construction of Arch bridge at Vanchipottilkadavu across Varattar River and capacity building of design engineers
0.00 Y 06.09.2019 9.5 NA NA 0 Y 03.03.2020 9.5 Y 14.08.2020 9.5 OG 0 0 31.03.2021
Order No.813/IDRB/DAMS/AD2/1987/Vol VI/Part File 1/1 dtd 24.08.2020.An amount of Rs.9.5 lakhs awarded to Associated Structural Consultants,'Souparnika,Kochi
3
Consultancy Services for Structural Design of Bridges and Capacity Building for Design Engineers
0.00 NA NA 0 NA 0 Y Retendered
on18.04.2020 7.35 Y 14.08.2020 7.35 OG 0 0 31.03.2021
Order No.813/IDRB/DAMS/AD2/1987/Vol VI/Part File 1/2 dtd 24.08.2020.An amount of Rs.7.35 lakhs awarded to Associated Structural Consultants,'Souparnika,Kochi
Total 0.00 4 75 0 3 3 41.4 4(OG)1(C) 20.05
Quality Control Division,Kottarakkara
5
Modernisation of Design Wing - PurchasingComputer and Printer for Subdivision and secction offices at Alappuzha and Pathanamthitta.
1.81 Y 28.09.2020 1.81 N Nil 0 N Nil 0 N Nil 0 Refer remarks
0 0 30.01.2021 T.S to be issued by the AEE
6
Hiring of vehicle for Irrigation Quality Control Section Pathanamthitta for the Year 2020-2021
1.50 Y 30.09.2020 1.50 Y 08.10.2020 1.50 Y Refer remarks 0 N Nil 0 Refer remarks
0 0 31.03.2021
Re-Quotation date extented to 17.12.2020 due to declaration of
Election
7
Hiring vehicle for QC Section Idukki under Quality Control Sub Division Kottayam
1.00 Y 30.09.2020 1.00 Y 12.10.2020 1.00 Y Refer remarks 0 N Nil 0 Refer remarks
0 0 31.03.2021
Re-Quotation Invited on 05.11.2020 and the same will be
opened on 17.11.2020
8
Hiring of vehicle for Irrigation Quality Control Subdivision and Section, Alappuzha
1.50 Y 30.09.2020 1.50 Y 08.10.2020 1.50 Y Refer remarks 0 N Nil 0 Refer remarks
0 0 31.03.2021
Re-Quotation date extented to 17.12.2020 due to declaration of
Election
9 Hiring vehicle for Quality Control Sub Division Kottayam
1.00 Y 30.09.2020 1.00 Y 12.10.2020 1.00 Y Refer remarks 0 N Nil 0 Refer remarks
0 0 31.03.2021 Re-Quotation Invited on
05.11.2020 and the same will be opened on 17.11.2020
10 Purchase of office (lab) equipments for Kottayam
0.80 N 0 N 0 N 0 N 0 Refer remarks
0 0 Nil A.S. to be Issued by the EE
11 Purchase of office furniture for Quality control sub division Kottayam
0.57 N 0 N 0 N 0 N 0 Refer remarks
0 0 Nil A.S. to be Issued by the EE
12 Modernisation of design wing - furniture procurement for quality control lab at Kottarakkara
1.73 N
0 N
0 N
0 N
0 Refer remarks
0 0 Nil A.S. to be Issued by the EE
109
13
Modernisation of design wing - purchasing furniture for irrigation quality control subdivision alappuzha and section offices at Alappuzha And Pathanamthitta
0.65 N
0 N
0 N
0 N
0 Refer remarks
0 0 Nil A.S. to be Issued by the EE
Total 10.56 5 - 6.81 4 - 5.00 4 - 0 0 - 0 0 0 - -
Quality Control Division,Thrissur
14
2020/165/IDRB Modernisation of Quality control wing under Irrigation DepartmentPhase III at Thrissur-Calibration charge for CTM
0.33 Y 22.09.2020 0.33 Y 29.9.2020 0.33 Y 05.10.2020 0.33 Y 23.10.2020 0.31 C 0 0 23.11.2020 work completed.Bill under preparation
15
2020/225/IDRB calibration of Compression testing Machine placed in the Lab at Angamaly for the year 20202021
0.12 Y 20.10.2020 0.12 Y 21.10.2020 0.12 N Nil 0 N Nil 0 Refer remarks
0 0 Nil TS Issued by AEE . Work Arrangement in Progress
16
2020/224/IDRB Calibration of Compression Testing machines placed in the lab at Koothattukulam for the year 2020-21
0.12 Y 21.10.2020 0.12 Y 21.10.2020 0.12 N Nil 0 N Nil 0 Refer remarks
0 0 Nil TS Issued by AEE . Work Arrangement in Progress
17
2020/250/IDRB Hiring charges of vehicles for QC section No.1, Muvattupuzha for the year 2020-21
2 Y 18.11.2020 2 N Nil 0 N Nil 0 N Nil 0 Refer remarks
0 0 Nil AS Issued. TS to be issued
18
2020/239/IDRB Hiring charges of vehicles for QC section No.2 ,Koothattukulam for the year 2020-21.
2 Y 18.11.2020 2 N Nil 0 N Nil 0 N Nil 0 Refer remarks
0 0 Nil AS Issued. TS to be issued
19 2020/258/IDRB Hiring charges of Vehicles for QC Section no. 3, Angamaly for the year 2020-21
1.98 Y 18.11.2020 1.98 N Nil 0 N Nil 0 N Nil 0 Refer remarks
0 0 Nil AS Issued. TS to be issued
20
2020/150/IDRB Irrigation Quality Control section Kozhikode-Hiring of vehicles for site inspection and sample collection
2 N Nil 0 N Nil 0 N Nil 0 N Nil 0 Refer remarks
0 0 Nil FS Issued .AS to be issued by EE
21 2020/152/IDRB Modernisation of Quality control wing - Maintenance of quality control lab at kozhikode
0.3 Y 13.11.2020 0.3 Y 16.11.2020 0.3 N Nil 0 N Nil 0 Refer remarks
0 0 Nil TS issued Tender activities in progress
22
2020/249/IDRB Name of work : Irrigation Quality Control section Wayanad - Hiring of vehicles for site inspection and sample collection
2.00 N Nil 0 N Nil 0 N Nil 0 N Nil 0 Refer remarks
0 0 Nil FS Issued .AS to be issued by EE
23
2020/235/IDRB Modernisation of Quality control wing under Irrigation DepartmentPhase III at Thrissur-Maintenance of Laboratary equipments .
0.35 Y 30.10.2020 0.35 N Nil 0 N Nil 0 N Nil 0 Refer remarks
0 0 Nil AS Issued. TS to be issued by
AEE
24 2020/318/IDRB Hiring vehicle for Irrigation Quality Control Sub Division Kannur-2020-21
3 N Nil 0.00 N Nil 0 N Nil 0 N Nil 0 Refer remarks
0 0 Nil FS Issued .AS to be issued by EE
25
2020/199/IDRB Hiring of Vehicle for Irrigation Quality Control Section, Ernakulam at Aluva for period of 12 months2020-21
2 Y 18.11.2020 2 N Nil 0 N Nil 0 N Nil 0 Refer remarks
0 0 Nil AS issued
Total 16.198 9 9.198 4 0.87 1 0.33 1 0.31 1(C) 0 0
Grand total 20-21 KERI Peechi 26.76 18 91.01 8 5.87 8 0.33 4 41.71 4(OG) 2(C) 20.05 0
Grand total 26.76 18 91.01 8 5.87 8 0.33 4 41.71 4(OG) 2(C) 20.05 0
WORKS OF 2019-2020
Quality Control Division,Kottarakkara
1
Purchase of Compression Testing Machine and Electrification work for Quality Control Lab at Kottarakara section
7.10 Y 20-3-2020 7.10 Y 14.10.2020 7.10 Y 02.11.2020 6.01 N Nil 0 Refer Remarks
0 0 31.01.2021
Tender Notice published on 02.11.2020 and the same will be
opened on 17.11.2020
2 Hiring of vehicle for QC sub division , Kottayam
2.00 Y 22-11-2019
2 Y 28.12.2019 2 Y 15.01.2020 2 Y 10.02.2020 1.99 C 1.1860 59.60 31.07.2020
Completed on 31.07.2020 Payment details - Rs.84590-09/05/2020, Rs.34008-16/08//2020, Total Paid Rs.118598/-
3 Hiring of vehicle for QC sub division , Alappuzha
2.00 Y 22-11-2019
2 Y 28.12.2019 2 Y 24.01.2020 2 Y 29.02.2020 1.9 C 0.9440 49.68 31.08.2020
Completeed on 31.08.2020. Payment details-Rs.30000-09/05/2020, Rs.18532-19/06/2020, Rs.18227-01/07/2020, Rs-7813-16/08/2020, Rs.19824-22/09/2020, Total-Rs.94,396/-
110
4 Setting up of quality control lab- Electrification work of the quality control lab at Kottarakkara
2.35 Y 25-01-2020
2.35 Y 25.01.2020 2.35 Y deposit work 2.35 Y deposit work
2.35 C 2.35 100 28.06.2020 Completed on 28.06.2020.
Expenditure at IDRB
Total 13.45 4 13.45 4 13.45 4 12.36 3 6.24 3(C) 4.48
Quality Control Division,Thrissur
1
H/A - 2701-80-005-93-00-00- 2019/421/IDRB Modernization of design wing/ Procuring Computer and Accessories for the functioning of the Quality Control Sub Division, Kannur, new quality control lab & section offices
1 Y 22.11.2019 1 Y 06.01.2020 1 Y 01.01.2020 0.95 Y 09.06.2020 0.95 C 0.95158 100 Work completed
Purchase order approved by Keltron
Vide Order No. 13036, Dated.,09/06/2020. The amount Rs.95158/- paid by CE, IDRB,
Tvm. Desktop supplied yet. The printer to be supplied.
2
2019/422/IDRB Modernization of design wing - Hiring vehicle for Irrigation Quality Control Sub Division, Kannur.
1 Y 11.10.2019 1 Y 22.11.2019 1 Y 06.01.2020 1 Y 13.01.2020 1 C 0.16587 16.59 16.03.2020
The Agreement is expired on 15/08/2020. So far Rs.16,587/-has
been spend as the charges.An amount of
Rs.10920.00 is pending for the remaining period. Total Value of
work done - Rs.27,507/-
3
2018/203/IDRB Modernisation of Quality Control wing under irrigationDepartment Phase III at Thrissur-(Building)
13.85 Y 01.03.2018 13.85 Y 05.10.2018 13.85 Y 20.10.2018 13.85 Y 21.11.2018 14.82 C 5.33616 44.73 Work completed
4.3.2020
Part bill paid on 30.9.2020. Payment pending in EMLI for Rs
9.48924
4
ModernisationSetting up of Irrigation quality Control lab in Thrissur- Electrification works
2.95 Y 01.03.2018 2.95 Y 22.06.2018 2.95 Y 05.12.2018 2.95 Y 1.04.2019 2.93 C 0 0.00%
Work completed
on 14.10.2019
Work completed. Payment pending in
EMLI for Rs 2.92866
5
2017/110/IDRB Modernisation of Quality Control wing under irrigation Department Phase III at Thrissur- APPENDIX III Machineries and Euipments Riffle sample divider, seive shaker, vicat apparatus, cubical mould, vernier calipper,Le- chatlier apparatus, weighing balance, stop watch etc.
4.40 Y 1.03.2018 4.40 Y 12.06.2019 4.40 Y 01.01.2020 4.40 Y 24.02.2020 4.31 C 0 0.00% 29.08.2019 Work completed. Requested for
fund
6
2019/194/IDRBModernisation of Quality Control wing under irrigation Department - Phase III at Thrissur- APPENDIX III Machineries and Euipments Rebound hammer
3.75 Y 01.03.2018 3.75 Y 12.06.2019 3.75 Y 16.10.2019 3.54 Y 20.01.2020 3.54 OG 0 0 28.09.2020 Machine supplied Bill under
scrutiny
7
2019/199/IDRBModernisation of Quality Control wing under irrigation Department - Phase III at Thrissur- APPENDIX III Machineries and Euipments -(8) Pyconometer, specific gravitybottle, copaction test apparatus, soil cone penetrometer, sand replacement etc.
1.52 Y 01.03.2018 1.52 Y 12.06.2019 1.52 Y 01.01.2020 1.52 Y 20.01.2020 1.16 C 0 0 26.8.2020 Work completed.Fund requested
8
2019/378/IDRBModernisation of Quality Control wing under irrigation Department -Phase III at Thrissur- APPENDIX III Machineries and Euipments -(10)
Vibrating machine with degital timer
0.54 Y 01.03.2018 0.54 Y 24.09.2019 0.54 Y 01.01.2020 0.54 Y 20.01.2020 0.27 C 0 0 19.06.2020 Work completed.Fund Requested on 19.10.2020
9
2019/266/IDRB Procurement of computer and allied accessories for quality control sub division Thrissur ,
new quality control lab & section offices
2 Y 14.11.2019 2 Y 29.11.2019 2 N Nil 0 N N 0 OG 0 0 31.03.2021 New invoice to be submitted from
CPRCS. Due to lockdown payment could not be made.
10 2019/414/IDRBHiring vehicle for Irrigation Quality Control Section
Aluva. 1 Y 22.11.2019 1 Y 28.12.2019 1 Y 17.01.2020 0.99 Y 23.03.2020 0.99 OG 0.29860 30 31.03.2021
work in progress 2nd Time extension applied for 22.11.2020. Ist part bill-
Rs.8705 paid as on 30.06.2020 IInd &III rd part bill-Rs.13670 & Rs.7485 paid as on 12.10.2020 Fund requested for Rs
0.28745 on 19.10.2020
11 2018/246/IDRBIrrigation
Department-Preparation of Irrigation Quality control Manual
2018 3.5 Y 01.3.2018 3.5 Y 03.03.2019 3.5 NA NA 0 NA NA 0 OG 0 0 31.03.2021
Draft manual prepared.Further discussion needed
12
2018/240/IDRB Modernisation of Quality Control wing under irrigation Department -Phase III at Thrissur- APPENDIX III Machineries and Euipments - Automatic Compression Testing Machine
6.32 Y 3.3.2019 6.32 Y 01.05.2019 6.32 Y 01.05.2019 5.15 Y 1-6-2019 5.15 C 5.15094 100 29.8.2019 Work completed Payment done on 8-10- 2020
111
13
2019/387/IDRB Modernisation of Quality Control wing under irrigation Department -Phase III at Thrissur- APPENDIX IV Miscellanious items-Furnture, storage facilites etc.
1.59 Y 01.03.2018 1.59 Y 24.09.2019 1.59 Y 23.10.2019 1.59 Y 20.01.2020 1.59 C 1.58834 100 20.05.2020 Work completed .final bill paid on 30-07 2020
14 Electrificationof MVIP Quality Control Lab at Koothattukulam including errection and callibration of Compression Testing Machine
0.72 Y 7 .2 .2019 0.72 Y 22 .2 .2019 0.72 Y 6 .3 .2019 0.4 Y 18.3.2019 0.38 C 0.331790 100 30.3.2019 Work completed .Bill paid on 25-092020.
15
2018/248/IDRB Modernisation of Quality Control wing under irrigation Department -Phase III at Thrissur- APPENDIX III Machineries and Euipments -6 Cutting Machine and Cutting saw
4.69 Y 01.03.2018 4.69 Y 12.06.2019 4.69 Y 01.01.2020 4.69 Y 20.01.2020 3.37 C 3.36090 100 03.07.2020 Work completed Payment done on 29- 09-2020
16 2019/265/IDRB Hiring vehicle for Irrigation Quality Control Section Thrissur
1.00 Y 22.11.2019 1.00 Y 28.12.2019 1.00 Y 24.01.2020 0.991 Y 06.03.2020 0.991 C 0.48805 100% 5.9.2020 Work completed .final bill paid on
12.10.2020
Total 49.83 16 49.83 16 49.83 14 42.56 14 41.45 12(C)4(OG) 17.67223
JD CM &FE KERI ,Peechi, (Division Office)
Construction Material Division (Sub Division office)
18 Updation of old electrical wiring in Construction Materials Lab to meet NABL requirements
11.5 Y 29.01.2020 11.5 Y 03.03.2020 11.5 Y 28.07.2020 10.26 Y 04.11.2020 11.27 Refer Remarks 0 0 30.01.2021 Selection notice issued 04.11.20
Soil Mechanics & Foundation Division (Sub Division office)
19 Upgradation of electrical works of Soil Mechanics Lab for NABL accreditation
7.75 Y 19.02.2020 7.75 Y 03.03.2020 7.75 Y 05.03.2020 6.72 Y 14.08.2020 7.32 C 0 0 31.10.2020 Work Completed .bill to be prepared by electrical wing.
Total 19.25 2 19.25 2 19.25 2 16.98 2 18.60 1(C) 0 0
Grand Total 19-20 KERI,Peechi 82.53 22 82.53 22 82.53 20 71.91 19 66.28 16(C)4(OG) 22.15
Grand total of 2020-2021 26.76 18 91.01 8 5.87 8 0.33 4 41.71 2(C)4(OG) 20.05 74.93
Grand total of 2019-2020 82.53 22 82.53 22 82.53 20 71.91 19 66.28 16(C)4(OG) 22.15
Grand total 109.29 40 173.54 30 88.40 28 72.24 23 107.99 18(C) 8(OG) 42.20 38.62%
112
Abstract of Weekly Progress of H/A: 2701-80-800-92-00-00-00-P-V Dam Safety Organisation & Dam Safety Measures
1 Budget Allocation (Rs Lakhs) 10
2 Number of FS Issued 0
3 Total FS Amount (Rs Lakhs) 0
4 Number of AS Issued 0
5 Total AS Amount (Rs Lakhs) 0
6 Number of TS Issued 0
7 Total TS Amount (Rs Lakhs) 0
8 Number of Works Tendered 0
9 Total Tendered Amount (Rs Lakhs) 0
10 Number of Works Awarded 0
11 Total Tendered Awarded (Rs Lakhs) 0
12 Number of Completed Works 0
13 Number of Ongoing Works 0
14 Expenditure for 2020-21 (Rs Lakhs) 0.07049
15 % Expenditure for 2020-21 w.r.t allocation for 2020-21 0.7049
16 Total Expediture up to date (including spillover) (Rs Lakhs) 0.07049
17 % Expenditure up to date (including spillover) w.r.t allocation for 2020-21 0.7049
113
Annual Plan 2020-21 - Weekly Progress Report
H/A:- 2701-80-800-92-00-00-00-P-V Dam Safety Organisation & Dam Safety Measures
Allocation of Rs 10 Lakhs
Sl. No.
Name of the Project
Project Cost* (Rs Lakhs)
AS Accorded
(Y/N)
Date of AS
AS Amount* (Rs Lakhs)
TS Accorded
(Y/N)
Date of TS
TS Amount* (Rs Lakhs)
Tendered or not (Y/N)
Date of Tender
Tendered Amount*
(Rs Lakhs)
Awarded or not (Y/N)
Date of Awarding
work
Awarded Amount* (Rs Lakhs)
Work Status: Completed
(C) or Ongoing
(OG)
Expenditure* (Rs
Lakhs)
Expenditure %
Remarks
1 Trainings, Technical visits to dams etc.
10
OG 0.07049 0.70
Since majority of the trainings, technical visits to dams etc are being charged under DRIP, the expenditure under this H-OA is less
Total 10 0 0 0 0 0 0 0 0 0 0 0 0 0 0.07049 0.70
114
Abstract of Weekly Progress of H/A: 4700-29-800-97-00-00-00-P-V Dam & Appurtenant Works - Mullaperiyar Project
1 Budget Allocation (Rs Lakhs) 100
2 Number of FS Issued 0
3 Total FS Amount (Rs Lakhs) 0
4 Number of AS Issued 1
5 Total AS Amount (Rs Lakhs) 29.60958
6 Number of TS Issued 0
7 Total TS Amount (Rs Lakhs) 0
8 Number of Works Tendered 0
9 Total Tendered Amount (Rs Lakhs) 0
10 Number of Works Awarded 0
11 Total Tendered Awarded (Rs Lakhs) 0
12 Number of Completed Works 0
13 Number of Ongoing Works 0
14 Expenditure for 2020-21 (Rs Lakhs) 0
15 % Expenditure for 2020-21 w.r.t allocation for 2020-21 0
16 Total Expediture up to date (including spillover) (Rs Lakhs) 0
17 % Expenditure up to date (including spillover) w.r.t allocation for 2020-21 0
115
Annual Plan 2020-21 - Weekly Progress Report
H/A:- 4700-29-800-97-00-00-00-P-V Dam & Appurtenant Works - Mullaperiyar Project
Allocation of Rs 100 Lakhs
Sl. No.
Head of Account/ Name of the
Project
Project Cost* (Rs Lakhs)
AS Accorded (Date of AS)
AS Amount* (Rs Lakhs)
TS Issued (Date of
TS)
TS Amount*
(Rs Lakhs)
Tendered (Date of Tender)
Tendered Amount* (Rs Lakhs)
Awarded (Date of
Awarding work)
Awarded Amount* (Rs Lakhs)
Work Status: Completed
(C) or Ongoing
(OG)
Expenditure* (Rs. Lakhs)
Expenditure %
Remarks
2020-21
4700-29-800-97 Mullaperiyar project
29.6095 03.03.2020 29.6095 Nil Nil Nil Nil Nil Nil Nil Nil Nil
Construction of new dam to replace existing Mullaperiyar dam, requires statutory clearances from MoEFCC including the clearance from the Hon. Supreme Court. MoEF & CC has approved the ToR for EIA study conditionally. EIA study is progressing through Pragathi Lab & Consultants and also revised DPR is under Preperation. AS accorded as per GO.(Rt.)No.198/2020/WRD dated 03.03.2020 for digitization of of ISW records.
2019-2020
4700-29-800-97 Mullaperiyar project
Nil Nil Nil Nil Nil Nil Nil Nil Nil Nil Nil
RS. 95 Lakhs has been reappropriated from H/A 4700-29-800-97 to H/A 4700-80-005-99-02-V (Investigation of Major Irrigation Schemes) vide G.O (Rt) No.7085/2019/fin Dtd:30/09/2019
Total 29.6095 0 0 0 0 0 0 0 0 0 0 0
116
Abstract of Weekly Progress of 4700-80-005-99-02-00-V Investigation of Major Irrigation Schemes"
1 Budget Allocation (Rs Lakhs) 250
2 Number of FS Issued 20
3 Total FS Amount (Rs Lakhs) 83.419
4 Number of AS Issued 19
5 Total AS Amount (Rs Lakhs) 81.588
6 Number of TS Issued 15
7 Total TS Amount (Rs Lakhs) 66.302
8 Number of Works Tendered 15
9 Total Tendered Amount (Rs Lakhs) 49.324
10 Number of Works Awarded 7
11 Total Tendered Awarded (Rs Lakhs) 30.722
12 Number of Completed Works 2
13 Number of Ongoing Works 17
14 Expenditure for 2020-21 (Rs Lakhs) 0
15 % Expenditure for 2020-21 w.r.t allocation for 2020-21 0
16 Total Expediture up to date (including spillover) (Rs Lakhs) 102.06
17 % Expenditure up to date (including spillover) w.r.t allocation for 2020-21 40.104
117
Annual Plan 2020-21 - Weekly Progress Report
H/A:- 4700-80-005-99-02-00-V Investigation of Major Irrigation Schemes
Sl. No. Head of Account/ Name of the Project Project Cost* (Rs Lakhs)
AS Accorded (Y/N) Date of AS AS Amount*
(Rs Lakhs) TS
Accorde d (Y/N)
Date of TS TS Amount* (Rs Lakhs)
Tendered or not (Y/N) Date of Tender
Tendered Amount*
(Rs Lakhs) Awarded or not
(Y/N) Date of
Awarding work Awarded Amount*
(Rs Lakhs) Work Status:
Completed (C) or Ongoing (OG)
Expenditure* (Rs. Lakhs) Expenditure % Target date of
completion Remark
On Going
2020-2021
1 2020/23/P2- Topographic survey for construction of Regulator cum Bridge across Meenachil River at Koottanal kadavu in Bharananganam Panchayath in Kottayam Dt.
2.182 Y 19-8-2020 2.182 Y 08-10-2020 2.182 Y 3-11-2020 1.948 N
Nil
Tender Notice published on
3/11/2020
2 2016/2954/IA-Investigation works for the construction of a check dam at the upstrem of Kayyanikadavu across Chalakudy river in between Meloor and Pariyaram panchayaths.
7.000 Y 12-05-2020 7.000 Y 11-6-2020 7.000 Y 16-6-2020 5.990 Y 10-8-2020 5.99295 OG
Topographic survey started on
03/11/2020
3 2019/11505/IA : Investigation work for the construction of Regulator cum Bridge across Cherupuzha at Kalpallikkadavu in Koduvally Muncipality
5.300 Y 15-07-2020 5.300 Y 15-09-2020 5.300 Y 05-11-2020 5.008
Selection notice tobe issued.
4 2020/131/IDRB : Soil investigation for the proposed RCB at Kainurchira, Nadathara GP, Thrissur Dt. 8.000 Y 15-7-2020 8.000 Y 28-7-2020 8.000 Y 10-8-2020 5.115 Y 28.10.20 4.973 OG 0 0
Work started
5 2020/153/IDRB : Investigation for the rectification of existing Regulators at Enamakkal and Idiyanchira, Thrissur District
6.700 Y 1-7-2020 6.700 Y 2-7-2020 6.700 Y Departmental Execution 0.000 Departmental
Execution Departmental
Execution 0 OG 4.00 60%
.Soil exploration completed
6 2020/148/IDRB : Soil investigation at Ch.17 km at KIP main canal, Pathanapuram, Kollam District 4.500 Y 8-7-2020 4.500 Y 9-7-2020 4.500 Y 19.10.20 3.093 N
0 OG 0 0
Selection notice issued
7 2020/3205/IA : Putting up temporary bund for Enamakkal and Idiyanchira for investigation works 2.100 Y 9-7-2020 2.100 Y 13-7-2020 2.100 Y 16-7-2020 2.100 Y 24/08/2020 2.1 C 0 0
Work completed.
8 2020/322/P1 Kabani Sub Basin - Taking fly levels and marking FRL in the Reservoir Area of Thondar Irrigation Project.
1.300 Y. 27-8-2020 1.300 Y 3-9-2020 1.300 Y Retendered (2nd
time )on 18-9- 2020
1.157 Y 30/10/2020 1.15699 OG 0 0
Bottle neck.Public protest against the
project.
9 2018/5779/IA-Investigation works to Regulator cum Bridge across Anjarakandy puzha at Kakvapara in Chittariparamba Panchayath,Kannur District.
4.620 Y 08-10-2020 4.620 Y 12-10-2020 4.620 Y 12-10-2020 4.120 Y 6-11-2020 4.38 OG Site handed over to the contractor.
10 2020/3654/IA-Investigation for the construction of protection walls for the proposed regulator across Chitturpuzha at Valavupalam in Nallepilly Panchayath in Palakkad District.
1.830 N As not issued 0.000 N T.S Not issued
N
N
location of proposed structure has been changed. A new estimate for
new location is to be submitted
118
11 2020/3096/IA Investigation of Azhakapara LIS in Thiruvegapura Panchayat of palakkad District 3.000 Y 15-8-2020 3.000 Y 18-9-2020 3.000 Y 29/09/2020 2.670 Y 21/10/2020 2.670 OG
Work started.
12 2020/3121/IA-Investigation for the construction ofThumpamon thazham -Mannakadavu bridge across Achenkovil river in kulanada Panchayat
6.200 Y 25-7-2020 6.200 Y 27-7-2020 6.200 Y 28/07/2020 5.464 Y 7-10-2020 5.45 OG
90 % completed.
13 2020/3849/IA Investigation for Check dam cum Tractor Bridge construction in njaviroor kadavu across Ithikkara river in Chathannoor Constituency
5.400 Y 28-9-2020 5.400 Y 08-10-2020 5.400 Y 10-09-2020 4.760 N
negotiation forwarded
14 2020/154/IDRB : Fundamental studies using Smart station for the year 2020-21 Topographycal survey for Seetharkundu waterfalls- Stage II, Coastal Engineering Division, KERI,Peechi
2.100 Y 3-7-2020 2.100 Y 9-7-2020 2.100 Y Departmental Execution 0.000
OG 0 0 12-03-2021 50 % completed. Part bill received
for an amount of Rs.61195/- on 30/10/2020.
15 2020/4797/IA-Investigation works for the construction of an overflowing weir at Orange Kallumedu in Kumily Panchayath
2.900 Y 24-10.2020 2.900 Y 24-10.2020 2.900 Y 29/10/2020 2.900 N
OG
Tender opened on 10/11/2020,process after election
16 2020/355/P1-RKI-AIP-Goolikkadavu chittoor road- Constructionof retaining wall -Investigation work 5.000 Y 27-4-2020 5.000 Y 23-5-2020 5.000 Y 23-05-2020 5.000 Y 16/06/2020 3.99911 C
Work completed.
17 Design consultancy of Mechanical Shutters - Reconstruction of Lock Gate and Bridge at Payyoli Canal
3.699 Y 18-09-2020 3.699 N
TS and Execution of work under the
Chief Engineer, Mechanical
18 Design consultancy of Mechanical Shutters - Construction of Regulator cum bridge across Kariangode river at Chemmarakkayam in West Eleri Grama Panchayath in Kasargod Distict
1.401 Y 18-09-2020 1.401 N
TS and Execution of work under the
Chief Engineer, Mechanical
19 Design consultancy of Mechanical Shutters - Construction of Regulator cum bridge across Venniyode river at Malankara in Parakadavu in Panamaram Panchayath
2.186 Y 18-09-2020 2.186 N
TS and Execution of work under the
Chief Engineer, Mechanical
20 2020/103/P1 KRP-Investigation works in the breached portion of Kariambady branch Canal near Ch:1800 m
8.000 Y 06-11-2020 8.000 N
AS issued on 6-11-2020
83.419 19
81.588 15
66.302 15
49.324 7.000
30.722
2019-2020
119
1 2019/1530/P2-MRVP Construction of Regulator across Meenachil River at Pallikunnu in Ettumanur municipality-Soil Investigation
3.981 Y 28.02.2020 3.981 Y 10-3-2020 3.981 Y 22-5-2020 3.543 Y 09-09-2020 3.543
Nil Nil
Work can be started only after receding water level in river.
2 2019/3084/P2-MRVP- Construction of Mini dam with Regulator across Teekoy river at Cherippad in Teekoy Panchayath- Soil Investigation
3.700 Y 26.03.2020 3.700 Y 26-3-2020 3.700 Y 19/10/2020 3.280 N
Nil Nil
single quotation received,quotation
to be approved..
3 2020/573/IA-Investigation for the construction of Regulator cum Bridge across Mahe River at Iyyamkode in Nadapuram Panchayath
6.100 Y 26.03.2020 6.100 Y 30-3-2020 6.100 Y 22-5-2020 5.547 Y 06-08-2020 5.547
work temporarily stopped due to
heavy rain. Work to be started soon
4 2020/8/IDRB-Investigation work for assessment of possible reasons of leakage of existing u/s apron of Attapilly RCB
4.600 Y 18.02.2020 4.600 Y 26-2-2020 4.600 Y 21-4-2020 4.107 Y 12-06-2020 3.88 Refer remarks 0 0
Since the investigation work includes putting up of ring bund in river, the contractor did not come forward to
start the work as the agreement period is monsoon
season. Agreement executed on 05.06.20. 1st TOC expired on
5 2019/196/IA-Investigation for Regulator cum Bridge across valiyathodu at valiyakandy in Peralassery panchayath, Kannur District.
5.300 Y 04.01.2020 5.300 Y 9-3-2020 5.300 Y 29-5-2020 4.680 Y 11-09-2020 4.29 OG
55% work completed.
6 2017/2937/IA-Reconstruction of Muttilkappu Regulator cum brdige in Cherukunnu panchayath, Kannur District.
10.550 Y .G.O.(Rt)
No.111/2019/WR D Dtd 23.02.2019
10.550 Y 13.06.2019 10.400 Y 3-7-2019 9.200 Y 27/08/2019 8.15 C
Completed (investigation report to be
obtained).
7 2019/281/IA Investigation estimate for installation of Lift irrigation schemes at Iluppakkal kolambu in Pattancherry Panchayath
2.870 Y 09-10-2020 1.610 Y 09-10-2020 1.610 Y 09-10-2020 1.431 N
Tender process.
8 2019/8348/IA Construction of Check dam across Vamanapuram River near Aruvipuram Bridge in Pullampara Panchayath.
4.980 Y 26-11-2019 4.980 Y 18-3-2020 4.980 Y 20-5-2020 4.438 Y 18/09/2020 4.43 OG
Work started
9 2019/7480/IA Construction of Check dam across Vamanapuram river near Karettu bridge in Attingal constituency - Investigation work
4.780 Y 26-11-2019 4.780 Y 18-3-2020 4.780 Y 20/5/2020 4.264 Y 18/09/2020 4.26 OG
Work started
10 2019/8310/IA Investigation work -Interlinking of Bharathapuzha and Biyyam Lake by gravity through natural streams in Ponnani Taluk in Malappuram District
1.800 Y 27-5-2020 1.800 Y 28-5-2020 1.800 Y 8-7-2020 1.572 Y 13/08/2020 1.29 OG
Work started
11 2019/570/IA-Mullaperiyar dam -total station survey work for the area between mullaperiyar dam and iddukki dam
5.200 Y 19-2-2020 5.200 Y 19-2-2020 5.200 Y 24/2/2020 4.095 Y 15/05/2020 3.9096 OG
55% Work completed.
12 2019/10493/IA-Investiation for the construction of Regulator across Manimala river at mooleplavu in chirakkadavu panchayath
3.900 Y 4-3-2020 3.900 Y 24-3-2020 3.900 Y 12-5-2020 3.447 Y 29/06/2020 3.278 OG
Work started
120
13 2019/977/KP P.M-Soil test estimate-Extra bore (under water)-Construction of Tractor Bridge across Puthenthodu between ward 6 and 7 of Pulinkunnu gramapanchayath in Alappuzha district.
1.240 Y 17-8-2019 1.240 Y 19-8-2019 1.240 Y
Y
1.289 C
Work completed.
14 2019/1615/P1 Soil investigation estimate for the enhancing storage capacity of Kambalathara EriSoil testing
3.387 Y 05-10-2018 1.200 Y 6-10-2018 1.200 Y 15/10/2018 1.200 Y 10-11-2018 1.200 C
Work completed.-AS & TS not
issued through PRICE
15 2019/1589/P1 : CPP - KKPS - Enhancement of Storage capacity- Soil investigation works for enhancing storage capacity of Kunnampidari Eri.
1.390 Y 18/09/2018 0.650 Y 19/09/2018 0.650 Y 19/09/2018 0.650 Y 20/10/2018 0.58 C
Work completed.-AS & TS not
issued through PRICE
16 2019/332/IDRB-Sedimentation study of Neyyar Reservoir using Integrated Bathymetric Study (IBS) &sub bottom profiler
3.500 Y 28-9-2019 3.500 Y 30-9-2019 3.500 Y Departmental Execution 0.000 Y Departmental
Execution C 2.47 71 17.03.2020 Work completed
17
2019/399/IDRB- Fundamental Studies using Smart Station for the year 2019-20 - Various Investigation surveyworks in Irrigation Department using Smart station-Conducting Topographic survey for investigation of Bharathapuzha irrigation Scheme in Muthuthala Panchayath
1.420 Y 22-10-2019 1.420 Y 24-10-2019 1.420 Y Departmental Execution 0.000 Departmental
Execution C 1.15 81.08 30.03.2020 Work completed.
18 2019/447/IDRB : Fundamental studies using Smart Station for the year 2019-20-Conducting topographic survey for assessing the sedimentation in Velliyamkallu RCB at Thrithala
7.000 Y 21-12.2019 7.000 Y 23-12-2019 7.000 Y Departmental Execution 8.150 Y Departmental
Execution C Work completed.
19 2019/452/IDRB Various Investigation survey works in Irrigation Department using Smart station 201920 - Identification of submersible areas while increasing FRL of Cheramangalam Anicut
10.000 N AS Not issued Work dropped.
20 2019/275/IDRB Soil Investigation for the construction of Check Dam across Gayatri Puzha at Anappara Chundekkad in Kavassery Panchayath in Palakkad District
3.150 Y 18-10-2019 3.150 Y :02-11-2019 3.150 Y Departmental Execution 4.438 Y Departmental
Execution C Work completed.
21 2019/349/IDRB-Soil investigation for the construction of new check dam across Thoothappuzha in Vilayoor Grama panchayat in Palakkad District
4.950 Y 18-10-2019 4.950 Y :02-11-2019 4.950 Y Departmental Execution 1.572 Y Departmental
Execution C Work completed.
22 2019/6693/IA Investigation works to the Construction of SWEVCB Cum Bridge across Naduvathithode at Poorappuzha river mouth in Tanur muncipality.
3.008 Y 26-102019 3.000 Y 28-10-2019 2.980 Y 28/10/2019 2.605 Y 10-12-2019 2.605 C Work completed.
23 2019/10604/IA : KIIFB WORK - Investigation for the Construction of SWE Regulator across Kadalundi River at Kadakkattupara Alunkdavu in Vallikkunnu Panchayath in Malappuram District.
7.960 Y 24-12-2019 7.960 Y 3-1-2020 7.960 N 30/01/2020 7.101 Y 20/03/2020 5.306 C Work completed.
24 2019/3039/IA-Investigation work for Protecting the Right Bank of Kadalundi River at Therkkayam at the downstream of Therkkayam Bridge in Vengara Panchayath in Malappuram Dist. in Vengara LAC.
3.700 Y 31-8-2019 3.700 Y 05.09.2019 3.700 N N Work dropped. An original side protection work is arranged in this site.
25 2018/3982/IA-Investigation of a regulator cum bridge across Kalikavupuzha at Muthanthandu Venthodanpadi in Kalikavu panchayath in Malappuram District.
9.685 N N N N N work dropped.
A bridge across the river at near by this site is proposed and included in state budget 220-21(sl no. 854,work appendix II, Vol II) also construction of a check dam under M.I division
Malappuram is starting stage at U/S of this site.
121
26 2019/1723/P2- Soil Investigation work for the construction of river training wall at right side downstream of Malankara dam
1.500 Y 26-3-2020 1.500 Y 31-3-2020 1.400 Y 05-06-2020 1.305 Y 13/07/2020 1.289 C Work completed.
27 2018/4964/IA- Construction of Marginal Earthen bund at western side of Thekkumbad island in Mattool Grama Panchayath - Investigation work
0.600 N N N N Tourism department has to be
constructed a walk way along the bund. Hence investigation work need
not required.
28 Design consultancy of Mechanical Shutters - Construction of regulator across Neyyar River at Mavilakadavu d/s side of KWA pump house to prevent Salinity intrusion
3.363 Y 26-04-2019 3.363 Y 08-05-2019 3.363 Y C 3.360 TS and Execution of work under the Chief Engineer, Mechanical
29 Design consultancy of Mechanical Shutters - Construction of regulator cum bridge at Palupuzhakadavu in Annamanada Panchayath in Thrissur District
2.803 Y 16-06-2019 2.803 Y 28-06-2019 2.803
Y
C
2.66
TS and Execution of work under the
Chief Engineer, Mechanical
30 Design consultancy of Mechanical Shutters - Construction of regulator across Olavilam Pathikkal in Chokli Panchayath in Kannur District
2.186 Y 06-08-2019 2.186 Y 31-08-2019 2.186
Y
C
2.08
TS and Execution of work under the
Chief Engineer, Mechanical
31 Design consultancy of Mechanical Shutters - Construction of regulator across Kuppam River upstream side of Kuppam Bridge in Pariyaram Panchayath in Kannur District
2.803 Y 10-01-2020 2.803 Y 24-02-2020 2.803
Y
C
2.800
TS and Execution of work under the
Chief Engineer, Mechanical
32 Design consultancy of Mechanical Shutters - Construction of regulator cum bridge at Chekkupalam across Ummanchira River in Pinarayi Panchayath
2.186 Y 31-01-2020 2.186 Y 20-02-2020 2.186
Y
C
2.186
TS and Execution of work under the
Chief Engineer, Mechanical
33 Sesmic study for AIP 15.270 Y 31-01-2020 15.270
Y 21-08-2020 12.940
12.94 100
Sesmic study for AIP is entrusted with CWPRS
2019-20 - Spill over works
1 2019/384/IDRB-Soil Investigation for the proposed check dam across Thoothapuzha at Mundorssikadavu in Sreekrishnapuram Panchayath of Palakkad district
4.270 Y 18-10-2019 4.270 Y :02-11-2019 4.270 Y Departmental Execution 4.264 Y
C 1.45 35%
Work completed.
Total ( 2019-20) 133.591
124.381 108.841
76.624
2018-2019
1 Design consultancy of Mechanical Shutters - Construction of regulator across Pampa River on the downstream of intake well of UIDSSMT for Alappuzha and adjoining villages of Pannayikadavu
3.363
28-04-2018 3.363
19-05-2018 3.363
Y
C 3.363
2 Design consultancy of Mechanical Shutters - Construction of salinity barrier ( sluice gate) across Pulikkezhu River at Mahadevikadavu in Karthikappally panchayath in Harippadu constituency
2.186
16-11-2018 2.186
30-11-2018 2.186
Y
C 2.19
3 Design consultancy of Mechanical Shutters- Construction of LB Canal shutter for Moolathara Regulator
1.093
16-11-2018 1.093
30-11-2018 1.093
Y
C 1.09
122
4 Design consultancy of Mechanical Shutters- Construction of regulator at Parappuram across Ancharakkandi river in Pinarayi grama Panchayath in Kannur Dist
3.363
29-01-2019 3.363
12-02-2019 3.363
Y
C 3.36
5 Design consultancy of Mechanical Shutters- Construction of regulator across Pampa river at Mundappuzha Thottamon in Ranni panchayath for the benefit od RWSS
3.363
12-12-2018 3.363
19-01-2019 3.363
Y
C 3.35
Total ( 2018-19) 13.368
13.368 13.368
Total (2020-21) 83.419
0.000 81.588 0.000 66.302
0.000 49.324
Abstract of Weekly Progress of H/A: 4700-80-800-97-01-00-00-P-V
Dam Safety Organisation & Dam Safety Measures
1 Budget Allocation (Rs Lakhs) 230
2 Number of FS Issued 25
3 Total FS Amount (Rs Lakhs) 222.02
4 Number of AS Issued 22
5 Total AS Amount (Rs Lakhs) 206.02
6 Number of TS Issued 16
7 Total TS Amount (Rs Lakhs) 134.49
8 Number of Works Tendered 14
9 Total Tendered Amount (Rs Lakhs) 107.44
10 Number of Works Awarded 6
11 Total Awarded amount (Rs Lakhs) 19.42
12 Number of Completed Works 1
13 Number of Ongoing Works 5
14 Expenditure for 2020-21 (Rs Lakhs)* 0.71
15 % Expenditure for 2020-21 w.r.t allocation for 2020-21* 0.31
16 Total Expediture up to date (including spillover) (Rs Lakhs) 42.11
17 % Expenditure up to date (including spillover) w.r.t allocation for 202021 18.31
* includes bill amount submitted for processing
124
Annual Plan 2020-21 - Weekly Progress Report
H/A:- 4700-80-800-97-02-00-00-P-V Dam Safety Organisation & Dam Safety Measures ** Allocation of Rs 230 Lakhs
Sl. No. Name of the Project
FS Amount / Project Cost* (Rs
Lakhs)
AS Accorded
(Y/N) Date of AS
AS Amount*
(Rs Lakhs)
TS Accorded
(Y/N) Date of TS TS Amount*
(Rs Lakhs) Tendered
or not (Y/N)
Date of Tender
Tendered Amount*
(Rs Lakhs) Awarded or
not (Y/N) Date of
Awarding work
Awarded Amount*
(Rs Lakhs)
Stage of Work: Completed (C) or
Ongoing (OG)
Bill submitted/ Expenditure*
(Rs Lakhs) Expenditure % Target date of
completion Remarks
1 PRICE ID: 2020/8/MH Repair, maintenance and painting of spillway shutters of Chulliyar Dam at Palakkad district
4.5 Y 26.05.2020 4.5 Y 30-05-2020 4.5 Y 01.06.2020 4.0078 Y 07.08.2020 4.16811 OG 0 0 30.11.2020 Work Ongoing. 70% completed
2 PRICE ID: 2020/181/P1 Pyip- Renovation of Electrical System and lighting arrangements at Pazhassi Barrage
22.10 Y 19.06.2020 22.10 Y 04.08.2020 22.10 Y 16.09.2020 19.65683 N 0 0 Tendered. Single tender received. Work
re-tendered and single tender received is under evaluation
3
PRICE ID: 2020/158/IDRB Conducting topographical investigations in connection with the rectification works of Karapuzha Irrigation Project under DRIP Phase-IIAppendices A & L of Part A
0.75 Y 17.07.2020 0.75 Y 21.07.2020 0.75 Y Dept
Execution by KERI
0.75 Y NA 0.75 OG 0.70646 0 30.12.2020
Field survey completed. Drawings and Report under preparation. Part bill submitted for an amount of Rs. 70646/- on 19/10/2020 (Fund requested) 96% completed
4 PRICE ID: 2020/814/P1 KRP-DRIP Phase II- Soil test for reviewing the stability analysis of Existing earth dam
7.20 Y 06.08.2020 7.20 Y 07.08.2020 7.20 Y 10.08.2020 4.80277 Y 30.10.2020 4.70163 OG 0 0 31.12.2020 Agreement executed and work started
5
PRICE ID: 2020/521/P2 Dam safety - Kallada Dam - Urgent protection works including Construction of parapet wall, Raising of handrails, provision of gate to inspection gallery.
26.6 Y 05.11.2020 26.6 N
N
N
0 0
TS to be issued
6 PRICE ID: 2020/615/P1 Clearing Jungle, Floating Materials, De-rooting plants from Peruvannamuzhi Dam
3 Y 11.09.2020 3 Y 11.09.2020 3 Y 11.09.2020 3 Y 05.10.2020 2.83833 OG 0 0 05.03.2021 Work ongoing (15% completed)
7 PRICE ID: 2020/989/P1 Karapuzha Irrigation Project - Providing KSEB service connection to spillway
2.88 Y 22.10.2020 2.88 Y 30.10.2020 2.88 Y 03.11.2020 2.56536 N 0 0 Work tendered. Tender opening on
17.11.2020
8 PRICE ID: 2019/6949/IA NIP-Construction of bridge across RBC in front of Govt. High School, Neyyar Dam
25 Y 21.10.2020 25 Y 05.11.2020 25 Y 05.11.2020 22.21292 N 0 0
Tender opening on 20.11.2020
9 PRICE ID: 2020/96/MH Annual maintenance to spillway shutters and emergency shutters of Peechi Dam
8 Y 22.09.2020 8 Y 30.10.2020 8 Y 30.10.2020 6.7544 N 0.00 0.00
Tendered.
10 PRICE ID: 2020/94/MH KIP- Supply and Fixing of new Wire rope for radial gate and Lubrication of Trunnion Pin of all gates at Parappar Dam, Thenmala
11.8 N
N
N
N
0.00 0.00
AS to be issued
11 PRICE ID: 2020/101/MH Dam safety-Annual Mechanical maintenance to spillway shutters of Vazhani Dam
4.7 Y 22.09.2020 4.7 Y 23.10.2020 4.52 Y 27.10.2020 3.94 N 0.00 0.00
Tendered.
12 PRICE ID: 2020/1147/P1 KPIP - Dam Safety - Installation Of Siren/Emergency Alarm In Kanhirapuzha Dam
2.89779 N N
N N
0 0 AS to be issued
13 PRICE ID: 2020/1079/P1 KyIP -Dam Safety- Peruvannamoozhi Electrification to Gallery
3.3 Y 06.11.2020 3.3 N N
N 0 0
AS to be issued
14 PRICE ID: 2020/1157/P1 Dam safety -Plastering and Painting of chulliyar masonry dam and earthen dam parapet 3 Y 14.10.2020 3 Y 02.11.2020 3 N
N
0 0
To be tendered
15 PRICE ID: 2020/1161/P1 Dam Safety - Fencing of chulliyar dam catchment area
8.5 Y 14.10.2020 8.5 Y 28.10.2020 8.5 Y 28.10.2020 7.58830 N 0 0 Tender opened on 13.11.2020. No
response from bidders
16
PRICE ID: 2020/1162/P1 GPS I - Dam Safety - Painting Works, Erection Of Sign Board, Jungle Clearance & Other Minor Rectification Works In Meenkara Dam & Its Premises
13.75 Y 16.10.2020 13.75 N
N
N
0 0
TS to be issued
17 PRICE ID: 2020/4782/IA Dam Safety- Providing safety measures to the Peechi Dam for the year 2020-2021
7 Y 13.10.2020 7 Y 13.10.2020 7 Y 15.10.2020 6.23962 N
0 0 Tender opened on 28.10.2020. No
bidders. Re-tendered on 03.11.2020 and retender opened on 17.11.2020. Selection notice issued
18 PRICE ID: 2020/1134/P1 Supply and installation of shutter motor to canal sluice and emergency shutter to Meenkara dam 1.7 Y 05.11.2020 1.7 N
N
N
0 0
TS to be issued
125
19 PRICE ID: 2020/1167/P1 WP -DSO-Rectification works such as plastering,Painting, Jungle clearance and maintenance works to Walayar Dam.
9 Y 14.10.2020 9 Y 05.11.2020 9 N
N
0 0
To be tendered
20
PRICE ID: 2020/119/MH Dam safety - Peechi dam - Urgent closing of emergency shutter and the work of temporary arrangement for water distribution through RBMC 7.6 Y 15.10.2020 7.6 Y 21.10.2020 7.6 Y 23.10.2020 6.78 Y 06.11.2020 6.78156 OG 0 0
Work awarded and ongoing
21
PRICE ID: 2020/111/MH Dam safety-Overhauling and painting of canal sluice shutter, Emergency shutter, Gantry crane and painting of spillway hoisting bridge and accessories of Chulliyar Dam in Palakkad District 14 Y 31.10.2020 14 N
N
N
0 0
TS to be issued
22
PRICE ID: 2020/120/MH CDP - Annual mechanical maintenance to spillway shutters of Chimoni dam for the year 2020-21 12 Y 27.10.2020 12 N
N
N
0 0
TS to be issued
23 PRICE ID: 2020/1290/P1 MP-DAM SAFETY- Providing stainless Steel hand rail on the dam-top parapet wall of Malampuzha dam.
21.25 Y 06.11.2020 21.25 Y 06.11.2020 21.25 Y 06.11.2020 18.97 N
0 0
Work tendered
24
PRICE ID: 2020/1435/P1 PyIP- Urgent removal of tree and branches stuck across the radial shutters 2&3 on the upstream side of pazhassi barrage for the year 2020-21 0.19 Y 06.11.2020 0.19 Y 07.11.2020 0.19 Y 09.11.2020 0.17687 Y 11.11.2020 0.176 C 0 0
Work completed. Bill under preparation
25 PRICE ID: 2020/5080/IA Peechi Dam - Emergency works for lowering Emergency Shutter
1.3
Total 222.02 22 206.02 16 134.49 14 107.44 6 19.42 1 0.71 0.31
Spill over works (2019-20)
1 Urgent Repairs to LBMC valve of Peechi dam 7.81413 Y 02.07.2019 7.81413 Y 17.08.2019 7.81413 Y 17.08.2019 6.5294 Y 21.10.2019 6.21558 C 6.21558 79.54 25.02.2020 Work completed. Bill submitted
2 PVIP-Dam Safety- Providing Roofing and side covering with GI grill for Generator Set of Barrage Bhoothathankettu.
4.96 Y 26.11.2019 4.96 Y 21.01.2020 4.96 Y 23.01.2020 4.96 Y 21.03.2020 3.55951 C 3.55951 71.76 20.06.2020 Work completed. Bill submitted
3 Dam Safety- Reconstruction of surplus escape in main canal near Peruvannamuzhi Dammechanical work
10.95 Y 23.09.2019 10.95 Y 02.11.2019 10.95 Y 05.11.2019 9.34165 N 0 0 Tendered 2 times. Quotation invited. No
response from bidders. Date of submission extended upto 20.11.2020
4 Dam safety:- Chimoni- Rectification works to the toe drain of earthen dam for the year 2019-20 17.54 Y 28.09.2019 17.54 Y 19-12-2019 17.54 Y 09.01.2020 14.43688 Y 08.06.2020 14.43658 OG 0 0 17.03.2021 Work Ongoing. 75% completed
5 NIP-Dam Safety Works-Providing MS Cable Trays and allied works at Dam Top
4.49 Y 10.04.2019 4.49 Y 23.03.2020 4.49 Y 19.05.2020 4.49 Y 30.07.2020 4.40333 C 4.387 97.71 05.10.2020 Work completed. Bill submitted
6 Dam safety:- KPIP-Urgent rectification and maintenance of seepage gallery.
17 Y 21.12.2019 17 Y 30.03.2020 17 Y 30.03.2020 13.29423 Y 23.09.2020 12.47938 OG 0 0 Work Ongoing
7 KPIP-Urgent jungle clearence and cleaning of Gallery in Kanhirapuzha.
4 Y 07.11.2019 4 Y 08.11.2019 4 Y 06.12.2019 3.8006 Y 06.12.2019 3.806 C 3.6643 91.61 15.06.2020 Work completed
8 Survey work for conducting model study of Kuttiyadi dam as part of DRIP
7.8 Y 10.02.2020 7.8 Y 09.03.2020 7.8 Y 12.03.2020 5.48187 Y 04.06.2020 5.4815 C 5.39608 0 06.07.2020 Work completed. Bill submitted
9 NIP- Dam Safety works- Urgent Jungle clearance at the saddle dams
2.48 Y 14.02.2020 2.48 Y 24.02.2020 2.48 Y 19.05.2020 2.48 Y 30.07.2020 2.42831 C 0 0 31.10.2020 Work completed
10 PyIP- Flood damages 2019- Refixing partially damaged scale for reading water level in the reservoir of pazhassi barrage
0.11267 Y 10.02.2020 0.11267 Y 10.02.2020 0.11267 Y _ 0.11267 Y 14.08.2019 0.11267 C 0.11267 100 14.08.2019 Work completed. Bill submitted
11 Dam Safety-Fitting of rubber seals of Radial gates of Pazhassi Barrage 26.28 Y 10.02.2020 26.28 Y 10.03.2020 26.28 Y 12.03.2020 21.36456 N
0 0
Tendered 2 times. Single tender received. Submitted to SE (Mech Ekm) for ratification. Single bid sanctioned
12 Dam Safety- Malampuzha Dam- Installation of new Hand rail and Platform on dam top, replacement of sluice well platform and other miscellaneous works 18.1 Y 31.03.2020 18.1 Y 31.03.2020 18.1 Y 31.03.2020 16.11725 Y 22.10.2020 17.00062 OG 0 0
Work ongoing. Material procurement and design in progress. 10 % completed
13 Dam Safety- Providing electric motors and overhauling and painting of spillway shutters of meenkara dam in Palakkad District
8.4 Y 22.01.2020 8.4 Y 09.03.2020 8.4 Y 11.03.2020 7.1274 Y 06.08.2020 7.27296 OG 0 0 31.12.2020 (Expected) Work ongoing. 20 % completed
14 Dam Safety- Overhauling and painting of canal sluice shutter and providing new ladder for the sluice well in Meenkara dam in Palakkad Disrtrict 7.5 Y 22.01.2020 7.5 Y 09.03.2020 7.1 Y 11.03.2020 6.00773 Y 06.08.2020 6.24221 OG 0 0 31.12.2020
(Expected) Work ongoing. 15 % completed
15 Dam Safety- MALAMPUZHA- Painting the Spillway gate & Replacement of existing Rubber seals of Spillway shutters
9.2 Y 07.01.2020 9.2 Y 02.03.2020 9.2 Y 11.02.2020 7.8574 Y 20.05.2020 6.88983 C 7.63564 83.00 27.05.2020 Work completed. Bill submitted
126
16 DRIP-Electrical works - Rewiring and repairs to EI in Inspection Banglow Kanjirapuzha
3 Y 29.01.2020 3 Y 20.03.2020 3 Y 20.03.2020 3 Y 27.10.2020 2.59506 OG 0 0 30.11.2020 Agreement executed and work started
17
Patchwork of hoisting mechanism cover- overhauling, greasing & replacement of dial gauges for emergency & radial shutters hoisting mechanism- painting of hoisting bridge mechanical structures, hoisting mechanism cover &hand rail etc. For radial shutters at Neyyar Irrigation Project.
6.3 Y 14.02.2020 6.3 Y 26.02.2020 6.3 Y 19.03.2020 5.62473 N
0 0
Tendered 3 times. two bidders attended last tender process, but both quoted above estimate PAC. After negotiation both bids rejected as bidders are not willing to reduce quoted amount to FS amount limit. Work re-tendered
18 MVIP- Malankara Dam -Removal of calcination and cleaning the pressure release valves of the Inspection Gallery 5.59 Y 12.03.2020 5.59 Y 16.03.2020 5.59 Y 18.06.2020 5.59 Y 07.07.2020 4.9037 OG 0 0 14.01.2021
Removal of calcination is completed. Reaming of foundation hole is not started. TOC of work extended up to 1401-2021
19 NIP- Providing partitions inside the Irrigation Museum at Neyyar Dam, Maintenance and Conveyance of items to be displayed
15 Y 14.02.2020 15 Y 20.03.2020 15 Y 19.05.2020 15 Y 30.07.2020 5.35016 OG 0 0 30.11.2020 Work delayed due to change in design
20 Walayar Project- DSO Rectification works to Walayar Dam and allied structures 25 Y 20.03.2020 25 Y 28.04.2020 25 Y 28.04.2020 22.31019 N
0 0
Work tendered 4 times. e-Quotation called with last date as 06.10.2020. No response from bidders. 2nd e-Quotation opened on 03.11.2020 and 2 bids received. Selection notice issued on 10.11.2020 in response to 2nd eQuotation
21 KIP- Dam Safety works -Removal of calcination, painting and lettering in the inspection gallery of Reservoir
16.5 Y 02.03.2020 16.5 Y 19.03.2020 16.5 Y 19.03.2020 16.5 Y 08.06.2020 15.69381 C 0 0 14.10.2020 Work completed. Bill under preparation
Total 218.02 21 218.02 21 217.62 21 191.43 17 118.87 9 30.97 13.47
GRAND TOTAL of 2020-21 GRAND TOTAL of 2020-21 & spillover 2019-20
222.02 440.03
22 43
0 206.02 424.04
16 37
0 134.49 352.11
14 35
0 107.44 298.87
6 23
0 19.42 138.29
1 10
42.11 42.11424
18.31 18.31
127
Abstract of Weekly Progress of H/A: 4701-80-800-81-00-00-00-P-V Bench Marking of Irrigation System
1 Budget Allocation (Rs Lakhs) 50
2 Number of FS Issued 0
3 Total FS Amount (Rs Lakhs) 0
4 Number of AS Issued 0
5 Total AS Amount (Rs Lakhs) 0
6 Number of TS Issued 0
7 Total TS Amount (Rs Lakhs) 0
8 Number of Works Tendered 0
9 Total Tendered Amount (Rs Lakhs) 0
10 Number of Works Awarded 0
11 Total Tendered Awarded (Rs Lakhs) 0
12 Number of Completed Works 0
13 Number of Ongoing Works 0
14 Expenditure for 2020-21 (Rs Lakhs) 0
15 % Expenditure for 2020-21 w.r.t allocation for 2020-21 0
16 Total Expediture up to date (including spillover) (Rs Lakhs) 0
17 % Expenditure up to date (including spillover) w.r.t allocation for 202021 0
128
Annual Plan 2020-21 - Weekly Progress Report
H/A:- 4701-80-800-81-00-00-00-P-V Bench Marking of Irrigation System
: Allocation of Rs 50 Lakhs
Sl. No. Head of Account/ Name of the Project FS Amount/
Project Cost* (Rs Lakhs)
AS Accorded (Date of AS)
AS Amount* (Rs Lakhs)
TS Issued (Date of TS)
TS Amount* (Rs Lakhs)
Tendered (Date of Tender)
Tendered Amount*
(Rs Lakhs)
Awarded (Date of
Awarding work)
Awarded Amount*
(Rs. Lakhs)
Work Status: Completed (C)
or Ongoing (OG)
Expenditure* (Rs. Lakhs) Expenditure % Remarks
2020-2021
4701-80-800-81 Benchmarking of Irrigation 0 0 0 0 0 0 0 0 0 0 0 0 For the financial year 2020-21 an amount of Rs. 50lakhs is the budget provision
2019-2020
4701-80-800-81 Benchmarking of Irrigation systems 0 0 0 0 0 0 0 0 0 0 0 0
Project report had been submitted to Govt. for an amount of Rs.125 Lakhs for approval on 16.05.2018.But in Budget 2019-2020 provided fund is insufficient for the work.Hence the estimate has been returned to SE Siruvani Project Circle Palakkad for revision.
Total 0 0 0 0 0 0 0 0 0 0 0 0
129
Abstract of Weekly Progress of H/A: 4701-80-800-88-00-00-00-P-V Formation of River Basin Organization
1 Budget Allocation (Rs Lakhs) 100
2 Number of FS Issued 1
3 Total FS Amount (Rs Lakhs) 23.68
4 Number of AS Issued 1
5 Total AS Amount (Rs Lakhs) 23.68
6 Number of TS Issued 1
7 Total TS Amount (Rs Lakhs) 23.68
8 Number of Works Tendered 1
9 Total Tendered Amount (Rs Lakhs) 23.68
10 Number of Works Awarded 1
11 Total Tendered Awarded (Rs Lakhs) 23.68
12 Number of Completed Works 0
13 Number of Ongoing Works 1
14 Expenditure for 2020-21 (Rs Lakhs) 16.9
15 % Expenditure for 2020-21 w.r.t allocation for 2020-21 71.37
16 Total Expediture up to date (including spillover) (Rs Lakhs) 62.13
17 % Expenditure up to date (including spillover) w.r.t allocation for 202021 44.77
131
Abstract of Weekly Progress of H/A: 4701-80-800-96-00-00-00-P-V Post Facto Evaluation Studies
1 Budget Allocation (Rs Lakhs) 5
2 Number of FS Issued 1
3 Total FS Amount (Rs Lakhs) 5
4 Number of AS Issued 1
5 Total AS Amount (Rs Lakhs) 5
6 Number of TS Issued
7 Total TS Amount (Rs Lakhs)
8 Number of Works Tendered
9 Total Tendered Amount (Rs Lakhs)
10 Number of Works Awarded
11 Total Tendered Awarded (Rs Lakhs)
12 Number of Completed Works
13 Number of Ongoing Works
14 Expenditure for 2020-21 (Rs Lakhs) 0.25
15 % Expenditure for 2020-21 w.r.t allocation for 2020-21 5.18
16 Total Expediture up to date (including spillover) (Rs Lakhs) 0.25
17 % Expenditure up to date (including spillover) w.r.t allocation for 202021 5.18
132
H/A:-
Sl. No. Head of Account/ Name of the Project
Project Cost ( ) Rs Lakhs
AS Accorded ( ) Y/N
AS Accorded Date of AS ( )
AS Amount* ) Rs Lakhs (
TS Accorded ) ( Y/N
TS Issued ) Date of TS (
TS Amount* ) Rs Lakhs (
Tendered or not ( Y/N )
Tendered ( Date of Tender)
Tendered Amount* Rs Lakhs ) (
Awarded or not ( Y/N )
Awarded Date of (
Awarding work)
Awarded Amount*
) Rs Lakhs (
Work Status: Completed ( C ) or Ongoing (OG)
Expenditure* Rs Lakhs ) ( Expenditure % Target date of
completion Remarks
1
4701-80-800-96-00-00-00- P-V Post Facto Evaluation Studies. Post Facto
Evaluation Study on Kuttiyadi and Neyyar
Irrigation Projects were selected in 2020-21.
5 Y 25.05.2020 5 OG 0.25918 31.03.2021 Preliminary works of both projects
started.
5.00 1.00 5.00 0.25 5.18 TOTAL
4701-80-800-96-00-00-00-P- V Post Facto Evaluation Studies Allocation of Rs 5 Lakhs
Annual Plan 2020-21 - Weekly Progress Report
133
Abstract of Weekly Progress of H/A: 4701-80-800-99 Development of Kerala Engineering Research Institute - Stage II
1 Budget Allocation (Rs Lakhs) 100
2 Number of FS Issued 32
3 Total FS Amount (Rs Lakhs) 100
4 Number of AS Issued 30
5 Total AS Amount (Rs Lakhs) 76.565
6 Number of TS Issued 30
7 Total TS Amount (Rs Lakhs) 76.565
8 Number of Works Tendered 7
9 Total Tendered Amount (Rs Lakhs) 24
10 Number of Works Awarded 1
11 Total Tendered Awarded (Rs Lakhs) 6
12 Number of Completed Works 1
13 Number of Ongoing Works 25
14 Expenditure for 2020-21 (Rs Lakhs) 18.74
15 % Expenditure for 2020-21 w.r.t allocation for 2020-21 18.74
16 Total Expediture up to date (including spillover) (Rs Lakhs) 18.74
17 % Expenditure up to date (including spillover) w.r.t allocation for 202021 18.74
134
Annual Plan 2020-21 - Weekly Progress Report
H/A:- 4701-80-800-99 -34-03-V Development of Kerala Engineering Research Institute - Stage II Allocation of Rs 100 Lakhs
Sl. No. Head of Account/ Name of the Project FS
amount/Proje ct Cost ( Rs.
Lakhs) AS Accorded
(Y/N) Date of AS AS Amount* (Rs Lakhs)
TS Issued (Y/N) Date of TS TS Amount*
(Rs Lakhs) Tendered or
not (Y/N) Date of Tender Tendered Amount*
(Rs Lakhs) Work
Awarded (Y/N)
Date of Awarding work
Awarded Amount*
(Rs Lakhs)
Work Status: Completed (C)
or Ongoing (OG)
Expenditure* (Rs Lakhs)
Expenditure %
Target date of completion Remarks
Joint Director Hydraulic Research (Division office)
A) Hydraulics Division (Sub division office)
1 Maintenance of Meteorological station -Replacing sensors of Automatic Weather Sation (AWS) 3.65 Y 05-08-2020 3.65 Y 10-08-2020 3.65 Y 06-10-2020 3.65 Y 16-10-2020 3.65 OG 0.00 0 01-03-2021 90% completed.
2 Routine works of Hydraulics division office and Meteorological stations for the year 2020-21 1.25 Y 24-07-2020 1.25 Y 24-07-2020 1.25
Deptmtl execution
Deptmtl execution 0
Deptmtl execution NA 0 OG 0.50 40 31-03-2021
50% completed. Request for second work advance for an amount of Rs 50,000/- submitted on 28/10/2020
3 Routine Maintenance of Kerala Model and building housing Model for the year 2020-21 0.15 Y 24-07-2020 0.15 Y 24-07-2020 0.15
Deptmtl execution
Deptmtl execution 0
Deptmtl execution NA 0 OG 0.00 0 31-03-2021 80% completed,Part bill received on 05/11/2020
4 Routine Maintenance of Model Area I & II for the year 2020 -21 0.75 Y 24-07-2020 0.75 Y 24-07-2020 0.75
Deptmtl execution
Deptmtl execution 0
Deptmtl execution NA 0 OG 0.35 46.67 31-03-2021 46% completed.settlement bill settled at treasury 09/10/20
.
5 Maintenance and yearly charges of FTTH internet connection of KERI offices foor the year 2020-21 0.50 Y 24-07-2020 0.50 Y 24-07-2020 0.50
Deptmtl execution
Deptmtl execution 0
Deptmtl execution NA 0 OG 0.21 42.24 31-03-2021 43% completed.
6 Urgent works for initial setting up at Model Lab for starting Modelstudy 2.00 Y 11-08-2020 2.00 Y 11-08-2020 2.00
Deptmtl execution
Deptmtl execution 0
Deptmtl execution NA 0
PLEASE REFER
REMARKS 1.90 95.00 01-01-2021 Not started.
7 Model study of Kuttiyadi Dam 2.00 Y 11-08-2020 2.00 Y 11-08-2020 2.00 Deptmtl
execution Deptmtl
execution 0 Deptmtl
execution NA 0 PLEASE REFER
REMARKS 0.00 0.00 10-03-21 Not started. This work can be started only after the completion of the work No.6 .
8 Maintenance of Instrumentation workshop building for using as a model lab 4.74 Y 05-08-2020 4.74 Y 10-08-2020 4.74 Y
Work Retenderedon
20/10/20 4.74 PLEASE
REFER REMARKS 0.00 0.00 01-03-2021
Not started. Work tendered agreement shall be done after 14/12/2020 .
Total 15.04 8
15.04 8 15.04 2
8.39 1 3.65 5(OG) 2.96 19.69
B) Coastal Engineering Division (Sub division office)
9 Fundamental Studies using Smart Station for the year 2020-21- Various Investigation survey works in Irrigation Department and Coastal survey using Smart station
11.05 Y
Y
Deptmtl execution
Deptmtl execution
Deptmtl
execution
OG
0.00 31-03-2021 Splitted in to 4 studies.remaining under preparation as per deptmtl requirement.
9A Conducting Topographical investigation for construction of check dam across Gayathri Puzha at Choondakkattil in Kavassery Panchayath-2020-2021
Above F.S split in to actual
requirements 11-08-2020 1.15
Above F.S split in to actual requirements
11-08-2020 1.15 Deptmtl execution
Deptmtl execution 0 Deptmtl
execution NA 0 PLEASE REFER
REMARKS 0.67 58.00 31-12-2020 96% completed.
9 B Topographycal investigation for demarcating submersible area of proposed Attapaddy Valley Irrigation project 202021
Above F.S split in to actual
requirements 06-10-2020 6.35
Above F.S split in to actual requirements
07-10-2020 6.35 Deptmtl execution
Deptmtl execution 0 Deptmtl
execution NA 0 PLEASE REFER
REMARKS 0.00 0.00 20-03-2021 10% completed. Work started on 16/11/2020 .
9C conducting topographical investigation for assessing the sedimentation in Peringad River in downstream of Idiyanchira regulator in Thrissur Dist.
Above F.S split in to actual
requirements 16-10-2020 0.75
Above F.S split in to actual requirements
18-10-2020 0.75 Deptmtl execution
Deptmtl execution 0 Deptmtl
execution NA 0 PLEASE REFER
REMARKS 0.00 0.00 31-03-2021 Not started. Work is proposed to be started on 04/01/2021.
9D Topographical investigation of KIP (RB) Main canal earth slippage at ch.17000m
Above F.S split in to actual
requirements 23-10-2020 1.40
Above F.S split in to actual requirements
26-10-2020 1.40 Deptmtl execution
Deptmtl execution 0 Deptmtl
execution NA 0 PLEASE REFER
REMARKS 0.00 0.00 31-03-2021 Work started on 13/10/2020 .35% completed
9E Topographical investigation in connection with the holistic linking of IIP and CRDS.
Above F.S split in to actual
requirements 13-11-2020 0.66
Above F.S split in to actual requirements
13-11-2020 0.66 Deptmtl execution
Deptmtl execution 0 Deptmtl
execution NA 0 PLEASE REFER
REMARKS 0.00 0.00 31-03-2021 30 % completed.
10 Routine activities of the Coastal Engineering Division office and the Offices of Director, F & AR and Joint Director, Hydraulic Research for the year 2020-21
1.50 Y 05-08-2020 1.50 Y 06-08-2020 1.50 Deptmtl execution
Deptmtl execution 0 Deptmtl
execution NA 0 OG 0.14 9.53 31-03-2021 10% completed
135
11 Maintenance of the model area of the Coastal Engineering Division and the office surroundings
0.40 Y 05-08-2020 0.40 Y 05-08-2020 0.40 Deptmtl execution
Deptmtl execution 0 Deptmtl
execution NA 0 OG 0.00 0.00 31-03-2021 30% completed. Partbill received for an amount of RS 14610/-
12 Annual Maintenance and purchase of accessories for Smart Station 1.50 Y 05-08-2020 1.50 Y 06-08-2020 1.50 Deptmtl
execution Deptmtl
execution 0 Deptmtl execution NA 0 OG 0.00 0.00 31-03-2021 10% completed.Submitted Part Bill-1 of Rs. 11653/-to
treasury 04/11/2020
Total 14.45 4.00
13.71 4.00
13.71
0.00
0 4(OG) 0.81 5.60
C) Sedimentation Division (Sub division office)
13 Fundamental studies of sedimentation survey various reservoirs- 9.32 Y
Y Deptmtl execution
Deptmtl execution 0
Deptmtl execution NA 0 OG 0.00 0.00 31-03-2021
Splitted in to 3 studies.remaining under preparation as per deptmtl requirement.
13.A Fundamental studies of sedimentation survey various reservoirsSedimentation Study of Pazhassi Reservoir using IBS and Sub Bottom Profiler
Above F.S split in to actual
requirements 07-08-2020 2.50 Above F.S split in to actual requirements
07-08-2020 2.50 Deptmtl
execution Deptmtl
execution 0
Deptmtl execution
NA 0 PLEASE REFER
REMARKS 0.00 0.00 15-03-2021 Not started. Request submitted for work advance on 10/11/2020. .
13.B Fundamental studies of sedimentation survey various reservoirsSedimentation -Sedimentation Study of Pothundy reservoir using IBS and Sub Bottom Profiler
Above F.S split in to actual
requirements 06-08-2020 1.25 Above F.S split in to actual requirements
07-08-2020 1.25 Deptmtl
execution Deptmtl
execution 0
Deptmtl execution
NA 0 PLEASE REFER
REMARKS 1.00 80.00 31-12-2020 60% completed.
13.C Sedimentation Study of Meenkara Reservoir using IBS and Sub Bottom Profiler Above F.S split
in to actual requirements 14-08-2020 1.20
Above F.S split in to actual requirements
17-08-2020 1.20 Deptmtl
execution Deptmtl
execution 0
Deptmtl execution
NA 0 PLEASE REFER
REMARKS 1.00 80.00 31-12-2020 55% completed.
14 Routine Activities of Sedimentation Division including upgradation of survey equipments and accessories 2.00 Y 03-08-2020 2.00 Y 03-08-2020 2.00
Deptmtl execution
Deptmtl execution 0
Deptmtl execution NA 0 OG 0.37 18.50 15-03-2021 30% completed
15 Upgradation of subbottom profiler by procouring a new dongle key 3.80 Y 24-08-2020 3.80 Y 28-08-2020 3.80 Y 16-10-2020 3.8 N
0 PLEASE REFER
REMARKS 0.00 0.00 31-12-2020 Work re- tendered due to no response in the first tender and retendered on 02/11/2020
Total 15.12 3
10.75 3 10.75 1
3.80 0 0.00 2(OG) 2.37 15.67
Grand Total- Joint Director Hydraulic Research (Division office) 44.61 15.00
39.50 15.00 39.50 3.00
12.19 1.00 3.65 11(OG) 6.14 13.77
Joint Director CM &FE, KERI,Peechi(Division office)
Instrumentation Division(Sub Division Office)
16 Upkeep and routine activities of publication wing including conducting Training and Seminars etc. 3.30 Y 22-09-2020 3.3 Y 25-09-2020 3.30
Deptmtl execution
Deptmtl execution 0
Deptmtl execution
Deptmtl execution 0 OG 0.00 0.00 01-03-2021
Amount alloted for the routine works for the financial year 2021 . One month training completed on 31.10.20 Bill under
prepration.
17 Routine activities of Instrumentation Division 1.21 Y 05-08-2020 1.21 Y 05-08-2020 1.21 Deptmtl
execution Deptmtl
execution 0 Deptmtl
execution Deptmtl
execution 0 OG 0.34 27.76 01-03-2021 Plant and Machinary repair works completed,Maintenance
work of office is on going
18 Revamping and modernisation of Instrumentation Division 2.50 Y 18-09-2020 2.50 Y 25-09-2020 2.50
Deptmtl execution
Deptmtl execution 0
Deptmtl execution
Deptmtl execution 0 OG 0.00 0.00 01-03-2021
Plant upgrading - Overhauling of plant, attaching new pump on plant completed.
19 Experimental Study of sediment sampling using newly fabricated Gravity Core Sampler 3.50 Y 28-09-2020 3.50 Y 29-09-2020 3.50
Deptmtl execution
Deptmtl execution 0
Deptmtl execution
Deptmtl execution 0 OG 0.00 0.00 01-03-2021 Work at inital stage.
20 Soil investigation for projects in Irrigation Department 4.50 To be issued
To be issued Deptmtl execution
Deptmtl execution 0
Deptmtl execution
Deptmtl execution 0
0.00 0 01-03-2021 This work can be taken up on any urgent requirement of this
Department
Total 15.01 4.00
10.51 4 10.51 0 0 0.00
0 0 4(OG) 0.34
Soil Mechanics And Foundation Division (Sub Division Office)
21 Up keep routine activities of SM Lab 3.00 Y 03-08-2020 3.00 Y 06-08-2020 3.00 Deptmtl execution
Deptmtl execution 0 Deptmtl
execution Deptmtl
execution 0 OG 0.17 5.58 01-03-2021
Amount alloted for routine works for financial year 20-21. Purchase of battery for UPS and purchase of stop watch is completed. Procurement of lab equipment and Maintenance of lab equipments is on going.Part bill of Rs. 24299/- is scrutening.
22 Fundamental Studies on Seismic refraction survey for subsurface profile investigation 1.00 Y 30-07-2020 1.00 Y 05-08-2020 1.00 Deptmtl
execution Deptmtl
execution 0 Deptmtl execution
Deptmtl execution 0 OG 0.00 0 01-03-2021 Part of research work,Literature study going on and
searching for the appropriate site.
136
23 Seismic tomography study on dams 4.00 Y 24-09-2020 4.00 Y 25-09-2020 4.00 Deptmtl execution
Deptmtl execution 0 Deptmtl
execution Deptmtl
execution 0 OG 0.00 0 01-03-2021 OnlineTraining on Geophysical Investigations for Dam Safety is completed and part bill of Rs. 3186/- is submitted. Skilled Rope Access professionals to be hired through quotation. Quotation opening on 07/12/2020
24 Charges for NABL accreditation process 2.00 Y 25-09-2020 2.00 Y 22-10-20 2.00 Deptmtl
execution Deptmtl
execution 0 Deptmtl
execution Deptmtl
execution 0 OG 0.00 0 01-03-2021 Selection notice issued for NABL facilitator on 9.11.2020
25 Fundamental Research on Geotechnical Engineering 1.00 Y 25-09-2020 1.00 Y 29-09-2020 1.00 Deptmtl execution
Deptmtl execution 0 Deptmtl
execution Deptmtl
execution 0 OG 0.00 0 01-03-2021 Research work,Literature study completed,materials
required for research activities to be purchased,Quotation opening on 07/12/20
Total 11.00 5
11.00 5 11.00
0.00 5(OG) 0.17
Construction Materials Division(Sub Division Office)
26 Supply of Rebound Hammer 2.36 Y 06-08-2020 2.36 Y 10-08-2020 2.36 Y 23-01-2020 2.36 07-03-2020 2.36 C 2.36 100 Completed Payment completed.
27 Routine Activities of CM lab 3.50 Y 03-08-2020 3.50 Y 10-08-2020 3.50 Deptmtl execution
Deptmtl execution 0 Deptmtl
execution Deptmtl
execution 0 OG 0.50 0.14 01-03-2021 Amount allotted for the routine works of lab (Purchase of consumables,maintenance of equipments, calibration, hiring labour charges etc) 1st Temporary Advance received Rs.50,000 on 29.09.2020. Deptmtl execution in progress, 15% Completed
28 Supply of Crack Microscope
0.85 Y 29.07.2020 0.85 Y 21-08-2020 0.85 Y 17.11.2020 0.85
Tender Proces Going On 0 OG 0.00 0 03-01-2021
1st tender published on 28.09.2020 (single tender), 1st Retender on 14.10.2020 opening on 03.11.2020 (No bids received), 2nd Retender on 02.11.2020 opening on 19.11.2020 (No bids received). 3rd Retender on 17.11.2020 opening on 07.12.2020.
29 Data acquisition system for Digital Compression testing ma c 6.00 Y 18.9.2020 6.00 Y 22-09-2020 6.00 Y
Appe C 07.10.2020,App e A 16.11.2020
6 Y (APP C on
03.11.2020), Tender process going on for App
A&B. 2.891 OG 0.00 0 03-01-2021
Estimate includes Appendix A,B,C. For Appendix A&C Tender published on 07.10.2020 opening on 27.10.2020, Selection Notice issued for Appendix C on 03.11.2020.Appendix A- 1st Retender on 02.11.2020, opening on 19.11.2020. 2nd re tendered on 16.11.2020 opening on 07.12.2020 Appendix B 1st quotation 25.09.2020, 2nd quotation 16.10.2020 (no quotation received), 3rd quotation on 05.11.2020 opening on
30 NABL Accreditation Fee, Consultation Fee, Attending Training Programme conducted by BIS etc required for NABL Accreditation
1.00 Y 21-10-20 1.00 Y 21-10-20 1.00 Deptmtl execution
Deptmtl execution 0 Deptmtl
execution Deptmtl
execution 0 OG 0.00 0 01-03-2021 Includes charges required for NABL accreditation process which mainly includes trainings to lab staff. Selection of NABL facilitator completed and Selection Notice issued to NABL facilitator. Deptmtl execution in progress
31 Expansion of Office facilities of CM lab for NABL accreditation
2.50 Y 03.08.2020 2.50 Y 08-10-2020 2.50 Y 29-09-2020 2.5
Tender Award Process Going
On 0 OG 0.00 0 01-03-2021 Negotiation letter issued to the contactor on 9.11.2020
32 Providing putty with neat epoxy painting work over wall surface of CM Lab for NABL accreditation
1.15
To be issued.
To be issued.
N To be tendered. 0
NA 0 Refer Remarks 0.00 0 01-03-2021 Selection of NABL accredtation expert is to be finalised.
The estimate will be finalised after completion of electrical work.work will start on 01-01-21
Total
17.36 6 16.21 6
16.21 4 11.71
5.25 5(OG),1(C) 2.86
Grand Total- Joint Director CM &FE, KERI,Peechi(Division office)
43.37 15.00 37.72 15.00
37.72 4.00 11.71
5.25 14(OG),1(C) 3.36
Q bill Amount (Expenditure)
12.009 12.01
GRAND TOTAL,KERI,PEECHI 100.00 30 77.225 30 77.225 7 23.90 1 9 25(OG),1(C) 21.51 21.51
Abstract of Weekly Progress of H/A: 4701-80-800-77 (P) Dam Rehabilitation and Improvement Project (DRIP)
Budget Allocation (2020-2021) (Rs Lakhs) 6300
DRIP- Phase I(2012-2021 March)
1 Overall AS (Rs Lakhs) 36000
2 Revised Allocation (Rs Lakhs) 32700
3 Total Expenditure up to date (including spillover) (Rs Lakhs) 24598
4 Percentage Expenditure up to date (including spillover) w.r.t revised allocation 75.22
5 Total Number of Dams 16
6 Institutional Strengthening ( Dam Safety Head Quarters, ISW Hub in Palakkad)
2
7 Total number of dams for which all packages completed 9
8 Number of packages(Civil, Mechanical, Electrical) 51
9 Number of packages completed 36
10 Number of packages ongoing 9
11 Number of packages to be awarded 6
12 Expenditure for 2020-21 (Rs Lakhs) 1752
13 % Expenditure for 2020-21 w.r.t allocation for 2020-21 27.81
DRIP- Phase II(2020-2026)
1 Overall AS (Rs Lakhs) 24000
2 In principle approval from CWC for "Works" 16590
3 Total Number of Dams 15
4 Number of TS issued 1
139
Externally Aided Projects 2020-21 - Weekly Progress Report
H/A:- 4701-80-800-77 (P) Dam Rehabilitation and Improvement Project (DRIP)
Allocation of Rs 6300 Lakhs (Phase I + Phase II)
Sl. No. Head of Account/ Name of the Project
Project Cost* (Rs Lakhs)/allocation
by WB AS Accorded
(Date of AS) AS Amount* (Rs Lakhs)(by GoK)
TS Issued (Date of TS)
TS Amount* (Rs Lakhs)
Tendered (Date of Tender)
Tendered Amount*
(Rs Lakhs)
Awarded (Date of
Awarding work)
Awarded Amount* (Rs Lakhs)
Work Status: Completed (C)
or Ongoing (OG)
Expenditure* (Rs
Lakhs) Expenditure % Remarks
Completed works under DRIP Phase I-( for which final bills pending for payment )
1 Construction of new bridge for diversion of traffic for safety of old barrage (at Bhoothathankettu)
Original cost15800
revised cost(1)-36000
Final revised cost- 32700
06-02-2013 Revised AS
29- 01-2016
Original AS- 15800 Revised AS -36000
24-02-2016 1940 29-02-2016 1795.56 18-05-2016 1998 C 1815 91 Completed on 13/01/2020.Bills pending payment -183Lakhs for
want of approval of RE from Govt
2 Rehabilitation and Improvement of basic facilities of Chimoni Irrigation Project- Civil Works-
19-06-2015 1635 23-07-2015 1598.98 20-01-2016 1241 C 1230 99
Completed on 14/04/2020 Final executed amount is 12.41
crores. Bills pending payment - 11
Lakhs, for want of approval of variations from Govt
3 Electrical Works of Kuttiyadi Irrigation Project – KyIP Peruvannamuzhi- Renovation of Electrical Installation
22-04-2016 78 29-09-2016 76.42 09-03-2017 71.31 C 47 66 Completed on 25/07/2019. Bills pending payment -24.31 Lakhs
4 Rehabilitation and Improvement of Basic Facilities of Moolathara Regulator
24-02-2016 4950 01-03-2016 4904.14 17-07-2017 5777 C 4918 85 Completed on 31/05/2020.Bills
pending payment -859Lakhs, for want of approval of RE from
Govt
5 Rehabilitation and Improvements of Basic Facilities of Pazhassi Irrigation Project (Civil Works)
19-06-2015 716 11-11-2015 699.4 06-08-2016 676 C 667 99 Completed on 05/11/2018. Final
executed amount is 6.76 crores.Bills pending payment
9Lakhs
6 Rehabilitation and Improvements of Basic Facilities of Peechi Irrigation Project (CivilWorks)
20-10-2015 151 15-07-2015 150.8 01-03-2016 253 C 243 96 Completed on 01/07/2019.Bills pending payment -10Lakhs
7 DRIP- Rehabilitation and improvement of basic facilities of Walayar Irrigation Project(Civil, Mechanical, Electrical)
07-06-2013 505 23-06-2016 501 23-12-2016 638 C 624 98 Completed on 26/12/2018.Bills pending payment -14Lakhs
140
8
DRIP-Rehabilitation and improvements of Basic facilities of Muvattupuzha Valley Irrigation Project - Construction of Comfort Station , Jet washing of dam, Providing hand rail at river training wall , Improvements of perumattom to Dam road.
16-10-2019 107 21-12-2019 107.16 27-02-2020 83 C 49.55 60 Completed on 28/08/2020. Bills pending payment -33.45 Lakhs,
bills under preparation
9
Rehabilitation and improvement of basic facilities of Meenkara Irrigation Project (Electrical)
18-07-2019 54 15-11-2019 48.1 - 47.6 C 0 0 Completed on 30/09/2020. Bill
under preparation
10
Electrical Works of Chimoni Irrigation Project-Renewal of damaged fitting of dam top lighting and gallery lighting and providing Generator at Chimoni dam
18-07-2019 90.15 19-10-2019 72.07 05-03-2020 71.13 C 0 0 Completed on 30/09/2020. Bill under preparation
11 DRIP-KyIP-Construction of Inspection Bungalow (Annex) and Control Room building at Peruvannamoozhi Dam site
03-05-2019 125 04-11-2019 109.08 12-02-2020 119.8 C 33 28 Completed on 31/10/2020.
Total 11 10351.15 11 10062.71 10975.84 11 9626.55
Ongoing Works under DRIP Phase I
1 Rehabilitation and basic facilities of Neyyar Irrigation Project – Civil works
07-06-2013 407 16-05-2015 407 04-01-2016 589 OG 292 50 Work expected to be completed on 30/11/2020.Physical progress
of the work is 68%
2 Dam Safety Head Quarters(Civil ) 22-04-2015 2450 08-03-2016 2415 06-06-2018 2926 OG 1243 42 Work expected to be completed on 31/03/2021.Physical progress
of the work is 52%
3
Rehabilitation and improvement of basic facilities of Kanhirapuzha Irrigation Project - sub estimate for block joint treatment and spillway pier rehabilitation
05-03-2019 82.43 23-11-2019 82.43 03-03-2020 73 OG 69 95 Work expected to be completed on 30/11/2020.Physical progress
of the work is 95%
4 Rehabilitation and Improvement of basic facilities of Kuttiyadi Irrigation Project (Civil works)
24-02-2016 2220 01-03-2016 2180.44 06-08-2016 1685 OG 1272 75 Work expected to be completed on 31/12/2020.Physical progress
of the work is 86.45%
5
Enabling ISW Hub in Palakkad with data interpretation centre and dam safety training faccility phase I Interior furnishing ,landscaping ,setting up data interpretation centre ,ISW museum ,ISW dcuments library & archives
06-01-2020 72.4 21-01-2020 49.61 26-03-2020 73.62 OG 26 35 Work expected to be completed on 30/11/2020.Physical progress
of the work is 42.5%
141
6
Enabling ISW Hub in Palakkad with data interpretation centre and dam safety training facility phase IIConstructin of first floor and furnsihing interior with necessary amenities
Original cost15800 revised cost(1)-36000 Final revised cost- 32700
06-02-2013 & 29-01-2016 (Revised AS)
Original AS- 15800 Revised AS -36000
06-01-2020 189 15-02-2020 153.81 13-05-2020 202 OG 87 43 Work expected to be completed on
30/11/2020.Physical progress of the work is 57.20%
7
DRIP- Construction of new bridge for Diversion of Traffic for safety of old Barrage at Bhoothathankettu (Electrical) – Providing street lights in new bridge at Bhoothathankettu
05-12-2019 22.96 19-02-2020 22.96 09-09-2020 18.57 OG 0 0 Agreement Executed. Work to be started. TOC 3 months
8
Rehabilitation and Improvement of Basic Facilities of Parappar dam in Kallada Irrigation Project (Balance Civil works) Epoxy plastering, road work and applying tack coat
27-02-2019 101 10-03-2020 101 14-09-2020 95.09 OG 0 0 Site handed over on 23/09/2020. Work expected to be completed on
22/03/2021
9 DRIP- Electrical Works of Neyyar Irrigation Project-Electrification of Control Room and Canteen Building
18-07-2019 9.25 01-10-2020 8.24
9.24
Agreement to be executed. TOC 3 months
10 Instrumentation of all dams 27-02-2019 950 07-09-2019 950 09-03-2020 549 OG 0 0 Work awarded .supply to be
started & expected to be completed on 31/03/2021
Consultancy to Architect for Construction of Dam Safety head Quarters in PMG Thiruvanathapuram
27-04-2020
11-05-2020 75.6 OG 17 22 Structural drawings received from
architect.MEP drawings to be receieved
Total 9 6504.04 9 6370.49 9 6296.12 9 3006
Works under DRIP Phase II
H/A 4701-80-800-77 (P)
1
Stabilization of Kuttiyadi Dam by providing supporting concrete structure on the downstream face and allied structures (Civil works) under DRIP II
Overall Project cost
16600 22/07/2020 & 21/08/2020 Overall AS -24000 24-08-2020 3514 25-08-2020 3070
TS issued is inclusive of 12% GST. Technical bid opened on
28/10/2020. Evaluation being done at Project Circle , Kannur
Total 1 3514 1 3070 0 0 0 0
142
Appendix IV- Works under Rebuild Kerala Initiative (RKI)
Name of Work Development of Kerala Water Resources Inforation System
Division Hydrology Division, IDRB
Administrative Sanction Order No, date, Amount
GO (Rt) No. 918/2019/WRD dated 07.12.2019 for an amount of Rs. 3.80 crores
Technical Sanction Order No, date, Amount TS accorded on 03.02.2020 vide order no. HYD-AD3/6/2019-IDRB/1
Agreement No and date Agreement signed on 20.02.2020 (T)
Agreed Amount(In Rs) Rs. 3.215 crores + Applicable taxes
Name of contractor M/S Nabard Consultancy Services
Site Handover Date 20.02.2020
Period of completion 9 months
Description
Kerala-Water Resources Information System (Kerala-WRIS) is a stateof-the-art platform which is proposed to be a comprehensive, dynamic and well-structured Information and Management System to facilitate and ensure judicious, equitable and sustainable management, allocation and utilisation of water resources. For effective water budgeting, its planning, conservation and sustainable management, the development of WRIS is one of the top most a priority for the State. Kerala -WRIS will act as a single authoritative system for all water resources related information, its budgeting as per hydrology norms and its monitoring.
Officer in charge and contact details
Sandhya S G Joint Director (Hydrology) Irrigation Design and Research Board Ph: 9446595509
Present Progress
Name of Work Development of Kerala Water Resources Inforation System
Date 12.11.2020
Physical Status Stage in % 65%
Financial Status Stage in 28% (Part payment made )
143
Description of Current status
1) First Milestone:- Completed (T+2 weeks: 05.03.2020) - Invoice against first deliverable for Rs 70,68,200/- submitted to Government vide letter no No. HYD-AD2/4/2020-IDRB dated 30.04.2020 - Payment of Rs. 70 lakhs only was alloted by government vide GO (Rt) no. 228/2020/P&EA dated. 27.05.2020
2) Second Milestone:- Completed (T+2 months: 20.04.2020) - Invoice against second deliverable (Rs. 35,34,100/-) and balance amount of Rs 68,200/- from first invoice, amounting to total of Rs. 36,02,300/- submitted to Government letter no No. HYD-AD2/4/2020IDRB dated. 16.07.2020
3) Third Milestone:- Component 3a (Water Availability Module) - Development and Evaluation completed Invoice against deliverable (Rs. 35,34,100/-) submitted to government.
4) Fourth Milestone:- Component 3b (Water Demand Module) - Development Completed, Evaluation Pending
5) Fifth and Sixth Milestone:- Components 3d & 3c (Water Budget and Audit Modules) - Progressing
Expected date of completion 31.12.2020
144
Appendix V- KIIFB projects (Design)
Sl
No: Name of Work Design status Remarks
1
Construction of RCB upstream of Perincherikadavu across Kuttiady river (Gulikapuzha) in Kozhikode District.
Design completed and forwarded on 09/08/2016.
Revised design forwarded on 04.02.2019
Revised drawing forwarded on 04/02/2019
2
MRVP Construction of Regulator cum bridge across Meenachil river at Koottanalkadavu in Bharananganam Pt
Design completed and forwarded on 17/06/2015
3 Construction of Regulator at Puzhankavu across Kadalundi River
Design completed and forwarded on 18/04/2015
4
Construction of RCB across Kuppam river at KooveriKattampally in Chapparappadavu Panchayat in Kannur Dt
Design completed and forwarded on 05/05/2014
5 MRVP Construction of Minidam cum regulator at Chempilavu in Kidangoor Panchayath-
Design completed and forwarded on : 10/12/2014
6
Construction of Regulator across Chaliyar river at Pannippara – Pallimukku in Edavanna Panchayath
Design completed and forwarded on 05/05/2014
7
Construction of RCB across Thootha River at Keezhumurikkadavu - Mothikkayam in Moorkkanad Panchayath of Malappuram Dist in Mankada LAC
Design completed and forwarded on 08/02/2015
8
Construction of RCB at Kankakadavu across Bharathapuzha in Kuttippuram Panchayath
Design completed and drawing forwarded on 14.8.2019.
9
Construction of a regulator cum bridge across Chittoor puzha at Vadakarapalli, Palathully in Perumvemba and Polpully Grama Panchayath in Palakkad District
Design completed and forwarded on Date: 16/04/2018
10
Construction of RCB across poonurpuzha near KWA pumping house at poolakkadave in Kozhikode District
Design completed and forwarded on 19/05/2018
11
Construction of Regulator across Chaliyar river at Kalathumkadavu in Nilambur Municipality in Nilambur LAC
Design completed and forwarded on 08/10/2017
12 Construction of a Regulator cum Bridge at the D/s of LIS Kaladikunnu in
Design of RCB completed and forwarded on 19/05/2018. Design revised as Regulator
cum foot bridge and
145
Thiruvegapura Panchayath Revised design of Regulatorcum foot bridge forwarded to CE(I&A) on 13.05. 2020
forwarded to CE I&A on 13/05/2020, for onward transmition to KIIDC subject to feasibility of the site.
13
Construction of Regulator at Parapram across Anjarakkandy river in Pinarayi Grama panchayath in Kannur District
Design completed and forwarded on 13/08/2018
14
Constuction of regulator across Muvattupuzha at Poothotta in Chembu Panchayath in Kottayam District
The details submitted by field officers are not sufficient for taking up the design work. Also, indent for design received is incomplete and not in standard format. Documents submitted were not authenticated. Addressed CE(I&A) and site officials to expedate the same.
Details awaiting
15
Construction of Regulator cum Bridge with lock across Muvattupuzha river at Ithipuzha in Vaikom Constituency.
The details submitted by field officers are not sufficient for taking up the design work. Also, indent for design received is incomplete and not in standard format. Documents submitted were not authenticated. Addressed CE(I&A) and site officials to expedate the same.
Indent received is incomplete.
16
Construction of Regulator cum Bridge with lock across Muvattupuzha river at Murinjapuzha in Vaikom Constituency.
Indent for design not received. Details received incomplete.
17
Construction of Regulator cum Bridge with lock across Meenachil river at Thazhathangadibhagom in Arpookara GP and Kottayam Municipality.
Site officials reported for shifting the site for incorporating KWA pump house on d/s of the proposed site. Letter to CE(I&A) forwarded on 17/12/2019 and reminded on 04.02.2020 & 29.02.2020 for clarifying the same. Addressed CE(I&A) on 25/06/2020 for a convenient date for conducting a joint inspection for finalizing an alternate site.
Even though the Chief Engineer (I&A) proposed date for site inspection, the same could not be conducted due to the present pandemic situation. New date for site visit fixed on 14/10/2020.
18
Construction of regulator across Manimala river on the downstream side of Paduthodu Bridge for the benefit of RWSS to PuramattamandEzhumattoor
Design completed and forwarded on 02/06/2018
19
Construction of regulator across Achenkovil river on the downstream side of Kaipattur bridge for the benefit of WSS to AdoorMunicipality, Ezhamkulam
Design completed and forwarded on 26/06/2018
146
,Enath, Erath,Pallikkal and Omallur Panchayaths Kuttanad Water Supply Scheme in Pathanamthitta District
20
Construction of regulator across Pampa river in MundapuzhaThottamon in Ranny Panchayat for the benefit of RWSS to RannyPazhavangadi and Vadasserikkara Pt
Design completed and forwarded on 01/ 10 /2018
21
Construction of regulator cum bridge across Neyyar River at Mavilalakadavu downstream of KWA pump house to prevent salinity intrusion
Design completed and forwarded on 06/03/2019
22 Construction of SWECB at Kanchiakatte across Kumbla river in Kumbla Panchayath
Design completed and forwarded on 07/02/2020
23 Construction of a new regulator across Konothupuzha
Design completed and forwarded on 21/05/2018
24
Construction of Regulator across Ummanchira river at Chekku Palam in Pinarayi Grama panchayath in Kannur District
Design completed and drawings forwarded on 5.9.2019.
25
Construction of Regulator across Vamanapuram river at Ayilamkadavu in Mudakkal Panchayath
In the minister level meeting held on 27.05.2019, it was decided to construct 2 checkdams at Ayilamkadavu and near Karettu bridge. Proposal for design yet to be received from field office.
26
Construction of Salt water extrusion Regulator across Poorapuzha at D/s of Kettungalthodu (near Kettungal beach) between Parappanangadi and Tanur Municipality.
Reported pile capacity found insufficient for an economic design.Hence addressed field officers for further soil investigation for taking boreholes extended upto hard rock, such that desired soil capacity may be achieved.
As the site is very near to the sea mouth, it was also requested to propose an alternate site if the present site is not feasible.
27
Construction of RCB across Kuppam river at Up stream of Kuppam Bridge in Pariyaram Panchayath in kannur District.
Design completed and forwarded on 26/04/2019
147
28
Construction of SWECB at Chithari Upstream of old Chithari Regulator in Pallikkara Panchayat
Indent from CE(I&A) received on 05/03/2019. Clarifications sought (vide letter dt.02/04/2019) but details yet to be received. Site officials (vide letter dt: 27.01.2020) informed that provision for lock is necessary.Proposal and details for lock to be received from CE(I&A)
Design in progress with the details furnished by site officials.
148
Appendix VI- SDRF Works 2020-21
SDRF Works 2020-21 - Weekly Progress Report under Irrigation Division Thrissur)
H/A:-
Allocation of Rs 1237.67Lakhs
-2 Head of Account/ Name of the Project Project Cost* (Rs
Lakhs)
AS Accorded (Date of AS)
AS Amount* (Rs Lakhs)
TS Issued (Date of TS)
TS Amount* (Rs Lakhs)
Tendered (Date of Tender)
Tendered Amount*
(Rs lakhs)
Awarded (Date of
Awarding work)
Awarded Amount*
(Rs)
Work Status: Completed (C) or
Ongoing (OG) Expenditure* (Rs Lakhs) Expenditure % Target date of
completion
Thrissur Sub Division
1 SDRF-Urgent rectification works to the Amballur branch canal in between ch 10/300 to 10/700 15 03.06.2019 15 04.06.2019 15 06-06-2019 13.28726 2.8.2019 12.30064 C 4.509 30.06
2 SDRF-Urgent rectification works to the Amballur branch canal in between ch 9/200 to 9/900 15 03.06.2020 15 04.06.2019 15 06-06-2019 13.2826 2.8.2019 12.4824 C Nil Nil
3
SDRF-Rectification And Leak Proofing Works To TDC Including Spout,BundProtection And Leading Channel At Swapnabhoomi In Kolazhy Panchayat 7.4 30.05.2019 7.4 31.05.2019. 7.4 09-10-2019 6.5227933 13.11.2019 6.5228 C 6.11387 82.62
4 SDRF-Rectification of Spout No.II At Arangazhikulam In Mulamkunnathukavu Panchayat 8.9 10.07.2019 8.9 10.07.2019 8.9 09-10-2019 7.85548 23.11.2019 7.85548 C 7.72659 86.81
5 SDRF-Rectification of Spout At Uthramkulangara Branch Canal Including Repair to Branch Canal Wadakkanchery 12 02.07.2019 12 04.07.2019 12 25-09-2019 10.67029 30.12.2019 10.67029 C 11.3645 94.55
6 SDRF- Rectification And Leak Proofing Works To TDC Between Ch.0/850 KM and 0/950M 23.30 25-05-2019 23.30 25-05-2019 23.3 12-06-2019 20.8 24.09.2019 20.58
70% completed. Covid and the rain
stared from 03.09.2020. Nil
30.11.20
7 SDRF- Rectification And Leak Proofing Works To TDC Between Ch.0/950 KM and 1/060M 23.30 28-05-2019 23.30 30-05-2019 23.3 12-06-2019 18.66596 04.10.2019 18.67 C 18.6543 80.06
8 SDRF-Rectification of Breached Canal of Kolazhy Branch At Ch..0/600 Km 3 02.08.2019 3 05.08.2019 3 09-10-2019 2.61735 11.11.2019 2.61735 C 2.5646 85.48
9
SDRF-Rectification of Spout No.1 At Arangazhikulam Including Repair to Canal In TDC At Ch.20/000 KM In Mulamkunnathukavu Panchayat 17.6 03-06-2019 17.6 06-08-2019 17.6 14-08-2019 15.64 16.11.2019 15.39 C 15.2091 86.4
10 SDRF-Rectification of Spout At Tail End of TDC Including Leading Channel In Wadakkanchery 9 .02.07.2019 9 04.07.2019 9 8.7.2019 8.03068 30.12.2019 8.03068 C 7.74999 86.07
134.5 134.5 134.5 117.37241 115.11964
Head Works Sub Division- Peechi 73.89195
11 SDRF PS Flood Related Works - Urgent Rectification works to Koottala Branch Canal from Ch0/200 Km to 0/500 Km 20 09-05-2019 20
IDTsr/201819/2018/ 3706/ IA dated
30/05/2019 20 Lakh 20 20.7.2019 20 12/EE/2019-20 dt 30.9.2019 16.83 C 18.85
12 SDRF PS Flood Related Works -Rectification works to Koottala Branch Canal from Ch 2/800 Km to 3/200 Km 28.5 10-05-2019 28.5
IDTsr/2019- 2020/2018/5598/ IA
dated 30/05/2019 28.5 Lakh
28.5 1.7.2019 28.5 29/EE/2019-20 dt 24.12.2019 25.12 C 27.012
13 SDRF PS Flood Related Works -Urgent Rectification works to Koottala Branch Canal from Ch 4/000 Km to 4/400 Km 25 9.5.2019 25 21.6.2019 25 27.7.2019 22.32 28.11.2019 C 24.99
14 SDRF PS Flood Related Works - Side lining of Koottala Branch Canal from Ch 5/400 to 5/800 Km for the year 2018-2019. 21.5 09-05-2019 21.5
IDTsr/2019- 2020/2018/1353/ IA
dated 31/05/2019 21.5 Lakh
21.5 1.7.2019 21.5 23/EE/2019-20 dt 28.11.2019 18.67 OG
149
15 SDRF PSM-Urgent Rectification and allied works of Apron D/S of stilling Basin For the year 2018-2019. 65 10-05-2019 65
IDTsr/2019- 2020/2018/5500/ IA
dated 16/08/2019 65 Lakh
65 4.11.2019 65 1/EE/2020-21 dt 5/5/2020 58 work started
16 SDRF PS-Protection Works & Leak Proofing Works Of RBMC From Ch 2/400 Km to 2/600 Km for the year 2018-2019. 15
IDTsr/2018/1350/ IA dated
09/05/2019 15 Lakh 15
IDTsr/2019- 2020/2018/1350/ IA
dated 01/06/2019 15 Lakh
15 24.08.2020 15 31/AEE/2020- 21 dt 9/9/2020
13.24 C 14.8
17 SDRF Peechi Scheme-Protection & Leak Proofing Works Of RBMC From Ch 3/200 Km to 3/350 Km for the year 2019-2020. 13.1
IDTsr/2019/7617/ IA dated26-09-
2019 13.10 Lakh 13.1
IDTsr/20192020/2019/7617/ IA dated27-09- 2019 13.10 Lakh 13.1 26.6.2020 13.1
35/AEE/2020- 21 dt 28/9/2020
11.64 Not Started
18 SDRF- Peechi Scheme-Flood related urgent works & Leak Proofing Works Of RBMC From Ch 5/400 Km to 5/600 Km for the year 2018-2019.
20 IDTSR/2019/ 3131/
IA dated 09/05//2019 20 Lkh
20
IDTSR/2019- 2020/2019/ 3131/ IA
dated 17/08/201920 Lakh
20 12.3.2020 20
C 17.32
19 SDRF Peechi Scheme-Protection & Leak Proofing Works Of LBMC From Ch 4/700 Km to 4/800 Km for the year 2019-2020. 5.7
IDTsr/2018/1354/ IA dated
18/09/2019 5.70 Lakh
5.7
IDTsr/2019- 2020/2018/1354/ IA
dated 27/09/2019 5.70 Lakh
5.7 30.03.2020 5.7 14/AEE/2020- 21 dt 18.6.2020
5.03 C 5.44
20 SDRF Peechi Scheme-Protection & Leak Proofing Works Of LBMC From Ch 5/100 Km to 5/200 Km for the year 2019-2020. 10.7
IDTsr/2019/7714/ IA dated
18/09/2019 10.70 Lakh
10.7
IDTsr/2019- 2020/2019/7714/ IA
dated 18/09/2019 10.70 Lakh
10.7 18.01.2020 10.7 81/AEE/2020- 21 dt 14.2.2020
9.4 C 10.5
21 SDRF PSM- Urgent Rectification works toLBMC Ch2/900 Km to 3/000 Km For the year 2018-2019. 20
IDTsr/2018/5504/ IA dated
09/05/2019 20.00 Lakh
20
IDTsr/2019- 2020/2018/5504/ IA
dated 06/08/2019 20.00 Lakh
20 16.10.2019 20 30/AEE/2019- 20 dt 9.8.2019
11.57 C 17.36
22 SDRF Peechi Scheme- Flood RelatedWorks-Urgent Rectification works at RBMC from Ch 5/000 Km to 5/200 km 50
IDTsr/2019/3707/IA Dated: 10- 05-2019 50.00 Lakh
50 IDTsr/2019-
2020/2019/3707/IA dated 30/07/2019
50.00 Lakh 50 6.8.2019 50
30-9-2020
23 SDRF -PEECHI SCHEME-PROTECTION WORKS AND LEAK PROOFING WORKS OF LBMC FROM- Ch 5/400 Km to 5/600 Km FOR THE YEAR 2019-2020.
22.8 IDTsr
/2018/1352/IA dt. 22.80 Lakh
22.8 IDTsr/2019-
2020/2018/1352/IA dt.11/11/2019 22.80 Lakh
22.8 12.3.2020 22.8 22.07.2020 20.25 C 22.587
24 SDRF-PEECHI SCHEME-PROTECTION & LEAK PROOFING WORKS OF LBMC CH.4/400to 4/600 Km. FOR THE YEAR 20192020.
30 IDTsr/2019/7713/IA dt 28.9.2019 30.00
Lakh 30
IDTsr/2019/7713/I A dt 25.2.2020
30.00 Lakh 30
30
OG
25 Natural calamity 2018 SDRF - Urgent rectification works to the LBMC from Ch. 44/600 to 44/700 Km 7.83
IDTsr/2019/10271/ IA dt
18.1.2020 7.83
IDTsr/2019/10271 /IA dt.1.2.2020
7.83 16.03.2020 7.83 9/AEE/20-21
dt 19.5.2020 6.15 C 6.898
26 SDRF - Natural calamity - Urgent rectification works between Ch. 3/200 to3/400 K m of Kallur Branch Canal 6.3 IDTsr/2019/7000/I
A dt.2.3.2020 6.3 IDTsr/2019/7000/I A dt.5.3.2020 6.3 12.3.2020 6.3 3/AEE/20-21
dt 19.5.2020 5.38 C 6.02
27 SDRF -PSM - 2018 - Urgent rectification works to Kallur Branch Canal between Ch. 3/600 KM to 3/800 KM 9
IDTsr/2018/1380/I A
dt.23.3.2020
9 IDTsr/2018/1380/I A dt.25.3.2020
9 08.04.2020 9 4/AEE/20-21
dt 19.5.2020 7.73 C 13.369
28 SDRF-Natural Calamity 2018-Urgent rectification to LBMC from ch:18/400 to 18/600 Km 15
IDTsr/2018/4271/I A
dt.8.5.2019
15
IDTsr/2018/4271/I A
dt.28.5.2019
15 12.3.2020 15 28/AEE/20-21 dt 9.9.2020 13.36 OG
29 SDRF-Natural Calamity 2018-Urgent rectification works to the LBMC from ch.19/650 to 19/790 KM 15
IDTsr/2018/6032/I A
dt.8.5.2019
15
IDTsr/2018/6032/I A
dt.17.5.2019
15 30.05.2019 15 8/AEE/19-20 dt 5.7.2019 12.72 C 12.89
30 SDRF-Natural Calamity 2018-Urgent rectification works to the LBMC from ch.19/790 to 19/930 KM 15
IDTsr/2018/4220/I A
dt.8.5.2019
15
IDTsr/2018/4220/I A
dt.15.5.2019
15 07.06.2019 15 4/AEE/19-20 dt 2.7.2019 12.84 C 13.37
150
31 SDRF-Natural Calamity 2018-Urgent rectification works to the LBMC from ch.19/930 to 20/070 KM 15
IDTsr/2018/5259/I A
dt.8.5.2019
15
IDTsr/2018/5259/I A
dt.15.5.2019
15 10.06.2019 15 6/AEE/19-20 dt 5.7.2019 12.72 C 13.15
32 SDRF-Natural Calamity 2018-Urgent rectification works to the LBMC from ch.20/070 to 20/210 KM 15
IDTsr/2018/5260/I A
dt.8.5.2019
15
IDTsr/2018/5260/I A
dt.15.5.2019
15 30.05.2019 15 7/AEE/19-20 dt 5.7.2019 12.69 C 13.14
33 SDRF-Natural Calamity 2018-Urgent rectification to Puthur branch canal from ch.2/200 to 2/400 Km 6
IDTsr/2018/1189/I A
dt.9.5.2019
6
IDTsr/2018/1189/I A
dt.18.5.2019
6 07.06.2019 6
Agreement executed.
34 SDRF- Natural calamities--Construction of Syphon canal in between Ch.3/400 KM and 4/000 KM of Kallur Branch canal in Ward No. 17 of Trikkur GP
15
IDTsr/2018/5792/I A
dt.9.5.2019
15
IDTsr/2018/5792/I A
dt.27.6.2019
15 23.07.2019 15 39/AEE/19-20 dt 3.10.2019 13.3 C 14.28
35 SDRF-Natural Calamity 2018-Urgent rectification works to LBMC at ch.38/400 of LBMC 38/800
6
IDTsr/2018/3471/I A
dt.9.5.2019
6
IDTsr/2018/3471/I A
dt.28.5.2019
6 29.06.2020 6 22/AEE/20-21 dt 21.08.2020 5.28 C 5.887
36 SDRF- Natural calamity -Urgent Rectification works to the Kallur branch canal between ch.1/200 to1/400 Km. 6.25
IDTsr/2018/3115/I A
dt.7.6.2019
6.25
IDTsr/2018/3115/I A
dt.10.6.2019
6.25 06.07.2019 6.25 34/AEE/19-20 dt 16.8.2019 5.32 C 5.96
37 SDRF- Natural calamity -Urgent Rectification works to the LBMC between ch.10/600 to 10/700 Km. 6
IDTsr/2018/3469/I A
dt.18.9.2019
6
IDTsr/2018/3469/I A
dt.27.9.2019
6 29.06.2020 6 30/AEE/20-21 dt 9.9.2020 5.31 OG
38 SDRF- Natural calamity -Urgent Rectification works between Ch. 6/000 to 6/200 KM of Puthur branch canal. 7.5 IDTsr/2019/2999/I A
dt.29.8.2019 7.5 IDTsr/2019/2999/I A dt3.9.2019 7.5 16.10.2019 7.5 51/AEE/19-20
dt 11.11.2019 6.42 C 7.17
39 SDRF- Natural calamity -Urgent Rectification works between ch.9/600 to 9/800 KM of Puthur branch canal. 9.4
IDTsr/2019/4360/I A dt.16.8.2019
9.40 9.4
IDTsr/2019/4360/I A dt.27.8.2019
9.40 9.4 28.10.2019 9.4 76/AEE/19-20
dt 27.12.2019 8.37 C 9.38
40 SDRF- Natural calamity -Urgent Rectification works to LBMC between ch.17/200 to 17/400 KM 7 IDTsr/2019/3125/I A
dt.16.8.2019 7 IDTsr/2019/3125/I A dt.26.8.2019 7 28.06.2020 7 29/AEE/19-20
dt 9.9.2020 6.24 C 11.03
41 SDRF- Natural calamity -Urgent Rectification works to LBMC between ch.42/810 to 42/900 KM 5.7 IDTsr/2019/3465/I A
dt.16.8.2019 5.7 IDTsr/2019/3465/I A dt.26.8.2019 5.7 11.10.2010 5.7 69/AEE/19-20
dt 13.12.2019 5.03 C 5.63
42 SDRF- Natural calamity -Urgent Rectification works between ch.2/500 to 2/700 KM of Kallur branch canal 9 IDTsr/2019/3450/I A
dt.16.8.2019 9 IDTsr/2019/3450/I A dt.26.8.2019 9 11.10.2019 9 67/AEE/19-20
dt 13.12.2019 7.93 C 8.77
43 SDRF- Natural calamity -Urgent Rectification works to the Puthur branch canal between ch.5/200 to 5/400 Km. 12.8 IDTsr/2019/3128/I A
dt.29.5.2019 12.8 IDTsr/2019/3128/I A dt.31.5.2019 12.8 14.06.2019 12.8 28/AEE/19-20
dt 9.8.2019 9.96 C 12.68
44 SDRF- Natural Calamity- Peechi Scheme-Urgent rectification works of RBMC at Ch. 8/550 Km to 8/ 650 Km 5.2
No. IDTsr/2019/ 3485/IA Dated: 9.5.2019
5.2 No. IDTsr/2019/ 3485/IA
Dated: 13.5.2019 5.2 22.07.2019 5.2
43/AEE/2019- 20 dtd
21/10/2019 4.63 C 5.05
45 Natural Calamity-Peechi Scheme-Urgent rectification works or RBMC at ch.8/750 to 8/850 4.6
No. IDTsr/2019/ 3486/IA Dated: 9.5.2019
4.6 No. IDTsr/2019/ 3486/IA
Dated: 13.5.2019 4.6 18.05.2019 4.6
03/AEE/2019- 20 dtd
15/06/2019 4.1 C 4.57
10.87
46 Peechi Scheme-Natural Calamity-Urgent rectification works of RBMC at Ch. 10/600 Km to 10/700Km 11.7
No. IDTsr/2019/ 3477/IA Dated: 9.5.2019
11.7 No. IDTsr/2019/ 3477/IA
Dated: 13.5.2019 11.7 07.06.2019 11.7
17/AEE/2019- 20 dtd
27/07/2019 10.36 C
47 Peechi Scheme-Natural Calamity-Urgent rectification works of RBMC at Ch. 14/950 Km to 15/100 Km 12.5
No. IDTsr/2019/ 3487/IA Dated: 9.5.2019
12.5 No. IDTsr/2019/ 3487/IA
Dated: 13.5.2019 12.5 18.06.2019 12.5
22/AEE/2019- 20 dtd
05/08/2019 11.1 C 11.92
48 Peechi Scheme-Natural Calamity-Urgent rectification works of RBMC at Ch. 15/850Km to 15/900 Km 14.4
No. IDTsr/2019/ 6996/IA
Dated: 29.5.2019 14.4
No. IDTsr/2019/ 6996/IA Dated: 1.6.2019
14.4 27.05.2019 14.4 14/AEE/2019-
20 dtd 16/07/2019
12.82 C 14.36
151
49 SDRF-Natural Calamity 2018-Urgent rectification to Mudikkodu branch canal 1/040 to 1/100 Km 7.3
No. IDTsr/2019/ 3476/IA Dated: 9.5.2019
7.3 No. IDTsr/2019/ 3476/IA
Dated: 13.5.2019 7.3 10.06.2019 7.3
31/AEE/2019- 20 dtd
14/08/2019 6.47 C 7.18
50 SDRF-Natural Calamity 2018-Urgent rectification to Vellanikkara branch canal 1/500to 1/650m 14.6
No. IDTsr/2019/ 3484/IA Dated: 9.5.2019
14.6 No. IDTsr/2019/ 3484/IA
Dated: 13.5.2019 14.6 24.05.2019 14.6
27/AEE/2019- 20 dtd
09/08/2019 12.95 C 14.51
51 SDRF-Natural Calamity 2018-Urgent rectification to Vellanikkara branch canal 0/500 to 0/700 Km 4
No. IDTsr/2019/ 3483/IA Dated: 9.5.2019
4 No. IDTsr/2019/ 3483/IA
Dated: 13.5.2019 4 18.05.2019 4
02/AEE/2019- 20 dtd
15/06/2019 3.23 C 3.52
52 SDRF-Natural Calamity 2018-Urgent rectification to Kozhukully branch canal 3/000 to 3/100 12.4
No. IDTsr/2019/ 3513/IA Dated: 9.5.2019
12.4 No. IDTsr/2019/ 3513/IA
Dated: 14.5.2019 12.4 10.06.2019 12.4
26/AEE/2019- 20 dtd
09/08/2019 11.03 C 12.35
53 SDRF- Natural Calamity- Peechi Scheme-Urgent rectification works of RBMC at Ch. 10/850 Km TO 10/950Km 8.1
No. IDTsr/2019/ 3478/IA Dated: 9.5.2019
8.1 No. IDTsr/2019/ 3478/IA
Dated: 13.5.2019 8.1 19.06.2019 8.1
24/AEE/2019- 20 dtd
05/08/2019 7.14 C 7.84
54 SDRF-Natural Calamity 2018-Urgent rectification to Pattikkad branch canal 1/150 to 1/300 7.7
No. IDTsr/2019/ 3482/IA Dated: 9.5.2019
7.7 No. IDTsr/2019/ 3482/IA
Dated: 13.5.2019 7.7 16.7.2019 7.7
25/AEE/2019- 20 dtd
05/08/2019 6.75 C 7.26
55 SDRF-Natural Calamity 2018-Urgent rectification to Kozhukully branch canal 4/100 to 4/600 10
No. IDTsr/2019/ 3514/IA Dated: 9.5.2019
10 No. IDTsr/2019/ 3514/IA
Dated: 14.5.2019 10 18.06.2019 10
23/AEE/2019- 20 dtd
05/08/2019 8.84 C 8.26
56 SDRF – Natural CalamityPSM –Urgent Rectification Works to RBMC between ch 16/200 to ch 16/250km 4.3
No. IDTsr/2019/ 3479/IA Dated: 9.5.2019
4.3 No. IDTsr/2019/ 3479/IA
Dated: 13.5.2019 4.3 30.5.2019 4.3
01/AEE/2019- 20 dtd
14/06/2019 3.77 C 4.14
57 SDRF – Natural CalamityPSM –Urgent Rectification Works to RBMC between ch 18/690 to ch 18/750km 9.2
No. IDTsr/2019/ 3480/IA Dated: 9.5.2019
9.2 No. IDTsr/2019/ 3480/IA
Dated: 18.5.2019 9.2 11.06.2019 9.2
18/AEE/2019- 20 dtd
27/07/2019 8.18 C 9.08
58 SDRF-Natural Calamity 2018-Urgent rectification to Kozhukully branch canal removal of slipped earth 5/400 to 6/500 3
No. IDTsr/2019/ 3517/IA Dated: 9.5.2019
3 No. IDTsr/2019/ 3517/IA
Dated: 14.5.2019 3 12.06.2019 3
10/AEE/2019- 20 dtd
08/07/2019 2.67 C 2.94
59 SDRF-Natural Calamity 2018-Urgent rectification to works- Mudikodu branch canal 3/300 to 3/400 9.7
No. IDTsr/2019/ 3515/IA Dated: 9.5.2019
9.7 No. IDTsr/2019/ 3515/IA
Dated: 13.5.2019 9.7 07.06.2019 9.7
05/AEE/2019- 20 dtd
02/07/2019 8.49 C 9.391
60 SDRF-Natural Calamity-Peechi Scheme--Deepening and removal of slipped earth of Mudikkode branch canal between ch 5/200 and 6/700 Km.
2.5 No. IDTsr/2019/ 3518/IA Dated: 9.5.2019
2.5 No. IDTsr/2019/ 3518/IA
Dated: 14.5.2019 2.5 12.06.2019 2.5
12/AEE/2019- 20 dtd
10/07/2019 2.23 C 1.77
61 SDRF Urgent rectification works to Kozhukully branch canal0/900 to 1/200 12
No. IDTsr/2019/ 3511/IA
Dated: 29.5.2019 12
No. IDTsr/2019/ 3511/IA Dated: 1.6.2019
12 05.07.2019 12 29/AEE/2019-
20 dtd 09/08/2019
9.96 C 11.03
62 SDRF Urgent rectification works to Kozhukully branch canal 3/ 200 to 3/500 5
No. IDTsr/2019/ 3512/IA
Dated: 29.5.2019 5
No. IDTsr/2019/ 3512/IA Dated: 1.6.2019
5 12.3.2020 5 2/AEE/2020-21 dt 19.5.2020 3.23 C 3.6
63 SDRF Urgent rectification works to Mudikode branch canal 1/450 to 1/800 11.9
No. IDTsr/2019/ 4762/IA
Dated: 29.5.2019 11.9
No. IDTsr/2019/ 4762/IA Dated: 1.6.2019
11.9 16.07.2019 11.9 41/AEE/2019-
20 dtd 21/10/2019
10.53 C 10.91
64 SDRF Urgent rectification works to Vellanikkara branch canal 2/900 to 3/200 12
No. IDTsr/2019/ 3520/IA
Dated: 29.5.2019 12
No. IDTsr/2019/ 3520/IA Dated: 1.6.2019
12 19.07.2019 12 36/AEE/2019-
20 dtd 16/08/2019
10.67 C 11.71
65 SDRF Urgent rectification works to Vellanikkara branch canal 1/100 to 1/200 8
No. IDTsr/2019/ 3519/IA
Dated: 28.5.2019 8
No. IDTsr/2019/ 3519/IA Dated: 1.6.2019
8 19.07.2019 8 37/AEE/2019-
20 dtd
16/08/2019 7.07 C 7.596
66 SDRF Urgent rectification works to Vazhakkumpara branch canal 3/000 to 3/100 4.8
No. IDTsr/2019/ 3509/IA
Dated: 28.5.2019 4.8
No. IDTsr/2019/ 3509/IA Dated: 1.6.2019
4.8 12.06.2019 4.8 11/AEE/2019-
20 dtd 10/07/2019
4.23 C 4.69
152
67 SDRF Urgent rectification works to Vazhukkumpara branch canal between ch.1/400 to 1/550 Km. 12
No. IDTsr/2019/ 5147/IA
Dated: 29.5.2019 12
No. IDTsr/2019/ 5147/IA
Dated: 31.5.2019 12 14.06.2019 12
09/AEE/2019- 20 dtd
05/07/2019 10.57 C 11.711
68 SDRF Urgent rectification works to Vazhukkumpara branch canal between ch.1/600 to 1/800 Km. 11.7
No. IDTsr/2019/ 3489/IA
Dated: 29.5.2019 11.7
No. IDTsr/2019/ 3489/IA Dated: 1.6.2019
11.7 19.07.2019 11.7 42/AEE/2019-
20 dtd 21/10/2019
10.42 C 11.496
69 SDRF Urgent rectification works to Vazhukkumpara branch canal between ch.2/300 to 2/500 Km. 14.4
No. IDTsr/2019/ 5149/IA
Dated: 29.5.2019 14.4
No. IDTsr/2019/ 5149/IA Dated: 1.6.2019
14.4 03.08.2019 14.4 44/AEE/2019-
20 dtd 21/10/2019
12.82 C 14.3
70 SDRF-Urgent rectification works to Mudikkode branch canal between ch.3/400 to 3/690 Km. 12.6
No. IDTsr/2019/ 4763/IA
Dated: 29.5.2019 12.6
No. IDTsr/2019/ 4763/IA Dated: 1.6.2019
12.6 3.8.2019 12.6 40/AEE/2019-
20 dtd 21/10/2019
11.2 C 10.42
71 SDRF-Urgent rectification works to Pattikkad branch canal between ch.3/ 500 to 3/700 Km. 12.8
No. IDTsr/2019/ 5145/IA
Dated: 29.5.2019 12.8
No. IDTsr/2019/ 5145/IA Dated: 1.6.2019
12.8 19.07.2019 12.8 35/AEE/2019-
20 dtd 16/08/2019
11.38 C 12.68
72 SDRF-Urgent Rectification works to RBMC between ch.27/250 Km to 27/350Km 14.65
No. IDTsr/2019/ 6986/IA Dated: 5.7.2019
14.65 No. IDTsr/2019/ 6986/IA Dated: 8.7.2019
14.65 08.07.2019 14.65 33/AEE/2019-
20 dtd 14/08/2019
12.78 C 14.28
73 SDRF-Urgent Rectification works to Left Bund of RBMC between Ch. 13/750Km to 13/850KM 4.9
No. IDTsr/2019/ 6987/IA
Dated: 29.5.2019 4.9
No. IDTsr/2019/ 6987/IA Dated: 1.6.2019
4.9 12.06.2019 4.9 13/AEE/2019-
20 dtd
12/07/2019 4.3 C 4.8
74 SDRF-Urgent Rectification works to RBMC between Ch.13/400Km to 13/500Km 14.7
No. IDTsr/2019/ 6988/IA Dated: 5.7.2019
14.7 No. IDTsr/2019/ 6988/IA Dated: 5.7.2019
14.7 22.07.2019 14.7 38/AEE/2019-
20 dtd
17/08/2019 11.63 C 13.03
75 SDRF-Urgent Rectification works to RBMC between Ch.13/550 Km to 13/650Km 13
No. IDTsr/2019/ 6989/IA Dated: 7.6.2019
13 No. IDTsr/2019/ 6989/IA
Dated: 10.6.2019 13 06.07.2019 13
30/AEE/2019- 20 dtd
09/08/2019 11.57 C 12.93
76 SDRF-Urgent Rectification works to RBMC between Ch.12/250Km to 12/350Km 12.7
No. IDTsr/2019/ 6993/IA
Dated: 29.5.2019 12.7
No. IDTsr/2019/ 6993/IA Dated: 1.6.2019
12.7 18.06.2019 12.7 21/AEE/2019-
20 dtd
05/08/2019 11.25 C 12.43
77 SDRF-Urgent Rectification works to RBMC between Ch.14/400Km to 14/500Km 11.7
No. IDTsr/2019/ 6994/IA
Dated: 31.5.2019 11.7
No. IDTsr/2019/ 6994/IA Dated: 1.6.2019
11.7 18.06.2019 11.7 20/AEE/2019-
20 dtd 05/08/2019
10.39 C 11.65
78 SDRF-Urgent Rectification works to RBMC between Ch.13/950Km to 14/050Km 11.5
No. IDTsr/2019/ 6997/IA
Dated: 29.5.2019 11.5
No. IDTsr/2019/ 6997/IA Dated: 1.6.2019
11.5 18.06.2019 10.11 19/AEE/2019-
20 dtd 05/08/2019
10.1 C 11.258
79 SDRF-Urgent Rectification works to RBMC between Ch.15/770Km to 15/820Km 13 13 13 18.6.2019 13
15/AEE/2019- 20 dtd
16/07/2019 11.5 C 12.58
80 SDRF-Urgent Rectification works to RBMC between Ch 34/400Km to 34/500Km 13.2
No. IDTsr/2019/ 6991/IA Dated: 5.7.2019
13.2 No. IDTsr/2019/ 6991/IA Dated: 8.7.2019
13.2 08.07.2019 13.2 32/AEE/2019-
20 dtd 14/08/2019
11.47 C 12.83
81 SDRF-Urgent Rectification works to Poovanchira Aqueduct at 12/000Km to 12/240 km. 13.3
No. IDTsr/2019/ 6998/IA Dated: 5.7.2019
13.3 No. IDTsr/2019/ 6998/IA
Dated: 19.10.2020 13.3 26.10.2020 13.3 OG
82 SDRF-Urgent Rectification works to Kozhukkully Branch canal between Ch.1/300Km to 1/360Km 4.6
No. IDTsr/2019/ 6992/IA Dated: 7.6.2019
4.6 No. IDTsr/2019/ 6992/IA
Dated: 10.6.2019 4.6 12.06.2019 4.6
16/AEE/2019- 20 dtd
16/07/2019 4.04 C 4.51
83 SDRF-Urgent rectification works to OBC between ch.3/800 to 4/000 Km. 6.46
No. IDTsr/2019/ 8121/IA
Dated: 26.9.2019 6.46
No. IDTsr/2019/ 8121/IA
Dated: 27.9.2019 6.46 18.01.2020 6.46
82/AEE/2019- 20 dtd
14.02.2020 5.74 C 6.429
84 SDRF – Natural Calamity-PSM -Urgent rectification works to Kozhukully branch canal 0/000 to 0/150 km 5
No. IDTsr/2019/8122/IA Dated: 26.9.2019
5 No.
IDTsr/2019/8122/I A Dated:
27.9.2019 5 16.10.2019 5
68/AEE/2019- 20 dtd
13.12.2019 4.45 C 4.98
153
85 SDRF-Urgent rectification works to Left Bund of RBMC between ch.15/400 to 15/500 Km. 15
No. IDTsr/2019/8124/IA Dated: 26.9.2019
15 No.
IDTsr/2019/8124/I A Dated:
08.9.2020 15 15 selection notice
issued 30-9-2020
86 SDRF-Urgent rectification works to RBMC between ch.12/460 to 12/500Km. 6.5
No. IDTsr/2019/8126/IA Dated: 14.8.2019
6.5 No.
IDTsr/2019/8126/I A Dated:
27.8.2019 6.5 4.11.2019 6.5
66/AEE/2019- 20 dtd
04.12.2019 5.74 C 6.39
87 SDRF – Natural CalamityPSM –Urgent Rectification Works of Kozhukully branch canal between ch 5/200 to ch 5/400km 20
No. IDTsr/2019/3516/IA
Dated: 9.5.2019 20
No. IDTsr/2019/3516/I A Dated:
28.5.2019 20 29.6.2019 20 38/EE/2020-21
dt 23.3.2020 16.69 Agreement Executed
88 SDRF-Urgent Rectification works to RBMC between Ch.27/100Km to 27/200Km 16.4
No. IDTsr/2019/6990/IA
Dated: 5.7.2019 16.4
No. IDTsr/2019/6990/I A Dated:
8.8.2019 16.4 16.10.2019 16.4 27/EE/2019-20
dtd 13.12.2019 C 13.79
89 SDRF-Urgent Rectification works to RBMC between Ch.15/600Km to 15/700Km 16.3
No. IDTsr/2019/6995/IA Dated: 29.5.2019
16.3 No.
IDTsr/2019/6995/I A Dated:
8.8.2019 16.3 15.10.2019 16.3 34/EE/2019-20
dtd 11.2.2020 C 13.49
90 SDRF-Urgent rectification works to the bund retaining wall side wall etc at ch:27/700 Km amd 27/900 Km of LBMC 24
No. IDTsr/2019/631/IA Dated: 9.5.2019
24 No.
IDTsr/2019/631/IA Dated: 13.8.2019
24 20.2.2020 24 Selection Notice issued
91 Natural Calamity 2018-SDRF - Urgent rectification works to Kozhukkully Branch Canal between Ch.3/100 to 3/150 Km and Ch 3/950 to 4/000 Km
7.6 2020/3089/IA dt 18.9.2020 7.6 2020/3089/IA dt
22.9.2020 7.6 29-9-2020 7.6 Selection Notice issued
31.12.2020
92 Natural Calamity 2018-SDRF - Urgent rectification works toLBMC at Ch.24/000 to 24/200 Km 9.9 9.9 9.9 OG
93 Urgent rectification works to LBMC abd bund protection wors at Ch 16/600 to 17/000 4.8 2020/3887/IA dt
6.9.2020 4.8 2020/3887/IA dt 7.9.2020 4.8 29-9-2020 4.8 28.10.2020 4.28 C 4.79 31.12.2020
94 Natural Calamity 2018-SDRF - Urgent rectification works to Mudicode Branch Canal between Ch.3/700 to 3/750 Km 5.3 2018/2854/IA
dt18.9.2020 5.3 2018/2854/IA dt 22.9.2020 5.3 29-9-2020 5.3 Retendered 31.12.2020
95 Natural Calamity 2018-SDRF - Urgent rectification works to Pattikkad Branch Canal between Ch.1/800 to 1/900 Km 11.7 2020/3093/IA dt
5.9.2020 11.7 2020/3093/IA dt 6.9.2020 11.7 29-9-2020 11.7 Agreement Executed 31.12.2020
96 Natural Calamity 2018-SDRF - Urgent rectification works to Mudicode Branch Canal between Ch.3/100 to 3/200 Km 3.7 2019/8119/IA dt.
23.9.2020 3.7 2019/8119/IA dt 25.9.2020 3.7 29-9-2020 3.7 Agreement Executed 31.12.2020
97 Natural Calamity 2018-SDRF - Urgent rectification works to OBC and repair of UT between Ch.1/950 to 2/050 Km 14.75 2020/3092/IA dt
23.9.2020 14.75 2020/3092/IA dt 25.9.2020 14.75 29-9-2020 14.75 Agreement Executed 31.12.2020
Total 1220.24 1056 797.69595 54
SDRF Works 2020-21 - Weekly Progress Report Under Hydrology Division Thrissur
H/A:-
Allocation of Rs 16.88 Lakhs
Sl. No. Head of Account/ Name of the Project Project Cost* (Rs Lakhs)
AS Accorded (Date of AS)
AS Amount* (Rs Lakhs)
TS Issued (Date of TS)
TS Amount* (Rs Lakhs)
Tendered (Date of Tender)
Tendered Amount*
(Rs lakhs)
Awarded (Date of Awarding
work)
Awarded Amount*
(Rs)
Work Status: Completed (C) or
Ongoing (OG) Expenditure* (Rs Lakhs) Expenditure % Target date of
completion
1 SDRF - Maintenance of Manali gauging station 0.53 28.05.2019 0.53 29.05.2019 0.53 09.09.2020 0.53 15.10.2020 0.45238 OG 22.12.2020
2 SDRF-Maintenanace of Kundukadu gauging station 0.56 28.05.2019 0.56 29.05.2019 0.56 09.09.2020 0.56 15.10.2020 0.47374 OG 22.12.2020
3 SDRF - Maintenance of Chittur gauging station 0.64 28.05.2019 0.64 29.05.2019 0.64 11-06-2019 0.64 02.3.2020 0.63678 C 0.63678 100 18.03.2020 4 SDRF - Maintenance of Thiruvegappura gauging station 0.66 28.05.2019 0.66 29.05.2019 0.66 09.09.2020 0.66 15.10.2020 0.5507 OG 22.12.2020
5 SDRF - Maintenance of Karikkadavu gauging station 0.41 28.05.2019 0.41 29.05.2019 0.41 11.06.2019 0.41 03.03.2020 0.31716 C 0.31716 100 09.03.2020 6 SDRF - Maintenance of Vettilappara gauging station 0.78 28.05.2019 0.78 29.05.2019 0.78 11.06.2019 0.78 01.02.2020 0.72722 C 0.72722 100 19.03.2020 7 SDRF - Maintenance of Office building of Hydrology section
Chalakkudy - Scheme I & II 2.35 28.05.2019 2.35 29.05.2019
2.35 15.06.2019
2.35 01.02.2020 2.11273 C 2.11273 100 23.11.2019
154
8 SDRF-Maintenance of Stations and office compound wall under Hydrology Section, Chalakudy
1.5 09.09.2020 1.5 14.09.2020 1.5
15.09.2020 1.5
08.10.2020 1.2744 C 1.2744 03.11.2020
9 SDRF-Repairs works for the steps at Karikkadavu river gauge station under Hydrology Section Chalakkudy
1.5 09.09.2020 1.5 15.09.2020 1.5
15.09.2020 1.5
08.10.2020 1.30917 C 1.30917 27.10.2020
10 Flood disaster - Repair works of Ambittan potty River gauge station
0.6 28.05.2019 0.6 28.05.2019 0.6 09.01.2020 0.6 09.03.2020 0.52672 OG 30.12.2020
11 Clearing the flow obstructing materials and silt deposits at Chittathpara, Karimpuzha, Punnapuzha and Kanjirapuzha
0.31 28.05.2019 0.31 28.05.2019 0.31 09.01.2020 0.31 09.03.2020 0.27546 OG 30.12.2020
12 SDRF-Urgent Maintenance (Civil) of Quarters building under Hydrology Sub Division office , Kozhikode
1.5 09.09.2020 1.5 10.09.2020 1.5 28.09.2020 1.5 15-10-2020 1.27229 OG 14.12.2020
13 SDRF-Urgent Maintenance of damaged Compound Wall on the East side of under Hydrology Sub Division office, Kozhikode
1.46 09.09.2020 1.48 10.09.2020 1.46 28.09.2020 1.46 15-10-2020 1.25011 OG 14.12.2020
14 SDRF-Urgent Maintenance of damaged Compound Wall on the North East and West side of Quarters building under Hydrology Sub Division , Kozhikode
1.48 09.09.2020 1.46 10.09.2020 1.46 28.09.2020 1.46 15-10-2020 1.25011 OG
14.12.2020
15 SDRF-Urgent Maintenance to the flood affected well, Pump House, and Ancillary structures, under Hydrology Sub Division premises, Kozhikode
1.4 14.09.2020 1.4 15.09.2020 1.4 28.09.2020 1.4 15-10-2020 1.2083 OG 14.12.2020
16 SDRF-Urgent Maintenance of flood affected Electrical works under Hydrology Sub Division, Kozhikode
1.2 24.09.2020 1.2 28.09.2020 1.2 28.09.2020 1.2 04-11-2020 1.0631 OG 30.12.2020
16.88 16.88 16.86 16.86 6.37746
SDRF Works 2020-21 - Weekly Progress Report Under Hydrology Division Chengannur
H/A:- Allocation of Rs ...........Lakhs
Sl. No. Head of Account/ Name of the Project Project Cost* (Rs Lakhs)
AS Accorded (Date of AS)
AS Amount* (Rs Lakhs)
TS Issued (Date of TS)
TS Amount* (Rs Lakhs)
Tendered (Date of Tender)
Tendered Amount*
(Rs lakhs)
Awarded (Date of Awarding
work)
Awarded Amount*
(Rs)
Work Status: Completed (C) or
Ongoing (OG) Expenditure* (Rs Lakhs) Expenditure % Target date of
completion
1 SDRF - Maintanance of gauging stations in Kottayam districtInstallation of velocity post, gauge post and gauge scales for hydrological stations Pala & Peroor under Hydrology Section,Kottayam
0.28788 04.06.2019 0.28788 16.05.2019 0.287 27.01.2020 0.25248 05.03.2020 0.25248 C 0.25
2 SDRF - Maintenance of Gauging Stations in Kottayam district - Supply and Installation of Gauge post, Velocity post and Staff gauge in various gauging stations (Mundakkayam, Manimala, Cheripad and Teekoy) under Hydrology Section Mundakkayam.
0.51364 08.03.2019 0.51 23.05.2019 0.51 27.01.2020 0.453 05.03.2020 0.453 C 0.453
3 SDRF-Maintanance of gauging stations in Ernakulam DistrictInstallation of velocity posts at Marthandavarma, Mangalapuzha and Kalady river gauge stations under Hydrology Section,Aluva
0.25 21.05.2019 0.2493 23.05.2019 0.2493 27.01.2020 0.22011 18.03.2020 0.22011 C 0.22
4 SDRF-Maintanance of gauging stations in Ernakulam Dist- Installation of gauge scale at Marthandavarma, Mangalapuzha and Kalady river gauge stations under Hydrology section Aluva
0.39583 21.05.2019 0.39583 23.05.2019 0.39583 27.01.2020 0.35168 18.03.2020 0.35168 C 0.35
5 SDRF Rectification of various station under Hydrology section No. I Chengannur ( River Gauge Station)
1.049 11.09.2020 1.049 11.09.2020 1.049 30.10.20 0.90093 31.03.2021
6 SDRF- Rectification of various station under Hydrolovy section no. II Chengannur ( River gauge station)
0.83 11.09.2020 0.83 11.09.2020 0.83 30.10.20 0.73729 31.03.2021
7 SDRF- Rectification of various station under Hydrolovy section Adoor ( River gauge station)
1.25 09.09.2020 1.25 11.09.2020 1.25 30.10.20 1.21906 31.03.2021
8 SDRF- Rectification of Tidal gauge station under Hydrolovy section Alappuzha.
1.37 10.09.2020 1.37 11.09.2020 1.37 30.10.20 1.07358 31.03.2021
9 SDRF- Rectification of various station under Hydrolovy section Vamanapuram
1.15 10.09.2020 1.15 14.09.2020 1.15 15.09.2020 1.02396 31.03.2021
7.09235 7.08801 7.08713 6.23209 1.27727 1.273