NON-ROUTINE TASK ANALYSIS Work Procedure

11
NON-ROUTINE TASK ANALYSIS Work Procedure: Northern System Purge Revision: Project Start Date & Time: July or August, 2016 Project Finish Date &Time: July or August, 2016 Page 1 of 11 Note: Any deviation from this NRTA requires Area Supervisor’s consent Date Prepared: May 18, 2016 Prepared by: Colin Turcotte AFE# MOC# Reviewed By Dept: Operations: Mechanical: Electrical: Eng: Dist Manager: ECC: SME: Pipe Diameter: 10Line Volume: 3407.9 m3 Station(s) in Local: Y Host Interlock Disable: N N2 Pad on line: Y Required Flow Rate: N/A Line Length: 62.53 km Product in line: Ethane Potential for 24 hr operation: Y Lockout/Tagout List: Y N2 Pumper Req: Y Pressure reading and logging: Y Min/Max Flow Rate:N/A MOP of line: 9930 kpa Any pressure restrictions: Y/N Active Pressure Restrictions P&ID Attached: N SCADA SCREEN SHOTS: N Shutdown Req: Y Outage Coordinator Notified: Y Separator Req: Y Amount to Flare: Stn. piping only. Min/Max Back Press:N/A Type of work Departments/Systems Affected Pembina Standards X If Applicable X Pipeline Purge NA Pipeline Fill NA Tool Run NA Station Piping work NA New Station/Site NA PLC upgrade/replacement NA VLV Replacements/Repair NA New Equipment Install NA Plant Startup NA Plant Shutdown NA Integrity Digs requiring cuts NA HDD NA Hot Tap NA Tank out of service NA Tank into service NA Changing Tank product NA Communications Work NA Confined Space Entry NA Inject Condensate NA X ECC Projects Notified X SES Notified NA Technical Services Review X Operations NA Electricians X Mechanical NA Pipeliners X Outage Required NA SCADA NA P&ID CHANGES NA Oil Accounting NA Programming Changes NA Engineering- Reviewed Press NA Quality Control NA Producers NA Receivers NA Pembina Regulatory-NEB R NA NA NA X 2.1.01Employee and Consultant Orientation X 2.1.02Contractor Orientation X 2.1.07- Job Hazard Analysis X 3.1.01- Hazard Identification, Assessment and Control X 3.1.02- Safe Work Permit X 3.1.03- Worksite Release NA 3.2.01- Asbestos Handling and Abatement X 3.2.03- Personal Protective Equipment X 3.2.04- Hearing Conservation and Noise Abatement X 3.2.05- Respiratory Protection NA 3.2.06- Hydrogen Sulphide X 3.2.07- Benzene X 3.2.08- WHMIS X 3.209- First Aid NA 3.2.10- NORMs X 3.2.11- Ergonomics X 3.3.01- Refusal of Unsafe Work NA 3.3.02- Working Alone NA 3.3.04- Working at Heights NA 3.3.06- Radiation Safety-Working with Radiation Devise or Nuclear Gauges X 3.3.07- Fatigue Management X 3.3.08- NSC-Hours of Service X 3.3.10 Safety Standby NA 3.3.11 Isolation from Energy Sources NA 3.3.12 Welding and Stress Relieving NA 3.3.13 Cleaning and Repairing Tanks NA 3.3.17 Hot Tapping NA 3.3.21 Electrical Arc Flash Safety NA 3.3.22 Area Classification for Electrical Equipment NA 3.3.23 Overhead Powerlines X 3.3.24 Static Electricity and Stray Currents X 3.3.26 Fire Fighting Equipment NA 3.3.27 Off Road Vehicles NA 3.3.28 Rigging, Hoisting and Critical Lifts NA 3.3.29 Ground Disturbance NA 3.3.30 Pipeline and Utility Crossings NA 3.3.31 Prevention and Removal of Hydrate Plugs NA 3.3.32 Helicopter Safety Legislation: NEB OPR

Transcript of NON-ROUTINE TASK ANALYSIS Work Procedure

NON-ROUTINE TASK ANALYSIS

Work Procedure: Northern System Purge Revision: Project Start Date & Time: July or August, 2016 Project Finish Date &Time: July or August, 2016

Page 1 of 11

Note: Any deviation from this NRTA requires Area Supervisor’s consent

Date Prepared: May 18, 2016 Prepared by: Colin Turcotte AFE# MOC# Reviewed By Dept: Operations: Mechanical: Electrical: Eng: Dist Manager: ECC: SME:

Pipe Diameter: 10” Line Volume: 3407.9 m3 Station(s) in Local: Y Host Interlock Disable: N N2 Pad on line: Y Required Flow Rate: N/A

Line Length: 62.53 km Product in line: Ethane Potential for 24 hr operation: Y Lockout/Tagout List: Y N2 Pumper Req: Y

Pressure reading and logging: Y

Min/Max Flow Rate:N/A

MOP of line: 9930 kpa Any pressure restrictions: Y/N

Active Pressure Restrictions

P&ID Attached: N

SCADA SCREEN SHOTS: N

Shutdown Req: Y

Outage Coordinator Notified: Y

Separator Req: Y

Amount to Flare: Stn. piping only.

Min/Max Back Press:N/A

Type of work Departments/Systems Affected Pembina Standards – X If Applicable

X Pipeline Purge

NA Pipeline Fill

NA Tool Run

NA Station Piping work

NA New Station/Site

NA PLC upgrade/replacement

NA VLV Replacements/Repair

NA New Equipment Install

NA Plant Startup

NA Plant Shutdown

NA Integrity Digs requiring cuts

NA HDD

NA Hot Tap

NA Tank out of service

NA Tank into service

NA Changing Tank product

NA Communications Work

NA Confined Space Entry

NA Inject Condensate

NA

X ECC Projects Notified

X SES Notified

NA Technical Services Review

X Operations

NA Electricians

X Mechanical

NA Pipeliners

X Outage Required

NA SCADA

NA P&ID CHANGES

NA Oil Accounting

NA Programming Changes

NA Engineering- Reviewed Press

NA Quality Control

NA Producers

NA Receivers

NA Pembina Regulatory-NEB R

NA

NA

NA

X 2.1.01– Employee and Consultant Orientation

X 2.1.02– Contractor Orientation

X 2.1.07- Job Hazard Analysis

X 3.1.01- Hazard Identification, Assessment and Control

X 3.1.02- Safe Work Permit

X 3.1.03- Worksite Release

NA 3.2.01- Asbestos Handling and Abatement

X 3.2.03- Personal Protective Equipment

X 3.2.04- Hearing Conservation and Noise Abatement

X 3.2.05- Respiratory Protection

NA 3.2.06- Hydrogen Sulphide

X 3.2.07- Benzene

X 3.2.08- WHMIS

X 3.209- First Aid

NA 3.2.10- NORMs

X 3.2.11- Ergonomics

X 3.3.01- Refusal of Unsafe Work

NA 3.3.02- Working Alone

NA 3.3.04- Working at Heights

NA 3.3.06- Radiation Safety-Working with Radiation Devise or Nuclear

Gauges

X 3.3.07- Fatigue Management

X 3.3.08- NSC-Hours of Service

X 3.3.10 – Safety Standby

NA 3.3.11 – Isolation from Energy Sources

NA 3.3.12 – Welding and Stress Relieving

NA 3.3.13 – Cleaning and Repairing Tanks

NA 3.3.17 – Hot Tapping

NA 3.3.21 – Electrical Arc Flash Safety

NA 3.3.22 – Area Classification for Electrical Equipment

NA 3.3.23 – Overhead Powerlines

X 3.3.24 – Static Electricity and Stray Currents

X 3.3.26 – Fire Fighting Equipment

NA 3.3.27 – Off Road Vehicles

NA 3.3.28 – Rigging, Hoisting and Critical Lifts

NA 3.3.29 – Ground Disturbance

NA 3.3.30 – Pipeline and Utility Crossings

NA 3.3.31 – Prevention and Removal of Hydrate Plugs

NA 3.3.32 – Helicopter Safety

Legislation: NEB OPR

NON-ROUTINE TASK ANALYSIS

Work Procedure: Northern System Purge Revision: Project Start Date & Time: July or August, 2016 Project Finish Date &Time: July or August, 2016

Page 2 of 11

Note: Any deviation from this NRTA requires Area Supervisor’s consent

Man Power Schedule -Use Template or Make your own Schedule and Attached to Email

NON-ROUTINE TASK ANALYSIS

Work Procedure: Northern System Purge Revision: Project Start Date & Time: July or August, 2016 Project Finish Date &Time: July or August, 2016

Page 3 of 11

Note: Any deviation from this NRTA requires Area Supervisor’s consent

PURPOSE: Use Nitrogen (N2) to purge from Taylor Station (7-36-82-18W6) to Bonanza Station (13-36-79-13W6); ~62.5 kms of 10” Pipeline. This is being done to facilitate the replacement of 1.5 kms of Pipeline between the Taylor Station and the Peace River valley.

SPECIFIC EQUIPMENT INVOLVED: Nitrogen Pumper, Nitrogen Bulkers, Temporary Piping, P-Tank, Flare Stack and Related Equipment, Locks, & Blinds.

POTENTIAL HAZARDS INVOLVED: Nitrogen asphyxiation, High pressure product, Noise, Flammable Product Release, Benzene, Pinch points, Extended work hours, Fatigue, Temporary piping, Slips, Trips and Falls

REQUIRED PERSONAL PROTECTIVE EQUIPMENT: Fire Retardant Coveralls, Side Impact Hard Hats, Safety Glasses, CSA Approved Steel Toe Boots, Four Head Monitor, Hearing Protection, SCBA/SABA , Communication Equipment, Brass Hammers, Wind Socks, Fire Extinguishers

REQUIRED EQUIPMENT ISOLATION: MOV-UV0215 at Taylor will be closed and Locked Out. The manual kicker valve (FN-1110) into the 10” trap at Taylor will be closed and Locked Out. Once the N2 purge is completed; both MOV-UV0214 and FN-1100 will be closed and locked out and a 10” 600# blind will be installed between these two valves. Once the Blowdown is completed, the two MOV Block valves at Bonanza Station (FN-1200 & FN-2100) will also be closed and locked out, with a 10” 600# blind installed between them.

OTHER COMMENTS SPECIAL TO THIS PROCEDURE: All Standards and SOP’s referred to in the NRTA are attached for reference.

NON-ROUTINE TASK ANALYSIS

Work Procedure: Northern System Purge Revision: Project Start Date & Time: July or August, 2016 Project Finish Date &Time: July or August, 2016

Page 4 of 11

Note: Any deviation from this NRTA requires Area Supervisor’s consent

Procedure

Work Procedure: Taylor to Bonanza Pipeline Purge 10” line

Distance: 62.5 km MLOP 9930 kpa

Line Fill 3407.9 m³

Date:

Reviewed:

Prepared by: Colin Turcotte

Overall Job Scope:

Legend: Black-Original Text RED-Important Information Green-Calgary Review Blue-Revision Text Purple- ECC Steps

Step # Job Steps Personnel Involved Equipment/Tool Potential Hazard(s) Control Initial When

Completed

Additional Comments/ Site name

1. 1.

Pre-job meeting & permitting Operations & Maintenance

P tank personnel

N2 Crew

All contractors involved in the job

Major projects rep

Standard 3.1.02 (Safe Work Permit),

Standard 3.1.02 (Hazard Identification)

Standard 3.3.07 (Fatigue Management)

Standard 3.3.08 (Hours of Service)

Good Communications is essential to completing this job safely and efficiently.

Lack of communication Inform every one of their roles and responsibilities as well as potential hazards and controls

Due to distance between site pre job will be held the day before the job takes place

2. 3.

Taylor station - Station needs to be shut down, isolated and locked out.

Pembina Ops Written lock out plan

Locks

Pressurized product Station will be properly isolated Notify SPCC prior to commencing work on-site.

Ensure cathodic is shut off

NON-ROUTINE TASK ANALYSIS

Work Procedure: Northern System Purge Revision: Project Start Date & Time: July or August, 2016 Project Finish Date &Time: July or August, 2016

Page 5 of 11

Note: Any deviation from this NRTA requires Area Supervisor’s consent

Procedure

Work Procedure: Taylor to Bonanza Pipeline Purge 10” line

Distance: 62.5 km MLOP 9930 kpa

Line Fill 3407.9 m³

Date:

Reviewed:

Prepared by: Colin Turcotte

Overall Job Scope:

Legend: Black-Original Text RED-Important Information Green-Calgary Review Blue-Revision Text Purple- ECC Steps

Step # Job Steps Personnel Involved Equipment/Tool Potential Hazard(s) Control Initial When

Completed

Additional Comments/ Site name

Standard 3.3.11 (Isolation from Energy Sources)

3. 4.

Close and Lock out MOV-UV0215 Pembina Ops Lock out Standard 3.3.11 (Isolation from Energy Sources)

Written Lock Out Plan

Locks

Pressurized product, Product release.

MOV-UV015 will be properly locked

Worker assigned to check on bleed

4. Prep & Load 10” tracking pig to be shipped.

Pembina Ops

10” poly pig, Tracking equipment

Standard 3.2.07 (Benzene)

SOP 40.04 (Pipeline Pigging)

Calibrated and Bumped personal monitor

Benzene Monitor

Pressure Gauge

Pressurized product, Product release. Benzenes, Flammable product

Working pressure gauge on trap

5. 7.

Rig in N2 Pumper to the 1” valve on top of the Pig launcher.

Pressure test temp. piping

N2 Crew, Pembina Ops N2 Pumper, temporary piping, hand tools, fire extinguishers Standard 3.3.15 (Purging, Venting and Inerting) 3.3.11

Leaks, Hazardous vapors, Tripping hazards, Oxygen deficient atmosphere.

Temporay piping must be tested and have a pressure rating higher than the relief setting on the N2 pumper.

Ensure a restricted area around pumper

. Pumpers and N2 equipment will have to be backed into the site. Use two (2) spotters at all times when moving equipment around station yard

NON-ROUTINE TASK ANALYSIS

Work Procedure: Northern System Purge Revision: Project Start Date & Time: July or August, 2016 Project Finish Date &Time: July or August, 2016

Page 6 of 11

Note: Any deviation from this NRTA requires Area Supervisor’s consent

Procedure

Work Procedure: Taylor to Bonanza Pipeline Purge 10” line

Distance: 62.5 km MLOP 9930 kpa

Line Fill 3407.9 m³

Date:

Reviewed:

Prepared by: Colin Turcotte

Overall Job Scope:

Legend: Black-Original Text RED-Important Information Green-Calgary Review Blue-Revision Text Purple- ECC Steps

Step # Job Steps Personnel Involved Equipment/Tool Potential Hazard(s) Control Initial When

Completed

Additional Comments/ Site name

(Isolation from Energy Sources)

Standard 3.3.28 (rigging, hoisting)

6. 8. Notify SPCC when starting purge.

SPCC will have an overage of 3407.9 m³.

Pembina Radio / Phone

7. 9.

Launch purge pig with N2 pumper.

Mop of the pipeline is 9930 kPa – at no time can any section of this pipeline exceed 9930 kPa.

N2 Crew, Pembina Ops, SPCC

N2 Pumper

Standard 3.3.15 (Purging, Venting and Inerting)

Standard 3.3.28 (rigging, hoisting)

SOP 40.04 (Pipeline Pigging)

Over pressure piping / pipeline, Leaks, Hazardous vapors, Tripping hazards, Oxygen deficient atmosphere.

Temporary piping must be tested and have a pressure rating higher than the relief setting on the N2 pumper

PSV on the Pipeline to protect it from over pressuring

SPCC can also monitor the pipeline pressure at various points. (Peace BV, Pouce BV, Bonanza stn)

Ensure good housekeeping and restricted areas

Notify SPCC before shipping the purge pig.

Pipeline Hydraulics to be considered due to the elevation changes from the Taylor station to the bottom of the Peace River Valley

8. 10.

N2 target injection rate is 270 Sm3/min

Pig speed at that injection rate should be ~4 km/hr

Pig must be tracked along the way to confirm its speed and arrival time.

N2 Crew, Pembina ops N2 Pumper, Tracker locator, geo phones.

Overspeed can allow product to bybass the pig. 2 Pigs?

Allow N2 to go past the Bonanza Station

Constant tracking of the purge pig. Proper communications with the crews at Taylor and Bonanza stations.

. Ensure Gordondale operators have emptied trap of all pigs before his job starts

Personnel must be ready at Bonanza station to stop the purge pig and ensure no N2 is allowed past that point

NON-ROUTINE TASK ANALYSIS

Work Procedure: Northern System Purge Revision: Project Start Date & Time: July or August, 2016 Project Finish Date &Time: July or August, 2016

Page 7 of 11

Note: Any deviation from this NRTA requires Area Supervisor’s consent

Procedure

Work Procedure: Taylor to Bonanza Pipeline Purge 10” line

Distance: 62.5 km MLOP 9930 kpa

Line Fill 3407.9 m³

Date:

Reviewed:

Prepared by: Colin Turcotte

Overall Job Scope:

Legend: Black-Original Text RED-Important Information Green-Calgary Review Blue-Revision Text Purple- ECC Steps

Step # Job Steps Personnel Involved Equipment/Tool Potential Hazard(s) Control Initial When

Completed

Additional Comments/ Site name

9. Bonanza Station - Pre-Job meeting and Hazard assessment. NRTA review

The N2 purge and blowdown will take between 25 – 35 consecutive hours, which will result in multiple shift and different personnel on-site.

Separate pre-job meeting will be held at both the Taylor and Bonanza sites, as the distance between the two is excessive. Proper communications between the two groups is absolutely essential.

Pembina Ops, P-Tank Crew Log book, daily journals, proper note taking

Standard 3.1.02 (Safe Work Permit),

Standard 3.1.02 (Hazard Identification)

Standard 3.3.07 (Fatigue Management)

Standard 3.3.08 (Hours of Service)

Good Communications is essential to completing this job safely and efficiently.

Long hours, Different personnel, improper shift hand over, bad communications

Inform every one of their roles and responsibilities as well as potential hazards and controls.

Hold a new safety meeting and handover meeting each shift.

10. 12 Rig in P tank and flare Pembina Ops, P-Tank Crew P Tank

Flare

Temporary piping

3.3.28 Rigging and Hoisting and Lifting3.3.11 (Isolation from Energy Sources)

Slips trips and falls

Live piping on site

Pinch points

Good housekeeping

and site awareness

Proper lockout

Use 2 spotters when moving equipment around station yard

13 Have Pembina Ops listening for the pig at the U/S Pouce Coupe BV. Once the pig goes by the U/S Pouce coupe BV, advise the Bonanza crew that the purge pig is 1.5 to 2hrs away.

Pembina Ops Tracker locator, Geo-phones

Standard 3.3.02 (Working Alone)

Driving,

Working alone

Wildlife

Wear seatbelt

Drive to conditions

Drive 10 km less than posted speed from dusk-dawn.

NON-ROUTINE TASK ANALYSIS

Work Procedure: Northern System Purge Revision: Project Start Date & Time: July or August, 2016 Project Finish Date &Time: July or August, 2016

Page 8 of 11

Note: Any deviation from this NRTA requires Area Supervisor’s consent

Procedure

Work Procedure: Taylor to Bonanza Pipeline Purge 10” line

Distance: 62.5 km MLOP 9930 kpa

Line Fill 3407.9 m³

Date:

Reviewed:

Prepared by: Colin Turcotte

Overall Job Scope:

Legend: Black-Original Text RED-Important Information Green-Calgary Review Blue-Revision Text Purple- ECC Steps

Step # Job Steps Personnel Involved Equipment/Tool Potential Hazard(s) Control Initial When

Completed

Additional Comments/ Site name

Continue tracking the pig along the pipeline into Bonanza Station – reporting back to both the Taylor and Bonanza crews on its location.

Watch for school zones and buses.

Drive with courtesy.

Bear spray

Air Horn

Use check in system

14 Once the anticipated arrival time is less than 1 hour away, the Taylor Crew should lower the N2 injection rate to slow down the pig speed.

The Bonanza crew can partially close the incoming (FN-1200) and discharge (FN-2100) valves to ensure the purge pig does not go past the Bonanza Station. No more than half way closed.

N2 Crew, Pembina Ops N2 Pumper, MOV’s, pressure gage

Too much restriction, over pressuring, possible hydrate

Continuous monitoring of the pressure is needed.

Personnel must be ready to close the Bonanza station discharge valve when the pig arrives.

15 When the purge pig arrives at Bonanza, the station discharge valve (FN-2100) must be closed and immediate notification to the Taylor crew to stop pumping N2, if job site supervisor has not already instructed the Taylor crew to stop pumping. Discharge valve FN-2100 can now be locked out.

Pembina Ops, N2 Crew MOV, N2 Pumper, locks

Standard 3.3.11 (Isolation from Energy Sources)

Over pressurize the pipeline PSV’s on both ends of the pipeline. Continuous monitoring of the pressure.

NON-ROUTINE TASK ANALYSIS

Work Procedure: Northern System Purge Revision: Project Start Date & Time: July or August, 2016 Project Finish Date &Time: July or August, 2016

Page 9 of 11

Note: Any deviation from this NRTA requires Area Supervisor’s consent

Procedure

Work Procedure: Taylor to Bonanza Pipeline Purge 10” line

Distance: 62.5 km MLOP 9930 kpa

Line Fill 3407.9 m³

Date:

Reviewed:

Prepared by: Colin Turcotte

Overall Job Scope:

Legend: Black-Original Text RED-Important Information Green-Calgary Review Blue-Revision Text Purple- ECC Steps

Step # Job Steps Personnel Involved Equipment/Tool Potential Hazard(s) Control Initial When

Completed

Additional Comments/ Site name

16 N2 Crew can now rig out and leave site. N2 Crew N2 pumper, associated piping and equipment

Standard 3.3.28 (rigging, hoisting)

Slips, Trips & Falls, Pinch points, driving around piping.

Use two (2) spotters when moving equipment around the station yard.

17 At Taylor, MOV – UV0214 and FN-110 can be closed and locked out. Bleed down to flare, until 0 pressure and then a 10” 600# blind is to be installed between these two valves.

Pembina Ops Hand Tools, locks, flange spreaders

Standard 3.3.11 (Isolation from Energy Sources)

Standard 3.1.02 (Hazard Identification)

Pinch points, Slips, Trips & Fall This can be done once the N2 pumping is completed.

18 Cautiously open up to the P-Tank and flare to de-pressure the pipeline of N2. Continue until there is zero pressure left on the Pipeline.

Pembina Ops, P-Tanks Crew.

P-Tank, Flare stack, Temp Piping.

IR Monitor

Standard 3.3.15 (Purging, Venting and Inerting)

Standard 3.3.28 (rigging, hoisting)

SOP 40.04 (Pipeline Pigging)

Over pressure piping / pipeline, Leaks, Hazardous vapors, Tripping hazards, Oxygen deficient atmosphere

Temporary piping between pipeline and P-Tank must be tested and have a pressure rating higher or equal to 600#.

Blowdown time could potentially be ~12hrs in length

NON-ROUTINE TASK ANALYSIS

Work Procedure: Northern System Purge Revision: Project Start Date & Time: July or August, 2016 Project Finish Date &Time: July or August, 2016

Page 10 of 11

Note: Any deviation from this NRTA requires Area Supervisor’s consent

Procedure

Work Procedure: Taylor to Bonanza Pipeline Purge 10” line

Distance: 62.5 km MLOP 9930 kpa

Line Fill 3407.9 m³

Date:

Reviewed:

Prepared by: Colin Turcotte

Overall Job Scope:

Legend: Black-Original Text RED-Important Information Green-Calgary Review Blue-Revision Text Purple- ECC Steps

Step # Job Steps Personnel Involved Equipment/Tool Potential Hazard(s) Control Initial When

Completed

Additional Comments/ Site name

19 Once zero pressure is achieved on the Pipeline, the Incoming valve at Bonanza (FN-1200) can be closed and locked out. A 10” 600# blind will be installed between FN-1200 and FN-2100.

The P-tank can be isolated, but remain tied in as it will be needed to return the line into service.

Pembina Ops

SPCC

Hand Tools, locks, flange spreaders

Standard 3.3.11 (Isolation from Energy Sources)

Standard 3.1.02 (Hazard Identification)

Pinch points, Slips, Trips & Falls

Fatigue

Working Pressure Gauge

Housekeeping

SPCC to confirm pressure reading

20 With the pipeline blinded at both ends, it can be turned over to Major projects to complete the tie in of the new section.

Pembina Ops, Major Projects rep.

Miscommunications WorkSite Release, LOTO log

Supplemental NRTA to be built to return the pipeline into service.

Insert Diagrams-SCADA Screen shot or attach P&ID to email (SCADA Screen shots can be sent to field personnel from ECC)

NON-ROUTINE TASK ANALYSIS

Work Procedure: Northern System Purge Revision: Project Start Date & Time: July or August, 2016 Project Finish Date &Time: July or August, 2016

Page 11 of 11

Note: Any deviation from this NRTA requires Area Supervisor’s consent