NLC India Limited (AG - Environmental Clearance

39
1 PRE FEASIBILITY REPORT FOR MINING CLAY AN ASSOCIATED PRODUCT AT BARSINGSAR LIGNITE MINE 1. INTRODUCTION: NLC India Limited (A Govt. of India Navratna enterprise) is operating the captive Barsingsar Lignite Mine of 2.10 MTPA (peak) near Barsingsar village, Bikaner District, Rajasthan for supplying lignite to the 2x125 MW Pit Head Thermal Power Plant at Barsingsar to fulfil part of power requirement of Rajasthan State for accelerating the economic development of the State. Mining Lease for an area of 971 ha was granted by Govt. of Rajasthan vide order No. P.17(55)/Khan/Group-1/2004 dated 2 nd March 2006. As per special clause No. 10 of the above order, “(a) In case any other mineral is found NLC would notify DMG/Rajasthan Government and use it after paying royalty”. Mining activity in Barsingsar lignite mine was commenced in August, 2006. The mine started producing lignite July, 2008. Overburden consists of Aeolian sand, kankar, Friable medium grained to coarse grained sandstone with bands of clay & marcasite and Variegated Clay. During overburden removal, economic bands of clay occurring within the overburden were found which are segregated towards conserving natural resources. However, Department of Mines and Geology, Govt. of Rajasthan had issued circular No. Kannank/Nide/P-2/Kas/Niyam/2017/393 dated 01.05.2018 stating that no special Permit/STP will be issued to transport the overburden until a clear guideline is issued by the MoEF. The matter was examined by MoEF. MoEF had communicated vide Office Memorandum No. Z- 11013/49/2018-IA.II(M) dated 18 th June, 2018 that “mining projects including dump mining, overburden mining etc. do require the prior Environmental Clearance as per the provisions of Environment Impact Assessment (EIA) Notification, 2006, the mining projects stated in the schedule require prior Environmental Clearance irrespective of the size of the mine lease area and type of mineral including overburden and dump mining”. In respect of this operating mine, EC was obtained by M/s Hindustan Vidyut Corporation Limited and it was transferred to NLC, vide Lr.no.J-15012/23/97-IA.II(M) dated 20 th Dec.,2002 as the ownership has changed. The Environmental impact assessment report prepared earlier considered lignite as the main product and did not consider the recovery of clay which occurs sporadically and is interspersed in the overburden. Now it is proposed to include the clay as an associated product/mineral with lignite, for which an amendment in EC is required incorporating the recovery of clay from overburden. In this regard, a pre

Transcript of NLC India Limited (AG - Environmental Clearance

1

PRE FEASIBILITY REPORT FOR MINING CLAY AN ASSOCIATED PRODUCT

AT BARSINGSAR LIGNITE MINE

1. INTRODUCTION:

NLC India Limited (A Govt. of India Navratna enterprise) is operating the captive

Barsingsar Lignite Mine of 2.10 MTPA (peak) near Barsingsar village, Bikaner District,

Rajasthan for supplying lignite to the 2x125 MW Pit Head Thermal Power Plant at Barsingsar

to fulfil part of power requirement of Rajasthan State for accelerating the economic development of

the State. Mining Lease for an area of 971 ha was granted by Govt. of Rajasthan vide order No.

P.17(55)/Khan/Group-1/2004 dated 2nd

March 2006. As per special clause No. 10 of the above

order, “(a) In case any other mineral is found NLC would notify DMG/Rajasthan Government and

use it after paying royalty”.

Mining activity in Barsingsar lignite mine was commenced in August, 2006. The mine started

producing lignite July, 2008. Overburden consists of Aeolian sand, kankar, Friable medium grained

to coarse grained sandstone with bands of clay & marcasite and Variegated Clay. During

overburden removal, economic bands of clay occurring within the overburden were found which

are segregated towards conserving natural resources.

However, Department of Mines and Geology, Govt. of Rajasthan had issued circular No.

Kannank/Nide/P-2/Kas/Niyam/2017/393 dated 01.05.2018 stating that no special Permit/STP will

be issued to transport the overburden until a clear guideline is issued by the MoEF. The matter

was examined by MoEF. MoEF had communicated vide Office Memorandum No. Z-

11013/49/2018-IA.II(M) dated 18th June, 2018 that “mining projects including dump mining,

overburden mining etc. do require the prior Environmental Clearance as per the provisions of

Environment Impact Assessment (EIA) Notification, 2006, the mining projects stated in the schedule

require prior Environmental Clearance irrespective of the size of the mine lease area and type of

mineral including overburden and dump mining”.

In respect of this operating mine, EC was obtained by M/s Hindustan Vidyut Corporation

Limited and it was transferred to NLC, vide Lr.no.J-15012/23/97-IA.II(M) dated 20th

Dec.,2002 as the ownership has changed. The Environmental impact assessment report

prepared earlier considered lignite as the main product and did not consider the recovery of

clay which occurs sporadically and is interspersed in the overburden. Now it is proposed to

include the clay as an associated product/mineral with lignite, for which an amendment in

EC is required incorporating the recovery of clay from overburden. In this regard, a pre

2

feasibility report and Form-I has been prepared for submitting an application to MoEF&CC

for the issue of amendment to EC.

2. DETAILS ABOUT THE MINE:

The Barsingsar lignite mine is situated 25 Kms, south-west of Bikaner. The nearest railway

station is Palana (7 Kms. away) on Bikaner-Jodhpur broad gauge section of North western

Railway. Mine project site is well connected with Jaipur by road and rail.

Barsingsar mine area lies in the Thar Desert with the area having a typical undulating

topology, underlain by a thick cover of aeolian sand and sand dunes. The maximum and

minimum elevations are 288 meter and 262 meter above sea level.

The climate of the area is typical of dry and arid regions having wide variation in

temperature between day and night. Maximum temperature goes up to 48o C and minimum

to 2o C. The average annual rainfall is around 330 mm during the period 2011 - 2016.

SALIENT DETAILS OF THE MINE PROJECT:

Name of Mine Barsingsar Lignite Mine (Open cast)

Mining Lease area 971 ha.

Location of Mine Barsingsar, Bikaner Dt., Rajasthan

Topo sheet No. 45 E/1

Production capacity of Lignite Mine 2.10 MTPA (Peak)

Production capacity of clay (Proposed) 0.424 Lakh tonnes (Peak)

Method of Mining Opencast

Drilling/blasting Not envisaged

No. of working days 330

Source of Water Indira Gandhi Nagar Project (IGNP)

Man Power Working lignite mine with sufficient man

power. No separate man power is required

for excavating clay mineral.

Nearest Airport Nal Airport near Bikaner at about 25 km

3

3. NEED FOR THE PROPOSAL AND ITS IMPORTANCE:

Lignite is the main product of Barsingsar lignite mine and for which approved mine plan is

available. During the progress of mining, bands of marketable/economic clay interspersed

in the overburden was noticed and was segregated and stacked separately for sale. Clay is

mainly used as raw material in ceramic industry. The sale of clay will bring good return to

state as well as central government in the form of royalty and taxes. This proposal is very

much essential in the perspective of conservation of valuable mineral namely clay,

otherwise it would go as waste to the dump yard.

4. LAND USE:

Total required land has already been acquired and is in the possession of NILCIL. Land

requirement for the mining project is 786 Ha. Total land including the apportioned acquired

land is 2343 ha as per approved mining plan. Head-wise requirement of land is given in

Table below:

Sl.No. Particulars Land

Requirements (in Ha)

1. Mining 526

2. Mine Periphery including haul roads,

power supply arrangements

50

3. External dumps 175

4. Repair facilities etc. 15

5. Township, approach road etc 20

6. Others (apportioned of acquired land) 1557

Total 2343

There is no additional land required in this process. The mine lease area remains the same

5. DEMAND AND SUPPLY GAP:

There is good market for clay particularly in ceramic industry. Clay is an incidental and

associate material in overburden, which occurs sporadically as lenses. It is proposed to

segregate the economic and marketable clay and stock separately for selling.

6. IMPORTS Vs INDIGENOUS PRODUCTION:

4

No import of this quality clay at present.

7. EXPORT POSSIBILITY:

No export of this quality clay at present.

8. DOMESTIC/EXPORT MARKET:

The applicant after obtaining the clearance will sell the clay to the potential buyers.

9. EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE

PROJECT:

As the clay is an associate material in the overburden, no additional man power

requirement is envisaged for removal of clay. Presently, 64 persons are directly employed

by NLCIL and another 268 are directly employed by the outsourcing contractors. About

100 persons are indirectly employed through various services in mines. However, indirect

employment opportunities through transport logistics, trading and utilization of clay are

envisaged which will raise the income levels and standard of living in the area.

10. PROJECT DESCRIPTION:

10.1 Type of project including interlinked and interdependent project, if any:

Barsingsar Lignite mine is a working mine, which feeds lignite to the Pit Head Barsingsar

TPS. Lignite is covered with a thick pile of overburden consists of Aeolian sand, kanker,

friable sandstone/sand with intervening clay bands followed by different forms of clay

varying from variegated to dull white and grey clay. Economic Clay occurs within the thick

clay horizon of overburden of Barsingsar Lignite mine. It is proposed to

segregate/selectively mine the economic and marketable clay whenever encountered.

10.2 Location of the Project site with coordinates:

Mining lease area is located in Barsingsar village, Bikaner district, Rajasthan. The entire

land required for the lignite mine project is already acquired. The ML area falls in Survey

of India topo sheet No. 45 E/1 and lies within longitude 73°11’20” – 73°11’58” and

latitude 27°48’59” - 27°51’02”. The location map of Barsingsar mine is given below:

5

10.3 Details of alternate sites considered and the basis of selecting the proposed site,

particularly the environmental consideration gone into should be highlighted:

Excavation of Clay is part of overburden removal for winning lignite at a specific location.

Therefore no alternate sites were examined.

10.4 Size or magnitude of operation:

Excavation of clay will be carried out within the lease hold area of 971 ha already obtained

for mining lignite. Peak rated capacity of Barsingsar mine is 2.10 MTPA. Overburden

removal is carried out by forming multiple benches with separate Haul Roads. The bench

parameters are maintained as per the permission granted by the DGMS. In overburden,

height of aeolian sand bench is maintained at not more than 3 metres and width is

maintained at 6m. The height of Kankar , sandstone, clay and lignite benches is maintained

at not more than 6 metres and width of the benches is maintained at not less than 11 metres.

Total number of benches varies from 12 to 20 depending upon the depth of mine. The

overall pit slope is being maintained at 260. In the main pit, 105.6 ha of area will be worked

out for the balance life of mine to produce about 8.48 lakh tones of clay.

6

11. GEOLOGY:

11.1 Regional Geology:

The Aravali range, traversing diagonally through the middle of Rajasthan in a NE-SW

trend, forms the eastern barrier of the Western Rajasthan. Geologically, this part of

Rajasthan, west of the Aravali range formed an extensive basinal set-up, from the

Cambrian till the Tertiary period, forming the Southerly and South-easterly continuation of

the Indus Basin. The area is now under a cover of alluvial and desert sand.

Several sedimentary basins have been identified in the western Rajasthan bounded between

the Aravali and the Delhi Super Group of rocks as the eastern most boundary and the

Malani Igneous suit as the southern boundary (Pareek H.S. 1981). They are:-

i. Marwar Basin (Cambrian)

ii. Bap – Badhura Remnant (Permian)

iii. Lathi – Basin (Lower Jurassic)

iv. Jaisalmer – Basin (Mesozoic and Tertiary)

v. Palana – Ganganagar shelf (Tertiary), and

vi. Barmer – Basin (Cretaceous – Tertiary)

11.2 Geology of the Area:

The whole of Barsingsar area is covered by Aeolian sand and has an undulating topography

with maximum and minimum altitudes of 288m RL and 262m RL respectively. It is

observed that the general slope of the region is towards northwest to west. As no exposure

of rocks except Aeolian sand has been observed in the area, interpretation of geological

features are made exclusively with the help of exploratory borehole data.

The generalized stratigraphic sequence of the geological block is given below:

7

Period Formation Litho Units Thickness(m)

Recent to Sub-

recent

Eocene

Aeolian sand and

Kankar

Aeolian sand Kankar 1.50 to 6.50

0.00 to 20.50

Palana Formation Friable medium

grained to coarse

grained sandstone with

bands of clay &

marcasite

6.10 to 120.80

Variegated Clay 0.00 to 63.20

Lignite, intercalation

and carbonaceous clay

0.00 to 61.60

Clayey silt 0.70 to 57.00

Fine grained sandstone (Continuing

towards bottom)

Structurally the area is very simple and is devoid of any fault. The formations have a gentle

rolling dip due to uneven floor of deposition. The lignite horizon as well as the other litho

units characteristically shows pinching and swelling nature. The dip of formations varies

from 2o to 6

o generally.

The economically marketable clay bands are occurring within the variegated clay.

11.3 RESERVES:

As already mentioned, marketable clay occur as thin lensoidal body within the variegated

clay formation. The exploratory boreholes are 200 m apart and the marketable clay bands

do not show lateral continuity due to pinching and swelling character. Hence, reserve

estimation of marketable clay has been made based on the experience gained over the

period of time. Based on the past experience, the average thickness of clay is estimated at

0.44 m in the main pit area. The estimated extractable clay reserves in the balance area of

the main pit are estimated and are given below and the sectors are shown in the surface

plan enclosed as Annexure-I:

8

S.No SECTOR Area (ha) Average thick.

of clay (m)

Density of clay Reserve

(Lakh ton)

1 I 41.8611 0.44 1.825 3.361

2 II 33.4931 0.44 1.825 2.690

3 III 30.2400 0.44 1.825 2.428

Total 105.5942 0.44 1.825 8.479

11.4 SELECTION OF MINE BOUNDARY:

The demarcated mine boundary is as per the mining plan approved by Ministry of coal vide

approval dated 8th

September, 2004. A mining lease deed was executed with Govt of

Rajasthan on 30.08.2006 valid for 30 years for mining lignite.

Proposed rate of production and expected life of mine:

The extractable clay reserve in the balance main pit area is estimated at 8.479 lakh tonnes.

Balance life of mine is 20 years at peak rated capacity of 2.10 MTPA of lignite. However,

life of mine will vary depending upon annual lignite production. Average clay production is

anticipated at 0.424 lakh tonnes per annum for rated capacity of 2.10 million tonnes of

lignite production. However, depending upon the development and spatial distribution of

marketable clay bands and annual lignite production, annual production of marketable clay

may vary. This proposal of excavation of marketable clay is for the life mine i.e. till the end

of lignite production.

11.5 PROJECT DESCRIPTION WITH PROCESS DETAILS (A SCHMATIC

DIAGRAM/FLOW CHART SHOWING THE PROJECT LAYOUT,

COMPONENTS OF THE PROJECT ETC. SHOULD BE GIVEN).

a. Method of Mining:

CME Technology is adopted for exploitation of Lignite and Overburden removal.

Overburden workings are having multiple benches with separate Haul Roads and Dump

Yards respectively. For overburden benches, Shovels/Backhoe of 3.5 Cum. bucket

Capacity and Rear Dumpers of Capacity 35 T / 16 Cum are deployed with motor grader,

Dozer, Rock Breaker, Pay Loader as ancillary equipments. Similarly for Lignite production

also similar Shovels/Backhoe with Rear Dumpers is deployed with Dozer & Motor Grader

as ancillary equipments.

9

Marketable clay co-exists in variegated clay as thin lenses are excavated by deploying

small capacity shovel in combination with motor grader/dozer. Excavated clay is

transported to the clay stock yard by deploying Dumpers of suitable capacity. Surface plan

showing mine pit, TPS and other infrastructure facilities is attached as Annexure-I.

b. Method of Working:

Marketable clay co-exists with variegated clay. Hence, the same method of working

adopted for removal of overburden is adopted for removal of marketable clay. By

deploying small capacity shovel, selective mining in combination with motor grader/dozer

are carried out. When the Marketable clay band is thin, the same is exploited by deploying

motor grader/dozer to make heaps and then loaded into dumpers and transported to the clay

stock yard. No drilling and blasting is carried out both in overburden and in lignite.

c. Mining Machinery required:

Some of the Mining Machineries deployed for excavation of overburden and small size

shovels are deployed on need basis for excavating marketable clay. Mining Machineries

deployed for clay excavation is given below:

S.No Name of equipment Population

1 Shovel 1.0 m3 Drawn from Overburden

equipment on need basis 2 Motor Grader/Dozer

3 Dumpers 35T

Year wise reserve calculation:

The extractable marketable clay reserve in the balance main pit area is estimated at 8.479

lakh tonnes. Balance life of mine is 20 years at peak rated capacity of 2.10 MTAP of

lignite. Year wise production schedule for marketable clay is tentatively calculated and

furnished below for the mine movement to produce lignite at peak rated capacity of 2.1

MTPA:

10

Year of production Extractable clay (Lakh tones)

1 0.424

2 0.424

3 0.424

4 0.424

5 0.424

6 0.424

7 0.424

8 0.424

9 0.424

10 0.424

11 0.424

12 0.424

13 0.424

14 0.424

15 0.424

16 0.424

17 0.424

18 0.424

19 0.424

20 0.424

Total 8.479

However, depending upon the development and spatial distribution of marketable clay

bands and annual lignite production, annual production of marketable clay and life of mine

may vary. Chemical analysis report of marketable clay enclosed as Annexure-II

11.6 RAW MATERIAL ALONG WITH ESTIMATED QUANTITY, LIKELY SOURCE

OF MARKETING AREA OF FINAL PRODUCTS, MODE OF TRANSPORT OF

RAW MATERIAL AND FINISHED PRODUCT:

No raw material for production of clay is envisaged except the diesel required for operating

the mining machineries.

11.7 RESOURCE OPTIMIZATION/RECYCLING AND REUSE ENVISAGED IN THE

PROJECT, IF ANY SHOULD BE BRIEFLY OUTLINED:

The clay which is a valuable raw material is conserved for beneficial industrial use instead

of dumping as a waste material.

11.8 AVAILABILITY OF WATER ITS SOURCE, ENERGY/POWER REQUIREMENT

AND SOURCE SHOULD BE GIVEN:

11

Water required for the Barsingsar Thermal and Mine project and allied activities is drawn

through an underground pipe line from Indira Gandhi Nagar Project (IGNP) at a distance of

about 62 km. The water is stored in a reservoir located within the Thermal complex and

transported through pipe lines to different destinations for use. As far as Barsingsar Mine is

concerned, water is mainly required for dust suppression in mines, watering of plants and

usage in colony and office premises.

Required power for Barsingsar Mine is drawn from pit head Barsingsar TPS. All the

mining machineries are diesel driven. Power is mainly required for lighting in mines, haul

roads, colony and office premises.

11.9 QUANTITY OF WASTE TO BE GENERATED (AIR, LIQUID AND SOLID) AND

SCHEME FOR THEIR MANAGEMENT/DISPOSAL:

Waste water:

Waste water from wash down bay in the workshop is passed through a grit and oil separator

and then into setting pond. Storm water is collected in the pit sump, before pumping it out

from the mine after settlement of solids. Clear pumped out water is used for watering

plants. The quality of effluents is being monitored from time to time. Run off from virgin

areas from the OC mine is diverted around the working areas. Effluents from the colony are

treated in the Effluent Treatment Plant (ETP).

Solid waste:

Solid waste from the mine is in the form of overburden removed for exploitation of lignite.

The Overburden removed till the development of mines was taken to dump yard and

dumped in benches at outside the Mine Pit. Outside dump was formed in 15 m bench

height with minimum 30m bench width restricting to 45 metres overall height. Internal

dumping in the de coaled area has already been started.

Reclamation of dumps:

The entire overburden is now back filled in the de coaled area and greeneries are raised.

Location of plantation, number of saplings planted, and plants survived (Live plants) and

the area covered is given in Annexure-III. As on year ending March,2019, about 56.7

thousand saplings have been planted, out of which 31.8 thousand plants have survived.

12

Some photographs showing the plantation at few localities of the project area are given

below:

Panoramic view of Barsingsar Township

Avenue Plantation

13

Plantation around Mine site office

Lush Green plantation in Township

14

11.10 Pollution Control measures:

Lignite mining and associated activities generate dust, water and noise pollution and other

associated environmental hazards.

a. Air Pollution Control measures:

The following measures are adopted to control air pollution:

Haul road dust suppression/watering are being done to maintain the required

moisture level in all active haul roads. Education of the workforce is done to ensure

that water truck operators are aware of the consequences of excess watering

including surface deterioration and erosion. A fleet of water trucks with adequate

water spray systems are available and operational at all times.

Partial enclosures of conveyor belts.

Provision of mechanical dust extraction and dust suppression systems at all major

dust generating points like Lignite Handling Plant etc.

In order to minimize dust generation, OB dump areas are isolated and re-vegetated

Plantation near infrastructure areas, avenue plantation and plantation in vacant areas

have been done and maintained so that the adverse impacts on ambient air and noise

become insignificant.

The following operation strategies and methods adopted to further compliment the

above.

i. Clearing in advance of mining operations is kept to a minimum with natural

grass being belt intact. Aeolian sand is removed only in the immediate areas of

mining operations. Aeolian sand stock piles have been stabilized by grassing.

ii. Both internal as well as external OB dumps are reclaimed and grassed/covered

by plantation as soon as practicable.

b. Noise Pollution Control:

i. Main overburden comprises of clay and sandstone, which are friable in nature and

the entire overburden, Parting, lignite offers free-digging without the use of

explosives. Hence, there is no blasting related noise pollution at Barsingsar Mine.

15

ii. The prevailing wind direction, undulating terrain and waste dumps tend to act as

attenuation obstacles to mining related noise.

iii. The external dumps are provided with suitable vegetation screening, and it provides

an effective noise, dust and aesthetic barrier.

iv. All machinery, vehicles and equipment used in the mine are fitted with appropriate

noise controls that are maintained regularly and serviced to the manufacturer’s

specifications.

The following control measures are practiced:

a. Development of additional green barrier around noise generating centers

b. Preventive maintenance of machinery.

c. Use of ear-muffs by operators exposed to noise level beyond permitted TLVs of

90 dB(A).

11.10 SCHEMATIC REPRESENTATION OF THE EC AMENDMENT PROCESS:

12. SITE ANALYSIS:

12.1 Connectivity:

Form – I

Along with Pre-Feasibility Report for Clay &

Approved Mining Plan for Lignite with

Annexure

To submit EAC

Presentation to EAC

Recommendation of EAC

Issue of Amendment to EC by MOEF&CC

16

The area is approachable by well developed road and rail network. Barsingsar is at 30 km

southwest of Bikaner, the district headquarter and is well connected with state capital

Jaipur by road and rail. The nearest railhead is at Palana at 7 km away on Bikaner –

Jodhpur broad gauge section of Northern Railway.

12.2 Land use and land ownership:

The entire land required for the project is mostly tenancy land except a small portion of

government land, which is already acquired/ transferred and is in the possession of NLCIL.

12.3 Topography:

The whole of Barsingsar mine area is covered by Aeolian sand and has an undulating

topography with maximum and minimum altitudes of 288m RL and 262m RL respectively.

The thickness of Aeolian sand varies from 1.50m to 6.50m. The general slope of the region

is towards northwest to west. The area is generally devoid of much vegetation, only thorny

shrubs and trees are found in scattered form.

12.4 Existing land use pattern (agriculture, non-agriculture, forest, water bodies

(including area under CRZ), shortest distances from the periphery of the project to

periphery of the forest, national park, wild life sanctuary, eco sensitive areas, water

bodies (distance from the HFL of the river), CRZ. In case of notified industrial area, a

copy of the Gazette notification should be given.

The mine project area is categorized as mostly tenancy land and some government land,

which has already been acquired. No forest land is diverted for the mine project The

environmental setting of the project site is given in the table below:

S.No Description Details

1 Site location Barsingsar village, Bikaner district, Rajasthan.

SOI topo sheet No. 45 E/1 Longitude 73°11’20”

– 73°11’58” and latitude 27°48’59” - 27°51’02

2 Topography Undulating, covered by Aeolian sand

3 National park Nil within 10 km radius

4 Biosphere reserve Nil within 10 km radius

5 Sanctuary Nil within 10 km radius

6 Habitat for migratory

birds

Nil within 10 km radius

17

7 Archeological site Nil within 10 km radius

8 Eco sensitive areas Nil within 10 km radius

9 Water bodies Devoid of any perennial streams, rivers and

nallahs within 10 km radius

10 Seismicity Does not fall in active zone

12.5 Existing Infrastructure:

Barsingsar lignite mine is a working mine, where all infrastructures like office building,

statutory buildings, colony, roads, water supply, power supply etc are in place.

12.6 Soil classification:

Mine area is covered by Aeolian sand varying in thickness from 1.50m to 6.50m.

12.7 Climate data from secondary source:

Mine area lies in an arid region where the climate is characterized by extreme variations in

temperature. The monthly maximum and minimum temperature, average rainfall, average

pressure and relative humidity for Bikaner (data source: worldweatheronline.com) for the

period 2011 to 2016 is presented in the following table:

Temperature:

Month Max/Min 2011 2012 2013 2014 2015 2016

January Max 21 20 20 20 21 23

Min 9 11 11 11 12 13

February Max 25 22 23 23 26 26

Min 13 12 15 14 16 16

March

Max 33 31 30 29 30 31

Min 18 19 21 20 21 23

April Max 37 36 35 36 37 37

Min 21 25 26 26 27 26

May Max 41 41 41 39 41 41

Min 29 30 30 30 31 31

June Max 41 41 41 42 40 42

Min 32 31 33 32 32 33

July Max 39 40 39 39 37 39

Min 32 32 33 32 31 32

August Max 35 36 36 37 36 36

Min 30 30 30 31 30 31

September Max 34 35 37 36 37 37

18

Min 28 29 30 29 29 29

October Max 33 33 34 34 35 35

Min 24 25 27 25 26 26

November Max 29 27 27 28 29 30

Min 20 18 19 18 20 19

December Max 23 22 23 22 23 26

Min 13 13 14 13 14 15

Average Pressure (mb):

Month 2011 2012 2013 2014 2015 2016

January 1016.2 1016.5 1017.6 1018.5 1018.5 1017.0

February 1013.7 1014.9 1015.2 1013.7 1014.9 1016.3

March 1010.4 1010.9 1012.2 1013.2 1012.7 1012.5

April 1008.3 1006.8 1007.3 1009.0 1006.9 1007.2

May 1001.9 1003.1 1001.7 1004.4 1003.9 1002.4

June 996.7 998.0 997.6 998.6 1000.1 1000.0

July 998.0 996.7 997.1 998.5 998.8 998.0

August 999.4 1000.3 1000.9 1001.6 1002.6 1001.1

September 1003.3 1004.7 1004.5 1005.0 1006.2 1005.2

October 1010.9 1011.6 1009.7 1012.0 1012.3 1009.7

November 1014.0 1014.1 1015.5 1014.7 1015.3 1015.0

December 1015.9 1015.8 1016.1 1017.5 1017.7 1016.3

Average 1007.4 1007.8 1008.0 1008.9 1009.2 1008.4

Average Humidity (%):

Month 2011 2012 2013 2014 2015 2016

January 29 33 28 36 39 34

February 39 26 39 31 31 23

March 21 20 24 25 29 28

April 19 21 20 19 21 16

May 25 17 15 23 17 23

June 31 32 31 30 29 29

July 40 38 42 38 47 43

August 55 49 50 44 48 48

September 55 43 38 45 33 35

October 26 23 32 24 24 28

November 30 25 28 25 25 20

December 26 31 33 28 25 26

Rainfall:

19

The table given below, shows annual average rainfall statistics of Bikaner District. Bikaner

received the highest rainfall distribution of 172.4 mm in August, 2012 during the period

2011 to 2016.

Yearly/Monthly rainfall data (mm)

2011 2012 2013 2014 2015 2016

January 0.0 0.6 5.8 0.00 0.20 0.0

February 15.3 0.0 37.5 0.70 2.80 2.5

March 3.8 0.0 7.4 3.80 60.50 14.9

April 0.8 5.3 7.3 9.90 43.30 2.0

May 14.5 33.1 0.2 34.90 37.70 0.6

June 13.1 4.3 22.4 27.20 44.00 44.5

July 93.6 22.3 98.2 78.20 162.00 69.7

August 113.8 172.4 113.2 50.50 93.90 143.6

September 97.3 72.5 6.8 66.70 33.90 7.6

October 0.0 3.5 4.4 0.00 1.90 8.8

November 0.0 0.0 0.4 0.00 0.00 0.0

December 0.0 6.2 0.0 0.00 0.00 0.0

Average 29.4 26.7 25.3 22.7 40.0 24.5

PLANNING BRIEF:

13.1 Planning concept (type of industries, facilities, transportation etc) Town and country

planning/Development authority classification:

Open cast mechanized mining facility available for excavation of overburden will be

utilized whenever marketable clay is encountered. Good network of road is available for

transporting clay to the desired destinations.

13.2 Transportation:

Marketable clay excavated during the course of overburden removal will be transported

deploying dumpers to the clay stock yard located near the mine. The entire mined out

Marketable clay will be sold to local industries.

13.3 Population projection:

There are four villages located within 5 km radius of mining area. The approximate

distance and population are given in the table below:

20

Direction from Mine Name of village Approx. Distance in

km

Population

(Latest census)

West Barsingsar 0.5 5766

East Palana 3.0 9331

North West Saroopdesar 5.0 4052

WNW Bholasar 5.0 2592

All basic needs like schools, hospitals, communication facilities etc are available in all the

villages.

13.4 Land use planning (break up along with green belt):

Land use is already discussed at para 4.0

The reclamation details carried out in Barsingsar lignite mine till March, 2019 are given in

the table below:

(Area in ha)

S.No Location Area planted Area available for plantation

1 External Dump 49.0 30.0

2 Internal Dump 1.0 14.2

Total 50.0 44.2

Total area reclaimed in the external dump is 79.0 ha, out of which 49.0 have been planted

and another 30.0 ha is ready for plantation. Similarly, area reclaimed in internal dump is

15.2 ha, out of which 1.0 ha is planted and another 14.2 ha is ready for plantation.

In addition to 50.0 ha planted in external and internal dump, gap and avenue plantation has

been done in another 31.0 ha. Since inception, 56,690 number of tree saplings have been

planted at different locations of mine project, out of which 31,814 have survived and are in

different stages of growth. . Reclamation measures adopted and measures taken up by the

proponent to protect the fauna and flora are briefed below:

Technical Reclamation:

After the lignite is mined out, the void area is filled back by overburden up to the original

ground level. Then a layer of top soil is spread over the backfilled area. Initial water

sprinkling is done and the area becomes ready for biological reclamation.

21

Spreading of top soil over the

reclaimed area

Biological reclamation:

After top soil layer is spread over de-coaled back filled area, small pits are excavated and

manure is applied. Before start of monsoon, the saplings are planted in the small pits and

regular watering is done. Fencing of the area is done for the protection of the plants from

grazing of animals. To provide regular watering, three numbers of water tanks have been

constructed in external dump area.

Reclaimed area covered by

plantation:

22

Protection of flora-fauna:

To conserve the flora and fauna of the area following measures are being taken

1. Water ponds (small capacity) are being formed at different locations for providing

drinking water for wild animals and birds.

2. Creation of temporary sump within working area.

3. Existing desert plants species such khejdi, babul and other local shrubs of ber, grass

etc are protected

.

Migratory birds visiting the mine and surrounding areas

13.5 Assessment of Infrastructure demand (Physical & social)

The existing road and other infrastructure facilities are enough to meet out the

requirements.

13.6 Amenities/Facilities:

All facilities like office, statutory buildings, water, power, medical facilities etc are already

available in the project.

13. PROPOSED INFRASTRUCTURE:

14.1 Industrial area (Processing area):

No mineral processing is proposed.

14.2 Residential area (non processing area):

23

No additional residential area is proposed.

14.3 Green belt:

In addition to bringing the reclaimed mined out area and reclaimed external dump under

green cover, additional green belt is under development by planting native species as per

approved Mining plan.

14.4 Social Infrastructure:

All essential facilities like primary & secondary schools, centre for technical education run

by NLCIL, hospitals (both govt & NLCIL), bank and other services are available in

Barsingsar. NLCIL has provided an I.T.I for skill development for the local villagers.

Rural infrastructure development works such as roads, water supply, sanitation, street lights

and women empowerment are carried out under CSR scheme to benefit surrounding

villages. About Rs. 3.0 crs is spent on CSR works every year.

14.5 Connectivity:

Area is connected with nearby villages and district headquarters by well maintained road

network.

14.6 Drinking water management (Source & Supply):

Water is drawn from IGNP canal to meet industrial as well domestic/drinking water

requirements. In order to improve water potential in the surrounding areas, de-silting of

nearby water storage structures is carried out.

Rain water Harvesting: Towards conserving rain water rain water storage tank has been

provided at Barsingsar.

14.7 Sewerage system:

Sewage generated from office premises is treated through septic tank and soak pit. Well

established ETP is functioning to treat the sewage from colony.

14.8 Industrial waste management:

24

No industrial waste will be generated from the mine.

14.9 Solid waste management:

Solid waste from the mine is in the form of overburden material removed for exploiting

lignite. The entire solid waste is managed as per the approved mining plan.

14.10 Power requirement, supply & source:

About 1.5 million units of power per annum is being consumed for mining related

activities. Required power for Barsingsar Mine is drawn from pit head Barsingsar TPS. All

the mining machineries are diesel driven. Power is mainly required for operating Lignite

Handling Plant, Lignite conveyors, lighting in mines, haul roads, colony and office

premises.

14. (1) REHABILITATION AND RESETTLEMENT (R&R) PLAN:

Policy to be adopted (Central/state) in respect of the project affected person including

home oustees, land oustees and landless laborers (a brief outline to be given).

The Project affected persons have already been rehabilitated and resettled in consultation

with state government. Direct employment has been provided depending upon eligibility.

Direct employment was given to 159 PAP’s and indirect employment to about 250 people.

Landless laborers are engaged in contractual jobs. Those who last their house were given

house plots for constructing new houses.

Developmental works like road construction, drinking water supply through construction of

bore wells, providing furniture’s to schools and hospitals, medical camp etc. are being

carried out under CSR for the benefit of local populace by the project.

(2) CORPORATE SOCIAL RESPONSIBILITY:

CSR Policy:

Corporate Social Responsibility (CSR) has always been intricately embedded in NLC’s

vision and mission to contour the corporate success. Right from its inception in 1956,

NLCIL is engaging itself in various Corporate Social Responsibility activities,

integrated with the business activities. NLCIL has been extending health, education,

25

transport, library and sports facilities to surrounding public along with such services

provided to NLCIL employees and their wards in the Neyveli Region. Exclusive CSR

projects/schemes/ activities/ programmes are also being carried on by NLCIL for the

benefit of the local society at large. With this long local CSR experience for over 5

decades, NLCIL has evolved and further formulated the Corporate Social

Responsibility Policy and formally documented it on 26.10.09.

The main objective of CSR plans of NLCIL is to maximize NLCIL’s contribution to the

Sustainable Development of the localities in which it operates.

This main objective is translated into the following workable and result oriented

objectives:

Striking win-win solutions in all situations involving the interest of the

stakeholders

Establishing a harmonious relationship of NLCIL with the local public

Inclusive growth with appropriate value shared with all the stakeholders

Environment protection and up-gradation for the future.

NLCIL’s CSR evolved as a natural corollary to its business operations:

NLCIL’s operations are technology and project driven. The following dimensions of

NLCIL’s CSR are conspicuous as a natural corollary to its business i.e., Mining and

Power Station Projects of large scale:

a. The production of desired products and rendering of quality services with

minimum impact on the environment, including the human environment

(during the economic life) and

b. The Peripheral Development (regular extra-business contributions to the

society/environment, integrated with business activities)

Activities undertaken under CSR Policy:

As regards the routine integrated CSR activities, NLCIL continues its contribution to the

neighboring society in the important areas such as Education, Peripheral Development,

Employability and Entrepreneurial/ Managerial Development, Health and also Life-quality

26

Improvement. NLCIL is keeping harmonious relationship with the society and striving to

maximize its contribution to the sustainable development of the region.

In case of natural calamities/disasters/distress also, NLCIL is most responsive and hard

working in the region and voluntarily extends emergency measures of help. CSR

projects/schemes/activities/ programmes being carried on by NLCIL for the benefit of the

local society at large in the Neyveli and Barsingsar regions are of the following forms,

among others.

Patronizing Social Welfare Societies/Opportunity Schools for Special Children

Grant and Infrastructure to such special institutions and other educational societies

Community Health Screening Camps

Medical support to the elderly

Mosquito control programme

Plastic menace control programme

Immunization programme

Epidemics-control programmes (prophylactic measures)

Supplying water to the surrounding villages for irrigation

Sinking of drinking water bore wells in the surrounding villages

Bridges/culverts in the nearby villages

Public toilets in the nearby villages

CSR focused programmes of training and development for students and teachers

Facilitating In-plant Training and Project Work for students of various disciplines

Past service recognition measures

Death benefits to the family of the deceased employees

Contributions to the cause of women

Providing access to facilities of township to the neighboring villagers through

subsidized Transport

Setting up of an Industrial Training Institute in Barsingsar

Supplied drinking water to urban agglomerations (1983 & 1993) and to Chennai

city (2001) by rail and road, when struck by drought

27

Voluntary deployment of NLCIL’s equipment and personnel with necessary

material for disaster related relief operations in the region – Voluntary work

undertaken in Tsunami affected areas (Jan 2005), Gaja affected areas (2018).

Food relief works in the surrounding area including repairs to Roads, providing

temporary shelter and supplying food & medicines to the flood affected.

Under “Swachch Vidyalaya Abhiyan” scheme, constructed 1275 toilets at a cost of

Rs.35.00 crores in government schools in the state of Rajasthan (140 Nos.) and

Tamilnadu (1135 Nos.).

The CSR activities carried out by Barsingsar project and the expenditure incurred during

the past three years is given as Annexure- IV, V & VI.

15. PROJECT SCHEDULE & COST ESTIMATES:

Barsingsar lignite Mine is a working mine being operated through outsourcing mode. All

the capital expenditure has already been incurred and further investment is not required for

excavating marketable clay.

16. ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS):

The lignite mine project has already given direct as well as indirect employment facilities

to the Project affected families and villagers and employment through contractors. Lot of

employment opportunities have been created in the form of service providers, petty

contracts, hiring vehicles etc. In addition to above, Clay mining will provide business

opportunities to transporters, traders and employment opportunities in ceramic industry. It

is an important activity in conservation of natural resource-clay which otherwise would

have been wasted in the dump yard There is no increase in pollution load due to this as it is

part of the overburden.

The socio economic and living conditions of the village and nearby areas have improved.

The infrastructures like road, transport, communication, medical etc have improved in the

locality.

28

Annexure-I

29

Annexure-II

30

Annexure-II contd…

31

Annexure-II contd…

32

Annexure-II contd…

33

Annexure-III

Plantation Details as on 31.03.2019

Sl.No Plantation Location Planted Survived Area covered

( in Ha)

1 Outside & Opposite to Main Gate of

Mine (Properly fenced) 10200 9159 22.65

2 Outside the Mine compound wall

(Towards Palana& Silo side) 2500 1562 4

3 Around Artificial Lake 4960 1363 15

4

Inside Mine periphery including

conveyor belt and behind main gate

sump

9775 3665 40

6 Dump yard Plantation - Phase I 5000 1177 15

7 Dump yard Plantation - Phase II 10000 5724 25

9 Road sides in front of First Aid centre 80 65 0.1

10 View point Road sides & Conveyor

Drive head area 225 88 0.5

11 Mine 1 in 20 ramp median - road sides 150 15 0.37

12 Afforestation near Decoaled area ( new

view point ) 850 73 1.1

13 On the new lawn near First AID Centre 25 25 0.1

14 Dump yard Plantation - Phase 3 10000 6023 25

15 Bore well 6 area 845 795 1

16 Dump yard Plantation - Phase 4 2080 2080 2

Total 56690 31814 151.82

34

Annexure-IV

NLC India Limited, Barsingsar Project - CSR activities carried out during F.Y. 2016-17

S.No Works done under CSR in F.Y. 2016-17 Location where

works have done

Amount

spent in Rs.

1 Construction water storage structure at PANCH

BORDI TALAI, Hanuman nagar, Bhelu, Kolayat under

Munkhyamantri Jal Swawlamban Yojna.

Hanuman nagar,

Bhelu, Kolayat

1727498.50

2 Construction water storage structure at SIDHOLAI

TALAI, DASAUDI, Kolayat under Munkhyamantri Jal

Swawlamban Yojna.

DASAUDI,

Kolayat

1775300.57

3 Repairing of water storage structure at Vijavrao ki

dhani, Bhelu and Chawani Nadi, Hanuman nagar,

Bhelu & Excavation and floor preparation at

Kadkhaliya Nadi, Hanuman nagar, Bhelu, Kolayat

under Munkhyamantri Jal Swawlamban Yojna.

Hanuman nagar,

Bhelu Kolayat

1550676.57

4 Providing rooftop water harvesting structures at Govt.

Upper Primary School and community hall at Khajoda

village, Nandada, Kolayat under Munkhyamantri Jal

Swawlamban Yojna.

Nandada, Kolayat 119995.00

5 Providing Black Top (BT) road between Swaroopdesar

and Barsingsar village.

Barsingsar and

Swaroopdesar

8491252.66

6 Providing WBM road between Bholasar and Barsingsar

village.

Barsingsar and

Bholasar

6300000.00

7 Painting inside Eight (8) class rooms, inside and

outside Gallery at Government Girls Secondary School,

Palana, Dist.-Bikaner.

Government Girls

Secondary

School, Palana,

Dist.-Bikaner

74673.28

8 Purchase of furniture for handing over to Govt. Girls

Sec. School Palana

Government Girls

Secondary

School, Palana,

Dist.-Bikaner

99708.00

9 Purchase of carpets for handing over to Govt. Girls Sec.

School Palana

Government Girls

Secondary

School, Palana,

Dist.-Bikaner

24990.00

10 Supply installation and commissioning of 3.5KVA &

2.5KVA invertor at GGSS, Palana under CSR activities

Government Girls

Secondary

School, Palana,

Dist.-Bikaner

160000.00

35

Annexure-IV contd….

S.No Works done under CSR in F.Y. 2016-17 Location where

works have done

Amount

spent in Rs.

11 Providing Projector and Projector screen at G.G.S.S.,

Palana, Dist. Bikaner

Government Girls

Secondary School,

Palana, Dist.-

Bikaner

57442.00

12 Purchase of fiber pole vault for handing over to Govt.

Sr. Sec. School Barsingsar

Government Girls

Secondary School,

Palana, Dist.-

Bikaner

26000.00

13 Purchase of two nos. 50 liter capacity RO and one

number 80 liter capacity Water cooler to hand over to

Govt. Sr. Sec. School Barsingsar.

Govt. Sr. Secondary

School, Barsingsar,

Dist.-Bikaner

143296.00

14 Purchase of two nos. Sanitary napkin destroying

machine to hand over to Govt. Sr. Sec. School

Barsingsar & Govt. Bothra Girls Sr. Sec. School

Gangasahar

Govt Sr. Secondary

School, Barsingsar,

& Govt. Bothra

Girls Sr. Sec.

School Gangasahar

58485.00

15 Construction of Girls Toilet block at Govt. Bothra

Girls Sr. Sec. School, Gangasahar, Bikaner under

CSR activities of NLC Barsingsar Project

Govt. Bothra Girls

Sr. Sec. School

Gangasahar

369779.24

16 Supplying 100 nos. tree guards to hand over to

District Sports Officer, Bikaner under CSR activities

of NLC Barsingsar Project

Karni Singh

Stadium, Bikaner

100000.00

17 Contribution of an amount of Rs. 2.00 lakhs (Rupees

Two Lakhs only) to the Non Profit Organization

LOKAYAN for the event ” The Rajasthan Kabir

Yatra”.

Bikaner 200000.00

18 Provding items to new born baby girl, girl students

studying in Ist std. and meritorius girl students of Xth

& XII std.

Basi, Barsingsar and

Palana

233032.00

19 Contribution for Camel festival in Bikaner Bikaner 30000.00

20 Contribution for sports meet at Income tax dept. Bikaner 10000.00

21 Providing Roads inside Basi and Barsingsar village

phase-1 under CSR activities of NLC-Barsingsar

project

Basi-Barsingsar,

Bikaner

5873290.00

Total amount spent during the F.Y 2016-17 27425418.82

36

Annexure-V

NLC India Limited, Barsingsar Project - CSR activities carried out during F.Y. 2017-18

S.No Works done under CSR in F.Y. 2017-18 Location where

works have

been done

Spent CSR

amount for

F.Y. 2017-18

1 Purchase of 20 sets of Sanitary napkins and

incinerator for distributing to Govt. Girls school

in Bikaner Dist.

Entire Bikaner

district, mainly

nearer to

Barsingsar

Project site

961712.00

2 Construction of drainage system for water outage

under Sansad Adarsh Gram Yojna at Panchayat

Bikampur, Panchayat Samiti Srikolayat, Bikaner

Bikampur,

Kolayat

3000000.00

3 Repairing of water storage structure Megha Talai

& Urmul Talai at Khariya Patawatan, Kolayat

under Munkhyamantri Jal Swawlamban Yojna

phase-II.

Khariya

Patawatan,

Kolayat

1799985.00

4 Repairing of water storage structure Bijeri Talai

& Natholi Talai, Tokla, Kolayat under

Munkhyamantri Jal Swawlamban Yojna phase-II.

Tokla, Kolayat 999993.00

5 Repairing of water storage structure Bero ka talab

and Motolav ka talab at Nokhara Kolayat under

Munkhyamantri Jal Swawlamban Yojna phase-II.

Nokhra, Kolayat 2699995.00

6 Providing two nos. bore wells for drinking water

in Basi – Barsingsar village

Basi - Barsingsar

village

3996000.00

7 Purchase of one number Fiber Pole Vault to hand

over to Govt. Senior Secondary School,

Barsingsar Bikaner

Barsingsar 150995.20

8 Renovation and certain misc. civil works at Play

ground of Basi-Barsingsar village

Basi-Barsingsar,

Bikaner

1832039.68

9 Providing drain and rain water storage tank at

Barsingsar

Barsingsar 728321.96

10 Construction of boundary wall at Playgrounds at

Lalamdesar & Palana

Lalamdesar and

Palana

1416915.95

11 Construction of Drinking place and toilet blocks

at Govt. Senior Secondary school, Bholasar

Bholasar 600274.90

12 Providing Infrastructure facilities at cow stable in

Swaroopdesar village

Swaroopdesar 779940.54

13 Providing paver blocks at Govt. Hospital,

Udairamsar

Udairamsar 782703.22

14 Distribution of baby kits to girl babies born in

Govt. hospitals nearer to project site.

Basi, Barsingsar

and Palana

31774.00

15 Distribution of school kits for Girls studying Ist

standard

Basi, Barsingsar

and Palana

2184.00

16 Distribution of school kits for Girls studying Ist

standard

Basi, Barsingsar

and Palana

23965.00

37

Annexure – V contd…

S.No Works done under CSR in F.Y. 2017-18 Location where

works have

been done

Spent CSR

amount for

F.Y. 2017-18

17 Distribution of school kits for Girls studying Ist

standard

Basi, Barsingsar

and Palana

8745.00

18 Scholarship to the meritorious girl students of

Government/ Private Schools around Barsingsar

Project.

Basi, Barsingsar,

Palana, Bholasar,

Swaroopdesar,

Lalamdesar,

Udairamsar

304000.00

19 Donation for camel festival january-2018 in

Bikaner.

Bikaner 30000.00

20 Providing and fixing one set of Basketball pole

along with board and ring at police line Bikaner

Bikaner 153065.88

21 Providing Bitumen carpet over the existing road

between Barsingsar to Udairamsar bypass at NH-

89 including attending patch works and

construction of Arches

Barsingsar and

Udairamsar

8586660.91

22 Providing 50 nos. tree guards to Govt. Chopra Sr.

Sec. School Bikaner.

Bikaner

109150.00

23 Providing 250 nos. Solar Photovoltaic based LED

street lighting systems in Pali parliament

constituency of Rajasthan state

Pali

5709000.00

24 Introduction of Surya Mitra Course at Rajeev

Gandhi ITI, Barsingsar Project

Barsingsar

435000.00

Total amount spent during F.Y 2017-18 35142421.24

38

Annexure-VI

NLC India Limited, Barsingsar Project - CSR activities carried out during F.Y. 2018-19

S.No Works done under CSR in F.Y. 2018-19 Location where

works have been

done

Amount

spent in Rs.

1 Renovation and certain misc. civil works at Play

ground of Basi-Barsingsar village

Basi - Barsingsar 209114.00

2 Providing drain and rain water storage tank at

Barsingsar

Basi - Barsingsar 443866.78

3 Construction of boundary wall at Playgrounds at

Lalamdesar & Palana

Lalamdesar and

Palana

916180.46

4 Construction of Drinking place and toilet blocks at

Govt. Senior Secondary school, Bholasar

Bholasar 49346.33

5 Providing Infrastructure facilities at cow stable in

Swaroopdesar village

Swaroopdesar 571572.00

6 Providing paver blocks at Govt. Hospital,

Udairamsar

Udairamsar 268906.60

7

Providing Bitumen carpet over the existing road

between Barsingsar to Udairamsar bypass at NH-89

including attending patch works and construction of

Arches

Barsingsar and

udairamsar

299210.91

8

Providing 250 nos. Solar Photovoltaic based LED

street lighting systems in Pali parliament

constituency of Rajasthan state

Ten villages in Pali 5497800.00

9 Introduction of Surya Mitra Course at Rajeev Gandhi

ITI, Barsingsar Project

Basi - Barsingsar 390575.00

10 Purchase of lab materials from Suryamitra Course in

RGITI

Basi - Barsingsar 23836.00

11

Repairing of water storage structure Bijeri Talai &

Natholi Talai, Tokla, Kolayat under Munkhyamantri

Jal Swawlamban Yojna phase-II.

Tokla, Kolayat 2106.00

12

Providing Black Top over the existing WBM road

between Barsingsar to Bholasar including attending

patch works

Barsingsar and

Bholasar

8461600.00

13

Repairing of water storage structures in Kolayat

under Munkhyamantri Jal Swawlamban Yojna -

phase-III

Kolayat 6139000.00

14

Distribution of scholarships under Cash Award

Scheme and Educational Assistance Scheme to the

meritorious girl students from schools situated in the

surrounding areas/villages of Barsingsar Project

Basi - Barsingsar,

Palana,

Lalamdesar,

Bholasar,

Swaroopdesar and

Udairamsar

601033.00

39

Annexure – VI contd….

S.No Works done under CSR in F.Y. 2018-19 Location where

works have been

done

Amount

spent in Rs.

15 &

16

Distribution of baby kits to new born babies under

Beti Bachao scheme &

Distribution of school kits to 1st standard girl student

under "Beti Padhao" scheme

Basi, Barsingsar

and Palana

a Study table and chair 78550.00

b Baby items 149550.00

c School bag & stationary items 53900.00

d Thermo Flask, Tiffin Box & Water Bottles 68750.00

17 Donation for camel festival January-19 in Bikaner Bikaner 30000.00

18

Infrastructure development in village and Govt.

schools in surrounding villages i.e. Palana,

Lalamdesar, Bholasar and Swaroopdesar.

Palana,

Lalamdesar,

Bholasar and

Swaroopdesar

a Renovation of Kumbhalai talai at Lalamdesar 23600.00

b

Construction of class rooms at Govt. Sr. Sec. School,

Bholasar and construction of Prayer shed at Govt. Sr.

Sec. School, Swaroopdesar

952080.96

c Providing infrastructure facilities at Govt. Sr.

Secondary School, Palana

23600.00

19

Arrangement of mobile ambulance for periodical

health check up of villagers

Basi - Barsingsar

and surrounding

villages

a Procurement of Medicines, Glucometer Strips &

Machines for Medicamp

198482.36

b Arrangements of Tent for medicamps. 19000.00

c Arrangements of Photography for Medicamps. 4500.00

d Arrangements of Refreshment for medicamps. 8327.00

e Arrangements of pumplets for medicamps. 3658.00

20 Infrastructure development in village and Govt.

schools in Basi and Barsingsar Basi - Barsingsar

a Providing infrastructure facilities at cow stable,

Barsingsar

857065.50

b

Renovation of Talai near hariram ram ji temple at

Barsingsar and Construction of toilet, bathroom and

other renovation works at community hall, Basi

212046.00

21 Providing Infrastructure facilities at physically

chalanged (blind) hostel cum Govt. school, Bikaner

Bikaner 685313.89

TOTAL 27242570.79