Final minutes of 4.95 th meeting held on 27-29 July, 2021 Minutes of the 4.95 th VC Meetings of the State Level Expert Appraisal Committee (SEAC), (Raj.), held on 27 th ,28 th and 29 th July ,2021 The 4.95 th VC Meeting of the members of State Level Expert Appraisal Committee (SEAC), Rajasthan constituted for considering environmental clearance projects (B-category) under GoI Notification 18.12.19 was held on 27 th , 28 th and 29 th July, 2021 at 10:30 AM through video conferencing under the Chairmanship of Sh. Manoj Kumar Agrawal. The names of the members who attended the meeting are as follows:- S. No. Name Designation 27.07.2021 28.07.2021 29.07.2021 1 Sh. Manoj Kumar Agrawal Chairman Attended Attended Attended 2 Dr. Suja George Vice Chairman - - - 3 Sh. Pushakar Singh Shekhawat Member Attended Attended Attended 4 Sh. Mukesh Behari Sharma Member Attended Attended Attended 5 Sh. Laxmi Kant Dashora Member Attended Attended Attended 6 Sh. Buddhi Prakash Pareek Member Attended Attended Attended 7 Sh. Vikram Singh Chauhan Member Attended Attended Attended 8 Sh. Nand Kumar Khare Co-opted Member, SEAC - - - The Secretary welcomed the members. The SEAC considered the following 19 projects and 07 Additional agenda, with the permission of Chairman, SEAC. S.No File No Subject Project Proponent Name & Consultant Name 1. 15817 EIA EMP of limestone (Minor Mineral )From 14,600 TPA to 15,00,000 TPa (Lime stone burning ) M.L no-122/91,Area- 100.00hect.,By M/s Nitesh mineral Pvt. Ltd location at village Hariyadhana, tehsil- bilara, dist- Jodhpur(Raj.) .(Proposal no-30615) Project Proponent Name-M/S. Nitesh Minerals Pvt. Ltd,Add-Old public park Road ,near K.N.collage, Rai ka Bagh Jodhpur(Rajasthan)Email- [email protected] ,[email protected], CONSULTANTS- Udaipur Min-Tech PVT. LTD.,Add-206,Apeksha Complex.Sec-11.Hiran Magri,Udaipur (Raj) [email protected] 2. 264 EIA EMP for of Chechat Limestone Proponent Name :- M/S SHIVA STONE

Transcript of Minutes of the 4.95th VC Meetings of the State Level Expert ...

Final minutes of 4.95th meeting held on 27-29 July, 2021

Minutes of the 4.95th VC Meetings of the State Level Expert Appraisal Committee

(SEAC), (Raj.), held on 27th ,28th and 29th July ,2021

The 4.95th VC Meeting of the members of State Level Expert Appraisal Committee

(SEAC), Rajasthan constituted for considering environmental clearance projects (B-category)

under GoI Notification 18.12.19 was held on 27th, 28th and 29th July, 2021 at 10:30 AM

through video conferencing under the Chairmanship of Sh. Manoj Kumar Agrawal. The

names of the members who attended the meeting are as follows:-

S. No. Name Designation 27.07.2021 28.07.2021 29.07.2021

1 Sh. Manoj Kumar

Agrawal

Chairman Attended Attended Attended

2 Dr. Suja George Vice

Chairman

- - -

3 Sh. Pushakar Singh

Shekhawat

Member Attended Attended Attended

4 Sh. Mukesh Behari

Sharma

Member Attended Attended Attended

5 Sh. Laxmi Kant

Dashora

Member Attended Attended Attended

6 Sh. Buddhi Prakash

Pareek

Member Attended Attended Attended

7 Sh. Vikram Singh

Chauhan

Member Attended Attended Attended

8 Sh. Nand Kumar

Khare

Co-opted

Member,

SEAC

- - -

The Secretary welcomed the members.

The SEAC considered the following 19 projects and 07 Additional agenda, with the

permission of Chairman, SEAC.

S.No File

No

Subject Project Proponent Name & Consultant

Name

1. 15817 EIA EMP of limestone (Minor

Mineral )From 14,600 TPA to

15,00,000 TPa (Lime stone burning

) M.L no-122/91,Area-

100.00hect.,By M/s Nitesh mineral

Pvt. Ltd location at village

Hariyadhana, tehsil- bilara, dist-

Jodhpur(Raj.) .(Proposal no-30615)

Project Proponent Name-M/S. Nitesh

Minerals Pvt. Ltd,Add-Old public park

Road ,near K.N.collage, Rai ka Bagh

Jodhpur(Rajasthan)Email-

[email protected]

,[email protected],

CONSULTANTS- Udaipur Min-Tech

PVT. LTD.,Add-206,Apeksha

Complex.Sec-11.Hiran Magri,Udaipur (Raj)

[email protected]

2. 264 EIA EMP for of Chechat Limestone Proponent Name :- M/S SHIVA STONE

Final minutes of 4.95th meeting held on 27-29 July, 2021

Building Stone mine over an area of

24.2503 Hect.M.L.

NO-24/93 Near Village- Chechat

,Tehail-Ramganjmandi, District-

Kota, Rajasthan in favor of M/S

Shiva Stone.(Proposal No-60416)

,In Front of RSEB, Near Hotel Indraprastha,

NH-12,Jhalawar Rajasthan,Email-

[email protected]

Name of the Consultant:- EIA

CONSULTANT, M/s UDAIPUR MINE-

TECH PVT. LTD. 206,APEKSHA

COMPLEX. SEC-11.,HIRAN MAGRI,

UDAIPUR,(RAJ) Email:-

[email protected]

3. 16951 EIA EMP of Environmental

Clearance for “Limestone

(Dimensional) & Masonry Stone

(Kali Chat), Ref. No.

2019100004792, Area 4.00 ha.(Pvt.

Land), Near Village Pipliya

(Runji),Tehsil Pachpahar, District

Jhalawar, (Raj). Khasra No. 653,

284, 287, 289, 290, 291,

292, (Proposal No. 62668)

Name of Proponent:- Shri Pukhraj

Jain,Add- “Miraya Mension”Opposite

RSEB, Near Indraprasth Hotel, Tehsil

Jhalrapatan, District Jhalawar, (Raj.).Email

[email protected]

Name of Consultant: -M/s Udaipur Min-

Tech Pvt. Ltd.206, Apeksha Complex. Sec-

11. Hiran Magri, Udaipur, (Raj.).email:-

[email protected],

4. 19623 E C of Golpur Sandstone Mining

Project Plot No. 32, Area 1.00 Ha.,

Khase No. 369/5, Add.- Golpur,

Tehsil- Bundi, District- Bundi,

(Raj.) (Proposal No.- 216092)

Name of Proponant :- Shri- Preetam

Singh Bhadoriya S/o Shri- Harendra Singh

Bhadoriya, Add.- Behind Star Public

School, Govind Nagar Road, Prem Nagar 1,

Kota, District- Kota, (Raj.) Email-

[email protected]

Name of Consultant:- P AND M

SOLUTION, Add.- Shivani mines &

Minerals, B-39, RIICO, Housing Colony,

Beawar, Distt.- Ajmer (Raj.) Email.-

[email protected]

5. 19631 E C of Khananiya Khera Quartz &

Feldspar Mine M.L. No. 81/2002,

Area 5.00 Ha., Khase No. 522, 530,

531, 529, 528, 527, 534, 535, 541,

538, 540, 539, 536, Add.-

Khananiya Khera, Tehsil- Raipur,

District- Bhilwara, (Raj.) By Mr.

Shabbur Ahmad S/o Mr. Fakhruddin

Sheikh (Proposal No.- 208561)

Name of Proponant :- Mr. Shabbur

Ahmad S/o Mr. Fakhruddin Sheikh, Add.-

Regaron Ki Kui, Tehsil- Asind, District-

Bhilwara, (Raj.) Email-

[email protected]

Name of Consultant:- P AND M

SOLUTION, Add.- Shivani mines &

Minerals, B-39, RIICO, Housing Colony,

Beawar, Distt.- Ajmer (Raj.) Email.-

[email protected]

Final minutes of 4.95th meeting held on 27-29 July, 2021

6. 19602 E C for Masonry Stone Mining

Project" Plot No. 03, Area 1.00

Ha., Khase No. 957, 340, Add.-

Ramgarh Padlibad, Tehsil- Sikrai,

District- Dausa, (Raj.) (Proposal

No.- 208038)

Name of Proponant :- Shri- Ramavtar

Sharma S/o Shri- Kundan Ram Sharma,

Add.- 191/27, Sector-19, Pratap Nagar,

Sanganer, Jaipur, Distt.- Jaipur, (Raj.)

Email- [email protected]

Name of Consultant:- :- Globus

Environment Services, Add.- 326-AB, 3rd

Floor, Sahara Shopping Center, Lekhraj

Crossing, Faizabad Road, Lucknow (U.P.)

Email. –

[email protected]

7. 19603 E C for Masonry Stone Mining

Project" Plot No. 02, Area 1.3774

Ha., Khase No. 957, 340, 171,

Add.- Ramgarh Geejgarh Padlibad,

Tehsil- Sikrai, District- Dausa,

(Raj.) (Proposal No.- 207955)

Name of Proponant :- Shri- Ramavtar

Sharma S/o Shri- Kundan Ram Sharma,

Add.- 191/27, Sector-19, Pratap Nagar,

Sanganer, Jaipur, Distt.- Jaipur, (Raj.)

Email- [email protected]

Name of Consultant:- :- Globus

Environment Services, Add.- 326-AB, 3rd

Floor, Sahara Shopping Center, Lekhraj

Crossing, Faizabad Road, Lucknow (U.P.)

Email. –

[email protected]

8. 19618 E C for Masonry Stone Mining

Project" Plot No. 05, Area 1.8827

Ha., Khase No. 134, Add.- Kalwan,

Tehsil- Sikrai, District- Dausa,

(Raj.) (Proposal No.- 199978)

Name of Proponant :- Shri- Rajendra

Prasad Sharma S/o Shri- Rameshwar

Prasad Sharma, Add.- Kuiwali Dhani,

Raipura, Sikrai, Distt.- Dausa, (Raj.)

Email- [email protected]

Name of Consultant:- :- Globus

Environment Services, Add.- 326-AB, 3rd

Floor, Sahara Shopping Center, Lekhraj

Crossing, Faizabad Road, Lucknow (U.P.)

Email. –

Final minutes of 4.95th meeting held on 27-29 July, 2021

[email protected]

9. 19619 E C for Sand Stone Mining

Project" Q.L. No. 2192, Area 0.18

Ha., Khase No. Not, Add.- Keru,

Tehsil- Jodhpur, District- Jodhpur,

(Raj.) (Proposal No.- 208590)

Name of Proponant :- Shri- Ghanshyam

Prajapati S/o Shri- Peeramal Prajapati,

Add.- Near Sankatmochan Balaji Temple

Duliya Bas, Sujangarh, Churu, Distt.-

Churu, (Raj.) Email-

[email protected]

Name of Consultant:- :- Globus

Environment Services, Add.- 326-AB, 3rd

Floor, Sahara Shopping Center, Lekhraj

Crossing, Faizabad Road, Lucknow (U.P.)

Email. –

[email protected]

10. 18798 E C for Sandstone Mining Project"

Ref. No. 20191000014379, Area

1.877 Ha., Khase No. 352/4, 352/7,

352/9, 352/10, Add.- Badli, Tehsil-

Jodhpur, District- Jodhpur, (Raj.)

(Proposal No.- 62792)

Name of Proponant :- Smt.-Narbada

Kachhawaha W/o Shri- Panna Lal

Kachhawaha, Add.- Kishan Service Center,

Pratap Nagar, Soorsagar Road, Jodhpur,

Distt.- Jodhpur, (Raj.) Email-

[email protected]

Name of Consultant:- :- Globus

Environment Services, Add.- 326-AB, 3rd

Floor, Sahara Shopping Center, Lekhraj

Crossing, Faizabad Road, Lucknow (U.P.)

Email. –

[email protected]

11. 18799 E C for Sandstone Mining Project"

Ref. No. 2019100004382, Area

1.4658 Ha., Khase No. 348/01,

Add.- Badli, Tehsil- Jodhpur,

District- Jodhpur, (Raj.) (Proposal

No.- 62778)

Name of Proponant :- Shri-Pukhraj Gehlot

S/o Shri- Ramchandra Gehlot, Add.- Gali

No. 1, Kheme Ka Kua, Pal road, Distt.-

Jodhpur, (Raj.) Email-

[email protected]

Name of Consultant:- :- Globus

Final minutes of 4.95th meeting held on 27-29 July, 2021

Environment Services, Add.- 326-AB, 3rd

Floor, Sahara Shopping Center, Lekhraj

Crossing, Faizabad Road, Lucknow (U.P.)

Email. –

[email protected]

12. 19606 E C for Masonry Stone (Crusher

Gitti) Mining Project Ref. No.

202010000 28711, M.L. No.

09/2020, Area 1.0427 Ha., Khase

No. 922, Add.- Kesunda, Tehsil-

Chhoti Sadri, District- Pratapgarh,

(Raj.) (Proposal No.- 214422)

Name of Proponant :- Shri- Labhachand

Meghwal S/o Shri- Gotam Lal Meghwal,

Add.- Kesunda, Tehsil- Chhoti Sadri,

Distt.- Pratapgarh, (Raj.) Email-

[email protected]

Name of Consultant:- :- Fulgro

Environmental & Engineering Services

India Pvt. Ltd., Add-27, Ashok Vatika,

Khatipura Road, Jhotwara, Jaipur, (Raj.)

Email:- [email protected].

13. 19607 E C for Granite Mining Project

M.L. No. 30/2021, Plot No. 64,

Area 1.0159 Ha., Khase No. 1767,

1768, 1769, 1770, 1772, 1774,

Add.- Mankhand, Tehsil- Kekri,

District- Ajmer, (Raj.) (Proposal

No.- 214058)

Name of Proponant :- Shri- Ugmaram

Khichad S/o Shri- Chelaram Khichad,

Add.- Mukam, Post- Seeniya, Ranigaon,

Tehsil- Makrana, Distt.- Nagaur, (Raj.)

Email- [email protected]

Name of Consultant:- :- Fulgro

Environmental & Engineering Services

India Pvt. Ltd., Add-27, Ashok Vatika,

Khatipura Road, Jhotwara, Jaipur, (Raj.)

Email:- [email protected],

14. 19608 E C for Quartz Feldspar Mining

Project M.L. No. 58/2020, Area

1.0882 Ha., Khase No. 62/613, 63,

64, 65/1, 65/2, Add.- Rampuriya,

Tehsil- Saraha, District- Bhilwara,

(Raj.) (Proposal No.- 209709)

Name of Proponant :- Shri- Shankar Lal

Jat S/o Shri- Bhura Lal Jat, Add.-

Rampuriya, Post- Lakhola, Tehsil- Sahada,

Distt.- Bhilwara, (Raj.) Email-

[email protected]

Name of Consultant:- :- Fulgro

Environmental & Engineering Services

India Pvt. Ltd., Add-27, Ashok Vatika,

Khatipura Road, Jhotwara, Jaipur, (Raj.)

Email:- [email protected],

15. 19622 E C for Granite Mining Project

M.L. No. 24/2021, Ref. No.

Name of Proponant :- Smt. Sangita Devi

W/o Shri- Hemraj Khatik, Add.- Ward No.

Final minutes of 4.95th meeting held on 27-29 July, 2021

20211000034409 Area 2.1528 Ha.,

Khase No. 2525, 2545, 4052/2524,

4478/2526, Add.- Bachhkhera,

Tehsil- Shahpura, District-

Bhilwara, (Raj.) (Proposal No.-

215008)

06, Khatik Mohalla Bachhkhera, Tehsil-

Shahpura, Distt.- Bhilwara, (Raj.)

Email- [email protected]

Name of Consultant:- :- Fulgro

Environmental & Engineering Services

India Pvt. Ltd., Add-27, Ashok Vatika,

Khatipura Road, Jhotwara, Jaipur, (Raj.)

Email:- [email protected],

16. 19633 E C for Granite Mining Project

M.L. No. 31/2021, Area 1.0982

Ha., Khase No. 1772, 1773, 1774,

Add.- Mankhand, Tehsil- Kekri,

District- Ajmer, (Raj.) (Proposal

No.- 216498)

Name of Proponant :- Shri- Amit Nayyar

S/o Shri- Praveen Kumar Nayyar, Add.- C-

17, Shalimar Colony, Adarsh Nagar, Ajmer,

Distt.- Ajmer, (Raj.) Email-

[email protected]

Name of Consultant:- :- Fulgro

Environmental & Engineering Services

India Pvt. Ltd., Add-27, Ashok Vatika,

Khatipura Road, Jhotwara, Jaipur, (Raj.)

Email:- [email protected],

17. 19634 E C for Granite Mining Project

M.L. No. 32/2021, Area 1.0257

Ha., Khase No. 1772, 1773, 1774,

1775, Add.- Mankhand, Tehsil-

Kekri, District- Ajmer, (Raj.)

(Proposal No.- 216472)

Name of Proponant :- Shri- Amit Nayyar

S/o Shri- Praveen Kumar Nayyar, Add.- C-

17, Shalimar Colony, Adarsh Nagar, Ajmer,

Distt.- Ajmer, (Raj.) Email-

[email protected]

Name of Consultant:- :- Fulgro

Environmental & Engineering Services

India Pvt. Ltd., Add-27, Ashok Vatika,

Khatipura Road, Jhotwara, Jaipur, (Raj.)

Email:- [email protected],

18. 19110 Environmental Clearance for Red

Ochre Mining Project ( ML. No.-

2/2020, Ref. No.- 20201000021155,

QL. Area- 2.0069ha., Khasra No.-

818, 819, 822, 825) Near Vill.-

Akhepur, Tehsil & Distt.-

Pratapgarh (Raj.) (Proposal No.-

193480)

Project Proponent Name- Smt. Resham

Bhai W/o Late Sh. Sukhnath, Add.- House

No.-8, Ward No.- 01, Jadwasa, Distt.-

Ratlam (MP)

[email protected],

Consultant Name-Fulgro Environmental &

Engineering Services India Pvt. Ltd.,

Add.- 27, Ashok Vatika, Khatipura Road,

Jhotwara, Jaipur, (Raj.).Email:-

Final minutes of 4.95th meeting held on 27-29 July, 2021

[email protected],

19. 16617 EIA EMP of Bhawanipura & Sutra

Sandstone & Khanda Mining Project

Ref. No. 2018100001552 Khasra

No. 138 & 140, at Near Village –

Bhawanipura, Tehsil – Talera,

Disst.- Bundi, (Raj.) (Proposal

No.61904)

Name of Proponant :- Shri Nana Lal

Dhakar, Co-owners – 1. Shri Jagdish Chand

Dhakar, 2. Shri Rekh Lal Darad, 3. Shri

Basanti Lal, Add.- E-820, Indra Vihar,

Kota Distt.- Kota (Raj.) Email –

[email protected]

Name of Consultant:- COGNIZANCE

RESEARCH INDIA PRIVATE LTD. Add.-

Office GT – 20, Sec – 117,

Noida (U.P.) Email –

[email protected]

20. 16564 EC of Bhawanipura & Sutra

Sandstone & Khanda Mining

Project (Ref. No.2018100001181)

Area-2.4111hect.,Khasra no-

1081/208,209,at village-Sutra,

Tehsil-Talera,Dist-

Bundi,Rajasthan,(Proposal No-

61918)

Name of Proponant : -Shri Devi Singh,Co-

owners-1.Shri Pappu Singh S/o Shri Kajod

Singh,2. Shri Mukesh Singh S/o Shri Kajod

Singh3. shri Bablu singh S/o Shri Kajod

Singh,Add-Sutra, Tehsi-Talera, Dist-

Bundi,Rajasthan,Email-

[email protected]

,[email protected], Name of

Consultant:- :- Cognizance Research

India Private Ltd.(Accredited by NABET,

Govt. of India Accredited No.

NABET/EIA/1619/IA006, Valid up to Aug

18, 2019)Office GT-20, Sec 177, Noida-

201301 (U.P.)email:-

[email protected]

21. 15883 EIA/EMP for Bhawanipura & Sutra

Sandstone & Khanda Mining

Project Reference No.

201810000631, Area-2.4353hact.,at

Vill.- Bhawanipura, Tehsil- Talera,

Distt.- Bundi, and State- Rajasthan.

(Praposal No- 61787)

Project Proponent Name- Shri Nanda

Karad, Vill.- Sutra Tehsil- Talera, Distt.-

Bundi (Raj.) Email.-

[email protected]

Consultant – COGNIZANCE RESEARCH

INDIA PRIVATE LTD. GT-20, Sec-117,

Noida-(U.P.)

Email. Cognizanceresearchimdiapl@

gmail. com

Final minutes of 4.95th meeting held on 27-29 July, 2021

22. 16819 EIA/EMP of Fakoliya

Granite Mining Project M.L. No.

23/2007, Khasra No. – 1523/1362,

1524/1362, at village- Fakoliya,

Tehsil- Karera, Dist- Bhilwara,

State-(Raj.), (Proposal No-61868)

Project Proponent Name- Shri Ankit

Kumar Surya, Add- Shanti Vila, Vidhya

Niketan, Tehsil- Amet, Dist- Rajsamand,

(H.R.) Email- [email protected]

Name of Consultant:- Cognizance Research

India Pvt. Ltd. Add.- GT -20, Sec - 117,

Noida (U.P.) Email.

cognizanceresearchindiapl@gmail. com

23. 19624 E C for Dhuwaliya Granite Mining

Project" M.L. No. 22/2021, Area

1.7215 Ha., Khase No. 1117, 1119,

1335/1119, 1342/1119, Add.-

Dhuwaliya, Tehsil- Kekri, District-

Ajmer, (Raj.) (Proposal No.-

215260)

Name of Proponant :- M/s Shri Shyam

Minerals, Add.- Khasra No. 117, Vill.-

Dhuwaliya, Tehsil- Kekri, Distt.- Ajmer,

(Raj.) (Project Proponent) Shri- Piyush

Kumar S/o Shri Ram Kumar Singh, Add.-

Adarsh Colony, Nawalgarh Road, Sikar,

Distt.- Sikar, (Raj.) Email-

[email protected]

Name of Consultant:- :- Cognizance

Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301

(U.P.) Email:-

[email protected]

24. 19593 Environmental Clearance Golpur

Sand Stone Mining Project, (Plot

No.- 39, Area-1.00 ha. Khasra

No.- 369/5), Near Vill.- Golpur,

Tehsil- Bundi Distt.-Bundi (Raj.)

(Proposal No.-207622)

Project Proponent Name- - M/s Sukesh

Industries Pvt. Ltd., Project In Charge- Shri

Naveen Jain, Add.- R/o--263/05, Pratap

Nagar, Sanganer, Jaipur(Raj.) Email-

[email protected]

Consultant Name:-Cognizance Research

India Private Ltd., Add.-Office GT-20, Sec

177, Noida- 201301 (U.P.)

email:-

[email protected]

25. 19604 E C for Kachariya Granite Mining

Project" M.L. No. 15/2021, Area

Name of Proponant :- Shri- Natvarlal

Sharma S/o Shri- Balkishan Sharma, Add.-

Final minutes of 4.95th meeting held on 27-29 July, 2021

2.9217 Ha., Khase No. 238/99,

Add.- Kachariya, Tehsil-

Kishangarh, District- Ajmer, (Raj.)

(Proposal No.- 214669)

Ward No. 41, Kachariya pith Marg,

Kachariya mandir, Kishangarh, tehsil-

Kishangarh, Distt.- Ajmer, (Raj.)

Email- [email protected]

Name of Consultant:- :- Cognizance

Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301

(U.P.) Email:-

[email protected]

26. 19605 E C for Kachariya Granite Mining

Project" M.L. No. 13/2021, Area

1.6186 Ha., Khase No. 377/244,

Add.- Kachariya, Tehsil-

Kishangarh, District- Ajmer, (Raj.)

(Proposal No.- 214993)

Name of Proponant :- Shri Mohanshyam,

Add.- Ward No. 41, Kachariya pith Marg,

Kachariya mandir, Kishangarh, tehsil-

Kishangarh, Distt.- Ajmer, (Raj.)

Email- [email protected]

Name of Consultant:- :- Cognizance

Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301

(U.P.) Email:-

[email protected]

27. 19609

Environmental Clearance for

Pipliya Granite Mining Project

(R.F.No-20211000031500),Area-

2.2258hact.,khasra No-777/3,768/3,

At Village-Pipliya, Tehsil-

Malpura,District-Tonk,State-

Rajasthan,(Proposal NO-214738)

Name of Proponant :- Shri Rajesh yadav,

Co-Applicant-Shri kamlesh,Add-

Chavandiya, Tonk,Rajasthan,Email-

[email protected]

Name of Consultant:- :- Cognizance

Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301

(U.P.) Email:-

[email protected]

28. 19610 E C for Udaipur Khurd Granite

Mining Project" M.L. No. 09/2021,

Area 1.1057 Ha., Khase No.

Name of Proponant :- M/s Raghupati

Mines & Minerals, Add.- LG-03 Murliwala

Tower Jaipur Road, Tehsil.- Madanganj-

Final minutes of 4.95th meeting held on 27-29 July, 2021

351/224, Add.- Udaipur Khurd,

Tehsil- Kishangarh, District- Ajmer,

(Raj.) (Proposal No.- 213932)

Kishangarh, Distt.- Ajmer, (Raj.) (Project

Pro.) Shri- Satya Narayan Garg S/o Shri-

Kailash Chand Garg, Add.- Plot No. 6,

Jivan-Deep Colony, Madanganj-

Kishangarh, Distt.- Ajmer, (Raj.)

Email- [email protected]

Name of Consultant:- :- Cognizance

Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301

(U.P.) Email:-

[email protected]

29. 19611 E C for Udaipur Khurd Masonary

Stone Mining Project" M.L. No.

22/2020, Area 1.6893 Ha., Khase

No. Not, Add.- Udaipur Khurd,

Tehsil- Kishangarh, District- Ajmer,

(Raj.) (Proposal No.- 211368)

Name of Proponant :- M/s Shree Ji Stonex,

Add.- N.H.8, Veer Taja Market, RAmner

Choraha, Ajmer Bypass, Tehil- Kishangarh,

Distt.- Ajmer, (Raj.) Email-

[email protected]

Name of Consultant:- :- Cognizance

Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301

(U.P.) Email:-

[email protected]

30. 19612 E C for Morajhari Granite Mining

Project" Plot No. 106, Area 1.44

Ha., Khase No. 1473 & 1735,

Add.- Morajhari, Tehsil- Nasirabad,

District- Ajmer, (Raj.) (Proposal

No.- 213570)

Name of Proponant :- Shri- Raghav

Chhaparwal S/o Shri- Shiv Prakash

Chhaparwal, Add.- Morajhari, Tehil-

Nasirabad, Distt.- Ajmer, (Raj.) Email-

[email protected]

Name of Consultant:- :- Cognizance

Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301

(U.P.) Email:-

[email protected]

Final minutes of 4.95th meeting held on 27-29 July, 2021

31. 19613 E C for Morajhari Granite Mining

Project" Plot No. 109, Area 1.32

Ha., Khase No. 1473 & 1735,

Add.- Morajhari, Tehsil- Nasirabad,

District- Ajmer, (Raj.) (Proposal

No.- 213575)

Name of Proponant :- Shri- Raghav

Chhaparwal S/o Shri- Shiv Prakash

Chhaparwal, Add.- Morajhari, Tehil-

Nasirabad, Distt.- Ajmer, (Raj.) Email-

[email protected]

Name of Consultant:- :- Cognizance

Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301

(U.P.) Email:-

[email protected]

32. 19614 E C for Ladera Granite Mining

Project" Ref. No. 2019100002852,

Area 1.0308 Ha., Khase No.

1743/1177 & 1178, Add.- Ladera,

Tehsil- Dudu, District- Jaipur,

(Raj.) (Proposal No.- 208660)

Name of Proponant :- M/s Unique

Granites, Add.- Shah Gokul Chand

Manohar Lal Near Balaji Temple,

Kishangarh, Distt.- Ajmer, (Raj.) Shri-

Abhishek Baheti S/o Shri- Jugal Kishor

Baheti, Add.- Baheti Bhavan, Katla Bazar,

Madangaj, Kishangarh, Distt.- Ajmer, (Raj.)

Email- [email protected]

Name of Consultant:- :- Cognizance

Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301

(U.P.) Email:-

[email protected]

33. 19615 Environmental Clearance for

Amargarh (Chang) Granite Mining

Project, (Plot No.- 48) Area-2.00 ha.

), Near Vill.- Amargarh, Tehsil-

Raipur, Distt.-Pali(Raj.) (Proposal

No.-211255)

Project Proponent Name- - Shri

Pushpendra Singh, Add.- R/o--Behind Shiv

Temple, Jaton Ka Bans, Jasnagar, Tehsil-

Riyanbadi, Distt.- Nagaur (Raj.) Email-

[email protected]

Consultant Name:-Cognizance Research

India Private Ltd., Add.-Office GT-20, Sec

177, Noida- 201301 (U.P.)

email:-

[email protected]

Final minutes of 4.95th meeting held on 27-29 July, 2021

34. 19616 Environmental Clearance of

Rambari Quartz & Feldspar Mining

Project, (ML. No.- 10/2009 Area-

4.00 ha. ), Near Vill.- Rambari,

Tehsil- Nasirbad, Distt.- Ajmer(Raj.)

(Proposal No.-211340)

Project Proponent Name- - Shri Chand

Mohammad, Add.- R/o-- Near Bus Stand,

Vill.- Ramsar, Tehsil- Nasirabad, Distt.-

Ajmer (Raj.) Email-

[email protected]

Consultant Name:-Cognizance Research

India Private Ltd., Add.-Office GT-20, Sec

177, Noida- 201301 (U.P.)

email:-

[email protected]

35. 19625 E C for Granite Mining Project"

Plot No. 108, Area 1.50 Ha., Khase

No. 1473, Add.- Morajhari, Tehsil-

Nasirabad, District- Ajmer, (Raj.)

(Proposal No.- 215442)

Name of Proponant :- Shri- Naresh

Agarwal, Add.- Sadar Bazar, Tantoti,

Distt.- Ajmer, (Raj.) Email-

[email protected]

Name of Consultant:- :- Cognizance

Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301

(U.P.) Email:-

[email protected]

36. 18031 EC of our Proposed “Quartz and

Feldspar Mine (M.L. No. 15/03)

Mining Lease Area 4.0 Hect.

, Khasra No. 8566, Near Vill.–

Devipura, Tehsil- Masuda, Distt.-

Ajmer, (Raj. (Proposal No. 139295)

Name of Proponant :- Shri Akhil

Sharma, Add.- C-53, RIICO Housing

Colony, Ajmer Road, Tehsil - Beawar

Distt.- Ajmer, (Raj.) Email.

[email protected] of Consultant:-

GAURANG ENVIRONMENTAL

SOLUTIONS PVT. LTD. Add.- 102, SNG,

Shri Ratna Apartment, Near Tambi Petrol

Pump, Peetal Factory, Jhotwara Road,

Jaipur, (Rajasthan) Email. –

Final minutes of 4.95th meeting held on 27-29 July, 2021

[email protected]

37. 19626

E C for Granite Mining Project"

Plot No. 107, Area 1.3680 Ha.,

Khase No. 1473 & 1735, Add.-

Morajhari, Tehsil- Nasirabad,

District- Ajmer, (Raj.) (Proposal

No.- 215473)

Name of Proponant :- Shri- Parasmal

Dhabariya, Add.- Sadar Bazar, Tantoti,

Distt.- Ajmer, (Raj.) Email-

[email protected]

Name of Consultant:- :- Cognizance

Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301

(U.P.) Email:-

[email protected]

38. 19627 E C for Granite Mining Project"

M.L. No. 02/2021, Area 1.5968

Ha., Khase No. Not, Add.- Nallu,

Tehsil- Kishangarh, District- Ajmer,

(Raj.) (Proposal No.- 214716)

Name of Proponant :- M/s Stone Tech

Granites, (Project in Charge) Shri- Jayram

Buldak S/o Shri- Mohan Ram, Add.-

Kh.No. 421/2, Khatoli, Tehsil- Kishangarh,

Distt.- Ajmer, (Raj.) Email-

[email protected]

Name of Consultant:- :- Cognizance

Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301

(U.P.) Email:-

[email protected]

39. 19582 Environmental Clearance for Juni

Aati Masonry Stone Mining Project,

Plot No.- 103, Area- 1.00 ha.,

Khasra No.- 579/321 Near Vill.-

Juni Aati, Tehsil & Distt.- Barmer

(Raj).(Proposal No.-214172)

Project Proponent Name- - M/s Tan

Singh Chouhan, Add.- R/o- Gandhi

Nagar,Tehsil & Distt.- Barmer (Raj.) Email-

[email protected]

Consultant Name:-M/s. N.S. Enviro-Tech

Laboratories & Consultant, Add.- Plot No.-

51, Ganeta House, Shiv Vihar Colony, Near

Patrakar Colony Road Mansarover- Jaipur-

(Raj.)

Email- [email protected]

40. 19583 Environmental Clearance for

Sodhon ki Dhani Masonry Stone

Mining Project Ref. No.-

20201000022559, Near Vill.-

Project Proponent Name- - M/s Tan

Singh Chouhan, Add.- R/o- Gandhi

Nagar,Tehsil & Distt.- Barmer (Raj.) Email-

[email protected]

Final minutes of 4.95th meeting held on 27-29 July, 2021

Sodhon Ki Dhani, Tehsil & Distt.-

Barmer (Raj.)Area- 2.00 ha.,

Khasara No.- 947/95, Near Vill.-

Juni Aanti Tehsil& Distt.- Barmer

(Raj.)(Proposal No.-214348)

Consultant Name:-M/s. N.S. Enviro-Tech

Laboratories & Consultant, Add.- Plot No.-

51, Ganeta House, Shiv Vihar Colony, Near

Patrakar Colony Road Mansarover- Jaipur-

(Raj.)

Email- [email protected]

41. 19586 Environmental Clearance for Bapcha

Masonry Stone Mine Ref. No.-

20191000014037, Proposed

Production- 200000 TPA (ROM)of

Masonry Stone Mine Applied area-

1.1612 ha., Khasra No.- 444 & 445,

Near Vill.- Bapcha, Tehsil- Chhabra,

Distt.- Baran(Raj).(Proposal No.-

207963)

Project Proponent Name- - Smt. Anita

Bagdi W/o Sh. Satyendra Maheshwari,

Add.- R/o- A-9-10, Shastri Nagar, Ward

No.-02, Hill View Colony, Chhabra, Distt.-

Baran (Raj.) Email-

[email protected]

Consultant Name:-M/s. N.S. Enviro-Tech

Laboratories & Consultant, Add.- Plot No.-

51, Ganeta House, Shiv Vihar Colony, Near

Patrakar Colony Road Mansarover- Jaipur-

(Raj.)

Email- [email protected]

42. 19587 Environmental Clearance for

Ganerav Granite Mining Project,

Ref. No.- 20191000010415,

Proposed Production- 65850 TPA

(ROM)of Mineral Granite , Khasra

No.- 4296/196, Near Vill.- Ganerav,

Tehsil- Desuri, Distt.- Pali

(Raj).(Proposal No.-209034)

Project Proponent Name- - Shri Chandra

Prakash Salvi, Add.- R/o- Salviyon Ka

Mohlla, Biyanan Post Tikad, Tehsil-

Devgarh, Distt.- Pali (Raj.) Email-

[email protected]

Consultant Name:-M/s. N.S. Enviro-Tech

Laboratories & Consultant, Add.- Plot No.-

51, Ganeta House, Shiv Vihar Colony, Near

Patrakar Colony Road Mansarover- Jaipur-

(Raj.)

Email- [email protected]

43. 19588 Environmental Clearance for Juni

Aati Masonry Stone Mining Project,

Plot No.- 98, Area- 1.00 ha., Khasra

No.- 579/321 Near Vill.- Juni Aati,

Tehsil & Distt.- Barmer

(Raj).(Proposal No.-213961)

Project Proponent Name- - M/s Tan

Singh Chouhan, Add.- R/o- Gandhi

Nagar,Tehsil & Distt.- Barmer (Raj.) Email-

[email protected]

Consultant Name:-M/s. N.S. Enviro-Tech

Laboratories & Consultant, Add.- Plot No.-

51, Ganeta House, Shiv Vihar Colony, Near

Patrakar Colony Road Mansarover- Jaipur-

Final minutes of 4.95th meeting held on 27-29 July, 2021

(Raj.)

Email- [email protected]

44. 19601 E C of Ghatiyali Granite Mining

Project Ref. No. 20201000026666,

Area 1.0198 Ha., Khase No.

1072/854, Production Capacity -

1,01,002, TPA (RoM), Mineral

Granite, Add.- Ghatiyali, Tehsil-

Phagi, District- Jaipur, (Raj.)

(Proposal No.- 209139)

Name of Proponant :- Shri- Prakash

Ranwa S/o Shri- Rameshwar Lal, Add.-

Ranwa House, Choudhary Charan Singh

Nagar, Navalgarh Road, Ward No. 41,

Distt- Sikar, (Raj.) (Co-Applicant), Shri-

Rameshwar Lal Choudhary S/o Shri- Tulsi

Ram Choudhary, Add.- Sikar Marg, Kadva

Complex Kuchaman City, Nagaur, Distt.-

Nagaur, (Raj.) Email-

[email protected]

Name of Consultant:- M/s. N.S. Envro-

Tech Laboratories & Consultant, , Add-

Plot No. 51, Ganeta House, Shiv Vihar

Colony, Near Patrakar Colony Road,

Mansarovar, Jaipur (Raj.).

Email:- [email protected]

45. 19617 Environmental Clearance of our

Bambuliya Ghata Masonry Stone

Mine Ref. No.- 20191000014359,

M.L. No.- 04/2019, Area- 1.00 ha.,

Khasara No.- 947/95, Near Vill.-

Bambuliya Ghata, Tehsil- Pipalda

Distt.- Kota (Raj.) in favor of Shri

Bijendra Verma (Raj.)(Proposal

No.-209141)

Project Proponent Name- - Shri

Bijendra Verma , Add.- R/o- Vill.- Jhirwali

Ka Bas, Post- Karoth, Tehsil- Rajgarh,

Distt.- Alwar (Raj.) Email-

[email protected]

Consultant Name:-M/s. N.S. Enviro-Tech

Laboratories & Consultant, Add.- Plot No.-

51, Ganeta House, Shiv Vihar Colony, Near

Patrakar Colony Road Mansarover- Jaipur-

(Raj.)

Email- [email protected]

46. 19620 E C of Proposed Project of Masonry

Stone Mining Plot. No. 176/1996,

Area 1.00 Ha., Khase No. 336,

Add.- Bhopas Dungri, Tehsil-

Name of Proponant :- Shri- Mahendra

Kumar Saini S/o Shri- Rajendra Kumar

Saini, Add.- K-25, Bhawani Nagar,

Murlipura, Jaipur, Distt.- Jaipur, (Raj.)

Final minutes of 4.95th meeting held on 27-29 July, 2021

Chomu, District- Jaipur, (Raj.) By

Shri- Mahendra Kumar Saini S/o

Shri- Rajendra Kumar Saini, Cat. B-

2, (Proposal No.- 215830)

Email- [email protected]

Name of Consultant:- M/s. N.S. Envro-

Tech Laboratories & Consultant, , Add-

Plot No. 51, Ganeta House, Shiv Vihar

Colony, Near Patrakar Colony Road,

Mansarovar, Jaipur (Raj.).

Email:- [email protected]

47. 19621 E C of Proposed Project of Masonry

Stone Mining Plot. No. 16/2020,

Area 1.6997 Ha., Khase No. 410,

Add.- Gunawata, Tehsil- Amer,

District- Jaipur, (Raj.) By Shri-

Ramesh Chand Gupta S/o Shri-

Gyarsi Lal Gupta, Cat. B-2,

(Proposal No.- 215850)

Name of Proponant :- Shri- Ramesh

Chand Gupta S/o Shri- Gyarsi Lal Gupta,

Add.- 11-Moji Colony, Malviyanagar,

Distt.- Jaipur, (Raj.) Email-

[email protected]

Name of Consultant:- M/s. N.S. Envro-

Tech Laboratories & Consultant, , Add-

Plot No. 51, Ganeta House, Shiv Vihar

Colony, Near Patrakar Colony Road,

Mansarovar, Jaipur (Raj.).

Email:- [email protected]

48. 19595 Environmental Clearance for

Masonry Stone (Minor Mineral)

Mining Project, (ML. No.- 86/2010

Area-1.00 ha. Khasra No.-295 ),

Production Capacity- 55000 TPA

(ROM) {Salable Mineral- 49500

TPA, Waste- 5500 TPA }Near

Vill.- Bhedoli, Tehsil- Bonli, Distt.-

Sawai Madhopur (Raj.)by M/s

Aditya Minerals (Raj.)(Proposal

No.-212036)

Project Proponent Name- - M/s Aditya

Minerals, Add.- R/o-- Jai Mandir Ke Pass,

Jhilai Road, Niwai, Distt.- Tonk (Raj.)

Email- [email protected]

Consultant Name:-:-VARDAN

ENVIRONET

Add: Plot No.-82-A, Sector- 5, IMT

Manesar, Gurgaon-122003 (Haryana).

email:- [email protected]

49. 19596 Environmental Clearance for Quartz

& Feldspar (Minor Mineral) Mining

Project Proponent Name- - M/s Jai

Shree Ganga Mines, Add.- R/o-Ward No.-

Final minutes of 4.95th meeting held on 27-29 July, 2021

Project, (ML. No.- 110/2012 Area-

4.5007 ha. Khasra No.- 1793,

3168/1794, 3157/1794, 1795, 1791),

Production Capacity- 179494 TPA

(ROM) {Salable 125646 TPA, Sub

grade- 26924 TPA & Waste- 26924

TPA }Near Vill.- Khemana, Tehsil-

Raipur, Distt.- Bhilwara, (Raj.)by

M/s Jai Shree Ganga Mines

(Raj.)(Proposal No.-212082)

5, Main Road, Gangapur, Tehsil- Sahada,

Distt.- Bhilwara (Raj.) Email-

[email protected]

Consultant Name:-VARDAN

ENVIRONET

Add: Plot No.-82-A, Sector- 5, IMT

Manesar, Gurgaon-122003 (Haryana).

email:- [email protected]

50. 19598 Environmental Clearance for

Marble Mineral Mining Project, Plot

No.- 5, Proposed Production

Capacity- 348106 TPA (ROM)

{Salable Mineral Marble- 131021

TPA, Waste- 191367 TPA & OB-

25718 T}Area- 4.0 ha., Khasra no.-

1536, Near Vill.- Lohagarh, Tehsil-

Dhariyawad, Distt.- Pratapgarh

(Raj.)by M/s Paramount Mines &

Minerals (Raj.)(Proposal No.-

210560)

Project Proponent Name- - M/s

Paramount Mines & Minerals Pro. Shri

Mahesh Agarwal , Add.- R/o- B-106, 10-B,

Scheme Gopalpura Bypass Jaipur, (Raj.)

Email- [email protected]

Consultant Name:-VARDAN

ENVIRONET

Add: Plot No.-82-A, Sector- 5, IMT

Manesar, Gurgaon-122003 (Haryana).

email:- [email protected]

51. 19599 Environmental Clearance for

Marble Mineral Mining Project, Plot

No.- 6, Production Capacity-

309529 TPA (ROM) {Salable

Mineral Marble- 125234 TPA,

Waste- 158577 TPA & OB- 25718

T}Area- 4.0 ha., Khasra no.- 1536,

Near Vill.- Lohagarh, Tehsil-

Dhariyawad, Distt.- Pratapgarh

(Raj.)by M/s Paramount Mines &

Minerals (Raj.)(Proposal No.-

210620)

Project Proponent Name- - M/s

Paramount Mines & Minerals Pro. Shri

Mahesh Agarwal , Add.- R/o- B-106, 10-B,

Scheme Gopalpura Bypass Jaipur, (Raj.)

Email- [email protected]

Consultant Name:-VARDAN

ENVIRONET

Add: Plot No.-82-A, Sector- 5, IMT

Manesar, Gurgaon-122003 (Haryana).

email:- [email protected]

Final minutes of 4.95th meeting held on 27-29 July, 2021

52. 19628 Transfer of E C under clause 11 of

EIA notification issued for Marble

Mining Lease, M.L. No. 07/1961,

81/1991, 22/2000, (R), Area 1.3935

Ha., Khase No. 977, Add.-

Bhaislana, Tehsil- Kotputli,

District- Jaipur, (Raj.), (Proposal

No.- 186593)

Name of Proponant :- Dr. Rashmi Patni,

Add.- 5, Jha 30, Jawahar Nagar, Jaipur,

Distt.- Jaipur, (Raj.) Email-

[email protected]

Name of Consultant:- MANTRAS

GREEN RESOURCES LTD

Hall No.- 1 NICE Sankul Plot No.- A-9,

Opp. Nasik Marchant Co Op Bank Ltd, ITI

Signal, MIDCSatpur, Nasik).

email:- [email protected]

53. 19629 Transfer of E C under clause 11 of

EIA notification issued for Masonry

Stone Mining Lease, M.L. No.

471/06, Area 1.0 Ha., Khase No.

376/1/1, 373/1, Add.- Kundala Ki

Dhani, Tehsil- Neem Ka Thana,

District- Sikar, (Raj.), (Proposal

No.- 180508)

Name of Proponant :- M/s Shri- Balaji

Stone Crusher, Add.- 9, Leela Mention,

Raj Bhawan Road, Civil Lines, Jaipur,

Distt.- Jaipur, (Raj.) Email-

[email protected]

Name of Consultant:- MANTRAS

GREEN RESOURCES LTD

Hall No.- 1 NICE Sankul Plot No.- A-9,

Opp. Nasik Marchant Co Op Bank Ltd, ITI

Signal, MIDCSatpur, Nasik).

email:- [email protected]

54. 18073 Environmental Clearance for

“Marble Mineral Mining Project,

Q.L. No.-96/A, Production

Capacity- 2200 TPA, Area-0.0574

ha, Khasra No.- 702, Near Village-

Ullodi Range, Tehsil- Makrana,

Distt.- Nagaur, (Raj.)M/s Mainudeen

and Brothers Makrana.(Proposal

No.-141385)

Name of Proponent: - M/s Mainudeen and

Brothers Makrana, Add.- Village- Makrana,

Tehsil- Makrana, Distt.- Nagaur,

(Raj.)Email –

[email protected] Name of

Consultant: -M/s. N.S. Envro- Tech

Laboratories & Consultant, Add.- Corpo

OFFICE Add Plot No. 69/318, V.T. Road

Chouraha, Madhyam Marg, Mansarovar,

Jaipur (Raj.). Email:-

[email protected],

[email protected]

Final minutes of 4.95th meeting held on 27-29 July, 2021

After examining the documents, information provided and deliberations, the committee

decided to

1. Recommend to SEIAA for grant of EC to proposals listed at serial no. 4, 6, 7, 8, 12,

13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 28, 29, 30, 31, 34, 35, 37, 38, 39,

40, 43, 44, 46, 47, 49, 50, 51, 54, ad1, ad2, ad3, ad4, ad5, ad6, ad7 with appropriate

conditions as recommended in the detailed minutes of the respective agenda items.

2. Recommend to SEIAA to close & delist the proposals listed at serial no. NIL.

3. Recommend to SEIAA for amendment in EC/ToR granted/change in name for

proposals listed at serial no. NIL with appropriate conditions as recommended in the

detailed minutes of the respective agenda items.

4. Recommend to SEIAA for grant of ToR to the proposals listed at serial no. 36 as

recommended in the detailed minutes of the respective agenda items.

5. Defer the proposals listed at Serial no. 1, 2, 3, 5, 9, 10, 11, 32, 42, 53, to be consider

in subsequently proposed meetings after receipt of the request from Project Proponent

/Consultant

6. Issue query/seek additional information with respect to the proposals listed at serial

no. 27, 33, 41, 45, 48, to be reexamined in the forthcoming meetings of the SEAC

upon receipt of the reply from PP/consultant.

7. Issue the warning letter to Project Proponent/ Consultant of the proposals listed at

Serial no. NIL .

8. Issue the ToR letter to Project Proponent/ Consultant of the proposals listed at Serial

no. NIL.

The detailed minutes with respect to the agenda items are as annexed. The meeting ended

with thanks to the Chair.

S. No. Name Designation

1 Manoj Kumar Agrawal Chairman

2 Suja George Vice Chairman

3 Pushakar Singh Shekhawat Member

4 Mukesh Behari Sharma Member

5 Laxmi Kant Dashora Member

6 Buddhi Prakash Pareek Member

7 Vikram Singh Chauhan Member

8 Nand Kumar Khare Co-opted Member

9 Rajneesh Jain Member Secretary

Final minutes of 4.95th meeting held on 27-29 July, 2021

Final minutes of 4.95th meeting held on 27-29 July, 2021

Agenda no. 01. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(15817)/ 2019-20

Project Name- Final EIA EMP Report for Environmental Clearance of limestone (Minor

Mineral ) Production Capacity From 14,600 TPA to 15,00,000 TPA (Lime stone burning )

M.L no-122/91, Area-100.00Ha., By M/s Nitesh mineral Pvt. Ltd location at village

Hariyadhana, Tehsil- bilara, dist- Jodhpur(Raj.) (Proposal no-30615).

Project Proponent Name- M/S. Nitesh Minerals Pvt. Ltd, Add-Old public park Road, near

K.N.collage, Rai ka Bagh Jodhpur (Rajasthan), [email protected],

,[email protected].

Consultant Name- Udaipur Min-Tech PVT.LTD., Add-206, Apeksha Complex.Sec-

11.Hiran Magri, Udaipur (Raj), [email protected].

Observations and Resolution of the committee:-

The PP vide letter dated 27.07.2021 has submitted an application for deferment of the

case. The SEAC agreed to the request of the PP and deferred the matter. The project shall be

taken up again on receipt of his request for consideration of the project by the PP, in the

subsequent proposed meeting.

Agenda no. 02. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B1(264)/ 2019-20

Project Name- Final EIA EMP Report for EC of Chechat Limestone Building Stone mine

over an area of :24.2350 Ha, ML NO-24/93 Production Capacity from 40305 TPA to

300000 TPA. Near Village- Chechat, Tehail- Ramganjmandi, District- Kota, Rajasthan in

favor of M/S Shiva Stone.(Proposal No-60416)

Project Proponent Name- M/S SHIVA STONE ,In Front of RSEB, Near Hotel

Indraprastha, NH-12,JhalawarRajasthan,[email protected].

Consultant Name- EIA CONSULTANT, M/s UDAIPUR MINE-TECH PVT. LTD.

206,APEKSHA COMPLEX. SEC-11.,HIRAN MAGRI, UDAIPUR,(RAJ) Email:-

[email protected]

Observations and Resolution of the committee:-

The PP vide letter dated 27.07.2021 has submitted an application for deferment of the

case. The SEAC agreed to the request of the PP and deferred the matter. The project shall be

taken up again on receipt of his request for consideration of the project by the PP, in the

subsequent proposed meeting.

Agenda no. 03. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B1(16951)/ 2019-20

Project Name- Final EIA EMP Report for Environmental Clearance of “Limestone

(Dimensional) & Masonry Stone (Kali Chat), Ref. No. 2019100004792, Area 4.00

ha.(cluster area 48.00 Ha), Production capacity - 404736 TPA Near Village Pipliya

(Runji),Tehsil Pachpahar, District Jhalawar, (Raj). Khasra No. 653, 284, 287, 289, 290, 291,

292, (Proposal No. 62668)

Final minutes of 4.95th meeting held on 27-29 July, 2021

Project Proponent Name Shri Pukhraj Jain,Add- “Miraya Mension”Opposite RSEB, Near

Indraprasth Hotel, Tehsil Jhalrapatan, District Jhalawar, (Raj.).Email – [email protected]

Consultant Name- M/s Udaipur Min- Tech Pvt. Ltd.206, Apeksha Complex. Sec-11. Hiran

Magri, Udaipur, (Raj.).email:[email protected],

Observations and Resolution of the committee:-

The PP vide letter dated 27.07.2021 has submitted an application for deferment of the

case. The SEAC agreed to the request of the PP and deferred the matter. The project shall be

taken up again on receipt of his request for consideration of the project by the PP, in the

subsequent proposed meeting.

Agenda no. 04. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19623)/ 2019-20

Project Name- EC for Golpur Sandstone Mining Project, Plot No. 32, Area 1.00 Ha.,

production capacity- 73,114.3 TPA (ROM), Khasra No. 369/5, Add.- Golpur, Tehsil- Bundi,

District- Bundi, (Raj.) (Proposal No.- 216092).

Project Proponent Name- Shri- Preetam Singh Bhadoriya S/o Shri- Harendra Singh

Bhadoriya, Add.- Behind Star Public School, Govind Nagar Road, Prem Nagar 1, Kota,

District- Kota, (Raj.), Email- [email protected].

Consultant Name- P AND M SOLUTION, Add.- Shivani mines & Minerals, B-39, RIICO,

Housing Colony, Beawar, Distt.- Ajmer (Raj.) Email.- [email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category / Item no.(in

Schedule):

1(a) B2

2. Location of Project Village - Golpur , Tehsil- Bundi , District - Bundi (Raj.

Pillar Latitude Longitude

A 25° 16’ 01.81950'' 75° 27' 14.20923”

B 25° 15’ 58.56989'' 75° 27' 14.19715”

C 25° 15’ 58.58086'' 75° 27' 10.62346”

D 25° 16’ 01.83048'' 75° 27' 10.63552”

3. Project Details

Plot No. /Production

capacity

Plot No.- 32

Area - 1.00Hect

Khasra No.- 369/5

Production (TPA) - 73114.3 TPA (ROM)

4. Project Cost: Rs. 0.50 Cr./-

5. Water Requirement

& Source

Total water requirement is about 4.0 KLD = 1.0 KLD (Drinking

& Domestic Uses) + 1.0 KLD (Plantation + 1.0 KLD Dust

Suppression) + 1.0 (Wet Drilling). Water for Drinking, dust

Final minutes of 4.95th meeting held on 27-29 July, 2021

suppression and plantation will be collected from nearby villages

by water tanker & PHED

6. Fuel & Energy:- Only diesel will be required to run vehicles for transportation.

7. Application No. & Date

& documents submitted :-

Proposal No.: SIA/RJ/MIN/216092/2021

Online Application Date: 22 Jun 2021

SEAC File No.: 19623

8. Information about

Aravalli Certificate.

This ML area does not fall in Aravalli ranges. Aravalli Certificate was

issued by Mining Engineer, Bundi vide letter no.

ME/Bundi/Map/2021/290 Dated 03/03/2021.

(Aravalli Certificate is enclosed with this proposal)

9. Date of Air/Water/Noise

Monitoring

Date of Monitoring

Monitoring Reports are enclosed with this proposal.

10. Information about 500

mts composite map

500 mts composite map with Cluster Certificate is enclosed with this

proposal which was issued by Mining Engineer, Bundi. Composite map

issued vide letter no. ME/Bundi/Map/2021/291 Dated 03/03/2021 &

Cluster certificate issued vide letter no ME/Bundi/Map/2021/291 Dated

03/03/2021. Area falling within 500 mts 1.58559 ha. excluding this mine

area.

(500m composite map & cluster certificate are enclosed with this

proposal).

11. Environment

Management Plan

Expenditure of EMP Rs 2,50,000/-

S.

No. Measures

Expenditure Cost

in Rs. (Fixed)

Expenditure Cost

in Rs. (Recurring)

(Per Year)

1

Pollution Control

i) Dust

Suppression &

Wet Drilling &

Others

30,000/- 80,000/-

Final minutes of 4.95th meeting held on 27-29 July, 2021

2

Pollution

Monitoring

i) Air pollution

ii)Water pollution

-- 20,000/-

3 Green Belt 1,00,000/- 1,50,000/-

Total 1,30,000/- 2,50,000/-

12. CSR /ESR Activates As Per MoEF OM F. No. 22-65/2017-IA.III Dated 30.09.2020, CER

activity will be part of Environment Management plan instead of

allocation of funds under CER.

13. Green Belt/ Plantation Expenditure of Green Belt Rs 1,50,000/-

Total green belt will be the 33% of the ML area 0.33 ha of the area will be

planted in khasra no 369/5 land provided by gram Panchayat Golpur. Total

330 trees will be planted over an area of 0.33 ha in Charagah land allotted

by gram panchayat. It is proposed to invest 1.50 Lac Rs. Per Annum for

Green Belt Development.

Plan for Afforestation

Year Saplings Species

Place of Plantation

Existing - Neem, Babool,

Pipal, Kair,

Sheesham,

Gulmohar etc. etc.

Charagah land near lease

area gram Golpur, Tehsil

& Dist. Bundi

I Year

110

II Year

110

III Year

110

Total

(As per the MoEF & CC Office Memorandum Dated 16th January, 2020

“The mining lease holders Shall after ceasing mining Operations,

undertake re-grassing the mining area and any other area which may have

been disturbed due to their mining activities and restore the land to a

condition which is fit for growth of fodder, flora, fauna etc.

The lessee shall comply all conditions as per Office Memorandum

16/1/2020.)

14. Budgetary Breakup for

Labour

Expenditure of Labour Rs 50,000/-

Sl.

No. Scheme

Expenditure

Cost in Rs.

(Fixed)

Expenditure

Cost in Rs.

(Recurring)

(Per Year)

Final minutes of 4.95th meeting held on 27-29 July, 2021

1 Drinking water facility 5,000/- 10,000/-

2

Health Facility (First aid

box, Rest shelter,

Medicine & Washroom)

& Insurance

5,000/- 10,000/-

3 Education for children

etc. 5,000/- 10,000/-

4

Safety equipment like

Ear plug, Dust mask,

hand gloves, Safety

Shoes etc.

10,000/- 20,000/-

Total 25,000/- 50,000/-

15. Present Status :- LOI Granted (This is a fresh applied ML area. Mining Operations will be

started after Environment Clearance & Consent to operate)

Observations of the committee:-

The SEAC considered/examined the project proposal on 27.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for EC for Golpur Sandstone Mining Project, Plot

No. 32, Area 1.00 Ha., production capacity- 73,114.3 TPA (ROM), Khasra No. 369/5, Add.-

Golpur, Tehsil- Bundi, District- Bundi, (Raj.) (Proposal No.- 216092). The project is

covered under B2 category. The SME, Kota vide order dated 16.12.2020 has issued LoI to the

PP for mining of Sandstone. The mining plan has been approved by the SME, Kota vide letter

dated 16.04.2021. ME, Bundi in his certificate dated 03.03.2021 has stated that the mining

lease does not fall in Aravalli hills. DCF, MNP, Kota in his letter dated 24.02.2021 has stated

that the MHTR is at a distance of 26.11 Km from applied lease. DCF, WL, Kota in his letter

dated 16.06.2021 has advised that PP could find out the distance of Ramgarh Vishdhari WLS

from KML file at his level. PP has mentioned in Form-1 that Ramgarh Vishdhari WLS is at a

distance of 25.61 Km from the applied lease area and this distance was found by the SEAC to

be correct from KML file as shown during presentation. The project does not involve

approval/ clearance under the Forest (Conservation) Act, 1980 and Wild Life Protection Act,

1972 as no forest land is involved and neither there is any Wild Life Sanctuary/ National Park

within 10 Km from the project site.

The SEAC considered the certificate dated 03.03.2021 issued by ME, Bundi. In the

certificate, it is stated that as per the MoEF & CC notification, dated 01.07.2016 there is no

other mining lease within the periphery of 500 meter and therefore, there is no cluster

formation.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1,Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri Preetam

Singh Bhadoriya S/o Shri- Harendra Singh Bhadoriya, for Golpur Sandstone Mining Project

Final minutes of 4.95th meeting held on 27-29 July, 2021

Plot No. 32, Area 1.00 Ha., production capacity- 73,114.3 TPA (ROM), Khasra No. 369/5,

Add.- Golpur, Tehsil- Bundi, District- Bundi, (Raj.) (Proposal No.- 216092), with the

stipulation that the PP shall abide by the annual production scheduled specified in mining

plan and that any deviation there in will render the PP liable for legal action in accordance

with Environment and Mining Laws, with the specific and general conditions annexed at

Annexure ‘A’. Name of Proponent: Shri- Preetam Singh Bhadoriya S/o Shri- Harendra

Singh Bhadoriya, Add.- Behind Star Public School, Govind Nagar Road, Prem Nagar 1,

Kota, District- Kota, (Raj.), Email- [email protected], Consultant Name:- P AND

M SOLUTION, Add.- Shivani mines & Minerals, B-39, RIICO, Housing Colony, Beawar,

Distt.- Ajmer (Raj.), Email.- [email protected].

Agenda no. 05. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19631)/ 2019-20

Project Name- EC for Khananiya Khera Quartz & Feldspar Mine M.L. No. 81/2002, Area

5.00 Ha., Khasra No. 522, 530, 531, 529, 528, 527, 534,535,541, 538, 540, 539, 536,

Production capacity: 1,12,398 TPA (ROM) {Saleable minerals: 67,438 TPA,

Subgrade:11,240 TPA, Waste: 33,720 TPA}, Add.- Khananiya Khera, Tehsil- Raipur,

District- Bhilwara, (Raj.) (Proposal No.- 208561).

Project Proponent Name Mr. Shabbur Ahmad S/o Mr. Fakhruddin Sheikh, Add.- Regaron

Ki Kui, Tehsil- Asind, District- Bhilwara, (Raj.) Email-

[email protected]

Consultant Name- P AND M SOLUTION, Add.- Shivani mines & Minerals, B-39, RIICO,

Housing Colony, Beawar, Distt.- Ajmer (Raj.), Email.- [email protected]

Observations and Resolution of the committee:-

The PP vide letter dated 27.07.2021 has submitted an application for deferment of the

case. The SEAC agreed to the request of the PP and deferred the matter. The project shall be

taken up again on receipt of his request for consideration of the project by the PP, in the

subsequent proposed meeting.

Agenda no. 06. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19602)/ 2019-20

Project Name- EC for Masonry Stone Mining Project, Plot No. 3, Area 1.00 Ha.,

Production Capacity- 1,00,000 TPA (ROM), Khasra No. 957, 340, Add.- Ramgarh Padli bad,

Tehsil- Sikrai, District- Dausa, (Raj.) (Proposal No.- 208038).

Project Proponent Name- Shri- Ramavtar Sharma S/o Shri- Kundan Ram Sharma, Add.-

191/27, Sector-19, Pratap Nagar, Sanganer, Jaipur, Distt.- Jaipur, (Raj.), Email-

[email protected].

Consultant Name- Globus Environment Services, Add.- 326-AB, 3rd Floor, Sahara

Shopping Center, Lekhraj Crossing, Faizabad Road, Lucknow (U.P.) Email. –

[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category/Item No. (In Schedule) 1(a) B2

Final minutes of 4.95th meeting held on 27-29 July, 2021

2. Location of Project Near village – Ramgarh, Padlibad, Tehsil - Sikrai,

District-Dausa (Rajasthan)

3. Project Details Plot No. – 3,

Area – 1.00Ha.

Khasra No. 957, 340

Production in TPA – Masonry Stone @ 100000 TPA

4. Project Cost Rs. 25 Lakh.

5. Water Requirement & Source 5.0KLD (Tanker supply from near village Ramgarh)

6. Fuel & Energy 300 Liter/day Fuel will be required for mining.

7. Application No. & Date &

Documents Submitted

Application No. : 19602

Online Submission Date:-06.04.2021

8. Information about Aravalli

Certificate

Aravalli certificate issued, vide letter no. AME/DAUSA/

Minor/Plot/02/2019/62 dated 30.03.2021.

9. Date of

Air/Water/Noise/Monitoring

Air/Water/Noise/Soil monitoring has been carried out on

17/06/2021.

10. Information about 500mts

Composite Map

Letter No. - AME/DAUSA/ Minor/Plot/02/2019/63 dated

30.03.2021.

11. Environment Management Plan Total Annual expenditure of EMP is Rs. 1,80,000/- per

year. Details are follow:

S.No Description of Item Amount (in Rs/yr.)

1. Annual Monitoring 1,00,000/-

2. Green Belt development 30,000/-

3. Water Sprinkling on haul roads

50,000/-

Total 1,80,000/-

12. CSR/ESR Activities

Total Annual expenditure of CSR/ESR is Rs. 50,000/- per year. Details are follow:

Year Name of Location Head Quantity Cost

I Year Govt. School,

Padlibad, Ramgarh,

Tehsil - Sikrai, District-Dausa,

Rajasthan

Water Cooler & Synthetic Tank &

AMC

Renovation & Repairing Work Furniture as Chairs & Tables

1

- 5+5

20,000/-

15,000/- 15,000/-

II Year LED Bulb/Tube light + Fan

Library Books, Sports kit & accessories as Football, Cricket,

Basket Ball etc.

10+10

-

20,000/-

30,000/-

III Year Computer with Printer, Almari (Steel) 1+1 50,000/-

IV Year Gram Panchayat of

Village - Padlibad, Ramgarh, Tehsil -

Sikrai, District-

Dausa, Rajasthan

Construction and maintenance of

village roads adjacent to project site

- 50,000/-

V Year Periodically medical checkup camps, blood donation camps. Eye checkup

camps

Health awareness camps for child and mother care, health and hygiene

practices

- -

20,000/- 20,000/-

10,000/-

The PP shall expenditure Rs. 50,000/- per year for CER. The above expenditure is for 5 years,

the onwards the PP shall be expend the amount of CER as per need of local stack holders/Govt.

Final minutes of 4.95th meeting held on 27-29 July, 2021

School/Hospitals & Gram Panchyat etc.

13. Green

Belt/Plantation

Year Un-worked

Area

Govt. Girls

High

Secondary

School,

Kalwan

Backfilled

(Reclaimed

Area)

Top soil

Dumps

Total

Area

(Ha.)

No. of

Plants

Area

(Ha.)

No. of

Plants

Area

(Ha.)

No. of

Plants

Area

(Ha.)

No. of

Plants

Area

(Ha.)

No. of

Plants

Existing - - - - - - - - - -

1st 0.10 100 0.015 15 0.115 115

2nd 0.10 100 0.015 15 0.115 115

3rd 0.085 85 0.015 15 0.100 100

4th Maintenance

5th Maintenance

Total 0.285 285 0.045 45 0.330 330

Note: As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after

ceasing mining operations, undertake re-grassing the mining area and any other

area which may have been disturbed due to their mining activities and restore

the land to a condition which is fit for growth of fodder, flora, fauna etc.

Note: - At the end of third year Green Belt/Plantation will be done in 0.330 ha.

area i.e. (330 trees) (0.285 ha + 0.045 ha.) out of which 0.285 ha.(285 Plants) area will be covered under green belt on around the mine periphery & remaining i.e.

0.045 ha. (45 Plants) Plantation will be done outside the lease area in village

Kalwan in Govt. Girls High Secondary School. Native species which are more suitable to the local environment are preferred to be

planted such as like Neem (Azadiracta indica), Pipal (Ficus religiosa), Babool

(Acacia nilotica), Kher (Acacia catechu) etc.

Source-Approved Mining Plan with Progressive Mine closure plan

Final minutes of 4.95th meeting held on 27-29 July, 2021

14. Budgetary Breakup for Labour

Total Annual expenditure for labours is Rs. 60,000/- per year. Details are follow:

Sr. No. Description Amount (in Rs./yr.)

1 Rest Shelter 10,000

2 Drinking water facility 10,000

3 Bio-Toilet Facility 30,000

5 Medical facility for labors 10,000

Total 60,000

15. Present Status This is Fresh mining lease of mineral Masonry Stone,

located near village - Ramgarh, Padlibad, Tehsil - Sikrai,

District-Dausa, Rajasthan

Observations of the committee:-

The SEAC considered/examined the project proposal on 27.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for EC for Masonry Stone Mining Project, Plot

No. 3, Area 1.00 Ha., Production Capacity- 1,00,000 TPA (ROM), Khasra No. 957, 340,

Add.- Ramgarh Padli bad, Tehsil- Sikrai, District- Dausa, (Raj.) (Proposal No.- 208038).

The project is covered under B2 category. The SME, Jaipur vide order dated 05.08.2020 has

issued LoI to the PP for mining of Masonry Stone. The mining plan has been approved by the

SME, Jaipur vide letter dated 30.03.2021. AME, Dausa in his certificate dated 30.03.2021 has

stated that the mining lease does not fall in Aravalli hills. DCF, Dausa in his certificate dated

26.07.2021 has stated that there is no Wildlife Sanctuary/National Park/ Conservation

Reserve within 10 km periphery of the mine. The project does not involve approval/

clearance under the Forest (Conservation) Act, 1980 and Wild Life Protection Act, 1972 as

no forest land is involved and neither there is any Wild Life Sanctuary/ National Park within

10 Km from the project site.

As per cluster certificate issued by AME, Dausa on 30.03.2021, the total area of all the

mining leases in the cluster having area of 3.3774 ha.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1,Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation resolved to recommend to SEIAA for grant of EC to Shri-

Ramavtar Sharma S/o Shri- Kundan Ram Sharma, for Masonry Stone Mining Project, Plot

No. 3, Area 1.00 Ha., Production Capacity- 1,00,000 TPA (ROM), Khasra No. 957, 340,

Add.- Ramgarh Padli bad, Tehsil- Sikrai, District- Dausa, (Raj.) (Proposal No.- 208038),

with the stipulation that the PP shall abide by the annual production scheduled specified in

mining plan and that any deviation there in will render the PP liable for legal action in

accordance with Environment and Mining Laws, with the specific and general conditions

annexed at Annexure ‘A’. Name of Proponent Shri- Ramavtar Sharma S/o Shri- Kundan

Ram Sharma, Add.- 191/27, Sector-19, Pratap Nagar, Sanganer, Jaipur, Distt.- Jaipur,

Final minutes of 4.95th meeting held on 27-29 July, 2021

(Raj.), Email- [email protected], Consultant Name:- Globus Environment

Services, Add.- 326-AB, 3rd Floor, Sahara Shopping Center, Lekhraj Crossing, Faizabad

Road, Lucknow (U.P.) Email– [email protected].

Agenda no. 07. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19603)/ 2019-20

Project Name- EC for Masonry Stone Mining Project, Plot No. 02, Area 1.3774 Ha.,

Production Capacity- 1,00,000 TPA (ROM), Khasra No. 957, 340, 171, Add.- Ramgarh

Geejgarh Padli bad, Tehsil- Sikrai, District- Dausa, (Raj.) (Proposal No.- 207955).

Project Proponent Name- Shri- Ramavtar Sharma S/o Shri- Kundan Ram Sharma, Add.-

191/27, Sector-19, Pratap Nagar, Sanganer, Jaipur, Distt.- Jaipur, (Raj.), Email-

[email protected].

Consultant Name- Globus Environment Services, Add.- 326-AB, 3rd Floor, Sahara

Shopping Center, Lekhraj Crossing, Faizabad Road, Lucknow (U.P.) Email.–

[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category/Item No. (In Schedule) 1(a) B2

2. Location of Project Near village – Ramgarh, Geejgarh, Padlibad, Tehsil -

Sikrai, District-Dausa (Rajasthan)

3. Project Details Plot No. – 2,

Area – 1.3774Ha.

Khasra No. 957, 340, 171 (Govt. Land & Charagah Land)

Production in TPA – Masonry Stone @ 100000 TPA

4. Project Cost Rs. 25 Lakh.

5. Water Requirement & Source 5.0KLD (Tanker supply from near village Ramgarh)

6. Fuel & Energy 300 Liter/day Fuel will be required for mining.

7. Application No. & Date &

Documents Submitted

Application No. : 19603

Online Submission Date:-05.04.2021

8. Information about Aravalli

Certificate

Aravalli certificate issued, vide letter no. AME/DAUSA/

Minor/Plot/02/2019/65 dated 30.03.2021.

9. Date of

Air/Water/Noise/Monitoring

Air/Water/Noise/Soil monitoring has been carried out on

17/06/2021.

10. Information about 500mts

Composite Map

Letter No. - AME/DAUSA/ Minor/Plot/02/2019/66 dated

30.03.2021.

11. Environment Management Plan Total Annual expenditure of EMP is Rs. 1,80,000/- per

year. Details are follow:

S.No Description of Item Amount (in Rs/yr.)

1. Annual Monitoring 1,00,000/-

2. Green Belt development 30,000/-

3. Water Sprinkling on haul

roads 50,000/-

Total 1,80,000/-

Final minutes of 4.95th meeting held on 27-29 July, 2021

12. CSR/ESR Activities

Total Annual expenditure of CSR/ESR is Rs. 50,000/- per year. Details are follow:

Year Name of Location Head Quantity Cost

I Year Govt. School,

Ramgarh, Geejgarh, Padlibad, Tehsil -

Sikrai, District-

Dausa, Rajasthan

Water Cooler & Synthetic Tank &

AMC Renovation & Repairing Work

Furniture as Chairs & Tables

1

-

5+5

15,000/-

15,000/-

20,000/-

II Year LED Bulb/Tube light + Fan Library Books, Sports kit &

accessories as Football, Cricket,

Basket Ball etc.

10+10 -

20,000/- 30,000/-

III Year Computer with Printer, Almari (Steel) 1+1 50,000/-

IV Year Gram Panchayat of Village - Ramgarh,

Geejgarh, Padlibad,

Tehsil - Sikrai,

District-Dausa, Rajasthan

Construction and maintenance of village roads adjacent to project site

- 50,000/-

V Year Periodically medical checkup camps,

blood donation camps. Eye checkup

camps Health awareness camps for child and

mother care, health and hygiene

practices

-

-

15,000/-

15,000/-

20,000/-

The PP shall expenditure Rs. 50,000/- per year for CER. The above expenditure is for 5 years, the

onwards the PP shall be expend the amount of CER as per need of local stack holders/Govt.

School/Hospitals & Gram Panchyat etc.

13. Green

Belt/Plantation

Year Un-worked

Area

Govt. Girls

High

Secondary

School,

Kalwan

Backfilled

(Reclaimed

Area)

Top soil

Dumps

Total

Area

(Ha.)

No. of

Plants

Area

(Ha.)

No. of

Plants

Area

(Ha.)

No. of

Plants

Area

(Ha.)

No. of

Plants

Area

(Ha.)

No. of

Plants

Existing - - - - - - - - - -

1st 0.11 110 0.0415 41 0.1515 151

2nd 0.11 110 0.0415 42 0.1515 152

3rd 0.1104 110 0.0420 42 0.1524 152

4th Maintenance

5th Maintenance

Total 0.3304 330 0.125 125 0.4554 455

Note: As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after

ceasing mining operations, undertake re-grassing the mining area and any other

area which may have been disturbed due to their mining activities and restore the

land to a condition which is fit for growth of fodder, flora, fauna etc.

Note: - At the end of third year Green Belt/Plantation will be done in 0.4554 ha. area

i.e. (455 trees) (0.3304 ha + 0.125 ha.) out of which 0.3304 ha.(330 Plants) area will be covered under green belt on around the mine periphery & remaining i.e. 0.125 ha.

(125 Plants) Plantation will be done outside the lease area in village Kalwan in Govt.

Girls High Secondary School.

Native species which are more suitable to the local environment are preferred to be planted such as like Neem (Azadiracta indica), Pipal (Ficus religiosa), Babool

(Acacia nilotica), Kher (Acacia catechu) etc.

Source-Approved Mining Plan with Progressive Mine closure plan

Final minutes of 4.95th meeting held on 27-29 July, 2021

14. Budgetary Breakup for Labour

Total Annual expenditure for labours is Rs. 60,000/- per year. Details are follow:

Sr. No. Description Amount (in Rs./yr.)

1 Rest Shelter 10,000

2 Drinking water facility 10,000

3 Bio-Toilet Facility 30,000

5 Medical facility for labors 10,000

Total 60,000

15. Present Status This is Fresh mining lease of mineral Masonry Stone,

located near village - Ramgarh, Geejgarh, Padlibad, Tehsil -

Sikrai, District-Dausa, Rajasthan

Observations of the committee:-

The SEAC considered/examined the project proposal on 27.07.2021by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for EC for Masonry Stone Mining Project, Plot No.

02, Area 1.3774 Ha., Production Capacity- 1,00,000 TPA (ROM), Khasra No. 957, 340, 171,

Add.- Ramgarh Geejgarh Padli bad, Tehsil- Sikrai, District- Dausa, (Raj.) (Proposal No.-

207955). The project is covered under B2 category. The SME, Jaipur vide order dated

05.08.2020 has issued LoI to the PP for mining of Masonry Stone. The mining plan has been

approved by the SME, Jaipur vide letter dated 30.03.2021. AME, Dausa in his certificate

dated 30.03.2021 has stated that the mining lease does not fall in Aravalli hills. DCF, Dausa

in his certificate dated 19.04.2021 has stated that there is no Wildlife Sanctuary/National

Park/ Conservation Reserve within 10 km periphery of the mine. The project does not involve

approval/ clearance under the Forest (Conservation) Act, 1980 and Wild Life Protection Act,

1972 as no forest land is involved and neither there is any Wild Life Sanctuary/ National Park

within 10 Km from the project site.

As per cluster certificate issued by AME, Dausa on 30.03.2021, the total area of all

the mining leases in the cluster having area of 3.3774 ha.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-1,

Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri-

Ramavtar Sharma S/o Shri- Kundan Ram Sharma, for Masonry Stone Mining Project, Plot

No. 02, Area 1.3774 Ha., Production Capacity- 1,00,000 TPA (ROM), Khasra No. 957, 340,

171, Add.- Ramgarh Geejgarh Padli bad, Tehsil- Sikrai, District- Dausa, (Raj.) (Proposal

No.- 207955), with the stipulation that the PP shall abide by the annual production scheduled

specified in mining plan and that any deviation there in will render the PP liable for legal

action in accordance with Environment and Mining Laws, with the specific and general

conditions annexed at Annexure ‘A’. Name of Proponent Shri- Ramavtar Sharma S/o Shri-

Kundan Ram Sharma, Add.- 191/27, Sector-19, Pratap Nagar, Sanganer, Jaipur, Distt.-

Final minutes of 4.95th meeting held on 27-29 July, 2021

Jaipur, (Raj.), Email- [email protected], Consultant Name:- Globus Environment

Services, Add.- 326-AB, 3rd Floor, Sahara Shopping Center, Lekhraj Crossing, Faizabad

Road, Lucknow (U.P.), Email.– [email protected].

Agenda no. 08. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19618)/ 2019-20

Project Name- EC for Masonry Stone Mining Project, Plot No. 05/2019, Area 1.8827 Ha.,

Production Capacity- 2,50,000 TPA (ROM), Khasra No. 134, Add.- Kalwan, Tehsil- Sikrai,

District- Dausa, (Raj.) (Proposal No.- 199978).

Project Proponent Name- Shri- Rajendra Prasad Sharma S/o Shri- Rameshwar Prasad

Sharma, Add.- Kuiwali Dhani, Raipura, Sikrai, Distt.- Dausa, (Raj.) Email-

[email protected].

Consultant Name- Globus Environment Services, Add.- 326-AB, 3rd Floor, Sahara

Shopping Center, Lekhraj Crossing, Faizabad Road, Lucknow (U.P.) Email. –

[email protected]

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category/Item No. (In Schedule) 1(a) B2

2. Location of Project Near village – Kalwan, Tehsil - Sikrai, District-Dausa,

Rajasthan

3. Project Details Plot No. – 5/2019,

Area – 1.8827Ha.

Khasra No. 134 (Govt. Land)

Production in TPA – Masonry Stone @ 250000 TPA

4. Project Cost Rs. 25 Lakh.

5. Water Requirement & Source 5.0KLD (Tanker supply from near village Kalwan)

6. Fuel & Energy 300 Liter/day Fuel will be required for mining.

7. Application No. & Date &

Documents Submitted

Application No. :

Online Submission Date:-25.03.2021

8. Information about Aravalli

Certificate

Aravalli certificate issued, vide letter no. AME/DAUSA/

Minor/Plot/05/2019 dated 22.02.2021.

9. Date of

Air/Water/Noise/Monitoring

Air/Water/Noise/Soil monitoring has been carried out on

17/06/2021.

10. Information about 500mts

Composite Map

Letter No. - AME/DAUSA/ Minor/Plot/05/2019/32 dated

22.02.2021.

11. Environment Management Plan Total Annual expenditure of EMP is Rs. 1,80,000/- per

year. Details are follow:

S.No Description of Item Amount (in Rs/yr.)

1. Air Pollution Control -

Water Sprinkling 1,00,000/-

2. Environmental Monitoring

and Management 30,000/-

3. Green Belt Development 50,000/-

Total 1,80,000/-

Final minutes of 4.95th meeting held on 27-29 July, 2021

12. CSR/ESR Activities

Total Annual expenditure of CSR/ESR is Rs. 50,000/- per year. Details are follow:

Year Name of Location Head Quantity Cost

I Year Govt. School,

Kalwan, Tehsil - Sikrai, District-

Dausa, Rajasthan

Water Cooler & Synthetic Tank &

AMC Renovation & Repairing Work

Furniture as Chairs & Tables

1

-

5+5

20,000/-

15,000/-

15,000/-

II Year LED Bulb/Tube light + Fan Library Books, Sports kit &

accessories as Football, Cricket,

Basket Ball etc.

10+10 -

15,000/- 35,000/-

III Year Computer with Printer, Almari (Steel) 1+1 50,000/-

IV Year Gram Panchayat of Village - Kalwan,

Tehsil - Sikrai,

District-Dausa,

Rajasthan

Construction and maintenance of village roads adjacent to project site

- 50,000/-

V Year Periodically medical checkup camps,

blood donation camps. Eye checkup

camps Health awareness camps for child and

mother care, health and hygiene

practices

-

-

15,000/-

15,000/-

20,000/-

The PP shall expenditure Rs. 50,000/- per year for CER. The above expenditure is for 5 years, the

onwards the PP shall be expend the amount of CER as per need of local stack holders/Govt.

School/Hospitals & Gram Panchyat etc.

13. Green

Belt/

Plantation

Year Un-worked

Area

Near area of

Shamshan

Ghat in

Kalwan

Backfilled

(Reclaimed

Area)

Top soil

Dumps

Total

Area

(Ha.)

No. of

Plants

Area

(Ha.)

No. of

Plants

Area

(Ha.)

No. of

Plants

Area

(Ha.)

No. of

Plants

Area

(Ha.)

No. of

Plants

Existing - - - - - - - - - -

1st 0.20 200 0.007 7 0.207 207

2nd 0.20 200 0.007 7 0.207 207

3rd 0.1993 199 0.008 8 0.2073 207

4th Maintenance

5th Maintenance

Total 0.5993 599 0.022 22 0.6213 621

Note: As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing

mining operations, undertake re-grassing the mining area and any other area which

may have been disturbed due to their mining activities and restore the land to a

condition which is fit for growth of fodder, flora, fauna etc.

Note: - At the end of third year Green Belt/Plantation will be done in 0.6213 ha. area i.e.

(621 trees) (0.5993 ha + 0.022 ha.) out of which 0.5993 ha.(599 Plants) area will be

covered under green belt on around the mine periphery & remaining i.e. 0.022 ha. (22 Plants) Plantation will be done outside the lease area in village Kalwan in Near area of

Shamshan Ghat.

Native species which are more suitable to the local environment are preferred to be planted such as like Neem (Azadiracta indica), Pipal (Ficus religiosa), Babool (Acacia

nilotica), Kher (Acacia catechu) etc. Source-Approved Mining Plan with Progressive Mine closure plan

Final minutes of 4.95th meeting held on 27-29 July, 2021

14. Budgetary Breakup for Labour

Total Annual expenditure for labours is Rs. 60,000/- per year. Details are follow:

Sr. No. Description Amount (in Rs./yr.)

1 Rest Shelter 10,000

2 Drinking water facility 10,000

3 Bio-Toilet Facility 30,000

5 Medical facility for labors 10,000

Total 60,000

15. Present Status This is Fresh mining lease of mineral Masonry Stone,

located near village - Kalwan, Tehsil - Sikrai, District-

Dausa, Rajasthan

Observations of the committee:-

The SEAC considered/examined the project proposal on 27.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for EC for Masonry Stone Mining Project, Plot

No. 05/2019, Area 1.8827 Ha., Production Capacity- 2,50,000 TPA (ROM), Khasra No.

134, Add.- Kalwan, Tehsil- Sikrai, District- Dausa, (Raj.) (Proposal No.- 199978). The

project is covered under B2 category. The SME, Jaipur vide order dated 04.02.2021 has

issued LoI to the PP for mining of Masonry Stone. The mining plan has been approved by the

SME, Jaipur vide letter dated 30.03.2021. AME, Dausa in his certificate dated 22.02.2021 has

stated that the mining lease does not fall in Aravalli hills. DCF, Dausa and in his certificate

dated 19.04.2021 has stated that there is no Wildlife Sanctuary/National Park/ Conservation

Reserve within 10 km periphery of the mine. The project does not involve approval/

clearance under the Forest (Conservation) Act, 1980 and Wild Life Protection Act, 1972 as

no forest land is involved and neither there is any Wild Life Sanctuary/ National Park within

10 Km from the project site.

According to cluster certificate issued by AME, Dausa on 22.02.2021, total area of all

the mining leases in the cluster is less than 5.0 ha.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-1,

Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri Rajendra

Prasad Sharma S/o Shri- Rameshwar Prasad Sharma for Masonry Stone Mining Project, Plot

No. 05/2019, Area 1.8827 Ha., Production Capacity- 2,50,000 TPA (ROM), Khasra No. 134,

Add.- Kalwan, Tehsil- Sikrai, District- Dausa, (Raj.) (Proposal No.- 199978), with the

stipulation that the PP shall abide by the annual production scheduled specified in mining

plan and that any deviation there in will render the PP liable for legal action in accordance

with Environment and Mining Laws, with the specific and general conditions annexed at

Annexure ‘A’. Name of Proponent Shri- Rajendra Prasad Sharma S/o Shri- Rameshwar

Prasad Sharma, Add.- Kuiwali Dhani, Raipura, Sikrai, Distt.- Dausa, (Raj.), Email-

Final minutes of 4.95th meeting held on 27-29 July, 2021

[email protected], Consultant Name:-. Globus Environment Services, Add.-

326-AB, 3rd Floor, Sahara Shopping Center, Lekhraj Crossing, Faizabad Road, Lucknow

(U.P.) Email. –[email protected].

Agenda no. 09. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19619)/ 2019-20

Project Name- EC for Sand Stone Mining Project, Q.L. No. 2192, Area 0.18 Ha., Khasra

No. not given, Production Capacity- 3700 TPA (ROM) Add.- Keru, Tehsil- Jodhpur,

District- Jodhpur, (Raj.) (Proposal No.- 208590).

Project Proponent Name: Shri- Ghanshyam Prajapati S/o Shri- Peeramal Prajapati, Add.-

Near Sankatmochan Balaji Temple Duliya Bas, Sujangarh, Churu, Distt.- Churu, (Raj.),

Email- [email protected].

Consultant Name- Globus Environment Services, Add.- 326-AB, 3rd Floor, Sahara

Shopping Center, Lekhraj Crossing, Faizabad Road, Lucknow (U.P.) Email. –

[email protected]

Observations and Resolution of the committee:-

The PP vide letter dated 27.07.2021 has submitted an application for deferment of the

case. The SEAC agreed to the request of the PP and deferred the matter. The project shall be

taken up again on receipt of his request for consideration of the project by the PP, in the

subsequent proposed meeting.

Agenda no. 10. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B1(18798)/ 2019-20

Project Name- EC for Sandstone Mining Project, Ref. No. 20191000014379, Area 1.877

Ha., Khasra No. 352/4, 352/7, 352/9, 352/10, Productoin Capacity 150000 TPA

(ROM){Sandstone : 135000 TPA,Waste: 15000TPA}Add.- Badli, Tehsil- Jodhpur, District-

Jodhpur, (Raj.) (Proposal No.- 62792).

Project Proponent Name- Smt.-Narbada Kachhawaha W/o Shri- Panna Lal Kachhawaha,

Add.- Kishan Service Center, Pratap Nagar, Soorsagar Road, Jodhpur, Distt.- Jodhpur,

(Raj.) Email- [email protected].

Consultant Name- Globus Environment Services, Add.- 326-AB, 3rd Floor, Sahara

Shopping Center, Lekhraj Crossing, Faizabad Road, Lucknow (U.P.) Email. –

[email protected].

Observations and Resolution of the committee:-

The PP vide letter dated 27.07.2021 has submitted an application for deferment of the

case. The SEAC agreed to the request of the PP and deferred the matter. The project shall be

taken up again on receipt of his request for consideration of the project by the PP, in the

subsequent proposed meeting.

Agenda no. 11. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B1( 18799)/ 2019-20

Project Name- E C for Sandstone Mining Project" Ref. No. 2019100004382, Area 1.4658

Ha., Khasra No. 348/01, Productoin Capacity 110000 TPA (ROM){Sandstone : 99000

Final minutes of 4.95th meeting held on 27-29 July, 2021

TPA,Waste: 11000 TPA} Add.- Badli, Tehsil- Jodhpur, District- Jodhpur, (Raj.) (Proposal

No.- 62778).

Project Proponent Name- Shri-Pukhraj Gehlot S/o Shri- Ramchandra Gehlot, Add.- Gali

No. 1, Kheme Ka Kua, Pal road, Distt.- Jodhpur, (Raj.) Email-

[email protected].

Consultant Name- Globus Environment Services, Add.- 326-AB, 3rd Floor, Sahara

Shopping Center, Lekhraj Crossing, Faizabad Road, Lucknow (U.P.) Email. –

[email protected].

Observations and Resolution of the committee:-

The PP vide letter dated 27.07.2021 has submitted an application for deferment of the

case. The SEAC agreed to the request of the PP and deferred the matter. The project shall be

taken up again on receipt of his request for consideration of the project by the PP, in the

subsequent proposed meeting.

Agenda no. 12. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19606)/ 2019-20

Project Name- EC for Masonry Stone (Crusher Gitti) Mining Project, Ref. No. 202010000

28711, M.L. No. 09/2020, Area 1.0427 Ha., Production Capacity 1,09,650 TPA (ROM)

{Saleable masonry stone: 1,04,169 TPA, Waste: 5481 TPA}, with stone crusher having

production capacity of 150 TPH, Khasra No. 922, Add.- Kesunda, Tehsil- Chhoti Sadri,

District- Pratapgarh, (Raj.) (Proposal No.- 214422).

Project Proponent Name- Shri- Labhachand Meghwal S/o Shri- Gotam Lal Meghwal,

Add.- Kesunda, Tehsil- Chhoti Sadri, Distt.- Pratapgarh, (Raj.) Email-

[email protected].

Consultant Name- Fulgro Environmental & Engineering Services India Pvt. Ltd., Add-27,

Ashok Vatika, Khatipura Road, Jhotwara, Jaipur, (Raj.), Email:- [email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category / Item no. (in

Schedule):

1 (a) /Category-B2

2. Location of

Project Near Village- Kesunda, Tehsil- Chhoti Sadri & District- Pratapgarh (Raj.)

Khasra No. 922

3. Project Details

REF.

No./Production

capacity

Ref. No. 20201000028711, Area- 1.0427 ha

Proposed Crusher capacity: 150 TPH

Proposed Production capacity: 1,09,650 TPA (R.O.M.)

(Production of saleable Masonary Stone: 1,04,169 TPA, Waste: 5,481 TPA)

4. Project Cost Rs. 1.50 Crore

5. Water

Requirement & Source

Total Water Requirement-2.36 KLD

Source: Water will be made available from nearby village Kesundavia water tanker supply.

6. Fuel &Energy: - Diesel operated machinery will be used and will be taken care by the contractor itself. If

required Electricity connection will be taken from concerned electricity department.

Final minutes of 4.95th meeting held on 27-29 July, 2021

7. Application No. & Date &

documents

submitted: -

Online Proposal No. SIA/RJ/MIN/214422/2021

Documents:FORM-I & PFR along with approved mining plan & all the requisite documents for

grant of EC have been submitted.

8. Information about

Aravalli

Certificate.

Aravalli Certificate was issued by ME, Pratapgarh vide letter no. ME/Pratap/CC-minor/ML

09/2020/2020-21/550 dated 01/04/2021.

9. Date of

Air/Water/Noise

Monitoring

Date of Air Monitoring: - 03/04/2021

Date of Water Sampling: 03/04/2021

Date of Noise Monitoring: 03/04/2021

10. Information about 500 mts

composite map

Cluster certificate was issued by ME, Udaipur vide letter no. ME/Pratap/CC- Minor/M.L.

09/2020/2020-21/549 dated 01/04/2021. No other mine lease are existing within 500 m radius of

the said mine lease area

11. Environment

Management

Plan

Annual Expenditure of Rs 7.50 Lac Per year

S.

No. Particulars

Capital Cost (in Rs Lac)

Recurring

cost

(in Rs. Lac)

1 Air, Water & Noise pollution monitoring -- 1.00

2 Installation of water sprinkling system 2.00 0.10

3 Installation of covered conveyer belts 2.00 0.20

4

Water Requirement (For dust

suppression and green belt/plantation

purpose)

-- 0.90

5 Green belt (including plant cost, tree

guard and its maintenance) -- 0.50

6

Contribution towards construction and

maintenance of the kachha roads after

consultation with the concerned gram Panchayat and local people

-- 0.80

Total 4.00 3.50

12 GreenBelt/

Plantation

Annual expenditure of Rs. 0.50Lac Per Year (Recurring Cost)

Year Un-worked

Area

Outside the mine

lease area in own

khasra land

Top Soil

Dumps Backfilled Area Total

Area (Ha)

No. of Trees

Area (Ha)

No. of Trees

Area (Ha)

No. of Trees

Area (Ha)

No. of Trees

Area (Ha)

No. of Trees

Existing - - - - - - - - - -

I - - 0.1147 114 - - - - 0.1147 114

II - - 0.1148 115 - - - - 0.1148 115

III - - 0.1148 115 - - - - 0.1148 115

IV MAINTENANCE TO BE DONE

V

At the end of life of Mine

- - - - - - - - - -

Total - - 0.3443 344 - - - - 0.3443 344

Note:Total 344 saplings will be planted over an area of 0.3443 ha (33% of the mine lease area)

which will be planted outside the mine lease in own khasra no. 736, 744 &745 and it will be

ensured that after ceasing mining operations re-grassing of the mining area and any other area

Final minutes of 4.95th meeting held on 27-29 July, 2021

which may have been disturbed due to the mining activities is done and will restore the land to a condition which is fit for growth of fodder, flora, fauna etc. as per the MoEF & CC O.M vide No.

22-34/2018-IA.III dated 16th Jan 2020.Native species which are more suitable to the local

environment are preferred to be planted such as Khejari, Neem, Pipal, Sheesham, Mango, etc.

13 Budgetary

Breakup for

Labours

Annual Expenditure of Rs. 1.702Lac Per year

Sr.

No. Facility Provided for Laborers

Capital Cost

in Rs. Recurring Cost in

Rs.

1. Shelters, Safe drinking water, Sanitation

facility

1,00,000 Maintenance Cost:

20,000

3. Periodical medical Examination per year @1000 Rs. per labor

18,000

4. Fuel for cooking (LPG Cylinder) @950 Rs.

Per month 9,500

5. Education for children of labors @ 2,400 Rs.

per labor 43,200

6. Group Insurance @1500 Rs. per worker 27,000 -

7.

Provision for personal protection equipment (PPEs) like ear plug, dust mask, Helmet, shoes

etc., for 18 workers

Safety shoes @350 Rs (2 times/year)

Hand Gloves @300 Rs (2 times/year)

Dust mask @25 Rs (2 times in month)

Ear plugs @25 Rs (2 times in month)

Helmets @450 Rs (1 time/years)

12,600

10,800

9,000

9,000

8,100

8. First Aid Box 10,000

9. Fire Safety 30,000 20,000

Total 1,57,000 1,70,200

14 Present Status Fresh LOI now proposed for the grant of Environmental Clearance.

Observations of the committee:-

The SEAC considered/examined the project proposal on 27.07.2021by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application EC for Masonry Stone (Crusher Gitti) Mining

Project, Ref. No. 202010000 28711, M.L. No. 09/2020, Area 1.0427 Ha., Production

Capacity 1,09,650 TPA (ROM) {Saleable masonry stone : 1,04,169 TPA, Waste: 5481

TPA}, with stone crusher having production capacity of 150 TPH, Khasra No. 922, Add.-

Kesunda, Tehsil- Chhoti Sadri, District- Pratapgarh, (Raj.) (Proposal No.- 214422). The

project is covered under B2 category. The SME, Udaipur vide order dated 28.12.2020 has

issued LoI to the PP for mining of Masonry Stone. The mining plan has been approved by the

SME, Udaipur vide letter dated 01.04.2021. ME, Pratapgarh in his certificate dated

01.04.2021 has stated that the mining lease does not fall in Aravalli hills. DCF, WL,

Chittorgarh in his certificate dated 05.03.2021 has stated that the Sitamata WLS is at a

distance of 24.10 Km from the applied lease area. DFO, Neemuch in his certificate dated

23.07.2021 has stated that there is no Wildlife Sanctuary/National Park within 10 km

periphery of the mine.

Final minutes of 4.95th meeting held on 27-29 July, 2021

As per cluster certificate issued by ME, Pratapgarh on 01.04.2021, the total area of all

the mining leases in the cluster having area of 1.0427 ha.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-1,

Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri-

Labhachand Meghwal S/o Shri- Gotam Lal Meghwal for Masonry Stone (Crusher Gitti)

Mining Project, Ref. No. 202010000 28711, M.L. No. 09/2020, Area 1.0427 Ha., Production

Capacity 1,09,650 TPA (ROM) {Saleable masonry stone : 1,04,169 TPA, Waste: 5481

TPA}, with stone crusher having production capacity of 150 TPH, Khasra No. 922, Add.-

Kesunda, Tehsil- Chhoti Sadri, District- Pratapgarh, (Raj.) (Proposal No.- 214422), with the

stipulation that the PP shall abide by the annual production scheduled specified in mining

plan and that any deviation there in will render the PP liable for legal action in accordance

with Environment and Mining Laws, with the specific and general conditions annexed at

Annexure ‘A’. Project Name- EC for Masonry Stone (Crusher Gitti) Mining Project, Ref.

No. 202010000 28711, M.L. No. 09/2020, Area 1.0427 Ha., Production Capacity 1,09,650

TPA (ROM) {Saleable masonry stone : 1,04,169 TPA, Waste: 5481 TPA}, with stone

crusher having production capacity of 150 TPH, Khasra No. 922, Add.- Kesunda, Tehsil-

Chhoti Sadri, District- Pratapgarh, (Raj.) (Proposal No.- 214422). Project Proponent

Name- Shri- Labhachand Meghwal S/o Shri- Gotam Lal Meghwal, Add.- Kesunda, Tehsil-

Chhoti Sadri, Distt.- Pratapgarh, (Raj.), Email- [email protected].

Agenda no. 13. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19607)/ 2019-20

Project Name- EC for Granite Mining Project, M.L. No. 30/2021, Plot No. 64, Area 1.0159

Ha., Khasra No. 1767, 1768, 1769, 1770, 1772, 1774, Production Capacity 81,400 TPA

(ROM) {Granite: 48,840 TPA, Waste: 32,560 TPA}, Add.- Mankhand, Tehsil- Kekri,

District- Ajmer, (Raj.) (Proposal No.- 214058).

Project Proponent Name: Shri- Ugmaram Khichad S/o Shri- Chelaram Khichad, Add.-

Mukam, Post- Seeniya, Ranigaon, Tehsil- Makrana, Distt.- Nagaur, (Raj.) Email-

[email protected].

Consultant Name- Fulgro Environmental & Engineering Services India Pvt. Ltd., Add-27,

Ashok Vatika, Khatipura Road, Jhotwara, Jaipur, (Raj.), Email:[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category /

Item no. (in Schedule):

1 (a) /Category-B2

2. Location of

Project Near Village: Mankhand Tehsil: Kekri, District- Ajmer (Raj.)

3. Project Details

REF. No./Production

capacity

Plot. No. 64, Area-1.0159 ha., Khasra No. 1767, 1768, 1769, 1770, 1772, 1774,

Proposed Production capacity: 81,400 TPA (ROM)

(Production of Granite: 48,840 TPA, Mineral Waste: 32,560 TPA

4. Project Cost Rs. 0.80 Crore

Final minutes of 4.95th meeting held on 27-29 July, 2021

5. Water Requirement

& Source

Total Water Requirement-3.92KLD Source: Water will be made available from nearby village Mankhandvia water tanker supply.

6. Fuel &Energy: - Diesel operated machinery will be used and will be taken care by the contractor itself. If

required Electricity connection will be taken from concerned electricity department.

7. Application No.

& Date &

documents submitted: -

Online Proposal No. SIA/RJ/MIN/214058/2021

Documents:FORM-I & PFR along with approved mining plan & all the requisite documents for grant of EC have been submitted.

8. Information

about Aravalli

Certificate.

Aravalli Certificate was issued by AME, Sawar vide letter no. AME/Sawar/Map/(L.O.I.)-30/21

(Plot No. 64)/ dated 12/04/2021.

9. Date of

Air/Water/Noise Monitoring

Date of Air Monitoring: - 01/06/2021

Date of Water Sampling: - 01/06/2021 Date of Noise Monitoring: 01/06/2021

10. Information

about 500 mts

composite map

Cluster certificate was issued by AME, Sawar vide letter no. AME/Sawar/Map/(L.O.I.)-30/21

(Plot No. 64)/

11. Environment

Management

Plan

Annual Expenditure of Rs. 4.0Lac Per year

S.

No. Particulars

Recurring cost

(in Rs. Lac)

1. Air, Water & Noise pollution monitoring 1.00

2. Water Requirement (For dust suppression and green

belt/plantation purpose)

1.20

3. Green belt (including plant cost, tree guard and its

maintenance)

0.30

4. Contribution towards construction and maintenance of

the kachha roads after consultation with the concerned

gram Panchayat and local people

1.50

Total 4.00

12 GreenBelt/

Plantation

Annual expenditure of Rs.0.30Lac Per Year (Recurring Cost)

Note:Total 576 saplings will be planted over an area of 0.5766 hectare (more than 33% of the

mine lease area) out of which 251 saplings will be planted over the undisturbed area of 0.2509 ha and 84 saplings will be planted at an area of 0.0843 hectare. Outside the mine site in khasra

no. 2175 of gram panchayat Mankhand. At the end of life of mine 241 saplings will be planted

over the backfilled area of 0.2414 ha and It will be ensured that after ceasing mining operations

re-grassing of the mining area and any other area which may have been disturbed due to the mining activities is done and will restore the land to a condition which is fit for growth of

Year Un-worked Area Outside the mine

lease area Backfilled Area Total

Area

(Ha)

No. of

Trees Area (Ha)

No. of

Trees

Area

(Ha)

No. of

Trees Area (Ha)

No. of

Trees

Existing -- -- -- -- -- -- -- --

I 0.0836 83 0.0281 28 -- -- 0.1117 111

II 0.0836 84 0.0281 28 -- -- 0.1117 112

III 0.0837 84 0.0281 28 -- -- 0.1118 112

IV

MAINTENANCE

TO BE DONE

MAINTENANCE

TO BE DONE

-- -- MAINTENANCE

TO BE DONE V -- --

End of

life of

mine

0.2414 241 0.2414 241

0.2509 251 0.0843 84 0.2414 241 0.5766 576

Final minutes of 4.95th meeting held on 27-29 July, 2021

fodder, flora, fauna etc. as per the MoEF & CC O.M vide No. 22-34/2018-IA.III dated 16th Jan 2020. Native species which are more suitable to the local environment are preferred to be

planted such as Neem, Babool, Vilayti Babool, Khejari etc

13 Budgetary

Breakup for

Labours

Annual Expenditure of Rs.1.925Lac Per year

Sr.

No. Facility Provided for Laborers

Capital

Cost in Rs.

Recurring Cost

in Rs.

1. Shelters, Safe drinking water,

Sanitation facility

1,00,000

Maintenance

Cost: 30,000

3. Periodical medical Examination per

year @1000 Rs. per labor

20,000

4. Fuel for cooking (LPG Cylinder) @950

Rs.For 10 months 9,500

5. Books/Uniforms/scholarship for children

of labors @ 2,400 Rs. per labor 48,000

6. Group Insurance @1500 Rs. per worker 30,000 -

7.

Provision for personal protection equipment

(PPEs) like ear plug, dust mask, Helmet,

shoes etc., for20 workers

Safety shoes@350 Rs (2 times/year)

Hand Gloves @300 Rs (2 times/year)

Face mask@25 Rs (2 times in 10 month)

Ear plugs@25 Rs (2 times in 10 month)

Helmets @450 Rs(1 time/years)

14,000

12,000

10,000

10,000

9,000

8. First Aid Box 10,000

9. Fire Safety 30,000 20,000

Total 1,60,000 1,92,500

14 Present Status Fresh LOI now proposed for the grant of Environmental Clearance.

Observations of the committee:-

The SEAC considered/examined the project proposal on 27.07.2021by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application EC for Granite Mining Project, M.L. No. 30/2021,

Plot No. 64, Area 1.0159 Ha., Khasra No. 1767, 1768, 1769, 1770, 1772, 1774, Production

Capacity 81,400 TPA (ROM) {Granite: 48,840 TPA, Waste: 32,560 TPA}, Add.- Mankhand,

Tehsil- Kekri, District- Ajmer, (Raj.) (Proposal No.- 214058). The project is covered under

B2 category. The SME, Ajmer vide order dated 19.03.2021 has issued LoI to the PP for

mining of Granite. The mining plan has been approved by the SME, Ajmer vide letter dated

09.04.2021. AME, Sawar in his certificate dated 21.05.2021 has stated that the mining lease

does not fall in Aravalli hills. DCF, Tonk and DCF, Ajmer in their certificates dated

23.02.2021 and 13.07.2021, respectively have stated that there is no Wildlife

Sanctuary/National Park/ Conservation Reserve within 10 km periphery of the mine. Besides,

Final minutes of 4.95th meeting held on 27-29 July, 2021

the PP in Form-1 has also stated that there is no WLS, RF, and Conservation Reserve within

10 Km of the project site.

The project does not involve approval/ clearance under the Forest (Conservation) Act,

1980 and Wild Life Protection Act, 1972 as no forest land is involved and neither there is any

Wild Life Sanctuary/ National Park within 10 Km from the project site.

As per cluster certificate issued by AME, Sawar on 21.05.2021, the total area of all the

mining leases in the cluster having area of 2.2962 ha.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1,Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri-

Ugmaram Khichad S/o Shri- Chelaram Khichad, for Granite Mining Project, M.L. No.

30/2021, Plot No. 64, Area 1.0159 Ha., Production Capacity 81,400 TPA (ROM) {Granite :

48,840 TPA, Waste: 32,560 TPA}, Khasra No. 1767, 1768, 1769, 1770, 1772, 1774, Add.-

Mankhand, Tehsil- Kekri, District- Ajmer, (Raj.) (Proposal No.- 214058), with the

stipulation that the PP shall abide by the annual production scheduled specified in mining

plan and that any deviation there in will render the PP liable for legal action in accordance

with Environment and Mining Laws, with the specific and general conditions annexed at

Annexure ‘A’. Name of Proponent Shri- Ugmaram Khichad S/o Shri- Chelaram Khichad,

Add.- Mukam, Post- Seeniya, Ranigaon, Tehsil- Makrana, Distt.- Nagaur, (Raj.)

Email- [email protected], Consultant Name:- Fulgro Environmental & Engineering

Services India Pvt. Ltd., Add-27, Ashok Vatika, Khatipura Road, Jhotwara, Jaipur, (Raj.),

Email:- [email protected].

Agenda no. 14. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19608)/ 2019-20

Project Name- EC for Quartz Feldspar Mining Project, M.L. No. 58/2020, Area 1.0882

Ha., Production Capacity 25934 TPA (ROM){ Quartz : 2996 TPA, Feldspar: 11,984 TPA,

Subgrade: 2140 TPA Waste: 4280 TPA and overburden: 4534 TPA} Khasra No. 62/613, 63,

64, 65/1, 65/2, Add.- Rampuriya, Tehsil- Sahara, District- Bhilwara, (Raj.) (Proposal No.-

209709).

Project Proponent Name- Shri- Shankar Lal Jat S/o Shri- Bhura Lal Jat, Add.- Rampuriya,

Post- Lakhola, Tehsil- Sahara, Distt.- Bhilwara, (Raj.), Email- [email protected].

Consultant Name- Fulgro Environmental & Engineering Services India Pvt. Ltd., Add-27,

Ashok Vatika, Khatipura Road, Jhotwara, Jaipur, (Raj.), Email:[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category /

Item no. (in

Schedule):

1 (a) /Category-B2

2. Location of Project

Khasra No. 62/613, 63, 64, 65/1, 65/2

Near Village- Rampuriya, Tehsil: Saraha, District: Bhilwara (Raj.)

Final minutes of 4.95th meeting held on 27-29 July, 2021

3. Project Details REF.

No./Production

capacity

ML No. 58/2020, Area- 1.0882 ha

Proposed Production capacity: 25,934 TPA (ROM)

(Production of Quartz: 2,996 TPA, Feldspar: 11,984 TPA,

Subgrade: 2,140 TPA, Waste: 4,280 TPA & Over Burden: 4,534 TPA) 4. Project Cost Rs. 0.30 Crore

5. Water

Requirement

& Source

Total Water Requirement-2.50KLD

Source: Water will be made available from nearby village Rampuriya via water tanker

supply.

6. Fuel &Energy: - Diesel operated machinery will be used. Fuel will be required for the operation of

mines machineries and transportation vehicles which will be taken care by the

contractor itself. Electricity connection will be taken from concerned electricity

department.

7. Application No.

& Date & documents

submitted: -

Online Proposal No. SIA/RJ/MIN/209709/2021

Documents:FORM-I & PFR along with approved mining plan & all the requisite documents for grant of EC have been submitted.

8. Information

about Aravalli

Certificate.

Aravalli Certificate was issued by ME, Bhilwara vide letter no.

ME/Bhil/MAP/Aravalli/M.L. 58/2020/209 dated 19/03/2021

9. Date of

Air/Water/Noise Monitoring

Date of Air Monitoring: - 16/04/2021

Date of Water Sampling: - 16/04/2021 Date of Noise Monitoring: 16/04/2021

10. Information

about 500 mts composite map

Cluster certificate was issued by ME, Bhilwara vide letter no. ME/Bhil/MAP/Cluster/M.L.

58/2020/211 dated 19/03/2021. No other mine lease is existing within 500 m radius of the

said mine lease area.

11. Environment Management

Plan

Annual Expenditure of Rs 2.20Lac Per year

S. No. Description Recurring Cost (Rs. in

lacs)

1 Air, Water & Noise pollution monitoring 1.00

2 Water Requirement (For dust suppression and green

belt/plantation purpose) v 0.75

3 Green belt (including plant cost, tree guard and its

maintenance) 0.30

4 Contribution towards construction and maintenance of the kachha roads after consultation with the concerned

gram Panchayat and local people

0.15

Total 2.20

12 GreenBelt/ Plantation

Annual expenditure of Rs. 0.30Lac Per Year (Recurring Cost)

Year Un-worked

Area

Outside the

lease area at

own Khasra

land

Backfilled

Area Total

Area

(Ha)

No. of

Trees

Area

(Ha)

No. of

Trees

Area

(Ha)

No.

of

Trees

Area

(Ha)

No. of

Trees

Existing -- -- -- -- -- -- -- --

I 0.092 92 0.0275 27 -- -- 0.1195 119

II 0.092 92 0.0275 28 -- -- 0.1195 120

III 0.092 92 0.0275 28 -- -- 0.1195 120

IV MAINTENANCE TO BE DONE

-- -- MAINTENANCE

TO BE DONE V -- --

Final minutes of 4.95th meeting held on 27-29 July, 2021

Note:Total 726 saplings will be planted over an area of 0.7260 hectare, out of which 276

saplings will be planted in first three years at an undisturbed area of 0.2764 hectare and to complete 33% of the total plantation 83 saplings will be planted in first three years outside

the Mining lease area of 0.0827 Hectare at own Khasra land no. 63. At the end of life of

mine 367 saplings will be planted over backfilled area of 0.3675 hectare and it will be

ensured that after ceasing mining operations re-grassing of the mining area and any other area which may have been disturbed due to the mining activities is done and will restore the

land to a condition which is fit for growth of fodder, flora, fauna etc. as per the MoEF& CC

O.M vide No. 22-34/2018-IA.III dated 16th Jan 2020. Native species which are more suitable to the local environment are preferred to be planted such as Khejdi, Neem, Babul,

etc.

End of

life of

mine

0.3675 367 0.3675 367

Total 0.2764 276 0.0827 83 0.3675 367 0.726 726

13 Budgetary

Breakup for Labours

Annual Expenditure of Rs. 1.74050Lac Per year

Sr.

No. Facility Provided for Laborers

Capital

Cost in Rs.

Recurring Cost

in Rs.

1. Shelters, Safe drinking water, Sanitation

facility

1,00,000

Maintenance

Cost: 30,000

3. Periodical medical Examination per year

@1000 Rs. per labor

17,000

4. Fuel for cooking (LPG Cylinder) @ 950

Rs. for 10 months 9,500

5. Books/Uniforms for children of labors

@ 2,400 Rs. per labor 40,800

6. Group Insurance @1500 Rs. per worker 25,500 -

7.

Provision for personal protection

equipment (PPEs) like ear plug, dust

mask, Helmet, shoes etc., for 17 workers

Safety shoes@350 Rs (2

times/year)

Hand Gloves @300 Rs (2

times/year)

Dust mask@25 Rs (2 times in 10

month)

Ear plugs@25 Rs (2 times in 10

month)

Helmets @450 Rs (1 time/years)

11,900

10,200

8,500

8,500 7,650

8. First Aid Box 10,000

9. Fire Safety 30,000 20,000

Total 1,55,500 1,74,050

14 Present Status Fresh LOI now proposed for the grant of Environmental Clearance.

Observations of the committee:-

The SEAC considered/examined the project proposal on 27.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

Final minutes of 4.95th meeting held on 27-29 July, 2021

The PP has submitted application EC for Quartz Feldspar Mining Project, M.L. No.

58/2020, Area 1.0882 Ha., Production Capacity 25934 TPA (ROM){ Quartz : 2996 TPA,

Feldspar: 11,984 TPA, Subgrade: 2140 TPA Waste: 4280 TPA and overburden: 4534 TPA}

Khasra No. 62/613, 63, 64, 65/1, 65/2, Add.- Rampuriya, Tehsil- Sahara, District- Bhilwara,

(Raj.) (Proposal No.- 209709). The project is covered under B2 category. The ADM,

Udaipur vide order dated 23.02.2021 has issued LoI to the PP for mining of Quartz &

Feldspar. The mining plan has been approved by the SME, Bhilwara vide letter dated

09.04.2021. AME, Bhilwara in his certificate dated 19.03.2021 has stated that the mining

lease does not fall in Aravalli hills. DCF, Bhilwara and DCF, WL, Chittorgarh in their

certificates dated 26.04.2021 and 22.07.2021, respectively have stated that there is no

Wildlife Sanctuary/National Park/ Conservation Reserve within 10 km periphery of the mine.

The project does not involve approval/ clearance under the Forest (Conservation) Act, 1980

and Wild Life Protection Act, 1972 as no forest land is involved and neither there is any Wild

Life Sanctuary/ National Park within 10 Km from the project site.

The SEAC considered the certificate dated 19.03.2021 issued by AME, Bhilwara In

the certificate, it is stated that as per the MoEF & CC notification, dated 01.07.2016 there is

no other mining lease within the periphery of 500 meter and therefore, there is no cluster

formation.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-1,

Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri- Shankar

Lal Jat S/o Shri- Bhura Lal Jat for Quartz Feldspar Mining Project, M.L. No. 58/2020, Area

1.0882 Ha., Production Capacity 25,934 TPA (ROM){Quartz : 2996 TPA, Feldspar: 11,984

TPA, Subgrade: 2140 TPA Waste: 4280 TPA and overburden: 4534 TPA}, Khasra No.

62/613, 63, 64, 65/1, 65/2, Add.- Rampuriya, Tehsil- Sahara, District- Bhilwara, (Raj.)

(Proposal No.- 209709), with the stipulation that the PP shall abide by the annual production

scheduled specified in mining plan and that any deviation there in will render the PP liable

for legal action in accordance with Environment and Mining Laws, with the specific and

general conditions annexed at Annexure ‘A’. Name of Proponent Shri- Shankar Lal Jat S/o

Shri- Bhura Lal Jat, Add.- Rampuriya, Post- Lakhola, Tehsil- Sahada, Distt.- Bhilwara,

(Raj.), Email- [email protected], Consultant Name:- Fulgro Environmental &

Engineering Services India Pvt. Ltd., Add-27, Ashok Vatika, Khatipura Road, Jhotwara,

Jaipur, (Raj.), Email:- [email protected].

Agenda no. 15. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19622)/ 2019-20

Project Name- EC for Granite Mining Project, M.L. No. 24/2021, Ref. No.

20211000034409, Area 2.1528 Ha., Production Capacity 1,48,383 TPA (ROM){ Granite

(Blockable) : 44,168 TPA, Granite khanda (non blockable): 89,377 TPA, Waste: 14,838

TPA}, Khasra No. 2525, 2545, 4052/2524, 4478/2526, Add.- Bachhkhera, Tehsil- Shahpura,

District- Bhilwara, (Raj.) (Proposal No.- 215008).

Final minutes of 4.95th meeting held on 27-29 July, 2021

Project Proponent Name- Smt. Sangita Devi W/o Shri- Hemraj Khatik, Add.- Ward No.

06, Khatik Mohalla Bachhkhera, Tehsil- Shahpura, Distt.- Bhilwara, (Raj.), Email-

[email protected].

Consultant Name- Fulgro Environmental & Engineering Services India Pvt. Ltd., Add-27,

Ashok Vatika, Khatipura Road, Jhotwara, Jaipur, (Raj.), Email:[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category /

Item no. (in

Schedule):

1 (a) /Category-B2

2. Location of Project

Near Village - Bachhkhera, Tehsil - Shahpura, District – Bhilwara, Rajasthan

Khasra No. 2525, 2545, 4052/2524, 4478/2526

3. Project Details

REF.

No./Production capacity

M.L. No. 24/2021, Ref. No.- 20211000034409, Area- 2.1528 ha

Proposed Production capacity: 1,48,383 TPA(ROM)

(Production of Granite (Blockable): 44,168 TPA,

Granite Khanda (Non Blockable): 89,377 TPA, Waste: 14,838 TPA) 4. Project Cost Rs. 1.00 Crore

5. Water

Requirement & Source

Total Water Requirement-5.41KLD

Source: Water will be made available from nearby village Bachhkhera via water tanker supply.

6. Fuel &Energy: - Diesel operated machinery will be used. Fuel will be required for the operation of

mines machineries and transportation vehicles which will be taken care by the

contractor itself. One D.G. Set of 15 KVA is also proposed. Electricity connection will

be taken from concerned electricity department.

7. Application No. & Date &

documents

submitted: -

Online Proposal No. SIA/RJ/MIN/215008/2021

Documents:FORM-I & PFR along with approved mining plan & all the requisite

documents for grant of EC have been submitted.

8. Information about

Aravalli

Certificate.

Aravalli Certificate was issued by ME, Bhilwara vide letter no.

ME/Bhil/MAP/(Cluster/M.L. 24/2021/246 dated 07/06/2021.

9. Date of Air/Water/Noise

Monitoring

Date of Air Monitoring: - 11/06/2021 Date of Water Sampling: - 11/06/2021

Date of Noise Monitoring: 11/06/2021

10. Information about 500 mts

composite map

Cluster certificate was issued by ME, Bhilwara vide letter no. ME/Bhil/MAP(Cluster/M.L.

24/2021/246 dated 07/06/2021. No other mine lease is existing within 500 m radius of the

said mine lease area.

Final minutes of 4.95th meeting held on 27-29 July, 2021

11. Environment Management

Plan

Annual Expenditure of Rs. 5.00 Lac Per year

S. No. Description Recurring Cost (Rs. in

lacs)

1 Air, Water & Noise pollution

monitoring

1.00

2 Water Requirement (For dust

suppression and green belt/plantation

purpose)

1.65

3 Green belt (including plant cost, tree

guard and its maintenance)

0.60

4 Contribution towards construction and

maintenance of the kachha roads after

consultation with the concerned gram

Panchayat and local people

1.75

Total 5.00

12 GreenBelt/

Plantation

Annual expenditure of Rs. 0.60Lac Per Year (Recurring Cost)

Total 1167 saplings will be planted over an area of 1.1673 hectare. Out of which 391

saplings will be planted within the first three years over an area of 0.3912 hectare at the undisturbed area and to complete 33% of the total plantation 319 saplings will be planted

outside the mine lease over an area of 0.3192 hectare in the remaining part of own Khasra

No. 2525. At the end of life of mine 457 saplings will be planted over the backfilled area of 0.4569 hectare and it will be ensured that after ceasing mining operations re-grassing of the

mining area and any other area which may have been disturbed due to the mining activities

is done and will restore the land to a condition which is fit for growth of fodder, flora, fauna

etc. as per the MoEF& CC O.M vide No. 22-34/2018-IA.III dated 16th Jan 2020. Native species which are more suitable to the local environment are preferred to be planted such as

Neem, Pipal, Sheesham, Mango etc.

Year Un-worked Area

Outside the mine

lease areaown

Khasra

Backfilled

Area Total

Area

(Ha)

No. of

Trees

Area

(Ha)

No. of

Trees

Area

(Ha)

No.

of Trees

Area

(Ha)

No. of

Trees

Existing - - - - - - - -

I 0.1304 130 0.1064 106 - - 0.2368 236

II 0.1304 130 0.1064 106 - - 0.2368 236

III 0.1304 131 0.1064 107 - - 0.2368 238

IV

MAINTENANCE

TO BE DONE

MAINTENANCE

TO BE DONE

- - MAINTENANCE

TO BE DONE V - -

At the

end of

life of

Mine

0.4569 457 0.4569 457

Total 0.3912 391 0.3192 319 0.4569 457 1.1673 1167

Final minutes of 4.95th meeting held on 27-29 July, 2021

13 Budgetary Breakup for

Labours

Annual Expenditure of Rs. 2.41700Lac Per year

Sr.

No. Facility Provided for Laborers

Capital

Cost in

Rs.

Recurring

Cost in Rs.

1. Shelters, Safe drinking water, Sanitation

facility

1,00,000

Maintenance

Cost: 30,000

3. Periodical medical examination per year

@1000 Rs. per labor

28,000

4. Fuel for cooking (LPG Cylinder) @950

Per cylinder. 9,500

5. Books and Uniforms for children of labors

@2,400 per labor 67,200

6. Group Insurance @ Rs.1500 per worker 42,000 -

7.

Provision for personal protection

equipment (PPEs) like ear plug, face

mask, Helmet, shoes etc., for 28 workers

Safety shoes@350 Rs (2

times/year)

Hand Gloves @300 Rs (2

times/year)

Face mask@25 Rs (2 times in 10

month)

Ear plugs@25 Rs (2 times in 10

month)

Helmets @450 Rs (1 times/year)

19,600

16,800

14,000

14,000

12,600

8. First Aid Box 10,000

9. Fire Safety 30,000 20,000

Total 1,72,000 2,41,700

14 Present Status Fresh LOI now proposed for the grant of Environmental Clearance.

Observations of the committee:-

The SEAC considered/examined the project proposal on 27.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for EC for Granite Mining Project, M.L. No.

24/2021, Ref. No. 20211000034409, Area 2.1528 Ha., Production Capacity 1,48,383 TPA

(ROM){ Granite (Blockable) : 44,168 TPA, Granite khanda (non blockable): 89,377 TPA,

Waste: 14,838 TPA }, Khasra No. 2525, 2545, 4052/2524, 4478/2526, Add.- Bachhkhera,

Tehsil- Shahpura, District- Bhilwara, (Raj.) (Proposal No.- 215008). The project is covered

under B2 category. The SME, Bhilwara vide order dated 07.04.2021 has issued LoI to the PP

for mining of Granite. The mining plan has been approved by the SME, Bhilwara vide letter

dated 02.06.2021. AME, Bhilwara in his certificate dated 07.06.2021 has stated that the

mining lease does not fall in Aravalli hills. DCF, Bhilwara and DCF, Ajmer in their

certificates dated 22.06.2021 and 26.07.2021, respectively have stated that there is no

Wildlife Sanctuary/National Park/ Conservation Reserve within 10 km periphery of the mine.

Final minutes of 4.95th meeting held on 27-29 July, 2021

DCF, Bhilwara in his certificate dated 22.06.2021 state that the nearest forest land Beed

Lasadiya is at about 6 km from the applied mining lease area. The project does not involve

approval/ clearance under the Forest (Conservation) Act, 1980 and Wild Life Protection Act,

1972 as no forest land is involved and neither there is any Wild Life Sanctuary/ National Park

within 10 Km from the project site.

The SEAC considered the certificate dated 07.06.2021 issued by AME, Bhilwara In

the certificate, it is stated that as per the MoEF & CC notification, dated 01.07.2016 there is

no other mining lease within the periphery of 500 meter and therefore, there is no cluster

formation.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1, Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Smt. Sangita

Devi W/o Shri- Hemraj Khatik, for Granite Mining Project, M.L. No. 24/2021, Ref. No.

20211000034409, Area 2.1528 Ha., Production Capacity 1,48,383 TPA (ROM) {Granite

(Blockable) : 44,168 TPA, Granite khanda (non blockable): 89,377 TPA, Waste: 14,838

TPA}, Khasra No. 2525, 2545, 4052/2524, 4478/2526, Add.- Bachhkhera, Tehsil- Shahpura,

District- Bhilwara, (Raj.) (Proposal No.- 215008), with the stipulation that the PP shall

abide by the annual production scheduled specified in mining plan and that any deviation

there in will render the PP liable for legal action in accordance with Environment and Mining

Laws, with the specific and general conditions annexed at Annexure ‘A’. Name of

Proponent Smt. Sangita Devi W/o Shri- Hemraj Khatik, Add.- Ward No. 06, Khatik

Mohalla Bachhkhera, Tehsil- Shahpura, Distt.- Bhilwara, (Raj.), Email-

[email protected], Consultant Name:- Fulgro Environmental & Engineering Services

India Pvt. Ltd., Add-27, Ashok Vatika, Khatipura Road, Jhotwara, Jaipur, (Raj.), Email:-

[email protected].

Agenda no. 16. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19633)/ 2019-20

Project Name- EC for Granite Mining Project, M.L. No. 31/2021, Plot no- 65, Area 1.0982

Ha., Production Capacity 1,15,830 TPA (ROM){ Granite: 69,498 TPA, Waste : 46,332

TPA}, Khasra No. 1772, 1773, 1774, 1775, Add.- Mankhand, Tehsil- Kekri, District- Ajmer,

(Raj.) (Proposal No.- 216498).

Project Proponent Name- Shri- Amit Nayyar S/o Shri- Praveen Kumar Nayyar, Add.- C-

17, Shalimar Colony, Adarsh Nagar, Ajmer, Distt.- Ajmer, (Raj.), Email-

[email protected].

Consultant Name- Fulgro Environmental & Engineering Services India Pvt. Ltd., Add-27,

Ashok Vatika, Khatipura Road, Jhotwara, Jaipur, (Raj.), Email:- [email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category /

Item no. (in Schedule):

1 (a) /Category-B2

Final minutes of 4.95th meeting held on 27-29 July, 2021

2. Location of Project

Near Village- Mankhand, Tehsil: Kekri, District: Ajmer, Rajasthan

Khasra No. 1772,1773,1774, 1775

3. Project Details

REF.

No./Production capacity

M.L. No. 31/2021, Delineated Plot No. 65, Area-1.0982 ha

Proposed Production capacity: 1,15,830 TPA (ROM)

(Production of Granite: 69,498 TPA, Waste: 46,332 TPA)

4. Project Cost Rs. 1.00 Crore

5. Water

Requirement & Source

Total Water Requirement-4.20KLD

Source: Water will be made available by nearby villageMankhandthrough water tanker.

6. Fuel &Energy: - Diesel operated machinery will be used. Fuel will be required for the operation of mines

machineries and transportation vehicles which will be taken care by the contractor itself.

Electricity connection will be taken from concerned electricity department.

7. Application No. & Date &

documents

submitted: -

Online Proposal No. SIA/RJ/MIN/216498/2021

Documents:FORM-I & PFR along with approved mining plan & all the requisite documents

for grant of EC have been submitted.

8. Information about

Aravalli

Certificate.

Aravalli Certificate was issued by AME, Sawar vide letter no. AME/Sawar/MAP/(L.O.I.)-

31/2021 (Plot No. 65)/106 dated 21/05/2021

9. Date of

Air/Water/Noise

Monitoring

Date of Air Monitoring: - 13/06/2021

Date of Water Sampling: - 13/06/2021

Date of Noise Monitoring: 13/06/2021

10. Information about 500 mts

composite map

Cluster certificate was issued by AME, Sawar vide letter no. AME/Sawar/MAP/ (L.O.I.)-

31/2021(Plot No. 65)/107 dated 21/05/2021. One other mine lease is existing within 500 m

radius of the said mine lease area.

11. Environment

Management

Plan

Annual Expenditure of Rs. 5.00 Lac Per year

S. No. Description Recurring Cost (Rs. in

lacs)

1 Air, Water & Noise pollution monitoring 1.00

2 Water Requirement (For dust suppression and

green belt/plantation purpose) 1.50

3 Green belt/Plantation (including plant cost, tree

guard and its maintenance) 0.50

4

Contribution towards construction and

maintenance of the kachha roads after

consultation with the concerned gram Panchayat

and local people

2.00

Total 5.00

12 GreenBelt/

Plantation

Annual expenditure of Rs. 0.50Lac Per Year (Recurring Cost)

Year Un-worked Area Outside the mine

lease area

(Backfilled

Area)

Top Soil

Dumps Total

Area (Ha)

No. of Trees

Area (Ha)

No. of Trees

Area (Ha)

No. of

Trees

Area (Ha)

No. of

Trees

Area (Ha)

No. of Trees

Existing - - - - - - - - - -

I 0.0860 86 0.0347 34 - - - - 0.1207 120

II 0.0860 86 0.0347 35 - - - - 0.1207 121

III 0.0860 86 0.0348 35 - - - - 0.1208 121

IV MAINTENANCE

TO BE DONE MAINTENANCE

TO BE DONE

- - - - MAINTENANCE

TO BE DONE V - - - -

At the 0.5000 500 - - 0.5000 500

Final minutes of 4.95th meeting held on 27-29 July, 2021

Note:Total 862 saplings will be planted over an area of 0.8622 hectare (33% of the mine

lease area) Out of which 258 saplings will be planted over the undisturbed area of 0.2582 hectare within the first three years and to complete 33%of the total plantation 104 saplings

will be planted outside the mine lease over an area of 0.1042 ha in Khasra no. 1652,1404

&544 of Gram panchayat Mankhand. At the end of life of mine 500 saplings will be planted over the backfilled area of 0.5000 ha and it will be ensured that after ceasing mining

operations re-grassing of the mining area and any other area which may have been disturbed

due to the mining activities is done and will restore the land to a condition which is fit for growth of fodder, flora, fauna etc. as per the MoEF& CC O.M vide No. 22-34/2018-IA.III

dated 16th Jan 2020. Native species which are more suitable to the local environment are

preferred to be planted such as Neem, Pipal, Sheesham, Mango etc.

end of life of Mine

Total 0.2582 258 0.1042 104 0.5000 500 - - 0.8622 862

13 Budgetary Breakup for

Labours

Annual Expenditure of Rs. 1.92500Lac Per year

Sr.

No. Facility Provided for Laborers

Capital

Cost in Rs.

Recurring Cost

in Rs.

1. Shelters, Safe drinking water, Sanitation

facility

1,00,000 Maintenance Cost:

30,000

3. Periodical medical Examination per year

@1000 Rs. per labor

20,000

4. Fuel for cooking (LPG Cylinder) @ 950

Rs. for 10 months 9,500

5. Education for children of labors @ 2,400

Rs. per labor 48,000

6. Group Insurance @1500 Rs. per worker 30,000 -

7.

Provision for personal protection

equipment (PPEs) like ear plug, dust mask,

Helmet, shoes etc., for 20 workers

Safety shoes@350 Rs (2

times/year)

Hand Gloves @300 Rs (2

times/year)

Dust mask@25 Rs (2 times in

month)

Ear plugs@25 Rs (2 times in

month)

Helmets @450 Rs (1 time/years)

14,000

12,000

10,000

10,000

9,000

8. First Aid Box 10,000

9. Fire Safety 30,000 20,000

Total 1,60,000 1,92,500

14 Present Status Fresh LOI now proposed for the grant of Environmental Clearance.

Observations of the committee:-

The SEAC considered/examined the project proposal on 27.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

Final minutes of 4.95th meeting held on 27-29 July, 2021

The PP has submitted EC for Granite Mining Project, M.L. No. 31/2021, Plot no- 65,

Area 1.0982 Ha., Production Capacity 1,15,830 TPA (ROM){ Granite: 69,498 TPA, waste

:46,332 TPA}, Khasra No. 1772, 1773, 1774, 1775, Add.- Mankhand, Tehsil- Kekri,

District- Ajmer, (Raj.) (Proposal No.- 216498). The project is covered under B2 category.

The SME, Ajmer vide order dated 18.03.2021 has issued LoI to the PP for mining of Granite.

The mining plan has been approved by the SME, Ajmer vide letter dated 10.06.2021. AME,

Sawar in his certificate dated 21.05.2021 has stated that the mining lease does not fall in

Aravalli hills. DCF, Ajmer and DCF, Tonk in their certificates dated 16.07.2021 and

23.02.2021, respectively have stated that there is no Wildlife Sanctuary/National Park/

Conservation Reserve within 10 km periphery of the mine. Besides, the PP in Form-1 has

also stated that there is no WLS, National Park and Conservation Reserve within 10 Km of

the project site.

The project does not involve approval/ clearance under the Forest (Conservation) Act,

1980 and Wild Life Protection Act, 1972 as no forest land is involved and neither there is any

Wild Life Sanctuary/ National Park within 10 Km from the project site.

As per cluster certificate issued by AME, Sawar on 21.05.2021, the total area of all the

mining leases in the cluster having area of 2.3785 ha.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1,Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri- Amit

Nayyar S/o Shri- Praveen Kumar Nayyar, for Granite Mining Project, M.L. No. 31/2021,

Plot no- 65, Area 1.0982 Ha., Production Capacity 1,15,830 TPA (ROM) {Granite: 69,498

TPA, Waste :46,332 TPA}, Khasra No. 1772, 1773, 1774, 1775, Add.- Mankhand, Tehsil-

Kekri, District- Ajmer, (Raj.) (Proposal No.- 216498), with the stipulation that the PP shall

abide by the annual production scheduled specified in mining plan and that any deviation

there in will render the PP liable for legal action in accordance with Environment and Mining

Laws, with the specific and general conditions annexed at Annexure ‘A’. Name of

Proponent Shri- Amit Nayyar S/o Shri- Praveen Kumar Nayyar, Add.- C-17, Shalimar

Colony, Adarsh Nagar, Ajmer, Distt.- Ajmer, (Raj.), Email- [email protected],

Consultant Name:- Fulgro Environmental & Engineering Services India Pvt. Ltd., Add-27,

Ashok Vatika, Khatipura Road, Jhotwara, Jaipur, (Raj.), Email:- [email protected].

Agenda no. 17. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19634)/ 2019-20

Project Name- EC for Granite Mining Project, M.L. No. 32/2021, Plot no- 67, Area 1.0257

Ha., Production Capacity 1,15,830 TPA (ROM){ Granite: 69498 TPA, Waste : 46,332

TPA}, Khasra No. 1772, 1773, 1774, 1775, Add.- Mankhand, Tehsil- Kekri, District- Ajmer,

(Raj.) (Proposal No.- 216472).

Project Proponent Name- Shri- Amit Nayyar S/o Shri- Praveen Kumar Nayyar, Add.- C-

17, Shalimar Colony, Adarsh Nagar, Ajmer, Distt.- Ajmer, (Raj.), Email-

[email protected].

Final minutes of 4.95th meeting held on 27-29 July, 2021

Consultant Name- Fulgro Environmental & Engineering Services India Pvt. Ltd., Add-27,

Ashok Vatika, Khatipura Road, Jhotwara, Jaipur, (Raj.), Email:- [email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category /

Item no. (in

Schedule):

1 (a) /Category-B2

2. Location of Project

Near Village- Mankhand, Tehsil: Kekri, District: Ajmer, Rajasthan

Khasra No. 1772,1773,1774, 1775

3. Project Details

REF.

No./Production capacity

M.L. No. 32/2021, Delineated Plot No. 67, Area- 1.0257 ha

Proposed Production capacity: 1,15,830 TPA (ROM)

(Production of Granite: 69,498 TPA, Waste: 46,332 TPA) 4. Project Cost Rs. 1.00 Crore

5. Water

Requirement & Source

Total Water Requirement-4.00KLD

Source: Water will be made available by nearby villageMankhandthrough water tanker.

6. Fuel &Energy: - Diesel operated machinery will be used. Fuel will be required for the operation of mines

machineries and transportation vehicles which will be taken care by the contractor itself.

Electricity connection will be taken from concerned electricity department.

7. Application No. & Date &

documents

submitted: -

Online Proposal No. SIA/RJ/MIN/216472/2021

Documents:FORM-I & PFR along with approved mining plan & all the requisite documents

for grant of EC have been submitted.

8. Information

about

Aravalli

Certificate.

Aravalli Certificate was issued by AME, Sawar vide letter no. AME/Sawar/MAP/(L.O.I.)-

32/2021/108 dated 21/05/2021.

9. Date of

Air/Water/Noise

Monitoring

Date of Air Monitoring: - 13/06/2021

Date of Water Sampling: - 13/06/2021

Date of Noise Monitoring: 13/06/2021

10. Information about 500 mts

composite map

Cluster certificate was issued by AME, Sawar vide letter no. AME/Sawar/MAP/ (L.O.I.)-

32/2021(Plot No. 67)/109 dated 21/05/2021. One other mine lease is existing within 500 m

radius of the said mine lease area

11. Environment

Management

Plan

Annual Expenditure of Rs. 5.00 Lac Per year

S. No. Description Recurring Cost (Rs. in

lacs)

1 Air, Water & Noise pollution monitoring 1.00

2 Water Requirement (For dust suppression and

green belt/plantation purpose) 1.50

3 Green belt/Plantation (including plant cost, tree

guard and its maintenance) 0.40

4

Contribution towards construction and

maintenance of the kachha roads after

consultation with the concerned gram Panchayat

and local people

2.10

Total 5.00

Final minutes of 4.95th meeting held on 27-29 July, 2021

12 GreenBelt/ Plantation

Annual expenditure of Rs. 0.40Lac Per Year (Recurring Cost)

Note:Total 839 saplings will be planted over an area of 0.8384 hectare (more than 33% of the mine lease area) Out of which 186 saplings will be planted over the undisturbed area of

0.1857 hectare within the first three years and to complete 33 % of the total plantation 153

saplings will be planted outside the mine lease over an area of 0.1527 ha in khasra no. 1652,1404 & 544 of Gram Panchayat Mankhand. At the end of the life of mine 500 saplings

will be planted at the backfilled area of 0.5000 ha and it will be ensured that after ceasing

mining operations re-grassing of the mining area and any other area which may have been

disturbed due to the mining activities is done and will restore the land to a condition which is fit for growth of fodder, flora, fauna etc. as per the MoEF& CC O.M vide No. 22-34/2018-

IA.III dated 16th Jan 2020. Native species which are more suitable to the local environment

are preferred to be planted such as Neem, Pipal, Sheesham, Mango etc.

Year Un-worked Area Outside the mine

lease area

(Backfilled

Area)

Top Soil

Dumps Total

Area

(Ha)

No. of

Trees

Area

(Ha)

No. of

Trees

Area

(Ha)

No. of

Trees

Area

(Ha)

No. of

Trees

Area

(Ha)

No. of

Trees

Existing - - - - - - - - - -

I 0.0619 62 0.0509 51 - - - - 0.1128 113

II 0.0619 62 0.0509 51 - - - - 0.1128 113

III 0.0619 62 0.0509 51 - - - - 0.1128 113

IV

MAINTENANCE

TO BE DONE MAINTENANCE

TO BE DONE

- - - - MAINTENANCE

TO BE DONE V - - - -

At the end of life of Mine

0.5000 500

- -

0.5000 500

Total 0.1857 186 0.1527 153 0.5000 500 - - 0.8384 839

13 Budgetary

Breakup for

Labours

Annual Expenditure of Rs. 1.92500Lac Per year

Sr.

No. Facility Provided for Laborers

Capital

Cost in Rs.

Recurring Cost

in Rs.

1. Shelters, Safe drinking water, Sanitation

facility

1,00,000 Maintenance Cost:

30,000

3. Periodical medical Examination per year

@1000 Rs. per labor

20,000

4. Fuel for cooking (LPG Cylinder) @ 950

Rs. for 10 months 9,500

5. Education for children of labors @ 2,400

Rs. per labor 48,000

6. Group Insurance @1500 Rs. per worker 30,000 -

7.

Provision for personal protection

equipment (PPEs) like ear plug, dust mask,

Helmet, shoes etc., for 20 workers

Safety shoes@350 Rs (2

times/year)

Hand Gloves @300 Rs (2

times/year)

Dust mask@25 Rs (2 times in

month)

Ear plugs@25 Rs (2 times in

month)

14,000

12,000

10,000

10,000

9,000

Final minutes of 4.95th meeting held on 27-29 July, 2021

Helmets @450 Rs (1 time/years)

8. First Aid Box 10,000

9. Fire Safety 30,000 20,000

Total 1,60,000 1,92,500

14 Present Status Fresh LOI now proposed for the grant of Environmental Clearance.

Observations of the committee:-

The SEAC considered/examined the project proposal on 27.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted EC for Granite Mining Project, M.L. No. 32/2021, Plot no-

67, Area 1.0257 Ha., Production Capacity 1,15,830 TPA (ROM){ Granite: 69498 TPA,

Waste : 46,332 TPA}, Khasra No. 1772, 1773, 1774, 1775, Add.- Mankhand, Tehsil- Kekri,

District- Ajmer, (Raj.) (Proposal No.- 216472). The project is covered under B2 category.

The SME, Ajmer vide order dated 18.03.2021 has issued LoI to the PP for mining of Granite.

The mining plan has been approved by the SME, Ajmer vide letter dated 10.06.2021. AME,

Sawar in his certificate dated 21.05.2021 has stated that the mining lease does not fall in

Aravalli hills. DCF, Ajmer and DCF, Tonk in their certificates dated 16.07.2021 and

23.02.2021, respectively have stated that there is no Wildlife Sanctuary/National Park/

Conservation Reserve within 10 km periphery of the mine. Besides, the PP in Form-1 has

also stated that there is no WLS, National Park and Conservation Reserve within 10 Km of

the project site.

The project does not involve approval/ clearance under the Forest (Conservation) Act,

1980 and Wild Life Protection Act, 1972 as no forest land is involved and neither there is any

Wild Life Sanctuary/ National Park within 10 Km from the project site.

As per cluster certificate issued by AME, Sawar on 21.05.2021, the total area of all the

mining leases in the cluster having area of 2.3060 ha.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1,Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri Amit

Final minutes of 4.95th meeting held on 27-29 July, 2021

Nayyar S/o Shri- Praveen Kumar Nayyar for Granite Mining Project, M.L. No. 32/2021,

Plot no- 67, Area 1.0257 Ha., Production Capacity 1,15,830 TPA (ROM){ Granite: 69,498

TPA, Waste : 46,332 TPA}, Khasra No. 1772, 1773, 1774, 1775, Add.- Mankhand, Tehsil-

Kekri, District- Ajmer, (Raj.) (Proposal No.- 216472), with the stipulation that the PP shall

abide by the annual production scheduled specified in mining plan and that any deviation

there in will render the PP liable for legal action in accordance with Environment and Mining

Laws, with the specific and general conditions annexed at Annexure ‘A’. Name of

Proponent Shri- Amit Nayyar S/o Shri- Praveen Kumar Nayyar, Add.- C-17, Shalimar

Colony, Adarsh Nagar, Ajmer, Distt.- Ajmer, (Raj.), Email- [email protected],

Consultant Name:- Fulgro Environmental & Engineering Services India Pvt. Ltd., Add-27,

Ashok Vatika, Khatipura Road, Jhotwara, Jaipur, (Raj.), Email:- [email protected].

Agenda no. 18. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19110)/ 2019-20

Project Name- Environmental Clearance for Red Ochre Mining Project, ML. No.- 2/2020,

Ref. No.- 20201000021155, QL. Area- 2.0069 ha., Production Capacity- 72,900 TPA {Red

Ochre- 72,900 TPA, Waste- nil}, Khasra No.- 818, 819, 822, 825, Near Vill.- Akhepur,

Tehsil & Distt.- Pratapgarh (Raj.) (Proposal No.-193480).

Project Proponent Name- Smt. Resham Bai W/o Late Sh. Sukhnath, Add.- House No.-8,

Ward No.01,Jadwasa,Distt.-Ratlam(MP) [email protected].

Consultant Name- Fulgro Environmental & Engineering Services India Pvt. Ltd., Add-27,

Ashok Vatika, Khatipura Road, Jhotwara, Jaipur,(Raj.)Email:[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category /

Item no. (in

Schedule):

1 (a) /Category-B2

2. Location of

Project Located at Khasra No. 818, 819, 822, 825

Near Village-Akhepur, Tehsil- Pratapgarh & District-Pratapgarh (Raj.)

3. Project Details REF.

No./Production

capacity

M.L. No.- 2/2020, Ref. No. 20201000021155, Area-2.0069 ha

Production capacity: 72,900 TPA

(Production of Red Ochre: 72,900 TPA, Waste: Nil) 4. Project Cost Rs. 0.40 Crore

5. Water

Requirement & Source

Total Water Requirement-3.02KLD

Source: Water will be made available from nearby village Akhepurvia water tanker supply.

6. Fuel &Energy: - Diesel operated machinery will be used. Fuel will be required for the operation of mines

machineries and transportation vehicles which will be taken care by the contractor itself.

Electricity connection will be taken from concerned electricity department.

7. Application No. & Date &

documents

submitted: -

Online Proposal No. SIA/RJ/MIN/193480/2021

Documents:FORM-I & PFR along with approved mining plan & all the requisite documents

for grant of EC have been submitted.

8. Information

about

Aravalli

Certificate.

Aravalli Certificate was issued by ME, Pratapgarh vide letter no. ME/Pratap/CC-Minor/M.L.

02/2020/2020-21/7766 dated 24/12/2020

Final minutes of 4.95th meeting held on 27-29 July, 2021

9. Date of Air/Water/Noise

Monitoring

Date of Air Monitoring: - 04/01/2021 Date of Water Sampling: - 04/01/2021

Date of Noise Monitoring: 04/01/2021

10. Information

about 500 mts composite map

Cluster certificate was issued by ME, Pratapgarh vide letter no. ME/Pratap/CC-Minor/M.L.

02/2020/2020-21/945 dated 22/07/2021. No other mine lease is existing within 500 m radius

of the said mine lease area.

11. Environment

Management

Plan

Annual Expenditure of Rs 2.50Lac Per year

S.

No. Particulars

Recurring cost

(in Rs. Lac)

5. Air, Water & Noise pollution monitoring 1.00

6. Water Requirement (For dust suppression and

green belt/plantation purpose) 0.90

7. Green belt (including plant cost, tree guard and its

maintenance) 0.50

8. Contribution towards construction and maintenance of the kachha roads after consultation with the concerned

gram Panchayat and local people

0.10

Total 2.50

12 GreenBelt/

Plantation

Annual expenditure of Rs. 0.50Lac Per Year (Recurring Cost)

Note:Total 1945 saplings will be planted over an area of 1.9444 ha. (more than 33% of the

mine lease area). Out of which 662 saplings will be planted within first three years of mining

at undisturbed area of 0.6620 Ha. within mining lease area. At the end of life of mine 1283 saplings will be planted at the backfilled area of 1.2824 ha.and it will be ensured that after

ceasing mining operations re-grassing of the mining area and any other area which may have

been disturbed due to the mining activities is done and will restore the land to a condition

which is fit for growth of fodder, flora, fauna etc. as per the MoEF& CC O.M vide No. 22-34/2018-IA.III dated 16th Jan 2020. Native species which are more suitable to the local

environment are preferred to be planted such as Shisam, Neem, Pipal, Babul, etc.

Year Undisturbed

Area

Outside the

mine lease

area in own

Khasra

Top Soil

Dumps

Backfilled

Area Total

Area

(Ha)

No. of

Trees

Area

(Ha)

No. of

Trees

Area

(Ha)

No. of

Trees

Area

(Ha)

No. of

Trees Area (Ha)

No. of

Trees

Existing -- -- -- -- -- -- -- --

-- --

I 0.2207 221 -- -- -- -- -- -- 0.2207 221

II 0.2207 221 -- -- -- -- -- -- 0.2207 221

III 0.2206 220 -- -- -- -- -- -- 0.2206 220

IV

MAINTENANCE TO BE

DONE

-- -- -- -- MAINTENANCE

TO BE DONE V -- -- -- --

End of

life of

mine

-- -- 1.2824 1283 1.2824 1283

Total 0.6620 662 -- -- -- -- 1.2824 1283 1.9444 1945

Final minutes of 4.95th meeting held on 27-29 July, 2021

13 Budgetary Breakup for

Labours

Annual Expenditure of Rs. 1.310 Lac Per year

Sr.

No. Facility Provided for Laborers

Capital Cost

in Rs.

Recurring Cost

in Rs.

1. Shelters, Safe drinking water,

Sanitation facility

1,00,000

Maintenance

Cost: 30,000

2. Periodical medical Examination per

year @1000 Rs. per labor

10,000

3. Fuel for cooking (LPG Cylinder) @950 Rs.

Per month 9,500

4. Books/Uniform for children of labors @

2,400 Rs. per labor 24,000

5. Group Insurance @1500 Rs. per worker 15,000 -

6.

Provision for personal protection

equipment (PPEs) like ear plug, face mask,

Helmet, shoes etc., for 10 workers

Safety shoes@350 Rs (2

times/year)

Hand Gloves @300 Rs (2

times/year)

Face mask@25 Rs (2 times in

month)

Ear plugs@25 Rs (2 times in

month)

Helmets @450 Rs(1 time/years)

7,000

6,000

5,000

5,000

4,500

7. First Aid Box 10,000

8. Fire Safety 30,000 20,000

Total 1,45,000 1,31,000

14 Present Status Fresh LOI now proposed for the grant of Environmental Clearance.

Observations of the committee:-

The SEAC considered/examined the project proposal on 27.07.2021by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application Environmental Clearance for Red Ochre Mining

Project, ML. No.- 2/2020, Ref. No.- 20201000021155, QL. Area- 2.0069 ha., Production

Capacity- 72,900 TPA {Red Ochre- 72,900 TPA, Waste- nil}, Khasra No.- 818, 819, 822,

825, Near Vill.- Akhepur, Tehsil & Distt.- Pratapgarh (Raj.) (Proposal No.-193480). The

project is covered under B2 category. The ADM, Udaipur vide order dated 21.09.2020 has

issued LoI to the PP for mining of Red Ochre. The mining plan has been approved by the

SME, Udaipur vide letter dated 04.12.2020. AME, Pratapgarh in his certificate dated

24.12.2020 has stated that the mining lease does not fall in Aravalli hills. DCF, Chittorgarh

and DFO, Mandsaur in their certificates dated 04.01.2020 and 20.07.2021, respectively have

stated that there is no Wildlife Sanctuary/National Park/ Conservation Reserve within 10 km

periphery of the mine. The DCF, Chittorgarh has also stated that the nearest Sitamata WLS is

at a distance of 25.0 Km from the applied lease area.

Final minutes of 4.95th meeting held on 27-29 July, 2021

The project does not involve approval/ clearance under the Forest (Conservation) Act,

1980 and Wild Life Protection Act, 1972 as no forest land is involved and neither there is any

Wild Life Sanctuary/ National Park within 10 Km from the project site.

As per cluster certificate issued by ME, Pratapgarh on 22.07.2021, the total area of all

the mining leases in the cluster having area of 2.0069 ha.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-1,

Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Smt. Resham

Bai W/o Late Sh. Sukhnath, for Red Ochre Mining Project, ML. No.- 2/2020, Ref. No.-

20201000021155, QL. Area- 2.0069 ha., Production Capacity- 72,900 TPA {Red Ochre-

72,900 TPA, Waste- nil}, Khasra No.- 818, 819, 822, 825, Near Vill.- Akhepur, Tehsil &

Distt.- Pratapgarh (Raj.) (Proposal No.-193480), with the stipulation that the PP shall abide

by the annual production scheduled specified in mining plan and that any deviation there in

will render the PP liable for legal action in accordance with Environment and Mining Laws,

with the specific and general conditions annexed at Annexure ‘A’. Name of Proponent: Smt.

Resham Bhai W/o Late Sh. Sukhnath, Add.- House No.-8, Ward No.- 01, Jadwasa, Distt.-

Ratlam (MP), [email protected], Consultant Name:- Fulgro Environmental

& Engineering Services India Pvt. Ltd., Add-27, Ashok Vatika, Khatipura Road, Jhotwara,

Jaipur, (Raj.), Email:- [email protected].

Agenda no. 19. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B1(16617)/ 2019-20

Project Name- Application for approval of EIA/ EMP with respect to Bhawanipura & Sutra

Sandstone & Khanda mine Cluster No.1, Cluster area 27.1351 ha., comprising 8 mining

leases, with consolidated carrying capacity of 11,75,891.58 TPA and EC to Shri Nana Lal

Dhakar for Bhawanipura Sandstone & Khanda Mining Project, Ref. No. 2018100001552,

area- 1.0023 ha., Production Capacity 1,35,662 TPA at Khasra No. 138 & 140, Near

Village– Bhawanipura, Tehsil– Talera, Dist.- Bundi, (Raj.) (Proposal No. 61904).

Project Proponent Name- Shri Nana Lal Dhakar, Co-owners– 1. Shri Jagdish Chand

Dhakar, 2. Shri Rekh Lal Darad, 3. Shri Basanti Lal, Add.- E-820, Indra Vihar, Kota Distt.

Kota (Raj.), Email –[email protected].

Consultant Name- COGNIZANCE RESEARCH INDIA PRIVATE LTD. Add.- Office GT

– 20, Sec – 117, Noida (U.P.).

Observations of the committee:-

The SEAC considered for approval of EIA/ EMP with respect to Bhawanipura &

Sutra Sandstone & Khanda mine Cluster No.1, Cluster area 27.1351 ha., comprising 8 mining

leases, with consolidated carrying capacity of 11,75,891.58 TPA and EC to Shri Nana Lal

Dhakar for Bhawanipura Sandstone & Khanda Mining Project, Ref. No. 2018100001552,

area- 1.0023 ha., Production Capacity 1,35,662 TPA at Khasra No. 138 & 140, Near

Village– Bhawanipura, Tehsil– Talera, Dist.- Bundi, (Raj.) (Proposal No. 61904), in its

Final minutes of 4.95th meeting held on 27-29 July, 2021

4.95th meeting held on 28.07.2021 through VC/ electronic media in accordance with letter

dated 27.05.2020 of SEIAA, Rajasthan.

The project was also considered earlier in terms of OM dated 12.12.2018 of the MoEF

& CC by SEAC in its 4.42th meeting held on 09th July, 2020 prescribing ToR for undertaking

EIA studies and for preparing EMP as the size of the cluster in which the proposed project

lies exceeded 5.0 ha. The SEAC vide letter dated 30.07.2020 asked the PP to conduct EIA

studies and prepare EMP for the entire cluster in order to capture all the possible externalities.

One season post monsoon primary base line data of the ambient air quality PM2.5,

PM10, SO2 and NOX, Water Quality, Noise level, Soil quality and Flora and Fauna were

collected during Oct. 2019 to Dec. 2019.

The PP following the above decision got public notice published in 04.12.2020

edition of Dainik Bhaskar, Bundi and 04.12.2020 edition of Jaabaz Patrika, Bundi and for

holding public hearing for the entire cluster for ascertaining material concerns for local

affected persons and it such concerns into account in the EIA/EMP report.

Public hearing was accordingly held on 08.01.2021 at 03.30 PM at Gram panchayat

Office, Sutda “Jan Suvida Kendra Sutda”, Tehsil Talera and District Bundi, for the entire

cluster and with reference to application for EC for mining activity by Bhawanipura & Sutra

Sandstone & Khanda Mining Project, (Cluster no.-1, Cluster area- 27.1351 ha.), Ref. No.

2018100001552, area-1.0023 ha., Production Capacity 1,35,662 TPA at Khasra No. 138 &

140, Near Village– Bhawanipura, Tehsil – Talera, Disst.- Bundi, (Raj.), under the

Chairmanship of Sh. Amanullah Khan, Add. District Collector, Bundi and Sh. Rakesh Gupta,

Regional officer, RSPCB, Kota, was also present during public hearing.

The details of issue raised by the public and commitments made by the PP during

public hearing and the action plan for implementation thereof are as follows:-

S.

No.

Name of Person with

address

Queries/Suggestions Replies Time bound plan of

action with

financial allocation

for cluster

1. Shri Papu Singh, Sutra What will be done to

prevent dust from

mining work ?

In the project, water

will be sprinkled on

the roads by tanker

and plantation will be

done nearby to

prevent dust from

blowing.

Financial Allocation

1,80,000/- Rupees

for water Sprinkling.

2. What will be done for

the animals ?

Tanks will be made

for animal water

drinking and if fodder

is needed in summer

provision has been

Allocation

1,00,000/- Rupees

per year for Tanks for

animal water

drinking .

Final minutes of 4.95th meeting held on 27-29 July, 2021

made to arrange

through CSR.

3. Shri Kanhaiya Lal

Prajapati, Sutra

If mining operation will

be start, what

arrangements made for

school children?

In the initial time, the

applicant shall be

arrange computer,

books and notebooks

for the children of

village – Sutra,

Bhawanipura, Dabi

under CSR activity

Allocation

4,50,000/- Rupees

for Schools.

4 Shri Kamal Kishor

Meena (SDM, Bundi)

SDM asked to project

proponent, you have

been told that 33% of

the plantation will be

done in the mining

area, will it be done on

the mines or can be

done in other places

also?

Plantation can be

done wherever land is

available mining area

and around the

mining area.

If land is not

available, Plantation

can also be done by

taking land from the

district

administration.

Allocation

1,80,000/- Rupees

for plantation.

5 SDM asked to project

proponent, Will you

keep the stairway

structure in the mining

pit or not ?

Staircase structures

are made in the

mining pit so that no

accidents occur.

The PP following issue of ToR, has submitted application for obtaining EC along with

the final EIA/ EMP report and the proceedings of public hearing on 13.03.2021.

The Bhawanipura & Sutra Sandstone & Khanda Cluster No. 1 as mentioned by SME,

Kota in certificate dated 27.07.2021 has Cluster area 27.1351 ha., and comprising 8 mining

leases, with consolidated carrying capacity of 11,75,891.58 TPA.

The particulars of individual mining/ leases including their budget for EMP/

Labour welfare, which area part of cluster no.1 are as follows:

Sr Name

Final minutes of 4.95th meeting held on 27-29 July, 2021

.

N

o.

of

Holder

of

LOI/Q

L/ML/

Ref.

No.

LOI/Q

L/

ML

No./Re

f. No.

Date of

Sanctio

n

Name of

Mineral

Area (in

Ha)

Khasra

No.

Pro

duct

ion

Cap

acity

Project

Cost

(in Cr.)

Weather

EC

obtained if

yes, Name

of

Authority

and Date

Bud

get

for

EM

P

(Rec

urri

ng)

(in

Rs)

Budg

et for

Gree

n

Belt

Devel

opme

nt (in

Rs)

Budget

for

Labour

Welfare

(in Rs)

1. Shri

Nanda

Karad

Ref.

no.

201810

000631

1/10/20

18

Sandstone

& Khanda 2.4353 192

4,84,

415

0.80 Now

applied

5,60,

000

60,00

0 110000

2

Shri

Nana

Lal

Dhakar

Ref.

no.

201810

000155

2

8/02/20

19

Sandstone

& Khanda 1.0023 138, 140 1,35,

662

0.80 Now

applied

5,60,

000

55,00

0 100000

3

Shri

Devi

Singh

Ref.

no.

201810

000118

1

10/01/2

019

Sandstone

2.4111 1081/208,

209

2,68,

528

0.50 Now

applied

3,50,

000

40,00

0 100000

4.

M/s

Shivam

Stone

M.L.N

o.04/20

13

26/02/2

014

Sandstone

4.8988

177,178,17

9,180,181,

446/182

70,0

00

0.40

F-

1/DEIAA/

Bundi/2018

/85-115 on

dated

23/03/2018

1,70,

000

30,00

0 100000

5

M/s

Leonar

d

Mineral

s &

Exim

PVT.

LTD.

M.L.N

o.09/20

12

03/04/1

3

Sandstone

4.0018

172,173,16

9 20,1

88.2

0.75

F-

1/DEIAA/

Bundi/2018

/161-191

on dated

06/09/2018

2,00,

000

30,00

0 100000

6

Smt.

Angur

Bala

Jain

M.L.N

o.3/201

4

1/09/20

17

Sandstone

4.1005

236,237,10

90/232,108

9/232,822,

1125/823,8

07

79,1

58

0.25

F(14)/DEI

AA/SEIAA

/SEAC-

Raj/Sectt/P

roject/Cat.1

(A)B2(EC)

14-15 on

dated

30/11/2016

2,05,

000

25,00

0 50000

7

M/s

Panna

Stone

Suppli

ers

M.L.N

o.03/20

13

26/09/2

013

Sandstone

4.0266 163,164,16

5,152

60,0

00

0.25

F(14)/DEI

AA/SEIAA

/SEAC-

Raj/Sectt/P

roject/Cat.1

(A)B2(EC)

2,05,

000

25,00

0 50000

Final minutes of 4.95th meeting held on 27-29 July, 2021

14-15 on

dated

30/11/2016

8 M/s

Dev

Stone

M.L.N

o.05/20

13

28/03/2

018

Sandstone

4.2587 197,197/2,

198,194/2

5794

0.38

0.60

F-

1/DEIAA/

Bundi/2018

/85-115 on

dated

23/03/2018

1,80,

000

20,00

0 50000

The SME, Kota vide letter dated 08.07.2021 has approved mining plan for mining of

Sandstone and Khanda with respect to the said cluster. According to the information

submitted by the PP, mining leases covered under the cluster do not fall in Aravalli hills and

that there is no National Park/ Wildlife Sanctuary within the periphery of 10 Km from the

mining leases in the cluster. The PP has given an undertaking that cluster EMP shall be

implemented by the LOIs/ mining lease holders collectively in consultation and supervision

of the concerned Mining Engineer.

The particulars of EMP with respect to cluster No. 1, are as follows:

S.

No

.

Particula

rs

Details/Information

1. Cat./ Item no. (in schedule):

1 (a)-B1

2. Location

of the Project

Near village – Bhawanipura & Sutra, Tehsil: Talera, District: Bundi (Rajasthan)

3. Project Details M.L No./ Production Capacity

S.

No.

Name of

Proponents

Ref. & ML. No Area

(Hect.)

Production

Capacity in

Tonnes

(ROM)

Project

Cost

(crore)

1. Shri Nanda

Karad 201810000631 2.4353 4,84,415 0.80

2. Shri Nana Lal

Dhakar 2018100001552 1.0023 1,35,662 0.80

3. Shri Devi Singh 2018100001181 2.4111 2,68,528 0.50

4. M/s Shivam

Stone 04/2013 4.8988 70,000 0.40

5.

M/s Leonard

Minerals &

Exim PVT. LTD.

09/2012 4.0018 20,188.2 0.75

6. Smt. Angur

Bala Jain 3/2014 4.1005 79,158 0.25

7.

M/s Panna

Stone

Suppliers

3/2013 4.0266 60,000 0.25

8. M/s Dev Stone 5/2013 4.2587 57940.38 0.60

Total 27.1351 1175891.58 4.35

4. Project Cost

S. No. Name of Proponents

Ref. & ML. No Project Cost (crore)

1. Shri Nanda Karad 201810000631 0.80

2. Shri Nana Lal Dhakar 2018100001552 0.80

3. Shri Devi Singh 2018100001181 0.50

4. M/s Shivam Stone 04/2013 0.40

5. M/s Leonard Minerals 09/2012 0.75

Final minutes of 4.95th meeting held on 27-29 July, 2021

& Exim PVT. LTD.

6. Smt. Angur Bala Jain 3/2014 0.25

7. M/s Panna Stone

Suppliers 3/2013 0.25

8. M/s Dev Stone 5/2013 0.60

Total 4.35

5. Water requirement & Source

S. No

Activities

Average demand KLD

0063

1

00155

2

00118

1

04/1

3

09/1

2

3/1

4

3/1

3

5/1

3

1 Dust

Suppression

1.5 1.0 1.0 1.5 1.0 2.5 2.5 1.5

2 Green Belt 1.5 1.5 1.0 2.0

1.0 3.0 3.0 2.5

3

Drinking &

Domestic use

2.0 1.5 2.0

2.5

1.5

3.5 3.5 3.0

Total 5.0 4.0 4.0 6.0 3.5 9.0 9.0 7.0

Total water demand of cluster (8 lease) = 47.5 KLD

Source: Water will be made available by nearby village Bhawanipura & Sutra through water tanker.

6. Fuel & Energy

Diesel operated machinery will be used. Fuel will be required for the operation of mines machineries and transportation vehicles which will be taken care by the contractor itself. 15 KVA of DG set also

proposed. Electricity connection will be taken from the concerned electricity department. For mining leases already operational electricity connection has already been taken.

7. Application no., Date of Documents Submitted

Category : B1 SEAC FILE NO. : 16617,16564,15883 Date of documents Submitted : 16/03/2021 SEAC Meeting No. : 4.95th Meeting Agenda Sr. No. : 19,20,21 Date of Presentation : 28/07/2021

8. Information about Aravalli certificate

Aravalli Certificate has been issued by Mining Engineer, Bhilwara vide letter No. ME/Bundi/Map/2019/65 dated 05/08/2019, ME/Bundi-1/CC/Ri.N. 1181(2018)717 dated 19/08/2019, ME/Bundi/Map/2019/58 dated 23/07/2019.

9. Date of Air,

Water, Noise, monitoring

Monitoring was conducted by Noida Testing Laboratories., Approved by NABL, Noida.

10. Information about 500 mts composite

map

500 mts composite map has been issued by Assistant Mining Engineer, Bhilwara vide letter No. ME/Bundi/Map/2019/65 dated 05/08/2019 , ME/Bundi-1/CC/Ri.N. 1181(2018)717 dated 19/08/2019, ME/Bundi/Map/2019/58 dated 23/07/2019. Area falling within 500 mts 27.1351ha.

Final minutes of 4.95th meeting held on 27-29 July, 2021

11. EMP Activities

Environment Management Plan Expenditures: Capital Cost: Rs. 24.3 lacs Recurring Cost: Rs. 24.3 lacs per annum.

Sl. No

Description Measures

Capital Cost (Rs. In lakhs)

Recurring Cost(in lakhs/annum)

1 Air Pollution Control

Road Preparation & Maintenance

Water Sprinkling

Planting plant species

which can control air pollution along the approach road.

6.40

1.00 1.30

6.40

1.00 1.30

2 Water Pollution Control

Septic tanks for

workers 1.00 1.00

3 Green Belt Development

Barrier zone

Near lease area 1.50 1.50

4 Water Tanks for cattles

Tanks will be made for

animal water drinking 1.00 1.00

5 Occupational health

Medical facilities

including periodic health checkups and first aid facility for labors.

1.90 1.90

6

Ramps Garland Drain Rainwater harvesting

For protection while

loading and transporting the mineral ramp will be constructed.

2.20 2.20

7

Govt. Sr. Sec. School at village Ganeshpura

Repair of School Building & Room Construction

Solar Power Plant 2KW

Furniture (Tables &

Chairs) & Computers

3.50 3.50

8 Sub health centre, Bhawanipura

Medicine and Medical

equipments

Sanitary Pads 2.50 2.50

9

Village Devlopment, Bhawanipura& Sutra

Cleanliness

Drinking water

Public toilets 2.00 2.00

Total 24.3 24.3

Protection & Conservation of Local Flora & Fauna other than EMP Funds- 12,93,000/- Mining leases and WCP - 1. Shri Nanda Karad 2. Shri Nana Lal Dhakar 3. Shri Devi Singh whose area is 5.8487 ha. will be responsible for execution of WCP. Remaining other lessees have already got EC and they will be executing their plan as per EC conditions.

12. Greenbelt

& Plantation

Total green belt will be the 33% of the mine area 8.955 ha of the area shall be carried out near lease

area and trees shall be planted both side of the road connected to mine, Statutory Barrier & Part of own khatedari land at village Bhawanipura & Sutra in 192,138,140, 209, 446/182, 169, 236, 164, 197 & with join venture association Native species which are more suitable to the local environment are preferred to be planted such as like Neem (Azadiracta indica), Pipal (Ficus religiosa), Mango (Mangifera Indica), Amla (Phyllanthus Emblica) etc. it is the proposed to invest 2 Lac. Rs. Per annum for greenbelt development.

Year Along the lease boundary &

Outside the lease area Top Soil Dumps Total

Final minutes of 4.95th meeting held on 27-29 July, 2021

The PP has submitted application for approval of EIA/EMP and EC with respect to

Bhawanipura Sandstone & Khanda Mining Project, Ref. No. 2018100001552, area- 1.0023

ha., Production Capacity 1,35,662 TPA at Khasra No. 138 & 140, Near Village–

Bhawanipura, Tehsil– Talera, Dist.- Bundi, (Raj.) (Proposal No. 61904). The SME, Kota

vide order dated 08.02.2019 has issued LoI to the PP having validity of a period of 18

months. The validity of LOI has been extended vide order dated 19.07.2021. The LOI is now

valid up to 07.09.2021. The mining plan has been approved by the SME, Kota vide letter

dated 08.07.2019. ME, Bundi II in his certificate dated 05.08.2019 has stated that the mining

lease does not fall in Aravalli hills. Range Officer, Ramgarh WLS, in his letter dated

29.06.2021 addressed to DCF, WL, Kota has stated that Ramgarh WLS is at a distance of

38.69 Km from the applied lease area. DCF, MNP, Kota in his certificate dated 22.07.2021

has stated that the MHTR is at a distance of 5.33 Km from the applied lease area.

The SEAC also went through para 4 (i)/ (ii)/ (iii) and (iv) of the OM dated

08.08.2019 of the MoEF & CC which requires that the Expert Appraisal Committee would

examine the proposal from environmental angle including impact of developmental activity/

project on the Wildlife and its habitat, if any, and recommend appropriate protection and

conservation measures and that these recommendations shall be explicitly mentioned in the

EC letter. Since the project falls within a distance of 10 Km from the boundary of National

Park/ Wildlife Sanctuary and outside notified ESZ, the following specific conditions shall

also be applicable in terms of OM dated 08.08.2019 of the MoEF & CC:

1. The mining activity should be carried out in a manner so that the water

regime/system of the sanctuary is not disturbed. The mining activity should not

adversely affect any existing water course, water body, catchment etc. The PP

shall while carrying out mining activity ensure compliance of the provisions of

Air (Prevention and Control of Pollution) Act 1981, Water (Prevention and

Control of Pollution) Act 1974 and the Environment (Protection) Act, 1986 so that

the wildlife in the area is not adversely affected.

Area (Ha.) No. of

Trees

Area

(Ha.)

No. of

Trees Area (Ha.)

No. of

Trees

1st Year 2.985 2985 -- -- 2.985 2985

2nd Year 2.985 2985 -- -- 2.985 2985

3rd Year 2.985 2985 -- -- 2.985 2985

Total 8.955Hect. 8955 -- -- 8.955Hect. 8955

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing mining

operations, undertake re-grassing the mining area and any other area which may have been

disturbed due to their mining activities and restore the land to a condition which is fit for growth of

fodder, flora, fauna etc.

13. Budgetary

breakup for labour

The information regarding Budgetary breakup for labour has been given in PFR & Power Point

Presentation

Sr. No. Facility provided for Labour Capital Cost in

Rs. Recurring cost in Rs.

1. Drinking water facility 2,00,000/- 2,00,000/-

2. Health Facility (First aid box, Rest shelter, Medicine & Washroom) & Insurance

3,00,000/- 3,00,000/-

3. Education for Labour children 70,000/- 70,000/-

4. Safety equipment like Ear plug, Dust mask, hand gloves, Safety Shoes etc.

90,000/- 90,000/-

Total 6,60,000 6,60,000

14. Present

Status

LOI Granted

Final minutes of 4.95th meeting held on 27-29 July, 2021

2. The processes like blasting, drilling, excavation, transport and haulage resulting

into noise, should be carried out in such an manner so that such activities do not

disturb wild animals and birds particularly during sunset to sunrise. The level of

noise should be kept within the permissible limits.

3. The mining activity should not create any obstacle in the way of free movement of

wildlife and adversely affect wildlife corridors.

4. The mineral waste/ slurry should be dumped only at the designated places only

and such waste dumps should be reclaimed in accordance with the conditions of

the mining plan/ consent issued by the RSPCB under the Water and Air act.

5. The PP shall cooperate with the concerned DCF, Wildlife in their efforts towards

protection and conservation of wildlife in the Sanctuary/ Park.

6. The PP shall ensure that the transporter and labor employed by him should not

damage flora and fauna in the ESZ and the Wildlife Sanctuary/ National Park.

The PP during presentation informed that he has submitted Wildlife conservation plan

to the respective DCF, on 27.07.2021 in terms of guidelines dated 24.05.2019 issued by the

Chief Wildlife Warden, Rajasthan, Jaipur.

The particulars of project of Sh. Nana Lal Dhakar, are as follows:

S

.

N

o.

Partic

ulars

Details/Information

1. Cat./ Item no. (in schedule):

1 (a)-B1

2. Location of the Project

Near village – Bhawanipura, Tehsil: Talera, District: Bundi (Rajasthan)

3. Project Detail

s M.L No./ Production Capacity

Ref. No. : 2018100001552 Khasra No. : 138 & 140 Area : 1.0023HECT.

Production (TPA) : 135662 TPA(ROM)

Details are given in cover page of Proposal obtaining of Environmental Clearance

4. Projec

t Cost

Project Cost: Rs 0.80 Cr./-(in Rs.)

Details are given in cover page of Proposal obtaining of Environmental Clearance

5. Water requirement & Source

Total water requirement is about 4.0 KLD= 1.5 KLD (Drinking & Domestic Uses) + 1.5 KLD (Plantation) + 1.0 KLD (Dust Suppression), Water for Drinking, dust suppression and plantation will be collected from nearby villages.

6. Fuel & Energy

Diesel will be used for transportation vehicles.

7. Application no., Date

of Documents

Category : B1 SEAC FILE NO. : 16617 Date of documents Submitted : 16/03/2021 SEAC Meeting No. : 4.95th Meeting

Agenda Sr. No. : 19 Date of Presentation : 28/07/2021

Final minutes of 4.95th meeting held on 27-29 July, 2021

Submitted

8. Informatio

n about Aravalli certificate

Aravalli Certificate has been issued by Mining Engineer, Bhilwara vide letter No. ME/Bundi/Map/2019/65 dated 05/08/2019.

9. Date of

Air, Water, Noise, monitoring

Monitoring was conducted by Noida Testing Laboratories., Approved by NABL, Noida.

10. Informa

tion about 500 mts composite map

500 mts composite map has been issued by Assistant Mining Engineer, Bhilwara vide letter No.

ME/Bundi/Map/2019/65 dated 05/08/2019 Area falling within 500 mts 27.1351ha.

11. EMP Activities

Environment Management Plan Expenditures: Capital Cost: Rs. 5.60 lacs Recurring Cost: Rs. 5.60 lacs per annum.

Sl. No Description Measures Capital Cost (Rs. In lakhs)

Recurring Cost (in

lakhs/annum)

1 Air Pollution Control

Road Preparation & Maintenance

Water Sprinkling Planting plant species

which can control air pollution along the approach road.

1.60

0.20 0.20

1.60

0.20 0.20

2

Water Pollution Control

Septic tanks for workers 0.30 0.30

3 Green Belt Development

Barrier zone Near lease area 0.50 0.50

4 Water Tanks for cattles

Tanks will be made for

animal water drinking 0.20 0.20

5 Occupational health

Medical facilities including periodic health checkups and first aid facility for labors.

0.40 0.40

6

Ramps Garland Drain Rainwater harvesting

For protection while loading and transporting the mineral ramp will be constructed.

1.00 1.00

7

Govt. Sr. Sec. School at village Ganeshpura

Repair of School Building

Furniture (Tables & Chairs)

0.80 0.80

8

Sub health centre, Bhawanipura

Medicine and Medical equipments

Sanitary Pads 0.30 0.30

9.

Village Devlopment, Bhawanipura

Cleanliness

Drinking water

Public toilets

0.10 0.10

Total 5.60 5.60

Final minutes of 4.95th meeting held on 27-29 July, 2021

Resolution

The SEAC, upon appraisal of the project and having regard to the information contained in

Form-1, Form-2, final EIA/ EMP reports and other documents, submitted by the PP and

presentation made by the PP/ Consultant, resolved to recommend to SEIAA for (1.) Approval

of EIA/ EMP with respect to Bhawanipura & Sutra Sandstone & Khanda Cluster No. 1 as

mentioned by SME, Kota in certificate dated 08.07.2021, having Cluster area of 27.1351 ha.,

and comprising 8 mining leases, with consolidated carrying capacity of 11,75,891.58 TPA.

(2.) Grant of EC to Shri Nana Lal Dhakar, Co-owners– 1. Shri Jagdish Chand Dhakar, 2. Shri

Rekh Lal Darad, 3. Shri Basanti Lal, for Bhawanipura Sandstone & Khanda Mining Project,

Ref. No. 2018100001552, area- 1.0023 ha., Production Capacity 1,35,662 TPA (ROM)

at Khasra No. 138 & 140, Near Village– Bhawanipura, Tehsil– Talera, Dist.- Bundi, (Raj.)

(Proposal No. 61904), covered under the above mentioned cluster comprising total lease area

of 27.1351 ha., with the stipulation that the PP shall abide by the annual production scheduled

Protection & Conservation of Local Flora & Fauna other than EMP Funds- 12,93,000/- Mining leases and WCP - 1. Shri Nanda Karad 2. Shri Nana Lal Dhakar 3. Shri Devi Singh whose area is 5.8487 ha. will be responsible for execution of WCP. Remaining other lessees have already got EC and they will be executing their plan as per EC conditions.

12. Greenbelt & Plantation

Expenditure of Green Belt Rs 50,000/- Total green belt will be the 33% of the mine area 0.330 ha shall be planted in the Remaining Part of Own khatedari land ai village Bhawanipura in Khasra No.138,140 & with association. Native specie which are more suitable to the local environment are preferred to be planted such as like Neem (Azadiracta indica), Peepal (Ficus religiosa), Mango (Mangifera indica ), Shisham ( Dalbergia sissoo

) etc.

Source- district survey report.

Yea

r

Outside the lease area( Part of Own khatedari land ai village

Bhawanipura in Khasra No.138,140 & with association)

Top Soil

Dumps Total

Area (Ha.) No. of

Trees

Area

(Ha.

)

No.

of

Trees

Area

(Ha.)

No.

of

Trees

1st

Yea

r

0.11 110

-- --

0.11 110

2nd

Yea

r

0.11 110 -- -- 0.11 110

3rd

Yea

r

0.11 110 -- -- 0.11 110

Tot

al

0.330 Hect. 330 -- -- 0.330

Hect.

330

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing mining operations,

undertake re-grassing the mining area and any other area which may have been disturbed due to their

mining activities and restore the land to a condition which is fit for growth of fodder, flora, fauna etc.

13. Budgetary break

up for labour

The information regarding Budgetary breakup for labour has been given in PFR & Power Point Presentation

Sr. No. Facility provided for Labour Capital Cost in Rs. Recurring cost in Rs.

1. Drinking water facility 20,000/- 20,000/-

2. Health Facility (First aid box, Rest shelter, Medicine & Washroom) & Insurance

30,000/- 30,000/-

3. Education for Labour children 20,000/- 20,000/-

4. Safety equipment like Ear plug, Dust mask,

hand gloves, Safety Shoes etc.

10,000/- 10,000/-

Total 80,000/- 80,000/-

14. Present Status

LOI Granted

Final minutes of 4.95th meeting held on 27-29 July, 2021

specified in mining plan and that any deviation there in will render the PP liable for legal

action in accordance with Environment and Mining Laws, with the specific and general

conditions annexed at Annexure ‘A’. The PP shall also abide by the special conditions as

mentioned in OM dated 08.08.2019 and as noted in the above mentioned observations.

Besides the general conditions mentioned in Annexure “A” the SEAC also resolved to

recommend to SEIAA to impose following additional condition:

The PP/all lessees in the cluster shall abide by the mitigation and restoration measures

provided in the final Environment Impact Assessment and Environment Management plan

prepared for the cluster as a whole for Bhawanipura & Sutra Sandstone & Khanda Cluster

No.1, Total Cluster Area- 27.1351 ha., total no. of mining leases 8, Cluster Production

Capacity- 11,75,891.58 TPA, cluster project cost 4.35 Crores.

Agenda no. 20. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(16564)/ 2019-20

Project Name- Application for approval of EIA/ EMP with respect to Bhawanipura & Sutra

Sandstone & Khanda mine Cluster No.1, Cluster area 27.1351 ha., comprising 8 mining

leases, with consolidated carrying capacity of 11,75,891.58 TPA and EC to Shri Devi Singh

for Sutra Sandstone & Khanda Mining Project, Ref. No.2018100001181, Area- 2.4111 ha.,

Production capacity- 2,68,528 TPA (ROM) at Khasra no-1081/208, 209, at village-Sutra,

Tehsil- Talera, Dist-Bundi, Rajasthan, (Proposal No-61918).

Project Proponent Name: Shri Devi Singh, Co-owners-1. Shri Pappu Singh S/o Shri Kajod

Singh, 2. Shri Mukesh Singh S/o Shri Kajod Singh 3. Shri Bablu singh S/o Shri Kajod Singh,

Add Sutra, Tehsi-Talera, Dist-Bundi, Rajasthan, [email protected].

Consultant Name- Cognizance Research India Private Ltd.(Accredited by NABET, Govt. of

India Accredited No. NABET/EIA/1619/IA006, Valid up to Aug 18, 2019)Office GT-20, Sec

177, Noida- 201301 (U.P.)email:- [email protected]

Observations of the committee:-

The SEAC considered for approval of EIA/ EMP with respect to Bhawanipura &

Sutra Sandstone & Khanda mine Cluster No.1, Cluster area 27.1351 ha., comprising 8 mining

leases, with consolidated carrying capacity of 11,75,891.58 TPA and EC to Shri Devi Singh

for Sutra Sandstone & Khanda Mining Project, Ref. No.2018100001181, Area- 2.4111 ha.,

Production capacity- 2,68,528 TPA (ROM) at Khasra no- 1081/208, 209, at village-Sutra,

Tehsil- Talera, Dist- Bundi, Rajasthan, (Proposal No-61918), in its 4.95th meeting held on

28.07.2021 through VC/ electronic media in accordance with letter dated 27.05.2020 of

SEIAA, Rajasthan.

The project was also considered earlier in terms of OM dated 12.12.2018 of the MoEF

& CC by SEAC in its 4.40th meeting held on 09-11 and 15-17 June, 2020 prescribing ToR for

undertaking EIA studies and for preparing EMP as the size of the cluster in which the

proposed project lies exceeded 5.0 ha. The SEAC vide letter dated 26.06.2020 asked the PP

to conduct EIA studies and prepare EMP for the entire cluster in order to capture all the

possible externalities.

Final minutes of 4.95th meeting held on 27-29 July, 2021

One season post monsoon primary base line data of the ambient air quality PM2.5,

PM10, SO2 and NOX, Water Quality, Noise level, Soil quality and Flora and Fauna were

collected during Oct. 2019 to Dec. 2019.

The PP following the above decision got public notice published in 04.12.2020

edition of Dainik Bhaskar, Bundi and 04.12.2020 edition of Jaabaz Patrika, Bundi and for

holding public hearing for the entire cluster for ascertaining material concerns for local

affected persons and it such concerns into account in the EIA/EMP report.

Public hearing was accordingly held on 08.01.2021 at 03.30 PM at Gram panchayat

Office, Sutda “Jan Suvida Kendra Sutda”, Tehsil Talera and District Bundi, for the entire

cluster and with reference to application for EC for mining activity by Bhawanipura & Sutra

Sandstone & Khanda Mining Project, (Cluster no.-1, Cluster area- 27.1351 ha.), Ref.

No.2018100001181, Area- 2.4111 ha., Production capacity- 2,68,528 TPA (ROM) at Khasra

no-1081/208, 209, at village-Sutra, Tehsil- Talera, Dist-Bundi, Rajasthan, under the

Chairmanship of Sh. Amanullah Khan, Add. District Collector, Bundi and Sh. Rakesh Gupta,

Regional officer, RSPCB, Kota, was also present during public hearing.

The details of issue raised by the public and commitments made by the PP during

public hearing and the action plan for implementation thereof are as follows:-

S.

No.

Name of Person with

address

Queries/Suggestions Replies Time bound plan of

action with

financial allocation

for cluster

1. Shri Papu Singh, Sutra What will be done to

prevent dust from

mining work ?

In the project, water

will be sprinkled on

the roads by tanker

and plantation will be

done nearby to

prevent dust from

blowing.

Financial Allocation

1,80,000/- Rupees

for water Sprinkling.

2. What will be done for

the animals ?

Tanks will be made

for animal water

drinking and if fodder

is needed in summer

provision has been

made to arrange

through CSR.

Allocation

1,00,000/- Rupees

per year for Tanks for

animal water

drinking .

3. Shri Kanhaiya Lal

Prajapati, Sutra

If mining operation will

be start, what

arrangements made for

school children?

In the initial time, the

applicant shall be

arrange computer,

books and notebooks

for the children of

village – Sutra,

Allocation

4,50,000/- Rupees

for Schools.

Final minutes of 4.95th meeting held on 27-29 July, 2021

Bhawanipura, Dabi

under CSR activity

4 Shri Kamal Kishor

Meena (SDM, Bundi)

SDM asked to project

proponent, you have

been told that 33% of

the plantation will be

done in the mining

area, will it be done on

the mines or can be

done in other places

also?

Plantation can be

done wherever land is

available mining area

and around the

mining area.

If land is not

available, Plantation

can also be done by

taking land from the

district

administration.

Allocation

1,80,000/- Rupees

for plantation.

5 SDM asked to project

proponent, Will you

keep the stairway

structure in the mining

pit or not ?

Staircase structures

are made in the

mining pit so that no

accidents occur.

The PP following issue of ToR, has submitted application for obtaining EC along with

the final EIA/ EMP report and the proceedings of public hearing on 13.03.2021.

The Bhawanipura & Sutra Sandstone & Khanda Cluster No. 1 as mentioned by SME,

Kota in certificate dated 27.07.2021 has Cluster area 27.1351 ha., and comprising 8 mining

leases, with consolidated carrying capacity of 11,75,891.58 TPA.

The particulars of individual mining/ leases including their budget for EMP/

Labour welfare, which area part of cluster no.1 are as follows:

Sr.

No

.

Name

of

Holder

of

LOI/QL

/ML/Re

f. No.

LOI/QL

/

ML

No./Ref.

No.

Date of

Sanctio

n

Name of

Mineral

Area (in Ha) Khasra No. Prod

uctio

n

Capa

city

Project

Cost

(in Cr.)

Weather EC

obtained if

yes, Name of

Authority

and Date

Budg

et for

EMP

(Recu

rring

) (in

Rs)

Budge

t for

Green

Belt

Devel

opme

nt (in

Rs)

Budget

for

Labour

Welfare

(in Rs)

1. Shri

Nanda

Karad

Ref. no.

2018100

00631

1/10/201

8

Sandstone

& Khanda 2.4353 192

4,84,

415

0.80 Now applied

5,60,0

00 60,000 110000

2

Shri

Nana

Lal

Dhakar

Ref. no.

2018100

001552

8/02/201

9

Sandstone

& Khanda 1.0023 138, 140 1,35,

662

0.80 Now applied

5,60,0

00 55,000 100000

Final minutes of 4.95th meeting held on 27-29 July, 2021

3

Shri

Devi

Singh

Ref. no.

2018100

001181

10/01/20

19

Sandstone

2.4111 1081/208,

209

2,68,

528

0.50 Now applied

3,50,0

00 40,000 100000

4.

M/s

Shivam

Stone

M.L.No.

04/2013

26/02/20

14

Sandstone

4.8988

177,178,179

,180,181,44

6/182

70,00

0

0.40

F-

1/DEIAA/Bu

ndi/2018/85-

115 on dated

23/03/2018

1,70,0

00 30,000 100000

5

M/s

Leonard

Minerals

& Exim

PVT.

LTD.

M.L.No.

09/2012 03/04/13

Sandstone

4.0018

172,173,169 20,18

8.2

0.75

F-

1/DEIAA/Bu

ndi/2018/161

-191 on dated

06/09/2018

2,00,0

00 30,000 100000

6

Smt.

Angur

Bala

Jain

M.L.No.

3/2014

1/09/201

7

Sandstone

4.1005

236,237,109

0/232,1089/

232,822,112

5/823,807

79,15

8

0.25

F(14)/DEIA

A/SEIAA/SE

AC-

Raj/Sectt/Pro

ject/Cat.1(A)

B2(EC) 14-

15 on dated

30/11/2016

2,05,0

00 25,000 50000

7

M/s

Panna

Stone

Supplie

rs

M.L.No.

03/2013

26/09/20

13

Sandstone

4.0266 163,164,165

,152

60,00

0

0.25

F(14)/DEIA

A/SEIAA/SE

AC-

Raj/Sectt/Pro

ject/Cat.1(A)

B2(EC) 14-

15 on dated

30/11/2016

2,05,0

00 25,000 50000

8 M/s

Dev

Stone

M.L.No.

05/2013

28/03/20

18

Sandstone

4.2587 197,197/2,1

98,194/2

5794

0.38

0.60

F-

1/DEIAA/Bu

ndi/2018/85-

115 on dated

23/03/2018

1,80,0

00 20,000 50000

The SME, Kota vide letter dated 08.07.2021 has approved mining plan for mining of

Sandstone and Khanda with respect to the said cluster. According to the information

submitted by the PP, mining leases covered under the cluster do not fall in Aravalli hills and

that there is no National Park/ Wildlife Sanctuary within the periphery of 10 Km from the

mining leases in the cluster. The PP has given an undertaking that cluster EMP shall be

implemented by the LOIs/ mining lease holders collectively in consultation and supervision

of the concerned Mining Engineer.

The particulars of EMP with respect to cluster No. 1, are as follows:

S.

No

.

Particula

rs

Details/Information

1. Cat./ Item no. (in schedule):

1 (a)-B1

2. Location of the Project

Near village – Bhawanipura & Sutra, Tehsil: Talera, District: Bundi (Rajasthan)

Final minutes of 4.95th meeting held on 27-29 July, 2021

3. Project Details M.L No./ Production

Capacity

S.

No.

Name of

Proponents

Ref. & ML. No Area

(Hect.)

Production

Capacity in

Tonnes

(ROM)

Project

Cost

(crore)

1. Shri Nanda

Karad 201810000631 2.4353 4,84,415 0.80

2. Shri Nana Lal

Dhakar 2018100001552 1.0023 1,35,662 0.80

3. Shri Devi Singh 2018100001181 2.4111 2,68,528 0.50

4. M/s Shivam

Stone 04/2013 4.8988 70,000 0.40

5.

M/s Leonard

Minerals &

Exim PVT. LTD.

09/2012 4.0018 20,188.2 0.75

6. Smt. Angur

Bala Jain 3/2014 4.1005 79,158 0.25

7.

M/s Panna

Stone

Suppliers

3/2013 4.0266 60,000 0.25

8. M/s Dev Stone 5/2013 4.2587 57940.38 0.60

Total 27.1351 1175891.58 4.35

4. Project

Cost S. No. Name of

Proponents Ref. & ML. No Project Cost

(crore)

1. Shri Nanda Karad 201810000631 0.80

2. Shri Nana Lal Dhakar 2018100001552 0.80

3. Shri Devi Singh 2018100001181 0.50

4. M/s Shivam Stone 04/2013 0.40

5. M/s Leonard Minerals

& Exim PVT. LTD. 09/2012 0.75

6. Smt. Angur Bala Jain 3/2014 0.25

7. M/s Panna Stone

Suppliers 3/2013 0.25

8. M/s Dev Stone 5/2013 0.60

Total 4.35

5. Water requirement & Source

S.

N

o

Activities

Average demand KLD

0063

1

00155

2

00118

1

04/1

3

09/1

2

3/1

4

3/1

3

5/1

3

1

Dust

Suppressio

n

1.5 1.0 1.0 1.5 1.0 2.5 2.5 1.5

2 Green Belt 1.5 1.5 1.0 2.0

1.0 3.0 3.0 2.5

3

Drinking &

Domestic

use

2.0 1.5 2.0

2.5

1.5

3.5 3.5 3.0

Total 5.0 4.0 4.0 6.0 3.5 9.0 9.0 7.0

Total water demand of cluster (8 lease) = 47.5 KLD

Source: Water will be made available by nearby village Bhawanipura & Sutra through water tanker.

6. Fuel &

Energy

Diesel operated machinery will be used. Fuel will be required for the operation of mines machineries and

transportation vehicles which will be taken care by the contractor itself. 15 KVA of DG set also proposed. Electricity connection will be taken from the concerned electricity department. For mining leases already operational electricity connection has already been taken.

7. Application no., Date of Document

s Submitted

Category : B1 SEAC FILE NO. : 16617,16564,15883 Date of documents Submitted : 16/03/2021 SEAC Meeting No. : 4.95th Meeting

Agenda Sr. No. : 19,20,21 Date of Presentation : 28/07/2021

8. Information about Aravalli certificate

Aravalli Certificate has been issued by Mining Engineer, Bhilwara vide letter No. ME/Bundi/Map/2019/65 dated 05/08/2019, ME/Bundi-1/CC/Ri.N. 1181(2018)717 dated 19/08/2019, ME/Bundi/Map/2019/58 dated 23/07/2019.

9. Date of

Air,

Monitoring was conducted by Noida Testing Laboratories., Approved by NABL, Noida.

Final minutes of 4.95th meeting held on 27-29 July, 2021

Water, Noise, monitoring

10. Information about 500 mts composite map

500 mts composite map has been issued by Assistant Mining Engineer, Bhilwara vide letter No. ME/Bundi/Map/2019/65 dated 05/08/2019 , ME/Bundi-1/CC/Ri.N. 1181(2018)717 dated 19/08/2019, ME/Bundi/Map/2019/58 dated 23/07/2019. Area falling within 500 mts 27.1351ha.

11. EMP Activities

Environment Management Plan Expenditures: Capital Cost: Rs. 24.3 lacs Recurring Cost: Rs. 24.3 lacs per annum.

Sl. No

Description Measures

Capital Cost (Rs. In lakhs)

Recurring Cost(in lakhs/annum)

1 Air Pollution Control

Road Preparation & Maintenance

Water Sprinkling

Planting plant species which can control air pollution along the approach road.

6.40

1.00 1.30

6.40

1.00 1.30

2 Water Pollution Control

Septic tanks for workers

1.00 1.00

3 Green Belt Development

Barrier zone

Near lease area 1.50 1.50

4 Water Tanks for cattles

Tanks will be made for animal water drinking 1.00 1.00

5 Occupational health

Medical facilities including periodic health checkups and first aid facility for labors.

1.90 1.90

6

Ramps Garland Drain Rainwater harvesting

For protection while loading and transporting the mineral ramp will be constructed.

2.20 2.20

7

Govt. Sr. Sec. School at village Ganeshpura

Repair of School Building & Room Construction

Solar Power Plant 2KW

Furniture (Tables & Chairs) & Computers

3.50 3.50

8 Sub health centre, Bhawanipura

Medicine and Medical equipments

Sanitary Pads 2.50 2.50

9

Village Devlopment, Bhawanipura& Sutra

Cleanliness

Drinking water

Public toilets 2.00 2.00

Total 24.3 24.3

Protection & Conservation of Local Flora & Fauna other than EMP Funds- 12,93,000/- Mining leases and WCP - 1. Shri Nanda Karad 2. Shri Nana Lal Dhakar 3. Shri Devi Singh whose area is 5.8487 ha. will be responsible for execution of WCP. Remaining other lessees have already got EC and they will be executing their plan as per EC conditions.

12. Greenbelt & Plantation

Total green belt will be the 33% of the mine area 8.955 ha of the area shall be carried out near lease area and trees shall be planted both side of the road connected to mine, Statutory Barrier & Part of own khatedari land at village Bhawanipura & Sutra in 192,138,140, 209, 446/182, 169, 236, 164, 197 & with join venture association Native species which are more suitable to the local environment are

Final minutes of 4.95th meeting held on 27-29 July, 2021

The PP has submitted application for approval of EIA/EMP and EC with respect to

Sutra Sandstone & Khanda Mining Project, Ref. No.2018100001181, Area- 2.4111 ha.,

Production capacity- 2,68,528 TPA (ROM) at Khasra no- 1081/208, 209, at village-Sutra,

Tehsil- Talera, Dist-Bundi, Rajasthan, (Proposal No-61918). The SME, Kota vide order

dated 10.01.2019 has issued LoI to the PP having validity of a period of 18 months. The

validity of LOI has been extended vide order dated 20.07.2021. The LOI is now valid up to

09.10.2021. The mining plan has been approved by the SME, Kota vide letter dated

20.02.2019. ME, Bundi I in his certificate dated 19.08.2019 has stated that the mining lease

does not fall in Aravalli hills. Range Officer, Ramgarh WLS, in his letter dated 29.06.2021

addressed to DCF, WL, Kota has stated that Ramgarh WLS is at a distance of 39.15 Km from

the applied lease area. DCF, MNP, Kota in his certificate dated 22.07.2021 has stated that the

MHTR is at a distance of 4.43 Km from the applied lease area.

The SEAC also went through para 4 (i)/ (ii)/ (iii) and (iv) of the OM dated 08.08.2019

of the MoEF & CC which requires that the Expert Appraisal Committee would examine the

proposal from environmental angle including impact of developmental activity/ project on the

Wildlife and its habitat, if any, and recommend appropriate protection and conservation

measures and that these recommendations shall be explicitly mentioned in the EC letter.

Since the project falls within a distance of 10 Km from the boundary of National Park/

Wildlife Sanctuary and outside notified ESZ, the following specific conditions shall also be

applicable in terms of OM dated 08.08.2019 of the MoEF & CC:

1. The mining activity should be carried out in a manner so that the water

regime/system of the sanctuary is not disturbed. The mining activity should not

adversely affect any existing water course, water body, catchment etc. The PP

preferred to be planted such as like Neem (Azadiracta indica), Pipal (Ficus religiosa), Mango (Mangifera Indica), Amla (Phyllanthus Emblica) etc. it is the proposed to invest 2 Lac. Rs. Per annum for greenbelt development.

Year

Along the lease boundary &

Outside the lease area Top Soil Dumps Total

Area (Ha.) No. of

Trees

Area

(Ha.)

No. of

Trees Area (Ha.)

No. of

Trees

1st Year 2.985 2985 -- -- 2.985 2985

2nd Year 2.985 2985 -- -- 2.985 2985

3rd Year 2.985 2985 -- -- 2.985 2985

Total 8.955Hect. 8955 -- -- 8.955Hect. 8955

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing mining

operations, undertake re-grassing the mining area and any other area which may have been

disturbed due to their mining activities and restore the land to a condition which is fit for growth of

fodder, flora, fauna etc.

13. Budgetary

breakup for labour

The information regarding Budgetary breakup for labour has been given in PFR & Power Point

Presentation

Sr. No. Facility provided for Labour Capital Cost in

Rs. Recurring cost in Rs.

1. Drinking water facility 2,00,000/- 2,00,000/-

2. Health Facility (First aid box, Rest shelter, Medicine & Washroom) & Insurance

3,00,000/- 3,00,000/-

3. Education for Labour children 70,000/- 70,000/-

4. Safety equipment like Ear plug, Dust mask, hand gloves, Safety Shoes etc.

90,000/- 90,000/-

Total 6,60,000 6,60,000

14. Present

Status

LOI Granted

Final minutes of 4.95th meeting held on 27-29 July, 2021

shall while carrying out mining activity ensure compliance of the provisions of

Air (Prevention and Control of Pollution) Act 1981, Water (Prevention and

Control of Pollution) Act 1974 and the Environment (Protection) Act, 1986 so that

the wildlife in the area is not adversely affected.

2. The processes like blasting, drilling, excavation, transport and haulage resulting

into noise, should be carried out in such an manner so that such activities do not

disturb wild animals and birds particularly during sunset to sunrise. The level of

noise should be kept within the permissible limits.

3. The mining activity should not create any obstacle in the way of free movement of

wildlife and adversely affect wildlife corridors.

4. The mineral waste/ slurry should be dumped only at the designated places only

and such waste dumps should be reclaimed in accordance with the conditions of

the mining plan/ consent issued by the RSPCB under the Water and Air act.

5. The PP shall cooperate with the concerned DCF, Wildlife in their efforts towards

protection and conservation of wildlife in the Sanctuary/ Park.

6. The PP shall ensure that the transporter and labor employed by him should not

damage flora and fauna in the ESZ and the Wildlife Sanctuary/ National Park.

The PP during presentation informed that he has submitted Wildlife conservation plan

to the respective DCF, on 27.07.2021 in terms of guidelines dated 24.05.2019 issued by the

Chief Wildlife Warden, Rajasthan, Jaipur.

The particulars of project of Sh. Devi Singh, are as follows:

S.

No

.

Particula

rs

Details/Information

1. Cat./ Item no. (in schedule):

1 (a)-B1

2. Location of the Project

Near village – Sutra, Tehsil: Talera, District: Bundi (Rajasthan)

3. Project

Details M.L No./ Production Capacity

Ref. No. : 2018100001181

Khasra No. : 1081/208, 209 Area : 2.4111HECT.

Production (TPA) : 268528 TPA(ROM)

Details are given in cover page of Proposal obtaining of Environmental Clearance

4. Project Cost

Project Cost: Rs 0.50 Cr./-(in Rs.) Details are given in cover page of Proposal obtaining of Environmental Clearance

5. Water requirement & Source

Total water requirement is about 4.0 KLD= 2.0 KLD (Drinking & Domestic Uses) + 1.0 KLD (Plantation) + 1.0 KLD (Dust Suppression), Water for Drinking, dust suppression and plantation will be collected from nearby villages.

6. Fuel & Energy

Diesel will be used for transportation vehicles.

7. Applicatio

n no., Date of Documents Submitted

Category : B1

SEAC FILE NO. : 16564 Date of documents Submitted : 16/03/2021 SEAC Meeting No. : 4.95th Meeting Agenda Sr. No. : 20 Date of Presentation : 28/07/2021

8. Information about

Aravalli certificate

Aravalli Certificate has been issued by Mining Engineer, Bhilwara vide letter No. ME/Bundi-1/CC/Ri.N. 1181(2018)717 dated 19/08/2019.

9. Date of Air, Water,

Monitoring was conducted by Noida Testing Laboratories., Approved by NABL, Noida.

Final minutes of 4.95th meeting held on 27-29 July, 2021

Noise, monitoring

10. Information

about 500 mts composite map

500 mts composite map has been issued by Assistant Mining Engineer, Bhilwara vide letter No.

ME/Bundi-1/CC/Ri.N. 1181(2018)717 dated 19/08/2019 Area falling within 500 mts 27.1351ha.

11. EMP Activities

Environment Management Plan Expenditures: Capital Cost: Rs. 3.50 lacs Recurring Cost: Rs. 3.50 lacs per annum.

Sl. No Description Measures Capital Cost (Rs. In lakhs)

Recurring Cost (in

lakhs/annum)

1 Air Pollution Control

Road Preparation & Maintenance

Water Sprinkling Planting plant species

which can control air pollution along the approach road.

1.00

0.20 0.20

1.00

0.20 0.20

2

Water Pollution Control

Septic tanks for workers 0.30 0.30

3 Green Belt Development

Barrier zone Near lease area 0.30 0.30

4 Water Tanks for cattles

Tanks will be made for

animal water drinking 0.20 0.20

5 Occupational health

Medical facilities

including periodic health checkups and first aid facility for labors.

0.40 0.40

6

Govt. Sr. Sec. School at village Ganeshpura

Repair of School

Building

0.50 0.50

7 Sub health centre, Sutra

Medicine and Medical equipments

Sanitary Pads 0.30 0.30

8

Village Devlopment, Sutra

Cleanliness

Drinking water

Public toilets

0.10 0.10

Total 3.50 3.50

Protection & Conservation of Local Flora & Fauna other than EMP Funds- 12,93,000/- Mining leases and WCP - 1. Shri Nanda Karad 2. Shri Nana Lal Dhakar 3. Shri Devi Singh whose area is 5.8487 ha. will be responsible for execution of WCP. Remaining other lessees have already got EC and they will be executing their plan as per EC conditions.

12. Greenbelt & Plantation

Expenditure of Green Belt Rs 40,000/- Total green belt will be the 33% of the mine area 0.795 ha shall be planted in the Remaining Part of

Own khatedari land ai village Sutra in Khasra No 209 & with association.

Native specie which are more suitable to the local environment are preferred to be planted such as like Neem (Azadiracta indica), Peepal (Ficus religiosa), Mango (Mangifera indica ), Shisham ( Dalbergia sissoo ) etc.

Year

Outside the lease area( Part

of Own khatedari land ai

village Sutra in Khasra No

209 & with association)

Top Soil Dumps Total

Area (Ha.) No. of

Trees

Area

(Ha.)

No. of

Trees Area (Ha.)

No. of

Trees

Final minutes of 4.95th meeting held on 27-29 July, 2021

Resolution:

The SEAC, upon appraisal of the project and having regard to the information

contained in Form-1, Form-2, final EIA/ EMP reports and other documents, submitted by the

PP and presentation made by the PP/ Consultant, resolved to recommend to SEIAA for (1.)

Approval of EIA/ EMP with respect to Bhawanipura & Sutra Sandstone & Khanda mine

Cluster No.1 as mentioned by SME, Kota in certificate dated 08.07.2021, having Cluster area

27.1351 ha., and comprising 8 mining leases, with consolidated carrying capacity of

11,75,891.58 TPA and (2.) Grant of EC to Shri Devi Singh, Co-owners- 1. Shri Pappu Singh

S/o Shri Kajod Singh, 2. Shri Mukesh Singh S/o Shri Kajod Singh, 3. Shri Bablu singh S/o

Shri Kajod Singh, for Sutra Sandstone & Khanda Mining Project, Ref. No.2018100001181,

Area- 2.4111 ha., Production capacity- 2,68,528 TPA (ROM) at Khasra no-1081/208, 209, at

village-Sutra, Tehsil- Talera, Dist-Bundi, Rajasthan, (Proposal No-61918), covered under the

above mentioned cluster comprising total lease area of 27.1351 ha., with the stipulation that

the PP shall abide by the annual production scheduled specified in mining plan and that any

deviation there in will render the PP liable for legal action in accordance with Environment

and Mining Laws, with the specific and general conditions annexed at Annexure ‘A’. The PP

shall also abide by the special conditions as mentioned in OM dated 08.08.2019 and as noted

in the above mentioned observations.

Besides the general conditions mentioned in Annexure “A” the SEAC also resolved to

recommend to SEIAA to impose following additional condition:

The PP/all lessees in the cluster shall abide by the mitigation and restoration measures

provided in the final Environment Impact Assessment and Environment Management plan

prepared for the cluster as a whole for Bhawanipura & Sutra Sandstone & Khanda Cluster

No. 1, Total Cluster Area- 27.1351 ha., total no. of mining leases 8, Cluster Production

Capacity- 11,75,891.58 TPA, cluster project cost 4.35 Crores.

Agenda no. 21. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B1(15883)/ 2019-20

1st Year 0.265 265 -- -- 0.265 265

2nd Year 0.265 265 -- -- 0.265 265

3rd Year 0.265 265 -- -- 0.265 265

Total 0.795 Hect. 795 -- -- 0.795

Hect.

795

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing mining

operations, undertake re-grassing the mining area and any other area which may have been

disturbed due to their mining activities and restore the land to a condition which is fit for growth of

fodder, flora, fauna etc.

13. Budgetary breakup for labour

The information regarding Budgetary breakup for labour has been given in PFR & Power Point Presentation

Sr. No. Facility provided for Labour Capital Cost in

Rs. Recurring cost in

Rs.

1. Drinking water facility 15,000/- 15,000/-

2. Health Facility (First aid box, Rest shelter, Medicine & Washroom) & Insurance

20,000/- 20,000/-

3. Education for Labour children 10,000/- 10,000/-

4. Safety equipment like Ear plug, Dust mask, hand gloves, Safety Shoes etc.

5,000/- 5,000/-

Total 50,000/- 50,000/-

14. Present Status

LOI Granted

Final minutes of 4.95th meeting held on 27-29 July, 2021

Project Name- Application for approval of EIA/ EMP with respect to Bhawanipura & Sutra

Sandstone & Khanda mine Cluster No.1, Cluster area 27.1351 ha., comprising 8 mining

leases, with consolidated carrying capacity of 11,75,891.58 TPA and EC to Shri Nanda Karad

for Bhawanipura Sandstone & Khanda Mining Project, Ref. No. 201810000631, Area-

2.4353 ha., Production Capacity- 4,84,415 TPA (ROM) at Khasra no 192, Vill.-

Bhawanipura, Tehsil- Talera, Distt.- Bundi, State- Rajasthan (Proposal No- 61787).

Project Proponent Name- Shri Nanda Karad, Co-applicant 1. Sh. Prabhu, 2. Smt. Aijan Bai,

3. Smt. Sosar Bai, 4. Smt. Motiya Bai, Vill.- Sutra Tehsil- Talera, Distt.- Bundi (Raj.),

[email protected].

Consultant Name- COGNIZANCE RESEARCH INDIA PRIVATE LTD., GT-20, Sec-117,

Noida-(U.P.) Email. [email protected].

Observations of the committee:-

The SEAC considered for approval of EIA/ EMP with respect to Bhawanipura &

Sutra Sandstone & Khanda mine Cluster No.1, Cluster area 27.1351 ha., comprising 8 mining

leases, with consolidated carrying capacity of 11,75,891.58 TPA and EC to Shri Nanda Karad

for Bhawanipura Sandstone & Khanda Mining Project, Ref. No. 201810000631, Area-

2.4353 ha., Production Capacity- 4,84,415 TPA (ROM) at Khasra no 192, Vill.-

Bhawanipura, Tehsil- Talera, Distt.- Bundi, State- Rajasthan (Proposal No- 61787), in its

4.95th meeting held on 28.07.2021 through VC/ electronic media in accordance with letter

dated 27.05.2020 of SEIAA, Rajasthan.

The project was also considered earlier in terms of OM dated 12.12.2018 of the MoEF

& CC by SEAC in its 4.18th meeting held on 06th August, 2019 prescribing ToR for

undertaking EIA studies and for preparing EMP as the size of the cluster in which the

proposed project lies exceeded 5.0 ha. The SEAC vide letter dated 27.08.2019 asked the PP

to conduct EIA studies and prepare EMP for the entire cluster in order to capture all the

possible externalities.

One season post monsoon primary base line data of the ambient air quality PM2.5,

PM10, SO2 and NOX, Water Quality, Noise level, Soil quality and Flora and Fauna were

collected during Oct. 2019 to Dec. 2019.

The PP following the above decision got public notice published in 04.12.2020

edition of Dainik Bhaskar, Bundi and 04.12.2020 edition of Jaabaz Patrika, Bundi and for

holding public hearing for the entire cluster for ascertaining material concerns for local

affected persons and it such concerns into account in the EIA/EMP report.

Public hearing was accordingly held on 08.01.2021 at 03.30 PM at Gram panchayat

Office, Sutda “Jan Suvida Kendra Sutda”, Tehsil Talera and District Bundi, for the entire

cluster and with reference to application for EC for mining activity by Bhawanipura & Sutra

Sandstone & Khanda Mining Project, (Cluster no.-1, Cluster area- 27.1351 ha.) Reference

No. 201810000631, Area-2.4353 ha., Production Capacity- 4,84,415 TPA (ROM) at Khasra

no 192, Vill.- Bhawanipura, Tehsil- Talera, Distt.- Bundi, State- Rajasthan, under the

Chairmanship of Sh. Amanullah Khan, Add. District Collector, Bundi and Sh. Rakesh Gupta,

Regional officer, RSPCB, Kota, was also present during public hearing.

Final minutes of 4.95th meeting held on 27-29 July, 2021

The details of issue raised by the public and commitments made by the PP during

public hearing and the action plan for implementation thereof are as follows:-

S.

No.

Name of Person with

address

Queries/Suggestions Replies Time bound plan of

action with

financial allocation

for cluster

1. Shri Papu Singh, Sutra What will be done to

prevent dust from

mining work ?

In the project, water

will be sprinkled on

the roads by tanker

and plantation will be

done nearby to

prevent dust from

blowing.

Financial Allocation

1,80,000/- Rupees

for water Sprinkling.

2. What will be done for

the animals ?

Tanks will be made

for animal water

drinking and if fodder

is needed in summer

provision has been

made to arrange

through CSR.

Allocation

1,00,000/- Rupees

per year for Tanks for

animal water

drinking .

3. Shri Kanhaiya Lal

Prajapati, Sutra

If mining operation will

be start, what

arrangements made for

school children?

In the initial time, the

applicant shall be

arrange computer,

books and notebooks

for the children of

village – Sutra,

Bhawanipura, Dabi

under CSR activity

Allocation

4,50,000/- Rupees

for Schools.

4 Shri Kamal Kishor

Meena (SDM, Bundi)

SDM asked to project

proponent, you have

been told that 33% of

the plantation will be

done in the mining

area, will it be done on

the mines or can be

done in other places

also?

Plantation can be

done wherever land is

available mining area

and around the

mining area.

If land is not

available, Plantation

can also be done by

taking land from the

district

administration.

Allocation

1,80,000/- Rupees

for plantation.

Final minutes of 4.95th meeting held on 27-29 July, 2021

5 SDM asked to project

proponent, Will you

keep the stairway

structure in the mining

pit or not ?

Staircase structures

are made in the

mining pit so that no

accidents occur.

The PP following issue of ToR, has submitted application for obtaining EC along with

the final EIA/ EMP report and the proceedings of public hearing on 13.03.2021 .

The Bhawanipura & Sutra Sandstone & Khanda Cluster No. 1 as mentioned by SME,

Kota in certificate dated 27.07.2021 has Cluster area 27.1351 ha., and comprising 8 mining

leases, with consolidated carrying capacity of 11,75,891.58 TPA.

The particulars of individual mining/ leases including their budget for EMP/

Labour welfare, which area part of cluster no.1 are as follows:

Sr

.

N

o.

Name

of

Holder

of

LOI/Q

L/ML/

Ref.

No.

1) Particulars of individual mining/Leases including their budget for EMP and labour welfare

LOI/Q

L/

ML

No./Re

f. No.

Date of

Sanctio

n

Name of

Mineral

Area (in

Ha)

Khasra

No.

Pro

duct

ion

Cap

acity

Project

Cost

(in Cr.)

Weather

EC

obtained if

yes, Name

of

Authority

and Date

Bud

get

for

EM

P

(Rec

urri

ng)

(in

Rs)

Budg

et for

Gree

n

Belt

Devel

opme

nt (in

Rs)

Budget

for

Labour

Welfare

(in Rs)

1. Shri

Nanda

Karad

Ref.

no.

201810

000631

1/10/20

18

Sandston

e &

Khanda

2.4353 192 4,84,

415

0.80 Now

applied

5,60,

000

60,00

0 110000

2

Shri

Nana

Lal

Dhakar

Ref.

no.

201810

000155

2

8/02/20

19

Sandston

e &

Khanda

1.0023 138, 140 1,35,

662

0.80 Now

applied

5,60,

000

55,00

0 100000

3

Shri

Devi

Singh

Ref.

no.

201810

000118

1

10/01/2

019

Sandston

e

2.4111 1081/208,

209

2,68,

528

0.50 Now

applied

3,50,

000

40,00

0 100000

4.

M/s

Shivam

Stone

M.L.N

o.04/20

13

26/02/2

014

Sandston

e

4.8988

177,178,17

9,180,181,

446/182

70,0

00

0.40

F-

1/DEIAA/

Bundi/2018

/85-115 on

dated

23/03/2018

1,70,

000

30,00

0 100000

Final minutes of 4.95th meeting held on 27-29 July, 2021

5

M/s

Leonar

d

Mineral

s &

Exim

PVT.

LTD.

M.L.N

o.09/20

12

03/04/1

3

Sandston

e

4.0018

172,173,16

9 20,1

88.2

0.75

F-

1/DEIAA/

Bundi/2018

/161-191

on dated

06/09/2018

2,00,

000

30,00

0 100000

6

Smt.

Angur

Bala

Jain

M.L.N

o.3/201

4

1/09/20

17

Sandston

e

4.1005

236,237,10

90/232,108

9/232,822,

1125/823,8

07

79,1

58

0.25

F(14)/DEI

AA/SEIAA

/SEAC-

Raj/Sectt/P

roject/Cat.1

(A)B2(EC)

14-15 on

dated

30/11/2016

2,05,

000

25,00

0 50000

7

M/s

Panna

Stone

Suppli

ers

M.L.N

o.03/20

13

26/09/2

013

Sandston

e

4.0266 163,164,16

5,152

60,0

00

0.25

F(14)/DEI

AA/SEIAA

/SEAC-

Raj/Sectt/P

roject/Cat.1

(A)B2(EC)

14-15 on

dated

30/11/2016

2,05,

000

25,00

0 50000

8 M/s

Dev

Stone

M.L.N

o.05/20

13

28/03/2

018

Sandston

e

4.2587 197,197/2,

198,194/2

5794

0.38

0.60

F-

1/DEIAA/

Bundi/2018

/85-115 on

dated

23/03/2018

1,80,

000

20,00

0 50000

The SME, Kota vide letter dated 08.07.2021 has approved mining plan for mining of

Sandstone and Khanda with respect to the said cluster. According to the information

submitted by the PP, mining leases covered under the cluster do not fall in Aravalli hills and

that there is no National Park/ Wildlife Sanctuary within the periphery of 10 Km from the

mining leases in the cluster. The PP has given an undertaking that cluster EMP shall be

implemented by the LOIs/ mining lease holders collectively in consultation and supervision

of the concerned Mining Engineer.

The particulars of EMP with respect to cluster No. 1, are as follows:

S.

No

.

Particula

rs

Details/Information

1. Cat./ Item

no. (in schedule):

1 (a)-B1

2. Location of the Project

Near village – Bhawanipura & Sutra, Tehsil: Talera, District: Bundi (Rajasthan)

3. Project Details

M.L No./ Productio

S. No.

Name of Proponent

s

Ref. & ML. No Area (Hect.)

Production

Capacity in Tonnes

Project Cost (crore)

Final minutes of 4.95th meeting held on 27-29 July, 2021

n Capacity

(ROM)

1. Shri Nanda

Karad 201810000631 2.4353 4,84,415 0.80

2. Shri Nana Lal

Dhakar 2018100001552 1.0023 1,35,662 0.80

3. Shri Devi

Singh 201810000118

1 2.4111 2,68,528 0.50

4. M/s Shivam

Stone 04/2013 4.8988 70,000 0.40

5.

M/s Leonard Minerals & Exim PVT.

LTD.

09/2012 4.0018 20,188.2 0.75

6. Smt. Angur Bala Jain

3/2014 4.1005 79,158 0.25

7. M/s Panna

Stone Suppliers

3/2013 4.0266 60,000 0.25

8. M/s Dev

Stone 5/2013 4.2587 57940.38 0.60

Total 27.135

1 1175891.58 4.35

4. Project Cost

S. No. Name of Proponents

Ref. & ML. No Project Cost (crore)

1. Shri Nanda Karad 201810000631 0.80

2. Shri Nana Lal Dhakar 2018100001552 0.80

3. Shri Devi Singh 2018100001181 0.50

4. M/s Shivam Stone 04/2013 0.40

5. M/s Leonard Minerals

& Exim PVT. LTD. 09/2012 0.75

6. Smt. Angur Bala Jain 3/2014 0.25

7. M/s Panna Stone

Suppliers 3/2013 0.25

8. M/s Dev Stone 5/2013 0.60

Total 4.35

5. Water requireme

nt & Source

S.

N

o

Activities

Average demand KLD

0063

1

00155

2

00118

1

04/1

3

09/1

2

3/1

4

3/1

3

5/1

3

1

Dust

Suppressio

n

1.5 1.0 1.0 1.5 1.0 2.5 2.5 1.5

2 Green Belt 1.5 1.5 1.0 2.0

1.0 3.0 3.0 2.5

3

Drinking &

Domestic

use

2.0 1.5 2.0

2.5

1.5

3.5 3.5 3.0

Total 5.0 4.0 4.0 6.0 3.5 9.0 9.0 7.0

Total water demand of cluster (8 lease) = 47.5 KLD

Source: Water will be made available by nearby village Bhawanipura & Sutra through water tanker.

6. Fuel & Energy

Diesel operated machinery will be used. Fuel will be required for the operation of mines machineries and transportation vehicles which will be taken care by the contractor itself. 15 KVA of DG set also proposed. Electricity connection will be taken from the concerned electricity department. For mining leases already operational electricity connection has already been taken.

7. Applicati

on no., Date of Documents Submitted

Category : B1

SEAC FILE NO. : 16617,16564,15883 Date of documents Submitted : 16/03/2021 SEAC Meeting No. : 4.95th Meeting Agenda Sr. No. : 19,20,21 Date of Presentation : 28/07/2021

Final minutes of 4.95th meeting held on 27-29 July, 2021

8. Information about Aravalli certificate

Aravalli Certificate has been issued by Mining Engineer, Bhilwara vide letter No. ME/Bundi/Map/2019/65 dated 05/08/2019, ME/Bundi-1/CC/Ri.N. 1181(2018)717 dated 19/08/2019, ME/Bundi/Map/2019/58 dated 23/07/2019.

9. Date of Air, Water, Noise, monitoring

Monitoring was conducted by Noida Testing Laboratories., Approved by NABL, Noida.

10. Information about 500

mts composite map

500 mts composite map has been issued by Assistant Mining Engineer, Bhilwara vide letter No. ME/Bundi/Map/2019/65 dated 05/08/2019 , ME/Bundi-1/CC/Ri.N. 1181(2018)717 dated 19/08/2019,

ME/Bundi/Map/2019/58 dated 23/07/2019. Area falling within 500 mts 27.1351ha.

11. EMP Activities

Environment Management Plan Expenditures: Capital Cost: Rs. 24.3 lacs Recurring Cost: Rs. 24.3 lacs per annum.

Sl. No

Description Measures

Capital Cost (Rs. In lakhs)

Recurring Cost(in lakhs/annum)

1 Air Pollution Control

Road Preparation & Maintenance

Water Sprinkling

Planting plant species

which can control air pollution along the approach road.

6.40

1.00 1.30

6.40

1.00 1.30

2 Water Pollution Control

Septic tanks for workers

1.00 1.00

3 Green Belt Development

Barrier zone

Near lease area 1.50 1.50

4 Water Tanks for cattles

Tanks will be made for

animal water drinking 1.00 1.00

5 Occupational health

Medical facilities

including periodic health checkups and first aid facility for labors.

1.90 1.90

6

Ramps Garland Drain Rainwater harvesting

For protection while

loading and transporting the mineral ramp will be constructed.

2.20 2.20

7

Govt. Sr. Sec. School at village Ganeshpura

Repair of School Building & Room Construction

Solar Power Plant 2KW

Furniture (Tables &

Chairs) & Computers

3.50 3.50

8 Sub health centre, Bhawanipura

Medicine and Medical

equipments

Sanitary Pads 2.50 2.50

9

Village Devlopment, Bhawanipura& Sutra

Cleanliness

Drinking water

Public toilets 2.00 2.00

Total 24.3 24.3

Protection & Conservation of Local Flora & Fauna other than EMP Funds- 12,93,000/- Mining leases and WCP - 1. Shri Nanda Karad 2. Shri Nana Lal Dhakar 3. Shri Devi Singh whose area is 5.8487 ha. will be responsible for execution of

Final minutes of 4.95th meeting held on 27-29 July, 2021

The PP has submitted application for approval of EIA/EMP and EC for Bhawanipura

Sandstone & Khanda Mining Project, Ref. No. 201810000631, Area- 2.4353 ha., Production

Capacity- 4,84,415 TPA (ROM) at Khasra no 192, Vill.- Bhawanipura, Tehsil- Talera, Distt.-

Bundi, State- Rajasthan (Proposal No- 61787). The SME, Kota vide order dated 01.10.2018

has issued LoI to the PP having validity of a period of 18 months. The valditiy of LOI has

been extended by SME, Kota vide letter dated 19.07.2021. The LOI is now valid up to

30.09.2021. The mining plan has been approved by the SME, Kota vide letter dated

01.11.2018. ME, Bundi II in his certificate dated 23.07.2019 has stated that the mining lease

does not fall in Aravalli hills. Range Officer, Ramgarh WLS, in his letter dated 08.06.2021

addressed to DCF, WL, Kota has stated that Ramgarh WLS is at a distance of 39.36 Km from

WCP. Remaining other lessees have already got EC and they will be executing their plan as per EC conditions.

12. Greenbelt & Plantation

Total green belt will be the 33% of the mine area 8.955 ha of the area shall be carried out near lease area and trees shall be planted both side of the road connected to mine, Statutory Barrier & Part of own khatedari land at village Bhawanipura & Sutra in 192,138,140, 209, 446/182, 169, 236, 164, 197 & with join venture association Native species which are more suitable to the local environment are

preferred to be planted such as like Neem (Azadiracta indica), Pipal (Ficus religiosa), Mango (Mangifera Indica), Amla (Phyllanthus Emblica) etc. it is the proposed to invest 2 Lac. Rs. Per annum for greenbelt development.

Year

Along the lease boundary &

Outside the lease area Top Soil Dumps Total

Area (Ha.) No. of

Trees

Area

(Ha.)

No. of

Trees Area (Ha.)

No. of

Trees

1st Year 2.985 2985 -- -- 2.985 2985

2nd Year 2.985 2985 -- -- 2.985 2985

3rd Year 2.985 2985 -- -- 2.985 2985

Total 8.955Hect. 8955 -- -- 8.955Hect. 8955

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing mining

operations, undertake re-grassing the mining area and any other area which may have been

disturbed due to their mining activities and restore the land to a condition which is fit for growth of

fodder, flora, fauna etc.

13. Budgetary breakup for labour

The information regarding Budgetary breakup for labour has been given in PFR & Power Point Presentation

Sr. No. Facility provided for Labour Capital Cost in

Rs. Recurring cost in Rs.

1. Drinking water facility 2,00,000/- 2,00,000/-

2. Health Facility (First aid box, Rest shelter, Medicine & Washroom) & Insurance

3,00,000/- 3,00,000/-

3. Education for Labour children 70,000/- 70,000/-

4. Safety equipment like Ear plug, Dust

mask, hand gloves, Safety Shoes etc.

90,000/- 90,000/-

Total 6,60,000 6,60,000

14. Present Status

LOI Granted

Final minutes of 4.95th meeting held on 27-29 July, 2021

the applied lease area. DCF, MNP, Kota in his certificate dated 22.07.2021 has stated that the

MHTR is at a distance of 4.29 Km from the applied lease area.

The SEAC also went through para 4 (i)/ (ii)/ (iii) and (iv) of the OM dated

08.08.2019 of the MoEF & CC which requires that the Expert Appraisal Committee would

examine the proposal from environmental angle including impact of developmental activity/

project on the Wildlife and its habitat, if any, and recommend appropriate protection and

conservation measures and that these recommendations shall be explicitly mentioned in the

EC letter. Since the project falls within a distance of 10 Km from the boundary of National

Park/ Wildlife Sanctuary and outside notified ESZ, the following specific conditions shall

also be applicable in terms of OM dated 08.08.2019 of the MoEF & CC:

1. The mining activity should be carried out in a manner so that the water

regime/system of the sanctuary is not disturbed. The mining activity should not

adversely affect any existing water course, water body, catchment etc. The PP

shall while carrying out mining activity ensure compliance of the provisions of

Air (Prevention and Control of Pollution) Act 1981, Water (Prevention and

Control of Pollution) Act 1974 and the Environment (Protection) Act, 1986 so that

the wildlife in the area is not adversely affected.

2. The processes like blasting, drilling, excavation, transport and haulage resulting

into noise, should be carried out in such an manner so that such activities do not

disturb wild animals and birds particularly during sunset to sunrise. The level of

noise should be kept within the permissible limits.

3. The mining activity should not create any obstacle in the way of free movement of

wildlife and adversely affect wildlife corridors.

4. The mineral waste/ slurry should be dumped only at the designated places only

and such waste dumps should be reclaimed in accordance with the conditions of

the mining plan/ consent issued by the RSPCB under the Water and Air act.

5. The PP shall cooperate with the concerned DCF, Wildlife in their efforts towards

protection and conservation of wildlife in the Sanctuary/ Park.

6. The PP shall ensure that the transporter and labor employed by him should not

damage flora and fauna in the ESZ and the Wildlife Sanctuary/ National Park.

The PP during presentation informed that he has submitted Wildlife conservation plan

to the respective DCF, on 27.07.2021 in terms of guidelines dated 24.05.2019 issued by the

Chief Wildlife Warden, Rajasthan, Jaipur.

The particulars of project of Sh. Nanda Karad, are as follows:

S.

No

.

Particula

rs

Details/Information

1. Cat./ Item

no. (in

schedule):

1 (a)-B1

2. Location

of the

Project

Near village – Bhawanipura, Tehsil: Talera, District: Bundi (Rajasthan)

3. Project

Details

M.L No./

Productio

n Capacity

Ref. No. : 201810000631

Khasra No. : 192

Area : 2.4353HECT.

Production (TPA) : 484415 TPA(ROM)

Details are given in cover page of Proposal obtaining of Environmental Clearance

4. Project Project Cost: Rs 0.80 Cr./-(in Rs.)

Final minutes of 4.95th meeting held on 27-29 July, 2021

Cost Details are given in cover page of Proposal obtaining of Environmental Clearance

5. Water

requireme

nt &

Source

Total water requirement is about 5.0 KLD= 2.0 KLD (Drinking & Domestic Uses) + 1.5

KLD (Plantation) + 1.5 KLD (Dust Suppression), Water for Drinking, dust suppression and

plantation will be collected from nearby villages.

6. Fuel &

Energy

Diesel will be used for transportation vehicles.

7. Application no.,

Date of

Documen

ts

Submitted

Category : B1 SEAC FILE NO. : 15883

Date of documents Submitted : 16/03/2021

SEAC Meeting No. : 4.95th Meeting

Agenda Sr. No. : 21

Date of Presentation : 28/07/2021

8. Informati

on about

Aravalli

certificate

Aravalli Certificate has been issued by Mining Engineer, Bhilwara vide letter No.

ME/Bundi/Map/2019/58 dated 23/07/2019.

9. Date of

Air,

Water,

Noise, monitorin

g

Monitoring was conducted by Noida Testing Laboratories., Approved by NABL, Noida.

10. Informatio

n about

500 mts

composite

map

500 mts composite map has been issued by Assistant Mining Engineer, Bhilwara vide letter

No. ME/Bundi/Map/2019/58 dated 23/07/2019.

Area falling within 500 mts 27.1351ha.

11. EMP

Activities

Environment Management Plan Expenditures: Capital Cost: Rs. 5.60 lacs Recurring Cost:

Rs. 5.60 lacs per annum.

Sl. No Description Measures

Capital

Cost

(Rs. In

lakhs)

Recurring Cost

(in

lakhs/annum)

1 Air Pollution Control

Road Preparation & Maintenance

Water Sprinkling Planting plant

species which can control air pollution along the approach road.

1.60

0.20 0.20

1.60

0.20 0.20

2

Water Pollution Control

Septic tanks for workers

0.30 0.30

3 Green Belt Development

Barrier zone Near lease area 0.50 0.50

4 Water Tanks for cattles

Tanks will be made for animal water drinking

0.20 0.20

5 Occupational health

Medical facilities including periodic health checkups and first aid facility for labors.

0.40 0.40

6

Ramps Garland Drain Rainwater

For protection while loading and transporting the mineral ramp will be

1.00 1.00

Final minutes of 4.95th meeting held on 27-29 July, 2021

harvesting constructed.

7

Govt. Sr. Sec. School at village Ganeshpura

Repair of School Building

Furniture (Tables & Chairs)

0.80 0.80

8

Sub health centre, Bhawanipura

Medicine and Medical equipments

Sanitary Pads

0.30 0.30

9.

Village Devlopment, Bhawanipura

Cleanliness

Drinking water

Public toilets

0.10 0.10

Total 5.60 5.60

Protection & Conservation of Local Flora & Fauna other than EMP Funds- 12,93,000/- Mining leases and WCP - 1. Shri Nanda Karad 2. Shri Nana Lal Dhakar 3. Shri Devi Singh whose area is 5.8487 ha. will be responsible for execution of WCP. Remaining other lessees have already got EC and they will be executing their plan as per EC conditions.

12. Greenbelt

&

Plantation

Expenditure of Green Belt Rs 50,000/-

Total green belt will be the 33% of the mine area 0.801 ha shall be planted in the

Remaining Part of Own khatedari land ai village Bhawanipura in Khasra No 192 & with

association.

Native specie which are more suitable to the local environment are preferred to be planted such as like Neem (Azadiracta indica), Peepal (Ficus religiosa), Mango (Mangifera indica

), Shisham ( Dalbergia sissoo ) etc.

Year

Outside the lease area( Part of Own khatedari

land ai village Sutra in

Khasra No 209 & with

association)

Top Soil Dumps Total

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

1st Year 0.267 267 -- -- 0.267 267

2nd

Year 0.267

267 -- -- 0.267

267

3rd Year 0.267 267 -- -- 0.267 267

Total 0.801

Hect.

801 -- -- 0.801

Hect.

801

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing

mining operations, undertake re-grassing the mining area and any other area which may

have been disturbed due to their mining activities and restore the land to a condition

which is fit for growth of fodder, flora, fauna etc.

13. Budgetary breakup

for labour

The information regarding Budgetary breakup for labour has been given in PFR & Power Point Presentation

Sr.

No.

Facility provided for Labour Capital Cost in

Rs.

Recurring cost in

Rs.

1. Drinking water facility 20,000/- 20,000/-

2. Health Facility (First aid box, Rest

shelter, Medicine & Washroom) &

Insurance

30,000/- 30,000/-

3. Education for Labour children 20,000/- 20,000/-

4. Safety equipment like Ear plug, Dust

mask, hand gloves, Safety Shoes etc.

10,000/- 10,000/-

Final minutes of 4.95th meeting held on 27-29 July, 2021

Resolution

The SEAC, upon appraisal of the project and having regard to the information contained in

Form-1, Form-2, final EIA/ EMP reports and other documents, submitted by the PP and

presentation made by the PP/ Consultant, resolved to recommend to SEIAA for (1.) Approval

of EIA/ EMP with respect to Bhawanipura & Sutra Sandstone & Khanda Cluster No. 1 as

mentioned by SME, Kota in certificate dated 08.07.2021, having Cluster area of 27.1351 ha.,

and comprising 8 mining leases, with consolidated carrying capacity of 11,75,891.58 TPA.

(2.) Grant of EC to Shri Nanda Karad, Co-applicant 1. Sh. Prabhu, 2. Smt. Aijan Bai, 3. Smt.

Sosar Bai, 4. Smt. Motiya Bai, for Bhawanipura Sandstone & Khanda Mining Project, Ref.

No. 201810000631, Area- 2.4353 ha., Production Capacity- 4,84,415 TPA (ROM) at Khasra

no. 192, Vill.- Bhawanipura, Tehsil- Talera, Distt.- Bundi, State- Rajasthan (Proposal No-

61787), covered under the above mentioned cluster comprising total lease area of 27.1351

ha., with the stipulation that the PP shall abide by the annual production scheduled specified

in mining plan and that any deviation there in will render the PP liable for legal action in

accordance with Environment and Mining Laws, with the specific and general conditions

annexed at Annexure ‘A’. The PP shall also abide by the special conditions as mentioned in

OM dated 08.08.2019 and as noted in the above mentioned observations.

Besides the general conditions mentioned in Annexure “A” the SEAC also resolved to

recommend to SEIAA to impose following additional condition:

The PP/all lessees in the cluster shall abide by the mitigation and restoration measures

provided in the final Environment Impact Assessment and Environment Management plan

prepared for the cluster as a whole for Bhawanipura & Sutra Sandstone & Khanda Cluster

No. 1, Total Cluster Area- 27.1351 ha., total no. of mining leases 8, Cluster Production

Capacity- 11,75,891.58 TPA, cluster project cost 4.35 Crores.

Agenda no. 22. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B1(16819)/ 2019-20

Project Name- Application for approval of EIA/ EMP with respect to Fakoliya Granite mine

Cluster, Cluster area 23.1322 ha, comprising 9 mining leases, with consolidated carrying

capacity of 8,91,669 TPA and EC to Shri Ankit Kumar Surya for Fakoliya Granite Mining

Project, M.L. No. 23/2007, Area- 2.2447 ha, Production Capacity– 3,19,742 TPA (ROM) at

Khasra No.– 1523/1362, 1524/1362, at village- Fakoliya, Tehsil- Karera, Dist- Bhilwara,

State-(Raj.), (Proposal No-61868).

Project Proponent Name: Shri Ankit Kumar Surya, Add- Shanti Vila, Vidhya

Niketan, Tehsil- Amet, Dist- Rajsamand, (H.R.), Email- [email protected].

Consultant Name- Cognizance Research India Pvt. Ltd. Add.- GT -20, Sec - 117, Noida

(U.P.) Email. [email protected].

Observations of the committee:-

The SEAC considered Final EIA/EMP report for approval of EIA/ EMP with respect

to Fakoliya Granite mine Cluster, Cluster area 23.1322 ha, comprising 9 mining leases, with

Total 80,000/- 80,000/-

14. Present

Status

LOI Granted

Final minutes of 4.95th meeting held on 27-29 July, 2021

consolidated carrying capacity of 8,91,669 TPA and EC to Shri Ankit Kumar Surya for

Fakoliya Granite Mining Project, M.L. No. 23/2007, Area- 2.2447 ha, Production Capacity–

3,19,742 TPA (ROM) at Khasra No.– 1523/1362, 1524/1362, at village- Fakoliya, Tehsil-

Karera, Dist- Bhilwara, State-(Raj.), (Proposal No-61868), in its 4.95th meeting held on

28.07.2021 through VC/ electronic media in accordance with letter dated 27.05.2020 of

SEIAA, Rajasthan.

The project was also considered earlier in terms of OM dated 12.12.2018 of the MoEF

& CC by SEAC in its 4.43th meeting held on 15th July., 2020 prescribing ToR for undertaking

EIA studies and for preparing EMP as the size of the cluster in which the proposed project

lies exceeded 5.0 ha.

One season post monsoon primary base line data of the ambient air quality PM2.5,

PM10, SO2 and NOX, Water Quality, Noise level, Soil quality and Flora and Fauna were

collected during Dec., 2019 to Feb., 2020.

The PP following the above decision got public notice published in 05.01.2021

edition of Dainik Bhaskar, Bhilwara and 05.01.2021 edition of Dainik Navjyoti, Bhilwara

and for holding public hearing for the entire cluster for ascertaining material concerns for

local affected persons and it such concerns into account in the EIA/EMP report.

Public hearing was accordingly held on 05.02.2021 at 1.00 PM at Rajiv Seva Kendra

Gram Panchayat Chitambha, Tehsil –Kareda and District Bhilwara, for the entire cluster and

with reference to application for EC for mining activity by Fakoliya Granite Mining Project,

M.L. No. 23/2007, (cluster area- 23.1322 ha), Area- 2.2447 ha, Production Capacity –

3,19,742 TPA (ROM) at Khasra No. – 1523/1362, 1524/1362, at village- Fakoliya, Tehsil-

Karera, Dist- Bhilwara, State-(Raj.), under the Chairmanship of Sh. Rakesh Kumar, Add.

District Collector, Bundi and Sh. Mahaveer Mehta, Regional officer, RSPCB, Bhilwara was

also present during public hearing.

The details of issue raised by the public and commitments made by the PP during

public hearing and the action plan for implementation thereof are as follows:-

S.

No.

Name of Person with address

Queries /Suggestions Replies Time bound Plan of Action

With Financial Allocation

for cluster

1 Memorandum submitted by all

the village Fakoliya, Majara

and Padampura, Gram

Panchayat Simiti Chitamba

Tehsil Kareda Dist. Bhilwara

during public hearing

(Memorandum copy enclosed

as annexure B)

A complaint filed by villagers

against the mining lease

allotted by mines department

in village Fakoliya, Majara

and Padampura, Gram

Panchayat Simiti Chitamba

Tehsil Kareda Dist. Bhilwara

around the Khari river and

the populate area of the

village. court case reference

(Om Singh Chundwat / Govt.

of Rajasthan OA no

71/2020) Honable national

Green Tribunal (NGT, Central

Zone) in Bhopal for the

cancelation mining leases.

Currently case is pending, so

department not allot new

The District collector Bhilwara

convinced the villagers that the

memorandum submitted by you

will be presented at the competent

level along with the working

details of this public hearing.

A court case (Om Singh

Chundwat / Govt. of

Rajasthan OA no 71/2020)

Honable national Green

Tribunal (NGT, Central Zone)

in Bhopal is filed. Lease case

is pending.

1. The lease area ML No.

23/07 is situated 1.46 km

form khari river and there will

be no discharge from the lease

so there will be no impact of

the water of the Khari river.

2. The Lease will not use

41/02 khasra for road.

Final minutes of 4.95th meeting held on 27-29 July, 2021

leases.

2 Kanhaiya lal During the public hearing,

the forest of Duvala has been

described as 3 kilometer by

the consultant, while the

mining units have been

approved at a distance of

only 200 meters from the

boundary of Padampura and

Forest Department and

mining units have been

sanctioned only 20 meters

from the Khari river.

This mining lease was located in

own khatedari land khasra no

1523/1362 and 1524/1362.

The Joint demarcation of this

mining lease has been done with

the Forest Department living 25m

from Un Settled Forest.

Also, ADM told to the villagers that

your suggestions have been filed.

you suggestions will be presented

at the competent level along with

the working details of this public

hearing.

The mining lease was granted

in year 2007 in own khatedari

land. so raised point is not

applicable.

The lessee will be make 6.0 m

height retaining wall around

the mining lease.

3 Prahalad It is requested that do not

grant any mining lease in

this area, when case is

pending at NGT level,

otherwise the life of the

people here will be ruined.

Water will be finished out.

Livestock will deteriorate due

to mines allotted by Mining

Department near the Khari

river.

4 Chandan singh It is requested that, During

the mining operation what

measures should be taken

for the control of dust

suppuration.

Environments consultant Sh.

Nimish Singhvi told that During

the mining operation continuous

sprinkling of water will be done to

stop the dust suppuration.

After commencement of

mining operation

Financial Allocation-1,50,000

Rs for water spraying.

The PP following issue of ToR, has submitted application for obtaining EC along with

the final EIA/ EMP report and the proceedings of public hearing on 16.03.2021.

The Fakoliya Granite Cluster formed by AME, Bhilwara in terms of Notification

dated 15.01.2016 and 01.07.2016 of the MoEF & CC and as defined in the map and the

certificate dated 10.03.2021 has LOI and Leases (09) with total lease area of 23.1322 ha., and

production capacity of Cluster- 8,91,669 TPA.

The particulars of individual mining/ leases including their budget for EMP/

Labour welfare, which area part of cluster are as follows:

Sr

.

N

o.

Name

of

Holder

of

LOI/Q

L/ML

2) Particulars of

LOI/QL/

ML No.

Date

of

Sancti

on

Name

of

Minera

l

Area

(in Ha)

Khasr

a No.

Product

ion

Capacit

y

Project

Cost

(in Cr.)

Weather EC

obtained if

yes, Name of

Authority

and Date

Budget

for EMP

(Recurri

ng) (in

Rs)

Budget

for

Green

Belt

Develo

pment

(in Rs)

Budget

for

Labour

Welfare

(in Rs)

1.

Shri Ankit

Kumar Surya

(M.L. No.

23/2007)

14/03/

2008 Granite 2.2447

1523/

1362,

1524/

1362

319742

TPA

(ROM)

1.10 Now applied 7,70,000 50,000 1,00,000

2

M/s

Yashdee

p

Granite

M.L.No.2

6/2014

22/08/

2017 Granite 3.00

1525/

1362,

1507/

1362,

1501/

49513

TPA

0.55

F1(4)/SEIAA/SEAC-

Raj/Sectt/Proj

ect/ Cat.1 (a)B2(EC)14-

15 Jaipur dated

17.05.2016

1.63,900 30,000 45,000

Final minutes of 4.95th meeting held on 27-29 July, 2021

407,

1563/

407

3

M/s A.

S.

Granites

M.L.No.2

7/2014

17/08/

2017 Granite 3.00

1539/

1362,1

509/1

362,

1515/

1362,

1505/

1362

117000

TPA

0.70

F1(4)/SEIAA/SEAC-

Raj/Sectt/Proj

ect/Cat. 1(a)B2/(3273)14-15 Jaipur

dated 17.12.2015

1,75,000 30,000 60,000

4.

M/s

Kaustub

h

Granites

M.L.No.2

8/2014

11/01/

2017 Granite 3.00

1516/

407,

1576/

407,

755/1

15,

757/1

15

50884

TPA 0.55

F1(4)/SEIAA/S

EAC-

Raj/Sectt/Proj

ect/Cat.1(a)B2

(EC)14-15

Jaipur dated

30.03.2016

1.63,900 30,000 45,000

5

M/s

Marudha

ra

Granites

M.L.No.2

9/2014

19/07/

2017 Granite 3.00

1511/

1362,

1510/

407,

1535/

407,

1526/

407

50249

TPA 0.55

F1(4)/SEIAA/S

EAC-

Raj/Sectt/Proj

ect/ Cat.1

(A)B2(EC)14-

15 jaipur

dated

30.03.2016

1.63,900 30,000 45,000

6

M/s

Mallinat

h

Granites

M.L.No.3

0/2014

19/07/

2017 Granite 1.8809

1516/

407,

1536/

407,

1526/

407,

1503/

407,

1504/

407,

1535/

407

106934

TPA 0.90

F1(4)/SEIAA/S

EAC-

Raj/Sectt/Proj

ect/ Cat.1

(A)B2(2426)1

4-15 jaipur

dated

10.05.2016

1,55,000 25,000 65,000

7 Shree

Stones

M.L.No.3

1/2014

17/01/

2017 Granite 3.00

113,

758/1

14,

786/9

7,

780/9

7

72495TP

A 0.75

F1(4)/SEIAA/S

EAC-

Raj/Sectt/Proj

ect/Cat.1

(a)B2 (EC)14-

15 Jaipur

dated

30.03.2016

1,80,000 25,000 60,000

Final minutes of 4.95th meeting held on 27-29 July, 2021

8

M/s

Crosslan

d

Granite

Pvt.

Ltd.

M.L.No.3

2/2014

17/08/

2017 Granite 3.00

1505/

1362,1

537/1

362,

1519/

1362,

1538/

1362,1

558/1

511

97000TP

A 0.60

F1(4)/SEIAA/S

EAC-

Raj/Sectt/Proj

ect/Cat.

1(a)B2/(2974)

14-15 Jaipur

dated

17.12.2015

1,60,000 20,000 40,000

9

M/s

Omkar

Granites

Pvt.

Ltd.

M.L. No.

40/2014

14/01/

2017 Granite 1.0066

106,

106/2,

106/5,

713/9

8, 101,

99,

714/9

8, 100,

102,

98/2,

98/3,

98/4,

98/5,

98/6,

105/1,

105/2,

105/3,

105/4,

105/5

27852

TPA 0.50

F1(4)/SEIAA/

SEAC-

Raj/Sectt/Proj

ect/ Cat.1

(a)B2(EC)14-

15 Jaipur

dated

30.03.2016

1,42,500 10,000 40,000

The SME, Bhilwara vide letter dated 23.07.2021 has approved mining plan for mining

of Granite with respect to the said cluster. According to the information submitted by the PP,

mining leases covered under the cluster do not fall in Aravalli hills and that there is no

National Park/ Wildlife Sanctuary within the periphery of 10 Km from the mining leases in

the cluster. The PP has given an undertaking that cluster EMP shall be implemented by the

LOIs/ mining lease holders collectively in consultation and supervision of the concerned

Mining Engineer.

The particulars of the project, in brief, as submitted by the PP for cluster are as

follows:

1. Category/ Item no. (in Schedule):

1 (a) /Category-B1

2. Location of Project

Near Village- Fakoliya, Tehsil Kareda, District Bhilwara, Rajasthan

3. Project Details REF. No./Production capacity

Sr.

No.

Name of Project

Proponent with

Location and M.L No.

M.L

Area

in ha

Lease

Status

EC Granted Proposed

/Existing

Production

(TPA)

Final minutes of 4.95th meeting held on 27-29 July, 2021

1. Shri Ankit Kumar

Surya

Near Village-

Fakoliya, Tehsil

Kareda, District

Bhilwara

(M.L No. 23/2007)

2.2447

Existing

Lease First

Time

Applied for

EC

--- Granite

319742TPA

2. M/s Yashdeep Granite

Near Village- Fakoliya,

Tehsil Kareda, District

Bhilwara

M.L.No.26/2014

3.00 Operational

Lease

F1(4)/SEIAA/SEAC-

Raj/Sectt/Project/ Cat.1

(a)B2(EC)14-15 Jaipur

dated 17/05/2016

Granite

49513TPA

3. M/s A. S. Granites

Near Village- Fakoliya,

Tehsil Kareda, District

Bhilwara

M.L.No. 27/2014

3.00 Operational

Lease

F1(4)/SEIAA/SEAC-

Raj/Sectt/Project/Cat.

1(a)B2/(3273)14-15 Jaipur

dated 17/12/2015

Granite

117000 TPA

4. M/s Kaustubh Granites

Near Village- Fakoliya,

Tehsil Kareda, District

Bhilwara

M.L.No.28/2014

3.00 Operational

Lease

F1(4)/SEIAA/SEAC-

Raj/Sectt/Project/Cat.1(a)B2

(EC)14-15 Jaipur dated

30/03/2016

Granite

50884 TPA

5. M/s Marudhara

Granites

Near Village- Fakoliya,

Tehsil Kareda, District

Bhilwara

M.L.No.29/2014

3.00 Operational

Lease

F1(4)/SEIAA/SEAC-

Raj/Sectt/Project/ Cat.1

(A)B2(EC)14-15 jaipur

dated 30/03/2016

Granite

50249 TPA

6. M/s Mallinath Granites

Near Village- Fakoliya,

Tehsil Kareda, District

Bhilwara

M.L.No.30/2014

1.8809 Operational

Lease

F1(4)/SEIAA/SEAC-

Raj/Sectt/Project/ Cat.1

(A)B2(2426)14-15 jaipur

dated 10/05/2016

Granite

106934 TPA

7. Shree Stones

Near Village- Fakoliya,

Tehsil Kareda, District

Bhilwara

M.L.No.31/2014

3.00 Operational

Lease

F1(4)/SEIAA/SEAC-

Raj/Sectt/Project/Cat.1

(a)B2 (EC)14-15 Jaipur

dated 30/03/2016

Granite

72495 TPA

8. M/s Crossland Granite

Pvt. Ltd.

Near Village- Fakoliya,

Tehsil Kareda, District

Bhilwara

M.L.No.32/2014

3.00 Operational

Lease

F1(4)/SEIAA/SEAC-

Raj/Sectt/Project/Cat.

1(a)B2/(2974)14-15 Jaipur

dated 17/12/2015

Granite

97000 TPA

Final minutes of 4.95th meeting held on 27-29 July, 2021

9. M/s Omkar Granites

Pvt. Ltd.

Near Village-

Baghjana, Tehsil

Kareda, District

Bhilwara

M.L. No. 40/2014

1.0066 Operational

Lease

F1(4)/SEIAA/SEAC-

Raj/Sectt/Project/ Cat.1

(a)B2(EC)14-15 Jaipur

dated 30/03/2016

Granite

27852 TPA

Total 23.1322

891669 TPA

Carrying Capacity of the cluster: 891669 TPA

4. Project Cost Sr. No. Name of Project Proponent LOI/QL/

ML No. Project Cost (in Cr.)

1. Shri Ankit Kumar Surya 23/2007

1.10

2 M/s Yashdeep Granite 26/2014

0.55

3 M/s A. S. Granites 27/2014

0.70

4 M/s Kaustubh Granites 28/2014

0.55

5 M/s Marudhara Granites 29/2014

0.55

6 M/s Mallinath Granites 30/2014

0.90

7 Shree Stones 31/2014

0.75

8 M/s Crossland Granite Pvt. Ltd. 32/2014

0.60

9 M/s Omkar Granites Pvt. Ltd. 40/2014 0.50

5. Water Requiremen

t & Source

Sr

.

N

o.

Water

Consum

ption

Shri

Anki

t

Ku

mar

Sury

a

M/s

Yashd

eep

Grani

te

R

M/s

A. S.

Gran

ites

M/s

Kaust

ubh

Granit

es

M/s

Marud

hara

Granite

s

M/s

Mallin

ath

Granit

es

Shr

ee

Sto

nes

M/s

Crossl

and

Granit

e Pvt.

Ltd.

M/s

Omk

ar

Gran

ites

Pvt.

Ltd.

Quantity (m3day)

Total Water

Requirement

4.00

KL

D

3.20

KLD

10.0

KLD

3.20

KLD

3.20

KLD

4.00

KLD

5.00

KL

D

10.00

KLD

3.20

KLD

Source: Water requirement of the projects falling in the cluster taken from issued EC Letter from

SEIAA-Raj/DEIAA-Bhilwara

Source: Water will be made available by nearby village Fakoliya through water tanker.

6. Fuel &Energy: -

Diesel operated machinery will be used. Fuel will be required for the operation of mines machineries and transportation vehicles which will be taken care by the contractor itself. 15 KVA of DG set also proposed. Electricity connection will be taken from the concerned electricity department. For mining leases already operational electricity connection has already been taken.

7. Application No. & Date & documents submitted: -

Online Proposal No. (SIA/RJ/MIN/61868/2019) Hard copy submission date- 16/03/2021 Documents: Cluster EIA/EMP Report along with approved mining plan & all the requisite documents for grant of EC have been submitted.

8. Information about

Aravali Certificate was issued by ME, Bhilwara, vide letter no ME/Bhil/CC 2/M.L. No23/2007/1807 on

Final minutes of 4.95th meeting held on 27-29 July, 2021

Aravalli Certificate.

dated 10/09/2018.

9. Date of Air/Water/

Noise Monitoring

Baseline period for Air/Water/Noise Monitoring was Post-Monsoon Season (Dec-2019 – Feb 2020)

10. Information about Cluster & 500 mts composite

map& Cluster Certificate

500 mts Composite map has been issued by AME, Bhilwara vide letter No- 195 on dated 10/03/201.

Cluster certificate has been issued by AME, Bhilwara vide letter No- ME/Bhil/Map/Cluster/M.L. No.

23/2007/196 on dated 10/03/201.

11. . Environment Management Plan

Sr

.

N

o.

Name

of

Project

Propo

nent

LOI/

QL/

ML

No.

Proj

ect

Cost

(in

Cr.)

Details of EC

Granted

Budget for

EMP

(in Lakh)

Budget

for

Green

Belt

Develop

ment (in

Lakh

per

annum)

Budget for

Labour

Welfare

(in Lakh)

Capi

tal

Recurr

ing per

annum

Capi

tal

Recurr

ing per

annum

1. Shri

Ankit

Kumar

Surya

23/20

07 1.10

Now applied 7.70 7.70 0.50 1.00 1.00

2 M/s

Yashdee

p

Granite

26/20

14 0.55

F1(4)/SEIAA/SEA

C-Raj/Sectt/Project/

Cat.1 (a)B2(EC)14-

15 Jaipur dated

17/05/2016

1.639 1.639 0.30 0.45 0.45

3

M/s A.

S.

Granites

27/20

14 0.70

F1(4)/SEIAA/SEA

C-

Raj/Sectt/Project/Ca

t. 1(a)B2/(3273)14-

15 Jaipur dated

17/12/2015

1.75 1.75 0.30 0.60 0.60

4

M/s

Kaustub

h

Granites

28/20

14 0.55

F1(4)/SEIAA/SEA

C-

Raj/Sectt/Project/Ca

t.1(a)B2 (EC)14-15

Jaipur dated

30/03/2016

1.639 1.639 0.30 0.45 0.45

5 M/s

Marudha

ra

Granites

29/20

14 0.55

F1(4)/SEIAA/SEA

C-Raj/Sectt/Project/

Cat.1

(A)B2(EC)14-15

jaipur dated

30/03/2016

1.639 1.639 0.30 0.45 0.45

6 M/s

Mallinat

h

Granites

30/20

14 0.90

F1(4)/SEIAA/SEA

C-Raj/Sectt/Project/

Cat.1

(A)B2(2426)14-15

jaipur dated

10/05/2016

1.55 1.55 0.25 0.65 0.65

7

Shree

Stones

31/20

14 0.75

F1(4)/SEIAA/SEA

C-

Raj/Sectt/Project/Ca

t.1 (a)B2 (EC)14-15

Jaipur dated

30/03/2016

1.80 1.80 0.25 0.60 0.60

8 M/s

Crosslan

d

Granite

Pvt. Ltd.

32/20

14 0.60

F1(4)/SEIAA/SEA

C-

Raj/Sectt/Project/Ca

t. 1(a)B2/(2974)14-

15 Jaipur dated

17/12/2015

1.60 1.60 0.20 0.40 0.40

9 M/s

Omkar

Granites

40/20

14 0.50

F1(4)/SEIAA/SEA

C-Raj/Sectt/Project/

Cat.1 (a)B2(EC)14-

1.425 1.425 0.10 0.40 0.40

Final minutes of 4.95th meeting held on 27-29 July, 2021

Pvt. Ltd. 15 Jaipur dated

30/03/2016

TOTAL 20.742 20.742 2.5 5.0 5.0

Source: EMP cost of the projects falling in the cluster taken from issued EC Letter from SEIAA-Raj/DEIAA-

Ajmer

Sl. No Description Measures Capital Cost (Rs. In lakhs)

Recurring Cost (in

lakhs/annum)

1 Air Pollution

Control

Water Sprinkling

Planting plant species which can control air pollution along the approach road.

2.0 1.0

2.0 1.0

2 Water Pollution Control

Septic tanks for workers 1.0 1.0

3 Green Belt Development

Barrier zone

Near lease area

Approach Road 2.5 2.5

4 Occupational health

Medical facilities including

periodic health checkups and first aid facility for labors.

2.5 2.5

5

Ramps Garland Drain Rainwater

harvesting

For protection while loading and transporting the mineral ramp will be constructed. 2.0 2.0

6 Road • Preparation &

Maintenance of Road 9.742 9.742

Total 20.742 20.742

Protection & Conservation of Schedule-I Fauna other than EMP Funds- 6,12,238/-.

This cluster EMP will be additional to the EMP proposed in the individual EC letters granted by

SEIAA-Raj/DEIAA-Bhilwara to the existing mine lease holders falling in this cluster and the

cluster EMP shall be implemented by the LOI’s/mining lease holders collectively in consultation

and supervision of the concerned Mining Engineer as also stated in the submitted undertaking.

12. . Green Belt/ Plantation

Year

Along the lease boundary &

Outside the lease area Top Soil Dumps Total

Area (Ha.) No. of

Trees

Area

(Ha.)

No. of

Trees Area (Ha.)

No. of

Trees

1st Year 0.247 247 -- -- 0.247 247

2nd Year 0.247 247 -- -- 0.247 247

3rd Year 0.247 247 -- -- 0.247 247

Total 0.741 Hect. 741 -- -- 0.741

Hect.

741

Total green belt will be the 33% of the mine area 0.741 ha of the area shall be carried out near lease

area and trees shall be planted both side of the road connected to mine, Statutory Barrier & Part of

own khatedari land at village Fakoliya in 1523/1362,1524/1362 Native species which are more

suitable to the local environment are preferred to be planted such as like Neem (Azadiracta indica),

Pipal (Ficus religiosa), Mango (Mangifera Indica), Amla (Phyllanthus Emblica) etc. it is the

proposed to invest 2 Lac. Rs. Per annum for greenbelt development.

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing mining

operations, undertake re-grassing the mining area and any other area which may have been

disturbed due to their mining activities and restore the land to a condition which is fit for growth of

fodder, flora, fauna etc.

Final minutes of 4.95th meeting held on 27-29 July, 2021

13. Budgetary Breakup for Labour

Sr.

No.

Name of

Project

Proponent

LOI/QL/

ML No.

Project

Cost

(in

Cr.)

Details of EC Granted Budget for Labour

Welfare

(in Lakh)

Capital Recurring

per

annum

1.

Shri Ankit

Kumar

Surya

23/2007 1.10 Now applied

1.00 1.00

2

M/s

Yashdeep

Granite

26/2014 0.55

F1(4)/SEIAA/SEAC-

Raj/Sectt/Project/ Cat.1

(a)B2(EC)14-15 Jaipur dated

17/05/2016

0.45 0.45

3 M/s A. S.

Granites 27/2014 0.70

F1(4)/SEIAA/SEAC-

Raj/Sectt/Project/Cat.

1(a)B2/(3273)14-15 Jaipur

dated 17/12/2015

0.60 0.60

4

M/s

Kaustubh

Granites

28/2014 0.55

F1(4)/SEIAA/SEAC-

Raj/Sectt/Project/Cat.1(a)B2

(EC)14-15 Jaipur dated

30/03/2016

0.45 0.45

5

M/s

Marudhara

Granites

29/2014 0.55

F1(4)/SEIAA/SEAC-

Raj/Sectt/Project/ Cat.1

(A)B2(EC)14-15 jaipur dated

30/03/2016

0.45 0.45

6

M/s

Mallinath

Granites

30/2014 0.90

F1(4)/SEIAA/SEAC-

Raj/Sectt/Project/ Cat.1

(A)B2(2426)14-15 jaipur dated

10/05/2016

0.65 0.65

7 Shree

Stones 31/2014 0.75

F1(4)/SEIAA/SEAC-

Raj/Sectt/Project/Cat.1 (a)B2

(EC)14-15 Jaipur dated

30/03/2016

0.60 0.60

8

M/s

Crossland

Granite Pvt.

Ltd.

32/2014 0.60

F1(4)/SEIAA/SEAC-

Raj/Sectt/Project/Cat.

1(a)B2/(2974)14-15 Jaipur

dated 17/12/2015

0.40 0.40

9

M/s Omkar

Granites

Pvt. Ltd.

40/2014 0.50

F1(4)/SEIAA/SEAC-

Raj/Sectt/Project/ Cat.1

(a)B2(EC)14-15 Jaipur dated

30/03/2016

0.40 0.40

TOTAL 5.0 5.0

14. Present Status

Sh. Ankit Kumar Surya is a Existing lease now proposed for the grant of Environmental Clearance and rest other mines in the cluster are already having EC as mentioned above at point no. 11 Column No. 4.

This is an existing lease. The mining lease for an area of 3.00 ha was granted in

favour of Shri Ankit Kumar Surya S/O Shri Sushil Kumar Surya vide order dated 02.01.2008.

The lease deed was executed on dated 14.03.2008 and was registered on 08.04.2008 for 20

years (08.04.2008 to 07.04.2028) a part of lease area fell in forest land so the lessee applied

to the Govt. of Rajasthan for partial surrender of 0.7553 ha of the lease area. The partial

surrender i.e. 0.7553 ha., was accepted vide order dated 31.08.2018. The modification in the

mining plan with progressive mine closure plan was approved by SME, Bhilwara vide order

dated 04.03.2019. The retained area therefore, is 2.2447 ha.

The project being one of minor mineral having lease area of 2.2447 ha., came under

the purview of the EIA Notification dated 09.09.2013 of the MoEF & CC. According to the

certificate dated 13.07.2020 of ME, Bhilwara, production of mineral in the year 2012-13 i.e.

base year was 2570 Ton and thereafter, up to 2019-20, production of mineral has either been

nil or less than the base years production level. The project, therefore, is not one of violation

of the EIA Notification. The PP has also submitted affidavit to the affect that no activity has

been carried out in violation of the EIA Notification and Common Cause Judgment

pronounced by the Hon’ble Supreme Court.

Final minutes of 4.95th meeting held on 27-29 July, 2021

The PP has submitted application for approval of EIA/EMP and EC with respect to

Fakoliya Granite Mining Project, M.L. No. 23/2007, Area- 2.2447 ha, Production Capacity–

3,19,742 TPA (ROM) at Khasra No.– 1523/1362, 1524/1362, at village- Fakoliya, Tehsil-

Karera, Dist- Bhilwara, State-(Raj.), (Proposal No-61868). ME, Bhilwara in his certificate

dated 10.09.2018 has stated that the mining lease does not fall in Aravalli hills. DCF,

Bhilwara in his certificate dated 04.07.2019 has stated that there is no Wildlife

Sanctuary/National Park/ Conservation Reserve within 10 km periphery of the mine. The

DCF, Bhilwara in his certificate dated 24.08.2018 has stated that the applied lease area is 25

meters away from the Forest land and has directed that mining activity should start only after

construction of Pucca wall on 3 sides of the Forest land and that no forest land will be used

for transportation.

The PP during presentation informed that he has submitted Wildlife conservation plan

to the respective DCF, on 27.07.2021 in terms of guidelines dated 24.05.2019 issued by the

Chief Wildlife Warden, Rajasthan, Jaipur.

The particulars of project of Sh. Ankit Kumar Surya, are as follows:

1. Category/

Item no. (in Schedule):

1 (a) /Category-B1

2. Location of

Project Near Village- Fakoliya, Tehsil Kareda, District Bhilwara, Rajasthan

3. Project Details

REF. No./Production

capacity

(M.L. No. – 23/2007), M.L. Area: 2.2447Ha. Khasra No. 1523/1362,1524/1362 Production–3,19,742TPA (R.O.M.)

(Granite : 114002TPA, Waste: 205740TPA)

4. Project Cost Rs. 1.10 Cr.

5. Water

Requirement

& Source

Total water requirement is about 4.0 KLD= 1.0 KLD (Drinking & Domestic Uses) + 1.0 KLD

(Plantation) + 0.5 KLD (Dust Suppression), 1.5 KLD (Wire saw cutting & Wet drilling). Water for

Drinking, dust suppression and plantation will be collected from nearby villages.

6. Fuel &Energy: - Diesel operated machinery will be used. Fuel will be required for the operation of mines

machineries and transportation vehicles which will be taken care by the contractor itself. 15 KVA

of DG set also proposed.

Electricity connection will be taken from the concerned electricity department.

7. Application No.

& Date &

documents submitted: -

Online Proposal No. (SIA/RJ/MIN/61868/2019) Hard copy submission date- 16/03/2021 Documents: Cluster EIA/EMP Report along with approved mining plan & all the requisite

documents for grant of EC have been submitted.

8. Information

about Aravalli

Certificate.

Aravali Certificate was issued by ME, Bhilwara, vide letter no ME/Bhil/CC 2/M.L.

No23/2007/1807 on dated 10/09/2018

9. Date of

Air/Water/Noise Monitoring

Baseline period for Air/Water/Noise Monitoring was Post-Monsoon Season (Dec-2019 – Feb

2020)

10. Information

about Cluster & 500 mts

composite

map& Cluster

Certificate

500 mts Composite map has been issued by AME, Bhilwara vide letter No- 195 on dated

10/03/201.

Cluster certificate has been issued by AME, Bhilwara vide letter No- ME/Bhil/Map/Cluster/M.L.

No. 23/2007/196 on dated 10/03/201.

Final minutes of 4.95th meeting held on 27-29 July, 2021

11. Environment Management

Plan

Annual Expenditure of Rs. 7.70 Lac Per year

Sl. No Description Measures

Capital

Cost

(Rs. In

lakhs)

Recurring Cost (in

lakhs/annum)

1 Air Pollution

Control

Water Sprinkling

Planting plant species

which can control air

pollution along the

approach road.

0.50

0.50

0.50

0.50

2

Water

Pollution

Control

Septic tanks for

workers 1.00 1.00

3 Green Belt

Development

Barrier zone

Near lease area

Approach Road

0.50 0.50

4 Occupational

health

Medical facilities

including periodic health

checkups and first aid

facility for labors.

1.50 1.50

5

Ramps

Garland Drain

Rainwater

harvesting

For protection while

loading and transporting

the mineral ramp will be

constructed.

1.00 1.00

6 Road • Preparation &

Maintenance of Road 2.70 2.70

Total 7.70 7.70

Protection & Conservation of Schedule-I Fauna other than EMP Funds- 6,12,238/-.

12. Green Belt/

Plantation

Annual expenditure of Rs. 0.50Lac Per Year (Recurring Cost)

Total green belt will be the 33% of the mine area 0.741 ha of the area shall be carried out in Statutory Barrier 0.441 hect. & remaining Part of own khatedari land (0.300 Hect.) at village

Fakoliya in Khasra No.1523/1362,1524/1362.

Year

Un-worked

Area

Outside (Own

Remaining Land ) near

the lease area

Statutory

Barrier

Top Soil

Dumps Total

Area

(Ha.)

No.

of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No.

of

Trees

Area

(Ha.)

No.

of

Trees

Area

(Ha.)

No.

of

Trees

1st

Year -- --

0.100 100 0.147 147 -- --

0.247 247

2nd

Year

-- -- 0.100 100 0.147 147

-- -- 0.247 247

3rd

Year

-- -- 0.100 100 0.147 147

-- -- 0.247 247

4th

Year

Maintenance

5th

Year

Maintenance

Total -- -- 0. 300 300 0.441 441 -- -- 0.741 741

Year

Outside (Own Remaining

Land ) near the lease area Top Soil Dumps Total

Area (Ha.) No. of

Trees

Area

(Ha.)

No. of

Trees Area (Ha.) No. of Trees

Final minutes of 4.95th meeting held on 27-29 July, 2021

1st Year 0.247 247 -- -- 0.247 247

2nd Year 0.247 247 -- -- 0.247 247

3rd Year 0.247 247 -- -- 0.247 247

Total 0.741 Hect. 741 -- -- 0.741 Hect. 741

Native species which are more suitable to the local environment are preferred to be planted such as like

Neem (Azadiracta indica), Pipal (Ficus religiosa), Mango (Mangifera Indica), Amla (Phyllanthus

Emblica) etc. it is the proposed to invest 2 Lac. Rs. Per annum for greenbelt development.

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing mining operations,

undertake re-grassing the mining area and any other area which may have been disturbed due to their

mining activities and restore the land to a condition which is fit for growth of fodder, flora, fauna etc.

13. Budgetary

Breakup for Labour

Annual Expenditure of Rs. 1.00 Lac per annum (Recurring Cost)

Sr. No. Facility provided for Labour Capital Cost in Rs. Recurring cost in Rs.

1. Drinking water facility 30,000/- 30,000/-

2. Health Facility (First aid box, Rest shelter,

Medicine & Washroom) & Insurance

30,000/- 30,000/-

3. Education for Labour children 20,000/- 20,000/-

4. Safety equipment like Ear plug, Dust mask,

hand gloves, Safety Shoes etc.

20,000/- 20,000/-

Total 1,00,000/- 1,00,000/-

14. Present Status Existing lease now proposed for the grant of Environmental Clearance.

Resolution

The SEAC, upon appraisal of the project and having regard to the information

contained in Form-1, Form-2, final EIA/ EMP reports and other documents, submitted by the

PP and presentation made by the PP/ Consultant resolved to recommend to SEIAA for (1.)

Approval of EIA/ EMP with respect to Fakoliya Granite mine cluster formed by AME,

Bhilwara in terms of Notification dated 15.01.2016 and 01.07.2016 of the MoEF & CC and

as defined in the map and the certificate dated 10.03.2021 has LOI and Leases (09) with total

lease area of 23.1322 ha., and production capacity of Cluster- 8,91,669 TPA. (2.) EC to Shri

Ankit Kumar Surya for Fakoliya Granite Mining Project, M.L. No. 23/2007, Area- 2.2447 ha,

Production Capacity– 3,19,742 TPA (ROM) at Khasra No.– 1523/1362, 1524/1362, at

village- Fakoliya, Tehsil- Karera, Dist- Bhilwara, State- Rajasthan, (Proposal No-61868),

covered under the above mentioned cluster comprising total lease area of 23.1322 ha., with

the stipulation that the PP shall abide by the annual production scheduled specified in mining

plan and that any deviation there in will render the PP liable for legal action in accordance

with Environment and Mining Laws, with the specific and general conditions annexed at

Annexure ‘A’, with additional condition that the PP shall construct pucca wall on 3 sides of

the Forest land before starting mining activity and that no forest land will be used for

transportation.

Besides the general conditions mentioned in Annexure “A” the SEAC also resolved to

recommend to SEIAA to impose following additional condition:

The PP/all lessees in the cluster shall abide by the mitigation and restoration measures

provided in the final Environment Impact Assessment and Environment Management plan

prepared for the cluster as a whole for Fakoliya Granite Cluster, Total Cluster Area- 23.1322

Final minutes of 4.95th meeting held on 27-29 July, 2021

ha., total no. of mining leases 9, Cluster Production Capacity- 8,91,669 TPA, cluster project

cost 6.20 Crores.

Agenda no. 23. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19624)/ 2019-20

Project Name- EC for Dhuwaliya Granite Mining Project, M.L. No. 22/2021, Area 1.7215

Ha., Khasra No. 1117, 1119, 1335/1119, 1342/1119, Production Capacity 1,70,000 TPA

(ROM) (Saleable Mineral- 85000TPA, Waste- 85000 TPA), Add.- Dhuwaliya, Tehsil-

Kekri, District- Ajmer, (Raj.) (Proposal No.- 215260).

Project Proponent Name- M/s Shri Shyam Minerals, Add.- Khasra No. 117, Vill.-

Dhuwaliya, Tehsil- Kekri, Distt.- Ajmer, (Raj.) (Project Proponent) Shri- Piyush Kumar S/o

Shri Ram Kumar Singh, Add.- Adarsh Colony, Nawalgarh Road, Sikar, Distt.- Sikar, (Raj.)

Email- [email protected]

Consultant Name- Cognizance Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301 (U.P.) Email:-

[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

S.N

o.

Particula

rs

Details/Information

1. Cat./ Item

no. (in

schedule):

1 (a)-B2

2. Location

of the

Project

Near village –Dhuwaliya, Tehsil: Kekri, District: Ajmer (Rajasthan)

3. Project

Details

M.L No./ Productio

n

Capacity

M.L. No. : 22/2021

Khasra No. : 1117,1119,1335/1119,1342/1119

Area : 1.7215 Hect. Production (TPA) : 170000TPA(ROM)

Granite (Saleable Mineral- 85000TPA, Waste- 85000 TPA)

Details are given in cover page of Proposal obtaining of Environmental

Clearance

4. Project Cost

Project Cost: Rs1.0 Cr./-(in Rs.) Details are given in cover page of Proposal obtaining of Environmental Clearance

5. Water

requirement &

Source

Total water requirement is about 4.0 KLD= 1.0 KLD (Drinking & Domestic Uses)

+ 1.0 KLD (Plantation) + 1.0 KLD (Dust Suppression) + 1.0 KLD (Wet Drilling). Water for Drinking, dust suppression and plantation will be collected from nearby

villages.

6. Fuel &

Energy

Only diesel will be required to run vehicles for transportation. Electricity will be

required for drill machines which will be fulfilled by proposed DG Set.

7. Applicati

on no.,

Date of

Documents

Submitte

d

Category : B2

SEAC FILE NO. : 19624

Date of documents Submitted :15/06/2021

SEAC Meeting No. :4.95thMeeting Agenda Sr. No. :23

Date of Presentation : 28/07/2021

8. Informati

on about

Aravalli Certificate has been issued byAssistant Mining Engineer, Sawarvide

letter No.AME/Sawar/machi/M.L.(LOI)-22/2021/127 on dated 03/06/2021.

Final minutes of 4.95th meeting held on 27-29 July, 2021

Aravalli certificate

9. Date of

Air,

Water, Noise,

monitorin

g

Monitoring was conducted byNoida Testing Laboratories., Approved by NABL,

Noida.

10. Informatio

n about

500 mts

composite map

500 mts composite map has been issued byAssistant Mining Engineer, Sawarvide

letter No. AME/SWR/DRG.NO./43on dated 03/06/2021.

Area falling within 500 mts2.7259 Ha.

11. EMP

Activities

Environment Management Plan Expenditures: Capital Cost: Rs. 5.0 lacs Recurring

Cost: Rs. 5.0lacs per annum.

Sr.

No. Particulars Capital Cost

(in Rs. Lac) Recurring

Cost (in Rs.

Lac)

1. Pollution Control

i) Dust Suppression 3,00,000/- 2,45,000/-

2. Pollution Monitoring

i) Air pollution

ii) Water pollution

-- 10,000/-

3. Green Belt 2,00,000/- 2,45,000/-

Total 5,00,000/- 5,00,000/-

12. Greenbelt

&

Plantation

Expenditure of Green Belt Rs2,45,000/- Total green belt will be the 33% of the mine area 0.567 ha of the area shall be planted in

the part of own Khatedari land at village Dhuwaliya in khasra no. 1117,1119,1335/

1119,1342/1119.

Native specie which are more suitable to the local environment are preferred to be

planted such as like Neem (Azadiractaindica), Pipal (Ficusreligiosa), Mango

(MangiferaIndica), Amla(PhyllanthusEmblica) etc. it is the proposed to invest 2.45 Lac.

Rs. Per annum for greenbelt devlopment

Year

( part of own Khatedari

land at village

Dhuwaliya in khasra

no. 1117,1119,1335/

1119,1342/1119)Outside

the lease area

Top Soil

Dumps Total

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

1st

Year

0.189 189 -- --

0.189 189

2nd

Year

0.189 189 -- -- 0.189 189

3rd

Year

0.189 189 -- -- 0.189 189

Total 0.567 567 -- -- 0.567 567

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing

mining operations, undertake re-grassing the mining area and any other area which

may have been disturbed due to their mining activities and restore the land to a

condition which is fit for growth of fodder, flora, fauna etc.

13. Budgetar

y breakup

The information regarding Budgetary breakup for labour has been given in PFR &

Power Point Presentation

Final minutes of 4.95th meeting held on 27-29 July, 2021

Observations of the committee:-

The SEAC considered/examined the project proposal on 28.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for Dhuwaliya Granite Mining Project, M.L. No.

22/2021, Area 1.7215 Ha., Production Capacity 1,70,000 TPA (ROM) (Saleable Mineral-

85000TPA, Waste- 85000 TPA), Khasra No. 1117, 1119, 1335/1119, 1342/1119, Add.-

Dhuwaliya, Tehsil- Kekri, District- Ajmer, (Raj.) (Proposal No.- 215260). The project is

covered under B2 category. The SME, Ajmer vide order dated 06.04.2021 has issued LoI to

the PP for mining of Granite. The mining plan has been approved by the SME, Ajmer vide

letter dated 02.06.2021. AME, Sawar in his certificate dated 03.06.2021 has stated that the

mining lease does not fall in Aravalli hills. DCF, Ajmer and DCF, Tonk in their certificates

dated 22.07.2021 and 23.02.2021, respectively have stated that there is no Wildlife

Sanctuary/National Park/ Conservation Reserve within 10 km periphery of the mine. Besides,

the PP in Form-1 has also stated that there is no WLS, National Park and Conservation

Reserve within 10 Km of the project site.

The project does not involve approval/ clearance under the Forest (Conservation)

Act, 1980 and Wild Life Protection Act, 1972 as no forest land is involved and neither there

is any Wild Life Sanctuary/ National Park within 10 Km from the project site.

As per cluster certificate issued by AME, Sawar on 03.06.2021, the total area of all

the mining leases in the cluster having area of 2.7259 ha.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1,Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation resolved to recommend to SEIAA for grant of EC to M/s Shri

Shyam Minerals, for Dhuwaliya Granite Mining Project, M.L. No. 22/2021, Area 1.7215 Ha.,

Production Capacity 1,70,000 TPA (ROM) (Saleable Mineral- 85000 TPA, Waste- 85000

TPA), Khasra No. 1117, 1119, 1335/1119, 1342/1119, Add.- Dhuwaliya, Tehsil- Kekri,

District- Ajmer, (Raj.) (Proposal No.- 215260), with the stipulation that the PP shall abide

by the annual production scheduled specified in mining plan and that any deviation there in

will render the PP liable for legal action in accordance with Environment and Mining Laws,

with the specific and general conditions annexed at Annexure ‘A’. Name of Proponent: M/s

for labour Sr.

No.

Facility provided for Labour Capital Cost in

Rs.

Recurring cost in

Rs.

1. Drinking water facility 20,000/- 25,000/-

2. Health Facility (First aid box, Rest

shelter, Medicine & Washroom) &

Insurance

20,000/- 25,000/-

3. Education for Labour children 20,000/- 25,000/-

4. Safety equipment like Ear plug, Dust

mask, hand gloves, Safety Shoes etc. 20,000/- 25,000/-

Total 80,000/- 1,00,000/-

14. Present

Status

LOI Granted

Final minutes of 4.95th meeting held on 27-29 July, 2021

Shri Shyam Minerals, Add.- Khasra No. 117, Vill.- Dhuwaliya, Tehsil- Kekri, Distt.- Ajmer,

(Raj.) (Project Proponent) Shri- Piyush Kumar S/o Shri Ram Kumar Singh, Add.- Adarsh

Colony, Nawalgarh Road, Sikar, Distt.- Sikar, (Raj.) Email-

[email protected], Consultant Name:- Cognizance Research India Private

Ltd. Add.- Office GT-20, Sec 177, Noida- 201301 (U.P.) Email:-

[email protected].

Agenda no. 24. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19593)/ 2019-20

Project Name- Environmental Clearance for Golpur Sand Stone Mining Project, (Plot No.-

39, Area- 1.00 ha., Production Capacity 1,16,854 TPA (ROM), Khasra No.- 369/5, Near

Vill.- Golpur, Tehsil- Bundi, Distt.-Bundi (Raj.) (Proposal No.-207622).

Project Proponent Name- M/s Sukesh Industries Pvt. Ltd., Project In Charge- Shri Naveen

Jain, Add.- R/o--263/05, Pratap Nagar, Sanganer, Jaipur(Raj.), Email-

[email protected].

Consultant Name- Cognizance Research India Private Ltd., Add.-Office GT-20, Sec 177,

Noida-201301(U.P.),email:[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category /

Item no.

(in

Schedule):

1(a) B2

2. Location

of Project

Village: Golpur, Tehsil - Bundi, District - Bundi (Raj.)

Latitude - 25016’01.81950" to 25016’05.06912"

Longitude - 75027’14.20923" to 75027’14.22132"

3. Project

Details

Plot No.

/Productio

n capacity

Plot No. 39

Khasra No.- 369/5

Area- 1.00Hect.

Production capacity - 116854TPA (ROM)

4. Project

Cost:

Project Cost: Rs. 60 Lac.

5. Water

Requireme

nt

& Source

Total water requirement is about 4.0 KLD= 1.0 KLD (Drinking & Domestic Uses) + 1.5

KLD (Plantation) + 1.0 KLD (Dust Suppression). + 0.5KLD (Wet Drilling). Water for

Drinking, dust suppression and plantation will be collected from nearby villages.

6. Fuel &

Energy:-

No electricity will be required in mining operations as mining will be carried out in day

time only. Diesel will be used for transportation vehicles.

7. Applicatio

n No. &

Category : B2

Final minutes of 4.95th meeting held on 27-29 July, 2021

Date &

documents

submitted

:-

SEAC FILE NO. : 19593

Date of documents Submitted :

SEAC Meeting No. : 4.95

Agenda Sr. No. : 24

Date of Presentation : 28/7/2021

8. Informatio

n about

Aravalli

Certificate

.

Aravalli Certificate has been issued by Mining Engineer, Bundi (Raj.) vide letter No.

ME/Bundi/Machi/2021/344 date 22/3/2021.

Date of

Air/

Noise/Wat

er/Soil

Monitorin

g

Monitoring was conducted by Noida Testing Laboratories, Approved by NABL, Noida

Lab report have been submitted on Dated :- 23/3/2021

9. Informatio

n about

500 mts

composite

map

500 mts composite map has been issued by Mining Engineer, Bundi (Raj.) vide letter No.

ME/Beawar/Composite/Map/249 date 12/7/2021

Area falling within 500 mts 1.00ha.

Cluster Certificate No.: ME/Bundi/Machi/2021/345 date 22/3/2021

10. Environm

ent

Managem

ent Plan

Environment Management Plan Expenditures: Fixed Cost: Rs. 1.40 lacs, Recurring Cost:

Rs. 2.40 lacs per annum.

S.

No. Measures

Capital Cost

(Rs. In lakh.)

Recurring Cost

(Rs. in

lakh./annum)

1

Pollution Control

i) Dust Suppression, Wet

Drilling & Others

50,000/- 1,00,000/-

2

Pollution Monitoring

i) Air pollution

ii) Water pollution

10,000/-

10,000/-

3 Green Belt 80,000/- 1,30,000/-

Total 1,40,000/- 2,40,000/-

11. Green

Belt/

Plantation

Expenditure of Green Belt Rs 1,30,000/-

Total green belt will be the 33% of the mine area 0.330 ha of the area and trees shall be

planted in the Part of Govt. Charagah land at Village Gardara in Khasra No.-58.

Native specie which are more suitable to the local environment are preferred to be

planted such as like Neem (Azadiracta indica), Peepal (Ficus Religiosa), Mango

(Mangifera indica), Shisham (Dalbergia sissoo) etc. it is the proposed to invest 1.30 Lac.

Rs. Per annum for greenbelt development

Year

Outside the lease

area (Part of Govt.

Charagah land at

Village Gardara

in Khasra No.-58)

Top Soil Total

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Final minutes of 4.95th meeting held on 27-29 July, 2021

1st Year 0.11 110

0.11 110

2nd Year 0.11 110

0.11 110

3rd Year 0.11 110

0.11 110

Total 0.33 330

0.33 330

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing

mining operations, undertake re-grassing the mining area and any other area which may

have been disturbed due to their mining activities and restore the land to a condition

which is fit for growth of fodder, flora, fauna etc.

12. Budgetary

Breakup

for

Labours

Expenditure of Labour Rs 60,000/-

Sl.

No.

Facility to be Provided for

Laborers

Capital Cost

(Fixed)

Recurring Cost

1 Drinking water facility 10,000/- 25,000/-

2

Health Facility (First aid box,

Rest shelter, Medicine &

Washroom) & Insurance

10,000/-

20,000/-

3

Safety equipment like Ear

plug, Dust mask, hand gloves, Safety Shoes etc.

10,000/-

15,000/-

Total 30,000 60,000/-

13. Present

Status :-

Proposed Mine site (LOI Granted)

Observations of the committee:-

The SEAC considered/examined the project proposal on 28.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for Environmental Clearance for Golpur Sand Stone

Mining Project, (Plot No.- 39, Area- 1.00 ha., Production Capacity 1,16,854 TPA (ROM),

Khasra No.- 369/5, Near Vill.- Golpur, Tehsil- Bundi, Distt.-Bundi (Raj.) (Proposal No.-

207622). The project is covered under B2 category. The SME, Kota vide order dated

22.12.2020 has issued LoI to the PP for mining of Sand Stone. The mining plan has been

approved by the SME, Kota vide letter dated 22.03.2021. ME, Bundi in his certificate dated

22.03.2021 has stated that the mining lease does not fall in Aravalli hills. DCF, MNP, Kota in

his certificate dated 06.04.2021 has stated MHTR is at a distance of 26.21 Km from the

applied lease area. Range Officer, Ramgarh WLS, in his letter dated 08.06.2021 addressed to

DCF, WL, Kota has stated that Ramgarh Vishdhari WLS is at a distance of 25.44 Km from

the applied lease area. There is no Wildlife Sanctuary/National Park/ Conservation Reserve

within 10 km periphery of the mine. The project does not involve approval/ clearance under

the Forest (Conservation) Act, 1980 and Wild Life Protection Act, 1972 as no forest land is

involved and neither there is any Wild Life Sanctuary/ National Park within 10 Km from the

project site.

The SEAC considered the certificate dated 22.03.2021 issued by ME, Bundi. In the

certificate, it is stated that as per the MoEF & CC notification, dated 01.07.2016 there is no

other mining lease within the periphery of 500 meter and therefore, there is no cluster

formation.

Resolution:

Final minutes of 4.95th meeting held on 27-29 July, 2021

The SEAC upon appraisal of the project in the light of information contained in Form-

1,Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to M/s Sukesh

Industries Pvt. Ltd., Project In Charge- Shri Naveen Jain for Golpur Sand Stone Mining

Project, Plot No.- 39, Area- 1.00 ha., Production Capacity 1,16,854 TPA (ROM), Khasra

No.- 369/5, Near Vill.- Golpur, Tehsil- Bundi, Distt.- Bundi (Raj.) (Proposal No.-207622),

with the stipulation that the PP shall abide by the annual production scheduled specified in

mining plan and that any deviation there in will render the PP liable for legal action in

accordance with Environment and Mining Laws, with the specific and general conditions

annexed at Annexure ‘A’. Name of Proponent M/s Sukesh Industries Pvt. Ltd., Project In

Charge- Shri Naveen Jain, Add.- R/o--263/05, Pratap Nagar, Sanganer, Jaipur(Raj.) Email-

[email protected], Consultant Name:- Cognizance Research India Private Ltd., Add.-

Office GT-20, Sec 177, Noida- 201301 (U.P.), email:-

[email protected].

Agenda no. 25. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19604)/ 2019-20

Project Name- EC for Kachariya Granite Mining Project, M.L. No. 15/2021, Area 2.9217

Ha., production capacity:- 2,73,000 TPA (ROM), Khasra No. 238/99, Add.- Kachariya,

Tehsil- Kishangarh, District- Ajmer, (Raj.) (Proposal No.- 214669).

Project Proponent Name- Shri- Natvarlal Sharma S/o Shri- Balkishan Sharma, Add.- Ward

No. 41, Kachariya pith Marg, Kachariya mandir, Kishangarh, tehsil- Kishangarh, Distt.-

Ajmer, (Raj.), Email- [email protected].

Consultant Name- Cognizance Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301 (U.P.) Email:-

[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

S.N

o.

Particula

rs

Details/Information

1. Cat./ Item

no. (in

schedule):

1 (a)-B2

2. Location

of the

Project

Near village – Kachariya, Tehsil:- Kishangarh, District- Ajmer, (Rajasthan)

3. Project

Details

M.L No./ Productio

n

Capacity

Plot No. : 15/2021

Khasra No. : 238/99

Area : 2.9217HECT. Production (TPA) : 273000 TPA (ROM)

Details are given in cover page of Proposal obtaining of Environmental Clearance (Slides No.: 1)

4. Project

Cost

Project Cost: Rs 1.30 Cr.

Details are given in cover page of Proposal obtaining of Environmental Clearance

(Slides No.: 1)

5. Water

requirem

ent &

Total water requirement is about 4.5 KLD= 2.0 KLD (Drinking & Domestic Uses)

+ 1.0 KLD (Plantation) + 1.0 KLD (Dust Suppression) 0.5 KLD (Wire saw

Cutting). Water for Drinking, dust suppression and plantation will be collected

Final minutes of 4.95th meeting held on 27-29 July, 2021

Source from nearby villages. Details are given in Slide no. 30 of Power Point Presentation.

6. Fuel &

Energy

No electricity will be required in mining operations as mining will be carried out

in day time only.

7. Application no.,

Date of

Documents

Submitte

d

Category : B2 SEAC FILE NO. : 19604

Date of documents Submitted : 12/6/2021

SEAC Meeting No. : 4.95rd Meeting Agenda Sr. No. : 25

Date of Presentation : 28/07/2021

8. Information about

Aravalli

certificate

Aravalli Certificate has been issued by Mining Engineer, Ajmer vide letter No. ME/Ajmer /Map./Arawali Pra-/247 on date 07/06/2021 as Slide No.. 10

9. Date of Air,

Water,

Noise, monitorin

g

Monitoring was conducted by Noida Testing Laboratories., Approved by NABL, Noida as Slide No.: 33-34

10. Informatio

n about 500 mts

composite

map

500 mts composite map has been issued by Mining Engineer, Ajmer vide letter

No. ME/Ajmer /Map./Arawali Pra-/248 on date 07/06/2021

as Slide No..: 11 Area falling within 500 mts 2.9217ha.

11. CER Activities

Environment Management Plan Expenditures: Capital Cost: Rs. 6,50,000/- Recurring Cost: Rs. 6,50,000/- per annum.

SI. No. Measures Exp. Cost in Rs.

(Fixed)

Exp. Cost in Rs.

(Recurring)

1 Pollution Control

i) Dust Suppression 3,00,000/ 3,00,000/-

2

Pollution Monitoring

i) Air pollution

ii) Water pollution

10,000/-

3 Green Belt 3,50,000/ 3,40,000/-

Total 6,50,000/ 6,50,000/

12. Greenbelt &

Plantatio

n

Expenditure of Green Belt Rs 3,40,000/- Total green belt will be the 33% of the lease area 0.96 Ha. of the area will be

planted in the road connected to mine, 7.5 m Statutory barrier, backfilled area

and Remaning part of own khatedari land at village Kachariya in Khasra No. 238/99 .Native specie which are more suitable to the local environment are preferred to

be planted such as like Aam (Mangifera indica), Imli(Tamarindus indica), Neem

(Azadirachta Indica), Shisham (Dalbergia sisso) etc. it is the proposed to invest 3.40Lac.

Rs. Per annum for greenbelt devlopment

Year

Outside the lease area( Remaning part of own

khatedari land at village

Kachariya in Khasra

No. 238/99)

Top Soil Dumps

7.5 m Statutory

barrier,

backfilled area

Total

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Final minutes of 4.95th meeting held on 27-29 July, 2021

Observations of the committee:-

The SEAC considered/examined the project proposal on 28.07.2021by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for E C for Kachariya Granite Mining Project,

M.L. No. 15/2021, Area 2.9217 Ha., production capacity:- 2,73,000 TPA (ROM), Khasra

No. 238/99, Add.- Kachariya, Tehsil- Kishangarh, District- Ajmer, (Raj.) (Proposal No.-

214669). The project is covered under B2 category. The SME, Ajmer vide order dated

23.04.2021 has issued LoI to the PP for mining of Granite. The mining plan has been

approved by the SME, Ajmer vide letter dated 02.06.2021. ME, Ajmer in his certificate dated

07.06.2021 has stated that the mining lease does not fall in Aravalli hills. DCF, Ajmer in his

certificate dated 24.05.2021 has stated that there is no Wildlife Sanctuary/National Park/

Conservation Reserve within 10 km periphery of the mine. The project does not involve

approval/ clearance under the Forest (Conservation) Act, 1980 and Wild Life Protection Act,

1972 as no forest land is involved and neither there is any Wild Life Sanctuary/ National Park

within 10 Km from the project site.

1st

Year 0.25 250 0.071 71 0.32 321

2nd

Year 0.25 250 0.071 71

0.32 321 3rd

Year 0.25 250 0.071 71 0.32 321

Total 0.75 963 0.213 213 0.96 963 Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing

mining operations, undertake re-grassing the mining area and any other area which

may have been disturbed due to their mining activities and restore the land to a

condition which is fit for growth of fodder, flora, fauna etc.

13. Budgetar

y breakup

for labour

The information regarding Budgetary breakup for labour has been given in Power

Point Presentation (Slide No.: 15)

Sr.

No.

Facility to be Provided for

Laborers

Exp. Cost in

Rs.

(Fixed)

Exp. Cost in

Rs.

(Recurring)

1. Drinking water facility 40,000/- 40,000/-

2.

Health Facility (First aid box,

Rest shelter, Medicine &

Washroom) & Insurance

40,000/- 40,000/-

3. Education for Labours children 30,000/- 30,000/-

4.

Safety equipment like Ear plug,

Dust mask, hand gloves, Safety

Shoes etc.

20,000/- 20,000/-

Total 1,30,000/ 1,30,000/-

14. Present

Status

Proposed Mine site.

Final minutes of 4.95th meeting held on 27-29 July, 2021

According to cluster map and cluster certificate dated 07.06.2021 issued by ME,

Ajmer, there is no cluster formation in terms of Notification dated 15.01.2016 and

01.07.2016.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-1,

Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri-

Natvarlal Sharma S/o Shri- Balkishan Sharma for Kachariya Granite Mining Project, M.L.

No. 15/2021, Area 2.9217 Ha., production capacity:- 2,73,000 TPA (ROM), Khasra No.

238/99, Add.- Kachariya, Tehsil- Kishangarh, District- Ajmer, (Raj.) (Proposal No.-

214669), with the stipulation that the PP shall abide by the annual production scheduled

specified in mining plan and that any deviation there in will render the PP liable for legal

action in accordance with Environment and Mining Laws, with the specific and general

conditions annexed at Annexure ‘A’. Name of Proponent Shri- Natvarlal Sharma S/o Shri-

Balkishan Sharma, Add.- Ward No. 41, Kachariya pith Marg, Kachariya mandir,

Kishangarh, Tehsil- Kishangarh, Distt.- Ajmer, (Raj.), Email

[email protected], Consultant Name:-. Cognizance Research India Private

Ltd. Add.- Office GT-20, Sec 177, Noida- 201301 (U.P.), Email:-

[email protected].

Agenda no. 26. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19605)/ 2019-20

Project Name- EC for Kachariya Granite Mining Project, M.L. No. 13/2021, Area 1.6186

Ha., Production Capacity:- 1,57,080 TPA (ROM) (Saleable Mineral- 59500 TPA, Waste-

59500 TPA & Soil - 38080 TPA), Khasra No. 377/244, Add.- Kachariya, Tehsil-

Kishangarh, District- Ajmer, (Raj.) (Proposal No.- 214993).

Project Proponent Name: Shri Mohanshyam, Add.- Ward No. 41, Kachariya pith Marg,

Kachariya mandir, Kishangarh, Tehsil- Kishangarh, Distt.- Ajmer, (Raj.), Email-

[email protected],

Consultant Name- Cognizance Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301 (U.P.) Email:-

[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

S.No. Particulars Details/Information

1. Cat./ Item no. (in schedule):

1 (a)-B2

2. Location of

the Project

Near village –Kachariya, Tehsil: Kishangarh, District: Ajmer (Rajasthan)

3. Project Details M.L

No./

Production

Capacity

M.L. No. : 13/2021 Khasra No. : 377/244

Area : 1.6186HECT.

Production

(TPA)

: 157080TPA (ROM) (Saleable Mineral- 59500 TPA, Waste- 59500 TPA &

Soil - 38080 TPA)

Details are given in cover page of Proposal obtaining of

Final minutes of 4.95th meeting held on 27-29 July, 2021

Environmental Clearance

4. Project Cost Project Cost: Rs 1.20 Cr./-(in Rs.)

Details are given in cover page of Proposal obtaining of Environmental

Clearance

5. Water requirement

& Source

Total water requirement is about 8.0 KLD= 3.0 KLD (Drinking &

Domestic Uses) + 2.0 KLD (Plantation) + 1.5 KLD (Dust

Suppression) 1.5 KLD (Wire Saw Cutting). Water for Drinking,

dust suppression and plantation will be collected from nearby

villages.

6. Fuel &

Energy Diesel will be used for transportation vehicles.

7. Application no., Date of

Documents

Submitted

Category : B2 SEAC FILE NO. : 16605

Date of documents Submitted : 12/06/2021

SEAC Meeting No. :4.95thMeeting Agenda Sr. No. :26

Date of Presentation :28/07/2021

8. Information

about Aravalli

certificate

Aravalli Certificate has been issued byMining Engineer, Ajmer (Raj.)

vide letter No. ME/AJ/Composite/Map/Aravali Pra/249 dated 07/06/2021

9. Date of Air,

Water, Noise, monitoring

Monitoring was conducted byNoida Testing Laboratories., Approved by

NABL, Noida

10. Information

about 500 mts composite map

500 mts composite map has been issued byMining Engineer, Kishangarh

(Raj.) vide letter No. ME/AJ/Composite/Map/Aravali Pra/250 dated 07/06/2021

Area falling within 500 mts 1.6186ha.

11. Environment

Management

Plan

Environment Management Plan Expenditures: Capital Cost : Rs. 6.0 Lac.

Recurring Cost : Rs. 6.0 Lac per annum.

SI.

No. Measures

Exp. Cost in

Rs.

(Fixed)

Exp. Cost in

Rs.

(Recurring)

1 Pollution Control

i) Dust Suppression 2,75,000/- 2,75,000/-

2

Pollution Monitoring

i) Air pollution

ii) Water pollution

15,000/- 15,000/-

3 Green Belt 3,10,000/- 3,10,000/-

Total 6,00,000/- 6,00,000/-

12. Greenbelt &

Plantation Expenditure of EMP Rs 3,10,000/- Total green belt will be the 33% of the mine area 0.534 ha shall be planted in

the Remaining Part of Own Khatedari land at village- Kachariya in Khasra No. 377/244.

Native specie which are more suitable to the local environment are preferred

to be planted such as like Neem (Azadiracta indica), Peepal (Ficus religiosa), Mango (Mangifera indica ), Shisham ( Dalbergia sissoo ) etc.

Source- district survey report.

Year Outside the

lease area( Part

of Own

Khatedari land

at village-

Top Soil

Dumps Total

Final minutes of 4.95th meeting held on 27-29 July, 2021

Observations of the committee:-

The SEAC considered/examined the project proposal on 28.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for E C for Kachariya Granite Mining Project, M.L.

No. 13/2021, Area 1.6186 Ha., Production Capacity:- 1,57,080 TPA (ROM) (Saleable

Mineral- 59500 TPA, Waste- 59500 TPA & Soil - 38080 TPA), Khasra No. 377/244, Add.-

Kachariya, Tehsil- Kishangarh, District- Ajmer, (Raj.) (Proposal No.- 214993). The project

is covered under B2 category. The SME, Ajmer vide order dated 23.04.2021 has issued LoI

to the PP for mining of Granite. The mining plan has been approved by the SME, Ajmer vide

letter dated 02.06.2021. ME, Ajmer in his certificate dated 07.06.2021 has stated that the

mining lease does not fall in Aravalli hills. DCF, Ajmer in his certificate dated 24.05.2021

has stated that there is no Wildlife Sanctuary/National Park/ Conservation Reserve within 10

km periphery of the mine. The project does not involve approval/ clearance under the Forest

(Conservation) Act, 1980 and Wild Life Protection Act, 1972 as no forest land is involved

Kachariya in

Khasra No.

377/244)

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

1st

Year 0.178 178

-- -- 0.178 178

2nd

Year 0.178 178

-- -- 0.178 178

3rd

Year 0.178 178

-- -- 0.178 178

Total 0.534 534 -- -- 0.534 534

Note:- The mining lease holders shall, after ceasing mining operations,

undertake re-grassing the mining area and any other area which may have

been disturbed due to their mining activities and restore the land to a

condition which is fit for growth of fodder, flora, fauna etc.”The lease shall

comply all conditions as per on 16/1/2020.

13. Budgetary breakup for

labour

The information regarding Budgetary breakup for labour has been given in PFR & Power Point Presentation.

Sr.

No.

Facility provided for Labour Exp. Cost in

Rs.

(Fixed)

Exp. Cost in

Rs.

(Recurring)

1. Drinking water facility 40,000/- 40,000/-

2. Health Facility (First aid box,

Rest shelter, Medicine &

Washroom) & Insurance

50,000/- 50,000/-

3. Education for Labours children 20,000/- 20,000/-

4. Safety equipment like Ear plug,

Dust mask, hand gloves, Safety

Shoes etc.

10,000/- 10,000/-

Total 1,20,000/- 1,20,000/-

14. Present Status Proposed Mine site.

Final minutes of 4.95th meeting held on 27-29 July, 2021

and neither there is any Wild Life Sanctuary/ National Park within 10 Km from the project

site.

According to cluster map and cluster certificate dated 07.06.2021 issued by ME,

Ajmer, there is no cluster formation in terms of Notification dated 15.01.2016 and

01.07.2016.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1,Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri

Mohanshyam for Kachariya Granite Mining Project, M.L. No. 13/2021, Area 1.6186 Ha.,

Production Capacity:- 1,57,080 TPA (ROM) (Saleable Mineral- 59500 TPA, Waste- 59500

TPA & Soil - 38080 TPA), Khasra No. 377/244, Add.- Kachariya, Tehsil- Kishangarh,

District- Ajmer, (Raj.) (Proposal No.- 214993), with the stipulation that the PP shall abide

by the annual production scheduled specified in mining plan and that any deviation there in

will render the PP liable for legal action in accordance with Environment and Mining Laws,

with the specific and general conditions annexed at Annexure ‘A’. Name of Proponent: Shri

Mohanshyam, Add.- Ward No. 41, Kachariya pith Marg, Kachariya mandir, Kishangarh,

tehsil- Kishangarh, Distt.- Ajmer, (Raj.), Email- [email protected],

Consultant Name:- Cognizance Research India Private Ltd. Add.- Office GT-20, Sec 177,

Noida- 201301 (U.P.) Email:- [email protected].

Agenda no. 27. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19609)/ 2019-20

Project Name- Environmental Clearance for Pipliya Granite Mining Project, Ref. No-

20211000031500, Area- 2.2258 ha., Production capacity:- 1,76,215 TPA (ROM), Khasra No-

777/3, 768/3, at Village- Pipliya, Tehsil- Malpura, District- Tonk, State-Rajasthan, (Proposal

No-214738).

Project Proponent Name- Shri Rajesh Yadav, Co-Applicant- Shri Kamlesh, Add-

Chavandiya, Tonk, Rajasthan, [email protected].

Consultant Name- Cognizance Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301 (U.P.) Email:-

[email protected].

Observations and Resolution of the committee:-

The SEAC considered/examined the project proposal on 28.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for Environmental Clearance for Pipliya Granite

Mining Project, Ref. No-20211000031500, Area- 2.2258 ha., Production capacity:- 1,76,215

TPA (ROM), Khasra No-777/3, 768/3, at Village- Pipliya, Tehsil- Malpura, District- Tonk,

State-Rajasthan, (Proposal No-214738). The project is covered under B2 category. The

SME, Jaipur vide order dated 12.02.2021 has issued LoI to the PP for mining of Granite. The

Final minutes of 4.95th meeting held on 27-29 July, 2021

mining plan has been approved by the SME, Jaipur vide letter dated 09.06.2021. AME, Tonk

in his certificate dated 08.06.2021 has stated that the mining lease does not fall in Aravalli

hills.

The SEAC considered the certificate dated 08.06.2021 issued by AME, Tonk. In the

certificate, it is stated that as per the MoEF & CC notification, dated 01.07.2016 there is no

other mining lease within the periphery of 500 meter and therefore, there is no cluster

formation.

The PP has not submitted certificate from the concerned DCF regarding existence or

otherwise of National Park or Wildlife Sanctuary from the applied lease area. The SEAC,

therefore, decided to ask the PP to submit certificate from DCF, Tonk and DCF, Jaipur,

regarding existence or otherwise of National Park or Wildlife Sanctuary from the applied

lease area, within a period of 45 days failing which the project shall be recommended to

SEIAA for closure and delistment.

Agenda no. 28. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2( 19610)/ 2019-20

Project Name- EC for Udaipur Khurd Granite Mining Project, M.L. No. 09/2021, Area

1.1057 Ha., Khasra No. 351/224, Production Capacity- 1,18,684 TPA (ROM), Add.-

Udaipur Khurd, Tehsil- Kishangarh, District- Ajmer, (Raj.) (Proposal No.- 213932).

Project Proponent Name:- M/s Raghupati Mines & Minerals, Add.- LG-03 Murliwala

Tower Jaipur Road, Tehsil.- Madanganj- Kishangarh, Distt.- Ajmer, (Raj.), Email-

[email protected].

Consultant Name- Cognizance Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301 (U.P.) Email:-

[email protected]

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category / Item no. (in

Schedule):

1(a) B2

2. Location of Project Village - Udaipur Khurd, Tehsil- Kishangarh, District- Ajmer (Raj.)

3. Project Details

ML No. /Production

capacity

M.L. No. - 09/2021,

Khasra No.- 351/224

Area- 1.1057 Hect.

Production (TPA) - 118684 TPA (ROM)

4. Project Cost: Project Cost: Rs. 1 Cr.

5. Water Requirement

& Source

Total water requirement is about 8.0 KLD = 2.0 KLD (Drinking & Domestic

Uses) + 1.5 KLD (Plantation) + 2.0 KLD (Dust Suppression) + 2.5 KLD (Wire

Saw cutting & Wet Drilling). Water for Drinking, dust suppression and plantation

will be collected from nearby villages.

6. Fuel & Energy:- Electricity will be required for drill machines which will be fulfilled by proposed

Final minutes of 4.95th meeting held on 27-29 July, 2021

DG Set. Diesel will be required to run vehicles for transportation.

7. Application No. & Date

& documents submitted

:-

Category : B2

SEAC FILE NO. : 19610

Date of documents Submitted : 12/06/2021

SEAC Meeting No. : 4.95th Meeting

Agenda Sr. No. : 28

Date of Presentation : 28/07/2021

8. Information about

Aravalli Certificate.

Aravalli Certificate has been issued by Mining Engineer, Ajmer (Raj.) vide letter

No. ME/Aj/Composit/Machi/Aravali Pra-/305 dated 16/07/2021

Date of Air/Water/

Noise Monitoring

Monitoring was conducted by Noida Testing Laboratories, Approved by NABL,

Noida

Lab report have been submitted on Dated :- 12/06/2021

9. Information about 500

mts composite map

500 mts composite map has been issued by Mining Engineer, Ajmer (Raj.) vide

letter No. ME/Aj/Composit/Machi/Aravali Pra-/305 dated 16/07/2021

Area falling within 500 mts 1.1057 ha.

Cluster Certificate No.: ME/Aj/Composit/Machi/Aravali Pra-/306 dated

16/07/2021

10. Environment

Management Plan

Environment Management Plan Expenditures: Fixed Cost: Rs. 5.00 lacs,

Recurring Cost: Rs. 5.00 lacs per annum.

SI.

No. Measures

Exp. Cost in Rs.

(Fixed)

Exp. Cost in Rs.

(Recurring)

1

Pollution Control

i) Dust Suppression & Wet

Drilling

3,05,000/- 2,90,000/-

2

Pollution Monitoring

i) Air pollution

ii) Water pollution

- 15,000/-

3 Green Belt 1,95,000/- 1,95,000/-

Total 5,00,000/- 5,00,000/-

11. Greenbelt & Plantation Expenditure Green Belt Rs 1,95,000/-

Total green belt will be the 33% of the mine area 0.364 ha of the area and trees

shall be planted in Remaining part of own khatedari Land at village Udaipur

Khurd in Khasra No.- 351/224. Native specie which are more suitable to the

local environment are preferred to be planted such as like Neem (Azadiracta

indica), Peepal (Ficus Religiosa), Mango (Mangifera indica), Shisham

(Dalbergia sissoo) etc. it is the proposed to invest 1.95 Lac. Rs. Per annum for

greenbelt devlopment

Year

Outside the lease area

(Remaining Part of own

Khatedari land at village

Udaipur Khurd in Khasra

No. 436/348, 348/112,

349/112)

Total

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Final minutes of 4.95th meeting held on 27-29 July, 2021

1st Year 0.121 121 0.121 121

2nd Year 0.121 121 0.121 121

3rd Year 0.122 122 0.122 122

Total 0.364 364 0.364 364

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after

ceasing mining operations, undertake re-grassing the mining area and any

other area which may have been disturbed due to their mining activities and

restore the land to a condition which is fit for growth of fodder, flora, fauna

etc.

12. Budgetary Breakup for

Labour

Expenditure of Labour Rs 1,00,000/-

Sr.

No.

Facility to be Provided for

Laborers

Exp. Cost in

Rs.

(Fixed)

Exp. Cost in

Rs.

(Recurring)

1. Drinking water facility 30,000/- 30,000/-

2.

Health Facility (First aid box,

Rest shelter, Medicine &

Washroom) & Insurance

30,000/- 30,000/-

3. Education for Labours children 25,000/- 25,000/-

4.

Safety equipment like Ear plug,

Dust mask, hand gloves, Safety

Shoes etc.

15,000/- 15,000/-

Total 1,00,000/- 1,00,000/-

13. Present Status :- Proposed Mine site (LOI Granted)

Observations of the committee:-

The SEAC considered/examined the project proposal on 28.07.2021by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for EC for Udaipur Khurd Granite Mining Project,

M.L. No. 09/2021, Area 1.1057 Ha., Khasra No. 351/224, Production Capacity- 1,18,684

TPA (ROM), Add.- Udaipur Khurd, Tehsil- Kishangarh, District- Ajmer, (Raj.) (Proposal

No.- 213932). The project is covered under B2 category. The SME, Ajmer vide order dated

23.04.2021 has issued LoI to the PP for mining of Granite. The mining plan has been

approved by the SME, Ajmer vide letter dated 02.06.2021. ME, Ajmer in his certificate dated

16.07.2021 has stated that the mining lease does not fall in Aravalli hills. DCF, Ajmer in his

certificate dated 24.05.2021 has stated that there is no Wildlife Sanctuary/National Park/

Conservation Reserve within 10 km periphery of the mine. The project does not involve

approval/ clearance under the Forest (Conservation) Act, 1980 and Wild Life Protection Act,

1972 as no forest land is involved and neither there is any Wild Life Sanctuary/ National Park

within 10 Km from the project site.

According to cluster map and cluster certificate dated 16.07.2021 issued by ME,

Ajmer, there is no cluster formation in terms of Notification dated 15.01.2016 and

01.07.2016.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1, Form-2, Pre-feasibility report and other documents and having regard to the submissions

Final minutes of 4.95th meeting held on 27-29 July, 2021

made during presentation, resolved to recommend to SEIAA for grant of EC to M/s

Raghupati Mines & Minerals, for Udaipur Khurd Granite Mining Project, M.L. No. 09/2021,

Area 1.1057 Ha., Production Capacity- 1,18,684 TPA (ROM), Khasra No. 351/224, Add.-

Udaipur Khurd, Tehsil- Kishangarh, District- Ajmer, (Raj.) (Proposal No.- 213932), with

the stipulation that the PP shall abide by the annual production scheduled specified in mining

plan and that any deviation there in will render the PP liable for legal action in accordance

with Environment and Mining Laws, with the specific and general conditions annexed at

Annexure ‘A’. Name of Proponent :- M/s Raghupati Mines & Minerals, Add.- LG-03

Murliwala Tower Jaipur Road, Tehsil.- Madanganj- Kishangarh, Distt.- Ajmer, (Raj.), Email-

[email protected], Consultant Name:- Cognizance Research India Private

Ltd. Add.- Office GT-20, Sec 177, Noida- 201301 (U.P.) Email:-

[email protected].

Agenda no. 29. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19611/ 2019-20

Project Name- EC for Udaipur Khurd Masonary Stone Mining Project, M.L. No. 22/2020,

Area 1.6893 Ha., Production Capacity- 2,63,158 TPA (ROM), Khasra No. 348/112, 349/112

and 436/348, Add.- Udaipur Khurd, Tehsil- Kishangarh, District- Ajmer, (Raj.) (Proposal

No.- 211368).

Project Proponent Name- M/s Shree Ji Stonex, Add.- N.H.8, Veer Taja Market, RAmner

Choraha, Ajmer Bypass, Tehil- Kishangarh, Distt.- Ajmer, (Raj.), Email-

[email protected].

Consultant Name- Cognizance Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301 (U.P.) Email:-

[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category /

Item no.

(in

Schedule):

1(a) B2

2. Location of

Project

Village: Udaipurkhurd, Tehsil - Kishangarh, District - Ajmer (Raj.)

Latitude - 26031’11.80196" to 26031’16.84456" N

Longitude - 74051’53.38545” to 74051’58.46638" E

3. Project

Details

M.L. No.

/Production

capacity

M.L. No. 22/2020

Khasra No.- 348/112, 349/112 & 436/348

Area- 1.6893 Hect.

Production capacity - 263158 TPA (ROM)

4. Project

Cost:

Project Cost: Rs. 50 Lac.

5. Water

Requiremen

Total water requirement is about 4.0 KLD= 2.0 KLD (Drinking & Domestic Uses) + 1.0

Final minutes of 4.95th meeting held on 27-29 July, 2021

t

& Source

KLD (Plantation) + 1.0 KLD (Dust Suppression). Water for Drinking, dust suppression

and plantation will be collected from nearby villages.

6. Fuel &

Energy:-

No electricity will be required in mining operations as mining will be carried out in day

time only. Diesel will be used for transportation vehicles.

7. Application

No. & Date

&

documents

submitted :-

Category : B2

SEAC FILE NO. : 19611

Date of documents Submitted : 19/05/2021

SEAC Meeting No. : 4.95th Meeting

Agenda Sr. No. : 29

Date of Presentation : 28/07/2021

8. Information

about

Aravalli

Certificate.

Aravalli Certificate has been issued by Mining Engineer, Ajmer (Raj.) vide letter No.

ME/Aj/Composit/Machi/Aravali Pra-/207 dated 06/05/2021

Date of Air/

Noise/Water

/Soil

Monitoring

Monitoring was conducted by Noida Testing Laboratories, Approved by NABL, Noida

Lab report have been submitted on Dated :- 12/06/2021

9. Information

about 500

mts

composite

map

500 mts composite map has been issued by Mining Engineer, Ajmer (Raj.) vide letter No.

ME/Aj/Composit/Machi/Aravali Pra-/207 dated 06/05/2021

Area falling within 500 mts 1.6893 ha.

Cluster Certificate No.: ME/Aj/Composit/Machi/Aravali Pra-/208 dated 06/05/2021

10. Environmen

t

Managemen

t Plan

Environment Management Plan Expenditures: Fixed Cost: Rs. 2.50 lacs, Recurring Cost:

Rs. 2.50 lacs per annum.

SI. No. Measures Exp. Cost in Rs.

(Fixed)

Exp. Cost in Rs.

(Recurring)

1

Pollution Control

i) Dust Suppression & Wet

Drilling

1,25,000 1,15,000

2

Pollution Monitoring

i) Air pollution

ii) Water pollution

- 10,000/-

3 Green Belt 1,25,000 1,25,000

Total 2,50,000/- 2,50,000/-

11. Green Belt/

Plantation

Expenditure of Green Belt Rs 1,25,000/-

Total green belt will be the 33% of the mine area 0.557 ha of the area and trees shall be

planted in 7.5m Statutory Barrier and Remaining part of own Khatedari land at village

Udaipur Khurd in Khasra No. 436/348, 348/112, 349/112. Native specie which are more

suitable to the local environment are preferred to be planted such as like Neem

(Azadiracta indica), Peepal (Ficus Religiosa), Mango (Mangifera indica), Shisham

(Dalbergia sissoo) etc. it is the proposed to invest 1.25 Lac. Rs. Per annum for greenbelt

Final minutes of 4.95th meeting held on 27-29 July, 2021

development

Year

7.5m Statutory

Barrier

Remaining Part of

own Khatedari land

at village Udaipur

Khurd in Khasra No.

436/348, 348/112,

349/112

Total

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

1st Year 0.076 76 0.11 110 0.186 186

2nd Year 0.076 76 0.11 110 0.186 186

3rd Year 0.075 75 0.11 110 0.185 185

Total 0.227 227 0.33 330 0.557 557

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing

mining operations, undertake re-grassing the mining area and any other area which

may have been disturbed due to their mining activities and restore the land to a

condition which is fit for growth of fodder, flora, fauna etc.

12. Budgetary

Breakup for

Labours

Expenditure of Labour Rs 50,000/-

Sr.

No.

Facility to be Provided for

Laborers

Exp. Cost in Rs.

(Fixed)

Exp. Cost in Rs.

(Recurring)

1. Drinking water facility 15,000/- 15,000/-

2.

Health Facility (First aid box, Rest

shelter, Medicine & Washroom) &

Insurance

15,000/- 15,000/-

3. Education for Labour children 10,000/- 10,000/-

4. Safety equipment like Ear plug, Dust

mask, hand gloves, Safety Shoes etc. 10,000/- 10,000/-

Total 50,000/- 50,000

13. Present

Status :-

Proposed Mine site (LOI Granted)

Observations of the committee:-

The SEAC considered/examined the project proposal on 28.07.2021by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for EC for Udaipur Khurd Masonary Stone Mining

Project, M.L. No. 22/2020, Area 1.6893 Ha., Production Capacity- 2,63,158 TPA (ROM),

Khasra No. 348/112, 349/112 and 436/348, Add.- Udaipur Khurd, Tehsil- Kishangarh,

District- Ajmer, (Raj.) (Proposal No.- 211368). The project is covered under B2 category.

The SME, Ajmer vide order dated 23.02.2021 has issued LoI to the PP for mining of

Masonry Stone. The mining plan has been approved by the SME, Ajmer vide letter dated

15.04.2021. ME, Ajmer in his certificate dated 06.05.2021 has stated that the mining lease

does not fall in Aravalli hills. DCF, Ajmer in its certificate dated 22.07.2021 has stated that

there is no Wildlife Sanctuary/National Park/ Conservation Reserve within 10 km periphery

of the mine. The project does not involve approval clearance under the Forest (Conservation)

Final minutes of 4.95th meeting held on 27-29 July, 2021

Act, 1980 and Wild Life Protection Act, 1972 as no forest land is involved and neither there

is any Wild Life Sanctuary/ National Park within 10 Km from the project site.

According to cluster map and cluster certificate dated 06.05.2021 issued by ME, Ajmer,

there is no cluster formation in terms of Notification dated 15.01.2016 and 01.07.2016.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1, Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to M/s Shree Ji

Stonex, for Udaipur Khurd Masonary Stone Mining Project, M.L. No. 22/2020, Area 1.6893

Ha., Production Capacity- 2,63,158 TPA (ROM), Khasra No. 348/112, 349/112 and 436/348,

Add.- Udaipur Khurd, Tehsil- Kishangarh, District- Ajmer, (Raj.) (Proposal No.- 211368),

with the stipulation that the PP shall abide by the annual production scheduled specified in

mining plan and that any deviation there in will render the PP liable for legal action in

accordance with Environment and Mining Laws, with the specific and general conditions

annexed at Annexure ‘A’. Name of Proponent M/s Shree Ji Stonex, Add.- N.H.8, Veer

Taja Market, RAmner Choraha, Ajmer Bypass, Tehil- Kishangarh, Distt.- Ajmer, (Raj.)

Email- [email protected], Consultant Name:- Cognizance Research India Private

Ltd. Add.- Office GT-20, Sec 177, Noida- 201301 (U.P.) Email:-

[email protected].

Agenda no. 30. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19612)/ 2019-20

Project Name- EC for Morajhari Granite Mining Project, Plot No. 106, Area 1.44 Ha.,

Production Capacity – 2,00,000 TPA (ROM), Khasra No. 1473 & 1735, Add.- Morajhari,

Tehsil- Nasirabad, District- Ajmer, (Raj.) (Proposal No.- 213570).

Project Proponent Name Shri- Raghav Chhaparwal S/o Shri- Shiv Prakash Chhaparwal,

Add.- Morajhari, Tehil- Nasirabad, Distt.- Ajmer, (Raj.) Email-

[email protected]

Consultant Name- Cognizance Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301 (U.P.) Email:-

[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category /

Item no.

(in

Schedule):

1(a) B2

2. Location of

Project

Village: Morajhari, Tehsil - Nasirabad, District - Ajmer (Raj.)

Latitude - 260 17’59.04741” to 260 17’59.72262”

Longitude - 740 55’38.57376” to 740 55’42.83612”

3. Project

Details

Plot No.

Plot No. 106

Khasra No.- 1473 & 1735

Final minutes of 4.95th meeting held on 27-29 July, 2021

/Production

capacity

Area- 1.44Hect.

Production capacity - 200000TPA (ROM)

4. Project

Cost:

Project Cost: Rs. 4Cr.

5. Water

Requiremen

t

& Source

Total water requirement is about 4.0 KLD= 1.0 KLD (Drinking & Domestic Uses) + 1.0 KLD

(Plantation) + 1.0 KLD (Dust Suppression). +1.0 KLD (Wire Saw cutting & Wet Drilling). Water for

Drinking, dust suppression and plantation will be collected from nearby villages.

6. Fuel & Energy:-

No electricity will be required in mining operations as mining will be carried out in day time only. Diesel will be used for transportation vehicles.

7. Application

No. & Date

&

documents

submitted :-

Category : B2

SEAC FILE NO. : 19612

Date of documents Submitted :

SEAC Meeting No. : 4.95

Agenda Sr. No. : 30

Date of Presentation : 28/7/2021

8. Information

about

Aravalli

Certificate.

Aravalli Certificate has been issued by Mining Engineer, Ajmer (Raj.) vide letter No.

SME/Aj/Mining Plan/F-A-119/2021/3756 date 10/6/2021.

Date of Air/

Noise/Wate

r/Soil

Monitoring

Monitoring was conducted by Noida Testing Laboratories, Approved by NABL, Noida

Lab report have been submitted on Dated :- 12/6/2021

9. Information

about 500

mts

composite

map

500 mts composite map has been issued by Mining Engineer, Ajmer (Raj.) vide letter No.

ME/Beawar/Composite/Map/249 date 12/7/2021

Area falling within 500 mts 1.00ha.

Cluster Certificate No.: ME/AJ/Composite/Machi/Aravali Pra-/214 date 25/5/2021

10. Environme

nt

Manageme

nt Plan

Environment Management Plan Expenditures: Fixed Cost: Rs. 3.0 lacs, Recurring Cost: Rs. 20.0 lacs per annum.

S.

No. Measures

Capital Cost

(Rs. In lakh.)

Recurring Cost

(Rs. in

lakh./annum)

1 Pollution Control i) Dust Suppression, Wet Drilling & Others

90,000/- 3,85,000/-

2 Pollution Monitoring i) Air pollution ii) Water pollution

10,000/- 15,000/-

3 Green Belt 1,00,000/- 2,00,000/-

4 Road Maintenance 1,00,000/- 8,00,000/-

Total 3,00,000/- 20,00,000/-

11. Green Belt/

Plantation

Expenditure of Green Belt Rs 2,00,000/-

Total green belt will be the 33% of the mine area 0.474 ha of the area shall be carried out part of

Govt. Charagah. Land at Village Morajhari in Khasra No. 23.

Native specie which are more suitable to the local environment are preferred to be planted such as

like Neem (Azadiracta indica), Peepal (Ficus Religiosa), Mango (Mangifera indica), Shisham

Final minutes of 4.95th meeting held on 27-29 July, 2021

(Dalbergia sissoo) etc. it is the proposed to invest 2.0 Lac. Rs. Per annum for greenbelt development

Year

Outside the lease

area (part of Govt.

Charagah. Land at

Village Morajhari in

Khasra No. 23)

7.5 m Statuary barrier

& Top Soil Dumps Total

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

1st Year 0.158 158

0.158 158

2nd Year 0.158 158

0.158 158

3rd Year 0.158 158

0.158 158

Total 0.474 474

0.474 474

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing mining

operations, undertake re-grassing the mining area and any other area which may have been

disturbed due to their mining activities and restore the land to a condition which is fit for growth

of fodder, flora, fauna etc.

12. Budgetary

Breakup for

Labours

Expenditure of Labour Rs 4,00,000/-

Sl.

No.

Facility to be Provided for

Laborers

Capital Cost

(Fixed)

Recurring Cost

1 Drinking water facility 30,000/- 1,30,000/-

2 Health Facility (First aid box, Rest shelter, Medicine & Washroom) & Insurance

25,000/- 1,00,000/-

3 Education for labor’s children 25,000/- 1,00,000/-

4 Safety equipment like Ear plug, Dust mask, hand gloves, Safety Shoes etc.

20,000/- 70,000/-

Total 1,00,000 4,00,000/-

13. Present

Status :-

Proposed Mine site (LOI Granted)

Observations of the committee:-

The SEAC considered/examined the project proposal on 28.07.2021by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for EC for Morajhari Granite Mining Project, Plot

No. 106, Area 1.44 Ha., Production Capacity – 2,00,000 TPA (ROM), Khasra No. 1473 &

1735, Add.- Morajhari, Tehsil- Nasirabad, District- Ajmer, (Raj.) (Proposal No.- 213570).

The project is covered under B2 category. The SME, Ajmer vide order dated 28.04.2021 has

issued LoI to the PP for mining of Granite. The mining plan has been approved by the SME,

Ajmer vide letter dated 10.06.2021. ME, Ajmer in his certificate dated 25.05.2021 has stated

that the mining lease does not fall in Aravalli hills. DCF, Ajmer in its certificate dated

04.06.2021 has stated that there is no Wildlife Sanctuary/National Park/ Conservation

Reserve within 10 km periphery of the mine. The project does not involve approval/

clearance under the Forest (Conservation) Act, 1980 and Wild Life Protection Act, 1972 as

no forest land is involved and neither there is any Wild Life Sanctuary/ National Park within

10 Km from the project site.

According to cluster map and cluster certificate dated 25.05.2021 issued by ME,

Ajmer, there is no cluster formation in terms of Notification dated 15.01.2016 and

01.07.2016.

Final minutes of 4.95th meeting held on 27-29 July, 2021

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-1,

Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri- Raghav

Chhaparwal S/o Shri- Shiv Prakash Chhaparwal for Morajhari Granite Mining Project, Plot

No. 106, Area 1.44 Ha., Production Capacity – 2,00,000 TPA (ROM), Khasra No. 1473 &

1735, Add.- Morajhari, Tehsil- Nasirabad, District- Ajmer, (Raj.) (Proposal No.- 213570).

with the stipulation that the PP shall abide by the annual production scheduled specified in

mining plan and that any deviation there in will render the PP liable for legal action in

accordance with Environment and Mining Laws, with the specific and general conditions

annexed at Annexure ‘A’. Name of Proponent Shri- Raghav Chhaparwal S/o Shri- Shiv

Prakash Chhaparwal, Add.- Morajhari, Tehil- Nasirabad, Distt.- Ajmer, (Raj.), Email-

[email protected], Consultant Name:- Cognizance Research India Private Ltd.

Add.-Office GT-20, Sec 177, Noida- 201301 (U.P.), Email:-

[email protected].

Agenda no. 31. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19613)/ 2019-20

Project Name- EC for Morajhari Granite Mining Project, Plot No. 109, Area 1.32 Ha., ,

Production Capacity- 1,88,412 TPA (ROM), Khasra No. 1473 & 1735, Add.- Morajhari,

Tehsil- Nasirabad, District- Ajmer, (Raj.) (Proposal No.- 213575).

Project Proponent Name- Shri- Raghav Chhaparwal S/o Shri- Shiv Prakash Chhaparwal,

Add.- Morajhari, Tehil- Nasirabad, Distt.- Ajmer, (Raj.), Email-

[email protected].

Consultant Name- Cognizance Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301 (U.P.) Email:-

[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category / Item no.(in

Schedule):

1(a) B2

2. Location of Project Village – Morajhari, Tehsil- Nasirabad, District- Ajmer (Raj.)

Latitude : 260 17‘59.04741'' to 260 18‘07.40633''

Longitude : 740 55'39.32287'' to 750 55‘43.97922''

3. Project Details

M.L No. /Production

capacity

(Plot No.- 109),

Khasra No. 1473 & 1735

Area - 1.32 Hect.

Prop. Production Capacity - 188412 TPA (ROM)

4. Project Cost: Rs. 3 Cr.

Final minutes of 4.95th meeting held on 27-29 July, 2021

5. Water Requirement

& Source

Total water requirement is about 8.0 KLD = 2.0 KLD (Drinking & Domestic Uses) + 2.0 KLD

(Plantation) + 1.0 KLD (Dust Suppression) + 3.0 KLD (Wire Saw cutting & Wet Drilling).

Drinking water will be brought from the nearby Tube-wells and water for dust suppression and

plantation will be collected from nearby villages.

6. Fuel & Energy:- Only diesel will be required to run vehicles for transportation. No electricity will be needed in the

proposed project.

7. Application No. & Date

& documents submitted

:-

Category : B2 SEAC FILE NO. : 19613

Date of documents Submitted : 12/6/2021

SEAC Meeting No. : 4.95th Meeting

Agenda Sr. No. : 31

Date of Presentation : 28/07/2021

8. Information about

Aravalli Certificate.

Aravalli Certificate has been issued by Mining Engineer, Ajmer vide letter No.

ME/Aj/Composite/Map/Aravalli Pra-/215 dated 25/5/2021

9. Date of

Air/Water/Noise

Monitoring was conducted by Noida Testing Laboratories., Approved by NABL, Noida

10. Information about 500

mts composite map

500 mts composite map has been issued by Mining Engineer, Ajmer vide letter No.

ME/Aj/Composite/Map/Aravalli Pra-/216 dated 25/5/2021

Area falling within 500 mts is 1.32 ha

11. Environment

Management Plan

Environment Management Plan Expenditures: Capital Cost: Rs. 12,00,000/- Recurring Cost: Rs

12,00,000/- per annum

SI. No. Measures Exp. Cost in Rs.

(Fixed)

Exp. Cost in Rs.

(Recurring Yearly)

1

Pollution Control

i) Road Preparation and maintenance

ii) Dust Suppression & Wet Drilling & other

6,00,000/- 6,00,000

2

Pollution Monitoring

i) Air pollution

ii) Water pollution

-- 15,000/-

3 Green Belt 6,00,000/- 5,85,000

Total 12,00,000/- 12,00,000/-

Final minutes of 4.95th meeting held on 27-29 July, 2021

12. Green Belt/ Plantation Expenditure of Green Belt Rs 5,85,000/-per year

Total green belt will be the 33% of the mine area 0.435 ha of the area will be planted in the part of

govt. charagrah land at village Morajhari in khasra no. 23

Native specie which are more suitable to the local environment are preferred to be planted such as

like Neem (Azadiracta indica), Pipal (Ficus religiosa), Babool (Acacia nilotica), Kher (Acacia

catechu) etc. it is the proposed to invest 5,85,000 Rs. Per annum for greenbelt development

Year

Outside the lease

area(part of govt

charagrah land at village

Morajhari in khasra no.

23)

Top Soil Dumps Total

Area (Ha.) No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

1st Year 0.145 145 -- -- 0.145 145

2nd Year 0.145 145 -- -- 0.145 145

3rd Year 0.145 145 -- -- 0.145 145

Total 0.435

Hect.

435 -- -- 0.435

Hect.

435

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing mining

operations, undertake re-grassing the mining area and any other area which may have been

disturbed due to their mining activities and restore the land to a condition which is fit for

growth of fodder, flora, fauna etc.

13. Budgetary Breakup for

Labour

The information regarding Budgetary breakup for labour has been given in PFR & Power Point

Presentation

Sr. No. Facility to be Provided for Laborers Exp. Cost in Rs.

(Fixed)

Exp. Cost in Rs.

(Recurring Yearly)

1. Drinking water facility 80,000 80,000

2.

Health Facility (First aid box, Rest

shelter, Medicine & Washroom) &

Insurance

80,000 80,000

3. Education for Labours children 70,000 70,000

4. Safety equipment like Ear plug, Dust

mask, hand gloves, Safety Shoes etc. 70,000 70,000

Total 3,00,000 1,50,000

14. Present Status :- LOI Granted

Observations of the committee:-

The SEAC considered/examined the project proposal on 28.07.2021by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for EC for Morajhari Granite Mining Project, Plot

No. 109, Area 1.32 Ha., Production Capacity- 1,88,412 TPA (ROM), Khasra No. 1473 &

1735, Add.- Morajhari, Tehsil- Nasirabad, District- Ajmer, (Raj.) (Proposal No.- 213575).

The project is covered under B2 category. The SME, Ajmer vide order dated 28.04.2021 has

issued LoI to the PP for mining of Granite. The mining plan has been approved by the SME,

Ajmer vide letter dated 10.06.2021. ME, Ajmer in his certificate dated 25.05.2021 has stated

that the mining lease does not fall in Aravalli hills. DCF, Ajmer in his certificate dated

Final minutes of 4.95th meeting held on 27-29 July, 2021

04.06.2021 has stated that there is no Wildlife Sanctuary/National Park/ Conservation

Reserve within 10 km periphery of the mine. The project does not involve approval/

clearance under the Forest (Conservation) Act, 1980 and Wild Life Protection Act, 1972 as

no forest land is involved and neither there is any Wild Life Sanctuary/ National Park within

10 Km from the project site.

According to cluster map and cluster certificate dated 25.05.2021 issued by ME, Ajmer,

there is no cluster formation in terms of Notification dated 15.01.2016 and 01.07.2016.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1,Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri- Raghav

Chhaparwal S/o Shri- Shiv Prakash Chhaparwal, for Morajhari Granite Mining Project, Plot

No. 109, Area 1.32 Ha., Production Capacity- 1,88,412 TPA (ROM), Khasra No. 1473 &

1735, Add.- Morajhari, Tehsil- Nasirabad, District- Ajmer, (Raj.) (Proposal No.- 213575),

with the stipulation that the PP shall abide by the annual production scheduled specified in

mining plan and that any deviation there in will render the PP liable for legal action in

accordance with Environment and Mining Laws, with the specific and general conditions

annexed at Annexure ‘A’. Name of Proponent Shri- Raghav Chhaparwal S/o Shri- Shiv

Prakash Chhaparwal, Add.- Morajhari, Tehil- Nasirabad, Distt.- Ajmer, (Raj.) Email-

[email protected], Consultant Name:- Cognizance Research India Private Ltd.

Add.-Office GT-20, Sec 177, Noida- 201301 (U.P.) Email:-

[email protected].

Agenda no. 32. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19614)/ 2019-20

Project Name- EC for Ladera Granite Mining Project, Ref. No. 2019100002852, Area

1.0308 Ha., Khasra No. 1743/1177 & 1178, Production capacity 84000 TPA(ROM) Add.-

Ladera, Tehsil- Dudu, District- Jaipur, (Raj.) (Proposal No.- 208660)

Project Proponent Name- M/s Unique Granites, Add.- Shah Gokul Chand Manohar Lal

Near Balaji Temple, Kishangarh, Distt.- Ajmer, (Raj.) Shri- Abhishek Baheti S/o Shri- Jugal

Kishor Baheti, Add.- Baheti Bhavan, Katla Bazar, Madangaj, Kishangarh, Distt.- Ajmer,

(Raj.) Email- [email protected]

Consultant Name- Cognizance Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301 (U.P.) Email:-

[email protected].

Observations and Resolution of the committee:-

The PP vide letter dated 28.07.2021 has submitted an application for deferment of the

case. The SEAC agreed to the request of the PP and deferred the matter. The project shall be

taken up again on receipt of his request for consideration of the project by the PP, in the

subsequent proposed meeting.

Final minutes of 4.95th meeting held on 27-29 July, 2021

Agenda no. 33. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19615)/ 2019-20

Project Name- Environmental Clearance for Amargarh (Chang) Granite Mining Project, Plot

No.- 48, Area-2.00 ha., Production Capacity -2,33,516 TPA (ROM), Khasra no 84, Near

Vill.- Amargarh, Tehsil- Raipur, Distt.-Pali(Raj.) (Proposal No.-211255).

Project Proponent Name- Shri Pushpendra Singh, Add.- R/o--Behind Shiv Temple, Jaton

Ka Bans, Jasnagar, Tehsil- Riyanbadi, Distt.- Nagaur (Raj.) Email-

[email protected].

Consultant Name- Cognizance Research India Private Ltd., Add.-Office GT-20, Sec 177,

Noida- 201301 (U.P.)email:- [email protected].

Observations and Resolution of the committee:-

The SEAC considered/examined the project proposal on 28.07.2021by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for Environmental Clearance for Amargarh (Chang)

Granite Mining Project, Plot No.- 48, Area-2.00 ha., Production Capacity- 2,33,516 TPA

(ROM), Khasra no 84, Near Vill.- Amargarh, Tehsil- Raipur, Distt.-Pali(Raj.) (Proposal No.-

211255). The project is covered under B2 category. The SME, Ajmer vide order dated

21.12.2020 has issued LoI to the PP for mining of Granite. The mining plan has been

approved by the SME, Ajmer vide letter dated 25.03.2021 ME, Beawar in his certificate

dated 12.04.2021 has stated that the mining lease does not fall in Aravalli hills.

The SEAC considered the certificate dated 12.04.2021 issued by ME, Beawar. In

the certificate, it is stated that as per the MoEF & CC notification, dated 01.07.2016 there is

no other mining lease within the periphery of 500 meter and therefore, there is no cluster

formation

The PP has not submitted certificate from the concerned DCF regarding existence or

otherwise of National Park or Wildlife Sanctuary from the applied lease area. The PP has not

clearly stated the place where green belt will be developed and permission of the competent

authority/ person to develop green belt on that land. The SEAC, therefore, decided to ask the

PP to submit the same within a period of 45 days failing which the project shall be

recommended to SEIAA for closure and delistment.

Agenda no. 34. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19616)/ 2019-20

Project Name- Environmental Clearance for Rambari Quartz & Feldspar Mining Project,

ML. No.- 10/2009, Area- 4.00 ha., Production capacity- 93,272 TPA (ROM), Khasra No.

124,125,126,120,117,118, Near Vill.- Rambari, Tehsil- Nasirbad, Distt.- Ajmer(Raj.)

(Proposal No.- 211340).

Project Proponent Name- Shri Chand Mohammad, Add.- R/o- Near Bus Stand, Vill.-

Ramsar, Tehsil- Nasirabad, Distt.- Ajmer (Raj.), Email- [email protected].

Final minutes of 4.95th meeting held on 27-29 July, 2021

Consultant Name- Cognizance Research India Private Ltd., Add.-Office GT-20, Sec 177,

Noida-201301(U.P.)email:[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

S.

No

.

Partic

ulars

Details/Information

1. Cat./ Item

no. (in schedule):

1 (a)-B2

2. Location of the Project

Near village –Rambari, Tehsil: Nasirabad, District: Ajmer(Rajasthan)

3. Project Details M.L No./ Production

Capacity

M.L. No. : 10/2009 Khasra No. : 124,125,126,120,117,118 Area : 4.0HECT.

Production (TPA)

: 93272 TPA(ROM) Quartz &Feldspar (Saleable Mineral- 35045TPA, Waste- 16174TPA& Sub Grade- 42053 TPA)

Details are given in cover page of Proposal obtaining of Environmental Clearance

4. Project Cost

Project Cost: Rs80.0lacs/-(in Rs.) Details are given in cover page of Proposal obtaining of Environmental Clearance

5. Water requirement

& Source

Total water requirement is about 3.0 KLD= 1.0 KLD (Drinking & Domestic Uses) + 0.8 KLD (Plantation) + 0.7 KLD (Dust Suppression) + 0.5 KLD (Wet Drilling). Water for Drinking, dust suppression and plantation will be collected from nearby villages.

6. Fuel & Energy

Diesel will be used for transportation vehicles.

7. Application no., Date of Documents Submi

tted

Category : B2 SEAC FILE NO. : 19616 Date of documents Submitted :14/05/2021 SEAC Meeting No. :4.95thMeeting Agenda Sr. No. :34 Date of Presentation : 28/07/2021

8. Information about Aravalli certifi

cate

Aravalli Certificate has been issued byMining Engineer, Ajmervide letter No.ME/Aj/Composite/Machi/AravaliPra-/69 on dated 05/02/2021.

9. Date of Air, Water, Noise, monitoring

Monitoring was conducted byNoida Testing Laboratories., Approved by NABL, Noida.

10. Information about 500 mts composite map

500 mts composite map has been issued by Mining Engineer, Ajmervide letter No. ME/Aj/Composite/Machi/AravaliPra-/69 on dated 05/02/2021. Area falling within 500 mts8.0 Ha.

Final minutes of 4.95th meeting held on 27-29 July, 2021

Observations of the committee:-

The SEAC considered/examined the project proposal on 28.07.2021by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

This is an existing lease. Initially, the mining lease for mineral Quartz & Feldspar,

Area- 4.0 ha., was granted in favour of Shri Chand Mohammad S/o.- Mr. Nasiruddin by vide

11. EMP Activities

Environment Management Plan Expenditures: Capital Cost: Rs. 4.0 lacs Recurring Cost: Rs. 4.0lacs per annum.

Sr.

No. Particulars Capital Cost

(in Rs. Lac) Recurring Cost (in

Rs. Lac)

1. Pollution Control i) Dust Suppression

1,95,000/- 1,95,000/-

2. Pollution Monitoring

i) Air pollution ii) Water pollution

-- 10,000/-

3. Green Belt 2,05,000/- 1,95,000/-

Total 4,00,000/- 4,00,000/-

12. Greenbelt & Plantation

Expenditure of Green Belt Rs 1,95,000/- Total green belt will be the 33% of the mine area 1.32 ha of the area shall be planted in the Part of Govt. Charahgah land at village Ramsar in khasra no.-9171. Nativespecie which are more suitable to the local environment are preferred to be planted such as like Neem (Azadiractaindica), Pipal (Ficusreligiosa), Mango (MangiferaIndica), Amla(PhyllanthusEmblica) etc. it is the proposed to invest 1.95 Lac. Rs. Per annum for greenbelt devlopment

Yea

r

Outside the lease area( Part of Govt. Charahgah

land at village Ramsar in khasra no.-9171)

Top Soil

Dumps Total

Area (Ha.) No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

1st

Yea

r

0.440 440 -- -- 0.440 440

2nd

Yea

r

0.440 440 -- --

0.440 440

3rd

Yea

r

0.440 440

-- --

0.440 440

Tot

al

1.320 1320 -- -- 1.320 1320

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing mining operations,

undertake re-grassing the mining area and any other area which may have been disturbed due to their

mining activities and restore the land to a condition which is fit for growth of fodder, flora, fauna etc.

13. Budgetary breakup for labour

The information regarding Budgetary breakup for labour has been given in PFR & Power Point Presentation

Sr. No. Facility provided for Labour Capital Cost in Rs. Recurring cost in Rs.

1. Drinking water facility 10,000/- 20,000/-

2. Health Facility (First aid box, Rest shelter,

Medicine & Washroom) & Insurance 10,000/- 20,000/-

3. Education for Labour children 10,000/- 20,000/-

4. Safety equipment like Ear plug, Dust mask, hand gloves, Safety Shoes etc.

10,000/- 20,000/-

Total 40,000/- 80,000/-

14. Present Status

M.L Granted

Final minutes of 4.95th meeting held on 27-29 July, 2021

order dated 03.08.2010. The lease was registered on 22.11.2010 for 30 years. The lease

validity was auto extended for 50 years and valid up to 21.11.2060.

The project being one of major mineral (before 10.02.2015) having lease area of 4.0

ha.(less than 5.0 ha.), came under the purview of the EIA Notification dated 07.10.2014 of

the MoEF & CC. According to the certificates dated 21.05.2014, 17.07.2015, 17.08.2016 and

15.07.2021 of ME, Ajmer the production of mineral from 2013-14 (base year) to 30.06.2021

has been nil. The project, therefore, is not one of violation of the EIA Notification. The PP

has also submitted affidavit to the affect that no activity has been carried out in violation of

the EIA Notification and Common Cause Judgment pronounced by the Hon’ble Supreme

Court.

The PP has submitted application for Rambari Quartz & Feldspar Mining Project,

ML. No.- 10/2009, Area- 4.00 ha., Production capacity- 93,272 TPA (ROM), Khasra No.

124, 125, 126, 120, 117, 118, Near Vill.- Rambari, Tehsil- Nasirbad, Distt.- Ajmer(Raj.)

(Proposal No.- 211340). The project is covered under B2 category. The mining plan has been

approved by the SME, Ajmer vide letter dated 15.04.2021. ME, Ajmer in his certificate dated

05.02.2021 has stated that the mining lease does not fall in Aravalli hills. DCF, Ajmer and in

his certificate dated 25.03.2021 has stated that there is no Wildlife Sanctuary/National Park/

Conservation Reserve within 10 km periphery of the mine. The project does not involve

approval/ clearance under the Forest (Conservation) Act, 1980 and Wild Life Protection Act,

1972 as no forest land is involved and neither there is any Wild Life Sanctuary/ National Park

within 10 Km from the project site.

As per cluster certificate issued by ME, Ajmer on 05.02.2021, the total area of all the

mining leases in the cluster having area of 4.0 ha. ME, Ajmer in his cluster certificate dated

05.02.2021 has also mentioned that the lease area falls in Sonkhaliya Conservation Reserve.

The SEAC, however, was of the view that no such conservation reserve has been notified in

the district. The DCF, Ajmer in his certificate dated 25.03.2021 has also not mentioned about

existence of such conservation reserve in the area.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1,Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri Chand

Mohammad, for Rambari Quartz & Feldspar Mining Project, ML. No.- 10/2009, Area- 4.00

ha., Production capacity- 93,272 TPA (ROM), Khasra No. 124,125,126,120,117,118, Near

Vill.- Rambari, Tehsil- Nasirbad, Distt.- Ajmer(Raj.) (Proposal No.- 211340), with the

stipulation that the PP shall abide by the annual production scheduled specified in mining

plan and that any deviation there in will render the PP liable for legal action in accordance

with Environment and Mining Laws, with the specific and general conditions annexed at

Annexure ‘A’. Name of Proponent Shri Chand Mohammad, Add.- R/o-- Near Bus Stand,

Vill.- Ramsar, Tehsil- Nasirabad, Distt.- Ajmer (Raj.) Email-

[email protected], Consultant Name:- Cognizance Research India Private

Ltd., Add.-Office GT-20, Sec 177, Noida- 201301 (U.P.)email:-

Final minutes of 4.95th meeting held on 27-29 July, 2021

[email protected].

Agenda no. 35. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19625)/ 2019-20

Project Name- EC for Granite Mining Project, Plot No. 108, Area 1.50 Ha., Production

Capacity 2,00,004 TPA (ROM), Khasra No. 1473, Add.- Morajhari, Tehsil- Nasirabad,

District- Ajmer, (Raj.) (Proposal No.- 215442).

Project Proponent Name- Shri- Naresh Agarwal, Add.- Sadar Bazar, Tantoti, Distt.- Ajmer,

(Raj.), Email- [email protected].

Consultant Name- Cognizance Research India Private Ltd. Add.-

Office GT-20, Sec 177, Noida- 201301 (U.P.) Email:-

[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

S.N

o.

Particula

rs

Details/Information

1. Cat./ Item no. (in

schedule)

:

1 (a)-B2

2. Location of the

Project

Near village – Morajhari, Tehsil: Nasirabad, District: Ajmer (Rajasthan)

3. Project Details

M.L No./

Productio

n Capacity

Plot. No. : 108 Khasra No. : 1473

Area : 1.50 HECT.

Production (TPA) : 200004 TPA(ROM)

Details are given in cover page of Proposal obtaining of Environmental Clearance

4. Project

Cost

Project Cost: Rs 3.60Cr/-(in Rs.)

Details are given in cover page of Proposal obtaining of Environmental Clearance

5. Water

requirem

ent &

Source

Total water requirement is about 5.0 KLD= 1.0 KLD (Drinking & Domestic Uses)

+ 2.0 KLD (Plantation) + 2.0 KLD (Dust Suppression). 1.0 KLD Wire Saw

cutting & Wet Drilling. Water for Drinking, dust suppression and plantation will

be collected from nearby villages.

6. Fuel &

Energy Only diesel will be required to run vehicles for transportation. Electricity will be

required for drill machines which will be fulfilled by proposed DG Set.

7. Application no.,

Date of

Documents

Submitte

d

Category : B2 SEAC FILE NO. : 19625

Date of documents Submitted : 23/06/2021

SEAC Meeting No. : 4.95th Meeting Agenda Sr. No. : 35

Date of Presentation : 28/07/2021

8. Information about

Aravalli

certificate

Aravalli Certificate has been issued by Mining Engineer, Ajmer vide letter No. ME/AJ/COMP/Map/ARAVALI-/P/2020 Date 25/05/2021

9. Date of Air,

Monitoring was conducted by Noida Testing Laboratories Approved by NABL.

Final minutes of 4.95th meeting held on 27-29 July, 2021

Water, Noise,

monitorin

g

10. Information about

500 mts

composite map

500 mts composite map has been issued by Mining Engineer, Ajmer vide letter No. ME/AJ/COMP/Map/ARAVALI-/P/2020 Date 25/05/2021

Area falling within 500 mts 1.50ha.

11. EMP

Activities

Environment Management Plan Expenditures: Capital Cost: Rs. 14.4lacs

Recurring Cost: Rs. 14.4 lacs per annum.

SI. No. Measures Exp. Cost in Rs.

(Fixed)

Exp. Cost in Rs.

(Recurring)

1

Pollution Control

i) Dust

Suppression

ii) Road

Preparation

and

maintenance

7,00,000/- 7,00,000/-

2

Pollution Monitoring

i) Air pollution

ii) Water pollution

15,000/- 15,000/-

3 Green Belt 7,25,000/- 7,25,000/-

Total 14,40,000/- 14,40,000/-

12. Greenbelt

& Plantatio

n

Expenditure of Green Belt Rs 7,25,000/- Total green belt will be the 33% of the mine area 0.495ha of the area shall be planted in

the part of Govt. Charagah land at village Morajhari in khasra no. 23. Native specie

which are more suitable to the local environment are preferred to be planted such as like Aam ( Mangifera indica ), Imli ( Tamarindus indica ), Shisham ( Dalbergia sisso ) etc.

it is the proposed to invest 7.25Lac. Rs. Per annum for greenbelt devlopment

Year

Outside the lease area( Govt. Charagah land at

village Morajhari in

khasra no. 23)

Top Soil

Dumps Total

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

1st

Year 0.165 165 -- -- 0.165 165

2nd

Year 0.165 165

-- -- 0.165 165

3rd

Year 0.165 165

-- -- 0.165 165

Total 0.495 495 -- -- 0.495 495

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing

mining operations, undertake re-grassing the mining area and any other area which

may have been disturbed due to their mining activities and restore the land to a

condition which is fit for growth of fodder, flora, fauna etc.

13. Budgetar

y breakup

for labour

The information regarding Budgetary breakup for labour has been given in PFR &

Power Point Presentation

Final minutes of 4.95th meeting held on 27-29 July, 2021

Observations of the committee:-

The SEAC considered/examined the project proposal on 28.07.2021by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for EC for Granite Mining Project, Plot No. 108,

Area 1.50 Ha., Production Capacity 2,00,004 TPA (ROM), Khasra No. 1473, Add.-

Morajhari, Tehsil- Nasirabad, District- Ajmer, (Raj.) (Proposal No.- 215442). The project is

covered under B2 category. The SME, Ajmer vide order dated 28.04.2021 has issued LoI to

the PP for mining of Granite. The mining plan has been approved by the SME, Ajmer vide

letter dated 16.06.2021. ME, Ajmer in his certificate dated 25.05.2021 has stated that the

mining lease does not fall in Aravalli hills. DCF, Ajmer and DCF, Tonk in their certificates

dated 23.07.2021 and 23.02.2021, respectively have stated that there is no Wildlife

Sanctuary/National Park/ Conservation Reserve within 10 km periphery of the mine. Besides,

the PP in Form-1 has also stated that there is no WLS, National Park and Conservation

Reserve within 10 Km of the project site.

The project does not involve approval/ clearance under the Forest (Conservation)

Act, 1980 and Wild Life Protection Act, 1972 as no forest land is involved and neither there

is any Wild Life Sanctuary/ National Park within 10 Km from the project site.

According to cluster map and cluster certificate dated 25.05.2021 issued by ME,

Ajmer, there is no cluster formation in terms of Notification dated 15.01.2016 and

01.07.2016.

Resolution:

Sr.

No.

Facility to be Provided for

Laborers

Exp. Cost in

Rs.

(Fixed)

Exp. Cost in

Rs.

(Recurring)

1. Drinking water facility 1,10,000/- 1,10,000/-

2.

Health Facility (First aid box, Rest

shelter, Medicine & Washroom)

& Insurance

1,00,000/- 1,00,000/-

3. Education for Labours children 80,000/- 80,000/-

4.

Safety equipment like Ear plug,

Dust mask, hand gloves, Safety

Shoes etc.

70,000/- 70,000/-

Total 3,60,000/- 3,60,000/-

14. Present Status

LOI Granted

Final minutes of 4.95th meeting held on 27-29 July, 2021

The SEAC upon appraisal of the project in the light of information contained in Form-

1,Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri- Naresh

Agarwal, for Granite Mining Project, Plot No. 108, Area 1.50 Ha., Production Capacity

2,00,004 TPA (ROM), Khasra No. 1473, Add.- Morajhari, Tehsil- Nasirabad, District-

Ajmer, (Raj.) (Proposal No.- 215442), with the stipulation that the PP shall abide by the

annual production scheduled specified in mining plan and that any deviation there in will

render the PP liable for legal action in accordance with Environment and Mining Laws, with

the specific and general conditions annexed at Annexure ‘A’. Name of Proponent Shri-

Naresh Agarwal, Add.- Sadar Bazar, Tantoti, Distt.- Ajmer, (Raj.), Email-

[email protected], Consultant Name:- Cognizance Research India Private

Ltd. Add.- Office GT-20, Sec 177, Noida- 201301 (U.P.) Email:-

[email protected].

Agenda no. 36. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(18031)/ 2019-20

Project Name- ToR/ EC for Quartz and Feldspar Mining project, M.L. No. 15/03, Mining

Lease Area 4.0 Hect., Khasra No. 8566, Proposed Capacity 80,553 TPA (ROM){

Mineral:47,817 TPA {(Quartz- 4782 TPA & feldspar 43,035 TPA), Waste- 32,736 TPA}

Near Vill.– Devipura, Tehsil- Masuda, Distt.- Ajmer, (Raj. (Proposal No. 139295).

Project Proponent Name- Shri Akhil Sharma, Add.- C-53, RIICO Housing Colony, Ajmer

Road, Tehsil - Beawar Distt.- Ajmer, (Raj.), Email. [email protected].

Consultant Name- GAURANG ENVIRONMENTAL SOLUTIONS PVT. LTD. Add.- 102,

SNG, Shri Ratna Apartment, Near Tambi Petrol Pump, Peetal Factory, Jhotwara Road,

Jaipur, (Rajasthan), Email.– [email protected].

Observations and Resolution of the committee:-

The SEAC considered/examined the project proposal on 28.07.2021by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

This is an existing lease. LOI with respect to the mining lease was issued vide order

dated 08.04.2010 in favour of Sh. Prasann Kumar Singhvi for a period of 20 years. The lease

deed was registered on 11.03.2014. The validity of mining lease was extended for 50 years.

The lease is therefore valid from 11.03.2014 to 10.03.2064. Later on the lease was transferred

in favour of Shri Akhil Sharma vide order dated 31.07.2017.

The project being one of major mineral (before 10.02.2015) having lease area of 4.0

ha.(less than 5.0 ha.), came under the purview of the EIA Notification dated 07.10.2014 of

the MoEF & CC. The certificate dated 22.01.2020 issued by ME, Beawar shows that the PP

started mining activity without obtaining prior EC from the regulatory authority in violation

of the provisions of the EIA Notification, 2006. The certificate shows that 2680 MT of

Feldspar in the year 2014-15 and 5650 MT in the year 2015-16 was mined out without

obtaining prior EC from the regulatory authority. The project, therefore, is one of violation

of the EIA Notification.

Final minutes of 4.95th meeting held on 27-29 July, 2021

The PP has submitted application for ToR/ EC for Quartz and Feldspar Mining

project, M.L. No. 15/03, Mining Lease Area 4.0 Hect., Khasra No. 8566, Proposed Capacity

80,553 TPA (ROM){ Mineral: 47,817 TPA {(Quartz- 4782 TPA & feldspar 43,035 TPA),

Waste- 32,736 TPA} Near Vill.– Devipura, Tehsil- Masuda, Distt.- Ajmer, (Raj. (Proposal

No. 139295). The project is covered under B2 category. The mining plan has been approved

by the SME, Ajmer vide letter dated 15.11.2019. ME, Beawar in his certificate dated

11.01.2021 has stated that the mining lease does not fall in Aravalli hills. DCF, Ajmer its

certificate dated 22.01.2020 has stated that there is no Wildlife Sanctuary/National Park/

Conservation Reserve within 10 km periphery of the mine. The project does not involve

approval/ clearance under the Forest (Conservation) Act, 1980 and Wild Life Protection Act,

1972 as no forest land is involved and neither there is any Wild Life Sanctuary/ National Park

within 10 Km from the project site.

The SEAC considered the certificate dated 11.01.2021 issued by ME, Beawar. In the

certificate, it is stated that as per the MoEF & CC notification, dated 01.07.2016 there is no

other mining lease within the periphery of 500 meter and therefore, there is no cluster

formation.

The SEAC examined the project in the light of OM dated 12.11.2020 of the MoEF &

CC. This OM provides that while considering the application for EC under violation category

as per Notification dated 14.03.2017 of the MoEF & CC, the SEAC may insist upon public

hearing to be conducted only for those category of projects for which EIA Notification, 2006

itself requires public hearing to be conducted. The project, under consideration, is one of ‘B2’

category and being so does not require public hearing as per EIA Notification, 2006 read with

various OM’s and guidelines issued by the MoEF & CC, from time to time.

The SEAC, in view of the project being one of violation of the EIA notification as

also in terms of Common Cause judgment of the Hon’ble Supreme Court, decided that the PP

is required to conduct Environmental Impact Assessment Study and prepare Remediation

Plan, Natural Resource Augment Plan and Community Resource Augmentation Plan.

Keeping in view the presentation made by the PP/ Consultant and examination of

documents submitted by them, the SEAC resolved to recommend to SEIAA for prescribing

the ToR mentioned at ‘Annexure B’, as a case of violation of the EIA notification, for

preparing comprehensive EIA/EMP reports and Assessment of Ecological Damage,

preparation of Remediation Plan and Natural Community Resource Augmentation Plan as a

case of violation, of the EIA notification.

Agenda no. 37. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19626)/ 2019-20

Project Name- EC for Granite Mining Project, Plot No. 107, Area 1.3680 Ha., Production

Capacity- 2,12,100 TPA (ROM), Khasra No. 1473, Add.- Morajhari, Tehsil- Nasirabad,

District- Ajmer, (Raj.) (Proposal No.- 215473).

Project Proponent Name- Shri- Parasmal Dhabariya, Add.- Sadar Bazar, Tantoti, Distt.-

Ajmer, (Raj.), Email- [email protected].

Final minutes of 4.95th meeting held on 27-29 July, 2021

Consultant Name- COGNIZANCE RESEARCH INDIA PRIVATE LTD. Add.- Office GT

– 20, Sec – 117, Noida (U.P.)

The particulars of the project, in brief, as submitted by the PP are as follows:

S.

No

.

Particulars Details/Information

1. Cat./ Item no. (in schedule):

1 (a)-B2

2. Location of the Project

Near village – Morajhari , Tehsil: Nasirabad , District: Ajmer (Rajasthan)

3. Project Details M.L No./ Production Capacity

ML. No. : Plot No.-107 Khasra No. : 1473 Area : 1.3680 HECT.

Production (TPA) : 212100 TPA(ROM)

Details are given in cover page of Proposal obtaining of Environmental Clearance

4. Project Cost Project Cost: Rs 3.00Cr/-(in Rs.) Details are given in cover page of Proposal obtaining of Environmental Clearance

5. Water requirement & Source

Total water requirement is about 5.0 KLD = 1.0 KLD (Drinking & Domestic Uses) + 1.0 KLD (Plantation) + 1.0 KLD (Dust Suppression). 2.0 KLD Water for Drinking, dust suppression and plantation will be collected from nearby villages.

6. Fuel & Energy

No electricity will be required in mining operations as mining will be carried out in day time only. Diesel will be used for transportation vehicles.

7. Application no., Date of Documents Submitted

Category : B2 SEAC FILE NO. : 19626 Date of documents Submitted : 24/06/2021 SEAC Meeting No. : 4.95nd Meeting Agenda Sr. No. : 37 Date of Presentation : 29/07/2021

8. Information about Aravalli certificate

Aravalli Certificate has been issued by Mining Engineer, Ajmer vide letter No. ME/AJ/Comp/Map/Aravali /p-/217 dated 25/05/2021.

9. Date of Air, Water, Noise,

monitoring

Monitoring was conducted by Noida Testing Laboratories. Approved by NABL.

10. Information about 500 mts composite map

500 mts composite map has been issued by Mining Engineer, Ajmer vide letter No. ME/AJ/Comp/Map/Aravali /p-/217 dated 25/05/2021. Area falling within 500 mts 1.3680ha.

11. EMP Activities

Environment Management Plan Expenditures: Capital Cost: Rs. 12.0 lacs Recurring Cost: Rs. 12.0 lacs per annum.

Sr.

No. Particulars Capital Cost

(in Rs. Lac) Recurring Cost

(in Rs. Lac)

1. Pollution Control i) Dust Suppression ii) Road Preparation And

Maintenance

6,00,000 6,00,000

2. Pollution Monitoring i) Air pollution ii) Water pollution

- 15,000/-

3. Green Belt 6,00,000 5,85,000

Total 12,00,000/- 12,00,000/-

12. Greenbelt & Plantation

Expenditure of Green Belt Rs 5,85,000/- Total green belt will be the 33% of the mine area 0.450ha of the area shall be in the part of Govt. Charagah land at village Morajhari in Khasra No.-23. Native specie which are more suitable to the local environment are preferred to be planted such as like Peepal (Ficus Religiosa),

Shisham(Dalbergia sissoo), Apple (Malus Domestica) Mango (Mangifera indica), etc. it is the proposed to invest 1.25 Lac. Rs. Per annum for greenbelt devlopment

Final minutes of 4.95th meeting held on 27-29 July, 2021

Observations of the committee:-

The SEAC considered/examined the project proposal on 29.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has applied for EC for Granite Mining Project, Plot No. 107, Area 1.3680

Ha., Production Capacity- 2,12,100 TPA (ROM), Khasra No. 1473, Add.- Morajhari, Tehsil-

Nasirabad, District- Ajmer, (Raj.) (Proposal No.- 215473). The project is covered under B2

category. The SME, Ajmer vide order dated 28.04.2021 has issued LoI to the PP for mining

of Granite. The mining plan has been approved by the SME, Ajmer vide letter dated

16.06.2021. ME, Ajmer in his certificate dated 25.05.2021 has stated that the mining lease

does not fall in Aravalli hills. DCF, Ajmer and DCF, Tonk in their certificates dated

23.07.2021 and 23.02.2021 have stated that there is no Wildlife Sanctuary/National Park/

Conservation Reserve within 10 km periphery of the mine. Besides, the PP in Form-1 has

also stated that there is no WLS, National Park and Conservation Reserve within 10 Km of

the project site.

The project does not involve approval/ clearance under the Forest (Conservation) Act,

1980 and Wild Life Protection Act, 1972 as no forest land is involved and neither there is any

Wild Life Sanctuary/ National Park within 10 Km from the project site.

Year

Outside the lease area ( part of

Govt. Charagah land at village

Morajhari in Khasra No.-23)

Top Soil Dumps Total

Area (Ha.) No. of

Trees

Area

(Ha.)

No. of

Trees Area (Ha.) No. of Trees

1st Year 0.150 150 -- -- 0.150 150

2nd Year 0.150 150 -- -- 0.150 150

3rd Year 0.150 150 -- -- 0.150 150

Total 0.450 Hect. 450 -- -- 0.450 Hect. 450

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing mining

operations, undertake re-grassing the mining area and any other area which may have been

disturbed due to their mining activities and restore the land to a condition which is fit for growth

of fodder, flora, fauna etc.

13. Budgetary breakup for labour

The information regarding Budgetary breakup for labour has been given in PFR & Power Point Presentation

Sr.

No. Facility provided for Labour Capital Cost in

Rs. Recurring cost in

Rs.

1. Drinking water facility 1,00,000/- 1,00,000/-

2. Health Facility (First aid box, Rest shelter, Medicine & Washroom) & Insurance

1,00,000/- 1,00,000/-

3. Education for Labour children 50,000/- 50,000/-

4. Safety equipment like Ear plug, Dust

mask, hand gloves, Safety Shoes etc. 50,000/- 50,000/-

Total 3,00,000/- 3,00,000/-

14. Present Status

LOI Granted

Final minutes of 4.95th meeting held on 27-29 July, 2021

According to cluster certificate and map dated 25.05.2021 issued by ME, Ajmer, in

terms of Notifications MoEF & CC dated 15.01.2016 and 01.07.2016, there is no cluster

formation.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1, Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri-

Parasmal Dhabariya, for Granite Mining Project, Plot No. 107, Area 1.3680 Ha., Production

Capacity- 2,12,100 TPA (ROM), Khasra No. 1473, Add.- Morajhari, Tehsil- Nasirabad,

District- Ajmer, (Raj.) (Proposal No.- 215473), with the stipulation that the PP shall abide

by the annual production scheduled specified in mining plan and that any deviation there in

will render the PP liable for legal action in accordance with Environment and Mining Laws,

with the specific and general conditions annexed at Annexure ‘A’. Name of Proponent Shri-

Parasmal Dhabariya, Add.- Sadar Bazar, Tantoti, Distt.- Ajmer, (Raj.), Email-

[email protected], Consultant Name:- COGNIZANCE RESEARCH

INDIA PRIVATE LTD. Add.- Office GT – 20, Sec – 117, Noida (U.P.).

Agenda no. 38. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19627)/ 2019-20

Project Name- EC for Granite Mining Project, M.L. No. 02/2021, Plot No.38, Area 1.5968

Ha., Production Capacity-1,59,999 TPA (ROM), Khasra No.- 1419/989, Add.- Nallu, Tehsil-

Kishangarh, District- Ajmer, (Raj.) (Proposal No.- 214716).

Project Proponent Name M/s Stone Tech Granites, (Project in Charge) Shri- Jayram

Buldak S/o Shri- Mohan Ram, Add.- Kh.No. 421/2, Khatoli, Tehsil- Kishangarh, Distt.-

Ajmer, (Raj.), [email protected].

Consultant Name- Cognizance Research India Private Ltd.(Accredited by NABET, Govt. of

India Accredited No. NABET/EIA/1619/IA006, Valid up to Aug 18, 2019)Office GT-20, Sec

177, Noida- 201301 (U.P.)email:- [email protected]

The particulars of the project, in brief, as submitted by the PP are as follows:

S.

No

.

Partic

ulars

Details/Information

1. Cat./

Item

no. (in

schedu

le):

1 (a)-B2

2. Locati

on of

the

Project

Near village – Nallu, Tehsil:- Kishangarh, District- Ajmer, , (Rajasthan)

3. Project

Details

M.L

No./ Produc

tion

Plot No. : 38, M.L.No. 02/2021,

Khasra No. : 1419/989

Area : 1.5968 Ha.

Production (TPA) : 159999TPA (ROM)

Details are given in cover page of Proposal obtaining of Environmental Clearance

(Slides No.: 1)

Final minutes of 4.95th meeting held on 27-29 July, 2021

Capaci

ty

4. Project

Cost

Project Cost: Rs 1.30 Cr.

Details are given in cover page of Proposal obtaining of Environmental Clearance

(Slides No.: 1)

5. Water

requirement

&

Source

Total water requirement is about 4.5 KLD= 2.0 KLD (Drinking & Domestic Uses) + 1.0 KLD

(Plantation) + 1.0 KLD (Dust Suppression) 0.5 KLD (Wire saw Cutting). Water for Drinking, dust suppression and plantation will be collected from nearby villages.

Details are given in Slide no. 30 of Power Point Presentation.

6. Fuel &

Energy

No electricity will be required in mining operations as mining will be carried out in day time

only.

7. Applic

ation

no.,

Date

of

Docu

ments

Submitted

Category : B2

SEAC FILE NO. : 19627

Date of documents Submitted : 23/6/2021

SEAC Meeting No. : 4.95rd Meeting

Agenda Sr. No. : 38

Date of Presentation : 28/07/2021

8. Inform

ation

about

Araval

li

certific

ate

Aravalli Certificate has been issued by Mining Engineer, Ajmer vide letter No. ME/AJ/Comp/Map/Aravalli P-/258 Date - 17/06/2021as Slide No.. 12

9. Date

of Air,

Water,

Noise,

monitoring

Monitoring was conducted by Noida Testing Laboratories., Approved by NABL, Noida as Slide

No.: 33-34

10. Informa

tion

about

500 mts

composi

te map

500 mts composite map has been issued by Mining Engineer, Ajmer vide letter No. ME/AJ/Comp/Map/Aravalli P-/258 Date - 17/06/2021as Slide No..: 13 Area falling within 500 mts 1.5968 Ha.

11. CER

Activit

ies

Environment Management Plan Expenditures: Capital Cost: Rs. 6,50,000/- Recurring Cost: Rs.

6,50,000/- per annum.

SI. No. Measures Exp. Cost in Rs.

(Fixed Yearly)

Exp. Cost in Rs.

( Recurring

Yearly)

1

Pollution Control

i) Dust Suppression & Wet Drilling

3,10,000/- 3,10,000/-

2 Pollution Monitoring i) Air pollution

ii) Water pollution

--- 15,000

3 Green Belt 3,40,000/- 3,25,000/-

Total 6,50,000/- 6,50,000/-

12. Green

belt & Plantat

ion

Expenditure of Green Belt Rs 3,25,000/-

Total green belt will be the 33% of the lease area 0.526 Ha. of the area will be planted in the part of govt. charagah land at village Nallu in Khasra no.- 1015.

Native specie which are more suitable to the local environment are preferred to be planted such

Final minutes of 4.95th meeting held on 27-29 July, 2021

Observations of the committee:-

The SEAC considered/examined the project proposal on 29.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for EC for Granite Mining Project, M.L.No.

02/2021, Plot No.38, Area 1.5968 Ha., Production Capacity- 1,59,999 TPA (ROM), Khasra

No.- 1419/989, Add.- Nallu, Tehsil- Kishangarh, District- Ajmer, (Raj.) (Proposal No.-

214716). The project is covered under B2 category. The SME, Ajmer vide order dated

26.03.2021 has issued LoI to the PP for mining of Granite. The mining plan has been

approved by the SME, Ajmer vide letter dated 02.06.2021. ME, Ajmer in his certificate dated

17.06.2021 has stated that the mining lease does not fall in Aravalli hills. DCF, Ajmer in his

certificate dated 22.07.2021 has stated that there is no Wildlife Sanctuary/National Park/

Conservation Reserve within 10 km periphery of the mine. The project does not involve

as like Aam (Mangifera indica), Imli(Tamarindus indica), Neem (Azadirachta Indica), Shisham

(Dalbergia sisso) etc. it is the proposed to invest 3.25Lac. Rs. Per annum for greenbelt

devlopment

Year

Outside the lease area ( charagah land at

village Nallu in Khasra no.- 1015)

Top Soil

Dumps Total

Area (Ha.) No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

1st

Year 0.175 175 -- -- 0.175 175

2nd

Year 0.175 175 -- -- 0.175 175

3rd

Year 0.176 176 -- -- 0.176 176

Tota

l 0.526 526 -- --

0.526 526

Note:- As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing mining

operations, undertake re-grassing the mining area and any other area which may have been

disturbed due to their mining activities and restore the land to a condition which is fit for

growth of fodder, flora, fauna etc.

13. Budget

ary

breakup for

labour

The information regarding Budgetary breakup for labour has been given in Power Point

Presentation (Slide No.: 17)

Sr.

No.

Facility to be Provided for

Laborers

Exp. Cost in Rs.

(Fixed Yearly)

Exp. Cost in Rs.

( Recurring Yearly)

1. Drinking water facility 50,000/- 50,000/-

2.

Health Facility (First aid box,

Rest shelter, Medicine &

Washroom) & Insurance

50,000/- 50,000/-

3. Education for Labours children 20,000/- 20,000/-

4.

Safety equipment like Ear plug,

Dust mask, hand gloves, Safety

Shoes etc.

10,000/- 10,000/-

Total 1,30,000/- 1,30,000/-

14. Presen

t Status

Proposed Mine site.

Final minutes of 4.95th meeting held on 27-29 July, 2021

approval/ clearance under the Forest (Conservation) Act, 1980 and Wild Life Protection Act,

1972 as no forest land is involved and neither there is any Wild Life Sanctuary/ National Park

within 10 Km from the project site.

According to cluster certificate and map dated 17.06.2021 issued by ME, Ajmer, in

terms of Notifications MoEF & CC dated 15.01.2016 and 01.07.2016, there is no cluster

formation.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-1,

Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to M/s Stone

Tech Granites, (Project in Charge) Shri- Jayram Buldak S/o Shri- Mohan Ram, for Granite

Mining Project, M.L.No. 02/2021, Plot No.38, Area 1.5968 Ha., Production Capacity-

1,59,999 TPA (ROM), Khasra No.- 1419/989, Add.- Nallu, Tehsil- Kishangarh, District-

Ajmer, (Raj.) (Proposal No.- 214716), with the stipulation that the PP shall abide by the

annual production scheduled specified in mining plan and that any deviation there in will

render the PP liable for legal action in accordance with Environment and Mining Laws, with

the specific and general conditions annexed at Annexure ‘A’. Name of Proponent M/s Stone

Tech Granites, (Project in Charge) Shri- Jayram Buldak S/o Shri- Mohan Ram, Add.-

Kh.No. 421/2, Khatoli, Tehsil- Kishangarh, Distt.- Ajmer, (Raj.), Email-

[email protected], Consultant Name:- Cognizance Research India Private

Ltd.(Accredited by NABET, Govt. of India Accredited No. NABET/EIA/1619/IA006, Valid

up to Aug 18, 2019)Office GT-20, Sec 177, Noida- 201301 (U.P.), email:-

[email protected].

Agenda no. 39. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19582)/ 2019-20

Project Name- Environmental Clearance for Juni Aati Masonry Stone Mining Project, Plot

No.- 103, Area- 1.00 ha., Production Capacity- 1,43,650TPA (ROM) Khasra No.- 579/321

Near Vill.- Juni Aati, Tehsil & Distt.- Barmer (Raj).(Proposal No.-214172).

Project Proponent Name- M/s Tan Singh Chouhan, Add.- R/o- Gandhi Nagar, Tehsil &

Distt.- Barmer (Raj.) Email- [email protected].

Consultant Name- M/s. N.S. Enviro-Tech Laboratories & Consultant, Add.- Plot No.-51,

Ganeta House, Shiv Vihar Colony, Near Patrakar Colony Road Mansarover- Jaipur- (Raj.)

Email- [email protected]

The particulars of the project, in brief, as submitted by the PP are as follows:

1 Category /Item No.(In Schedule): 1(a) B2

2 Location of Project “Juni Aati Masonary Stone Plot Area, Plot. No103.-, located

at Near Village – Juni Aati

Tehsil – Barmer, District – Barmer,(Rajasthan)

3 Project Details ML. No. / Production Capacity Plot. No 103.Applied Area–1.00Hect. (Govt waste Land)

Khasra No. 579/321 , Proposed Production Capacity-

143650TPA (ROM)

4 Project Cost: 30.0Lacs

5 Water Requirement & Source: 3.0KLD

Final minutes of 4.95th meeting held on 27-29 July, 2021

6 Fuel & Energy:- 0.5 KLD (HSD)

7 Application No. & Date & Document Submitted:- Proposal No (214172)

8 Information About Aravalli Certificate. Aravalli letter was issued by ME BR vide letter no. ME/ BR

/ environment/Aravli/2021/207 on dated 28-/05/2021

9 Date of Air/Water/Noise/Monitoring Nodia Testing Laboratories 3/06/2021

10 Information About 500 mts Composite Map 500 M Map was issued by ME BR vide letter no. ME/ BR /

EC/DRG/2021/473 on dated 28-/05/2021

11 Environment Management Plan EMP Cost :- Capital Cost is 1.15,000 Lac

Recurring cost is 85,000 Lac per years.

S. No. Particulars Capital Cost in RS. Recurring cost in Rs.

per years

1 Pollution control ( water

sprinkling for dust

suppression )

-- 20,000

2 Pollution monitoring (Air.

Water ,Noise, Soil) -- 15,000

3 Greenbelt Sr.

No

Particulars Amount

1 Plant 330 20,000

2 Tree guard 330 20,000

3 Water Tanker 10,000

4 Maintains & security 10,000

Total 60,000

25,000

4 Occupation health 20,000/- 10,000

5 Miscellaneous (Fencing, etc.) 35,000/- 15,000

Total 1,15,000/- 85,000/-

12 Green Belt/ Plantation 0.60 Lac

Places of Plantation:- About 330 saplings will be planted in an area of 0.33 ha (33% of applied area) upto the end

of 5 years, About 330 Sapling will be planted out side the lease boundary at own khatedari land Khasra No

586/95.

Year Along the lease

boundary

On Backfilled

area

Outside the lease

area

Top Soil Dumps Total

Area

(Ha.)

No. of Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Trees

2021-22 -- -- -- -- 0.066 66 -- -- 0.066 66

2022-23 -- -- -- -- 0.066 66

-- -- 0.066 66

2023-24 -- -- -- -- 0.066 66

-- -- 0.066 66

2024-25 -- -- -- -- 0.066 66 -- -- 0.066 66

2025-26 -- -- -- --

0.066 66

-- -- 0.066 66

Total -- -- -- --

0.330 330

-- -- 0.330 330

As per Office Memorandum 16.01.2020: Commitment by PP The mining lease holders shall after ceasing mining operations, undertake re-grassing the mining area and any other area which may have been disturbed due to their mining activates and restore the land to a condition which is for growth of fodder, Flora, Fauna etc.”

13 Budgetary Breakup For Labor Labor Welfare Capital Cost is 0.60 Lac, and

Recurring Cost is 0.30 lac.

S. No. Facility Provided for Laborers Capital Cost in RS. Recurring Cost In

RS. Per Year

1. Drinking water provided by Tanker 20,000/- 10,000/-

2. First Aid Box 5,000/- 2,000/-

3. Rest Shelter 8,000/- 4,000/-

4. Washroom Facilities for laborers 12,000/- 6,000/-

5 Safety Shoes, hand gloves, Dust mask, Ear plugs,

Helmet 10,000/- 8,000/-

6 Insurance 5,000/- --

Final minutes of 4.95th meeting held on 27-29 July, 2021

Total 60,000/- 30,000/-

Observations of the committee:-

The SEAC considered/examined the project proposal on 29.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for Environmental Clearance for Juni Aati Masonry

Stone Mining Project, Plot No.- 103, Area- 1.00 ha., Production Capacity- 1,43,650TPA

(ROM) Khasra No.- 579/321 Near Vill.- Juni Aati, Tehsil & Distt.- Barmer (Raj).(Proposal

No.-214172). The project is covered under B2 category. The SME, Jodhpur vide order dated

07.01.2021 has issued LoI to the PP for mining of Masonry Stone. The mining plan has been

approved by the SME, Jodhpur vide letter dated 18.05.2021. ME, Barmer in his certificate

dated 28.05.2021 has stated that the mining lease does not fall in Aravalli hills. DCF, Barmer

in its certificate dated 21.09.2020 has stated that there is no Wildlife Sanctuary/National

Park/ Conservation Reserve within 10 km periphery of the mine. The project does not involve

approval/ clearance under the Forest (Conservation) Act, 1980 and Wild Life Protection Act,

1972 as no forest land is involved and neither there is any Wild Life Sanctuary/ National Park

within 10 Km from the project site.

The SEAC considered the certificate dated 28.05.2021 issued by ME, Barmer. In the

certificate, it is stated that as per the MoEF & CC notification, dated 01.07.2016 there is no

other mining lease within the periphery of 500 meter and therefore, there is no cluster

formation

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1,Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to M/s Tan

Singh Chouhan, for Juni Aati Masonry Stone Mining Project, Plot No.- 103, Area- 1.00 ha.,

Production Capacity- 1,43,650 TPA (ROM), Khasra No.- 579/321 Near Vill.- Juni Aati,

Tehsil & Distt.- Barmer (Raj).(Proposal No.-214172), with the stipulation that the PP shall

abide by the annual production scheduled specified in mining plan and that any deviation

there in will render the PP liable for legal action in accordance with Environment and Mining

Laws, with the specific and general conditions annexed at Annexure ‘A’. Name of

Proponent M/s Tan Singh Chouhan, Add.- R/o- Gandhi Nagar,Tehsil & Distt.- Barmer

(Raj.)[email protected], Consultant Name:- M/s. N.S. Enviro-Tech

Laboratories & Consultant, Add.- Plot No.-51, Ganeta House, Shiv Vihar Colony, Near

Patrakar Colony Road Mansarovar- Jaipur- (Raj.)

Email- [email protected].

Agenda no. 40. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19583)/ 2019-20

Project Name- Environmental Clearance for Sodhon ki Dhani Masonry Stone Mining

Project Ref. No.- 20201000022559, Area- 2.00 ha., Production Capacity- 2,65,625 TPA

Final minutes of 4.95th meeting held on 27-29 July, 2021

(ROM), Khasra No.- 947/95, Near Vill.- Sodhon Ki Dhani, Tehsil & Distt.- Barmer (Raj.),

(Proposal No.-214348).

Project Proponent Name: M/s Tan Singh Chouhan, Add.- R/o- Gandhi Nagar, Tehsil &

Distt.- Barmer (Raj.), [email protected].

Consultant Name- M/s. N.S. Enviro-Tech Laboratories & Consultant, Add.- Plot No.-51,

Ganeta House, Shiv Vihar Colony, Near Patrakar Colony Road Mansarover- Jaipur- (Raj.)

Email- [email protected]

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category /Item No.(In Schedule): 1(a) B2

2 Location of Project “Sodhon Ki DhaniMasonary Stone Mine, Ref No

20201000022559.,Near Village – Sodhon Ki

Dhani Tehsil – Barmer, District – Barmer,

(Rajasthan)

3 Project Details ML. No. / Production Capacity Ref No 20201000022559.Applied Area–2.00Hect.

(Khatedari Land) Khasra No. 947/95 , Proposed

Production Capacity- 265625 TPA (ROM)

4 Project Cost: 50.0Lacs

5 Water Requirement & Source: 3.0KLD

6 Fuel & Energy:- 0.5 KLD (HSD)

7 Application No. & Date & Document

Submitted:-

Proposal No (214348)

8 Information About Aravalli Certificate. Aravalli letter was issued by ME BR vide letter no.

ME/ BR / environment/Aravli/2021/203 on dated 28-

/05/2021

9 Date of Air/Water/Noise/Monitoring Nodia Testing Laboratories 3/06/2021

10 Information About 500 mts Composite Map 500 M Map was issued byME BR/vide letter no. ME/

BR / EC/DRG/2021/475on dated 28-/05/2021

11 Environment Management Plan EMP Cost :- Capital Cost is 1,25,000 Lac

Recurring cost is 90,000 Lac per years.

S. No. Particulars Capital Cost in RS. Recurring cost in

Rs. per years 1 Pollution control (

water sprinkling for

dust suppression )

-- 20,000

2 Pollution monitoring

(Air. Water ,Noise,

Soil)

-- 15,000

3 Greenbelt Sr.

No

Particulars Amount

1 Plant 660 30,000

2 Tree guard 660 20,000

3 Water Tanker 5,000

4 Maintains &

security

10,000

Total 65,000

25,000

4 Occupation health 25,000 15,000

5 Miscellaneous

(Fencing, etc.) 35,000 15,000

Total 1.25,000 90,000

12 Green Belt/ Plantation 0.65 Lac Places of Plantation:- About 660 saplings will be planted in an area of 0.66 ha (33% of applied area)

Final minutes of 4.95th meeting held on 27-29 July, 2021

upto the end of 5years,About 660 sapling will be planted out side the lease boundary at own khatedari

land Khasra No 586/95.

Year Along the lease

boundary

On Backfilled

area

Outside the

lease area

Top Soil Dumps Total

Area

(Ha.)

No. of Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees Trees

2021-22 -- -- -- -- 0.132 132 -- -- 0.132 132

2022-23 -- -- -- -- 0.132 132 -- -- 0.132 132

2023-24 -- -- -- --

0.132 132 -- -- 0.132 132

2024-25 -- -- -- -- 0.132 132 -- -- 0.132 132

2025-26 -- -- -- -- 0.132 132 -- -- 0.132 132

Total -- -- -- --

0.660 660

-- -- 0.660 660

As per Office Memorandum 16.01.2020: Commitment by PP The mining lease holders shall after ceasing mining operations, undertake re-grassing the mining area and any other area which may have been disturbed due to their mining activates and restore the land to a condition which is for growth of fodder, Flora, Fauna etc.”

13 Budgetary Breakup For Labor Labor Welfare Capital Cost is 0.60 Lac,

and Recurring Cost is 0.30 lac.

S. No. Facility Provided for Laborers Capital Cost in

RS.

Recurring

Cost In RS.

Per Year

1. Drinking water provided by Tanker 20,000/- 10,000/-

2. First Aid Box 5,000/- 2,000/-

3. Rest Shelter 8,000/- 4,000/-

4. Washroom Facilities for laborers 12,000/- 6,000/-

5 Safety Shoes, hand gloves, Dust

mask, Ear plugs, Helmet 10,000/- 8,000/-

6 Insurance 5,000/- --

Total 60,000/- 30,000/-

Observations of the committee:-

The SEAC considered/examined the project proposal on 29.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has applied for Environmental Clearance for Sodhon ki Dhani Masonry Stone

Mining Project Ref. No.- 20201000022559, Area- 2.00 ha., Production Capacity- 2,65,625

TPA (ROM), Khasra No.- 947/95, Near Vill.- Sodhon Ki Dhani, Tehsil & Distt.- Barmer

(Raj.), (Proposal No.-214348). The project is covered under B2 category. The SME, Jodhpur

vide order dated 24.12.2020 has issued LoI to the PP for mining of Masonry Stone. The

mining plan has been approved by the SME, Jodhpur vide letter dated 12.05.2021. ME,

Barmer in his certificate dated 28.05.2021 has stated that the mining lease does not fall in

Aravalli hills. DCF, Barmer in its certificate dated 16.10.2020 has stated that there is no

Final minutes of 4.95th meeting held on 27-29 July, 2021

Wildlife Sanctuary/National Park/ Conservation Reserve within 10 km periphery of the mine

and the nearest forest land is at a distance of 0.25 Km from the applied lease area. The project

does not involve approval/ clearance under the Forest (Conservation) Act, 1980 and Wild

Life Protection Act, 1972 as no forest land is involved and neither there is any Wild Life

Sanctuary/ National Park within 10 Km from the project site.

As per cluster certificate issued by ME, Barmer on 28.05.2021, the total area of all the

mining leases in the cluster having area of 4.90 ha.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-1,

Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation resolved to recommend to SEIAA for grant of EC to M/s Tan Singh

Chouhan, for Sodhon ki Dhani Masonry Stone Mining Project, Ref. No.- 20201000022559,

Area- 2.00 ha., Production Capacity- 2,65,625 TPA (ROM), Khasra No.- 947/95, Near Vill.-

Sodhon Ki Dhani, Tehsil & Distt.- Barmer (Raj.) (Proposal No.-214348), with the stipulation

that the PP shall abide by the annual production scheduled specified in mining plan and that

any deviation there in will render the PP liable for legal action in accordance with

Environment and Mining Laws, with the specific and general conditions annexed at

Annexure ‘A’. Name of Proponent M/s Tan Singh Chouhan, Add.- R/o- Gandhi

Nagar,Tehsil & Distt.- Barmer (Raj.) Email- [email protected],

Consultant Name:- M/s. N.S. Enviro-Tech Laboratories & Consultant, Add.- Plot No.-51,

Ganeta House, Shiv Vihar Colony, Near Patrakar Colony Road Mansarover- Jaipur- (Raj.)

[email protected].

Agenda no. 41. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19586)/ 2019-20

Project Name- Environmental Clearance for Bapcha Masonry Stone Mine, Ref. No.-

20191000014037, area- 1.1612 ha., Production Capacity- 2,00,000 TPA (ROM), Khasra No.-

444 & 445, Near Vill.- Bapcha, Tehsil- Chhabra, Distt.- Baran (Raj) (Proposal No.-207963).

Project Proponent Name- Smt. Anita Bagdi W/o Sh. Satyendra Maheshwari, Add.- R/o- A-

9-10, Shastri Nagar, Ward No.-02, Hill View Colony, Chhabra, Distt.- Baran (Raj.) Email-

[email protected].

Consultant Name- M/s. N.S. Enviro-Tech Laboratories & Consultant, Add.- Plot No.-51,

Ganeta House, Shiv Vihar Colony, Near Patrakar Colony Road Mansarover- Jaipur- (Raj.)

Email- [email protected]

Observations and Resolution of the committee:-

The SEAC considered/examined the project proposal on 29.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for Environmental Clearance for Bapcha Masonry

Stone Mine, Ref. No.- 20191000014037, area- 1.1612 ha., Production Capacity- 2,00,000

Final minutes of 4.95th meeting held on 27-29 July, 2021

TPA (ROM), Khasra No.- 444 & 445, Near Vill.- Bapcha, Tehsil- Chhabra, Distt.- Baran

(Raj) (Proposal No.-207963). The project is covered under B2 category. The SME, Kota vide

order dated 23.10.2020 has issued LoI to the PP for mining of Masonry Stone .The mining

plan has been approved by the SME, Kota vide letter dated 25.03.2021. AME, Baran in his

certificate dated 05.11.2020 has stated that the mining lease does not fall in Aravalli hills.

According to cluster certificate and map dated 05.11.2020 issued by AME, Baran, in

terms of Notifications of the MOEF & CC dated 15.01.2016 and 01.07.2016, there is no

cluster formation.

The PP has not submitted certificate from the concerned DCF regarding existence or

otherwise of National Park or Wildlife Sanctuary from the applied lease area. The SEAC,

therefore, decided to ask the PP to submit the same within a period of 45 days failing which

the project shall be recommended to SEIAA for closure and delistment.

Agenda no. 42. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19587)/ 2019-20

Project Name- Environmental Clearance for Ganerav Granite Mining Project, Ref. No.-

20191000010415,area-1.1519 ha,Production Capacity - 65850 TPA (ROM), Khasra No.-

4296/196, Near Vill.- Ganerav, Tehsil- Desuri, Distt.- Pali (Raj).(Proposal No.-209034)

Project Proponent Name- Shri Chandra Prakash Salvi, Add.- R/o- Salviyon Ka Mohlla,

Biyanan Post Tikad, Tehsil- Devgarh, Distt.- Pali (Raj.) Email-

[email protected]

Consultant Name- M/s. N.S. Enviro-Tech Laboratories & Consultant, Add.- Plot No.-51,

Ganeta House, Shiv Vihar Colony, Near Patrakar Colony Road Mansarover- Jaipur- (Raj.)

Email- [email protected].

Observations and Resolution of the committee:-

The PP vide letter dated 29.07.2021 has submitted an application for deferment of the

case. The SEAC agreed to the request of the PP and deferred the matter. The project shall be

taken up again on receipt of his request for consideration of the project by the PP, in the

subsequent proposed meeting.

Agenda no. 43. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19588)/ 2019-20

Project Name- Environmental Clearance for Juni Aati Masonry Stone Mining Project, Plot

No.- 98, Area- 1.50 ha., Production Capacity- 2,43,750 TPA (ROM), Khasra No.- 579/321

Near Vill.- Juni Aati, Tehsil & Distt.- Barmer (Raj).(Proposal No.-213961).

Project Proponent Name- M/s Tan Singh Chouhan, Add.- R/o- Gandhi Nagar, Tehsil &

Distt.- Barmer (Raj.) Email- [email protected]

Consultant Name- M/s. N.S. Enviro-Tech Laboratories & Consultant, Add.- Plot No.-51,

Ganeta House, Shiv Vihar Colony, Near Patrakar Colony Road Mansarover- Jaipur- (Raj.)

Email- [email protected]

The particulars of the project, in brief, as submitted by the PP are as follows:

Final minutes of 4.95th meeting held on 27-29 July, 2021

1. Category /Item No.(In Schedule): 1(a) B2

2 Location of Project -:- “Juni Aati Masonary Stone Plot Area, Plot. No98.-,

located at Near Village – Juni Aati

Tehsil – Barmer, District – Barmer,

(Rajasthan)

3 Project Details ML. No. / Production Capacity Plot. No98. Applied Area–1.50 Hect. (Govt Landi Land)

Khasra No. 579/321 , Proposed Production Capacity-

243750TPA (ROM)

4 Project Cost: 40.0 Lacs

5 Water Requirement & Source: 3.0KLD

6 Fuel & Energy:- 0.5 KLD (HSD)

7 Application No. & Date & Document Submitted:- Proposal No (213961)

8 Information About Aravalli Certificate. Aravalli letter was issued by ME BR vide letter no. ME/ BR

/ environment/Aravli/2021/205 on dated 28-/05/2021

9 Date of Air/Water/Noise/Monitoring Nodia Testing Laboratories 3/06/2021

10 Information About 500 mts Composite Map 500 M Map was issued by ME BR vide letter no. ME/ BR /

EC/DRG/2021/474 on dated 28-/05/2021

11 Environment Management Plan EMP Cost :- Capital Cost is 1.20,000 Lac

Recurring cost is 80,000 Lac per years.

S. No. Particulars Capital Cost in RS. Recurring cost in Rs.

per years

1 Pollution control ( water

sprinkling for dust

suppression )

-- 20,000

2 Pollution monitoring

(Air. Water ,Noise, Soil) -- 15,000

3 Greenbelt Sr.

No

Particulars Amount

1 Plant 490 20,000

2 Tree guard 490 20,000

3 Water Tanker 10,000

4 Maintains &

security

10,000

Total 60,000

20,000

4 Occupation health 25,000/- 10,000

5 Miscellaneous (Fencing,

etc.) 35,000/- 15,000

Total 1,20,000/- 80,000/-

12 Green Belt/ Plantation 0.60 Lac

Places of Plantation:- About 490 saplings will be planted in an area of 0.49 ha (33% of applied area) upto the end

of 5years, About 490 Sapling will be planted out side the lease boundary at own khatedari land Khasra No 586/95.

Year Along the lease

boundary

On Backfilled area Outside the lease

area

Top Soil Dumps Total

Area

(Ha.)

No. of Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area (Ha.) No. of

Trees

Trees

2021-22 -- -- -- --

0.098 98 -- -- 0.098 98

2022-23 -- -- -- --

0.098 98 -- -- 0.098 98

2023-24 -- -- -- --

0.098 98 -- -- 0.098 98

2024-25 -- -- -- -- 0.098 98 -- -- 0.098 98

2025-26 -- -- -- --

0.098 98 -- -- 0.098 98

Total -- -- -- --

0.490 490

-- -- 0.490 490

As per Office Memorandum 16.01.2020: Commitment by PP The mining lease holders shall after ceasing mining operations, undertake re-grassing the mining area and any other area which may have been disturbed due to their mining activates and restore the land to a condition which is for growth of fodder, Flora, Fauna etc.”

Final minutes of 4.95th meeting held on 27-29 July, 2021

13 Budgetary Breakup For Labor Labor Welfare Capital Cost is 0.50 Lac, and

Recurring Cost is 0.20 lac.

S. No. Facility Provided for Laborers Capital Cost in RS. Recurring Cost In

RS. Per Year

1. Drinking water provided by Tanker 15,000/- 8,000/-

2. First Aid Box 5,000/- 2,000/-

3. Rest Shelter 8,000/- 3,000/-

4. Washroom Facilities for laborers 9,000/- 4,000/-

5 Safety Shoes, hand gloves, Dust mask, Ear plugs,

Helmet 8,000/- 3,000/-

6 Insurance 5,000/- --

Total 50,000/- 20,000/-

Observations of the committee:-

The SEAC considered/examined the project proposal on 29.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for Environmental Clearance for Juni Aati Masonry

Stone Mining Project, Plot No.- 98, Area- 1.50 ha., Production Capacity- 2,43,750 TPA

(ROM), Khasra No.- 579/321 Near Vill.- Juni Aati, Tehsil & Distt.- Barmer (Raj) (Proposal

No.-213961). The project is covered under B2 category. The SME, Jodhpur vide order dated

07.01.2021 has issued LoI to the PP for mining of Masonry Stone. The mining plan has been

approved by the SME, Jodhpur vide letter dated 18.05.2021. ME, Barmer in his certificate

dated 28.05.2021 has stated that the mining lease does not fall in Aravalli hills. DCF, Barmer

in its certificate dated 21.09.2020 has stated that there is no Wildlife Sanctuary/National

Park/ Conservation Reserve within 10 km periphery of the mine and the forest land is at a

distance of 5.0 Km from the applied lease area.

The project does not involve approval/ clearance under the Forest (Conservation) Act,

1980 and Wild Life Protection Act, 1972 as no forest land is involved and neither there is any

Wild Life Sanctuary/ National Park within 10 Km from the project site.

The SEAC considered the certificate dated 28.05.2021 issued by ME, Barmer. In the

certificate, it is stated that as per the MoEF & CC notification, dated 01.07.2016 there is no

other mining lease within the periphery of 500 meter and therefore, there is no cluster

formation

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1,Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to M/s Tan

Singh Chouhan, for Juni Aati Masonry Stone Mining Project, Plot No.- 98, Area- 1.50 ha.,

Production Capacity- 2,43,750 TPA (ROM), Khasra No.- 579/321, Near Vill.- Juni Aati,

Tehsil & Distt.- Barmer (Raj).(Proposal No.-213961), with the stipulation that the PP shall

abide by the annual production scheduled specified in mining plan and that any deviation

there in will render the PP liable for legal action in accordance with Environment and Mining

Final minutes of 4.95th meeting held on 27-29 July, 2021

Laws, with the specific and general conditions annexed at Annexure ‘A’. Name of

Proponent M/s Tan Singh Chouhan, Add.- R/o- Gandhi Nagar, Tehsil & Distt.- Barmer

(Raj.) [email protected], Consultant Name:-. M/s. N.S. Enviro-Tech

Laboratories & Consultant, Add.- Plot No.-51, Ganeta House, Shiv Vihar Colony, Near

Patrakar Colony Road Mansarover- Jaipur- (Raj.)

Email- [email protected].

Agenda no. 44. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19601)/ 2019-20

Project Name- EC for Ghatiyali Granite Mining Project, Ref. No. 20201000026666, Area

1.0198 Ha., Production Capacity- 1,01,002, TPA (RoM), Khasra No.1072/854, Add.-

Ghatiyali, Tehsil- Phagi, District- Jaipur, (Raj.) (Proposal No.- 209139).

Project Proponent Name Shri- Prakash Ranwa S/o Shri- Rameshwar Lal, Add.- Ranwa

House, Choudhary Charan Singh Nagar, Navalgarh Road, Ward No. 41, Distt- Sikar, (Raj.)

(Co-Applicant), Shri- Rameshwar Lal Choudhary S/o Shri- Tulsi Ram Choudhary, Add.-

Sikar Marg, Kadva Complex Kuchaman City, Nagaur, Distt.- Nagaur, (Raj.) Email-

[email protected]

Consultant Name- M/s. N.S. Envro- Tech Laboratories & Consultant, , Add- Plot No. 51,

Ganeta House, Shiv Vihar Colony, Near Patrakar Colony Road, Mansarovar, Jaipur (Raj.).

Email:[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1 Category /Item No.(In Schedule): 1(a) B2

2 Location of Project Ghatiyali Granite Mining Project, Ref .No-

20201000026666, of Mineral Granite, N/v-

Ghatiyali, Tehsil- Phagi District- Jaipur,

Rajasthan 3 Project Details ML. No. / Production

Capacity Khasra No.1072/854 Applied Area- 1.0198

Ha. Production Capacity- 101002 TPA

(RoM) 4 Project Cost: 90.0 Lacs

5 Water Requirement & Source: 4.5 KLD

6 Fuel & Energy:- 0.5 KLD (HSD)

7 Application No. & Date & Document

Submitted:-

Proposal No: SIA/RJ/MIN/209139/2021,

8 Information About Aravalli Certificate. Aravalli letter was issued by ME Jaipur vide

letter no. ME

Jaipur/Environment/Cluster/2020-21/1101 on

dated 07/04/2021

9 Date of Air/Water/Noise/Monitoring 03/06/2021

10 Information About 500 mts Composite Map Aravalli letter was issued by ME Jaipur vide

letter no. ME Jaipur/Environment /Cluster

/2020-21/1101 on dated 07/04/2021

11 Environment Management Plan EMP Cost :- Capital Cost is 2,90,000 Lac

Recurring cost is 2,40,000 Lac per years.

S. No. Particulars Proposed Capital cost in Rs/

Annum

1 Pollution control ( water 60,000

Final minutes of 4.95th meeting held on 27-29 July, 2021

sprinkling for dust

suppression )

2 Pollution monitoring (Air.

Water ,Noise, Soil) 50,000

3 Greenbelt

Sr.

No

Particulars Amount

1 Plant330 30,000

2 Tree

guard330

30,000

3 Water

Tanker

25,000

4 Maintains &

security

25,000

Total 1,10,000

65,000

4 Occupation health 80,000/- 35,000 5 Miscellaneous (Fencing, etc.) 90,000/- 30,000 Total 2,90,000/- 2,40,000

12 Green Belt/ Plantation 1.10Lac

Places of Plantation:- About 330saplings will be planted in an area of 0.33 ha (33% of applied area)

upto the end of 5years, About 330 sapling will be planted along the lease boundary own khatedari

land.

Year Along the lease

boundary

On

Backfilled

area

Outside the

lease area

Top Soil

Dumps

Total

Area

(Ha.)

No. of Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees Trees

2021-22 0.066 66 -- -- -- -- -- -- 0.066 66

2022-23 0.066 66 -- --

-- -- -- -- 0.066 66

2023-24 0.066 66 -- --

-- -- -- -- 0.066 66

2024-25 0.066 66 -- -- -- -- -- -- 0.066 66

2025-26 0.066 66 -- -- -- -- -- -- 0.066 66

Total 0.330 330 -- --

-- -- -- -- 0.330 330

As per Office Memorandum 16.01.2020: Commitment by PP The mining lease holders shall after ceasing mining operations, undertake re-grassing the mining area and any other area which may have been disturbed due to their mining activates and restore the land to a condition which is for growth of fodder, Flora, Fauna etc.”

13 Budgetary Breakup For Labor Labor Capital Cost in RS. 0.90 Lac &

Recurring Cost In RS. Per Year 0.60 Lac.

S. No. Facility Provided for Laborers Capital Cost in RS. Recurring Cost In RS.

Per Year

1. Drinking water provided by Tanker 30,000/- 30,000/-

2. First Aid Box 5,000/- 4,000/-

3. Rest Shelter 10,000/- 6000/-

4. Washroom Facilities for laborers 15,000/- 5,000/-

5 Safety Shoes, hand gloves, Dust mask, Ear plugs,

Helmet 20,000/- 15,000/-

6 Insurance 10,000/- --

Final minutes of 4.95th meeting held on 27-29 July, 2021

Total 90,000/- 60,000/-

Observations of the committee:-

The SEAC considered/examined the project proposal on 29.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for EC for Ghatiyali Granite Mining Project, Ref.

No. 20201000026666, Area 1.0198 Ha., Production Capacity- 1,01,002, TPA (RoM), Khasra

No.1072/854, Add.- Ghatiyali, Tehsil- Phagi, District- Jaipur, (Raj.) (Proposal No.-

209139). The project is covered under B2 category. The SME, Jaipur vide order dated

09.03.2021 has issued LoI to the PP for mining of Granite. The mining plan has been

approved by the SME, Jaipur vide letter dated 08.04.2021. ME, Jaipur in his certificate dated

29.04.2021 has stated that the mining lease does not fall in Aravalli hills. DCF, Jaipur in its

certificate dated 03.03.2021 has stated that there is no Wildlife Sanctuary/National Park/

Conservation Reserve within 10 km periphery of the mine. The project does not involve

approval/ clearance under the Forest (Conservation) Act, 1980 and Wild Life Protection Act,

1972 as no forest land is involved and neither there is any Wild Life Sanctuary/ National Park

within 10 Km from the project site.

The SEAC considered the certificate dated 29.04.2021 issued by ME, Jaipur. In the

certificate, it is stated that as per the MoEF & CC notification, dated 01.07.2016 there is no

other mining lease within the periphery of 500 meter and therefore, there is no cluster

formation

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1,Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri- Prakash

Ranwa S/o Shri- Rameshwar Lal, (Co-Applicant) Shri- Rameshwar Lal Choudhary S/o

Shri- Tulsi Ram Choudhary for Ghatiyali Granite Mining Project, Ref. No.

20201000026666, Area 1.0198 Ha., Production Capacity - 1,01,002 TPA (RoM), Khasra No.

1072/854, Add.- Ghatiyali, Tehsil- Phagi, District- Jaipur, (Raj.) (Proposal No.- 209139)

with the stipulation that the PP shall abide by the annual production scheduled specified in

mining plan and that any deviation there in will render the PP liable for legal action in

accordance with Environment and Mining Laws, with the specific and general conditions

annexed at Annexure ‘A’. Name of Proponent Shri- Prakash Ranwa S/o Shri- Rameshwar

Lal, Add.- Ranwa House, Choudhary Charan Singh Nagar, Navalgarh Road, Ward No. 41,

Distt- Sikar, (Raj.) (Co-Applicant), Shri- Rameshwar Lal Choudhary S/o Shri- Tulsi Ram

Choudhary, Add.- Sikar Marg, Kadva Complex Kuchaman City, Nagaur, Distt.- Nagaur,

(Raj.) Email- [email protected], Consultant Name:- M/s. N.S. Envro- Tech

Laboratories & Consultant, , Add- Plot No. 51, Ganeta House, Shiv Vihar Colony, Near

Patrakar Colony Road, Mansarovar, Jaipur (Raj.).

Email:- [email protected].

Agenda no. 45. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19617)/ 2019-20

Final minutes of 4.95th meeting held on 27-29 July, 2021

Project Name- Environmental Clearance for Bambuliya Ghata Masonry Stone Mine, Ref.

No.- 20191000014359, M.L. No.- 04/2019, Area- 1.0 ha., Production Capacity- 1,27,275

TPA (ROM), Khasra No.- 131 and 306/293, Near Vill.- Bambuliya Ghata, Tehsil- Pipalda

Distt.- Kota (Raj.) (Proposal No.-209141).

Project Proponent Name: Shri Bijendra Verma , Add.- R/o- Vill.- Jhirwali Ka Bas, Post-

Karoth, Tehsil- Rajgarh, Distt.- Alwar (Raj.), [email protected].

Consultant Name- M/s. N.S. Enviro-Tech Laboratories & Consultant, Add.- Plot No.-51,

Ganeta House, Shiv Vihar Colony, Near Patrakar Colony Road Mansarover- Jaipur- (Raj.)

[email protected].

Observations and Resolution of the committee:-

The SEAC considered/examined the project proposal on 29.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for EC for Bambuliya Ghata Masonry Stone Mine,

Ref. No.- 20191000014359, M.L. No.- 04/2019, Area- 1.0 ha., Production Capacity-

1,27,275 TPA (ROM), Khasra No.- 131 and 306/293, Near Vill.- Bambuliya Ghata, Tehsil-

Pipalda Distt.- Kota (Raj.) (Proposal No.-209141). The project is covered under B2 category.

The SME, Kota vide order dated 15.02.2021 has issued LoI to the PP for mining of Masonry

Stone .The mining plan has been approved by the SME, Kota vide letter dated 09.04.2021.

ME, Kota in his certificate dated 05.03.2021 has stated that the mining lease does not fall in

Aravalli hills.

The SEAC considered the certificate dated 05.03.2021 issued by ME, Kota In the

certificate, it is stated that as per the MoEF & CC notification, dated 01.07.2016 there is no

other mining lease within the periphery of 500 meter and therefore, there is no cluster

formation

DCF, Kota in his certificate dated 05.01.2021 has stated that the applied lease area is

non forest land and nearest forest land is at a distance of 1.40 Km from the applied lease area.

The certificate, however, does not speak about existence or otherwise of National Park or

Wildlife Sanctuary from the applied lease area. The SEAC, therefore, decided to ask the PP

to submit certificate from concerned DCF regarding existence or otherwise of National Park

or Wildlife Sanctuary from the applied lease area. within a period of 45 days failing which

the project shall be recommended to SEIAA for closure and delistment.

Agenda no. 46. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2( 19620)/ 2019-20

Project Name- EC for Proposed Project of Masonry Stone Mining project, Plot. No.

176/1996, Area 1.00 Ha., Production Capacity- 62,475 TPA (ROM), Khasra No. 336, Add.-

Bhopas Dungri, Tehsil- Chomu, District- Jaipur, (Raj.) (Proposal No.- 215830).

Project Proponent Name- Shri- Mahendra Kumar Saini S/o Shri- Rajendra Kumar Saini,

Add.- K-25, Bhawani Nagar, Murlipura, Jaipur, Distt.- Jaipur, (Raj.), Email-

[email protected].

Final minutes of 4.95th meeting held on 27-29 July, 2021

Consultant Name- M/s. N.S. Envro- Tech Laboratories & Consultant, , Add- Plot No. 51,

Ganeta House, Shiv Vihar Colony, Near Patrakar Colony Road, Mansarovar, Jaipur (Raj.).

Email:[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category /Item No.(In Schedule): 1(a) B2

2 Location of Project “Bhopas Dungri Masonry Stone Mining

Project”, M.L No.- 176/96, Area- 1.00 Ha.,

Khasra No-336 Near Village- Bhopas

Dungri, Tehsil – Chomu, District – Jaipur

(Rajasthan) of Mahendra Kumar Saini S/o

Shree Rajendra Kumar Saini.

3 Project Details ML. No. / Production Capacity Applied Area- 1.00 Ha. Khasra No – 336,

Proposed Production Capacity – 62,475 TPA

(ROM)

4 Project Cost: 50.0 Lacs

5 Water Requirement & Source: 4.50 KLD

6 Fuel &Energy:- 0.5 KLD (HSD)

7 Application No. & Date & Document Submitted:- SIE/RJ/MIN/215830/2021 on dated 19-06-

2021

8 Information About Aravalli Certificate. Aravalli letter was issued by ME Jaipur vide

letter no. ME/Jai/ Minor/CC-4/Chomu/M.L

176/1996/399 on dated 30.03.2021

9 Date of Air/Water/Noise/Monitoring Nodia Testing Laboratories 25/05/2021 to

29.05.2021

10 Information About 500 mts Composite Map 500 Mtr Map was issued by ME Jaipur vide

letter no. ME/JPR/DWG/2021/457 on dated

30.03.2021

1 Environment Management Plan EMP Cost – Capital Cost 2.0 Lac &

Recurring Cost is 2.18 Lac/Annum

S. No. Particulars Capital Cost in

Lakh Recurring Cost in Lakh

1 Pollution control ( water sprinkling for dust

suppression ) 0.80 0.40

2 Pollution monitoring (Air. Water ,Noise, Soil) -- 0.70

3 Greenbelt 0.40 0.53

4 Occupation health 0.40 0.25

5 Miscellaneous (Fencing with maintenance

etc.) 0.40 0.30

Total 2.0 Lakh 2.18 lakh/Annum

13 Green Belt/ Plantation Capital Cost- 0.40 Lakh

Recurring Cost 0.53 Lac/Annum

Places of Plantation:-

About 330 saplings will be planted in an area of 0.33 ha (33% of applied area) upto the end of 5 years, About 330

sapling will be planted along the lease boundary at safety barrier zone & out side lease area at Grampanchyat

Hathnoda Khasra No 2384/2338

Year

Along the mine

boundary

On Backfilled

area

Outside the

mine area Top Soil Dumps Total

Area

(Ha.)

No. of Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees Trees

Existing -- -- -- -- - -- -- -- -- --

2021-2022 0.046 46 -- -- 0.02 20 -- -- 0.066 66

2022-2023 0. 046 46 ---- -- 0.02 20 - - 0.066 66

2023-2024 0.046 46 -- -- 0.02 20 - - 0.066 66

2024-2025 0.046 46 -- -- 0.02 20 -- -- 0.066 66

Final minutes of 4.95th meeting held on 27-29 July, 2021

2025-2026 0.046 46 -- -- 0.02 20 -- - 0.066 66

TOTAL 0.23 230 -- -- 0.10 100 -- -- 0.33 330

As per Office Memorandum 16.01.2020: Commitment by PP The mining lease holders shall after ceasing mining operations, undertake re-grassing the mining area and any other area which may have been disturbed due to their mining activates and restore the land to a condition which is for growth of fodder, Flora, Fauna etc.”

14 Budgetary Breakup For Labor Labor Welfare Cost Capital Cost-1.0 Lakh

and Recurring Cost is 0.60 Lakh/Annum

Sr. No. Facility Provided for Laborers Capital Cost in RS. Recurring Cost In RS.

Per Year

1. Drinking water provided By Tanker 30,000/- 25,000/-

2. First Aid Box 5,000/- --

3. Rest Shelter 20,000/- 10,000/-

4. Washroom Facilities for laborers 15,000/- 10,000/-

5 Safety Shoes, hand gloves, Dust mask, Ear

plugs, Helmet 20,000/- 10,000/-

6 Insurance 10,000/- 5,000/-

Total 1.0 lakh 0.60 lakh/Annum

Observations of the committee:-

The SEAC considered/examined the project proposal on 29.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

This is an existing lease. Initially the mining lease was granted in favour of Shri Jai

Singh S/o Shri Pradeep Singh vide order dated 10.02.1997. The lease deed was executed on

dated 23.10.1998 and was registered on 30.10.1998 for 20 years (30.10.1998 to 29.10.2018).

Later on the lease was transferred to Shri Mahendra Kumar Saini S/O Shri Rajendra Kumar

Saini vide order dated 19.01.2006. Lease validity was auto extended for 50 years and valid up

to 29.10.2048.

The project being one of minor mineral having lease area of 1.0 ha., came under the

purview of the EIA Notification dated 09.09.2013 of the MoEF & CC. According to the

certificate dated 22.07.2021 of ME, Jaipur, production of mineral from 2012-13 (base year)

to 2020-21 has been nil. The project, therefore, is not one of violation of the EIA

Notification. The PP has also submitted affidavit to the affect that no activity has been carried

out in violation of the EIA Notification and Common Cause Judgment pronounced by the

Hon’ble Supreme Court.

The PP has submitted application for the first time for EC for Proposed Project of

Masonry Stone Mining project, Plot. No. 176/1996, Area 1.00 Ha., Production Capacity-

62,475 TPA (ROM), Khasra No. 336, Add.- Bhopas Dungri, Tehsil- Chomu, District-

Jaipur, (Raj.) (Proposal No.- 215830). The project is covered under B2 category. The

Simplified mining plan has been approved by the SME, Jaipur vide letter dated 09.06.2017.

ME, Jaipur in his certificate dated 30.03.2021 has stated that the mining lease does not fall in

Aravalli hills. DCF (TP), Sariska in his certificate dated 16.06.2021 has stated that Sariska

Tiger Reserve is at a distance of 48.0 Km and Sariska WLS is at a distance of 55.5 Km, DCF,

WL, Jaipur in his certificate dated 30.06.2021 has stated that Jamwaramgarh WLS is at a

distance of 27.4 Km and DCF, WL, Zoo, Jaipur in his certificate dated 24.06.2021 has stated

that Nahargarh WLS is at distance of 19.3 Km from the applied lease area and there is no

Wildlife Sanctuary/National Park/ Conservation Reserve within 10 km periphery of the mine.

The project does not involve approval/ clearance under the Forest (Conservation) Act, 1980

Final minutes of 4.95th meeting held on 27-29 July, 2021

and Wild Life Protection Act, 1972 as no forest land is involved and neither there is any Wild

Life Sanctuary/ National Park within 10 Km from the project site.

The SEAC considered the certificate dated 30.03.2021 issued by ME, Jaipur In the

certificate, it is stated that as per the MoEF & CC notification, dated 01.07.2016 there is no

other mining lease within the periphery of 500 meter and therefore, there is no cluster

formation

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1,Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri-

Mahendra Kumar Saini S/o Shri Rajendra Kumar Saini, for Masonry Stone Mining project,

Plot. No. 176/1996, Area 1.00 Ha., Production Capacity- 62,475 TPA (ROM), Khasra No.

336, Add.- Bhopas Dungri, Tehsil- Chomu, District- Jaipur, (Raj.) (Proposal No.- 215830),

with the stipulation that the PP shall abide by the annual production scheduled specified in

mining plan and that any deviation there in will render the PP liable for legal action in

accordance with Environment and Mining Laws, with the specific and general conditions

annexed at Annexure ‘A’. Name of Proponent :- Shri- Mahendra Kumar Saini S/o Shri-

Rajendra Kumar Saini, Add.- K-25, Bhawani Nagar, Murlipura, Jaipur, Distt.- Jaipur, (Raj.)

Email- [email protected], Consultant Name:- M/s. N.S. Envro- Tech

Laboratories & Consultant, , Add- Plot No. 51, Ganeta House, Shiv Vihar Colony, Near

Patrakar Colony Road, Mansarovar, Jaipur (Raj.).

Email:- [email protected].

Agenda no. 47. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19621/ 2019-20

Project Name- EC for Masonry Stone Mining project, Plot. No. 16/2020, Area 1.6997 Ha.,

Production Capacity- 4,30,737 TPA (ROM), Khasra No. 410, Add.- Gunawata, Tehsil-

Amer, District- Jaipur, (Raj.), (Proposal No.- 215850).

Project Proponent Name- Shri- Ramesh Chand Gupta S/o Shri- Gyarsi Lal Gupta, Add.-

11-Moji Colony, Malviyanagar, Distt.- Jaipur, (Raj.) Email-

[email protected].

Consultant Name- M/s. N.S. Envro- Tech Laboratories & Consultant, , Add- Plot No. 51,

Ganeta House, Shiv Vihar Colony, Near Patrakar Colony Road, Mansarovar, Jaipur (Raj.).

Email:[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1 Category /Item No.(In Schedule): 1(a) B2

2 Location of Project Gunawata Masonry Stone Mining Project,

Plot No.- 16/2020, Area- 1.6997 Ha., Near

Village- Gunawara, Tehsil – Amer, District

– Jaipur (Rajasthan) of Shri Ramesh Chand

Gupta S/o Shree Gyarsi Lal Gupta.

Final minutes of 4.95th meeting held on 27-29 July, 2021

3 Project Details ML. No. / Production Capacity Applied Area- 1.6997 Ha. Khasra No – 410,

Proposed Production Capacity – 4,30,737

TPA (ROM)

4 Project Cost: 40.0 Lacs

5 Water Requirement & Source: 5.KLD

6 Fuel &Energy:- 0.5 KLD (HSD)

7 Application No. & Date & Document Submitted:- SIE/RJ/MIN/206417/2021 on dated 26-03-

2021

8 Information About Aravalli Certificate. Aravalli letter was issued by ME Jaipur vide

letter no. ME/Jai/ CC-3/Plot No-16/20/75 on

dated 18.06.2021

9 Date of Air/Water/Noise/Monitoring Nodia Testing Laboratories 26/05/2021 to

30.05.2021

10 Information About 500 mts Composite Map 500 Mtr Map was issued by ME Jaipur vide

letter no. ME/JPR/DWG/2021/485 on dated

18.06.2021

1 Environment Management Plan EMP Cost – Capital Cost 1.60 Lac&

Recurring Cost is 1.66 Lac/Annum

S.

No. Particulars

Capital Cost in

Lakh Recurring Cost in Lakh

1 Pollution control ( water sprinkling for dust

suppression ) 0.55 0.25

2 Pollution monitoring (Air. Water ,Noise, Soil) -- 0.40

3 Greenbelt 0.56 0.73

4 Occupation health 0.25 0.10

5 Miscellaneous (Fencing, etc.) 0.24 0.15

Total 1.60 Lakh 1.63 lakh/Annum

12 Green Belt/ Plantation Capital Cost- 0.56 Lakh

Recurring Cost 0.73 Lac/Annum

Places of Plantation:-

About 560 saplings will be planted in an area of 0.560 ha (33% of applied area) upto the end of 5 years, About

560 sapling will be planted along the lease boundary at safety barrier zone& out side lease area at Govt.

Primary School, Gunavta, Jaipur (Raj).

Year

Along the mine

boundary

On Backfilled

area

Outside the

mine area Top Soil Dumps Total

Area

(Ha.)

No. of Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees Trees

Existing -- -- -- -- - -- -- -- -- --

2021-2022 0.04 40 -- -- 0.072 72 -- -- 0.112 112

2022-2023 0. 04 40 ---- -- 0.072 72 - - 0.112 112

2023-2024 0.04 40 -- -- 0.072 72 - - 0.112 112

2024-2025 0.04 40 -- -- 0.072 72 -- -- 0.112 112

2025-2026 0.04 40 -- -- 0.072 72 -- - 0.112 112

TOTAL 0.20 200 -- -- 0.36 360 -- -- 0.560 560

As per Office Memorandum 16.01.2020: Commitment by PP The mining lease holders shall after ceasing mining operations, undertake re-grassing the mining area and any other area which may have been disturbed due to their mining activates and restore the land to a condition which is for growth of fodder, Flora, Fauna etc.”

13 Budgetary Breakup For Labor Labor Welfare Cost Capital Cost-0.80 Lakh

and Recurring Cost is 0.40 Lakh/Annum

Sr. No. Facility Provided for Laborers Capital Cost in RS. Recurring Cost In RS.

Per Year

1. Drinking water provided By Tanker 20,000/- 10,000/-

2. First Aid Box 5,000/- --

3. Rest Shelter 20,000/- 7000/-

4. Washroom Facilities for laborers 10,000/- 8,000/-

5 Safety Shoes, hand gloves, Dust mask, Ear

plugs, Helmet 15,000/- 10,000/-

6 Insurance 10,000/- 5,000/-

Final minutes of 4.95th meeting held on 27-29 July, 2021

Total 0.80 lakh 0.40 Lakh/Annum

Observations of the committee:-

The SEAC considered/examined the project proposal on 29.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for EC for Masonry Stone Mining project, Plot. No.

16/2020, Area 1.6997 Ha., Production Capacity- 4,30,737 TPA (ROM), Khasra No. 410,

Add.- Gunawata, Tehsil- Amer, District- Jaipur, (Raj.), (Proposal No.- 215850). The

project is covered under B2 category. The SME, Jaipur vide order dated 23.02.2021 and

24.03.2021 (corrigendum regarding rectification of PPs name in LoI) has issued LoI to the PP

for mining of Masonry Stone. The mining plan has been approved by the SME, Jaipur vide

letter dated 10.06.2021. ME, Jaipur in his certificate dated 18.06.2021 has stated that the

mining lease does not fall in Aravalli hills. DCF (WL), Jaipur in his certificate dated

30.06.2021 has stated that Jamwaramgarh WLS is at a distance of 7.52 Km and its ESZ is at a

distance of 6.45 Km from the applied lease area. Similarly DCF, WL, Zoo, Jaipur in his

certificate dated 29.06.2021 has stated that Nahargarh WLS is at a distance of 8.7 Km and its

ESZ is at a distance of 0.36 Km from the applied lease area.

The SEAC also went through para 4 (i)/ (ii)/ (iii) and (iv) of the OM dated 08.08.2019

of the MoEF & CC which requires that the Expert Appraisal Committee would examine the

proposal from environmental angle including impact of developmental activity/ project on the

Wildlife and its habitat, if any, and recommend appropriate protection and conservation

measures and that these recommendations shall be explicitly mentioned in the EC letter.

Since the project falls within a distance of 10 Km from the boundary of National Park/

Wildlife Sanctuary and outside notified ESZ, the following specific conditions shall also be

applicable in terms of OM dated 08.08.2019 of the MoEF & CC:

1. The mining activity should be carried out in a manner so that the water

regime/system of the sanctuary is not disturbed. The mining activity should not

adversely affect any existing water course, water body, catchment etc. The PP

shall while carrying out mining activity ensure compliance of the provisions of

Air (Prevention and Control of Pollution) Act 1981, Water (Prevention and

Control of Pollution) Act 1974 and the Environment (Protection) Act, 1986 so that

the wildlife in the area is not adversely affected.

2. The processes like blasting, drilling, excavation, transport and haulage resulting

into noise, should be carried out in such an manner so that such activities do not

disturb wild animals and birds particularly during sunset to sunrise. The level of

noise should be kept within the permissible limits.

3. The mining activity should not create any obstacle in the way of free movement of

wildlife and adversely affect wildlife corridors.

4. The mineral waste/ slurry should be dumped only at the designated places only

and such waste dumps should be reclaimed in accordance with the conditions of

the mining plan/ consent issued by the RSPCB under the Water and Air act.

Final minutes of 4.95th meeting held on 27-29 July, 2021

5. The PP shall cooperate with the concerned DCF, Wildlife in their efforts towards

protection and conservation of wildlife in the Sanctuary/ Park.

6. The PP shall ensure that the transporter and labor employed by him should not

damage flora and fauna in the ESZ and the Wildlife Sanctuary/ National Park.

The SEAC considered the certificate dated 18.06.2021 issued by ME, Jaipur In the

certificate, it is stated that as per the MoEF & CC notification, dated 01.07.2016 there is no

other mining lease within the periphery of 500 meter and therefore, there is no cluster

formation

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-1,

Form- 2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to Shri- Ramesh

Chand Gupta S/o Shri- Gyarsi Lal Gupta, for Masonry Stone Mining project, Plot. No.

16/2020, Area 1.6997 Ha., Production Capacity- 4,30,737 TPA (ROM), Khasra No. 410,

Add.- Gunawata, Tehsil- Amer, District- Jaipur, (Raj.), (Proposal No.- 215850), with the

stipulation that the PP shall abide by the annual production scheduled specified in mining

plan and that any deviation there in will render the PP liable for legal action in accordance

with Environment and Mining Laws, with the specific and general conditions annexed at

Annexure ‘A’. The PP shall also abide by the special conditions as mentioned in OM dated

08.08.2019 and as noted in the above mentioned observations. Name of Proponent Shri-

Ramesh Chand Gupta S/o Shri- Gyarsi Lal Gupta, Add.- 11-Moji Colony, Malviyanagar,

Distt.- Jaipur, (Raj.), Email- [email protected], Consultant Name:- M/s.

N.S. Enviro- Tech Laboratories & Consultant, Add- Plot No. 51, Ganeta House, Shiv Vihar

Colony, Near Patrakar Colony Road, Mansarovar, Jaipur (Raj.),

Email:- [email protected].

Agenda no. 48. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19595)/ 2019-20

Project Name- Environmental Clearance for Masonry Stone (Minor Mineral) Mining

Project, ML. No.- 86/2010, Area-1.00 ha., Production Capacity- 55,000 TPA (ROM)

{Saleable Mineral- 49,500 TPA, Waste- 5500 TPA }, Khasra No.- 295, Near Vill.- Bhedoli,

Tehsil- Bonli, Distt.- Sawai Madhopur (Raj.) (Proposal No.-212036).

Project Proponent Name- M/s Aditya Minerals, Add.- R/o-- Jai Mandir Ke Pass, Jhilai

Road, Niwai, Distt.- Tonk (Raj.) Email- [email protected].

Consultant Name- VARDAN ENVIRONET Add: Plot No.-82-A, Sector- 5, IMT Manesar,

Gurgaon-122003 (Haryana). email:[email protected].

Observations and Resolution of the committee:-

The SEAC considered/examined the project proposal on 29.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

This is an existing lease. Initially the mining lease was granted in favour of Shri

Mukesh Kumar vide order dated 04.05.2011. The lease deed was registered on 30.09.2011 for

Final minutes of 4.95th meeting held on 27-29 July, 2021

30 years. Later on the lease was transferred to M/s Aditya Minerals vide order dated

18.12.2014.

The project being one of minor mineral having lease area of 0.1393 ha., came under

the purview of the EIA Notification dated 09.09.2013 of the MoEF & CC. According to the

certificate dated 27.07.2021 of AME, Sawai Madhopur, production of mineral from 2012-13

(base year) to 2020-21 has been nil. The project, therefore, is not one of violation of the EIA

Notification. The PP has also submitted affidavit to the affect that no activity has been carried

out in violation of the EIA Notification and Common Cause Judgment pronounced by the

Hon’ble Supreme Court.

The PP has submitted application for Environmental Clearance for Masonry Stone

(Minor Mineral) Mining Project, ML. No.- 86/2010, Area-1.00 ha., Production Capacity-

55,000 TPA (ROM) {Saleable Mineral- 49,500 TPA, Waste- 5500 TPA }, Khasra No.- 295,

Near Vill.- Bhedoli, Tehsil- Bonli, Distt.- Sawai Madhopur (Raj.) (Proposal No.-212036).

The project is covered under B2 category. The mining plan has been approved by the SME,

Bharatpur vide letter dated 02.03.2020. ME, Sawai Madhopur in his certificate dated

15.07.2021 has stated that the mining lease does not fall in Aravalli hills.

The SEAC considered the certificate dated 15.07.2021 issued by ME, Sawai Madhopur

In the certificate, it is stated that as per the MoEF & CC notification, dated 01.07.2016 there

is no other mining lease within the periphery of 500 meter and therefore, there is no cluster

formation.

The PP has not submitted certificate from the concerned DCF regarding existence or

otherwise of National Park or Wildlife Sanctuary from the applied lease area. The SEAC,

therefore, decided to ask the PP to submit the same within a period of 45 days failing which

the project shall be recommended to SEIAA for closure and delistment.

Agenda no. 49. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19596)/ 2019-20

Project Name- Environmental Clearance for Quartz & Feldspar (Minor Mineral) Mining

Project, ML. No.- 110/2012, Area- 4.5007 ha., Production Capacity- 1,79,494 TPA (ROM)

{Saleable 1,25,646 TPA, Sub grade- 26,924 TPA & Waste- 26,924 TPA} at Khasra No.-

1793,3168/1794, 3157/1794, 1795, 1791, 1798, 1802, 1838, 1839, 1840, 1841, 1842, 1843,

1844, 1845, 1846, 3162/1847, 3173/1847, 1848, 1849 and 3163/1851, Near Vill.- Khemana,

Tehsil- Raipur, Distt.- Bhilwara, (Raj.) (Proposal No.- 212082).

Project Proponent Name- M/s Jai Shree Ganga Mines, Add.- R/o-Ward No.- 5, Main Road,

Gangapur, Tehsil- Sahada, Distt.- Bhilwara (Raj.) Email- [email protected].

Consultant Name- VARDAN ENVIRONET, Add: Plot No.-82-A, Sector- 5, IMT Manesar,

Gurgaon-122003 (Haryana)., email:[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. 1

.

Category / Item no.(in

Schedule):

1(a)B2

2. 2

.

Location of Project Near village –Khemana, Tehsil– Raipur, District –Bhilwara(Rajasthan)

Final minutes of 4.95th meeting held on 27-29 July, 2021

3. 3

.

Project Details

M.L.No. /Area/Production

capacity/Khasra No.

M.L. No.-110/2012

Area – 4.5007 Hectare

Production capacity -179494 TPA (ROM) [Saleable- 125646 TPA, Sub grade-

26924 TPA & Waste- 26924 TPA]

Khasra No.-1793, 3168/1794, 3157/1794, 1795, 1791, 1798, 1802, 1838, 1839,

1840, 1841, 1842, 1843, 1844, 1845, 1846, 3162/1847, 3173/1847, 1848, 1849,

3163/1851

4. 4

.

Project Cost Rs. 50 Lakhs

5. 5

.

Water Requirement & Source 3.0 KLD (Tanker Water Supply from nearby village)

6. 6

.

Fuel & Energy

300Litres/day HSD Fuel will be required for mine machineries.

7. 7

.

Application No.& Date &

documents submitted

Hard Copy Submitted to SEIAA, Rajasthan SIA/RAJ/MIN/208342/2021, dated

.04.21

8. 8 Information about Aravalli

Certificate

ME/Bhil/Machi./M.L. 110/2012/1013 onDated- 25/11/2019

Date of Air/Water/Noise

Monitoring

Environment Monitoring was carried out by NABL approved laboratory.

9. 9 Information about Topo-sheet

map

45 K 03

10. Environment Sensitivity

1 Nearest Village Nearest Village is Khamana at a distance of 0.9 km in South direction from the mine site.

2 Nearest Railway Station Nearest Railway Station is Amet Railway Station at a distance of 23.0 km in West direction from the mine site.

3 Nearest Airport Nearest Airportis MaharanaPratap Airport, Udaipur at a distance of 84.0 km in SW direction from the mine site.

4 Nearest National / State Highway S.H.-61 at a distance of 20 Km in NE direction from the mine site.

5 Archaeological Important Place No any Archaeological Important Place found within 15 km distance from the periphery of lease area.

6 Ecological Sensitive Park, Wildlife Sanctuary, Reserve etc.)

No any Ecological Sensitive Park, Wildlife Sanctuary, Reserve etc. found within 15 km distance from the periphery of lease area.

7 Nearest River/water body

NaharSagar at a distance of 6.4 km in West direction from the mine site.

Kothari River at a distance of 9.5 km in NW direction from the mine site. PadamSagar at a distance of 10.7 km in West direction from the mine site. BanmaniNadi at a distance of 13.0 km in East direction from the mine site. KhushalSagar at a distance of 13.0 km in SE direction from the mine site. FatehSagar at a distance of 14.2 km in South direction from the mine site.

JhanvaranKaTalav at a distance of 14.4 km in SE direction from the mine site.

8 Reserved/Protected Forests

Charot P.F. at a distance of 5.4 km in SW direction from the mine site. Sirodi P.F. at a distance of 10.5 km in West direction from the mine site. Sarawat Mata P.F. at a distance of 9.3 km in NW direction from the mine site. Kangni R.F. at a distance of 11.8 km in SE direction from the mine site.

Final minutes of 4.95th meeting held on 27-29 July, 2021

11. 1

0

Environment Management Plan

Sr.No. PARTICULAR CAPITAL COST

(IN RS.) RECURRING COST

(IN RS./YEAR)

1 Water sprinkle facility on haul roads to prevent dust suppression. - 30,000/-

2 Maintenance of approach road - 70,000/-

3 Pollution Monitoring of Ambient Air, Noise, Water & Soil Quality - 50,000/-

4 Plantation/Green Belt & maintenance 4,00,000/- 80,000/-

5 Wire fence around mining pits 1,00,000/- 10,000/-

6 Occupational health check-up in a year - 30,000/-

7 Provision of PPES (helmet shoes gloves goggles etc.) - 10,000/-

9 Emergency rescue fire fighting equipments and first aid 30,000/- 15,000/-

10 Caution board (will illustrate lease detail and name of the PHC and contact no. of doctor)

20,000/- 1,000/-

11 Solar pole with LED light @ 8000/- Per Light 50,000/- 4,000/-

TOTAL 6,00,000/- 3,00,000/-

12. 1

2

Green Belt/ Plantation

Year Un-worked Area (Outside haul

roads)

Top Soil Dumps Total

Area

(Ha.)

No. of

Trees

Area

(Ha.

No. Of

Trees

Area

(Ha.)

No. Of

Trees

Area (Ha.) No. Of

Trees

Existing - - - - - - - -

I 0.50 500 0.01 10 0.51 510

II 0.49 490 - - 0.49 490

III 0.49 490 - - 0.49 490

IV Maintenance - - - - Maintenance

V

Total 1.48 1480 0.01 10 1.49 1490

Annual expenditure: Rs80, 000/- Total 1490 saplings will be planted in upcoming 3 years and Area for plantation-1.48

ha will developed inside the lease area at 7.5 m safety boundary & rest 0.01 ha. will developed as greenbelt outside

along haul roads.

The mining lease holders shall, after ceasing mining operations, undertake re-grassing the mining area and any other

area which may have been disturbed due to their mining activities and restore the land to a condition which is fit for

growth of fodder, flora, fauna etc. as per MoEF& CC O.M. dated 16.01.20.

13. 1

3

Budgetary Breakup for Labour

Annual expenditure: Rs30,000

Sr.No

.

Description Capital Cost(in Rs.) Recurring Cost(in Rs./Yr.)

1 Rest Shelter 40,000 1,000

2 Drinking water facility 20,000 3,000

3 Toilet Facility (2 units for Male & Female) 10,000 2,000

4 Fuel for cooking - 10,000

5 Medical facility for labors - 14,000

Total 70,000 30,000

14. 1

4

Present Status

Existing Mining Project

Observations of the committee:-

The SEAC considered/examined the project proposal on 29.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

Final minutes of 4.95th meeting held on 27-29 July, 2021

This is an existing lease. The mining lease for mineral Quartz and Feldspar over an

area 4.5007 ha was granted in favour of M/S Jai Shree Ganga Mines vide order dated

16.05.2013. The lease deed was registered on 12.08.2013 for 30 years.

The project being one of major mineral (before 10.02.2015) having lease area of

4.5007 ha. (less than 5.0 ha.), came under the purview of the EIA Notification dated

07.10.2014 of the MoEF & CC. According to the certificate dated 26.07.2021 of AME,

Bhilwara the production of mineral from 2013-14 (base year) to 2020-21 has been nil. The

project, therefore, is not one of violation of the EIA Notification. The PP has also submitted

affidavit to the affect that no activity has been carried out in violation of the EIA Notification

and Common Cause Judgment pronounced by the Hon’ble Supreme Court.

The PP has submitted application for EC for Quartz & Feldspar (Minor Mineral)

Mining Project, ML. No.- 110/2012, Area- 4.5007 ha., Production Capacity- 1,79,494 TPA

(ROM) {Saleable 1,25,646 TPA, Sub grade- 26,924 TPA & Waste- 26,924 TPA} at Khasra

No.- 1793,3168/1794, 3157/1794, 1795, 1791, 1798, 1802, 1838, 1839, 1840, 1841, 1842,

1843, 1844, 1845, 1846, 3162/1847, 3173/1847, 1848, 1849 and 3163/1851, Near Vill.-

Khemana, Tehsil- Raipur, Distt.- Bhilwara, (Raj.) (Proposal No.-212082). The project is

covered under B2 category. The mining plan has been approved by the SME, Bhilwara vide

letter dated 03.01.2019. AME, Bhilwara in his certificate dated 25.11.2019 has stated that the

mining lease does not fall in Aravalli hills. DCF, Bhilwara in his certificate dated 02.12.2019

has stated that there is no Wildlife Sanctuary/National Park/ Conservation Reserve within 10

km periphery of the mine in his jurisdiction.

DCF (WL), Rajsamand in his certificate dated 23.11.2020 has stated that Todgarh

Raoli WLS is situated at a distance of 28.0 Km and Kumbhalgarh WLS is situated at a

distance of 35.5 Km from the applied lease area.

The project does not involve approval/ clearance under the Forest (Conservation)

Act, 1980 and Wild Life Protection Act, 1972 as no forest land is involved and neither there

is any Wild Life Sanctuary/ National Park within 10 Km from the project site.

According to cluster certificate and map dated 19.07.2021 issued by AME, Bhilwara,

issued in terms of Notifications of MoEF & CC dated 15.01.2016 and 01.07.2016, there is no

cluster formation.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-1,

Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to M/s Jai Shree

Ganga Mines, for Quartz & Feldspar (Minor Mineral) Mining Project, ML. No.- 110/2012,

Area- 4.5007 ha., Production Capacity- 1,79,494 TPA (ROM) {Saleable 1,25,646 TPA, Sub

grade- 26,924 TPA & Waste- 26,924 TPA} at Khasra No.- 1793, 3168/1794, 3157/1794,

1795, 1791, 1798, 1802, 1838, 1839, 1840, 1841, 1842, 1843, 1844, 1845, 1846, 3162/1847,

3173/1847, 1848, 1849 and 3163/1851, Near Vill.- Khemana, Tehsil- Raipur, Distt.-

Bhilwara, (Raj.) (Proposal No.-212082), with the stipulation that the PP shall abide by the

annual production scheduled specified in mining plan and that any deviation there in will

Final minutes of 4.95th meeting held on 27-29 July, 2021

render the PP liable for legal action in accordance with Environment and Mining Laws, with

the specific and general conditions annexed at Annexure ‘A’. Name of Proponent M/s Jai

Shree Ganga Mines, Add.- R/o-Ward No.- 5, Main Road, Gangapur, Tehsil- Sahada, Distt.-

Bhilwara (Raj.), Email- [email protected], Consultant Name:- VARDAN

ENVIRONET Add: Plot No.-82-A, Sector- 5, IMT Manesar, Gurgaon-122003 (Haryana).

email:- [email protected].

Agenda no. 50. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19598)/ 2019-20

Project Name- Environmental Clearance for Marble Mineral Mining Project, Plot No.- 5,

Production Capacity- 3,48,106 TPA (ROM) {Saleable Mineral Marble- 1,31,021 TPA,

Waste- 1,91,367 TPA & OB- 25,718 TPA}, Area- 4.0 ha., Khasra no.- 1536, Near Vill.-

Lohagarh, Tehsil- Dhariyawad, Distt.- Pratapgarh (Raj.) (Proposal No.-210560).

Project Proponent Name- M/s Paramount Mines & Minerals, Pro. Shri Mahesh Agarwal ,

Add.- R/o- B-106, 10-B, Scheme Gopalpura Bypass Jaipur, (Raj.) Email-

[email protected]

Consultant Name- VARDAN ENVIRONET, Add: Plot No.-82-A, Sector- 5, IMT Manesar,

Gurgaon- 122003 (Haryana)., email:[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. 1

.

Category / Item no.(in

Schedule):

1(a)B2

2. 2

.

Location of Project Near village –Lohagarh, Tehsil– Dhariyawad, District– Pratapgarh(Rajasthan)

3. 3

.

Project Details

M.L.No. /Area/Production

capacity/Khasra No.

Plot No.-05

Area – 4.0 Hectare

Production capacity -348106 TPA (ROM) {Salable Mineral Marble-1,31,021 TPA, Waste – 1,91,367 TPA & OB- 25,718 TPA}

Khasra No.-1536

4. 4

.

Project Cost Rs. 80 Lakhs

5. 5

.

Water Requirement & Source 3.0 KLD (Tanker Water Supply from nearby village)

6. 6

.

Fuel & Energy

250Litres/day HSD Fuel will be required for mine machineries.

7. 7

.

Application No.& Date &

documents submitted

Online Submitted by Proposal No.-SIA/RAJ/MIN/210560/2021, dated 29.04.21

8. 8 Information about Aravalli

Certificate

ME/Pratap/CC-Minor/Delie Plot No.05/2019/2020-21/148 onDated- 22/1/2021

Date of Air/Water/Noise

Monitoring

Environment Monitoring was carried out by NABL approved laboratory.

9. 9 Information about Topo-sheet

map

45I 5

10. Environment Sensitivity

1 Nearest Village Nearest Village is Lohagarh at a distance of 3.24 km in North direction from the

mine site.

2 Nearest Railway Station Nearest railway station is Semari Railway Station ~ 44.78 km in NW direction

from Mine Site.

3 Nearest Airport Nearest Airport is in Udaipur ~ 79.91 Km in NW direction from mine site.

4 Nearest National / State

Highway

S.H.-32 is found about 14.0 km in SW direction from mine site.

No any Nearest National found within 15 km distance from the periphery of lease

area.

Final minutes of 4.95th meeting held on 27-29 July, 2021

5 Archaeological Important

Place

No any Archaeological Important Place is found within 15 km distance from the

periphery of lease area.

6 Ecological Sensitive Park,

Wildlife Sanctuary, Reserve

etc.

No any Ecological Sensitive Park, National Parks, Wildlife Sanctuary, Reserve

etc. are found within 15 km distance from the periphery of lease area.

7 Nearest River / water body Jakam River is found about 0.60 km in ESE direction from mine site.

BinatalNadi is found about 8.3 km in NE direction from mine site.

Mahi River is found about 10.2 km in SE direction from mine site.

SukilNadi is found about 14.6 km in NE direction from mine site.

BarasNadi is found about 14.3 km in WNW direction from mine site.

Som River is found about 6.1 km in SW direction from mine site.

8 Reserved/Protected Forests Kanaiya RF exists about 2.8 km in SSE direction from mine site.

Haswar PF exists about 3.8 km in ESE direction from mine site.

Padlabavri PF exists about 5.3 km in NE direction from mine site.

Padlabavri RF exists about 7.3 km in NE direction from mine site.

Devla PF exists about 5.1 km in NE direction from mine site.

Manpur PF exists about 9.1 km in ENE direction from mine site.

Makpura PF exists about 13.0 km in ESE direction from mine site.

Jagpura RF exists about 11.1 km in SE direction from mine site. Mundela RF exists about 10.2 km in SE direction from mine site.

Rathri PF exists about 2.3 km in SW direction from mine site.

Dad RF exists about 12.1 km in WSW direction from mine site.

Dad PF exists about 13.7 km in WNW direction from mine site.

Manpur Block RF exists about 6.5 km in NW direction from mine site.

Padva Block RF exists about 9.0 km in NNW direction from mine site.

Padla Block PF exists about 10.3 km in N direction from mine site.

Narveri PF exists about 12.6 km in NNE direction from mine site.

Dholagarh Block RF exists about 13.5 km in NW direction from mine site.

Kukra Block RF exists about 14.0 km in NNW direction from mine site.

Sarvadiven Block RF exists about 13.5 km in NW direction from mine site.

11. 1

0

Environment Management Plan

Sr.

No. PARTICULAR

CAPITAL

COST

(IN RS.)

RECURRING

COST

(IN

RS./YEAR)

1 Water sprinkle facility on haul roads to prevent dust suppression. - 40,000

2 Maintenance of approach road - 1,00,000

3 Pollution Monitoring of Ambient Air, Noise, Water & Soil Quality - 50,000

4 Plantation/Green Belt & maintenance 4,00,000 1,20,000

5 Wire fence around mining pits 1,00,000 30,000

6 Occupational health check-up in a year - 40,000

7 Provision of PPES (helmet shoes gloves goggles etc.) - 10,000

9 Emergency rescue fire fighting equipments and first aid 30,000 5,000

10 Caution board (will illustrate lease detail and name of the PHC and

contact no. of doctor) 20,000 1,000

11 Solar pole with LED light @ 8000/- Per Light 50,000 4,000

TOTAL 6,00,000 4,00,000

12. 1

2

Green Belt/ Plantation Year Un-worked Area (Outside haul

roads)

Top Soil Dumps Total

Area

(Ha.)

No. of

Trees

Area

(Ha.

No. Of

Trees

Area

(Ha.)

No. Of

Trees

Area (Ha.) No. Of

Trees

Existing - - - - - - - -

I 0.38 380 0.1 100 0.48 480

II 0.37 370 0.1 100 0.47 470

III 0.37 370 0.37 370

IV Maintenance - - - - Maintenance

V

1.12 1120 0.2 200 1.32 1320

Final minutes of 4.95th meeting held on 27-29 July, 2021

Annual expenditure: Rs 1, 20,000 Total 1320 saplings will be planted in upcoming 3 years and Area for plantation-1.12

ha. will developed inside the lease area at 7.5 m safety boundary & rest will developed as greenbelt outside along haul

roads.

The mining lease holders shall, after ceasing mining operations, undertake re-grassing the mining area and any other

area which may have been disturbed due to their mining activities and restore the land to a condition which is fit for

growth of fodder, flora, fauna etc. as per MoEF& CC O.M. dated 16.01.20.

13. 13

Budgetary Breakup for Labour

Annual expenditure: Rs30,000

Sr.No

.

Description Capital Cost(in Rs.) Recurring Cost(in Rs./Yr.)

1 Rest Shelter 40,000 1,000

2 Drinking water facility 20,000 3,000

3 Toilet Facility (2 units for Male & Female) 10,000 2,000

4 Fuel for cooking - 10,000

5 Medical facility for labors - 14,000

Total 70,000 30,000

14. 1

4

Present Status

New Mining Project

Observations of the committee:-

The SEAC considered/examined the project proposal on 29.07.2021by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for EC for Marble Mineral Mining Project, Plot

No.- 5, Production Capacity- 3,48,106 TPA (ROM) {Saleable Mineral Marble- 1,31,021

TPA, Waste- 1,91,367 TPA & OB- 25,718 TPA}, Area- 4.0 ha., Khasra no.- 1536, Near

Vill.- Lohagarh, Tehsil- Dhariyawad, Distt.- Pratapgarh (Raj.) (Proposal No.-210560). The

project is covered under B2 category. The SME, Udaipur vide order dated 21.12.2020 has

issued LoI to the PP for mining of Marble. The mining plan has been approved by the SME,

Udaipur vide letter dated 20.04.2021. ME, Pratapgarh in his certificate dated 22.01.2021 has

stated that the mining lease does not fall in Aravalli hills. DCF, WL, Chittorgarh in his

certificate dated 05.03.2021 has stated that Sitamata WLS is at a distance of 28.56 Km from

the applied lease area and there is no Wildlife Sanctuary/National Park/ Conservation

Reserve within 10 km periphery of the mine. The project does not involve approval/

clearance under the Forest (Conservation) Act, 1980 and Wild Life Protection Act, 1972 as

no forest land is involved and neither there is any Wild Life Sanctuary/ National Park within

10 Km from the project site.

As per cluster certificate issued by ME, Pratapgarh on 22.01.2021, the total area of all

the mining leases in the cluster having area of 4.00 ha.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-1,

Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to M/s

Paramount Mines & Minerals, Pro. Shri Mahesh Agarwal, for Marble Mineral Mining

Project, Plot No.- 5, Production Capacity- 3,48,106 TPA (ROM) {Saleable Mineral Marble-

1,31,021 TPA, Waste- 1,91,367 TPA & OB- 25,718 TPA}, Area- 4.0 ha., Khasra no.- 1536,

Final minutes of 4.95th meeting held on 27-29 July, 2021

Near Vill.- Lohagarh, Tehsil- Dhariyawad, Distt.- Pratapgarh (Raj.) (Proposal No.-210560),

with the stipulation that the PP shall abide by the annual production scheduled specified in

mining plan and that any deviation there in will render the PP liable for legal action in

accordance with Environment and Mining Laws, with the specific and general conditions

annexed at Annexure ‘A’. Name of Proponent: M/s Paramount Mines & Minerals Pro. Shri

Mahesh Agarwal , Add.- R/o- B-106, 10-B, Scheme Gopalpura Bypass Jaipur, (Raj.) Email-

[email protected], Consultant Name:- VARDAN ENVIRONET

Add: Plot No.-82-A, Sector- 5, IMT Manesar, Gurgaon-122003 (Haryana).

email:- [email protected].

Agenda no. 51. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19599)/ 2019-20

Project Name- Environmental Clearance for Marble Mineral Mining Project, Plot No.- 6,

Production Capacity- 3,09,529 TPA (ROM) {Saleable Mineral Marble- 1,25,234 TPA,

Waste- 1,58,577 TPA & OB- 25,718 TPA}, Area- 4.0 ha., Khasra no.- 1536, Near Vill.-

Lohagarh, Tehsil- Dhariyawad, Distt.- Pratapgarh (Raj.) (Proposal No.-210620).

Project Proponent Name- M/s Paramount Mines & Minerals, Pro. Shri Mahesh Agarwal ,

Add.- R/o- B-106, 10-B, Scheme Gopalpura Bypass Jaipur, (Raj.) Email-

[email protected].

Consultant Name- VARDAN ENVIRONET

Add: Plot No.-82-A, Sector- 5, IMT Manesar, Gurgaon-122003 (Haryana).

email:[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. 1

.

Category / Item no.(in

Schedule):

1(a)B2

2. . Location of Project Near village –Lohagarh, Tehsil– Dhariyawad, District– Pratapgarh(Rajasthan)

3. 3

.

Project Details

PlotNo. /Area/Production

capacity/Khasra No.

Plot No.-06

Area – 4.0 Hectare

Production capacity -3,09,529 TPA (ROM) {Salable Mineral Marble-1,25,234 TPA,

Waste – 1,58,577 TPA & OB- 25,718 TPA}

Khasra No.-1536

4. . Project Cost Rs. 80 Lakhs

5. 5

.

Water Requirement & Source 3.0 KLD (Tanker Water Supply from nearby village)

6. 6

.

Fuel & Energy

300Litres/day HSD Fuel will be required for mine machineries.

7. 7

.

Application No.& Date &

documents submitted

SIA/RAJ/MIN/210620/2021

8. 8 Information about Aravalli

Certificate

ME/Pratap/CC-Minor/Delineated Plot No.06/2019/2020-21/150 onDated- 22/1/2021

Date of Air/Water/Noise Monitoring

Environment Monitoring was carried out by NABL approved laboratory.

9. 9 Information about Topo-sheet

map

45I 5

10. Environment Sensitivity

1 Nearest Village Lohagarh at 3.24 km in North direction from Mine Site.

2 Nearest Railway Station Nearest railway station is Semari Railway Station ~ 44.78

km in NW direction from Mine Site.

3 Nearest Airport Nearest Airport is in Udaipur ~ 79.91 Km in NW direction

from mine site.

Final minutes of 4.95th meeting held on 27-29 July, 2021

4 Nearest National / State Highway S.H.-32 is found about 14.0 km in SW direction from mine

site.

5 Archaeological Important Place None, within 15 km distance from the periphery of lease

area.

6 Ecological Sensitive Park, Wildlife

Sanctuary, Reserve etc.)

None, within 15 km distance from the periphery of lease

area.

7 Nearest River/water body Jakam River is found about 0.60 km in ESE direction from mine site.

BinatalNadi is found about 8.3 km in NE direction from

mine site.

Mahi River is found about 10.2 km in SE direction from

mine site.

SukilNadi is found about 14.6 km in NE direction from

mine site.

BarasNadi is found about 14.3 km in WNW direction from

mine site.

Som River is found about 6.1 km in SW direction from

mine site.

8 Reserved/Protected Forests Kanaiya RF exists about 2.8 km in SSE direction from mine site.

Haswar PF exists about 3.8 km in ESE direction from mine

site.

Padlabavri PF exists about 5.3 km in NE direction from

mine site.

Padlabavri RF exists about 7.3 km in NE direction from

mine site.

Devla PF exists about 5.1 km in NE direction from mine

site.

Manpur PF exists about 9.1 km in ENE direction from mine

site. Makpura PF exists about 13.0 km in ESE direction from

mine site.

Jagpura RF exists about 11.1 km in SE direction from mine

site.

Mundela RF exists about 10.2 km in SE direction from

mine site.

Rathri PF exists about 2.3 km in SW direction from mine

site.

Dad RF exists about 12.1 km in WSW direction from mine

site.

Dad PF exists about 13.7 km in WNW direction from mine site.

Manpur Block RF exists about 6.5 km in NW direction

from mine site.

Padva Block RF exists about 9.0 km in NNW direction

from mine site.

Padla Block PF exists about 10.3 km in N direction from

mine site.

Narveri PF exists about 12.6 km in NNE direction from

mine site.

Dholagarh Block RF exists about 13.5 km in NW direction

from mine site.

Kukra Block RF exists about 14.0 km in NNW direction from mine site.

Sarvadiven Block RF exists about 13.5 km in NW direction

from mine site.

11. 1

0

Environment Management Plan

Sr.

No. PARTICULAR

CAPITAL

COST

(IN RS.)

RECURRING

COST

(IN RS./YEAR)

1 Water sprinkle facility on haul roads to prevent dust suppression. - 40,000

Final minutes of 4.95th meeting held on 27-29 July, 2021

2 Maintenance of approach road - 1,00,000

3 Pollution Monitoring of Ambient Air, Noise, Water & Soil Quality - 50,000

4 Plantation/Green Belt & maintenance 4,00,000 1,20,000

5 Wire fence around mining pits 1,00,000 30,000

6 Occupational health check-up in a year - 40,000

7 Provision of PPES (helmet shoes gloves goggles etc.) - 10,000

9 Emergency rescue fire fighting equipments and first aid 30,000 5,000

10 Caution board (will illustrate lease detail and name of the PHC and

contact no. of doctor) 20,000 1,000

11 Solar pole with LED light @ 8000/- Per Light 50,000 4,000

TOTAL 6,00,000 4,00,000

12. 1

2

Green Belt/ Plantation

Year Un-worked Area (Outside haul

roads)

Top Soil

Dumps

Total

Area

(Ha.)

No. of

Trees

Area

(Ha.

No. Of

Trees

Area

(Ha.)

No. Of

Trees

Area

(Ha.)

No. Of

Trees

Existing - - - - - - - -

I 0.38 380 0.1 100 0.48 480

II 0.37 370 0.1 100 0.47 470

III 0.37 370 0.37 370

IV Maintenance - - - - Maintenance

V

1.12 1120 0.2 200 1.32 1320

Annual expenditure: Rs 1,20,000/- Total 1320 saplings will be planted in upcoming 3 years and Area for plantation-

1.12 ha will developed inside the lease area at 7.5 m safety boundary & rest will developed as greenbelt outside along

haul roads.

The mining lease holders shall, after ceasing mining operations, undertake re-grassing the mining area and any other

area which may have been disturbed due to their mining activities and restore the land to a condition which is fit for

growth of fodder, flora, fauna etc. as per MoEF& CC O.M. dated 16.01.20.

13. 1

3

Budgetary Breakup for Labour

Annual expenditure: Rs30,000

S.No. Description Capital Cost(in Rs.) Recurring Cost(in Rs./Yr.)

1 Rest Shelter 40,000 1,000

2 Drinking water facility 20,000 3,000

3 Toilet Facility (2 units for Male &

Female) 10,000 2,000

4 Fuel for cooking - 10,000

5 Medical facility for labors - 14,000

Total 70,000 30,000

14. 4 Present Status New Mining Project

Observations of the committee:-

The SEAC considered/examined the project proposal on 29.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for Marble Mineral Mining Project, Plot No.- 6,

Production Capacity- 3,09,529 TPA (ROM) {Saleable Mineral Marble- 1,25,234 TPA,

Waste- 1,58,577 TPA & OB- 25,718 TPA}, Area- 4.0 ha., Khasra no.- 1536, Near Vill.-

Lohagarh, Tehsil- Dhariyawad, Distt.- Pratapgarh (Raj.) (Proposal No.-210620). The project

is covered under B2 category. The SME, Udaipur vide order dated 21.12.2020 has issued LoI

to the PP for mining of Marble. The mining plan has been approved by the SME, Udaipur

vide letter dated 20.04.2021. ME, Pratapgarh in his certificate dated 22.01.2021 has stated

Final minutes of 4.95th meeting held on 27-29 July, 2021

that the mining lease does not fall in Aravalli hills. DCF, WL, Chittorgarh in his certificate

dated 05.03.2021 has stated that Sitamata WLS is at a distance of 28.66 Km from the applied

lease area and there is no Wildlife Sanctuary/National Park/ Conservation Reserve within 10

km periphery of the mine. The project does not involve approval/ clearance under the Forest

(Conservation) Act, 1980 and Wild Life Protection Act, 1972 as no forest land is involved

and neither there is any Wild Life Sanctuary/ National Park within 10 Km from the project

site.

As per cluster certificate issued by ME, Pratapgarh on 22.01.2021, the total area of

all the mining leases in the cluster having area of 4.00 ha.

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-1,

Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, resolved to recommend to SEIAA for grant of EC to M/s

Paramount Mines & Minerals, Pro. Shri Mahesh Agarwal, for Marble Mineral Mining

Project, Plot No.- 6, Production Capacity- 3,09,529 TPA (ROM) {Saleable Mineral Marble-

1,25,234 TPA, Waste- 1,58,577 TPA & OB- 25,718 TPA}, Area- 4.0 ha., Khasra no.- 1536,

Near Vill.- Lohagarh, Tehsil- Dhariyawad, Distt.- Pratapgarh (Raj.) (Proposal No.-210620),

with the stipulation that the PP shall abide by the annual production scheduled specified in

mining plan and that any deviation there in will render the PP liable for legal action in

accordance with Environment and Mining Laws, with the specific and general conditions

annexed at Annexure ‘A’. Name of Proponent M/s Paramount Mines & Minerals Pro. Shri

Mahesh Agarwal , Add.- R/o- B-106, 10-B, Scheme Gopalpura Bypass Jaipur, (Raj.) Email-

[email protected], Consultant Name:- VARDAN ENVIRONET

Add: Plot No.-82-A, Sector- 5, IMT Manesar, Gurgaon-122003 (Haryana).

email:- [email protected].

Agenda no. 52. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19628)/ 2019-20

Project Name- Application for ToR/ Transfer of EC from Shri Nirmal Kumar Patni to Dr.

Rashmi Patni for Marble Mining Lease, M.L. No. 07/1961 {22/2000 (R)}, Area 1.3935

Ha., Production Capacity- 11,394.6 TPA (ROM), at Khasra No. 977, Add.- Bhaislana,

Tehsil- Kotputli, District- Jaipur, (Raj.), (Proposal No.- 186593).

Project Proponent Name- Dr. Rashmi Patni, Add.- 5, Jha 30, Jawahar Nagar, Jaipur,

Distt.- Jaipur, (Raj.) Email- [email protected]

Consultant Name- MANTRAS GREEN RESOURCES LTD

Hall No.- 1 NICE Sankul Plot No.- A-9, Opp. Nasik Marchant Co Op Bank Ltd, ITI Signal,

MIDC Satpur, Nasik), email:[email protected].

Observations and Resolution of the committee:-

The SEAC considered/examined the project proposal on 29.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

Final minutes of 4.95th meeting held on 27-29 July, 2021

This is an existing lease. Initially, the mining lease for mineral Marble (Minor

Mineral), Area- 1.3935 ha. was granted in favour of Shri Nirmal Kumar Patni by vide order

dated 23.08.1961 for a period of 5 years. The validity of mining lease was extended from

time to time and the same is now valid from 16.10.1961 to 31.03.2025. The lease was later on

transferred to Dr. Rashmi Patni vide order dated 11.07.2018. The lease was executed on

dated 09.10.2018 & registered on dated 28.11.2018.

The DEIAA, Jaipur vide letter dated 11.04.2017 had granted EC to Shri Nirmal

Kumar Patni for mining of Marble having production capacity of 11,394.6 TPA.

The project being one of minor mineral having lease area of 1.3935 ha., came under

the purview of the EIA Notification dated 09.09.2013 of the MoEF & CC. According to the

certificate dated 09.02.2021 of AME, Kotputli, production of mineral in the base year i.e.

2012-13 was 1060.5 Ton (Marble block) and 930.00 Ton (Marble Khanda). The production of

mineral, however, increased in the year 2013-14 and 2014-15, in comparison to base years

production level without obtaining prior EC from the regulatory authority in violation of the

EIA Notification. Production of mineral, in the subsequent years i.e. 2019-20 has been less

than the base year’s production level or as per EC granted by DEIAA vide order dated

11.04.2017. The project is therefore one of violation of the EIA Notification/ Common Cause

Judgement of the Hon’ble Supreme Court and has to be dealt with accordingly.

The PP has submitted application for ToR/ Transfer of EC in form -7, from Shri

Nirmal Kumar Patni to Dr. Rashmi Patni for Marble Mining Lease, M.L. No. 07/1961

{22/2000 (R)}, Area 1.3935 Ha., Production Capacity- 11,394.6 TPA (ROM), at Khasra No.

977, Add.- Bhaislana, Tehsil- Kotputli, District- Jaipur, (Raj.), (Proposal No.- 186593).

The project is covered under B2 category. The mining scheme in favour of Dr. Rashmi Patni

has been approved by the SME, Jaipur vide letter dated 16.10.2020. AME, Kotputli in his

certificate dated 12.01.2021 has stated that the mining lease does not fall in Aravalli hills.

DCF (WL), Jaipur in his certificate dated 24.02.2021 has stated that Jamwaramgarh WLS is

at a distance of 46.94 Km and DCF (WL), Zoo, Jaipur in his certificate dated 08.03.2021 has

stated that Nahargarh WLS is at distance of 70.0 Km from the applied lease area.

The SEAC considered the certificate dated 12.01.2021 issued by AME, Kotputli In the

certificate, it is stated that as per the MoEF & CC notification, dated 12.01.2021 is no other

mining lease within the periphery of 500 meter and therefore, there is no cluster formation.

Sh. Nirmal Kumar Patni has given no objection certificate regarding transfer of EC to

Dr. Rashmi Patni. Dr. Rashmi Patni (PP) has submitted undertaking that she will comply with

all the conditions (specific and general) laid down in the EC issued by DEIAA vide order

dated 11.04.2017.

The PP with the application for transfer of EC has not submitted report of compliance

of conditions of earlier EC as certified by the MoEF & CC/ RSPCB. The SEAC during

presentation asked the PP to submit the same at the time of final presentation of the project

for obtaining EC.

The SEAC examined the project in the light of OM dated 12.11.2020 of the MoEF &

CC. This OM provides that while considering the application for EC under violation category

Final minutes of 4.95th meeting held on 27-29 July, 2021

as per Notification dated 14.03.2017 of the MoEF & CC, the SEAC may insist upon public

hearing to be conducted only for those category of projects for which EIA Notification, 2006

itself requires public hearing to be conducted. The project, under consideration, is one of ‘B2’

category and being so does not require public hearing as per EIA Notification, 2006 read with

various OM’s and guidelines issued by the MoEF & CC, from time to time.

The SEAC, in view of the project being one of violation of the EIA notification as

also in terms of Common Cause judgment of the Hon’ble Supreme Court, decided that the PP

is required to conduct Environmental Impact Assessment Study and prepare Remediation

Plan, Natural Resource Augment Plan and Community Resource Augmentation Plan.

Keeping in view the presentation made by the PP/ Consultant and examination of

documents submitted by them, the SEAC resolved to recommend to SEIAA for prescribing

the ToR mentioned at ‘Annexure B’, as a case of violation of the EIA notification, for

preparing comprehensive EIA/EMP reports and Assessment of Ecological Damage,

preparation of Remediation Plan and Natural Community Resource Augmentation Plan as a

case of violation, of the EIA notification.

Agenda no. 53. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(19629)/ 2019-20

Project Name- Transfer of E C from Shri Lala Ram Choudhary to M/s Shri Balaji Stone

Crusher for Masonry Stone Mining Lease, M.L. No. 471/06, Area 1.0 Ha.,Production

Capacity-99000 TPA(ROM), at Khasra No. 376/1/1, 373/1, Add.- Kundala Ki Dhani,

Tehsil- Neem Ka Thana, District- Sikar, (Raj.), (Proposal No.- 180508)

Project Proponent Name- M/s Shri- Balaji Stone Crusher, Add.- 9, Leela Mention, Raj

Bhawan Road, Civil Lines, Jaipur, Distt.- Jaipur, (Raj.) Email-

[email protected]

Consultant Name- MANTRAS GREEN RESOURCES LTD

Hall No.- 1 NICE Sankul Plot No.- A-9, Opp. Nasik Marchant Co Op Bank Ltd, ITI Signal,

MIDCSatpur,Nasik),email:[email protected]

Observations and Resolution of the committee:-

The PP vide letter dated 29.07.2021 has submitted an application for deferment of the

case. The SEAC agreed to the request of the PP and deferred the matter. The project shall be

taken up again on receipt of his request for consideration of the project by the PP, in the

subsequent proposed meeting.

Agenda no. 54. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2(18073)/ 2019-20

Project Name: - Environmental Clearance for Marble Mineral Mining Project, Q.L. No.-

96/A, Area-0.0574 ha, Production Capacity- 2200 TPA at Khasra No.- 702, Near Village-

Ullodi Range, Tehsil- Makrana, Distt.- Nagaur, (Raj.).(Proposal No.-141385).

Project Proponent Name:- M/s Mainudeen and Brothers Makrana, Add.- Village- Makrana,

Tehsil- Makrana, Distt.- Nagaur, (Raj.)Email – [email protected]

Final minutes of 4.95th meeting held on 27-29 July, 2021

Consultant Name:- M/s. N.S. Envro- Tech Laboratories & Consultant, Add.- Corpo

OFFICE Add Plot No. 69/318, V.T. Road Chouraha, Madhyam Marg, Mansarovar, Jaipur

(Raj.). Email:- [email protected], [email protected]

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category /Item No.(In Schedule): 1(a) B2

2 Location of Project Near village- Makrana, Tehsil- Makrana, District- Nagaur, Rajasthan.

3 Project Details ML. No. / Production

Capacity Q. L. No.-96/A

Existing Area-).0574 Ha.

Production Capacity: 2200 TPA Marble

4 Project Cost: 30.0 Lac

5 Water Requirement & Source: 2.50KLD

6 Fuel & Energy:- 0.5 KLD (HSD)

7 Application No. & Date & Document

Submitted:- Proposal No: SIA/RJ/MIN/141385/2020,

8 Information About Aravalli Certificate. Aravalli letter was issued by ME Makrana, vide

letter no. ME/Mak / Mach/2018/06, Dated-27.01.2020.

9 Date of Air/Water/Noise/Monitoring 01/01/2020 to 02/01/2020

10 Information About 500 mts Composite

Map 500 m Map was issued by ME Makrana, vide letter

no. ME/Mak/QL/Bapi -96/17/523, Dated-16.08.2017.

11 Environment Management Plan EMP Cost Capital cost 1.15 Lac and

Recurring cost – 0.85 Lac.

S. No. Particulars Capital Cost in RS.

Recurring

cost in Rs.

per years 1 Pollution control ( water

sprinkling for dust

suppression )

-- 20,000

2 Pollution monitoring (Air.

Water ,Noise, Soil) -- 15,000

3 Greenbelt Sr.

No

Particulars Amount

1 Plant 60 20,000

2 Tree guard 60 20,000

3 Water Tanker 10,000

4 Maintains &

security

10,000

Total 60,000

25,000

4 Occupation health 20,000/- 10,000 5 Miscellaneous (Fencing, etc.) 35,000/- 15,000 Total 1.15,000 0.85,000

12 Green Belt/ Plantation 0.60 Lac

Places of Plantation:- About 60 saplings will be planted in an area of 0.06 ha (33% of applied area)

upto the end of 5years,About 60 sapling will be planted out side the lease boundary at Govt. Secondary

School Matabar Makrana..

Year Along the lease

boundary

On Backfilled

area

Outside the

lease area

Top Soil Dumps Total

Area No. of Area No. of Area No. of Area No. of Area No. of

Final minutes of 4.95th meeting held on 27-29 July, 2021

(Ha.) Trees (Ha.) Trees (Ha.) Trees (Ha.) Trees (Ha.) Trees

2021-22 -- -- -- -- 0.012 12 -- -- 0.012 12

2022-23 -- -- -- -- 0.012 12

-- -- 0.012 12

2023-24 -- -- -- -- 0.012 12

-- -- 0.012 12

2024-25 -- -- -- -- 0.012 12 0.012 12

2025-26 -- -- -- --

0.012 12

0.012 12

Total -- -- -- --

0.060 60

-- - 0.060 60

As per Office Memorandum 16.01.2020: Commitment by PP The mining lease holders shall after ceasing mining operations, undertake re-grassing the mining area and any other area which may have been disturbed due to their mining activates and restore the land to a condition which is for growth of fodder, Flora, Fauna etc.”

13 Budgetary Breakup For Labor Labor Welfare Capital Cost is 0.60 Lac, and

Recurring Cost is 0.30 lac.

S. No. Facility Provided for Laborers Capital Cost in RS. Recurring Cost In

RS. Per Year

1. Drinking water provided by Tanker 20,000/- 10,000/-

2. First Aid Box 5,000/- 2,000/-

3. Rest Shelter 8,000/- 4,000/-

4. Washroom Facilities for laborers 12,000/- 6,000/-

5 Safety Shoes, hand gloves, Dust mask, Ear plugs,

Helmet 10,000/- 8,000/-

6 Insurance 5,000/- --

Total 60,000/- 30,000/-

Observations of the committee:-

The SEAC considered/examined the project proposal on 29.07.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for Environmental Clearance for Marble Mineral Mining

Project, Q.L. No.- 96/A, Area-0.0574 ha, Production Capacity- 2200 TPA at Khasra No.-

702, Near Village- Ullodi Range, Tehsil- Makrana, Distt.- Nagaur, (Raj.)(Proposal No.-

141385).The project is covered under B2 category. The ME, Makrana has granted LOI for

mineral on 10.08.2017 and 27.07.2021 (amendment order). The mining scheme has been

approved by the SME, Ajmer vide letter dated 14.09.2017. ME, Makrana in his certificate

dated 11.09.2020 has stated that the mining lease does not fall in Aravalli hills. DCF, Nagaur

in his certificate dated 31.01.2020 has stated that there is no Wildlife Sanctuary/National

Park/ Conservation Reserve within 10 km periphery of the mine. The project does not involve

approval/ clearance under the Forest (Conservation) Act, 1980 and Wild Life Protection Act,

1972 as no forest land is involved and neither there is any Wild Life Sanctuary/ National Park

within 10 Km from the project site.

The SEAC considered the certificate dated 11.09.2020 issued by ME, Makrana. In the

certificate, it is stated that as per the MoEF & CC notification, dated 01.07.2016 there is no

other mining lease within the periphery of 500 meter and therefore, there is no cluster

formation.

Final minutes of 4.95th meeting held on 27-29 July, 2021

Resolution:

The SEAC upon appraisal of the project in the light of information contained in Form-

1,Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, the members resolved to recommend to SEIAA for grant of EC to

M/s Mainudeen and Brothers Makrana for Marble Mineral Mining Project, Q.L. No.- 96/A,

Area- 0.0574 ha, Production Capacity- 2200 TPA at Khasra No.- 702, Near Village- Ullodi

Range, Tehsil- Makrana, Distt.- Nagaur, (Raj.).(Proposal No.-141385), with the stipulation

that the PP shall abide by the annual production scheduled specified in mining plan and that

any deviation there in will render the PP liable for legal action in accordance with

Environment and Mining Laws, with the specific and general conditions annexed at

Annexure ‘A’. Name of Proponent- M/s Mainudeen and Brothers Makrana, Add.- Village-

Makrana, Tehsil- Makrana, Distt.- Nagaur, (Raj.)Email – [email protected],

Consultant Name:- M/s. N.S. Envro- Tech Laboratories & Consultant, Add.- Corpo

OFFICE Add Plot No. 69/318, V.T. Road Chouraha, Madhyam Marg, Mansarovar, Jaipur

(Raj.). Email:[email protected], [email protected]

Final minutes of 4.95th meeting held on 27-29 July, 2021

Additional Agenda:

S.No File

No

Subject Project Proponent Name & Consultant

Name

1. 18978 Environmental Clearance for Mining

Project of Red Ochre, M.L No.

26/2018, Ref. No.2018100001233,

Mine area 2.0184 ha., production

capacity 1,57,895 TPA (ROM)

{Saleable 1,50,000 TPA and waste

7,895 TPA}, Khasra No. 366 & 367,

Near Village Kesunda, Tehsil-Chotti

Sadri & District- Pratapgrah,

Rajasthan, (Proposal No-188032)

Project Proponent Name- Sh. Bharat

Kumar Anjana S/o Sh. Ram Lal Anjana,

Add-Chotti Sadri, District-Pratapgarh

(Rajasthan), Email-

[email protected].

Consultant Name:- R.K. Consultants,

Add.- 17 E/777, C.H.B, Jodhpur (Raj.)

Email:- [email protected].

2. 19092 Environmental Clearance for

Masonry Stone (Minor Mineral)

Mining Project, Plot No. 93, Area-

1.00 Ha., with Production capacity –

80,100 TPA (ROM) {Saleable

Mineral-72,090 TPA & Waste- 8010

TPA}, Khasra No- 1, at Near village

– Kanwlai, Tehsil– Pushkar,

District– Ajmer (Rajasthan)

(Proposal No.- 195607).

Project Proponent Name:- M/s Pink City

Commercial Pvt. Ltd. Add.- B-219, B-

Scheme, Gopalpura, Bypass, Distt.- Jaipur

(Raj.)

[email protected].

Consultant Name:-VARDAN

ENVIRONET, Add: Plot No.-82-A, Sector-

5, IMT Manesar, Gurgaon-

122003(Haryana).email:-

[email protected].

3. 19091 Environmental Clearance for

Masonry Stone (Minor Mineral)

Mining Project, Plot No. 94, Area-

1.00 Ha., Production capacity -

78,300 TPA (ROM) {Saleable

Mineral- 70,470 TPA & Waste-

7830 TPA}, Khasra No-1, at Near

village – Kanwlai, Tehsil– Pushkar,

District– Ajmer (Rajasthan).

(Proposal No.- 195667).

Project Proponent Name:- M/s Pink City

Commercial Pvt. Ltd. Add.- B-219, B-

Scheme, Gopalpura, Bypass, Distt.- Jaipur

(Raj.),[email protected].

Consultant Name:- VARDAN

ENVIRONET, Add: Plot No.-82-A, Sector-

5, IMT Manesar, Gurgaon-

122003(Haryana).email:-

[email protected].

4. 19088 Environmental Clearance for

Masonry Stone (Minor Mineral)

Mining Project (Plot No.- 86, Area-

1.00 Ha) with Production Capacity-

81000 TPA (ROM) {Saleable

Mineral- 72,900 TPA & Waste-

8100 TPA}, Khasra No- 36/1402, at

Near Vill.- Kanwlai, Tehsil-

Project Proponent Name:- M/s Pink City

Commercial Pvt. Ltd. Add.- B-219, B-

Scheme, Gopalpura, Bypass, Distt.- Jaipur

(Raj.)

[email protected]. Com

Consultant Name:- VARDAN

ENVIRONET

Add: Plot No.-82-A, Sector- 5, IMT

Final minutes of 4.95th meeting held on 27-29 July, 2021

Pushkar, Distt.- Ajmer (Raj.)

(Proposal No.- 195072).

Manesar, Gurgaon-122003 (Haryana).

email:- [email protected].

5. 19107 Environmental Clearance for

Masonry Stone (Minor Mineral)

Mining Project, Plot No. 83, Area-

1.00 Ha., with Production capacity –

58,000 TPA (ROM) {Saleable

Mineral-52,200 TPA & Waste- 5800

TPA}, Khasra No- 36/1402, at Near

village – Kanwlai, Tehsil– Pushkar,

District– Ajmer (Rajasthan)

(Proposal No.- 195311).

Project Proponent Name:- M/s Pink City

Commercial Pvt. Ltd. Add.- B-219, B-

Scheme, Gopalpura, Bypass, Distt.- Jaipur

(Raj.), [email protected].

Consultant Name:- VARDAN

ENVIRONET Add: Plot No.-82-A, Sector-

5, IMT Manesar, Gurgaon-122003

(Haryana).email:-

[email protected].

6. 19089 Environmental Clearance for

Masonry Stone (Minor Mineral)

Mining Project, Plot No.- 84, Area-

1.00 Ha, with Production Capacity-

58,000 TPA (ROM) {Saleable

Mineral- 52,200 TPA & Waste-

5800 TPA}, Khasra No- 36/1402, at

Near Vill.- Kanwlai, Tehsil-

Pushkar, Distt.- Ajmer (Raj.)

(Proposal No.- 194897).

Project Proponent Name:- M/s Pink City

Commercial Pvt. Ltd. Add.- B-219, B-

Scheme, Gopalpura, Bypass, Distt.- Jaipur

(Raj.), [email protected].

Com

Consultant Name:- VARDAN

ENVIRONET Add: Plot No.-82-A, Sector-

5, IMT Manesar, Gurgaon-122003

(Haryana). email:-

[email protected].

7. 15602 Application for expansion in

production capacity from 50,000

TPA - 12,61,730 MTPA of Quartz,

Feldspar, Calcite and inclusion of

Masonry Stone mining project along

with Mineral Grinding Unit/Crusher

at mine lease of 12,61,730 TPA

capacity in total, M.L.- 34/04, Area-

20.0 ha., Khasra no. 1, 3, 47, 49, 56,

34 to 39, 50 to 52 of Village

Atbhigha; Khasra no. 96, 97, 93, 94

of village Chak basdi; Khasra no.

60, 69, 71, 70, 70/471, 67, 68, 66

and 70 of village Chak Khandela;

Khasra no. 65/1, 65/2, 66, 66/170 of

village Khandela basdi and Khasra

no. 2, 11/305 of village Charanwas

at near Village- Atbhigha, Tehsil-

Khandela, District- Sikar, State-

Rajasthan (Proposal no - 75949).

Project Proponent Name:- M/s Reverence

Mines & Minerals Pvt. Ltd., Sh. Anil Gupta,

Director and Authorized Signatory Sh. Inder

Kumar, Add-A-28, Anita Colony, Bajaj

Nagar, Jaipur, E-Mail-

[email protected]

Consultant Name:- TEAM Institute of

Science & Technology Pvt. Ltd.,E-

65,Chitranjan marg, C-Scheme, Jaipur.

Final minutes of 4.95th meeting held on 27-29 July, 2021

Additional Agenda no. 01. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. B2 (18978)/

2019-20

Project Name: - Environmental Clearance for Mining Project of Red Ochre, M.L No.

26/2018, Ref. No.2018100001233, Mine area 2.0184 ha., production capacity 1,57,895 TPA

(ROM) {Saleable 1,50,000 TPA and waste 7,895 TPA}, Khasra No. 366 & 367, Near Village

Kesunda, Tehsil-Chotti Sadri & District- Pratapgrah, Rajasthan, (Proposal No-188032)

Project Proponent Name- Sh. Bharat Kumar Anjana S/o Sh. Ram Lal Anjana, Add-Chotti

Sadri, District-Pratapgarh (Rajasthan), [email protected].

Consultant Name:- R.K. Consultants, Add.- 17 E/777, C.H.B, Jodhpur (Raj.) Email:-

[email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category / Item no.

(in Schedule):

1(a) B2

S.No. in Agenda- 66

2. Location of Project Village –Kesunda Tehsil–Chotti Sadri

District– Pratapgarh(Raj.) Latitude&Longitude

S.No. Latitude Longitude

A 24027’43.5335” 74048’33.3541”

B 24027’43.6055” 74048’32.7442”

C 24027’48.7981” 74048’33.4171”

D 24027’51.2209” 74048’32.2892”

E 24027’51.2858” 74048’34.2417”

F 24027’50.4638” 74048’36.1746”

G 24027’48.4488” 74048’38.5418”

H 24027’47.4217” 74048’36.5238”

I 24027’45.3519” 74048’35.1151”

3. Project Details

Lease No. /Production

capacity

Ref. No. 2018100001233, ML No. 26/2018

Khasra No. 366 & 367, Area-2.0184Hect.

Production –157895 TPA ROM Red Ocher

{(95% Saleable Mineral= 150000 TPA & 5% Mineral Waste-= 7895 TPA)}

(Mentioned on Page no-1 of FORM-1)

4. Project Cost: Rs. 70.0Lacs

5. Water Requirement

& Source

Total water requirement is about 2-3KLD

6. Fuel &Energy: - Only diesel will be required to run vehicles for transportation. No electricity will be needed in

the proposed project.

Final minutes of 4.95th meeting held on 27-29 July, 2021

7. Reference No. &

Date & documents

submitted: -

Ref. No. Nil&NA

Documents- Form-1, PFR & Approved mining plan with Annexure

8. Information about

Aravalli Certificate.

Area is not falling in Aravalli Hill Ranges issued by DMGPratapgarh vide letter

No.ME/Pratap/CC-Minor/ML/26/2018/2020-21/7650 dated 03.12.2020 (Letter enclosed with Checklist.)

9 Date of Air/Water/ Noise Monitoring

05.11.2020 (Test Reports enclosed with Checklist.)

10 Information about

500 mts composite map

Total lease area within 500 mts is 2.0184 hect. issued by DMG, Pratapgarhvide letter no.

ME/Pratap/CC-Minor/ML/26/2018/2020-21/7649 dated 03.12.2021 & Cluster map vide map no. ME/PRG/DRG/96 dated 02.12.2021

(Cluster Map& Certificate enclosed with Checklist.)

11 Environment Management Plan

Expenditure of EMP Rs3,00,000/-

S.No. Particulars Amount (in Rs./Year)

1. Pollution Control Air (water sprinkling for dust suppression) 40000/-

2. Pollution Monitoring

a. Air sampling stations & analysis b. Water Quality Analysis

c. Noise & Vibration Monitoring d. Soil Quality Analysis

60000/-

3. Greenbelt development (Tree Guards, Re-sapling Plantation & Its

Maintenance etc.) 70000/-

4 Progressive reclamation of Mine Pit 50000/-

5 Maintenance of approach Road 50000/-

6 Occupational Health & Safety 30000/-

TOTAL 3,00,000/-

12 CSR /ESR Activates

Expenditure of CSR Rs1,00,000/-

13 Green Belt/ Plantation

Expenditure of Green Belt Rs. 70,000/-

Year Peripheral area outside Area Total Type of plants

Area (Ha.) Trees Area (Ha.)

Trees Area (Ha.)

Trees Neem, Flower, Gulmohor, Kanjari, Lemonand similar type of species which can grow easily in this area.

Ist year 0.2231 220 - - 0.2231 220

IInd year 0.2 200 - - 0.2 200

IIIrd year - - 0.1369 135 0.1369 135

IVth year - - 0.1 100 0.1 100 Total 0.4231 420 0.2369 235 0.66 655

Note:-As per O.M. dated 16.01.2020 “The Mining Lease holders shall, after ceasing mining operations, undertake

re-grassing the mining area and any other area which may have been disturbed due to their mining activities and

restore the land to a condition which is fit for growth of fodder, flora, fauna etc.”

Total 0.66-hectare area will be covered under the plantation in which 0.4231 ha will be done on Boundary Barrier &

0.2369 ha will be done on Outside the Applied area within own land khasra No. no. 367.

Final minutes of 4.95th meeting held on 27-29 July, 2021

14 Budgetary

Breakup for

Labour

Expenditure of Labor Rs60,000/-

Particulars Total Expenditure as proposed by Project

Proponent

Rest Shelters Rs. 10,000/-

Medical aid for the laborers and their families Rs. 10000/-

Provision of Drinking water Rs. 6500/-

Provision for clean sanitation for laborers and their families Rs. 8000/-

Provision for Educational facilities for children etc. Rs. 8000/-

Fuel for cooking Rs. 8500/-

Creche Rs. 4000/-

Recreation Rs. 5000/-

Total Rs. 60,000/-

15 Present Status: - Fresh LOI Area

Brief details of the project:-

The SEAC considered/examined the project proposal on 29.04.2021 by way of VC in

accordance with letter dated 27.05.2020 of SEIAA, Rajasthan in the presence of PP and his

Consultant.

The PP has submitted application for Environmental Clearance for Mining Project of

Red Ochre, M.L No. 26/2018, Ref. No.2018100001233, Mine area 2.0184 ha., production

capacity 1,57,895 TPA (ROM) {Saleable 1,50,000 TPA and waste 7,895 TPA}, Khasra No.

366 & 367, Near Village Kesunda, Tehsil- Chotti Sadri & District- Pratapgrah, Rajasthan,

(Proposal No-188032).

The project is covered under B2 category. The ADM, Udaipur vide order dated

21.09.2020 has issued LoI to the PP for mining of Red Ochre. The mining plan has been

approved by the SME, Udaipur vide letter dated 27.10.2020. ME, Pratapgarh in his certificate

dated 03.12.2020 has stated that the mining lease does not fall in Aravalli hills.

As per cluster certificate dated 03.12.2020 issued by ME, Pratapgarh, the total area of

all the mining leases in the cluster is 2.0184 ha.

DCF (WL), Chittorgarh in his certificate dated 26.11.2020 has stated that Sitamata

WLS is at distance of 22.0 Km from the proposed lease area from the applied lease area. The

PP in form 1 has stated that the boundary of the State of MP is at a distance of 1.10 Km from

the applied lease area.

Since the 10 km distance from the applied lease area extends to MP state also, the

SEAC asked the PP to submit certificate from competent authority of the forest department of

Final minutes of 4.95th meeting held on 27-29 July, 2021

the State of Mdhya Pradesh, regarding existence or otherwise of National Park or Wildlife

Sanctuary within 10 km from the applied lease area within a period of 45 days failing which

the proposal shall be recommended to SEIAA for closure & delistment.

Observations and Resolution of the committee:-

The PP, in response to the query made by SEAC vide letter dated 30.06.2021, has

submitted reply vide letter dated nil received on 20.07.2021. The SEAC in its 4.95th meeting

held on 27-29 July, 2021 went through the reply. The PP incompliance of the query has

submitted letter of DCF (WL), Chittorgarh in his certificate dated 26.11.2020 has stated that

Sitamata WLS is at distance of 22.0 Km from the proposed lease area from the applied lease

area. The PP in form 1 has stated that the boundary of the State of MP is at a distance of 1.10

Km from the applied lease area.

The PP has also submitted copy of letter written by Up Van Mandal Adhikari, Up Van

Mandal, Neemuch to Van Mandal Adhikari, Van Mandal, Neemuch dated 09.07.2021, which

stated that there is no National Park/ Wildlife Sanctuary within 10 Km from the applied lease

area and nearest forest block Kasbi is at about 13.25 Kms.

The SEAC upon appraisal of the project in the light of information contained in Form-

1, Form-2, Pre-feasibility report and other documents and having regard to the submissions

made during presentation, the members resolved to recommend to SEIAA for grant of EC to

Shri Bharat Kumar Anjana S/o Sh. Ram Lal Anjana, for Mining Project of Red Ochre, M.L

No. 26/2018, Ref. No.2018100001233, Mine area 2.0184 ha., production capacity 1,57,895

TPA (ROM) {Saleable 1,50,000 TPA and waste 7,895 TPA}, Khasra No. 366 & 367, Near

Village Kesunda, Tehsil-Chotti Sadri & District- Pratapgrah, Rajasthan, (Proposal No-

188032), with the stipulation that the PP shall abide by the annual production scheduled

specified in mining plan and that any deviation there in will render the PP liable for legal

action in accordance with Environment and Mining Laws, with the specific and general

conditions annexed at Annexure ‘A’. Project Name: - Environmental Clearance for Mining

Project of Red Ochre, M.L No. 26/2018, Ref. No.2018100001233, Mine area 2.0184 ha.,

production capacity 1,57,895 TPA (ROM) {Saleable 1,50,000 TPA and waste 7,895 TPA},

Khasra No. 366 & 367, Near Village Kesunda, Tehsil-Chotti Sadri & District- Pratapgrah,

Rajasthan, (Proposal No-188032), Project Proponent Name- Sh. Bharat Kumar Anjana S/o

Sh. Ram Lal Anjana, Add-Chotti Sadri, District-Pratapgarh (Rajasthan), Email-

[email protected].

Additional Agenda no. 02. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat.1(a)

B2(19092)/ 2019-20

Project Name:- Environmental Clearance for Masonry Stone (Minor Mineral) Mining

Project, Plot No. 93, Area- 1.00 Ha., with Production capacity – 80,100 TPA (ROM)

{Saleable Mineral-72,090 TPA & Waste- 8010 TPA}, Khasra No- 1, at Near village –

Kanwlai, Tehsil– Pushkar, District– Ajmer (Rajasthan) (Proposal No.- 195607).

Project Proponent Name:- M/s Pink City Commercial Pvt. Ltd. Add.- B-219, B-Scheme,

Gopalpura, Bypass, Distt.- Jaipur (Raj.)

[email protected].

Final minutes of 4.95th meeting held on 27-29 July, 2021

Consultant Name:-VARDAN ENVIRONET, Add: Plot No.-82-A, Sector- 5, IMT Manesar,

Gurgaon-122003(Haryana).email:- [email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category / Item no.(in Schedule): B-2/1(a)

2. Location of Project Near village – Kanwlai, Tehsil– Pushkar, District–

Ajmer(Rajasthan)

3. Project Details

M.L. No. /Production capacity

Masonry Stone (Minor Mineral) Mining Project” (Plot No.

93, Area- 1.00 Ha.) with Production capacity -80100 TPA

(ROM) {Saleable Mineral-72090 TPA & Waste-8010 TPA}

at Near village – Kanwlai, Tehsil– Pushkar, District– Ajmer

(Rajasthan) by M/s Pink City Commercial Pvt. Ltd.

Khasra No- 01

4. Project Cost Rs50 Lakhs

5. Water Requirement

& Source

2.5 KLD (Tanker Water Supply from nearby village)

6. Fuel & Energy 180 Litres/day HSD Fuel will be required for mine

machineries.

7. Application No. & Date &

documents submitted

Proposal No. - SIA/RJ/MIN/195607/2021 dated 4.02.21

8 Information about Aravalli

Certificate

ME/AJ/COMPOSIT/MACHI/ ARAVALLI PRA-/35 Dated

22/01/2021

Date of Air/Water/Noise

Monitoring

Environment Monitoring was carried out by NABL

approved laboratory.

9 Information about Topo-sheet

map

45 J 10

Environment Sensitivity:-

1 Nearest Village Kanwlai (~1.1 km in SW direction)

2 Nearest Railway Station Makarwadi Halt Railway station (~7.7 Km, SE direction)

3 Nearest Airport Kishangarh Airport, Ajmer (~22.8 Km, E direction)

4 Nearest National / State

Highway

N.H.89 is ~ 9.7 km ,in SW direction.

N.H.8 is ~ 14.9 km ,in SE direction.

S.H.60 is 13.8 km ,in W direction.

S.H.59 is ~ 14.5km ,in NW direction.

5 Archaeological Important

Place

No any Archaeological Important Place found within 15

km distance from the periphery of lease area.

6 Ecological Sensitive Park,

Wildlife Sanctuary, Reserve

etc.

No any Ecological Sensitive Park, Wildlife Sanctuary,

Reserve etc. found within 15 km distance from the

periphery of lease area.

7 Nearest River / water body SaraswatiNadi is ~ 1.6 km, in S direction.

NaharNadi is ~ 6.3 km, in SE direction.

PhulSagar is ~ 10.8 km, in SE direction.

Ana sagar is ~ 13.9 km, in S direction

Pushkar Lake is ~ 13.6 km, in S direction.

KansiyaBala is ~ 4.2 km, in NW direction.

PalriNadi is ~ 14.3 km, in N direction.

8 Reserved/Protected Forests PadampurDungar P.F is ~3.7 km ,in SE direction.

KarelGhati P.F. is ~1.0 km in W direction MakarwaliHokran R.F is ~7.2 km in SE direction.

DuletGhati R. F. is ~7.3 km ,in SW direction

Mahavir R.F is ~12.3 km ,in SE direction.

Final minutes of 4.95th meeting held on 27-29 July, 2021

Manpur Ki Dhani R.F is ~ 14.2 km ,in E direction.

Pilwa R.F. is ~ 9.1 km ,in N direction

Ghinwali P.F is ~ 12.6 km ,in N direction.

10 Environment Management Plan

S.No. PARTICULAR

CAPITAL

COST

(IN RS.)

RECURRING

COST

(IN RS./YEAR)

1 Water sprinkle facility on haul roads to

prevent dust suppression. - 25,000/-

2 Maintenance of approach road - 80,000/-

3 Pollution Monitoring of Ambient Air, Noise,

Water & Soil Quality - 30,000

4 Plantation/Green Belt & maintenance 3,50,000/- 90,000

5 Wire fence around mining pits 1,00,000/- 10,000/-

6 Occupational health check-up in a year - 45,000/-

7 Provision of PPES (helmet shoes gloves

goggles etc.) - 15,000/-

9 Emergency rescue fire fightingequipments

and first aid 30,000/- 30,000/-

10 Caution board (will illustrate lease detail and

name of the PHC and contact no. of doctor) 20,000/- 15,000

11 Solar pole with LED light @ 8000/- Per Light 50,000/- 10,000/-

TOTAL 5,50,000/- 3,50,000/-

12 Green Belt/ Plantation

Year (Outside the lease area in Khasra

No. 124/1617, 39 & 99 of village Kanwlai, Tehsil Pushkar, District-Ajmer)

(Outside haul roads)

Top Soil Dumps Total

Area (Ha.) No. of Trees

Area (Ha.

No. Of Trees

Area (Ha.)

No. Of Trees

Area (Ha.) No. Of Trees

Existing - - - - - - 0.11 110

I 0.11 110 - - - - 0.11 110

II 0.11 110 - - - - 0.11 110

III 0.11 110 - - - -

IV Maintenance - - - - Maintenance

V

Total 0.33 330 0.33 330

Annual expenditure: Rs 90,000/- Total 330 saplings will be planted in upcoming 3 years and Area for

plantation is 0.33 Ha will be done outside the lease area in Khasra no. 124/1617, 39 & 99 of village

Kanwlai, Tehsil Pushkar, District-Ajmer

The mining lease holders shall, after ceasing mining operations, undertake re-grassing the mining area

and any other area which may have been disturbed due to their mining activities and restore the land to a

condition which is fit for growth of fodder, flora, fauna etc. as per MoEF& CC O.M. dated 16.01.20

13 Budgetary Breakup for Labour

Sr. No. Description

Capital

Cost

(in Rs.)

Recurring Cost

(in Rs./Yr.)

1 Rest Shelter 45,000 2,000

2 Drinking water facility 10,000 5,000

3 Toilet Facility (2 units for Male &

Female) 10,000 5,000

4 Fuel for cooking - 8,000

5 Medical facility for labors - 15,000

Final minutes of 4.95th meeting held on 27-29 July, 2021

Total 65,000 35,000

14 Present Status New Mining lease

Brief details of the project:-

The SEAC considered/examined the project proposal submitted by the PP and also the

presentation made by him through VC/Electronic media in accordance with letter dated

27.05.2020 of SEIAA, Rajasthan.

The PP has submitted application for Environmental Clearance for Masonry Stone

(Minor Mineral) Mining Project, Plot No. 93, Area- 1.00 Ha., with Production capacity –

80,100 TPA (ROM) {Saleable Mineral-72,090 TPA & Waste- 8010 TPA}, Khasra No- 1, at

Near village – Kanwlai, Tehsil– Pushkar, District– Ajmer (Rajasthan) (Proposal No.-

195607). The project is covered under B2 category. The SME, Ajmer vide order dated

18.12.2020 has issued LoI to the PP for mining of Masonry Stone (Cheja Patther). The

mining plan has been approved by the SME, Ajmer vide letter dated 21.01.2021. ME, Ajmer

in his certificate dated 22.01.2021 has stated that the mining lease does not fall in Aravalli

hills.

According to the certificate dated 22.01.2021, issued by ME, Ajmer, there is no

cluster formation in terms of notification dated 15.01.2016 and 01.07.2016 of the MoEF &

CC.

The PP has not submitted certificate from the concerned DCF regarding existence or

otherwise of National Park or Wildlife Sanctuary from the applied lease area. The SEAC,

therefore, decided to ask the PP to submit the same within a period of 45 days failing which

the project shall be recommended to SEIAA for closure and delistment.

Observations and Resolutions of the Committee:

The PP, in response to the query made by SEAC vide letter dated 30.06.2021, has

submitted reply vide letter dated 30.06.2021. The SEAC, in its 4.95th meeting held on 27-29

July, 2021 went through the reply. Incompliance of the query the PP has submitted copy of

certificate dated 27.05.2021 of DCF, Ajmer stating that there is no National Park/ Wildlife

Sanctuary within 10 Km from plot no. 82, 83, 84, 86, 86, 88, 90, 91, 92, 93, 94 (total 11

plots) (LOI).

Keeping in view the information contained in the documents submitted by the PP and

presentation made by him before the SEAC and after detailed deliberations, the members

resolved to recommend to SEIAA for the grant of EC to M/s Pink City Commercial Pvt. Ltd.

for Masonry Stone (Minor Mineral) Mining Project, Plot No. 93, Area- 1.00 Ha., with

Production capacity – 80,100 TPA (ROM) {Saleable Mineral-72,090 TPA & Waste- 8010

TPA}, Khasra No- 1, at Near village – Kanwlai, Tehsil– Pushkar, District– Ajmer

(Rajasthan) (Proposal No.- 195607), with the stipulation that the PP shall abide by the annual

production scheduled specified in mining plan and that any deviation there in will render the

PP liable for legal action in accordance with Environment and Mining Laws, with the specific

and general conditions annexed at Annexure ‘A’. Project Name:- Environmental Clearance

for Masonry Stone (Minor Mineral) Mining Project, Plot No. 93, Area- 1.00 Ha., with

Production capacity – 80,100 TPA (ROM) {Saleable Mineral-72,090 TPA & Waste- 8010

Final minutes of 4.95th meeting held on 27-29 July, 2021

TPA}, Khasra No- 1, at Near village – Kanwlai, Tehsil– Pushkar, District– Ajmer

(Rajasthan) (Proposal No.- 195607), Project Proponent Name:- M/s Pink City Commercial

Pvt. Ltd. Add.- B-219, B-Scheme, Gopalpura, Bypass, Distt.- Jaipur (Raj.) Email-

[email protected], Consultant:- VARDAN ENVIRONET Add: Plot No.-82-A,

Sector- 5, IMT Manesar, Gurgaon-122003 (Haryana). email:- [email protected].

Additional Agenda no. 03. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat.

1(a)B2(19091)/ 2019-20

Project Name:- Environmental Clearance for Masonry Stone (Minor Mineral) Mining

Project, Plot No. 94, Area- 1.00 Ha., Production capacity -78,300 TPA (ROM) {Saleable

Mineral- 70,470 TPA & Waste- 7830 TPA}, Khasra No-1, at Near village – Kanwlai, Tehsil–

Pushkar, District– Ajmer (Rajasthan). (Proposal No.- 195667).

Project Proponent Name:- M/s Pink City Commercial Pvt. Ltd. Add.- B-219, B-Scheme,

Gopalpura, Bypass, Distt.- Jaipur (Raj.),[email protected].

Consultant Name:- VARDAN ENVIRONET, Add: Plot No.-82-A, Sector- 5, IMT

Manesar, Gurgaon-122003(Haryana).email:- [email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category / Item no.(in

Schedule):

B-2

2. Location of Project Near village – Kanwlai, Tehsil– Pushkar, District–

Ajmer(Rajasthan)

3. Project Details

M.L. No. /Production capacity

“Masonry Stone (Minor Mineral) Mining Project” (Plot

No. 94, Area- 1.00 Ha.) with Production capacity -78300

TPA (ROM) { Saleable Mineral-70470 TPA & Waste-

7830 TPA} at Near village – Kanwlai, Tehsil– Pushkar,

District– Ajmer (Rajasthan) by M/s Pink City

Commercial Pvt. Ltd.

Khasra No-1

4. Project Cost Rs50 Lakhs

5. Water Requirement & Source

2.5 KLD (Tanker Water Supply from nearby village)

6. Fuel & Energy 150 Litres/day HSD Fuel will be required for mine

machineries.

7. Application No. & Date & documents submitted

Proposal No. - SIA/RJ/MIN/195667/2021 Dated 02/02/2021

8 Information about Aravalli

Certificate

ME/AJ/COMPOSIT/MACHI/ ARAVALLI PRA-/37

Dated 22/01/2021

Date of Air/Water/Noise Monitoring

Environment Monitoring was carried out by NABL approved laboratory.

9 Information about Topo-sheet

map

45 J 10

Environment Sensitivity:-

1 Nearest Village Kanwlai (~1.1 km in SW direction)

Final minutes of 4.95th meeting held on 27-29 July, 2021

2 Nearest Railway Station Makarwadi Halt Railway station (~7.7 Km, SE direction)

3 Nearest Airport Kishangarh Airport, Ajmer (~22.8 Km, E

direction)

4 Nearest National / State Highway N.H.89 is ~ 9.7 km,in SW direction.

N.H.8 is ~ 14.9 km,in SE direction.

S.H.60 is 13.8 km,in W direction.

S.H.59 is ~ 14.5km,in NW direction.

5 Archaeological Important Place No any Archaeological Important Place within

15 km distance from the periphery of lease area.

6 Ecological Sensitive Park, Wildlife Sanctuary, Reserve etc.

No any Ecological Sensitive Park, Wildlife Sanctuary, Reserve etc.within 15 km distance

from the periphery of lease area.

7 Nearest River / water body SaraswatiNadi is ~ 1.6 km, in S direction.

NaharNadi is ~ 6.3 km, in SE direction. PhulSagar is ~ 10.8 km, in SE direction.

Ana sagar is ~ 13.9 km, in S direction

Pushkar Lake is ~ 13.6 km, in S direction. KansiyaBala is ~ 4.2 km, in NW direction.

PalriNadi is ~ 14.3 km, in N direction.

8 Reserved/Protected Forests Reserved/Protected Forests found within 15

km radius of mine site:

PadampurDungar P.F is ~3.7 km,in SE direction.

KarelGhati P.F. is ~1.0 km in W direction

MakarwaliHokran R.F is ~7.2 km in SE

direction. DuletGhati R. F. is ~7.3 km,in SW direction

Mahavir R.F is ~12.3 km,in SE direction.

Manpur Ki Dhani R.F is ~ 14.2 km,in E direction.

Pilwa R.F. is ~ 9.1 km,in N direction.

Ghinwali P.F is ~ 12.6 km,in N direction.

10 Environment Management Plan

S.No. PARTICULAR

CAPITAL

COST

(IN RS.)

RECURRING

COST

(IN RS./YEAR)

1 Water sprinkle facility on haul roads to

prevent dust suppression. - 25,000/-

2 Maintenance of approach road - 80,000/-

3 Pollution Monitoring of Ambient Air, Noise, Water & Soil Quality

- 30,000

4 Plantation/Green Belt & maintenance 3,50,000/- 90,000

5 Wire fence around mining pits 1,00,000/- 10,000/-

6 Occupational health check-up in a year - 45,000/-

7 Provision of PPES (helmet shoes gloves

goggles etc.) - 15,000/-

9 Emergency rescue fire fighting equipments

and first aid 30,000/- 30,000/-

10

Caution board (will illustrate lease detail

and name of the PHC and contact no. of

doctor)

20,000/- 15,000

11 Solar pole with LED light @ 8000/- Per 50,000/- 10,000/-

Final minutes of 4.95th meeting held on 27-29 July, 2021

Light

TOTAL 5,50,000/- 3,50,000/-

12 Green Belt/ Plantation Year (Outside the lease area in

Khasra No. 124/1617, 39 & 99 of village Kanwlai, Tehsil Pushkar, District-Ajmer)

(Outside haul roads)

Top Soil Dumps Total

Area (Ha.) No. of Trees

Area (Ha.

No. Of Trees

Area (Ha.)

No. Of Trees

Area (Ha.)

No. Of Trees

Existing - - - - - - 0.11 110

I 0.11 110 - - - - 0.11 110

II 0.11 110 - - - - 0.11 110

III 0.11 110 - - - -

IV Maintenance - - - - Maintenance

V Total 0.33 330 0.33 330

Annual expenditure: Rs 90,000/- Total 330 saplings will be planted in upcoming 3 years and Area for

plantation is 0.33 Ha will be done outside the lease area in Khasra no. 124/1617, 39 & 99 of village

Kanwlai, Tehsil Pushkar, District-Ajmer

The mining lease holders shall, after ceasing mining operations, undertake re-grassing the mining area

and any other area which may have been disturbed due to their mining activities and restore the land to a

condition which is fit for growth of fodder, flora, fauna etc. as per MoEF& CC O.M. dated 16.01.20

13 Budgetary Breakup for Labour

Sr. No. Description Capital Cost

(in Rs.)

Recurring Cost

(in Rs./Yr.)

1 Rest Shelter 45,000 2,000

2 Drinking water facility 10,000 5,000

3 Toilet Facility (2 units for Male &

Female) 10,000 5,000

4 Fuel for cooking - 8,000

5 Medical facility for labors - 15,000

Total 65,000 35,000

14 Present Status New Mining lease

Brief details of the project:-

The SEAC considered/examined the project proposal submitted by the PP and also the

presentation made by him through VC/Electronic media in accordance with letter dated

27.05.2020 of SEIAA, Rajasthan.

The PP has submitted application for Masonry Stone (Minor Mineral) Mining Project, Plot

No. 94, Area- 1.00 Ha., Production capacity -78,300 TPA (ROM) {Saleable Mineral- 70,470

TPA & Waste- 7830 TPA}, Khasra No-1, at Near village – Kanwlai, Tehsil– Pushkar,

District– Ajmer (Rajasthan). (Proposal No.- 195667). The project is covered under B2

category. The SME, Ajmer vide order dated 18.12.2020 has issued LoI to the PP for mining

of Masonry Stone (Cheja Patther). The mining plan has been approved by the SME, Ajmer

vide letter dated 21.01.2021. ME, Ajmer in his certificate dated 22.01.2021 has stated that the

mining lease does not fall in Aravalli hills.

According to the certificate dated 22.01.2021, issued by ME, Ajmer, there is no

cluster formation in terms of notification dated 15.01.2016 and 01.07.2016 of the MoEF &

CC.

Final minutes of 4.95th meeting held on 27-29 July, 2021

The PP has not submitted certificate from the concerned DCF regarding existence or

otherwise of National Park or Wildlife Sanctuary from the applied lease area. The SEAC,

therefore, decided to ask the PP to submit the same within a period of 45 days failing which

the project shall be recommended to SEIAA for closure and delistment.

Observations and Resolutions of the Committee:

The PP, in response to the query made by SEAC vide letter dated 30.06.2021, has

submitted reply vide letter dated 30.06.2021. The SEAC, in its 4.95th meeting held on 27-29

July, 2021 went through the reply. Incompliance of the query the PP has submitted copy of

certificate dated 27.05.2021 of DCF, Ajmer stating that there is no National Park/ Wildlife

Sanctuary within 10 Km from plot no. 82, 83, 84, 86, 86, 88, 90, 91, 92, 93, 94 (total 11

plots) (LOI).

Keeping in view the information contained in the documents submitted by the PP and

presentation made by him before the SEAC and after detailed deliberations, the members

resolved to recommend to SEIAA for the grant of EC to M/s Pink City Commercial Pvt. Ltd.

for Masonry Stone (Minor Mineral) Mining Project, Plot No. 94, Area- 1.00 Ha., Production

capacity -78,300 TPA (ROM) {Saleable Mineral- 70,470 TPA & Waste- 7830 TPA}, Khasra

No-1, at Near village – Kanwlai, Tehsil– Pushkar, District– Ajmer (Rajasthan). (Proposal

No.- 195667), with the stipulation that the PP shall abide by the annual production scheduled

specified in mining plan and that any deviation there in will render the PP liable for legal

action in accordance with Environment and Mining Laws, with the specific and general

conditions annexed at Annexure ‘A’. Project Name:- Environmental Clearance for Masonry

Stone (Minor Mineral) Mining Project, Plot No. 94, Area- 1.00 Ha., Production capacity -

78,300 TPA (ROM) {Saleable Mineral- 70,470 TPA & Waste- 7830 TPA}, Khasra No-1, at

Near village – Kanwlai, Tehsil– Pushkar, District– Ajmer (Rajasthan). (Proposal No.-

195667). Project Proponent Name:- M/s Pink City Commercial Pvt. Ltd. Add.- B-219, B-

Scheme, Gopalpura, Bypass, Distt.- Jaipur (Raj.),[email protected].

Consultant Name:- VARDAN ENVIRONET, Add: Plot No.-82-A, Sector- 5, IMT Manesar,

Gurgaon-122003(Haryana).email:- [email protected].

Additional Agenda no. 04. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat.

1(a)B2(19088)/ 2019-20

Project Name:- Environmental Clearance for Masonry Stone (Minor Mineral) Mining

Project (Plot No.- 86, Area- 1.00 Ha) with Production Capacity- 81000 TPA (ROM)

{Saleable Mineral- 72,900 TPA & Waste- 8100 TPA}, Khasra No- 36/1402, at Near Vill.-

Kanwlai, Tehsil- Pushkar, Distt.- Ajmer (Raj.) (Proposal No.- 195072).

Project Proponent Name:- M/s Pink City Commercial Pvt. Ltd. Add.- B-219, B-Scheme,

Gopalpura, Bypass, Distt.- Jaipur (Raj.)

[email protected]. Com

Consultant Name:- VARDAN ENVIRONET

Add: Plot No.-82-A, Sector- 5, IMT Manesar, Gurgaon-122003 (Haryana).

email:- [email protected].

Final minutes of 4.95th meeting held on 27-29 July, 2021

The particulars of the project, in brief, as submitted by the PP are as follows:

1. 1 Category / Item no.(in

Schedule):

1(a)B2

2. 2 Location of Project Near village – Kanwlai, Tehsil– Pushkar, District – Ajmer (Rajasthan)

3. 3 Project Details PlotNo./Area/Production

capacity/Khasra No.

Plot No.-86

Area – 1.0Ha.

Production capacity -81000 TPA (ROM)

[Saleable Mineral-72900 TPA &Waste- 8100 TPA]

Khasra No.-36/1402

4. ` Project Cost Rs. 60Lakhs

5. 5 Water Requirement

& Source

2.5 KLD (Tanker Water Supply from nearby village)

6. 6 Fuel & Energy 150Litres/day HSD Fuel will be required for mine machineries.

7. 7 Application No.& Date &

documents submitted

Hard Copy Submitted to SEIAA, Rajasthan SIA/RAJ/MIN/195072/2021on

dated 28-01-2021

8. 8 Information about Aravalli

Certificate

ME/Aj/Composite/Machi/AravaliPra-/23, dated- 22.01.2021

9. 9 Date of Air/Water/Noise

Monitoring

Environment Monitoring was carried out by NABL approved laboratory.

10. Information about Topo-

sheet map

45 J 10

11. Environment Sensitivity

1 Nearest Village Kanwlai (~0.5 km in South direction)

2 Nearest Railway Station Makarwadi Halt Railway station (~7.5 Km, SE direction)

3 Nearest Airport Kishangarh Airport, Ajmer (~22.9 Km, SE direction)

4 Nearest National / State Highway N.H.89 (~8.9 km, SW)

S.H.60 (~13.1 km, West)

S.H.59 (~14.5km, NW)

N.H.8 (~14.9 km, SE)

5 Archaeological Important Place No any Archaeological Important Place found within 15 km

distance from the periphery of lease area.

6 Ecological Sensitive Park, Wildlife

Sanctuary, Reserve etc.

No any Ecological Sensitive Park, Wildlife Sanctuary, Reserve

etc. found within 15 km distance from the periphery of lease area.

7 Nearest River / water body SaraswatiNadi (~0.6 Km, South)

KansiyaBala (~4.2 km , NW)

NaharNadi (~6.3 km ,SE)

PhulSagar (~10.8 km, SE)

Pushkar Lake (~12.8km ,South)

Anasagar (~13.3 km, South)

PalriNadi (~14.7 km, North)

8 Reserved/Protected Forests KarelGhati P.F. (~0.8 km , West)

PadampurDungar P.F (~3.7 km ,SE) DuletGhati R. F. (~6.5 km , SW)

MakarwaliHokran R.F (~6.9 km ,SE)

Pilwa R.F. (~10.0 km ,North)

Mahavir R.F (~11.6 km ,SE)

Manpur Ki Dhani R.F (~14.5 km ,East)

Ghinwali P.F (~13.6 km ,North)

Final minutes of 4.95th meeting held on 27-29 July, 2021

12. 1 Environment Management Plan

S.No. PARTICULAR CAPITAL COST

(IN RS.)

RECURRING COST

(IN RS./YEAR)

1 Water sprinkle facility on haul roads to prevent dust suppression.

- 25,000/-

2 Maintenance of approach road - 80,000/-

3 Pollution Monitoring of Ambient Air, Noise, Water & Soil Quality

- 30,000

4 Plantation/Green Belt & maintenance 3,50,000/- 90,000

5 Wire fence around mining pits 1,00,000/- 10,000/-

6 Occupational health check-up in a year - 45,000/-

7 Provision of PPES (helmet shoes gloves goggles etc.) - 15,000/-

9 Emergency rescue fire fighting equipments and first aid

30,000/- 30,000/-

10 Caution board (will illustrate lease detail and name of the PHC and contact no. of doctor)

20,000/- 15,000

11 Solar pole with LED light @ 8000/- Per Light 50,000/- 10,000/-

TOTAL 5,50,000/- 3,50,000/-

13. 1 Green Belt/ Plantation

Year (Outside the lease area in Khasra

No. 124/1617, 39 & 99 of village Kanwlai, Tehsil Pushkar, District-Ajmer)

(Outside haul roads)

Top Soil Dumps Total

Area (Ha.) No. of Trees

Area (Ha.

No. Of Trees

Area (Ha.)

No. Of Trees

Area (Ha.) No. Of Trees

Existing - - - - - - 0.11 110

I 0.11 110 - - - - 0.11 110

II 0.11 110 - - - - 0.11 110

III 0.11 110 - - - -

IV Maintenance - - - - Maintenance

V

Total 0.33 330 0.33 330

Annual expenditure: Rs 90,000/- Total 330 saplings will be planted in upcoming 3 years and Area for plantation is 0.33 Ha will be done outside the lease area in Khasra no. 124/1617, 39 & 99 of village Kanwlai, Tehsil Pushkar, District-Ajmer

The mining lease holders shall, after ceasing mining operations, undertake re-grassing the mining area and any other area which may have been disturbed due to their mining activities and restore the land to a condition which is fit for growth of fodder, flora, fauna etc. as per MoEF& CC O.M. dated 16.01.20

14. 1 Budgetary Breakup for Labour Sr. No. Description Capital Cost

(in Rs.) Recurring Cost

(in Rs./Yr.)

1 Rest Shelter 45,000 3,000

2 Drinking water facility 20,000 2,000

3 Toilet Facility (2 units for Male & Female)

10,000 3,000

4 Fuel for cooking - 12,000

5 Medical facility for labors - 15,000

Total 75,000 35,000

15. 1 Present Status

New Mining Project

Brief details of the project:-

The SEAC considered/examined the project proposal submitted by the PP and also the

presentation made by him through VC/Electronic media in accordance with letter dated

27.05.2020 of SEIAA, Rajasthan.

Final minutes of 4.95th meeting held on 27-29 July, 2021

The PP has submitted application for Environmental Clearance for Masonry Stone

(Minor Mineral) Mining Project (Plot No.- 86, Area- 1.00 Ha) with Production Capacity-

81000 TPA (ROM) {Saleable Mineral- 72,900 TPA & Waste- 8100 TPA} Khasra No-

36/1402 at Near Vill.- Kanwlai, Tehsil- Pushkar, Distt.- Ajmer (Raj.) (Proposal No.-

195072). The project is covered under B2 category. The SME, Ajmer vide order dated

18.12.2020 has issued LoI to the PP for mining of Masonry Stone (Cheja Patther). The

mining plan has been approved by the SME, Ajmer vide letter dated 21.01.2021. ME, Ajmer

in his certificate dated 22.01.2021 has stated that the mining lease does not fall in Aravalli

hills.

According to the certificate dated 22.01.2021, issued by ME, Ajmer, there is no cluster

formation within the periphery of 500 meter from the applied lease area in terms of

notification dated 15.01.2016 and 01.07.2016 of the MoEF & CC.

The PP has not submitted certificate from the concerned DCF regarding existence or

otherwise of National Park or Wildlife Sanctuary from the applied lease area. The SEAC,

therefore, decided to ask the PP to submit the same within a period of 45 days failing which

the project shall be recommended to SEIAA for closure and delistment.

Observations and Resolutions of the Committee:

The PP, in response to the query made by SEAC vide letter dated 30.06.2021, has

submitted reply vide letter dated 30.06.2021. The SEAC, in its 4.95th meeting held on 27-29

July, 2021 went through the reply. Incompliance of the query the PP has submitted copy of

certificate dated 27.05.2021 of DCF, Ajmer stating that there is no National Park/ Wildlife

Sanctuary within 10 Km from plot no. 82, 83, 84, 86, 86, 88, 90, 91, 92, 93, 94 (total 11

plots) (LOI).

Keeping in view the information contained in the documents submitted by the PP and

presentation made by him before the SEAC and after detailed deliberations, the members

resolved to recommend to SEIAA for the grant of EC to M/s Pink City Commercial Pvt. Ltd.

for Masonry Stone (Minor Mineral) Mining Project (Plot No.- 86, Area- 1.00 Ha) with

Production Capacity- 81,000 TPA (ROM) {Saleable Mineral- 72,900 TPA & Waste- 8100

TPA}, Khasra No- 36/1402, at Near Vill.- Kanwlai, Tehsil- Pushkar, Distt.- Ajmer (Raj.)

(Proposal No.- 195072), with the stipulation that the PP shall abide by the annual production

scheduled specified in mining plan and that any deviation there in will render the PP liable

for legal action in accordance with Environment and Mining Laws, with the specific and

general conditions annexed at Annexure ‘A’. Project Name:- Environmental Clearance for

Masonry Stone (Minor Mineral) Mining Project (Plot No.- 86, Area- 1.00 Ha) with

Production Capacity- 81000 TPA (ROM) {Saleable Mineral- 72,900 TPA & Waste- 8100

TPA}, Khasra No- 36/1402, at Near Vill.- Kanwlai, Tehsil- Pushkar, Distt.- Ajmer (Raj.)

(Proposal No.- 195072). Project Proponent Name:- M/s Pink City Commercial Pvt. Ltd.

Add.- B-219, B-Scheme, Gopalpura, Bypass, Distt.- Jaipur (Raj.)

[email protected]. Com, Consultant Name:- VARDAN ENVIRONET

Add: Plot No.-82-A, Sector- 5, IMT Manesar, Gurgaon-122003 (Haryana).

email:- [email protected].

Final minutes of 4.95th meeting held on 27-29 July, 2021

Additional Agenda no. 05. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat.

1(a)B2(19107)/ 2019-20

Project Name:- Environmental Clearance for Masonry Stone (Minor Mineral) Mining

Project, Plot No. 83, Area- 1.00 Ha., with Production capacity – 58,000 TPA (ROM)

{Saleable Mineral-52,200 TPA & Waste- 5800 TPA}, Khasra No- 36/1402, at Near village –

Kanwlai, Tehsil– Pushkar, District– Ajmer (Rajasthan) (Proposal No.- 195311).

Project Proponent Name:- M/s Pink City Commercial Pvt. Ltd. Add.- B-219, B-Scheme,

Gopalpura, Bypass, Distt.- Jaipur (Raj.), [email protected].

Consultant Name:- VARDAN ENVIRONET Add: Plot No.-82-A, Sector- 5, IMT Manesar,

Gurgaon-122003 (Haryana).email:- [email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. Category / Item no.(in Schedule): B-2

2. Location of Project Near village – Kanwlai, Tehsil– Pushkar, District– Ajmer(Rajasthan)

3. Project Details

M.L. No. /Production capacity “Masonry Stone (Minor Mineral) Mining Project” (Plot No. 83,

Area- 1.00 Ha.) with Production capacity -58000 TPA (ROM) {

Saleable Mineral-52200 TPA & Waste-5800 TPA} Khasra No-

36/1402, at Near village – Kanwlai, Tehsil– Pushkar, District–

Ajmer (Rajasthan) by M/s Pink City Commercial Pvt. Ltd.

4. Project Cost Rs55 Lakhs

5. Water Requirement

& Source

2.5 KLD (Tanker Water Supply from nearby village)

6. Fuel & Energy 180 Litres/day HSD Fuel will be required for mine machineries.

8 Information about Aravalli

Certificate

ME/Aj./Composite/Machi/Aravali/19, dated-22-01-2021

Date of Air/Water/Noise

Monitoring

Environment Monitoring was carried out by NABL approved

laboratory.

9 Information about Topo-sheet map 45 J 10

Environment Sensitivity:

1 Nearest Village Kanwlai (~0.5 km in S direction)

2 Nearest Railway Station Makarwadi Halt Railway station (~7.4 Km, SE direction)

3 Nearest Airport Kishangarh Airport, Ajmer (~23.11 Km, E direction)

4 Nearest National / State

Highway

N.H.89 is ~ 8.9 km ,in SW direction.

N.H.8 is ~ 14.9 km ,in SE direction.

S.H.60 is ~13.1 km ,in W direction. S.H.59 is ~ 14.5 km ,in NW direction.

5 Archaeological Important Place No any Archaeological Important Place found within 15 km

distance from the periphery of lease area.

6 Ecological Sensitive Park,

Wildlife Sanctuary, Reserve etc.

No any Ecological Sensitive Park, Wildlife Sanctuary,

Reserve etc. found within 15 km distance from the periphery

of lease area.

7 Nearest River / water body SaraswatiNadi is ~ 0.6 km, in S direction.

NaharNadi is ~ 6.3 km, in SE direction.

PhulSagar is ~ 10.8 km, in SE direction.

Ana sagar is ~ 13.3 km, in S direction

Pushkar Lake is ~ 12.8 km, in S direction.

KansiyaBala is ~ 4.2 km, in NW direction.

PalriNadi is ~ 14.7 km, in N direction.

8 Reserved/Protected Forests PadampurDungar P.F is ~3.7 km ,in SE direction.

Final minutes of 4.95th meeting held on 27-29 July, 2021

KarelGhati P.F. is ~0.8 km in W direction

MakarwaliHokran R.F is ~6.9 km in SE direction.

DuletGhati R. F. is ~6.5 km ,in SW direction

Mahavir R.F is ~11.6 km ,in SE direction.

Manpur Ki Dhani R.F is ~ 14.5 km ,in E direction. Pilwa R.F. is ~ 10.0 km ,in N direction

Ghinwali P.F is ~ 13.6 km ,in N direction.

10 Environment Management Plan

S.N

o. PARTICULAR

CAPITAL

COST (IN RS.)

RECURRING

COST (IN RS./YEAR)

1 Water sprinkle facility on haul roads to

prevent dust suppression. - 25,000/-

2 Maintenance of approach road - 80,000/-

3 Pollution Monitoring of Ambient Air,

Noise, Water & Soil Quality - 30,000

4 Plantation/Green Belt & maintenance 3,50,000/- 85,000

5 Wire fence around mining pits 1,00,000/- 10,000/-

6 Occupational health check-up in a year - 45,000/-

7 Provision of PPES (helmet shoes gloves

goggles etc.) - 15,000/-

9 Emergency rescue fire fightingequipments

and first aid 30,000/- 20,000/-

10

Caution board (will illustrate lease detail

and name of the PHC and contact no. of

doctor)

20,000/- 10,000

11 Solar pole with LED light @ 8000/- Per

Light 50,000/- 5,000/-

TOTAL 5,50,000/- 3,25,000/-

12 Green Belt/ Plantation

Year (Outside the lease area in Khasra No. 124/1617, 39 & 99 of village Kanwlai, Tehsil Pushkar, District-Ajmer)

(Outside haul roads)

Top Soil Dumps Total

Area (Ha.) No. of Trees

Area (Ha.

No. Of Trees

Area (Ha.)

No. Of Trees

Area (Ha.)

No. Of Trees

Existing - - - - - - 0.11 110 I 0.11 110 - - - - 0.11 110

II 0.11 110 - - - - 0.11 110

III 0.11 110 - - - -

IV Maintenance - - - - Maintenance

V

Total 0.33 330 0.33 330

Annual expenditure: Rs 85,000/- Total 330 saplings will be planted in upcoming 3 years and Area for

plantation is 0.33 Ha will be done outside the lease area in Khasra no. 124/1617, 39 & 99 of village

Kanwlai, Tehsil Pushkar, District-Ajmer

The mining lease holders shall, after ceasing mining operations, undertake re-grassing the mining area

and any other area which may have been disturbed due to their mining activities and restore the land to a

condition which is fit for growth of fodder, flora, fauna etc. as per MoEF& CC O.M. dated 16.01.20

13 Budgetary Breakup for Labour

Final minutes of 4.95th meeting held on 27-29 July, 2021

Sr.

No.

Description Capital Cost

(in Rs.) Recurring Cost

(in Rs./Yr.)

1 Rest Shelter 40,000 3,000

2 Drinking water facility 15,000 4,000

3 Toilet Facility (2 units for Male &

Female) 15,000 4,000

4 Fuel for cooking - 4,000

5 Medical facility for labors - 15,000

Total 70,000 30,000

14 Present Status New Mining lease

Brief details of the project:-

The SEAC considered/examined the project proposal submitted by the PP and also the

presentation made by him through VC/Electronic media in accordance with letter dated

27.05.2020 of SEIAA, Rajasthan.

The PP has submitted application for Environmental Clearance for Masonry Stone

(Minor Mineral) Mining Project, Plot No. 83, Area- 1.00 Ha., with Production capacity –

58,000 TPA (ROM) {Saleable Mineral-52,200 TPA & Waste- 5800 TPA}, Khasra No-

36/1402, at Near village – Kanwlai, Tehsil– Pushkar, District– Ajmer (Rajasthan) (Proposal

No.- 195311). The project is covered under B2 category. The SME, Ajmer vide order dated

18.12.2020 has issued LoI to the PP for mining of Masonry Stone (Cheja Patther). The

mining plan has been approved by the SME, Ajmer vide letter dated 21.01.2021. ME, Ajmer

in his certificate dated 22.01.2021 has stated that the mining lease does not fall in Aravalli

hills.

According to the certificate dated 22.01.2021, issued by ME, Ajmer, there is no

cluster formation in terms of notification dated 15.01.2016 and 01.07.2016 of the MoEF &

CC.

The PP has not submitted certificate from the concerned DCF regarding existence or

otherwise of National Park or Wildlife Sanctuary from the applied lease area. The SEAC,

therefore, decided to ask the PP to submit the same within a period of 45 days failing which

the project shall be recommended to SEIAA for closure and delistment.

Observations and Resolutions of the Committee:

The PP, in response to the query made by SEAC vide letter dated 30.06.2021, has

submitted reply vide letter dated 30.06.2021. The SEAC, in its 4.95th meeting held on 27-29

July, 2021 went through the reply. Incompliance of the query the PP has submitted copy of

certificate dated 27.05.2021 of DCF, Ajmer stating that there is no National Park/ Wildlife

Sanctuary within 10 Km from plot no. 82, 83, 84, 86, 86, 88, 90, 91, 92, 93, 94 (total 11

plots) (LOI).

Keeping in view the information contained in the documents submitted by the PP and

presentation made by him before the SEAC and after detailed deliberations, the members

resolved to recommend to SEIAA for the grant of EC to M/s Pink City Commercial Pvt. Ltd.

Final minutes of 4.95th meeting held on 27-29 July, 2021

for Masonry Stone (Minor Mineral) Mining Project, Plot No. 83, Area- 1.00 Ha., with

Production capacity – 58,000 TPA (ROM) {Saleable Mineral-52,200 TPA & Waste- 5800

TPA}, Khasra No- 36/1402, at Near village – Kanwlai, Tehsil– Pushkar, District– Ajmer

(Rajasthan) (Proposal No.- 195311), with the stipulation that the PP shall abide by the annual

production scheduled specified in mining plan and that any deviation there in will render the

PP liable for legal action in accordance with Environment and Mining Laws, with the specific

and general conditions annexed at Annexure ‘A’. Project Name:- Environmental Clearance

for Masonry Stone (Minor Mineral) Mining Project, Plot No. 83, Area- 1.00 Ha., with

Production capacity – 58,000 TPA (ROM) {Saleable Mineral-52,200 TPA & Waste- 5800

TPA}, Khasra No- 36/1402, at Near village – Kanwlai, Tehsil– Pushkar, District– Ajmer

(Rajasthan) (Proposal No.- 195311). Project Proponent Name:- M/s Pink City Commercial

Pvt. Ltd. Add.- B-219, B-Scheme, Gopalpura, Bypass, Distt.- Jaipur (Raj.)

[email protected]. Consultant Name:- VARDAN ENVIRONET Add: Plot

No.-82-A, Sector- 5, IMT Manesar, Gurgaon-122003 (Haryana).email:-

[email protected].

Additional Agenda no. 06. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat.

1(a)B2(19089)/ 2019-20

Project Name:- Environmental Clearance for Masonry Stone (Minor Mineral) Mining

Project, Plot No.- 84, Area- 1.00 Ha, with Production Capacity- 58,000 TPA (ROM)

{Saleable Mineral- 52,200 TPA & Waste- 5800 TPA}, Khasra No- 36/1402, at Near Vill.-

Kanwlai, Tehsil- Pushkar, Distt.- Ajmer (Raj.) (Proposal No.- 194897).

Project Proponent Name:- M/s Pink City Commercial Pvt. Ltd. Add.- B-219, B-Scheme,

Gopalpura, Bypass, Distt.- Jaipur (Raj.), [email protected]. Com

Consultant Name:- VARDAN ENVIRONET Add: Plot No.-82-A, Sector- 5, IMT Manesar,

Gurgaon-122003 (Haryana). email:- [email protected].

The particulars of the project, in brief, as submitted by the PP are as follows:

1. 1 Category / Item no.(in Schedule):

1(a)B2

2. 2 Location of Project Near village – Kanwlai, Tehsil– Pushkar, District – Ajmer (Rajasthan)

3. 3 Project Details PlotNo./Area/Production capacity/Khasra No.

Plot No.-84

Area – 1.0Ha.

Production capacity -58000 TPA (ROM) {Saleable- 52200 TPA & Waste- 5800 TPA}

Khasra No.-36/1402

4. 4 Project Cost Rs. 60Lakhs

5. 5 Water Requirement & Source

2.5 KLD (Tanker Water Supply from nearby village)

6. 6 Fuel & Energy

150Litres/day HSD Fuel will be required for mine machineries.

7. 7 Application No.& Date & documents submitted

Hard Copy Submitted to SEIAA, Rajasthan SIA/RAJ/MIN/194897/2021on dated 28-01-2021

8. 8 Information about Aravalli Certificate

ME/Aj/Composite/Machi/AravaliPra-/21, dated- 22.01.2021

9. 9 Date of Air/Water/Noise Monitoring

Environment Monitoring was carried out by NABL approved laboratory.

10. Information about Topo-sheet

map

45 J 10

Final minutes of 4.95th meeting held on 27-29 July, 2021

11. Environment Sensitivity

1 Nearest Village Kanwlai (~0.5 km in South direction)

2 Nearest Railway Station Makarwadi Halt Railway station (~7.5 Km, SE direction)

3 Nearest Airport Kishangarh Airport, Ajmer (~22.9 Km, SE direction)

4 Nearest National / State Highway N.H.89 (~8.9 km, SW) S.H.60 (~13.1 km, West) S.H.59 (~14.5km, NW) N.H.8 (~14.9 km, SE)

5 Archaeological Important Place No any Archaeological Important Place found within 15 km distance from the periphery of lease area.

6 Ecological Sensitive Park, Wildlife

Sanctuary, Reserve etc.

No any Ecological Sensitive Park, Wildlife Sanctuary, Reserve etc.

found within 15 km distance from the periphery of lease area.

7 Nearest River / water body SaraswatiNadi (~0.6 Km, South) KansiyaBala (~4.2 km , NW) NaharNadi (~6.3 km ,SE) PhulSagar (~10.8 km, SE) Pushkar Lake (~12.8km ,South) Anasagar (~13.3 km, South) PalriNadi (~14.7 km, North)

8 Reserved/Protected Forests KarelGhati P.F. (~0.8 km , West) PadampurDungar P.F (~3.7 km ,SE) DuletGhati R. F. (~6.5 km , SW) MakarwaliHokran R.F (~6.9 km ,SE) Pilwa R.F. (~10.0 km ,North) Mahavir R.F (~11.6 km ,SE) Manpur Ki Dhani R.F (~14.5 km ,East) Ghinwali P.F (~13.6 km ,North)

12. 1 Environment Management Plan

S.No. PARTICULAR CAPITAL

COST (IN RS.)

RECURRING

COST (IN RS./YEAR)

1 Water sprinkle facility on haul roads to prevent dust suppression. - 25,000/-

2 Maintenance of approach road - 80,000/-

3 Pollution Monitoring of Ambient Air, Noise, Water & Soil Quality

- 30,000

4 Plantation/Green Belt & maintenance 3,50,000/- 90,000

5 Wire fence around mining pits 1,00,000/- 10,000/-

6 Occupational health check-up in a year - 45,000/-

7 Provision of PPES (helmet shoes gloves goggles etc.) - 15,000/-

9 Emergency rescue fire fighting equipments and first aid 30,000/- 30,000/-

10 Caution board (will illustrate lease detail and name of the PHC and contact no. of doctor)

20,000/- 15,000

11 Solar pole with LED light @ 8000/- Per Light 50,000/- 10,000/-

TOTAL 5,50,000/- 3,50,000/-

13. 1 Green Belt/ Plantation

Year (Outside the lease area in Khasra No. 124/1617, 39 & 99 of village Kanwlai, Tehsil Pushkar, District-

Ajmer)

(Outside haul roads)

Top Soil Dumps Total

Area (Ha.) No. of Trees

Area (Ha.

No. Of Trees

Area (Ha.)

No. Of Trees

Area (Ha.) No. Of Trees

Existing - - - - - - 0.11 110

I 0.11 110 - - - - 0.11 110

II 0.11 110 - - - - 0.11 110

III 0.11 110 - - - -

IV Maintenance - - - - Maintenance

V

Total 0.33 330 0.33 330

Annual expenditure: Rs 90,000/- Total 330 saplings will be planted in upcoming 3 years and Area for plantation is 0.33 Ha

will be done outside the lease area in Khasra no. 124/1617, 39 & 99 of village Kanwlai, Tehsil Pushkar, District-Ajmer

Final minutes of 4.95th meeting held on 27-29 July, 2021

The mining lease holders shall, after ceasing mining operations, undertake re-grassing the mining area and any other area

which may have been disturbed due to their mining activities and restore the land to a condition which is fit for growth of

fodder, flora, fauna etc. as per MoEF& CC O.M. dated 16.01.20 14. 1 Budgetary Breakup for Labour

Sr. No.

Description Capital Cost (in Rs.)

Recurring Cost (in Rs./Yr.)

1 Rest Shelter 45,000 3,000

2 Drinking water facility 20,000 2,000

3 Toilet Facility (2 units for Male & Female)

10,000 3,000

4 Fuel for cooking - 12,000

5 Medical facility for labors

- 15,000

Total 75,000 35,000

15. 1 Present Status

New Mining Project

Brief details of the project:-

The SEAC considered/examined the project proposal submitted by the PP and also the

presentation made by him through VC/Electronic media in accordance with letter dated

27.05.2020 of SEIAA, Rajasthan.

The PP has submitted application for Masonry Stone (Minor Mineral) Mining Project,

Plot No.- 84, Area- 1.00 Ha, with Production Capacity- 58,000 TPA (ROM) {Saleable

Mineral- 52,200 TPA & Waste- 5800 TPA}, Khasra No- 36/1402, at Near Vill.- Kanwlai,

Tehsil- Pushkar, Distt.- Ajmer (Raj.) (Proposal No.- 194897). The project is covered under

B2 category. The SME, Ajmer vide order dated 18.12.2020 has issued LoI to the PP for

mining of Masonry Stone (Cheja Patther). The mining plan has been approved by the SME,

Ajmer vide letter dated 21.01.2021. ME, Ajmer in his certificate dated 22.01.2021 has stated

that the mining lease does not fall in Aravalli hills.

According to the certificate dated 22.01.2021, issued by ME, Ajmer, there is no

cluster formation in terms of notification dated 15.01.2016 and 01.07.2016 of the MoEF &

CC.

The PP has not submitted certificate from the concerned DCF regarding existence or

otherwise of National Park or Wildlife Sanctuary from the applied lease area. The SEAC,

therefore, decided to ask the PP to submit the same within a period of 45 days failing which

the project shall be recommended to SEIAA for closure and delistment.

Observations and Resolutions of the Committee:

The PP, in response to the query made by SEAC vide letter dated 30.06.2021, has

submitted reply vide letter dated 30.06.2021. The SEAC, in its 4.95th meeting held on 27-29

July, 2021 went through the reply. Incompliance of the query the PP has submitted copy of

certificate dated 27.05.2021 of DCF, Ajmer stating that there is no National Park/ Wildlife

Sanctuary within 10 Km from plot no. 82, 83, 84, 86, 86, 88, 90, 91, 92, 93, 94 (total 11

plots) (LOI).

Keeping in view the information contained in the documents submitted by the PP and

presentation made by him before the SEAC and after detailed deliberations, the members

resolved to recommend to SEIAA for the grant of EC to M/s Pink City Commercial Pvt. Ltd.

Final minutes of 4.95th meeting held on 27-29 July, 2021

for Masonry Stone (Minor Mineral) Mining Project, Plot No.- 84, Area- 1.00 Ha, with

Production Capacity- 58,000 TPA (ROM) {Saleable Mineral- 52,200 TPA & Waste- 5800

TPA}, Khasra No- 36/1402, at Near Vill.- Kanwlai, Tehsil- Pushkar, Distt.- Ajmer (Raj.)

(Proposal No.- 194897), with the stipulation that the PP shall abide by the annual production

scheduled specified in mining plan and that any deviation there in will render the PP liable

for legal action in accordance with Environment and Mining Laws, with the specific and

general conditions annexed at Annexure ‘A’. Project Name:- Environmental Clearance for

Masonry Stone (Minor Mineral) Mining Project, Plot No.- 84, Area- 1.00 Ha, with

Production Capacity- 58,000 TPA (ROM) {Saleable Mineral- 52,200 TPA & Waste- 5800

TPA}, Khasra No- 36/1402, at Near Vill.- Kanwlai, Tehsil- Pushkar, Distt.- Ajmer (Raj.)

(Proposal No.- 194897). Project Proponent Name:- M/s Pink City Commercial Pvt. Ltd.

Add.- B-219, B-Scheme, Gopalpura, Bypass, Distt.- Jaipur (Raj.), Email-

[email protected]. Com, Consultant Name:- VARDAN ENVIRONET Add: Plot

No.-82-A, Sector- 5, IMT Manesar, Gurgaon-122003 (Haryana). email:-

[email protected].

Additional Agenda no. 07. File no. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat.

1(a)B2(15602)/ 2019-20

Project Name:- Application for expansion in production capacity from 50,000 TPA -

12,61,730 MTPA of Quartz, Feldspar, Calcite and inclusion of Masonry Stone mining project

along with Mineral Grinding Unit/Crusher at mine lease of 12,61,730 TPA capacity in total,

M.L.- 34/04, Area- 20.0 ha., Khasra no. 1, 3, 47, 49, 56, 34 to 39, 50 to 52 of Village

Atbhigha; Khasra no. 96, 97, 93, 94 of village Chak basdi; Khasra no. 60, 69, 71, 70, 70/471,

67, 68, 66 and 70 of village Chak Khandela; Khasra no. 65/1, 65/2, 66, 66/170 of village

Khandela basdi and Khasra no. 2, 11/305 of village Charanwas at near Village- Atbhigha,

Tehsil- Khandela, District- Sikar, State- Rajasthan (Proposal no - 48618).

Project Proponent Name:- M/s Reverence Mines & Minerals Pvt. Ltd., Sh. Anil Gupta,

Director and Authorized Signatory Sh. Inder Kumar, Add-A-28, Anita Colony, Bajaj Nagar,

Jaipur, [email protected].

Consultant Name:- TEAM Institute of Science & Technology Pvt. Ltd.,E-65,Chitranjan

marg, C-Scheme, Jaipur.

The particulars of the project, in brief, as submitted by the PP are as follows:

1. 1 Category / Item No.

(in Schedule)

Item No.- 1(a)

Category- B-1

2. 2 Location of Project Quartz, Feldspar, Calcite and Masonry Stone Mine Mine (ML No.- 34/04) Near Village-

Athbigha, Tehsil- Khandela, District-Bhilwara, Rajasthan

3. 3 Project Details

M.L. No. /Production

capacity

M. L. No.- 34/04

Area- 20.0 ha

Production of Quartz, Feldspar, Calcite and Masonry Stone - 1261730 TPA

Final minutes of 4.95th meeting held on 27-29 July, 2021

Along with Mineral Grinding Unit/Crusher at mine lease of 1261730 TPA capacity in total

4. Life of Mine Co-terminus with the lease period.

As per approved mining plan LOM is 8 years, but as the reserves will increase, the life of

mine will also increase.

5. 4 Project Cost Rs. 2.0 Crore

6. 5 Water Requirement

& Source

Water Requirement- 8.0 KLD

Source- Water will be sourced from nearby village from the lease area.

Details are available in the submitted report.

7. 6 Fuel & Energy

Electric power will be fulfilled by RSEB.

Fuel is required for the operation of machines mounted compressor, truck/ tipper; this will

be taken care by the contractor.

8. 7 Application No. &

Date & documents

submitted

Application No.- 15602

Final EIA Report Submission Date- 08.01.2020

Documents Submitted- Form-1, EIA/EMP report, Annexures.

9. 8 Information about

Aravalli Certificate.

Date and dispatch No. of Aravalli certificate- ME/Sikar/M.L.20198/33 Dated 31.05.2019.

Details are available in report as Annexure-V

10. Date of

Air/Water/Noise

Monitoring

Study was carried out for three month from March 2019 to may 2019

Report is enclosed in report as Annexure VI

11. 9 Information about 500

mts composite map

As it is “Category B1” project.

12. 1 Environment

Management Plan

Capital Cost- Rs. 11,84,000/-

Recurring Cost-Rs. 4,67,400/-

Details are available of the submitted report.

Budgetary Allowance for Environmental Management

S.

No.

Description Capital

Cost (Rs.)

Recurring

Cost/Year

(Rs.)

1 Septic Tank followed by soak pit 20,000 500

2 Green Belt Development (including maintenance) 1,64,000 4,10,000

3 Wire fencing at plantation site 65,000 5,000

4 Water Sprinkling 5,000 10,000

Final minutes of 4.95th meeting held on 27-29 July, 2021

5 Waste Dump Management 20,000 5,000

6 Haul road and other roads repair and maintenance - 10,000

7 Monitoring of Air, Water, Noise & Soil - 26,900

Total Rs.

2,74,000/-

Rs.

4,67,400/-

Infrastructural support to Rajkiya Ucchay Prathmik Vidhylaya Piploda ka Bas, Village-

Atbhigha, Tehsil-Khandela, Sikar (Total Students-50, Boys-20;Girls-30;Staff-4.)

8 Construction of

kitchen in school.

One kitchen Rs.50,000/- 50,000/- -

9 One unit RO with

water cooler.

Rs.50,000/- per unit. 50,000/- -

10 Furniture for students

and staff.

Rs.50,000/-(50 benches+

[email protected]/unit, & one

table +four chairs for staff.

60,000/- -

11 Repairing of ceiling

in class rooms.

Rs.1,50,000/- (Four class

rooms)

1,50,000/- -

12 Repairing of the

school boundary wall.

Rs. 40,000/- 40,000/- -

13 Fans and bulbs along

with fitting.

Rs. 50,000/- 50,000/- -

Total Rs.

4,00,000/-

Public Hearing points

14 Solar light on both

side of road

Rs.20,000/- per unit. 4,00,000/-

15 Water tank along

with one unit RO

with water cooler in

village Atbhigha near

bus stand

Rs.60,000/- per unit. 60,000/-

16 Plantation of on

both side of road

Rs. 500/- per tree with tree

guard

50,000/-

Total Rs.

5,10,000/-

-

Grand total Rs.

11,84,000/-

Rs.

4,67,400/-

13. Public hearing Points S.No Major issues raised in Public Hearing

Action taken by PP Budget allotted and time period

1. Shri Mahesh Kr PP replied that plantation Rs. In monsoon

Final minutes of 4.95th meeting held on 27-29 July, 2021

Bajiya raised issue

of Air Pollution and

Job opportunities for

local people

at mine site, along with

boundary and both side of

road will be done to protect

the air pollution.

Mine will provide 135 jobs

to local people directly and more than 100 will be

associated through

indirectly.

50,000/-

for

plantation

on both

side of

road to control

air

pollution

season,

plantation

drive will be

arranged and

more than 100

plants will be planted

alongside the

road.

2. Shri Aminchnad and

Sarli Hakim said

drinking water

facility should be

arranged for

villagers at village.

PP assured that one water

tank with RO unit and

cooler will be set up at

near bus stand in village

atbhigha for safe and clean

water.

Rs.

60,000/-

for the

safe

drinking

water

facility

This activity

will be done at

the time of the

inauguration

of mine

activity.

3. Shri Bhawani Singh

raised that proper

lighting arrangement should be made for

safe movement of

road.

PP in reply assure that

solar lights will be

provided on road side for better visibility at night.

Rs.

4,00,000/

- will be spent on

solar

lights on

the road

sides.

In first year 10

solar lights

and next year 10 lights will

be installed.

14. 1 Green Belt/ Plantation

Proposed Plantation will be 2650 Plants, which will cover 6.60 Ha. Of the total land.

Year Un-worked

Area

Waste Dump

(Outside)

Inside Dump

(Reclaimed

Area)

Top Soil

Dumps

Total

Area

(Ha.)

No.

of

Tree

Area

(Ha.)

No.

of

Trees

Area

(Ha.)

No.

of

Trees

Area

(Ha.)

No.

of

Trees

Area

(Ha.)

No.

of

Trees

Existing 0.20 50 - - - - - - 0.20 50

I 1.28 520 - - - - - - 1.28 520

II 1.28 520 - - - - - - 1.28 520

III 1.28 520 - - - - - - 1.28 520

IV 1.28 520 - - - - - - 1.28 520

V 1.28 520 - - - - - - 1.28 520

VIth

Year

Onwards

- - - - - - - - - -

Total 6.60 2650 - - - - - - 6.60 2650

15. 1 Budgetary Breakup Fixed Explicit Investment- Rs. 50,000/-

Final minutes of 4.95th meeting held on 27-29 July, 2021

for Labour Running Expenses Per Year- Rs. 50,000/-

Details are available in the submitted report.

16. Present Status The mine is closed (since 1.04.2013 to till date).

Brief details of the project:-

The SEAC considered/examined the project proposal submitted by the PP and also the

presentation made by him through VC/Electronic media in accordance with letter dated

27.05.2020 of SEIAA, Rajasthan.

BACK Ground Note : Proceeding of the 4.13th meeting of SEAC held on 27th

, 28th

, 29th

and 30th

May, 2019 at Agenda no. 16.

The PP had obtained EC from the MoEF & CC vide letter dated 15.05.2006 for

mining of 5000 TPA of Quartz Feldspar, Calcite and Masonry Stone at mining lease No.

34/04 comprising 20.0 hectare located at Village - Athbigha, Tehsil-Khandela, District-Sikar,

State- Rajasthan under the EIA notification dated 27.01.1994. As per approved mining plan

the lease area comprises Khasra no. 1, 3, 47, 49, 56, 34 to 39, 50 to 52 of Village Athbigha;

Khasra no. 96, 97, 93, 94 of village Chak basdi; Khasra no. 60, 69, 71, 70, 70/471, 67, 68, 66

and 70 of village Chak Khandela; Khasra no. 65/1, 65/2, 66, 66/170 of village Khandela

basdi and Khasra no. 2, 11/305 of village Charanwas. The PP has sought ToR for increasing

production of the aforesaid minerals from 5,000 TPA to 12,61,730 TPA. The modified

mining plan has been approved by SME, Jaipur on 19.04.2018. The project cost is 2.00

Crore. The mining lease is a part of cluster as per cluster map prepared by the Mining

Engineer and being so the project requires preparation of cluster EIA and EMP and holding

of common public hearing.

The SEAC in pursuance to the decision taken on 28th May, 2019, inter alia, prescribed

the ToR vide letter dated 19.06.2019. The PP has collected base line data from March, 2019-

May, 2019. In compliance of ToR, PP has conducted Public hearing on 21.11.2019 at

Karyalay Panchayat Samiti Khandela, Sikar, under the Chairmanship of DIG, Stamp Cum

Secretary, UIT and RO, RSPCB, Sikar.

The PP has submitted application for expansion in production capacity from 50,000

TPA - 12,61,730 MTPA of Quartz, Feldspar, Calcite and inclusion of Masonry Stone mining

project, along with Mineral Grinding Unit/Crusher at mine lease of 12,61,730 TPA capacity

in total, M.L.- 34/04, Area- 20.0 ha., at near Village- Atbhigha, Tehsil- Khandela, District-

Sikar, State- Rajasthan. The SME, Udaipur has granted LOI for inclusion of mineral Masonry

Stone on 09.01.2018. SME, Udaipur vide letter dated 12.11.2020 has extended validity of

LOI for 06 months from date of issue of letter. The mining plan has been approved by the

SME, Jaipur vide letter dated 26.05.2020. ME, Ajmer in his certificate dated 31.05.2019 has

stated that the mining lease does not fall in Aravalli hills. DCF, Sikar in his certificated dated

03.01.2020 stated that there is no Wildlife Sanctuary/National Park/ Conservation Reserve

within 10 km periphery of the mine. The project does not involve approval/ clearance under

the Forest (Conservation) Act, 1980 and Wild Life Protection Act, 1972 as no forest land is

involved and neither there is any Wild Life Sanctuary/ National Park within 10 Km from the

Final minutes of 4.95th meeting held on 27-29 July, 2021

project site. As per cluster certificate issued by ME, Sikar on 19.12.2019, the total area of all

the mining leases in the cluster having area of 20.0 ha.

The PP has submitted affidavit of transferor stating that he has no objection to transfer

of EC from Sh. Parakram Singh to M/s Reverence Mines & Minerals Pvt. Ltd. Undertaking

has also been given by the transferee, M/s Reverence Mines & Minerals Pvt. Ltd (Sh. Inder

Kumar, Director) that he will comply with all the conditions (specific and general) laid down

in the EC issued by MoEF & CC vide order dated 15.05.2006.

The SEAC, while considering the proposal for transfer of EC and enhancement of

production capacity, as mentioned above, was of the view that the recommendation for

enhancement of production can only be made after SEIAA has sanctioned proposal for

transfer of EC. The SEAC, therefore, decided in the first instance to make recommendation

only with respect to the proposal for transfer of EC. The SEAC accordingly also decided that

it will be take up the matter of enhancement of production only after SEIAA has sanctioned

transfer of EC.

Observations and Resolution of the Committee:

The SEAC took up the matter and considered/examined the project proposal in its

4.95th meeting held on 27-29 July, 2021 in the light of the order dated 16.04.2021 of SEIAA

transfer in EC from Sh. Parakram Singh to M/s Reverence Mines & Minerals Pvt. Ltd.

The SEAC, in its 4.65th meeting held on 28-29 Dec, 2020, had recommended to

SEIAA for transferring of EC dated 15.05.2006.

The SEIAA in its order dated 16.04.2021 has mentioned that the authority has

accepted the recommendation of SEAC as per provisions of Para 11 of EIA Notification

2006. The para 11 of EIA notification 2006 relates with transfer of EC.

The SME, Udaipur has granted LOI for inclusion of mineral Masonry Stone on

09.01.2018. SME, Udaipur vide letter dated 12.11.2020 has extended validity of LOI for 06

months from date of issue of letter. SME, Udaipur vide letter dated 20.07.2021 has further

extended validity of LOI for 06 months from date of issue of letter.

The SEAC in pursuance to the decision taken on 28th May, 2019, inter alia, prescribed

the ToR vide letter dated 19.06.2019. The PP has collected base line data from March, 2019-

May, 2019. In compliance of ToR, PP has conducted Public hearing on 21.11.2019 at

Karyalay Panchayat Samiti Khandela, Sikar, under the Chairmanship of DIG, Stamp Cum

Secretary, UIT and RO, RSPCB, Sikar.

The PP has submitted compliance report, vide letter dated 06.01.2019 of the RO,

RSPCB, Sikar certifying compliance of conditions of the earlier EC issued vide letter dated

15.05.2006.

The SEAC considered the order dated 16.04.2021 of the SEIAA, Form-1, Form-2,

Pre-feasibility report, other documents submitted by the PP/Consultant and background as

stated above and therefore, resolved to recommend to SEIAA for grant of EC to M/s

Reverence Mines & Minerals Pvt. Ltd., Sh. Anil Gupta, Director and Authorized Signatory

Sh. Inder Kumar for expansion in production capacity from 50,000 TPA - 12,61,730 MTPA

of Quartz, Feldspar, Calcite and inclusion of Masonry Stone mining project, along with

Final minutes of 4.95th meeting held on 27-29 July, 2021

Mineral Grinding Unit/Crusher at mine lease of 12,61,730 TPA capacity in total, M.L.-

34/04, Area- 20.0 ha., Khasra no. 1, 3, 47, 49, 56, 34 to 39, 50 to 52 of Village Athbigha;

Khasra no. 96, 97, 93, 94 of village Chak basdi; Khasra no. 60, 69, 71, 70, 70/471, 67, 68, 66

and 70 of village Chak Khandela; Khasra no. 65/1, 65/2, 66, 66/170 of village Khandela

basdi and Khasra no. 2, 11/305 of village Charanwas at near Village- Athbigha, Tehsil-

Khandela, District- Sikar, State- Rajasthan (Proposal no- 48618), with the stipulation that the

PP shall abide by the annual production scheduled specified in mining plan and that any

deviation there in will render the PP liable for legal action in accordance with Environment

and Mining Laws, with the specific and general conditions annexed at Annexure ‘A’. Project

Name:- Application for expansion in production capacity from 50,000 TPA - 12,61,730

MTPA of Quartz, Feldspar, Calcite and inclusion of Masonry Stone mining project, M.L.-

34/04, Area- 20.0 ha., Khasra no. 1, 3, 47, 49, 56, 34 to 39, 50 to 52 of Village Athbigha;

Khasra no. 96, 97, 93, 94 of village Chak basdi; Khasra no. 60, 69, 71, 70, 70/471, 67, 68, 66

and 70 of village Chak Khandela; Khasra no. 65/1, 65/2, 66, 66/170 of village Khandela

basdi and Khasra no. 2, 11/305 of village Charanwas at near Village- Athbigha, Tehsil-

Khandela, District- Sikar, State- Rajasthan (Proposal no- 48618). Project Proponent

Name:- M/s Reverence Mines & Minerals Pvt. Ltd., Sh. Anil Gupta, Director and Authorized

Signatory Sh. Inder Kumar, Add-A-28, Anita Colony, Bajaj Nagar, Jaipur, E-Mail-

[email protected].

Final minutes of 4.95th meeting held on 27-29 July, 2021

AANNNNEEXXUURREE--““AA””

1. Statutory compliance:

i. This Environmental Clearance (EC) is subject to orders/ directions of Hon’ble

Supreme Court of India, Hon’ble High Court, Hon’b1e NGT and any other Court

of Law, as is applicable.

ii. The Project proponent complies with all the statutory requirements and judgments

of Hon’b1e Supreme Court dated 2nd August, 2017 in Writ Petition (Civil) No.

114 of 2014 in matter of Common Cause versus Union of India & Ors before

commencing the mining operations.

iii. The Department of Mines & Geology, Government of Rajasthan (DMG, GoR)

shall ensure that mining operation shall not be commenced till the entire

compensation levied, if any, for illegal mining paid by the Project Proponent

through Department of Mining & Geology in strict compliance of Judgment of

Hon’ble Supreme Court dated 2nd August, 2017 in Writ Petition (Civil) No. 114 of

2014 in matter of Common Cause versus Union of India & Ors.

iv. In case the project falls within a distance of 10 Km from the boundary of a

National Park/ Wildlife Sanctuary, wherein final ESZ Notification has not

been issued so far, the EC shall come into effect only after the PP obtains

clearance from the Standing Committee of National Board for Wildlife

(SCNBWL) as per OM dated 08.08.2019 of MoEF & CC.

v. This Environmental Clearance shall become operational only after receiving

formal SCNBWL Clearance from Ministry of Environment, Forest & Climate

Change, (MoEF & CC), Government of India (GoI) subsequent to the

recommendations of the Standing Committee of National Board for Wildlife, if

applicable to the Project.

vi. This Environmental Clearance shall become operational only after receiving

Forest Clearance (FC) under the provision of Forest Conservation Act, 1980, if

applicable to the Project.

vii. Project Proponent (PP) shall obtain Consent to Operate after grant of EC and

effectively implement all the conditions stipulated therein. The mining activity

shall not commence prior to obtaining Consent to Establish/ Consent to Operate

from the State Pollution Control Board.

viii. The PP shall adhere to the provision of the Mines Act, 1952, Mines and Mineral

(Development & Regulation), Act, 2015 and rules & regulations made there under.

PP shall adhere to various circulars issued by Directorate General Mines Safety

(DGMS) and Indian Bureau of Mines (IBM) from time to time.

ix. The Project Proponent shall obtain consents from all the concerned land owners,

Final minutes of 4.95th meeting held on 27-29 July, 2021

before start of mining operations, as per the provisions of MMDR Act, 1957 and

rules made thereunder in respect of lands which are not owned by it.

x. The Project Proponent shall follow the mitigation measures provided in MoEF

CC’s Office Memorandum No. Z-11013/57/2014-IA.II (M), dated 29th October,

2014, titled “Impact of mining activities on Habitations-Issues related to the

mining Projects wherein Habitations and villages are the part of mine lease areas

or Habitations and villages are surrounded by the mine lease area”.

xi. The Project Proponent shall obtain necessary prior permission of the competent

authorities for drawl of requisite quantity of surface water and from CGWA for

withdrawal of ground water for the project.

xii. A copy of EC letter will be marked to concerned Panchayat/ local NGO etc. if

any, from whom suggestion/ representation has been received while processing

the proposal.

xiii. State Pollution Control Board shall be responsible for display of this EC letter at

its Regional office, District Industries Centre and Collector’s office/ Tehsildar’s

Office for 30 days.

xiv. The Project Authorities should widely advertise about the grant of this EC letter by

printing the same in at least two local newspapers, one of which shall be in

vernacular language of the concerned area. The advertisement shall be done

within 7 days of the issue of the clearance letter mentioning that the instant project

has been accorded EC and copy of the EC letter is available with the State

Pollution Control Board and website of the Department of Environment, Govt. of

Rajasthan, RSPCB for compliance and record.

xv. The Project Proponent shall inform the MoEF & CC/ SEIAA for any change in

ownership of the mining lease. In case there is any change in ownership or mining

lease is transferred then mining operation shall only be carried out after transfer of

EC as per provisions of the para 11 of EIA Notification, 2006 as amended from

time to time.

xvi. The Mining Department will ensure that while executing the mining lease, if the

mining lease forms a cluster of total area of more than 5.0 ha, in accordance with

EIA notification dated 15.01.2016 and 01.07.2016, then such mining lease will be

executed/ registered only after public hearing has taken place for the entire cluster

and there has been EIA/EMP study of the entire cluster. The Mining Department

will further ensure that revised EC is also obtained by such mining lease holder (s)

in the cluster.

xvii. The Mining lease holder shall, after ceasing mining operations, undertake re-

grassing the mining area and any other area which may have been disturbed due to

the mining activities and restore the land to a condition which is fit for growth of

fodder, flora, fauna etc.

Final minutes of 4.95th meeting held on 27-29 July, 2021

xviii. That the grant of this E.C. is issued from the environmental angle only, and does

not absolve the project proponent from the other statutory obligations prescribed

under any other law or any other instrument in force. The sole and complete

responsibility, to comply with the conditions laid down in all other laws for the

time-being in force, rests with the project proponent.

xix. No further expansion or modifications in the project shall be carried out without

prior approval of the SEIAA/MoEF & CC as the case may be. In case of

deviations or alterations in the project proposal from those submitted to this

Authority for clearance, a fresh reference shall be made to the Authority to assess

the adequacy of conditions imposed and to include additional environmental

protection measures required, if any.

xx. The EC is liable to be rejected/ revoked, in case it is found that the PP has

deliberately concealed and/or furnished false and misleading information or data

which is material to screening or scoping or appraisal or decision on the

application for EC.

xxi. Officials from the Department of Environment, Government of Rajasthan, Jaipur/

Regional Office of MoEF & CC, Lucknow, RSPCB who would be monitoring the

implementation of Environmental safeguards should be extended full cooperation,

facilities and documents/data by the project proponents during their inspection. A

complete set of all the documents submitted to SEIAA should be forwarded to the

CCF, Regional Office of MoEF, Lucknow, Department of Environment,

Government of Rajasthan, Jaipur / RSPCB.

xxii. The Authority reserves the right to add additional safeguard measures

subsequently, if found necessary, and to take action including revoking of the

environment clearance under the provision of the Environment (Protection) Act,

1986, to ensure effective implementation of the suggested safeguard measures in a

time bound and satisfactory manner.

xxiii. The above condition shall be enforced among others under the provisions of

Water (Prevention and Control of Pollution) Act, 1974, the Air (Prevention and

Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986, the

Public Liability (Insurance) Act, 1991 and EIA Notification, 2006, along with

their amendments and rules.

xxiv. The PP shall obtain prior clearance from forestry and wildlife aspects including

clearance from Standing Committee of National Board of Wild Life (if

applicable). It is further categorically stated that grant of EC does not necessary

imply that Forestry and Wildlife clearance shall be granted to the project by the

concerned authorities. Proposals for forestry and wildlife clearance will be

considered by the concerned authorities on its merits and decision taken

accordingly. The investment made in the project, if any based on EC so granted,

in anticipation of clearance from Forestry and Wildlife aspects shall be entirely at

the cost and risk of the PP and MOEF & CC/SEIAA/ SEAC/ DOE shall not be

responsible in this regard in any manner.

xxv. The SEIAA, Rajasthan may revoke or suspend the Environmental Clearance, if

implementation of any of the above conditions is not satisfactory.

Final minutes of 4.95th meeting held on 27-29 July, 2021

xxvi. The PP shall submit an environmental statement for the financial year ending 31st

March in Form-V as prescribed under the environment (Protection) Rules, 1986,

as amended subsequently on or before the 30th day of September every year, to the

Rajasthan State Pollution Control Board/SEIAA and shall also be put on the

website of the company/ unit/ industry along with the status of compliance of

environmental clearance conditions and shall also be sent to the Lucknow

Regional offices of MoEF/SEIAA/ RSPCB by e-mail as well as hard copy duly

signed by competent person of company.

xxvii. This EC is granted for mining of the mineral with production mentioned in the

above table subject to the stipulation that the PP shall abide by the annual/

permitted production schedule specified in the mining plan and that any deviation

therein will render the PP liable for legal action in accordance with Environment

and Mining Laws.

xxviii. The PP shall spend the various amounts in the respective heads as mentioned in

Annexure G.

xxix. Drills shall either be operated with dust extractors or equipped with water

injections system.

xxx. Data on ambient air quality and stack emissions should be submitted to Rajasthan

State Pollution Control Board once in six months. The monitoring/ sampling and

analysis are to be carried out by MOEF/ NABL/ CPCB/ RSPCB/ Government

approved lab.

xxxi. Blasting operations, if permitted, should be carried out only during the daytime

with safe blasting parameters.

xxxii. The PP shall carry out mining activities with open cast method. The PP to

undertake underground mining only if permitted specifically.

xxxiii. In the project related to Bajri mining the PP shall follow the ‘Sustainable Sand

Mining Guidelines 2016’ and ‘Enforcement and Monitoring Guidelines for Sand

Mining, 2020’ laid down by the MoEF & CC, GOI. The Bajri sand mining

activity is restricted to three meters from ground level or water level whichever is

less and the PP shall carry out river sand (Bajri) mining activity only manually or

semi mechanized method as provided under the ‘Sustainable Sand Mining

Management Guidelines, 2016’ and ‘Enforcement and Monitoring Guidelines for

Sand Mining, 2020’.

xxxiv. Any appeal against this environmental clearance shall lie with the National Green

Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of

the National Green Tribunal Act, 2010.

2. Air quality monitoring and preservation:

i. The Project Proponent shall install a minimum of 3 (three) online Ambient Air

Quality Monitoring Stations with 1 (one) in upwind and 2 (two) in downwind

direction based on long term climatological data about wind direction such that an

angle of 120° is made between the monitoring locations to monitor critical

Final minutes of 4.95th meeting held on 27-29 July, 2021

parameters, relevant for mining operations, of air pollution viz. PMI 0, PM2.5,

NO2; CO and SO2 etc. as per the methodology mentioned in NAAQS

Notification No. B-29016/20/90/PCI/I. dated l 8.11.2009 covering the aspects of

transportation and use of heavy machinery in the impact zone. The ambient air

quality shall also be monitored at prominent places like office building, canteen

etc. as per the site condition to ascertain the exposure characteristics at specific

places. The above data shall be digitally displayed within 03 months in front of the

main Gate of the mine site.

ii. Effective safeguard measures for prevention of dust generation and subsequent

suppression (like regular water sprinkling, metalled road construction etc.) shall

be carried out in areas prone to air pollution wherein high levels of PM10 and

PM2.5 are evident such as haul road, loading and unloading point and transfer

points. The fugitive dust emissions from all sources shall be regularly controlled by

installation of required equipments/ machineries and preventive maintenance. Use

of suitable water-soluble chemical dust suppressing agents may be explored for

better effectiveness of dust control system. It shall be ensured that air pollution

level conform to the standards prescribed by the MoEF & CC/ Central Pollution

Control Board.

3. Water quality monitoring and preservation:

i. In case, immediate mining scheme envisages intersection of ground water table, then

Environmental Clearance shall become operational only after receiving formal

clearance from CGWA. In case, mining operation involves intersection of ground

water table at a later stage, then PP shall ensure that prior approval from CGWA and

MoEF & CC is in place before such mining operations. The permission for

intersection of ground water table shall essentially be based on detailed hydro-

geological study of the area.

ii. Regular monitoring of the flow rate of the springs and perennial nallahs flowing in

and around the mine lease shall be carried out and records maintain. The natural water

bodies and or streams which are flowing in an around the village, should not be

disturbed. The Water Table should be nurtured so as not to go down below the pre-

mining period. In case of any water scarcity in the area, the Project Proponent has to

provide water to the villagers for their use. A provision for regular monitoring of

water table in open dug well located in village should be incorporated to ascertain the

impact of mining over ground water table. The Report on changes in Ground water

level and quality shall be submitted on six-monthly basis to the Regional Office of the

Ministry, CGWA and State Groundwater Department / State Pollution Control Board.

iii. Project Proponent shall regularly monitor and maintain records w.r.t. ground water

level and quality in and around the mine lease by establishing a network of existing

wells as well as new piezo-meter installations during the mining operation in

consultation with Central Ground Water Authority/ State Ground Water Department.

The Report on changes in Ground water level and quality shall be submitted on six-

monthly basis to the Regional Office of the Ministry, CGWA and State Groundwater

Final minutes of 4.95th meeting held on 27-29 July, 2021

Department / State Pollution Control Board.

iv. The Project Proponent shall undertake regular monitoring of natural water course/

water resources/ springs and perennial nallahs existing/ flowing in and around the

mine lease and maintain its records. The project proponent shall undertake regular

monitoring of water quality upstream and downstream of water bodies passing within

and nearby/ adjacent to the mine lease and maintain its records. Sufficient number of

gullies shall be provided at appropriate places within the lease for management of

water. PP shall carryout regular monitoring w.r.t. pH and included the same in

monitoring plan. The parameters to be monitored shall include their water quality vis-

a-vis suitability for usage as per CPCB criteria and flow rate. It shall be ensured that

no obstruction and/ or alteration be made to water bodies during mining operations

without justification and prior approval of MoEF & CC. The monitoring of water

courses/ bodies existing in lease area shall be carried out four times in a year viz. pre-

monsoon (April-May), monsoon (August), post-monsoon (November) and winter

(January) and the record of monitored data may be sent regularly to Ministry of

Environment, Forest and Climate Change and its Regional Office, Central Ground

Water Authority and Regional Director, Central Ground Water Board, State Pollution

Control Board and Central Pollution Control Board. Clearly showing the trend

analysis on six –monthly basis.

v. Quality of polluted water generated from mining operations which include Chemical

Oxygen Demand (COD) in mines run-off; acid mine drainage and metal

contamination in runoff shall be monitored along with Total Dissolved Solids (TDS),

Dissolved Oxygen (DO), pH and Total Suspended Solids (TSS). The monitored data

shall be uploaded on the website of the company as well as displayed at the project

site in public domain, on a display board, at a suitable location near the main gate of

the Company. The circular No.I-20012/1/2006-IA.II (M) dated 27.05.2009 issued by

Ministry of Environment, Forest and Climate Change may also be referred in this

regard.

vi. Project Proponent shall plan, develop and implement rainwater harvesting measures

on long term basis to augment ground water resources in the area in consultation with

Central Ground Water Board/ State Groundwater Department. A report on amount of

water recharged needs to be submitted to Regional Office MoEF & CC annually.

vii. Industrial waste water (workshop and waste water from the mine) should be properly

collected and treated so as to conform to the notified standards prescribed from time

to time. The standards shall be prescribed through Consent to Operate (CTO) issued

by concerned State Pollution Control Board (SPCB). The workshop effluent shall be

treated after its initial passage through Oil and grease trap.

viii. The water balance/water auditing shall be carried out and measure for reducing the

consumption of water shall be taken up and reported to the Regional Office of the

MoEF & CC and State Pollution Control Board.

Final minutes of 4.95th meeting held on 27-29 July, 2021

4. Noise and vibration monitoring and prevention:

i. The peak particle velocity at 500m distance or within the nearest habitation,

whichever is closer shall be monitored periodically as per applicable DGMS

guidelines.

ii. The illumination and sound at night at project sites disturb the villages in respect

of both human and animal population. Consequent sleeping disorders and stress

may affect the health in the villages located close to mining operations.

Habitations have a right for darkness and minimal noise levels at night. PPs must

ensure that the biological clock of the villages is not disturbed; by orienting the

floodlights/ masks away from the villagers and keeping the noise levels well

within the prescribed limits for day /night hours.

iii. The Project Proponent shall take measures for control of noise levels below 85

dBA in the work environment. The workers engaged in operations of HEMM,

etc. should be provided with ear plugs/ muffs. All personnel including laborers

working in dusty areas shall be provided with protective respiratory devices along

with adequate training, awareness and information on safety and health aspects.

The PP shall be held responsible in case it has been found that workers/

personals/ laborers are working without personal protective equipment.

iv. The ambient noise level should confirm to the standards prescribed under E (P)

A Rules, 1986 viz 75 dB (A) during day time and 70 dB (A) during night time.

5. Mining plan:

i. The Project Proponent shall adhere to the working parameters of mining plan

which was submitted at the time of EC appraisal wherein year-wise plan was

mentioned for total excavation i.e. quantum of mineral, waste, over burden, inter

burden and top soil etc.. No change in basic mining proposal like mining

technology, total excavation, mineral & waste production, lease area and scope of

working (viz. method of mining, overburden & dump management , O.B & dump

mining, mineral transportation mode, ultimate depth of mining etc.) shall not be

carried out without prior approval of the Ministry of Environment, Forest and

Climate Change/ SEIAA, which entail adverse environmental impacts, even if it

is a part of approved mining plan modified after grant of EC or granted by State

Govt. in the form to Short Term Permit (STP), Query license or any other name.

ii. The Project Proponent shall get the Final Mine Closure Plan along with Financial

Assurance approved from Indian Bureau of Mines/Department of Mining &

Geology as required under the Provision of the MMDR Act, 1957 and Rules/

Guidelines made there under. A copy of approved final mine closure plan shall be

submitted within 2 months of the approval of the same from the competent

authority to the concerned Regional Office, MoEF & CC/ SEIAA/ SPCB for

record and verification.

Final minutes of 4.95th meeting held on 27-29 July, 2021

iii. The land-use of the mine lease area at various stages of mining scheme as well as

at the end-of-life shall be governed as per the approved Mining Plan. The

excavation vis-a-vis backfilling in the mine lease area and corresponding

afforestation to be raised in the reclaimed area shall be governed as per approved

mining plan. PP shall ensure the monitoring and management of rehabilitated

areas until the vegetation becomes self- sustaining. The compliance status shall be

submitted half-yearly to the MoEF & CC/ SEIAA/ SPCB and its concerned

Regional Office.

6. Land reclamation:

i. The Overburden (O.B.) generated during the mining operations shall be stacked at

earmarked OB dump site(s) only and it should not be kept active for a long period

of time. The physical parameters of the OB dumps like height, width and angle of

slope shall be governed as per the approved Mining Plan as per the

guidelines/circulars issued by D.G.M.S w.r.t. safety in mining operations shall be

strictly adhered to maintain the stability of top soil/OB dumps. The topsoil shall be

used for land reclamation and plantation.

ii. The reject/waste generated during the mining operations shall be stacked at

earmarked waste dump site(s) only. The physical parameters of the waste dumps

like height. width and angle of slope shall be governed as per the approved

Mining Plan as per the guidelines/circulars issued by DGMS w.r.t. safety in

mining operations shall be strictly adhered to maintain the stability of waste

dumps.

iii. The reclamation of waste dump sites shall be done in scientific manner as per the

Approved Mining Plan cum Progressive Mine Closure Plan.

iv. The slope of dumps shall be vegetated in scientific manner with suitable native

species to maintain the slope stability, prevent erosion and surface run off. The

selection of local species regulates local climatic parameters and help in

adaptation of plant species to the microclimate. The gullies formed on slopes

should be adequately taken care of as it impacts the overall stability of dumps. The

dump mass should be consolidated with the help of dozer/ compactors thereby

ensuring proper filling/ leveling of dump mass. In critical areas, use of geo

textiles/ geo-membranes / clay liners / Bentonite etc. shall be undertaken for

stabilization of the dump.

v. The Project Proponent shall carry out slope stability study in case the dump height

is more than 30 meters. The slope stability report shall be submitted to concerned

regional office of MoEF & CC/ RSPCB.

vi. Catch drains, settling tanks and siltation ponds of appropriate size shall be

Final minutes of 4.95th meeting held on 27-29 July, 2021

constructed around the mine working, mineral yards and Top Soil/OB/Waste

dumps to prevent run off of water and flow of sediments directly into the water

bodies (Nallah/ River/ Pond etc.). The collected water should be utilized for

watering the mine area, roads, green belt development, plantation etc. The drains/

sedimentation sumps etc. shall be de-silted regularly, particularly after monsoon

season, and maintained properly.

vii. Check dams of appropriate size, gradient and length shall be constructed around

mine pit and OB dumps to prevent storm run-off and sediment flow into adjoining

water bodies. A safety margin of 50% shall be kept for designing of sump

structures over and above peak rainfall (based on 50 years data) and maximum

discharge in the mine and its adjoining area which shall also help in providing

adequate retention time period thereby allowing proper settling of sediments/ silt

material. The sedimentation pits/ sumps shall be constructed at the corners of the

garland drains.

viii. The top soil, if any, shall temporarily be stored at earmarked site(s) within the

mine lease only and should not be kept unutilized for long. The physical

parameters of the top soil dumps like height, width and angle of slope shall be

governed as per the approved Mining Plan and as per the guidelines framed by

DGMS w.r.t. safety in mining operations shall be strictly adhered to maintain the

stability of dumps. The topsoil shall be used for land reclamation and plantation

purpose.

7. Transportation:

i. No Transportation of the minerals shall be allowed in case of roads passing through

villages/ habitations. In such cases, PP shall construct a 'bypass’ road for the

purpose of transportation of the minerals leaving an adequate gap (say at least 200

meters) so that the adverse impact of sound and dust along with chances of

accidents could be mitigated. All costs resulting from widening and strengthening

of existing public road network shall be borne by the PP in consultation with nodal

State Govt. Department. Transportation of minerals through road movement in

case of existing village/ rural roads shall be allowed in consultation with nodal

State Govt. Department only after required strengthening such that the carrying

capacity of roads is increased to handle the traffic load. The pollution due to

transportation load on the environment will be effectively controlled and water

sprinkling will also be done regularly. Vehicular emissions shall be kept under control

and regularly monitored. Project should obtain Pollution Under Control (PUC)

certificate for all the vehicles from authorized pollution testing centers.

ii. The Main haulage road within the mine lease should be provided with a permanent

water sprinkling arrangement for dust suppression. Other roads within the mine

lease should be wetted regularly with tanker-mounted water sprinkling system.

The other areas of dust generation like crushing zone, material transfer points,

material yards etc. should invariably be provided with dust suppression

Final minutes of 4.95th meeting held on 27-29 July, 2021

arrangements. The air pollution control equipments like bag filters, vacuum suction

hoods, dry fogging system etc. shall be installed at Crushers, belt-conveyors and

other areas prone to air pollution. The belt conveyor should be fully covered to

avoid generation of dust while transportation. PP shall take necessary measures to

avoid generation of fugitive dust emissions.

8. Green Belt:

i. The Project Proponent shall develop greenbelt in 7.5m wide safety zone all along the

mine lease boundary as per the guidelines of CPCB in order to arrest pollution

emanating from mining operations within the lease. The whole Green belt shall be

developed within first 5 years starting from windward side of the active mining area.

The development of greenbelt shall be governed as per the EC granted by the

Ministry/ SEIAA irrespective of the stipulation made in approved mine plan.

ii. The Project Proponent shall carryout plantation/ afforestation in backfilled and

reclaimed area of mining lease, around water body, along the roadsides, in

community areas etc. by planting the native species in consultation with the State

Forest Department/ Agriculture Department/ Rural development department/ Tribal

Welfare Department/ Gram Panchayat such that only those species be selected

which are of use to the local people. The CPCB guidelines in this respect shall

also be adhered. The density of the trees should be around 2500 saplings per

Hectare. Adequate budgetary provision shall be made for protection and care of

trees.

iii. The Project Proponent shall make necessary alternative arrangements for livestock

feed by developing grazing land with a view to compensate those areas which are

coming within the mine lease. The development of such grazing land shall be

done in consultation with the State Government. In this regard, Project Proponent

should essentially implement the directions of the Hon’b1e Supreme Court with

regard to acquisition of grazing land. The sparse trees on such grazing ground,

which provide mid-day shelter from the scorching sun, should be scrupulously

guarded/ protected against felling and plantation of such trees should be promoted.

iv. The Project Proponent shall undertake all precautionary measures for

conservation and protection of endangered flora and fauna and Schedule-I species

during mining operation. A Wildlife Conservation Plan shall be prepared for the

same clearly delineating action to be taken for conservation of flora and fauna.

The Plan shall be approved by Chief Wild Life Warden of the State Govt.

v. And implemented in consultation with the State Forest and Wildlife Department.

A copy of Wildlife Conservation Plan and its implementation status (annual) shall

be submitted to the Regional Office of the Ministry/ SEIAA.

9. Public hearing and human health issues:

Final minutes of 4.95th meeting held on 27-29 July, 2021

i. The Project Proponent shall appoint an Occupational Health Specialist for

Regular as well as Periodical medical examination of the workers engaged in the

mining activities, as per the DGMS guidelines. The records shall be maintained

properly. PP shall also carryout Occupational health check-ups in respect of

workers which are having ailments like nr, diabetes, habitual smoking, etc. The

check-ups shall be undertaken once in s1x months and necessary remedial/

preventive measures be taken. A status report on the same may be sent to MoEF &

CC/ SEIAA/ Regional Office and DGMS on half-yearly basis.

ii. The Project Proponent must demonstrate commitment to work towards ‘Zero

Harm’ from their mining activities and carry out Health Risk Assessment (HRA)

for identification workplace hazards and assess their potential risks to health and

determine appropriate control measures to protect the health and wellbeing of

workers and nearby community. The proponent shall maintain accurate and

systematic records of the HRA. The HRA for neighborhood has to focus on

Public Health Problems like Malaria, Tuberculosis, HIV, Anaemia, Diarrhoea in

children under five, respiratory infections due to bio mass cooking. The

proponent shall also create awareness and educate the nearby community and

workers for Sanitation, Personal Hygiene, Hand wasting, not to defecate in open,

Women Health and Hygiene (Providing Sanitary Napkins), hazard of tobacco and

alcohol use. The Proponent shall carryout base line HRA for all the category of

workers and thereafter every five years.

iii. The Proponent shall carry out Occupational health surveillance which be a part

of HRA and include Biological Monitoring where practical and feasible, and the

tests and investigations relevant to the exposure (e.g. for Dust a X-Ray chest; For

Noise Audiometric; for Lead Exposure Blood Lead, For Welders Full

Ophthalmologic Assessment; for Manganese Miners a complete Neurological

Assessment by a Certified Neurologist, and Manganese (Mn) Estimation in

Blood; For Inorganic Chromium- Fortnightly skin inspection of hands and

forearms by a responsible person. Except routine tests all tests would be carried

out in a Lab accredited by NABH. Records of Health Surveillance must be kept

for 30 years, including the results of and the records of Physical examination and

tests. The record of exposure due to materials like Asbestos. Hard Rock Mining,

Silica, Gold, Kaolin, Aluminium. Iron, Manganese, Chromium, Lead, Uranium

need to be handed over to the Mining Department of the State in case the life of

the mine is less than 30 years. It would be obligatory for the State Mines

Departments to make arrangements for the safe and secure storage of the records

including X-Ray. Only conventional X-Ray will be accepted for record purposes

and not the digital one). X-Ray must meet ILO criteria (17 x14 inches and of

good quality).

iv. The Proponent shall maintained a record of performance indicators for workers

which includes (a) there should not be a significant decline in their Body Mass

Index and it should stay between 18.5 -24.9, (b) the Final Chest X-Ray compared

with the base line X-Ray should not show any capacities ,(c) At the end of their

Final minutes of 4.95th meeting held on 27-29 July, 2021

leaving job there should be no Diminution in their Lung Functions Forced

Expiratory Volume in one second (FEV1),Forced Vital Capacity (FVC), and the

ratio) unless they are smokers which has to be adjusted, and the effect of age, (d)

their hearing should not be affected. As a proof an Audiogram (first and last need

to be presented), (e) they should not have developed any Persistent Back Pain,

Neck Pain, and the movement of their Hip, Knee and other joints should have

normal range of movement, (f) they should not have suffered loss of any body

part. The record of the same should be submitted to the Regional Office, MoEF &

CC/ SEIAA annually along with details of the relief and compensation paid to

workers having above indications.

v. The Project Proponent shall ensure that Personnel working in dusty areas should

wear protective respiratory devices and they should also be provided with

adequate training and information on safety and health aspects.

vi. Project Proponent shall make provision for the housing for workers/labors or

shall construct labor camps within/outside (company owned land) with necessary

basic infrastructure/ facilities like fuel for cooking, mobile toilets, mobile STP,

safe drinking water, medical health care, creche for kids etc. The housing may be

provided in the form of temporary structures which can be removed after the

completion of the project related infrastructure. The domestic waste water should

be treated with STP in order to avoid contamination of underground water.

vii. The activities proposed in Action plan prepared for addressing the issues raised

during the Public Hearing shall be completed as per the budgetary provisions

mentioned in the Action Plan and within the stipulated time frame. The Status

Report on implementation of Action Plan shall be submitted to the concerned

Regional Office o1 the Ministry along with District Administration.

10. Miscellaneous:

i. The Project Proponent shall prepare digital map (land use & land cover) of the

entire lease area once in five years purpose of monitoring land use pattern and

submit a report to concerned Regional Office of the MoEF & CC/ SEIAA/ SPCB.

ii. The Project Authorities should inform to the SEIAA/ Regional Office regarding

date of financial closures and final approval of the project by the concerned

authorities and the date of start of land development work.

iii. The Project Proponent shall submit six monthly compliance reports on the status

of the implementation of the stipulated environmental safeguards to the

MOEFCC & its concerned Regional Office, Central Pollution Control Board and

State Pollution Control Board.

iv. A separate ‘Environmental Management Cell’ with suitable qualified manpower

should be set-up under the control of a Senior Executive. The Senior Executive

Final minutes of 4.95th meeting held on 27-29 July, 2021

shall directly report to Head of the Organization. Adequate number of qualified

Environmental Scientists and Mining Engineers shall be appointed and submit a

report to RO, MoEF & CC/ SEIAA/ SPCB.

v. The MoEF & CC/ SEIAA/ SPCB shall randomly monitor compliance of the

stipulated conditions. The project authorities should extend full cooperation to the

MoEF & CC/ SEIAA/ SPCB officer(s) by furnishing the requisite data /

information / monitoring reports.

vi. Project Proponent shall keep the funds earmarked for environmental protection

measures in a separate account and refrain from diverting the same for other

purposes. The Year wise expenditure of such funds should be reported to the

MoEF & CC/ SEIAA/ SPCB and its concerned Regional Office.

Additional conditions recommended in view of OM dated 08.08.2019 of the MoEF &

CC (applicable where the project falls within a distance of 10 Km from the boundary of

National Park/ Wildlife Sanctuary and outside notified ESZ):

1. The mining activity should be carried out in a manner so that the water regime/system of

the sanctuary is not disturbed. The mining activity should not adversely affect any

existing water course, water body, catchment etc. The PP shall while carrying out mining

activity ensure compliance of the provisions of Air (Prevention and Control of Pollution)

Act 1981, Water (Prevention and Control of Pollution) Act 1974 and the Environment

(Protection) Act, 1986 so that the wildlife in the area is not adversely affected.

2. The processes like blasting, drilling, excavation, transport and haulage resulting into

noise, should be carried out in such an manner so that such activities do not disturb wild

animals and birds particularly during sunset to sunrise. The level of noise should be kept

within the permissible limits.

3. The mining activity should not create any obstacle in the way of free movement of

wildlife and adversely affect wildlife corridors.

4. The mineral waste/ slurry should be dumped only at the designated places only and such

waste dumps should be reclaimed in accordance with the conditions of the mining plan/

consent issued by the RSPCB under the Water and Air act.

5. The PP shall cooperate with the concerned DCF, Wildlife in their efforts towards

protection and conservation of wildlife in the Sanctuary/ Park.

6. The PP shall ensure that the transporter and labor employed by him should not damage

flora and fauna in the ESZ and the Wildlife Sanctuary/ National Park.

Specific Conditions applicable, in the cases of violation in terms of the Notification dated

14.3.2017 and 8.3.2018 and OMs dated 30.5.2018, 4.7.2018 of the MoEF & CC :

Final minutes of 4.95th meeting held on 27-29 July, 2021

1. The PP shall give an undertaking by way of affidavit to comply with all the statutory

requirements and judgment of the Hon’ble Supreme Court dated 02.08.2017 in the

matter of Writ Petition (Civil) No. 114 of 2014, Common Cause V/s Union of India &

others before grant of ToR/EC. The undertaking inter-alia include commitment of the PP

not to be repeat any such violation in future.

2. In case of violation of above undertaking/ affidavit, the ToR/EC shall be liable to be

terminated forthwith.

3. The environmental clearance will not be operational, till such time the Project Proponent

complies with all the statutory requirements and judgment of the Hon’ble Supreme

Court dated 02.08.2017 in the matter of Writ Petition (Civil) No. 114 of 2014, Common

Cause V/s Union of India & others.

4. The department of Mines & Geology shall ensure that the mining operations shall not

commence till the entire compensation levied, if any, for illegal mining, is paid, by the

Project Proponent through the Department of Mines and Geology, in strict compliance of

the judgment of the Hon’ble Supreme Court dated 02.08.2017 in the matter of Writ

Petition (Civil) No. 114 of 2014, Common Cause V/s Union of India & others.

Final minutes of 4.95th meeting held on 27-29 July, 2021

AANNNNEEXXUURREE--““BB””

TERMS OF REFERENCE FOR CONDUCTING ENVIRONMENT

IMPACT ASSESSMENT STUDY FOR NON-COAL MINING PROJECTS AND

INFORMATION TO BE INCLUDED IN EIA/EMP REPORT

1) Year-wise production details since 1994 should be given, clearly stating the highest

production achieved in any one year prior to 1994. It may also be categorically informed

whether there had been any increase in production after the EIA Notification 1994 came into

force, w.r.t. the highest production achieved prior to 1994.

2) A copy of the document in support of the fact that the Proponent is the rightful lessee of the

mine should be given.

3) All documents including approved mine plan, EIA and Public Hearing should be compatible

with one another in terms of the mine lease area, production levels, waste generation and its

management, mining technology etc. and should be in the name of the lessee.

4) All corner coordinates of the mine lease area, superimposed on a High Resolution Imagery/

toposheet, topographic sheet, geomorphology and geology of the areashould be provided.

Such an Imagery of the proposed area should clearly show the land use and other ecological

features of the study area (core and buffer zone).

5) Information should be provided in Survey of India Toposheet in 1:50,000 scale indicating

geological map of the area, geomorphology of land forms of the area, existing minerals and

mining history of the area, important water bodies, streams and rivers and soil characteristics.

6) Details about the land proposed for mining activities should be givenwith information as to

whether mining conforms to the land use policy of the State; land diversion for mining should

have approval from State land use board or the concerned authority.

7) It should be clearly stated whether the Proponent Company has a well laid down

Environment Policy approved by its Board of Directors? If so, it may be spelt out in the EIA

Report with description of the prescribed operating process/procedures to bring into focus

any infringement/deviation/ violation of the environmental or forest norms/ conditions? The

hierarchical system or administrative order of the Company to deal with the environmental

issues and for ensuring compliance with the EC conditions may also be given. The system of

reporting of non-compliances / violations of environmental norms to the Board of Directors

of the Company and/or shareholders or stakeholders at large,may also be detailed in the EIA

Report.

8) Issues relating to Mine Safety, including subsidence study in case of underground mining and

slope study in case of open cast mining, blasting study etc. should be detailed. The proposed

safeguard measures in each case should also be provided.

9) The study rea will comprise of 10 km zone around the mine lease from lease periphery and

the data contained in the EIA such as waste generation etc. should be for the life of the mine /

lease period.

Final minutes of 4.95th meeting held on 27-29 July, 2021

10) Land use of the study rea delineating forest area, agricultural land, grazing land, wildlife

sanctuary, national park, migratory routes of fauna, water bodies, human settlements and

other ecological features should be indicated. Land use plan of the mine lease area should be

prepared to encompass preoperational, operational and post operational phases and submitted.

Impact, if any, of change of land use should be given.

11) Details of the land for any Over Burden Dumps outside the mine lease, such as extent of

land area, distance from mine lease, its land use, R&R issues, if any, should be given.

12) A Certificate from the Competent Authority in the State Forest Department should be

provided, confirming the involvement of forest land, if any, in the project area. In the event of

any contrary claim by the Project Proponent regarding the status of forests, the site may be

inspected by the State Forest Department along with the Regional Office of the Ministry to

ascertain the status of forests, based on which, the Certificate in this regard as mentioned

above be issued. In all such cases, it would be desirable for representative of the State Forest

Department to assist the Expert Appraisal Committees.

13) Status of forestry clearance for the broken up area and virgin forestland involved in the

Project including deposition of net present value (NPV) and compensatory afforestation (CA)

should be indicated. A copy of the forestry clearance should also be furnished.

14) Implementation status of recognition of forest rights under the Scheduled Tribes and other

Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 should be indicated.

15) The vegetation in the RF / PF areas in the study area, with necessary details, should be

given.

16) A study shall be got done to ascertain the impact of the Mining Project on wildlife of the

study area and details furnished. Impact of the project on the wildlife in the surrounding and

any other protected area and accordingly, detailed mitigative measures required, should be

worked out with cost implications and submitted.

17) Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors, Ramsar

site Tiger/ Elephant Reserves/(existing as well as proposed), if any, within 10 km of the mine

lease should be clearly indicated, supported by a location map duly authenticated by Chief

Wildlife Warden. Necessary clearance, as may be applicable to such projects due to

proximity of the ecologically sensitive areas as mentioned above, should be obtained from the

Standing Committee of National Board of Wildlife and copy furnished.

18) A detailed biological study of the study area [core zone and buffer zone (10 km radius of the

periphery of the mine lease)] shall be carried out. Details of flora and fauna, endangered,

endemic and RET Species duly authenticated, separately for core and buffer zone should be

furnished based on such primary field survey, clearly indicating the Schedule of the fauna

present. In case of any scheduled-I fauna found in the study area, the necessary plan

alongwith budgetary provisions for their conservation should be prepared in consultation with

State Forest and Wildlife Department and details furnished. Necessary allocation of funds for

implementing the same should be made as part of the project cost.

Final minutes of 4.95th meeting held on 27-29 July, 2021

19) Proximity to Areas declared as 'Critically Polluted' or the Project areas likely to come under

the 'Aravali Range', (attracting court restrictions for mining operations), should also be

indicated and where so required, clearance certifications from the prescribed Authorities,

such as the SPCB or State Mining Department should be secured and furnished to the effect

that the proposed mining activities could be considered.

20) R&R Plan/compensation details for the Project Affected People (PAP) should be furnished.

While preparing the R&R Plan, the relevant State/National Rehabilitation & Resettlement

Policy should be kept in view. In respect of SCs /STs and other weaker sections of the society

in the study area, a need based sample survey, family-wise, should be undertaken to assess

their requirements, and action programmes prepared and submitted accordingly, integrating

the sectoral programmes of line departments of the State Government. It may be clearly

brought out whether the village(s) located in the mine lease area will be shifted or not. The

issues relating to shifting of village(s) including their R&R and socio-economic aspects

should be discussed in the Report.

21) One season (non-monsoon) [i.e. March-May (Summer Season); October-December (post

monsoon season) ; December-February (winter season)]primary baseline data on ambient air

quality as per CPCB Notification of 2009, water quality, noise level, soil and flora and fauna

shall be collected and the AAQ and other data so compiled presented date-wise in the EIA

and EMP Report. Site-specific meteorological data should also be collected. The location of

the monitoring stations should be such as to represent whole of the study area and justified

keeping in view the pre-dominant downwind direction and location of sensitive receptors.

There should be at least one monitoring station within 500 m of the mine lease in the pre-

dominant downwind direction. The mineralogical composition of PM10, particularly for free

silica, should be given.

22) Air quality modeling should be carried out for prediction of impact of the project on the air

quality of the area. It should also take into account the impact of movement of vehicles for

transportation of mineral. The details of the model used and input parameters used for

modeling should be provided. The air quality contours may be shown on a location map

clearly indicating the location of the site, location of sensitive receptors, if any, and the

habitation. The wind roses showing pre-dominant wind direction may also be indicated on the

map.

23) The water requirement for the Project, its availability and source should be furnished. A

detailed water balance should also be provided. Fresh water requirement for the Project

should be indicated.

24) Necessary clearance from the Competent Authority for drawl of requisite quantity of water

for the Project should be provided.

25) Description of water conservation measures proposed to be adopted in the Project should be

given. Details of rainwater harvesting proposed in the Project, if any, should be provided.

26) Impact of the Project on the water quality, both surface and groundwater, should be assessed

and necessary safeguard measures, if any required, should be provided.

Final minutes of 4.95th meeting held on 27-29 July, 2021

27) Based on actual monitored data, it may clearly be shown whether working will intersect

groundwater. Necessary data and documentation in this regard may be provided. In case the

working will intersect groundwater table, a detailed Hydro Geological Study should be

undertaken and Report furnished. The Report inter-alia, shall include details of the aquifers

present and impact of mining activities on these aquifers. Necessary permission from Central

Ground Water Authority for working below ground water and for pumping of ground water

should also be obtained and copy furnished.

28) Details of any stream, seasonal or otherwise, passing through the lease area and modification

/ diversion proposed, if any, and the impact of the same on the hydrology should be brought

out.

29) Information on site elevation, working depth, groundwater table etc. Should be provided

both in AMSL and bgl. A schematic diagram may also be provided for the same.

30) A time bound Progressive Greenbelt Development Plan shall be prepared in a tabular form

(indicating the linear and quantitative coverage, plant species and time frame) and submitted,

keeping in mind, the same will have to be executed up front on commencement of the

Project. Phase-wise plan of plantation and compensatory afforestation should be charted

clearly indicating the area to be covered under plantation and the species to be planted. The

details of plantation already done should begiven. The plant species selected for green belt

should have greater ecological value and should be of good utility value to the local

population with emphasis on local and native species and the species which are tolerant to

pollution.

31) Impact on local transport infrastructure due to the Project should be indicated. Projected

increase in truck traffic as a result of the Project in the present road network (including those

outside the Project area) should be worked out, indicating whether it is capable of handling

the incremental load. Arrangement for improving the infrastructure, if contemplated

(including action to be taken by other agencies such as State Government) should be covered.

Project Proponent shall conduct Impact of Transportation study as per Indian Road Congress

Guidelines.

32) Details of the onsite shelter and facilities to be provided to the mine workers should be

included in the EIA Report.

33) Conceptual post mining land use and Reclamation and Restoration of mined out areas (with

plans and with adequate number of sections) should be given in the EIA report.

34) Occupational Health impacts of the Project should be anticipated and the proposed preventive

measures spelt out in detail. Details of pre-placement medical examination and periodical

medical examination schedules should be incorporated in the EMP. The project specific

occupational health mitigation measures with required facilities proposed in the mining area

may be detailed.

35) Public health implications of the Project and related activities for the population in the impact

zone should be systematically evaluated and the proposed remedial measures should be

detailed along with budgetary allocations.

Final minutes of 4.95th meeting held on 27-29 July, 2021

36) Measures of socio economic significance and influence to the local community proposed to be

provided by the Project Proponent should be indicated. As far as possible, quantitative

dimensions may be given with time frames for implementation.

37) Detailed environmental management plan (EMP) to mitigate the environmental impacts

which, should inter-alia include the impacts of change of land use, loss of agricultural and

grazing land, if any, occupational health impacts besides other impacts specific to the

proposed Project.

38) Public Hearing points raised and commitment of the Project Proponent on the same along

with time bound Action Plan with budgetary provisions to implement the same should be

provided and also incorporated in the final EIA/EMP Report of the Project.

39) Details of litigation pending against the project, if any, with direction /order passed by any

Court of Law against the Project should be given.

40) The cost of the Project (capital cost and recurring cost) as well as the cost towards

implementation of EMP should be clearly spelt out.

41) A Disaster management Plan shall be prepared and included in the EIA/EMP Report.

42) Benefits of the Project if the Project is implemented should be spelt out. The benefits of the

Project shall clearly indicate environmental, social, economic, employment potential, etc.

43) Besides the above, the below mentioned general points are also to be followed:-

a) Executive Summary of the EIA/EMP Report

b) All documents to be properly referenced with index and continuous page numbering.

c) Where data are presented in the Report especially in Tables, the period in which the data

were collected and the sources should be indicated.

d) Project Proponent shall enclose all the analysis/testing reports of water, air, soil, noise etc.

using the MoEF&CC/NABL accredited laboratories. All the original analysis/testing reports

should be available during appraisal of the Project.

e) Where the documents provided are in a language other than English, an English translation

should be provided.

f) The Questionnaire for environmental appraisal of mining projects as devised earlier by the

Ministry shall also be filled and submitted.

g) While preparing the EIA report, the instructions for the Proponents and instructions for

the Consultants issued by MoEF&CC vide O.M. No. J-11013/41/2006-IA.II(I) dated 4th

August, 2009, which are available on the website of this Ministry, should be followed.

h) Changes, if any made in the basic scope and project parameters (as submitted in Form-I

and the PFR for securing the TOR) should be brought to the attention of MoEF&CC with

reasons for such changes and permission should be sought, as the TOR may also have to be

altered. Post Public Hearing changes in structure and content of the draft EIA/EMP (other

Final minutes of 4.95th meeting held on 27-29 July, 2021

than modifications arising out of the P.H. process) will entail conducting the PH again with

the revised documentation.

i) As per the circular no. J-11011/618/2010-IA.II(I) dated 30.5.2012, certified report of the

status of compliance of the conditions stipulated in the environment clearance for the existing

operations of the project, should be obtained from the Regional Office of Ministry

ofEnvironment, Forest and Climate Change, as may be applicable.

j) The EIA report should also include (i) surface plan of the area indicating contours of main

topographic features, drainage and mining area, (ii) geological maps and sections and (iii)

sections of the mine pit and external dumps, if any, clearly showing the land features of the

adjoining area.

Specific ToR in the cases of cluster situation:

1. The PP shall conduct Environmental Impact Assessment Study and prepare

Environmental Management Plan for the entire cluster in order to capture all the possible

externalities. These reports are required to incorporate carrying capacity of the cluster,

transportation and related issues, replenishment and recharge issues, geo- hydrological

study of the cluster.

2. The EIA/EMP shall be prepared by the state or state nominated agency or group of PP in

the cluster or the PP in the cluster. The PP shall get one public consultation done for the

entire cluster and after which prepare final EIA/EMP reports.

Specific ToRs applicable, in the cases of violation in terms of the Notification dated

14.3.2017 and 8.3.2018 and OMs dated 30.5.2018, 4.7.2018 of the MoEF & CC :

1. The PP shall undertake assessment of ecological damage, remediation plan and

natural and community resource augmentation plan. Such plan shall be prepared as an

independent chapter in the Environment Impact Assessment report. The report shall

be prepared by the accredited consultant. Collection and analyses of data for

assessment of ecological damage, preparation of remediation plan and natural and

community resource augmentation plan shall be done by an environmental laboratory

duly notified under the Environment (Protection) Act, 1986 or an environmental

Laboratory, accredited by the National Accreditation Board for Testing and

Calibration Laboratories or a Laboratory of the Council of Scientific and Industrial

Research Institution working in the field of environment.

2. The Environment Management Plan shall comprise remediation plan and natural and

community resource augmentation plan corresponding to ecological damage assessed

and economic benefit derived due to the violation.

3. The PP shall undertake Final Environment Impact Assessment and prepare Final

Environment Management Plan after conducting Public Hearing.

4. The PP shall be required to submit a bank guarantee equivalent to the amount of

remediation plan and natural and community resource augmentation plan with the

State Pollution Control Board and the PP shall deposit the bank guarantee prior to the

grant of Environmental Clearance and which shall be released after successful

implementation of the remediation plan and natural and community resource

Final minutes of 4.95th meeting held on 27-29 July, 2021

augmentation plan and after recommendation by Regional Office of the Ministry,

State Level Expert Appraisal Committee and approval of SEIAA.

5. The project Proponent shall give an undertaking by way of affidavit to comply with

all the statutory requirements and judgment of Hon’ble Supreme Court dated the 2nd

August 2017 in Writ Petition (Civil) No. 114 of 2014 in the matter of Common Cause

versus Union of India and Ors. before grant of ToR/ EC the undertaking inter-alia

include commitment of the PP not to repeat any such violation in future.

6. In case of violation of above undertaking, the Environmental Clearance shall be liable

to be terminated forthwith as per OM dated 30.5.2018 of the MoEF&CC.

7. The Environmental Clearance will not be operational till such time the project

Proponent complies with all the statutory requirements and judgment of Hon’ble

Supreme Court dated the 2nd August 2017 in Writ Petition (Civil) No. 114 of 2014 in

the matter of Common Cause versus Union of India and Ors.

8. State Government concerned shall ensure that mining operation shall not commence

till the entire compensation levied, if any, for illegal mining is paid by the Project

Proponent through their respective Department of Mining & Geology in strict

compliance of judgment of Hon’ble Supreme Court dated 2nd August 2017 in Writ

Petition (Civil) No. 114 of 2014 in the matter of Common Cause versus Union of

India and Ors.

The validity period of this ToRs letter would be for a period of four years from the date of

dispatch of the ToRs letter.

S. No Items in the letter of the ToRs Reply / Response by the PP