Initial Environmental Examination - 51337-001: Tamil Nadu ...

466
Initial Environmental Examination Project Number: P51337-001 December 2020 India: Tamil Nadu Industrial Connectivity Project CheyyurVandavasiPolur (C-V-P) Road & ECR LINK: CheyyurPanaiyur (ODR)Road (SH115) Prepared by Highways and Minor Ports Department (TNHD), Government of Tamil Nadu for the Asian Development Bank.

Transcript of Initial Environmental Examination - 51337-001: Tamil Nadu ...

Initial Environmental Examination Project Number: P51337-001 December 2020

India: Tamil Nadu Industrial Connectivity Project Cheyyur–Vandavasi–Polur (C-V-P) Road & ECR LINK: Cheyyur–Panaiyur (ODR)Road (SH115)

Prepared by Highways and Minor Ports Department (TNHD), Government of Tamil Nadu for the Asian Development Bank.

CURRENCY EQUIVALENTS (as of 30 November 2020)

Currency unit Re1.00 $1.00

= = =

Indian rupee/s (Re/Rs) $0.013 Rs.74.9311

ABBREVIATION

AADT - Annual Average Daily Traffic AAQM - Ambient air quality monitoring ADB - Asian Development Bank AMSL - Above Mean Sea Level ASI - Archaeological Survey of India BDL - Below detectable limit BGL - Below ground level BOD - Biochemical oxygen demand BOQ - Bill of quantity CGWA - Central Ground Water Authority CKICP - Chennai Kanyakumari Industrial Corridor Project CO - Carbon monoxide COD - Chemical oxygen demand CPCB - Central Pollution Control Board CSC - Construction Supervision Consultant DFO - Divisional Forest Officer DG - Diesel generating set DO - Dissolved oxygen DPR - Detailed project report E&S - Environment and social EA - Executing agency EAC - Expert Appraisal Committee EFP - Environmental Focal Person EHS - Environment Health and Safety EIA - Environmental impact assessment EMOP - Environmental monitoring plan EMP - Environmental management plan FIU - Field Implementation Unit FRL - Finished Road Level GHG - Greenhouse gas GIS - Geographical information system GOI - Government of India GRC - Grievance redress committee GRM - Grievance redress mechanism HFL - Highest flood level IA - Implementing Agency IEE - Initial Environmental Examination IMD - Indian Meteorological Department IRC - Indian Road Congress IUCN - International Union for Conservation of Nature LHS - Left hand side LPG - Liquefied petroleum gas MOEFCC - Ministry of Environment, Forest and Climate Change MORTH - Ministry of Road Transport and Highways

N, S, E, W, NE, SW, NW

- Wind Directions (North, South, East, West or combination of Two directions like South West, North West)

NGO - Non-governmental organization NH - National Highway NOC - No Objection Certificate NOx - Oxides of nitrogen PAP - Project Affected Persons PAs - Protected Areas PCR - Public Community Resources PCU - Passenger Car Units PD - Project Director PM - Particulate Matter PIU - Project Implementation Unit PPE - Personal protective equipment PPT - Parts per trillion PUC - Pollution Under Control R & R - Rehabilitation and Resettlement RHS - Right hand side ROB - Road Over Bridge ROW - Right of way SEIAA - State Environmental Impact Assessment Authority SH - State highway SO2 - Sulphur Dioxide SOI - Survey of India SPCB - State Pollution Control Board SPL - Sound Pressure Level SPM - Suspended Particulate Matter SPS - ADB Safeguard Policy Statement, 2009 ST - Scheduled Tribes TA - Technical assistance TDS - Total dissolved solids TNRSP - Tamil Nadu Road Sector Project TSS - Total Suspended Solids ZSI - Zoological survey of India

WEIGHTS AND MEASURES

dB(A) – A-weighted decibel ha – hectare km – kilometer µg – microgram m – meter MW (megawatt) – megawatt PM 2.5 or 10 – Particulate Matter of 2.5 micron or 10 micron size

NOTE

In this report, "$" refers to US dollars.

This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

TABLE OF CONTENTS

Executive Summary ............................................................................................................. i

I. INTRODUCTION ............................................................................................................ 1

A. Project Background .................................................................................................... 1 B. Nature, Size and Location of Project Road ................................................................. 2 C. Background of the Present Report .............................................................................. 3 D. Objective and Scope of the Study ............................................................................... 3 E. Methodology Adopted for IEE Study ........................................................................... 4 F. Structure of the Report ................................................................................................ 6

II. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK ........................................... 8

A. National (India) Environmental Policy Framework ....................................................... 8 B. Social Regulatory Requirements of India and Tamil Nadu ........................................ 12 C. International Treaties and Relevance to the Project .................................................. 12 D. Project Standards ..................................................................................................... 13 E. ADB’s Safeguard Policy Statement Requirements .................................................... 13 F. Category of the Project ............................................................................................. 13

III. PROJECT DESCRIPTION ........................................................................................... 14

A. Type and Features of Project .................................................................................... 14 B. Location of the Project Road ..................................................................................... 15 C. Engineering Surveys and Investigations ................................................................... 18 D. Design Standards ..................................................................................................... 19 E. Proposed Improvement ............................................................................................. 25 F. Construction Camps ................................................................................................. 47 G. Project Cost .............................................................................................................. 47 H. Construction Packaging and Implementation Schedule ............................................ 47 I. Project Benefits......................................................................................................... 47

IV. DESCRIPTION OF THE ENVIRONMENT .................................................................... 49

A. Introduction ............................................................................................................... 49 B. Physical Environment ............................................................................................... 51 C. Coastal and Marine Resources in Project Influence Area ......................................... 76 D. Biological Environment ............................................................................................. 77 E. Socio-economic Environment ................................................................................... 86

V. ANALYSIS OF ALTERNATIVES ................................................................................. 92

A. With Project’ and ‘Without Project’ Scenario ............................................................. 92 B. Location and Alignment Alternatives ......................................................................... 96 C. Design Decision Constraints For Various Alternatives ............................................ 103 D. Alignment Modifications due to Environmental Considerations ............................... 103 E. Engineering / Technological Alternatives ................................................................ 104

VI. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ....... 105

A. Introduction ............................................................................................................. 105 B. Screening of Impacts .............................................................................................. 109 C. Typical Potential Adverse Impacts .......................................................................... 113 D. Impacts on Physical Environment ........................................................................... 113

E. Impacts on Biological environment ......................................................................... 128 F. Impacts on Social Environment ............................................................................... 131 G. Physical and Cultural Resources ............................................................................ 149 H. Induced and Cumulative Impacts ............................................................................ 149 I. Expected benefits from the Project ........................................................................ 149

VII. CONSULTATION, PARTICIPATION AND INFORMATION DISCLOSURE ............... 150

A. Meaningful Consultation ......................................................................................... 150 B. Objectives of the Consultations ............................................................................... 150 C. Methodology for Consultations ................................................................................ 150 D. Interaction with NGOs ............................................................................................. 155 E. Public Disclosure and Further Consultations ........................................................... 155

VIII. GRIEVANCE REDRESS MECHANISM ..................................................................... 156

IX. ENVIRONMENTAL MANAGEMENT PLAN ............................................................... 158

A. Introduction ............................................................................................................. 158 B. Objectives of Environmental Management Plan ...................................................... 158 C. Environmental Management Plan Matrix................................................................. 158 D. Environmental Monitoring and Reporting Program .................................................. 158 E. Institutional Requirements ...................................................................................... 185 F. Environmental Reporting System ............................................................................ 191 G. Environmental Management Budget ....................................................................... 192

X. CONCLUSIONS AND RECOMMENDATIONS .......................................................... 199

APPENDICES ................................................................................................................... 201

LIST OF TABLES Table 1: Project road details (SH-115) 1 Table 2: Location Details of Project Road Sections 2 Table 3: Primary and Secondary Information Sources 5 Table 4: Applicable Environmental National and State Requirements 9 Table 5: Cheyyur to Polur Project Road (SH-115) Road Features 14 Table 6: Annual Average Daily Traffic Volume along Homogenous Road Sections 16 Table 7: Villages and Urban Built Up Locations on Project Road and RoW 17 Table 8: Radius for Horizontal Curves 20 Table 9: Sight Distance 22 Table 10: Junction Improvement with Transverse Rumble Strip 40 Table 11: Environmental Attributes and Frequency of Monitoring 49 Table 12: Average Annual Rainfall (mm) in Project Districts 52 Table 13: Quality Monitoring Results for the Project Road 60 Table 14: Details of Waterbodies along the Project Road 63 Table 15: Details of Drainage along Project Road 64 Table 16: Water Quality Monitoring Locations 65 Table 17: Surface Water Quality Characteristics along the Project Road 65 Table 18: Ground Water Quality Characteristics along the Project Road 68 Table 19: Details of Ambient Air Quality Monitoring Locations along Project Road 71 Table 20: Techniques Used for Ambient Air Quality Monitoring 72 Table 21: Summary of AAQM Results along the Project Road 72 Table 22: Details of Noise Level Monitoring Locations 74 Table 23: Ambient Noise Level in dB(A) along the Project Road 75 Table 24: Forest Cover in Project Districts (Km2) 78 Table 25: Forest areas along the Project Road 78 Table 26: Tree Enumeration within Formation Width of Project Road (>30 cm) 79 Table 27: IUCN status of Major Tree Species within Formation Width (>30 cm) 80 Table 28: Protected areas of Tamil Nadu 80 Table 29: List of Fauna in the influence area of project road 85 Table 30: Physical /Sensitive Features along the Project Road 88 Table 31: Comparison of Positive and Negative Impacts of ‘With’ and ‘Without’ Project

Scenario 94 Table 32: Comparison of Alternative Alignments of Proposed Bypass For Vandavasi Town

(SH-115) 97 Table 33: Comparison of Alternative Alignments of Proposed Bypass for Chetpet Town (SH-

115) 101 Table 34: Sensitivity of VECs in the Project Area 107 Table 35: Criteria for Rating the Significance of Impacts 109 Table 36: Screening of Environmental Impacts 110 Table 37: Impact on Air Quality during Construction Stage 114 Table 38: Annual Average Daily Motorized Traffic Data 115 Table 39: Emission Factors for Different Types of Vehicle (ARAI, 2007) 116 Table 40: Meteorological Parameters used for Modelling 116 Table 41: Average Background Concentration of Pollutants along the Project Road 117 Table 42: CO Predicted Concentrations (ppm) along the Proposed Road 118 Table 43: PM2.5 Predicted Concentrations (µg/m3) along the Proposed Road 118 Table 44: PM10 Predicted Concentrations (µg/m3) along the Proposed Road 118 Table 45: NOx Predicted Concentrations (µg/m3) along the Proposed Road 119 Table 46: SO2 Predicted Concentrations (µg/m3) along the Proposed Road 119

Table 47: Construction Noise / Distance Relationship 133 Table 48: Likely Impact on Noise Quality in the Vicinity of Project Area 133 Table 49: Typical Noise Levels of Principal Construction Equipment (Noise Level in dB (A)

at 50 Feet) 134 Table 50: List of Sensitive Recepator along the Project Road 135 Table 51: Annual Average Daily Motorized Traffic Data 140 Table 52: Equivalent Background Noise levels 140 Table 53: Predicted Noise Levels along the Project Road 142 Table 54: Vibration Generated from Different Construction Equipment 143 Table 55: Building Vibration Damage Assessment Criteria 144 Table 56: The details of Public Consultation for Project Road 151 Table 57: Summary of Issues Discussed and Measures Taken 153 Table 58: Environmental Management Plan 161 Table 59: Environmental Monitoring Plan (EMoP) 181 Table 60: Environmental Reporting System 192 Table 61: Environmental Management Cost Estimates* 193

LIST OF FIGURES

Figure 1: Location of Project Road Alignment on Map 3 Figure 2: Typical Road Cross Sections 26 Figure 3: Environmental Monitoring Locations along the Project Road 50 Figure 4: Rainfall Distribution in the State of Tamil Nadu 52 Figure 5: Temperature Distribution Map of Tamil Nadu 53 Figure 6: Humidity Map of Tamil Nadu 54 Figure 7: Topographic map of Tamil Nadu 55 Figure 8: Elevation Map of Project Road and District 56 Figure 9: Geological Map of Tamil Nadu 57 Figure 10: Soil Texture Map of Tamil Nadu 58 Figure 11: Soil Order Map of Tamil Nadu 59 Figure 12: Soil Type Based on Water Retention Properties 59 Figure 13: Seismic Map of Tamil Nadu State 62 Figure 14: River Basins and Water Resources Map of Tamil Nadu 63 Figure 15: Coastal Zone Management Plan of Tamil Nadu 77 Figure 16: Forest Cover Map of Tamil Nadu showing Project Road 79 Figure 17: Protected Area Map of Tamil Nadu 83 Figure 18: Alternative Alignments of Proposed Bypass For Vandavasi Town (SH-115) 96 Figure 19: Alternative Alignments of Proposed Bypass For Chetpet Town (SH-115) 100 Figure 20: Photographs of Public Consultation 152 Figure 21: Grievance Redress Mechanism 157

EXECUTIVE SUMMARY

A. Introduction

1. The Government of Tamil Nadu proposes to upgrade its road network falling in the conceptual influence area of the Chennai Kanyakumari Industrial Corridor (CKIC), which aims at improving the transport infrastructure, such as the connectivity of industrial nodes to ports, urban areas and critical hinterland areas. The Highways and Minor Ports Department (TNHD) of Tamil Nadu has been mandated to undertake improvement and upgradation of various State Highways at different locations in the State and will serve as the Executing Agency (EA) under this project. As part of this mandate, the Construction and Maintenance (C&M) Wing of TNHD has identified the 16 road sections for improvement totaling about 590 km spread across the State. The project will be financed through a project loan from the Asian Development Bank (ADB) under Tamil Nadu Industrial Connectivity Project (TNICP). The Project Implementation Unit (PIU) formed within TNHD will be the Implementing Agency (IA).

2. As part of detailed project report (DPR) preparation, this Initial Environmental Examination (IEE) report was prepared to cover Cheyyur – Vandavasi - Chetpet - Polur section of SH 115 and Cheyyur – Panayur section of ECR link road. The total design length of the road alignment is 109.273 km covering eight sections. The details of these road sections taken up as project road are presented below:

Sl. No.

Design Chainage (km) Length (m) Widening

From To

1 1.620 42.840 41220 2-lane with Paved Shoulder (SH-115)

2 45.060 47.920 2860 2-lane with Paved Shoulder (SH-115)

3 53.810 79.390 25580 2-lane with Paved Shoulder (SH-115)

4 82.980 106.246 23266 2-lane with Paved Shoulder (SH-115)

5 42.840 45.060 2220 2-lane with Paved Shoulder Maruthadu Realignment

6a 47.920 52.185 4265 2-lane with Paved Shoulder Vandavasi Bypass

6b 52.185 52.545 360 Divided 4 lane – RUB (Vehicular Underpass Portion) Vandavasi Bypass

6c 52.545 53.810 1265 2-lane with Paved Shoulder Vandavasi Bypass

7 79.390 82.980 3590 2-lane with Paved Shoulder Chetpet Bypass

8 0.000 4.647 4647 2-lane with Paved Shoulder ECR Link (ODR)

Total Length (m) 109,273 109.273km

3. As per provisions of the EIA Notification 2006 (amended in 2020), all new state highway and state highway expansion projects except in hilly terrain (above 1,000m AMSL) and or notified ecologically sensitive areas fall under Category B and does not require environmental clearance from the State Environmental Impact Assessment Authority (SEIAA). The project road section is a state highway located on plain terrain with elevation is below 1000m AMSL. The project road alignment is not passing through any forest area and notified protected area. Thus, the project

ii

road does not fall under the purview of environmental clearance under EIA notification 2006 of MOEFCC.

4. IEE has been prepared in accordance with relevant policies and regulations of the Government of India, Government of Tamil Nadu (GoTN), and the ADB’s Safeguard Policy Statement 2009 (SPS). This IEE report will be disclosed in the office of TNHD and on the ADB website. The project road sections are located in Chengalpattu (Kanchipuram bifurcated into Chengalpattu and Kanchipuram districts) and Thiruvannamalai districts of Tamil Nadu.

B. Description of the Project

5. The length of the project road section is 109.273 km. This Project road, the State Highway 115 originates from Cheyyur and ends with NH-234 in Polur (design km 1.620 to 106.246 and existing km1.620 km to km103.780) and the link road from Cheyyur to East Coast Road (ECR) is other district road section originates from Cheyyur at km 0.000 and terminates at km (4.720) with ECR (design chainage 0.000 km to 4.647 km and existing chainage 0.000 km to 4.720 km). The existing road sections are of mostly 2-lane confirguration without proper shoulders, and poor pavement condition.

6. The existing road section is planned to be widened to 2 lane configuration with paved shoulders in this project. The road section will be widened following existing alignment and twonew bypasses are proposed for Vandvasi and Chetpet towns and One Maruthadu realignment. The road section traverses through plain terrain. The project road alignment is linear in nature.

7. The landuse along the project road is mostly agriculture and passes through 59 builtup/villages. Around 6% of project road passes through forest area (RoW excluded from RF), 43% passes through builtup/habitation areas and 51% passes through agricultural areas.

8. One realignment at Marudharu Village and two bypasses are proposed for Vandavasi and Chetpet towns for free movement of the traffic. Vandavasi bypass starts from km 47+920 and ends at km 53+810. Total length of this bypass is 5.89 km. Chetpet bypass starts from km 79+390 and ends at km 82+980. Total length of this bypass is 3.59 km. Additionally geometric improvement is proposed at Maruthadu Village which starts at km 42+84 and ends at km 45+06 for a length of 2.22 km.

9. The bridge and culvert inventory was carried out to assess the existing condition and hydrological adequacy. There are existing 214 culverts along the project road. 94 culverts will be reconstructed, 30 are retained, 68 will be widened and additional 52 new culverts are proposed depending on the hydrological requirements along along SH-115 and ECR link project road sections. There are 5 major bridges, 12 minor bridges, and 1 RUB and 1 railway level crossing existing along the road.

10. The proposed RoW for the 2-lane configuration has been fixed as 16.0m in urban built-up areas and 30m in open and rural areas. For the bypass section in green field it has been fixed as 30m. For realignment and bypass following existing alignment of village road PRoW is 16 m for in urban and built up areas and 23 m in rural areas. A total of 41.9833 ha. additional land will be acquired for realignment and for proposed bypass sections. C. Description of the Environment

i. Physical Environment 11. Meteorological Conditions: The climate of Tamil Nadu state is tropical, with distinct wet and dry seasons. According to Agro-ecological classification, the state has a hot and semi-arid

iii

climate. The climate may be classified into four distinct seasons: winter (January – February), summer (March – May), southwest monsoons (June – September) and northeast monsoon (October – December). The project road section is located in two districts. The details of physical environmental parameters of the district are: Parameter Value Average Annual Rainfall The average annual rainfall in the project area varies from

773 mm to 1775 mm (Vandavasi: 957 mm to 1407 mm, Kanchipuram: 773 mm to 1775 mm, Chengalpattu: 1092 mm to 1534 mm, Arani: 826 mm to 1570 mm).

Concentration of precipitation Rainfall mainly occurs during north to east monsoon. Monsoon season starts in June and ends in the month of November.

Humidity Humidity generally varies in the range of 35 to 95% throughout the year.

Wind Generally light except rainy season Temperature In project districts, April and May months are the hottest

months with mean monthly temperature varying between 36.3 oC and 40.8 oC. December and January are comparatively the coolest months with average mean monthly temperature varying from 16.1 to 20.5 oC.

12. Geography and Topography: The project region has plain topography having an altitude in the range of 1-300m AMSL. The land use in the project area is mainly agricultural followed by built up areas and forests. elevation of project road varies from 3m - 174m in the project area. The average elevation of project road is 93m AMSL. 13. Land use: Road area is predominantly agricultural land (66%) followed by built-up areas (43%) and forests (6%). Agriculture is the main occupation of the people with 47% of the population engaged in it. Paddy is the major crop cultivated in this district. Groundnuts, Sugarcane, Cereals & Millets and Pulses are the other major crops cultivated. Also, it is to be noted that the project road passes through reserved Reserved Forest (RoW excluded) and social forests in multiple patches.

14. Geology: Geologically, the entire state can be broadly classified into hard rock or crystalline formation and sedimentary formations. Nearly 73% of the state is underlain by crystalline rocks of Archean metamorphic complex comprising of granite, charnockites, gneisses, chists etc. They are further intruded at many places by quartz veins, pegmatites and other ultra-basics like dolomites. The sedimentary rocks occur along the coast, flanking the crystalline mass in the west. Geological formation in the project area comprises mainly of alluvium.

15. Soil: The soil in general is silty, sandy and clay with good amount of primary nutrients i.e., nitrogen (N), phosphorus (P) and potassium (K) content. It is dry in nature and chemically neutral or slightly basic (pH range 6.61 - 8.47). It is observed that the soil in the project area is fertile with high agricultural productivity with appropriate use of fertilizer. Based on water retention characteristics, a portion of project region have soils that have low water retention and rest portion have soil that have high water retention characteristic.

16. Water Resources: Cheyyar and Vegavathi are the small tributaries of Palar river. Cheyyar and Ponaiyar rivers are the major rivers in Thiruvannamalai district. In order to represent the true profile of the project area, samples from surface water source through which the project road runs were collected and analyzed as per IS- 2488 (Part I-V). Ground water (drinking water) samples were analyzed as per IS: 10500-1991. Water quality was monitored at six locations at three for

iv

surface and three for ground water. Results show that the pH of the drinking water in the region is well within permissible limits (6.5 – 7.5). The samples collected from ground water shows the parameter is well within the permissible standards, except TDS and Total Hardness for drinking water. Other parameters analyzed like chloride, sulphate, fluorides are found well within standards. Overall, the ground water quality in the project area is good.

17. Air Quality: Ambient air quality in the state is quite pure compared to other neighboring states. Ambient air quality for particulate matters (PM10 and PM2.5), SO2, NOx and CO was monitored at five locations along the project road. It is found from the results that PM10 concentration at both monitoring locations were well within the permissible limits for residential zone i.e. 100 μg/m3 prescribed by the Ministry of Environment, Forest and Climate Change (MOEFCC) but slightly higher than IFC EHS guideline limit of 50 μg/m3. The highest value of PM10 is observed at Govt Primary School, Kattuthevathur (71.2μg/m3 ), which is well within permissible limits. Similarly, PM2.5 concentration is highest at Govt Primary School, Kattuthevathur and is 24.5 μg/m3 well within the permissible limit i.e. 60 μg/m3 prescribed by MOEFCC and within limits of of 25 μg/m3 as mentioned in the IFC EHS guideline. Other parameters monitored i.e. NOx, SO2 were found within the permissible limits for all the locations. Overall, the air quality in the project area is good.

18. Noise Levels: Noise levels were monitored at twelve locations along the project road. It is found that hourly day equivalent noise level varies from 54.43 dB(A) to 72.14 dB(A), whereas hourly night equivalent noise level ranges from 49.35 dB (A ) to 63.81 dB(A). The recorded noise level is higher than the Central Pollution Control Board (CPCB) as well as IFC permissible limits for residential area of 55 dB(A) and 45 dB(A) for daytime and nighttime, respectively. This noise is mainly from vehicular traffic and local domestic/commercial activities.

ii. Biological Environment 19. There is no protected area (National Park, Wildlife Sanctuary, Biosphere Reserve, Wetland) directly falling within the proposed RoW of project road. However, small section of the project road passes through social forests and reserved forests but the RoW has already been excluded from forests. Total 6.977 km length of project road passes through forest areas. However, the existing RoW of the project road is available for improvement works in the forest area and no forest land diversion is required for project. Thus does not attract forest clearance.

20. The dominant tree species along project road are Mango, Tamarind, Palm, Neem, Coconut, Peepal, Indian beech, Siris and Black Plum. Other observed species are either Least Concerned or not yet been assessed for the IUCN Red List. There are no vulnerable/ endangered or rare species fauna around the project site. There is no presence of any fauna species listed in Schedule I of the Wild Life (Protection).

iii. Socio-economic Environment

21. The project road passes through two districts of Tamil Nadu namely Kanchipuram and Tiruvannamalai. Kanchipuram: According to 2011 census, Kanchipuram district had a population of 3,998,252 with male population of 2012958 and female population of 1985294. Sex-ratio of district is 986 females for every 1,000 males, much above the national average of 929. Male and female literacy rate in the district is 89.89% and 79.02% respectively. The population density in the district is 892 persons per sq.km. Scheduled Castes and Scheduled Tribes accounted for 23.71% and 1.03% of the population respectively. The average literacy of the district was 75.37%, compared to the national average of 72.99%. The district had a total of 1,006,245 households. There was a total of 1,673,814 workers, comprising 74,761 cultivators, 162,494 main agricultural labourers, 41,149 in house hold industries, 1,088,974 other workers, 306,436 marginal workers,

v

14,582 marginal cultivators, 110,020 marginal agricultural labourers, 13,583 marginal workers in household industries and 168,251 other marginal workers.

22. According to 2011 census, Tiruvannamalai District had a population of 2,464,875 with a sex-ratio of 994 females for every 1,000 males, much above the national average of 929. A total of 272,569 were under the age of six, constituting 141,205 males and 131,364 females. Scheduled Castes and Scheduled Tribes accounted for 22.94% and 3.69% of the population respectively. The average literacy of the district was 66 %, compared to the national average of 72.99%. The district had a total of 588,836 households. There was a total of 1,238,177 workers, comprising 265,183 cultivators, 351,310 main agricultural labourers, 37,020 in house hold industries, 316,559 other workers, 268,105 marginal workers, 27,458 marginal cultivators, 173,753 marginal agricultural labourers, 9,700 marginal workers in household industries and 57,194 other marginal workers.

23. Most of the land surrounding the project road are agricultural fields with intermittent rural/urban build up structures. The major land use along the project roads is agriculture, followed by rural settlement, urban settlement, open and forest land. There are important community structures along the project road, which has cultural and sociological importance.

24. There are 108 sensitive receptors/structures present within 50 m from center line of the road. No archaeological sites or historical monuments notified under Tamil Nadu State importance under “Ancient and Historical Monument and Archaeological Sites and Remains Act, 1966 of Tamil Nadu and National importance under “The Ancient Monuments and Archaeological Sites and Remains Act 1958 of India are located along the project road section.

D. Analysis of Alternatives 25. Since the proposed project is an improvement of the existing road section of SH-115 from design chainage km 1+620 to km 106+246 in plain terrain, except in the proposed bypass sections. Two bypasses are proposed for Vandavasi and Chetpet towns and one realignmnent in Maruthadu for free movement of the traffic and saving in travel time and fuel. The project road alignment is linear in nature.

26. Vandavasi bypass starts from km 47+920 and ends at km 53+810. Total length of this bypass is 5.89 km. Chetpet bypass starts from km 79+390 and ends at km 82+980. Total length of this bypass is 3.59 km. Additionally geometric improvement is proposed at Maruthadu Village which starts at km 42+84 and ends at km 45+06 for a length of 2.22 km.

27. Three options for each proposed bypasses were considered and studied with merits and demerits for selection of one feasible option. There are few sharp and blind curves along the project road for which curve improvements have been proposed to improve the geometry and safety. The improvement of curves on existing state highway section was determined to be the best possible within existing RoW or minimal additional land acquisition.

28. The alternatives were considered in road design such as cross sections, soil erosion and slope protections, drainage structures, flexible pavement etc. The analysis of alternatives has also been made on the basis of “with and without project scenarios” in terms of potential environmental impacts. On the basis of the analysis, we can say that “with project” scenario will provide beneficial impacts, greatly improve the environment and enhance social and economic development of the region compared to “without project” scenario, which will further deteriorate the existing environment and quality of life.

vi

E. Consultation, Disclosure and Grievance Redress Mechanism 29. In accordance with ADB’s Safeguard Policy Statement (SPS) 2009, public consultations were held as part of the IEE study. Consultations were undertaken with project beneficiaries, local/ government officials, community leaders, women groups, stakeholders in corridor of impact and people likely to be affected by the project. Various measures pertaining to environmental issues were incorporated based on the responses from the people. Both formal and informal modes of consultation were used in the public consultation process for the project.

30. Consultations were carried out using standard structured questionnaires as well as unstructured questionnaires. In addition, focused group discussions (FGDs) and personal discussions with officials from key line agencies, on-site discussion with project affected stakeholders, and reconnaissance visits have also been made to the project areas. The attempts were made to encourage participation in the consultation process of the Government officials from different departments that have relevance to the project. Same way, local people from different socio-economic backgrounds in the villages as well as urban areas along the road alignment and at detours, residents near the existing road, women representatives, local commuters, and other concerned were also consulted.

31. The consultations were conducted during preparation of the IEE. Six consultations with the key stakeholders were undertaken in the months of September 2019 and January 2020 at Karaipondi, Vadavankkambadi and Cheyyur as part of DPR preparation. Various officials consulted include TNHD Officials, Forest Officers, Environmental Officers from pollution control board, statistical officer in the project areas etc. Besides interview surveys, FGDs were organized at key locations along the project road. In total 50 people were involved in the consultations. Most of the people interviewed strongly support the project. The people living in the entire project area expect the different project elements to facilitate transport, employment, boost economic development and thereby provide direct, and indirect benefits to them.

32. In compliance with ADB’s SPS requirements consultation will be continued throughout the project process. Prior to finalization of detailed engineering design, the contractor, with the assistance of the PIU should consult affected persons. Further, project consultations will be organized by the FIU in coordination with Construction Supervision Consultant (CSC) and with the presence of representatives from the contractor. These should be done at least quarterly during construction period.

33. A Grievance Redress Mechanism (GRM) will be established by TNHD prior to mobilization of contractors to address grievances related to the implementation of the project, particularly regarding the EMP. Through the GRM, responsible parties will acknowledge, evaluate, and respond to the complainant with corrective action proposed using understandable and transparent processes that are gender responsive, culturally appropriate, and readily accessible to all segments of the affected people.

34. Records of grievances received, corrective actions taken, and their outcomes will be properly maintained and form part of the quarterly progress reports (QPR) and semi-annual environmental monitoring report to ADB. The Project GRM will be established to evaluate and facilitate the resolution of affected persons concerns, complaints, and grievances related to environmental aspects of the project. The GRM will aim to provide a time-bound and transparent mechanism to voice and to resolve the concerns linked with the project. Depending on the nature and significance of the grievances or complaints, the grievance redress mechanism (GRM) will comprise procedures to address grievances at several levels. A two-tier GRM will be established. Regional Level Project GRC will be chaired by the TNHD Divisional Engineer concerned and would comprise of TNHD Environment Wing Assistant Environment Specialist, Project Manager

vii

of EPC contractor and Resident Engineer of CSC concerned. Complaints that cannot be resolved at the field level within 7 days will be elevated to the State Level Project GRC. It will serve as appellate authority and will be chaired by the Chief Engineer and will comprise the Superintending Engineer concerned, Environment Specialist, Team Leader of CSC concerned, Project Manager from Project Management Services of CSC-01 and Authorized Representative from EPC contractors, as needed. Grievance response period for all GRCs is 3 weeks.

35. As project executing agency, TNHD will be responsible for the disclosure of this IEE in compliance to ADB’s Access to Information Policy 2019 and ADB SPS 2009. The report will be made available to interested parties on request from the office of the TNHD. Since this is environment Category B project, the IEE report will be disclosed to the public through the ADB and CKICP websites.

F. Project Benefits 36. The key positive environmental impacts of the project include improved vegetation cover, increase in area of good quality habitat by tree plantation 1:10 tree removed for the project through compensatory afforestation, which will be fully realized in 10-15 years and improvement of infrastructure along the project area. Further, the implementation of various project items is envisaged to have the following direct benefits:

• better connectivity to key locations within State;

• smooth flow of traffic on State Highway Network;

• improved quality of life for the rural population in the project influence: this as a result of better access to markets, health, education and other facilities; and the derived stimulus for local economic activity;

• a more efficient and safe road transport system: through reduced travel times, reduced road accidents, reduced vehicle operating and maintenance costs and reduced transportation costs for goods;

• the facilitation of tourism.

G. Anticipated Environmental Impacts and Mitigation Measures 37. Based on analysis of project activities and environmental baseline conditions, various valued environmental components (VECs) under physical, biological and social environment were identified. Assessment of the impacts on each of these VECs during pre-construction and design stage, construction stage and operation stage was carried out. Impacts were determined to be minor, moderate or major based on a rating criterion of sensitivity of the VEC, duration of impact, area of impact and severity of impact.

38. Most negative impacts are of minor to moderate risk. There is no potential impact with high risk in involved in the project implementation. Negative impacts with moderate risks include removal of trees, noise and impacts on air quality during construction and operation stages, and occupational and community health and safety. These impacts are largely short term and expected to occur during construction, with some minor induced and residual impacts expected to occur during operation.

39. The acquiring of 41.9833 ha of private land and felling of 4770 trees will be compensated under a mandatory compensatory scheme under the government wherein total 47700 trees (1:10 ratio) will be planted. This mandatory compensation scheme is expected to result in the creation of good vegetation cover along the road section in the long-term (>10 years).

viii

40. Other moderate and minor negative environmental impacts include dust; pollution of air and water; impacts on 567 private structures and 50 common property resources; inconveniences caused by shifting of utilities; soil erosion; contamination and siltation of surface water, waste and spoils disposal.

41. These will be addressed through various mitigation measures included in the EMP such as regular sprinkling of water; enforcement of construction time limits; regular monitoring of air, water and noise; payment of compensation to affected people in accordance with the entitlement matrix in the Resettlement Plan (RP); regular public communication on shifting of utilities; enforcement of health and safety requirements in the work sites and camps; implementation of slope stabilization measures; management of solid and liquid waste and chemicals and other measures.

H. Environmental Management Plan 42. A fully budgeted EMP has been prepared for mitigation/management/ avoidance of the potential adverse impacts and enhancement of various environmental components along the project road section. For each mitigation measures to be carried out, its location, timeframe, implementation and overseeing/ supervising responsibilities have been identified. Monitoring plan for construction and operation phase has been framed to ensure effective implementation of EMP.

43. The monitoring plan includes performance indicators for wildlife, water, air, and noise level monitoring, frequency of monitoring, and institutional arrangements of the project in the construction and operation stages, along with the estimated cost. The reporting system includes roles and responsibilities of each party involved in the project implementation i.e. PIU, CSC, Contractor (s), external monitor and reporting mechanisms during implementation and operation phases.

44. The monitoring plan also includes regular site inspections and checks by the PIU and FIU under TNHD. The CSC will conduct weekly and joint PIU quarterly site inspections to monitor implementation of the EMP. The CSC Environmental Specialist will monitor implementation of the EMP while the Biodiversity Specialist from external monitor consultant will monitor implementation of the biodiversity management measures.

45. An environmental management budget of INR 193.50 million (USD 2.58 million) has been estimated for implementation of the EMP. This budget also includes cost of environmental monitoring and associated trainings.

I. Conclusions and Recommendations 46. The proposed project road Cheyyur to Polur (SH-115) and ECR link is classified as environment Category B project as per ADB SPS requirements. Environmental screening and assessment of likely impacts and rating of risks shows that with implementation of mitigation measures and road improvement activities the project will not result in significant residual environmental impacts.

47. A number of potential adverse impacts have been identified on issues related to dust, noise, pollution, soil erosion, waste, occupational health and safety, community health and safety, and biodiversity. Most impacts were assessed to be of low to moderate risk. Potential impacts on biodiversity were assessed to be of medium risk. Biodiversity impacts include loss of about 4770 trees due to widening of road and proposed bypass alignment, potential mortality and destruction of habitat for wildlife species, mainly birds. However, project area does not trigger critical habitat.

ix

48. Mitigation measures have been proposed and budgeted to address all the above identified impacts and risks in the EMP. As part of the EMP, environment management actions have also been recommended to mitigate environment related risks related to social, physical and biological aspects.

49. The EMP is a living document and will be subject to revision following finalization of the detailed design by the EPC. The EMP may undergo further revision during project construction if there is any change in project design and occurrence of unanticipated impacts. The environmental mitigation measures are itemized in the EMP and the Executing Agency (TNHD) shall ensure that the most recent EMP and EMoP are included in the civil works contract agreement.

I. INTRODUCTION

A. Project Background

1. The Government of Tamil Nadu proposes to upgrade its road network falling in the conceptual influence area of the Chennai Kanyakumari Industrial Corridor (CKIC), which aims at improving the transport infrastructure, such as the connectivity of industrial nodes to ports, urban areas and critical hinterland areas. The Highways and Minor Ports Department (TNHD) of Tamil Nadu has been mandated to undertake improvement and upgradation of various State Highways at different locations in the State under this project and will serve as the Executing Agency (EA). As part of this mandate, the Construction and Maintenance (C&M) Wing of TNHD has identified the 16 road sections for improvement totally totaling about 590 km spread across the State. The project will be financed through a project loan from the Asian Development Bank (ADB) under Tamil Nadu Industrial Connectivity Project (TNICP). The Project Implementation Unit (PIU) formed within TNHD will be the Implementing Agency (IA).

2. Cheyyur - Polur via Vandavasi Road Section of SH-115 and Cheyyur - Panaur (ECR link) is one of the 16 corridors taken up for improvement under this project. As part of detailed project report (DPR) preparation, this Initial Environmental Examination (IEE) report was prepared to cover Cheyyur - Polur via Vandavasi road Section of SH-115 and Cheyyur - Panaur (ECR link). The total design length of the road alignment is 109.293km in length. The details of project road are given in Table-1.

Table 1: Project Road Details (SH-115)

Sl. No.

Design Chainage (km) Length (m)

Widening

From To

1 1.620 42.840 41220 2-lane with Paved Shoulder (SH-115)

2 45.060 47.920 2860 2-lane with Paved Shoulder (SH-115)

3 53.810 79.390 25580 2-lane with Paved Shoulder (SH-115)

4 82.980 106.246 23266 2-lane with Paved Shoulder (SH-115)

5 42.840 45.060 2220 2-lane with Paved Shoulder Maruthadu Realignment

6a 47.920 52.185 4265 2-lane with Paved Shoulder Vandavasi Bypass

6b 52.185 52.545 360 Divided 4 lane – RUB (Vehicular Underpass Portion) Vandavasi Bypass

6c 52.545 53.810 1265 2-lane with Paved Shoulder Vandavasi Bypass

7 79.390 82.980 3590 2-lane with Paved Shoulder Chetpet Bypass

8 0.000 4.647 4647 2-lane with Paved Shoulder ECR Link (ODR)

Total Length (m) 109273 109.273km

3. As part of detailed project report (DPR) preparation, this initial environmental examination (IEE) report was prepared to cover Cheyyur - Polur via Vandavasi Road Section (SH-115) Road project. All discussions thereafter focus on this road section. IEE has been prepared in accordance with relevant policies and regulations of the Government of India, GoTN, and the

2

ADB’s Safeguard Policy Statement 2009 (SPS). This IEE report will be disclosed in the office of Tamil Nadu Highways Department and on the CKICP and ADB website.

B. Nature, Size and Location of Project Road

4. SH-115 Project Road: The SH-115 project road originates from Cheyyur in Tiruvanamalai district at an existing chainage of km1+620 having latitude 12°21’07.50”N and longitude 80°12’36.92”E and ends at Polur in Chengalpattu (Kanchipuram bifurcated into Chengalpattu and Kanchipuram districts) district at an existing chainage of km103.780 having latitude 12°57’21.63”N and longitude 79°56’33.05”E.

5. ODR: ECR Link: Cheyyur – Panayur Road: The link road from Cheyyur to East Coast Road (ECR) is other district road originates from Cheyyur at km 0.000 having latitude 12°21’04.44”N and longitude 80°00’26.35”E and terminates at Panayur km4.720 with ECR (Chennai-Puducherry; SH-49) having latitude 12°19’07.46”N and longitude 80°01’51.06”E, see Table -2 for location details.

Table 2: Location Details of Project Road Sections

Description Location Latitude Longitude

SH-115: (Cheyyur – Vandavasi–Polur)

Start of Project Highway Cheyyur (km 1+620) 12°21’07.50” N 80°12’36.92” E

End of Project Highway Polur (km 103+780) 12°57’21.63” N 79°56’33.05” E

ECR Link: Cheyyur – Panayur (ODR)

Start of Project Highway Cheyyur (km 0+000 at Jn.) 12°21’04.44” N 80°00’26.35” E

End of Project Highway Panayur (ECR/SH-49) at km 4+720

12°19’07.46” N 80°01’51.06” E

6. The project road is located in Chengalpattu and Tiruvannamalai districts of Tamil Nadu. The project road has two lane carriageway configurations in its entire length except for small sections near built-up area and townships where the road has four lane carriageway configurations. The project road has a number of congested towns throughout its length namely Vandavasi and Chetpet town. There are no existing bypass/ realignment on the project road from Cheyyur to Polur (SH-115). Two bypasses are proposed for Vandavasi and Chetpet towns for free movement of the traffic and saving in travel time and fuel. The project road alignment is linear in nature as alignment is shown in Figure 1.

3

Figure 1: Location of Project Road Alignment on Map

C. Background of the Present Report

7. This IEE report is prepared for the project road in order to identify the baseline environmental status of the project road alignment, assess impacts due to the proposed widening of the road on various environmental parameters and preparation of environmental management plan to mitigate the negative impact on these parameters.

8. The initial environmental examination study was prepared between the months of November 2019 to June 2020 to meet ADB’s Safeguards policy requirements. This is the draft IEE report prepared to fulfill ADB’s SPS 2009 requirements for financing the Project. The detailed engineering design report has been prepared by M/s. RITES Limited. The IEE report is being prepared by TNHD as the EA with the help of independent environmental specialist supported by ADB technical assistance.

D. Objective and Scope of the Study

9. This IEE report documents the environmental assessment of the Cheyyur to Polur (SH-115) including ECR link road project and identifies the environmental issues to be considered in the project planning and design stages. In this report, the different activities that are likely to take place to achieve the project objectives have been analysed. Potential impacts that may accompany them have been identified, assessed for significance, and concomitant avoidance, mitigation, and compensation measures were prepared in consultation with stakeholders. The IEE

4

addresses the environmental management requirements of the Government of India (GOI) and ADB. Specifically, this report-

• provides information about the baseline environmental setting of the project. • provides information on potential environmental impacts of the proposed project

activities with its magnitude, distribution and duration and sensitivity of receptors. • provides information on required mitigation measures with cost to minimize the

impacts. • analyses the alternatives options considering alternative locations, designs,

management approaches for selection of most feasible and environmental acceptable options.

• provides details of stakeholder’s consultations. • designs an environmental management and monitoring plan with institutional

responsibilities measures for effective implementation of mitigation measures proposed and provides addressing grievances.

10. The environmental studies have been confined to the situation around the deemed project area of influence caused by constructional and operational facilities along the proposed road sections. The IEE is based on proposed road alignment and key construction activities involved such as site clearing, removal of trees, excavation, filling, grading and embankment formation, excavation for utility trenches, subgrade preparation, base course and asphalt overlay, shoulder, and construction of permanent structures like retaining walls, culverts and drains. The IEE also covered ancillary activities like camp site establishment and maintenance, sourcing of materials, and operation of equipment like rock crusher and hot mix plants . The corridor of impact is taken as 10 meters either side of the proposed alignment (from edge of the proposed road) including RoW of 16 meters for urban stretches, 23 meters for rural areas, and 30 meters for bypasses. However, the study area impact zone is considered up to 10 km aerial distance on both sides of road alignment to allow for coverage of indirect and induced impacts and a larger analysis of land use and other environmental features. Assessment is carried out on the following environment components: terrestrial and aquatic ecology, soil, water, air, noise, and socio-economic aspects. The project area of influence (PAI) was determined as the ROW plus 500m on either side of the road.

11. The following sections of the report discusses the methodology adopted by the consultants in conducting the IEE study and presents the results of the same.

E. Methodology Adopted for IEE Study

12. The Initial Environmental Examination (IEE) study has been carried out in accordance with the requirements of the ADB’s Safeguard Policy Statement (SPS 2009). The Government of India guidelines for Rail/Road/Highway projects; EIA notification 2006 and its amendment of MOEFCC and the Highway Sector EIA guidance manual 2010 have also been followed in the process of this environmental assessment. The study methodology has been adopted in such a manner to ensure that environmental concerns are given adequate weightage in the selection of alignment and design of proposed road improvements. The study in this project employs an iterative approach in which potential environmental issues have been examined at successive levels in detail and specificity, at each step in the process.

13. The environmental assessment is based on the information collected from primary as well as secondary sources on various environmental attributes. Monitoring of air, water, noise and soil

5

quality was also carried out within the ROW and significant issues were examined during field surveys to determine the magnitude of significant environmental impacts.

14. The major steps in the IEE process for the project were as follows:

1. Collection and Analysis of Data

15. The Baseline data was collected on various environmental components such as soil, meteorology, geology, hydrology, water quality, flora and fauna, habitat, demography, land use, cultural resources, properties and structures. Secondary data on environment for the project corridor were collected both from published and other relevant sources e.g., the Department of Forest, Tamil Nadu State Pollution Control Board, State Statistical Department etc. The data collection from the field was completed with the help of enumerators / investigators. The interviewers were trained for filling up the questionnaire at the site. To ensure the accuracy of the data, data collection was done under the supervision of the ADB TA consultant. The type and source of information compiled in this IEE are shown in Table 3.

Table 3: Primary and Secondary Information Sources Information Sources

Technical information on existing road features and proposed Rehabilitation work. Inventory of road features; viz. water bodies community structures, environmental sensitive location areas, congested

Department of Highways Tamil Nadu, Project Implementation Unit, ADB Project, CKICP Design Consultant, Ground physical surveys and graphics consultants

Climatic Conditions Indian Meteorological Department, ENVIS Website, NIC, primary data Collection

Geology, Seismicity, Soil and Topography Geological survey of India, Survey of India (SOI) Toposheets, Primary data collection

Land Use/ Land Cover Survey of India (SoI) Toposheet, Observation during survey.

Drainage Pattern Survey of India Toposheet and field observation

Status of forest areas, Compensatory afforestation norms etc.

Divisional Forest Office, Chengalpattu and Tiruvannamalai District.

Status of Fishing Activity District Fisheries Offices at Chengalpattu and Tiruvannamalai District

Air quality Noise, Soil and Water Onsite monitoring and Analysis of Field samples during field visit

Borrow Areas, Quarries and other construction material source

Feasibility report, field observations

River geo-morphology, hydrology, drainage, flood patterns

Socio-economic Environment Primary Census Abstract of Chengalpattu and Tiruvannamalai, District 2011. Official websites maintained by state Govt., and Public Consultation during the Field survey

6

2. Environmental Monitoring and Analysis

16. Different locations were identified for monitoring and analysis of noise level, ambient air and water quality. The monitoring and analysis of water quality, air quality and noise level has been done by M/s Global Lab and Consultancy Services, Salem a leading environmental research laboratory. Air quality monitoring has been carried out as per MOEFCC notification of November 2009 the revised Air Quality standards and the on-site monitoring results are incorporated in Chapter- 4 of this IEE report.

17. Vegetation and Wildlife Surveys: In order to assess presence of flora and fauna along the proposed alignment field surveys have been carried out with the help of field officers of the state forest department Specific attention was given to collect the data on presence of Wildlife and birds. Findings are incorporated in Chapter- 4 of this IEE report.

3. Analysis of Alternative

18. Alternative analysis for the present project road alignment has been made on the basis of “with-” and “without project” scenarios. The parameters considered for the analysis are the environmental as well as social features and their likely impact on the natural ecosystem.

4. Stakeholder and Public Consultations

19. Extensive consultations were held during different stages (reconnaissance, detailed design and design review) with key stakeholders that includes local and beneficiary population, government departments/agencies, road users, and project-affected persons. These consultations allowed the interaction between the stakeholders and road designers to identify road features and construction methods that will enhance road upgrading and minimize potential impacts. Information gathered was integrated in the project design and used in formulating mitigation measures and environmental management plan. Detailed description of public consultation is presented in Chapter-7 of this IEE report.

5. Assessment of Potential Impacts

20. Potential impacts were identified on the basis of analytical review of baseline data; review of environmental conditions at site and analytical review of the underlying socio-economic conditions with the project influence area.

6. Preparation of the Environment Management Plan

21. An EMP for the project contract packages has been prepared to specify the steps required to ensure that the necessary measures have been taken and the same will be incorporated during construction and operation stage of the project. The EMP includes the monitoring plan giving details of the resources budgeted and the implementation arrangements.

F. Structure of the Report

22. This IEE report has been presented as per requirements of the ADB’s Safeguard Policy Statement (SPS) 2009. The report is organized into following ten chapters, a brief of each chapter is described below:

• Chapter 1 - Introduction: This section describes the background information about the project and IEE study.

7

• Chapter 2 - Policy, Legal, and Administrative Frameworks: this section summarizes the national and local legal and institutional frameworks that guided the conduct of the assessment as well as applicable international conventions and protocols.

• Chapter 3 - Project Description: This section presents the key features and components of the proposed project.

• Chapter 4 - Description of the Environment: This section discusses the relevant physical, biological, and socioeconomic features that may be affected by the proposed project.

• Chapter 5 - Analysis of Alternatives: This section covers analysis of various alternatives considered to minimize the overall impacts of proposed development and suggest most appropriate alternatives based on detailed analysis of impact and risk associated with each alternative.

• Chapter 6 - Anticipated Environmental Impacts and Mitigation Measures: This section presents the environmental assessment of likely positive and adverse impacts attributed to the proposed project and concomitant mitigation measures.

• Chapter 7 - Consultation, Participation and Information Disclosure: This section describes the consultation process undertaken during the environmental examination and its results, their consideration in the project design, and manner of compliance to the ADB’s Publication Policy and related national laws.

• Chapter 8 - Grievance Redress Mechanism: This section describes the formal and informal redress procedures for registering, resolving, and reporting complaints.

• Chapter 9 - Environmental Management Plan: This section discusses the lessons from the impact assessment and translated into action plans to avoid, reduce, mitigate or compensate adverse impacts and reinforces beneficial impacts. This plan is divided into three sub-sections: mitigation, monitoring, and implementation arrangements

• Chapter 10 - Conclusion and Recommendation: This section states whether there is a need for further detailed environmental studies / assessments and highlights key findings and recommendations to be implemented by the borrower.

23. An Executive Summary is also prepared and presented in the beginning of the report.

8

II. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK

24. India has well defined institutional and legislative framework. The legislation covers all components of environment such as air, water, soil, terrestrial and aquatic flora and fauna, natural resources, and sensitive habitats. India is also signatory to various international conventions and protocols. The environmental legislations in India are framed to protect the valued environmental components and comply with its commitment to the international community under above conventions and protocols. Asian Development Bank (ADB) has also defined its Environmental and Social Safeguard policies. This assessment is about the applicability of above laws and regulations, conventions, protocols, and safeguards. This section summaries the following:

• National (India) Environmental Legislation and Legal Administrative Framework, • Social Safeguard Regulatory Requirements, • ADB safeguard policies and categorization of the project, and • Summary of international treaties and applicability to the project

A. National (India) Environmental Policy Framework

25. The legal framework of the country consists of several acts, notifications, rules and regulations to protect environment and wildlife. In 1976, the 42nd Constitutional Amendment created Article 48A and 51A, placing an obligation on every citizen of the country to conserve the environment. The national legislations are broadly divided under following categories:

• Environmental Protection, • Forests Conservation, and • Wild Life Protection.

26. The umbrella legislation under each of above category is highlighted below:

• The Environment (Protection) Act 1986 was enacted with the objective of providing for the protection and improvement of the environment. It empowers the Central Government to establish authorities charged with the mandate of preventing environmental pollution in all its forms and to tackle specific environmental problems that are peculiar to different parts of the country. Various rules are framed under this Act for grant of environmental clearance for any developmental project, resources conservation and waste management.

• The Forest Conservation Act 1980 was enacted to help conserve the country's forests. It strictly restricts and regulates the de-reservation of forests or use of forest land for non-forest purposes without the prior approval of Central Government. To this end the Act lays down the pre-requisites for the diversion of forest land for non-forest purposes.

• Wildlife (Protection) Act 1972 amended in 2003 was enacted with the objective of effectively protecting the wild life of this country and to control poaching, smuggling and illegal trade in wildlife and its derivatives. It defines rules for the protection of wild life and ecologically important protected areas.

27. State Pollution Control Boards (SPCBs) together form the regulatory and administrative core of the government for managing environmental impacts. Other Ministries/ Statutory Bodies/ Departments responsible for ensuring environmental compliance and granting various clearances

9

includes state ministry/department of environment, regional offices of MOEFCC and state forests/wildlife departments. 28. The environmental impact assessment (EIA) requirement in India is based on the Environment (Protection) Act, 1986, the EIA Notification, 2006 (latest amendment in 2020), all its related circulars, MOEFCC’s Environmental Impact Assessment Guidance Manual for Highways 2010 and IRC Guidelines for Environmental Impacts Assessment (IRC:104-1988) of highway projects. In addition to road widening and rehabilitation including establishment of temporary workshops, construction camps, hotmix plants, and opening of quarries for road construction work require compliance with provisions of The Forest (Conservation) Act 1980 as amended 1988 and Rules 1981 as amended 2003: The Wildlife (Protection) Act, 1972 (amended 1993); The Water (Prevention and Control of Pollution) Act 1972 (amended 1988) and Rules 1974; The Air (Prevention and Control of Pollution) Act, 1981 (amended 1987) and Rules 1982; The Noise Pollution (Regulation and Control) Rules, 2000 (amended 2002) and the Hazardous Waste (Management, Handling and Trans-boundary Movement) Rules 2008 (amended 2016). 29. A review is undertaken for all the environmental rules and regulation which might be applicable to the proposed road corridor improvement activities. Legislations applicable to this project are summarised below in Table 4. There is no separate state level legislation. However various acts like Water and Air are enforced through state level authority: the State Pollution Control Board (SPCB).

30. Specifically for the proposed Cheyyur - Polur road and ECR link in the state of Tamil Nadu, the following environmental laws and regulations applicable are in Table 4:

Table 4: Applicable Environmental National and State Requirements

Sl. No.

Activity Statute Requirement Competent Authority

Responsible Agency forObtaining Clearance

Time Required

Planning Stage: Before start of Civil Works Construction (Responsibility: Executing/Implementing Agency)

1. Borrow areas EIA Notification 2006

Environmental Clearance

State/District EIAA

The Contractor

4-6 months

2. Implementing Project

Revenue Standing orders

Tree cutting permission

Revenue Officers

TNHD 2-6 months

Note : Borrowing of ordinary earth for linear projects exempted from purview of EIA notification 2006 vide MoEF Notification S.O. No. 1224 (E) dated 28.03.2020

Construction Stage (Responsibility: Contractor)

1

Establishing campsites, stone crusher, hot mix plant, wet mix plant and Diesel Generator Sets

Water Act of 1974, Air Act of 1981, Noise Rules of 2000 and Environmental Protection Action of 1986 and as amended

Consent to establish

Tamil Nadu Pollution Control Board

The Contractor

2-3 months

10

Sl. No.

Activity Statute Requirement Competent Authority

Responsible Agency forObtaining Clearance

Time Required

2

Operating camps, stone crusher, hot mix plant, wet mix plant and Diesel Generator Sets

Water Act of 1974, Air Act of 1981, Noise Rules of 2000 and Environmental Protection Action of 1986 and as amended

Consent to operate

Tamil Nadu Pollution Control Board

The Contractor

2-3 months

3

Storage of fuel oil, lubricants, diesel etc. at construction camp

Manufacture storage and Import of Hazardous Chemical Rules 1989

Permission for storage of hazardous chemical

Tamil Nadu Pollution Control Board or Local Authority (District Magistrate /District Collector)

The Contractor

2-3 months

4 Quarry operation

State Minor Mineral Concession Rules, The Mines Act of 1952, Indian Explosive Act of 1984, Air Act of 1981 and Water Act of 1974

Quarry Lease Deed and Quarry License

Tamil Nadu Department of Mines and Geology

The Contractor

2-3 months

5 Extraction of ground water

Ground Water Rules of 2002

Permission for extraction of ground water for use in road construction activities

State Ground Water Board

The Contractor

2-3 months

6 Use of surface water for construction

-

Permission for use of water for construction purpose

Tamil Nadu Irrigation Department

The Contractor

2-3 months

7 Engagement of labor

Labor Act Labor license District Labor officer

The Contractor

2-3 months

31. In addition to the acts and regulations listed above the Environmental Impact Assessment Guidance Manual for Highways 2010 issued by MOEFCC and the IRC Guidelines for Environmental Impacts Assessment (IRC:104-1988) of highway projects issued by MORTH, were referred in the process of preparing this IEE. The following requirements are particularly important and need special attention in order to avoid any delays for a project:

• As per provisions of the EIA Notification 2006 (amended in 2009, 2011 and 2013), all new state highway and state highway expansion projects except in hilly terrain (above 1,000m AMSL) and or notified ecologically sensitive areas (ESA) fall under

11

Category B and does not require environmental clearance from the State Environmental Impact Assessment Authority (SEIAA) at the state level. Since the proposed project involves expansion of the existing state highway road section between Cheyyur - Polur road and ECR link and this section is not located in hilly terrain (above 1,000m AMSL) or any notified ecologically sensitive areas, it does not fall under the purview of EIA notification.1 Therefore an environmental clearance from SEIAA is not required for this project road.

• As per the Forest Conservation Rules (1981, amended 2003) a forestry clearance from Department of Forests is required for diversion of forest land for non-forest purpose. Processing of the forestry clearance entails two stages: stage I and stage II. Amongst other requirements stage I clearance requires the applicant to make payments for compensation of forestry land that will be acquired and trees that will be cut under the project. Accordingly, timely allocation of budget for this purpose by the applicant is necessary to expedite the clearance process. Proposed Cheyyur - Polur road and ECR link road passes through forest areas in patches. The widening in forest stretches will be limited to available RoW and no additional land acquisition is required. Therefore, forest clearance is not required as per Government of India requirements.

• As per the Wildlife Protection Act, clearance from National Board for Wildlife (NBWL) is not required for proposed Cheyyur - Polur road and ECR link road project as the project road not located within core or notified buffer zone boundary of any protected area.

• Cutting of trees in non-forest land requires a tree cutting permit from the Revenue department. All trees cut under a project must be compensated by compensatory afforestation in the ratio of 1:10.

• As per Office Memorandum (OM) issued by MOEFCC on 19 March 2013 the grant of environmental clearance for linear projects including roads has been delinked from the forestry clearance procedure. Hence, after receipt of environmental clearance construction works may commence on sections/parts of a linear project that do not require forestry clearance. Construction works may commence on sections requiring forestry clearance only after receipt of the respective clearance.

• Placement of hot-mix plants, borrow areas, quarrying and crushers, batch mixing plants, discharge of sewage from construction camps requires No Objection Certificate (Consent to Establish and Consent to Operate) from SPCB prior to establishment (Table 3, construction stage item 1 and 2).

• Permission from Central Ground Water Authority is required for extracting ground water for construction purposes, from areas declared as critical or semi critical from ground water potential prospective by them (Table 3, construction stage item 5).

• ECR link is crossing Odiyur lake having CRZ. Coastal Regulation Zone (CRZ) clearance is not required for ECR link, since there is no improvement in the backwater stretch of ECR link.

• Before the start of civil works for the any component of the project the project proponent (TNHD) must obtain necessary clearances/permits from the regional office of the Ministry of Environment and Forest and Climate Change, National Wildlife Board and State Pollution Control Board.

1 Ecologically Sensitive Areas (ESA) are areas notified by MoEFCC an ecologically fragile area under EPA rules, 1986.

List of notified ESA in India are available at http://moef.gov.in/rules-and-regulations/esa-notifications/. While Eco-sensitive Zone (ESZ) is area around the notified Protected Areas (National Parks and Wildlife Sanctuaries) as per the Guidelines for Deceleration of ESZ around National Parks and Wildlife Sanctuaries, as details are given at http://moef.gov.in/rules-and-regulations/esz-notifications-2/.

12

B. Social Regulatory Requirements of India and Tamil Nadu

32. There are many rules and regulations framed by the Government of India for the protection of workers. Most of these legislations will be applicable to contractors in charge of construction. EA will ensure compliance to these social legislations through contractual obligation and regular checks and penalties. These legislations include the Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996, Child Labour (prohibition and Regulation) Act, 1986; Minimum Wages Act, 1948; Workmen Compensation Act, 1923; Payment of Gratuity Act, 1972; Employee State Insurance Act; Employees P.F. and Miscellaneous Provision Act, 1952; Maternity Benefit Act, 1951; Payment of Wages Act, 1936; Equal Remuneration Act, 1979; Inter-State Migrant Workmen’s (Regulation of Employment & Conditions of Service) Act, 1979; Equal Remuneration Act, 1979 etc.

C. International Treaties and Relevance to the Project

33. Government of India has signed many international treaties. GOI has also framed various laws, regulations and guidelines to meet country’s obligations under these treaties. Projects of this magnitude may contribute in meeting country’s obligation directly or indirectly. A screening was carried out of these treaties regarding its applicability to this project. The relevant international treaties are:

• Kyoto Protocol to the United Nations Framework Convention on Climate Change (Ratified by India in 1997): The Kyoto Protocol is an international agreement linked to the United Nations Framework Convention on Climate Change. The major feature of the Kyoto Protocol is that it sets binding targets for 37 industrialized countries and the European community for reducing greenhouse gas (GHG) emissions. These amount to an average of five per cent against 1990 levels over the five-year period 2008-2012.

• The Paris Agreement 2015: The Paris Agreement is an international agreement by 196 parties which aims at limiting global warming to 1.5 to 2 degrees C above pre-industrial levels. Through this, the parties also agreed to a long-term goal for adaptation through nationally determined contributions (NDCs), which is requested to be submitted every 5 years. India submitted its first NDC on October 2, 2016.

• Convention Concerning the Protection of the World Cultural and Natural Heritage (Ratified by India in 1972): The most significant feature of the 1972 World Heritage Convention is that it links together in a single document the concepts of nature conservation and the preservation of cultural properties. The Convention recognizes the way in which people interact with nature, and the fundamental need to preserve the balance between the two.

• Convention on International Trade in Endangered Species of Wild Fauna and Flora (Washington, 1973): Seek to avoid poaching by construction workers especially in environmentally sensitive areas.

• Convention on Migratory Species of Wild Animals (Bonn, 1979): Ensure potential impacts on any migratory species supported by the project area of influence assessed and managed.

• Convention Relative to the Preservation of Fauna and Flora in the Natural State (1933): Preservation of Flora and Fauna.

13

D. Project Standards

34. Environmental standards for air, water, soil, noise, and vibration, among others will follow applicable CPCB, World Bank Group (WBG)/International Finance Corporation (IFC) Environment Health and Safety (EHS), or State-imposed limits, whichever is most stringent. When national regulations differ from the performance levels and measures presented in EHS Guidelines, projects are expected to achieve whichever is more stringent. If less stringent measures are appropriate in view of specific project circumstances, full and detailed justification of the applied standard or guideline should be presented in the environmental assessment. The justification should demonstrate that the chosen alternative’s performance level is protective of human health and the environment. CPCB and IFC EHS guidelines are provided in Appendices.

E. ADB’s Safeguard Policy Statement Requirements

35. ADB has defined its Safeguard requirements under its ‘Safeguard Policy Statement 2009 (SPS 2009). The prime objectives of safeguard policy are to: (i) avoid adverse impacts of projects on the environment and affected people, where possible; and (ii) minimize, mitigate, and/or compensate for adverse project impacts on the environment and affected people when avoidance is not possible. This policy requires assessment, mitigation and commitment towards environmental protection. The extent of assessment depends on the category of the project. ADB’s SPS 2009 classifes a project depending on following three categories.

• Category A: A proposed project is classified as category A if it is likely to have significant adverse environmental impacts that are irreversible, diverse, or unprecedented. These impacts may affect an area larger than the sites or facilities subject to physical works. An environmental impact assessment is required.

• Category B: A proposed project is classified as category B if its potential adverse environmental impacts are less adverse than those of category A projects. These impacts are site-specific, none or very few of them are irreversible, and in most cases mitigation measures can be designed more readily than for category A projects. An initial environmental examination is required.

• Category C: A proposed project is classified as category C if it is likely to have minimal or no adverse environmental impacts. No environmental assessment is required although environmental implications need to be reviewed.

F. Category of the Project

36. The project has been evaluated considering the outcome of the ADB Rapid Environmental Assessment (REA) checklist and the same is enclosed as Appendix 1. All environmentally sensitive areas along the proposed alignment have been critically analyzed to assess the magnitude and extent of likely impacts.The project road do not falls within core/buffer zone of any protected area

37. Certain sections of the project road involve expansion of the existing road to two lane standard road, where there will be substantial land use change and earthworks involved. The road section crosses some of the water bodies and acquisition of land may be involved at a few stretches.

38. The project section is not located near to any notified protected area and there are no wildlife has been reported due to residential habitation development along the road. There are no potential significant ecological impacts anticipated from project during construction and operation stage. Hence, the project falls under environment Category B as per ADB Safeguard Policy Statement 2009.

14

III. PROJECT DESCRIPTION

A. Type and Features of Project

39. The present report on Initial Environmental Examination (IEE) deals with the environmental analysis of the project road considered under ADB supported TNICP - Upgrading Cheyyur - Polur road and ECR link road section of SH-115.

40. The project road section of State Highway 115 (SH-115) starts from km 1+620 (Cheyyur) and ends at km103+780 at Polur town (Intersection with NH-234, Old SH-9) connecting Vandavasi, Chetpet and Devikapuramen towns route. Therefore, the road section is important route from tourist as well as commercial point of view.

41. The link road from Cheyyur to East Coast Road (ECR) is other district road (ODR) originates from Cheyyur at km0+000 and terminates at km4+720 with ECR (Chennai-Puducherry Road, SH-49). The link will provide a shorter route to the commuters while using this link to reach at Puducherry.

42. The project road is located in Chengalpattu and Tiruvannamalai districts of Tamil Nadu. The project road has two lane carriageway configurations in its entire length except for small sections near built-up area and townships where the road has four lane carriageway configurations. The project road has a number of congested towns throughout its length namely Vandavasi and Chetpet town. There are no existing bypass/ realignment on the project road from Cheyyur to Polur (SH-115). Two bypasses are proposed for Vandavasi and Chetpet towns for free movement of the traffic and saving in travel time and fuel. The total length of project road is 109.273 km. The project road alignment is linear in nature.

43. Project activity involves resurfacing, widening, restoration, and rehabilitation. It will involve improvement in project road taking into consideration of lane configuration, widening scheme, speed, embankment height and the urban or rural setting of the road. The project is linear in nature. Table 5 present key project road features and design standards for project road.

Table 5: Cheyyur to Polur Project Road (SH-115) Road Features

Parameter Details

Road Length 109.273 km including bypasses and ECR link.

Alignment Follow the existing road alignment. Except some of the locations where geometric improvements is required and at the location of proposed bypass

Bridges 5 Major bridges, 12Minor bridges, and 1 under pass along Cheyyur - Polur road and ECR link road.

Cross Drainage Structures

There are 230 culverts which includes1RCC slab, 61 pipe, 168 box .

Embankment Design

As per IRC the Embankment Height shall be 1.0 m from HFL to the Top of subgrade. Keeping in view of local person’s suggestion the Proposed FRL is kept as 1.0 m from the top of existing FRL.

Design Standard

As per IRC Codes and MOR&TH Guidelines Vertical Clearance 0.60 m above HFL for bridges upto 30 m length 0.90 m above HFL for bridges above 30 m length. The discharges for which the bridge has been designed are maximum flood discharge on record for a period of 100 years for major bridges and 50 years for minor bridges.

Speed Design : 100 Km/h, Permissible: 80 Km/h

15

Horizontal Controls

As per IRC: SP: 73 – 1980

The vertical alignment of the project road is substantially designed for speeds of 80 kph to 100 kph.

Vertical Controls

Grade break of 0.6%, vertical curves will be provided.

Length of vertical curve will be restricted to minimum 50m

Carriageway Carriageway :7 m

Camber of 2.5% in main carriageway.

Source: Detailed Project Report, 2019

B. Location of the Project Road

44. The State Highway 115 (SH-115) originates from Cheyyur 12°21’07.50”N and 80°12’36.92”E, at km 1.620 and ends in Polur 12°57’21.63” N and 79°56’33.05” E, at km 103.780. An Ultra Mega Power Plant (UMPP) of 4000 MW is coming up at Cheyyur, which will result in substantial increase in traffic on the project road section between Cheyyur and Melmaruvathur (NH-45 crossing). Some of the important towns located on the project road are Cheyyur, Melmaruvathur, Vandavasi, Chetpet and Polur.

45. The link road from Cheyyur to East Coast Road (ECR) is other district road (ODR) originates from Cheyyur 12°21’04.44”N, 80°00’26.35”E at km 0.000 and terminates in Panuayur (ECR/ SH49) 12°19’07.46” N and 80°01’51.06”E at km 4.720. The link will provide a shorter route to the commuters while using this link to reach at Puducherry. There are 59 habitations/villages along the SH115.

46. The bypasses are proposed at congested locations where widening is not feasible due to inadequate ROW and high R&R issues. There are two bypasses apart from geometric improvements/realignments along the project road section of SH-115. Two bypasses are proposed for Vandavasi town and Chetpet towns and one realignment in Maruthadu village.

47. The project road traverses in plain terrain passing through rural areas as well as semi-urban and urban settlements; intermittently. In rural areas the land use on both sides is agricultural land/open spaces interspersed with small structures. The abutting land use in the built-up areas is predominantly residential and commercial. Few educational institutions and religious structures exist along the project road in some of the villages and town sections. It is observed that the vertical alignment of the road is quite flat except at few culvert locations. Traffic signs are missing at many locations along the project road. No warning signs exist before the approach of the junction and approach of curves. Directional signs exist at few locations.

B.1 Right of Way (RoW)

48. The road improvement is proposed from existing 2 lane with earthen shoulder to 2 lane with paved shoulder configuration with existing ROW. The existing RoW varies from 10m to 40m. The exiting ROW for ECR link is 10-13 m. The project road section is predominantly passing through flat/plain terrain in its entire length. The project road passes through the agricultural and barren land, built-up and forest land. There are a number of habitations located all along the project roads. The details of available RoW along the project road is given in Table 7.

16

B.2 Cross Drainage Structures

49. There are 230 culverts which includes 1 RCC slab, 61 pipe, 168 box, 5 Major bridges, 12 Minor bridges, and 1 underpass along Cheyyur - Polur road and ECR link road.

B.3 Traffic Scenario

50. The 7-day 24-hour directional classified Traffic Volume Count (TVC) was carried out at two different locations on the project road section during DPR preparation. The average daily traffic volumes are given below in Table 6. Traffic projections are in Table 51 in Chapter 6 of this report.

Table 6: Annual Average Daily Traffic Volume along Homogenous Road Sections

Vehicle Type L1151 L1152 L1153 L1154 L1155

2W 2747 2572 2801 2087 3164

3W 242 93 243 78 353

Car 700 312 1093 659 334

Bus 211 59 918 648 298

LCV 248 329 624 553 304

Truck 390 148 288 429 333

Other Fast Moving Vehicle 33 13 47 67 75

All Fast 4572 3526 6014 4521 4861

All Slow 83 204 159 203 1158

AADT (in Nos.) 4655 3730 6173 4724 6019

AADT (In PCUs) 4618 2856 7362 6056 5453 L1151: Cheyyur - Chitamur, L1152: Chitamur-NH45 Jn., L1153: NH45 Jn - Vandavasi, L1154: Vandavasi-Chetpet, L1155: Chetpet - Polur

Source: Traffic volume Survey by the DPR Consultant

B.4 Road Width

51. This project road has 7.0m carriageway with earthen shoulder width varying between 0.5m to 1m in the entire length except at built up sections.

B.5 Villages and Urban-Built Up Sections

52. This project road passes through many villages and towns. The major builtup locations along the project road are Cheyyur Town, Mudaliyarkuppam, Nallur, Vallarai, Onampakkam, Kathudhevathur, Kepkoshikarai, Nallamur, Chittamur, Kolampakkam, Polambakkam, Mazhubkadu, Sothupakkam, Agili, Sandivakkam, Ramapuram, Salavedu, Mamandur, Kilkodungaloore/, Kallankuthu, Kaveripakkam, Maruthadu, Kodaisikulam, Biridhur, Chinnavaram, Vandavasi Town, Karajar Nagar, Mampattu, Ramraj Nagar, Kilnanthyambadi, Thirumarithanaga, Vadavarakkamba, Kilvelliyur, Periyar Nagar, Thirukarai, Mazhaiyur, Earthal, Ettithangal, Chinna, Arasumpattu, Nedugunam, Chetpet Town, Nirmala Nagar, Ideyankulam, Muthuswami, Nambedu, Pandiyapuram,Thachanbadi, Cheyarandal, Devikapuram, Modiyur, Mattaperiyar, Pulivardal, Komanandal, Karaipondi, Vermani and Polur Town.

17

Table 7: Villages and Urban Built Up Locations on Project Road and RoW

Sl. No. Ext. Chainage (km)

Village Name Land Use Available

ROW (in m) From To Left Right

1 1+620 3+000 Cheyyur Town AR AR 16.4 – 40.9

2 3+200 4+647 Mudaliyarkuppam AB AB 10.2

3 4+400 5+400 Nallur AB AB 34.3 - 43.5

4 5+400 7+000 Vallarai AB AB 34.3 - 43.5

5 7+000 8+000 Onampakkam AB AB 16.3

6 9+900 10+700 Kathudhevathur ACR ACR 17.1

7 11+800 12+300 Kepkoshikarai AB AB 36-55

8 13+000 13+400 Nallamur 36-41 --

9 16+000 16+800 Chittamur ACR ARG 34.5

10 18+000 18+300 Kolampakkam AB AB 30

11 19+000 19+400 Polambakkam ABR ABR 20-23

12 20+000 20+400 Mazhubkadu AB AB 22-65

13 22+700 24+800 Sothupakkam AR AR 35-56

14 24+900 25+000 Agili AR AR 21.6

15 27+300 27+600 Sandivakkam AR ARB 17

16 31+400 32+900 Ramapuram ARB ARB 23

17 35+200 36+200 Salavedu ARB ARB 101.6

18 38+900 39+100 Mamandur ARB ARB 16

19 39+100 39+700 Kilkodungaloore/ ARB ARB 20.5

20 40+800 41+800 Kallankuthu ARB ARB 20.2-41

21 42+200 42+500 Kaveripakkam ABC AB 25-94

22 42+000 43+300 Maruthadu ABRC ACR 15-53

23 45+100 45+400 Kodaisikulam ABR AB 20-35

24 47+100 47+400 Biridhur ABR BR 18-40

25 48+500 49+300 Chinnavaram AR AC 20-65

26 49+300 50+500 Vandavasi Town AR AR 20-42

27 50+500 50+650 Karajar Nagar AR AR 40-47

28 54+000 55+000 Mampattu AR AR 32-40

29 56+000 56+500 Ramraj Nagar ABR ABR 20-61

30 59+000 59+800 Kilnanthyambadi BR BR 27

31 60+000 60+400 Thirumarithanaga AB B 18-71

32 61+100 61+600 Vadavarakkamba A A 18-35

33 61+800 62+300 Kilvelliyur AR AR 20-32

34 63+600 63+800 Periyar Nagar ABR ABR 22-40

35 64+100 64+300 Thirukarai AB AB 35-111

18

Sl. No. Ext. Chainage (km)

Village Name Land Use Available

ROW (in m) From To Left Right

36 65+100 65+300 Mazhaiyur AB AB 20-65

37 68+000 68+300 Earthal AB AB 20-72

38 69+000 69+600 Ettithangal ABR ABR 20-36

39 70+100 70+700 Chinna AR AR 18-36

40 71+700 72+400 Arasumpattu AR AR 20-54

41 74+800 75+800 Nedugunam ABR ABR 20-64

42 77+900 80+300 Chetpet Town ABCR ABCR 18-60

43 80+600 80+500 Nirmala Nagar ABC ABCR 22-36

44 82+600 83+000 Ideyankulam ABR ABR 16-45

45 83+600 84+000 Muthuswami ABR ABR 18-40

46 85+500 85+900 Nambedu ABR ABR 20-36

47 86+400 87+300 Pandiyapuram A A 22-45

48 87+800 88+300 Thachanbadi A A 30-42

49 89+100 89+400 Cheyarandal ABR ABR 22-50

50 90+000 91+800 Devikapuram BR ABR 20-50

51 93+400 94+700 Modiyur ACR ACR 16-50

52 97+000 97+200 Mattaperiyar BCR BCR 16-50

53 99+100 100+100 Pulivardal ABC ABC 17.5-43

54 100+100 100+800 Komanandal AB AB 21-56

55 101+300 101+800 Karaipondi ABCR ABCR 19.7-63

56 102+100 103+500 Vermani ABCR ABCR 18.6-44

57 104+100 105+000 Polur Town BCR BCR 19-56

ECR Link

1 0+000 0+150 Cheyyur Town B A/F 10-13

2 0+000 4+720

Alemn Koil Village (Panayur/Odiyur Village Jn. At km 97/890 of SH-49)

WB/R WB/R 10-13

Note: A: Agriculture; B: Barren; R: Residential; C: Commercial

Source: DPR

C. Engineering Surveys and Investigations 53. Following surveys and investigations had been carried out on the project road for collection of data for incorporation in the DPR and to adapt the design for improvement and upgradation:

• topographic surveys; • traffic surveys;

19

• road and pavement condition survey and inventory; • culverts and bridges condition survey and inventories; • material surveys; • hydrology studies for new bridge structures; • Geotechnical investigations & subsoil exploration for structures; and • existing utilities surveys. D. Design Standards

54. This section describes the design standards and principles based on which the various designs have been carried out. The formulation of the design standards is required in order to avoid any inconsistency in design from one section to the other and to provide a desired level of service and safety. These proposed standards are consistent with the parameters recommended in the relevant standards of the Indian Roads Congress (IRC). The relevant IRC/ MORT&H design standards adopted for the Engineering Design are given below.

• Manual of Specifications and Standards for Two Laning of State Highways: IRC SP 73– 2015

• Manual of Specifications and Standards for Four Laning of State Highways: IRC SP 84 – 2014

• Ministry of Road Transport & Highways (MoRTH) specifications and circulars – Fifth edition.

1. Geometric Design

55. While doing the geometric design, the following have been taken into consideration:

• The designed facility shall not become obsolescent before the design year. • Design shall be consistent and the standards followed for different elements shall

be compatible with one another. • The design shall cover all geometric aspects of road including road, safety features,

road furniture, signages, grade separated structures, etc. • The design will be done aiming at minimizing the vehicle operating cost including

initial cost, cost of maintenance etc. • The design will take into consideration the environmental, aesthetic and landscaping

aspects of the project road.

2. Geometric Design Control

56. The detailed design for geometric elements covered, but were not limited to the following major aspects:

• Horizontal alignment • Longitudinal profile or vertical alignment • Cross-sectional elements • Junctions, intersections and Interchanges

57. The detailed analysis of traffic flow and level of service for the existing road has been made and traffic flow capacity for the project road was worked out. This analysis establishes the widening requirements with respect to the different horizon period.

20

58. Different options for providing grade separated interchanges and at grade intersections have been examined and the geometric design of interchanges has taken into account the site conditions, turning movement characteristics, level of service, overall economy and operational safety.

3. Horizontal Alignment

a. Design Speed

59. Design speed is the basic parameter were adopted, which determines the geometric features of the road. The proposed design speeds for state highway roads in different terrain categories as per IRC-73-1980 were adopted.

60. The project road located in plain terrain improved to provide minimum radius in most of the locations of curves to attain better alignment for the design speed of 80kmph to 100kmph except at built up location. The only physical hindrance in the existing road corridor was from the road side settlements and facilities scattered all along the road. The road is designed in accordance with agreed design standards depending on the type of terrain and the land-use. Further reductions in the design speed along sensitive land uses may be adopted to reduce noise and for pedestrian safety.

b. Radii of Curve

61. The geometry of the road is corrected to have the horizontal geometry correspond well with the IRC standards. At the locations where the existing geometry is not in accordance with the design standards, an attempt has been made to regularize it. The minimum radii of the curve corresponding to the design speed have been applied as per IRC stipulations.

62. The minimum radius of horizontal curves is calculated from the following formula:

R = V2 / 127 (e+f)

Where,

V = vehicle speed in Kmph

e = Super elevation in %

f = Co-efficient of friction between vehicle tyre and pavement (taken as 0.15)

R = radius in metres

63. Adopting a maximum value of 7% for super elevation, the minimum radius for horizontal curves works out to be per Table 8 as per IRC: 38/IRC SP-48. It is required to provide the desirable radius on the curves.

Table 8: Radius for Horizontal Curves

Terrain Categories

Radius of horizontal curves (m)

Desirable Minimum

Plain 400 255

Rolling 255 170

Mountainous 100 65

21

c. Super-elevation

64. The super elevation at curves have been arrived at as per the following equation: e=V2/225R

where: V = Vehicle speed in m/sec. e = Super elevation ratio in meter per meter R = Radius in meters.

65. The super elevation has been calculated keeping in view the horizontal radii and gradient at curves at different locations and maximum super-elevation is restricted to 7%.

d. Curves without Super Elevation

66. When the value of super elevation obtained from the parameters stated above is less than the road camber, the normal cambered sections are continued on the curve portion, without providing any super elevation. Normal camber of 3% is provided for flexible pavement.

e. Transition Curves

67. Transition curves are necessary for vehicle to progress smoothly from a straight section into a circular curve or between curves of different radius. The transition curve also facilitates a gradual application of the super elevation and any widening of the carriageway that may be required for the horizontal curves. The minimum length of the transition curve is determined from the following two considerations:

a. As per Comfort criteria, Ls = 0.0215 V3 / CR

Where, Ls = length of transition in metres V = Speed in kmph R = radius of circular curve in metres C = 80/ (75+V) (subject to maximum of 0.8 and minimum of 0.5)

b. b) As per rate of change of Super-elevation,

68. The rate of change of super elevation cannot be steeper than 1 in 150. The formula for minimum length of transitions depending on the terrain (plain/rolling) is: Ls = 2.7 V2 / R

f. Sight Distance

69. Intermediate sight distances have been adopted for the highway design as per the requirements of 2 lane manual provision. In general Intermediate Sight distance is adopted for the

22

2 lane sections but at locations where minimum intermediate sight distance cannot be followed safe stopping sight distance has been adopted.

4. Vertical Alignment

a. Gradients

70. The vertical alignment of the carriageway has generally been compatible with the guidelines given in the IRC SP 23 and the maximum gradient at all structure approaches is restricted to 2%.

• At locations of grade break of 0.5%, vertical curves have been provided. • The length of vertical curve is restricted to minimum 50 m • Number of PVI are not be more than 4 in one km. • At locations of sight deficiency, at least Stopping Sight Distance (SSD) are provided.

71. Safe stopping sight distance, both in the vertical and horizontal directions are applied in design where ever possible. The sight distance values as per IRC recommendations are given in Table 9.

Table 9: Sight Distance Design Speed (km/h) Safe stopping sight distance (m)

80 120

65 90

50 60

40 45

72. The vertical alignment of the project road is substantially designed for speeds of 80kmph to 100kmph.

5. Pavement Design

73. The entire road stretch is proposed as per the guidelines comprise of Flexible Pavement. Design is primary in accordance with IRC guidelines. The recommendation given in IRC: 37-2012, or equivalent method are used for new carriageway and paved shoulders. The pavement are designed for a service life of 20 years. Strengthening of the pavement by bituminous overlay are done periodically after 10 years.

74. Thickness requirements for flexible pavement has been established based on IRC: 81:1997 and IRC: 37-2012.

6. Embankments

75. Width: The width of the embankment is as per the approved typical cross-sections.

76. Height: The height of the embankment is as per the final road levels.

77. Slope Protection Embankments is protected with stone pitching as per “IRC 75-2015; Guidelines for Design of High Embankments”.

23

7. Grade Intersections

78. The locations where at grade junctions are required, the designs have been done as per the Guidelines given in MoRTH and on the basis of “IRC SP: 41-1994, Guidelines for the Design of At-grade Intersections in Rural and Urban Areas.”

8. Bus Stops

79. The bus bays where provided in accordance with guidelines specified in “IRC: 80-1981, Type Designs for Pick-up Bus Stops on Rural (i.e. Non-Urban) Highways”. The bus stop layout has been provided for safe entry and exit of buses and safe movement of passengers. Bus stops with passenger shelter are proposed at suitable selected locations.

9. Truck Parking Areas

80. The proposed layout and the locations of truck lay-by are generally based on the provisions of 2 lane manual; if required.

10. Traffic Safety Features, Road Furniture, Road Markings and Other Facilities

81. Traffic signs are missing at many locations on the project road. No warning signs exist before the junction and curves. Directional signs exist only at a few locations. These missing safety features will be the part of the proposed improvements. High Intensity Micro-Prismatic Grade sheeting (HIP) (Type IV) shall be provided.

82. Traffic Signs: The traffic signs are divided into three broad categories as warning signs, regulatory signs and information signs. Warning sign plays a crucial role in terms of road safety and for advance information about hazards ahead. Typical examples of warning signs are curve ahead, pedestrian crossings, gap in median etc. Regulatory/ Mandatory signs regulate the side of road or through traffic in order to have a safe movement. STOP, speed limit, NO parking and rest areas etc. are some of the regulatory traffic signs. Information signs are provided to give information and guidance about the facilities available to the road users. Village sign boards, fuel stations, hospitals etc are some of the information sign boards.

83. All critical locations are identified at the proposed geometric improvements along the project road and cross roads where Warning, Regulatory and Information signs are required. Traffic signs have been designed to convey clear and unambiguous messages to road users so that they can understand quickly and easily. IRC-67:1977, code for practice of road sign, has been followed for finalization of sign installation. On unkerbed roads segments, the extreme edge of the sign would be 2m to 3m from the edge of the carriageway. On kerbed road it is proposed as not less than 60 cm away from the edge of the kerb.

84. Road Markings: Road markings play a very important role in guiding the driver and providing the information necessary to negotiate conflict points on the road network. It is given a high priority to improve the safety. IRC-35: 1997, Code of Practice for Road Markings, provides the recommended practice for use of road markings. Road markings are lines, words and symbols attached to the carriageway or adjacent to the carriageway for controlling, warning, guiding and informing the users. Yellow, white and black colours are the standard colours used for marking. Road marking are classified as longitudinal marking, marking at intersections, marking at hazardous locations, marking for parking and word messages. Thermoplastic road markings have been proposed considering their long lasting effect.

24

85. Delineators: The delineators are effective on dangerous bends, on approaches to intersections and on embankments. Though all horizontal curves are designed to the IRC standards, delineators have been proposed for additional guidance and information to the commuter at curves (Radius less than 1000m). Locations along the high embankment have also been provided with delineators. Delineators with reflectorized panels have been considered.

86. Road lighting: Night-time accidents in urban areas can be substantially reduced by the implementation of adequate street lighting. The stretches of the project road traversing through the built-up/urban areas are proposed with adequate lighting. Road lighting has also been proposed at all major junctions. One/ Two/ Three arm bracket Sodium vapour lamps have been considered.

87. Crash Barrier: In addition to the adequate provisions of roadway width and roadside design, crash barrier/guard rails have been proposed along the roadway edge on either side based on the sections of the road:

88. For the embankments up to 3m height, reasonably flatter side slope of 1 vertical: 3 horizontal or more would enable erring vehicles to return to the traffic stream.

89. Roadside Facilities: The roadside facilities are provided as per the requirement of road users. On street parking, bus lay-by and bus shelters are proposed for project road of SH-115.

90. On-street Parking: The project road traverses through built-up areas where small commercial activities are carried out on both side of the road. The proposed 1.5m paved shoulder may be utilized for short time parking of the vehicles. This curb side parking is permitted only if stationary vehicles do not unduly interfere with free and safe movement of vehicles, bus lay byes, off street parking is proposed.

91. Bus lay-by and Shelters: Consultants have identified the location/site for the proposed bus lay bye for each village or built-up locations based on the following criteria:

92. Bus shelters are proposed near to settlement areas to minimize the walking distance and major intersection/junction should have direct pedestrian links segregated from motorized traffic.

93. It should be positioned in straight and level sections of road and should be visible from a long distance from both the directions.

94. For safety and operational reasons suitable safety features, road furniture and other facilities along the project road have been provided. These features included safety barriers, road signs, road markings, road lighting, route markers, kilometre and hectometre stones, road delineators, ROW pillars, parking areas and rest areas, bus stops/bays, and landscaping. Wherever possible these features are provided in accordance with relevant IRC or another standard, as detailed below. If no IRC Codes or the MoRTH Specifications are available, international standards such as BIS/AASHTO/ASTM/British Standards have been used in detailed design.

95. Road Humps: Road humps or speed breakers are formed by providing a rounded hump of 3.7m width (17m radius) and 100 mm height for the preferred advisory crossing speed of 25 kmph for general traffic as per the IRC: 99–1988. The basic material for construction is bituminous concrete formed to required shape. Road humps have been proposed on minor roads at junctions /intersections with major roads, School and Hospital zones. Proper signboards and markings are

25

provided to advise the drivers in advance of the situation. Road humps are extended across carriageway up to the edge of paved shoulder.

96. Rumble Strips: Rumble strips are formed by a sequence of transverse strips laid across a carriageway with maximum permitted height of 20 mm. These rumble devices produce audible and vibratory effects to alert drivers to take greater care and do not normally reduce traffic speeds in themselves. The typical design details of rumble strips proposed are transverse strips of Pre-mix bituminous concrete 500 mm wide and overall thickness 20 mm laid across a carriageway up to the end of paved shoulder. There will be 6 such transverse strips spaced at 0.5 m c/c. Proper signboards and marking are proposed to caution the drivers in advance of the situation. Rumble strips are proposed.

a. Sharp curves with radius less than 170m.

b. Transition zones (speed limit zones).

c. Village/built-up approaches.

d. Sensitive receptors (schools and hospitals)

E. Proposed Improvement

97. The project road will receive the following upgrades under the project:

a. Proposed ROW b. Embankment Height c. Bus Bays d. Cross Sectional Details e. Realignment and Bypasses f. Culverts and Bridges g. Geometric Design h. Intersections

1. Proposed Right of Way

98. The proposed RoW for the 2 lane configuration has been fixed as 16.0m in urban built-up areas, 23m in open and rural areas. The proposed RoW for bypasses has been fixed at 23 m. Widening in forest stretches will be carried out in within available RoW. There is a need for land acquisition for road widening and at the location of realignments and for bypass section. The total land (private & Govt.) acquisition for the project road improvement has been estimated as 43.74 hectares.

2. Embankment Height

99. As per IRC the embankment height shall be 1.0m from HFL to the top of sub grade. Keeping in view of local person's suggestion the proposed FRL is kept as 1.0m from the top of existing FRL.

3. Bus Bays

100. With various road improvement works, there are total 126 bus bays and passenger shelters are proposed along SH115 and ECR link. This includes 74 bus bays along SH115 road and 2 bus bays along ECR link .

4. Cross Sectional Details

26

101. The existing carriageway of project road is two lanes in most of the portions, however, in builtup sections existing carriageway is of intermediate lane configuration. The project road has a flexible pavement with 7m carriageway width. Widening is proposed concentric or eccentric (LHS/RHS), based on existing site conditions and technical requirements.

102. The project is proposed for widening of existing road to two lanes with paved shoulders. The typical cross sections (TCS) in built-up area, rural areas, overlay locations are shown in Figure 2.

Figure 2: Typical Road Cross Sections

27

28

29

30

31

32

33

34

35

36

37

38

39

5. Realignment and Bypasses

103. The project road has a number of congested towns throughout its length namely Vandavasi and Chetpet town. There are no existing bypass/ realignment on the project road from Cheyyur to Polur (SH-115) for the congested area. Two bypasses are proposed for one each for Vandavasi and Chetpet towns for free movement of the traffic and saving in travel time and fuel. The project road alignment is linear in nature.

104. Vandavasi bypass starts from km47+920 and ends at km53+810. Total length of this bypass is 5.89km. Chetpet bypass starts from km79+390 and ends at km82+980. Total length of this bypass is 3.59km. Additionally geometric improvement along the existing alignment is proposed at Maruthadu Village which starts at km42+84 and ends at km45+06 for a length of 2.22 km.

6. Culverts and Bridges

105. There are 3 major bridge, 15 minor bridges and one flyover existing on the project road section. Total 94 culverts will be reconstructed as new box culverts, 30 are retained/rehabilitated, 68 are proposed for widening and 68 new culverts are proposed along Cheyyur - Polur road and ECR link.

7. Borrow and Quarry Materials Sourcing

106. About 1,026,200 cum of borrow earth, 70,000 cum of fine aggregate and 7,28,000 cum of coarse aggregates is estimated to be required for the constructional activities of road section. The information about existing stone Quarries, Morum Quarries/ Borrow pits, Sand Quarries was collected from local PWD Divisional Offices and Sub divisional Offices, local construction contractors and local material suppliers throughout the project area, from other sources and from direct observation and by site visits. Location maps and type of material available in each project road were also collected and produced. The suitability of the materials sources is evaluated based on laboratory testing. After analyzing the suitability of those material sources quantitatively and qualitatively, the lead chart is prepared. The Locations of borrow area for the project road has been shown in Appendix 2.

8. Geometric Design

107. All the geometric design elements proposed in this project is carried out as per the design standards stipulated in IRC code provisions. Comprehensive design standards have been utilized linking individual design elements to best estimates of actual speed. The emphasis has been given on maintaining continuity or giving adequate warning where it could not be made. The realignment locations identified to improve the horizontal geometrics of the project road.

108. Plan and profile has been designed keeping in view the considerations such as design speed appropriate for the terrain and site constraints. The finished road level (FRL) given in the profile shall be followed as a minimum. However, the Contractor shall improve upon the plan and profile to the extent possible within the site (proposed ROW) with prior approval of CSC.

109. Except in the following curve locations the design speed all along the project road is designed as 80 kmph to 100 kmph and will be kept as the operational speed..

40

• The speed has been restricted due to geometry and social impacts (e.g. school, places of worship, hospital, etc.) with additional signages in the specific chainages.

• Improvement of the existing road geometrics.

9. Intersections

110. The important major and minor junctions leading to villages and major settlements have been identified and improvement of junctions has been carried out based on peak hour traffic data and accident record. The major and minor junction along the project road is provided in Table 10.

Table 10: Junction Improvement with Transverse Rumble Strip

S.No. Existing

Chainage (Km)

Proposed Chainage

(Km)

Type of Junction

Side Remarks

Cheyyur -Vandavasi - Polur Road (SH-115)

1 1+780 1.779 4-Legged LHS CC road to Cheyyur Village.

2 1+780 1.779 4-Legged RHS CC road to Cheyyur Village.

3 1+940 1.941 3-Legged RHS CC Road to Pavanjur

4 2+115 2.114 3-Legged RHS CC Road to Cheyyur

5 2+130 2.128 3-Legged LHS CC Road to Devrajpuram Village

6 2+380 2.378 3-Legged LHS CC Road to Bus Stop

7 2+468 2.468 3-Legged RHS CC Road to Cheyyur

8 2+520 2.517 3-Legged LHS BT Road to VKR Nagar

9 2+907 2.906 3-Legged RHS CC Road to Cheyyur

10 3+178 3.178 3-Legged LHS BT Road to Cheyyur

11 3+400 3.400 3-Legged LHS CC Road to Cheyyur

12 4+430 4.432 3-Legged RHS CC Road to Kicheri

13 5+080 5.085 3-Legged RHS CC Road to Nallur

14 5+225 5.230 3-Legged LHS LHS BT Road to Villivakkam.

15 6+735 6.736 3-Legged RHS CC Road to Viralur

16 7+155 7.158 3-Legged RHS BT Road to Periyavenmani

17 7+707 7.710 3-Legged LHS BT Road to Nalur/ Bandaigarnai

18 7+717 7.719 3-Legged RHS BT Road to Vanamvakkam

19 7+880 7.880 3-Legged RHS CC Road to Local Area

20 9+433 9.439 3-Legged RHS BT Road to Chittamur

21 9+458 9.464 3-Legged LHS BT Road to Vetur

22 10+885 10.890 3-Legged LHS CC Road to kattudhevathur Village

23 11+135 11.142 3-Legged RHS BT Road to Kalamvakkam

24 11+148 11.157 3-Legged LHS BT Road to Kadai Vathur Village

25 11+888 11.895 3-Legged LHS CC Road to Local Area

26 11+920 11.927 3-Legged LHS CC Road to Local Area

27 12+117 12.124 3-Legged LHS CC Road to Local Area

28 13+077 13.085 3-Legged LHS CC Road to Nallamur

29 13+167 13.175 3-Legged LHS CC Road to Nallamur

30 13+638 13.647 3-Legged LHS BT Road to Nallamur

41

S.No. Existing

Chainage (Km)

Proposed Chainage

(Km)

Type of Junction

Side Remarks

31 13+648 13.655 3-Legged RHS CC Road to Graveyard

32 13+785 13.791 3-Legged RHS CC Road to Graveyard

33 13+860 13.867 3-Legged LHS CC Road to Local Area

34 13+867 13.874 3-Legged RHS BT Road to Kolathur

35 14+498 14.509 3-Legged LHS BT Road to Tonadu

36 15+927 15.940 3-Legged RHS BT Road to Sarvambakkam

37 16+195 16.219 3-Legged RHS CC Road to Chitamur Village

38 16+308 16.332 3-Legged LHS CC Road to Chitamur Village

39 18+068 18.085 3-Legged LHS BT Road to Perambakkam

40 18+285 18.305 3-Legged RHS BT Road to Polupakkam

41 20+203 20.230 3-Legged RHS CC Road to Village

42 20+365 20.390 3-Legged RHS CC Road to Kurumpirai Village

43 20+500 22.537 3-Legged RHS BT Road to kurumpirai Village

44 21+310 21.344 3-Legged LHS BT Road to Irumbili Village

45 21+800 21.837 3-Legged RHS BT Road to Poraiyur Village

46 22+155 22.194 4-Legged LHS Gravel Road to Keelmaruvathur

47 22+155 22.194 4-Legged RHS BT Road to Pakkami.

48 22+340 22.378 3-Legged LHS CC Road to Poraiyur

49 22+685 22.725 3-Legged LHS BT Road to Keelmaruvathur

50 22+775 22.813 3-Legged LHS CC Road to Sothupakkam

51 22+875 22.914 3-Legged RHS CC Road to Sothupakkam

52 22+950 22.989 3-Legged LHS CC Road to Sothupakkam

53 23+185 23.231 3-Legged RHS CC Road to Sothupakkam

54 23+725 23.747 3-Legged LHS CC Road to Sothupakkam

55 23+900 23.921 3-Legged LHS CC Road to Sothupakkam

56 23+1010 24.032 3-Legged LHS CC Road to Sothupakkam

57 23+1085 24.108 3-Legged LHS CC Road to Sothupakkam

58 24+165 24.288 3-Legged RHS BT Road to Village

59 24+190 24.315 3-Legged RHS CC Road to Sothupakkam

60 24+285 24.408 3-Legged LHS CC Road to Adhipara Sakthy Institute

61 24+340 24.464 3-Legged RHS CC Road to Sothupakkam

62 24+445 24.567 3-Legged RHS BT Road to MelmaduVillage

63 24+880 25.005 3-Legged RHS BT Road to Chinthamani

64 24+995 25.119 3-Legged RHS BT Road to Chinthamani

65 25+725 25.858 3-Legged RHS CC Road to Private Land

66 26+405 26.539 3-Legged RHS BT Road to Agili Village

67 26+830 26.960 3-Legged LHS BT Road to Neman Athivakkam

68 27+280 27.414 3-Legged RHS BT Road to Sandyvakkam

69 27+590 27.722 3-Legged LHS BT Road to Sandyvakkam

70 27+645 27.779 3-Legged RHS BT Road to Sandyvakkam

71 29+680 29.826 3-Legged RHS BT Road to Kizhamur

42

S.No. Existing

Chainage (Km)

Proposed Chainage

(Km)

Type of Junction

Side Remarks

72 31+460 31.608 3-Legged RHS BT Road to Pasuvankranai

73 31+600 31.750 3-Legged RHS CC Road to Padrikeera more

74 31+625 31.776 3-Legged LHS BT Road to Kattukarnai

75 31+705 31.854 3-Legged LHS CC Road to Factory

76 31+775 31.923 3-Legged LHS CC Road to Velamur

77 31+785 31.932 3-Legged RHS CC Road to Ramapuram

78 32+235 32.386 3-Legged LHS BT Road to Mogalvadi/Alapakkam

79 32+431 32.594 3-Legged RHS BT Road to Ramapuram

80 32+655 32.814 3-Legged LHS CC Road to Mogalvadi

81 32+835 32.994 3-Legged LHS CC Road to Bardas Nagar

82 32+955 33.111 3-Legged LHS CC Road to Bardoss Nagar

83 33+385 33.555 3-Legged RHS BT Road to Redypalayam

84 34+130 34.300 3-Legged LHS BT Road to Karudapuram

85 34+950 35.119 3-Legged RHS BT Road to Mettupalayam/Ottakoil Lake

86 35+185 35.353 3-Legged LHS CC Road to Salavedu Village

87 35+275 35.445 3-Legged LHS CC Road to Salavedu Village

88 35+675 35.848 4-Legged LHS BT Road to Salavedu Village.

89 35+675 35.848 4-Legged RHS BT Road to Salavedu Village.

90 35+700 35.858 3-Legged LHS CC Road to Salavedu Village

91 35+760 35.917 3-Legged LHS CC Road to Salavedu Village

92 35+825 35.983 3-Legged LHS CC Road to Salavedu Village

93 35+980 36.120 3-Legged LHS CC Road to Salavedu Village

94 36+100 36.258 3-Legged LHS CC Road to Salavedu Village

95 36+660 36.821 3-Legged RHS BT Road to Salavedu Village

96 38+895 39.058 3-Legged RHS CC Road to Mamandur Village

97 39+280 39.450 4-Legged LHS BT Road to Mamandur Village

98 39+280 39.450 4-Legged RHS CC Road to Uthiramerur

99 40+675 40.850 3-Legged LHS BT Road to Katai Village

100 40+800 40.973 3-Legged RHS BT Road to Melkugadathur Village

101 41+620 41.800 4-Legged LHS CC Road to Kallankuttu Kaveripakkam Village

102 41+620 41.800 4-Legged RHS CC Road to Kallankuttu Kaveripakkam Village

103 41+658 41.838 3-Legged LHS CC Road to Maruthadu Realignment

104 41+720 41.904 3-Legged LHS CC Road to Kallankattu Kaveripakkam

105 41+830 41.984 3-Legged RHS BT Road to kallankuttu Kaveripakkam

106 42+205 42.386 3-Legged RHS CC Road to Kaveripakkam

107 42+420 42.600 3-Legged RHS CC Road to Village

108 42+425 42.605 3-Legged LHS BT Road to Aadha ManglamVillage

109 42+498 42.675 3-Legged LHS CC Road to Kallankattu

43

S.No. Existing

Chainage (Km)

Proposed Chainage

(Km)

Type of Junction

Side Remarks

110 42+545 42.723 3-Legged RHS CC Road to Kallankattu

111 42+665 42.848 3-Legged LHS CC Road to Kallankattu

112 - 43.404 4-Legged RHS BT Road to Village

113 - 43.404 4-Legged RHS BT Road to Village

114 - 44.047 4-Legged LHS BT Road to Voshur

115 - 44.047 4-Legged RHS BT Road to SH-115

116 45+205 45.763 3-Legged RHS CC Road to Kadaisikulam Village

117 45+483 46.037 3-Legged LHS CC Road to Kadaisikulam Village

118 45+530 45.084 3-Legged LHS CC Road to Kodaisikulam

119 45+700 46.347 3-Legged RHS CC Road to Kodaisikulam

120 45+845 46.400 3-Legged LHS BT Road to Suryakuppam Village

121 - 48.646 4-Legged LHS Road to Vandavasi

122 - 48.646 4-Legged RHS Road to Vandavasi

123 - 48.932 4-Legged LHS Road to Temple

124 - 48.932 4-Legged RHS Road to Vandavasi

125 - 50.038 4-Legged LHS Road to Sedarakuppam

126 - 50.038 4-Legged RHS Road to Vandavasi

127 - 53.454 4-Legged LHS BT Road to Kilsathmanglam

128 - 53.454 4-Legged RHS BT Road to Vandavasi

129 54+100 55.218 3-Legged LHS CC Road to Mampattu Village

130 54+160 55.277 3-Legged RHS CC Road to Mummuni Village

131 54+375 55.495 3-Legged LHS CC Road to Mampattu Village

132 54+385 55.505 3-Legged RHS CC Road to Mummuni Village

133 54+395 55.512 3-Legged LHS CC Road to Terur Village

134 54+960 56.077 3-Legged LHS BT Road to Avnavadi Village

135 56+055 57.168 3-Legged LHS BT Road to Arasur Village

136 56+430 57.545 3-Legged LHS BT Road to Ponnur Village

137 56+525 57.640 3-Legged RHS CC Road to Arasur Village

138 56+615 57.730 3-Legged RHS BT Road to Arasur Village

139 57+612 58.723 3-Legged RHS CC Road to village

140 59+190 60.300 3-Legged LHS BT Road to Ponnur Hill

141 59+565 60.677 3-Legged RHS BT Road to Melpadi Village

142 60+325 61.438 3-Legged RHS CC Road to Thimanithangal Residential Area

143 60+377 61.490 3-Legged RHS CC Road to Thimanithangal Residential Area

144 60+470 61.578 3-Legged LHS BT Road to Kundampattai Village

145 61+455 62.562 3-Legged RHS BT Road to vadavankambadi Village

146 61+905 63.014 3-Legged LHS BT Road to Kilvelliyur Village

147 62+050 63.153 3-Legged LHS CC Road to Kilvelliyur

148 63+630 64.737 4-Legged LHS BT Road to Desur Village

44

S.No. Existing

Chainage (Km)

Proposed Chainage

(Km)

Type of Junction

Side Remarks

149 63+630 64.737 4-Legged RHS BT Road to Vallam Village

150 63+723 64.830 3-Legged LHS CC Road to Desur village

151 64+270 65.377 3-Legged RHS BT Road to Thenkarrai Village

152 64+690 65.794 3-Legged LHS CC Road to Karambai Village

153 65+225 66.328 3-Legged LHS BT Road to Dayasur Village

154 65+290 66.393 3-Legged LHS CC Road to Majhaiyur Village

155 65+312 66.418 3-Legged LHS CC Road to Majhaiyur Village

156 65+327 66.435 3-Legged RHS BT Road to Graveyard

157 65+595 66.694 3-Legged RHS CC Road to Mazhaiyur

158 65+807 66.913 3-Legged LHS CC Road to Majhaiyur Village

159 65+943 67.049 3-Legged RHS CC Road to Majhaiyur Village

160 66+052 67.147 3-Legged RHS BT Road to Korwari Village

161 66+415 67.510 3-Legged RHS CC Road to Majhaiyur Village

162 66+485 67.579 3-Legged LHS CC Road to Mazhaiyur

163 66+540 67.634 3-Legged RHS CC Road to Majhaiyur Village

164 66+938 68.033 3-Legged RHS CC Road to Majhaiyur Village

165 67+038 68.146 3-Legged LHS CC Road to Majhaiyur Village

166 67+110 68.218 3-Legged LHS CC Road to Majhaiyur Village

167 67+435 68.543 3-Legged RHS BT Road to Matatliur Village

168 67+605 68.713 3-Legged LHS BT Road to Matathur Village

169 68+057 69.159 3-Legged RHS BT Road to Earthal Village

170 68+092 69.190 3-Legged LHS BT Road to Solaiayuvur Village

171 68+620 69.717 3-Legged LHS BT Road to Kalyanapuram Village

172 69+362 70.461 3-Legged RHS BT Road to Ettithangal Village

173 70+315 71.416 3-Legged LHS CC Road to Chinakoiyapolur Village

174 70+325 71.426 3-Legged RHS CC Road to Chinakoiyapolur Village

175 70+890 71.990 3-Legged RHS BT Road to Peramandulur Village

176 70+895 71.995 3-Legged LHS CC Road to Chinakoiyapolur Village

177 70+940 72.038 3-Legged LHS BT Road to Kothupakkam Village

178 71+390 72.495 3-Legged LHS BT Road to J.Patti

179 72+318 73.408 3-Legged LHS BT Road to Jaganathpuram Village

180 72+670 73.758 3-Legged RHS BT Road to Melathangal Village

181 73+670 74.770 3-Legged RHS BT Road to Bulukumbattu Village

182 74+925 76.028 3-Legged LHS CC Road to Lake

183 75+043 76.150 4-Legged LHS CC Road to Nedungunam Village

184 75+043 76.150 4-Legged RHS CC Road to Nedungunam Village

185 75+188 76.295 3-Legged RHS CC Road to Nedungunam Residential Area

186 75+324 76.428 3-Legged LHS Interlink CC Road

187 75+455 76.562 3-Legged LHS CC Road to Nedungunam Village

188 75+467 76.571 3-Legged RHS CC Road to Nedungunam Village

45

S.No. Existing

Chainage (Km)

Proposed Chainage

(Km)

Type of Junction

Side Remarks

189 75+613 76.721 3-Legged LHS CC Road to Nedungunam Village

190 75+805 76.913 3-Legged LHS CC Road to Nedungunam Village

191 76+1000 78.107 3-Legged LHS CC Road to Church(Hill Top)

192 76+1017 78.120 3-Legged LHS BT Road to Melvillibalam Village

193 77+500 78.668 3-Legged LHS CC Road to Nedugunam

194 80+620 83.041 3-Legged RHS BT Road to Nirmal Nagar

195 80+670 83.089 3-Legged RHS BT Road to Nirmala Nagar

196 80+805 83.225 3-Legged RHS CC Road to Kannanur Village

197 80+850 83.269 3-Legged RHS CC Road to Nirmala Nagar

198 80+970 83.389 3-Legged RHS CC Road to nirmala Nagar

199 81+023 83.443 3-Legged RHS CC Road to Nirmal Nagar

200 81+155 83.575 3-Legged RHS CC Road to Nirmal Nagar

201 81+310 83.730 3-Legged RHS CC Road to Nirmal Nagar

202 81+590 84.010 3-Legged LHS BT Road to Idayankulathur

203 82+407 84.825 3-Legged RHS CC Road to Local Area

204 82+610 85.027 3-Legged RHS CC Roads to Edayan Kulathur

205 82+615 85.032 3-Legged LHS CC Roads to Edayan Kulathur

206 83+055 85.475 3-Legged RHS BT Road to Maruthuvampadi Village

207 83+153 85.568 3-Legged LHS BT Road to Parthipuram Village

208 84+420 86.832 3-Legged RHS BT Road to Nambedu

209 84+525 86.937 3-Legged LHS CC Roads to Nambedu

210 85+195 87.608 3-Legged RHS CC Roads to Nambedu

211 85+210 87.620 3-Legged LHS BT Road to Sevarampoondi Village

212 85+227 87.639 3-Legged RHS BT Road to Karripur Village

213 85+288 87.700 3-Legged RHS CC Roads to Nambedu Lake

214 85+955 88.368 3-Legged RHS BT Road to Kolakarvady Village

215 87+300 89.710 3-Legged RHS WBM Road Right Side

216 87+880 90.294 3-Legged LHS BT Road to Cheyyanandal Village

217 88+005 90.395 3-Legged LHS CC Roads toThatchambadi

218 88+485 90.877 3-Legged LHS CC Roads toThatchambadi

219 88+525 90.915 3-Legged LHS CC Roads toThatchambadi

220 89+185 91.586 3-Legged LHS BT Roads toChayanandan

221 90+250 92.651 3-Legged LHS CC Road to Devikapuram

222 90+330 92.732 3-Legged RHS CC Roads to Devikapuram

223 90+418 92.820 3-Legged LHS CC Roads to Devikapuram

224 90+455 92.857 3-Legged RHS CC Roads to Devikapuram

225 90+495 92.896 3-Legged LHS CC Roads to Devikapuram

226 90+500 92.903 3-Legged RHS CC Roads to Devikapuram

227 90+840 93.239 3-Legged LHS CC Roads to Devikapuram

228 90+915 93.315 4-Legged LHS BT Road to Avalupetial Village

229 90+915 93.315 4-Legged RHS BT Road(ODR) to Arni

46

S.No. Existing

Chainage (Km)

Proposed Chainage

(Km)

Type of Junction

Side Remarks

230 91+122 93.531 3-Legged RHS BT Roads to Arni

231 91+140 93.547 3-Legged LHS BT Roads to Athurai

232 91+200 93.603 3-Legged RHS CC Roads to Devikapuram

233 91+288 93.693 3-Legged RHS CC Roads to Devikapuram

234 91+328 93.731 3-Legged RHS CC Roads to Devikapuram

235 91+612 94.016 3-Legged RHS CC Roads to Devikapuram

236 91+753 94.157 3-Legged RHS CC Roads to Devikapuram

237 93+015 95.420 3-Legged RHS BT Roads to Madiamerade

238 93+887 96.294 3-Legged RHS CC Roads to Modaiyur

239 94+045 96.468 3-Legged LHS CC Roads to Modaiyur

240 94+170 96.590 3-Legged LHS BT Road to Modiyur

241 94+195 96.617 3-Legged RHS CC Roads to Uthur

242 94+393 96.813 3-Legged RHS CC Roads to Modaiyur

243 94+478 96.898 3-Legged RHS CC Roads to Modaiyur

244 95+605 98.032 3-Legged RHS BT Roads to Arambulur

245 96+050 98.513 3-Legged LHS BT Road to Mattapayur

246 97+170 99.613 3-Legged RHS BT Roads to Madakolathur

247 97+268 99.710 3-Legged LHS BT Roads to Mathuputtu

248 97+923 100.365 3-Legged LHS BT Road to Mandakolathur

249 98+395 100.822 3-Legged RHS CC Roads to Pullivanandal

250 98+500 100.926 3-Legged LHS BT Road to Pulivanadal

251 99+205 101.630 3-Legged LHS BT Roads to Tiruvattinandal

252 99+670 102.097 3-Legged LHS BT Roads to Tiruvattinandal

253 99+950 102.378 3-Legged RHS BT Roads toMandakolathur

254 99+995 102.419 3-Legged LHS BT Roads to Sothukanni

255 100+267 102.708 3-Legged LHS CC Roads to Komnandal

256 100+290 102.734 3-Legged RHS BT Roads to Kulathur

257 100+670 103.111 3-Legged LHS BT Road to Komanandal

258 101+670 104.115 3-Legged LHS BT Roads to Koralpakkam

259 101+700 104.144 3-Legged RHS CC Roads to Karaipoondi

260 102+360 104.842 3-Legged LHS CC Roads to Venmani

261 102+475 104.957 3-Legged LHS CC Roads to Venmani

262 103+050 105.527 3-Legged LHS CC Roads to Venmani

263 103+118 105.603 3-Legged LHS CC Roads to Venmani

264 103+290 105.766 3-Legged RHS CC Roads to Venmani

265 103+357 105.830 3-Legged LHS CC Roads to Venmani

266 103+640 106.110 3-Legged RHS BT Roads to Pappambadi

ECR LINK

Sl. No.

Existing Chainage (Km)

Proposed Chainage (Km)

Leg Side Remarks

47

1 3+490 3.435 4-Legged LHS BT Road to Odiyur

2 3+490 3.435 4-Legged RHS BT Road to Mugaiyur.

3 3+660 3.712 3-Legged RHS BT Road to Cheyyur

4 3+875 3.825 3-Legged LHS BT Road to Alemn Koil

5 3+890 3.839 3-Legged RHS BT Road to Alemn Koil

6 3+950 3.900 3-Legged RHS CC to Alemn Koil

7 4+162 4.110 3-Legged LHS BT Road to Alemn Koil

8 4+170 4.118 3-Legged RHS BT Road to Alemn Koil

9 4+515 4.464 3-Legged LHS BT Road to Village

10. Water for Construction

111. The water requirement has been assumed based on past project experience and on the strict quality control basis. A domestic requirement of 150 liters per worker for each day has been assumed. For this project about 250 resident workers have been considered. A volume of 540 KLD (40 KLD domestic water demand and average 500 KLD water required for construction activities) during the construction phase will be taken from surface water bodies or withdrawn ground water after obtaining necessary permissions, in such a manner that the local water supply is not affected. The water withdrawal will not be from the single location as the project is linear in nature. No water will be sourced from local public utility for road construction.

F. Construction Camps

112. Two construction camp will be set up by the contractor at a suitable location along the project corridor which will be in consultation with the Project Director and Tamil Nadu State Pollution Control Board. The camp will be setup away from the settlements, in the downwind direction. The guidelines for siting & layout of construction camp is given in Appendix 9.

G. Project Cost

113. Based on the bill of quantities and unit rates, the total project cost (inclusive of GST, price variation, utility shifting, overlay, maintenance and other contingencies etc.) was estimated for Rehabilitation and upgrading Cheyyur - Polur road (SH-115) and ECR link and is about INR 900.93 Cr. H. Construction Packaging and Implementation Schedule

114. The Project Road Section is proposed for single construction package under EPC procurement mode as being carried out for fast track corridors. The contract duration is decided based on the conductive time period available for construction and the ease of providing the encumbrance free site to the contractor. Keeping in view of all these aspects duration of 42 months is proposed for construction. The project is proposed to be undertaken through International Competitive Bidding (ICB). I. Project Benefits

115. The implementation of various project items is envisaged to have the following direct benefits:

48

• better connectivity to key locations within State;

• smooth flow of traffic on State Highway Network;

• improved quality of life for the rural population in the project influence: this as a result of better access to markets, health, education and other facilities; and the derived stimulus for local economic activity;

• a more efficient and safe road transport system: through reduced travel times, reduced road accidents, reduced vehicle operating and maintenance costs and reduced transportation costs for goods; and

• the facilitation of tourism.

49

IV. DESCRIPTION OF THE ENVIRONMENT

A. Introduction

116. In order to assess the impacts of the proposed improvement to the project road, field visits were undertaken to understand environmental profile of the project influence area. This involved field inspections at all the sensitive locations, collection of secondary information for all the environmental components and discussions with the officials, NGO’s and local populace. The profile presented below comprises of the following:

• Physical environmental components such as meteorology, geology, topography, soil

characteristics, ambient air quality, surface and sub-surface water quality;

• Biological environmental components such as aquatic life, avian and terrestrial fauna, vegetation and other flora, fauna and mammals, and

• Land environment in terms of land use, soil composition.

117. The data on water, soil, air and noise were collected through field monitoring. The environmental monitoring was carried out by NABL accredited laboratory “Global Lab and Consultancy Service Pvt. Ltd.”, Salem in the month of November- December 2019 for baseline air, noise, water and soil parameters. Climatological data was collected from India Meteorological Department. Efforts have been made to compile the available data from literature, books, maps and reports. The methodology adopted for data collection is highlighted wherever necessary. Environmental attributes and frequency of baseline surveys are presented in Table-11. The environment parameters monitoring locations are shown in Figure 3. The baseline parameters are selected as specified by regulatory agencies in India and number and locations of the sampling are selected with due consideration to environmental sensitivity along the project line alignment and as agreed upon with the client.

Table 11: Environmental Attributes and Frequency of Monitoring

S. No Attribute Parameter No. of Samples Source

LAND ENVIRONMENT

1 Geology Geological Status --- Literature review

2 Seismology Seismic Hazard --- Literature review

WATER ENVIRONME

3 Water Quality

Physical, Chemical and Biological parameters. i.e., pH, DO, BOD, Oil and grease, COD, total Suspended Solids, total dissolved solids, total solids, chlorides Turbidity and Alkalinity.

3-Ground water and 3- Surface water

Sampling/ monitoring locations

AIR, NOISE, SOIL AND METEOROLOGY

4 Ambient Air Quality & meteorological conditions

PM2.5, PM10, Carbon Monoxide (CO), Oxides of Nitrogen (NOx) and Sulphur Dioxide (SO2).

Five Sampling/ monitoring locations

5 Noise Noise levels in dB (A) Twelve

50

S. No Attribute Parameter No. of Samples Source

Leq, Lmax, Lmin, L10, L50, L90

Sampling/ monitoring locations

6 Soil Quality Physico-chemical parameters

Six Sampling/ monitoring locations

BIODIVERSITY AND ECOLOGY

7 Terrestrial Flora/Vegetation

Type of vegetation, trees and flora

Once (over 1 week period)

Literature review, field inventory / sampling, and consultations

8 Fauna and Wildlife Wildlife and Species Once (over 1 week period

Literature review, field surveys, and consultations with wildlife/forest officials and experts

SOCIO-ECONOMIC

9 Socio-economic aspects

Socio-economic profile Once Field studies, literature review.

Figure 3: Environmental Monitoring Locations along the Project Road

AAQ: Ambient Air Quality Monitoring Locations, N: Noise Monitoring Locations, SW: Surface Water Quality Monitoring Locations, GW: Ground Water Quality Monitoring Locations, S: Soil

Quality Monitoring Locations

51

B. Physical Environment

118. Information of various physical parameters was collected from the Indian Meteorological Department (IMD), Statistical Department, Gazetteer of Tamil Nadu, Forest Department, Department of Environment and other concerned government departments and discussions with the officials from these agencies.

1. Meteorological Conditions

119. Meteorology plays an important role in transport, diffusion and dispersion of pollutants in the atmosphere. Due to this reason meteorological data has been collected from the field in the month of November- December 2019 as well as secondary data has taken from the IMD website.

120. Among all other physical factors, climate is the most important factor-influencing environment because it plays a vital role in determining the evolution of landforms (erosion, soil characteristics), types of flora and fauna (ecological diversity), the productivity of ecosystems. It also has an influence on the pollution loads on the environment.

121. The climate of Tamil Nadu state is tropical, with distinct wet and dry seasons. According to Agro-ecological classification, the state has hot and semi-arid climate. The climate may be classified into four distinct seasons: winter (January – February), summer (March – May), southwest monsoon (June – September) and northeast monsoon (October – December).

122. The project districts Kanchipuram and Tiruvannamalai districts fall in the semi-Arid Tropical Zone of climatic classification. There are mainly three seasons in Tamil Nadu, but duration of the season varies as per the location of the district.

123. The various climatic factors such as temperature, humidity and rainfall pattern in the project area have been discussed in detail in the following sections.

a. Rainfall

124. The state has distinct periods of rainfall, which are the advancing monsoon period, South West monsoon (from June to September) with strong southwest winds, the North East monsoon (from October to December), with dominant northeast winds, and the Dry season (from January to May). The average annual rainfalls in Tamil Nadu range between 635mm and 1905mm a year of which 48% is through the North East monsoon, and 32% through the South West monsoon, whereas, the normal rainfall in the state is about 950mm with an average number of 50 rainy days.

125. Monsoon season starts in June and ends in the month of November. 70% of the total rainfall occurs during monsoon season while February to April is dry period. The extreme climatic conditions sometimes occurs which include cyclones/depression. Rainfall data collected from Regional Meteorological Centre, Vellore shows that the average annual rainfall in the project area varies from 773 mm to 1775 mm (Vandavasi: 957 mm to 1407 mm, Kanchipuram: 773 mm to 1775 mm, Chengalpattu: 1092 mm to 1534 mm, Arani: 826 mm to 1570 mm). Rainfall mainly occurs during north to east monsoon.

126. The rainfall distribution map of Tamil Nadu is shown in figure 4. From figure 4 it is clear that project road lies in area of high rainfall region of the state. The actual rainfall in project district for the last five years (2014-2018) as provided by the Hydro-met division of the India Meteorological Department is given in Table 12.

52

Figure 4: Rainfall Distribution in the State of Tamil Nadu

Table 12: Average Annual Rainfall (mm) in Project Districts

Year Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec

Kanchipuram

2014 0.5 3.4 0 0 35.7 117.6 50.9 130.9 130.6 196.3 135 106.9

2015 1.7 0 0 49.5 45.4 32.2 102.2 140.4 70.3 179.8 1061.3 574

2016 0.4 0 0 0 173.2 81.6 76.6 112.7 213.3 28.6 26.1 280

2017 16.4 0.1 0 0 14.4 67.8 98.8 228.6 98.7 287.6 335.7 49.3

2018 2.6 1.8 7.9 0.4 6.2 51.1 64.8 189.7 91.4 133 241.1 43

Tiruvannamalai

2014 0 10 0 0 94.9 67.4 68.9 149.2 160 123.3 66.2 59.4

2015 0 0 1.8 114.7 61 81.3 92.1 175.8 124.9 127.3 326.4 142

2016 9 0 0 0 84.1 103.5 116.3 95.9 103.3 64.8 6.1 101.6

2017 47 0 4.9 3.4 49.2 55.6 69.1 366.5 130.7 276.5 80.4 168

2018 0 34.9 34.2 3.7 14.5 58.3 72 42.8 136.6 180.6 187.5 25

Source: IMD

127. Above rainfall data shows that project districts received maximum rainfall during months of August– December i.e., in rainy and winter season.

b. Temperature

128. The climate of Tamil Nadu is tropical in nature with little variation in summer and winter temperatures. While April-June is the hottest summer period with the temperature rising up to the 40oC mark whereas November-February is the coolest winter period with temperature ranging between 10°C-20oC which makes the climate quite pleasant.

Project Road

53

129. In project districts, April and May months are the hottest months with mean monthly temperature varying between 36.3oC and 40.8oC. December and January are comparatively the coolest months with average mean monthly temperature varying from 16.1 oC to 20.5 oC. The minimum monthly temperature is 16 oC in the project area.

130. The minimum, maximum and average temperature recorded during the study period (November- December 2019) were 23.5 °C, 37.5 °C and 30.5 °C; respectively. However the average temperature recorded was along the project road. Project region falls in strong hyperthermic zone as per temperature distribution map of Tamil Nadu State. The temperature distribution map of Tamil Nadu is presented in figure 5.

Figure 5: Temperature Distribution Map of Tamil Nadu

131. The project influenced area (PIA) has humid and sub-humid climate as shown in Figure 6. The analysis of five year humidity data taken at 8.30 am and 5.30 pm indicates the maximum humidity value of 93% and minimum as 35%. The humidity decides the nature and characteristics of pollution in the atmosphere. Fog helps in coalescence of suspended particles and enhances the chemical reaction of gaseous pollutants. Humidity is high during the monsoon season and rest of the year, air is generally dry.

132. The minimum and maximum humidity recorded during the study period (November- December 2019) were 51 % and 96 %. However the average humidity recorded was 75.9 % along the project road.

Project Road

54

Figure 6: Humidity Map of Tamil Nadu

c. Winds

133. Wind speed and wind direction have a significant role on the dispersion of atmospheric pollutants and therefore, the air quality of the area. Ground level concentrations for the pollutants are inversely proportional to the wind speed in the down wind direction, while in upwind direction no effect will be observed and in cross wind direction partial effect due to the emission sources is observed.

134. The minimum and maximum wind speed observed along the alignment during field monitoring was 1 kmph and 9 kmph; respectively. The dominating wind direction observed along the alignment during field monitoring was NW (North-West) followed by SW (South-West).

135. The details of other meteorological parameters observed along the road section during the baseline environmental monitoring is given in Appendix 3.

d. Climate Risks and Vulnerability

136. A detailed climate risk and vulnerability assessment has been prepared for the project in compliance with ADB requirements. The assessment revealed that the project has high overall risk for flooding due to extreme rainfall, storm surges, and other extreme events such as water scarcity and heat waves. Measures to address these have been included in the design which include increased drainage capacity and embankment heights2.

2 Details in the Project Climate Change Assessment and Climate Risk and Vulnerability Assessment Report

Project Road

55

2. Topography and Geography

137. Geomorphologically from west to east, three major units are recognised in Tamil Nadu: the Western Ghats, the Central Region and the Coastal Plains. The project road falls in Kanchipuram district of Tamil Nadu. The terrain is generally plain and rolling terrain.

138. Kanchipuram: Kanchipuram district is situated on the Northern East Coast of Tamil Nadu and is bounded by Vellore and Tiruvannamalai district in the west; Tiruvallur district and Chennai district in the north. Kanchipuram city is at an elevation of 83.2m above sea level. The land around Kanchipuram is flat and slopes towards the south and east. Kancheepuram district is classified into coastal areas and other plain lands with small intermittent hills. Few residual hills such as St.Thomas Mount, Thirukkalukundram hills and Vandalur hills are found in the district. The general elevation of the district ranges from 0.5m to 230m AMSL.

139. Thiruvannamalai District lies between 11° 55' and 13° 15' North latitude and 78° 20' to 79° 50' East longitude. The district is bounded on the north and west by Vellore District, on the southwest by Dharmapuri District, on the south by Villupuram District and on the east by Kanchipuram District.

140. The topography (altitude) map for the State of Tamil Nadu is presented in Figure 7 wherein project road is also marked. As can be inferred from the map, the project region has plain topography having an altitude in the range of 1-300m AMSL.

141. Also, the elevation of project road is shown in Figure 8. As observed from figure, elevation of project road varies from 3m - 174m in the project area. The average elevation of project road is 93m AMSL.

Figure 7: Topographic Map of Tamil Nadu

Source: DPR

Project Road

56

Figure 8: Elevation Map of Project Road and District

3. Geology and Mineralogy

142. Geologically, the entire state can be broadly classified into hard rock or crystalline formation and sedimentary formations. Nearly 73% of the state is underlain by crystalline rocks of Archean metamorphic complex comprising of granite, charnockites, gneisses, chists etc. They are further intruded at many places by quartz veins, pegmatites and other ultra-basics like dolomites. The sedimentary rocks occur along the coast, flanking the crystalline mass in the west. This sedimentary formation mainly comprises of recent alluvial deposits, tertiary sandstone, lignite, cretaceous limestone, argillaceous sandstone etc. Besides these, sporadic occurrences of upper Gondwana formations consisting of compact sandstone, shale etc, are found as thin and isolated patches. Younger alluvial deltaic deposits cover the entire coastal belt: The geological map of Tamil Nadu state is shown in Figure 9.

143. Tamil Nadu is the leading holder of India's resources of vermiculite, magnetite, dunite, rutile, garnet, molybdenum and limonite. The State accounts for 81% lignite, 75% vermiculite, 69% dunite, 59% garnet, 52% molybdenum and 30% titanium mineral resources of the country. The geology and mineralogy of the project districts and the project districts are as follow.

144. Geology of Kanchipuram district is characterized by hard rock predominantly charnocites Gneiss with Gondwana formations. These are overlain by laterites and alluvium. Thiruvannamalai district is underlain by geological formations ranging in age from Achaean to Recent. Charnockites, gneisses and granites traversed by quartz veins and pegmatites underlain the major part of the district. Upper Gondwana formations are exposed in the north-eastern part of the district.

57

Figure 9: Geological Map of Tamil Nadu

4. Soil Characteristics

145. In Tamil Nadu soils are classified into six orders, 12 sub-orders, 20 great groups, 44 subgroups and 94 soil families in the hierarchy. The six orders are Entisols, Inceptisols, Alfisols, Mollisols, Ultisols, Vertisols. Inceptisols cover about 50% of the State’s total geographical area followed by Alfisols (30%), Vertisols (7%), Entisols (6%), Ultisols (1%) and negligible area by Mollisols. About 5% of the areas are miscellaneous land types, which includes rocklands, marshes, urban areas and water bodies. The soil texture, soil order and water retention characteristics of Tamil Nadu is shown in figure 10, figure 11 and figure 12; respectively.

146. Kanchipuram: Soils of the district have been classified into 1) clayey soil, 2) red sandy or red loamy soil 3) Red sandy brown clayey soil and 4) Alluvial soil. Of the above soils brown clayey soil is the most predominant, covering more than 71 percent of the areal extent of Kanchipuram district. Alluvial soils are found on the banks of Palar, Cheyyar and other rivers. The river alluvium is transported and is seen in coastal area of this district. Sandy coastal alluvial (arenacious soil) occurs along the seacoast in a narrow belt.

147. Thiruvannamalai: The predominant soil type is red and is found in all the taluks with more concentration in Polur Taluk. Red sand is found in all the taluks, but predominantly in Chengam,

Project Road

58

Thiruvannamalai and Vandavasi taluks. Different types of soil like ferruginous loamy and sandy loamy are seen extensively throughout the district and black loam is found in tank and river bed areas of Cheyyar and Vandavasi taluk.

Figure 10: Soil Texture Map of Tamil Nadu

Project Road

59

Figure 11: Soil Order Map of Tamil Nadu

148. Based on water retention characteristics, major length of project road falls in area of soils having moderate and low water retention characteristic as shown in Figure 12.

Figure 12: Soil Type Based on Water Retention Properties

Project Road

Project Road

60

149. Soil samples were collected at 6 locations, along the project road during DPR preparation. These soil samples were analysed for physical characteristics (colour, texture, water retention capacity, infiltration rate and density), particle size distribution, chemical characteristics (pH, electrical conductivity and organic carbon), and nutrient contents (NPK). The results of the soil sample analysis for the project roads are given in Table 13.

Table 13: Quality Monitoring Results for the Project Road

Sl. No.

Parameters Units S1 (Km

26)

S2 (Km 39.2)

S3 (Km 59.5)

S4 (Km 81.2)

S5 (Km 105)

S6 (ECR

Link Km 0)

1 pH - 6.61 7.31 7.39 7.06 8.47 6.85

2 Moisture Content % 5.93 1.86 2.65 3.26 2.94 9.08

3 Soil Classification /Texture

(a)Sand % 47.0 70.20 49 61.60 50.40 62.20

(b)Silt % 12.0 2.80 22 16.40 12.60 4.60

(c)Clay % 41.0 27.0 29 22 37.0 33.20

(d) Soil classification -

Sandy Clay

Sand clay

Sandy clay

Sand clay

Sandy clay

Sandy clay

4

Electrical Conductivity (1:5 Soil Extract)

µmhos / cm

122 180 133

36

198

82

5 Sodium Absorption Ratio(SAR)

- 1.07 6.30 3.80 4.60

0.31 0.82

6 Cation Meq/ 12.50 13.80 22.18 11.40 12.40 13.50

Exchange capacity 100g

7 Calcium mg/Kg 1925 1270 1155 1581 1853 902

8 Potassium mg/Kg 1656 1836 1842 1608 997 300

9 Sodium mg/Kg 206.4 162.1 158.70 161.2 75 172

10 Magnesium mg/Kg 677 2652 526 602 1541 1480

11 Chlorides mg/Kg 534 1229 1243 9330 1150 1260

12 Total Nitrogen mg/Kg 110 120 730 210 1150 280

13 Total Phosphorus

mg/Kg 94 210 630 150

820 160

14 Available Phosphorus

mg/Kg 1 6 9 1

20 34

15 Organic Matter mg/Kg 5480 7690 7860 8250 20880 10065

16 Carbonate mg/Kg Nil Nil Nil Nil 0.18 Nil

17 Sulphur mg/Kg 112 210 138 185 164 139

18 Arsenic mg/Kg Nil Nil Nil Nil Nil Nil

19 Boron mg/Kg 2 6.70 40 1 9.2 8.7

61

Sl. No.

Parameters Units S1 (Km

26)

S2 (Km 39.2)

S3 (Km 59.5)

S4 (Km 81.2)

S5 (Km 105)

S6 (ECR

Link Km 0)

20 Iron mg/Kg 48 28 23.0 32 43 22

21 Lead mg/Kg 1.45 1.40 1.62 1.62 1.80 1.72

22 Manganese mg/Kg 0.10 1.20 0.87 0.92 Nil 1.20

23 Zinc mg/Kg 80 180 95 110 80 75

Source: Monitoring undertaken during DPR preparation

150. The pH of the soils ranges between 6.61 - 8.47. Based on soil texture, soils can be classified as sandy clay at monitoring locations. The nutrient status of soil is also a key element in agriculture. Above results also shows that the soils of the study area have good amount of primary nutrients i.e., Nitrogen (N), Phosphorus (P) and Potassium (K) content. From the results it can be observed that the soil in the project area is fertile with high agricultural productivity with appropriate use of fertilizer. The soil has good electrical conductivity. 5. Seismicity and Volcanic Activity

151. The State of Tamil Nadu is a zone of low to moderate seismic activity with a sparse historical record of significant earthquakes. Seismicity / Effect due to earthquake have been accounted for by considering the seismic load in longitudinal and transverse direction. For the purpose of determining the seismic forces the country is divided into four zones (Zone II to Zone V) based on the intensity of earthquakes that a particular area may be subjected to, with Zone V comprising of areas which have been subjected to severe earthquakes & Zone-II comprising areas least liable to earthquakes. The seismic loads are calculated using Response Spectrum method as per Modified clause of IRC 6: 2010. The seismic force depends upon several factors like zone factor, Period of vibration, Soil type etc. The whole project area falls in the vast volcanic basalt beds of Deccan plate, which formed towards the end of Cretaceous period, between 65 and 67 million years ago. There is no recent seismic and volcanic activity reported along the project area.

152. The major length of project road fall under zone II (Low risk zone) and relevant provisions in IRC- 6:2010 have been adopted in the design. The seismic map of Tamil Nadu has been shown in Figure 13.

62

Figure 13: Seismic Map of Tamil Nadu State

(Source: Tamil Nadu State Disaster Management Plan)

6. Water Resources and Hydrology

a. Drainage

153. The seasonal rivers like Araniyar and Korattalaiar and Thondiar drain in the northern and southern part of the Kanchipuram district. The Palar, Araniyar and Korattalaiar and Thondiar river basins which are used for drinking and irrigation purpose. River Palar is a major river course, which drains this district originates from the Western Ghats in Karnataka State. Cheyyar and Vegavathi are the small tributaries of Palar river. Cheyyar and Ponaiyar rivers are the major rivers in Thiruvannamalai district.

b. Water Bodies along the Project Road

154. There are streams/canals crossing the project road. Ponds and lake are observed along the project road. Very few of them are partially impacted due to the proposed road improvement and none of the them are completely impacted. River Cheyyar is major waterbody crossed by project road.

Project Road

63

Figure 14: River Basins and Water Resources Map of Tamil Nadu

155. Details of the drainage channels, water bodies and likely impact observed along the project road are presented in Table 14 and Table 15.

Table 14: Details of Waterbodies along the Project Road

S.No. Structure Village Name Chainage Distance from PCL

Impact LHS/ RHS

1 Erry or Pond Pondurkarnai 20+800 10 Direct RHS

2 Erry or Pond Agili 27+177 6 Direct LHS

3 Erry or Pond Agili 27+177 6 Direct RHS

4 Erry or Pond Kaveri pakkam 42+026 6 Direct LHS

5 Erry or Pond Kallankutthu 42+700 11 Direct LHS

6 Pond Maruthadu 42+950 7 Direct LHS

7 Erry or Pond Arasampettai 73+130 3 Direct LHS

Project Road

64

8 Erry or Pond Nedungunam 75+875 5 Direct LHS

9 Erry Ramapuram 89+800 10 Direct LHS

10 Erry Modiyur 96+361 6 Direct RHS

11 Erry Selvampettai 106+352 6 Direct RHS

12 Erry Selvampettai 106+352 6 Direct LHS

13 Erry or Pond Ellaman koil 3+400 6 Direct RHS

Table 15: Details of Drainage along Project Road

S.No Chainage Water body Width LHS/ RHS

1 34+732 Stream 61 Crossing

2 46+460 Subam river 74 Crossing

3 50+900 Subam river 60 Crossing

4 101+900 Cheyyar river 217.5 Crossing

156. Major source of drinking water along project road is ground water. The major ground water resources along the project road are overhead tanks, water tank with tap and ponds. Few handpumps are also observed along SH-115 and ECR link project road.

157. Kancheepuram district has both sedimentary and fissured formations for the groundwater acquifer. The important aquifer system in the district are constituted by i) unconsolidated and semi consolidated formations and ii) weathered, fissured and fractured crystalline rocks. The ground water resources have been computed jointly by Central Ground Water Board and State Ground & Surface Water Resources Data Centre (PWD, WRO, Government of Tamil Nadu) in year 2004. The ground water occurs under water table conditions and the depth of the wells ranges from 5 to 10 m bgl. The specific capacity of porus formation ranged from 1.00 to 80.00 lpm/m/dd. The depth to water level ranged from 2.89 to 4.09 m bgl during May 2006 and 1.05 to 3.40m bgl during January 2007.

158. In block of Walajabad and Kancheepuram dug wells tap the alluvium with depths ranging between 6 and 12 m bgl having yield between 25 to 35 m3 /hr. The yield of infiltration wells with varying depths of 5 – 12 m bgl is around 35 m3 /hr. The estimation of ground water resources for the district has shown that two blocks are over exploited and two blocks are under “Critical” category.

159. The dynamic ground water resources for Thiruvannamalai district are studied under Thanjavur before separation as a district. As per study by Central Ground Water Board and State Ground & Surface Water Resources and Data Center (PWD, WRO, Government of Tamil Nadu). The district is underlain by the geological formations ranging in age from Archaean to Recent (Plate – II). In the district ground water occurs in six different aquifers as observed during study in pre monsoon (May 2006) season the depth of water level between 1.55 to 18.32 m bgl and 0.22 to 19.20 m bgl during post monsoon (January 2007). Out of total 14 blocks, there are three block listed as over exploited, one block is critical and three blocks are semi-critical stage in the district.

65

7. Water Quality

160. The sampling locations were selected after the field investigations and review of all the water bodies/ resources along the project road stretch. The water quality monitoring locations have been marked in Figure-3 for the project road. The surface water quality monitoring were carried at three locations and ground water sampling were also carried out at three locations along the alignment and the details are given in below Table-16.

161. Samples were collected as per IS- 2488 (Part I-V). Samples were taken from surface water as well as ground water sources during November 2019 along project road alignment. Samples were analyses as per IS: 10500-1991. Grab sample were collected from water source and were analyzed for various physico- chemical parameters as per the procedures laid down in the APHA and BIS. Atomic Absorption Spectrophotometer and UV/VIS Spectrophotometer were used for analysis of water samples according to the necessity.

Table 16: Water Quality Monitoring Locations Station Location Coordinates Sources

GW-1 Near Cheyur 12.3522N 80.0070E Tank Water

GW-2 Sandivakkam 12.2708N 79.4744E Hand Pump

GW-3 Ramraj Nagar 12.3007N 79.3230E Hand Pump

SW-1 Onambakkam 12.2310N 79.5724E Pond Water

SW-2 Malliyur 12.4941N 79.4644E Pond Water

SW-3 Devigapuram 12.4959N 79.2497E Pond Water

Table 17: Surface Water Quality Characteristics along the Project Road

Sl. No

Test Parameters

Test Method

Unit SW1 SW2 SW3 CPCB Designated , Best Use

1 Color IS 3025 PART 4

Hazen < 5 < 5 < 5 300

2 Odor IS 3025 PART 5

- objectionable objectionable objectionable Un-objectionable

3 pH@ 25oC IS 3025 PART 11

- 7.61 7.25 7.68 6.5 to 8.5

4 Conductivity@ 25oC

IS 3025 PART 14

µs/cm 850 798 830 Not Specified

5 Turbidity IS 3025 PART 10

NTU 5.2 5.5 2.8 Not Specified

6 Total Dissolved Solids

IS 3025 PART 16

mg/l 510 463 519 1500

7 Total Suspended Solids

IS 3025 PART17

mg/l 18.3 20.1 16.2 -

66

Sl. No

Test Parameters

Test Method

Unit SW1 SW2 SW3 CPCB Designated , Best Use

8 Total Alkalinity IS 3025 PART 23

mg/l 159 145 167 Not Specified

9 Total Hardness as CaCO3

IS 3025 PART 21

mg/l 175.5 157.7 157.7 Not Specified

10 Calcium as Ca IS 3025 PART 40

mg/l 38.9 33.4 41.8 Not Specified

11 Magnesium as Mg

IS 3025 PART 46

mg/l 19.1 18.1 19.2 Not Specified

12 Chloride as Cl IS 3025 PART 32

mg/l 66 61.3 68.3 Not Specified

13 Sulphate as SO4

IS 3025 PART 24

mg/l 53.2 49 54 Not Specified

14 Sodium as Na IS 3025 PART 45

mg/l 129.3 119.2 131.4 Not Specified

15 Free Ammonia

IS 3025 PART 34

mg/l 17.1 15.3 17.1 -

16 Nitrate as NO3

IS 3025 PART 34

mg/l 11.3 10 10.8 50

17 Potassium as K

IS 3025 PART 45

mg/l 18.1 15.2 18.3 Not Specified

18 Bicarbonate IS 3025 PART 51

mg/l 159 145 167 Not Specified

19 Fluoride as F IS3025 PART 60

mg/l 0.27 0.21 0.33 1.5

20 Phenolic Compounds (as C6H5OH)

IS 3025 PART 43

mg/l Absent Absent Absent 0.005

21 *Cyanide as CN

IS 3025 PART 27

mg/l Absent Absent Absent 0.05

22 *Aluminium as Al

IS 3025 PART 2

mg/l BDL(DL: 0.03) BDL(DL: 0.03) BDL(DL: 0.03) Not Specified

23 *Arsenic as As IS 3025 Part 37

mg/l BDL (DL:0.01) BDL (DL:0.01) BDL (DL:0.01) 0.2

24 *Cadmium as Cd

IS 3025 PART 2

mg/l BDL (DL:0.01) BDL (DL:0.01) BDL (DL:0.01) 0.01

67

Sl. No

Test Parameters

Test Method

Unit SW1 SW2 SW3 CPCB Designated , Best Use

25 Chromium as Cr6+

IS 3025 PART 52

mg/l BDL (DL:0.1) BDL (DL:0.1) BDL (DL:0.1) 0.05

26 *Copper as Cu IS 3025 PART 2

mg/l BDL (DL:0.2) BDL (DL:0.2) BDL (DL:0.2) 1.5

27 *Lead as Pb IS 3025 PART 2

mg/l BDL (DL:0.01) BDL (DL:0.01) BDL (DL:0.01) 0.1

28 Manganese as Mn

IS 3025 PART 59

mg/l BDL (DL:0.1) BDL (DL:0.1) BDL (DL:0.1) Not Specified

29 *Mercury as Hg

IS 3025 PART 2

mg/l BDL(DL:0.0005) BDL(DL:0.0005) BDL(DL:0.0005) Not Specified

30 *Zinc as Zn IS 3025 PART 2

mg/l BDL (DL:0.02) BDL (DL:0.02) BDL (DL:0.02) 15

31 Iron as Fe IS 3025 PART 53

mg/l 0.18 0.14 0.16 0.5

32 Dissolved Oxygen

IS 3025 PART 38

mg/l BDL (DL:1) BDL (DL:1) BDL (DL:1) Not Specified

33 COD IS 3025 PART 58

mg/l 61.4 57.3 65.2 Not Specified

34 BOD, 27̊C 3 Days

IS 3025 PART44

mg/l 20.1 18.9 23.6 3

35 Oil & Grease IS 3025 PART 39

mg/l BDL(DL:5) BDL(DL:5) BDL(DL:5) 0.1

36 Sodium Absorption Ratio

IS 11624 : 1986

meq/l 6 6 5.9 -

37 Boron IS 3025 PART 57

mg/l BDL(DL:0.01) BDL(DL:0.01) BDL(DL:0.01) -

38 Total Phosphorus

IS 3025 PART 31

mg/l 0.19 0.14 0.22 -

39 Total Nitrogen IS 3025 PART 34

mg/l 56 43 49 -

40 *Total Coliform

IS 1622-1981

MPN/ 100ml

68 60 71 500

162. The results of the ground water and surface water samples were analyzed and presented in Table 17 and Table 18; respectively. It can be seen from Table 17 that all surface water quality parameters were well within the permissible limit of CPCB except the presence of Total Coliforms which represent presence of organic matter in surface water body.

68

Table 18: Ground Water Quality Characteristics along the Project Road

Sl. No

Test Parameters

Test Method

Unit GW 1 GW 2 GW 3

IS 10500 : 2012

Drinking Water

Acceptable Limit

Permissible Limit

1 Colour IS 3025 PART 4

Hazen <5 <5 <5 5 15

2 Odour IS 3025 PART 5

- Agreeable

Agreeable Agreeable Agreeable

Agreeable

3 Taste IS 3025 PART 7

- Agreeable

Agreeable Agreeable Agreeable

Agreeable

4 pH IS 3025 PART 11

- 7.41 7.28 7.64 6.5 – 8.5 No Relaxation

5 Turbidity IS 3025 PART 10

NTU <1 <1 <1 1 5

6 Electrical Conductivity

IS 3025 PART14

µS/cm 1721 1866 1899 - -

7 Total Dissolved solids

IS 3025 PART 16

mg/l 998 1082 1207 500 2000

8 Total Alkalinity

IS 3025 PART 23

mg/l 331 351 379 200 600

9 Total Hardness

IS 3025 PART 21

mg/l 239.4 267.5 323.3 200 600

10 Calcium as Ca

IS 3025 PART 40

mg/l 54.6 59.6 71.8 75 200

11 Magnesium as Mg

IS 3025 PART 46

mg/l 25.1 28.9 35.1 30 100

12 Chloride as Cl

IS 3025 PART 32

mg/l 296 313 352 250 1000

13 Sulphate as SO4

IS 3025 PART 24

mg/l 89 99 112 200 400

14 Iron as Fe IS 3025 PART 53

mg/l 0.22 0.16 0.21 0.3 No Relaxation

15 Sodium as Na

IS 3025 PART 45

mg/l 151 168 198 - -

16 Potassium as K

IS 3025 PART 45

mg/l 11.9 19.4 24.1 - -

17 Bicarbonate IS 3025 PART 51

mg/l 331 351 379 - -

69

Sl. No

Test Parameters

Test Method

Unit GW 1 GW 2 GW 3

IS 10500 : 2012

Drinking Water

Acceptable Limit

Permissible Limit

18 Fluoride as F

GLCS/SOP/W/015

mg/l 0.19 0.24 0.21 1 1.5

19 *Copper (Cu)

ITC/CHN/FD/STP/020

mg/l BLQ(LOQ:0.005)

BLQ(LOQ:0.005)

BLQ(LOQ:0.005)

0.05 1.5

20 Phenolic Compounds(C6H5OH)

IS 3025 PART 43

mg/l BLQ(LOQ:0.001)

BLQ(LOQ:0.001)

BLQ(LOQ:0.001)

0.001 0.002

21 *Anionic Detergents(MBAS)

IS 13428 Anx K

mg/l BLQ(LOQ:0.05)

BLQ(LOQ:0.05)

BLQ(LOQ:0.05)

0.2 1

22 *Mineral Oil IS 3025 PART 39

mg/l BLQ(LOQ:0.01)

BLQ(LOQ:0.01)

BLQ(LOQ:0.01)

0.5 No Relaxation

23 *Aluminium (Al)

ITC/CHN/FD/STP/020

mg/l BLQ(LOQ:0.005)

BLQ(LOQ:0.005)

BLQ(LOQ:0.005)

0.03 0.2

24 Manganese as Mn

IS 3025 PART 59

mg/l BDL (DL :0.1)

BDL (DL :0.1)

BDL (DL :0.1)

0.1 0.3

25 Nitrate as NO3

IS 3025 PART 34

mg/l 17.6 18.1 14.2 45 No Relaxation

26 *Selenium (Se)

ITC/CHN/FD/STP/020

mg/l BLQ(LOQ:0.005)

BLQ(LOQ:0.005)

BLQ(LOQ:0.005)

0.01 No Relaxation

27 *Zinc (Zn) ITC/CHN/FD/STP/020

mg/l BLQ(LOQ:0.005)

BLQ(LOQ:0.005)

BLQ(LOQ:0.005)

5 15

28 *Cadmium (Cd)

ITC/CHN/FD/STP/020

mg/l BLQ(LOQ:0.001)

BLQ(LOQ:0.001)

BLQ(LOQ:0.001)

0.003 No Relaxation

29 *Lead (Pb) ITC/CHN/FD/STP/020

mg/l BLQ(LOQ:0.005)

BLQ(LOQ:0.005)

BLQ(LOQ:0.005)

0.01 No Relaxation

30 *Mercury (Hg)

ITC/CHN/FD/STP/020

mg/l BLQ(LOQ:0.0005)

BLQ(LOQ:0.0005)

BLQ(LOQ:0.0005)

0.001 No Relaxation

31 *Arsenic (As)

ITC/CHN/FD/STP/020

mg/l BLQ(LOQ:0.005)

BLQ(LOQ:0.005)

BLQ(LOQ:0.005)

0.01 No Relaxation

70

Sl. No

Test Parameters

Test Method

Unit GW 1 GW 2 GW 3

IS 10500 : 2012

Drinking Water

Acceptable Limit

Permissible Limit

32 *Total Chromium (Cr)

ITC/CHN/FD/STP/020

mg/l BLQ(LOQ:0.005)

BLQ(LOQ:0.005)

BLQ(LOQ:0.005)

0.05 No Relaxation

33 *Cyanide as CN

IS 3025 PART 27

mg/l BLQ (LOQ : 0.01)

BLQ (LOQ : 0.01)

BLQ (LOQ : 0.01)

0.05 No Relaxation

34 Ammoniacal Nitrogen As NH3-N

IS 3025 PART 34

mg/l BDL( DL: 1)

BDL( DL: 1)

BDL( DL: 1)

- -

35 *Barium as Ba

IS 13428 Annex F

mg/l BLQ (LOQ : 0.05)

BLQ (LOQ : 0.05)

BLQ (LOQ : 0.05)

0.7 No Relaxation

36 Boron as B IS 3025 PART 57

mg/l BDL(DL:0.01)

BDL(DL:0.01)

BDL(DL:0.01)

0.5 1

37 *Chloramine

IS 3025 PART 26

mg/l BDL( DL:0.1)

BDL( DL:0.1)

BDL( DL:0.1)

4 No Relaxation

38

Free Residual Chlorine as Cl2

IS 3025 PART 26

mg/l BDL( DL: 1)

BDL( DL: 1)

BDL( DL: 1)

0.2 1

39 *Silver as Ag

IS 13428 Annex J

mg/l BDL(DL:0.005)

BDL(DL:0.005)

BDL(DL:0.005)

0.1 No Relaxation

40 *Sulphide IS 3025 PART 29

mg/l BDL( DL: 1)

BDL( DL: 1)

BDL( DL: 1)

0.05 No Relaxation

41 *Molybdenum as Mo

IS 3025 PART 2

mg/l BDL(DL:0.005)

BDL(DL:0.005)

BDL(DL:0.005)

0.07 No Relaxation

42 *Nickel as Ni

IS 3025 PART 54

mg/l BDL(DL:0.005)

BDL(DL:0.005)

BDL(DL:0.005)

0.02 No Relaxation

43

*Polychlorinated Biphenyls (PCB)

ASTM 5175

mg/l BLQ(LOQ:0.00002)

BLQ(LOQ:0.00002)

BLQ(LOQ:0.00002)

0.0005 No Relaxation

44

*Poly nuclear aromatic hydrocarbons(PAH)

APHA 6440B

mg/l BLQ(LOQ:0.00002)

BLQ(LOQ:0.00002)

BLQ(LOQ:0.00002)

0.0001 No Relaxation

45 *Total Coliform

IS 1622-1981

MPN/ 100ml

Absent Absent Absent Shall not be detectable in any 100ml of sample

71

Sl. No

Test Parameters

Test Method

Unit GW 1 GW 2 GW 3

IS 10500 : 2012

Drinking Water

Acceptable Limit

Permissible Limit

46 *E.Coli IS 1622-1981

MPN/ 100ml

Absent Absent Absent Shall not be detectable in any 100ml of sample

Source: Water Quality Monitoring carried out in the month of November - December 2019

163. From Table 18 it is clear that the ground water quality parameters were well within the permissible limits for drinking waters as specified by IS 10500:2012 on project road. Overall the ground water quality in the project areas is good. 8. Air Quality

164. The ambient air quality was monitored to characterize baseline scenario in the study area and direct project influence area. The study area comprises of rural, residential and urban areas. The sources of air pollution in the region are mainly vehicular traffic, dust arising from unpaved road and domestic fuel burning. The prime objective of the baseline air quality study is to establish the existing ambient air quality along the project road. This will also be useful for impact assessment during the construction and operation phases. In order to establish baseline ambient air quality, monitoring locations were finalized following the notification of MoEFCC dated 16 November 2009; so as to be true representatives of the study area. Further, the locations were selected with the following considerations:

• meteorological conditions; • the assumed regional influences on background air quality; • the areas where impact would most likely be greatest; • present land use along the proposed alignment; and • traffic congestion points.

165. To establish the baseline air quality, Ambient Air Quality (AAQ) monitoring was carried out in last quarter of 2019 and air quality monitoring stations were set up at 5 locations as indicated in Table 19 along the project road.

Table 19: Details of Ambient Air Quality Monitoring Locations along Project Road Station Location Coordinates Land Use

AAQ1 Govt Primary School, Kattuthevathur

12.3966N 79.9382E Residential Area/Rural

AAQ2 Killkodunaganalur 12.4937N 79.7013E

Residential Area/Semi Urban

AAQ3 Kund Kundar Nagar, Opp. Ponnur Malai

12.2759N 79.2047E Residential Area/ Rural

AAQ4 Near Chetpet 12.2757N 79.2049E

Residential Area/Urban

AAQ5 Oxford College of Engineering, Karaipoondi

12.5078N 79.1542E Residential Area//Semi Urban

166. At each of the five locations ambient air monitoring was undertaken as per latest notification issued by MOEFCC on 16 November 2009 to represent air quality of the urban and rural habitation area with normal activities and traffic on the project road section. The averaging

72

period is 24 hours for all parameters monitored, following National standards of air quality monitoring. Methodology adopted for sampling and analysis and instrument used for analysis in laboratory are presented in Table 20.

Table 20: Techniques Used for Ambient Air Quality Monitoring

Sl. No.

Parameter Technique Instrument Used

Minimum Detectable Limit(μg/m3)

1. PM10 Respirable Dust Sampler (Gravimetric method)

Electrical Balance

1.0

2. PM2.5 Respirable Dust Sampler (Gravimetric method)

Electrical Balance

1.0

3. Sulphur Dioxide

Improved West & Gaeke Method

Colorimeter 5.0

4. Nitrogen Oxide

Jacob & Hochheiser modified (Na-Arsenite) Method

Colorimeter 5.0

5. Carbon Monoxide

Gas Chromatograph 0.01

167. A summary of results for each location is presented in Table 21. These results are compared with the latest National Ambient Air Quality Standards prescribed by the MOEFCC and air quality standards of World Bank Group for respective zones.

Table 21: Summary of AAQM Results along the Project Road

Sl.No

Test Parameters

Test Method

Units AAQ1 AAQ2 AAQ3 AAQ4 AAQ5

NAAQ (2009)* Limits Standards Limits

World Bank (IFC) Standards

1 Sulphur dioxide as SO2

IS 5182 Part2: 2001 (RA 2017)

µg/m3 22.1 16.8 16.6 14.2 14.5 80 -

2 Nitrogen dioxide as NO2

IS 5182 Part:6: 2006 (RA 2017)

µg/m3 39.6 34.7 37.2 29.2 23.4 80 40

3

Respirable Particulate matter (Size less than 10 µm/PM10)

IS 5182 Part23:2006 (RA 2017)

µg/m3 71.2 65.1 65.1 53.2 63.5 100 50

4

Respirable Particulate matter (Size less than 2.5 µm/PM2.5)

GLCS/SOP/AAQ/017

µg/m3 24.5 21.1 18.1 15.3 22.4 60 25

5 Ozone as O3 GLCS/SOP/AAQ/002

µg/m3 BDL(DL:5.0)

BDL(DL:5.0)

BDL(DL:5.0)

BDL(DL:5.0)

BDL(DL:5.0)

180 100

6 *Lead as Pb IS 5182 Part22:2004 (RA 2009)

µg/m3 BDL(DL:0.1)

BDL(DL:0.1)

BDL(DL:0.1)

BDL(DL:0.1)

BDL(DL:0.1)

1 -

7 *Carbon Monoxide as CO

IS 5182 Part10:1999 (RA 2009)

mg/m3

BDL(DL:1.15)

BDL(DL:1.15)

BDL(DL:1.15)

BDL(DL:1.15)

BDL(DL:1.15)

4 -

73

8 Ammonia as NH3

GLCS/SOP/AAQ/001

µg/m3 26 26.7 15.5 13.6 15.3 400 -

9 *Benzene as C6 H6

IS 5182 Part11:2006 (RA 2017)

ng/m3 BDL(DL:0.1)

BDL(DL:0.1)

BDL(DL:0.1)

BDL(DL:0.1)

BDL(DL:0.1)

5 -

10 *Benzo(a)Pyrene as BaP

IS 5182 Part23:2006 (RA 2014)

ng/m3 BDL(DL:0.1)

BDL(DL:0.1)

BDL(DL:0.1)

BDL(DL:0.1)

BDL(DL:0.1)

1 -

11 *Arsenic as As IS 5182 Part22:2004 (RA 2009)

ng/m3 BDL(DL:1.0)

BDL(DL:1.0)

BDL(DL:1.0)

BDL(DL:1.0)

BDL(DL:1.0)

6 -

12 *Nickel as Ni IS 5182 Part22:2004 (RA 2009)

ng/m3 BDL(DL:1.0)

BDL(DL:1.0)

BDL(DL:1.0)

BDL(DL:1.0)

BDL(DL:1.0)

20 -

13 * Hydrocarbon IS 5182 Part17:1979 (RA 2009)

PPM BDL(DL:0.01)

BDL(DL:0.01)

BDL(DL:0.01)

BDL(DL:0.01)

BDL(DL:0.01)

- -

14 *Hydrogen Fluoride

IS 5182 Part13:1991 (RA 2009)

PPM BDL(DL:0.02)

BDL(DL:0.02)

BDL(DL:0.02)

BDL(DL:0.02)

BDL(DL:0.02)

- -

168. The monitored values are compared with National Ambient Air Quality Standards prescribed by Central Pollution Control Board (CPCB) and IFC EHS standards for residential, rural and other areas. The Ambient air quality levels meet the National air quality standards for rural, residential and industrial area along the project road.

• PM2.5: The mean PM2.5 concentration at ambient air quality monitoring locations varies from 15.3 to 24.5 µg/m3. The values are within the permissible limit at all the stations.

• PM10: The mean PM10 concentration at ambient air quality monitoring locations varies from 53.2 to 71.2 µg/m3. The values are within the permissible limit at all the stations for CPCB but marginally exceed IFC standards.

• SO2: The mean concentrations of SO2 at all ambient air quality monitoring locations varies from 14.2 to 22.1 µg/m3. The values are within the permissible limit at all the stations.

• NOx: The mean concentrations of NOx at all AAQM locations range from 23.4 to 39.6 µg/m3. The values are within the permissible limit at all the stations.

• CO: The concentrations of CO at all AAQM locations were below 0.01 mg/m3. The values are within the permissible limit at all the stations.

169. Overall the air quality along the project roads is not an issue. The National Ambient Air Quality Standards (NAAQS) prescribed by MOEFCC. However, the values for PM10 are slightly exceeding IFC EHS air quality standards. The National Ambient Air Quality Standards (NAAQS) prescribed by MOEFCC together with IFC standards are given in Appendix 4. 9. Noise

170. Noise in general is a sound which is composed of many frequency components of different loudness distributed over the audible frequency range. Noise in the project area was assessed using the GoI and IFC EHS noise guide values which are similar for day and nighttime residential and nighttime industrial land uses. The GoI is more stringent in commercial land use while the IFC EHS is less stringent for daytime noise for industrial land use. The IFC EHS does not provide guide values for silent zone which is defined as at least 100-meter perimeter around hospitals,

74

educational institutions, courts, religious places and similar area. GoI standards when the existing noise levels already exceed the limits. IFC-EHS provides a 3 dB maximum increase from the background (i.e. doubling of noise levels) when the existing measure noise already exceeds the standards. GoI does not stipulate clear guidelines for such scenarios.

171. A preliminary reconnaissance survey was undertaken in project road to identify the major noise generating sources along the project road. To assess prevailing noise levels in the surroundings of project road, ambient noise monitoring was carried out considering all categories of land uses along the project road (e.g. commercial, residential and silence zones)

172. A total of 12 locations within the study area were selected for noise level measurements along the project road. The selected monitoring locations are representative of sensitive receptors in urban/semi-urban area and residential location from rural area. The background noise level at the monitoring location are generated from routine human activities and traffic on the road section in urban and rural area. The monitoring locations are representing educational institutes/schools and hospitals in residential area with few of commercial activties in urban and small rural area with normal activities and traffic volume. Thus, at these locations noise monitoring is done to observed maximum level and normal level of background noise. The locations of noise level measurement are shown in Figure 3 while location detail of the noise monitoring are given in Table 22.

Table 22: Details of Noise Level Monitoring Locations

Station Location Coordinates Land Use

NL1 Girls Govt Hr Sec School, Chayyur

12.3528N 80.0008E Residential Area/Urban

NL2 Govt Middle School, Nallamur 12.4059N 79.9152E Residential Area/Rural

NL3 Adhi Parasakthi College, Melmaruvathur

12.4393N 79.8251E Residential Area/Semi Urban

NL4 Govt Hr Secondary School, Salavedu

12.4847N 79.7303E Residential Area/ Semi Urban

NL5 Vetennary Hospital, Kilkodunganalur

12.4937N 79.7013E Rural/Silent

NL6 S.R.I College, Vandavassi 12.4970N 79.6362E Residential Area/Urban

NL7 Kund Kund College, Kund Nagar

12.2759N 79.2047E Residential Area/ Rural

NL8 Suraj Matriculation School, Kuttroad

12.4966N 79.4071E Residential Area/ Rural

NL9 St Thomas Hospital, Chettupattu

12.3028N 79.0914E Urban /Silent

NL10 Govt High Sec School, Divikapuram

12.2938N 79°.518E Residential Area/Semi Urban

NL11 Oxford College, Polur 12.5078N 79.1542E Residential Area/Urban

NL12 Don Bosco Hr Sec School 12.2757N 79.2049E Residential Area /Urban

173. Methodology: At each of the selected locations, Sound Pressure Level (SPL) measurements were taken at an interval of 1 minute using a sound level meter of Lutron make Digital Sound Level Meter. At all these locations, daytime noise levels were monitored during the period 6 am to 9 pm and night-time noise levels during the period 9 pm to 6 am following national

75

guidelines. Noise readings, with setting at ‘A’ response - slow mode, were recorded. The readings were tabulated, and a frequency distribution table prepared from which 24 hourly, hourly, and average Leq noise levels were calculated. The baseline values were recomputed to align them with IFC EHS prescribed periods, which is 7am to 10pm for daytime and 10pm to 7am for nighttime.

174. Presentation of Results: It can be seen from the Table 23 that at all the monitoring locations the ambient noise levels exceeds the permissible limits for residential areas prescribed by CPCB and also by IFC EHS standards of 55 dB(A) and 45 dB(A) for day time and night time respectively. The maximum recorded day time noise level is 75.6 dB(A) and night time noise level is 60 dB(A) along the project alignment.

Table 23: Ambient Noise Level in dB(A) along the Project Road

Monitoring Location

Monitoring Duration

Leq L10 L50 L90

CPCB Standard

for residential

WB/ IFC Standard

for residential

NL1 Day 61.08 63.78 59.9 56.92 55 55

Night 51.18 50.44 49 46.36 45 45

NL2 Day 62.02 63.28 61.5 58.92 55 55

Night 54.78 54.64 52.2 50.06 45 45

NL3 Day 69.1 72.47 68.79 61.42 55 55

Night 60.12 58.64 57.6 57.06 45 45

NL4 Day 70.22 71.87 70.49 67.92 55 55

Night 63.81 53.54 51.7 49.96 45 45

NL5 Day 72.14 75.07 72.09 68.91 50 -

Night 56.98 52.14 50.6 44.06 40 -

NL6 Day 70.84 72.87 69.69 67.52 55 55

Night 61.51 54.54 51.9 48.86 45 45

NL7 Day 61.42 64.28 60.6 53.42 55 55

Night 50.74 50.84 46.5 44.16 45 45

NL8 Day 58.03 60.48 59 53.92 55 55

Night 51.9 52.24 51.35 48.66 45 45

NL9 Day 54.43 56.18 54.15 53.21 50 -

Night 49.35 48.74 47.4 44.96 40 -

NL10 Day 66.82 71.37 62.8 58.82 55 55

Night 55.34 56.64 53.6 50.96 45 45

NL11 Day 67.21 70.47 67.59 61.82 55 55

Night 55.4 55.94 55.2 52.56 45 45

NL12 Day 69.25 72.67 69.89 62.62 55 55

Night 60.38 61.64 59.6 56.46 45 45

Source: Noise Monitoring carried out by Consultant Team, 2019

76

C. Coastal and Marine Resources in Project Influence Area

175. Under the Environment Protection Act, 1986 a notification was issued in February, 1991, for regulation of activities in the coastal area by the Ministry of Environment, Forests and Climate Change (MOEFCC). As per the notification, the coastal land up to 500m from the High Tide Line (HTL) and a stage of 100m along banks of creeks, estuaries, backwater and rivers subject to tidal fluctuations, is called the Coastal Regulation Zone (CRZ). Government of Tamil Nadu have prepared Coastal Zone Management Plan Maps for its entire coastal stretches of Tamil Nadu on the basis of CRZ Notification 1991. The activities in CRZ areas have been regulated based on the above approved Coastal Zone Management Plan maps till date. CRZ-III are areas that are relatively undisturbed and those do not belong to either CRZ-I or II which include coastal zone in the rural areas (developed and undeveloped) and also areas within municipal limits or in other legally designated urban areas, which are not substantially builtup. The project is located in the bank of backwater categorised as CRZ-III area. Regulations:

• The area up to 200m from the HTL is be earmarked as 'No Development Zone'. No construction shall be permitted in this zone except for repairs of existing authorized structures not exceeding existing FSI, existing plinth area and existing density. However, the following uses may be permissible in this zone-agriculture, horticulture, gardens, pastures, parks, play fields, forestry and salt manufacture from sea water.

• Development of vacant plots between 200 and 500m of High Tide Line in designated areas of CRZ-III with prior approval of Ministry of Environment and forests permitted for construction of hotels/beach resorts for temporary occupation of tourists / visitors.

• Construction/ reconstruction of dwelling units between 200m and 500m of the High Tidal Line permitted so long as it is within the ambit of traditional rights and customary uses such as existing fishing villages and gothans. Building permission for such Construction/reconstruction will be subject to the conditions that the total member of dwelling unit shall not be more than twice the number of existing units; total area covered on all floors shall not exceed 9 meters and construction shall not be more than 2 floors (ground floor plus one floor).

• Reconstruction/alteration of an existing authorized building permitted subject to (1) to (3) above.

176. ECR link crosses Odiyur lake under CRZ which considered as Hot Spot. However, CRZ clearance is not required for ECR link, since there is no improvement of project road in the backwater stretch of ECR link. Figure 15 shows CRZ map of Tamil Nadu.

77

Figure 15: Coastal Zone Management Plan of Tamil Nadu

D. Biological Environment

1. Forests

177. The recorded forest area in Tamil Nadu state is 22,428 km2 which constitutes 20.21% of the geographical area of the state. Reserved Forests comprise 88.70%, Protected Forests 7.79% and Unclassified Forests constitute 3.51%. The forest cover in project districts is presented in Table 24 which shows that Kancheepuram district have very thin forest cover and in Tiruvannamalai district good forest cover having all classes of forest.

78

Table 24: Forest Cover in Project Districts (Km2) 3

District Geographical Area (GA)

VDF MDF OF Total % of GA

Kancheepuram 4,483 0 69.95 237.83 307.78 6.87

Tiruvannamalai 6188 233.79 595.83 478.74 1308 21.14

TN State 130060 3672 10979 11630 26281 20.21

VDF: Very Dense Forest, MDF: Moderately Dense Forest, OF: Open Forest

178. The project road passes through reserved forests and social forests in multiple patches. Total 6.977 km length of project road passes through reserved forests (RoW excluded from RF). The details of forest abutted by project road is presented in Table 25.

179. Forest clearance is not required for any of the stretches since no forest land is proposed to be acquired for widening and strengthening of the project road. The road section in the forest area will be widened and strengthened within the existing right of way. The road section in Kattuguladur reserve forest area has been excluded from forest land, copy of the notification is given in Appendix 17.

Table 25: Forest Areas along the Project Road

Existing Chainage Length (km)

Location Type of forest

Km 25+890 to km 26+825 (Gudalur RF) 0.935 LHS Reserve Forest

Km 26+125 to km 26+400 0.275 RHS Social Forest

Km 26+825 to km 26+980 (Kattuguladur RF) 0.155 LHS Reserve Forest

Km 26+980 to km 31+217 (Kattuguladur RF) 4.237 Both Sides Reserve Forest

Km 57+800 to km 59+450 (Ponnur Malai RF) 1.65 LHS Reserve Forest

Km 58+100 to km 58+400 0.3 RHS Social Forest

Km 58+600 to km 58+700 0.1 RHS Social Forest

Total 6.977

3 Tamil Nadu State of the Forest Report, 2019.

79

Figure 16: Forest Cover Map of Tamil Nadu Showing Project Road

Source: India State of Forest Report

2. Flora and Vegetation along the project road

180. The roadside trees falling within formation width of project road have been enumerated as per the available design. The tree enumeration details of trees >30cm girth size along project road are provided in Table 26. The roadside trees are continuous throughout the corridor except some stretches where open land/agricultural land are observed. The trees are generally having good canopy as observed during environmental impact survey. Every effort has been made by engineering and environmental team to save these trees. There is no green tunnel along the project road. As observed from above tree details, a total of 4770 trees >30cm girth size fall within formation width of project road, which will be affected due to road widening. The detail of the impacted trees above 30 cm girth size is provided in Appendix 5.

Table 26: Tree Enumeration within Formation Width of Project Road (>30 cm)

Link Description Trees on LHS

Trees on RHS

Total Trees

SH115 2216 2500 4716

ECR Link 37 17 54

Marudharu Village Realignment -- - -

Proposed Vandvasi Bypass - - -

Proposed Chetpet Town Bypass - - -

Total 2253 2517 4770

80

181. The local and scientific names of tree species observed along the project road with their CITES and IUCN status are listed in Table 27. The dominant tree species along project road are Mango, Tamarind, Palm, Neem, Coconut, Peepal, Indian beech, Siris and Black Plum.. Other observed species are either Least Concerned or have not yet been assessed for the IUCN Red List.

Table 27: IUCN Status of Major Tree Species within Formation Width (>30 cm)

Common Name

Tamil Name

Scientific Name IUCN Status

Banyan Alamaram Ficus benghalensis -

Peepal Arasan Ficus religiosa -

Coconut Coconut Cocos nucifera -

Mango Mango Mangifera indica -

Black Plum Naval Syzygium cumini LC

Neem Neem Azadirachta indica LC

Palm Palm Borassus flabellifer

-

Indian Beech

Pungai Millettia pinnata LC

Tamarind Tamarind Tamarindus indica LC

Siris Vagai Albizia lebbeck -

3. Protected Areas

182. There are five national parks, four tiger reserves, fifteen wildlife sanctuaries, fifteen bird sanctuaries, three biosphere reserves, (four) zoological park, three crocodile farms and two conservation reserve in the State of Tamil Nadu. (Source: Tamil Nadu Forest Department).

183. There is no protected area within 10 km aerial distance of the project site. The area did not record the presence of any critically threatened species. The field survey and investigation also indicates the absence of any high endemic or vulnerable species in this area. There is no critical habitat within the project area of influence. The project area can also be considered to be entirely modified habitat. The list of protected area within Tamil Nadu are shown in Table 28.

Table 28: Protected Areas of Tamil Nadu S. No.

Name District Area in ha Year Decl.

Major Animals Found

Wildlife Sanctuaries

1 Mudumalai Wildlife Sanctuary

Nilgiris 21,776.00 1940 Elephant, Gaur, Sambar, Chital, Panther, Tiger, Birds, Reptiles

2 Indira Gandhi Wildlife Sanctuary

Coimbatore 84,149.00 1976 Elephant, Gaur, Tiger, Panther, Sloth bear, Wild boar

3 Mundanthurai Wildlife Sanctuary

Tirunelveli 58,207.58 1962 Tiger, Bonnet Macaque, Langurs, Slender Loris, Sloth Bear, Sambar, Chital, Wild Dog

4 Kalakad Wildlife Sanctuary

Tirunelveli 22,358.00 1976 Lion Tailed Macaque, Nilgiri Tahr, Sambar, Sloth Bear, Elephant, Panther, Tiger

5 Srivilliputhur Grizzled Squirrel Wildlife Sanctuary

Virudhunagar 48,520.00 1988 Grizzled Giant Squirrel, Flying Squirrel, Nilgiri Tahr, Elephant, Lion Tailed Macaque

81

S. No.

Name District Area in ha Year Decl.

Major Animals Found

6 Point Calimere Wildlife Sanctuary

Nagapattinam 1,726.00 1967 Black Buck, Bonnet Macaque, Wild Boar, Flamingoes, variety of birds such as Teals, Gulls

7 Vallanadu Black Buck Sanctuary

Thoothukudi 1,641.00 1987 Black buck, Spotted deer, Macaques, Jungle cat, Mongoose, Hares

8 Kanyakumari Wildlife Sanctuary

Kanyakumari 40,239.55 2007 Bonnet Macaque, Nilgiri Langur, Slender Loris, Tiger, Panther, Elephant, Bird, jackal, Nilgiri Tahr

9 Sathyamangalam Wildlife Sanctuary

Erode 1,41,160.94 2011 Elephant, birds etc.

10 Megamalai Wildlife Sanctuary

Theni & Madurai 26,910.82 2009 Elephant, birds etc.

11 Point Calimere Wildlife Sanctuary Block A & Block B

Thanjavur & Tiruvarur

12,407.27 2013 Black Buck, Bonnet Macaque, Wild Boar, Flamingoes, variety of birds such as Teals, Gulls

12 Kodaikanal Wildlife Sanctuary

Dindigul & Theni 60,895.48 2013

Nilgiri Langur, Common Langur, Bonnet Macaque, Indian Giant Squirrel, Common Giant Flying Squirrel, Tiger, Leopard/Panther, Birds, Reptiles, Elephant

13 Gangaikondan Spotted Deer Sanctuary

Tirunelveli 288.4 2013 Spotted Deer

14 Cauvery North Wildlife Sanctuary

Krishnagiri & Dharmapuri

50,433.48 2014 Grizzled Giant Squirrels, Panthers, Elephants, Dhole, Sloth Bear etc.

15 Nellai Wildlife Sanctuary

Tirunelveli 35,673.33 2015

India Gaur, Leopard, Nilgiri Tahr, Sambar, Wild Boar, Sloth Bear, Indian Elephant, Lion Tailed Macaque etc.

Bird Sanctuaries

16 Vedanthangal Birds Sanctuary

Kancheepuram 30 1998 Cormorants, egrets, gray heron, spoon billed stork, migratory birds like garguney, teals, shovallers

17 Karikili Birds Sanctuary

Kancheepuram 61.21 1989 Cormorants, egrets, grey heron, spoon billed stork,

18 Pulicat Lake Birds Sanctuary

Tiruvallur 15,367.00 1980 Flamingoes, ducks, osprey, avocet, cormorants, herons, spoon bills, gulls and other migratory birds

19 Vettangudi Birds Sanctuary

Sivagangai 38.4 1977 Cormorants, egrets, herons, teals, pelicans

20 Kanjirankulam Birds Sanctuary

Ramanathapuram 104 1989 Cormorants, egrets, herons, teals, pelicans

21 Chitrangudi Birds Sanctuary

Ramanathapuram 47.63 1989 Cormorants, egrets, herons, teals, pelicans

22 Udayamarthandpu ram Birds Sanctuary

Tiruvarur 45.28 1998 Little cormorant, darter, spoon bill, Indian Reef Heron, Grey heron, white necked stork

23 Vaduvoor Birds Sanctuary

Tiruvarur 128.1 1999 Cormorants, egrets, ibis, herons and many variety of birds

24 Koonthankulam-Kadankulam Birds Sanctuary

Tirunelveli 129 1994 Grey pelican, painted stork, white Ibis, jackal, rat snake

82

S. No.

Name District Area in ha Year Decl.

Major Animals Found

25 Karaivetti Birds Sanctuary

Ariyalur 453.71 1999 Egrets, pelican, grey heron, white ibis, spoon bill

26 Vellode Birds Sanctuary

Erode 77.18 2000 Spoon bill, teals, pintail ducks, darter

27 Melaselvanur- Kilaselvanur Birds Sanctuary

Ramanathapuram 593.08 1998 Grey pelican, painted stork

28 Theerthangal Bird Sanctuary

Ramanathapuram 29.29 2010 White-breasted kingfisher, spot- billed pelican, brahminy kite

29 Sakkarakottai Tank Birds Sanctuary

Ramanathapuram 230.49 2012 Spot-billed pelican, egret, common myna, grey heron, little cormorant, black kite, etc.

30 Oussudu Lake Birds Sanctuary

Villupuram 331.79 2015 Spot-billed pelican, egret, common myna, grey heron, little cormorant, black kite, etc.

National Parks

31 Mudumalai National Park

Nilgiris 10,323.00 2005 Elephant, Gaur, Sambar, Chital, Tiger, Birds, and reptiles

32 Indira Gandhi National Park

Coimbatore 11,710.00 1989 Elephant, Gaur, Tiger, Panther, Sloth Bear, Wild Boar

33 Mukurthi National Park

Nilgiris 7,846.00 2001 Nilgiri Tahr, Jackal, Otter, Jungle cat, Sambar, Barking deer.

34 Guindy National Park

Chennai 270.57 1978 Black Buck, Chital, Jackal, Pangolin and variety of birds

35

Gulf of Mannar Marine National Park (21 Islands) and biosphere reserve

Ramanathapuram & Thoothukudi

52,602.00 1986 Characteristic tropical flora & fauna of coral reefs, Dugong, Turtles, Dolphins and Balanoglossus

Conservation Reserves

36

Thiruppudaimaruth ur Birds Conservation Reserve

Tirunelveli 2.84 2005 Birds

37

Suchindrum- Theroor-Managudi Conservation Reserve

Kaninyakumari 484.77 2015 Birds

83

Figure 17: Protected Area Map of Tamil Nadu

Source: Tamil Nadu Forest Department, Government of Tamil Nadu.

4. Fauna/Wildlife

184. India is represented by a wide array of faunal species. More than 50,000 species of insects, 4,000 of mollusks, 6,500 of other invertebrates, 2,000 of fishes, 140 of amphibians, 420 of reptiles, 1,200 of birds and 340 of mammals, totaling more than 65,000 species of animals are recorded from the country.

185. Tamil Nadu's faunal biodiversity is equally impressive. Dr. K. Venkataraman of Zoological Survey of India, Chennai has published about 595 species of freshwater faunal, 2,247 species of marine faunal and 1,898 species of terrestrial faunal species in Tamil Nadu.

Project road

84

186. The faunal diversity of the State includes 165 species of fresh water fishes, 76 species of amphibians, 177 species of reptiles, 454 species of birds and 187 species of mammals. According to the CAMP reports the red-listed species include 126 species of fishes, 56 species of amphibians, 77 species of reptiles, 32 species of birds and 40 species of mammals.

187. The endemic fauna includes 36 species of amphibians, 63 species of reptiles, 17 species of birds and 24 species of mammals. Many faunal species have been included in the various schedules of the Wild Life Protection Act 1972, considering their endangered status. Schedule I animals include 22 species of mammals, 42 species of birds and 9 species of reptiles.

188. Schedule II includes 13 species of mammals. Schedule III includes 5 species of mammals and Schedule IV includes 5 species of mammals, 367 species of birds, 109 species of reptiles and 23 species of amphibians. Schedule V incorporates 13 species of mammals and 1 species of birds4.

a. Assessment of Fauna along the Project Road

189. In order to establish baseline data on the presence of important wildlife and faunal habitats in the project area, a field assessment has been carried using field surveys (walkover surveys and consultations with local forestry and wildlife officials and local communities). The main findings of this Wildlife Study are summarized herewith.

190. The main objectives of the biodiversity study were to assess and document wildlife and faunal habitats in the project area and along the proposed alignment in particular. The study has been carried out in the months of January-February 2020. The methods including literature review, direct field sightings by transect walk, discussions with local communities, consultations with local (field level) forest officials etc. were used to collect data on presence of wildlife and avifauna in protected areas along the project road.

191. The fauna along and surrounding the project road incudes mammals such Porcupine, Mongoose, Wild boar, Common monkey, Hare and Jackal. Birds include Little cormorant, Eastern purple heron, Night heron, Paddy bird, Little Egret, Cattle Egret, Brahmny kite, Pariah kite, Koel, Southern Indian roller, Common myna, Ceylon house crow, Indian house sparrow, Tailor bird, Common teal, Jungle bush quail, Satone curlew, Spotted dove, Parakeet and Crow pheasant. Butterflies includes Indian common crow, Indian red grass and Tailed jay. Reptiles includes House Lizard, Common garden lizard, Indian chameleon, Krait and Indian cobra. Amphibians includes common frog and Toad. There are no vulnerable/ endangered or rare species fauna around the project site. There is no presence of any fauna species listed in Schedule I of the Wild Life (Protection) Act, 1972 of Government of India. The fauna along the project road is presented in below Table 29.

4 Tamil Nadu Forest Department. http://tnenvis.nic.in/Database/SoilResources_1171.aspx

85

Table 29: List of Fauna in the Influence Area of Project Road

S. No.

Zoological Name Local Name

Conservation status as per Wild life Protection Act (1972)

IUCN

Mammals

1 Hystrix indica Porcupine IV Least Concern

2 Herpestes edwardsi Mongoose II Least Concern

3 Sus scrofa Wild boar III Least Concern

4 Macaca radiata Common monkey II -

5 Lepus nigricollis Hare IV Least Concern

6 Canis aureus Jackal II Least Concern

Reptiles

1 Hemidactylus frenatus House Lizard Schedule IV Least Concern

2 Calotes versicolor Common garden lizard

Schedule IV -

3 Chamaeleo zeylanicus Indian chameleon Schedule IV Least Concern

4 Bungarus caeruleus Krait Schedule-IV -

5 Naja naja Indian cobra Schedule IV -

Amphibian

1 Rana tigrina Common frog Schedule IV Least Concern

2 Bufo melanostictus Toad Schedule IV Least Concern

Bird

1 Phalacrocorax niger Little cormorant Schedule IV Least Concern

2 Ardea purpurea manilensis

Eastern purple heron

Schedule IV -

3 nycticorax nycticorax Night heron Schedule IV Least Concern

4 Ardeola grayii Paddy bird Schedule IV Least Concern

5 Egretta garzetta Little Egret Schedule IV Least Concern

6 Bubulcus ibis Cattle Egret Schedule IV Least Concern

7 Haliastur Indus Brahmny kite Schedule IV Least Concern

8 Milvus migrans Pariah kite Schedule IV Least Concern

9 Eudynamys scolopaceus Koel Schedule IV Least Concern

10 Coracias benghalensis Southern Indian roller

Schedule IV Least Concern

11 Acridotheres tristis Common myna Schedule IV Least Concern

12 Corvus splendens Ceylon house crow Schedule V Least Concern

13 Passer domesticus indicus

Indian house sparrow

Schedule IV Least Concern

14 Orthotomus sutorius Tailor bird Schedule IV Least Concern

15 Anas crecca Common teal Schedule-IV Least Concern

16 Perdicula asiatica Jungle bush quail Schedule-IV Least Concern

17 Burhinus oedicnemus Satone curlew Schedule-IV Least Concern

18 Spilopelia chinensis Spotted dove Schedule-IV Least Concern

19 Psittacula cyanocephala Parakeet Schedule-IV Least Concern

20 Centropus sinensis Crow pheasant Schedule-IV Least Concern

86

Butterfly

1 Euploea core Indian common crow Schedule-IV Least Concern

2 Euploea crassa Indian red grass Schedule-IV -

3 Graphium agamemnon Tailed jay Schedule-IV -

b) Threatened Species

192. The field survey results and consultation with stakeholder confirm that in the PAI for the road section there is no habitat of globally threatened species or migratory species visiting the protected area.

E. Socio-economic Environment

1. Demography

193. The project road passes through two districts of Tamil Nadu namely Kanchipuram and Tiruvannamalai.

194. Kanchipuram: According to 2011 census, Kancheepuram district had a population of 3,998,252 with male population of 2,012,958 and female population of 1,985,294. Sex-ratio of district is 986 females for every 1,000 males, much above the national average of 929. Male and female literacy rate in the district is 89.89% and 79.02% respectively. The population density in the district is 892 persons per sq.km. Scheduled Castes and Scheduled Tribes accounted for 23.71% and 1.03% of the population respectively. The average literacy of the district was 75.37%, compared to the national average of 72.99%. The district had a total of 1,006,245 households. There was a total of 1,673,814 workers, comprising 74,761 cultivators, 162,494 main agricultural labourers, 41,149 in house hold industries, 1,088,974 other workers, 306,436 marginal workers, 14,582 marginal cultivators, 110,020 marginal agricultural labourers, 13,583 marginal workers in household industries and 168,251 other marginal workers.

195. According to 2011 census, Tiruvannamalai District had a population of 2,464,875 with a sex-ratio of 994 females for every 1,000 males, much above the national average of 929. A total of 272,569 were under the age of six, constituting 141,205 males and 131,364 females. Scheduled Castes and Scheduled Tribes accounted for 22.94% and 3.69% of the population respectively. The average literacy of the district was 66.%, compared to the national average of 72.99%. The district had a total of 588,836 households. There were a total of 1,238,177 workers, comprising 265,183 cultivators, 351,310 main agricultural labourers, 37,020 in house hold industries, 316,559 other workers, 268,105 marginal workers, 27,458 marginal cultivators, 173,753 marginal agricultural labourers, 9,700 marginal workers in household industries and 57,194 other marginal workers.

2. Land Use

196. The land use distribution along the 500 m of project road is predominantly Agricultural land followed by Settlement followed by open dry land. The land use along the project road is mostly arable land. Around 6% of project road passes through and along forest area, and social forestry plantations 43% passes through builtup/habitation areas and 51% passes through agricultural areas.

87

3. Economic Development

197. The economy of Tamil Nadu has grown steadily from a plan allocation of about ₹280 billion during 2012–2013, to about ₹606 billion during 2016–2017. The plan expenditure has grown by over 20% per annum during this period. Gross state domestic product and net state domestic product have been growing at over 10% from 2011–2012 to 2016–2017, though there is an expectation in the budget for 2017–2018 that these may drop below 10% in view of the impact of demonetization and introduction of the goods and services tax regime. From 2017– 2018, the concept of plan and non-plan expenditure is no longer followed and a substitute measure could be the capital expenditure as a proportion of the budget. The state budget mentions that it is paying special attention to capital expenditure. The allocation for capital expenditure is about 15% of the total budget expenditure for 2017–2018.

4. Agriculture

198. Agriculture plays a vital role in the State’s economy. The major source of economy along the project road is agriculture and livestock. Agriculture is the main occupation of the people with 47% of the population engaged in it. Paddy is the major crop cultivated in this district. Groundnuts, sugarcane, cereals, millets and pulses are the other major crops cultivated. 76.50 Metric Tonnes of fuel wood and 8.039 Tonnes of cashew are produced from cultivated lands. Palar river along with tanks and wells are the main sources of irrigation in this district.

5. Archaeological and Historical Monuments

199. Road survey during DPR and preparation of this report revealed that there are no archaeological or historical monuments or physical cultural resources present along the road. No archaeological sites or historical monuments of state importance notified under Ancient and Historical Monument and Archaeological Sites and Remains Act, 1966 of Tamil Nadu nor of national importance notified under The Ancient Monuments and Archaeological Sites and Remains Act 1958 of India are located along the project road section.

6. Sensitive Receptors

200. Road survey during DPR and preparation of this report revealed that there are no archaeological or historical monuments or physical cultural resources present along the road. During the environmental and social screening survey, number of sensitive receptors such as school, temple etc. are located along the alignment.

201. The list of sensitive receptors/structures on either side within 50m from center line of the road is presented in Table 30. These sensitive features along the road will be updated following the finalization of the resettlement plan by TNHD and the final detailed engineering design by the EPC contractor of the project road.

88

Table 30: Physical/Sensitive Features along the Project Road

S. No. Structure Village Name Chainage Distance from edge* (m)

Side

Educational Institutes along SH115

1 Saint Exupery matric high school

Cheyyur 0+850 8.7 LHS

2 Crescent metric high school Cheyyur 1+682 6.2 RHS

3 School Cheyyur 2+395 5.4 RHS

4 Girls Hostel Cheyyur 2+395 5.6 LHS

5 Girls School Cheyyur 2+395 5.2 LHS

6 Library Cheyyur 2+400 6 RHS

7 Library Cheyyur 2+500 14 RHS

8 Government high school Cheyyur 2+700 12.3 LHS

9 Gov primary school Kat-devatur 10+900 28 LHS

10 School Ki-karnai 12+125 9 LHS

11 Library Nallamur 13+100 13 LHS

12 School Kollathur 13+850 18 LHS

13 School Sarvanapakam 16+350 7 LHS

14 Bharathi mertriculation school

Chitamoor 16+600 6 RHS

15 Students Hostel Chitamoor 16+750 12 RHS

16 Government High school Chitamoor 16+850 11 LHS

17 Saint Anthony’s nursery & primary school

Mazhavangaranai, polambakkam

20+100 10 LHS

18 Adiparasathi college Melmervathur 24+430 10.3 LHS

19 Alfredo Cuomo High secondary school

Sendivakkam 27+450 7.2 LHS

20 School Ramapuram 31+115 8 RHS

21 School Salavedu 35+482 8 LHS

22 Higher Secondary School Salavedu 35+980 8 RHS

23 Sendhamizh matriculation school

Dip ammal nagar

39+007 6 LHS

24 School Kallankutthu 42+650 7 LHS

25 School Kadaisikulam 45+722 6 RHS

26 SRI Polytechnic college & School

Kadaisikulam 47+150 11 RHS

27 Thirrukal manadapam and research centre

Ponnur malai 60+594 36 RHS

28 Jain I.T.I. Ki nandimbadi 60+677 8 LHS

29 Thiruvallur college of engineering and technology

Thirumani 60+850 11 LHS

30 Arunachal city matriculation school

Thirumani 61+025 6 RHS

89

S. No. Structure Village Name Chainage Distance from edge* (m)

Side

31 ITI Kadambai 64+900 6 LHS

32 Library Mazhayur 67+000 8 LHS

33 High School Mazhayur 67+331 11 RHS

34 Suraj matric school &college Melthangal 72+750 8 LHS

35 College Nedungunam 75+450 41 RHS

36 School Nedungunam 76+086 11 LHS

37 Dr Maria ashoorf school of nursing

Chetpet 83+750 8 LHS

38 Govt. Higher Secondary School

Nembedu 88+356 16 LHS

39 Mishery school Tachambadi 90+775 6 LHS

40 Cluny matriculation high sec school

Devikapuram 93+100 6 LHS

41 Govt. high sec school Devikapuram 93+220 8 RHS

42 Vinayaka nursery & pri school

Devikapuram 95+325 36 RHS

43 Annamalai college of engineering

Modiyur 95+882 46 RHS

44 Library Modiyur 96+935 2 LHS

45 Chinmaya vidyalaya & matriculation school

Mattaiperaiyur 99+550 36 RHS

46 School Pulivananthal 102+325 6 RHS

47 School + temple Kommananthal 102+169 36 RHS

48 Gov high school Kommananthal 102+800 6 RHS

49 Oxford college of engineering Venmani 104+651 11 RHS

50 Oxford matric school Venmani 105+375 11 LHS

51 Primary school Venmani 106+065 11 RHS

52 Don Bosco ITI. Polur 106+750 11 RHS

53 Oxillium matriculation school Polur 106+871 8 RHS

54 St Joseph RCM School Polur 107+058 6 LHS

55 School Polur 107+400 7 LHS

Educational Institutes along ECR link road

1 School Mudaliyar kuppam

4+250 3.2 LHS

Community Structures along SH-115

1 Vinayaka koil Cheyyur 1+781 2.4 LHS

2 Vinayaka koil Cheyyur 1+781 0.6 LHS

3 Vinayaka koil Cheyyur 2+100 0.5 RHS

4 Ammaya temple Cheyyur 2+303 2 LHS

5 Ammaya temple Cheyyur 2+488 3.8 LHS

6 Ammaya temple Cheyyur 2+810 0.7 RHS

90

S. No. Structure Village Name Chainage Distance from edge* (m)

Side

7 Vinayaka koil Onambakkam 7+750 3.9 RHS

8 Munishvaran temple Munishvaran temple

10+244 4 RHS

9 Ammaya temple Kat-devatur 10+600 0.5 LHS

10 Vigneshvara temple Ki-karnai 12+107 1.5 LHS

11 Vinayaka temple Nallamur 13+100 0.4 LHS

12 Sai baba temple Nallamur 14+900 5 LHS

13 Nagdevata temple Perumbakkam 18+250 2 LHS

14 Kaliamman temple Mazhavangaranai

20+450 2.1 RHS

15 Hanuman temple Mazhavangaranai

20+480 1 RHS

16 Vinayaka koil Sothupakkam 22+870 1.2 RHS

17 Vinayaka temple Sothupakkam 22+449 0.5 RHS

18 Vinayaka koil Sothupakkam 23+750 2 LHS

19 Ammaya temple Sothupakkam 23+930 3 RHS

20 Church Melmervathur 24+988 4.5 LHS

21 Nag koil Ramapuram 31+050 1.5 LHS

22 Ammaya temple Dipammal nagar

37+875 4 RHS

23 Kumar swami temple Dipammal nagar

38+280 6 RHS

24 Ammaya temple Kil kodangalore 38+480 2.6 RHS

25 Temple Kallankutthu 42+680 2 LHS

26 Vinayaka temple Kallankutthu 42+730 4.3 LHS

27 Navagraha temple Kallankutthu 42+730 4 LHS

28 Church Kallankutthu 42+900 3 RHS

29 Vinayaka koil Kadaisikulam 46+036 6 RHS

30 Vinayaka koil Annanagar Mambat

55+493 2 LHS

31 Ammaya temple Arasur 57+675 3 RHS

32 Vinayaka koil Kadambai 64+750 4 RHS

33 Ammaya temple Kadambai 64+925 6 LHS

34 Perumal temple Mazhayur 67+520 6 RHS

35 Perumal temple Mazhayur 68+000 4 RHS

36 Vinayaka temple Mazhayur 68+150 6 LHS

37 Munishvaran temple Ettithangal 70+00 3 LHS

38 Vinayaka and navagraha koil Chinakoipuliyur 72+05 5 RHS

39 Vinayaka temple Nedungunam 76+115 3 RHS

40 Vinayaka temple Nembedu 87+221 3 LHS

91

S. No. Structure Village Name Chainage Distance from edge* (m)

Side

41 Amman koil Nembedu 87+650 3 RHS

42 Vinayaka koil Nembedu 87+750 0.5 RHS

43 Vinayaka koil Ramapuram 89+525 4 LHS

44 Ammaya temple Ramapuram 89+650 6 LHS

45 Dropadi amman temple Devikapuram 93+250 0.5 LHS

46 Temple Modiyur 96+621 4 LHS

47 Rama temple Modiyur 96+765 6 RHS

48 Siva temple Modiyur 96+939 2 LHS

49 Ammaya temple Modiyur 96+941 2 LHS

50 Church Pulivananthal 100+810 2 RHS

51 Amman koil Pulivananthal 101+175 3 LHS

52 Vinayaka temple Pulivananthal 102+400 2 RHS

53 Ammaya temple Kommananthal 102+691 3 RHS

54 Kumarswamy temple Karaipondi 104+175 3 LHS

Community Structures along ECR Link road

1 Church Mudaliyar kuppam

4+170 1.3 RHS

1 Government hospital Cheyyur 2+205 15 LHS

2 Veterinary hospital Cheyyur 2+604 13 LHS

3 Vetarnary hospital Kil kodangalore 39+338 11 LHS

4 Govt. primary health centre gate

Mazhayur 65+800 11 LHS

5 St Thomas hospital & leprosy center

Chetpet 83+500 11 LHS

6 Vetarnary hospital Tachambadi 91+700 8 LHS

7 Gov pri health care cantre Devikapuram 95+225 6 RHS

8 Vetarnary hospital Modiyur 96+410 26 LHS

9 Village hospital Modiyur 96+474 25 LHS

10 Govt. pri health care centre Kommananthal 102+650 11 RHS

*Note-Approx. distance from the edge of the existing road (carriageway)

92

V. ANALYSIS OF ALTERNATIVES

202. This chapter presents the feasible alternatives to the proposed project with respect to site, design, technology etc. Since, the proposed project is an improvement of the existing road, no alternative alignments were considered for alternate route. Hence, an evaluation has been carried out for the ‘with’ and ‘without’ project situation in terms of the potential environmental impacts for the justification of the project. This chapter discusses how environmental parameters were assigned due importance and were carefully considered in the analysis of alternatives. The alternate alignment options for proposed bypasses were analysed based on technical, social, environmental and economic aspects

A. With Project’ and ‘Without Project’ Scenario

(i) ‘With Project’ Scenario

203. The ‘with project’ scenario includes the widening of road section to two lane carriageway with paved shoulders configurations of the existing road section of Cheyyur - Polur section of SH 115 and ECR Link in Tamil Nadu. The ‘with project’ scenario has been assessed to be economically viable and will alleviate the existing conditions. It would thereby, contribute to the development goals envisaged by State Government, and enhance the growth potential of the state through Chennai-Kanyakumari Industrial Corridor as well as the region. 204. To avoid the large-scale acquisition of land and properties, the project envisages the widening of existing road to two-lane with paved shoulders configuration and mostly along the existing alignment to minimize the loss of properties and livelihood of the PAPs.

(ii) ‘Without Project’ Scenario

205. In the case of ‘without project’ scenario the existing road with narrow carriageway width will be considered as it is. Considering the present traffic volume and potential for growth in near future, the capacity of the present road is insufficient for handling expected traffic volume and calls for immediate improvements.

206. The existing road section has poor riding condition, drainage, and geometry. Poor drainage is seriously impacting and deteriorating the road surface. The poor road conditions, population growth, increase in traffic volumes and the economic development along the project corridor would further exacerbate the already critical situation. The existing unsafe conditions and the adverse environmental consequences, in terms of the environmental quality along the roads, would continue to worsen in the absence of the proposed improvements.

207. Therefore, the no-action alternative is neither a reasonable nor a prudent course of action for the proposed project, as it would amount to failure to initiate any further improvements and impede economic development. Keeping in view the site conditions and the scope of development of the area, the ‘With-’ and ‘Without project’ scenarios have been compared as shown in Table 31. By looking at the table it can be concluded that “With project” scenario with positive/beneficial impacts will vastly improve the environment and enhance social and economic development of the region compared to the “Without project” scenario, which will further deteriorate the present environmental setup and quality of life. Hence the “With project” scenario with minor reversible impacts is an acceptable option than the “Without project” scenario. The implementation of the

93

project therefore will be definitely advantageous to achieve the holistic development of the economy and progress of the State.

94

Table 31: Comparison of Positive and Negative Impacts of ‘With’ and ‘Without’ Project Scenario With Project Without Project

Impacts Impacts

+ve -ve +ve -ve

Environmental Aspects

• With the improvement of road surface and slope protection measures, the traffic congestion due to obstructed movement of vehicles will be minimized and thus wastage of fuel emissions from the vehicles will be reduced.

• Providing better level of service in terms of improved riding quality and smooth traffic flow.

• Reduce in air pollutants emission

• Minor change in topography is expected due to construction of embankments.

• Minor changes in land use pattern.

Nil • Increase in travel time.

• Increase case of landslide and soil erosion.

• Increase in fuel consumptions.

• Increase in dust pollution and vehicular emission.

• Land degradation, dust pollution and damage to pastureland, contamination in water bodies due to vehicles travelling along multiple tracks on the open ground.

• Reduced transportation costs. • Increase in air pollution due to vehicular traffic.

• Increase in noise pollution due to vehicular traffic during construction work.

• Short term local increase in dust due to earth work during construction at micro-level.

Nil • Project road will further deteriorate.

• Possible increase in air pollutants due to poor road conditions and increased traffic

• All industrial corridor access reliability.

• Plantation of trees as part of compensatory afforestation

• Removal of vegetative cover along the road due to loss of trees.

• Impacts of flora and fauna.

• Diversion of area of revenue land.

Nil • Aged trees will removed with due period

• Reduction in erosion of elevated embankments. Nil Nil • Increase in erosions due to poor conditions of protection works

• Creation of sedimentation problems in water bodies.

• The widened and paved road will reduce impacts due to multiple tracking of vehicles on soil and vegetation along the road.

• Improved drainage capacities

• Nil Nil • Increased adverse impacts on soil erosion and loss of vegetation cover.

95

With Project Without Project

Impacts Impacts

+ve -ve +ve -ve

Socio-economic Aspects

• Increased access to markets. • Loss to properties and livelihood. Nil • Increased vehicle operation cost.

• Access to new employment centers. Nil Nil • Reduced employment/ economic opportunities.

• Employment to local workers during the execution of the project.

Nil Nil • Arrest of possible significant enhancement and economic development of the region.

• Better access to part of the district as the project road is a lifeline of industrial area of the district.

• Reduced accidents/increased road safety.

• Tourism will flourish

• Better access to health care centres and other social services.

• Improved quality of life.

Nil Nil • Increase in accidents.

• Overall economy of the State will be affected.

• Deep impact to human health in case of emergency.

• Strengthening of local economies. Nil Nil • In absence of the project, it is extremely difficult to generate funds for such a massive improvement of the road infrastructure from its own resources.

• Reduction in travel time and development of the important places in the districts of Kanchipuram and Tiruvannamalai of Tamil Nadu State.

Increase in speed may lead to accidents in congested areas.

Nil • Hamper the development of the area.

96

208. Based on analysis of “with” and “without” project scenario presented in Table 31, “with” project scenario, with its minor adverse impacts is more acceptable than the “without” project scenario. The potential benefits of the proposed road improvements are substantial and far-reaching both in terms of the geographical spread and time. Hence, it is clear that the implementation of the project with the environmental management plan for mitigation of adverse environmental impacts will contribute to the development of economy and progress for its people of the vicinity as well as environmental improvements.

B. Location and Alignment Alternatives

209. Detail discussion on Bypasses proposal for the congested area along the existing road are given in following sections. The various options of alternate alignments were studied and feasible option is selected on the basis of comparative analysis of technical, social, environment and economical aspects.

i. Vandavasi Bypass

210. Though bypassable traffic to Vandavasi town is only 29%, it is very essential to provide bypass for Vandavasi town on this road section considering poor geometrics along existing alignment and large demolition of existing structures (shops, residential, commercial) which may lead to public agitation. The consultant studied the alignment corridor and prepared the comparison among various alternative alignment corridors to identify the most suitable corridor for further study. The alternative alignments of proposed bypass for Vandavasi Town is shown in Figure 18. Comparison of alternative alignments of proposed bypass for Vandavasi Town is given in Table 32.

Figure 18: Alternative Alignments of Proposed Bypass For Vandavasi Town (SH-115)

97

Table 32: Comparison of Alternative Alignments of Proposed Bypass For Vandavasi

Town (SH-115)

Sl. No.

Feature/Description

Existing Alignment Option-1 Alternative Option - 2 Alternative Option - 3

Existing Road (A-B-C-D-E) New Alignment (B-F-E) New Alignment (A-G-H)

1 Road Length (km)

7.47km (km 45.200 to km 52.670)

5.46km (km 45.200 to km 52.670)

5.18km (km 45.850 of SH-115 to km 36.930 of SH-116)

2 Existing ROW

10 - -

3 Proposed ROW

16 30 30

4 Geometrics / Horizontal Curve

(i) Number of curves

33 5 2

(ii) Radius (m)

20 (R<40); 13(R<150) 5 (R>360) 2 (R>360)

5 Divertible Traffic (Car, Bus, Truck)

3076 Nos. 902 Nos. (29.32*%); 1871 PCU

1238 Nos. (29.32*%); 1871 PCU

6 Cross Drainage

(i) Major (no. & length)

1 (1-70m) 1 (1-80m) 1 (1-90m)

(ii) Minor (no. & length)

1 (1-15m) 2 (1-35m) 1 (1-50)

(iii) Culverts (nos.)

14 17 18

(iv) ROB/RUB

- - -

7 Major Junction Improvements

14 4 5

8 Environmental Issues

98

(i) Affected Water Bodies, ponds

- 1-Pond partially affected -

(ii) Forest Land

- - -

9 Social Issues

(i) Habitations/Built-up

5 villages/towns including Vandavasi town area

- -

(ii) Land Requirements (ha.)

5 17 16

10 Stakeholders/Public Consultation

Yes Yes Yes

11 Justification for proposed bypass

Improvement through the existing road and built-up area of Vandavasi town will lead to the following: i. The improvement of existing road through the Vandavasi town is not feasible and viable; ii. Displacement of market area of a length of about 3.00km; iii. Acquisition of structures i.e. commercial areas as well as residential houses of 2/3/4 storey buildings and even more will affect the cost of the project; iv. Movement of heavy vehicles even after improvement of existing road will enhance air & noise pollution; v. Even more, the traffic is not allowed to pass through the built- up area of Vandavasi town these days; vi.The improvement of existing road through built-up section is only feasible at the cost of displacement and dismantling of old structures through the commercial area; vii. Affect the livelihood of locals; viii. Stakeholders were in the

The consultant conducted public stakeholder/consultation meeting in the presence of public and local representatives: i. The length of the proposed bypass is about 5.50km only; ii. The stakeholders were in the strong opinion for bypass to Vandavasi town; iii. The proposal will decongest the town; iv. It will improve road safety in the project area; v. Improve economic and social conditions of the area; vi. Avoid rehabilitation of affected stakeholders; vii. Reduce air and noise pollution; viii. There is little higher land acquisition (17.00 ha.) including provision for junction improvement;

The consultant carried out detailed study on the alternative alignments and conducted public consultation meeting in the presence of stakeholders and local representatives. The outcome of the detailed study is as under: i. Comparatively shorter length of alternative alignment as 5.18km, however the user have to travel all through proposed Vandavasi bypass on SH-116, SH-5 and Vandavasi bypass about a length of 8.20km to reach to Polur Road; ii. Involve and acquisition requirement of 16.00

99

opinion to provide bypass or a ring road to Vandavasi town without loss of livelihood.

ix. Involve construction of 1 major and two minor bridge of 80m and 35.0m length respectively;

ha; iii. Involves construction of one major bridge of length 90m. iv. Involve construction of one minor bridge of length 50m

12 Recommendations

- Recommended Option -

a. Alternative-1:

• Involves acquisition of maximum structures, houses, shops; buildings etc. for improvement of road through the built-up area of Vandavasi town;

• Will lead to enhancement of air and noise pollution by movement of through heavy traffic;

• Number of sub-standard curves in existing road alignment. • Technically, improvement of existing road through the Vandavasi town is not feasible,

which will require to demolish a number of buildings/houses and commercial structures and lead to public agitation too;

b. Alternative-2 (Recommended):

• About 29% traffic is bypassable to Vandavasi town; • Tentative length of proposed bypass 5.50km; • Involves acquisition of land about 17.0 ha.; • Will reduce the pollution level by providing bypasses; • Involves construction of one major and two minor bridges of 80m and 35m respectively; • No acquisition of structures, etc

c. Alternative-3:

• Involve land requirement of 16.00 ha; • Involve construction of one minor bridge of length 50m; • Involver construction of one Major Bridge of length 90m;

211. Finalization of Alternative: Keeping all above in view, the Alternative Alignment Option-2 (Southern Side) has minimum hindrances except acquisition of land of about 17.00 ha. as comparing with improvement of existing road through the built-up area of Vandavasi town. Thus, Alternative Alignment Option-2 is found most suitable for Vandavasi town with minimum hindrances.

ii. Chetpet Bypass

212. Though bypass able traffic to Chetpet town is only 36%, it is very essential to provide bypass for Chetpet town on this road section considering poor geometrics along existing alignment and large demolition of existing structures (shops, residential, commercial) which may lead to public agitation. The consultant studied the alignment corridor and prepared the comparison among various alternative alignment corridors to identify the most suitable corridor for further study. The alternative Alignments of Proposed Bypass for Chetpet Town is shown in

100

Figure 19. Comparison of Alternative Alignments of Proposed Bypass for Chetpet Town is given in Table 33.

Figure 19: Alternative Alignments of Proposed Bypass For Chetpet Town (SH-115)

101

Table 33: Comparison of Alternative Alignments of Proposed Bypass for Chetpet Town (SH-115) Sl. No.

Feature/Description Existing Alignment Option-1 Alternative Option - 2 Alternative Option - 3

Existing Road (A-B-C-D-E) New Alignment (B-F-E) New Alignment (A-G-H)

1 Road Length (km) 2.19km (km 78.300 to km 80.490) 4.24km 3.44km

2 Existing ROW 9 - -

3 Proposed ROW 16 30 30

4 Geometrics / Horizontal Curve

(i) Number of curves 13 3 4

(ii) Radius (m) 6 (R<50); 7(R<200) 3 (R>360) 4 (R>360)

5 Divertible Traffic (Car, Bus, Truck)

3076 Nos. 1113 Nos. (36.18*%); 2418 PCU

1113 Nos. (36.18*%); 2418 PCU

6 Cross Drainage

(i) Major (no. & length) - - 1 (1-65m)

(ii) Minor (no. & length) 1 (1-11m) 2 (1-40m; 1-15) 2 (2-15)

(iii) Culverts (nos.) 5 14 12

(iv) ROB/RUB - - -

7 Major Junction Improvements 5 3 5

8 Environmental Issues

(i) Affected Water Bodies, ponds

- - -

(ii) Forest Land - - -

9 Social Issues

10 (i) Habitations/Built-up 2 villages/towns including Chetpet town area

- -

(ii) Land Requirements (ha.) 2 13 11

Stakeholders/Public Consultation

Yes Yes Yes

11 Justification for proposed bypass

Improvement through the existing road and built-up area of Chetpet town will lead to the following: i. The improvement of existing road through the Chetpet town is not feasible

The consultant conducted public / stakeholder consultation meeting in the presence of public and local representatives:

The consultant carried out detailed study on the alternative alignments and conducted public consultation meeting in the

102

due to sub standard curves and restricted ROW; ii. Displacement of market area of a length of about 2.50km; iii. Acquisition of structures i.e. commercial areas as well as residential houses of 2/3/4 storey buildings and even more will affect the cost of the project; iv. Movement of heavy vehicles even after improvement of existing road will enhance air & noise pollution; v. The improvement of existing road through built-up section is only feasible at the cost of displacement and dismantling of old structures through the commercial area; vi. Affect the livelihood of locals; vii. Stakeholders were in the opinion to provide bypass / ring road to Chetpet town without loss of livelihood.

i. The length of the proposed bypass is about 4.25km only; ii. The stakeholders were in the strong opinion for bypass/Ring Road to Chetpet town; iii. The proposal will decongest the town; iv. It will improve road safety in the project area; v. Improve economic and social conditions of the area; vi. Avoid rehabilitation of affected stakeholders; vii. Reduce air and noise pollution; viii.There is land acquisition of 13.00 ha. including provision for junction improvement; ix. Involve construction of two minor bridge of 40m and 15.0m length respectively;

presence of stakeholders and local representatives. The outcome of the detailed study is as under: i. Comparatively shorter length of alternative alignment as 3.44km; ii. Involve land acquisition requirement of 11.00 ha; iii. Involves construction of one major bridge of length 65m. iv. Involve construction of two minor bridge of length 15m.

12 Recommendations - Recommended Option -

103

a. Alternative-1:

• Involves acquisition of maximum structures, houses, shops; buildings etc. for improvement of road through the built-up area of Chetpet town;

• Will lead to enhancement of air and noise pollution by movement of through heavy traffic;

• Number of sub-standard curves in existing road alignment. • Technically, improvement of existing road through the Chetpet town is not

feasible, which will require to demolish a number of buildings/houses and commercial structures and lead to public agitation too.

b. Alternative-2 (Recommended):

• Tentative length of proposed bypass 4.25km; • Involves acquisition of land about 13.0 ha.; • Will reduce the pollution level by providing bypasses; • Involves construction of two minor bridges of 40m and 15m respectively; • No acquisition of structures, etc. • About 36% of traffic is bypassable to Chetpet town.

c. Alternative-3: • Involve land requirement of 11.00 ha; • Involve construction of two minor bridge of length 15m; • Involve construction of one Major Bridge of length 65m;

213. Finalization of Alignment: Keeping all above in view, the Alternative Alignment Option-2 (Northern Side) has minimum hindrances except acquisition of land of about 13.00 ha as comparing with improvement of existing road through the built-up area of Chetpet town. Thus, based on the comparison of all alternative alignment options, Alternative Alignment Option-2 is found most suitable for Chetpet town with minimum hindrances.

C. Design Decision Constraints For Various Alternatives

214. Road widening and design speed were considered for the various alternatives considered for the project. The design decisions were taken up considering the following factors also:

▪ Road submerges in rainy season; ▪ Public water taps and water tanks along the corridor; ▪ Religious structures; ▪ Roadside ponds; ▪ Hand Pumps; ▪ Bore Wells and wells; and ▪ Presence of canals and drains,and ; ▪ Congested settlements.

D. Alignment Modifications due to Environmental Considerations

215. The selection of the alignment / widening options along various sections has been worked out based on continuous interaction between the engineering design team and environmental study teams. Various alignment improvement alternatives (left/right) for the project road have been analysed along entire project road considering rural sections, and junction improvements. The factors considered for evaluation of alignment option are:

104

• Flora and fauna likely to be impacted;

• Productive agricultural land likely to be impacted;

• Impact on water resources and surface water bodies;

• Environmental quality;

• Land availability;

• Land uses along the alignment;

• Residential / Commercial structures Impacted;

• Utilities likely to be impacted;

• Common property resources likely to be impacted; and

• Religious structures affected.

E. Engineering/Technological Alternatives

216. The formulation and analysis of engineering alternatives have been undertaken in terms of alternative cross-sections of road, highway-design principles (such as embankments for soil erosion and slope protections, hill cuttings, minimum width of road ride drainage, adequacy of roadway width at cross drainage structures, minimum gradient, etc.), comparison between flexible and rigid pavements (cement-concrete built rigid pavement as being environmentally superior then traditional flexible pavement), and selection of environmental friendly road construction methods.

105

VI. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

A. Introduction

217. This chapter presents key environmental issues associated with various aspects of the proposed project. The environmental impacts caused due to the development of the project road section were assessed on the basis of nature, extent and magnitude of likely changes due to project activities during all stages of the project cycle, i.e. preconstruction, construction and operation. Potential cumulative and induced impacts were also considered. Beneficial impacts are mostly long-term and permanent whereas adverse impacts are localized and temporary in nature and are likely to occur mostly during construction stage.

218. The methodology of assessing environmental impacts from the project entailed clearly identifying the environmental components that will impacted, type of impacts, assessment area where the impacts will be felt and defining the criteria for assessing the significance of each type of impact. After defining these aspects, a screening of project impacts during design and preconstruction, construction and operation stages of the project was carried out to identify the minor, moderate and major impacts to guide development of mitigation measures and ensure that there are no or minimal residual impacts.

219. Identification of impacts: This includes identifying the valued environmental components (VEC) of the physical, biological, and human environments that are at risk of being impacted by the project. The VECs for this project which are based on the environmental baseline are:

a. Physical environment: air quality and greenhouse gas emissions, land and soil, and groundwater quality and quantity

b. Biological environment: terrestrial and aquatic vegetation, mammals, avifauna, and ecologically important areas

c. Human environment: private land and buildings, public infrastructure including utility structures, noise and vibration levels, cultural/heritage buildings, and occupational health and safety for the construction workers and local community living within the vicinity of the project area.

220. Type of impact on the VECs: The type of impact can be described as:

a. Positive: Improvement in the quality of the VECs because of the project, b. Negative: Degradation or reduction in the quality of the VECs because of the project, c. Neutral: No noticeable change in VECs

221. Area of impact assessment. The area covered for assessing direct impacts include:

a. The right of way of project road section is taken as 16 meters for urban stretches, 23 meters for rural areas, and 30 meters for bypasses 30m corridor. This includes 10m on either side studied for direct impacts (corridor of impact).

b. Project area of influence is defined as ROW plus 500m on either side; c. In addition, a 10 km buffer was studied for indirect impacts. Other indirect impact

area covers location of quarries; borrow areas, storage area of construction material etc.

222. Significance of impacts. The assessment of the significance of the impacts on the VECs requires understanding the duration of impact, area of impact and severity of impact as follow

106

(i) Duration of the impact: Duration means the time dimension of the impact on the VECs. The terms permanent, temporary and short-loved are used to describe the duration of impact:

a. Short-lived: The impact is limited to particular activity/ies or phase/s of the project lifecycle

b. Temporary: The impact is felt during one project activity or, at most, during the construction period of the project

c. Permanent: The impacts are felt throughout the life of the infrastructure

223. Area of impact: The area of impact entails the spatial scale of impact on one or more of the VECs. The terms regional, local and limited are used to describe the area of impact:

a. Limited: The impact is felt within the corridor of impact

b. Local: The impact is felt within the project area of influence

c. Regional: The impact is felt beyond the project area of influence but within the 10km buffer

(ii) Sensitivity of VEC: The sensitivity of a VEC can be determined by the existing

conditions of the VEC within the project area and existence of important VECs within the project areas. Sensitivity of each VEC is described as high, medium or low as described below.

a. Low: No environmentally important areas (such as protected areas, natural or

critical habitat areas, heritage sites, places of worship etc.) are located within the direct and indirect impact zone. The quality of existing conditions of VECs is good or fair;

b. Medium: There are one or more environmentally important areas within the indirect impact zone of the project area. The quality of existing conditions of VECs is good or fair; and

c. High: There are one or more environmentally important areas within the direct impact zone of the project area. The quality of existing conditions of the VECs is poor or degraded (such as poor air quality, high noise levels, poor water quality) which makes the VEC highly susceptible to further deterioration.

224. Based on baseline conditions in the project area and sensitivity criteria, the level of sensitivity of each VEC is provided in Table 34.

107

Table 34: Sensitivity of VECs in the Project Area

VEC Sensitivity Level

Remarks

Physical environment

Air quality

Medium The overall the air quality in the project area is average and within national permissible levels for the monitored parameters. However, the monitored values exceeds the World Bank group standards for ambient air quality.

GHG emissions

Medium Firewood burning is the major contributor in the ambient pollution load. Vehicular pollution is a secondary source of pollution in the state as the traffic density is average.

Surface water quality

Medium Overall, the surface water quality in the project area is good, permissible levels are not exceeded for the monitored parameters. Natural river streams, many village ponds and lake, Irrigation Canal are main water bodies in CoI of the project.

Surface water quantity

Low The state has good water resources in the form of lakes, ponds, rivers and streams. The project area has sources of water potential both ground as well as surface water.

Ground water quality

Low Overall, the ground water quality in the project area is good, permissible levels are not exceeded for the monitored parameters.

Ground water quantity

Low Since the project area has good surface water resources the project will have sufficient sources of water for construction and groundwater abstraction will be negligible if needed at all..

Land degradation and pollution

Low There is no forest along the project road section, land use mainly agriculture and built-up. Land degradation and pollution is low.

Biological environment

Trees, terrestrial and aquatic vegetation

Low The project road passes through reserved and social forests in multiple patches.

The road in these forest stretches will be widened and strengthen within the existing right of way and no land acquisition is required in this stretch.

Also, there are no endangered flora species which are likely to be affected by the proposed project.

Fauna (mammals, birds, fishes, reptiles, amphibians)

Low There are no vulnerable/ endangered or rare species fauna around the project site. There is no presence of any fauna species listed in Schedule I of the Wild Life (Protection) Act, 1972 of Government of India.

Ecologically important areas

Low The project is not located in core/ buffer zone of ecologically sensitive areas.

Social environment

108

VEC Sensitivity Level

Remarks

Private land and buildings

Medium 41.9833 hectare (ha.) of private land are required for the improvements. The private land to be acquired is mostly composed of small strips of land, with a width varying from 0.1 to 5.0 meters. Further, 1.76 ha of government land will also be required to be transferred for the proposed improvements.

The improvements proposed will cause impact to 567 private structures and 50 common property resources.

Public property/ infrastructure/ utility structures

Medium The ROW is available for widening or even minimum improvement of road geometry, except at few locations. Impact on utility structures is expected due to shifting from current location.

Noise

Medium Existing noise levels are higher than the permissible limits for residential area in both daytime and night time.

Vibration Low The structures are located away from CoI. Since road is existing one the vibration impacts are not expected to be high.

Occupational health and safety

Medium Road construction and increased traffic will lead to occupational health and safety risks.

Public health and safety

Medium Influx of workers during construction and the construction activities may pose risks to communities along the project road and ancillary sites. The expected increase in traffic during operation stage potentially leads to an increase in unsafe situations.

Physical cultural resources (PCR)

Low There are no adverse impacts anticipated on historical places/monuments. However, there are small shrines along the road.

(iii) Severity of impact. The severity or seriousness of an impact entails understanding the repercussion or risks posed by the impact. This is a subjective criterion, which is defined as high, medium or low as below:

a. High: The severity of impact is high if grave repercussions are expected as a

result of the impact due to any of the following or similar situations: the impact will be felt by a large number of people or receptors; the receptors are highly sensitive; the impacts will cause serious health issues; there is already a history of complaints from the project area and people have raised significant concerns during public consultation; some of the VEC in the project area already severely degraded and maybe further worsened by the project; there will be a significant change in one or more VEC because of the project

b. Medium: The severity of impact is medium due to any of the following or similar situations: the impact will be felt by a small number of people; some receptors are affected but they are not sensitive; the impact will not cause serious health issues; some concerns were raised during public consultations, but they were not significant; there will be minor changes in one or more VEC because of the project

109

c. Low: The severity of impact is low due to any of the following or similar situations: the impact will not be felt by anyone; no or limited receptors are affected; no concerns were raised during public consultations; there will be no noticeable changes in one or more VEC because of the project.

225. Based on the rating of duration, area and severity of impact as described above the overall significance of each impact as major, moderate or minor was determined as demonstrated in table 35 below.

Table 35: Criteria for Rating the Significance of Impacts Significance Sensitivity Duration Area Severity Minor Medium or Low Short lived or

temporary Limited or local or regional

Low

Low Permanent Limited low Moderate High or Medium Temporary Limited or local

or regional Medium

Medium permanent Limited Medium Major High Permanent or

temporary Limited or local or regional

High

High or Medium Permanent Local or regional

Medium

B. Screening of Impacts

226. Based on the rating criteria provided in Table 35, environmental impacts anticipated during the project design and pre-construction stage, construction stage and operation stage were screened for their level of significance as demonstrated in Table 36 below. The screening was carried out for impacts that are expected without mitigation. Hence, it guided the identification of impacts that need mitigation and clearly point out significant/major negative impacts that need to be prioritized for mitigation.

227. The significance of each environmental impact or project activity is indicated by the colors of the cells in the last column of the table. Red indicates major impact, orange indicates moderate impact, yellow indicates minor impact and green indicates positive impact. The following section discusses the details of impacts on each of the VECs in line with identification of major, moderate, minor impacts in the screening matrix. Major impacts have been given priority for identification of mitigation measures to ensure that there are minimal or no residual impacts.

110

Table 36: Screening of Environmental Impacts VEC/Sensitivity Impact/Activity Stag

e Duration Area Severity Significance

1. Physical environment

1.1 Air quality (Medium sensitivity)

No impact due to design D N N N N

Vegetation clearing and removal of trees quarrying, material transport and storage, drilling, hill cutting, Pavement works, use of construction equipment

C -ve temporary

-ve limited -ve medium -ve moderate

Emissions from increased road traffic O -ve permanent

-ve limited -ve low -ve minor

1.2 GHG emissions (Medium sensitivity) GHG Emissions

D, C, O

N N N N

1.3 Surface water quality (Medium sensitivity) Disruptions to the natural hydrology D

-ve temporary

-ve limited -ve medium -ve moderate

Construction near sensitive areas, culvert and bridge construction, use of construction equipment, pavement works, Labour camp activities

C -ve temporary

-ve limited -ve medium -ve moderate

No anticipated impacts O N N N N

1.4 Surface water quantity (Low sensitivity) Disruptions to the natural hydrology D

-ve temporary

-ve limited -ve medium -ve moderate

Construction near sensitive areas (RoW excluded from Reserve Forest) and sensitive areas Culvert and bridge construction, Drainage work, Earthwork, Quarrying, Debris generation

C -ve permanent

-ve limited -ve low -ve minor

No anticipated impacts O N N N N

1.5 Ground water quality (Low sensitivity)

No anticipated impacts D N N N N

Groundwater pollution due to labour camp activities C -ve temporary

-ve local -ve low -ve minor

No anticipated impacts O N N N N

1.6 Ground water quantity (Low sensitivity)

None D N N N N

Construction water requirement (avg. 500 KLD and peak 800 KLD and 40 KLD for workers)

C -ve permanent

-ve limited -ve low -ve minor

None O N N N N

111

VEC/Sensitivity Impact/Activity Stage

Duration Area Severity Significance

1.7 Land degradation/ pollution (Low sensitivity)

Changes in the local-level topography and appearance of the project site

D -ve permanent

-ve local -ve medium -ve minor

Drilling, hill cutting, earthwork, quarrying, pavement works, stripping of top soil, debris generation, oil and grease spoils disposal

C -ve temporary

-ve limited -ve medium -ve moderate

Soil erosion prevention O +ve permanent

+ve limited

+ve medium +ve

2. Biological environment

2.1 Trees, terrestrial and aquatic vegetation (Low sensitivity)

Vegetation clearing and removal of trees D -ve temporary

-ve limited -ve medium -ve moderate

Drilling, blasting and hill cutting, road widening, Vegetation clearing and removal of trees

C -ve temporary

-ve limited -ve medium -ve moderate

Planting of trees O +ve permanent

+ve local +ve medium +ve

2.2 Terrestrial fauna (mammals, birds, insects) (Low sensitivity)

Accident of wild mammals/birds/insects D -ve permanent

-ve limited -ve medium

-ve moderate

Use of construction materials, labour camp C -ve temporary

-ve limited -ve medium

-ve moderate

reduced human-animal conflict due to road safety features O +ve permanent

+ve local +ve medium +ve

2.3 Migratory birds and Ecologically important areas (Low sensitivity)

Loss of vegetative cover D -ve Temporary

-ve limited -ve medium -ve moderate

Labour camps, dust and pollution C -ve temporary

-ve limited -ve medium -ve moderate

No anticipated impacts O N N N N

3. Social environment

3.1 Private land and buildings (Medium sensitivity)

temporary structure and shrines likely to be affected due to widening of road section

D -ve permanent

-ve local -ve medium -ve moderate

Limited use of private land for ancillary facilities C -ve temporary

-ve local -ve low -ve minor

Possible impacts are not directly attributable to the project O N N N N

112

VEC/Sensitivity Impact/Activity Stage

Duration Area Severity Significance

3.2 Public property/infrastructure/ utility structures (Medium sensitivity)

Utility shifting preparation D -ve temporary

-ve local -ve low -ve minor

Utility shifting C -ve temporary

-ve local -ve low -ve minor

No anticipated impacts O N N N N

3.3 Noise (Medium sensitivity)

Road widening will produce noise levels higher than ambient noise levels (>3dB)

D,O -ve permanent

-ve local -ve medium -ve moderate

Quarrying, material transport and storage, drilling, hill cutting, pavement works, culvert and bridge construction

C -ve temporary

-ve limited -ve medium -ve moderate

3.4 Vibration (Low sensitivity)

None D N N N N

Construction machinery C -ve temporary

-ve local -ve medium -ve moderate

No anticipated impacts O N N N N

3.5 Occupational health and safety (Medium sensitivity)

No anticipated impacts D N N N N

Vehicle-related, falls and slips, struck-bys, caught-in-betweens, electrocution risks while carrying out work or residing in campsites

C -ve temporary

-ve local -ve high -ve moderate

No anticipated impacts O N N N N

3.6 Public health and safety (Medium sensitivity)

No anticipated impacts D N N N N

Disturbance and pollution, traffic-related safety risks, falls and slips in active construction sites, debris generation

C -ve temporary

-ve limited -ve high -ve moderate

Potential increase in accidents due to increase in traffic O -ve permanent

-ve limited -ve medium -ve moderate

Better access to healthcare and education O +ve permanent

+ve limited

+ve medium +ve

3.7 Physical cultural resources (PCR) (Medium sensitivity)

None D, C, O

N N N N

Note: +ve = positive impact; -ve = negative impact; AG = above ground; C = construction stage; D = design & pre- construction stage; N = neutral; O = operation stage; PC = pre-construction; UG = underground; VEC = valued environmental component

: positive impact : minor negative impact : moderate negative impact : major negative impact

113

C. Typical Potential Adverse Impacts

228. Identification and assessment of the potential environmental impacts are based on secondary information supplemented by field visits. Impacts on various environmental components have been assessed at four different stages, namely:

• the project location; • design and pre-construction; • construction; and • operation stages.

D. Impacts on Physical Environment

1. Air quality and Greenhouse gas emissions

Design and pre-construction stage – minor negativeimpact

229. The project aims to improve a section of 109.273 km of the existing state highway no. 115 from Cheyyur – Vandavasi – Polur Road. Based on the capacity augmentation the present road section is proposed for improvement and upgrading to a two lane configuration with shoulders and side drains. TNHD considered minimum clearing of trees and vegetation and will have minimal impact on the air quality and GHG emissions. A total of 4,770 trees >30 cm girth will be cleared for the road widening which is about 40% less than standard clearing requirements for the scale of widening since extra care was taken to minimize impacts on trees. Carbon sequestration capacity lost through clearing of trees is roughly 21 kg CO2/year per mature tree. These will be replaced with 10 saplings per cut tree whose survival (70%) will be ensured through monitoring and replacement. Each sapling has the ability to absorb roughly 5 kg CO2/year which largely offsets carbon sequestration capacity lost. More details on afforestation are under the section on Trees and Vegetation.

Construction stage – moderate negative impact

230. Impact: During construction air quality may be negatively impacted for short periods due to (i) the exhaust emissions from the operation of construction equipment and machinery; (ii) fugitive emissions from brick, concrete, and asphalt plants; (iii) the dust generated from the haulage of materials, exposed soils and material stockpiles, fugitive dust from earth-moving operations and demolition; (iv) cutting and filling of hill slope; (v) cleaning of the road; (vi) material loading; (vii) unloading; and (viii) increased traffic congestion in construction areas. The impact is expected to be localized, temporary and confined to construction areas. Care should, however, be taken at sensitive habitation locations so that harmful impacts can be minimized. The adverse impacts on air quality during construction stage were classified and presented in Table 37. There are two types of pollution i.e. dust pollution and pollution from harmful gases.

114

Table 37: Impact on Air Quality during Construction Stage

S. No. Impact Source 1. Generation of dust • Excavation activities

• Transportation and tipping of excavated material - while the former will occur over the entire stretch between the cutting location and disposal site, the latter is more location specific and more intense;

• Transportation of raw materials from quarries, borrow and disposal sites;

• Stone crushing, handling and storage of aggregates in asphalt plants;

• Site leveling, clearing of trees, laying of asphalt, construction of bridges;

• Concrete batching plants; • Asphalt mix plants – due to the mixing of aggregates

with bitumen; and • Construction of structures and allied activities

2. Generation of harmful emissions including SO2, NOx and HC

• Hot mix plants; • Large construction equipment, trucks and asphalt

producing and paving equipment; • Toxic gases released through the heating process

during bitumen production; and • Inadequate vehicle maintenance and the use of

adulterated fuel in vehicles.

231. Mitigation Measures: The project road section mainly passes through agriculture areas and presently air/dust pollution is not a major issue. In order to suppress any negative impact from the generation of dust during construction there will be regular watering of the road surfaces and exposed spoils or the application of emulsion coats near villages, where dust is a nuisance. Provisions will be incorporated into the contractor’s contract to require the use of dust suppression measures.

232. As it is expected that suspended particulate matter (PM10) levels will increase during construction, certain mitigation measures are suggested in order to keep these levels within the permissible standards. The following actions should be implemented:

• regular check-up and maintenance of construction equipment is required; • idling of engines is strongly discouraged; • mixing plants i.e. asphalt, concrete, and bricks, should be operated within the

permissible limits of CPCB and IFC EHS, and located away from settlements; • the contractor will submit a dust suppression and control programme to the PIU prior to

construction – this plan details actions to be taken to minimize dust generation and identify equipment to be used;

• vehicles delivering loose and fine materials should be covered to reduce spills and speed limits should be imposed;

• bitumen emulsion should be used wherever feasible; • no unauthorized burning of C&D waste materials; • bitumen heaters should be used and the use of wood for fuel prohibited. • Ambient air quality monitoring shall be done regularly at representative sensitive

locations to ensure that all the emissions from construction activities are within CPCB

115

and IFC EHS standards and therefore ensuring the effectiveness of mitigation measures taken.

233. Residual Impact: With the proper application of the proposed mitigation measures a residual impact on the air quality during construction phase will be minimal.

Operation stage – minor negative impact

234. Impact: To assess the likely impact on air quality at the various locations along the project road corridor, the prediction of the pollutant concentrations has been carried out using AERMOD, a dispersion model based on Gaussian Equation. Detailed analysis is presented in Appendix -7. The input parameters for the prediction are detailed in subsequent paragraphs.

235. The AERMOD atmospheric dispersion modeling system is an integrated system that includes three modules: (a) A steady-state dispersion model designed for short-range (up to 50 kilometers) dispersion of air pollutant emissions from stationary industrial sources. (b) A meteorological data preprocessor (AERMET) that accepts surface meteorological data, upper air soundings, and optionally, data from on-site instrument towers. It then calculates atmospheric parameters needed by the dispersion model, such as atmospheric turbulence characteristics, mixing heights, friction velocity, Monin-Obukov length and surface heat flux. (c) A terrain preprocessor (AERMAP) whose main purpose is to provide a physical relationship between terrain features and the behavior of air pollution plumes. It generates location and height data for each receptor location. It also provides information that allows the dispersion model to simulate the effects of air flowing over hills or splitting to flow around hills. AERMOD also includes PRIME (Plume Rise Model Enhancements) which is an algorithm for modeling the effects of downwash created by the pollution plume flowing over nearby buildings. Various input parameters for the prediction of pollutant concentrations are discussed below:

236. Traffic Volume: The fleet wise traffic volumes for the present study have been taken from the detailed feasibility report of the project. The annual average daily traffic (AADT) data is available for the proposed road through traffic survey. AERMOD model needs hourly average traffic volume. The total traffic hour volume is further categorized in to two wheeler, four wheeler, Light commercial vehicles (LCVs), Bus and high commercial vehicles (HCVs), based on the traffic survey at different road stretched along the highway. The annual average daily motorized traffic data are given in Table 38 with projected future traffic growth.

Table 38: Annual Average Daily Motorized Traffic Data

Year 4W LCV Truck Bus 3W 2W

2020 1963 801 449 1436 316 4323

2025 2964 961 551 1959 379 5894

2030 4236 1124 661 2584 444 7667

2035 5776 1285 774 3282 515 9646

237. Emission Factors: Emission factor is one of the important input parameter in AERMOD model. In the present study, the emission factors specified by the Automotive Research Association of India (ARAI, 2007) have been used for calculation of weighted emission factors. These emission factors have been expressed in terms of type of vehicles and type of fuel used (for petrol and diesel driven passenger cars). The emission factors used in the present study for different vehicles type are given in Table 39.

116

Table 39: Emission Factors for Different Types of Vehicle (ARAI, 2007)

Emission factors, g/km (ARAI, 2007)

2W 3W 4W LCV Bus Truck

CO 1.04 1.25 1.28 1.56 8.03 6

NOx 0.31 0.6 0.32 1.46 9.01 9.3

PM 0.02 0.22 0.04 0.28 0.55 1.24

SO2 0.01 0.01 0.03 0.06 0.13 0.13

238. Meteorological Conditions: The meteorological parameters such as wind speed, wind direction, temperature, rainfall, cloud cover, pressure, and humidity were used in model. Meteorological parameters observed during environmental monitoring carried out in the month of December 2019 were used for the model and is given below Table 40.

Table 40: Meteorological Parameters used for Modelling

Hour Temperature

(oC) Humidity

(%) WD (o)

Wind Speed (kmph)

Pressure (Pa)

Precip. (mm)

Cl

1:00 28.6 84 315 0 29.82 0 0

2:00 27.6 86 45 1 29.82 0 0

3:00 26.8 81 315 4 29.87 0 0

4:00 26.7 92 0 5 29.87 0 0

5:00 24.3 94 0 7 29.87 0 0

6:00 26.4 96 0 6 29.84 0 0

7:00 27.6 92 315 2 29.84 0 0

8:00 28.7 86 45 2 29.84 0 0

9:00 32.4 73 315 3 27.78 0 0

10:00 33.6 70 45 4 27.78 0 0

11:00 33.4 77 315 2 27.78 0 0

12:00 35.6 76 315 5 29.76 0 0

13:00 34.8 71 315 1 29.76 0 0

14:00 35.5 69 0 6 29.76 0 0

15:00 32.4 72 0 7 29.83 0 0

16:00 36.5 65 0 1 29.83 0 0

17:00 32.5 62 0 6 29.83 0 0

18:00 30.5 78 315 7 29.83 0 0

19:00 31.5 88 315 6 29.83 0 0

20:00 34.2 75 315 5 29.83 0 0

21:00 32.2 62 315 5 29.8 0 0

22:00 31.8 58 315 6 29.8 0 0

23:00 30.4 51 315 3 29.8 0 0

24:00 29.8 79 315 2 29.82 0 0

117

239. Receptors: A set of link receptors were taken at various receptor locations within each section at a distance of 10m, 20m, 50m, 100m, 200m and 500m both sides from center line of the carriageway to know the dispersion of pollutant from the road.

240. Background Concentration: The background pollutant concentrations were taken from environmental monitoring data. Air quality monitoring was carried out in the month of November 2019 at five locations throughout the alignment on two alternate days in a week. The background pollutant concentrations that were taken for model predictions are listed in Table 41.

Table 41: Average Background Concentration of Pollutants along the Project Road

Pollutant Average Background

concentration Unit

SO2 16.84 µg/m3

NOx 32.82 µg/m3

PM10 63.62 µg/m3

PM2.5 20.28 µg/m3

CO 0 mg/m3

241. Predicted Pollution Levels: The model has been setup and run to predict hourly average of CO and 24 hourly average of PM2.5, PM10, NOx and SO2 concentrations for the years 2020, 2025, 2030 and 2035 using forecasted traffic data on proposed highway. The predicted hourly average concentration of CO and 24 hourly average concentration of PM2.5, PM10, SO2 and NOx during peak traffic are shown in Tables 42 to 45 for proposed highway project.

118

Table 42: CO Predicted Concentrations (µg/m3) along the Proposed Road

Year

CO Concentration (µg/m3)

Distance from the centre line of the road, m. (Left side)

Distance from the centre line of the road, m. (Right side)

-500 -200 -100 -50 -20 -10 10 20 50 100 200 500

2020 11.37 19.85 32.71 51.57 82.41 130.42 6.42 2.79 0.80 0.51 0.10 0.03

2025 16.11 28.10 46.40 73.15 116.69 184.65 9.09 3.96 1.14 0.73 0.15 0.05

2030 21.80 38.04 62.64 98.75 157.94 249.92 12.28 5.35 1.54 0.98 0.20 0.06

2035 28.46 49.66 81.93 129.16 206.19 326.27 16.05 6.99 2.01 1.28 0.26 0.08

Table 43: PM2.5 Predicted Concentrations (µg/m3) along the Proposed Road

Year

PM2.5 Concentration (µg/m3)

Distance from the centre line of the road, m. (Left side)

Distance from the centre line of the road, m. (Right side)

-500 -200 -100 -50 -20 -10 10 20 50 100 200 500

2020 18.71 19.13 19.91 21.03 22.48 24.34 18.20 18.10 18.05 18.04 18.03 18.03

2025 18.95 19.52 20.56 22.07 24.05 26.57 18.27 18.13 18.06 18.05 18.03 18.03

2030 19.22 19.96 21.28 23.22 25.81 29.12 18.34 18.62 18.07 18.05 18.03 18.03

2035 19.53 20.46 22.13 24.58 27.83 32.01 18.42 18.20 18.08 18.06 18.03 18.03

Table 44: PM10 Predicted Concentrations (µg/m3) along the Proposed Road

Year

PM10 Concentration (µg/m3)

Distance from the centre line of the road, m. (Left side)

Distance from the centre line of the road, m. (Right side)

-200 -100 -50 -20 -10 10 20 50 100 200

2020 45.67 46.09 46.87 47.99 49.44 51.28 45.16 45.06 45.01 45.00 44.99 44.99

2025 45.91 46.48 47.52 49.03 51.01 53.53 45.23 45.09 45.02 45.01 44.99 44.99

119

2030 46.18 46.92 48.24 50.18 52.77 56.08 45.30 45.12 45.03 45.01 44.99 44.99

2035 46.49 47.42 49.09 51.54 54.79 58.97 45.38 45.16 45.04 45.02 44.99 44.99

Table 45: NOx Predicted Concentrations (µg/m3) along the Proposed Road

Year

NOx Concentration (µg/m3)

Distance from the centre line of the road, m. (Left side)

Distance from the centre line of the road, m. (Right side)

-500 -200 -100 -50 -20 -10 10 20 50 100 200 500

2020 7.51 12.12 20.51 32.71 48.82 69.44 1.95 0.85 0.24 0.16 0.03 0.01

2025 10.44 16.86 28.51 45.46 67.92 96.66 2.71 1.18 0.34 0.22 0.04 0.01

2030 13.88 22.41 37.90 60.45 90.29 128.49 3.60 1.57 0.45 0.29 0.06 0.02

2035 17.92 28.94 48.99 78.08 116.57 165.57 4.65 2.02 0.58 0.37 0.07 0.02

Table 46: SO2 Predicted Concentrations (µg/m3) along the Proposed Road*

Year

SO2 Concentration (µg/m3)

Distance from the centre line of the road, m. (Left side)

Distance from the centre line of the road, m. (Right side)

-500 -200 -100 -50 -20 -10 10 20 50 100 200 500

2020 15.12 15.22 15.39 15.64 15.96 16.37 15.01 14.99 14.97 14.97 14.97 14.97

2035 15.43 15.71 16.22 16.97 17.93 19.16 15.09 15.02 14.98 14.98 14.97 14.97

*Note- SO2 predictions’ not done for 2025 and 2030 as there is very minor change in SO2 concentration (less than 2.0

µg/m3 ) from year 2020 to 2035. This can be seen from the results of Air modelling given in Appendix-7.

120

242. Green House Gases Emissions: Upgrading and strengthening the surface condition of existing SH-115 road under project will bring about a change in vehicle operation speeds, traffic composition on the highway. Such changes with respect to present conditions will have an impact on emission levels of the gases emitted by vehicles travelling along the section of SH-115

highway. Most common types of vehicles that would move on the particular section are motor cycles, three wheelers, cars, vans, buses, light and heavy commercial vehicles. Thus, emission

of Carbon Dioxide (CO2) from motorized vehicles which is a GHG needs to be analyzed to

evaluate the overall contribution of this investment program in terms of the change in CO2 emissions.

243. Evaluation Knowledge Brief has developed a set of spreadsheet-based models to evaluate

the CO2 impacts of rural roads. These Transport Emissions Evaluation Model for projects (TEEMP)

consider passenger and freight travel activity, the shares of trips by different modes and vehicle types (structure), fuel CO2 efficiency (intensity), and fuel type, validated by more detailed emission

factor models. The models directly estimate CO2 emissions for a business-as-usual case (a no-action alternative) vs. alternative including improvement to road pavement and calculate scenario differences.

244. The TEEMP model for rural/urban roads was used for the analysis with using default parameters for base fuel consumption, emission factor and upstream emission percentage. Occupancy-loading, average trip lengths of each type of vehicle, vehicle type growth and roughness factors (before and after improvements) were fed to the model based on the details of traffic and economic analysis for the two sections of SH-115 road. The model was run separately for the road sections. The traffic data used in the model is given in Table-38.

245. Model output includes CO2 emissions at Business as Usual (BAU) or without project; with project (i.e. with improvements) and with induced traffic; and with project and without induced traffic.

Parameters Emission of CO2 in Ton/km/year

BAU 525.34

Project with induced traffic 516.75

Project without induced traffic 516.75

Net reduction in CO2 emission 8.58

246. As indicated in the model output as summarized above, the proposed improvement to existing highway pavements will bring a reduction in CO2 emission even with a growth of traffic. However, this analysis is based on the assumption that the roughness of improved highway pavement surface will be maintained during the project life. Therefore, it is important that the road maintenance program is maintained throughout the project life. The total length of SH-115 to be improved is 109.273 km. Based on the net change in CO2 emissions or CO2 savings of the sections is 8.58 Tons/km/year, and thus the proposed investment program of SH-115 and ECR link as will save emissions of 944.84 Tons CO2/year.

247. Mitigation Measures: It has been observed from the model output that when the traffic volume increases, the concentration of air pollutants also increases correspondingly. However, the maximum predicted pollutant concentrations of PM2.5, PM10, and SO2 over the existing ambient air quality are found to be within the National Ambient Air Quality Standards of CPCB, except CO

121

and NOx but higher than the IFC EHS guideline limits for PM2.5, PM10 and NOx parameters. Increases from the baseline values are not significant based on the modeling. Since the project will improve the road conditions, it is not expected to cause significant increases in existing concentrations of pollutants. Majority of these will be contributed by vehicle emissions and reanimation of dust from roads. Proper and regular maintenance of roads will decrease these indirect impacts. The details of air quality modelling and pollutant dispersion along the alignment is given in Appendix 7.

248. Residual Impact: The project is projected to have minor residual impact on the air quality. It is expected that with proper and regular road maintenance, the road improvement will not have significant negative residual and cumulative impacts on road quality.

2. Surface water quality and quantity

Design and pre-construction stage – moderate negative impact

249. During preliminary planning and design of this project, the Consultant has taken into account the need for:

• reduced incidence of embankment erosion due to inadequate drainage; • providing adequate culverts/drains; • providing side-drainage structures.

250. Impact: Given the presence of river, canal, backwater and ponds along the project road and some of the seasonal stream crossing the project road, improvement of road may result in disruptions to the natural hydrology and water mismanagement and lead to further problems of soil erosion.

251. Mitigation Measures: The natural courses of rivers/streams will be maintained. Appropriate temporary diversions of streams will be made and brought back to their natural course as soon works are completed in that section. No disposal of construction debris in streams and rivers is allowed. Regarding design, the following should be followed:

• drainage structures are properly designed to accommodate forecast discharges; • side drain waters must be discharged at every available stream crossing to minimize

volume and prevent erosion at discharge point; • provide lined drainage structures; • where an increased discharge of surface water endangers the stability of the water

outlet, erosion protection measures such as bioengineering measures, ripraps, and check dams are incorporated; and

• in areas with high water tables, seepage may occur, and side drains and up-slope catch drains must always be lined to avoid percolation.

252. Residual impact: With the proper application of the proposed mitigation measures residual impacts on the surface water quality and quantity will be minimal.

Construction stage - moderate negative impact

122

253. Impact: Minor impacts on water resources are expected during the construction phase construction site runoff, wastewater discharge, etc. The rehabilitation of existing bridges may also cause soil erosion and turbidity in downstream water bodies.

254. The likely impacts of surface water movements are changes in the natural drainage systems, downstream scour, and erosion due to constriction in flows. If suspended solid concentrations in the water are affected, this could also affect aquatic river ecology. However, these impacts are expected to be minor as there are no perennial rivers along the proposed road alignment and construction will take place during dry period.

255. Mitigation Measures: To mitigate this, river-bank slope stabilities will be monitored and, if necessary, appropriate remedial measures applied throughout the construction period. Construction work at bridges during rainy season will be minimized to avoid erosion and sedimentation.

256. To mitigate these impacts the following measures should be implemented:

• maintain adequate vegetative cover on unpaved shoulders of the road; • maintain the natural course of water bodies (as much as possible) and • no throwing of C&D spoils into water bodies; • chemicals and oils are stored in secure, impermeable containers, and disposed of

well away from surface waters In an environmentally sound manner while adhering to applicable laws and regulations;

• no vehicle repair/cleaning activity is allowed within 300m of water bodies/drains; • construction camps are equipped with sanitary latrines (septic tanks); • construction establishments such as construction camps, labor camps,

asphalt/concrete mixing stations, stone crushing units should be located away from the water bodies. Domestic and sewage wastes from labor camps shall be treated with a sewage treatment system (septic tanks) to comply with the standards specified by CPCB and WBG before disposal. Testing of effluent has to be done in accordance with the rules and regulations of CPCB and SCPB;

• drainage structures are properly designed to accommodate forecast discharges; • side drain waters must be discharged at every available stream crossing to minimize

volume and prevent erosion at discharge point; • provide lined drainage structures; • where an increased discharge of surface water endangers the stability of the water

outlet, erosion protection measures such as bioengineering measures, ripraps, and check dams are incorporated;

• in areas with high water tables, seepage may occur, and side drains and up-slope catch drains must always be lined to avoid percolation; and

• all debris and vegetation, clogging culverts are regularly cleared.

257. Residual Impact: With the proper application of the proposed mitigation measures a residual impact on the surface water quality and quantity during construction will be minimal to moderate.

Operation stage – neutral impact

258. Once construction is finished no impact on the surface water quality and quantity is expected. In order to check if unexpected erosion and siltation (including accidental spillage of

123

pollutants from vehicles) in major water bodies is happening periodic surveillance will be conducted and mitigation measures will be taken, if necessary.

3. Groundwater quality and quantity

Design and pre-construction stage – neutral impact

259. No impacts are envisaged during design and preconstruction stage.

Construction stage - minor negative impact

260. Impact: The quality of the groundwater could be impacted at sites where process water or wastewater is generated and disposed of in an improper manner. This could be the case at labor camps, at temporary construction sites and at fuel stations. Quantity may be affected if construction water requirement is obtained from groundwater sources.

261. Mitigation Measures: Sewage generated at labour camps will be disposed in septic tanks which may be emptied periodically through local sewage disposal system. Latrines should be located away and downstream of any source for drinking water in order to prevent accidental contamination of drinking water sources. All latrines will be connected with a septic tank to ensure sewage is not released into the environment. Locations for fueling and/or maintenance should be fitted with impervious flooring and a drainage system connected to an oil/water separator and settling tank to treat sewage before being discharged. Fuel tanks shall be placed in a catch basin large enough to hold the entire contents of the tank and an additional ten percent. More detail on the layout and requirements for labour camps and construction sites can be found in Appendix 8: Plant Management and Appendix 9: Camp Site Management.

262. Construction water requirement (avg. 500 KLD and peak 800 KLD) will be met through CGWB approved ground water source. Domestic water requirement (40 KLD) for workers will also be met mainly through approved sources only. Necessary permits will be obtained prior to water abstraction and only when there is no other viable option so as not to compete with local domestic demand. It is envisaged that groundwater will be utilized for camp domestic water requirement if there are no other viable sources or if the safety of workers will be at risk. Water abstraction will be included in monitoring.

263. Residual Impact: With the proper application of the proposed mitigation measures a residual impact on the groundwater quality will be minimal during construction.

Operation stage – neutral impact

264. During the operation stage of the project no impacts on groundwater quality or quantity are foreseen.

4. Land degradation and pollution

Design and pre-construction stage – minor negative impact

265. Impact: Construction activities of the project road will bring permanent changes in the local-level topography and appearance of the project site. There will be a change in aesthetic beauty of the project area mainly due to the earthwork.

124

266. The use of proper sources for stone and aggregates has become a major issue in most of the region. Historically, stone has been collected from the roadside or from shallow surface workings. Small quarries on steep slopes are often enlarged by blasting or excavation at the base. This is dangerous and can cause slope failures. Roadside stone collection continues in some districts despite its proven negative impacts on road safety and stability.

267. Sand and gravel are often obtained from river deposits. Jurisdiction over stone and aggregates is shared between the Geological Survey of India and the State Forest Department. The Geological Survey of India issues licenses for major mineral developments while the for stone quarrying and for sand and gravel extraction. This is largely because these are mostly found on forest lands. Roadside quarrying is officially discouraged, but unofficially continues, invariably by petty contractors.

268. The engineering team as part of material survey has identified and recommended sources of the construction materials. Details of these sources are provided in Volume 1 (Material survey chapter) of Detailed Project Report. As a prior requirement of project, every new quarry and borrow area should also be subjected to a site-specific environmental investigation work according to an approved plan; and should be left in a safe condition or restored to a productive land use. Subject to these conditions, obtaining construction materials for projects will not cause unacceptable impacts.

269. Mitigation Measures: During preliminary planning and design of this project, the Consultant has taken into account the need for:

• optimization of the center line so that embankment raised on both side; • temporary and permanent drainage systems to minimize soil erosion; • optimum siting and control of quarries; • mechanized construction methods.

270. The following should be considered during finalization of detailed engineering design:

• Minimize permanent and temporary land take for development • Optimize balance between cut and fill and avoid deep cuts and high embankments

to minimize earthworks • Maximize reuse of spoils and old asphalt paving material within the construction • Agree on spoils disposal sites, management and rehabilitation plan with relevant

local agencies • Specify vegetation that serves specific bioengineering functions.

271. Adequate earth material is available from barren land in the vicinity. About 1,026,200 cum of borrow earth, 86,000 cum of sand and 130,000 cum of aggregates are estimated to be required for the constructional activities of road section and will be mostly sourced from licensed quarries available locally. Tentatively it is proposed that the aggregates and boulders will be sources from previously approved quarry area located near to the project road. Earth cut materials will be maximized for reuse in backfilling on the same rural road to minimize the quantities of borrow materials and spoil disposal. Borrow earth material will still be required but this will be taken from quarries or riverbeds after prior permission from competent authority.

272. There is a need to establish construction camps and related facilities, such as borrow pits and quarries. These must be located in environmentally sound and socially safe areas. It is

125

expected that construction materials for the road works will be mined mostly from approved quarries. The following criteria are applied for locating the borrow areas:

• If new borrow areas are opened for the project, they should obtain necessary clearances;

• borrow areas are not established in ecologically sensitive areas; • villagers are consulted in regard to the design and location of all borrow areas –

these should ensure the safety of local communities and, if possible, should incorporate beneficial post construction features for the villages;

• located away from the road as well as the road, so as to minimize visual and slope stability impacts;

• construction facilities such as temporary workers camp, hot mix plants, and concrete batching plant and stone crushers will not be established in reserve / protected forests. Local forest department / village panchayat committees should be consulted before locating these temporary project facilities;

• construction camps for labourers should be located at a suitable distance away from settlements in accordance with relevant national or state regulations such as the State Pollution Control Board and in a manner to avoid stressing local resources (water, electricity etc.) and away from forest/protected areas as per recommendations of local forest department;

• living accommodation and ancillary facilities should be erected and maintained to standards and scales approved by the CSC; and

• toilets and urinals should be provided in accessible places away from the asphalt plant and mixing yard.

273. Residual Impact: With the proper implementation of the proposed mitigation measures and low likelihood of the project requiring opening of new quarry sites the project is not expected to have a significant residual impact on the soil and local topography.

Construction stage - moderate negative impact

274. Impact: There may be permanent changes in the landscape. Disposal of excavated soils and debris at improper locations such as low laying area will make the area look untidy and unattractive. Disposal of waste and litter at improper locations and deforestation for firewood will make the area look dirty and unattractive.

275. During the improvement works for the road section, the cutting of trees, stone quarrying, and construction of structures, the micro-level topography may change. With proper planning, these topographical impacts can be kept within acceptable limits and sometimes even used to enhance local aesthetics. Any negative impacts on topography (existing or new), particularly soil erosion due to a lack of drainage facilities, will be minimized with the provision of proper drainage facilities such as culverts etc. The overall impact on topography is, therefore, anticipated to be insignificant.

276. The terrain and geological conditions of area is plain, hence the interaction between proposed road features and existing land features will not reveal/result in significant land instabilities.

277. Given the existence of low gradient slope and proper drainage in almost entire project area, it is inevitable that the project site will face problems of erosion. Unstable, uncompacted

126

road embankment materials and exposed material can result to soil erosion, clogging of side drains and the spill-over of rainwater runoff onto the road surface. These problems can be mitigated by maintaining the batter gradients as specified in the MORTH guidelines. The existing vegetation on embankment slopes the immediate area of construction must remain undisturbed during construction and/or upgrading. Grass seeding will be used to prevent barren embankment and to stop soil erosion. Support structures will be installed where slope failures are anticipated or may have occurred previously.

278. Construction work in the project road section will be virtually through plain terrain and stable slopes. Much of areas in this section are surrounded by agriculture fields with adequate natural drainage of storm, resulting in stable substrates.

279. The project will require large amounts of bitumen or bitumen emulsion usually stored in drums. These empty bitumen drums are generally recycled as steel sheeting or used in road construction as parapets or for riverbank stabilization. When supplied and used in this manner, bitumen, if not containing Polycyclic Aromatic Hydrocarbons (PAH), is not regarded as a significant environmental hazard.

280. The project will require the import, transport, and use of fuel and oils. Minor diesel spills are common in region, especially around fuel stations.

281. Mitigation Measures: During the construction phase the existing vegetation including shrubs and grasses along the road (except within the strip directly under embankments or cuttings) should be properly maintained. Sites for quarrying, borrowing and disposal of spoils are to be confirmed according to the applicable laws and regulations in the state and the practices followed in recent/ongoing internationally funded road projects. Major excavation and earthworks should only be undertaken during the dry season.

282. Quarry and borrow pits may be filled with rejected construction waste such as top soil etc. and afterwards should be given a vegetative cover. If this is not possible, then the excavated slopes will be filled in such a way that they resemble an original ground surface.

283. Mitigation measures for quarries are:

• aggregates will be first sourced from licensed quarry sites (which are in operation) that comply with environmental and other applicable regulations;

• quarries must use controlled and environmentally friendly quarrying techniques in order to minimize erosions and landslides (Appendix 12 provides guidelines for quarry management);

• occupational safety procedures/practices for the work force will be adhered to in all quarries;

• quarry and crushing units will be provided with adequate dust suppression measures; and

• regular monitoring of the quarries by concerned authorities to ensure compliance with environmental management and monitoring measures.

284. Mitigation measures for borrow areas are:

• prior approval will be obtained from concerned authorities and all local environmental regulations be complied with;

127

• within all identified borrow areas, the actual extent of area to be excavated will be demarcated with signs and access to the operational area controlled;

• borrow pit plant and machinery will conform to CPCB and IFC EHS noise emission regulations;

• protective gear will be provided to the workforce exposed to noise levels beyond threshold limits and there should be proper rotation of such personnel; and

• all operation areas will be water sprinkled to control dust levels to national ambient air quality standards, and

• borrow areas are provided with gentle side slope that are connected to the nearest drainage channel to avoid the formation of cess pools during the rainy season.

285. Other mitigation measures to be taken during the construction phase are:

• Any temporary lands required for labour camps or any other sites required for the project shall be transferred back to the owner after the land has been restored to its original state before the completion of construction works. Contractor has to collect baseline data on the quality of ambient air, ambient noise, soil, surface water and groundwater before establishing and after decommissioning the camps or sites.

• excavated material shall be stockpiled and covered in such a way the soil will not erode away and should be used to widen the road or disposed of at proper disposal sites following spoil disposal management guidelines (Appendix 10);

• Removal of bituminous wastes from existing roads should not be disposed of in nearby water bodies, open spaces and parks and wastes should not be left unmanaged on the road sides. Bituminous material should be examined for PAH to establish if it can be recycled /reused for road construction. If not, the bitumen shall be treated as hazardous waste and disposed of in pre-identified and approved disposal sites”

• Any construction and demolition waste generated during the construction phase should be managed in accordance with the C&D Waste Management Rules, 2016. As far as possible, demolition and construction waste should be segregated and recycled. The unserviceable waste left after recycling should be dumped in pre-identified and approved pits as per Construction & Demolition Waste Management Rules. All required permissions shall be obtained from the concerned authorities before disposal of the debris”

• cut slopes should be re-vegetated immediately after widening activities; • cut material should be disposed of in suitable depressions.

286. To mitigate the impacts of possible fuel spills the following measures will be applied:

• secondary containment around fuel tanks large enough to hold the entire contents of the tank and an additional ten percent and at fueling stations will be built;

• oil and fuel spills, and other runoff from contaminated areas will be controlled; and • equipment and fuel depots will be placed in safe zones away from drinking water

sources and riverbanks;

287. Appendix -8 to Appendix -12 of this IEE Report presents good environmental management practices and guide documents in the following aspects of road construction:

• Plant Management – Appendix 8;

128

• Camp Site Management – Appendix 9; • Debris and Spil Disposal Management – Appendix 10; • Borrow Area Management – Appendix 11; • Quarry Area Management – Appendix 12.

288. Residual Impact: With the proper application of the proposed mitigation measures the construction phase should not have any significant residual impact (except minor impacts for the initial years) on the soil or the local topography.

Operation stage – positive impact

289. Repairs to culverts and new drainage work will eliminate/reduce the soil erosion problems presently caused by poor cross drainage. The situation will remain good because this road passes through an area that is largely agriculture fields and trees and plants have the capacity to stabilize the soil and prevent soil erosion.

E. Impacts on Biological environment

1. Trees and vegetation

Design and pre-construction stage – moderate negative impact

290. Impact: The improvement work will be kept limited to existing ROW with minimal additional land acquisition. Nonetheless, land clearing will involve cutting of trees and horticulture shrubs within the ROW along the road.. The improvement of the proposed road is largely confined on the existing alignment. However, improvements to the geometry may involve excavation and filling and the need to clear vegetation.

291. Mitigation Measures: To minimize loss of trees, the following mitigation measures have been adopted during the detailed design and construction stage of the project:

• widening proposal considered option with minimal tree cutting; • adopting Environmentally Friendly Road Construction (EFRC) methods; • Budget provisions for following the mandatory afforestation program which requires

planting native trees (in consultation with forest people) at the rate of 1:10 for trees cut and improving vegetation cover in the project area.

• The plantation under compensatory afforestation plan will be scheduled within 15 months of the construction works, as preparation of seedlings in the approved nursery will start with commencement of construction work for the project road.

292. Residual Impact: As a result of the proposed afforestation program and additional improvement activities it is expected that there will be a net gain of trees and vegetation under the project.

Construction stage – moderate negative impact

293. Impact: Removal of trees for road widening etc. will result in temporary loss of habitat and associated biodiversity. The project will not require diversion of any forest land for widening of the road. Only vegetation within ROW will be cleared after approval from revenue department.

129

294. Another impact from road construction activities and deriving from the vehicle movement, quarrying, preparation and transfer of material and other earthwork is the accumulation of dust on the surrounding vegetation. This leads to deterioration of the vegetative health, which in turn will affect the ecology as well as the aesthetic beauty of the area. Induced impacts may also result from the following:

• increased tree harvesting for firewood, construction timber, forage, medicinal plants, and other products;

• increased earth and rock extraction; • construction crew demands for wood as a fuel and for building materials.

295. Invasive Species: Soil brought into the project area from outside may contain seeds of alien invasive species. Also, the construction machinery and vehicles can accidentally introduce seeds of such plants if used without proper cleaning. This will negatively affect both the natural and manmade habitats. Securing soil from locations close to the project area will reduce the chances of transporting any seeds of alien invasive species to the project area.

296. Mitigation measures. Compensatory afforestation plan will be developed in consultation with local forest department. In detail, the recommended mitigation measures include:

• Compensatory afforestation plans • Cut only trees which are necessary. Ensure that the vegetation is cleared as per

terms and conditions of tree cutting permit • Compliance with guidelines issued by the Indian Road Congress • all wood building material for workers’ housing should be brought from outside the

project area; • workers should be supplied with non-wood fuels such as kerosene or liquefied

petroleum gas for the duration of the contract; • Prohibit collection, sale or purchase of timber/firewood by staff and contractors,

with heavy penalties applied • all contract equipment and plants should be cleaned to the satisfaction of the CSC

in charge prior to their relocation to project sites; • during site clearance, care should be taken to ensure that the minimum area of

vegetation area is affected; and • water sprinkling of trucks used as construction vehicles should be properly and

regularly undertaken, so that dust deposition problem on vegetation are minimized. Cleaning/washing of construction vehicles arriving in the project areaSecuring soil from locations close to the project area will reduce the chances of transporting any seeds of alien invasive species to the project area.

297. Residual Impact: With the implementation of the measures above, minimal residual impacts on trees and vegetation is expected.

Operation stage – positive impact

298. Impact: A net gain of good vegetation cover is expected as a result of the mandatory compensatory afforestation program. It is expected that vegetation such as shrubs, herbs and bushes will reestablish themselves within one to two years after project construction. However, the trees will take longer 5-10 years to attain substantial growth. Hence, there will be no residual

130

impacts in relation to smaller vegetation species such as shrubs, bushes etc. Residual impacts in relation to mature trees will be mitigated eventually after 5-10 years after project construction.

Operation stage – positive impact

2. Ecologically important areas

Design and pre-construction stage – moderate negative impact

299. Impact: The project road section passes though plain terrain with agriculture areas residential areas in between. Road section is not passing through any forest and protected area. Ecologically important areas within the project area includes water bodies. There may also be a low risk of disturbance to wildlife from traffic noise of the project road.

300. Mitigation Measures: Measures to protect surface water resources such as appropriate drainage design to accommodate predicted water volume and minimize impacts on existing waterways will help address these impacts on ecologically important areas and wildlife. Undertaking pre-construction survey along the alignment to identify the section required for protection measures by the EPC contractor will further address fragmentation effects of the road improvement.

301. Residual Impact: If the above mitigation measures get implemented as planned, minimal residual impacts are expected due to project design.

302. Construction stage - moderate negative impact

303. Impact: Temporary sedimentation and water quality deterioration is expected during the construction stage. Increase in turbidity due to erosion will lead to reduction of light penetration and make it an undesirable place for aquatic fauna and flora. Further due to the reduced light penetration to the water body, the primary productivity of the biota in the water body will be reduced resulting in increased mortality. The impact is insignificant since construction of road section in the area will be mostly during summer and short-term only. Siltation will be avoided by measures suggested above in impact on surface water resource section. Construction crew demands for food and recreational hunting and fishing may also result to poaching during construction.

304. Impacts on Protected Area: The project road does not pass through any reserved/protected area. There is no species in the area qualifying the project area as Critical Habitat. The protected area is a natural habitat for wildlife having core zone deep inside the protected fragmented by physical barriers, restricting wildlife movement towards road alignment.

305. Mitigation Measures: To minimize negative impacts on ecologically important features in the project area the following should be followed:

• If any wild animal (except birds) come within the vicinity of 100m from the construction site, construction works must immediately stop and resume only after the wild animals have moved away.

• Employment agreements should specify heavy penalties for illegal hunting, fishing, trapping and wildlife trading (as per Wildlife Act 1972)– all other ancillary works should also agree not to participate in such activities.

• Strict anti-poaching surveillance measures will be implemented, especially during project construction phase.

131

• Use only existing licensed quarries for sourcing aggregates. Further, any newly-established quarries – whether inside or outside of rivers and streams – have potential to clear Natural Habitat. These risks can be simply and effectively avoided by sourcing of all aggregates only from existing licensed quarries outside of rivers and streams.

• Avoid borrow pits in areas of Natural Habitat (Water reservoir/Stream) and within 200 m of waterways. No borrow pits will be allowed at least 200 m next to waterways. This will help avoid risks of runoff and sedimentation impacting aquatic Habitat. Further, to avoid additional Project impacts on Natural Habitat, no borrow pits will be established in areas of Natural Habitat.

• Installation of speed limits caution boards and speed breakers at identified location, informatory boards for road users.

306. Residual Impact: Considering the above measures, the project road meets the requirements of para 28 (page 35) of the SPS – no measurable adverse impacts, no reduction in population of threatened species etc. Hence, the project works will be in compliance with the SPS and residual impacts on wildlife are expected to be insignificant.

Operation stage – positive impact

307. If the habitat improvement activities described above are implemented as planned an overall positive impact of more sustainable use of natural resources and habitat improvementis expected..

F. Impacts on Social Environment

308. The sensitive location such as places of worship, school, college and hospital along project road within 100 meters from the edge of the existing road has been identified as given in Table 30. These structures are kept unaffected by the proposed improvement proposal. Short term impacts during the construction stage are expected. Measures such as timely scheduling of construction activities in these areas, provision of sign boards, appropriate barriers such as planting trees and / or raised boundary walls are adopted to minimize impacts.

1. Private land and buildings

Design and pre-construction stage – moderate negative impact

309. Impact: There will be moderate impacts due to acquisition of 41.9833 ha private land acquisition as the proposed widening will be accommodated within existing ROW. Community impacts are mostly due to the resettlement of people due to widening of the project road to 2 lanes.

310. Resettlement plan for the project road has been prepared for 567 private structures.

311. Mitigation Measures: A resettlement plan is prepared to address this issue. The affected people will be compensated and rehabilitated as per the provisions of the Resettlement Plan.

312. Residual Impact: Since any foreseen impact on private land and buildings will be addressed in a separate resettlement plan no residual impacts are envisaged.

Construction stage – minor negative impact

132

313. Impact: At certain locations on the road, particularly at bridge/culvert sites, traffic will be temporarily diverted from the existing carriageway while construction is in progress and temporary traffic diversions will be managed within the ROW. In other instances, traffic may have to be diverted across adjacent private land.

314. Mitigation Measures: In case private land is temporarily used during construction compensation will be paid for any loss of crops or the replacement of damaged structures. Most construction will be undertaken during the dry season when few crops are planted. Losses should be minimized during construction. After completion of the construction works the used land will be reinstated to the state it had before commencement of the works. Access to adjacent properties and agricultural land will be maintained, as necessary. Any damage to areas and infrastructure outside the agreed work sites (Corridor of Impact assessed in project RP) will be restored to pre-construction conditions and will be subject to compensation at contractor cost and through written agreement with the land owner, as applicable.

315. Residual Impact: With adequate compensation for any damages resulting from using private land during construction no residual impacts are to be expected from construction.

Operation stage – neutral impact

316. The likely impacts on land use and settlement patterns are limited. Improved access will lead to increased migration, but this will occur gradually and over a prolonged period. There will be time for expansion of residential areas to be established. However, there will be a need to control ribbon development.

2. Public infrastructure and utility structures

Design and pre-construction stage – minor negative impact

317. Impact: On the project road, utilities interfere with the ROW at few locations that will have to be shifted / removed prior to construction.

318. Mitigation Measures: Before construction commences a detailed survey has to be carried out in order to list all utilities that will interfere with the road works. These utilities will have to be shifted before the works in close cooperation with the respective owners of the utilities.

319. Residual Impact: With proper preparation no residual impacts are to be expected.

Construction stage –minor negative impact

320. Impact: Traffic may experience minor delays when diverted around active construction areas but will be more severely hampered at the locations where temporary road closures are necessary. There are also likely impacts on communities from the construction activities.

321. Mitigation Measures: Contractor will prepare and implement traffic management plan. Key hazard points will have proper signs indicating the nature of the problem envisaged. Road closures / diversions must comply with the guidelines laid out in IRC:SP:55.2014: Guidelines on Traffic Management in work zones. Contractor will ensure that information on the timing of construction works and notifications of road closure (if any) is provided via the local media (radio, TV, newspaper etc.) or through the local community heads.

133

322. Residual Impact: With the proper implementation of the proposed mitigation measures the construction of the project is not expected to have a residual impact on public utilities. However some temporary negative impact on traffic flow will be unavoidable.

Operation stage – neutral impact

323. During the operation stage of the project no impact on public infrastructure and utilities is expected.

3. Noise and disturbance

Design and pre-construction stage – moderate negative impact

324. Impact: The ambient noise level throughout the road section exceeds the standards for residential areas except at some locations. During the construction period, noise will be generated from the operation of heavy machinery, the haulage of construction materials to the construction yard and the general activities at the yard itself. Concrete mixing and material movements will be the primary noise generating activities and will be uniformly distributed over the entire construction period. These construction activities are expected to produce noise levels in the range of 80-95 dB(A) at a distance of about 5m from the source. Cost of standard solid (concrete) noise barriers have been included in the bid documents for sensitive receptors identified during detailed project report preparation.

325. The noise generating equipment used in construction activities is also regulated under Noise Pollution (Regulation and Control) Rules 2000, which may cause concern among local villagers. The range of typical noise levels in relation to distance from a construction site is shown in Table 47.

Table 47: Construction Noise/Distance Relationship

Distance from Construction Site (m) Range of typical Noise Level dB(A)

8 82-102

15 75-95

30 69-89

61 63-83

91 59-79

122 57-77

152 55-75

305 49-69

Source: Department of Transportation, State of Wisconsin (USA)

326. Noise and vibration from piling (if used at bridge locations) will be unavoidable, but the impact will only be temporary and affect people living or working near piling locations, if involved at location of bridge constructions. The impact and sources of noise are summarized in Table 48.

Table 48: Likely Impact on Noise Quality in the Vicinity of Project Area

Impact Source

Increased noise levels • Mobilization of heavy construction machinery;

134

causing discomfort to

local residents, workers

and local fauna

• Accelerations/ decelerations/ gear changes – though the extent of impact will depend on the level of congestion and smoothness of the road surface;

• Excavation work for foundations and grading; • Construction of structures and other facilities; • Crushing plants, asphalt production plants; and loading,

transportation and unloading of construction materials.

327. Typical noise levels associated with various construction activities and equipment are presented in Table 49.

Table 49: Typical Noise Levels of Principal Construction Equipment (Noise Level in dB (A) at 50 Feet)

Clearing Structure Construction

Bulldozer 80 Crane 75-77

Front end loader 72-84 Welding generator 71-82

Jack hammer 81-98 Concrete mixer 74-88

Crane with ball 75-87 Concrete pump 81-84

Concrete vibrator 76

Excavation and Earth Moving Air compressor 74-87

Bulldozer 80 Pneumatic tools 81-98

Backhoe 72-93 Bulldozer 80

Front end loader 72-84 Cement and dump trucks 83-94

Dump truck 83-94 Front end loader 72-84

Jack hammer 81-98 Dump truck 83-94

Scraper 80-93 Paver 86-88

Grading and Compaction Landscaping and clean-up

Grader 80-93 Bulldozer 80

Roller 73-75 Backhoe 72-93

Truck 83-94

Paving Front and end loader 72-84

Paver 86-88 Dump truck 83-94

Truck 83-94 Paver 86-88

Tamper 74-77 Dump truck 83-94

Source: U.S. Environmental Protection Agency, noise from Construction Equipment and Operations. Building Equipment and Home Appliance. NJID. 300.1.December 31, 1971

328. Mitigation Measures: By using noise reduction equipment, the hindrance from construction equipment can be minimized. By planning noise generating activities during daytime only hindrance to local residents can be minimized. At sensitive locations such as schools, colleges and hospitals along the project road noise barrier shall need to be provided

329. Residual Impact: With the proper implementation of mitigation measures the project design is not expected to have minimal residual impact.

135

Construction stage – moderate negative impact

330. Impact: The noise levels indicated for various construction activities/equipment, while far exceeding permissible standards of CPCB and IFC EHS for residential areas, will occur only intermittently. Still, these extremely high sound levels present real risk to the health of workers on- site.

331. The construction activities are introduced in Noise Pollution Rules, 2000 with its amendment in 2017. The maximum limit for noise near the construction site is 75 dB (A) Leg (5 min) in industrial areas and to 65 dB (A) Leg (5 min) in residential and other areas.

332. There are total 108 sensitive receptors identified within 50m from the centre line along the proposed project road as given in Table-50. The noise (existing noise and construction noise) levels during construction is predicted higher than the National Ambient Noise Standards (CPCB limits) and IFC EHS standards as ambient noise level eceeds the limits. As a best construction practices necessary mitigation measures are proposed during each phase of construction activity.

Table 50: List of Sensitive Recepator along the Project Road

S. No. Receptor Chainage Side Distance

from edge (m)

1 Saint Exupery matric high school, Cheyyur 0+850 LHS 8.7

2 Crescent metric high school, Cheyyur 1+682 RHS 6.2

3 School, Cheyyur 2+395 RHS 5.4

4 Girls Hostel, Cheyyur 2+395 LHS 5.6

5 Girls School, Cheyyur 2+395 LHS 5.2

6 Library, Cheyyur 2+400 RHS 6

7 Library, Cheyyur 2+500 RHS 14

8 Government high school, Cheyyur 2+700 LHS 12.3

9 School, Ki-karnai 12+125 LHS 9

10 School, Sarvanapakam 16+350 LHS 7

11 Bharathi mertriculation school, Chitamoor 16+600 RHS 6

12 Students Hostel, Chitamoor 16+750 RHS 12

13 Government High school, Chitamoor 16+850 LHS 11

14 Saint Anthony’s nursery & primary school, Mazhavangaranai, polambakkam

20+100 LHS 10

15 Adiparasathi college, Melmervathur 24+430 LHS 10.3

16 Alfredo Cuomo High secondary school, Sendivakkam

27+450 LHS 7.2

17 School, Ramapuram 31+115 RHS 8

18 School, Salavedu 35+482 LHS 8

19 Higher Secondary School, Salavedu 35+980 RHS 8

20 Sendhamizh matriculation school, Dip ammal nagar

39+007 LHS 6

21 School, Kallankutthu 42+650 LHS 7

136

S. No. Receptor Chainage Side Distance

from edge (m)

22 School, Kadaisikulam 45+722 RHS 6

23 SRI Polytechnic college & School, Kadaisikulam

47+150 RHS 11

24 Jain I.T.I., Ki nandimbadi 60+677 LHS 8

25 Thiruvallur college of engineering and technology, Thirumani

60+850 LHS 11

26 Arunachal city matriculation school, Thirumani

61+025 RHS 6

27 ITI, Kadambai 64+900 LHS 6

28 Library, Mazhayur 67+000 LHS 8

29 High School, Mazhayur 67+331 RHS 11

30 Suraj matric school &college, Melthangal 72+750 LHS 8

31 School, Nedungunam 76+086 LHS 11

32 Dr Maria ashoorf school of nursing, Chetpet 83+750 LHS 8

33 Mishery school, Tachambadi 90+775 LHS 6

34 Cluny matriculation high sec school, Devikapuram

93+100 LHS 6

35 Govt. high sec school, Devikapuram 93+220 RHS 8

36 Library, Modiyur 96+935 LHS 2

37 School, Pulivananthal 102+325 RHS 6

38 Gov high school, Kommananthal 102+800 RHS 6

39 Oxford college of engineering, Venmani 104+651 RHS 11

40 Oxford matric school, Venmani 105+375 LHS 11

41 Primary school, Venmani 106+065 RHS 11

42 Don Bosco ITI, Polur 106+750 RHS 11

43 Oxillium matriculation school, Polur 106+871 RHS 8

44 St Joseph RCM School, Polur 107+058 LHS 6

45 School, Polur 107+400 LHS 7

46 School, Mudaliyar kuppam 4+250 LHS 3.2

47 Vinayaka koil, Cheyyur 1+781 LHS 2.4

48 Vinayaka koil, Cheyyur 1+781 LHS 0.6

49 Vinayaka koil, Cheyyur 2+100 RHS 0.5

50 Ammaya temple, Cheyyur 2+303 LHS 2

51 Ammaya temple, Cheyyur 2+488 LHS 3.8

52 Ammaya temple, Cheyyur 2+810 RHS 0.7

53 Vinayaka koil, Onambakkam 7+750 RHS 3.9

54 Munishvaran temple, Munishvaran temple 10+244 RHS 4

55 Ammaya temple, Kat-devatur 10+600 LHS 0.5

56 Vigneshvara temple, Ki-karnai 12+107 LHS 1.5

137

S. No. Receptor Chainage Side Distance

from edge (m)

57 Vinayaka temple, Nallamur 13+100 LHS 0.4

58 Sai baba temple, Nallamur 14+900 LHS 5

59 Nagdevata temple, Perumbakkam 18+250 LHS 2

60 Kaliamman temple, Mazhavangaranai 20+450 RHS 2.1

61 Hanuman temple, Mazhavangaranai 20+480 RHS 1

62 Vinayaka koil, Sothupakkam 22+870 RHS 1.2

63 Vinayaka temple, Sothupakkam 22+449 RHS 0.5

64 Vinayaka koil, Sothupakkam 23+750 LHS 2

65 Ammaya temple, Sothupakkam 23+930 RHS 3

66 Church, Melmervathur 24+988 LHS 4.5

67 Nag koil, Ramapuram 31+050 LHS 1.5

68 Ammaya temple, Dipammal nagar 37+875 RHS 4

69 Kumar swami temple, Dipammal nagar 38+280 RHS 6

70 Ammaya temple, Kil kodangalore 38+480 RHS 2.6

71 Temple, Kallankutthu 42+680 LHS 2

72 Vinayaka temple, Kallankutthu 42+730 LHS 4.3

73 Navagraha temple, Kallankutthu 42+730 LHS 4

74 Church, Kallankutthu 42+900 RHS 3

75 Vinayaka koil, Kadaisikulam 46+036 RHS 6

76 Vinayaka koil, Annanagar Mambat 55+493 LHS 2

77 Ammaya temple, Arasur 57+675 RHS 3

78 Vinayaka koil, Kadambai 64+750 RHS 4

79 Ammaya temple, Kadambai 64+925 LHS 6

80 Perumal temple, Mazhayur 67+520 RHS 6

81 Perumal temple, Mazhayur 68+000 RHS 4

82 Vinayaka temple, Mazhayur 68+150 LHS 6

83 Munishvaran temple, Ettithangal 70+00 LHS 3

84 Vinayaka and navagraha koil, Chinakoipuliyur

72+05 RHS 5

85 Vinayaka temple, Nedungunam 76+115 RHS 3

86 Vinayaka temple, Nembedu 87+221 LHS 3

87 Amman koil, Nembedu 87+650 RHS 3

88 Vinayaka koil, Nembedu 87+750 RHS 0.5

90 Vinayaka koil, Ramapuram 89+525 LHS 4

91 Ammaya temple, Ramapuram 89+650 LHS 6

92 Dropadi amman temple, Devikapuram 93+250 LHS 0.5

138

S. No. Receptor Chainage Side Distance

from edge (m)

93 Temple, Modiyur 96+621 LHS 4

94 Rama temple, Modiyur 96+765 RHS 6

95 Siva temple, Modiyur 96+939 LHS 2

96 Ammaya temple, Modiyur 96+941 LHS 2

97 Church, Pulivananthal 100+810 RHS 2

98 Amman koil, Pulivananthal 101+175 LHS 3

99 Vinayaka temple, Pulivananthal 102+400 RHS 2

100 Ammaya temple, Kommananthal 102+691 RHS 3

101 Kumarswamy temple, Karaipondi 104+175 LHS 3

102 Church, Mudaliyar kuppam 4+170 RHS 1.3

103 Vetarnary hospital, Kil kodangalore 39+338 LHS 11

104 Govt. primary health centre gate, Mazhayur 65+800 LHS 11

105 St Thomas hospital & leprosy center, Chetpet 83+500 LHS 11

106 Vetarnary hospital, Tachambadi 91+700 LHS 8

107 Govt primary health care centre, Devikapuram

95+225 RHS 6

108 Govt. primary health care centre, Kommananthal

102+650 RHS 11

333. During construction, varying degree of noise impacts are likely to be felt by the communities of settlements along the project road i.e. Cheyyur Town, Mudaliyarkuppam, Nallur, Vallarai, Onampakkam, Kathudhevathur, Kepkoshikarai, Nallamur, Chittamur, Kolampakkam, Polambakkam, Mazhubkadu, Sothupakkam, Agili, Sandivakkam, Ramapuram, Salavedu, Mamandur, Kilkodungaloore/, Kallankuthu, Kaveripakkam, Maruthadu, Kodaisikulam, Biridhur, Chinnavaram, Vandavasi Town, Karajar Nagar, Mampattu, Ramraj Nagar, Kilnanthyambadi, Thirumarithanaga, Vadavarakkamba, Kilvelliyur, Periyar Nagar, Thirukarai, Mazhaiyur, Earthal, Ettithangal, Chinna, Arasumpattu, Nedugunam, Chetpet Town, Nirmala Nagar, Ideyankulam, Muthuswami, Nambedu, Pandiyapuram,Thachanbadi, Cheyarandal, Devikapuram, Modiyur, Mattaperiyar, Pulivardal, Komanandal, Karaipondi, Vermani, Polur Town and other small settlements along the project road. However, the above listed sensitive receptors will be especially impacted due to increase in noise levels as these would be near the construction site. Although temporary in nature, the construction noise will affect the most communities living close to the construction zone.

334. Mitigation Measures: In construction sites within 500 meters of a settlement, noisy operations should cease between 22:00 and 06:00 hrs. Regular maintenance of construction vehicles and machinery must also be undertaken to reduce noise.

335. Timely scheduling of construction activities, proper maintenance of construction machineries, use of personnel protective equipment, etc. will minimize these impacts.

336. Noise impacts are an unavoidable consequence of construction that should be mitigated by limiting the times of construction to daylight hours (8am - 5pm) in the vicinity of sensitive receptors. Further to minimize noise impacts near sensitive receptors (particularly schools),

139

operation of excavator and other heavy machineries will be carried out mostly during off-hours (10.00 am to 3.30 pm) and on holidays (Saturday and Sundays). The schedule will be prepared/modified in consultation with the community and relevant local authorities. Baseline noise will be established for all sensitive areas prior to construction and follow up noise monitoring will be carried out during the construction.

337. Implementation of suitable mitigation measures will reduce the construction noise to acceptable limits. Mitigation measures should include:

• Installations of noise barriers; • construction machinery should be located away from settlements. If noise levels

exceed the prescribed Leq, suitable mitigation measures like using additional silencers in noise generating equipment; erecting additional noise barriers and the use of proper PPEs shall be implemented;

• Construction machinery and equipment must properly maintained and designed with built-in silencers, mufflers and enclosures. This will reduce the noise by 5 to 10 dB(A);

• careful planning of machinery operation and the scheduling of such operations, no idling of machinery;

• controlled blasting should only be carried out with prior approval from the Engineer in charge;

• contractors should be required to fit noise shields on construction machinery and to provide earplugs to the operators of heavy machines.

338. Residual Impact: With the proper implementation of the proposed mitigation measures the project construction is not expected to have any significant residual impact.

Operation stage – moderate impact

339. The current low traffic flows along the project road are expected to increase because of improved economic activities associated with better access. The larger numbers of vehicles will be an additional source of noise and gaseous emissions.

340. Federal Highway Administration's Traffic Noise Model (FHWA TNM) helps for highway traffic noise prediction and analysis. Detailed analysis is presented in Appendix-13. TNM computes highway traffic noise at nearby receivers. As sources of noise, it includes noise emission levels for the following vehicle types:

• Automobiles: all vehicles with two axles and four tires -- primarily designed to carry nine or fewer people (passenger cars, vans) or cargo (vans, light trucks) -- generally with gross vehicle weight less than 4,500 kg (9,900 lb);

• Medium trucks: all cargo vehicles with two axles and six tires -- generally with gross vehicle weight between 4,500 kg (9,900 lb) and 12,000 kg (26,400 lb);

• Heavy trucks: all cargo vehicles with three or more axles -- generally with gross vehicle weight more than 12,000 kg (26,400 lb);

• Buses: all vehicles designed to carry more than nine passengers; and • Motorcycles: all vehicles with two or three tires and an open-air driver / passenger

compartment.

341. The procedure for prediction of noise levels involves the following steps:

140

a. Identification of various receivers, b. Determination of land uses and activities which may be affected by the noise

generated, c. Assemble input parameters, and d. Application of the model.

342. The description of the components to predict noise level are as follows:

• Receivers: TNM calculates the sound levels at the input receivers. • Land Uses: Land use along the road is obtained from the topographic drawings.

This information provides the range of shielding and absorption factors to be applied at the various receivers.

• Input Parameters: Traffic volume for the projected period is obtained from the traffic projections. The total number of vehicles passing per hour by type - light, medium and heavy along with their average speed is used for predictions.

• Average Noise Level: All vehicles produce noise, which is taken as the base, and the cumulative noise at the receiver distance due to the whole traffic is estimated. The average noise level varies depending on the type of vehicle.

• Application of Model: Equivalent noise levels due to traffic at the receivers are estimated using Federal Highway Noise model. Equivalent Sound Level (TEQ, denoted by the symbol, LAeqT): Ten times the base-10 logarithm of the square of the ratio of time-average, mean-square, instantaneous A-weighted sound pressure, during a stated time interval, T (where T=t2-t1), and the reference mean-square sound pressure of 20: Pa, the threshold of human hearing, e.g., 1HEQ, denoted by the symbol, LAeq1H, represents the hourly equivalent sound level.

LAeqT = LAE - 10*log10(t2-t1) where LAE = Sound exposure level in dB

343. Sound Exposure Level (SEL, denoted by the symbol, LAE): Over a stated time interval, T (where T=t2-t1), ten times the base-10 logarithm of the ratio of a given time integral of squared instantaneous A-weighted sound pressure, and the product of the reference sound pressure of 20:Pa, the threshold of human hearing, and the reference duration of 1 sec. The time interval, T, must be long enough to include a majority of the sound source’s acoustic energy. As a minimum, this interval should encompass the 10 dB down point.

Table 51: Annual Average Daily Motorized Traffic Data

Year 4W LCV Truck Bus 3W 2W

2020 1963 801 449 1436 316 4323

2025 2964 961 551 1959 379 5894

2030 4236 1124 661 2584 444 7667

2035 5776 1285 774 3282 515 9646

Table 52: Equivalent Background Noise levels

Equivalent Noise Levels in dB(A)

DAY NIGHT

67.8 58.2

141

142

Table 53: Predicted Noise Levels along the Project Road Day

LHS RHS

200 100 50 20 10 10 20 50 100 200

2020 67.8 67.9 68.3 69.7 70.9 70.9 69.7 68.3 67.8 67.8

2025 67.8 67.9 68.5 70.3 71.6 71.6 70.3 68.5 67.9 67.8

2030 67.8 67.9 68.7 70.8 72.3 72.3 70.8 68.6 67.9 67.8

2035 67.8 68.0 68.9 71.3 73.0 73.0 71.3 68.8 67.9 67.8

Night

LHS RHS

200 100 50 20 10 10 20 50 100 200

2020 58.4 59.2 61.7 66.2 68.4 68.4 66.2 61.6 59.0 58.4

2025 58.5 59.5 62.5 67.3 69.6 69.6 67.3 62.4 59.3 58.5

2030 58.6 59.8 63.2 68.3 70.7 70.7 68.3 63.1 59.5 58.6

2035 58.6 60.1 63.9 69.1 71.6 71.6 69.1 63.8 59.8 58.6

344. The IFC Environmental Health and Safety Guidelines – “General EHS Guidelines (Environmental Noise Management”) and the World Health Organization (WHO, 1999) states that noise levels from a project should not result in a maximum increase in background levels of 3 dB(A) at the nearest receptor location off-site.

345. The Indian standard requires noise levels for the 12 hour Leq-dB(A) not to exceed 65 dB(A) and 55 dB(A) at commercial building during the daytime and at nighttime respectively. This is also the IFC standard. Indian standards require noise levels for the 12 hour Leq-dB(A) not to exceed 55dB(A) in daytime and not to exceed 45dB(A) nighttime at residential property.

346. From Table 53, it is observed that predicted noise levels (Leq) near the receivers within 20m from the centre line of the road are found to exceed the permissible limit of 3 dB(A) during day time however noise levels (Leq) near the receivers within 50m from the centre line of the road are found to exceed the permissible limit of 3 dB(A) during night time for the respective landuse categories. The baseline noise levels (2019) are marginally higher than the permissible limits of CPCB for different landuse categories for day and night. The predicted levels based on noise modelling show increase in noise levels for future years at all receivers (including sensitive receptors listed above) considering increase in traffic volume.

347. Mitigation Measures: The incremental noise levels for future years exceed the allowable limit of 3 dB (A) from the baseline levels. There are several measures that can be explored for the road, particularly along sensitive land uses such as solid noise barriers, establishment of greenbelt along the road edge, imposing speed limits, use of noise reducing pavements along built up portions, noise insulation of sensitive receivers, among others. One or a combination of these measures may be able to bring down the noise within acceptable range. These measures can be incorporated in the final detailed engineering by the contractor after consultation with affected persons so that the most suitable mitigation measures are considered. For example, solid noise barriers can reduce noise by 8- 9 dB which will bring noise levels down within permissible limits, but these can be obstructive especially along market areas or storefronts where sensitive receptors may also be located. The final measures considered will be reviewed and approved by the CSC and the PIU.

143

348. Vibration

Design and pre-construction stage – neutral impact

349. Existing ambient vibration levels at the sensitive receptors are low. Any impact on structures by means of vibration will be generated during the construction phase of the project, regardless of the design chosen.

Construction stage –moderate negative impact

350. When the ground is subject to vibratory excitation from a vibratory source, a disturbance propagates away from the vibration source. The ground vibration waves created are similar to those that propagate in water when a stone is dropped into the water. The duration and amplitude of vibration generated by construction equipment varies widely depending on the type of equipment and the purpose for which it is being used. The vibration from blasting has a high amplitude and short duration, whereas vibration from grading is lower in amplitude but longer in duration. In assessing vibration from construction equipment, it is useful to categorize the equipment by the nature of the vibration generated.

351. Review of available literature indicates that there is limited information available on vibration source levels from general construction equipment. The most comprehensive list of vibration source amplitudes is provided in the document entitled Transit Noise and Vibration Impact Assessment (Federal Transit Administration 2006).

Table 54: Vibration Generated from Different Construction Equipment

Equipment Reference PPV at 25 ft.

(in/sec)

Vibratory Roller 0.21

Large Bulldozer 0.089

Caisson Drilling 0.089

Loaded Trucks 0.076

Jackhammer 0.035

Small Bulldozer 0.003 Sources: Federal Transit Administration 2006 (except Hanson 20015 for vibratory rollers)

352. Using these source vibration levels, vibration from these equipment can be estimated by the following formula:

PPVEquipment = PPVRef (25/D)n (in/sec)

Where: PPVRef = reference PPV at 25 ft. D = distance from equipment to the receiver in ft. n = 1.1, attenuation rate(6)

5 Peck R B, Hanson W E and Thornburn T H (1974). Foundation Engineering. John Wiley and Sons, New York. 6 WOODS, R.D. and JEDELE, L.P., 1985. Energy-attenuation relationships from construction vibrations. American

Society of Civil Engineers, Proceedings of ASCE Symposium on Vibration Problems in Geotechnical Engineering, Detroit, Michigan, G. Gazetas and E.T. Selig, Editors, pp. 229-246.

144

353. International Guidelines and Standards present criteria for vibration related building damage in the form of threshold levels of vibration (peak particle velocity), as either a value or range of values. Key factors in determining these levels are as follows:

• the nature of the building including its construction, its condition, and whether is of

historic importance; • the likely extent of damage i.e. cosmetic, minor structural or major structural; and • whether the source of vibration is continuous or a single event and the dominant

frequency (Hz).

Table 55: Building Vibration Damage Assessment Criteria Building Vibration Damage Risk Level

Building Description

Cosmetic Damage

Threshold ppv (mm/s)

Source Reference for

Criteria

Assumed Building Coupling

Loss

Extremely fragile historic buildings, ruins, ancient monuments

2 Caltrans/BART n/a

High Risk A

Fragile buildings of clay construction with shallow (<1m) rubble footings

3 Caltrans 1

High Risk B

Fragile buildings of clay construction with concrete foundations/footings

3 Caltrans 0.5

Medium Risk

Residential brick built on concrete foundations/footings and light commercial

10 BS 7385/DIN

4150 0.5

Low Risk Heavy commercial, industrial and framed buildings

25 BS 7385/DIN

4150 0.5

354. Impact: The values of vibration generated from the operation of various equipment in construction of project road are below the threshold ppv (mm/s) as mentioned in Table-55. However, vibration during construction may induce cracks and damages to structure next to road alignment particularly Overhead water storage tanks and identified buildings or sensitive receptors.

355. Mitigation Measures: For the structures within 4.5 m (as vibration impacts from construction equipment’s beyond this limit will be insignificant) from road edge, suitable mitigation measures should be adopted to minimize the vibration levels. In case any structure is weak, a pre-construction survey of the building shall be done in detail by the Contractor, witnessed by the CSC as well as the property owner. Vibration monitoring will be carried out at weak structures during construction and additional mitigation measures will be installed in case measured vibration levels (peak particle velocity) exceed 3 mm/s for very sensitive buildings or 5 mm/s for residential structures per DIN 4150-3 threshold. Signed documents and photographic records will be kept as evidence to protect both the owner as well as the project from spurious claims.

356. A wave barrier is typically a trench, or a thin wall made of sheet piles or similar structural members. The purpose of a barrier is to reflect or absorb wave energy, thereby reducing the propagation of energy between a source and a receiver. The depth and width of a wave barrier must be proportioned to the wavelength of the wave intended for screening.

145

357. Adverse human response to construction vibration can be mitigated by good communication between the contractor and local residents. If occupiers of dwellings are informed of their nature, duration, and potential vibration effects prior to the works, then adverse response will be less. Generally, the main concern relating to construction vibration is of damage to property and if this is not likely to occur, then this point should be made clear to residents.

358. Residual Impact: With the proper implementation of the proposed mitigation measures the construction of the project is not expected to have a residual impact due to vibration.

Operation stage – minor negative impact

359. Impact: Because vehicles travelling on highway are supported on flexible suspension systems and pneumatic tires, these vehicles are not an efficient source of ground vibration. They can, however, impart vibration into the ground when they roll over pavement that is not smooth. Continuous traffic travelling on a smooth highway creates a fairly continuous but relatively low level of vibration. Where discontinuities exist in the pavement, heavy truck passages can be the primary source of localized, intermittent vibration peaks. These peaks typically last no more than a few seconds and often for only a fraction of a second. Because vibration drops off rapidly with distance, there is rarely a cumulative increase in ground vibration from the presence of multiple trucks. In general, more trucks result in more vibration peaks, though not necessarily higher peaks. Automobile traffic normally generates vibration amplitudes that are one-fifth to one-tenth the amplitude of truck vibration amplitudes. Accordingly, ground vibration generated by automobile traffic is usually overshadowed by vibration from heavy trucks.

360. Mitigation Measures: Because vibration from vehicle operations is almost always the result of pavement discontinuities, the solution is to smoothen the pavement to eliminate the discontinuities. This step will eliminate perceptible vibration from vehicle operations in virtually all cases.

361. Residual Impact: The impact of vibrations due to road traffic will be negligible given the highway pavement is maintained at good condition.

4. Occupational health and safety

Design and pre-construction stage – neutral impact

362. No impacts on occupational health and safety are expected to arise from the design phase of the project. Road design proposed standards are consistent with the parameters recommended in the relevant standards of the IRC and are detailed in Chapter III of this report.

Construction stage - moderate negative impact

363. Impact: Transportation incidents accounted for majority of fatal roadway worksite incidents.7 In India, Tamil Nadu has recorded the highest rate of road accident fatalities at 23 fatalities/lakh persons.8 As such, particular attention to transportation-related work hazards should be given under the project. Among other construction-related risks in highway projects are:

7 https://www.dbkrieginc.com/onsite-work-safety.php; data taken from US Bureau of Labor Statistics 8 Policy Research Studies (PRS) Legislative Research, India. https://www.prsindia.org/policy/vital-stats/overview-road-

accidents-india

146

• falls and slips due to uneven surfaces, edges of elevated ground with no proper barricading;

• struck-bys falling debris or flying objects; • caught-in-betweens due to rotating equipment or unguarded parts of construction

machinery; and • electrocution risks while carrying out work or residing in campsites

364. The construction camps are anticipated to house up to 250 people for about three years. With this concentration of people, the potential for the transmission of diseases and illnesses will increase. The main health and safety risks during construction will arise from:

• inadequate sanitation facilities in worker camps; • introduction of sexually transmitted, and other diseases, by immigrant workers; • outbreaks of malaria, typhoid, cholera etc. amongst the labour force; and given the

current COVID-19 pandemic there is also a risk of construction workers being exposed to this and other communicable viral diseases, particularly given construction is directly within the community and the transient nature of the construction workforce.

365. Mitigation Measures: The following shall be followed before, during, and after construction activities, as applicable:

• The Contractor will be required to conduct workplace risk assessment to identify potential risks to workers.

• The Health and Safety Officer shall also conduct regular training on health and safety.

• The contractor is responsible for instituting measures and procedures to maintain cleanliness and order in campsites and construction sites.

• The Contractor will provide facilities such as dust bins and collectors for the temporary storage of all waste. This waste should be adequately stored to avoid pollution of water supplies and water sources and to avoid dust formation.

• The Contractor will be responsible for the safe removal and/or storage of all waste in order to prevent environmental pollution of any type that may be harmful to people or animals.

• All necessary safeguards should be taken to ensure the safety, welfare and good health of all persons entitled to be on the sites and to ensure that works are carried out in a safe and efficient manner.

• All personnel working at vulnerable site locations will wear safety helmets and strong footwear (OSHA recommended PPE).

• It should be ensured that all workmen and staff employed on site use proper safety equipment – for example, eye protectors, ear plugs, safety helmets, the designated safety equipment when working over water – and that proper rescue equipment is available.

• Fire extinguishers and first-aid equipment will be kept at all sites.

• Additional health and safety protocols for prevention and control of the spread of COVID 19 and other communicable diseases shall be put in place in accordance with local/national guidelines and international best practices.

• To ensure safe construction, lighting devices and safety signals shall be installed and traffic rules and regulations to be strictly followed.

147

• The electrical equipment should be checked regularly to avoid risks to workers. Adhere to strict schedule for completion of road works and avoid prolonged construction and disturbance

• Implement SEMP Sub-plans (e.g. Health and Safety Plan, Traffic and Road Management Plan, Camp Management Plan)

• Provide barricade fencing to mitigate trespassing

• Provide barricade to temporarily enclose open excavated slopes / foundations

• Provide sufficient lights, clear warning signs and danger signals

• Assign security personnel to prevent accidents,

• Warning signs and cones will be installed in and around the work site and along haul roads, with clearly marked danger zones

• Safety flags and flag persons will be used, as needed

• Record of incidents /accidents / near-miss/ fatalities associated with the project will be maintained

• Records of issues raised will be maintained in accordance with the project GRM

366. Outreach to local communities and information disseminate e.g. on project implementation schedule, health & safety and ERPs will be provided via information disclosure and meaningful consultation activities) in local language in the project area of influence..

367. The following actions will be undertaken at construction camps and stipulated in construction contracts:

• submit and obtain approval for a health and safety plan prior to the commencement of work;

• provision of adequate health care facilities and healthcare staff; • ensure adequate security is provided to construction staff on site and at worker

accommodation; • workers will be required to undergo pre-employment medical screening and

treatment (if required) and periodic health checks thereafter; and • For COVID-19 related health and safety risk, the contractor will be required to

prepare and implement a COVID-19 Action Plan9.

368. The project will support a public health education programme for workers and villagers covering road safety, malaria, hygiene, endemic and communicable diseases such as COVID-19 and sexually transmitted diseases. The district health departments will also be invited to participate in monitoring and educating communities and workers affected by the project.

369. Residual Impact: With proper implementation of the proposed mitigation measures the residual impact on occupational health and safety is expected to be low.

Operation stage – neutral impact

9 For COVID-19 national restrictions for containing the spread of COVID-19 must be complied with and in developing

the health and safety management plan Government of India (https://www.mygov.in/covid-19) and World Health Organization guidance (https://www.who.int/emergencies/diseases/novel-coronavirus-2019/technical-guidance) should be followed ensuring adequate sanitation and welfare facilities including for hand washing and personal protective equipment are provided to construction workers. Given the specialist nature of responding to COVID-19 public health officials/experts to be consulted.

148

370. No impact on occupational health and safety is envisaged during operation phase of the project. Road safety features are included in the project design as discussed in Chapter III of this report.

5. Community health and safety and local resources

Design and pre-construction stage – neutral impact

371. No impacts on community health and safety are expected to derive from the design phase of the project. Improving overall safety during operation is a major consideration in the design of the road. Road safety features are included in the project design as discussed in Chapter III of this report.

Construction stage – moderate negative and positive impacts

372. Impact: Construction camps may put stress on local resources and the infrastructure in nearby communities resulting to people raising grievances. This sometimes leads to conflict between residents and migrant workers. The construction activities may also potentially result in adverse impacts to community health and safety such as construction traffic and accidents, and accidental spills of liquid materials. There are also chances of exposure to communicable diseases from migrant workers.

373. Mitigation Measures: To prevent problems between construction workers and the local communities, the contractor should provide the construction camps with facilities such as health care clinics, places of worship, and occasional entertainment. During construction, benefits to local people can be maximized if the contractor recruit construction workers locally regardless of gender. Contractor should also not discriminate in the employment of women. The contractor will be required to develop a community health and safety plan which will also include emergency response and preparedness procedures.

374. The project will support a public health education programme for workers and villagers covering road safety, hygiene, malaria and other endemic diseases, and communicable diseases such as COVID-19 and sexually transmitted diseases. The district health departments will also be invited to participate in monitoring and educating communities and workers affected by the project.

375. Residual impact. With proper implementation of the proposed mitigation measures no residual impact is expected on the community health and safety.

Operation stage – positive impact

376. The improvements of the project road are expected to benefit the socio-economic conditions of communities in and around the project area. Improved access and reduced travel time and cost will be major stimuli to economic growth, health and education, particularly in rural areas. Better access of agricultural goods to market will be important and a major contributor to poverty reduction. These benefits are likely to have a positive impact on community health. Some risks associated with improved road such as accidents etc. are however anticipated. Implementation of road safety measures will minimize these risks. Section 10 under Design Standards of Chapter III deals with traffic safety features, road furniture, road markings and other facilities which shall contribute to increased safety, not only for vehicles but also pedestrians and

149

other road users. Geometric and sight distance improvement considered in the road designs used during bidding are also meant to improve fundamental features of the road to increase safety.

G. Physical and Cultural Resources

377. There are no adverse impacts anticipated on historical places/monuments. However, there are few small shrines along the road. Care must be taken to clearly identify these structures before construction and avoid any damage to these structures. If necessary, these structures maybe moved after carrying out proper consultation with the local community people. Earthworks, as associated with the road construction/improvement works, or deriving from secondary sites such as quarries or borrow pits, may reveal sites or artefacts of cultural/archaeological significance. In the event of such discovery, the concerned authorities should be informed and the requirement to take such action should be incorporated in contract documents.

H. Induced and Cumulative Impacts

378. According to the ADB Environment Safeguards Sourcebook Cumulative Impacts is described as: “The combination of multiple impacts from existing projects, the proposed project, and anticipated future projects that may result in significant adverse and/or beneficial impacts that cannot be expected in the case of a stand-alone project.” The sourcebook also describes Induced Impacts as: “Adverse and/or beneficial impacts on areas and communities from unintended but predictable developments caused by a project, which may occur at later or at a different location.

379. The road upgrading will improve the travel speed and travel condition along the project road corridor and is expected to generate a road user cost saving and this will result in additional traffic generation along the corridor. Currently there is no other information on future development projects along the project road. Hence, it is difficult to assess other cumulative impacts from other projects which may get implemented in the project area.

380. The improved road is expected to increase transport through the project region but is unlikely to trigger exponential development in this region. Setting up few new industries and increase in trade volume though cannot be ruled out. Noise and air quality impacts due to increased traffic volume are also envisaged. Mitigation measures are available for noise impacts while air quality impacts are considered insignificant. As such no significant induced environmental impact is anticipated due to proposed project activity.

I. Expected benefits from the Project

381. The immediate benefits of road construction and improvement will come in the form of direct employment opportunities during construction for the roadside communities engaged as wage laborer, petty contractors and suppliers of raw materials. During operation stage, road-side economic activities supporting transport like gasoline stations, automotive repair shops, lodging, and restaurants will increase due to increased number of vehicles. The project road section is part of connecting industrial zones to enhance transportation services for raw material and products. Increase in agro-industrial activities are also expected to take advantage of improved access to urban centers where there are higher demands and better prices for agricultural products. Project will accelerate the economic opportunities resulting in reduced migration. Other benefits of project road improvement are: (i) reduction in travel time, (ii) better mode and frequency of transport, (iii) access to quality health care, educational, and other infrastructural facilities (iv) improved quality

150

of life of rural population, and (v) better investment climate for industries creating more employment opportunities for local people.

VII. CONSULTATION, PARTICIPATION AND INFORMATION DISCLOSURE

A. Meaningful Consultation

382. In accordance with ADB’s Safeguard Policy Statement (SPS) 2009 meaningful consultations were held early and throughout the project development stages to allow the incorporation of relevant views of the stakeholders in the final project design, mitigation measures, implementation issues, and enhance the distribution of benefits. All the five principles of information dissemination, information solicitation, integration, co-ordination, and engagement into dialogue were incorporated in the consultation process. The analysis of environmental impacts from the projects was strengthened and modified based on opinions of all those consulted, especially in the micro level by setting up dialogues with the village people from whom information on site facts and prevailing conditions were collected. The requirement of public consultation during the implementation of the project has been proposed as part of the mitigation plan. B. Objectives of the Consultations

383. Stakeholder’s consultations were held with intent to understand their concerns, apprehensions, overall opinion and solicit recommendations to improve project design and implementation. Informal meetings, interviews were organized covering the entire projects design stage. Consultations provide affected people a platform to ensure incorporation of their concerns in the decision making process and foster co-operation among officers of CKICP, the community and the stakeholders to achieve a cordial working relationship for smooth implementation of the projects. It inculcates the sense of belongingness in the public about the project.

384. The discussions were designed to receive maximum inputs from the participants regarding their acceptability and environmental concerns arising out of the project. They were given the brief outline of the projects to which their opinions were requested particularly in identifying and mitigating any potential adverse impact. C. Methodology for Consultations

385. Consultation with the stakeholders, beneficiaries, and community leaders were carried out using standard structured questionnaires as well as unstructured questionnaires. Questionnaire survey/ discussions were designed to obtain background information and details of general environmental issues that concern people in the project areas. In addition, environmental issues were discussed with relevant organizations, government officials, beneficiaries, community leaders and experts. Aside from these, personal discussions with officials, on site discussion with affected stakeholders, and reconnaissance visits have also been made to the project areas. Public consultation has been carried out at six locations along the project road section.

386. Environmental and social experts conducted informal public consultations with local community during site visit along the project road. Main objective of the public consultation was to aware the community regarding the proposed development and to obtain their views and suggestions on the likely impacts due to the project and their mitigations. To further strengthen this, formal Public Consultation was conducted during September 2019 and January 2020 at six locations along SH-115 and ECR link road. All technical, social and environmental issues

151

pertaining to the stretch were briefed and discussed. Potential PAPs, District level Govt. officials, MLAs/ MPs/ Panchayat Members, TNRSP Officials, Village representatives, PRIs, Village level health workers, Patwaris, Local voluntary organizations like CBOs and NGOs attended the consultations.

387. A total 50 participants including 41 males and 9 females attended the public consultation meeting. Below Table 56 show the details of the public consultations carried out along road section.

Table 56: The details of Public Consultation for Project Road

Sl. No.

Village/Town Name

Date of Consultation

No. of participants

M F T

1 Vandavasi 24/09/2019 7 2 9

2 Arasur Village 25/09/2019 9 5 14

3 Melmaruvathur 27/01/2020 5 1 6

4 Nedungunam 31/01/2020 9 1 10

5 Chetpet 31/01/2020 7 0 7

6 ECR link 31/01/2020 4 0 4

Total 41 9 50

1. Project Stakeholders

388. All types of stakeholders were identified to ensure as wide coverage as possible.

• Residents, shopkeepers and business people who live and work along the road specially the project affected persons

• All type of road users/commuters • Executing Agency, Construction Supervision Consultant and Implementing NGOs • Other government institutions whose remit includes areas or issues affected by the

project (state environment and forest department, Pollution Control Board (PCB), Irrigation Department, Public Health Engineering (PHED) Department, and

• The beneficiary community in general.

2. Consultation with Government Departments

389. Various officials consulted during IEE preparation included State Forest Department, Department of Science Technology and Environment, Urban Development and Tamil Nadu State pollution control board for air, noise and water quality information, IMD for the climatic data, statistical officer for population and demographic profile, panchayat department for village level information, Survey of India for the toposheet requirement, revenue department for the land record information, PHED officers for hand pump relocation and quality assessment, state electricity board offices for electric pole shifting etc.

390. These departments helped to provide various project related data and information which helped preparation of reports and data analysis.

3. Consultation with Local People and Beneficiaries

152

391. The informal consultation generally started with explaining the projects, followed by an explanation to potential impacts. Participant’s views were gathered with regard to all aspects of the environment which may have direct or indirect impact on local people. Key issues discussed were:

• Awareness and extent of the project and development components; • Benefits of the project for the economic and social upliftment of community; • Labour availability in the project area or requirement of outside labour involvement; • Local disturbances due to project construction work; • Necessity of tree felling etc. at project sites; • Impact on water bodies, water logging and drainage problem if any; • Environment and health aspects; • Flora and fauna of the project areas, and • Socio-economic standing of the local people.

392. The project has immense acceptability among the local people. They perceive that in addition to providing all weather connectivity, the project roads will bring positive socioeconomic changes in the areas. Local people mainly discussed on the issues related to flooding, rehabilitation, resettlement, and road safety issues. The outcome of the consultations have been summarized in Table 57.

Figure 20: Photographs of Public Consultation

153

393. The details of participants and public consultation attendance list are attached in Appendix 14. In addition information on the GRM procedures and formats in local language i.e. Tamil was shared with the local people.

Table 57: Summary of Issues Discussed and Measures Taken

Location and Date

Issues Discussed Measures Taken Participant

Vandavasi:

24/09/2019

Arasur Village:

25/09/2019

Melmaruvathur: 27/01/2020

Nedungunam: 31/01/2020

Chetpet: 31/01/2020

ECR link: 31/01/2020

• People are facing acute problem related to poor condition of the road.

• Where the road passing through the settlements there should be

• provision of Speed breakers Suggestion viz. (i) design shall take into hydrological aspects into consideration (ii) minimal loss of structures (iii) adequate settlement and rehabilitation measures including provision of jobs to land losers

• Local people informed that present road in some sections of this area submerges during normal rainfall also. Adequate measures shall be taken to avoid water logging during normal rainfall.

• They suggested that existing alignment shall also be improved and maintained properly.

• Suggestion viz., Minimal loss of structures, Adequate rehabilitation and resettlement ,measures

• Area is one of the congested stretches due to that problem of traffic jam and

Proposed widening and strengthening of the road will provide better level of services in terms of improved riding quality and smooth traffic flow.

• There will be considerable reduction in the number of accident and level of pollution.

• Accessibility to social health and educational infrastructure will increase through all-weather road.

• Generation of employment during construction phase of the road.

• The discussion generates.

• considerable awareness of the project .

• As the proposed road shall be a widened one, it shall provide an efficient public transportation system besides.

• ensuring reduction in congestion level

• The title holders shall also be compensated as per ADB guidelines.

• Drainage system is mention in built-up area and earthen drainage for rural area.

• Drainage system is mention in built-up area and earthen

Total 50 Participant was attended the consultation meetings which includes 41 male and 9 female participants.

154

Location and Date

Issues Discussed Measures Taken Participant

accident is common.

• Stress was put by the community on adequate safety provisions to be made along the road particularly at locations of school,

• cattle underpass, provision of bus stop and provision of green belt development Compensation should be as per market value.

drainage for rural area. Road safety features like traffic signs, Overhead Sign Boards, Road Illumination, Delineators,

• pavement marking, pedestrian path and rumble strips has been included in the design.

• Proper Rehabilitation measures will be taken for . Affected Household’s and compensation will be as per market rate.

394. Most of the people interviewed were well aware of the environmental conditions in and around their villages. A major percentage are not aware of any foreseen deterioration in the air and noise quality due to expansion of existing highway. The villagers are quite enthusiastic about the proposed project as it will give fillip to rural economy and present them many employment opportunities during construction of project road. Overall positive approach towards the project is observed.

4. Results of Consultation with Local People

395. Most of the people interviewed strongly support the project work. The people living in the entire project area expect the different project elements to facilitate transport, employment, tourism, boost economic development and thereby provide direct, or indirect, benefits to them. In order to access the existing environment and likely impacts on surrounding population, an interview survey was carried out. A priority of the population was interviewed through a designed questionnaire. Precaution has been exercised during the survey to ensure that the priority interviewed is truly representative of the affected groups and the questions are worded so as not to generate a bias response.

396. Overall, most of the people interviewed strongly support the project. The people living in the entire project area expect the different project elements to facilitate transport, employment, tourism, boost economic development and thereby provide direct, or indirect, benefits to them. Construction camps may, however, put stress on local resources and the infrastructure in nearby communities. In addition, local people raised construction-process related grievances with the workers. This sometimes leads to aggression between residents and migrant workers. To prevent such problems, the contractor should provide the construction camps with facilities such as proper housing, health care clinics, proper drinking water and timely payment. The use of local laborers during the construction will, of course, increase benefits to local peoples and minimise these problems. Wherever possible, such people should be employed.

397. Design considerations have been made to incorporate most of the suggestions and demands of the local people except those which are beyond the scope of the project like improvement of already deteriorated water quality, drinking water facility and reconstruction of link roads, etc.

155

D. Interaction with NGOs

398. In order to get independent views on the likely impacts of the project, non-government organizations at local as well as regional level were consulted during the IEE process. Aspects such as conservation activities, presence of flora and fauna, likely project impacts and possible mitigation measures were discussed and views and suggestions from these NGO’s were incorporated in the EMP. Consultation will continue with these NGO’s during project implementation and operation.

E. Public Disclosure and Further Consultations

399. The TNICP will be responsible for the disclosure of this IEE in compliance to ADB’s Access to Information Policy 2019 and ADB’s SPS 2009. The IEE will be disclosed in the English language in the office of TNICP. The report will also be made available to interested parties on request from the office of the TNICP. Since this is Category B project, this IEE report will be disclosed to the public through the ADB and CKICP website. This IEE report will also be made available to all stakeholders as part of the consultation process required under the SPS 2009.

400. Prior to finalization of detailed engineering design, the contractor, with the assistance of the PIU should consult affected persons along sensitive receptors identified during survey on structural and institutional mitigation measures for impacts such as, but not limited to, noise. Further, project consultations will be organized by the FIU in coordination with CSC and with the presence of representatives from the contractor. Participation of women and FGDs with women and vulnerable groups will be prioritized and conducted to the extent feasible. These should be done at least quarterly during construction period.

156

VIII. GRIEVANCE REDRESS MECHANISM

401. Project grievance redress mechanism (GRM) will be established to evaluate and facilitate the resolution of affected persons concerns, complaints, and grievances related to social and environmental issues of the project. The GRM will provide a time-bound and transparent mechanism to voice and resolve social and environmental concerns linked to the project.

402. GRM Information: Information on the availability of GRM shall be disclosed to public through the TNICP website and through information boards by TNICP along the project road. The setup GRM shall have the system of records keeping of details such as contact details of complainant, date of the complaint received nature of grievance, etc. for the project road and shall take necessary action to address the complaint. The concerned grievance redress committee (GRC) will determine the merit of each grievance and resolve grievances within an outer time limit of three months of receiving the complaint. All complaints determined to be within the purview of land acquisition, rehabilitation and resettlement will be dealt with under the LARR GRC detailed in the RPs. Otherwise, all other social and environmental related complaints will be coursed through the grievance redress process detailed below.

403. Grievance Redress Process: The grievance redress process will be a two-tier process for both LARR and all other project-related complaints. In case of grievances that are immediate and urgent in the perception of the complainant, the contractor and Construction Supervision Consultant (CSC) on-site personnel will provide the most easily accessible or first level of contact for quick resolution of grievances. Contact phone numbers and names of the concerned Divisional Engineer, Assistant Environment Specialist, contractors, and CSC will be posted at all construction sites at visible locations. The PIU safeguard officers will be responsible to see through the process of redressal of each grievance.

(i) 1st Level Grievance: The Regional level Project GRC will be chaired by the concerned Divisional Engineer and would comprise the Assistant Environment Specialist, Project Manager of EPC contractor and Resident Engineer of CSC concerned. The Regional level GRC can immediately resolve relatively simple, on-site concerns and grievances in consultation with each other. Grievances at this level will be addressed within 7 days of receipt of a complaint/grievance.

(ii) 2nd Level Grievance: All grievances that cannot be redressed within 7 days at the Regional level will be reviewed by the State level Project GRC. It will serve as appellate authority and will be chaired by the Chief Engineer and will comprise the Superintending Engineer concerned, Environment Specialist, Team Leader of CSC concerned, Project Manager from Project Management Services of CSC-01 and Authorized Representative from EPC contractors, as needed. Grievance response period for all GRCs is 3 weeks.

404. Complaints Register with EPC Contractor: The contractor shall keep and maintain a complaint register report at their site office along the project road as well as project facilities like construction camp, labour camp etc., for public to register their complaints. The EPC Contractor, after taking necessary action based on the complaint, will also incorporate the same in the complaint register. This report will also be part of the monthly report, to be submitted to the Regional GRC and for CSC to monitor and take necessary action, if needed. It is to be noted that, inaction upon the complaint of the public will be considered as a major lapse from the side of the EPC contractor, leading to invoking of penalty clause which is given in bid document/EMP.

157

3

wee

ks

7 d

ay

s

405. Despite the project GRM, an aggrieved person shall have access to the country's legal system at any stage, and accessing the country's legal system can run parallel to accessing the GRM and is not dependent on the negative outcome of the GRM. The GRCs will continue to function throughout the project duration including the defects liability period. The schematic of the GRM is presented in Figure 21.

Figure 21: Grievance Redress Mechanism

Affected Person

1st Level Grievance

2ndLevel Grievance

Court of Law

Regional Level Responsible: DE, Asst. Env. Specialist, PM EPC Contractor, RE CSC

State Level Responsible: Chief Engineer, SE, Env. Specialist, TL CSC, PM PMS of CSC-01, EPC contractor representative

Not Resolved

Grievance Redress &

Record Keeping

Grievance Redress &

Record Keeping

Not Resolved

Resolved

Resolved

158

IX. ENVIRONMENTAL MANAGEMENT PLAN

A. Introduction

406. The Environmental Management Plan (EMP) is the synthesis of all proposed mitigation and monitoring actions, set to a time-frame with specific responsibility assigned and follow-up actions defined. It contains all the information for the proponent, the contractor and the regulatory agencies to implement the projects within a specified time-frame.

407. This EMP consists of a set of mitigation, monitoring and institutional measures to be taken for the project to avoid, minimize and mitigate adverse environmental impacts and enhance positive impacts. The plan also includes the actions needed for the implementation of these measures. The major components of the Environmental Management Plan are:

• Mitigation of potentially adverse impacts; • Monitoring of EMP implementation during project construction and operation; and • Institutional arrangements to implement the EMP.

408. Prior to start of construction work Environmental Expert of the CSC team in coordination with Contractor will update this EMP to make it site specific in the form of Construction EMP (CEMP).

B. Objectives of Environmental Management Plan

409. The main objectives of this EMP are:

• To ensure compliance with Asian Development Bank’s applicable safeguard policies, and regulatory requirements of the Government of Tamil Nadu and India;

• To formulate avoidance, mitigation and compensation measures for anticipated adverse environmental impacts during construction and operation, and ensure that environmentally sound, sustainable and good practices are adopted;

• To stipulate monitoring and institutional requirements for ensuring safeguard compliance; and

• The project road should be environmentally sustainable.

C. Environmental Management Plan Matrix

410. The EMP matrix provided in Table 58 (prepared section wise as per contract package) follows the environmental impacts and proposed mitigation measures for the identified Valued Environmental Components (VECs) identified and discussed in Chapter VI. The matrix provides an implementable plan with recommended mitigation measures for each anticipated impact and also assigns responsibilities for implementation, supervision and monitoring. D. Environmental Monitoring and Reporting Program

411. The environmental monitoring program has the underlying objective to ensure that the intended environmental mitigations are realized and these results in desired benefits to the target population causing minimal deterioration to the environmental parameters. Such program targets proper implementation of the EMP. The broad objectives are:

• To evaluate the performance of mitigation measures proposed in the EMP.

159

• To evaluate the adequacy of environmental assessment. • To suggest ongoing improvements in management plan based on the monitoring and

to devise fresh monitoring on the basis of the improved EMP. • To enhance environmental quality through proper implementation of suggested

mitigation measures. • To meet the requirements of the existing environmental regulatory framework and

community obligations.

412. The EMOP matrix covering various performance indicators, frequency and institutional arrangements of the project in the construction and operation stages, along with the estimated cost, is summarized in Table 59. Key features of the EMOP are described in the following paragraphs.

1. Performance Indicators

413. The potential physical, biological and social components affecting the environment at critical locations serve as wider/overall Performance Indicators. However, the following specific environmental parameters can be quantitatively measured and compared over a period of time and are, therefore, selected as specific Performance Indicators (PIs) for monitoring because of their regulatory importance and the availability of standardized procedures and relevant expertise.

• Air Quality with respect to PM2.5, PM10, CO, NOx and SO2 at selected location. • Water Quality with reference to pH, DO, BOD, Oil and grease, COD, Suspended

Solids, total dissolved solids, total solids, chlorides Turbidity and Alkalinity at crossing points on rivers/streams at selected points.

• Noise and vibration levels at sensitive receptors (schools, hospitals, community/religious places and weak structures).

• Survival rates of trees planted as compensatory plantation should not be less than 70 percent and compensatory plantation raised for removal of roadside trees.

414. Ambient Air Quality (AAQ) Monitoring: Ambient air quality parameters recommended for monitoring road development projects are PM2.5, PM10, Carbon Monoxide (CO), Oxides of Nitrogen (NOx) and Sulphur Dioxide (SO2). These are to be monitored, right from the commencement of construction activity at selected locations of plants and machinery, crushers on sites, excavation works etc. Data should be generated quarterly excluding monsoon at the monitoring locations in accordance with the revised National Ambient Air Quality Standards formulated by MOEFCC in 2009 as well as IFC air quality standards (Appendix-4).

415. Water Quality Monitoring: The physical and chemical parameters recommended for analysis of water quality relevant to road development project are pH, DO, BOD, Oil and grease, COD, total Suspended Solids, total dissolved solids, total solids, chlorides Turbidity and Alkalinity. The location, duration and the pollution parameters to be monitored and the responsible institutional arrangements are given in the Environmental Monitoring Plan. The monitoring of the water quality is to be carried out at locations identified along the project road during construction and operation phase. The Indian Standard Specifications – IS 10500: 1991 and IS 2296: 1992 is given in Appendix 15.

416. Noise and Vibration Level Monitoring: The measurements for monitoring noise and vibration levels would be carried out at sensitive receptors, construction sites and at weak

160

structures locations along the project road. The Ambient Noise Standards prescribed in the Noise pollution (Regulation and Control), Rules 2000 issued by the MOEFCC, GoI as well as IFC noise standards will be followed. Sound pressure levels would be monitored on a 24-hour basis. Noise should be recorded at “A” weighted frequency using a “slow time response mode” of the measuring instrument. Differences between IFC EHS and MOEFCC daytime and nighttime periods should be accounted for in establishing baseline noise levels prior to start of works. The CPCB standards are given in Appendix – 16.

417. Success of Re-vegetation: The project involves widening and up-gradation including construction of cross drainage structures hence these will require felling of trees. Such lost vegetation will be required to be replaced by compensatory plantation. As per policy of the State Government 10 trees have to be planted for each tree removed. These compensatory plantations will have to be monitored for 70% survival rate for three years by the implementing agency with the help of the Forest Department. Such monitoring will be conducted through random samples. Such sampling should cover at least 5% of the area planted up.

161

Table 58: Environmental Management Plan Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

A. DESIGN AND PRE-CONSTRUCTION STAGE

I. Physical environment

1. Surface water quality and quantity

- Construction of culverts and bridges.

- Disruptions to the natural hydrology

- Worsening of erosion problems

- Maintain natural courses of rivers and streams - Identify temporary diversions required and ensure that

these are restored to their natural course as soon as possible

- drainage structures to be properly designed to accommodate forecast discharges;

- side drain waters must be discharged at every available stream crossing to minimize volume and prevent erosion at discharge point;

- provide lined drainage structures; and - where an increased discharge of surface water

endangers the stability of the water outlet, erosion protection measures such as bioengineering measures, ripraps, and check dams are incorporated

- in areas with high water tables, seepage may occur, and side drains and up-slope catch drains must always be lined to avoid percolation

-

Contractor PIU / CSC

2. Land degradation and pollution

- Road widening and related earthworks;

- Collection, quarrying and use of stone, aggregates and sand.

- Construction of sharp curves

- Permanent changes in the local-level topography and appearance of the project site.

- Slope failure at quarry sites;

- Road side instability due to stone collection;

- The construction of sharp curve may add to instability in

- Optimization of the centre line so that embankment raised on both sides;

- Temporary and permanent drainage systems to minimize soil erosion;

- Optimum siting and control of quarries; and - mechanized construction methods. - Minimize land take for development - Optimize balance between cut and fill and avoid deep

cuts and high embankments to minimize earthworks - Maximize reuse of spoils and old asphalt paving material

within the construction - Agree on spoils disposal sites, management and

rehabilitation plan with relevant local agencies

Contractor PIU / CSC

162

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

raised embankment.

- Specify vegetation that serves specific bioengineering functions.

- Aggregates will be sourced from licensed local quarries; - Sand will be taken from quarries or river beds after prior

permission from competent authority; - every new quarry, borrow area, and spoils disposal site is

subjected to a site-specific environmental investigation according to an approved plan;

- new quarry and borrow areas must be left in a safe condition or restored to a productive land use;

- borrow areas are not established in ecologically sensitive areas and should obtain necessary clearances;

- villagers are consulted in regard to the design and location of all borrow areas – these should ensure the safety of local communities and, if possible, should incorporate beneficial post construction features for the villages;

- borrow areas must be located away from the road and hill slopes as well as settlements facing the road, so as to minimize visual impacts.

- Earth cut materials will be maximized for reuse in backfilling on the same rural road to minimize the quantities of borrow materials and spoil disposal.

II. Biological environment

3. Trees and vegetation

- Clearing of vegetation from mostly natural habitat areas for hill cutting and other road improvement works;

- Loss of 4770 trees existing in the RoW

- Minimise removal of vegetation and width of road expansion along the existing alignment to the extent possible.

- the road improvement works will adopt Environmentally Friendly Road Construction (EFRC) methods and should minimise environmental impacts from inadequate drainage and/or slope failures and should assist in maintaining, or repairing, Tree cover;

- Mandatory compensatory afforestation program for plantation 47700 trees (@1:10) within the project area

PIU/ Contractor PIU/CSC

163

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

- Removal of trees

where possible resulting in the improvement of road side green belt development.

- The plantation under compensatory afforestation plan will be scheduled within 15 months of the construction works, as preparation of seedlings in the approved nursey will start with commencement of construction work for the project road

4. Ecologically important areas

- Location of the project road is not within core/ buffer zone of protected area. No major water body crossing and all water sources are in dry condition

- Siltation/pollution of waterbodies Possible fragmentation effects due to increased traffic

- Undertake pre-construction survey along the alignment to identify the section required for protection measures accordingly.

Contractor / CSC PIU

PIU/ CSC

III. Social environment

5. Private land and buildings

- Road widening

- Resettlement of people;

- Acquisition of 41.98 ha. of addition agriculture private land

- Relocation of 567nos. of private structures and 50 nos. of common

A separate resettlement plan is prepared to address these issues in compliance with Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 and ADB SPS 2009.

PIU/ LARR implementation Consultancy

PIU/ LARR Monitoring Consultancy

164

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

property structures (No. of structures mentioned above are tentative).

6. Public property/ infrastructure/ utility structures

- Shifting of electric lines, water pipes, sewage lines, gas pipes and telecom lines

- Temporary outages of public utility services

- Before construction commences a detailed survey has to be carried out in order to list all utilities that will interfere with the road works;

- Together with the respective owners of the utilities plans will be prepared how and when these utilities will be shifted before the works commence.

- Access to adjacent properties and agricultural land will be maintained, as necessary.

- Any damage to areas and infrastructure outside the agreed work sites (Corridor of Impact assessed in project RP) will be restored to pre-construction conditions and will be subject to compensation at contractor cost and through written agreement with the land owner, as applicable.

EPC Contractor CSC / PIU

7. Noise and disturbance

- Operation of construction equipment and machinery, hauling of materials and blasting works

- Increased noise levels causing discomfort to local residents, workers and local fauna

- Prior to finalization of detailed engineering design, the following must be done:

- Survey of sensitive receptors (sensitivity, distance from edge of the proposed road, baseline noise levels)

- Consultation with affected persons on noise abatement measures (e.g. preference for/location and design of noise barriers, reduction of speed limits, etc.)

- Planning of location, duration of noise-generating activities and equipment, particularly along sensitive land uses

- Use of noise reduction equipment; - Planning noise generating activities during daytime.

EPC Contractor CSC/PIU

8. Vibration Operation of vibration rollers during construction

- Possible cosmetic damage to very sensitive buildings

- Pre-construction survey and documentation of structures to determine weak structures that need monitoring during construction

EPC Contractor CSC/PIU

165

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

9. Air quality - Crushers, Hot

Mix Plants & Batching plants

- Temporary localized increase in levels of dust and air pollutants including SO2, NOx and HC

- The contractor shall obtain Consent from the Tamil Nadu Pollution Control Board (TNPCB) for the establishment and operation of crusher, Batching plant and hot mix plant as per the proceedings & guidelines laid down by the TNPCB.

EPC Contractor CSC/PIU

10. Health and safety (H&S)

- Operation of construction equipment and machinery, hauling of materials and blasting works

- Construction activities causing health and safety risks to workers and communities.

- For all construction works comply with Government of India rules and regulations for the protection of workers.

- For all construction works undertake risk assessment and prepare H&S plan in accordance with IFC EHS Guidelines for clearance by CSC and PIU, considering occupational and community H&S and including adherence to emergency preparedness and response plan with communication systems and protocols to report an emergency situation.

- In undertaking H&S risk assessment and planning adequate attention to be given to the risks associated with transportation/vehicles and with COVID-19 pandemic and other communicable viral diseases.

- National restrictions for containing the spread of COVID-19 must be complied with and in developing the health and safety management plan Government of India (https://www.mygov.in/covid-19) and World Health Organization guidance (https://www.who.int/emergencies/diseases/novel-coronavirus-2019/technical-guidance) should be followed.

- Contractor to ensure adequate sanitation and welfare facilities including for hand washing and personal protective equipment are provided and to consider the ability of communities to comply with protective measures such as regular handwashing and for the local health care facilities capacity to deal with any infections.

- Emergency preparedness and response plan to deal with

EPC Contractor PIU

166

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

situation should any construction worker or community member be diagnosed with COVID-19 during the course of the works.

- Given the specialist nature of responding to COVID-19 public health officials/experts to be consulted in undertaking the risk assessment and management planning for COVID-19.

- Contractor to conduct regular training (including refreshers) on occupational health and safety for all construction workers including refreshers. To include training for PIU and all Contractor management and construction workers including subcontractors before commencement of works.

- Contractor to conduct training of workers on emergency preparedness and response procedures in case of an occupational or community health and safety incident during construction works.

B. CONSTRUCTION STAGE I. Physical environment

1. Air quality and GHGs

- Operation of construction equipment and machinery;

- Emissions from brick, concrete and asphalt plants;

- Haulage and stockpiling of materials;

- Controlled earthworks.

• Temporary localized increase in levels of dust and air pollutants including PM2.5, PM10, SO2, NOx, CO, HC (Ambient Air quality standards published in 2009)

- Regular watering of road surfaces, exposed spoils - regular check-up and maintenance of construction

equipment; - idling of engines shall be strongly discouraged; - mixing plants i.e. asphalt, concrete, and bricks, should be

operated within the permissible limits of CPCB and IFC EHS, and located away from settlements;

- the contractor will submit a dust suppression and control programme to the CSC prior to construction – this plan details actions to be taken to minimize dust generation and identify equipment to be used;

- vehicles delivering loose and fine materials should be covered with tarpaulin to reduce spills and speed limits should be imposed;

- no unauthorized burning of C&D waste materials;

Contractor CSC/PIU

167

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

- bitumen emulsion should be used wherever feasible; - bitumen heaters should be used, the use of firewood is

prohibited - ambient air quality monitoring shall be done regularly at

representative sensitive locations to ensure that all the emissions from construction activities are within CPCB and IFC EHS standards and therefore ensuring the effectiveness of mitigation measures taken.

- 2. Surface water

quality and quantity

- Use of surface water for construction and domestic use

- Rehabilitation of existing bridges

- Siltation and erosion impacts

- Use and maintenance of construction equipment

- Labour camps

- Soil erosion and downstream turbidity at bridge locations

- Soil erosion due to changes in natural drainage systems.

- Pollution due to use and maintenance of construction equipment;

- Pollution caused by labour camps

- maintain adequate vegetative cover above and below the road;

- maintain the natural course of water bodies (as much as possible) and avoid throwing debris, C&D spoils into water bodies;

- chemicals and oils are stored in secure, impermeable containers, and disposed of well away from surface waters;

- no vehicle cleaning activity is allowed within 300 m of water bodies/ drains;

- construction camps are equipped with sanitary latrines (septic tanks);

- the work on bridges and culverts is limited to dry seasons, when many of the smaller streams will have low water - water diversion works can be minimised and the original course restored immediately after the work has been completed;

- construction establishments such as construction camps, labor camps, asphalt/concrete mixing stations, stone crushing units should be located away from the water bodies. Domestic and sewage wastes from labor camps shall be treated with a sewage treatment system (septic tanks) to comply with the standards specified by CPCB and WBG before disposal. Testing of effluent has to be done in accordance with the rules and regulations of CPCB and SCPB

Contractor CSC/PIU

168

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

- drivers are made aware of diversions and other works at bridge construction site to avoid accidents;

- all debris and vegetation, clogging culverts must be regularly cleared.

- Prior to use of surface water by workers it has to be established the water quality meets the standards for drinking water. Also regular monitoring of the quality shall be done.

3. Ground water quality and quantity

- Operation of labour camps, temporary construction sites and fuelling stations

- Groundwater abstraction and potential impacts on local sources

- Pollution of groundwater at sites where process water or wastewater is generated and disposed of in an improper manner.

- Construction water requirement (avg. 500KLD and peak 800 KLD) will be met through local surface water sources and other canals in the project area. Domestic water requirement (40 KLD) for workers will also be met mainly through local streams

- Sewage generated at labour camps should be disposed of in an environmentally sound manner.

- construction camps should be equipped with sanitary mobile toilets or toilets with treatment and disposal arrangement by means of septic tank followed by soak pit that do not pollute groundwater;

- Latrines should be located away and downstream of any source for drinking water in order to prevent contamination of drinking water sources.

- Locations for fuelling and/or maintenance should be fitted with impervious flooring and a drainage system connected to an oil/water separator and settling tank to treat sewage before being discharged.

- The layout of labour camps and construction sites should comply with the requirements in appendix 8: Plant Management and appendix 9: Camp Site Management as given in the IEE.

- If groundwater sources will be used for construction, it should be obtained from licensed sources. Domestic water requirement (30 KLD) for workers will also be met through approved sources only. Necessary permits will be obtained prior to water abstraction and only when

Contractor CSC/PIU

169

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

there is no other viable option so as not to compete with local domestic demand.

- Water abstraction will be included in monitoring.

4. Land degradation/ pollution

- Road construction through plain terrain with raised embankment in low laying area;

- Cutting and filling of low laying area for road improvement works

- Disposal of cut soil, debris and waste at improper locations

- Operation of quarry and borrow areas

- Scarring of landscape and potential potholes in raised embankment;

- Dirty and unattractive area due to presence of waste materials;

- Soil erosion might lead to clogging of side drains, leading to spill-over of rainwater runoff;

- Improper restored abandoned quarry and borrow and spoils disposal areas can lead to soil erosion and vector borne diseases due to stagnant water.

- Sites for quarrying, borrowing and disposal of spoils are to be confirmed according to the applicable laws and regulations in the state and the practices followed in recent/ongoing internationally funded road projects.

- Major excavation and earthworks should only be undertaken during the dry season;

- Embankment grades should not be too steep; - The existing vegetation on slopes outside the immediate

area of construction must remain undisturbed during construction and/or upgrading;

- Embankment raised slopes should be re-vegetated immediately after widening activities

- Bioengineering techniques will be used to prevent barren slopes and to stop soil erosion and to protect the animals from grazing animals;

- Support structures will be installed where slope failures are anticipated or may have occurred previously;

- logging immediately above road should be restricted to reduce erosion/landslide potential;

- quarrying along road ROW should be restricted; - Excavated material should be used in the construction

works as much as possible, otherwise it has to be disposed of at proper disposal sites. The management of debris has to comply with the requirements in Appendix 10: Debris and Spoil Disposal Management.

- Mitigation measures for quarry sites are: - Aggregates will be sourced from licensed operational

quarry sites that comply with environmental and other applicable regulations on labour, dust suppression and the use of environmentally friendly quarrying techniques;

Contractor CSC/PIU

170

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

- regular monitoring of the quarries by concerned authorities to ensure compliance with environmental management and monitoring measures;

- Mitigation measures for borrow areas are: - Demarcation of the actual extent of area to be excavated; - borrow pit plant and machinery will conform to

CPCB/SPCB and IFC EHS noise emission regulations; - protective gear will be provided to the workforce exposed

to noise levels beyond threshold limits and there should be proper rotation of such personnel; and

- all operation areas will be water sprinkled to control dust levels to national ambient air quality standards.

- borrow areas are provided with gentle side slope that are re-vegetated and connected to the nearest drainage channel to avoid the formation of cess pools during the rainy season:

- To mitigate the impacts of possible fuel spills the following measures will be applied:

- secondary containment around fuel tanks and at fuelling stations will be built;

- oil and fuel spills, and other runoff from contaminated areas will be controlled; and

- equipment and fuel depots will be placed in safe zones away from drinking water sources and canal and lake;

- the project will provide an opportunity to assist the contractors in improving fuel handling practices so as to minimize future fuel spillage.

Other measures on land and C&D disposal:

• Any temporary lands required for labour camps or any other sites required for the project shall be transferred back to the owner after the land has been restored to its original state before the completion of construction works.

171

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

• Contractor has to collect baseline data on the quality of ambient air, ambient noise, soil, surface water and groundwater before establishing and after decommissioning the camps or sites.

• excavated material shall be stockpiled and covered in such a way the soil will not erode away and should be used to widen the road or disposed of at proper disposal sites following spoil disposal management guidelines (Appendix 10).

• Removal of bituminous wastes from existing roads should not be disposed of in nearby water bodies, open spaces and parks and wastes should not be left unmanaged on the roadsides.

• Bituminous material should be examined for PAH to establish if it can be recycled/ reused for road construction. If not, the bitumen shall be treated as hazardous waste and disposed of in pre-identified and approved disposal sites.

• Any construction and demolition waste generated during the construction phase should be managed in accordance with the C&D Waste Management Rules, 2016.

• As far as possible, demolition and construction waste should be segregated and recycled.

• The unserviceable waste left after recycling should be dumped in pre-identified and approved pits as per Construction & Demolition Waste Management Rules. All required permissions shall be obtained from the concerned authorities before disposal of the debris.

• cut slopes should be re-vegetated immediately after widening activities.

• cut material should be disposed of in suitable depressions.

172

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

To mitigate the impacts of possible fuel spills the following measures will be applied:

• secondary containment around fuel tanks large enough to hold the entire contents of the tank and an additional ten percent and at fueling stations will be built;

• oil and fuel spills, and other runoff from contaminated areas will be controlled; and

• equipment and fuel depots will be placed in safe zones away from drinking water sources and riverbanks;

- Quarry, borrow, and spoils disposal sites must comply

with the requirements in appendix 10-12given in IEE report.

II. Biological environment

5. Trees and vegetation

- Clearing of vegetation for road improvement works;

- Removal of 4770 trees

- Spread of invasive species by construction vehicles and machinery and transport of earth and construction material/debris

- Loss of 4770 trees - Loss of habitat for

birds fauna. - Fragmentation of

habitat due to loss of vegetation cover

- Degradation of vegetation due to timber/firewood collection

• Avoid introduction of new invasive species to, and spread of existing invasive species within, the project area, captured in an Invasive Species Management Plan, which, at the minimum, shall include:

- washing of vehicles, equipment and supplies before entry to the Project area

- monitoring for invasive species; and - control/eradication of invasive species where found - Cut only trees which are necessary. Ensure that the

vegetation is cleared as per terms and conditions of tree cutting permit

- Compliance with guidelines issued by the Indian Road Congress

- Immediately plant native grass and tree species on cut slopes to reduce erosion

- Prohibit collection, sale or purchase of timber/firewood by staff and contractors, with heavy penalties applied

EPC Contractor/

CSC/PIU

173

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

- all wood building material for workers’ housing should be brought from outside the project area;

- workers should be supplied with non-wood fuels such as kerosene or liquefied petroleum gas for the duration of the contract;

- Implement mandatory compensatory afforestation program to plant 47700 trees (@1:10) resulting in the improvement of tree cover in the area.

- Re-vegetation of tree cut from road side; -

6. Ecologically important areas

- Road widening activities within the ROW

- Use of construction equipment;

- Presence of labour camps

- road construction activities;

- the cutting for earthworks;

- quarrying, preparation and transfer of stone chips.

- degradation of aquatic habitat during construction from sedimentation, dust, sewage, or other construction waste along the river

- degradation of habitat from hydrological changes

- increase in animal and human conflicts in area due to road improvement

- Displacement of species due to noise, presence of machinery and equipment and presence of

- Use only existing licensed quarries outside for sourcing aggregates

- Avoid borrow pits in areas of Natural Habitat and within 200 m of waterways

- Only undertake earthworks during the dry season - Train staff and contractors in good environmental

practice, and prohibited activities - Ensure contractors supply all necessary food, cooking

fuel and appropriate housing - If any wild animal (except birds) comes within 100m from

the construction site, construction works must immediately stop and resume only after the wild animalhas moved away.

- The contractor will clearly brief the construction workers on strict forestry rules on illegal harvesting of forest products, poaching of wildlife and illegal fishing;

- Train staff and contractors in good environmental practice, and prohibited activities

- Employment agreements should specify heavy penalties for illegal hunting, trapping and wildlife trading (per Wildlife Act 1972) – all other ancillary works should also agree not to participate in such activities;

- Contractor will ensure supply of all necessary food items, cooking fuel and proper housing to prevent illegal hunting and tree felling;

Contractor CSC/PIU/Forest Department

174

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

construction workers.

- Injury and mortality of fishes due to underwater construction noise

- Strict anti-poaching surveillance measures need to be implemented, especially during project construction phase.

III. Social environment

7. Private land and buildings

- Temporary road diversions

- Traffic may have to be diverted across private land adjacent to the road.

- Financial compensation for loss of crops or replacement of damaged structures.

- After completion of the construction works the used land will be reinstated to the state it had before commencement of the works.

- Access to adjacent properties and agricultural land will be maintained, as necessary.

- Any damage to areas and infrastructure outside the agreed work sites (Corridor of Impact assessed in project RP) will be restored to pre-construction conditions and will be subject to compensation at contractor cost and through written agreement with the land owner, as applicable.

-

Contractor/ LARR Implementation Consultancy

PIU/LARR Monitoring Consultancy CSC

8. Public property/ infrastructure/ utility structures

- Traffic diversions and temporary road closures

- Hinder and nuisance for road users.

- Proper signs indicating the nature of the hazard/activity envisaged;

- Contractor will ensure that information on the timing of works and notifications of road closure (if any) is provided via the local media (radio, TV, newspaper etc.) or through the local community heads.

Contractor CSC/PIU

9. Noise and disturbance

- Operation of construction equipment and machinery,

- extremely high sound levels present real risk to the health of workers on- site;

- Installation of 3m noise barriers - Provision of proper PPEs for on-site workers; - In construction sites within 500 metres of a settlement,

noisy operations should cease between 22:00 and 06:00 hrs

Contractor CSC/PIU

175

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

hauling of materials and blasting works

- sensitive areas within 100 m the roadways will be affected temporarily;

- construction noise will affect the most communities living close to the construction zone

- To further minimize noise impacts near sensitive receptors (particularly schools), operation of excavator and other heavy machineries will be carried out mostly during off-hours (10:30 am to 3.30 pm) and on holidays (Saturday and Sundays) in consultation with the community and relevant local authorities.

- Regular maintenance of construction vehicles and machinery;

- Noise generating equipment and construction machinery will be equipped with acoustic enclosures and/or mufflers;

- Timely scheduling of construction activities and communication to affected receptors;

- Use of noise barriers where necessary - Baseline noise will be established for all sensitive areas

prior to construction - Follow up noise monitoring will be carried out during the

construction.

10. Vibration - Operation of

vibration rollers during ground preparation

- Model study shows buildings/structures within 4.5m from edge of the road will have major impact of vibrations;

- Model study shows sensitive receptors will encounter moderate impact of vibrations due to construction equipment

- Use of wave barriers where structures are within 4.5m from the edge of the road; mainly overhead water storage tanks along the road alignment

- inform occupants of dwellings near the edge of the road in a timely manner of the nature, duration and potential vibration effects of the works

Contractor CSC/PIU

176

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

11. Occupational health and safety

- Housing of up to 400 people for about two years with 2 labour camps

- Work in hazardous conditions

- Increase in the potential for the transmission of diseases and illnesses;

- Accidents and incidents due to hazardous working conditions

- Contractor must control the construction site, keep it clean and provide facilities such as dust bins and collectors for the temporary storage of all waste;

- The Contractor will be responsible for the safe removal and/or storage of all waste in order to prevent environmental pollution of any type that may be harmful to people or animals;

- All personnel working at vulnerable site locations will wear proper PPE like (but not limited to) safety helmets, eye and ear protection and strong footwear;

- Contractor must ensure that proper rescue equipment, fire extinguishers and first-aid equipment is available at all work locations at all times;

- Contractor must submit and obtain approval for a health and safety plan prior to the commencement of work, provide adequate health care facilities and arrange pre-employment medical screening and treatment (if required) and periodic health checks thereafter for employed personnel;

- support a public health education programme for workers and villagers covering road safety, malaria, hygiene, and sexually transmitted diseases with participation of the district health departments;

- construction workers to be given medical check-up including checks for COVID-19 symptoms before being allowed on site;

- provide PPE for workers in accordance with Building and other Construction Workers Act, 1996 requirement and Recommendation of Personal Protective Equipment According to Hazard in EHS Guidelines on OHS with additional PPE provided as needed for COVID-19 risks;

- ensure employees are able to take time off sick without being penalized, including any self-isolation for COVID-19 that is required.

Contractor CSC/PIU

177

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

- The used face mask for COVID-19 should be properly collected from the workers/ labours and same shall be handed over to the local body to dispose through Common Bio Medical Waste Treatment and Disposal Facility.

12. Community health and safety

- Presence of labour camps

- Conflict between community and migrant workers

- the contractor should provide the construction camps with facilities such as health care clinics, places of worship, and occasional entertainment;

- Contractor should maximize recruitment of local construction workers regardless of gender;

- Contractor will ensure affected communities are pre-informed of emergency procedures included in the agreed community health and safety plan and as appropriate given proximity of residents to works included in their mock drills etc.

- contractors staff and local communities will also be given awareness raising in COVID-19, HIV/AIDS, other communicable diseases, and sexual, exploitation, abuse and harassment with strict penalties (e.g. immediate removal from site) for any non-compliance of workers to an agreed code of practice

- display posters to promote handwashing and respiratory hygiene etc.

- wherever possible, the contractor should not discriminate and should proactively encourage the employment of suitably skilled women on the project.

Contractor CSC/PIU

C. OPERATION STAGE

I. Physical environment

1. Air quality and GHGs

- Increase in traffic volume

- Atmospheric dispersion modelling

- Increased levels of emission of typical transport related pollutants (PM 2.5, PM10, CO, SO2 and NOx)

- Proper and regular maintenance of roads to minimize air pollution due to reanimation of dust from the road

Contractor PIU

178

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

shows that the project is likely to cause air pollution concentrations exceeding the National Ambient Air Quality Standards of CPCB as well as IFC EHS standards in the next 15 years due to higher background concentrations in the project area. In fact, the project has been shown to decrease GHG compared to BAU levels with increased road width and better road conditions.

- 2. Surface water

quality and quantity

- Functionality of implemented

- Unexpected erosion and siltation in major water bodies

- Periodic surveillance to check on siltation of major water bodies due to the completed road works

Contractor PIU

179

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

mitigation measures

II. Biological environment

1. Trees and terrestrial vegetation

- Status of tree cover improved under the project to achieve net gain of terrestrial vegetation

- low survival rate of trees planted

- Poor performance of habitat improvement activities

- Monitor the tree plantation of 47700 trees. Take remedial measures to ensure minimum 70% survivability rate after three years

- Check the effectiveness of additional habitat improvement activities and make adjustments and revisions to improve effectiveness.

Contractor .

PIU

2. Terrestrial fauna

- Effectiveness of implemented mitigation measures

- Displacement of species due to noise from normal traffic or maintenance activities

- Increased poaching from increased traffic through the area.

- Mortality of individuals due to vehicle collision

- Unforeseen human-animal conflicts

- Periodic surveillance and maintenance works to ensure that the green belt along the road and measures for soil erosion are effective to control water pollution along river banks and canals

PIU/ Forest Dept.

Forest Dept

III. Social environment

180

Activity/Valued Environment Component

Negative Impact Mitigation Measure Responsibility Implementation Supervision

1. Noise - Increase in

traffic volume

- Unexpected hindrance experienced by sensitive receptors

- Constructing/instituting of additional noise abatement measures such as noise barriers at sensitive receptor locations

Contractor PIU

2. Vibration - Road use by

heavy trucks

- Nuisance experienced by occupants of dwellings near the edge of the road

- Periodic maintenance of pavement to eliminate the discontinuities

Contractor/PIU PIU

3. Community Health and Safety

- Improved road

- Risk of accidents due to increased traffic

- Monitoring of road accidents to determine whether improvement of road safety features is necessary

PIU/EPC Contractor

PIU

CSC: Construction Supervision Consultant, EA: Executing Agency, CPCB: Central Pollution Control Board, EMP: Environment management Plan, EMOP: Environment Monitoring Plan, IRC: Indian Road Congress, CKIC: Chennai-Kanyakumari Industrial Corridor, MORTH: Ministry of Road Transport and Highways

181

Table 59: Environmental Monitoring Plan (EMoP)

Environmental Features / Stage

Parameters and Standards Location Frequency Duration

Action Plan in case criteria exceeds the standards

Responsible party

Implementation Supervision

Air Quality and Noise Levels

Pre-construction Stage

• PM2.5, PM10, SO2, NOx, CO, HC (Ambient Air quality standards published in 2009)

• Leq - Noise levels on dB (A) scale (MOEFCC Noise Rules, 2000(Ambient Noise Standards)) compared with IFC EHS

• Along the project road at different zone as suggested by CSC for regular monitoring

• At construction camps, hot mix plant and equipment yards locations

Once prior to start of construction

Continuous 24 hours/ or for 1 full working day

Noise day time and noise night time

Include additional measures in the EMP

Provide noise barriers

Contractor

Through approved monitoring agency

CSC, PIU

Construction Stage

• PM2.5, PM10, SO2, NOx, CO, HC (Ambient Air quality standards published in 2009)

• Leq - Noise levels on dB (A) scale (MOEFCC Noise Rules, 2000(Ambient Noise Standards)) compared with IFC EHS

• Wherever the contractor decides to locate the Hot mix plant

• Along the project road at different zone as suggested by CSC for regular monitoring

• At hot mix plant and equipment yards

Once in a quarter excluding monsoon months for construction period

Continuous 24 hours/ or for 1 full working day

Check and modify control devices like bag filter/cyclones of hot mix plant

Provide additional noise barriers

Contractor

Through approved monitoring agency

CSC, PIU

Operations Stage

• PM2.5, PM10, SO2, NOx, CO, HC (Ambient Air quality standards published in 2009)

• Leq - Noise levels on dB (A) scale (MOEFCC Noise Rules, 2000(Ambient Noise Standards)) compared with IFC EHS

Along the project road at different zone as suggested by CSC for regular monitoring

Once in a quarter excluding monsoon months for 2 years

Continuous 24 hours/ or for 1 full working day

- Contractor

Through approved monitoring agency

CSC, PIU

182

Environmental Features / Stage

Parameters and Standards Location Frequency Duration

Action Plan in case criteria exceeds the standards

Responsible party

Implementation Supervision

Water Quality

Construction Stage

pH, Temperature, DO, Oil & Grease, Conductivity, TSS, TDS, Alkalinity, Total Hardness, Calcium, Magnesium Chloride, Phosphate, Sulphate, Nitrate, COD, BOD, Iron, Total Coliform, Faecal Coliform, Salinity (Indian Standards for Inland Surface Waters (IS: 2296, 1982) and for Drinking Water (IS: 10500 - 2012))

At identified locations Once in a quarter excluding monsoon month for construction period

- Check and modify petrol interceptors, Silt fencing devices.

Contractor

Through approved monitoring agency

CSC, PIU

pH, Temperature, Conductivity, TSS, TDS, Alkalinity, Total, Hardness, Calcium, Magnesium Chloride, Phosphate, Sulphate, Nitrate, Iron. (Indian Standards for Inland Surface Waters (IS: 2296, 1982) and for Drinking Water (IS: 10500 – 2012))

At identified locations Once in a quarter excluding monsoon for construction period

- Check and modify petrol interceptors, Silt fencing devices.

Contractor

Through approved monitoring agency

CSC, PIU

Operation Stage

pH, Temperature, DO, Oil & Grease, Conductivity, TSS, TDS, Alkalinity, Total Hardness, Calcium, Magnesium Chloride, Phosphate, Sulphate, Nitrate, COD, BOD, Iron, Total Coliform, Faecal Coliform, Salinity ((Indian Standards for Inland Surface Waters (IS:

At identified locations along the project road

Once in a quarter

excluding monsoon for 2 years

- Check and modify petrol interceptors, Silt fencing devices.

Contractor

Through approved monitoring agency

CSC, PIU

183

Environmental Features / Stage

Parameters and Standards Location Frequency Duration

Action Plan in case criteria exceeds the standards

Responsible party

Implementation Supervision

2296, 1982) and for Drinking Water (IS: 10500 - 2012))

pH, Temperature, Conductivity, TSS, TDS, Alkalinity, Total, Hardness, Calcium, Magnesium Chloride, Phosphate, Sulphate, Nitrate, Iron. (Indian Standards for Inland Surface Waters (IS: 2296, 1982) and for Drinking Water (IS: 10500 - 2012))

At identified locations along the project road

Once in a quarter

excluding monsoon for 2 years

- Check and modify petrol interceptors, Silt fencing devices.

Contractor Through approved monitoring agency

CSC, PIU

Soil Quality

Construction Chemical properties including oil and grease and PAH

At identified locations in construction camp & plants and along the project road section

Once in a quarter excluding monsoon months for construction period

- Check oil and chemical spillage

Contractor Through approved monitoring agency

CSC, PIU

Operation Chemical properties including oil and grease

At identified locations along the project road

Once in a quarter excluding monsoon months for 2 years

- Check oil and chemical spillage

Contractor Through approved monitoring agency

CSC, PIU

Accidental and Health and Safety

Construction No. of accidents or near miss involving workers.

All along the road and construction activities areas

Once in 3 months

- Corrective measures

Contractor CSC, PIU

Operation No. of accidents or near miss involving workers.

All along the road Once in 3 months

- Corrective measures

Contractor PIU

184

Environmental Features / Stage

Parameters and Standards Location Frequency Duration

Action Plan in case criteria exceeds the standards

Responsible party

Implementation Supervision

excluding for 2 years

Tree Plantation

Operation Survival rate of plants All along the project corridor

1 samples (quadrants) for each km

Once every year after monsoon for 3 years

Corrective measures

Forest department

CSC/PIU,

Note: PIU – Project Implementation Unit (of CKICP), CSC- Construction Supervision Consultant

185

E. Institutional Requirements

418. The Highways and Minor Ports Department (TNHD) of Government of Tamil Nadu will be the Executing Agency (EA) for the project and the Implementing Agency (IA) will be the CKICP. A Project Implementation Unit (PIU) has been established within CKICP to implement the project. EA together with IA will be responsible for the implementation of the Project. The Project Director of PIU will be overall responsible for EMP implementation. The following key players are involved in EMP implementation during construction stage:

• TNHD as Project executing agency • CKICP-PIU as project PIU and its environmental wing; • Project Management Services (PMS) and Construction Supervision Consultants

(CSC) and their representatives; and • Contractors.

419. The PIU is headed by a Project Director and supported by Chief Engineer and Superintending Engineer, and Engineering unit, Land Acquisition And Resettlement & Rehabilitation (LARR) unit, Environmental wing, and Audit/ Finance unit. The environment wing has an Environmental Cell and Forest Wing headed by an Environment Specialist and Assistant Conservator of Forests, respectively. The environmental wing is composed of Assistant Environment Specialist, Forest Ranger, and Foresters, along with support staff to conduct monitoring and provide support to the Field Implementation Units (FIU) to ensure the quality of EMP implementation. The PIU Environmental Wing shall be responsible for the review and final approval of Health and Safety Plans based on the latest guidelines issued by concerned government agencies as well as national and international best practices. The PIU will conduct at least quarterly site monitoring or more frequently as the need arises. The PIU with the support of the PMS of construction supervision consultants will review all environmental monitoring reports prepared by the contractor and the consultants. The PIU will ensure that semi-annual environmental monitoring reports are submitted within 3 calendar months from the end of the respective reporting period to ADB for disclosure on the ADB website. FIUs will have one nominated social and environmental safeguards focal who will be will be present on site on a day-to-day basis and shall ensure the reports submitted by the contractor and the construction supervision consultants are consistent with site conditions.

420. PMS team will include environment, health and safety (EHS) Specialist whose role will be to support the PIU in monitoring the implementation of environmental safeguards under the project. The CSC will have an Environmental Specialist (ES) in its team, and it will liaise with PIU environmental wing through the FIU to ensure that Contractor complies with the requirements of various environmental safeguard measures through supervision, monitoring and reporting on the same. Efforts must be made by the CSC to ensure that environmental mitigation and good-construction-practices are not only considered but actually implemented as integral component of each civil activity. It should be considered as day-to-day activity. Implementation of wildlife and environmental safeguard measures needs team effort and as such the Team Leader of CSC will delegate the responsibilities to each member of the supervision team with respect to their core responsibilities. The project should have a provision of Environmental Specialist within CSC to supervise implementation of safeguard measures. ES role would be more on advisory. He will assist the Team Leader of CSC on the following:

• Advise PIU through the FIU and PMS on preparing reports to ADB and other statutory

bodies; • Preparing procedures for implementing EMP;

186

• Review Contractor’s Construction EMP (CEMP), traffic management plan and safety plan and recommend for its approval / improvements, to the Team Leader;

• Provide training to FIU, PIU, CSC and Contractors’ staff on implementing environmental safeguard measures;

• Advise on obtaining various statutory environmental clearances on time; • Conduct at least weekly field visits to examine environmental compliances and

suggest corrective actions; and • Address any other issues as will be required to ensure environmental compliance.

421. The Environmental Expert within CSC will be responsible for monitoring implementation of the biodiversity conservation activities to be implemented by the contractor during project construction and until the end of the contractor’s defect liability period. He/she will conduct quarterly monitoring during project construction and provide inputs to the semi-annual environmental monitoring reports.

422. Besides, the Team Leader of CSC will nominate a senior engineer from the site office for being directly responsible for day-to-day supervision of implementation of stipulated safeguard measures, to ensure accountability. He will provide guidance to the field staff of CSC and Contractor for implementing each of the activities as per the EMP. He will be responsible for record keeping, providing instructions through the Engineer for corrective actions, ensuring compliance of various statutory and legislative requirements and assist Engineer for submitting reports to PIU. He will maintain a close co-ordination with the Contractor and PIU for successful implementation of the environmental safeguard measures.

423. An external monitoring agency will be engaged to conduct third party monitoring on implementation of environment safeguards and biodiversity related activities for the sensitive roads (SH191, SH63, and SH40-II).

424. Responsibilities of various agencies involved in the project implementation are described in following paragraphs.

425. Highways and Minor Ports Department (TNHD): As the executing agency TNHD’s responsibilities will mainly be focused on addressing national or state level environment safeguard issues and decisions concerning the projects. Specific responsibilities on environment safeguards at the executing agency level are:

• Ensure that all environment safeguard requirements as given in ADB SPS 2009, and applicable laws and rules under MOEFCC are being complied with during all stages of respective project under the loan.

426. Project Implementation Unit (PIU): TNHD CKICP will be the implementing agency for the project. A PIU within CKICP will be responsible for implementing environment safeguard requirements in accordance with the IEE and EMP at the project level whereas site level work will be monitored by Field Implementation Units (FIU). Specific responsibilities on environment safeguards of the PIU and FIUs are (both if not specified):

• The PIU will ensure timely recruitment and mobilization of the environmental

specialist as well as health and safety officer under the CSC and the external monitor. • The PIU and FIUs will coordinate to ensure timely processing of forestry clearances,

tree cutting permits, and other similar clearances and permits required for the project.

187

• primary responsibility per jurisdiction will fall on respective FIU. • FIU will coordinate with the Forestry Department on biodiversity monitoring and

habitat improvement activities. • PIU will review the budgetary needs for complying with the Government’s and ADB’s

requirements on environment safeguards and ensure the proposed budget is available.

• Prepare forms, reports and all documents, etc. for processing of environmental, forestry and related clearances in a timely manner and submit them for further review and signing to the authorized officer in the respective executing agency office.

• If any problems or long delays are encountered when processing the clearance documents, immediately alert the authorized officer at the executing agency level and seek ways resolve the problem at the soonest.

• Ensure that all necessary regulatory clearances are obtained prior to commencing any civil work of the respective road section.

• The PIU will ensure that the most recent version of the EMP (including biodiversity conservation measures) and EMOP which include required mitigation measures and monitoring requirements with defined Bill of Quantity (BOQ), forms part of contractor’s agreement.

• Ensure that contractor have access to the IEE report including EMP, and EMOP. • The FIU will ensure that the Engineering Procurement and Construction (EPC)

contractor updates the EMP, EMOP based on detailed design and prepare CEMP. • Ensure that contractor understand their responsibilities to mitigate environmental

problems associated with their construction activities. • The FIU will ensure and monitor that all required permits, no objection certificates

etc. are obtained by the contractor for establishment and operation of equipment and facilities as detailed in the IEE.

• The FIU, with the support of the environmental Engineer of the contractor and CSC ensure that the contractor implements the EMP (including biodiversity conservation measures) and EMOP as given in the latest version of the IEE report.

• In case of unanticipated environmental impacts during project implementation stage, with the support of CSC prepare and implement an updated EMP to account for such impacts after seeking concurrence from ADB. The updating shall be carried out after due consultation with the stakeholders and concerned government agencies.

• In case during project implementation if the project needs to be redesigned or there are unanticipated environmental impacts, the PIU will immediately inform ADB and jointly agree on whether the IEE needs to be revised or whether only the EMP and/or EMOP needs to be revised.

• Conduct regular (at least quarterly for PIU and at least weekly for FIUs) site visits to ensure that the contractor is complying with the EMP, EMOP and the CSC is conducting regular supervision and monitoring as outlined below in the next paragraph.

• Ensure effective implementation of Grievance Redress Mechanism to address affected people’s concerns and complaints.

• With the support of CSC and contractor, conduct public consultations during project construction to seek feedback of the local community people and ensure that the project is not having adverse impacts on them.

• The PIU, with the help of respective FIU, will review, verify and endorse the monthly, quarterly and semi-annual environmental monitoring reports submitted by the CSC and PMS.

188

• The PIU, with the help of respective FIU, will review and endorse the semi-annual environmental monitoring reports submitted by the external monitor.

• Once deemed satisfactory, the PIU will submit consolidated semi-annual environmental monitoring reports submitted by the PMS and external monitor to ADB and make these reports available for public disclosure.

• The FIU will review and approve all environment safeguards related documents such as updated IEE, monitoring reports etc. prepared for project with recommendations and clarifications from the implementing agency where necessary.

• The PIU will ensure timely endorsement and signing of key documents and forwarding to the respective agency such as those required for processing of wildlife clearance, forestry clearance etc. and disclosure on ADB website.

• Take proactive and timely measures to address any environment safeguards related challenges at the national or state level such as delays in processing of clearances (during pre-construction stage), significant grievances (during construction stage).

• The PIU will recruit an external monitor to conduct third party environmental monitoring for the project.

• The PIU will submit all reports including consolidated semi-annual environmental monitoring report and external monitoring reports to ADB.

• Safeguards focals of FIUs will inspect field work at field level.

427. Project Management Service (PMS): Project management support, including safeguards implementation, will be provided to the PIU by one of the construction supervision consultants (CSC-01). The project management service (PMS) team of CSC-01 will include environment, health and safety (EHS) expert and resettlement specialists whose role will be to support the PIU in monitoring the implementation of environmental and social safeguards under the project. Details of EHS related responsibilities of the PMS are provided below.

• Support the PIU in monitoring the implementation of environmental and social

safeguards under the project • Review and clear contractors’ Health and Safety Plans which shall include COVID19

measures and submit it to the PIU for further assessment and final approval; • Review the environmental monitoring reports submitted by the construction

supervision consultants and the contractors; and • Consolidate the monitoring reports submitted by the CSCs into semi-annual

environmental monitoring reports for submission to PIU for their review and endorsement for further submission to ADB.

428. Construction Supervision Consultant (CSC): The CSC will support the PIU to supervise and monitor environment safeguard requirements in accordance with the IEE, EMP, and EMOP. The CSC will include an environmental specialist. Details of environment safeguards related responsibilities of the CSC are provided below.

• Conduct continuous check on the status of environment safeguards in relation to air,

noise, water, soil, occupational health and safety, and ecological activities and mitigation measures.

• Based on site visits (monthly) and monthly reports submitted by the contractor prepare monthly environmental monitoring reports for the review and approval of PIU.

189

• Compile the monthly monitoring reports into semi-annual environmental monitoring reports and submitted and further submission to ADB for disclosure on the ADB website.

• In coordination with PIU through FIU, ensure that all necessary regulatory clearances are obtained prior to commencing any civil work of the respective road section.

• Ensure that the EPC contractor updates the EMP and EMoP based on detailed design, prepares CEMP, and implements them properly.

• Ensure that the EPC contractor updates the biodiversity components of the EMP and EMoP based on detailed design and implements them properly.

• Ensure that the EPC contractor designs and constructs measures suggested in the road section in areas near to protected areas.

• Review and approve environment related sub plans such as camp layout plan, traffic management plan, borrow area management plan, construction debris management plan etc. to be submitted by the contractor.

• Provide technical guidance to the contractor to ensure they understand their responsibilities to mitigate environmental problems associated with their construction activities.

• Provide training to FIU, PIU, CSC and Contractors’ staff on implementing environmental safeguard measures.

• Ensure and monitor that all required permits, no objection certificates etc. are obtained by the contractor for establishment and operation of equipment and facilities as detailed in IEE.

• In case of non-compliances with the EMP and EMOP prepare a corrective action plan and ensure it is implemented

• In case during project implementation if the project needs to be redesigned or there are unanticipated environmental impacts immediately inform the PIU and provide recommendation on whether the IEE and EMP and EMOP needs to be revised.

• Support the PIU to ensure effective implementation of Grievance Redress Mechanism to address affected people’s concerns and complaints.

• Ensure regular consultations are taking place with affected communities and key stakeholders during construction as well as operation phases of the project.

• Review and verify all environmental reports prepared by contractor. Based on site inspections and environmental reports from the contractors, prepare quarterly environmental monitoring reports for submission to the PIU. Consolidated quarterly reports into a semi-annual environmental monitoring report and submit it to the PIU.

429. External Monitor: The External Monitor will conduct third party monitoring of environment safeguard and biodiversity conservation activities. The following are a summary of the key responsibilities of the External Monitor.

• Review the IEE, EMP and Biodiversity Action Plans with the Biodiversity and Critical

Habitat Assessment report to understand the background environmental and biodiversity issues of the project.

• Conduct third party monitoring of the implementation of the EMP, EMOP and biodiversity conservation activities by the contractor and supervisory activities of the CSC through quarterly site visits and review of environment safeguard and biodiversity conservation related documents maintained by the contractor, CSC and PIU.

• Advise the PIU on the need for corrective actions if any.

190

• The External Monitor must not be involved in the day to day implementation and supervision of environment safeguards and biodiversity conservation activities under the project.

• Based on the observations from the site visits and review of documents and monitoring reports prepared by the contractor and CSC, prepare semi-annual reports for submission to the PIU and onward to ADB for disclosure on the ADB website.

430. ADB: ADB is responsible for the following:

• Review IEE report and disclose the draft and final reports on the ADB website as required;

• Issue project’s approval based on IEE report; • Monitor implementation of the EMP through due diligence missions; • Provide assistance to the executing agency and implementing agency of project, if

required, in carrying out itsresponsibilities and for building capacity for safeguard compliance; and

• If necessary provide further guidance to the implementing agency on the format, content, and scope of semi-annual monitoring reports for submission to ADB.

431. Contractor: For ensuring that EMP is properly implemented, Contractor shall appoint a full time qualified and experienced Environmental Officer (EO) and a Health and Safety Officer (HSO) from the commencement to completion of the project. These experts will be recruited within 30 days of contract signing.

432. The responsibilities of EO&HSO of Contractor will include the following:

• Directly reporting to the Project Engineer of the Contractor; • Discussing various environmental issues and environmental mitigation,

enhancement and monitoring actions with all concerned directly or indirectly; • Prepare Contractor’s Construction EMP (CEMP), traffic management plan and safety

plan and other environmental subplans, as part of their Work Program; • Ensure contractor’s compliance with the EMP stipulations and conditions of statutory

bodies; • Assisting his project Engineer to ensure environmentally sound and safe construction

practices; • Assisting the project Engineer to ensure the timely procurement of materials that are

included in the Bill of Quantities relating to environmental mitigation and enhancement measures;

• Conducting periodic environmental and safety training for contractor’s engineers, supervisors and workers;

• Preparing a registers for material sources, labour, pollution monitoring results, public complaint and as may be directed by the Engineer;

• Coordinate closely with the construction supervision consultants on climate and disaster risk adaptation measures;

• Assisting the PIU on various environmental monitoring and control activities including pollution monitoring;

• Preparing and submitting monthly reports to CSC on status of implementation safeguard measures; and

191

• SHO will be responsible for H&S Plan preparation and implementation, with particular attention to COVID 19.

433. As mentioned above, there will be a need for capacity building of PIU on various environmental and social aspects of the project through various environmental training. Recently, there has been change of statutory requirements for these similar projects based on new EIA Notification. This has changed the landscape of legal and administrative framework for implementing the projects. Thus, there is a need for the PIU staff to updating the information and keeping abreast with the changing legal and administrative requirement, and requirements of various statutory permits and clearances. For successful implementation of EMP, it is essential to orient engineers of PIU, FIUs, CSC and Contractor who would be mobilized for this project. One day environmental orientation workshop will be organized by the PIU (with support from ADB TA consultant, if required) after most staff of the CSC and contractor has been mobilized.

F. Environmental Reporting System

434. The reporting system will operate linearly with the contractor who is at the ground level of the implementation system reporting to the CSC, who in turn shall report to the PIU and FIUs. All reporting by the contractor and CSC shall be on a monthly basis. The CSC will compile the monthly reports into quarterly reports and then semi-annual environmental monitoring reports and submit them to the PIU. The PIU shall be responsible for preparing targets for each of the identified EMP activities. The environmental specialist of the PMS will consolidate semi-annual monitoring reports submitted of CSCs into semi-annual environmental monitoring reports for submission to PIU for their review and endorsement for further submission to ADB.

435. The PIU will review and endorse the monthly and semi-annual environmental monitoring reports submitted by the PMS and CSC. The PIU through TNHW will forward the consolidated semi-annual environmental monitoring reports to ADB for disclosure on the ADB website during the project construction period. The PIU will compile and submit consolidated annual environmental monitoring reports to ADB during the project operation stage until the Project Completion Report (PCR) is finalized.

436. During the implementation period, a compliance report may include description of the items of EMP, which were not complied with by any of the responsible agencies. It would also report to the management about actions taken to enforce compliance. It may, however, be noted that certain items of the EMP might not be possibly complied with for a variety of reasons. The intention of the compliance report is not to suppress these issues but to bring out the circumstances and reasons for which compliance was not possible (such as jurisdictional issues). This would help in reinforcing the implementation of the EMP. Photographic records will also be established to provide useful environmental monitoring tools. A full record will be kept as part of normal contract monitoring. Reporting and Monitoring Systems for various stages of construction and related activities have been proposed to ensure timely and effective implementation of the EMP.

437. A summary of the key environment safeguards activities and reporting system to be followed under the project is provided in the Table 60 below.

192

Table 60: Environmental Reporting System Activity Responsibility Outputs Deliverable to

ADB Period

Appointment of Contractor Environmental Focal Person (EFP)

Contractor Appointment letter submitted to PIU through CSC

Included in semi-annual environmental monitoring report

At least 45 days before start of construction

Induction training of contractors

CSC

Training materials and training proceedings

Included in semi-annual environmental monitoring report

At least 30 days before start of construction

On-site training and field level guidance

CSC

Records of training and field level guidance provided

Included in semi-annual environmental monitoring report

Continuously as needed during construction

Monthly reporting Environmental self-monitoring report

Contractor Completed checklist submitted to CSC and PIU

None

Monthly after commencement date

Site inspection

CSC, PIU, FIU

Inspection report prepared for inclusion in monthly monitoring report

None Monthly after commencement date

Quarterly reporting Site inspection CSC Inspection report on

findings of biodiversity monitoring

CSC to submit to PIU and ADB

Quarterly after commencement

Site inspection

External monitor (for sensitive roads)

Inspection report submitted to PIU for review and endorsement

None

First inspection within 3 months of commencement

Semi-annual Semi-Annual Monitoring report

CSC

Consolidated monitoring reports submitted to PIU for review and endorsement

PIU to further submit to ADB for disclosure on ADB website

No later than 3 months after reporting period

Consolidated Semi-annual monitoring report

PMS Consolidated monitoring reports submitted to PIU for review and endorsement

PIU to further submit to ADB for disclosure on ADB website

No later than 3 months after reporting period.

CSC: Construction Supervision Consultant; PIU: Project Implementation Unit G. Environmental Management Budget

438. An environmental management budget of INR 193.50 million (US$ 2.582 million) has been estimated for implementation of the environmental management plan. This budget also includes cost of environmental monitoring and associated trainings. A detail of environmental management budget is given in Table 61.

193

Table 61: Environmental Management Cost Estimates*

A. Cost Estimate for Environmental Management - SH 115

SL. No. ITEM DESCRIPTION QUANTITY UNIT RATE (Rs.)

AMOUNT (Rs.)

RESPONSIBILITY

A. Tree cutting and Compensatory Afforestation Plantation

A.1 Payment of tree Compensation for plantation of 47160 trees PIU through EPC Contractor

A.1.1 Compensatory Afforestation/Plantation (Covered under regulatory clearance, Engineering cost)

47160 No. 2600 122616000

B. Environmental Monitoring

B.1 Ambient air quality monitoring during pre-construction, construction and operations phases

201 No. 8000 1608000

B.2 Ambient noise level monitoring during pre-construction, construction and operations phases

222 No. 3000 666000

B.3 Water quality monitoring of surface water during construction and operations phases

81 No. 6000 486000

B.4 Water quality monitoring of drinking water (Groundwater) during construction and operations phases

36 No. 5000 180000

B.5 Soil quality monitoring during construction and operations phases

90 No. 6000 540000

B.6 Monitoring survival rate of plantation 8 No. 20000 160000

Sub-Total(B) 3640000

194

C. Enhancement of environmental improvement in the project alignment as directed by project authority including the following items

Contractor through BOQ

C.1 Oil Interception 3 No. 15000 45000

C.2 Rainwater harvesting cum recharge pits @1 structure per Km

64 No. 50000 3200000

C.3 Silt fencing 1745 Rm. 1200 2094000

C.4 School (Noise Barrier Wall) 5 No 150000 750000

C.5 Enhancement Measures for Surface water Bodies (Ponds enhancements)

11 No 5000000 55000000

Sub-Total(C) 61089000

D. Environmental Training  

D.1 Training at site as mentioned in IEE report. 1 Lumpsum 1000000 1000000 PIU through CSC

Grand Total (A+B+C+D) 188345000

B. Cost Estimates for Environmental Management – ECR link

SL. No. ITEM DESCRIPTION QUANTITY UNIT RATE (Rs.)

AMOUNT (Rs.)

RESPONSIBILITY

A. Tree cutting and Compensatory Afforestation Plantation

A.1 Payment of tree Compensation for plantation of 540 trees PIU through EPC Contractor

A.1.1 Compensatory Afforestation/Plantation (Covered under regulatory clearance, Engineering cost)

540 No. 2600 1404000

B. Environmental Monitoring

195

B.1 Ambient air quality monitoring during pre-construction, construction and operations phases

30 No. 8000 240000

B.2 Ambient noise level monitoring during pre-construction, construction and operations phases

30 No. 3000 90000

B.3 Water quality monitoring of surface water during construction and operations phases

15 No. 6000 90000

B.4 Water quality monitoring of drinking water (Groundwater) during construction and operations phases

24 No. 5000 120000

B.5 Soil quality monitoring during construction and operations phases

15 No. 6000 90000

Sub-Total(B) 630000

C. Enhancement of environmental improvement in the project alignment as directed by project authority including the following items

Contractor through BOQ

C.1 Oil Interception 1 No. 15000 15000

C.2 Rainwater harvesting cum recharge pits in urban area 4 No. 50000 200000

C.3 Silt fencing 57 Rm. 1200 68400

C.4 School (Noise Barrier Wall) 1 No 120000 120000

C.5 Enhancement Measures for Surface water Bodies (Ponds enhancements)

1 No 1850000 1850000

Sub-Total(C) 2253400

D. Environmental Training  

D.1 Training at site as mentioned in IEE report. (cover under SH-115 section)

0 Lump Sum

500000 0 PIU through CSC

Grand Total (A+B+C+D) 4287400

196

C. Cost Estimates for Environmental Management – Vandhavasi Bypass

SL. No. ITEM DESCRIPTION QUANTITY UNIT RATE (Rs.)

AMOUNT (Rs.)

RESPONSIBILITY

A. Tree cutting and Compensatory Afforestation Plantation

A.1 Payment of tree Compensation for plantation of 0 trees PIU through EPC Contractor

A.1.1 Compensatory Afforestation/Plantation (Covered under regulatory clearance, Engineering cost) 0 No. 2600 0

B. Environmental Monitoring

B.1 Ambient air quality monitoring during pre-construction, construction and operations phases

18 No. 8000 144000

B.2 Ambient noise level monitoring during pre-construction, construction and operations phases

18 No. 3000 54000

B.3 Water quality monitoring of surface water during construction and operations phases

12 No. 6000 72000

B.4 Water quality monitoring of drinking water (Groundwater) during construction and operations phases

6 No. 5000 30000

B.5 Soil quality monitoring during construction and operations phases

12 No. 6000 72000

Sub-Total(B) 372000

C. Enhancement of environmental improvement in the project alignment as directed by project authority including the following items

Contractor through BOQ

C.1 Oil Interception 1 No. 15000 15000

C.3 Silt fencing 57 Rm. 1200 68400

Sub-Total(C) 83400

197

D. Environmental Training  

D.1 Training at site as mentioned in IEE report. 0 Lump Sum

500000 0 PIU through CSC

Grand Total (A+B+C+D) 455400

D. Cost Estimates for Environmental Management – Chetpet Bypass

SL. No.

ITEM DESCRIPTION QUANTITY UNIT RATE (Rs.)

AMOUNT (Rs.)

RESPONSIBILITY

A. Tree cutting and Compensatory Afforestation Plantation

A.1 Payment of tree Compensation for plantation of 0 trees PIU through EPC Contractor

A.1.1 Compensatory Afforestation/Plantation (Covered under regulatory clearance, Engineering cost) 0 No. 2600 0

B. Environmental Monitoring

B.1 Ambient air quality monitoring during pre-construction, construction and operations phases

18 No. 8000 144000

B.2 Ambient noise level monitoring during pre-construction, construction and operations phases

18 No. 3000 54000

B.3 Water quality monitoring of surface water during construction and operations phases

12 No. 6000 72000

B.4 Water quality monitoring of drinking water (Groundwater) during construction and operations phases

6 No. 5000 30000

B.5 Soil quality monitoring during construction and operations phases

12 No. 6000 72000

Sub-Total(B) 372000

198

C. Enhancement of environmental improvement in the project alignment as directed by project authority including the following items

Contractor through BOQ

C.1 Oil Interception 1 No. 15000 15000

C.2 Silt fencing 24 Rm. 1200 28800

Sub-Total(C) 43800

D. Environmental Training  

D.1 Training at site as mentioned in IEE report. 0 Lumpsum

500000 0 PIU through CSC

Grand Total (A+B+C+D) 415800

E. Summary of Cost Estimates for Environmental Management

Sl. No. Component Amount (Rs.)

1. SH-115 (Cheyyur - Vandavasi - Polur Road Section 188345000

2. ECR Link (Cheyyur - Panayur Road) 4287400 3. Vandavasi Bypass 455400 4. Chetpet Bypass 415800

Total Amount (Rs.) 1,93,503,600

* Cost estimate is preliminary based on the current unit rates. Therefore, this estimate is tentative only.

199

X. CONCLUSIONS AND RECOMMENDATIONS

439. The project proposed for the improvement is classified as environment Category B project as per ADB SPS requirements. As per GOI requirements state highway road do not fall in the purview of EIA Notification 2006 of MOEFCC, therefore as per GOI norms environmental clearance is not required for this project. For ADB the categorization has been done based on environmental screening and assessment of likely impacts. While the environmental assessment ascertains that it is unlikely to cause any major significant environmental impacts, some impacts were identified attributable to the proposed project, all of which are localized and temporary in nature and easy to mitigate.

440. Road widening will be confined within the available RoW with minimum additional land acquisition. There is no presence sensitive environmental issue like wildlife sanctuary, national park, bio reserve, along the project road alignment and most of water body crossed by the road are non-perennial in nature.

441. The road section does not pass through any protected area, wildlife sanctuary, national park. There are no ecologically sensitive areas along the project road neither there are any archaeological/protected monument located in the vicinity of project corridor. The land use pattern around the proposed alignment is predominantly agricultural except in patches of section where land use predominantly mix of built-up and agriculture land.

442. The potential adverse impacts of the road sections upgrading are:

• Impacts on surrounding area due to tree cutting (4,770) for the proposed widening; • Impacts due to conversion of about 41.983 hectare of private land for road widening

purpose • Temporary impact on land and air environment due to locating construction camp; • Temporary impact on land, air and water environment due to establishing and

operating construction plants (Hot Mix Plant and Diesel Generator [DG] sets); • Impacts on trees due to removal on section of road with realignment and proposed

bypass; • Impact on air quality, water quality, drainage, road users due to construction activities

of project road; • Impact on land and water environment due to improper disposal waste water and

improper disposal of solid waste generated from camps and construction activities; and

• Impact on occupational health and safety due to all on-site and off-site construction works, and

• Induced cumulative impact on noise levels and air quality due to increase in traffic.

443. Measures such as use of EFRC i.e. slope protection measures are proposed to minimize the impacts of slope instability, compensatory afforestation @ 1:10 ratio, engineering alternatives to limit impacts on forest areas etc. are proposed to minimize the potential impacts.

444. Besides, series of mitigation measures have been proposed that are described in the IEE Report and addressed comprehensively in the environmental management plan. These include use of spoil disposal areas to minimize destruction of land forms along the alignment, proper sizing of hydraulic structures to assure adequate capacity and prevent destruction of adjacent land, provision of sign boards and noise barriers at sensitive receptor’s locations, identification of

200

vulnerable community infrastructure that must be preserved or replaced under construction contracts, identification of sensitive receptors and consultation of affected persons prior to finalization of road design to incorporate noise abatement measures, limits on location and access of workers and other provisions regarding construction to assure minimum impact, and other basic provisions on air pollution control, noise control, waste management as found in the EMP. All the above observations and mitigation measures will be included in the tender documents for contract works and the final contract agreement.

445. Application of these measures in parallel with MoRTH environmentally friendly road construction practices will reduce significantly any potential environmental impact. Impacts remaining on the physical environment (air and water pollution) are temporary and often occur away from the presence of people.

446. A systematic approach for surveillance and monitoring is provided by means of a management framework, and monitoring and reporting protocol. In general, the project received good support from local people. The local people appreciated that besides providing an all-weather efficient connectivity to large rural populations and improving the traffic scenario in the region, it will bear out several other socio-economic positive benefits. Follow-up public consultation is intended to provide future input to the identification of environmental impact during the construction phase as well as a grievance redress mechanism for project affected persons. The EMP is a living document and the same will be revised if necessary during project implementation or if there is any change in the project design and with approval of ADB during the construction period. The environmental mitigation measures are itemized in the EMP and the PIU shall ensure that EMP and EMoP are included in Bill of Quantity (BOQ) and forms part of bid document and civil works contracts for each package.

447. Before the start of civil works for the any section of the project road, the project proponent (TNHD and CKICP-PIU-ADB) must obtain necessary clearances / permits from statutory authorities.

448. Environmental benefits of the proposed road improvement and long-term project objectives far outweigh the manageable and temporary negative impacts that will arise during project construction and any residual or induced impacts during project operation phase. Provided the EMP is properly implemented there will be no significant negative impacts arising from the project.

201

APPENDICES

(Provided in a Separate Volume) List of Appendices: 1. ADB’s Rapid Environmental Assessment (REA) Checklist 2. Locations of borrow and Quarries area for the project road 3. Baseline Environmental Parameter monitoring results 4. National Ambient Air Quality Standards (MoEFCC, 2009) 5. Tree inventory within formation width of the project road 6. Details of Protected Areas in Tamil Nadu 7. Detailed Analysis of Air Modeling 8. Guidelines For Plant Management 9. Guidelines for Camp Site Management 10. Guidelines for Waste (Debris) Disposal and Management 11. Guidelines for Borrow Area Management 12. Guidelines for Quarry Area Management 13. Noise Modeling Details 14. Details of Participants and Public Consultation attendance list 15. Indian Standard Drinking Water Specification: IS 10500:1991 and IS 2296:1992 16. National Ambient Noise Level Standards 17. Copy of Forest Notification for Kattuguladur and Gudalur RF

202

Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist

Country/Project Title:

Sector Division:

Screening Questions Yes No Remarks

A. PROJECT SITING

Is the project area adjacent to or within any of the following environmentally sensitive areas?

X

Cultural heritage site

X No cultural heritage site is located within the road RoW.. The project road does not pass through any Archaeological sensitive area.

Protected Area X The project road is not located core/buffer zone of any protected area. However, proposed Cheyyur - Polur road and ECR link road passes through forest areas in patches. The widening in forest stretches will be limited to available RoW and no additional land acquisition is required.

ECR link is crossing Odiyur lake having CRZ and are considered as Hot Spot. No such hot spot is existing along the SH 115. Coastal Regulation Zone (CRZ) clearance is not required for ECR link, since there is no improvement of project road in the backwater stretch of ECR link.

Wetland X

Mangrove

X

Estuarine

X

Buffer zone of protected area

X The project road is not located core/buffer zone of any protected area.

Special area for protecting biodiversity

X

B. POTENTIAL ENVIRONMENTAL IMPACTS

Will the project cause…

encroachment on historical/cultural areas; disfiguration of landscape by road embankments, cuts, fills, and quarries?

X No encroachment of historical places. Disfiguration of landscape is not envisaged since it is expansion/reconstruction of existing alignment. Cut and fills are required only to improve the vertical profile of the road. Most of the construction materials would be available from existing quarries nearby, relatively few new borrow areas will be required, borrow area and gravel quarry area are identified within the vicinity of project road.

INDIA: TAMIL NADU INDUSTRIAL CONNECTIVITY PROJECT (TNICP) Upgrading Cheyyur - Polur (SH115) and ECR link road

SARD - SATC

203

Screening Questions Yes No Remarks

encroachment on precious ecology (e.g. sensitive or protected areas)?

X The project road is not located core/buffer zone of any protected area. However, proposed Cheyyur - Polur road and ECR link road passes through forest areas in patches. The widening in forest stretches will be limited to available RoW and no additional land acquisition is required.

ECR link is crossing Odiyur lake having CRZ and are considered as Hot Spot. No such hot spot is existing along the SH 115. Coastal Regulation Zone (CRZ) clearance is not required for ECR link, since there is no improvement of project road in the backwater stretch of ECR link.

alteration of surface water hydrology of waterways crossed by roads, resulting in increased sediment in streams affected by increased soil erosion at construction site?

X The project road crosses Subam river, Cheyyar river and small natural streams. Water Bodies such as village ponds and lake are present along the project road. None of them are impacted due to the project road as every measure has been taken in design to avoid the impact on these water bodies.

deterioration of surface water quality due to silt runoff and sanitary wastes from worker-based camps and chemicals used in construction?

X During construction period suitable mitigation measures will be required to control the silt runoff. Adequate Sanitary facilities and drainage in the workers camps will help to avoid this possibility. As the construction activity in this project will not contain any harmful ingredients, no impact on surface water quality is anticipated.

increased local air pollution due to rock crushing, cutting and filling works, and chemicals from asphalt processing?

X With appropriate mitigation measures and use of most modern environment friendly equipments/machineries air pollution shall be reduced to permissible levels.

risks and vulnerabilities related to occupational health and safety due to physical, chemical, biological, and radiological hazards during project construction and operation during project construction and operation?

X Possible. With appropriate mitigation measures such risks would be minimized.

noise and vibration due to blasting and other civil works?

X No Blasting is involved. No significant noise generation is expected during construction activities except normal construction equipment operational noise. These noise levels will be impulsive in nature and its impact will be confined within few meters of either side of the road.

dislocation or involuntary resettlement of people?

X Likely. A Resettlement Plan will be prepared, and compensation shall be paid as per approved entitlement matrix.

dislocation and compulsory resettlement of people living in right-of-way?

X Likely. A Resettlement Plan will be prepared, and compensation shall be paid as per approved entitlement matrix.

disproportionate impacts on the poor, women and children, Indigenous Peoples or other vulnerable groups?

X No such impact is anticipated.

other social concerns relating to inconveniences in living conditions in the project areas that may trigger cases of upper respiratory problems and stress?

X Imposing of appropriate mitigation measures in contract agreement to keep the air pollution within permissible levels will keep a check on this problem.

hazardous driving conditions where construction interferes with pre-existing roads?

X To minimized the impact suitable traffic management plan will be required

204

Screening Questions Yes No Remarks

poor sanitation and solid waste disposal in construction camps and work sites, and possible transmission of communicable diseases (such as STI's and HIV/AIDS) from workers to local populations?

X Proper provisions for sanitation, health care and solid waste disposal facilities will be available in the contract documents to avoid such possibility.

Workers will be made aware about communicable diseases

creation of temporary breeding habitats for diseases such as those transmitted by mosquitoes and rodents?

X

accident risks associated with increased vehicular traffic, leading to accidental spills of toxic materials?

X Adoption of suitable traffic signage system at sensitive places will reduce such possibility.

increased noise and air pollution resulting from traffic volume?

X Due to improvement in Riding Quality & Comfort in driving due to unidirectional traffic such pollution will be reduced.

Mitigation measures along with monitoring plan will be required

increased risk of water pollution from oil, grease and fuel spills, and other materials from vehicles using the road?

X Controlled construction activities and proper drainage system will reduce this possibility.

social conflicts if workers from other regions or countries are hired?

X Not anticipated. Local labours would be hired to the extent possible.

large population influx during project construction and operation that causes increased burden on social infrastructure and services (such as water supply and sanitation systems)?

X Possible.

risks to community health and safety due to the transport, storage, and use and/or disposal of materials such as explosives, fuel and other chemicals during construction and operation?

X Possible. EMP shall be followed to minimize this risk.

community safety risks due to both accidental and natural causes, especially where the structural elements or components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation and decommissioning.

X Impact is anticipated, and measures will be considered in preparation of detailed Traffic Control Plans prepared prior to commencement of works on any section of road.

The Contractor will provide safe and convenient passage for vehicles, pedestrians and livestock to and from side roads and property accesses connecting the project road.

205

A Checklist for Preliminary Climate Risk Screening

Country/Project Title: India: Tamil Nadu Industrial Connectivity Project (Cheyyur - Polur (SH115) and ECR link road)

Sector : Transport

Subsector: Roads and Highways

Division/Department: SATC

Screening Questions Score Remarks1

Location and Design of project

Is siting and/or routing of the project (or its components) likely to be affected by climate conditions including extreme weather related events such as floods, droughts, storms, landslides?

0 There is no issue of landslide/ landslip in the project area as the project road fall in plain terrain. The upgradation of road will not have any impact on extreme weather-related events.

Would the project design (e.g. the clearance for bridges) need to consider any hydro-meteorological parameters (e.g., sea-level, peak river flow, reliable water level, peak wind speed etc.)?

1 Hydrological surveys have been done at all the major and minor river crossings with a view to obtain the Cross section of the rivers/streams at the centre line of the road and up to a reasonable distance at upstream and downstream. The Highest Recorded Flood Levels (HFL) has been obtained from existing flood marks or ascertained from local enquiry with local knowledgeable persons.

Materials and Maintenance

Would weather, current and likely future climate conditions (e.g. prevailing humidity level, temperature contrast between hot summer days and cold winter days, exposure to wind and humidity hydro-meteorological parameters likely affect the selection of project inputs over the life of project outputs (e.g. construction material)?

1 The project districts Kanchipuram and Tiruvannamalai districts fall in the semi-Arid Tropical Zone of climatic classification. project road lies in area of high rainfall. maximum rainfall during months of August - December. The average annual rainfall in the project area varies from 773 mm to 1775 mm (Vandavasi: 957 mm to 1407 mm, Kanchipuram: 773 mm to 1775 mm, Chengalpattu: 1092 mm to 1534 mm, Arani: 826 mm to 1570 mm). Rainfall mainly occurs during north to east monsoon.

April and May months are the hottest months with mean monthly temperature varying between 36.3 °C and 40.8 °C. December and January are comparatively the coolest months with average mean monthly temperature varying from 16.1 ° to 20.5 °C. The minimum monthly temperature is 16 °C in the project area.

Would weather, current and likely future climate conditions, and related extreme events likely affect the maintenance (scheduling and cost) of project output(s) ?

0 April and May months are the hottest months with mean monthly temperature varying between 36.3 °C and 40.8 °C. Further, asphalt overlay maintenance requirement to concessionaires ensure continued good road quality.

Performance of project outputs

Would weather/climate conditions, and related extreme events likely affect the performance (e.g. annual power production) of project output(s) (e.g. hydro-power generation facilities) throughout their design life time?

0 The predicted increase in temperature is at levels that may cause rutting but not at a scale that can jeopardize the achieving the project objective of providing safe and efficient transport.

Options for answers and corresponding score are provided below:

1 If possible, provide details on the sensitivity of project components to climate conditions, such as how climate parameters are considered in design standards for infrastructure components, how changes in key climate parameters and sea level might affect the siting/routing of project, the selection of construction material and/or scheduling, performances and/or the maintenance cost/scheduling of project outputs.

206

Response Score

Not Likely 0

Likely 1

Very Likely 2

Responses when added that provide a score of 0 will be considered low risk project. If adding all responses will result to a score of 1-4 and that no score of 2 was given to any single response, the project will be assigned a medium risk category. A total score of 5 or more (which include providing a score of 1 in all responses) or a 2 in any single response, will be categorized as high risk project.

Result of Initial Screening (Low, Medium, High): Medium

Other Comments:______________________________________________________________ _________________________________________________________________________

Prepared by: ________________

207

Appendix 2: Locations of Borrow and Quarries area for the Project Road

208

Appendix 3: Baseline Environmental Parameter Monitoring Results

209

210

211

212

213

214

215

216

217

218

219

220

221

222

223

224

225

226

227

228

229

230

231

232

233

234

235

236

237

238

239

240

241

242

243

244

245

246

247

248

249

250

251

252

253

254

255

256

257

258

259

260

Appendix 4: Comparison of World Bank and GoI Ambient Air Quality Standards

A comparison between the ambient air quality requirements between the World Bank (WB) Environment, Health and Safety (EHS) guidelines and the National Ambient Air Quality standards (NAAQS) under the Air (Prevention and Control of Pollution) Act, 1981 of GOI as given in table below shows that the NAAQS has requirements on three more parameters (Pb, Co and NH3) in comparison to the WB EHS. The NAAQS has differentiated standards for two types of areas: i) industrial, residential, rural and other areas and ii) ecologically sensitive areas. The WB EHS has guidelines values which are the required standards but allows for gradual compliance to the guideline values through staged interim targets. Most WB EHS guideline requirements are more stringent than NAAQS except for the NOx one year average in ecologically sensitive areas where the NAAQS requirements are more stringent.

Table 1: Ambient Air Quality standards of WB EHS Vs. the GOI NAAQS Ambient Air

Quality Parameter

Averaging Period

WB Guideline Value GOI Standards for Industrial,

Residential, Rural and Other Areas

GoI Ecologically Sensitive Area

(notified by Central Government)

Sulfur dioxide

(SO2) (ug/m3) 24-hr

125 (Interim target 1)

80

80

50 (Interim target 2)

20 (guideline)

10 min 500 (guideline)

Annual None 50 20

Nitrogen dioxide (NO2) (ug/m3)

1 Year 40 (guideline) 40 30

24 Hour None 80 80

1 Hour 200 (guideline)

PM10

(ug/m3) 1 Year

70 (Interim target 1)

50 (Interim target 2)

30 (Interim target 3)

20 (guideline) 60 60

24-hr

150 (Interim target 1)

100 (Interim target 2)

75 (Interim target 3)

50 (guideline) 100 100

PM2.5 (ug/m3) 1 year

35 (Interim target 1)

25 (Interim target 2)

15 (Interim target 3)

10 (guideline) 40 40

24-Hour

75 (Interim target 1)

50 (Interim target 2)

37.5 (Interim target 3)

25 (guideline) 60 60

Ozone (O3) (ug/m3)

8-hr daily max 160 (Interim target 1)

100 (guideline) 100 100

Lead (Pb) µg/m3)

Annual 0.5 0.5

24 hours 1.0 1.0

Carbon Monoxide (CO) µg/m3

8 hours 2000 2000

1 hour 4000 4000

Ammonia (NH3) µ/m3

Annual 100 100

24 hours 400 400

261

National Ambient Air Quality Standards (MOEFCC, 2009)

Pollutant Time Weighted

Average

Concentration in Ambient air (g/m3)

Industrial, Residential, Rural and Other Areas

Ecologically Sensitive Areas

Sulphur Dioxide (SO2) Annual Average* 50 20

24 hr** 80 80

Oxides of Nitrogen (as NO2) Annual Average * 40 30

24 hr** 80 80

Particulate Matter: PM10 (<10 μm )

Annual Average * 60 60

24 hr** 100 100

Particulate Matter: PM2.5 (<2.5 μm)

Annual Average * 40 40

24 hr** 60 60

Lead Annual Average * 0.5 0.5

24 hr** 1.0 1.0

Carbon monoxide mg/m3 8 hr 2.0 2.0

1 hr 4.0 4.0

* Annual Arithmetic mean of minimum 104 measurement in a year taken for a week 24 hourly at uniform interval.

** 24 hourly or 8 hourly or 1 hourly monitored values should meet 98 percent of the time in a year

Source: MoEF notification Central Pollution Control Board (1997) National Ambient Air Quality Monitoring Series, NAQMS/a/1996-97.

262

Appendix 5: Tree inventory within the Formation Width of the Project Road

TREES WITHIN PROPOSED RIGHT OF WAY (PROW) OF SH 115 INCLUSIVE OF BYPASSES

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1 2/650

6/700

2.00 Illuppai Tree 2.85 Left

2 2.50 Neem Tree 1.40 Left

3 3.00 Nona Tree 1.20 Left

4 2/700 2/750 6.50 Tamarind Tree 3.00 Right

5

2/750

2/800

5.10 Illuppai Tree 2.40 Left

6 5.00 Illuppai Tree 2.50 Left

7 6.50 Poovarasam Tree

1.80 Right

8 6.30 Poovarasam Tree

0.90m

Right

9 2/800 2/850

6.20 Neem Tree 2.60 Right

10 6.30 Tamarind Tree 2.00 Right

11 2/850

2/900

5.50 Banyan Tree 4.30 Left

12 5.60 Tamarind Tree 4.10 Left

13 6.10 Tamarind Tree 3.30 Right

2.

3.

263

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

14 6.20 Banyan Tree 3.00 Right

15

2/900

2/950

6.00 Tamarind Tree 2.10 Left

16 5.80 Naval Tree 2.30 Left

17 6.00 Neem Tree 2.40 Right

18 5.00 Tamarind Tree 5.20 Right

19 2/950

3/000

5.00 Banyan Tree 5.40 Left

20 5.90 Banyan Tree 4.80 Left

21 5.00 Banyan Tree 4.50 Left

22 3/000 3/050

6.50 Tamarind Tree 3.30 Left

23 5.60 Tamarind Tree 2.30 Right

24 3/050

3/100

6.20 Tamarind Tree 2.60 Right

25 4.00 Illuppai Tree 3.10 Right

26 6.20 Tamarind Tree 1.70 Right

27 3/100 3/150

5.90 Tamarind Tree 4.30 Left

28 6.50 Tamarind Tree 1.80 Right

29

3/150

3/200

6.10 Tamarind Tree 2.10 Left

30 4.50 Tamarind Tree 4.40 Right

31 6.50 Tamarind Tree 1.30 Right

32 5.80 Tamarind Tree 2.10 Right

33 3/200 3/250 6.00 Tamarind Tree 2.00 Left

34 3/250 3/300

5.50 Tamarind Tree 5.00 Left

35 5.60 Tamarind Tree 1.70 Right

36 3/300

3/350

4.50 Banyan Tree 7.50 Right

37 4.00 Tamarind Tree 4.10 Right

38 6.50 Tamarind Tree 1.20 Right

39 3/350 3/400

4.80 Banyan Tree 11.10 Left

40 5.10 Illuppai Tree 3.60 Right

41 3/400 3/450 5.80 Illuppai Tree 2.50 Left

42

3/400

3/450

5.20 Illuppai Tree 4.15 Left

43 5.20 Illuppai Tree 4.20 Left

44 4.90 Naval Tree 3.10 Right

45 5.90 Illuppai Tree 3.20 Right

46 3/450

3/500

5.60 Palm Tree 1.30 Right

47 6.10 Palm Tree 1.20 Right

48 6.00 Tamarind Tree 2.20 Right

49 3/550 3/600 4.70 Illuppai Tree 3.80 Left

50 4.80 Banyan Tree 5.30 Left

51 6.50 Neem Tree 1.20 Right

52 6.50 Palm Tree 1.50 Right

53 4.65 Banyan Tree 6.40 Right

264

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

54 4.30 Tamarind Tree 4.80 Right

55 3/600 3/650 5.20 Illuppai Tree 3.90 Right

56 3/650 3/700 3.90 Illuppai Tree 4.30 Right

57 6.20 Tamarind Tree 2.80 Right

58 3/700 3/750 6.50 Neem Tree 0.90 Left

59 6.40 Tamarind Tree 3.60 Right

60 6.30 Tamarind Tree 3.20 Right

61 3/750 3/800 5.80 Tamarind Tree 2.30 Left

62 3/800 3/850 4.00 Illuppai Tree 3.60 Left

63 6.50 Banyan Tree 6.40 Right

64 3/850 3/900 6.50 Tamarind Tree 2.10 Left

65 6.50 Tamarind Tree 2.40 Left

66 4.20 Tamarind Tree 2.40 Right

67 4.70 Tamarind Tree 2.10 Right

68 3/900 3/950 4.50 Palm Tree 1.20 Right

69 4.20 Palm Tree 1.10 Right

70 4.20 Palm Tree 1.30 Right

71 3/950 4/000 3.70 Banyan Tree 9.70 Right

72 6.50 Banyan Tree 4.30 Right

73 4/000 4/050 6.50 Tamarind Tree 2.60 Right

74 4/050 4/100 6.50 Tamarind Tree 2.10 Right

75 4/100 4/150 6.30 Neem Tree 1.70 Left

76 5.80 Tamarind Tree 1.90 Right

77 4/150 4/200 5.60 Banyan Tree 4.90 Left

78 6.10 Tamarind Tree 2.60 Left

79 4/200 4/250 4.50 Illuppai Tree 2.20 Left

80 5.60 Illuppai Tree 2.60 Right

81 4/250 4/300 4.70 Illuppai Tree 2.30 Left

82 5.90 Illuppai Tree 3.00 Right

83 4/300 4/350 6.20 Palm Tree 1.20 Left

84 4.10 Illuppai Tree 1.70 Right

85 6.50 Tamarind Tree 1.90 Right

86 6.50 Palm Tree 4.90 Right

87 6.50 Tamarind Tree 2.60 Right

88 6.50 Neem Tree 2.20 Right

89 4/350 4/400 6.50 Palm Tree 1.70 Right

90 6.50 Palm Tree 1.90 Right

91 6.50 Tamarind Tree 4.90 Right

92 6.50 Tamarind Tree 2.60 Right

93 4/400 4/450 6.80 Tamarind Tree 4.90 Left

5.

265

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

94 6.50 Tamarind Tree 1.70 Right

95 6.30 Tamarind Tree 1.90 Right

96 6.50 Tamarind Tree 4.90 Right

97 6.50 Tamarind Tree 2.60 Right

98 4/450 4/500 6.40 Illuppai Tree 2.60 Left

99 6.30 Tamarind Tree 4.90 Left

100 6.50 Palm Tree 4.90 Right

101 6.50 Neem Tree 2.60 Right

102 4/450 4/500 6.40 Illuppai Tree 3.20 Left

103 4/500 4/550 6.50 Banyan Tree 1.40 Left

104 6.50 Palm Tree 1.20 Right

105 6.40 Illuppai Tree 3.40 Right

106 6.50 Palm Tree 1.20 Right

107 6.50 Palm Tree 1.20 Right

108 6.50 Palm Tree 1.20 Right

109 6.50 Palm Tree 1.20 Right

110 6.50 Palm Tree 3.40 Right

111 4/550 4/600 6.50 Tamarind Tree 1.60 Left

112 6.50 Illuppai Tree 1.50 Left

113 6.50 Palm Tree 1.30 Left

114 6.50 Palm Tree 1.20 Right

115 6.50 Illuppai Tree 1.30 Right

116 4/600 4/650 6.50 Palm Tree 1.30 Right

117 6.50 Palm Tree 1.30 Right

118 6.50 Palm Tree 1.30 Right

119 6.50 Palm Tree 1.30 Right

120 6.50 Illuppai Tree 1.40 Right

121 6.50 Tamarind Tree 2.20 Right

122 4/650 4/700 6.50 Tamarind Tree 1.50 Left

123 6.50 Palm Tree 1.20 Left

124 6.50 Palm Tree 1.20 Right

125 6.50 Palm Tree 1.20 Right

126 6.50 Palm Tree 1.20 Right

127 6.50 Palm Tree 1.20 Right

128 6.50 Palm Tree 1.20 Right

129 4/700 4/750 6.50 Palm Tree 1.30 Left

130 6.50 Neem Tree 0.20 Left

131 6.50 Illuppai Tree 0.80 Left

132 6.50 Illuppai Tree 2.50 Left

133 6.50 Tamarind Tree 1.50 Right

266

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

134 6.50 Tamarind Tree 1.50 Right

135 6.80 Palm Tree 1.20 Right

136 6.80 Palm Tree 1.20 Right

137 6.80 Palm Tree 1.20 Right

138 6.80 Palm Tree 1.20 Right

139 6.80 Palm Tree 1.20 Right

140 6.80 Naval Tree 1.20 Right

141 4/750 4/800 6.50 Palm Tree 1.20 Left

142 6.50 Palm Tree 1.20 Left

143 6.50 Palm Tree 1.20 Left

144 6.80 Tamarind Tree 0.90 Left

145 6.80 Palm Tree 1.20 Right

146 6.80 Palm Tree 1.20 Right

147 6.80 Palm Tree 1.20 Right

148 6.80 Palm Tree 1.20 Right

149 6.80 Palm Tree 1.20 Right

150 6.80 Palm Tree 1.20 Right

151 6.80 Palm Tree 1.20 Right

152 6.80 Illuppai Tree 1.00 Right

153 6.80 Illuppai Tree 1.00 Right

154 4/800 4/850 6.80 Illuppai Tree 1.20 Left

155 6.80 Illuppai Tree 1.20 Left

156 6.80 Palm Tree 1.20 Left

157 6.80 Palm Tree 1.20 Left

158 6.50 Palm Tree 2.20 Left

159 6.80 Illuppai Tree 1.20 Right

160 6.80 Illuppai Tree 0.90 Right

161 6.80 Palm Tree 1.30 Right

162 6.80 Palm Tree 1.30 Right

163 6.80 Palm Tree 1.30 Right

164 4/850 4/900 6.50 Palm Tree 1.20 Left

165 6.50 Palm Tree 1.20 Left

166 6.50 Palm Tree 1.20 Left

167 6.50 Palm Tree 1.20 Left

168 6.50 Palm Tree 1.20 Left

169 6.50 Tamarind Tree 1.20 Left

170 6.50 Tamarind Tree 1.20 Left

171 6.80 Neem Tree 0.20 Left

172 6.80 Palm Tree 1.30 Right

173 6.80 Palm Tree 1.30 Right

7.

8.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

174 6.80 Palm Tree 1.30 Right

175 6.80 Palm Tree 1.30 Right

176 6.80 Palm Tree 1.30 Right

177 4/900 4/950 6.80 Palm Tree 1.20 Left

178 6.80 Tamarind Tree 1.30 Left

179 6.80 Vangai Tree 0.50 Left

180 6.80 Palm Tree 1.20 Right

181 6.80 Palm Tree 1.20 Right

182 6.80 Palm Tree 1.20 Right

183 6.80 Palm Tree 1.20 Right

184 6.80 Vangai Tree 0.90 Right

185 4/950 5/000 4.00 Illuppai Tree 2.40 Left

186 4.50 Palm Tree 1.20 Left

187 5/000 5/050 3.50 Neem Tree 0.30 Left

188 3.80 Palm Tree 1.20 Left

189 3.80 Neem Tree 0.50 Left

190 3.80 Neem Tree 0.50 Left

191 5/050 5/100 4.00 Palm Tree 1.50 Left

192 4.00 Banyan Tree 1.50 Left

193 4.80 Vangai Tree 0.90 Left

194 4.80 Vangai Tree 0.90 Left

195 6.50 Vangai Tree 0.80 Left

196 6.50 Neem Tree 0.50 Left

197 6.50 Neem Tree 0.50 Left

198 6.50 Neem Tree 0.50 Left

199 6.50 Neem Tree 0.50 Left

200 5/100 5/150 5.70 Palm Tree 1.20 Left

201 5.70 Palm Tree 1.20 Left

202 6.00 Neem Tree 2.60 Left

203 6.80 Illuppai Tree 1.20 Left

204 6.50 Palm Tree 1.30 Right

205 6.50 Palm Tree 1.30 Right

206 6.50 Palm Tree 1.30 Right

207 6.50 Palm Tree 1.30 Right

208 6.50 Palm Tree 1.30 Right

209 6.50 Palm Tree 1.30 Right

210 6.50 Tamarind Tree 1.50 Right

211 5/150 5/200 6.50 Illuppai Tree 1.60 Left

212 6.50 Palm Tree 1.20 Left

213 6.50 Neem Tree 0.40 Left

268

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

214 6.50 Neem Tree 0.40 Left

215 6.50 Pungai Tree 0.40 Right

216 5/150 5/200 6.50 Illuppai Tree 1.60 Left

217 6.50 Palm Tree 1.20 Left

218 6.50 Neem Tree 0.40 Left

219 6.50 Neem Tree 0.40 Left

220 5/200 5/250 6.50 Palm Tree 1.20 Left

221 6.50 Neem Tree 0.50 Right

222 5/250 5/300 6.50 Neem Tree 2.90 Left

223 6.50 Palm Tree 1.20 Left

224 5/300 5/350 6.80 Palm Tree 1.20 Left

225 6.50 Tamarind Tree 2.00 Left

226 6.80 Neem Tree 2.40 Left

227 5.50 Palm Tree 13.00 Right

228 5.50 Palm Tree 13.00 Right

229 5.50 Palm Tree 13.00 Right

230 5/350 5/400 6.80 Banyan Tree 4.80 Left

231 6.80 Naval Tree 2.10 Right

232 6.80 Palm Tree 1.30 Right

233 6.80 Neem Tree 1.40 Right

234 6.80 Palm Tree 1.20 Right

235 6.80 Palm Tree 1.20 Right

236 5/400 5/450 6.80 Palm Tree 1.20 Left

237 6.80 Palm Tree 1.20 Left

238 6.50 Illuppai Tree 1.90 Left

239 6.80 Neem Tree 3.50 Right

240 6.80 Illuppai Tree 3.60 Right

241 5/450 5/500 6.80 Illuppai Tree 5.30 Left

242 6.80 Illuppai Tree 2.20 Left

243 6.80 Illuppai Tree 4.20 Right

244 6.80 Illuppai Tree 5.70 Right

245 5/500 5/550 6.00 Illuppai Tree 2.40 Left

246 6.80 Tamarind Tree 4.40 Right

247 5/550 5/600 6.80 Tamarind Tree 1.60 Left

248 6.80 Tamarind Tree 3.90 Right

249 5/600 5/650 6.80 Tamarind Tree 3.50 Left

250 6.80 Illuppai Tree 1.60 Left

251 6.80 Tamarind Tree 3.20 Right

252 6.80 Illuppai Tree 3.40 Right

253 6.80 Neem Tree 0.80 Right

11.

12.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

254 6.50 Palm Tree 1.20 Right

255 6.50 Palm Tree 1.20 Right

256 5/650 5/700 6.50 Banyan Tree 2.60 Left

257 6.50 Palm Tree 1.20 Left

258 6.50 Palm Tree 1.20 Left

259 6.50 Palm Tree 1.20 Left

260 6.80 Neem Tree 1.80 Right

261 6.80 Illuppai Tree 2.20 Right

262 6.80 Palm Tree 1.20 Right

263 6.80 Palm Tree 1.20 Right

264 6.80 Palm Tree 1.20 Right

265 5/700 5/750 6.50 Palm Tree 1.20 Left

266 6.50 Palm Tree 1.20 Left

267 6.50 Palm Tree 1.20 Right

268 5/750 5/800 6.80 Neem Tree 1.50 Left

269 5/800 5/850 6.50 Illuppai Tree 1.30 Right

270 6.80 Tamarind Tree 2.00 Right

271 5/850 5/900 6.80 Palm Tree 1.20 Left

272 6.80 Palm Tree 1.20 Left

273 5/900 5/950 6.50 Palm Tree 1.20 Left

274 6.50 Neem Tree 0.40 Left

275 6.80 Naval Tree 1.40 Left

276 6.50 Banyan Tree 6.20 Right

277 5.60 Banyan Tree 6.50 Right

278 5/250 6/000 6.50 Illuppai Tree 2.00 Left

279 6.50 Illuppai Tree 2.70 Right

280 6.50 Neem Tree 0.70 Right

281 6/000 6/050 6.00 Illuppai Tree 3.20 Left

282 6.80 Naval Tree 1.80 Right

283 6.80 Palm Tree 1.30 Right

284 6.80 Palm Tree 1.30 Right

285 6.80 Neem Tree 0.50 Right

286 6.80 Neem Tree 0.50 Right

287 6/050 6/100 6.50 Neem Tree 2.20 Left

288 6.50 Banyan Tree 7.40 Left

289 6.80 Palm Tree 1.30 Right

290 6.80 Palm Tree 1.30 Right

291 6.80 Tamarind Tree 2.20 Right

292 6.50 Neem Tree 2.00 Right

293 6/100 6/150 6.50 Palm Tree 1.30 Left

270

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

294 6.50 Palm Tree 1.30 Left

295 6.50 Palm Tree 1.30 Left

296 6.50 Tamarind Tree 1.20 Left

297 6.50 Palm Tree 1.30 Right

298 6/100 6/150 6.50 Palm Tree 1.30 Left

299 6.50 Palm Tree 1.30 Left

300 6.50 Palm Tree 1.30 Left

301 6.50 Tamarind Tree 1.20 Left

302 6.50 Tamarind Tree 1.20 Right

303 6/150 6/200 6.50 Palm Tree 1.20 Left

304 6.80 Neem Tree 0.50 Left

305 6.80 Neem Tree 0.50 Left

306 6.80 Neem Tree 0.50 Left

307 6/200 6/250 6.80 Nona Tree 0.50 Left

308 6.80 Nona Tree 0.50 Left

309 6/250 6/300 6.80 Neem Tree 0.50 Left

310 6.80 Neem Tree 0.50 Left

311 6.80 Illuppai Tree 2.70 Left

312 6.80 Tamarind Tree 4.80 Right

313 6/250 6/300 6.50 Neem Tree 0.70 Left

314 6/300 6/350 6.80 Neem Tree 0.80 Left

315 6.50 Banyan Tree 2.20 Right

316 6/350 6/400 6.80 Neem Tree 0.30 Left

317 6/400 6/450 6.80 Neem Tree 1.00 Left

318 6.80 Neem Tree 1.30 Left

319 6/450 6/500 6.80 Neem Tree 0.90 Left

320 6.80 Neem Tree 1.00 Left

321 6.80 Palm Tree 1.50 Left

322 6.80 Neem Tree 0.60 Left

323 6.80 Neem Tree 1.30 Left

324 6.50 Illuppai Tree 3.80 Right

325 6.50 Neem Tree 0.90 Right

326 6.50 Neem Tree 0.90 Right

327 6/500 6/550 3.80 Tamarind Tree 1.50 Left

328 3.00 Naval Tree 1.80 Left

329 2.50 Tamarind Tree 4.10 Left

330 6/600 6/650 1.50 Tamarind Tree 4.10 Left

331 6/650 6/700 6.80 Tamarind Tree 4.10 Left

332 6.00 Illuppai Tree 3.00 Left

333 6.80 Neem Tree 1.00 Right

15.

16.

271

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

334 6/750 6/800 6.00 Banyan Tree 12.00 Left

335 6.50 Palm Tree 1.20 Left

336 6.80 Neem Tree 1.00 Left

337 6.80 Neem Tree 1.00 Left

338 6.80 Neem Tree 1.40 Right

339 6.80 Neem Tree 1.20 Right

340 6.80 Palm Tree 1.20 Right

341 6/800 6/850 6.50 Tamarind Tree 1.70 Left

342 6.80 Neem Tree 3.50 Left

343 6.80 Neem Tree 3.40 Right

344 6/850 6/900 6.50 Neem Tree 2.20 Left

345 6.80 Neem Tree 2.70 Right

346 6.80 Palm Tree 1.20 Right

347 6.50 Illuppai Tree 2.20 Right

348 6/900 6/950 6.50 Palm Tree 1.20 Right

349 6/950 7/000 6.80 Tamarind Tree 2.60 Left

350 6.50 Naval Tree 2.80 Left

351 7/000 7/050 6.80 Neem Tree 1.00 Left

352 6.80 Neem Tree 2.60 Left

353 6.80 Neem Tree 1.00 Left

354 7/050 7/100 6.50 Illuppai Tree 2.40 Left

355 6.80 Neem Tree 1.20 Left

356 6.80 Palm Tree 1.20 Left

357 6.80 Neem Tree 2.10 Left

358 6.80 Illuppai Tree 2.10 Right

359 6.80 Neem Tree 0.70 Right

360 6.80 Illuppai Tree 3.40 Right

361 7/100 7/150 6.80 Palm Tree 1.20 Left

362 6.80 Neem Tree 0.80 Left

363 6.50 Palm Tree 1.20 Left

364 6.80 Neem Tree 2.50 Left

365 6.80 Neem Tree 2.70 Left

366 6.80 Neem Tree 2.20 Right

367 6.80 Palm Tree 1.20 Right

368 6.80 Palm Tree 1.20 Right

369 7/150 7/200 6.80 Illuppai Tree 3.00 Left

370 6.80 Illuppai Tree 1.70 Right

371 6.50 Neem Tree 1.80 Right

372 7/200 7/250 6.80 Illuppai Tree 1.20 Left

373 6.80 Palm Tree 1.20 Left

272

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

374 6.80 Neem Tree 0.90 Left

375 6.80 Illuppai Tree 1.20 Left

376 6.80 Neem Tree 0.50 Right

377 6.80 Neem Tree 0.50 Right

378 6.00 Neem Tree 3.20 Right

379 7/250 7/300 6.80 Illuppai Tree 2.70 Left

380 6.80 Illuppai Tree 2.90 Left

381 6.80 Tamarind Tree 2.00 Left

382 6.00 Illuppai Tree 2.90 Right

383 6.00 Illuppai Tree 3.20 Right

384 6.50 Illuppai Tree 4.30 Right

385 7/300 7/350 6.80 Illuppai Tree 2.40 Left

386 6.00 Illuppai Tree 3.00 Right

387 7/350 7/400 6.80 Illuppai Tree 6.20 Left

388 6.00 Illuppai Tree 3.20 Right

389 6.00 Tamarind Tree 3.60 Right

390 7/400 7/450 6.80 Tamarind Tree 2.90 Left

391 6.00 Naval Tree 2.60 Right

392 7/500 7/550 6.80 Neem Tree 3.60 Left

393 6.80 Tamarind Tree 2.40 Left

394 6.80 Tamarind Tree 2.40 Left

395 6.80 Illuppai Tree 3.90 Right

396 6.80 Tamarind Tree 3.80 Right

397 7/550 7/600 6.80 Illuppai Tree 4.00 Left

398 6.80 Neem Tree 2.80 Right

399 7/600 7/650 6.80 Illuppai Tree 1.70 Left

400 6.50 Illuppai Tree 2.40 Right

401 7/700 7/750 6.80 Tamarind Tree 2.50 Left

402 6.50 Illuppai Tree 2.00 Right

403 6.50 Neem Tree 2.80 Right

404 7/780 7/800 6.80 Neem Tree 2.80 Left

405 6.80 Illuppai Tree 1.70 Left

406 6.80 Tamarind Tree 5.50 Right

407 7/850 7/900 6.80 Tamarind Tree 2.60 Left

408 6.80 Neem Tree 1.20 Left

409 6.80 Poovarasan Tree 0.60 Left

410 6.50 Neem Tree 3.80 Right

411 8/000 8/050 5.50 Poovarasan Tree 0.50 Right

412 5.50 Poovarasan Tree 0.90 Right

413 5.50 Poovarasan Tree 0.90 Right

18.

19.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

414 6.00 Poovarasan Tree 0.80 Right

415 6.00 Neem Tree 1.20 Right

416 8/050 8/100 6.80 Illuppai Tree 4.10 Left

417 6.80 Illuppai Tree 4.50 Left

418 6.00 Illuppai Tree 3.90 Right

419 5.80 Coconut Tree 1.20 Right

420 5.80 Coconut Tree 1.20 Right

421 8/100 8/150 6.80 Illuppai Tree 3.40 Left

422 6.80 Neem Tree 1.00 Left

423 5.60 Coconut Tree 1.20 Right

424 5.60 Coconut Tree 1.20 Right

425 5.60 Coconut Tree 1.20 Right

426 5.60 Coconut Tree 1.20 Right

427 5.60 Coconut Tree 1.20 Right

428 6.50 Palm Tree 1.30 Right

429 8/150 8/200 6.80 Tamarind Tree 1.40 Left

430 6.50 Palm Tree 1.20 Right

431 6.00 Tamarind Tree 3.60 Right

432 8/200 8/250 6.80 Neem Tree 1.00 Left

433 6.00 Illuppai Tree 2.40 Right

434 6.50 Illuppai Tree 1.20 Right

435 8/250 8/300 6.00 Karuvelam Tree 2.40 Right

436 5.00 Palm Tree 1.20 Right

437 5.00 Palm Tree 1.20 Right

438 5.00 Palm Tree 1.20 Right

439 5.00 Palm Tree 1.20 Right

440 5.00 Palm Tree 1.20 Right

441 8/400 8/450 6.00 Neem Tree 1.20 Right

442 5.00 Palm Tree 1.20 Right

443 5.00 Palm Tree 1.20 Right

444 5.50 Illuppai Tree 2.00 Right

445 8/450 8/500 4.00 Eacham Tree 1.10 Right

446 4.00 Fire wood 1.20 Right

447 3.50 Neem Tree 2.60 Right

448 5.90 Poovarasan Tree 1.00 Right

449 8/450 8/500 5.00 Neem Tree 1.20 Right

450 8/500 8/550 2.00 Illuppai Tree 3.50 Right

451 8/550 8/600 5.00 Palm Tree 1.20 Right

452 5.00 Palm Tree 1.20 Right

453 4.60 Illuppai Tree 5.20 Right

274

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

454 6.00 Neem Tree 1.00 Right

455 4.00 Neem Tree 1.10 Right

456 3.00 Palm Tree 1.20 Right

457 8/600 8/650 1.50 Neem Tree 1.00 Right

458 1.50 Neem Tree 1.00 Right

459 2.00 Palm Tree 1.30 Right

460 2.80 Neem Tree 0.50 Right

461 1.00 Neem Tree 1.20 Right

462 4.00 Neem Tree 0.70 Right

463 1.50 Illuppai Tree 3.80 Right

464 2.50 Tamarind Tree 2.60 Right

465 2.50 Illuppai Tree 2.00 Right

466 8/650 8/700 2.00 Illuppai Tree 2.70 Right

467 3.00 Illuppai Tree 0.70 Right

468 3.80 Palm Tree 1.20 Right

469 8/700 8/750 4.00 Illuppai Tree 2.60 Right

470 8/750 8/800 4.00 Illuppai Tree 2.30 Right

471 4.80 Illuppai Tree 2.80 Right

472 8/800 8/850 3.80 Palm Tree 1.20 Right

473 3.80 Neem Tree 0.60 Right

474 8/850 8/900 3.00 Illuppai Tree 1.80 Right

475 3.00 Palm Tree 1.30 Right

476 3.00 Naval Tree 1.30 Right

477 2.70 Palm Tree 1.30 Right

478 2.70 Palm Tree 1.30 Right

479 8/900 8/950 3.00 Naval Tree 1.40 Right

480 4.00 Neem Tree 0.70 Right

481 4.00 Palm Tree 0.30 Right

482 4.00 Palm Tree 0.30 Right

483 4.00 Palm Tree 0.30 Right

484 4.00 Palm Tree 0.30 Right

485 8/900 8/950 1.00 Palm Tree 1.20 Right

486 1.50 Naval Tree 1.30 Right

487 3.00 Illuppai Tree 3.20 Right

488 3.00 Palm Tree 1.20 Right

489 6.50 Palm Tree 1.30 Right

490 6.50 Palm Tree 1.30 Right

491 6.50 Palm Tree 1.30 Right

492 6.50 Palm Tree 1.30 Right

493 8/950 9/000 2.50 Illuppai Tree 2.80 Right

22.

23.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

494 6.80 Palm Tree 1.30 Right

495 6.80 Palm Tree 1.30 Right

496 6.80 Palm Tree 1.30 Right

497 6.80 Palm Tree 1.30 Right

498 6.80 Palm Tree 1.30 Right

499 6.80 Palm Tree 1.30 Right

500 6.80 Palm Tree 1.30 Right

501 6.80 Palm Tree 1.30 Right

502 6.80 Palm Tree 1.30 Right

503 6.80 Palm Tree 1.30 Right

504 6.80 Palm Tree 1.30 Right

505 6.80 Palm Tree 1.30 Right

506 6.80 Palm Tree 1.30 Right

507 3.50 Palm Tree 1.30 Right

508 9/000 9/050 2.00 Fire wood 1.00 Right

509 2.00 Palm Tree 1.40 Right

510 6.80 Palm Tree 1.30 Right

511 6.80 Palm Tree 1.30 Right

512 6.80 Palm Tree 1.30 Right

513 6.80 Palm Tree 1.30 Right

514 6.80 Palm Tree 1.30 Right

515 6.80 Palm Tree 1.30 Right

516 6.80 Palm Tree 1.30 Right

517 6.80 Palm Tree 1.30 Right

518 6.80 Palm Tree 1.30 Right

519 6.80 Palm Tree 1.30 Right

520 6.80 Palm Tree 1.30 Right

521 6.80 Palm Tree 1.30 Right

522 6.80 Palm Tree 1.30 Right

523 6.80 Palm Tree 1.30 Right

524 6.80 Palm Tree 1.30 Right

525 6.80 Palm Tree 1.30 Right

526 6.80 Palm Tree 1.30 Right

527 6.80 Palm Tree 1.30 Right

528 9/050 9/100 3.80 Palm Tree 1.30 Right

529 3.80 Palm Tree 1.30 Right

530 3.80 Palm Tree 1.30 Right

531 3.80 Palm Tree 1.30 Right

532 3.80 Palm Tree 1.30 Right

533 3.80 Palm Tree 1.30 Right

276

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From To

534 2.80 Illuppai Tree 2.80 Right

535 3.50 Neem Tree 1.20 Right

536 3.00 Palm Tree 1.20 Right

537 3.00 Palm Tree 1.20 Right

538 9/100 9/150 3.90 Illuppai Tree 2.50 Right

539 3.50 Illuppai Tree 3.50 Right

540 4.00 Neem Tree 1.20 Right

541 4.00 Neem Tree 1.20 Right

542 9/150 9/200 1.00 Neem Tree 0.50 Right

543 1.00 Illuppai Tree 3.00 Right

544 1.50 Neem Tree 1.00 Right

545 6.00 Palm Tree 1.20 Right

546 9/200 9/250 1.00 Neem Tree 1.40 Right

547 1.80 Illuppai Tree 2.40 Right

548 9/250 9/300 6.80 Palm Tree 1.20 Right

549 4.00 Marutham Tree 1.40 Right

550 9/300 9/350 3.80 Palm Tree 1.30 Right

551 4.00 Tamarind Tree 1.80 Right

552 4.00 Tamarind Tree 1.80 Right

553 4.00 Tamarind Tree 1.80 Right

554 6.50 Palm Tree 1.20 Right

555 9/350 9/400 5.00 Naval Tree 1.50 Right

556 6.80 Palm Tree 1.20 Right

557 6.80 Palm Tree 1.20 Right

558 6.80 Palm Tree 1.20 Right

559 6.80 Palm Tree 1.20 Right

560 6.80 Palm Tree 1.20 Right

561 6.80 Palm Tree 1.20 Right

562 1.00 Palm Tree 1.30 Right

563 2.00 Vengai Tree 0.90 Right

564 9/400 9/450 2.00 Illuppai Tree 1.80 Right

565 6.50 Nona Tree 0.40 Right

566 3.00 Illuppai Tree 3.20 Right

567 6.50 Neem Tree 0.80 Right

568 5.00 Illuppai Tree 2.20 Right

569 9/450 9/500 5.50 Illuppai Tree 1.70 Right

570 5.50 Illuppai Tree 2.30 Right

571 6.00 Neem Tree 2.40 Right

572 5.50 Neem Tree 1.20 Right

573 6.00 Naval Tree 1.50 Right

26.

27.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From To

574 9/500 9/550 4.00 Palm Tree 1.20 Right

575 4.50 Neem Tree 1.20 Right

576 4.50 Neem Tree 1.20 Right

577 5.00 Banyan Tree 3.80 Right

578 9/550 9/600 5.00 Palm Tree 1.20 Right

579 6.00 Illuppai Tree 3.40 Right

580 6.50 Vengai Tree 1.70 Right

581 6.00 Palm Tree 1.20 Right

582 6.80 Naval Tree 1.00 Right

583 6.80 Naval Tree 1.00 Right

584 6.00 Palm Tree 1.20 Right

585 6.80 Naval Tree 5.50 Right

586 9/600 9/650 6.00 Neem Tree 0.50 Right

587 5.80 Palm Tree 1.20 Right

588 5.00 Palm Tree 1.20 Right

589 6.00 Palm Tree 1.20 Right

590 6.00 Palm Tree 1.20 Right

591 5.00 Banyan Tree 5.00 Right

592 5.00 Palm Tree 1.20 Right

593 5.00 Palm Tree 1.20 Right

594 6.80 Illuppai Tree 1.70 Right

595 6.80 Neem Tree 0.50 Right

596 9/650 9/700 6.80 Neem Tree 2.50 Right

597 6.00 Palm Tree 1.20 Right

598 6.00 Palm Tree 1.20 Right

599 6.20 Neem Tree 1.20 Right

600 9/700 9/750 6.00 Banyan Tree 5.20 Right

601 6.00 Neem Tree 1.00 Right

602 9/750 9/800 5.80 Illuppai Tree 2.30 Right

603 6.00 Naval Tree 1.00 Right

604 6.50 Palm Tree 1.20 Right

605 6.50 Neem Tree 1.00 Right

606 6.00 Illuppai Tree 1.90 Right

607 6.50 Palm Tree 1.20 Right

608 6.50 Palm Tree 1.20 Right

609 6.50 Palm Tree 1.20 Right

610 6.50 Banyan Tree 2.80 Right

611 9/800 9/850 6.80 Palm Tree 1.20 Right

612 6.80 Banyan Tree 1.20 Right

613 5.00 Illuppai Tree 2.60 Right

278

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

614 6.80 Palm Tree 1.20 Right

615 6.00 Banyan Tree 1.20 Right

616 6.00 Palm Tree 1.20 Right

617 6.00 Palm Tree 1.20 Right

618 6.80 Naval Tree 3.00 Right

619 9/850 9/900 6.80 Palm Tree 1.20 Right

620 6.80 Palm Tree 1.50 Right

621 6.00 Neem Tree 0.80 Right

622 6.00 Illuppai Tree 2.60 Right

623 9/900 9/950 6.00 Palm Tree 1.20 Right

624 6.80 Palm Tree 1.20 Right

625 6.50 Illuppai Tree 2.40 Right

626 6.80 Naval Tree 0.90 Right

627 6.80 Illuppai Tree 2.60 Right

628 5.50 Palm Tree 1.20 Right

629 9/950 10/000 6.00 Tamarind Tree 1.70 Right

630 6.00 Illuppai Tree 1.80 Right

631 6.00 Neem Tree 0.70 Right

632 6.80 Naval Tree 0.80 Right

633 6.80 Neem Tree 0.70 Right

634 6.00 Palm Tree 1.20 Right

635 6.80 Neem Tree 1.00 Right

636 10/000 10/050 6.50 Neem Tree 1.00 Right

637 6.50 Neem Tree 1.00 Right

638 6.50 Palm Tree 1.20 Right

639 6.50 Palm Tree 1.20 Right

640 6.00 Illuppai Tree 1.00 Right

641 6.80 Neem Tree 0.20 Right

642 6.00 Palm Tree 1.20 Right

643 6.50 Vengai Tree 0.40 Right

644 10/050 10/100 6.00 Palm Tree 1.20 Right

645 6.50 Fire wood 1.40 Right

646 5.50 Illuppai Tree 2.80 Right

647 6.00 Neem Tree 0.40 Right

648 5.50 Tamarind Tree 3.20 Right

649 6.80 Fire wood 0.70 Right

650 10/100 10/150 6.50 Palm Tree 1.20 Left

651 6.50 Neem Tree 1.80 Left

652 6.00 Neem Tree 1.00 Right

653 6.50 Palm Tree 1.30 Right

30.

31.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

654 6.50 Palm Tree 1.30 Right

655 6.00 Illuppai Tree 2.50 Right

656 6.50 Neem Tree 0.50 Right

657 6.50 Neem Tree 0.50 Right

658 10/150 10/200 6.80 Neem Tree 0.70 Right

659 6.00 Illuppai Tree 2.70 Right

660 6.50 Palm Tree 1.40 Right

661 6.50 Palm Tree 1.30 Right

662 10/200 10/250 6.50 Nona Tree 0.50 Right

663 10/200 10/250 6.50 Neem Tree 0.70 Right

664 5.50 Neem Tree 0.80 Right

665 4.00 Neem Tree 1.30 Right

666 4.00 Neem Tree 1.00 Right

667 10/250 10/300 6.50 Neem Tree 3.20 Right

668 6.80 Palm Tree 1.30 Right

669 6.80 Illuppai Tree 2.60 Right

670 6.80 Nona Tree 0.80 Right

671 5.50 Vengai Tree 3.40 Right

672 10/300 10/350 6.50 Neem Tree 1.40 Left

673 6.50 Neem Tree 0.50 Left

674 6.80 Illuppai Tree 2.00 Right

675 6.00 Neem Tree 1.20 Right

676 6.80 Neem Tree 0.60 Right

677 6.80 Illuppai Tree 3.80 Right

678 10/350 10/400 6.00 Illuppai Tree 3.20 Left

679 10/400 10/450 6.00 Kodukkapuli Tree 1.30 Left

680 6.80 Pungai Tree 0.50 Left

681 6.80 Illuppai Tree 1.40 Left

682 10/450 10/500 6.80 Arasam Tree 4.20 Left

683 6.50 Palm Tree 1.20 Left

684 6.50 Palm Tree 1.20 Left

685 6.50 Palm Tree 1.20 Left

686 6.50 Palm Tree 1.30 Left

687 6.50 Palm Tree 1.30 Left

688 6.80 Illuppai Tree 3.70 Right

689 10/500 10/550 6.80 Palm Tree 1.20 Left

690 10/550 10/600 6.80 Tamarind Tree 3.60 Left

691 10/600 10/650 6.80 Arasam Tree 3.20 Left

692 6.00 Gova Tree 0.40 Left

693 6.80 Neem Tree 1.20 Left

280

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

694 6.80 Palm Tree 1.20 Right

695 6.80 Illuppai Tree 1.30 Right

696 10/650 10/700 6.00 Illuppai Tree 3.80 Left

697 6.80 Illuppai Tree 1.50 Right

698 6.80 Neem Tree 0.90 Right

699 10/700 10/750 6.80 Neem Tree 0.50 Left

700 6.80 Palm Tree 12.00 Left

701 6.80 Tamarind Tree 2.10 Left

702 6.80 Illuppai Tree 2.20 Right

703 6.80 Illuppai Tree 2.20 Right

704 6.80 Tamarind Tree 2.00 Right

705 10/750 10/800 6.80 Neem Tree 0.50 Left

706 6.80 Neem Tree 0.30 Left

707 6.80 Neem Tree 0.30 Left

708 6.80 Tamarind Tree 1.00 Left

709 6.20 Tamarind Tree 2.20 Left

710 6.20 Tamarind Tree 2.20 Right

711 10/750 10/800 6.80 Neem Tree 0.50 Left

712 6.80 Neem Tree 0.30 Left

713 6.80 Neem Tree 0.30 Left

714 6.80 Tamarind Tree 1.00 Left

715 6.20 Tamarind Tree 2.20 Left

716 10/800 10/850 6.20 Tamarind Tree 2.80 Left

717 6.80 Palm Tree 1.20 Left

718 6.80 Illuppai Tree 1.40 Left

719 10/850 10/900 6.50 Palm Tree 1.20 Right

720 6.50 Palm Tree 1.20 Right

721 6.80 Neem Tree 1.00 Right

722 6.80 Tamarind Tree 3.80 Right

723 10/950 11/000 6.50 Palm Tree 1.20 Left

724 6.50 Palm Tree 1.20 Left

725 6.50 Palm Tree 1.20 Left

726 6.50 Palm Tree 1.20 Left

727 3.50 Tamarind Tree 4.30 Left

728 11/000 11/050 3.50 Tamarind Tree 4.30 Left

729 4.00 Tamarind Tree 4.20 Left

730 11/050 11/100 6.80 Illuppai Tree 2.20 Right

731 6.80 Illuppai Tree 1.90 Right

732 11/100 11/150 6.80 Illuppai Tree 2.90 Left

733 6.50 Neem Tree 2.90 Right

34.

35.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

734 11/200 11/250 6.80 Neem Tree 0.70 Right

735 11/250 11/300 6.80 Neem Tree 2.20 Left

736 6.80 Tamarind Tree 3.80 Left

737 6.00 Tamarind Tree 4.60 Right

738 6.20 Tamarind Tree 4.30 Right

739 11/300 11/350 6.80 Neem Tree 0.40 Left

740 6.50 Neem Tree 0.50 Right

741 11/350 11/400 6.80 Neem Tree 0.80 Right

742 11/400 11/450 6.80 Tamarind Tree 3.80 Left

743 6.80 Neem Tree 0.40 Right

744 6.80 Neem Tree 0.40 Right

745 6.50 Tamarind Tree 2.60 Right

746 11/450 11/500 6.80 Tamarind Tree 2.90 Left

747 6.50 Illuppai Tree 1.90 Left

748 6.80 Naval Tree 3.20 Left

749 6.50 Palm Tree 1.30 Right

750 6.80 Tamarind Tree 3.70 Right

751 6.80 Neem Tree 2.90 Right

752 11/500 11/550 6.80 Illuppai Tree 2.70 Left

753 6.80 Neem Tree 2.50 Left

754 6.80 Neem Tree 2.30 Right

755 6.80 Neem Tree 1.80 Right

756 11/500 11/550 6.80 Neem Tree 1.40 Left

757 6.80 Neem Tree 1.40 Left

758 6.50 Naval Tree 2.80 Left

759 11/550 11/600 6.50 Neem Tree 3.20 Left

760 6.80 Neem Tree 1.40 Left

761 6.00 Neem Tree 1.40 Right

762 6.80 Tamarind Tree 1.90 Right

763 6.80 Illuppai Tree 1.00 Right

764 6.80 Neem Tree 2.00 Right

765 11/600 11/650 6.50 Naval Tree 1.60 Left

766 6.80 Illuppai Tree 1.90 Left

767 6.80 Palm Tree 1.30 Right

768 6.00 Illuppai Tree 2.70 Right

769 11/650 11/700 6.80 Illuppai Tree 2.00 Left

770 6.80 Neem Tree 2.20 Left

771 6.00 Illuppai Tree 1.00 Right

772 6.00 Tamarind Tree 3.60 Right

773 6.00 Tamarind Tree 3.10 Right

282

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

774 11/700 11/750 6.80 Tamarind Tree 4.00 Left

775 6.50 Tamarind Tree 4.20 Left

776 6.50 Tamarind Tree 3.70 Left

777 6.50 Tamarind Tree 2.20 Left

778 6.00 Tamarind Tree 2.70 Right

779 6.00 Tamarind Tree 2.00 Right

780 6.50 Tamarind Tree 2.80 Right

781 6.80 Tamarind Tree 3.60 Right

782 11/800 11/850 6.80 Tamarind Tree 4.40 Left

783 6.80 Tamarind Tree 2.70 Right

784 6.80 Tamarind Tree 3.80 Right

785 6.80 Neem Tree 1.00 Right

786 11/850 11/900 6.80 Tamarind Tree 2.90 Left

787 6.80 Tamarind Tree 1.70 Left

788 6.80 Tamarind Tree 3.80 Left

789 6.80 Neem Tree 1.00 Right

790 6.80 Tamarind Tree 3.00 Right

791 6.80 Tamarind Tree 2.20 Right

792 11/900 11/950 6.80 Tamarind Tree 2.70 Left

793 6.80 Neem Tree 2.10 Left

794 6.80 Illuppai Tree 2.00 Left

795 6.80 Tamarind Tree 5.40 Right

796 11/950 12/000 6.80 Tamarind Tree 1.80 Left

797 6.80 Tamarind Tree 1.80 Left

798 6.80 Tamarind Tree 2.30 Right

799 6.50 Tamarind Tree 3.00 Right

800 12/000 12/050 5.50 Tamarind Tree 2.00 Left

801 5.50 Tamarind Tree 4.20 Left

802 5.50 Tamarind Tree 4.40 Left

803 6.50 Tamarind Tree 2.40 Right

804 6.50 Tamarind Tree 3.80 Right

805 12/050 12/100 6.50 Pencil Tree 0.50 Left

806 6.80 Tamarind Tree 1.50 Right

807 12/100 12/150 1.00 Tamarind Tree 2.40 Left

808 12/150 12/200 2.80 Tamarind Tree 4.40 Left

809 12/200 12/250 3.50 Tamarind Tree 4.80 Left

810 6.80 Tamarind Tree 2.90 Right

811 12/250 12/300 6.80 Tamarind Tree 4.30 Left

812 6.80 Tamarind Tree 2.80 Left

813 6.80 Tamarind Tree 2.80 Left

38.

39.

Section 7: Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

814 6.80 Illuppai Tree 2.10 Left

815 6.80 Tamarind Tree 2.00 Right

816 6.80 Tamarind Tree 2.50 Right

817 12/300 12/350 6.80 Neem Tree 0.70 Left

818 6.80 Tamarind Tree 2.80 Left

819 6.80 Tamarind Tree 2.60 Right

820 6.80 Tamarind Tree 2.80 Right

821 12/350 12/400 6.80 Tamarind Tree 2.40 Left

822 6.80 Tamarind Tree 1.20 Left

823 6.50 Illuppai Tree 1.20 Left

824 6.80 Tamarind Tree 1.80 Left

825 12/400 12/450 6.50 Illuppai Tree 2.40 Left

826 6.50 Vengai Tree 1.50 Right

827 12/450 12/500 6.80 Tamarind Tree 1.50 Left

828 6.80 Tamarind Tree 1.80 Left

829 6.80 Marutham Tree 2.80 Right

830 6.50 Illuppai Tree 2.70 Right

831 12/500 12/550 6.80 Tamarind Tree 1.00 Left

832 6.80 Tamarind Tree 1.30 Left

833 6.80 Tamarind Tree 1.40 Left

834 6.80 Tamarind Tree 1.40 Left

835 6.50 Illuppai Tree 2.70 Right

836 12/550 12/600 6.80 Tamarind Tree 2.20 Left

837 6.80 Tamarind Tree 2.00 Left

838 6.80 Tamarind Tree 2.20 Left

839 6.80 Tamarind Tree 1.10 Right

840 6.80 Vangai Tree 3.80 Right

841 6.80 Neem Tree 1.20 Right

842 12/600 12/650 6.80 Tamarind Tree 2.80 Left

843 6.80 Tamarind Tree 3.00 Left

844 6.80 Tamarind Tree 4.00 Right

845 6.80 Illuppai Tree 1.00 Right

846 6.80 Tamarind Tree 1.80 Right

847 6.80 Marutham Tree 2.20 Right

848 12/650 12/700 6.80 Marutham Tree 1.90 Left

849 6.80 Naval Tree 1.40 Right

850 6.80 Palm Tree 1.20 Right

851 12/750 12/800 6.00 Marutham Tree 2.90 Left

852 6.80 Marutham Tree 1.80 Left

853 6.80 Tamarind Tree 1.80 Left

284

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

854 6.80 Tamarind Tree 2.40 Right

855 6.80 Tamarind Tree 1.00 Right

856 6.80 Tamarind Tree 1.90 Right

857 12/750 12/800 6.80 Tamarind Tree 2.40 Left

858 6.80 Tamarind Tree 2.00 Left

859 6.80 Tamarind Tree 2.40 Right

860 12/800 12/850 6.80 Tamarind Tree 0.80 Left

861 6.80 Tamarind Tree 1.00 Left

862 6.80 Illuppai Tree 2.50 Left

863 6.80 Tamarind Tree 1.40 Left

864 6.80 Tamarind Tree 2.00 Left

865 6.80 Tamarind Tree 2.20 Right

866 6.80 Tamarind Tree 2.10 Right

867 12/850 12/900 6.80 Tamarind Tree 1.00 Left

868 6.80 Tamarind Tree 1.70 Left

869 6.80 Tamarind Tree 2.50 Right

870 6.80 Tamarind Tree 1.70 Right

871 6.80 Tamarind Tree 1.40 Right

872 6.80 Tamarind Tree 1.20 Right

873 12/900 12/950 6.80 Tamarind Tree 2.50 Left

874 6.80 Illuppai Tree 1.80 Right

875 6.80 Tamarind Tree 1.70 Right

876 6.80 Pungai Tree 0.40 Right

877 6.80 Pungai Tree 0.40 Right

878 12/950 13/000 6.80 Neem Tree 1.40 Left

879 6.80 Tamarind Tree 2.90 Right

880 13/000 13/050 6.50 Neem Tree 1.90 Left

881 4.60 Tamarind Tree 3.30 Left

882 6.50 Pungai Tree 1.00 Right

883 6.80 Naval Tree 2.40 Right

884 13/050 13/100 4.70 Tamarind Tree 4.80 Left

885 6.50 Tamarind Tree 2.60 Left

886 6.50 Neem Tree 1.70 Right

887 5.80 Neem Tree 2.00 Right

888 13/100 13/150 6.50 Tamarind Tree 6.20 Left

889 5.80 Tamarind Tree 2.30 Right

890 13/150 13/200 6.50 Tamarind Tree 3.20 Left

891 6.50 Tamarind Tree 3.30 Left

892 6.00 Tamarind Tree 2.80 Right

893 5.50 Tamarind Tree 4.20 Right

42.

43.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

894 13/200 13/250 6.80 Tamarind Tree 4.20 Left

895 6.80 Tamarind Tree 3.00 Left

896 13/250 13/300 5.80 Tamarind Tree 4.40 Left

897 6.50 Tamarind Tree 2.60 Left

898 6.00 Tamarind Tree 4.05 Right

899 5.80 Tamarind Tree 5.60 Right

900 13/300 13/350 6.80 Tamarind Tree 3.40 Left

901 6.40 Tamarind Tree 2.80 Left

902 6.40 Tamarind Tree 3.40 Left

903 6.40 Tamarind Tree 3.90 Right

904 6.20 Tamarind Tree 3.40 Right

905 13/350 13/400 6.50 Tamarind Tree 3.60 Left

906 5.00 Tamarind Tree 3.30 Right

907 13/350 13/400 6.30 Tamarind Tree 2.90 Left

908 6.80 Neem Tree 0.30 Right

909 6.50 Tamarind Tree 2.00 Right

910 13/400 13/450 6.50 Illuppai Tree 1.40 Left

911 6.50 Tamarind Tree 4.60 Left

912 6.50 Illuppai Tree 2.20 Right

913 6.80 Illuppai Tree 1.40 Right

914 13/450 13/500 6.50 Tamarind Tree 2.00 Left

915 5.80 Tamarind Tree 3.70 Left

916 6.80 Neem Tree 0.70 Right

917 6.40 Tamarind Tree 2.00 Right

918 6.00 Tamarind Tree 2.50 Right

919 13/500 13/550 6.00 Tamarind Tree 2.10 Right

920 6.00 Tamarind Tree 5.20 Right

921 13/550 13/600 6.50 Illuppai Tree 3.20 Left

922 6.80 Illuppai Tree 3.30 Left

923 6.50 Illuppai Tree 3.30 Right

924 6.50 Tamarind Tree 2.40 Right

925 13/600 13/650 6.80 Tamarind Tree 6.20 Right

926 13/650 13/700 5.80 Tamarind Tree 5.60 Left

927 6.50 Tamarind Tree 5.40 Left

928 6.80 Tamarind Tree 3.20 Left

929 6.00 Tamarind Tree 3.40 Right

930 6.80 Tamarind Tree 3.70 Right

931 6.80 Tamarind Tree 3.70 Right

932 13/700 13/750 6.40 Tamarind Tree 5.20 Left

933 6.30 Tamarind Tree 4.20 Left

286

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From To

934 6.00 Tamarind Tree 3.10 Right

935 13/750 13/800 6.80 Tamarind Tree 3.80 Left

936 6.00 Tamarind Tree 1.20 Left

937 6.80 Tamarind Tree 2.40 Right

938 6.80 Tamarind Tree 2.00 Right

939 13/800 13/850 6.50 Tamarind Tree 2.80 Left

940 6.80 Tamarind Tree 2.30 Left

941 6.80 Tamarind Tree 2.30 Left

942 6.80 Tamarind Tree 2.20 Right

943 6.80 Tamarind Tree 3.20 Right

944 6.80 Tamarind Tree 2.90 Right

945 13/850 13/900 6.80 Tamarind Tree 2.00 Left

946 6.50 Tamarind Tree 2.00 Left

947 6.50 Tamarind Tree 2.30 Left

948 6.80 Tamarind Tree 2.20 Right

949 6.80 Tamarind Tree 2.40 Right

950 6.80 Tamarind Tree 2.80 Right

951 13/900 13/950 6.50 Tamarind Tree 2.90 Left

952 6.50 Tamarind Tree 3.40 Left

953 6.50 Tamarind Tree 2.90 Right

954 6.10 Tamarind Tree 6.20 Right

955 13/950 14/000 5.50 Illuppai Tree 1.50 Left

956 5.80 Tamarind Tree 3.20 Left

957 6.00 Tamarind Tree 5.30 Left

958 5.70 Tamarind Tree 6.40 Right

959 14/000 14/050 5.50 Tamarind Tree 3.50 Left

960 6.80 Tamarind Tree 3.10 Right

961 6.80 Neem Tree 1.10 Right

962 6.80 Illuppai Tree 1.40 Right

963 14/050 14/100 6.80 Tamarind Tree 3.40 Left

964 6.50 Illuppai Tree 1.70 Left

965 6.50 Vangai Tree 1.20 Right

966 5.40 Tamarind Tree 2.60 Right

967 5.50 Tamarind Tree 2.50 Right

968 14/100 14/150 6.50 Tamarind Tree 3.40 Left

969 6.50 Illuppai Tree 1.60 Left

970 6.50 Illuppai Tree 2.20 Left

971 5.00 Tamarind Tree 7.20 Right

972 6.00 Tamarind Tree 1.80 Right

973 6.00 Tamarind Tree 2.30 Right

46.

47.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

974 14/150 14/200 6.80 Tamarind Tree 3.20 Left

975 6.50 Tamarind Tree 2.10 Left

976 6.50 Tamarind Tree 2.90 Left

977 6.50 Neem Tree 0.40 Right

978 6.50 Vangai Tree 1.30 Right

979 14/200 14/250 6.80 Tamarind Tree 2.90 Left

980 6.50 Illuppai Tree 0.90 Left

981 6.80 Tamarind Tree 0.90 Left

982 6.80 Tamarind Tree 2.70 Right

983 6.80 Tamarind Tree 4.40 Right

984 6.80 Tamarind Tree 3.80 Right

985 14/250 14/300 6.50 Tamarind Tree 3.50 Left

986 6.50 Tamarind Tree 2.70 Left

987 6.50 Tamarind Tree 4.80 Left

988 6.50 Tamarind Tree 3.30 Right

989 6.50 Tamarind Tree 5.20 Right

990 14/300 14/350 6.50 Tamarind Tree 4.20 Left

991 6.50 Neem Tree 1.20 Right

992 6.50 Neem Tree 1.20 Right

993 6.80 Tamarind Tree 1.40 Right

994 6.50 Illuppai Tree 4.40 Right

995 14/350 14/400 6.80 Tamarind Tree 1.30 Left

996 6.80 Tamarind Tree 3.00 Left

997 6.20 Tamarind Tree 3.80 Right

998 6.80 Tamarind Tree 3.20 Right

999 14/400 14/450 6.50 Tamarind Tree 2.80 Right

1000 14/400 14/450 6.80 Neem Tree 1.30 Right

1001 6.80 Neem Tree 1.00 Right

1002 14/450 14/500 6.80 Illuppai Tree 1.30 Right

1003 14/500 14/550 6.50 Illuppai Tree 2.70 Left

1004 6.50 Neem Tree 1.80 Left

1005 6.80 Tamarind Tree 2.20 Right

1006 6.50 Tamarind Tree 4.90 Right

1007 6.50 Tamarind Tree 2.70 Right

1008 14/550 14/600 6.50 Tamarind Tree 2.60 Left

1009 6.50 Tamarind Tree 2.80 Left

1010 6.50 Tamarind Tree 2.50 Left

1011 6.50 Tamarind Tree 2.90 Right

1012 6.50 Tamarind Tree 1.50 Right

1013 6.50 Tamarind Tree 3.50 Right

288

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1014 14/600 14/650 6.80 Tamarind Tree 3.40 Left

1015 6.50 Neem Tree 0.70 Left

1016 6.50 Neem Tree 0.50 Left

1017 6.50 Neem Tree 0.50 Left

1018 6.50 Neem Tree 0.50 Left

1019 14/650 14/700 6.50 Banyan Tree 3.00 Left

1020 6.80 Neem Tree 0.90 Right

1021 6.80 Neem Tree 0.50 Right

1022 6.80 Neem Tree 0.50 Right

1023 6.50 Neem Tree 1.00 Right

1024 6.50 Neem Tree 1.30 Right

1025 14/700 14/750 6.50 Neem Tree 1.50 Left

1026 6.50 Naval Tree 3.40 Left

1027 6.80 Neem Tree 1.40 Right

1028 14/750 14/800 6.80 Neem Tree 0.30 Left

1029 6.50 Illuppai Tree 0.50 Right

1030 14/800 14/850 6.50 Tamarind Tree 1.70 Left

1031 6.50 Tamarind Tree 2.80 Left

1032 6.50 Tamarind Tree 3.20 Left

1033 6.50 Tamarind Tree 2.00 Right

1034 6.50 Tamarind Tree 2.40 Right

1035 6.80 Tamarind Tree 2.40 Right

1036 14/850 14/900 6.50 Tamarind Tree 4.20 Left

1037 6.50 Tamarind Tree 1.20 Left

1038 6.50 Tamarind Tree 1.30 Left

1039 6.50 Tamarind Tree 2.50 Left

1040 6.50 Tamarind Tree 3.20 Left

1041 6.80 Tamarind Tree 3.50 Right

1042 6.80 Tamarind Tree 3.70 Right

1043 6.80 Tamarind Tree 4.70 Right

1044 14/900 14/950 6.50 Tamarind Tree 1.20 Left

1045 6.50 Tamarind Tree 1.40 Left

1046 6.50 Tamarind Tree 2.20 Right

1047 14/950 15/000 6.80 Tamarind Tree 1.70 Left

1048 6.80 Neem Tree 0.90 Left

1049 6.80 Neem Tree 0.50 Left

1050 6.50 Tamarind Tree 0.50 Left

1051 6.50 Tamarind Tree 0.50 Left

1052 6.50 Tamarind Tree 0.50 Left

1053 6.00 Fire wood 0.90 Left

50.

51.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1054 6.00 Tamarind Tree 2.50 Right

1055 15/000 15/050 0.20 Tamarind Tree 1.20 Left

1056 0.70 Tamarind Tree 1.30 Left

1057 15/000 15/050 0.50 Tamarind Tree 1.70 Left

1058 0.50 Tamarind Tree 1.90 Left

1059 0.70 Tamarind Tree 1.50 Left

1060 15/050 15/100 0.80 Tamarind Tree 2.10 Left

1061 1.00 Tamarind Tree 2.40 Left

1062 2.00 Tamarind Tree 2.40 Left

1063 15/100 15/150 1.00 Illuppai Tree 3.00 Left

1064 1.00 Tamarind Tree 1.20 Left

1065 1.00 Tamarind Tree 1.40 Left

1066 2.00 Illuppai Tree 2.00 Left

1067 1.50 Tamarind Tree 2.20 Left

1068 15/200 15/250 0.30 Palm Tree 1.30 Left

1069 0.40 Naval Tree 0.50 Left

1070 1.00 Neem Tree 0.50 Left

1071 1.00 Neem Tree 0.50 Left

1072 15/250 15/300 5.00 Tamarind Tree 0.50 Left

1073 5.00 Tamarind Tree 2.40 Left

1074 5.50 Illuppai Tree 1.90 Left

1075 15/300 15/350 6.50 Tamarind Tree 3.00 Left

1076 6.00 Tamarind Tree 2.90 Left

1077 6.00 Palm Tree 1.30 Left

1078 6.00 Palm Tree 1.30 Left

1079 6.80 Tamarind Tree 1.20 Left

1080 15/350 15/400 6.80 Tamarind Tree 2.90 Left

1081 6.50 Tamarind Tree 3.10 Left

1082 6.50 Tamarind Tree 2.70 Left

1083 6.80 Tamarind Tree 2.90 Left

1084 6.80 Tamarind Tree 1.50 Left

1085 6.80 Tamarind Tree 2.00 Right

1086 6.50 Neem Tree 2.00 Right

1087 6.50 Tamarind Tree 1.20 Right

1088 15/400 15/450 6.50 Tamarind Tree 1.70 Left

1089 6.50 Tamarind Tree 2.20 Left

1090 6.80 Tamarind Tree 1.00 Right

1091 6.50 Tamarind Tree 2.50 Right

1092 15/450 15/500 6.50 Neem Tree 2.00 Left

1093 6.50 Palm Tree 1.20 Left

290

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1094 15/500 15/550 6.50 Neem Tree 1.00 Left

1095 6.80 Neem Tree 1.20 Left

1096 6.80 Illuppai Tree 3.20 Left

1097 6.50 Palm Tree 1.30 Right

1098 15/550 15/600 6.80 Palm Tree 1.20 Left

1099 6.80 Palm Tree 1.20 Left

1100 6.80 Illuppai Tree 4.00 Right

1101 15/600 15/650 6.80 Illuppai Tree 3.20 Left

1102 6.80 Pungai Tree 1.00 Left

1103 6.50 Neem Tree 1.00 Left

1104 6.50 Neem Tree 1.00 Left

1105 6.80 Neem Tree 1.00 Left

1106 6.80 Palm Tree 1.20 Left

1107 6.50 Palm Tree 1.20 Right

1108 6.50 Palm Tree 1.20 Right

1109 6.50 Palm Tree 1.20 Right

1110 6.50 Neem Tree 1.00 Right

1111 15/650 15/700 6.80 Neem Tree 2.60 Left

1112 6.80 Neem Tree 1.20 Left

1113 6.80 Neem Tree 2.50 Left

1114 15/650 15/700 6.80 Neem Tree 2.20 Left

1115 6.80 Pungai Tree 1.00 Left

1116 15/700 15/750 6.00 Neem Tree 1.30 Left

1117 6.00 Neem Tree 1.00 Left

1118 6.00 Neem Tree 1.30 Left

1119 6.00 Neem Tree 2.60 Left

1120 6.50 Neem Tree 1.30 Right

1121 15/750 15/800 6.80 Neem Tree 1.00 Left

1122 6.50 Neem Tree 1.90 Left

1123 6.00 Neem Tree 1.50 Left

1124 15/800 15/850 6.50 Neem Tree 1.30 Left

1125 6.50 Neem Tree 1.30 Left

1126 6.80 Neem Tree 0.90 Left

1127 6.80 Neem Tree 0.50 Left

1128 6.80 Neem Tree 1.00 Left

1129 15/850 15/900 6.80 Neem Tree 1.00 Left

1130 6.80 Neem Tree 1.00 Left

1131 6.80 Neem Tree 1.00 Left

1132 6.80 Neem Tree 1.00 Left

1133 6.80 Neem Tree 1.00 Left

54.

55.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1134 15/900 15/950 6.50 Tamarind Tree 3.20 Left

1135 6.50 Tamarind Tree 2.90 Left

1136 6.80 Palm Tree 1.20 Right

1137 6.80 Palm Tree 1.20 Right

1138 6.80 Palm Tree 1.30 Right

1139 6.80 Palm Tree 1.30 Right

1140 15/950 16/000 6.50 Tamarind Tree 3.60 Left

1141 6.80 Tamarind Tree 4.70 Right

1142 6.80 Tamarind Tree 2.50 Right

1143 16/000 16/050 6.80 Tamarind Tree 1.70 Left

1144 6.80 Tamarind Tree 2.20 Left

1145 6.80 Tamarind Tree 3.80 Left

1146 6.50 Tamarind Tree 2.60 Right

1147 16/050 16/100 5.50 Tamarind Tree 2.00 Left

1148 5.80 Tamarind Tree 1.40 Right

1149 6.30 Tamarind Tree 1.75 Right

1150 6.50 Tamarind Tree 2.00 Right

1151 6.50 Tamarind Tree 1.10 Right

1152 16/100 16/150 6.50 Neem Tree 0.70 Left

1153 6.20 Tamarind Tree 2.90 Left

1154 6.50 Tamarind Tree 3.80 Right

1155 6.50 Tamarind Tree 1.60 Right

1156 16/150 16/200 4.50 Tamarind Tree 4.50 Left

1157 6.10 Tamarind Tree 6.30 Right

1158 6.80 Tamarind Tree 2.70 Right

1159 16/200 16/250 6.80 Tamarind Tree 1.90 Left

1160 6.80 Tamarind Tree 3.20 Left

1161 6.00 Tamarind Tree 3.80 Left

1162 6.80 Tamarind Tree 2.20 Right

1163 16/250 16/300 6.00 Tamarind Tree 5.90 Left

1164 5.60 Tamarind Tree 3.10 Right

1165 16/300 16/350 5.90 Tamarind Tree 3.00 Left

1166 5.90 Tamarind Tree 3.00 Right

1167 16/350 16/400 6.50 Tamarind Tree 1.70 Left

1168 6.20 Tamarind Tree 2.60 Left

1169 5.70 Tamarind Tree 3.10 Right

1170 5.90 Tamarind Tree 4.10 Right

1171 16/400 16/450 6.80 Tamarind Tree 4.40 Left

1172 6.20 Tamarind Tree 4.40 Left

1173 5.70 Tamarind Tree 2.60 Right

292

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1174 6.80 Tamarind Tree 3.60 Right

1175 16/450 16/500 6.80 Tamarind Tree 3.30 Left

1176 6.80 Tamarind Tree 3.50 Left

1177 6.80 Tamarind Tree 4.20 Right

1178 6.80 Tamarind Tree 6.80 Right

1179 16/550 16/600 6.80 Tamarind Tree 5.20 Left

1180 6.80 Tamarind Tree 3.70 Right

1181 16/650 16/700 4.80 Tamarind Tree 3.70 Left

1182 6.80 Tamarind Tree 3.90 Right

1183 16/700 16/750 5.20 Tamarind Tree 3.20 Left

1184 6.80 Tamarind Tree 2.70 Right

1185 6.00 Pungai Tree 0.40 Right

1186 16/750 16/800 6.80 Tamarind Tree 1.50 Left

1187 6.80 Tamarind Tree 2.60 Left

1188 6.00 Vangai Tree 0.70 Right

1189 6.80 Vagai Tree 0.40 Right

1190 5.90 Tamarind Tree 3.60 Right

1191 16/800 16/850 6.80 Tamarind Tree 2.70 Left

1192 6.80 Tamarind Tree 2.50 Right

1193 16/800 16/850 6.10 Tamarind Tree 2.20 Left

1194 6.00 Tamarind Tree 3.00 Left

1195 6.80 Palm Tree 1.20 Right

1196 6.80 Palm Tree 1.20 Right

1197 6.80 Neem Tree 0.70 Right

1198 6.80 Neem Tree 0.40 Right

1199 16/850 16/900 6.80 Palm Tree 1.30 Left

1200 6.80 Palm Tree 1.20 Left

1201 6.80 Tamarind Tree 3.20 Right

1202 6.50 Palm Tree 1.20 Right

1203 6.50 Vagai Tree 1.20 Right

1204 16/900 16/950 6.80 Tamarind Tree 2.30 Left

1205 6.80 Neem Tree 0.60 Left

1206 6.50 Vangai Tree 1.70 Right

1207 6.80 Tamarind Tree 2.90 Right

1208 16/950 17/000 6.80 Tamarind Tree 2.70 Left

1209 5.30 Tamarind Tree 2.50 Right

1210 6.80 Neem Tree 2.20 Right

1211 17/000 17/050 6.20 Tamarind Tree 2.10 Left

1212 6.80 Palm Tree 1.20 Right

1213 6.80 Neem Tree 0.40 Right

58.

59.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1214 4.80 Palm Tree 1.30 Right

1215 6.80 Neem Tree 1.20 Right

1216 6.80 Neem Tree 0.60 Right

1217 17/100 17/150 6.80 Palm Tree 1.20 Left

1218 6.80 Palm Tree 1.20 Right

1219 6.80 Illuppai Tree 1.20 Right

1220 6.80 Neem Tree 1.10 Right

1221 17/150 17/200 6.80 Vagai Tree 1.20 Left

1222 6.80 Neem Tree 1.20 Left

1223 6.80 Palm Tree 1.20 Left

1224 6.80 Palm Tree 1.20 Left

1225 6.80 Palm Tree 1.20 Left

1226 6.80 Palm Tree 1.20 Left

1227 6.00 Neem Tree 0.70 Right

1228 6.50 Palm Tree 1.30 Right

1229 17/200 17/250 6.80 Tamarind Tree 1.50 Left

1230 6.80 Palm Tree 1.20 Left

1231 6.80 Tamarind Tree 1.80 Right

1232 6.00 Tamarind Tree 2.80 Right

1233 17/250 17/300 5.80 Tamarind Tree 2.10 Left

1234 5.90 Tamarind Tree 2.80 Left

1235 6.00 Tamarind Tree 1.80 Right

1236 6.80 Neem Tree 0.40 Right

1237 17/300 17/350 6.80 Tamarind Tree 2.00 Left

1238 6.30 Tamarind Tree 3.40 Right

1239 6.80 Tamarind Tree 1.30 Right

1240 6.80 Tamarind Tree 1.80 Right

1241 17/350 17/400 6.50 Neem Tree 0.60 Left

1242 6.50 Neem Tree 0.40 Left

1243 17/350 17/400 6.50 Terminalia Tree 1.20 Left

1244 6.50 Tamarind Tree 1.70 Left

1245 6.50 Terminalia Tree 1.10 Right

1246 6.50 Terminalia Tree 1.10 Right

1247 6.50 Terminalia Tree 1.20 Right

1248 17/400 17/450 6.00 Palm Tree 1.20 Left

1249 6.50 Neem Tree 0.40 Left

1250 6.50 Jambolana Tree 2.20 Left

1251 6.50 Palm Tree 1.20 Left

1252 6.50 Palm Tree 1.20 Left

1253 6.50 Palm Tree 1.20 Left

294

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1254 6.20 Palm Tree 1.20 Right

1255 6.20 Palm Tree 1.20 Right

1256 6.50 Palm Tree 1.20 Right

1257 6.50 Palm Tree 1.20 Right

1258 6.50 Palm Tree 1.20 Right

1259 17/450 17/500 6.50 Palm Tree 1.50 Left

1260 6.50 Palm Tree 1.30 Left

1261 6.50 Neem Tree 0.60 Left

1262 6.50 Neem Tree 0.60 Left

1263 6.50 Palm Tree 1.20 Right

1264 6.50 Palm Tree 1.20 Right

1265 6.50 Palm Tree 1.20 Right

1266 6.50 Tamarind Tree 2.70 Right

1267 17/500 17/550 6.50 Tamarind Tree 3.20 Left

1268 6.50 Palm Tree 1.20 Left

1269 6.00 Tamarind Tree 2.20 Right

1270 6.50 Palm Tree 1.20 Right

1271 6.50 Neem Tree 0.90 Right

1272 6.50 Neem Tree 0.40 Right

1273 6.50 Tamarind Tree 3.60 Right

1274 17/550 17/600 6.50 Tamarind Tree 2.60 Left

1275 6.50 Palm Tree 1.20 Left

1276 6.50 Peepal Tree 3.40 Left

1277 6.50 Tamarind Tree 3.50 Right

1278 6.50 Tamarind Tree 2.90 Right

1279 17/600 17/650 6.50 Neem Tree 1.20 Left

1280 6.50 Palm Tree 1.30 Left

1281 6.50 Palm Tree 1.30 Left

1282 6.50 Palm Tree 1.30 Left

1283 6.50 Tamarind Tree 3.80 Left

1284 6.50 Tamarind Tree 1.20 Left

1285 6.50 Tamarind Tree 4.80 Right

1286 6.50 Tamarind Tree 2.90 Right

1287 6.50 Palm Tree 1.20 Right

1288 6.20 Tamarind Tree 3.20 Right

1289 17/650 17/700 6.00 Tamarind Tree 3.70 Left

1290 5.90 Palm Tree 0.60 Left

1291 5.90 Palm Tree 0.60 Left

1292 6.50 Tamarind Tree 3.30 Left

1293 6.50 Palm Tree 1.20 Left

62.

63.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1294 6.50 Palm Tree 1.20 Left

1295 6.50 Palm Tree 1.20 Left

1296 6.50 Tamarind Tree 1.80 Right

1297 6.50 Neem Tree 0.90 Right

1298 6.50 Palm Tree 1.20 Right

1299 6.50 Palm Tree 1.20 Right

1300 6.50 Palm Tree 1.20 Right

1301 6.50 Palm Tree 1.20 Right

1302 6.50 Palm Tree 1.20 Right

1303 6.50 Palm Tree 1.20 Right

1304 6.50 Palm Tree 1.20 Right

1305 6.50 Palm Tree 1.20 Right

1306 17/700 17/750 6.50 Ptrocarpus marsupium

1.40

Left

1307 6.50 Palm Tree 1.30 Right

1308 6.50 Palm Tree 1.30 Right

1309 6.50 Palm Tree 1.30 Right

1310 6.50 Palm Tree 1.30 Right

1311 6.50 Palm Tree 1.30 Right

1312 6.50 Palm Tree 1.30 Right

1313 6.50 Palm Tree 1.30 Right

1314 6.50 Palm Tree 1.30 Right

1315 6.50 Palm Tree 1.30 Right

1316 6.50 Palm Tree 1.30 Right

1317 6.50 Palm Tree 1.30 Right

1318 17/750 17/800 6.50 Palm Tree 1.20 Left

1319 6.50 Palm Tree 1.30 Right

1320 6.50 Palm Tree 1.30 Right

1321 6.50 Palm Tree 1.30 Right

1322 6.50 Palm Tree 1.30 Right

1323 6.50 Palm Tree 1.30 Right

1324 6.50 Palm Tree 1.30 Right

1325 6.50 Palm Tree 1.30 Right

1326 6.50 Palm Tree 1.30 Right

1327 6.50 Palm Tree 1.30 Right

1328 6.50 Palm Tree 1.30 Right

1329 6.50 Palm Tree 1.30 Right

1330 6.50 Palm Tree 1.30 Right

1331 6.50 Palm Tree 1.30 Right

1332 6.50 Palm Tree 1.30 Right

1333 6.50 Palm Tree 1.30 Right

296

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1334 6.50 Palm Tree 1.30 Right

1335 6.50 Palm Tree 1.30 Right

1336 6.50 Palm Tree 1.30 Right

1337 6.50 Palm Tree 1.30 Right

1338 6.50 Palm Tree 1.30 Right

1339 6.50 Palm Tree 1.30 Right

1340 17/800 17/850 6.50 Mowa Tree 2.00 Left

1341 6.50 Mowa Tree 1.30 Left

1342 6.50 Palm Tree 1.20 Left

1343 6.50 Palm Tree 1.20 Left

1344 6.50 Palm Tree 1.20 Left

1345 6.50 Palm Tree 1.20 Left

1346 6.50 Palm Tree 1.20 Left

1347 6.50 Palm Tree 1.20 Left

1348 6.50 Palm Tree 1.20 Left

1349 6.50 Palm Tree 1.20 Left

1350 6.50 Palm Tree 1.20 Left

1351 6.50 Palm Tree 1.20 Right

1352 6.50 Palm Tree 1.20 Right

1353 6.50 Neem Tree 1.40 Right

1354 17/850 17/900 6.50 Palm Tree 1.20 Left

1355 6.50 Palm Tree 1.20 Left

1356 6.50 Palm Tree 1.20 Left

1357 6.50 Palm Tree 1.20 Left

1358 6.50 Palm Tree 1.20 Left

1359 17/900 17/950 6.50 Palm Tree 1.30 Left

1360 6.50 Palm Tree 1.30 Right

1361 6.50 Palm Tree 1.30 Right

1362 17/950 18/000 6.50 Tamarind Tree 1.20 Left

1363 6.50 Neem Tree 1.30 Left

1364 6.50 Neem Tree 0.40 Left

1365 6.50 Palm Tree 1.20 Right

1366 18/000 18/050 6.50 Neem Tree 0.40 Left

1367 6.50 Neem Tree 0.40 Left

1368 6.50 Neem Tree 1.20 Left

1369 6.40 Tamarind Tree 2.70 Left

1370 6.50 Neem Tree 0.90 Right

1371 18/100 18/150 6.50 Palm Tree 1.30 Left

1372 6.40 Neem Tree 1.20 Left

1373 6.50 Tamarind Tree 2.40 Left

66.

67.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1374 18/150 18/200 6.50 Tamarind Tree 2.10 Left

1375 5.20 Neem Tree 1.00 Left

1376 6.50 Neem Tree 0.70 Left

1377 6.50 Neem Tree 0.70 Left

1378

6.50 Ptrocarpus marsupium

0.70

Right

1379 6.50 pongame oil Tree 0.20 Right

1380 18/200 18/250 6.50 Tamarind Tree 2.10 Right

1381 18/250 18/300 6.50 Neem Tree 0.20 Left

1382 6.50 Tamarind Tree 2.20 Right

1383 18/300 18/350 6.50 Peepal Tree 2.20 Left

1384 6.50 Neem Tree 0.40 Left

1385 6.50 Palm Tree 1.30 Left

1386 6.50 Palm Tree 1.20 Left

1387 6.50 Palm Tree 1.20 Left

1388 18/350 18/400 6.50 Palm Tree 1.20 Left

1389 6.50 Palm Tree 1.20 Left

1390 6.50 Tamarind Tree 1.70 Left

1391 6.50 Palm Tree 1.20 Left

1392 6.50 Palm Tree 1.20 Left

1393 6.50 Palm Tree 1.20 Left

1394 6.50 Palm Tree 1.20 Left

1395 6.50 Tamarind Tree 3.40 Right

1396 6.50 Neem Tree 1.00 Right

1397 18/400 18/450 6.50 Palm Tree 1.20 Left

1398 6.50 Palm Tree 1.20 Left

1399 6.50 Palm Tree 1.20 Left

1400 6.50 Palm Tree 1.20 Left

1401 6.50 Palm Tree 1.20 Right

1402 6.50 Palm Tree 1.20 Right

1403 6.50 Palm Tree 1.20 Right

1404 6.50 Palm Tree 1.20 Right

1405 6.50 Tamarind Tree 3.00 Right

1406 6.50 Tamarind Tree 3.50 Right

1407 18/450 18/500 6.50 Palm Tree 1.20 Left

1408 6.50 Palm Tree 1.20 Left

1409 6.20 Tamarind Tree 3.20 Left

1410 6.50 Palm Tree 1.20 Left

1411 6.50 Palm Tree 1.20 Left

1412 6.50 Palm Tree 1.20 Left

1413 6.50 Palm Tree 1.20 Left

298

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1414 6.50 Palm Tree 1.20 Left

1415 6.50 Palm Tree 1.20 Left

1416 6.50 Palm Tree 1.20 Left

1417 6.50 Palm Tree 1.20 Left

1418 6.50 Palm Tree 1.20 Left

1419 6.50 Palm Tree 1.20 Left

1420 6.50 Palm Tree 1.20 Left

1421 6.50 Palm Tree 1.20 Left

1422 6.50 Palm Tree 1.20 Left

1423 6.50 Palm Tree 1.20 Left

1424 6.50 Palm Tree 1.20 Left

1425 6.50 Tamarind Tree 2.30 Left

1426 6.30 Palm Tree 1.20 Right

1427 6.50 Palm Tree 1.20 Right

1428 6.50 Palm Tree 1.20 Right

1429 6.50 Palm Tree 1.20 Right

1430 6.50 Palm Tree 1.20 Right

1431 6.30 Tamarind Tree 3.30 Right

1432 6.40 Tamarind Tree 2.50 Right

1433 18/500 18/550 6.50 Neem Tree 0.40 Left

1434 6.50 Palm Tree 1.20 Left

1435 6.50 Palm Tree 1.20 Left

1436 6.50 Palm Tree 1.20 Left

1437 6.50 Palm Tree 1.20 Left

1438 6.50 Palm Tree 1.20 Left

1439 6.50 Palm Tree 1.20 Left

1440 6.50 Palm Tree 1.20 Left

1441 6.50 Palm Tree 1.20 Left

1442 6.50 Palm Tree 1.20 Left

1443 6.50 Palm Tree 1.20 Left

1444 6.50 Palm Tree 1.20 Left

1445 6.50 Palm Tree 1.20 Left

1446 6.50 Palm Tree 1.20 Left

1447 6.50 Palm Tree 1.20 Left

1448 6.50 Palm Tree 1.20 Left

1449 6.50 Palm Tree 1.20 Left

1450 6.50 Palm Tree 1.20 Left

1451 6.50 Palm Tree 1.20 Left

1452 6.50 Palm Tree 1.20 Left

1453 6.50 Palm Tree 1.20 Left

70.

71.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1454 6.50 Palm Tree 1.20 Left

1455 6.50 Palm Tree 1.20 Left

1456 6.50 Palm Tree 1.20 Left

1457 6.50 Tamarind Tree 1.20 Right

1458 6.50 Palm Tree 1.00 Right

1459 6.50 Palm Tree 1.00 Right

1460 6.50 Palm Tree 1.00 Right

1461 6.50 Palm Tree 1.00 Right

1462 6.50 Palm Tree 1.00 Right

1463 6.30 Neem Tree 1.00 Right

1464 18/550 18/600 6.50 Neem Tree 0.30 Left

1465 6.50 Palm Tree 1.20 Left

1466 6.50 Palm Tree 1.20 Left

1467 6.50 Palm Tree 1.20 Left

1468 6.50 Palm Tree 1.20 Left

1469 6.50 Palm Tree 1.20 Left

1470 6.50 Palm Tree 1.20 Left

1471 6.50 Palm Tree 1.20 Left

1472 6.50 Palm Tree 1.20 Left

1473 6.50 Palm Tree 1.20 Left

1474 6.50 Palm Tree 1.20 Left

1475 6.50 Palm Tree 1.20 Left

1476 6.50 Palm Tree 1.20 Left

1477 6.50 Palm Tree 1.20 Left

1478 6.50 Palm Tree 1.20 Left

1479 6.50 Palm Tree 1.20 Left

1480 6.50 Palm Tree 1.20 Left

1481 6.50 Palm Tree 1.20 Left

1482 6.50 Palm Tree 1.20 Left

1483 6.50 Palm Tree 1.20 Left

1484 6.50 Palm Tree 1.20 Left

1485 18/600 18/650 6.80 Palm Tree 1.20 Left

1486 6.80 Palm Tree 1.20 Left

1487 6.80 Palm Tree 1.20 Left

1488 6.80 Palm Tree 1.20 Left

1489 6.80 Palm Tree 1.20 Left

1490 6.80 Palm Tree 1.20 Left

1491 6.80 Palm Tree 1.20 Left

1492 6.80 Palm Tree 1.20 Left

1493 6.80 Palm Tree 1.20 Left

300

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1494 6.80 Palm Tree 1.20 Left

1495 6.80 Palm Tree 1.20 Left

1496 6.80 Palm Tree 1.20 Left

1497 6.80 Palm Tree 1.20 Left

1498 6.80 Palm Tree 1.20 Left

1499 6.80 Palm Tree 1.20 Left

1500 6.80 Palm Tree 1.20 Left

1501 6.80 Palm Tree 1.20 Left

1502 6.80 Palm Tree 1.20 Left

1503 6.50 Tamarind Tree 1.20 Right

1504 18/650 18/700 6.20 Tamarind Tree 3.80 Left

1505 6.80 Palm Tree 1.20 Left

1506 6.80 Palm Tree 1.20 Left

1507 6.80 Palm Tree 1.20 Left

1508 6.80 Palm Tree 1.20 Left

1509 6.80 Palm Tree 1.20 Left

1510 6.80 Palm Tree 1.20 Left

1511 6.80 Palm Tree 1.20 Left

1512 6.30 Tamarind Tree 2.80 Left

1513 6.20 Tamarind Tree 3.40 Left

1514 6.80 Tamarind Tree 1.40 Left

1515 6.50 Tamarind Tree 2.10 Right

1516 6.50 Palm Tree 1.30 Right

1517 6.50 Tamarind Tree 1.50 Right

1518 18/700 18/750 6.50 Vagai Tree 0.70 Left

1519 5.80 Tamarind Tree 2.20 Left

1520 5.80 Tamarind Tree 2.20 Right

1521 18/750 18/800 6.50 Vagai Tree 0.40 Left

1522 6.80 Tamarind Tree 3.30 Right

1523 18/800 18/850 6.80 Palm Tree 1.20 Left

1524 6.80 Palm Tree 1.20 Left

1525 6.80 Palm Tree 1.20 Left

1526 6.80 Palm Tree 1.20 Left

1527 6.80 Palm Tree 1.20 Left

1528 6.80 Palm Tree 1.20 Left

1529 6.80 Palm Tree 1.20 Left

1530 6.80 Palm Tree 1.20 Left

1531 6.80 Palm Tree 1.20 Left

1532 6.80 Palm Tree 1.20 Left

1533 6.80 Palm Tree 1.20 Left

75.

76.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1534 6.80 Palm Tree 1.20 Left

1535 5.80 Tamarind Tree 3.80 Left

1536 5.80 Tamarind Tree 3.30 Left

1537 6.80 Tamarind Tree 3.40 Right

1538 6.50 Tamarind Tree 2.10 Right

1539 18/850 18/900 5.90 Neem Tree 0.70 Left

1540 6.50 Palm Tree 1.20 Left

1541 6.50 Palm Tree 1.20 Left

1542 6.50 Palm Tree 1.20 Left

1543 6.50 Palm Tree 1.20 Left

1544 6.50 Palm Tree 1.20 Left

1545 6.50 Palm Tree 1.20 Left

1546 6.50 Tamarind Tree 2.40 Right

1547 6.50 Tamarind Tree 3.10 Right

1548 18/900 18/950 6.50 Palm Tree 1.20 Left

1549 6.50 Palm Tree 1.20 Left

1550 6.50 Palm Tree 1.20 Left

1551 6.50 Palm Tree 1.20 Left

1552 6.50 Palm Tree 1.20 Left

1553 6.50 Palm Tree 1.20 Left

1554 6.50 Palm Tree 1.20 Left

1555 6.50 Palm Tree 1.20 Left

1556 6.50 Palm Tree 1.20 Left

1557 6.50 Palm Tree 1.20 Left

1558 6.50 Palm Tree 1.20 Left

1559 6.50 Palm Tree 1.20 Left

1560 6.50 Tamarind Tree 2.90 Right

1561 6.50 Tamarind Tree 3.90 Right

1562 6.50 Tamarind Tree 2.40 Right

1563 18/950 19/000 6.80 Palm Tree 1.20 Left

1564 6.80 Palm Tree 1.20 Left

1565 6.80 Palm Tree 1.20 Left

1566 6.80 Palm Tree 1.20 Left

1567 6.80 Palm Tree 1.20 Left

1568 6.80 Palm Tree 1.20 Left

1569 6.80 Palm Tree 1.20 Left

1570 6.80 Palm Tree 1.20 Left

1571 6.40 Tamarind Tree 4.30 Left

1572 6.30 Tamarind Tree 4.00 Left

1573 6.30 Tamarind Tree 3.10 Left

302

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1574 6.50 Tamarind Tree 2.60 Right

1575 6.50 Tamarind Tree 2.20 Right

1576 6.50 Tamarind Tree 3.20 Right

1577 19/000 19/050 6.80 Palm Tree 1.20 Left

1578 6.80 Palm Tree 1.20 Left

1579 6.80 Palm Tree 1.20 Left

1580 6.50 Tamarind Tree 2.70 Right

1581 6.50 Tamarind Tree 3.30 Right

1582 19/050 19/100 6.40 Tamarind Tree 3.80 Left

1583 6.50 Tamarind Tree 2.70 Left

1584 6.50 Palm Tree 1.20 Left

1585 6.50 Palm Tree 1.20 Left

1586 6.50 Palm Tree 1.20 Left

1587 6.50 Palm Tree 1.20 Left

1588 6.50 Tamarind Tree 2.30 Right

1589 6.50 Tamarind Tree 1.20 Right

1590 6.50 Tamarind Tree 3.20 Right

1591 6.50 Tamarind Tree 2.60 Right

1592 19/100 19/150 6.50 Palm Tree 1.20 Left

1593 6.50 Palm Tree 1.20 Left

1594 6.50 Palm Tree 1.20 Left

1595 6.50 Palm Tree 1.20 Left

1596 6.50 Palm Tree 1.20 Left

1597 6.50 Palm Tree 1.20 Left

1598 6.50 Palm Tree 1.20 Left

1599 6.50 Palm Tree 1.20 Left

1600 6.50 Palm Tree 1.20 Left

1601 6.50 Palm Tree 1.20 Left

1602 6.50 Palm Tree 1.20 Left

1603 6.50 Palm Tree 1.20 Left

1604 6.50 Palm Tree 1.20 Left

1605 6.50 Palm Tree 1.20 Left

1606 6.00 Tamarind Tree 2.20 Left

1607 6.50 Tamarind Tree 3.20 Right

1608 6.50 Tamarind Tree 2.90 Right

1609 6.50 Tamarind Tree 3.20 Right

1610 19/150 19/200 6.00 Tamarind Tree 2.50 Left

1611 6.80 Tamarind Tree 1.80 Left

1612 6.80 Tamarind Tree 1.80 Left

1613 6.80 Palm Tree 1.80 Left

79.

80.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1614 6.80 Palm Tree 1.80 Left

1615 6.80 Palm Tree 1.80 Left

1616 6.80 Palm Tree 1.80 Left

1617 6.80 Palm Tree 1.80 Left

1618 6.80 Palm Tree 1.80 Left

1619 6.80 Palm Tree 1.80 Left

1620 6.80 Palm Tree 1.80 Left

1621 6.80 Palm Tree 1.80 Left

1622 6.80 Palm Tree 1.80 Left

1623 6.80 Palm Tree 1.80 Left

1624 6.80 Palm Tree 1.80 Left

1625 6.80 Palm Tree 1.80 Left

1626 6.80 Tamarind Tree 2.90 Left

1627 6.50 Tamarind Tree 3.10 Right

1628 6.50 Tamarind Tree 4.40 Right

1629 19/200 19/250 6.50 Tamarind Tree 2.70 Left

1630 6.00 Tamarind Tree 2.90 Left

1631 6.00 Tamarind Tree 5.20 Left

1632 6.50 Palm Tree 1.20 Left

1633 6.50 Palm Tree 1.20 Left

1634 6.50 Palm Tree 1.20 Left

1635 6.50 Palm Tree 1.20 Left

1636 6.50 Palm Tree 1.20 Left

1637 6.50 Palm Tree 1.20 Left

1638 6.50 Palm Tree 1.20 Left

1639 6.50 Palm Tree 1.20 Left

1640 6.50 Palm Tree 1.20 Left

1641 6.80 Tamarind Tree 2.60 Right

1642 6.50 Tamarind Tree 1.70 Right

1643 19/250 19/300 6.00 Tamarind Tree 3.10 Left

1644 6.00 Tamarind Tree 3.40 Left

1645 6.80 Palm Tree 1.20 Left

1646 6.80 Palm Tree 1.20 Left

1647 6.80 Palm Tree 1.20 Left

1648 6.80 Palm Tree 1.20 Left

1649 6.80 Palm Tree 1.20 Left

1650 6.80 Palm Tree 1.20 Left

1651 6.80 Palm Tree 1.20 Left

1652 6.80 Palm Tree 1.20 Left

1653 6.80 Palm Tree 1.20 Left

304

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1654 6.80 Palm Tree 1.20 Left

1655 6.80 Palm Tree 1.20 Left

1656 6.50 Tamarind Tree 2.40 Right

1657 6.50 Tamarind Tree 2.90 Right

1658 6.50 Tamarind Tree 2.80 Right

1659 19/300 19/350 6.10 Tamarind Tree 2.90 Left

1660 6.80 Palm Tree 1.20 Left

1661 6.80 Palm Tree 1.20 Left

1662 6.80 Palm Tree 1.20 Left

1663 6.80 Palm Tree 1.20 Left

1664 6.80 Palm Tree 1.20 Left

1665 6.80 Palm Tree 1.20 Left

1666 6.80 Palm Tree 1.20 Left

1667 6.80 Palm Tree 1.20 Left

1668 6.80 Palm Tree 1.20 Left

1669 6.80 Palm Tree 1.20 Left

1670 6.80 Palm Tree 1.20 Left

1671 6.80 Tamarind Tree 3.00 Right

1672 6.80 Tamarind Tree 3.20 Right

1673 6.80 Tamarind Tree 3.40 Right

1674 19/350 19/400 6.80 Palm Tree 1.20 Left

1675 6.80 Palm Tree 1.20 Left

1676 6.80 Palm Tree 1.20 Left

1677 6.80 Palm Tree 1.20 Left

1678 6.80 Palm Tree 1.20 Left

1679 6.80 Palm Tree 1.20 Left

1680 6.80 Palm Tree 1.20 Left

1681 6.80 Palm Tree 1.20 Left

1682 6.80 Palm Tree 1.20 Left

1683 6.80 Palm Tree 1.20 Left

1684 6.80 Palm Tree 1.20 Left

1685 6.80 Palm Tree 1.20 Left

1686 6.80 Palm Tree 1.20 Left

1687 6.80 Palm Tree 1.20 Left

1688 6.00 Tamarind Tree 2.80 Left

1689 6.00 Tamarind Tree 3.10 Left

1690 6.00 Tamarind Tree 2.90 Left

1691 6.80 Tamarind Tree 4.40 Right

1692 6.80 Tamarind Tree 2.60 Right

1693 19/400 19/450 6.00 Tamarind Tree 3.30 Left

83.

84.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1694 6.00 Tamarind Tree 3.10 Left

1695 6.80 Palm Tree 1.20 Left

1696 6.80 Palm Tree 1.20 Left

1697 6.80 Palm Tree 1.20 Left

1698 6.80 Palm Tree 1.20 Left

1699 6.80 Palm Tree 1.20 Left

1700 6.80 Palm Tree 1.20 Left

1701 6.80 Palm Tree 1.20 Left

1702 6.50 Tamarind Tree 3.30 Right

1703 6.50 Tamarind Tree 3.40 Right

1704 19/450 19/500 4.40 Tamarind Tree 3.40 Left

1705 6.50 Neem Tree 0.80 Left

1706 6.80 Tamarind Tree 4.00 Right

1707 19/450 19/500 4.40 Tamarind Tree 2.60 Left

1708 4.40 Tamarind Tree 2.90 Left

1709 5.50 Palm Tree 1.20 Left

1710 5.50 Palm Tree 1.20 Left

1711 5.50 Palm Tree 1.20 Left

1712 5.50 Palm Tree 1.20 Left

1713 5.50 Palm Tree 1.20 Left

1714 5.50 Palm Tree 1.20 Left

1715 5.50 Palm Tree 1.20 Left

1716 19/500 19/550 4.40 Tamarind Tree 3.20 Left

1717 4.80 Palm Tree 1.20 Left

1718 4.80 Palm Tree 1.20 Left

1719 4.80 Palm Tree 1.20 Left

1720 4.80 Palm Tree 1.20 Left

1721 4.90 Neem Tree 0.40 Left

1722 19/550 19/600 4.20 Neem Tree 1.20 Left

1723 5.50 Neem Tree 0.40 Left

1724 5.5 Neem Tree 0.40 Left

1725 5.90 Neem Tree 0.70 Left

1726 5.90 Neem Tree 0.70 Left

1727 6.00 Palm Tree 1.20 Left

1728 6.80 Neem Tree 0.40 Left

1729 6.80 Tamarind Tree 3.30 Right

1730 19/600 19/650 5.30 Neem Tree 0.40 Left

1731 5.30 Neem Tree 0.40 Left

1732 5.30 Neem Tree 0.40 Left

1733 4.40 Neem Tree 0.40 Left

306

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1734 5.70 Neem Tree 0.90 Left

1735 5.70 Neem Tree 0.90 Left

1736 5.70 Neem Tree 0.90 Left

1737 5.70 Neem Tree 1.00 Left

1738 19/600 19/650 6.00 Palm Tree 1.20 Left

1739 6.00 Palm Tree 1.20 Left

1740 6.00 Palm Tree 1.20 Left

1741 6.00 Palm Tree 1.20 Left

1742 6.00 Palm Tree 1.20 Left

1743 6.00 Palm Tree 1.20 Left

1744 6.00 Palm Tree 1.20 Left

1745 6.00 Palm Tree 1.20 Left

1746 6.00 Palm Tree 1.20 Left

1747 6.00 Palm Tree 1.20 Left

1748 6.00 Palm Tree 1.20 Left

1749 6.00 Palm Tree 1.20 Left

1750 6.00 Palm Tree 1.20 Left

1751 6.00 Neem Tree 0.30 Left

1752 6.00 Neem Tree 0.30 Left

1753 19/650 19/700 6.00 Neem Tree 0.40 Left

1754 6.00 Neem Tree 0.40 Left

1755 6.00 Neem Tree 0.40 Left

1756 6.00 Neem Tree 0.90 Left

1757 6.00 Neem Tree 0.90 Left

1758 6.00 Neem Tree 1.20 Left

1759 6.80 Palm Tree 1.20 Left

1760 6.80 Palm Tree 1.20 Left

1761 6.80 Palm Tree 1.20 Left

1762 6.80 Palm Tree 1.20 Left

1763 6.80 Palm Tree 1.20 Left

1764 6.80 Palm Tree 1.20 Left

1765 6.80 Palm Tree 1.20 Left

1766 6.80 Palm Tree 1.20 Left

1767 6.80 Palm Tree 1.20 Left

1768 6.80 Palm Tree 1.20 Left

1769 6.80 Palm Tree 1.20 Left

1770 6.80 Palm Tree 1.20 Left

1771 6.80 Palm Tree 1.20 Left

1772 19/700 19/750 5.50 Neem Tree 0.70 Left

1773 5.50 Tamarind Tree 1.20 Left

87.

88.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1774 6.80 Palm Tree 0.20 Left

1775 6.80 Palm Tree 0.20 Left

1776 6.80 Palm Tree 0.20 Left

1777 6.80 Palm Tree 0.20 Left

1778 6.80 Palm Tree 0.20 Left

1779 6.80 Palm Tree 0.20 Left

1780 6.80 Palm Tree 0.20 Left

1781 19/750 19/800 4.50 Tamarind Tree 2.90 Left

1782 4.50 Tamarind Tree 2.80 Left

1783 4.50 Palm Tree 1.20 Left

1784 4.50 Palm Tree 1.20 Left

1785 4.50 Palm Tree 1.20 Left

1786 4.50 Palm Tree 1.20 Left

1787 4.50 Palm Tree 1.20 Left

1788 6.80 Tamarind Tree 1.70 Right

1789 19/800 19/850 4.50 Neem Tree 0.40 Left

1790 4.50 Neem Tree 0.40 Left

1791 4.50 Neem Tree 0.40 Left

1792 4.50 Palm Tree 1.20 Left

1793 4.50 Palm Tree 1.20 Left

1794 4.50 Palm Tree 1.20 Left

1795 4.50 Palm Tree 1.20 Left

1796 4.50 Palm Tree 1.20 Left

1797 4.50 Palm Tree 1.20 Left

1798 6.80 Tamarind Tree 3.30 Right

1799 6.80 Tamarind Tree 3.50 Right

1800 19/800 19/850 5.00 Tamarind Tree 2.60 Left

1801 6.80 Tamarind Tree 2.20 Right

1802 19/850 19/900 5.00 Tamarind Tree 1.80 Left

1803 5.00 Tamarind Tree 4.40 Left

1804 5.00 Palm Tree 1.20 Left

1805 5.00 Palm Tree 1.20 Left

1806 5.00 Palm Tree 1.20 Left

1807 6.80 Tamarind Tree 3.60 Right

1808 19/900 19/950 5.00 Tamarind Tree 2.70 Left

1809 19/950 20/000 6.80 Palm Tree 1.20 Left

1810 6.80 Palm Tree 1.20 Left

1811 6.80 Palm Tree 1.20 Left

1812 6.00 Tamarind Tree 1.80 Left

1813 6.80 Palm Tree 1.20 Left

308

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1814 6.80 Palm Tree 1.20 Left

1815 6.80 Palm Tree 1.20 Left

1816 6.00 Tamarind Tree 3.80 Left

1817 6.50 Palm Tree 1.20 Left

1818 6.80 Palm Tree 1.20 Right

1819 6.80 Palm Tree 1.20 Right

1820 6.80 Palm Tree 1.20 Right

1821 6.80 Palm Tree 1.20 Right

1822 6.80 Tamarind Tree 1.90 Right

1823 20/000 20/050 5.90 Tamarind Tree 2.80 Left

1824 6.50 Palm Tree 1.20 Right

1825 6.50 Palm Tree 1.20 Right

1826 6.50 Palm Tree 1.20 Right

1827 6.50 Palm Tree 1.20 Right

1828 5.60 Tamarind Tree 3.70 Right

1829 5.50 Tamarind Tree 3.30 Right

1830 20/050 20/100 6.50 Palm Tree 1.20 Left

1831 6.50 Tamarind Tree 4.10 Right

1832 20/100 20/150 6.50 Palm Tree 1.20 Left

1833 6.50 Palm Tree 1.20 Left

1834 6.50 Tamarind Tree 4.00 Left

1835 6.50 Palm Tree 1.20 Right

1836 6.10 Tamarind Tree 2.80 Right

1837 20/150 20/200 6.80 Palm Tree 1.20 Left

1838 6.50 Palm Tree 1.20 Left

1839 6.50 Palm Tree 1.20 Left

1840 6.50 Palm Tree 1.20 Left

1841 6.50 Palm Tree 1.20 Right

1842 6.10 Tamarind Tree 2.20 Right

1843 6.10 Tamarind Tree 2.20 Right

1844 20/200 20/250 6.80 Tamarind Tree 3.30 Left

1845 6.50 Tamarind Tree 3.40 Left

1846 6.80 Tamarind Tree 2.80 Left

1847 20/250 20/300 6.80 Palm Tree 1.20 Left

1848 6.80 Palm Tree 1.20 Left

1849 6.80 Palm Tree 1.20 Left

1850 6.80 Palm Tree 1.20 Left

1851 6.50 Tamarind Tree 2.60 Right

1852 6.20 Tamarind Tree 2.40 Right

1853 20/300 20/350 6.50 Palm Tree 1.20 Left

91.

92.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1854 6.50 Palm Tree 1.20 Left

1855 6.50 Palm Tree 1.20 Left

1856 6.50 Palm Tree 1.20 Left

1857 5.70 Tamarind Tree 5.30 Right

1858 20/300 20/350 6.50 Palm Tree 1.20 Left

1859 5.80 Tamarind Tree 3.50 Left

1860 5.50 Tamarind Tree 3.20 Right

1861 20/350 20/400 6.50 Palm Tree 1.30 Left

1862 6.50 Palm Tree 1.30 Left

1863 6.50 Palm Tree 1.30 Left

1864 6.50 Palm Tree 1.30 Left

1865 6.50 Palm Tree 1.30 Left

1866 6.50 Palm Tree 1.30 Left

1867 6.00 Tamarind Tree 3.40 Left

1868 6.20 Palm Tree 1.40 Left

1869 5.80 Tamarind Tree 4.20 Right

1870 6.80 Palm Tree 1.10 Right

1871 6.80 Tamarind Tree 3.10 Right

1872 20/400 20/450 6.80 Palm Tree 1.20 Right

1873 6.80 Palm Tree 1.20 Right

1874 6.80 Palm Tree 1.20 Right

1875 20/400 20/450 6.50 Palm Tree 1.20 Left

1876 6.50 Palm Tree 1.20 Left

1877 6.50 Palm Tree 1.20 Left

1878 6.50 Palm Tree 1.20 Left

1879 6.50 Palm Tree 1.20 Left

1880 6.50 Palm Tree 1.20 Left

1881 6.50 Palm Tree 1.20 Left

1882 6.10 Tamarind Tree 4.30 Left

1883 5.80 Tamarind Tree 4.80 Left

1884 6.30 Tamarind Tree 4.20 Right

1885 6.50 Tamarind Tree 2.10 Right

1886 5.90 Tamarind Tree 4.10 Right

1887 20/450 20/500 5.90 Tamarind Tree 5.20 Left

1888 6.00 Tamarind Tree 4.90 Left

1889 5.90 Tamarind Tree 4.10 Right

1890 5.80 Tamarind Tree 4.30 Right

1891 20/500 20/550 6.00 Tamarind Tree 4.50 Left

1892 6.10 Tamarind Tree 3.80 Left

1893 5.70 Tamarind Tree 2.50 Right

310

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1894 6.50 Tamarind Tree 6.20 Right

1895 20/550 20/600 6.10 Tamarind Tree 3.40 Left

1896 6.50 Tamarind Tree 3.70 Right

1897 6.10 Tamarind Tree 4.70 Right

1898 20/550 20/600 6.50 Tamarind Tree 2.70 Left

1899 6.80 Tamarind Tree 4.10 Left

1900 6.80 Palm Tree 1.20 Left

1901 6.80 Palm Tree 1.20 Left

1902 6.80 Palm Tree 1.20 Left

1903 6.80 Palm Tree 1.20 Left

1904 6.80 Palm Tree 1.20 Left

1905 6.80 Tamarind Tree 4.30 Right

1906 6.20 Tamarind Tree 3.80 Right

1907 20/600 20/650 6.80 Tamarind Tree 3.20 Left

1908 6.80 Tamarind Tree 3.60 Left

1909 6.80 Tamarind Tree 3.30 Right

1910 20/650 20/700 6.80 Tamarind Tree 4.10 Left

1911 6.80 Tamarind Tree 3.80 Left

1912 6.80 Tamarind Tree 3.90 Right

1913 6.80 Tamarind Tree 3.20 Right

1914 20/700 20/750 6.20 Tamarind Tree 3.60 Left

1915 6.50 Tamarind Tree 3.60 Left

1916 6.30 Tamarind Tree 4.20 Left

1917 6.30 Tamarind Tree 4.20 Left

1918 6.50 Tamarind Tree 3.30 Right

1919 6.50 Tamarind Tree 2.20 Right

1920 20/750 20/800 6.30 Tamarind Tree 3.80 Left

1921 6.40 Tamarind Tree 4.40 Left

1922 6.50 Tamarind Tree 2.90 Left

1923 6.80 Tamarind Tree 2.40 Right

1924 6.40 Tamarind Tree 2.70 Right

1925 20/800 20/850 6.80 Tamarind Tree 4.60 Left

1926 5.40 Tamarind Tree 4.80 Left

1927 6.20 Tamarind Tree 1.80 Right

1928 6.80 Tamarind Tree 1.20 Right

1929 6.00 Tamarind Tree 2.40 Right

1930 6.00 Tamarind Tree 2.40 Right

1931 6.80 Tamarind Tree 1.20 Right

1932 6.10 Tamarind Tree 3.90 Right

1933 20/850 20/900 5.00 Tamarind Tree 6.00 Left

95.

96.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1934 5.90 Palm Tree 1.20 Left

1935 5.90 Palm Tree 1.20 Left

1936 5.90 Palm Tree 1.20 Left

1937 6.80 Tamarind Tree 2.30 Left

1938 6.80 Tamarind Tree 2.20 Left

1939 6.80 Tamarind Tree 2.20 Left

1940 6.80 Palm Tree 1.20 Right

1941 6.00 Tamarind Tree 2.20 Right

1942 20/900 20/950 6.80 Palm Tree 1.20 Left

1943 6.80 Palm Tree 1.20 Left

1944 6.80 Palm Tree 1.20 Left

1945 6.00 Neem Tree 1.10 Left

1946 6.00 Palm Tree 1.20 Left

1947 6.10 Neem Tree 1.20 Left

1948 6.10 Eacham Tree 1.20 Left

1949 6.10 Palm Tree 1.20 Left

1950 6.50 Neem Tree 0.50 Right

1951 6.80 Eacham Tree 1.10 Right

1952 6.80 Palm Tree 1.20 Right

1953 20/950 21/000 6.80 Neem Tree 0.70 Left

1954 6.80 Neem Tree 0.70 Left

1955 6.80 Neem Tree 0.40 Left

1956 6.80 Neem Tree 0.40 Left

1957 6.40 Palm Tree 1.20 Left

1958 5.50 Neem Tree 1.30 Left

1959 5.50 Neem Tree 1.30 Left

1960 6.80 Neem Tree 0.90 Left

1961 6.80 Palm Tree 1.30 Left

1962 6.20 Palm Tree 1.20 Right

1963 6.00 Tamarind Tree 1.90 Right

1964 6.80 Palm Tree 1.20 Right

1965 21/000 21/050 6.80 Palm Tree 1.20 Left

1966 6.80 Palm Tree 1.20 Left

1967 6.80 Neem Tree 1.40 Left

1968 6.80 Palm Tree 1.20 Left

1969 6.80 Palm Tree 1.20 Left

1970 6.80 Eacham Tree 0.90 Left

1971 6.80 Neem Tree 1.00 Left

1972 6.80 Neem Tree 1.00 Left

1973 6.80 Neem Tree 1.00 Left

312

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

1974 6.80 Neem Tree 1.00 Left

1975 6.80 Neem Tree 1.00 Left

1976 6.80 Palm Tree 1.00 Left

1977 6.80 Palm Tree 1.00 Left

1978 6.80 Palm Tree 1.20 Right

1979 6.80 Palm Tree 1.20 Right

1980 6.80 Tamarind Tree 4.20 Right

1981 21/050 21/100 6.50 Neem Tree 0.70 Left

1982 6.50 Tamarind Tree 3.20 Left

1983 6.50 Palm Tree 1.20 Left

1984 6.20 Tamarind Tree 3.30 Right

1985 6.20 Tamarind Tree 4.10 Right

1986 6.20 Tamarind Tree 3.30 Right

1987 21/100 21/150 6.50 Palm Tree 1.20 Left

1988 6.50 Palm Tree 1.20 Left

1989 6.50 Palm Tree 1.20 Left

1990 6.00 Tamarind Tree 2.40 Left

1991 6.50 Palm Tree 1.30 Left

1992 6.50 Palm Tree 1.20 Left

1993 6.50 Palm Tree 1.20 Right

1994 6.80 Palm Tree 0.40 Right

1995 5.90 Tamarind Tree 3.40 Right

1996 21/150 21/200 5.40 Tamarind Tree 4.60 Left

1997 5.40 Tamarind Tree 1.70 Right

1998 5.90 Tamarind Tree 3.60 Right

1999 21/200 21/250 6.80 Tamarind Tree 1.40 Left

2000 6.80 Neem Tree 1.20 Left

2001 6.80 Palm Tree 1.20 Left

2002 6.80 Tamarind Tree 1.40 Left

2003 5.60 Tamarind Tree 3.00 Right

2004 5.90 Tamarind Tree 2.00 Right

2005 6.80 Palm Tree 1.20 Right

2006 21/250 21/300 6.80 Tamarind Tree 2.90 Right

2007 6.80 Palm Tree 1.30 Right

2008 6.80 Palm Tree 1.30 Right

2009 6.80 Palm Tree 1.30 Right

2010 6.80 Palm Tree 1.30 Right

2011 6.80 Palm Tree 1.30 Right

2012 6.80 Palm Tree 1.30 Right

2013 21/300 21/350 6.50 Tamarind Tree 1.80 Left

99.

100.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2014 6.80 Palm Tree 1.30 Right

2015 6.80 Palm Tree 1.30 Right

2016 6.80 Palm Tree 1.30 Right

2017 6.80 Palm Tree 1.30 Right

2018 6.80 Palm Tree 1.30 Right

2019 6.80 Palm Tree 1.30 Right

2020 21/350 21/400 6.80 Palm Tree 1.30 Left

2021 6.80 Palm Tree 1.30 Left

2022 6.80 Neem Tree 1.20 Right

2023 6.00 Palm Tree 1.20 Right

2024 6.00 Palm Tree 1.20 Right

2025 6.00 Palm Tree 1.20 Right

2026 6.00 Palm Tree 1.20 Right

2027 21/400 21/450 6.80 Palm Tree 1.20 Left

2028 6.80 Palm Tree 1.20 Left

2029 6.80 Palm Tree 1.20 Left

2030 6.80 Palm Tree 1.20 Left

2031 6.80 Palm Tree 1.20 Left

2032 6.80 Palm Tree 1.20 Left

2033 6.80 Palm Tree 1.20 Left

2034 6.80 Palm Tree 1.20 Left

2035 6.80 Neem Tree 0.70 Left

2036 6.20 Palm Tree 1.30 Right

2037 6.20 Palm Tree 1.30 Right

2038 6.20 Palm Tree 1.30 Right

2039 6.20 Palm Tree 1.30 Right

2040 6.20 Palm Tree 1.30 Right

2041 6.20 Palm Tree 1.30 Right

2042 6.20 Palm Tree 1.30 Right

2043 6.20 Palm Tree 1.30 Right

2044 6.20 Palm Tree 1.30 Right

2045 6.20 Palm Tree 1.30 Right

2046 6.20 Palm Tree 1.30 Right

2047 6.20 Palm Tree 1.30 Right

2048 6.50 Tamarind Tree 5.20 Right

2049 21/450 21/500 6.80 Palm Tree 1.20 Left

2050 6.80 Neem Tree 0.40 Left

2051 6.30 Tamarind Tree 2.80 Right

2052 6.30 Tamarind Tree 2.00 Right

2053 21/500 21/550 6.80 Neem Tree 0.40 Left

314

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2054 6.80 Tamarind Tree 2.50 Left

2055 6.80 Tamarind Tree 2.80 Left

2056 6.50 Palm Tree 1.20 Right

2057 6.50 Palm Tree 1.20 Right

2058 6.50 Palm Tree 1.20 Right

2059 6.20 Tamarind Tree 4.80 Right

2060 6.20 Tamarind Tree 5.20 Right

2061 21/550 21/600 6.80 Neem Tree 1.20 Left

2062 6.80 Palm Tree 1.20 Left

2063 6.80 Palm Tree 1.20 Left

2064 6.80 Tamarind Tree 4.60 Right

2065 6.80 Tamarind Tree 4.60 Right

2066 21/600 21/650 6.80 Neem Tree 0.90 Left

2067 6.80 Neem Tree 0.90 Left

2068 6.80 Neem Tree 0.70 Left

2069 6.80 Neem Tree 0.70 Left

2070 21/650 21/700 6.80 Neem Tree 1.20 Left

2071 6.80 Tamarind Tree 3.20 Left

2072 6.80 Palm Tree 1.20 Left

2073 21/700 21/750 6.50 Palm Tree 1.20 Left

2074 6.80 Tamarind Tree 1.40 Left

2075 6.80 Tamarind Tree 2.00 Left

2076 6.80 Tamarind Tree 1.30 Left

2077 4.00 Palm Tree 1.20 Right

2078 6.80 Palm Tree 1.20 Right

2079 21/750 21/800 6.80 Palm Tree 1.30 Left

2080 6.80 Palm Tree 1.30 Left

2081 6.80 Palm Tree 1.30 Left

2082 6.80 Palm Tree 1.20 Right

2083 6.80 Palm Tree 1.20 Right

2084 6.80 Palm Tree 1.20 Right

2085 6.80 Neem Tree 0.90 Right

2086 21/800 21/850 6.80 Palm Tree 1.20 Left

2087 6.80 Tamarind Tree 1.40 Left

2088 21/850 21/900 6.50 Banyan Tree 5.00 Left

2089 6.50 Vangai Tree 0.70 Left

2090 6.80 Palm Tree 1.20 Right

2091 6.80 Neem Tree 0.70 Right

2092 6.80 Tamarind Tree 2.00 Right

2093 21/900 21/950 6.80 Neem Tree 1.00 Left

103.

104.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2094 21/950 22/000 6.80 Tamarind Tree 4.40 Left

2095 22/000 22/050 6.80 Neem Tree 1.00 Left

2096 6.50 Neem Tree 1.30 Right

2097 6.50 Neem Tree 1.00 Right

2098 6.50 Palm Tree 1.30 Right

2099 6.50 Neem Tree 1.10 Right

2100 22/050 22/100 6.50 Vangai Tree 2.40 Left

2101 6.50 Neem Tree 0.90 Left

2102 6.50 Neem Tree 0.70 Left

2103 6.50 Neem Tree 0.70 Left

2104 6.50 Neem Tree 1.00 Left

2105 6.50 Neem Tree 0.60 Left

2106 6.50 Neem Tree 0.60 Left

2107 6.50 Neem Tree 0.60 Left

2108 6.50 Vangai Tree 1.40 Left

2109 6.50 Neem Tree 0.90 Left

2110 22/100 22/150 6.50 Neem Tree 1.20 Left

2111 6.50 Palm Tree 1.20 Right

2112 6.50 Palm Tree 1.20 Right

2113 6.50 Palm Tree 1.20 Right

2114 6.50 Palm Tree 1.20 Right

2115 6.50 Neem Tree 1.00 Right

2116 6.50 Neem Tree 1.00 Left

2117 6.50 Neem Tree 0.90 Left

2118 6.50 Vangai Tree 2.20 Right

2119 6.50 Tamarind Tree 1.00 Right

2120 22/150 22/200 6.50 Neem Tree 0.70 Left

2121 6.50 Palm Tree 1.20 Right

2122 6.50 Palm Tree 1.20 Right

2123 6.50 Neem Tree 0.50 Left

2124 6.50 Neem Tree 1.00 Right

2125 22/200 22/250 6.50 Palm Tree 1.20 Left

2126 6.50 Palm Tree 1.20 Left

2127 6.50 Vangai Tree 1.40 Left

2128 6.50 Vangai Tree 1.00 Left

2129 6.50 Neem Tree 1.00 Left

2130 6.50 Neem Tree 0.50 Left

2131 22/250 22/300 6.50 Palm Tree 1.20 Left

2132 6.50 Tamarind Tree 2.00 Left

2133 6.40 Neem Tree 2.00 Left

316

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2134 6.50 Vangai Tree 2.50 Left

2135 6.50 Neem Tree 0.70 Left

2136 6.50 Vangai Tree 1.80 Left

2137 22/300 22/350 6.50 Neem Tree 1.00 Left

2138 6.50 Tamarind Tree 2.20 Left

2139 22/350 22/400 6.50 Palm Tree 1.20 Left

2140 6.50 Palm Tree 1.20 Left

2141 6.50 Tamarind Tree 2.80 Left

2142 6.50 Tamarind Tree 4.20 Left

2143 6.40 Neem Tree 0.40 Left

2144 6.40 Neem Tree 0.40 Left

2145 22/400 22/450 6.50 Palm Tree 1.20 Left

2146 6.50 Palm Tree 1.20 Left

2147 6.50 Palm Tree 1.20 Left

2148 6.50 Vangai Tree 1.60 Left

2149 6.50 Tamarind Tree 1.50 Left

2150 6.50 Tamarind Tree 1.70 Left

2151 6.50 Palm Tree 1.20 Left

2152 6.50 Palm Tree 1.20 Left

2153 6.50 Tamarind Tree 2.60 Left

2154 6.50 Neem Tree 4.80 Left

2155 22/450 22/500 6.50 Palm Tree 1.20 Left

2156 6.50 Palm Tree 1.20 Left

2157 6.50 Palm Tree 1.20 Left

2158 6.50 Palm Tree 1.20 Left

2159 6.50 Palm Tree 1.20 Left

2160 6.50 Tamarind Tree 2.40 Left

2161 6.50 Tamarind Tree 1.70 Left

2162 22/500 22/550 6.50 Neem Tree 1.00 Left

2163 6.50 Palm Tree 1.20 Left

2164 6.50 Palm Tree 1.20 Left

2165 6.50 Palm Tree 1.20 Left

2166 6.50 Palm Tree 1.20 Left

2167 6.50 Neem Tree 0.90 Left

2168 6.50 Palm Tree 1.20 Right

2169 6.50 Palm Tree 1.20 Right

2170 6.50 Neem Tree 1.40 Right

2171 6.50 Palm Tree 1.20 Right

2172 22/550 22/600 6.50 Neem Tree 2.80 Left

2173 6.50 Neem Tree 1.00 Left

107.

108.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2174 6.50 Naval Tree 1.30 Left

2175 6.50 Neem Tree 0.50 Left

2176 6.50 Neem Tree 1.20 Left

2177 22/600 22/650 6.50 Neem Tree 1.20 Left

2178 6.50 Neem Tree 1.20 Left

2179 6.50 Tamarind Tree 3.40 Left

2180 22/650 22/700 6.50 Tamarind Tree 2.20 Left

2181 22/700 22/750 6.50 Tamarind Tree 3.20 Left

2182 6.50 Tamarind Tree 1.10 Left

2183 22/750 22/800 6.50 Tamarind Tree 5.80 Left

2184 6.50 Tamarind Tree 2.70 Left

2185 6.50 Tamarind Tree 1.60 Left

2186 22/800 22/850 6.50 Tamarind Tree 2.90 Left

2187 6.50 Tamarind Tree 2.20 Left

2188 6.50 Tamarind Tree 2.10 Left

2189 22/850 22/900 5.50 Tamarind Tree 3.00 Left

2190 5.90 Tamarind Tree 2.40 Left

2191 22/900 22/050 5.00 Tamarind Tree 2.80 Left

2192 5.50 Tamarind Tree 3.80 Left

2193 22/950 23/000 5.70 Tamarind Tree 3.00 Right

2194 5.50 Tamarind Tree 3.70 Right

2195 23/000 23/050 5.30 Tamarind Tree 3.60 Left

2196 5.30 Tamarind Tree 4.00 Left

2197 5.30 Tamarind Tree 3.70 Left

2198 23/050 23/100 4.90 Tamarind Tree 1.60 Left

2199 5.50 Tamarind Tree 3.60 Left

2200 23/100 23/150 5.50 Tamarind Tree 5.40 Right

2201 4.40 Tamarind Tree 4.20 Left

2202 4.40 Tamarind Tree 4.70 Left

2203 23/150 23/200 4.30 Tamarind Tree 3.60 Left

2204 4.70 Tamarind Tree 1.20 Right

2205 23/200 23/250 3.50 Tamarind Tree 3.90 Left

2206 6.50 Tamarind Tree 3.20 Right

2207 23/250 23/300 2.30 Tamarind Tree 3.30 Left

2208 1.10 Tamarind Tree 3.80 Left

2209 0.90 Tamarind Tree 2.70 Left

2210 23/700 23/750 6.20 Panyan Tree 4.20 Left

2211 23/800 23/850 6.30 Name of Tree 3.70 Left

2212 23/900 23/950 3.90 Marutham Tree 4.60 Left

2213 3.70 Marutham Tree 3.90 Left

318

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2214 23/950 24/000 6.50 Nona Tree 2.40 Right

2215 24/050 24/100 5.40 Vangai Tree 2.40 Right

2216 24/100 24/150 5.00 Illuppai Tree 3.20 Left

2217 6.50 Tamarind Tree 2.20 Left

2218 24/150 24/200 6.30 Vangai Tree 2.70 Left

2219 4.20 Illuppai Tree 5.30 Left

2220 24/200 24/250 4.20 Tamarind Tree 4.90 Left

2221 6.50 Tamarind Tree 1.90 Left

2222 24/250 24/300 6.40 Neem Tree 1.30 Right

2223 24/300 24/350 4.80 Tamarind Tree 3.10 Left

2224 4.60 Tamarind Tree 3.20 Left

2225 24/350 24/400 4.80 Tamarind Tree 4.20 Left

2226 5.10 Tamarind Tree 3.10 Left

2227 24/450 24/500 5.80 Tamarind Tree 4.80 Left

2228 24/500 24/550 5.10 Tamarind Tree 2.30 Left

2229 5.30 Tamarind Tree 2.30 Left

2230 24/550 24/600 5.20 Tamarind Tree 3.80 Left

2231 4.70 Tamarind Tree 3.10 Right

2232 6.20 Tamarind Tree 2.90 Right

2233 24/600 24/650 5.50 Tamarind Tree 2.10 Left

2234 24/650 24/700 4.90 Tamarind Tree 3.10 Left

2235 4.80 Tamarind Tree 3.30 Left

2236 6.30 Tamarind Tree 2.40 Right

2237 24/700 24/750 5.20 Tamarind Tree 3.10 Left

2238 6.50 Tamarind Tree 3.70 Right

2239 24/750 24/800 4.70 Tamarind Tree 4.00 Left

2240 4.80 Tamarind Tree 4.20 Left

2241 24/800 24/850 4.60 Tamarind Tree 4.40 Left

2242 4.50 Tamarind Tree 4.90 Left

2243 24/850 24/900 5.50 Tamarind Tree 3.10 Left

2244 5.30 Tamarind Tree 4.30 Left

2245 24/900 24/950 4.40 Tamarind Tree 4.40 Left

2246 24/950 25/000 4.50 Tamarind Tree 2.80 Left

2247 25/000 25/050 6.50 Neem Tree 0.60 Left

2248 5.10 Tamarind Tree 3.90 Left

2249 25/050 25/100 4.50 Tamarind Tree 3.90 Left

2250 25/100 25/150 6.40 Tamarind Tree 3.40 Right

2251 6.20 Tamarind Tree 3.10 Right

2252 25/150 25/200 4.70 Tamarind Tree 2.80 Right

2253 6.15 Tamarind Tree 3.20 Right

111.

112.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2254 25/150 25/200 6.20 Tamarind Tree 2.90 Left

2255 25/200 25/250 6.00 Neem Tree 2.10 Left

2256 6.10 Neem Tree 1.20 Left

2257 5.90 Tamarind Tree 2.80 Left

2258 25/250 25/300 5.50 Tamarind Tree 3.50 Left

2259 6.20 Tamarind Tree 3.10 Right

2260 6.20 Tamarind Tree 3.30 Right

2261 25/300 25/350 6.30 Tamarind Tree 2.90 Right

2262 6.00 Tamarind Tree 3.20 Right

2263 25/350 25/400 5.20 Tamarind Tree 3.40 Left

2264 25/400 25/450 4.70 Tamarind Tree 3.60 Left

2265 5.40 Tamarind Tree 2.40 Left

2266 5.30 Tamarind Tree 3.30 Left

2267 5.10 Tamarind Tree 3.90 Left

2268 25/500 25/550 6.10 Karungali Tree 0.60 Left

2269 5.90 Neem Tree 3.20 Right

2270 6.20 Neem Tree 0.80 Right

2271 6.20 Neem Tree 1.30 Right

2272 6.40 Neem Tree 1.50 Right

2273 25/600 25/650 6.40 Neem Tree 1.30 Left

2274 25/700 25/750 4.90 Neem Tree 0.90 Right

2275 5.50 Neem Tree 1.20 Right

2276 6.50 Neem Tree 1.50 Right

2277 4.20 Neem Tree 1.90 Right

2278 25/750 25/800 6.10 Neem Tree 1.90 Left

2279 5.70 Neem Tree 0.30 Right

2280 25/800 25/850 6.20 Neem Tree 1.40 Left

2281 25/850 25/900 5.90 Tamarind Tree 2.40 Left

2282 6.10 Tamarind Tree 1.80 Left

2283 25/050 25/900 4.80 Neem Tree 0.70 Right

2284 25/900 25/950 6.50 Neem Tree 1.40 Left

2285 25/950 26/000 6.50 Tamarind Tree 2.20 Left

2286 26/000 26/050 6.40 Tamarind Tree 2.80 Left

2287 6.40 Tamarind Tree 3.00 Left

2288 26/050 26/100 4.90 Illuppai Tree 2.00 Right

2289 4.60 Neem Tree 1.20 Right

2290 26/100 26/150 5.60 Neem Tree 0.80 Right

2291 6.40 Neem Tree 0.10 Right

2292 26/150 26/200 6.50 Tamarind Tree 2.60 Left

2293 26/200 26/250 6.50 Tamarind Tree 3.40 Left

320

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2294 4.90 Illuppai Tree 2.00 Right

2295 4.60 Neem Tree 1.20 Right

2296 5.60 Neem Tree 0.80 Right

2297 26/250 26/300 6.40 Neem Tree 0.10 Left

2298 26/250 26/300 6.50 Neem Tree 1.30 Left

2299 26/350 26/400 5.90 Tamarind Tree 4.70 Left

2300 5.90 Vagai Tree 1.90 Left

2301 26/400 26/450 6.50 Neem Tree 1.50 Left

2302 6.50 Neem Tree 1.60 Right

2303 5.60 Neem Tree 0.80 Right

2304 26/450 26/500 5.70 Neem Tree 0.90 Right

2305 6.40 Palm Tree 1.60 Right

2306 26/500 26/550 6.00 Neem Tree 1.10 Left

2307 26/550 26/600 6.00 Tamarind Tree 2.30 Left

2308 26/600 26/650 4.10 Tamarind Tree 2.80 Left

2309 4.20 Tamarind Tree 2.10 Left

2310 6.50 Neem Tree 1.80 Left

2311 26/750 26/800 6.30 Tamarind Tree 3.00 Left

2312 26/800 26/850 6.20 Neem Tree 0.70 Right

2313 26/850 26/900 6.40 Neem Tree 0.60 Right

2314 6.30 Neem Tree 0.50 Right

2315 6.30 Neem Tree 0.90 Right

2316 6.00 Neem Tree 0.80 Right

2317 6.50 Neem Tree 0.40 Right

2318 26/900 26/950 6.40 Neem Tree 1.20 Left

2319 26/950 27/000 6.00 Illuppai Tree 5.90 Left

2320 6.00 Illuppai Tree 3.20 Left

2321 27/000 27/050 6.10 Illuppai Tree 6.20 Left

2322 6.50 Neem Tree 0.60 Left

2323 6.00 Illuppai Tree 5.50 Left

2324 6.30 Neem Tree 0.70 Left

2325 27/050 27/100 6.20 Banyan Tree 2.90 Left

2326 6.50 Neem Tree 0.40 Left

2327 6.40 Neem Tree 0.90 Left

2328 6.50 Neem Tree 0.60 Left

2329 27/100 27/150 6.10 Tamarind Tree 3.30 Right

2330 27/150 27/200 6.50 Neem Tree 1.20 Left

2331 27/200 27/250 6.10 Palm Tree 1.20 Left

2332 6.20 Vaval Tree 2.20 Left

2333 5.90 Neem Tree 0.90 Left

115.

116.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2334 27/250 27/300 6.00 Palm Tree 1.20 Left

2335 5.80 Neem Tree 1.40 Left

2336 6.20 Neem Tree 1.70 Left

2337 6.30 Neem Tree 1.20 Left

2338 27/300 27/350 4.50 Naval Tree 2.10 Right

2339 27/350 27/400 5.10 Fire Wood 1.20 Right

2340 27/350 27/400 5.10 Naval Tree 1.50 Right

2341 27/400 27/450 5.90 Neem Tree 0.90 Right

2342 6.50 Neem Tree 0.70 Right

2343 6.50 Naval Tree 1.20 Right

2344 6.50 Naval Tree 1.20 Right

2345 27/450 27/500 6.50 Neem Tree-2 0.75 Left

2346 27/500 27/550 6.50 Palm Tree 1.00 Right

2347 6.50 Neem Tree 1.20 Right

2348 27/600 27/650 5.10 Tamarind Tree 5.70 Left

2349 5.20 Tamarind Tree 5.30 Left

2350 27/650 27/700 4.50 Tamarind Tree 2.70 Left

2351 4.90 Tamarind Tree 2.40 Left

2352 27/700 27/750 5.10 Tamarind Tree 3.00 Left

2353 5.30 Tamarind Tree 4.30 Right

2354 27/750 27/800 4.80 Tamarind Tree 3.50 Left

2355 4.70 Tamarind Tree 4.00 Left

2356 27/800 27/850 4.70 Tamarind Tree 4.50 Left

2357 4.90 Tamarind Tree 3.20 Left

2358 27/850 27/900 4.80 Tamarind Tree 3.00 Left

2359 6.50 Neem Tree 1.00 Left

2360 27/900 27/950 5.70 Tamarind Tree 3.00 Right

2361 5.90 Tamarind Tree 2.25 Right

2362 4.20 Tamarind Tree 3.70 Right

2363 27/950 28/000 5.80 Tamarind Tree 4.20 Left

2364 28/000 28/050 5.80 Tamarind Tree 3.00 Left

2365 6.00 Tamarind Tree 3.00 Left

2366 4.70 Tamarind Tree 3.40 Right

2367 28/050 28/100 6.50 Fire Wood 1.60 Left

2368 5.20 Palm Tree 1.70 Right

2369 5.20 Palm Tree 1.70 Right

2370 5.10 Neem Tree 2.25 Right

2371 5.10 Neem Tree 2.25 Right

2372 6.50 Thailam Tree 1.00 Right

2373 6.50 Thailam Tree 1.00 Right

322

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2374 6.50 Thailam Tree 1.00 Right

2375 6.50 Thailam Tree 1.00 Right

2376 6.50 Thailam Tree 1.00 Right

2377 28/100 28/150 6.50 Thailam Tree 0.75 Right

2378 6.50 Thailam Tree 0.75 Right

2379 6.50 Thailam Tree 0.75 Right

2380 6.50 Thailam Tree 0.75 Right

2381 6.50 Thailam Tree 0.75 Right

2382 6.50 Thailam Tree 0.75 Right

2383 6.50 Thailam Tree 0.75 Right

2384 6.50 Thailam Tree 0.75 Right

2385 6.50 Thailam Tree 0.75 Right

2386 6.50 Thailam Tree 0.75 Right

2387 28/150 28/200 6.50 Tamarind Tree 3.00 Left

2388 28/200 28/250 6.50 Neem Tree 2.00 Left

2389 6.50 Tamarind Tree 1.50 Left

2390 6.50 Palm Tree 1.60 Left

2391 6.20 Neem Tree 1.40 Right

2392 28/250 28/300 6.50 Tamarind Tree 2.50 Left

2393 4.60 Tamarind Tree 2.00 Right

2394 4.90 Tamarind Tree 3.00 Right

2395 28/300 28/350 6.50 Tamarind Tree 2.50 Left

2396 6.50 Neem Tree 0.75 Right

2397 6.10 Tamarind Tree 1.20 Right

2398 6.20 Tamarind Tree 2.50 Right

2399 28/350 28/400 5.90 Neem Tree 0.80 Right

2400 28/400 28/450 6.50 Tamarind Tree 1.50 Left

2401 6.50 Neem Tree 0.75 Right

2402 4.90 Tamarind Tree 2.20 Right

2403 28/450 28/500 6.20 Tamarind Tree 2.20 Left

2404 6.00 Tamarind Tree 1.60 Left

2405 6.30 Tamarind Tree 2.50 Left

2406 28/500 28/550 4.80 Tamarind Tree 3.40 Right

2407 4.20 Tamarind Tree 4.00 Right

2408 28/550 28/600 6.10 Tamarind Tree 2.00 Left

2409 6.30 Tamarind Tree 3.00 Left

2410 28/600 28/650 6.50 Tamarind Tree 1.50 Left

2411 6.50 Tamarind Tree 2.10 Left

2412 28/650 28/700 6.40 Tamarind Tree 2.00 Left

2413 6.30 Tamarind Tree 3.30 Left

119.

120.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2414 6.10 Tamarind Tree 2.10 Left

2415 28/700 28/750 6.50 Tamarind Tree 1.00 Left

2416 5.70 Tamarind Tree 4.00 Right

2417 28/700 28/750 5.70 Tamarind Tree 3.00 Right

2418 28/750 28/800 4.40 Tamarind Tree 4.20 Left

2419 5.50 Tamarind Tree 2.50 Left

2420 5.70 Tamarind Tree 1.00 Left

2421 28/800 28/850 5.20 Tamarind Tree 2.60 Left

2422 5.20 Tamarind Tree 1.70 Left

2423 5.10 Tamarind Tree 2.00 Left

2424 28/850 28/900 5.20 Tamarind Tree 3.00 Left

2425 28/900 28/950 4.60 Tamarind Tree 2.20 Left

2426 4.60 Tamarind Tree 2.00 Right

2427 4.40 Tamarind Tree 2.50 Left

2428 28/950 29/000 4.90 Tamarind Tree 3.00 Right

2429 4.20 Tamarind Tree 2.00 Left

2430 4.90 Tamarind Tree 3.00 Right

2431 29/000 29/050 4.90 Tamarind Tree 2.50 Right

2432 29/000 29/050 4.40 Tamarind Tree 2.00 Left

2433 4.60 Tamarind Tree 1.60 Left

2434 4.70 Tamarind Tree 2.50 Left

2435 4.80 Tamarind Tree 1.60 Left

2436 29/050 29/100 4.60 Tamarind Tree 3.00 Left

2437 4.70 Tamarind Tree 3.00 Left

2438 5.00 Tamarind Tree 1.50 Right

2439 29/100 29/150 4.20 Tamarind Tree 1.60 Left

2440 4.10 Tamarind Tree 1.75 Left

2441 4.40 Tamarind Tree 1.20 Left

2442 29/150 29/200 4.50 Tamarind Tree 3.10 Left

2443 4.60 Tamarind Tree 2.50 Left

2444 4.70 Tamarind Tree 3.00 Left

2445 29/200 29/280 4.80 Tamarind Tree 2.00 Left

2446 4.80 Tamarind Tree 1.50 Left

2447 29/280 29/300 4.00 Tamarind Tree 3.50 Left

2448 4.20 Tamarind Tree 1.75 Left

2449 29/300 29/350 4.70 Tamarind Tree 2.80 Left

2450 29/350 29/400 4.90 Tamarind Tree 2.20 Left

2451 29/400 29/450 5.10 Tamarind Tree 2.25 Left

2452 29/450 29/500 5.80 Tamarind Tree 2.00 Left

2453 5.90 Tamarind Tree 3.00 Left

324

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2454 29/500 29/550 6.00 Tamarind Tree 1.90 Left

2455 6.20 Tamarind Tree 1.60 Left

2456 6.40 Tamarind Tree 1.20 Left

2457 29/550 29/600 4.90 Tamarind Tree 2.70 Left

2458 5.20 Tamarind Tree 3.40 Left

2459 29/600 29/650 4.70 Tamarind Tree 3.60 Left

2460 4.80 Tamarind Tree 2.80 Left

2461 29/650 29/700 4.90 Tamarind Tree 1.80 Left

2462 29/650 29/700 4.90 Tamarind Tree 2.10 Left

2463 4.90 Tamarind Tree 2.10 Left

2464 29/700 29/750 4.30 Tamarind Tree 3.50 Left

2465 5.70 Karungali Tree 4.10 Left

2466 5.10 Tamarind Tree 1.10 Left

2467 5.10 Tamarind Tree 1.10 Left

2468 4.20 Tamarind Tree 5.40 Left

2469 29/750 29/800 5.10 Tamarind Tree 3.30 Left

2470 29/800 29/850 5.20 Tamarind Tree 3.60 Left

2471 4.00 Tamarind Tree 3.90 Left

2472 29/950 30/000 5.10 Tamarind Tree 3.40 Left

2473 5.40 Tamarind Tree 3.60 Left

2474 6.40 Vagai Tree 0.40 Right

2475 6.40 Vagai Tree 0.40 Right

2476 30/000 30/050 6.20 Tamarind Tree 1.50 Left

2477 6.20 Tamarind Tree 2.10 Left

2478 30/050 30/100 5.10 Tamarind Tree 1.20 Right

2479 5.20 Tamarind Tree 4.50 Right

2480 30/100 30/150 6.50 Fire wood 4.50 Left

2481 30/250 30/300 3.80 Tamarind Tree 2.00 Left

2482 30/300 30/350 3.80 Tamarind Tree 3.10 Left

2483 30/350 30/400 6.50 Neem Tree 3.10 Left

2484 30/400 30/450 5.70 Tamarind Tree 0.90 Left

2485 5.10 Tamarind Tree 2.20 Left

2486 5.00 Tamarind Tree 3.90 Left

2487 30/500 30/550 6.50 Neem Tree 2.00 Left

2488 6.50 Neem Tree 0.60 Left

2489 30/550 30/600 6.50 Tamarind Tree 0.60 Left

2490 30/600 30/650 5.10 Tamarind Tree 1.20 Left

2491 30/650 30/700 4.30 Tamarind Tree 2.70 Left

2492 30/750 30/800 6.50 Fire wood 2.60 Left

2493 6.50 Fire wood 0.70 Left

123.

124.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2494 30/800 30/850 6.50 Fire wood 0.40 Left

2495 30/800 30/850 4.90 Tamarind Tree 2.80 Left

2496 5.10 Tamarind Tree 3.20 Left

2497 30/850 30/900 6.10 Tamarind Tree 1.70 Left

2498 30/900 30/950 4.90 Tamarind Tree 2.40 Left

2499 30/950 31/000 6.50 Fire wood 1.10 Right

2500 31/000 31/050 3.70 Tamarind Tree 3.00 Left

2501 31/050 31/100 3.90 Tamarind Tree 3.50 Left

2502 31/100 31/150 5.10 Tamarind Tree 5.30 Left

2503 4.50 Tamarind Tree 2.00 Right

2504 31/150 31/200 4.70 Tamarind Tree 2.70 Left

2505 31/200 31/250 4.90 Tamarind Tree 3.80 Right

2506 31/250 31/300 4.80 Tamarind Tree 2.80 Left

2507 4.90 Tamarind Tree 3.60 Left

2508 5.10 Tamarind Tree 3.10 Left

2509 5.20 Tamarind Tree 4.30 Left

2510 31/300 31/350 4.90 Tamarind Tree 5.90 Right

2511 5.20 Tamarind Tree 3.40 Right

2512 31/350 31/400 4.10 Tamarind Tree 6.60 Left

2513 4.10 Tamarind Tree 6.60 Left

2514 31/400 31/450 3.70 Tamarind Tree 5.90 Left

2515 3.90 Tamarind Tree 6.40 Left

2516 31/450 31/500 3.60 Tamarind Tree 3.90 Left

2517 31/500 31/550 5.50 Neem Tree 1.70 Left

2518 5.30 Tamarind Tree 4.10 Left

2519 5.10 Illuppai Tree 4.20 Left

2520 31/650 31/700 4.90 Illuppai Tree 3.70 Left

2521 31/700 31/750 3.70 Illuppai Tree 2.20 Right

2522 4.20 Illuppai Tree 2.80 Right

2523 3.60 Tamarind Tree 5.60 Right

2524 31/750 31/800 4.90 Tamarind Tree 3.90 Left

2525 4.80 Tamarind Tree 4.20 Right

2526 4.20 Tamarind Tree 5.10 Right

2527 31/800 31/850 4.40 Tamarind Tree 5.20 Left

2528 3.90 Tamarind Tree 4.80 Left

2529 31/800 31/850 4.20 Tamarind Tree 4.30 Left

2530 3.80 Tamarind Tree 3.70 Left

2531 31/850 31/900 4.20 Tamarind Tree 3.90 Left

2532 31/900 31/950 3.90 Tamarind Tree 3.20 Left

2533 4.20 Tamarind Tree 3.40 Left

326

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2534 31/950 32/000 3.60 Tamarind Tree 3.32 Left

2535 3.90 Tamarind Tree 4.20 Left

2536 3.70 Tamarind Tree 3.10 Left

2537 32/000 32/050 3.60 Tamarind Tree 4.80 Left

2538 4.90 Tamarind Tree 2.00 Left

2539 4.90 Tamarind Tree 5.20 Left

2540 32/050 32/100 3.80 Tamarind Tree 5.20 Left

2541 32/100 32/150 6.00 Vengai Tree 2.70 Left

2542 6.50 Vengai Tree 1.20 Left

2543 6.50 Vengai Tree 1.50 Left

2544 5.50 Palm Tree 1.10 Right

2545 5.70 Palm Tree 1.15 Right

2546 32/150 32/200 5.70 Vengai Tree 1.80 Right

2547 5.70 Vengai Tree 1.90 Right

2548 5.70 Palm Tree 1.10 Right

2549 32/200 32/250 5.60 Vengai Tree 2.50 Right

2550 5.70 Vengai Tree 1.60 Right

2551 6.10 Palm Tree 1.50 Right

2552 6.00 Tamarind Tree 2.00 Right

2553 6.00 Vengai Tree 1.50 Right

2554 32/250 32/300 6.50 Tamarind Tree 3.60 Left

2555 6.50 Neem Tree 1.70 Left

2556 32/450 32/500 3.60 Neem Tree 2.70 Right

2557 3.60 Neem Tree 1.60 Right

2558 32/500 32/550 3.60 Poovarasan Tree 0.30 Right

2559 3.70 Tamarind Tree 5.70 Right

2560 32/550 32/600 4.00 Tamarind Tree 3.10 Right

2561 32/600 32/650 3.70 Tamarind Tree 1.90 Right

2562 32/650 32/700 3.70 Tamarind Tree 3.70 Right

2563 32/700 32/750 3.80 Tamarind Tree 3.00 Right

2564 4.70 Tamarind Tree 2.30 Right

2565 3.90 Tamarind Tree 4.40 Right

2566 32/750 32/800 3.50 Tamarind Tree 5.10 Left

2567 3.70 Tamarind Tree 4.60 Left

2568 4.00 Tamarind Tree 4.60 Left

2569 32/800 32/850 3.70 Tamarind Tree 5.40 Left

2570 3.80 Tamarind Tree 3.10 Left

2571 32/850 32/900 3.70 Tamarind Tree 4.00 Right

2572 32/900 32/950 3.70 Tamarind Tree 4.90 Left

2573 32/950 33/000 3.90 Tamarind Tree 3.30 Left

127.

128.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2574 3.90 Tamarind Tree 3.50 Left

2575 33/000 33/050 4.00 Tamarind Tree 3.90 Left

2576 4.10 Tamarind Tree 3.80 Right

2577 33/050 33/100 3.90 Tamarind Tree 3.90 Right

2578 6.80 Neem Tree 0.30 Right

2579 6.80 Neem Tree 0.30 Right

2580 33/100 33/150 3.70 Tamarind Tree 5.60 Left

2581 4.20 Tamarind Tree 2.10 Left

2582 3.90 Tamarind Tree 4.80 Left

2583 6.10 Palm Tree 1.20 Left

2584 6.10 Palm Tree 0.90 Left

2585 6.10 Palm Tree 0.90 Left

2586 33/150 33/200 6.50 Palm Tree 1.70 Left

2587 5.90 Palm Tree 1.40 Left

2588 6.50 Palm Tree 1.30 Left

2589 6.50 Palm Tree 1.60 Left

2590 6.20 Neem Tree 0.90 Left

2591 6.20 Neem Tree 1.10 Left

2592 6.50 Palm Tree 1.20 Left

2593 6.40 Palm Tree 1.10 Left

2594 6.50 Neem Tree 1.40 Left

2595 6.40 Palm Tree 1.30 Left

2596 6.50 Palm Tree 1.40 Left

2597 33/200 33/250 6.50 Palm Tree 1.10 Left

2598 6.50 Palm Tree 1.10 Left

2599 6.50 Palm Tree 1.10 Left

2600 33/250 33/300 6.50 Palm Tree 1.20 Left

2601 33/300 33/350 6.50 Palm Tree 1.30 Left

2602 6.50 Palm Tree 0.90 Right

2603 6.50 Palm Tree 0.90 Right

2604 6.50 Palm Tree 0.90 Right

2605 6.50 Neem Tree 0.70 Right

2606 33/350 33/400 6.50 Palm Tree 1.10 Left

2607 6.50 Palm Tree 1.20 Left

2608 6.50 Neem Tree 1.10 Left

2609 33/400 33/450 6.50 Neem Tree 0.80 Left

2610 6.50 Palm Tree 0.80 Right

2611 6.50 Palm Tree 1.30 Left

2612 6.50 Palm Tree 1.30 Left

2613 6.50 Palm Tree 1.30 Left

328

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2614 6.50 Palm Tree 1.30 Left

2615 6.50 Neem Tree 0.80 Left

2616 6.50 Neem Tree 0.80 Left

2617 6.50 Palm Tree 1.20 Left

2618 6.50 Neem Tree 1.50 Right

2619 33/450 33/500 6.50 Palm Tree 1.20 Left

2620 6.50 Poovarasam Tree 1.20 Left

2621 33/500 33/550 6.50 Arasam Tree 2.40 Left

2622 33/650 33/700 6.50 Neem Tree 0.50 Right

2623 6.50 Neem Tree 0.50 Right

2624 6.50 Palm Tree 1.20 Right

2625 6.50 Palm Tree 1.20 Right

2626 6.50 Palm Tree 1.20 Right

2627 6.50 Palm Tree 1.20 Right

2628 33/700 33/750 6.50 Poovaram Tree 2.50 Right

2629 6.10 Palm Tree 1.25 Right

2630 6.10 Palm Tree 1.25 Right

2631 6.10 Palm Tree 1.25 Right

2632 6.10 Palm Tree 1.25 Right

2633 6.10 Palm Tree 1.25 Right

2634 6.10 Palm Tree 1.25 Right

2635 6.10 Palm Tree 1.25 Right

2636 6.10 Palm Tree 1.25 Right

2637 6.10 Palm Tree 1.25 Right

2638 6.10 Palm Tree 1.25 Right

2639 6.10 Palm Tree 1.25 Right

2640 6.10 Palm Tree 1.25 Right

2641 6.10 Palm Tree 1.25 Right

2642 33/750 33/800 6.50 Palm Tree 1.25 Right

2643 6.50 Palm Tree 1.25 Right

2644 6.50 Palm Tree 1.25 Right

2645 6.50 Palm Tree 1.25 Right

2646 6.50 Palm Tree 1.25 Right

2647 6.50 Palm Tree 1.25 Right

2648 6.50 Palm Tree 1.25 Right

2649 6.50 Palm Tree 1.25 Right

2650 6.50 Palm Tree 1.25 Right

2651 6.50 Palm Tree 1.25 Right

2652 6.50 Palm Tree 1.25 Right

2653 6.50 Palm Tree 1.25 Right

131.

132.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2654 6.50 Palm Tree 1.25 Right

2655 6.50 Palm Tree 1.25 Right

2656 6.50 Palm Tree 1.25 Right

2657 6.50 Palm Tree 1.25 Right

2658 6.50 Palm Tree 1.25 Right

2659 6.50 Palm Tree 1.25 Right

2660 6.50 Palm Tree 1.25 Right

2661 6.50 Palm Tree 1.25 Right

2662 6.50 Palm Tree 1.25 Right

2663 6.50 Palm Tree 1.25 Right

2664 6.50 Palm Tree 1.25 Right

2665 6.50 Palm Tree 1.25 Right

2666 6.50 Palm Tree 1.25 Right

2667 6.50 Palm Tree 1.25 Right

2668 6.50 Palm Tree 1.25 Right

2669 6.50 Palm Tree 1.25 Right

2670 6.50 Palm Tree 1.25 Right

2671 6.50 Palm Tree 1.25 Right

2672 6.50 Tamarind Tree 1.10 Right

2673 33/850 33/900 6.50 Palm Tree 1.40 Left

2674 33/900 33/950 6.50 Palm Tree 1.50 Left

2675 6.50 Palm Tree 1.50 Left

2676 6.50 Nona Tree 0.80 Left

2677 33/950 34/000 6.50 Palm Tree 1.30 Left

2678 6.50 Palm Tree 1.30 Left

2679 6.50 Palm Tree 1.10 Left

2680 34/000 34/050 6.50 Palm Tree 1.20 Left

2681 6.50 Palm Tree 1.20 Left

2682 6.50 Palm Tree 1.20 Left

2683 6.50 Palm Tree 1.20 Left

2684 6.50 Palm Tree 1.20 Left

2685 6.50 Palm Tree 1.20 Left

2686 6.50 Palm Tree 1.20 Left

2687 6.50 Palm Tree 1.20 Left

2688 6.50 Palm Tree 1.20 Left

2689 6.50 Palm Tree 1.20 Left

2690 6.50 Neem Tree 0.60 Left

2691 6.50 Neem Tree 0.60 Left

2692 6.50 Kodukkapuli Tree 1.20 Left

2693 34/050 34/100 6.50 Palm Tree 1.30 Left

330

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2694 6.50 Palm Tree 1.30 Left

2695 34/050 34/100 6.50 Tamarind Tree 3.10 Left

2696 6.50 Palm Tree 1.20 Right

2697 34/100 34/150 6.50 Palm Tree 1.20 Right

2698 6.50 Palm Tree 1.20 Right

2699 6.50 Palm Tree 1.20 Right

2700 34/150 34/200 6.50 Palm Tree 1.30 Right

2701 6.50 Tamarind Tree 2.80 Right

2702 6.50 Palm Tree 1.20 Right

2703 6.50 Palm Tree 1.20 Right

2704 6.50 Palm Tree 1.20 Right

2705 6.50 Palm Tree 1.20 Right

2706 6.50 Palm Tree 1.20 Right

2707 6.50 Palm Tree 1.20 Right

2708 6.50 Palm Tree 1.20 Right

2709 6.50 Palm Tree 1.20 Right

2710 6.50 Palm Tree 1.20 Right

2711 6.50 Palm Tree 1.20 Right

2712 6.50 Palm Tree 1.20 Right

2713 6.50 Palm Tree 1.20 Right

2714 34/200 34/250 6.50 Palm Tree 1.30 Right

2715 6.50 Palm Tree 1.30 Right

2716 6.50 Palm Tree 1.30 Right

2717 6.50 Palm Tree 1.30 Right

2718 34/400 34/450 6.50 Echam Tree 1.20 Right

2719 5.00 Palm Tree 1.40 Right

2720 5.00 Palm Tree 1.40 Right

2721 5.00 Palm Tree 1.40 Right

2722 5.00 Palm Tree 1.40 Right

2723 5.00 Palm Tree 1.40 Right

2724 34/450 34/500 5.10 Teak Tree 0.50 Right

2725 5.20 Palm Tree 1.40 Right

2726 5.20 Palm Tree 1.40 Right

2727 5.20 Palm Tree 1.40 Right

2728 34/500 34/550 4.90 Palm Tree 1.20 Right

2729 4.90 Palm Tree 1.20 Right

2730 4.90 Palm Tree 1.20 Right

2731 4.90 Palm Tree 1.20 Right

2732 5.10 Echam Tree 1.40 Right

2733 34/550 34/600 4.50 Fire wood 1.10 Left

135.

136.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2734 4.20 Tamarind Tree 2.60 Left

2735 4.30 Neem Tree 1.60 Left

2736 3.40 Neem Tree 1.60 Left

2737 34/600 34/650 6.50 Echam Tree 1.20 Left

2738 34/650 34/700 6.50 Neem Tree 1.30 Left

2739 6.50 Fire wood 1.10 Left

2740 6.50 Neem Tree 1.40 Left

2741 6.50 Neem Tree 0.60 Left

2742 6.50 Echam Tree 1.00 Left

2743 6.50 Neem Tree 0.50 Left

2744 6.50 Neem Tree 1.26 Left

2745 6.50 Palm Tree 1.00 Left

2746 6.50 Echam Tree 1.20 Left

2747 6.50 Neem Tree 0.90 Left

2748 34/650 34/700 5.20 Neem Tree 1.60 Left

2749 34/700 34/750 5.20 Palm Tree 1.70 Left

2750 5.20 Palm Tree 1.70 Left

2751 5.20 Palm Tree 1.70 Left

2752 5.20 Palm Tree 1.70 Left

2753 5.20 Palm Tree 1.70 Left

2754 5.20 Palm Tree 1.70 Left

2755 5.20 Palm Tree 1.70 Left

2756 5.20 Palm Tree 1.70 Left

2757 5.20 Palm Tree 1.70 Left

2758 5.20 Palm Tree 1.70 Left

2759 6.50 Neem Tree 1.20 Left

2760 34/750 34/800 6.50 Echam Tree 0.90 Left

2761 6.50 Neem Tree 1.50 Left

2762 35/000 35/050 6.50 Pungai Tree 1.00 Right

2763 35/050 35/100 6.50 Neem Tree 0.80 Left

2764 6.50 Palm Tree 1.30 Left

2765 6.50 Neem Tree 0.30 Left

2766 35/150 35/200 6.50 Palm Tree 1.20 Left

2767 6.50 Coconut Tree 1.40 Left

2768 6.50 Coconut Tree 1.40 Left

2769 35/200 35/250 6.50 Echam Tree 1.15 Left

2770 35/250 35/300 6.50 Palm Tree 1.30 Right

2771 6.50 Palm Tree 1.30 Right

2772 6.50 Tamarind Tree 1.30 Left

2773 35/400 34/450 6.50 Tamarind Tree 3.50 Right

332

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2774 35/850 35/900 1.10 Tamarind Tree 2.20 Right

2775 3.40 Neem Tree 3.60 Right

2776 35/900 35/950 6.80 Tamarind Tree 1.50 Right

2777 35/950 36/000 6.80 Pungai Tree 2.20 Right

2778 36/000 36/050 6.50 Pungai Tree 2.20 Right

2779 36/200 36/250 6.50 Tamarind Tree 2.00 Left

2780 6.50 Tamarind Tree 2.00 Left

2781 36/450 36/500 5.90 Tamarind Tree 4.60 Left

2782 36/500 36/550 6.50 Tamarind Tree 4.70 Left

2783 36/550 36/600 6.50 Neem Tree 1.50 Left

2784 36/550 36/600 6.50 Palm Tree 2.10 Left

2785 6.50 Palm Tree 2.10 Left

2786 36/600 36/650 6.50 Tamarind Tree 5.20 Left

2787 5.70 Tamarind Tree 2.90 Right

2788 36/700 36/750 6.50 Pungai Tree 0.70 Right

2789 36/750 36/800 6.50 Naval Tree 2.00 Left

2790 36/800 36/900 6.50 Tamarind Tree 4.20 Left

2791 36/950 37/000 6.50 Tamarind Tree 6.00 Left

2792 37/000 37/050 6.50 Neem Tree 1.10 Left

2793 6.50 Neem Tree 1.10 Left

2794 37/150 37/200 6.50 Neem Tree 1.40 Left

2795 6.50 Neem Tree 0.70 Left

2796 6.50 Palm Tree 1.30 Left

2797 37/200 37/250 6.50 Neem Tree 1.30 Right

2798 6.50 Neem Tree 1.20 Right

2799 37/200 37/250 6.50 Neem Tree 1.10 Right

2800 6.50 Neem Tree 1.50 Right

2801 6.50 Neem Tree 0.90 Right

2802 6.50 Neem Tree 2.40 Right

2803 6.50 Neem Tree 0.80 Right

2804 6.50 Neem Tree 1.20 Right

2805 6.30 Neem Tree 1.00 Right

2806 6.30 Neem Tree 1.00 Right

2807 6.30 Neem Tree 1.00 Right

2808 6.50 Neem Tree 0.70 Right

2809 6.50 Neem Tree 0.70 Right

2810 6.10 Neem Tree 2.10 Right

2811 37/250 37/300 6.40 Neem Tree 1.50 Right

2812 6.30 Neem Tree 1.30 Right

2813 6.50 Neem Tree 1.10 Right

139.

140.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2814 6.50 Neem Tree 1.70 Right

2815 6.50 Neem Tree 1.20 Right

2816 6.50 Neem Tree 1.10 Right

2817 6.50 Neem Tree 1.10 Right

2818 6.50 Neem Tree 0.90 Right

2819 6.50 Neem Tree 1.30 Right

2820 6.50 Neem Tree 0.70 Right

2821 37/300 37/350 6.50 Palm Tree 1.50 Right

2822 6.50 Palm Tree 1.50 Right

2823 6.50 Nona Tree 0.80 Right

2824 6.50 Neem Tree 0.90 Right

2825 6.50 Neem Tree 0.90 Right

2826 6.50 Pungai Tree 1.10 Right

2827 6.50 Palm Tree 1.10 Right

2828 6.50 Neem Tree 1.30 Right

2829 6.50 Neem Tree 1.30 Right

2830 37/350 37/400 6.50 Tamarind Tree 2.80 Right

2831 37/450 37/500 6.50 Fire wood 2.50 Left

2832 6.50 Echam Tree 1.10 Left

2833 6.50 Mango Tree 1.00 Left

2834 37/500 37/550 6.50 Echam Tree 1.10 Left

2835 6.50 Tamarind Tree 3.70 Left

2836 37/550 37/600 6.50 Neem Tree 2.10 Left

2837 6.50 Palm Tree 1.20 Left

2838 37/600 37/650 6.50 Palm Tree 1.10 Left

2839 6.50 Palm Tree 1.20 Left

2840 6.50 Palm Tree 1.20 Left

2841 6.50 Palm Tree 1.20 Left

2842 6.50 Palm Tree 1.30 Left

2843 6.50 Teak Tree 0.50 Left

2844 6.50 Teak Tree 0.50 Left

2845 6.50 Nona Tree 0.40 Left

2846 5.70 Banyan Tree 5.50 Left

2847 37/650 37/700 6.50 Neem Tree 1.20 Left

2848 6.50 Neem Tree 2.10 Left

2849 6.50 Palm Tree 0.80 Left

2850 37/700 37/750 5.70 Neem Tree 2.00 Left

2851 6.50 Neem Tree 1.60 Left

2852 37/700 37/750 6.50 Palm Tree 1.50 Left

2853 37/750 37/800 6.50 Palm Tree 1.20 Right

334

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2854 6.50 Banyan Tree 6.00 Right

2855 37/800 37/850 3.90 Neem Tree 4.00 Left

2856 6.50 Neem Tree 1.70 Right

2857 6.50 Palm Tree 1.50 Left

2858 37/850 37/900 6.50 Neem Tree 1.70 Right

2859 6.50 Neem Tree 2.20 Right

2860 37/900 37/950 6.50 Illuppai Tree 1.60 Right

2861 6.50 Tamarind Tree 4.00 Right

2862 38/000 38/050 6.50 Neem Tree 2.60 Left

2863 38/050 38/100 5.50 Neem Tree 1.60 Left

2864 3.10 Neem Tree 1.70 Right

2865 6.00 Palm Tree 1.20 Right

2866 6.30 Neem Tree 1.30 Right

2867 6.50 Neem Tree 0.80 Right

2868 38/150 38/200 6.50 Palm Tree 1.00 Left

2869 6.50 Palm Tree 0.90 Left

2870 6.50 Neem Tree 1.70 Left

2871 38/200 38/250 6.50 Neem Tree 1.20 Right

2872 6.50 Neem Tree 1.50 Right

2873 6.50 Neem Tree 0.90 Right

2874 38/250 38/300 6.50 Neem Tree 1.60 Left

2875 38/300 38/350 6.50 Neem Tree 0.50 Left

2876 6.50 Pungai Tree 0.30 Right

2877 6.50 Neem Tree 1.70 Right

2878 5.70 Neem Tree 1.30 Right

2879 6.50 Neem Tree 0.90 Right

2880 6.50 Neem Tree 1.30 Right

2881 6.50 Neem Tree 2.30 Left

2882 6.50 Neem Tree 1.10 Left

2883 38/350 38/000 6.50 Neem Tree 1.60 Left

2884 6.50 Neem Tree 1.60 Left

2885 6.50 Palm Tree 1.60 Right

2886 6.50 Palm Tree 1.60 Right

2887 6.50 Palm Tree 1.40 Right

2888 6.50 Palm Tree 1.40 Right

2889 6.20 Neem Tree 1.70 Right

2890 6.50 Neem Tree 1.80 Right

2891 6.10 Neem Tree 1.30 Right

2892 38/400 38/450 4.90 Neem Tree 1.80 Right

2893 4.90 Neem Tree 0.90 Right

143.

144.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2894 5.90 Neem Tree 2.80 Right

2895 6.50 Neem Tree 1.20 Right

2896 38/450 38/500 6.50 Neem Tree 2.20 Right

2897 6.50 Neem Tree 1.80 Right

2898 38/450 38/500 5.10 Neem Tree 2.80 Right

2899 6.50 Neem Tree 0.90 Right

2900 6.50 Neem Tree 1.10 Right

2901 38/500 38/550 6.50 Neem Tree 0.90 Left

2902 6.50 Neem Tree 0.40 Left

2903 6.50 Neem Tree 0.70 Left

2904 6.50 Neem Tree 1.20 Left

2905 5.90 Neem Tree 1.80 Right

2906 5.80 Neem Tree 0.60 Right

2907 6.50 Neem Tree 0.80 Right

2908 6.50 Neem Tree 1.10 Right

2909 38/550 38/600 6.50 Neem Tree 1.00 Left

2910 6.50 Neem Tree 1.40 Left

2911 6.20 Neem Tree 1.20 Right

2912 38/600 38/650 6.20 Tamarind Tree 3.90 Left

2913 6.50 Tamarind Tree 3.20 Right

2914 38/650 38/700 6.50 Neem Tree 1.50 Left

2915 6.50 Neem Tree 3.30 Left

2916 38/700 38/750 4.30 Neem Tree 1.50 Right

2917 38/750 38/800 6.50 Neem Tree 2.00 Right

2918 38/700 38/800 5.50 Neem Tree 1.90 Left

2919 5.50 Neem Tree 0.90 Left

2920 5.50 Neem Tree 1.30 Left

2921 5.50 Neem Tree 1.90 Right

2922 38/800 38/850 6.50 Neem Tree 2.40 Left

2923 6.50 Neem Tree 1.20 Left

2924 6.50 Neem Tree 1.60 Left

2925 38/850 38/900 6.50 Neem Tree 1.10 Left

2926 6.50 Neem Tree 1.50 Left

2927 6.50 Neem Tree 1.00 Left

2928 38/900 38/950 6.50 Neem Tree 2.50 Left

2929 39/050 39/100 5.50 Tamarind Tree 2.50 Right

2930 39/150 39/200 5.70 Vagai Tree 1.00 Right

2931 39/150 39/200 6.50 Neem Tree 1.20 Left

2932 39/200 39/250 6.50 Neem Tree 1.30 Left

2933 5.90 Tamarind Tree 3.50 Right

336

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2934 39/250 39/300 6.50 Neem Tree 0.90 Left

2935 6.50 Neem Tree 1.60 Right

2936 39/500 39/550 4.90 Neem Tree 1.30 Right

2937 5.30 Neem Tree 1.70 Right

2938 6.10 Neem Tree 1.70 Right

2939 5.80 Palm Tree 1.30 Right

2940 39/550 39/600 4.10 Neem Tree 0.80 Right

2941 4.20 Neem Tree 0.80 Right

2942 4.10 Neem Tree 0.85 Right

2943 39/550 39/600 4.90 Neem Tree 1.40 Right

2944 5.00 Neem Tree 0.80 Right

2945 5.10 Neem Tree 2.40 Right

2946 39/600 39/650 6.50 Neem Tree 0.70 Left

2947 6.10 Neem Tree 0.90 Right

2948 6.20 Neem Tree 1.90 Right

2949 6.10 Neem Tree 1.50 Right

2950 39/650 39/700 6.00 Neem Tree 1.00 Left

2951 6.50 Tamarind Tree 2.80 Left

2952 39/700 39/750 6.50 Tamarind Tree 2.70 Right

2953 6.50 Neem Tree 0.70 Left

2954 6.50 Neem Tree 1.30 Left

2955 39/750 39/800 6.50 Banyan Tree 2.10 Left

2956 39/800 39/850 6.50 Tamarind Tree 5.50 Left

2957 6.50 Neem Tree 0.50 Right

2958 39/850 39/900 6.50 Neem Tree 2.20 Left

2959 6.30 Neem Tree 2.30 Right

2960 4.90 Neem Tree 1.30 Right

2961 39/900 39/950 6.50 Neem Tree 2.10 Left

2962 6.50 Neem Tree 3.40 Left

2963 39/800 49/000 6.50 Neem Tree 1.10 Left

2964 6.50 Neem Tree 1.40 Left

2965 6.20 Neem Tree 1.20 Left

2966 6.10 Neem Tree 0.80 Left

2967 6.10 Neem Tree 1.20 Left

2968 6.10 Neem Tree 1.20 Left

2969 6.10 Neem Tree 1.20 Left

2970 40/000 40/050 5.30 Neem Tree 1.00 Left

2971 5.80 Neem Tree 1.30 Left

2972 5.30 Neem Tree 1.00 Left

2973 5.90 Neem Tree 0.90 Left

147.

148.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

2974 40/000 41/050 6.50 Neem Tree 1.70 Left

2975 6.50 Neem Tree 2.90 Right

2976 40/050 40/100 6.50 Neem Tree 1.00 Left

2977 6.50 Neem Tree 1.10 Left

2978 5.30 Neem Tree 1.20 Left

2979 5.20 Neem Tree 1.80 Left

2980 40/100 40/150 6.10 Neem Tree 1.20 Left

2981 5.50 Neem Tree 1.30 Left

2982 6.30 Neem Tree 1.10 Right

2983 6.50 Neem Tree 0.90 Right

2984 6.50 Neem Tree 1.10 Right

2985 6.50 Neem Tree 1.60 Right

2986 40/150 40/200 6.50 Neem Tree 0.90 Right

2987 6.50 Neem Tree 1.60 Right

2988 40/200 40/250 6.50 Tamarind Tree 5.90 Left

2989 6.50 Tamarind Tree 4.40 Left

2990 6.00 Neem Tree 1.20 Right

2991 6.00 Neem Tree 1.80 Right

2992 40/250 40/300 6.10 Neem Tree 1.40 Right

2993 6.50 Neem Tree 1.20 Right

2994 40/300 40/350 5.90 Tamarind Tree 4.90 Left

2995 6.00 Tamarind Tree 3.80 Left

2996 6.50 Tamarind Tree 4.50 Left

2997 40/350 40/400 6.50 Tamarind Tree 4.20 Left

2998 6.50 Banyan Tree 4.90 Left

2999 6.50 Tamarind Tree 4.10 Right

3000 40/400 40/450 6.50 Tamarind Tree 2.20 Left

3001 40/450 40/500 6.50 Tamarind Tree 0.90 Left

3002 7.50 Tamarind Tree 0.60 Left

3003 40/500 40/550 6.50 Tamarind Tree 3.80 Left

3004 40/550 40/600 6.10 Neem Tree 3.20 Left

3005 6.50 Palm Tree 1.40 Right

3006 6.50 Palm Tree 1.40 Right

3007 6.50 Palm Tree 1.40 Right

3008 6.50 Palm Tree 1.40 Right

3009 6.50 Neem Tree 2.20 Right

3010 6.50 Neem Tree 1.20 Right

3011 40/550 40/600 6.10 Tamarind Tree 2.70 Left

3012 6.50 Neem Tree 0.70 Right

3013 6.50 Tamarind Tree 4.30 Left

338

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3014 6.20 Palm Tree 1.20 Right

3015 6.10 Neem Tree 2.10 Right

3016 40/600 40/650 6.50 Tamarind Tree 3.90 Left

3017 40/650 40/700 6.50 Banyan Tree 7.00 Right

3018 40/700 40/750 6.50 Tamarind Tree 2.70 Right

3019 40/750 40/800 6.50 Neem Tree 0.60 Left

3020 40/800 40/850 6.50 Neem Tree 0.70 Left

3021 6.50 Neem Tree 1.20 Left

3022 6.80 Neem Tree 1.60 Left

3023 40/800 40/850 6.10 Neem Tree 1.20 Left

3024 40/850 40/900 6.50 Neem Tree 1.10 Left

3025 6.50 Neem Tree 0.60 Left

3026 6.50 Neem Tree 1.30 Left

3027 40/900 40/950 5.60 Banyan Tree 4.80 Left

3028 40/950 41/000 6.50 Neem Tree 1.20 Left

3029 6.50 Banyan Tree 3.20 Left

3030 42/000 41/050 6.50 Neem Tree 1.80 Left

3031 41/050 41/100 6.50 Neem Tree 0.60 Right

3032 41/150 41/200 5.10 Tamarind Tree 3.60 Left

3033 41/200 41/250 5.20 Tamarind Tree 4.50 Left

3034 5.70 Tamarind Tree 4.40 Left

3035 5.90 Neem Tree 2.30 Left

3036 41/250 41/300 6.00 Tamarind Tree 4.40 Left

3037 6.00 Tamarind Tree 5.00 Left

3038 41/300 41/350 6.10 Tamarind Tree 2.80 Left

3039 5.90 Tamarind Tree 3.50 Left

3040 41/350 41/400 6.50 Neem Tree 0.90 Right

3041 6.50 Neem Tree 0.40 Right

3042 6.50 Neem Tree 0.40 Right

3043 6.50 Tamarind Tree 3.80 Right

3044 41/400 41/450 6.50 Palm Tree 1.20 Left

3045 6.50 Neem Tree 1.70 Left

3046 41/500 41/550 6.20 Banyan Tree 4.50 Left

3047 41/550 41/600 5.90 Banyan Tree 7.00 Right

3048 41/600 41/650 6.50 Palm Tree 1.20 Left

3049 41/650 41/700 6.50 Neem Tree 3.10 Right

3050 41/700 41/750 6.00 Neem Tree 3.40 Left

3051 6.50 Banyan Tree 4.70 Right

3052 41/750 41/800 6.50 Banyan Tree 3.90 Right

3053 42/000 42/050 0.90 Nona Tree 0.40 Left

151.

152.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3054 0.70 Neem Tree 0.30 Left

3055 42/050 42/100 0.90 Palm Tree 1.40 Left

3056 0.90 Neem Tree 0.30 Left

3057 42/300 42/350 3.40 Mango Tree 1.20 Right

3058 3.40 Mango Tree 1.70 Right

3059 3.20 Teak Tree 0.80 Right

3060 3.10 Neem Tree 0.70 Right

3061 6.50 Coconut Tree 1.30 Right

3062 42/350 42/400 6.50 Lemon Tree 0.20 Right

3063 5.30 Pungai Tree 1.00 Right

3064 5.40 Pungai Tree 1.10 Right

3065 6.50 Lemon Tree 0.50 Right

3066 6.20 Naval Tree 1.90 Right

3067 42/750 42/800 6.20 Teak Tree 0.70 Right

3068 6.20 Teak Tree 0.70 Right

3069 6.20 Teak Tree 0.60 Right

3070 6.20 Teak Tree 0.60 Right

3071 42/800 42/850 6.50 Teak Tree 0.70 Right

3072 5.70 Coconut Tree 0.94 Right

3073 5.70 Coconut Tree 0.94 Right

3074 5.70 Coconut Tree 0.94 Right

3075 5.70 Coconut Tree 0.94 Right

3076 5.70 Coconut Tree 0.94 Right

3077 5.70 Coconut Tree 0.94 Right

3078 5.70 Coconut Tree 0.94 Right

3079 6.50 Coconut Tree 1.10 Right

3080 6.50 Teak Tree 0.20 Right

3081 5.60 Palm Tree 1.10 Right

3082 45/250 45/300 6.50 Palm Tree 1.20 Right

3083 45/300 45/350 6.50 Palm Tree 1.20 Right

3084 6.50 Neem Tree 0.20 Right

3085 45/350 45/400 6.30 Palm Tree 1.30 Right

3086 6.20 Palm Tree 1.30 Right

3087 6.40 Arasam Tree 1.10 Right

3088 45/450 45/500 6.50 Palm Tree 1.40 Right

3089 6.50 Palm Tree 1.40 Right

3090 6.50 Palm Tree 1.40 Right

3091 6.50 Nona Tree 0.90 Right

3092 45/600 45/650 5.80 Neem Tree 1.90 Left

3093 45/650 45/700 6.50 Palm Tree 1.20 Right

340

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3094 45/700 45/750 6.50 Coconut Tree 1.20 Left

3095 6.50 Coconut Tree 1.20 Left

3096 45/750 45/800 5.00 Tamarind Tree 3.00 Left

3097 5.00 Neem Tree 0.90 Left

3098 45/850 45/900 1.20 Pungai Tree 1.30 Right

3099 45/900 45/950 6.50 Tamarind Tree 4.00 Left

3100 46/000 46/050 6.50 Neem Tree 2.70 Right

3101 46/100 46/150 6.50 Tamarind Tree 4.00 Right

3102 6.50 Tamarind Tree 4.00 Right

3103 46/150 46/200 6.50 Tamarind Tree 1.40 Right

3104 6.50 Tamarind Tree 1.20 Right

3105 6.10 Tamarind Tree 3.50 Right

3106 6.50 Tamarind Tree 3.00 Right

3107 46/250 46/300 6.50 Tamarind Tree 2.25 Right

3108 6.50 Tamarind Tree 3.00 Left

3109 46/300 46/350 6.50 Neem Tree 0.90 Right

3110 46/350 46/400 5.50 Tamarind Tree 3.00 Left

3111 46/400 46/450 6.50 Neem Tree 1.10 Left

3112 46/450 46/500 6.50 Neem Tree 2.00 Right

3113 46/750 46/800 6.50 Neem Tree 0.50 Right

3114 6.50 Neem Tree 0.50 Right

3115 46/900 46/950 6.50 Palm Tree 1.10 Right

3116 47/000 47/050 6.50 Teak Tree 0.85 Left

3117 47/050 47/100 6.50 Teak Tree 0.60 Right

3118 6.50 Palm Tree 0.90 Right

3119 6.50 Neem Tree 0.20 Right

3120 47/100 47/150 6.50 Teak Tree 0.50 Left

3121 47/150 47/200 6.50 Teak Tree 0.60 Left

3122 47/200 47/250 6.50 Neem Tree 0.90 Right

3123 47/250 47/300 6.50 Neem Tree 1.10 Right

3124 6.50 Neem Tree 1.10 Right

3125 6.50 Neem Tree 1.10 Right

3126 6.50 Pungai Tree 0.65 Right

3127 6.50 Neem Tree 1.80 Right

3128 47/400 47/450 6.50 Pungai Tree 1.00 Right

3129 6.50 Pungai Tree 1.00 Right

3130 47/450 47/500 6.50 Pungai Tree 1.10 Right

3131 6.50 Pungai Tree 1.10 Right

3132 47/550 47/600 6.50 Pungai Tree 1.10 Right

3133 6.50 Palm Tree 1.30 Right

155.

156.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3134 6.50 Palm Tree 1.30 Right

3135 6.50 Palm Tree 1.30 Right

3136 6.50 Palm Tree 1.30 Right

3137 6.50 Nona Tree 0.80 Right

3138 6.50 Neem Tree 0.70 Right

3139 6.50 Banyan Tree 5.00 Right

3140 47/600 47/650 6.50 Coconut Tree 1.20 Right

3141 47/650 47/700 6.50 Pungai Tree 0.60 Right

3142 6.50 Pungai Tree 0.70 Right

3143 47/850 47/900 6.50 Coconut Tree 0.70 Left

3144 6.50 Kodukkapuli Tree 0.50 Right

3145 47/900 47/950 6.50 Coconut Tree-4 0.50 Left

3146 6.50 Neem Tree 0.50 Right

3147 6.50 Tamarind Tree Left

3148 53/800 53/820 6.5 Terminalia Tree 3 Left

3149 53/820 53/850 6.5 Tamarind Tree 1.6 Left

3150 6.5 Neem Tree 0.8 Left

3151 6.5 Terminalia Tree 4 Left

3152 6.5 Neem Tree 0.8 Left

3153 6.5 Terminalia Tree 4 Left

3154 53/800 53/900 6.5 Terminalia Tree 5.2 Left

3155 53/900 53/950 6.5 Neem Tree 0.8 Right

3156 6.5 Neem Tree 0.8 Right

3157 53/950 54/000 6 Neem Tree 0.6 Left

3158 6.1 Tamarind Tree 3.2 Left

3159 6.2 Neem Tree 0.5 Left

3160 6.2 Neem Tree 0.5 Left

3161 6.2 Tamarind Tree 3.8 Left

3162 6.3 Neem Tree 0.4 Left

3163 54/000 54/050 6.5 Neem Tree 1.5 Right

3164 54/050 54/100 6.4 Neem Tree 1 Right

3165 54/050 54/100 6.6 Tamarind Tree 3.8 Right

3166 6.2 Neem Tree 1.6 Left

3167 5.9 Neem Tree 0.6 Left

3168 54/100 54/150 6 Neem Tree 0.4 Left

3169 6 Neem Tree 0.6 Left

3170 5.9 Neem Tree 0.6 Left

3171 6 Neem Tree 1 Left

3172 6 Neem Tree 0.8 Left

3173 54/150 54/200 5.9 Neem Tree 1 Left

342

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3174 6 Tamarind Tree 4 Left

3175 6 Tamarind Tree 4.2 Left

3176 54/200 54/250 6 Tamarind Tree 3.6 Left

3177 6.2 Tamarind Tree 4.3 Left

3178 54/250 54/300 6.1 Tamarind Tree 4.2 Left

3179 4.6 Neem Tree 0.8 Left

3180 5.5 Tamarind Tree 4.2 Left

3181 5.5 Tamarind Tree 4 Left

3182 54/300 54/350 5.4 Tamarind Tree 4.2 Left

3183 6 Tamarind Tree 5.2 Right

3184 5.5 Tamarind Tree 4.5 Right

3185 54/400 54/450 5.9 Tamarind Tree 3.8 Left

3186 6 Tamarind Tree 2.8 Left

3187 6 Tamarind Tree 2.9 Left

3188 54/450 54/500 6.5 Neem Tree 0.6 Left

3189 54/500 54/550 6.5 Tamarind Tree 4 Right

3190 54/550 54/600 3.5 Neem Tree 0.8 Left

3191 3.4 Neem Tree 0.8 Left

3192 54/550 54/600 3.6 Tamarind Tree 4.1 Left

3193 54/650 54/700 6.3 Tamarind Tree 4.2 Left

3194 54/700 54/750 6.5 Neem Tree 2.5 Left

3195 5.8 Tamarind Tree 3.9 Right

3196 6 Tamarind Tree 2.5 Right

3197 54/750 54/800 6.2 Tamarind Tree 3.1 Left

3198 6.2 Tamarind Tree 3.4 Left

3199 6.2 Tamarind Tree 4.2 Left

3200 54/800 54/850 5.6 Tamarind Tree 3.2 Left

3201 5.6 Tamarind Tree 3.6 Right

3202 5.7 Tamarind Tree 4 Left

3203 54/850 54/900 5.2 Tamarind Tree 4.8 Left

3204 5 Tamarind Tree 6.6 Left

3205 5 Tamarind Tree 4 Left

3206 54/900 54/950 5.4 Tamarind Tree 2.2 Left

3207 6.2 Tamarind Tree 1.1 Left

3208 54/950 55/000 6.1 Tamarind Tree 4.8 Right

3209 6.2 Tamarind Tree 4.8 Right

3210 55/000 55/050 6.2 Tamarind Tree 3.8 Right

3211 55/050 55/100 6.2 Tamarind Tree 6.4 Left

3212 55/150 55/200 6.5 Tamarind Tree 5 Right

3213 6.3 Tamarind Tree 5 Left

159.

160.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3214 55/200 55/250 6.4 Neem Tree 1 Left

3215 6.4 Neem Tree 0.8 Left

3216 55/250 55/300 6.4 Neem Tree 1.1 Left

3217 55/300 55/318 6.3 Neem Tree 1.2 Left

3218 3.2 Neem Tree 0.8 Left

3219 55/330 55/370 2 Neem Tree 0.6 Left

3220 55/370 55/400 3.5 Tamarind Tree 4.7 Left

3221 4 Tamarind Tree 2.8 Left

3222 55/400 55/450 6.2 Tamarind Tree 3.4 Left

3223 6.2 Tamarind Tree 4.6 Left

3224 6.4 Tamarind Tree 4.2 Right

3225 55/450 55/500 6.3 Tamarind Tree 4.2 Left

3226 55/500 55/550 6 Tamarind Tree 4.6 Right

3227 55/550 55/600 6.5 Tamarind Tree 5.1 Left

3228 55/600 55/650 6.4 Tamarind Tree 5.2 Right

3229 55/700 55/750 6.2 Tamarind Tree 4.6 Right

3230 5.8 Tamarind Tree 5.4 Right

3231 55/750 55/800 6.4 Neem Tree 1 Left

3232 55/800 55/850 6.5 Palm Tree 1 Right

3233 55/800 55/850 6.2 Neem Tree 1 Left

3234 6.2 Neem Tree 0.8 Left

3235 6.2 Neem Tree 1 Left

3236 56/000 56/050 6.5 Neem Tree 1.4 Left

3237 56/100 56/150 6.3 Neem Tree 1.2 Right

3238 56/150 56/200 6.5 Neem Tree 0.8 Left

3239 56/200 56/250 6.5 Neem Tree 1 Right

3240 56/250 56/300 6.5 Tamarind Tree 5.4 Left

3241 56/300 56/350 4.8 Tamarind Tree 5.8 Right

3242 5.4 Tamarind Tree 3.6 Right

3243 56/350 56/400 6.4 Tamarind Tree 5.8 Left

3244 56/350 56/400 5.8 Tamarind Tree 3.2 Right

3245 5.8 Tamarind Tree 2.8 Right

3246 5.8 Tamarind Tree 4.8 Right

3247 6.2 Tamarind Tree 4.6 Right

3248 56/450 56/500 5.8 Tamarind Tree 4.8 Left

3249 5.8 Tamarind Tree 6.1 Left

3250 56/500 56/550 6.3 Tamarind Tree 3.4 Right

3251 6 Tamarind Tree 4 Right

3252 6.3 Tamarind Tree 2.8 Right

3253 56/550 56/600 6.5 Tamarind Tree 4 Left

344

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3254 6.5 Tamarind Tree 3.8 Left

3255 6.5 Tamarind Tree 4 Left

3256 56/600 56/650 6.2 Tamarind Tree 4.2 Left

3257 5.6 Tamarind Tree 3.6 Right

3258 56/600 56/650 6 Tamarind Tree 3.6 Left

3259 56/650 56/700 6 Tamarind Tree 4.6 Left

3260 5.8 Tamarind Tree 5.5 Left

3261 56/700 56/750 5.6 Tamarind Tree 5.1 Right

3262 5.8 Tamarind Tree 2.8 Right

3263 56/750 56/800 6 Tamarind Tree 3 Left

3264 5.8 Tamarind Tree 3.4 Left

3265 5.6 Tamarind Tree 5.5 Left

3266 56/800 56/850 5.6 Tamarind Tree 4 Left

3267 56/850 56/900 5.6 Tamarind Tree 3.8 Left

3268 5.8 Tamarind Tree 5 Left

3269 56/900 56/950 5.8 Tamarind Tree 3.4 Left

3270 5.8 Tamarind Tree 5.4 Left

3271 5.8 Tamarind Tree 3.2 Left

3272 56/950 57/000 6.2 Tamarind Tree 4 Right

3273 56/950 57/000 5.8 Tamarind Tree 4.2 Left

3274 57/100 57/050 6.5 Tamarind Tree 4.4 Left

3275 5.8 Tamarind Tree 4.2 Right

3276 57/050 57/100 5.8 Tamarind Tree 4.2 Right

3277 57/100 57/150 6.2 Tamarind Tree 1.8 Left

3278 57/150 57/200 5.4 Flower Tree 1.6 Right

3279 5.4 Neem Tree 0.8 Right

3280 5.4 Neem Tree 0.9 Right

3281 5.6 Flower Tree 0.8 Right

3282 57/200 57/250 6.2 Tamarind Tree 4.8 Left

3283 6.2 Tamarind Tree 3.2 Left

3284 6.2 Tamarind Tree 3.2 Left

3285 57/250 57/300 6.4 Tamarind Tree 2.8 Left

3286 6.4 Tamarind Tree 5.2 Left

3287 57/350 57/400 6.4 Tamarind Tree 3.6 Left

3288 57/400 57/450 6.4 Tamarind Tree 4.4 Left

3289 6.5 Tamarind Tree 3.8 Left

3290 57/450 57/500 6.5 Tamarind Tree 3.4 Left

3291 6.4 Tamarind Tree 3.3 Left

3292 57/500 57/550 5 Tamarind Tree 3.4 Left

3293 5.4 Tamarind Tree 3.8 Left

163.

164.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3294 6 Tamarind Tree 1.8 Right

3295 6 Tamarind Tree 4.6 Right

3296 5.4 Tamarind Tree 4.2 Right

3297 57/550 57/600 5.5 Tamarind Tree 3.4 Left

3298 57/600 57/650 5.5 Tamarind Tree 3.2 Left

3299 5.4 Tamarind Tree 3.2 Left

3300 57/650 57/700 5.4 Tamarind Tree 4.3 Left

3301 57/700 57/750 6.2 Tamarind Tree 4 Left

3302 57/750 57/800 5.4 Tamarind Tree 3.4 Right

3303 57/850 57/900 6 Tamarind Tree 4.6 Left

3304 57/900 57/950 4.5 Tamarind Tree 3 Left

3305 57/950 58/000 5.6 Tamarind Tree 4 Left

3306 5.8 Tamarind Tree 2.8 Left

3307 58/000 58/050 6 Tamarind Tree 3 Left

3308 5.8 Tamarind Tree 2.8 Left

3309 58/050 58/100 5.8 Tamarind Tree 1.8 Left

3310 6.2 Tamarind Tree 3 Left

3311 5.6 Tamarind Tree 2.8 Left

3312 5.8 Tamarind Tree 3.4 Left

3313 58/100 58/150 5.4 Tamarind Tree 3.8 Left

3314 5.4 Tamarind Tree 2.6 Left

3315 58/150 58/200 5.2 Tamarind Tree 3.4 Left

3316 58/150 58/200 5.4 Neem Tree 1 Left

3317 58/200 58/250 6.3 Neem Tree 0.8 Left

3318 6.3 Neem Tree 0.8 Left

3319 58/250 58/300 6.5 Tamarind Tree 3 Left

3320 6.5 Tamarind Tree 3 Left

3321 58/300 58/350 6 Tamarind Tree 4 Left

3322 4.6 Tamarind Tree 2.8 Right

3323 58/400 58/450 6.4 Neem Tree 1.2 Right

3324 58/450 58/500 6.2 Tamarind Tree 3.8 Left

3325 58/500 58/550 6 Tamarind Tree 3.8 Right

3326 58/600 58/650 6.5 Neem Tree 0.8 Left

3327 58/650 58/700 6.5 Neem Tree 0.8 Left

3328 6.5 Neem Tree 1.3 Left

3329 58/700 58/750 6.2 Tamarind Tree 3.4 Left

3330 6.5 Tamarind Tree 3.6 Left

3331 58/750 58/800 6.5 Tamarind Tree 3.4 Left

3332 6.5 Tamarind Tree 4.8 Left

3333 58/800 58/850 4.6 Tamarind Tree 5.7 Left

346

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3334 4.8 Tamarind Tree 5.4 Left

3335 58/850 58/900 5.5 Neem Tree 0.8 Left

3336 5.7 Neem Tree 0.5 Left

3337 5.8 Neem Tree 1.2 Left

3338 4.6 Tamarind Tree 5.8 Left

3339 58/900 58/950 5.8 Neem Tree 0.8 Left

3340 58/950 59/000 6 Neem Tree 0.8 Right

3341 5.6 Neem Tree 1 Right

3342 5.6 kattuva tree 1 Right

3343 5 Tamarind Tree 4.8 Right

3344 59/050 59/100 2.6 Neem Tree 1 Right

3345 2.6 Neem Tree 0.8 Right

3346 0.5 Neem Tree 3.8 Right

3347 0.5 Illuppai Tree 3.8 Right

3348 1 Neem Tree 0.8 Right

3349 2.3 Neem Tree 1 Right

3350 59/100 59/150 0.2 Neem Tree 0.6 Right

3351 0.4 Neem Tree 0.8 Right

3352 59/150 59/200 0.2 Palm Tree 1 Left

3353 0.2 kattuva tree 0.8 Right

3354 0.2 Neem Tree 0.6 Right

3355 0.1 Neem Tree 1 Right

3356 1 Neem Tree 0.9 Right

3357 0.2 Neem Tree 0.6 Right

3358 0.2 Etti Tree 0.6 Right

3359 1.2 Palm Tree 1 Right

3360 1.2 Neem Tree 0.4 Right

3361 59/200 59/250 1.8 Neem Tree 0.8 Right

3362 59/200 59/250 0.6 Tamarind Tree 1.8 Left

3363 59/250 59/300 0.4 Tamarind Tree 3.2 Left

3364 59/300 59/350 1 Naval Tree 2.8 Left

3365 59/350 59/400 0.1 Tamarind Tree 2.8 Left

3366 59/400 59/450 1.3 Tamarind Tree 3 Right

3367 59/450 59/500 3.2 Kattuva Tree 1 Right

3368 3.2 Neem Tree 0.8 Right

3369 59/500 59/530 1.2 Kattuva Tree 0.6 Right

3370 59/550 59/600 4.9 Neem Tree 1.2 Right

3371 59/650 59/700 1.3 Tamarind Tree 4.2 Right

3372 59/700 59/750 1 Palm Tree 1 Right

3373 59/950 60/000 1.8 Tamarind Tree 3.2 Right

167.

168.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3374 60/000 60/050 2.5 Neem Tree 2 Right

3375 0.2 Palm Tree 1 Right

3376 2.3 Palm Tree 1 Right

3377 2.3 Palm Tree 0.8 Right

3378 60/050 60/100 0.2 Tamarind Tree 4.8 Right

3379 60/100 60/150 0.4 Illippai Tree 3.2 Left

3380 60/150 60/200 0.4 Palm Tree 1 Left

3381 60/200 60/250 1.8 Tamarind Tree 3.2 Right

3382 60/250 60/300 2.3 Tamarind Tree 3.2 Right

3383 2.3 Tamarind Tree 3.4 Right

3384 60/300 60/350 5.8 Tamarind Tree 4.2 Right

3385 60/350 60/400 4.5 Tamarind Tree 4 Right

3386 60/400 60/450 4 Tamarind Tree 3.8 Right

3387 60/500 60/550 2.5 Tamarind Tree 4.8 Right

3388 60/550 60/600 4.6 Etti Tree 0.8 Left

3389 5.4 Neem Tree 1 Left

3390 60/600 60/650 6.5 Banyan Tree 5.4 Right

3391 60/650 60/700 6.5 Tamarind Tree 3.8 Left

3392 5.6 Tamarind Tree 4.2 Left

3393 60/700 60/750 5.4 Tamarind Tree 4.2 Left

3394 5.6 Tamarind Tree 3.4 Left

3395 60/750 60/800 5.2 Neem Tree 0.6 Right

3396 5.2 Palm Tree 0.4 Right

3397 5.2 Palm Tree 1.2 Right

3398 4.6 Palm Tree 1.2 Right

3399 5.2 Tamarind Tree 2.8 Right

3400 60/850 60/900 5.6 Tamarind Tree 3.4 Left

3401 5.5 Neem Tree 1.2 Right

3402 60/900 60/950 5.6 Neem Tree 0.6 Right

3403 5.8 Pungai Tree 0.8 Right

3404 60/950 61/000 6.5 Neem Tree 1 Left

3405 6.5 Neem Tree 1.2 Left

3406 61/000 61/050 6.2 Neem Tree 0.7 Left

3407 6.5 Neem Tree 0.7 Left

3408 6.5 Neem Tree 1.2 Left

3409 61/050 61/100 6.5 Neem Tree 0.8 Left

3410 6 Neem Tree 0.6 Right

3411 5.8 Neem Tree 0.7 Right

3412 5.8 Neem Tree 0.6 Right

3413 6 Neem Tree 0.4 Right

348

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3414 5.8 Neem Tree 0.6 Right

3415 61/100 61/120 5.6 Neem Tree 0.8 Left

3416 61/120 61/170 6.5 Palm Tree 1.2 Left

3417 5.5 Palm Tree 1.2 Left

3418 6.5 Palm Tree 1 Left

3419 6.5 Neem Tree 1.2 Right

3420 6.5 Neem Tree 0.6 Right

3421 61/170 61/200 5 Palm Tree 1 Left

3422 61/200 61/250 5.2 Palm Tree 1 Left

3423 6.2 Palm Tree 1 Left

3424 5.6 Palm Tree 1.3 Right

3425 5.5 Palm Tree 1.2 Right

3426 6.5 Neem Tree 1.5 Right

3427 61/250 61/300 6.5 Neem Tree 0.8 Left

3428 6.4 Palm Tree 1.2 Left

3429 61/300 61/330 3.8 Palm Tree 1 Left

3430 61/350 61/400 5 Tamarind Tree 4.2 Left

3431 5 Palm Tree 1.2 Left

3432 5.5 Palm Tree 1.2 Left

3433 61/400 61/450 0.6 Tamarind Tree 2.8 Left

3434 4 Batham Tree 0.9 Left

3435 61/450 61/500 6.2 Marutham Tree 4.6 Right

3436 61/500 61/550 6.2 Marutham Tree 1.4 Right

3437 5 Palm Tree 1 Right

3438 4.2 Arasam Tree 3.4 Right

3439 4.2 Palm Tree 1 Right

3440 61/550 61/600 0.2 Tamarind Tree 2.8 Left

3441 61/600 61/650 6.5 Marutham Tree 5.8 Left

3442 2 Tamarind Tree 3.4 Right

3443 61/650 61/700 6.5 Marutham Tree 3.2 Left

3444 4 Tree 3.6 Left

3445 61/700 61/750 6.5 Palm Tree 1.2 Left

3446 61/750 61/800 2.4 Marutham Tree 4 Right

3447 2.2 Palm Tree 1.4 Right

3448 3.4 Palm Tree 1 Right

3449 61/800 61/850 4.4 Marutham Tree 4.2 Right

3450 61/850 61/900 6.1 Neem Tree 0.8 Left

3451 61/900 61/950 6.2 Neem Tree 0.6 Left

3452 61/950 62/000 6.5 Neem Tree 0.8 Left

3453 6.5 Neem Tree 1 Left

171.

172.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3454 62/000 62/050 4 Echam Tree 1.2 Right

3455 6.5 Neem Tree 1.2 Right

3456 6.5 Kattuva Tree 3.2 Right

3457 6.2 Neem Tree 0.8 Right

3458 62/130 62/150 1.5 Neem Tree 1.2 Right

3459 1.6 Neem Tree 0.6 Right

3460 1 Neem Tree 0.8 Right

3461 62/150 62/200 2.5 Tamarid Tree 3.4 Right

3462 5.5 Palm Tree 1.2 Right

3463 62/200 62/250 5.5 Palm Tree 1.2 Right

3464 62/250 62/300 5.8 Palm Tree 1.2 Right

3465 5.8 Naval Tree 1 Right

3466 62/300 62/350 6 Nona Tree 1 Right

3467 4 Tamarid Tree 4 Right

3468 62/350 62/400 5.8 Neem Tree 1.2 Right

3469 62/450 62/500 6 Arasam Tree 4 Left

3470 62/500 62/550 5.8 Tamarid Tree 6.2 Left

3471 62/550 62/600 4.6 Tamarid Tree 5.6 Right

3472 62/600 62/650 5.8 Tamarid Tree 5 Left

3473 6 Pungai Tree 1.2 Left

3474 62/650 62/700 6.2 Tamarid Tree 2.5 Left

3475 62/700 62/750 6.2 Tamarid Tree 4.4 Left

3476 5.8 Tamarid Tree 6.2 Left

3477 62/750 62/800 5.4 Neem Tree 1 Right

3478 62/800 62/850 6 Illippai Tree 4.8 Left

3479 62/850 62/900 6 Illippai Tree 2.6 Left

3480 6.2 Illippai Tree 4.2 Left

3481 62/900 62/950 4.5 Tamarind Tree 3.8 Right

3482 4.5 Illippai Tree 5.2 Right

3483 4.2 Illippai Tree 4.4 Right

3484 63/000 63/050 6 Neem Tree 1.2 Right

3485 63/050 63/100 6.4 Illippai Tree 5.2 Right

3486 6.2 Illippai Tree 5.2 Right

3487 63/100 63/150 6.2 Illippai Tree 4.2 Left

3488 6.5 Tamarind Tree 3.2 Left

3489 63/200 63/250 5.6 Illippai Tree 3 Left

3490 63/250 63/300 6.2 Illippai Tree 2.8 Left

3491 63/250 63/300 6.4 Illippai Tree 3.2 Left

3492 6.4 Illippai Tree 2.8 Left

3493 63/300 63/350 6.4 Neem Tree 0.8 Left

350

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3494 6.2 Neem Tree 1 Left

3495 6.4 Neem Tree 0.8 Left

3496 6.5 Neem Tree 0.7 Left

3497 63/350 63/400 6.4 Tamarind Tree 5.2 Left

3498 63/400 63/450 4.5 Neem Tree 3.6 Left

3499 63/450 63/500 6.5 Neem Tree 1.8 Left

3500 5.6 Neem Tree 1.4 Left

3501 63/550 63/600 1.4 Illuppai Tree 4.2 Left

3502 63/650 63/700 0.6 Illuppai Tree 3 Left

3503 63/700 63/750 0.2 Neem Tree 1 Left

3504 63/700 63/750 0.4 Neem Tree 0.8 Left

3505 1.2 Neem Tree 1.2 Left

3506 0.3 Neem Tree 1 Left

3507 0.3 Neem Tree 1.2 Left

3508 63/800 63/850 1.4 Illuppai Tree 4.4 Left

3509 63/850 63/900 3.2 Illuppai Tree 3.4 Left

3510 63/950 64/000 6.4 Tamarind Tree 3.2 Left

3511 6.4 Neem Tree 2.6 Left

3512 64/000 64/050 5.2 Tamarind Tree 3.4 Right

3513 64/050 64/100 6.5 Neem Tree 1.2 Right

3514 6.3 Neem Tree 1 Right

3515 64/150 64/200 6 Neem Tree 1 Right

3516 64/150 64/200 1.5 Tamarind Tree 3.5 Right

3517 84/200 64/250 1.6 Tamarind Tree 4.2 Right

3518 64/250 64/300 5 Othiya Tree 1.2 Right

3519 2.3 Neem Tree 1 Right

3520 4.4 Neem Tree 1 Right

3521 2.4 Neem Tree 1 Right

3522 1.6 Neem Tree 0.8 Right

3523 64/300 64/350 0.2 Neem Tree 1 Right

3524 0 Tamarind Tree 4 Right

3525 0.2 Tamarind Tree 3.4 Right

3526 64/350 64/400 1 Palm Tree 1 Right

3527 64/400 64/450 1.4 Tamarind Tree 4 Right

3528 1.4 Tamarind Tree 3 Right

3529 64/450 64/500 2.6 Tamarind Tree 3.8 Right

3530 2.6 Tamarind Tree 3.9 Right

3531 64/500 64/550 2.7 Tamarind Tree 3.8 Right

3532 2.8 Tamarind Tree 4.2 Right

3533 64/550 64/600 3.7 Tamarind Tree 5.4 Right

175.

176.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3534 3.4 Tamarind Tree 5.8 Right

3535 64/600 64/650 5.2 Neem Tree 1 Right

3536 5.4 Neem Tree 0.8 Left

3537 5.6 Neem Tree 1 Left

3538 64/650 64/700 5.6 Neem Tree 1.2 Left

3539 5.6 Neem Tree 0.8 Left

3540 6 Neem Tree 1.4 Left

3541 6 Neem Tree 1 Left

3542 6.5 Neem Tree 1.2 Left

3543 64/700 64/750 6.4 Tamarind Tree 4 Left

3544 6.2 Tamarind Tree 4.7 Left

3545 64/750 64/800 5 Tamarind Tree 3.8 Left

3546 64/850 64/900 6 Tamarind Tree 4.2 Left

3547 64/900 64/950 5.8 Tamarind Tree 4.2 Left

3548 64/950 65/000 5.2 Marutham Tree 4 Left

3549 5.4 Marutham Tree 4.4 Left

3550 5.8 Marutham Tree 4.2 Left

3551 65/000 65/050 6 Marutham Tree 5.9 Left

3552 6.4 Marutham Tree 4.8 Left

3553 65/050 65/100 6.5 Marutham Tree 3.8 Left

3554 6.4 Marutham Tree 3.4 Left

3555 6.5 Marutham Tree 3.2 Left

3556 65/100 65/150 6.2 Marutham Tree 4 Left

3557 6 Marutham Tree 2.8 Left

3558 65/150 65/200 6.2 Illuppai Tree 3.5 Left

3559 65/200 65/250 6.5 Neem Tree 1.2 Left

3560 65/300 65/350 6.5 Tamarind Tree 3.5 Left

3561 65/600 65/650 5.4 Flower Tree 0.8 Left

3562 66/000 66/050 5.4 Banyan Tree 5.2 Left

3563 66/200 66/250 6.4 Tamarind Tree 3.5 Right

3564 66/250 66/300 4.8 Neem Tree 0.6 Right

3565 66/300 66/350 6 Pungai Tree 2 Right

3566 66/350 66/400 7 Pungai Tree 3 Left

3567 66/400 66/450 6.5 Tamarind Tree 3.8 Left

3568 66/550 66/600 6.5 Tamarind Tree 2.6 Left

3569 66/600 66/650 6.2 Echam Tree 1.2 Left

3570 66/650 66/700 6.5 Tamarind Tree 3.6 Left

3571 66/850 66/900 4.7 Tamarind Tree 4.8 Left

3572 66/900 66/950 4.8 Tamarind Tree 4.6 Left

3573 67/000 67/050 3.2 Pungai Tree 2.4 Right

352

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3574 67/200 67/250 6.2 Pungai Tree 2 Left

3575 67/500 67/550 6.5 Neem Tree 0.6 Left

3576 67/550 67/600 5.8 Flower Tree 1.2 Left

3577 67/600 67/650 4.8 Neem Tree 0.8 Left

3578 4.8 Tamarind Tree 2.1 Left

3579 5.4 Palm Tree-3 1.2 Left

3580 67/650 67/700 5.2 Neem Tree 0.6 Left

3581 5.6 Nona Tree 1 Left

3582 67/700 67/750 6.4 Palm Tree 1 Left

3583 67/750 67/800 6.8 Palm Tree 1 Left

3584 68/000 68/050 5.8 Tamarind Tree 3.5 Right

3585 6.2 Flower Tree 1 Right

3586 68/100 68/150 5.6 Palm Tree 1.2 Right

3587 68/300 68/350 6.4 Neem Tree 0.3 Left

3588 6.4 Pungai Tree 0.3 Right

3589 68/350 68/400 5.4 Palm Tree 1.2 Right

3590 68/450 68/500 6.2 Tamarind Tree 2.8 Right

3591 6 Palm Tree 1.2 Right

3592 68/500 68/550 6.5 Palm Tree 1 Right

3593 68/600 68/650 6.3 Kattuva Tree 0.9 Left

3594 5.3 Kattuva Tree 2 Left

3595 68/650 68/700 6.2 Kattuva Tree 0.6 Left

3596 6.2 Kattuva Tree 0.8 Left

3597 6.5 Kattuva Tree 1.2 Left

3598 68/700 68/750 6.4 Neem Tree 1.1 Right

3599 68/750 68/800 6.5 Kattuva Tree 1 Left

3600 68/800 68/850 5.8 Neem Tree 1.8 Right

3601 6 Kattuva Tree 1.2 Right

3602 5.8 Nona Tree 1.2 Right

3603 68/850 68/900 6.4 Marutham Tree 4.2 Left

3604 6.2 Naval Tree 3 Left

3605 6.5 Palm Tree 1 Left

3606 6.5 Palm Tree 1 Right

3607 5.4 Neem Tree 0.9 Right

3608 68/900 68/950 6.5 Neem Tree 1.4 Left

3609 68/950 69/00 6.5 Banyan Tree 4.6 Right

3610 69/000 69/050 5.8 Palm Tree 1.2 Left

3611 6.4 Flower Tree 1.2 Left

3612 6.1 Eacham Tree 1 Left

3613 6.1 Eacham Tree 1 Left

179.

180.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3614 69/050 69/100 4 Palm Tree 1.2 Left

3615 5.6 Neem Tree 0.8 Left

3616 5.8 Neem Tree 1.7 Left

3617 5 Palm Tree 1 Left

3618 5.2 Palm Tree 1.2 Left

3619 6 Neem Tree 1 Left

3620 6.2 Palm Tree 1 Left

3621 69/100 69/150 2.5 Flower Tree 1 Right

3622 6.3 Nona Tree 1 Right

3623 6 Pungai Tree 1.2 Right

3624 69/230 69/250 0.8 Neem Tree 0.4 Right

3625 2 Neem Tree 0.4 Right

3626 69/230 69/250 5 Kodukapuli Tree 1 Right

3627 69/250 69/270 1.5 Flower Tree 1 Right

3628 2.3 Flower Tree 1.2 Right

3629 69/270 69/300 3.2 Eacham Tree 1.2 Right

3630 3.4 Eacham Tree 1 Right

3631 69/300 69/350 3.2 Pungai Tree 1.1 Right

3632 5.8 Pungai Tree 2 Right

3633 69/350 69/400 6 Flower Tree 0.8 Right

3634 6.5 Pungai Tree 0.8 Right

3635 69/400 69/450 6.5 Flower Tree 1.1 Left

3636 69/450 69/500 6.1 Neem Tree 1.8 Left

3637 69/500 69/550 6.5 Tamarind Tree 2.2 Left

3638 6.5 Palm Tree 1 Left

3639 69/550 69/600 6.5 Neem Tree 0.2 Right

3640 69/550 69/600 5.7 Neem Tree 1.3 Left

3641 69/600 69/650 6.5 Neem Tree 1.1 Right

3642 69/650 69/700 6 Neem Tree 0.6 Left

3643 6.1 Eacham Tree 1 Left

3644 6.5 Neem Tree 1.3 Right

3645 6.5 Neem Tree 0.7 Right

3646 69/750 69/800 6.2 Tamarind Tree 3 Left

3647 6.5 Tamarind Tree 2.6 Left

3648 69/800 69/850 6.2 Pungai Tree 1.2 Left

3649 69/950 70/000 6.5 Tamarind Tree 6 Left

3650 70/000 70/050 6.5 Marutham Tree 2.8 Left

3651 6.1 Pungai Tree 1.4 Left

3652 70/050 70/100 5.8 Marutham Tree 5.4 Left

3653 70/100 70/150 6 Illuppai Tree 4.2 Left

354

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3654 70/150 70/200 5.6 Tamarind Tree 5.2 Left

3655 70/200 70/250 6.5 Tamarind Tree 3.2 Right

3656 70/250 70/300 6.5 Neem Tree 1.4 Right

3657 70/350 70/400 5.6 Neem Tree 1.2 Right

3658 70/400 70/450 6.5 Neem Tree 0.6 Left

3659 6.3 Pungai Tree 0.6 Left

3660 70/566 70/646 4.6 Neem Tree 1.2 Right

3661 6.2 Neem Tree 0.9 Right

3662 70/646 70/700 6.2 Tamarind Tree 3 Left

3663 70/700 70/750 6.5 Neem Tree 0.8 Right

3664 70/750 70/756 6.4 Neem Tree 1 Right

3665 71/200 71/250 5.8 Palm Tree 1.2 Right

3666 71/250 71/300 6.4 Tamarind Tree 3.4 Left

3667 6.2 Palm Tree 1.2 Right

3668 6.2 Palm Tree 1.2 Right

3669 71/450 71/500 5 Tamarind Tree 3.6 Left

3670 71/550 71/600 6.8 Palm Tree 1.3 Left

3671 6.5 Illuppai Tree 3.2 Left

3672 71/650 71/700 5.8 Tamarind Tree 3.8 Left

3673 71/700 71/750 5.7 Tamarind Tree 4.1 Left

3674 71/850 71/906 6.4 Tamarind Tree 3.2 Left

3675 71/906 71/950 6.4 Tamarind Tree 1.6 Left

3676 71/950 72/000 6.4 Tamarind Tree 2.4 Left

3677 6.4 Tamarind Tree 1.6 Left

3678 71/950 72/000 6.4 Tamarind Tree 1.4 Left

3679 72/050 72/100 6.5 Tamarind Tree 3 Left

3680 72/150 72/200 6 Tamarind Tree 3.8 Left

3681 72/300 72/350 6 Marutham Tree 3.8 Left

3682 5.8 Palm Tree 1 Left

3683 72/350 72/400 6.3 Illuppai Tree 4.2 Left

3684 72/450 72/500 5 Tamarind Tree 2.95 Right

3685 2.6 Tamarind Tree 1.8 Right

3686 72/500 72/530 5.2 Tamarind Tree 2.4 Right

3687 72/530 72/550 4 Tamarind Tree 1.2 Right

3688 72/530 72/550 3.8 Tamarind Tree 1.4 Right

3689 72/550 72/600 3.5 Tamarind Tree 1.4 Right

3690 3.5 Tamarind Tree 1.2 Right

3691 3.4 Palm Tree 1.2 Right

3692 3.4 Palm Tree 1.2 Right

3693 3.4 Palm Tree 1.2 Right

183.

184.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3694 5.5 Kattuva Tree 1.1 Right

3695 72/600 72/650 2.4 Tamarind Tree 1.8 Right

3696 2.4 Tamarind Tree 1.1 Right

3697 2.6 Tamarind Tree 2 Right

3698 72/650 72/700 3 Tamarind Tree 1.6 Right

3699 3.2 Tamarind Tree 1.2 Right

3700 3.2 Tamarind Tree 1.2 Right

3701 4.6 Palm Tree 1.2 Right

3702 4.6 Palm Tree 1.3 Right

3703 72/650 72/700 3.4 Tamarind Tree 0.9 Right

3704 3 Palm Tree 1.3 Right

3705 72/700 72/750 3 Tamarind Tree 1.4 Right

3706 3.2 Tamarind Tree 1.2 Right

3707 3.2 Palm Tree 1.3 Right

3708 3.6 Palm Tree 1.2 Right

3709 3.2 Tamarind Tree 1.4 Right

3710 72/750 72/800 4.5 Palm Tree 1.3 Right

3711 4.5 Palm Tree 1.3 Right

3712 6.5 Palm Tree 1 Right

3713 6.5 Palm Tree 1.2 Right

3714 4.8 Tamarind Tree 1.3 Right

3715 72/800 72/850 4.7 Palm Tree 1.2 Right

3716 4.7 Palm Tree 1.2 Right

3717 4.8 Palm Tree 1.2 Right

3718 72/800 72/850 5.4 Tamarind Tree 1.1 Right

3719 5.5 Palm Tree 1 Right

3720 5.4 Tamarind Tree 1.3 Right

3721 72/850 72/900 4.8 Tamarind Tree 1.2 Right

3722 4.6 Tamarind Tree 1.2 Right

3723 4.6 Neem Tree 0.3 Right

3724 4.8 Palm Tree 1.2 Right

3725 4.6 Palm Tree-3 1 Right

3726 4.6 Palm Tree 1.2 Right

3727 72/900 72/950 4.5 Tamarind Tree 1.1 Right

3728 4.4 Tamarind Tree 1.2 Right

3729 5.2 Palm Tree 1.4 Right

3730 6.5 Palm Tree 1.2 Right

3731 6.5 Palm Tree 1.3 Right

3732 72/950 73/000 6 Tamarind Tree 2.1 Right

3733 73/000 73/050 3.4 Tamarind Tree 2.7 Right

356

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3734 5.2 Tamarind Tree 2.4 Right

3735 3.4 Tamarind Tree 5.4 Right

3736 73/050 73/100 6 Tamarind Tree 2.3 Right

3737 6.4 Tamarind Tree 2.4 Right

3738 6.5 Tamarind Tree 2 Right

3739 6.2 Tamarind Tree 2.5 Right

3740 73/100 73/150 5.2 Marutham Tree 5.4 Right

3741 6.5 Tamarind Tree 3.2 Right

3742 73/250 73/300 6 Illuppai Tree 4.6 Right

3743 73/300 73/350 6.2 Illuppai Tree 2.8 Right

3744 6.5 Naval Tree 3.4 Right

3745 73/350 73/400 6.5 Tamarind Tree 3.4 Left

3746 73/400 73/450 6.4 Flower Tree 2.2 Right

3747 73/450 73/500 6 Illuppai Tree 3.4 Left

3748 73/500 73/550 5.4 Tamarind Tree 3.9 Left

3749 73/550 73/600 6.5 Tamarind Tree 1.4 Right

3750 73/600 73/650 6.5 Tamarind Tree 1.3 Right

3751 6.5 Tamarind Tree 1.2 Right

3752 73/650 73/700 6.5 Tamarind Tree 1 Right

3753 73/700 73/750 6.5 Palm Tree 1.2 Left

3754 6.5 Palm Tree 1.2 Left

3755 6.5 Palm Tree 1.2 Left

3756 6.2 Palm Tree 1.2 Left

3757 6.2 Palm Tree 1.2 Left

3758 6.1 Palm Tree 1.2 Left

3759 73/750 73/800 5.8 Palm Tree 1.4 Left

3760 5.4 Palm Tree 1.3 Left

3761 73/750 73/800 5.6 Palm Tree 1.2 Left

3762 6.3 Palm Tree 1.2 Left

3763 6.5 Palm Tree 1.2 Left

3764 6.3 Palm Tree 1.1 Left

3765 6.3 Palm Tree 1.1 Left

3766 6.3 Palm Tree 1.1 Left

3767 6.3 Palm Tree 1.1 Left

3768 6.3 Palm Tree 1.1 Left

3769 6.3 Palm Tree 1.1 Left

3770 6.3 Palm Tree 1.1 Left

3771 6.3 Palm Tree 1.1 Left

3772 6.3 Palm Tree 1.1 Left

3773 6.3 Palm Tree 1.1 Left

187.

188.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3774 6.3 Palm Tree 1.1 Left

3775 6.3 Palm Tree 1.1 Left

3776 6.3 Palm Tree 1.1 Left

3777 6.3 Palm Tree 1.1 Left

3778 6.3 Palm Tree 1.1 Left

3779 6.3 Palm Tree 1.1 Left

3780 6.3 Palm Tree 1.1 Left

3781 6.3 Palm Tree 1.1 Left

3782 6.3 Palm Tree 1.1 Left

3783 6.3 Palm Tree 1.1 Left

3784 6.3 Palm Tree 1.1 Left

3785 6.3 Palm Tree 1.1 Left

3786 6.3 Palm Tree 1.1 Left

3787 6.3 Palm Tree 1.1 Left

3788 6.3 Palm Tree 1.1 Left

3789 6.3 Palm Tree 1.1 Left

3790 73/800 73/850 6.4 Palm Tree 1.2 Left

3791 6.4 Palm Tree 1.2 Left

3792 6.4 Palm Tree 1.2 Left

3793 6.4 Palm Tree 1.2 Left

3794 6.4 Palm Tree 1.2 Left

3795 6.4 Palm Tree 1.2 Left

3796 6.4 Palm Tree 1.2 Left

3797 6.4 Palm Tree 1.2 Left

3798 6.4 Palm Tree 1.2 Left

3799 6.4 Palm Tree 1.2 Left

3800 6.4 Palm Tree 1.2 Left

3801 6.4 Palm Tree 1.2 Left

3802 6.4 Palm Tree 1.2 Left

3803 73/900 73/950 6.2 Palm Tree 1.2 Left

3804 6.1 Palm Tree 1.4 Left

3805 5 Palm Tree 1.2 Left

3806 4.2 Palm Tree 1.3 Left

3807 6.5 Tamarind Tree 1.2 Left

3808 73/950 74/000 6.2 Palm Tree 1.4 Left

3809 5.8 Palm Tree 1.1 Left

3810 73/950 74/000 5.8 Palm Tree 1.4 Left

3811 5.6 Palm Tree 1.3 Left

3812 6.5 Palm Tree 1 Left

3813 6.5 Palm Tree 1.2 Left

358

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3814 6.5 Palm Tree 1.2 Left

3815 74/000 74/050 6.5 Palm Tree 1.2 Left

3816 6.5 Palm Tree 1.2 Left

3817 74/050 74/100 6.5 Tamarind Tree 1.2 Left

3818 6.5 Tamarind Tree 0.9 Left

3819 74/100 74/120 6.5 Tamarind Tree 1.3 Left

3820 1.9 Tamarind Tree 1 Left

3821 74/120 74/150 1.7 Tamarind Tree 1.2 Left

3822 1.3 Tamarind Tree 1.2 Left

3823 1.2 Tamarind Tree 1 Left

3824 74/150 74/170 1 Tamarind Tree 1 Left

3825 74/150 74/170 2.6 Eacham Tree 1 Left

3826 3.5 Tamarind Tree 1.2 Left

3827 74/170 74/200 3.8 Tamarind Tree 1.1 Left

3828 6.5 Marutham Tree 2.2 Left

3829 74/200 74/220 2.3 Tamarind Tree 3.8 Right

3830 74/220 74/250 4.3 Palm Tree 1.2 Right

3831 4.4 Palm Tree 1.2 Right

3832 4.4 Tamarind Tree 1.6 Right

3833 4.4 Palm Tree 1.2 Right

3834 4.5 Palm Tree 1.3 Right

3835 4.5 Palm Tree 1.3 Right

3836 4.5 Palm Tree 1.3 Right

3837 74/250 74/300 4 Tamarind Tree 2.2 Right

3838 5.5 Palm Tree 1.2 Right

3839 5.5 Palm Tree 1.2 Right

3840 5.5 Palm Tree 1.2 Right

3841 0.8 Neem Tree 1 Right

3842 5.2 Neem Tree 1.1 Right

3843 6.2 Palm Tree 1.3 Right

3844 74/250 74/300 1.8 Neem Tree 0.8 Right

3845 74/300 74/350 1.8 Tamarind Tree 2 Right

3846 3 Tamarind Tree 1.8 Right

3847 3.2 Tamarind Tree 1 Right

3848 1.4 Neem Tree 1 Right

3849 74/350 74/400 3 Tamarind Tree 1.2 Right

3850 3.2 Tamarind Tree 1 Right

3851 3.1 Tamarind Tree 1.4 Right

3852 3.5 Tamarind Tree 3.4 Right

3853 74/400 74/450 4.4 Neem Tree 0.8 Right

191.

192.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3854 4.4 Neem Tree 1 Right

3855 6.4 Neem Tree 1.3 Right

3856 74/450 74/500 6.3 Tamarind Tree 3.2 Left

3857 74/550 74/600 6.5 Tamarind Tree 4.2 Right

3858 74/800 74/850 6.5 Tamarind Tree 3 Right

3859 75/050 75/100 5.7 Tamarind Tree 3.5 Right

3860 5 Banyan Tree 3.4 Right

3861 75/100 75/150 6.5 Tamarind Tree 3.5 Right

3862 75/200 75/250 6.4 Tamarind Tree 3.6 Left

3863 75/350 75/400 6.2 Tamarind Tree 5 Left

3864 75/400 75/450 6.5 Tamarind Tree 5.1 Left

3865 75/500 75/550 6.5 Tamarind Tree 4.1 Left

3866 75/700 75/750 5.4 Palm Tree 0.8 Left

3867 5.4 Palm Tree 0.9 Left

3868 5.6 Naval Tree 2.2 Left

3869 6.5 Tamarind Tree 1.7 Left

3870 75/750 75/800 5.6 Illuppai Tree 2.8 Left

3871 75/800 75/850 4.5 Naval Tree 4.2 Left

3872 75/800 75/850 6.5 Tamarind Tree 1.6 Left

3873 75/850 75/870 5.3 Tamarind Tree 1.8 Left

3874 75/870 75/915 4.8 Neem Tree 1 Left

3875 4.8 Neem Tree 0.9 Left

3876 5 Neem Tree 0.8 Left

3877 2 Tamarind Tree 1.2 Left

3878 5.3 Tamarind Tree 4.5 Left

3879 6 Banyan Tree 6.2 Left

3880 75/915 75/950 6.5 Tamarind Tree 2.8 Left

3881 75/950 76/000 6.5 Tamarind Tree 1.4 Left

3882 5.6 Tamarind Tree 1.4 Left

3883 76/000 76/050 5 Kottuva Tree 2 Left

3884 76/050 76/100 6.5 Pungai Tree 1.9 Right

3885 76/100 76/150 4.2 Banyan Tree 6.4 Right

3886 76/250 76/300 5.7 Banyan Tree 5.4 Right

3887 76/300 76/350 6.5 Banyan Tree 3.4 Left

3888 4.2 Banyan Tree 5.2 Right

3889 76/500 76/550 3.6 Tamarind Tree 6.2 Left

3890 76/750 76/800 3.5 Naval Tree 1 Right

3891 76/800 76/850 6.5 Illuppai Tree 1 Right

3892 3.2 Kattuva Tree 1.1 Right

3893 76/800 76/850 6 Illuppai Tree 4.6 Right

360

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3894 5.8 Illuppai Tree 1.5 Right

3895 2.3 Kattuva Tree 0.8 Right

3896 2.5 Kattuva Tree 0.9 Right

3897 2.8 Kattuva Tree 0.6 Right

3898 2.5 Kattuva Tree 0.6 Right

3899 76/850 76/900 6.4 Illuppai Tree 1.2 Right

3900 6.2 Illuppai Tree 1.8 Right

3901 6.2 Illuppai Tree 2.3 Right

3902 6.5 Illuppai Tree 1.6 Right

3903 76/900 76/950 3.2 Pungai Tree 1.3 Right

3904 6.5 Tamarind Tree 1.4 Right

3905 76/950 77/000 5.8 Kodukkapuli Tree 1 Right

3906 77/000 77/050 6.5 Illuppai Tree 5.1 Right

3907 7.5 Illuppai Tree 6.1 Right

3908 77/050 77/100 6.5 Kodukkapuli Tree 3 Left

3909 77/100 77/150 4.8 Illuppai Tree 2.1 Left

3910 6.3 Neem Tree 0.8 Left

3911 77/150 77/200 6.4 Neem Tree 1 Left

3912 77/200 77/250 5.6 Illuppai Tree 1.2 Left

3913 77/250 77/300 4.8 Illuppai Tree 2.1 Left

3914 77/300 77/350 6.5 Neem Tree 0.8 Right

3915 77/400 77/450 6 Tamarind Tree 3.7 Right

3916 77/450 77/500 6.5 Tamarind Tree 3.4 Right

3917 77/500 77/550 6.5 Neem Tree 1.2 Left

3918 77/550 77/600 4.9 Murungai Tree 1.2 Right

3919 77/600 77/650 5.8 Palm Tree 1 Right

3920 5.7 Neem Tree 1 Right

3921 6 Neem Tree 1.6 Right

3922 77/650 77/700 6.2 Neem Tree 1 Left

3923 6.2 Neem Tree 0.8 Left

3924 6.5 Neem Tree 1.1 Left

3925 6.2 Neem Tree 1.1 Left

3926 6.5 Neem Tree 0.9 Left

3927 77/700 77/750 6.1 Neem Tree 3.1 Right

3928 77/750 77/800 6 Tamarind Tree 3.6 Left

3929 5.8 Tamarind Tree 3.8 Left

3930 77/800 77/850 5.2 Tamarind Tree 4 Left

3931 77/900 77/950 5.6 Tamarind Tree 2.5 Left

3932 78/000 78/050 6 Tamarind Tree 4.1 Left

3933 6 Tamarind Tree 1.4 Right

195.

196.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3934 5.7 Neem Tree 1 Right

3935 78/100 78/130 3.5 Palm Tree 1.4 Right

3936 3.5 Palm Tree 1.4 Right

3937 3.5 Palm Tree 1.4 Right

3938 3.5 Palm Tree 1.4 Right

3939 3.5 Palm Tree 1.4 Right

3940 78/130 78/180 3.8 Palm Tree 1.4 Right

3941 3.8 Tamarind Tree 2.8 Right

3942 6.5 Palm Tree 1.2 Right

3943 6.5 Palm Tree 1.2 Right

3944 6.5 Palm Tree 1.2 Right

3945 78/180 78/170 6 Tamarind Tree 2.2 Left

3946 78/170 78/200 5.8 Tamarind Tree 1.8 Left

3947 5.6 Tamarind Tree 1.9 Left

3948 78/200 78/250 0.8 Tamarind Tree 1.3 Right

3949 2.5 Tamarind Tree 4.1 Right

3950 1.2 Tamarind Tree 2.2 Right

3951 1.3 Tamarind Tree 1.4 Right

3952 5 Tamarind Tree 3 Right

3953 78/250 78/300 5.1 Tamarind Tree 1.1 Right

3954 5 Tamarind Tree 2.9 Right

3955 5.5 Tamarind Tree 2.4 Right

3956 5.6 Tamarind Tree 1.6 Right

3957 5.5 Tamarind Tree 1.8 Right

3958 78/300 78/350 5.5 Tamarind Tree 2.1 Right

3959 5.8 Tamarind Tree 1.2 Right

3960 6 Tamarind Tree 1.8 Right

3961 78/300 78/350 2.5 Tamarind Tree 2.2 Right

3962 2.5 Tamarind Tree 1.2 Right

3963 78/350 78/400 6 Tamarind Tree 3.2 Left

3964 2.2 Tamarind Tree 1.4 Right

3965 2 Tamarind Tree 2.8 Right

3966 78/400 78/420 6 Tamarind Tree 1.1 Left

3967 78/420 78/450 6.5 Tamarind Tree 5.2 Left

3968 78/500 78/550 5.8 Neem Tree 1.3 Left

3969 78/550 78/600 6 Neem Tree 1.3 Left

3970 78/650 78/700 5.8 Tamarind Tree 4.8 Left

3971 78/700 78/750 5.5 Tamarind Tree 4.6 Left

3972 79/350 79/390 4.5 Tamarind Tree 2 Left

3973 83/050 83/100 5.6 Palm Tree 1 Left

362

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

3974 5.5 Palm Tree 0.8 Left

3975 83/100 83/150 5.2 Arasam Tree 5.8 Left

3976 5.4 Palm Tree 0.8 Left

3977 83/150 83/200 5.8 Neem Tree 0.8 Left

3978 5.6 Nona Tree 0.6 Left

3979 83/200 83/250 5.3 Neem Tree 0.6 Left

3980 6.3 Neem Tree 1 Left

3981 83/250 83/300 6.2 Tamarind Tree 2.2 Left

3982 6.1 Tamarind Tree 2 Left

3983 83/300 83/350 6.3 Tamarind Tree 2.4 Left

3984 6.2 Tamarind Tree 1.9 Left

3985 6.2 Tamarind Tree 3.2 Left

3986 83/300 83/350 6.5 Tamarind Tree 2.4 Left

3987 83/350 83/400 6.5 Tamarind Tree 2.6 Left

3988 6.5 Tamarind Tree 2.6 Left

3989 83/400 83/450 6.5 Tamarind Tree 2.6 Left

3990 6.5 Tamarind Tree 2.8 Left

3991 6.5 Tamarind Tree 2.8 Left

3992 6.5 Tamarind Tree 2.6 Left

3993 83/450 83/500 6.3 Tamarind Tree 2.6 Right

3994 4.3 Neem Tree 0.8 Right

3995 4.3 Neem Tree 1 Right

3996 83/500 83/550 6.5 Tamarind Tree 2.5 Left

3997 6.5 Tamarind Tree 2.3 Left

3998 6.5 Tamarind Tree 3 Left

3999 6.5 Tamarind Tree 3.3 Left

4000 83/550 83/600 6.3 Tamarind Tree 3.2 Right

4001 83/550 83/600 6.8 Tamarind Tree 3.6 Right

4002 5.8 Tamarind Tree 2.8 Right

4003 83/600 83/650 5 Tamarind Tree 2.65 Right

4004 5.1 Tamarind Tree 2.7 Right

4005 5.4 Tamarind Tree 1.6 Right

4006 5.4 Tamarind Tree 1.9 Right

4007 6.2 Tamarind Tree 2.3 Left

4008 83/650 83/700 6.4 Tamarind Tree 3.2 Left

4009 5 Tamarind Tree 2.7 Left

4010 83/750 83/800 4.4 Tamarind Tree 2.7 Left

4011 4.4 Tamarind Tree 2.6 Left

4012 4.4 Tamarind Tree 3.4 Left

4013 4.2 Tamarind Tree 4 Left

199.

200.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4014 4.2 Tamarind Tree 2.8 Left

4015 83/800 83/850 5.2 Tamarind Tree 3 Left

4016 83/850 83/900 6.3 Tamarind Tree 3 Left

4017 6 Tamarind Tree 3.1 Left

4018 6.2 Tamarind Tree 2.9 Left

4019 83/900 83/950 6.5 Tamarind Tree 2.8 Right

4020 83/950 94/000 6.5 Tamarind Tree 2.9 Left

4021 84/050 84/100 6 Tamarind Tree 2.8 Right

4022 84/100 84/150 6 Tamarind Tree 3.2 Right

4023 5.8 Tamarind Tree 3.2 Right

4024 84/150 84/200 6 Tamarind Tree 2.9 Right

4025 6 Tamarind Tree 2.4 Right

4026 84/200 84/250 6.5 Eacham Tree 1 Left

4027 84/250 84/300 6.5 Tamarind Tree 4.2 Right

4028 84/350 84/400 6.2 Tamarind Tree 3.4 Left

4029 84/400 84/450 5.8 Tamarind Tree 3 Left

4030 5.6 Tamarind Tree 2.6 Left

4031 84/500 84/550 6.2 Tamarind Tree 4.8 Left

4032 84/550 84/600 3.5 Naval Tree 3.4 Left

4033 84/600 84/650 6.5 Tamarind Tree 3 Left

4034 5.6 Tamarind Tree 5.9 Left

4035 6 Tamarind Tree 2.8 Left

4036 5.6 Marutham Tree 3.2 Left

4037 84/650 84/700 5.2 Marutham Tree 1.9 Left

4038 5.1 Marutham Tree 2.6 Left

4039 5.8 Marutham Tree 3.4 Left

4040 5.6 Marutham Tree 2.6 Left

4041 84/700 84/750 6 Marutham Tree 3 Right

4042 84/700 84/750 5.4 Marutham Tree 2.3 Left

4043 5.3 Marutham Tree 3.4 Left

4044 5.5 Marutham Tree 3.2 Left

4045 5.2 Marutham Tree 2.6 Right

4046 84/750 84/800 5 Marutham Tree 3.6 Left

4047 5.4 Marutham Tree 2.4 Left

4048 5.4 Marutham Tree 1.8 Right

4049 84/800 84/850 5.2 Marutham Tree 3.6 Left

4050 5.4 Marutham Tree 3 Right

4051 5.8 Tamarind Tree 3.8 Right

4052 84/850 84/900 6.5 Tamarind Tree 4.2 Left

4053 6.5 Tamarind Tree 1.6 Left

364

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4054 84/900 84/950 6 Neem Tree 1.2 Right

4055 4.5 Etti Tree 1.4 Right

4056 84/950 85/000 5.8 Palm Tree 1.2 Right

4057 5.8 Palm Tree 1.2 Right

4058 84/950 85/000 6.5 Tamarind Tree 3.4 Right

4059 6 Palm Tree 1.2 Right

4060 85/000 85/050 5.5 Palm Tree 1.1 Left

4061 5.6 Palm Tree 1.2 Left

4062 6.5 Tamarind Tree 3.5 Left

4063 85/050 85/100 5.8 Tamarind Tree 2.6 Left

4064 85/100 85/150 5.8 Tamarind Tree 3.1 Right

4065 85/150 85/200 6.5 Tamarind Tree 2.8 Right

4066 6.5 Tamarind Tree 2.6 Right

4067 6.5 Tamarind Tree 3.2 Left

4068 85/200 85/250 6.5 Tamarind Tree 3.1 Left

4069 6.2 Tamarind Tree 2.8 Right

4070 85/350 85/380 6.4 Tamarind Tree 2.9 Right

4071 85/400 85/450 2 Tamarind Tree 3.2 Right

4072 2.2 Tamarind Tree 2.6 Right

4073 85/450 85/500 1 Tamarind Tree 3 Right

4074 2.5 Tamarind Tree 3.4 Right

4075 85/500 85/550 5.8 Tamarind Tree 3.6 Left

4076 85/700 85/750 6.5 Tamarind Tree 2.8 Left

4077 6.5 Tamarind Tree 3.8 Left

4078 85/750 85/800 6.5 Tamarind Tree 3.2 Left

4079 6.5 Tamarind Tree 2.9 Left

4080 85/800 85/850 6.5 Tamarind Tree 2.8 Right

4081 6.5 Tamarind Tree 2.4 Right

4082 85/800 85/850 6.5 Tamarind Tree 2.8 Right

4083 6 Tamarind Tree 3.2 Right

4084 6.3 Tamarind Tree 2.6 Right

4085 85/850 85/900 6.1 Tamarind Tree 1.6 Right

4086 6 Tamarind Tree 1.8 Right

4087 85/900 85/950 6.5 Tamarind Tree 2.6 Right

4088 6.5 Tamarind Tree 2.4 Right

4089 86/250 86/300 5.2 Tamarind Tree 3.2 Left

4090 5.2 Tamarind Tree 3.3 Left

4091 86/250 86/300 6.5 Tamarind Tree 2.6 Right

4092 86/600 86/650 5.6 Tamarind Tree 2.3 Left

4093 86/650 86/700 5.4 Tamarind Tree 3 Left

203.

204.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4094 86/700 86/750 5.7 Tamarind Tree 4.2 Left

4095 5.8 Tamarind Tree 3 Left

4096 5.8 Tamarind Tree 3 Left

4097 86/750 86/800 4.5 Tamarind Tree 3.4 Left

4098 6 Tamarind Tree 2.6 Right

4099 86/800 86/850 6.5 Tamarind Tree 4 Left

4100 86/900 86/950 4 Palm Tree 1.2 Left

4101 3.7 Tamarind Tree 4.3 Left

4102 5.7 Palm Tree 1 Left

4103 6.2 Palm Tree 1 Left

4104 86/950 87/000 3.5 Tamarind Tree 2.7 Left

4105 87/000 87/050 3.6 Tamarind Tree 2.5 Left

4106 5.3 Tamarind Tree 3.4 Left

4107 87/050 87/100 4.7 Tamarind Tree 3.7 Left

4108 4.6 Tamarind Tree 3.6 Left

4109 4.4 Tamarind Tree 2.4 Left

4110 5.2 Tamarind Tree 3.1 Left

4111 87/100 87/150 5.6 Tamarind Tree 4 Left

4112 5.6 Tamarind Tree 3.4 Left

4113 5.6 Tamarind Tree 3.4 Left

4114 87/150 87/200 5.8 Tamarind Tree 3.1 Left

4115 6 Tamarind Tree 1 Left

4116 87/250 87/300 4.4 Tamarind Tree 3.1 Left

4117 87/350 87/400 6.4 Tamarind Tree 3 Left

4118 87/450 87/500 5.6 Tamarind Tree 3.1 Left

4119 5.4 Tamarind Tree 2.9 Left

4120 5.3 Tamarind Tree 4.7 Left

4121 87/500 87/550 5 Tamarind Tree 2.2 Left

4122 5 Tamarind Tree 3.8 Left

4123 4.8 Tamarind Tree 2.4 Left

4124 87/550 87/600 5 Tamarind Tree 3.2 Left

4125 5.2 Tamarind Tree 2.4 Left

4126 87/600 87/650 5.4 Illuppai Tree 4.1 Left

4127 87/750 87/800 2.7 Tamarind Tree 5.1 Right

4128 3 Palm Tree 1.2 Right

4129 87/800 87/850 4.5 Tamarind Tree 3.9 Right

4130 87/850 87/900 6.5 Tamarind Tree 3.4 Left

4131 88/000 88/050 5.6 Pungai Tree 0.7 Right

4132 88/050 88/100 6.5 Tamarind Tree 3.3 Left

4133 6.5 Tamarind Tree 3.8 Left

366

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4134 6 Tamarind Tree 3 Left

4135 6.5 Tamarind Tree 1.2 Left

4136 88/100 88/150 6.2 Tamarind Tree 2 Left

4137 88/100 88/150 6.2 Tamarind Tree 3.8 Left

4138 88/200 88/250 4.7 Tamarind Tree 3.2 Left

4139 5 Tamarind Tree 3 Left

4140 88/250 88/300 5 Tamarind Tree 2.8 Left

4141 5.4 Tamarind Tree 2.2 Left

4142 5.6 Tamarind Tree 3.4 Left

4143 6.5 Tamarind Tree 4 Left

4144 6.5 Tamarind Tree 2.4 Left

4145 88/350 88/400 5.5 Kondai Tree 1.2 Left

4146 88/400 88/450 5.9 Tamarind Tree 3.2 Left

4147 6.5 Kattuva Tree 3.2 Right

4148 6.5 Kattuva Tree 2.8 Right

4149 88/400 88/500 5.6 Tamarind Tree 3.3 Left

4150 88/500 88/550 6.2 Tamarind Tree 2.6 Left

4151 6.2 Tamarind Tree 3.8 Left

4152 88/550 88/600 5.6 Tamarind Tree 3.6 Left

4153 5.6 Tamarind Tree 3.2 Left

4154 5.4 Tamarind Tree 2.8 Left

4155 5.8 Tamarind Tree 2.9 Left

4156 88/600 88/650 5.1 Tamarind Tree 6 Left

4157 5.4 Tamarind Tree 3.6 Left

4158 5.4 Tamarind Tree 2.9 Left

4159 88/650 88/700 6.5 Tamarind Tree 3.4 Right

4160 88/750 88/800 6.5 Tamarind Tree 3.7 Left

4161 4.8 Tamarind Tree 3.3 Right

4162 88/800 88/850 5.7 Tamarind Tree 3.2 Left

4163 4.3 Tamarind Tree 3.1 Right

4164 88/850 88/900 5.4 Tamarind Tree 4.1 Left

4165 5.6 Tamarind Tree 4.6 Left

4166 5.4 Tamarind Tree 4 Left

4167 88/900 88/950 5.6 Tamarind Tree 5.1 Left

4168 5.6 Tamarind Tree 5.4 Left

4169 5.8 Banyan Tree Left

4170 88/950 89/000 4 Tamarind Tree 3.5 Right

4171 89/000 89/050 4 Tamarind Tree 4.1 Right

4172 5.5 Tamarind Tree 3.1 Right

4173 5 Tamarind Tree 2.8 Right

207.

208.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4174 89/050 89/100 6.1 Tamarind Tree 2.4 Left

4175 6 Tamarind Tree 4.8 Left

4176 89/100 89/150 5.6 Tamarind Tree 3.8 Left

4177 89/150 89/200 6.5 Tamarind Tree 3.3 Left

4178 6.4 Tamarind Tree 3.3 Left

4179 89/150 89/200 6.4 Tamarind Tree 5.1 Left

4180 89/200 89/250 5.8 Tamarind Tree 4.2 Left

4181 6.2 Naval Tree 3.6 Right

4182 89/250 89/300 5.9 Naval Tree 3 Right

4183 5 Naval Tree 3.1 Right

4184 5.4 Naval Tree 4.4 Right

4185 89/300 89/350 6.3 Tamarind Tree 1.4 Left

4186 89/350 89/400 6.5 Tamarind Tree 5.4 Left

4187 6.2 Tamarind Tree 3.6 Left

4188 89/400 89/450 6.5 Tamarind Tree 2.8 Left

4189 5.5 Tamarind Tree 4.1 Left

4190 5.5 Tamarind Tree 3.8 Left

4191 89/450 89/500 5.8 Tamarind Tree 3.2 Left

4192 6.5 Tamarind Tree 3.4 Left

4193 89/500 89/550 6.1 Tamarind Tree 3.6 Left

4194 89/500 89/550 6.4 Tamarind Tree 3.8 Left

4195 6.5 Tamarind Tree 3.1 Left

4196 89/550 89/600 5.8 Tamarind Tree 3.6 Left

4197 5.1 Neem Tree 1 Left

4198 89/650 89/700 6.1 Tamarind Tree 3.2 Left

4199 89/700 89/750 5.8 Tamarind Tree 5.4 Left

4200 5.6 Tamarind Tree 3.2 Left

4201 89/750 89/800 6.2 Tamarind Tree 2.6 Right

4202 89/850 89/900 6.2 Naval Tree 3.6 Left

4203 6.2 Palm Tree 1.2 Left

4204 89/900 89/950 6.2 Marutham Tree 2.6 Left

4205 6.5 Tamarind Tree 1.2 Left

4206 89/950 90/000 4 Marutham Tree 3.6 Right

4207 89/950 90/000 4 Marutham Tree 2 Right

4208 5.3 Marutham Tree 3.4 Right

4209 90/000 90/050 3.8 Marutham Tree 2.9 Right

4210 4.2 Naval Tree 3.4 Right

4211 90/050 90/100 5.1 Tamarind Tree 2.8 Left

4212 3.8 Tamarind Tree 3.3 Right

4213 90/100 90/150 4.5 Tamarind Tree 1.8 Left

368

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4214 4.8 Tamarind Tree 3.2 Left

4215 4.6 Tamarind Tree 1.9 Left

4216 90/200 90/250 5.8 Pungai Tree 0.6 Left

4217 2.5 Marutham Tree 1.5 Left

4218 2.7 Naval Tree 3.1 Left

4219 90/250 90/300 2.5 Marutham Tree 1.4 Left

4220 2.4 Marutham Tree 3.2 Left

4221 2.4 Naval Tree 3.1 Left

4222 5.8 Marutham Tree 3.8 Right

4223 90/300 90/350 4.6 Naval Tree 4.1 Right

4224 6 Naval Tree 3.6 Right

4225 4.9 Tamarind Tree 3.4 Right

4226 90/350 90/400 6.5 Pungai Tree 0.8 Left

4227 90/500 90/550 6.4 Tamarind Tree 3.8 Left

4228 90/550 90/600 4 Tamarind Tree 3.2 Left

4229 90/600 90/950 4 Tamarind Tree 1.6 Left

4230 4.2 Tamarind Tree 3.1 Left

4231 90/650 90/700 5 Neem Tree 0.5 Left

4232 4.8 Tamarind Tree 2.8 Left

4233 90/850 90/900 6.5 Neem Tree 0.8 Left

4234 90/900 90/950 6.5 Tamarind Tree 1.1 Left

4235 90/950 91/000 6.5 Tamarind Tree 1.1 Left

4236 91/000 91/050 6.5 Tamarind Tree 2.6 Right

4237 6.5 Tamarind Tree 1.6 Right

4238 91/400 91/450 6.5 Tamarind Tree 1 Right

4239 91/450 91/500 6.3 Tamarind Tree 1 Right

4240 6.5 Tamarind Tree 1.2 Right

4241 91/500 91/550 6.5 Tamarind Tree 1.7 Right

4242 91/750 91/800 5.8 Neem Tree 1 Left

4243 91/800 91/850 5.8 Neem Tree 1.1 Left

4244 6.5 Neem Tree 0.7 Right

4245 91/850 91/900 6.5 Neem Tree 1.3 Left

4246 6.1 Neem Tree 1.1 Left

4247 91/900 91/950 6 Neem Tree 0.5 Left

4248 6 Neem Tree 0.9 Left

4249 6 Karivelam Tree 1.3 Left

4250 91/950 92/000 5.8 Neem Tree 0.9 Left

4251 5.4 Tamarind Tree 2.6 Left

4252 92/000 92/050 5 Palm Tree 1.1 Left

4253 6.1 Neem Tree 1 Left

211.

212.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4254 92/050 92/100 5.4 Banyan Tree 6.1 Left

4255 6.5 Neem Tree 0.85 Right

4256 92/100 92/150 6.2 Neem Tree 0.5 Right

4257 92/150 92/200 5.3 Banyan Tree 3.3 Left

4258 5.8 Tamarind Tree 1.3 Left

4259 6 Neem Tree 0.85 Left

4260 6.3 Neem Tree 1 Left

4261 92/200 92/250 6.5 Tamarind Tree 1.1 Left

4262 92/250 92/300 6.4 Tamarind Tree 1 Left

4263 6.4 Tamarind Tree 1.2 Left

4264 92/300 92/350 6.5 Tamarind Tree 1.1 Left

4265 92/350 92/400 5.6 Tamarind Tree 3.6 Left

4266 92/500 92/550 6.2 Tamarind Tree 1.3 Left

4267 6.3 Tamarind Tree 1.1 Left

4268 5.2 Tamarind Tree 2.7 Left

4269 92/550 92/600 5.5 Tamarind Tree 3.9 Left

4270 6.5 Tamarind Tree 2 Left

4271 6.3 Tamarind Tree 2.1 Left

4272 92/600 92/650 6.3 Tamarind Tree 2 Left

4273 92/650 92/700 6.4 Tamarind Tree 1.2 Left

4274 92/700 92/750 5.8 Tamarind Tree 2.6 Left

4275 92/750 92/800 5.8 Tamarind Tree 3.1 Left

4276 6.4 Neem Tree 0.9 Right

4277 6.1 Tamarind Tree 2.1 Right

4278 92/800 92/850 5.2 Tamarind Tree 3.3 Left

4279 5 Tamarind Tree 3 Left

4280 92/800 92/850 6.4 Neem Tree 0.9 Left

4281 92/850 92/900 6.5 Neem Tree 1 Left

4282 6.5 Neem Tree 1.2 Left

4283 92/900 92/950 4.2 Tamarind Tree 2.2 Left

4284 4 Tamarind Tree 3.1 Left

4285 4.1 Tamarind Tree 2.1 Left

4286 3.8 Tamarind Tree 2.4 Left

4287 92/950 93/000 3.6 Tamarind Tree 3 Left

4288 3.8 Tamarind Tree 3.6 Left

4289 93/050 93/100 5.8 Tamarind Tree 3 Right

4290 93/100 93/150 5 Tamarind Tree 3.2 Right

4291 93/200 93/250 6.3 Tamarind Tree 5.2 Right

4292 93/250 93/300 6.5 Tamarind Tree 4.5 Right

4293 5.4 Tamarind Tree 3.8 Left

370

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4294 93/300 93/350 4 Tamarind Tree 4.2 Right

4295 5.6 Tamarind Tree 4.3 Right

4296 6.4 Tamarind Tree 3.6 Right

4297 93/350 93/400 6.5 Tamarind Tree 2.9 Left

4298 93/400 93/450 5 Tamarind Tree 3.1 Right

4299 93/450 93/500 4.2 Tamarind Tree 2.7 Left

4300 3.8 Tamarind Tree 2.4 Left

4301 94/250 94/300 6.5 Naval Tree 2 Right

4302 5.8 Palm Tree 1.4 Right

4303 5.9 Palm Tree 1.1 Right

4304 94/350 94/400 0.5 Palm Tree 1.1 Right

4305 2 Palm Tree 1.1 Right

4306 2 Palm Tree 1.1 Right

4307 1 Palm Tree 1.2 Right

4308 94/350 94/400 3 Palm Tree 1.2 Left

4309 3 Neem Tree 1 Left

4310 3.7 Tamarind Tree 1.3 Left

4311 94/400 94/450 3.3 Palm Tree 1.3 Left

4312 3.3 Tamarind Tree 1.4 Left

4313 3.6 Neem Tree 1 Left

4314 3.4 Neem Tree 1.1 Left

4315 4 Palm Tree 1.4 Left

4316 6 Palm Tree 1.2 Left

4317 6 Neem Tree 1.3 Left

4318 6.5 Palm Tree-3 1.2 Left

4319 6 Neem Tree 0.9 Left

4320 94/550 94/600 5.8 Palm Tree 1.1 Right

4321 94/600 94/650 5.8 Palm Tree 1.4 Right

4322 6.4 Palm Tree 1.2 Right

4323 6.4 Palm Tree 1.2 Right

4324 94/650 94/700 5.7 Palm Tree 1.2 Right

4325 5.7 Palm Tree 1.2 Right

4326 5.8 Palm Tree 1.3 Right

4327 4.6 Tamarind Tree 1.2 Right

4328 94/700 94/750 4.6 Palm Tree 1.4 Right

4329 94/750 94/800 5.8 Neem Tree 1.1 Right

4330 94/800 94/850 6.3 Palm Tree 1.3 Right

4331 94/850 94/900 6.3 Palm Tree 1.1 Right

4332 6.4 Palm Tree 1.1 Right

4333 6.4 Palm Tree 1.1 Right

215.

216.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4334 6.4 Palm Tree 1.1 Right

4335 6.2 Neem Tree 0.7 Right

4336 94/900 94/950 6.3 Neem Tree 0.8 Right

4337 6.5 Palm Tree 1.3 Right

4338 6.5 Palm Tree 1.1 Right

4339 94/900 94/950 6.8 Palm Tree 1.2 Left

4340 5.1 Neem Tree 0.95 Right

4341 6.5 Palm Tree 1 Right

4342 6.5 Palm Tree 1 Right

4343 6.5 Palm Tree 1 Right

4344 6.5 Neem Tree 0.8 Right

4345 95/000 95/050 4.9 Palm Tree 1.2 Left

4346 5.8 Neem Tree 1 Left

4347 5.1 Palm Tree 1 Left

4348 6.5 Palm Tree 1.2 Left

4349 6.5 Neem Tree 1 Left

4350 6.5 Nona Tree 1 Left

4351 6.5 Palm Tree 1.5 Left

4352 95/050 95/100 6.3 Palm Tree 1.6 Left

4353 5.5 Palm Tree 1.5 Left

4354 5.5 Palm Tree 1.2 Left

4355 5.5 Palm Tree 1.2 Left

4356 5.5 Palm Tree 1.2 Left

4357 5.5 Palm Tree 1.2 Left

4358 5.5 Palm Tree 1.2 Left

4359 5.5 Palm Tree 1.2 Left

4360 95/100 95/150 5.5 Neem Tree 0.4 Left

4361 5.8 Palm Tree 1.3 Left

4362 5.8 Neem Tree 1.1 Left

4363 6.3 Neem Tree 0.9 Left

4364 6.3 Palm Tree 1.6 Left

4365 6.5 Palm Tree 1.2 Left

4366 95/100 95/200 6.5 Kattuva Tree 1.3 Left

4367 6.2 Neem Tree 0.7 Left

4368 6.5 Palm Tree 1.2 Left

4369 6.5 Palm Tree 1.2 Left

4370 6.5 Palm Tree 1.3 Right

4371 6.5 Palm Tree 1.3 Right

4372 5.2 Neem Tree 0.8 Right

4373 95/200 95/250 6.5 Neem Tree 0.9 Left

372

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4374 5.2 Neem Tree 1.3 Right

4375 6.5 Palm Tree 1.4 Right

4376 6.1 Tamarind Tree 1.7 Right

4377 95/250 95/300 5.8 Palm Tree 1.2 Right

4378 95/250 95/300 3.4 Neem Tree 1 Right

4379 5.7 Palm Tree 1.5 Right

4380 5.7 Palm Tree 1.5 Right

4381 5.7 Palm Tree 1.5 Right

4382 4.8 Kattuva Tree 1.1 Right

4383 4 Neem Tree 1.2 Right

4384 4.6 Neem Tree 1.3 Right

4385 5.2 Neem Tree 1.8 Right

4386 95/300 95/350 5.5 Palm Tree 1.4 Right

4387 5.5 Palm Tree 1.4 Right

4388 6.5 Palm Tree 1.3 Right

4389 6.5 Palm Tree 1.3 Right

4390 95/350 95/400 5.9 Neem Tree 1.2 Right

4391 6.1 Neem Tree 0.6 Right

4392 5.9 Neem Tree 0.8 Right

4393 6.3 Neem Tree 1 Right

4394 95/400 95/450 4.8 Palm Tree 1.1 Right

4395 4.8 Palm Tree 1.1 Right

4396 5.6 Palm Tree 1.2 Right

4397 95/500 95/550 6.5 Banyan Tree 3.2 Left

4398 6.5 Tamarind Tree 3.4 Left

4399 6.5 Tamarind Tree 2 Left

4400 6.5 Tamarind Tree 1.8 Left

4401 95/550 95/600 6.5 Tamarind Tree 1 Left

4402 6 Tamarind Tree 2.4 Left

4403 6.5 Tamarind Tree 1.9 Left

4404 95/600 95/650 6.5 Tamarind Tree 2 Left

4405 6.4 Tamarind Tree 2.8 Left

4406 6.5 Tamarind Tree 1.9 Left

4407 95/650 95/700 6.5 Tamarind Tree 2 Right

4408 6.3 Palm Tree 1.1 Right

4409 95/950 96/000 6.5 Palm Tree 1.2 Left

4410 96/000 96/050 6 Tamarind Tree 3 Right

4411 96/200 96/250 4.5 Tamarind Tree 2.3 Left

4412 96/250 96/300 6.5 Naval Tree 1.1 Left

4413 96/300 96/350 6.3 Naval Tree 1.6 Left

219.

220.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4414 96/450 96/500 5.5 Kattuva Tree 1 Left

4415 5.2 Kattuva Tree 2.2 Left

4416 6.2 Kattuva Tree 2.1 Left

4417 96/450 96/500 4.8 Tamarind Tree 1.4 Left

4418 96/600 96/650 6.2 Pungai Tree 2.8 Right

4419 96/850 96/900 6.4 Pungai Tree 1.4 Right

4420 97/050 97/100 3 Pungai Tree 0.8 Right

4421 3.4 Pungai Tree 0.6 Right

4422 97/100 97/150 4.1 Pungai Tree 0.8 Right

4423 6 Pungai Tree 1.4 Right

4424 3.9 Eacham Tree 1 Right

4425 97/150 97/200 6.1 Pungai Tree 1.3 Left

4426 6.5 Palm Tree 1 Right

4427 6.5 Palm Tree 1 Right

4428 6.5 Pungai Tree 2 Right

4429 6.5 Pungai Tree 1.4 Right

4430 6.5 Eacham Tree 1.2 Right

4431 6.3 Eacham Tree 1.2 Right

4432 97/200 97/250 5 Eacham Tree 1 Left

4433 6.5 Pungai Tree 1.4 Left

4434 6.5 Pungai Tree 1.8 Left

4435 6.5 Kattuva Tree 0.5 Left

4436 6.5 Kattuva Tree 0.7 Left

4437 97/250 97/300 6 Pungai Tree 1.6 Left

4438 6.2 Pungai Tree 1.8 Left

4439 97/250 97/300 4 Eacham Tree 1.1 Left

4440 4.4 Eacham Tree 1.1 Left

4441 6 Pungai Tree 1.2 Left

4442 97/300 97/350 5.8 Eacham Tree 1.2 Left

4443 6.4 Pungai Tree 2 Left

4444 6.5 Marutham Tree 0.9 Left

4445 97/350 97/400 6.1 Pungai Tree 1.8 Left

4446 6.5 Pungai Tree 1.2 Left

4447 6.5 Pungai Tree 1.6 Left

4448 97/400 97/450 6 Pungai Tree 1.2 Left

4449 6.5 Palm Tree 1.3 Left

4450 97/450 97/500 6.5 Neem Tree 1.1 Left

4451 6.2 Pungai Tree 0.9 Left

4452 6 Neem Tree 1.2 Left

4453 6.5 Pungai Tree 1.1 Left

374

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4454 97/500 97/550 6.3 Pungai Tree 0.7 Left

4455 6.5 Pungai Tree 0.9 Left

4456 6.5 Pungai Tree 0.9 Left

4457 5 Palm Tree 1.3 Right

4458 97/550 97/600 5.2 Palm Tree 1.6 Right

4459 5.2 Palm Tree 1.2 Right

4460 97/650 97/700 6.2 Palm Tree 1 Left

4461 6.5 Eacham Tree 1.1 Left

4462 97/720 97/750 6.5 Pungai Tree 0.3 Left

4463 6.3 Eacham Tree 1.1 Left

4464 6.5 Marutham Tree 0.8 Left

4465 6.5 Palm Tree 1.4 Right

4466 97/750 97/800 5.3 Neem Tree 1.8 Left

4467 5.2 Palm Tree 1.3 Left

4468 97/750 97/800 5.4 Eacham Tree 1.3 Left

4469 5.3 Neem Tree 3.2 Left

4470 97/800 97/850 6 Neem Tree 1.4 Right

4471 6.2 Pungai Tree 0.9 Right

4472 97/850 97/900 5.6 Palm Tree 1.4 Right

4473 5.6 Palm Tree 1.4 Right

4474 5.6 Palm Tree 1.4 Right

4475 5.6 Palm Tree 1.4 Right

4476 5.6 Palm Tree 1.4 Right

4477 4.8 Banyan Tree 4.8 Right

4478 97/900 97/950 4 Palm Tree 1.6 Right

4479 97/950 98/000 5 Tamarind Tree 2.8 Right

4480 5.2 Tamarind Tree 1.8 Right

4481 5.1 Tamarind Tree 2.3 Right

4482 98/000 98/050 5.1 Tamarind Tree 2.1 Right

4483 98/050 98/100 2.6 Pungai Tree 1.3 Right

4484 98/100 98/150 2 Tamarind Tree 1.6 Right

4485 2.5 Tamarind Tree 2.6 Right

4486 2.6 Tamarind Tree 2.9 Right

4487 98/100 98/150 2 Tamarind Tree 2.3 Right

4488 98/150 98/200 2.1 Tamarind Tree 2.8 Right

4489 2.2 Tamarind Tree 2.6 Right

4490 2.2 Tamarind Tree 2.1 Right

4491 2.5 Tamarind Tree 2.7 Right

4492 98/200 98/250 2.6 Tamarind Tree 1.3 Right

4493 2.5 Tamarind Tree 1.4 Right

223.

224.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4494 2.5 Tamarind Tree 2.6 Right

4495 2.8 Tamarind Tree 1.8 Right

4496 2.8 Tamarind Tree 1.2 Right

4497 98/250 98/300 5.3 Neem Tree 1.1 Right

4498 5.1 Tamarind Tree 3.1 Right

4499 5.3 Tamarind Tree 2.1 Right

4500 98/300 98/350 5.3 Palm Tree 1.3 Right

4501 98/350 98/400 4.5 Tamarind Tree 1.4 Right

4502 98/350 98/400 4.6 Tamarind Tree 1.2 Right

4503 98/400 98/450 4.4 Neem Tree 0.9 Right

4504 4.4 Neem Tree 0.6 Right

4505 98/500 98/550 6.1 Neem Tree 0.7 Right

4506 4.6 Palm Tree 1.5 Right

4507 6.3 Neem Tree 1.2 Right

4508 6.2 Neem Tree 0.3 Right

4509 5.1 Palm Tree 1.3 Right

4510 5.2 Nona Tree 0.4 Right

4511 98/800 98/850 6.5 Marutham Tree 1 Right

4512 98/850 98/900 4.3 Palm Tree 1.2 Right

4513 5.7 Neem Tree 0.9 Right

4514 98/900 98/950 6.5 Neem Tree 1.6 Left

4515 6.5 Neem Tree 1.2 Left

4516 98/950 99/000 6.3 Palm Tree 1.1 Left

4517 6 Palm Tree 1.2 Left

4518 6 Palm Tree 1.2 Left

4519 6.3 Pungai Tree 0.7 Right

4520 99/000 99/050 4.5 Palm Tree 1.1 Right

4521 6.5 Palm Tree 1.1 Right

4522 4.5 Palm Tree 1.1 Right

4523 99/050 99/100 5.8 Palm Tree 1.3 Left

4524 5.8 Palm Tree 1.3 Left

4525 6.2 Palm Tree 1.2 Left

4526 6.2 Palm Tree 1.2 Left

4527 6.2 Palm Tree 1.2 Left

4528 5.7 Palm Tree 1.2 Right

4529 6.5 Palm Tree 1.3 Right

4530 99/150 99/200 5.4 Marutham Tree 1.1 Left

4531 99/200 99/250 6.1 Palm Tree 1 Left

4532 5.7 Palm Tree 1.2 Right

4533 6 Palm Tree 1 Left

376

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4534 99/250 99/300 3.8 Palm Tree 1.1 Left

4535 99/350 99/400 6.2 Palm Tree 1.2 Left

4536 99/600 99/650 6.5 Neem Tree 2 Left

4537 99/650 99/700 5.9 Pungai Tree 1.3 Left

4538 99/700 99/750 6.5 Tamarind Tree 2.2 Left

4539 99/750 99/800 6.1 Palm Tree 1.2 Right

4540 100/100 100/150 4.3 Palm Tree 1.1 Right

4541 100/450 100/500 6 Palm Tree 1.3 Left

4542 6.5 Pungai Tree 1.1 Left

4543 100/650 100/700 6.5 Palm Tree 1.2 Left

4544 6.5 Palm Tree 1.1 Left

4545 100/700 100/750 6.5 Palm Tree 1.5 Left

4546 6.5 Palm Tree 1.5 Left

4547 6.5 Palm Tree 1.5 Left

4548 100/750 100/800 6.3 Karuvelam Tree 1.9 Right

4549 100/800 100/850 6.5 Palm Tree 1.3 Right

4550 6.5 Othiyam Tree 2.6 Right

4551 6.5 Pungai Tree 2.4 Right

4552 100/850 100/900 6.5 Palm Tree 1.3 Right

4553 100/900 100/950 6.5 Tamarind Tree 2.9 Left

4554 100/950 101/000 6.1 Neem Tree 0.9 Right

4555 6.2 Neem Tree 1 Right

4556 6.8 Palm Tree 1.2 Right

4557 101/000 101/050 6.3 Palm Tree 1.4 Right

4558 101/000 101/050 5.5 Palm Tree 1.1 Right

4559 6.2 Palm Tree 1.3 Right

4560 101/050 101/100 4.8 Palm Tree 1.2 Right

4561 6.4 Palm Tree 1.1 Right

4562 101/100 101/150 6.5 Neem Tree 0.8 Right

4563 5.8 Palm Tree 1.1 Right

4564 101/150 101/200 6.5 Marutham Tree 1.2 Left

4565 101/200 101/250 5.8 Palm Tree 1.3 Right

4566 6 Palm Tree 1.2 Right

4567 101/250 101/300 6.5 Palm Tree 1.3 Right

4568 1 Pungai Tree 0.9 Right

4569 1 Pungai Tree 0.8 Right

4570 1 Pungai Tree 1 Right

4571 1 Palm Tree 1.1 Right

4572 101/300 101/330 3 Marutham Tree 1.2 Right

4573 101/400 101/450 6 Palm Tree 1.1 Right

227.

228.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4574 101/450 101/500 0.8 Tamarind Tree 1.2 Right

4575 101/500 101/550 0.5 Tamarind Tree 2.6 Left

4576 2 Tamarind Tree 2 Left

4577 101/700 101/750 3 Tamarind Tree 2.6 Right

4578 3 Tamarind Tree 2.8 Right

4579 4.2 Tamarind Tree 2.7 Right

4580 101/800 101/830 6.2 Tamarind Tree 3.4 Left

4581 101/850 101/900 4 Tamarind Tree 3.5 Left

4582 101/900 101/950 4.5 Tamarind Tree 2.8 Left

4583 101/950 102/000 5.7 Tamarind Tree 3.7 Left

4584 6.5 Kodukkapuli Tree 1.3 Left

4585 6 Palm Tree 1.3 Left

4586 101/000 102/050 5 Palm Tree 1.1 Left

4587 5 Palm Tree 1.1 Left

4588 5 Palm Tree 1.1 Left

4589 5 Palm Tree 1.1 Left

4590 5 Palm Tree 1.1 Left

4591 102/050 102/100 5.9 Neem Tree 1.1 Right

4592 5.6 Tamarind Tree 4.2 Right

4593 102/150 102/200 5 Naval Tree 3.5 Left

4594 6.5 Palm Tree 1 Left

4595 6.5 Palm Tree 1 Left

4596 102/200 102/250 6.5 Neem Tree 1.6 Right

4597 102/250 102/300 6 Tamarind Tree Left

4598 102/300 102/350 6.5 Palm Tree 1.2 Right

4599 6.5 Palm Tree 1.2 Right

4600 102/400 102/450 6.5 Badham Tree 1 Left

4601 6.2 Badham Tree 0.4 Left

4602 102/450 102/500 6.4 Palm Tree 1 Left

4603 6.2 Neem Tree 1.8 Left

4604 6.5 Palm Tree 1.2 Left

4605 5.2 Palm Tree 1.3 Left

4606 102/500 102/550 5.3 Palm Tree 1.2 Left

4607 102/550 102/600 5.8 Palm Tree 1 Left

4608 4.4 Palm Tree 1.1 Left

4609 6 Kattuva Tree 3.2 Left

4610 6.5 Neem Tree 3.1 Left

4611 102/650 102/700 4.7 Palm Tree 1.2 Left

4612 102/800 102/850 5.7 Pungai Tree 1.2 Right

4613 6.5 Kattuva Tree 1.9 Right

378

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4614 102/900 102/950 3 Tamarind Tree 2.7 Right

4615 102/950 103/000 5.2 Tamarind Tree 2.1 Right

4616 103/000 103/050 5.6 Tamarind Tree 3.7 Left

4617 103/100 103/150 6 Palm Tree 1 Left

4618 6.5 Neem Tree 1.1 Right

4619 103/200 103/250 5.8 Palm Tree 1 Right

4620 103/250 103/300 6 Palm Tree 1.2 Left

4621 103/300 103/350 6.5 Palm Tree 1.1 Left

4622 103/350 103/400 5 Tamarind Tree 2.3 Left

4623 5 Palm Tree 1.2 Left

4624 103/400 103/450 3 Tamarind Tree 3.4 Left

4625 5.2 Tamarind Tree 2.8 Left

4626 103/450 103/500 5.8 Tamarind Tree 3.4 Left

4627 103/500 103/550 6.1 Tamarind Tree 3.4 Right

4628 103/550 103/600 5.7 Tamarind Tree 2.8 Left

4629 103/600 103/650 5.8 Tamarind Tree 2.6 Left

4630 6.2 Tamarind Tree 3.2 Left

4631 6 Tamarind Tree 2.8 Left

4632 103/650 103/700 6 Tamarind Tree 2.6 Right

4633 6.1 Tamarind Tree 1.9 Right

4634 103/700 103/750 6.5 Tamarind Tree 3.2 Left

4635 6 Tamarind Tree 2.6 Left

4636 5.8 Tamarind Tree 3.4 Left

4637 103/750 103/800 4.4 Palm Tree 1.2 Left

4638 6.5 Palm Tree 1.1 Left

4639 103/800 103/850 6 Tamarind Tree 3.3 Left

4640 6.2 Tamarind Tree 3.3 Left

4641 103/850 103/900 4.2 Palm Tree 1.2 Right

4642 4.2 Palm Tree 1.2 Right

4643 4.2 Palm Tree 1.2 Right

4644 4.2 Palm Tree 1.2 Right

4645 4.2 Palm Tree 1.2 Right

4646 4.2 Palm Tree 1.1 Right

4647 4.2 Palm Tree 1.1 Right

4648 4.2 Palm Tree 1.1 Right

4649 4.2 Palm Tree 1.1 Right

4650 4.4 Palm Tree 1.1 Right

4651 4.4 Palm Tree 1.1 Right

4652 5.9 Palm Tree 1.2 Right

4653 103/900 103/950 5.7 Tamarind Tree 4.6 Left

231.

232.

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4654 5.7 Tamarind Tree 4.5 Left

4655 5.6 Tamarind Tree 3.8 Left

4656 5.2 Palm Tree 1.4 Right

4657 5 Palm Tree 1.1 Right

4658 5.2 Palm Tree 1.1 Right

4659 5.2 Palm Tree 1.1 Right

4660 103/950 104/000 6.4 Tamarind Tree 3.2 Left

4661 5.7 Palm Tree 1.3 Right

4662 5.4 Palm Tree 1.3 Right

4663 5.4 Palm Tree 1.3 Right

4664 5.4 Palm Tree 1.3 Right

4665 5.4 Palm Tree 1.3 Right

4666 5.4 Palm Tree 1.3 Right

4667 5.4 Palm Tree 1.3 Right

4668 5.4 Palm Tree 1.3 Right

4669 5.4 Palm Tree 1.3 Right

4670 5.4 Palm Tree 1.3 Right

4671 5.4 Palm Tree 1.3 Right

4672 5.4 Palm Tree 1.3 Right

4673 5.4 Palm Tree 1.3 Right

4674 104/000 104/050 4.2 Palm Tree 1.4 Right

4675 4.2 Palm Tree 1.4 Right

4676 4.2 Palm Tree 1.4 Right

4677 4.2 Palm Tree 1.4 Right

4678 6.5 Neem Tree 1.6 Right

4679 104/000 104/050 4.5 Neem Tree 0.6 Right

4680 4.8 Neem Tree 0.9 Right

4681 6.2 Tamarind Tree 5 Right

4682 6.4 Neem Tree 0.5 Right

4683 104/150 104/200 6.2 Thailam Tree 1.9 Left

4684 104/550 104/570 1.5 Palm Tree 1 Right

4685 104/570 104/600 1.5 Tamarind Tree 2 Right

4686 104/650 104/700 1.7 Tamarind Tree Left

4687 104/700 104/750 1.7 Tamarind Tree 1.8 Left

4688 1.7 Tamarind Tree 1.9 Left

4689 104/750 104/800 0.2 Tamarind Tree 2.2 Left

4690 1 Tamarind Tree 3.4 Left

4691 104/800 104/850 3.9 Tamarind Tree 3 Right

4692 3.6 Tamarind Tree 3.1 Right

4693 104/850 104/900 4.2 Tamarind Tree 4.7 Left

380

Sl. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

4694 104/900 104/950 4.2 Tamarind Tree 2.6 Right

4695 105/000 105/050 2.3 Tamarind Tree 1.2 Left

4696 105/030 105/050 2.3 Tamarind Tree 2.8 Left

4697 105/050 105/080 1.5 Tamarind Tree 2.4 Left

4698 0.6 Tamarind Tree 2.6 Left

4699 105/100 105/150 6.1 Kodukkapuli Tree 3.4 Left

4700 105/150 105/200 6.5 Nona Tree 0.6 Left

4701 3.9 Tamarind Tree 3.6 Left

4702 105/200 105/250 6.5 Tamarind Tree 3.7 Right

4703 105/500 105/550 5.42 Tamarind Tree 3.2 Right

4704 105/550 105/600 1.58 Tamarind Tree 1.1 Left

4705 105/600 105/650 5.3 Tamarind Tree 3.1 Right

4706 5 Tamarind Tree 2.8 Right

4707 105/650 105/700 0.2 Tamarind Tree 2.9 Left

4708 2.2 Tamarind Tree 2.8 Left

4709 105/700 105/720 3.2 Tamarind Tree 3.1 Left

4710 105/720 105/750 0.1 Tamarind Tree 3.6 Right

4711 105/750 105/800 4.6 Neem Tree 3 Left

4712 105/950 106/000 6.5 Tamarind Tree 4.4 Left

4713 5.2 Palm Tree 1 Left

4714 106/000 106/050 4.2 Palm Tree 1.1 Left

4715 106/050 106/100 3 Tamarind Tree 4.1 Left

4716 4.8 Tamarind Tree 3.8 Left

1. ECR Link

1 3/500 3/550 6.5 Palm Tree 1.2 Left

2 3/750 3/800 6.5 Palm Tree 1.3 Right

3 3/800 3/850 6.5 Palm Tree 1.2 Left

4 6 Palm Tree 1.2 Left

5 6.5 Palm Tree 1.2 Left

6 6.5 Palm Tree 1.3 Left

7 6.5 Palm Tree 1.3 Left

8 6.5 Palm Tree 1.2 Left

9 3/850 3/900 6.5 Palm Tree 1.2 Left

10 6.5 Palm Tree 1.3 Left

11 4/100 4/150 6.5 Palm Tree 1.2 Left

12 4/150 4/200 6.5 Poovarasam Tree 1 Left

13 3.5 Palm Tree 1.2 Right

14 3.5 Palm Tree 1.2 Right

15 3.5 Palm Tree 1.2 Right

235.

381

381

l. No.

Chainage Offset from C/L

Name of Tree

Girth

Left/Right

Remarks

From

To

16 3.9 Palm Tree 1.2 Right

17 6.5 Palm Tree 1.2 Right

18 6.5 Palm Tree 1.2 Right

19 6.5 Palm Tree 1.2 Right

20 4/200 4/250 6.5 Pencil Tree 0.6 Left

21 6.5 Pencil Tree 0.6 Left

22 6.5 Pencil Tree 0.6 Left

23 6.5 Pencil Tree 0.6 Left

24 6.5 Pencil Tree 0.6 Left

25 6.5 Pencil Tree 0.6 Left

26 6.5 Pencil Tree 0.6 Left

27 6.5 Tailam Tree 1.3 Left

28 6.5 Pencil Tree 0.2 Left

29 6.5 Pencil Tree 0.2 Left

30 6.5 Pencil Tree 0.2 Left

31 6.5 Pencil Tree 0.2 Left

32 6.5 Tailam Tree 0.5 Left

33 6.5 Tailam Tree 0.5 Left

34 6.5 Tailam Tree 0.5 Left

35 6.5 Tailam Tree 0.5 Left

36 5.5 Palm Tree 1.2 Right

37 5.5 Neem Tree 0.5 Right

38 5.5 Neem Tree 0.6 Right

39 4/250 4/300 6.5 Tailam Tree 0.3 Left

40 6.5 Tailam Tree 2.2 Left

41 6.5 Tailam Tree 1 Left

42 6.5 Tailam Tree 1 Left

43 Palm Tree 1.2 Right

44 4/300 4/350 6.5 Neem Tree 1.8 Left

45 6.5 Neem Tree 1 Left

46 6.5 Palm Tree 1.2 Left

47 4/450 4/500 1 Palm Tree 1.2 Left

48 1 Neem Tree 1.3 Left

49 4/550 4/600 6.5 Neem Tree 0.5 Left

50 6.5 Neem Tree 0.5 Left

51 6.5 Poovarasam Tree 0.4 Right

52 4/600 4/650 6.5 Neem Tree 1.5 Left

53 6.5 Poovarasam Tree 0.2 Right

54 4/650 4/700 6.5 Pungai Tree 0.4 Left

382

383

Appendix -6: Details of Protected Areas in Tamil Nadu

Protected Natural Habitats

Tamilnadu Government has established many National Parks and Wild Life Sanctuaries to protect important species. None of the national parks and Wild life Sanctuaries pass through the Project enroute. The following is the list of National Parks and Wildlife Sanctuaries (WS) and their year of establishment are presented in Table below.

National Parks

Tamil Nadu has 5 declared National Parks with a total area over 307.84 km2 (118.86 sq mi), covering only 0.24% of the state. This is the third lowest % area covered of all Indian states and Union territories.

List of National Park in Tamilnadu

Name of National Park Area (in km2) Establishment

Indira Gandhi National Park (Aanamalai National Park) 117.10 1989

Mudumalai National Park 103.24 1990

Mukurthi National Park 78.46 1982

Gulf of Mannar Marine National Park 6.23 1980

Guindy National Park 2.82 1976

Wildlife sanctuaries:

There are 7 wildlife sanctuaries plus 13 bird sanctuaries that together cover over 2,997.60 km2 (1,157.38 sq mi), 2.30% of the total state area.

List of Wild Life Sanctuaries in Tamil Nadu

Name of Wild Life Sanctuaries Area (in km

2)

Animals

Grizzled Squirrel Wildlife Sanctuary, near Srivilliputhur in Virudhunagar district

485 Grizzled Giant Squirrel, Flying Squirrel, Tree Shrew, Elephant, lion-tailed macaque, Nilgiri Tahr, mouse deer, barking deer

Indira Gandhi Wildlife Sanctuary, Coimbatore District

841.49 Indian Elephant, Gaur, Tiger, Panther, Sloth Bear, Wild Boar, Dhole, Nilgiri Langur, Lion-tailed Macaque, Sambar, Four horned Antelope, Chital and a host of birds, notably the Trogar, Pied Hornbill and several types of Eagles may be seen

Kalakkad Wildlife Sanctuary in Tirunelveli District

Lion-tailed macaque. All four species (common Langur, Nilgiri Langur, Bonnet Macaque and lion tailed Macaque) can be seen. . Other animals include Nilgiri tahr, sambar, sloth bear, gaur, Indian elephant, tiger, flying squirrel, panther, Dhole, pangolin and a variety of birds and reptiles.

Mundanthurai Sanctuary, Tirunelveli District

282.08 Part of Kalakkad Mundanthurai Tiger Reserve

Kanyakumari Wildlife Sanctuary, Kanyakumari district

457.78 Tiger habitat in declared a sanctuary in February 2008.

Mudumalai Wildlife Sanctuary in Nilgiris district is contiguous with Mudumalai National Park.

217.76 Elephant, Gaur, Sambar, Chital, Dhole Panther, Tiger, Sloth bear, Python, Barking deer, Four-horned antelope, common Langur, Otter, Crocodiles (mugger) and a variety of birds and reptiles may be seen.

Sathyamangalam Wildlife Sanctuary in Erode district, the largest wildlife sanctuary in Tamil Nadu, was declared a sanctuary in 2008.

1,411.6 Bengal Tigers, Indian Elephants, Gaurs, and leopards, Spotted deer, Blackbuck, Sambar deer, Barking deer, Four-horned antelope, wild boar, Sloth bear, striped hyenas, Treepies, Bulbuls, Babblers, Mynahs and Crows

384

385

Appendix 7: Detailed Analysis of Air Modeling

A. Introduction

1. The major impact on the air quality during the operation stage will be due to plying of vehicles on the proposed corridor. The impact on air quality depends upon traffic volume, traffic fleet including fuel type and prevailing atmospheric conditions. An unstable atmospheric condition disperses pollutants more and results in to low pollutant concentrations while stable atmospheric conditions buildup the pollution level. To assess the likely impacts on the ambient air quality due to the proposed highway project, the prediction of the carbon monoxide (CO) and particulate matter (PM), Nitrogen Dioxide (NOx) and Sulphur Dioxide (SO2) concentrations have been carried out using line source dispersion modelling approach, based on Gaussian equation. CO is an indicator pollutant for vehicular pollution. So, prediction of CO concentration is representative of the impacts of air pollution due to traffic movement. The modeling for this project has been carried out using AERMOD-9, a steady-state plume model that incorporates air dispersion based on planetary boundary layer turbulence structure and scaling concepts, including treatment of both surface and elevated sources, and both simple and complex terrain, developed by the “The American Meteorological Society/Environmental Protection Agency Regulatory Model Improvement Committee (AERMIC)”. 2. It has been setup and run by using emission factors prevalent for Indian vehicles (ARAI, 2007) and hourly traffic volumes as predicted for the project. The study is conducted to predict 1-houly increment in CO and 24-houly increment in PM2.5, PM10, NOx and SO2 concentrations for the years 2020, 2025, 2030, 2035 and 2040.

B. Model descriptions

3. The AERMOD atmospheric dispersion modeling system is an integrated system that includes three modules: (a) A steady-state dispersion model designed for short-range (up to 50 kilometers) dispersion of air pollutant emissions from stationary industrial sources. (b) A meteorological data preprocessor (AERMET) that accepts surface meteorological data, upper air soundings, and optionally, data from on-site instrument towers. It then calculates atmospheric parameters needed by the dispersion model, such as atmospheric turbulence characteristics, mixing heights, friction velocity, Monin-Obukov length and surface heat flux. (c) A terrain preprocessor (AERMAP) whose main purpose is to provide a physical relationship between terrain features and the behavior of air pollution plumes. It generates location and height data for each receptor location. It also provides information that allows the dispersion model to simulate the effects of air flowing over hills or splitting to flow around hills. AERMOD also includes PRIME (Plume Rise Model Enhancements) [4] which is an algorithm for modeling the effects of downwash created by the pollution plume flowing over nearby buildings.

C. Source information

1. Traffic data

4. The fleet wise traffic volumes for the present study have been taken from the detailed feasibility report of the project. The annual average daily traffic (AADT) data is available for the proposed road through traffic survey. AERMOD model needs hourly average traffic volume. The total traffic hour volume is further categorized in to two-wheeler, four wheeler, Light

386

commercial vehicles (LCVs), Bus and high commercial vehicles (HCVs), based on the traffic survey at different road stretched along the highway (Figure 1).

Figure 1: Traffic Fleet on the highway

5. The annual average daily motorized traffic data are given in table 1 along with future traffic growth.

Table 1: Annual Average Daily Motorized Traffic Data

Year 4W LCV Truck Bus 3W 2W

2020 1963 801 449 1436 316 4323

2025 2964 961 551 1959 379 5894

2030 4236 1124 661 2584 444 7667

2035 5776 1285 774 3282 515 9646

2. Emission factors

6. Emission factor is one of the important input parameters in AERMOD model. In the present study, the emission factors specified by the Automotive Research Association of India (ARAI, 2007) have been used for calculation of weighted emission factors. These emission factors have been expressed in terms of type of vehicles and type of fuel used (for petrol and diesel driven passenger cars).

7. The emission factor used in the present study for different vehicles type are given in table 2.

Table 2: Emission factors for different types of Vehicle (ARAI, 2007)

Emission factors, g/km (ARAI, 2007)

4W

15%LCV

1%

Truck

11%

Bus

9%

3W

1%

2W

63%

387

2w 3w 4w lcv bus truck

CO 1.04 1.25 1.28 1.56 8.03 6

NOx 0.31 0.6 0.32 1.46 9.01 9.3

PM 0.02 0.22 0.04 0.28 0.55 1.24

SO2 0.01 0.01 0.03 0.06 0.13 0.13

3. Meteorological data

8. The meteorological parameters such as wind speed, wind direction, temperature, rainfall, cloud cover, pressure, and humidity were used in model. Meteorological parameters observed during environmental monitoring carried out in the month of December 2019 were used for the model and is given below table 3.

Table 3: Meteorological Parameters used for modelling

Hour Temperature (oC)

Humidity (%)

WD (o)

Wind Speed (kmph)

Pressure (Pa)

Precip. (mm)

Cl

1:00 28.6 84 315 0 29.82 0 0

2:00 27.6 86 45 1 29.82 0 0

3:00 26.8 81 315 4 29.87 0 0

4:00 26.7 92 0 5 29.87 0 0

5:00 24.3 94 0 7 29.87 0 0

6:00 26.4 96 0 6 29.84 0 0

7:00 27.6 92 315 2 29.84 0 0

8:00 28.7 86 45 2 29.84 0 0

9:00 32.4 73 315 3 27.78 0 0

10:00 33.6 70 45 4 27.78 0 0

11:00 33.4 77 315 2 27.78 0 0

12:00 35.6 76 315 5 29.76 0 0

13:00 34.8 71 315 1 29.76 0 0

14:00 35.5 69 0 6 29.76 0 0

15:00 32.4 72 0 7 29.83 0 0

16:00 36.5 65 0 1 29.83 0 0

17:00 32.5 62 0 6 29.83 0 0

18:00 30.5 78 315 7 29.83 0 0

19:00 31.5 88 315 6 29.83 0 0

20:00 34.2 75 315 5 29.83 0 0

21:00 32.2 62 315 5 29.8 0 0

22:00 31.8 58 315 6 29.8 0 0

23:00 30.4 51 315 3 29.8 0 0

388

24:00 29.8 79 315 2 29.82 0 0

4. Receptors

9. A set of link receptors were taken at various receptor locations within each section at a distance of 10 m, 20 m, 50 m, 100 m, 200 m and 500 m, both sides from center line of the carriageway to know the dispersion of pollutant from the road.

5. Background Concentration

10. The background pollutant concentrations were taken from environmental monitoring data. Air quality monitoring was carried out in the last quarter of 2019 at five locations throughout the alignment on two alternate days in a week. The following background pollutant concentrations were taken for model predictions:

Table 4: Average background concentration of pollutants along the alignment

Pollutant Average

Background concentration

Unit

SO2 16.84 µg/m3

NOx 32.82 µg/m3

PM10 63.62 µg/m3

PM2.5 20.28 µg/m3

CO 0 mg/m3

D. Results

11. The model has been setup and run to predict hourly average CO, PM2.5, PM10, SO2 and NOx concentrations for year 2020, 2025, 2030 and 2035 using forecasted traffic data on proposed highway. The predicted hourly average concentration of CO and 24 hourly average concentration of PM2.5, PM10, SO2 and NOx during peak traffic are shown in tables 5, 6, 7, 8, 9 for proposed highway project. The graphical representation of average pollutant concentrations on both side of the road sections shown in figures 2, 3, 4, 5 and 6 at different locations.

38

9

Ta

ble

5:

CO

pre

dic

ted

co

nc

en

tra

tio

ns

(p

pm

) a

lon

g t

he

pro

po

se

d r

oa

d

Ye

ar

CO

Co

nc

en

tra

tio

n (

µg

/m3

)

Dis

tan

ce

fro

m t

he

ce

ntr

e l

ine

of

the r

oad

, m

.

(Le

ft s

ide

)

Dis

tan

ce

fro

m t

he c

en

tre

lin

e o

f th

e r

oa

d,

m.

(Rig

ht

sid

e)

-50

0

-20

0

-10

0

-50

-2

0

-10

1

0

20

5

0

10

0

20

0

50

0

20

20

1

1.3

7

19

.85

3

2.7

1

51

.57

8

2.4

1

13

0.4

2

6

.42

2

.79

0

.80

0.5

1

0.1

0

0.0

3

20

25

1

6.1

1

28

.10

4

6.4

0

73

.15

11

6.6

9

18

4.6

5

9

.09

3

.96

1.1

4

0.7

3

0.1

5

0.0

5

20

30

2

1.8

0

38

.04

6

2.6

4

98

.75

15

7.9

4

24

9.9

2

1

2.2

8

5.3

5

1.5

4

0.9

8

0.2

0

0.0

6

20

35

2

8.4

6

49

.66

8

1.9

3

129

.16

20

6.1

9

32

6.2

7

1

6.0

5

6.9

9

2.0

1

1.2

8

0.2

6

0.0

8

Ta

ble

6:

PM

2.5

pre

dic

ted

co

nc

en

tra

tio

ns

g/m

3)

alo

ng

th

e p

rop

ose

d r

oa

d

Ye

ar

PM

2.5

Co

nc

en

tra

tio

n (

µg

/m3

)

Dis

tan

ce

fro

m t

he

ce

ntr

e l

ine

of

the r

oad

, m

. (L

eft

sid

e)

D

ista

nc

e f

rom

th

e c

en

tre

lin

e o

f th

e r

oa

d,

m.

(Rig

ht

sid

e)

-50

0

-20

0

-10

0

-50

-2

0

-10

10

2

0

50

1

00

2

00

50

0

20

20

1

8.7

1

19.1

3

19

.91

2

1.0

3

22

.48

2

4.3

4

1

8.2

0

18.1

0

18

.05

1

8.0

4

18

.03

1

8.0

3

20

25

1

8.9

5

19.5

2

20

.56

2

2.0

7

24

.05

2

6.5

7

1

8.2

7

18.1

3

18

.06

1

8.0

5

18

.03

1

8.0

3

20

30

1

9.2

2

19.9

6

21

.28

2

3.2

2

25

.81

2

9.1

2

1

8.3

4

18.6

2

18

.07

1

8.0

5

18

.03

1

8.0

3

20

35

1

9.5

3

20.4

6

22

.13

2

4.5

8

27

.83

3

2.0

1

1

8.4

2

18.2

0

18

.08

1

8.0

6

18

.03

1

8.0

3

Ta

ble

7:

PM

10

pre

dic

ted

co

nc

en

tra

tio

ns

g/m

3)

alo

ng

th

e p

rop

os

ed

ro

ad

Ye

ar

PM

10

Co

nc

en

tra

tio

n (

µg

/m3

)

Dis

tan

ce

fro

m t

he

ce

ntr

e l

ine

of

the r

oad

, m

. (L

eft

sid

e)

D

ista

nc

e f

rom

th

e c

en

tre

lin

e o

f th

e r

oa

d,

m.

(Rig

ht

sid

e)

-2

00

-1

00

-5

0

-20

-1

0

1

0

20

5

0

10

0

20

0

20

20

4

5.6

7

46.0

9

46

.87

4

7.9

9

49

.44

5

1.2

8

4

5.1

6

45.0

6

45

.01

4

5.0

0

44

.99

4

4.9

9

20

25

4

5.9

1

46.4

8

47

.52

4

9.0

3

51

.01

5

3.5

3

4

5.2

3

45.0

9

45

.02

4

5.0

1

44

.99

4

4.9

9

20

30

4

6.1

8

46.9

2

48

.24

5

0.1

8

52

.77

5

6.0

8

4

5.3

0

45.1

2

45

.03

4

5.0

1

44

.99

4

4.9

9

3

90

20

35

4

6.4

9

47.4

2

49

.09

5

1.5

4

54

.79

5

8.9

7

4

5.3

8

45.1

6

45

.04

4

5.0

2

44

.99

4

4.9

9

Ta

ble

8:

NO

x p

red

icte

d c

on

ce

ntr

ati

on

s (

µg

/m3

) a

lon

g t

he p

rop

os

ed

ro

ad

Ye

ar

NO

x C

on

ce

ntr

ati

on

g/m

3)

Dis

tan

ce

fro

m t

he

ce

ntr

e l

ine o

f th

e r

oa

d,

m.

(Le

ft s

ide

)

Dis

tan

ce

fro

m t

he

ce

ntr

e l

ine

of

the

ro

ad

, m

.

(Rig

ht

sid

e)

-50

0

-20

0

-100

-5

0

-20

-10

10

20

5

0

10

0

20

0

50

0

20

20

7

.51

1

2.1

2

20

.51

3

2.7

1

48.8

2

69

.44

1.9

5

0.8

5

0.2

4

0.1

6

0.0

3

0.0

1

20

25

1

0.4

4

16.8

6

28

.51

4

5.4

6

67.9

2

96

.66

2.7

1

1.1

8

0.3

4

0.2

2

0.0

4

0.0

1

20

30

1

3.8

8

22.4

1

37

.90

6

0.4

5

90.2

9

12

8.4

9

3

.60

1.5

7

0.4

5

0.2

9

0.0

6

0.0

2

20

35

1

7.9

2

28.9

4

48

.99

7

8.0

8

11

6.5

7

16

5.5

7

4

.65

2.0

2

0.5

8

0.3

7

0.0

7

0.0

2

Ta

ble

9:

SO

2 p

red

icte

d c

on

cen

trati

on

s (

µg

/m3

) a

lon

g t

he

pro

po

se

d r

oa

d*

Ye

ar

SO

2 C

on

ce

ntr

ati

on

g/m

3)

Dis

tan

ce

fro

m t

he

ce

ntr

e l

ine

of

the r

oad

, m

. (L

eft

sid

e)

D

ista

nc

e f

rom

th

e c

en

tre

lin

e o

f th

e r

oa

d,

m.

(Rig

ht

sid

e)

-50

0

-20

0

-10

0

-50

-2

0

-10

10

2

0

50

1

00

2

00

50

0

20

20

1

5.1

2

15.2

2

15

.39

1

5.6

4

15

.96

1

6.3

7

1

5.0

1

14.9

9

14

.97

1

4.9

7

14

.97

1

4.9

7

20

35

1

5.4

3

15.7

1

16

.22

1

6.9

7

17

.93

1

9.1

6

1

5.0

9

15.0

2

14

.98

1

4.9

8

14

.97

1

4.9

7

*No

te-t

he

re is v

ery

min

or

ch

an

ge in

SO

2 c

once

ntr

atio

n (

less t

ha

n 2

.0 µ

g/m

3 )

fro

m y

ear

202

0 to

20

35

.

391

Figure 2: CO distribution from Centre line of the road

Figure 3: NOx distribution from Centre line of the road

0.00

50.00

100.00

150.00

200.00

250.00

300.00

350.00

400.00

450.00

500.00

-500 -400 -300 -200 -100 0 100 200 300 400 500

CO Concentration (mg/m3)

2020

2025

2030

2035

0.00

50.00

100.00

150.00

200.00

-500 -400 -300 -200 -100 0 100 200 300 400 500

NOx Concentration (µg/m3)

2020

2025

2030

2035

392

Figure 4: PM2.5 distribution from Centre line of the road

Figure 5: PM10 distribution from Centre line of the road

15.00

17.00

19.00

21.00

23.00

25.00

27.00

29.00

31.00

33.00

-500 -400 -300 -200 -100 0 100 200 300 400 500

PM2.5 Concentration (µg/m3)

2020

2025

2030

2035

40.00

42.00

44.00

46.00

48.00

50.00

52.00

54.00

56.00

58.00

60.00

-600 -400 -200 0 200 400 600

PM10 Concentration (µg/m3)

2020

2025

2030

2035

393

Figure 6: SO2 distribution from Centre line of the road

14.00

15.00

16.00

17.00

18.00

19.00

20.00

-500 -400 -300 -200 -100 0 100 200 300 400 500

SO2 Concentration (µg/m3)

2020

2035

394

12. In addition, the spatial distribution of hourly average predicted CO, PM2.5 and PM10 concentrations have been plotted in figures 7,8, 9, 10 and 11 respectively which shows that pollutant concentrations is decreasing when goes away from the kerb side.

Figure 7: Spatial Distribution of CO (2020-2035)

Spatial Distribution of CO for year 2020

Spatial Distribution of CO for year 2025

Spatial Distribution of CO for year 2030

395

Spatial Distribution of CO for year 2035

Figure 8: Spatial Distribution of PM2.5 (2020-2035)

Spatial Distribution of PM2.5 for year 2020

Spatial Distribution of PM2.5 for year 2025

396

Spatial Distribution of PM2.5 for year 2030

Spatial Distribution of PM2.5 for year 2035

Figure 9: Spatial Distribution of PM10 (2020-2035)

Spatial Distribution of PM10 for year 2020

397

Spatial Distribution of PM10 for year 2025

Spatial Distribution of PM10 for year 2030

Spatial Distribution of PM10 for year 2035

Figure 10: Spatial Distribution of NOx (2020-2035)

398

Spatial Distribution of NOx for year 2020

Spatial Distribution of NOx for year 2030

Spatial Distribution of NOx for year 2035

Figure 11: Spatial Distribution of SO2 (2020-2035)

399

Spatial Distribution of SO2 for year 2020

Spatial Distribution of SO2 for year 2035

400

Appendix 8: Guidelines For Plant Management

A. Purpose

To ensure that statutory / regulatory requirements are complied with

To ensure that safeguard measures are taken to avoid / mitigate / minimize environmental impacts

B. Site selection criteria

1. Following criteria are to be met wherever possible for crusher and HMP:

500 m away from settlement, school, hospital on downwind directions

1 km from any archaeological site

1 km from ecologically sensitive areas i.e. forest, national park, sanctuary etc.

500 m from rivers, streams and lakes

500 m from ponds

200 m from State and National Highway boundary

away from agricultural land

preference to barren land

2. Concrete batching plant should be located at least 500 m from the settlement, preferably on leeward side, whenever possible. 3. The format for submission of details to the Engineer during finalisation of plant site is given as follows (Site identification for Plants). C. Statutory Requirements

Obtaining Consent-for-Establishment (CFE) under Air and Water Acts from the State Pollution Control Board (SPCB) before start of installation

Obtaining Consent-for-Operation (CFO) under Air and Water Acts from the State Pollution Control Board (SPCB) before start of commissioning and trial run

Complying with the terms and conditions laid down in the CFE and CFO, which generally include providing metallic road inside plant campus for movement of vehicles, plantation, periodic (monthly) pollution monitoring i.e. ambient air, noise and stack emission

The suspended particulate matter contribution value at a distance of 40 m from a controlled isolated as well as from a unit located in a cluster should be

less than 600 g/m3 or as shall be prescribed by SPCB.

Obtain certificates from manufacturer for Type Approval and Conformity of Production for Diesel Generator (DG) set/s.

For DG sets of capacity up to 1000 kVA, the noise level at 1 m from the enclosure surface shall not exceed 75 dB (A).

D. Pollution control measures

Dust control measures in stone crusher plant i.e. water sprinkling at primary crusher and secondary crusher, conveyor & return belts, covered conveyor system, chute at outfall of aggregates, cyclone separator, wind braking wall etc.

For HMP, ensure adequate stack height as stipulated in CFE, install emission control devices such as bag house filters, cyclone separators, water scrubbers etc., as attached with the plant by the manufacturer or stipulated in CFE.

401

Prefer bulk bitumen storage with mechanized handling facilities that storage in drums with manual operation at HMP to prevent / minimize bitumen spillage and thereby contaminating soil and ground water.

Impervious platform for storage of bituminous and other liquid hazardous chemical

Bag house filter / multi-cone cyclone for emission control. For bag house, cartridge filters reported to be more efficient than fabric filters

Pollution control measures for Diesel Generator (DG) set i.e. stack height, acoustic enclosure etc.

Greenbelt along the periphery of plant site.

SITE IDENTIFICATION FOR PLANTS

Construction Stage Report: One Time Date: Installed Capacity (tph): Location of Plant (Ch. & offset):

Sl. No.

Item / Requirement Details as per Actual

1 Predominant wind direction

2 Size and area of the proposed plant site (m xm & Sq.m)

3 Present land use (barren or fallow land having no prominent vegetation should be preferred)

4 No dwelling units within 500 m from the plant boundary in downwind direction

5 Distance of nearest boundary of State Highways and National Highways (should be at least 200 m from the plant boundary)

6 Sensitive areas such as religious places, schools/educational institutions, reserved / protected forest, sanctuary etc. within 1 km (should be nil)

7 River/Stream/Lake within 500 m and ponds within 500 m

8 No other trees of girth>0.3m present and will be affected (no tree should be affected)

9 Width of Haul road (m)

10 Total Length of Haul Road (km)

11 Length of non-metal Haul Road (km) (should be as minimum as possible)

Documents to be attached: Site plan showing wind direction, haul road and other environmental features. Certified that the furnished information is correct and all relevant information as required is attached. Contractor:

402

Appendix 9: Guidelines for Camp Site Management

A. Purpose

1. Campsite of a contractor represents the single potentially most polluting location during implementation of any road project. Air pollution may be caused by emissions from Crushers, Hot-Mix, and Concrete Batching Plants. Water pollution may be caused by discharge of sediment, oil & grease, and organics laden run-off from these plants and their ancillary facilities as well as workshops, residential quarters for the labor. Land may be polluted due to indiscriminate disposal of domestic waste or (accidental) release of hazardous solids from storage areas. 2. While the installation and operation of Crushers and Hot-Mix Plants are regulated by the respective Pollution Control Boards, the other sources described above usually do not appear to be causes of significant concern. Items to be considered for labor camps are mentioned briefly in Clause 105.2 (as part of 105: Scope of Work) of the Ministry of Road Transport and Highways (MoRTH) publication: Specifications for Road and Bridge Works. Some specific requirements for labor accommodation and facilities are to be met by the Contractor in line with Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996. Currently, there is no one-point guidance regarding the environmental management aspects of the Contractor’s campsite. This guideline on Campsites is designed to fill this gap. B. Scope

3. This guideline covers the Contractors’ camp sites – whether used by in-house crew or by any sub-contractors’ crew. It covers siting, operation, maintenance, repair and dismantling procedures for facilities for labor employed on project (and ancillary) activities as well as equipment and vehicles. It does not include siting, operation, maintenance, repair and dismantling of major plants – Hot-mix Plant, Concrete Batching Plant, Crusher or Wet Mix Macadam Plant.

1. Siting, Establishing, Operation and Closure of Construction Camp

a. Potential Environmental Impacts

4. Construction camps require large areas for siting facilities like major plants, storage areas for material, residential accommodation for construction labor and supervisors, and offices. Removal of topsoil and vegetation from the land to be utilized for camps is the first direct impact of any such establishment. In addition, local drainage may be impaired if proper drainage is not effected by grading. Other impacts may include damage to ecologically important flora and fauna, if campsites are located close to such areas. Water pollution because of discharge of sediment, fuel and chemicals is also a possibility. Pollution of land due to indiscriminate disposal of construction wastes including scarified pavement, concrete and even substantial quantities of domestic wastes from residential areas can also be potentially disastrous, especially if the site is reverted to its original use after the project (mostly agriculture).

b. Mitigation Measures

2. Siting of Construction Camps 5. The following guidelines will assist the Contractor to avoid any environmental issues while siting construction camps:

403

Maintain a distance of at least 1 km from boundaries of designated Reserved Forests, Sanctuary or National Park area for locating any temporary or permanent camps.

Maintain 500m from river, stream and lake and from ponds

Maintain 200 m from the boundary of state and national highways

Locate facilities in areas not affected by flooding and clear of any natural or storm water courses.

Locate campsites in the (most prevalent) downwind direction of nearest village(s). The boundary of the campsite should be at least 500m from the nearest habitation so that the incoming labor does not stress the existing local civic facilities.

The ground should have gentle slope to allow free drainage of the site.

Recorded consultations should be held with residents of the nearest settlement and/or their representatives to understand and incorporate where possible, what they would like to see within their locality.

3. Establishment, Operation, and Closure of Camps

The facilities within the camp site should be laid out so that the separation distances suggested in other guidelines are maintained. A notional lay-out of the facilities except the major plants is included in this guideline.

Topsoil from the area of the plant shall be stored separately for the duration of the operation of the camp and protected from being washed away, unless agreed otherwise in writing with the owner. If stored, it will be returned on to its original location at the time of closure of the site.

The Contractor shall prepare, make widely available (especially to staff responsible for water and material management), and implement a Storm water Management Plan (SWMP) for (all) the site(s) following approval of the same by the Engineer. .

The Contractor shall prepare an Emergency and Spill Response Plan as per the requirements of Appendix 1 to Clause 501 of Specifications for Road and Bridge Works to cover the spillage of bitumen and/or chemicals like retarders, curing compounds, etc.

The Contractor shall prepare a Waste Management Plan describing the types and quantities that are likely to be generated from within the camp site, with the period and duration during the construction schedule; methods to be adopted to minimize these; methods of removal, treatment and (on-site or off-site) disposal for each type; as well as location of final disposal site, if any.

The Contractor shall provide safe ingress and egress for vehicles from the site and public roads and shall not impact existing through traffic.

Water tankers with sprayers must be available at the camp site at all times to prevent dust generation.

In case of stockpiles of stored material rising higher than wind-breaking perimeter fencing provided, sprinklers shall be available on site to prevent dusting from the piles during windy days.

On completion of works, the Contractor shall restore the site to the condition it was in before the establishment of the campsite, unless agreed otherwise in writing with the owner(s) of the site(s). If such a written agreement has been made, the Contractor shall hand over the site to the owner(s) in accordance with such an agreement.

Construction waste disposal should be disposed only at landfill facilities which are selected, designed, constructed and operated to ensure environmentally safe disposal, and these facilities have to be approved by the regulators.

404

4. Equipment and Vehicle-related issues

a. Potential Environmental Impacts 6. The maintenance and repair of equipment and vehicles in Contractor’s camp are activities that can have significant adverse impacts if not carried out properly. The concern mainly arises from discharge of wash water contaminated with oil and grease, whether from washing of vehicles or degreasing of equipment and vehicle parts. Vehicle washing, especially dirt from tires, also gives rise to sediment-laden run-off. No such discharges should be directly allowed into surface water bodies since they can be harmful to aquatic species.

b. Mitigation Measures

i. Vehicles

All vehicles used by the Contractor must have copies of currently valid Pollution Under Control Certificates displayed as per the requirement of the Motor Vehicles Department for the duration of the Contract.

All vehicles and equipment will be fitted with silencers and/or mufflers which will be serviced regularly to maintain them in good working condition and conforming to the standard of 75dB (A) at 1m from surface of enclosure.

ii. Workshop and Maintenance areas

These areas must have impervious flooring to prevent seepage of any leaked oil & grease into the ground. The area should be covered with a roof to prevent the entry of rainwater.

The flooring shall be sloped to from both directions to one corner where an oil-and-grease trap with sufficient capacity should be installed. All discharges from the workshop area must pass through the trap to remove the floating oil and grease before entering the drainage system of the site. The trap should be designed to provide a hydraulic residence time of about 20 minutes for the peak hourly discharge anticipated from the area (as per following figure).

Alternatively, degreasing can also be carried out using mechanical spray type degreaser, with complete recycle using an enclosure with nozzles and two sieves, coarse above and fine below, may be used as shown in the adjacent photograph. This arrangement will require some initial investment and running cost for the pump, but the payback period, in terms of the use of diesel, under Indian conditions, has been reported to be less than 1 year.

405

Figure 1: Workshop Area Pollution Control

All the waste oil collected, from skimming of the oil trap as well as from the drip pans, or the mechanical degreaser shall be stored in accordance with the Environment Protection (Storage and Disposal of Hazardous Wastes) Rules, 1989. For this purpose, metallic drums should be used. These should be stored separately in sheds, preferably bunded. The advantage of this arrangement is that it allows for accurate accounting in case the waste material is sold to oil waste recyclers or other users like brick-kiln owners who can burn such inferior fuel.

Slope of the Workshop area floor

O&G

Deta

ilTo drainage system for the site

406

A separate vehicle washing ramp shall be constructed adjacent to the workshop for washing vehicles, including truck mounted concrete mixers, if any, after each day’s construction is over, or as required. This ramp should have an impervious bottom and it should be sloped so that it drains into a separate chamber to remove the sediment from the wash water before discharge. The chamber should allow for a hydraulic residence time of about 10 minutes for discharge associated with the washing of each truck. Following figure 2 shows an outline sketch for a sedimentation chamber.

Figure 2: Sedimentation Chamber for vehicle washing ramp discharge

5. Facilities for Labour

a. Potential Environmental Impacts

7. The sudden arrival and relatively longer duration of stay of construction crew can cause substantial strain on the existing infrastructure facilities like water supply, sanitation and medical care, especially in rural areas. Pollution from domestic wastes can affect local sources of water supply and may harm the crew themselves as well as local residents.

407

Improper sanitation and inadequate health care also potential bottlenecks that the Contractor can eliminate with relatively little effort.

b. Mitigation Measures

8. It should be emphasized that the Indian Law requires that the Contractor provide several facilities to for the workers as per Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996. Some of the provisions described herein are more stringent to act as benchmark for improved environmental performance of road projects:

The contractor shall provide free-of-charge temporary accommodation to all the labour employed for the project. The accommodation includes separate cooking place, bathing, washing and lavatory facilities. At least, one toilet will be provided for every 35 people and one urinal will be provided for every 20 persons. More toilets and/or urinals may have to be provided if the Engineer decides that these numbers are insufficient. In case female labourers are employed, separate toilet and urinals will be provided in locations clearly marked “Ladies Toilets” in a language understood by most labourers.

The contractor shall ensure the supply of wholesome water for all the labour, including those employed by any other agency working for the contractor. These locations will be marked “Drinking Water” in the language most commonly understood among the labour. In hot season, the contractor shall make efforts to ensure supply of cool water. No water point shall be located within 15 m of any washing place, urinal, or latrine.

The contractor shall ensure that adequate cooking fuel, preferably kerosene or LPG, is available on-site. The contractor will ensure that wood/ coal are not used as fuel on the site. Workers need to be made aware of this restriction. In cases where more than 250 labours are employed, canteen facility should be provided by the Contractor.

A crèche must be provided in each campsite where more than 50 female labourers are employed, whether directly or indirectly, for the project or its ancillary activities.

Contractor must provide adequate facilities for first-aid treatment at the campsite. A doctor / ambulance should be available on call for the duration of project implementation.

The contractor shall obtain the approval of the Engineer for these facilities within 30 days of mobilization.

408

TYPICAL DRAWING OF WORKERS’ CAMP SANITARY FACILITY

409

Layout of a Construction camp

Vehicle Washing Area / Ramp

Workshop

Cement and Spares Store

Security & Weigh Bridge

Office Block

Family Quarters

Rooms for Men

Rooms for Women

Ladies Toilet

Washing area

Gents Toilet

PLANTS

(Concre

te

Batchin

g, etc.)

and

MATERI

AL

Canteen / Mess

LEGEND: Septic Tank + Soak Pit Water Source Oil & Grease Separator

Gate

Exis

tin

g

Slo

pe

410

Appendix 10: Guidelines for Waste (Debris and Spoils) Disposal and Management

A Waste disposal and management plan will be prepared by the contractor before start of construction works and submitted to CKICP, PIU-ADB and the Construction Supervision Consultant for their review and approval. The management plan will follow the guidelines as given below:

(i) The debris disposal site should be identified which are preferably barren or low-lying areas away from settlements.

(ii) Contractor to prepare spoil disposal plan which identifies spoil disposal sites including volume of spoils that can be accommodated by each site, and agreed restoration measures (e.g. revegetation, compaction, provision of drainage, etc.) and timeline

(iii) Prior concurrence will be taken from concerned Government Authorities or land owner for selected disposal sites and restoration measures

(iv) Due care should be taken during site clearance and disposal of debris so that public/ private properties are not damaged or affected, no traffic are interrupted.

(v) All efforts should be made to use debris in road construction or any other public utilities to minimize spoils and debris

(vi) If immediate disposal is not possible, the debris and spoils should be stored at site ensuring that existing water bodies and drains within or adjacent to the site are kept safe and free and no blocking of drains occurs until ready to be transported to final spoils disposal site

(vii) All dust prone material should be transported in a covered truck.

(viii) All liquid waste like oils and paint waste should be stored at identified locations and preferably on a cemented floor. Provision of spill collection pit will be made in the floor to collect the spilled oil or paint. These should be sold off to authorized recyclers.

(ix) All domestic waste generated at construction camp preferably be composted in portable mechanized composter. The composted material will be used as manure. In case composting is not feasible, the material will either be disposed off though municipal waste disposal system or disposed of through land burial. The dump site must be covered up with at least six inch thick layer of soil.

(x) Only appropriately design and compliant landfills will be used for disposing waste

(xi) All efforts should be made that no chemical/ oily waste spill over to ground or water bodies.

(xii) All precautions should be followed for emergency preparedness and occupational health & safety during construction and handling wastes and spoils.

(xiii) Provision of fire extinguishers will be made at the storage area

(xiv) Adequate traffic control signals and barriers should be used in case traffic is to be diverted during debris disposal. All efforts should be made to ensure avoidance of traffic jam, which otherwise results in air pollution, noise pollution and inconveniences to the road users and adjacent communities.

(xv) Hazardous waste and chemicals should be stored in a dedicated storage area that has: 1) weather protection, 2) solid impermeable surface and drainage to treatment system, 3) security fence/lock, 4) primary and secondary containment with 110% volume for liquids.

(xvi) Domestic waste shall only be disposed of at the approved, appropriately designed, compliant waste management facility (landfill). Land burial of waste shall not be permitted.

Records: The following records will be maintained

Generation and disposal quantity with location of disposal

Recyclables waste generation and disposal

411

Domestic waste disposal locations details

Reporting:

The waste generation and disposal details will form part of quarterly report to CKICP, PIU-ADB

Responsibility:

Prime Responsibility: Contractor will be responsible for waste management and reporting

Supervisory Responsibility: Construction Supervision Consultant (CSC) will check the contractor’s adherence to the above guidelines

412

Appendix 11: Guidelines for Borrow Area Management

A. Purpose 1. Borrow areas are generally required to provide material for road construction sites, can have significant adverse environmental effects, especially on ecologically sensitive areas. Borrow areas can become environmental hotspots and can significantly affect the visual appearance of an area. Special mitigation and management measures are often required to avoid or minimise the environmental and social impacts of borrow areas.

B. Scope 2. These guidelines for borrow areas cover:

• statutory approvals • environmental and social impacts of borrow areas • selection of borrow areas • operation of borrow areas • rehabilitation of borrow areas

3. The guidelines seek to ensure that Contractors:

• comply with the regulatory requirements in force at the time • reasonably manage any impacts • reinstate and rehabilitate the land appropriately • consult with affected communities

C. Impacts

4. Some of the potential impacts of borrow areas are:

• trucks transporting materials to the site causing air pollution, and noise and vibrations

• ponds of stagnant water forming in excavated areas giving rise to the breeding of mosquitoes and the spreading of malaria and other mosquito-borne diseases

• natural beauty of the landscape being affected by excavations and the removal of vegetation

• natural drainage systems in the area being affected by excavations • agriculture land and productive soils being lost, especially in paddy field areas

5. Borrow areas are not generally specified in Contract documents but rather it is generally the responsibility of Contractors to identify borrow areas and obtain the necessary consent from land owner and approval from SC. 6. In IRC: 10 and Clause 305.2.2.2 of MoRTH Specification, exclusive guideline has been given for borrow areas located alongside the road and only some of the requirements have been indicated for borrow areas located outside the road land. Following guideline is proposed to supplement the existing stipulation in IRC:10 and Clause 305.2.2.2 of MoRTH Specification for Roads and Bridge Works:

D. Location • Identify areas having present land use as barren land, riverside land.

Otherwise, un-irrigated agriculture land or land without vegetation and tree cover;

• Prefer borrow areas on bed of irrigation water storage tank; • Prefer areas of highland with respect to surroundings;

413

• Avoid locating borrow area close to any road (maintain atleast 30 m distance from ROW and 10 m from toe of embankment, whichever is higher);

• Should be at least 1.5 km away from inhabited areas; • Maintain a distance of about 1.5km from ecologically sensitive area i.e.

Reserve Forest, Protected Forest, Sanctuary, wetland etc.; • Maintain a distance of about 1.5 km from school, hospital and any

archaeological sites; • Having adequate approach road with minimum length of earthen road; • Ensure that unsuitable soft rock is not prominent within the proposed depth of

excavation which will render rehabilitation difficult; • Depth of excavation should be decided based on natural ground level of the

land and the surroundings, and rehabilitation plan. In case higher depth of excavation is agreed with backfilling by unsuitable excavated soil (from roadway), then filling should be adequately compacted except topsoil which is to be spread on topmost layer (for at least 20cm thick).

E. Operation

• Controlled operation as per agreed / approved plan; • Preservation of topsoil at designated areas e.g. corners of the area etc.; • Maintain necessary buffer zone in all directions and go for vertical cut within

this area. Final cut slope should be maintained within the buffer zone; • Step-wise excavation if borrow area is located on inclined area having more

than 2% slope; • Restricting excavation up to 2m for each stages of operation if allowed depth

is more; • Avoid cutting of any tree of girth size > 30cm2. if any tree cutting is inevitable,

prior permission (written) from the competent authority should be taken and compensatory plantation has to be raised.

F. Rehabilitation

• Prior approval of Rehabilitation Plan considering terrain, land use and local need;

• Restricting operation as agreed by landowner and approved by the Engineer; • Rehabilitation within agreed timeframe and before taking over; • Integrate debris disposal and borrow area redevelopment.

G. Management Procedure

7. The important aspects of this procedure are:

• The first and foremost thing is to have tentative estimate of borrow material requirement chainage-wise. For this, Bill of Quantities(BOQ) quantity for earth work, which is given as total quantity for the entire package/milestone, has to be distributed chainage-wise. The requirement of borrow material chainage-wise then has to be estimated based on the suitability of roadway excavation material for reuse and BOQ.

• Contractor to site borrow areas fulfilling environmental requirements and obtaining one time approval of the Engineer both on quality as well as environmental consideration thereby integrating environmental safeguard measures into day-to-day activities;

• Contractor to submit environmental information in prescribed format for obtaining Engineer’s approval, as given in the following format (Borrow Area

2 Plant having girth size more than 30cm is considered as tree.

414

Identification). The format has been so designed that it stipulates the requirements as well as what is actual for each borrow areas and could be easily understood by any person, whoever in-charge of identifying borrow areas;

• Contractor to submit Borrow Area Layout Plan as attachment to the format showing the land use of the proposed and surrounding area along with the presence of other environmental features such as water bodies, forests, settlement, temple and any sensitive receptor i.e. health and educational institution, roads etc. within a radius of 1.5km area from the boundary of the borrow area;

• Contractor to prepare and submit Block Contour Map of each borrow area (especially which are located close to road and on undulating terrain) for deciding on operation and redevelopment plan;

• Contractor to prepare Operation Plan and submit as attachment to the format including cross sections on both directions (x,y) mentioning natural ground level, depth of topsoil (if any), total depth of excavation, cut side slope and bed slope;

• Contractor to prepare Rehabilitation/ Restoration and submit as attachment to the format include cross sections on both directions (x,y) mentioning natural ground level, excavated profile, finished profile after rehabilitation, volume of spoils that can be accommodated etc.;

• Contractor to maintain Borrow Material Register; • Periodic joint inspections of each borrow area until rehabilitation is complete

as agreed and approved. • The checklist for periodic inspection is given in this appendix.

415

Borrow Areas Identification

Construction Stage Report: One Time Date:

Location of Borrow Area (Ch. & Offset): Revenue Survey

No.:

Sl. No.

Item / Requirement Details as per Actual (to be filled by Contractor &

checked by Engineer)

1 Date of Borrow Area planned to be operational

2 Current Land use (preference to barren land, riverside land, otherwise, un-irrigated agriculture land or land without tree cover)

3 Size (Sq.m) and area (m x m) of Borrow Area

4 Proposed maximum depth of pit in m (IRC 10 & Clause 305.2.2 of MoRTH Spec.)

5 Details of riverside borrow area (inner edge should not be less than 10m from the toe of the bank and bottom of pit should not cut the imaginary line of 1:4 from embankment top)

6 Borrow area in cultivable land (should be avoided or restricted to total depth of 45cm including preservation of 15cm topsoil)

7 Quantity Available (Cum)

8 Quantity of top soil to be removed (Sq.m & depth in cm)

9 Details of preservation (storage) and management (re-use / re-laid) of top soil

10 Width of Haul road (m)

11 Total Length of Haul Road (km)

12 Length of Non-metal Haul Road (should be as minimum as possible)

13 No of settlements within 200 m of Non-metal Haul Road (should be as minimum as possible)

14 Distance from settlement (should be minimum 1500 m)

15 Should be away from water bodies. Give details of water bodies within 250 m.

16 Details of water sources for dust suppression

17 Quantity of water required for dust suppression i.e. sprinkling at borrow area and on haul road (Cum)

18 Availability of water required for dust suppression (Cum)

19 Details of ecologically sensitive area i.e. Reserved Forest, Protected Forest, Sanctuary etc. within 1500m (should be nil)

20 Details of settlements/residential areas school, hospital and any archaeological sites within 1500m (should be nil)

21 Distance from nearby road embankment, fence line / boundary (should be minimum 30m from ROW and 10m from toe of embankment, whichever is higher)

22 No of Trees with girth more than 0.3 m (No tree should be affected)

Documents to be attached:

416

1) Site plan and layout plan of borrow area; 2) Proposed borrow area operation and redevelopment plan; 3) Written consent from competent authority for use of water for dust

suppression 4) Written consent of landowner on agreed operation and redevelopment plan

Certified that the furnished information is correct and all relevant information as required is attached Contractor’s Representative:

417

Checklist For Monitoring Borrow Area Operation & Management

Attributes Requirements

Access road Only approved access road shall be used

Top soil preservation

Top soil, if any, shall be stripped and stored at corners of the area before start of excavation for material collection;

Top soil should be re-used / re-laid as per agreed plan

Depth of excavation For cultivable (agriculture) land, total depth of excavation should be limited to 45 cm including top 15 cm for top soil preservation;

For riverside borrow area, the depth of excavation shall be so regulated that the inner edge of any borrow pit should not be less than 10m from the toe of the bank and bottom of pit should not cut the imaginary line of 1:4 from embankment top;

If borrow area is located within 1500 m of towns or villages, they should not exceed 30 cm in depth and should be properly drained;

Borrow areas close to ROW should be rectangular in shape with one side parallel to center line of the road and depth should be so regulated that it should not cut an imaginary line having slope of 1 in 4 projected from the edge of the final section of the embankment.

Damage to surrounding land

Movement of man & machinery should be regulated to avoid damage to surrounding land.

Drainage control Borrow areas must have adequate drainage provisions to prevent soil erosion

The surface drainage in and around the area should be connected to the natural drainage;

No water stagnation shall occur.

Dust suppression Water should be sprayed on kutcha (earthen) haul road twice in a day or as may be required to avoid dust generation during transportation of material;

Depending on moisture content, 0.5 to 1.5% water may be added to excavated soil before loading during dry weather to avoid fugitive dust emission.

Covering material transport vehicle

Material transport vehicle shall be provided with tarpaulin cover

Personal Protective Equipment

Workers should be provided with helmet, gumboot and air mask and their use should be strictly enforced.

Redevelopment The area should be rehabilitated within agreed timeframe on completion of material collection as per agreed rehabilitation plan.

418

Appendix 12: Guidelines for Quarry Area Management

A. Purpose

1. Quarries generally required to provide material for road construction sites, can have significant adverse environmental effects, especially on ecologically sensitive areas. Quarries can become environmental hotspots and can significantly affect the visual appearance of an area. Special mitigation and management measures are often required to avoid or minimise the environmental and social impacts of quarries.

B. Scope

2. These guidelines for quarries cover: • statutory approvals • environmental and social impacts of quarries • selection of quarries • operation of quarries • rehabilitation of quarries

3. The guidelines seek to ensure that Contractors3:

• comply with the regulatory requirements in force at the time • reasonably manage any impacts • reinstate and rehabilitate the land appropriately • consult with affected communities

C. Impacts

4. Some of the potential impacts of quarries are: • rock blasting causing air pollution, and noise and vibrations • trucks transporting materials to the site causing air pollution, and noise and

vibrations • ponds of stagnant water forming in excavated areas giving rise to the

breeding of mosquitoes and the spreading of malaria and other mosquito-borne diseases

• natural beauty of the landscape being affected by excavations and the removal of vegetation

• natural drainage systems in the area being affected by excavations

5. The procedure for identification and finalization of quarry site/s shall be as given below:

• Estimating the quantity of quarry material to be collected from each quarry area

• Only licensed quarry will be used • New quarry will be at least 1.5 km away from the settlement, forest and

other ecologically sensitive areas • Away from water body • Contractor shall identify alternative quarry sites along the whole corridor

based on required quantity and environmental consideration as given in the following prescribed format of Quarry source identification.

• Contractor shall submit to the Engineer the detailed information / documents as prescribed in the format;

3 The EMP stipulations will be applicable even if contract use existing licensed quarry. In case contractor use

the existing licensed quarry a copy of the quarry license and lease / sub-lease agreement should be submitted to the Project Proponent. Contractor shall submit a plan delineating how he shall comply with requirements stipulated in this plan and elsewhere in the EMP on quarrying activity.

419

• Engineer shall undertake site inspection of alternate quarry sites and convey to Contractor on accepting a particular quarry site on environmental consideration;

• Contractor shall then take apply and obtain Quarry Lease Deed / License from the Government of Tamil Nadu Department of Mines and Geology and Mining and provide copy of the same to the Engineer prior to operation;

• Contractor shall estimate water requirement for dust suppression at quarry sites during operation and for water spraying on kutcha (non-metal) haul road and ensure availability water by identifying sources and obtaining necessary permission;

• Contractor shall prepare quarry sites operation and redevelopment plan considering surrounding land uses, local needs and agreement with the landowner;

• Only licensed blaster i.e. short-firer certificate holder will be responsible for quarry blasting

• Permits for transportation, storage and use of explosive, as will be required, shall be obtained from the Controller of Explosive;

• Whenever so advised by the Engineer, controlled blasting e.g. using less charge, restricting depth and dia or drill holes, cut-off blasting etc., shall be undertaken.

• Quarry operation will be undertaken in stages with adequate benching

6. The procedure for environmentally sound operation and management of quarry sites is given below:

• Estimating the quantity of quarry material to be collected from each quarry area;

• Demarcating the entire quarry area by fencing and putting red-flag poles; • Providing adequate metallic access road; • Preserving topsoil from the quarry compound, if any, by stripping and

stacking aside separately at corners; • Carrying out blasting as per agreed operational plan complying with the

requirements of MoRTH Specification (Clause 302 & 303) and Ministry of Environment & Forests and Climate Change (MoEFCC) as given below;

• Maintaining a Quarry Material Collection Register on daily material collection for each of the quarry area, which shall be produced to Engineer’s representative as and when requested;

• Redeveloping the area within 2 months (or as will be agreed upon) of completion of quarry material collection;

D. Use of Explosive for Blasting 1. General

7. Blasting shall be carried out in a manner that completes the excavation to the lines indicated in drawings, with the least disturbance to adjacent material. It shall be done only with the written permission of the Engineer. All the statutory laws, regulations, rules, etc., pertaining to the acquisition, transport, storage, handling and use of explosives shall be strictly followed. 8. The Contractor may adopt any method or methods of blasting consistent with the safety and job requirements. Prior to starting any phase of the operation the Contractor shall provide information describing pertinent blasting procedures, dimension and notes. 9. The magazine for the storage of explosives shall be built as per national / international standards and located at the approved site. No unauthorized person shall be

420

admitted into the magazine which when not in use shall be kept securely locked. No matches or inflammable material shall be allowed in the magazine. The magazine shall have an effective lightning conductor. The following shall be displayed in the lobby of the magazine:

• A copy of the relevant rules regarding safe storage in English, Portuguese and in the language with which the workers concerned are familiar.

• A statement of up-to-date stock in the magazine. • A certificate showing the last date of testing of the lightning conductor. • A notice that smoking is strictly prohibited.

10. All explosives shall be stored in a secure manner in compliance with all laws and ordinances, and all such storage places shall be clearly marked. Where no local laws or ordinances apply, storage shall be provided to the satisfaction of the Engineer and in general not closer than 300 m from the road or from any building or camping area or place of human occupancy. In addition to these, the Contractor shall also observe the following instructions and any further additional instructions which may be given by the Engineer and shall be responsible for damage to property and any accident which may occur to workmen or the public on account of any operations connected with the storage, handling or use of explosives and blasting. The Engineer shall frequently check the Contractor’s compliance with these precautions.

2. Materials, Tools and Equipment

11. All the materials, tools and equipment used for blasting operations shall be of approved type. The Engineer may specify the type of explosives to be allowed in special cases. The fuse to be used in wet locations shall be sufficiently water-resistant as to be unaffected when immersed in water for 30 minutes. The rate of burning of the fuse shall be uniform and definitely known to permit such a length being cut as will permit sufficient time to the firer to reach safety before explosion takes place. Detonators shall be capable of giving effective blasting of the explosives. The blasting powder, explosives, detonators, fuses, etc., shall be fresh and not damaged due to dampness, moisture or any other cause. They shall be inspected before use and damaged articles shall be discarded totally and removed from the site immediately.

3. Personnel

12. The blasting operation shall remain in the charge of competent and experienced supervisor and workmen who are thoroughly acquainted with the details of handling explosives and blasting operations.

4. Blasting Operations

13. The blasting shall be carried out during fixed hours of the day preferably during the mid-day luncheon hour or at the close of the work as ordered in writing by the Engineer. The hours shall be made known to the people in the vicinity. All the charges shall be prepared by the man in charge only. 14. The Contractor shall notify each public utility company having structures in proximity to the site of the work of his intention to use explosives. Such notice shall be given sufficiently in advance to enable the companies to take such steps as they may deem necessary to protect their property from injury. In advance of any blasting work within 50 m of any railway track or structures, the Contractor shall notify the concerned Railway Authority of the location, date, time and approximate duration of such blasting operations.

421

15. Red danger flags shall be displayed prominently in all directions during the blasting operations. The flags shall be planted 200m and 500m from the blasting site in all directions for blasting at work site and quarry, respectively. People, except those who actually light the fuse, shall be prohibited from entering this area, and all persons including workmen shall be excluded from the flagged area at least 10 minutes before the firing, a warning siren being sounded for the purpose. 16. The charge holes shall be drilled to required depths and at suitable places. Blasting should be as light as possible consistent with thorough breakage of the material necessary for economic loading and hauling. Any method of blasting which leads to overshooting shall be discontinued. 17. When blasting is done with powder, the fuse cut to the required length shall be inserted into the hole and the powder dropped in. The powder shall be gently tamped with copper rods with rounded ends. The explosive powder shall then be covered with tamping material which shall be tamped lightly but firmly. 18. When blasting is done with dynamite and other high explosives, dynamite cartridges shall be prepared by inserting the square cut end of a fuse into the detonator and finishing it with nippers at the open end, the detonator gently pushed into the primer leaving 1/3rd of the copper tube exposed outside. The paper of the cartridge shall then be closed up and securely bound with wire or twine. The primer shall be housed into the explosive. Boreholes shall be such size that the cartridge can easily go down. The holes shall be cleared of all debris and explosive inserted. The space of about 200 mm above the charge shall then be gently filled with dry clay, pressed home and the rest of the tamping formed of any convenient material gently packed with a wooden rammer. 19. At a time, not more than 10 such charges will be prepared and fired. The man in charge shall blow a siren in a recognised manner for cautioning the people. All the people shall then be required to move to safe distances. The charges shall be lighted by the man-in-charge only. The man-in-charge shall count the number of explosions. He shall satisfy himself that all the charges have been exploded before allowing the workmen to go back to the blasting site.

5. Misfire

20. In case of misfire, the following procedure shall be observed:

Sufficient time shall be allowed to account for the delayed blast. The man-in-charge shall inspect all the charges and determine the missed charge.

If it is the blasting powder charge, it shall be completely flooded with water. A new hole shall be drilled at about 450 mm from the old hole and fired. This should blast the old charge. Should it not blast the old charge, the procedure shall be repeated till the old charge is blasted.

In case of charges of gelignite, dynamite, etc., the man-in-charge shall gently remove the tamping and the primer with the detonator. A fresh detonator and primer shall then be used to blast the charge. Alternatively, the hole may be cleared of 300 mm of tamping and the direction then ascertained by placing a stick in the hole. Another hole may then be drilled 150 mm away and parallel to it. This hole shall then be charged and fired when the misfired hole should explode at the same time. The man-in-charge shall at once report to the Contractor’s office and the Engineer all cases of misfire, the cause of the same and what steps were taken in connection therewith.

422

If a misfire has been found to be due to defective detonator or dynamite, the whole quantity in the box from which defective article was taken must be sent to the authority directed by the Engineer for inspection to ascertain whether all the remaining materials in the box are also defective.

6. Account

21. A careful and day to day account of the explosive shall be maintained by the Contractor in an approved register and manner which shall be open to inspection by the Engineer at all times. 22. During quarry operation, periodic joint inspection should be carried out by the Contractor and Engineer’s representatives. 23. A typical checklist for the same is given here.

423

Quarry Source Identification Construction Stage Report: One Time Date: Supervision Consultant: Contractor: Contract Package: Location of Quarry (Ch. & Offset):

Sl. No. Item / Requirement Details as per Actual

1 Present land use (bare land with no prominent vegetation is preferred)

2 Predominant wind direction

3 Size and area of Quarry (m xm & Sq.m)

4 Quantity Available (Cum)

5 Quantity proposed to be collected (Cum)

6 No of Trees with girth more than 0.3 m

7 No Settlement within 1500 m of Quarry

8 No water body within 1500 m of Quarry

9 Width of Haul road (m)

10 Total Length of Haul Road (km)

11 Length of Non-metal Haul Road (km) (should be as minimum as possible)

12 No of Settlements within 200m of Non-metal Haul Road (should be as minimum as possible)

13 Quantity of water required for dust suppression i.e. sprinkling at borrow area and on non-metal haul road (Cum)

14 Details of Water sources for dust suppression

15 Availability of water required for dust suppression (Cum)

Documents to be attached:

1) Site plan and layout plan of quarry site 2) Proposed quarry site operation and redevelopment plan 3) Written consent / lease agreement with the Department of Mines & Geology 4) Written consent from competent authority for use of water for dust suppression

Certified that the furnished information is correct and all relevant information as required is attached

Contractor’s Representative:

Details to be inspected for Monitoring Quarry Area Operation & Management

Attributes

Requirements

Access road Only approved access road shall be used

Top soil preservation

Top soil, if any, should be stripped and stored at designated area before start of quarry material collection;

Top soil should be re-used / re-laid as per agreed plan

424

Attributes

Requirements

Controlled blasting & safety

Storage of explosive magazine as per threshold quantity with all the safety measures;

Handling of explosive by licensed blaster only;

Use low intensity explosive;

Check unfired explosive, if any, before drilling;

Carryout blasting at lean time only;

Cordoned the area within 500m radius with flagmen having whistle for signaling preparedness;

Using properly designed audio visual signal system i.e. siren and flagmen for blasting;

Keep ready an emergency vehicle near blasting area with first aid facility and with active emergency response system.

Damage to surrounding land

Movement of man & machinery should be regulated to avoid damage to surrounding land.

Drainage control

The surface drainage in and around the area should be connected to the natural drainage;;

Dust control Haul road should be made metallic;

Suitable dust arrester for drilling;

Water spraying at quarry complex, if required.

Covering material transport vehicle

Material transport vehicle should be provided with tail board, and cover

Personal Protective Equipment

Workers shall be provided with helmet, safety shoes, ear muffler and air musk and their use should be strictly enforced.

Redevelopment The area should be redeveloped within two months (or as agreed) on completion of material collection as per agreed plan.

425

Appendix 13: Noise Modeling Details

1. Federal Highway Administration's Traffic Noise Model (FHWA TNM) helps for highway traffic noise prediction and analysis. TNM computes highway traffic noise at nearby receivers. As sources of noise, it includes noise emission levels for the following vehicle types:

Automobiles: all vehicles with two axles and four tires -- primarily designed to carry nine or fewer people (passenger cars, vans) or cargo (vans, light trucks) -- generally with gross vehicle weight less than 4,500 kg (9,900 lb);

Medium trucks: all cargo vehicles with two axles and six tires -- generally with gross vehicle weight between 4,500 kg (9,900 lb) and 12,000 kg (26,400 lb);

Heavy trucks: all cargo vehicles with three or more axles -- generally with gross vehicle weight more than 12,000 kg (26,400 lb);

Buses: all vehicles designed to carry more than nine passengers; and

Motorcycles: all vehicles with two or three tires and an open-air driver / passenger compartment.

2. The procedure for prediction of noise levels involves the following steps: 1. Identification of various receivers 2. Determination of landuse and activities which may be affected by the noise

generated 3. Assemble input parameters 4. Application of the model

3. The description of the components to predict noise level are as follows: a. Receivers: TNM calculates the sound levels at the input receivers. In this

study two type of receivers selected to assess the impacts of moving traffic on surrounding noise level. One, discrete receptor and second, grid receptor.

b. Land uses: Land use along the road is obtained from the topographic drawings. This information provides the range of shielding and absorption factors to be applied at the various receivers.

c. Input Parameters: Traffic volume for the projected period is obtained from the traffic projections. The total number of vehicles passing per hour by type - light, medium and heavy along with their average speed is used for predictions.

d. Average Noise Level: All vehicles produce noise, which is taken as the base, and the cumulative noise at the receiver distance due to the whole traffic is estimated. The average noise level varies depending on the type of vehicle.

e. Application of Model: Equivalent noise levels due to traffic at the receivers are estimated using Federal Highway Noise model. Equivalent Sound Level (TEQ, denoted by the symbol, LAeqT): Ten times the base-10 logarithm of the square of the ratio of time-average, mean-square, instantaneous A-weighted sound pressure, during a stated time interval, T (where T=t2-t1), and the reference mean-square sound pressure of 20 : Pa, the threshold of human hearing, e.g., 1HEQ, denoted by the symbol, LAeq1H, represents the hourly equivalent sound level. LAeqT is related to LAE by the following equation :

LAeqT = LAE - 10*log10(t2-t1)

where LAE = Sound exposure level in dB

426

Sound Exposure Level (SEL, denoted by the symbol, LAE): Over a stated time interval, T (where T=t2-t1), ten times the base-10 logarithm of the ratio of a given time integral of squared instantaneous A-weighted sound pressure, and the product of the reference sound pressure of 20:Pa, the threshold of human hearing, and the reference duration of 1 sec. The time interval, T, must be long enough to include a majority of the sound source’s acoustic energy. As a minimum, this interval should encompass the 10 dB down points. Annual average daily motorized traffic data is given in table 1.

Table 1: Annual average daily motorized traffic data

Year 4W LCV Truck Bus 3W 2W

2020 1963 801 449 1436 316 4323

2025 2964 961 551 1959 379 5894

2030 4236 1124 661 2584 444 7667

2035 5776 1285 774 3282 515 9646

Table 2: Baseline (Equivalent) Noise Levels at monitoring locations in dB (A) along the project road

Equivalent Noise Levels in dB(A)

DAY NIGHT

67.8 58.2

Table 3: Predicted Noise Levels in dB (A) along the project road (without Barrier)

Day

LHS RHS

200 100 50 20 10 10 20 50 100 200

2020 67.8 67.9 68.3 69.7 70.9 70.9 69.7 68.3 67.8 67.8

2025 67.8 67.9 68.5 70.3 71.6 71.6 70.3 68.5 67.9 67.8

2030 67.8 67.9 68.7 70.8 72.3 72.3 70.8 68.6 67.9 67.8

2035 67.8 68.0 68.9 71.3 73.0 73.0 71.3 68.8 67.9 67.8

Night

LHS RHS

200 100 50 20 10 10 20 50 100 200

2020 58.4 59.2 61.7 66.2 68.4 68.4 66.2 61.6 59.0 58.4

2025 58.5 59.5 62.5 67.3 69.6 69.6 67.3 62.4 59.3 58.5

2030 58.6 59.8 63.2 68.3 70.7 70.7 68.3 63.1 59.5 58.6

2035 58.6 60.1 63.9 69.1 71.6 71.6 69.1 63.8 59.8 58.6

Observations

427

4. Predicted noise levels (Leq) near the receivers are found to be marginally higher than desired levels for the respective landuse categories for receptors falling within 50m from road edge. The baseline noise levels(2019) are already higher than the permissible limits of CPCB for different landuse categories for day and night. The predicted levels show increase in noise levels for future years at all receivers considering increase in traffic volume. The incremental noise levels for future years exceeds the allowable limit of 3 dB (A) from the baseline levels. Mitigation measures suggested in EMP should be adopted for the sensitive receptors falling within 50m from road edge of the road corridor.

Figure 1: Noise levels from edge of the road (Day)

Noise dispersion

5. A small road corridor has been selected to develop noise contour for base year as well as future years also. The contour lines are generated by plotting a contour zone within 30 m distance from edge of the road on both side of the road. Due to model limitation, it is not possible to select the whole road corridor in the modelling domain. Therefore, spatial dispersion of noise has been shown with a small stretch of road. Figure 2 to 5 shows noise level contour around a small road corridor for year 2020, 2025, 2030 and 2035 respectively. These predicted results are for peak traffic hours. During non-peak traffic hours, the noise levels are very less compared to noise level for peak traffic hours.

Figure 2: Noise contour for year 2020

67.0

68.0

69.0

70.0

71.0

72.0

73.0

74.0

-300 -200 -100 0 100 200 300

No

ise

Le

ve

ls i

n d

B

Distance from edge of the road, m

2020

2025

2030

2035

428

Figure 3: Noise contour for year 2025

Figure 4: Noise contour for year 2030

Figure 5: Noise contour for year 2035

429

Appendix 14: Details of Participants and Public Consultation attendance list

SH-115 – Public Consultation Meeting

Photos of the FGD at Mariyamman Kovil, Arasur

430

Attendance Sheet

431

Photos of the FGD at Muthumariyamman Kovil Arasur Village

432

Attendance Sheet

Photos of the FGD:

433

Attendance Sheet:

434

Photos of the FGD:

435

Attendance Sheet:

436

437

Photos of the FGD:

Attendance Sheet:

438

Photos of the FGD:

439

Attendance Sheet:

440

441

442

Appendix 15: Indian Standard Drinking Water Specification: IS 2296:1992 and IS 10500:1991

Indian Standard Drinking Water Specification: IS 2296:1992

S. No. Parameter Unit Tolerance Limit as per IS:2296

Class A Class B Class C Class D Class E

1 pH - 6.5-8.5 6.5-8.5 6.5-8.5 6.5-8.5 6.5-8.5

2 Temperature OC - - - - -

3 Turbidity NTU - - - - -

4 Conductivity @25°C µs/cm. - - - 1000 2250

5 Total Suspended Solid

mg/l - - - - -

6 Biological Oxygen Demand (Max.) (at 270C for 3 days)

mg/l 2 3 3 - -

7 Dissolved Oxygen (as O2) Min.

mg/l 6 5 4 4 -

8 Calcium(as Ca) mg/l 80 - - - -

9 Magnesium(as Mg) mg/l 24 - - - -

10 Chloride(as Cl),Max mg/l 250 - - - 600

11 Iron(as Fe),Max mg/l 0.3 - 50 - -

12 Fluoride(as F),Max mg/l 1.5 1.5 1.5 - -

13 Total Dissolved Solid mg/l 500 - 1500 - 2100

14 Total Hardness (as CaCO3)

mg/l 300 - - - -

15 Sulphate (as SO4)Max

mg/l 400 - 400 - 1000

16 Phosphate (as P) mg/l - - - - -

17 Sodium (as Na) mg/l - - - - -

18 Manganese (as Mn) mg/l 0.5 - - - -

19 Total Chromium (as Cr)

mg/l 0.05 0.05 0.05 - -

20 Zinc (as Zn) mg/l 15 - 15 - -

21 Potassium (as K) mg/l - - - - -

22 Nitrate (as NO3),Max mg/l 20 - 50 - -

23 Lead ( as Pb) mg/l 0.1 - 0.1 -

24 Chemical Oxygen Demand (asO2)

mg/l - - - - -

25 Arsenic (as As ) mg/l 0.05 0.2 0.2 -

26 Total Coli Form MPN/100ml

Class A-Drinking water without conventional treatment but after disinfection

Class B-Water for outdoor bathing

Class C-Drinking water with conventional treatment followed by disinfection

Class D-Water for fish culture and wild life propagation

Class E-Water for irrigation, industrial cooling and control waste disposal

Indian Standard Drinking Water Specification: IS 10500:1991

Sl. No.

Substance/ Characteristic Desirable Limit Permissible

limit Remarks

1 Colour, Hazen units, Max 5 25 Extended to 25 if toxic substance are not suspected in absence of alternate sources

2 Odour Unobjectionable a) Test cold and when heated

b) Test at several dilution

3 Taste Agreeable Test to be conducted only after safety has been established

443

Sl. No.

Substance/ Characteristic Desirable Limit Permissible

limit Remarks

4 Turbidity NTU, Max 5 10

5 pH value 6.5 to 8.5 No relaxation

6 Total Hardness (as CaCO3 mg/lit)

600 600

7 Iron (as Fe mg/lit, Max 0.3 1.0

8 Chlorides (as Cl mg/lit Max 250 1000

9 Residual Free Chlorine, mg/lit Max

0.2

To be applicable only when water is chlorinated. Treated at consumer end. When protection against viral infection is required, it should be Min 0.5 mg/lit

10 Dissolved Solids mg/l, Max 500 2000

11 Calcium (as Ca) mg/l, Max 75 200

12 Copper (as Cu) mg/l, Max 0.05 1.5

13 Manganese (Mn) mg/l Max 0.1 0.3

14 Sulphate (As SO4), Max 200 400 May be extended up to 400 provided (as Mg) does not exceed 30

15 Nitrate (as NO3) mg/l, Max 45 100

16 Fluoride (as F) mg/l, Max 1.0 1.5

17 Phenolic Compounds (as C6H6OH) mg/l Max

0.001 0.002

18 Arsenic (as As mg/l 0.05 No relaxation To be tested when pollution is suspected

19 Lead (as Pb) mg/l 0.05 No relaxation

20 Anionic Detergents (as MBAS) mg/l

0.2 1.0

21 Chromium (as Cr) mg/l 0.05 1.0 To be tested when pollution is suspected

22 Mineral Oil mg/l 0.01 0.03

23 Alkalinity mg/l 200 600

24 Total Coliform 95% of the sample should not contain coliform in 100 ml. 10 coliform

/100 ml

444

Appendix 16: National Ambient Noise Level Standards

Area Code Category Limits in Decibels (dB A)

Day Time Night Time

A Industrial 75 70

B Commercial 65 55

C Residential 55 45

D Silence Zones 50 40

Note: (1) Daytime: 6 AM to 9 P.M., Night-time 9 PM to 6 AM;

(2) Silence zone is an area up to 100 m around premises as hospitals, educational institutions

and courts.

Source: Central Pollution Control Board, New Delhi

445

Appendix 17: Copy of Forest Notification for Kattuguladur and Gudalur RF

446

447

448