47913-014: Yangon Urban Renewal and District Cooling Project
Environmental Compliance Monitoring Report - 43524-014 ...
-
Upload
khangminh22 -
Category
Documents
-
view
1 -
download
0
Transcript of Environmental Compliance Monitoring Report - 43524-014 ...
Environmental Compliance Monitoring Report
Semi-annual Report January 2020 Project No: 43524-015
NEP: Kathmandu Valley Wastewater Management Project
Prepared by Kathmandu Valley Wastewater Management Project (KVWMP) for the Government of Nepal and the Asian Development Bank. This environmental compliance monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Semi-annual Environmental Monitoring Report July-December 2019
ii | P a g e
CURRENCY EQUIVALENTS
(as of 23 December 2019)
Currency unit – Nepalese rupee (NRs)
NRs 1.00 = $ 0.0088
$1.00 = NRs 113.50
Source: Nepal Rastra Bank, Kathmandu
NOTE{S}
(i) The fiscal year (FY) of the Government of Nepal and its agencies ends on 15 July. FY
before a calendar year denotes the year in which the fiscal year ends, e.g., FY 2018 ends
on 16 July 2019.
(ii) In this report, "$" refers to US dollars.
ABBREVIATIONS
ADB – Asian Development Bank
CASSC – Community Awareness and Safeguard Support Consultant
CBS – Central Bureau of Statistics
CDC – Compensation Determination Committee
CEMP – Contractor Environmental Management Plan
DSC – Design and Supervision Consultants
EA – Executing Agency
EMP – Environmental Management Plan
GON – Government of Nepal
GRC – Grievance Redress Committee
IP – Indigenous People
IR – Involuntary Resettlement
IS - Interceptor Sewers
KUKL – Kathmandu Upatyaka Khanepani Limited
KVWMP – Kathmandu Valley Wastewater Management Project
MoWS – Ministry of Water Supply
PD – Project Director
PID – Project Implementation Directorate
PID-SU – Project Implementation Directorate-Safeguard Unit
PIU – Project Implementation Unit
PM – Project Manager
Semi-annual Environmental Monitoring Report July-December 2019
iii | P a g e
ROR – Right of River
RP/IPP – Resettlement Plan
R&R – Resettlement and Rehabilitation
ToR – Terms of Reference
WWTP – Waste Water Treatment Plant
Semi-annual Environmental Monitoring Report July-December 2019
iv | P a g e
Table of Contents
Executive Summary ....................................................................................................................... vi
1 Introduction ................................................................................................................................. 1
Background ................................................................................................................... 1
Objectives ..................................................................................................................... 1
Scope ............................................................................................................................ 1
Monitoring Requirements ............................................................................................... 2
Environmental Category ................................................................................................. 2
Project Safeguards Team ................................................................................................ 2
Overall Project and sub-project Progress / Status ............................................................... 4
2 Compliance Status with National / State / Local Statutory Environmental Requirements ........ 8
3 Compliance Status with Environmental Loan Covenants ........................................................ 10
4 Status of Corrective Action Plan set forth in ADB review mission. ........................................ 12
5 Contractor Compliance Status as per CEMP ............................................................................ 13
6 Contractor Compliance with Environmental Safeguard Requirement ..................................... 14
Compensation tree plantation ........................................................................................ 14
7 Compliance Status with the Environmental Management Plan................................................ 15
8 Environmental Monitoring for Air, Noise and Water............................................................... 28
8.1 Air Quality Monitoring ........................................................................................... 28
8.2 Noise Level Monitoring .......................................................................................... 28
8.3 Water Quality Test .................................................................................................. 29
9 Consultations and Focal Group Discussions ............................................................................ 30
10 Training to contractor/workers on Occupational Health and Safety (OHS) ............................. 31
10.1 Hazard Identification Risk Assessment .................................................................... 31
10.2 Training on OHS by ADB OHS consultant .............................................................. 33
10.3 Training to the Labors ........................................................................................... 34
10.4 Meeting for Safeguard Compliance (OHS review meeting) ........................................ 34
10.5 First Aid Training ................................................................................................. 34
11 Grievance Redress Mechanism ................................................................................................. 34
12 Other Safeguard Related Activities Conducted During This Period ........................................ 36
13 Summary of Key Issues and Corrective Action ....................................................................... 38
14 Status of Corrective Action Plan from Previous Reporting Period .......................................... 38
15 Action Planned for Next Reporting Period ............................................................................... 39
16 APPENDIX ............................................................................................................................... 40
Appendix 1: Photographs .............................................................................................. 40
Appendix 2: Road Cut Permit ........................................................................................ 47
Appendix 3: Package wise Contractor’s Nodal person for Environmental Safeguard ........... 51
Appendix 4: Attendance sheet of Tree Plantation............................................................. 52
Appendix 5: Minutes of Meeting ................................................................................... 55
Appendix 6: Sample Checklist Of Hazard Identification Risk Assessment ......................... 59
Appendix 7: Attendance sheet of the training given by ADB OHS consultant ..................... 61
Appendix 8: Attendance sheet of the training given by DSC ............................................. 66
Appendix 9: Minutes of meeting of Safeguard Compliance (OHS review meeting) ............. 68
Appendix 10: Attendance sheet of First Aid training ........................................................ 70
Appendix 11: Some Filled Safety Checklists for Different Projects. .................................. 71
Semi-annual Environmental Monitoring Report July-December 2019
v | P a g e
Appendix 12: Sample Site Inspection Report .................................................................. 85
Appendix 13: Automated Safeguard Performance Monitoring Scoring .............................. 89
Appendix 14: CEMPs of All Packages ........................................................................... 91
Appendix 15: Automated Safeguard Performance Monitoring Scoring of All Packages ....... 91
List of Tables
Table 1-1: Project Safeguard Support Team ................................................................................... 2
Table 1-2: Package Wise Implementation Progress ........................................................................ 7
Table 2-1: Compliance Status with National Environment Requirement ....................................... 8
Table 2-2: Package-wise IEE Documentation Status ...................................................................... 9
Table 3-1: Status of Environmental Loan Covenants ................................................................... 10
Table 4-1: Status of the corrective action plan set forth in ADB review mission ......................... 12
Table 5-1: Compliance as per CEMP ............................................................................................ 13
Table 6-1: Contractor compliance status with environmental safeguard requirement .................. 14
Table 7-1: Compliance Status of EMP .......................................................................................... 15
Table 7-2: EMP compliance status of IS projects ......................................................................... 16
Table 7-3: EMP compliance status of TP projects ........................................................................ 22
Table 8-1: Noise Level Monitoring Result in TP-01 .................................................................... 28
Table 8-2: Noise Level Monitoring Result in TP-02 .................................................................... 28
Table 8-3: Noise Level Monitoring Result in TP-03 .................................................................... 29
Table 8-4: Drinking water quality test at TP-01. .......................................................................... 30
Table 9-1: List of public consultation done during this reporting period ..................................... 30
Table 10-1: Major Environmental Safeguard (OHS) issues with their mitigation measure and
compliance status raised during risk assessment........................................................................... 32
Table 10-2: Number of participants in different training .............................................................. 34
Table 11-1: Grievances and complains reported. .......................................................................... 35
Table 13-1: List of key issues and corrective action ..................................................................... 38
Table 14-1: Status of Corrective Action Plan ............................................................................... 38
Table 15-1: List of action planned for next reporting period ........................................................ 39
List of Figures
Figure 1-1: Project Locations of WWTP and Interceptor Sewer Lines. ......................................... 6
Figure 10-1: Grievance Redress Mechanism (GRM) ................................................................... 35
Semi-annual Environmental Monitoring Report July-December 2019
vi | P a g e
Executive Summary
The Kathmandu Valley Wastewater Management Project (KVWMP) (ADB Loan No. 3000-NEP)
is working for the improvement in the wastewater services in Kathmandu Valley with the
expansion, upgrading and new construction of sewer networks to improve quality of wastewater
before it disposes directly into the natural streams flowing along the valley. The major objective
of the project is to manage waste water of the Kathmandu valley. The project is considered
Category B as per the SPS 2009 as no significant impacts are envisioned.
The KVWMP involves (i) rehabilitation and expansion of sewerage network including property
connections; (ii) rehabilitation and construction of interceptors along the streams and rivers; (iii)
modernization and expansion of wastewater treatment plants to 138.1 MLD capacity; (iv) energy
generation of approximately 434 kW through sludge digestion and/ or gasification; and (v)
supporting operational and financial improvements and capacity building. The expected outcome
of the project will be an improved wastewater collection and treatment system and increased access
of wastewater services to the residents of Kathmandu Valley including poor women and men.
Environmental Safeguard conditions of the implemented wastewater treatment plant are
satisfactory and interceptor sewer projects are partially satisfactory. During the construction phase,
the health and safety of the workers, technical staff, visitors and public is one of the most important
aspects. Several instruction letters have been issued to contractors to enhance safety at the working
sites. Similarly, no remarkable impacts upon the surroundings due to noise generated from the
construction and excavation work. Further, no significant impact upon air and surrounding water
with the construction activities carried during this biannual. Till date contractor at WWTP-01 has
removed 90 numbers of trees requiring compensatory plantation.
Semi-annual Environmental Monitoring Report July-December 2019
1 | P a g e
1 Introduction
Background
The Kathmandu Valley Wastewater Management Project (ADB Loan No. 3000-NEP) is
working for the improvement in the wastewater services in Kathmandu Valley with the
expansion, upgrading and new construction of sewer networks to improve quality of
wastewater before it disposes directly into the natural streams flowing along the valley. The
project is investing in rehabilitation and construction of new wastewater treatment plants,
expansion of sewerage network, and improvement of wastewater management in Kathmandu
Valley. The project is expected to increase operational efficiency, enhance service delivery,
and improve health and quality of life of the inhabitants of Kathmandu Valley. Safeguard
policy are the policies that require to “avoid, minimize or mitigate adverse environmental and
social impacts” that may result from development projects. The safeguard policies adopt “do no harm” approach. Development projects that change patterns of use of land, water and other natural resources can cause a range of resettlement effects.
Objectives
The overall objective of the Project is to improve water quality in rivers and tributaries and
their ecosystem in Kathmandu Valley by enhancing wastewater management capacity; whereas
the specific objectives are as follows;
i. rehabilitating and expanding the sewerage networks;
ii. modernizing, expanding, and constructing wastewater treatment plants
(WWTPs); and
iii. supporting operational and financial improvements and capacity building.
Kathmandu Valley is characterized by high population growth (estimated to be 6.6% per
annum) and high population density (estimated at more than 2,500 persons per km2). The total
population of Kathmandu Valley (Kathmandu, Lalitpur and Bhaktapur Districts) was estimated
at 2.51 million in 2011 (CBS, census 2011) and will reach 3.26 million by 2021.
The existing wastewater network has not been maintained or expanded to serve the spreading
urban areas and increased population. This has resulted in untreated sewage being discharged
directly into local watercourses. The rivers have become open sewers presenting severe public
health risks, in particular to the urban poor. Moreover, poor access to sanitation facilities, an
improper solid waste management system, and groundwater and surface water pollution from
untreated domestic sewage have caused increased disease, health risks, and associated
economic burdens disproportionately impacting the poor and vulnerable.
Scope
The KVWWMP involves (i) rehabilitation and expansion of sewerage network including
property connections; (ii) rehabilitation and construction of interceptors along the streams and
rivers; (iii) modernization and expansion of wastewater treatment plants to 138.1 MLD
capacity; (iv) energy generation of approximately 434 kW through sludge digestion and/ or
Semi-annual Environmental Monitoring Report July-December 2019
2 | P a g e
gasification. The expected outcome of the project will be an improved wastewater collection
and treatment system and increased access of wastewater services to the residents of
Kathmandu Valley.
Monitoring Requirements
Monitoring is a major part of the safeguard/resettlement management system to ensure that its
goals are met. Supervision Consultant (DSC-6) has been preparing monthly, quarterly and
semi-annual progress reports on safeguards activities and submitting to KUKL/PID. The
KUKL/PID expert or focal person has been reviewing and consolidating their reports into semi-
annual monitoring and submitting to ADB.
This is the semi-annual environmental monitoring report for the month of July to December
2019 and is prepared in compliance with the ADB Policies. The report comprises activities
performed under Wastewater Treatment Plant (WWTP) package TP-01, TP-02, and TP-03,
Interceptor Sewer packages IS-01, IS-02 and IS-03, Decentralized Wastewater Treatment
Systems (DEWATS) packages Hunumanghat and Gokarna and Sewerage Network SN-03.
Environmental Category
The project is considered Category B as per the SPS 2009 as no significant impacts are
envisioned. As per ADB's Safeguard Policy Statement (2009) and Operations Manual
section on Safeguard Policy (OM F1), borrowers/clients are required to submit monitoring
reports for ADB review. ADB's Environment Policy is to consider environmental issues in all
aspects of the Bank's operations. ADB requires environmental assessment of all project loans,
program loans, sector loans, sector development program loans, financial intermediation loans
and private sector investment operations. The nature of the assessment required for a project
depends on the significance of its environmental impacts, which are related to the type and
location of the project, the sensitivity, scale, nature and magnitude of its potential impacts, and
the availability of cost- effective mitigation measures.
Project Safeguards Team
The project safeguard team supporting for the L-3000 is presented in the following table.
Table 1-1: Project Safeguard Support Team SN Name Designation/Office Email Address Roles
1. PID
1. Bhoj Bikram Thapa
Project Director [email protected]
Overall guidance and direction to the team
2. Laxmi Pant Chief, Safeguard Unit PID
[email protected] As a SU Chief, maintaining safeguard of TP and IS sub-projects compliance and enforcement, meetings with consultants and contractor's ESSS teams,
Semi-annual Environmental Monitoring Report July-December 2019
3 | P a g e
SN Name Designation/Office Email Address Roles
guidance and direction to the teams.
3. Vidya
Bhandari
Sociologist,
Safeguard Unit PID
[email protected] Support unit head in
making necessary
arrangements to review
RP, GESI Action plan
and DDR prepared by
consultant /GESI Focal
person
4. Pramila
Adhikari
Sociologist,
Safeguard Unit PID
Support unit head in
making necessary
arrangements to review
RP, GESI Action plan
and DDR prepared by
consultant /GESI Focal
person/OHS focal person
2. DSC-06
1. Sarika Gharana
Environment Safeguard Specialist
[email protected] Monitoring and supervision of environmental safeguard works of TP, IS and SN projects of L-3000
2. Shisir Gautam
Social Safeguard Specialist
[email protected] Monitoring and supervision of social safeguard works of TP, IS and projects of L-3000
3. Dikshya Dhakal
Environment and OHS Associate
[email protected] Monitoring of environmental safeguard works of TP, IS and SN projects of L-3000
3. Consultants (CASSC)
1. Madhukar
Shrestha
Public Health
Expert-CASSC
[email protected] Orientation /Awareness program for school students, Municipality Mayor, vice- Mayor, ward chairman and members, women members ,women’s group, youth group , Female Community Health Volunteers
2. Rooja
Bajracharya
OHS Expert [email protected]
Support PID in assessment of risks and evaluation of Contractors safety performance, Identification and
Semi-annual Environmental Monitoring Report July-December 2019
4 | P a g e
SN Name Designation/Office Email Address Roles
assessment of OHS requirements
3. Pushpa
Koirala
Environment
Safeguard
Specialist,
PID/CASSC
[email protected] Support safeguard unit in reviewing IEE documents; monitoring and supervision of environmental safeguard compliance of PID projects
4. Ram Krishna Giri
Social Safeguard Specialist, CASSC
[email protected] Generation of awareness at community level and supervision of the sub-projects implemented by PID.
5. Bharat Acharaya
Community Mobilization Expert
[email protected] Coordination with the community level.
6. Min Dahal Field Coordinator meendahal102gmail.com Coordination with the community level.
Overall Project and sub-project Progress / Status
The proposed project includes (i) rehabilitation or construction of new WWTP already
established in different locations in the Kathmandu Valley; (ii) construction of interceptors;
and (iii) improvement in the wastewater network system (rehabilitation, replacing, laying of
new sewer and storm water drains, etc.).
A. Wastewater Treatment Plant (WWTP)
As per the procurement plan, the work includes the rehabilitation and construction of new
WWTP at Kodku 7.0 MLD (Patan), Sallaghari 13.1 MLD (Bhaktapur), Dhobighat 39 MLD
(Kathmandu), Guesheshowri 30.6 MLD (Kathmandu). The two numbers of packages are
ongoing for the implementation of WWTPs based on the updated capacity as per the revised
design, Package I consisting of one treatment plant i.e. Guheshwori (32.4 MLD) as WWTP-
01, WWTP-02 consisting of three WWTPs i.e. Sallaghari (14.20 MLD), Kodku (17.5 MLD)
and Dhobighat (37 MLD) and WWTP-03 i.e. Dhobighat (37 MLD). The WWTPs have been
designed for extension and rehabilitation in the existing locations, and on government land that
was acquired more than 3 decades ago. The land required for updated capacity is within the
threshold of available land acquired. Population and service area coverage figures are changed
based on current design estimation. Decentralized Wastewater Treatment Systems (DEWATS)
have been added. DEWATS component split into two separate packages - WW/DCTP-01 for
Hanumanghat DEWATS and WW/DCTP-02 for Gokarna DEWATS.
B. Interceptor Sewers
At present, the KVWWMP is laying interceptors along the banks of Hanumante, Manohara
and Khashyasang Khusung rivers in different packages IS-01, IS-02 and IS-03 respectively.
Semi-annual Environmental Monitoring Report July-December 2019
5 | P a g e
The package KUKL/WW/IS-01 includes construction of Intercepting Sewerage System along
both bank of Hanumante river from Jagati of Bhaktapur along the left bank and from Chokin
Chilla bridge at Kharipati along right bank of Hanumante upto Manohara confluence down
stream. The package KUKL/WW/IS-02 includes extension and construction of intercepting
sewer system along both banks of Manohara River from Manohara and Hanumante confluence
up to Sun City colony along Manohara. The package KUKL/WW/IS-03 includes laying of
interceptor sewer pipeline along the Khashyasang Khusung River catering the sewer into
Sallaghari WWTP. The storm water from sewerage network will be over flowed to the nearby
stream or river through the overflow/diversion structures. The pipeline alignments will be on
existing RoRs. The government has defined 20 m on both banks of rivers in Kathmandu as
RoRs, so the interceptors will be laid within the RoWs to the extent technically feasible.
C. Sewer Cleaning and Rehabilitation
Sewer Cleaning and Rehabilitation in Core Area of Patan (KUKL/WW/SN-03) is also a new
package initiated on the request of KUKL and Lalitpur Metropolitan City (LMC). As discussed
with LMC and KUKL, the rehabilitation work will be focused to reduce flooding in the core
area of Patan, which also includes a UNESCO heritage site Durbar Square. DSC-04 prepared
and submitted a draft DPR of the combined sewer and storm water drainage network to the
PID, which has been discussed with KUKL and LMC. The preparation of environmental and
social safeguards documents meeting ADB requirements has been done. Heritage Impact
Assessment (HIA) report and Initial Environmental Examination (IEE) report have been
prepared. IEE report has been presented in the Ministry of Water Supply (MoWS) on
01/06/2019 and is in the process of approval.
Semi-annual Environmental Monitoring Report July-December 2019
6 | P a g e
Figure 1-1: Project Locations of WWTP and Interceptor Sewer Lines.
Semi-annual Environmental Monitoring Report July-December 2019
7 | P a g e
Description of Subprojects (package-wise) and Status of Implementation
Table 1-2: Package Wise Implementation Progress
Present Progress Status of Ongoing Contracts as of December 2019
SN
Contract Package
Contractor
Contract
Amount,
million
NPR
Commenc
ement
Date
Initial
Completion
Date
Revised
Completion
Date
Financi
al status
(%)
Status as of December 31, 2019
(KUKL/WW/...)
Time
Elapsed
(%)
Progress
1 TP/01 Guheshwori
WWTP VA Tech
Wabag Ltd. 2,558.32 1-Aug-16 22-Jul-18 31-Dec-19 86.00 100.0
Detailed design: 100 %
Manufacturing and supply: 100%
Civil works: 99.8%
Overall progress: 98.78 %
2 TP-02 Sallagahri, Kodku & Dhobighat
Safbon Water Service
(Holding) 3,920.62 7-May-19 6-Nov-19
EoT recommended
upto 7 Dec 2019
19.88 100.0
Basic Design: 100% approved
Detail Design:98.8% approved
Overall Progress: 17.27%
3 TP-03 Dhobighat
WWTP CGCOC - ATAL JV
1,962.39 25-Mar-18 14-Mar-20 12.36 81.9
Basic design : 100%
Detail Design: 100% completed
Construction: 4.29%
Overall Progress: 9.67%
4 IS-01 Hanumante Interceptors
GIETC-Lama-Raman
JV 636.04 3-May-16 23-Apr-18
EOT-01: 5-Apr-19 EOT-02: 31-Dec-
19
52.60 100.0
Hume pipe laying: 16.6 km
Manholes: 388 nos.
Aqueducts/Crossings: 6
River training works: 568 m
Hume pipes for Overflow/Outfall structures:60m
Overall Progress: 42.42%
5 IS-02 Manohara
Interceptors
ZIEC-Sharma-BKOI JV
758.66 2-Nov-16 23-Oct-18
EOT-01: 31-May-19
EOT-2: 16 Dec 2019
45.90 100.0
Hume pipe laying: 5.5 km
Manholes: 120at various stage
Aqueducts/Crossings:2
River training works: 2686 m
Overall Progress: 41.9%
6 IS-03 KashayangKh
usung Collectors
Lama-Raman-Golden Good
JV 411.23 15-Dec-17 8-Jun-19
EoT recommended
upto 7 Dec 2019
87.00 100
Hume pipe laying:7.075km
Manholes: 182 nos.
River Crossings: 3
Overflow/Outfall structures: 25
Over all Progress: 100%
Semi-annual Environmental Monitoring Report July-December 2019
8 | P a g e
2 Compliance Status with National / State / Local Statutory Environmental
Requirements
The project has fulfilled all the statutory requirements in order to safeguard environment with
the consequences due to construction works.
Table 2-1: Compliance Status with National Environment Requirement Package
No.
Sub-project
Name
Statutory
Environmental
Requirements1
Status of
Compliance2
Validity
if
obtaine
d
Action
Required
Specific Conditions
that will require
environmental
monitoring as per
Environment
Clearance,
Consent/Permit to
Establish3
KUKL/WW/TP-01
Guheshwori WWTP
Initial Environmental Examination (IEE)
IEE report approved
N/A N/A No any permission required
KUKL/WW/TP-02
Sallaghari, Kodku and Dhobighat WWTPs
Initial Environmental Examination (IEE)
IEE report approved
N/A N/A No any permission required
KUKL/WW/TP-03
Dhobighat WWTP
Initial Environmental Examination (IEE)
IEE report approved
N/A N/A No any permission required
DEWATS
Hanumanghat and Gokarna
Initial Environmental Examination (IEE)
Submitted to ADB for review
N/A Finalize the report
No any permission required
KUKL/WW/IS-01
Hanumante Interceptor Sewer
Initial Environmental Examination (IEE)
IEE report approved
N/A N/A No any permission required.
KUKL/WW/IS-02
Manohara Interceptor Sewer
Initial Environmental Examination (IEE)
IEE report approved
N/A N/A No any permission required
KUKL/WW/IS-03
Khashyang Khusung Interceptor Sewer
Initial Environmental Examination (IEE)
IEE report approved
N/A N/A Road cut permit required. (Obtained and permit attached in Appendix 2)
KUKL/WW/SN-03
Sewer cleaning and rehabilitation in core area of Patan
Initial Environmental Examination (IEE)
IEE Approved by ADB and ToR approved by (MoWS), IEE presented in MoWS and incorporation of comments ongoing
N/A Finalize the report
Heritage Impact Assessment (HIA ) is required that is prepared and submitted to DoA for approval.
1 Specify (environmental clearance? Permit/consent to establish? Forest clearance ?Etc.) 2 Specify if obtained, submitted and awaiting approval, application not yet submitted 3Example: Environmental Clearance requires ambient air quality monitoring, Forest Clearance/Tree-cutting Permit
requires 2 trees for every tree, etc.
Semi-annual Environmental Monitoring Report July-December 2019
9 | P a g e
Package wise IEE report is prepared for each sub-project. The status of IEE report of each sub-project is presented in Table 2-2.
Table 2-2: Package-wise IEE Documentation Status Package Number Final IEE based on Detailed Design Site-specific EMP
(or Construction
EMP) approved by
Project Director?
(Yes/No)
Not yet due (detailed design not yet
completed)
Disclosed on project website (Provide Link) EMPs
included in the bidding
documents
(Yes/No)
KUKL/WW/TP-01
IEE Approved by ADB http://www.kuklpid.org.np/kukl/Content/Upload/document/safeguard/43524-014-iee-en_3.pdf
Yes Construction EMP prepared and approved
KUKL/WW/TP-02
IEE Approved by ADB http://www.kuklpid.org.np/kukl/Content/Upload/document/safeguard/43524-014-iee-en_1.pdf
Yes Construction EMP prepared and approved
KUKL/WW/TP-03
IEE Approved by ADB http://www.kuklpid.org.np/kukl/Content/Upload/document/safeguard/43524-014-iee-en_2.pdf
Yes Construction EMP prepared and under approval
DEWATS Comments on IEE received from ADB and incorporation of comments ongoing
Not Yet Yes Not Yet
KUKL/WW/IS-01 IEE Approved by ADB https://www.adb.org/projects/documents/nep-43524-014-iee
Yes Construction EMP prepared and approved
KUKL/WW/IS-02 IEE Approved by ADB http://www.kuklpid.org.np/kukl/Content/Upload/document/safeguard/Kathmandu%20Valley%20Wastewater%20Management%20Project%20Interceptor%20Sewer%20(IS-02)%20Initial%20Environmental%20Examination%20.pdf
Yes Construction EMP prepared and approved
KUKL/WW/IS-03 IEE Approved by ADB http://www.kuklpid.org.np/kukl/Content/Upload/document/safeguard/Kathmandu%20Valley%20Wastewater%20Management%20Project%20Interceptor%20Sewer%20(IS-03)%20Initial%20Environmental%20Examination.pdf
Yes Construction EMP prepared and approved
KUKL/WW/SN-03
IEE Approved by ADB and ToR approved by Government of Nepal, Ministry of Water Supply (MoWS), IEE presented in MoWS and incorporation of comments ongoing
Not Yet Yes Not Yet
Semi-annual Environmental Monitoring Report July-December 2019
10 | P a g e
3 Compliance Status with Environmental Loan Covenants
The compliance status with environmental and social loan covenants is presented in the following table.
Table 3-1: Status of Environmental Loan Covenants S.N. Covenants as Mentioned in Schedule 5 Status of Compliance
Implementation Arrangements
Loan
Agreement
Schedule 5,
para 6
The Borrower shall make available KVWSMB and KUKL to make available necessary budgetary and human
resources to fully implement the EMP and the RP.
Complied. PID now has Safeguards Unit with
full-time officers and DSC and Community
Awareness and Social Safeguard Consultant
(CASSC) is in place.
Loan
Agreement
Schedule 5,
para 7
The Borrower shall ensure, or cause KVWSMB and KUKL to ensure, that all bidding documents and contracts
for Works contain provisions that require contractors to:
(a) comply with the measures relevant to the contractor set forth in the IEE, the EMP, and the RP (to the
extent they concern impacts on affected people during construction), and any corrective or preventative actions
set forth in a Safeguards Monitoring Report;
(b) make available a budget for all such environmental and social measures;
(c) provide the Borrower with a written notice of any unanticipated environmental, resettlement or
indigenous peoples risks or impacts that arise during construction, implementation or operation of the Project
that were not considered in the IEE, the EMP, and the RP;
(d) adequately record the condition of roads, agricultural land and other infrastructure prior to starting to
transport materials and construction; and
(e) reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition
upon the completion of construction.
Complied All bidding documents are
prepared as per ADB Standard Bidding
Document (SBD).
Semi-annual Environmental Monitoring Report July-December 2019
11 | P a g e
Safeguards Monitoring and Reporting
Loan
Agreement
Schedule 5,
para 8
The Borrower shall do the following, or cause KVWSMB and KUKL to do the following:
(a) submit semiannual Safeguards Monitoring Reports to ADB and disclose relevant information from such
reports to affected persons promptly upon submission;
(b) if any unanticipated environmental and/or social risks and impacts arise during construction, implementation
or operation of the Project that were not considered in the IEE, the EMP, and the RP, promptly inform ADB of
the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action
plan; and
(c) report any actual or potential breach of compliance with the measures and requirements set forth in the EMP
or the RP promptly after becoming aware of the breach.
Complied Semi-annual environmental
monitoring reports have been prepared and
submitted regularly.
Labor Standards
Loan
Agreement
Schedule 5,
para 10
The Borrower and KUKL shall ensure that the contractors comply with all applicable labor, health, and safety
laws and regulations of the Borrower and, in particular, (a) do not employ child labor for construction and
maintenance activities, and (b) provide appropriate facilities (latrines, etc.) for workers at construction sites. The
Borrower shall require contractors not to differentiate wages between men and women for work of equal value.
The Borrower and KUKL shall ensure that specific clauses shall be included in bidding documents to ensure
adherence to these provisions, and that compliance are strictly monitored during project implementation.
Complied. PID through its Design and
Supervision Engineer (DSC) is supervising
and monitoring the compliance with labor,
health and safety law regulations. The project
work is in compliance with ADB's
requirements and national laws & regulations.
Grievance Redress Mechanism
Loan
Agreement
Schedule 5,
para 16
Within 12 months of Effective Date, KUKL shall prepare a grievance redress mechanism, acceptable to ADB,
and establish a special committee to receive and resolve complaints and grievances or act upon reports from
stakeholders on misuse of funds and other irregularities, including grievances due to any resettlement. The special
committee shall (a) make public the existence of the grievance mechanism, (b) review and address grievances of
stakeholders of the Project, in relation to either the Project, any of the service providers, or any person responsible
for carrying out any aspect of the project; and (c) proactively and constructively responding to them.
Complied.
Grievance redress mechanism (GRM)
established. A special committee in PID to
receive and resolve complaints and grievances
has also been formed. The project has formed
16 GRC at ward level to redress grievance
during the period till the date.
Semi-annual Environmental Monitoring Report July-December 2019
12 | P a g e
4 Status of Corrective Action Plan set forth in ADB review mission.
The status of the corrective action plan set forth in ADB review mission in November 2019 is given
in Table 4-1.
Table 4-1: Status of the corrective action plan set forth in ADB review mission Description Time frame Responsible Current Status
Appoint an environment expert in the Safeguard Unit/PID and train in OHS requirements. Outsource a full-time environment consultant until the position is vacant
15 Jan 2020 MWSS/PID Environment consultant is working at safeguard unit
PID to immediately instruct contractor of all contracts (TP and IS packages) to urgently replace the shanty camps constructed with tarpaulin/rusted old CGI sheet by following PID specification for camp, kitchen, cafeteria, toilets and shower rooms etc.)
15 Dec 2019 Contractors SU/PID
Under Process
PID to immediately instruct contractor of all contracts (TP packages) to establish a medical bay with sick-bed, simple medical equipment and first-aid medicines managed by an assistant health worker
15 Dec 2019 Contractors SU/PID
Complied
PID to immediately instruct contractor of all contracts (TP packages) to submit air, water and noise standard
15 Dec 2019 Contractors SU/PID
Done
Consult with existing contractors and agree to urgently mobilize an environment cum OHS staff at every work site. Train the staff in OHS requirements through support of PID
31 Dec 2019 PID/Contractors ADB
Complied
Instruct contractors of all contract packages to spray water on dry area of work or vehicle operation inside or approach road to work sites in order to suppress dust
Immediately PID Contractors
Complied
Grade the approach roads irrespective of responsible agency for maintaining or black-topping (eg. in TP Dhobighat, Kodku, and most of IS work areas)
Immediately PID Contractor
Under Process
Instruct contractor to submit landscaping and vegetation plan in all the concerned contract packages
30 Nov 2019 PID Done
PID to organize a joint meeting with ADB and the contractor of non-performing contract packages, and agree to take urgent corrective actions and record in minutes
15 Dec 2019 PID/SU, ADB, Contractor
Complied
ADB to finalize environmental safeguards and OHS guidelines, also including procedural guideline and “zero soil” concept Customize the guidelines and get approval from MWSS and translate in Nepali
31 Dec 2019 29 Feb 2020
ADB/PID KUKL/MWSS
PID has not received environmental safeguards and OHS guidelines from ADB
Review and update safeguards BOQ items and contract agreement provisions, and use in all future contract packages. The bidding and CA documents shall be screened for safeguard/OHS provisions by SU.
31 Jan 2020 PID/ADB Already done in new contract package
Keep mandatory provision of site-specific EMP and OHS submission in all future contracts prior to mobilization or initiation of work at a given site
On-going PID Compiled
Semi-annual Environmental Monitoring Report July-December 2019
13 | P a g e
Mobilize a software designer to prepare a safeguard information management system (part of PPMS at PID level), which will be useful to manage multiple projects by PID. The system shall complimentary to the safeguards monitoring system being prepared by SAUW and linked to SARD safeguard tracking system
15 Feb 2020 PID/ADB Complied. ADB has supported PID to operate Automated safeguard performance monitoring.
Explore national institutions to provide OHS training, and arrange for the training through appropriate source of funding
On-going activity ADB PID
OHS expert has been recruited and expert has planned for OHS training to contractors and labours
At the Sallaghari WWTP sites (TP-02 package) conduct an environmental due diligence with all required chemical tests to identify possibility of toxicity to pollute soil and surface/groundwater prior to managing solid waste mixed earth excavated for project work.
As and when required and before disposing
DSC PID Contractor
Complied
5 Contractor Compliance Status as per CEMP
Overall Compliance with Contractor Environmental Management Plan (CEMP)/ Environmental
Management Plan (EMP) is presented in Table 5-1.
Table 5-1: Compliance as per CEMP SN. Sub-Project Name EMP/ CEMP
Part of
Contract
Documents
(Y/N)
CEMP/ EMP
Being
Implemented
(Y/N)
Status of
Implementation
(Excellent/ Satisfactory/
Partially Satisfactory/
Below Satisfactory)
Action Proposed
and Additional
Measures
Required
1. KUKL/WW/TP-01 CEMP prepared by contractor
CEMP implemented
Satisfactory N/A
2. KUKL/WW/TP-02 CEMP prepared by contractor
CEMP partially implemented
Satisfactory N/A
3. KUKL/WW/TP-03 CEMP prepared by contractor and under approval process
CEMP partially implemented
Satisfactory N/A
4. KUKL/WW/IS-01 CEMP prepared by contractor
CEMP not implemented properly
Partially Satisfactory N/A
5. KUKL/WW/IS-02 CEMP prepared by contractor
CEMP not implemented properly
Partially Satisfactory N/A
6. KUKL/WW/IS-03 CEMP prepared by contractor
CEMP not implemented properly
Partially Satisfactory N/A
Semi-annual Environmental Monitoring Report July-December 2019
14 | P a g e
6 Contractor Compliance with Environmental Safeguard Requirement
Table 6-1: Contractor compliance status with environmental safeguard requirement
S.N Description Remarks
1. Appointment of Environment, Health and Safety (HSE) and/or nodal person
Appointed. Details in Appendix 3.
2. Submission of site-specific EMPs Under revision/approval phase
3. Submission of SEMP implementation report Monthly
4. Site verification by PMU, PIU or consultants Continuous process.
5. SEMR compliance matrix on mitigation measures implementation
Continuous process.
Compensation tree plantation
IS02 has done tree plantation along right bank of Manohara river upstream of Pepsi Cola Bridge in
first phase on 19th August 2019 and downstream of Balkumari Bridge in second phase on 31st August
2019. In each phase, 100 numbers of tree saplings were planted in coordination with the people of
community, PID, DSC and CASSC. Total 200 trees including the tree sapling of camphor, rudraksha
of height 5ft to 6 ft were planted. Tree plantation was done to rehabilitate greenbelt damage that was
done during the construction works and to fulfill the requirement of local community as agreed at
the time of commencing constructing activities at the locality. Tree saplings have been protected by
barricading with bamboo strips and the contractor shall provide service of maintenance for the
planted trees till the end of the contract period. The minutes of meeting of tree plantation is attached
in Appendix 4.
TP01 has also cut trees during the construction phase within WWTP with ownership by KUKL. For
this, the contractor need to plant trees for the compensation of the tress that are cut down. Hence,
they have started first phase plantation to plant 180 trees inside the plant boundary on 13th December
2019. Tree saplings of Jacaranda Mimosifolia, Dhupi, Kapur, Palm, Parijat, Tejpatta, etc are
proposed to be planted. The main objective for the plantation of saplings is to comply with the
environmental compliance measures to improve the environmental conditions and for recreation of
the space.
Se
mi-a
nn
ua
l En
viro
nm
en
tal M
on
itorin
g R
epo
rt Ju
ly-D
ecem
be
r 20
19
15 | P
ag
e
7
Co
mp
lian
ce Sta
tus w
ith th
e En
viro
nm
enta
l Ma
na
gem
ent P
lan
Ta
ble
7-1
: Co
mp
lian
ce
Sta
tus o
f EM
P
Subproject Name
Imp
lemen
tatio
n P
hase (C
om
plia
nce to
EM
P P
rovisio
ns)
Proper spoil management
Proper drainage management
Workers are insured
Occupational health and safety at work site and camps
Open defecation controlled at work sites
Reinstate of public and private structures
Proper housekeeping in work area
Safety drill and tool box talk, safety signage available
Contractor has compensated for temporary land and crop damage
Safety plan prepared and implemented
Employment to local beneficiaries
Bio-engineering for slope protection
Plantation on required areas
Other EMP Compliance
Safeguard desk meeting
convened regularly and minutes kept
Grievance redress mechanism functioning
Public consultation organized regularly as per the plan
Monthly and Semi-annual monitoring report submission
Total Weightage of Implementation
Total Weightage in percentage
3
3
2
7
2
3
3
3
2
3
2
2
2
12
2
3
3
3
60
TP
01
2.6
25
2.5
2
6
2
N/A
2.7
5
2.8
75
N/A
2.5
2
N/A
N
/A
11.2
5
2
3
3
3
47.5
/51
93.1
3
TP
02
2.5
2.5
2
6
2
N/A
2.3
75
2.5
N
/A
2.6
25
2
N/A
N
/A
10
1.5
3
3
3
45/5
1
88.2
3
TP
03
2.2
5
2.5
2
5.7
5
2
N/A
2.8
75
1.2
5
N/A
2.2
5
2
N/A
N
/A
9.7
5
0.5
3
3
3
42.1
2/5
1
82.5
8
IS01
1.2
5
2
2
3.5
2
3
2
1.5
2
1.7
5
2
N/A
N
/A
7.5
2
3
3
3
41.5
/56
74.1
IS02
2
2
2
5.2
5
2
3
2.7
5
2.5
2
2
2
N/A
N
/A
8.5
2
3
3
3
47/5
6
83.9
2
IS03
1.7
5
2
2
4
2
3
2
1.7
5
2
1.7
5
2
N/A
N
/A
7.5
2
3
3
3
42.7
5/5
6
76.3
3
Semi-annual Environmental Monitoring Report July-December 2019
16 | P a g e
Table 7-2: EMP compliance status of IS projects
Semi-annual Environmental Monitoring Report July-December 2019
17 | P a g e
Activities
(Ongoing)
Environmental Impact Location Mitigation Measures Monitoring method Compliance Status
Earthworks Soil Erosion and slope instability
Project Site i. Separate stockpiling of topsoil for further use; ii. Spoil disposal at designated and stabilize sites;
iii. Compact the excavated areas; iv. backfill and include replacement of topsoil; v. avoid work during the rainy
vi. use bioengineering techniques (e.g. re-vegetating area promptly);
vii. line steep channels and slopes(e.g. use of jute matting);
i. Visual Inspections ii. Photographs and local
people’s views if excavation and other site works have caused soils erosion
iii. Check logbook on transportation of excess spoil materials from the sites
Stockpiling of excavated soil
all IS sites are used to backfill
in the trench.
Construction and pipe laying
work is done only in dry
season.
In all IS sites the excavated
area is compacted.
Impact on river water quality and ecosystem
Project Site i. Place the excavated soil properly so that it does not get disposed in the river.
i. Visual Inspections ii. Ground level monitoring in
river alignment
Now excavated soil is not
disposed river in all IS sites.
Interception and interference with localized groundwater flows due to deep excavation
Project Site i. provide permeable base and side backfill at deeply excavated reservoir sites
i. check the water quality of local wells and spring fed or Kuwas particularly downhill of reservoir excavation
Permeable base is not required.
Labor Camp and
Construction of
toilets in the camps
Water and land pollution Labor Camp i. Provide designated areas with collection bins for wastes;
ii. provide toilet facilities and prohibit open defection
iii. prohibit washing of vehicles next to rivers and streams
i. Check the availability of dustbins.
ii. No of toilets and waste disposal system
▪ No dedicated area for the collection of waste at vicinity of construction area. But collection bins are available in the labour camp at IS-01, IS02 and IS03. ▪ Toilet facilities are provided in the labour camp and open defection is prohibited. ▪ washing of vehicles next to rivers and streams are not done.
Storing of materials
and dumping of
Water and land pollution Project site i. Store construction aggregates, hazardous and toxic materials, lubricating oils
i. Inspection of store room ii. Behavior of disposing waste
iii. Check the training records
All the sites have designated area i.e. store room in their labor camp for the storage of
Semi-annual Environmental Monitoring Report July-December 2019
18 | P a g e
excessive materials
in the project area.
And handling of
toxic materials
ii. Use batteries in safe areas and away from any drainage leading to water bodies;
iii. have designated bounded area for storage; iv. dispose of an wastes generated by construction
activities in designated area; v. provide training to workforce on safe handling of
toxic materials
hazardous and toxic materials
1. Quarrying operations. 2. Movement of vehicles 3. Operation of crusher 4. Earthworks, Stockpiling of construction materials
Air quality deterioration. Eye injury of workers due to dust particles.
Project site i. Dust suppression on roads or at open sites by sprinkling water as required at regular intervals;
ii. Cover earth stockpiles using plastic sheets or cement jute bags;
iii. Use tarpaulins to cover sand and other loose material during transport;
iv. Limit vehicle speed 10-15 km/hr; v. site to be signed specifying speed limits
vi. Ensure that vehicles comply with National Vehicle Mass Emission Standard , 2056 BS;
vii. Do regular maintenance of vehicles;
i. Check whether water is sprinkled or not.
ii. Check the speed of vehicles during site visit.
Water sprinkling is not practiced for dust suppression in IS-01 site. Earth stockpiles are not covered. Speed of vehicles is limited to 10-15 km/hr. Regular maintenance of vehicles is done.
Movement of vehicles, operation of Crusher
Noise and Vibration Project site i. Monitor noise levels regularly at site to meet noise standards
ii. Fit mufflers in vehicles to control noise iii. Limit the speed of vehicles. iv. Compensate the damages caused by vibration if
caused by construction activities.
i. Baseline noise level monitoring in the site
ii. Baseline noise level monitoring of the vehicles.
iii. Check the number of speed limit signage at the project site.
iv. Photographs of building and structures before and after construction works.
-Noise level monitoring is not done in all IS sites. -No use of mufflers in vehicles to control noise. -Damage done by the construction work is compensated.
Pipe laying works and construction of manholes
1. Vegetation clearance 2. Damage to fisheries and aquatic ecology of riverbeds and habitats
Project site and nearby water sources
i. Cut only trees that are marked and have been approved by the Department of Forestry
ii. Plant and rear tree sampling at the rate of 25 samplings for each felled tree
iii. Do construction during dry seasons and use river diversions and bunding work section
i. Check records of tree cut and plantation.
Construction works are done
only in dry season.
Influx of outside workforce, money and unwanted activities
Increase in crime and community stress
Labour Camp i. Prohibit gambling and alcohol consumption in contractor's camp sites;
ii. Instruct the workforce to respect the local cultures, traditions, rights etc;
iii. Provide security in contractor's camp.
i. Inspection of the worker’s camp regularly.
ii. Check record of the trainings given to workers.
Gambling and alcohol consumption is not recorded in all sites. Instructions are given regularly. Tool box talk is done regularly
Semi-annual Environmental Monitoring Report July-December 2019
19 | P a g e
in all IS sites. Security at labor camp is not satisfactory.
Manual handling of
construction
material and
equipment
May cause, strain and
sprains such as back
damage.
Project Site i. Provide adequate rest periods, allowed job rotation job rotation, minimize repetitious twisting and shoveling;
i. Communication with the workers
Lunch hour is fixed for 1 hour during which labors get short time break.
Construction
activities like
excavation, pipe
laying, manhole
construction,
backfilling, etc
Impact on Health and
hygiene on workers
(unsafe working
conditions, accidents, fire
hazard, transmission of
communicable diseases
etc.)
Project site i. Provide regular health checkup, sanitation and hygiene, health care and control of epidemic diseases to the workforce;
ii. Wear personal protective equipment including high visibility vest, hard hat, boot, gloves, etc
iii. Launch awareness programs concerning human trafficking and the possibility of spread of sexually transmitted diseases(STDs) HIV/AIDS using brochures, posters and signboards;
iv. Provide insurance to workers and training in occupational health and safety;
v. Give importance to community health and safety: vi. Provide alternate portable water supply during
maintenance works and notify the public in advance,
• Prevent pollution of air in agricultural land, vegetation, and human settlement due to dust and vehicular emissions
i. Check the availability of first aid kits, ambulance and fire extinguishers in construction sites;
ii. Check that the contractor has provided PPE to all workers;
iii. Ensure that all the safety measures are implemented by the Contractor;
iv. Ensure that the PID safeguard manual is strictly followed.
Record the number of awareness programs launched.
▪ Health checkup of worker is done in IS01 and IS02 sites. ▪ The compliance of use of PPE i.e. reflective jacket, safety boots, gloves, and hard helmet by workers are satisfactory in all IS sites. ▪ Health insurance is given to all the workers. First aid kit is available in all the site with complete set of items.
• Avoid wastewater pollution on land, humans, receiving waters, and the environment
• Minimize nuisance due to traffic noise and vibrations
• Prevent nuisance from odors and noise from wastewater treatment plants,
• Avoid traffic accidents and traffic jam
• Prevent the possibility of accidents and fire extinguishers in camp due to trench excavation,
Semi-annual Environmental Monitoring Report July-December 2019
20 | P a g e
• make available first aid kits, ambulance and fire extinguishers in camp sites,
• Make available protection gears to all construction workers and compensate for the loss of life or any type of injuries
May damage community services and infrastructure
Project Site i. Compensate or reinstate/relocate community assets that are disturbed such as irrigation canals, electricity poles, telephone lines, drinking water pipes, sewerage lines, roads etc. to the satisfaction of the people;
ii. coordinate with concerned utilities, local people; iii. Design maps of the area with utilize and
emergency response plans (develop and include an emergency response plan/template that includes notification and reporting protocols).
i. Field observation to visually assess if disturbed community assets are reinstated.
ii. Photographs before and after construction in sensitive areas
Compensation has been distributed to project affected people and community in all the sites.
Injury to public Project Site i. Provide fencing and/or barricades as per site risk assessment;
ii. Apply signage and pedestrian control; iii. Devise and implement system for site inspection
and security; iv. Make a grievance register so that public can
mention their problem
i. Inspect the site regularly to check barricade wall, signage boards and other safety measures.
ii. Inspect that grievance register is placed in such a way that it is visible to public people.
Green net is used as barricade wall but that is not adequate and effective as the distance between barricade wall and slope edge is less. -No proper Signage board is seen around the construction site.
Vehicle accidents Project Site i. Develop a traffic control plan and keep areas clean and clear obstacles
i. Check the traffic control plan and working schedules.
ii. Inspect the location of construction material storage area.
No traffic disruption along the sewer alignment.
Existing underground services can cause explosion, electrocution and damage.
Project Site i. Inform site in-charge before digging/excavation; ii. Check relevant authority (e.g. power, water.
telephone) records for location of services; iii. If in doubt use the experienced service of people
in the locality.
i. Inspect public houses to ensure no service is disrupted.
Site in-charge is informed before digging/excavation.
Semi-annual Environmental Monitoring Report July-December 2019
21 | P a g e
Falling objects during
storage of materials
during excavation.
Project Site i. No materials to be used placed or staked near the edge of any excavation;
ii. No load to be placed or moved near the edge of the excavation where it is likely to cause collapse of side of work;
iii. No load handling/movement across excavation; iv. No roll able objects stored uphill from excavation.
i. Measure the distance between the slope edge and stockpiled materials.
Excavated soil is piled safely without the chance of falling. No load is moved near the edge of the excavation where it is likely to cause collapse of side of work; Across excavation no load handling is done.
Sloping ground can cause
the falling of rolling
objects.
Project Site i. Maintain good housekeeping (remove debris, trip hazards, site tidiness);
ii. Secure/retain potential falling/ rolling objects.
i. Inspection of the site for housekeeping.
Housekeeping of all IS sites is not in satisfactory in the construction site. But it is satisfactory in the labor camp.
Trench collapse and
falling objects.
Project Site i. Support/bench/batter excavation; ii. Install a shoring system
iii. Keep safe distance from edge of trench (at least 0.60m away from sides of trench depending on soil type and to be barricade/fenced to debar the public).
iv. No load to be placed or moved near the edge of trench where it is likely to cause collapse of the trench;
v. Where possible backfill trenches or barricade when left open for a period of time.
i. Inspect the excavated areas. Measure the distance between the slope edge and stockpiles materials near the excavated areas.
Shoring is not installed properly in any of the sites. Support is given in some section only. Barricade is not done properly when left open for a period of time.
Slippery surface can
cause slips and fails
Project Site i. Wear non-slip safety footwear in all site; ii. Ensure extreme care when working in wet and
slippery areas; iii. Personnel should never run on worksite.
i. Check whether the worker wear safety boot or not.
Workers wearing safety boots on most of sites. And such slippery surface is also not seen in construction sites.
Storage of
hazardous
materials used for
construction
May cause injuries and
illness.
Store room of construction site.
i. Handling and storage to be done carefully under guidelines.
ii. Put a name tag on every hazardous material.
i. Inspect store room of construction site to monitor weather materials are stored safely or not.
Hazardous materials are stored in the store room made in the labor camp at IS02 and IS03.
Semi-annual Environmental Monitoring Report July-December 2019
22 | P a g e
Impacts Mitigation Measures Parameters to be monitored Method of Monitoring\
Measurement
Compliance status
Construction Phase
Physical Issue
Employ labour
Job opportunity
▪ Employ local people (not under age 16)
▪ Settle wage rate based on DWEC ▪ Provide the list of employees to
DSC
▪ Number of local persons employed
▪ Number of under-aged people employed
▪ Whether the wage rate is as per with DWEC
▪ List of employees ▪ Nationality ▪ Age of Employees ▪ Wages
Local people are employed in all sites and even female workers are employed in TP01. Equal wages are given to all the workers. Provide the list of employees to DSC.
Earthwork/Excavation for trenches
Soil erosion and slope stabilization
▪ Separate stockpiling of topsoil for further use
▪ Spoil disposal at designated and stabilized
▪ Mulching to stabilize exposed areas
▪ Use bioengineering techniques(re-vegetating area promptly)
▪ Construction to be done in the dry season only
▪ Drainages systems ▪ Stockpiling of top soil for its
reuse ▪ Bio-engineering measures ▪ Management of excessive
spoil materials
▪ Site drawings showing drainage system in project sites
▪ Visual inspections ▪ Photographs and the local ▪ People’s views if excavation
and other site works have caused soils erosion
▪ Stockpiling of excavated soils have been done or not (logbook on transportation of excess spoil materials from the sites)
Excavated soil is stockpiled properly at allocated area near site in all sites. Construction is done in dry season .
Table 7-3: EMP compliance status of TP projects
Semi-annual Environmental Monitoring Report July-December 2019
23 | P a g e
Water Pollution
▪ Avoid camping facilities within clear water supply rivers
▪ Provide designated areas with collection bins for wastes
▪ Provide safe toilets and septics tanks in site
▪ Prohibit open defecation in open areas
▪ Storage of construction aggregrates, hazardous, and toxic materials in safe areas and disposal of chemical containers, packaging materials, plastic bags etc.
▪ Prohibit washing of vehicles next to rivers and streams
▪ Provide training to workforce on safe handling of toxic materials and OHS measures during construction
▪ Recover used oil and lubricants and reuse or remove from the sites
▪ Storage areas for fuels and lubricants should be away from any drainage leading to water bodies
▪ All fuel use areas e.g. generator must have drip basins installed to prevent any leakages and recycled
▪ Yes proper facilities given should be done on a concrete surface provided with a catch tank that can be cleaned and all spilled fuel recovered and recycled
▪ Water quality and health status of workers before and during construction
▪ Site Plan of camp facilities showing nearby receptors, toilet facilities/ ablution blocks
▪ Site plan showing designated storage areas, list of chemicals on site
▪ Prohibition/restrictive signage at the construction sites
▪ OHS training plan and material safety data sheets (MSDS) on site at all times
▪ Oil and lubricant spill prevention measures
▪ Baseline water quality of receiving water (complete physical, chemical and bacteriological tests
▪ Inspection of site plans, distance of camping facility from drainage areas (at least 100m)
▪ Number of toilets/ablution blocks provided
▪ Audit of training plan ▪ Inspection of signage and
MSDS health/clinic reports of workers
▪ Observation of fueling and generator areas
▪ Labour camp is made within a boundary and not on the river side.
▪ Collection bins are placed adequately in designated area in all sites.
▪ Toilets and septic tanks are constructed .
▪ Open defecation is prohibited. ▪ Washing vehicle is also prohibited
in the river. ▪ Training to workforce on safe
handling of toxic materials is given in TP01 but not in TP02 and TP03.
▪ Storage of construction aggregrates, hazardous, and toxic materials in safe areas and disposal of chemical containers, packaging materials, plastic bags etc. is done in all TP sites.
▪ Training to workforce on safe handling of toxic materials and OHS measures during construction is regularly provided.
▪ Storage areas for fuels and lubricants is away from any drainage leading to water bodies.
Air Pollution
▪ Dust suppression on roads or at open sites by sprinkling water as required at regular intervals
▪ Cover earth stockpiles using plastic sheets or cement jute bags
▪ Operation of dust suppression tank, sprinklers on site
▪ Stockpiles covered with appropriate sheeting
▪ Vehicle maintenance records ▪ Renewal of “green stickers” ▪ Ventilators confined spaces
▪ Visual inspection if water is sprinkled or not
▪ Logbook of operation of dust suppression trucks
▪ Photographs of stockpiles ▪ Visual inspection reports
▪ Water sprinkling is done for dust suppression in all TP sites. ▪ Earth stockpiles are not covered using plastic sheets or cement jute bags. ▪ Speed of vehicles is limited to 10-15 km/hr in all sites
Semi-annual Environmental Monitoring Report July-December 2019
24 | P a g e
▪ See that vehicles comply with the National Vehicle Mass Emission Standards, 2056 BS
▪ Regular maintenance of vehicles ▪ Provide ventilation in confined
working areas
▪ Check maintenance records and “Green Stickers
▪ Inspection reports of site plans and no of ventilators (meets international standards
▪ Site drawings showing location of ventilators
▪ No of ventilators
▪ Regular maintenance of the vehicles is done.
Movement of vehicles Operation of crusher Operation of construction machineries and equipment Horn honking
Noise Pollution/ Vibration
▪ Monitor noise levels regularly at site
▪ Fit mufflers in vehicles to control noise.
▪ Limit the speed of vehicles. ▪ Ban the use of power horns in
vehicles. ▪ Regularly maintain the equipment. ▪ Prohibit the operation of crushing
plants and construction vehicles from 7 p.m. to 6 a.m. in residential areas.
▪ Compensate the damages caused by vibration if caused by construction activities.
▪ Baseline noise level Adoption of noise level control measures as specified
▪ Baseline noise level Vehicles with mufflers installed or not
▪ Speed limit signage erected ▪ Maintenance schedule of
equipment ▪ Operation log of crushing
plants ▪ Nearby structures/buildings in
construction areas
▪ Sound level (DBA) feedback/complaints from nearby residents
▪ Number of vehicles installed with mufflers
▪ Number of vehicles with/without power horns
▪ Number of speed limit signage at the project site
▪ Inspection report/photographs of nearby buildings/structures for cracks before/during construction
▪ Noise level is monitored in all TP sites which is under the permissible limit.
▪ Mufflers are not fitted in vehicles to control noise as noise level is under permissible limit.
▪ Damage by vibration is not observed until now.
Waste Disposal
Waste Management
▪ Store all materials, toxic, non-toxic and hazardous materials in safe place (warehouse).
▪ Collect, segregate and dispose waste at designated areas
▪ Waste management plan ▪ Log of collection and disposal
of waste from site
▪ Check amount of solid waste generated and if solid waste management is carried out efficiently.
▪ Audit of waste management plans
▪ Inspection of disposal areas/site plan drawings, photographs, etc.
▪ All materials are stored properly in safe place in all the sites.
▪ Waste is collected properly in all the sites.
Biological Issue
Vegetation Clearance
Loss of Vegetation
▪ Cut only trees that are marked and have been approved by the Department of Forestry. Plant and rear tree saplings at the rate of 25 saplings for each felled tree.
▪ Cutting of only the specified and marked trees
▪ use of timber and wood ▪ availability of LPG/kerosene ▪ tree plantation at the rate of f
25 saplings for each cut tree
▪ Check records of tree cut and planted;
▪ Trees have been cut down in TP01 but will be planted for compensation of the cut down trees.
▪ No trees were cut down in TP02 and TP03.
Semi-annual Environmental Monitoring Report July-December 2019
25 | P a g e
▪ Permits for tree felling and its use
Cultural and Socio-economical Issue
Reinstate/relocate community structure
Damaged of infrastructures and services
▪ Compensate or reinstate/relocate community assets that are disturbed such as irrigation canals, electricity poles, telephone lines, drinking water pipes, sewerage lines, roads, etc. to the satisfaction of the people. Coordinate with concerned utilities, local people, design maps of the area with utilities and emergency response plans (develop and include an emergency response plan/template that includes notification and reporting protocols)
▪ Reinstatement of structurally damaged infrastructure like temples, bridges, irrigation channels, electricity poles, telephone lines, drinking water pipes, sewers, access roads, cracks in buildings etc.
▪ Field observation to visually assess if disturbed community assets are reinstated.
▪ Design drawings and technical specifications showing areas for potential reinstatement.
▪ Photographs before and after construction in sensitive areas
▪ Emergency response plans
▪ Compensation is given whenever required.
Influx of outside work force
Increase in crime and community stress
▪ Instruct the workforce to respect the local cultures, traditions, rights, etc.
▪ Provide security in contractors’ camps.
▪ Awareness program ▪ Workers/staff conduct policy
▪ Enforcement of remedies security situation in camps
▪ Audit of staff/workers conduct policy
▪ Contractor camp is inside a boundary so there is a provision of security to the workers.
OHS Measures/ Project activities relating to health and safety issues at work areas
Negative impact on Health and Hygiene of people (unsafe working conditions, accidents, fire hazard, transmission of communicable diseases, etc.)
▪ Provide regular health checkups, sanitation and hygiene, health care, and control of epidemic diseases to the workforce.
▪ Launch awareness programs concerning human trafficking and the possibility of spread of sexually transmitted diseases (STDs) and HIV/AIDS using brochures, posters, and signboards.
▪ Provide insurance to workers and training in occupational health and safety.
▪ Give importance to community health and safety:
▪ Provide alternate potable water supply during maintenance works and notify the public in advance
▪ The use of safety equipment by workforce
▪ The provision of health measures and training
▪ Awareness program ▪ Signs and posters ▪ Compensation for health
▪ Health records ▪ Records of outbreaks of
diseases ▪ Maintenance of health clinic ▪ Health complaints ▪ Number of awareness programs
launched ▪ Number of persons trained
▪ Health checkup of workers is done in TP01 and TP02 but not in TP03.
▪ Insurance is provided to the entire worker in all the sites.
▪ First aid box and fire extinguishers are available.
▪ Awareness programs are conducted in all sites.
▪ Training in occupational health and safety is provided.
▪ Wastewater pollution on land, humans, receiving waters, and the environment is avoided.
▪ Nuisance due to traffic noise and vibrations is minimized.
▪ Protection gears to all construction workers are provided in all TP Sites.
Semi-annual Environmental Monitoring Report July-December 2019
26 | P a g e
▪ Prevent pollution of air in agricultural land, vegetation, and human settlements due to dust and vehicular emissions.
▪ Avoid wastewater pollution on land, humans, receiving waters, and the environment.
▪ Minimize nuisance due to traffic noise and vibrations.
▪ Prevent nuisance from odors and noise from wastewater treatment plants.
▪ Avoid traffic accidents and traffic jams.
▪ Prevent the possibility of accidents to the people of the community due to trench excavations.
▪ Make available first aid kits, ambulance and fire extinguishers in camp sites.
▪ Make available protection gears to all construction workers and compensate for the loss of life or any type of injuries.
Laying of sewers
injury to the public, contractors, and employees; and vehicle accidents.
▪ Develop a traffic control plan and keep areas clean and clear of obstacles
▪ Working schedule and traffic plans.
▪ Placement of the materials/equipment used in the site.
▪ Visual observation of traffic, signage board
▪ Observation of the storage of materials/equipment
▪ Traffic control plan is not required as all TPs are in confined area.
Semi-annual Environmental Monitoring Report July-December 2019
28 | P a g e
8 Environmental Monitoring for Air, Noise and Water
8.1 Air Quality Monitoring
Monitoring air quality is essential in a project site to know the emission due to different activities in a construction site. Emission of suspended particle and particulate matter is a major concern in the construction site that affects health of the people working in the construction site. None of the contractors have done the air quality monitoring in this reporting period. The period between July-October is the monsoon period and also the festival season in Nepal, the construction works were not carried in a rapid way during this period in the IS projects. Also in TP project water sprinkling is done regularly to prevent dust emission.
Figure: Water is being sprayed in TP03 for dust suppression.
8.2 Noise Level Monitoring
Measuring noise level in a site and noise exposure of workers working in that area is one of the most
important things to monitor. Monitoring noise level helps to identify the work location which is
dangerous, workers who might be affected and identify the workers who need PPE i.e. ear plug while
working. Noise level monitoring was done at all the WWTP projects in this quater. The noise level
monitoring result with the permissible limit of exposure of site TP-01, TP-02 and TP-03 is given in
Table 8-1, Table 8-2 and Table 8-3 respectively. It was found that some equipment like blower,
pump and jack hammer in TP01, batching plant, concrete mixer in TP02 and grinder in TP03 produce
sound greater than 85 dBA but the time of exposure is under the permissible limit. Hence the workers
are safe in regard to the noise level exposure. But if the workers are exposed for a period of time
greater than the permissible time limit, then ear plug should be used. The contractors are instructed
to give ear plug in such cases.
Table 8-1: Noise Level Monitoring Result in TP-01
S.N Description Noise level
(dBA)
Permissible exposure
(Noise level-time)
1. Blower (for 1 min after
starting) 105
105 dBA- 1 hr
2. Blower (after 1 min of
starting) 85
under the permissible limit
3. Pump operated near inlet 88.6 87 dBA- 12.3 hrs
90 dBA- 8 hrs
4. Jack hammer 86.6 87 dBA- 12.3 hrs
Table 8-2: Noise Level Monitoring Result in TP-02
S.N Description Noise level
(dBA)
Permissible exposure
(Noise level-time)
Kodku
1. Office 49.2 under the permissible limit
Semi-annual Environmental Monitoring Report July-December 2019
29 | P a g e
2. Generator 76.4 under the permissible limit
3. Batching Plant: ON
condition 81.7 under the permissible limit
4. Batching Plant: Concrete
Pumping 91.1
90 dBA- 8 hrs
93 dBA- 5.3 hrs
5. Normal working condition of
site (I) 61.8
under the permissible limit
6. Normal working condition of
site (II) 62.7
under the permissible limit
8. Concrete mixer 87.3 87 dBA- 12.3 hrs
9. Rod and pipe cutter 79.2 under the permissible limit
Sallaghari
1. Office 51.12 under the permissible limit
3. Small Tractor during
operation 71.14
under the permissible limit
4. Rod and Pipe Cutter during
operation 74.76
under the permissible limit
5. Concrete Mixer during
operation 70.76
under the permissible limit
7. Normal working time 58.31 under the permissible limit
Dhobighat
1. Welder 60.3 under the permissible limit
2. Generator 75.6 under the permissible limit
Table 8-3: Noise Level Monitoring Result in TP-03
S.N Description Noise level
(dBA)
Permissible exposure
(Noise level-time)
1. Office 52.3 under the permissible limit
2. Grinder (on condition) 88.7 under the permissible limit
3. Grinder (in use) 93.3 93 dBA- 5.3 hrs
96 dBA- 3.5 hrs
4. Rod and pipe cutter (on
condition) 77.3 under the permissible limit
5. Rod and pipe cutter (in use) 90.7 90 dBA- 8 hrs
93 dBA- 5.3 hrs
6. Rod bender 68.7 under the permissible limit
7. Excavator 76.2 under the permissible limit
8. Loader 76.8 under the permissible limit
9. Bar bending condition 60.9 under the permissible limit
8.3 Water Quality Test
Water Quality Test is another important parameter that needs to be done regularly. Drinking
contaminated water will directly hamper the health of the people consuming it. As per the EMP, the
contractors are required to test the drinking water used by labors. Out of six contractors only TP01
Semi-annual Environmental Monitoring Report July-December 2019
30 | P a g e
conducted water quality test while other contractor have not done the water quality test. But the
entire contractor has provided jar water to the workers which are considered as a safe source of
drinking water by the local community people.
Table 8-4: Drinking water quality test at TP-01.
S.N. Parameters Observed Values NDWQS, Nepal
1. pH 7.5 6.5-8.5
2. Electrical Conductivity, (µS/cm) 228.0 1500
3. Turbidity, (NTU) <1 5
4. Total Dissolved Solids 139.0 1000
5. Total Hardness as CaCO3. (mg/L) 96.0 500
6. Total Alkalinity as CaCO3. (mg/L) 74.0 -
7. Chloride, (mg/L) 11.9 250
8. Ammonia, (mg/L) 0.08 1.5
9. Iron, (mg/L) 0.1 0.3
10. Arsenic <0.005 0.05
11. Manganese, (mg/L) 0.49 0.5(WHO)
12. E. coli Count, (MPN Index/100 mL) Nil Nil
13. Total Coliform Nil Nil
9 Consultations and Focal Group Discussions
Public consultation were organized on different location to inform the people about the works going
on under Kathmandu valley wastewater management project, benefits of the projects and some
environmental impact that may occur during the construction works. Three consultation meeting
were organized in this quarter in Gueshwori WWTP (TP-01) on 26th November 2019, Sallaghari
WWTP (TP-02) on 4th December and Ward office of ward no 7 of Bhaktapur Municipality on 5th
December 2019. The minutes of meetings are attached in Appendix 5. Other public consultation
done during the reporting period is listed in Table 9-1.
Table 9-1: List of public consultation done during this reporting period
Date Location No of
Participants
Participants
Attended
Main Topic/issues of
discussion
9 July 2019
Bhaktapur Municipality ward no 4 office (Barahi than area)
M-12 F-1
Total -13
Ward Chairman (local body) ,Local affected people DSC-6 CASSC
Coordination with Municipality ward and local people for boundary setting near Barahi Temple and Ram Mandir Temple
16 October 2019
IS01 office (Radhe Radhe area)
M-13 F-0
Total-13
Local Community people,DSC-6 CASSC
1.About Sewerage pipe laying work and Smoothly Sewerage pipe lying 2. Next coordination meeting will be conduct with Hanumante corridor committee PID and DSC in 22,Nov 2019.
Semi-annual Environmental Monitoring Report July-December 2019
31 | P a g e
25 Nov 2019
Balkumari area Lalitpur 9
M-8 F-27
Total-35
CASSC Local Community people,
1. Awareness about Wastewater Treatment plant project.
27 Nov, 2019
Kathmandu-8, Guheshwori
M-8 F-26
Total -34
Local people, local women group, elected ward representatives, DSC-6 CASSC
1. Construction site observation by meeting participants.
2. Any public grievances will be settled with mutual understanding.
3. This TP will have no impacts on private land or other assets.
4 Dec, 2019
Bhaktapur-2, Sallaghari Treatment plant office
M-20 F-6
Total-26
Local people, and civil society DSC-6 CASSC
1. Construction site observation by meeting participants, and TP construction should be complete within time.
2. Any public grievances will be settled with mutual understanding.
3. This TP will have construction and conduction and no impacts on environment.
5 Dec, 2019
Bhaktapur-7, Hanumanghat ward office near Hanumanghat treatment plant
M-6 F-40
Total-46
Local people, and civil society women group ward representatives DSC-6 CASSC
1. Orientation/ interaction regarding social and environment aspect of Hanumanghat DEWAT and sewage pipe line laying along the Hanumante River.
2. Any environment related suggestion collected and issues will be settled with mutual understanding during the construction of Hanumanghat DEWAT.
Total Participants -167
Male- 67 and Female -100
10 Training to contractor/workers on Occupational Health and Safety (OHS)
10.1 Hazard Identification Risk Assessment
Hazard Identification Risk Assessment should be done at least twice a year. Hazard Identification
Risk Assessment of IS01, IS02, IS03 and TP02 have been done in this reporting period. Risk
assessment was done by forming a risk assessment team and visiting each site individually. At first,
the construction area and labor camp was visited and walked around to gather information. Then the
risk assessment checklist was filled by discussing about the risks/hazard that has arisen in the past
and risks/hazards that are likely to happen in the future. Some of the major issues identified during
Semi-annual Environmental Monitoring Report July-December 2019
32 | P a g e
the assessment are listed in Table 10-1. Sample of Hazard Identification Risk Assessment checklist
is attached in Appendix 6.
Table 10-1: Major Environmental Safeguard (OHS) issues with their mitigation measure and compliance status raised during risk assessment.
S.N Type of Work/
Hazards
Further mitigation measure
required
Compliance Status
IS01
1. RCC Manhole Steps Benching
Shoring should be done as required. Access and egress should be provided. Danger signs should be provided.
Shoring is not done. Access and egress ladder and danger signs are in place.
2. Fire and diseases in Labour Camp
First Aid to be provided with complete items. Easily washable floor and door that can be locked. Fire extinguish will be provided. Provision of separate kitchen and room.
Labor camp is still not in acceptable condition.
3. Vehicle movement during road reinstate work
Hard barricade should be provided Barricading is done with green net and caution tape.
4. Deep trenches during pipe laying
Shoring should be done for excavation greater than 1.5 m depth. Ladder for access and egress should be provided.
Shoring is not done. Access and egress ladder is provided.
5. Confined space: hazards during pipe cleaning works
Health checkup of workers should be done. Work permit system should be applied. Gas detector and masks should be provided. Air blower should be used whenever necessary. Full body harness should be used and a standby man should be recruited.
Health checkup of 9 workers who work in confined spaces has been done. Work permit system has been started. Gas detector is being used and air blower is not required until now.
IS02
1. Pipe Cleaning and Joint Improvement
Work Permit System should be applied as per the report of Health Check Up. Multiple Gas Detector should be used for gas detection. Air Blower should be used to circulate air inside pipes. Gas masks should be provided. Full body harness should be used.
Work permit system is started. Health checkup of worker has been done. Multiple gas detector is being used. Tripod and full body harness are used while working in confined spaces.
Semi-annual Environmental Monitoring Report July-December 2019
33 | P a g e
IS03
1. Confined space works: Outfall chamber cleaning, Pipe Cleaning, Leakage test & Pipe Sealing
Work permit system should be applied. Gas masks should be provided. Multiple Gas Detector should be used for gas detection Stretcher should be brought. Air Blower should be used to circulate air inside pipes Adequate light should be provided. Health checkup of workers should be done. Full body harness should be used and a standby man should be recruited.
Work permit system is started. Multiple gas detector is being used. Health checkup of worker is not done. Stretcher is not brought.
TP02
1. Scaffolding Work permit system should be applied. Deformed pipe should not be used. Scaffold inspection checklist shall be used and non-compliance should be corrected.
Work permit system is started. Deformed pipe are not used.
2. Excavation Shoring should be done as required. Benching, sloping method should be done as per the nature of the soil. Access and egress should be provided. Danger signs should be provided.
Benching, sloping method is used as per the nature of the soil. Access and egress is provided. Danger signs are placed
10.2 Training on OHS by ADB OHS consultant
OHS consultant of ADB has organized three OHS training sessions on Confined space work; Work
at height and scaffold; and Trenching and Excavation Safety on 3-5th September. The training was
given to the safeguard unit of PID, CASSC, DSC05, DSC06 and OHS representative of all the
contractors of PID. Again, two training sessions were organized on ‘Writing OHS contracts and BOQs’ and ‘Tools and Equipment Tagging’ on 23-24th October. The ‘Writing OHS contracts and BOQs’ training was given to those who are involved or had clear understanding in contract writing,
proposing and reviewing OHS BoQs. The ‘Tools and Equipment Tagging’ training was given to the
safeguard unit of PID, CASSC, DSC05, DSC06 and OHS representative of all the contractors of
PID. The attendance sheet of the 5 training is attached in Appendix 7. The total number of
participants along with number of male and female participant is given in
Semi-annual Environmental Monitoring Report July-December 2019
34 | P a g e
Table 10-2: Number of participants in different training
Topic of Training Total particiapants
Female participants
Male participants
Confined space work 35 9 26
Work at height and scaffold 37 8 29
Trenching and Excavation Safety 33 8 25
Writing OHS contracts and BOQs 40 8 32
Tools and Equipment Tagging 34 9 25
10.3 Training to the Labors
The people who attended the training given by OHS consultant of ADB needed to give the same
training on their respective site to at least 10 other people. All the contractors as well as DSC-06 has
conducted the training except IS-01. The person who took training has left his job and DSC-06 has
given the training on Work at height and scaffold and Trenching and Excavation Safety to the
workers of IS-01 and Sallaghari site of TP-02 on 30th September. The training was given to the
workers on the safety measures that should be applied while working in height and while doing
excavation works. The attendance sheet of the training is attached in Appendix 8. There were total
7 participants in the training from IS01 and 27 participants in the training from TP02 out of which
all 34 participants were male participants.
10.4 Meeting for Safeguard Compliance (OHS review meeting)
One day workshop on Safeguard Compliance was held on 27 August 2109 with the contractors
representing all packages of Wastewater Projects and representatives of PID, ADB, DSC and CASSC.
The workshop was held to know about the issues and problems of the contractor about the non-
compliance of the safeguard issues and make them aware about the importance of safeguard aspect of a
project. Total 49 participants were present in the review meeting out of which 10 were female participants
and 39 were male participants. The minutes of the meeting is attached in Appendix 9.
10.5 First Aid Training
DSC and CASSC in coordination with Nepal Res Cross Society has organized one day first aid
training on 15th December 2019 at Nepal Res Cross Society training hall, Soaltee mode, Tahachal.
13 participants from the contractors under loan 3000 had participated in the training. The training
covered the topics such as first aid introduction, Cardio Pulmonary Resuscitation (CPR) and
recovery position, big bleeding and shock, fractures lifting moving with full demo and practical.
OHS consultant of ADB suggested these topics to be covered during the training for the safety
in-charges working at sites. The attendance sheet is attached in Appendix 10. There were total 29
participants out of which 5 participants were female and 24 participants were male.
11 Grievance Redress Mechanism
A grievance redress mechanism (GRM) is established to receive, evaluate, and facilitate the
resolution of affected people’s concerns, complaints, and grievances about the social and
Semi-annual Environmental Monitoring Report July-December 2019
35 | P a g e
environmental performance of the project. The GRM aims to provide a trusted way to voice and
resolve concerns linked to the project, and to be an effective way to address affected people’s concerns. The GRM for the project is outlined below and consists of four levels with time-bound
schedules and specific persons to address grievances as shown in figure below.
Figure 11-1: Grievance Redress Mechanism (GRM)
Table 11-1: Grievances and complains reported. Sn Location Date Type of
grievance
Status Redress process Time line ( if
Pending)
1 Ram Mandir area
4 July, 2019/IS01
Re work start in Heritage area Bhaktapur
Solved Coordination with local ward office, CSE and Contractor and Survey office
NA
2 Barahi than 10 July, 2019/IS01
Availability of Grievance register in construction site
Solved Coordination with CSE and Contractor
NA
3 Sallaghari 14 July, 2019/IS01
Overflow manual restatement and crop compensation
Solved Coordination with local ward office, CSE and Contractor
NA
4 Bramayani Temple area
5 Aug, 2019/IS01
Gravel of Road and construction of river bank step
Solved Coordination with , CSE and Contractor
NA
5 Sallagharii area
5 Aug, 2019/IS01
Dust pollution due to road cutting
Solved Coordination with , CSE and Contractor
NA
6 Waard no 8 9 Sept, 2019/IS01
Overflow manual reinstatement of Road
Solved Coordination with local ward chairman , CSE and Contractor
NA
7 Sallaghari 2 Oct, 2019/IS01
Dust Pollution Solved Coordination with local ward office, CSE and Contractor
NA
Semi-annual Environmental Monitoring Report July-December 2019
36 | P a g e
8 Solid waste area
17 Oct, 2019/IS01
Crop compensation
Solved Coordination with local ward office, CSE and Contractor
NA
9 Sallaghari 3 Nov, 2019/IS01
Dust Pollution Solved Coordination with local ward office, CSE and Contractor
NA
10 Barahithan 7 Nov, 2019/IS01
Retaining wall and Crop compensation
Solved Coordination with local ward office, CSE and Contractor
NA
11 Maheshwori Ground
10 Nov, 2019/IS01
Crop compensation
Solved Coordination with local ward office, CSE and Contractor
NA
12 Sallaghari 12 Nov, 2019/IS01
Dust pollution, due to under construction road
Solved Coordination with local ward office, CSE and Contractor
NA
13 Barahithan 20 Nov, 2019/IS01
Crop compensation
Solved Coordination with local ward office, CSE and Contractor
NA
14 Maheshwori Ground
13 Dec, 2019/IS01
Request to wall construction
Solved Coordination with local ward office, CSE and Contractor
NA
15 Hanumanghat Area
25 Dec, 2019/IS01
Inceptor should be linked downstream of river for cultural festival
Solved Coordination with local ward office, CSE and Contractor
NA
12 Other Safeguard Related Activities Conducted During This Period
1. Safeguards Orientation Training to KUKL: 3 day safeguard orientation training was organized by KUKL/ADB on 20-22nd August in which safeguard unit of DSC-06 were used as a resource person to orient the staff of KUKL.
2. ToR of DEWATS: ToR for IEE of Decentralized Wastewater Treatment System at Gokarna and Hanumanghat (DEWATS) has been approved by the Ministry of Water Supply and Sanitation in this reporting period.
3. Audit follow up by ADB OHS consultant: In this reporting period, the major activity carried out was OHS audit by ADB OHS consultant. OHS consultant of ADB visited the sites of Loan 3000 to observe the OHS compliance/non-compliance status of the site. OHS audit has been done by the OHS consultant of ADB in 4 projects including IS-01 (audit done on 23rd August), IS-02 (audit done on 30th August), IS-03 (audit done on 1st September) and TP-02 (audit done on 22nd August). Based on the findings on each site, OHS consultant of ADB has recommended some major aspects that the contractors need to fulfill to improve the condition of OHS in their site. The recommendations are listed with target dates that the contractors must fulfill within the specified target dates. DSC followed up with the contractors and guide them to prepare the recommended documents.
Semi-annual Environmental Monitoring Report July-December 2019
37 | P a g e
4. Public notice was published in a newspaper: To carry out IEE of DEWATS, a public notice was published in a national daily newspaper named as ‘Gorkhapatra’ on 21 October 2019. The notice was published so that the opinions and suggestions from public people would be received within 15 days and that shall be included in the IEE report.
5. IEE public notice was affixed: To carry out IEE of DEWATS, public notice was affixed in the concerned ward offices, concerned municipalities, nearby school and nearby bank requesting their written opinions and suggestions within 15 days that includes the possible impact during the construction and implementation of DEWATS.
6. Submitted Geophysical Survey Report to DoA: Geophysical Survey along the pipe laying alignment of SN03 has been finished and the Survey Report has been submitted to DoA on 21 October 2019. The Survey report has been submitted so that the Heritage Impact Assessment (HIA) Report gets approved from DoA. The Survey report and Heritage Impact Assessment (HIA) Report is still in the review phase in DoA.
7. Solid Waste at Sallaghari: At Wastewater Treatment Plant (WWTP-02) Sallaghari, during the construction a waste accumulation has been detected. To assist the waste at site ADB deployed a solid waste expert. On site investigation was done on 2nd December on Sallaghari. The entire site was visited by joint team i.e. ADB, PID, DSC and Contractor. The ADB solid waste expert inspected the pit and excavated material. From the visual inspection and by checking the waste the material was seen as being widely stabilized and decomposed. The entire fill consists of plastic and fine material mostly sandy and clay. The smell was soil like material in upper zones which was relocated about a year ago was dry. ADB solid waste expert recommend for the verification of the rapid assessment. For this purpose the sample was collected from deeper area (test pit) and given for test at laboratory. After the result of the test report appropriate method for handling and placement (safe disposal) of waste will be suggested.
8. Automated Safeguard Performance Monitoring: Automated safeguard performance monitoring (ASPM) is web-based system for tracking performance and progress of safeguard planning and implementation activities in the projects and sub-projects. Implementing agencies will be able to update safeguard implementation records regularly and it will be easier to monitor the current state of activities of the project and sub-projects. The tracking system covers three safeguards components i.e. Environment, Resettlement and Indigenous people. There are 8 main safeguard indicators of the Environment Component i.e. 1) Safeguard Screening, 2) EIA/IEE/DDR, 3) Institutional Setup, 4) Recommendations and Endorsement, 5) Implementation Performance, 6) Corrective Action, 7) Safeguard Reporting and 8) Safeguard Covenants. Each indicator is assigned different points and their total point is 100. Implementation Performance weightage is 40 points. Different weights are also assigned to each key activity of sub-indicator. Similarly other Resettlement and Indigenous People components also have 8 main indicators. Automated safeguard performance monitoring software training was conducted by ADB consultant at PID. Safeguard unit, DSC and CASSAC participated in the training on 19th November 2019. In the ASPM system data entry was done and after that system was updated. On the basis of values assigned to each key activated the level of compliance of a project at different stages was analyzed. For this reporting period only safeguard for the environment component was updated. The result of automated safeguard performance monitoring software for environment component of sub-projects under loan-3000 KVWMP is attached in Appendix 13. Due to this ASPM training Safeguard unit, DSC and CASSAC are able to incorporate new skills into routine safeguard work.
Semi-annual Environmental Monitoring Report July-December 2019
38 | P a g e
13 Summary of Key Issues and Corrective Action
Table 13-1: List of key issues and corrective action S.N Key Issues Description Corrective Actions
1. Tree cut TP01 and IS02 has cut down trees during construction period.
IS02 has planted 200 trees and TP-01 has proposed to plant 180 trees.
2. Open Trenches Some trenches of IS01 and IS02 project are left open without barricade wall.
Contractors are instructed to install green nets/caution tape and also hard barricades where necessary. Safety signboards should also be kept at certain intervals. If the trench should be left open for a long period of time, it should be backfilled temporarily. These corrective actions are continuous process and should be done continuously.
3. Open Manholes Some manholes of IS sites are left uncovered.
Contractors are instructed to cover open manhole with appropriate cover and barricade them properly. Open manholes should be covered by the end of each day and should be done continuously.
4. Incomplete First Aid Box
The first aid box is not updated frequently. Only some items are found in the box.
First aid box should be improvised with complete items. The list of items that should be in the first aid box was provided to the contractor. This corrective action is a continuous process and should be done continuously.
5. Improper barricading along the construction sites
All the IS sites do not do proper barricading in all the construction sites.
Contractors were instructed to install green nets and also hard barricades where necessary. Safety signboards should also be kept at certain intervals. These corrective actions are continuous process and should be done continuously.
6. Improper Housekeeping
Housekeeping in the labor camp of TP02 (Dhobighat), IS01, IS03 is not good.
Contractors were instructed to maintain a safe and clean area. Working area and labor camp area should be cleaned regularly.
7. Incomplete use of PPEs
All required PPEs are often not worn by the workers and field staff.
Worker should wear complete PPEs (job specific PPEs) during construction works. PPEs should be worn before starting the construction works.
14 Status of Corrective Action Plan from Previous Reporting Period
Table 14-1: Status of Corrective Action Plan
S.N Action Planned in Previous Reporting Period Remarks
1. Incorporation of comments obtained from MoWS in IEE report of SN03.
Done.
2. Safeguard review meeting Done in September.
3. Onsite SEMP orientation Done.
4. Preparation and Submission of IEE of DEWATS Prepared and submitted to ADB.
Semi-annual Environmental Monitoring Report July-December 2019
39 | P a g e
5. Risk Hazard Assessment Done and will be continued.
6. Joint site inspection of all ongoing projects. Done and will be continued.
7. Regular Monitoring Done and will be continued.
15 Action Planned for Next Reporting Period
The next reporting period will focus on safeguard activities:
Table 15-1: List of action planned for next reporting period
S.N Description Responsible Unit Time Schedule
1. Preparation of IEE of DEWATS for GoN.
PID-SU/DSC/CASSC April (2nd week)
2. Update Environment Management Plan of SN03.
PID-SU/DSC/CASSC March (2nd-3rd week)
3. Update and submit IEE of Sallaghari WWTP
DSC/PID January (4th week)
4. Risk Hazard Assessment DSC/CASSC April (1st week)
5. Joint site inspection of all ongoing projects.
PID-SU, DSC and CASSC
Continuous (Once in each month)
6. Regular Monitoring DSC Continuous
Semi-annual Environmental Monitoring Report July-December 2019
40 | P a g e
16 APPENDIX
Appendix 1: Photographs
Figure: Temporary fencing completed in TP02
(Dhobightat)
Figure:Sign board placed in front of labor camp of TP03
Figure: Security guard hired in TP03.
Figure: Waste from labor camp taken to pig shed.
Figure: Shed for security guard made in TP02
Figure: Logbook to record name of the visitors in TP02.
Semi-annual Environmental Monitoring Report July-December 2019
41 | P a g e
Figure: Safeguard Compliance Review Workshop
Figure: Safeguards Orientation Training to KUKL
Figure: Practical training session during traing on
Confined space work. Figure: Work at height and Scaffold training session.
Figure: Training on OHS to the workers of IS-01 and TP-
02 by DSC
Figure: Training on OHS to the workers of IS-01 and TP-
02 by DSC
Semi-annual Environmental Monitoring Report July-December 2019
42 | P a g e
Figure: Training on Writing OHS contracts and BOQs
Figure: Training on Tools and Equipment Tagging
Figure: Tree plantation in upstream of Pepsi Cola Bridge
Figure: Tree plantation in downstream of Balkumari Bridge
Semi-annual Environmental Monitoring Report July-December 2019
43 | P a g e
Figure: Public notice published for collection of suggestions for DEWATS.
Figure: Constrution works going on in IS01
Figure: Field visit during ADB mission
Figure: Tools and Equipment Tagging done on IS02.
Figure: Tools and Equipment Tagging done on TP02.
Semi-annual Environmental Monitoring Report July-December 2019
44 | P a g e
Figure: Stretcher available in TP02.
Figure: Hard barricading done on TP02 for excavated
areas.
Figure: Beching method used for excavation in TP02.
Figure: Solid waste investigation by ADB expert in TP02.
Figure: Emergency number displayed in labor camp of
TP03.
Figure: Water is being sprayed in TP03 for dust
suppression.
Semi-annual Environmental Monitoring Report July-December 2019
45 | P a g e
Figure: First aid room made in TP03.
Figure: Green and red signage used in TP03
Figure: Confined Space training in TP01.
Figure: Lifesaving tube kept in TP01.
Semi-annual Environmental Monitoring Report July-December 2019
46 | P a g e
Figure: Landscaping work going on in TP01. Figure: Tree plantation being done in TP01.
Figure: Sample of monitoring noise level of different equipment
Figure: Contractor safety workers performing CPR practical
during first aid training.
Figure: Contractor safety workers performing big
bleeding and shock practical during first aid training.
Semi-annual Environmental Monitoring Report July-December 2019
47 | P a g e
Appendix 2: Road Cut Permit
Road Cut Permit taken by IS-03
Semi-annual Environmental Monitoring Report July-December 2019
48 | P a g e
English Translation of Road Cut Permit
Department of Roads, Bhaktapur
Date: 2076/06/08
(25 September 2019)
Subject: Regarding Reinstatement of Road
Kathmandu Upatyaka Khanepani Limited,
Project Implementation Directorate
Kathmandu Valley Water and Wastewater Projects
Anamnagar, Kathmandu.
In reference to above subject, as per the permission to cut the road from this division in Bhaktapur
municipality ward no 2 and chagunarayan municipality ward no 3 near the bridge in Kalighat, the pipe
laying works is going on. In this regard a letter has been issued with ref no 075/76/686 dated 2075/12/19
(17 March 2019) stating certain condition to cut the road and now you are aslo requested to reinstate
the pavement wearing coat (asphalt concrete), side drain, foothpath, etc and maintain the condition as
before.
Semi-annual Environmental Monitoring Report July-December 2019
50 | P a g e
English Translation of Road Cut Permit
Department of Roads, Bhaktapur
Date: 2075/12/19
(02 April 2019)
Subject: Laying of sewer pipe
Kathmandu Upatyaka Khanepani Limited,
Project Implementation Directorate
Kathmandu Valley Water and Wastewater Projects
Anamnagar, Kathmandu.
In reference to above subject, we have received a letter with reference number 075/76/850 dated
2075/12/11 (25 March 2019) asking for the permission to cut the road in both side of the bridge in
Kalighat, Jhaukhel for the laying of sewer pipe with 500 mm diameter. In this regard, we permit you
to cut the road but the conditions listed below should be fulfilled accordingly.
Conditions:
1. Public people and the vehicles in the the road should not be obstructed.
2. Excavated soil and material while cutting the road should be stockpiled in safe place.
3. This road cut permit is given only to cut the estimated area.
4. After the laying of the sewer pipe, the excavated trench should be backfilled and compacted
properly so that vehicles can move. And the remaining soil should be disposed in proper place.
5. Road Safety should be considered while doing the construction works.
6. If the road cut should be done outside the estimated area, then road cut permit should be taken
again.
7. Works should be done within the boundary of Standard Specification of Department of Roads.
8. The road shall be reinstated as it was before.
9. After finishing the works, the information should be given to Department of Roads.
Semi-annual Environmental Monitoring Report July-December 2019
51 | P a g e
Appendix 3: Package wise Contractor’s Nodal person for Environmental Safeguard
S.N Sub-Project Name Nodal Person (HSE
officer)
Contact Details
1. KUKL/WW/TP-01 Mohammed Mashoom Email: [email protected] Contact no: 9823094090
2. KUKL/WW/TP-02 1. Narayan Gnawali (HSE coordinator) 2. Dharma Raj Thapa (HSE officer: Dhobighat) 3. Manish Giri (HSE officer: Kodku) 4. Pratik Phuyal (HSE officer: Sallaghari)
1. Email: [email protected] Contact no: 9851188288 2. Email: [email protected] Contact no: 9842382023 3. Email: [email protected] Contact no: 9842538887 4. Email: [email protected] Contact no:
3. KUKL/WW/TP-03 Khusmita Dangol Email: [email protected]
Contact no: 9801904894
4. KUKL/WW/IS-01 Eak Raj Shakya Email: [email protected]
5. KUKL/WW/IS-02 Neyaz Alam Email: [email protected]
Contact no: 9801240970
6. KUKL/WW/IS-03 Ebin Shrestha Contact no: 9801140074
Semi-annual Environmental Monitoring Report July-December 2019
52 | P a g e
Appendix 4: Attendance sheet of Tree Plantation
Tree Plantation (1st Phase)
Semi-annual Environmental Monitoring Report July-December 2019
54 | P a g e
Tree Plantation (2nd Phase)
Semi-annual Environmental Monitoring Report July-December 2019
55 | P a g e
Appendix 5: Minutes of Meeting
Public Consultation at Gueshwori (TP-01)
A public discussion was organized on Gueshwori WWTP (TP-01) on 26th November 2019 about the Wastewater treatment plant and Kathmandu valley
wastewater management project with the people of ward no 8 of Kathmandu metropolitan city. It was also discussed that the construction works will
be done mitigating the possible environmental impact and addressing and solving the grievance of the public.
Semi-annual Environmental Monitoring Report July-December 2019
56 | P a g e
Public Consultation at Sallaghari (TP-02)
A public discussion was organized on Sallaghari WWTP (TP-02) on 4th December 2019 about the Wastewater treatment plant and Kathmandu valley
wastewater management project with the people of ward no 2 of Bhaktapur metropolitan city. It was decided that the construction works will be done
mitigating the possible environmental impact and addressing and solving the grievance of the public.
Semi-annual Environmental Monitoring Report July-December 2019
57 | P a g e
Public Consultation in Hanumanghat (DEWATS) A public discussion was organized on Ward office of ward no 7 of Bhaktapur Municipality on 5th December 2019 about the Decentralized Wastewater Treatment System and Kathmandu valley wastewater management project with the people of ward no 7 of Bhaktapur Municipality. It was decided that the construction works will be done mitigating the possible environmental impact and addressing/solving the grievance of the public.
Semi-annual Environmental Monitoring Report July-December 2019
59 | P a g e
Appendix 6: Sample Checklist Of Hazard Identification Risk Assessment
Hazard identification risk assessment checkist of IS-03
Semi-annual Environmental Monitoring Report January-June 2019
61 | P a g e
Appendix 7: Attendance sheet of the training given by ADB OHS consultant
Semi-annual Environmental Monitoring Report January-June 2019
66 | P a g e
Appendix 8: Attendance sheet of the training given by DSC
Semi-annual Environmental Monitoring Report January-June 2019
68 | P a g e
Appendix 9: Minutes of meeting of Safeguard Compliance (OHS review meeting)
Semi-annual Environmental Monitoring Report January-June 2019
70 | P a g e
Appendix 10: Attendance sheet of First Aid training
Semi-annual Environmental Monitoring Report January-June 2019
Appendix 11: Some Filled Safety Checklists for Different Projects.
Environmental monitoring checklist of IS-01
Semi-annual Environmental Monitoring Report January-June 2019
Environmental monitoring checklist of IS-02
Semi-annual Environmental Monitoring Report January-June 2019
Environmental monitoring checklist of TP-01
Semi-annual Environmental Monitoring Report January-June 2019
Environmental monitoring checklist of TP-02 (Kodku)
Semi-annual Environmental Monitoring Report January-June 2019
Environmental monitoring checklist of TP-02 (Dhobighat)
Semi-annual Environmental Monitoring Report January-June 2019
Environmental monitoring checklist of TP-02 (Sallaghari)
Semi-annual Environmental Monitoring Report January-June 2019
Environmental monitoring checklist of TP-03
Semi-annual Environmental Monitoring Report January-June 2019
Scaffold inspection checklist of TP02
Trenching and Excavation inspection checklist of TP02
Semi-annual Environmental Monitoring Report January-June 2019
Trenching and Excavation inspection checklist of TP03
Trenching and Excavation inspection checklist of TP03
Semi-annual Environmental Monitoring Report January-June 2019
Appendix 12: Sample Site Inspection Report
1. Interceptor Sewer (IS-02); Balkumari 19th August 2019
Environmental monitoring checklist was filled to
analyze the environmental compliance status at
IS-02 at Balkumari. In general, the environment
compliance status of manhole construction from
the contractor (ZIEC-Sharma-Bkoi JV) is not
satisfactory.
The obtained score for the environmental
compliance is 26 out of total score 61 (42%).
This scoring represent the environment
compliance is not satisfactory.
Major Recommendation from the monitoring team
• Complete project information board should be in place with the name & contact address
of contractor, type of work, start & completion date.
• PPE should be provided to all workers
• Even though site is closed local people are using are walking around so manhole should
be barricade with green net
• Help desk and grievance register book should be at work site.
• FAB should be available at site
Manhole near Site office
Signage Health & Safety Site cleanliness &
Housekeeping
GRM Damage / repairs
❖ Project information board was not in place.
❖ PPE was not used by workers (Half were in PPE and half of them were without PPE) ❖ Green net & cautionary ribbon was not done for the manhole ❖ Drinking water was available at site in small bottle ❖ FAB was not available at site.
❖ Work is ongoing along the river bank. Excavated soil is around the manhole
❖ Help desk & GRM register was not available at site.
❖ No major issue
Semi-annual Environmental Monitoring Report January-June 2019
Chamber cleaning work is ongoing near IS-02 site office. Three workers are cleaning the
chamber and there was no presence of safety office and site supervisor at site. As per worker’s tool box talk was not done before
entering in the chamber so there were not
aware of possible risk while working at
chamber. Due to absence of proper
lighting system they were working with
mobile light. PPE was not used by all
workers. Ladder was not used at site.
So from the environment compliance
point of view work is conducted under
highly risk environment. The situation
was discussed with ASE and the site was
closed and instructed to resume only after
having all safety precautions.
Semi-annual Environmental Monitoring Report January-June 2019
2. Field Visit Report
To: Chief, Safeguard Unit, KUKL/PID
From: Pramila Adhikari, Sociologist
Visiting Team: Pushpa Koirala Environment Expert CASSC; Yadab Singh SM CASSC
Date: 2076/08/26
Reference no: 16
Site visited with project name, observation and further action
1. Balkumari IS-02 Observation
• Workers without complete PPEs
• Frist Aid box and Drinking water was not seen
• Information board not seen
• Not any safety precaution, Full body harness was not use at site
• No gas detection, no work permit, no trained rescue team
Semi-annual Environmental Monitoring Report January-June 2019
Further action
• Worker Should wear complete PPEs.
• Full body harness compulsory use doing work.
• FAB should be at site
• Multi gas detection should be done
• Safety officer should be available at site
Working condition is not satisfactory so work should stop
immediately
Semi-annual Environmental Monitoring Report January-June 2019
Appendix 13: Automated Safeguard Performance Monitoring Scoring