PT SAHID PUTRA HARAPANPROYEK : Sudirman Square
ALAMAT : JL. Jendral Sudirman No. 5, Sungailiat, Bangka Belitung
PEMBAYARAN OPNAME SEWA ALAT BERATTanggal 14-Apr-2015
Minggu Ke 9
Periode 12 Apr 2015 - 18 Apr 2015
Sub Upah/Sub Kontraktor Pak Haji Yadin Progress Opname
No. No. SPK Bangunan Pekerjaan Volume Satuan Harsat Jumlah
S/d
Minggu
Lalu
Minggu
Ini
S/d
Minggu
ini
Minggu ini Minggu Lalu
1 001.SU : Ruko 1-8/Sudirman Square/SPH/II/2015 -01 KantorKantor Marketing, Pagar Seng dan
Bowplank 1.00 Ls 10,682,778.00 10,683,000.00 81.33% 18.68% 100.01% 1,995,578.00 8,688,200.00
2 001.SU : Ruko 1-8/Sudirman Square/SPH/II/2015 -02 Pagar Keliling Pondasi 1.00 Ls 16,441,730.00 16,442,000.00 0.00% 0.00% 0.00% - -
3 001.SU : Ruko 1-8/Sudirman Square/SPH/II/2015 -03 Pagar Keliling Slope dan Kolom 1.00 Ls 2,745,994.68 2,746,000.00 0.00% 0.00% 0.00% - -
4 001.SU : Ruko 1-8/Sudirman Square/SPH/II/2015 -04 Pagar Keliling Dinding Bata, plester dan Aci 1.00 Ls 17,545,200.00 17,545,000.00 0.00% 0.00% 0.00% - -
5 001.SU : Ruko 1-8/Sudirman Square/SPH/II/2015 -05 Ruko 1 - 8 Pondasi Tapak 1.00 Ls 48,177,416.95 48,177,000.00 93.32% 5.67% 98.99% 2,730,000.00 44,958,685.00
6 001.SU : Ruko 1-8/Sudirman Square/SPH/II/2015 -06 Ruko 1 - 8Struktur Kolom, Balok, Slope, Lantai dan
Tangga 1.00 Ls 296,316,587.70 296,317,000.00 3.24% 3.61% 6.85% 10,698,853.09 9,607,503.52
7 001.SU : Ruko 1-8/Sudirman Square/SPH/II/2015 -07 Ruko 1 - 8 Dinding Hebel, Plester dan Aci 1.00 Ls 222,765,947.60 222,766,000.00 0.00% 0.42% 0.42% 940,500.00 -
8 001.SU : Ruko 1-8/Sudirman Square/SPH/II/2015 -08 Ruko 1 - 8Pasang Keramik lantai dan, Tangga dan
Kamar mandi 1.00 Ls 96,017,475.30 96,017,000.00 0.00% 0.00% 0.00% - -
9 001.SU : Ruko 1-8/Sudirman Square/SPH/II/2015 -09 Ruko 1 - 8 Cat dinding, plafond dan Waterproofing 1.00 Ls 71,096,356.75 71,096,000.00 0.00% 0.00% 0.00% - -
10 001.SU : Ruko 1-8/Sudirman Square/SPH/II/2015 -10 Ruko 1 - 8 Septictank 1.00 Ls 25,402,680.00 25,403,000.00 63.58% 0.00% 63.58% - 16,152,050.00
11 001.SU : Ruko 1-8/Sudirman Square/SPH/II/2015 -11 Ruko 1 - 8Stager, Lisplank, Waterproofing dan
Flashing 1.00 Ls 17,291,586.00 17,292,000.00 0.00% 0.00% 0.00% - -
12
GRAND TOTAL 824,484,000.00 16,364,931.09 79,406,438.52
A. PROGRESS MINGGU INI Rp 16,364,931
B. PROGRESS MINGGU LALU Rp 79,406,439
C. RETENSI PROGRESS MINGGU INI 5% ( A x 5% ) Rp 818,247
D. TOTAL RETENSI SAMPAI DENGAN MINGGU LALU ( B x 5% ) Rp 3,970,322
E. JUMLAH YANG HARUS DIBAYAR S/D MINGGU INI ( A x 95% ) {nilai di genapkan kebawah 3 digit} Rp 15,546,000
F. SISA PEMBAYARAN SPK ( Nilai SPK - A - B + C + D ) Rp 733,501,199
SUNGAILIAT-BANGKA, 14 Apr 2015
Keuangan Kantor
( Ahmad Fahmi )
Site Manager
( Mulyono )
Administrasi Proyek
( Harry Archandy )
Pihak Sub Upah/. Subkont
(_H. Yadin )
Divisi Konstruksi
( Agung W )
Direktur Operasional
( Tjandra Poernama )