Rab Masjid Unaaha Baru

88
REKAPITULASI HARGA NO. URAIAN PEKERJAAN 1 2 I PEKERJAAN TANAH , PASIR DAN BATU II PEKERJAAN BETON III PEKERJAAN PEMASANGAN TEGEL IV PEKERJAAN DINDING, PLESTERAN DAN PROFIL V PEK. KUSEN PINTU, JENDELA, PLAFOND, KACA DAN ALAT PENGGANTUNG VI PEKERJAAN KUDA-KUDA/KAP DAN PENUTUP ATAP VII PEKERJAAN FINISHING REAL COST (A) PPN 10 % x A IMB 2 % x A TOTAL COST DIBULATKAN TERBLANG : LIMA RATUS EMPAT PULUH EMPAT JUTA RUPIAH

description

Rencana Anggaran Biaya

Transcript of Rab Masjid Unaaha Baru

Page 1: Rab Masjid Unaaha Baru

REKAPITULASI HARGA

NO. URAIAN PEKERJAAN JUMLAH HARGA (RP)

1 2 3

I PEKERJAAN TANAH , PASIR DAN BATU Rp 106,838,978.86 II PEKERJAAN BETON Rp 65,418,456.11 III PEKERJAAN PEMASANGAN TEGEL Rp 38,541,638.14 IV PEKERJAAN DINDING, PLESTERAN DAN PROFIL Rp 64,523,346.48 V PEK. KUSEN PINTU, JENDELA, PLAFOND, KACA DAN ALAT PENGGAN Rp 18,270,512.45 VI PEKERJAAN KUDA-KUDA/KAP DAN PENUTUP ATAP Rp 171,157,698.46 VII PEKERJAAN FINISHING Rp 21,230,777.90

REAL COST (A) Rp 485,981,408.40 PPN 10 % x A Rp 48,598,140.84 IMB 2 % x A Rp 9,719,628.17

TOTAL COST Rp 544,299,177.40 DIBULATKAN Rp 544,299,177

TERBLANG : LIMA RATUS EMPAT PULUH EMPAT JUTA RUPIAH

Page 2: Rab Masjid Unaaha Baru

RENCANA ANGGARAN BIAYA

NO Uraian Pekerjaan Satuan VolumeHarga Satuan Jumlah Harga

(Rp) (Rp)

1 2 3 4 5 6

I PEKERJAAN PENDAHULUAN

1 Pek. Pengukuran dan pemasangan Bowplank Ls 38,766.60 - 2 Pembuatan Barak Kerja dan Gudang 1.00 1,056,253.40 1,056,253.40 3 Pengerjaan Pembersiha lokasi 1.00 3,614.00 3,614.00 4 Timbunan Tanah 1,750.00 73,900.00 129,325,000.00

SUB TOTAL ( I ) 130,384,867.40 II PEKERJAAN TANAH , PASIR DAN BATU

1 Pek. Galian Pondasi Batu Gunung dlm 1m 122.90 50,360.00 6,189,244.00 2 Pek. Urugan Pasir 30.08 253,748.00 7,632,739.84 3 Pek. Pasangan Batu Kosong 29.44 460,512.46 13,557,486.88 4 Pek. Pemasangan Pondasi Batu Gunung 1 PC : 3 PP 67.70 917,047.70 62,084,129.29 5 Pek. Peninggian Lantai Bangunan 76.80 217,528.00 16,706,150.40 6 Pek. Urugan Kembali 39.87 16,786.67 669,228.4

SUB TOTAL ( II ) 106,838,978.86

III PEKERJAAN BETON

1 Pek. Sloof 20x40 cm (150 kg + Bekisting) 5.52 5,616,382.20 31,002,429.74 2 Pek. Kolom 20 x 20 Cm 1pc : 2psr : 3krl (150Kg + Bekisting) 3.60 7,118,882.20 25,627,975.92 3 Pek. Kolom Praktis 1pc : 2psr : 3krl (150 Kg + Bekisting) 48.00 106,960.55 5,134,106.30 4 Pek. Ring Balok Beton Betulang 15 x 15 cm 6.72 129,402.64 869,585.74 5 Pek lantai kerja 1Pc : 3Psr : 5Krl 12.80 217,528.00 2,784,358.40

SUB TOTAL ( II ) 65,418,456.11

IV PEKERJAAN PEMASANGAN TEGEL

1 Pek. Pasangan Tegel 40 x 40 cm M² 256.00 150,553.27 38,541,638.14

SUB TOTAL ( III ) 38,541,638.14

V PEKERJAAN DINDING, PLESTERAN DAN PROFIL

1 Pek Dinding Tembok 1/2 Bata 1Pc : 3Psr 297.42 110,620.64 32,900,790.75 2 Pek Plesteran Tembok, 1Pc : 3Psr 594.84 53,161.45 31,622,555.73

SUB TOTAL ( IV ) 64,523,346.48 VI PEK. KUSEN PINTU, JENDELA, PLAFOND, KACA DAN ALAT PENGGANTUNG

1 Pek. Kusen Pintu P1 kayu kelas II Unit 0.18 6,938,716.40 1,259,897.43 2 Pek. Kusen Jendela J1 kayu kelas II Unit 0.60 6,938,716.40 4,134,087.23 3 Pek. Pintu Klamp Sederhana Kayu kelas III M2 7.56 498,119.40 3,765,782.66 4 Pek. Jendela M2 7.56 498,119.40 3,765,782.66 5 Engsel Pintu Unit 18.00 18,800.00 338,400.00 6 Engsel Kupu-Kupu Unit 72.00 11,200.00 806,400.00 7 Kunci Tanam Antik Unit 3.00 136,700.00 410,100.00

M2

M2

M3

M3

M3

M3

M3

M3

M5

M3

M3

M¹M¹M3

M2

M2

Page 3: Rab Masjid Unaaha Baru

8 Grendel Jendela Unit 36.00 5,600.00 201,600.00 9 Kait Angin Unit 18.00 9,400.00 169,200.00

10 Pek. Plafond M2 256.00 13,356.49 3,419,262.46

SUB TOTAL ( V ) 18,270,512.45

VII PEKERJAAN KUDA-KUDA/KAP DAN PENUTUP ATAP

1 Pekerjaan Kuda-Kuda Kayu Kls II 8/12 4.40 6,309,477.60 27,760,893.83 2 Pekerjaan Gordeng Kayu Kls II 6/12 2.26 5,700,486.56 12,854,825.21 3 Pekerjaan Rangka Atap kayu Kls II 403.96 192,365.98 77,707,199.45 4 Pasangan Atap Sakura Roof 403.96 87,358.98 35,289,096.77 5 Pas. Bumbungan Atap Sakura Roof 63.20 68,264.32 4,314,305.02 6 Pas. Listplank Kayu Klas II 110.40 119,849.44 13,231,378.18

SUB TOTAL ( VI) 171,157,698.46

VIII PEKERJAAN FINISHING

1 Pek. Pengecatan Tembok M2 594.84 35,691.58 21,230,777.90

SUB TOTAL ( VI) 21,230,777.90

M3

M3

M2

M2

M1

M1

Page 4: Rab Masjid Unaaha Baru
Page 5: Rab Masjid Unaaha Baru

DAFTAR HARGA SATUAN PEKERJAAN

NO KODE URAIAN ANALISA HARGA SATUAN a b c d

A. PEKERJAAN PERSIAPAN

1 A.01 1 M1 Pengukuran Dan Pemasangan Bouwplank Rp 38,766.60 2 A.02 1 M2 Pembuatan Barak Kerja Dan Gudang Rp 1,056,253.40 3 A.03 1 M2 Pekerjaan Pembersihan Lokasi (Stripping) Rp 3,614.00

B. PEKERJAAN TANAH DAN PASIR

2 B.01 Memadatkan 1 m3 tanah (per 20 cm) Rp 36,140.00 3 B.02 Menggali 1 m3 tanah biasa sedalam 1 meter Rp 50,360.00 4 B.03 Menggali 1 m3 tanah lumpur sedalam 1 meter Rp 80,961.00 5 B.04 Membuang 1 m3 tanah sejauh 30 meter Rp 22,081.40 6 B.05 Mengurug kembali 1 m3 galian Rp 16,786.67 7 B.06 Memadatkan 1 m3 tanah (per 20 cm) Rp 36,140.00 8 B.07 Mengurug 1 m3 tanah urug Rp 108,824.00 9 B.08 Mengurug 1 m3 pasir urug Rp 253,748.00

10 B.09 Mengurug 1 m3 sirtu padat untuk peninggian lantai bangunan Rp 217,528.00

C. PEKERJAAN PONDASI

1 C.01 Memasang 1 m3 pondasi batu gunung, campuran 1 PC : 3 PP Rp 917,047.70 2 C.02 Memasang 1 m3 batu kosong (aanstamping) Rp 460,512.46 3 C.03 Memasang 1 m3 pondasi Sumuran dia 100 cm Rp 1,192,239.40

D. PEKERJAAN BETON

1 D.01 Membuat 1 m3 beton (K 150) Rp 1,147,800.51 2 D.02 Membuat 1 m3 pondasi beton bertulang ( 150 Kg besi + bekisiting ) Rp 5,616,090.01 3 D.03 Membuat 1 m3 sloof beton bertulang ( 150 Kg besi + bekisiting ) Rp 5,616,382.20 4 D.04 Membuat 1 m3 kolom beton bertulang ( 150 Kg besi + bekisiting ) Rp 7,118,882.20 5 D.05 Membuat 1 m3 balok beton bertulang ( 150 Kg besi + bekisiting ) Rp 7,196,695.40 6 D.06 Membuat 1 m3 Plat beton bertulang ( 200 Kg besi + bekisiting ) Rp 7,632,708.10 7 D.07 Membuat 1 m1 kolom praktis beton bertulang ( 11 x 11 ) cm Rp 106,960.55

D.08 Membuat m1 Ring Balok Beton Bertulang Rp 129,402.64

E. PEKERJAAN DINDING

1 E.01 Memasang 1 m2 dinding bata merah 1/2 bata, campuran 1 PC : 2 PP Rp 117,924.06 2 E.02 Memasang 1 m2 dinding bata merah 1/2 bata, campuran 1 PC : 3 PP Rp 110,620.64

Page 6: Rab Masjid Unaaha Baru

F. PEKERJAAN PLESTERAN

1 F.01 Memasang 1 m2 plesteran 1 PC : 3 PP, tebal 15 mm Rp 53,161.45 2 F.02 Memasang 1 m2 dinding Batu tempel hitam Rp 563,188.82 3 F.03 Memasang 1 m1 Saluran air hujan keliling bangunan dalam 30 cm Rp 144,160.14 4 F.04 Memasang 1 m2 Pelicinan dengan Air Semen Rp 22,813.97 5 F.05 Membuat 1 m1 Profil Tembok Rp 50,099.96

G. PEKERJAAN KAYU

1 G.01 Membuat dan memasang 1m3 kusen pintu & kusen jendela, kayu kelas I Rp 7,436,835.80 2 G.02 Membuat dan memasang 1m3 kusen pintu & kusen jendela, kayu kelas II Rp 6,938,716.40 3 G.03 Membuat dan memasang 1m2 daun pintu klamp sederhana kelas III Rp 489,119.40 4 G.04 Membuat dan memasang 1m2 pintu dan jendela kaca, kayu kelas I atau II Rp 498,119.40 5 G.05 Memasang 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III Rp 6,309,477.60 6 G.06 Memasang 1 m3 konstruksi gordeng, kayu kelas II Rp 5,700,486.56 7 G.07 Memasang 1 m2 rangka atap, kayu kelas II Rp 192,365.98 8 G.08 Memasang 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II Rp 111,854.94 9 G.09 Memasang 1 m1 lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II Rp 119,849.44

10 G.10 Memasang 1 M2 Bingkai Jendela/Pintu Rp 381,203.60

H. PEKERJAAN LANTAI

1 H.01 Memasang 1 m2 lantai tegel keramik putih ukuran (40 x 40) cm Rp 150,553.27 2 H.02 Memasang 1 m2 lantai tegel keramik Warna Corak ukuran (40 x 40) cm Rp 152,210.77 3 H.03 Memasang 1 m2 lantai tegel keramik putih ukuran (30 x 30) cm Rp 144,876.99 4 H.04 Memasang 1 m2 lantai tegel keramik Warna Corak ukuran (30 x 30) cm Rp 145,848.17 5 H.05 Memasang 1 m2 lantai tegel Anti Sleep ukuran (20 x 20) cm Rp 461,928.10 6 H.06 Memasang 1 m2 dinding tegel keramik ukuran (20 x 25) cm Rp 200,866.05 7 H.07 Memasang 1 m2 dinding Batu tempel hitam Rp 563,188.82

I. PEKERJAAN LANGIT-LANGIT

1 I.01 Memasang 1 m2 langit-langit tripleks Rp 42,411.48 2 I.02 Memasang 1 m2 langit-langit Gypsum board, tebal 9 mm permukaan rata Rp 43,003.88 3 I.03 1 M2 Langit-langit Triplek 3 mm + Rangka Kayu Kls II Rp 175,815.02

J. PEKERJAAN PENUTUP ATAP

1 J.01 Memasang 1 m2 atap sakura roof Rp 87,358.98 2 J.02 Memasang 1 m1 nok atap sakura roof Rp 68,264.32

K. PEKERJAAN FINISHING DAN PENGECETAN

Page 7: Rab Masjid Unaaha Baru

1 K.01 Pengecetan 1 m2 Tembok baru (1 lapis cat dasar, 2 lapis cat penutup) Rp 35,691.58 2 K.02 Pengecetan 1 m2 bidang kayu baru Rp 24,580.90 3 K.03 Pengecetan 1 m2 Plafond (langit-langit) Rp 13,356.49 4 K.04 1 M2 Mendempul dan Menggosok Kayu Rp 10,058.89

L. PEKERJAAN PENGGANTUNG DAN KACA

1 L.01 1 Buah Pasang Kunci Tanam Biasa Rp 180,449.80 2 L.02 1 Buah Pasang Engsel Pintu Rp 33,814.80 3 L.03 1 Buah Pasang Engsel Jendela Kupu-kupu Rp 21,207.30 4 L.04 1 Buah Pasang Kait Angin Rp 24,414.80 5 L.05 1 Buah Pasang Door Closer Rp 206,736.50 6 L.06 1 M2 Pasang Kaca , tebal 5 mm Rp 141,404.80 7 L.07 1 BH Pasang Grendel Pintu/Jendela Rp 25,614.60

M. PEKERJAAN SANITAIR

1 M.01 Pemasangan 1 Unit Septictank Uk. 2 x 2 x 1,5 m + Peresapan Rp 5,266,727.73 2 M.02 Pemasangan 1 Bh Bak Kamar Mandi Fiberglass 1 M3 Rp 905,605.00 3 M.03 Memasang 1 bh Closed duduk Rp 540,386.40 4 M.04 Memasang 1 bh Floor drain Rp 39,918.80 5 M.05 Memasang 1 m1 Pipa PVC type AW dia 3/4" Rp 44,558.28 6 M.06 Memasang 1 bh kran dia. 3/4" Rp 47,668.80 7 M.07 Rp -

N. PEKERJAAN INSTALASI LISTRIK

1 N.01 1 m' Pekerjaan Pemasangan Jalur Kabel Utama Rp 18,264.02 2 N.02 1 ttk Pekerjaan Pemasangan MCB Pembatas Rp 294,664.12 3 N.03 1 Bh Pekerjaan Pemasangan saklar Ganda Rp 88,114.12 4 N.04 1 Bh Pekerjaan Pemasangan Stop Kontak Rp 50,864.12 5 N.05 1 ttk Pekerjaan Pentanahan (Grounding) Rp 82,064.12 6 N.06 1 ttk Pekerjaan Penangkal Petir Rp 1,295,064.12

Page 8: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

A. PEKERJAAN PERSIAPAN

A.01 1 M1 Pengukuran Dan Pemasangan Bouwplank

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Kayu Balok 5/7 M3 0.007 4,000,000 28,000.00

Paku Campur Kg 0.020 20,000 400.00

Papan Kelas III M3 0.003 3,500,000 8,750.00

Tenaga Kerja

Pekerja OH 0.010 64,580 645.80

Tukang Kayu OH 0.010 83,490 834.90

Kepala Tukang OH 0.001 97,398 97.40

Mandor OH 0.0005 77,000 38.50

Jumlah harga per-satuan pekerjaan 38,766.60

A.02 1 M2 Pembuatan Barak Kerja Dan Gudang

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Dolken Kayu Btg 1.700 8,300 14,110.00

Papan Kls III M3 0.210 3,500,000 735,000.00

Paku Biasa Kg 0.300 19,800 5,940.00

Semen Poortland Zak 0.210 82,200 17,262.00

Pasir Pasang M3 0.030 236,710 7,101.30

Pasir Beton M3 0.050 236,710 11,835.50

Seng Gelombang Bljs 20 Kaki 8.500 9,900 84,150.00

Tenaga Kerja

Pekerja OH 0.500 64,580 32,290.00

Tukang Kayu OH 1.500 83,490 125,235.00

Kepala Tukang OH 0.200 97,398 19,479.60

Mandor OH 0.0500 77,000 3,850.00

Jumlah harga per-satuan pekerjaan 1,056,253.40

A.03 1 M2 Pekerjaan Pembersihan Lokasi (Stripping)

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Tenaga KerjaPekerja OH 0.050 64,580 3,229.00

Mandor OH 0.0050 77,000 385.00

Jumlah harga per-satuan pekerjaan 3,614.00

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 9: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

B. PEKERJAAN TANAH DAN PASIR

B.02 Memadatkan 1 m3 tanah (per 20 cm)

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Tenaga KerjaPekerja OH 0.500 64,580 32,290.00

Mandor OH 0.050 77,000 3,850.00

Jumlah harga per-satuan pekerjaan 36,140.00

B.03 Menggali 1 m3 tanah biasa sedalam 1 meter

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Tenaga KerjaPekerja OH 0.750 64,580 48,435.00

Mandor OH 0.025 77,000 1,925.00

Jumlah harga per-satuan pekerjaan 50,360.00

B.04 Menggali 1 m3 tanah lumpur sedalam 1 meter

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Tenaga KerjaPekerja OH 1.200 64,580 77,496.00

Mandor OH 0.045 77,000 3,465.00

Jumlah harga per-satuan pekerjaan 80,961.00

B.05 Membuang 1 m3 tanah sejauh 30 meter

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Tenaga KerjaPekerja OH 0.330 64,580 21,311.40

Mandor OH 0.010 77,000 770.00

Jumlah harga per-satuan pekerjaan 22,081.40

B.06 Mengurug kembali 1 m3 galian

Mengurug kembali 1 m3 galian dihitung dari 1/3 kali indeks pekerjaan galia 16,786.67

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 10: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

B.07 Memadatkan 1 m3 tanah (per 20 cm)

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Tenaga KerjaPekerja OH 0.500 64,580 32,290.00

Mandor OH 0.050 77,000 3,850.00

Jumlah harga per-satuan pekerjaan 36,140.00

B.08 Mengurug 1 m3 tanah urug

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan Tanah Urug m3 1.200 73,900 88,680.00

Tenaga KerjaPekerja OH 0.300 64,580 19,374.00

Mandor OH 0.010 77,000 770.00

Jumlah harga per-satuan pekerjaan 108,824.00

B.09 Mengurug 1 m3 pasir urug

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan Pasir Urug m3 1.200 194,670 233,604.00

Tenaga KerjaPekerja OH 0.300 64,580 19,374.00

Mandor OH 0.010 77,000 770.00

Jumlah harga per-satuan pekerjaan 253,748.00

B.10 Mengurug 1 m3 sirtu padat untuk peninggian lantai bangunan

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan Sirtu m3 1.200 166,215 199,458.00

Tenaga KerjaPekerja OH 0.250 64,580 16,145.00

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 11: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

Tenaga KerjaMandor OH 0.025 77,000 1,925.00

Jumlah harga per-satuan pekerjaan 217,528.00

C. PEKERJAAN PONDASI

C.01 Memasang 1 m3 pondasi batu gunung, campuran 1 PC : 3 PP

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Batu Gunung m3 1.200 238,900.00 286,680.00

Portland Cement Kg 202.000 1,698.00 342,996.00

Pasir Pasang m3 0.485 236,710.00 114,804.35

Tenaga Kerja

Pekerja OH 1.500 64,580.00 96,870.00

Tukang Batu OH 0.750 83,490.00 62,617.50

Kepala Tukang OH 0.075 97,398.00 7,304.85

Mandor OH 0.075 77,000.00 5,775.00

Jumlah harga per-satuan pekerjaan 917,047.70

C.02 Memasang 1 m3 batu kosong (aanstamping)

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

BahanBatu gunung m3 1.200 238,900 286,680.00

Pasir Urug m3 0.432 194,670 84,097.44

Tenaga Kerja

Pekerja OH 0.780 64,580 50,372.40

Tukang Batu OH 0.390 83,490 32,561.10

Kepala Tukang OH 0.039 97,398 3,798.52

Mandor OH 0.039 77,000 3,003.00

Jumlah harga per-satuan pekerjaan 460,512.46

C.03 Memasang 1 m3 pondasi Sumuran dia 100 cm

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Batu Belah m3 0.450 238,900 107,505.00

Portland Cement Kg 280.000 1,698 475,440.00

Batu Pecah 1 - 2 m3 0.670 470,068 314,945.56

Pasir Beton m3 0.450 236,710 106,519.50

Tenaga Kerja

Pekerja OH 2.380 64,580 153,700.40

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 12: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

Tenaga KerjaTukang Batu OH 0.300 83,490 25,047.00

Kepala Tukang OH 0.030 97,398 2,921.94

Mandor OH 0.080 77,000 6,160.00

Jumlah harga per-satuan pekerjaan 1,192,239.40

D. PEKERJAAN BETON

D.01 Membuat 1 m3 beton (K 150)

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Portland Cement Kg 299.000 1,698 507,702.00

Pasir Beton m3 0.571 236,710 135,161.41

Koral beton m3 0.753 470,068 353,961.20

Air Liter 215.000 57 12,341.00

Tenaga Kerja

Pekerja OH 1.650 64,580 106,557.00

Tukang Batu OH 0.275 83,490 22,959.75

Kepala Tukang OH 0.028 97,398 2,727.14

Mandor OH 0.083 77,000 6,391.00

Jumlah harga per-satuan pekerjaan 1,147,800.51

D.02 Membuat 1 m3 pondasi beton bertulang ( 150 Kg besi + bekisiting )

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Papan Kayu (Bekisting) m3 0.200 3,500,000 700,000.00

Paku 5 cm - 12 cm Kg 1.500 19,800 29,700.00

Minyak Bekisting Liter 0.400 3,000 1,200.00

Besi Beton Polos Kg 157.000 20,000 3,140,000.00

Kawat Beton Kg 2.250 26,100 58,725.00

Portland Cement Kg 336.000 1,698 570,528.00

Pasir Beton m3 0.540 236,710 127,823.40

Koral beton m3 0.810 470,068 380,755.08

Tenaga Kerja

Pekerja OH 5.300 64,580 342,274.00

Tukang Batu OH 0.275 83,490 22,959.75

Tukang Kayu OH 1.300 83,490 108,537.00

Tukang Besi OH 1.050 83,490 87,664.50

Kepala Tukang OH 0.262 97,398 25,518.28

Mandor OH 0.265 77,000 20,405.00

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 13: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

Jumlah harga per-satuan pekerjaan 5,616,090.01

D.03 Membuat 1 m3 sloof beton bertulang ( 150 Kg besi + bekisiting )

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Papan Kayu (Bekisting) m3 0.200 3,500,000 700,000.00

Paku 5 cm - 12 cm Kg 1.500 19,800 29,700.00

Minyak Bekisting Liter 0.400 3,000 1,200.00

Besi Beton Polos Kg 157.000 20,000 3,140,000.00

Kawat Beton Kg 2.250 26,100 58,725.00

Portland Cement Kg 336.000 1,698 570,528.00

Pasir Beton m3 0.540 236,710 127,823.40

Koral beton m3 0.810 470,068 380,755.08

Tenaga Kerja

Pekerja OH 5.300 64,580 342,274.00

Tukang Batu OH 0.275 83,490 22,959.75

Tukang Kayu OH 1.300 83,490 108,537.00

Tukang Besi OH 1.050 83,490 87,664.50

Kepala Tukang OH 0.265 97,398 25,810.47

Mandor OH 0.265 77,000 20,405.00

Jumlah harga per-satuan pekerjaan 5,616,382.20

D.04 Membuat 1 m3 kolom beton bertulang ( 150 Kg besi + bekisiting )

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Papan Kayu (Bekisting) m3 0.320 3,500,000 1,120,000.00

Paku 5 cm - 12 cm Kg 3.200 20,000 64,000.00

Minyak Bekisting Liter 1.600 3,000 4,800.00

Besi Beton Polos Kg 157.500 20,000 3,150,000.00

Kawat Beton Kg 2.250 26,100 58,725.00

Portland Cement Kg 336.000 1,698 570,528.00

Pasir Beton m3 0.540 236,710 127,823.40

Koral beton m3 0.810 470,068 380,755.08

Kayu Klas III Balok m3 0.120 3,200,000 384,000.00

Plywood 9 mm Lembar 2.800 137,500 385,000.00

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 14: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

Bahan

Kayu Dolken Batang 32.000 8,300 265,600.00

Tenaga Kerja

Pekerja OH 5.300 64,580 342,274.00

Tukang Batu OH 0.275 83,490 22,959.75

Tukang Kayu OH 1.300 83,490 108,537.00

Tukang Besi OH 1.050 83,490 87,664.50

Kepala Tukang OH 0.265 97,398 25,810.47

Mandor OH 0.265 77,000 20,405.00

Jumlah harga per-satuan pekerjaan 7,118,882.20

D.05 Membuat 1 m3 balok beton bertulang ( 150 Kg besi + bekisiting )

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Papan Kayu (Bekisting) m3 0.320 3,500,000 1,120,000.00

Paku 5 cm - 12 cm Kg 3.200 20,000 64,000.00

Minyak Bekisting Liter 1.600 3,000 4,800.00

Besi Beton Polos Kg 150.000 20,000 3,000,000.00

Kawat Beton Kg 2.250 26,100 58,725.00

Portland Cement Kg 323.000 1,698 548,454.00

Pasir Beton m3 0.520 236,710 123,089.20

Koral beton m3 0.780 470,068 366,653.04

Kayu Klas II Balok m3 0.120 4,000,000 480,000.00

Plywood 9 mm Lembar 2.800 137,500 385,000.00

Kayu Dolken Batang 32.000 8,300 265,600.00

Tenaga Kerja

Pekerja OH 5.800 64,580 374,564.00

Tukang Batu OH 0.350 83,490 29,221.50

Tukang Kayu OH 2.800 83,490 233,772.00

Tukang Besi OH 1.0500 83,490 87,664.50

Kepala Tukang OH 0.420 97,398 40,907.16

Mandor OH 0.185 77,000 14,245.00

Jumlah harga per-satuan pekerjaan 7,196,695.40

D.06 Membuat m1 Ring Balok Beton Bertulang

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Papan Kayu (Bekisting) m3 0.003 3,500,000 10,500.00

Paku 5 cm - 12 cm Kg 0.020 20,000 400.00

Besi Beton Polos Kg 3.600 20,000 72,000.00

Kawat Beton Kg 0.050 26,100 1,305.00

Portland Cement Kg 5.500 1,698 9,339.00

Pasir Beton m3 0.009 236,710 2,130.39

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 15: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAANBahan

Krikil m3 0.015 276,900 4,153.50

Tenaga Kerja

Pekerja OH 0.297 64,580 19,180.26

Tukang Batu OH 0.033 83,490 2,755.17

Tukang Kayu OH 0.033 83,490 2,755.17

Tukang Besi OH 0.033 83,490 2,755.17

Kepala Tukang OH 0.010 97,398 973.98

Mandor OH 0.015 77,000 1,155.00

Jumlah harga per-satuan pekerjaan 129,402.64

D.07 Membuat 1 m3 Plat beton bertulang ( 200 Kg besi + bekisiting )

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Kayu Klas III (Bekisting) m3 0.250 3,200,000 800,000.00

Paku 5 cm - 12 cm Kg 3.000 20,000 60,000.00

Minyak Bekisting Liter 1.200 3,000 3,600.00

Besi Beton Polos Kg 210.000 20,000 4,200,000.00

Kawat Beton Kg 3.000 26,100 78,300.00

Portland Cement Kg 336.000 1,698 570,528.00

Pasir Beton m3 0.540 236,710 127,823.40

Koral beton m3 0.810 276,900 224,289.00

Kayu Klas II Balok m3 0.105 4,000,000 420,000.00

Plywood 9 mm Lembar 2.500 137,500 343,750.00

Kayu Dolken Batang 14.000 8,300 116,200.00

Tenaga Kerja

Pekerja OH 5.650 64,580 364,877.00

Tukang Batu OH 0.275 83,490 22,959.75

Tukang Kayu OH 1.560 83,490 130,244.40

Tukang Besi OH 1.400 83,490 116,886.00

Kepala Tukang OH 0.323 97,398 31,459.55

Mandor OH 0.283 77,000 21,791.00

Jumlah harga per-satuan pekerjaan 7,632,708.10

D.08 Membuat 1 m1 kolom praktis beton bertulang ( 11 x 11 ) cm

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Kayu Klas III (Bekisting) m3 0.002 3,200,000 6,400.00

Paku 5 cm - 12 cm Kg 0.010 20,000 200.00

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 16: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

Bahan

Besi Beton Polos Kg 3.000 20,000 60,000.00

Kawat Beton Kg 0.450 26,100 11,745.00

Portland Cement Kg 4.000 1,698 6,792.00

Pasir Beton m3 0.006 236,710 1,420.26

Koral beton m3 0.009 276,900 2,492.10

Tenaga Kerja

Pekerja OH 0.180 64,580 11,624.40

Tukang Batu OH 0.020 83,490 1,669.80

Tukang Kayu OH 0.020 83,490 1,669.80

Tukang Besi OH 0.020 83,490 1,669.80

Kepala Tukang OH 0.006 97,398 584.39

Mandor OH 0.009 77,000 693.00

Jumlah harga per-satuan pekerjaan 106,960.55

E. PEKERJAAN DINDING

E.01 Memasang 1 m2 dinding bata merah 1/2 bata, campuran 1 PC : 2 PP

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Bata Merah Buah 70.000 670 46,900.00

Portland Cement Kg 18.950 1,698 32,177.10

Pasir Pasang m3 0.038 236,710 8,994.98

Tenaga Kerja

Pekerja OH 0.300 64,580 19,374.00

Tukang Batu OH 0.100 83,490 8,349.00

Kepala Tukang OH 0.010 97,398 973.98

Mandor OH 0.015 77,000 1,155.00

Jumlah harga per-satuan pekerjaan 117,924.06

E.02 Memasang 1 m2 dinding bata merah 1/2 bata, campuran 1 PC : 3 PP

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Bata Merah Buah 70.000 670 46,900.00

Portland Cement Kg 14.370 1,698 24,400.26

Pasir Pasang m3 0.040 236,710 9,468.40

Tenaga Kerja

Pekerja OH 0.300 64,580 19,374.00

Tukang Batu OH 0.100 83,490 8,349.00

Kepala Tukang OH 0.010 97,398 973.98

Mandor OH 0.015 77,000 1,155.00

Jumlah harga per-satuan pekerjaan 110,620.64

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 17: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

F. PEKERJAAN PLESTERAN

F.02 Memasang 1 m2 plesteran 1 PC : 3 PP, tebal 15 mm

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

BahanPortland Cement Kg 7.776 1,698 13,203.65

Pasir Pasang m3 0.023 236,710 5,444.33

Tenaga Kerja

Pekerja OH 0.300 64,580 19,374.00

Tukang Batu OH 0.150 83,490 12,523.50

Kepala Tukang OH 0.015 97,398 1,460.97

Mandor OH 0.015 77,000 1,155.00

Jumlah harga per-satuan pekerjaan 53,161.45

F.03 Memasang 1 m2 plesteran 1 PC : 4 PP, tebal 15 mm (pondasi)

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

BahanPortland Cement Kg 6.240 1,698 10,595.52

Pasir Pasang m3 0.024 236,710 5,681.04

Tenaga Kerja

Pekerja OH 0.300 64,580 19,374.00

Tukang Batu OH 0.150 83,490 12,523.50

Kepala Tukang OH 0.015 97,398 1,460.97

Mandor OH 0.015 77,000 1,155.00

Jumlah harga per-satuan pekerjaan 50,790.03

F.08 Memasang 1 m1 Saluran air hujan keliling bangunan dalam 30 cm

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Galian Tanah m3 0.250 50,360 12,590.00

Bata Merah Buah 41.000 670 27,470.00

Portland Cement Kg 6.480 1,698 11,003.04

Pasir Pasang m3 0.030 236,710 7,101.30

Tenaga Kerja

Pekerja OH 0.300 64,580 19,374.00

Tukang Batu OH 0.350 83,490 29,221.50

Kepala Tukang OH 0.350 97,398 34,089.30

Mandor OH 0.043 77,000 3,311.00

Jumlah harga per-satuan pekerjaan 144,160.14

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 18: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

F.09 Memasang 1 m2 Pelicinan dengan Air Semen

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan Portland Cement Kg 1.500 1,698 2,547.00

Tenaga Kerja

Pekerja OH 0.150 64,580 9,687.00

Tukang Batu OH 0.100 83,490 8,349.00

Kepala Tukang OH 0.015 97,398 1,460.97

Mandor OH 0.010 77,000 770.00

Jumlah harga per-satuan pekerjaan 22,813.97

F.10 Membuat 1 m1 Profil Tembok

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

BahanPC warna Untuk Acian Dasar Kg 0.080 22,900 1,832.00

Amplas Lbr 0.500 4,500 2,250.00

Tenaga Kerja

Pekerja OH 0.400 64,580 25,832.00

Tukang Profil OH 0.200 83,490 16,698.00

Kepala Tukang OH 0.020 97,398 1,947.96

Mandor OH 0.020 77,000 1,540.00

Jumlah harga per-satuan pekerjaan 50,099.96

G. PEKERJAAN KAYU

G.01 Membuat dan memasang 1m3 kusen pintu & kusen jendela, kayu kelas I

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Balok Kayu m3 1.100 4,500,000 4,950,000.00

Paku 10 cm Kg 1.250 20,000 25,000.00

Lem Kayu Kg 1.000 25,000 25,000.00

Tenaga Kerja

Pekerja OH 7.000 64,580 452,060.00

Tukang Kayu OH 21.000 83,490 1,753,290.00

Kepala Tukang OH 2.100 97,398 204,535.80

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 19: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAANTenaga Kerja

Mandor OH 0.350 77,000 26,950.00

Jumlah harga per-satuan pekerjaan 7,436,835.80

G.02 Membuat dan memasang 1m3 kusen pintu & kusen jendela, kayu kelas II

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Balok Kayu m3 1.200 4,000,000 4,800,000.00

Paku 10 cm Kg 1.250 20,000 25,000.00

Lem Kayu Kg 1.000 25,000 25,000.00

Tenaga Kerja

Pekerja OH 6.000 64,580 387,480.00

Tukang Kayu OH 18.000 83,490 1,502,820.00

Kepala Tukang OH 1.800 97,398 175,316.40

Mandor OH 0.300 77,000 23,100.00

Jumlah harga per-satuan pekerjaan 6,938,716.40

G.03 Membuat dan memasang 1m2 daun pintu klamp sederhana kelas III

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

BahanPapan Kayu m3 0.040 3,500,000 140,000.00

Paku Kg 0.050 20,000 1,000.00

Tenaga Kerja

Pekerja OH 1.000 64,580 64,580.00

Tukang Kayu OH 3.000 83,490 250,470.00

Kepala Tukang OH 0.300 97,398 29,219.40

Mandor OH 0.050 77,000 3,850.00

Jumlah harga per-satuan pekerjaan 489,119.40

G.04 Membuat dan memasang 1m2 pintu dan jendela kaca, kayu kelas I atau II

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

BahanPapan Kayu m3 0.040 3,500,000 140,000.00

Lem Kayu Kg 0.500 20,000 10,000.00

Tenaga Kerja

Pekerja OH 1.000 64,580 64,580.00

Tukang Kayu OH 3.000 83,490 250,470.00

Kepala Tukang OH 0.300 97,398 29,219.40

Mandor OH 0.050 77,000 3,850.00

Jumlah harga per-satuan pekerjaan 498,119.40

G.07 Memasang 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 20: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Balok Kayu m3 1.100 4,000,000 4,400,000.00

Besi strip tebal 5 mm Kg 15.000 27,000 405,000.00

Paku 12 cm Kg 5.600 20,000 112,000.00

Tenaga Kerja

Pekerja OH 4.000 64,580 258,320.00

Tukang Kayu OH 12.000 83,490 1,001,880.00

Kepala Tukang OH 1.200 97,398 116,877.60

Mandor OH 0.200 77,000 15,400.00

Jumlah harga per-satuan pekerjaan 6,309,477.60

G.09 Memasang 1 m3 konstruksi gordeng, kayu kelas II

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Balok Kayu m3 1.100 4,000,000 4,400,000.00

Besi strip tebal 5 mm Kg 15.000 27,000 405,000.00

Paku 12 cm Kg 3.000 20,000 60,000.00

Tenaga Kerja

Pekerja OH 2.400 64,580 154,992.00

Tukang Kayu OH 7.200 83,490 601,128.00

Kepala Tukang OH 0.720 97,398 70,126.56

Mandor OH 0.120 77,000 9,240.00

Jumlah harga per-satuan pekerjaan 5,700,486.56

G.10 Memasang 1 m2 rangka atap, kayu kelas II

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Kaso-kaso ( 5 x 7 ) cm m3 0.014 4,000,000 56,000.00

Reng ( 2 x 3 ) cm Kg 0.036 3,200,000 115,200.00

Paku 5 cm dan 10 cm Kg 0.250 20,000 5,000.00

Tenaga Kerja

Pekerja OH 0.100 64,580 6,458.00

Tukang Kayu OH 0.100 83,490 8,349.00

Kepala Tukang OH 0.010 97,398 973.98

Mandor OH 0.005 77,000 385.00

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 21: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

Jumlah harga per-satuan pekerjaan 192,365.98

G.11 Memasang 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

BahanKaso-kaso ( 5 x 7 ) cm m3 0.016 4,000,000 65,200.00

Paku 7 cm dan 10 cm Kg 0.250 20,000 5,000.00

Tenaga Kerja

Pekerja OH 0.200 64,580 12,916.00

Tukang Kayu OH 0.300 83,490 25,047.00

Kepala Tukang OH 0.030 97,398 2,921.94

Mandor OH 0.010 77,000 770.00

Jumlah harga per-satuan pekerjaan 111,854.94

G.12 Memasang 1 m1 lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

BahanPapan Kayu 3/20 m3 0.015 4,702,500 72,418.50

Paku 7 cm dan 10 cm Kg 0.200 20,000 4,000.00

Tenaga Kerja

Pekerja OH 0.150 64,580 9,687.00

Tukang Kayu OH 0.300 83,490 25,047.00

Kepala Tukang OH 0.030 97,398 2,921.94

Mandor OH 0.075 77,000 5,775.00

Jumlah harga per-satuan pekerjaan 119,849.44

G.13 Memasang 1 M2 Bingkai Jendela/Pintu

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan Papan Jati M2 0.035 4,000,000 140,000.00

Tenaga Kerja

Pekerja OH 0.800 64,580 51,664.00

Tukang Kayu OH 2.000 83,490 166,980.00

Kepala Tukang OH 0.200 97,398 19,479.60

Mandor OH 0.0400 77,000 3,080.00

Jumlah harga per-satuan pekerjaan 381,203.60

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 22: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

H. PEKERJAAN LANTAI

H.03 Memasang 1 m2 lantai tegel keramik putih ukuran (40 x 40) cm

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Tegel keramik putih Buah 6.630 9,750 64,642.50

Portland Cement Kg 9.800 1,698 16,640.40

Pasir Pasang m3 0.045 236,710 10,651.95

Semen Warna Kg 1.300 22,900 29,770.00

Tenaga Kerja

Pekerja OH 0.250 64,580 16,145.00

Tukang Batu OH 0.125 83,490 10,436.25

Kepala Tukang OH 0.013 97,398 1,266.17

Mandor OH 0.013 77,000 1,001.00

Jumlah harga per-satuan pekerjaan 150,553.27

H.04 Memasang 1 m2 lantai tegel keramik Warna Corak ukuran (40 x 40) cm

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Tegel keramik Warna Buah 6.630 10,000 66,300.00

Portland Cement Kg 9.800 1,698 16,640.40

Pasir Pasang m3 0.045 236,710 10,651.95

Semen Warna Kg 1.300 22,900 29,770.00

Tenaga Kerja

Pekerja OH 0.250 64,580 16,145.00

Tukang Batu OH 0.125 83,490 10,436.25

Kepala Tukang OH 0.013 97,398 1,266.17

Mandor OH 0.013 77,000 1,001.00

Jumlah harga per-satuan pekerjaan 152,210.77

H.05 Memasang 1 m2 lantai tegel keramik putih ukuran (30 x 30) cm

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Tegel keramik putih Buah 11.870 4,464 52,983.36

Portland Cement Kg 10.000 1,698 16,980.00

Pasir Pasang m3 0.045 236,710 10,651.95

Semen Warna Kg 1.500 22,900 34,350.00

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 23: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

Tenaga Kerja

Pekerja OH 0.260 64,580 16,790.80

Tukang Batu OH 0.130 83,490 10,853.70

Kepala Tukang OH 0.013 97,398 1,266.17

Mandor OH 0.013 77,000 1,001.00

Jumlah harga per-satuan pekerjaan 144,876.99

H.06 Memasang 1 m2 lantai tegel keramik Warna Corak ukuran (30 x 30) cm

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Tegel keramik Warna Buah 11.870 4,545 53,954.55

Portland Cement Kg 10.000 1,698 16,980.00

Pasir Pasang m3 0.045 236,710 10,651.95

Semen Warna Kg 1.500 22,900 34,350.00

Tenaga Kerja

Pekerja OH 0.260 64,580 16,790.80

Tukang Batu OH 0.130 83,490 10,853.70

Kepala Tukang OH 0.013 97,398 1,266.17

Mandor OH 0.013 77,000 1,001.00

Jumlah harga per-satuan pekerjaan 145,848.17

H.06 Memasang 1 m2 lantai tegel Anti Sleep ukuran (20 x 20) cm

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Tegel keramik Warna Buah 11.870 3,760 44,631.20

Portland Cement Kg 10.000 4,545 45,454.55

Pasir Pasang m3 0.045 1,698 76.41

Semen Warna Kg 1.500 236,710 355,065.00

Tenaga Kerja

Pekerja OH 0.260 22,900 5,954.00

Tukang Batu OH 0.130 64,580 8,395.40

Kepala Tukang OH 0.013 83,490 1,085.37

Mandor OH 0.013 97,398 1,266.17

Jumlah harga per-satuan pekerjaan 461,928.10

H.07 Memasang 1 m2 dinding tegel keramik ukuran (20 x 25) cm

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Tegel keramik Buah 21.500 4,960 106,640.00

Portland Cement Kg 10.200 1,698 17,319.60

Pasir Pasang m3 0.045 236,710 10,651.95

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 24: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAANBahan

Semen Warna Kg 1.560 22,900 35,724.00

Tenaga Kerja

Pekerja OH 0.265 64,580 17,113.70

Tukang Batu OH 0.133 83,490 11,062.43

Kepala Tukang OH 0.014 97,398 1,314.87

Mandor OH 0.014 77,000 1,039.50

Jumlah harga per-satuan pekerjaan 200,866.05

H.11 Memasang 1 m2 dinding Batu tempel hitam

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Ubin Batu Andesit Bintik (20x4 m3 4.000 120,000 480,000.00

PC Kg 6.000 1,698 10,188.00

Pasir Pasang m3 0.143 236,710 33,825.86

Tenaga Kerja

Pekerja OH 0.300 64,580 19,374.00

Tukang Batu OH 0.200 83,490 16,698.00

Kepala Tukang OH 0.020 97,398 1,947.96

Mandor OH 0.015 77,000 1,155.00

Jumlah harga per-satuan pekerjaan 563,188.82

I. PEKERJAAN LANGIT-LANGIT

I.01 Memasang 1 m2 langit-langit tripleks

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

BahanTripleks Lembar 0.375 67,900 25,462.50

Paku Tripleks Kg 0.030 26,100 783.00

Tenaga Kerja

Pekerja OH 0.100 64,580 6,458.00

Tukang Kayu OH 0.100 83,490 8,349.00

Kepala Tukang OH 0.010 97,398 973.98

Mandor OH 0.005 77,000 385.00

Jumlah harga per-satuan pekerjaan 42,411.48

I.03 Memasang 1 m2 langit-langit Gypsum board, tebal 9 mm permukaan rata

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

BahanGypsum Board Lembar 0.3472 81,500 28,296.80

Paku Biasa Kg 0.0300 19,800 594.00

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 25: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

Tenaga Kerja

Pekerja OH 0.0700 64,580 4,520.60

Tukang Kayu OH 0.1000 83,490 8,349.00

Kepala Tukang OH 0.0100 97,398 973.98

Mandor OH 0.0035 77,000 269.50

Jumlah harga per-satuan pekerjaan 43,003.88

I.07 1 M2 Langit-langit Triplek 3 mm + Rangka Kayu Kls II

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Kayu Balok 5/7 M3 0.023 4,000,000 92,000.00

Paku biasa 2" - 5" Kg 0.060 26,100 1,566.00

Triplek Lbr 0.390 67,900 26,481.00

Tenaga Kerja

Pekerja OH 0.270 64,580 17,436.60

Tukang Kayu OH 0.400 83,490 33,396.00

Kepala Tukang OH 0.040 97,398 3,895.92

Mandor OH 0.014 77,000 1,039.50

Jumlah harga per-satuan pekerjaan 175,815.02

J. PEKERJAAN PENUTUP ATAP

J.01 Memasang 1 m2 atap sakura roof

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

BahanAtap Metal sakura Roof M2 1.620 36,500 59,130.00

Paku Sekrup Kg 0.200 26,100 5,220.00

Tenaga Kerja

Pekerja OH 0.200 64,580 12,916.00

Tukang Kayu OH 0.100 83,490 8,349.00

Kepala Tukang OH 0.010 97,398 973.98

Mandor OH 0.010 77,000 770.00

Jumlah harga per-satuan pekerjaan 87,358.98

J.02 Memasang 1 m1 nok atap sakura roof

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Nok Atap Sakura Roof Lbr 1.000 39,100 39,100.00

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 26: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

Bahan Paku Sekrup Kg 0.050 26,100 1,305.00

Alumunium Voil m1 1.000 8,000 8,000.00

Tenaga Kerja

Pekerja OH 0.250 64,580 16,145.00

Tukang Kayu OH 0.015 83,490 1,252.35

Kepala Tukang OH 0.015 97,398 1,460.97

Mandor OH 0.013 77,000 1,001.00

Jumlah harga per-satuan pekerjaan 68,264.32

K. PEKERJAAN FINISHING DAN PENGECETAN

K.01 Pengecetan 1 m2 Tembok baru (1 lapis cat dasar, 2 lapis cat penutup)

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Plamir Kg 0.1000 8,800 880.00

Cat dasar Kg 0.1000 20,000 2,000.00

Cat penutup 2 kali Kg 0.2600 97,900 25,454.00

Tenaga Kerja

Pekerja OH 0.0200 64,580 1,291.60

Tukang Cat OH 0.0630 83,490 5,259.87

Kepala Tukang OH 0.0063 97,398 613.61

Mandor OH 0.0025 77,000 192.50

Jumlah harga per-satuan pekerjaan 35,691.58

K.02 Pengecetan 1 m2 bidang kayu baru

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Cat meni kayu Kg 0.200 19,500 3,900.00

Cat dasar Kg 0.170 20,000 3,400.00

Cat penutup 2 kali Kg 0.260 43,200 11,232.00

Tenaga Kerja

Pekerja OH 0.070 64,580 4,520.60

Tukang Cat OH 0.009 83,490 751.41

Kepala Tukang OH 0.006 97,398 584.39

Mandor OH 0.0025 77,000 192.50

Jumlah harga per-satuan pekerjaan 24,580.90

K.03 Pengecetan 1 m2 Plafond (langit-langit)

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 27: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

Bahan

Cat Tembok metrolight Kg 0.200 26,100 5,220.00

Plamir Tembok Kg 0.160 8,800 1,408.00

Roll Cat Bh 0.010 31,300 313.00

Amplas Lbr 0.500 4,500 2,250.00

Tenaga Kerja

Pekerja OH 0.020 64,580 1,291.60

Tukang Cat OH 0.030 83,490 2,504.70

Kepala Tukang OH 0.0030 97,398 292.19

Mandor OH 0.0010 77,000 77.00

Jumlah harga per-satuan pekerjaan 13,356.49

K.11 1 M2 Mendempul dan Menggosok Kayu

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

BahanDempul Jadi Kg 0.080 16,300 1,304.00

Amlas Halus Lbr 0.500 4,500 2,250.00

Tenaga Kerja

Pekerja OH 0.040 64,580 2,583.20

Tukang Cat OH 0.040 83,490 3,339.60

Kepala Tukang OH 0.004 97,398 389.59

Mandor OH 0.0025 77,000 192.50

Jumlah harga per-satuan pekerjaan 10,058.89

L PEKERJAAN PENGGANTUNG DAN KACA

M.02 1 Buah Pasang Kunci Tanam Biasa

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan Kunci Tanam Biasa Bh 1.000 136,700 136,700.00

Tenaga Kerja

Pekerja OH 0.010 64,580 645.80

Tukang Kayu OH 0.500 83,490 41,745.00

Kepala Tukang OH 0.010 97,400 974.00

Mandor OH 0.0050 77,000 385.00

Jumlah harga per-satuan pekerjaan 180,449.80

M.03 1 Buah Pasang Engsel Pintu

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 28: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan Engsel Pintu Bh 1.000 18,800 18,800.00

Tenaga Kerja

Pekerja OH 0.015 64,580 968.70

Tukang Kayu OH 0.150 83,490 12,523.50

Kepala Tukang OH 0.015 97,400 1,461.00

Mandor OH 0.0008 77,000 61.60

Jumlah harga per-satuan pekerjaan 33,814.80

M.04 1 Buah Pasang Engsel Jendela Kupu-kupu

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan Engsel Jendela Bh 1.000 11,200 11,200.00

Tenaga Kerja

Pekerja OH 0.010 64,580 645.80

Tukang Kayu OH 0.100 83,490 8,349.00

Kepala Tukang OH 0.010 97,400 974.00

Mandor OH 0.0005 77,000 38.50

Jumlah harga per-satuan pekerjaan 21,207.30

M.05 1 Buah Pasang Kait Angin

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan Hak Angin Bh 1.000 9,400 9,400.00

Tenaga Kerja

Pekerja OH 0.015 64,580 968.70

Tukang Kayu OH 0.150 83,490 12,523.50

Kepala Tukang OH 0.015 97,400 1,461.00

Mandor OH 0.0008 77,000 61.60

Jumlah harga per-satuan pekerjaan 24,414.80

M.06 1 Buah Pasang Door Closer

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan Door Closer Bh 1.000 156,700 156,700.00

Tenaga Kerja

Pekerja OH 0.050 64,580 3,229.00

Tukang Kayu OH 0.500 83,490 41,745.00

Kepala Tukang OH 0.050 97,400 4,870.00

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 29: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAANTenaga Kerja

Mandor OH 0.0025 77,000 192.50

Jumlah harga per-satuan pekerjaan 206,736.50

M.08 1 M2 Pasang Kaca , tebal 5 mm

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan Kaca 5 mm M2 1.100 114,900 126,390.00

Tenaga Kerja

Pekerja OH 0.015 64,580 968.70

Tukang Kayu OH 0.150 83,490 12,523.50

Kepala Tukang OH 0.015 97,400 1,461.00

Mandor OH 0.0008 77,000 61.60

Jumlah harga per-satuan pekerjaan 141,404.80

M.09 1 BH Pasang Grendel Pintu/Jendela

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan Grendel Pintu/Jendela Bh 1.000 5,600 5,600.00

Tenaga Kerja

Pekerja OH 0.020 64,580 1,291.60

Tukang Kayu OH 0.200 83,490 16,698.00

Kepala Tukang OH 0.020 97,400 1,948.00

Mandor OH 0.0010 77,000 77.00

Jumlah harga per-satuan pekerjaan 25,614.60

N. PEKERJAAN SANITAIR

N.01 Pemasangan 1 Unit Septictank Uk. 2 x 2 x 1,5 m + Peresapan

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Galian tanah M3 3.3750 50,360.00 169,965.00

Pasir urug M3 0.1607 194,670.00 31,273.74

Lantai kerja M2 1.6875 150,000.00 253,125.00

Pas. Bata 1PC : 2PS + plester M2 11.2500 117,924.06 1,326,645.68

Plat beton penutup M3 0.2250 7,632,708.10 1,717,359.32

Pipa PVC AW 4" + sambungan Btg 2.2500 112,900.00 254,025.00

Pipa GIP 1,5" M1 0.9000 185,100.00 166,590.00

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 30: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAANBahan

Galian tanah untuk Peresapan M3 2.5313 50,360.00 127,473.75

Pas. Injuk M2 4.0500 3,000.00 12,150.00

Pasangan kerikil 3.5 cm M3 0.7875 276,900.00 218,058.75

Pipa PVC AW 4" berlubang Btg 2.2500 112,900.00 254,025.00

Urugan tanah kembali M3 0.8438 108,824.00 91,820.25

Tenaga Kerja

Pekerja OH 4.5000 64,580.00 290,610.00

Tukang Batu OH 1.8750 83,490.00 156,543.75

Kepala Tukang OH 1.8750 97,400.00 182,625.00

Mandor OH 0.1875 77,000.00 14,437.50

Jumlah harga per-satuan pekerjaan 5,266,727.73

N.03 Pemasangan 1 Bh Bak Kamar Mandi Fiberglass 1 M3

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

BahanBak Fiberglass Bh 1.0000 160,000.00 160,000.00

Perlengkapan (12 % dari harga Ls 1.0000 19,200.00 19,200.00

Tenaga Kerja

Pekerja OH 3.0000 64,580.00 193,740.00

Tukang OH 4.5000 83,490.00 375,705.00

Kepala Tukang OH 0.9000 97,400.00 87,660.00

Mandor OH 0.9000 77,000.00 69,300.00

Jumlah harga per-satuan pekerjaan 905,605.00

N.04 Memasang 1 bh Closed duduk

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

BahanClosed duduk porselin Bh 1.100 182,800 201,080.00

Perlengkapan % 1.000 21,936 21,936.00

Tenaga Kerja

Pekerja OH 3.300 64,580 213,114.00

Tukang OH 1.100 83,490 91,839.00

Kepala Tukang OH 0.001 97,400 97.40

Mandor OH 0.160 77,000 12,320.00

Jumlah harga per-satuan pekerjaan 540,386.40

N.05 Memasang 1 bh Floor drain

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan Floor Drain Bh 1.000 26,100 26,100.00

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 31: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

Tenaga Kerja

Pekerja OH 0.010 64,580 645.80

Tukang OH 0.100 83,490 8,349.00

Kepala Tukang OH 0.010 97,400 974.00

Mandor OH 0.050 77,000 3,850.00

Jumlah harga per-satuan pekerjaan 39,918.80

N.08 Memasang 1 m1 Pipa PVC type AW dia 3/4"

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

BahanPipa PVC Type AW dia 3/4" m1 1.200 27,600 33,120.00

Perlengkapan % 0.350 9,660 3,381.00

Tenaga Kerja

Pekerja OH 0.036 64,580 2,324.88

Tukang OH 0.060 83,490 5,009.40

Kepala Tukang OH 0.006 97,400 584.40

Mandor OH 0.0018 77,000 138.60

Jumlah harga per-satuan pekerjaan 44,558.28

N.13 Memasang 1 bh kran dia. 3/4"

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

BahanKran Air 3/4" Bh 1.000 37,000 37,000.00

Seal Tape Bh 0.025 12,600 315.00

Tenaga Kerja

Pekerja OH 0.010 64,580 645.80

Tukang OH 0.100 83,490 8,349.00

Kepala Tukang OH 0.010 97,400 974.00

Mandor OH 0.0050 77,000 385.00

Jumlah harga per-satuan pekerjaan 47,668.80

O. PEKERJAAN INSTALASI LISTRIK

O.01 1 m' Pekerjaan Pemasangan Jalur Kabel Utama

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan Kabel NYM 3 x 2.5 sqmm M1 1.1000 15,000.00 16,500.00

Tenaga Kerja

Mekanik OH 0.0208 17,600.00 366.08

Pembantu Mekanik OH 0.0417 14,320.00 597.14

Mandor OH 0.0104 77,000.00 800.80

Jumlah harga per-satuan pekerjaan 18,264.02

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 32: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

O.02 1 ttk Pekerjaan Pemasangan MCB Pembatas

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

MCB 4 A Bh 2.000 50,000.00 100,000.000

MCB 10 A Bh 1.000 70,000.00 70,000.000

NYM 4 x 2.5 sqmm M1 6.000 15,000.00 90,000.000

Pipa PVC dia. 3/4" M1 1.000 27,600.00 27,600.00

Tenaga Kerja

Mekanik OH 0.083 17,600.00 1,466.08

Pembantu Mekanik OH 0.167 14,320.00 2,387.14

Mandor OH 0.042 77,000.00 3,210.90

Jumlah harga per-satuan pekerjaan 294,664.12

O.04 1 Bh Pekerjaan Pemasangan saklar Ganda

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Kabel NYM 2 x 1.5 sqmm M1 2.050 15,000.00 30,750.000

Saklar Dowble Bh 1.000 16,300.00 16,300.000

Plafond fitting Bh 2.000 10,100.00 20,200.000

Pipa PVC dia. 3/4" M1 0.500 27,600.00 13,800.00

Tenaga Kerja

Mekanik OH 0.0833 17,600.00 1,466.08

Pembantu Mekanik OH 0.1667 14,320.00 2,387.14

Mandor OH 0.0417 77,000.00 3,210.90

Jumlah harga per-satuan pekerjaan 88,114.12

O.05 1 Bh Pekerjaan Pemasangan Stop Kontak

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Kabel NYM 3 x 1.5 sqmm M1 1.100 15,000.00 16,500.000

Stop Kontak Bh 1.000 13,500.00 13,500.000

Pipa PVC dia. 3/4" M1 0.500 27,600.00 13,800.00

Tenaga Kerja

Mekanik OH 0.0833 17,600.00 1,466.08

Pembantu Mekanik OH 0.1667 14,320.00 2,387.14

Mandor OH 0.0417 77,000.00 3,210.90

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 33: Rab Masjid Unaaha Baru

ANALISIS HARGA SATUAN PEKERJAAN

Jumlah harga per-satuan pekerjaan 50,864.12

O.06 1 ttk Pekerjaan Pentanahan (Grounding)

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan Pentanahan panel Bh 1.0000 75,000.00 75,000.00

Tenaga Kerja

Mekanik OH 0.0833 17,600.00 1,466.08

Pembantu Mekanik OH 0.1667 14,320.00 2,387.14

Mandor OH 0.0417 77,000.00 3,210.90

Jumlah harga per-satuan pekerjaan 82,064.12

O.07 1 ttk Pekerjaan Penangkal Petir

Kebutuhan Satuan Indeks Jumlah Harga (Rp)

Bahan

Pentanahan Penangkal petir Bh 1.000 60,000.00 60,000.000

Kabel BC Kg 35.000 35,000.00 1,225,000.000

Jarum Penangkal Petir 16 sq Bh 1.000 3,000.00 3,000.000

Tenaga Kerja

Mekanik OH 0.0833 17,600.00 1,466.08

Pembantu Mekanik OH 0.1667 14,320.00 2,387.14

Mandor OH 0.0417 77,000.00 3,210.90

Jumlah harga per-satuan pekerjaan 1,295,064.12

Harga Satuan Bahan/Upah

(Rp)

Harga Satuan Bahan/Upah

(Rp)

Page 34: Rab Masjid Unaaha Baru

PEK. TANAH

PANJANG PONDASI 1 184GALIAN PASIR URUG BATU KOSONG PONDASI URUGAN KEMBALI

119.6 M3 30.08 M3 29.44 M3 64.4 M3 39.867 M3

PANJANG PONDASI 2 30 PENINGGIAN LTPONDASI 76.8 M33.3 M3

HITUNG BETON

PANJANG PONDASI 1 184SLOOF RINGBALK KOLOM KOLOM PRAKTIS KOLOM PRAKTIS

5.52 M3 6.72 M3 3.6 M3 48 M 20.1 M 68.1

PEK. LANTAI & PLAFOND

LUAS BANGUNAN 256TEGEL LANTAI KERJA PLAFOND

256 M2 12.8 M3 256 M2

PEK. DINDING

DINDING LUAR DINDING DALAM TOTAL PLASTERAN151.6 M2 145.82 M2 297.42 M2 594.84 M2

PINTU DAN JENDELA

KP KJ KACA0.18158 M3 0.5958 M3 12.06 M2

DAUN PINTU BINGKAI JENDELA7.56 M2 7.56 M2

KUDA - KUDA & ATAP

KUDA2 I (atas) KUDA2 II (atas D) KUDA2 III (bawah) KUDA2 IV (bawah D) KUDA2 ALL0.65933 M3 0.90739 M3 1.927296 M3 0.905856 M3 4.3999 M3

ATAP 1 ATAP 2 LIST PLANK297.587 M2 106.368 M2 110.4 M

ATAP IIReng Gordeng Kasau

Page 35: Rab Masjid Unaaha Baru

0.8784 M3 2.25504 M3 1.8018 M3

Page 36: Rab Masjid Unaaha Baru

HARGA UPAH BAHAN

NAMA/JENIS BARANG SATUAN HARGA SATUAN KET

1 UPAH PEKERJA

Kepala Tukang Batu OH (7 jam) Rp 97,400 Kepala Tukang Kayu OH (7 jam) Rp 97,400 Kepala Tukang Besi OH (7 jam) Rp 97,400 Kepala Tukang Cat OH (7 jam) Rp 97,400 Kepala Tukang Listrik OH (7 jam) Rp 97,400 Kepala Tukang Pipa OH (7 jam) Rp 97,400 Kepala Tukang Jam Rp 13,914 Tukang batu OH (7 jam) Rp 83,490 Tukang Besi OH (7 jam) Rp 83,490 Tukang Kayu OH (7 jam) Rp 83,490 Tukang Cat OH (7 jam) Rp 83,490 Tukang bongkar OH (7 jam) Rp 100,000 Tukang jam Rp 11,927 Mandor OH (7 jam) Rp 77,000 Pekerja OH (7 jam) Rp 64,580 Operator OH Rp 17,600 Pembantu Operaor OH Rp 14,320 Sopir/Driver OH Rp 17,600 Pembantu Sopir OH Rp 14,320 Mekanik OH Rp 17,600 Pembantu Mekanik OH Rp 14,320

A. Bahan Pasangan

Pasir pasang/beton pasir Rp 236,710 pasir Rp 135,100 Quary

Rp 236,740 AMP Rp 249,820 Lokasi Pekerjaan

pasir urug Rp 93,100 Quary Rp 194,670 Lokasi Pekerjaan

semen/PC(50 Kg) Zag Rp 82,200 DistributorKg Rp 1,698 Lokasi AMPKg Rp 1,692 Base Camp

Semen Warna (Nak Untuk tegel) Kg Rp 22,900 Urugan Tanah Pilihan Rp 56,400 Quary

Rp 96,900 Lokasi PekerjaanUrugan tanah biasa Rp 40,100 Quary

Rp 73,900 Lokasi PekerjaanBatu Gunung Rp 112,200 Quary

Rp 230,120 Stone Crusher Rp 238,900 Lokasi Pekerjaan

Batu Pecah 1 - 2 cm Rp 354,027 Stone Crusher

M³M³M³M³M³M³

M³M³M³M³M³M³M³M³

Page 37: Rab Masjid Unaaha Baru

HARGA UPAH BAHAN

NAMA/JENIS BARANG SATUAN HARGA SATUAN KET Rp 434,235 AMP Rp 470,068 Lokasi Pekerjaan

Batu Pecah 2 - 3 cm Rp 322,707 Base Camp Rp 385,196 Lokasi Pekerjaan

Kerikil Rp 276,900 Sirtu Gunung Rp 84,600 Quary

Rp 166,215 Lokasi PekerjaanSirtu Kali Rp 50,700 Quary

Rp 120,020 Base CampKapur Rp 459,800 Batu Belah Rp 238,900 Lokasi PekerjaanAbu batu/Filler Kg Rp 1,000 Stone Crusher

Kg Rp 962 AMPKg Rp 988 Lokasi Pekerjaan

Aspal Cemen Kg Rp 13,200 DistributorKg Rp 13,287 Base CampKg Rp 13,307 Lokasi Pekerjaan

Dolken Diameter 8-10 Cm Btg Rp 8,300 Bh Rp 12,500

Kuas Roll Bh Rp 31,300 Air L Rp 57

B. Bahan Penggantung

Kunci Tanam 2 kali putar Kuda T Bh Rp 136,700 Kunci Tanam Antik Bh Rp 313,500 Grendel Jendela Bh Rp 5,600 Grendel Tanam Bh Rp 28,200 Engsel Kupu-Kupu Bh Rp 11,200 Engsel Pintu Bh Rp 18,800 Door Closer Bh Rp 156,700 Kait Angin Bh Rp 9,400

C. Bahan Lantai

Tegel Kramik KIA 30 x 30 cm Dos Rp 49,100 Tegel Kramik KIA 40 x 40 cm Dos Rp 58,500 Tegel Kramik Anti Sleep 20 x 20 Dos Rp 94,000 Tegel dinding Kramik 20 x 25 Cm Dos Rp 99,200 Tegel Kramik Motif Penyandang cacat Dos Rp 107,000 Batu Ganik Bh Rp 73,100 Tegel Kuku/Sudut Dos Rp 188,100 Semen Warna kg Rp 12,500 tempat sabun keramik Bh Rp 36,500

M³M³M³M³M³M³M³M³M³M³M³

Kuas 3"

Page 38: Rab Masjid Unaaha Baru

HARGA UPAH BAHAN

NAMA/JENIS BARANG SATUAN HARGA SATUAN KET

D. Bahan Dinding

Batako ukuran 20x40x10 Bh Rp 5,200 Batu Bata Bh Rp 670 Beton Roster/Kerawang Bh Rp 6,200

E. Bahan Penutup Langit-Langit

Asbes 3mm ukuran 100x100 lembar Rp 13,700 Tripleks tebal 3mm lembar Rp 67,900 Teakwood lembar Rp 14,500 List Plafond kayu kelas II m Rp 5,200 Multipleks 4mm lembar Rp 100,300 Multipleks 6mm lembar Rp 119,100 Multipleks 9mm lembar Rp 188,100 GipsunBoard 240x120x0.4 cm lembar Rp 81,500 KalsiBoard lembar Rp 73,100 Kayu Lapis 4 mm ukuran 8x4 cm Rp 51,700 Kayu Lapis 12 mm ukuran 8x4 cm Rp 149,400 Lapisan Bahan taco HPL Rp 235,100

F. Bahan Penutup Atap

Genteng Kodok M² Rp 26,100 Asbes Gelombang Kaki Rp 25,200 Genteng Metal M² Rp 83,600 Atap Sirap M² Rp 78,300 Alumunium M² Rp 103,400 Nok Bumbungan Genteng Kodok M Rp 18,200 Nok Bumbungan Asbes M Rp 22,900 Nok Bumbungan Genteng Metal M Rp 38,100 Nok Bumbungan Genteng Plenttong "S" Bh Rp 3,650 Genteng Plenttong Bh Rp 2,290 Seng Datar BJL.S 0,3 Lembar Rp 31,300 Seng Gelombang Kecil Kaki Rp 9,900 Atap Sakura Roof Lembar Rp 36,500 Nook Sakura Roof M Rp 39,100 Karet Talang Air M Rp 16,100

Page 39: Rab Masjid Unaaha Baru

HARGA UPAH BAHAN

NAMA/JENIS BARANG SATUAN HARGA SATUAN KETTalang Air Fiber M Rp 21,400 Lem Seng Atap Multi Roof Kg Rp 74,100 lem Seng Nok Multi Roof Kg Rp 74,100 Genteng Atap Zincalume Lbr Rp 43,100 Nok C Rad:9-9.5 : 40 cm Bh Rp 16,900 Tutup Nok Zincalume Bh Rp 42,800

G. Bahan Kayu

Kayu Balok Kelas I Rp 4,500,000 Kayu Balok Kelas II Rp 4,000,000 Kayu Balok Kelas III Rp 3,200,000 Kayu Balok Kalapi Untuk Kusen Rp 4,000,000 Kayu Balok 7/15 Silae/Bisulo/Bitti (Kelas II untuk Kuda- Rp 4,000,000 Papan Kelas I Rp 4,702,500 Papan Kelas II Rp 4,000,000 Papan Kelas III Rp 3,500,000 Papan Kelas IV Rp 2,090,000 Balok Kayu Bitti Rp 4,000,000 Kayu Besi dia 20 cm M Rp 60,000 Kayu Besi dia 30 cm M Rp 150,000 Plywood 9 mm Lbr Rp 137,500

H. Bahan Besi dan Aluminium

Baja Tulangan U24 Polos Kg Rp 21,000 Baja Tulangan U32 Polos Kg Rp 23,300 Baja Tulangan U32 Ulir Kg Rp 27,800 Baja Tulangan U39 Ulir Kg Rp 30,500 Baja Tulangan U48 Ulir Kg Rp 33,600 Besi Struktur Kg Rp 18,100 kawat Beton Kg Rp 26,100 Kawat Bronjong Kg Rp 52,800 Modifier Kg Rp 23,000 Baja Struktur (Bangunan Konstruksi Baja) Kg Rp 18,100 Elascomer 3 cm Bh Rp 645,000 Elascomer 6 cm Bh Rp 1,980,000 Kawat Las Kg Rp 17,500 Pipa Baja Bergelombang Kg Rp 17,500 Angker/Baut/ Plat Pengikat untuk Kuda-Kuda/Consol Kg Rp 20,900 Paku Kg Rp 20,000 Paku Campur Kg Rp 20,000 Paku Seng Kg Rp 28,200 Paku Biasa Kg Rp 19,800 Paku Anti karat Kg Rp 31,300

M³M³M³M³M³M³M³M³M³M³

Page 40: Rab Masjid Unaaha Baru

HARGA UPAH BAHAN

NAMA/JENIS BARANG SATUAN HARGA SATUAN KETPaku Tripleks/Pladfond Kg Rp 26,100 Paku GipsunBoard Kg Rp 16,700 Paku KalsiBoard Kg Rp 17,700 Paku Skrup Kg Rp 26,100

I. Bahan Cat

Cat Besi Kg Rp 13,000 Flamir tembok Kg Rp 8,800 Flamir Kayu Kg Rp 16,100 Cat Tembok

Boyo 23 kg Kg Rp 5,200 Avitex Kg Rp 10,200 Vinilex Nippon Paint Kg Rp 97,900 Metrolight Kg Rp 26,100

Cat KayuGlotex Kg Rp 41,800 Avian Kg Rp 45,700 Platone Kg Rp 43,200 Polytur Kg Rp 3,400 Meni Kg Rp 3,400 Minyak Cat L Rp 3,400

Cat Minyak Kg Rp 13,000 Cat Mini Kayu Kg Rp 19,500 Cat Atap Seng (Merk YOKO) Kg Rp 16,900 Cat Vernis Kg Rp 9,700 Meni Besi Kg Rp 14,800 Politur L Rp 44,500 Dempul Kayu Kg Rp 16,300 Residu Kg Rp 9,500 Kuas Biasa 3cm Bh Rp 3,900 Amplas Kasar Lebar Rp 4,500 Amplas Halus Lebar Rp 4,500 Cat Marka (Non Thermoplas) Kg Rp 92,400 Cat Marka (Thermoplastic) Kg Rp 118,800

J Bahan sanitair/Sanitasi/Saluran Air

Pipa PVC diameter 3/4 Inci M Rp 27,600 Pipa PVC diameter 1 Inci M Rp 33,400

Page 41: Rab Masjid Unaaha Baru

HARGA UPAH BAHAN

NAMA/JENIS BARANG SATUAN HARGA SATUAN KETPipa PVC diameter 1 1/2 Inci M Rp 47,750 Pipa PVC diameter 2 Inci M Rp 62,100 Pipa PVC diameter 3 Inci (RR - Join) M Rp 76,400 Pipa PVC diameter 4 Inci (RR- Join) M Rp 112,900 Pipa PVC diameter 6 Inci (RR- Join) M Rp 241,000 Pipa PVC diameter 8 Inci (RR- Join) M Rp 371,800 Pipa PVC diameter 10 Inci (RR- Join) M Rp 582,100 Pipa GI diameter 1 1/2 Inci M Rp 185,100 Pipa GI diameter 2 Inci M Rp 246,800 Pipa GI diameter 3 Inci M Rp 368,600 Pipa GI diameter 4 Inci M Rp 500,300 Pipa GI diameter 6 Inci M Rp 1,222,600 Pipa GI diameter 8 Inci M Rp 1,395,000 Pipa GI diameter 10 Inci M Rp 1,802,600 Reducer TEE PVC diameter 10x8 inci Bh Rp 1,485,400 Reducer TEE PVC diameter 8x6 inci Bh Rp 928,300 Reducer TEE PVC diameter 6x4 inci Bh Rp 773,500 Reducer TEE PVC diameter 4x3 inci Bh Rp 574,000 Reducer PVC diameter 10x4 inci Bh Rp 1,214,800 Reducer PVC diameter 8x6 inci Bh Rp 624,100 Reducer PVC diameter 6x4 inci Bh Rp 327,400 Reducer PVC diameter 4x3 inci Bh Rp 143,900

Bh Rp 957,000 Bh Rp 1,148,000 Bh Rp 1,449,900 Bh Rp 3,828,300 Bh Rp 1,953,200 Bh Rp 2,056,000 Bh Rp 3,012,500

Teeflange GI dia 8x8 Inci Bh Rp 2,586,300 Teeflange GI dia 14 x 6 Inci Bh Rp 3,167,100 Teeflange GI dia 14 x 10 Inci Bh Rp 4,750,500 Teeflange GI dia 20 x 10 Inci Bh Rp 7,125,800 Tee PVC (RR) dia 12 x 10 x 12 Inci Bh Rp 3,820,200 Tee PVC (RR) dia 12 x 6 x 12 Inci Bh Rp 3,439,200 Tee PVC (RR) dia 12 x 12 x 12 Inci Bh Rp 3,309,500 Tee PVC (RR) dia 12 x 8 x 12 Inci Bh Rp 2,745,600 Tee PVC (RR) dia 8 x 6 x 8 Inci Bh Rp 1,712,300 Tee PVC (RR) dia 8 x 4 x 8 Inci Bh Rp 1,521,400 Tee PVC (RR) dia 6 x 6 x 6 Inci Bh Rp 1,324,500 Tee PVC (RR) dia 6 x 4 x 6 Inci Bh Rp 1,204,700 Tee PVC (RR) dia 4 x 4 x 4 Inci Bh Rp 762,300 Tee PVC (RR) dia 4 x 3 x 4 Inci Bh Rp 688,100 Tee PVC (RR) dia 3 x 3 x 3 Inci Bh Rp 596,900 Flange GI dia 6 Inci Bh Rp 753,100 Flange GI dia 8 Inci Bh Rp 1,075,000

Bend PVC dia 4x22.5°Bend PVC dia 6x45°Bend PVC dia 6x90°Bend PVC dia 8x22.5°Bend PVC dia 8x45°Bend PVC dia 8x90°Band PVC dia 10 Inci x 45 °

Page 42: Rab Masjid Unaaha Baru

HARGA UPAH BAHAN

NAMA/JENIS BARANG SATUAN HARGA SATUAN KETFlange GI dia 10 Inci Bh Rp 1,369,300 Flange GI dia 12 Inci Bh Rp 1,662,800 Flange GI dia 14 Inci Bh Rp 1,956,200 Flange GI dia 16 Inci Bh Rp 2,249,600 Flange GI dia 20 Inci Bh Rp 2,934,300 Flange Spigot dia 4 Inci Bh Rp 791,900 Flange Spigot dia 6 Inci Bh Rp 1,258,300 Flange Spigot dia 8 Inci Bh Rp 2,005,800 Flange Spigot dia 10 Inci Bh Rp 2,809,900 gate Valve dia 3 Inci Bh Rp 1,956,200 gate Valve dia 4 Inci Bh Rp 4,288,600 gate Valve dia 6 Inci Bh Rp 6,809,200 gate Valve dia 8 Inci Bh Rp 8,803,000 gate Valve dia 10 Inci Bh Rp 11,737,400 Air Valve dia 2 x 3/4 Inci Bh Rp 146,700 Air Valve dia 3 x 0.8 Inci Bh Rp 176,000 Air Valve dia 4 x 0.8 Inci Bh Rp 293,400 Air Valve dia 6 x 1 Inci Bh Rp 342,300 Air Valve dia 8 x 1 Inci Bh Rp 489,000 Air Valve dia 10 x 1 Inci Bh Rp 684,600 DOP GI dia 8 Inci Bh Rp 862,600 DOP PVC 10 Dia Inci Bh Rp 1,241,400 DOP PVC 8 Dia Inci Bh Rp 602,000 DOP PVC 6 Dia Inci Bh Rp 314,300 DOP PVC 4 Dia Inci Bh Rp 12,500 DOP PVC 3 Dia Inci Bh Rp 29,600 Dreser Joint Dia 20 Inci Bh Rp 3,636,300 Dreser Joint Dia 14 Inci Bh Rp 2,727,100 Dreser Joint Dia 12 Inci Bh Rp 2,045,300 Dreser Joint Dia 10 Inci Bh Rp 1,533,900 Dreser Joint Dia 8 Inci Bh Rp 1,150,400 Dreser Joint Dia 6 Inci Bh Rp 862,600 Water Meter Dia 6 Inci Bh Rp 13,204,600 Water Meter Dia 8 Inci Bh Rp 15,845,500 Water Meter Dia 10 Inci Bh Rp 19,014,500 Seal Tipe/Isolasi Pipa Bh Rp 12,600 Multiplek 4 mm Lbr Rp 112,600 KP/Isolasi Pipa Bh Rp 9,600 Pasangan Balk Air 0.4 m3 (Ditegel 10 x 20) + Sumbat Ba Bh Rp 224,600 Closet Duduk Toto Bh Rp 2,090,000 Closet Duduk KIA Bh Rp 418,000 Closet Duduk Porselin Bh Rp 182,800 Wastafel M3 Rp 209,000 Bak Cuel Logam 1 Lubang Bh Rp 261,200 Bak Mandi Fiber Glass Bh Rp 313,500 Kran Air Bh Rp 47,000

Page 43: Rab Masjid Unaaha Baru

HARGA UPAH BAHAN

NAMA/JENIS BARANG SATUAN HARGA SATUAN KETFlor Drain Urin Noir Buis Beton dia 10 Cm Bh Rp 26,100 Kran Kuning Dia 1/2 Inci Bh Rp 1,567,500 Kran Kuning Dia 3/4 Inci Bh Rp 41,800 Jetwasher Bh Rp 25,000 Penyambung Pipa PVCSoker Dia 1/2" - 3/4" Bh Rp 3,135 Knee dia 1/2" - 3/4" Bh Rp 3,135 elbow diameter 1/2" s/d 3/4" Bh Rp 3,950 tee Stuk diameter 1/2" s/d 3/4" Bh Rp 3,700 lem pipa PVC Lbr Rp 22,600 lem alteco 110 Bh Rp 5,200 water meter 3/4 inci Bh Rp 815,488 water meter 2 inci Bh Rp 2,988,896 water meter 3 inci Bh Rp 4,470,109 water meter 4 inci Bh Rp 5,979,431 Water Noor (Galvans) 1/2 inci Bh Rp 11,678 Water Noor (Galvans) 3/4 inci Bh Rp 13,121 Water Noor (Galvans) 1 inci Bh Rp 29,011 Water Noor (Galvans) 1 1/2 inci Bh Rp 39,221 Water Noor (Galvans) 2 inci Bh Rp 79,959 Pipa PVC - AW dia 1/2 inci 4 m Btg Rp 84,645 Pipa PVC - AW dia 3/4 inci 4 m Btg Rp 100,940 Pipa PVC - AW dia 1 inci 4 m Btg Rp 116,802 Pipa PVC - AW dia 1 1/4 inci 4 m Btg Rp 288,403 Pipa PVC - AW dia 1 1/2 inci 4 m Btg Rp 304,264 Pipa PVC - AW dia 2 inci 4 m BtgBall Valve GL uk. 3/4 inci Bh Rp 336,710 Ball Valve GL uk. 1/2 inci Bh Rp 416,741 Gate Valve GL uk. 4 inci Bh Rp 456,376 Gate Valve GL uk. 3 inci BhGate Valve GL uk. 2 1/2 inci Bh Rp 497,494 Gate Valve GL uk. 2 inci Bh Rp 41,596 Gate Valve GL uk. 1 1/2 inci Bh Rp 49,531 Pipa Water Moor GL Uk. 3 Inci Bh Rp 78,589 Pipa Water Moor GL Uk. 1 Inci Bh Rp 12,338 Stop kran biasa 1/2 inci Bh Rp 32,329 Stop kran biasa 2/4 inci Bh Rp 46,258 Stop kran biasa 3 inci Bh Rp 68,149 Stop kran biball 1/2 inci BhKran Biasa 1/2 Bh Rp 39,871 Kran Biasa 3/4 Bh Rp 37,000 Doubel Nepel (Glasvanis) 1/2 inci Bh Rp 32,660 Doubel Nepel (Glasvanis) 3/4 inci Bh Rp 29,560 Doubel Nepel (Glasvanis) 1 inci Bh Rp 15,284 Doubel (Glasvanis) 1/2 inci Bh Rp 10,814 Doubel (Glasvanis) 3/4 inci Bh Rp 69,143

Page 44: Rab Masjid Unaaha Baru

HARGA UPAH BAHAN

NAMA/JENIS BARANG SATUAN HARGA SATUAN KETDoubel (Glasvanis) 1 inci Bh Rp 55,517 Plug (Glasvanis) 1/2 inci Bh Rp 55,804 Plug (Glasvanis) 3/4 inci Bh Rp 59,770 Pipa PVC Uk. 1/2 Inci M Rp 8,800 Pipa PVC Uk. 1 Inci M Rp 13,600 Pipa PVC Uk. 1 1/2 Inci M Rp 20,900 Pipa PVC Uk. 2 Inci M Rp 32,200 Pipa PVC Uk. 2 1/2 Inci M Rp 49,600 Pipa PVC Uk. 3 Inci M Rp 76,400 Pipa PVC Uk. 4 Inci M Rp 112,900 Pipa PVC Uk. 6 Inci M Rp 241,000 Pipa PVC Uk. 8 Inci 250 mm M Rp 371,800 Pipa PVC Uk. 10 Inci M Rp 687,556

K. bahan Lain

Kaca Bening 5 mm M² Rp 88,800 Pompa Tangan Bh Rp 3,657,500 Kaca Bening 5 mm M² Rp 114,900 Kaca Rasa (Cermin) Lembar M² Rp 41,800 Glass Block Bh Rp 18,200 Instalasi Listrik Titik Rp 167,200 Pipa Union Untuk Kabel

5/8 Inci- 4m Btg Rp 7,400 34/ inci - 4 m Btg Rp 23,700 1 inci - 4 m Btg Rp 26,600

type NYA2x 2.5 mm Roll Rp 176,600

Type NYH2 x 1.1/2 mm Roll Rp 679,200 2 x 2.1/2 mm Roll Rp 910,100 2 x 4 mm Roll Rp 1,209,000

Pipa Listrik PVC 5/8 Btg Rp 7,400 Sakelar Tunggal Broco Bh Rp 13,500 Sakelar Double Broco Bh Rp 16,300 Stop Kontak Bh Rp 13,500 Sekring Kaat 1 Group/ Asli Bh Rp 36,600 Sekring Kaat 2 Group/ Asli Bh Rp 50,900 Sekring Kaat 1 Group/ Biasa Bh Rp 17,800 Sekring Kaat 2 Group/ Biasa Bh Rp 26,300 Fitting Gantung Broko Bh Rp 3,360 Fitting flafon Brocko Bh Rp 10,100 Bola Lampu 15 sd 75 watt pijar Bh Rp 5,400

Page 45: Rab Masjid Unaaha Baru

HARGA UPAH BAHAN

NAMA/JENIS BARANG SATUAN HARGA SATUAN KETBola Lampu 100 watt Bh Rp 6,700 Lampu TL Philips 1 x 20w Bh Rp 13,500 Lampu TL Philips 2 x 20w Bh Rp 24,500 Lampu TL Philips 1 x 40w Bh Rp 13,500 Lampu TL Philips 2 x 40w Bh Rp 176,600 Lampu TL Lingkar 32 w Bh Rp 25,800 Lampu TL Lingkar 20 w Bh Rp 23,000 Lampu PLC 5 Watt Philips Bh Rp 20,300 Lampu PLC 6 Watt Bh Rp 28,500 Lampu PLC 11 Watt Bh Rp 32,000 Lampu PLC 14 Watt Bh Rp 27,100 Lampu PLC 18 Watt Bh Rp 33,900 Lampu PLC 23 Watt Bh Rp 39,300 Lampu PLC 24 Watt Bh Rp 40,700 Lampu Pijar 25 Watt Bh Rp 4,700 Lampu Pijar 45 Watt Bh Rp 4,700 Lampu Pijar 60 Watt Bh Rp 5,400 Lampu Pijar 100 Watt Bh Rp 5,400 Lampu Taman Mercury Bh Rp 142,600 Lampu RM 2 x 20 Bh Rp 237,700 Lampu RM 2 x 40 Bh Rp 312,400 Lampu Down Light Bh Rp 61,100 Panel Listrik Bh Rp 2,037,700 Kayu Perancah Rp 2,100,000 Kayu bakar Rp 2,200,000 Minyak Pemlumas/ Oil L Rp 28,800 Plastik Filter Rp 43,000 Pipa Porus M Rp 148,000 Minyak Fluks L Rp 1,350 Bunker Oil L Rp 1,850 Terma Plastik Kg Rp 53,000

M³M³