REKAPITULASI OPNAM PEKERJAAN
PEMBANGUNAN GEDUNG KANTOR DPRDKABUPATEN SIJUNJUNG
Project : Pembangunan Gedung Kantor DPRD Sijunjung
PRESTASI PRESTASI PRESTASI SISANO URAIAN PEKERJAAN JUMLAH TOTAL (Rp.) YANG LALU SAAT INI S/D SAAT INI PRESTASI
( % ) ( % ) ( % ) ( % )
I PEKERJAAN PLAFON DAN RANGKA 1,227,380,467.76 1,188,782,877 38,597,591 1,227,380,468 -
TOTAL UPAH PEKERJAAN 1,227,380,467.76 1,188,782,877 38,597,591 1,227,380,468 -
TOTAL 1,188,782,877 38,597,591 1,227,380,468 - Jumlah yang dibayarkan 1,188,782,877 38,597,591 1,227,380,468 - Jumlah yang dibayarkan ( Dibulatkan ) 1,188,782,000 38,597,000 1,227,380,000 -
Note :Pengambilan Uang : 993,500,000 Opnam s/d saat ini : 1,227,380,000 Retensi 5% : 61,369,000 Jumlah yang dibayarkan : 172,511,000
RINCIAN OPNAM PEKERJAANPEMBANGUNAN GEDUNG KANTOR DPRD
KABUPATEN SIJUNJUNG
Project : Pembangunan Gedung Kantor DPRDNo. SPK : Pekerjaan : Pekerjaan Plafon dan RangkaOpnam ke :
HARGA JUMLAH VOLUME
PRESTASI VOLUME
PRESTASI VOLUME
PRESTASI NO URAIAN PEKERJAAN VOLUME SATUAN UPAH HARGA UPAH YANG LALU SAAT INI S/D SAAT INI
( Rp. ) ( Rp. ) ( % ) ( Rp. ) ( % ) ( Rp. ) ( % ) ( Rp. )
I PEKERJAAN KUDA KUDA DAN ATAP
1 Pekerjaan Plafon dan RangkaPlafon Akustik 4,488.00 m2 98,863 443,697,711 4,263.60 m2 95% 421,512,825 224.40 m2 5% 22,184,886 4,488.00 m2 100% 443,697,711
Rangka Plafon Akustik 4,488.00 m2 58,637 263,162,289 4,375.80 m2 98% 256,583,232 112.20 m2 2% 6,579,057 4,488.00 m2 100% 263,162,289
Plafon Gypsum + Rangka 2,966.00 m2 97,500 289,185,000 2,966.00 m2 100% 289,185,000 - m2 0% - 2,966.00 m2 100% 289,185,000
Plafon Kalsiboard + Rangka 295.00 m2 117,500 34,662,500 295.00 m2 100% 34,662,500 - m2 0% - 295.00 m2 100% 34,662,500
List Profil 1,771.32 m' 17,500 30,998,100 1,682.75 m' 95% 29,448,195 88.57 m' 5% 1,549,905 1,771.32 m' 100% 30,998,100
PEKERJAAN ADDPlafon Gypsum + Rangka 804.87 m2 97,500 78,474,593 764.62 m2 95% 74,550,863 40.24 m2 5% 3,923,730 804.87 m2 100% 78,474,593
Plafon Kalsiboard + Rangka 742.13 m2 117,500 87,200,275 705.02 m2 95% 82,840,261 37.11 m2 5% 4,360,014 742.13 m2 100% 87,200,275
SUB TOTAL 1,227,380,468 1,188,782,877 38,597,591.151 1,227,380,468 TOTAL UPAH PEKERJAAN 1,188,782,877 38,597,591 1,227,380,468
TOTAL 1,188,782,877 38,597,591 1,227,380,468 Jumlah yang dibayarkan 1,188,782,877 38,597,591 1,227,380,468 Jumlah yang dibayarkan ( Dibulatkan ) 1,188,782,000 38,597,000 1,227,380,000