R. RayMu2e Project manager
R. Ray - Mu2e WGM 2
L2 Systems and Managers
1.2 Accelerator
S. WerkemaFNAL
1.3 Conventional ConstructionT. Lackowski
FNAL
1.4 Solenoids
M. LammFNAL
1.5 Muon Channel
S. FeherFNAL
1.6 Tracker
A. MukherjeeFNAL
1.7 Calorimeter
INFN
1.8 Cosmic Ray
VetoC. Dukes
UVa.
1.9 Trigger and
DAQM. Bowden
FNAL
1.1 Project
ManagementR. RayFNAL
• Steve Werkema has filled the spot vacated by Mike Syphers.• Steve was already engaged as a L3 leader, so he has hit the
ground running.• Jim Morgan has replaced Steve as the L3• Vladimir Nagaslaev will serve as Steve’s deputy.
R. Ray - Mu2e WGM 3
Superconductivity Conference
• Significant fraction of solenoid team attended the Applied Superconductivity Conference in Washington DC in early August.
Significant vendor presence at conference• With help from Bruce Strauss (DOE/OHEP) Mu2e organized a
meeting with interested vendors to discuss industrial opportunities for the Mu2e solenoids
• Mike Lamm made a presentation to a nearly full room of vendors.• The following morning we had private conversations with a number of
vendors.• Significant interest in this project by people who have relevant
experience and can do the job.• We learned a lot from the discussions and will likely modify our
procurement plan based on what we learned.
R. Ray - Mu2e WGM 4
Solenoids: Next steps
• Finish reference designs and write an abbreviated magnet “CDR” that describes those designs.
• Distribute to industry as part of an RFI to further gauge interest and capabilities.
• Make site visits to verify capabilities• Send out RFP, select vendors and obligate funds as soon as possible
after CD-1. Procurement plan will determine what we ask for in RFP.
R. Ray - Mu2e WGM 5
ES&H
• Project Information Form (PIF) completed and sent to PPD ES&H. Sending up the ES&H chain. Need to complete Radiation Protection Plan to understand full impact of
operating at 23 kW. PIF is important input for a CX for Mu2e.
o Would like to get this signed off on as soon as we can, otherwise we have to plan for and identify resources to work on an EA.
• Completed 1st draft of Preliminary HA (required for CD-1) based on input from L2 Managers
32 pages of text. 96 pages of Hazard analysis sheets Sent to PPD ES&H for comment
R. Ray - Mu2e WGM 6
Zones
R. Ray - Mu2e WGM 7
Hazards
R. Ray - Mu2e WGM 8
Hazards identified in every zone
R. Ray - Mu2e WGM 9
R. Ray - Mu2e WGM 10
Only take credit for passive mitigation measures. Active mitigation measures will reduce risks further.
• There are no unmitigated risks that are deemed to be Critical but a number of potentially High risks that could be present in Mu2e in the absence of passive mitigation.
• When taking into account the planned passive mitigations there are no risks higher than Moderate and most are Low or Minimal. Active mitigation measures will reduce the risks even farther.
R. Ray - Mu2e WGM 11
Other Documents
• Starting to Work on Acquisition Strategy and PEP with DOE• Mature drafts also exist for
Project assumptions document PMP Integrated Safety Management Plan Security Vulnerability Assessment Configuration Management Plan Risk Management Plan Quality Management Plan
R. Ray - Mu2e WGM 12
Handoff to Operations
• Added some text to the PMP to try and define where the Project’s responsibility ends.
• Handoff has not always been seamless in the past, so Lab/DOE has become sensitized to the issue.
• Handoff of beamline to AD After the performance of all individual components has been tested for
compliance with specifications. Responsibility of the Accelerator Division to perform system level commissioning with beam.
• Handoff of detector hall to PPD Once beneficial occupancy has been granted, the Mu2e Project will hand over
operational responsibility for the Mu2e Detector Hall to the Particle Physics Division.
Building Management and ES&H oversight. Utilities will be funded from an operations budget.
R. Ray - Mu2e WGM 13
Handoff – cont.
• Handoff of detector to collaboration The Mu2e Project is responsible for all commissioning activities of the solenoids
and detector systems up to the point where proton beam is required. The solenoids will be commissioned as a single magnetic system. Solenoid commissioning will include operation at full field, field mapping, quench
studies and complete exercising of the controls system. The Cosmic Ray Veto, Tracker, Calorimeter and DAQ will be commissioned for
full functionality using cosmic rays. Once all systems have been successfully commissioned and the detector is ready
for beam, the apparatus will be handed off to the Mu2e Collaboration Runs with cosmic rays will not test the detector components or the DAQ at the
rates required during beam operations, so some additional commissioning will be required when beam is available.
R. Ray - Mu2e WGM 14
Pre CD-1 Review
• LBNE had a pre-CD-1 review last month. Run by Lab but with a small committee from outside lab. Just cost, schedule and management. LBNE is not done with cost and schedule. Reviewers wanted to see where they
were to estimate when they would be ready for CD-1 Evaluate how they are planning to do their cost and schedule, tools in place, etc.
We will have a similar review in the Fall. Working on the details.
R. Ray - Mu2e WGM 15
CD-1
Lehman CD-1 Review March 1, 2011
Director’s Review Feb. 1, 2011
CDR complete Jan. 15, 2011
Final cost & schedule and associated documentation.
Jan. 15, 2011
L2 CDR contributions submitted Dec. 1, 2010
Pre CD-1 Cost and Schedule Review Nov 15, 2010
Director’s Design Review Nov. 1, 2010
L2 Design Reviews October, 2010
Time
R. Ray - Mu2e WGM 16
Schedule
CD-1 CD-2/3a
CD-3b
R. Ray - Mu2e WGM 17
Requirements
R. Ray - Mu2e WGM 18
Action Items
• Get L2 Manager for calorimeter in place – R. Ray Still working on this. Won’t happen until September.
• Quantify safety factor for Heat Shield/Production Solenoido Think we are “OK” but we have to be more quantitative about what “OK”
means (safety factor). Measurements being made in Japan on cold aluminum samples in the Fall could change this perception.
• Get moving on Electronics – Ron Ray Met with PPD to discuss Project EE. Expect a name soon. Progress on tracker electronics. Need to make some progress on Calorimeter and CRV electronics.
• Complete set of requirements documents – Miller/Bernstein Really want to finish these by the next meeting