JUKNIS PERENCANAAN 2014

235
DINAS PEKERJAAN UMUM KOTA LHOKSEUMAWE LEMB BIDANG PERENCANAAN DAN PROGRAM KODE PAKET KEGIATAN KONSULTAN URAIAN PERMASALAHAN UNTUK PERBAIKAN TANGGAL ASISTENSI DIKOREKSI OLEH DINAS PU

Transcript of JUKNIS PERENCANAAN 2014

Page 1: JUKNIS PERENCANAAN 2014

DINAS PEKERJAAN UMUM KOTA LHOKSEUMAWELEMBAR ASISTENSIBIDANG PERENCANAAN DAN PROGRAM

KODE PAKETKEGIATANKONSULTAN

URAIAN PERMASALAHAN UNTUK PERBAIKANTANGGAL ASISTENSI

DIKOREKSI OLEH DINAS

PU

DIKETAHUI DAN

DIPAHAMI OLEH

KONSULTAN

DIKETAHUI OLEH PPK

Page 2: JUKNIS PERENCANAAN 2014
Page 3: JUKNIS PERENCANAAN 2014

REGISTER ASISTENSI PERTAMABIDANG PERENCANAAN DAN PROGRAM

NAMA REKANAN

KODE REKENING KEGIATAN

JUDUL KEGIATAN

JUDUL PEKERJAAN

SATKER PENGGUNA ANGGARAN

PEJABAT PEMBUAT KOMITMEN NAMA :(hanya untuk Dinas Luar) TELEPON :

KODE PAKET

NILAI FISIK Rp.

NILAI KONTRAK PERENCANAAN Rp.

CONTACT PERSONTEAM NAMA :LEADER TELEPON :

TANGGAL TERIMA DOKUMEN

DITERIMA OLEH NAMA: TANDA TANGAN

Catatan-catatan:

Page 4: JUKNIS PERENCANAAN 2014

DINAS PEKERJAAN UMUM KODE PAKET:

KOTA LHOKSEUMAWE

FORM SURVEYNAMA REKANAN :PEKERJAAN :KEGIATAN :

PARAF

SurveyorTeam Leader

Estimator/Engineer

Page 5: JUKNIS PERENCANAAN 2014

catatan: lembar ini dapat diperbanyak sesuai kebutuhan

PARAF

SurveyorTeam Leader

Estimator/Engineer

Page 6: JUKNIS PERENCANAAN 2014

catatan: lembar ini dapat diperbanyak sesuai kebutuhan

PARAF

Surveyor

Lhokseumawe, …. , 2014

cap stempel dan tandatangan cap stempel dan tandatangan

Team Leader

Estimator/Engineer

Diketahui olehKeuchik Gampong …

Penanggungjawab PerencanaanPT./CV. …

Page 7: JUKNIS PERENCANAAN 2014

(nama terang) (nama terang)Direktur

Page 8: JUKNIS PERENCANAAN 2014

REKAPITULASI RENCANA ANGGARAN BIAYA

Kegiatan : Pembangunan Gedung Kantor XXXXXPekerjaan : Pembangunan GedungLokasi : Gampong ... , Kecamatan ...T.A. : 2014

NO.URAIAN

JUMLAH TOTAL HARGA

Divisi 1 Design development Rp. 450,000.00

Divisi 2 Sitework Rp. 889,000.00

Divisi 3 Pekerjaan Struktural Rp. 8,745,090.00

Divisi 4 Pekerjaan Arsitektur Rp. -

Divisi 5 Pekerjaan Mekanikal Rp. -

Divisi 6 Pekerjaan Elektrikal Rp. -

Divisi 7 Fasilitas eksterior bangunan Rp. -

Divisi 8 Pekerjaan Mekanikal Rp. -

Divisi 9 Pekerjaan Mekanikal Rp. -

REKAPITULASI JUMLAH TOTAL Rp. 10,084,090.00

terbilang: ...

Lhokseumawe, .... Mengetahui CV. Cok Dari Agen Sabee

Kepala Bidang Program dan Perencanaan Penanggungjawab PerencanaanDinas Pekerjaan Umum Kota Lhokseumawe

TUTI INDRIANI, ST, MM Hananan PerkasaNIP. 19680614 199703 2 002 Direktur

MenyetujuiKepala Dinas Pekerjaan Umum Kota Lhokseumawe

Ir. TEUKU ZAHEDI, MTNIP. 19621103 199203 1 001

Page 9: JUKNIS PERENCANAAN 2014

RENCANA ANGGARAN BIAYA

Kegiatan :Pekerjaan :Lokasi :T.A. :

NO. URAIANVolume Sat. Analisa Harga Satuan Jumlah Harga

(Rp.) (Rp.) Divisi 1 Design development

1.1 Dokumen kontrak 1.000 Ls. Taksir 150,000.00 150,000.00 1.2 Asuransi dan jaminan - - - 1.3 Shop drawing dan as-built drawing 1.000 Ls. Taksir 150,000.00 150,000.00 1.4 Site management - - - 1.5 Dokumentasi proyek 1.000 Ls. Taksir 150,000.00 150,000.00

Total Jumlah Harga Divisi 1 : 450,000.00 Divisi 2 Sitework

2.1 Setting-out2.2 Fasilitas sementara2.3 Mobilisasi dan demobilisasi2.4 Pembersihan lahan dan removal

2.5 Galian, pemotongan, timbunan dan buangan2.5.1 Timbunan pasir bawah lantai 5.000 m3 Anl. SNI 2835-2008 6.11 177,800.00 889,000.00

Total Jumlah Harga Divisi 2 : 889,000.00 Divisi 3 Pekerjaan Struktural

3.1 Pekerjaan struktural di atas tanah3.1.1 Cor rabat beton K-125 10.000 m3 Anl. SNI 7394-2008 6.2 874,509.00 8,745,090.00 3.1.2 Kolom Lantai 1 tipe K1, uk. (40x40) cm3.1.2 Kolom Lantai 1 tipe K2, uk. (40x40) cm3.1.3 dst.

3.2 Pekerjaan struktural di bawah tanah3.2.1 Pondasi tipe P1, uk. (120x120x40) cm

3.3 Mobilisasi dan demobilisasiTotal Jumlah Harga Divisi 3 : 8,745,090.00

Divisi 4 Pekerjaan Arsitektur4.1 Beton4.2 Logam4.3 Kayu dan plastik

4.3.1 Rangka kuda-kuda kayu kelas-I tipe-1 m34.3.1 Rangka kuda-kuda kayu kelas-I tipe-2 m3

4.4 Pasangan (masonry)4.5 Perlindungan suhu dan kelembaban

4.5.1 Pengecatan dinding luar4.5.2 Pengecatan dinding dalam4.5.3 Pekerjaan plafond gypsum

dst.4.6 Bukaan (jendela, pintu, kusen)4.7 Finishing

4.7.1 Railing tangga stainless steel tipe-1dst.

Total Jumlah Harga Divisi 4 : - Divisi 5 Pekerjaan Mekanikal

5.1 Plambing

5.25.3 Pencegahan Kebakaran

Total Jumlah Harga Divisi 5 : - Divisi 6 Pekerjaan Elektrikal

6.1 Sistem distribusi jaringan listrik6.2 Sistem pencahayaan6.3 Sistem komunikasi6.4 Pencegahan petir

Total Jumlah Harga Divisi 6 : - Divisi 7 Fasilitas eksterior bangunan

7.1 Paving, perparkiran, pedestrian7.2 Pagar dan gerbang

7.3Total Jumlah Harga Divisi 7 : -

Divisi 8 Interior fixtures8.18.2

Total Jumlah Harga Divisi 8 : -

ParafTeam Leader Estimator

Pemanasan, ventilasi dan pengkodisian udara

Pertamanan dan landscaping (tanaman, rumput, tanah)

Page 10: JUKNIS PERENCANAAN 2014

NO. URAIANVolume Sat. Analisa Harga Satuan Jumlah Harga

(Rp.) (Rp.) Divisi 9 Miscellneous works

9.1 Peralatan9.2 Konstruksi khusus9.3 Conveying equipment

Total Jumlah Harga Divisi 9 : -

Lhokseumawe, .... CV. Cok Dari Agen Sabee

Penghitung RAB/Estimator Team Leader

Konlonhitung HanakuturiEstimator Team Leader

Penanggungjawab Perencanaan

Hananan PerkasaDirektur

Catatan: item-item pekerjaan dapat dikembangkan sesuai kebutuhan

Page 11: JUKNIS PERENCANAAN 2014

DAFTAR HARGA UPAH

NO. URAIAN SATUAN HARGA (Rp)

1 Mandor OH 80,000.00 2 Kepala Tukang OH 100,000.00 3 Tukang OH 80,000.00 4 Tukang Batu OH 80,000.00 5 Tukang Kayu OH 80,000.00 6 Tukang Las Konstruksi OH 80,000.00

Tukang Besi Konstruksi OH 80,000.00 7 Pekerja OH 70,000.00 8 Penjaga Malam / SATPAM OH 46,500.00 9 Supir OH 100,000.00

10 Operator OH 135,000.00

DAFTAR HARGA BAHAN

NO. URAIAN SATUAN HARGA (Rp)

1 Abu Bata 520,000.00 2 Acustic 30 x 60 Lembar 148,000.00 3 Alat-alat Bantu Unit 212,000.00 4 Alti Meter Unit 4,346,000.00 5 Alumunium Foil M2 12,000.00 6 Arang Kg 4,000.00 7 Asbes Eternit 1 x 1 m M2 22,000.00 8 Asbes Gelombang Besar Lembar 57,000.00 9 Asbes Gelombang Kecil Lembar 53,000.00

10 Asbes Quality 1 x 1 m Lembar 28,000.00 11 Asphalt Kg 20,000.00 12 Asphalt Semen Pen. 60/70 atau Pen. 80/100 Kg 13,000.00 13 Atap Asbes Gelombang 8 Kaki Lembar 57,000.00 14 Atap Harflek Lembar 84,000.00 15 Atap multiroof M2 54,000.00 16 Atap Naungan Lembar 4,000.00 17 Atap Rumbia Lembar 4,000.00 18 Ayakan Buah 66,000.00 19 Baja Profil) Kg 14,000.00 20 Bak Cuci Piring Logam Buah 363,000.00 21 Bak Cuci Tangan / Wastaafel Keramik Buah 445,000.00 22 Bak Mandi Fibre Buah 445,000.00 23 Bak Mandi Plastik Buah 445,000.00 24 Bak Mandi Porselin Buah 1,484,000.00 25 Bambu Batang 13,000.00 26 Bataco Buah 8,450.00 27 Batu Bata Buah 570.00 28 Batu Belah 0.5 - 1 cm 455,000.00 29 Batu Belah 1 - 2 cm 455,000.00 30 Batu Belah 10 - 15 cm 455,000.00 31 Batu Belah 3 - 5 cm 455,000.00 32 Batu Belah 5 - 7 cm 455,000.00

33 Batu Belah 7 - 10 cm 455,000.00

34 Batu Gunung 233,000.00

35 Batu Gunung Quary 106,000.00

36 Batu ( < 250 ) Kg - Material Water Break 268,000.00

37 Batu ( > 1000) Kg - Material Water Break 361,000.00

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

Page 12: JUKNIS PERENCANAAN 2014

38 Batu (250-1000) Kg - Material Water Break 279,000.00

39 Batu Kali 260,000.00

M3

M3

Page 13: JUKNIS PERENCANAAN 2014

NO. URAIAN SATUAN HARGA (Rp)

40 Batu Kali Quary 260,000.00

41 Batu Kali / Batu Belah (Sungai / Gunung) 260,000.00

42 Batu Pakhlag (Batu 5-7 cm ) 265,000.00

43 Batu Pecah 2-3 cm 325,000.00

44 Batu Tempel 291,000.00 45 Baut Kap Dia. 1/2 - 8 Buah 3,000.00 46 Bensin ( Indrustri ) Liter 10,000.00 47 Besi Beton Polos Kg 12,000.00 48 Besi Beton Ulir Kg 13,000.00 49 Besi Bout ( Kuda-kuda ) 5/8 - 10" Buah 9,000.00 50 Besi Gip 2 in Biasa Batang 392,000.00 51 Besi Pipa Roda 16" Batang 555,000.00 52 Beton Pagar Tian Antik I = 70 cm Buah 46,000.00 53 Beton Rooster / Kerawang Buah 10,000.00 54 BRC, 5 - 7 cm; 0,8 mm M2 15,000.00 55 Bubuk / Tepung Batu Kapur Kg 1,000.00 56 Bubungan Genteng M' 61,000.00 57 Bubungan Seng M' 23,000.00 58 Buis Beton ₵ 10 cm Buah 28,000.00 59 Buis Beton ₵ 100 cm M' 164,000.00 60 Buis Beton ₵ 15 cm Buah 37,000.00 61 Buis Beton ₵ 20 cm Buah 42,000.00 62 Buis Beton ₵ 30 cm Buah 63,000.00 63 Buis Beton ₵ 40 cm M' 84,000.00 64 Buis Beton ₵ 50 cm M' 127,000.00 65 Buis Beton ₵ 60 cm M' 143,000.00 66 Buis Beton ₵ 80 cm M' 180,000.00 67 Cat Extana Avitek Kg 32,000.00 68 Cat ICI Super Clos Kg 111,000.00 69 Cat Kayu Dasar Kg 23,400.00 70 Cat Kilat Kg 58,500.00 71 Cat Kayu mengkilap Kg 58,500.00 72 Cat Marka Jalan ( Non Thermoplast ) Kg 65,000.00 73 Cat Marka Jalan ( Thermoplast ) Kg 72,000.00 74 Cat Menie Besi Kg 32,500.00 75 Cat Minyak Kg 58,500.00 76 Cat Tembok 5 Kg 31,200.00 77 Cat tembok ICI (Watersheild) 5 Kg 39,000.00 78 Dalkin (Karpus 361) 30 x 60 cm, t = 12 mm Lembar 77,000.00 79 Dalkin Cealing (Karpus 361) 30 x 60 cm, t = 9 mm Lembar 63,000.00 80 Dalkin Rib (Karpus 361) 30 x 60 cm, t = 12 mm Lembar 74,000.00 81 Dempul Kg 19,500.00 82 Dempul Kayu Kg 19,500.00 83 Dempul Wallfiller Avitek Kg 32,500.00 84 Elbow Galvani ₵ 1 Inch Buah 10,400.00 85 Elbow Galvani ₵ 1/2 Inch Buah 7,800.00 86 Elbow Galvani ₵ 3 Inch Buah 36,400.00 87 Elbow Galvani ₵ 3/4 Inch Buah 7,800.00 88 Elbow Galvani ₵ 4 Inch Buah 62,400.00 89 Elbow Galvani ₵ 5 Inch Buah 126,000.00 90 Elbow PVC ₵ 1/2 Inch Buah 2,600.00 91 Elbow PVC ₵ 3 Inch Buah 15,600.00 92 Elbow PVC ₵ 3/4 Inch Buah 2,600.00 93 Elbow PVC ₵ 4 Inch Buah 28,600.00 94 Elbow PVC ₵ 5 Inch Buah 36,400.00

M3

M3

M3

M3

M3

Page 14: JUKNIS PERENCANAAN 2014

95 Engsel ARCH 3 Inch Buah 16,900.00

Page 15: JUKNIS PERENCANAAN 2014

NO. URAIAN SATUAN HARGA (Rp)

96 Engsel ARCH 4 Inch Buah 19,500.00 97 Engsel Bubut 40 mm Pasang 31,200.00 98 Filter Kg 23,000.00 99 Floor Drain Sun Ei Buah 9,100.00

100 Gantungan Handuk Sun Ei Double Buah 519,000.00 101 Gantungan Handuk Sun Ei Single Buah 371,000.00 102 Gemuk / Grease Kg 27,000.00 103 Genteng Concreat Warna Buah 10,000.00 104 Genteng Ekatana Berpasir Keping 111,000.00 105 Genteng Keramik KIA Warna Exclusive Keping 37,000.00 106 Genteng Keramik KIA Warna Khusus Keping 29,000.00 107 Genteng Kerami KIA Warna Natural Keping 25,000.00 108 Genteng Kerami KIA Warna Premium Keping 44,000.00 109 Genteng Kerami KIA Warna Standar Keping 29,000.00 110 Genteng Metal Emerald Lembar 46,800.00 111 Genteng Super Stell (0.4 x 1.2 m) Keping 75,000.00 112 Geogrid Impor Jerman Type 120/40 R-1 M2 218,000.00 113 Geogrid Impor Jerman Type 120/40 R-6 M2 285,000.00 114 Geogrid Impor Jerman Type 40/40 R-1 M2 132,000.00 115 Geogrid Impor Jerman Type40/40 R- 6 M2 162,000.00 116 Geogrid Impor Jerman Type 80/40 R- 6 M2 227,000.00 117 Geotekstil Non Woven ( 300 gr ) M2 40,000.00 118 Geotekstil M2 33,000.00 119 Gip Sum ( 120 x 240 cm ) Tebal 1.2 cm Lembar 139,000.00 120 Gipsum Australia ( 1,2 x 2,4 m ) T = 6 mm Lembar 74,000.00 121 Gipsum Australia ( 1,2 x 2,4 m ) T = 9 mm Lembar 96,200.00 122 Glas Block (15 x 15 cm) Buah 32,500.00 123 Gorong-gorong Aramco ₵ 1000 x 2 mm M' 2,332,000.00 124 Gorong-gorong Aramco ₵ 1500 x 2.5 mm M' 3,922,000.00 125 Gorong-gorong Aramco ₵ 1500 x 3.5 mm M' 5,512,000.00 126 Gravel 149,000.00 127 Grendel Jendela / Pintu Buah 9,100.00 128 Hak Angin Buah 7,800.00 129 Ijuk Kg 32,500.00 130 Interblock Warna Buah 4,000.00 131 Jendela Naco 5 mm (8 Sisir) Set 120,000.00 132 Kaca Bening Uk. 2 mm M2 87,000.00 133 Kaca Bening Uk. 3 mm M2 99,000.00 134 Kaca bening Uk. 5 mm M2 111,000.00 135 Kaca Cermin Wastafel Buah 200,000.00 136 Kaca Rayband Uk. 3 mm M2 111,000.00 137 Kaca Rayband Uk. 5 mm M2 137,000.00 138 Kaca Reyben 4 mm M2 143,000.00 139 Kanstin beton L = 50 cm M' 29,000.00 140 Kapur Batu Kg 6,000.00 141 Kapur Sirih Kg 6,000.00 142 Karpet 4 mm L 2 m Merek Nobel Buah 203,000.00 143 Karpu Asbes Gelombang Besar M' 95,000.00 144 Karpu Asbes Gelombang Kecil M' 80,000.00 145 Karpus Genteng Beton M' 60,000.00 146 Karpus Genteng Keramik M' 96,000.00 147 Kawat Ayam 3 mm M2 15,600.00 148 Kawat Beton Kg 19,500.00 149 Kawat Bronjong 0.4 mm Kg 20,800.00 150 Kawat Bronjong Dia. 3 mm Kg 20,800.00

M3

Page 16: JUKNIS PERENCANAAN 2014

NO. URAIAN SATUAN HARGA (Rp)

151 Kawat Bronjong Dia. 4 mm Kg 20,800.00 152 Kawat Bronjong DIA. 5 mm Kg 20,800.00 153 Kawat Bronjong Pabrikan Uk. (2 x 1 x 0,5) Lembar 508,000.00 154 Kawat Bronjong Pabrikan Uk. (2 x 1 x 1) Lembar 477,000.00 155 Kawat Bronjong Pabrikan Uk. (3 x 1 x 0,5) Lembar 47,000.00 156 Kawat Duri Kg 17,550.00 157 Kawat Harmonika M2 31,200.00 158 Kawat Nyamuk / Kasa Logam M2 19,500.00 159 Kawat Nyamuk / Kasa Plastik M2 19,500.00 160 Kayu Bakar 190,000.00 161 Kayu Bakau 10 cm Batang 54,000.00 162 Kayu Klas I (Merbo/Seumantok/Ulin/dll.) 10,400,000.00

163 Kayu Klas II (Kamper/Kruing/dll.) 7,800,000.00

164 Kayu Klas III (Borneo/dll.) 5,200,000.00

165 Kayu Klas IV (Sengon/dll.) 3,250,000.00 166 Kayu Untuk Perancah Batang 10,000.00 167 Keramik Roman M2 117,000.00 168 Keramik Sisik Kulit Jeruk 20 x 20 cm M2 84,500.00 169 Keramk Uk. 30 x 30 cm M2 65,000.00 170 Keramik Uk. 40 x 40 cm M2 71,500.00 171 Kerikil Bersih 220,000.00

171.a Kerikil Bersih (per kg; maksimum 30 mm) kg 162.96 172 Kerikil Quary 208,000.00 173 Kerosen / Minyak Tanah ( Industri ) Liter 10,500.00 174 Kertas Amplas Lembar 2,600.00 175 Kertas Pasir Lembar 6,500.00 176 Kloset Duduk Keramik Buah 585,000.00 177 Kloset Duduk KIA Buah 123,500.00 178 Kloset Jongkok Keramik Buah 188,500.00 179 Kloset Jongko KIA Buah 188,500.00 180 Kloset Jongkong Trassol Buah 84,500.00 181 Kran Merek Sun Ei Biasa Buah 16,250.00 182 Kunci Lesa Type 2328 Buah 110,500.00 183 Kunci lips Buah 110,500.00 184 Kunci Pintu Buah 71,500.00 185 Kunci Union 2 Slag Buah 68,900.00 186 Kunci Verro Asli Buah 593,000.00 187 Lampu Pijar 40 Watt Buah 7,800.00 188 Lampu TL 20 Watt Buah 13,000.00 189 Lampu TL 40 Watt Buah 19,500.00 190 Lat 1 x 2 Julotong Batang 71,000.00 191 Lat Asbes Batang 5,200.00 192 Lem Kayu (Aibon) Buah 32,500.00 193 Lempengan Rumput M2 31,000.00 194 List Eternit Kayu M' 7,000.00 195 Marmer M2 572,000.00 196 Marmer Lampung 10 x 20 x 0.7 cm M2 288,000.00 197 Marmer Lampung 10 x 30 x 0.7 cm M2 288,000.00 198 Marmer Lampung 10 x 30 x 1.8 cm M2 288,000.00 199 Marmer Lampung 15 x 30 x 0.7 cm M2 288,000.00 200 Marmer Lampung 15 x 30 x 1.8 cm M2 288,000.00 201 Marmer Lampung 20 x 20 x 1.8 cm M2 288,000.00

M3

M3

M3

M3

M3

M3

M3

Page 17: JUKNIS PERENCANAAN 2014

NO. URAIAN SATUAN HARGA (Rp)

202 Marmer Lampung 20 x 30 x 0.7 cm M2 288,000.00 203 Marmer Lampung 20 x 30 x 1.8 cm M2 288,000.00 204 Marmer Lampung 20 x 40 x 1.8 cm M2 832,000.00 205 Marmer Lampung 30 x 30 x 1.8 cm M2 832,000.00 206 Marmer Lampung 30 x 40 x 1.8 cm M2 832,000.00 207 Marmer Lampung 30 x 50 x 1.8 cm M2 832,000.00 208 Marmer Lampung 30 x 60 x 1.8 cm M2 832,000.00 209 Marmer Lampung 40 x 40 x 1.8 cm M2 832,000.00 210 Marmer Lampung 40 x 50 x 1.8 cm M2 832,000.00 211 Marmer Lampung 40 x 60 x 1.8 cm M2 832,000.00 212 Marmer Lampung 5 x 15 x 0.7 cm M2 288,000.00 213 Minyak Aspal Liter 20,800.00 213.a Minyak Bekisting Liter 3,500.00 214 Minyak Cat Liter 26,000.00 215 Minyak Pelumas Liter 48,000.00 216 Minyak Premium Liter 6,500.00 217 Minyak Rem Liter 27,000.00 218 Minyak Solar Liter 5,500.00 219 Mozaik M2 146,000.00 220 Multipleks 3 mm Lembar 58,500.00 221 Multipleks 4 mm Lembar 71,500.00 222 Multipleks 6 mm Lembar 97,500.00 223 Multipleks 9 mm Lembar 136,500.00 224 Naco ( Kerangka + Daun ) M2 328,000.00 225 Nok / Rabung Seng 0.35 Cat Prabrik Lembar 37,000.00 226 Nok / Rabung Seng 0.35 tidak Dicat Lembar 29,000.00 227 Oksigen 377,000.00 228 Paku Asbes Kg 16,900.00 229 Paku Berbagai Jenis 0,5 mc;1,5 mc; 1 Inch Kg 20,800.00 230 Paku Beton Kotak 20,800.00 231 Paku Beton 8 Inch Kotak 20,800.00 232 Paku Cacing RRT Kg 31,200.00 233 Paku Jembatan Kg 23,400.00 234 Paku Kait Buah 1,000.00 235 Paku Kayu (2"-5") Kg 17,000.00 236 Paku Klem Kotak Kg 43,000.00 237 Paku Kotak RRT Kg 20,800.00 238 Paku Reng Kg 15,600.00 239 Paku Sekrup Kg 32,500.00 240 Paku Seng Kg 31,200.00 241 Paku Sumbat Buah 1,000.00 242 Paku Ulir Primadek Buah 3,000.00 243 Palu unit 42,900.00 244 Papan 1 x 12 x 4,5 Julotong Lembar 85,000.00 245 Papan 1 x 9 x 4,5 Julotong Lembar 71,000.00 246 Papan Lisplank Kayu Kelas II M2 93,000.00 247 Papan Lisplank Kayu Seumantok M2 159,000.00 248 Papan Merbo 1 1/2 x 12 x 16 Lembar 265,000.00 249 Papan merbo 1 1/2 x 9 x 16 Lembar 243,000.00 250 Pasir Batu ( Sirtu ) - Material Jalan 233,000.00

251 Pasir Beton Bersih 190,000.00 252.a Pasir Beton Bersih (per kg) kg 135.71 252 Pasir Pasang 180,000.00

253 Pasir urug 130,000.00 254 Paving Block Buah 8,450.00

M3

M3

M3

M3

M3

Page 18: JUKNIS PERENCANAAN 2014

255 Pelumas / Oli Liter 40,000.00 256 Pipa Besi 1 inch Batang 110,500.00

Page 19: JUKNIS PERENCANAAN 2014

NO. URAIAN SATUAN HARGA (Rp)

257 Pipa Besi 1/2 inch Batang 84,500.00 258 Pipa Besi 2 inch Batang 16,250.00 259 Pipa Besi 3/4 inch Batang 97,500.00 260 Pipa GIP ₵ 2 Inch Batang 733,000.00 261 Pipa GIP ₵ 3 Inch Batang 1,505,000.00 262 Pipa GIP ₵ 4 Inch Batang 2,241,000.00 263 Pipa Leiding Ø 1/2 Inch Galvanis Tebal 3,2 mm Batang 95,000.00 264 Pipa Leiding Ø 1 1/2 Inch Galvanis Tebal 3,2 mm Batang 212,000.00 265 Pipa Leiding Ø 2 Inch Galvanis Tebal 3,2 mm Batang 318,000.00 266 Pipa Leiding Ø 3 Inch Galvanis Tebal 3,2 mm Batang 583,000.00 267 Pipa Leiding Ø 4 Inch Galvanis Tebal 3,2 mm Batang 795,000.00 268 Pipa Leiding Ø 6 Inch Galvanis Tebal 3,2 mm Batang 1,590,000.00 269 Pipa Leiding Ø 1 Inch Galvanis Tebal 3,2 mm Batang 137,000.00 270 Pipa PVC ₵ 1/2 Inch (Super Insar) Batang 26,000.00 271 Pipa PVC ₵ 2 Inch (Super Insar) Batang 78,000.00 272 Pipa PVC ₵ 3 Inch (Super Insar) Batang 175,500.00 273 Pipa PVC ₵ 3/4 Inch (Super Insar) Batang 32,500.00 274 Pipa PVC ₵ 4 Inch (Super Insar) Batang 237,000.00 275 Pipa PVC ₵ 6 Inch (Super Insar) Batang 409,500.00 276 Pipa PVC ₵ 8 Inch (Super Insar) Batang 715,000.00 277 Pipa PVC Ø 1 " Batang 45,500.00 278 Pipa PVC Ø 1/2 " Kualitas AWE (United) Batang 26,000.00 279 Pipa PVC Ø 1 1/2 " Batang 65,000.00 280 Pipa PVC Ø 2 " Batang 78,000.00 281 Pipa PVC Ø 3/4 " Batang 32,500.00 282 Pipa PVC Ø 3 " Batang 175,000.00 283 Pipa PVC Ø 4 " Batang 273,000.00 284 Plamur Tembok Kg 32,500.00 285 Plint Keramik 15 x 30 Buah 18,000.00 286 Plint Ubin Abu-abu 15 x 20 Buah 1,000.00 287 Plin Ubin Teraso 10 x 30 Buah 7,000.00 288 Plywood 12 mm Lembar 188,500.00 289 Plywood 4 mm Lembar 71,500.00 290 Plywood 6 mm Lembar 97,500.00 291 Plywood 9 mm Lembar 136,500.00 292 Polyplek 4 mm Lembar 110,500.00 293 Porselin 10 x 15 M2 148,000.00 294 Porselin 11 x 11 M2 148,000.00 295 Porselin 15 x 15 M2 148,000.00 296 Porselin 20 x 20 M2 148,000.00 297 Profil 2 x3 Batang 36,400.00 298 Pupuk Kandang (ukuran karung 15 kg) M3 19,500.00 299 Rabung Genteng Merek Ekapana Gerard L = 1.2 m M' 41,000.00 300 Rabung Genteng Merek KIA (NOK S2) Warna Exclusive M' 38,000.00 301 Rabung Genteng Merek KIA (NOK S2) Warna khusus M' 38,000.00 302 Rabung Genteng Merek KIA (NOK S2) Warna Natural M' 38,000.00 303 Rabung Genteng Merek KIA (NOK S2) Warna Premium M' 38,000.00 304 Rabung Genteng Merek KIA (NOK S2) Warna Standar M' 38,000.00 305 Rabung Genteng Merek Super Steel M' 93,000.00 306 Rabung Seng Lembar 26,000.00 307 Rabung Seng Superdeck 8 Kaki Lembar 104,000.00 308 Residu Kg 7,800.00 309 Resesrvoir Air 0,5 m3 Fibre Buah 1,696,000.00 310 Resesrvoir Air 0,5 m3 Stainlees steel Buah 1,961,000.00

Page 20: JUKNIS PERENCANAAN 2014

311 Resesrvoir Air 1 m3 Fibre Buah 2,554,000.00

Page 21: JUKNIS PERENCANAAN 2014

NO. URAIAN SATUAN HARGA (Rp)

312 Resesrvoir Air 1 m3 Stainlees Steel Buah 3,286,000.00 313 Schakelar Buah 25,000.00 314 Semen Andalas @ 40 Kg Zak 63,700.00 314.a Semen PC (per kg) Kg 1,592.50 314.b Semen PC Type I (per kg) Kg 1,592.50 315 Semen Andalas @ 50 Kg Zak 80,600.00 316 Semen Putih @ 50 Kg Zak 148,000.00 317 Seng BJLS 0,20 M2 27,300.00 318 Seng BJLS 0,20 Cat Pabrik M2 36,400.00 319 Seng Gelombang BJLS 0,20 - 8" Lembar 78,000.00 320 Seng Gelombang BJLS 0,30 - 8" Lembar 114,000.00 321 Seng Gelombang BJLS 0,35 - 8" Lembar 138,000.00 322 Seng Gelombang BJLS 30 M2 42,900.00 323 Seng Gelombang BJLS 30 Cat Pabrik M2 46,800.00 324 Seng Plat BJLS 20 M2 29,900.00 325 Seng Plat BJLS 30 M2 40,300.00 326 Seng Superdeck 8 Kaki Lembar 104,000.00 327 Socket GIP Ø 1 Inch Buah 15,000.00 328 Socket GIP Ø 1.5 Inch Buah 17,000.00 329 Socket GIP Ø 1/2 Inch Buah 10,000.00 330 Socket GIP Ø 3 Inch Buah 69,000.00 331 Socket GIP Ø 3/4 Inch Buah 9,000.00 332 Socket GIP Ø 4 Inch Buah 75,000.00 333 Socket PVC Ø 3 Inch Buah 9,100.00 334 Socket PVC Ø 4 Inch Buah 15,600.00 335 Socket PVC Ø 1 Inch Buah 3,900.00 336 Socket PVC Ø 1.5 Inch Buah 5,200.00 337 Socket PVC Ø 1/2 Inch Buah 2,600.00 338 Socket PVC Ø 3/4 Inch Buah 2,600.00 338.a Solar (industri) Liter 15,800.00 339 Stop Kontak + Instalasi Titi 84,500.00 340 Tanah Humus M3 79,000.00 341 Tanah Ladang M3 74,000.00 342 Tanah Timbun M3 52,000.00 343 Tanah Timbun Pilihan - Material Jalan M3 91,000.00 344 Tanah Timbun Pilihan Tanah berbatu M3 104,000.00 345 Tang Buah 32,200.00 346 Tempat Memasak Aspal Buah 212,000.00 347 Tempat Sabun Merek KIA Buah 84,000.00 348 Tempat Sabun Merek Sun Ei Buah 260,000.00 349 Tempat Sikat Gigi Merek Sun Ei Buah 198,000.00 350 Teralis Besi M2 519,000.00 351 Timbunan Didatangkan dari Buket Rata utk Wil. I (Anls.BOW) M3 42,000.00 352 Timbunan Didatangkan dari Buket Rata utk Wil. II (Anls.BOW) M3 48,000.00 353 Timbunan Didatangkan dari Buket Rata utk Wil. III (Anls.BOW) M3 56,000.00 354 Tinner Liter 23,000.00 355 Titik Lampu + Instalasi Titik 58,500.00 356 Triplek Formika 4 m Lembar 110,000.00 357 Ubin Abu-abu 20 x 20 M2 47,000.00 358 Ubin Berwarna 20 x 20 M2 47,000.00 359 Ubin Teraso 20 x 20 M2 47,000.00 360 Ubin Wafel 20 x 20 M2 47,000.00 361 Urinoir Buah 1,169,000.00 362 Urinoir Keramik Buah 1,505,000.00 363 Urinoir Keramik Buah 1,166,000.00 364 Vernis Liter 46,000.00

Page 22: JUKNIS PERENCANAAN 2014

365 Vinyl M2 206,000.00 366 Zekering (Kast Lokal 1 Zekering) Buah 143,000.00 367 Zekering (Kast Lokal 2 Zekering) Buah 174,000.00 368 Zekering (Kast Lokal 3 Zekering) Buah 243,000.00

Page 23: JUKNIS PERENCANAAN 2014

IV. DAFTAR ANALISA PEKERJAAN PLAFON DAN KAYU

Anl. SNI 2839-2008 6.5 : 1 M2 Memasang Langit-Langit Triplek Ukuran (120 x 240) cm, tebal 3 mm: Bahan

0.375 Lembar Multipleks 3 mm @ Rp.0.030 kg Paku Kayu (2"-5") @ Rp.

: Tenaga Kerja0.100 OH Pekerja @ Rp.0.100 OH Tukang Kayu @ Rp.0.010 OH Kepala Tukang @ Rp.0.005 OH Mandor @ Rp.

Anl. SNI 2839-2008 6.5 : 1 M2 Memasang Langit-Langit Triplek Ukuran (120 x 240) cm, tebal 6 mm: Bahan

0.375 Lembar Multipleks 6 mm @ Rp.0.030 kg Paku Kayu (2"-5") @ Rp.

: Tenaga Kerja0.100 OH Pekerja @ Rp.0.100 OH Tukang Kayu @ Rp.0.010 OH Kepala Tukang @ Rp.0.005 OH Mandor @ Rp.

Anl. SNI 2839-2008 6.6 : 1 M2 Memasang Langit-Langit Lambriziring Kayu, Tebal 9 mm: Bahan

0.015 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll.@ Rp.0.010 kg Paku Kayu (2"-5") @ Rp.

: Tenaga Kerja0.800 OH Pekerja @ Rp.0.800 OH Tukang Kayu @ Rp.0.080 OH Kepala Tukang @ Rp.0.040 OH Mandor @ Rp.

Anl. SNI 2839-2008 6.1 : 1 M2 Memasang Langit-Langit Kayu Profil: Bahan

1.050 m' List Eternit Kayu @ Rp.0.010 kg Paku Kayu (2"-5") @ Rp.

: Tenaga Kerja0.050 OH Pekerja @ Rp.0.050 OH Tukang Kayu @ Rp.0.005 OH Kepala Tukang @ Rp.0.003 OH Mandor @ Rp.

Page 24: JUKNIS PERENCANAAN 2014

V. DAFTAR ANALISA PEKERJAAN LANTAI

Anl. SNI 7395-2008 6.4 : 1 M2 Memasang Lantai Keramik Ukuran (40 x 40) cm: Bahan

1.060 m2 Keramik Uk. 40 x 40 cm @ Rp.9.800 kg Semen PC (per kg) @ Rp.0.045 m3 Pasir Pasang @ Rp.1.300 kg Semen Warna per Kg @ Rp.

: Tenaga Kerja0.250 OH Pekerja @ Rp.0.125 OH Tukang @ Rp.0.013 OH Kepala Tukang @ Rp.0.013 OH Mandor @ Rp.

Anl. SNI 7395-2008 6.4 : 1 M2 Memasang Lantai Keramik Roman: Bahan

1.060 m2 Keramik Roman @ Rp.9.800 kg Semen PC (per kg) @ Rp.0.045 m3 Pasir Pasang @ Rp.

Page 25: JUKNIS PERENCANAAN 2014

1.300 kg Semen Warna per Kg @ Rp.: Tenaga Kerja

0.250 OH Pekerja @ Rp.0.125 OH Tukang @ Rp.0.013 OH Kepala Tukang @ Rp.0.013 OH Mandor @ Rp.

Anl. SNI 7395-2008 6.5 : 1 M2 Memasang Lantai Keramik Ukuran (30 x 30) cm: Bahan

1.060 m2 Keramk Uk. 30 x 30 cm @ Rp.10.000 kg Semen PC (per kg) @ Rp.0.045 m3 Pasir Pasang @ Rp.1.500 kg Semen Warna per Kg @ Rp.

: Tenaga Kerja0.260 OH Pekerja @ Rp.0.130 OH Tukang @ Rp.0.013 OH Kepala Tukang @ Rp.0.013 OH Mandor @ Rp.

Anl. SNI 7395-2008 6.6 : 1 M2 Memasang Lantai Keramik Sisik Kulit Jeruk Ukuran (20 x 20) cm: Bahan

1.060 m2 Keramik Sisik Kulit Jeruk 20 x 20 cm @ Rp.10.400 kg Semen PC (per kg) @ Rp.0.045 m3 Pasir Pasang @ Rp.0.162 kg Semen Warna per Kg @ Rp.

: Tenaga Kerja0.270 OH Pekerja @ Rp.0.135 OH Tukang @ Rp.0.014 OH Kepala Tukang @ Rp.0.014 OH Mandor @ Rp.

Anl. SNI 7395-2008 6.1 : 1 M2 Memasang Plint Keramik Warna Ukuran (15 x 30) cm: Bahan

5.300 Buah Plint Keramik 15 x 30 @ Rp.1.140 kg Semen PC (per kg) @ Rp.0.003 m3 Pasir Pasang @ Rp.0.100 kg Semen Warna per Kg @ Rp.

: Tenaga Kerja0.090 OH Pekerja @ Rp.0.090 OH Tukang @ Rp.0.009 OH Kepala Tukang @ Rp.0.005 OH Mandor @ Rp.

Anl. SNI 7395-2008 6.5 : 1 M2 Memasang Dinding Keramik Ukuran (20 x 20) cm: Bahan

1.060 m2 Keramik Dinding 20 x 20 cm @ Rp.9.300 kg Semen PC (per kg) @ Rp.0.018 m3 Pasir Pasang @ Rp.1.940 kg Semen Warna per Kg @ Rp.

: Tenaga Kerja0.900 OH Pekerja @ Rp.0.450 OH Tukang @ Rp.0.045 OH Kepala Tukang @ Rp.0.045 OH Mandor @ Rp.

Page 26: JUKNIS PERENCANAAN 2014

V. DAFTAR ANALISA BIAYA KONSTRUKSI PEKERJAAN BETON

Anl. SNI 7394-2008 6.1 : 1 M3 Membuat Beton Tumbuk 1 PC : 3 PS : 5 KR: Bahan247.000 kg Semen PC Type I (per kg) @ Rp.

0.621 m3 Pasir Beton Bersih @ Rp.0.740 m3 Kerikil Bersih @ Rp.

215.000 Liter Air Bersih @ Rp.: Tenaga Kerja

1.650 OH Pekerja @ Rp.0.275 OH Tukang @ Rp.0.028 OH Kepala Tukang @ Rp.0.083 OH Mandor @ Rp.

Anl. SNI 7394-2008 6.7 : 1 M3 Membuat Beton Dengan Mutu K-225: Bahan371.000 kg Semen PC Type I (per kg) @ Rp.

0.499 m3 Pasir Beton Bersih @ Rp.0.776 m3 Kerikil Bersih @ Rp.

215.000 Liter Air Bersih @ Rp.: Tenaga Kerja

1.650 OH Pekerja @ Rp.0.275 OH Tukang @ Rp.0.028 OH Kepala Tukang @ Rp.0.083 OH Mandor @ Rp.

Anl. SNI 7394-2008 6.1 : 1 Kg Pembesian Dengan Besi Polos: Bahan

1.050 kg Besi Beton Polos @ Rp.0.015 kg Kawat Beton @ Rp.

: Tenaga Kerja0.007 OH Pekerja @ Rp.0.007 OH Tukang @ Rp.

0.0007 OH Kepala Tukang @ Rp.0.0004 OH Mandor @ Rp.

Anl. SNI 7394-2008 6.2 : 1 M2 Memasang Bekisting Untuk Pondasi: Bahan

0.040 m3 Kayu Kelas III @ Rp.0.300 kg Paku @ Rp.0.100 Liter Minyak Bekisting @ Rp.

: Tenaga Kerja0.520 OH Pekerja @ Rp.

Page 27: JUKNIS PERENCANAAN 2014

0.260 OH Tukang @ Rp.0.026 OH Kepala Tukang @ Rp.0.026 OH Mandor @ Rp.

Anl. SNI 7394-2008 6.2 : 1 M2 Memasang Bekisting Untuk Sloof: Bahan

0.045 m3 Kayu Kelas III @ Rp.0.300 kg Paku @ Rp.0.100 Liter Minyak Bekisting @ Rp.

: Tenaga Kerja0.520 OH Pekerja @ Rp.0.260 OH Tukang @ Rp.0.026 OH Kepala Tukang @ Rp.0.026 OH Mandor @ Rp.

Anl. SNI 7394-2008 6.2 : 1 M2 Memasang Bekisting Untuk Kolom: Bahan

0.040 m3 Kayu Kelas III @ Rp.0.400 kg Paku @ Rp.0.200 Liter Minyak Bekisting @ Rp.0.015 m3 Balok Kayu Kelas II @ Rp.0.350 Lembar Plywood Tebal 9 mm @ Rp.2.000 Batang Dolken Kayu Galam, (8-10)cm, panjan@ Rp.

: Tenaga Kerja0.660 OH Pekerja @ Rp.0.330 OH Tukang @ Rp.0.033 OH Kepala Tukang @ Rp.0.033 OH Mandor @ Rp.

Anl. SNI 7394-2008 6.2 : 1 M2 Memasang Bekisting Untuk Balok: Bahan

0.040 m3 Kayu Kelas III @ Rp.0.400 kg Paku @ Rp.0.200 Liter Minyak Bekisting @ Rp.0.018 m3 Balok Kayu Kelas II @ Rp.0.350 Lembar Plywood Tebal 9 mm @ Rp.2.000 Batang Dolken Kayu Galam, (8-10)cm, panjan@ Rp.

: Tenaga Kerja0.660 OH Pekerja @ Rp.0.330 OH Tukang @ Rp.0.033 OH Kepala Tukang @ Rp.0.033 OH Mandor @ Rp.

Anl. SNI 7394-2008 6.2 : 1 M2 Memasang Bekisting Untuk Plat Lantai: Bahan

0.040 m3 Kayu Kelas III @ Rp.0.400 kg Paku @ Rp.0.200 Liter Minyak Bekisting @ Rp.0.015 m3 Balok Kayu Kelas II @ Rp.0.350 Lembar Plywood Tebal 9 mm @ Rp.6.000 Batang Dolken Kayu Galam, (8-10)cm, panjan@ Rp.

: Tenaga Kerja0.660 OH Pekerja @ Rp.0.330 OH Tukang @ Rp.0.033 OH Kepala Tukang @ Rp.0.033 OH Mandor @ Rp.

Page 28: JUKNIS PERENCANAAN 2014

Pekerjaan Lain-lain : Untuk Membongkar Cetakan dan Menyiram Beton Diperlukan: Tenaga Kerja

1.000 OH Pekerja @ Rp.

SUPLEMEN 01 : 1 m3 Pondasi Tapak1.000 m3 Anl. SNI 7394-2008 6.7 @ Rp.

DESIGN kg Anl. SNI 7394-2008 6.17a @ Rp. DESIGN m2 Anl. SNI 7394-2008 6.20 @ Rp. 1.000 OH Pekerja Lain-lain @ Rp.

SUPLEMEN 02 : 1 m3 Sloof1.000 m3 Anl. SNI 7394-2008 6.7 @ Rp.

DESIGN kg Anl. SNI 7394-2008 6.17a @ Rp. DESIGN m2 Anl. SNI 7394-2008 6.21 @ Rp. 1.000 OH Pekerja Lain-lain @ Rp.

SUPLEMEN 03 : 1 m3 Kolom1.000 m3 Anl. SNI 7394-2008 6.7 @ Rp.

DESIGN kg Anl. SNI 7394-2008 6.17a @ Rp. DESIGN m2 Anl. SNI 7394-2008 6.22 @ Rp. 1.000 OH Pekerja Lain-lain @ Rp.

SUPLEMEN 04 : 1 m3 Balok1.000 m3 Anl. SNI 7394-2008 6.7 @ Rp.

DESIGN kg Anl. SNI 7394-2008 6.17a @ Rp. DESIGN m2 Anl. SNI 7394-2008 6.22 @ Rp. 1.000 OH Pekerja Lain-lain @ Rp.

SUPLEMEN 05 : 1 m3 Kolom1.000 m3 Anl. SNI 7394-2008 6.7 @ Rp.

DESIGN kg Anl. SNI 7394-2008 6.17a @ Rp. DESIGN m2 Anl. SNI 7394-2008 6.22 @ Rp. 1.000 OH Pekerja Lain-lain @ Rp.

SUPLEMEN 06 : 1 m3 Ring Balok1.000 m3 Anl. SNI 7394-2008 6.7 @ Rp.

DESIGN kg Anl. SNI 7394-2008 6.17a @ Rp. DESIGN m2 Anl. SNI 7394-2008 6.23 @ Rp. 1.000 OH Pekerja Lain-lain @ Rp.

SUPLEMEN 07 : 1 m3 Balok Lantai1.000 m3 Anl. SNI 7394-2008 6.7 @ Rp.

Page 29: JUKNIS PERENCANAAN 2014

DESIGN kg Anl. SNI 7394-2008 6.17a @ Rp. DESIGN m2 Anl. SNI 7394-2008 6.23 @ Rp. 1.000 OH Pekerja Lain-lain @ Rp.

SUPLEMEN 08 : 1 m3 Sun Wearing/Plat Dack1.000 m3 Anl. SNI 7394-2008 6.7 @ Rp.

DESIGN kg Anl. SNI 7394-2008 6.17a @ Rp. DESIGN m2 Anl. SNI 7394-2008 6.24 @ Rp. 1.000 OH Pekerja Lain-lain @ Rp.

SNI.03-3436-2002 (6.32: 1 M2 Atap Seng Genteng 0.25: Bahan

1.020 Lbr Seng Genteng 0.25 @ Rp.0.200 kg Paku Khusus Seng Genteng @ Rp.

: Tenaga Kerja0.200 OH Pekerja @ Rp.0.100 OH Tukang @ Rp.0.010 OH Kepala Tukang @ Rp.0.001 OH Mandor @ Rp.

SNI.03-3436-2002 (6.36: 1 M2 Bubungan Seng Genteng: Bahan

1.100 Lbr Bubungan Seng Genteng @ Rp.0.050 kg Paku Khusus Seng Genteng @ Rp.

: Tenaga Kerja0.250 OH Pekerja @ Rp.0.150 OH Tukang @ Rp.0.015 OH Kepala Tukang @ Rp.0.013 OH Mandor @ Rp.

SNI.03-2838-2002 6 - h : 1 M2 Pengecatan Bidang Kayu Baru (1 Lapis Plamir), 1 Lapis Cat Dasar, 2 Lapis Penutup: Bahan

0.200 kg Cat Meni @ Rp.0.150 kg Plamir @ Rp.0.170 kg Cat Dasar @ Rp.0.260 kg Cat Penutup @ Rp.

: Tenaga Kerja0.250 OH Pekerja @ Rp.0.150 OH Tukang @ Rp.0.015 OH Kepala Tukang @ Rp.0.013 OH Mandor @ Rp.

SNI.03-2838-2002 6 - 1 : 1 M2 Pengecatan Bidang Kayu Baru (1 Lapis Plamir), 1 Lapis Cat Dasar, 3 Lapis Penutup: Bahan

Page 30: JUKNIS PERENCANAAN 2014

0.200 kg Cat Meni @ Rp.0.150 kg Plamir @ Rp.0.170 kg Cat Dasar @ Rp.0.350 kg Cat Penutup @ Rp.

: Tenaga Kerja0.070 OH Pekerja @ Rp.0.105 OH Tukang @ Rp.0.004 OH Kepala Tukang @ Rp.0.003 OH Mandor @ Rp.

SNI.03-2838-2002 6 - 1 : 1 M2 Pelaburan Bidang kayu Dengan cat Residu dan Ter: Bahan

0.200 Liter Residu atau ter @ Rp.: Tenaga Kerja

0.070 OH Pekerja @ Rp.0.105 OH Tukang @ Rp.0.004 OH Kepala Tukang @ Rp.0.003 OH Mandor @ Rp.

SNI.03-2838-2002 6 - n : 1 M2 Pengecatan tembok baru (1 Lapis Plamir, 1 Lapis Cata Dasar, 2 lapis Cat penutup): Bahan

0.100 kg Plamir @ Rp.0.100 kg Cat dasar @ Rp.0.260 kg Cat Penutup @ Rp.

: Tenaga Kerja0.020 OH Pekerja @ Rp.0.063 OH Tukang @ Rp.0.006 OH Kepala Tukang @ Rp.0.003 OH Mandor @ Rp.

SNI.03-2838-2002 6 - t : 1 M2 Pengecatan Manie: Bahan

0.100 kg Cat Manie Besi @ Rp.0.010 Bh Kuas @ Rp.

: Tenaga Kerja0.020 OH Pekerja @ Rp.0.200 OH Tukang @ Rp.0.020 OH Kepala Tukang @ Rp.0.010 OH Mandor @ Rp.

Jumlah (1)

: Tenaga Kerja0.620 OH Pekerja @ Rp.0.350 OH Tukang @ Rp.0.035 OH Kepala Tukang @ Rp.0.030 OH Mandor @ Rp.

Jumlah (2) Jumlah (1+2)

Page 31: JUKNIS PERENCANAAN 2014

SNI 2835:2008

Tata cara perhitungan harga satuan pekerjaan tanah

untuk konstruksi bangunan gedung dan perumahan

Page 32: JUKNIS PERENCANAAN 2014

Anl. SNI 2835-2008 6.1

: Tenaga Kerja0.750 OH Pekerja @ Rp. 70,000.00 Rp. 52,500.00 0.025 OH Mandor @ Rp. 80,000.00 Rp. 2,000.00

Jumlah Rp. 54,500.00 Dibulatkan Rp. 54,500.00

Anl. SNI 2835-2008 6.2

: Tenaga Kerja0.900 OH Pekerja @ Rp. 70,000.00 Rp. 63,000.00 0.045 OH Mandor @ Rp. 80,000.00 Rp. 3,600.00

Jumlah Rp. 66,600.00 Dibulatkan Rp. 66,600.00

Anl. SNI 2835-2008 6.3

: Tenaga Kerja1.050 OH Pekerja @ Rp. 70,000.00 Rp. 73,500.00 0.067 OH Mandor @ Rp. 80,000.00 Rp. 5,360.00

Jumlah Rp. 78,860.00 Dibulatkan Rp. 78,860.00

Anl. SNI 2835-2008 6.4

: Tenaga Kerja1.000 OH Pekerja @ Rp. 70,000.00 Rp. 70,000.00 0.032 OH Mandor @ Rp. 80,000.00 Rp. 2,560.00

Jumlah Rp. 72,560.00 Dibulatkan Rp. 72,560.00

Anl. SNI 2835-2008 6.5

: Tenaga Kerja1.500 OH Pekerja @ Rp. 70,000.00 Rp. 105,000.00 0.060 OH Mandor @ Rp. 80,000.00 Rp. 4,800.00

Jumlah Rp. 109,800.00 Dibulatkan Rp. 109,800.00

Anl. SNI 2835-2008 6.6

: Tenaga Kerja1.200 OH Pekerja @ Rp. 70,000.00 Rp. 84,000.00 0.045 OH Mandor @ Rp. 80,000.00 Rp. 3,600.00

Jumlah Rp. 87,600.00 Dibulatkan Rp. 87,600.00

Anl. SNI 2835-2008 6.7

: Tenaga Kerja0.050 OH Pekerja @ Rp. 70,000.00 Rp. 3,500.00 0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. 3,900.00 Dibulatkan Rp. 3,900.00

Anl. SNI 2835-2008 6.8

: Tenaga Kerja0.330 OH Pekerja @ Rp. 70,000.00 Rp. 23,100.00 0.010 OH Mandor @ Rp. 80,000.00 Rp. 800.00

Jumlah Rp. 23,900.00 Dibulatkan Rp. 23,900.00

Anl. SNI 2835-2008 6.9

1 M3 Galian Tanah Biasa Sedalam 1 Meter

1 M3 Galian Tanah Biasa Sedalam 2 Meter

1 M3 Galian Tanah Biasa Sedalam 3 Meter

1 M3 Galian Tanah Keras Sedalam 1 Meter

1 M3 Galian Tanah Cadas Sedalam 1 Meter

1 M3 Galian Tanah Lumpur Sedalam 1 Meter

1 M3 Stripping Tebing Setinggi 1 Meter

1 M3 Membuang Tanah Sejauh 15 Meter

Page 33: JUKNIS PERENCANAAN 2014

: Tenaga KerjaMengurug kembali 1 m3 galian dihitung dari 1/3 kali dari indeks pekerjaan galian 18,166.67

Anl. SNI 2835-2008 6.10

: Tenaga Kerja0.500 OH Pekerja @ Rp. 70,000.00 Rp. 35,000.00 0.050 OH Mandor @ Rp. 80,000.00 Rp. 4,000.00

Jumlah Rp. 39,000.00 Dibulatkan Rp. 39,000.00

Anl. SNI 2835-2008 6.11

: Bahan1.200 M3 Pasir urug @ Rp. 130,000.00 Rp. 156,000.00 0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.010 OH Mandor @ Rp. 80,000.00 Rp. 800.00

Jumlah Rp. 177,800.00 Dibulatkan Rp. 177,800.00

Anl. SNI 2835-2008 6.11a

: Bahan1.200 OH Tanah Timbun @ Rp. 52,000.00 Rp. 62,400.00 0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.010 OH Mandor @ Rp. 80,000.00 Rp. 800.00

Jumlah Rp. 84,200.00 Dibulatkan Rp. 84,200.00

Anl. SNI 2835-2008 6.14

: Bahan6.000 Kg Ijuk @ Rp. 32,500.00 Rp. 195,000.00

: Tenaga Kerja0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 206,700.00 Dibulatkan Rp. 206,700.00

1 M3 Urugan Kembali Galian

1 M3 Memadatkan Tanah (per 20 cm)

1 M3 Mengurug Pasir Urug

1 M3 Mengurug Tanah Urug

1 M2 Memasang Lapisan Ijuk Tebal 10 cm, Untuk Bidang Resapan

Page 34: JUKNIS PERENCANAAN 2014

:

SNI 2836:2008

Tata cara perhitungan harga satuan pekerjaan pondasi

untuk konstruksi bangunan gedung dan perumahan

Page 35: JUKNIS PERENCANAAN 2014

:

Anl. SNI 2836-2008 6.1

: Bahan1.200 M3 Batu Kali @ Rp. 260,000.00 Rp. 312,000.00

202.000 Kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 321,685.00 0.485 M3 Pasir Pasang @ Rp. 180,000.00 Rp. 87,300.00

: Tenaga Kerja1.500 OH Pekerja @ Rp. 70,000.00 Rp. 105,000.00 0.750 OH Tukang Batu @ Rp. 80,000.00 Rp. 60,000.00 0.075 OH Kepala Tukang @ Rp. 100,000.00 Rp. 7,500.00 0.075 OH Mandor @ Rp. 80,000.00 Rp. 6,000.00

Jumlah Rp. 899,485.00 Dibulatkan Rp. 899,485.00

Anl. SNI 2836-2008 6.2

: Bahan1.200 m3 Batu Kali @ Rp. 260,000.00 Rp. 312,000.00

163.000 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 259,577.50 0.520 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 93,600.00

: Tenaga Kerja1.500 OH Pekerja @ Rp. 70,000.00 Rp. 105,000.00 0.750 OH Tukang Batu @ Rp. 80,000.00 Rp. 60,000.00 0.075 OH Kepala Tukang @ Rp. 100,000.00 Rp. 7,500.00 0.075 OH Mandor @ Rp. 80,000.00 Rp. 6,000.00

Jumlah Rp. 843,677.50 Dibulatkan Rp. 843,677.00

Anl. SNI 2836-2008 6.3

: Bahan1.200 m3 Batu Kali @ Rp. 260,000.00 Rp. 312,000.00

136.000 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 216,580.00 0.540 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 97,200.00

: Tenaga Kerja1.500 OH Pekerja @ Rp. 70,000.00 Rp. 105,000.00 0.750 OH Tukang Batu @ Rp. 80,000.00 Rp. 60,000.00 0.075 OH Kepala Tukang @ Rp. 100,000.00 Rp. 7,500.00 0.075 OH Mandor @ Rp. 80,000.00 Rp. 6,000.00

Jumlah Rp. 804,280.00 Dibulatkan Rp. 804,280.00

Anl. SNI 2836-2008 6.4

: Bahan1.200 m3 Batu Kali @ Rp. 260,000.00 Rp. 312,000.00

117.000 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 186,322.50 0.561 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 100,980.00

: Tenaga Kerja1.500 OH Pekerja @ Rp. 70,000.00 Rp. 105,000.00 0.750 OH Tukang Batu @ Rp. 80,000.00 Rp. 60,000.00 0.075 OH Kepala Tukang @ Rp. 100,000.00 Rp. 7,500.00 0.075 OH Mandor @ Rp. 80,000.00 Rp. 6,000.00

Jumlah Rp. 777,802.50 Dibulatkan Rp. 777,802.00

Anl. SNI 2836-2008 6.5

: Bahan1.200 m3 Batu Kali @ Rp. 260,000.00 Rp. 312,000.00 91.000 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 144,917.50 0.584 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 105,120.00

: Tenaga Kerja1.500 OH Pekerja @ Rp. 70,000.00 Rp. 105,000.00 0.750 OH Tukang Batu @ Rp. 80,000.00 Rp. 60,000.00 0.075 OH Kepala Tukang @ Rp. 100,000.00 Rp. 7,500.00

1 M3 Memasang Pondasi Batu Kali, Campuran 1 PC : 3 PP

1 M3 Memasang Pondasi Batu Kali, Campuran 1 PC : 4 PP

1 M3 Memasang Pondasi Batu Kali, Campuran 1 PC : 5 PP

1 M3 Memasang Pondasi Batu Kali, Campuran 1 PC : 6 PP

1 M3 Memasang Pondasi Batu Kali, Campuran 1 PC : 8 PP

Page 36: JUKNIS PERENCANAAN 2014

:

0.075 OH Mandor @ Rp. 80,000.00 Rp. 6,000.00 Jumlah Rp. 740,537.50 Dibulatkan Rp. 740,537.00

Anl. SNI 2836-2008 6.9

: Bahan1.200 m3 Batu Kali @ Rp. 260,000.00 Rp. 312,000.00 0.432 m3 Pasir urug @ Rp. 130,000.00 Rp. 56,160.00

: Tenaga Kerja0.780 OH Pekerja @ Rp. 70,000.00 Rp. 54,600.00 0.390 OH Tukang Batu @ Rp. 80,000.00 Rp. 31,200.00 0.039 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,900.00 0.039 OH Mandor @ Rp. 80,000.00 Rp. 3,120.00

Jumlah Rp. 457,860.00 Dibulatkan Rp. 457,860.00

Anl. SNI 2836-2008 6.10

: Bahan0.480 m3 Batu Kali @ Rp. 260,000.00 Rp. 124,800.00

194.000 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 308,945.00 0.312 m3 Pasir Beton Bersih @ Rp. 190,000.00 Rp. 59,280.00 0.468 m3 Kerikil Bersih @ Rp. 220,000.00 Rp. 102,960.00

126.000 kg Besi Beton Polos @ Rp. 12,000.00 Rp. 1,512,000.00 1.800 kg Kawat Beton @ Rp. 19,500.00 Rp. 35,100.00

: Tenaga Kerja3.400 OH Pekerja @ Rp. 70,000.00 Rp. 238,000.00 0.850 OH Tukang Batu @ Rp. 80,000.00 Rp. 68,000.00 0.085 OH Kepala Tukang @ Rp. 100,000.00 Rp. 8,500.00 0.170 OH Mandor @ Rp. 80,000.00 Rp. 13,600.00

Jumlah Rp. 2,471,185.00 Dibulatkan Rp. 2,471,185.00

Anl. SNI 2836-2008 6.11

: Bahan0.450 m3 Batu Kali @ Rp. 260,000.00 Rp. 117,000.00

194.000 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 308,945.00 0.312 m3 Pasir Beton Bersih @ Rp. 190,000.00 Rp. 59,280.00 0.468 m3 Kerikil Bersih @ Rp. 220,000.00 Rp. 102,960.00

: Tenaga Kerja2.400 OH Pekerja @ Rp. 70,000.00 Rp. 168,000.00 0.800 OH Tukang Batu @ Rp. 80,000.00 Rp. 64,000.00 0.080 OH Kepala Tukang @ Rp. 100,000.00 Rp. 8,000.00 0.119 OH Mandor @ Rp. 80,000.00 Rp. 9,520.00

Jumlah Rp. 837,705.00 Dibulatkan Rp. 837,705.00

1 M3 Memasang Batu Kosong (anstamping)

1 M3 Memasang Pondasi Siklop, 60% Beton Campuran 1 PC : 2 PB : 3 KR dan 40% Batu Kali

1 M3 Memasang Pondasi Sumuran, Diameter 100 cm

Page 37: JUKNIS PERENCANAAN 2014

SNI 3434:2008

Tata cara perhitungan harga satuan pekerjaan kayu

untuk konstruksi bangunan gedung dan perumahan

Page 38: JUKNIS PERENCANAAN 2014

Anl. SNI 3434-2008 6.11 M2 Membuat dan Memasang Kusen Pintu dan Kusen Jendela, Kayu Kelas I: Bahan

1.100 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll@ Rp. 10,400,000.00 Rp. 11,440,000.00 1.250 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 21,250.00 1.000 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 32,500.00

: Tenaga Kerja7.000 OH Pekerja @ Rp. 70,000.00 Rp. 490,000.00 21.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 1,680,000.00 2.100 OH Kepala Tukang @ Rp. 100,000.00 Rp. 210,000.00 0.350 OH Mandor @ Rp. 80,000.00 Rp. 28,000.00

Jumlah Rp. 13,901,750.00 Dibulatkan Rp. 13,901,750.00

Anl. SNI 3434-2008 6.21 M2 Membuat dan Memasang Kusen Pintu dan Kusen Jendela, Kayu Kelas II: Bahan

1.200 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 9,360,000.00 1.250 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 21,250.00 1.000 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 32,500.00

: Tenaga Kerja6.000 OH Pekerja @ Rp. 70,000.00 Rp. 420,000.00 18.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 1,440,000.00 1.800 OH Kepala Tukang @ Rp. 100,000.00 Rp. 180,000.00 0.300 OH Mandor @ Rp. 80,000.00 Rp. 24,000.00

Jumlah Rp. 11,477,750.00 Dibulatkan Rp. 11,477,750.00

Anl. SNI 3434-2008 6.31 M2 Membuat dan Memasang Pintu Klam Standar, Kayu Kelas II: Bahan

0.040 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 312,000.00 0.050 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 850.00

: Tenaga Kerja0.350 OH Pekerja @ Rp. 70,000.00 Rp. 24,500.00 1.050 OH Tukang Kayu @ Rp. 80,000.00 Rp. 84,000.00 0.105 OH Kepala Tukang @ Rp. 100,000.00 Rp. 10,500.00 0.018 OH Mandor @ Rp. 80,000.00 Rp. 1,440.00

Jumlah Rp. 433,290.00 Dibulatkan Rp. 433,290.00

Anl. SNI 3434-2008 6.41 M2 Membuat dan Memasang Pintu Klam Sederhana, Kayu Kelas III Untuk Gudang Sementara: Bahan

0.040 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 208,000.00 0.050 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 850.00

: Tenaga Kerja0.350 OH Pekerja @ Rp. 70,000.00 Rp. 24,500.00 1.050 OH Tukang Kayu @ Rp. 80,000.00 Rp. 84,000.00 0.105 OH Kepala Tukang @ Rp. 100,000.00 Rp. 10,500.00 0.018 OH Mandor @ Rp. 80,000.00 Rp. 1,440.00

Jumlah Rp. 329,290.00 Dibulatkan Rp. 329,290.00

Anl. SNI 3434-2008 6.51 M2 Membuat dan Memasang Daun Pintu Panel, Kayu Kelas I : Bahan

0.040 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll@ Rp. 10,400,000.00 Rp. 416,000.00 0.500 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 16,250.00

: Tenaga Kerja1.000 OH Pekerja @ Rp. 70,000.00 Rp. 70,000.00 3.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 240,000.00 0.300 OH Kepala Tukang @ Rp. 100,000.00 Rp. 30,000.00 0.050 OH Mandor @ Rp. 80,000.00 Rp. 4,000.00

Jumlah Rp. 776,250.00 Dibulatkan Rp. 776,250.00

Page 39: JUKNIS PERENCANAAN 2014

Anl. SNI 3434-2008 6.5a1 M2 Membuat dan Memasang Daun Pintu Panel, Kayu Kelas II: Bahan

0.040 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 312,000.00 0.500 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 16,250.00

: Tenaga Kerja1.000 OH Pekerja @ Rp. 70,000.00 Rp. 70,000.00 3.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 240,000.00 0.300 OH Kepala Tukang @ Rp. 100,000.00 Rp. 30,000.00 0.050 OH Mandor @ Rp. 80,000.00 Rp. 4,000.00

Jumlah Rp. 672,250.00 Dibulatkan Rp. 672,250.00

Anl. SNI 3434-2008 6.61 M2 Membuat dan Memasang Pintu dan Jendela Kaca, Kayu Kelas I: Bahan

0.024 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll@ Rp. 10,400,000.00 Rp. 249,600.00 0.300 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 9,750.00

: Tenaga Kerja0.800 OH Pekerja @ Rp. 70,000.00 Rp. 56,000.00 2.400 OH Tukang Kayu @ Rp. 80,000.00 Rp. 192,000.00 0.240 OH Kepala Tukang @ Rp. 100,000.00 Rp. 24,000.00 0.040 OH Mandor @ Rp. 80,000.00 Rp. 3,200.00

Jumlah Rp. 534,550.00 Dibulatkan Rp. 534,550.00

Anl. SNI 3434-2008 6.6a1 M2 Membuat dan Memasang Pintu dan Jendela Kaca, Kayu Kelas II: Bahan

0.024 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 187,200.00 0.300 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 9,750.00

: Tenaga Kerja0.800 OH Pekerja @ Rp. 70,000.00 Rp. 56,000.00 2.400 OH Tukang Kayu @ Rp. 80,000.00 Rp. 192,000.00 0.240 OH Kepala Tukang @ Rp. 100,000.00 Rp. 24,000.00 0.040 OH Mandor @ Rp. 80,000.00 Rp. 3,200.00

Jumlah Rp. 472,150.00 Dibulatkan Rp. 472,150.00

Anl. SNI 3434-2008 6.71 M2 Membuat dan Memasang Pintu dan Jendela Jalusi, Kayu Kelas I: Bahan

0.064 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll@ Rp. 10,400,000.00 Rp. 665,600.00 0.500 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 16,250.00

: Tenaga Kerja1.000 OH Pekerja @ Rp. 70,000.00 Rp. 70,000.00 3.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 240,000.00 0.300 OH Kepala Tukang @ Rp. 100,000.00 Rp. 30,000.00 0.050 OH Mandor @ Rp. 80,000.00 Rp. 4,000.00

Jumlah Rp. 1,025,850.00 Dibulatkan Rp. 1,025,850.00

Anl. SNI 3434-2008 6.7a1 M2 Membuat dan Memasang Pintu dan Jendela Jalusi, Kayu Kelas II: Bahan

0.064 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 499,200.00 0.500 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 16,250.00

: Tenaga Kerja1.000 OH Pekerja @ Rp. 70,000.00 Rp. 70,000.00 3.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 240,000.00 0.300 OH Kepala Tukang @ Rp. 100,000.00 Rp. 30,000.00 0.050 OH Mandor @ Rp. 80,000.00 Rp. 4,000.00

Jumlah Rp. 859,450.00 Dibulatkan Rp. 859,450.00

Page 40: JUKNIS PERENCANAAN 2014

Anl. SNI 3434-2008 6.81 M2 Membuat Daun Pintu Kayu Lapis (Plywood) Rangkap, Rangka Tertutup Kayu Kelas II (Lebar Sampai 90 cm): Bahan

0.025 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 195,000.00 0.030 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 510.00 0.500 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 16,250.00 1.000 lembar Multipleks 4 mm @ Rp. 71,500.00 Rp. 71,500.00

: Tenaga Kerja0.700 OH Pekerja @ Rp. 70,000.00 Rp. 49,000.00 2.100 OH Tukang Kayu @ Rp. 80,000.00 Rp. 168,000.00 0.210 OH Kepala Tukang @ Rp. 100,000.00 Rp. 21,000.00 0.035 OH Mandor @ Rp. 80,000.00 Rp. 2,800.00

Jumlah Rp. 524,060.00 Dibulatkan Rp. 524,060.00

Anl. SNI 3434-2008 6.9a1 M2 Membuat Pintu Plywood Rangkap, Rangka Expose Kayu Kelas I: Bahan

0.0256 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll@ Rp. 10,400,000.00 Rp. 266,240.00 0.030 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 510.00 0.500 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 16,250.00 1.000 lembar Multipleks 4 mm @ Rp. 71,500.00 Rp. 71,500.00

: Tenaga Kerja0.800 OH Pekerja @ Rp. 70,000.00 Rp. 56,000.00 2.400 OH Tukang Kayu @ Rp. 80,000.00 Rp. 192,000.00 0.240 OH Kepala Tukang @ Rp. 100,000.00 Rp. 24,000.00 0.040 OH Mandor @ Rp. 80,000.00 Rp. 3,200.00

Jumlah Rp. 629,700.00 Dibulatkan Rp. 629,700.00

Anl. SNI 3434-2008 6.9b1 M2 Membuat Pintu Plywood Rangkap, Rangka Expose Kayu Kelas II: Bahan

0.0256 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 199,680.00 0.030 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 510.00 0.500 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 16,250.00 1.000 lembar Multipleks 4 mm @ Rp. 71,500.00 Rp. 71,500.00

: Tenaga Kerja0.800 OH Pekerja @ Rp. 70,000.00 Rp. 56,000.00 2.400 OH Tukang Kayu @ Rp. 80,000.00 Rp. 192,000.00 0.240 OH Kepala Tukang @ Rp. 100,000.00 Rp. 24,000.00 0.040 OH Mandor @ Rp. 80,000.00 Rp. 3,200.00

Jumlah Rp. 563,140.00 Dibulatkan Rp. 563,140.00

Anl. SNI 3434-2008 6.101 M2 Memasang Jalusi Kusen, Kayu Kelas I: Bahan

0.060 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll@ Rp. 10,400,000.00 Rp. 624,000.00 0.150 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 2,550.00

: Tenaga Kerja0.670 OH Pekerja @ Rp. 70,000.00 Rp. 46,900.00 2.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 160,000.00 0.200 OH Kepala Tukang @ Rp. 100,000.00 Rp. 20,000.00 0.335 OH Mandor @ Rp. 80,000.00 Rp. 26,800.00

Jumlah Rp. 880,250.00 Dibulatkan Rp. 880,250.00

Anl. SNI 3434-2008 6.10a1 M2 Memasang Jalusi Kusen, Kayu Kelas II: Bahan

0.060 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 468,000.00 0.150 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 2,550.00

Page 41: JUKNIS PERENCANAAN 2014

: Tenaga Kerja0.670 OH Pekerja @ Rp. 70,000.00 Rp. 46,900.00 2.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 160,000.00 0.200 OH Kepala Tukang @ Rp. 100,000.00 Rp. 20,000.00 0.335 OH Mandor @ Rp. 80,000.00 Rp. 26,800.00

Jumlah Rp. 724,250.00 Dibulatkan Rp. 724,250.00

Anl. SNI 3434-2008 6.13aMemasang 1 m3 kuda-kuda konvensional, kayu kelas I, bentang 6 meter: Bahan

1.100 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll@ Rp. 10,400,000.00 Rp. 11,440,000.00

15.000 kg Besi strip tebal 5 mm

@ Rp. 14,000.00 Rp. 210,000.00 (dipakai harga Baja Profil)5.600 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 95,200.00

: Tenaga Kerja4.000 OH Pekerja @ Rp. 70,000.00 Rp. 280,000.00 12.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 960,000.00 1.200 OH Kepala Tukang @ Rp. 100,000.00 Rp. 120,000.00 0.200 OH Mandor @ Rp. 80,000.00 Rp. 16,000.00

Jumlah Rp. 13,121,200.00 Dibulatkan Rp. 13,121,200.00

Anl. SNI 3434-2008 6.13bMemasang 1 m3 kuda-kuda konvensional, kayu kelas II, bentang 6 meter: Bahan

1.100 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 8,580,000.00

15.000 kg Besi strip tebal 5 mm

@ Rp. 14,000.00 Rp. 210,000.00 (dipakai harga Baja Profil)5.600 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 95,200.00

: Tenaga Kerja4.000 OH Pekerja @ Rp. 70,000.00 Rp. 280,000.00 12.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 960,000.00 1.200 OH Kepala Tukang @ Rp. 100,000.00 Rp. 120,000.00 0.200 OH Mandor @ Rp. 80,000.00 Rp. 16,000.00

Jumlah Rp. 10,261,200.00 Dibulatkan Rp. 10,261,200.00

Anl. SNI 3434-2008 6.13cMemasang 1 m3 kuda-kuda konvensional, kayu kelas III, bentang 6 meter: Bahan

1.100 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 5,720,000.00

15.000 kg Besi strip tebal 5 mm

@ Rp. 14,000.00 Rp. 210,000.00 (dipakai harga Baja Profil)5.600 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 95,200.00

: Tenaga Kerja4.000 OH Pekerja @ Rp. 70,000.00 Rp. 280,000.00 12.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 960,000.00 1.200 OH Kepala Tukang @ Rp. 100,000.00 Rp. 120,000.00 0.200 OH Mandor @ Rp. 80,000.00 Rp. 16,000.00

Jumlah Rp. 7,401,200.00 Dibulatkan Rp. 7,401,200.00

Anl. SNI 3434-2008 6.14Memasang 1 m3 kuda-kuda ekspose, kayu kelas I: Bahan

1.200 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll@ Rp. 10,400,000.00 Rp. 12,480,000.00

15.000 kg Besi strip tebal 5 mm

@ Rp. 14,000.00 Rp. 210,000.00 (dipakai harga Baja Profil)5.600 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 95,200.00

: Tenaga Kerja6.700 OH Pekerja @ Rp. 70,000.00 Rp. 469,000.00 20.100 OH Tukang Kayu @ Rp. 80,000.00 Rp. 1,608,000.00 2.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 201,000.00 0.335 OH Mandor @ Rp. 80,000.00 Rp. 26,800.00

Page 42: JUKNIS PERENCANAAN 2014

Jumlah Rp. 15,090,000.00 Dibulatkan Rp. 15,090,000.00

Anl. SNI 3434-2008 6.15Memasang 1 m3 konstruksi gordeng, kayu kelas II: Bahan

1.100 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 8,580,000.00

15.000 kg Besi strip tebal 5 mm

@ Rp. 14,000.00 Rp. 210,000.00 (dipakai harga Baja Profil)3.000 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 51,000.00

: Tenaga Kerja2.400 OH Pekerja @ Rp. 70,000.00 Rp. 168,000.00 7.200 OH Tukang Kayu @ Rp. 80,000.00 Rp. 576,000.00 0.720 OH Kepala Tukang @ Rp. 100,000.00 Rp. 72,000.00 0.120 OH Mandor @ Rp. 80,000.00 Rp. 9,600.00

Jumlah Rp. 9,666,600.00 Dibulatkan Rp. 9,666,600.00

Anl. SNI 3434-2008 6.16Memasang 1 m2 rangka atap genteng keramik, kayu kelas II: Bahan

0.014 kg Kaso-kaso (5 x 7 ) cm

@ Rp. 7,800,000.00 Rp. 109,200.00 Kayu Klas II (Kamper/Kruing/dll.)

0.004 kg Reng (3 x 4) cm

@ Rp. 7,800,000.00 Rp. 28,080.00 Kayu Klas II (Kamper/Kruing/dll.) 0.250 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 4,250.00

: Tenaga Kerja0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00 0.100 OH Tukang Kayu @ Rp. 80,000.00 Rp. 8,000.00 0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00 0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. 157,930.00 Dibulatkan Rp. 157,930.00

Anl. SNI 3434-2008 6.19a1 M2 Memasang Rangka Langit-Langit (50 x 100) cm, Kayu Kelas II: Bahan

0.015 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 117,000.00 0.200 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 3,400.00

: Tenaga Kerja0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00 0.300 OH Tukang Kayu @ Rp. 80,000.00 Rp. 24,000.00 0.030 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,000.00 0.075 OH Mandor @ Rp. 80,000.00 Rp. 6,000.00

Jumlah Rp. 163,900.00 Dibulatkan Rp. 163,900.00

Anl. SNI 3434-2008 6.19b1 M2 Memasang Rangka Langit-Langit (50 x 100) cm, Kayu Kelas III: Bahan

0.015 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 78,000.00 0.200 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 3,400.00

: Tenaga Kerja0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00 0.300 OH Tukang Kayu @ Rp. 80,000.00 Rp. 24,000.00 0.030 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,000.00 0.075 OH Mandor @ Rp. 80,000.00 Rp. 6,000.00

Jumlah Rp. 124,900.00 Dibulatkan Rp. 124,900.00

Page 43: JUKNIS PERENCANAAN 2014

Anl. SNI 3434-2008 6.20a1 M2 Memasang Rangka Langit-Langit (60 x 60) cm, kayu kelas II: Bahan

0.0163 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 127,140.00 0.250 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 4,250.00

: Tenaga Kerja0.200 OH Pekerja @ Rp. 70,000.00 Rp. 14,000.00 0.300 OH Tukang Kayu @ Rp. 80,000.00 Rp. 24,000.00 0.030 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,000.00 0.010 OH Mandor @ Rp. 80,000.00 Rp. 800.00

Jumlah Rp. 173,190.00 Dibulatkan Rp. 173,190.00

Anl. SNI 3434-2008 6.20b1 M2 Memasang Rangka Langit-Langit (60 x 60) cm, kayu kelas III: Bahan

0.0163 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 84,760.00 0.250 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 4,250.00

: Tenaga Kerja0.200 OH Pekerja @ Rp. 70,000.00 Rp. 14,000.00 0.300 OH Tukang Kayu @ Rp. 80,000.00 Rp. 24,000.00 0.030 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,000.00 0.010 OH Mandor @ Rp. 80,000.00 Rp. 800.00

Jumlah Rp. 130,810.00 Dibulatkan Rp. 130,810.00

Anl. SNI 3434-2008 6.21a1 M1 Memasang Lisplank Ukuran (3 x 20) cm, Kayu Kelas I: Bahan

0.0108 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll@ Rp. 10,400,000.00 Rp. 112,320.00 0.100 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 1,700.00

: Tenaga Kerja0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00 0.200 OH Tukang Kayu @ Rp. 80,000.00 Rp. 16,000.00 0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00 0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. 139,420.00 Dibulatkan Rp. 139,420.00

Anl. SNI 3434-2008 6.21b 1 M1 Memasang Lisplank Ukuran (3 x 20) cm, Kayu Kelas II: Bahan

0.0108 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 84,240.00 0.100 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 1,700.00

: Tenaga Kerja0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00 0.200 OH Tukang Kayu @ Rp. 80,000.00 Rp. 16,000.00 0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00 0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. 111,340.00 Dibulatkan Rp. 111,340.00

Anl. SNI 3434-2008 6.22a1 M1 Memasang Lisplank Ukuran (3 x 30) cm, Kayu Kelas I: Bahan

0.0110 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll@ Rp. 10,400,000.00 Rp. 114,400.00 0.050 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 850.00

: Tenaga Kerja0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00 0.200 OH Tukang Kayu @ Rp. 80,000.00 Rp. 16,000.00 0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00 0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. 140,650.00 Dibulatkan Rp. 140,650.00

Anl. SNI 3434-2008 6.22b1 M1 Memasang Lisplank Ukuran (3 x 30) cm, Kayu Kelas II: Bahan

0.0110 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 85,800.00 0.050 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 850.00

Page 44: JUKNIS PERENCANAAN 2014

: Tenaga Kerja0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00 0.200 OH Tukang Kayu @ Rp. 80,000.00 Rp. 16,000.00 0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00 0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. 112,050.00 Dibulatkan Rp. 112,050.00

Anl. SNI 3434-2008 6.231 M2 Memasang Rangka Dinding Pemisah Ukuran (60 x 120) cm, Kayu Kelas II: Bahan

0.028 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 218,400.00 0.150 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 2,550.00

: Tenaga Kerja0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00 0.450 OH Tukang Kayu @ Rp. 80,000.00 Rp. 36,000.00 0.045 OH Kepala Tukang @ Rp. 100,000.00 Rp. 4,500.00 0.008 OH Mandor @ Rp. 80,000.00 Rp. 640.00

Jumlah Rp. 272,590.00 Dibulatkan Rp. 272,590.00

Anl. SNI 3434-2008 6.25Memasang 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II: Bahan

0.028 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 218,400.00 0.150 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 2,550.00 0.860 Lembar Plywood 4 mm @ Rp. 71,500.00 Rp. 61,490.00 0.560 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 18,200.00

: Tenaga Kerja0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00 0.450 OH Tukang Kayu @ Rp. 80,000.00 Rp. 36,000.00 0.045 OH Kepala Tukang @ Rp. 100,000.00 Rp. 4,500.00 0.008 OH Mandor @ Rp. 80,000.00 Rp. 640.00

Jumlah Rp. 352,280.00 Dibulatkan Rp. 352,280.00

Anl. SNI 3434-2008 6.261 M2 Memasang Dinding Lambriziring Dari Papan Kayu Kelas I: Bahan

0.0070 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll@ Rp. 10,400,000.00 Rp. 72,800.00 0.100 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 1,700.00 0.150 kg Paku Sekrup @ Rp. 32,500.00 Rp. 4,875.00

: Tenaga Kerja0.600 OH Pekerja @ Rp. 70,000.00 Rp. 42,000.00 1.800 OH Tukang Kayu @ Rp. 80,000.00 Rp. 144,000.00 0.180 OH Kepala Tukang @ Rp. 100,000.00 Rp. 18,000.00 0.030 OH Mandor @ Rp. 80,000.00 Rp. 2,400.00

Jumlah Rp. 285,775.00 Dibulatkan Rp. 285,775.00

Page 45: JUKNIS PERENCANAAN 2014

SNI 6897:2008

Tata cara perhitungan harga satuan pekerjaan dinding

untuk konstruksi bangunan gedung dan perumahan

Page 46: JUKNIS PERENCANAAN 2014

Anl. SNI 6897-2008 6.11 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1 Bata, Campuran Spesi 1 PC : 2 PP: Bahan140.0000 Buah Batu Bata @ Rp. 570.00 Rp. 79,800.00 43.500 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 69,273.75 0.080 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 14,400.00

: Tenaga Kerja0.600 OH Pekerja @ Rp. 70,000.00 Rp. 42,000.00 0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00 0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00 0.030 OH Mandor @ Rp. 80,000.00 Rp. 2,400.00

Jumlah Rp. 225,873.75 Dibulatkan Rp. 225,873.00

Anl. SNI 6897-2008 6.21 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1 Bata, Campuran Spesi 1 PC : 3 PP: Bahan140.0000 Buah Batu Bata @ Rp. 570.00 Rp. 79,800.00 32.950 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 52,472.88 0.091 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 16,380.00

: Tenaga Kerja0.600 OH Pekerja @ Rp. 70,000.00 Rp. 42,000.00 0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00 0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00 0.030 OH Mandor @ Rp. 80,000.00 Rp. 2,400.00

Jumlah Rp. 211,052.88 Dibulatkan Rp. 211,052.00

Anl. SNI 6897-2008 6.31 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1 Bata, Campuran Spesi 1 PC : 4 PP: Bahan140.0000 Buah Batu Bata @ Rp. 570.00 Rp. 79,800.00 26.550 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 42,280.88 0.093 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 16,740.00

: Tenaga Kerja0.600 OH Pekerja @ Rp. 70,000.00 Rp. 42,000.00 0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00 0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00 0.030 OH Mandor @ Rp. 80,000.00 Rp. 2,400.00

Jumlah Rp. 201,220.88 Dibulatkan Rp. 201,220.00

Anl. SNI 6897-2008 6.41 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1 Bata, Campuran Spesi 1 PC : 5 PP: Bahan140.0000 Buah Batu Bata @ Rp. 570.00 Rp. 79,800.00 22.200 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 35,353.50 0.102 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 18,360.00

: Tenaga Kerja0.600 OH Pekerja @ Rp. 70,000.00 Rp. 42,000.00 0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00 0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00 0.030 OH Mandor @ Rp. 80,000.00 Rp. 2,400.00

Jumlah Rp. 195,913.50 Dibulatkan Rp. 195,913.00

Anl. SNI 6897-2008 6.51 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1 Bata, Campuran Spesi 1 PC : 6 PP: Bahan140.0000 Buah Batu Bata @ Rp. 570.00 Rp. 79,800.00 18.500 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 29,461.25 0.122 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 21,960.00

: Tenaga Kerja0.600 OH Pekerja @ Rp. 70,000.00 Rp. 42,000.00 0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00 0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00 0.030 OH Mandor @ Rp. 80,000.00 Rp. 2,400.00

Page 47: JUKNIS PERENCANAAN 2014

Jumlah Rp. 193,621.25 Dibulatkan Rp. 193,621.00

Anl. SNI 6897-2008 6.71 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1/2 Bata, Campuran Spesi 1 PC : 2 PP: Bahan

70.000 Buah Batu Bata @ Rp. 570.00 Rp. 39,900.00 18.950 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 30,177.88 0.038 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 6,840.00

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.100 OH Tukang Batu @ Rp. 80,000.00 Rp. 8,000.00 0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 108,117.88 Dibulatkan Rp. 108,117.00

Anl. SNI 6897-2008 6.81 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1/2 Bata, Campuran Spesi 1 PC : 3 PP: Bahan

70.000 Buah Batu Bata @ Rp. 570.00 Rp. 39,900.00 14.370 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 22,884.23 0.040 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 7,200.00

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.100 OH Tukang Batu @ Rp. 80,000.00 Rp. 8,000.00 0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 101,184.23 Dibulatkan Rp. 101,184.00

Anl. SNI 6897-2008 6.91 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1/2 Bata, Campuran Spesi 1 PC : 4 PP: Bahan

70.000 Buah Batu Bata @ Rp. 570.00 Rp. 39,900.00 11.500 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 18,313.75 0.043 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 7,740.00

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.100 OH Tukang Batu @ Rp. 80,000.00 Rp. 8,000.00 0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 97,153.75 Dibulatkan Rp. 97,153.00

Anl. SNI 6897-2008 6.101 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1/2 Bata, Campuran Spesi 1 PC : 5 PP: Bahan

70.000 Buah Batu Bata @ Rp. 570.00 Rp. 39,900.00 8.320 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 13,249.60 0.049 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 8,820.00

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.100 OH Tukang Batu @ Rp. 80,000.00 Rp. 8,000.00 0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 93,169.60 Dibulatkan Rp. 93,169.00

Anl. SNI 6897-2008 6.111 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1/2 Bata, Campuran Spesi 1 PC : 6 PP: Bahan

70.000 Buah Batu Bata @ Rp. 570.00 Rp. 39,900.00 8.320 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 13,249.60 0.049 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 8,820.00

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.100 OH Tukang Batu @ Rp. 80,000.00 Rp. 8,000.00

Page 48: JUKNIS PERENCANAAN 2014

0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 93,169.60 Dibulatkan Rp. 93,169.00

Anl. SNI 6897-2008 6.121 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1/2 Bata, Campuran Spesi 1 PC : 8 PP: Bahan

70.000 Buah Batu Bata @ Rp. 570.00 Rp. 39,900.00 6.500 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 10,351.25 0.050 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 9,000.00

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.100 OH Tukang Batu @ Rp. 80,000.00 Rp. 8,000.00 0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 90,451.25 Dibulatkan Rp. 90,451.00

Anl. SNI 6897-2008 6.221Memasang 1 m2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 PC : 3 PP

: Bahan30.000 Buah Terawang @ Rp. #N/A Rp. #N/A14.000 kg Batu Bata @ Rp. 570.00 Rp. 7,980.00 0.032 m3 Semen PC (per kg) @ Rp. 1,592.50 Rp. 50.96

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.100 OH Tukang Batu @ Rp. 80,000.00 Rp. 8,000.00 0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Page 49: JUKNIS PERENCANAAN 2014

SNI 7394:2008

Tata cara perhitungan harga satuan pekerjaan beton

untuk konstruksi bangunan gedung dan perumahan

Page 50: JUKNIS PERENCANAAN 2014

Anl. SNI 7394-2008 6.11 M3 Membuat Beton Mutu F'c=7.4 Mpa (K100), Slump (12 ± 2)cm,w/c=0.87: Bahan

247.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 393,347.50 869.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 117,935.71 999.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 162,800.00 215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00 0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00 0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00 0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

54 Jumlah Rp. 831,773.21 Dibulatkan Rp. 831,773.00

Anl. SNI 7394-2008 6.21 M3 Membuat Beton Mutu F'c=9.8 Mpa (K125), Slump (12 ± 2)cm,w/c=0.78: Bahan

276.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 439,530.00 828.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 112,371.43 1012.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 164,918.52 215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00 0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00 0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00 0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 874,509.95 Dibulatkan Rp. 874,509.00

Anl. SNI 7394-2008 6.31 M3 Membuat Beton Mutu F'c=12.2 Mpa (K150), Slump (12 ± 2)cm,w/c=0.72: Bahan

299.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 476,157.50 799.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 108,435.71 1017.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 165,733.33 215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00 0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00 0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00 0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 908,016.55 Dibulatkan Rp. 908,016.00

Anl. SNI 7394-2008 6.41 M3 Membuat Lantai Kerja Beton Mutu F'c=7.4 Mpa (K100), Slump (3 - 6) cm, w/c=0.72: Bahan

230.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 366,275.00 893.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 121,192.86 1027.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 167,362.96 200.000 liter Air Bersih @ Rp. 50.00 Rp. 10,000.00

: Tenaga Kerja1.200 OH Pekerja @ Rp. 70,000.00 Rp. 84,000.00 0.200 OH Tukang @ Rp. 80,000.00 Rp. 16,000.00 0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00 0.060 OH Mandor @ Rp. 80,000.00 Rp. 4,800.00

Jumlah Rp. 771,630.82 Dibulatkan Rp. 771,630.00

Page 51: JUKNIS PERENCANAAN 2014

Anl. SNI 7394-2008 6.51 M3 Membuat Beton Mutu F'c=14.5 Mpa (K175), Slump (12 ± 2)cm,w/c=0.66: Bahan

326.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 519,155.00 760.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 103,142.86 1029.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 167,688.89 215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00 0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00 0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00 0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 947,676.75 Dibulatkan Rp. 947,676.00

Anl. SNI 7394-2008 6.61 M3 Membuat Beton Mutu F'c=16.9 Mpa (K200), Slump (12 ± 2)cm,w/c=0.61: Bahan

352.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 560,560.00 731.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 99,207.14 1031.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 168,014.81 215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00 0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00 0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00 0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 985,471.96 Dibulatkan Rp. 985,471.00

Anl. SNI 7394-2008 6.71 M3 Membuat Beton Mutu F'c=19.3 Mpa (K225), Slump (12 ± 2) cm, w/c=0.58: Bahan

371.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 590,817.50 698.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 94,728.57 1047.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 170,622.22 215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00 0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00 0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00 0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 1,013,858.29 Dibulatkan Rp. 1,013,858.00

Anl. SNI 7394-2008 6.81 M3 Membuat Beton Mutu F'c=21.7 Mpa (K250), Slump (12 ± 2) cm, w/c=0.56: Bahan

384.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 611,520.00 692.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 93,914.29 1039.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 169,318.52 215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00 0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00 0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00 0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 1,032,442.80 Dibulatkan Rp. 1,032,442.00

Page 52: JUKNIS PERENCANAAN 2014

Anl. SNI 7394-2008 6.91 M3 Membuat Beton Mutu F'c=24.0 Mpa (K275), Slump (12 ± 2)cm,w/c=0.53: Bahan

406.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 646,555.00 684.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 92,828.57 1026.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 167,200.00 215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00 0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00 0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00 0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 1,064,273.57 Dibulatkan Rp. 1,064,273.00

Anl. SNI 7394-2008 6.101 M3 Membuat Beton Mutu F'c=26.4 Mpa (K300), Slump (12 ± 2)cm,w/c=0.52: Bahan

413.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 657,702.50 681.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 92,421.43 1021.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 166,385.19 215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00 0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00 0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00 0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 1,074,199.11 Dibulatkan Rp. 1,074,199.00

Anl. SNI 7394-2008 6.111 M3 Membuat Beton Mutu F'c=28.8 Mpa (K325), Slump (12 ± 2)cm,w/c=0.49: Bahan

439.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 699,107.50 670.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 90,928.57 1006.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 163,940.74 215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja2.100 OH Pekerja @ Rp. 70,000.00 Rp. 147,000.00 0.350 OH Tukang @ Rp. 80,000.00 Rp. 28,000.00 0.035 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,500.00 0.105 OH Mandor @ Rp. 80,000.00 Rp. 8,400.00

Jumlah Rp. 1,151,626.81 Dibulatkan Rp. 1,151,626.00

Anl. SNI 7394-2008 6.121 M3 Membuat Beton Mutu F'c=31.2 Mpa (K350), Slump (12 ± 2)cm,w/c=0.48: Bahan

448.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 713,440.00 667.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 90,521.43 1000.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 162,962.96 215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja2.100 OH Pekerja @ Rp. 70,000.00 Rp. 147,000.00 0.350 OH Tukang @ Rp. 80,000.00 Rp. 28,000.00 0.035 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,500.00 0.105 OH Mandor @ Rp. 80,000.00 Rp. 8,400.00

Jumlah Rp. 1,164,574.39 Dibulatkan Rp. 1,164,574.00

Page 53: JUKNIS PERENCANAAN 2014

Anl. SNI 7394-2008 6.1710 kg Pembesian Dengan Besi Ulir: Bahan

10.500 kg Besi Beton Ulir @ Rp. 13,000.00 Rp. 136,500.00 0.150 kg Kawat Beton @ Rp. 19,500.00 Rp. 2,925.00

: Tenaga Kerja0.070 OH Pekerja @ Rp. 70,000.00 Rp. 4,900.00 0.070 OH Tukang @ Rp. 80,000.00 Rp. 5,600.00 0.007 OH Kepala Tukang @ Rp. 100,000.00 Rp. 700.00 0.004 OH Mandor @ Rp. 80,000.00 Rp. 320.00

Jumlah Rp. 150,945.00 per 1 kg Rp. 15,094.50 Dibulatkan Rp. 15,094.50

Anl. SNI 7394-2008 6.17a1 kg Pembesian Dengan Besi Polos: Bahan

10.500 kg Besi Beton Polos @ Rp. 12,000.00 Rp. 126,000.00 0.150 kg Kawat Beton @ Rp. 19,500.00 Rp. 2,925.00

: Tenaga Kerja0.070 OH Pekerja @ Rp. 70,000.00 Rp. 4,900.00 0.070 OH Tukang @ Rp. 80,000.00 Rp. 5,600.00 0.007 OH Kepala Tukang @ Rp. 100,000.00 Rp. 700.00 0.004 OH Mandor @ Rp. 80,000.00 Rp. 320.00

Jumlah Rp. 140,445.00 per kg Rp. 14,044.50 Dibulatkan Rp. 14,044.50

Anl. SNI 7394-2008 6.1810 Kg Kabel Presstressed Polos: Bahan

10.500 kg Besi Beton Polos @ Rp. 12,000.00 Rp. 126,000.00 0.100 kg Kawat Beton @ Rp. 19,500.00 Rp. 1,950.00

: Tenaga Kerja0.050 OH Pekerja @ Rp. 70,000.00 Rp. 3,500.00 0.050 OH Tukang @ Rp. 80,000.00 Rp. 4,000.00 0.0050 OH Kepala Tukang @ Rp. 100,000.00 Rp. 500.00 0.0030 OH Mandor @ Rp. 80,000.00 Rp. 240.00

Jumlah Rp. 136,190.00 Dibulatkan Rp. 136,190.00

Anl. SNI 7394-2008 6.201 M2 Memasang Bekisting Untuk Pondasi: Bahan

0.040 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 208,000.00 0.300 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 5,100.00 0.100 Liter Minyak Bekisting @ Rp. 3,500.00 Rp. 350.00

: Tenaga Kerja0.520 OH Pekerja @ Rp. 70,000.00 Rp. 36,400.00 0.260 OH Tukang @ Rp. 80,000.00 Rp. 20,800.00 0.026 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,600.00 0.026 OH Mandor @ Rp. 80,000.00 Rp. 2,080.00

Jumlah Rp. 275,330.00 Dibulatkan Rp. 275,330.00

Anl. SNI 7394-2008 6.211 M2 Memasang Bekisting Untuk Sloof: Bahan

Page 54: JUKNIS PERENCANAAN 2014

0.045 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 234,000.00 0.300 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 5,100.00 0.100 Liter Minyak Bekisting @ Rp. 3,500.00 Rp. 350.00

: Tenaga Kerja0.520 OH Pekerja @ Rp. 70,000.00 Rp. 36,400.00 0.260 OH Tukang @ Rp. 80,000.00 Rp. 20,800.00 0.026 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,600.00 0.026 OH Mandor @ Rp. 80,000.00 Rp. 2,080.00

Jumlah Rp. 301,330.00 Dibulatkan Rp. 301,330.00

Anl. SNI 7394-2008 6.221 M2 Memasang Bekisting Untuk Kolom: Bahan

0.040 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 208,000.00 0.400 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 6,800.00 0.200 Liter Minyak Bekisting @ Rp. 3,500.00 Rp. 700.00 0.015 m3 Balok Kayu Kelas II @ Rp. 8,450.00 Rp. 126.75 0.350 Lembar Multipleks 9 mm @ Rp. 136,500.00 Rp. 47,775.00 2.000 Batang Dolken Kayu Galam Dia. 8 - 10 Panjang 4 m @ Rp. 10,000.00 Rp. 20,000.00

: Tenaga Kerja0.660 OH Pekerja @ Rp. 70,000.00 Rp. 46,200.00 0.330 OH Tukang @ Rp. 80,000.00 Rp. 26,400.00 0.033 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,300.00 0.033 OH Mandor @ Rp. 80,000.00 Rp. 2,640.00

Jumlah Rp. 361,941.75 Dibulatkan Rp. 361,941.00

Anl. SNI 7394-2008 6.231 M2 Memasang Bekisting Untuk Balok: Bahan

0.040 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 208,000.00 0.400 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 6,800.00 0.200 Liter Minyak Bekisting @ Rp. 3,500.00 Rp. 700.00 0.018 m3 Balok Kayu Kelas II @ Rp. 8,450.00 Rp. 152.10 0.350 Lembar Multipleks 9 mm @ Rp. 136,500.00 Rp. 47,775.00 2.000 Batang Dolken Kayu Galam Dia. 8 - 10 Panjang 4 m @ Rp. 10,000.00 Rp. 20,000.00

: Tenaga Kerja0.660 OH Pekerja @ Rp. 70,000.00 Rp. 46,200.00 0.330 OH Tukang @ Rp. 80,000.00 Rp. 26,400.00 0.033 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,300.00 0.033 OH Mandor @ Rp. 80,000.00 Rp. 2,640.00

Jumlah Rp. 361,967.10 Dibulatkan Rp. 361,967.00

Anl. SNI 7394-2008 6.241 M2 Memasang Bekisting Untuk Plat Lantai: Bahan

0.040 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 208,000.00 0.400 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 6,800.00 0.200 Liter Minyak Bekisting @ Rp. 3,500.00 Rp. 700.00 0.015 m3 Balok Kayu Kelas II @ Rp. 8,450.00 Rp. 126.75 0.350 Lembar Multipleks 9 mm @ Rp. 136,500.00 Rp. 47,775.00 6.000 Batang Dolken Kayu Galam Dia. 8 - 10 Panjang 4 m @ Rp. 10,000.00 Rp. 60,000.00

: Tenaga Kerja0.660 OH Pekerja @ Rp. 70,000.00 Rp. 46,200.00 0.330 OH Tukang @ Rp. 80,000.00 Rp. 26,400.00 0.033 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,300.00 0.033 OH Mandor @ Rp. 80,000.00 Rp. 2,640.00

Jumlah Rp. 401,941.75 Dibulatkan Rp. 401,941.00

Anl. SNI 7394-2008 6.261 M2 Memasang Bekisting Untuk Tangga: Bahan

0.030 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 156,000.00

Page 55: JUKNIS PERENCANAAN 2014

0.400 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 6,800.00 0.150 Liter Minyak Bekisting @ Rp. 3,500.00 Rp. 525.00 0.015 m3 Balok Kayu Kelas II @ Rp. 8,450.00 Rp. 126.75 0.350 Lembar Multipleks 9 mm @ Rp. 136,500.00 Rp. 47,775.00 2.000 Batang Dolken Kayu Galam Dia. 8 - 10 Panjang 4 m @ Rp. 10,000.00 Rp. 20,000.00

: Tenaga Kerja0.660 OH Pekerja @ Rp. 70,000.00 Rp. 46,200.00 0.330 OH Tukang @ Rp. 80,000.00 Rp. 26,400.00 0.033 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,300.00 0.033 OH Mandor @ Rp. 80,000.00 Rp. 2,640.00

Jumlah Rp. 309,766.75 Dibulatkan Rp. 309,766.00

Anl. SNI 7394-2008 6.271 M2 Memasang Jembatan Untuk Pengecoran Beton: Bahan

0.0264 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 137,280.00 0.600 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 10,200.00 0.500 Batang Dolken Kayu Galam Dia. 8 - 10 Panjang 4 m @ Rp. 10,000.00 Rp. 5,000.00

: Tenaga Kerja0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00 0.050 OH Tukang @ Rp. 80,000.00 Rp. 4,000.00 0.005 OH Kepala Tukang @ Rp. 100,000.00 Rp. 500.00 0.008 OH Mandor @ Rp. 80,000.00 Rp. 640.00

Jumlah Rp. 168,120.00 Dibulatkan Rp. 168,120.00

Page 56: JUKNIS PERENCANAAN 2014

SNI 2837:2008

Tata cara perhitungan harga satuan pekerjaan plesteran

untuk konstruksi bangunan gedung dan perumahan

Page 57: JUKNIS PERENCANAAN 2014

Anl. SNI 2837-2008 6.11 M2 Membuat Plesteran 1 PC : 1 PP, Tebal 15 mm: Bahan

15.504 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 24,690.12 0.016 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 2,880.00

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00 0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 63,270.12 Dibulatkan Rp. 63,270.00

Anl. SNI 2837-2008 6.21 M2 Membuat Plesteran 1 PC : 2 PP, Tebal 15 mm: Bahan

10.224 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 16,281.72 0.020 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 3,600.00

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00 0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 55,581.72 Dibulatkan Rp. 55,581.00

Anl. SNI 2837-2008 6.31 M2 Membuat Plesteran 1 PC : 3 PP, Tebal 15 mm: Bahan

7.776 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 12,383.28 0.023 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 4,140.00

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00 0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 52,223.28 Dibulatkan Rp. 52,223.00

Anl. SNI 2837-2008 6.41 M2 Membuat Plesteran 1 PC : 4 PP, Tebal 15 mm: Bahan

6.240 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 9,937.20 0.024 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 4,320.00

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00 0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 49,957.20 Dibulatkan Rp. 49,957.00

Page 58: JUKNIS PERENCANAAN 2014

ParafPenanggung jawab Estimator

Anl. SNI 2837-2008 6.51 M2 Membuat Plesteran 1 PC : 5 PP, Tebal 15 mm: Bahan

5.184 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 8,255.52 0.026 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 4,680.00

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00 0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 48,635.52 Dibulatkan Rp. 48,635.00

Anl. SNI 2837-2008 6.61 M2 Membuat Plesteran 1 PC : 6 PP, Tebal 15 mm: Bahan

4.416 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 7,032.48 0.027 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 4,860.00

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00 0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 47,592.48 Dibulatkan Rp. 47,592.00

Anl. SNI 2837-2008 6.71 M2 Membuat Plesteran 1 PC : 7 PP, Tebal 15 mm: Bahan

3.936 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 6,268.08 0.028 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 5,040.00

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00 0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 47,008.08 Dibulatkan Rp. 47,008.00

Anl. SNI 2837-2008 6.81 M2 Membuat Plesteran 1 PC : 8 PP, Tebal 15 mm: Bahan

3.456 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 5,503.68 0.029 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 5,220.00

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00 0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 46,423.68 Dibulatkan Rp. 46,423.00

Page 59: JUKNIS PERENCANAAN 2014

ParafPenanggung jawab Estimator

Anl. SNI 2837-2008 6.131 M2 Membuat Plesteran 1 PC : 2 PP, Tebal 20 mm: Bahan

13.632 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 21,708.96 0.027 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 4,860.00

: Tenaga Kerja0.400 OH Pekerja @ Rp. 70,000.00 Rp. 28,000.00 0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00 0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00 0.022 OH Mandor @ Rp. 80,000.00 Rp. 1,760.00

Jumlah Rp. 74,328.96 Dibulatkan Rp. 74,328.00

Anl. SNI 2837-2008 6.141 M2 Membuat Plesteran 1 PC : 3 PP, Tebal 20 mm: Bahan

10.368 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 16,511.04 0.031 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 5,580.00

: Tenaga Kerja0.260 OH Pekerja @ Rp. 70,000.00 Rp. 18,200.00 0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00 0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00 0.013 OH Mandor @ Rp. 80,000.00 Rp. 1,040.00

Jumlah Rp. 59,331.04 Dibulatkan Rp. 59,331.00

Anl. SNI 2837-2008 6.15: 1 M2 Membuat Plesteran 1 PC : 4 PP, Tebal 20 mm: Bahan

8.320 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 13,249.60 0.032 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 5,760.00

: Tenaga Kerja0.400 OH Pekerja @ Rp. 70,000.00 Rp. 28,000.00 0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00 0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00 0.022 OH Mandor @ Rp. 80,000.00 Rp. 1,760.00

Jumlah Rp. 66,769.60 Dibulatkan Rp. 66,769.00

Anl. SNI 2837-2008 6.161 M2 Membuat Plesteran 1 PC : 5 PP, Tebal 20 mm: Bahan

6.912 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 11,007.36 0.035 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 6,300.00

: Tenaga Kerja0.400 OH Pekerja @ Rp. 70,000.00 Rp. 28,000.00 0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00 0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00 0.022 OH Mandor @ Rp. 80,000.00 Rp. 1,760.00

Jumlah Rp. 65,067.36 Dibulatkan Rp. 65,067.00

Page 60: JUKNIS PERENCANAAN 2014

ParafPenanggung jawab Estimator

Anl. SNI 2837-2008 6.171 M2 Membuat Plesteran 1 PC : 6 PP, Tebal 20 mm: Bahan

5.888 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 9,376.64 0.036 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 6,480.00

: Tenaga Kerja0.400 OH Pekerja @ Rp. 70,000.00 Rp. 28,000.00 0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00 0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00 0.022 OH Mandor @ Rp. 80,000.00 Rp. 1,760.00

Jumlah Rp. 63,616.64 Dibulatkan Rp. 63,616.00

Anl. SNI 2837-2008 6.191 M2 Membuat Berapen 1 PC : 5 PP, Tebal 15 mm: Bahan

5.184 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 8,255.52 0.026 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 4,680.00

: Tenaga Kerja0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00 0.075 OH Tukang Batu @ Rp. 80,000.00 Rp. 6,000.00 0.008 OH Kepala Tukang @ Rp. 100,000.00 Rp. 800.00 0.008 OH Mandor @ Rp. 80,000.00 Rp. 640.00

Jumlah Rp. 30,875.52 Dibulatkan Rp. 30,875.00

Anl. SNI 2837-2008 6.201 M2 Membuat Plesteran Skoning Lebar 10 mm 1 PC : 2 PP: Bahan

0.500 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 796.25 0.013 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 2,340.00

: Tenaga Kerja0.080 OH Pekerja @ Rp. 70,000.00 Rp. 5,600.00 0.400 OH Tukang Batu @ Rp. 80,000.00 Rp. 32,000.00 0.040 OH Kepala Tukang @ Rp. 100,000.00 Rp. 4,000.00 0.004 OH Mandor @ Rp. 80,000.00 Rp. 320.00

Jumlah Rp. 45,056.25 Dibulatkan Rp. 45,056.00

Anl. SNI 2837-2008 6.231 M2 Membuat Plesteran Ciprat/Kamprotan 1 PC : 2 PP: Bahan

4.320 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 6,879.60 0.006 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 1,080.00

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.100 OH Tukang Batu @ Rp. 80,000.00 Rp. 8,000.00 0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00

Page 61: JUKNIS PERENCANAAN 2014

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00 Jumlah Rp. 39,159.60 Dibulatkan Rp. 39,159.00

ParafPenanggung jawab Estimator

Anl. SNI 2837-2008 6.241 M2 Membuat Finishing Siar Pasangan Dinding Bata Merah (=20 m'): Bahan

3.108 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 4,949.49 : Tenaga Kerja

0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00 0.075 OH Tukang Batu @ Rp. 80,000.00 Rp. 6,000.00 0.008 OH Kepala Tukang @ Rp. 100,000.00 Rp. 800.00 0.008 OH Mandor @ Rp. 80,000.00 Rp. 640.00

Jumlah Rp. 22,889.49 Dibulatkan Rp. 22,889.00

Anl. SNI 2837-2008 6.251 M2 Membuat Finishing Siar Pasangan Dinding Conblock Ekspose (=8 m'): Bahan

1.600 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 2,548.00 : Tenaga Kerja

0.070 OH Pekerja @ Rp. 70,000.00 Rp. 4,900.00 0.035 OH Tukang Batu @ Rp. 80,000.00 Rp. 2,800.00 0.004 OH Kepala Tukang @ Rp. 100,000.00 Rp. 400.00 0.004 OH Mandor @ Rp. 80,000.00 Rp. 320.00

Jumlah Rp. 10,968.00 Dibulatkan Rp. 10,968.00

Anl. SNI 2837-2008 6.261 M2 Membuat Finishing Siar Pasangan Batu Kali Adukan 1 PC : 2 PP: Bahan

6.340 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 10,096.45 0.012 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 2,160.00

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00 0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 45,796.45 Dibulatkan Rp. 45,796.00

Anl. SNI 2837-2008 6.271 M2 Membuat Acian: Bahan

3.250 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 5,175.63 : Tenaga Kerja

0.200 OH Pekerja @ Rp. 70,000.00 Rp. 14,000.00 0.100 OH Tukang Batu @ Rp. 80,000.00 Rp. 8,000.00 0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00

Page 62: JUKNIS PERENCANAAN 2014

0.010 OH Mandor @ Rp. 80,000.00 Rp. 800.00 Jumlah Rp. 28,975.63 Dibulatkan Rp. 28,975.00

22,150,000.00 0.413

430.75912.521

10918312

ParafPenanggung jawab Estimator

Page 63: JUKNIS PERENCANAAN 2014

SNI

Tata cara perhitungan harga satuan pekerjaan plesteran

untuk konstruksi bangunan gedung dan perumahan

Page 64: JUKNIS PERENCANAAN 2014

Anl. Pt T-38-2000-C-Tembok.11 m2 Mengikis atau mengerok cat tembok cara manual: Bahan

0.000 - - @ Rp. - Rp. - 0.000 - - @ Rp. - Rp. -

: Alat Bantu0.050 buah Kape/Skrap @ Rp. 10,000.00 Rp. 500.00

: Tenaga Kerja0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00 0.000 OH Tukang @ Rp. 80,000.00 Rp. - 0.000 OH Kepala Tukang @ Rp. 100,000.00 Rp. - 0.008 OH Mandor @ Rp. 80,000.00 Rp. 640.00

Jumlah Rp. 11,640.00 Dibulatkan Rp. 11,640.00

Anl. Pt T-38-2000-C-Tembok.21 m2 mencuci bidang permukaan tembok lama dengan sabun: Bahan

0.050 kg Sabun @ Rp. - Rp. - : Alat Bantu

0.000 buah - @ Rp. - Rp. - : Tenaga Kerja

0.080 OH Pekerja @ Rp. 70,000.00 Rp. 5,600.00 0.000 OH Tukang @ Rp. 80,000.00 Rp. - 0.000 OH Kepala Tukang @ Rp. 100,000.00 Rp. - 0.004 OH Mandor @ Rp. 80,000.00 Rp. 320.00

Jumlah Rp. 5,920.00 Dibulatkan Rp. 5,920.00

Anl. Pt T-38-2000-C-Tembok.31 m2 Lapis plamir: Bahan

0.100 kg Plamur Tembok @ Rp. 32,500.00 Rp. 3,250.00 : Alat Bantu

0.500 lbr Kertas Amplas @ Rp. 2,600.00 Rp. 1,300.00 : Tenaga Kerja

0.020 OH Pekerja @ Rp. 70,000.00 Rp. 1,400.00 0.030 OH Tukang @ Rp. 80,000.00 Rp. 2,400.00 0.003 OH Kepala Tukang @ Rp. 100,000.00 Rp. 300.00 0.001 OH Mandor @ Rp. 80,000.00 Rp. 80.00

Jumlah Rp. 8,730.00 Dibulatkan Rp. 8,730.00

Anl. Pt T-38-2000-C-Tembok.41 m2 Pengecatan bidang tembok 2 lapis dengan kuas: Bahan

0.240 kg Cat Tembok @ Rp. 31,200.00 Rp. 7,488.00 : Alat Bantu

0.015 buah Kuas @ Rp. 7,865.00 Rp. 117.98 : Tenaga Kerja

0.060 OH Pekerja @ Rp. 70,000.00 Rp. 4,200.00 0.050 OH Tukang @ Rp. 80,000.00 Rp. 4,000.00 0.005 OH Kepala Tukang @ Rp. 100,000.00 Rp. 500.00 0.003 OH Mandor @ Rp. 80,000.00 Rp. 240.00

Jumlah Rp. 16,545.98 Dibulatkan Rp. 16,545.00

Page 65: JUKNIS PERENCANAAN 2014

Anl. Pt T-38-2000-C-Tembok.51 m2 Pengecatan bidang tembok 2 lapis dengan roll: Bahan

0.470 kg Cat Tembok @ Rp. 31,200.00 Rp. 14,664.00 : Alat Bantu

0.010 kg Roll @ Rp. 35,000.00 Rp. 350.00 : Tenaga Kerja

0.040 OH Pekerja @ Rp. 70,000.00 Rp. 2,800.00 0.030 OH Tukang @ Rp. 80,000.00 Rp. 2,400.00 0.003 OH Kepala Tukang @ Rp. 100,000.00 Rp. 300.00 0.002 OH Mandor @ Rp. 80,000.00 Rp. 160.00

Jumlah Rp. 20,674.00 Dibulatkan Rp. 20,674.00

Anl. Pt T-38-2000-C-Langit2.61 m2 Pengecatan langit-langit 2 lapis dengan cat tembok, menggunakan kuas termasuk plamir: Bahan

0.100 kg Plamur Tembok @ Rp. 32,500.00 Rp. 3,250.00 0.240 kg Cat Tembok @ Rp. 31,200.00 Rp. 7,488.00 0.500 Lembar Kertas Amplas @ Rp. 2,600.00 Rp. 1,300.00 0.050 Buah Kape @ Rp. #N/A Rp. #N/A

: Alat Bantu0.015 buah Kuas @ Rp. 7,865.00 Rp. 117.98 0.050 Buah Kape @ Rp. #N/A Rp. #N/A

: Tenaga Kerja0.080 OH Pekerja @ Rp. 70,000.00 Rp. 5,600.00 0.060 OH Tukang @ Rp. 80,000.00 Rp. 4,800.00 0.006 OH Kepala Tukang @ Rp. 100,000.00 Rp. 600.00 0.004 OH Mandor @ Rp. 80,000.00 Rp. 320.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. Pt T-38-2000-C-Langit2.71 m2 Pengecatan langit-langit 2 lapis dengan cat tembok, menggunakan roll termasuk plamir: Bahan

0.100 kg Plamur Tembok @ Rp. 32,500.00 Rp. 3,250.00 0.470 kg Cat Tembok @ Rp. 31,200.00 Rp. 14,664.00 0.500 kg Kertas Amplas @ Rp. 2,600.00 Rp. 1,300.00

: Alat Bantu0.010 buah Roll @ Rp. #N/A Rp. #N/A0.050 Buah Kape @ Rp. #N/A Rp. #N/A

: Tenaga Kerja0.080 OH Pekerja @ Rp. 70,000.00 Rp. 5,600.00 0.060 OH Tukang @ Rp. 80,000.00 Rp. 4,800.00 0.006 OH Kepala Tukang @ Rp. 100,000.00 Rp. 600.00 0.004 OH Mandor @ Rp. 80,000.00 Rp. 320.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. Pt T-38-2000-C-Wallpaper.81 m2 Pasang wallpaper dengan perekat: Bahan

1.100 m2 Wallpaper @ Rp. #N/A Rp. #N/A0.200 kg Perekat/Lem @ Rp. #N/A Rp. #N/A

: Alat Bantu0.000 buah - @ Rp. - Rp. - 0.000 Buah - @ Rp. - Rp. -

: Tenaga Kerja0.010 OH Pekerja @ Rp. 70,000.00 Rp. 700.00 0.100 OH Tukang @ Rp. 80,000.00 Rp. 8,000.00

Page 66: JUKNIS PERENCANAAN 2014

0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00 0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. Pt T-38-2000-C-Kayu.11 m2 melapis meni kayu: Bahan

0.170 kg Meni @ Rp. #N/A Rp. #N/A0.100 kg Minyak cat @ Rp. 26,000.00 Rp. 2,600.00

: Alat Bantu0.015 buah Kuas @ Rp. 7,865.00 Rp. 117.98 0.000 Buah - @ Rp. - Rp. -

: Tenaga Kerja0.075 OH Pekerja @ Rp. 70,000.00 Rp. 5,250.00 0.000 OH Tukang @ Rp. 80,000.00 Rp. - 0.000 OH Kepala Tukang @ Rp. 100,000.00 Rp. - 0.004 OH Mandor @ Rp. 80,000.00 Rp. 320.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. Pt T-38-2000-C-Kayu.21 m2 mendempul/memplamir dan menggosok kayu: Bahan

0.150 kg Dempul kayu @ Rp. 19,500.00 Rp. 2,925.00 0.080 kg Plamur kayu @ Rp. #N/A Rp. #N/A0.100 kg Minyak cat @ Rp. 26,000.00 Rp. 2,600.00

: Alat Bantu1.000 buah Kertas amplas @ Rp. 2,600.00 Rp. 2,600.00 0.015 Buah Kuas @ Rp. 7,865.00 Rp. 117.98

: Tenaga Kerja0.000 OH Pekerja @ Rp. 70,000.00 Rp. - 0.110 OH Tukang @ Rp. 80,000.00 Rp. 8,800.00 0.011 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,100.00 0.000 OH Mandor @ Rp. 80,000.00 Rp. -

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. Pt T-38-2000-C-Kayu.31 m2 mengecat dasar 1 (satu) lapis: Bahan

0.170 kg Cat dasar @ Rp. #N/A Rp. #N/A0.100 kg Minyak cat @ Rp. 26,000.00 Rp. 2,600.00

: Alat Bantu1.000 buah Kertas amplas @ Rp. 2,600.00 Rp. 2,600.00 0.015 Buah Kuas @ Rp. 7,865.00 Rp. 117.98

: Tenaga Kerja0.000 OH Pekerja @ Rp. 70,000.00 Rp. - 0.075 OH Tukang @ Rp. 80,000.00 Rp. 6,000.00 0.008 OH Kepala Tukang @ Rp. 100,000.00 Rp. 800.00 0.000 OH Mandor @ Rp. 80,000.00 Rp. -

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. Pt T-38-2000-C-Kayu.41 m2 mengecat penutup 2 lapis pada kayu: Bahan

0.300 kg Cat warna @ Rp. #N/A Rp. #N/A0.200 kg Minyak cat @ Rp. 26,000.00 Rp. 5,200.00

Page 67: JUKNIS PERENCANAAN 2014

: Alat Bantu0.020 Buah Kuas @ Rp. 7,865.00 Rp. 157.30

: Tenaga Kerja0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00 0.150 OH Tukang @ Rp. 80,000.00 Rp. 12,000.00 0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00 0.008 OH Mandor @ Rp. 80,000.00 Rp. 640.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Page 68: JUKNIS PERENCANAAN 2014

Anl. Pt T-38-2000-C-Baja.51 m2 mengerok karat atau cat pada permukaan baja dengan soda api: Bahan

0.050 kg Soda api @ Rp. #N/A Rp. #N/A: Alat Bantu

0.500 Lembar Kertas Amplas @ Rp. 2,600.00 Rp. 1,300.00 0.050 Buah Sikat baja @ Rp. #N/A Rp. #N/A

: Tenaga Kerja0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00 0.000 OH Tukang @ Rp. 80,000.00 Rp. - 0.000 OH Kepala Tukang @ Rp. 100,000.00 Rp. - 0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. Pt T-38-2000-C-Baja.61 m2 melapis meni pada permukaan baja: Bahan

0.100 kg Meni @ Rp. #N/A Rp. #N/A0.100 Liter Minyak cat @ Rp. 26,000.00 Rp. 2,600.00

: Alat Bantu0.050 Lembar Kertas Amplas @ Rp. 2,600.00 Rp. 130.00 0.015 Buah Kuas @ Rp. 7,865.00 Rp. 117.98

Page 69: JUKNIS PERENCANAAN 2014

: Tenaga Kerja0.075 OH Pekerja @ Rp. 70,000.00 Rp. 5,250.00 0.000 OH Tukang @ Rp. 80,000.00 Rp. - 0.000 OH Kepala Tukang @ Rp. 100,000.00 Rp. - 0.004 OH Mandor @ Rp. 80,000.00 Rp. 320.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. Pt T-38-2000-C-Baja.71 m2 mengecat penutup 2 lapis pada permukaan baja secara manual: Bahan

0.200 kg Cat warna @ Rp. #N/A Rp. #N/A0.100 Liter Minyak cat @ Rp. 26,000.00 Rp. 2,600.00

: Alat Bantu0.020 Buah Kuas @ Rp. 7,865.00 Rp. 157.30

: Tenaga Kerja0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00 0.150 OH Tukang @ Rp. 80,000.00 Rp. 12,000.00 0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00 0.008 OH Mandor @ Rp. 80,000.00 Rp. 640.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. Pt T-38-2000-C-Baja.81 m2 mengecat penutup 2 lapis pada permukaan baja/kayu dengan penyemprot: Bahan

0.400 kg Cat warna @ Rp. #N/A Rp. #N/A0.300 Liter Minyak cat @ Rp. 26,000.00 Rp. 7,800.00

: Alat Bantu0.000 Buah - @ Rp. - Rp. -

: Tenaga Kerja0.020 OH Pekerja @ Rp. 70,000.00 Rp. 1,400.00 0.150 OH Tukang @ Rp. 80,000.00 Rp. 12,000.00 0.001 OH Kepala Tukang @ Rp. 100,000.00 Rp. 100.00 0.001 OH Mandor @ Rp. 80,000.00 Rp. 80.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. Pt T-38-2000-C-Baja.81 m2 mengecat penutup 2 lapis pada permukaan baja/kayu dengan penyemprot: Bahan

0.400 kg Cat warna @ Rp. #N/A Rp. #N/A0.300 Liter Minyak cat @ Rp. 26,000.00 Rp. 7,800.00

: Alat Bantu0.000 Buah - @ Rp. - Rp. -

: Tenaga Kerja0.020 OH Pekerja @ Rp. 70,000.00 Rp. 1,400.00 0.150 OH Tukang @ Rp. 80,000.00 Rp. 12,000.00 0.001 OH Kepala Tukang @ Rp. 100,000.00 Rp. 100.00 0.001 OH Mandor @ Rp. 80,000.00 Rp. 80.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Page 70: JUKNIS PERENCANAAN 2014

ParafPenanggung jawab Estimator

Page 71: JUKNIS PERENCANAAN 2014

REKAPITULASI RENCANA ANGGARAN BIAYA

Kegiatan :Pekerjaan :Lokasi :T.A. :

NO. URAIAN JUMLAH TOTAL HARGA

Divisi 1 Design development Rp. ...

Divisi 2 SiteworkRp. ...

Divisi 3 Pekerjaan StrukturalRp. ...

Divisi 4 Pekerjaan ArsitekturRp. ...

Divisi 5 Pekerjaan MekanikalRp. ...

Divisi 6 Pekerjaan ElektrikalRp. ...

Divisi 7 Fasilitas eksterior bangunanRp. ...

Divisi 8 Pekerjaan MekanikalRp. ...

Divisi 9 Pekerjaan MekanikalRp. ...

REKAPITULASI JUMLAH TOTAL Rp. ...

terbilang: ...

Lhokseumawe, .... Mengetahui Penanggungjawab Perencanaan

Kepala Bidang Program dan Perencanaan PT./CV. ....Dinas Pekerjaan Umum Kota Lhokseumawe

TUTI INDRIANI, ST, MM NAMA PIMPINANNIP. 19680614 199703 2 002 Jabatan

MenyetujuiKepala Dinas Pekerjaan Umum Kota Lhokseumawe

Ir. TEUKU ZAHEDI, MTNIP. 19621103 199203 1 001

Page 72: JUKNIS PERENCANAAN 2014

RENCANA ANGGARAN BIAYA

Kegiatan :Pekerjaan :Lokasi :T.A. :

NO. URAIANSATUAN ANALISA HARGA SATUAN JUMLAH HARGA

(Rp.) (Rp.)Divisi 1 Design development

1.1 Dokumen kontrak1.2 Asuransi dan jaminan1.3 Shop drawing dan as-built drawing1.4 Site management1.5 Dokumentasi proyek

Total Jumlah Harga Divisi 1 : ...Divisi 2 Sitework

2.1 Setting-out2.2 Fasilitas sementara2.3 Mobilisasi dan demobilisasi2.4 Pembersihan lahan dan removal

2.5

Total Jumlah Harga Divisi 2 : ...Divisi 3 Pekerjaan Struktural

3.1 Pekerjaan struktural di atas tanah3.2 Pekerjaan struktural di bawah tanah3.3 Mobilisasi dan demobilisasi

Total Jumlah Harga Divisi 3 : ...Divisi 4 Pekerjaan Arsitektur

4.1 Beton4.2 Logam4.3 Kayu dan plastik4.4 Pasangan (masonry)4.5 Perlindungan suhu dan kelembaban4.6 Bukaan (jendela, pintu, kusen)4.7 Finishing

Total Jumlah Harga Divisi 4 : ...Divisi 5 Pekerjaan Mekanikal

5.1 Plambing

5.2

5.3 Pencegahan KebakaranTotal Jumlah Harga Divisi 5 : ...

Divisi 6 Pekerjaan Elektrikal6.1 Sistem distribusi jaringan listrik6.2 Sistem pencahayaan6.3 Sistem komunikasi6.4 Pencegahan petir

Total Jumlah Harga Divisi 6 : ...Divisi 7 Fasilitas eksterior bangunan

7.1 Paving, perparkiran, pedestrian7.2 Pagar dan gerbang

7.3

Total Jumlah Harga Divisi 7 : ...Divisi 8 Interior fixtures

8.18.2

Total Jumlah Harga Divisi 8 : ...

ParafPenanggung jawab Estimator

Galian, pemotongan, timbunan dan buangan

Pemanasan, ventilasi dan pengkodisian udara

Pertamanan dan landscaping (tanaman, rumput, tanah)

Page 73: JUKNIS PERENCANAAN 2014
Page 74: JUKNIS PERENCANAAN 2014

NO. URAIANSATUAN ANALISA HARGA SATUAN JUMLAH HARGA

(Rp.) (Rp.)Divisi 9 Miscellneous works

9.1 Peralatan9.2 Konstruksi khusus9.3 Conveying equipment

Total Jumlah Harga Divisi 9 : ...

Lhokseumawe, .... PT./CV. ....

Penghitung RAB/Estimator Team Leader

NAMA NAMA PIMPINANJabatan (sesuai dalam kontrak) Jabatan (sesuai dalam kontrak)

Penanggungjawab Perencanaan

NAMA PIMPINANJabatan (sesuai dalam kontrak)

Catatan: item-item pekerjaan dapat dikembangkan sesuai kebutuhan

Page 75: JUKNIS PERENCANAAN 2014

DAFTAR HARGA UPAH 3.00

NO. URAIAN SATUAN HARGA (Rp)

1 Mandor OH 75,000.00 2 Kepala Tukang OH 100,000.00 3 Tukang OH 80,000.00 4 Pekerja OH 60,000.00 5 Penjaga Malam / SATPAM OH 46,500.00 6 Supir OH 90,000.00 7 Operator OH 130,000.00

Page 76: JUKNIS PERENCANAAN 2014

DAFTAR HARGA BAHAN

NO. URAIAN SATUAN HARGA (Rp)

1 Abu Bata 340,000.00 2 Acustic 30 x 60 Lembar 140,000.00 3 Air liter 50.00 4 Alat-alat Bantu Unit 200,000.00 5 Alti Meter Unit 4,100,000.00 6 Alumanium Foil M2 12,100.00 7 Arang Kg 4,000.00 8 Asbes Eternit 1 x 1 m M2 21,000.00 9 Asbes Gelombang Besar Lembar 50,400.00

10 Asbes Gelombang Kecil Lembar 50,400.00 11 Asbes Quality 1 x 1 m Lembar 28,000.00 12 Asphalt Kg 9,350.00 13 Asphalt Semen Pen. 60/70 atau Pen. 80/100 Kg 12,900.00 14 Atap Asbes Gelombang 8 Kaki Lembar 50,400.00 15 Atap Harflek Lembar 80,000.00 16 Atap multiroof M2 95,200.00 17 Atap Naungan Lembar 4,500.00 18 Atap Rumbia Lembar 6,800.00 19 Atap Seng genteng Metal 0.25 Lembar 90,000.00 20 Atap Seng genteng 0.35 Lembar 110,000.00 21 Ayakan Buah 63,000.00 22 Baja Profil Kg 13,700.00 23 Bak Cuci Piring Logam Buah 343,000.00 24 Bak Cuci Tangan / Wastaafel Keramik Buah 420,000.00 25 Bak Mandi Fibre Buah 420,000.00 26 Bak Mandi Plastik Buah 420,000.00 27 Bak Mandi Porselin Buah 1,400,000.00 28 Balok Kayu Kelas I 11,859,375.00 29 Balok Kayu Kelas II 7,115,625.00 30 Bambu Batang 30,000.00 31 Bataco Buah 4,750.00 32 Batu Bata Buah 560.00 33 Batu Belah 0.5 - 1 cm 435,000.00 34 Batu Belah 1 - 2 cm 435,000.00 35 Batu Belah 10 - 15 cm 300,000.00 36 Batu Belah 3 - 5 cm 300,000.00 37 Batu Belah 5 - 7 cm 350,000.00

38 Batu Belah 7 - 10 cm 350,000.00

39 Batu Gunung 220,000.00

40 Batu Gunung Quary 100,000.00

41 Batu ( < 250 ) Kg - Material Water Break 253,000.00

42 Batu ( > 1000) Kg - Material Water Break 341,000.00

43 Batu (250-1000) Kg - Material Water Break 264,000.00

44 Batu Kali 230,000.00

45 Batu Kali Quary 100,000.00

46 Batu Kali / Batu Belah (Sungai / Gunung) 250,000.00

47 Batu Pakhlag (Batu 5-7 cm ) 250,000.00

48 Batu Pecah 2-3 cm 443,000.00

49 Batu Tempel 275,000.00 50 Baut Kap Dia. 1/2 - 8 Buah 3,000.00 51 Bensin ( Indrustri ) Liter 8,990.00 52 Besi Beton Polos Kg 11,900.00 53 Besi Beton Ulir Kg 13,000.00 54 Besi Bout ( Kuda-kuda ) 5/8 - 10" Buah 9,000.00

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

Page 77: JUKNIS PERENCANAAN 2014

NO. URAIAN SATUAN HARGA (Rp)

55 Besi Gip 2 in Biasa Batang 370,000.00 56 Besi Pipa Roda 16" Batang 524,000.00 57 Beton Pagar Tian Antik I = 70 cm Buah 43,500.00 58 Beton Rooster / Kerawang Buah 10,000.00 59 BRC, 5 - 7 cm; 0,8 mm M2 126,000.00 60 Bubuk / Tepung Batu Kapur Kg 1,750.00 61 Bubungan Genteng M' 58,000.00 62 Bubungan Seng M' 22,000.00 63 Buis Beton 10 cm ₵ Buah 27,000.00 64 Buis Beton 100 cm ₵ M' 155,000.00 65 Buis Beton 15 cm ₵ Buah 35,000.00 66 Buis Beton 20 cm ₵ Buah 40,000.00 67 Buis Beton 30 cm ₵ Buah 60,000.00 68 Buis Beton 40 cm ₵ M' 80,000.00 69 Buis Beton 50 cm ₵ M' 120,000.00 70 Buis Beton 60 cm ₵ M' 135,000.00 71 Buis Beton 80 cm ₵ M' 170,000.00 72 Cat Extana Avitek Kg 30,800.00 73 Cat ICI Super Clos Kg 105,000.00 74 Cat Kayu Dasar Kg 25,200.00 75 Cat Kilat Kg 56,000.00 76 Cat Kayu mengkilap Kg 56,000.00 77 Cat Marka Jalan ( Non Thermoplast ) Kg 62,000.00 78 Cat Marka Jalan ( Thermoplast ) Kg 68,000.00 79 Cat Menie Besi Kg 32,200.00 80 Cat Minyak Kg 56,000.00 81 Cat Tembok 5 Kg 123,200.00 82 Cat tembok ICI (Watersheild) 5 Kg 350,000.00 83 Dalkin (Karpus 361) 30 x 60 cm, t = 12 mm Lembar 73,000.00 84 Dalkin Cealing (Karpus 361) 30 x 60 cm, t = 9 mm Lembar 60,000.00 85 Dalkin Rib (Karpus 361) 30 x 60 cm, t = 12 mm Lembar 70,000.00 86 Dempul Kg 16,680.00 87 Dempul Kayu Kg 16,680.00 88 Dempul Wallfiller Avitek Kg 28,000.00 89 Dolken kayu Dia. 8 - 10 Panjang 4 m Batang 20,000.00 90 Elbow Galvani 1 Inch ₵ Buah 9,800.00 91 Elbow Galvani 1/2 Inch ₵ Buah 5,600.00 92 Elbow Galvani 3 Inch ₵ Buah 33,600.00 93 Elbow Galvani 3/4 Inch ₵ Buah 8,400.00 94 Elbow Galvani 4 Inch ₵ Buah 91,000.00 95 Elbow Galvani 5 Inch ₵ Buah 119,000.00 96 Elbow PVC 1/2 Inch ₵ Buah 2,800.00 97 Elbow PVC 3 Inch ₵ Buah 14,000.00 98 Elbow PVC 3/4 Inch ₵ Buah 2,800.00 99 Elbow PVC 4 Inch ₵ Buah 28,000.00

100 Elbow PVC 5 Inch ₵ Buah 40,600.00 101 Engsel ARCH 3 Inch Buah 11,200.00 102 Engsel ARCH 4 Inch Buah 16,800.00 103 Engsel Bubut 40 mm Pasang 39,200.00 104 Filter Kg 22,000.00 105 Floor Drain Sun Ei Buah 250,000.00 106 Gantungan Handuk Sun Ei Double Buah 490,000.00 107 Gantungan Handuk Sun Ei Single Buah 350,000.00 108 Gemuk / Grease Kg 26,000.00 109 Genteng Concreat Warna Buah 10,000.00 110 Genteng Ekatana Berpasir Keping 105,000.00 111 Genteng Keramik KIA Warna Exclusive Keping 35,000.00 112 Genteng Keramik KIA Warna Khusus Keping 28,000.00

Page 78: JUKNIS PERENCANAAN 2014

NO. URAIAN SATUAN HARGA (Rp)

113 Genteng Kerami KIA Warna Natural Keping 24,500.00 114 Genteng Kerami KIA Warna Premium Keping 42,000.00 115 Genteng Kerami KIA Warna Standar Keping 28,000.00 116 Genteng Metal Emerald Lembar 91,000.00 117 Genteng Super Stell (0.4 x 1.2 m) Keping 71,000.00 118 Geogrid Impor Jerman Type 120/40 R-1 M2 206,000.00 119 Geogrid Impor Jerman Type 120/40 R-6 M2 269,000.00 120 Geogrid Impor Jerman Type 40/40 R-1 M2 125,000.00 121 Geogrid Impor Jerman Type40/40 R- 6 M2 153,000.00 122 Geogrid Impor Jerman Type 80/40 R- 6 M2 215,000.00 123 Geotekstil Non Woven ( 300 gr ) M2 38,000.00 124 Geotekstil M2 32,000.00 125 Gip Sum ( 120 x 240 cm ) Tebal 1.2 cm Lembar 132,000.00 126 Gipsum Australia ( 1,2 x 2,4 m ) T = 6 mm Lembar 70,000.00 127 Gipsum Australia ( 1,2 x 2,4 m ) T = 9 mm Lembar 97,000.00 128 Glas Block (15 x 15 cm) Buah 22,000.00 129 Gorong-gorong Aramco 1000 x 2 mm ₵ M' 2,200,000.00 130 Gorong-gorong Aramco 1500 x 2.5 mm ₵ M' 3,700,000.00 131 Gorong-gorong Aramco 1500 x 3.5 mm ₵ M' 5,200,000.00 132 Gravel 140,600.00 133 Grendel Jendela / Pintu Buah 14,000.00 134 Hak Angin Buah 11,200.00 135 Ijuk Kg 15,000.00 136 Interblock Warna Buah 3,800.00 137 Jendela Naco 5 mm (8 Sisir) Set 114,000.00 138 Kaca Bening Uk. 2 mm M2 82,500.00 139 Kaca Bening Uk. 3 mm M2 94,000.00 140 Kaca bening Uk. 5 mm M2 105,000.00 141 Kaca Cermin Wastafel Buah 189,000.00 142 Kaca Rayband Uk. 3 mm M2 105,000.00 143 Kaca Rayband Uk. 5 mm M2 130,000.00 144 Kaca Reyben 4 mm M2 135,000.00 145 Kanstin beton L = 50 cm M' 28,000.00 146 Kapur Batu Kg 6,500.00 147 Kapur Sirih Kg 6,500.00 148 Karpet 4 mm L 2 m Merek Nobel Buah 192,000.00 149 Karpu Asbes Gelombang Besar M' 90,000.00 150 Karpu Asbes Gelombang Kecil M' 76,000.00 151 Karpus Genteng Beton M' 57,000.00 152 Karpus Genteng Keramik M' 91,000.00 153 Kawat Ayam 3 mm M2 16,800.00 154 Kawat Beton Kg 21,000.00 155 Kawat Bronjong 0.4 mm Kg 25,200.00 156 Kawat Bronjong Dia. 3 mm Kg 25,200.00 157 Kawat Bronjong Dia. 4 mm Kg 25,200.00 158 Kawat Bronjong DIA. 5 mm Kg 25,200.00 159 Kawat Bronjong Pabrikan Uk. (2 x 1 x 0,5) Lembar 480,000.00

M3

Page 79: JUKNIS PERENCANAAN 2014

NO. URAIAN SATUAN HARGA (Rp)

160 Kawat Bronjong Pabrikan Uk. (2 x 1 x 1) Lembar 450,000.00 161 Kawat Bronjong Pabrikan Uk. (3 x 1 x 0,5) Lembar 450,000.00 162 Kawat Duri Kg 21,000.00 163 Kawat Harmonika M2 33,600.00 164 Kawat Nyamuk / Kasa Logam M2 21,000.00 165 Kawat Nyamuk / Kasa Plastik M2 11,200.00 166 Kayu Bakar 180,000.00 167 Kayu Bakau 10 cm Batang 51,000.00 168 Kayu Klas I (Merbo/Seumantok / Ulin / dll ) 7,000,000.00

169 Kayu Klas II ( Kamper / Kruing / dll ) 6,200,000.00

170 Kayu Klas III ( Borneo / dll ) 4,500,000.00

171 Kayu Klas IV ( Sengon / dll ) 4,000,000.00

172 Kayu Untuk Perancah 2,500,000.00 173 Keramik Dinding 20 x 20 cm M2 70,840.00 174 Keramik Roman M2 104,000.00 175 Keramik Sisik Kulit Juruk 20 x 20 cm M2 63,000.00 176 Keramk Uk. 30 x 30 cm M2 59,000.00 177 Keramik Uk. 40 x 40 cm M2 61,800.00 178 Kerikil Bersih 280,000.00

179 Kerikil Quary 106,000.00 180 Kerosen / Minyak Tanah ( Industri ) Liter 15,000.00 181 Kerosen / Minyak Tanah ( Subsidi ) Liter 4,100.00 182 Kertas Amplas Lembar 5,000.00 183 Kertas Pasir Lembar 2,800.00 184 Kloset Duduk Keramik Buah 532,000.00 185 Kloset Duduk KIA Buah 644,000.00 186 Kloset Jongkok Keramik Buah 156,000.00 187 Kloset Jongko KIA Buah 189,000.00 188 Kloset Jongkong Trassol Buah 91,000.00 189 Kran Merek Sun Ei Biasa Buah 175,000.00 190 Kunci Lesa Type 2328 Buah 133,000.00 191 Kunci lips Buah 91,000.00 192 Kunci Pintu Buah 84,000.00 193 Kunci Union 2 Slag Buah 107,000.00 194 Kunci Verro Asli Buah 560,000.00 195 Kuas Buah 7,865.00 196 Lampu Pijar 40 Watt Buah 7,000.00 197 Lampu TL 20 Watt Buah 14,000.00 198 Lampu TL 40 Watt Buah 21,000.00 199 Lat 1 x 2 Julotong Batang 67,200.00 200 Lat Asbes Batang 5,600.00 201 Lem Kayu (Aibon) Buah 35,000.00 202 Lempengan Rumput M2 30,000.00 203 List Eternit Kayu M' 7,000.00 204 Marmer M2 540,000.00 205 Marmer Lampung 10 x 20 x 0.7 cm M2 272,000.00 206 Marmer Lampung 10 x 30 x 0.7 cm M2 272,000.00 207 Marmer Lampung 10 x 30 x 1.8 cm M2 272,000.00 208 Marmer Lampung 15 x 30 x 0.7 cm M2 272,000.00 209 Marmer Lampung 15 x 30 x 1.8 cm M2 272,000.00 210 Marmer Lampung 20 x 20 x 1.8 cm M2 272,000.00 211 Marmer Lampung 20 x 30 x 0.7 cm M2 272,000.00 212 Marmer Lampung 20 x 30 x 1.8 cm M2 272,000.00 213 Marmer Lampung 20 x 40 x 1.8 cm M2 785,000.00 214 Marmer Lampung 30 x 30 x 1.8 cm M2 785,000.00

M3

M3

M3

M3

M3

M3

M3

M3

Page 80: JUKNIS PERENCANAAN 2014

NO. URAIAN SATUAN HARGA (Rp)

215 Marmer Lampung 30 x 40 x 1.8 cm M2 785,000.00 216 Marmer Lampung 30 x 50 x 1.8 cm M2 785,000.00 217 Marmer Lampung 30 x 60 x 1.8 cm M2 785,000.00 218 Marmer Lampung 40 x 40 x 1.8 cm M2 785,000.00 219 Marmer Lampung 40 x 50 x 1.8 cm M2 785,000.00 220 Marmer Lampung 40 x 60 x 1.8 cm M2 785,000.00 221 Marmer Lampung 5 x 15 x 0.7 cm M2 272,000.00 222 Minyak Aspal Liter 12,900.00 223 Minyak Bekisting Liter 12,000.00 224 Minyak Cat Liter 25,200.00 225 Minyak Pelumas Liter 46,000.00 226 Minyak Premium Liter 4,500.00 227 Minyak Rem Liter 26,000.00 228 Minyak Solar Liter 8,990.00 229 Mozaik Buah 17,457.00 230 Mozaik M2 138,000.00 231 Multipleks 3 mm Lembar 56,000.00 232 Multipleks 4 mm Lembar 70,000.00 233 Multipleks 6 mm Lembar 98,000.00 234 Multipleks 9 mm Lembar 151,200.00 235 Naco ( Kerangka + Daun ) M2 310,000.00 236 Nok / Rabung Seng 0.35 Cat Prabrik Lembar 35,000.00 237 Nok / Rabung Seng 0.35 tidak Dicat Lembar 28,000.00 238 Oksigen 356,000.00 239 Paku Asbes Kg 18,200.00 240 Paku Berbagai Jenis 0,5 mc;1,5 mc; 1 Inch Kg 16,800.00 241 Paku Beton Kotak 22,400.00 242 Paku Beton 8 Inch Kotak 28,000.00 243 Paku Cacing RRT Kg 21,000.00 244 Paku Jembatan Kg 24,000.00 245 Paku Kait Buah 1,500.00 246 Paku Kayu (2"-5") Kg 16,800.00 247 Paku Klem Kotak Kg 40,600.00 248 Paku Kotak RRT Kg 21,000.00 249 Paku Reng Kg 16,800.00 250 Paku Sekrup Kg 63,000.00 251 Paku Seng Kg 21,000.00 252 Paku Sumbat Buah 1,500.00 253 Paku Ulir Primadek Buah 3,000.00 254 Palu unit 49,000.00 255 Papan 1 x 12 x 4,5 Julotong Lembar 81,000.00 256 Papan 1 x 9 x 4,5 Julotong Lembar 67,000.00 257 Papan Lisplank Kayu Kelas II M2 88,000.00 258 Papan Lisplank Kayu Seumantok M2 150,000.00 259 Papan Merbo 1 1/2 x 12 x 16 Lembar 250,000.00 260 Papan merbo 1 1/2 x 9 x 16 Lembar 230,000.00 261 Pasir Batu ( Sirtu ) - Material Jalan 220,000.00

262 Pasir beton /Kerikil 280,000.00

263 Pasir Beton Bersih 180,000.00

264 Pasir Pasang 170,000.00

265 Pasir urug 123,000.00 266 Paving Block Buah 2,800.00 267 Pelumas / Oli Liter 38,000.00 268 Pipa Besi 1 inch Batang 154,000.00 269 Pipa Besi 1/2 inch Batang 105,000.00 270 Pipa Besi 2 inch Batang 350,000.00 271 Pipa Besi 3/4 inch Batang 119,000.00

M3

M3

M3

M3

M3

M3

Page 81: JUKNIS PERENCANAAN 2014

NO. URAIAN SATUAN HARGA (Rp)

272 Pipa GIP 2 Inch ₵ Batang 692,000.00 273 Pipa GIP 3 Inch ₵ Batang 1,420,000.00 274 Pipa GIP 4 Inch ₵ Batang 2,115,000.00 275 Pipa Leiding Ø 1/2 Inch Galvanis Tebal 3,2 mm Batang 90,000.00 276 Pipa Leiding Ø 1 1/2 Inch Galvanis Tebal 3,2 mm Batang 200,000.00 277 Pipa Leiding Ø 2 Inch Galvanis Tebal 3,2 mm Batang 300,000.00 278 Pipa Leiding Ø 3 Inch Galvanis Tebal 3,2 mm Batang 550,000.00 279 Pipa Leiding Ø 4 Inch Galvanis Tebal 3,2 mm Batang 750,000.00 280 Pipa Leiding Ø 6 Inch Galvanis Tebal 3,2 mm Batang 1,500,000.00 281 Pipa Leiding Ø 1 Inch Galvanis Tebal 3,2 mm Batang 130,000.00 282 Pipa PVC 1/2 Inch (Super Insar) ₵ Batang 21,000.00 283 Pipa PVC 2 Inch (Super Insar) ₵ Batang 98,000.00 284 Pipa PVC 3 Inch (Super Insar) ₵ Batang 140,000.00 285 Pipa PVC 3/4 Inch (Super Insar) ₵ Batang 40,600.00 286 Pipa PVC 4 Inch (Super Insar) ₵ Batang 287,000.00 287 Pipa PVC 6 Inch (Super Insar) ₵ Batang 574,000.00 288 Pipa PVC 8 Inch (Super Insar) ₵ Batang 812,000.00 289 Pipa PVC Ø 1 " Batang 49,000.00 290 Pipa PVC Ø 1/2 " Kualitas AWE (United) Batang 21,000.00 291 Pipa PVC Ø 1 1/2 " Batang 84,000.00 292 Pipa PVC Ø 2 " Batang 119,000.00 293 Pipa PVC Ø 3/4 " Batang 40,600.00 294 Pipa PVC Ø 3 " Batang 203,000.00 295 Pipa PVC Ø 4 " Batang 287,000.00 296 Plamur Tembok Kg 35,000.00 297 Plint Keramik 15 x 30 Buah 17,000.00 298 Plint Ubin Abu-abu 15 x 20 Buah 1,500.00 299 Plint Ubin Berwarna 15 x 20 Buah 6,000.00 300 Plint Ubin warna M2 86,969.00 301 Plin Ubin Teraso 10 x 30 Buah 7,500.00 302 Plint Ubin Teraso Buah 79,063.00 303 Plywood 12 mm Lembar 203,000.00 304 Plywood 4 mm Lembar 70,000.00 305 Plywood 6 mm Lembar 98,000.00 306 Plywood 9 mm Lembar 151,200.00 307 Polyplek 4 mm Lembar 114,800.00 308 Porselin 10 x 15 M2 140,000.00 309 Porselin 11 x 11 M2 140,000.00 310 Porselin 15 x 15 M2 140,000.00 311 Porselin 20 x 20 M2 140,000.00 312 Profil 2 x3 Batang 39,200.00 313 Pupuk Kandang M3 185,000.00 314 Rabung Genteng Merek Ekapana Gerard L = 1.2 m M' 38,700.00 315 Rabung Genteng Merek KIA (NOK S2) Warna Exclusive M' 36,500.00 316 Rabung Genteng Merek KIA (NOK S2) Warna khusus M' 36,500.00 317 Rabung Genteng Merek KIA (NOK S2) Warna Natural M' 36,500.00 317 Rabung Genteng Merek KIA (NOK S2) Warna Premium M' 36,500.00 306 Rabung Genteng Merek KIA (NOK S2) Warna Standar M' 36,500.00 307 Rabung Genteng Merek Super Steel M' 88,400.00 308 Rabung Seng Lembar 28,000.00 309 Rabung Seng Superdeck 8 Kaki Lembar 39,200.00 310 Residu Kg 7,000.00 311 Resesrvoir Air 0,5 m3 Fibre Buah 1,600,000.00 312 Resesrvoir Air 0,5 m3 Stainlees steel Buah 1,850,000.00 313 Resesrvoir Air 1 m3 Fibre Buah 2,400,000.00 314 Resesrvoir Air 1 m3 Stainlees Steel Buah 3,100,000.00 315 Schakelar Buah 24,000.00 316 Semen Andalas @ 40 Kg Zak 62,200.00 317 Semen Andalas (per kg) Kg 1,555.00 318 Semen Andalas @ 50 Kg Zak 77,750.00

Page 82: JUKNIS PERENCANAAN 2014

NO. URAIAN SATUAN HARGA (Rp)

319 Semen Putih @ 50 Kg Zak 140,000.00 320 Semen Warna @ 40 Kg Zak 197,656.00 321 Semen Warna per Kg Kg 4,941.40 322 Seng BJLS 0,20 M2 32,200.00 323 Seng BJLS 0,20 Cat Pabrik M2 53,200.00 324 Seng Gelombang BJLS 0,20 - 8" Lembar 72,800.00 325 Seng Gelombang BJLS 0,30 - 8" Lembar 95,200.00 326 Seng Gelombang BJLS 0,35 - 8" Lembar 106,400.00 327 Seng Gelombang BJLS 30 M2 48,500.00 328 Seng Gelombang BJLS 30 Cat Pabrik M2 66,500.00 329 Seng Plat BJLS 20 M2 33,600.00 330 Seng Plat BJLS 30 M2 49,000.00 331 Seng Superdeck 8 Kaki Lembar 128,800.00 332 Buah 14,500.00 333 Buah 16,300.00 334 Buah 9,500.00 335 Buah 66,000.00 336 Buah 9,000.00 337 Buah 71,400.00 338 Buah 11,200.00 339 Buah 15,400.00 340 Buah 4,200.00 341 Buah 5,600.00 342 Buah 2,800.00 343 Buah 4,200.00 344 Stop Kontak + Instalisi Titi 91,000.00 345 Tanah Humus M3 75,000.00 346 Tanah Ladang M3 70,000.00 347 Tanah Timbun M3 40,000.00 348 Tanah Timbun Pilihan - Material Jalan M3 123,200.00 349 Tanah Timbun Pilihan Tanah berbatu M3 67,000.00 350 Tanah Urug M3 80,500.00 351 Tang Buah 33,600.00 352 Tempat Memasak Aspal Buah 200,000.00 353 Tempat Sabun Merek KIA Buah 63,000.00 354 Tempat Sabun Merek Sun Ei Buah 245,500.00 355 Tempat Sikat Gigi Merek Sun Ei Buah 187,600.00 356 Teralis Besi M2 49,000.00 357 Timbunan Didatangkan dari Buket Rata utk Wil. I (Anls.BOW) M3 40,000.00 358 Timbunan Didatangkan dari Buket Rata utk Wil. II (Anls.BOW) M3 46,000.00 359 Timbunan Didatangkan dari Buket Rata utk Wil. III (Anls.BOW) M3 53,000.00 360 Tinner Liter 22,400.00 361 Titik Lampu + Instalasi Titik 140,000.00 362 Triplek Formika 4 m Lembar 105,500.00 363 Triplek 3 mm Lembar 63,250.00 364 Triplek 6 mm Lembar 88,550.00 365 Ubin Abu-abu 20 x 20 Buah 1,800.00 366 Ubin Abu-abu 20 x 20 M2 45,000.00 367 Ubin abu-abu 30 x 30 Buah 101,200.00 368 Ubin Berwarna 20 x 20 M2 45,000.00 369 Ubin Warna 30 x 30 Buah 51,750.00 370 Ubin Teraso 20 x 20 M2 45,000.00 371 Ubin Teraso 30 x 30 Buah 94,875.00 372 Ubin Wafel 20 x 20 M2 45,000.00 373 Urinoir Buah 1,103,000.00 374 Urinoir Keramik Buah 1,420,000.00 375 Urinoir Keramik Buah 1,100,000.00 376 Vernis Liter 50,400.00 377 Vinyl M2 195,000.00 378 Zekering (Kast Lokal 1 Zekering) Buah 135,000.00 379 Zekering (Kast Lokal 2 Zekering) Buah 165,000.00 380 Zekering (Kast Lokal 3 Zekering) Buah 23,000.00

Socket GIP Ø 1 InchSocket GIP Ø 1.5 InchSocket GIP Ø 1/2 InchSocket GIP Ø 3 InchSocket GIP Ø 3/4 InchSocket GIP Ø 4 InchSocket PVC Ø 3 InchSocket PVC Ø 4 InchSocket PVC Ø 1 InchSocket PVC Ø 1.5 InchSocket PVC Ø 1/2 InchSocket PVC Ø 3/4 Inch

Page 83: JUKNIS PERENCANAAN 2014

DAFTAR SEWA ALAT 3.00

NO. JENIS SATUAN HARGA (Rp)

1 Alat Penggetar Beton Jam 42,500.00 2 AMP 10 t/h (Asphalt Mixing Plant) Jam 655,500.00 3 Asphalt Finisher Jam 238,300.00 4 Bulldozer Jam 440,000.00 5 Dump Truck 5 Ton (Hino) Jam 120,100.00 6 Dump Truck 3.5 Ton Jam 85,100.00 7 Concrezt Mixer 0,25 M3 Jam 68,100.00 8 Compresosor 210 M3/Jam Jam 85,100.00 9 Exavator Back Hoe Jam 374,500.00

10 Generator Jam 85,100.00 11 Jackhammer, Wquitmant, etc Jam 187,200.00 12 Mesin Penyemprot Asphalt 1000 Liter Jam 85,100.00 13 Mesin Penyemprot Asphalt 4000 Liter Jam 102,100.00 14 Mesin Penyemprot Asphalt 350 Liter Jam 36,600.00 15 Motor Grader Jam 425,600.00 16 Mesin Gilas Bergetar 1 ton Jam 68,100.00 17 Mesin Gilas Bergetar 6-7 ton Jam 102,100.00 18 Mesin Gilas Roda Karet 8-10 ton Jam 102,100.00 19 Mesin Gilas Tandem (Bergetar) 6-10 ton Jam 187,200.00 20 Mesin Gilas Tandem 2,5 ton Jam 85,100.00 21 Pemecah Batu 30 t/j Jam 425,600.00 22 Pompa Air (0,50 mm) 30 M3 Jam 34,000.00 23 Peralatan Tractor, Dll Jam 144,000.00 24 Stumper Jam 47,600.00 25 Truck Tangki Air Jam 144,700.00 26 Truk Bak terbuka 3 ton Jam 68,100.00 27 Tractor Jam 204,300.00 28 Well Loader Jam 340,500.00

Page 84: JUKNIS PERENCANAAN 2014

1. Anl. SNI 2835-2008 6.1

Nomor Uraian Satuan KoefisienHarga Satuan Jumlah Harga

(Rp) (Rp)

ATENAGA

Pekerja OH 0.7500 60,000.00 45,000.00 Mandor OH 0.0250 75,000.00 1,875.00

B BAHAN - C PERALATAN -

Jumlah harga per satuan pekerjaan 46,875.00

2. Anl. SNI 2835-2008 6.1

Nomor Uraian Satuan KoefisienHarga Satuan Jumlah Harga

(Rp) (Rp)

ATENAGA

Pekerja OH 0.7500 60,000.00 45,000.00 Mandor OH 0.0250 75,000.00 1,875.00

B BAHAN - C PERALATAN -

Jumlah harga per satuan pekerjaan 46,875.00

: 1 M3 Galian Tanah Biasa Sedalam 1 Meter

: 1 M3 Galian Tanah Biasa Sedalam 2 Meter

Page 85: JUKNIS PERENCANAAN 2014

DAFTAR ANALISA

I. DAFTAR ANALISA PEKERJAAN TANAH

Anl. SNI 2835-2008 6.1

: Tenaga Kerja

0.750 OH Pekerja @ Rp. 70,000.00 Rp. 52,500.00

0.025 OH Mandor @ Rp. 80,000.00 Rp. 2,000.00

Jumlah Rp. 54,500.00

Dibulatkan Rp. 54,500.00

Anl. SNI 2835-2008 6.2

: Tenaga Kerja

0.900 OH Pekerja @ Rp. 70,000.00 Rp. 63,000.00

0.045 OH Mandor @ Rp. 80,000.00 Rp. 3,600.00

Jumlah Rp. 66,600.00

Dibulatkan Rp. 66,600.00

Anl. SNI 2835-2008 6.3

: Tenaga Kerja

1.050 OH Pekerja @ Rp. 70,000.00 Rp. 73,500.00

0.067 OH Mandor @ Rp. 80,000.00 Rp. 5,360.00

Jumlah Rp. 78,860.00

Dibulatkan Rp. 78,860.00

Anl. SNI 2835-2008 6.4

: Tenaga Kerja

1.000 OH Pekerja @ Rp. 70,000.00 Rp. 70,000.00

0.032 OH Mandor @ Rp. 80,000.00 Rp. 2,560.00

Jumlah Rp. 72,560.00

Dibulatkan Rp. 72,560.00

Anl. SNI 2835-2008 6.5

: Tenaga Kerja

1.500 OH Pekerja @ Rp. 70,000.00 Rp. 105,000.00

0.060 OH Mandor @ Rp. 80,000.00 Rp. 4,800.00

Jumlah Rp. 109,800.00

Dibulatkan Rp. 109,800.00

Anl. SNI 2835-2008 6.6

: Tenaga Kerja

1.200 OH Pekerja @ Rp. 70,000.00 Rp. 84,000.00

0.045 OH Mandor @ Rp. 80,000.00 Rp. 3,600.00

Jumlah Rp. 87,600.00

Dibulatkan Rp. 87,600.00

Anl. SNI 2835-2008 6.7

: Tenaga Kerja

0.050 OH Pekerja @ Rp. 70,000.00 Rp. 3,500.00

0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. 3,900.00

Dibulatkan Rp. 3,900.00

Anl. SNI 2835-2008 6.8

: Tenaga Kerja

0.330 OH Pekerja @ Rp. 70,000.00 Rp. 23,100.00

0.010 OH Mandor @ Rp. 80,000.00 Rp. 800.00

Jumlah Rp. 23,900.00

Dibulatkan Rp. 23,900.00

: 1 M3 Galian Tanah Biasa Sedalam 1 Meter

: 1 M3 Galian Tanah Biasa Sedalam 2 Meter

: 1 M3 Galian Tanah Biasa Sedalam 3 Meter

: 1 M3 Galian Tanah Keras Sedalam 1 Meter

: 1 M3 Galian Tanah Cadas Sedalam 1 Meter

: 1 M3 Galian Tanah Lumpur Sedalam 1 Meter

: 1 M3 Stripping Tebing Setinggi 1 Meter

: 1 M3 Membuang Tanah Sejauh 15 Meter

Page 86: JUKNIS PERENCANAAN 2014

Anl. SNI 2835-2008 6.9

: Tenaga Kerja

0.250 OH Pekerja @ Rp. 70,000.00 Rp. 17,500.00

0.008 OH Mandor @ Rp. 80,000.00 Rp. 640.00

Jumlah Rp. 18,140.00

Dibulatkan Rp. 18,140.00

Anl. SNI 2835-2008 6.10

: Tenaga Kerja

0.500 OH Pekerja @ Rp. 70,000.00 Rp. 35,000.00

0.050 OH Mandor @ Rp. 80,000.00 Rp. 4,000.00

Jumlah Rp. 39,000.00

Dibulatkan Rp. 39,000.00

Anl. SNI 2835-2008 6.11

: Bahan

1.200 M3 Pasir urug @ Rp. 130,000.00 Rp. 156,000.00

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.010 OH Mandor @ Rp. 80,000.00 Rp. 800.00

Jumlah Rp. 177,800.00

Dibulatkan Rp. 177,800.00

Anl. SNI 2835-2008 6.11a

: Bahan

1.200 OH Tanah Urug @ Rp. #N/A Rp. #N/A

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.010 OH Mandor @ Rp. 80,000.00 Rp. 800.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 2835-2008 6.14

: Bahan

6.000 Kg Ijuk @ Rp. 32,500.00 Rp. 195,000.00

: Tenaga Kerja

0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 206,700.00

Dibulatkan Rp. 206,700.00

: 1 M3 Urugan Kembali Galian

: 1 M3 Memadatkan Tanah (per 20 cm)

: 1 M3 Mengurug Pasir Urug

: 1 M3 Mengurug Tanah Urug

: 1 M2 Memasang Lapisan Ijuk Tebal 10 cm, Untuk Bidang Resapan

Page 87: JUKNIS PERENCANAAN 2014

II. DAFTAR ANALISA PEKERJAAN PONDASI

Anl. SNI 2836-2008 6.1

: Bahan

1.200 M3 Batu Kali @ Rp. 260,000.00 Rp. 312,000.00

202.000 Kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 321,685.00

0.485 M3 Pasir Pasang @ Rp. 180,000.00 Rp. 87,300.00

: Tenaga Kerja

1.500 OH Pekerja @ Rp. 70,000.00 Rp. 105,000.00

0.750 OH Tukang Batu @ Rp. 80,000.00 Rp. 60,000.00

0.075 OH Kepala Tukang @ Rp. 100,000.00 Rp. 7,500.00

0.075 OH Mandor @ Rp. 80,000.00 Rp. 6,000.00

Jumlah Rp. 899,485.00

Dibulatkan Rp. 899,485.00

Anl. SNI 2836-2008 6.2

: Bahan

1.200 m3 Batu Kali @ Rp. 260,000.00 Rp. 312,000.00

163.000 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 259,577.50

0.520 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 93,600.00

: Tenaga Kerja

1.500 OH Pekerja @ Rp. 70,000.00 Rp. 105,000.00

0.750 OH Tukang Batu @ Rp. 80,000.00 Rp. 60,000.00

0.075 OH Kepala Tukang @ Rp. 100,000.00 Rp. 7,500.00

0.075 OH Mandor @ Rp. 80,000.00 Rp. 6,000.00

Jumlah Rp. 843,677.50

Dibulatkan Rp. 843,677.00

Anl. SNI 2836-2008 6.3

: Bahan

1.200 m3 Batu Kali @ Rp. 260,000.00 Rp. 312,000.00

136.000 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 216,580.00

0.540 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 97,200.00

: Tenaga Kerja

1.500 OH Pekerja @ Rp. 70,000.00 Rp. 105,000.00

0.750 OH Tukang Batu @ Rp. 80,000.00 Rp. 60,000.00

0.075 OH Kepala Tukang @ Rp. 100,000.00 Rp. 7,500.00

0.075 OH Mandor @ Rp. 80,000.00 Rp. 6,000.00

Jumlah Rp. 804,280.00

Dibulatkan Rp. 804,280.00

Anl. SNI 2836-2008 6.4

: Bahan

1.200 m3 Batu Kali @ Rp. 260,000.00 Rp. 312,000.00

117.000 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 186,322.50

0.561 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 100,980.00

: Tenaga Kerja

1.500 OH Pekerja @ Rp. 70,000.00 Rp. 105,000.00

0.750 OH Tukang Batu @ Rp. 80,000.00 Rp. 60,000.00

0.075 OH Kepala Tukang @ Rp. 100,000.00 Rp. 7,500.00

0.075 OH Mandor @ Rp. 80,000.00 Rp. 6,000.00

Jumlah Rp. 777,802.50

Dibulatkan Rp. 777,802.00

Anl. SNI 2836-2008 6.5

: Bahan

1.200 m3 Batu Kali @ Rp. 260,000.00 Rp. 312,000.00

91.000 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 144,917.50

0.584 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 105,120.00

: 1 M3 Memasang Pondasi Batu Kali, Campuran 1 PC : 3 PP

: 1 M3 Memasang Pondasi Batu Kali, Campuran 1 PC : 4 PP

: 1 M3 Memasang Pondasi Batu Kali, Campuran 1 PC : 5 PP

: 1 M3 Memasang Pondasi Batu Kali, Campuran 1 PC : 6 PP

: 1 M3 Memasang Pondasi Batu Kali, Campuran 1 PC : 8 PP

Page 88: JUKNIS PERENCANAAN 2014

: Tenaga Kerja

1.500 OH Pekerja @ Rp. 70,000.00 Rp. 105,000.00

0.750 OH Tukang Batu @ Rp. 80,000.00 Rp. 60,000.00

0.075 OH Kepala Tukang @ Rp. 100,000.00 Rp. 7,500.00

0.075 OH Mandor @ Rp. 80,000.00 Rp. 6,000.00

Jumlah Rp. 740,537.50

Dibulatkan Rp. 740,537.00

Anl. SNI 2836-2008 6.9

: Bahan

1.200 m3 Batu Kali @ Rp. 260,000.00 Rp. 312,000.00

0.432 m3 Pasir urug @ Rp. 130,000.00 Rp. 56,160.00

: Tenaga Kerja

0.780 OH Pekerja @ Rp. 70,000.00 Rp. 54,600.00

0.390 OH Tukang Batu @ Rp. 80,000.00 Rp. 31,200.00

0.039 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,900.00

0.039 OH Mandor @ Rp. 80,000.00 Rp. 3,120.00

Jumlah Rp. 457,860.00

Dibulatkan Rp. 457,860.00

Anl. SNI 2836-2008 6.10

: Bahan

0.480 m3 Batu Kali @ Rp. 260,000.00 Rp. 124,800.00

194.000 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 308,945.00

0.312 m3 Pasir beton /Kerikil @ Rp. #N/A Rp. #N/A

0.468 m3 Kerikil Bersih @ Rp. 220,000.00 Rp. 102,960.00

126.000 kg Besi Beton Polos @ Rp. 12,000.00 Rp. 1,512,000.00

1.800 kg Kawat Beton @ Rp. 19,500.00 Rp. 35,100.00

: Tenaga Kerja

3.400 OH Pekerja @ Rp. 70,000.00 Rp. 238,000.00

0.850 OH Tukang Batu @ Rp. 80,000.00 Rp. 68,000.00

0.085 OH Kepala Tukang @ Rp. 100,000.00 Rp. 8,500.00

0.170 OH Mandor @ Rp. 80,000.00 Rp. 13,600.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 2836-2008 6.10a : 1 M3 Memasang Pondasi Siklop, 60% Beton Campuran 1 PC : 2 PB : 3 KR dan 40% Batu Kali

: Bahan

0.480 m3 Batu Kali @ Rp. 260,000.00 Rp. 124,800.00

194.000 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 308,945.00

0.312 m3 Pasir Beton Bersih @ Rp. 190,000.00 Rp. 59,280.00

0.468 m3 Pasir beton /Kerikil @ Rp. #N/A Rp. #N/A

: Tenaga Kerja

3.400 OH Pekerja @ Rp. 70,000.00 Rp. 238,000.00

0.850 OH Tukang Batu @ Rp. 80,000.00 Rp. 68,000.00

0.085 OH Kepala Tukang @ Rp. 100,000.00 Rp. 8,500.00

0.170 OH Mandor @ Rp. 80,000.00 Rp. 13,600.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 2836-2008 6.11

: Bahan

0.450 m3 Batu Kali @ Rp. 260,000.00 Rp. 117,000.00

194.000 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 308,945.00

0.312 m3 Pasir Beton Bersih @ Rp. 190,000.00 Rp. 59,280.00

0.468 m3 Kerikil Bersih @ Rp. 220,000.00 Rp. 102,960.00

: Tenaga Kerja

2.400 OH Pekerja @ Rp. 70,000.00 Rp. 168,000.00

0.800 OH Tukang Batu @ Rp. 80,000.00 Rp. 64,000.00

0.080 OH Kepala Tukang @ Rp. 100,000.00 Rp. 8,000.00

0.119 OH Mandor @ Rp. 80,000.00 Rp. 9,520.00

Jumlah Rp. 837,705.00

Dibulatkan Rp. 837,705.00

: 1 M3 Memasang Batu Kosong (anstamping)

: 1 M3 Memasang Pondasi Siklop, 60% Beton Campuran 1 PC : 2 PB : 3 KR dan 40% Batu Kali

: 1 M3 Memasang Pondasi Sumuran, Diameter 100 cm

Page 89: JUKNIS PERENCANAAN 2014

III. DAFTAR ANALISA PEKERJAAN PLESTERAN UNTUK KONSTRUKSI BANGUNAN GEDUNG PERUMAHAN

Anl. SNI 2837-2008 6.1 : 1 M2 Membuat Plesteran 1 PC : 1 PP, Tebal 15 mm

: Bahan

15.504 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 24,690.12

0.016 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 2,880.00

: Tenaga Kerja

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00

0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 63,270.12

Dibulatkan Rp. 63,270.00

Anl. SNI 2837-2008 6.2 : 1 M2 Membuat Plesteran 1 PC : 2 PP, Tebal 15 mm

: Bahan

10.224 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 16,281.72

0.020 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 3,600.00

: Tenaga Kerja

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00

0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 55,581.72

Dibulatkan Rp. 55,581.00

Anl. SNI 2837-2008 6.3 : 1 M2 Membuat Plesteran 1 PC : 3 PP, Tebal 15 mm

: Bahan

7.776 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 12,383.28

0.023 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 4,140.00

: Tenaga Kerja

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00

0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 52,223.28

Dibulatkan Rp. 52,223.00

Anl. SNI 2837-2008 6.4 : 1 M2 Membuat Plesteran 1 PC : 4 PP, Tebal 15 mm

: Bahan

6.240 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 9,937.20

0.024 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 4,320.00

: Tenaga Kerja

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00

0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 49,957.20

Dibulatkan Rp. 49,957.00

Anl. SNI 2837-2008 6.5 : 1 M2 Membuat Plesteran 1 PC : 5 PP, Tebal 15 mm

: Bahan

5.184 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 8,255.52

Page 90: JUKNIS PERENCANAAN 2014

0.026 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 4,680.00

: Tenaga Kerja

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00

0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 48,635.52

Dibulatkan Rp. 48,635.00

Anl. SNI 2837-2008 6.6 : 1 M2 Membuat Plesteran 1 PC : 6 PP, Tebal 15 mm

: Bahan

4.416 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 7,032.48

0.027 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 4,860.00

: Tenaga Kerja

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00

0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 47,592.48

Dibulatkan Rp. 47,592.00

Anl. SNI 2837-2008 6.7 : 1 M2 Membuat Plesteran 1 PC : 7 PP, Tebal 15 mm

: Bahan

3.936 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 6,268.08

0.028 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 5,040.00

: Tenaga Kerja

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00

0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 47,008.08

Dibulatkan Rp. 47,008.00

Anl. SNI 2837-2008 6.8 : 1 M2 Membuat Plesteran 1 PC : 8 PP, Tebal 15 mm

: Bahan

3.456 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 5,503.68

0.029 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 5,220.00

: Tenaga Kerja

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00

0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 46,423.68

Dibulatkan Rp. 46,423.00

Anl. SNI 2837-2008 6.13 : 1 M2 Membuat Plesteran 1 PC : 2 PP, Tebal 20 mm

: Bahan

13.632 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 21,708.96

0.027 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 4,860.00

: Tenaga Kerja

0.400 OH Pekerja @ Rp. 70,000.00 Rp. 28,000.00

0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00

0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00

0.022 OH Mandor @ Rp. 80,000.00 Rp. 1,760.00

Jumlah Rp. 74,328.96

Dibulatkan Rp. 74,328.00

Anl. SNI 2837-2008 6.14 : 1 M2 Membuat Plesteran 1 PC : 3 PP, Tebal 20 mm

: Bahan

Page 91: JUKNIS PERENCANAAN 2014

10.368 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 16,511.04

0.031 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 5,580.00

: Tenaga Kerja

0.260 OH Pekerja @ Rp. 70,000.00 Rp. 18,200.00

0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00

0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00

0.013 OH Mandor @ Rp. 80,000.00 Rp. 1,040.00

Jumlah Rp. 59,331.04

Dibulatkan Rp. 59,331.00

Anl. SNI 2837-2008 6.15 : 1 M2 Membuat Plesteran 1 PC : 4 PP, Tebal 20 mm

: Bahan

8.320 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 13,249.60

0.032 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 5,760.00

: Tenaga Kerja

0.400 OH Pekerja @ Rp. 70,000.00 Rp. 28,000.00

0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00

0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00

0.022 OH Mandor @ Rp. 80,000.00 Rp. 1,760.00

Jumlah Rp. 66,769.60

Dibulatkan Rp. 66,769.00

Anl. SNI 2837-2008 6.16 : 1 M2 Membuat Plesteran 1 PC : 5 PP, Tebal 20 mm

: Bahan

6.912 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 11,007.36

0.035 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 6,300.00

: Tenaga Kerja

0.400 OH Pekerja @ Rp. 70,000.00 Rp. 28,000.00

0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00

0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00

0.022 OH Mandor @ Rp. 80,000.00 Rp. 1,760.00

Jumlah Rp. 65,067.36

Dibulatkan Rp. 65,067.00

Anl. SNI 2837-2008 6.17 : 1 M2 Membuat Plesteran 1 PC : 6 PP, Tebal 20 mm

: Bahan

5.888 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 9,376.64

0.036 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 6,480.00

: Tenaga Kerja

0.400 OH Pekerja @ Rp. 70,000.00 Rp. 28,000.00

0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00

0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00

0.022 OH Mandor @ Rp. 80,000.00 Rp. 1,760.00

Jumlah Rp. 63,616.64

Dibulatkan Rp. 63,616.00

Anl. SNI 2837-2008 6.19 : 1 M2 Membuat Berapen 1 PC : 5 PP, Tebal 15 mm

: Bahan

5.184 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 8,255.52

0.026 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 4,680.00

: Tenaga Kerja

0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00

0.075 OH Tukang Batu @ Rp. 80,000.00 Rp. 6,000.00

0.008 OH Kepala Tukang @ Rp. 100,000.00 Rp. 800.00

0.008 OH Mandor @ Rp. 80,000.00 Rp. 640.00

Jumlah Rp. 30,875.52

Dibulatkan Rp. 30,875.00

Page 92: JUKNIS PERENCANAAN 2014

Anl. SNI 2837-2008 6.20 : 1 M2 Membuat Plesteran Skoning Lebar 10 mm 1 PC : 2 PP

: Bahan

0.500 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 796.25

0.013 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 2,340.00

: Tenaga Kerja

0.080 OH Pekerja @ Rp. 70,000.00 Rp. 5,600.00

0.400 OH Tukang Batu @ Rp. 80,000.00 Rp. 32,000.00

0.040 OH Kepala Tukang @ Rp. 100,000.00 Rp. 4,000.00

0.004 OH Mandor @ Rp. 80,000.00 Rp. 320.00

Jumlah Rp. 45,056.25

Dibulatkan Rp. 45,056.00

Anl. SNI 2837-2008 6.23 : 1 M2 Membuat Plesteran Ciprat/Kamprotan 1 PC : 2 PP

: Bahan

4.320 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 6,879.60

0.006 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 1,080.00

: Tenaga Kerja

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.100 OH Tukang Batu @ Rp. 80,000.00 Rp. 8,000.00

0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 39,159.60

Dibulatkan Rp. 39,159.00

Anl. SNI 2837-2008 6.24 : 1 M2 Membuat Finishing Siar Pasangan Dinding Bata Merah (=20 m')

: Bahan

3.108 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 4,949.49

: Tenaga Kerja

0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00

0.075 OH Tukang Batu @ Rp. 80,000.00 Rp. 6,000.00

0.008 OH Kepala Tukang @ Rp. 100,000.00 Rp. 800.00

0.008 OH Mandor @ Rp. 80,000.00 Rp. 640.00

Jumlah Rp. 22,889.49

Dibulatkan Rp. 22,889.00

Anl. SNI 2837-2008 6.25 : 1 M2 Membuat Finishing Siar Pasangan Dinding Cobblock Ekpose (=8 m')

: Bahan

1.600 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 2,548.00

: Tenaga Kerja

0.070 OH Pekerja @ Rp. 70,000.00 Rp. 4,900.00

0.035 OH Tukang Batu @ Rp. 80,000.00 Rp. 2,800.00

0.004 OH Kepala Tukang @ Rp. 100,000.00 Rp. 400.00

0.004 OH Mandor @ Rp. 80,000.00 Rp. 320.00

Jumlah Rp. 10,968.00

Dibulatkan Rp. 10,968.00

Anl. SNI 2837-2008 6.26 : 1 M2 Membuat Finishing Siar Pasangan Batu Kali Adukan 1 PC : 2 PP

: Bahan

6.340 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 10,096.45

0.012 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 2,160.00

: Tenaga Kerja

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.150 OH Tukang Batu @ Rp. 80,000.00 Rp. 12,000.00

0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 45,796.45

Page 93: JUKNIS PERENCANAAN 2014

Dibulatkan Rp. 45,796.00

Anl. SNI 2837-2008 6.27 : 1 M2 Membuat Acian

: Bahan

3.250 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 5,175.63

: Tenaga Kerja

0.200 OH Pekerja @ Rp. 70,000.00 Rp. 14,000.00

0.100 OH Tukang Batu @ Rp. 80,000.00 Rp. 8,000.00

0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00

0.010 OH Mandor @ Rp. 80,000.00 Rp. 800.00

Jumlah Rp. 28,975.63

Dibulatkan Rp. 28,975.00

IV. DAFTAR ANALISA PEKERJAAN PLAFON DAN KAYU

Anl. SNI 2839-2008 6.5 : 1 M2 Memasang Langit-Langit Triplek Ukuran (120 x 240) cm, tebal 3 mm

: Bahan

0.375 Lembar Multipleks 3 mm @ Rp. 58,500.00 Rp. 21,937.50

0.030 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 510.00

: Tenaga Kerja

0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00

0.100 OH Tukang Kayu @ Rp. 80,000.00 Rp. 8,000.00

0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00

0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. 38,847.50

Dibulatkan Rp. 38,847.00

Anl. SNI 2839-2008 6.5b : 1 M2 Memasang Langit-Langit Triplek Ukuran (120 x 240) cm, tebal 6 mm

: Bahan

0.375 Lembar Multipleks 6 mm @ Rp. 97,500.00 Rp. 36,562.50

0.030 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 510.00

: Tenaga Kerja

0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00

0.100 OH Tukang Kayu @ Rp. 80,000.00 Rp. 8,000.00

0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00

0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. 53,472.50

Dibulatkan Rp. 53,472.00

Anl. SNI 2839-2008 6.6 : 1 M2 Memasang Langit-Langit Lambriziring Kayu, Tebal 9 mm

: Bahan

0.015 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll.) @ Rp. 10,400,000.00 Rp. 156,000.00

0.010 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 170.00

: Tenaga Kerja

0.800 OH Pekerja @ Rp. 70,000.00 Rp. 56,000.00

0.800 OH Tukang Kayu @ Rp. 80,000.00 Rp. 64,000.00

0.080 OH Kepala Tukang @ Rp. 100,000.00 Rp. 8,000.00

0.040 OH Mandor @ Rp. 80,000.00 Rp. 3,200.00

Jumlah Rp. 287,370.00

Dibulatkan Rp. 287,370.00

Anl. SNI 2839-2008 6.10 : 1 M2 Memasang Langit-Langit Kayu Profil

: Bahan

1.050 m' List Eternit Kayu @ Rp. 7,000.00 Rp. 7,350.00

Page 94: JUKNIS PERENCANAAN 2014

0.010 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 170.00

: Tenaga Kerja

0.050 OH Pekerja @ Rp. 70,000.00 Rp. 3,500.00

0.050 OH Tukang Kayu @ Rp. 80,000.00 Rp. 4,000.00

0.005 OH Kepala Tukang @ Rp. 100,000.00 Rp. 500.00

0.003 OH Mandor @ Rp. 80,000.00 Rp. 240.00

Jumlah Rp. 15,760.00

Dibulatkan Rp. 15,760.00

Anl. SNI 3434-2008 6.1 : 1 M2 Membuat dan Memasang Kusen Pintu dan Kusen Jendela, Kayu Kelas I

: Bahan

1.100 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll.) @ Rp. 10,400,000.00 Rp. 11,440,000.00

1.250 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 21,250.00

1.000 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 32,500.00

: Tenaga Kerja

7.000 OH Pekerja @ Rp. 70,000.00 Rp. 490,000.00

21.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 1,680,000.00

2.100 OH Kepala Tukang @ Rp. 100,000.00 Rp. 210,000.00

0.350 OH Mandor @ Rp. 80,000.00 Rp. 28,000.00

Jumlah Rp. 13,901,750.00

Dibulatkan Rp. 13,901,750.00

Anl. SNI 3434-2008 6.2 : 1 M2 Membuat dan Memasang Kusen Pintu dan Kusen Jendela, Kayu Kelas II

: Bahan

1.200 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 9,360,000.00

1.250 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 21,250.00

1.000 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 32,500.00

: Tenaga Kerja

6.000 OH Pekerja @ Rp. 70,000.00 Rp. 420,000.00

18.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 1,440,000.00

1.800 OH Kepala Tukang @ Rp. 100,000.00 Rp. 180,000.00

0.300 OH Mandor @ Rp. 80,000.00 Rp. 24,000.00

Jumlah Rp. 11,477,750.00

Dibulatkan Rp. 11,477,750.00

Anl. SNI 3434-2008 6.3 : 1 M2 Membuat dan Memasang Pintu Klam Standar, Kayu Kelas II

: Bahan

0.040 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 312,000.00

0.050 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 850.00

: Tenaga Kerja

0.350 OH Pekerja @ Rp. 70,000.00 Rp. 24,500.00

1.050 OH Tukang Kayu @ Rp. 80,000.00 Rp. 84,000.00

0.105 OH Kepala Tukang @ Rp. 100,000.00 Rp. 10,500.00

0.018 OH Mandor @ Rp. 80,000.00 Rp. 1,440.00

Jumlah Rp. 433,290.00

Dibulatkan Rp. 433,290.00

Anl. SNI 3434-2008 6.4 : 1 M2 Membuat dan Memasang Pintu Klam Sederhana, Kayu Kelas III Untuk Gudang Sementara

: Bahan

0.040 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 208,000.00

0.050 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 850.00

: Tenaga Kerja

0.350 OH Pekerja @ Rp. 70,000.00 Rp. 24,500.00

1.050 OH Tukang Kayu @ Rp. 80,000.00 Rp. 84,000.00

0.105 OH Kepala Tukang @ Rp. 100,000.00 Rp. 10,500.00

0.018 OH Mandor @ Rp. 80,000.00 Rp. 1,440.00

Jumlah Rp. 329,290.00

Dibulatkan Rp. 329,290.00

Anl. SNI 3434-2008 6.5 : 1 M2 Membuat dan Memasang Daun Pintu Panel, Kayu Kelas I

Page 95: JUKNIS PERENCANAAN 2014

: Bahan

0.040 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll.) @ Rp. 10,400,000.00 Rp. 416,000.00

0.500 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 16,250.00

: Tenaga Kerja

1.000 OH Pekerja @ Rp. 70,000.00 Rp. 70,000.00

3.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 240,000.00

0.300 OH Kepala Tukang @ Rp. 100,000.00 Rp. 30,000.00

0.050 OH Mandor @ Rp. 80,000.00 Rp. 4,000.00

Jumlah Rp. 776,250.00

Dibulatkan Rp. 776,250.00

Anl. SNI 3434-2008 6.5a : 1 M2 Membuat dan Memasang Daun Pintu Panel, Kayu Kelas II

: Bahan

0.040 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 312,000.00

0.500 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 16,250.00

: Tenaga Kerja

1.000 OH Pekerja @ Rp. 70,000.00 Rp. 70,000.00

3.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 240,000.00

0.300 OH Kepala Tukang @ Rp. 100,000.00 Rp. 30,000.00

0.050 OH Mandor @ Rp. 80,000.00 Rp. 4,000.00

Jumlah Rp. 672,250.00

Dibulatkan Rp. 672,250.00

Anl. SNI 3434-2008 6.6 : 1 M2 Membuat dan Memasang Pintu dan Jendela Kaca, Kayu Kelas I

: Bahan

0.024 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll.) @ Rp. 10,400,000.00 Rp. 249,600.00

0.300 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 9,750.00

: Tenaga Kerja

0.800 OH Pekerja @ Rp. 70,000.00 Rp. 56,000.00

2.400 OH Tukang Kayu @ Rp. 80,000.00 Rp. 192,000.00

0.240 OH Kepala Tukang @ Rp. 100,000.00 Rp. 24,000.00

0.040 OH Mandor @ Rp. 80,000.00 Rp. 3,200.00

Jumlah Rp. 534,550.00

Dibulatkan Rp. 534,550.00

Anl. SNI 3434-2008 6.6a : 1 M2 Membuat dan Memasang Pintu dan Jendela Kaca, Kayu Kelas II

: Bahan

0.024 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 187,200.00

0.300 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 9,750.00

: Tenaga Kerja

0.800 OH Pekerja @ Rp. 70,000.00 Rp. 56,000.00

2.400 OH Tukang Kayu @ Rp. 80,000.00 Rp. 192,000.00

0.240 OH Kepala Tukang @ Rp. 100,000.00 Rp. 24,000.00

0.040 OH Mandor @ Rp. 80,000.00 Rp. 3,200.00

Jumlah Rp. 472,150.00

Dibulatkan Rp. 472,150.00

Anl. SNI 3434-2008 6.7 : 1 M2 Membuat dan Memasang Pintu dan Jendela Jalusi, Kayu Kelas I

: Bahan

0.064 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll.) @ Rp. 10,400,000.00 Rp. 665,600.00

0.500 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 16,250.00

: Tenaga Kerja

1.000 OH Pekerja @ Rp. 70,000.00 Rp. 70,000.00

3.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 240,000.00

0.300 OH Kepala Tukang @ Rp. 100,000.00 Rp. 30,000.00

0.050 OH Mandor @ Rp. 80,000.00 Rp. 4,000.00

Jumlah Rp. 1,025,850.00

Dibulatkan Rp. 1,025,850.00

Page 96: JUKNIS PERENCANAAN 2014

Anl. SNI 3434-2008 6.7a : 1 M2 Membuat dan Memasang Pintu dan Jendela Jalusi, Kayu Kelas II

: Bahan

0.064 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 499,200.00

0.500 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 16,250.00

: Tenaga Kerja

1.000 OH Pekerja @ Rp. 70,000.00 Rp. 70,000.00

3.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 240,000.00

0.300 OH Kepala Tukang @ Rp. 100,000.00 Rp. 30,000.00

0.050 OH Mandor @ Rp. 80,000.00 Rp. 4,000.00

Jumlah Rp. 859,450.00

Dibulatkan Rp. 859,450.00

Anl. SNI 3434-2008 6.8 : 1 M2 Membuat Daun Pintu Kayu Lapis (Plywood) Rangkap, Rangka Tertutup Kayu Kelas II (Lebar Sampai 90 cm)

: Bahan

0.025 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 195,000.00

0.030 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 510.00

0.500 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 16,250.00

1.000 lembar Multipleks 4 mm @ Rp. 71,500.00 Rp. 71,500.00

: Tenaga Kerja

0.700 OH Pekerja @ Rp. 70,000.00 Rp. 49,000.00

2.100 OH Tukang Kayu @ Rp. 80,000.00 Rp. 168,000.00

0.210 OH Kepala Tukang @ Rp. 100,000.00 Rp. 21,000.00

0.035 OH Mandor @ Rp. 80,000.00 Rp. 2,800.00

Jumlah Rp. 524,060.00

Dibulatkan Rp. 524,060.00

Anl. SNI 3434-2008 6.9 : 1 M2 Membuat Pintu Plywood Rangkap, Rangka Expose Kayu Kelas I

: Bahan

0.250 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll.) @ Rp. 10,400,000.00 Rp. 2,600,000.00

0.030 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 510.00

0.500 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 16,250.00

1.000 lembar Multipleks 4 mm @ Rp. 71,500.00 Rp. 71,500.00

: Tenaga Kerja

0.800 OH Pekerja @ Rp. 70,000.00 Rp. 56,000.00

2.400 OH Tukang Kayu @ Rp. 80,000.00 Rp. 192,000.00

0.240 OH Kepala Tukang @ Rp. 100,000.00 Rp. 24,000.00

0.040 OH Mandor @ Rp. 80,000.00 Rp. 3,200.00

Jumlah Rp. 2,963,460.00

Dibulatkan Rp. 2,963,460.00

Anl. SNI 3434-2008 6.9a : 1 M2 Membuat Pintu Plywood Rangkap, Rangka Expose Kayu Kelas II

: Bahan

0.250 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 1,950,000.00

0.030 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 510.00

0.500 kg Lem Kayu (Aibon) @ Rp. 32,500.00 Rp. 16,250.00

1.000 lembar Multipleks 4 mm @ Rp. 71,500.00 Rp. 71,500.00

: Tenaga Kerja

0.800 OH Pekerja @ Rp. 70,000.00 Rp. 56,000.00

2.400 OH Tukang Kayu @ Rp. 80,000.00 Rp. 192,000.00

0.240 OH Kepala Tukang @ Rp. 100,000.00 Rp. 24,000.00

0.040 OH Mandor @ Rp. 80,000.00 Rp. 3,200.00

Jumlah Rp. 2,313,460.00

Dibulatkan Rp. 2,313,460.00

Anl. SNI 3434-2008 6.10 : 1 M2 Memasang Jalusi Kusen, Kayu Kelas I

: Bahan

0.060 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll.) @ Rp. 10,400,000.00 Rp. 624,000.00

0.150 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 2,550.00

Page 97: JUKNIS PERENCANAAN 2014

: Tenaga Kerja

0.670 OH Pekerja @ Rp. 70,000.00 Rp. 46,900.00

2.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 160,000.00

0.200 OH Kepala Tukang @ Rp. 100,000.00 Rp. 20,000.00

0.335 OH Mandor @ Rp. 80,000.00 Rp. 26,800.00

Jumlah Rp. 880,250.00

Dibulatkan Rp. 880,250.00

Anl. SNI 3434-2008 6.10a : 1 M2 Memasang Jalusi Kusen, Kayu Kelas II

: Bahan

0.060 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 468,000.00

0.150 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 2,550.00

: Tenaga Kerja

0.670 OH Pekerja @ Rp. 70,000.00 Rp. 46,900.00

2.000 OH Tukang Kayu @ Rp. 80,000.00 Rp. 160,000.00

0.200 OH Kepala Tukang @ Rp. 100,000.00 Rp. 20,000.00

0.335 OH Mandor @ Rp. 80,000.00 Rp. 26,800.00

Jumlah Rp. 724,250.00

Dibulatkan Rp. 724,250.00

Anl. SNI 3434-2008 6.19 : 1 M2 Memasang Rangka Langit-Langit (50 x 100) cm, Kayu Kelas II

: Bahan

0.015 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 117,000.00

0.200 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 3,400.00

: Tenaga Kerja

0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00

0.300 OH Tukang Kayu @ Rp. 80,000.00 Rp. 24,000.00

0.030 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,000.00

0.075 OH Mandor @ Rp. 80,000.00 Rp. 6,000.00

Jumlah Rp. 163,900.00

Dibulatkan Rp. 163,900.00

Anl. SNI 3434-2008 6.21 : 1 M1 Memasang Lisplank Ukuran (3 x 20) cm, Kayu Kelas I

: Bahan

0.0108 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll.) @ Rp. 10,400,000.00 Rp. 112,320.00

0.100 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 1,700.00

: Tenaga Kerja

0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00

0.200 OH Tukang Kayu @ Rp. 80,000.00 Rp. 16,000.00

0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00

0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. 139,420.00

Dibulatkan Rp. 139,420.00

Anl. SNI 3434-2008 6.21a : 1 M1 Memasang Lisplank Ukuran (3 x 20) cm, Kayu Kelas II

: Bahan

0.0108 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 84,240.00

0.100 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 1,700.00

: Tenaga Kerja

0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00

0.200 OH Tukang Kayu @ Rp. 80,000.00 Rp. 16,000.00

0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00

0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. 111,340.00

Dibulatkan Rp. 111,340.00

Anl. SNI 3434-2008 6.22 : 1 M1 Memasang Lisplank Ukuran (3 x 30) cm, Kayu Kelas I

: Bahan

0.0110 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll.) @ Rp. 10,400,000.00 Rp. 114,400.00

0.050 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 850.00

: Tenaga Kerja

Page 98: JUKNIS PERENCANAAN 2014

0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00

0.200 OH Tukang Kayu @ Rp. 80,000.00 Rp. 16,000.00

0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00

0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. 140,650.00

Dibulatkan Rp. 140,650.00

Anl. SNI 3434-2008 6.22a : 1 M1 Memasang Lisplank Ukuran (3 x 30) cm, Kayu Kelas II

: Bahan

0.0110 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 85,800.00

0.050 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 850.00

: Tenaga Kerja

0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00

0.200 OH Tukang Kayu @ Rp. 80,000.00 Rp. 16,000.00

0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00

0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. 112,050.00

Dibulatkan Rp. 112,050.00

Anl. SNI 3434-2008 6.23 : 1 M2 Memasang Rangka Dinding Pemisah Ukuran (60 x 120) cm, Kayu Kelas II

: Bahan

0.028 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 218,400.00

0.150 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 2,550.00

: Tenaga Kerja

0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00

0.450 OH Tukang Kayu @ Rp. 80,000.00 Rp. 36,000.00

0.045 OH Kepala Tukang @ Rp. 100,000.00 Rp. 4,500.00

0.008 OH Mandor @ Rp. 80,000.00 Rp. 640.00

Jumlah Rp. 272,590.00

Dibulatkan Rp. 272,590.00

Anl. SNI 3434-2008 6.26 : 1 M2 Memasang Dinding Lambriziring Dari Papan Kayu Kelas I

: Bahan

0.0070 m3 Kayu Klas I (Merbo/Seumantok/Ulin/dll.) @ Rp. 10,400,000.00 Rp. 72,800.00

0.100 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 1,700.00

0.150 kg Paku Sekrup @ Rp. 32,500.00 Rp. 4,875.00

: Tenaga Kerja

0.600 OH Pekerja @ Rp. 70,000.00 Rp. 42,000.00

1.800 OH Tukang Kayu @ Rp. 80,000.00 Rp. 144,000.00

0.180 OH Kepala Tukang @ Rp. 100,000.00 Rp. 18,000.00

0.030 OH Mandor @ Rp. 80,000.00 Rp. 2,400.00

Jumlah Rp. 285,775.00

Dibulatkan Rp. 285,775.00

Page 99: JUKNIS PERENCANAAN 2014

IV. DAFTAR ANALISA PEKERJAAN DINDING BATU

Anl. SNI 6897-2008 6.1 : 1 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1 Bata, Campuran Spesi 1 PC : 2 PP

: Bahan

140.0000 Buah Batu Bata @ Rp. 570.00 Rp. 79,800.00

43.500 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 69,273.75

0.080 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 14,400.00

: Tenaga Kerja

0.600 OH Pekerja @ Rp. 70,000.00 Rp. 42,000.00

0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00

0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00

0.030 OH Mandor @ Rp. 80,000.00 Rp. 2,400.00

Jumlah Rp. 225,873.75

Dibulatkan Rp. 225,873.00

Anl. SNI 6897-2008 6.2 : 1 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1 Bata, Campuran Spesi 1 PC : 3 PP

: Bahan

140.0000 Buah Batu Bata @ Rp. 570.00 Rp. 79,800.00

32.950 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 52,472.88

0.091 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 16,380.00

: Tenaga Kerja

0.600 OH Pekerja @ Rp. 70,000.00 Rp. 42,000.00

0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00

0.032 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,200.00

Page 100: JUKNIS PERENCANAAN 2014

0.030 OH Mandor @ Rp. 80,000.00 Rp. 2,400.00

Jumlah Rp. 212,252.88

Dibulatkan Rp. 212,252.00

Anl. SNI 6897-2008 6.3 : 1 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1 Bata, Campuran Spesi 1 PC : 4 PP

: Bahan

140.0000 Buah Batu Bata @ Rp. 570.00 Rp. 79,800.00

26.550 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 42,280.88

0.093 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 16,740.00

: Tenaga Kerja

0.600 OH Pekerja @ Rp. 70,000.00 Rp. 42,000.00

0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00

0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00

0.030 OH Mandor @ Rp. 80,000.00 Rp. 2,400.00

Jumlah Rp. 201,220.88

Dibulatkan Rp. 201,220.00

Anl. SNI 6897-2008 6.4 : 1 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1 Bata, Campuran Spesi 1 PC : 5 PP

: Bahan

140.0000 Buah Batu Bata @ Rp. 570.00 Rp. 79,800.00

22.200 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 35,353.50

0.102 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 18,360.00

: Tenaga Kerja

0.600 OH Pekerja @ Rp. 70,000.00 Rp. 42,000.00

0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00

0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00

0.030 OH Mandor @ Rp. 80,000.00 Rp. 2,400.00

Jumlah Rp. 195,913.50

Dibulatkan Rp. 195,913.00

Anl. SNI 6897-2008 6.5 : 1 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1 Bata, Campuran Spesi 1 PC : 6 PP

: Bahan

140.0000 Buah Batu Bata @ Rp. 570.00 Rp. 79,800.00

18.500 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 29,461.25

0.122 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 21,960.00

: Tenaga Kerja

0.600 OH Pekerja @ Rp. 70,000.00 Rp. 42,000.00

0.200 OH Tukang Batu @ Rp. 80,000.00 Rp. 16,000.00

0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00

0.030 OH Mandor @ Rp. 80,000.00 Rp. 2,400.00

Jumlah Rp. 193,621.25

Dibulatkan Rp. 193,621.00

Anl. SNI 6897-2008 6.7 : 1 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1/2 Bata, Campuran Spesi 1 PC : 2 PP

: Bahan

70.000 Buah Batu Bata @ Rp. 570.00 Rp. 39,900.00

18.950 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 30,177.88

0.038 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 6,840.00

: Tenaga Kerja

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.100 OH Tukang Batu @ Rp. 80,000.00 Rp. 8,000.00

0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 108,117.88

Dibulatkan Rp. 108,117.00

Anl. SNI 6897-2008 6.8 : 1 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1/2 Bata, Campuran Spesi 1 PC : 3 PP

: Bahan

70.000 Buah Batu Bata @ Rp. 570.00 Rp. 39,900.00

14.370 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 22,884.23

0.040 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 7,200.00

: Tenaga Kerja

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.100 OH Tukang Batu @ Rp. 80,000.00 Rp. 8,000.00

Page 101: JUKNIS PERENCANAAN 2014

0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 101,184.23

Dibulatkan Rp. 101,184.00

Anl. SNI 6897-2008 6.9 : 1 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1/2 Bata, Campuran Spesi 1 PC : 4 PP

: Bahan

70.000 Buah Batu Bata @ Rp. 570.00 Rp. 39,900.00

11.500 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 18,313.75

0.043 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 7,740.00

: Tenaga Kerja

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.100 OH Tukang Batu @ Rp. 80,000.00 Rp. 8,000.00

0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 97,153.75

Dibulatkan Rp. 97,153.00

Anl. SNI 6897-2008 6.10 : 1 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1/2 Bata, Campuran Spesi 1 PC : 5 PP

: Bahan

70.000 Buah Batu Bata @ Rp. 570.00 Rp. 39,900.00

9.680 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 15,415.40

0.045 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 8,100.00

: Tenaga Kerja

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.100 OH Tukang Batu @ Rp. 80,000.00 Rp. 8,000.00

0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 94,615.40

Dibulatkan Rp. 94,615.00

Anl. SNI 6897-2008 6.11 : 1 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1/2 Bata, Campuran Spesi 1 PC : 6 PP

: Bahan

70.000 Buah Batu Bata @ Rp. 570.00 Rp. 39,900.00

8.320 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 13,249.60

0.049 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 8,820.00

: Tenaga Kerja

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.100 OH Tukang Batu @ Rp. 80,000.00 Rp. 8,000.00

0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 93,169.60

Dibulatkan Rp. 93,169.00

Anl. SNI 6897-2008 6.12 : 1 M2 Memasang Dinding Bata Merah Ukuran (5 x 11 x 22) cm Tebal 1/2 Bata, Campuran Spesi 1 PC : 8 PP

: Bahan

70.000 Buah Batu Bata @ Rp. 570.00 Rp. 39,900.00

6.500 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 10,351.25

0.050 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 9,000.00

: Tenaga Kerja

0.300 OH Pekerja @ Rp. 70,000.00 Rp. 21,000.00

0.100 OH Tukang Batu @ Rp. 80,000.00 Rp. 8,000.00

0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00

0.015 OH Mandor @ Rp. 80,000.00 Rp. 1,200.00

Jumlah Rp. 90,451.25

Dibulatkan Rp. 90,451.00

Anl. SNI 6897-2008 6.18 : 1 M2 Memasang Talang Datar/Jurai Seng BJLS 28 Lebar 90 cm

: Bahan

1.050 m Seng Plat BJLS 20 @ Rp. 29,900.00 Rp. 31,395.00

0.015 kg Paku Seng @ Rp. 31,200.00 Rp. 468.00

0.019 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 148,200.00

Page 102: JUKNIS PERENCANAAN 2014

: Tenaga Kerja

0.200 OH Pekerja @ Rp. 70,000.00 Rp. 14,000.00

0.400 OH Tukang @ Rp. 80,000.00 Rp. 32,000.00

0.025 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,500.00

0.010 OH Mandor @ Rp. 80,000.00 Rp. 800.00

Jumlah Rp. 229,363.00

Dibulatkan Rp. 229,363.00

Anl. SNI 6897-2008 6.18a : 1 M2 Memasang Talang Datar/Jurai Seng BJLS 28 Lebar 90 cm

: Bahan

1.050 m Seng Plat BJLS 20 @ Rp. 29,900.00 Rp. 31,395.00

0.015 kg Paku Seng @ Rp. 31,200.00 Rp. 468.00

0.019 m3 Kayu Klas II (Kamper/Kruing/dll.) @ Rp. 7,800,000.00 Rp. 148,200.00

: Tenaga Kerja

0.200 OH Pekerja @ Rp. 70,000.00 Rp. 14,000.00

0.400 OH Tukang @ Rp. 80,000.00 Rp. 32,000.00

0.025 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,500.00

0.010 OH Mandor @ Rp. 80,000.00 Rp. 800.00

Jumlah Rp. 229,363.00

Dibulatkan Rp. 229,363.00

IV. DAFTAR ANALISA PEKERJAAN BETON UNTUK KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN

Anl. SNI 7394-2008 6.1 : 1 M3 Membuat Beton Mutu F'c=7.4 Mpa (K100), Slump (12 ± 2)cm,w/c=0.87

: Bahan

247.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 393,347.50

869.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 117,935.71

999.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 162,800.00

215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja

1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00

0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00

0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00

0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 831,773.21

Dibulatkan Rp. 831,773.00

Page 103: JUKNIS PERENCANAAN 2014

Anl. SNI 7394-2008 6.2 : 1 M3 Membuat Beton Mutu F'c=9.8 Mpa (K125), Slump (12 ± 2)cm,w/c=0.78

: Bahan

276.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 439,530.00

828.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 112,371.43

1012.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 164,918.52

215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja

1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00

0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00

0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00

0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 874,509.95

Dibulatkan Rp. 874,509.00

Anl. SNI 7394-2008 6.3 : 1 M3 Membuat Beton Mutu F'c=12.2 Mpa (K150), Slump (12 ± 2)cm,w/c=0.72

: Bahan

299.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 476,157.50

799.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 108,435.71

1017.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 165,733.33

215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja

1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00

0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00

0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00

0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 908,016.55

Dibulatkan Rp. 908,016.00

Anl. SNI 7394-2008 6.4 : 1 M3 Membuat Lantai Kerja Beton Mutu F'c=7.4 Mpa (K100), Slump (3 - 6)cm,w/c=0.72

: Bahan

230.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 366,275.00

893.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 121,192.86

1027.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 167,362.96

200.000 liter Air Bersih @ Rp. 50.00 Rp. 10,000.00

: Tenaga Kerja

1.200 OH Pekerja @ Rp. 70,000.00 Rp. 84,000.00

0.200 OH Tukang @ Rp. 80,000.00 Rp. 16,000.00

0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00

0.060 OH Mandor @ Rp. 80,000.00 Rp. 4,800.00

Jumlah Rp. 771,630.82

Dibulatkan Rp. 771,630.00

Anl. SNI 7394-2008 6.5 : 1 M3 Membuat Beton Mutu F'c=14.5 Mpa (K175), Slump (12 ± 2)cm,w/c=0.66

: Bahan

326.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 519,155.00

760.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 103,142.86

1029.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 167,688.89

215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja

1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00

0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00

0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00

0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 947,676.75

Page 104: JUKNIS PERENCANAAN 2014

Dibulatkan Rp. 947,676.00

Anl. SNI 7394-2008 6.6 : 1 M3 Membuat Beton Mutu F'c=16.9 Mpa (K200), Slump (12 ± 2)cm,w/c=0.61

: Bahan

352.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 560,560.00

731.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 99,207.14

1031.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 168,014.81

215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja

1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00

0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00

0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00

0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 985,471.96

Dibulatkan Rp. 985,471.00

Anl. SNI 7394-2008 6.7 : 1 M3 Membuat Beton Mutu F'c=19.3 Mpa (K225), Slump (12 ± 2) cm, w/c=0.58

: Bahan

371.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 590,817.50

698.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 94,728.57

1047.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 170,622.22

215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja

1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00

0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00

0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00

0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 1,013,858.29

Dibulatkan Rp. 1,013,858.00

Anl. SNI 7394-2008 6.8 : 1 M3 Membuat Beton Mutu F'c=21.7 Mpa (K250), Slump (12 ± 2) cm, w/c=0.56

: Bahan

384.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 611,520.00

692.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 93,914.29

1039.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 169,318.52

215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja

1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00

0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00

0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00

0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 1,032,442.80

Dibulatkan Rp. 1,032,442.00

Anl. SNI 7394-2008 6.9 : 1 M3 Membuat Beton Mutu F'c=24.0 Mpa (K275), Slump (12 ± 2)cm,w/c=0.53

: Bahan

406.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 646,555.00

684.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 92,828.57

1026.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 167,200.00

215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja

1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00

0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00

Page 105: JUKNIS PERENCANAAN 2014

0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00

0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 1,064,273.57

Dibulatkan Rp. 1,064,273.00

Anl. SNI 7394-2008 6.10 : 1 M3 Membuat Beton Mutu F'c=26.4 Mpa (K300), Slump (12 ± 2)cm,w/c=0.52

: Bahan

413.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 657,702.50

681.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 92,421.43

1021.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 166,385.19

215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja

1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00

0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00

0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00

0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 1,074,199.11

Dibulatkan Rp. 1,074,199.00

Anl. SNI 7394-2008 6.11 : 1 M3 Membuat Beton Mutu F'c=28.8 Mpa (K325), Slump (12 ± 2)cm,w/c=0.49

: Bahan

439.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 699,107.50

670.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 90,928.57

1006.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 163,940.74

215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja

2.100 OH Pekerja @ Rp. 70,000.00 Rp. 147,000.00

0.350 OH Tukang @ Rp. 80,000.00 Rp. 28,000.00

0.035 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,500.00

0.105 OH Mandor @ Rp. 80,000.00 Rp. 8,400.00

Jumlah Rp. 1,151,626.81

Dibulatkan Rp. 1,151,626.00

Anl. SNI 7394-2008 6.12 : 1 M3 Membuat Beton Mutu F'c=31.2 Mpa (K350), Slump (12 ± 2)cm,w/c=0.48

: Bahan

448.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 713,440.00

667.000 kg Pasir Beton Bersih (per kg) @ Rp. 135.71 Rp. 90,521.43

1000.000 kg Kerikil Bersih (per kg; maksimum 30 mm) @ Rp. 162.96 Rp. 162,962.96

215.000 liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja

2.100 OH Pekerja @ Rp. 70,000.00 Rp. 147,000.00

0.350 OH Tukang @ Rp. 80,000.00 Rp. 28,000.00

0.035 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,500.00

0.105 OH Mandor @ Rp. 80,000.00 Rp. 8,400.00

Jumlah Rp. 1,164,574.39

Dibulatkan Rp. 1,164,574.00

Anl. SNI 7394-2008 6.17 : 10 Kg Pembesian Dengan Besi Ulir

: Bahan

10.500 kg Besi Beton Ulir @ Rp. 13,000.00 Rp. 136,500.00

0.150 kg Kawat Beton @ Rp. 19,500.00 Rp. 2,925.00

: Tenaga Kerja

0.070 OH Pekerja @ Rp. 70,000.00 Rp. 4,900.00

0.070 OH Tukang @ Rp. 80,000.00 Rp. 5,600.00

0.007 OH Kepala Tukang @ Rp. 100,000.00 Rp. 700.00

0.004 OH Mandor @ Rp. 80,000.00 Rp. 320.00

Jumlah Rp. 150,945.00

per kg Rp. 15,094.50

Dibulatkan Rp. 15,094.50

Anl. SNI 7394-2008 6.17a : 1 Kg Pembesian Dengan Besi Polos

: Bahan

1.500 kg Besi Beton Polos @ Rp. 12,000.00 Rp. 18,000.00

0.015 kg Kawat Beton @ Rp. 19,500.00 Rp. 292.50

: Tenaga Kerja

Page 106: JUKNIS PERENCANAAN 2014

0.007 OH Pekerja @ Rp. 70,000.00 Rp. 490.00

0.007 OH Tukang @ Rp. 80,000.00 Rp. 560.00

0.0007 OH Kepala Tukang @ Rp. 100,000.00 Rp. 70.00

0.0004 OH Mandor @ Rp. 80,000.00 Rp. 32.00

Jumlah Rp. 19,444.50

Dibulatkan Rp. 19,444.00

Anl. SNI 7394-2008 6.18 : 10 Kg Kabel Presstressed Polos

: Bahan

10.500 kg Besi Beton Polos @ Rp. 12,000.00 Rp. 126,000.00

0.100 kg Kawat Beton @ Rp. 19,500.00 Rp. 1,950.00

: Tenaga Kerja

0.050 OH Pekerja @ Rp. 70,000.00 Rp. 3,500.00

0.050 OH Tukang @ Rp. 80,000.00 Rp. 4,000.00

0.0050 OH Kepala Tukang @ Rp. 100,000.00 Rp. 500.00

0.0030 OH Mandor @ Rp. 80,000.00 Rp. 240.00

Jumlah Rp. 136,190.00

Dibulatkan Rp. 136,190.00

Anl. SNI 7394-2008 6.20 : 1 M2 Memasang Bekisting Untuk Pondasi

: Bahan

0.040 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 208,000.00

0.300 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 5,100.00

0.100 Liter Minyak Bekisting @ Rp. 3,500.00 Rp. 350.00

: Tenaga Kerja

0.520 OH Pekerja @ Rp. 70,000.00 Rp. 36,400.00

0.260 OH Tukang @ Rp. 80,000.00 Rp. 20,800.00

0.026 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,600.00

0.026 OH Mandor @ Rp. 80,000.00 Rp. 2,080.00

Jumlah Rp. 275,330.00

Dibulatkan Rp. 275,330.00

Anl. SNI 7394-2008 6.21 : 1 M2 Memasang Bekisting Untuk Sloof

: Bahan

0.045 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 234,000.00

0.300 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 5,100.00

0.100 Liter Minyak Bekisting @ Rp. 3,500.00 Rp. 350.00

: Tenaga Kerja

0.520 OH Pekerja @ Rp. 70,000.00 Rp. 36,400.00

0.260 OH Tukang @ Rp. 80,000.00 Rp. 20,800.00

0.026 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,600.00

0.026 OH Mandor @ Rp. 80,000.00 Rp. 2,080.00

Jumlah Rp. 301,330.00

Dibulatkan Rp. 301,330.00

Anl. SNI 7394-2008 6.22 : 1 M2 Memasang Bekisting Untuk Kolom

: Bahan

0.040 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 208,000.00

0.400 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 6,800.00

0.200 Liter Minyak Bekisting @ Rp. 3,500.00 Rp. 700.00

0.015 m3 Balok Kayu Kelas II @ Rp. 8,450.00 Rp. 126.75

0.350 Lembar Multipleks 9 mm @ Rp. 136,500.00 Rp. 47,775.00

2.000 Batang Dolken Kayu Galam Dia. 8 - 10 Panjang 4 m @ Rp. 10,000.00 Rp. 20,000.00

: Tenaga Kerja

0.660 OH Pekerja @ Rp. 70,000.00 Rp. 46,200.00

0.330 OH Tukang @ Rp. 80,000.00 Rp. 26,400.00

0.033 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,300.00

0.033 OH Mandor @ Rp. 80,000.00 Rp. 2,640.00

Jumlah Rp. 361,941.75

Dibulatkan Rp. 361,941.00

Anl. SNI 7394-2008 6.23 : 1 M2 Memasang Bekisting Untuk Balok

: Bahan

Page 107: JUKNIS PERENCANAAN 2014

0.040 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 208,000.00

0.400 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 6,800.00

0.200 Liter Minyak Bekisting @ Rp. 3,500.00 Rp. 700.00

0.018 m3 Balok Kayu Kelas II @ Rp. 8,450.00 Rp. 152.10

0.350 Lembar Multipleks 9 mm @ Rp. 136,500.00 Rp. 47,775.00

2.000 Batang Dolken Kayu Galam Dia. 8 - 10 Panjang 4 m @ Rp. 10,000.00 Rp. 20,000.00

: Tenaga Kerja

0.660 OH Pekerja @ Rp. 70,000.00 Rp. 46,200.00

0.330 OH Tukang @ Rp. 80,000.00 Rp. 26,400.00

0.033 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,300.00

0.033 OH Mandor @ Rp. 80,000.00 Rp. 2,640.00

Jumlah Rp. 361,967.10

Dibulatkan Rp. 361,967.00

Anl. SNI 7394-2008 6.24 : 1 M2 Memasang Bekisting Untuk Plat Lantai

: Bahan

0.040 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 208,000.00

0.400 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 6,800.00

0.200 Liter Minyak Bekisting @ Rp. 3,500.00 Rp. 700.00

0.015 m3 Balok Kayu Kelas II @ Rp. 8,450.00 Rp. 126.75

0.350 Lembar Multipleks 9 mm @ Rp. 136,500.00 Rp. 47,775.00

6.000 Batang Dolken Kayu Galam Dia. 8 - 10 Panjang 4 m @ Rp. 10,000.00 Rp. 60,000.00

: Tenaga Kerja

0.660 OH Pekerja @ Rp. 70,000.00 Rp. 46,200.00

0.330 OH Tukang @ Rp. 80,000.00 Rp. 26,400.00

0.033 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,300.00

0.033 OH Mandor @ Rp. 80,000.00 Rp. 2,640.00

Jumlah Rp. 401,941.75

Dibulatkan Rp. 401,941.00

Anl. SNI 7394-2008 6.26 : 1 M2 Memasang Bekisting Untuk Tangga

: Bahan

0.030 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 156,000.00

0.400 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 6,800.00

0.150 Liter Minyak Bekisting @ Rp. 3,500.00 Rp. 525.00

0.015 m3 Balok Kayu Kelas II @ Rp. 8,450.00 Rp. 126.75

0.350 Lembar Multipleks 9 mm @ Rp. 136,500.00 Rp. 47,775.00

2.000 Batang Dolken Kayu Galam Dia. 8 - 10 Panjang 4 m @ Rp. 10,000.00 Rp. 20,000.00

: Tenaga Kerja

0.660 OH Pekerja @ Rp. 70,000.00 Rp. 46,200.00

0.330 OH Tukang @ Rp. 80,000.00 Rp. 26,400.00

0.033 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,300.00

0.033 OH Mandor @ Rp. 80,000.00 Rp. 2,640.00

Jumlah Rp. 309,766.75

Dibulatkan Rp. 309,766.00

Anl. SNI 7394-2008 6.27 : 1 M2 Memasang Jembatan Untuk Pengecoran Beton

: Bahan

0.0264 m3 Kayu Klas III (Borneo/dll.) @ Rp. 5,200,000.00 Rp. 137,280.00

0.600 kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 10,200.00

0.500 Batang Dolken Kayu Galam Dia. 8 - 10 Panjang 4 m @ Rp. 10,000.00 Rp. 5,000.00

: Tenaga Kerja

0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00

0.050 OH Tukang @ Rp. 80,000.00 Rp. 4,000.00

0.005 OH Kepala Tukang @ Rp. 100,000.00 Rp. 500.00

0.008 OH Mandor @ Rp. 80,000.00 Rp. 640.00

Jumlah Rp. 168,120.00

Dibulatkan Rp. 168,120.00

Page 108: JUKNIS PERENCANAAN 2014

V. DAFTAR ANALISA PEKERJAAN LANTAI

Anl. SNI 7395-2008 6.1 : 1 M2 Memasang Lantai Ubin PC Abu-abu Ukuran (40 x 40) cm

: Bahan

6.630 Buah Ubin Abu-abu @ Rp. #N/A Rp. #N/A

9.800 kg Semen @ Rp. #N/A Rp. #N/A

0.045 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 8,100.00

: Tenaga Kerja

0.250 OH Pekerja @ Rp. 70,000.00 Rp. 17,500.00

0.125 OH Tukang @ Rp. 80,000.00 Rp. 10,000.00

0.013 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,300.00

0.013 OH Mandor @ Rp. 80,000.00 Rp. 1,040.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 7395-2008 6.2 : 1 M2 Memasang Lantai Ubin PC Abu-abu Ukuran (30 x 30) cm

: Bahan

1.060 Buah Ubin abu-abu 30 x 30 @ Rp. 101,200.00 Rp. 107,272.00

10.000 kg Semen PC (per kg) @ Rp. 1,592.50 Rp. 15,925.00

0.045 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 8,100.00

: Tenaga Kerja

0.260 OH Pekerja @ Rp. 70,000.00 Rp. 18,200.00

0.130 OH Tukang @ Rp. 80,000.00 Rp. 10,400.00

0.013 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,300.00

0.013 OH Mandor @ Rp. 80,000.00 Rp. 1,040.00

Jumlah Rp. 162,237.00

Dibulatkan Rp. 162,237.00

Anl. SNI 7395-2008 6.3 : 1 M2 Memasang Lantai Ubin PC Abu-abu Ukuran (20 x 20) cm

: Bahan

26.500 Buah Ubin Abu-Abu @ Rp. #N/A Rp. #N/A

10.400 kg Semen @ Rp. #N/A Rp. #N/A

0.045 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 8,100.00

: Tenaga Kerja

0.270 OH Pekerja @ Rp. 70,000.00 Rp. 18,900.00

0.135 OH Tukang @ Rp. 80,000.00 Rp. 10,800.00

0.014 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,400.00

0.014 OH Mandor @ Rp. 80,000.00 Rp. 1,120.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 7395-2008 6.4 : 1 M2 Memasang Lantai Ubin Warna Ukuran (40 x 40) cm

: Bahan

1.060 m2 Keramik Uk. 40 x 40 cm @ Rp. 71,500.00 Rp. 75,790.00

9.800 kg Semen Andalas (per kg) @ Rp. #N/A Rp. #N/A

0.045 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 8,100.00

1.300 kg Semen Warna per Kg @ Rp. 2,960.00 Rp. 3,848.00

: Tenaga Kerja

0.250 OH Pekerja @ Rp. 70,000.00 Rp. 17,500.00

0.125 OH Tukang @ Rp. 80,000.00 Rp. 10,000.00

0.013 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,300.00

0.013 OH Mandor @ Rp. 80,000.00 Rp. 1,040.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Page 109: JUKNIS PERENCANAAN 2014

Anl. SNI 7395-2008 6.5 : 1 M2 Memasang Lantai Ubin Warna Ukuran (30 x 30) cm

: Bahan

11.870 Buah Ubin Warna @ Rp. #N/A Rp. #N/A

10.000 kg Semen @ Rp. #N/A Rp. #N/A

0.045 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 8,100.00

1.500 kg Semen Warna @ Rp. #N/A Rp. #N/A

: Tenaga Kerja

0.260 OH Pekerja @ Rp. 70,000.00 Rp. 18,200.00

0.130 OH Tukang @ Rp. 80,000.00 Rp. 10,400.00

0.013 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,300.00

0.013 OH Mandor @ Rp. 80,000.00 Rp. 1,040.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 7395-2008 6.6 : 1 M2 Memasang Lantai Ubin Warna Ukuran (20 x 20) cm

: Bahan

26.500 Buah Ubin Warna @ Rp. #N/A Rp. #N/A

10.400 kg Semen @ Rp. #N/A Rp. #N/A

0.045 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 8,100.00

0.162 kg Semen Warna @ Rp. #N/A Rp. #N/A

: Tenaga Kerja

0.270 OH Pekerja @ Rp. 70,000.00 Rp. 18,900.00

0.135 OH Tukang @ Rp. 80,000.00 Rp. 10,800.00

0.014 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,400.00

0.014 OH Mandor @ Rp. 80,000.00 Rp. 1,120.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 7395-2008 6.7 : 1 M2 Memasang Lantai Ubin Teraso Ukuran (40 x 40) cm

: Bahan

6.630 Buah Ubin Teraso @ Rp. #N/A Rp. #N/A

9.800 kg Semen @ Rp. #N/A Rp. #N/A

0.045 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 8,100.00

1.300 kg Semen Warna @ Rp. #N/A Rp. #N/A

: Tenaga Kerja

0.250 OH Pekerja @ Rp. 70,000.00 Rp. 17,500.00

0.125 OH Tukang @ Rp. 80,000.00 Rp. 10,000.00

0.013 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,300.00

0.013 OH Mandor @ Rp. 80,000.00 Rp. 1,040.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 7395-2008 6.8 : 1 M2 Memasang Lantai Ubin Teraso Ukuran (30 x 30) cm

: Bahan

11.870 Buah Ubin Teraso @ Rp. #N/A Rp. #N/A

10.000 kg Semen @ Rp. #N/A Rp. #N/A

0.045 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 8,100.00

1.500 kg Semen Warna @ Rp. #N/A Rp. #N/A

: Tenaga Kerja

0.260 OH Pekerja @ Rp. 70,000.00 Rp. 18,200.00

0.130 OH Tukang @ Rp. 80,000.00 Rp. 10,400.00

0.013 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,300.00

0.013 OH Mandor @ Rp. 80,000.00 Rp. 1,040.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Page 110: JUKNIS PERENCANAAN 2014

Anl. SNI 7395-2008 6.16 : 1 M2 Memasang Plint Ubin PC Abu-abu Ukuran (15 x 20) cm

: Bahan

5.300 Buah Plint Ubin @ Rp. #N/A Rp. #N/A

1.650 kg Semen @ Rp. #N/A Rp. #N/A

0.004 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 720.00

: Tenaga Kerja

0.090 OH Pekerja @ Rp. 70,000.00 Rp. 6,300.00

0.090 OH Tukang @ Rp. 80,000.00 Rp. 7,200.00

0.009 OH Kepala Tukang @ Rp. 100,000.00 Rp. 900.00

0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 7395-2008 6.17 : 1 M2 Memasang Plint Ubin PC Abu-abu Ukuran (10 x 30) cm

: Bahan

3.530 Buah Plint Ubin @ Rp. #N/A Rp. #N/A

1.240 kg Semen @ Rp. #N/A Rp. #N/A

0.003 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 540.00

: Tenaga Kerja

0.090 OH Pekerja @ Rp. 70,000.00 Rp. 6,300.00

0.090 OH Tukang @ Rp. 80,000.00 Rp. 7,200.00

0.009 OH Kepala Tukang @ Rp. 100,000.00 Rp. 900.00

0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 7395-2008 6.18 : 1 M2 Memasang Plint Ubin PC Abu-abu Ukuran (10 x 40) cm

: Bahan

2.650 Buah Plint Ubin @ Rp. #N/A Rp. #N/A

1.240 kg Semen @ Rp. #N/A Rp. #N/A

0.003 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 540.00

: Tenaga Kerja

0.090 OH Pekerja @ Rp. 70,000.00 Rp. 6,300.00

0.090 OH Tukang @ Rp. 80,000.00 Rp. 7,200.00

0.009 OH Kepala Tukang @ Rp. 100,000.00 Rp. 900.00

0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 7395-2008 6.19 : 1 M2 Memasang Plint Ubin PC Warna Ukuran (10 x 20) cm

: Bahan

5.300 Buah Plint Ubin Pc Warna @ Rp. #N/A Rp. #N/A

1.140 kg Semen @ Rp. #N/A Rp. #N/A

0.003 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 540.00

0.100 kg Semen Warna @ Rp. #N/A Rp. #N/A

: Tenaga Kerja

0.090 OH Pekerja @ Rp. 70,000.00 Rp. 6,300.00

0.090 OH Tukang @ Rp. 80,000.00 Rp. 7,200.00

0.009 OH Kepala Tukang @ Rp. 100,000.00 Rp. 900.00

0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 7395-2008 6.20 : 1 M2 Memasang Plint Ubin PC Warna Ukuran (10 x 30) cm

: Bahan

3.530 Buah Plint Ubin Pc Warna @ Rp. #N/A Rp. #N/A

1.140 kg Semen @ Rp. #N/A Rp. #N/A

Page 111: JUKNIS PERENCANAAN 2014

0.003 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 540.00

0.100 kg Semen Warna @ Rp. #N/A Rp. #N/A

: Tenaga Kerja

0.090 OH Pekerja @ Rp. 70,000.00 Rp. 6,300.00

0.090 OH Tukang @ Rp. 80,000.00 Rp. 7,200.00

0.009 OH Kepala Tukang @ Rp. 100,000.00 Rp. 900.00

0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 7395-2008 6.21 : 1 M2 Memasang Plint Ubin PC Warna Ukuran (10 x 40) cm

: Bahan

2.650 Buah Plint Ubin Pc Warna @ Rp. #N/A Rp. #N/A

1.140 kg Semen @ Rp. #N/A Rp. #N/A

0.003 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 540.00

0.100 kg Semen Warna @ Rp. #N/A Rp. #N/A

: Tenaga Kerja

0.090 OH Pekerja @ Rp. 70,000.00 Rp. 6,300.00

0.090 OH Tukang @ Rp. 80,000.00 Rp. 7,200.00

0.009 OH Kepala Tukang @ Rp. 100,000.00 Rp. 900.00

0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 7395-2008 6.38 : 1 M2 Memasang Lantai Mosaik Ukuran (30 x 30) cm, Campuran spesi 1 PC : 3 PP

: Bahan

11.870 Buah Mosaik @ Rp. #N/A Rp. #N/A

14.150 kg Semen @ Rp. #N/A Rp. #N/A

0.039 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 7,020.00

2.000 kg Semen Warna @ Rp. #N/A Rp. #N/A

: Tenaga Kerja

0.070 OH Pekerja @ Rp. 70,000.00 Rp. 4,900.00

0.350 OH Tukang @ Rp. 80,000.00 Rp. 28,000.00

0.035 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,500.00

0.035 OH Mandor @ Rp. 80,000.00 Rp. 2,800.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 7395-2008 6.39 : 1 M2 Memasang Plint Keramik Ukuran (10 x 20) cm

: Bahan

5.300 Buah Plint Keramik Artistik @ Rp. #N/A Rp. #N/A

1.140 kg Semen @ Rp. #N/A Rp. #N/A

0.003 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 540.00

0.025 kg Semen Warna @ Rp. #N/A Rp. #N/A

: Tenaga Kerja

0.090 OH Pekerja @ Rp. 70,000.00 Rp. 6,300.00

0.090 OH Tukang @ Rp. 80,000.00 Rp. 7,200.00

0.009 OH Kepala Tukang @ Rp. 100,000.00 Rp. 900.00

0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 7395-2008 6.40 : 1 M2 Memasang Plint Keramik Ukuran (10 x 10) cm

: Bahan

10.600 Buah Plint Keramik Artistik @ Rp. #N/A Rp. #N/A

1.140 kg Semen @ Rp. #N/A Rp. #N/A

0.003 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 540.00

0.050 kg Semen Warna @ Rp. #N/A Rp. #N/A

: Tenaga Kerja

0.090 OH Pekerja @ Rp. 70,000.00 Rp. 6,300.00

0.090 OH Tukang @ Rp. 80,000.00 Rp. 7,200.00

0.009 OH Kepala Tukang @ Rp. 100,000.00 Rp. 900.00

0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. #N/A

Page 112: JUKNIS PERENCANAAN 2014

Dibulatkan Rp. #N/A

Anl. SNI 7395-2008 6.41 : 1 M2 Memasang Plint Keramik Ukuran (5 x 20) cm

: Bahan

5.300 Buah Plint Keramik Artistik @ Rp. #N/A Rp. #N/A

0.570 kg Semen @ Rp. #N/A Rp. #N/A

0.0015 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 270.00

0.013 kg Semen Warna @ Rp. #N/A Rp. #N/A

: Tenaga Kerja

0.090 OH Pekerja @ Rp. 70,000.00 Rp. 6,300.00

0.090 OH Tukang @ Rp. 80,000.00 Rp. 7,200.00

0.009 OH Kepala Tukang @ Rp. 100,000.00 Rp. 900.00

0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 7395-2008 6.54 : 1 M2 Memasang Dinding Keramik Ukuran (20 x 20) cm

: Bahan

26.500 Buah Keramik @ Rp. #N/A Rp. #N/A

9.300 kg Semen @ Rp. #N/A Rp. #N/A

0.018 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 3,240.00

1.940 kg Semen Warna @ Rp. #N/A Rp. #N/A

: Tenaga Kerja

0.900 OH Pekerja @ Rp. 70,000.00 Rp. 63,000.00

0.450 OH Tukang @ Rp. 80,000.00 Rp. 36,000.00

0.045 OH Kepala Tukang @ Rp. 100,000.00 Rp. 4,500.00

0.045 OH Mandor @ Rp. 80,000.00 Rp. 3,600.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 7395-2008 6.56 : 1 M2 Memasang Dinding Bata Pelapis Ukuran (3 x 7 x 24) cm

: Bahan

63.000 Buah Bata @ Rp. #N/A Rp. #N/A

12.440 kg Semen @ Rp. #N/A Rp. #N/A

0.025 m3 Pasir Pasang @ Rp. 180,000.00 Rp. 4,500.00

2.750 kg Semen Warna @ Rp. #N/A Rp. #N/A

: Tenaga Kerja

1.000 OH Pekerja @ Rp. 70,000.00 Rp. 70,000.00

0.500 OH Tukang @ Rp. 80,000.00 Rp. 40,000.00

0.050 OH Kepala Tukang @ Rp. 100,000.00 Rp. 5,000.00

0.050 OH Mandor @ Rp. 80,000.00 Rp. 4,000.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 7395-2008 6.63 : 1 M2 Memasang Plint Kayu Kelas II Tebal 2 cm, Lebar 10 cm

: Bahan

0.003 m Kayu Kelas II @ Rp. #N/A Rp. #N/A

0.050 kg Paku Sekrup @ Rp. 32,500.00 Rp. 1,625.00

: Tenaga Kerja

0.120 OH Pekerja @ Rp. 70,000.00 Rp. 8,400.00

0.120 OH Tukang @ Rp. 80,000.00 Rp. 9,600.00

0.012 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,200.00

Page 113: JUKNIS PERENCANAAN 2014

0.006 OH Mandor @ Rp. 80,000.00 Rp. 480.00

Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

V. DAFTAR ANALISA BIAYA KONSTRUKSI PEKERJAAN BETON

Anl. SNI 7394-2008 6.1 : 1 M3 Membuat Beton Tumbuk 1 PC : 3 PS : 5 KR

: Bahan

247.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 393,347.50

0.621 m3 Pasir Beton Bersih @ Rp. 190,000.00 Rp. 117,990.00

0.740 m3 Kerikil Bersih @ Rp. 220,000.00 Rp. 162,800.00

215.000 Liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja

1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00

0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00

0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00

0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 831,827.50

Dibulatkan Rp. 831,827.00

Anl. SNI 7394-2008 6.7 : 1 M3 Membuat Beton Dengan Mutu K-225

: Bahan

371.000 kg Semen PC Type I (per kg) @ Rp. 1,592.50 Rp. 590,817.50

0.499 m3 Pasir Beton Bersih @ Rp. 190,000.00 Rp. 94,810.00

0.776 m3 Kerikil Bersih @ Rp. 220,000.00 Rp. 170,720.00

215.000 Liter Air Bersih @ Rp. 50.00 Rp. 10,750.00

: Tenaga Kerja

1.650 OH Pekerja @ Rp. 70,000.00 Rp. 115,500.00

0.275 OH Tukang @ Rp. 80,000.00 Rp. 22,000.00

0.028 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,800.00

0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. 1,014,037.50

Dibulatkan Rp. 1,014,037.00

Anl. SNI 7394-2008 6.17a : 1 Kg Pembesian Dengan Besi Polos

: Bahan

1.050 kg Besi Beton Polos @ Rp. 12,000.00 Rp. 12,600.00

0.015 kg Kawat Beton @ Rp. 19,500.00 Rp. 292.50

: Tenaga Kerja

0.007 OH Pekerja @ Rp. 70,000.00 Rp. 490.00

0.007 OH Tukang @ Rp. 80,000.00 Rp. 560.00

0.0007 OH Kepala Tukang @ Rp. 100,000.00 Rp. 70.00

0.0004 OH Mandor @ Rp. 80,000.00 Rp. 32.00

Jumlah Rp. 14,044.50

Dibulatkan Rp. 14,044.00

Anl. SNI 7394-2008 6.20 : 1 M2 Memasang Bekisting Untuk Pondasi

: Bahan

0.040 m3 Kayu Kelas III @ Rp. 4,500,000.00 Rp. 180,000.00

0.300 kg Paku @ Rp. 16,800.00 Rp. 5,040.00

0.100 Liter Minyak Bekisting @ Rp. 12,000.00 Rp. 1,200.00

: Tenaga Kerja

Page 114: JUKNIS PERENCANAAN 2014

0.520 OH Pekerja @ Rp. 60,000.00 Rp. 31,200.00

0.260 OH Tukang @ Rp. 80,000.00 Rp. 20,800.00

0.026 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,600.00

0.026 OH Mandor @ Rp. 75,000.00 Rp. 1,950.00

Jumlah Rp. 242,790.00

Dibulatkan Rp. 242,790.00

Anl. SNI 7394-2008 6.21 : 1 M2 Memasang Bekisting Untuk Sloof

: Bahan

0.045 m3 Kayu Kelas III @ Rp. 4,500,000.00 Rp. 202,500.00

0.300 kg Paku @ Rp. 16,800.00 Rp. 5,040.00

0.100 Liter Minyak Bekisting @ Rp. 12,000.00 Rp. 1,200.00

: Tenaga Kerja

0.520 OH Pekerja @ Rp. 60,000.00 Rp. 31,200.00

0.260 OH Tukang @ Rp. 80,000.00 Rp. 20,800.00

0.026 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,600.00

0.026 OH Mandor @ Rp. 75,000.00 Rp. 1,950.00

Jumlah Rp. 265,290.00

Dibulatkan Rp. 265,290.00

Anl. SNI 7394-2008 6.22 : 1 M2 Memasang Bekisting Untuk Kolom

: Bahan

0.040 m3 Kayu Kelas III @ Rp. 4,500,000.00 Rp. 180,000.00

0.400 kg Paku @ Rp. 16,800.00 Rp. 6,720.00

0.200 Liter Minyak Bekisting @ Rp. 12,000.00 Rp. 2,400.00

0.015 m3 Balok Kayu Kelas II @ Rp. 7,115,625.00 Rp. 106,734.38

0.350 Lembar Plywood Tebal 9 mm @ Rp. 151,200.00 Rp. 52,920.00

2.000 Batang Dolken Kayu Galam, (8-10)cm, panjang 4 m @ Rp. 20,000.00 Rp. 40,000.00

: Tenaga Kerja

0.660 OH Pekerja @ Rp. 60,000.00 Rp. 39,600.00

0.330 OH Tukang @ Rp. 80,000.00 Rp. 26,400.00

0.033 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,300.00

0.033 OH Mandor @ Rp. 75,000.00 Rp. 2,475.00

Jumlah Rp. 460,549.38

Dibulatkan Rp. 460,549.00

Anl. SNI 7394-2008 6.23 : 1 M2 Memasang Bekisting Untuk Balok

: Bahan

0.040 m3 Kayu Kelas III @ Rp. 4,500,000.00 Rp. 180,000.00

0.400 kg Paku @ Rp. 16,800.00 Rp. 6,720.00

0.200 Liter Minyak Bekisting @ Rp. 12,000.00 Rp. 2,400.00

0.018 m3 Balok Kayu Kelas II @ Rp. 7,115,625.00 Rp. 128,081.25

0.350 Lembar Plywood Tebal 9 mm @ Rp. 151,200.00 Rp. 52,920.00

2.000 Batang Dolken Kayu Galam, (8-10)cm, panjang 4 m @ Rp. 20,000.00 Rp. 40,000.00

: Tenaga Kerja

0.660 OH Pekerja @ Rp. 60,000.00 Rp. 39,600.00

0.330 OH Tukang @ Rp. 80,000.00 Rp. 26,400.00

0.033 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,300.00

0.033 OH Mandor @ Rp. 75,000.00 Rp. 2,475.00

Jumlah Rp. 481,896.25

Dibulatkan Rp. 481,896.00

Anl. SNI 7394-2008 6.24 : 1 M2 Memasang Bekisting Untuk Plat Lantai

: Bahan

0.040 m3 Kayu Kelas III @ Rp. 4,500,000.00 Rp. 180,000.00

0.400 kg Paku @ Rp. 16,800.00 Rp. 6,720.00

0.200 Liter Minyak Bekisting @ Rp. 7,115,625.00 Rp. 1,423,125.00

0.015 m3 Balok Kayu Kelas II @ Rp. 6,200,000.00 Rp. 93,000.00

0.350 Lembar Plywood Tebal 9 mm @ Rp. 151,200.00 Rp. 52,920.00

6.000 Batang Dolken Kayu Galam, (8-10)cm, panjang 4 m @ Rp. 20,000.00 Rp. 120,000.00

: Tenaga Kerja

0.660 OH Pekerja @ Rp. 60,000.00 Rp. 39,600.00

0.330 OH Tukang @ Rp. 80,000.00 Rp. 26,400.00

0.033 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,300.00

0.033 OH Mandor @ Rp. 75,000.00 Rp. 2,475.00

Page 115: JUKNIS PERENCANAAN 2014

Jumlah Rp. 1,947,540.00

Dibulatkan Rp. 1,947,540.00

Pekerjaan Lain-lain : Untuk Membongkar Cetakan dan Menyiram Beton Diperlukan

: Tenaga Kerja

1.000 OH Pekerja @ Rp. 60,000.00 Rp. 60,000.00

Jumlah Rp. 60,000.00

Dibulatkan Rp. 60,000.00

SUPLEMEN 01 : 1 m3 Pondasi Tapak

1.000 m3 Anl. SNI 7394-2008 6.7 @ Rp. Rp.

DESIGN kg Anl. SNI 7394-2008 6.17a @ Rp. Rp.

DESIGN m2 Anl. SNI 7394-2008 6.20 @ Rp. Rp.

1.000 OH Pekerja Lain-lain @ Rp. Rp.

Jumlah Rp.

Dibulatkan Rp.

SUPLEMEN 02 : 1 m3 Sloof

1.000 m3 Anl. SNI 7394-2008 6.7 @ Rp. Rp.

DESIGN kg Anl. SNI 7394-2008 6.17a @ Rp. Rp.

DESIGN m2 Anl. SNI 7394-2008 6.21 @ Rp. Rp.

1.000 OH Pekerja Lain-lain @ Rp. Rp.

Jumlah Rp.

Dibulatkan Rp.

SUPLEMEN 03 : 1 m3 Kolom

1.000 m3 Anl. SNI 7394-2008 6.7 @ Rp. Rp.

DESIGN kg Anl. SNI 7394-2008 6.17a @ Rp. Rp.

DESIGN m2 Anl. SNI 7394-2008 6.22 @ Rp. Rp.

1.000 OH Pekerja Lain-lain @ Rp. Rp.

Jumlah Rp.

Dibulatkan Rp.

SUPLEMEN 04 : 1 m3 Balok

1.000 m3 Anl. SNI 7394-2008 6.7 @ Rp. Rp.

DESIGN kg Anl. SNI 7394-2008 6.17a @ Rp. Rp.

DESIGN m2 Anl. SNI 7394-2008 6.22 @ Rp. Rp.

1.000 OH Pekerja Lain-lain @ Rp. Rp.

Jumlah Rp.

Dibulatkan Rp.

SUPLEMEN 05 : 1 m3 Kolom

1.000 m3 Anl. SNI 7394-2008 6.7 @ Rp. Rp.

DESIGN kg Anl. SNI 7394-2008 6.17a @ Rp. Rp.

DESIGN m2 Anl. SNI 7394-2008 6.22 @ Rp. Rp.

1.000 OH Pekerja Lain-lain @ Rp. Rp.

Jumlah Rp.

Dibulatkan Rp.

SUPLEMEN 06 : 1 m3 Ring Balok

1.000 m3 Anl. SNI 7394-2008 6.7 @ Rp. Rp.

DESIGN kg Anl. SNI 7394-2008 6.17a @ Rp. Rp.

DESIGN m2 Anl. SNI 7394-2008 6.23 @ Rp. Rp.

1.000 OH Pekerja Lain-lain @ Rp. Rp.

Jumlah Rp.

Dibulatkan Rp.

SUPLEMEN 07 : 1 m3 Balok Lantai

1.000 m3 Anl. SNI 7394-2008 6.7 @ Rp. Rp.

Page 116: JUKNIS PERENCANAAN 2014

DESIGN kg Anl. SNI 7394-2008 6.17a @ Rp. Rp.

DESIGN m2 Anl. SNI 7394-2008 6.23 @ Rp. Rp.

1.000 OH Pekerja Lain-lain @ Rp. Rp.

Jumlah Rp.

Dibulatkan Rp.

SUPLEMEN 08 : 1 m3 Sun Wearing/Plat Dack

1.000 m3 Anl. SNI 7394-2008 6.7 @ Rp. Rp.

DESIGN kg Anl. SNI 7394-2008 6.17a @ Rp. Rp.

DESIGN m2 Anl. SNI 7394-2008 6.24 @ Rp. Rp.

1.000 OH Pekerja Lain-lain @ Rp. Rp.

Jumlah Rp.

Dibulatkan Rp.

SNI.03-3436-2002 (6.32) : 1 M2 Atap Seng Genteng 0.25

: Bahan

1.020 Lbr Seng Genteng 0.25 @ Rp. 90,000.00 Rp. 91,800.00

0.200 kg Paku Khusus Seng Genteng @ Rp. 21,000.00 Rp. 4,200.00

: Tenaga Kerja

0.200 OH Pekerja @ Rp. 60,000.00 Rp. 12,000.00

0.100 OH Tukang @ Rp. 80,000.00 Rp. 8,000.00

0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00

0.001 OH Mandor @ Rp. 75,000.00 Rp. 75.00

Jumlah Rp. 117,075.00

Dibulatkan Rp. 117,075.00

SNI.03-3436-2002 (6.36) : 1 M2 Bubungan Seng Genteng

: Bahan

1.100 Lbr Bubungan Seng Genteng @ Rp. 58,000.00 Rp. 63,800.00

0.050 kg Paku Khusus Seng Genteng @ Rp. 21,000.00 Rp. 1,050.00

: Tenaga Kerja

0.250 OH Pekerja @ Rp. 60,000.00 Rp. 15,000.00

0.150 OH Tukang @ Rp. 80,000.00 Rp. 12,000.00

0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00

0.013 OH Mandor @ Rp. 75,000.00 Rp. 975.00

Jumlah Rp. 94,325.00

Dibulatkan Rp. 94,325.00

SNI.03-2838-2002 6 - h : 1 M2 Pengecatan Bidang Kayu Baru (1 Lapis Plamir), 1 Lapis Cat Dasar, 2 Lapis Penutup

: Bahan

0.200 kg Cat Meni @ Rp. 32,200.00 Rp. 6,440.00

0.150 kg Plamir @ Rp. 35,000.00 Rp. 5,250.00

0.170 kg Cat Dasar @ Rp. 25,200.00 Rp. 4,284.00

0.260 kg Cat Penutup @ Rp. 56,000.00 Rp. 14,560.00

: Tenaga Kerja

0.250 OH Pekerja @ Rp. 60,000.00 Rp. 15,000.00

0.150 OH Tukang @ Rp. 80,000.00 Rp. 12,000.00

0.015 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,500.00

0.013 OH Mandor @ Rp. 75,000.00 Rp. 975.00

Jumlah Rp. 60,009.00

Dibulatkan Rp. 60,009.00

SNI.03-2838-2002 6 - 1 : 1 M2 Pengecatan Bidang Kayu Baru (1 Lapis Plamir), 1 Lapis Cat Dasar, 3 Lapis Penutup

: Bahan

Page 117: JUKNIS PERENCANAAN 2014

0.200 kg Cat Meni @ Rp. 32,200.00 Rp. 6,440.00

0.150 kg Plamir @ Rp. 35,000.00 Rp. 5,250.00

0.170 kg Cat Dasar @ Rp. 25,200.00 Rp. 4,284.00

0.350 kg Cat Penutup @ Rp. 56,000.00 Rp. 19,600.00

: Tenaga Kerja

0.070 OH Pekerja @ Rp. 60,000.00 Rp. 4,200.00

0.105 OH Tukang @ Rp. 80,000.00 Rp. 8,400.00

0.004 OH Kepala Tukang @ Rp. 100,000.00 Rp. 400.00

0.003 OH Mandor @ Rp. 75,000.00 Rp. 225.00

Jumlah Rp. 48,799.00

Dibulatkan Rp. 48,799.00

SNI.03-2838-2002 6 - 1 : 1 M2 Pelaburan Bidang kayu Dengan cat Residu dan Ter

: Bahan

0.200 Liter Residu atau ter @ Rp. 7,000.00 Rp. 1,400.00

: Tenaga Kerja

0.070 OH Pekerja @ Rp. 60,000.00 Rp. 4,200.00

0.105 OH Tukang @ Rp. 80,000.00 Rp. 8,400.00

0.004 OH Kepala Tukang @ Rp. 100,000.00 Rp. 400.00

0.003 OH Mandor @ Rp. 75,000.00 Rp. 225.00

Jumlah Rp. 14,625.00

Dibulatkan Rp. 14,625.00

SNI.03-2838-2002 6 - n : 1 M2 Pengecatan tembok baru (1 Lapis Plamir, 1 Lapis Cata Dasar, 2 lapis Cat penutup)

: Bahan

0.100 kg Plamir @ Rp. 35,000.00 Rp. 3,500.00

0.100 kg Cat dasar @ Rp. 30,800.00 Rp. 3,080.00

0.260 kg Cat Penutup @ Rp. 24,640.00 Rp. 6,406.40

: Tenaga Kerja

0.020 OH Pekerja @ Rp. 60,000.00 Rp. 1,200.00

0.063 OH Tukang @ Rp. 80,000.00 Rp. 5,040.00

0.006 OH Kepala Tukang @ Rp. 100,000.00 Rp. 600.00

0.003 OH Mandor @ Rp. 75,000.00 Rp. 225.00

Jumlah Rp. 20,051.40

Dibulatkan Rp. 20,051.00

SNI.03-2838-2002 6 - t1 : 1 M2 Pengecatan Manie

: Bahan

0.100 kg Cat Manie Besi @ Rp. 32,200.00 Rp. 3,220.00

0.010 Bh Kuas @ Rp. 7,865.00 Rp. 78.65

: Tenaga Kerja

0.020 OH Pekerja @ Rp. 60,000.00 Rp. 1,200.00

0.200 OH Tukang @ Rp. 80,000.00 Rp. 16,000.00

0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00

0.010 OH Mandor @ Rp. 75,000.00 Rp. 750.00

Jumlah (1) Jumlah Rp. 23,248.65

: Tenaga Kerja

0.620 OH Pekerja @ Rp. 60,000.00 Rp. 37,200.00

0.350 OH Tukang @ Rp. 80,000.00 Rp. 28,000.00

0.035 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,500.00

0.030 OH Mandor @ Rp. 75,000.00 Rp. 2,250.00

Jumlah (2) Jumlah Rp. 70,950.00

Jumlah (1+2) Dibulatkan Rp. 94,198.65

Page 118: JUKNIS PERENCANAAN 2014

USULAN PERUBAHAN DAFTAR HARGA SATUAN BAHAN BANGUNAN

DALAM KOTA LHOKSEUMAWEBAGIAN XI. KELOMPOK BAHAN-BAHAN BANGUNAN

DALAM KEPUTUSAN WALIKOTA LHOKSEUMAWE NOMOR: 598 TAHUN 2013;

TANGGAL: 26 AGUSTUS 2013

No Uraian Jenis Harga Sebelumnya

Rp. Rp.

1 27 Batu Bata 520.00 570.00 2 46 Bensin (Industri) 10,000.00 13,700.00 3 171 Kerikil Bersih 143,000.00 220,000.00 4 223 Multipleks 9 mm 13,650.00 136,500.00

5 - 15,800.00

Lhokseumawe, 18 Februari 2014Mengetahui/Menyetujui Dibuat oleh

Kabid Program dan Perencanaan Pj. Kasi Perencanaan Teknis

Dinas Pekerjaan Umum Dinas Pekerjaan Umum

Kota Lhokseumawe Kota Lhokseumawe

Tuti Indriani, ST, MM Said Ihsan, ST, M.ScNIP. 19680614 199703 2 002 NIP. 19770513 200504 1 001

Nomor Urut Dalam Lampiran Peraturan

Walikota

Usulan Koreksi (Harga Baru)

Solar Non Subsidi (Industri)

Page 119: JUKNIS PERENCANAAN 2014

SNI 7393:2008

untuk konstruksi bangunan gedung dan perumahan

Tata cara perhitungan harga satuan pekerjaan besi dan alumunium

Page 120: JUKNIS PERENCANAAN 2014

Anl. SNI 7393-2008 6.11 Kg Memasang Besi Profil: Bahan

1.150 Kg Baja Profil) @ Rp. 14,000.00 Rp. 16,100.00 : Tenaga Kerja

0.060 OH Pekerja @ Rp. 70,000.00 Rp. 4,200.00 0.060 OH Tukang Las Konstruksi @ Rp. 80,000.00 Rp. 4,800.00 0.006 OH Kepala Tukang @ Rp. 100,000.00 Rp. 600.00 0.003 OH Mandor @ Rp. 80,000.00 Rp. 240.00

Jumlah Rp. 25,940.00 Dibulatkan Rp. 25,940.00

Anl. SNI 7393-2008 6.21 Kg Memasang Rangka Kuda - Kuda Baja IWF: Bahan

1.150 Kg Besi Baja IWF @ Rp. #N/A Rp. #N/A: Tenaga Kerja

0.060 OH Pekerja @ Rp. 70,000.00 Rp. 4,200.00 0.060 OH Tukang Las Konstruksi @ Rp. 80,000.00 Rp. 4,800.00 0.006 OH Kepala Tukang @ Rp. 100,000.00 Rp. 600.00 0.003 OH Mandor @ Rp. 80,000.00 Rp. 240.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. SNI 7393-2008 6.3100 Kg Mengerjakan Pekerjaan Perakitan: Bahan

1.000 Liter Solar (industri) @ Rp. 15,800.00 Rp. 15,800.00 0.100 Liter Minyak Pelumas @ Rp. 48,000.00 Rp. 4,800.00

: Tenaga Kerja0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00 0.100 OH Tukang Besi Konstruksi @ Rp. 80,000.00 Rp. 8,000.00 0.001 OH Kepala Tukang @ Rp. 100,000.00 Rp. 100.00 0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

: Alat0.800 Jam Sewa Alat @ Rp. #N/A Rp. #N/A

Jumlah Rp. #VALUE!Dibulatkan Rp. #VALUE!

Anl. SNI 7393-2008 6.41 M2 Membuat Pintu Besi Plat Baja Tebal 2 Mm Rangkap, Rangka Baja Siku: Bahan

15.000 Kg Besi Siku L.30.30.3 @ Rp. #N/A Rp. #N/A32.800 Kg Besi Plat Baja @ Rp. #N/A Rp. #N/A0.050 Kg Kawat Las @ Rp. #N/A Rp. #N/A

: Tenaga Kerja1.050 OH Pekerja @ Rp. 70,000.00 Rp. 73,500.00 1.050 OH Tukang Las Biasa @ Rp. #N/A Rp. #N/A0.105 OH Kepala Tukang @ Rp. 100,000.00 Rp. 10,500.00 0.052 OH Mandor @ Rp. 80,000.00 Rp. 4,160.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. SNI 7393-2008 6.510 Cm Mengerjakan Pengelasan Dengan Las Listrik: Bahan

0.400 Kg Kawat Las Listrik @ Rp. #N/A Rp. #N/A0.300 Liter Solar (industri) @ Rp. 15,800.00 Rp. 4,740.00 0.040 Liter Minyak Pelumas @ Rp. 48,000.00 Rp. 1,920.00

: Tenaga Kerja0.040 OH Pekerja @ Rp. 70,000.00 Rp. 2,800.00 0.020 OH Tukang Besi Konstruksi @ Rp. 80,000.00 Rp. 1,600.00 0.002 OH Kepala Tukang @ Rp. 100,000.00 Rp. 200.00 0.002 OH Mandor @ Rp. 80,000.00 Rp. 160.00

: Alat0.170 Jam Sewa Alat @ Rp. #N/A Rp. #N/A

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Page 121: JUKNIS PERENCANAAN 2014

Anl. SNI 7393-2008 6.61 M2 Membuat Rangka Jendela Besi Scuare Tube (25 x 5) Cm: Bahan

4.760 M Besi Square Tube @ Rp. #N/A Rp. #N/A4.522 M Besi Lis Kaca (1 x 1) Cm @ Rp. #N/A Rp. #N/A

20.000 Cm Pengelasan @ Rp. : Tenaga Kerja #N/A Rp. #N/A

0.650 OH Pekerja @ Rp. 70,000.00 Rp. 45,500.00 0.650 OH Tukang Las Biasa @ Rp. #N/A Rp. #N/A0.065 OH Kepala Tukang @ Rp. 100,000.00 Rp. 6,500.00 0.032 OH Mandor @ Rp.Jumlah Rp. #N/A

Dibulatkan Rp. #N/A

Anl. SNI 7393-2008 6.71 M2 Memasang Pintu Rolling Door Besi: Bahan

1.000 M2 Pintu Gulung Besi @ Rp. #N/A Rp. #N/A: Tenaga Kerja @ Rp. #N/A Rp. #N/A

1.200 OH Pekerja @ Rp. 70,000.00 Rp. 84,000.00 1.200 OH Tukang Las Biasa @ Rp. #N/A Rp. #N/A0.120 OH Kepala Tukang 0.006 OH Mandor @ Rp. 80,000.00 Rp. 480.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. SNI 7393-2008 6.81 M2 Memasang Pintu Lipat ( Folding Door) Bahan Plastik / PVC: Bahan

1.000 M2 Pintu Lipat @ Rp. #N/A Rp. #N/A: Tenaga Kerja @ Rp. #N/A Rp. #N/A

0.440 OH Pekerja @ Rp. 70,000.00 Rp. 30,800.00 0.440 OH Tukang @ Rp. 80,000.00 Rp. 35,200.00 0.044 OH Kepala Tukang 0.022 OH Mandor @ Rp. 80,000.00 Rp. 1,760.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. SNI 7393-2008 6.91 M2 Memasang Sunscreen Allumunium: Bahan

1.000 M2 Sunsreen Allumunium @ Rp. #N/A Rp. #N/A: Tenaga Kerja @ Rp. #N/A Rp. #N/A

0.080 OH Pekerja @ Rp. 70,000.00 Rp. 5,600.00 0.800 OH Tukang @ Rp. 80,000.00 Rp. 64,000.00 0.080 OH Kepala Tukang 0.004 OH Mandor @ Rp. 80,000.00 Rp. 320.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. SNI 7393-2008 6.101 M2 Memasang Rolling Door Allumunium: Bahan

1.000 M2 Rolling Door Allumunium @ Rp. #N/A Rp. #N/A: Tenaga Kerja @ Rp. #N/A Rp. #N/A

1.000 OH Pekerja @ Rp. 70,000.00 Rp. 70,000.00 1.000 OH Tukang Khusus Allumunium @ Rp. #N/A Rp. #N/A0.100 OH Kepala Tukang 0.050 OH Mandor @ Rp. 80,000.00 Rp. 4,000.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. SNI 7393-2008 6.111 M2 Memasang Kusen Pintu Allumunium: Bahan

1.100 M Profil Allumunium @ Rp. #N/A Rp. #N/A2.000 Buah Skrup Fixer @ Rp. #N/A Rp. #N/A0.060 Tube Sealant @ Rp. #N/A Rp. #N/A

: Tenaga Kerja @ Rp. #N/A Rp. #N/A0.043 OH Pekerja @ Rp. 70,000.00 Rp. 3,010.00 0.043 OH Tukang Khusus Allumunium @ Rp. #N/A Rp. #N/A

0.0043 OH Kepala Tukang 0.0021 OH Mandor @ Rp. 80,000.00 Rp. 168.00

Page 122: JUKNIS PERENCANAAN 2014

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Page 123: JUKNIS PERENCANAAN 2014

Anl. SNI 7393-2008 6.121 M2 Memasang Pintu Allumunium Strip Lebar 8 Cm: Bahan

4.400 M Profil Allumunium @ Rp. #N/A Rp. #N/A14.600 M Allumunium Strip @ Rp. #N/A Rp. #N/A

: Tenaga Kerja @ Rp. #N/A Rp. #N/A0.085 OH Pekerja @ Rp. 70,000.00 Rp. 5,950.00 0.085 OH Tukang Khusus Allumunium @ Rp. #N/A Rp. #N/A

0.0085 OH Kepala Tukang 0.0042 OH Mandor @ Rp. 80,000.00 Rp. 336.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. SNI 7393-2008 6.131 M2 Memasang Pintu Kaca Rangka Allumunium : Bahan

4.400 M Pintu Allumunium @ Rp. #N/A Rp. #N/A4.500 M Profil Kaca @ Rp. #N/A Rp. #N/A0.270 Tube Sealant @ Rp. #N/A Rp. #N/A

: Tenaga Kerja @ Rp. #N/A Rp. #N/A0.085 OH Pekerja @ Rp. 70,000.00 Rp. 5,950.00 0.085 OH Tukang Allumunium / Kaca @ Rp. #N/A Rp. #N/A0.009 OH Kepala Tukang 0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. SNI 7393-2008 6.151 M2 Memasang Teralis Besi Strip (2 x 3 ) Mm: Bahan

6.177 Kg Besi Strip @ Rp. #N/A Rp. #N/A27.080 Cm Pengelasan @ Rp. #N/A Rp. #N/A

: Tenaga Kerja @ Rp. #N/A Rp. #N/A1.670 OH Pekerja @ Rp. 70,000.00 Rp. 116,900.00 1.670 OH Tukang Las @ Rp. #N/A Rp. #N/A0.167 OH Kepala Tukang 0.083 OH Mandor @ Rp. 80,000.00 Rp. 6,640.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. SNI 7393-2008 6.161 M2 Memasang Kawat Nyamuk: Bahan

1.100 M2 Kawat Nyamuk @ Rp. #N/A Rp. #N/A11.110 Cm Pengelasan @ Rp. #N/A Rp. #N/A1.716 KG Baja Strip (0,2 x 2 ) Cm @ Rp. #N/A Rp. #N/A

: Tenaga Kerja @ Rp. #N/A Rp. #N/A0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00 0.100 OH Tukang @ Rp. 80,000.00 Rp. 8,000.00 0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00 0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. SNI 7393-2008 6.171 M2 Memasang Jendela Nako Dan Tralis: Bahan

1.100 M2 Jendela Nako (Rangka + Kaca 5 M@ Rp. #N/A Rp. #N/A10.000 Buah Paku Sekrup @ Rp. 32,500.00 Rp. 325,000.00 7.000 M Besi Strip @ Rp. #N/A Rp. #N/A

: Tenaga Kerja0.200 OH Pekerja @ Rp. 70,000.00 Rp. 14,000.00 0.200 OH Tukang @ Rp. 80,000.00 Rp. 16,000.00 0.020 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,000.00 0.010 OH Mandor @ Rp. 80,000.00 Rp. 800.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Page 124: JUKNIS PERENCANAAN 2014

Anl. SNI 7393-2008 6.181 M Memasang Talang Datar / Jurai Seng BJLS 28 Lebar 90 CM: Bahan

1.050 M Seng Plat @ Rp. #N/A Rp. #N/A0.015 Kg Paku 1 Cm - 2,5 Cm @ Rp. #N/A Rp. #N/A0.019 M3 Papan Kayu Kelas II Atau III @ Rp. #N/A Rp. #N/A

: Tenaga Kerja0.200 OH Pekerja @ Rp. 70,000.00 Rp. 14,000.00 0.400 OH Tukang @ Rp. 80,000.00 Rp. 32,000.00 0.025 OH Kepala Tukang @ Rp. 100,000.00 Rp. 2,500.00 0.010 OH Mandor @ Rp. 80,000.00 Rp. 800.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. SNI 7393-2008 6.181 M Memasang Talang 1/2 Lingkaran D - 15 Cm, Seng Plat BJLS 30 Lebar 45 Cm: Bahan

1.050 M Seng Plat @ Rp. #N/A Rp. #N/A0.010 Kg Paku 1 Cm - 2,5 Cm @ Rp. #N/A Rp. #N/A0.500 Kg Besi Strip @ Rp. #N/A Rp. #N/A

: Tenaga Kerja0.150 OH Pekerja @ Rp. 70,000.00 Rp. 10,500.00 0.300 OH Tukang @ Rp. 80,000.00 Rp. 24,000.00 0.030 OH Kepala Tukang @ Rp. 100,000.00 Rp. 3,000.00 0.008 OH Mandor @ Rp. 80,000.00 Rp. 640.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Page 125: JUKNIS PERENCANAAN 2014

SNI 2839:2008

untuk konstruksi bangunan gedung dan perumahan

Tata cara perhitungan harga satuan pekerjaan langit - langit

Page 126: JUKNIS PERENCANAAN 2014

Anl. SNI 2839-2008 6.11 M2 Memasang Langit - Langit Asbes Semen, Tebal 4 mm, 5 mm, dan 6 mm: Bahan

1.100 M2 Asbes Eternit 1 x 1 m @ Rp. 22,000.00 Rp. 24,200.00 0.010 Kg Paku Asbes @ Rp. 16,900.00 Rp. 169.00

: Tenaga Kerja0.030 OH Pekerja @ Rp. 70,000.00 Rp. 2,100.00 0.070 OH Tukang Kayu @ Rp. 80,000.00 Rp. 5,600.00 0.007 OH Kepala Tukang @ Rp. 100,000.00 Rp. 700.00 0.004 OH Mandor @ Rp. 80,000.00 Rp. 320.00

Jumlah Rp. 32,920.00 Dibulatkan Rp. 32,920.00

Anl. SNI 2839-2008 6.21 M2 Memasang Langit - Langit Akustik Ukuran ( 30 x 30 ) Cm: Bahan

12.000 Lembar Akustik @ Rp. #N/A Rp. #N/A0.050 Kg Paku Asbes @ Rp. 16,900.00 Rp. 845.00

: Tenaga Kerja0.120 OH Pekerja @ Rp. 70,000.00 Rp. 8,400.00 0.120 OH Tukang Kayu @ Rp. 80,000.00 Rp. 9,600.00 0.012 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,200.00 0.006 OH Mandor @ Rp. 80,000.00 Rp. 480.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. SNI 2839-2008 6.31 M2 Memasang Langit - Langit Akustik Ukuran ( 30 x 60 ) Cm: Bahan

12.000 Lembar Akustik @ Rp. #N/A Rp. #N/A0.050 Kg Paku Asbes @ Rp. 16,900.00 Rp. 845.00

: Tenaga Kerja0.120 OH Pekerja @ Rp. 70,000.00 Rp. 8,400.00 0.120 OH Tukang Kayu @ Rp. 80,000.00 Rp. 9,600.00 0.012 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,200.00 0.006 OH Mandor @ Rp. 80,000.00 Rp. 480.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. SNI 2839-2008 6.41 M2 Memasang Langit - Langit Akustik Ukuran ( 60 x 120 ) Cm: Bahan

1.500 Lembar Akustik @ Rp. #N/A Rp. #N/A0.050 Kg Paku Asbes @ Rp. 16,900.00 Rp. 845.00

: Tenaga Kerja0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00 0.100 OH Tukang Kayu @ Rp. 80,000.00 Rp. 8,000.00 0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00 0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Page 127: JUKNIS PERENCANAAN 2014

Anl. SNI 2839-2008 6.51 M2 Memasang Langit - Langit Triplek Ukuran ( 120 x 240 ) cm, Tebal 3 mm, 4 mm, dan 6 mm: Bahan

0.375 Lembar Triplek @ Rp. #N/A Rp. #N/A0.030 Kg Paku Asbes @ Rp. 16,900.00 Rp. 507.00

: Tenaga Kerja0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00 0.100 OH Tukang Kayu @ Rp. 80,000.00 Rp. 8,000.00 0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00 0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. SNI 2839-2008 6.5.a1 M2 Memasang Langit - Langit Triplek Ukuran ( 120 x 240 ) cm, Tebal 3 mm: Bahan

0.375 Lembar Multipleks 3 mm @ Rp. 58,500.00 Rp. 21,937.50 0.030 Kg Paku Asbes @ Rp. 16,900.00 Rp. 507.00

: Tenaga Kerja0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00 0.100 OH Tukang Kayu @ Rp. 80,000.00 Rp. 8,000.00 0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00 0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. 38,337.50 Dibulatkan Rp. 38,337.00

Anl. SNI 2839-2008 6.5.b1 M2 Memasang Langit - Langit Triplek Ukuran ( 120 x 240 ) cm, Tebal 4 mm: Bahan

0.375 Lembar Multipleks 4 mm @ Rp. 71,500.00 Rp. 26,812.50 0.030 Kg Paku Asbes @ Rp. 16,900.00 Rp. 507.00

: Tenaga Kerja0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00 0.100 OH Tukang Kayu @ Rp. 80,000.00 Rp. 8,000.00 0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00 0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. 43,212.50 Dibulatkan Rp. 43,212.00

Anl. SNI 2839-2008 6.5.b1 M2 Memasang Langit - Langit Triplek Ukuran ( 120 x 240 ) cm, Tebal 6 mm: Bahan

0.375 Lembar Multipleks 6 mm @ Rp. 97,500.00 Rp. 36,562.50 0.030 Kg Paku Asbes @ Rp. 16,900.00 Rp. 507.00

: Tenaga Kerja0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00 0.100 OH Tukang Kayu @ Rp. 80,000.00 Rp. 8,000.00 0.010 OH Kepala Tukang @ Rp. 100,000.00 Rp. 1,000.00 0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. 52,962.50 Dibulatkan Rp. 52,962.00

Page 128: JUKNIS PERENCANAAN 2014

Anl. SNI 2839-2008 6.61 M2 Memasang Langit - Langit Lambrizing Kayu, Tebal 9 mm: Bahan

0.015 M3 Kayu Papan @ Rp. #N/A Rp. #N/A0.010 Kg Paku Asbes @ Rp. 16,900.00 Rp. 169.00

: Tenaga Kerja0.800 OH Pekerja @ Rp. 70,000.00 Rp. 56,000.00 0.800 OH Tukang Kayu @ Rp. 80,000.00 Rp. 64,000.00 0.080 OH Kepala Tukang @ Rp. 100,000.00 Rp. 8,000.00 0.040 OH Mandor @ Rp. 80,000.00 Rp. 3,200.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. SNI 2839-2008 6.71 M2 Memasang Langit - Langit Gypsum Board Ukuran ( 1200 x 2400 x 9 ) mm: Bahan

0.364 M3 @ Rp. 96,200.00 Rp. 35,016.80

0.110 Kg Paku Sekrup @ Rp. 32,500.00 Rp. 3,575.00 : Tenaga Kerja

0.100 OH Pekerja @ Rp. 70,000.00 Rp. 7,000.00 0.050 OH Tukang Kayu @ Rp. 80,000.00 Rp. 4,000.00 0.005 OH Kepala Tukang @ Rp. 100,000.00 Rp. 500.00 0.005 OH Mandor @ Rp. 80,000.00 Rp. 400.00

Jumlah Rp. 46,916.80 Dibulatkan Rp. 46,916.00

Anl. SNI 2839-2008 6.81 M Memasang List Plafond Gypsum Profil: Bahan

1.050 M List Gypsum Profil @ Rp. #N/A Rp. #N/A0.150 Kg Tepung Gypsum @ Rp. #N/A Rp. #N/A

: Tenaga Kerja0.060 OH Pekerja @ Rp. 70,000.00 Rp. 4,200.00 0.060 OH Tukang Kayu @ Rp. 80,000.00 Rp. 4,800.00 0.006 OH Kepala Tukang @ Rp. 100,000.00 Rp. 600.00 0.003 OH Mandor @ Rp. 80,000.00 Rp. 240.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Anl. SNI 2839-2008 6.91 M2 Memasang Langit - Langit Akustik Ukuran (60 x 120 ) Cm + Rangka Allumunium: Bahan

3.600 M Profil Allumunium " T " @ Rp. #N/A Rp. #N/A0.150 Kg Kawat Diameter 4 mm @ Rp. #N/A Rp. #N/A1.050 Buah Ramset @ Rp. #N/A Rp. #N/A1.500 Lembar Akustik 60 cm x 120 cm @ Rp. #N/A Rp. #N/A

: Tenaga Kerja0.500 OH Pekerja @ Rp. 70,000.00 Rp. 35,000.00 0.500 OH Tukang Kayu @ Rp. 80,000.00 Rp. 40,000.00 0.050 OH Kepala Tukang @ Rp. 100,000.00 Rp. 5,000.00 0.025 OH Mandor @ Rp. 80,000.00 Rp. 2,000.00

Jumlah Rp. #N/ADibulatkan Rp. #N/A

Gipsum Australia ( 1,2 x 2,4 m ) T = 9 mm

Page 129: JUKNIS PERENCANAAN 2014

Anl. SNI 2839-2008 6.101 M List Langit - Langit Kayu Profil: Bahan

1.050 M List Eternit Kayu @ Rp. 7,000.00 Rp. 7,350.00 0.010 Kg Paku Kayu (2"-5") @ Rp. 17,000.00 Rp. 170.00

: Tenaga Kerja0.500 OH Pekerja @ Rp. 70,000.00 Rp. 35,000.00 0.500 OH Tukang Kayu @ Rp. 80,000.00 Rp. 40,000.00 0.050 OH Kepala Tukang @ Rp. 100,000.00 Rp. 5,000.00 0.030 OH Mandor @ Rp. 80,000.00 Rp. 2,400.00

Jumlah Rp. 89,750.00 Dibulatkan Rp. 89,750.00