KEGIATAN : PEMBANGUNAN GEDUNG KANCA (KANTOR CABANG)
PERKERJAAN : PEMBANGUNAN GEDUNG KANTOR CABANG PT. BRI (PERSERO) Tbk. LHOKSEUMAWE
LOKASI : KOTA LHOKSEUMAWE
TAHUN : 2015
1 3 4 5 6
PEKERJAAN STRUKTUR
1 Balok Praktis Lantai I
- Beton K-300 M3 0.962 1,540,000.00Rp 1,482,180.70Rp
- Besi Beton KG 257.700 15,435.00Rp 3,977,599.43Rp
- Bekisting M2 14.807 169,522.50Rp 2,510,119.66Rp
2 Tangga Utama Lantai 2
- Beton K-300 M3 3.159 1,540,000.00Rp 4,864,860.00Rp
- Besi Beton KG 392.917 15,435.00Rp 6,064,677.77Rp
- Bekisting M2 20.397 169,522.50Rp 3,457,750.43Rp
3 Beton Topi-topi Lantai I
- Beton K-300 M3 2.056 1,540,000.00Rp 3,165,624.00Rp
- Besi Beton KG 56.333 15,435.00Rp 869,493.31Rp
- Bekisting M2 25.124 169,522.50Rp 4,259,083.29Rp
4 Beton Topi-topi Lantai II
- Beton K-300 M3 2.502 1,540,000.00Rp 3,853,080.00Rp
- Besi Beton KG 68.566 15,435.00Rp 1,058,314.98Rp
- Bekisting M2 30.580 169,522.50Rp 5,183,998.05Rp
5 Beton Janggutan (Balok Teras Depan)
- Beton K-300 M3 1.320 1,540,000.00Rp 2,032,800.00Rp
- Besi Beton KG 144.432 15,435.00Rp 2,229,313.85Rp
- Bekisting M2 18.800 169,522.50Rp 3,187,023.00Rp
TOTAL 48,195,918.46Rp
Dibuat Oleh
PT. ELEKTRINDO ARTHA PRATAMA
ACHMAD NOFEL
Project Manager
BILL OF QUANTITY
Uraian Pekerjaan
2
No. Sat. VolumeHARGA SATUAN
(Rp)JUMLAH HARGA (Rp)
-
PEKERJAAN STRUKTUR
P1 P2 L1 L2 T
1 2 3 4 5 6 7 8 9 10 11 13
1 Balok Praktis Lantai I 56.95 0.13 0.13 0.962 M3
- Beton K-300 0.962 M3
- Besi Beton 257.700 Kg
- Bekisting 14.807 M2
2 Tangga Utama Lantai 2
- Plat Tangga 7.28 1.50 0.15 1.638 M3
- Plat Bordes 3.10 1.50 0.15 0.698 M3
- anak Tangga 20 0.30 1.50 0.18 0.824 M3
3.159 M3
- Beton K-300 3.159 M3
- Besi Beton 392.917 Kg
- Bekisting 20.397 M2
3 Beton Topi-topi Lantai I 45.68 0.45 0.10 2.056 M3
- Beton K-300 2.056 M3
- Besi Beton 56.333 Kg
- Bekisting 25.124 M2
4 Beton Topi-topi Lantai II 55.60 0.45 0.10 2.502 M3
- Beton K-300 2.502 M3
- Besi Beton 68.566 Kg
- Bekisting 30.580 M2
5 Beton Janggutan (Balok Teras Depan) 8.00 1.10 0.15 1.320 M3
- Beton K-300 1.320 M3
- Besi Beton 144.432 Kg
- Bekisting 18.800 M2
Volume Rumus
12
CALCULATION SHEET
No Uraian Pekerjaan Type Jumlah
(Bh)Panjang (m) Lebar (m)
Tinggi
(m)Diameter
(m)Luas (m2)