INFORMASI PELAKSANAAN KEGIATANPROVINSI BANTEN DAN METROPOLITAN JAKARTA
TAHUN ANGGARAN 2018
KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYATDIREKTORAT JENDERAL BINA MARGABALAI BESAR PELAKSANAAN JALAN NASIONAL VI
STATUS 24 JULI 2018
PETA RUAS JALAN NASIONAL
INFORMASI PAKET PEKERJAAN KONSTRUKSI TA.2018
INFORMASI PAKET TAHAPAN PROSES LELANG TA.2018
INFORMASI KEGIATAN PADAT KARYA TA.2018
O U T L I N E
INFORMASI PAKET PEKERJAAN KONSTRUKSI TA.2018PROVINSI BANTEN
NO NAMA PAKET KONTRAKTOR KONSULTANNILAI PAGU
(Rp.)
NILAI KONTRAK
(Rp.)
TANGGAL
KONTRAK
MASA
PELAKSANAAN
(HK)
RENCANA
PHOPROGRES FISIK PROGRES KEUANGAN KETERANGAN
PROVINSI BANTEN
SKPD PROVINSI BANTEN
PPK S 01 SKPD BANTEN
Rutin = 21.86 % Rutin = 22.12 %
Rutin Kondisi = 21.86 % Rutin Kondisi = 22.29 %
Rutin Jbt = 14.12 % Rutin Jbt = 20.13 %
Rehab = 39.58 % Rehab = 27.71 %
Rekon = 64.34 % Rekon = 51.64 %
2 Pemeliharaan Rehabillitasi Jembatan
Ciujung Baru
- - 2.124.000.000 - - 150 - 14,09% 17,29% - APBN
PPK S 02 SKPD BANTEN
Rutin = 24.46 % Rutin = 15.68 %
Rutin Kondisi = 24.46 % Rutin Kondisi = 29.07 %
Rutin Jbt = 21.90 % Rutin Jbt = 17.99 %
Rehab = 33.82 % Rehab = 32.30 %
Berkala Jbt = 46.07 % Berkala Jbt = 16.41 %
4 Pemeliharaan Rehabillitasi Jembatan
Cilancar Cs
- - 2.191.500.000 - - 150 - 19,98% 17,84% - APBN
SATKER PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI BANTEN
PPK 1 PJN I BANTEN
Rutin = 46.20 % Rutin = 39.17 %
Rutin Kondisi = 45.18 % Rutin Kondisi = 23.97 %
Rehab Minor = 14.43 % Rehab Minor = 19.28 %
Rehab Mayor = 64.31 % Rehab Mayor = 50.70 %
2 Rehabilitasi dan Pemeliharaan Berkala
Jembatan Ciujung Kragilan, cs
CV. Galang Putra PT.Daksinapati Karsa
Konsultindo dan KSO
1.559.146.600 1.335.514.000 2 Mar 2018 120 29 Juni 2018 100,00% 85,65% APBN
3 Pembangunan Jembatan Gantung
Cisimeut Kp. Ciparay, cs
PT. Sinatria Inti
Surya
Parama Karya Mandiri 27.968.000.000 24.985.000.000 - - - 0% 0% - APBN
- Proses Lelang
PPK 2 PJN I BANTEN
Rutin = 48.52 % Rutin = 56.54 %
Rutin Kondisi = 51.06 % Rutin Kondisi = 47.42 %
Rehab Minor = 14.46 % Rehab Minor = 27.27 %
Rehab Mayor = 48.87 % Rehab Mayor = 44.11 %
5 Rehabilitasi Jembatan Lebak Gede II, cs CV. Gunung PT.Daksinapati Karsa 1.664.215.000 1.427.732.000 2 Mar 2018 150 29 Juli 2018 98,04% 69,96% APBN
6 Penggantian Jembatan Sagarahan PT. Bangun Nusa
Raya
- 6.278.517.000 6.515.000.000 9 Juli 2018 - - 0% 0% - APBN
- Revisi pemenuhan
dana dalam DIPA
7 Pembangunan Jembatan Gantung
Gabus, cs
Sinarkarya
Porodisa
Parama Karya Mandiri 15.470.600.000 14.285.134.000 9 Juli 2018 - - 0% 0% - APBN
APBN
APBN21 Des 201825016 Apr 20189.104.905.000 Preservasi Rehabilitasi Jalan Raya
Serang (Pandeglang)-Saketi-Simpang
Labuan
17 Des 201825012 Apr 201813.172.900.000 16.193.519.000
Preservasi Rehabilitasi Jln. Abdul Hadi
(Serang) - Jln. Kh. Abdul Fatah Hasan
(Serang) - Sudirman (Serang) - Bts.
Kota Serang - Cikande - Rangkasbitung
1 APBNPT.Daksinapati Karsa
Konsultindo dan KSO
PT.Purnajasa
Bimapratama
PT.Mutiara Indah
Purnama - PT.
Bengkel Konstruksi
Mandiri, KSO
3
PT. Parama Karya
Mandiri KSO
PT. Vanca Utama
Perkasa
PT. Parama Karya
Mandiri KSO
PT. Dwi Ratna
Putra
10.820.660.000
Preservasi Rehabilitasi Batas Kota
Pandeglang-Rangkasbitung-Cigelung
1
APBN26 Des 201826 Mar 2018Preservasi Rehabilitasi Jalan Bts. Kota
Pandeglang - Serang - Cilegon dan
Serdang - Bojonegara - Merak
4
26 Des 20183002 Mar 201837.133.553.000 40.893.217.000
28.501.187.000 34.636.774.900 PT.Daksinapati Karsa
Konsultindo dan KSO
PT.Purnajasa
Bimapratama
PT. Kuala Batee
Indonesia
INFORMASI PAKET PEKERJAAN KONSTRUKSI TA.2018PROVINSI BANTEN (LANJUTAN)
NO NAMA PAKET KONTRAKTOR KONSULTANNILAI PAGU
(Rp.)
NILAI KONTRAK
(Rp.)
TANGGAL
KONTRAK
MASA
PELAKSANAAN
(HK)
RENCANA
PHOPROGRES FISIK PROGRES KEUANGAN KETERANGAN
PROVINSI BANTEN
SATKER PELAKSANAAN JALAN NASIONAL WILAYAH II PROVINSI BANTEN
PPK 1 PJN II BANTEN
1 Preservasi Jln. Raya Anyer (Cilegon)
dan Bts. Kota Cilegon - Pasauran
PT.Bangun Cipta
Azima Mandiri
- 5.648.686.000 5.167.426.000 26 Mar 2018 Rutin = 28.65 % Rutin = 37.08 % APBN
2 Preservasi dan Pelebaran Jalan
Menuju Standar Ruas Pasauran - Sp
Labuhan - Cibaliung dan Citeureup-
Tanjung Lesung
- - 50.000.000.000 - - - - 0% 0% - SBSN
- MYC
- Proses Lelang
3 Pemeliharaan Berkala Jembatan
Cipasauran dan Cipakis / TJ.Lesung
CV. Mitra Utama - 1.511.800.000 1.299.570.000 16 Mei 2018 19,87% 17,19% APBN
4 Rehabilitasi Jembatan Citeureup I Cs PT. Fast Teknologi
Indonesia
- 3.728.350.000 3.609.860.000 10 Apr 2018 58,19% 42,14% APBN
5 Penggantian Jembatan Cisoge dan
Kosambi
PT. Marga Jaya
Konstruksi
- 4.177.850.000 3.425.820.000 18 Juli 2018 - - 0% 0% APBN
6 Pembangunan Jembatan Gantung
Kampung Sukacai Cs
PT. Cimendang
Sakti Kontrakindo
- 19.221.843.000 15.762.735.000 18 Juli 2018 - - 0% 0% APBN
7 Penanganan Banjir Kota Cilegon Ruas
Cilegon-Pasauran
- - 5.000.000.000 - 0% 0% - APBN
- Usulan Baru Sisa Lelang
PPK 2 PJN II BANTEN
8 Preservasi dan Pelebaran Jalan Menuju
Standar Ruas Sumur - Cibaliung - Muara
Binuangeun
- - 50.000.000.000 - - - - 0% 0% - SBSN
- Proses Lelang
9 Paket Rehabilitasi Jembatan Kolecer 2 PT. Surya Bakti
Perkasa Utama
2.950.350.000 2.647.761.000 10 Apr 2018 19,24% 17,95% APBN
10 Penggantian Jembatan Sumur II- -
2.977.850.000 - - - -
0% 0% - APBN
- Lelang Ulang
11 Pembangunan Jembatan Gantung
Sukaseneng Cs
PT. Mutiara Indah
Purnama-
19.963.100.000 16.571.943.000 18 Juli 2018- -
0% 0% APBN
PPK 3 PJN II BANTEN
Rutin = 36.64 % Rutin = 39.26 %
Rekon = 44.01 % Rekon = 31.13 %
Pelebaran = 85.08 % Pelebaran = 43.49 %
13 Pemeliharaan Berkala Jembatan
Cikiray dan Cimadur B
PT. Restu Ibu - 3.791.850.000 3.207.091.000 16 Mei 2018 45,80% 16,92% APBN
14 Paket Rehabilitasi Jembatan
Cipanyaungan Cs
PT.Bumi Mandala
Wangi
- 4.919.850.000 4.071.966.000 16 Mei 2018 12,50% 16,55% APBN
APBNPreservasi dan Pelebaran Jalan Menuju
Standar Muara Binuangeun - Simpang -
Bts. Prov. Jabar
12 27 Mar 201817.891.881.000 21.322.680.000 PT. Sogisa Bangun
Sejahtera
-
INFORMASI PAKET PEKERJAAN KONSTRUKSI TA.2018METROPOLITAN DKI JAKARTA
NO NAMA PAKET KONTRAKTOR KONSULTANNILAI PAGU
(Rp.)
NILAI KONTRAK
(Rp.)
TANGGAL
KONTRAK
MASA
PELAKSANAAN
(HK)
RENCANA
PHOPROGRES FISIK PROGRES KEUANGAN KETERANGAN
METROPOLITAN DKI JAKARTA
SATKER PELAKSANAAN JALAN NASIONAL METROPOLITAN I JAKARTA
PPK 1 METROPOLITAN I JAKARTA
Rutin = 31.15 % Rutin = 29.54 %
Rutin Kondisi = 31.15 % Rutin Kondisi = 37.60 %
Rehab Minor = 31.15 % Rehab Minor = 21.29 %
Rehab Mayor = 31.15 % Rehab Mayor = 28.68 %
2 Pelebaran Jalan Kalimalang PT. Rekayasa
Semesta Utama
PT. Bennatin Surya
Cipta
1.477.800.000 30.254.342.000 - 180 - 0% 0% - APBN
- Proses Lelang
- Review design
- Lahan belum bebas
- Ttd Kontrak menunggu
revisi pemenuhan dana
dalam DIPA
3 Pelebaran Jalan Pekayon - Narogong
(SS JAKASETIA)
- - 8.480.500.000 - - - - 0% 0% - APBN
- Batal Lelang
4 Pembangunan Jembatan pada Jalan
Akses Muara Gembong
- - 480.500.000 - 5 Juli 2018 180 - 0% 0% - APBN
- Ttd Kontrak menunggu
revisi pemenuhan dana
dalam DIPA
PPK 2 METROPOLITAN I JAKARTA
Rutin = 58.61 % Rutin = 24.09 %
Rutin Kondisi = 58.61 % Rutin Kondisi = 34.75 %
Rehab Minor = 58.61 % Rehab Minor = 20.34 %
Rehab Mayor = 58.61 % Rehab Mayor = 69.46 %
6 Penggantian Jembatan Cileungsi A dan
B
- - 24.583.100.000 - - 540 - 0% 0% - APBN
- Proses Lelang
- Review desain
- Lahan belum bebas
7 Pembangunan Fly Over Pasir Gombong PT. Asri Karya
Lestari
PT. Seecons JO PT.
Indec Internusa
35.283.000.000 32.838.258.700 22 Nov 2018 330 16 Okt 2018 34,10% 5,56% APBN
8 Pembangunan Fly Over Martadinata
(Pamulang)
- - 11.489.400.000 - - 540 - 0% 0% - APBN
- Proses Lelang
- Izin MYC 2018-2019
belum terbit
- Perubahan pendanaan
dari APBN ke SBSN
- Revisi pemenuhan
dana dalam DIPA
18.022.231.000 PT. Seecons, JO PT.
Purnajasa
Bimapratama - PT.
Mono Hekss
PT. Lumbung
Pinayu Risqi
14.877.578.000 Paket Preservasi Rehabilitasi Jln. Tb.
Simatupang - Bts. DKI - Banten/Bts.
Depok (Ciputat-Bogor) - Jln. Trans Yogi
(Depok)
5
24.915.391.000 28.568.396.000 31 Des 2018 APBN
APBN31 Des 20182703 Juni 2018
PT. INDEC Internusa,
JO PT. Triduta
Mitraparama - PT.
Plato Isoiki
Paket Preservasi Jln. Sultan Agung -
Bts. Kota Karawang - Akses Marunda
1 PT. Saranabumi
Ekaputra
2703 Juni 2018
INFORMASI PAKET PEKERJAAN KONSTRUKSI TA.2018METROPOLITAN DKI JAKARTA (LANJUTAN)
NO NAMA PAKET KONTRAKTOR KONSULTANNILAI PAGU
(Rp.)
NILAI KONTRAK
(Rp.)
TANGGAL
KONTRAK
MASA
PELAKSANAAN
(HK)
RENCANA
PHOPROGRES FISIK PROGRES KEUANGAN KETERANGAN
METROPOLITAN DKI JAKARTA
SATKER PELAKSANAAN JALAN NASIONAL METROPOLITAN I JAKARTA
PPK 3 METROPOLITAN I JAKARTA
Rutin = 22.76 % Rutin = 16.07 %
Rutin Kondisi = 22.76 % Rutin Kondisi = 15.91 %
Rehab Minor = 22.76 % Rehab Minor = 17.86 %
Rehab Mayor = 22.76 % Rehab Mayor = 18.18 %
Rekon = 22.76 % Rekon = 16.24 %
10 Rehabilitasi/Pemeliharaan Berkala
Jembatan Cisadane A, FO Cengkareng
B, jembatan Gembong, FO Rawa Buaya,
Jembatan Cimanceuri
- - 11.922.300.560 - - - - 0% 0% - APBN
- Proses Lelang
SATKER PELAKSANAAN JALAN NASIONAL METROPOLITAN II JAKARTA
PPK 1 METROPOLITAN II JAKARTA
Rutin = 55.00 % Rutin = 37.20 %
Rutin Kondisi = 26.60 % Rutin Kondisi = 22.85 %
Rehab Minor = 91.00 % Rehab Minor = 50.59 %
Rehab Mayor = 82.00 % Rehab Mayor = 27.43 %
PPK 2 METROPOLITAN II JAKARTA
Rutin = 30.80 % Rutin = 13.13 %
Rutin Kondisi = 25 % Rutin Kondisi = 16.25 %
Rehab Minor = 18.42 % Rehab Minor = 18.42 %
Rehab Mayor = 25 % Rehab Mayor = 19.86 %
3 Pembangunan Fly Over Martadinata
(Bogor) (UMYC)
- - 44.977.600.000 - - - - 0% 0% - APBN
- Proses Lelang
- Lahan belum bebas
- DED dan EE belum ada
- Persetujuan MYC
belum ada
4 Penanganan Pasca Bencana Longsor
Ruas Cigelung (Bts.Prov.Banten)-Bts.
Kota Jasinga
- - 15.000.000.000 - - - - 0% 0% - APBN
- Usulan Baru Sisa Lelang
PPK 3 METROPOLITAN II JAKARTA
Rutin = 46.60 % Rutin = 34.74 %
Rutin Kondisi = 43.90 % Rutin Kondisi = 32.30 %
Rehab Minor = 89.00 % Rehab Minor = 21.65 %
Rehab Mayor = 43.40 % Rehab Mayor = 19.71 %
Rekon = 84.60 % Rekon = 44.82 %
5 Duplikasi Jembatan Gadog (Ciawi -
Puncak)
PT. Bumi Duta
Persada
PT. Daya Creasi
Mitrayasa
21.073.056.000 11.482.249.000 8 Juni 2018 16,82% 16,82% APBN
6 Penanganan Pasca Bencana Longsor
Gunung Mas dan Riung Gunung
PT. Lamna-
19.500.000.000 17.936.280.000 8 Juni 2018 86,40% 18,45% APBN
7 Pelebaran Jalan Ciawi - Puncak - - 85.000.000.000 - - - - 0% 0% APBN
APBN21 Des 20182606 Apr 2018Preservasi Rehabilitasi Ciawi - Puncak -
Bts.Kota Cianjur - Benda
PT. Lumbung
Pinayu Risqi
4 23.656.218.000 23.656.218.000 PT. Daya Creasi
Mitrayasa
22.461.254.000 Preservasi Rehabilitasi Cigelung
(Bts.Prov.Banten) - Bts.Kota Jasinga -
Bts.Kota Leuwiliang - Bts.Kota Bogor
2 22.461.254.000 PT.NusveyPT. Mutiara Indah
Purnama
PT. Wesitan
Konsultasi
Pembangunan
PT. Saranabumi
Ekaputra
1 Preservasi Rehabilitasi
Cilodong/Bts.Depok - Bts.Kota Bogor -
Jl.Sawangan Raya (Depok)
19.832.575.000 19.832.575.000 APBN
APBN26 Des 20182609 Apr 2018
21 Des 20182606 Apr 2018
9 27.162.627.000 PT. Wahana Mitra
Amerta, JO PT. hi-way
Indotek konsultan,
PT. Ciriatama
Nusawidya Consult,
PT. Esti Yasagama
PT. Mastic Utama
Sarana
APBN31 Des 20182703 Juni 2018 22.694.104.000 Paket Preservasi rehabilitasi Jln.
Lingkar Barat - Bts. Kota Serang - Bts.
Kota Karawang
INFORMASI PAKET TAHAPAN PROSES LELANGTA.2018
NO PAKET PEKERJAANJENIS
KONTRAK
NILAI PAGU
(Rp.)TAHAPAN LELANG
SATKER PELAKSANAAN JALAN NASIONAL METROPOLITAN I JAKARTA
1 Pelebaran Jalan Pekayon - Narogong (SS JAKASETIA) Tahunan 8.480.500.000 Batal Lelang
2 Rehabilitasi Jembatan Cisadane A, Flyover Cengkareng B, Jembatan Pasar
Gembong, Flyover Rawa Buaya B, Jembatan Cimanceuri
Tahunan 11.922.300.000 - Tahap Masa Sanggah
- Rencana kontrak 3 Agustus 2018
3 Penggantian Jembatan Kali Cileungsi A dan B (MYC) Tahunan 24.583.100.000 - Evaluasi penawaran
- Rencana kontrak 23 Agustus 2018
4 Pembangunan Fly Over Martadinata (Pamulang) (UMYC) MYC 11.489.400.000 - Tahap Upload Dokumen Penawaran
- Rencana kontrak 24 Agustus 2018
SATKER PELAKSANAAN JALAN NASIONAL METROPOLITAN II JAKARTA
1 Pembangunan Fly Over Martadinata (Bogor) (UMYC) MYC 44.977.600.000 - Tahap Pembuktian Kualifikasi
- Rencana kontrak 28 Oktober 2018
2 Pelebaran Jalan Ciawi - Puncak MYC 85.000.000.000 - Tahap Upload Dokumen
Prakualifikasi
- Rencana kontrak 2 November 2018
SATKER PELAKSANAAN JALAN NASIONAL WILAYAH II PROVINSI BANTEN
1 Preservasi dan Pelebaran Jalan Menuju Standar Ruas Pasauran - Sp Labuhan -
Cibaliung dan Citeureup-Tanjung Lesung
MYC 50.000.000.000 - Menunggu rekomendasi ULP
- Rencana kontrak 7 Agustus 2018
4 Preservasi dan Pelebaran Jalan Menuju Standar Ruas Sumur - Cibaliung - Muara
Binuangeun
MYC 50.000.000.000 - Proses penetapan Menteri
- Rencana kontrak 7 Agustus 2018
5 Penggantian Jembatan Sumur II Tahunan 2.977.850.000 - Lelang Ulang
289.430.750.000 TOTAL
INFORMASI KEGIATAN PADAT KARYA TA.2018PROVINSI BANTEN
Fisik FisikPendam
pingUpah
(Rp Ribu) (%) (%) (Rp Ribu) (Rp Ribu) (Rp Ribu) (Rp Ribu) (%)(Rp
Ribu)(%) (Rp Ribu) (%) Renc Real Renc Real
PELAKSANAAN JALAN NASIONAL WILAYAH I
PROVINSI BANTEN
1 11.1 PRESERVASI REHABILITASI JLN. ABDUL HADI
(SERANG) - JLN. KH. ABDUL FATAH HASAN
(SERANG) - SUDIRMAN (SERANG) - BTS.
KOTA SERANG - CIKANDE - RANGKASBITUNG
(PEMELIHARAAN RUTIN)
16 Km BANTEN KOTA SERANG 927.457 363.273 39,17 41,0 131.871 - 795.586 126.224 95,72 - - 237.049 29,80 45 45 4.680 4.680
2 23.00 PEMELIHARAAN RUTIN TRANSISI JALAN
SATKER PJN I BANTEN
1 LS BANTEN KOTA
TANGERANG
3.012.484 3.010.983 100,0 100,0 298.026 - 189.280 298.026 100,00 - - 189.280 100,00 26 24 1.872 738
3 24.1 PRESERVASI REHABILITASI JALAN BTS.
KOTA PANDEGLANG - SERANG - CILEGON
DAN SERDANG - BOJONEGARA - MERAK
(PEMELIHARAAN RUTIN)
32 Km BANTEN KAB.
PANDEGLANG
3.192.528 1.804.909 56,54 41,02 689.376 - 2.503.152 508.332 73,74 - - 1.296.557 51,80 50 50 3.900 3.900
7.132.469 5.179.165 195,7 182,0 1.119.273 - 3.488.018 932.582 269,46 - - 1.722.886 181,60 121 119 10.452 9.318
PELAKSANAAN JALAN NASIONAL WILAYAH
II PROVINSI BANTEN
1 1.2 Pemeliharaan Rutin Jalan Ruas Pasauran-
Sp.Labuan-Cibaliung dan Citeureup Tanjung
Lesung (PN)
69 Km BANTEN KAB.
PANDEGLANG
4.037.903 - - - 457.296 - 337.253 - - - - - - 20 - 2.000 -
2 33.1 Preservasi Jln. Raya Anyer (Cilegon) dan Bts.
Kota Cilegon - Pasauran
42 Km BANTEN KAB. SERANG 5.648.686 1.033.485 18,30 24,76 233.428 - 606.312 102.232 43,80 - - 113.484 18,72 46 46 7.218 1.351
9.686.589 1.033.485 18,3 24,8 690.724 - 943.565 102.232 43,80 - - 113.484 18,72 66 46 9.218 1.351 TOTAL
No Kode Satker/Paket
TOTAL
4498603
4498604
Pagu
Vol Sat
Output Lokasi Paket
Pagu
(Rp Ribu)Kec
Kel/
Des
Hari Orang Kerja
(Hari)
Tenaga Kerja
(Orang)
Realisasi
Realisasi
Prov Kab/ Kota
FisikPendam
pingUpah
Alokasi Padat Karya
INFORMASI KEGIATAN PADAT KARYA TA.2018METROPOLITAN DKI JAKARTA
Fisik FisikPendam
pingUpah
(Rp Ribu) (%) (%) (Rp Ribu) (Rp Ribu) (Rp Ribu) (Rp Ribu) (%)(Rp
Ribu)(%) (Rp Ribu) (%) Renc Real Renc Real
PELAKSANAAN JALAN NASIONAL
METROPOLITAN I JAKARTA
1 10.1 Preservasi Rehabilitasi Jln. Sultan Agung - Bts.
Kota Karaw ang - Jln. Akses Marunda (Rutin)
25 Km JAWA
BARAT
KAB. BEKASI 3.138.293 563.691 17,96 31,15 2.432.901 - 608.225 466.235 19,16 - - 66.500 10,93 30 88 7.020 3.762
2 34.1 Preservasi Rehabilitasi Jl. TB.Simatupang -
Bts.DKI - Banten/Bts.Depok (Ciputat-Bogor) - Jl.
Trans Yogi (Depok) (Rutin)
18 Km DKI
JAKARTA
KOTA
JAKARTA
SELATAN
3.328.588 801.698 24,09 58,61 1.586.774 - 396.694 350.000 22,06 - - 50.000 12,60 40 40 5820 3.666
3 43 Pemeliharaan Rutin Jalan Cimanggis - Nagrak
(Sw akelola)
2 Km JAWA
BARAT
KOTA DEPOK 170.004 - - - 136.003 - 34.001 - - - - - - 13 13 2.410 650
4 44 Pemeliharaan Rutin Jalan Daan Mogot
(Sw akelola)
3 Km DKI
JAKARTA
KOTA
JAKARTA
BARAT
241.146 21.305 8,83 8,83 192.917 - 48.229 21.305 11,04 - - - - 22 22 6.864 1.716
6.878.031 1.386.694 12,72 24,65 4.348.595 - 1.087.149 837.540 13,07 - - 116.500 5,88 75 75 15.094 6.032
PELAKSANAAN JALAN NASIONAL
METROPOLITAN II JAKARTA
1 1.1 PRESERVASI REHABILITASI CILODONG/BTS.
DEPOK - BTS. KOTA BOGOR - JLN.
SAWANGAN RAYA (DEPOK)
25 Km JAWA
BARAT
KAB. BOGOR 2.033.099 756.217 37,20 37,19 126.217 - 1.135.957 17.455 13,83 - - 157.094 13,83 35 35 9.450 2.100
2 4.1 PRESERVASI REHABILITASI CIGELUNG
(BTS.PROV. BANTEN) - BTS. KOTA JASINGA -
BTS. KOTA LEUWILIANG - BTS. KOTA BOGOR
38 Km JAWA
BARAT
KAB. BOGOR 1.885.779 247.546 13,13 25,00 101.382 - 912.436 43.116 42,53 - - 259.800 28,47 45 55 7.875 2.165
3 7.1 PRESERVASI REHABILITASI CIAWI - PUNCAK -
BTS. KOTA CIANJUR - BENDA
17 Km JAWA
BARAT
KAB. CIANJUR 1.261.575 438.284 34,74 34,74 244.063 - 734.859 54.018 22,13 - - 284.000 38,65 40 40 8.760 2.760
5.180.453 1.442.047 28,36 32,31 471.662 - 2.783.252 114.589 26,16 - - 700.894 26,98 120 130 26.085 7.025
DINAS BINA MARGA DAN TATA RUANG
PROVINSI BANTEN
1 1.1 PAKET PRESERVASI REHABILITASI BTS.
KOTA PANDEGLANG-RANGKASBITUNG-
CIGELUNG (Pemeliharaan Rutin)
18 Km BANTEN KAB.
PANDEGLANG
1.201.881 265.799 22,12 16,81 20.188 - 100.000 2.500 12,38 - - 12.500 12,50 5 5 125 125
2.1 PAKET PRESERVASI REHABILITASI JLN.
RAYA SERANG (PANDEGLANG)-SAKETI-
SIMPANG LABUAN (Pemeliharaan Rutin)
23 Km BANTEN KAB.
PANDEGLANG
1.415.496 221.932 15,68 22,37 453.998 - 360.539 112.085 24,69 - - 107.500 29,82 44 44 8.976 2.068
15.00 PENANGANAN TRANSISI RUAS JALAN
BATAS KOTA PANDEGLANG-
RANGKASBITUNG-CIGELUNG
1 LS BANTEN KAB.
PANDEGLANG
725.199 725.132 99,99 100,00 40.000 - 250.000 40.000 100,00 - - 250.000 100,00 50 50 2.500 2.500
2 16.00 PENANGANAN TRANSISI RUAS JALAN RAYA
SERANG (PANDEGLANG)-SAKETI-SIMPANG
LABUAN
1 LS BANTEN KAB. SERANG 712.727 710.227 99,65 100,00 35.000 - 250.000 35.000 100,00 - - 250.000 100,00 100 100 5.000 5.000
4.055.303 1.923.090 59,36 59,80 549.186 - 960.539 189.585 59,27 - - 620.000 60,58 199 199 16.601 9.693
No Kode Satker/Paket
4498597
4498781
4299030
Pagu
Vol Sat
Output Lokasi Paket
Pagu
(Rp Ribu)Kec
Kel/
Des
Hari Orang Kerja
(Hari)
Tenaga Kerja
(Orang)
Realisasi
TOTAL
TOTAL
TOTAL
Realisasi
Prov Kab/ Kota
FisikPendam
pingUpah
Alokasi Padat Karya