WEEKLY REPORT PROGRES
PROYEK“EPC” ELECTROCOAGULATION PLANT
Jl. Raya Jakarta-Bogor. Km.35 Cimanggis-DepokNo Dok : RP/W001/A1-002 Rev : 000 TglTerbit : 15 Oktober 2014 Hal : 1/
Bush Bar Cable
BEFORE AFTER
Action Material & Equipment
- Ganti dengan Cable Casing 2 Warna menggunakan Vyniel Merah dan Biru MATERIAL & TOOLS Qty APD &Safety Equipment
Mesin Las PVC 1 - Sarung tangan- Face shield/safety glases
1
![Page 2: Form Report 02](https://reader038.fdokumen.com/reader038/viewer/2022102808/55cf91c2550346f57b90575d/html5/thumbnails/2.jpg)
WEEKLY REPORT PROGRES
PROYEK“EPC” ELECTROCOAGULATION PLANT
Jl. Raya Jakarta-Bogor. Km.35 Cimanggis-DepokNo Dok : RP/W001/A1-002 Rev : 000 TglTerbit : 15 Oktober 2014 Hal : 1/
REACTORPVC PLATE
BEFORE AFTER
Action Material & Equipment
- Material Stopper diganti menggunakan PVC Plate MATERIAL & TOOLS Qty APD &Safety Equipment
Gerinda 4” 1 - Work Permit- APAR- Sarung tangan- Face shield/safety glases- Isolated Area
Bor Tangan 2
2
![Page 3: Form Report 02](https://reader038.fdokumen.com/reader038/viewer/2022102808/55cf91c2550346f57b90575d/html5/thumbnails/3.jpg)
WEEKLY REPORT PROGRES
PROYEK“EPC” ELECTROCOAGULATION PLANT
Jl. Raya Jakarta-Bogor. Km.35 Cimanggis-DepokNo Dok : RP/W001/A1-002 Rev : 000 TglTerbit : 15 Oktober 2014 Hal : 1/
FLOOR PAINT
BEFORE AFTER
Action Material & Equipment
- - Dilakukan Pembersihan dan Di Cat Ulang MATERIAL & TOOLS Qty APD &Safety Equipment
Gerinda 4” 1 - Sarung tangan- Face shield/safety glasesBor Tangan 2
Cat 1Kuas 2” 1
3
![Page 4: Form Report 02](https://reader038.fdokumen.com/reader038/viewer/2022102808/55cf91c2550346f57b90575d/html5/thumbnails/4.jpg)
WEEKLY REPORT PROGRES
PROYEK“EPC” ELECTROCOAGULATION PLANT
Jl. Raya Jakarta-Bogor. Km.35 Cimanggis-DepokNo Dok : RP/W001/A1-002 Rev : 000 TglTerbit : 15 Oktober 2014 Hal : 1/
METERING and GROUND TANK SYSTEMBOLT and NUT
BEFORE AFTER
Action Material & Equipment
- - Ganti Mur dan Baut denga Material Stainless MATERIAL & TOOLS Qty APD &Safety Equipment
Kunci sock 1 - Sarung tangan- Face shield/safety glases- Isolated Minor Area
4