BQ ME - JEC#Hexa-Vendoor#

2
BILL OF QUANTITY PROYEK : JAKARTA EYE CENTRE (JEC) PEKERJAAN : ELEKTRONIK MATERIAL UPAH MATERIAL UPAH Rp. Rp. Rp. Rp. III INSTALASI FIRE ALARM A PERALATAN UTAMA 1 MCPFA Semi Addresable 1 loop 1 set 73,622,250 8,450,000 73,622,250 8,450,000 c/w Accessories pendukung 2 Annunciator Panel 1 bh 28,080,000 2,275,000 28,080,000 2,275,000 3 Sistim Pentanahan (Grounding) 1 lot 2,362,500 5,655,000 2,362,500 5,655,000 4 Material bantu 1 lot 7,726,808 1,597,050 7,726,808 1,597,050 111,791,558 17,977,050 B INSTALASI FIRE ALARM 1 Lantai Basement - Rate Of Rase detector (ROR) 9 bh 351,000 84,500 3,159,000 760,500 - Smoke Detector 5 bh 1,017,900 84,500 5,089,500 422,500 - Manual push button 1 bh 666,900 84,500 666,900 84,500 - Indicator Lamp 1 bh 491,400 84,500 491,400 84,500 - Alarm bell 1 bh 666,900 84,500 666,900 84,500 - End Of Line 2 bh 438,750 84,500 877,500 169,000 - Instalasi Titik Detector d/kabel 14 ttk 288,900 65,000 4,044,600 910,000 NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm - Instalasi Titik Manual push button d/kabel 1 ttk 288,900 65,000 288,900 65,000 NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm - Instalasi Titik Indicator lamp d/kabel 1 ttk 383,400 65,000 383,400 65,000 NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm - Instalasi Titik Alarm bell d/kabel 1 ttk 383,400 65,000 383,400 65,000 NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm - Material Bantu 1 lot 1,625,214 599,021 1,625,214 599,021 17,676,714 3,309,521 2 Lantai 1 - Fixed Detector 1 bh 351,000 84,500 351,000 84,500 - Smoke Detector 12 bh 1,017,900 84,500 12,214,800 1,014,000 - Manual push button 1 bh 666,900 84,500 666,900 84,500 - Indicator Lamp 1 bh 491,400 84,500 491,400 84,500 - Alarm bell 1 bh 666,900 84,500 666,900 84,500 - End Of Line 1 bh 438,750 84,500 438,750 84,500 - Instalasi Titik Detector d/kabel 13 ttk 288,900 65,000 3,755,700 845,000 NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm - Instalasi Titik Manual push button d/kabel 1 ttk 288,900 65,000 288,900 65,000 NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm - Instalasi Titik Indicator lamp d/kabel 1 ttk 383,400 65,000 383,400 65,000 NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm - Instalasi Titik Alarm bell d/kabel 1 ttk 383,400 65,000 383,400 65,000 NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm - Material Bantu 1 lot 1,988,666 547,307 1,988,666 547,307 21,629,816 3,023,807 NO URAIAN JML SAT. TOTAL HARGA Sub Total 1 HARGA SATUAN Total A Sub Total 2 Page 1 ELEKTRONIK

description

BoQ Elektronika

Transcript of BQ ME - JEC#Hexa-Vendoor#

Page 1: BQ ME - JEC#Hexa-Vendoor#

BILL OF QUANTITY

PROYEK : JAKARTA EYE CENTRE (JEC)

PEKERJAAN : ELEKTRONIK

MATERIAL UPAH MATERIAL UPAH

Rp. Rp. Rp. Rp.

III INSTALASI FIRE ALARM

A PERALATAN UTAMA

1 MCPFA Semi Addresable 1 loop 1 set 73,622,250 8,450,000 73,622,250 8,450,000

c/w Accessories pendukung

2 Annunciator Panel 1 bh 28,080,000 2,275,000 28,080,000 2,275,000

3 Sistim Pentanahan (Grounding) 1 lot 2,362,500 5,655,000 2,362,500 5,655,000

4 Material bantu 1 lot 7,726,808 1,597,050 7,726,808 1,597,050

111,791,558 17,977,050

B INSTALASI FIRE ALARM

1 Lantai Basement

- Rate Of Rase detector (ROR) 9 bh 351,000 84,500 3,159,000 760,500

- Smoke Detector 5 bh 1,017,900 84,500 5,089,500 422,500

- Manual push button 1 bh 666,900 84,500 666,900 84,500

- Indicator Lamp 1 bh 491,400 84,500 491,400 84,500

- Alarm bell 1 bh 666,900 84,500 666,900 84,500

- End Of Line 2 bh 438,750 84,500 877,500 169,000

- Instalasi Titik Detector d/kabel 14 ttk 288,900 65,000 4,044,600 910,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Instalasi Titik Manual push button d/kabel 1 ttk 288,900 65,000 288,900 65,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Instalasi Titik Indicator lamp d/kabel 1 ttk 383,400 65,000 383,400 65,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Instalasi Titik Alarm bell d/kabel 1 ttk 383,400 65,000 383,400 65,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Material Bantu 1 lot 1,625,214 599,021 1,625,214 599,021

17,676,714 3,309,521

2 Lantai 1

- Fixed Detector 1 bh 351,000 84,500 351,000 84,500

- Smoke Detector 12 bh 1,017,900 84,500 12,214,800 1,014,000

- Manual push button 1 bh 666,900 84,500 666,900 84,500

- Indicator Lamp 1 bh 491,400 84,500 491,400 84,500

- Alarm bell 1 bh 666,900 84,500 666,900 84,500

- End Of Line 1 bh 438,750 84,500 438,750 84,500

- Instalasi Titik Detector d/kabel 13 ttk 288,900 65,000 3,755,700 845,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Instalasi Titik Manual push button d/kabel 1 ttk 288,900 65,000 288,900 65,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Instalasi Titik Indicator lamp d/kabel 1 ttk 383,400 65,000 383,400 65,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Instalasi Titik Alarm bell d/kabel 1 ttk 383,400 65,000 383,400 65,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Material Bantu 1 lot 1,988,666 547,307 1,988,666 547,307

21,629,816 3,023,807

NO URAIAN JML SAT.

TOTAL HARGA

Sub Total 1

HARGA SATUAN

Total A

Sub Total 2

Page 1 ELEKTRONIK

Page 2: BQ ME - JEC#Hexa-Vendoor#

BILL OF QUANTITY

PROYEK : JAKARTA EYE CENTRE (JEC)

PEKERJAAN : ELEKTRONIK

MATERIAL UPAH MATERIAL UPAH

Rp. Rp. Rp. Rp.

NO URAIAN JML SAT.

TOTAL HARGAHARGA SATUAN

3 Lantai 2

- Smoke Detector 10 bh 1,017,900 84,500 10,179,000 845,000

- Manual push button 1 bh 666,900 84,500 666,900 84,500

- Indicator Lamp 1 bh 491,400 84,500 491,400 84,500

- Alarm bell 1 bh 666,900 84,500 666,900 84,500

- End Of Line 1 bh 438,750 84,500 438,750 84,500

- Instalasi Titik Detector d/kabel 10 ttk 288,900 65,000 2,889,000 650,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Instalasi Titik Manual push button d/kabel 1 ttk 288,900 65,000 288,900 65,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Instalasi Titik Indicator lamp d/kabel 1 ttk 383,400 65,000 383,400 65,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Instalasi Titik Alarm bell d/kabel 1 ttk 383,400 65,000 383,400 65,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Material Bantu 1 lot 1,659,250 448,188 1,659,250 448,188

18,046,900 2,476,188

4 Lantai 3

- Fixed Detector 1 bh 351,000 84,500 351,000 84,500

- Smoke Detector 15 bh 1,017,900 84,500 15,268,500 1,267,500

Thermatic Holotron 1 bh 11,475,000 828,750 11,475,000 828,750

- Manual push button 1 bh 666,900 84,500 666,900 84,500

- Indicator Lamp 1 bh 491,400 84,500 491,400 84,500

- Alarm bell 1 bh 666,900 84,500 666,900 84,500

- End Of Line 1 bh 438,750 84,500 438,750 84,500

- Instalasi Titik Detector d/kabel 16 ttk 288,900 65,000 4,622,400 1,040,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Instalasi Titik Manual push button d/kabel 1 ttk 288,900 65,000 288,900 65,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Instalasi Titik Indicator lamp d/kabel 1 ttk 383,400 65,000 383,400 65,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Instalasi Titik Alarm bell d/kabel 1 ttk 383,400 65,000 383,400 65,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Material Bantu 1 lot 3,547,451 829,579 3,547,451 829,579

38,584,001 4,583,329

5 Lantai 3

- Smoke Detector 13 bh 1,017,900 84,500 13,232,700 1,098,500

- Manual push button 1 bh 666,900 84,500 666,900 84,500

- Indicator Lamp 1 bh 491,400 84,500 491,400 84,500

- Alarm bell 1 bh 666,900 84,500 666,900 84,500

- End Of Line 1 bh 438,750 84,500 438,750 84,500

- Instalasi Titik Detector d/kabel 13 ttk 288,900 65,000 3,755,700 845,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Instalasi Titik Manual push button d/kabel 1 ttk 288,900 65,000 288,900 65,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Instalasi Titik Indicator lamp d/kabel 1 ttk 383,400 65,000 383,400 65,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Instalasi Titik Alarm bell d/kabel 1 ttk 383,400 65,000 383,400 65,000

NYA 2x1x1,5 mm2 di dalam pipa PVC Konduit ¢ 20 mm

- Material Bantu 1 lot 2,056,190 547,307 2,056,190 547,307

22,364,240 3,023,807 Sub Total 5

Sub Total 3

Sub Total 4

Page 2 ELEKTRONIK