REKAPITULASI PEKERJAAN PILE CAP (ADDENDUM I) PROYEK WARE HOUSE AMPLAS - MEDAN BLOK B & C (57 UNIT) NO URAIAN SATUAN VOLUME 1 Galian tanah M3 128.45 2 Beton lantai kerja, tb = 50mm, mutu K-100 M3 14.27 3 Beton cor mutu K-225 M3 64.22 4 Bekisting / acuan M2 428.16 5 Pembesian: - D 10mm Kg 5,823.63 Medan, 25 Januari 2013 Diajukan Oleh, Diperiksa Oleh, KONTRAKTOR BURSA PROPERTY SARIPUDDIN RAHMAD S. PROJECT MANAGER PIMPRO

Transcript of Back Up Data Pile Cap

Page 1: Back Up Data Pile Cap

REKAPITULASI PEKERJAAN PILE CAP (ADDENDUM I)PROYEK WARE HOUSE AMPLAS - MEDAN

BLOK B & C (57 UNIT)

NO URAIAN SATUAN VOLUME KETERANGAN

1 Galian tanah M3 128.45 2 Beton lantai kerja, tb = 50mm, mutu K-100 M3 14.27 3 Beton cor mutu K-225 M3 64.22 4 Bekisting / acuan M2 428.16 5 Pembesian:

- D 10mm Kg 5,823.63

Medan, 25 Januari 2013Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

SARIPUDDIN RAHMAD S.PROJECT MANAGER PIMPRO

Page 2: Back Up Data Pile Cap

PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I

TOTAL LUAS 25.277,70 M2 (57 UNIT) GALIAN TANAH PILE CAPTanggal: 25 Januari 2013

Sketsa:

NO.DIMENSI VOLUME JUMLAH PILE CAP (UNIT) VOLUME/BLOK (m3)

Panjang (m') Lebar (m') Tinggi (m') BLOK B BLOK C BLOK B BLOK Ca b c d e= (b x c x d) f g h=(f x e) i= (g x e)1 0.80 0.80 0.45 0.288 222.000 224.000 63.936 64.512

Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

HENDRA SAFRIZA THAMBOSSite Manager Site Manager

(m3)

Page 3: Back Up Data Pile Cap

BACK-UP DATA ADDENDUM I

GALIAN TANAH PILE CAPTanggal: 25 Januari 2013

TOTAL VOLUMEKETERANGAN

m3j= (h + i)128.448

Diperiksa Oleh,BURSA PROPERTY

THAMBOSSite Manager

Page 4: Back Up Data Pile Cap

PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I

TOTAL LUAS 25.277,70 M2 (57 UNIT) BETON LANTAI KERJA (K100) PILE CAPTanggal: 25 Januari 2013

Sketsa:

NO.DIMENSI VOLUME JUMLAH PILE CAP (UNIT) VOLUME/BLOK (m3)

Panjang (m') Lebar (m') Tinggi (m') BLOK B BLOK C BLOK B BLOK Ca b c d e= (b x c x d) f g h=(f x e) i= (g x e)1 0.80 0.80 0.05 0.032 222.000 224.000 7.104 7.168

Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

HENDRA SAFRIZA THAMBOSSite Manager Site Manager

(m3)

Page 5: Back Up Data Pile Cap

BACK-UP DATA ADDENDUM I

BETON LANTAI KERJA (K100) PILE CAPTanggal: 25 Januari 2013

TOTAL VOLUMEKETERANGAN

m3j= (h + i)14.272

Diperiksa Oleh,BURSA PROPERTY

THAMBOSSite Manager

Page 6: Back Up Data Pile Cap

PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I

TOTAL LUAS 25.277,70 M2 (57 UNIT) BETON LANTAI KERJA (K100) PILE CAPTanggal: 25 Januari 2013

Sketsa:

NO.DIMENSI VOLUME JUMLAH PILE CAP (UNIT) VOLUME/BLOK (m3)

Sisi (m') Jumlah Segi Tinggi (m') (m2) BLOK B BLOK C BLOK B BLOK Ca b c d e= (b x c x d) f g h=(f x e) i= (g x e)1 0.60 4.00 0.40 0.960 222.000 224.000 213.120 215.040

Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

HENDRA SAFRIZA THAMBOSSite Manager Site Manager

Page 7: Back Up Data Pile Cap

BACK-UP DATA ADDENDUM I

BETON LANTAI KERJA (K100) PILE CAPTanggal: 25 Januari 2013

TOTAL VOLUMEKETERANGAN

m2j= (h + i)428.160

Diperiksa Oleh,BURSA PROPERTY

THAMBOSSite Manager

Page 8: Back Up Data Pile Cap

PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I

TOTAL LUAS 25.277,70 M2 (57 UNIT) BETON COR MUTU K 225 PILE CAPTanggal: 25 Januari 2013

Sketsa:

NO.DIMENSI VOLUME JUMLAH PILE CAP (UNIT) VOLUME/BLOK (m3)

Panjang (m') Lebar (m') Tinggi (m') BLOK B BLOK C BLOK B BLOK Ca b c d e= (b x c x d) f g h=(f x e) i= (g x e)1 0.60 0.60 0.40 0.144 222.000 224.000 31.968 32.256

Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

HENDRA SAFRIZA THAMBOSSite Manager Site Manager

(m3)

Page 9: Back Up Data Pile Cap

BACK-UP DATA ADDENDUM I

BETON COR MUTU K 225 PILE CAPTanggal: 25 Januari 2013

TOTAL VOLUMEKETERANGAN

m3j= (h + i)64.224

Diperiksa Oleh,BURSA PROPERTY

THAMBOSSite Manager

Page 10: Back Up Data Pile Cap

PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I

TOTAL LUAS 25.277,70 M2 (57 UNIT) PEMBESIAN D 10 mm PILE CAPTanggal: 25 Januari 2013

Sketsa:

TipeJLH. Panjang Jlh. Batang Volume Berat Besi JUMLAH PILE CAP (UNIT) VOLUME/BLOK (m3) TOTAL VOLUME

KETERANGANPANJANG (m') (m') (Btg.) (m') (Kg) BLOK B BLOK C BLOK B BLOK C Kg

a b c d= (a+b+c) e f=(d x e) g h i j=(h x g) k= (i x g) l =(j +k)

1 0.100 0.12 0.520 0.740 10.00 7.400 4.562 222.00 224.00 1,012.79 1,021.91 2,034.70 2 0.320 0.32 0.520 1.160 10.00 11.600 7.151 222.00 224.00 1,587.61 1,601.91 3,189.52 3 1.040 1.04 0.100 2.180 1.00 2.180 1.344 222.00 224.00 298.36 301.05 599.41

TOTAL 5,823.63

Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

HENDRA SAFRIZA THAMBOSSite Manager Site Manager

Besi D 10 mm - 15 cm

a abb

c ba

c

b b

a

a c

c

Tipe 1 = 10 unit Tipe 2 = 10 unit Tipe 3 = 1 unit