REKAPITULASI PEKERJAAN PILE CAP (ADDENDUM I)PROYEK WARE HOUSE AMPLAS - MEDAN
BLOK B & C (57 UNIT)
NO URAIAN SATUAN VOLUME KETERANGAN
1 Galian tanah M3 128.45 2 Beton lantai kerja, tb = 50mm, mutu K-100 M3 14.27 3 Beton cor mutu K-225 M3 64.22 4 Bekisting / acuan M2 428.16 5 Pembesian:
- D 10mm Kg 5,823.63
Medan, 25 Januari 2013Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY
SARIPUDDIN RAHMAD S.PROJECT MANAGER PIMPRO
PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I
TOTAL LUAS 25.277,70 M2 (57 UNIT) GALIAN TANAH PILE CAPTanggal: 25 Januari 2013
Sketsa:
NO.DIMENSI VOLUME JUMLAH PILE CAP (UNIT) VOLUME/BLOK (m3)
Panjang (m') Lebar (m') Tinggi (m') BLOK B BLOK C BLOK B BLOK Ca b c d e= (b x c x d) f g h=(f x e) i= (g x e)1 0.80 0.80 0.45 0.288 222.000 224.000 63.936 64.512
Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY
HENDRA SAFRIZA THAMBOSSite Manager Site Manager
(m3)
BACK-UP DATA ADDENDUM I
GALIAN TANAH PILE CAPTanggal: 25 Januari 2013
TOTAL VOLUMEKETERANGAN
m3j= (h + i)128.448
Diperiksa Oleh,BURSA PROPERTY
THAMBOSSite Manager
PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I
TOTAL LUAS 25.277,70 M2 (57 UNIT) BETON LANTAI KERJA (K100) PILE CAPTanggal: 25 Januari 2013
Sketsa:
NO.DIMENSI VOLUME JUMLAH PILE CAP (UNIT) VOLUME/BLOK (m3)
Panjang (m') Lebar (m') Tinggi (m') BLOK B BLOK C BLOK B BLOK Ca b c d e= (b x c x d) f g h=(f x e) i= (g x e)1 0.80 0.80 0.05 0.032 222.000 224.000 7.104 7.168
Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY
HENDRA SAFRIZA THAMBOSSite Manager Site Manager
(m3)
BACK-UP DATA ADDENDUM I
BETON LANTAI KERJA (K100) PILE CAPTanggal: 25 Januari 2013
TOTAL VOLUMEKETERANGAN
m3j= (h + i)14.272
Diperiksa Oleh,BURSA PROPERTY
THAMBOSSite Manager
PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I
TOTAL LUAS 25.277,70 M2 (57 UNIT) BETON LANTAI KERJA (K100) PILE CAPTanggal: 25 Januari 2013
Sketsa:
NO.DIMENSI VOLUME JUMLAH PILE CAP (UNIT) VOLUME/BLOK (m3)
Sisi (m') Jumlah Segi Tinggi (m') (m2) BLOK B BLOK C BLOK B BLOK Ca b c d e= (b x c x d) f g h=(f x e) i= (g x e)1 0.60 4.00 0.40 0.960 222.000 224.000 213.120 215.040
Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY
HENDRA SAFRIZA THAMBOSSite Manager Site Manager
BACK-UP DATA ADDENDUM I
BETON LANTAI KERJA (K100) PILE CAPTanggal: 25 Januari 2013
TOTAL VOLUMEKETERANGAN
m2j= (h + i)428.160
Diperiksa Oleh,BURSA PROPERTY
THAMBOSSite Manager
PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I
TOTAL LUAS 25.277,70 M2 (57 UNIT) BETON COR MUTU K 225 PILE CAPTanggal: 25 Januari 2013
Sketsa:
NO.DIMENSI VOLUME JUMLAH PILE CAP (UNIT) VOLUME/BLOK (m3)
Panjang (m') Lebar (m') Tinggi (m') BLOK B BLOK C BLOK B BLOK Ca b c d e= (b x c x d) f g h=(f x e) i= (g x e)1 0.60 0.60 0.40 0.144 222.000 224.000 31.968 32.256
Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY
HENDRA SAFRIZA THAMBOSSite Manager Site Manager
(m3)
BACK-UP DATA ADDENDUM I
BETON COR MUTU K 225 PILE CAPTanggal: 25 Januari 2013
TOTAL VOLUMEKETERANGAN
m3j= (h + i)64.224
Diperiksa Oleh,BURSA PROPERTY
THAMBOSSite Manager
PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I
TOTAL LUAS 25.277,70 M2 (57 UNIT) PEMBESIAN D 10 mm PILE CAPTanggal: 25 Januari 2013
Sketsa:
TipeJLH. Panjang Jlh. Batang Volume Berat Besi JUMLAH PILE CAP (UNIT) VOLUME/BLOK (m3) TOTAL VOLUME
KETERANGANPANJANG (m') (m') (Btg.) (m') (Kg) BLOK B BLOK C BLOK B BLOK C Kg
a b c d= (a+b+c) e f=(d x e) g h i j=(h x g) k= (i x g) l =(j +k)
1 0.100 0.12 0.520 0.740 10.00 7.400 4.562 222.00 224.00 1,012.79 1,021.91 2,034.70 2 0.320 0.32 0.520 1.160 10.00 11.600 7.151 222.00 224.00 1,587.61 1,601.91 3,189.52 3 1.040 1.04 0.100 2.180 1.00 2.180 1.344 222.00 224.00 298.36 301.05 599.41
TOTAL 5,823.63
Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY
HENDRA SAFRIZA THAMBOSSite Manager Site Manager
Besi D 10 mm - 15 cm
a abb
c ba
c
b b
a
a c
c
Tipe 1 = 10 unit Tipe 2 = 10 unit Tipe 3 = 1 unit