By : Budi Santoso, ST
SLOOF
WF
KOLOM
BALOK
ANALISA PERHITUNGAN
PONDASI P. BATU KALIA. HARGA
P. BORED PILE
PLAT LANTAI S6
S7
S8
P. PLAT 2
ANALISA PERHITUNGAN : DATA SLOOFTULANGAN UTAMA Tump ANALISA HARGA :
Diameter 13 mm Atas 3 D 13 Harga : Rp 7,751,846.41 Panjang tul 135.750 m Bawah 2 D 13Volume tul 141.373 kg Sengkang 8 150
SENGKANG (TUMPUAN) LapDiameter 8 mm 2 D 13Jarak 150 mm 3 D 13Pjg total 68.952 m 8 200Volume tul 27.194 kg
INSERT PANJANG : 30.000 M
SLOOF S1SENGKANG (LAPANGAN) HASIL : KET :Diameter 8 mm Vol tulangan 198.959 kg B 0.15 mJarak 200 mm Vol beton 1.350 m3 H 0.30 mPjg total 77.064 m Kg/m3 147.38 kg/m3 Luas 0.05 m2Volume tul 30.393 kg
TUMPUAN LAPANGAN
ANALISA PERHITUNGAN : DATA BALOK ANALISA HARGA :
TULANGAN UTAMA Tump Lap Harga Rp 471,208.06
Diameter 13 mm Atas 2 D 13 2 D 13
Panjang tul 4.000 m Bawah 2 D 13 2 D 13
Volume tul 4.166 kg Sengkang 8 ### 8 ###
SENGKANG (TUMPUAN)
Diameter 8 mm BALOK BP1
Jarak 150 mm KET :
Pjg total 5.856 m INSERT PANJANG : 1.000 M B 0.40 m
Volume tul 2.310 kg H 0.20 m
HASIL : Luas 0.08 m2
SENGKANG (LAPANGAN) Vol tulangan 8.400 kg
Diameter 8 mm Vol beton 0.080 m3
Jarak 200 mm Kg/m3 104.997 kg/m3
Pjg total 4.88 m
Volume tul 1.925 kg
TUMPUAN LAPANGAN
ANALISA PERHITUNGAN : DATA KOLOM
TULANGAN UTAMA Tul Utama ANALISA HARGA :
Diameter 16 mm 6 D 16 Harga Rp 731,262.65
Panjang tul 6 m Sengkang
Volume tul 9.465 kg 16 150
SENGKANG
Diameter 16 mm
Jarak 150 mm
Panjang tul 8.736 m
Volume tul 13.781 kg INSERT PANJANG : 1.000 M
KOLOM K1 HASIL :
KET : Vol tulangan 23.247 kg B 0.25 m
Tul utama 6 D16 Vol beton 0.100 m3 H 0.40 m
Sengkang ∅8-125 Kg/m3 232.466 kg/m3 Luas 0.10 m2
WF 150 x 75 HITUNG : HASIL :
TULANGAN UTAMA (T1) Berat wf 14.0000 kg
Diameter 10 mm Vol beton 0.002 m3
Pjg tul utama Vol tulangan 4.881 kg
Atas 2.00 m'
Bawah 2.00 m'
Samping 2.00 ANALISA HARGA :
Tot pjg 6.00 m' Harga Wf Rp 394,926.00
Volume tul 3.70 kg Beton Rp 10,513.83
Jumlah Rp 405,439.83
Ket : SENGKANG (T2)
Ukuran Wf 75 x 150 Diameter 8.00 mm
Tul atas 2 P 10 Jarak 300 m
Tul bwh 2 P 10 Panjang Tul 3 m
Tul samping 2 P 10 Volume tul 1.18 kg
Sengkang ∅8-300
B 0.217 m
H 0.135 m WF
A balok 0.0293 m2
Section area 17.8500 cm2
Input panjang1.000 m' A balok/cm2 292.9500 cm2
A Wf 0.0275 m2
Unit weight 14.0000 kg
Volume tul 4.8805 kg
Volume Wf 0.0275 m3
Berat Wf 14.0000 kg
PLAT TYPE S6
LX 1
LY 1
Tebal plat 0.15
HITUNG :
Arah Y > ∅10-300 10 300 6.282 31.41 19.356 kg
Arah Y < ∅12-150 12 150 1.01 8.08 7.170 kg
Arah Y < ∅12-150 12 150 1.01 8.08 7.170 kg
Arah X > ∅12-150 12 150 2.154 17.232 15.291 kg
Arah X > ∅12-150 12 150 1.077 8.616 7.646 kg
Arah X > ∅12-150 12 150 1.077 8.616 7.646 kg
64.278 kg
HASIL :
Vol tulangan 64.278 kg
Vol beton 0.15 m3
Kg/m3 428.51694924 kg/m3
ANALISA HARGA :
Harga ###
PLAT S7
Mesh M8-150
Berat mesh 61.790 kg
Luas Mesh 8.50 m2
P 1.00 m
L 1.00 m
Tebal plat 0.150 m
Luas plat 1.000 m2
Luas bekisting 1.6 m2
Kebutuhan Mesh
Mesh/lbr 1.000 lbr
Mesh/kg 61.79 kg
Vol mesh 123.58 kg
Volume beton 0.150 m3
PLAT S8
Mesh M6-150
Berat mesh 34.760 kg
Luas Mesh 8.50 m2
P 1.00 m
L 1.00 m
Tebal plat 0.150 m
Luas plat 1.000 m2
Luas bekisting 1.6 m2
Kebutuhan Mesh
Mesh/lbr 1.000 lbr
Mesh/kg 34.76 kg
Vol mesh 69.52 kg
Volume beton 0.150 m3
PONDASI BATU KALI INSERT PANJANG :
HITUNG : 1.000 m
Urugan Pasir
B1 0.700 m
B1' 0.797 m
T1 0.145 m
Luas 0.109 m2
Volume 0.109 m3
Batu Pecah
B2 0.797 m
B2' 0.897 m
T2 0.150 m
Luas 0.127 m2
Volume 0.127 m3
Batu Kali
B3 0.600 m
B3' 0.250 m
T3 0.525 m
Luas 0.223 m2
Volume 0.223 m3
HASIL :
Tanah Urug Volume
B3 0.148 m Galian tanah 0.798 m3
B3' 0.498 m Urugan pasir 0.109 m3
T3 0.525 m Pasangan pondasi 0.223 m3
Luas 0.339 m2 Urugan tanah kembali 0.339 m3
Volume 0.339 m3
ANALISA HARGA :
Galian tanah Rp 44,499.78
Urugan pasir Rp 19,654.91
Pasangan pondasi Rp 138,437.79
Urugan tanah kembali Rp 5,345.65
Jumlah Total Rp 207,938.14
MENU
PONDASI PLAT TYPE 2 Tul Bgkk HASIL :
Lebar telapak : 2 m Diameter 13 mm Volume
Jumlah Pond. Plat 1 m n tul 4 Galian tanah 9.307 m3
Panjang tul 9.492 m Urugan pasir 0.560 m3
HITUNG : Volume tul 9.885 kg Volume beton 2.040 m3
Urugan Pasir Urugan tanah kembal 6.706 m3
Luas 0.280 Tul Lrs Vol tulangan 171.745 kg
Volume 0.560 m3 Diameter 13 mm
n tul 4
Tanah Urug Pjg total 7.544 m
Luas 3.353 Volume tul 7.856 kg ANALISA HARGA :
Volume 6.706 m3 Galian tanah Rp 519,080.85
Sengkang Klm Urugan pasir Rp 101,489.66
Volume Beton Diameter 13 mm### 1 Volume beton ###
Luas 1.020 Jarak 100 mm### 1 Urugan tanah kembal Rp 105,706.05
Volume 2.040 m3 Pjg total 25.574 m 13 0 Jumlah Total ###
Volume tul 26.633 kg 1
Sengkang Tlpk ### 4
Diameter 13 mm### 1
Jarak 150 mm 13 0
Pjg total 61.152 m 4
Volume tul 127.370 kg
MENU
BORED PILE HITUNG : ANALISA HARGA :
Ket : TULANGAN UTAMA (T1) Pengeboran Rp 104,201,826.30
Tul utama D16 Diameter 16 mm Beton Rp 120,794,473.80
Sengkang ∅8-150 Panjang tul 3932.5 m Tulangan Rp 107,291,602.31
Diameter 0.6 m Volume tul 6203.66 kg Jumlah Total Rp332,287,902.41
Input pjg 30.000 m'
Jumlah PB 13.000 bh SENGKANG SPIRAL
Diameter 8 mm
DATA PB Jarak 150 mm
Tul Utama Panjang tul 7347.600 m
10 D 19 Volume tul 2,897.776 kg
Sengkang spiral HASIL :
8 150 Vol beton 110.214
Vol tulangan 9101.436
PILE CAP HITUNG : HASIL :
Ket : SENGKANG Vol beton 17.55
Diameter 13 mm Panjang tot 260 m Vol tulangan 270.769
Jarak 150 mm
B 1.5 m
H 1.5 m
T 0.6 m
Panjang Skg 3.6 m
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : A. PEKERJAAN TANAHJenis Pekerjaan : Pekerjaan Galian TanahVolume : m3Total Biaya : Rp 55,774.10
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah PekerjaTk. Gali tanah oh 0.7350 65,800.00 48,363.00 Mandor oh 0.0730 85,700.00 6,256.10
2 Bahan
3 Alat BantuPacul bh 0.0250 45,000.00 1,125.00 Benang rami glg 0.0150 2,000.00 30.00
Sub Total 55,774.10
Total 55,774.10
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : A. PEKERJAAN TANAH
Pekerjaan Urugan TanahVolume : m3Total Biaya : Rp 15,761.90
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah PekerjaTk. Gali tanah oh 0.1920 65,800.00 12,633.60 Mandor oh 0.0190 85,700.00 1,628.30
2 Bahan
3 Alat BantuPacul bh 0.0250 45,000.00 1,125.00 Pengki bh 0.0150 25,000.00 375.00
Sub Total 15,761.90
Total 15,761.90
MENU
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : A. PEKERJAAN TANAH
Pekerjaan Urugan Pasir Bawah PondasiVolume : m3Total Biaya : Rp 181,097.00
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah PekerjaPekerja oh 0.3000 55,800.00 16,740.00 Mandor oh 0.0100 85,700.00 857.00
2 BahanPasir urug m3 1.2000 135,000.00 162,000.00
3 Alat BantuPacul bh 0.0250 45,000.00 1,125.00 Pengki bh 0.0150 25,000.00 375.00
Sub Total 181,097.00
Total 181,097.00
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : A. PEKERJAAN TANAH
Pekerjaan Urugan Pasir Bawah LantaiVolume : m3Total Biaya : Rp 181,097.00
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah PekerjaPekerja oh 0.3000 55,800.00 16,740.00 Mandor oh 0.0100 85,700.00 857.00
2 BahanPasir urug m3 1.2000 135,000.00 162,000.00
3 Alat BantuPacul bh 0.0250 45,000.00 1,125.00 Pengki bh 0.0150 25,000.00 375.00
Sub Total 181,097.00
Total 181,097.00
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : A. PEKERJAAN TANAH
Pembuangan Tanah Sejauh 200 meterVolume : m3Total Biaya : Rp 55,425.40
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah PekerjaPekerja oh 0.6880 55,800.00 38,390.40 Mandor oh 0.0500 85,700.00 4,285.00
2 Bahan
3 Alat BantuPacul bh 0.2000 45,000.00 9,000.00 Pengki bh 0.1500 25,000.00 3,750.00
Sub Total 55,425.40
Total 55,425.40
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : B. PEKERJAAN PONDASI
Pondasi Batu Kali(150 kg besi + bekisting)
Volume : m3Total Biaya : Rp 620,449.50
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah PekerjaPekerja oh 1.5000 55,800.00 83,700.00 Tukang batu oh 0.6000 65,800.00 39,480.00 Kepala tukang oh 0.0600 75,700.00 4,542.00 Mandor oh 0.0750 85,700.00 6,427.50
2 BahanBatu belah 15/20 cm m3 1.1000 165,000.00 181,500.00 Semen Portland (PC) Kg 163.0000 1,200.00 195,600.00 Pasir Pasang m3 0.5200 185,000.00 96,200.00
3 Alat BantuEmber aduk bh 1.0000 6,000.00 6,000.00 Pacul bh 0.1000 45,000.00 4,500.00 Sekop bh 0.1000 25,000.00 2,500.00
Sub Total 620,449.50
Total 620,449.50
Boq No : F-3 Pekerjaan StrukturPekerjaan : B. PEKERJAAN PONDASI
Pondasi Plat Gabungan (PC 1)(150 kg besi + bekisting)
Volume : m3Total Biaya : ###
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah PekerjaPekerja oh 4.3000 55,800.00 239,940.00 Tukang batu oh 0.3500 65,800.00 23,030.00 Tukang kayu oh 1.0400 65,800.00 68,432.00 Tukang besi oh 1.0500 65,800.00 69,090.00 Kepala tukang oh 0.2450 75,700.00 18,546.50 Mandor oh 0.1650 85,700.00 14,140.50
2 BahanKayu terentang m3 0.2000 2,640,225.00 528,045.00 Paku biasa 2"-5" Kg 1.5000 11,610.00 17,415.00 Minyak bekisting kg 0.4000 21,525.00 8,610.00 Besi beton Kg 150.0000 10,126.00 1,518,900.00 Kawat beton Kg 2.2500 12,000.00 27,000.00 Semen portland Kg 323.0000 1,200.00 387,600.00 Pasir beton m3 0.5200 177,000.00 92,040.00 Koral beton m3 0.7800 210,600.00 164,268.00 Benang rami glg 0.0150 2,000.00 30.00
3 Alat BantuEmber aduk bh 1.0000 6,000.00 6,000.00 Pacul bh 0.1000 45,000.00 4,500.00 Sekop bh 0.1000 25,000.00 2,500.00
Sub Total 3,190,087.00
Total 3,190,087.00
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : B. PEKERJAAN PONDASI
Pondasi Plat 1 (PP 1)(150 kg besi + bekisting)
Volume : m3Total Biaya : ###
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah PekerjaPekerja oh 4.3000 55,800.00 239,940.00 Tukang batu oh 0.3500 65,800.00 23,030.00 Tukang kayu oh 1.0400 65,800.00 68,432.00 Tukang besi oh 1.0500 65,800.00 69,090.00 Kepala tukang oh 0.2450 75,700.00 18,546.50 Mandor oh 0.1650 85,700.00 14,140.50
2 BahanKayu terentang m3 0.2000 2,640,225.00 528,045.00 Paku biasa 2"-5" kg 1.5000 11,610.00 17,415.00 Minyak bekisting Lt 0.4000 21,525.00 8,610.00 Besi beton kg 150.0000 10,126.00 1,518,900.00 Kawat beton kg 2.2500 12,000.00 27,000.00 Semen portland kg 323.0000 1,200.00 387,600.00 Pasir beton m3 0.5200 177,000.00 92,040.00 Koral beton m3 0.7800 210,600.00 164,268.00 Benang rami glg 0.0150 2,000.00 30.00
3 Alat BantuEmber aduk bh 1.0000 6,000.00 6,000.00 Pacul bh 0.0250 45,000.00 1,125.00 Sekop bh 0.0150 40,000.00 600.00
Sub Total 3,184,812.00
Total 3,184,812.00
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : B. PEKERJAAN PONDASI
Pondasi Plat 2 (PP 2)(150 kg besi + bekisting)
Volume : m3Total Biaya : ###
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah PekerjaPekerja oh 4.3000 55,800.00 239,940.00 Tukang batu oh 0.3500 65,800.00 23,030.00 Tukang kayu oh 1.0400 65,800.00 68,432.00 Tukang besi oh 1.0500 65,800.00 69,090.00 Kepala tukang oh 0.2450 75,700.00 18,546.50 Mandor oh 0.1650 85,700.00 14,140.50
2 BahanKayu terentang m3 0.2000 2,640,225.00 528,045.00 Paku biasa 2"-5" kg 1.5000 11,610.00 17,415.00 Minyak bekisting Lt 0.4000 21,525.00 8,610.00 Besi beton kg 150.0000 10,126.00 1,518,900.00 Kawat beton kg 2.2500 12,000.00 27,000.00 Semen portland kg 323.0000 1,200.00 387,600.00 Pasir beton m3 0.5200 177,000.00 92,040.00 Koral beton m3 0.7800 210,600.00 164,268.00 Benang rami glg 0.0150 2,000.00 30.00
3 Alat BantuEmber aduk bh 1.0000 6,000.00 6,000.00 Pacul bh 0.0250 45,000.00 1,125.00 Sekop bh 0.0150 40,000.00 600.00
Sub Total 3,184,812.00
Total 3,184,812.00
ANALISA PERHITUNGAN UPAH DAN BAHAN
PEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : B. PEKERJAAN PONDASI
Pondasi Bor Piled ( D30cm) Pengeboran D30 cm /m', Bored Pile
Volume : m'Total Biaya : Rp 97,603.60
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Tukang gali oh 0.1600 65,800.00 10,528.00 Mandor oh 0.0080 85,700.00 685.60
2 Alat Bantu Crawler Crane jam 0.1300 322,000.00 41,860.00 Mesin Bor jam 0.1300 215,000.00 27,950.00
3 Lain-lainOli+Solar ls 1.0000 13,500.00 13,500.00 Alat Bantu ls 0.2200 14,000.00 3,080.00
Sub Total 97,603.60
Total 97,603.60
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : B. PEKERJAAN PONDASI
Pondasi Bor Piled ( D30cm) Beton D30cm /m3, Bored Pile
Volume : m3Total Biaya : Rp 945,450.00
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Pekerja oh 2.1000 55,800.00 117,180.00 Tukang batu oh 0.3500 65,800.00 23,030.00 Kepala tukang oh 0.0350 75,700.00 2,649.50 Mandor oh 0.1050 85,700.00 8,998.50
2 BahanSemen Portland (PC) kg 448.0000 1,200.00 537,600.00 Pasir Beton m3 0.4000 177,000.00 70,800.00 Koral Beton m3 0.8200 210,600.00 172,692.00
3 Lain-lain Alat Bantu : Pipa Tremi+Cas ls 1.0000 12,500.00 12,500.00
Sub Total 945,450.00
Total 945,450.00
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : B. PEKERJAAN PONDASI
Pondasi Bor Piled ( D30cm) Pembesian Bored Pile /kg
Volume : kgTotal Biaya : Rp 11,447.85
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Tukang besi oh 0.0050 65,800.00 329.00 Mandor oh 0.0005 85,700.00 42.85
2 BahanBesi Beton Ulir kg 1.0000 10,126.00 10,126.00 Kawat Beton ls 1.0000 250.00 250.00 Kawat Las ls 1.0000 100.00 100.00 Kawat Gantung ls 1.0000 600.00 600.00
Sub Total 11,447.85
Total 11,447.85
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : C. PEKERJAAN LANTAI
Precast Plat Lantai HCSVolume : m2Total Biaya : Rp 350,700.00
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah
Mandor oh 1.0000 85,700.00 85,700.00
2 BahanPrecast HCS m2 1.0000 265,000.00 265,000.00
Sub Total 350,700.00
Total 350,700.00
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : C. PEKERJAAN LANTAI
Floor Lantai Dasar Adukan K 275
1 m3 Beton Ad. 1 : 2 : 3 (150 Kg besi)Volume : m3Total Biaya : ###
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Pekerja oh 3.9000 55,800.00 217,620.00 Tukang batu oh 0.3500 65,800.00 23,030.00 Tukang besi oh 1.0500 65,800.00 69,090.00 Kepala tukang oh 0.2450 75,700.00 18,546.50 Mandor oh 0.1650 85,700.00 14,140.50
2 BahanSemen Portland (PC) kg 232.0000 1,200.00 278,400.00 Pasir beton m3 0.5200 177,000.00 92,040.00 Koral Beton m3 0.7800 210,600.00 164,268.00 Besi beton kg 150.0000 10,126.00 1,518,900.00 kawat beton kg 2.2500 12,000.00 27,000.00
3 Alat BantuEmber aduk bh 1.0000 6,000.00 6,000.00 Pacul bh 0.0250 45,000.00 1,125.00 Sekop bh 0.0150 40,000.00 600.00
Sub Total 2,430,760.00
Total 2,430,760.00
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : C. PEKERJAAN LANTAI
Floor Lantai Adukan K 2751 m3 Beton Ad. 1 : 2 : 3 (150 Kg besi)
Volume : m3Total Biaya : ###
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Pekerja oh 3.9000 55,800.00 217,620.00 Tukang batu oh 0.3500 65,800.00 23,030.00 Tukang besi oh 1.0500 65,800.00 69,090.00 Kepala tukang oh 0.2450 75,700.00 18,546.50 Mandor oh 0.1650 85,700.00 14,140.50
2 BahanSemen Portland (PC) kg 232.0000 1,200.00 278,400.00 Pasir beton m3 0.5200 177,000.00 92,040.00 Koral Beton m3 0.7800 210,600.00 164,268.00 Besi beton kg 150.0000 10,126.00 1,518,900.00 kawat beton kg 2.2500 12,000.00 27,000.00
3 Alat BantuEmber aduk bh 1.0000 6,000.00 6,000.00 Pacul bh 0.0250 45,000.00 1,125.00 Sekop bh 0.0150 40,000.00 600.00
Sub Total 2,430,760.00
Total 2,430,760.00
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : C. PEKERJAAN LANTAI
Beton Tumbuk, 1Pc : 3Ps : 5KrVolume : m3Total Biaya : Rp 661,855.50
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Pekerja oh 1.6500 55,800.00 92,070.00 Tukang batu oh 0.2500 65,800.00 16,450.00 Kepala Tukang oh 0.0250 75,700.00 1,892.50 Mandor oh 0.0800 85,700.00 6,856.00
2 BahanSemen Portland (PC) kg 218.0000 1,200.00 261,600.00 Pasir beton m3 0.5200 177,000.00 92,040.00 Koral Beton m3 0.8700 210,600.00 183,222.00
3 Alat BantuEmber aduk bh 1.0000 6,000.00 6,000.00 Pacul bh 0.0250 45,000.00 1,125.00 Sekop bh 0.0150 40,000.00 600.00
Sub Total 661,855.50
Total 661,855.50
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : C. PEKERJAAN LANTAI
Pekerjaan Lapisan Beton Kedap Air (Eskalator)Volume : m3Total Biaya : Rp 991,984.50
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Pekerja oh 2.0000 55,800.00 111,600.00 Tukang batu oh 0.3500 65,800.00 23,030.00 Kepala Tukang oh 0.0350 75,700.00 2,649.50 Mandor oh 1.0000 85,700.00 85,700.00
2 BahanSemen Portland (PC) kg 400.0000 1,200.00 480,000.00 Pasir beton m3 0.4800 177,000.00 84,960.00 Koral Beton m3 0.8000 210,600.00 168,480.00 Pelapis Kedap air (MU 600) kg 1.2000 23,200.00 27,840.00
3 Alat BantuEmber aduk bh 1.0000 6,000.00 6,000.00 Pacul bh 0.0250 45,000.00 1,125.00 Sekop bh 0.0150 40,000.00 600.00
Sub Total 991,984.50
Total 991,984.50
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : C. PEKERJAAN LANTAI
Pekerjaan Lapisan Beton Kedap Air (Lift)Volume : m3Total Biaya : Rp 991,984.50
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Pekerja oh 2.0000 55,800.00 111,600.00 Tukang batu oh 0.3500 65,800.00 23,030.00 Kepala Tukang oh 0.0350 75,700.00 2,649.50 Mandor oh 1.0000 85,700.00 85,700.00
2 BahanSemen Portland (PC) kg 400.0000 1,200.00 480,000.00 Pasir beton m3 0.4800 177,000.00 84,960.00 Koral Beton m3 0.8000 210,600.00 168,480.00 Pelapis Kedap air (MU 600) kg 1.2000 23,200.00 27,840.00
3 Alat BantuEmber aduk bh 1.0000 6,000.00 6,000.00 Pacul bh 0.0250 45,000.00 1,125.00 Sekop bh 0.0150 40,000.00 600.00
Sub Total 991,984.50
Total 991,984.50
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : D. PEKERJAAN BETON BERTULANG
Beton Bertulang Sloof + Bekisting(351 Kg besi)
Volume : m3Total Biaya : ###
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Pekerja oh 8.8500 55,800.00 493,830.00 Tukang batu oh 0.3500 65,800.00 23,030.00 Tukang kayu oh 1.5600 65,800.00 102,648.00 Tukang besi oh 1.4000 65,800.00 92,120.00 Kepala tukang oh 0.3310 75,700.00 25,056.70 Mandor oh 0.1700 85,700.00 14,569.00
2 BahanKayu terentang m3 0.2700 2,640,225.00 712,860.75 Paku biasa 2"-5" kg 2.0000 11,610.00 23,220.00 Minyak bekisting Lt 0.6000 21,525.00 12,915.00 Besi beton kg 351.0000 10,126.00 3,554,226.00 Kawat beton kg 3.0000 12,000.00 36,000.00 Semen portland kg 323.0000 1,200.00 387,600.00 Pasir beton m3 0.5200 177,000.00 92,040.00 Koral beton m3 0.7800 210,600.00 164,268.00
3 Alat BantuEmber aduk bh 1.0000 6,000.00 6,000.00 Pacul bh 0.0250 45,000.00 1,125.00 Sekop bh 0.0150 40,000.00 600.00
Sub Total 5,742,108.45
Total 5,742,108.45
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : D. PEKERJAAN BETON BERTULANG
Beton Bertulang Kolom + Bekisting(260 Kg besi)
Volume : m3Total Biaya : ###
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Pekerja oh 11.3000 55,800.00 630,540.00 Tukang batu oh 0.3500 65,800.00 23,030.00 Tukang kayu oh 3.3000 65,800.00 217,140.00 Tukang besi oh 2.1000 65,800.00 138,180.00 Kepala tukang oh 0.5700 75,700.00 43,149.00 Mandor oh 0.2500 85,700.00 21,425.00
2 BahanKayu terentang m3 0.4000 2,640,225.00 1,056,090.00 Paku biasa 2"-5" kg 4.0000 11,610.00 46,440.00 Minyak bekisting Lt 2.0000 21,525.00 43,050.00 Besi beton kg 260.0000 10,126.00 2,632,760.00 Kawat beton kg 4.5000 12,000.00 54,000.00 Semen portland kg 323.0000 1,200.00 387,600.00 Pasir beton m3 0.5200 177,000.00 92,040.00 Koral beton m3 0.7800 210,600.00 164,268.00 Kayu borneo balok m3 0.1500 5,055,750.00 758,362.50
Plywood 9 mm lbr 3.5000 230,522.00 806,827.00 Dolken kayu galam Ø-8-10/4 btg 20.0000 9,500.00 190,000.00
3 Alat BantuEmber aduk bh 1.0000 6,000.00 6,000.00 Pacul bh 0.0250 45,000.00 1,125.00 Sekop bh 0.0150 40,000.00 600.00
Sub Total 7,312,626.50
Total 7,312,626.50
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : D. PEKERJAAN BETON BERTULANG
Beton Bertulang Balok+ Bekisting(185 Kg besi)
Volume : m3Total Biaya : ###
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Pekerja oh 9.9600 55,800.00 555,768.00 Tukang batu oh 0.3500 65,800.00 23,030.00 Tukang kayu oh 2.8000 65,800.00 184,240.00 Tukang besi oh 1.4000 65,800.00 92,120.00 Kepala tukang oh 0.4550 75,700.00 34,443.50 Mandor oh 0.2080 85,700.00 17,825.60
2 BahanKayu terentang m3 0.3200 2,640,225.00 844,872.00 Paku biasa 2"-5" kg 3.2000 11,610.00 37,152.00 Minyak bekisting Lt 1.6000 21,525.00 34,440.00 Besi beton kg 185.0000 10,126.00 1,873,310.00 Kawat beton kg 3.0000 12,000.00 36,000.00 Semen portland kg 323.0000 1,200.00 387,600.00 Pasir beton m3 0.5200 177,000.00 92,040.00 Koral beton m3 0.7800 210,600.00 164,268.00 Kayu borneo balok m3 0.1400 5,055,750.00 707,805.00 Plywood 9 mm lbr 2.8000 230,522.00 645,461.60 Dolken kayu galam Ø-8-10/4 btg 16.0000 9,500.00 152,000.00
3 Alat BantuEmber aduk bh 1.0000 6,000.00 6,000.00 Pacul bh 0.0250 45,000.00 1,125.00 Sekop bh 0.0150 40,000.00 600.00
Sub Total 5,890,100.70
Total 5,890,100.70
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : D. PEKERJAAN BETON BERTULANG
Beton Bertulang Tangga+ Bekisting
(200 Kg besi)Volume : m3Total Biaya : ###
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Pekerja oh 9.9600 55,800.00 555,768.00 Tukang batu oh 0.3500 65,800.00 23,030.00 Tukang kayu oh 2.3000 65,800.00 151,340.00 Tukang besi oh 1.4000 65,800.00 92,120.00 Kepala tukang oh 0.4050 75,700.00 30,658.50 Mandor oh 0.2020 85,700.00 17,311.40
2 BahanKayu terentang m3 0.2500 2,640,225.00 660,056.25 Paku biasa 2"-5" kg 3.0000 11,610.00 34,830.00 Minyak bekisting Lt 1.2000 21,525.00 25,830.00 Besi beton kg 200.0000 10,126.00 2,025,200.00 Kawat beton kg 3.0000 12,000.00 36,000.00 Semen portland kg 323.0000 1,200.00 387,600.00 Pasir beton m3 0.5200 177,000.00 92,040.00 Koral beton m3 0.7800 210,600.00 164,268.00 Kayu borneo balok m3 0.1050 5,055,750.00 530,853.75 Plywood 9 mm lbr 2.5000 230,522.00 576,305.00 Dolken kayu galam Ø-8-10/4 btg 14.0000 9,500.00 133,000.00
3 Alat BantuEmber aduk bh 1.0000 6,000.00 6,000.00 Pacul bh 0.0250 45,000.00 1,125.00 Sekop bh 0.0150 40,000.00 600.00
Sub Total 5,543,935.90
Total 5,543,935.90
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : D. PEKERJAAN BETON BERTULANG
Beton Mutu K 275 u/ Perkuatan Kolom(180 Kg besi)
Volume : m3Total Biaya : ###
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Pekerja oh 11.3000 55,800.00 630,540.00 Tukang batu oh 0.3500 65,800.00 23,030.00 Tukang kayu oh 3.3000 65,800.00 217,140.00 Tukang besi oh 2.1000 65,800.00 138,180.00 Kepala tukang oh 0.5700 75,700.00 43,149.00 Mandor oh 0.2500 85,700.00 21,425.00
2 BahanKayu terentang m3 0.4000 2,640,225.00 1,056,090.00 Paku biasa 2"-5" kg 4.0000 11,610.00 46,440.00
Minyak bekisting Lt 2.0000 21,525.00 43,050.00 Semen Portland (PC) kg 400.0000 1,200.00 480,000.00 Pasir beton m3 0.4000 177,000.00 70,800.00 Koral Beton m3 0.8200 210,600.00 172,692.00 Grouting StoCrete NSG-H kg 80.0000 4,600.00 368,000.00 Besi beton kg 180.0000 10,126.00 1,822,680.00 kawat beton kg 2.2500 12,000.00 27,000.00 Kayu borneo balok m3 0.1500 5,055,750.00 758,362.50 Plywood 9 mm lbr 3.5000 230,522.00 806,827.00 Dolken kayu galam Ø-8-10/4 btg 20.0000 9,500.00 5,651,941.50
3 Alat BantuEmber aduk bh 1.0000 6,000.00 6,000.00 Pacul bh 0.0250 45,000.00 1,125.00 Sekop bh 0.0150 40,000.00 600.00
Sub Total 12,385,072.00
Total 12,385,072.00
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : D. PEKERJAAN BETON BERTULANG
Dinding Beton Bertulang + Bekisting(150 Kg besi)
Volume : m3Total Biaya : ###
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Pekerja oh 5.6000 55,800.00 312,480.00 Tukang batu oh 0.3500 65,800.00 23,030.00 Tukang kayu oh 2.6400 65,800.00 173,712.00 Tukang besi oh 1.0500 65,800.00 69,090.00 Kepala tukang oh 0.4000 75,700.00 30,280.00 Mandor oh 0.1930 85,700.00 16,540.10
2 BahanKayu terentang m3 0.2400 2,640,225.00 633,654.00 Paku biasa 2"-5" kg 3.2000 11,610.00 37,152.00 Minyak bekisting lt 1.6000 21,525.00 34,440.00 Besi beton polos kg 150.0000 10,126.00 1,518,900.00 kawat beton kg 2.2500 12,000.00 27,000.00 Semen Portland (PC) kg 323.0000 1,200.00 387,600.00 Pasir beton m3 0.5200 177,000.00 92,040.00 Koral Beton m3 0.7800 210,600.00 164,268.00 Kayu borneo balok m3 0.1600 5,055,750.00 808,920.00 Plywood 9 mm lbr 2.8000 230,522.00 645,461.60 Dolken kayu galam Ø-8-10/4 btg 2.4000 9,500.00 22,800.00 Storox - 100 kg 1.2000 23,200.00 27,840.00
3 Alat BantuEmber aduk bh 1.0000 6,000.00 6,000.00 Pacul bh 0.0250 45,000.00 1,125.00 Sekop bh 0.0150 40,000.00 600.00
Sub Total 5,032,932.70
Total 5,032,932.70
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : E. PEK. CHEMICAL ANCHOR (MERK FISCHER)
Fischer injection mortar FIS VT 380 CVolume : ttkTotal Biaya : Rp 40,460.00
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Upah bor + pasang ttk 1.0000 9,500.00 9,500.00
2 BahanFTR - 19 ttk 1.0000 30,960.00 30,960.00
Sub Total 40,460.00
Total 40,460.00
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : E. PEK. CHEMICAL ANCHOR (MERK FISCHER)
Thereaded Rod + Fischer Chamical Capsul RM ( FTR M12 )
Volume : ttkTotal Biaya : Rp 43,995.00
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Upah bor + pasang ttk 1.0000 6,000.00 6,000.00
2 BahanFTR M12 pc 1.0000 13,800.00 13,800.00 RM 12 pc 1.0000 24,195.00 24,195.00
Sub Total 43,995.00
Total 43,995.00
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : E. PEK. CHEMICAL ANCHOR (MERK FISCHER)
Thereaded Rod + Fischer Chamical Capsul RM ( FTR M16 )
Volume : ttk
Total Biaya : Rp 67,790.00
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Upah bor + pasang ttk 1.0000 8,000.00 8,000.00
2 BahanFTR M16 Pc 1.0000 24,150.00 24,150.00 RM 16 Pc 1.0000 35,640.00 35,640.00
Sub Total 67,790.00
Total 67,790.00
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : E. PEK. CHEMICAL ANCHOR (MERK FISCHER)
Thereaded Rod + Fischer Chamical Capsul RM ( FTR M20 )
Volume : ttkTotal Biaya : Rp 104,050.00
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Upah bor + pasang ttk 1.0000 10,000.00 10,000.00
2 BahanFTR M20 Pc 1.0000 44,850.00 44,850.00 RM 20 Pc 1.0000 49,200.00 49,200.00
Sub Total 104,050.00
Total 104,050.00
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : E. PEK. CHEMICAL ANCHOR (MERK FISCHER)
GroutingVolume : zakTotal Biaya : Rp 69,000.00
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah
2 BahanStocrete NSG-H zak 1.0000 69,000.00 69,000.00 Standard non shrink grout25 Kg / zak
Sub Total 69,000.00
Total 69,000.00
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : F. PEKERJAAN BESI
Pemasangan Rangka BajaVolume : kgTotal Biaya : Rp 28,209.00
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Pekerja oh 0.0200 55,800.00 1,116.00 Tukang Baja oh 0.0200 90,000.00 1,800.00 Mandor Baja oh 0.0700 115,000.00 8,050.00
2 BahanBesi Profil WF Kg 1.1000 11,700.00 12,870.00 Meni besi Kg 0.0800 12,000.00 960.00 Genzet 20KVa unit 0.0020 100,000.00 200.00 Travo Las unit 0.0010 100,000.00 100.00 Mata Gerinda bh 0.0030 20,000.00 60.00 Mata Bor bh 0.0030 25,000.00 75.00 Kawat Las kg 0.0030 20,000.00 60.00 Baut dia 12mm-1" bh 0.1500 1,500.00 225.00
3 Upah Erection+Transport Transport kg 1.0000 1,455.00 1,455.00 Pekerja oh 0.0100 55,800.00 558.00 Tukang Baja oh 0.0050 90,000.00 450.00 Mandor Baja oh 0.0020 115,000.00 230.00
Sub Total 28,209.00
Total 28,209.00
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : G. PEKERJAAN BEKISTING
Pasang dan Bongkar BekistingVolume : m3Total Biaya : Rp 396,632.35
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 Upah Pekerja oh 0.5760 55,800.00 32,140.80 Tukang kayu oh 0.4800 65,800.00 31,584.00 Kepala tukang oh 0.0480 75,700.00 3,633.60 mandor oh 0.0100 85,700.00 857.00
2 Bahankayu terentang m3 0.0400 2,640,225.00 105,609.00 paku biasa 2"-5" kg 0.4000 11,610.00 4,644.00 Minyak bekisting lt 0.2000 21,525.00 4,305.00 Balok kayu borneo m3 0.0150 5,055,750.00 75,836.25 Plywood tebal 9mm lbr 0.3500 230,522.00 80,682.70 Dolken kayu galam Ø-8-10/4 btg 6.0000 9,500.00 57,000.00
2 Alat BantuPalu bh 0.0100 9,000.00 90.00
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : H. PEKERJAAN SEWA ALAT
COLT DIESEL FE 74 / 125 PSVolume : unitTotal Biaya : Rp 300,000.00
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 COLT DIESEL FE 74 / 125 PS unit 1.0000 300,000.00 300,000.00 Capacity 7 tonDimensi Bak 14.538 m3
Sub Total 300,000.00
Total 300,000.00
ANALISA PERHITUNGAN UPAH DAN BAHANPEKERJAAN KONSTRUKSI
Boq No : F-3 Pekerjaan StrukturPekerjaan : H. PEKERJAAN SEWA ALAT
HINO TRACTOR HEAD FM 320 PVolume : unitTotal Biaya : ###
No. Uraian Satuan Koef Harga Satuan Jumlah ( Rp ) ( Rp )
1 HINO TRACTOR HEAD FM 320unit 1.0000 1,100,000.00 1,100,000.00 Capacity 7 tonDimensi Bak 14.538 m3
Sub Total 1,100,000.00
Total 1,100,000.00