Analisis Pengendalian Waktu Dan Biaya Proyek Metode Earned Value (Nilai Hasil) Pada Proyek...

9
ANALISIS PENGENDALIAN WAKTU DAN BIAYA PROYEK DENGAN METODE EARNED VALUE (NILAI HASIL) PADA PROYEK PEMBANGUNAN FASILITAS PENUNJANG BANDARA KUALANAMU TUGAS AKHIR Ditulis sebagai syarat menyelesaikan Mata kuliah Tugas Akhir Semester VIII Pendidikan Program Sarjana Sains Terapan Oleh: SYINTHA MARDYANTIKA NIM: 0905141024 PROGRAM STUDI MANAJEMEN REKAYASA KONSTRUKSI GEDUNG JURUSAN TEKNIK SIPIL POLITEKNIK NEGERI MEDAN 2013

Transcript of Analisis Pengendalian Waktu Dan Biaya Proyek Metode Earned Value (Nilai Hasil) Pada Proyek...

  • ANALISIS PENGENDALIAN WAKTU DAN BIAYA PROYEK DENGAN

    METODE EARNED VALUE (NILAI HASIL) PADA PROYEK PEMBANGUNAN

    FASILITAS PENUNJANG BANDARA KUALANAMU

    TUGAS AKHIR

    Ditulis sebagai syarat menyelesaikan

    Mata kuliah Tugas Akhir Semester VIII

    Pendidikan Program Sarjana Sains Terapan

    Oleh:

    SYINTHA MARDYANTIKA

    NIM: 0905141024

    PROGRAM STUDI MANAJEMEN REKAYASA KONSTRUKSI GEDUNG

    JURUSAN TEKNIK SIPIL

    POLITEKNIK NEGERI MEDAN

    2013

    perpusText BoxKATA PENGANTAR Dengan rahmat Tuhan Yang Maha Esa sehingga penulis dapat menyelesaikan Tugas Akhir ini dengan baik. Tugas Akhir ini berjudul "Analisis Pengendalian Waktu dan Biaya Proyek dengan Metode Earned Value (nilai hasil) pada Proyek Pembangunan Fasilitas Penunjang Bandara Kualanamu". Laporan Tugas Akhir ini merupakan satu diantara mata kuliah Tugas Akhir yang ditempuh oleh Mahasiswa/i semester VIII Pendidikan Program Sarjana Sains Terapan (Diploma IV) Jurusan Teknik Sipil Politeknik Negeri Medan. Penulis banyak mendapatkan bantuan dan masukan maupun dukungan dari berbagai pihak, oleh karena itu, penulis mengucapkan terima kasih kepada: 1. Bapak M. Syahruddin, ST, MT, Direktur Politeknik Negeri Medan. 2. Bapak Drs. Syaiful Hazmi, ST, MT, Ketua Jurusan Teknik Sipil Politeknik Negeri Medan. 3. Bapak Fadli, ST, MT, Kepala Program Studi Manajemen Rekayasa Konstruksi Gedung (MRKG) DIV Teknik Sipil. 4. Bapak Bambang Winarno, ST, MT, Dosen Pembimbing Tugas Akhir. 5. Civitas Akademika Politeknik Negeri Medan. 6. Kedua Orang Tua. Penulis telah berusaha semaksimal mungkin dalam menyelesaikan Tugas Akhir ini, namun demikian, kemungkinan masih terdapat kekurangan. Untuk itu penulis mengharapkan masukan untuk perbaikan laporan Tugas Akhir ini. Medan, Agustus 2013 Hormat saya, Syintha Mardyantika 0905141024

  • KATA PENGANTAR Dengan rahmat Tuhan Yang Maha Esa sehingga penulis dapat menyelesaikan Tugas Akhir ini dengan baik. Tugas Akhir ini berjudul Analisis Pengendalian Waktu dan Biaya Proyek dengan Metode Earned Value (nilai hasil) pada Proyek Pembangunan Fasilitas Penunjang Bandara Kualanamu. Laporan Tugas Akhir ini merupakan satu diantara mata kuliah Tugas Akhir yang ditempuh oleh Mahasiswa/i semester VIII Pendidikan Program Sarjana Sains Terapan (Diploma IV) Jurusan Teknik Sipil Politeknik Negeri Medan. Penulis banyak mendapatkan bantuan dan masukan maupun dukungan dari berbagai pihak, oleh karena itu, penulis mengucapkan terima kasih kepada: 1. Bapak M. Syahruddin, ST, MT, Direktur Politeknik Negeri Medan.

    2. Bapak Drs. Syaiful Hazmi, ST, MT, Ketua Jurusan Teknik Sipil Politeknik Negeri Medan.

    3. Bapak Fadli, ST, MT, Kepala Program Studi Manajemen Rekayasa Konstruksi Gedung (MRKG) DIV Teknik Sipil.

    4. Bapak Bambang Winarno, ST, MT, Dosen Pembimbing Tugas Akhir.

    5. Civitas Akademika Politeknik Negeri Medan.

    6. Kedua Orang Tua. Penulis telah berusaha semaksimal mungkin dalam menyelesaikan Tugas Akhir ini, namun demikian, kemungkinan masih terdapat kekurangan. Untuk itu penulis mengharapkan masukan untuk perbaikan laporan Tugas Akhir ini. Medan, Agustus 2013 Hormat saya, Syintha Mardyantika 0905141024

  • ANALISIS PENGENDALIAN WAKTU DAN BIAYA PROYEK DENGAN

    METODE EARNED VALUE (NILAI HASIL) PADA PROYEK FASILITAS

    PENUNJANG BANDARA KUALANAMU

    Abstrak

    Oleh: Syintha Mardyantika

    Pengendalian dalam proyek konstruksi pada umumnya menyangkut tiga aspek utama,

    yaitu, biaya, waktu dan SDM. Didalam pelaksanaan suatu proyek konstruksi, perencanaan

    dan pengendalian merupakan fungsi yang paling pokok didalam mewujudkan keberhasilan

    proyek. Persoalan yang timbul adalah bagaimana mencapai pemecahan optimum dengan

    kondisi sumber daya yang serba terbatas. Bagaimana menerapkan suatu metode pada

    proyek untuk mengendalikan biaya dan waktu, serta mengendalikan pelaksanaan proyek

    konstruksi terhadap terjadinya penyimpangan, dan mengevaluasi proyeksi penyelesaian

    terhadap terjadinya penyimpangan pada proyek merupakan tujuan dari penelitian ini.

    Untuk meningkatkan efektivitas dalam memantau dan mengendalikan proyek, perlu

    dipakai metode yang mengintegrasikan jadwal dan biaya sehingga mengungkapkan kinerja

    kegiatan. Salah satu metode yang memenuhi tujuan ini adalah Konsep Nilai Hasil, Earned

    Value Concept, yang terdiri dari tiga indikator yaitu BCWS, BCWP, dan ACWP. Prosedur

    penelitian dimulai dengan melakukan studi kepustakaan, pengambilan data, melakukan

    pengamatan langsung pada proyek, dan merangkum hasil pengumpulan data-data yang

    ada. Variansi yang ditekankan disini adalah untuk menyelidiki penyimpangan biaya atau

    jadwal pelaksanaan yang telah direncanakan atau ditentukan. Bila angka kinerja ditinjau

    lebih lanjut maka Angka indeks kinerja kurang dari satu (1) yang berarti makin

    besar penyimpangannya dari perencanaan dasar atau anggaran, atau prestasi pelaksanaan

    pekerjaan sangat baik, perlu diadakan pengkajian apakah mungkin perencanaan tidak

    realistis. Konsep Nilai Hasil bisa diterapkan pada penelitian di proyek ini di dalam tujuan

    pengendalian dimana berdasarkan analisis maka pengendalian yang dilakukan banyak

    terjadi penyimpangan dari sisi penjadwalan pada saat pelaporan-pelaporannya.

    Berdasarkan nilai ETC dan EAC yang terhitung maka apabila kinerja tidak diperbaharui

    akan terjadi bergeseran.

    Kata Kunci : Metode Nilai Hasil, BCWS, BCWP, ACWP

  • DAFTAR ISI

    LEMBAR PERSETUJUAN

    LEMBAR PENGESAHAN

    KATA PENGANTAR ......................................................................................................... i

    ABSTRAK ............................................................................................................ ii

    DAFTAR ISI ............................................................................................................ iii

    DAFTAR TABEL ............................................................................................................ iv

    DAFTAR GAMBAR ........................................................................................................... v

    DAFTAR LAMPIRAN ........................................................................................................ vi

    BAB I PENDAHULUAN

    1.1 Latar Belakang Masalah .................................................................................. 1

    1.2 Rumusan Masalah ........................................................................................... 2

    1.3 Maksud dan Tujuan Penulisan ......................................................................... 2

    1.4 Pokok Bahasan dan Batasan Masalah .............................................................. 3

    1.5 Sistematika Penulisan ...................................................................................... 3

    BAB II LANDASAN TEORI

    2.1 Pengertian Sistem Pengendalian ...................................................................... 5

    2.2 Pengendalian Waktu ........................................................................................ 6

    2.2.1 Barchart ............................................................................................... 6

    2.2.2 Kurva S ................................................................................................ 8

    2.3 Pengendalian Biaya ......................................................................................... 8

    2.4 Konsep Nilai Hasil (Earned Value) .................................................................. 9

    2.4.1 Indikator-indikator Earned Value ......................................................... 10

    2.4.2 Analisa Varians .................................................................................... 11

    2.4.3 Analisa Indeks Performansi .................................................................. 14

    2.4.4 Perkiraan Biaya Akhir dan Penyelesaian Proyek .................................. 16

    2.4.4.1 Perkiraan Biaya Akhir Proyek .................................................. 16

    2.4.4.2 Perkiraan Jadwal Penyelesaian Proyek ...................................... 17

    2.4.5 Biaya Pekerjaan Berdasarkan Anggaran ............................................... 17

  • BAB III METODOLOGI PENELITIAN

    3.1 Metodologi Pelaksanaan Penelitian .................................................................. 21

    3.1.1 Pengumpulan Data .................................................................................. 22

    3.2 Analisis Data ................................................................................................... 23

    BAB IV HASIL DAN PEMBAHASAN

    4.1 Data Umum Proyek ......................................................................................... 25

    4.2 Pengolahan Data .............................................................................................. 26

    4.2.1 Perhitungan Kinerja Proyek pada Bulan ke-3 ....................................... 26

    4.2.2 Perhitungan Kinerja Proyek pada Bulan ke-6 ....................................... 30

    4.2.3 Perhitungan Kinerja Proyek pada Bulan ke-9 ....................................... 33

    4.2.4 Faktor-faktor yang Menyebabkan Keterlambatan/Kemajuan Proyek ... 36

    4.2.5 Perkiraan Biaya dan Waktu Akhir Proyek ............................................ 37

    BAB V PENUTUP

    5.1 Kesimpulan ..................................................................................................... 35

    5.2 Saran ............................................................................................................ 36

    DAFTAR PUSTAKA

  • DAFTAR TABEL

    Tabel 2.1 Analisis Varians Biaya Terpadu .................................................................. 13

    Tabel 4.1 Nilai Bobot Progress Rencana Bulan ke-3 ................................................... 27

    Tabel 4.2 Nilai Bobot Progress Realisasi .................................................................... 27

    Tabel 4.3 Rekap EBPP s/d Bulan Januari 2013 ........................................................... 27

    Tabel 4.4 Laporan Kinerja Proyek s/d Bulan ke-3 ....................................................... 28

    Tabel 4.5 Nilai Bobot Progress Rencana Bulan ke-6 ................................................... 30

    Tabel 4.6 Nilai Bobot Progress Realisasi Bulan ke-6 .................................................. 30

    Tabel 4.7 Rekap EBPP s/d April 2013 ........................................................................ 30

    Tabel 4.8 Laporan Kinerja Proyek s/d Bulan ke-6 ....................................................... 32

    Tabel 4.9 Nilai Bobot Progress rencana Bulan ke-9 .................................................... 33

    Tabel 4.10 Nilai Bobot Progress Realisasi Bulan ke-9 .................................................. 33

    Tabel 4.11 Rekap EBPP s/d Juli 2013 ........................................................................... 33

    Tabel 4.12 Laporan Kinerja Proyek s/d Bulan ke-9 ....................................................... 34

  • DAFTAR GAMBAR

    Gambar 2.1 Contoh diagram batang ............................................................................... 6

    Gambar 2.2 Contoh Kurva S .......................................................................................... 7

    Gambar 2.3 Target prestasi berupa Kurva S ................................................................... 8

    Gambar 2.4 Analisa Varians terpadu disajikan dengan grafik S ...................................... 14

    Gambar 2.5 Menilai biaya pekerjaan yang telah diselesaikan dilihat dari bangun jumlah

    anggaran yang terpakai ............................................................................... 17

    Gambar 2.6 Hubungan antara BCWP, BCWS dan ACWP .............................................. 19

    Gambar 3.1 Diagram Alir Penelitian .............................................................................. 21

    Gambar 4.1 Lokasi pembangunan gedung stasiun kereta api, gedung administrasi,

    parkir bandara, perkantoran kargo, gedung AME/peralatan, dan gedung

    masjid bandara kualanamu .......................................................................... 25

    Gambar 4.2 Grafik Laporan Kinerja Bulan ke-3 ............................................................. 29

    Gambar 4.3 Grafik Laporan Kinerja Bulan ke-6 ............................................................. 32

    Gambar 4.4 Grafik Laporan Kinerja Bulan ke-9 ............................................................. 35

  • DAFTAR LAMPIRAN

    Lampiran 1 Master Schedule Kurva S

    Lampiran 2 Laporan Progress Mingguan

    Lampiran 3 Biaya Aktual Proyek (Rekap EBPP)

    Lampiran 4 Hasil Perhitungan dan Grafik perbandingan BCWS, BCWP, ACWP

    Lampiran 5 Surat Keterangan Validitas data dari PT. PP (Persero)

  • KATA PENGANTAR

    Dengan rahmat Tuhan Yang Maha Esa sehingga penulis dapat menyelesaikan

    Tugas Akhir ini dengan baik.

    Tugas Akhir ini berjudul Analisis Pengendalian Waktu dan Biaya Proyek dengan

    Metode Earned Value (nilai hasil) pada Proyek Pembangunan Fasilitas Penunjang Bandara

    Kualanamu.

    Laporan Tugas Akhir ini merupakan satu diantara mata kuliah Tugas Akhir yang

    ditempuh oleh Mahasiswa/i semester VIII Pendidikan Program Sarjana Sains Terapan

    (Diploma IV) Jurusan Teknik Sipil Politeknik Negeri Medan.

    Penulis banyak mendapatkan bantuan dan masukan maupun dukungan dari

    berbagai pihak, oleh karena itu, penulis mengucapkan terima kasih kepada:

    1. Bapak M. Syahruddin, ST, MT, Direktur Politeknik Negeri Medan.

    2. Bapak Drs. Syaiful Hazmi, ST, MT, Ketua Jurusan Teknik Sipil Politeknik Negeri

    Medan.

    3. Bapak Fadli, ST, MT, Kepala Program Studi Manajemen Rekayasa Konstruksi

    Gedung (MRKG) DIV Teknik Sipil.

    4. Bapak Bambang Winarno, ST, MT, Dosen Pembimbing Tugas Akhir.

    5. Civitas Akademika Politeknik Negeri Medan.

    6. Kedua Orang Tua.

    Penulis telah berusaha semaksimal mungkin dalam menyelesaikan Tugas Akhir ini,

    namun demikian, kemungkinan masih terdapat kekurangan. Untuk itu penulis

    mengharapkan masukan untuk perbaikan laporan Tugas Akhir ini.

    Medan, Agustus 2013

    Hormat saya,

    Syintha Mardyantika

    0905141024