PROGRESS LAPANGAN Minggu :Tanggal :
Type 60/105
Blok / Nomor : B21
Mandor TAYO
Jenis Item Pekerjaan Volume Satuan Bobot
A Pekerjaaan Pondasi
1 Bowplank 60 Type 163,402 1.43% 100
2 Galian 4.68 m3 196,082 1.72% 100
3 Pondasi Batu kali 4.68 m3 544,673 4.78% 100
4 Cor sloof 42.5 m' 381,271 3.34% 100
5 Pasang Paralon 3" 12 m' 108,935 0.96% 100
6 Galian Septictank 1 ls 119,828 1.05% 100
7 Urugan elevasi lantai 9.375 m3 130,721 1.15% 100
B Pekerjaan Dinding -
1 Dinding Bata 128.65 m2 1,960,822 17.20% 100
2 Kusen + Daun Pintu,Jendela 11.79 m2 326,804 2.87% 100
3 Plesteran + Acian Dinding 187.71 m2 2,053,416 18.01% 100
4 Cor Kolom Praktis 30 m' 217,869 1.91% 100
5 Cor Ring Balk 42.5 m' 272,336 2.39% 100
7 Rooster 1 ls 108,935 0.96% 100
8 Dinding Bata Ampig 11.05 m2 326,804 2.87% 100
9 Cor Topi Panel 0.1 m3 163,402 1.43% 100
C Pekerjaan ATAP -
3 Pasang Genteng Morando 58 m2 326,804 2.87% 100
4 Nok / Karpusan 6 m' 108,935 0.96% 100
5 Pasang ListPlank 2/20 20 m' 108,935 0.96% 100
6 Ban-banan Atap Pembatas 20 m' 108,935 0.96% 100
7 Pasang Rangka Plafond 54 m2 223,316 1.96% 100
8 Pasang Plafond Enthernit 54 m2 223,316 1.96% 100
D Pekerjaaan Pintu & Jendela -
1 Pasang Engsel Jendela 5 Bh 92,594 0.81%
2 Pasang Engsel Pintu & Kunci 5 Bh 163,402 1.43%
3 Pasang Slot 5 Bh 27,234 0.24%
4 Pasang Hak angin 5 Bh 27,234 0.24%
E Keramik -
1 Keramik Lantai 40x40 60 m2 762,542 6.69% 100
2 Keramik Dinding 20x25 6 m2 163,402 1.43% 100
3 Keramik Lantai Kamar Mandi 2.5 m2 76,254 0.67% 100
4 Bak mandi Tempel 1 Bh 54,467 0.48% 100
5 Closed 1 Bh 54,467 0.48% 100
6 Pintu Kamar Mandi 1 Bh 76,254 0.67% 100
7 Saringan Air 1 Bh 10,893 0.10% 100
No.
Pembulatan Kontrak
171.500,-
Prestasi lapangan
8 Intalasi Air Bersih 4 m' 108,935 0.96% 100
F Pekerjaan Lain - lain -
1 Carport 5 m' 163,402 1.43%
2 Pemberesan 1 Bh 76,254 0.67%
G Pekerjaan Tambahan -
1 Canopi Enterance + Topi -topi 1 ls 817,009 7.17% 100
2 Plesteran + Acian Dinding 1 ls 190,635 1.67% 100
4 Pembesian ( Rp. 5500 X 60 M2 ) 1 ls 359,484 3.15% 100
NILAI KONTRAK 11,400,000 100.00%
Jumlah :
Retensi Pekerjaan ( 100 Hari ) = 5% -
Jumlah Tagihan Progrees Pekerjaan Minggu ini
Jumlah Tagihan Progrees Pekerjaan Minggu lalu
Total Tagihan Progrees Pekerjaan Minggu ini
Bobot minggu lalu =
Diajukan : Bobot minggu ini =
Bobot aktual =
163,402
196,082
544,673
381,271
108,935
119,828
130,721
1,960,822
326,804
2,053,416
217,869
272,336
108,935
326,804
163,402
326,804
108,935
108,935
108,935
223,316
223,316
-
-
-
-
-
762,542
163,402
76,254
54,467
54,467
76,254
10,893
Jumlah ( Rp )
108,935
-
-
817,009
190,635
359,484
10,849,881
542,494
10,307,387
10,307,387
(0)
90.42
90.42
(0.00)
190,000
PROGRESS LAPANGAN Minggu :Tanggal :
Type 60/105
Blok / Nomor : B32
Mandor TAYO
No. Jenis Item Pekerjaan Volume Satuan
A Pekerjaaan Pondasi
1 Bowplank 60 Type 163,402 11,400,000
2 Galian 4.68 m3 196,082 11,400,000
3 Pondasi Batu kali 4.68 m3 544,673 11,400,000
4 Cor sloof 42.5 m' 381,271 11,400,000
5 Pasang Paralon 3" 12 m' 108,935 11,400,000
6 Galian Septictank 1 ls 119,828 11,400,000
7 Urugan elevasi lantai 9.375 m3 130,721 11,400,000
B Pekerjaan Dinding - 11,400,000
1 Dinding Bata 128.65 m2 1,960,822 11,400,000
2 Kusen + Daun Pintu,Jendela 11.79 m2 326,804 11,400,000
3 Plesteran + Acian Dinding 187.71 m2 2,053,416 11,400,000
4 Cor Kolom Praktis 30 m' 217,869 11,400,000
5 Cor Ring Balk 42.5 m' 272,336 11,400,000
7 Rooster 1 ls 108,935 11,400,000
8 Dinding Bata Ampig 11.05 m2 326,804 11,400,000
9 Cor Topi Panel 0.1 m3 163,402 11,400,000
C Pekerjaan Atap - 11,400,000
3 Pasang Genteng Morando 58 m2 326,804 11,400,000
4 Nok / Karpusan 6 m' 108,935 11,400,000
5 Pasang ListPlank 2/20 20 m' 108,935 11,400,000
6 Ban-banan Atap Pembatas 20 m' 108,935 11,400,000
7 Pasang Rangka Plafond 54 m2 223,316 11,400,000
8 Pasang Plafond Enthernit 54 m2 223,316 11,400,000
D Pekerjaaan Pintu & Jendela - 11,400,000
1 Pasang Engsel Jendela 5 Bh 92,594 11,400,000
2 Pasang Engsel Pintu & Kunci 5 Bh 163,402 11,400,000
3 Pasang Slot 5 Bh 27,234 11,400,000
4 Pasang Hak angin 5 Bh 27,234 11,400,000
E Keramik - 11,400,000
1 Keramik Lantai 40x40 60 m2 762,542 11,400,000
2 Keramik Dinding 20x25 6 m2 163,402 11,400,000
3 Keramik Lantai Kamar Mandi 2.5 m2 76,254 11,400,000
4 Bak mandi Tempel 1 Bh 54,467 11,400,000
5 Closed 1 Bh 54,467 11,400,000
6 Pintu Kamar Mandi 1 Bh 76,254 11,400,000
7 Saringan Air 1 Bh 10,893 11,400,000
8 Intalasi Air Bersih 4 m' 108,935 11,400,000
F Pekerjaan Lain - lain - 11,400,000
1 Carport 5 m' 163,402 11,400,000
2 Pemberesan 1 Bh 76,254 11,400,000
Pembulatan Kontrak
171.500,-
G Pekerjaan Tambahan - 11,400,000
1 Canopi Enterance + Topi -topi 1 ls 817,009 11,400,000
2 Plesteran + Acian Dinding 1 ls 190,635 11,400,000
4 Pembesian ( Rp. 5500 X 60 M2 ) 1 ls 359,484 11,400,000
NILAI KONTRAK 11,400,000
Retensi Pekerjaan ( 100 Hari ) = 5% -
Jumlah Tagihan Progrees Pekerjaan Minggu ini
Jumlah Tagihan Progrees Pekerjaan Minggu lalu
Total Tagihan Progrees Pekerjaan Minggu ini
Diajukan :
Bobot
1.43% 100 163,402
1.72% 100 196,082
4.78% 100 544,673
3.34% 100 381,271
0.96% 100 108,935
1.05% -
1.15% -
17.20% 100 1,960,822
2.87% 100 326,804
18.01% 100 2,053,416
1.91% 100 217,869
2.39% 100 272,336
0.96% 100 108,935
2.87% 100 326,804
1.43% 100 163,402
2.87% 100 326,804
0.96% 100 108,935
0.96% 100 108,935
0.96% 100 108,935
1.96% 100 223,316
1.96% 100 223,316
0.81% -
1.43% -
0.24% -
0.24% -
-
6.69% 100 762,542
1.43% 100 163,402
0.67% 100 76,254
0.48% 100 54,467
0.48% 100 54,467
0.67% 100 76,254
0.10% 100 10,893
0.96% 100 108,935
1.43% -
0.67% -
Prestasi lapangan
Jumlah ( Rp )
7.17% 75 612,757
1.67% 50 95,318
3.15% 100 359,484
100.00%
Jumlah : 10,299,761
514,988
9,784,773
9,267,334
517,439
Bobot minggu lalu = 81.29
Bobot minggu ini = 85.83
Bobot aktual = 4.54
PROGRESS LAPANGAN Minggu :Tanggal :
Type 60/105
Blok / Nomor : B21
Mandor TAYO
Jenis Item Pekerjaan Volume Satuan Bobot
A Pekerjaaan Pondasi
1 Bowplank 60 Type 163,402 11,209,365 1.46%
2 Galian 4.68 m3 196,082 11,209,365 1.75%
3 Pondasi Batu kali 4.68 m3 544,673 11,209,365 4.86%
4 Cor sloof 42.5 m' 381,271 11,209,365 3.40%
5 Pasang Paralon 3" 12 m' 108,935 11,209,365 0.97%
6 Galian Septictank 1 ls 119,828 11,209,365 1.07%
7 Urugan elevasi lantai 9.375 m3 130,721 11,209,365 1.17%
B Pekerjaan Dinding - 11,209,365
1 Dinding Bata 128.65 m2 1,960,822 11,209,365 17.49%
2 Kusen + Daun Pintu,Jendela 11.79 m2 326,804 11,209,365 2.92%
3 Plesteran + Acian Dinding 187.71 m2 2,053,416 11,209,365 18.32%
4 Cor Kolom Praktis 30 m' 217,869 11,209,365 1.94%
5 Cor Ring Balk 42.5 m' 272,336 11,209,365 2.43%
7 Rooster 1 ls 108,935 11,209,365 0.97%
8 Dinding Bata Ampig 11.05 m2 326,804 11,209,365 2.92%
9 Cor Topi Panel 0.1 m3 163,402 11,209,365 1.46%
C Pekerjaan Kayu - 11,209,365
1 Gording 6/12 32 m' - 11,209,365
2 Usuk / reng 2/3 58 m2 - 11,209,365
3 Pasang Genteng Morando 58 m2 326,804 11,209,365 2.92%
4 Nok / Karpusan 6 m' 108,935 11,209,365 0.97%
5 Pasang ListPlank 2/20 20 m' 108,935 11,209,365 0.97%
6 Ban-banan Atap Pembatas 20 m' 108,935 11,209,365 0.97%
7 Pasang Rangka Plafond 54 m2 223,316 11,209,365 1.99%
8 Pasang Plafond Enthernit 54 m2 223,316 11,209,365 1.99%
D Pekerjaaan Pintu & Jendela - 11,209,365
1 Pasang Engsel Jendela 5 Bh 92,594 11,209,365 0.83%
2 Pasang Engsel Pintu & Kunci 5 Bh 163,402 11,209,365 1.46%
3 Pasang Slot 5 Bh 27,234 11,209,365 0.24%
4 Pasang Hak angin 5 Bh 27,234 11,209,365 0.24%
E Keramik - 11,209,365
1 Keramik Lantai 40x40 60 m2 762,542 11,209,365 6.80%
2 Keramik Dinding 20x25 6 m2 163,402 11,209,365 1.46%
3 Keramik Lantai Kamar Mandi 2.5 m2 76,254 11,209,365 0.68%
4 Bak mandi Tempel 1 Bh 54,467 11,209,365 0.49%
5 Closed 1 Bh 54,467 11,209,365 0.49%
6 Pintu Kamar Mandi 1 Bh 76,254 11,209,365 0.68%
7 Saringan Air 1 Bh 10,893 11,209,365 0.10%
8 Intalasi Air Bersih 4 m' 108,935 11,209,365 0.97%
No.
Pembulatan
Kontrak 171.500,-
F Pekerjaan Lain - lain - 11,209,365
1 Carport 5 m' 163,402 11,209,365 1.46%
2 Pemberesan 1 Bh 76,254 11,209,365 0.68%
G Pekerjaan Tambahan - 11,209,365
1 Canopi Enterance + Topi -topi 1 ls 817,009 11,209,365 7.29%
4 Pembesian ( Rp. 5500 X 60 M2 ) 1 ls 359,484 11,209,365 3.21%
NILAI KONTRAK ### 100.00%
Retensi Pekerjaan ( 100 Hari ) = 5% -
Jumlah Tagihan Progrees Pekerjaan Minggu ini
Jumlah Tagihan Progrees Pekerjaan Minggu lalu
Total Tagihan Progrees Pekerjaan Minggu ini
Bobot minggu lalu =
Diajukan : Bobot minggu ini =
Bobot aktual =
100 163,402
100 196,082
100 544,673
100 381,271
100 108,935
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Prestasi lapangan
Jumlah ( Rp )
-
-
-
50 179,742
Jumlah : 1,574,104
78,705
1,495,399
858,949
636,450
Bobot minggu lalu = 7.66
Bobot minggu ini = 13.34
Bobot aktual = 5.68
PROGRESS LAPANGAN Minggu :Tanggal :
Type 60/105
Blok / Nomor : B18
Mandor TAYO
No. Jenis Item Pekerjaan Volume Satuan Bobot
A Pekerjaaan Pondasi
1 Bowplank 60 Type 252,041 1.46% 100 252,041
2 Galian 4.68 m3 302,449 1.75% 100 302,449
3 Pondasi Batu kali 4.68 m3 840,136 4.86% 100 840,136
4 Cor sloof 42.5 m' 588,095 3.40% 100 588,095
5 Pasang Paralon 3" 12 m' 168,027 0.97% 100 168,027
6 Galian Septictank 1 ls 184,830 1.07% -
7 Urugan elevasi lantai 9.375 m3 201,633 1.17% -
B Pekerjaan Dinding
1 Dinding Bata 128.65 m2 3,024,490 17.49% 30 907,347
2 Kusen + Daun Pintu,Jendela 11.79 m2 504,082 2.92% 50 252,041
3 Plesteran + Acian Dinding 187.71 m2 3,167,313 18.32% -
4 Cor Kolom Praktis 30 m' 336,054 1.94% -
5 Cor Ring Balk 42.5 m' 420,068 2.43% -
7 Rooster 1 ls 168,027 0.97% -
8 Dinding Bata Ampig 11.05 m2 504,082 2.92% -
9 Cor Topi Panel 0.1 m3 252,041 1.46% -
C Pekerjaan Kayu
1 Gording 6/12 32 m' -
2 Usuk / reng 2/3 58 m2 -
3 Pasang Genteng Morando 58 m2 504,082 2.92% -
4 Nok / Karpusan 6 m' 168,027 0.97% -
5 Pasang ListPlank 2/20 20 m' 168,027 0.97% -
6 Ban-banan Atap Pembatas 20 m' 168,027 0.97% -
7 Pasang Rangka Plafond 54 m2 344,456 1.99% -
8 Pasang Plafond Enthernit 54 m2 344,456 1.99% -
D Pekerjaaan Pintu & Jendela
1 Pasang Engsel Jendela 5 Bh 142,823 0.83% -
2 Pasang Engsel Pintu & Kunci 5 Bh 252,041 1.46% -
3 Pasang Slot 5 Bh 42,007 0.24% -
4 Pasang Hak angin 5 Bh 42,007 0.24% -
E Keramik -
1 Keramik Lantai 40x40 60 m2 1,176,190 6.80% -
2 Keramik Dinding 20x25 6 m2 252,041 1.46% -
3 Keramik Lantai Kamar Mandi 2.5 m2 117,619 0.68% -
4 Bak mandi Tempel 1 Bh 84,014 0.49% -
5 Closed 1 Bh 84,014 0.49% -
6 Pintu Kamar Mandi 1 Bh 117,619 0.68% -
7 Saringan Air 1 Bh 16,803 0.10% -
8 Intalasi Air Bersih 4 m' 168,027 0.97% -
Pembulatan Kontrak
171.500,-
Prestasi lapangan
Jumlah ( Rp )
F Pekerjaan Lain - lain
1 Carport 5 m' 252,041 1.46% -
2 Pemberesan 1 Bh 117,619 0.68% -
G Pekerjaan Tambahan
1 Canopi Enterance + Topi -topi 1 ls 1,260,204 7.29% -
2 Plesteran + Acian Dinding 1 ls -
4 Pembesian ( Rp. 5500 X 60 M2 1 ls 554,490 3.21% 50 277,245
NILAI KONTRAK 17,289,999 100.00%
Jumlah : 3,587,381
Retensi Pekerjaan ( 100 Hari ) = 5% - 179,369
Jumlah Tagihan Progrees Pekerjaan Minggu ini 3,408,012
Jumlah Tagihan Progrees Pekerjaan Minggu lalu 1,324,895
Total Tagihan Progrees Pekerjaan Minggu ini 2,083,117
Bobot minggu lalu = 7.66
Diajukan : Bobot minggu ini = 19.71
Bobot aktual = 12.05
PROGRESS LAPANGAN Minggu :Tanggal :
Type 60/105
Blok / Nomor : B21
Mandor PA TAYO
Jenis Item Pekerjaan Volume Satuan Bobot
A Pekerjaaan Pondasi
1 Bowplank 60 Type 163,402 1.46% 100
2 Galian 4.68 m3 196,082 1.75% 100
3 Pondasi Batu kali 4.68 m3 544,673 4.86% 100
4 Cor sloof 42.5 m' 381,271 3.40% 100
5 Pasang Paralon 3" 12 m' 108,935 0.97%
6 Galian Septictank 1 ls 119,828 1.07%
7 Urugan elevasi lantai 9.375 m3 130,721 1.17%
B Pekerjaan Dinding -
1 Dinding Bata 128.65 m2 1,960,822 17.49%
2 Kusen + Daun Pintu,Jendela 11.79 m2 326,804 2.92%
3 Plesteran + Acian Dinding 187.71 m2 2,053,416 18.32%
4 Cor Kolom Praktis 30 m' 217,869 1.94%
5 Cor Ring Balk 42.5 m' 272,336 2.43%
7 Rooster 1 ls 108,935 0.97%
8 Dinding Bata Ampig 11.05 m2 326,804 2.92%
9 Cor Topi Panel 0.1 m3 163,402 1.46%
C Pekerjaan Kayu -
1 Gording 6/12 32 m' -
2 Usuk / reng 2/3 58 m2 -
3 Pasang Genteng Morando 58 m2 326,804 2.92%
4 Nok / Karpusan 6 m' 108,935 0.97%
5 Pasang ListPlank 2/20 20 m' 108,935 0.97%
6 Ban-banan Atap Pembatas 20 m' 108,935 0.97%
7 Pasang Rangka Plafond 54 m2 223,316 1.99%
8 Pasang Plafond Enthernit 54 m2 223,316 1.99%
D Pekerjaaan Pintu & Jendela -
1 Pasang Engsel Jendela 5 Bh 92,594 0.83%
2 Pasang Engsel Pintu & Kunci 5 Bh 163,402 1.46%
3 Pasang Slot 5 Bh 27,234 0.24%
4 Pasang Hak angin 5 Bh 27,234 0.24%
E Keramik -
1 Keramik Lantai 40x40 60 m2 762,542 6.80%
2 Keramik Dinding 20x25 6 m2 163,402 1.46%
3 Keramik Lantai Kamar Mandi 2.5 m2 76,254 0.68%
4 Bak mandi Tempel 1 Bh 54,467 0.49%
5 Closed 1 Bh 54,467 0.49%
6 Pintu Kamar Mandi 1 Bh 76,254 0.68%
7 Saringan Air 1 Bh 10,893 0.10%
No.
Pembulatan Kontrak
171.500,-
Prestasi lapangan
8 Intalasi Air Bersih 4 m' 108,935 0.97%
F Pekerjaan Lain - lain -
1 Carport 5 m' 163,402 1.46%
2 Pemberesan 1 Bh 76,254 0.68%
G Pekerjaan Tambahan -
1 Canopi Enterance + Topi -topi 1 ls 817,009 7.29%
4 Pembesian ( Rp. 5500 X 60 M2 ) 1 ls 359,484 3.21% 25
NILAI KONTRAK 11,209,365 100.00%
Jumlah :
Retensi Pekerjaan ( 100 Hari ) = 5% -
Jumlah Tagihan Progrees Pekerjaan Minggu ini
Jumlah Tagihan Progrees Pekerjaan Minggu lalu
Total Tagihan Progrees Pekerjaan Minggu ini
Bobot minggu lalu =
Diajukan : Bobot minggu ini =
Bobot aktual =
163,402
196,082
544,673
381,271
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Jumlah
( Rp )
-
-
-
-
89,871
1,375,299
68,765
###
###
-
11.66
11.66
PROGRESS LAPANGAN Minggu :Tanggal :
Type 60/105
Blok / Nomor : B21
Mandor PA TAYO
No. Jenis Item Pekerjaan Volume Satuan
A Pekerjaaan Pondasi
1 Bowplank 60 Type 546,647 37,500,000
2 Galian 4.68 m3 655,977 37,500,000
3 Pondasi Batu kali 4.68 m3 1,822,157 37,500,000
4 Cor sloof 42.5 m' 1,275,510 37,500,000
5 Pasang Paralon 3" 12 m' 364,431 37,500,000
6 Galian Septictank 1 ls 400,875 37,500,000
7 Urugan elevasi lantai 9.375 m3 437,318 37,500,000
B Pekerjaan Dinding
1 Dinding Bata 128.65 m2 6,000,000 37,500,000
2 Kusen + Daun Pintu,Jendela 11.79 m2 886,296 37,500,000
3 Plesteran + Acian Dinding 187.71 m2 6,869,533 37,500,000
4 Cor Kolom Praktis 30 m' 728,863 37,500,000
5 Cor Ring Balk 42.5 m' 911,079 37,500,000
7 Rooster 1 ls 364,431 37,500,000
8 Dinding Bata Ampig 11.05 m2 1,093,294 37,500,000
9 Cor Topi Panel 0.1 m3 546,647 37,500,000
C Pekerjaan Atap
1 Pasang Genteng Morando 58 m2 1,093,294 37,500,000
2 Nok / Karpusan 6 m' 364,431 37,500,000
3 Pasang ListPlank 2/20 20 m' 364,431 37,500,000
4 Ban-banan Atap Pembatas 20 m' 364,431 37,500,000
5 Pasang Rangka Plafond 54 m2 747,085 37,500,000
6 Pasang Plafond Enthernit 54 m2 747,085 37,500,000
D Pekerjaaan Pintu & Jendela
1 Pasang Engsel Jendela 5 Bh 309,767 37,500,000
2 Pasang Engsel Pintu & Kunci 5 Bh 546,647 37,500,000
3 Pasang Slot 5 Bh 91,108 37,500,000
4 Pasang Hak angin 5 Bh 91,108 37,500,000
E Keramik
1 Keramik Lantai 40x40 60 m2 2,551,020 37,500,000
2 Keramik Dinding 20x25 6 m2 546,647 37,500,000
3 Keramik Lantai Kamar Mandi 2.5 m2 255,102 37,500,000
4 Bak mandi Tempel 1 Bh 182,216 37,500,000
5 Closed 1 Bh 182,216 37,500,000
6 Pintu Kamar Mandi 1 Bh 255,102 37,500,000
7 Saringan Air 1 Bh 36,443 37,500,000
8 Intalasi Air Bersih 4 m' 364,431 37,500,000
F Pekerjaan Lain - lain 37,500,000
Pembulatan Kontrak
171.500,-
1 Carport 5 m' 546,647 37,500,000
2 Pemberesan 1 Bh 255,102 37,500,000
G Pekerjaan Tambahan
1 Canopi Enterance + Topi -topi 1 ls 2,000,000 37,500,000
2 Pembesian ( Rp. 5500 X 60 M2 ) 1 ls 1,202,626 37,500,000
3 Pemasangan ornamen batu alam 1 ls 1,500,000 37,500,000
NILAI KONTRAK 37,500,000
Retensi Pekerjaan ( 100 Hari ) = 5% -
Jumlah Tagihan Progrees Pekerjaan Minggu ini
Jumlah Tagihan Progrees Pekerjaan Minggu lalu
Total Tagihan Progrees Pekerjaan Minggu ini
Diajukan :
Bobot
1.46% 100 546,647
1.75% 25 163,994
4.86% -
3.40% -
0.97% -
1.07% -
1.17% -
16.00% -
2.36% -
18.32% -
1.94% -
2.43% -
0.97% -
2.92% -
1.46% -
2.92% -
0.97% -
0.97% -
0.97% -
1.99% -
1.99% -
0.83% -
1.46% -
0.24% -
0.24% -
-
6.80% -
1.46% -
0.68% -
0.49% -
0.49% -
0.68% -
0.10% -
0.97% -
Prestasi lapangan
Jumlah
( Rp )
1.46% -
0.68% -
5.33% -
3.21% -
4.00% - (0)
100.00%
Jumlah : 710,641
35,532
675,109
675,109
Bobot minggu lalu = -
Bobot minggu ini = 1.80 17.5 17.5 15
Bobot aktual = 1.80 5.25 14 7.512.25 42.25 5.4
7.5 642.5 73.75 33.9 150.15
REKAPAN PROGRESS DAN UPAH MANDORMinggu Ke : VIITanggal : 11_11_2011PT. Persada Bumi Kencana
No Jenis Kontrak Total Tagihan Pembayaran s/d hari ini Pembayaran Minggu ini
1 TAYO1 Rumah B21 11,400,000 (0.00) 90.42 90.42 10,849,881 542,494 10,307,387 10,307,387 (0)2 Rumah B32 11,400,000 4.54 81.29 85.83 10,299,761 514,988 9,267,334 9,903,784 636,450 3 Rumah B14 11,209,365 5.68 7.66 13.34 1,574,104 78,705 858,949 1,495,399 636,450 4 Rumah B18 17,289,999 12.05 7.66 19.71 3,587,381 179,369 1,324,895 3,408,012 2,083,117
3,356,016 2 PA TAYO
1 Rumah B02 11,209,365 11.66 - 11.66 1,375,299 68,765 - 1,306,534 1,306,534 2 Rumah B22 37,500,000 1.80 - 1.80 710,641 35,532 - 675,109 675,109
1,981,643
Rp 5,337,659
Cikunir, 11 November 2011di Periksa Di Setujui Di Ajukan
Ujang C Mursidi AGUS
Nilai Kontrak
(Rp)
Bobot Aktual %
Bobot s.d minggu lalu
Bobot s.d minggu ini
Retensi 5%
Pembayaran s\d Minggu
lalu