PROGRESS LAPANGAN Minggu :Tanggal :
Type 90/60
Blok / Nomor : A06
Mandor KAMAL
No Jenis Item Pekerjaan Satuan Bobot
A Pekerjaaan Pondasi
1 Bowplank 50 Type 150,000 0.72% 100 150,000
2 Galian 20 m3 310,000 1.50% 100 310,000
3 Pondasi Batu kali 12 m3 480,000 2.32% 100 480,000
4 Pasang Paralon 3" 50 m' 125,000 0.60% 50 62,500
5 Galian Septictank 1 ls 400,000 1.93% -
6 Urugan elevasi lantai 15 m3 52,500 0.25% 100 52,500
B Pekerjaan Beton
1 Pondasi beton cakar ayam 120x120x25 8.00 bh 1,600,000 7.73% 100 1,600,000
2 Sloof Beton 2.90 m3 580,800 2.81% 100 580,800
3 Kolom beton 15/30 1.43 m3 214,200 1.03% -
4 Kolom beton 15/15 1.45 m3 218,025 1.05% 50 109,013
5 Kolom beton 20/30 1.51 m3 226,800 1.10% 50 113,400
6 Kolom beton 30/30 3.67 m3 550,800 2.66% 100 550,800
7 Balok beton 15/20 2.90 m3 435,600 2.10% -
8 Balok beton15/25 5.07 m3 761,063 3.68% -
9 Balok beton 15/30 1.34 m3 200,475 0.97% -
10 Balok beton 20/40 2.29 m3 343,200 1.66% -
11 Balok beton 25/45 7.43 m3 1,039,500 5.02% -
12 Balok beton 30/55 6.60 m3 990,000 4.78% -
13 Balok beton 10/20 0.26 m3 39,600 0.19% -
14 Tangga beton 1.68 m3 420,000 2.03% -
15 Dak beton t : 12 cm 6.00 m3 1,200,000 5.80% -
16 Plat beton t : 10 cm 1.62 m3 243,000 1.17% -
B Pekerjaan Dinding
1 Dinding Bata 128.65 m2 1,929,750 9.32% 50 964,875
2 Plesteran + Acian Dinding 187.72 m2 2,252,640 10.88% 10 225,264
3 Dinding Bata Ampig 11.06 m2 221,200 1.07% -
3 ban-ban pembatas 11.01 m2 990,900 4.79% -
C Pekerjaan Kayu
1 Pasang Genteng plat 58 m2 406,000 1.96% -
2 Nok / Karpusan 6 m' 54,000 0.26% -
3 Pasang ListPlank 2/20 20 m' 180,000 0.87% -
4 Pasang Rangka Plafond 54 m2 216,000 1.04% -
5 Pasang Plafond Enthernit 54 m2 216,000 1.04% -
E Keramik
Volume
Pembulatan Kontrak 230,000
Prestasi lapangan
Jumlah ( Rp
)
1 Keramik Lantai 40x40 91 m2 1,183,000 5.71% -
2 Keramik Dinding 20x25 6 m2 240,000 1.16% -
3 Keramik Lantai Kamar Mandi 5 m2 100,000 0.48% -
3 Keramik Lantai Tangga 30 x 30 5 m2 250,000 1.21% -
4 Bak mandi Tempel 2 Bh 200,000 0.97% -
5 Closed duduk 2 Bh 30,000 0.14% -
6 Pintu Kamar Mandi 2 Bh 180,000 0.87% -
7 Saringan Air 2 Bh 30,000 0.14% -
8 Intalasi Air kotor 49 m' 367,500 1.78% -
8 Intalasi Air Bersih 49 m' 367,500 1.78% -
F Pekerjaan Lain - lain
1 Pemberesan 1 Bh 404,947 1.96% -
G Pekerjaan Tambahan
1 Plesteran + Acian Dinding hook 1 ls 300,000 1.45% 50 150,000
NILAI KONTRAK ### 100%
Jumlah : 5,349,152
Retensi Pekerjaan ( 100 Hari ) = 5% - 267,458
Jumlah Tagihan Progrees Pekerjaan Minggu ini 5,081,694
Jumlah Tagihan Progrees Pekerjaan Minggu lalu 4,675,318
Total Tagihan Progrees Pekerjaan Minggu ini 406,376
Bobot minggu lalu = 22.59
Bobot minggu ini = 24.55
Bobot aktual = 1.96
PROGRESS LAPANGAN Minggu :Tanggal :
Type 90/60
Blok / Nomor : A07
Mandor KAMAL
No Jenis Item Pekerjaan Satuan Bobot
A Pekerjaaan Pondasi
1 Bowplank 50 Type 150,000 0.72% 100
2 Galian 20 m3 310,000 1.50% 100
3 Pondasi Batu kali 12 m3 480,000 2.32% 100
4 Pasang Paralon 3" 50 m' 125,000 0.60% 50
5 Galian Septictank 1 ls 400,000 1.93%
6 Urugan elevasi lantai 15 m3 52,500 0.25% 100
B Pekerjaan Beton
1 Pondasi beton cakar ayam 120x 8.00 bh 1,600,000 7.73% 100
2 Sloof Beton 2.90 m3 580,800 2.81% 100
3 Kolom beton 15/30 1.43 m3 214,200 1.03%
4 Kolom beton 15/15 1.45 m3 218,025 1.05% 50
5 Kolom beton 20/30 1.51 m3 226,800 1.10% 50
6 Kolom beton 30/30 3.67 m3 550,800 2.66% 100
7 Balok beton 15/20 2.90 m3 435,600 2.10%
8 Balok beton15/25 5.07 m3 761,063 3.68%
9 Balok beton 15/30 1.34 m3 200,475 0.97%
10 Balok beton 20/40 2.29 m3 343,200 1.66%
11 Balok beton 25/45 7.43 m3 1,039,500 5.02%
12 Balok beton 30/55 6.60 m3 990,000 4.78%
13 Balok beton 10/20 0.26 m3 39,600 0.19%
14 Tangga beton 1.68 m3 420,000 2.03%
15 Dak beton t : 12 cm 6.00 m3 1,200,000 5.80%
16 Plat beton t : 10 cm 1.62 m3 243,000 1.17%
B Pekerjaan Dinding
1 Dinding Bata 128.65 m2 1,929,750 9.32% 50
2 Plesteran + Acian Dinding 187.72 m2 2,252,640 10.88% 35
3 Dinding Bata Ampig 11.06 m2 221,200 1.07%
3 ban-ban pembatas 11.01 m2 990,900 4.79%
C Pekerjaan Kayu
1 Pasang Genteng plat 58 m2 406,000 1.96%
2 Nok / Karpusan 6 m' 54,000 0.26%
3 Pasang ListPlank 2/20 20 m' 180,000 0.87%
4 Pasang Rangka Plafond 54 m2 216,000 1.04%
5 Pasang Plafond Enthernit 54 m2 216,000 1.04%
E Keramik
Volume
Pembulatan
Kontrak 230,000
Prestasi lapanga
n
1 Keramik Lantai 40x40 91 m2 1,183,000 5.71%
2 Keramik Dinding 20x25 6 m2 240,000 1.16%
3 Keramik Lantai Kamar Mandi 5 m2 100,000 0.48%
3 Keramik Lantai Tangga 30 x 30 5 m2 250,000 1.21%
4 Bak mandi Tempel 2 Bh 200,000 0.97%
5 Closed duduk 2 Bh 30,000 0.14%
6 Pintu Kamar Mandi 2 Bh 180,000 0.87%
7 Saringan Air 2 Bh 30,000 0.14%
8 Intalasi Air kotor 49 m' 367,500 1.78%
8 Intalasi Air Bersih 49 m' 367,500 1.78%
F Pekerjaan Lain - lain
1 Pemberesan 1 Bh 404,947 1.96%
G Pekerjaan Tambahan
1 Plesteran + Acian Dinding hook 1 ls 300,000 1.45% 50
NILAI KONTRAK ### 100%
Jumlah :
Retensi Pekerjaan ( 100 Hari ) = 5% -
Jumlah Tagihan Progrees Pekerjaan Minggu ini
Jumlah Tagihan Progrees Pekerjaan Minggu lalu
Total Tagihan Progrees Pekerjaan Minggu ini
Bobot minggu lalu =
Bobot minggu ini =
Bobot aktual =
150,000
310,000
480,000
62,500
-
52,500
###
580,800
-
109,013
113,400
550,800
-
-
-
-
-
-
-
-
-
-
964,875
788,424
-
-
-
-
-
-
-
Jumlah
( Rp )
-
-
-
-
-
-
-
-
-
-
-
150,000
###
295,616
###
###
192,375
26.20
27.13
0.93
PROGRESS LAPANGAN Minggu :Tanggal :
Type 90/60
Blok / Nomor : A07
Mandor KAMAL
No Jenis Item Pekerjaan Volume Satuan Bobot
A Pekerjaaan Pondasi
1 Bowplank 50 Type 150,000 0.72%
2 Galian 20 m3 310,000 1.50%
3 Pondasi Batu kali 12 m3 480,000 2.32%
4 Pasang Paralon 3" 50 m' 125,000 0.60%
5 Galian Septictank 1 ls 400,000 1.93%
6 Urugan elevasi lantai 15 m3 52,500 0.25%
B Pekerjaan Beton
1 Pondasi beton cakar ayam 120x120x25 8.00 bh 1,600,000 7.73%
2 Sloof Beton 2.90 m3 580,800 2.81%
3 Kolom beton 15/30 1.43 m3 214,200 1.03%
4 Kolom beton 15/15 1.45 m3 218,025 1.05%
5 Kolom beton 20/30 1.51 m3 226,800 1.10%
6 Kolom beton 30/30 3.67 m3 550,800 2.66%
7 Balok beton 15/20 2.90 m3 435,600 2.10%
8 Balok beton15/25 5.07 m3 761,063 3.68%
9 Balok beton 15/30 1.34 m3 200,475 0.97%
10 Balok beton 20/40 2.29 m3 343,200 1.66%
11 Balok beton 25/45 7.43 m3 1,039,500 5.02%
12 Balok beton 30/55 6.60 m3 990,000 4.78%
13 Balok beton 10/20 0.26 m3 39,600 0.19%
14 Tangga beton 1.68 m3 420,000 2.03%
15 Dak beton t : 12 cm 6.00 m3 1,200,000 5.80%
16 Plat beton t : 10 cm 1.62 m3 243,000 1.17%
B Pekerjaan Dinding
1 Dinding Bata 128.65 m2 1,929,750 9.32%
2 Plesteran + Acian Dinding 187.72 m2 2,252,640 10.88%
3 Dinding Bata Ampig 11.06 m2 221,200 1.07%
3 ban-ban pembatas 11.01 m2 990,900 4.79%
C Pekerjaan Kayu
1 Pasang Genteng plat 58 m2 406,000 1.96%
2 Nok / Karpusan 6 m' 54,000 0.26%
3 Pasang ListPlank 2/20 20 m' 180,000 0.87%
4 Pasang Rangka Plafond 54 m2 216,000 1.04%
5 Pasang Plafond Enthernit 54 m2 216,000 1.04%
E Keramik
Pembulatan Kontrak 230,000
1 Keramik Lantai 40x40 91 m2 1,183,000 5.71%
2 Keramik Dinding 20x25 6 m2 240,000 1.16%
3 Keramik Lantai Kamar Mandi 5 m2 100,000 0.48%
3 Keramik Lantai Tangga 30 x 30 5 m2 250,000 1.21%
4 Bak mandi Tempel 2 Bh 200,000 0.97%
5 Closed duduk 2 Bh 30,000 0.14%
6 Pintu Kamar Mandi 2 Bh 180,000 0.87%
7 Saringan Air 2 Bh 30,000 0.14%
8 Intalasi Air kotor 49 m' 367,500 1.78%
8 Intalasi Air Bersih 49 m' 367,500 1.78%
F Pekerjaan Lain - lain
1 Pemberesan 1 Bh 404,947 1.96%
G Pekerjaan Tambahan
1 Plesteran + Acian Dinding hook 1 ls 300,000 1.45%
NILAI KONTRAK ### 100%
Retensi Pekerjaan ( 100 Hari ) = 5% -
Jumlah Tagihan Progrees Pekerjaan Minggu ini
Jumlah Tagihan Progrees Pekerjaan Minggu lalu
Total Tagihan Progrees Pekerjaan Minggu ini
Bobot minggu lalu =
Bobot minggu ini =
Bobot aktual =
100 150,000
100 310,000
100 480,000
50 62,500
-
100 52,500
100 1,600,000
100 580,800
-
50 109,013
50 113,400
100 550,800
-
-
-
-
-
-
-
-
-
-
50 964,875
25 563,160
-
-
-
-
-
-
-
Prestasi lapanga
n
Jumlah ( Rp
)
-
-
-
-
-
-
-
-
-
-
-
100 300,000
Jumlah : 5,837,048
291,852
5,545,195
5,210,320
334,875
Bobot minggu lalu = 25.17
Bobot minggu ini = 26.79
Bobot aktual = 1.62
REKAPAN PROGRESS DAN UPAH MANDORMinggu Ke : IVTanggal : 09_11_2011PT. Persada Bumi Kencana
No Total Tagihan
1 KAMAL
1 RUKO A06 20,700,000 1.96 22.59 24.55 5,349,152 267,458 4,675,318 5,081,694 406,376
2 RUKO A07 20,700,000 0.93 26.20 27.13 5,912,312 295,616 5,424,321 5,616,696 192,375
3 RUKO A08 20,700,000 1.62 25.17 26.79 5,837,048 291,852 5,210,320 5,545,195 334,875
Rp 933,626
Cikunir, 11 November 2011
Di Periksa Di Setujui Di Ajukan
Ujang C Mursidi AGUS
Jenis Kontrak
Nilai Kontrak (Rp)
Bobot Aktual %
Bobot s.d minggu
lalu
Bobot s.d minggu ini
Retensi 5%
Pembayaran s\d Minggu
lalu
Pembayaran s/d hari ini
Pembayaran Minggu ini
PROGRESS LAPANGAN Minggu :Tanggal :
Type 90/60
Blok / Nomor : ruko
Mandor
Jenis Item Pekerjaan
A Pekerjaaan Pondasi
1 Bowplank 50 Type
2 Galian 20 m3
3 Pondasi Batu kali 12 m3
4 Pasang Paralon 3" 50 m'
5 Galian Septictank 1 ls
6 Urugan elevasi lantai 15 m3
B Pekerjaan Beton
1 Pondasi beton cakar ayam 120x120x25 8.00 bh
2 Sloof Beton 2.90 m3
3 Kolom beton 15/30 1.43 m3
4 Kolom beton 15/15 1.45 m3
5 Kolom beton 20/30 1.51 m3
6 Kolom beton 30/30 3.67 m3
7 Balok beton 15/20 2.90 m3
8 Balok beton15/25 5.07 m3
9 Balok beton 15/30 1.34 m3
10 Balok beton 20/40 2.29 m3
11 Balok beton 25/45 7.43 m3
12 Balok beton 30/55 6.60 m3
13 Balok beton 10/20 0.26 m3
14 Tangga beton 1.68 m3
15 Dak beton t : 12 cm 6.00 m3
16 Plat beton t : 10 cm 1.62 m3
B Pekerjaan Dinding
1 Dinding Bata 129 m2
2 Plesteran + Acian Dinding 188 m2
3 Dinding Bata Ampig 11.06 m2
3 ban-ban pembatas 11.01 m2
C Pekerjaan Kayu
1 Pasang Genteng plat 58 m2
2 Nok / Karpusan 6 m'
3 Pasang ListPlank 2/20 20 m'
4 Pasang Rangka Plafond 54 m2
5 Pasang Plafond Enthernit 54 m2
No
Volume
Satuan
mg1
mg2
mg3
mg4
mg5
mg6
mg7
mg8
mg9
E Keramik
1 Keramik Lantai 40x40 91 m2
2 Keramik Dinding 20x25 6 m2
3 Keramik Lantai Kamar Mandi 5 m2
3 Keramik Lantai Tangga 30 x 30 5 m2
4 Bak mandi Tempel 2 Bh
5 Closed duduk 2 Bh
6 Pintu Kamar Mandi 2 Bh
7 Saringan Air 2 Bh
8 Intalasi Air kotor 49 m'
8 Intalasi Air Bersih 49 m'
F Pekerjaan Lain - lain
1 Pemberesan 1 Bh
G Pekerjaan Tambahan
1 Plesteran + Acian Dinding hook 1 ls
NILAI KONTRAK
Retensi Pekerjaan ( 100 Hari ) = 5%
Jumlah Tagihan Progrees Pekerjaan Minggu ini
Jumlah Tagihan Progrees Pekerjaan Minggu lalu
Total Tagihan Progrees Pekerjaan Minggu ini
Bobot aktual =
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
mg10
mg11
mg12
-
-
-
-
-
-
-
-
-
-
-
-
Juml -
-
-
-
-
-
Bobot aktual = -