Project Efficiency

Post on 07-Jan-2016

27 views 2 download

description

Project Efficiency. INOVASI. Metode Pelaksanaan Pekerjaan Drain Balkon. Metode Coring. Metode Sparing. Pekerjaan Sparing Ø 2 ”= Bahan = Rp . 13.187,00 Alat Bantu = Rp . 3.297,00 Upah = Rp . 14.000,00 TOTAL= Rp . 30.484,00. Pekerjaan Coring dan Grouting : - PowerPoint PPT Presentation

Transcript of Project Efficiency

Project Efficiency

INOVASIMetode Pelaksanaan

Pekerjaan Drain Balkon

Metode Coring Metode Sparing

Pekerjaan Coring dan Grouting :

Ø 2” = Rp. 75.000,00 (sudah termasuk upah,alat,dan bahan)

Pekerjaan Sparing

Ø 2” =

Bahan = Rp. 13.187,00Alat Bantu = Rp. 3.297,00Upah = Rp. 14.000,00

TOTAL = Rp. 30.484,00

Rp 75.000,00 – Rp 30.484,00

Hemat Rp. 44.516,00

Hemat >50 % BIAYA

Frangky Ronaldo Aruan (2013177)