Analisa Harga Satuan Bondex Dan Multi Revisi

Post on 23-Jun-2015

754 views 15 download

Transcript of Analisa Harga Satuan Bondex Dan Multi Revisi

PERBANDINGAN BIAYA PEMBUATAN PLAT LANTAI DENGAN CARA KONVENSIONAL DAN PLAT FLOORDECK / m2

NO ITEM PEKERJAAN VOL SATHarga Satuan

matrialHarga Satuan

Upah Jumlah Matrial Jumlah Upah

TOTAL UPAH DAN MATRIAL

A PEKERJAAN BETON PLAT LANTAI SISTEM KONVENSIONAL / M2 433,659Rp

1Pekerjaan beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 0.12 m3 119,985Rp 6,894Rp 126,879Rp

Portland Cement 44.52 kg 1,000Rp 44,520Rp Pasir beton ( kg ) 83.76 kg 107Rp 8,974Rp koral beton kg 125.64 kg 119Rp 14,891Rp Air 25.80 Liter 2,000Rp 51,600Rp Pekerja 0.20 OH 25,000Rp 4,950Rp Tukang batu 0.03 OH 39,500Rp 1,304Rp Kepala tukang 0.00 OH 42,500Rp 143Rp Mandor 0.01 OH 50,000Rp 498Rp

2 Pembesian besi polos atau besi ulir 11.04 106,507Rp 5,535Rp 112,043Rp Besi beton (polos/ulir) 11.59 kg 9,000Rp 104,354Rp Kawat beton 0.17 kg 13,000Rp 2,153Rp Pekerja 0.08 OH 25,000Rp -Rp 1,932Rp Tukang besi 0.08 OH 39,500Rp -Rp 3,053Rp Kepala tukang 0.01 OH 42,500Rp -Rp 329Rp Mandor 0.00 OH 50,000Rp -Rp 221Rp

3 Pekerjaan bekisting untuk lantai 1.00 m2 162,150Rp 32,588Rp 194,738Rp Kayu kelas III 0.04 m3 1,200,000Rp 48,000Rp -Rp Paku 5 cm – 12 cm 0.40 kg 13,000Rp 5,200Rp -Rp Minyak bekisting 0.20 Liter 6,000Rp 1,200Rp -Rp Balok kayu kelas II 0.02 m3 1,300,000Rp 19,500Rp -Rp Plywood tebal 9 mm 0.35 Lbr 115,000Rp 40,250Rp -Rp Dolken kayu galam, ö(8-10) cm, panjang 4 m 6.00 Batang 8,000Rp 48,000Rp -Rp Pekerja 0.66 OH -Rp 25000 -Rp 16,500Rp Tukang kayu 0.33 OH -Rp 39500 -Rp 13,035Rp Kepala tukang 0.03 OH -Rp 42500 -Rp 1,403Rp Mandor 0.03 OH -Rp 50000 -Rp 1,650Rp

NO ITEM PEKERJAAN VOL SATHarga Satuan

matrialHarga Satuan

Upah Jumlah Matrial Jumlah Upah

TOTAL UPAH DAN MATRIAL

B PEKERJAAN BETON PLAT LANTAI SISTEM BONDEX / M2 405,441Rp

1Pekerjaan beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 0.11 m3 113,986Rp 6,550Rp 120,535Rp

Portland Cement 42.29 kg 1,000Rp 42,294Rp Pasir beton ( kg ) 79.57 kg 107Rp 8,526Rp koral beton kg 119.36 kg 119Rp 14,146Rp Air 24.51 Liter 2,000Rp 49,020Rp Pekerja 0.19 OH 25,000Rp 4,703Rp Tukang batu 0.03 OH 39,500Rp 1,238Rp Kepala tukang 0.00 OH 42,500Rp 136Rp Mandor 0.01 OH 50,000Rp 473Rp

2 Pembesian besi polos atau besi ulir 5.52 53,254Rp 2,768Rp 56,021Rp Besi beton (polos/ulir) 5.80 kg 9,000Rp 52,177Rp Kawat beton 0.08 kg 13,000Rp 1,077Rp Pekerja 0.04 OH 25,000Rp -Rp 966Rp Tukang besi 0.04 OH 39,500Rp -Rp 1,527Rp Kepala tukang 0.00 OH 42,500Rp -Rp 164Rp Mandor 0.00 OH 50,000Rp -Rp 110Rp

3 Pekerjaan bekisting untuk lantai 1.00 m2 220,738Rp 8,147Rp 228,884Rp plat bondex 1.03 m2 140,000Rp 144,200Rp Kayu kelas III 0.04 m3 1,200,000Rp 48,000Rp -Rp Paku 5 cm – 12 cm 0.10 kg 13,000Rp 1,300Rp -Rp Minyak bekisting 0.05 Liter 6,000Rp 300Rp -Rp Balok kayu kelas II 0.00 m3 1,300,000Rp 4,875Rp -Rp Plywood tebal 9 mm 0.09 Lbr 115,000Rp 10,063Rp -Rp Dolken kayu galam, ö(8-10) cm, panjang 4 m 1.50 Batang 8,000Rp 12,000Rp -Rp Pekerja 0.17 OH -Rp 25000 -Rp 4,125Rp Tukang kayu 0.08 OH -Rp 39500 -Rp 3,259Rp Kepala tukang 0.01 OH -Rp 42500 -Rp 351Rp Mandor 0.01 OH -Rp 50000 -Rp 413Rp