- Jadwal PLTMG Selayar

Post on 07-Jul-2018

218 views 0 download

Transcript of - Jadwal PLTMG Selayar

8/18/2019 - Jadwal PLTMG Selayar

http://slidepdf.com/reader/full/-jadwal-pltmg-selayar 1/1

ID Task Name Duration Start Finish

1 Penandatanganan Kontrak 1 day Mon 28/12/15 Mon 28/12/15

2 Efektif Kontrak 1 day Mon 11/01/16 Mon 11/01/16

3 PERSIAPAN 14 days Tue 12/01/16 Tue 26/01/16

6 SURVEY DAN PENGUMPULAN DATA 24 days Wed 27/01/16 Thu 25/02/16

7 Koordinasi dengan Pemrakarsa 3 days Wed 27/01/16 Fr i 29/01/16

8 Persiapan deskripsi rencana kegiatan 6 days Sat 30/01/16 Fri 05/02/16

9 Persiapan dan Pengajuan Form Penapisan 

5 days Tue 02/02/16 Mon 08/02/16

10 Koordinasi awal dengan BLH Selayar, BAPPEDA 

14 days Tue 02/02/16 Thu 18/02/16

11 Persiapan Sosialisasi & Pelaksanaan Konsultasi 8 days Mon 08/02/16 Tue 16/02/16

12 Pengumpulan Data Primer & Sekunder   20 days Mon 01/02/16 Thu 25/02/16

13 PENYUSUNAN DOKUMEN UKL-UPL 15 days Fri 26/02/16 Wed 16/03/16

14 Penyusunan Dokumen UKL-UPL 10 days Fri 26/02/16 Wed 09/03/16

15 Penyampaian Draft UKL - UPL ke PLN 2 days Thu 10/03/16 Fr i 11/03/16

16 Rapat Pembahasan Draft UKL - UPL 1 da Mon 14/03/16 Mon 14/03/16

17 Perbaikan dan Penyampaian Hasil Perbaikan Ke 1 da Wed 16/03/16 Wed 16/03/16

18 PROSES PEMERIKSAAN DAN PENILAIAN 

8 days Tue 22/03/16 Thu 31/03/16

19 Penyampaian Draft UKL-UPL ke BLH 2 days Tue 22/03/16 Wed 23/03/16

20 Rapat Pemeriksaan dan Pembahasan UKL-UPL 2 days Thu 24/03/16 Fr i 25/03/16

21 Perbaikan dan Penyampaian Hasil Perbaikan Ke PL 2 days Mon 28/03/16 Tue 29/03/16

22 Penerbitan Rekomendasi Kelayakan Lingkungan 2 days Wed 30/03/16 Thu 31/03/16

23 PENERBITAN IZIN LINGKUNGAN 1 day Fri 01/04/16 Fri 01/04/16

24 PENYERAHAN HASIL PEKERJAAN 1 day Mon 04/04/16 Mon 04/04/16

W T F S S M T W T F S S M T W

  20 Dec '15 10 Jan '16 31 Jan '16 21 Feb '16 13 Mar '16 03 Apr '1

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Progress

Deadline

BAB IIIJADWAL PELAKSANAAN PEKERJAAN

PENYUSUNAN DOKUMEN UKL-UPL DAN IZIN LINGKUNGAN PLTMG SELAYAR (10 MW)

Page 1