Ministry of Higher Education and Highways Road Development Authority
25th Project Steering Committee Meeting ADB Funded
Integrated Road Investment Program (iROAD)
Asian Development Bank
22-06-2018
Overall Status of Rural Road PackagesProvince No. of
PackagesNo. of Roads
Km No. of Roads surfacing
completed
No. of km completed
Physical Progress as at 31 May 2018
Planned (%)
Actual (%)
Southern 09 183 582 156 560 100.0 94.3
Central 09 144 595 88 507 94.5 89.1
Sabaragamuwa 06 101 472 22 294 81.4 65.2
North Central 07 115 500 55 380 86.1 76.8
North Western 08 114 705 28 325 84.2 45.4
Kalutara 03 83 277 4 88 84.8 44.6
Total 42 740 3,131 353 2,154 89.8 73.3
25-Jun-18
Overall Status of Road Management Contracts (RMC)National Roads
The roads will be rehabilitated / improved and routine maintained for a period of SIX years
25-Jun-18
Name of the Road Length (km) Status
Maradankadawala – Habarana Road (A011) 25.0 Financial bid evaluation nearing completion.
Galle District(Karapitiya – Nagoda Road: B248, B454Udugama Bar Junction – Thavalama Road: B129, B429, B156)
51.7 IFB published. Closing date of bids on 20 September 2018
Thalawa – Kekirawa – Ganewalpola –Galenbidunuwewa – Dachchihalmillewa Road
80.0 Design works are in progress
Palmadulla – Ambilipitiya – Padanangala Road (A018) 66.0 Design works are in progress
Colombo – Kandy Road(Ambepusa – Peradeniya section)
42.3 Preliminary survey works and Design works in progress
265.0
Source USD -Mn
Share of Total (%)
Indicative Tranching Plan and Amount($Million)
1(2014)
2(2014)
3(2015)
4(2017)
5(2018)
6(2020)
ADB 800 88.3 100.0 107.0 200.0 150.0 150.0 93.0
GOSL 106 11.7 18.0 12.5 25.0 18.0 18.0 14.5
Total 906 100.0 118.0 119.5 225.0 168.0 168.0 107.5
Financial StatusTranching Plan
Loan signed for Tranche 1, 2, 3, & 4
No Description LKR (Mn)
1 Budget Allocation 8,000
2 Expenditure as at 20 June 2018 5,425
3 % Financial achievement 68%
Allocation - 2018
Cumulative Expenditure - Province
Province Total Contract Sum(LKR Mn)
Expenditure as at 20 June 2018
(LKR Mn)
%
Southern 13,847 12,006 86.7
Central 15,665 11,098 70.8
Sabaragamuwa 11,849 6,646 56.1
North Central 10,500 5,935 56.5
North Western 14,575 6,773 46.5
KalutharaDistrict
5,542 2,167 39.1
Total 71,978 44,625 62.0
Cumulative Expenditure - Contractor Name of the Contractor Total Contract
Amount(LKR Mn)
Number of Contracts
Amount paid as at 20 June 2018
(LKR Mn)
K.D. Ebert & Sons Holdings (Pvt.) Ltd 12,470 07 6,898
K.D.A. Weerasinghe & Company (Pvt.) Ltd 4,800 03 4,404
CML – MTD Construction Ltd 4,933 03 4,778
R. R. Construction (Pvt.) Ltd 3,073 02 2,770
Edward & Christie 3,346 02 2,500
Nawaloka Construction Company (Pvt.) Ltd 3,450 02 1,800
Sierra Construction (Pvt.) Ltd 9,290 05 6,602
Maga Engineering (Pvt.) Ltd 13,169 08 7,325
V. V. Karunaratne & Company 4,766 03 1,935
Ranken Railway Construction Company (China)
5,679 03 2,417
KDAW – BMG JV 2,124 01 1,211
OCPL – RCPL JV 3,629 02 1,195
Tissa – AMSK JV 1,249 01 790
Total 71,978 42 44,625
1. Unsatisfactory physical progress of few contract packages in Southern, Central, Sabaragmuwa, North Western provinces and Kalutara district. Contractors are;(i) K.D. Ebert & Sons (ii) V.V. Karunaratne(iii) Ranken Railway(iv) Olympus – Rani JV
25-Jun-18 8
Issues
9
Progress of Civil Works Contracts up to
31st May 2018
Loan 3171 – SRI : Integrated Road Investment Program
Consulting Services for Project ImplementationIncluding Construction Supervision, Contract
Management and Other Activities in Sabaragamuwa, Central Provinces and Kalutara
District – PIC 03
Overall Physical Progress Summary –iROAD-Central Province /(up to 31 May 2018)
16
Package
No.Contractor
Accepted
Contract
Amount/
(Rs. Million)
No. of
Roads
Total Road
Length as
per the
BOQ/ (km)
No. of
Roads
Civil
Works in
Progress
Total road
pavement length
(asphalt+concrete)
completed (km)
Actual Physical
Progress as at 30
April 2018 (%)
Physical Progress; Cumulative
Status up to 31 May 2018 (%)
Target (Revised) Actual
KA 01 Sierra 1,756 17 76.20 16 69.90 87.70% 100.00*(95.40)% 89.00%
KA 02 Sierra 1,924 17 70.85 17 70.30 96.53% 100.00*(97.20)% 97.10%
KA 03 Edward and Christie. 2,097 16 73.95 16 64.66 90.54% 100.00*(96.00)% 91.73%
MA 01 KD Ebert 1,622 18 75.70 16 53.83 62.88% 100.00*(72.30)% 64.66%
MA 02 Edward and Christie. 1,249 14 57.00 14 55.45 99.95% 100.00% 100.00%
MA 03 CML-MTD 1,408 19 61.30 18 60.69 98.20% 100.00*(98.20)% 98.80%
NE 01 Sierra 2,298 14 76.60 11 45.52 71.85% 100.00*(96.00)% 71.98%
NE 02 Sierra 1,242 14 38.50 14 36.03 97.00% 100.00*(99.00)% 98.00%
NE 03 Sierra 2,070 15 64.90 12 50.49 89.91% 100.00*(96.37)% 90.52%
Total / Avg. 15,666 144 595.00 134 506.87 88.28% 94.50% 89.09%
NOTE : * - Physical target percentage is based on the Revised Construction Programme (Revision 2).
17
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
Cum. Plan % 0.11% 0.54% 1.81% 4.69% 6.87% 10.67% 14.32% 18.99% 23.78% 29.29% 33.97% 38.68% 43.60% 49.46% 54.76% 60.59% 65.49% 71.84% 77.95% 83.74% 89.40% 94.31% 98.08% 99.57% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan
%0.01% 0.29% 1.34% 3.29% 5.08% 8.15% 11.93% 16.57% 22.22% 27.38% 34.10% 39.32% 44.11% 49.37% 53.57% 58.51% 62.17% 65.83% 69.92% 73.61% 76.72% 79.45% 81.82% 83.10% 84.91% 87.50% 89.58% 91.64% 92.83% 94.50% 96.09% 97.44% 98.40% 99.00% 99.47% 99.90% 100.00%
Cum. Actual % 0.03% 0.41% 1.41% 3.71% 5.73% 9.08% 13.07% 17.39% 22.62% 27.67% 33.82% 38.27% 43.00% 48.54% 53.20% 58.58% 61.84% 64.87% 69.04% 72.68% 75.74% 78.43% 80.51% 81.97% 83.41% 84.76% 86.10% 87.61% 88.28% 89.09%
Summary of Progress of Contracts–iROAD-Central Province /(up to 31 May 2018)
18
Package
NoContractor
No. of
Roads
Actual
Total
Road
Length /
(km)
No. of
Roads Civil
Works in
Progress
Road
Length Civil
works in
Progress/
(km)
Road length
of Asphalt
completed/
(km)
KA 01 Sierra 17 75.11 16 73.00 69.90
KA 02 Sierra 17 72.46 17 72.46 70.30
KA 03Edward and
Christie.16 68.55 16 68.55 64.66
MA 01 KD Ebert . 18 75.12 16 68.00 53.83
MA 02Edward and
Christie.14 55.55 14 55.55 55.45
MA 03 CML-MTD 19 60.78 18 60.75 60.69
NE 01 Sierra 14 72.45 11 65.00 45.52
NE 02 Sierra 14 36.21 14 36.21 36.03
NE 03 Sierra 15 66.11 12 62.50 50.49
Total 144.00 582.34 134.00 562.02 506.87
Package
No
ContractorAccepted Contract
Amount/ (Rs.
Million)
Total Certified Amount (Mobilization
Advance) /(Rs. Million)
KA1 Sierra Construction (Pvt.) Ltd. 1,756 1,259.08 (131.78)
KA2 Sierra Construction (Pvt.) Ltd. 1,924 1,388.69 (131.91)
KA3 Edward and Christie. 2,097 1,464.95 (179.21)
MA1KD Ebert and Sons Holdings(Pvt)
Ltd.1,622 899.22 (215.50)
MA2 Edward and Christie. 1,249 1035.28 (15.32)
MA3 CML-MTD Construction limited 1,408 1088.87 (62.94)
NE1 Sierra Construction (Pvt.) Ltd. 2,298 1,327.68 (276.77)
NE2 Sierra Construction (Pvt.) Ltd. 1,242 1,003.14 (29.83)
NE3 Sierra Construction (Pvt.) Ltd. 2,070 1,553.09 (125.60)
Total 15,666 11,020.00 (1168.86)
Overall Financial Status –iROAD-Central Province /(up to end of May 2018)
19
Progress of Culverts & Bridges /(up to 31 May 2018)
20
DistrictPackage
No.Contractor
No. of Culverts No.of Culvers
No.of
BridgesRemarks
New / Re -
Construction/
Widening
Completed / in
ProgressRepair
Completed /
in Progress
Kandy
KA1Sierra Construction (Pvt.)
Ltd.80 74 434 387 4
Three bridges completed and another
one in progress
KA2Sierra Construction (Pvt.)
Ltd.234 229 225 186 3 All bridges completed
KA3 Edward and Christie 172 161 240 238 3 All bridges completed
Matale
MA1KD Ebert and Sons
Holdings (Pvt.) Ltd.116 85 357 255 3
Design approved for all bridges and two
bridges in progress
MA2 Edward and Christie 94 94 127 127 1 Bridge is completed
MA3 CML-MTD Construction Ltd. 84 84 139 139 4 All bridges completed
Nuwara
Eliya
NE1Sierra Construction (Pvt.)
Ltd.230 183 313 254 6
Design approved for all bridges and three
bridges in progress
NE2Sierra Construction (Pvt.)
Ltd.177 176 83 76 3
One bridge is completed and another two
in progress
NE3Sierra Construction (Pvt.)
Ltd.289 245 295 240 4
Two bridges completed and another two
in progress
Total 1476 1331 2213 1902 31
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 KA1
Total Surfacing Length : 69.90 Km (93.06%)
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
Handed Over Road
21
45 Manikhinna (Pitiye Dewalaya) Galaluwa Road PRDA 1.26 1.26 100%
46 Gagasiriwatta Polgolla Road PRDA 2.62 2.62 100%
47Digana Aluthwatta Road (Aluthwatta No. 10 Junction) -
Parana Gagapitiya RoadPRDA 2.59 2.59 100%
44 Sirimalwatta Nattarampotha Road PRDA 2.47 2.47 100%
41Wattegama, Pinnalanda Junction - Thunkandura Junction
via PuwakgahadeniyaPRDA 4.53 4.53 100%
21 Angammana Nikathenna Road PRDA 1.38 1.38 100%
43 Digana Ambakotte Road PRDA 4.47 4.47 100%
52 Malwanahinna Nirella Via Main Road PS 3.51 3.21 91%
4Bambaragala Junction - Nithulemada Bus stand,
Nithulmada main road via Senarathwela PS 6.81 6.81 100%
2Medamahanuwara town - Kandekumbura Road
(Retiyagama bus stand) Via MetideniyaPRDA 7.72 7.06 91%
36 Parana Polonnaruwa PRDA 7.37 7.23 98%
1Bambaragahadeniya Junction - Madamahanuwara Via
Meeriyagolla.PS 7.06 5.69 81%
4AIskolamuduna Junction - Hiloya Road (Watagala Road) via
PoddalgodaPRDA 4.23 2.80 66%
42Pitiyegedara Junction - Polgolla 6th mile Post via
MeegamawattaPS 5.24 5.07 97%
53 Nugethenna to Kewulagama Pamunuwella Road PS 5.43 5.40 99%
3Werapitiya Road, Dunhinna Junction - Makuldeniya Road
(Makuldeniya Junction) via WaradiwelaPRDA 4.98 3.87 78%
32 Madugalla Kalawala Road PRDA/PS 3.45 2.53 73%
ROAD
NO.Road Name
Road
Catogory
Design
Length
completed
Lengthcompleted %
6 km 7 km 8 km
Surfacing
1 km 2 km 5 km3 km 4 km
22
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18
Cum. Plan % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 57.05% 62.45% 65.91% 70.52% 75.60% 80.65% 86.05% 91.77% 96.59% 99.81% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 1 % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 55.45% 58.58% 61.67% 64.63% 68.57% 71.20% 73.22% 76.70% 78.60% 80.17% 83.64% 86.90% 90.85% 93.15% 96.20% 98.80% 100.00% 100.00% 100.00%
Cum. Revised Plan 2 % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 55.45% 58.58% 61.67% 64.63% 68.57% 71.20% 73.22% 76.70% 78.60% 80.17% 82.03% 85.45% 87.50% 90.35% 92.80% 95.40% 97.10% 98.70% 100.00%
Cum. Actual % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 55.45% 58.58% 61.67% 64.63% 68.57% 71.20% 73.22% 76.70% 78.60% 80.17% 82.03% 84.10% 85.15% 86.70% 87.70% 89.00%
Physical Progress – KA 1
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target Actual Target Actual
Physical 100.00*(92.80)% 87.70% 100.00*(95.40)% 89.00%
23
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,756,280,100.00
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)1,259,079,026.57
Payments Certified – KA 1
NOTE : * - Physical target percentage is based on the Revised Programme (Revision 2) of KA1 Contract
Photographs – KA 1
24
Asphalt laying work at, CH: 1+360 – 1+550
Nugethenna to KewulagamaPamunuwella Road (Road No.53)
ABC laying work at, CH: 0+180 – 0+210
Nugethenna to KewulgamaPamunuwella Road (Road No.53)
Embankment compaction work atCH: 5+880 LHS
Bambaragahadeniya Junction Madamahanuwara via
Meeriyagolla Road (Road No.01)
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 KA2
Total Surfacing Length : 70.30 Km (97.02%)
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
Handed Over Road
25
12 Kobbekadwa Gamameda Road PRDA 1.98 1.98 100%
13 Dodamwala Dewalaya - Wathurakumbura Road PRDA 3.26 3.26 100%
14 SiyambalagodaiOmandel Sikurapotha Road PRDA 3.00 3.00 100%
15 Pottapitiya 4th mile Post Udaranmeewatta Road PS 2.48 2.48 100%
16Galpaya, Thelihunna Colany Via Kurunduwatta Nee Town
Pellapitiya colonyPRDA 8.30 8.30 100%
17 Yatapana Boswod road PS 4.56 4.54 100%
18Nawalapitiya-Udakanda bus stand via veralugashinna,
WellgodawattaPS 7.80 7.80 100%
19 Aluthgama centre village road PS 2.75 2.75 100%
20 Dekinda, Weralugoda road PS 2.64 2.64 100%
23Pussellawa melfert boment kalgala Wanahapuwa via
Dunukeulla roadPS 7.24 6.74 93%
24Panvilathenna junction-Legumdeniya main road via robert
nocks Gla pussathennaPS 3.77 3.77 100%
25Boralu mankada junction-Milagahamulla junction via
grohil road Angammanadrate KahawttaPS 8.29 6.59 79%
26 Udaguruwatta road to Wewathenna road PRDA 3.34 3.34 100%
27 Manikkawa junction to Gonadhikawatta road PRDA 6.85 6.85 100%
28 Viharagama-Watadeniya road via Appallagoda PS 1.89 1.89 100%
29 Pamunuwa Dailawala Mugatiyapola road PRDA 2.33 2.33 100%
30 Pamunuwa junction-Elugoda road PRDA 1.87 1.87 100%
8km 9kmCompleted
%
ROAD
NO.Road Name
Road
CatogoryLength
Completed
Length
Surfacing length
1km 2km 3km 4km 5km 6km 7km
26
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
Cum. Plan % 0.00% 0.08% 1.92% 4.10% 5.39% 9.89% 14.56% 19.69% 25.27% 32.82% 42.95% 49.74% 56.03% 63.76% 70.09% 74.36% 76.90% 81.07% 83.69% 87.15% 89.52% 92.58% 98.03% 99.78% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 1 % 0.00% 0.45% 2.22% 5.16% 7.25% 9.04% 16.09% 19.94% 26.12% 32.93% 40.00% 44.81% 49.82% 53.50% 57.50% 61.78% 65.01% 69.25% 74.21% 79.21% 84.22% 89.86% 95.31% 98.10% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 2 % 0.00% 0.45% 2.22% 5.16% 7.25% 9.04% 16.09% 19.94% 26.12% 32.93% 40.00% 44.81% 49.82% 53.50% 57.35% 61.60% 62.91% 68.42% 73.22% 78.13% 82.14% 86.64% 90.65% 92.01% 94.00% 95.00% 96.32% 96.34% 96.80% 97.20% 97.50% 97.90% 98.30% 98.70% 99.15% 99.80% 100.00%
Cum. Actual % 0.00% 0.45% 2.22% 5.16% 7.25% 9.04% 16.09% 19.94% 26.12% 32.93% 40.00% 44.81% 49.82% 53.50% 57.35% 61.60% 62.91% 68.42% 73.22% 78.13% 82.14% 86.64% 90.65% 92.01% 94.00% 95.00% 96.32% 96.34% 96.53% 97.10%
Physical Progress – KA 2
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target (Revised) Actual Target (Revised) Actual
Physical 100.00*(96.80)% 96.53% 100.00*(97.20)% 97.10%
27
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,923,673,744.80
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)1,388,694,897.24
Payments Certified – KA 2
NOTE : * - Physical target percentage is based on the Revised Programme (Revision 2) of KA2 Contract
28
Photographs – KA 2
ABC laying work at
Ch. 4+500-4+700
Pussella Melfret Boment Kalugala
Wanahapuwa via Dunukeula Road
Road (KRN 23)
Maintenance of turffing at
Ch. 3.+700
Nawalapitiya-Udakanda Bus
Stand via Weralugashinna
Weligodawaththa Road
(KRN 18)
Sand sealing work at
Ch. 5+920-6+340
Pussella Melfret Boment Kalugala
Wanahapuwa via Dunukeula
Road (KRN 23)
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 KA3
tal Surfacing Length : 64.66 Km (94.33%)
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
Handed Over Road
29
5 Ogastawatta Wagirarama Road-Udaperadeniya PS 1.700 1.50 88%
6Mahakanda Junction Mobre Samadhi Mawatha Via
Sarasavigama RoadPS 3.320 3.32 100%
7 Gurudeniya -Dambawela Bus Stand PRDA 0.750 0.75 100%
8 Dambawela Road,Kandy Talathuoya via Govi Janapadaya PS 1.100 1.10 100%
9Hanthana Uduwela Watta - Galaha Town via Galaha
Watta ,Kithulgolla PRDA + PS 9.450 9.45 100%
10 Delthota Town -Gabadagama Road PRDA 7.590 7.59 100%
11 Maussawa - Kolabissa Junction PRDA 3.700 3.70 100%
37
Hatharaliyadda,Mahanuwara main Road Cross Junction to
Galagedara Minigamuwa main Road via Polwatta
Ihalagama
PS 3.670 3.58 98%
38Poththapitiya Weligodapola main Road to Patapola post
Office via Alagalla Primary School PRDA + PS 2.570 2.57 100%
39Hatharaliyadda Rambukkana main Road to Dedunupitiya
Post Office to Weniwella Road via kalotuwawaPRDA + PS 11.030 9.93 90%
40Hatharaliyadda Mawathagama main Road to Anludeniya
School to Paragoda Gonathenna Road PS 4.630 3.99 86%
48 karaduwawala Gatathale Road PS 2.780 2.78 100%
49 Bokkawala Pahala Higulwala via Miliyedda Road PRDA 4.280 4.28 100%
49A Vilana Pallegama - Watagoda Burton Watta PRDA 1.890 0.97 51%
50Poojapitiya,Dodamthanna,Bothota,Antharagama,Pattiyawat
ta via Rajapihilla RoadPRDA 6.820 6.82 100%
51 Kasawatta Poojapitiya Road PS 2.230 2.23 100%
6 km Road No Road Name
Road
Catogory
Actual Road
Length (km)
Completed
Length (km)
Surfacing
Completed %
Surfacing Length
1 km 2 km 3 km 4 km 5 km 7 km 8 km 9 km 10 km 11 km
30
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18
Cum. Initial Plan % 0.13% 0.39% 2.23% 5.08% 7.28% 10.87% 18.36% 26.21% 34.39% 42.69% 50.85% 58.66% 64.53% 69.75% 74.45% 79.18% 82.11% 85.11% 88.42% 91.53% 94.14% 96.56% 98.95% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 1 % 0.00% 0.05% 0.19% 1.02% 3.67% 8.18% 11.94% 16.34% 21.22% 27.16% 32.38% 36.20% 39.38% 44.33% 49.52% 54.88% 60.07% 66.43% 73.15% 80.10% 87.20% 93.01% 97.46% 99.47% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 2 % 0.00% 0.05% 0.19% 1.02% 3.67% 8.18% 11.83% 15.87% 19.68% 23.96% 30.15% 33.57% 38.21% 42.54% 47.17% 52.05% 54.74% 57.51% 60.62% 63.76% 67.21% 70.91% 74.50% 76.25% 79.00% 84.00% 88.00% 92.00% 94.00% 96.00% 98.00% 100.00%
Cum. Actual % 0.00% 0.05% 0.19% 1.02% 3.67% 8.18% 11.83% 15.87% 19.68% 23.96% 30.15% 33.57% 38.21% 42.54% 47.17% 52.05% 54.74% 57.51% 60.62% 63.76% 67.21% 70.91% 74.50% 76.25% 78.90% 81.89% 83.98% 88.47% 90.54% 91.73%
Physical Progress – KA 3
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target (Revised) Actual Target (Revised) Actual
Physical 100.00*(94.00)% 90.54% 100.00*(96.00)% 91.73%
31
Payments Certified – KA 3
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 2,096,869,910.40
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)1,464,949,162.2
NOTE : * - Physical target percentage is based on the Revised Programme (Revision 2) of KA3 Contract
32
Photographs – KA 3
Embankment construction at Ch. 0+450
Vilana Pallegama - Watagoda Burton Watta Road (KRN 49A)
Asphalt compaction at Ch. 1+170
Hatharaliyadda,Mahanuwara Main Road Cross Junction to Galagedara
Minigamuwa Main Road via PolwattaIhalagama (KRN 37)
Hard shoulder construction at Ch. 1+690
Kasawatta Poojapitiya Road(KRN 51)
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 MA1
Total Surfacing Length : 53.83 Km (71.66%)
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
Handed Over Road
33
2 Ratalwawa Juntction to Nikagolla road via Kottagolla PS 1.56 1.56 100%
3Mathalapitiya Rahminda Thuththiripitiya Atipola
Dullawa via walawela Aluthgama roadPRDA /PS 11.36 11.12 98%
4
Yatawatta Mathalapitiya Road to Kurunegala Matale
road via idangama Aluthwatta Walpola &
Maligatenna
PS 5.06 0.00 0%
5Yatawatta Mahawela road to Pathingaskotuwa
Kurunagala on Yatawatta road via Nikagolla NorthPRDA 2.17 2.17 100%
56Beeridewala to Walawela and Muduna road via
dullawa JunctionPRDA 5.36 5.32 99%
6 Uda Hapuwida Junction to Laliabbe Junction Road PRDA/ PS 3.24 3.24 100%
7 Polwattakanda to kaudagammana road PS 4.16 0.35 8%
8 Madakumbura to udatenna road (Reveston road) PS 1.60 0.00 0%
9 Udahapuwidiya keselwatta road PS 1.05 1.05 100%
10 Bodikotuwa Junction to Hoagolla Bridge road PRDA 6.11 3.21 53%
11 Kambiadiya to Kandenuwara road via Bogambara PS 9.08 8.98 99%
12 Dombagoda Pahala Hapuwida road PS 2.68 0.53 20%
13 Udaweragama Tennewatta Gansarapola road PS 5.53 4.90 89%
15Kaikawela temple to pahala owela punchikade main
road PS 4.06 4.06 100%
14 Hulagamuwa Junction to Watagoda road PRDA 2.74 2.56 93%
45OviliKanda to babaragahakanda road via wademada
pahtingolla PRDA/PS 4.73 3.69 78%
46Rathwtta to Elkaduwa road via wawugammadda
roadPS 1.99 0.24 12%
47 Kaduwela to Pujagoda gama maeda road PS 2.64 0.00 0%
10 km 12 km3 km 4 km 5 km 6 km 7 km 8 km 9 km1 km 2 km
Surfacing Length Road
No 11 kmRoad Name
Road
Catogory
Actual Road
Length (km)
Completed
Length (km)Completed %
34
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
Cum. Plan % 0.00% 0.12% 1.06% 6.15% 7.79% 11.53% 16.99% 23.27% 29.15% 34.24% 38.64% 45.01% 52.43% 59.08% 64.15% 70.87% 75.39% 80.73% 85.41% 90.58% 94.67% 97.38% 99.16% 99.98% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 1 % 0.00% 0.14% 1.17% 3.01% 5.10% 5.91% 10.97% 15.10% 19.18% 23.29% 28.57% 31.91% 35.33% 41.78% 48.56% 55.72% 61.24% 68.57% 75.92% 83.26% 89.79% 94.71% 98.02% 99.84% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 2 % 0.00% 0.14% 1.17% 3.01% 5.10% 5.91% 10.97% 15.10% 19.18% 23.29% 27.80% 31.07% 35.18% 38.72% 41.28% 48.73% 50.83% 53.48% 54.83% 54.93% 54.96% 54.99% 54.99% 54.99% 54.99% 56.30% 59.80% 63.80% 67.30% 72.30% 77.30% 82.30% 87.30% 92.30% 96.10% 99.30% 100.00%
Cum. Actual % 0.00% 0.14% 1.17% 3.01% 5.10% 5.91% 10.97% 15.10% 19.18% 23.29% 27.80% 31.07% 35.18% 38.72% 41.28% 48.73% 50.83% 53.48% 54.83% 54.93% 54.96% 54.99% 54.99% 54.99% 54.99% 56.30% 58.72% 62.30% 62.88% 64.66%
Physical Progress – MA 1
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target (Revised) Actual Target (Revised) Actual
Physical 100.00*(67.30)% 62.88% 100.00*(72.30)% 64.66%
35
Payments Certified – MA 1
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,622,371,389.60
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)899,221,201.16
NOTE : * - Physical target percentage is based on the Revised Programme (Revision 2) of MA1 Contract
36
Photographs – MA 1
DGAB construction at Ch. 1+870Dombagoda – Pahala Hapuwida
Road (R 12)
Roadway excavation at Ch. 4+565(RHS)
Mathalapitiya - Kurunegala MataleRoad (R 04)
Gabion wall construction at Ch. 0+535(LHS)
Bodhikotuwa – Horagolla Bridge Road (R 10)
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 MA2
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
Total Surfacing Length : 55.45 Km (99.83%)37
Handed Over Road18 Dambuluoya Junction to Kalundewa Road PRDA 7.89 7.89 100%
19 Kapuwatta Yapagama Road MC 3.82 3.82 100%
20 Kapuwatta Akkara Seeya Yapagama Road MC 3.88 3.88 100%
21Yapagama Dambulla Pola Ate Ela Batuyaya via
Diddeniya Kade RoadMC 6.13 6.13 100%
22 Kandalama Rotawewa Road PS 4.87 4.87 100%
23 Thiththawelgolla Rathmalgaha Ela Road MC 5.00 5.00 100%
24Sisirawatta Bulanwala Athuparayaya Dambulla Town
RoadMC 5.98 5.98 100%
25 Pelwehara Randeniya Bulagala Road PS/PRDA 4.25 4.25 100%
49 Walaswewa Main Road PS 2.14 2.14 100%
50 Galapaula Damunumulla Road PS 3.39 3.39 100%
52 Akuramboda Temple to Koswatta Road PS 2.00 2.00 100%
53 Dabuyaya Dambagolla Road PS 4.08 4.08 100%
54 Ambokka Dewalaya Road PS 2.27 2.27 100%
55 Damunumulla Yatigalpoththa Road PS 2.14 2.14 100%
Road
NoRoad Name
Road
Catogory
Actual Road
Length (km)
Completed
Length (km)
Completed
%
Surfacing Length
1 km 8 km 9 km2 km 3 km 4 km 5 km 6 km 7 km
38
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18
Cum. Plan % 0.00% 0.47% 1.84% 6.09% 7.24% 11.00% 12.70% 16.00% 19.15% 22.01% 26.00% 31.10% 35.85% 43.00% 50.20% 58.15% 66.80% 75.10% 81.94% 87.78% 93.58% 96.63% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Actual % 0.00% 0.19% 0.75% 1.57% 2.90% 6.50% 13.80% 19.94% 25.93% 32.45% 39.24% 43.40% 48.53% 51.10% 56.84% 63.05% 65.91% 70.06% 75.05% 80.47% 86.84% 90.74% 92.83% 95.90% 97.50% 98.20% 98.58% 99.50% 99.95% 100.00%
Physical Progress – MA 2
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target Actual Target Actual
Physical 100.00% 99.95% 100.00% 100.00%
39
Payments Certified – MA 2
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,248,826,902.00
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)1,035,283,940.40
40
Photographs – MA 2
Finished road section at Ch.3+500
Kandalama – Rotawewa Road
(R 22)
Finished road section at Ch. 0+450
Kapuwatta – Akkara Seeya Road
(R 20)
Hand rail fixing for the bridge at
Ch. 4+140
Kandalama - Rotawewa Road
(R 22)
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 MA3
Total Surfacing Length : 60.69 Km (99.85%)
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
Handed Over Road
41
27 Boballa Bibila Road PS 1.48 1.48 100%
40 Kanamulyaya Rubber Watta Via Police Station Road PS 2.56 2.56 100%
41 Meegolla Deewara Gammanaya Road PS 1.20 1.20 100%
42 Gedige Junction to Hapugasyaya Tamil Village Via Ududeniya Road PS 3.04 3.04 100%
39 Bibila Murutholuwa Road PS 1.68 1.68 100%
29 Weeragolla Munamalpitiya Via Moragaha Ulpatha Road PS 2.83 2.50 88%
33 Malgammana Gangayaya Road PS 2.32 2.32 100%
28 Lewiyangala Junction to Weheragala Via Himbiliyakada Road PS 3.30 3.30 100%
30 Nagolla Amunuyaya Via Godaulpotha Weheragala Road PS 4.64 4.60 99%
31 Alikanda Cemetry Via Kaduruvediya Ela Road PS 3.52 3.32 94%
32 Medakanda Maraka Road PRDA 6.20 6.20 100%
34 Handungamuwa Kumbukoya Road PS 4.25 4.25 100%
35 Madawela Junction to Nalanda Industrials Zone Road PRDA/PS 2.50 2.50 100%
36 Ellepola Kalupalama to Hilton Janapadaya Road PS 1.00 1.00 100%
38 Kanangamuwa Parawatta Road PS 2.80 2.80 100%
16 Kosgolla Adawela Road Via Kumballoluwa Magallewa PS 8.52 7.71 90%
43 Kosgolla Muduna to Loluwela Junction Via Imbulgolla Road PS 6.00 6.00 100%
44 Mahalakotuwa to Meda Ela Via Raththinda Junction PS 2.08 1.85 89%
7 km
Road
NoRoad Name
Road
Catogory
Actual Road
Length (km)
Completed
Length (km)
Completed
%
Surfacing Length
1 km 2 km 3 km 4 km 5 km 6 km 8 km 9 km 10 km 11 km 12 km
42
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18
Cum. Initial Plan % 0.00% 0.24% 1.28% 4.38% 5.88% 9.70% 14.21% 20.21% 27.66% 34.58% 38.76% 44.52% 47.82% 53.57% 58.68% 63.60% 66.68% 73.48% 83.93% 91.46% 95.28% 97.02% 99.66% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 1 % 0.00% 0.09% 0.93% 1.95% 2.79% 4.50% 9.52% 15.24% 23.18% 28.28% 32.17% 35.71% 39.37% 44.55% 51.11% 57.84% 62.03% 69.07% 76.08% 82.84% 89.60% 96.09% 99.73% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 2 % 0.00% 0.09% 0.93% 1.95% 2.79% 4.50% 9.52% 15.24% 23.18% 28.28% 32.17% 36.01% 40.27% 44.77% 51.00% 57.37% 62.15% 66.28% 72.10% 78.50% 82.40% 86.50% 90.10% 91.20% 92.80% 94.35% 95.50% 96.50% 97.40% 98.20% 99.00% 100.00%
Cum. Actual % 0.00% 0.09% 0.93% 1.95% 2.79% 4.50% 9.52% 15.24% 23.18% 28.28% 32.17% 36.01% 40.27% 44.77% 51.00% 57.37% 62.15% 66.28% 72.10% 78.50% 82.40% 86.50% 90.10% 91.20% 92.80% 94.15% 96.68% 97.30% 98.20% 98.80%
Physical Progress – MA 3
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target (Revised) Actual Target (Revised) Actual
Physical 100.00*(97.40)% 98.20% 100.00*(98.20)% 98.80%
43
Payments Certified – MA 3
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,407,719,849.18
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)1,088,874,664.84
NOTE : * - Physical target percentage is based on the Revised Programme (Revision 2) of MA3 Contract
44
Photographs – MA 3
Shoulder construction at Ch. 1+750
Mahalakotuwa - Meda Ela Road (R 44)
Road maintenance at Ch. 0+450
Meegolla – Deewara GammanayaRoad (R 41)
Bridge construction at Ch. 1+390
Mahalakotuwa - Meda Ela Road (R 44)
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 NE1
Total Surfacing Length : 45.52 Km (62.82%)
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
Handed Over Road
45
1AMBAGASPITIYA LANDUPITA
LIYANWELA ROAD PRDA 3.000 0.73 24%
2RAGALA WATER BOARD
EKAGAPURA ROAD PRDA 4.400 2.37 54%
3RAGALA STARPET PANDITHA
KUMBURA KOTAMBE ROAD PRDA 9.600 9.03 94%
4
UDUPUSSELLAWA
KURUPANAWELA MEEPANAWA
ROAD
PRDA 6.900 1.61 23%
5DELMAR GALKADANAPATHANA
RUPAHA ROAD PS 4.340 0.42 10%
6 WALAPANE HOSPITAL ROAD PRDA 2.200 2.20 100%
7ADHIKARIGAMA AMBEWELA
MERIMOUNT ROAD PRDA 4.796 4.79 100%
8RIKILLAGASKADA
DIMBULKUMBURA ROAD PRDA 4.930 4.39 89%
9KARALIYADDA VILLAGE ROAD VIA
GONAGANTENNA HOSPITAL PS 2.150 2.15 100%
10 MAHAUVA HIGHFOREST ROAD PS 13.540 11.36 84%
11RIKILLAGASKADA HAPUWELA
ROAD PRDA,PS 5.010 4.42 88%
12AMBALIYADDA IHALA KOTAPE
RIKILLAGASKADA ROAD PRDA 7.799 0.00 0%
13PALLEBOWALA- MEDAGAMA-
DELTHOTA ROAD PS 1.680 1.32 79%
15 KEENAGALA ESTATE ROAD PS 2.000 0.00 0%
14km8 km 9 km 10 km 11km 12km 13km7 km
Roa d
NoRoa d Na me
Roa d
Ca togory
Ac tua l
Roa d
Le ngth
(km)
Comple t
e d
Le ngth
(km)
Comple te
d %
Surfacing Length
1 km 2 km 3 km 4 km 5 km 6 km
46
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
Cum. Plan % 0.00% 0.00% 0.10% 1.10% 4.20% 8.70% 12.20% 17.40% 19.70% 24.90% 30.10% 37.20% 42.00% 46.30% 50.10% 55.70% 60.50% 67.00% 75.30% 81.10% 86.20% 91.30% 95.20% 98.20% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 1 % 0.00% 0.00% 0.10% 1.30% 3.20% 5.30% 10.70% 14.00% 19.00% 23.00% 30.50% 36.40% 40.50% 45.20% 53.05% 57.10% 60.82% 67.75% 75.02% 81.43% 87.06% 92.95% 97.11% 99.38% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 2 % 0.00% 0.00% 0.10% 1.30% 3.20% 5.30% 10.70% 14.00% 19.00% 23.00% 30.50% 36.40% 40.50% 45.20% 51.34% 53.76% 56.40% 59.25% 65.00% 67.00% 69.00% 69.50% 70.20% 70.40% 75.57% 84.05% 88.70% 91.20% 93.90% 96.00% 98.20% 99.06% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 3 % 0.00% 0.00% 0.10% 1.30% 3.20% 5.30% 10.70% 14.00% 19.00% 23.00% 30.50% 36.40% 40.50% 45.20% 51.34% 53.76% 56.40% 59.25% 65.00% 67.00% 69.00% 69.50% 70.20% 70.40% 70.60% 71.05% 71.15% 71.75% 71.85% 76.35% 84.52% 92.12% 96.90% 98.31% 98.87% 99.72% 100.00%
Cum. Actual % 0.00% 0.00% 0.10% 1.30% 3.20% 5.30% 10.70% 14.00% 19.00% 23.00% 30.50% 36.40% 40.50% 45.20% 51.34% 53.76% 56.40% 59.25% 65.00% 67.00% 69.00% 69.50% 70.20% 70.40% 70.60% 71.05% 71.15% 71.75% 71.85% 71.98%
Physical Progress – NE 1
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target (Revised) Actual Target (Revised) Actual
Physical 100.00*(93.90)% 71.85% 100.00*(96.00)% 71.98%
47
Payments Certified – NE 1
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 2,297,886,621.60
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)1,327,680,822.13
NOTE : * - Physical target percentage is based on the Revised Programme (Revision 2) of NE1 Contract
Photographs – NE 1
48
Rock blasting at Ch. 3+562 - 3+566
Rikillagaskada Dimbulkumbura Road (RD 08)
Asphalt work at Ch. 8+210 – 8+240Udupussellawa Kurupanawela
Meepanawa Road (RD 04)
Priming work at Ch.10+000 – 10+280
Mahauva Highforest Road (RD 10)
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 NE2
Total Surfacing Length : 36.03 Km (99.50%)
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
Handed Over Road -Without the Bridge
Handed Over Road –Total Length
49
16 Uwakale Estate Road Estate/ps 4.411 4.33 98%
17Lower Pundaluoya Upper kothmale
Sheengama RoadPS 2.058 2.05 100%
18 Pilot project Road PS 0.868 0.87 100%
19 Piduruthalagala Farm Road PS 1.330 1.33 100%
2 0Kantha govipola Ranaviru Gammana
Road PS 1.430 1.43 100%
2 1 Meepilimana Gammeddda Road PS 2.580 2.58 100%
2 3 Thalawakale Galkanda Road Estate/ps 3.770 3.65 97%
2 4 Rahanwaththa Maussalle Road Estate/ps 3.730 3.72 100%
2 6 Kandapola Konkordia Road Estate/ps 1.820 1.82 100%
2 8 Kandapola Heatherset Road Estate/ps 0.800 0.80 100%
2 9 Nanuoya udaradella Road PS 6.230 6.23 100%
3 0Kothmale Dam view point to
Kotagepitiya Road PS 3.050 3.05 100%
3 1 Connecting Road to Halpola PS 1.380 1.38 100%
3 2 Henfold Estate Road Estate/ps 2.606 2.61 100%
4 km 5 km 6 km 7 km
Roa d
NoRoa d Na me
Roa d
Ca togory
Ac tua l
Roa d
Le ngth
(km)
Comple te d
Le ngth
(km)
C o mpleted
%
Surfacing Length
1 km 8 km2 km 3 km
50
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18
Cum. Plan % 0.27% 1.60% 4.10% 7.81% 11.97% 16.75% 21.63% 26.42% 31.14% 36.26% 41.82% 47.79% 53.89% 59.74% 65.58% 72.12% 78.63% 84.66% 89.20% 92.34% 95.14% 97.82% 99.25% 99.62% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 1 % 0.10% 0.71% 3.79% 6.49% 9.22% 13.54% 16.08% 24.00% 32.10% 40.00% 51.00% 57.00% 63.00% 67.00% 69.00% 72.00% 75.00% 78.00% 80.00% 83.00% 86.00% 88.00% 89.00% 92.00% 94.00% 95.00% 96.00% 97.00% 98.00% 99.00% 100.00%
Cum. Actual % 0.10% 0.71% 3.79% 6.49% 9.22% 13.54% 16.08% 24.00% 32.10% 40.00% 51.00% 57.00% 63.00% 67.00% 69.00% 72.00% 75.00% 78.00% 80.00% 83.00% 86.00% 88.00% 89.00% 92.00% 94.00% 95.00% 96.00% 97.00% 97.00% 98.00%
Physical Progress – NE 2
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target Actual Target Actual
Physical 100.00*(98.00)% 97.00% 100.00*(99.00)% 98.00%
51
Payments Certified – NE 2
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,241,719,309.20
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)1,003,137,134.33
NOTE : * - Physical target percentage is based on the Revised Programme (Revision 2) of NE2 Contract
Photographs – NE 2
Construction of pier for bridge atUwakale Estate Road (RD 16)
52
Road marking atPilot Project Road (RD 18)
Road surface cleaning for road marking
Pilot Project Road (RD 18)
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 NE3
Total Surfacing Length : 50.49 Km (76.38%)
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
Handed Over Road
53
3 3Hitiyagama Udapolgaswaththa
Minuwandeniya Road PS 8.505 8.20 96%
3 4 Tillary Tinsing Road PS 3.610 0.00 0%
3 6Beramanna Udagama Madakubura
Road PS 4.470 2.51 56%
3 7Katugolla Hunugaloya Nawathispane
Road PS 2.545 2.54 100%
3 8 Stockhome Lower Gruden Road PS 3.075 2.10 68%
4 0 Waladola Mare Road PS 3.907 0.00 0%
4 1 Walioya Shanon Road PRDA/PS(0+000-
4+000PRDA)9.287 9.29 100%
4 2 Vencher State Road PS 3.728 3.47 93%
4 3 Hapugasthalawa Halgolla Road PS 5.000 1.16 23%
4 4 Nawathispane Harangala Road PS 2.950 2.95 100%
4 5 Hapugasthalawa Dabagala Road PS 2.065 2.07 100%
4 6Ginigathhena Dehigasthanna Ellauda
Road
PRDA/PS(0+000-
6+000PRDA)6.640 6.64 100%
4 7 Pallewatta Dagampitiya Road PRDA/PS(5+000-
7+000PRDA)7.340 7.25 99%
4 8 Ginigathhena School Road PS 1.080 1.08 100%
4 9 Ambagamuwa Shilalekana Road PS 1.543 1.20 78%
4 km 5 km 6 km 7 km
Roa d
NoRoa d Na me Roa d Ca togory
Ac tua l
Roa d
Le ngth
(km)
Comple te d
Le ngth
(km)
C o mpleted
%
Surfacing Length
1 km 8 km 9 km 10 km2 km 3 km
54
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18
Cum. Initial Plan % 0.53% 1.51% 2.81% 4.00% 5.41% 6.73% 9.89% 14.97% 20.96% 26.65% 33.06% 39.76% 46.28% 53.00% 60.04% 67.26% 74.60% 81.85% 87.73% 92.68% 95.88% 97.49% 98.74% 99.73% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan % 0.00% 0.00% 0.09% 0.71% 2.23% 7.13% 12.02% 17.12% 22.67% 28.75% 34.87% 41.30% 47.68% 53.87% 60.25% 65.30% 68.87% 75.25% 80.48% 86.08% 91.95% 95.99% 99.23% 99.89% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 2 % 0.00% 0.00% 0.09% 0.71% 2.23% 3.81% 6.56% 12.60% 23.56% 30.56% 36.89% 44.00% 46.92% 53.81% 59.18% 64.17% 66.95% 68.98% 71.99% 77.12% 79.86% 81.93% 83.71% 84.79% 85.80% 88.34% 90.75% 93.93% 95.23% 96.37% 97.68% 98.96% 99.98% 100.00%
Cum. Actual % 0.00% 0.00% 0.09% 0.71% 2.23% 3.81% 6.56% 12.60% 23.56% 30.56% 36.89% 44.00% 46.92% 53.81% 59.18% 64.17% 66.95% 68.98% 71.99% 77.12% 79.86% 81.93% 83.71% 84.79% 85.80% 87.08% 88.14% 89.15% 89.91% 90.52%
Physical Progress – NE 3
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target (Revised) Actual Target (Revised) Actual
Physical 100.00*(95.23)% 89.91% 100.00*(96.37)% 90.52%
55
Payments Certified – NE 3
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 2,069,691,582.00
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)1,553,091,061.86
NOTE : * - Physical target percentage is based on the Revised Programme (Revision 2) of NE3 Contract
Photographs – NE 3
56
ABC compaction work at Ch. 0+006 Ambagamuwa Shilalekana By Road
(ID 49A)
Excavation for shoulder top turfing at Ch. 0+485 – 0+550 RHS
Katugolla Hunugaloya NawathispaneRoad (ID 37)
Backfilling work for bridge construction at Ch. 8+465
Hitiyegama Minuwandeniya Road (ID 33)
Overall Physical Progress Summary –iROAD-Sabaragamuwa Province(up to 31 May 2018)
60
Package
No.Contractor
Accepted
Contract
Amount/ (Rs.
Million)
No. of
Roads
Total Road
Length as
per the
BOQ/ (km)
No. of
Roads Civil
Works in
Progress
Total road
pavement length
(asphalt+concrete)
completed (km)
Actual Physical
Progress as at
30 April 2018
(%)
Physical Progress; Cumulative
Status up to 31 May 2018 (%)
Target (Revised) Actual
R 01 KD Ebert 2,022 12 82.95 7 47.55 63.02% 100.00*(75.32)% 64.00%
R 02 KD Ebert 2,384 14 91.70 11 42.97 54.04% 100.00*(72.20)% 56.35%
R 03 R.R. Const. 2,021 12 80.35 12 81.01 99.90% 100.00*(99.93)% 99.93%
KE 01 KD Ebert 1,973 17 74.75 13 36.40 51.26% 100.00*(62.56)% 52.10%
KE 02 Nawaloka 1,817 21 78.25 19 47.67 60.39% 100.00*(92.69)% 64.21%
KE 03 Nawaloka 1,632 25 64.15 21 38.29 51.78% 100.00*(85.50)% 54.18%
Total / Avg. 11,849 101 472.15 83 293.89 63.40% 81.37% 65.13%
NOTE : * - Physical target percentage is based on the Revised Construction Programme (Revision 2).
61
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
Cum. Plan % 0.02% 0.09% 0.23% 0.85% 2.59% 5.43% 9.28% 13.77% 17.94% 21.95% 23.66% 26.14% 32.42% 39.52% 45.92% 52.71% 56.07% 62.48% 68.95% 75.01% 81.67% 87.46% 92.35% 95.76% 97.73% 99.02% 99.58% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised
Plan %0.02% 0.08% 0.34% 0.83% 1.50% 2.56% 4.51% 7.84% 10.71% 14.01% 18.86% 24.33% 29.11% 35.65% 39.89% 44.46% 46.74% 49.22% 50.82% 52.29% 53.13% 54.01% 55.41% 57.48% 60.20% 63.65% 67.34% 71.86% 76.55% 81.37% 85.86% 90.06% 93.52% 95.79% 97.59% 99.05% 100.00%
Cum. Actual % 0.02% 0.08% 0.34% 0.83% 1.50% 2.56% 4.51% 7.84% 10.71% 14.01% 18.86% 24.15% 28.90% 35.00% 40.07% 44.55% 46.65% 49.22% 50.83% 52.29% 53.13% 54.01% 54.69% 55.24% 56.27% 58.00% 60.11% 62.49% 63.40% 65.13%
Asphalt Paving Progress –iROAD-Sabaragamuwa Province (up to 31 May 2018)
62
Package No.
ContractorNo. of Roads
Actual Total Road
Length / (km)
No. of Roads Civil Works in Progress
Road Length
Civil works in
Progress/ (km)
Road length of Asphalt
completed/(km)
R 01 KD Ebert 12 80.13 7 51.00 47.55
R 02 KD Ebert 14 92.37 11 55.00 42.97
R 03R.R.
Construction12 81.01 12 81.01 81.01
KE 01 KD Ebert 17 74.525 13 53.02 36.40
KE 02 Nawaloka 21 77.70 19 65.50 47.67
KE 03 Nawaloka 25 67.42 21 45.26 38.29
Total 101 473.15 83 350.79 293.89
Package NoContractor
Accepted Contract Amount/ (Rs.
Million)
Total Certified Amount (Mobilization Advance) /(Rs.
Million)
R 01 KD Ebert and Sons Holdings(Pvt) Ltd. 2,022 1,004.35 (340.90)
R 02 KD Ebert and Sons Holdings(Pvt) Ltd. 2,384 1,137.12 (456.34)
R 03 R.R. Construction (Pvt) Ltd. 2,021 1,758.11 (7.16)
KE 01 KD Ebert and Sons Holdings(Pvt) Ltd. 1,973 940.13 (347.81)
KE 02 Nawaloka Construction Co. (Pvt) Ltd. 1,817 959.42 (265.06)
KE 03 Nawaloka Construction Co. (Pvt) Ltd. 1,632 825.36 (264.16)
Total 11,849 6,624.49 (1,681.43)
Overall Financial Status –iROAD-Sabaragamuwa Province /(up to end of May 2018)
63
Progress of Culverts & Bridges /(up to 31 May 2018)
64
DistrictPackage
NoContractor
No. of Culverts No. of Culverts
No.of Bridges
RemarksNew / Re -
Construction/ Widening
Completed / in Progress
RepairCompleted / in Progress
Rathnapura
R1K.D. Ebert & Sons Holdings
(pvt) Ltd.252 79 132 7 4
Design approved for all bridges and
two bridges partially completed
R2K.D. Ebert & Sons Holdings
(pvt) Ltd.380 175 261 72 3
Design approved for all bridges and
one bridge is in progress
R3 R.R. Construction (PVT) LTD 402 402 114 114 7 All bridges completed
Kegalle
KE1KD Ebert and Sons
Holdings(Pvt) limited.535 238 153 28 9
Design approved for all bridges.
Four bridges completed and another
one in progress
KE2Nawaloka Construction CO.
(Pvt) Ltd.368 239 234 106 6
Design approved for all bridges.
One bridge is completed and
another one in progress
KE3Nawaloka Construction CO.
(Pvt) Ltd.128 53 206 32 -
Total 2065 1186 1100 359 29
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 R1
Total Surfacing Length : 47.55 Km (59.34%)
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
Handed Over Road
65
7Dumbaramanana wathukaragama to Dumbara Kovila
main roadPRDA 7.95 4.58 58%
11 Kuruwita Dearwood tea factory PRDA 5.96 5.7 96%
12Batathota Junction via Divaguhawa to Kalanchiwatta
road PRDA 4.00 3.24 81%
13Galaboda-Rathganga Tempal-Kudava-Mapalana-Via
Palabaddala roadPRDA/PS 16.41 7.94 48%
14Near Saman Dewalaya Kataliyanpall-New-Town Up
to Muttetupita Via Prince CollegePS 3.26 2.09 64%
16 Mahingoda Viyalagoda Via puvakgahadeniya road Ps 2.98 2.98 100%
17Muruthangala deurampitiya Estate via Kaluandura &
Muruthangala Tempal via Deurampitiya RoadPs 5.98 4.54 76%
19Ihalakanda Kanukgala Rukhena Hatharaendahena
Pahalawatta ParanagamaPRDA/PS 7.74 6.78 88%
19A Bodimaluwa Pohorabeva School via Paranagama PRDA 5.95 5.69 96%
20Madalagettuva Vithanakanda via Keenagahawela
Road PRDA/PS 6.05 3.27 54%
39Nammuniyawatta nammunuthanna Gangodakanda
RoadPRDA 4.02 0 0%
40 Palawela-Ayagama road PRDA 9.83 0 0%
7 km
Road
NoRoad Name
Road
Catogory
Actual Road
Length (km)
Completed
Length (km)
Completed
%
Surfacing Length
1 km 2 km 3 km 4 km 5 km 6 km 14 km 15 km 16 km 17 km8 km 9 km 10 km 11 km 12 km 13 km
66
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
Cum. Plan % 0.06% 0.30% 0.71% 1.36% 4.55% 8.65% 14.42% 19.81% 24.42% 29.06% 34.22% 40.47% 46.48% 53.52% 61.10% 68.28% 74.87% 80.97% 86.50% 90.93% 94.23% 97.27% 99.34% 99.95% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised - 1 % 0.06% 0.30% 0.87% 1.86% 2.69% 4.12% 5.94% 9.62% 11.33% 15.58% 21.01% 27.38% 33.77% 39.69% 45.20% 52.63% 58.14% 64.77% 72.19% 79.45% 86.37% 92.39% 96.64% 99.39% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised - 2 %
(31.12.2017)0.06% 0.30% 0.87% 1.86% 2.69% 4.12% 5.94% 9.62% 11.33% 17.02% 22.78% 27.45% 31.60% 38.88% 44.37% 49.04% 50.45% 53.96% 55.01% 55.51% 55.51% 55.51% 55.51% 55.51% 55.51% 58.64% 61.75% 65.90% 70.63% 75.32% 79.63% 83.42% 86.76% 89.51% 92.83% 97.36% 100.00%
Cum. Actual % 0.06% 0.30% 0.87% 1.86% 2.69% 4.12% 5.94% 9.62% 11.33% 17.02% 22.78% 27.45% 31.60% 38.88% 44.37% 49.04% 50.45% 53.96% 55.01% 55.51% 55.51% 55.51% 55.51% 55.51% 55.51% 57.80% 61.23% 62.79% 63.02% 64.00%
Physical Progress – R 1
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target (Revised) Actual Target (Revised) Actual
Physical 100.00*(70.63)% 63.02% 100.00*(75.32)% 64.00%
67
Payments Certified – R1
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 2,022,050,560.00
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)1,004,345,482.95
NOTE : * - Physical target percentage is based on the Revised Programme (Revision 2) of R1 Contract
68
Photographs – R1
Construction of road base atCh. (3+110 – 3+180)
Madalagettuva Vithanakanda via Keenagahawela Road (ID-20)
Application of prime coat atCh. (3+320 – 3+380)
Madalagettuva Vithanakanda via Keenagahawela Road (ID-20)
Roadway excavation at Ch. (5+617 – 5+670)
Madalagettuva Vithanakanda via Keenagahawela Road (ID-20)
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 R2
Total Surfacing Length : 42.97 Km (46.52%)
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
Handed Over Road
69
3Hallinna Junction to Polwaththahena Matihakwela
Hunuwella RoadPRDA 10.100 5.10 50%
5 Kongasthanna Junction to Ilukkumbura Road PRDA 4.030 1.93 48%
21 Bopeththa Handiya to Mawalla Road PRDA, PS 5.450 1.96 36%
22 Marapana Mada Handiya to Dala Road PRDA 5.175 5.05 98%
23Dakunu Panawanna Rubber Factory to Poronuwa
RoadPRDA 6.400 2.47 39%
25 Wewalwatta junction to Alupola Road PRDA 4.440 0.00 0%
28Labuwatta Junction to Crossing Pinnagolla to
Hapugahawela JunctionPRDA 1.820 0.00 0%
29Elapatha-Damme Junction to Damme Prajasalawa
RoadPRDA 2.920 1.20 41%
30 Sidurupitiya Junction-Waththehena Pitakelaya Road PRDA 10.030 1.89 19%
31Rassagala-Haramitigala-Samanalawatta-Massanna
RoadPRDA, PS 16.000 4.64 29%
32Rathmalawinna-Hatharabage-Udagama-
Oluganthota RoadPRDA 11.750 7.27 62%
33 Halpe Weharagoda Road PRDA 4.200 4.00 95%
33A Gurubawila Kanawinna Road PS 3.350 0.00 0%
33B Gurubawila Halapandeniya Gallenakanda Road PS 6.700 6.14 92%
7 km
Road
NoRoad Name
Road
Catogory
Actual Road
Length (km)
Completed
Length (km)
Completed
%
Surfacing Length
1 km 2 km 3 km 4 km 5 km 6 km 14 km 15km 16km8 km 9 km 10 km 11 km 12 km 13 km
70
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
Cum. Initial Plan % 0.00% 0.00% 0.00% 0.54% 1.64% 4.73% 10.54% 16.98% 23.04% 29.84% 36.12% 41.99% 48.89% 56.30% 61.56% 67.00% 71.16% 77.29% 82.67% 87.81% 93.60% 97.32% 99.42% 99.99% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised - 1 % 0.00% 0.00% 0.50% 0.92% 1.08% 1.32% 3.36% 7.43% 11.10% 15.13% 19.54% 24.14% 28.97% 35.49% 42.07% 51.24% 56.87% 64.64% 72.18% 79.38% 87.14% 94.04% 98.25% 99.80% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised - 2 % -
15.03.20180.00% 0.00% 0.50% 0.92% 1.08% 1.32% 3.36% 7.43% 11.10% 15.13% 18.58% 23.51% 27.10% 31.35% 35.16% 40.49% 43.41% 45.68% 46.53% 46.66% 46.66% 46.66% 46.86% 46.86% 46.86% 47.24% 51.26% 56.89% 64.66% 72.20% 79.39% 87.14% 94.04% 98.25% 99.80% 100.00% 100.00%
Cum. Actual % 0.00% 0.00% 0.50% 0.92% 1.08% 1.32% 3.36% 7.43% 11.10% 15.13% 18.58% 23.51% 27.10% 31.35% 35.16% 40.49% 43.41% 45.68% 46.53% 46.66% 46.66% 46.66% 46.86% 46.86% 46.86% 47.24% 48.55% 52.95% 54.04% 56.35%.
Physical Progress – R 2
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target (Revised) Actual Target (Revised) Actual
Physical 100.00*(64.66)% 54.04% 100.00*(72.20)% 56.35%
71
Payments Certified – R 2
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 2,383,993,873.89
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)1,137,118,669.35
NOTE : * - Physical target percentage is based on the Revised Programme (Revision 2) of R2 Contract
72
Photographs – R2
Edge widening compaction at CH 01+400-01+500 RHS
Near Dakunu Panawanna Rubber Factory to Poronuwa Road (ID 23)
ABC laying atCH 2+750- 2+850
Halpe Veheragoda Road (ID 33)
Asphalt laying at CH 07+100-7+420
Rathmalawinna Hathrabage Udagama Road (ID 32)
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 R3
Total Surfacing Length : 81.01 Km (100.00%)
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
73
Handed Over Road -Road Section Only
Handed Over Road –Total Length
1Ellagewatta junction to Godakawela via
Opatha, MakanduraPRDA 7.013 7.013 100%
2Palamkotta junction to Ambalama via
Nawinna, HeneggegodaPRDA 10.676 10.676 100%
4 Badullegama to Elamalpe~ Godakawela road PRDA 2.140 2.14 100%
8Thapassarakanda~Wiskamgoda road via
Karapotha bridgePS/PRDA 2.716 2.716 100%
10 Weddagala~Kudawa~Wewagama road PRDA/PS 12.000 12.000 100%
10ANikagoda~Batamandiya~Polwatta~Sisira
kade, piburaPS 5.090 5.090 100%
26 Rilladola bo-tree to Amunukara junction road PRDA 5.585 5.585 100%
27Amunukara junction Gabbela Digandala
Demuwatha roadPRDA 7.830 7.800 100%
34Ambagahayaya junction to 8 Mile post via
Mahayaya roadPS 5.854 5.854 100%
35Nawaneliya temple to Iththekanda via Nedola
roadPRDA 5.726 5.726 100%
3696 Junction to Panamura road via
Ranchamadama EthgalaPRDA/PS 10.251 10.251 100%
38 Delgoda Balipola up Wathurawa road PRDA 6.130 6.130 100%
Surfacing Length
2 km 3 km 4 km 5 km 6 km 7 km
Road
NoRoad Name
Road
Catogory
Actual Road
Length (km)
Completed
Length (km)
Completed
% 1 km 8 km 9 km 10 km 11 km 12 km
74
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18
Cum. Plan % 0.02% 0.07% 0.24% 1.45% 3.03% 7.48% 13.20% 19.56% 31.05% 44.54% 56.59% 65.87% 71.30% 75.89% 81.65% 86.80% 89.16% 93.95% 97.50% 98.89% 99.31% 99.58% 99.79% 99.93% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum.Revised - R1 % 0.00% 0.00% 0.56% 1.56% 3.80% 7.88% 11.54% 18.18% 24.74% 28.60% 36.66% 43.59% 51.87% 60.59% 68.39% 75.16% 79.38% 85.95% 90.92% 92.00% 96.86% 98.18% 99.49% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum.Revised - R2 % 0.00% 0.00% 0.56% 1.56% 3.80% 7.88% 11.54% 18.18% 24.74% 28.60% 36.66% 44.68% 53.15% 64.47% 67.32% 74.61% 79.95% 82.29% 86.81% 91.50% 93.00% 94.75% 95.25% 95.83% 98.64% 99.68% 99.78% 99.85% 99.90% 99.93% 99.95% 99.97% 100.00%
Cum. Actual % 0.00% 0.00% 0.56% 1.56% 3.80% 7.88% 11.54% 18.18% 24.74% 28.60% 36.66% 44.68% 53.15% 64.47% 67.32% 74.61% 79.95% 82.29% 86.81% 91.50% 93.00% 94.75% 95.25% 95.83% 98.64% 99.68% 99.78% 99.85% 99.90% 99.93%
Physical Progress – R 3
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target (Revised) Actual Target (Revised) Actual
Physical 100.00*(99.90)% 99.90% 100.00*(99.93)% 99.93%
75
Payments Certified – R 3
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 2,020,996,336.79
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)
1,758,107,330.71
NOTE : * - Physical target percentage is based on the Revised Programme (Revision 2) of R3 Contract
Photographs – R 3
Construction of ‘U’ drain at Ch. 3+650 - 3+675 RHS
Nawaneliya Temple to Iththekanda via Nedola Road (ID-35)
Concreting of a house access at Ch.0+250
Nawaneliya Temple to Iththekanda via Nedola Road (Road ID-35)
Shoulder construction at Ch. 3+090 - 3+110 RHS
96 Junction to Panamura Road via Ranchamadama Ethgala Road
(ID-36)76
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 KE1
Total Surfacing Length : 36.40 Km (48.84%)
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
Handed Over Road
77
1 Theligama - Ganepalle PRDA 1.730 1.71 99%
3 Nawata - Parussella PRDA 2.050 2.05 100%
4 Parussella - Ranpaumgama PS 2.970 0.00 0%
5 Batakitta - Mahabge PRDA 7.390 2.30 31%
6 Seepoth - Nagastenna PRDA 3.090 0.00 0%
7 Maliboda - Magala Ingiriyawatta PS 2.790 0.76 27%
9 Deraniyagala Hospital - Dikella/Dehiovita PRDA,PS 8.800 1.13 13%
10 Thannimale - Maharangalla PRDA,PS 3.620 3.24 90%
11Bulathkohupitiya Dedugala Road 8th Bend - Kalupahana
watta Neluwakkana -NarangallaPS 2.700 0.00 0%
12 Panapitiya Junction - Poonahela Panapitiya - Ambamalla PRDA 5.110 3.42 67%
14 Warakatenna - Meegastenna PRDA 4.520 0.00 0%
15 Ambalanpitiya Bridge - Godagampala Junction PRDA 2.700 0.00 0%
16Atulugama Junction to Kanangama Udukumbura Road
Tenkiyawaththa RoadPRDA 3.450 3.14 91%
17 Boralankada Udabage Junction to Iyalawatta Kelani River PRDA,PS 10.330 6.92 67%
18 Katulanda Road PRDA 5.500 3.85 70%
19 Debegama - Kelegama - Napawala PS 3.280 3.26 99%
70 Maniyangama junction to Welangalla Kadamandiya PRDA 4.500 4.23 94%
3 km 4 km 5 km 6 km 7 km 8 km 9 km1 km 2 km
Surfacing Length Road No Road Name
11 km10 km
Road
Catogory
Actual Road
Length (km)
Completed
Length (km)
Completed
%
78
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
Cum. Plan % 0.00% 0.00% 0.41% 1.74% 4.30% 8.74% 13.50% 18.27% 23.13% 28.26% 33.39% 38.52% 43.65% 48.78% 53.91% 59.04% 64.17% 69.30% 74.43% 79.56% 84.64% 89.47% 94.23% 98.23% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan % 0.00% 0.00% 0.12% 0.66% 1.41% 2.01% 4.21% 7.81% 11.91% 15.11% 21.42% 27.87% 33.07% 39.96% 46.84% 53.72% 58.92% 65.80% 72.68% 79.56% 84.64% 89.47% 94.23% 98.23% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 2 % -
07.03.20180.00% 0.00% 0.12% 0.66% 1.41% 2.01% 4.21% 7.81% 11.91% 15.11% 20.24% 24.78% 29.39% 35.04% 40.20% 43.26% 45.43% 47.10% 47.74% 47.89% 47.89% 47.89% 47.99% 47.99% 47.99% 49.01% 51.32% 55.23% 58.04% 62.56% 67.99% 74.18% 80.59% 86.96% 92.91% 96.95% 100.00%
Cum. Actual % 0.00% 0.00% 0.12% 0.66% 1.41% 2.01% 4.21% 7.81% 11.91% 15.11% 20.24% 24.78% 29.39% 35.04% 40.20% 43.26% 45.43% 47.10% 47.74% 47.89% 47.89% 47.89% 47.99% 47.99% 47.99% 48.87% 49.85% 50.97% 51.26% 52.10%
Work Progress Physical – KE 1
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target (Revised) Actual Target (Revised) Actual
Physical 100.00*(58.04)% 51.26% 100.00*(62.56)% 52.10%
79
Payments Certified – KE1
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,972,526,288.65
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)940,126,319.92
NOTE : * - Physical target percentage is based on the Revised Programme (Revision 2) of KE1 Contract
80
Photographs – KE 1
Site clearing at Ch. 8+400 - 8+800 BS Deraniyagala Hospital - Dikella
Dehiowita Road (ID09)
L drain construction at Ch. 3+520 3+540 LHS
Thannimale - Maharangalla Road (ID10)
Sub base surface preparation at Ch. 8+530 - Ch. 8+543 RHS
Deraniyagala Hospital - DikellaDehiowita Road (ID09)
Total Surfacing Length : 47.67 Km (61.35%)
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 KE2
Handed Over Road
81
20Atalawaththa Wangedimole Ela Hedungama Puhulwala
Salgala WelhellaPS 9.690 6.60 68%
21 Kithalangamuwa Batuwana Road PS 5.690 3.06 54%
22Kadigamuwa - (Kiriwana Junction) Narangastenna
TemplePS 1.282 1.28 100%
23 Mahalla - Troywatta - Eke kanuwa Road PS 3.864 0.50 13%
24 Indurana - Amithirigala Road PRDA 6.685 5.55 83%
26 Pamankade - Mahadeniya Road PRDA 4.619 3.72 81%
27 Imbulana - Weddawala - Gonagaldeniya Road PRDA 5.619 4.57 81%
33 Arandara Dewalaya - Boyagoda - Holombuwa Road PRDA, PS 3.867 3.82 99%
34 Hapudeniya - Malwana PS 1.722 1.72 100%
35 Pindeniya Bridge Weliwanguwa PS 1.960 1.91 97%
36 Etikeeriyagolla - Naberiyawa – Atugoda Road PRDA 5.094 3.69 72%
37 Makuddala Ayurrvedic Center - Kahatagolla Junction PS 2.763 1.91 69%
38 Imbulgala to Ambanpitiya - Kumarage Mawatha PS 3.464 0.00 0%
39 Alawattenna - Dedigama PS 5.008 2.98 60%
40 Palapoluwa - Kumbalgama PS 2.988 0.00 0%
57 Tholangamuwa - Ihalagama Gasnawa Road PS 0.965 0.73 76%
58Algama - Dikdeniya Road (Algama Kanista
Vidyalaya,Ihalagama RoadPS 3.595 0.00 0%
59Dedigama - Veneriwaththa - Koongahamula Pitadeniya
RoadPS 3.356 0.00 0%
60 Dedigama - Herathgoda - Othnapitiya Road PS 1.842 0.92 50%
61 Dummaladeniya - Meneripitiya - Meerigama Road PS 1.250 0.00 0%
63 Ambepussa Dadli Senanayaka Mawatha PS 2.381 2.38 100%
Road No Road NameRoad
Catogory
Actual Road
Length (km)
Completed
Length (km)
Completed
% 9 km 10 km
Surfacing Length
4 km 5 km 6 km 7 km 8 km1 km 2 km 3 km
82
Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18
Cum. Plan % 0.00% 1.00% 1.00% 2.00% 4.00% 7.00% 12.00% 17.00% 24.00% 31.00% 38.00% 44.00% 51.00% 56.00% 61.00% 67.00% 72.00% 78.00% 84.00% 89.00% 94.00% 96.00% 97.00% 98.00% 99.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised - 1 % 0.00% 0.00% 0.00% 1.00% 2.00% 3.00% 4.40% 8.80% 14.14% 18.90% 25.60% 31.10% 37.20% 42.27% 47.62% 53.60% 61.38% 69.56% 77.69% 85.45% 90.78% 94.60% 97.49% 98.88% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Revised Programme
Submitted with EOT 0.00% 0.00% 0.00% 1.00% 2.00% 2.70% 4.40% 8.80% 14.14% 17.73% 22.22% 26.19% 29.33% 30.44% 34.00% 35.94% 37.69% 39.54% 41.66% 45.69% 51.56% 58.47% 66.43% 73.25% 80.17% 86.48% 92.69% 96.95% 99.23% 100.00%
Cum. Actual % 0.00% 0.00% 0.00% 1.00% 2.00% 2.70% 4.40% 8.80% 14.14% 17.73% 22.22% 26.19% 29.33% 30.44% 34.00% 35.94% 37.69% 39.54% 41.66% 43.36% 44.44% 46.14% 49.32% 53.35% 57.48% 60.39% 64.21%
Work Progress Physical – KE 2
83
Payments Certified – KE2
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target (Revised) Actual Target (Revised) Actual
Physical 100.00*(86.48)% 60.39% 100.00*(92.69)% 64.21%
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,816,999,270.80
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)959,415,976.55
NOTE : * - Physical target percentage is based on the Revised Programme (Revision 2) of KE2 Contract
Photographs – KE 2
84
ABC final cut at Ch. 0+550 –0+650Ibulana Ambanpitiya Kumarage
Mawatha Road (ID 38)
Asphalt laying at Ch. 2+508-2+570Etikeeriyagola Naberiyawa Atugoda
Road (ID 36)
Final inspection for road handing over in Hapudeniya Malwana
Road (ID 34)
Total Surfacing Length : 38.29 Km (56.79%)
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 KE3
Handed Over Road
85
28 Molagoda (Shed) - Alulena Temple PRDA 2.680 2.462 92%
29 Kempitiya Muslim Palileya - Kempitiya Temple PRDA 2.600 0.884 34%
30Korahetta Meeduma Vidyalaya - Dambulla Clinic Center (Rabukkana -
Dobemada Road) PS 2.560 1.954 76%
31 Daluggala (Junction) - Bathaburaya Playground PRDA,PS 3.900 3.896 100%
32 Deldeniya (Junction) - Randeniya PS 2.290 0.000 0%
42Wanduragoda Teample Junction (Mawanella - Hemmathagama Road) -
AluthnuwaraPS 1.250 1.247 100%
43(Mawanella - Hemmathagama Road) Eraminigammana Temple -
Thambavita - Gampola Road JunctionPS 3.440 1.317 38%
44 Alpitiya - Dompitiya Magama - Ambadeniya PS 1.110 0.000 0%
45Heendeniya - Danagama Road (Anwarama Shed) Heendeniya
Danagama JunctionPS 2.730 2.460 90%
46 Road to Weganthale Saradeyal Village PS 2.000 1.584 79%
47Keppitipola - Mahakehelwala Ihalagama - Galpotta Pasal junction -
Kiriyateuna - BeddewelaPS 6.380 3.591 56%
48Gangoda Temple - Eke Kanuwa Mediliya Road (From Dippitiya -
Hemmathagama Road,Sarath's Kade)PS 1.830 0.000 0%
71 Widiyathenna dumabuluwawa via Walekade PS 2.600 1.473 57%
50 Dippitiya - Demadahiriya - Dooldeniya - Thalgaspitiya Road PS 4.990 2.780 56%
51 Thuththiripitiya Junction - Wattegadara PRDA,PS 4.260 2.487 58%
52 Thalgamuwa - Attapitiya PRDA,PS 3.160 3.160 100%
53 Wakirigala Dispensary - Polkubura Namalgama Road PS 2.450 0.000 0%
54 Aranayaka Town - Sapumal Ambe Welanthalawa Road PS 2.070 0.535 26%
55 Yalapala - Galatara - Erawwala Road PS 1.850 1.853 100%
56 Hathgampola Vidyalaya - Elangapitita PS 2.690 0.660 25%
64 Elbert Senavirathne Mawatha - Kegalle UC 0.880 0.860 98%
65 Ranwala - Kahagalla - Nawagamuwa Road PRDA,PS 3.540 2.617 74%
66 Randeniya Graselin Janapadaya - Dimbulgamuwa Road PS 2.250 0.685 30%
68 Paragammana - Dikkella - Babaradeniya Beragala Road PS 1.230 1.230 100%
69 Karadupana - Malwatta Kanda - Dewela Road PS 2.550 0.190 7%
Road
NoRoad Name
Road
Catogory
Actual Road
Length (km)
Completed
Length (km)
Completed
% 7 km
Surfacing Length
1 km 2 km 3 km 4 km 5 km 6 km
86
Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18
Cum. Initial Plan % 0.00% 0.00% 1.00% 2.00% 2.00% 4.00% 8.00% 13.00% 18.00% 23.00% 29.00% 35.00% 40.00% 46.00% 52.00% 58.00% 63.00% 69.00% 75.00% 80.00% 86.00% 91.00% 94.00% 97.00% 98.00% 99.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan % 0.00% 0.00% 0.00% 0.00% 1.00% 2.00% 3.00% 7.51% 12.83% 17.76% 22.11% 27.60% 31.02% 35.60% 40.81% 46.08% 52.10% 58.31% 65.47% 72.97% 80.04% 86.86% 91.77% 96.64% 98.61% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Revised Programme
Submitted with EOT 0.00% 0.00% 0.00% 0.00% 1.00% 2.00% 2.50% 3.80% 6.10% 11.40% 15.70% 21.93% 26.10% 30.00% 30.76% 32.26% 32.88% 34.50% 36.18% 37.60% 41.18% 47.10% 53.70% 60.87% 66.68% 73.11% 79.58% 85.50% 91.26% 96.45% 99.70% 100.00%
Cum. Actual % 0.00% 0.00% 0.00% 0.00% 1.00% 2.00% 2.50% 3.80% 6.10% 11.40% 15.70% 21.93% 26.10% 30.00% 30.76% 32.26% 32.88% 34.50% 36.18% 37.60% 39.19% 40.83% 42.45% 45.09% 47.91% 50.88% 51.78% 54.18%
Work Progress Physical – KE 3
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target (Revised) Actual Target (Revised) Actual
Physical 100.00*(79.58)% 51.78% 100.00*(85.50)% 54.18%
87
Payments Certified – KE 3
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,632,455,502.55
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)825,363,939.23
NOTE : * - Physical target percentage is based on the Revised Programme (Revision 2) of KE3 Contract
Photographs – KE 3
88
Culvert Concreting at Ch.1+680Ranwala Kahagalla Road.
(Rd No-65)
Priming at Ch.0+500Kempitiya-Kempitikanda Road.
(Rd No-29)
Shoulder construction (Box method) at Ch. 3+270
Hathgambola Elagapitiya Road(Rd ID 56)
Overall Physical Progress Summary – iROAD – Kalutara District(up to 31 May 2018)
91
Package
No.Contractor
Accepted
Contract
Amount/
(Rs. Million)
No. of
Roads
Total Road
Length as per
the BOQ/ (km)
No. of Roads
Civil Works
in Progress
Total road
pavement length
(asphalt+concrete)
completed (km)
Actual Physical
Progress as at
30 April 2018
(%)
Physical Progress; Cumulative
Status up to 31 May 2018 (%)
Target (Revised) Actual
KL 01 Maga 1,912 42 94.00 28 42.89 65.71% 93.38(89.03)% 67.87%
KL 02OCPL Jv
RCPL1,811 19 89.00 9 22.87 27.29% 96.03(92.36)% 28.15%
KL 03OCPL Jv
RCPL1,817 22 94.00 14 21.34 40.78% 80.92(91.15)% 41.48%
Total / Avg. 5,540 83 277.00 51 87.11 44.59% 90.85% 45.83%
92
Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18
Cum. Plan % 0.04% 0.08% 0.24% 0.89% 2.31% 4.46% 7.97% 10.69% 14.90% 19.69% 25.77% 31.68% 38.30% 45.49% 51.81% 58.80% 65.84% 72.49% 78.30% 84.83% 90.85% 95.47% 97.94% 99.82% 100.00%
Cum. Actual % 0.00% 0.00% 0.23% 0.38% 2.11% 4.24% 6.75% 8.53% 10.45% 14.65% 18.80% 23.19% 25.59% 28.53% 31.21% 33.67% 37.82% 40.46% 42.91% 44.59% 45.83%
Asphalt Paving Progress –iROAD Kalutara District /(up to 31 May 2018)
93
Package No.
ContractorNo. of Roads
Actual Total Road
Length / (km)
No. of Roads Civil Works in Progress
Road Length Civil works in
Progress/ (km)
Road length of Asphalt
completed/(km)
KL 01 Maga 42 91.43 28 63.00 42.89
KL 02 OPCL JV RCPL 19 88.44 9 62.80 22.87
KL 03 OPCL JV RCPL 22 93.35 14 56.70 21.34
Total 83 273.22 51 182.50 87.11
Package NoContractor
Accepted Contract Amount/ (Rs.
Million)
Total Certified Amount (Mobilization Advance) /(Rs.
Million)
KL 01 Maga Engineering (Pvt.)Ltd 1,912 971.28 (220.43)
KL 02Olympus Construction(Pvt.)Ltd JV
with Rani Construction (Pvt.)Ltd1,811 554.86 (278.25)
KL 03Olympus Construction(Pvt.)Ltd JV
with Rani Construction (Pvt.)Ltd1,817 594.15 (282.71)
Total 5,541 2,120.29 (781.39)
Overall Financial Status –iROAD-Kalutara District/(up to end of 31 May 2018)
94
Progress of Culverts & Bridges /(up to 31 May 2018)
95
DistrictPackage
NoContractor
No. of Culverts No. of Culverts
No. of Bridges
RemarksNew / Re -Construction/
Widening
Completed / in Progress
RepairCompleted / in
Progress
Kalutara
KL1 Maga Engineering (Pvt) Ltd 337 171 37 0 2
Design work is in progress for re-
construction of bridge at
Ch.2+040 in Rd no.83
KL2
Olympus Construction(Pvt.)Ltd
JV with Rani Construction
(Pvt.)Ltd
453 117 156 17 3
Design submitted for one bridge
and comments were given to the
Contractor
KL3
Olympus Construction(Pvt.)Ltd
JV with Rani Construction
(Pvt.)Ltd
488 130 9 0 3Bridge status report submitted for
all bridges
Total 1278 418 202 17 8
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 KL1
Handed Over Road
96
Asphalt Concrete
Completed Length
(km)Surfacing Length
2 Kawatayagoda Pahala Road (by road) PS 0.77 0.411 0.357 100%
16 Kiriberiya Mandawala Road (by road) PS 0.75 0.746 0.000 99%
0.000 88%45From Ilimba Junction to Ilimba Thotupola
Road PS 3.34 2.940
0.000 73%
95From Arukgoda Indrasara Mawatha to
(Pulungas Junction) Thimbiriya JunctionPS 1.40 0.781 0.100 63%
92Bellanthudawa Galkade Junction to Panadura
Rathnapura Nambapana RoadPS 3.30 2.400
0.000 52%
16 Kiriberiya Mandawala Road PS 1.45 0.766 0.675 99%
64 Kudagonaduwa Thuduwa Road PRDA 1.61 0.835
64 Kudagonaduwa Thuduwa Road (by road) PRDA 0.99 0.710 0.205 93%
2 Kawatayagoda Pahala Road PS 1.38 1.380 0.000 100%
41Millaniya Lenawara Sidurangala Watta via
HoranaPS 2.60 2.270
75From Fonseka Road, Soloman Road Across
Kaviraja Mawatha GalthudeMC 1.76 1.647 0.000 94%
0.000 87%
3.93 3.092 0.795 99%
93 Atalugama Mubarak Mawatha PS 1.30 1.285 0.000 99%
Road
NoRoad Name
Road
Catogory
Actual
Road
Length
(km)
Completed
%1 km 2 km 3 km 4 km 5 km
83 Panape Ketagoda Millaniya Road PS
Total Surfacing Length : 42.89 Km (46.91%)
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 KL1 (Cont.)
Handed Over Road
97
Asphalt Concrete
Completed Length
(km)Surfacing Length
37%85
Thumminigoda Road (From Madurawala 458
Bus Route to Raigama Anguruwathoda Bus
Route)
PS 0.72 0.264 0.000
65%
96From Rukgaha Bus road Retiyalagoda
Belikele Via Alubomulla.PS 2.71 1.445 0.000 53%
94Alubomulla Batadombathudawa Retiyalagoda
Via MaswattaPS 1.47 0.960 0.000
40%
47 Walathara - Munhena Kurudugasmulla by Rd PS 1.24 0.555 0.000 45%
47 Walathara - Munhena Kurudugasmulla Rd PS 4.12 1.656 0.000
82%
67From Paraduwa Bogaha junction to Gunagoda
RoadPS 2.02 0.240 0.850 54%
66 From Kalapugama junction to Palpola road PRDA/PS 2.80 2.015 0.270
97%
44 From Kandana to Ilimba road PS 3.28 2.390 0.000 73%
76
From Galthude Samagi Mawatha -
Rathanagiriya Watta road to Hirana Temple
(by road)
PS 0.95 0.920 0.000
96%
76From Galthude Samagi Mawatha -
Rathanagiriya Watta road to Hirana TemplePS 1.55 0.723 0.100 53%
9 New Chattle Tamil School Road PS 2.50 2.295 0.100
43 Yala Junction to Werawaththa Naragala Road PRDA 3.80 2.100 0.540 69%
2 km 3 km 4 km 5 km
Road
NoRoad Name
Road
Catogory
Actual
Road
Length
(km)
Completed
%1 km
98
Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18
Cum. Plan % 0.13% 0.25% 0.71% 2.65% 5.30% 8.79% 12.36% 15.18% 19.39% 24.71% 30.79% 36.58% 42.38% 48.46% 54.93% 62.24% 69.65% 77.13% 83.56% 88.62% 93.38% 96.56% 98.90% 100.00%
Cum. Revised Plan % 0.00% 0.01% 0.67% 1.10% 4.68% 8.43% 13.22% 15.84% 19.82% 24.91% 31.03% 36.62% 42.12% 47.69% 53.68% 60.64% 68.00% 75.26% 81.02% 84.79% 89.03% 93.15% 96.88% 100.00%
Cum. Actual % 0.00% 0.01% 0.67% 1.10% 4.68% 8.43% 12.74% 15.21% 18.45% 23.35% 27.42% 32.42% 36.58% 40.68% 45.18% 49.83% 55.93% 59.82% 63.41% 65.71% 67.87%
Work Progress Physical – KL 1
99
Payments Certified – KL 1
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,912,467,146.40
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)971,284,929.74
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target (Revised) Actual Target (Revised) Actual
Physical 88.62(84.79)% 65.71% 93.38(89.03)% 67.87%
Photographs – KL 1
100
Boulders packing at Ch. 0+800Kudagonaduwa Thuduwa Road
(ID 64)
Culvert construction at Ch. 0+590
From Kandana to Ilimba Road (RD No 44)
Embankment construction at Ch. 3+000
Wilpatha to Magurugoda via Thalliyadda Road (ID 15)
Total Surfacing Length : 22.87 Km (25.86%)
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 KL2
Handed Over Road
101
3 Bellana Panadadukanda Rd PS 4.72 0.00 0%
5 From Addaragoda Weepalla Rd via Wedigoda PS 6.45 0.00 0%
6 Athwelthota Ambegoda via Bampara Rd PS 4.93 0.00 0%
8 Boralugoda Thiniyawala Road PS 5.83 0.00 0%
54Morapitiya New road to 1st mile post via Rankoth
mawathaPS 3.87 0.00 0%
34 Katugahahena Hospital Rd to Kosgahakanda Junction via
St. George WattaPS 3.40 2.81 83%
35Kurudippita Road(HAA rd to Meegama- Galmaththa
Road)PS 2.70 2.66 99%
36 Mahawatta Junction to Soldarakada Junction. PS 4.00 3.83 96%
37 Walipanna Junction to Rameeya Junction Road. PS 2.10 2.06 98%
39 Bodhiyakanda junction to Mulatiyana rd PS 2.64 0.00 0%
40 Walkandala junction to Wellatha junction PRDA/PS 6.16 0.00 0%
7 Nerihena Wewalla Yattapatha PS 4.35 0.00 0%
51 Pannila Kannangara Mw,Halwala via Galathara PS 4.69 1.72 37%
52From Maddegama to Thalpadiwala road across
Meegahathenna ( Nawalalkanda road)PS 4.57 0.00 0%
53 Walallawita Uthumgama via Koopiyawatta road PRDA 14.50 6.28 43%
88 Malliwatta rd via Paraigama, Elagiriya PRDA/PS 4.92 1.59 32%
89 Pimbura Halowita Road PS 3.13 0.00 0%
90 Kirimetidola Kiril lahendeniya Via Kewitiyagala road PS 2.820.00 0%
91 Dapiligoda Diyawana Road PS 2.660.00 0%
14 km 15 km8 km 9 km 10 km 11 km 12 km 13 km7 km
Road
NoRoad Name
Road
Catogory
Actual Road
Length (km)
Completed
Length (km)
Completed
%
Surfacing Length
1 km 2 km 3 km 4 km 5 km 6 km
102
Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18
Cum. Plan % 0.00% 3.11% 6.63% 8.72% 11.26% 15.19% 21.84% 27.68% 34.76% 40.42% 48.05% 53.37% 58.83% 63.91% 68.24% 73.45% 79.50% 84.53% 89.20% 92.90% 96.03% 98.22% 99.48% 99.89% 100.00%
Cum. Revised Plan(Wei.) %0.00% 0.00% 0.01% 0.03% 1.25% 3.56% 7.45% 10.72% 14.89% 18.95% 24.65% 31.27% 39.12% 47.20% 52.62% 58.12% 65.12% 71.00% 77.00% 85.60% 92.36% 97.67% 99.25% 99.89% 100.00%
Cum. Actual % 0.00% 0.00% 0.01% 0.03% 1.25% 3.26% 4.26% 5.83% 7.23% 9.41% 13.38% 16.25% 17.24% 18.66% 20.02% 21.21% 23.56% 25.08% 26.93% 27.29% 28.15%
Work Progress Physical – KL 2
103
Payments Certified – KL 2
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,811,352,867.60
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)554,864,377.01
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target (Revised) Actual Target (Revised) Actual
Physical 92.90(85.60)% 27.29% 96.03(92.36)% 28.15%
Photographs – KL 2
104
Excavation for concrete drain at Ch. 1+900 RHS
Katugahahena Kosgahakanda Road (Rd ID 34)
Asphalt Laying & Compaction at Ch. 3+200
Malliwatta to Pareigama Road (Road ID 88)
Culvert backfilling at Ch. 2+053 RHS
Katugahahena Kosgahakanda Road (Rd ID 34)
Total Surfacing Length : 21.34 Km (22.86%)
Surfacing Work Completed
Surfacing Work in progress
Surfacing Not Started
Total Road Length
Asphalt work Completed Length
Concrete work Completed Length
ROAD SURFACING PROGRESS AS AT END OF MAY 2018 KL3
Handed Over Road
105
17From Olaboduwa Main Rd to Mahawatta Ju; Dehigaspitiya(From Mahawatta
Junction to Maharagama Horana Rd)PS 3.527 3.11 88%
20From thalgahawila rd to Kirigala junction,Gurugada,Munagama East Grama
Niladari Division to Gurugoda padukka RdPS 2.921 2.11 72%
21 Moragahahena Uduwa Kanishta Vidyalaya via Kananwila PS 3.234 1.56 48%
78 Korala-ima junction Mohottigoda rd across Jayadadagama PS 4.810 0.00 0%
79 Thalagala-Gonapala across Unkuttawala to Kiriwaththuduwa rd PS 3.570 2.50 70%
80 Pokunuwita across Shanthi mawatha to Anguruwathota PS 1.640 0.00 0%
22 Ihala Welgama Kallumale Bulathsinhala road PRDA/PS 5.478 0.00 0%
23 Polegoda Ihala Welgama Paragoda via Wadigangoda road PS 9.433 0.00 0%
24 Ihala Kudaligama Iddagoda road PS 3.823 0.00 0%
25 Polegoda P.S. Junction to Immilla Junction PS 2.233 0.00 0%
26 Bogahawaththa to Gallakpahala rd PS 3.096 0.00 0%
27 Halwathura(from School junction) Mugunakolahena Delmalla PS 4.432 0.00 0%
28 Niggaha Agirikanaththa Via Gawaragiriya PS 4.952 0.00 0%
29From Malwatta junction Meegahakumbura Heenela Diwalakada Kalugala
Malwattha roadPS 11.251 2.12 19%
70 Pahala Naragala Dewamulla Gangaramaya Kokhena Temple Road PS 2.311 0.90 39%
71 From Govinna Kota road to Govinna Weralugusthotupola rd PS 2.893 0.00 0%
73 Paruthalvila Bakamunawatta Heenpandala Paragoda Road PS 5.359 0.00 0%
30From Ratnapura Panadura Rd to Akkara 100 New Town to Sagara Palansooriya
Collage Rd via Batugampala PS 6.884 0.84 12%
31 From Boralugoada Rd to Poruwadanda Jun via Manana Sudarshanaramaya. PS 2.799 0.73 26%
32 From Kotigala Ju. To Karauda Village via Kurana Akkara 60 Rd PS 4.018 2.92 73%
81 From kadanapitiya sawgus junction to Degamthilaka Mawatha PS 2.630 2.55 97%
82 Rathmalgoda Deerananda Mawatha PS 2.058 2.06 100%
Road
NoRoad Name
Road
Catogory
Actual Road
Length (km)
Completed
Length (km)
Completed
% 12 km
Surfacing Length
1 km 2 km 3 km 4 km 5 km 11 km7 km6 km 8 km 9 km 10 km
106
Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18
Cum. Plan % 0.00% 2.79% 5.93% 7.66% 8.44% 10.90% 13.36% 15.84% 20.29% 25.60% 28.99% 30.54% 33.65% 39.71% 43.45% 47.78% 55.06% 61.00% 68.78% 74.93% 80.92% 87.20% 92.44% 99.52% 100.00%
Cum. Revised Plan
with Weitage %0.00% 0.00% 0.00% 0.00% 0.39% 1.02% 3.25% 5.50% 9.99% 15.20% 21.64% 27.15% 33.65% 41.58% 49.12% 57.63% 64.41% 71.21% 76.89% 84.10% 91.15% 95.60% 97.70% 99.58% 100.00%
Cum. Actual % 0.00% 0.00% 0.00% 0.00% 0.39% 1.02% 3.25% 4.56% 5.76% 11.20% 15.60% 20.90% 22.94% 26.26% 28.43% 29.98% 33.98% 36.48% 38.40% 40.78% 41.48%
Work Progress Physical – KL 3
107
Payments Certified – KL 3
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,817,750,688.60
Cumulative Certified Amount up to End of May 2018
(With Mobilization advance)594,147,369.53
Progress
Cumulative Status as at30-April-2018 (%)
Cumulative Status as at31-May-2018 (%)
Target (Revised) Actual Target (Revised) Actual
Physical 74.93(84.10)% 40.78% 80.92(91.15)% 41.48%
Photographs – KL 3
108
Culvert construction at Ch. 2+418
Manan Sudarshanramaya Road (Road ID 31)
ABC laying at Ch. 0+000-0+480
Rathnapura Panadura Road to Batugampola Road (Road ID 30)
Asphalt laying at Ch. 0+330-0+590
Thalagala Gonapola Ankuttawala Road (Road ID 79)
Details of Handed Over Roads (Central Province / up to end of May 2018)
110
District Package
No.Contractor
No. of Handed
Over Roads (Total
No. of Roads)
Handed Over Length
(Total Road Length) /
(km)
KA 01 Sierra Construction (Pvt.)Ltd. 5 (17) 10.57 (75.11)
KA 02 Sierra Construction (Pvt.)Ltd. 4 (17) 13.73 (72.46)
KA 03 Edward and Christie. 5 (16) 17.56 (68.55)
MA 02 Edward and Christie. 14 (14) 57.87 (57.97)
MA 03 CML-MTD Construction limited 8 (19) 16.53 (60.96)
NE 01 Sierra Construction (Pvt.)Ltd. 3 (14) 9.00 (72.45)
NE 02 Sierra Construction (Pvt.)Ltd. 7 (14) 14.20 (36.21)
NE 03 Sierra Construction (Pvt.)Ltd. 2 (15) 4.00 (66.11)
48 (126) 144.12 (509.82)
Kandy
Matale
Nuwara-Eliya
Total
Details of Performance Based Maintenance in Central Province(up to end of May 2018)
111
Note : √ - PBM started x – PBM not yet done ∙ - Not yet taken over
Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18
21 Angammana Nikathenna Road 11-Dec-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √
44 Sirimalwatta Nattarampotta Road 31-May-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √ √ √ √ √
45Manikkahinna (Pitiye Dewalaya) Galaluwa
Road31-May-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √ √ √ √ √
46 Gagasiriwatta Polgolla Road 31-May-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √ √ √ √ √
47Digana Aluthwatta Road (Aluthwatta No.
10 Junction) - Parana Gagapitiya Road7-Jan-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √
12 Kobbekaduwa Gamameda Road 31-Jan-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √
29 Pamunuwa Daliwala Mugatiyapola Road 19-Sep-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √
18Nawalapitiya - Udakanda Bus Stand via
Veralugashinna, Weligodawatta2-Mar-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √
30 Pamunuwa Junction - Elugoda Road 19-Sep-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √
10 Delthota town - Gabadagama Road 6-Oct-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √
7 Gurudeniya - Dambawela Bus Stand 21-Nov-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √
38
Poththapitiya Weligodapola Main Road to
Dedunupitiya Post Office to Weniwella
Road via Kalatuwawa
26-Sep-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √
48 Karaduwawala Gatathale Road 21-Feb-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √
49Bokkawala Pahala Higulwala via
Miliyedda Road28-Nov-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √
7 Adikarigama - Ambewela - Merimount Road 24-Jan-2017 ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √
9Karaliyadda Village Road Via Gonagantenna
Hospital29-Mar-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √
6 Walapane Hospital Road 29-Mar-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √
18 Pilot Project road 22-Mar-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √
17 Lower Pudaluoya to Upper Shinigama Road 9-Apr-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √
32 Henfold Couleena State Road 27-Dec-2016 ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √
23 Thalawakele - Galkanda Road 16-Mar-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √ √ √ √ √ √ √
28 Kandapola Heatherset Estate Road 31-May-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ x
30Kothmale Dam View Point to Kotagepitiya
Road1-Sep-2016 √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √
31 Connecting Road to Halpola 1-Nov-2016 ∙ ∙ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √
44 Nawathispane Harangala Road 3-Feb-2017 ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √
48 Ginigathhena School Road 3-Jul-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √ √ √ √
Kandy
KA01
KA02
KA03
Nuwara-Eliya
NE01
NE02
NE03
DistrictContract
Package
Road
No Road Name
Date of Taking
Over
PBM Inspection
Details of Performance Based Maintenance in Central Province(up to end of May 2018) Cont.
112
Note : √ - PBM started x – PBM not yet done ∙ - Not yet taken over
Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18
18 Dambuluoya Juction to Kalundewa Road 15-Aug-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √ √
20 Kapuwatta Akkara Seeya Yapagama Road 8-Jan-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √
21Yapagama dambulla pola ate Batuyaya via
diddeniya Kade Road8-Jan-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √
24Sisirawatta Bulanwala Ahuparayaya
Dambulla Town Road 8-Jan-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √
19 Kapuwatta Yapagama Road 8-Jan-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √
23 Thiththawelgolla Rathmalgahaela Road 29-Sep-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √
22 Kandalama Rotawewa Road 7-Dec-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √
25 Pelwehara Randeniya Bulagala Road 29-Sep-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √
49 Walasewewa Road 12-Dec-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √
53 Dabuyaya dambagolla Road 12-Dec-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √
50 Galapaulla Damunumulla Road 15-Aug-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √ √
55 Damaunumulla Yatigalpoththa Road 15-Aug-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √ √
52 Akuramboda temple to Koswatta Road 12-Dec-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √
54 Ambokka Dewalaya Road 12-Dec-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √
27 Boballa Bibila Road 22-Aug-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √ √
39 Bibila Murutholuwa Road 7-Mar-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √
40Kanamulayaya Rubber Watta via Police
Station Road7-Mar-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √
41 Meegolla Deewara Gammanaya Road 7-Mar-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √
42Gedige Junction to Hapugasyaya Tamil
village via Ududeniya Road22-Aug-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √ √
35Madawela Junction to Nalanda Industrial
Zone2-Mar-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √
36Ellepola Kalupalama to Hilton Janapadaya
Road26-Sep-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √
38 Kanangamuwa Parawatta Road 25-Aug-2017 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √ √ √ √ √ √ √ √
DistrictContract
Package
Road
No Road Name
Date of Taking
Over
Matale
MA02
MA03
PBM Inspection
Photographs of Joint PBM Inspection in Central Province
113
Delthota town – Gabadagama Road (ID 10)
KA3 Package, Kandy District
Kapuwatta Akkara 100 Yapagama Road (ID 20)
MA2 Package, Matale District
Walapane Hospital Road (ID 06)NE1 Package, Nuwara Eliya District
Details of Handed Over Roads (Sabaragamuwa Province)(up to end of May 2018)
115
District Package
No.Contractor
No. of Handed
Over Roads (Total
No. of Roads)
Handed Over Length
(Total Road Length) /
(km)
Ratnapura R3 R R Construction (Pvt.)Ltd. 5 (12) 37.83 (81.01)
5 (12) 37.83 (81.01)Total
Details of Performance Based Maintenance in Sabaragamuwa Province(up to end of May 2018)
116
Note : √ - PBM started x – PBM not yet done ∙ - Not yet taken over
- Not ApplicableNA
Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18
1 Ellagewatta junction to Godakawela via Opatha, Makandura 7-Nov-2017 ∙ ∙ √ √ √ √ √ √ √
8 Thapassarakanda~Wiskamgoda road via Karapotha bridge 7-Nov-2017 ∙ ∙ √ √ √ √ √ √ √
34 Ambagahayaya Juntion to 8th Mile Post via Mahayaya Road 17-Jan-2018 ∙ ∙ ∙ ∙ √ √ √ √ √
3696 Junction to Panamura road via Ranchamadama Ethgala-
ch.(6+500~10+250)km section (for water project)3-Apr-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ NA NA
3696 Junction to Panamura road via Ranchamadama Ethgala-
ch.(0+000~6+500)km section18-May-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ ∙ √
10 Weddagala~Kudawa~Wewagama road 5-Apr-2018 ∙ ∙ ∙ ∙ ∙ ∙ ∙ √ √
DistrictContract
Package
Road
No Road Name
Date of
Taking Over
PBM Inspection
Ratnapura R3
Photographs of Joint PBM Inspection in Sabaragamuwa Province
117
Ambagahayaya junction to 8 Mile Post via Mahayaya Road (ID 34) R3 Package, Ratnapura District
Thapassarakanda~Wiskamgoda Road via Karapotha Bridge (ID 08)
R3 Package, Ratnapura District
Ellagewatta junction to Godakawela via Opatha, Makandura Road (ID 01)
R3 Package, Ratnapura District
Wrokshop on Performance Based Maintenance in Nuwara Eliya District
118Photographs taken during the Workshop
Workshop on ‘Performance Based Maintenance’ was conducted by Eng. R M Amarasekara (Rural Road Specialist, iRoad Project) for Nuwara Eliya District at Sampath Hotel on 16th May 2018.
Participants :• Employer - RDA – PD(CP), PEs(CP), Executive Engineers
PS – Development Officers, Technical Officers, SecretariesDS – Assistant Directors, Secretaries
PRDA – Executive Engineers, Engineers• Consultant – TL, REs• Contractor – Project Managers
Road Pavement Construction Progress in PIC 03 up to 31 May 2018
119
Pro
vin
ce/
Dis
tric
t
Package No.
Name of the Contractor
Acc. Contract Amount/
(Rs. Million)
No. of Roads
Total Road
Length as per the BOQ/ (km)
Actual Total Road
Length/ (km)
Completion of Road Pavement Construction up to 30 April 2018/km
Asphalt length Contractor Agreed to complete during the
month of May 2018/km
Completion of Road Pavement
Construction during the month of May
2018
Total Asphalt length
completed up to end of
May 2018/km
Total road Pavement length
(Concrete+Asphalt) completed up to
end of May 2018/km
Percentage of Total
Pavement Completion of the Contract
Asphalt Concrete Asphalt Concrete
Ce
ntr
al P
rovi
nce
KA 01 Sierra Construction (Pvt.) Ltd. 1,756 17 76.20 75.11 68.78 0.28 2.95 0.840 0.00 69.62 69.90 93.06%
KA 02 Sierra Construction (Pvt.) Ltd. 1,924 17 70.85 72.46 64.76 5.29 2.35 0.250 0.00 65.01 70.30 97.02%
KA 03 Edward and Christie. 2,097 16 73.95 68.55 60.29 4.26 1.70 0.000 0.11 60.29 64.66 94.33%
MA 01KD Ebert and Sons Holdings(Pvt)
Ltd.1,622 18 75.70 75.12 52.98 0.00 3.40 0.850 0.00 53.83 53.83 71.66%
MA 02 Edward and Christie. 1,249 14 57.00 55.55 54.67 0.78 0.00 0.00 0.00 54.67 55.45 99.83%
MA 03 CML-MTD Construction limited 1,408 19 61.30 60.78 57.45 3.24 0.00 0.000 0.00 57.45 60.69 99.85%
NE 01 Sierra Construction (Pvt.) Ltd. 2,298 14 76.60 72.45 44.49 0.28 2.09 0.746 0.00 45.24 45.52 62.82%
NE 02 Sierra Construction (Pvt.) Ltd. 1,242 14 38.50 36.21 32.94 3.09 0.10 0.000 0.00 32.94 36.03 99.50%
NE 03 Sierra Construction (Pvt.) Ltd. 2,070 15 64.90 66.11 49.41 1.08 1.94 0.000 0.00 49.41 50.49 76.38%
Sab
arag
amu
wa
Pro
vin
ce
R 01KD Ebert and Sons Holdings(Pvt)
Ltd.2,022 12 82.95 80.13 46.56 0.00 3.50 0.990 0.00 47.55 47.55 59.34%
R 02KD Ebert and Sons Holdings(Pvt)
Ltd.2,384 14 91.70 92.37 41.06 0.00 6.00 1.910 0.00 42.97 42.97 46.52%
R 03 R.R. Construction (Pvt) Ltd. 2,021 12 80.35 81.01 77.50 3.51 0.00 0.000 0.00 77.50 81.01 100.00%
KE 01KD Ebert and Sons Holdings(Pvt)
Ltd.1,973 17 74.75 74.53 36.01 0.00 4.20 0.390 0.00 36.40 36.40 48.84%
KE 02Nawaloka Construction Co. (Pvt)
Ltd.1,817 21 78.25 77.70 44.44 0.86 5.86 2.370 0.00 46.81 47.67 61.35%
KE 03Nawaloka Construction Co. (Pvt)
Ltd.1,632 25 64.15 67.42 37.46 0.35 3.31 0.480 0.00 37.94 38.29 56.79%
Kal
uth
ara
Dis
tric
t
KL 01 Maga Engineering (Pvt) Ltd 1,912 42 94.00 91.43 36.84 3.99 5.00 1.680 0.39 38.52 42.89 46.91%
KL 02Olympus Construction(Pvt.)Ltd JV
with Rani Construction (Pvt.)Ltd 1,811 19 89.00 88.44 19.20 2.10 4.89 1.570 0.00 20.77 22.87 25.86%
KL 03Olympus Construction(Pvt.)Ltd JV
with Rani Construction (Pvt.)Ltd 1,817 22 94.00 93.35 19.94 0.12 3.91 1.140 0.14 21.08 21.34 22.86%
List of Utilities - Central Province (up to 31 May 2018)
120
PackageNo. of Roads
No. of Roads
Surveyed for Utility Shifting
Utilities to be Shifted
Electricity Pole/(Nos.) Telecom Pole/(Nos.) Water Line/(m)
Identifiedin
ProgressCompleted Identified
in Progress
Completed Identifiedin
ProgressCompleted
MA1 18 16 6 - 2 5 - - 600 - 600
MA2 14 14 11 - 11 3 - 3 300 - 300
MA3 19 19 4 - 4 8 - 7 8369 - 8369
KA1 17 17 49 - 24 18 10 08 700 - 700
KA2 17 17 55 - 48 73 - 42 993 - 993
KA3 16 16 63 11 52 47 - 47 4600 - 4600
NE1 14 14 20 - 5 13 - 1 1228 - 630
NE2 14 14 3 - 3 4 - 4 35420 90 35330
NE3 15 14 6 - 6 10 - 10 1315 - 1315
List of Utilities – Sabaragamuwa Province & Kalutara District (up to 31 May 2018)
121
PackageNo. of Roads
No. of Roads
Surveyed for Utility Shifting
Utilities to be Shifted
Electricity Pole/(Nos.) Telecom Pole/(Nos.) Water Line/(m)
Identifiedin
ProgressCompleted Identified
in Progress
Completed Identifiedin
ProgressCompleted
R1 12 10 47 9 38 49 - 49 420 28 392
R2 14 13 30 22 8 18 10 8 4750 1600 3150
R3 12 12 56 4 52 19 - 19 5735 - 5735
KE1 17 13 109 84 25 78 51 26 2000 - -
KE2 21 21 154 83 71 174 75 99 5750 2800 2950
KE3 25 21 174 78 96 254 46 208 2605 865 1740
KL1 42 34 75 44 31 180 85 95 300 25 275
KL2 19 10 38 7 7 86 - 58 1700 500 50
KL3 22 15 52 18 34 92 6 86 - - -
Cost of Utility Relocation - Central Province (up to 31 May 2018)
122
Dis
tric
t
Package No.
Name of the ContractorAmount paid up to 31st May 2018
Telecom Poles Electricity Poles Water Lines
Kan
dy
KA 01 Sierra Construction (Pvt.) Ltd. 1,596,006.21 3,610,411.10 1,873,037.73
KA 02 Sierra Construction (Pvt.) Ltd. 609,969.66 380,702.74 -
KA 03 Edward and Christie. 1,188,547.56 2,367,167.59 -
Mat
ale
MA 01 KD Ebert and Sons Holdings(Pvt) Ltd. - 262,823.80 404,793.26
MA 02 Edward and Christie - - 48,965.40
MA 03 CML-MTD Construction Ltd. - 65,018.12 14,594,696.06
Nu
war
a-El
iya NE 01 Sierra Construction (Pvt.) Ltd. 266,576.39 5,175.00 507,239.75
NE 02 Sierra Construction (Pvt.) Ltd. 37,628.00 - -
NE 03 Sierra Construction (Pvt.) Ltd. 62,580.77 79,594.24 2,406,647.86
Total 3,761,308.59 6,770,892.59 19,835,380.06
Cost of Utility Relocation - Sabaragamuwa Province & Kalutara District(up to 31 May 2018)
123
Dis
tric
t
Package No.
Name of the ContractorAmount paid up to 31st May 2018
Telecom Poles Electricity Poles Water Lines
Rat
nap
ura R 01 KD Ebert and Sons Holdings(Pvt) Ltd. 1,787,500.00 4,024,628.67 95,866.25
R 02 KD Ebert and Sons Holdings(Pvt) Ltd. 70,488.00 877,021.10 -
R 03 R.R. Construction (Pvt) Ltd. 111,098.80 2,469,243.80 521,590.62
Ke
galle
KE 01 KD Ebert and Sons Holdings(Pvt) Ltd. 103,363.00 3,048,511.43 -
KE 02 Nawaloka Construction Co. (Pvt) Ltd. 2,032,747.70 5,438,285.92 64,905.50
KE 03 Nawaloka Construction Co. (Pvt) Ltd. 3,012,620.47 2,767,032.22 532,980.57
Kal
uta
ra
KL 01 Maga Engineering (Pvt) Ltd 2,621,234.19 1,237,867.61 2,378,337.90
KL 02Olympus Construction(Pvt.)Ltd JV with Rani Construction (Pvt.)Ltd
2,947,532.88 937,770.57 -
KL 03Olympus Construction(Pvt.)Ltd JV with Rani Construction (Pvt.)Ltd
2,485,547.99 2,267,190.19 -
Total 15,172,133.03 23,067,551.51 3,593,680.84
Summary of Accidents reported in all Contracts-PIC 03 during the month of May 2018
124
Minor Major
KA1
KA2
KA3
MA1
MA2
MA3
NE1
NE2
NE3
R1
R2
R3
KE1
KE2
KE3 05/05/2018Telecom post and telecom cables were damaged
due to a tipper accidentMinor
Road : ID 45
Tipper No : LL 0734
Location : 4+870 LHS
Time : 12.45 pm
KL1
KL2
KL3
District Package Date of
Occurrence
No accidents reported during the month
DescriptionLevel of Condition
Matale
Kalutara No accidents reported during the month
Nuwara -Eliya
Ratnapura
Kandy
Remarks
Kegalle
Summary of Public Complaints – Central Provinceas at 31 May 2018
125
Dis
tric
t
Package No.
Name of the Contractor
No. of Public Complaints Received
TotalNo.
Completely Settled
Solutions in ProgressRequests Suggestions Complaints
Crack Related Issues
Kan
dy
KA 01 Sierra Construction (Pvt.) Ltd. 109 0 13 9 131 112 19
KA 02 Sierra Construction (Pvt.) Ltd. 129 2 20 0 151 151 0
KA 03 Edward and Christie. 253 1 26 5 285 260 25
Mat
ale
MA 01KD Ebert and Sons Holdings(Pvt)
Ltd.104 10 80 30 224 160 64
MA 02 Edward and Christie. 106 22 30 4 162 159 3
MA 03 CML-MTD Construction limited 85 1 24 21 131 110 21
Nu
war
a El
iya NE 01 Sierra Construction (Pvt.) Ltd. 138 3 3 0 144 85 61
NE 02 Sierra Construction (Pvt.) Ltd. 28 0 0 0 28 28 0
NE 03 Sierra Construction (Pvt.) Ltd. 123 4 14 0 141 77 64
Total 1075 43 210 69 1397 1142 257
Summary of Public Complaints – Sabaragamuwa Province & Kalutara Districtas at 31 May 2018
126
Dis
tric
t
Package No.
Name of the Contractor
No. of Public Complaints Received
TotalNo.
Completely Settled
Solutions in ProgressRequests Suggestions Complaints
Crack Related Issues
Rat
nap
ura
R 01KD Ebert and Sons Holdings(Pvt)
Ltd.55 11 41 0 107 102 5
R 02KD Ebert and Sons Holdings(Pvt)
Ltd.42 11 36 4 93 76 17
R 03 R.R. Construction (Pvt) Ltd. 449 14 31 7 501 450 51
Keg
alle
KE 01KD Ebert and Sons Holdings(Pvt)
Ltd.39 5 42 0 86 54 32
KE 02Nawaloka Construction Co. (Pvt)
Ltd.178 11 90 1 280 244 36
KE 03Nawaloka Construction Co. (Pvt)
Ltd.71 18 48 8 145 84 61
Kal
uta
ra
KL 01 Maga Engineering (Pvt) Ltd 95 2 101 11 209 117 92
KL 02Olympus Construction(Pvt.)Ltd JV
with Rani Construction (Pvt.)Ltd 123 10 41 14 188 111 77
KL 03Olympus Construction(Pvt.)Ltd JV
with Rani Construction (Pvt.)Ltd 104 5 31 0 140 118 22
Total 1156 87 461 45 1749 1356 393
Cost of Accommodating Public Complaints - Central Province (up to 31 May 2018)
127
KA 01 Sierra Construction (Pvt.) Ltd. 66 6,186,351.54
KA 02 Sierra Construction (Pvt.) Ltd. 133 17,200,780.00
KA 03 Edward and Christie. 69 7,736,637.00
MA 01 KD Ebert and Sons Holdings(Pvt) Ltd. 80 1,850,000.00
MA 02 Edward and Christie. 36 1,250,000.00
MA 03 CML-MTD Construction limited 45 2,425,000.00
NE 01 Sierra Construction (Pvt.) Ltd. 28 9,041,123.00
NE 02 Sierra Construction (Pvt.) Ltd. 28 4,414,450.00
NE 03 Sierra Construction (Pvt.) Ltd. 52 7,824,800.00
537 57,929,141.54 Total
Dis
tric
t
Package
No.Name of the Contractor
Total No. of
ComplaintsAccommodating Cost
Kan
dy
Ma
tale
Nu
war
a El
iya
Cost of Accomodating Public Complaints - Sabaragamuwa Province & KalutaraDistrict (up to 31 May 2018)
128
R 01 KD Ebert and Sons Holdings(Pvt) Ltd. 97 3,400,000.00
R 02 KD Ebert and Sons Holdings(Pvt) Ltd. 93 1,400,000.00
R 03 R.R. Construction (Pvt) Ltd. 71 39,160,000.00
KE 01 KD Ebert and Sons Holdings(Pvt) Ltd. 55 5,050,000.00
KE 02 Nawaloka Construction Co. (Pvt) Ltd. 50 5,500,000.00
KE 03 Nawaloka Construction Co. (Pvt) Ltd. 30 3,000,000.00
KL 01 Maga Engineering (Pvt) Ltd 130 13,800,000.00
KL 02Olympus Construction(Pvt.)Ltd JV with Rani
Construction (Pvt.)Ltd 180 13,700,000.00
KL 03Olympus Construction(Pvt.)Ltd JV with Rani
Construction (Pvt.)Ltd 89 5,113,771.00
795 90,123,771.00
Kal
uth
ara
Dis
tric
t
Total
Dis
tric
t
Package
No.Name of the Contractor
Total No. of
ComplaintsAccommodating Cost
Rat
nap
ura
Ke
galle
Summary of Training Programmes / Workshops Conducted by iRoad-PIC 03 up to 31 May 2018
129
Male Female Total
1 Workshop on Environment and Social Consideration 4 63 22 85
2 Workshop on Contract Administration in Construction Supervision 1 68 12 80
3 Workshop on Road Investigation and Pavement Design 1 57 4 61
4 Workshop on Social Safeguard and Environment Progress, ADB Mission 2 106 19 125
5 Workshop on Social Safeguard Concept in iRoad Programme 1 67 14 81
6 Workshop on Calculation of Physical Progress using MS Project 2 39 46 85
7 Identification workshop on Co-operate Social Responsibility Programme 1 43 4 47
8 Awareness workshop on Environment and Social Safeguard 2 98 14 112
9 Awareness workshop for Local Government and Provincial Council Officers 6 447 75 522
10 Awareness Workshop on Road Safety for Drivers of PIU and PIC 2 108 - 108
11Workshop on Interpretation of FIDIC Contract Documents and Overview of
Contract Claims2 81 7 88
12 Workshop on Road Pavement Design 1 67 3 70
13 Workshop on Approval Process of Borrow Materials 1 72 13 85
14 Workshop on Preparation of Quality IPC 1 77 24 101
15Awareness workshop on monitoring environmental & safegurad activities using by
excel spread sheet and GIS package2 46 4 50
16 Workshop on Preparation of As Build Drawings 1 80 3 83
17 Workshop on PBM (Central Province, Kandy,Matale & Nuwara Eliya Districts) 4 213 80 293
34 1732 344 2076
No. Name of the Programme
No. of
Programmes
held
Participants
Total
Submission of Reports by iRoad-PIC 03 up to the end of May 2018
130
Name of the Report Reporting Period Submission Date
Semi-Annual Report on Social and Resettlement Safeguard Consideration
January 2016 to June 2016 04-Nov-16
Semi-Annual Report on Social and Resettlement Safeguard Consideration
July 2016 to December 2016 31-March-17
Annual Environmental Monitoring Report January 2016 to December 2016 28-March-17
Report on Project Performance Management System (PPMS)
Construction Stage 27-March-17
Cost to Completion (Revision - 2) As at 30th June 2017 14-Jul-17
Semi-Annual Report on Social and Resettlement Safeguard Consideration
January 2017 to June 2017 18-Sep-17
Semi-Annual Report on Social and Resettlement Safeguard Consideration
July 2017 to December 2017 12-March-18
Annual Environmental Monitoring Report January 2017 to December 2017 12-March-18
Cost to Completion (Revision - 3) As at 28th February 2018 18-April-18
Cost to Completion
131
• Cost to Completion (Revision 03) for all 18 contracts have been prepared and forwarded to the Employer.
• All contracts are within the accepted contract amount except one contract (R3). (Amount has been exceeded by 5% of the
accepted contract amount and this is mainly due to the improvement of drainages and construction of additional 03 bridges).
Environmental Safeguard activities
• Environmental field inspections and checking, environmental monitoring check lists have been conducted by Contractors, PIU and PIC Environmental and Social Safeguard Specialists, on all active sites.
• Mr Saranga Gajasighe –ADB CSD/SG Specialist conducted a field inspection in KalutaraDistrict on 28 and 30 May 2018 at KL1, KL2 and KL3 Packages.
Progress of Environmental Safeguard Activities (Sabaragamuwa & Central Provinces and Kalutara District)
132
Submission of the EMAP
• EMAPs were submitted and acceptation was given for these all 18 EMAPs by PIC up to the month
Submission of the EMC up to the month
• 267 EMCs at design and preconstruction stage
• 167 EMCs at 25% construction stage
• 112 EMCs at 50% construction stage
• 106 EMCs at 75% construction stage
• 39 EMCs at 100% construction stage
• 30 EMCs at post construction stage
133
Progress of Environmental Safeguard Activities (Sabaragamuwa & Central Provinces and Kalutara District)
Site Safety Arrangement - KE3
52
At Ch: 0+320 Road ID 65 (KahagallaRandeniya
NawagamuwaRoad)
At Ch: 0+090 Road ID 43
(EraminigammanaThambawita
Road)
At Ch: 0+280 Road ID 65 (KahagallaRandeniya
NawagamuwaRoad)
At Ch: 0+320 Road ID 29
(KempitikandaMosque to
KempikandaRoad)
Environmental Impact Mitigation Measures – KA3
Erosion control and embankment protection by turffing and construction of protection wall
Road No 06 – Ch. 2 + 420
Road Name : Mahalakotuwa Meda Ela Road
Chainage : 0+680 km
Activity : Turffing for erosion control
Date of Exposure : 08.05.2018
Road Name : Mahalakotuwa Meda Ela Road
Chainage : 1+960 km
Activity : Turffing for erosion control
Date of Exposure : 28.05.2018
Erosion control by turffing
Environmental Impact Mitigation Measures - MA3
139
Erosion control by turffing
Road No 10A - Chanage 0+550
Environmental Impact Mitigation Measures - R3
• 1,901 trees were removed up to this month in all Packages
• 5,703 trees have to be planted for those removed trees.
• 5,522 trees have alreadyplanted by MA1(109), MA2(50),MA3 (586),KA1(110) KA2(177),KA3(370), NE1(60), NE2(50),NE3(300), R1(160), R2(212),R3(1170), KE1(1027) KE2(993),KE3(76), KL1(60) & KL2(12)
Details of Removal and Planting of Trees in all Contracts up to the end of May 2018
Package Contractor Total Trees Removed
Total Trees Planted
KA1 Sierra Construction (Pvt) Ltd 37 110
KA2 Sierra Construction (Pvt) Ltd 62 177
KA3 Edward and Christie (Pvt) Ltd 209 370
MA1 K D Ebert and Sons Holdings (Pvt) Ltd 23 109
MA2 Edward and Christie (Pvt) Ltd 10 50
MA3 CML-MTD Construction (Pvt) Ltd 100 586
NE1 Sierra Construction (Pvt) Ltd 54 60
NE2 Sierra Construction (Pvt) Ltd None 50
NE3 Sierra Construction (Pvt) Ltd 19 300
R1 K D Ebert and Sons Holdings (Pvt) Ltd 139 160
R2 K D Ebert and Sons Holdings (Pvt) Ltd 63 212
R3 RR Construction (Pvt) Ltd 400 1170
KE1 K D Ebert and Sons Holdings (Pvt) Ltd 240 1027
KE2 Nawaloka Construction (Pvt) Ltd 362 993
KE3 Nawaloka Construction (Pvt) Ltd 64 76
KL1 Maga Construction (Pvt) Ltd 78 60
KL2 Olympus Construction (Pvt) Ltd 10 12
KL3 Olympus Construction (Pvt) Ltd 31 None
Total 1901 5522
❖ Reviewed 03 GRC reports and made corrections. Introduced proper reporting system about GRC.
❖ Monitored Public Complaints/Suggestions/Requests Registers and Registers were maintained at
Contractor’s main offices.
❖ Motivated to maintain Public Complaints/Suggestions/Request boxes and display the publicawareness posters at each and every sites by Contractors.
❖ Five public complaints received directly and have been addressed.
❖ Monitored the public complaints administration in all Six Districts and instructed to the Social and
environment Development Assistants to coordinate with Project Managers to addressed the
public complaints in a short periods.
❖ Participated for three GRC Meetings were held at Kalutara District.
❖ Assist for land donation process at Kalutara District.
Progress of Safeguard Social Consideration(Central and Sabaragamuwa Provinces and Kalutara District)
- Addressing Public Complaints, Suggestions, Grievances & Requests
145
❖ Motivated contractors to conduct Corporate Social Responsibility programmes for the next month.
❖ Monitored CSR programmes conducted by Contractors. They conducted one programme in KalutaraDistrict (KL2 Package).
❖ Collected public opinion from 16 road users about road development in their villages.
❖ Conducted a HIV/AIDS Prevention, Human Trafficking and Health Awareness Programme for communityin Nuwaraeliya District (NE3 Package).
❖ Assistence was provided for ADB Safeguard Specialist to conduct two days field visit at KalutaraDistrict.
- Other Activities
Progress of Safeguard Social consideration(Central and Sabaragamuwa Provinces and Kalutara District)
146
147
Progress of the Safeguard Social Consideration(Central and Sabaragamuwa Provinces and Kalutara District of Western Province)
ADB Filed visit and discussion with ADB, PIU, PIC and Contractors after the field visit on
30 May 2018 at Kalutara District
148
Progress of the Safeguard Social Consideration(Central and Sabaragamuwa Provinces and Kalutara District of Western Province)
A Gender Awareness Training Program was conducted on 16 May 2018 at Ananda
Reception Hall by ADB Gender Specialist together with the Consultant Team
Kegalle District
149
Progress of the Safeguard Social Consideration(Central and Sabaragamuwa Provinces and Kalutara District of Western Province)
GRC Meeting at Paraduwa - Bogaha Junction to Gunagoda Road (ID 67) of KL1 Package
Kalutara District
150
Progress of the Safeguard Social ConsiderationEstablishment of Grievances Redressing Committees (GRCs) in
Divisional Secretariat & Grama Niladhari LevelsP
rov
ince/
Dis
tric
t
Package
No.Name of the Contractor
Total No.
of DSDs
DSD LevelTotal No.
of GNDs
GND Level
EstablishedTo be
EstablishedEstablished
To be
Established
Cen
tral P
rov
ince
KA 01 Sierra Construction (Pvt.) Ltd. 6 6 0 57 57 0
KA 02 Sierra Construction (Pvt.) Ltd. 6 6 0 20 20 0
KA 03 Edward and Christie. 7 7 0 56 56 0
MA 01 KD Ebert and Sons Holdings(Pvt) Ltd. 3 3 0 34 34 0
MA 02 Edward and Christie. 3 3 0 29 29 0
MA 03 CML-MTD Construction limited 5 5 0 19 19 0
NE 01 Sierra Construction (Pvt.) Ltd. 2 2 0 14 14 0
NE 02 Sierra Construction (Pvt.) Ltd. 2 2 0 18 18 0
NE 03 Sierra Construction (Pvt.) Ltd. 2 2 0 15 15 0
Sab
ara
gam
uw
a
Pro
vin
ce
R 01 KD Ebert and Sons Holdings(Pvt) Ltd. 6 6 0 31 31 0
R 02 KD Ebert and Sons Holdings(Pvt) Ltd. 8 8 0 30 30 0
R 03 R.R. Construction (Pvt) Ltd. 6 6 0 30 30 0
KE 01 KD Ebert and Sons Holdings(Pvt) Ltd. 4 4 0 26 23 3
KE 02 Nawaloka Construction Co. (Pvt) Ltd. 3 3 0 38 32 6
KE 03 Nawaloka Construction Co. (Pvt) Ltd. 4 4 0 50 47 3
Kalu
thara
Dis
tric
t
KL 01 Maga Engineering (Pvt) Ltd 7 7 0 32 32 0
KL 02Olympus Construction(Pvt.)Ltd JV with Rani
Construction (Pvt.)Ltd 4 4 0 42 42 0
KL 03Olympus Construction(Pvt.)Ltd JV with Rani
Construction (Pvt.)Ltd 3 3 0 22 22 0
Total 82 82 0 563 551 12
151
ASIAN DEVELOPMENT BANK FUNDED
PROJECT IMPLEMENTATION CONSULTANTS
PIC 02
Progress up to 31.05.2018
INTEGRATED ROAD INVESTMENT PROGRAMME (iROAD)
– NWP & NCP
Overall Physical Progress Summary – iROAD – North Central Province / (up to 31st of May 2018)
Package No.
ContractorAccepted Contract
Amount / (Rs.)No. Of Roads
Roads Length / (km)
No. of Roads;
Civil Works in Progress
Asphalt Completed
/ (km)
BalanceAsphalt to
be Completed
Physical Progress as
at 30th of April 2018 Actual (%)
Physical Progress;Cumulative Status up
to end of May 2018 (%)
Target Actual
AP1 MAGA 1,656,915,760.80 17 85.52 17 58.14 27.38 68.50 84.00 75.50
AP2 MAGA 1,824,178,003.20 12 76.52 12 57.47 19.05 65.39 80.79 71.40
AP3 MAGA 1,492,772,165.28 12 82.48 11 50.39 32.09 62.72 74.98 69.86
AP4 MAGA 1,635,133,956.00 19 89.16 19 72.07 17.09 72.95 81.95 80.74
PO1 MAGA 1,158,532,987.42 18 51.38 18 41.74 9.64 81.62 98.21 84.82
PO2 MAGA 1,483,692,044.52 25 72.53 25 59.44 13.09 74.04 96.04 78.21
PO3TISSA-
AMSK JV1,249,343,460.00 11 48.63 10 39.11 9.52 73.23 87.11 76.91
Project Location Maps – Polonnaruwa District
Package PO1 PO2 PO3 TOTAL
Road Length (km) 51.38 72.53 48.63 172.54
Progress of Road Work Bar Chart in PO1
Note: Earth Work Construction Started for all Roads.Earthwork in progress ABC Completed Asphalt Completed
Serial No DS.Division Road ID Road NameRoad
CatogoryLength (Km)
Progress Up to End of May 20181 km 2 km 3 km 4 km 5 km 6 km
1
Elahera
1 Ihakuluwewa Village Road PS 3.77
2 2 Ganageyaya Village Road PS 3.76
3 3 Athtanakadawala Pokunugala PS 3.29
4 4 Welankattuwa Village Road PS 2.12
5 5 Sarubima- Segala Village Road PS 2.62
6 6 Bakamuna -Damanayaya Village Road PS 2.26
7 7 Sirikanduyaya Track 18 Village Road PS 2.22
8 8 Orubendisiyambalawa Village Road PS 1.88
9 9 Bisokotuwa-Konduruwawa PS 1.91
10 10 Yaya 32 Temple - 33 Bisokotuwa Junction PS 3.37
11
Thamankaduwa
11Athmalpitiya Junction -Laxauyana Siyabalagaswewa Junction
PRDA 4.70
12 12 Palugasdamana Senanayake Road PS 1.21
13 13 Parakramasamuthra- Kalahagala Village Road PRDA 5.23
14 14 Kadawalawewa Village Road PS 1.75
15 18 DI Channel- Vijawahapura Village Road PRDA 4.45
16 21Parakramasamudraya- Ambanganga Village Road
PS 3.14
17 22Parakramasamudraya- Dakunu Ela Village Road
PS 2.06
18 20 Onegama Main Road-Galkoriya Village Road PS 1.65
Physical Progress of Plan Work in PO1
Mo
nth
s
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Fe
b-1
7
Ma
r-1
7
Ap
r-1
7
Ma
y-1
7
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-1
7
De
c-1
7
Jan
-18
Fe
b-1
8
Ma
r-1
8
Ap
r-1
8
Ma
y-1
8
Jun
-18
Jul-
18
Original Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
7%
0.1
7%
0.5
8%
2.7
0%
5.7
7%
9.2
9%
15
.96
%
19
.67
%
31
.28
%
37
.07
%
44
.08
%
52
.60
%
63
.57
%
73
.61
%
85
.45
%
89
.78
%
96
.49
%
98
.02
%
99
.21
%
10
0.0
0%
Revised Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.1
2%
0.3
0%
0.9
8%
3.2
2%
6.4
8%
10
.14
%
16
.70
%
20
.54
%
32
.06
%
37
.88
%
45
.12
%
53
.62
%
67
.42
%
77
.30
%
85
.72
%
90
.02
%
96
.61
%
98
.21
%
99
.37
%
10
0.0
0%
Actual Progress
Monthly (%) 0.0
0%
0.0
0%
0.0
0%
0.0
1%
0.2
8%
0.6
1%
2.2
0%
4.2
0%
7.4
4%
10
.30
%
16
.20
%
20
.45
%
29
.50
%
34
.13
%
39
.53
%
46
.33
%
60
.34
%
65
.69
%
72
.46
%
76
.49
%
81
.62
%
84
.82
%
Delay Progress (%)
0.0
0%
0.0
0%
0.0
0%
0.0
1%
0.1
6%
0.3
1%
1.2
2%
0.9
8%
0.9
6%
0.1
6%
-0.5
0%
-0.0
9%
-2.5
6%
-3.7
5%
-5.5
9%
-7.2
9%
-7.0
8%
-11
.61
%
-13
.26
%
-13
.53
%
-14
.99
%
-13
.39
%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Au
g-1
6
Se
p-1
6
Oct
-16
No
v-1
6
Dec
-16
Jan-
17
Feb
-17
Mar
-17
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Se
p-1
7
Oct
-17
No
v-1
7
Dec
-17
Jan-
18
Feb
-18
Mar
-18
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Original Planned Progress Monthly (%) Revised Planned Progress Monthly (%) Actual Progress Monthly (%)
PO1 Total (Up to May - 18)Description Up to Dec - 17 Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment 38.01 1.55 2.80 1.77 1.76 2.91 48.80
Sub base 36.25 2.11 2.70 1.49 2.49 0.82 45.86
A.B.C 33.55 4.31 2.00 0.32 3.22 0.23 43.63
Prime 31.20 4.46 3.10 1.13 1.85 1.51 43.25
Asphalt(Total Length 51.38 km)
30.86 3.80 1.85 3.13 0.90 1.20 41.74
0.00
2.00
4.00
6.00
Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment Sub base A.B.C Prime Asphalt
Physical Progress –PO1
Progress
Cumulative Status as at 30th
April 2018Cumulative Status as at 31st May
2018
Target (%) Actual (%) Target (%) Actual (%)
Physical 96.61% 81.62% 98.21% 84.82%
Payments Certified –PO1
Description Certified Amount (LKR)
Accepted Contract Amount 1,158,532,987.42
Up to Cumulative Certified Amount 641,356,325.74
Contract PO1 - Progress Photographs
Before Construction
Before Construction
After Construction at Road ID 02 3+100 km
ABC Construction at Road ID 040+850 km
Progress of Road Work Bar Chart in PO2
Note: Earth Work Construction Started for all Roads.Earthwork in progress ABC Completed Asphalt Completed
Serial No
DS.DivisionRoad
IDRoad Name
Road Catogory
Length (Km)
Progress Up to End of May 20181 km 2 km 3 km 4 km 5 km 6 km 7 km 8 km
1
Lankapura
24 Hingurakgoda- 7th Mile's Post -Gallamuna Hingurukdamana PRDA 4.12
2 25 Weerapura 317-Karathakade Junction PRDA 3.98
3 27 BOP 317- Dalpalama PRDA 1.29
4 28 BOP 316- Karuwalagas Junciton -Chandanapokuna PRDA 3.04
5 29 Patunagama Junction -Damwelmangada- Buthayaya PS 3.48
6 31 Kubukkanaruwa- 127 Bawdarthgama PS 1.50
7 72 Deberella Sudupalama-Gallamuna PS 4.60
8
Madirigiriya
33 Track 12 Bridge -Nagarapura-Weligampura PS 7.06
9 34 Yuthaganawa -Irrigation Junction- Dinisuru Junction PRDA 3.04
10 35 Kusumpokuna- Pimpura PRDA 3.51
11 36 Pimpura Pansalgodall Main Road- Sansugama 21 Division PRDA 1.31
12 37 Meegaswewa- Wadigawewa PS 3.08
13 40 Medirigiriya Town Internal Road PS 1.88
14 41 Jayathugama Junction Meegollawa School PS 3.20
15 42 Medirigiriya Water Tank- Mr. Vijayadasa's House PS 2.23
16 44 Medirigiriya Kalagedi Palama- Bisobandaragama School PS 2.55
17 73 Diulankadawela Aliwankuwa Junction PS 3.13
18
Hingurakgoda
45 Minneriya Central Collage Road PS 3.05
19 46 Hathamuna Bridge - Nugagahadamana Road PS 3.71
20 47 Dora 2 Junction-Paluwewa PS 1.81
21 48 Girithale Middle Road PS 1.49
22 49 Hingurakgoda Airport-Vidyaloka School Road PRDA 1.41
23 51 Batukotuwa Middle Road PS 1.13
24 52 Minneriya Samagipura PS 2.37
25 55 Hinguraka 4th Miles Post-Chandanapokuna Aliwanguwa PS 4.56
Physical Progress of Plan Work in PO2
Mo
nth
s
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Fe
b-1
7
Ma
r-1
7
Ap
r-1
7
Ma
y-1
7
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-1
7
De
c-1
7
Jan
-18
Fe
b-1
8
Ma
r-1
8
Ap
r-1
8
Ma
y-1
8
Jun
-18
Jul-
18
Original Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.1
4%
0.5
2%
1.9
0%
4.5
2%
8.2
5%
13
.41
%
19
.29
%
25
.78
%
32
.45
%
40
.00
%
47
.77
%
54
.57
%
60
.48
%
66
.39
%
73
.91
%
82
.25
%
88
.80
%
94
.84
%
97
.34
%
10
0.0
0%
Revised Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.1
1%
0.4
4%
2.0
0%
4.8
4%
8.8
0%
14
.43
%
20
.56
%
27
.42
%
34
.24
%
42
.06
%
49
.78
%
56
.56
%
62
.47
%
68
.38
%
75
.84
%
84
.17
%
90
.51
%
96
.04
%
98
.04
%
10
0.0
0%
Actual Progress
Monthly (%) 0.0
0%
0.0
0%
0.0
0%
0.0
5%
0.3
5%
1.1
0%
3.1
2%
4.9
0%
10
.10
%
16
.50
%
22
.00
%
26
.90
%
32
.50
%
38
.17
%
41
.49
%
44
.71
%
48
.54
%
54
.10
%
63
.03
%
70
.51
%
74
.04
%
78
.21
%
Delay Progress (%)
0.0
0%
0.0
0%
0.0
0%
0.0
5%
0.2
4%
0.6
6%
1.1
2%
0.0
6%
1.3
0%
2.0
7%
1.4
4%
-0.5
2%
-1.7
4%
-3.8
9%
-8.2
9%
-11
.85
%
-13
.93
%
-14
.28
%
-12
.81
%
-13
.66
%
-16
.47
%
-17
.83
%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Au
g-1
6
Se
p-1
6
Oct
-16
No
v-1
6
Dec
-16
Jan-
17
Feb
-17
Mar
-17
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Se
p-1
7
Oct
-17
No
v-1
7
Dec
-17
Jan-
18
Feb
-18
Mar
-18
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Original Planned Progress Monthly (%) Revised Planned Progress Monthly (%) Actual Progress Monthly (%)
PO2 Total (Up to May - 18)Description Up to Dec - 17 Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment 40.54 3.40 2.65 7.13 4.78 2.83 61.33
Sub base 42.90 4.17 5.17 3.95 2.95 4.39 63.53
A.B.C 41.84 5.23 5.17 2.65 2.87 3.55 61.31
Prime 40.59 6.14 2.62 4.27 3.98 3.40 60.99
Asphalt(Total Length 72.53 km)
39.11 5.53 3.11 4.02 4.59 3.08 59.44
0.00
2.00
4.00
6.00
8.00
Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment Sub base A.B.C Prime Asphalt
Physical Progress –PO2
Progress
Cumulative Status as at 30th
April 2018Cumulative Status as at 31st May
2018
Target (%) Actual (%) Target (%) Actual (%)
Physical 90.51% 74.04% 96.04% 78.21%
Payments Certified –PO2
Description Certified Amount (LKR)
Accepted Contract Amount 1,483,692,044.52
Up to Cumulative Certified Amount 786,880,264.98
Contract PO2 - Progress Photographs
Before Construction Asphalt Construction at Road ID 723+660 km
Before Construction Asphalt Construction at Road ID 73 0+400 km
Progress of Road Work Bar Chart in PO3
Earthwork in progress ABC Completed Asphalt Completed
Note: Road ID No. 71 Earth Work Construction Still Has Not
Started.
Serial No
DS.DivisionRoad
IDRoad Name
Road Catogory
Length (Km)
Progress Up to End of May 2018
1 km 2 km 3 km 4 km 5 km 6 km 7 km 8 km 9 km 10 km 11 km 12 km
1
Welikanda
57 Welikanda-Singhapura Road PRDA 12.00
2 58 Athugala -Katuwanwila PRDA 6.00
3 59 Ginidamana-Nelumwewa PRDA 2.05
4
Dimbulagala
61Mahadamanawewa Village
roadPRDA
5 62Dimbulgala Junction-Bogaswewa Village Road
PRDA 6.50
6 64 Manmpitiya Hospital Road PRDA 1.25
7 65 2nd Mile's Post-Seelapura PS 1.50
8 66Siripura Nuwaragala Village Road
PRDA 9.63
9 67Aluthoya Junction - Village Road
PS 2.00
10 68Dimbulagala Junction-Soruwila Village
PS 1.75
Physical Progress of Plan Work in PO3
Mo
nth
s
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Fe
b-1
7
Ma
r-1
7
Ap
r-1
7
Ma
y-1
7
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-1
7
De
c-1
7
Jan
-18
Fe
b-1
8
Ma
r-1
8
Ap
r-1
8
Ma
y-1
8
Jun
-18
Jul-
18
Planned Progress
Monthly (%) 0.0
0%
0.0
0%
0.0
0%
0.1
5%
0.6
3%
2.7
1%
5.6
8%
8.9
9%
12
.50
%
16
.03
%
20
.45
%
25
.31
%
30
.73
%
36
.03
%
41
.83
%
48
.22
%
55
.08
%
61
.93
%
68
.06
%
73
.48
%
79
.83
%
87
.11
%
95
.20
%
10
0.0
0%
Actual Progress
Monthly (%) 0.0
0%
0.0
0%
0.0
7%
0.2
5%
0.6
2%
1.7
0%
4.1
0%
8.9
8%
11
.70
%
16
.39
%
20
.60
%
25
.69
%
32
.75
%
39
.06
%
44
.17
%
49
.02
%
54
.19
%
60
.94
%
65
.60
%
71
.25
%
73
.23
%
76
.91
%
Delay Progress (%)
0.0
0%
0.0
0%
0.0
7%
0.1
0%
-0.0
1%
-1.0
1%
-1.5
8%
-0.0
1%
-0.8
0%
0.3
6%
0.1
5%
0.3
8%
2.0
2%
3.0
3%
2.3
4%
0.8
0%
-0.8
9%
-0.9
9%
-2.4
6%
-2.2
3%
-6.6
0%
-10
.20
%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Au
g-1
6
Sep-
16
Oct
-16
No
v-1
6
Dec
-16
Jan
-17
Feb
-17
Mar
-17
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Sep-
17
Oct
-17
No
v-17
Dec
-17
Jan
-18
Feb
-18
Mar
-18
Ap
r-1
8
Ma
y-1
8
Jun
-18
Jul-
18
Planned Progress Monthly (%) Actual Progress Monthly (%)
PO3 Total (Up to May - 18)Description Up to Dec - 17 Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment 33.60 2.50 2.10 1.90 0.45 1.40 41.95
Sub base 33.50 2.60 2.10 1.90 0.15 1.40 41.65
A.B.C 30.60 4.60 1.00 2.00 1.40 1.35 40.95
Prime 29.80 2.50 2.30 2.30 0.75 2.74 40.39
Asphalt(Total Length 48.63 km)
28.20 2.80 2.00 3.55 0.76 1.80 39.11
0.00
2.00
4.00
6.00
Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment Sub base A.B.C Prime Asphalt
Physical Progress –PO3
Progress
Cumulative Status as at 30th
April 2018Cumulative Status as at 31st May
2018
Target (%) Actual (%) Target (%) Actual (%)
Physical 79.83% 73.23% 87.11% 76.91%
Payments Certified –PO3
Description Certified Amount (LKR)
Accepted Contract Amount 1,249,343,460.00
Up to Cumulative Certified Amount 789,072,024.80
Contract PO3 - Progress Photographs
Before Construction Roadway Excavation at Road ID 61 2+060 km
During Construction Priming Construction at Road ID 67 1+020 km
Contract PO3 - Progress Photographs
Before Construction Edge Widening Construction at Road ID 67 0+200 km
Road Work Progress – iROAD - Polonnaruwa District
Package No.
ContractorNo. of Roads
Total Road Length (km)
No. of Roads Civil Works in Progress
Road Length Civil Works in Progress (km)
PO1 MAGA 18 51.38 18 49.43
PO2 MAGA 25 72.53 25 68.37
PO3 TISSA-AMSK JV 11 48.63 10 43.45
Total 54 172.54 53 161.25
51.38
72.53
48.63
49.43
68.37
43.45
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00
PO1
PO2
PO3
Road Length (km)
Co
ntr
act
Pa
cka
ge
Road Length Civil Works in Progress (km)
Total Road Length (km)
Progress Summary of Culverts & Bridges - iROAD-Polonnaruwa District
DistrictPackage
No.Contractor
Total No. of Culvert
No. of Culvert No. of Culvert
New / Reconstruction / Widening
Completed / In
progress
Cleaning & Repair
Completed / In progress
Polonnaruwa
PO1 MAGA 208 104 102 105 1
PO2 MAGA 290 164 136 142 23
PO3 TISSA-AMSK JV 95 11 5 84 17
Total 593 279 243 331 41
Overall Financial Status - iROAD-Polonnaruwa District
Package No. ContractorAccepted Contract Amount
(LKR)
Total Certified Amount to Date (LKR) (Including Advance
Payment)
PO1 MAGA 1,158,532,987.42 641,356,325.74
PO2 MAGA 1,483,692,044.52 786,880,264.98
PO3 TISSA-AMSK JV 1,249,343,460.00 789,072,024.80
Total 3,891,568,491.94 2,217,308,615.52
Status of GRC Committee Formation in Polonnaruwa Districts – NCP
Contract
No.Contractor
No. of
RoadsNo. of Divisions
No. of GRC (Level
3 - DS) formed
No. of GRC (Level 2 -
GN) formed
PO1 MAGA 18 2 2 18
PO2 MAGA 25 3 3 25
PO3 TISSA-AMSK 11 2 2 11
TOTAL 54 7 7 54
List of Utilities - iROAD-Polonnaruwa District
Package No.
No. of Roads
No. of Roads Surveyed for
Utility Shifting
Utilities to be Shifted
Electricity Pole / (Nos.) Telecom Pole / (Nos.) Water Line / (m)
Identified Progress Identified Progress Identified Progress
PO1 18 18 15 11 43 43 2345 600
PO2 25 25 2 - 18 - 220 120
PO3 11 11 - - - - - -
Summary of Public Complaints - iROAD-Polonnaruwa District
DistrictPackage
No.
Public Complaints Received
TotalNo.
Attended
No. Completely
Settled
Solutions in Progress
No. UnattendedNo. of
RequestNo. of
SuggestionNo. of
Complaints
No. of Crack related issues
Po
lon
nar
uw
a PO1 45 0 27 3 75 75 73 2 0
PO2 34 0 18 7 59 59 52 7 0
PO3 26 5 22 0 53 53 49 4 0
Total 105 5 67 10 187 187 174 13 0
Project Location Maps –Anuradhapura District
Package AP1 AP2 AP3 AP4 TOTAL
Road Length (km) 85.52 76.52 82.48 89.16 333.68
Progress of Road Work Bar Chart in AP1
Earthwork in progress ABC Completed Asphalt Completed
Note: Earth Work Construction Started for all Roads.
Serial No
DS. DivisionRoad
IDRoad Name
Road Category
Length (Km)
Progress Up to End of May 20181 km 2 km 3 km 4 km 5 km 6 km 7 km 8 km 9 km 10 km 11 km 12 km 13 km
1
Thalawa
1 Thalawa -Jayagaga 149 Hagurankethagama PRDA 10.24
2 2 Eppawala Police Junction Jaya Ganga Rotawewa PRDA 2.92
3 3 15 Kanuwa - Kiriamunukole -Mawathawewa PS 2.72
4
Nochchiyagama
10 Mahawelithenna Ralapanawa Janapadaya PS 5.27
5 12 Pahalamaragahawewa Katupathwewa PS 3.28
6
Wilachchiya
37Maningamuwa Junction Ihala Oyamaduwa Nawodagama Road
PRDA 13.19
7 36Yaya4 Junction Bogas Handiya Kiralapetiyawa Halambewewa Road
PRDA 11.21
8
Nuwaragampalatha Central
38 4 Ela Junction Mankadawala Jaffna Road PS 4.49
9 39 4 Ela Junction Parasangaswewa Hospital Road PS 4.47
10 40 Saliya Mawatha Thannayakulama Road PS 2.33
11
Nuwaragampalatha East
41 Sucharithagama Yahalegam Temple Road PS 4.50
12 43CEB Deport Pahala Keerikkulama -Keerikkulama Nochchaduwa Road
PS 3.67
13 45 Abyepura Housingh Sheme to Tammennapura PS 3.20
14 46 Nagasena Mawatha PRDA 1.94
15
Nachchaduwa
61 9 Ela Janahitha Junction 7 Ela Thuruwila PRDA 4.76
16 63 Rathmale Nachchaduwa PRDA 2.84
17 65 Nelubuwa Bidunkadawala PS 4.37
Physical Progress of Plan Work in AP1
Mo
nth
s
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Fe
b-1
7
Ma
r-1
7
Ap
r-1
7
Ma
y-1
7
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-1
7
De
c-1
7
Jan
-18
Fe
b-1
8
Ma
r-1
8
Ap
r-1
8
Ma
y-1
8
Jun
-18
Jul-
18
Original Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
1.0
0%
3.0
0%
6.0
0%
12
.00
%
20
.00
%
24
.00
%
28
.00
%
33
.00
%
40
.00
%
47
.00
%
56
.00
%
61
.00
%
66
.00
%
70
.00
%
78
.00
%
85
.00
%
90
.00
%
93
.00
%
97
.00
%
99
.00
%
10
0.0
0%
Revised Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
0.0
0%
1.0
0%
2.0
0%
3.0
0%
4.0
0%
5.0
0%
7.0
0%
9.0
0%
12
.00
%
16
.00
%
21
.00
%
26
.00
%
33
.00
%
40
.70
%
49
.00
%
57
.00
%
65
.00
%
73
.00
%
84
.00
%
94
.00
%
10
0.0
0%
Actual Progress
Monthly (%) 0.0
0%
0.0
0%
0.0
0%
0.5
0%
1.0
0%
1.5
0%
3.0
0%
4.0
0%
5.0
0%
7.0
0%
9.6
0%
12
.50
%
16
.20
%
21
.20
%
26
.50
%
32
.50
%
40
.90
%
50
.40
%
57
.90
%
64
.90
%
68
.50
%
75
.50
%
Delay Progress (%)
0.0
0%
0.0
0%
0.0
0%
0.5
0%
0.0
0%
-0.5
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.6
0%
0.5
0%
0.2
0%
0.2
0%
0.5
0%
-0.5
0%
0.2
0%
1.4
0%
0.9
0%
-0.1
0%
-4.5
0%
-8.5
0%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Au
g-1
6
Se
p-1
6
Oct
-16
No
v-1
6
Dec
-16
Jan-
17
Feb
-17
Mar
-17
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Se
p-1
7
Oct
-17
No
v-1
7
Dec
-17
Jan-
18
Feb
-18
Mar
-18
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Original Planned Progress Monthly (%) Revised Planned Progress Monthly (%) Actual Progress Monthly (%)
AP1Total (Up to
May - 18)Description Up to Dec - 17 Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment 39.00 5.90 7.07 7.22 3.31 9.00 71.50
Sub base 30.10 5.90 7.30 7.61 6.10 9.00 66.01
A.B.C 31.00 10.20 5.74 7.01 4.25 5.72 63.92
Prime 28.97 8.43 6.11 7.37 2.80 6.52 60.20
Asphalt(Total Length 85.52 km)
28.00 8.30 4.95 7.18 3.08 6.63 58.14
0.00
2.00
4.00
6.00
8.00
10.00
12.00
Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment Sub base A.B.C Prime Asphalt
Physical Progress –AP1
Progress
Cumulative Status as at 30th
April 2018Cumulative Status as at 31st May
2018
Target (%) Actual (%) Target (%) Actual (%)
Physical 73.00% 68.50% 84.00% 75.50%
Payments Certified –AP1
Description Certified Amount (LKR)
Accepted Contract Amount 1,656,915,760.80
Up to Cumulative Certified Amount 913,434,612.34
Contract AP1 - Progress Photographs
Before Construction ABC Laying at Road ID 430+900 km
ABC Compaction at Road ID 37 9+820 km
Shoulder Construction at Road ID 379+000 km
Contract AP1 - Progress Photographs
Edge Widening at Road ID 121+440 km
Turfing at Road ID 631+800 km
Progress of Road Work Bar Chart in AP2
Earthwork in progress ABC Completed Asphalt Completed
Note: Earth Work Construction Started for all Roads.
Serial No
DS.DivisionRoad
IDRoad Name
Road Catogory
Length (Km)
Progress Up to End of May 2018
1 km 2 km 3 km 4 km 5 km 6 km 7 km 8 km 9 km 10 km 11 km 12 km 13 km 14 km 15 km 16 km 17 km
1
Kakirawa
19Elagamuwa Junction canal Road, Horapola new mosque Road
PS 3.27
2 23 Dabawatana Road PS 4.24
3
Palagala
26 Balaluwewa Karawilagala Road PS 3.83
4 27Kudawatagala Dambuluhalmillewa Road
PRDA 9.35
5 28Ulpothagama Junction Morotthegama Road
PS 4.78
6 Galnewa 66Thammennawawa Junction Kumbukwewa Siyabalawewa Hunupalagama Road
PRDA 10.98
7
Ipalogama
67 Kalawewa Aukana Road RDA 4.60
8 686 Ela Walpaluwa to Kagama 2 Ela Road
PS 3.75
9 69Mahailuppallama Farm Akkara 100 to Senapura Katiyawa Road
PS 4.94
10
Rajanganaya
47Thambuththegama Rajanganaya Road
PRDA 16.86
11 48Ayurwedic Hospital Nawagattegama Road
PRDA 4.02
12Thambuthega
ma49 Eriyagama Paindakulama Road PRDA 6.20
Physical Progress of Plan Work in AP2
Mo
nth
s
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Fe
b-1
7
Ma
r-1
7
Ap
r-1
7
Ma
y-1
7
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-1
7
De
c-1
7
Jan
-18
Fe
b-1
8
Ma
r-1
8
Ap
r-1
8
Ma
y-1
8
Jun
-18
Jul-
18
Original Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
3%
0.5
0%
1.3
1%
2.8
5%
6.6
1%
9.6
5%
11
.05
%
12
.50
%
16
.64
%
22
.95
%
28
.55
%
35
.89
%
45
.52
%
53
.69
%
64
.69
%
73
.29
%
79
.92
%
85
.61
%
88
.32
%
92
.01
%
96
.81
%
10
0.0
0%
Revised Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
0.1
7%
0.8
4%
2.3
4%
3.9
2%
5.7
3%
8.6
0%
10
.53
%
13
.59
%
18
.27
%
24
.70
%
29
.89
%
33
.25
%
37
.09
%
40
.04
%
46
.25
%
53
.09
%
60
.79
%
69
.83
%
80
.79
%
90
.29
%
10
0.0
0%
Actual Progress
Monthly (%) 0.0
0%
0.0
0%
0.0
0%
0.1
7%
0.8
4%
2.3
2%
3.2
0%
5.6
8%
7.3
0%
10
.45
%
13
.48
%
18
.13
%
24
.50
%
31
.15
%
33
.00
%
37
.00
%
41
.01
%
45
.74
%
51
.68
%
57
.72
%
65
.39
%
71
.40
%
Delay Progress (%)
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
-0.0
2%
-0.7
2%
-0.0
5%
-1.3
0%
-0.0
8%
-0.1
1%
-0.1
4%
-0.2
0%
1.2
6%
-0.2
5%
-0.0
9%
0.9
7%
-0.5
1%
-1.4
1%
-3.0
7%
-4.4
4%
-9.3
9%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Au
g-1
6
Se
p-1
6
Oct
-16
No
v-1
6
Dec
-16
Jan-
17
Feb
-17
Mar
-17
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Se
p-1
7
Oct
-17
No
v-1
7
De
c-1
7
Jan-
18
Feb
-18
Mar
-18
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Original Planned Progress Monthly (%) Revised Planned Progress Monthly (%) Actual Progress Monthly (%)
AP2Total (Up to
May - 18)Description Up to Dec -17 Jan-18 Feb-18 Mar-18 Apr - 18 May - 18
Embankment 42.96 3.70 3.33 6.19 3.72 3.25 63.15
Sub base 35.47 6.96 4.44 7.80 2.06 5.30 62.03
A.B.C 33.87 4.16 5.90 7.59 4.16 4.10 59.78
Prime 32.87 4.80 5.75 7.19 4.06 4.90 59.57
Asphalt(Total Length 76.52 km)
32.22 5.05 6.15 4.39 6.26 3.40 57.47
0.00
2.00
4.00
6.00
8.00
10.00
Jan-18 Feb-18 Mar-18 Apr - 18 May - 18
Embankment Sub base A.B.C Prime Asphalt
Physical Progress –AP2
Progress
Cumulative Status as at 30th
April 2018Cumulative Status as at 31st May
2018
Target (%) Actual (%) Target (%) Actual (%)
Physical 69.83% 65.39% 80.79% 71.40%
Payments Certified –AP2
Description Certified Amount (LKR)
Accepted Contract Amount 1,824,178,003.20
Up to Cumulative Certified Amount 999,346,815.36
Contract AP2 - Progress Photographs
Before Construction Asphalt Completed at Road ID 472+300 km
Before Construction Asphalt Completed at Road ID 280+000 km
Progress of Road Work Bar Chart in AP3
Earthwork in progress ABC Completed Asphalt Completed
Note: Road ID No. 25 Earth Work Construction Still Has Not Started.
Serial No
DS.DivisionRoad
IDRoad Name
Road Catogory
Length (Km)
Progress Up to End of May 2018
1 km 2 km 3 km 4 km 5 km 6 km 7 km 8 km 9 km 10 km 11 km 12 km 13 km 14 km
1
Mihinthale
5 Matale Junction Samagipura Road PS 2.64
2 6Kurundankulama School via Kalaththewa Matale Junction Road
PS 2.83
3 7 Mahakanadarawa Left Bank Elakanda Road PRDA 5.40
4 8 Kannattiya Ashokapura Road PS 2.76
5 9 Welankulama Junction Alappamkulama Road PRDA 7.76
6 30 Galkulama Sivalakulama Yakalla Road PRDA 7.82
7 70Katukeliyawa Ihala Halmillewa Sivalakulama Road
PRDA 5.38
8 Thirappane 60 A-9 Road Labunoruwa Muriyakadawala Road PRDA 18.51
9
Palugaswewa
24 Palugaswewa Mahakekirawa Road PRDA 8.88
10 71 Yakalla Palugollagama Upuldeniya Road PRDA 1.73
11Galenbidunuw
ewa29 Yakalla Palugollagama Upuldeniya Road PRDA 12.15
Physical Progress of Plan Work in AP3
Mo
nth
s
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Fe
b-1
7
Ma
r-1
7
Ap
r-1
7
Ma
y-1
7
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-1
7
De
c-1
7
Jan
-18
Fe
b-1
8
Ma
r-1
8
Ap
r-1
8
Ma
y-1
8
Jun
-18
Jul-
18
Original Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
1.7
5%
4.2
6%
8.4
0%
12
.45
%
17
.54
%
22
.86
%
28
.15
%
33
.48
%
37
.83
%
45
.19
%
50
.21
%
56
.10
%
62
.09
%
67
.82
%
73
.52
%
79
.08
%
84
.71
%
90
.77
%
95
.77
%
98
.85
%
10
0.0
0%
Revised Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
0.0
4%
1.1
0%
1.9
4%
4.0
7%
4.7
0%
5.2
4%
8.5
5%
11
.23
%
13
.50
%
17
.66
%
23
.20
%
28
.25
%
32
.30
%
37
.38
%
43
.37
%
49
.65
%
56
.18
%
62
.10
%
74
.98
%
88
.14
%
10
0.0
0%
Actual Progress
Monthly (%) 0.0
0%
0.0
0%
0.0
0%
0.0
4%
1.1
0%
1.9
4%
4.0
7%
4.7
0%
5.2
4%
8.5
5%
11
.23
%
13
.50
%
17
.66
%
23
.20
%
28
.25
%
32
.30
%
37
.38
%
42
.37
%
48
.72
%
57
.58
%
62
.72
%
69
.86
%
Delay Progress (%)
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
-1.0
0%
-0.9
3%
1.4
0%
0.6
2%
-5.1
2%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
Dec
-16
Jan-
17
Feb
-17
Mar
-17
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Se
p-1
7
Oct
-17
No
v-1
7
Dec
-17
Jan-
18
Feb
-18
Mar
-18
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Original Planned Progress Monthly (%) Revised Planned Progress Monthly (%) Actual Progress Monthly (%)
AP3Total (Up to
May - 18)Description Up to Dec -17 Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment 31.33 3.61 6.73 6.83 3.99 4.16 56.65
Sub base 20.02 5.90 5.99 6.44 2.31 4.30 44.96
A.B.C 27.92 4.31 5.40 6.85 3.2 4.21 51.89
Prime 26.92 4.11 4.36 5.76 5.01 4.22 50.38
Asphalt(Total Length 82.48 km)
26.72 3.38 4.65 5.11 5.41 5.12 50.39
0.00
2.00
4.00
6.00
8.00
Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment Sub base A.B.C Prime Asphalt
Physical Progress –AP3
Progress
Cumulative Status as at 30th
April 2018Cumulative Status as at 31st May
2018
Target (%) Actual (%) Target (%) Actual (%)
Physical 62.10% 62.72% 74.98% 69.86%
Payments Certified –AP3
Description Certified Amount (LKR)
Accepted Contract Amount 1,492,772,165.28
Up to Cumulative Certified Amount 818,988,659.42
Contract AP3 - Progress Photographs
Before Construction ABC Laying at Road ID 298+300 km
Before Construction Embankment Filling Construction at Road ID 6010+100 km
Progress of Road Work Bar Chart in AP4
Earthwork in progress ABC Completed Asphalt Completed
Note: Earth Work Construction Started for all Roads.
Serial No
DS.DivisionRoad
IDRoad Name
Road Catogory
Length (Km)
Progress Up to End of May 20181 km 2 km 3 km 4 km 5 km 6 km 7 km 8 km 9 km 10 km 11 km 12 km 13 km
1
Horowpathana
33 ElapathwewaRitigahawewa Road PS 3.81
2 34Kapugollewa Maradanmaduwa Wagollewa Road
PRDA 4.17
3 35 Nanumillewa Junction to Vilewewa Road PS 2.73
4
Padaviya
50 40 kolaniya bus halt Nawagammanaya Road PS 2.85
5 51 Thelmola Junction Bilankulama Road PS 2.21
6 52 Mailagashandiya daluggala jayanthi Road PS 3.49
7 53 Ruwanpura School Road PS 1.05
8 55 Kobbekaduwa Road PS 1.91
9 56 4th Post Thonigala Bridge Road PS 1.60
10
Kebithigollewa
57 Kanugahawewa Herathhalmillewa Road PS 8.94
11 59 Halmillawatiya Yakawewa Road PS 3.53
12
Medawachchiya
16A9 Karapikkada Kurukkandegama Kebithigollewa
PRDA 6.05
13 17 Puhudiula Junction to Galkadawala Road PRDA 3.80
14 18Kirigalawewa Unagaswewa Moragoda School Road
PRDA 4.94
15Kahatagasdigili
ya
31 Kahatagasdigiliya Kainattama Road PRDA 12.80
16 32Rathmalgahawewa Road Kurukkuragama Junction to Hettikattiya Road
PS 7.00
17
Rabewa
15 Pihibiyagollewa 9th Post Ambagaswewa Road PRDA 5.88
18 13 Mahakandarawa Walioya Road PRDA 4.01
19 14 Ihalagama Junction Muslim Diulwewa PRDA 8.33
Physical Progress of Plan Work in AP4
Mo
nth
s
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Fe
b-1
7
Ma
r-1
7
Ap
r-1
7
Ma
y-1
7
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-1
7
De
c-1
7
Jan
-18
Fe
b-1
8
Ma
r-1
8
Ap
r-1
8
Ma
y-1
8
Jun
-18
Jul-
18
Original Planned
Progress Monthly
(%) 0.0
3%
0.0
6%
0.1
1%
0.6
9%
2.1
2%
4.7
8%
7.7
3%
13
.86
%
17
.05
%
23
.50
%
28
.14
%
34
.40
%
40
.03
%
45
.60
%
51
.07
%
57
.81
%
64
.10
%
69
.46
%
75
.48
%
80
.48
%
84
.90
%
90
.91
%
96
.52
%
10
0.0
0%
Revised Planned
Progress Monthly
(%) 0.0
1%
0.0
2%
0.0
5%
0.4
2%
1.3
6%
2.8
4%
5.6
5%
8.5
3%
10
.28
%
13
.60
%
18
.15
%
20
.70
%
25
.31
%
30
.20
%
34
.30
%
38
.30
%
42
.45
%
48
.78
%
56
.95
%
65
.60
%
72
.19
%
81
.95
%
91
.74
%
10
0.0
0%
Actual Progress
Monthly (%) 0.0
1%
0.0
2%
0.0
5%
0.4
2%
1.3
6%
2.8
4%
5.6
5%
8.5
3%
10
.28
%
13
.60
%
18
.15
%
20
.70
%
25
.31
%
30
.20
%
34
.30
%
38
.50
%
44
.38
%
51
.12
%
57
.72
%
66
.95
%
72
.95
%
80
.74
%
Delay Progress (%)
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.2
0%
1.9
3%
2.3
4%
0.7
7%
1.3
5%
0.7
6%
-1.2
1%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
Dec
-16
Jan-
17
Feb
-17
Mar
-17
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Se
p-1
7
Oct
-17
No
v-1
7
Dec
-17
Jan-
18
Feb
-18
Mar
-18
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Original Planned Progress Monthly (%) Revised Planned Progress Monthly (%) Actual Progress Monthly (%)
AP4 Total (Up to May - 18)Description Up to Dec -17 Jan-18 Feb-18 Mar-18 Apr - 18 May - 18
Embankment 41.86 6.93 8.57 7.92 4.22 6.08 75.58
Sub base 23.50 5.07 8.61 8.01 3.70 5.55 54.44
A.B.C 45.48 4.40 5.67 10.08 4.59 7.48 77.70
Prime 42.74 5.50 4.90 9.01 6.35 6.27 74.77
Asphalt(Total Length 89.16 km)
36.00 7.74 4.46 9.47 6.21 8.19 72.07
0.00
2.00
4.00
6.00
8.00
10.00
12.00
Jan-18 Feb-18 Mar-18 Apr - 18 May - 18
Embankment Sub base A.B.C Prime Asphalt
Physical Progress –AP4
Progress
Cumulative Status as at 30th
April 2018Cumulative Status as at 31st May
2018
Target (%) Actual (%) Target (%) Actual (%)
Physical 72.19% 72.95% 81.95% 80.74%
Payments Certified –AP4
Description Certified Amount (LKR)
Accepted Contract Amount 1,635,133,956.00
Up to Cumulative Certified Amount 968,048,459.01
Contract AP4 - Progress Photographs
Before Construction Asphalt Compaction at Road ID 133+516 km
Before Construction Priming at Road ID 165+280 km
Road Work Progress – iROAD - Anuradhapura District
Package No. Contractor No. of RoadsTotal Road Length
(km)No. of Roads Civil Works
in ProgressRoad Length Civil Works in
Progress (km)
AP1 MAGA 17 85.52 17 79.94
AP2 MAGA 12 76.52 12 68.11
AP3 MAGA 12 82.48 11 60.77
AP4 MAGA 19 89.16 19 86.85Total 60 333.68 59 295.67
85.52
76.52
82.48
89.16
79.94
68.11
60.77
86.85
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00
AP1
AP2
AP3
AP4
Road Length (km)
Co
ntr
act
Pa
cka
ge
Road Length Civil Works in Progress (km)
Progress Summary of Culverts & Bridges - iROAD-Anuradhapura District
DistrictPackage
No.Contractor
Total No. of Culvert
No. of Culvert No. of Culvert
New / Reconstruction
/ Widening
Completed / In
progress
Cleaning & Repair
Completed / In
progress
Anuradhapura
AP1 MAGA 248 118 108 130 27
AP2 MAGA 297 122 109 171 31
AP3 MAGA 265 161 148 100 6
AP4 MAGA 333 153 144 180 26
Total 1143 554 509 581 90
Overall Financial Status - iROAD- Anuradhapura District
Package No. ContractorAccepted Contract Amount
(LKR)
Total Certified Amount to Date (LKR) (Including Advance
Payment)
AP1 MAGA 1,656,915,760.80 913,434,612.34
AP2 MAGA 1,824,178,003.20 999,346,815.36
AP3 MAGA 1,492,772,165.28 818,988,659.42
AP4 MAGA 1,635,133,956.00 968,048,459.01
Total 6,608,999,885.28 3,699,818,546.13
Status of GRC Committee Formation Anuradhapura District - NCP
Contract No. Contractor No. of RoadsNo. of
DivisionsNo. of GRC (Level
3 - DS) formedNo. of GRC (Level 2 - GN)
formed
AP1 MAGA 17 6 6 17
AP2 MAGA 12 6 6 12
AP3 MAGA 12 4 4 12
AP4 MAGA 19 6 6 19
TOTAL 60 22 22 60
List of Utilities - iROAD- Anuradhapura District
Package No.
No. of Roads
No. of Roads Surveyed for
Utility Shifting
Utilities to be Shifted
Electricity Pole / (Nos.) Telecom Pole / (Nos.) Water Line / (m)
Identified Progress Identified Progress Identified Progress
AP1 17 17 9 1 Shifted 14 9 Shifted - -
AP2 12 12 9 9 Shifted 53 53 shifted 3800 2900 Completed
AP3 12 12 9 9 Shifted 4 4 Shifted 30 30 Shifted
AP4 19 19 5 5 Shifted 3 3 Shifted - -
Summary of Public Complaints - iROAD- Anuradhapura District
DistrictPackage
No.
Public Complaints Received
TotalNo.
Attended
No. Completely
Settled
Solutions in Progress
No. UnattendedNo. of
RequestNo. of
SuggestionNo. of
Complaints
No. of Crack related issues
An
ura
dh
apu
ra
AP1 99 3 2 - 104 103 97 6 1
AP2 47 0 11 - 58 58 40 18 -
AP3 42 45 7 - 94 93 89 4 -
AP4 73 15 4 3 95 95 80 15 -
Total 261 63 24 3 351 349 306 43 1
Overall Physical Progress Summary – iROAD – North Western Province / (up to 31st of May 2018)
Package No.
ContractorAccepted Contract
Amount / (Rs.)No. Of Roads
Roads Length /
(km)
No. of Roads; Civil
Works in Progress
Asphalt Completed
/ (km)
BalanceAsphalt to
be Completed
Physical Progress as
at 30th of April 2018 Actual (%)
Physical Progress;
Cumulative Status up to end of May
2018 (%)
Target Actual
KU1 MAGA 2,005,790,082.72 16 82.62 14 68.27 14.35 71.98 90.19 75.50
KU2KDAW-BMG JV
2,124,166,266.00 19 100.00 17 67.98 32.02 60.11 84.76 62.90
KU3Ranken Group
1,976,721,917.95 12 99.00 8 42.23 56.77 49.29 84.13 49.56
KU4 VVK & Co. 2,091,174,540.00 12 97.10 9 31.73 65.37 31.30 84.30 32.38
KU5Ranken Group
1,996,560,050.43 17 99.86 10 29.24 70.62 28.30 85.50 29.62
PU1Ranken Group
1,706,320,523.61 11 91.96 9 45.81 46.15 51.14 80.53 51.28
PU2 VVK & Co. 1,463,917,284.00 11 73.51 6 22.53 50.98 30.13 83.26 30.21
PU3 VVK & Co. 1,210,355,904.00 15 48.43 11 17.25 31.18 30.99 80.70 31.31
Project Location Maps – Kurunegala District
Package
Road Length (km)
KU1 82.62
KU2 100.00
KU3 99.00
KU4 97.10
KU5 99.86
TOTAL 478.58
Progress of Road Work Bar Chart in KU1
Earthwork in progress ABC Completed Asphalt Completed
Note: Road ID No. 36, 98 Earth Work Construction Still Has Not
Started.
Serial No
DS.DivisionRoad
IDRoad Name
Road Catogory
Length (Km)
Progress Up to End of May 2018
1 km 2 km 3 km 4 km 5 km 6 km 7 km 8 km 9 km 10 km 11 km
1
Bingiriya
30 Talagahapitiya Junction to Walrawa Road PRDD 5.05
2 32 Kaduruwewa School to Wallawewa School Road PRDD 2.45
3 34Meladeniya Junction Udawela Kakiriyamdiththa, Ganegoda to Ambawewa Road
PS 8.23
4 Udubaddawa 33Karaulla Horathapola Kibulkotumulla via Paliyagara Road
PS 6.22
5Panduwasnuw
ara Eest81
Mavi ela Junction to Nagulmunna road via Thelibewa Temple ,kosdeniya, Ilukpitiya Junction
PS 7.50
6
Kuliyapitiya East
47 Bihalpola Muthugala Road PRDD 10.30
7 48 Ihalamuluthangala to Korale Junction Road PRDD 3.78
8 49 NakkawatthaTemple Road to Kaballa Road PS 2.20
9 50Katupotha, Dalupothagama, Thoranegedara, Kirimatiyawa Road
PRDD 6.62
10 86 Horamubuwa Mawee Ela Road PRDD 6.50
11Kuliyapitiya
West55
Kosgahamula Junction to Katugampola (Dambadeniya Road)
PRDD 5.25
12
Panduwasnuwara West
76Kamburapola Junction to Pahalagomugomuwa, Nindawela Road
PS 4.50
13 82Magulagama Junction to Ambagahlanda Mohoththauwagoda Junction
PS 4.51
14 97 Hidiyamulla Junction to Guruthippala Junction PS 4.03
Physical Progress of Plan Work in KU1
Mo
nth
s
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Fe
b-1
7
Ma
r-1
7
Ap
r-1
7
Ma
y-1
7
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-1
7
De
c-1
7
Jan
-18
Fe
b-1
8
Ma
r-1
8
Ap
r-1
8
Ma
y-1
8
Jun
-18
Jul-
18
Planned Progress
Monthly (%) 0.0
0%
0.0
0%
0.0
9%
0.4
6%
1.2
3%
3.3
3%
6.3
9%
9.4
5%
11
.55
%
14
.98
%
21
.29
%
27
.62
%
32
.22
%
36
.37
%
42
.01
%
47
.53
%
54
.12
%
61
.26
%
67
.51
%
75
.22
%
81
.37
%
90
.19
%
98
.12
%
10
0.0
0%
Actual Progress
Monthly (%) 0.0
0%
0.0
0%
0.0
0%
0.1
9%
0.5
5%
1.6
4%
4.2
9%
8.0
0%
11
.95
%
16
.59
%
19
.91
%
26
.55
%
32
.04
%
35
.98
%
39
.68
%
42
.83
%
48
.83
%
54
.90
%
61
.52
%
67
.19
%
71
.98
%
75
.50
%
Delay Progress (%)
0.0
0%
0.0
0%
-0.0
9%
-0.2
7%
-0.6
8%
-1.6
9%
-2.1
0%
-1.4
5%
0.4
0%
1.6
1%
-1.3
8%
-1.0
7%
-0.1
8%
-0.3
9%
-2.3
3%
-4.7
0%
-5.2
9%
-6.3
6%
-5.9
9%
-8.0
3%
-9.3
9%
-14
.69
%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Au
g-1
6
Sep-
16
Oct
-16
No
v-1
6
Dec
-16
Jan
-17
Feb
-17
Ma
r-1
7
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-17
Dec
-17
Jan
-18
Feb
-18
Ma
r-1
8
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Planned Progress Monthly (%) Actual Progress Monthly (%)
KU1Total (Up to
May - 18)Description Up to Dec - 17 Jan-18 Feb-18 Mar-18 Apr - 18 May - 18
Embankment 56.99 7.11 4.30 1.10 3.00 1.50 74.00
Sub base 53.29 6.25 4.26 5.30 3.20 1.93 74.23
A.B.C 50.49 5.72 4.54 4.54 3.96 2.38 71.63
Prime 50.49 5.92 4.56 4.54 3.40 1.48 70.39
Asphalt(Total Length 82.62 km)
48.09 5.52 4.24 4.80 4.84 0.78 68.27
0.00
2.00
4.00
6.00
8.00
Jan-18 Feb-18 Mar-18 Apr - 18 May - 18
Embankment Sub base A.B.C Prime Asphalt
Physical Progress -KU1
Progress
Cumulative Status as at 30th
April 2018Cumulative Status as at 31st May
2018
Target (%) Actual (%) Target (%) Actual (%)
Physical 81.37% 71.98% 90.19% 75.50%
Payments Certified - KU1
Description Certified Amount (LKR)
Accepted Contract Amount 2,005,790,082.72
Up to Cumulative Certified Amount 1,208,515,441.95
Contract KU1 - Progress Photographs
Before Construction
Completed at Road ID 491+400 km
After Road Signs Installation at Road ID 47 7+920 km
Before Construction
Contract KU1 - Flooding Photographs
Road ID 76 at 4+100 km
Road ID 76 at 0+750 - 0+800 km
Road ID 76 at 2+200 - 2+300 km
Road ID 33 at 4+500 km
Road ID 33 at 6+000 - 6+100 km
Road ID 81 at 3+965 km
Road ID 98 at 1+900 - 1+950 km
Road ID 98 at 2+100 - 2+150 km
Progress of Road Work Bar Chart in KU2
Earthwork in progress ABC Completed Asphalt Completed
Note: Road ID No. 101, 66 Earth Work Construction Still Has
Not Started.
Serial No
DS.DivisionRoad
IDRoad Name
Road Catogory
Length (Km)
Progress Up to End of May 20181 km 2 km 3 km 4 km 5 km 6 km 7 km 8 km 9 km 10 km 11 km
1
Pannala
56Elabadagema, Bummanna, Kadirapola, Labbala via Negambo Kurunegala Road
PRDD 10.29
2 57Jayagama Kete Junction to Nabirittankadawara via Welipennagahamulla Road
PRDD 5.93
3 58 Eliwila, Daraluwa via Yakwila Road PRDD 7.54
4-i 59-RNendalagamuwa Ayurweda Junction to Ninuwangamuwa Walakumburumulla Road
PS 2.84
4-ii 59-LNandalagamuwa Ayurweda Junction to Ninuwangamuwa Walikuburumulla Road
PS 1.95
5
Alawwa
1Boyawalana Nawathalawatta Wewwala School Road Across Habaralagasinna Madurupitiya Road
PRDD 11.50
6 Paramaulla to Morugama across Bujjomuwa Road PS 3.472
7 4 6 Mile Post Thumbulla Road PRDA 2.55
8-i 100-RHumbuluwa Henahundeniya Via ambowa Wanathalwatta Hospital Road
PRDD 1.82
8-ii 100-LHumbuluwa Henahundeniya Via ambowa Wanathalwatta Hospital Road
PRDD 2.75
9
Narammala
5Dampelessa Dostarawaththa Across Welikumburawatta Road
PS 3.74
10 102 Pahatha medagoda Welikumburawatta Road PS 3.18
11
Polgahawela
41 Hodalla,Polpitiya,Dambagolla,Kandahena Road PRDA/PS 5.89
12-i 43-R Panaliya Railway gate to Pillwatta Road PRDD 1.86
12-ii 43-L Panaliya Railway gate to Pillwatta Road PRDD 3.13
13 Wariyapola 67 Nawagatta,Yatikadurawa,Ketapathwehera, PS 4.73
14Weerambuge
dera
46 Pambe Lokahettiya Ranwala gedara Road PS 6.82
15 45 Piduruwella, Sandagala, Weherabanda Road PRDD/PS 5.76
16
Kurunegala
74Wewa Gedara Ranviru School to Klohogedara via Yanthampalawa Junction
PRDD 2.62
17 75 Minihettiya Baddegama Kelimune Junction PS 3.39
Physical Progress of Plan Work in KU2
Mo
nth
s
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Fe
b-1
7
Ma
r-1
7
Ap
r-1
7
Ma
y-1
7
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-1
7
De
c-1
7
Jan
-18
Fe
b-1
8
Ma
r-1
8
Ap
r-1
8
Ma
y-1
8
Jun
-18
Jul-
18
Original Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
0.0
7%
1.1
6%
3.8
1%
6.4
6%
9.4
6%
12
.66
%
19
.33
%
25
.80
%
32
.47
%
39
.14
%
45
.68
%
52
.55
%
59
.42
%
66
.50
%
73
.24
%
79
.37
%
86
.11
%
89
.24
%
95
.91
%
99
.86
%
10
0.0
0%
Revised Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
8%
0.2
2%
0.9
0%
3.8
4%
6.9
6%
10
.02
%
13
.76
%
19
.86
%
22
.10
%
25
.84
%
29
.93
%
34
.69
%
38
.09
%
41
.35
%
44
.69
%
52
.85
%
61
.70
%
71
.22
%
74
.56
%
84
.76
%
95
.65
%
10
0.0
0%
Actual Progress
Monthly (%) 0.0
0%
0.0
0%
0.0
8%
0.2
2%
0.9
0%
3.8
4%
6.9
6%
10
.02
%
13
.77
%
19
.87
%
22
.11
%
25
.86
%
30
.10
%
32
.34
%
35
.94
%
38
.76
%
41
.65
%
46
.68
%
49
.41
%
54
.94
%
60
.11
%
62
.90
%
Delay Progress (%)
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
1%
0.0
1%
0.0
1%
0.0
2%
0.1
7%
-2.3
5%
-2.1
5%
-2.5
9%
-3.0
4%
-6.1
7%
-12
.29
%
-16
.28
%
-14
.45
%
-21
.86
%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Au
g-1
6
Se
p-1
6
Oct
-16
No
v-1
6
Dec
-16
Jan-
17
Feb
-17
Mar
-17
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Se
p-1
7
Oct
-17
No
v-1
7
Dec
-17
Jan-
18
Feb
-18
Mar
-18
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Original Planned Progress Monthly (%) Revised Planned Progress Monthly (%) Actual Progress Monthly (%)
KU2Total (Up to
May - 18)Description Up to Dec - 17 Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment 56.50 4.80 7.08 7.94 1.70 3.21 81.23
Sub base 55.11 5.69 5.26 8.24 1.70 3.29 79.28
A.B.C 52.85 3.50 4.72 5.95 2.32 2.65 71.98
Prime 49.73 5.09 3.95 5.44 3.35 2.06 69.62
Asphalt(Total Length 100.00 km)
47.69 5.58 3.45 4.40 4.94 1.92 67.98
0.00
2.00
4.00
6.00
8.00
10.00
Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment Sub base A.B.C Prime Asphalt
Physical Progress – KU2
Progress
Cumulative Status as at 30th
April 2018Cumulative Status as at 31st May
2018
Target (%) Actual (%) Target (%) Actual (%)
Physical 74.56% 60.11% 84.76% 62.90%
Payments Certified – KU2
Description Certified Amount (LKR)
Accepted Contract Amount 2,124,166,266.00
Up to Cumulative Certified Amount 1,212,416,824.47
Contract KU2 - Progress Photographs
Before Construction Shoulder Construction at Road ID 46 3+300 - 3+555 km
Before Construction Sub Base Compaction at Road ID 67 2+970 - 3+050 km
Contract KU2 - Flooding Photographs
Road ID 57 at 0+800 km
Road ID 57 at 4+650 - 4+685 km
Road ID 58 at 2+285 - 2+500 km
Road ID 58 at 2+420 - 2+500 km Road ID 59R at 2+170 - 2+270 km
Road ID 59R at 2+170 - 2+270 km
Road ID 05 at 0+080 - 0+105 km
Road ID 05 at 1+730 km
Road ID 56 at 5+125 - 5+220 km
Contract KU2 - Flooding Photographs
Road ID 56 at 5+125 - 5+220 km
Road ID 102 at 1+755 km Road ID 102 at 2+580 - 2+595 km
Road ID 102 at 3+114 - 3+174 km Road ID 01 at 9+000 - 9+050 km Road ID 04 at 1+881 - 2+050 km
Road ID 04 at 1+240 - 1+247 km
Road ID 100L at 2+590 - 2+750 km Road ID 41 at 3+623 - 3+640 km
Contract KU2 - Flooding Photographs
Road ID 41 at 3+694 - 3+705 km
Road ID 41 at 1+314 - 1+402 km
Road ID 41 at 1+314 - 1+402 km
Road ID 41 at 3+750 - 3+778 km Road ID 41 at 3+986 - 3+996 km Road ID 46 at 5+250 - 5+325 km
Road ID 43R at 1+823 km Road ID 43R at 1+465 - 1+495 km Road ID 43R at 1+230 - 1+240 km
Progress of Road Work Bar Chart in KU3
Earthwork in progress ABC Completed Asphalt Completed
Note: Road ID No. 37, 39, 40, 23 Earth Work Construction Still Has Not
Started.
Serial No
DS. Division
Road ID
Road NameRoad
Category
Length (Km)
Progress Up to End of May 2018
1 km 2 km 3 km 4 km 5 km 6 km 7 km 8 km 9 km 10 km 11 km 12 km 13 km 14 km 15 km 16 km 17 km 18 km 19 km 20 km 21 km 22 km 23 km
1
Kurunegala
71Colombo Road NarammalaKurunegala Main Road KubalpolaJunction Hal Para
PRDD 4.18
2 68Malpitiya Junction to Bogamuwa Junction Theeragama Road
PRDD 6.70
3
Mawathagama
17Wataraka Junction to Uda Iguruwaththa via Kudumiriya Road
PRDD/PS
6.24
4 20Wataraka Junction to Uda Iguruwaththa via Kudumiriya Road
PS 5.00
5
Ridigama
38Palle Horombuwa Ginihiriya Margaya Road
PRDD/PS
7.17
6 84Meeliyadda-Ikiriwaththa-Bokkawala Road
PRDD 3.54
7
Ganewaththa
22Nabiriththawewa Junction to Hunupola, Siradunna via, Pannala Road
PRDD 23.12
8 87Hiripitiya Aluthgama Kalawana Road
PS 5.77
Physical Progress of Plan Work in KU3
Mo
nth
s
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Fe
b-1
7
Ma
r-1
7
Ap
r-1
7
Ma
y-1
7
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-1
7
De
c-1
7
Jan
-18
Fe
b-1
8
Ma
r-1
8
Ap
r-1
8
Ma
y-1
8
Jun
-18
Jul-
18
Original Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
0.1
7%
0.9
9%
3.2
8%
6.8
5%
11
.97
%
15
.39
%
20
.68
%
26
.15
%
31
.64
%
36
.94
%
42
.71
%
49
.43
%
55
.97
%
61
.81
%
67
.38
%
73
.90
%
81
.85
%
88
.03
%
93
.53
%
98
.16
%
10
0.0
0%
Revised Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
4%
1.3
7%
4.0
8%
8.7
5%
9.4
5%
14
.48
%
18
.23
%
21
.48
%
25
.06
%
28
.38
%
32
.36
%
36
.87
%
42
.55
%
50
.26
%
58
.91
%
67
.99
%
74
.50
%
84
.13
%
92
.90
%
10
0.0
0%
Actual Progress
Monthly (%) 0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.7
7%
1.3
7%
4.0
8%
8.7
2%
9.4
4%
14
.47
%
18
.23
%
22
.48
%
25
.06
%
29
.32
%
32
.36
%
35
.12
%
40
.02
%
44
.07
%
47
.17
%
49
.22
%
49
.29
%
49
.56
%
Delay Progress (%)
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.7
3%
0.0
0%
0.0
0%
-0.0
3%
-0.0
1%
-0.0
1%
0.0
0%
1.0
0%
0.0
0%
0.9
4%
0.0
0%
-1.7
5%
-2.5
3%
-6.1
9%
-11
.74
%
-18
.77
%
-25
.21
%
-34
.57
%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Au
g-1
6
Se
p-1
6
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Feb
-17
Mar
-17
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Se
p-1
7
Oct
-17
No
v-1
7
Dec
-17
Jan
-18
Feb
-18
Mar
-18
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Original Planned Progress Monthly (%) Revised Planned Progress Monthly (%) Actual Progress Monthly (%)
KU3 Total (Up to May - 18)Description Up to Dec - 17 Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment 41.41 4.14 3.98 1.00 0.00 0.00 50.53
Sub base 41.14 4.14 3.50 1.00 0.00 0.00 49.78
A.B.C 36.86 4.40 4.20 1.68 0.00 0.10 47.23
Prime 35.57 4.40 4.60 1.68 0.64 0.00 46.89
Asphalt(Total Length 99.00 km)
33.48 4.69 0.00 3.39 0.00 0.67 42.23
0.00
2.00
4.00
6.00
Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment Sub base A.B.C Prime Asphalt
Progress Up to 19.06.2018 – KU3
Road No.Road length
(Km)Starting
DateAbandoned
DateRestarting Date
Material stock/ (cube)
Remarks
17 6.24 8-Jan-17 3-Mar-18 Not Started - No Work
20 5.04 15-Nov-17 4-Jan-18 Not Started Gravel - 1600 No Work
22 23.12 5-Dec-16 1-Jun-18 13/Jun/18 - ABC laying
23 13.75 30-Dec-17 3-Feb-18 Not Started - No Work
37 3.14 20-Oct-17 N/A N/A - Culvert Construction
38 7.17 6-Feb-17 16-Feb-18 Not Started ABC - 1175 No Work
39 6.02 Not Started - No Work
40 6.11 Not Started - No Work
68 6.68 23-Apr-17 N/A N/A - Retaining Wall Construction
71 4.18 31-Dec-16 20-Feb-18 Not Started - No Work
84 3.54 7-Aug-17 21-Feb-18 Not Started - No Work
87 5.77 13-Nov-17 31-Jan-18 Not Started - No Work
Physical Progress –KU3
Progress
Cumulative Status as at 30th
April 2018Cumulative Status as at 31st May
2018
Target (%) Actual (%) Target (%) Actual (%)
Physical 74.50% 49.29% 84.13% 49.56%
Payments Certified – KU3
Description Certified Amount (LKR)
Accepted Contract Amount 1,976,721,917.95
Up to Cumulative Certified Amount 871,904,478.46
TL’s Comments - KU3 • Rate of Progress ( Sub-Clause 8.6 of GCC) issued on 20.02.17 , letter ref. no. iROAD/PIC-02/RE/Ranken/KU3/06/003.
• Notice to Correct (Clause 15.1 of GCC) issued on 17.05.2018, letter ref. no. iROAD/PIC-02/Ranken/KU3/01/2556 and Ranken were provided 30days from the date of the letter to achieve the progress /catch up on the delays, failing which the Client will exercise the contractual optionunder the contract by issuing Notice for Termination under Sub Clause 15.2. to date no significant progress has been achieved and many roadshas been abandoned.
• Delay of works has been thoroughly discussed in all the Monthly Progress Review Meetings where direction, advise and the delays wereidentified for Ranken to speed up the works and catch up on the delays and the same was discussed in the PCC Meetings.
• Numerous ‘Special Meetings’ were conducted with the Chairman on Delays of Ranken for all their contracts, where it was stressed of the serioussituation with the progress, for the contractor to catch up on the progress and the consequences if the contractor fails to achieve the progresswhich will lead to the issuance of Notice under Sub Clause 15.2.
• ‘Special Meeting’ was held on the 6th April 2018 with the participation of Ranken’s Sri Lanka General Manager, Mr. Liao Kui where the Chairmanhas provided clear direction to overcome the situations, catchup on the delays, Ranken to resolve their cash flow problems, failing which, theclient will take the contractual remedy to terminate the contract under Sub Clause 15.2. A recent ‘Special Meeting “ on Termination – Sub-Clause15.2 was held on the 01st June 2018.
• Non-Compliance to the above Notices, non compliance to the discussions and directions provided in the Monthly Progress review Meetings tospeed up the works and to restart the works at all the roads that has been abandoned, to complete all the works as per the schedule and PCCMeetings discussions and direction has lead to the Non-Performance of the contractor Ranken.
• Adequate time till now to show progress by providing Ranken with an opportunity to put right previous identified contractual failures inachieving the progress as scheduled has been provided but Ranken has failed to achieve the progress and to catch up on the delays.
❑ Present situation on site, works on all roads are generally neglected.
▪ Insignificant Gabion wall construction in progress only on road ID 22 and only one Gabion wall was carried out.
▪ Asphalt restarted on road ID 22 on 30 May 2018, on areas where the priming was completed in March 2018. All new asphalt operator, labor teamhas been brought in from Kegalle site instead of the previous team(which still has not been paid).
▪ No any other significant works on any road since end of March up to date. Ranken agreed to restart retaining wall balance work in front of Armycamp after receiving the complains from the Army camp and public on road ID 68, but Ranken still has not commenced the work.
▪ 9 Nos of Roads such as RD ID 71 (Fixing sign boards), 17 (Finishing work), 38 (Balance work), 84, 87, 37, 20, 23 & 68 started and abandoned. 2Nos of roads still has not commenced the construction work.
Contract KU3 - Progress Photographs
Before Construction Shoulder Construction at Road ID 22 19+350 km
Before Construction Asphalt Laying at Road ID 2210+630 km
Contract KU3 - Progress Photographs
Before Construction Gabion Wall Construction at RD ID 223+300 km
Summary of Progress-Survey/Investigation & Design in KU4
Description
To
tal
Le
ng
th (
km
) Horizontal Alignment
Initial Cross section
InvestigationPavement
DesignVertical
AlignmentDesign Cross
Section
Road No.
Su
bm
itte
d
Ap
pro
ve
d
Su
bm
itte
d
Ap
pro
ve
d
Te
st p
it
La
b T
est
ing
Re
po
rt
Su
bm
itte
d
Ap
pro
ve
d
Su
bm
itte
d
Ap
pro
ve
d
Su
bm
itte
d
Ap
pro
ve
d
90 15.00 13.25 12.79 12.79 12.79 15.00 15.00 15.00 13.50 13.50 12.80 12.80 12.80 12.80
7 4.43 4.43 4.43 4.43 4.43 4.43 4.43 4.43 4.43 4.43 4.43 4.43 3.22 3.22
8 8.00 7.50 7.50 7.50 7.50 7.50 7.50 7.50 7.50 7.50 7.50 7.50 7.50 7.50
Note: Road ID No. 27, 28, 91, 10, 94, 92, 11, 16, 96 Completed.
Progress of Road Work Bar Chart in KU4
Earthwork in progress ABC Completed Asphalt Completed
Note: Road ID No. 28, 7, 8 Earth Work
Construction Still Has Not Started.
Serial No
DS. DivisionRoad
IDRoad Name
Road Catogory
Length (Km)
Progress Up to End of May 2018
1 km 2 km 3 km 4 km 5 km 6 km 7 km 8 km 9 km 10 km 11 km 12 km 13 km 14 km 15 km
1
Galgamuwa
90Inginimitiya to Wannikudawewa via nanneriya Junction
PRDD 15.00
2 92Wathuwaththegama to Mudiyanegama via Kumbukkadawala
PRDD 9.72
3 Ehetuwa 11Kothnoru Junction to near the School Reswehera Temple Road
PRDD 5.20
4 Kotawehera 27Palugolla Iginimitiya Road (Aluthgama Kotawehera Road
PRDD 6.98
5 Maho 94Daladagama to Nikaweratiya, Ambanpola Road via Wathupalagama, Polpithigama,Waduressa
PS 6.98
6 Giribawa 91Paluwewa Junction to Giribawa Road via Ussana
PS 6.42
7
Abanpola
16 Nelumpathwewa Udadiulwewa Road PS 7.60
8 96 Kasikote Junction to Meeoya Bridge via Peella PS 4.30
9 10In front Atharagalla School, Gurugoda, Kothalawetiya, Kalegama Road
PS 6.16
Physical Progress of Plan Work in KU4
Mo
nth
s
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Fe
b-1
7
Ma
r-1
7
Ap
r-1
7
Ma
y-1
7
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-1
7
De
c-1
7
Jan
-18
Fe
b-1
8
Ma
r-1
8
Ap
r-1
8
Ma
y-1
8
Jun
-18
Jul-
18
Original Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
1%
2.2
9%
6.0
1%
11
.24
%
15
.19
%
20
.56
%
26
.11
%
30
.76
%
35
.30
%
40
.28
%
45
.76
%
51
.34
%
57
.46
%
64
.19
%
72
.43
%
81
.46
%
87
.00
%
92
.42
%
96
.62
%
10
0.0
0%
Revised Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
0.0
4%
0.3
2%
0.5
4%
1.0
6%
2.1
4%
3.5
9%
4.9
2%
6.0
5%
8.5
4%
11
.18
%
14
.28
%
18
.15
%
22
.72
%
28
.34
%
34
.67
%
45
.10
%
58
.45
%
71
.93
%
84
.30
%
92
.18
%
10
0.0
0%
Actual Progress
Monthly (%) 0.0
0%
0.0
0%
0.0
0%
0.0
4%
0.3
2%
0.5
4%
1.0
6%
2.1
4%
3.5
9%
4.9
2%
6.0
5%
8.5
4%
11
.24
%
13
.70
%
16
.22
%
18
.42
%
20
.67
%
23
.12
%
28
.42
%
30
.48
%
31
.30
%
32
.38
%
Delay Progress (%)
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
6%
-0.5
8%
-1.9
3%
-4.3
0%
-7.6
7%
-11
.55
%
-16
.68
%
-27
.97
%
-40
.63
%
-51
.92
%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Au
g-1
6
Se
p-1
6
Oct
-16
No
v-1
6
Dec
-16
Jan-
17
Feb
-17
Mar
-17
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Se
p-1
7
Oct
-17
No
v-1
7
Dec
-17
Jan-
18
Feb
-18
Mar
-18
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Original Planned Progress Monthly (%) Revised Planned Progress Monthly (%) Actual Progress Monthly (%)
KU4 Total (Up to May - 18)Description Up to Dec - 17 Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment 31.13 3.85 3.95 9.10 1.75 2.02 51.80
Sub base 26.03 4.00 3.55 2.33 1.38 2.18 39.47
A.B.C 24.06 5.37 3.36 1.84 1.05 1.23 36.91
Prime 23.49 2.58 4.72 1.73 0.49 0.53 33.54
Asphalt(Total Length 97.10 km)
23.35 0.85 5.12 2.41 0.00 0.00 31.73
0.00
2.00
4.00
6.00
8.00
10.00
Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment Sub base A.B.C Prime Asphalt
Progress Up to 19.06.2018 – KU4
Road No.Road
length (Km)
Starting Date
Abandoned Date
Restarting Date
Material stock/ (cube)
On going works Remarks
96 4.30 14-Nov-16 20-Jul-17 4-Apr-18ABC - 220
Sub base - 120 ABC Works
Fuel insufficient for the machineries to work at optimum level. Works ongoing
albeit very slowly
16 7.64 5-Jan-17 N/A N/A - Structure Works -
92 9.72 21-Dec-16 26-Mar-18 Not Started - No Work -
94 6.98 20-Feb-17 25-Jan-18 Not Started - No Work -
27 11.97 8-Jan-18 N/A N/A Sub base - 300 Embankment, Subbase,
and Structure Works
Fuel insufficient for the machineries to work at optimum level. Works ongoing
albeit very slowly
28 9.50 4-Jun-18 N/A N/A - Structure WorksFuel insufficient for the machineries to work at optimum level. Works ongoing
albeit very slowly
90 15.00 12-Jul-17 N/A N/A ABC - 250 Embankment,ABC,
Structure Works
Fuel insufficient for the machineries to work at optimum level. Works ongoing
albeit very slowly
91 6.42 10-Dec-17 N/A N/AABC - 39
Sub base - 3 ABC and Structure
Works
Fuel insufficient for the machineries to work at optimum level. Works ongoing
albeit very slowly
08 8.00Not started
yet- No Work -
10 6.16 6-Oct-17 N/A N/AABC - 653
Sub base - 35 Structure Works -
11 4.88 4-Apr-17 16-Jan-18 28-Mar-18ABC - 148
Sub base - 1035 Embankment Works
Fuel insufficient for the machineries to work at optimum level. Works ongoing
albeit very slowly
07 4.43Not started
yet- No Work -
Physical Progress – KU4
Progress
Cumulative Status as at 30th
April 2018Cumulative Status as at 31st May
2018
Target (%) Actual (%) Target (%) Actual (%)
Physical 71.93% 31.30% 84.30% 32.38%
Payments Certified – KU4
Description Certified Amount (LKR)
Accepted Contract Amount 2,091,174,540.00
Up to Cumulative Certified Amount 795,606,601.51
Contract KU4 - Progress Photographs
Embankment Construction at Road ID 113+940 km
Sub Base Compaction at Road ID 27 11+950 km
Shoulder Construction at Road ID 909+550 km
Edge Widening at Road ID 27 10+100 km
Contract KU4 - Progress Photographs
Sub Base Compaction at Road ID 11
3+830 km
Priming at Road ID 90 9+430 km
Contract KU4 - Flooding Photographs
Road ID 28 at 0+900 - 0+950 km
Road ID 28 at 1+150 km Road ID 28 at 1+150 - 1+475 km
Road ID 28 at 1+150 - 1+475 km Road ID 28 at 1+150 - 1+475 km Road ID 28 at 1+150 - 1+475 km
Road ID 28 at 1+150 - 1+475 km
Road ID 28 at 4+250 - 4+340 km Road ID 28 at 4+250 - 4+340 km
Contract KU4 - Flooding Photographs
Road ID 28 at 5+240- 5+450 km
Road ID 28 at 5+370 km Road ID 28 at 5+480 km
Road ID 28 at 5+480 km
Road ID 28 at 5+480 km
Road ID 28 at 5+550 - 5+760 km
Road ID 28 at 7+640 - 7+700 km
Road ID 28 at 7+900 - 7+980 km Road ID 28 at 7+970 km
Summary of Progress-Survey/Investigation & Design in KU5
Description
To
tal
Le
ng
th (
km
) Horizontal Alignment
Initial Cross section
InvestigationPavement
DesignVertical
AlignmentDesign Cross
Section
Road No.
Su
bm
itte
d
Ap
pro
ve
d
Su
bm
itte
d
Ap
pro
ve
d
Te
st p
it
La
b T
est
ing
Re
po
rt
Su
bm
itte
d
Ap
pro
ve
d
Su
bm
itte
d
Ap
pro
ve
d
Su
bm
itte
d
Ap
pro
ve
d
79 4.47 4.47 4.47 4.47 4.47 4.47 4.47 4.47 4.47 4.47 4.47 3.92 4.47 3.92
Note: Road ID No. 14, 12, 13, 29, 70, 77, 80, 24, 26, 61, 62, 65, 83, 89, 99 Completed.
Progress of Road Work Bar Chart in KU5
Earthwork in progress ABC Completed Asphalt Completed
Note: Road ID No. 65, 95, 13, 29, 79, 80, 89 Earth Work Construction Still Has Not Started.
Serial No
DS. DivisionRoad
IDRoad Name
Road Catogory
Length (Km)
Progress Up to End of May 2018
1 km 2 km 3 km 4 km 5 km 6 km 7 km 8 km 9 km 10 km 11 km
1 Kobeigane 26 Padeniya Kobeigane Road PRDD 10.93
2
Wariyapola
62 Werella Junction to Naramana Thambarawewa Road PS 4.61
3 61Rambawewa Junction to Ambakadawara, Hettigedara via Mirihanegama Road
PS 4.94
4
Paduwasnuwara West
99Wilbagedara Junction to Dunupotha Rathmalla Junction Road
PS 4.19
5 77 Hunugama Junction to Nallur Junction PS 4.12
6 83 Kajuwatta junction to Koonwewa Balagolla road PS 6.03
7 Nikaweratiya 24Gangoda Road (Jayalanka Trade Centre to Court Complex via Budumuththawa Temple)
PS 1.38
8 Mahawa 12 Wilawa Junction to Kumbukwewa Road PS 6.80
9 Kurunegala 70 Porapola Junction to Thalvita Siradunna Junction Road PS 8.50
10 Polpithigama 14 Madahapola Mahayaya Madahapola Road PS 8.15
Physical Progress of Plan Work in KU5
Mo
nth
s
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Fe
b-1
7
Ma
r-1
7
Ap
r-1
7
Ma
y-1
7
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-1
7
De
c-1
7
Jan
-18
Fe
b-1
8
Ma
r-1
8
Ap
r-1
8
Ma
y-1
8
Jun
-18
Jul-
18
Original Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
1.2
0%
4.8
2%
8.4
7%
10
.94
%
16
.78
%
22
.62
%
28
.49
%
35
.09
%
41
.58
%
48
.06
%
55
.05
%
62
.03
%
69
.05
%
75
.89
%
82
.58
%
86
.33
%
89
.62
%
94
.81
%
10
0.0
0%
Revised Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.3
1%
0.7
4%
2.0
3%
2.8
5%
2.8
7%
3.5
7%
4.3
3%
6.0
8%
8.7
8%
10
.57
%
17
.22
%
27
.09
%
37
.73
%
48
.25
%
58
.36
%
68
.71
%
76
.13
%
85
.50
%
93
.18
%
10
0.0
0%
Actual Progress
Monthly (%) 0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.3
1%
0.7
4%
2.0
3%
2.8
5%
2.8
7%
3.5
7%
4.3
3%
6.0
8%
8.7
8%
10
.57
%
12
.83
%
14
.86
%
18
.08
%
24
.10
%
25
.80
%
27
.90
%
28
.30
%
29
.62
%
Delay Progress (%)
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
-4.3
9%
-12
.23
%
-19
.65
%
-24
.15
%
-32
.56
%
-40
.81
%
-47
.83
%
-55
.88
%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Au
g-1
6
Se
p-1
6
Oct
-16
No
v-1
6
Dec
-16
Jan-
17
Feb
-17
Mar
-17
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Se
p-1
7
Oct
-17
No
v-1
7
Dec
-17
Jan-
18
Feb
-18
Mar
-18
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Original Planned Progress Monthly (%) Revised Planned Progress Monthly (%) Actual Progress Monthly (%)
KU5 Total (Up to May - 18)Description Up to Dec - 17 Jan-18 Feb-18 Mar-18 Apr - 18 May - 18
Embankment 25.62 3.17 4.75 1.00 0.03 0.00 34.57
Sub base 25.34 4.00 5.28 2.80 0.00 0.00 37.42
A.B.C 20.32 6.59 5.10 2.80 0.09 0.00 34.90
Prime 20.66 2.74 3.77 2.28 1.75 0.00 31.20
Asphalt(Total Length 99.86 km)
19.32 3.36 0.00 2.91 1.03 2.62 29.24
0.00
2.00
4.00
6.00
8.00
Jan-18 Feb-18 Mar-18 Apr - 18 May - 18
Embankment Sub base A.B.C Prime Asphalt
Progress Up to 19.06.2018 – KU5
Road No. Road length (Km)Starting
DateAbandoned
DateRestarting Date Material stock/ (cube) Remarks
12 6.8 15-May-17 15-Mar-18 Not started ABC - 297.5 No Work
13 9.42 Not Started - No Work
14 8.15 15-Mar-18 30-Mar-18 Not started - No Work
24 1.38 25-Apr-17 9-Apr-18 6-Jun-18 ABC - 28.3 No Work
26 10.93 22-Dec-16 9-Apr-18 11-Jun-18 - Culvert Work
29 11.35 10-Jan-18 3-Mar-18 Not started - No Work
61 4.93 20-Oct-16 10-Apr-18 Not started - No Work
62 4.61 10-May-17 5-Mar-18 Not started - No Work
65 3.37 Not Started - No Work
70 8.5 1-Oct-17 15-Jan-18 30-May-18 ABC - 636.75 Structure Work
77 4.12 15-Mar-17 17-Mar-18 Not started Soil - 84.9 No Work
79 4.47 Not Started Soil - 1100.87 No Work
80 4.86 Not Started - No Work
83 6.03 15-Jan-18 30-Jan-18 Not started Soil - 1415.00 No Work
89 3.44 Not Started - No Work
95 3.3 Not Started No Work
99 4.19 10-Mar-17 9-Apr-18 5-May-18 Soil - 113.2 ,ABC-353.75 Structure Work
Physical Progress – KU5
Progress
Cumulative Status as at 30th
April 2018Cumulative Status as at 31st May
2018
Target (%) Actual (%) Target (%) Actual (%)
Physical 76.13% 28.30% 85.50% 29.62%
Payments Certified – KU5
Description Certified Amount (LKR)
Accepted Contract Amount 1,996,560,050.43
Up to Cumulative Certified Amount 778,018,073.48
TL’s Comments – KU5
• Rate of Progress ( Sub-Clause 8.6 of GCC) issued on 03.04.17 , letter ref. no. iROAD/PIC-02/Ranken/KU5/01/915.
• Notice to Correct (Clause 15.1 of GCC) issued on 12.05.2017, letter ref. no. iROAD/PIC-02/Ranken/KU5/06/996 and Ranken were providedanother letter on the Notice to Correct to confirm that the earlier letter ref. no 996 is still in force and valid whereby we cannot nullify theearlier letter on Notice to Correct through letter ref. no. iROAD/PIC-02/Ranken/KU5/06/2191 dated 14.02.18. You were advised to achievethe progress /catch up on the delays. You have failed to achieve the progress as discussed with your Director/Ranken, whereby now theClient will exercise the contractual option under the contract by issuing Notice for Termination under Sub Clause 15.2. to date no significantprogress has been achieved and many roads has been abandoned.
• Meeting on the 01st June 2018, is to provide you a final opportunity to explain, propose the way forward, provide assurance on resolving thecash flow problems with documented proof, guarantee to the Client for all of Ranken’s contracts failing which the contractual option underthe contract by issuing Notice for Termination under Sub Clause 15.2. will be carried out.
• Delay of works has been thoroughly discussed in all the Monthly Progress Review Meetings where direction, advise and the delays wereidentified for Ranken to speed up the works and catch up on the delays and the same was discussed in the PCC Meetings.
• Numerous ‘Special Meetings’ were conducted with the Chairman on Delays of Ranken for all their contracts, where it was stressed of theserious situation with the progress, for the contractor to catch up on the progress and the consequences if the contractor fails to achieve theprogress which will lead to the issuance of Notice under Sub Clause 15.2.
• ‘Special Meeting’ was held on the 6th April 2018 with the participation of Ranken’s Sri Lanka General Manager, Mr. Liao Kui where theChairman has provided clear direction to overcome the situations, catchup on the delays, Ranken to resolve their cash flow problems, failingwhich, the client will take the contractual remedy to terminate the contract under Sub Clause 15.2. A recent ‘Special Meeting “ onTermination – Sub-Clause 15.2 was held on the 01st June 2018.
• Non-Compliance to the above Notices, non compliance to the discussions and directions provided in the Monthly Progress review Meetingsto speed up the works and to restart the works at all the roads that has been abandoned, to complete all the works as per the schedule andPCC Meetings discussions and direction has lead to the Non-Performance of the contractor Ranken.
• Adequate time till now to show progress by providing you with an opportunity to put right previous identified contractual failures inachieving the progress as scheduled has been provided but Ranken has failed to achieve the progress and to catch up on the delays.
Contract KU5 - Progress Photographs
Before Construction Lined Drain Construction at Road ID 99 3+660 km
Before Construction Asphalt Compaction at Road ID 70 7+520 km
Road Work Progress – iROAD - Kurunegala District
Package No. Contractor No. of RoadsTotal Road Length
(km)No. of Roads Civil Works in
ProgressRoad Length Civil Works in
Progress (km)
KU1 MAGA 16 82.62 14 74.62
KU2 KDAW-BMG JV 19 100.00 17 78.66
KU3 Ranken Group 12 99.00 8 50.04
KU4 VVK & Co. 12 97.10 9 48.32
KU5 Ranken Group 17 99.86 10 41.47
Total 76 478.58 58 293.11
82.62
100.00
99.00
97.10
99.86
74.62
78.66
50.04
48.32
41.47
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00
KU1
KU2
KU3
KU4
KU5
Road Length (km)
Co
ntr
act
Pa
cka
ge
Road Length Civil Works in Progress (km)
Total Road Length (km)
Progress Summary of Culverts & Bridges - iROAD-Kurunegala District
DistrictPackage
No.Contractor
Total No. of Culvert
No. of Culvert No. of Culvert
New / Reconstruction / Widening
Completed / In
progress
Cleaning & Repair
Completed / In
progress
Kurunegala
KU1 MAGA 317 149 132 152 58
KU2 KDAW-BMG JV 444 174 130 262 70
KU3 Ranken Group 498 73 48 424 103
KU4 VVK & Co. 336 101 52 238 51
KU5 Ranken Group 407 186 53 215 27
Total 2002 683 415 1291 309
Overall Financial Status - iROAD-Kurunegala District
Package No. ContractorAccepted Contract Amount
(LKR)
Total Certified Amount to Date (LKR) (Including Advance
Payment)
KU1 MAGA 2,005,790,082.72 1,208,515,441.95
KU2 KDAW-BMG JV 2,124,166,266.00 1,212,416,824.47
KU3 Ranken Group 1,976,721,917.95 871,904,478.46
KU4 VVK & Co. 2,091,174,540.00 795,606,601.51
KU5 Ranken Group 1,996,560,050.43 778,018,073.48
Total 10,194,412,857.10 4,866,461,419.87
Status of GRC Committee Formation Kurunegala District – NWP
Contract No. Contractor No. of RoadsNo. of
DivisionsNo. of GRC (Level
3 - DS) formedNo. of GRC (Level 2 -
GN) formed
KU1 MAGA 16 6 6 17
KU2 KDAW-BMG JV 19 7 8 23
KU3 Ranken 12 6 6 16
KU4 VVK & Co. 12 6 8 12
KU5 Ranken 17 10 10 18
TOTAL 76 35 38 86
List of Utilities - iROAD-Kurunegala District
Package No.
No. of Roads
No. of Roads Surveyed for
Utility Shifting
Utilities to be Shifted
Electricity Pole / (Nos.) Telecom Pole / (Nos.) Water Line / (m)
Identified Progress Identified Progress Identified Progress
KU1 16 16 12 9 27 11 8500 6100
KU2 19 17 15 6 31 6 1000 1000
KU3 12 12 4 3 21 20 570 414
KU4 12 12 - - 2 2 587 201
KU5 17 17 7 - 10 0 400 -
Summary of Public Complaints - iROAD-Kurunegala District
DistrictPackage
No.
Public Complaints Received
TotalNo.
Attended
No. Completely
Settled
Solutions in Progress
No. UnattendedNo. of
RequestNo. of
SuggestionNo. of
Complaints
No. of Crack related issues
Ku
run
egal
a
KU1 157 2 15 1 175 175 160 14 1
KU2 377 8 49 11 445 445 402 39 -
KU3 59 2 13 3 77 77 67 10 -
KU4 24 6 9 3 42 42 41 1 -
KU5 5 - 9 4 18 18 13 5 -
Total 622 18 95 22 757 757 683 69 1
Project Location Maps – Puttalam District
Package Road Length (km)
PU1 91.96
PU2 73.51
PU3 48.43
TOTAL 213.90
Summary of Progress-Survey/Investigation & Design in PU1
Description
To
tal
Le
ng
th (
km
) Horizontal Alignment
Initial Cross section
InvestigationPavement
DesignVertical
AlignmentDesign Cross
Section
Road No.
Su
bm
itte
d
Ap
pro
ve
d
Su
bm
itte
d
Ap
pro
ve
d
Te
st p
it
La
b T
est
ing
Re
po
rt
Su
bm
itte
d
Ap
pro
ve
d
Su
bm
itte
d
Ap
pro
ve
d
Su
bm
itte
d
Ap
pro
ve
d
1 12.20 12.20 12.20 12.20 12.20 12.20 12.20 12.20 12.20 12.20 12.20 12.20 11.00 11.00
12 7.17 7.17 7.17 6.61 6.61 7.17 7.17 7.17 7.17 7.17 6.61 6.61 6.61 0.18
14 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 2.60 2.60 0.25
15 7.26 7.26 7.26 7.26 7.26 7.26 7.26 7.26 7.26 7.26 7.26 7.26 1.59 1.52
Note: Road ID No. 11, 5, 6, 7, 8, 43, 44 Completed.
Progress of Road Work Bar Chart in PU1
Earthwork in progress ABC Completed Asphalt Completed
Note: Road ID No. 12, 15 Earth Work Construction Still Has Not
Started.
Serial No
DS.DivisionRoad
IDRoad Name
Road Catogory
Length (Km)
Progress Up to End of May 2018
1 km 2 km 3 km 4 km 5 km 6 km 7 km 8 km 9 km 10 km 11 km 12 km 13 km 14 km
1 Puttalam 8Sirambiadiya, 4th Mile Post, Manaweriya, Sellakandal area
PS 7.27
2
Nawagathtthegama
6Internal Road at Nawagaththegama -Galgamuwa Road
PRDD 3.00
3 5Welewewa Garment Junction -Tharanagahawewa - Rajawegama Road
PS 12.25
4
Karuwalagaswewa
7 Saliyawewa Junction to Neelabemma Road PRDD 13.00
5 43 Thabbowa, Karuwalagaswewa, Outer Circle PRDD 13.11
6 44 Milankuluma -Thabbowa Temple Junction PRDD 7.06
7 Anamaduwa 1 Mahauswewa-Waththegedara-Thalgaswewa PRDD 12.20
8
Wanathawillu
11 Wanathawillu - Morapothawa School PS 7.05
9 14 Thehili - Aththala Internal Road PS 3.50
Physical Progress of Plan Work in PU1
Mo
nth
s
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Fe
b-1
7
Ma
r-1
7
Ap
r-1
7
Ma
y-1
7
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-1
7
De
c-1
7
Jan
-18
Fe
b-1
8
Ma
r-1
8
Ap
r-1
8
Ma
y-1
8
Jun
-18
Jul-
18
Original Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
3%
0.2
0%
1.4
0%
4.3
5%
7.3
0%
12
.42
%
14
.98
%
20
.26
%
25
.59
%
31
.56
%
36
.87
%
43
.29
%
49
.62
%
56
.23
%
62
.38
%
68
.83
%
75
.98
%
82
.87
%
85
.46
%
90
.44
%
96
.35
%
99
.98
%
Revised Planned
Progress Monthly
(%) 0.0
0%
0.0
7%
0.1
5%
0.3
8%
1.3
7%
3.0
3%
5.4
1%
9.8
6%
12
.26
%
14
.08
%
18
.06
%
21
.28
%
24
.77
%
28
.44
%
31
.10
%
35
.43
%
40
.50
%
46
.81
%
54
.74
%
63
.24
%
71
.80
%
80
.53
%
89
.75
%
10
0.0
0%
Actual Progress
Monthly (%) 0.0
0%
0.0
0%
0.0
9%
0.3
8%
1.5
5%
2.1
1%
4.6
7%
9.8
6%
12
.26
%
14
.64
%
18
.62
%
21
.28
%
24
.77
%
28
.44
%
31
.09
%
35
.51
%
38
.44
%
41
.74
%
43
.38
%
47
.32
%
51
.14
%
51
.28
%
Delay Progress (%)
0.0
0%
-0.0
7%
-0.0
6%
0.0
0%
0.1
8%
-0.9
2%
-0.7
4%
0.0
0%
0.0
0%
0.5
6%
0.5
6%
0.0
0%
0.0
0%
0.0
0%
-0.0
1%
0.0
8%
-2.0
6%
-5.0
7%
-11
.36
%
-15
.92
%
-20
.66
%
-29
.25
%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Au
g-1
6
Se
p-1
6
Oct
-16
No
v-1
6
Dec
-16
Jan-
17
Feb
-17
Mar
-17
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Se
p-1
7
Oct
-17
No
v-1
7
Dec
-17
Jan-
18
Feb
-18
Mar
-18
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Original Planned Progress Monthly (%) Revised Planned Progress Monthly (%) Actual Progress Monthly (%)
PU1 Total (Up to May - 18)Description Up to Dec - 17 Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment 53.50 0.50 6.00 5.89 0.00 0.00 65.89
Sub base 45.80 2.00 3.80 6.00 0.00 0.00 57.60
A.B.C 33.99 6.70 3.00 4.09 2.01 5.92 55.71
Prime 30.65 4.78 3.76 3.74 4.80 0.00 47.73
Asphalt(Total Length 91.96 km)
30.43 4.75 0.00 2.46 8.17 0.00 45.81
0.00
2.00
4.00
6.00
8.00
10.00
Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment Sub base A.B.C Prime Asphalt
Progress Up to 19.06.2018 – PU1
Road
ID
Road
Length
(km)
Starting DateAbandoned
Date
Restarting
Date
Material stock /
(Cube) available
on site
Remarks
ID 08 7.27 23-Sep-16 06-Apr-18No Work (Asphalt Completed & incidental work to be
completed)
ID 43 13.11 20-Sep-16 03-Apr-18No Work (Asphalt Completed. Concrete Pavement &
incidental work to be completed)
ID 44 7.02 21-Sep-16 04-Apr-18No Work (Asphalt Completed. Incidental work to be
completed)
ID 07 13.00 03-Oct-16 02-May-18No Work (Asphalt Completed. Incidental work to be
completed)
ID 05 12.01 08-Sep-17ABC-2000,
Sub Base-1000
Asphalt completed from 8+000 to 12+010, Shoulder laying &
ABC work is going on
ID 01 12.20 22-July-17Asphalt completed on 18th June 2018, concrete sections to be
done
ID 14 3.50 25-May-18 ABC – 18 ABC Laying & Finishing
ID 06 3.00 06-Sep-17 05-Feb-18No Work (Structures works & Embankment work
Completed)
ID 11 7.05 28-Mar-18 Structures works going on
ID 15 7.26 Not Started
ID 12 7.17 Not Started
Physical Progress –PU1
Progress
Cumulative Status as at 30th
April 2018Cumulative Status as at 31st May
2018
Target (%) Actual (%) Target (%) Actual (%)
Physical 71.80% 51.14% 80.53% 51.28%
Payments Certified –PU1
Description Certified Amount (LKR)
Accepted Contract Amount 1,706,320,523.61
Up to Cumulative Certified Amount 767,490,199.39
TL’s Comments – PU1
• Rate of Progress ( Sub-Clause 8.6 of GCC) issued on 02.06.17 , letter ref. no. iROAD/PIC-02/Ranken/PU1/01/1051
• Notice to Correct (Clause 15.1 of GCC) will be issued after observing the progress in the coming week as there was no progressfor Embankment and Subbase work in April 2018 and May 2018, other than laying of ABC of 5.25km in length in May 2018.
• Delay of works has been thoroughly discussed in all the Monthly Progress Review Meetings where direction, advise and thedelays were identified for Ranken to speed up the works and catch up on the delays and the same was discussed in the PCCMeetings.
• Numerous ‘Special Meetings’ were conducted with the Chairman on Delays of Ranken for all their contracts, where it wasstressed of the serious situation with the progress, for the contractor to catch up on the progress and the consequences if thecontractor fails to achieve the progress which will lead to the issuance of Notice under Sub Clause 15.2.
• The last of such ‘Special Meeting’ was held on the 6th April 2018 with the participation of Ranken’s Sri Lanka General Manager,Mr. Liao Kui where the Chairman has provided clear direction to overcome the situations, catchup on the delays, Ranken toresolve their cash flow problems, failing which, the client will take the contractual remedy to terminate the contract under SubClause 15.2.
• Non-Compliance to the above Notices, non compliance to the discussions and directions provided in the Monthly Progressreview Meetings to speed up the works and to restart the works at all the roads that has been abandoned, to complete all theworks as per the schedule and PCC Meetings discussions and direction has lead to the Non-Performance of the contractorRanken.
Contract PU1 - Progress Photographs
Before Construction Sub Base Construction at Road ID 05 7+900 km
Before Construction ABC Construction at Road ID 05 8+900 km
Contract PU1 - Flooding Photographs
Road ID 08 at 0+000 - 2+500 km
Road ID 08 at 0+000 - 2+500 km Road ID 08 at 2+620 km
Road ID 44 at 1+280 km Road ID 43 at 9+100 km Road ID 43 at 8+400km
Road ID 43 at 8+230 km Road ID 43 at 6+960 - 7+160 km Road ID 43 at 6+490 km
Summary of Progress-Survey/Investigation & Design in PU2
Description
To
tal
Le
ng
th (
km
) Horizontal Alignment
Initial Cross section
InvestigationPavement
DesignVertical
AlignmentDesign Cross
Section
Road No.
Su
bm
itte
d
Ap
pro
ve
d
Su
bm
itte
d
Ap
pro
ve
d
Te
st p
it
La
b T
est
ing
Re
po
rt
Su
bm
itte
d
Ap
pro
ve
d
Su
bm
itte
d
Ap
pro
ve
d
Su
bm
itte
d
Ap
pro
ve
d
26 10.95 10.95 10.95 10.95 10.95 10.95 10.95 10.95 10.95 10.95 10.92 10.92 10.92 10.92
Note: Road ID No. 13, 2, 3, 28, 30, 45, 4, 9, 27, 29, Completed.
Progress of Road Work Bar Chart in PU2
Earthwork in progress ABC Completed Asphalt Completed
Note: Road ID No. 13, 2, 45, 28, 30 Earth Work Construction
Still Has Not Started.
Serial No
DS.DivisionRoad
IDRoad Name
Road Catogory
Length (Km)
Progress Up to End of May 2018
1 km 2 km 3 km 4 km 5 km 6 km 7 km 8 km 9 km 10 km 11 km 12 km 13 km
1 Pallama 3 Adammana Juncition to Madawakkulama Road PS 9.83
2Mahakubukkada
wala4 Mahakubukkadawala Kottukachchiya Road PRDD 12.40
3 Puttalam 9 Madyama Attavilluwa to Kiula Road PS 3.67
4
Arachikattuwa
26 Arachikattuwa to Pallama via Adippala PRDD 10.95
5 27Nalladurankattuwa to Wendakaduwa via Aththanaganyaya
PRDD 12.56
6 Chilaw 29Thiththakade to Manuwangama via Thissogama Co-operative Shop
PRDD 5.38
Physical Progress of Plan Work in PU2
Mo
nth
s
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Fe
b-1
7
Ma
r-1
7
Ap
r-1
7
Ma
y-1
7
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-1
7
De
c-1
7
Jan
-18
Fe
b-1
8
Ma
r-1
8
Ap
r-1
8
Ma
y-1
8
Jun
-18
Jul-
18
Original Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.1
6%
0.8
2%
3.8
8%
8.5
5%
14
.88
%
21
.98
%
30
.29
%
38
.05
%
44
.99
%
51
.33
%
57
.40
%
61
.42
%
64
.81
%
70
.51
%
78
.80
%
85
.84
%
91
.08
%
96
.11
%
10
0.0
0%
Revised Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.0
0%
0.0
7%
0.1
3%
0.4
0%
0.6
7%
1.7
2%
3.4
9%
4.0
5%
6.3
0%
9.1
6%
11
.98
%
15
.14
%
23
.11
%
31
.06
%
36
.77
%
47
.68
%
57
.59
%
67
.29
%
74
.83
%
83
.26
%
91
.59
%
10
0.0
0%
Actual Progress
Monthly (%) 0.0
0%
0.0
0%
0.0
0%
0.0
7%
0.1
3%
0.4
0%
0.6
7%
1.7
2%
3.4
9%
4.0
5%
6.3
0%
9.1
6%
11
.98
%
14
.79
%
17
.60
%
20
.16
%
24
.49
%
26
.38
%
26
.84
%
29
.64
%
30
.13
%
30
.21
%
Delay Progress (%)
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
-0.3
5%
-5.5
1%
-10
.90
%
-12
.28
%
-21
.30
%
-30
.75
%
-37
.65
%
-44
.70
%
-53
.05
%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Au
g-1
6
Se
p-1
6
Oct
-16
No
v-1
6
Dec
-16
Jan-
17
Feb
-17
Mar
-17
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Se
p-1
7
Oct
-17
No
v-1
7
Dec
-17
Jan-
18
Feb
-18
Mar
-18
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Original Planned Progress Monthly (%) Revised Planned Progress Monthly (%) Actual Progress Monthly (%)
PU2 Total (Up to May - 18)Description Up to Dec - 17 Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment 22.17 6.17 0.00 1.25 1.60 0.90 32.09
Sub base 24.19 3.83 0.67 1.35 0.93 0.12 31.09
A.B.C 17.47 4.14 2.38 1.24 0.00 0.00 25.23
Prime 20.04 0.96 0.28 3.26 0.00 0.00 24.54
Asphalt(Total Length 73.51 km)
17.68 1.62 0.00 2.63 0.60 0.00 22.53
0.00
2.00
4.00
6.00
8.00
Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment Sub base A.B.C Prime Asphalt
Progress Up to 19.06.2018 – PU2
Road
ID
Road
Length
(km)
Starting DateAbandoned
Date
Restarting
Date
Material stock /
(Cube) available
on site
Remarks
ID 02 6.73 Not Started
ID 03 9.83 01-Aug-16 10-Feb-18 - ABC-106 No Work (Machines, Labours and staff not available at site)
ID 04 12.34 23-June-17 -ABC-330
Gravel-1545
ABC Laying, Shoulder work. (19/06/2018 - fuel not available
at site)
ID 09 3.67 05-Nov-17 20-May-18 - Gravel-530 No Work (Sub-contractor left due to payment problem)
ID 13 6.13 Not Started
ID 26 10.91 01-Aug-16 31-Dec-17 - Gravel-3533 No Work (Machines, Labours and staff not available at site)
ID 27 12.52 01-Aug-16ABC-600
Gravel-2235
ABC Laying, Sub base laying. (19/06/2018 - fuel not
available at site)
ID 28 1.97 Not Started
ID 29 5.30 04-July-17 10-Feb-18 - ABC-708 No Work (Structure work started, 5 culvert completed)
ID 30 3.02 Not Started
ID 45 1.75 Not Started
Physical Progress –PU2
Progress
Cumulative Status as at 30th
April 2018Cumulative Status as at 31st May
2018
Target (%) Actual (%) Target (%) Actual (%)
Physical 74.83% 30.13% 83.26% 30.21%
Payments Certified –PU2
Description Certified Amount (LKR)
Accepted Contract Amount 1,463,917,284.00
Up to Cumulative Certified Amount 663,780,357.45
Contract PU2 - Progress Photographs
Sub Base Construction at Road ID 090+950 km
Sub Base Construction at Road ID 2710+825 km
Edge Widening at Road ID 2710+910 km
Sub Base Compaction at Road ID 2710+880 km
Contract PU2 - Progress Photographs
Sub Base Construction at Road ID 2711+860 km
Sub Base Compaction at Road ID 27
Contract PU2 - Flooding Photographs
Road ID 04 at 2+768 km Road ID 09 at 2+170 km Road ID 09 at 1+943 km
Road ID 03 at 6+520 - 6+560 km Road ID 03 at 6+600 - 6+628 km
Road ID 03 at 7+100 - 7+160 km
Road ID 03 at 8+290 km Road ID 03 at 8+394 - 8+420 km Road ID 03 at 8+760 - 8+775 km
Contract PU2 - Flooding Photographs
Road ID 03 at 8+810 - 8+820 km Road ID 03 at 8+905 - 8+920 km Road ID 03 at 9+000 - 9+024 km
Road ID 03 at 9+090 - 9+115 km Road ID 26 & 27
Summary of Progress-Survey/Investigation & Design in PU3
Description
To
tal
Le
ng
th (
km
) Horizontal Alignment
Initial Cross section
InvestigationPavement
DesignVertical
AlignmentDesign Cross
Section
Road No.
Su
bm
itte
d
Ap
pro
ve
d
Su
bm
itte
d
Ap
pro
ve
d
Te
st p
it
La
b T
est
ing
Re
po
rt
Su
bm
itte
d
Ap
pro
ve
d
Su
bm
itte
d
Ap
pro
ve
d
Su
bm
itte
d
Ap
pro
ve
d
21 6.85 6.78 6.78 6.78 6.78 6.85 6.85 6.85 6.85 6.78 6.78 6.78 6.78 6.53
24 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.48 1.48
32 2.40 2.40 2.40 2.40 2.40 2.40 2.40 2.40 2.40 2.40 2.40 2.40 2.38 2.38
36 4.29 4.29 4.29 4.29 4.29 4.29 4.29 4.29 2.90 2.90 2.90 2.90 2.90 2.00
39 1.85 1.85 1.85 1.85 1.85 1.85 1.85 1.85 1.85 1.85 1.85 1.85 1.84 1.84
41 3.38 3.38 3.38 2.28 2.28 3.38 3.38 3.38 3.38 3.38 2.28 2.28 2.28 2.27
42 2.44 2.44 2.44 2.44 2.44 2.44 2.44 2.44 2.44 2.44 2.44 2.44 2.43 2.43
Note: Road ID No. 16, 31, 33, 40 Completed.
Progress of Road Work Bar Chart in PU3
Earthwork in progress ABC Completed Asphalt Completed
Note: Road ID No. 17, 22, 24, 38 Earth Work
Construction Still Has Not Started.
Serial No
DS.DivisionRoad
IDRoad Name
Road Category
Length (Km)
Progress Up to End of May 2018
1 km 2 km 3 km 4 km 5 km 6 km 7 km
1
Madampe
31 Madampe Ihalagama Road PS 1.69
2 32 Suduwella Junction to Mukunuwatawana Road PS 2.40
3 Nattandiya 16 Megahawilla Junction to Yakkdessawa Primary School Road PRDD 2.65
4 Mahawewa 21Waduraba BO Tree to Walahapitiya Cemetery via Muttibadivila Post office Road
PRDD 6.85
5
Wennappuwa
33 Srigampola Church to Zinnor Juncion via Aubowan Junction PRDD 2.89
6 34Weralugaha road Balldi junction Bandaranayake janapadaya to Dummaladeniya Haldaduwana Road
PRDD 4.26
7 36 Bandirippuwa-Kirimetiyana Jerad mawatha to end of Jaya Mawatha PRDD 4.29
8
Dankotuwa
39 Atiyawela Road (North) PRDD 1.85
9 40 Atiyawela Mohottimulla Road PRDD 2.91
10 41 Kirimatiyana Varalla Watta Road PRDD 3.38
11 42 Morukkuliya to Dankotuwa PRDD 2.44
Physical Progress of Plan Work in PU3
Mo
nth
s
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Fe
b-1
7
Ma
r-1
7
Ap
r-1
7
Ma
y-1
7
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-1
7
De
c-1
7
Jan
-18
Fe
b-1
8
Ma
r-1
8
Ap
r-1
8
Ma
y-1
8
Jun
-18
Jul-
18
Original Planned
Progress Monthly
(%) 0.0
0%
0.0
2%
0.1
4%
0.2
9%
0.5
3%
1.4
3%
2.6
9%
7.0
3%
9.8
7%
15
.75
%
22
.72
%
30
.54
%
38
.57
%
47
.46
%
55
.22
%
61
.87
%
67
.99
%
75
.62
%
82
.58
%
87
.04
%
90
.42
%
94
.71
%
98
.13
%
10
0.0
0%
Revised Planned
Progress Monthly
(%) 0.0
0%
0.0
0%
0.1
4%
0.4
1%
0.5
5%
1.6
0%
2.7
1%
4.2
3%
5.1
7%
7.6
4%
9.6
7%
11
.22
%
12
.89
%
16
.56
%
23
.41
%
30
.33
%
38
.07
%
46
.59
%
55
.36
%
64
.26
%
71
.46
%
80
.70
%
90
.30
%
10
0.0
0%
Actual Progress
Monthly (%) 0.0
0%
0.0
0%
0.1
4%
0.4
1%
0.5
5%
1.6
0%
2.7
1%
4.2
3%
5.1
7%
7.6
4%
9.6
7%
11
.22
%
12
.89
%
15
.60
%
17
.44
%
21
.81
%
25
.46
%
28
.03
%
28
.33
%
30
.44
%
30
.99
%
31
.31
%
Delay Progress (%)
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
-0.9
6%
-5.9
7%
-8.5
2%
-12
.61
%
-18
.56
%
-27
.03
%
-33
.82
%
-40
.47
%
-49
.39
%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Au
g-1
6
Se
p-1
6
Oct
-16
No
v-1
6
Dec
-16
Jan-
17
Feb
-17
Mar
-17
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Se
p-1
7
Oct
-17
No
v-1
7
Dec
-17
Jan-
18
Feb
-18
Mar
-18
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Original Planned Progress Monthly (%) Revised Planned Progress Monthly (%) Actual Progress Monthly (%)
PU3 Total (Up to May - 18)Description Up to Dec - 17 Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment 11.58 1.30 0.00 0.75 0.25 0.57 14.45
Sub base 16.83 3.26 0.26 0.00 0.20 0.43 20.98
A.B.C 16.25 1.81 0.40 1.00 0.15 0.47 20.08
Prime 15.11 2.53 0.46 0.84 0.60 0.34 19.88
Asphalt(Total Length 48.43 km)
13.54 1.59 0.00 2.12 0.00 0.00 17.25
0.00
2.00
4.00
Jan-18 Feb-18 Mar-18 Apr - 18 May-18
Embankment Sub base A.B.C Prime Asphalt
Progress Up to 19.06.2018 – PU3
Road
ID
Road
Length
(km)
Starting DateAbandoned
Date
Restarting
Date
Material stock /
(Cube) available
on site
Remarks
ID 16 2.65 16-Jan-17 19-Feb-18No Work (Asphalt Completed & incidental work to be
completed)
ID 17 3.90 28-Oct-17 11-May-18 ABC-28 One Culvert Backfilling (Minor work)
ID 21 6.85 02-Nov-17 ABC-100ABC work, One Box Culvert Construction, Roadway
Excavations
ID 22 5.10 Not started No Work
ID 24 1.49 Not started No Work
ID 31 1.69 20-July-17 21-Dec-17 No Work (Asphalt Completed)
ID 32 2.40 28-Mar-17 19-May-18 02-June-18 Soil-100Structure work at 2 Culvert (R/F + F/W + Deck Concrete +
Base Concrete)
ID 33 2.89 25-Oct-17 08-Apr-18 13-June-18 ABC-247 ABC work
ID 34 4.26 10-Jan-18 11-May-18 31-May-18 ABC work
ID 36 4.29 04-Dec-17 06-Apr-18 No Work
ID 38 2.33 Not started No Work
ID 39 1.85 20-Apr-17 08-Nov-17No Work (Asphalt Completed, Concrete pavement & 2
culverts to be completed)
ID 40 2.91 22-Dec-16 25-Nov-17No Work (Asphalt Completed, Shoulder works & incidental
work to be completed)
ID 41 3.38 04-Oct-17 19-Mar-18 No Work (2km Asphalt Completed)
ID 42 2.44 03-July-17 16-Feb-18No Work (Asphalt Completed, Concrete Pavement &
incidental work to be completed)
Physical Progress –PU3
Progress
Cumulative Status as at 30th
April 2018Cumulative Status as at 31st May
2018
Target (%) Actual (%) Target (%) Actual (%)
Physical 71.46% 30.99% 80.70% 31.31%
Payments Certified –PU3
Description Certified Amount (LKR)
Accepted Contract Amount 1,210,355,904.00
Up to Cumulative Certified Amount 490,134,011.10
Contract PU3 - Progress Photographs
Edge Widening at Road ID 340+100 km
Edge Widening at Road ID 340+150 km
Surface Cleaning for Priming at Road ID 210+250 km
Priming at Road ID 210+450 km
Contract PU3 - Progress Photographs
Priming at Road ID 210+250 km
Concreting of Widening Culvert at Road ID 17 0+700 km
Contract PU3 - Flooding Photographs
Road ID 40 at 2+068 km Road ID 40 at 2+068 - 2+120 km Road ID 40 at 2+068 - 2+120 km
Road ID 40 at 2+200 km
Road Work Progress – iROAD - Puttalam District
Package No. Contractor No. of RoadsTotal Road Length
(km)No. of Roads Civil
Works in ProgressRoad Length Civil Works in
Progress (km)
PU1 Ranken Group 11 91.96 9 70.89
PU2 VVK & Co. 11 73.51 6 52.31
PU3 VVK & Co. 15 48.43 11 22.98
Total 37 213.9 26 146.18
91.96
73.51
48.43
70.89
52.31
22.98
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00
PU1
PU2
PU3
Road Length (km)
Co
ntr
act
Pa
cka
ge
Road Length Civil Works in Progress (km)Total Road Length (km)
Progress Summary of Culverts & Bridges - iROAD-Puttalam District
DistrictPackage
No.Contractor
Total No. of Culvert
No. of Culvert No. of Culvert
New / Reconstruction / Widening
Completed / In
progress
Cleaning & Repair
Completed / In
progress
Puttalam
PU1 Ranken Group 232 114 91 117 18
PU2 VVK & Co. 255 126 42 126 63
PU3 VVK & Co. 124 79 25 63 6
Total 611 319 158 306 87
Overall Financial Status - iROAD- Puttalam District
Package No. ContractorAccepted Contract Amount
(LKR)
Total Certified Amount to Date (LKR) (Including Advance
Payment)
PU1 Ranken Group 1,706,320,523.61 767,490,199.39
PU2 VVK & Co. 1,463,917,284.00 663,780,357.45
PU3 VVK & Co. 1,210,355,904.00 490,134,011.10
Total 4,380,593,711.61 1,921,404,567.94
Status of GRC Committee Formation Puttalam District - NWP
Contract No. Contractor No. of RoadsNo. of
DivisionsNo. of GRC (Level
3 - DS) formedNo. of GRC (Level 2 -
GN) formed
PU1 Ranken 11 6 6 9
PU2 VVK & Co. 11 7 7 11
PU3 VVK & Co. 15 5 5 15
TOTAL 37 18 18 35
List of Utilities - iROAD-Puttalam District
Package No.
No. of Roads
No. of Roads Surveyed for
Utility Shifting
Utilities to be Shifted
Electricity Pole / (Nos.) Telecom Pole / (Nos.) Water Line / (m)
Identified Progress Identified Progress Identified Progress
PU1 11 9 24 19242 Nos. Pipe
Crossing238 Nos.
completed
PU2 11 10 52 Nos. shifted
18 814 Nos. Road
Crossing to be completed
All road crossing
completed
PU3 15 15 18 in progress 22 in progress 4 in progress
Summary of Public Complaints - iROAD-Puttalam District
DistrictPackage
No.
Public Complaints Received
TotalNo.
Attended
No. Completely
Settled
Solutions in Progress
No. UnattendedNo. of
RequestNo. of
SuggestionNo. of
Complaints
No. of Crack related issues
Pu
ttal
am
PU1 67 - - - 67 50 38 12 17
PU2 35 - 16 11 62 59 53 9 -
PU3 20 - 26 - 46 46 34 12 -
Total 122 0 42 11 175 155 125 33 17
Safeguard – Environmental & Social
❖ 218 Site Specific Environmental Management Action Plans (SSEMAPs)
Approved/Commented.
❖ 204 Environmental Monitoring Check lists (EMC’s) for preconstruction, 96 at 25%, 108 at
50% and 46 at 75% of construction stage approved/Commented.
❖ Participated in a joined site visit to observe RD ID 12 of PU1 to obtain condition of Wiled Life
Department.
❖ RD ID 12 (Gangewadiya) of PU1 (which stretchers close to buffer zone of Wilpaththuwa
National Park) observed jointly with PD/NWP, AD/DWLC, RFO/FD, ES & PM.
❖ 4 Awareness programmes for DSESA’s were conducted at district level on post construction
stage SSEMAP’s & EMC’s preparation.
❖ One GN level GRC meeting has been held during May 2018 to resolve public complaints and
discuss public requests in Rd ID 86 of KU1 of NWP.
❖ GN level GRC Committee was formed at Kalpitiya for Rd 14 & 15 on 8th and 10th May.
❖ Due to the requests came from public to improve road shoulders, bends, embankments of
roads and new lead ways for drains, additional land strips have been taken from adjoining
land owners with 481 consent letters from NWP and 195 consent letters from NCP as at end
Package No
Contractor
Accepted Contract Amount/
(Rs. Million)
No.of Roads
Road Length/
(Km)
No.of Roads; Civil
Works in Progress
Asphalt Completed
/(Km)
Physical Progress as at 30 April-2018
Actual(%)
Physical Progress; Cumulative Status up to end of May-2018 /
(%)
Target Actual
G1K.D.Ebert & Sons Holdings (Pvt.) Ltd
1,458 15 64.6 15 49.1 75.0 100.0 75.5
G2K.D.A. Weerasinghe & Co (Pvt) Ltd
1,483 22 66.0 22 66.0 98.0 100.0 99.0
G3K.D.A. Weerasinghe & Co(Pvt) Ltd
1,733 29 73.2 29 73.2 97.0 100.0 99.0
M1CML-MTD Construction Ltd
2,315 22 97.5 22 97.2 99.0 100.0 99.0
M2K.D.Ebert & Sons Holdings (Pvt.) Ltd
1,803 19 69.2 19 54.5 82.0 100.0 83.0
M3K.D.Ebert & Sons Holdings (Pvt.) Ltd
1,208 25 53.4 25 52.8 99.0 100.0 99.0
H1K.D.A. Weerasinghe & Co (Pvt) Ltd
1,584 19 67.1 19 67.1 95.0 100.0 96.0
H2CML-MTD Construction Ltd
1,210 18 58.0 18 58.0 100.0 100.0 100.0
H3R.R Construction. (Pvt.) Ltd
1,052 14 41.9 14 41.9 100.0 100.0 100.0
Total 13,847 183 590.9183/
(590.9km)559.8
(94.7%)93.6 100.0 94.3
Overall Physical Progress Summary – iROAD-Southern Province /(up to end of May 2018)
302
Summary of Monthly Work done – Asphalt + Concrete Pavement
303
G1 G2 G3 M1 M2 M3 H1 H2 H3
KDE KDAW KDAW CML KDE KDE KDAW CML RR
Neluwa Galle Elpitiya Deniyaya Akuressa Weligama Ambalantota Tangalle Middeniya
0.0 0.0 0.0 2.3 0.0 0.2 1.3 0.3 - 4.0 535.1 7
3.3 0.0 0.0 1.9 0.1 0.4 0.3 - - 6.0 541.1 40
2.5 0.0 0.0 0.7 1.4 0.3 1.6 - - 6.5 547.6 102
2.1 0.4 0.2 0.8 2.1 0.4 1.3 - - 7.3 554.9 283
1.1 - - 1.8 0.3 0.7 - - - 3.9 558.9 174
0.0 - - 0.3 0.7 0.0 - - - 1.0 559.8 178
49.1 66.0 73.2 97.2 54.5 52.8 67.1 58.0 41.9
(76%) (100%) (100%) (99.7%) (79%) (99%) (100%) (100%) (100%)
75.5% 99.0% 99.0% 99.0% 83.0% 99.0% 96.0% 100.0% 100.0%
64.6 66.0 73.2 97.5 69.2 53.4 67.1 58.0 41.9
63.6 61.8 71.7 96.9 65.7 54.9 70.9 58.6 41.4 m
15.5 0.0 0.0 0.3 14.7 0.6 0.0 0.0 0.0
2.0 2.6 3.1 3.6 2.2 2.2 2.3 2.4 1.9
30-Oct-18 31-Mar-18 31-Mar-18 31-May-18 31-Aug-18 15-Jun-18 31-Mar-18 31-Oct-17 30-Sep-17
1.1 3.0 6.8 3.1 2.0 0.2
31-Dec-18 31-Jul-18 31-Jul-18 30-Sep-18 31-Dec-18 31-Oct-18 31-Jul-18 31-Dec-17 31-Oct-17
16.2Existing Good
Balance Paving Length
BOQ Package Length
Mar-18
Actual Package Length
Physical Progress
94.7%
590.9
31.1
94.3%
Opt.Prod.Rate
585.5
Target paving
Completion Date
2.5
Asphalt + Concrete Paving Completed Length /(km)
Close Office by
Total
(Percentage)
Apr-18
May-18
Monthly
IPC-SP
/Rs.Million
Jan-18
Dec-17
Total/
(Monthly)
Total
/(Cumulative)
559.8 11,949
Feb-18
Period
Package/Area
Package NoContractor Accepted Contract
Amount/ (Rs. Million)Total Certified
Amount/(Rs. Million)
G1 K.D.Ebert & Sons Holdings (Pvt.) Ltd 1,458 861
G2 K.D.A. Weerasinghe & Co (Pvt) Ltd 1,483 1,390
G3 K.D.A. Weerasinghe & Co (Pvt) Ltd 1,733 1,636
M1 CML-MTD Construction Ltd 2,315 2,451
M2 K.D.Ebert & Sons Holdings (Pvt.) Ltd 1,803 1,092
M3 K.D.Ebert & Sons Holdings (Pvt.) Ltd 1,208 928
H1 K.D.A. Weerasinghe & Co (Pvt) Ltd 1,584 1,342
H2 CML-MTD Construction Ltd 1,210 1,238
H3 R.R Construction. (Pvt.) Ltd 1,052 1,012
Total 13,847 11,949(86%)
Overall Financial Status –iROAD-Southern Province /(up to end of May-2018)
304
Progress of Culverts & Bridges
DistrictPackage
NoContractor
No.of Culvers No.of Culvers Bridges
New / Re -Construction/
Widening
Completed / in Progress
RepairCompleted / in Progress
Total /Nos.
Under Design
Construction in Progress/Completed
Galle
G1K.D.Ebert & Sons Holdings (Pvt.) Ltd
210 135 214 110 2 - 1
G2K.D.A. Weerasinghe & Co (Pvt) Ltd
271 269 204 198 6 - 6
G3K.D.A. Weerasinghe & Co(Pvt) Ltd
184 184 248 232 15 - 8
Matara
M1 CML-MTD Construction Ltd 508 508 140 140 6 - 6
M2K.D.Ebert & Sons Holdings (Pvt.) Ltd
270 150 73 67 1 - 1
M3K.D.Ebert & Sons Holdings (Pvt.) Ltd
201 201 29 24 - - -
Hambantota
H1K.D.A. Weerasinghe & Co (Pvt) Ltd
139 139 80 0 6 - 4
H2 CML-MTD Construction Ltd 163 163 28 28 10 - 10
H3 R.R Construction. (Pvt.) Ltd 100 100 54 54 9 - 9
Total 2,046 1,849(91%) 1,069 853(80%) *56 - 5/40
305*56 Includes 31 nos. repair only
308
Note : Road Lengths are revised in all Packages
nos. km nos. km nos. km nos. km nos. km nos. km nos. km
Total Length3 22.9 20 109.9 5 24.7 155 434.4 183 590.9 154 559.8 100 295.1
Road Works in Progress
Paving Completed
- 6 1 51 167.0- 43.7 6.2 117.1 42
Paving
CompletedTOC Issued
119.0
Southern Province
55 188.3 23 64.1
48 204.6 35 112.0
1 5 4
PS Roads
20.7
45.5
18.5
-
155.2
161.155
51 167.0
RDA Roads PRDA RoadsPRDA/ PS
Roads
9.4
13.5
56
2 9
Southern ProvinceRoad Works in Progress
Asphalt Completed
Matara District
44
Galle District
Matara District
Hambantota District
Hamabntota DistrictRoad Works in Progress
Asphalt Completed
Asphalt Completed66 220.1
-
Galle DistrictRoad Works in Progress
Asphalt Completed66 203.8
183 590.9
Progress up to End of May 2018
Road Works in Progress
Work Description
Integrated Road Development Investment Programme (iROAD)
Progress Summary
Southern Province & 3 Districts
Total
No.of
Roads
Total
Road
Length/
(km)
Start Date: 18 May 2015
Revised Completion Date: 19 December 2017 + 3yrs Maintenance
Province/Districts
203.8
220.1
167.0
Total
66
66
51
25km 75km50km 100km 125km 150km 175km 200km 225km 250km 275km 300km 325km 350km 375km 400km 425km 450km 475km 500km 525km 550km 575km 600km
(559.8km) (95%)
(66 Nos ,203.8 km)
(66 Nos ,220.1 km)
(51Nos ,167.0 km)
(188.3km) (92%)
(204.6 km) (93%)
(167.0 km) (100%)
Type of Road
Location
(183Nos, 590.9km)
Payments Certified – G1
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,458,055,706.14
Total (Certified by end of May-2018) 860,861,558.02
Physical Progress – G1
Cumulative Status up to End of
April-2018 / (%)
Cumulative Status up to End of
May-2018 / (%)
Target Actual Target Actual
100.0 75.0 100.0 75.5
313
Asphalt Progress Bar Chart – G1
314
Start Date: 18 May 2015
64.6
Road Works in Progress (63.4km / 15Roads) 4/15/1 Paving Completed
Paving Completed (49.1km / 4 Roads completed ) Road Handed Over
7 7 Habarakada - Ibbawala Yattapatha
6 6 Dharmapala Vidyalaya - Dunhena PS 1.2
5 5 Batahena - Kudagalpola - Habarakada PS 9.6
4 4 Danawala - Mawita
Batuwangala - Ehalapitiya
14 31 Udugama - Kothalawala Rd PS 8.0
13 30Kurupanawa Maliban Junction - Old Samurdhi
Building Via Polkella
TOTAL
Nagoda
15 32 Udugama - Aluthwatta PS
9 9 Halwitigala - Janapadaya - Tawalama Mukalana PRDA 2.8
1.8
11 28 Kimbulawala - Porawagama Road PS 3.9
Tawalama
Niyagama
10 11 Mandalapura 12th mile post PS
8 8 Kumburagoda - Mandalapura
12 29 Hattaka - Pityagala North Sasanathilaka Mawatha PS
PS 1.1
3 3Madagama - Ihalamadagama - Puswelkada -
Madeegama - BopagodaPS 7.3
2 2
Neluwa
PS 3.7
Revised Completion Date: 02 December 2017 + 3yrs Maintenance
Integrated Road Development Investment Programme (iROAD)
Galle District, Southern Province
Contract Package G1
Contractor: KD Ebert & Sons Holdings (PVT) LtdTotal Contract Amount (LKR): 1,458,055,706.14
1 1 Mavita - Dooliella Road PS 6.2
Serial
NoDSD
Road IDRoad Name
Road
Category
Length
(km)Progress up to End of May 2018
PS 2.9
6.4
3.4
5.1
PS 1.2
PS
9km1km 6km5km2km 3km 4km 7km 8km 10km
315
Photographs – G1
Rock Excavation;Halwitigala Janapadaya - Tawalama
Mukalana Road,CH 01+829
Asphalting;Udugama – Kothalawala Road;
CH 6+528
Leadaway Construction; Udugama Kothalawala Road;
CH 4+525.
Payments Certified – G2
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,483,136,252.40
Total (Certified by end of May-2018) 1,390,152,655.03
Physical Progress – G2
Cumulative Status up to End of
April-2018 / (%)
Cumulative Status up to End of
May-2018 / (%)
Target Actual Target Actual
100.0 98.0 100.0 99.0
318
Asphalt Progress Bar Chart – G2
319
Start Date: 18 May 2015
66.0
Road Works in Progress (66.0km / 22 Roads) 22/22/20 Paving Completed
Paving Completed (66.0km / 22 Roads completed) Road Handed Over
PS
PS
PS 1.5
PS 2.3
1.8
PS 4.0
PS
0.9
1.3
0.9PS
3.4PS
Integrated Road Development Investment Programme (iROAD)
Galle District, Southern Province
Contract Package G2
Contractor: KDA Weerasinghe & CO (pvt) Ltd
Revised Completion Date: 29 September 2017 + 3yrs MaintenanceTotal Contract Amount (LKR): 1,483,136,252.40
PS 7.1
0.9
2 13
Serial
NoDSD
Road IDRoad Name
Road
Category
Length
(km)
Kabaragala Badipita Puswelkada Unagaswita Galpoththa Kombala
Junior School 10th mile post thiyabarahena Rd(400 m already
asphalted)
3.0
7 18 Dodampe - Padinnoruwa(2.745)
12 24 Kapuhempala, Ambalamakanda, Hinidumgoda, Haliwala
1.5
17 34 Janahitha Tea factory - Nawunugala School via Muslim Janapadaya
15 27Hiyare East - School Road via Kaluwala Badipita Hawpe(106m
interlocked)
16 33 Yakkalamulla Via Udumala gala to Nakiyadeniya(86m interlocked)
14 26 Bataduwa - Sudarmaramaya Rd (200m asphalted) PS
PS
13 25 Poorwarama Road Bataduwa PS
K. G. Palis Mawatha PS 2.0
2.0
22 39 Nagashandiya - Halpathota PS 1.2
PS
Progress up to End of May 2018
TOTAL
Habaraduwa -
Imaduwa
Bope - Poddala
Akmeemana
Yakkalamulla
Baddegama21 38 Waulagala - Batakatiya
3.3
18 35Nawala Community Hall to Goluwamal hena via Ellagawa(200m
asphalted)PS 5.1
PS
19 36 Wackwella - Ginimallagaha(400m bridge section not done) PRDA 7.0
20 37
Edirisinghe Mawatha - Navinna2311
2.9PRDAHapugala - Eriyagaha Junction2210
5.3PSMayakaduwa - Wadiyakanda, Makaduwa Temple 209
Kombala - Halamulla - Niriwella(70m interlocked)198
2.8
PRDA/PSLiyanagoda - Lanumodara - Pitiduwa176
5.8PRDAPangiri hena -Mayakaduwa(300 m already asphalted)165
Galkatiya - Jayasumanaramaya, Goviyapana Junction154
Taramulla - Allalagoda Rd143
Mayakaduwa - Kombala Temple - Watiyadeniya - Heenpandala121
7km1km 6km5km2km 3km 4km 8km
Photographs -G2
Completed Road; Hapugala - Eriyagaha Junction
Road;CH 2+830
Completed Road;Wackwella - Ginimallagaha Road;
CH 2+850
Road Maintenance (PBM);Edirisinghe Mawatha - Navinna
Road;CH 3+680
320
Payments Certified – G3
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,733,440,933.20
Total (Certified by end of May-2018) 1,635,903,561.70
Physical Progress – G3
Cumulative Status up to End of
April-2018 / (%)
Cumulative Status up to End of
May-2018 / (%)
Target Actual Target Actual
100.0 97.0 100.0 99.0
323
Asphalt Progress Bar Chart – G3
32473.2
Road Works in Progress (73.2 km / 29 Roads) 29/29/15 Paving Completed
Paving Completed (73.2km / 29 Roads completed) Road Handed Over
PS 1.0
Mada Kubura Junction Kaluwala goda PS/PRDA 4.5
27 67 Bogaha Junction Kaluwala goda PS 1.9
24 64 Galduwa Aranya Rd PS 2.3
Hikkaduwa
Karandeniya
19 59 Buddajayanthi Mawatha Thirangama PS 1.3
20 60
25 65 Kaluwalagoda Road PS/PRDA 6.2
TOTAL
16 56 Kahawa - Galduwa Rd PS 1.9
17 57 Dewagoda - Balabokka Rd PS
28 69 Hatharaman Junction - Pasman Junction PS 1.7
29 70 Thannahengoda Rd PS 1.9
26 66
Balapitiya
21
Nindana School to 05th mile post via Wathurawila (add2.4 asphalted) PS 5.0
23 63 Boosa Hegoda Rajakoratuwa Rd PS 1.2
PS 3.4
61 Sirikadura Watta Sunami Niwasa Rd (add0.6 asphalted already) PS 1.4
22 62 Dudley Senanayake Mawatha Weragoda
Ratagama Imbulgoda PS 1.4
0.7
18 58 Boosa Kekilla Mandiya Regjipura Madawala Rd
13 52 Ampegama School - Unapandura Junction Road PS 1.4
14 53 Batapola Dorala Junction to Kirimatiara Road PS 1.1
Gonapinuwala
Ambalangoda
11 49 Manampita - Dehigaha Bedda Kirindiela PS 2.7
12 51 Welibokkuwa - Banwelgodella PS 0.9
15 54
47 Deddugala - Bataduwa PS 1.0
10 48 Waduweliwitiya Muktawela Junction - Putuwagoda Watta via Soratha Gammanaya PS 1.3Weliwitiya -
Diwithura
PS 2.7
5 44 Opatha - Omatta - Bulugoda PRDA/PS 4.8
2.0
8 46 Surasena Mawatha PS 2.2Bentota
6 44 A Elpitiya - Awiththawa RDA 9.4
7 45 Galparaya Road PS
9
3 42 Amuna Junction - Maitrigama PS 3.9
Progress up to End of May 2018
1
Elpitiya
40 Goluwamulla - Atakohota PRDA 2.2
2 41
Serial
NoDSD
Road IDRoad Name
Road
Category
Length
(km)
4 43 Pinikahana - Puwakdola
Integrated Road Development Investment Programme (iROAD)
Galle District, Southern Province
Contract Package G3
Contractor: KDA Weerasinghe & CO (pvt) LtdStart Date: 18 May 2015 Total Contract Amount (LKR): 1,733,440,933.20
Revised Completion Date: 25 October 2017 + 3yrs Maintenance
Goluwamulla - Welimanana Nagahatenna PS 1.9
7km1km 6km5km2km 3km 4km 10km8km 9km
Photographs – G3
Shoulder Construction;Elpitiya – Awiththawa Road;
CH 3+800-4+000
Shoulder Construction;Thannahengoda Road;
CH 0+950-01+100
Safety Workshop for PBM Team;Goluwamulla – Atakohota Road
325
329
0.3 km Asphalted in May and 0.3 km balance to be asphalted
Advance Payment has been fully recovered (July 2017 IPC)
Payments Certified – M1
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 2,315,346,953.44
Total (Certified by end of May-2018) 2,451,118,813.15
Physical Progress – M1
Cumulative Status up to End of
April-2018 / (%)
Cumulative Status up to End of
May-2018 / (%)
Target Actual Target Actual
100.0 99.0 100.0 99.0
330
Asphalt Progress Bar Chart – M1
331
Start Date: 18 May 2015
97.5
Road Works in Progress (97.5 km / 22 Roads) 21/22/21 Paving Completed
Paving Completed (97.2 km / 21 Roads completed) Road Handed Over
TOTAL
20 64 Diyadawa - Olakumbura via Kosmodara PS 2.5
21 65 Diyadawa - Bata Adura PS
6.3
22 66 Kolawaenigama - Uggalpotha PS 1.6
7.5
Kotapola -
Morawaka
18 24 Bengamuwa - Dabogala Road up to Napath Ella Road PS 2.6
19 24A Deniyaya - Viharahena RDA
16 22 Millalle via Aluwana Sankassa to Madde Ala Road PS 7.0
17 23
13 19 Kiriwalladola Junction to Hingurahena PS 2.1
14 20 Keeriwaldola - Keeriwelgama
Weliwa Pahuruthota - Neel Ella PS 4.5
PS 2.3
15 21 Porupitiya - Annasigalawila PS 1.4
11 17 Pathawala - Nadakanda - Keeriwellagama PS 2.8
12 18 Kiriwellagama Market to Dewala Road PS 1.0
7 13 Batayaya - Kandilpana - Bewraliiya PRDA
PRDA 6.1
10 16 Kosmodara - Bodeniya PS 4.1
13.1
8 14 Morawaka - Paragala Diyadawa PS 11.7
9 15 Berala Panathara - Thala Palakanda
PRDA 4.9
5 11 Millagahahena - Kudagalahena PS 4.4
6 12 Darangala - Dahaya Kanda Mahena PS 3.8
3 10 Morawaka - Millawa PRDA 2.9
Progress up to End of May 2018
1
Pitabeddara
8 Alapaladeniya - Thalpekumbura PS 2.5
2 9
Serial
NoDSD
Road IDRoad Name
Road
Category
Length
(km)
4 10A Abewala -Thibbatuwawa
Integrated Road Development Investment Programme (iROAD)
Matara District, Southern Province
Contract Package M1
Contractor: CML-MTD Construction Ltd
Revised Completion Date: 27 October 2017 + 3yrs Maintenance
Dangala - Dellawa PRDA 2.4
14km1km 13km12km9km 10km 11km2km 3km 4km 5km 6km 7km 8km
Photographs – M1
Pedestrian Crossing; Deniyaya - Viharahena Road;
CH 03+375
Completed Road; Deniyaya - Viharahena Road;
CH 03+900
Road Maintenance (PBM);Diyadawa - Bata Adura Road;
CH 02+180
332
Payments Certified – M2
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,803,301,712.60
Total (Certified by end of May-2018) 1,091,520,041.46
Physical Progress – M2
Cumulative Status up to End of
April-2018 / (%)
Cumulative Status up to End of
May-2018 / (%)
Target Actual Target Actual
100.0 82.0 100.0 83.0
335
Asphalt Progress Bar Chart – M2
336
69.2
Road Works in Progress (69.2km / 19 Roads) 5/19/1 Paving Completed
Paving Completed (54.5km / 5 Roads completed) Road Handed Over
TOTAL
Akuressa
Athuraliya
Pasgoda
Mulatiyana
Malimboda
PS 4.6
19 57A Thumbe - Kongala Road(2.5 was asphalted already) PRDA 4.8
1.3
17
Hakmana
56 Kongala D. C. Abeywuckrama Road PS 2.4
18 57 Obadakanda Badabadda Road
-
13 51 Agawaththa Thalgahagoda for Jayawardhana Road PS 1.1
54 Sulthangoda Kotavila via Kirimatimulla Road(1.3km) PS
16 55 Sulthangoda - Welihinna Road PS
14 52 Ogaspe Junction to Maligathenna Aththuduwa Road PS 0.8
15 53 Pahattu Kade to Nagoda via Welihinda Junction PS 0.9
Omitted
11 49 Atapattukanda Handiya - Pothuvila Road PS 1.5
12 50 Wilpita - Ukgashena via Ransagoda Galpoththa Junction PS 8.3
9 41 Lew Pothdeniya Road PS 2.7
10 42 Urubokka - Pothdeniya Road PRDA 6.5
7 7 Sri Sudarshi Pirivena Junction to Bibulewela Shramadana Road PS 3.8
8 40 Urawa - Pilikannahena Thalgasthenna Rotuba Road PS 2.9
5 5 Paraduwa - Pahuranwila Road PS 2.4
6 6 Bangama Junction - Dola Mawatha Road PS 2.5
Road
Category
Length
(km)Progress up to End of May 2018
4 4 Akuressa - Katanavila Road RDA 7.2
3 3 Iluppella - Mahingoda - Bopitiya Road PS 5.3
Integrated Road Development Investment Programme (iROAD)
Matara District, Southern Province
Contract Package M2
Contractor: KD Ebert & Sons Holdings (PVT) LtdStart Date: 18 May 2015 Total Contract Amount (LKR): 1,803,301,712.6Revised Completion Date: 19 December 2017 + 3yrs Maintenance
Poramba School - Diyalape Junction via Hikgoda Road PS 3.7
1 1 Kohugoda Road PS 5.5
2 2
Serial
NoDSD
Road IDRoad Name
7km1km 6km5km2km 3km 4km 8km 9km
Photographs – M2
House Access Placing; Obadakanda Badabadda Road;
CH 0+450
Hard Shoulder Construction; Thumbe – Kongala Road;
CH 3+939-3+983
RRM Retaining Wall Construction;Thumbe Kongala Road;
CH 00+980 – 00+986 (LHS)
337
339
0.0km Asphalted in May and 0.6km balance to be asphalted
Advance Payment has been fully recovered (March 2018 IPC)
Payments Certified – M3
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,207,599,780.58
Total (Certified by end of May-2018) 928,213,653.99
Physical Progress – M3
Cumulative Status up to End of
April-2018 / (%)
Cumulative Status up to End of
May-2018 / (%)
Target Actual Target Actual
100.0 99.0 100.0 99.0
340
Asphalt Progress Bar Chart – M3
341
53.4
Road Works in Progress (53.4 km / 25Roads) 22/25/22 Paving Completed
Paving Completed (52.8 km / 22 Roads completed) Road Handed Over
23 59 Ashokarama Rd PS 1.8
TOTAL
21 48 Samagi Mawatha via Siridewapriya Mawatha PS 2.8
22 58 Sri Piyarathna Mawatha (Kakuluwangoda Mawatha)Devinuwara
Dickwella
Thihagoda
24 60 Degigewatta Hakalamulla PS 1.3
25 61 Kaluhena Kolaniya Rd PS 4.4
PS 1.9
17 44 Narangalgoda - Palliya Gedara PS 2.3
18 45 10th Mile Post - Hakmana Gedara Kade PS 3.5
Kirinda -
Puhulwella46 Karatota School - Gewal Dahaya PS 2.5
20 47 Kubalgoda Seelaratana Mawatha PS 1.7
19
2.5
16 43 Baragammulla Moragasmandiya PS 1.8
Weligama -
Welipitiya
Kamburupitiya
14 38 Udukawa Baduravila Rd PS 1.3
15 39 Welipitiya Junction - Munamalpe Udukawa PRDA
1.6
13 37 Kotavila Kudawella Sulthanagoda PS 2.0
11 35 Jamburagoda Heelelgoda Junction - Bodduwa PS 1.9
12 36 Kananke police station Dewelagoda PS
9 33 Jaburegoda - Bodirukkaramaya PS 2.3
10 34 Pathegama - Kudalumulla for Kurubawila - Pitaduwa Thdukola Gammadda PS 2.3
1.3
8 32 Welipitiya Junction - Addarawela PS 2.3
6 30 Ibbawala - Panchaliya - Andugoda PRDA 2.3
7 31 Ibbawala - Ranamaduuragama PS
4 28 Yatipila - Udahahena - Henwala PS 1.8
5 29 Upupila Junction - Udupila Vihandagoda PS 1.0
2.5
3 27 Denuwala - Kapuwatta Jaya Wijayagama PS 2.2
1 25 Kananke - Polhene - Nagashena - Puhulhene Road PS 2.1
2 26 Dehigahahena - Udukawa PS
Integrated Road Development Investment Programme (iROAD)
Matara District, Southern Province
Contract Package M3
Contractor: KD Ebert & Sons Holdings (PVT) Ltd
Revised Completion Date: 10 October 2017 + 3yrs Maintenance
Serial
NoDSD Road ID Road Name
Road
CategoryLength (km)
Start Date: 18 May 2015 Total Contract Amount (LKR): 1,207,599,780.58
Progress up to End of May 20184km1km 3km2km 5km
Photographs – M3
Culvert Abutment 3rd Step Concete & Formwork;
Narangalgoda - Palliya GedaraRoad;
CH 1+518
Shoulder Filling; Narangalgoda - Palliya Gedara Road;
CH 0+560-0+710.
Guard Stone Painting; Kaluhena Kolaniya Road;
CH 0+300
342
Payments Certified – H1
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,583,594,552.40
Total (Certified by end of May-2018) 1,342,181,279.81
Physical Progress – H1
Cumulative Status up to End of
April-2018 / (%)
Cumulative Status up to End of
May-2018 / (%)
Target Actual Target Actual
100.0 95.0 100.0 96.0
347
Asphalt Progress Bar Chart – H1
348
67.1
Road Works in Progress (67.1km / 19 Roads) 19/19/17 Paving Completed
Paving Completed (67.1km / 19 Roads Completed) Road Handed Over
7.3
TOTAL
Road ID
2.3
3.6
6.8
9.7
7.7
6.2
8.0
1.9
1.9
1.1
1.2
3.2
0.9
1.5
0.8
1.6
0.8
Ridiyagama Livestock Farm / Gangawalana Road PS29
Sooriyawewa
16Hathagala Handiya / Deniya Pinama / Athbatuwa /
Hanunkatuwa PS28
19 Koggala Sooriyawewa Road PRDA36
18Ridiyagama / Kahabodawila / Thuduwa mulla
Road(1km belong to PRDA)PS/PRDA30
Ambalanthota
17
26
15Thuduwa Mulla / Habarakathawala Goda Koggala
RoadPS27
14 Eraminiyaya / Hadunkatuwa Road (1.4 km Asphalted) PS
PS20 0.6
10 Diya Bediya Road PS18
11 Weeravila Ara 01st Cross Road PSLunugamwehera
13 Piyapala Mawatha PS21
19
12 Ittan wewa 02nd Cross Road
16
9 Ikkapallama School Road PS17
8 Sabapathikade / Gonamuwa Hospital Road PSTissa
6 Manchgawa Layma Handiya Road PS13
7 Magama Road PRDA14
4Boralukanda Cooperative / Boralukanda Hnadiya
(Laksiri Road)PRDA11
5 Godawaya Junction / Temple Road PS12
Hambanthota
9
3 Boondala / Meda Para PS10
1Boralukanda Junction Uda Beragama / Maha Ara
Junction
Integrated Road Development Investment Programme (iROAD)
Hambanthota District, Southern Province
Contract Package H1
Contractor: KDA Weerasinghe & CO (pvt) LtdStart Date: 18 May 2015 Total Contract Amount (LKR): 1,583,594,552.40
PRDA8
2 4 Ela / School Road PS
Revised Completion Date: 11 October 2017 + 3yrs Maintenance
Serial
NoDSD
Length
(km)Road Name
Road
Category
Progress up to End of May 20181km 3km 10km2km 4km 5km 6km 7km 8km 9km
Photographs – H1
Junction Improvements;Boralukanda Junction Uda Beragama /
Maha Ara JunctionRoad;
Female Workers; Hathagala Handiya / Deniya Pinama / Athbatuwa / Hanunkatuwa Road;
CH 1+025
Completed Road; Diya Bediya Road;
CH 3+225
349
Payments Certified – H2
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,210,330,393.84
Total (Certified by end of May-2018) 1,238,449,546.36
Physical Progress – H2
Cumulative Status up to End of
April-2018 / (%)
Cumulative Status up to End of
May-2018 / (%)
Target Actual Target Actual
100.0 100.0 100.0 100.0
352
Asphalt Progress Bar Chart – H2
353
58.0
Road Works in Progress (58.0 km / 18 Roads) 18/18/18 Paving Completed
Paving Completed (58.0km / 18 Roads Completed) Road Handed Over
3.7Kadigamuwa Palamkada to Ekamuthu mawatha
to BatalawattaPS43
15
Okewella
18
Pattiyapola - Marakolliya PS33
Thangalla
12
1.1
TOTAL
13 2.6Kadurupokuna - Seenimodara road PS34
14 4.2Pattiyapola - Akkarawela Thalunna PS35
1.8Pallekanda junction - Udahatana Gambaddala PS41
16 1.9Sumihirigama Co-op city - Kukula Mandiya Hena
MahamadiththaPS42
Gonadenihena kanda via Rajapaksha mawatha PS44
17
Angunukolap
elassa
11 6.4Uswewa via Pahalagama sooriya pokuna junction PS25
3.1
7
8 15.6Uswewa - Binkama Road (0.5) by road PRDA22
9 4.5Dambarella Co-op - Kanabandi Area PS23
10 1.9Gajanayakagama Debokkawa junction -
Gajanayakagama junctionPS24
6 1.9Anamaduwa - Aranwela(Angulmaduwa-Aranwela) PS6
7 1.0Pattiyawela - Tharapeliya PS
Beliatta PS4
5 1.1Siyabalapa hena PS5
2
1 3.9Pattiyawela - Pallattara PS1
2
Integrated Road Development Investment Programme (iROAD)
Hambanthota District, Southern Province
Contract Package H2
Contractor: CML-MTD Construction LtdStart Date: 18 May 2015 Total Contract Amount (LKR): 1,210,330,393.84Revised Completion Date: 06 October 2017 + 3yrs Maintenance
Serial
NoDSD
Length
(km)Road Name
Road
CategoryRoad ID Progress up to End of May 2018
3 1.2Edirisinghe Mawatha PS3
4 0.9Polapathe watta road
1.2Upasakagoda well - Water Tank PS
1km 3km2km 4km 5km 6km 7km 8km 9km 10km 11km 12km 13km 14km 15km 16km
Photographs – H2
Completed Road;Uswewa - Binkama Road;
CH 1+100
Completed Road;Dambarella - Kanabadhiara Road;
CH 8+250
PBM Tool Box Meeting for workers/supervisors.
354
Payments Certified – H3
Description Certified Amount (LKR)
Accepted Contract Amount (ACA) 1,052,141,503.89
Total (Certified by end of May-2018) 1,011,811,248.97
Physical Progress – H3
Cumulative Status up to End of
April-2018 / (%)
Cumulative Status up to End of
May-2018 / (%)
Target Actual Target Actual
100.0 100.0 100.0 100.0
357
Asphalt Progress Bar Chart – H3
358
41.9
Road Works in Progress (42.9km / 14 Roads) 14/14/14 Paving Completed
Paving Completed (42.9km / 14 Roads Completed) Road Handed Over
TOTAL
45
PS
Wataramuma Road (and By pass - 160m)52
11
PS
Welipitiya Ambagasara via Siyarapitiya Road
Ela Banteka Para (Note : Existing good pavement of 1km
section was removed / not included in PBM works also)
14
Thorakolayaya - Gammaimpara Road PS31
12
13
Kudabibula Lidagawa Road
32
37
38
39
40
49
50
Road Name
Total Contract Amount (LKR): 1,052,141,503.89Revised Completion Date: 18 August 2017 + 3yrs Maintenance
Progress up to End of May 2018
Bariyar Junction to Galwadiya 4th Mile Post
Warapitiya Hospital to Karadeniya Road
School to Ela Banteka Para 2.3
Weeraketiya
7
8
9
10
PS
PS
Kakunayaya Market to Bhuweliara Road
Maregawa Road
Gonadeniya / Kaluwagaha yaya / Talawa Road
Perahara Mawatha / Mulkirigala School Road
Katuwewa to Mulgirigala School Road
Okandayaya Paluwatta Road(100 m already
concreted) (Okandayaya Lidagawa Road)
46
47
48
Integrated Road Development Investment Programme (iROAD)
Hambanthota District, Southern Province
Contract Package H3
Contractor: RR Construction (PVT) LtdStart Date: 18 May 2015
8.8
4.5
2.6
3.2
Road IDSerial
NoDSD
Katuwana
Walasmulla
6
1
Road
Category
2
3
4
5
3.1
Length
(km)
51
3.6PS
PRDA
PS
PS
PS
PS
PS
PS
PS 1.1
1.5
5.2
1.4
2.8
1.1
0.8
9km1km 3km 4km2km 5km 6km 7km 8km
Photographs – H3
Completed Road; Wataramuma Road;
CH 01+150
Completed Road; Bariyar Junction to Galwadiya 4th Mile
Post Road; CH 00+830
Road Maintenance (PBM);School to Ela Banteka Para Road;
CH 01+220
359
List of Utilities
Package No
No.of Roads
No.of Roads Surveyed for
Utility Shifting
Utilities to be Shifted
Electricity Pole / (Nos.) Telecom Pole/ (Nos.) Water Line / (m)
Identified Progress Identified Progress Identified Progress
G1 15 15 165 164 Nos. shifted 1 1 Nos. shifted - -
G2 22 22 116 114 Nos. Shifted 74 74Nos. shifted -
G3 29 29 241 235Nos. Shifted 113 111Nos. Shifted 3,300 3,300m shifted
M1 22 22 311 311Nos. Shifted 125 125Nos. Shifted 6,550 6,550 m shifted
M2 19 19 211 174Nos. Shifted 173 145Nos. Shifted 10,570 5,790m shifted
M3 25 25 162 162 Nos. shifted 118 118Nos. Shifted 6,005 5,245m shifted
H1 19 19 33 33 Nos. Shifted 13 13 Nos. Shifted 5,770 5,419m shifted
H2 18 18 156 156 Nos. Shifted 61 61Nos. Shifted 8,824 5,102m shifted
H3 14 14 27 27 Nos. Shifted 18 18Nos. Shifted 11,090 7,080m shifted
Total 183 183 1,4421,376Nos. shifted(95%)
(08nos. in May)696
666Nos. shifted (96%) (07 nos.in May)
51,92938,486 m
shifted(74%)
Payments to Utility Authorities up to End of May 2018
District Package No Contractor Electrical Services (Rs.)Telecommunication
Services (Rs.)Water Services (Rs.) Total (Rs.)
Galle
G1 KDESH 10,800,848.62 11,201.30 - 10,812,049.92
G2 KDAW 9,257,988.55 1,785,591.88 65,920.77 11,109,501.20
G3 KDAW 22,261,326.37 2,573,620.72 3,929,539.52 28,764,486.61
Sub Total 42,320,163.54 4,370,413.90 3,995,460.29 50,686,037.73
Matara
M1 CML-MTD 30,002,229.04 3,411,615.00 3,939,717.92 37,353,561.96
M2 KDESH 11,982,067.75 3,542,449.00 22,354,941.23 37,879,457.98
M3 KDESH 812,143.75 1,470,477.00 31,938,512.80 34,221,133.55
Sub Total 42,796,440.54 8,424,541.00 58,233,171.95 109,454,153.49
Hambantota
H1 KDAW 2,323,061.80 - 2,794,027.17 5,117,088.97
H2 CML-MTD 9,333,537.99 930,359.03 11,147,334.96 21,411,231.98
H3 RR - 90,796.00 11,982,259.97 12,073,055.97
Sub Total 11,656,599.79 1,021,155.03 25,923,622.10 38,601,376.92
Grand Total (Rs.) 96,773,204 13,816,110 88,152,254 198,741,568
❖Road Safety Audits done at;
1. Prelim. Stage = 183 nos. of roads (Check list- Austroads)
2. Design Stage = 22 nos. of roads (Format – ADB, Safeguard Team)
3. Construction Stage = 21 nos. of roads (Format – ADB, Safeguard Team)
Target of 10% of 183 nos. road complied with
❖Bi-monthly Safeguard and Road Safety Progress meetings are held.
❖Contractors are holding regular tool box meetings at site level.
Road Safety & Work Safety
362
Safeguard - Environmental
❖ Environmental field inspections are being done by PIC daily basis + monthly inspectionincluding night visits.
❖ National Building and Research Organization (NBRO) and The Open University (Dr.Padmalal) conducted baseline survey of air, noise level and water quality parameters andfauna flora monitoring respectively in pre-construction stage in all 9 Contract Packagesand submitted reports.
❖ Second phase monitoring (construction stage) conducted for physical and biologicalparameters in 31 July 2017 - 02 August 2017 and 18 August 2017, reports received.
❖ Re-submission of Annual Environmental Compliance Monitoring Report 2017, Submittedon 9 May 2018.
❖ Trees to be removed ~ 241 nos., Required replanting (removal x 3) =13,215 nos., Treesremoved to date = 4,164 nos. & Trees Planted to date = 10,844 nos. 363
Safeguard - Social
❖Addressing Public Complaints, Suggestions, Grievances & Requests✓ 45 (out of 45 Nos) Grievance Redress Committees (GRCs) established at DSD level.✓ 228 (out of 228 Nos) GRCs established at GND level.✓ 1638 GRC Meetings held to date.
❖Land Donation - A Memorandums of Understanding (MOU) has been developed, translatedinto local language and distributed to all 9 Packages.✓ 25 Individual MOUs have been signed with land owners.✓ 3 Common MOUs have been signed with Residents living along the roads.
365
366
Photographs – Safeguard Events
PBM Safety Workshop for all 3 Contract Packages, Hambantota District.
Gender Awareness Program at Matara District.
DistrictContract
Package
Public Complaints Received
TotalNo.
attended
No.
completely
settled
Solutions
in progress
No.
unattended
No. of
reques
ts
No. of
suggestions
No. of
complaints
No. of crack
related
issues
Galle
G1 95 13 35 - 134 134 50 84 -
G2 230 26 75 47 345 345 191 154 -
G3 545 - 22 106 675 675 348 324 -
Sub
Total870 39 132 153 1194 1194 618 566 -
Matara
M1 136 19 46 5 192 192 156 36 -
M2 95 2 62 25 181 181 75 106 -
M3 64 1 60 12 124 124 41 83 -
Sub
Total295 22 168 42 527 527 280 229 -
Hambantota
H1 49 - 43 3 92 92 81 11 -
H2 111 5 39 10 164 164 106 58 -
H3 318 6 10 7 340 340 187 153 -
Sub
Total501 11 92 20 624 624 398 230 -
Total 1675 72 399 215 2361 2361 2184 177 -
Summary of Public Complaints
367
368
Public Complaints / Requests / Suggestions
Contract Package G1
Contract Package G2
Contract Package G3
Total (Rs.)
House Access 1,835,400 4,674,765 907,893 7,418,058
Retaining Wall 3,126,090 2,637,041 18,798,576 24,561,707
Culvert 2,645,412 11,504,602 1,986,269 16,136,283
Concrete Dain 903,900 10,554,275 30,111,840 41,570,015
Service Ducts 1,051,560 - - 1,051,560
Earth Drain 349,650 - 41,735 391,385
Curb &Channel 300,000 - - 300,000
Property Damages - 444,100 216,910 661,010
Cover Slab - 135,900 - 135,900
ABC/Soil work - 1,490,580 - 1,490,580
Pave Asphalt - 214,843 - 214,843
Dish Drains - - 2,654,808 2,654,808
L Drains - 2,409,244 2,409,244
Total (Rs.) 10,212,012 31,656,108 57,127,276 98,995,396
Cost of Attending to Public Complaints / Requests / Suggestions – Galle District
Public Complaints / Requests / Suggestions
Contract Package M1
Contract Package M2
Contract Package M3
Total (Rs.)
House Access - 2,239,500 2,915,733 5,155,234
Retaining Wall 44,290,224 13,913,431 8,063,965 66,267,621
Culvert 71,257 5,017,628 1,604,089 6,692,974
Concrete Dain 3,759,041 1,364,953 1,297,342 6,421,338
By Road 831,985 - 500,000 1,331,985
Earth Drain - - 86,520 86,520
Curb &Channel 1,314,698 1,220,160 - 2,534,858
Hard Shoulder - - 965,995 965,995
Turfing - - 5,940 5,940
Boundary Wall - - 18,594 18,594
Pave Asphalt - - 406,011 406,011
Total (Rs.) 50,267,207 23,755,675 15,864,191 89,887,074
Cost of Attending to Public Complaints / Requests / Suggestions – Matara District
Cost of Attending to Public Complaints / Requests / Suggestions – Hambantota District
Public Complaints / Requests / Suggestions
Contract Package H1
Contract Package H2
Contract Package H3
Total (Rs.)
House Access 318,450 3,488,282 15,756,224 19,562,956
Retaining Wall 1,884,030 16,830,032 5,797,056 24,511,118
Culvert 17,285,915 - 6,471,339 23,757,254
Concrete Drain 13,821,850 17,083,230 29,233,828 60,138,908
Dish Drain 114,480 - - 114,480
Service Ducts 213,720 - - 213,720
By Road - 779,965 - 779,965
Earth Drain - 865,074 1,562,960 2,428,034
Kerb & Channel - - 11,914,791 11,914,791
Bell Mouth 580,000 - - 580,000
Design Improvements - 12,610,352 - 12,610,352
Total (Rs.) 34,178,445 51,656,935 70,736,198 156,571,578
Cost to Completion
❖Review meetings on draft C to C- Ver. 3 completed in all 9 Packages,C to C- Ver. 3 is completed, Final document submitted to RDA .
❖Southern Province as a whole will come under the total 9 x ACAs.
Project Performance Monitoring System (PPMS)
❖PPMS submitted.
❖Reviews to be done✓Mid Term – Construction Completion ~May 2017, in progress
✓ Project Completion ~ May 2020
371
Performance Based Maintenance (PBM) and Taking Over Certificate (TOC)
❖ TOCs - Taking over of roads commenced from Feb 2017 onwards & PBM in progress.
❖ 100 nos. of TOCs issued to date.
❖ PBM staffing & resources plan for 3 years finalized.
372
Ministry of Higher Education and Highways Road Development Authority
3rd Project Steering Committee Meeting ADB Funded
Second Integrated Road Investment Program (iROAD 2)
Asian Development Bank
22-06-2018
Fact Finding Mission 22 May 2017
Loan Negotiation 10 Aug 2017
Board Consideration 28 Sept 2017
Loan Agreement Signing 22 Nov 2017
Loan Effectiveness 09 February 2018
Implementation Period 2018 - 2027
25-Jun-18 376
25-Jun-18 377
Tranching Plan
Tranches
1(2017)
2(2018)
3(2019)
4(2020)
5(2021)
Total
Amount (U$SMn)
150 150 200 200 200 900
Tranche 1 loan signed and effective.
Category Approximate Cost
(LKR Mn)Total Cost including
Taxes (USD Mn)
Civil Works 135,910 892.40
Equipment (R & D enhancement) 885 5.80
Consulting Services for Project Implementation and Capacity Development
5,775 37.90
Recurrent Cost (Project Management) 2,620 17.20
Contingencies 16,500 108.30
Financial Charges during implementation 3,500 23.00
Total 165,190 1,084.60
Estimated cost of the project is approximately USD 1,085 million
(ADB: 900; GOSL: 185) through MFF with 5 tranches.
25-Jun-18 378
Loan Components
Province Packages Length (km) Approximate Cost(LKR Mn)
Northern 17 1,060 38,970
Eastern 11 845 26,600
Uva 15 1,045 33,300(Awarded –
Total Contract Sum)
Western 10 800 22,230
Total 53 3,750 121,100
25-Jun-18 379
Proposed Road Lengths and Tentative Estimated Cost
25-Jun-18 380
Proposed Road Length
Province DistrictNational
Road (km)
No. of Roads
RuralRoad (km)
No. of Roads
No. of Roads (Total) Total (km)
Northern
Jaffna
114.89
1 260.24 127 128
1,057.77
Kilinochchi - 181.78 47 47
Mannar 1 137.74 67 68
Vavuniya 2 221.78 62 64
Mullaitivu - 141.34 36 36
Eastern
Batticaloa155.76
1 184.99 123 124
845.83Ampara 14 319.45 144 158
Trincomalee 1 185.63 123 124
Uva Badulla72.90
6 494.53 147 1531,044.51
Moneragala 1 477.08 95 96
Western Colombo
-
- 247.21 149 149
799.98Gamapha - 307.37 183 183
Kalutara - 245.40 102 102
Total 343.55 27 3,404.54 1,405 1,432 3,748.09
1. Civil works of Uva province (15 civil work contracts) awarded and agreements signed. Advance paid.
2. Procurement of civil works for other provinces.
3. Recruitment of Project Implementation Consultants (PIC) Uva: Awarded and agreement signed on 20 June 2018Eastern: Financial proposal evaluation report sent for ADB concurrence. Northern & Western: Technical proposal evaluation report sent for ADBconcurrence.
25-Jun-18 381
Present Status – Overall
Province Expected date of inviting bids Expected date of award
Eastern 15 July 2018 22 December 2018
Northern 03 September 2018 24 February 2018
Western 20 October 2018 25 March 2019
Project Implementation Consultants:
Name of the Firm:
Pyunghwa Engineering Consultants Ltd. (Korea) in joint venture with Consulting Engineers and Architects Associated (Pvt.) Ltd (Sri Lanka)
Contract Amount:
US$ 2,537,737LKR 761,325,000
25-Jun-18 383
Uva Province – Consultancy
25-Jun-18 384
Uva Province – Badulla district - Civil WorksPackage Name of the Contractor No. of
RoadsLength (km)
Contract Sum(LKR Mn)
BA-01 NEM Construction (Pvt.) Ltd 14 57.88 2,055.89
BA-02 Komuthi Engineering Services (Pvt.) Ltd (Sri Lanka) in joint venture with HCM Engineering (Malaysia) (Kumuthi - HCM Engineering JV)
20 79.86 2,262.82
BA-03 CML – MTD Construction Limted 36 83.53 2,458.96
BA-04 China National Technical Import & Export Corporation (China) in joint venture with Ruhunu Development Contractors and Engineers (Pvt.) Ltd (Sri Lanka) (CINTIC – RDCE JV)
20 65.46 2,118.73
BA-05 China National Technical Import & Export Corporation (China) in joint venture with Ruhunu Development Contractors and Engineers (Pvt.) Ltd (Sri Lanka) (CINTIC – RDCE JV)
17 77.99 2,504.97
BA-06 CML – MTD Construction Limited 11 63.00 2,345.80
BA-07 CML – MTD Construction Limited 17 68.95 2,461.43
BA-08 Tissa Builders (Pvt.) Ltd in joint venture with PND Construction (Pvt.) Ltd (Tissa – PND JV)
18 60.82 1,847.72
Total – Badulla 153 557.49 18,056.32
25-Jun-18 385
Uva Province – Monaragala district - Civil WorksPackage Name of the Contractor No. of
RoadsLength (km)
Contract Sum(LKR Mn)
MO-01 AMSK Construction (Pvt.) Ltd (Sri Lanka) in joint venture with China Gezhouba Group Company Limited (China) (AMSK – CGGC JV)
10 63.76 2,241.23
MO-02 Tudawe Brothers (Pvt.) Ltd 14 63.29 1,891.88
MO-03 Maga Engineering (Pvt.) Ltd 21 70.02 2,201.47
MO-04 CML – MTD Construction Limited 12 65.78 2,274.49
MO-05 Tudawe Brothers (Pvt.) Ltd 14 64.15 2,056.80
MO-06 Hovael Construction (Pvt.) Ltd 16 96.98 2,713.44
MO-07 Tudawe Brothers (Pvt.) Ltd 9 64.80 1,858.08
Total – Monaragala 96 549.60 15,237.39
Total – Uva 249 1,107.09 33,293.71
No Description LKR (Mn)
1 Budget Allocation 5,000
2 Expenditure as at 20 June 2018 2,385
3 % Financial achievement 48%
Allocation - 2018
1. Approval of staff by MSD – only part of requested staff have been approved
2. Appointment of staff in Uva province to be expedited.
25-Jun-18 387