TUGAS AKHIR MANAJEMEN
PELAKSANAAN
PEMBANGUNAN JALAN TOLMOJOKERTO KERTOSONO STA. 5+350 STA. 10+350
DENGAN MENGGUNAKAN PERKERASAN KAKUDI KABUPATEN MOJOKERTO PROVINSI JAWA
TIMUR
ZULFIKARJAUHARI
NRP. 3110040601
PROGRAM STUDI DIPLOMA 4 TEKNIK SIPIL
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
2/36
Fakultas Teknik Sipil dan Perencanaan
Institut Teknologi Sepuluh Nopember
Surabaya 2012
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
3/36
STA 10 +350STA 5 +350
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
4/36
BAGAN ALURMETODELOGI
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
5/36
GI
LANJUTANMETODELO
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
6/36
PETA LOKASI QUARRY
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
7/36
PETA LOKASI QUARRY
JARAK LOKASI PROYEK DENGAN LOKASI QUARRY
ADALAH 32, 4 KM
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
8/36
PEKERJAAN TANAH
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
9/36
Pekerjaan Tanah
Pembersihan dan Pembongkaran
Galian Konstruksi 0 - 2 m
Pekerjaan Timbunan
Lapisan Geotextile
Penyiapan Badan Jalan
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
10/36
PEMBERSIHAN & PEMBONGKARAN
1. Pembongkaran dilakukan pada daerah milikjalan yang telah ditentukan dan atas petunjukdireksi.
2. Harus dilakukan dengan hati-hati berkaitandengan banyaknya utilitas existing bawahtanah.
2. Hasil pembongkaran dibuang diluar lokasipekerjaan atau lokasi yang telah ditentukanoleh direksi .
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
11/36
PEMBERSIHAN & PEMBONGKARAN
PEMBERSIHAN/PENGUPASAN TOP SOIL, PENGANGKUTAN DAN PERATAAN
1. Pembersihan permukaan tanah dengan Bulldozer 2. Loading hasil streping ke Dump truck denganExcavator
3. Galian tanah permukaan + 50 cm dengan Bulldozer 4. Loading hasil galian dengan excavator ke dump truckuntuk dibuang ke disposal area
50 cm
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
12/36
PEKERJAAN DRAINASE
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
13/36
PEKERJAAN GALIAN SALURAN TEPI
CONTOH TYPE SALURAN
GALIAN SALURAN
TEPI 1
GALIAN SALURAN TEPI 2
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
14/36
PEKERJAAN GALIAN SALURAN TEPI
PERSIAPAN
Rencanakan urutan penggalian, urutan pekerjaan
U-Ditch, tempat penimbunan tanah hasil galian
sementara sebelum diangkut keluar dari site.
PEMBUATAN GALIAN
Rencana Galian Pondasi
Galian untuk Pondasi
1. Siapkan alat-alat yang diperlukan.
2. Menggali tanah dengan ukuran lebar sama
dengan lebar bagian bawah dengan kedalamanyang disyaratkan.
3. Menggali sisi-sisi miringnya, sehingga
diperoleh sudut kemiringan yang tepat.
4. Buang tanah sisa galian ketempat yang telah
ditentukan.
5. Cek posisi, lebar, kedalaman dan kerapianya,
sesuai dengan rencana.
Papan Bouwplank
Bekas Galian
Tiang Bouwplank
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
15/36
PEKERJAAN PEMADATAN
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
16/36
Dump truck 11 tonMaterial timbuanan
(Sirtu)
Bulldozer 150 HP Motor Grader 3.1 m3 Vibrator roller 12 ton Truck tanki air (6000 m3)
Timbunan lapis 2Timbunan lapis 3
Timbunan lapis 1
Muka tanah asli
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
17/36
PENYIAPAN BADAN JALAN
1. Pekerjaan pembentukan badan jalan dan perapihan
serta perataan menggunakan motor grader sehinggamembentuk kemiringan sesuai design
2. - Vibrator Roller memadatkan permukaan yang telahdiratakan oleh motor grader dgn diberi airsecukupnya
- Sekelompok pekerja akan membantu meratakanbadan jalan dengan alat bantu
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
18/36
PEKERJAAN TIMBUNAN TANAH BIASA
1. EXCAVATOR MEMUAT MATERIAL TIMBUNAN
KEDALAM DUMP TRUCK DI BORROW AREA KE
MUDIAN DIANGKUT KELOKASI PEKERJAAN
2. TIBA DILOKASI PEKERJAAN MATERIAL DIDUMPINGDARI DUMP TRUCK KEMUDIAN DILAKUKAN PENGHAMPARAN
3. PENGHAMPARAN TANAH TIMBUNAN MENGGUNAKAN
MOTOR GRADER
4. HAMPARAN MATERIAL DISIRAM AIR SEBELUM DI
PADATKAN
-PEMADATAN MATERIAL DILAKUKAN DENGAN MENG
GUNAKAN ALAT VIBRATOR ROLLER
WATER TANK TRUCK
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
19/36
PEKERJAAN TIMBUNAN PILIHAN
1. EXCAVATOR MEMUAT MATERIAL TIMBUNAN
PILIHAN KEDALAM DUMP TRUCK DI BORROW
AREA KE MUDIAN DIANGKUT KELOKASI
PEKERJAAN
2. TIBA DILOKASI PEKERJAAN MATERIAL DIDUMPINGDARI DUMP TRUCK KEMUDIAN DILAKUKAN PENGHAMPARAN
3. PENGHAMPARAN TIMBUNAN PILIHAN MENGGUNAKAN
MOTOR GRADER
4. HAMPARAN TIMBUNAN PILIHAN DISIRAM AIR
SEBELUM DI PADATKAN
-PEMADATAN MATERIAL DILAKUKAN DENGAN MENG
GUNAKAN ALAT VIBRATOR ROLLER
WATER TANK TRUCK
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
20/36
PEKERJAAN PERKERASAN BERBUTIR
1. Pendatangan material timbunan dari luar denganmenggunakan Dump Truck
2. Material di hampar dengan Motor Grader
3. Proses pemadatan hasil peghamparan denganmenggunakan Vibrator Roller
4. Prosess pemadatan diikuti pembasahan dengan WaterTank Truck
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
21/36
PEKERJAAN PERKERASAN BETON
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
22/36
Rigid PavementPERSYARATAN TEKNIS
a. Beton Lantai Kendaraan, mutu beton K-400 (umur 28 hari) Lantai Kerja, Mutu beton harus setara dengan beton K-125 (umur 28 hari)
b. Baja Tulangan
Diameter > 13 mm : U-39 (ulir) Diameter < 13 mm : U-32 (polos)
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
23/36
KONSTRUKSIPEKERJAAN PERKERASAN BETON
FLOWCHART PEKERJAAN K - 40
START
MATERIAL KLAS B = 20 CMBY MOTOR GRADER/VIBRO ROLLER/TANKI AIR
LEAN CONCRETE thick = 5 cmBY TRUCK MIXER
CONCRETE PAVEMENT
LEAN CONCRETE t=5 CONCRETE PAVEMENT thick = 27 cmBY TRUCK MIXER
FINISH
CONCRETE PAVEMENT
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
24/36
KONSTRUKSIPEKERJAAN PERKERASAN BETON
PELAKSANAAN PEKERJAAN SLAB K-400
1. Pekerjaan Persiapan
Pekerjaan persiapan yang dilakukan untuk perkerasan beton yaitupenentuan elevasi lean concrete yang akan di cor. Pemasanganbekisting pada sisi jalan untuk pengecoran lean concrete pekerjaan
pengecoran lean concrete
2. Pekerjaan pengecoran lean concrete
3. Pemasangan bekisting sisi jalan yang juga berfungsi sebagai rel dariconcrete paver. Pemasangan pelastik dan kayu yang berfungsi
sebagai crack inducer4. Pembuatan Dowel, Tie Bar dan Wire Mesh
Pembuatan dowel, tie bar dan pemasangan wire mesh, dilakukansebelum pekerjaan pengecoran dimulai.
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
25/36
PEKERJAAN PERKERASAN BETON KONSTRUKSI
Mulai
Penyiapan Alat
Paver
Pemasangan Rel
Pemasangan Plastik,
crack inducer, Dowel &
Tie Bar
PERSIAPAN
Pemasangan
Wire MeshPerkuatan
Selesai
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
26/36
PEKERJAAN PERKERASAN BETON
Pengukuran/Penentuan Elevasi Lean Concrete
Pembuatan Dowell dan Tie bar
26
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
27/36
26METODE PELAKSANAAN PEKERJAAN RIGID PAVEMENT
1. Buat Patokan Lean Concrete
10 Cm
2. Pengecoran Lapisan Lean Concrete Papan Pijakan Pekerja
10 Cm
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
28/36
PEKERJAAN PERKERASAN BETON KONSTRUKSI
Persiapan
Membuat Alur
Pengecoran
Compound
Menggelar & Meratakan
Pembasahan Beton
PemadatanPemotongan
Joint
Meratakan
Permukaan Pengisian Joint Sealant
Finish
ALUR PENGECORAN CONCRETE
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
29/36
+
+
+
+
++
++
++
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
ALUR PENGECORAN CONCRETE
Oleh karena lebar Jalan 7 m
Maka lebar penghamparan
dibuat dua kali masing masing
Dengan lebar hampar 3.5 m
2
3 4 1
3.50 m
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
30/36
++
+
3.50 m 3.50 m 3.50 m
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
31/36
PEKERJAAN PERKERASAN BETON KONSTRUKSI
1 2
Pengecoran Penyebaran & Pemadatan
3 4 5
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
32/36
Meratakan Permukaan Pembuatan Alur Curing Compound
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
33/36
PEKERJAAN PERKERASAN BETON KONSTRUKSI
6 7 8
Pembasahan Beton Pemotongan Joint Pengisian Joint Sealant
9
10
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
34/36
Perlindungan dengan Tenda Hasil RIGID PAVEMENT
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
35/36
Manajemen
Untuk mengetahui bagaimana manajemen yangdipakai, saya menggunakan bantuan program
MS Project untuk memfasilitasi pengaturanBiaya, Waktu, dan Mutu
32
7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf
36/36
32