HYDRAULIC HEAD

21

V

Hukum Bernoulli pada aliran saluran

datum

Page 2: HYDRAULIC HEAD

HYDRAULIC HEADHukum Bernoulli pada aliran air tanah

Karena kecepatan aliran air tanah sangat kecil, maka

0

Maka,

Dimana, he = hydraulic head antara titik 1 dan 2

Page 3: HYDRAULIC HEAD

CONTOH

Page 4: HYDRAULIC HEAD

FLOW NET

a. Flow net in an solid dam b. Flow net in an earth dam

Flow net adalah jaring-jaring aliran air, dimana berlaku garis alir () ortogonal terhadap garis tekanan (h)

Merupakan solusi dari pers. Laplace

Page 5: HYDRAULIC HEAD

CREEP LENGTH

Scoured

Creep length, L

he

L = Lv + 1/3 Lh

Keterangan:Lv = lengths of vertical flow pathsLh = lengths of horizontal paths

Kemiringan ≤ 45 termasuk Lh > 45 termasuk Lv

Page 6: HYDRAULIC HEAD

CREEP LENGTH

Save Length L

ehL ≥

ehL (ijin)

(Tabel 5.1)

Page 7: HYDRAULIC HEAD

CREEP LENGTHContoh,

Page 8: HYDRAULIC HEAD

CONTOHContoh,

+84

+74

30 m 3

3 m

4 m

Medium sand, creep head rations ijin = 6

Coba anda selidiki keamanan tubuh bendung tersebut dari bahaya creep,

Page 9: HYDRAULIC HEAD

SECURITY (Pengamanan)

1. Memasang sheet piles (turap)

Page 10: HYDRAULIC HEAD

SECURITY (Pengamanan)

2. Memasang impervious blanket (lapisan kedap air) atau graded fillter

Page 11: HYDRAULIC HEAD

CONTOHContoh,

+84

+74

30 m 3

3 m

4 m

Medium sand, creep head rations ijin = 6

a. jika digunakan turap untuk meningkatkan keamanan bendung terhadap creep, berapa panjang turap harus dipasang.

b. Jika digunakan impervious blanket (lapisan kedap air) di upstream, berapa panjang lapisan tersebut.