Presentation Title(Front Cover ver.1)

© 2019 JGC Corporation

Pushing the Limit of LNG Production by AI Technology “HAR Digital 1.0”

JGC Technology Forum 2019

Hirokatsu UchidaProcess Group Leader & LNG Digital Promoter

1

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

Agenda

1.What is Hot Air Recirculation?

2.JGCʼs Solution for HAR Management

3.HAR Mitigating Technologies

4.HAR Adapting Technologies (AI Technology)

5.JGCʼs Proposal for AIRLIZE Initiation in Plant and LNG3

2

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

1. What is Hot Air Recirculation?

3

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

What is Hot Air Recirculation?

Hot Air Recirculation (HAR)

Cross Wind

(3 m/s)

Hot Air from

Adjacent Train

Source: LNG17 UNDERSTANDING OF HOT AIR RECIRCULATION PHENOMENA IN AIR COOLED BASE LOAD LNG PLANT

4

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

HAR Impact on LNG Production

90

95

100

105

110

115

120

0

5

10

15

20

25

30

35

40

20‐07‐12 20‐07‐12 20‐07‐12 20‐07‐12 20‐07‐12 21‐07‐12 21‐07‐12 21‐07‐12 21‐07‐12 21‐07‐12 22‐07‐12

LNG Prod

uctio

n

Air Intak

e Tem

perature (d

egC)

Plant Slowdown due to Hot Air Recirculation 

Target

+5%

‐5%

Loss of LNG Production

Increased Aircooler Inlet Air Temperature

0:00 0:000:00 12:0012:00 18:006:00 18:006:00

Source: LNG17 UNDERSTANDING OF HOT AIR RECIRCULATION PHENOMENA IN AIR COOLED BASE LOAD LNG PLANT

5

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

2. JGC’s Solution for HAR Management

6

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

HAR Management: Two Solutions2. Adapt (by Advanced

Control)1. Mitigate (by Hardware

Modification)

To mitigate the cause(s) of Hot Air Recirculation by means of

Technology to improve LNG production capacity

To adjust (adapt) operation in real time manner to cope with HAR by means of HAR Digital to push LNG production to the limit

7

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

3. HAR “Mitigating” Technologies

8

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

HAR View Technologies

9

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

Air Flow Vector Analysis

Hot Spot Analysis

CFD Simulation is a powerful tool for JGC to visualize hotspots, air flow behavior inside the plant (for both design phase and operation phase). Not only that, it can be used to evaluate the plant modification without needing to implement it.

Isothermal Surface Analysis

Advantages of CFD analysis and why we use it

Examples of Past ExperienceProject Phase(s)Tangguh EPCMLNG Tiga OperationPetronas Tr-9 Pre-FEED, FEED, EPC Bid, EPCDSLNG EPCIchthys FEED, EPCMozambique(Anadarko) Before FEED, FEED, Pre-FID, Re-FEED, EPC Bid

Mozambique(Eni Onshore) EPC Bid

Kitimat FEED Verification & FEED Plus, FEED Completion, Concept Selection

Lake Charles FEEDYamal FEED, EPCTangguh Expansion FEED

Cameron EPC BidGorgon Expansion Business Case Improvement StudiesLNG Canada EPC BidGolden Pass EPC Bid

Diagnosis: CFD Analysis

10

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

4. HAR “Adapting” Technologies

11

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

JGC has been able to apply their extensive knowledge and experience through R&D program in AIRLIZE LNG ® to establish an advanced control scheme to over-come the HAR issues.

The Feed-forward process control powered by HAR Predictive Model allows you to realize the full benefit of the motor power which will enhance your LNG throughput by at least 3~5% without any major modification to your facility

Key success factors of the Technology- Introduction of the Real time Weather Monitoring System- Process Big Data Analysis, CFD Simulation, and Rigorous Process Simulation- JGCʼs extensive experience in LNG processes and Hot Air Recirculation Analysis

12

HAR Digital

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

Plant Historical Data

Weather Simulation(Forecast/Sudden Change)

Plant Layout

Weather Measurement(Actual)

CFD Simulation

Rigorous Process Simulation

FEED BACK FOR DATA IMPROVEMENT

REAL TIME DATA COLLECTION

LNG PREDICTIVE ANALYTICS SERVER

Operators take action in advance for higher LNG production

DCSAPC SERVER

13

HAR Digital System Configuration

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

5. JGC’s Proposal for AIRLIZE Initiation in Plant and LNG3

14

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

Example : Implementation of AIRLIZE Technology

15

AIRLIZE LNG®

WorkshopHAR Digital Business Case Study(Weather Analysis, Operational Data Analysis)

HARView® Diagnosis(CFD, Aircooler and GT Performance Survey)

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

AIRLIZE LNG®

WorkshopHAR Digital Business Case Study(Weather Analysis, Operational Data Analysis)

HAR Digital Demonstration(CFD, HAR Predictive Model Development, Verification)

HAR DigitalImplementation(APC, Predictive Model Installation)

Optic Fiber Cable Installation & Reinforce HAR Digital

HARView® Diagnosis(CFD, Aircooler and GT Performance Survey)

ANNUAL LNG INCREASE

2~3%PER TRAIN

1 MONTH 3 MONTH 6~10 MONTH

8~12 MONTH6 MONTH

HARView® Mitigation(Wind Screen, Fogging, Ventilation Improvement)

8~12 MONTH

ANNUAL LNG INCREASE

2~3%PER TRAIN

Execute Two Initiatives in Parallel

ANNUAL LNG INCREASE

1~2%PER TRAIN

Initiative 2 : HARView®

Initiative 1 : HAR Digital

Example : Implementation of AIRLIZE Technology

16

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

AIRLIZE Service for Life Cycle Solution

17

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

Explore together Workshop&ConsultingWorkshop&Consulting Service for LNG plant by the worldʼs leading EPC Contractor

Our extensive experience and capability to forecast LNG project will guide you with “quick” & “complete” solution for optimum project execution

LNG3 (LNG Cube)

18

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

LNG3 =Technology-Driven Workshop & Consulting

19

Copyright 2019 JG

C All Rights Reserved

Copyright © JGC CORPORATION All rights reserved.

Hirokatsu UchidaProcess Technology DivisionHAR Digital Solution [email protected]

Contact

Teru AsakaOil & Gas DivisionAIRLIZE LNG ® Technology [email protected]