JAI VIKAS B H.E L(TURBO GENERATOR)

16
An Industrial Training PPT Submitted in Partial Fulfilment for the award of the Degree of Bachelor of Technology in Department of Electrical Engineering Submitted to: Mr. Manish Agarwal Asst. Prof.(EE) Submitted by: Jai Vikas 11E1SBEEM35P03 0 Department of Electrical Engineering SRI BALAJI TECHNICAL CAMPUS, JAIPUR Rajasthan Technical University, KOTA August 2014

Transcript of JAI VIKAS B H.E L(TURBO GENERATOR)

An Industrial Training PPT

Submitted in Partial Fulfilment

for the award of the Degree of Bachelor of Technology

in Department of Electrical Engineering

Submitted to:Mr. Manish AgarwalAsst. Prof.(EE)

Submitted by:Jai Vikas 11E1SBEEM35P030Department of Electrical Engineering

SRI BALAJI TECHNICAL CAMPUS, JAIPURRajasthan Technical University, KOTA

August 2014

A Presentation on summer training

atB.H.E.L, Turbo generator ,

Ranipur ( Haridwar)

Main Gate of B.H.E.L ,HARIDWAR

CONTENTS COVERED1. Introduction to BHEL.2. BHEL Has Supplied3. HEEP classification4. BLOCK-1 (HEEP)5. Parts of Turbo Generator6. Stator7. Rotor8. Cooling System9. Conclusion

B.H.E.L . AN OVERVIEW

• BHEL is the largest engineering & manufacturing enterprise in India.

• 1st maharatna company in india• BHEL caters to the core sectors of the Indian Economy, viz. Power, Transmission, Industry, Transportation, Renewable Energy, Oil & Gas and Defence.

• It was Established 43 years ago in 1971.

• It is earning profits continuously since 1971-72, & paying dividends since 1976-77

MANUFACTURING UNITS OF B.H.E.L.

First Generation UnitsBHOPAL Heavy Electrical PlantHARIDWAR Heavy Electrical Equipment plantHYDRABAD Heavy Electrical Power Equipment PlantTIRUCHY High pressure Boiler Plant

Second Generation UnitsJHANSI Transformer and Locomotive PlantHARIDWAR Central foundry and forge PlantTIRUCHY Seamless Steel Tube Plant

BHEL HAS SUPPLIED

•Over 1,00,000 MW of power generation equipments.

• Over 2,25,000 MVA transformer capacity and other equipment operating in Transmission & Distribution network.

• Over 25,000 Motors with Drive Control System to Power projects.

• Traction electrics and AC/DC locos to power over 12,000 kms Railway network.

•Supplied over one million Valves to Power Plants and other Industries.

About B.H.E.L. HARIDWAR UNITtotal worker-3500executive engineer-3000LOCATION-RANIPUR,HARIDWAR

HEEP (Heavy Electrical Equipment Plant) There are eight blocks in the HEEP namely 1-8.Block-1 Turbo generator ShopBlock-2 Fabrication ShopBlock-3 Turbine and Auxiliary ShopBlock-4 Insulation ShopBlock-5 Forging ShopBlock-6 Stamping Shop Block-7 Packing and Wood Working ShopBlock-8 Condenser and Piping ShopNew Blade ShopCFFP (Central Foundry And Forge Plant)

Block-1 (ELECTRICAL MACHINE BLOCK) EQUIPMENTS

Turbo generators

CAPACITY500 MW Turbo generators at a

glance -2-Pole machine with the following features:-

 Technical data–Rated output : 588 MVA , 500 MW

 Terminal voltage :21 KV Rated stator current :16 KA Rated frequency: 50 Hz Rated power factor: 0.85 Lag Efficiency: 98.55%

Developed approach of alternator10 Stat

or

Rotor

• Stator Frame

• Stator core

• Stator Winding & Core assemble

• Rotor Shaft

• Rotor winding

MAIN PARTS OF 500 MW TURBOGENERATOR Stator Rotor Excitation system Cooling system Insulation system Bearings Insulation system a) Insulating materials b) Classification of Insulating material

c) Properties

STATOR STATOR FRAME STATOR CORE STATOR WINDING STATOR COILS INSULATION SYSTEMS

ROTOR Rotor Shaft Rotor Winding Insulation Field Connections

STATOR WINDING

• IT INDUCES EMF AND SUPPLIES LOAD PLACED IN SLOTS OF STATOR CORE • TWO LAYER LAP WINDING.

• IT IS MADE UP OF NUMBER OF STRIPS, INSTEAD SINGLE SOLID PIECE TO REDUCE SKIN EFFECT.

• MATERAIAL USED IS COPPER.

COOLING

• De-ionized water with in the stator coil is used for cooling the stator

• The exciter is air cooled. The cooling air is circulated in a closed circuit and re-cooled in two cooling sections arranged along side the exciter

Thank you……..