Bidding Documents of Package PK2

235
TABLE OF CONTENTS Page Abbreviations Part I. Instruction to Bidders 1 2 Chapter I. Requirements on bidding procedures A. General Information B. Preparation of Bids C. Submission of Bids D. Bid Opening and Evaluation of Bids E. Contract Award 2 2 3 7 8 15 Chapter II. Bid data sheet 16 Chapter III. Evaluation Criteria and Contents for Evaluation 22 Chapter IV. Technical Proposal form Form 1: Bid Application (Technical proposal) Form 2: Power of Attorney Form 3: Joint-Venture Agreement Form 4: List of main construction machine and equipment Form 5: List of site testing instruments Form 6: Scope of work of sub-contractor Form 7A: List of key personnel Form 7B: Summary of qualification and experience of key personnel Form 8: On-going contracts of the Bidder Form 9: Similar contracts implemented by the Bidder Form 10: Summary on the Bidder’s activities Form 11: Financial capacity of the Bidder Form 12. Bid Security Chapter V. Forms of Financial Proposal Form 13. Bid application (Financial Proposal) Form 14. General Statement of Bid Price 35 36 37 38 40 41 42 43 44 45 46 47 48 49 50 51

Transcript of Bidding Documents of Package PK2

TABLE OF CONTENTS Page

Abbreviations

Part I. Instruction to Bidders

1

2

Chapter I. Requirements on bidding procedures

A. General Information

B. Preparation of Bids

C. Submission of Bids

D. Bid Opening and Evaluation of Bids

E. Contract Award

2

2

3

7

8

15

Chapter II. Bid data sheet 16Chapter III. Evaluation Criteria and Contents for Evaluation

22

Chapter IV. Technical Proposal formForm 1: Bid Application (Technical proposal) Form 2: Power of Attorney Form 3: Joint-Venture Agreement Form 4: List of main construction machine andequipment Form 5: List of site testing instruments Form 6: Scope of work of sub-contractor Form 7A: List of key personnel Form 7B: Summary of qualification and experience ofkey personnelForm 8: On-going contracts of the Bidder Form 9: Similar contracts implemented by the BidderForm 10: Summary on the Bidder’s activitiesForm 11: Financial capacity of the Bidder Form 12. Bid Security Chapter V. Forms of Financial ProposalForm 13. Bid application (Financial Proposal)Form 14. General Statement of Bid Price

35363738404142434445464748495051

Form 15. Detailed Statement of Bid PriceForm 16A. Analysis of Bid Price Unit – For detailed construction price unitForm 16B. Analysis of Bid Price Unit – For overall construction price unit

Form 17. Calculation of material price in the Bid Price Unit

52525354

55

Part 2. Requirements on construction 56Chapter VI. Introduction to Project and Bid package1. Project Introduction2. Package Introduction3. The time limid for completion

56565666

Chapter VII. Bill of Quantity Table 1: Part 1- Reclamation of Pavement areaTable 2: Part 2- Reclamation of Revetment areaTable 3: Part 3- Soil improvement of Pavement area Table 4: Part 4- Soil improvement of Revetment areaTable 5: Part 5- Pavement Table 6: Part 6- Drainage systemTable 7: Part 7- Protective Revetment along Thi Vai River

6767686984909297

Chapter VIII. Requirements on construction progressChapter IX. Technical requirements

100101

1. General requirements 2. Technical proposal of the Bidder3. Requirements on material4. Requirement on human resource 5. Requirement on construction equipment 6. Requirement on labor safety and environment

101102118124125127127

hygiene 7. Requirement on method and technique of construction8. Technical Specificationsa. Requirement on materialsb. Requirement on construction worksc. Requirements on warranty

129129129136

Chapter X. Detailed design Drawings 137Part III. Requirements on the Contract 138Chapter XI. General conditions of contractA.GeneralB.Schedule management C.Quality management D.Cost management

E.Contract completion and Termination

138138142143144145

Chapter XII. Specific conditions of contract 147Chapter XIII. Contract form 156Form 18. Contract 156Form 19. Contract performance security 159Form 18. Advance payment security 160

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

ABBREVIATIONS

BDS Bid data sheetGCC General conditions of the contractSCC Specific conditions of the contract

Circular 63/CPCircular No. 85/2014/ND-CP dated June 26,2014 of the Goverment detailing theimplementation of some articles ofBidding Law on Bidder Selection.

VND Vietnam Dong

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province1

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Part IINSTRUCTION TO BIDDERS

Chapter IREQUIREMENTS ON THE BIDDING PROCEDURES

A. GENERAL INFORMATIONItem 1. Contents of the bidding1. The Bid Solicitor would like to invite qualified

Bidders to participate in the construction package underthe Project mentioned in BDS. Name of the package and maincontents are described in BDS.

2. Contract performance period as defined in BDSshall be from valid date of the Contract to warrantyperiod. Contract performance period is stated in BDS.

3. Capital source for the package is defined in BDS. Item 2. Eligibility for tender 1. Ensuring legal status as stipulated in BDS;2. Submitting only one Bids as an independent Bidder

or joint-venture. It is necessary for the joint-venture tosubmit joint-venture agreement signed by all members inaccordance with Form 3, Chapter IV, clarifying name of theleading member, general and individual responsibilities ofeach member in the bid package;

3. Sastifying all requirements of the Bid Solicitoras stated in the Invitation to Bid.

4. Ensuring competitiveness as stated in BDS.5. Not being prohibited from tender activities as

specified in Article 89, Bidding Law. Item 3. Validity of materials, machine, equipment to

be used1. Materials, machinery and equipment used in the

construction activities must be of legitimate and clearorigin and meet other requirements mentioned in BDS. TheBidder shall provide origin of materials, machinery, andequipment; marking and brand of products.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province2

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

2. “Origin of materials, machinery and equipment” isunderstood as the country or region where the wholematerials, machinery and equipment are manufactured, or,where the final process is carried out in case productionprocess consists of a number of countries or regions.

3. Bidders must provide evidences for (suitability)compliance of materials, machines, equipments and goods inaccordance with requirements as stated in BDS.

Item 4. Bidding expenses The Bidders shall be responsible for any expenses

arising out of or in connection to bidding from theacquisition of the Bidding Document to letter ofacceptance, or to the signing date of contract in case ofwinning.

Item 5. Bidding Document and clarification1. Bidding Document consists of the contents stated

in the Table of Contents herein. The Bidders shall beresponsible for checking and reviewing contents of BiddingDocument to prepare their Bids.

2. Any difficulties of contents in the BiddingDocument shall be notified in writing to the Bid Solicitorfor clarification in the period and address as stated inBDS (A bidder may send a prior notice to the bid solicitorby fax, etc.). Upon receipt of request for clarificationin the period as stipulated in BDS, the Bid Solicitorshall provide a written feedback to all bidders.

If required, the Bid Solicitor shall organize a pre-tender meeting to discuss and clarify contents of theBidding Document. The contents of meeting shall berecorded in minutes and then forwarded to Bidders.

Item 6. Site inspection1. The Bidders are responsible for inspecting the

site for preparation of Bids. The Bid Solicitor shallfacilitate and instruct the Bidders to survey the site asstated in BDS. Any arisen expenses shall be borne by theBidders.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province3

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

2. The Bid Solicitor holds harmless from any riskssuffered by Bidders relating to site inspection includingaccident, loss of assets and other risks.

Item 7. Amendment to the Bidding DocumentIn case of amendment to the Bidding document, if

required, the Bid Solicitor shall amend the BiddingDocument (including extension of bids submission deadline,if required) by notifying Bidding Document amendment tothe Bidders prior to closing date of the bid package asstated in BDS. This amendment is an integral part of theBidding Document. The Bidder shall notify his receipt inwriting or by fax to the Bid Solicitor.

B. PREPARATION OF BIDSItem 8. Applicable languageBids as well as all communications between the Bid

Solicitor and Bidders in relation to the tender shall bemade in writing in the language as specified in BDS.

Item 9. Contents of BidsBids prepared by the Bidder shall include the

following contents:1. Technical proposal as stipulated in Chapter IV;2. Financial proposal as stipulated in Chapter V;3. Other contents specified in BDS.Item 10. Change in legal status of BiddersIn case of any changes in legal status of Bidders

after acquisition of the Bidding Document, such changesshall comply with provisions in BDS.

Item 11. Bid application The bid application of Bidders comprises bid

application for technical proposal in accordance with Form1 of Chapter IV and for financial proposal in accordancewith Form 13 of Chapter V of the Bidding Document. Thebid application shall be prepared and filled by the Bidderin accordance with Form 1 of Chapter IV with signature ofthe legal representative of the Bidder (the legal

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province4

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

representative or the authorized person of the Bidder asspecified in the Power of Attorney in accordance with Form2 of Chapter IV). In case of authorization, all relevantdocuments shall be submitted by the Bidders.

In case of joint-venture, the bid application shouldbe signed by the legal representatives of each member,unless otherwise the leading member is authorized to signon behalf of the joint-venture as specified in the joint-venture agreement. In that case, written authorization isenclosed by each member as if each member was anindependent bidder.

Item 12. Alternative technical proposal in Bids1. The techncial proposal stated in Bids (new design

alternative) replacing technicial proposals in BiddingDocument shall not be evaluated.

2. The Bidder desiring to submit an alternativetechnical proposal shall prepare Bids in accordance withBidding Document (the main alternative). In addition, theBidder shall provide all neccessary information includingshop drawing, bid price for alternatives specifying costs,specifications, construction methods and other contentsrelated to the alternative. The alternative shall beconsidered for bidder at lowest evaluated price only.

Item 13. Proposal of construction method in BidsExcept for the construction methods required to

comply with specified in the Bidding Document, bidder isentitled to propose construction methods for other worksin accordance with their abilities and characteristics ofthe package, but must sure to meet the technicalrequirements to complete the construction work asdesigned.

Item 14. Bid price and price list1. The bid price means price mentioned in the bid

application, price list including total expenses requiredto perform the bid package in accordance with requirementsof Bidding Document.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province5

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

2. The Bidder is required to fill the unit price andamounts for each work item in Bill of Quantity inaccordance with Form 14 and 15 of Chapter V. Bidapplication must consist of factors stipulated in BDS.

In case of any difference between the Bill ofQuantity and design found by either Bidder, such Biddermay send a notice to the Bid Solicitor and prepare aparticular price list for this difference for the BidSolicitor’s consideration. Such difference shall not beincluded in the bid price.

3. In case of a discount letter issued by eitherBidder, such Bidder may submit it together with theFinancial Proposal or separately; however, it should besubmitted before bid closing. In case the Bidder does notsubmit the discount letter with the Financial Proposal,the Bidder shall notify the Bid Solicitor prior to or atthe bid closing or shall prepare list of elements offinancial proposal including discount letter. The discountletter must be coverd with a sealed envelop stating“discount letter” with the warning text of not openingwith technical proposal. In the discount letter, thecontents and the method of discount to the specific itemsin the Financial Proposal, the Bidder shall notify Billof Quantity must be clarified.

4. Bidder analyzes the bid price according torequirements as stipulated in BDS, Bidder also fills allnecessary information in the Analysis of Bid price (as inForm 16A or 16B, Chapter V), Price list of materials inthe bid price (as Form 17, Chapter V).

Item 15. Currency of BidsThe bid price shall be offered by the currency

specified in BDS.Item 16. Evidence of legality, qualification, and

experience of Bidders1. Evidence of legality of the Bidders:a) For an independent Bidder, he should provide his

evidence of legality as stated in the BDS.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province6

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

b) For joint-venture, following documents should beprovided:

The documents described in Point a, this Item foreach member in the joint-venture;

The joint-venture agreement signed by all membersas stated in Sub-point 2 of Item 2 of this Chapter.

2. Evidence of qualification and experience: a) Capacity of mobilizing construction equipments

listed in accordance with Form 4 of Chapter IV (Biddermust prove its mobilizing all main equipment forconstruction); list of key personnel at the site in Form7A, 7B of Chapter IV; list of on-going similar contractsin Form 8 and 9 of Chapter IV; Summary of Bidder’sactivities in Form 10 of Chapter IV; Financial capacity ofBidder in Form 11 of Chapter IV. The qualification andexperience of joint-venture Bidders refer to those of eachmember in relation to works taken by them. Each member isrequired to prove its experience and qualification to meetrequirements of Bidding Document for the assigned tasks inthe joint-venture.

b) Other documents specified in BDS.Item 17. Bid security1. Upon bidding, a bid security is provided by

either Bidder as stated in the BDS. In case of joint-venture, a bid security will be provided in one or twomanners as follows:

a) Each joint-venture member shall provide its bidsecurity separately but should ensure that the total valueis not lower than the required amount in Item 17.1 of BDS;in case of any illegal bid security, Bids of the joint-venture shall be rejected in accordance with the precedentconditions.

b) Joint-venture members agree on a member beingresponsible for the bid security of the joint-venture. Inthis case, bid security shall include name of the joint-venture or of the member being responsible for bidsecurity of the joint-venture but the total value is not

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province7

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

lower than the required amount as specified in Item 17.1of this BDS.

2. Bid security shall be null and void in one offollowing cases: lower value, incorrect currency, shortervalidity, wrong name and address of the Bid Solicitor) andtime as stipulated in the Bidding Document, incorrect nameof package, Bidder (in accordance with Point 1 of thisItem for the associate Bidder), non-original and withoutlegal signature (for guarantee of bank, financialinstitution). In case of necessity, the Bid Solicitorshall require the Bid to provide documents proving thevalidity of bid security (Power of Attoney, duties of bankor financial organization, and authorized representativeof bid security), the bidder shall be resposible forproviding these full documents.

3. The bid security of the unsuccessful Bidder shallbe returned within the period specified in the BDS. Forthe successful Bidder, bid security shall be returnedafter contract performance security is provided byBidders.

4. The Bid Solicitor shall confiscate bid security ofBidder in the following cases:

a) Bidding Document and proposal are withdrawn by theBidder after bid closing but the Bidding Document is stillvalid;

b) The Bidder violates the bidding law resulting inbidding cancellation in accordance with regulations inArticle 17.4 of Bidding Law No. 43/2013/QH13;

c) The Bidder does not provide contract performancesecurity in accordance with regulations in Article 66 andArticle72 of Bidding Law No. 43/2013/QH13;

d) The Bidder fails or refuses performing contractconclusion within 20 days from the letter of acceptanceprovided by the Bid Solicitor or contract conclusion butnot sign other than force majeure;

Item 18. Validity of Bids

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province8

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

1. The validity of Bids should be in strictaccordance with the provisions specified in BDS and takeeffect as of the bid closing; Bids of shorter validityshall be null and void.

2. The Bid Solicitor may request in writing theBidder to extend validity of Bids one or many times butshall not be later than 30 days in attachment with therequest for the extension of validity of bid guarantee. Ifthe Bidder rejects the extension, this Bids shall receiveno further consideration and the bid security of suchBidder shall be returned.

Item 19. Bids specifications and signature in Bids1. The Bidder should prepare one original and some

copies of Bids specified in the BDS and mark the relevant"original" and "copy ." The Bidder shall be responsible forthe accuracy and satisfaction between the copies and theoriginal. During assessment, if the Bid Solicitor finds anytechnical mistake such as blur copy, unclear text, pagemissing, etc., the content of the original shall prevail.In case the content of the copy is different from theoriginal, subject to the level of difference, the BidSolicitor shall provide suitable handling decision (thatdifference is not significant, making little change to thenature of the Bids) shall be deemed as acceptable; if thatdifference causes great change to the fundamental contentof the Bids as compared with the original, it shall bedeemed as fraud and rejected, and the Bidder will also betreated in accordance with the provisions in the BiddingLaw.

2. The Bids should be typed, printed in inerasableink, paged in continuous order. The Bid application,discount letter (if any), the additional documentclarifying the Bids, price list and other forms of ChapterIV should be signed by the legal representative of theBidder.

3. The inserted, deleted and overlapped letters onthe typing original shall only be valid when it is

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province9

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

provided with the signature of the bid application signerbeside and sealed (if any).

C. SUBMISSION OF BIDSItem 20. Sealing and Marking of Bids1. Bids shall include the contents mentioned in Item

9 of this Chapter. The original and copy of Technicalproposal should be contained in the envelop with outsideseal stating “Technical proposal”. Similarly, FinancialProposal should be contained in sealed envelop and marked“Financial proposal” with the warning text “Do not open atthe time of opening Technical proposal” (sealing methodshall be stipulated by the Bidder). The layout ofinformation on Bids envelop shall be specified in BDS.

2. In case Bids includes many documents, the Biddershall carry out packaging the whole document so that thereceipt and preservation of all Bids of the Bid Solicitorshall be convenient, ensuring the intactness of Bids andavoiding loss. If possible, the Bidder should package inseveral little envelops for easy transportation, eachshould be specified with number to ensure the consistencyand shall be packaged, sealed, and specified in accordancewith the provisions in this Item.

Item 21. Deadline for Bids submission 1. Bids directly submitted by the Bidder or sent to

the address of the Bid Solicitor but should make sure thatthe Bid Solicitor receives it before bid closing specifiedin BDS.

2. The Bid Solicitor can extend the time-limit forBids submission (time of bid closing) in case it isrequired to increase the number of Bids or amendment tothe Bidding Document in accordance with the provisions inItem 7 of this Chapter or the requirements of the Bidderwhen the Bid Solicitor find it necessary.

3. Upon Bids extension, the Bid Solicitor shallnotify in writing to the Bidder purchasing BiddingDocument, and the time-limit for Bids should be printed in

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province10

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

the Bidding Newspaper at least one period and theelectronic information page (excluding the cases notspecified as compulsory); for the international bidding,it must be printed on a widely distributed Englishnewspaper. Upon notification, the Bid Solicitor shallspecify the new bid closing time so that the Bidder shallchange the validity of Bidsif necessary. The Biddersubmitted Bids can get it back and change Bids. In casethe Bidder has not got Bids yet or does not get it back,the Bid Solicitor shall manage the document as“confidential.”

Item 22. Late submission of BidsAny documents including the discount letter (if any)

received by the Bid Solicitor after bid closing shall bedeemed as invalid and shall be returned to the Bidderintact except the documents clarifying Bids as requestedby the Bid Solicitor in Item 25 of this Chapter.

Item 23. Bids amendment or withdrawal When it is desired to amend or withdraw the

submitted Bids, the Bidder should provide proposaldocument and the Bid Solicitor shall only approve if hereceives such document before bid closing; the proposaldocument for Bids withdrawal should be sent in separationwith Bids.

D. BID OPENING AND EVALUATION OF BIDS

Item 24. Opening Technical proposal:The Technical proposal opening shall be publicly

carried out within 1 hour right after bid closing inaccordance with time and location specified in BDS. TheTechnical proposal should be only openned before bidclosing as required in the Bidding document before thewitness of the attendants and shall not be dependent onthe absence or presence of the invited Bidders;

The bid opening shall be performed according to thealphabetical order for the name of the bidders and inaccordance with following consequence:

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province11

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

- Checking the seal of Bids;- Opening Bids and stating main information: Name of

Bidders; number of originals, Bid application in Technicalproposal, Valid time of Technical proposal, Time ofContract implementation, Value, validity and bidsecurity; and other related information;

The Bid opening minutes: Information stated in Point bof this Clause should be included in the Bid openingminutes.

The bid opening minute should be signed forconfirmation by the representatives of the Bid Solicitor,present Bidders and the concerned agencies. Copies of thebid opening minutes shall be sent to all bidderssubmitting bids;

The representative of the Bid Solicitor shall sign forconfirmation on the original of bid application and powerof attorney of legal representative of the Bidders (ifany); associate agreement (if any); Bid sercurity;important contents of each Technical Proposal;

The Financial proposal Financial Proposal of all Bidders shall be sealed in a

separated envelop by the Bid Solicitor and shall be signedby representatives of the Bid Solicitor and participatingBidder.

Item 25. Bids clarification 1. During bids assessment, the Bid Solicitor can

require the Bidder to clarify the content of Bids. In caseof lack of documents proving eligibility, qualificationand experience. For Technical proposal, the Bidder isrequired to supplement documents proving the eligibility,qualification and experience given that no change in bidsand unit price is resulted.

2. In case the bidder finds that his bid lacksdocuments proving eligibility, qualification andexperience, the bidder is allowed to submit documents tothe Bid Solicitor to clarify his eligibility,qualification and experience. The Bid Solicitor shall beobligated to receive these documents of the Bidder for

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province12

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

review, evaluation; additional documents provingeligibility, qualification and experience shall be deemedas part the Bid.

3. The clarification of Bids shall only be performedbetween the Bid Solicitor and the Bidders with Bids to beclarified and shall ensure principle of no change innature of bidders. The content of Bid clarification shownin the document shall be preserved as a part of Bids.

Item 26. Assessment of Technical proposal1. The legality of the Technical proposal shall be

checked, including:a) Checking the quantity of originals, copies off

Technical proposal;b) Checking contents of Technical proposal, including:

Bid application in Technical proposal, Associate Agreement(if any), Power of Attorney for signing Bid Application(if any); Bid Security; documents proving eligibility;technical proposal; other contents in Technical Proposal;

c) Checking the consistency between the original andthe copy to serve the detailed assessment process oftechnical proposal;

d) Attached appendix, documents to the Technicalproposal stated in BDS.

2. Assessing the validity of the technical proposal:Technical proposal of Bidders are considered valid

when including full contents as follows: a) The original of the Technical Proposal;b) Bid Application in Technical Procedures signed and

sealed by the bidder’s legal representative (if any); Inthe Bid Application, the Bidder shall specify schedule forpackage implemantation in accordance with technicalproposal. For joint venture bidders, the Bid Applicationshould be signed and sealed by each member (if any) or thehead of the joint venture bidders on behalf of the joint

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province13

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

venture bidders in accordance with responsibilityassignment in the associate agreement;

c) The validity of the Technical proposal that meetrequirements shall be in accordance with regulations inBidding Document;

d) Bid Security with value and validity period meetrequirements of Bidding Document. In case the submit ofBid Sercurity is stipulated in the form of susbmit ofguarantee letter, the guarantee letter should be signed bylegal represeantative of credit institutions or branch offorreign bank established under Vietnamese Law with valueand validity period, benificiary in accordance withrequirements of Bidding Document;

d) The name is not included in two or more Technicalproposal as the main bidder (independent bidder or amember of the joint venture);

e) Joint venture Agreement signed and sealed (if any)by legal representative of each member of the jointventure;

g) The Bidder is not prohibited from participating inbid activities under regulations of Bidding Law;

h) The Bidder ensure eligibility in accordance withClause 1 in Article 5 of Bidding Law

The Bidder having eligible Technical proposal shall beconsidered for assessment of capability and experience.

3. Assessment of capability and experience:a) Capability and experience assessment of the Bidder

shall be in conformity with the standards for capabilityand experience specified in Item 1 of Chapter III;

b) The Bidder having eligible Technical proposal,capability and experience meeting reuirements shall beconsidered for technical assessment;

4. Technical assesment:

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province14

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

a) Techncial assessment shall be performed inaccordance with assessment standards stipulated in Item 2,Chapter III;

b) The Bidders meeting technical requirements shall beconsidered for assessment of Financial Proposal.

5. The list of Bidders meeting technical requirementsshall be approved in writing and based on the statement,appraisal report on results of technical assessment, thelist is delivered to all Bidders and the Bidders meetingtechncial requirements are invited to the opening ceremonyand open Financial Proposal.

Item 27. The opening of Financial proposal1. Checking the seal of the Financial proposal. 2. Opening the Financial proposal:a) Only Financial proposal of the Bidders named in the

list of Bidders meeting technicial requirements shall beopened in the presence of represenatives of Bidderattending the opening ceremony of Financial Proposal, notdepending on the presence or absence of the Bidders;

b) Represenative of each attending Bidder is requiredto open Financial proposal corfirming whether or notinclude discount letter in his Financial proposal;

c) The opening of Financial proposal shall be carriedout for each Financial Proposal in alphabetical order ofthe name of Bidders in the list of Bidders meetingtechnical requirements and shall be in the followingsequence:

- Checking the seal;- Opening the Financial proposal and Reading

information: The name of the Bidder; the quantity oforiginals, copies; the validity time of Financialproposal, Bid Price stated in the Bid Application;discount value (if any); technical point of bids meetingtechnical requirements, other relevant information.

3. The minutes of opening Financial proposal:

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province15

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

a) Information stated in Clause 1 and Clause 2 of thisArticle shall be included in the minutes of openingFinancial proposal. The minutes of opening Financialproposal should be signed for confirmation by therepresentatives of the Bid Solicitor, Bidders attendingthe opening of Financial proposal. This minutes shall besent to all Bidder meeting technical requirements;

b) Representative of the Bid Solicitor shall sign forconfirmation on all originals of Financial Proposals.

Article 28. Assessment of Financial proposal1. The legality of the Financial proposal shall be

checked, including:a) Checking the quantity of originals, copies of

Financial proposal;b) Checking contents of Technical proposal, including:

Bid application in Technical proposal, consolidated Pricelist, detailed Price list, detailed unit price analysis(if any), other contents in Financial Proposal;

c) Checking the consistency between the original andthe copy to serve the detailed assessment process offinancial proposal.

2. Assessing the validity of the financial proposal:Financial proposal of Bidders are considered valid

when including full contents as follows: a) The original of the Financial proposal;b) Bid Application in Technical Procedures signed and

sealed (if any) by the bidder’s legal representative inaccordance with requirements of Bidding Document; bidprice in bid application must be detailed, fixed in numberand in words logically consistent with total bid price inthe consolidated price list. Do not propose different bidprices or enclosed with conditions detrimental to theEmployer and the Bid Solicitor. For joint venture bidders,the Bid Application should be signed and sealed by eachmember (if any) or the head of the joint venture bidders

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province16

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

on behalf of the joint venture bidders in accordance withresponsibility assignment in the associate agreement;

c) The validity of the Financial proposal that meetrequirements shall be in accordance with regulations inBidding Document.

The Bidder having eligible Financial proposal shall beconsidered for detailed financial assessment.3. Detailed assessment of financial proposal and bidderranking:

The financial assessment shall be perfomed usingcopies. The Bid Solicitor carry out mistake correction anddifference adjustment of Financial proposal in accordancewith regulations in Item 29 and 30 of this Chapter andFinancial proposal shall be assessed in accordance withfinancial assessment standards stated in Item 3 of ChapterIII.The Bidder having lowest price assessment was rankedfirst.

Item 29. CorrectionMistake correction means the mistakes in Bids

including the arithmetic, other mistakes and shall becarried out in the following principles:

a) For the arithmetic mistakes including those causedby inaccurate addition, subtraction, multiplication,division when calculating bid price. In case BiddingDocument require detailed unit price analysis, figures indetailed unit price analysis shall prevail for arithmeticmistake correction. In case of inconsistency between unitprice and amount, the unit price shall prevail for mistakecorrection; if abnormal diferences are found in the unitprice due to decimal mistakes (10 times, 100 times, 1000times), amount shall prevail for correction;

b) For other mistakes: -The amount column filled with no relevant unitprice, the unit price shall be additionally identified bydividing the money to quantity; When unit price isprovided, but the amount column is left blank, the amount

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province17

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

shall be additionally identified by multiplying quantitywith unit price; If any content filled with unit price andamount but left with no filling of quantity, the quantityshall be additionally by dividing the amount to the unitprice of that content. In case the number is additionallyidentified mentioned different from that referred to inthe Bidding Document shall be deemed as variation in scopeof supply and shall be adjusted in accordance with theprovisions in Clause 2 of this Chapter;

- Unit confusion: Correct in accordance withrequirements of Bidding Document;

- In case of inconsistency between the contents ofTechnical proposal and Financial proposal, contents ofTechnical Propossals shall prevail for mistake correction. - In case of inconsistency between the number andtext, the text shall be the basis for variationadjustment. If the text is wrong, the number shall prevailfor arithmetic mistake correction (if any) in accordancewith provisions in point a of this clause; - In case of difference between the pricespecified in the bid application (excluding discount) andthe price in the consolidated price list, the variationadjustment shall be based on the consolidated price listin accordance with the detailed price list.

2. After making the mistakes basing on the aboveprinciples, the Bid Solicitor shall notify the Bidder inwriting. The Bidder should provide the notificationdocument for the acceptance to the aforesaid correction.In case the Bidder does not accept the correction, hisBids shall be rejected. In case Bids has the arithmeticmistake whose total absolute value is over 10% of bidprice shall also be rejected. The arithmetic mistakecalculated in accordance with total absolute value,independent on the increase or decrease after correction.

Item 30. Variation adjustment Variation adjustment means the adjustment to the

contents of insufficiency or redundancy in Bids in

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province18

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

comparison with the requirements for the Bidding Document.The variation adjustment shall be as follows:

a) In case of variation about the scope of supply,the missing offer shall be added; the redundant one shallbe subtracted in accordance with corresponding unit pricelevel bids with variation of the Bidder; in case no unitprice is inluded in bids of bidders with variation, thehighest offer price for this content among other Bidspassing technical assessment shall prevail for variationcorrection; If no unit price is inclued in Bids of theBidders passing technical assessment, unit price rate inestimation shall prevail for correction; If no bid packageestimation is made, unit price forming bid package priceshall prevail for correction;

In case only one Bidder passes technical assessment,corresponding unit price in Bids of these Bidders shallprevail for variation adjustment; If no unit price isinclued in Bids of the Bidders passing technicalassessment, unit price in estimation shall prevail forcorrection; If no bid package estimation is made, unitprice forming bid package price shall prevail forcorrection;

b) In case the Bidder offers with lack of taxes, feesand charges payablr under requirements stated in theBidding Document, the Bid Solicitor shall add these coststo the bid price. The costs shall not be included ininsufficiency prescribed in Point d Clause 1, Article 43of Bidding Law;

c) In case the Bidder has a discount letter, themistake correction and variation adjustment are performedon the basic of bid price that has not subtracted discountvalue. The percentage (%) of i insufficiency shall bedetermined by comparing to the bid price stated in the bidapplication;

d) In case the Bidder whose variation adjusted bidsranks the first, is invited for contract negotiation, thelowest unit price among other bids passing technical

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province19

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

assessment shall be taken for negotiation ofinsufficiency.

Item 31. Conversion to a common currencyIn case the Bidders offer price in different

currencies in accordance with the provisions in Item 16 ofthis Chapter, Bid offered with other currencies shall berejected.

Item 32. Contacting the Bid SolicitorUnless otherwise requested to clarify Bids in

accordance with the provisions in Item 25 of this Chapter,contract negotiation (for complex erection package, ifany), contract completion, no Bidder is entitled tocontact the Bid Solicitor about the issues in relation tohis Bids as well as in relation to the bid package frombid opening until the tender result is announced.

Item 33. Contract negotiation1. On the basic of the Employer’s decision, the Bid

Solicitor invites the Bidder ranked first in the list ofapproved Bidder ranking for contract negotiation. In caseof contract negotiation authorization, the Bidder shallhave a valid Power of Attorney in accordance with Form 2of Chapter IV of this Bidding Document.

2. Contents of contract negotiations a) Negotiating the contents that are not detailed,

unclear or inappropriate, in consistent between theBidding Document and Bids, between different contents inBids resulting in disputes or affecting liability of theparties in the course of contract performance;

b) Negotiating deviations found and proposed by theBidder in the Bidding Document (if any), includingchanging proposals or alternatives of the Bidder if aregulation allowing the Bidder to offer alternative isincluded in the Bidding Document;

c) Negotiation of personnel:

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province20

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

During negotiation, the Bidder shall not change thekey personnel proposed in Bids to the position of Sitemanager except the case the proposed key personnel cannotparticipate in contract performance because bid assessmenttime extends longer than prescribed or because of forcemajeure. In that case, the Bidder is entitled to changethe key personnel ensuring that expected personnel havequalification, experience and capability equal to orhigher than proposed personnel and the Bidder shall notchange the bid price;

d) Negotiating the issues arising in the process ofselecting Bidder (if any) aiming at completing detailedcontents of the bid package;

d) Negotiating other necessary contents.3. During contract negotiation, the parties attending

negotiation complete draft of contract documents, contractappendices including detailed list of the scope of work,price list, implementation schedule.

4. In case the Bidder is invited to negotiate thecontract with time specified in the BDS fails to reach anagreement, the Bid Solicitor shall notifies the Employerto consider and decide the next ranked Bidder tonegotiate; in case the negotiation with the next rankedBidder is not successful, the Bid Solicitor shall notifiesthe Employer to consider or decide tender cancellationunder regulations in Clause 1 Article 17 of Bidding Law.

E. CONTRACT AWARD Item 34. Conditions for consideration of Contract

Award recommendationThe Bidder shall be considered for Contract Award

recommendation when he meets all the following conditions:1) Having valid Bids;b) Meeting requirements on capability, experience in

Bidding Document;

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province21

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

c) Providing technical proposal which is assessed assatisfactory to the requirements in accordance withBidding Document;

d) Insufficiency does not exceed 10% of bid price;d) Having lowest bid price after mistake correction

and difference adjustment and subtraction of discount (ifany) under assessment method in Item e3 of Chapter III;

e) Having the proposed Contract Award price nothigher than the approved bid package.

Item 35. Right of the Bid Solicitor for accepting,rejecting bids or cancelling tender

The Bid Solicitor shall be entitled to accept orreject any Bids or cancel tender but obeying Law ontender, amended law and implementation instructiondocuments.

Item 36. Bid result notificationAfter the approval for the bid result, the Bid

Solicitor shall send the document notifying the bid resultto the participants (including successful and unsuccessfulbidders).

Item 37. Contract completion and signingAfter achieving the negotiation result and completing

the contract, the Employer and the Bidder shall carry outcontract signing. In case of associate, the contractsigned should include the signature of all the members ofthe associate.

Item 38. Performance securityThe successful Bidder is required to perform the

measures ensuring contract performance in accordance withthe provisions in Item 3 of Chapter X to ensure his ownobligation in contract performance.

The Bidder shall not receive the performance securityin case of refusal to contract performance after thecontract takes effect, violating agreements in thecontract and delay in contract implementation due to their

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province22

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

fault but refusing to extend validity of performancesecurity.

(End of Chapter I)

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province23

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Chapter IIBID DATA SHEET

This bid data sheet consists of details of thebid package as per corresponding sections included inChapter I (Requirements on tender procedures). Ifthere is any contradiction or conflict betweencontents dealing with the same topic in Chapter I,then the contents in this Section shall be preferred.

Item Point Content1 1 Name of the package PK2: Onshore works - Phase 1:

Reclamation, Soil Improvement, Internal roadsand yards, Water drainage system andRevetment along Thi Vai RiverProject name: THI VAI PORT CONSTRUCTIONINVESTMENT PROJECT Name of Bid Solicitor: THI VAI INTERNATIONAL PORTCO., LTDMain work content: Reclamation, Soil Improvement,Internal roads and yards, Water drainagesystem and Revetment along Thi Vai River inaccordance with approved Design Documents andconstruction drawing including followingitems:

1. Reclamation;2. Soil Improvement;3. Internal roads and yards;4. Surface water drainage system;5. Revetment along Thi Vai River.

Construction location: Phu My Town, Tan BarDistrict, Ba Ria – Vung Tau Province.

2 Term for contract implementation: Maximunduration is 24,0 months. Day of implementation including days off,

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province24

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

holidays, Tet Holiday since the date theContract takes effective.

3 Capital source for contract implementation:Capital owned and commercial borrowed funds

2 1 The Bidder shall be eligible if satisfying allthe following conditions:

a) Registration Certificate ofEstablishment, Certificate of Operation issuedby competent authorities of the country wherethe Bidder and the Employer are working;

b) Independent economic accounting;c) Not being assessed by authorized bodies

to have the unhealthy financial status;proceeding to bankruptcy or in debt withoutliquidation; or being on the way of winding up

d) Ensuring competitiveness in biddingunder regulations in Article 6 of this Law;

e) Not in period of bidding prohibition;g) Being included in the short list in case

the short list has been selected.In case of associate, there must be a writtendocument among the members specifyingresponsibility of the head and generalresponsibility, specific responsibility ofeach member in associate in accordance withForm 3 of Chapter IV.

4 Ensuring competitiveness in bidding: inaccordance with Article 6 of Bidding Law No.43/2013/QH13 and Article 2 of Decree No.63/2014/ND-CP

3 1 Other provisions of the eligibility ofmaterials to be used:- In Bids, the Bidder must specify the origin,manufacturer, code of products, specificationsof all materials used in the Works. Allmaterials used shall meet quality standards

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province25

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

under TCVN or other standards stipulated inBidding Document for these materials. Allmaterials shall be fully detailed andtabulated.- The Bidder shall offer materials meetingtechnical requirements stated in BiddingDocument, design document, constructiondrawing or products with equal or higherspecifications, quality and functions. TheBidder must prove the equivalence orsuperiority of materials offered compared torequirements of Bidding Document.- For each category of materials, the Biddershall be entitled to offer a corresondingproduct of the same brand, code of productsand origin to ensure the uniformity ofequipment and materials used in the Works.

3 Evidence documents for conformity(satisfactory) of materials in Bids:- Detailed list of materials, equipments forthe Works under Form 4 of Chapter IV;

- Catalogues, technical documents, conformitycertificate and conformity announcement ofthe main materials.

- As for imported products, following documentsare required:+ Import declaration (a certified copy);+ Certificate of Origin issied by Chamber ofCommerce and Industry of manufacturingcountries (for imported goods) (C/O)(original);

+ Certificate of quality and quantity of themanufacturer (C/Q) (original);

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province26

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

+ Test report of Manufacturer (original);+ Certificate of Quality issued by acompetent authority under regulations oflaw;

+ Packing list (copy);+ Results of recognized laboratory (ifnecessary) and test results of quantity,quality and category of materials,equipment from organzation recognized btcompetent authorities of State (ifnecessary);

+ Technical documents, warrantyspecifications.

5 2 - Term for receipt of the written bidinterpretation documents is not later than 07days before the bid closing.- Address of the Bid Solicitor: Thi VaiInternational Terminal Co., LtdAddress: Phu My Town, Tan Bar District, Ba Ria– Vung Tau ProvinceTel: 064.3895.807 Fax: 064.3895.808

6 1 In case the Bidder deems it necessary tosurvey the site to make Bids, the Bidder shallnotify the Bid Solicitor no later than 07 daysbefore bid closing. The Bid Solicitor shallarrange reasonable time for the Bidder toinvestigate the site.

7 Amended document of Bidding Document (if any)shall be sent to Bidders purchasing BiddingDocument at least 05 days before bid closing.

8 Language in use: Vietnamese For technical Catalog of genuine, English orVietnamese can be used.

9 3 The Bidder shall provide written Commitments

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province27

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

including following contents:- Works warranty of the Bidder which commitswarranty period is at least 12 months sincethe date of handover and putting into use.- Commitment on providing certificate ofwarranty for the main materials. - Commitment on labor safety, sanitation andfire prevention in the construction site.

10 Alteration of the eligibility status:In case Bidders needs to change his status(name) when attending tender compared to whenbuying Bidding Document, they have to sendsend a written notification on the alterationof the eligibility status (if any) to the BidSolicitor. The Bid Solicitor accepts suchalteration of the eligibility status uponreceipt of Bidder’s notification 10 daysbefore the bid closing. The alteration of theeligibility status is eligible when approvedin writing by the Employer before bid closing.When necessary, the Bid Solicitor shall send awritten approval in advance by fax, theoriginal shall be sent by post. In case ofdisapproval of the alteration of theeligibility status, the Bid Solicitor shallstate the reasons in accordance withregulations of Bidding Law.

11 Documents to prove the eligibility of theauthorized person:- Having valid Power of Attorney in accordancewith form in Bidding Document filled with fullinformation and signed by the legal attorneyand authorizer of the Bidder.

14 2 Bid price: Bid price is the consolidated unitprice including all necessary costs includingtaxes and fees for completion of a work inBill of quantity.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province28

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

4 Unit bid price analysis:The Bidder shall analyze unit price of items inBill of Quantity.

15 Currency of Bid: The Bidder shall offer byVietnam Dong (VND) only. If the Bidder offersby other currencies, the Bid shall berejected.

16 1 a) Documents proving eligibility of theBidder: - Units attending the tender shall preparevalid Bid Application (in accordance with formin Bidding Document – Form 01) in Bids. TheBid Application should be signed, sealed bycompetent person (in case of authorization,Power of Attorney Form 02 is required)- Having notarized copies of followingdocuments: Business Registration Certificateor Investment Certificate issued underregulations of Law;

2 b) Other documents to prove the capabilitiesand experience of the Bidders:1. Documents proving financial capability ofthe Bidders:- A notarized copy of audited FinancialStatement of 2011, 2012 and 2013.- Charter capital > 150 billion dong. In caseof associate, the head of the associate musthave charter capital of > 150 billion dong andother members must have charter capital of >15 billion dong.2. Documents proving capability on personneland equipment of the Bidders: - A list of personnel and technical staff ofthe Bidder certified by the Bidder inaccordance with Form 7A of chapter IV.- Certified declaration of capability,experience of key personnel of the Bidder in

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province29

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

accordance with Form 7B of chapter IV. - Key personnel operating construction on thesite shall present a notarized copy ofuniversity degree or suitable practicecertificate to prove.- For the Site manager: The Bidder shallpresent full documents proving the capabilityof the Site manager ranks grade 2 or higherunder regulations in Article 52 Decree No.12/2009/ND-CP.The documents include: copies notarized bycompetent authority: university degree,Certificate of Professional training for Sitemanager issued by training institutionspermitted by Ministry of Construction,declaration of capability, copy of valid laborcontract with the bidder and documents provingexperience of working as a Site manager insimilar projects.- The list of machinery, equipment servingconstruction, installation, inspection ofequipment in accordance with Form 4, 5 ofChapter IV.- The Bidder shall submit a notarized copy ofentire on-going contract enclosed with thelatest approval (of the Employer of on-goingcontract) on construction schedule andmobilization of personnel, equipment to provethe capability of mobilizing personnel,equipment available as proposed in Bidsmeeting this Bidding Document to implement thebid package.3. Documents proving experience of theBidders:

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province30

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

- The list of years of establishment andoperation in the fields of TransportationConstruction or/and Shipping Constructionenclosed with legal documents for proving.- Copies notarized by competent authorities ofat least 02 contracts of projects with similarnature and scale or greater.

17 1 Contents required in bid security:- Form of bid security: bank guarantee orfinancial institutions legally operating inVietnam- Value and currency of Bid Security: VND6.000.000.000 (Six billion dong only). - The valid term of Bid Security: 120 dayssince the bid closing

3 Bid securities shall be returned to non-winning Bidder: within a time-limit of 30 daysas from the date of notification of results ofbidding

18 1 The valid term of Bids is 90 days since thebid closing.

19 1 Number of Bids for submission: 01 original and05 copies, 01 CD-Rom with full information ofbid price

20 1 Way to present information on Bids Envelop: The Bidders must fill all of following information on BidsEnvelop:- Name, address, telephone number of the Bidder: ______________- Address of bid submit (name, address of the Bid Solicitor): __________- Name of the package: _________________________- Do not open before ___ hour, day ___ month ___ year ___(recording according to time of bid opening)Name and address of the Bid Solicitor: Name: Thi Vai International Port Co., Ltd

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province31

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Address: Phu My Town, Tan Bar District, Ba Ria– Vung Tau ProvinceTel: +84 643 895 807; Fax: +84 643 895 808.

21 1 Bid closing time: 09 am, on February 12, 201524 1 The bid opening shall be openly implemented at

09.05 am, on February 12, 2015 at the officeof Thi Vai International terminal Co., Ltd.

26 1 d) The attached documents in technicalproposal: other relevant documents if any

33 4 The Bidder must send a written approval formto negotiate and fulfill the contract within10 days since the date of receipt of winningresult.

(End of Chapter II)

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province32

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Chapter IIIEVALUATION CRITERIA AND CONTENTS FOR EVALUATIONSection 1. Evaluation criteria of qualification andexperience of Bidder

Evaluations criteria of qualification and experienceof Bidder shall be classified into different criteria of“Qualified”, “Unqualified”. The Contractors satisfying all3 items defined in item 1, 2, 3 and 4 in the followingtable shall be assessed as eligible in qualifications.Item 1, 2, 3 and 4 are considered as “satisfy" once alldetailed content in each point are satisfactory.

AS on qualifications of the Contractors shallinclude:No. Content Minimum requirements 1 Experience1.1 General experience in:

Years operating inconstruction of trafficworks or/and maritimework..

Certificate of BusinessRegistration orEstablishment License hasmore than 10 years ofexperience. In case ofjoint venture, leadingmember has to certificateof business registrationor Establishment Licensewith more than 10 years’experience, and othershave Certificate ofBusiness Registration orEstablishment License withmore than 5 years’experience.

1.2 Experience in constructing similar bid package:

More than (or equal) 02contract similar infeatures and complexity

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province33

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No. Content Minimum requirements Number of constructioncontracts implemented asa main Bidder of sub-Bidder, joint ventureBidder in Vietnam andforeign. (Copy of contractand minutes of acceptance andput into service (for completedwork) must be certified bycompetent authority)

(Reclamation; treatment ofsoft soil layer, verticalartificial drain,construction of dike,basin root, and otherconstruction from LevelIII or greater) and scope(contract value ≥ 50%construction performancevalue  of this package). (For joint venturebidders, member of jointventure must have 02contract similar to thework volume in jointventure)

2 Technical qualification 2.1 Capabilities in

construction operation To meet requirements ofGrade 2 in accordance withArticle 52 of Decree No.12/2009/ND-CP.

2.2 Site manager must bequalified to implementthis construction (has fullof documents in according toSection 16 clause 2 BDS, thisdocuments must be certificated bycompetent authorities)

Site manager must be satisfied with following work requirements:- To be a constructingengineer holding atertiary or higher degreein transport or waterwayport issued university oftechnology; - Have valid laborcontract; - Have minimum of 10 yearsexperiences in leveling insoft soil layer;

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province34

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No. Content Minimum requirements - Supervise constructionin Grade II or 02constructions in Grade III(work constructioncontracts, assignmentsheet or Decision onappointing, minutes ofacceptance); - Certificate of work Sitemanager professionaltraining issued bytraining facilities withpermission of Ministry ofConstruction;

2.3 Officers in charge oflabor safety, firefighting, and environmenthygiene shall besatisfied withrequirements (it is required toprovide a copy of certificatecertificated by competentauthorities, certificate ofprofessional training in laborsafety; a copy of labor contractwith bidder)  

At least:- 01 Engineer of fire

fighting;- 01 Environmental

Engineer- 03 construction

engineers withcertificate of laborsafety in accordancewith applicablerequirements.

2.4 The number of offices andengineers with majors:construction, transport,harbor, geology (practicecertificates in handlingwith soft soil layer);Construction economics,construction materials,construction engineers

Have at least 15construction engineerswith majors: Construction;Transport, harbor, geology(practice certificates inhandling with soft soillayer); Constructioneconomics, constructionmaterials, construction

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province35

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No. Content Minimum requirements with evaluationcertificate, Engineer ofconstruction machinery,measurement, engineer ofwater supply anddrainage, mechanicalengineer(Document: copy ofprofessional certificate,certificates, labor contract, socialinsurance book).

engineers with evaluationcertificate, Engineer ofconstruction machinery,measurement, engineer ofwater supply and drainage,mechanical engineer.

2.5 Number of workers ofBidder (with labor contract,certificate (if any) for proving)

Have more than 50 workersshown in Form No. 7A,Charter IV

2.6 Main constructionequipment: In case of joint venture,construction equipmentare equipment proposed byeach member of jointventure (For each kind of equipment,requirements on technique andfunctions, quantity shall be clearlystated. It is required to prove itsmobilization capability to meetrequirements of the bid package)

Enumerate list ofconstruction equipmentwith types, quantitymeeting Form No. 4, 5,Chatter IV andrequirements of BiddingDocument according to listin Charter IX. Bidders shall sendcertified copies of on-going contracts enclosedwith last approval (ofEmployer of on-goingcontract) of constructionprogress and progress ofequipment and humanresources mobilization asproposal in Bids to meetrequirements of BiddingDocument.

3 Financial capability

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province36

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No. Content Minimum requirements 3.1 Financial statement in 3

years: 2011, 2012, 2013A certified financialstatement 2011, 2012 and2013 were audited.

3.2 Annual turnover in 2011,2012, 2013.

annual turnover ≥ 250billion dong In case of joint venture:Annual turnover of leadingmember > 200 billion dong,total annual turnover ofother member is more than50 billion dong.

3.3 Profit after tax ofbidders in 3consecutive  years(2011, 2012, 2013) (In case of joint venture, profitafter tax of each member must besatisfied requirements)

Have profit (profit > 0)

3.4 The Bidders must conformto requirements ofhealthy finance status:at least 03 followingcriteria for 03consecutive years 2011,2012 and 2013 (in case ofjoint venture, each membermust be satisfied with healthyfinance status).

Factor of short-term debtspayment capability >1.Net value > 0.Quick payment ratio >0.1.

3.5 Tax obligations :Bidders have no taxliabilities up to thetime of bid closing (Incase of joint venture, leadingmember has no tax liabilities)

Bidders have no taxliabilities up to the timeof bid closing and haveconfirmation of taxauthorities

4 Other requirements

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province37

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No. Content Minimum requirements 4.1 Bidders or member of

joint venture implementedconstruction or wereaccepted at least 02construction of handlingsoft soil layer of harborproject by prefabricatedvertical drain withincremental loading toavoid progressivecollapse duringconstruction and harborexploitation .

4.2 Bidders or member ofjoint venture implementedand were accepted atleast 01 bank revetmentwork with high pile capon soft soil layer toavoid progressivecollapse duringconstruction and harborexploitation.

4.3 Supply capacity of sandfor leveling with volume> 700.000 m3.

Bidder must proveits supply capacity (to beowners or sign inprinciple contract withowners of materials) withlegal documents of mine,materials testing resultsand other necessarydocuments.

5 Conclusion Bidder is concluded assatisfactory with allabove requirements.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province38

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Bidding Document is evaluated that they satisfiedwith experience and qualification; it is continuouslyevaluated technique in according to following criteria.

Section 2. Evaluation criteria of technique - Apply evaluation criteria in according to scoring

criterion.

- For technique provisions, minimum required score isnot lower than 75% of total score and requirement scorefor each content.

- Bids which have total scores and score for eachcontent equal to or higher than the minimum required scorelimit shall be evaluated as meeting requirements ontechnical provisions and shall be defined estimationprice.

- Evaluation criteria on technical provision asfollows:

No.

Contents Maximumscorescheme

Minimumrequiredscore

1 Understanding thoroughly scope ofthe Project and Bid Package

12 8

1.1 The contractor describes theproject in detail, has fullunderstanding of all items of thePackage, carries out survey ofconstruction site and givesconnection solutions.

12

1.2 The contractor describes theproject in detail, has fullunderstanding of all items of thePackage, but has no survey ofconstruction site and connection

6

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province39

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No.

Contents Maximumscorescheme

Minimumrequiredscore

solutions.1.3 The contractor does not

understand the Project andcurrent situation in constructionarea.

0

2 Satisfying level of technicalstandard of main material andability of material supply

20 16

2.1 Have detailed list ofconstructional equipment whichshall be used for the workaccording to requirements inSection III and Catalogue ofChapter VIII and requirements onvalidity and technical standard.

2

Not have or have insufficientlist of constructional equipmentwhich shall be used for the workaccording to requirements inSection III and Catalogue ofChapter VIII and requirements onvalidity and technical standard.

0

2.2 Sand for aggrandizement: Must satisfy all criteria asfollow: be the owner of mines orhave supply principle contractwhich satisfies allspecifications of material inBidding document, has volume of >700,000 m3 and testingcertificates or catalogue meetingtechnical specifications inBidding Document

5

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province40

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No.

Contents Maximumscorescheme

Minimumrequiredscore

Not satisfy one of criteria asfollow: Be the owner of mines orhave supply principle contractwhich satisfies allspecifications of material inBidding Document, has volume of >700,000 m3 and testingcertificates or catalogue meetingtechnical specifications inBidding Document.

0

2.3 PVD:Must satisfy all criteria asfollow: Be the owner ofmanufacturing facility or haveprinciple contract of supplymaterial which satisfies allrequirements, specifications andvolume of material in technicaldesign document and have materialtesting certificates or cataloguemeeting requirements in Biddingdocument.

3

Not satisfy one of criteria asfollow: Be the owner ofmanufacturing facility or haveprinciple contract of supplymaterial which satisfies allrequirements, specifications andvolume of material in technicaldesign document and have materialtesting certificates or cataloguemeeting requirements in Biddingdocument.

0

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province41

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No.

Contents Maximumscorescheme

Minimumrequiredscore

2.4 Geotextile fabricGeotextile fabric shall meet allfollowing criteria: Be the ownerof manufacturing facility or haveprinciple contract of supplymaterial which satisfies allrequirements, specifications andvolume of material in technicaldesign document and have materialtesting certificates or cataloguemeeting requirements in Biddingdocument.

2

Not satisfy one of criterions asfollow: Be the owner ofmanufacturing facility or haveprinciple contract of supplymaterial which satisfies allrequirements, specifications andvolume of material in technicaldesign document and have materialtesting certificates or cataloguemeeting requirements in Biddingdocument.

0

2.5 Prestressed- pile with diameterof D500Satisfy all criteria as follow:Be the owner of manufacturingfacility or have principlecontract of supply material whichsatisfies all requirements,specifications and volume ofmaterial in Bidding document.

2

Not satisfy one of criteria as 0

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province42

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No.

Contents Maximumscorescheme

Minimumrequiredscore

follow: Be the owner ofmanufacturing facility or haveprinciple contract of supplymaterial which satisfies allrequirements, specifications andvolume of material in Biddingdocument.

2.6 Grade aggregate 0x4Satisfy all criteria as follow:Be the owner of manufacturingfacility or have principlecontract of supply material whichsatisfies all requirements,specifications and volume ofmaterial in Bidding document.

2

Not satisfy one of criteria asfollow: Be the owner ofmanufacturing facility or haveprinciple contract of supplymaterial which satisfies allrequirements, specifications andvolume of material in Biddingdocument.

0

2.7 Asphaltic concreteSatisfy all criteria as follow:Be the owner of manufacturingfacility or have principlecontract of supply material whichsatisfies all requirements,specifications and volume ofmaterial in Bidding document.

2

Not satisfy one of criteria asfollow: Be the owner of

0

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province43

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No.

Contents Maximumscorescheme

Minimumrequiredscore

manufacturing facility or haveprinciple contract of supplymaterial which satisfies allrequirements, specifications andvolume of material in Biddingdocument.

2.8 Centrifugally cast concreteculvert Satisfy all criteria as follow:Be the owner of manufacturingfacility or have principlecontract of supply material whichsatisfies all requirements,specifications and volume ofmaterial in Bidding document.

1

Not satisfy one of criteria asfollow: Be the owner ofmanufacturing facility or haveprinciple contract of supplymaterial which satisfies allrequirements, specifications andvolume of material in Biddingdocument.

0

2.9 Other materials (cement, sand,stone, steel, commercialconcrete) Satisfy all criteria as follow:Be the owner of manufacturingfacility or have principlecontract of supply material whichsatisfies all requirements,specifications and volume ofmaterial in Bidding document.

1

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province44

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No.

Contents Maximumscorescheme

Minimumrequiredscore

Not satisfy one of criteria asfollow: Be the owner ofmanufacturing facility or haveprinciple contract of supplymaterial which satisfies allrequirements, specifications andvolume of material in Biddingdocument.

0

3 Constructional equipment used forconstruction of the Package

20 16

3.1 List of constructional equipmentHave detailed list ofconstructional equipment whichshall be used for the work withrequired quantity according toSection V and Catalogue ofChapter VIII.

5

Not have or have undetailed andinsufficient list ofconstructional equipment whichshall be used for the work withrequired quantity according toSection V and Catalogue ofChapter VIII.

0

3.2 Equipment for prefabricatedvertical drainSatisfy all criteria as follow:Have principle contract or haveat least 04 dedicated PVDmachines which meet technicalrequirements of Bidding Documentand can be mobilized steadily ineach time according to

5

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province45

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No.

Contents Maximumscorescheme

Minimumrequiredscore

requirement of the Package (basedon reasonable recommendedprogress of the contractor).Not satisfy one of criteria asfollow: Have principle contractor have at least 04 dedicated PVDmachines which meet technicalrequirements of Bidding Documentand with ability of mobilizationin each time according torequired progress of the Package(based on reasonable recommendedprogress of the contractor).

0

3.3 Transport and sand pump equipmentSatisfy all criteria as follow:Have principle contract or haveat least 10 sand transportingbarges which meet technicalrequirements of Bidding Documentand can be mobilized steadily ineach time according to requiredprogress of the Package (based onreasonable recommended progressof the contractor).

5

Not satisfy all criteria asfollow: Have principle contractor have at least 10 sandtransporting barges which meettechnical requirements of BiddingDocument and can be mobilizedsteadily in each time accordingto required progress of thePackage (based on reasonable

0

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province46

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No.

Contents Maximumscorescheme

Minimumrequiredscore

recommended progress of thecontractor).

3.4 Observation equipment for softground processing Satisfy all criteria as follow:Be the owner or have principlecontract of hiring testing Unitfor testing specifications ofmaterial and Observation Unit forsoft ground processing accordingto requirement in BiddingDocument. Testing and observationequipment must have Ownershipdocument and verificationdocument which remain shelf lifeand can be mobilized steadily intime of bid opening.

5

Not satisfy one of criteria asfollow: Be the owner or haveprinciple contract of hiringtesting Unit for testingspecifications of material andObservation Unit for soft groundprocessing according torequirement in Bidding Document.Testing and observation equipmentmust have Ownership document andverification document whichremain shelf life and can bemobilized steadily in time of bidopening.

0

4 Construction methods for mainwork items

15 12

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province47

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No.

Contents Maximumscorescheme

Minimumrequiredscore

4.1 Have detailed note and drawing oftotal construction site  whichshow sufficient contents asfollow: (1) Plan for temporaryworks, construction equipment,yards for materials and wastes;(2) Arrangement of entrances,barriers, signs; (3) Solutionsfor supplying electricity, water,drainage, traffic, communicationduring construction.

1

Be unreasonable 04.2 Have reasonable survey solution

to position yard boundary, thearea to be considered andbenchmarks during constructing.

1

Be unreasonable 04.3 Have note and drawing which show

general construction method andtechnique and details for itemsof excavation and excavated soilremoving.

2

Be unreasonable 04.4 Have note and drawing which show

reasonable general constructionmethod and technique and detailsfor item of plan aggrandizement.

2

Be unreasonable 04.5 Have note and drawing which show

reasonable general constructionmethod and technique and detailsfor item of soft groundprocessing (making PVD, spreading

3

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province48

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No.

Contents Maximumscorescheme

Minimumrequiredscore

out geotextile fabric, installinghorizontal PVD, survey outline,prior loading).Be unreasonable 0

4.6 Have note and drawing which showreasonable general constructionmethod and technique and detailsfor item of road and yard in theport (ballast aggregate, cement-stabilized ballast, asphalticconcrete, water drainage).

2

Be unreasonable 04.7 Have note and drawing which show

reasonable general constructionmethod and technique and detailsfor item of revetment.

4

Be unreasonable 05 Method and procedure of

construction management 5 3

5.1 Have reasonable procedure ofmanaging material quality(procedures of inspectingmaterial quality, receiving,storage and maintenance),Procedure of quality managementfor each main construction item(excavation of organicsubstances, aggrandizement,making PVD, driving pipe,spreading out geotextile fabric,spraying asphalt concrete,embankment) and method ofmaterial and work preservation

3

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province49

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No.

Contents Maximumscorescheme

Minimumrequiredscore

during suspending construction orrain storming. Be unreasonable 0

5.2 Have reasonable procedure ofmanaging document, materials andas-built drawings; acceptance andfinal payment.

1

Be unreasonable 05.3 Have reasonable procedure of

managing labor safety, firefighting inside and outside ofthe site, environmentalsanitation, traffic safety andsecurity and order.

1

Be unreasonable 06 Organization and personnel

assignment for execution of thePackage

10 7

6.1 Have construction organizationchart, management organizationchart, supervision of quality andlabor safety. The charts must besufficient, reasonable and showrelation between divisions of theContractor and relation to theEmployer and Engineer in site.

2

Be insufficient and unreasonable. 06.2 Have list of personnel for

execution of the Package. Inwhich, there are at least 15staff and engineers in major ofConstruction, Transport, Port,Geology with practice

5

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province50

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No.

Contents Maximumscorescheme

Minimumrequiredscore

certificates in the field of softground processing; ConstructionMaterial; ConstructionEconomics, Construction Engineerwith value certificate;,Measurement and Constructionalmachine Engineer, ElectricalEngineer, Water DrainageEngineer, Mechanical Engineer whoare assigned to be technical andconstructional staff for eachwork item; and have sufficientworkers according to requirementof Bidding Document.Have an insufficient arrangement 0

6.3 Have arrangement of staff incharge of labor safety, firefighting and environmentalsanitation : there are at least03 qualified staff who weretrained in labor safety accordingto current regulation and 01 firefighting Engineer, 01Environmental Engineer in orderto satisfy criteria of the BidingDocument.

3

Have an insufficient arrangement 07 Construction progress 7 57.1 Have detailed and reasonable

progress chart of construction,Contract Performance Period shallnot exceed 24.0 months since dateof Notice to proceed from the

3

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province51

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No.

Contents Maximumscorescheme

Minimumrequiredscore

Employer.The construction progress isundetailed and unreasonable.

0

7.2 Have chart of mobilizingworkforce, material and equipmentwhich is suitable forconstruction progress of thework.

2

The chart is unsuitable. 07.3 Have construction method to

ensure progress, keepconstruction when power failureoccurs and ensure continuousoperation of equipment in site.

2

Have no method to ensureprogress, keep construction whenpower failure occurs and ensurecontinuous operation of equipmentin site.

0

8 Work guarantee 3 2

Have commitment of more than 12month- guarantee period for thework.

3

Have commitment of 12 month-guarantee period for the work.

2

Have no commitment or havecommitment of less than 12 month-guarantee period for the work.

0

9 Other requirements 8 6Have constructed works or workitems for Port constructionProjects in area of Cai Mep Thi

3

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province52

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No.

Contents Maximumscorescheme

Minimumrequiredscore

Vai.Have constructed > 02 works ofsoft ground processing using PVDwith volume of more than1.000.000 m each work for Portconstruction Projects.

3

The Contractor must own plan usedas spoil area or have principlecontract of hiring plan used asspoil area.

2

Total score 100 75

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province53

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Item 3. Contents of evaluated price determination

Table of evaluated price determination:

No.

Items Base

1 Bid price Item 28, Chapter I

2 Correction Item 29, Chapter I

3 Error remedy Item 30, Chapter I

4 Bid price after correctionand remedy

Total value:

(1) + (2) + (3)

5 Corrected bid price less discount (if any

Value in (4) – discount(if an y)

6 Evaluated price Total value in (5)

(End of Chapter III)

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province54

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Chapter IV

TECHNICAL PROPOSAL FORM Technical proposal of Bidders comprises bid

application for technical proposal, organizationalstructure and experience of bidders, comments (if any) onterms of reference (TOR), solution and method proposed byBidders, list of consultants, their CV, their workingexperience and agenda.

Form 1: Bid Application (Technical proposal) Form 2: Power of Attorney Form 3: Joint-Venture Agreement Form 4: List of main construction machine and equipment Form 5: List of site testing instruments Form 6: Scope of work of sub-contractor Form 7A: List of key personnel Form 7B: Summary of qualification and experience of key personnelForm 8: On-going contracts of the Bidder Form 9: Similar contracts implemented by the BidderForm 10: Summary on the Bidder’s activitiesForm 11: Financial capacity of the Bidder Form 12. Bid Security

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province55

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Form 1

BID APPLICATION

(Technical proposal)

_____, date ____ month ____ year ______

Respecfully address to:______________________ [Name of Bid Solicitor]

(Hereinafter referred to asBid Solicitor)

After receiving and reviewing the Bidding Documentand the amended Bidding Document No. ______[insert number ofthe additional documents (if any)], we, ______[insert name of the Bidder],undertake to perform the package _____ [insert name of thepackage] in accordance with the provisions of the BiddingDocument. Our bids includes a technical proposal and afinancial proposal which are sealed independently.

Should our bid be accepted, we will have the measuresto ensure the implementation of the contract in accordancewith the provisions of Item 38, Chapter I and Article 3 ofGeneral conditions of Contract in the BIDDING DOCUMENT.

This technical proposal takes effect within____day(s)from date____month ____year____[insert the bid closing time].

Legal representative of the Bidders (1)

[Insert name, position, signature and seal (2)]

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province56

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

(1) In case the legal representative of the Bidders authorizes one ofhis subordinates to sign the bidding application, a Power of Attorney -Form 2 of this Chapter must be enclosed; in case in the Charter of thecompany of other concerned documents stipulate the appointment of asubordinate to sign the bidding application, a scan copy of thesedocuments must be enclosed (then Power of Attorney - Form 2 of thisChapter is not needed). In case of awarding, the Bidder shall submit thenotarized copy of this document to the Bid Solicitor prior to the signingdate of the Contract. In case of false information discovered, the Bidderis deemed to violate Item c, Clause IV, Article 89 of Bidding Law and isincurred a penalty in accordance with Item 42, Chapter I of this BiddingDocument.

(2) In case foreign Bidders have no seal, they shall submitcertifications of competence authorities which specify that the signaturesin Bid Application and other documents in Bids are of legalrepresentative of Bidders.

Form 2

POWER OF ATTORNEY (1)

Today, Date ____ Month ____ Year ____, in____

I ____ [Name, ID No. Or Passport No., Position of the legalrepresentative of the Bidder], the legal attorney of [name of theBidder] address ____ [address of the Bidder] do hereby appoint ____[Name, ID No. Or Passport No., Position of Name, ID No. Or Passport No.,Position of] to implement following tasks during bidding thepackage ____ [Name of the Package] under the project ____[Name of the Project] organized by ____ [Name of Bid Solicitor]:

[- Signing the Bid Application;

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province57

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

- Signing document, deeds to transact with Bid Solicitor during thepackage bidding, including documents clarifying Bidding Document anddocuments accounting and clarifying Bidding Document;- Participating in the negotiation and finalization of the Contract;- Signing the written complaint if the Bidder complains;- Signing the Contract with the Bid Solicitor if selected.] (2)

The Attorney mentioned above only implements taskswithin the content of authorization as a legalrepresentative of ____ [Name of the Bidder]. ____ [Name of theBidder] bears responsibilities for jobs done by ____ [name ofthe Attorney] within the content of authorization.

Power of Attorney will be in full force and effectfrom date ____ to date ____(3). This Power of Attorney ismade into ____ copies of equally legal value, theAuthorizer holds ____ copies, and the Attorney holds ____copies.

The Attorney[Name, position, signature and

stamp if any]

Authorizer[Name of representative of the Bidder,

position, signature and stamp]

Note:(1) In the authorization, The original Power of Attorney and Bidding

Document application must be sent to the Bid Solicitor in accordance withregulations stipulated in Item 10, Chapter I. The the legal representative ofthe Bidder authorizes the lower rank, Directors of branches, Heads ofRepresentative Office of the Bidder to implement one of above tasks. Thestamp (if any) used in authorization might be the stamp of the Bidder or the Unitwhich the Attorney is appointed. The Attorney shall not transfer to the thirdperson.

(2) The content of authorization consists of one or some tasks mentionedabove.

(3) The effective date and expiry date of Power of Attorney are suitable forprocurement.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province58

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Form 3JOINT VENTURE AGREEMENT1

, Date Month Year

Package: _________________[Name of the Package]Under the project: ________________[Name of the Project]

Pursuant to2 __________[Bidding Law No. 43/2013/QH13 ofthe XIIIth National Assembly on November 26, 2013];

Pursuant to_____________[Decree No. 63/2014/NĐ-CP of theGoverment on June 26, 2014 on guiding the implementation of Bidding Lawand selecting Bidders in accordance with Law on Construction];

Pursuant to Bidding Document for bidpackage_____________[Name of the Package] on ___ Month ____Year ____[Date as specified in Bidding Document];

We, representatives of Parties signing the Joint-Venture Agreement, are:

Name of joint venture members [Name of each joint venture member]Representatice: Position: Address: Telephone No.: Fax: E-mail: Account: Tax code: Power of Attorney No. date ___ month ____ year ___ (if authorized).

Parties (herein after referred to as members) agreeto sign the Joint-Venture Agreement with followingcontents:

Article 1. General principles

1Basing on scale and characters of the bid package, contents of the Contractunder this Form may be amended, supplemented accordingly.2Legal documents are updated in accordance with applicable provisions.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province59

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

1. Members voluntarily agree to establish the jointventure to participate in the packagepackage_____________[Name of the Package]under the project________________[Name of the Project].

2. Members approve of the name of association for alltransactions related to this package: _____________[Name ofassociation as approved].

3. Members commit not to participate in thisassociation independently or cooperate with other membersto participate in this package. If the package is won, nomember is allowed to reject the liabilities as stipulatedin the Contract except for there is an approval of membersin the associationin writing. If any member of theassociation rejects its liabilities completely asapproved, that member is punished as follows:

- Compensating for parties in the association- Compensating for the Bid Solicitor referring to regulations mentioned

in the Contract - Other methods of settlement_____________[Giving the detail of

other methods of settlement].

Article 2. Allocation of responsibilities Members agree to allocate responsibilities among all

members to implement the package ___________[Name of thepackage] under the project ___________[name of the project] asfollows:

1. Leader Parties agree to appoint _____________[Name of one party]

to be the Leader, representing the joint venture infolowing tasks (1):

[-Signing Bidding Document application form- Signing document, deeds to transact with Bid Solicitor during thepackage bidding, including documents clarifying Bidding Document anddocuments accounting and clarifying Bids;- Participating in the negotiation and finalization of the Contract;- Signing the written complaint if the Bidder complains;

1 Content of authorization consists of one or many tasks mentioned above.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province60

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

- Other tasks except for the contract signing______[Writing contentsof other tasks (if any)].

2. Members in the joint venture______ [Writing work andrespective value, general responsibilities, responsibilities of each memberincluding the Leader and corresponding percentage if any].

Article 3. Effect of Joint-Venture Agreement1. Joint-Venture Agreement will be in effect since

the date of signing. 2. Joint-Venture Agreement terminates its effect in

following cases:- Parties complete their responsibilities and

liquidate the Contract;- Parties agree to terminate the Contract;- Joint venture members who do not award the bid

package - The package _____[Name of the package] under the project

______[name of the project] is cancelled referring to the Noticeof Bid Solicitor.

Joint-Venture Agreement is made into __________ copies,each Party holds ___________ copies. All copies are of the samelegal value.

LEGAL REPRESENTATIVE OF THE LEADER[Name, position, signature and stamp]

LEGAL REPRESENTATIVE OF JOINT VENTURE MEMBERS[Name of each member, position, signature and stamp]

Form 4LIST OF MAIN CONSTRUCTION MACHINE AND EQUIPMENT (1)

Type Q’ty Capac Featu Count Year Owner Quali

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province61

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

ofmachines

ity res ry oforigi

n

ofmanufactur

e

orleasee (2)

ty

Note:

(1) List of construction machines and equipment for this package.

(2) In case of leasing, it is required to provide writtenconfirmation (commitment of parties, copy of agreement,etc). In case of sucessful bidder, the bidder shallprovide a copy of lease agreement. In case of owner, it isunnecessary to provide such evidence.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province62

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Form 5

LIST OF SITE TESTING INSTRUMENTS

Type Q’ty Specifications

Countryof

manufacture

Owner orlessee

Quality

Note: Main construction machines and testing devices are supported withrelevant documents in Item VII, Chapter IX. In case of hiringlaboratory, it is required to provide principle contractand company profile of such laboratory. If not, Bids of thebidders shall not be reviewed.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province63

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Form 6

SCOPE OF WORK OF SUBCONTRACTOR(1)

No.

Subcontractor

(if any)(2)

Scope ofwork

Q’ty Estimated value

Contract oragreementsigned withthe main

contractor (ifany)

1

2

3

Note:

(1) It is not required to fill this form in case of nosubcontractor.

(2) In case of subcontracting, bidder shall fill name ofsubcontractor, if estimated. It is required to list scopeof works and estimated value performed by subcontractor.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province64

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Form 7A

LIST OF KEY PERSONNEL

No. Full name Title (1)

1

2

3

Note: Attached with summary on qualification and working experience of each key employee in Form 7B.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province65

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Form 7B

LIST OF QUALIFICATION AND EXPERIENCE OF KEY PERSONNEL

Title(2): _____________

1- Full name: ______________ Age: _____________________2- Qualification: __________ School: ________________________________________Major: 3- Address: ________________Tel: ______________________The following table shows professional qualifications of key personnel in chrnological order: From To Company/

similarproject

Similartitle

Experience

Note: Attached with certified copy of degrees or certificate.

Date ____ month ___ year_____

Applicant[signed]

(1), (2) Specify estimated title for this package. i.e: Director

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province66

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Form 8ON-GOING CONTRACTS OF THE BIDDER

________, date ____ month ____ year ____

Name of the Bidder: ________________________ (Full name of the Bidder)

No.

Nameofthecontract

Nameofthe

project

Nameofthe

Employer

Contract value(or theassigne

dvalue)

Valueof

incompletevalue

Date ofeffect

Date offinalizat

ion

123...

The Bidder has to attach copies of related documentsof the Contract (the confirmation of the Employer aboutrelated contents in the above table).

Legal representative of the Bidder[Full name, position, sign and seal ]

Note:In case of joint venture, each joint venture member has to enumerate

this form.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province67

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Form 9SIMILAR CONTRACTS IMPLEMENTED BY THE BIDDER (1)

________, date ____ month ____ year ____

Name of the Bidder: ________________________ [Full nameof the Bidder]Each Contract needs to have following information:

Name and number of the Contract

[name of the Contract, code No.]

Date of signing the [date, month, year]Date of finalization [date, month, year]

Price of the Contract

[total value of the Contract inamount and money unit which has

been approved for the Contractsigning]

Equivalent in _____ VND or USD [The amount of moneyexchanging into VND or USD is written out]

For member in the association or Sub-Bidder, the value of the Contract, which the Bidder was in charged of, should be written down.

[Filling thepercentage of theContract value inthe total amountof the Contract]

[Filling theamount andmoney unit

which has beenapproved for theContract signing]

Equivalent in _____ VND or USD [The amount of moneyexchanging into VND or USD is written out]

Name of the project: [Filling name of the Project which has the enumerated Contract]

Name of the Employer: [Filling the name of the Bidder in the enumerated Contract]Address:Telephone/fax:E-mail:

[Filling current address of the Employer][Filling telephone number, fax number including national code, regional code, email address]

Description of similar features referring to regulation item 11. Types of goods [Filling suitable information]2. Value [Filing amount of money exchanged in VND USD]3. Scale [Filling the scale referring to the Contract ]4. Other [Filling other characteristics (if necessary)]

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province68

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

The Bidder has to attach the copies of relateddocuments.

Note:(1) The Bidder enumerates this form for similar on-going contracts.In case of association, every member in the list is required to list as in this

form.(2) The Bidder only enumerates contents similar to the requirements of the

Package.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province69

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Form 10

SUMMARY ON THE BIDDER’S ACTIVITIES

1. Name of the Bidder: ____________________________

Address: _________________________________2. Experience in construction activities

Total years of experience in construction activities for this bid package:

3. Total number of available employees: a) In the field of general operation:

_____________________

b) In the field of construction activities____________________

In which, Specializedstaff:__________________

____, date ____ month ____ year ____Representative of the Bidder

[Name, position, signature and stamp]

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province70

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Form 11

FINANCIAL CAPACITY OF THE BIDDER

_____, date ____ month ____ year ____

Name of bidder: _________________________________ [full name of bidder]

A. Summary of financial data in recent ___________ fiscal years [Specify number of years as specified in Item 1.3 of Chapter III]

Unit: _______ [Currency]

No.

Year___ Year ___ Year ___1 Total assets2 Total liabilities3 Short-term assets4 Short-term

liabilities5 Revenue6 Pretax profit7 Post-tax profit8 Others (If

required)B. Attached documents are used to test data listed by theBidder, the Bidder has to submit Financial Statements andone of these certified copies:1. Tax accounting inspection in recent _____ financialyears [Specify number of years as specified in Item 1.3 of Chapter III] 2. The declaration of annual tax balancing (VAT andbusiness income tax) with the confirmation of declarationfinalization by Tax agent in recent _____ financial years[Specify number of years as specified in Item 1.3 of Chapter III]3. Confirmation of declaration by Tax agent referring toduty of tax payment in recent ____ financial years [Specifynumber of years as specified in Item 1.3 of Chapter III]4. Audit report

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province71

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Representative of the Bidder[Name, position, signature and stamp]

Note:In case of a joint venture, each joint venture member has to enumerate

this form.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province72

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Form 12

BID SECURITY (1)

________, date ____ month ____ year_____

To: ___________________ (Name of the Bid Solicitor)(Hereafter referred to as Employer)

Pursuant to the event _____ [Name of the attending Bidder],hereafter referred to as “the Bidder”, will participate inbidding the package ______[Name of the package] under theproject________[Name of the project].

We [Name of the bank, financial organization] registered officeat [Address of the bank, financial organization] commit with Employerto guarantee the Bidder to participate in this packagewith the amount of [In numbers, words and used currency].

We commit to sending the amount of money mentionedabove to the Employer once the Employer informs in writingthat the Bidder violates the regulations of bidding asstipulated in the Bidding Document.(2)

This guarantee will be in full force and effect in_________(3) days since_______(4). Any requirements of theEmployer related to this Guarantee _________ [Name of bank,financial organization] must be received before the datementioned above.

Legal representative of the Bank[Name, position, signature and seal]

Note:(1) Only applied in case bidding security method is security letter from bank

or financial organization(2) In case joint venture bidder and other members of association

undertake separately to bid or one member of the association will bethe representative to undertake bidding security method, this regulationwill be replaced as follows: “We commit to pay total amount mentionedabove to the Employer once the Employer informs in writing that theBidder or any member of bidding association violates the regulations ofbidding as stipulated in the Bidding Document.

(3) In accordance with Item 17.1 of BDS.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province73

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

(4) In accordance with Item 21.1 of BDS.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province74

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Chapter V

FORMS OF FINANCIAL PROPOSAL FORMS

Financial Proposal is made subject to technical proposaland in line with requirements and provisions of biddingdocument comprising bid application for financialproposal, summary of costs, remuneration of specialistsand other expenses.

Form 13. Bid application (Financial proposal)Form 14. General Statement of Bid PriceForm 15. Detailed Statement of Bid PriceForm 16A. Analysis of Bid Price Unit – For detailed construction price unitForm 16B. Analysis of Bid Price Unit – For overall construction price unitForm 17. Calculation of material price in the Bid Price Unit

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province75

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Form 13

BID APPLICATION

(Financial Proposal)

_____, date ____ month ____ year ______

Respecfully address to:______________________ [Name of Bid Solicitor]

(Hereinafter referred to asBid Solicitor)

After receiving and reviewing the Bidding Document and theamended Bidding Document No. ______[insert number of theadditional documents (if any)] , we, ______[insert name of the Bidder],undertake to perform the package _____ [insert name of thepackage] in accordance with the provisions of the BiddingDocument. Out of tehnical proposal, the financialprosposal is attached with amount of _____ [Specifying value infigures, words and currency] which is valid within ____ days[Specifying number of days based on valid time of technical proposal], from___ hour, date ___ month ___ year _____ [Closing date ofbidding].

Legal representative of theBidders (1)

[Insert name, position, signature and seal (2)]

Note:

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province76

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

(1) In case the legal representative of the Bidders authorizes one of hissubordinates to sign the bidding application, a Power of Attorney - Form2 of this Chapter must be enclosed; in case in the Charter of thecompany of other concerned documents stipulate the appointment of asubordinate to sign the bidding application, a scan copy of thesedocuments must be enclosed (then Power of Attorney - Form 2 of thisChapter is not needed). In case of awarding, the Bidder shall submit thenotarized copy of this document to the Bid Solicitor prior to the signingdate of the Contract. In case of false information discovered, the Bidderis deemed to violate Item c, Cluase IV, Article 89 of Bidding Law and isincurred a penalty in accordance with Item 42, Chapter I of this BiddingDocument.

(2) In case foreign Bidders have no seal, they shall submitcertifications of competence authorities which specify that the signaturesin Bid Application and other documents in Bids are of legalrepresentative of Bidders.

Form 14GENERAL STATEMENT OF BID PRICE

No. Items Amount1 1. Reclamation at yard area (Detailed pricelist 1);2 2. Reclamation at Revetment area (Detailed pricelist 2);3 3. Soil Improvement for yard area (Detailed pricelist 3);4 4. at yard area revetment area (Detailed pricelist 4);5 5. Internal road and yard (Detailed pricelist 5);6 6. Surface water drainage system (Detailed pricelist 6);7 7. Revetment along Thi Vai River (Detailed pricelist 7);… …

Sub-total

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province77

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Tax (Applicable in case of pre-tax unit price)

TOTAL

Total: _______________ [In figures]In

words:_____________________________________________

Legal representative of theBidders

[Insert name, position, signature and seal]

Note: General statement of bid price is made based ondetailed statements.

Form 15DETAILED STATEMENT OF BID PRICE (1)

No. Workitems

Unit Q’ty Unitprice

Amount

(1) (2) (3) (4) (5) (6)

…Total

Legal representative ofthe Bidders

[Insert name, position, signature and seal]

Note:(1) Detailed price list may be made for each main

work items, for example water drainage system, etc. Column (2): Specifying work items as in Bill of

Quantity Column (4): Specifying work items as in Bill of

Quantity

In case of any difference in bill of quantity anddesign, the bidder shall notify to the employer and prepare

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province78

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

a table for such difference for approval of the employer,not included into this Price list.

Form 16A

ANALYSIS OF BID PRICE UNIT (1)

For detailed construction price unitWork ítems:_______________

Unit : ______ [Currency]MarkNo.

Code Wastage Unit Q’tyUnitprice

Amount

(1) (2) (3) (4) (5) (6) (7)DG.1 Materials

Vl.1Vl.2...

Total VLLabor (Based on average grade)

man-day

NC

Constructionmachine

M.1Shift

M.2Shift

...Subtotal M

TOTAL 1

Note: (1) Subject to nature of work ítems, whether bidder analyzes unitprice or not. If not, this form shall not be used. The price unit comprises otherdirect cost, general cost and pre-tax income in case of full collection.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province79

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Column (6): Price unit offered by the bidder notposted by the State.

Form 16B

ANALYSIS OF BID PRICE UNIT(1)

For overall construction price unit Work items:_______________

Unit : ______ [Currency]

Code Items Unit Q’ty

Cost

TotalMaterial

LaborMachin

e

(1) (2) (3) (4) (5) (6) (7) (8)

DG.1 1

DG.2

DG.3

...

Total VL NC M

Note:

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province80

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

(1) Subject to nature of work items, whether bidder analyzes priceunit or not. If not, this form shall not be used. The price unit comprises otherdirect cost, general cost and pre-tax income in case of full collection. Column (5), (6) and (7): Price unit offered by thebidder not posted by the State.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province81

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Form 17CALCULATION OF MATERIAL PRICE IN THE BID PRICE UNIT (1)

No.

Type Unit Priceunit

Cost tothe site

Included inbid price (2)

1

2

Note:(1) Subject to nature of work items, whether bidder analyzes price unit or not. If not, this form is non-applicable.(2): Price unit offered by the bidder not posted by theState.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province82

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Part IIREQUIREMENTS ON CONSTRUCTION

Chapter VIINTRODUCTION TO PROJECT AND BID PACKAGE

1. Project introduction Project: Thi Vai Port Construction Investment Project -Phase I Package PK2: Construction of Onshore works - Phase I:Reclamation, Soil Improvement,Internal road and yard,Surface water drainage system and Revetment along ThiVai River.Site location: Phu My Town, Tan Bar District, Ba Ria-Vung Tau Province Grade of Works: Transport Works and TechnicalInfrastructure - grade III.The Client: Thi Vai International Port Limited Company.Investment capital sources: Self-funded and Commercial

LoanGeneral information about the Project

Thi Vai Port Construction Investment Project owned by ThiVai International Port Co., Ltd on the left bank of ThiVai River with 620ml berth. Thi Vai Port can accommodateto general cargo ship up to 80,000DWT and container vesselof 80,000DWT with estimated cargo throughput handling of4,286 million tons/year in phase I (2015) and 7,796million tons/year in phase II (2020).Grade of works: Reclamation is for works of grade IV, SoilImprovement, Internal road and yard, surface waterdrainage system are grade III, revetment item is gradeIII.

The Client: Thi Vai International Port Limited Company Head office: Phu My Town, Tan Bar District, Ba Ria-Vung Tau province.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province83

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Design Consultant: Consultancy Company Limited ofUniversity of Civil Engineering

Head office:No.55 Giai Phong street, Hai Ba Trưng District, Ha Noi city; Tel: (84-4) 3869 6570 Fax: (84-4) 3869 9720 Website: http://ccu.vn

2. Package IntroductionPackage PK2: Construction of Onshore works - Phase 1 inaccordance with approved Detailed Design document ,including: Reclamation for the remaining yard of the phase 1

(except reclamation of package PK4A-1) and Reclamationfor the revetment area;

Soil improvement for the remaining yard (except forsoft Soil Improvement of package PK4A-1) of phase Iand road foundation behind the revetment;

Road, yard on the left side of the main gate (exceptfor road, yard of package PK4A-1) and the access roadfrom upstream access bridge to the main gate arterialroad;

The rest of surface water drainage system (except forsurface water drainage system of package PK4A-1) ofphase I;

Revetment along Thi Vai River.Basis for design

Construction Law No.16/2003-QH11 dated 26/11/2003passed by the National Assembly of the SocialistRepublic of Vietnam;

Decree No.15/2012/ND-CP dated 06/02/2013 of theGovernment about Construction Quality Management;

Circular No.10/2013/TT-BXD dated 25.07.2013 of theMinistry of Construction about detailing some contentsof the Construction Quality Management;

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province84

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Circular No.27/2009/ TT-BXD dated 31/7/2009 of theMinistry of Construction about guidelines on somecontents of Construction Quality Management;

Decree No.12/2009/ND-CP dated 10/02/2009 of theGovernment about Management of Construction InvestmentProjects;

Circular No.03/2009/TT-BXD dated 26/03/2009 of theMinistry of Construction about detailing some contentsof Decree No. 12/2009/ND-CP of the Government;

Decree No.83/2009/ND-CP dated 15/10/2009of theGovernment about amending and supplementing a numberof articles of Decree No. 12/2009/ND-CP dated12/02/2009 of the Government;

Decree No. 112/2009/ND-CP dated 14/12/2009 of theGovernment about Management of the ConstructionInvestment Cost;

Circular No.04/2010/TT-BXD dated 26/5/2010 of theMinistry of Construction about guiding theestablishment and management of ConstructionInvestment Cost;

Decree No. 71/2006 / ND-CP dated 25/07/2006 of theGovernment about Management of Port and MaritimeChannel;

Circular No. 10/2007 / TT-BGTVT 06/08/2007 of theMinistry of Transport, about guiding theimplementation of Decree No. 71/2006 / ND-CP of theGovernment;

Technical Regulations on wharf operation, which isattached to Decision No.109/QD-CHHVN dated 10/03/2005of Vietnam Maritime Administration;

Decree No.186/2004/ND-CP dated 05/11/2004of theGovernment about Regulations of Management andProtection of roadway infrastructure;

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province85

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Vietnam Port system development planning up to 2020and orientation to 2030, approved by the PrimeMinister in Decision No. 2190/QD-TTg dated 24/12/2009;

Detailed planning of South Eastern Port group (Group5) in 2020, strategy to 2030 approved by the Ministryof Transport in Decision No. 1745 / QD-BGTVT dated03/8/2011;

Document No. 300/QD-CHHVN dated 09/04/2011 of theVietnam Maritime Administration about approving theexploitation of Vung Tau - Thi Vai maritime channel;

Investment license No 491.022000342 dated 3/7/2014; Decision No. 52/QD.UBT dated 13/01/1999 of Ba Ria-VungTau People Committee on issuing certificates of410,000 m2 of land and water in use in Phu My town,Tan Bar district, Ba Ria - Vung Tau province for ThiVai Vung Tau International Port;

Certificate of land use right No.M149879 issued by BaRia-Vung Tau People Committee dated 13/01/1999.

Document No.1496/CV-UBT dated 08/07/1996 of Ba Ria-Vung Tau People Committee about location agreements ofGeneral port investment projects of joint venturebetween Vietnam - Vung Tau Ship Steel Corporation -Kyoei Steel Company (Japan);

Document No.3292/KHDT dated 28/10/1996 of the Ministryof Transport about location agreement of the Portfeasibility Project Agreement of joint venture betweenVietnam Steel Corporation - Kyoei Steel Company(Japan)-Vung Tau Ship;

Document No.1072/XDCB dated31/10/1996 of VietnamMaritime Administration about the port locationagreement of the joint venture between Vietnam SteelCorporation - Kyoei Steel Company (Japan) - Vung TauShip ;

Document No.3993/KHDT dated 27/12/1997 of the Ministryof Transport about adjusting the berthing line andsupplementing the barge line for Thi Vai port;

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province86

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Decision No.354/QD.MTg dated 29/03/1997 of theMinistry of Science, Technology and Environment aboutenvironmental impact assessment of project "Thi Vaiport construction project "of the joint venture KYOEI-VSC-VTS in Ba Ria - Vung Tau;

Based on the principle of ContractNo.20/2012/HDTV(HDT)-TVP-CS3 CS3 dated 27/12/2012 andContract No.05/2013/HDTVTVP-CS3 dated 22/08/2013between the Thi Vai Port International Limited Companyand Consultancy Company Limited of University ofCivil Engineering about detail design of buildingconstruction on land-Phase I of Thi Vai PortConstruction Investment Project;

Document No.177/VPCP-KTN dated 10/01/2010 of theGovernment Office about implementation of Thi VaiInternational Port project;

Document No.5623/UBND-VP dated 19/08/2010 of Ba Ria-Vung Tau People Committee about implementation of ThiVai International Port project;

Document No.6546/BGTVT-KHDT dated 21/09/2010 of theMinistry of Transport about implementation of Thi VaiInternational Port project, Ba Ria - Vung Tauprovince;

Document No.6781/UBND-VP dated 07/10/2010 of Ba Ria-Vung Tau People Committee about implementation of ThiVai International Port project;

Document No.8774/BKH-DTNN dated 08/11/2010 of theMinistry of Planing and Investment aboutimplementation of Thi Vai International Port project;

Document No.660/CHHVN-KHTC dated 30/03/2011 of VietnamMaritime Administration about location agreement andscope of Thi Vai International Port construction.

Documents for design Topographical survey map updated land and water areasin the construction site done by Construction

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province87

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Consultancy Joint Stock Company for Maritime Building(CMB) in 12/2011; Map scale 1/1000; ChartDatum;

Geological investigation document includes 02 holesHK1/02 and HK2/02 implemented by REARTEC in 2002; 12boreholes from HK1/11 to HK12/11 implemented by CMB inApril, 2011; 17 boreholes from TK3 to TK19 done by CMBin November, 2011 to serve for design phase of shopdrawings for embankment, barge berth, storage,office, road, yard and other on-shore structures;

Documents of basic design stage by CMB in July, 2011.NATURAL CONDITIONS OF CONSTRUCTION SITESite LocationThi Vai port is located on the left bank of Thi VaiRiver (Northern bank) in Phu My Town, Tan Bar District,Ba Ria – Vung Tau Province.

Figure 0-1. Site locationTopographic conditionsThe land lotThe land lot to build Thi Vai Port covers totalapproximate area of 41 ha (on provided boundaries). Theland lot on which the port is going to be be built isfeatured by:

Bordering SITV Port to the North; Being adjacent to Ba Ria Serece Port to the South;

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province88

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Bordering Thi Vai River to the West;Being contiguous to inter-port roads.ground levelIts land form is characterized by ground levelranging from +3.5m to +4.0m (Chart Datum Level - CDL).Southern land lot was already leveled with sand up toelevation of +5.3 to +5.4m.

Water ZoneGround levelThe port is situated on the concave bank ofThi Vai River. Form of water zone at the coastline to themargin of navigational channel is sloping from the bankoutwards, in this scope, ground level (as per Chart Datum)ranges as below:

At the existing coastline, the ground level variesfrom +1.0 to +2.4m;

For line which is 50m far from the current coastline:the ground level varies from ±0.0 to -1.0m;

For line which is 100m far from the current coastline:the ground level varies from -4.0 to -7.0m;For linewhich is 150m far from the current coastline: theground level varies from -5.0 to -7.0m on theupstream and varies from -10.0 to -11.0m on thedownstream. From this line to the navigational channelmargin, the ground level varies from -11.0 to -12.0mon the downstream and from -5.0 to -9.0m on theupstream.

Geological conditionsThe geological investigation report numberred 16/2011/KSĐCby CMB, Ho Chi Minh City Branch, conducted on 11/2011 hassummarized physico-mechanical properties of soil layers asper investigation results produced in 4/2011 and 11/2011,in favo of Design stage of shop drawings for Thi Vai Port– Phase I. Stratum structure of the ground from the upperto the lower includes 9 soil layers:

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province89

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

On the basis of geological investigatino results at sitelocation, it is found that stratum under investigationincludes soil layers with following characteristics:

Layer 1a is backfilling soil layer, small thickness,limited distribution.

Layer 1 is levelled soil layer, small thickness, withmedium to rather high bearing force, andinconsiderable settlement.

Layer 2, 2a, 2b, 4a and 5a are soft soil layers, withlow bearing capacity and high settlement

Layer 2c, 3b, 3, 4, 4b, 5, 6a, 6b, 6, 7 and 7a havemedium to rather low bearing capacity, with mediumsettlement..

Layers 3a, 6c, 8 and 8a are soil layer types of ratherhigh bearing capacity, low settlement.

Layer 9 is type of high bearing capacity, lowsettleemnt

Hydrology conditionsTide – Water levelTide of Ganh Rai Bay-Thi Vai River and the neighbouringplaces is unusual semi-diurnal tide, the value of tideheight is over 4m. The average sea water levels of dryseasonal months are higher than that of rainy seasonalmonths; resulting from rising of sea water level in theEast Sea under monsoon influences.On Thi Vai River: The average tide height is 281cm;maximum tide height is 415cm; minimum tide height is143cm. Generally, tide height rises alongside Thi VaiRiver to up stream, getting the maximum height of 465cm atGo Dau (Long Bar, Dong Nai).In Vung Tau: The characteristics of tide height range from329cm in October and 407cm in June every year. The averageyearly tide height is 368cm.Physical – Chemical properties of water

River water

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province90

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

pH degree: pH = 7.20÷7.66.Salty degree: S = 23.6÷27.4‰.Suspended sediment: TSS = 9.1÷175.8 mg/l.Turbidity: NTU = 9.4÷154.7 mg/l.

Underground waterBased on the testing results of of 8 undergroundwater samples at the site, ground water has total ofaverage chemical-mineral concentrations ofM=35.68g/litre.Evaluation on structure corrosionAccording to Vietnam standard TCVN3994:1985 “Anticorrosionin Construction - Concrete and reinforced concretestructures– Classification of corrosive medium”, this areais subject to medium corrosive medium. In order to protectconcrete structures against corrosion, all concretestructures must have high density (TCVN 149:1986).

Flow DirectionBased on measurement results of flow direction on: 01÷03,November, 2005, it is showed that in construction site ofthe Plant, flow direction is nearly parallel with thebank.

WaveWave on Thi Vai River is not high. Result of wave observation for coastal area in period of hurricane influences (October, November), shows that:

Wave only occurs in direction of East, Southeast,South, and Southwest. Maximum frequency is Southeast(57.47%), following by the South direction (29.88%),East (8.05%) and Southwest (4.6%).

The average wave height observed from the East,Southeast, South and Southwest is 1.25m, 1.46m, 1.06mand 1.00m, respectively.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province91

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Meteorology conditionsAir temperatureAnnual average air temperature is 26.8oC, maximumtemperature is 33oC, minimum temperature is 20.0oC. Thehottest month is May whereas January is the coldest month.Annual average air temperature varies inconsiderably(26.8oC¸27.2oC). Maximum temperature varies from 30.7oC to38.0oC and minimum temperature varies from 14.1oC to22.5oC.Humidity

The average relative air humidity for years(1986÷2000) is 79%;

The lowest relative air humidity for years is 41%(26/2/1994);

WindAccording to data measured at Vung Tau meotereological station, some main characteristics of wind are shown as follows:

In dry season: the main direction is East andNortheast, average wind speed is 4.7 m/s (ranging from4.0 to 5.7m/s); max value is 5.7m/s in July;

In rainy season, the main direction is Southwest andWest – Southwest, average wind speed in rainy seasonreaches 3.6m/s (ranging from 3.5 to 4.2m/s).

The yearly average wind speed is 4.1 (m/s).RainfallRainy season occurs from May to October; total rainfall inrainy season accounts for about 91%. Total annual averagerainfall is 1,508mm. June and July are months witnessingthe highest frequency of precipitation. Dry season starts from November of previous year to thenext April; Rainfaill of this season is very little, evenit has no rain for month.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province92

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Special weather phenomenon (thunderstorm, storm, fog,…)In rainy seaons (from May to November), maximum number ofrainy days ranges from 18÷27. Number of rainstorm daysoccurs on the same (9÷25 days/month). Maximum number ofrainstorm days occur from February to November. The lowestmonth has only 8 rainy days, the highest month has 28rainy days (August). Maximum number of foggy days occursform previous October to next April (6÷26 days/month).

Storm: The southern area is under very little impact ofstorms. Normally, storm and tropical low pressure form inEast Sea in June to August.TECHNICAL SOLUTIONS FOR PACKAGE PK2Technical solutions and technical specifications aredetailed in Section 3 – Design Statement and TechnicalSpecifications of the Bid Package.Reclamation Reclamation of the package PK2 is divided into two areas:

Yard area: S=148,595.781 m2

Revetment area: S=9,450 m2

Reclamation at yard areaThe reclamation at yard area of package PK2 is derterminedby the control points in Table 0-1 (Volume 4-TechnicalStatement), excluding the leveled area of office block asshown in Table 3-2 (Volume 4-Technical Statement)For reclamation for Package PK2, refer to Drawing No: TV-2014-SN-02Reclamation volume of yard of PK2 is shown in drawing No: TV-2014-SN-05Reclamation at revetment areaThe reclamation of revetment area of package PK2 isdetermined by the control points in Table 0-1(Volume 4-Detailed design report). Reclamation at revetment area of package PK2 is shown in Drawing No: TV-2014-SNK-01

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province93

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Reclamation volume of revetment area of package PK2 is shown in drawingNo: TV-2014-SNK-02-13/13Soil ImprovementScope and parameters of Soil Improvement of yardSoil Improvement area of package PK2 is 140,456m2

Soil Improvement area is determined by control points atTable 0-4 (Volume 4-Detailed design report).Soil Improvement plan is shown in drawing No: TV-2014-CTĐ-02Layout of preload orde refer to Drawing: TV-2014-CTĐ-07, 08, 09, 10,11Layout for expected testing area is shown in drawing No: TV-2014-CTĐ-15Scope and parameters of Soil Improvement of revetment

Scope of Soil Improvement of revetment is S=4,200m2, it isdivided two regions: KV4’ with SKV4’ = 2,400m2 and KV7’ withSKV7’ = 1,800m2 adjacent to the KV4 and KV7 regions of theyard. Scope of Soil Improvement behind revetment isdetermined by the control points in Table 3-6 (Volume 4-Technical Statement).Layout for Soil Improvement division, please refer to Drawing No: TV-2014-CTĐK-01. Layout of preload orde refer to Drawing No: TV-2014-CTĐK-4-1/2, TV-2014-CTĐK-4-2/2.Layout for expected testing area is shown in drawing No TV-2014-CTĐK-07In order to ensure the stability for fill slope forsurcharge, it is necessary to place 2 layers of reinforcedgeotextile with strength of 400kN/m (each layer is 50mlong) at level of +5.30m and + 6.00m. In addition, at thesurcharge slope toe (level +4.7m) and the surface ofsurcharge block, at level of +7.0m, for Thi Vai RiverBank, sand bags are also provided.Cross section shall be provided with high strengthgeotextile, please refer to Drawing: TV-2014-CTĐK-05

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province94

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

MonitoringMonitoring for soft Soil Improvement includes the following works:

Measuring site settlement with settlement monitoringplate

Measuring penetration; Measuring pore water pressure Measuring underground water level Measuring horizontal displacement

Layout of monitoring equipment arrangement of yard area is shown indrawing No: TV-2014-CTĐ-15Layout for monitoring equipment arrangement of revetment area is shown indrawing No: TV-2014-CTĐK-07Road and yardConstruction ScaleInternal road system of Package PK2 includes: 01 main roadhas width of 25m from main gate to the berth and 02 subroads have width of 15m from berth to fence. 02 roads alsolocate along berth have width of 15m to separate betweenthe yard, storage, office area, and 01 road adjacentaccess road and parallel to berth has width of 20m.

- Total area of roads: 34,436.60 m2.- Total area of yards: 67,056.41 m2.

Roads and yards plan of package PK2 are shown in drawing No: TV-2014-ĐB-03.

Technical solutionTop elevation of yard is +5.8m (CDL) at center of yard,slope from 0.39% to 0.7% from the center to the boundary,elevation of road boundary is +5.5m (CDL).Plan of elevation and slope of road and yard are shown in drawing No: TV-2014-ĐB-02There are 3 types of pavement for each region, as follows:

Type 1: at the general cargo yard, empty container yard, steel yard, cargoyard areas.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province95

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Type 2: at the heavy cargo yard around general storage areas.

Type 4: at the internal road, road from internal road to outside road,road around steel yard, vehicle waiting road, road in vehicle areas.

Structure of road, yard detail are shown in drawing No: TV-2014-ĐB-05Traffic signal by paint detail is shown in drawing No: TV-2014-ĐB-07Detail of kerb is shown in drawing No: TV-2014-ĐB-09Surface drainage systemSurface drainage system of package PK2 includes: manhole,U-shape gutter, circular sewer, oil collecting pit, divideinto main lines as:

B1-B7 line is 447m long, along the adjacent phase 2road and perpendicular to Thi Vai River revetment.Structure of this line is reinforcement concretecircular sewer with some types of diameter.

1F, 1G lines: D1000 sewer, slope 0.2%, MH04, MG02manholes to collect surface water and discharge tooutlet 02.

1A, 2A, 2F, 3A lines (cross–tunnel): D800 sewer,connect U shape gutter, manholes to B1-B7 line.

1B, 1E, 2B, 2E, 3B, 3C, 3E lines loacate in theboundary of road, slope 0.2%, connect to manhole tocollect surface water from road and yard, structureof these lines is U shape gutter with 30cm width.

Lines (cross–tunnel under main arterial road) is 25mwide, at main gate and sub gate (1C, 1D, 2C, 2D, 3Dlines) slope 0.2%, collect surface water from mainarterial road and connecting road.

Surface water drainage system plan is shown in drawing No: TV-2014-TN-01Manhole detail is shown in drawing No: TV-2014-TN-03, 04, 05, 06,07Oil collecting pit detail is shown in drawing No: TV-2014-TN-08.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province96

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Revetment along Thi Vai RiverConstruction Scale

The length of revetment along Thi Vai River is 285m, 20mcandle cone at barge berth, 10m at phase 2 adjacentposition, so that the total length of revetment is 315m.The control points of revetment position are shown inTable 3-8 (Volume 4- Detailed design report).Area plan of revetment is shown in drawing No: TV-2014-KB-03Technical solution

Structural revetment is retaining wall by reinforcedconcrete M350 supported by PHC pile D500, combineswith slope embankment. The top elevation of revetmentis + 5.50m (Chart datum level).

To ensure the stability of the revetment duringoperation, must use two layers of high-strengthgeotextile 400kN/m, the length of high-strengthgeotextile is 46m at +4.00m elevation and 48m at+4.50m elevation.

Structural revetment detail is shown in drawings No: From TV-2014-KB-06-1/5 to 4/5Due to the area of reclamation of package PK2 overlaping20m at boundary line between phase 1 – phase 2 so the 80min total length of slope of reclamation(river side) atsegment No.5 (to SN7’ point) is covered by rubble with50cm thickness, crushed stone with 25cm thicknes under,the last layer is geotextile to prevent loss of sand whenwater level fluctuate. Control points of slopereclamationprotection revetment are shown in Table 3-9(Volume 4- Detailed design report).

Plan of revetment is shown in drawing No: TV-2014-KB-16Structural detail of revetment is shown in drawings No: TV-2014-KB-06-5/5

3. The time limit for completion 24.0 months, include rest days, holidays, new year fromthe date of commencement of construction.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province97

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province98

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Chapter VIIBILL OF QUANTITY

In this chapter, the tenderer lists work items that the contractor shallimplement, this is also basis for contractors to calculate bidding price.

TABLE 1: BILL OF QUANTITY OF PACKAGE PK2THI VAI PORT CONSTRUCTION INVESTMENT PROJECT – PHASE I

PART 1: RECLAMATION OF PAVEMENT AREA

No.Normcode

Work description Unit Quantity

1 AA.11121 Manual trees clearance 100m2 1485.96

2 AB.24141

Excavating soil (grade-I) and pouring soil into the vehicles by using excavators

100m3 822.07

3

AB.41431

AB.42331

AB.42431

Transporting and dumping soil using dump trucks within the distance of 10km

100m3 822.07

4 AB.24141

Excavating soil to the elevation of +4.7m 100m3 425.55

5 AB.41231

Transporting and dumping soil using dump trucks within the distance of <=500m

100m3 425.55

6 AB.66123

Filling sand to compensate the discharge volume and to level the ground in phase no.1 with the compacted sand density K=0.95 (re-use of preloading material)

100m3 425.55

7 AB.66123

Filling sand to compensate the discharge volume and to level the ground in phase no.1 with the compacted sand density K=0.95 (thematerial price is specified at theconstruction site)

100m3 1701.53

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province99

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

8 AL.16122 Non-woven geotextiles 100m2 75.37

TABLE 2: BILL OF QUANTITY OF PACKAGE PK2 THI VAI PORT CONSTRUCTION INVESTMENT PROJECT – PHASE I

PART 2: RECLAMATION OF REVETMENT AREA

No.Normcode

Work description Unit Quantity

1 AA.11121 Manual trees clearance 100m2 94.50

2 AB.24141

Excavating soil (grade-I) and pouring soil into the vehicles by using excavators

100m3 51.68

3

AB.41431

AB.42331

AB.42431

Transporting and dumping soil using dump trucks within the distance of 10km

100m3 51.68

4 AB.66123

Filling sand to compensate the discharge volume and reclamationofrevetment

100m3 247.04

5 AL.13311 Roof rubble 100m3 15.46

6 AL.16122 Non-woven geotextiles 100m2 114.98

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province100

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

TABLE 3: BILL OF QUANTITY OF PACKAGE PK2 THI VAI PORT CONSTRUCTION INVESTMENT PROJECT – PHASE I

PART 3: SOIL IMPROVEMENT OF PAVEMENT AREA

No.Normcode

Work description Unit Quantity

    AREA NO.2    

    1st preloading fill (up to the elevation of +7.0m)    

58 AB.66123

Surcharge up to the elevation of +7.0m with the compacted sand density of K=0.95 (making use of

100m3 975.05

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province101

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

unloading material from the area no.1)

59 AB.66123

Surcharge up to the elevation of +7,0m with the compacted sand density of K=0.95 (the material ispurchased)

100m3 81.92

60 AL.16111 PVD installation 100m 4174.73

61 AL.16111

Spread prefabricated horizontal strip drains m 19089.0

0

62 AL.16122 Non-woven geotextiles 100m2 38.75

63 AK.98110 Filter layer (crushed stone 2x4cm) m3 259.80

64 AK.98110 Blinding crushed stone 5-10cm m+ 0.51

65 BB.19412 Installing plastic pipe PVC D140 100m 13.28

66 BB.14219 Installing steel pipe D600 bar 31.80

67 BB.35201 Installing pump 6m3/h item 6.00

68 AB.11621

Excavation for pipe trench and water-collecting hole m3 261.49

    2nd surcharge (up to the elevation of +8.5m)    

69 AB.66123

Surcharge up to the elevation of +8.5m with the compaction density of K=0.95 (the material is purchased)

100m3 884.98

    Installing the equipment for monitoring the surface settlement    

70 AI.53121

Processing and installing steel plate structures ton 0.32

71 BB.14103

Processing and installing GS D25 steel structures 100m 0.54

72 BB.14105

Processing and installing GS D40 steel structures 100m 0.56

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province102

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

73 BA.14306

Conecting and installing plastic pipe D85 m 54.00

74 BB.38110 D100 plastic pipe end cap cover set 15.00

75 AB.13411 Manual sand filling m3 15.00

76 AG.42111

Installing the settlement monitoring equipment (labor only) item 15.00

77 CO.02102

Observing and recording settlementdata (10-15 points) time 40.00

    Installing Inclinometer    

78 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 14.30

79 BB.19408 Installing ABS plastic pipe 100m 0.18

80 BB.38108 ABS pipe end cap cover set 2.00

81 AC.32810 Pumping bentonite, cement motar m3 0.45

82 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Installing the Piezometer    

83 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 22.60

84 BA.16405 Installing signal cable m 68.00

85 AL.16122 None-woven geotextiles 100m2 0.01

86 AB.13411 Manual sand filling m3 0.06

87 AC.32810 Pumping bentonite, cement mortar m3 0.65

88 TT Piezometer item 2.00

89 CO.021001

Observing and recording settlementdata (<10 points)

time 40.00

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province103

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

    Installing monitoring equipment for depth settlement    

90 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 25.60

91 BB.19404 Installing plastic pipe D34mm 100m 0.33

92 BB.29101 Installing plastic elbow D34mm item 6.00

93 BB.38104

Installing pipe end caps D34 (a set of two end caps) set 2.00

94 TT Spider marget item 6.00

95 TT Positioning marget item 4.00

96 AC.32810 Pumping bentonite, cement mortar m3 0.80

97 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Underground water observation well    

98 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 14.60

99 BB.19406 Installing plastic pipe D50mm 100m 0.22

100 BB.29103 Installing plastic elbow D50mm item 4.00

101 BB.38106

Installing pipe end caps D50 (a set of two end caps) set 2.00

102 AL.16122 Non-woven geotextiles 100m2 0.01

103 AB.13411 Manual sand filling m3 0.39

104 AC.32810 Pumping bentonite, cement mortar m3 0.07

105 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Investigaion soil    

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province104

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

106 CC.011001 Depth of boring hole 0-30m m 30.00

107 CQ.011001 Cone penetration test (CPT) m 30.00

108 CQ.021001 Field vane shear test point 20.00

    Removal up to +5.0m level    

109 AB.24141 Removal up to +5.0m level 100m3 1322.01

110 AB.66124

Preparing the construction site bycompacting the ground with the compacted sand density of K=0.98

100m3 44.61

111 AB.41231

Transporting and dumping soil using dump trucks within the distance of <=500m

100m3 1322.01

    AREA NO.3    

    1st preloading fill (up to the elevation of 7.0m)    

112 AB.66123

Surcharge up to the elevation of +7,0m with the compacted sand density of K=0.95 (the material ispurchased)

100m3 1183.66

113 AL.16111 PVD installation 100m 4994.81

114 AL.16111

Spread prefabricated horizontal strip drains m 20310.0

0

115 AL.16122 Non-woven geotextiles 100m2 33.23

116 AK.98110 Filter layer (crushed stone 2x4cm) m3 225.47

117 AK.98110 Blinding crushed stone 5-10cm m3 0.34

118 BB.19412 Installing plastic pipe PVC D140 100m 11.79

119 BB.14219 Installing steel pipe D600 bar 21.20

120 BB.3520 Installing pump 6m3/h item 4.00

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province105

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

1

121 AB.11621

Excavation for pipe trench and water - collecting hole m3 226.60

    2nd preloading fill (up to the elevation of +8.5m)    

122 AB.66123

Preloading up to the elevation of +8.5m with the compacted sand density of K=0.95 (the material ispurchased)

100m3 1072.71

    Installing the equipment for monitoring surface settlement    

123 AI.53121

Processing and installing steel plate structures ton 0.34

124 BB.14103

Processing and installing GS D25 steel structures 100m 0.58

125 BB.14105

Processing and installing GS D40 steel structures 100m 0.60

126 BA.14306

Connecting and installing plastic pipe D85 m 57.60

127 BB.38110 D100 plastic pipe end cap cover item 16.00

128 AB.13411 Manual sand filling m3 16.00

129 AG.42111

Installing the settlement monitoring equipment (labor only) item 16.00

130 CO.02103

Observing and recording settlementdata (16-20 points) time 40.00

    Installing the inclinometer    

131 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 14.30

132 BB.19408 Installing ABS plastic pipe 100m 0.18

133 BB.38108 ABS Pipe end cap cover item 2.00

134 AC.32810 Pumping bentonite, cement mortar m3 0.45

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province106

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

135 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Installing Piezometer    

136 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 24.60

137 BA.16405 Installing signal cables m 70.00

138 AL.16122 Non-woven geotextiles 100m2 0.01

139 AB.13411 Manual sand filling m3 0.06

140 AC.32810 Pumping bentonite, cement mortar m3 0.71

141 TT Piezometer item 2.00

142 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Installing soil settlement indicator    

143 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 27.60

144 BB.19404 Installing plastic pipes 34mm 100m 0.35

145 BB.29101 Installing plastic elbow D 34mm item 6.00

146 BB.38104

Installing pipe end caps D34 (a set of two end caps) set 2.00

147 TT Spider magnet item 6.00

148 TT Spider magnet item 4.00

149 AC.32810 Pumping bentonite, cement mortar m3 0.87

150 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Underground water observation well    

151 BD.1810 Drilling D200 hole for installing m 14.60

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province107

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

1 the settlement monitoring equipment

152 BB.19406 Installing the plastic pipe 50mm 100m 0.22

153 BB.29103 Installing the plastic pipe 50mm item 4.00

154 BB.38106

Installing pipe end caps D50 (a set of two end caps) set 2.00

155 AL.16122 Non-woven geotextiles 100m2 0.01

156 AB.13411 Manual sand filling m3 0.39

157 AC.32810 Pumping bentonite, cement mortar m3 0.07

158 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Investigaion soil    

159 CC.011001 Depth of boring hole 0-30m m 32.00

160 CQ.011001 Cone penetration test (CPT) m 32.00

161 CQ.021001 Field Vane Shear Test point 22.00

    Removal up to +5.0m level    

162 AB.24141 Removal up to +5.0m level 100m3 1451.33

163 AB.66124

Preparing the construction site bycompacting the ground with the compacted sand density of K=0.98

100m3 50.02

164 AB.41231

Transporting and dumping soil using dump trucks within the distance of <=500m

100m3 1451.33

    AREA NO.4    

    1st preloading fill (up to the elevation of +7.0m)    

165 AB.66123

Filling sand up to the elevation of +7.0m with the compacted sand

100m3 188.16

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province108

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

densisty of K=0.95 (the material is purchased)

166 AL.16111 PVD installation 100m 995.11

167 AL.16111

Spread prefabricated horizontal strip drains m 3080.00

168 AL.16122 Non-woven geotextiles 100m2 4.93

169 AK.98110 Filter layer (crushed stone 2x4cm) m3 32.52

170 AK.98110 Blinding crushed stone 5-10cm m3 0.08

171 BB.19412 Installing plastic pipe PVC D140 100m 1.60

172 BB.14219 Installing steel pipe D600 bar 5.30

173 BB.35201 Installing pump 6m3/h item 1.00

174 AB.11621

Excavation for pipe trench and water-collecting hole m3 32.80

    timeSurcharge 2 nd time to level +8.5m    

175 AB.66123

Surcharge up to the elevation of +8.5m with the compacted sand density of K=0.95 (the material ispurchased)

100m3 171.46

    Installing the equipment for monitoring surface settlement    

176 AI.53121

Processing and installing steel plate structures ton 0.13

177 BB.14103

Processing and installing GS D25 steel structures 100m 0.22

178 BB.14105

Processing and installing GS D40 steel structures 100m 0.23

179 BA.14306

Connecting and installing plastic pipes D85 m 21.60

180 BB.3811 D100 Plastic pipe end cap cover item 6.00

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province109

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

0

181 AB.13411 Manual sand filling m3 6.00

182 AG.42111

Installing the settlement monitoring equipment (labor only) item 6.00

183 CO.02101

Observing and recording settlementdata (<10 points) time 40.00

    Installing the Inclinometer    

184 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 55.90

185 BB.19408 Installing ABS plastic pipe 100m 0.67

186 BB.38108 ABS Pipe end cap cover set 6.00

187 AC.32810 Pumping bentonite, cement mortar m3 1.76

188 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Installing the piezometer    

189 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 18.80

190 BA.16405 Installing signal cables m 43.50

191 AL.16122 Non-woven geotextiles 100m2 0.01

192 AB.13411 Manual sand filling m3 0.03

193 AC.32810 Pumping bentonite, cement mortar m3 0.56

194 TT Piezometer item 1.00

195 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Installing soil settlement indicator    

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province110

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

196 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 20.30

197 BB.19404 Installing plastic pipes 34mm 100m 0.24

198 BB.29101 Installing plastic elbow D 34mm item 4.00

199 BB.38104

Installing pipe end caps D34 (a set of two end caps) set 1.00

200 TT Spider magnet item 3.00

201 TT Positioning magnet item 2.00

202 AC.32810 Cement mortar pumping, bentonite m3 0.64

203 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Underground water observation well    

204 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 7.30

205 BB.19406 Installing the plastic pipe 50mm 100m 0.11

206 BB.29103

Installing the plastic elbow D 50mm item 2.00

207 BB.38106

Installing pipe end caps D50 (a set of two end caps) set 1.00

208 AL.16122 Non-woven geotextiles 100m2 0.01

209 AB.13411 Manual sand filling m3 0.16

210 AC.32810 Pumping bentonite, cement mortar m3 0.07

211 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Investigation soil    

212 CC.011001 Depth of boring hole 0-30m m 23.00

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province111

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

213 CQ.011001 Cone penetration test (CPT) m 23.00

214 CQ.021001 Field Vane Shear Test point 18.00

    Removal up to +5.0m level    

215 AB.24141 Removal up to +5.0m level 100m3 201.75

216 AB.66124

Preparing the construction site bycompacting the ground with the compacted sand density of K=0.98

100m3 7.53

217 AB.41231

Transporting and dumping soil using dump trucks within the distance of <=500m

100m3 201.75

    AREA NO.5    

    Loading the 1st time (up to the elevation of +7.0m)    

218 AB.66123

Surcharge up to the elevation of +7.0m with the compacted sand density of K=0.95 (making use of unloading material from the area no.3,4)

100m3 353.23

219 AL.16111 PVD installation 100m 1488.46

220 AL.16111

Spread prefabricated horizontal strip drains m 6600.00

221 AL.16122 Non-woven geotextiles 100m2 8.07

222 AK.98110 Filter layer (crushed stone 2x4cm) m+ 52.31

223 AK.98110 Blinding crushed stone 5-10cm m3 0.17

224 BB.19412 Installing plastic pipe PVC D140 100m 2.48

225 BB.14219 Installing steel pipe D600 bar 10.60

226 BB.35201 Installing pump 6m3/h item 2.00

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province112

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

227 AB.11621

Excavation for pipe trench and water-collecting hole m3 52.87

    2nd preloading fill (up to the elevation of +8.5m)    

228 AB.66123

Surcharge up to the elevation of +8.5 m with the compacted sand density of K=0.95 (making use of unloading material)

100m3 283.36

    Installing the equipment for monitoring surface settlement    

229 AI.53121

Processing and installing steel plate structures ton 0.13

230 BB.14103

Processing and installing GS D25 steel structures 100m 0.22

231 BB.14105

Processing and installing GS D40 steel structures 100m 0.23

232 BA.14306

Connecting and installing plastic pipes D85 m 21.60

233 BB.38110 D100 Plastic pipe end cap cover item 6.00

234 AB.13411 Manual sand filling m3 6.00

235 AG.42111

Installing the settlement monitoring equipment (labor only) item 6.00

236 CO.02101

Observing and recording settlementdata (<10 points) time 40.00

    Installing the Inclinometer    

237 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 15.30

238 BB.19408 Installing ABS plastic pipe 100m 0.19

239 BB.38108 ABS Pipe end cap cover set 2.00

240 AC.32810 Pumping bentonite, cement mortar m3 0.48

241 CO.0210 Observing and recording settlement time 40.00

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province113

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

01 data (<10 points)

    Installing piezometer    

242 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 13.30

243 BA.16405 Installing signal cables m 37.00

244 AL.16122 Non-woven geotextiles 100m2 0.01

245 AB.13411 Manual sand filling m3 0.03

246 AC.32810 Pumping bentonite, cement mortar m3 0.39

247 TT Piezometer item 1.00

248 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Installing soil settlement indicator    

249 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 14.30

250 BB.19404 Installing plastic pipes 34mm 100m 0.18

251 BB.29101 Installing plastic elbow D 34mm item 3.00

252 BB.38104 Installing plastic elbow D 34mm set 1.00

253 TT Spider magnet item 3.00

254 TT Positioning magnet item 2.00

255 AC.32810 Pumping bentonite, cement mortar m3 0.45

256 CO.021001

Observing and recording settlementdata (<10 points)) time 40.00

    Underground water observation well    

257 BD.18101

Drilling D200 hole for installing the settlement monitoring

m 7.30

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province114

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

equipment

258 BB.19406 Installing the plastic pipe 50mm 100m 0.11

259 BB.29103

Installing the plastic elbow D 50mm item 2.00

260 BB.38106

Installing pipe end caps D50 (a set of two end caps) set 1.00

261 AL.16122 Non-woven geotextiles 100m2 0.01

262 AB.13411 Manual sand filling m3 0.16

263 AC.32810 Pumping bentonite, cement mortar m3 0.07

264 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Investigaion soil    

265 CC.011001 Depth of boring hole 0-30m m 17.00

266 CQ.011001 Cone penetration test (CPT) m 17.00

267 CQ.021001 Field Vane Shear Test point 12.00

    Removal up to +5.0m level    

268 AB.24141 Removal up to +5.0m level 100m3 475.68

269 AB.66124

Preparing the construction site bycompacting the ground with the compacted sand density of K=0.98

100m3 15.80

270 AB.41231

Transporting and dumping soil using dump trucks within the distance of <=500m

100m3 475.68

    AREA NO.6    

    1st preloading fill (up to the elevation of +7.0m)    

271 AB.66123

Surcharge up to the elevation of +7.0m with the compacted sand density of K=0.95 (making use of

100m3 606.07

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province115

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

unloading material from the area 3and4)

272 AL.16111 PVD installation 100m 2687.73

273 AL.16111

Spread prefabricated horizontal strip drains m 11000.0

0

274 AL.16122 Non-woven geotextiles 100m2 17.58

275 AK.98110 Filter layer (crushed stone 2x4cm) m3 119.58

276 AK.98110 Blinding crushed stone 5-10cm m3 0.17

277 BB.19412 Installing plastic pipe PVC D140 100m 6.27

278 BB.14219 Installing steel pipe D600 bar 10.60

279 BB.35201 Installing pump 6m3/h item 2.00

280 AB.11621

Excavation for pipe trench and water-collecting hole m3 120.14

    2nd preloading fill (up to the elevation of +8.5m)    

281 AB.66123

Surcharge up to the elevation of +8.5 m with the compacted sand density of K=0.95 (making use of unloading material)

100m3 410.42

282 AB.66123

Surcharge up to the elevation of +8.5m with the compacted density of K=0.95 (the material is purchased)

100m3 136.59

    Installing the equipment for monitoring surface settlement    

283 AI.53121

Processing and installing steel plate structures ton 0.15

284 BB.14103

Processing and installing GS D25 steel structures 100m 0.25

285 BB.14105

Processing and installing GS D40 steel structures

100m 0.26

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province116

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

286 BA.14306

Connecting and installing plastic pipes D85 m 25.20

287 BB.38110 D100 Plastic pipe end cap cover item 7.00

288 AB.13411 Manual sand filling m3 7.00

289 AG.42111

Installing the settlement monitoring equipment (labor only) item 7.00

290 CO.02101

Observing and recording settlementdata (<10 points) time 40.00

    Installing the Inclinometer    

291 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 16.30

292 BB.19408 Installing ABS plastic pipe 100m 0.20

293 BB.38108 ABS Pipe end cap cover set 2.00

294 AC.32810 Pumping bentonite, cement mortar m3 0.51

295 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Installing piezometer    

296 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 13.80

297 BA.16405 Installing signal cables m 37.50

298 AL.16122 Non-woven geotextiles 100m2 0.01

299 AB.13411 Manual sand filling m3 0.03

300 AC.32810 Pumping bentonite, cement mortar m3 0.40

301 TT Piezometer item 1.00

302 CO.021001

Observing and recording settlementdata (<10 points)

time 40.00

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province117

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

    Installing soil settlement indicator    

303 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 15.30

304 BB.19404 Installing plastic pipes 34mm 100m 0.19

305 BB.29101 Installing plastic elbow D 34mm item 4.00

306 BB.38104

Installing pipe end caps D34 (a set of two end caps) set 1.00

307 TT Spider magnet item 3.00

308 TT Positioning magnet item 2.00

309 AC.32810 Pumping bentonite, cement mortar m3 0.48

310 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Underground water observation well    

311 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 7.30

312 BB.19406 Installing the plastic pipe 50mm 100m 0.11

313 BB.29103

Installing the plastic elbow D 50mm item 2.00

314 BB.38106

Installing pipe end caps D50 (a set of two end caps) set 1.00

315 AL.16122 Non-woven geotextiles 100m2 0.01

316 AB.13411 Manual sand filling m3 0.16

317 AC.32810 Pumping bentonite, cement mortar m3 0.07

318 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Investigaion soil    

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province118

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

319 CC.011001 Depth of boring hole 0-30m m 18.00

320 CQ.011001 Cone penetration test (CPT) m 18.00

321 CQ.021001 Field Vane Shear Test point 13.00

    Removal up to +5.0m level    

322 AB.24141 Removal up to +5.0m level 100m3 772.31

323 AB.66124

Preparing the construction site bycompacting the ground with the compacted sand density of K=0.98

100m3 26.57

324 AB.41231

Transporting and dumping soil using dump trucks within the distance of <=500m

100m3 772.31

    AREA NO.7    

    1st preloading fill (up to the elevation of +7.0m)    

325 AB.66123

Surcharge up to the elevation of +7.0m with the compacted density of K=0.95 (making use of unloading material from the area no. 2)

100m3 125.69

326 AL.16111 PVD installation 100m 628.88

327 AL.16111

Spread prefabricated horizontal strip drains m 2320.00

328 AL.16122 Non-woven geotextiles 100m2 3.92

329 AK.98110 Filter layer (crushed stone 2x4cm) m3 25.32

330 AK.98110 Blinding crushed stone 5-10cm m3 0.08

331 BB.19412 Installing plastic pipe PVC D140 100m 1.20

332 BB.14219

Installing steel pipe D600 bar 5.30

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province119

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

333 BB.35201 Installing pump 6m3/h item 1.00

334 AB.11621

Excavation for pipe trench and water-collecting hole m3 25.60

    2nd preloading fill (up to the elevation of +8.5m)    

335 AB.66123

Filling sand up to the elevation of +8.5 m with the compaction densisty of K=0.95 (making use ofunloading material)

100m3 107.27

    Installing the equipment for monitoring surface settlement    

336 AI.53121

Processing and installing steel plate structures ton 0.08

337 BB.14103

Processing and installing GS D25 steel structures 100m 0.14

338 BB.14105

Processing and installing GS D40 steel structures 100m 0.15

339 BA.14306

Connecting and installing plastic pipes D85 m 14.40

340 BB.38110 D100 Plastic pipe end cap cover item 4.00

341 AB.13411 Manual sand filling m3 4.00

342 AG.42111

Installing the settlement monitoring equipment (labor only) item 4.00

343 CO.02101

Observing and recording settlementdata (<10 points) time 40.00

    Installing the Inclinometer    

344 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 30.60

345 BB.19408 Installing ABS plastic pipe 100m 0.38

346 BB.38108 ABS Pipe end cap cover set 4.00

347 AC.3281 Pumping bentonite, cement mortar m3 0.96

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province120

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

0

348 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Installing piezometer    

349 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 13.80

350 BA.16405 Installing signal cables m 37.50

351 AL.16122 Non-woven geotextiles 100m2 0.01

352 AB.13411 Manual sand filling m3 0.03

353 AC.32810 Pumping bentonite, cement mortar m3 0.40

354 TT Piezometer item 1.00

355 CO.021001

Observing and recording settlementdata (<10 points) timetime 40.00

    Installing soil settlement indicator    

356 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 15.30

357 BB.19404 Installing plastic pipes 34mm 100m 0.18

358 BB.29101 Installing plastic elbow D 34mm item 3.00

359 BB.38104

Installing pipe end caps D34 (a set of two end caps) set 1.00

360 TT Spider magnet item 3.00

361 TT Positioning magnet item 2.00

362 AC.32810 Pumping bentonite, cement mortar m3 0.48

363 CO.021001 Pumping bentonite, cement mortar time 40.00

    Underground water observation well    

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province121

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

364 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 7.30

365 BB.19406 Installing the plastic pipe 50mm 100m 0.11

366 BB.29103

Installing the plastic elbow D 50mm item 2.00

367 BB.38106

Installing pipe end caps D50 (a set of two end caps) set 1.00

367 AL.16122 Non-woven geotextiles 100m2 0.01

368 AB.13411 Manual sand filling m3 0.16

370 AC.32810 Pumping bentonite, cement mortar m3 0.07

371 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Investigaion soil    

372 CC.011001 Depth of boring hole 0-30m m 18.00

373 CQ.011001 Cone penetration test (CPT) m 18.00

374 CQ.021001 Field Vane Shear Test point 13.00

    Removal up to +5.0m level    

375 AB.24141 Removal up to +5.0m level 100m3 171.62

376 AB.66124

Preparing the construction site bycompacting the ground with the compacted sand density of K=0.98

100m3 5.98

377 AB.41231

Transporting and dumping soil using dump trucks within the distance of <=500m

100m3 171.62

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province122

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

TABLE 4: BILL OF QUANTITY OF PACKAGE PK2 THI VAI PORT CONSTRUCTION INVESTMENT PROJECT – PHASE I

PART 4: SOIL IMPROVEMENT OF REVETMENT AREA

No.Normcode

Work description Unit Quantity

    AREA NO.4'    

    1st preloading fill (up to the elevation of +7.0m)    

1 AB.66123

Surcharge up to the elevation of +7.0m with the compacted sand density of K=0.95

100m3 58.65

2 AL.16111 PVD installation 100m 373.05

3 AL.16111

Spread prefabricated horizontal strip drains m 1155.00

4 AL.16122 Non-woven geotextiles 100m2 4.92

5 AK.98110 Filter layer (crushed stone 2x4cm) m3 32.39

6 AK.98110 Blinding crushed stone 5-10cm m3 0.08

7 BB.19412 Installing plastic pipe PVC D140 100m 1.59

8 BB.14219 Installing steel pipe D600 bar 5.30

9 BB.35201 Installing pump 6m3/h item 1.00

10 AB.11621

Excavation for pipe trench and water-collecting hole m3 32.67

11 AL.16121 Spreading geotextiles 400/50KN/m 100m2 170.00

12 AL.81110

Packing sandbags (included material, packing bags, arranging to bulk)

m3 36.27

13 AL.73310

Loading and transporting sandbags using labor within the distance of10m

m3 36.27

    2nd surcharge (up to the elevation of +8.5m)    

14 AB.66123

Surcharge up to the elevation of +8.5m with the compacted sand

100m3 60.44

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province123

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

density of K=0.95

15 AL.81110

Packing sandbags (included material, packing bags, arranging to bulk)

m3 18.13

16 AL.73310

Loading and transporting sandbads using labor within the distance of10m

m3 18.13

    Installing the equipment for monitoring surface settlement    

17 AI.53121

Processing and installing steel plate structures ton 0.04

18 BB.14103

Processing and installing GS D25 steel structures 100m 0.07

19 BB.14105

Processing and installing GS D40 steel structures 100m 0.08

20 BA.14306

Connecting and installing plastic pipes D85 m 2.00

21 BB.38110 D100 Plastic pipe end cap cover item 2.00

22 AB.13411 Manual sand filling m3 2.00

23 AG.42111

Installing the settlement monitoring equipment (labor only) item 2.00

24 CO.02101

Observing and recording settlementdata (10-15 points) time 40.00

    Installing the Inclinometer    

25 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 40.60

26 BB.19408 Installing ABS plastic pipe 100m 0.48

27 BB.38108 ABS Pipe end cap cover set 4.00

28 AC.32810 Pumping bentonite, cement mortar m3 1.28

30 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Installing the piezometer    

31 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 18.30

32 BA.16405

Installing signal cables m 43.50

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province124

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

33 AL.16122 Non-woven geotextiles 100m2 0.01

34 AB.13411 Manual sand filling m3 0.03

35 AC.32810 Pumping bentonite, cement mortar m3 0.54

36 TT Piezometer set 3.00

38 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Installing soil settlement indicator    

39 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 20.30

40 BB.19404 Installing plastic pipes 34mm 100m 0.24

41 BB.29101 Installing plastic elbow D 34mm item 4.00

42 BB.38104

Installing pipe end caps D34 (a set of two end caps) set 1.00

43 TT Spider magnet item 3.00

44 TT Positioning magnet item 2.00

45 AC.32810 Pumping bentonite, cement mortar m3 0.64

47 CO.021001

Observing and recording settlementdata (<10 points)

times 40.00

    Underground water observation well    

48 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 7.30

49 BB.19406 Installing the plastic pipe 50mm 100m 0.20

50 BB.29103

Installing the plastic elbow D 50mm item 4.00

51 BB.38106

Installing pipe end caps D50 (a set of two end caps) set 1.00

52 AL.16122 Non-woven geotextiles 100m2 0.01

53 AB.13411 Manual sand filling m3 0.16

54 AC.32810

Pumping bentonite, cement mortar m3 0.07

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province125

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

55 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Investigaion soil    

56 CC.011001 Depth of boring hole 0-30m m 17.00

57 CQ.011001 Cone penetration test (CPT) m 17.00

58 CQ.021001 Field Vane Shear Test poin

t 17.00

    Removal up to +5.0m level    

59 AB.24141 Removal up to +5.0m level 100m3 80.84

60 AB.41231

Transporting and dumping soil using dump trucks within the distance of <=500m

100m3 80.84

    AREA NO.7'    

    1st preloading fill (up to the elevation of +7.0m)    

62 AB.66123

Surcharge up to the elevation of +7.0m with the compacted density of K=0.95 (making use of unloading material)

100m3 41.40

63 AL.16111 PVD installation 100m 235.76

64 AL.16111

Spread prefabricated horizontal strip drains m 870.00

65 AL.16122 Non-woven geotextiles 100m2 3.90

66 AK.98110 Filter layer (crushed stone 2x4cm) m3 25.19

67 AK.98110 Blinding crushed stone 5-10cm m3 0.08

68 BB.19412 Installing plastic pipe PVC D140 100m 1.19

69 BB.14219 Installing steel pipe D600 bar 5.30

70 BB.35201 Installing pump 6m3/h item 1.00

71 AB.11621

Excavation for pipe trench and water-collecting hole m3 25.47

72 AL.16121

Spreading geotextiles 400/50KN/m 100m2 120.00

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province126

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

73 AL.81110

Packing sandbags (included material, packing bags, arranging to bulk)

m3 25.60

74 AL.73310

Loading and transporting sandbags using labor within the distance of10m

m3 25.60

    2nd preloading fill (up to the elevation of +8.5m)    

75 AB.66123

Filling sand up to the elevation of +8.5 m with the compaction densisty of K=0.95 (making use ofunloading material)

100m3 39.44

76 AB.66123

Filling sand up to the elevation of +8.5 m with the compaction densisty of K=0.95 (the material is purchased)

100m3 1.07

77 AL.81110

Packing sandbags (included material, packing bags, arranging to bulk)

m3 12.80

78 AL.73310

Loading and transporting sandbags using labor within the distance of10m

m3 12.80

    Installing the equipment for monitoring surface settlement    

79 AI.53121

Processing and installing steel plate structures ton 0.04

80 BB.14103

Processing and installing GS D25 steel structures 100m 0.07

81 BB.14105

Processing and installing GS D40 steel structures 100m 0.08

82 BA.14306

Connecting and installing plastic pipes D85 m 2.00

83 BB.38110 D100 Plastic pipe end cap cover item 2.00

84 AB.13411 Manual sand filling m3 2.00

85 AG.42111

Installing the settlement monitoring equipment (labor only) item 2.00

86 CO.02101

Observing and recording settlementdata (<10 points) time 40.00

    Installing the Inclinometer    87 BD.1810

1Drilling D200 hole for installing the settlement monitoring equipment

m 15.30

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province127

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

88 BB.19408 Installing ABS plastic pipe 100m 0.19

89 BB.38108 ABS Pipe end cap cover set 2.00

90 AC.32810 Pumping bentonite, cement mortar m3 0.48

91 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

   Drilling D200 hole for installing the settlement monitoring equipment

   

92 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 18.30

93 BA.16405 Installing signal cables m 43.50

94 AL.16122 Non-woven geotextiles 100m2 0.01

95 AB.13411 Manual sand filling m3 0.03

96 AC.32810 Pumping bentonite, cement mortar m3 0.54

97 TT Piezometer item 3.00

98 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

    Installing soil settlement indicator    

99 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 20.30

100 BB.19404 Installing plastic pipes 34mm 100m 0.24

101 BB.29101 Installing plastic elbow D 34mm item 4.00

102 BB.38104

Installing pipe end caps D34 (a set of two end caps) set 1.00

103 TT Spider magnet item 3.00

104 TT Positioning magnet item 2.00

105 AC.32810 Pumping bentonite, cement mortar m3 0.64

106 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province128

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

    Underground water observation well    

107 BD.18101

Drilling D200 hole for installing the settlement monitoring equipment

m 7.30

108 BB.19406 Installing the plastic pipe 50mm 100m 0.20

109 BB.29103

Installing the plastic elbow D 50mm item 4.00

110 BB.38106

Installing pipe end caps D50 (a set of two end caps) set 1.00

111 AL.16122 Non-woven geotextiles 100m2 0.02

112 AB.13411 Manual sand filling m3 0.16

113 AC.32810 Pumping bentonite, cement mortar m3 0.07

114 CO.021001

Observing and recording settlementdata (<10 points) time 40.00

  Investigaion soil    

115 CC.011001 Depth of boring hole 0-30m m 17.00

116 CQ.011001 Cone penetration test (CPT) m 17.00

117 CQ.021001 Field Vane Shear Test poin

t 17.00

    Removal up to +5.0m level    

118 AB.24141 Removal up to +5.0m level 100m3 57.24

119 AB.41231

Transporting and dumping soil using dump trucks within the distance of <=500m

100m3 57.24

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province129

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

TABLE 5: BILL OF QUANTITY OF PACKAGE PK2THI VAI PORT CONSTRUCTION INVESTMENT PROJECT – PHASE I

PART 5: PAVEMENT

No.Normcode

Work description Unit Quantity

I   PAVEMENT TYPE I    

    1-2:General cargo pavement    

4 AL.16122 Spreading woven geotextiles 100m2 120.14

5 AD.11212 Paving the graded aggregate base 100m3 72.09

6 AD.23225

Medium-grained asphaltic course, thickness 8cm 100m2 120.14

    1-3: General cargo pavement    

7 AL.16122 Spreading woven geotextiles 100m2 351.04

8 AD.11212 Paving the graded aggregate base 100m3 210.62

9 AD.23225

Medium-grained asphaltic course, thickness 8cm 100m2 351.04

    1-6: Cargo pavement    

16 AL.16122 Spreading woven geotextiles 100m2 109.60

17 AD.11212 Paving the graded aggregate base 100m3 65.76

18 AD.23225

Medium-grained asphaltic course, thickness 8cm 100m2 109.60

II   PAVEMENT TYPE II    

    2-1: Pavement surrounding General warehouse    

19 AL.16122 Spreading woven geotextiles 100m2 89.78

20 AD.27311

Transporting the cement-bound graded from the mixing plant to

100m3 31.42

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province130

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

the construction site

21 AD.12330 Paving the cement-bound graded 100m3 31.42

22 AD.11212 Paving the graded aggregate base 100m3 35.91

23 AD.23225

Medium-grained asphaltic course, thickness 8cm 100m2 89.78

 III   PAVEMENT TYPE IV    

    4-1: Internal roads    

36 AL.16122 Spreading woven geotextiles 100m2 287.50

37 AD.11212 Paving the graded aggregate base 100m3 129.38

38 AD.23225

Medium-grained asphaltic course, thickness 8cm 100m2 287.50

    4-4: Connecting roads (at the maingate)    

45 AL.16122 Spreading woven geotextiles 100m2 32.10

46 AD.11212 Paving the graded aggregate base 100m3 14.45

47 AD.23225

Medium-grained asphaltic course, thickness 8cm 100m2 32.10

    4-5: Roads at the waiting area    

48 AL.16122 Spreading woven geotextiles 100m2 16.32

49 AD.11212 Paving the graded aggregate base 100m3 7.34

50 AD.23225

Medium-grained asphaltic course, thickness 8cm 100m2 16.32

    4-6: Roads at the parking area    

51 AL.16122 Spreading woven geotextiles 100m2 8.44

52 AD.11212 Paving the graded aggregate base 100m3 3.80

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province131

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

53 AD.23225

Medium-grained asphaltic course, thickness 8cm 100m2 8.44

 V   ROAD MARKING    

54 AK.91221 Road marking m2 762.10

 VI   KERB    

    6-1: Kerb at the border line next to the Phase no.2 area    

55 AG.32211 Formwork for concrete kerb 100m2 5.11

56 AG.11450 Precast concrete blocks M250 m3 51.04

57 AG.42141 Placing concrete blocks bloc

k 319.00

58 AF.11120 Concrete base course M150 m3 1.60

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province132

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

TABLE 6: BILL OF QUANTITY OF PACKAGE PK2THI VAI PORT CONSTRUCTION INVESTMENT PROJECT - PHASE I

PART 6: DRAINAGE SYSTEM

No.Normcode

Work description Unit Quantity

    DRAINAGE DITCHES WITH REINFORCED CONCRETE COVER    

    Drainage ditches    

1 AB.11521

Digging drainage ditches with the width of <=3m, the depth <=2m (grade-I soil)

m3 1814.88

2 AB.13113

Filling soil base with the compaction density of K=0.95 m3 909.72

3 AB.41231

Transporting and dumping soil usingdump trucks within the distance of <=500m

100m3 18.15

4 AK.98110

Paving the crushed stone aggregate sub-base course m3 83.54

5 AF.63220

Fabricating and placing reinforcingsteel for water drainage ditches, reinforcing steel bars' diameter <=18mm

ton 66.09

6 AI.13111 Fabricating steel structures ton 7.87

7 AI.64211 Placing steel structures ton 7.87

8 AF.81311 Formwork 100m2 47.20

9 AF.13210 Concrete grade 350 m3 527.37

    Drainage ditches' cover    

10 AG.13221

Fabricating and placing reinforcingsteel for water drainage ditches' slabs

ton 6.94

11 AG.31311

Formwork for water drainage ditches' slabs 100m2 5.70

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province133

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

12 AG.11410

Placing grade350 concrete for constructing water drainage ditches' slabs

m3 58.49

13 AI.13111 Fabricating steel structures ton 7.88

14 AI.64211 Placing steel structures ton 7.88

15 AG.42111

Placing slabs of the water drainageditches item 2089.0

0

    DRAINAGE DITCHES WITH STEEL COVER    

    Drainage ditches    

16 AB.11521

Digging drainage ditches with the width of <=3m, the depth <=2m (grade-I soil)

m3 84.39

17 AB.13113

Filling soil base with the compaction density of K=0.95 m3 27.38

18 AB.41231

Transporting and dumping soil usingdump trucks within the distance of <=500m

100m3 0.84

19 AK.98110

Paving the crushed stone aggregate sub-base course m3 10.26

20 AF.63220

Fabricating and placing reinforcingsteel for water drainage ditches, reinforcing steel bars' diameter <=18mm

ton 8.14

21 AI.13111 Fabricating steel structures ton 1.09

22 AI.64211 Placing steel structures ton 1.09

23 AF.81311 Formwork 100m2 2.68

24 AF.13210 Concrete grade 350 m3 61.54

    Drainage ditches' cover    

25 AG.11410 Fabricating steel cover ton 6.91

26 AG.4221 Placing steel cover item 145.00

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province134

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

1

27 AI.13111 Fabricating steel structures ton 5.10

28 AI.64211 Placing steel structures ton 5.10

    PLACING REINFORCED CONCRETE SEWER D1000, D800, D1250, D1500    

29 AB.11521

Digging drainage ditches with the width of <=3m, the depth <=2m (grade-I soil)

m3 2606.00

30 AB.13123

Filling soil base for sewer with the compaction densisty of K=0.95 m3 1484.7

3

31 AB.41231

Transporting and dumping soil usingdump trucks within the distance of <=500m

100m3 11.21

32 AF.61220

Fabricating and placing reinforcingsteel for sewer bearing pads , steel bars' diameter <=18mm

ton 4.54

33 AF.81111 Formwork for sewer bearing pads 100m2 5.56

34 AK.98110

Paving the crushed stone aggregate sub-base course m3 120.90

35 AF.11410

Placing grade350 concrete for constructing culvert bearing pads m3 184.54

36 BB.11507

Placing reinforced concrete sewer D1000, using rubber gaskets 100m 1.84

37 BB.11505

Placing reinforced concrete sewer D800, using rubber gaskets 100m 0.48

38 BB.11509

Placing reinforced concrete sewer D1250, using rubber gaskets 100m 1.50

39

BB.11510

BB.11511

Placing reinforced concrete sewer D1500, using rubber gaskets 100m 1.23

    MANHOLE    

    Fabricating and placing manholes' bottom slabs (type 1,2,3)    

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province135

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

40 AB.11441 Digging manholes' foundation m3 261.18

41 AB.13113

Filling soil base with the compaction density of K=0.95 m3 175.21

42 AB.41231

Transporting and dumping soil usingdump trucks within the distance of <=500m

100m3 0.86

43 AK.98110

Paving the crushed stone aggregate sub-base course m3 7.95

44 AF.11120 Concrete base course M150 m3 7.95

45 AG.13121

Fabricating and placing reinforcingsteels for manholes' bottom slabs, steel bars' diameter of <=18mm

ton 2.31

46 AG.31211 Formwork for manholes' bottom slabs 100m2 0.48

47 AG.11210

Placing grade350 concrete for manholes' bottom slabs m3 9.75

48 AG.42241 Placing manholes' bottom slabs item 10.00

    Fabricating and placing manholes' bottom slabs (type 4, 5)    

49 AB.11441 Digging manholes' foundation m3 78.64

50 AB.13113

Filling soil base with the compaction density of K=0.95 m3 50.64

51 AB.41231

Transporting and dumping soil usingdump trucks within the distance of <=500m

100m3 0.28

52 AK.98110

Paving the crushed stone aggregate sub-base course m3 1.94

53 AF.11120 Concrete base course M150 m3 1.94

54 AG.13121

Fabricating and placing reinforcingsteels for manholes' bottom slabs, steel bars' diameter of <=18mm

ton 0.54

55 AG.31211 Formwork for manholes' bottom slabs 100m2 0.10

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province136

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

56 AG.11210

Placing grade350 concrete for manholes' bottom slabs m3 2.80

57 AG.42241 Placing manholes' bottom slabs item 2.00

    Bearing beams    

58 AF.61220

Fabircating and placing reinforcingsteel for bearing beams, steel bars' diameter of <=18mm

ton 0.43

59 AF.61230

Fabircating and placing reinforcingsteel for bearing beams, steel bars' diameter of >18mm

ton 1.01

60 AF.81111 Formwork for bearing beams 100m2 0.23

61 AF.11410

Placing grade350 concrete for bearing beams m3 37.63

    Manholes' walls 2x2m (type 1, 2, 3)    

62 AF.63120

Fabricating and placing reinforcingsteel for manholes' walls, steel bars' diameter of <=18mm

ton 2.91

63 AF.81311 Formwork for manholes' walls 100m

2 2.83

64 AF.17210

Placing grade350 concrete for manholes' walls m3 26.69

    Manholes' walls 2x2.5m (type 4, 5)    

65 AF.63120

Fabricating and placing reinforcingsteel for manholes' walls, steel bars' diameter of <=18mm

ton 0.77

66 AF.81311 Formwork for manholes' walls 100m2 0.90

67 AF.17210

Placing grade350 concrete for manholes' walls m3 6.55

    Manholes' slabs type 1.7x1.7m    

68 AI.13111 Fabricating steel structures ton 1.04

69 AI.64211 Placing steel structures ton 1.04

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province137

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

70 AI.52231 Fabricating steel cover ton 5.13

71 AG.42211 Placing steel cover item 10.00

    Manholes' slabs type 1.7x2.2m    

72 AI.13111 Fabricating steel structures ton 0.24

73 AI.64211 Placing steel structures ton 0.24

74 AI.52231 Fabricating steel cover ton 1.32

75 AG.42211 Placing steel cover item 2.00

    OIL-REMOVAL HOLES    

    Oil-removal holes    

76 AB.11441 Digging manholes' foundation m3 246.10

77 AB.13113

Filling soil base with the compaction density of K=0.95 m3 142.14

78 AB.41231

Transporting and dumping soil usingdump trucks within the distance of <=500m

100m3 1.04

79 AK.98110

Paving the crushed stone aggregate sub-base course m3 4.79

80 AF.11120 Concrete base course M150 m3 4.79

81 AG.13121

Fabricating and placing reinforcingsteel for oil-removal holes, steel bars' diameter of <=18mm

ton 6.52

82 AF.63130

Fabricating and placing reinforcingsteel for oil-removal holes, steel bars' diameter of >18mm

ton 0.19

83 AF.81311 Formwork for oil-removal holes 100m2 1.04

84 AF.17210

Placing grade350 concrete for oil-removal holes m3 40.67

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province138

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

85 BB.19413 Placing plastic pipes PVC D200 100m 0.45

    Oil-removal holes' cover    

86 AI.13111 Fabricating steel structures ton 0.85

87 AI.64211 Placing steel structures ton 0.85

88 AI.52231 Fabricating steel cover ton 3.87

89 AG.42211 Placing steel cover item 8.00

    OUTLET    

90 AF.61220

Fabricating and placing reinforcingsteel for outlet, steel bars' diameter of <=18mm

ton 0.22

91 AF.11410

Placing grade 300 concrete for outlet m3 4.50

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province139

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

TABLE 7: BILL OF QUANTITY OF PACKAGE PK2THI VAI PORT CONSTRUCTION INVESTMENT PROJECT - PHASE IPART 7: PROTECTIVE REVETMENT ALONG THI VAI RIVER

No.Normcode

Work description Unit Quantity

    DREDGING EMBANKMENT    

1 AL.13312

Removel rubble under water (the labor and machine equal 70% arrangeworks)

100m3 15.46

2 AB.81222

Digging cap concrete area to construct embankment 100m3 340.24

3 AB.41231

Transporting and dumping soil usingdump trucks within the distance of <=500m

100m3 340.24

    TESTING PILE    

    Producing PHC pile    

4 TBG Testing pile D500, L=22m m 132.00

5 TBG Testing pile D500, L=24m m 96.00

6 AG.42231 VD

Craning pile from the seller’s vehicle to the material pavement pile 10.00

    Driving of testing pile    

7 AC.21121

Driving PHC pile on ground, pile diameter <= 550 mm (the undergroundpile part)

100m 2.28

8 TTLabor and machine waiting for driving pile (Price unit equal 70%), waiting time is 7 days

total 1.00

9 B8-4BNS Welding line 8mm 10m 1.28

10 B8-4BNS Welding line 10mm 10m 0.63

11 AK.94111 Bituminous 2 layers m2 1.48

12 TT Cutting pile cap pile 10.00

    Driving pile    

    Producing PHC pile    

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province140

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

13 TBG PHC pile D500, L=20m m 3840.00

14 TBG PHC pile D500, L=22m m 2640.00

15 AG.42231 VD

Craning pile from the seller’s vehicle to the material pavement pile 312.00

    Driving pile    

16 AC.21111

Driving PHC pile on ground, pile diameter <= 550 mm (the undergroundpile part)

100m 30.96

17 AC.21111

Driving raker PHC pile on ground, pile diameter <= 550 mm (the underground pile part)

100m 33.84

18 TT Cutting pile cap pile 312.00

    PILE CAP    

19 AF.65130

Fabricating and placing reinforcingsteel for pile cap, steel bars' diameter of >18mm

ton 20.33

20 AF.87211 Formwork for pile cap 100m2 5.16

21 AF.51140

Producing concrete by mixing plant on site, capacity mixing plant <=50m3/h

m3 52.62

22 AF.52112

Transporting concrete mortar by truck, distance <= 1km, truck 10.7m3, distance of <=0.5km

100m3 0.53

23 AF.34110

Placing grade350 concrete for pile cap m3 51.84

    CONNECTING PILE AND PILE CAP    

24 AF.65110

Fabricating and placing reinforcingsteel for conecting pile and pile cap, steel bars' diameter of <=10mm

ton 1.59

25 AF.65130

Fabricating and placing reinforcingsteel for conecting pile and pile cap, steel bars' diameter of >18mm

ton 18.61

26 AI.13111

Producing steel plate for connecting pile and pile cap ton 0.89

27 AF.5114 Producing concrete by mixing plant m3 23.20

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province141

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

0 on site, capacity mixing plant <=50m3/h

28 AF.52112

Transporting concrete mortar by truck, distance <= 1km, truck 10.7m3, distance of <=0.5km

100m3 0.23

29 AF.34110

Placing concrete for connecting pile and pile cap m3 22.86

    CORNER WALL    

30 AF.72210

Fabricating and placing reinforcingsteel for corner wall, steel bars' diameter of <=10mm

ton 0.07

31 AF.72220

Fabricating and placing reinforcingsteel for corner wall, steel bars' diameter of <=18mm

ton 39.61

32 AF.72230

Fabricating and placing reinforcingsteel for corner wall, steel bars' diameter of >18mm

ton 81.59

33 AF.86211 Formwork for corner wall 100m2 18.67

34 AI.13111 Fabricating shaped steel structures ton 1.06

35 AI.64211 Placing steel structures ton 1.06

36 AF.51140

Producing concrete by mixing plant on site, capacity mixing plant <=50m3/h

m3 661.45

37 AF.52112

Transporting concrete mortar by truck, distance <= 1km, truck 10.7m3, distance of <=0.5km

100m3 6.61

38 AF.44210

Placing grade350 concrete for corner wall m3 651.67

    TRANSITION SLAB    

39 AG.13121

Fabricating and placing reinforcingsteel for transition slab, steel bars' diameter of <=18mm

ton 18.61

40 AG.13131

Fabricating and placing reinforcingsteel for transition slab, steel bars' diameter of >18mm

ton 23.40

41 AG.3221 Formwork for transition slab 100m2 2.96

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province142

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

1

42 AG.11210

Placing grade350 concrete for transition slab m3 177.60

43 AG.42221 Installing transition slabs block 148.00

    FILTER LAYER    

44 AL.16122 Non-woven geotextiles 100m2 3.20

45 AL.12113 Filter layer (crushed stone 1x2cm) 100m3 0.29

    OTHER WORKS    

46 AF.11110 Concrete base course M100 m3 51.50

47 AL.41410 Strecth joint m 17.20

48 AL.13311

Filling the rubble base (the material is puchased ) 100m3 24.21

49 AL.13311

Filling the rubble base (making useof available material) 100m3 15.46

50 AL.13311 Roofing rubble 100m3 9.03

51 AL.12113 Filter layer (crushed stone 2x4cm) 100m3 3.13

52 AL.12113 Filter layer (crushed stone 4x6cm) 100m3 12.20

53 AL.16122 Non-woven geotextiles 100m2 67.39

54 AB.66124

Filling sand after embankment, tight requirement K = 0.98 100m3 183.40

55 AL.16121 Spreading geotextiles 400/50KN/m 100m 296.10

56 BB.19107 Installing plastic pipe PVC D90 100m 0.95

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province143

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Chapter VIIIREQUIREMENTS ON CONSTRUCTION PROGRESS

Total time for all construction work, supply ofmaterials, equipment, installation, inspection, and hand-over to put into service is 24.0 months, include day offwork, holiday, new year and value time from effective dateof the contract.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province144

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Chapter IXTECHNICAL REQUIREMENTS

1. General requirementsApplication Document

The single document using contractors from participatingin the tender to carry out construction, construction,handover and acceptance of work is put into use is definedas follows:

The legals for construction; Vietnam building code; The construction standards of Vietnam (TCVN, TCXD,

TCN, etc):Code Name of standard

TCXD 9355:2012Ground improvement by pretabricated vertical drain (PVD)/

22 TCN 262 - 2000 Design & Survey Process for highway foundation on soft soil

22TCN 211 - 06 Pavement - Requirements and guidelines for Design

22 TCN 207 - 92 Sea port construction - Design Standards

TCVN 5574:2012 Concrete and reinforced concrete structures - Design Standard

TCVN 9116:2012 Reinforced concrete box culverts

TCVN 9113:2012 Reinforced concrete pipes for water draining -

TCVN 9345:2012

Concrete and reinforced concrete structures - Guide on technical measures for prevention of cracks occurred under the action of hot humid climate

TCVN 9346:2012 Concrete and reinforcedconcrete

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province145

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

structures - Requirement of protection from corrosion in marine environment

TCVN 9386:2012 Design of structures for earthquake resistances -

TCVN 7957:2008Drainage and sewerage - External Networks and Facilities - Design Standard

TCVN 3989:1012

System of documents for building design water supply and drainage -External networks - Working drawings

TCVN 4447: 2012 Soil works - Construction, check and acceptance

TCVN 9361: 2012 Foundation works - Check and acceptance

TCVN 9379: 2012Building structures and foundations - Basic rules for calculations

TCVN 1651-2008 Steel for the reinforcement of concrete

TCVN 7570 - 2006 Aggregate for concrete and mortar - Specifications

TCVN 4506 : 2012 Water for concrete and mortar - Technical specification

TCVN 8819 : 2011Specification for Construction of Hot Mix Asphalt Concrete Pavement and Acceptence

TCVN 8820 : 2011Standard Practice for Asphalt Concrete Mix Design Using MarshallMethod

TCVN 8859:2011Graded Aggregate Bases and Subbases Pavement - Specification for Construction and Acceptance

Foreign Standards are approved by the competentauthority.

The tender document, detailed design documents of thepackage.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province146

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

The bidding document of contractor.

Definitions Client (Party A): Supervision consultant of client: is person of

supervision consultant unit is approved by client toimplement the supervision, responsibility andauthorization are regulated in Decree No. 12/2009 /ND-CP dated 12/02/2009 of the Government aboutManagement of Construction Investment Projects,Decree No. 15/2013 / ND-CP dated 06/02/2013 of theGovernment about Construction Quality Management.

Contractor (Party B): is constractor is approved byclient to implement the works content in thecontract.

Testing work

Testing agency is an agency is certified by the State All test results must be technicality legal

properties.2. Technical proposal of the Bidder

Based on the requirements of the tender document,detailed design document, standards, regulations ofVietnam, documents, related documents; the Contractor mustmake technical document in bidding document. Technicaldocument of contractor must show the main contents asfollowing:

1. The contractor's understanding about the project,work, include the scope, character of the work ...

2. The organization guidelines, technical management,construction quality of contractor.

3. The standards, regulations are used in theinstallation construction and equipment installation.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province147

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

4. Construction management organization methods areincluding:

Management organization in head office and at thesite;

Quality control unit in head office; Construction technique and safety management unit,

environmental, fire prevention at the site; Technical supervision unit at the site Equipments, materials supply Administrative, service unit at the site; Directly construction labor; The site preparation; The protections; Electrical system, lighting system to serve the

construction; Communication system to serve the construction;

5. Construction methods:Contractor must suggest by report and drawing (if

necessary). It needs to show the main contents asfollowing:

Survey, preparation of construction works; Materials, equipments Supply; The installation construction; The progress of construction and overall progress

graph of construction; List of construction equipments, quality control

instruments. Process and quality control methods.Repair damaged, warranty;

The security work, safety, fire prevention,environmental sanitation, ensuring traffic safety.

The other work which contractor is necessary…

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province148

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

TECHNICAL SOLUTIONS OF PACKAGE PK2

The solutions and requirements for construction arepresented in detail, specifically in Item 3 - Volume 4(Design Report) and Volume 2 (Specifications report) ofthe package.ReclamationReclamationarea of the package PK2 is divided into twoareas:

Yard area: S=148,595.781 m2

- Revetment area: S=9,450 m2

Reclamationof yard areaThe reclamationof yard area of package PK2 is derterminedby the control points in Table 0-1 (Volume 4-Detaileddesign report), exclude the reclamated area of office asshown in Table 3-2 (Volume 4-Detailed design report)

Table 0-1. Control points coordination of reclamationof yard area ofpackage PK2

No NamePoints

Coordinate system VN2000,central meridian 107o45’,

projection 3o

X(m) Y(m)

1 SN6 1,171,348.458 420,969.207

2 SN7 1,171,292.749 420,880.251

3 SN12 1,171,546.998 420,721.026

4 SN11 1,171,772.501 421,081.107

5 SN2 1,171,638.005 421,184.379

6 SN10 1,171,419.736 421,265.778

7 SN9 1,171,266.249 421,020.691

Table 0-2. reclamationcontrol points coordination of Office area (completed)

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province149

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No NamePoints

Coordinate system VN2000,central meridian 107o45’,

projection 3o

X(m) Y(m)1 QH5 1,171,715.928 421,028.4522 QH6 1,171,757.637 421,095.0533 QH7 1,171,745.756 421,104.1644 QH8 1,171,656.686 421,159.9455 QH9 1,171,614.225 421,092.143

Plan of Reclamation of PK2 is shown in Drawing No: TV-2014-SN-02With others areas that have not been reclamated, in areassuch existing elevation is lower than design elevation thesurface soil shall be excavated 1m thickness and then fillup to design elevation.At the adjacent river areas out of existing roads withaverage level + 5.0m (from SN7- SN7' line), the surfacesoil shall be excavated 1m thickness, spread geotextile,and then fill up and compact to design elevation.The main paremeters of reclamation work (The reclamationof yard area of package PK2) as:

Total reclamation area: 148,595.781 m2; Reclamation elevation: +4.70m (CDL); Compacting factor K ≥ 0.95; Reclamation volume: 130,550.770 m3; Excvation volume (to +4.7m elevation): 42,554.810

m3; Surface soil excavated volume: 82,207.420 m3; Geotextile: 7,536.79 m2.

Reclamation volume is shown in drawing No: TV-2014-SN-05

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province150

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Reclamation of Revetment areaThe reclamation of revetment area of package PK2 isdertermined by the control points in Table 0-3. Controlpoints coordination of reclamation of revetment area arefollowing:

Table 0-3. Control points coordination of reclamation of revetment area ofpackage PK2

NoNameof

Points

Coordinate system VN2000,central meridian 107o45’,

projection 3o

X(m) Y(m)

1 SNK1 1,171,280.036 420,888.212

2 SNK2 1,171,264.113 420,862.787

3 SNK3 1,171,531.075 420,695.600

4 SNK4 1,171,546.998 420,721.026Reclamation plan of revetment area of package PK2 is shown in drawing No: TV-2014-SNK-01For areas with elevations greater than + 4.7 m (ChartDatum Level); This area shall be excavated up to +4.7m(CDL) and the removal material shall be filled to lowerareas.With others areas that have not been reclamated, in areassuch existing elevation is lower than design elevation thesurface soil shall be excavated 1m thickness and then fillup to design elevation.In areas adjacent to the river (from SNK1-SNK2-SNK3-SNK4line), the surface soil shall be excavated 1m thickness,spread geotextile, and then fill up and compact to designelevation.The main paremeters of reclamation work (The reclamationarea of package PK2) as:

- Total reclamation area: 9,450 m2;- Reclamation elevation: +4.70m (CDL);

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province151

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

- Compacting factor: K ≥ 0.95;- Reclamation volume: 19,536.00 m3;- Surface soil excavated volume: 5,168.35 m3;- Geotextile: 11,497.78 m2,- Volume of roofing stone embankment: 1,545.50 m3,

Distance from the site to the surface soil dumpinglocation is 10km or another location as directed by theClient.Reclamation volume of revetment area of package PK2 is shown in drawingNo: TV-2014-SNK-02-13/13Soil ImprovementArea and main information of Soil Improvement of yard areaSoil Improvement yard area of package PK2 is 140,456m2.Depend on operation time requirement and the effectivenessto maximize re-using the pre-load material, soilimprovment area is divided into six regions as follow:

KV2 area: SKV2 = 44,476m2; KV3 area: SKV3 = 45,765m2; KV4 area: SKV4 = 6,400m2; KV5 area: SKV5 = 15,015m2; KV6 area: SKV6 = 24, 000m2;- KV7 area: SKV7 = 4,800m2.

Soil Improvement area is determined by control points atTable 0-4

Table 0-4. Control points coordination of Soil Improvement of yard area ofPK2

No Name ofpoints

(Coordinate system VN2000,central meridian 107o45’,

projection 3o)X(m) Y(m)

1 GT8-PK4A1 1,171,262.063 421,02.312

2 GT8 1,171,348.458 420,969.207

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province152

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No Name ofpoints

(Coordinate system VN2000,central meridian 107o45’,

projection 3o)X(m) Y(m)

3 GT9 1,171,292.749 420,880.2514 GT10 1,171,530.048 420,731.6415 GT11 1,171,723.246 421,040.1386 GT12 1,171,634.841 421,097.8577 GT13 1,171,669.206 421,150.6598 GT14 1,171,703.709 421,128.2039 GT15 1,171,710.950 421,139.76510 GT16 1,171,706.561 421,155.22111 GT17 1,171,603.091 421,206.22112 GT18 1,171,573.907 421,159.620

13 GT9-PK4A1 1,171,411.226 421,261.501

Soil Improvement of yard area plan is shown drawing No: TV-2014-CTĐ-02: Techinical requirement of Soil Improvementsoft Soil Improvement:

The top elevation of PVD: +5.3m (CDL) Operation Load: q = 4T/m2

Consolidation degree after a period of 200 days: U≥90%;

Residual settlement after a period of 200 days:+ Yard and road area: S 20cm+ Building area: S 20cm

Surcharge removal Elevation: +5.0mFor regions (from KV2 to KV7) 2nd surcharge periods shallbe done, 1st preloading fill up to +7.00m elevation (100days duration). The 2nd preloading fill up to +8.50m

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province153

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

elevation (100 days duration). Settlement for each regionin each surcharge period are shown at table 0-5:

Table 0-5. Settlement after surcharge period

No

Nameof

Regions

Settlement after surcharge period

100 days 200 days

1 KV2 55 1002 KV3 68 1223 KV4 82 1454 KV5 48 895 KV6 70 1256 KV7 70 133

Order of Soil Improvement for each region: Soil Improvement at KV3, KV4 region Re-use removal material from KV1’ for KV2 (the extra

volume will be bought) Re-use KV3, KV4’ surcharge material for KV5 and KV6

(the extra volume will be bought) Re-use KV2’ surcharge material for KV7 Removal material of KV2, KV5, KV6, KV7’ region shall

be displaced to phase 2 (for Reclamation). Allmaterial after unloading the property of the Client.

The order of Soil Improvement is shown in drawings No: TV-2014-CTĐ-07, 08, 09, 10, 11To evaluate the effectiveness of the Soil ImprovementsoftSoil Improvement, in addition to actual settlement andconsolidation (caculated based on observational data), thefield vane shear and standard penetration test CPTu in theSoil Improvement region as specified in the drawings andspecification shall be conducted. The field vane shearshall be carried out for each meter of depth of SoilImprovement layer.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province154

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

The expected testing location plan is shown drawing No:TV-2014-CTĐ-15Area and main information of Soil Improvement of revetment area

Soil Improvement revetment area of package PK2 is S =4,200m2 is divided into two areas KV4 'have SKV4’ = 2,400m2

and KV7 'have SKV7’ = 1,800m2 adjacent to the area of theyard KV4 and KV7. Soil Improvement revetment areadetermined by control points at Table 0-6

Table 0-6. Control points coordination of Soil Improvement of foundation ofroad behind revetment

No Name ofpoints

(Coordinate system VN2000,central meridian 107o45’,

projection 3o)X(m) Y(m)

1 K1 1,171,284.790 418,867.5382 K2 1,171,522.098 418,718.9273 GT9 1,171,292.749 420,880.2514 GT10 1,171,530.048 420,731.641

Soil Improvement plan of revetment area is shown drawing No: TV-2014-CTĐK-01Techinical requirement of Soil Improvementsoft Soil Improvement:

The top elevation of PVD: +5.3m (CDL) Load elevation: +8.5m (CDL) Operation Load: q = 2T/m2 Consolidation degree after a period of 200 days: U≥

90%;Residual settlement after a period of 200 days is S 20cm

Surcharge removal Elevation: +5.0mFor regions (from KV2 to KV7) 2 surcharge periods shall bedone, 1st preloading fill up to +7.00m elevation (100 days

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province155

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

duration). The 2nd preloading fill up to +8.50m elevation(100 days duration). Settlement for each region in eachsurcharge period are shown at table 0-7:

Table 0-7. Settlement after surcharge periods

NoNameof

Regions

Settlement after surcharge period

100 days 200 days

1 KV4’ 87.6 121.12 KV7’ 75.4 107.5

Order of Soil Improvement for each region: First conducted Soil Improvement at KV4' size

170mx15m (conducted at the same time Soil Improvementwith KV4' size 170mx40m of the yard area);

Re-use removal material from KV4’ for KV7’ size125mx15m (conducted at the same time Soil Improvementwith KV7 size 170mx40m of the yard area)

The order of Soil Improvement is shown in drawing No: TV-2014-CTĐK-4-1/2, TV-2014-CTĐK-4-2/2To evaluate the effectiveness of the Soil ImprovementsoftSoil Improvement, in addition to actual settlement andconsolidation (caculated based on observational data), thefield vane shear and standard penetration test CPTu in theSoil Improvement region as specified in the drawings andspecification shall be conducted. The field vane shearshall be carried out for each meter of depth of SoilImprovement layer.The expected testing location plan is shown drawing No: TV-2014-CTĐK-07

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province156

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

To ensure the stability of the slope of surchargematerial, must use two layers of high-strength geotextile400kN/m (50m for each layer) at the + 5.30m and +6.00melevation. Also at the toe of slope of surcharge material(+ 4.7m elevation) and on surface of slope (to + 7.0melavation) – Thi Vai River side must be covered by sandbag.High-strength geotextile detail cross-section is shown in drawings No:TV-2014-CTĐK-05ObservationParameters need for observationing in the reclamation workis as follow:

Surface settlement Deep settlement Pore water pressure Ground water level Horizontal displacement

At the +5.30m elevation, after the completion PVDinstalation and observational equipment set up iscompleted, all parameter must be observed to process theresults later.Surcharge material are filled up with 20cm thickness pertimes or 1 times per day depending on smaller thickness.After finishing surcharge work, observation work isstarted with frequency of 7 days / 1 times. The totalobservation period does not less than 40 times.The frequency of observation should be sufficient toensure the allowable appropriate tolerances fill forsettlement and ensure the design elevation in the finalstages of Reclamation.Before removing surcharge material, settlement value mustwithin 90% - 95% of the estimated consolidationsettlement.The observational equipment installation andobservational data processing detail are presented in the

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province157

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

specification. The contractor must have detailed outlineobservation fully reflect the content requirements in ofbidding.Plan of Observational equipment arrangement is shown drawing No: TV-2014-CTĐ-15Detail and instalation order of observational equipment is shown drawing No:TV-2014-CTĐK-07

The 2nd period surcharge and removing time regulationThe 2nd period surcharge starting condition (fill up to+8.5m elevation): consolidation degree is at least 68% andsettlement in the regions not less than the values listedin Table 3-4.Removing condition: consolidation degree (U) is at least90% and residual settlement S ≤ 20 cm (at the yard), S ≤20 cm (at the storage) and the settlement before removingis not less than the value in Table 3-4. Time for removingmust be approved by the supervisor.Do not remove surcharge material for conducting the nextwork if the observation data has not achieved thenecessary consolidation settlement as designed.Road and yardConstruction ScaleRoad network (phase 1 area) include: 01 main arterial roadhas width of 25m from main gate to the berth and 02 subroads have width of 15m from berth to fence. 02 roads alsolocate along berth have width of 15m to separate betweenthe yard, storage, office area, and 01 road adjacentaccess road and parallel to berth has width of 20m.Roads and yards: Yard (Legend 1-1, 1-4, 1-6), generalcargo (legend 1-2, 1-3), emty container yard (legend 1-5),yard around cargo storage (legend 2-1), yard around steelstorage (legend 2-3), repair yard around maintenancestation (legend 3), internal road (legend 4-1), roadaround steel yard (legend 4-2), road from internal road tooutside road at sub-gate (legend 4-3), road from internalroad to outside road at main-gate (legend 4-4), vehiclewaiting road at the main gate (legend 4-5), road in

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province158

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

vehicle parking site (legend 4-6). All legends are shownin roads and yards plan drawing (TV-2013-ĐB-03).

- Total area of roads: 34,436.60 m2.- Total area of yards: 67,056.41 m2.

Roads and yards plan of package PK2 are shown in drawing No: TV-2014-ĐB-03.Technical solutionTop elevation of yard is +5.8m (CDL) at center of yard,slope from 0.39% to 0.7% from the center to the boundary,elevation of road boundary is +5.5m (CDL).Plan of elevation and slope of road and yard are shown indrawing No: TV-2014-ĐB-02There are 3 types of pavement for each region, as follows:

Type 1: at the general cargo yard, empty container yard, steel yard, cargoyard areas, pavement layer from top to bottom is follows:

Medium-grained asphaltic 8cm thickness 0x4cm graded aggregate, 60cm thickness Woven geotextile Reclamated subgrade, compacting factor K≥ 0.98. Type 2: at the heavy cargo yard around general storage areas, pavement

layer from top to bottom is follows:

Medium-grained asphaltic 8cm thickness 0x4cm graded aggregate treated cement (7%), 35cm

thickness 0x4cm graded aggregate, 40cm thickness Woven geotextile Reclamated subgrade, compacting factor K≥ 0.98. Type 4: at the internal road, road from internal road to outside road,

road around steel yard, vehicle waiting road, road in vehicle areas,pavement layer from top to bottom as follows:

Medium-grained asphaltic 8cm thickness 0x4cm graded aggregate, 45cm thickness

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province159

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Woven geotextile Reclamated subgrade, compacting factor K≥ 0.98

Structure of road, yard detail are shown in drawing No: TV-2014-ĐB-05Traffic signal by paint detail is shown in drawing No: TV-2014-ĐB-07The height of kerb is 80cm at the road adjacent berths barges (319m length).Detail of kerb is shown in drawing No: TV-2014-ĐB-09Infrastructure systemSurface drainage system of package PK2 includes: manhole,U-shape gutter, circular sewer, oil collecting pit, divideinto main lines as:B1-B7 line is 447m long, along the adjacent phase 2 roadand perpendicular to Thi Vai River revetment. Structure ofthis line is reinforcement concrete circular sewer withsome types of diameter as:

B1, B2, B3 lines: D1000 sewer, slope 0.15%, MH19,MH11, MH06 manholes to collect surface water. Atthese manholes, there are starter point to connect upphase 2.

B4, B5 lines: D1250 sewer, slope 0.15%, MH06, MH05,MH02 manholes to collect surface water. At the thesemanholes, there are starter point to connect up phase2.

B6, B7 lines: D1500 sewer, slope 0.15%, MH02, MH01,MG03 manholes to collect surface water and dischargeto outlet 03. At the these manholes, there arestarter point to connect up phase 2.

1F, 1G lines: D1000 sewer, slope 0,2%, MH04, MG02 manholesto collect surface water and discharge to outlet 02.1A, 2A, 2F, 3A lines (cross–tunnel): D800 sewer, connect Ushape gutter, manholes to B1-B7 line.1B, 1E, 2B, 2E, 3B, 3C, 3E lines loacate in the boundaryof road, slope 0.2%, connect to manhole to collect surfacewater from road and yard, structure of these lines is U

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province160

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

shape gutter with 30cm width, 70cm minimum depth, concreteslab is 15cm thickness.Lines (cross–tunnel under main arterial road) is 25m wide,at main gate and sub gate (1C, 1D, 2C, 2D, 3D lines) slope0.2%, collect surface water from main arterial road andconnecting road, U shape gutter, reinforcement concretestructure, 30cm width, minimum depth is 70cm, cover sheetis steel.Surface water drainage system plan is shown in drawing No: TV-2014-TN-01There are 12 manholes, reinforcement concrete structure , cover sheet is steel. Quantity and dimensions as:- Type 1: 03 holes, 2x2m length x width, 2m average deepth.- Type 2: 05 holes, 2x2m length x width, 1.9m average deepth.- Type 3: 02 holes, 2x2m length x width, 2.27m average deepth.- Type 4: 01 holes, 2x2.5m length x width, 2.8m average deepth.- Type 5: 01 hole, 2x2.5m length x width, 2.705m deepth.Manhole detail is shown in drawing No: TV-2014-TN-03, 04, 05, 06,07There are 02 oil collecting pits, with reinforcementconcrete structure and steel cover sheet, to ensure thatsurface water before escaping through Thi Vai River nooil, grease. The location of oil collecting pits is 15mfrom 2st outlet, 5m from 3rd outlet. Dimensions of oilcollecting pit are 2.5mx5.4m length x width, 3.76m averagedeepth.Oil collecting pit detail is shown in drawing No: TV-2014-TN-08.Revetment along Thi Vai RiverConstruction Scale

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province161

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

The length of revetment along Thi Vai River is 285m, 20mcandle cone at barge berth, 10m at phase 2 adjacentposition, so that the total length of revetment is 315m.The control points of revetment position are shown inTable 3-8 (Volume 4- Detailed design report).

Table 0-8. Control points coordination of revetment along Thi Vai River

No Name ofpoints

(Coordinate system VN2000,central meridian 107o45’,

projection 3o)X(m) Y(m)

1 KB1 1,171,288.511 420,882.9052 KB2 1,171,277.896 420,865.9543 KB3 1,171,519.439 420,714.6864 KB4 1,171,524.746 420,723.161

The revetment is divided into 5 segments, as follows: Segment 1: 80m, include 60m along the river and 20mcandle cone at barge berth; Segment 2: 60m long; Segment 3: 60 m long; Segment 4: 60m long; Segment 5: 55m including 45m along the river and 10mat phase 2 adjacent position.Revetment plan is shown drawing No: TV-2014-KB-03Technical solutions

Structural revetment is retaining wall by reinforcedconcrete M350 supported by PHC pile D500, combineswith slope embankment. The top elevation of revetmentis + 5.50m (Chart datum level).

The height of retaining wall is 2.5m, Vertical wall is30cm thick, bottom slab is 2m wide and 50cm thick,supported by 20m length PHC pile D500 with 1, 4, 5segment and 22m length PHC pile D500 with 2, 3segment. The pile spans are 2m longitudinally, 1.5m

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province162

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

horizontally. Outermost pile row (river side) isleaning (6:1), the rest of pile row is vertical.

Under the bottom slab is poor concrete M100 layer with10cm thick, next layer is rubber stone with 10 ÷ 30kg/piece weight, next layer is 2x4cm crushed stone,next layer is non-woven geotextile and the last issand Reclamation.

The slope revetment is rock fill cofferdam with 20 ÷30 kg /piece weight, slope m = 1.5, 50cm thickness.The top elevation of slope revetment is + 3.5m, theelevation of toe varies follw cut- off (varies from +1.0m to + 2.0m).

The cut-off elevation has 3 types : + 2.0m elevationwith 105m length includes the entire segment 1 and45m of segment 2; + 1.0m elevation with 140m lengthincludes 15m of segment 2, 3, 4 and 5m of segment 5;+ 1.5m elevation with 35m length of segment 5. Thewidth of cut-off is 2m. The slope of cut-off is m =1.5. Structure of cut-off is rubber with 50 ÷ 100kg /piece weight.

Behind of the bottom slab is a reinforced concreteM350 transitional slab with 20cm thickness, under thetransitional slab is 1x2cm crushed rock with 20cmthickness, next layer is 2x4cm crushed rock with 30 cmthickness, the last layer is rock fill cofferdam.

Above of transitional slab is non-woven geotextilelayer, compacted sand with k = 0.98 and structurallayer of pavement belongs to CS3 package.

To ensure the stability of the revetment duringoperation, must use two layers of high-strengthgeotextile 400kN/m, the length of high-strengthgeotextile is 46m at +4.00m elevation and 48m at+4.50m elevation

At the expansion joint, use tarpaulin to chork, woodgroup 7 above with 2cm thickness and 50cm width, andtwo layers of geotextile with 1m width.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province163

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Structural revetment detail is shown drawings No: from TV-2014-KB-06-1/5 to 4/5Due to the area of reclamation of package PK2 overlaping20m at boundary line between phase 1 – phase 2 so the 80min total length of slope of reclamation (river side) atsegment No.5 (to SN7’ point) is covered by rubble with50cm thickness, crushed stone with 25cm thicknes under,the last layer is geotextile to prevent loss of sand whenwater level fluctuate. Control points of slope reclamationprotection revetment are shown in Table 0-9. Table 0-9. Control points of slope reclamation protection embankment

No Name ofpoints

(Coordinate system VN2000,central meridian 107o45’,

projection 3o)X(m) Y(m)

1 KB4 1,171,524.746 420,723.1612 T1 1,171,541.690 420,712.5503 T2 1,171,546.998 420,721.0264 SN7’ 1,171,589.381 420,694.483

Plan of revetment is shown in drawing No: TV-2014-KB-16Structural detail revetment is shown in drawings No: TV-2014-KB-06-5/5Major excecution method and sequenceOrder and decisive construction method must adhere specification. Construction order of main works ensure thestability of the foundation of building onshore, as follows:

1) Reclamation work (the yard and embankment): fill upto +4.7m elevation (CDL).

2) Soil ImprovementSoft Soil Improvement: After finishthe reclamation work, consolidation and settlementas required, move pre-load material (down until+5.0m elevation). Construction time depends on theneed to use of client.

3) Construction of revetment structure.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province164

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

4) Surface water drainage system construction.5) Road and yard construction: after finishing

underground construction work (drainage system,water sypply system, electrical system...).

Order and construction method of each work as:ReclamationThe order construction as follows:1) Locating reclamation area2) Surface soil clearance3) Fill up to + 4.7m (CDL) in phase 1 area, layer by

layer fill, thickness of each layer is no more than 30cm. Use bulldozer, combined compaction, compating factor K ≥ 0.95. At area where higher +4.7m elevation, excavate and move to lower area.

4) reclamation roof Revetment (along the river) by 50cm thick stone.

5) Completion and Acceptance.Soil ImprovementOnly start when finishing reclamation work . Pre-load material (after moving down until +5.0m elevation) will bere-used for reclamation of phase 2. Working reclamation area KV4 of the yard must be conducted in parallel with the work of reclamation area KV4 of the embankment, Similarly KV7 of yard must be conducted in parallel with the work of reclamation area KV7 of the embankment.Water collection system (at location bordering betweenregions) will be re-used in next region.Order and construction method of each region yard area as:1) Fill up to +5.3m (CDL), layer by layer fill,

thickness of each layer no more than 30cm, compatingfactor K ≥ 0.95.

2) To Locate and pilot PVD drive3) To Locate and mass PVD drive after decision from

pilot PVD drive result.4) To Set SD and water collect system5) To Locate and set observation equipments

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province165

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

6) Fill up to +7.0m (CDL), layer by layer fill,thickness of each layer is no more than 30cm,compacting factor K ≥ 0.95.

7) After 100 days (since completion 1st surcharge up to+7.0m), when base is satisfactory, fill up to +8.5m (surcharge 2nd period).

8) After 100 days (since completion 2nd surcharge up to+8.5m), when base is satisfactory, to move pre-loadmaterial down until + 5.0m (CDL).

9) Compact (factor K ≥ 0.98)10) Completion and Acceptance.

Order and construction method of each region revetment area as:1) Fill up to +5.3m (CDL), layer by layer fill,

thickness of each layer no more than 30cm, compatingfactor K ≥ 0.95.

2) To Locate and pilot drive PVD3) To Locate and mass drive PVD after decision from

pilot PVD drive result.4) To Set SD and water collect system5) Lay high-strength geotextile 400kN/m at +5.3m

elevation6) To Locate and observation equipments installation 7) Fill up to +6.0m (CDL), layer by layer fill,

thickness of each layer is no more than 30cm,compacting factor K ≥ 0.95.

8) Lay high-strength geotextile 400kN / m at +6.0melevation

9) Fill up to +7.0m (CDL), layer by layer fill,thickness of each layer is no more than 30cm,compacting factor K ≥ 0.95.

10) After 100 days (since completion 1st surcharge up to+7.0m), when base is satisfactory, fill up to +8.5m (surcharge 2nd period).

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province166

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

11) After 100 days (since completion 2nd surcharge up to+8.5m), when base is satisfactory, to move pre-loadmaterial down until + 5.0m (CDL).

12) Completion and Acceptance.Construction of surface drainage system

Construction is started when Soil Improvement iscompleted. Order and construction method is as follow:1) Locate sewers, U shape gutter, manholes, oil

collecting pits2) U shape gutter construction3) D800, D1000, D1250, D1500 sewer, manhole, oil

collecting pits construction4) Outlet construction5) Completion and Acceptance .

Yard, road constructionThese works can be carried out at the same time with theinfrastructure construction. Order and construction methodas:1) Locating2) To Setup kerbs3) Woven geotextile4) 0x4cm graded aggregate construction, to compact

factor as required5) 0x4cm cement-bound graded aggregate (7%) construction

(with yard around maintenance storage), to compactfactor as required

6) Medium-grained asphaltic construction, to compactfactor as required

7) Painting sign on road and yard8) Completion and Acceptance .

Revetment construction

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province167

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

This work is conducted after the reclamation workcompleted. The order of execution is following:

1) Clearance 50cm thickness of rubber stone and capconcrete;

2) Construction of test pile to determine the actuallength of the pile;

3) Contruction of mass pile after pile length decisionfrom design consultation;

4) Construction of filter layer, cut-off, stone layerunder the bottom slab of retaining wall;

5) Cut the top op pile (with the excess length of piles)and construction of concrete of retaining wall;

6) Installation of transitional slab, then constructionof 2 layers of high-strength geotextile 400kN/mcombine with sand backfill behind the revetment inthe rarea from + 4.00m elevation to bottom ofstructural layer of pavement. Before laying thegeotextile at + 4.0m elevation, the surface of theexisting sand layer must be compacted with k≥0.98,from + 4.0m elevation above and from inner edge ofretaining wall to the end of geotextile sand must becompacted layer by layer with k≥0.98.

7) Completion and Acceptance .Construction of pile of revetment must be coordinated withthe construction of pile of access bridge, in areasadjacent especially, not allow finishing revetmentconstruction progresses construction of pile of accessbridge to ensure that piles not being displaced because ofthe influence of the pile construction.

3. Requirements on materials

Applicable standards

The used materials supplied by Bidder must comply withcurrent regulations and standards and must be approved by

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province168

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Thi Vai International Port Co.,Ltd before signing a formalcontract for major materials.

Requirements on materials

All kinds of supplies, materials, equipment andaccessories that Bidder recommented to provide forthis package should have a clear origin, legal, inaccordance with the requirements of the BiddingDocument and meet the minimum requirements accordingto current regulations and standards of Vietnam and /or international standards (Bidder should make a listof categories and codes, the origin of the supplies,materials, equipment, accessories).

The Bidder must present their bids, catalog (releasedby manufacturer or genuine representative in Vietnam)of goods and supplies, equipment and accessories thatBidder recommented to provide for the project.

The contractor must present the documents relating tothe source, origin (C / O for imported materials,equipment, accessories), C / Q, Quality InspectionCertificate for materials and equipment beforedelivering to construct.

All supplies and materials used for construction mustbe 100% brand new. Supplies and materials inwarehouse must remain intact parcels, stamps and codein the stamps should be clear, no peeling; theoriginate and brand of the category must matchrequirements in bids.

List of categories and requirements, technicalspecifications for major materials, goods andequipment, accessories was specified in the tablebelow:

Construction materials

Construction materials has been specified in theSpecification of the package. Here are some of therequirements of the major materials.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province169

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

a) Cement The used Cement has to meet the requirements in TCVN6260-2009 standard - Portland cement - Technical requirements.Each batch of cement must be accompanied by amanufacturer's certificate indicating that the cement wasinspected . Cement is transported to the site by car orwaterway transport covered to avoid affecting the weatherand be storaged in a well-ventilated warehouse, warehousefoundation has to higher at least 30cm from the ground.The cement bags shall be placed on the pads.b) Aggregates for concrete Comply with TCXD 7570 - 2006: Aggregates for concrete andmortar - Technical requirements and the SPEC of Package.c) WaterThe used Water in construction must be the clean water,with impurities, oil film and must comply with standardTCVN4506-2012: Mixing water for cement and mortar –Technical requirement.d) Steels

The used steels must strictly comply with the standardTCVN 1651:2008 Concrete reinforcement - Round bars anddeformed bar.e) Filling sand

Characteristics LabourityStandards Requirements

Type of material TCN 7572-2:06Concentration ofparticles smaller

than 0.14mm is under10%

Pummel Checking 22 TCN 333:06 ≥ 1.8 tons /m3

Magnitude Module ≥1.2f) Woven geotextile fabric

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province170

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Characteristics LabourityStandards Requirements

Tensile strength for thewarp ASTMD4595 ≥ 40kN

Tensile strength for theweft ASTM D4632 ≥ 40kN

Elongation for the warp ASTMD4595 15 ¸ 25%Elongation for the weft ASTM D4632 15 ¸ 25%Resistance to penetration CBR

BS 6906part 4 4.3kN

Grab tensile strength ASTMD4595 ≥ 1.1kNSize of the mesh O90 ASTMD4751 150 ¸ 400mSoefficient of of fabrics in 100mm presure

BS 6906part 3 1,4 ¸ 35x10-4 m/s

Weight ≥ 210 g/m2

Rolling width ASTMD5261 4m

Capability to ResistanceUV ASTM-D4355

50% after 500exposured hoursof or 03 months

outdoor.

g) Non-Geotextile fabric (used for the Reclamation)

Characteristics LabourityStandards Requirements

Tensile strength ASTM D 4595 ≥ 9 kN/mMaximum elongation (MD/CD) ASTM D 4595 40/65 %Resistance to penetration CBR DIN 54307 ≥ 1500 N

Size of the mesh O90EN ISO12956

120micron

Soefficient of fabrics in 100mm a water height BS 6906/3 ≥ 170 l/m2/s

h) Non-woven geotextile (used for revetment)

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province171

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Characteristics LabourityStandards Requirements

Tensile strength ASTM D 4595 ≥ 14 kN/mMaximum elongation (MD/CD) ASTM D 4595 45/75 %Resistance to penetration CBR DIN 54307 ≥ 2100 N

Size of the mesh O90EN ISO12956

100micron

Soefficient of fabrics in 100mm a water height

BS 6906/3125 m2/

s

i) Prefabricated vertical drain

Characteristics LabourityStandards Requirements

Size of the filter jacketASTM

D4751 –87

under 75m

Grab tensile strengthASTM

D4632 –91

More than1.6kN

Drainage capacity under pressure of 10kPa, gradient I= 0.5

ASTMD4716 –

87

qw= 80x10-6÷140x10-6m3/s

Drainage capacity under pressure of 400kPa, gradient I = 0.5

ASTMD4716 –

87

qw= 60x10-

6÷80x10-6m3/s

The absorbent coefficient of the filter jacket

ASTMD4491 ≥ 1x10-4 m/s

Maximum elongation of the absorbent sponge ASTM 4595 ≥ 20%

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province172

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Characteristics LabourityStandards Requirements

Corresponding tensile strength of elongation less than 10% because of the resistance of the ground during plug the absorbent sponge

ASTM 4595 ≥ 1kN/PVD

The width of absorbent sponge 100mm±5mmThe thickness of absorbent sponge 3mm

j) Horisontal absorbent sponge

Characteristics

LabourityStandards

Requirements

With ASTM D3774 20010 mmThickness ASTM D5199 81.5 mmDrainage capacity under pressure I=0.1; 100kN/m2 ASTMD4761 ≥ 2 m3/day

Compressive strength ASTMD1621 ≥ 250 kPa

Permeability ASTM D4491 ≥ 1.4x10-4

m/sMaximum elongation JIS K6911 10% ¸ 25%tensile strength in longitudinal

ASTM D4632-91 ≥ 0.28kN

k) Aggregate 0x4

Aggregate 0x4 has the physical and mechanical standardsAASHTO specified in SPEC. Here are required components ofgrain in aggregate 0x4:

Table 2-6. Requirement of grain in aggregate 0x4Nominalsize

Volume of grain smaller than sieve size(%weight)

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province173

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Size(mm) 50 mm 40 mm 20 mm 5 mm 2.5

mm0.4mm

0.074mm

40 to 0 100 95¸100

60¸90 30¸65 20¸50 10¸30 2¸10

l) Asphalt concrete

Asphalt concrete should be design accordant with TCXD8820:2011 standart Hot Asphalt concrete mix – Design byMarshall’s method and combine with TCXD 8819 : 2011standart Hot Asphalt concrete pavement – Construction andacceptance requirements. The specifications required for the Asphalt concrete course is as follows:

Characteristics Labouritystandards

Requirements

Number of tamping bar TCVN 8860-1:2011 75x2

Stability at 600C, 40 mins TCVN 8860-1:2011 ≥ 8.0 kN

Elasticity level  TCVN 8860-1:2011 2 ¸ 4 mm

Rest stability TCVN 8860-12:2011 ≥ 75%

Residual voids TCVN 8860-9:2011 3 ¸ 6 %

Aggregate voids (Residual voids at 4%)

TCVN 8860-10:2011 ≥ 15%

m) Centrifugal concrete culvert

Centrifugal concrete culverts need bearing 3 load levelsof 3-side compression method as follows:

Table. 2-7. Requirements of culvert’s load

Culvert’sdiameter

Pilot load (kN/m)Inbreak

Hardness LoadOperating

Load Damage Load

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province174

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

D800 47 75 94D1000 57 91 113D1500 82 132 164

n) Prestressed Reinforeced concrete pipe pile (PHC) D500-300

External diameter: 500mm;Internal diameter: 300mm;Thickness of pipe: 100mm;Concrete M800 stone 1x2;Cracking Moment: 15Tm;Damaging Moment: 35Tm.o) High strength geotextile

Characteristics Labouritystandards

Requirements

Tensile strength for the warp ASTM D4595 ≥ 400kNTensile strength for the weft ASTM D4595 ≥ 50kNElongation for the warp, weft ASTMD4595 12%

Drainage Capacity BS6906/3 ≥ 1x10-5

m/s

p) Other materials

Other materials need meeting the requirements of SPEC ofthe package.q) Techinical Requirements of Construction

In order to ensure the quality of the construction, theconstructors need to follow the requirements, the rules inTechnical Instructions of the project and the relatedprocedure, regulations, specified standards.Regulations of operation and maintenance

a) Operation load

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province175

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

The road behind revetment, within 20m from revetment toyard is operated with maximum load of 2T/m2. Maximumoperation load on yard is 4T/m2.b) Maintenance

Road and drainage system maintenance inlude frequentmaintenance, period repair và immediate repair. Frequentmaintenance is weekly conducted in order to observe andcheck construction condition, work out measerments toavoid damage for timely repairs to maintain constructionquality. That all is to ensure the safe and effeciency ofthe construction in exploitation period.Period repair is to repair road and drainage system damagein period prescribed in Table 0-3 along with defectliability in operation period in order to restore primarytechnical condition and enhance construction conditions ofexploiting. Period repair including small big repair andthere is at least one small-scale repair conducted betweentwo big-scale repairs.Table 0-8. Regulations of Road and Drainage Maintenance and Repair

Period

No. Types of roadpavement

The period forsmall-scale

repair (Years)

The period forbig-scale

repair (Years)1 Asphalt concrete 4 122 Cement concrete 8 24

3 Water drainage system 2 4

Revetment maintenance inludes frequent maintenance, periodrepair and immediate repair. Frequent maintenance isweekly conducted in order to observe and checkconstruction condition, work out measerments to avoiddamage for timely repairs to maintain constructionquality. That all is to ensure the safe and effeciency ofthe construction in operation period.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province176

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Period repair is to repair revetment damage in periodprescribed in Table 0-4 along with defect liability inoperation period in order to restore primary technicalcondition and enhance construction conditions ofoperating. Period repair including small big repair andthere is at least one small-scale repair conducted betweentwo big-scale repairs.

Table. 0-9. Maintenance and repair period of revetment

No. ItemSmall-scalerepair period

(years)

Big-scalerepair period

(years)1 Revetment 3 12

The major materials and equipments

The major materials, equipments and other accessories needto meet the requirements Tender documeent and DetailedDesign qualified by manufactures of Vietnamese standard orequivalence.In which, the “equivalence” means the supplies, materialsand equipments, etc sharing the same technicalcharacteristics or functions with mentioned materials andequipments.The contructors need to list of all materials andequipments provided by constructors to implement theproject in Table 10, chapter IV. In case the constructordoes not list the specific pofolio, the Bidding documentof the constructor will not be taken in consideration.

4. Requirements on human resource Considering volume, geographic conditions of the Site

and completion time, construction personnel isrequired to be qualified and personnel arrangement issuitable for construction methods so that quality,safety and schedule are ensured.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province177

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Site leader shall be experienced with more than 5years of working, meeting requirement for Site leaderGrade II according to the regulation of Decree12/2009/ND-CP, key officers shall meet therequirement on scale and conditions of the Works,technicians are qualified for items of works heundertakes. The Contractor shall provide identitydocument (including notarial copies of degrees andcertificates...), meeting requirement of BiddingDocument for these positions.

The number of labor shall be more than 50 people,among them they are basically trained according toForm No. 7A, Chapter IV

The Contractor shall provide with full information onpersonnel for the Works. The Employer shall have theright to inspect the correctness of each part or thewhole of this information.

5. Requirements on construction equipment The Contractor shall supply with machine, specialized

equipment and equipment related to the construction. The equipment shall conform to the notes of

construction methods in Bidding Document, ensuretechnical functions and required capacity, andreaches quality specification according to applicableregulation.

- The equipment as mentioned shall be hired or boughtby the Contractor and be identified with relevantdocument (vehicle registration or invoice; agreementon purchase and hire or other documents for theiridentification). The equipment shall meet requirementfor environment hygiene, fire prevention throughvehicle registration, insurance. The operator shallbe well-qualified as stipulated and submit drivinglicense, master’s certificate, motor vehicle drivinglicense along with equipment’s document. Theequipment of waterway traffic used for leveling and

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province178

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

backfilling shall be licensed by functional agencies.Bidding document shall not be considered if therelacks relevant documents as mentioned. Theinstrumentation and experiments shall have validownership documents and verified paper.

The Contractor shall collect the equipment aftercompleting or when they are not used. The following is the list of minimum constructionmachine to ensure the construction of the Works:

No Machine Quantity

Machine: Recalamation, Soil Improvement, Pavement, DrainageSystem, Revetment along Thi Vai River

1 Bulldozer 110Cv 6

2 Compactor 16T 07

3 Excavator 0.7- 1.6m3 05

4 Dump truck 10T 15

5 PVD installation machine with automatic control

04

6 Ni 030 01

7 Theo 020 01

8 Ni 004 01

9 Attack drill 54CV 01

10 Mixer 750l 02

11 Pump 2kW 02

12 Vibrating sieve 01

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province179

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

No Machine Quantity

13 Pump 200m3/h 02

14 Welder 23KW 03

15 Grinder 2.7Kw 01

16 Static Penetrometer Gouda or similar 01

17 Bending and cutting machine 5KW 03

18 Concrete mixer station 50m3/h 02

19 Vibrating compactor 25T 03

20 Vibratory plate compactor 1KW 02

21 Concrete compactor 1.5kw 07

22 Pile hammer 02

23 Centrifugal culvert casting shop 01

24 Asphalt concrete mixer station >=100m3/h

01

25 Asphalt concrete paver 01

26 Grader 01

27 Barge ≥ 600 T 10

28 Barge carrier 03

6. Requirements for labor safety and environment hygiene

Labor Safety: The Contractor shall comply withregulations on labor and equipment safety for eachitem of work during the construction.

There shall be trained officers in charge of laborsafety.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province180

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

The Contractor shall buy insurance for personnel andequipment, and shall be responsible for any accidentand damage on the Site due to no ensure of laborsafety.

Environment hygiene: During the construction, theContractor shall take measures to make sure thatentire Site is clean and material waste (remainingsoil, waste…) is treated and collected to the rightplace. Building material shall be covered when theyare transported by truck so as not to fall on theroad; otherwise this affects public traffic and thesurrounding area. The Contractor shall make anagreement with local agencies about the gatheringplace and shall bear total expense of transportationto the right place.

After completing the construction, the Contractorshall transport remaining building material andequipment out of the Site for the purpose ofacceptance.

7. Requirements on method and technique of construction Basing on the requirement in Tender Document, designdocument, specifications and regulations of Vietnam,relevant documents; the Contractor shall prepare methodsand techniques in his Bidding Document. Technical documentshall include the following contents: 1. Statement of the Contractor’s knowledge of the Works:scale and characteristics of the Works; source ofmaterial, electricity and water supplier. 2. Statement of principles of organization, technicalmanagement, construction quality of the Contractor.3. Statement of standards and specification ofconstruction 4. Methods of construction include:

Base for preparation of construction methods;

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province181

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Arrangement of management regime in the head officeand on the Site;

Unit of quality management in the head office; Unit of construction technical management, labor

safety and environment hygiene on the Site; Unit of technical supervision on the Site; Unit of material supply; Administrative unit and serving unit on the Site; Workers; Preparation of the Site; Protection of the Works; Electricity and lighting system for construction

period; Communication system for construction period.

5. Technical methods: the Contractor shall submitstatement and drawing.5.1. In the statement, the Contractor shall present fullbasic contents as the following:

Organization of the Site: Layout for temporary works, construction equipmentand storage place of material and waste.

Arrangement of gate, barrier and signs; Remedies for water and electricity supply, waterdrainage, traffic, communication during theconstruction.

General construction methods: Excavation of foundation; Items of concrete (include blinding concrete,assembly of formwork, steel bars, casting concrete…);

Completion; Installation of electrical water equipment ; Cleaning and transporting waste;

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province182

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Schedule of the Works and the chart for overallschedule

Remedy for improving the quality of the Works: listof equipment, inspection tool for quality. Procedureand remedy for inspection of material quality. Repairfor damage, warranty of the Works;

Applying the advance of technical science to theconstruction of the Works

Security, labor safety, fire prevention, environmenthygiene, traffic safety;

Assurance about safety and schedule in the rainyreason.

5.2. Drawing includes: Layout of Executing Site; Surveying method; Excavation and backfilling construction method Concrete casting method: (Include assembly of

formwork, steel bars, casting concrete maintenance); Drawing of completed works; Drawing of method of labor safety.

8. Technical SpecificationsSpecific technical requirements are presented in Volume 2:Specification of Bidding Document. The following are onlythe main requirements for major materials used for theconstruction and necessary notes on technical methods andmanagement. a. Requirements on materials All major materials such as steel bar, concrete, concreteaggregate, Horisontal absorbent sponge, Prefabricatedvertical drain, Geotextile, PHC D500-300 pile….are statedin Section 5- Volume 4: (Technical Report) and in Volume2: Specification of Bidding Document.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province183

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

b. Requirements of construction works1) Positioning

Referring to the Detailed design and standardlandmarks on the site handed over by Investor, theContractor shall determine and bear responsibilityfor reasonable data about positioning theconstruction scale of the project.

The contractor is responsible for safekeepingstandard landmarks on the construction site handedover by Investor.

2) Preparation for construction

The contractor is supposed to be well-prepared forconstruction site in accordance with the Detaileddesign and provisions signed with Investor aboutsite clearance, thus ensuring the smooth progress ofconstruction.

3) Land Reclamation

Because the surface of reclamtion area contains claymud, vegetation and peat coal, dirt band shoud beremoved after the area is leveled. After finishingsite clearing, the contractor must conduct aninvestigation into re-measurement of site level inorder to accurately calculate the volume of levelingsand for acceptance and liquidation.

Leveling materials are delivered to the constructionsite by waterway and by motorised vehicles, and thenreclamation is done by bulldozers. The contractorneeds to carry out the project in a certain way andembank dykes with soil sacks to protect two sides.

Filling period shall divide in layers with thicknessof(25 ¸ 40)cm. They need to be compacted and wateredto keep the humidity. Before being used for leveling,the filling sand needs to be put to the test first.Each backfilling layer requires a set of experimentsamples.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province184

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

The design elevation level for leveling +4.70m (Chartdatum) and foundation compactness after layercompated density must be guaranteed. Requiredcompated density value of 2 top layers (50cm thick)is K>=0.95; compated density value of below lowerslayers is K 0.90 and elastic modulus of the toplayer is E 400 kg/cm2. On the reclamtion area,there is a measuring point on each 1,000m2. Checkinglayer compated density is carried out alternately.

4) Pavement work

After removal up to +5.00m (Chart datum) in order tobuild internal road and yard, the Contractor needs toundertake leveling work and use sand to compensatefor the surface slop in accordance with the designslope before constructing the pavement.

In order to ensure the completion of constructionworks, the Contractor needs to consider referenceDesign documents about relevant facilities such as:Reclamation, Soil Improvements, Surface waterdrainage systems, Revetment, ... to arrangeconstruction layout, locating construction stops aswell as preparatory technical infrastructurepositions. This helps avoid the overlap ofconstruction.

5) Construction of Revetment

Construction of revetment foundation and accessbridge pile foundation must be carried out at thesame time, especially at bordering areas. The purposeof this is to make sure that pile foundations are notdisplaced under the influence of piling work.

The Contractor needs to consider reference Designdocuments about relevant facilities such as:Reclamation, Soil Improvements, Surface waterdrainage systems, Revetment, ... to arrangeconstruction layout, locating construction stops as

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province185

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

well as preparatory technical infrastructurepositions. This helps avoid the overlap ofconstruction.

6) Excavation work

Methods of excavation work are chosen by theContractor and approved by Investor.

Excavation work must be done in accordance with TCVN447- 1980. The contractor is responsible for ensuringsafety and stability of nearby construction sites aswell as security for workers and constructionequipment in the construction process.

Shape, size and height of foundation hole shall becompliant to the design and be inspected beforeexcavation. The bottom of foundation pits must beclean, flat and dry.

Foundation hole backfilling is only carried out afterconcrete is maintained in a required period of time.The compacted density of backfill must be inagreement with the design. The Contractor shall holdresponsibility for construction transition whenexcavation work is not accepted.

7) Formworks and working platform

Quality of formworks and working platform. Recommendations for the Contractor using steelformworks. If wooden formworks are used, they arenot supposed to be warfed, cracked and theirsurface in contact with concrete must be clean andflat.

Formworks and working platform must be secure,strong, stable, collapsible and convenient forsteel installation, concrete casting and tamping.Calculation of formwork design done by theContractor must comply with TCVN 4453- 1995.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province186

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

The Contractor is responsible for design andsupply as well as ensuring safety in formwork andworking platform for construction.

Formwork and working platform construction Formwork clean-up

When exposed to concrete, formworks must be kept in cleanplaces and brushed with a suitable kind of oil or anothersubstance approved by Investor. This oil coating or othersubstance is not allowed to get exposed to rebar or mixwith concrete.8) Steel Reinforcement

Steel cutting and bending The Contractor is responsible for re-checking sizespecifications in accordance with the designdrawing before steel cutting and bending are done.

Steel cutting and bending are done with mechanicalmethods unless there is another directive fromInvestor. Only when Investor’s approval ispresented in written forms, reinforcing bars arebended in hot temperatures. Hot bended steelarenot allowed to be dipped in cold water.

Bending or straightening steel is done within aradius of rebar less than 4 times greater than thediameter of flexible steel or 6 times greater thanthat of highly-intensified steels.

Making any changes to steel shall be approved byInvestor in written.

Steel connection In a cross-section, the joining connectionaccounts for less than 25% of the total area ofreinforced steel compared with round plainreinforcements and less than 50% compared withrebars. Dead soft steel wires with a diameter of1mm are recommended.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province187

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Steel welding Steel welding cannot be carried out unless it isindicated on the design drawing and that kind ofsteel is weldable.

Allowable tolerance is that the weld is notallowed to exceed the value in conformity withSection 4.3 TCVN 4453-95. At least 6 samples of100 connected welds will be experimented, with 3samples being bended and the other 3 being pulled.If necessary, Investor can request to haveadditional examination of steel welding with theexpense of the Contractor.

Steel delivery and installation On delivery of processed steel, the contractorshall ensure that steel products are not damagedor deformed.

Steel installation needs to meet the followingrequirements :

+ Previous installation parts do not negativelyaffect subsequent installation parts.

+ In order to avoid displacement during concretecasting, steel must be firmly fixed. It is vitalto come up with solutions to protect steel usedfor concrete structures against damages and otherdeformations

+ Using zinc in order to bind steel bars connection.The number of steel bar connections occupies atleast 50% of the number of joining points in analternate order. In all case, the angle of steelwire and reinforcing steels needs to be 100% tiedor welded.

Protective concrete layers Protective concrete layers are calculated from thesurface to the edges of steel bar inclusive of

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province188

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

joining points. The thickness of protectiveconcrete layers must abide by the design drawing.

9) Concrete

Design concrete aggregate The contractor shall be responsible for designingconcrete aggregate which is suitable for actualorigin of material and designed concrete strength.Designing concrete aggregate shall be performed bya laboratory which have legal entity status.Certificate of designed concrete aggregate shallbe submitted to Investor before carrying outconcrete work.

Because the work mostly uses cast insitu concrete,the Contractor shall prepare document ensuringquality of concrete aggregate such as : cement,sand, stone, gravel and addition (if any) andassign staff to follow mixing process. Concreteslump shall be measured prior to pouring concrete.Never add water into concrete once concrete slumpis measured.

Mix concrete If concrete structure used in small volume must bemixed in site, only concrete mixer is allowed to mixconcrete. Under no circumtances, is manually mixingconcrete allowed.

Transport concrete Transporting concrete from mixing place to pouringplace shall be ensured so that concrete mixture isnot be segregated and grout is not flowed out.

In case that addition is used to prolong settingtime, the Contractor shall submit testingcertificate of setting time based on weatherconditions, type of concrete and used addition toInvestor for considering.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province189

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Pour concrete Unless there is proper covering method, concreteshall not be poured under bad weather (rain,storm)

Positions of steel bars, formwork and thickness ofconcrete cover shall not be deviated duringpouring concrete. The Contractor shall supervisestatus of formwork, abutment and steelreinforcement to give timely remedies.

Concrete shall not be poured from height of 1.5min order to avoid segregation. If height of freefall is more than 1.5 m, inclined chute ordedicated equipment shall be used. For pile andwall, some holes in fromwork wall shall be made inorder to ensure concrete is poured continuouslywith free fall- heightt of less than 1.5 m.

Compact concrete Compacting concrete must be ensure so that aftercompacting, concrete is compact and there is noporous spot. Signs to identify the concretecompacted carefully are cement mortar emerging thesurface and no air bubble. When using the spudroller machine, its pitch does not exceed 1.5 ofits effective radius and it must be plugged deeplyinto the 10 cm previously poured concrete layer.

Under no circumstance, shall compactor contactwith steel reinforcement or formwork.

It is neceaasry to assign a qualified reinforcingworker for from first to last- following in orderto correct movement of the steel reinforcement.

Constructional joint Conduct constructional joint according to designdocument.

Prior to pouring concrete again, concrete surfacein structure joint shall be cleaned with water

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province190

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

injector and the largest exposed aggregate shallbe made free from roughness with wire-brush. Steelreinforcement surface in constructional jointshall be cleaned before concrete is poured.

Maintain concrete: Process of natural moist-aircuring for concrete shall be divided into 2 stages : The first maintenance : after forming concrete,the concrete surface shall be covered withhumidified material (sackcloth, canvas, nylon) toprevent concrete from losing water uder impact ofsunshine, wind and temperature. Covering will lastfor 2.5- 5 hours after concrete dried.

The next humidity mainteance : Shall be conductedright after the first one and last for 4-7 days(according to weather conditions). During thisstage, it is necessary to water in orer to keephumidity of structure surface. Times of wateringis based on necessary level of each area, howeverkeeping concrete surface wet is important. Fordeck roof, during this stage, cement in concretesurface shall be macerated.

All completed surfaces, corners and edges shall beprotected from damages caused by collisions. Never walk or load into concrete if its strength isinsufficient.

Remove formwork and working platform Formwork is removed only when concrete strength issufficient and the structure can bear its weightand other loads in the next construction stage.After removing formwork, the constractor shall notdemolish concrete, especcially corners and adgesand pre-burried parts.

Time for removing formwork of each concretestructure is based on specification or specifiedin design document.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province191

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

The Contractor must take full responsibilitiesfor all damages of concrete caused by impropermethod and removal time of formwork.

After removing formwork, the Contractor shallreport to Investor and Investor shall conductinspection. In case of repair requested byInvestor, the contractor shall carry out withoutdelay. The concrete structure shall not beaccepted in case the contractor solves problem onits own initiative prior to Investor’s inspection.

Check of water proof of reinforced concrete The outer surface of structure shall be revisedand in case of any sign of water penetrationdetected, the Contractor shall take fullresponsibility for repairing with solutionaccepted by Investor. The Contractor will pay forall expenses for inspection and remedy.

Check of concrete quality Concrete sampling

* A group of concrete compressive strength sampleincluding 3 samples with dimension of (150x150x150) mmshall be taken at the same time and in a same place. Incase of request from Investor, a group of samples fortesting water proof including 6 cylinder samples withdiameter and height of 150 mm shall be taken at the sametime and in a same place. * If necessary, Investor has right to conductunscheduled inspection for quality of concrete work. Thecontractor shall provide in sufficient amount of 12 castconcrete pattern sets to use in. * Samples shall be taken in exit end of mixer inpouring position. Samples shall be produced and testedaccording to TCVN Standard with condition that the sampleshall be compacted in the same way with concrete in site.Strength of the sample is determined by average strength

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province192

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

of all briquettes in sample group. The sample shall beconsider as satisfying requirement on strength if there isno sample whose strength is 15% less than average. Additional tests shall be conducted for followingcases: * Casted -in place sample does not satisfy requiredstrength when compacting * Number of samples is insufficient as required According to characteristic of the structure,Investor shall decide additional test method (takingsample in place by drilling, using echography or reboundhammer...) * When the concrete is rejected, it must be removedfrom work according to decision of Investor. If concretecan be remedied, the Contractor shall submit remedy methodto Investor and carry out remedies only when receivingapproval in writing of Investor. * The Contractor shall bear all expense arising fromremedy, test or removal due to unqualified concrete. Building mortar must be mixed by mixer and complywith designed aggregate. Mortar is mixed until it ishomogeneous in more than 2 minutes. In case mortar volumeis small, mixing can be conducted manually in more than 3minutes. Hardened mortar with insufficient strength mustnot be used. * During construction, if there is any crack ofconcrete detected the Contractor shall determine thecauses and find solution and notify to Investor. TheContractor shall actively mark up to keep track of thecrack.10) Paint work

Use paint with correct color and type according todesign document.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province193

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Painting construction shall comply with instructionsof the manufacturer enclosed with goods lot.

Surface of all structure to be painted shall becleaned before conducting.

Painting surface must be even, smooth, shining,evenly colored without condensed paint and covered toavoid being dirty or scratched until delivery.Measures to cover completed painting parts shall betaken in position where many people go pass or doother works to avoid dirty or stain or other matterssticking.

11) Install water drainage and water supply system

Installing pipe and water supply and drainageequipment according to design, meeting requirements ontechnique and urban aesthetic; pipe is installed insidethe wall. Prior to acceptance, even prior to tiling, it isnecessary to carry out pressure testing according to4159:1998 standard, testing of appearance and operation ofthe entire water supply and drainage system. Clean pipebefore putting into use. c. Requirements on warranty

 The Contractor is responsible for performing thewarranty of the Works after handover to the Investor.Contents of warranty include repair, maintenance andreplacement of damage or abnormal operations of the Worksnot caused by users.

Warranty period is 12 months from the Commencementdate to Handover date by Constructor to Investor. Warranty mechanism for solving damage ordeflection arising during use of the work within warrantyperiod: when detecting any deflection or damage, theInvestor shall notify the Contractor about them; theContractor shall carry out repairing the damage or

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province194

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

deflection after 02 days since receiving notification ofthe Investor. The Contractor shall bear all costs risingfrom repairing.As built drawing is required 15 days since the date ofcompletion.d. Other requirements

During construction, the Contractor shall comply withregulations on technique and labor safety and otherregulations on safety issued by the State.

Comply with Standard and Specification on qualitymanagement.

Construction supervision and acceptance. Comply with regulations on construction technique and

supervision (In Decree No. 12/2009/ND-CP dated12/02/2009 of the Government on Management ofinvestment projects on the construction of works,Decree No. 15/2013/ND-CP dated 06/02/2013 of theGovernment on management of quality on theconstruction of works).

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province195

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Chapter XDETAILED DESIGN DRAWINGS

Detailed Design and Cost estimation of PK2 packageOnshore work- Phase 1 : Reclamation, Soft improvement,Internal roads and yard, Water drainage system andRevetment along Thi Vai River is prepared by ConsultancyCompany Limited of University of Civil Engineering andverified by Joint Venture of VaPo - ViPo with items shownin Volume 3- Drawings, including following drawings:

1. Item: Part 1- Reclamation- Detailed Design Drawings: + Yard area : A3 Drawing - (TV-2014-SN-01 TV-2014-SN-06);+ Revetment area : A3 Drawing - (TV-2014-SNK-01 TV-2014-SN-03-13/13);

2. Item: Part 2- Soft improvement+ Yard area: A3 Drawing - (TV-2014-CTĐ-01 TV-2014-CTĐ-17);+ Revetment area: A3 Drawing - (TV-2014-CTĐK-01 TV-2014-CTĐK-09);

3. Item: Part 3- Internal roads and yard- Detailed Design Drawings: A3 Drawing - (TV-

2014-ĐB-01 TV-2014-ĐB-10). 4. Item: Part 4- Water drainage system - Detailed Design Drawings: A3 Drawing - (TV-2014-TN-01 TV-2014-TN-15).

5. Item: Part 5- Revetment along Thi Vai River- Detailed Design Drawings: A3 Drawing - (TV-2014-KB-01 TV-2014-KB-19).

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province196

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province197

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Part IIIREQUIREMENTS ON THE CONTRACT

Chapter XIGENERAL CONDITIONS OF CONTRACT

A. GENERALArticle 1: Interpretation of terms In this Contract, Terms below are understood as

follows:1. “Contract” is the agreement agreed by the Employer

and the Contractor in writing, signed by two parties,including appendix and attached documents.

2. “Contract price” is total amount that the Employeragrees with the Contractor in the Contract.

3. “The Employer” is an organization as mentioned inSCC.

4. “The Contractor” is the successful Bidder(independently or in association) shown in SCC.

5. “Sub-contractor” is the Contractor that signs anagreement with the main Contractor to implement one partof construction as expected in BIDS.

6. “The Engineer” is consulting bidder selected by theEmployer to work regularly and continuously at theconstruction site to supervise the execution of theconstruction and work items. Name of consulting bidder islisted in SCC.

7. "Commencement day " is the day that the Employerallows the Contractor to start executing the construction.

8. "Completion time” is a necessary period of time toexecute the construction starting from commencement dayuntil the construction is delivered and accepted.

9. “Date” is the calendar day, continuouslycalculated, including holidays and weekend.

10. “Warranty period” is the time that the Contractorshall be liable on repairing defects of the construction.Warranty period is started from the day that theconstruction is delivered and accepted.

11. "Site " is a place that the Employer hands over tothe Contractor to execute the construction as mentioned inSCC.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province198

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article 2. Applicable law and languages used inContract

Language of the Contract is Vietnamese, governing lawis Vietnamese law, unless otherwise stated in the SCC.

Article 3. Contract performance security 1. The Contractor shall issue contract performance

security with required contents in SCC to ensure theirliabilities fulfillment for contract performance.

2. The Contract performance security is made in favorof the Employer, as an indemnity for any loss caused bythe Contractor in case of failure to fulfill theircontractual obligations.

3. The Employer must return the contract performancesecurity to the Contractor in the duration stipulated inSCC.

Article 4. Contract form.Contract form is stipulated in SCC.Article 5. Sub-contractor1. The Contractor may sign agreements with Sub-

contractor listed in SCC to implement one part of workshown in BIDS. The employment of Sub-Contractors does notchange liabilities of the Contractor. The Contractor hasto be responsible to the Employer for quantity, quality,supply progress and other liabilities of work done by Sub-Contractors.

The replacement and amendment of Sub-Contractors otherthan those to be listed in the SCC shall be applied oncegetting approval of the Employer.

2. The value of work done by Sub-Contractors isstipulated in Section 1 of this Article and does notexceed the percentage of the Contract stipulated in SCC.

3. The Contractor is not allowed to employ the Sub-Contractors to implement other works besides tasks listedin BIDS.

4. Other requirements of Sub-Contractors arestipulated in SCC.

Article 6. Cooperation with other Contractors

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province199

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

The cooperation with other contractors to jointly usethe construction site shall be implemented as stated inSCC.

Article 7. The Contractor’s personnel1. The Contractor shall employ key personnel as named

in List of Key personnel as in DKCT to implement works inthis list or use other officers under the approval of theEmployer. The Employer shall only approve the replacementof officers in case that capacity and qualification ofreplacement officers are the same or higher than that ofofficers in the list.

2. If the Employer requires the Contractor to dismissone or more members in the Contractor’s personnel withexcusable reasons, the Contractor shall ensure that suchemployees must leave the site within 5 working dayswithout any relation with the contract performance.

Article 8. Compensation for damage1. The Contractor shall compensate and be responsible

for damages, losses and other relevant expenses to theEmployer and the Employer’s staff including:

a) Injury, disease, illness or death of any personhappen in or outside the construction process or resultfrom the Contractor’s drawings, execution, constructioncompletion, defect repair, unless such defects are theEmployer’s faults, Employer’s staff are negligence,intentional breach or contract violation;

b) Damage or loss of any property (not Works) happensin or outside the construction process or result from theContractor’s drawings, execution, construction completion,defect repair, unless such defects are the Employer’sfaults, Employer’s staff are negligence, intentionalbreach or contract violation.

2. The Employer shall compensate and bear cost to theContractor, Contractor’s personnel for damages, losses andother expenses related to injury, disease, illness ordeath caused by negligence, intentional breach or contractviolation of the Employer or the Employer’s staff.

Article 9. Risks of the Employer

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province200

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

From the commencement day to the expiration day of theContractor’s guarantee obligation, the Employer shall beresponsible for following risks:

1. Risks of injury, death of human, loss or damage ofassets (except Works, machines, materials and equipmentcaused by the mistake of Employer).

2. Risks of damages for Works, machines, material andequipment caused by the mistake of the Employer or forcemajeure.

Article 10. Risks of the Contractor1. Risks of the Contractor include:a) Risks are not the Employer’s risks including risk

of injury, death, loss or damage of assets (Works,machines, materials and equipment) from the commencementday to the expiration day of guarantee obligations.

b) Risks of damage or loss from the date of acceptanceand work delivery to the expiration day of guaranteeobligations of the Contractor due to:

- Any defect occurs on the date of completion;- Any event occurs before the completion date while

this event is not Employer’s risk;- Operations of the Contractor at the site after the

date of completion.2. The Employer shall be responsible for all the

Contractor’s risks as stated in Item 1 of this Article.Article 11. Limitation of liability 1. Neither party shall bear liability for the other

party due to loss in using the Works, loss of profits, orindirect loss related to this contract, except for otherprovisions of penalty for delayed contract performance,defect repair, payment due to contract termination andcompensation for damage.

2. The liability of the Contractor to the Employerunder this contract or related to this contract exceptregulations on the compensation as referred in Article 8,shall not exceed the total amount as in SCC.

3. It is not limited liability in terms of fraud,intentional defects or negligent acts of the violatingparty.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province201

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article 12. Force Majeure 1. In this Contract, force majeure is understood as

uncontrollable or unforeseeable event; for instance: war,riot, strike, fire, flood, diseases, isolation due toquarantine, embargo etc.

2. If force majeure occurs, the affected party has toinform in writing to the other party about the event andcauses of the events. Furthermore, such party sends theother a confirmation letter of force majeure issued by anAuthority Organization in the country where force majeureoccurs.

During the time construction is impossible due toforce majeure, the Contractor, under guidance of theEmployers, still continues to perform contractualobligations under actual circumstances and the Contractorshall seeks reasonable measures to implemented remainingparts. In this case, the Employer shall reimburse for theContractor necessary additional and reasonable expensesthat the Contractor has to be suffered from.

3. If one party fails to perform its obligations dueto force majeure, such party shall not compensate fordamage, or bear any penalty or contract termination.

In the case of disputes arising between parties due tothe occurence of force majeure, such disputes shall besettled by regulations as prescribed in Article 19.

Article 13. Insurance Requirements of insurance is stipulated in SCC.Article 14. Temporary worksRequirements of temporary work is stipulated in SCC.Article 15. Safety The Contractor shall be responsible for implementing

all safety measures at the construction site in accordancewith regulations of applicable law.

The Contractor shall comply with regulations of theState and other competent authorities for any mattersbeyond the scope of work and take full responsibilitiesbefore law for including but not limited to truck load,sanitation, safety and environment at the disposal site.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province202

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

The Contractor shall be responsable for applying licenseat the competent authority in accordance with theapplicable law (if any).

Article 16. Fossils at the site Any historical or valuable things discovered by

chance at the site shall be the property of the SocialistRepublic of Vietnam. The Contractor shall promptly makenotification to the Employer about this discovery tosettle according to regulations of applicable law.

In case of delay due to fossil discovery, theContractor shall handle, maintain and transport fossilsand notify to the Employer for approval.

Article 17. Site use rights The Employer shall assign the site use rights to

the Contractor on the date as mentioned in SCC. Article 18. The Engineer (Supervision Consultant) 1. The Engineer shall be responsible for implementing

works as specified in the contract. 2. The Engineer can provide guidance to the Contractor

on the construction and repair defect at any time. theContractor shall comply with guidance of the Engineer.

3. In the case that the Employer changes the Engineer,the Employer shall give notice in writing to theContractor.

Article 19. Dispute settlement 1. The Contractor and the Employer are responsible

for settling disputes arising between two parties throughnegotiation.

2. If the dispute is not settled by negotiation inthe duration as stipulated in SCC since the date ofdispute arising, any Parties can solve the dispute as inthe regulations defined in SCC.

B. SCHEDULE MANAGEMENT Article 20. Date of completion The Contractor can start executing the construction on

the date of commencement as in SCC and shall execute in

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province203

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

accordance with the Detailed schedule of constructionprogress submitted by the Contractor and approved by theEmployer. The Contractor shall complete all works on theexpected completion day as mentioned in SCC.

Article 21. Detailed construction schedule 1. During the period of time as stipulated in SCC, the

Contractor shall submit the Detailed construction scheduleto the Employer for consideration and approval withfollowing contents:

a) Execution order of works of the Contractor andexpected construction time for each main phase of theconstruction;

b) Process, inspection time and testing time asspecified in the contract;

c) Attached reports including: General report on themethods which the Contractor shall apply for theconstruction and major phases in construction execution;the number of staff, employees, workers and equipment ofthe Contractor shall be used at the site for these majorphases.

2. The Contractor shall comply with Detailedconstruction schedule after approved by the Employer.

3. The Contractor shall submit to the Employer forconsideration and approval of the Detailed constructionschedule which has been updated on the time no later thanthe required time as stipulated in SCC. If the Contractorfails to submit Detailed construction schedule to theEmployer which has been updated on the time as mentionedabove, the Employer shall retain amount of money asstipulated in SCC for next payment. This amount of moneyshall be paid at the next payment after Detailedconstruction schedule is submitted and approved.

4. The approval of Detailed construction schedule bythe Employer shall not replace obligations of theContractor. the Contractor can adjust the Detailedconstruction schedule and submit to the Employer at anytime.

Article 22. Changing the contract period

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province204

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

1. The Employer and the Contractor shallnegotiate about the extension for contract performance incases as follows:

a) The Employer fails to hand over the site use rightfor the Contractor at the time stipulated in Article 17;

b) The Employer disagrees to sub-contractors excludedin the list as referred in Item 1 Article 5 withoutexcusable reasons;

c) The Employer delays in providing the acceptancecertificate of the construction without reasonablereasons.

d) Other cases are described in SCC.2. The Employer can require the Contractor to suspend

the commencement or delay the progress of any activity ofthe construction.

3. In the case that it is necessary to shorten thetime of contract performance, The Employer shall negotiatewith the Contractor about relevant contents.

Article 23. Prediction of incidents The Employer should early predict to the

Contractor about incidents that can happen and its badlyimpacts on construction quality leading to the increase ofcontract price or the delay of the contract performance.The Employer can require the Contractor to predict theimpact of these incidents for contract price and contractperformance. The Employer shall cooperate with theContractor to provide appropriate remedy.

C. QUALITY MANAGEMENT Article 24. Inspection of quality of materials and

equipment 1. The Contractor shall ensure all materials and

equipment to be in accordance with technical requirements.2. The Contractor shall provide samples, test results

of materials, equipment as specified in SCC to check andmake a basis for the acceptance of work.

3. The Employer shall test materials and equipment atplaces of exploitation, production or at the constructionsite at any time.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province205

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

4. the Contractor must ensure the appropriatearrangement of staff and other necessary conditions forthe inspection of materials and equipment as mentionedabove.

Article 25. Defect correction 1. The Engineer shall be responsible for testing,

assessing the quality of works of the Contractor. In thecase of defects, the Engineer shall require the Contractorto find out causes for such defects and provide remedy.Such inspection and assessment shall not impact on theliability and obligations of the Contractor.

2. In the event that the Engineer requires theContractor to implement a test that is not specified inthe technical standards to check defect of any work. Ifthe test shows defect in any work, the Contractor shallpay costs for this test. If there is no defect, this costshall be included in the contract price and the Employershall pay for such cost.

Article 26. Construction guarantee 1. The time for construction guarantee shall be from

the date that the Employer signs the acceptancecertificate of the work item, the Works is completed to beput into operation and as specified in SCC. The time forconstruction guarantee shall be extended until all defectscaused by the Contractor are repaired.

2. Requirements on construction guarantee is describedin SCC.

3. During the guarantee period, the Employer shallgive notification to the Contractor about any damagerelated to the construction due to the Contractor’s fault.The Contractor, on its own expenses, shall be responsiblefor remedy for defects within the required time by theEmployer.

4. In the case that the Contractor fails to giveremedy in the required time, the Employer shall determinethe cost for remedying such defects and the Contractorshall have to pay for these costs.

D. COST MANAGEMENT

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province206

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article 27. Contract price listContract price list is an intergal part of this

Contract including work items which the Contractor shallperform and price unit of such work items. The work volumethat the Contractor must implement to complete the design,might be more or less than the work volume as described inContract price list (if any), but not change the contractprice.

Article 28. TaxRequirements on tax are described in SCC.Article 29. Adjustment of Contract priceThe adjustment of the Contract price is applied for

price unit applying work. Content, method and time ofadjustment, input data for adjustment are stipulated inSCC.

Article 30. Revision and amendment of the Contract1. The revision and amendment of the Contract can be

implemented in following cases:a) Supplementing necessary work items, materials,

equipment or services out of the work volume that must beimplemented according to the design and out of the scopeof work as stipulated in the contract;

b) Changes of design;2. The Employer and the Contractor may negotiate to

sign supplementary appendix for the Contract in case ofrevision and amendment of the Contract.

3. In the case of revision and amendment of theContract, the Contractor shall provide the work volumethat is supplemented to the Detailed constructionschedule.

Article 31. Payment in advance 1. The Employer shall pay in advance for the

Contractor according to contents as stipulated in SCC.2. The return of payment in advance shall be implemented

according to regulations as in SCC.Article 32. PaymentThe Employer shall pay for the Contractor according to

contents as stipulated in SCC.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province207

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article 33. Reward and punishment in case of contractviolation

1. For cases as stated in SCC, the Contractor shall berewarded with amount of money according to regulations asstated in SCC for the Contractor’s initiatives, for eachearly completion day of the construction compared toexpected completion day. The total reward shall not exceedthe total amount as stipulated in SCC.

2. The Contractor shall be punished according toregulations as stipulated in SCC for each delayed daycompared to the expected completion day or extension daysof expected completion day. The total fines shall notexceed the total money as stipulated in SCC. The Employercan deduct the fines from due payments of the Contractor.

3. In case of failure to make payment, the Employershall be incurred a penalti as specified in SCC.

E. CONTRACT COMPLETION AND TERMINATIONArticle 34. Acceptance The Employer shall accept in accordance with current

regulations of the construction law. The acceptancecertificate shall be signed by the Employer’srepresentative, the Engineer and the Contractor.

The Employer is entitled to access the site and theconstruction within the number of days as stipulated inSCC since the Contractor is issued the acceptancecertificate of construction.

Article 35. As-built drawing, operating instructions 1. the Contractor shall complete and submit to the

Employer for as-built drawing in accordance with currentregulations of applicable law, operating instructions ofinstalled equipment (if any) on the time specified in SCC.

2. If the Contractor fails to submit as-built drawingor operating instructions on the date specified in SCC orthese documents are not approved by the Employer, theEmployer shall retain the amount as specified in SCC fromthe due payments for the Contractor.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province208

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article 36. Contract termination 1. The Employer or the Contractor can terminate the

Contract if one of two parties violates the contract asfollows:

a) The Contractor stops to execute the construction inthe period of time as stipulated in SCC while thiscessation is not mentioned in the Detailed constructionschedule and not approved by the Employer;

b) The Employer requires the Contractor to prolong theconstruction progress exceeding the time as stipulated inSCC;

c) The Contractor goes bankruptcy or winds up;d) Other actions shown in SCC.2. In the case of contract termination, the Contractor

shall promptly stop every work, keep safe condition forthe site and leave the site at the require of theEmployer.

Article 37. Payment for contract termination 1. If the contract is terminated due to the

Contractor’s faults as referred in Article 36, theEmployer shall establish the certificate of value ofcompleted works and purchased materials minus the advancethat the Contractor has received. If the advance is higherthan the value of completed works and purchased materials,the Contractor shall be responsible for paying to Employerfor this difference amount. Otherwise, the Employer shallbe responsible for paying this difference amount to theContractor.

2. If the contract is terminated due to the Employer’sfaults or force majeure as referred in Article 36, theEmployer shall establish the certificate of value ofcompleted works, purchased materials and reasonableexpenses for removing equipment, personnel repatriationthat the Employer has hired for the construction and theContractor’s expenses for construction protection minusthe advance payment that the Contractor has received. the

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province209

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Employer shall be responsible for paying this differenceamount to the Contractor.

3. All materials, equipment, machines and temporaryworks at the site shall be deemed as the Employer’s assetsif the contract is terminated due to the Contractor’sfaults.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province210

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Chapter XIISPECIFIC CONDITIONS OF CONTRACT

Article

Clause

Content

1 3 Employer: Thi Vai International Port Co., LtdRepresentative of the Employer: ProjectManagement Unit (PMU)

6 Engineer:

12 Site: Phu My Town, Tan Bar District, Ba Ria -Vung Tau Province

2 Language used in the Contract: VietnameseGoverning law: Law of Vietnam

3 1 Requirements on contract performancesecurity:- Time-limit for submission of contractperformance security: Within 7 days sincethe signing date of the contract.- Forms of contract performance security:Issued by a Bank, financial institute legallyoperating in Vietnam or a Bank, financialinstitute in foreign countries (approved bythe Employer) in accordance with the Formspecified in this Bidding Document. Ifcontract performance security is submitted bya bank or financial institute in foreigncountries, this contract performance securityshall be issued through a branch in Vietnamor certified by a bank of Vietnam which hasrelationship with the issuing bank before

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province211

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article

Clause

Content

submitting to the Employer.- Value of the contract performance security:10% of contract value.- Validity of contract performance security:The contract performance security shall comeinto full force and effect from the Effectivedate to the date that the Works is acceptedand delivered, and the Employer shifts toguarantee obligations as regulated. In casethe contract term is renewed as specified inArticle 7, the Contractor shall renew hisContract Performance Security accordinglyuntill the Works is accepted and delivered,and the Employer shifts to guaranteeobligations as regulated.

3 Term of repayment for contract performancesecurity: No later than 30 days since thedate that the Works is accepted anddelivered, and the Employer shifts toguarantee obligations as regulated.

4 Contract form: Fixed unit-price contract.Payment principles of Fixed unit-pricecontract are as follows:

a) Payment for the Fixed unit-pricecontract is carried on the basis of fixedprice for works multiplied by the actualvolume of completed works which is acceptedaccordingly. The fixed price unit shall notbe changed during the contract performance;

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province212

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article

Clause

Content

b) If the accepted work volume is less ormore than (in consistent with the design) thevolume in signed contract, payment is carriedout according to the actual accepted volume. In case that there is eligibleadditional work aroused out of scope of theBidding Document, the Employer shallnegotiate with the Contractor to calculateadditional works and report to responsiblepeople for review and decision. Unlessotherwise, contents of such additional worksshall form a new bid package and a newcontractor will be selected.The payment of additional volume (out of thescope of Contract) without price unit setforth in the Contract, the two parties shallcomply with additional contract agreementsas specified and in accordance with relevantregulations of the law.

5 1 List of Sub-contractors:__________ (Insert thelist of subcontractors in accordance with the list ofsubcontractors as stated in Bids).

2 Work value implemented by the sub-contractordoes not exceed: 30% of the contract value(Subject of nature, scale of the bid package to insert percent,accordingly).

4 Other requirements of subcontractors orsuppliers of materials and equipment:Subcontractors or suppliers of materials and

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province213

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article

Clause

Content

equipment (if any) shall be approved by theEmployer or representative of the Employer.

6 Cooperation with other Contractors: Duringthe construction, the Employer is liable tocooperate with other contractors at the Sitewithin the scope of works and other relevantworks. The Contractor shall compensate forall or any incurred damages to the Employeror the third party in case of interferes orbad coordination with contractors of otherpackaged at the Site.

7 1 List of Key personnel: In accordance with theList of Key personnel as stipulated in Bids.

11 2 Maximum liability:__________________(The Maximum liability shall not exceed the contract price xk, in which, k is a coefficient and often defined as 1).

13 Insurance requirements: The Parties shallpurchase types of insurances according toregulations of the State. The Contractorshall buy the insurance for materials,construction equipment, plant and insurancefor employees and civil liability insurancefor the third party for Contractor’s risksetc.Within 10 days since the Effective date, theContractor shall submit to the Employer typesof insurance as mentioned above.No change of terms of insurance is permittedwithout the consent of the Employer.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province214

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article

Clause

Content

14 Requirements of temporary works: Theconstruction of temporary works shall beagreed and approved by the Employer. TheContractor shall submit designs and otherspecifications used for such temporary worksto the Employer for approval. The Employer’sapproval shall not change any responsibilityof the Contractor in terms of design of thetemporary works. Construction costs oftemporary works shall not be paid if they arenot accepted and approved by the Employer.

17 Date of site delivery (construction site): ___(insert the date of site delivery)

19 2 Any dispute aroused during the course of thisContract shall be firstly handled amicably byParties within 45 days. Unless otherwise,such disputes shall be lodged and settled byEconomic Court of Ba Ria - Vung Tay Provincein accordance with applicable laws. The awardof the Court shall be final and bind bothParties. The losing party shall bear allrelevant court fees.

20 Commencement date: According to requirementof the Employer.Expected date of completion:_____________(insert theexpected date of completion, in accordance with theconstruction schedule specified in Bids).

21 1 The time-limit to submit Detailedconstruction schedule: Within 05 days since

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province215

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article

Clause

Content

the effective date, the Contractor shallsubmit to the Employer a Detailedconstruction schedule.

3 The time-limit to update Detailedconstruction schedule: 30 days/time.Retention amount: 5% (five percent) value ofthe payment.

22 1 Other cases:__________________

24 2 Materials and equipment: The Contractor shallprovide samples and testing results of allequipment, materials at the request of theEmployer.

26 1 The time for constructionguarantee:_____________(stated clearly in accordance withrequirements in Bidding Document)

2 Requirements of work warranty: According toregulations of Construction law.

28 Requirements of tax: According to otherrequirements of the State. The contract priceincludes kinds of tax, fees, duty etc.

29 Modification of contract:- For additional works arising out of thescope of bidding document, resulting in thecontract price exceeds the award unit rate,this new price unit shall be reviewed andapproved by responsible people.- Modification of the contract is onlyapplied during the contract performance and

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province216

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article

Clause

Content

approved by responsible people. The contractprice after modification shall not exceed theestimate, total cost estimate or packageprice as specified in the approved biddingplan, unless otherwise clearly approved byresponsible people.- In case that there is eligible additionalwork aroused out of scope of the BiddingDocument, the Employer shall negotiate withthe Contractor to calculate additional worksand report to responsible people for reviewand decision. Unless otherwise, contents ofsuch additional works shall form a new bidpackage and a new contractor will beselected.

31 1 Employer shall advance to Contractor amountequal 20% contract value after effective dateof the contract and Contractor submit validadvance payment document, including:

1. Signed and valid Contract (Copy) ;2. Contract performance security

(Original);3. Written request for advance payment

(Original) and advance explanations;4. Contract advance security is valued at

20% of contract value through a legalbank in Vietnam (original). Thiscontract advance security shall be validfrom the date that Employer reclaims

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province217

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article

Clause

Content

total advance payment; 5. Detailed construction progress of

package and progress of mobilizingequipments and human resource;

6. Commitment of Bank in the use of advancepayment for proper purpose ofContractor.

These above documents shall not be validwithout agreement of Employer.

2 Advance refund value is 30% value of eachpayment installment and the first payment.Advance value is reclaimed since total amountof payment installments, less applicabledeductions as requirements of contract, is80% contract value.

32 Employer make payment to Contractor asfollows:

1. Payment form: By transfer;2. Currency of payment: Vietnam dong3. Payment method: Fixed price unit

multiply actual completed and acceptedwork volume;

4. Payment schedule: progress payment of 01(one) month. The last day of each month,Employer and Contractor shall conductacceptance of work items accepted byEngineer to determine the amount ofpayment for that month;

5. Payment period: within 30 days for

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province218

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article

Clause

Content

payment installments, except for thefinal payment installment is 60 dayssince the Contractor provides validpayment documents;

6. Payment value for each paymentinstallment as follows:

- Pay up ...% value of completedconstruction volume accepted in paymentfor work items;

- Pay up ...% value of completedconstruction volume accepted in paymentfor work items such as: (1) Reclamation;(2) soft ground improvement; (3) Basinroot ect…;

- Pay up to 90% of the actual settlementafter certifications of completed worksaccording to contract content issued byEmployer or representative of Employerand taking over the Works to put thesame into service;

- The A shall retain 10% of the settlementvalue (A) + (B) of which 5% settlementvalue approved by holding agency ofParty A and 5% for work warranty. Incase if Party B has guarantee letter oflegal bank in Vietnam with equivalentamount to 5% of the settlement value,Party A shall pay to Party B 95% of thesettlement value (A) + (B) .

- Party A shall pay to Party B 5% actualsettlement value after Package PK2 isapproved by Members' Council of Thi VaiGeneral Port company limited;

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province219

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article

Clause

Content

- Party A shall pay to Party B 5% of theactual settlement value after Party Aaccepts guarantee letter of legal bankin Vietnam with amount equal to 5% ofretained settlement value for warranty.

1. Payment document: is made into 06originals for each payment installment.Contractor shall be responsible forexplanation and clarification of paymentdocuments in direct or in written within03 days at the request of the Employer.Payment documents include the followingdocuments: For monthly payment or payment in middleof month (if any):

- Payment requests of Contractor shallpresent following contents: value ofcompleted volumes under Contract, valueof works arising (if any), deduction ofadvance payment, deduction amount ofpaid work items for payment of workitems and value of payment request inphases after deducting these amounts;

- Acceptance certificate of the work item(original) ;

- Agreed Minutes for works arising out ofContract and price unit corresponding tothe work certified by the Employer andthe Contractor (if any), (Original);

- Acceptance minutes of actual completedvolume of payment installment certifiedby the Employer and the Contractor (ifany), (Original);

- Hand-over minutes, As-built documents of

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province220

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article

Clause

Content

completed work items in paymentinstallment (Original) ;

- The certificate of the actual completedvolume under the installment contract(which represents the value of thecorresponding contract) certified byRepresentative of Employer, Consultingunit and Contractors (original);

- The certificate of actual completedvolume of work arising out of contractof the payment installment (if any)certified by the representativeEmployer, Consulting unit andContractors (original);

- The certificate of payment value(original) demonstrated the followingvalues: Value volume of actual completedwork under the contract, the valuevolume of arising works (if any),deduction value, payment value forpayment installment, retained amount;

- Financial invoice for paymentinstallment. For settlement:

- Final Statement (original);- Acceptance minutes for completed volume

within the scope of contract, minutes ofhand-over and put into use (original);

- Certificate of completion work issued bythe Employer to the Contractor (copy);

- Agreed minutes for the work arising outof the contract and price unitcorresponding to that work certified bythe Employer and the Contractor (if

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province221

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article

Clause

Content

any), (copy);- The certificate of the actual completed

volume under the installment contract(which represents the value of thecorresponding contract) certified byRepresentative of Employer, Consultingunit and Contractors (original);

- The certificate of actual completedvolume of work arising out of contractof the payment installment (if any)certified by the representativeEmployer, Consulting unit andContractors (original);

- The certificate of settlement value forconstruction contract (original) inwhich describe the paid value andretaining one certified by Employer andContractor;

- Certificate of Handover of as-builtdocument (Copy);

- Financial invoice for paymentinstallment;

- Warranty Bond (if any, original)equivalent to a value of 5% of thecontract value, having effect in 12months after the work was accepted andput into use;

- Contract liquidation minute;Other documents and document requirements asrequirements of Employer.

33 1 Reward:______________(for early completion of the work,contractor’s initiatives…In case of not applicable reward,please specify): ______________

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province222

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article

Clause

Content

Maximum bonus: ___________(total maximum bonus, if any)

2 Penalty: - If Contractor violates due to progress

delay in according to Article 20 (except forforce majeure), the Contractor shall be finedwith amount of ...% of the contract value dueto progress delay for... days, the totalvalue of the fine shall not exceed 12% ofvalue of delayed part;- If the Contractor delays completion of

work items more than 30 (thirty) days withoutproper measures approved by the Employerresulting serious damage to the Employer, theEmployer is entitled to unilaterallyterminate the contract and recovers amountequal to the value of serious damage(determined by the Employer, but not exceedthe value of the contract performancesecurity).

3 Comply with law of construction.

4 Other requirements for contract violations:Where Contractor violates the obligation toensure the quality of the work under thecontract, the contractor shall bear all costsof repairs or replacement as request ofEmployer. Contractor shall be subject topenalties as specified in Clause 2 of thisArticle if construction progress is delayedrepair remedy or replacement.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province223

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Article

Clause

Content

34 The time to accept the construction: within… day after the date of acceptance and putinto operation.

35 1 Time to submit as-built drawing: within …day after the date of acceptance and put intooperation.

2 Retained amount: …% settlement value

36 1 - The Contractor stops to execute theconstruction: … day.

- he Employer requires the Contractor toprolong the construction progressexceeding: … day. Excluding technicalproblems and force ;

Other activities: - Employer will be entitled to terminate

the contract if the contractor stopsconstruction or expressly show itsintention to stop performing obligationsunder the Contract;, or

- Subcontractor shall implement workexceeding 30% of contract value or transferContract without permission of Employer ;

- Contractor will be entitled to terminatethe contract if the Employer goes bankrupt orinsolvency, force to close the business, theasset of which being managed or Employerdelays to make payment to Contractorexceeding … days.

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province224

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province225

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Chapter XIIICONTRACT FORM

Form 18CONTRACT

, date ..... month ... year ....ContractNo.:...............................................................................................................Bidding package: (Insert name of bidding package)............................................................ Under the project: (Inset name of project)......…………..…………………………….….. - Pursuant to__________ Civil Law No. 33/2005/QH11 dated14 June 2005 of the National Assembly;Pursuant to __________(Bidding Law No. 43/2013/QH13 of theNational Assembly on November 26, 2013];Pursuant to __________(Construction Law No. 16/2003/QH11 of the NationalAssembly on November 26, 2013Pursuant to_____________[Decree No. 63/2014/NĐ-CP of the Govermenton June 26, 2014 on guiding the implementation of Bidding Law and selectingBidders in accordance with Law on Construction];- Pursuant to Decision No. ………. dated …. month …. year …..of _________ dated …month …. year….on approving the biddingresult for bidding package …and the Letter of Award No. ….dated …. month …. year …. of the Bid Solicitor;- Pursuant to the minute of negotiation and completion ofthe contract signed by the Bid Solicitor and the winningBidder dated ….month ….. year …..;We, representatives of the signing parties, include:

Employer (hereinafter referred to as Party A)Employer’s name [insert name of Investor]:_________________Address:____________________________________________Telephone No.:______________________________________Fax No.::___________________________________________E-mail:_____________________________________________Account No.:________________________________________Tax code:___________________________________________

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province226

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Representative: Mr./Mrs.____________________________Position:___________________________________________Power of Attorney for signing the contract No.

____dated_______(in case the person is granted authorisation).Bidder (hereinafter referred to as Party B)Bidder’s name [insert name of the winning Bidder]:___________Address:____________________________________________Telephone No.:______________________________________Fax No.:____________________________________________E-mail:_____________________________________________Account No.:________________________________________Tax code:___________________________________________Representative: Mr./Mrs.____________________________Position:___________________________________________Power of Attorney for signing the contract No.

____dated_______(in case the person is granted authorisation).Two Parties agree to enter into the contract of commodity

supply with following contents:Article 1. Objects of the contract.

Object on the contract is office leasing services asspecified in Appendix 1 attached.Article 2. Parts of the Contract

Parts of contract and legal priority as follows:1. Written contract (Attached to List of services and

Appendices);2. Minutes of contract negotiation and completion;3. Decision on the approval of the bidding result;4. Specific conditions of the contract;5. General conditions of the Contract;6. Bids and clarification of Bids of the winning Bidder (if

any);7. Bidding Document and additional Bidding Document (if

any);8. Other enclosed documents (if any). Article 3. Obligations of Bidder

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province227

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

The Bidder commits to construct and fulfill itsliability and obligations in accordance with te generaland specific provisions of the contract.

Article 4. Obligations of EmployerThe Employer commits to paying for the contract value

stated in Article 5 of this contract to Party B in thepayment method stipulated in the specific provisions ofthe contract, as well as fulfull its liability andobligations in accordance with GCC and SCC.

Article 5. Contract value and the payment methods 1. Contract value: _______________ [Insert the value in words, in

numbers and the currency of the contract.].2. Payment method: The payment is made in accordance

with the method stated in (Article. ... SCC) Article 6. Contract form:

____________________________[Insert forms of contract in compliance with the Item ... SCC] Article 7. Contract term: _______________[Insert time for contract implementation in accordance with term 2 Item

1 in the BDS, Bids and the result of negotiation and completion of the contractbetween two parties].

Article 8. Validity of Contract 1. The contract takes effect since _____ [Insert the valid

date of the contract in accordance with the provisions stated in Item 7 Article 1of SCCT].

2. The contract shall be deemed as invalid after thetwo parties liquidatte the contract in accordance with lawprovisions.

The contract is made in ____ copies, investorkeeps ____ copies, Bidder keeps ____ copies, Thesecopies are equal legal value.

LEGAL REPRESENTATIVE OF BIDDER

LEGAL REPRESENTATIVE OF INVESTOR

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province228

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

[Insert name, position,signature and seal]

[Insert name, position,signature and seal]

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province229

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Form 19

CONTRACT PERFORMANCE SECURITY________, date _______month_______year_______

To: ____________________ [Name of the Employer](Hereafter referred to the Employer)

At the proposal of [insert name of the Contractor] (hereinafterreferred to as the Contractor) is the winning Bidder for thebidding package [insert name of the bidding package];

In reference to the provisions in the bidding document,the Contractor has to submit to the Employer a bank guaranteewith a specific amount of money to ensure their liability andobligations in the contract performance;

We, [name of the bank] in [insert name of country and territory] havingregistered headquarter at [insert address of the bank] (hereinafterreferred to as “the Bank”) agree unconditionally andirrevocably, to guarantee the contract performance with theamount of [insert value in words, in numbers and type of the currency in use]. Wecommit to make unconditional, irrevocable payment to theEmployer any amount in our ability [insert amount of guarantee] asstated above when a written notification of the Employer onthe contract violation of the Contractor within the valid termof the guarantee of the contract performance security.

This security takes effect since the date of issuanceuntil the end of date ____.

Legal representative of Bank[Insert name, position,signature and seal]

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province230

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

Form 20

ADVANCE PAYMENT SECURITY________, date _______month_______year_______

To: ____________________ [Name of the Employer](Hereafter referred to the Employer)

[Name and number of the contract]

In accordance with the advance payment provision included

in the specific conditions of the contract, __________ [insert

name and address of the Contractor] (hereafter referred to as the

Contractor), shall present to the Employer a bank security

to guarantee that the Contractor will use the advance payment

for proper purpose of________ [in numbers, words and used currency] for

contract performance.

We, _________ [name of the bank] in __________ [insert name of

country and territory] having registered headquarter at ________

[insert address of the bank] (hereinafter referred to as “the Bank”),

as requested by the Employer, agree unconditionallyy and

irrevocably, without any request for advance consideration

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province231

Bidding Documents of Package PK2: Construction of Onshore works – Phase 1

from the Contractor, to make payment to the Employer an amount

of money not exceeding in __________ [in numbers, words and used

currency] as required by the Employer.

We further agree that no change or addition to or other

modification of terms to be performed thereunder or of any of

Contract documents which may be made between the Contractor

and the Employer, shall in no way release us from liability

under this security.

The value of this security will be gradually reduced

corresponding with the advance payment reclaimed by the

Employer after each payment period referring to Article ......

of this Contract once the Contractor presents document

confirmed by the Employer of the reclaimed money after each

payment period.

The security shall be in full effect since the date of

advance payment to the date ______ (3) or until the Employer

reclaims total advance payment, whichever is later.

Legal representative of Bank

[Insert name, position, signature and seal

Thi Vai Port Construction Investment Project - Phu My Town, Tan Thanh District, Ba Ria-Vung Tau Province232