Annual Report 2015 - Biodiversity Management Bureau
-
Upload
khangminh22 -
Category
Documents
-
view
4 -
download
0
Transcript of Annual Report 2015 - Biodiversity Management Bureau
Biodiversity Management Bureau | Annual Report 2015
Department of Environment and Natural Resources
BIODIVERSITY MANAGEMENT BUREAU
TABLE OF CONTENTS
List of Figures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iii
List of Acronyms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iv
Volume I: Narrative Report . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
I. Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
II. Accomplishments
1. Policies formulated and approved . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2. Major Programs and Projects Implemented . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
A. Establishing and Managing Protected Areas . . . . . . . . . . . . . . . . . . . . . . . 5
B. Monitoring of Existing Threatened Species Conservation and
Management Programs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
a. Pawikan Conservation Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
b. Philippine Raptor Conservation Program . . . . . . . . . . . . . . . . . . . . . . . 8
c. Palawan Wildlife Rescue and Conservation Center . . . . . . . . . . . . . . . 8
d. National Wildlife Rescue and Rehabilitation Center . . . . . . . . . . . . . . 8
e. Wildlife Regulation and Enforcement . . . . . . . . . . . . . . . . . . . . . . . . . . 8
C. Promoting and Institutionalizing Ecotourism . . . . . . . . . . . . . . . . . . . . . . . 9
D. Managing Coastal Biodiversity and Wetlands Ecosystems . . . . . . . . . . . . . 9
a. Coastal Management and Conservation Program . . . . . . . . . . . . . . . . 9
b. Wetland Management and Conservation Program . . . . . . . . . . . . . . . 11
E. Conserving Caves and Cave Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
F. Information and Education on Biodiversity and Nature Conservation . . . 12
G. Managing Ninoy Aquino Parks and Wildlife Center . . . . . . . . . . . . . . . . . . 13
3. Foreign-Assisted and Special Projects Implemented
A. NBSAP-BIOFIN . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
B. BPP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
C. SGP5 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
D. NewCAPP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
E. PAME . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
F. IAS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
G. MKBA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
H. SSME . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
4. Gender and Development (GAD) Mainstreaming . . . . . . . . . . . . . . . . . . . . . . . 15
5. Other significant accomplishments/milestones/breakthroughs . . . . . . . . . . . 16
Volume II: Tables and Annexes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
Table 1: Physical and Financial Performance Report . . . . . . . . . . . . . . . . . . . . . . . 19
Table 2: Gender and Development Annual Report . . . . . . . . . . . . . . . . . . . . . . . . . 44
Annex A: Number of Visitors and Income Generated at NAPWC
for CY 2015 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
ii
LIST OF FIGURES
Figure 1. Meetings lead by BMB . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Figure 2. Philippine AHP of 2015 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Figure 3. 5th ToT on the Application of the Wildlife Law Enforcement Manual
of Operations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Figure 4. Intelligence-led surveillance and enforcement operations in violation
of R.A. 9147 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Figure 5. CorVA Trainings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Figure 6. 11th Senior Officials Meeting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Figure 7. Awareness Campaigns conducted . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Figure 8. Participated/Conducted the following meetings/conferences/assessment
in wetland management and conservation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Figure 9. Conducted the following meetings/trainings re caves and cave resources . . . . . . 12
Figure 10. Produced the following IEC materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Figure 11. Conducted the following GAD activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Figure 12. Conducted Learning event on Mainstreaming and Integrating Gender Tool
in Biodiversity Conservation and Protected Areas in the following PAs . . . . . . . . 15
Figure 13. BMB Gender Sensitivity Training . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
Figure 14. Post Assessment Workshop on the conduct of learning events in the 4 regions . . 16
Figure 15. Strategic Planning and Consultation Workshop on Biodiversity Conservation . . . . 16
Figure 16. Monitored and evaluated the following Priority Sites under the Ecotourism
Development Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
iii
LIST OF ACRONYMS
ADB Asian Development Bank
AHP ASEAN Heritage Park
ASEAN Association of Southeast Asian Nations
AWC Asian Waterbird Census
AWP Annual Work Plan
BMB Biodiversity Management Bureau
BMS Biodiversity Monitoring System
BPP Biodiversity Partnership Projects
CA Certificate of Appointments
CAWED Coastal and Wetlands and other
Ecosystems Division
CH Critical Habitat
CITES Convention on International Trade in
Endangered Species of Wild Fauna and
Flora
CMD Coastal and Marine Division
COP12 12th Meeting of the Conference of the
Parties
CorVA Coral Reef Visualization and
Assessment
CSO Civil Society Organizations
CTI Coral Triangle Initiative
CTI-CFF Coral Triangle Initiative on Coral Reefs,
Fisheries, and Food Security
DMC DENR Memorandum Circular
FAPs Foreign-Assisted Projects
GAD Gender and Development
GEF Global Environment Facility
GIS Geographic Information System
GIZ Deutsche Gesellschaft für
Internationale Zusammenarbeit
IAS Invasive Alien Species
ICC International Coastal Clean-up
ICCA Indigenous Community Conservation
Areas
ICM Integrated Coastal Management
IDBD International Day for Biological
Diversity
IOSEA Indian Ocean – Southeast Asian
IP Indigenous People
IPAF Integrated Protected Area Fund
IUU Fishing Illegal, Unregulated, and Unreported
Fishing
KBA Key Biodiversity Area
LCA Local Conservation Area
MHRWS Mt. Hamiguitan Range Wildlife
Sanctuary
MKBA Marine Key Biodiversity Areas
MPA Marine Protected Areas
MR Marine Reserve
NAPWC Ninoy Aquino Parks and Wildlife
Center
NBSAP-BIOFIN National Biodiversity Strategy and
Action Plan – Biodiversity Finance
Initiative
NCIP National Commission on Indigenous
People
NESC National Ecotourism Steering
Committee
NIPAS National Integrated Protected Area
System
NP National/Natural Park
NWRRC National Wildlife Rescue and Research
Center
PA Protected Area
PACBRMA Protected Area Community-Based
Resource Management Agreement
PAFID Philippine Association for Intercultural
Development
PAMB Protected Area Management Board
PAME Protected Area Management
Enhancement
PASu Protected Area Superintendent
PCP Pawikan and Dugong Conservation
Program
PEF Philippine Eagle Foundation
PEIP Philippine Eagle Integrated Plan
PEW Philippine Eagle Week
PEWG Philippine Eagle Working Group
PL Protected Landscape
PMU Project Management Unit
POGI Philippine Operations Group on Ivory
PPEI Philippine Poverty Environment
Initiative
PRCP Philippine Raptors Conservation
Program
Pre-SOM Pre-Senior Officials Meeting
PWRCC Palawan Wildlife Rescue and
Conservation Center
RETA Regional Technical Assistance
SBR Special Budget Request
SC-MPAN Sub-Committee on Marine Protected
Areas and Networks
SGP5 Fifth Operation Phase of the GEF Small
Grants Program in the Philippines
SOM11 11th Senior Officials Meeting
SSME Sulu-Sulawesi Marine Eco-Region
TEZ Tourism Enterprise Zones
TIWS Turtle Island Wildlife Sanctuary
UNDP United Nations Development
Programme
WA Wilderness Area
WFR Watershed Forest Reserve
WRC Wildlife Rescue Center
WRD Wildlife Resources Division
iv
2
Department of Environment and Natural Resources
BIODIVERSITY MANAGEMENT BUREAU
CY 2015 Annual Report
I. Introduction
The Biodiversity Management Bureau (BMB), as one of the staff Bureaus of the Department of Environment and Natural Resources (DENR) and the lead agency tasked to conserve biodiversity, is mandated to protect the country’s biological diversity and to properly manage and conserve its resources as well as the ecosystem services they provide.
For CY 2015, the Bureau continuously implemented activities based on its 3 major programs,
namely: (1) Protected Area and Ecosystems Management and Protection; (2) Wildlife Protection and Conservation; and, (3) Coastal and Marine Biodiversity Conservation. The Bureau was also able to formulate policies and implemented programs which focus on the establishment of an integrated protected areas system and the conservation of biological diversity. Following the Bureau’s mandates, specific activities per program were accomplished. In particular, on the formulation and development of plans and policies, the Bill on the Expanded NIPAS Act was approved in the 3rd Reading of the Plenary at the Senate and passed the House Committee Level. Aside from this initiative, several policies that support the protection and conservation of protected areas (PA), critical habitats, and other conservation areas were developed. In terms of developing protected areas, technical assistance on the management of protected areas and other ecosystems were undertaken specifically on the designation and management of 2 PAs as ASEAN Heritage Parks (AHP) which were officially launched this year, namely: (1) Tubbataha Reef Natural Park; and, (2) Mt. Timpoong Hibok-Hibok Natural Monument. The Bureau also led the implementation of Ecotourism Development Program in about 22 PAs including the Mt. Makiling Forest Reserve in Los Baños, Laguna. It is hoped that these PAs including those already developed in the past years would contribute to the enhancement of ecosystem services in these areas and would continuously promote the unique and important landscape and seascape in the country.
In terms of other ecosystems such as caves and wetlands, the Bureau pursued the
implementation of programs, projects and activities in line with the implementation of the Caves and Cave Resources Conservation and Protection Act (RA 9072) and the National Wetlands Action Plan. In particular, the Bureau facilitated the classification of additional 51 caves which gives a total of 415 caves classified as of December 2015.
In terms of wildlife protection and conservation, BMB continuously monitored and provided
technical guidance to Regional Offices and other clienteles in the conservation and management of threatened species, i.e. marine turtles, dugong, Philippine raptors, and in the designation and management of critical habitats in line with the implementation of the Wildlife Resources Conservation and Protection Act (RA 9147). The Bureau also intensified the regulation of wildlife collection and trade through among others, continuous capacitation and mobilization of the Philippine Operations Group on Ivory and Wildlife Resources (POGI), the Wildlife Enforcement Officers and other partners on wildlife conservation.
In terms of coastal and marine biodiversity conservation program, the Bureau has been
instrumental in implementing capacity building programs in the implementation of various programs on coastal and marine such as the Integrated Coastal Management (ICM), Coral Reef Visualization and Assessment (CorVA), Corals and Fish Assessment, Automated Rapid Reef Assessment System (ARRAS), and Coastal Integrity, Seagrass and Mangrove Habitat. Likewise, the
3
Bureau continued the engagement with scientific institutions in the effective implementation costal and marine activities particularly in the baselining of coral reef ecosystems in the country.
II. Accomplishments
1. Policies formulated and approved
For CY 2015, the Bureau was able to prepare/draft a total of 21 policies. Of these, 8
targeted policies were endorsed for approval of the Secretary and among these policies, 1 was
approved i.e. 2015 List of Classified Caves. Moreover, 5 targeted policies and/or guidelines for
drafting were also accomplished.
Aside from the targeted policies, the Bureau was also able to endorse 3 additional policies
which were not originally targeted for 2015. Of these, 2 were approved. Furthermore, the
Bureau was also able to draft 5 additional policies that were not targeted for 2015.
Specifically, the endorsed policies, which are included in the targets for CY 2015, are:
1. DENR Memorandum Circular (DMC) 2015-08 re: 2015 List of Classified Caves
- approved last November 10, 2015
2. Proposed DENR Administrative Order (DAO) establishing certain areas as Critical
Habitat (CH):
a. DAO declaring certain parcels of land at Purok 1-4 of Brgy. Kandiis as Parcel 1
and Purok 1-6 of Brgys. San Isidro and Damoyohan as Parcel 2 in the
Municipality of Magsaysay, Misamis Oriental as Critical Habitat (CH) for
Hawksbill Turtle
b. DAO declaring portion of Lobo Watershed in Bargy. Sawang, Municipality of
Lobo, Province of Batangas as CH for the Philippine Teak
c. DAO re: establishment of 22.67 ha of mangrove and coastal areas in San
Diego, Lian, Batangas as CH for Marine turtles and Waterbirds
3. Policy on the registration of raw and/or worked elephant ivory
4. Additional Guidelines on the Local Transport of Wildlife, Wildlife by-products,
and/or derivatives for shows, exhibitions and educational purposes
5. Proposed DAO updating the Threatened Flora List established under DAO No.
2007-01
6. Policy on Wildlife Emergency Response
The drafted policies, which are included in the targets for CY 2015, are:
1. Proposed DAO updating the Threatened Fauna List established under DAO No.
2004-15
2. List of Economically Important Plant Species
4
3. Proposed Guidelines on the issuance of clearance for wildlife research within
Protected Areas
4. Guidelines and Manual on Nature Interpretation
5. Updating of Manual on Design of Structures, Facilities, and Markers on Protected
Areas
Also, the additional policies and/or guidelines, which are not targeted for CY 2015 but
were drafted and/or endorsed to OSEC or through Technical Bulletins are:
1. DENR Administrative Order (DAO) No. 2015-10 re: Guidelines on the Delineation
and Demarcation of Protected Areas under the NIPAS
- approved last May 29, 2015
2. BMB Technical Bulletin No. 2015-01 re: Guideline in the Production of Coffee
Table Book for Protected Areas
- approved last November 26, 2015
3. Addendum to DAO 2007-17 re: Rules and Regulations Governing Special Uses
within Protected Areas
- re-endorsed last August 25, 2015
4. Drafted policy re: “Marine Ecosystems Recovery and Rehabilitation Program”
5. Drafted policy re: “Implementation/ Operationalization of National Integrated
Coastal Management (ICM) Strategy for the Sustainable Development of the
Coastal and Marine Biodiversity in the Philippines”
6. Drafted DAO re: “Comprehensive Management Program for Coastal and Marine
Biodiversity”
7. Drafted DAO re: Prescribing the Requirements for the Issuance of PAMB
Clearance for the Designation of Tourism Enterprise Zones (TEZ) within Protected
Areas
8. Drafted Executive Order (EO) re: Establishing a Wetland National Policy and
creating the National Wetlands Conservation Committee
The following Memorandum of Agreements (MOA) were also reviewed:
1. Diversity, Ecology and Long-Term Population Dynamics of Philippine Bat
Communities
2. Investigations into the Taxonomy, Diversity and Ecology of Mangrove Oomycetes
in the Philippines
5
3. Scientific Investigation on Rice-associated Wild Fauna and Flora for Research
Advancement and Biodiversity Conservation
4. Cultivation of Rafflesia for Ex-situ Conservation
5. Biodiversity Research, Education Outreach and Conservation Genetics of
Philippine Amphibians, Reptiles and Invertebrates
6. Comparative Biogeoraphy and Conservation of Philippine Vertebrates
7. Scientific Survey of the Streaked Reed Warbler (Arcrocephalus sorghophilus) and
other Bird Species in the Philippines
8. Collaborative Program for the Conservation of the Philippine Cockatoo: The
Singapore Project
Furthermore, draft proposals and policies, bills, and resolutions have also been reviewed,
to wit: 18 research/project proposals; 17 policies; 79 Bills (HB and SB); and, 5 resolutions
(Please see Table 1 for the detailed accomplishment matrices of BMB for CY 2015).
2. Major Programs and Projects Implemented
A. Establishing and Managing Protected Areas
On monitoring of NIPAS establishment and disestablishment, the Bureau was able to
review the proposed withdrawal/disestablishment of Mt. Data NP, Lower Agno WFR, and
Roosevelt PL; as well as, the proposed Presidential Proclamation of Bulabog-Putian NP,
Lake Buluan NP, Koronadal Watershed Area, Hinabian-Lawigan WFR, and Bantayan Island
WA. One hundred seven (107) PA bills were also endorsed for filing/refiling.
Cognizant with the targets under the NIPAS management, 39 CAs for PAMB
organization and strengthening were endorsed to OSEC and 23 approved CAs were
forwarded to the Regional offices. One hundred three (103) resolutions and 25 minutes
of meeting on PAMB operationalization were reviewed. Moreover, 22 SBRs for IPAF
establishment/operation were endorsed, and 33 IPAF collection reports were reviewed.
Five (5) management plans were also reviewed for PA management plan
preparation/updating.
The Bureau conducted the PA Business Planning Orientation-Workshop last
November 12-13, 2015 at Icon Hotel, Quezon City. Updates from Regional Offices were
also requested on the adoption of the Business Plans of the following PAs already
presented to their respective PAMBS: (1) Mt. Banahaw-San Cristobal PL (R4A); (2) Mt. Apo
NP (R11); and (3) Naujan Lake (R4B). Region updates from DENR CALABARZON were also
requested on the presentation of Business Plan of Mts. Palay-Palay/Mataas-na-Gulod PL.
6
The Bureau was also able to monitor PACBRMA applications of 31 People’s Organizations within the Municipalities of Pantabangan-Carranglan, Nueva Ecija. Review and validation of Boundary Delineation and Demarcation monitoring reports and monitoring of NIPAS implementation were also conducted.
Several proposals were also prepared which include the National ICCA Project
Proposal, National PAMB Conference Proposal, and Biodiversity Assessment Training. The Bureau also spearheaded the conduct of the National Consultation for the
Finalization of Handbook on PA Law Enforcement last July 4-5, 2015, the National PAMB Summit last July 13-14, 2015 (Fig. 1A, 1B), and the 4th Regional PAMB Summit on DENR Region 4A last August 17-19, 2015 (Fig. 1C, 1D).
Moreover, the Bureau was able to officially launch the Tubbataha Reef Natural Park
(Fig. 2A) and Mt. Timpoong Hibok-Hibok Natural Monument (Fig. 2B) as the 7th and 8th ASEAN Heritage Park (AHP) of the Philippines, respectively.
Figure 1. Meetings lead by BMB: (A,B) National PAMB Summit; and (C,D) 4th Regional PAMB Summit
Figure 2. Philippine AHP of 2015: (A) Tubbataha Reef Natural Park; and (B) Mt. Timpoong Hibok-Hibok
Natural Monument
The Expanded NIPAS Act (SBN 2712), which covers 96 PAs and 1 CH, was approved
in the 3rd Reading of the Plenary at the Senate. Likewise, the Enhanced NIPAS Act (HBN
4336), covering 101 PAs, passed the House Committee Level.
B. Monitoring of Existing Threatened Species Conservation and Management Programs
Through the Wildlife Resources Division (WRD), the Bureau was able to submit a
consolidated National Asian Waterbird Census (AWC) report to Wetland International.
A B
D C
A B
7
Furthermore, on the establishment and management of Critical Habitats (CH), 7 proposals
from Regional offices were reviewed and evaluated, while 3 proposals for establishment
as CH were endorsed for approval (Please see Formulation and Review of policies). The
Bureau was also able to conduct field validations of the implementation of Biodiversity
Monitoring System (BMS) in 16 protected areas and reviewed and evaluated 35 BMS
reports submitted by Regional Offices.
Organized the 5th Training of Trainers on the Application of the Wildlife Law
Enforcement Manual of Operations (Fig. 3).
Moreover, the Bureau continuously implemented programs that focus on the
conservation of threatened wildlife such as: the Pawikan and Dugong Conservation
Program (PCP), the Philippine Raptors Conservation Program (PRCP), the Palawan Wildlife
Rescue and Conservation Center (PWRCC)-Crocodile Farming Project, as well as the
National Wildlife Rescue and Research Center (NWRRC) which is a component of the
Ninoy Aquino Parks and Wildlife Center.
Figure 3. 5th ToT on the Application of the Wildlife Law Enforcement Manual of Operations last September
7-11, 2015
Some of the notable accomplishments of the Threatened Species Conservation and
Management Programs for CY 2015 include the following:
a. Pawikan Conservation Program (PCP)
The Bureau, through WRD, continuously consolidated and encoded the data on
tagging, nesting incidence, nest/egg transplanted and hatchling emerged and
released submitted by Turtle Islands Wildlife Sanctuary (TIWS) and conservation
partners. Continuous coordination with concerned DENR Regional/Field Offices
and/or partners on the rescue, protection, and other conservation related activities
of Marine turtles are also conducted religiously.
Revision of the proposal to include the Philippine TIWS as Indian Ocean –
Southeast Asian (IOSEA) Marine Turtle Site Network is underway with regards to the
comments and review of the Advisory Committee.
Conducted Biological Resource Assessment and Vulnerability Assessment in TIWS
from September 28 – October 9, 2015. Assisted the PASu staff of TIWS in the search
and retrieval of the 6 data loggers that was installed on the beach and coral reef in
Baguan Island.
8
b. Philippine Raptor Conservation Program (PRCP)
The Bureau, through WRD, organized and spearheaded the 2015 celebration of the Philippine Eagle Week (PEW) last June 4-10, with the theme, “Saving Eagles, Protecting Forests, Securing our Future” with BMB-CAWED, Manila Ocean Park, and Wild Bird Photographers of the Philippines. The Bureau also continuously coordinated with concerned DENR Regional/Field Offices and/or partners on the rescue or protection of Philippine Raptors. There were a total of 48 Philippine Eagle sightings for 2015.
The Philippine Eagle Working Group (PEWG) convened on November 10, 2015 to
discuss the latest concerns raised by FMB vis-à-vis for inclusion into the draft Loan Protocol for Philippine Eagles. The Memorandum Circular re: Philippine Eagle Loan Protocol was drafted by December 2015.
For the continuous updating of the Philippine Eagle Integrated Plan (PEIP), a meeting among Haribon Foundation, Inc., Philippine Eagle Foundation, and BMB-WRD staff were organized. Inputs gathered during consultation workshops and writeshops were also incorporated to the updating of the PEIP. Moreover, the renewal of the Memorandum of Agreement between BMB and Philippine Eagle Foundation (PEF) on continued Philippine Eagle conservation was drafted after the existing MOA expired last December 2014.
Series of investigations are continuously being conducted by Davao Oriental and DENR Region 11 after the Philippine Eagle, “Pamana”, was found shot dead last August 16, 2015 at Mt. Hamiguitan Range Wildlife Sanctuary (MHRWS). According to PEF’s Conservation and Research Director, Dr. Jayson Ibañez, an Inter-Agency Task Force was created to find the killer(s) of “Pamana”. Moreover, reports from PASu Ruel Colong of MHRWS were collated. A timeline/dossier was also prepared on “Pamana” for reference purposes.
c. Palawan Wildlife Rescue and Conservation Center (PWRCC) – Crocodile Farming Project
The Palawan Wildlife and Rescue Center (PWRCC) was able to maintain 1,656 crocodiles and 731 other wildlife species. Aside from the continuous monitoring of the PWRCC, site and population assessments were also conducted.
d. National Wildlife Rescue and Rehabilitation Center (NWRRC)
The BMB-Wildlife Rescue Center (WRC) was able to rehabilitate and maintain
2,982 animals and release 82 wildlife species as of December 2015. Guided tours and
orientation of mini-zoo/Lungsod Kalikasan and about the WRC are being done
regularly. Cognizant with the aim to improve the facilities within the WRC, 16 cages
were repaired and 30 were purchased.
e. Wildlife Regulation and Enforcement
The BMB-WRC was able to process and issue a total of one thousand three hundred thirty-nine (1,339) CITES permits as of December 2015. Configuration of CITES E-Permitting and Management Information System, as well as, updating of
9
database on wildlife crimes, list of wildlife permit holders per region, production and trade report of wildlife breeders are continuously being conducted and maintained.
In relation with the implementation of Wildlife Special Projects, 4 out of 4 project
implementation reports on Invasive Alien Species were prepared and submitted.
Continuing its fight against ivory trade, several activities were conducted by the Bureau through the Philippine Operations Group on Ivory (POGI). For 2015, there were seven (7) intelligence-led surveillance and enforcement operations against violators on which confiscations were made (Fig. 4). During these operations, 2,100 wildlife species were confiscated.
Figure 4. Intelligence-led surveillance and enforcement operations in violation of R.A. 9147
Legal actions were also taken by the Bureau such as by providing assistance in the
filing of prosecution of criminal cases against violators of wildlife laws and relevant policies. Moreover, six (6) case reports were also submitted and 18 court hearings were attended, notably, the court hearing in General Trias, Cavite in connection with the criminal case filed against a certain Mr. John Cardel I. Macario in violation of Section 27 of R.A. 9147 (illegal trading of Serpent eagle).
C. Promoting and Institutionalizing Ecotourism
Representatives from BMB conducted regular and active participation with the
National Ecotourism Steering Committee (NESC) and Ecotourism Technical Working
Group (ETWG). Some points of discussion are as follows: (1) presentation of logframe
system; (2) status/updates on the development of model sites; (3) sustainable
consumption and production mainstreaming; (4) proposed collaboration with UNDP-DILG
on Philippine Poverty Environment Initiative (PPEI); and, (5) Convention on Migratory
Species hosting of DOT on 2017.
A Capacity Building Workshop on Ecotourism Development in Priority Protected Areas
was also conducted last May 5-8, 2015. Site assessments and monitoring of 2014 priority
ecotourism sites were also conducted.
D. Managing Coastal Biodiversity and Wetlands Ecosystems
a. Coastal Management and Conservation Program
The Coastal and Marine Division (CMD) of the Bureau facilitated the Planning
Workshop for Integrated Coastal Management (ICM) Implementation: Learnings from
Bataan and Cavite held in Subic last May 18-19, 2015. A Learning Event on ICM for
10
Landlocked Local Government Units within Manila Bay Regions was organized
through Manila Bay Project.
Under the SCREMP program, the Bureau was able to manage and protect a total
of 54,197.81 ha of coral reefs and a total of 91,737.64 ha of coral reefs assessed and
mapped.
Eleven (11) newly certified open-water SCUBA divers were accredited from the
Coral Reef Visualization and Assessment (CorVA) trainings (Fig. 5A). Other CORVA
trainings conducted were: Corals and Fish Assessment (Fig.5B); Automated Rapid Reef
Assessment System (ARRAS) (Fig. 5C); and, Coastal Integrity, Seagrass and Mangrove
Habitat (Fig. 5D). All newly capacitated technical staff were from the different
technical divisions of BMB with the exception of the two (2) new divers from Region
4A. Continuous surveillance, mapping, and research of Coastal and Marine habitats
are conducted.
Figure 5. CorVA Trainings: (A) Coral Reef Visualization and Assessment; (B) Coral and Fish Assessment;
(C) ARRAS; and (D) Coastal Integrity, Seagrass and Mangrove Habitat Training
A database and website was developed by UP MSI to house all the data and
profiles of local and NIPAS Marine Protected areas (MPAs) which is now mirrored in
the BMB website
Formed part of the Philippine delegation who attended the Coral Triangle
Initiative (CTI) Pre-Senior Officials Meeting (Pre-SOM); Illegal, Unregulated, and
Unreported (IUU) Fishing; and the 11th Senior Officials Meeting (SOM11) held in
Manado, Indonesia last November 30 – December 3, 2015 (Fig. 6). Representatives of
the Bureau also participated in the 4th Coral Triangle Initiative on Coral Reefs,
Fisheries and Food Security (CTI-CFF) Regional Business Forum on August 27-29, 2015
at Nusa Dua Convention Center, Bali, Indonesia. The Bureau also led the
implementation of the CTI MPA Working Group Work Plan.
Figure 6. 11th Senior Officials Meeting (SOM11)
A A B C D
11
Moreover, CMD personnel spearheaded the conduct of several Awareness Campaigns such as: Month of the Ocean (Fig. 7A); International Coastal Clean-up (ICC) (Fig. 7B); and, Coral Triangle Day (Fig. 7C).
Figure 7. Awareness Campaigns conducted: (A) Month of the Ocean; (B) International Coastal Clean-up;
and (C) Coral Triangle Day
b. Wetland Management and Conservation Program
The Bureau, through the Caves and Wetlands and other Ecosystems Division (CAWED) hosted the 1st ASEAN Task Force on Peatland last June 22-23, 2015 in Manila (Fig. 8A). The Bureau also participated in the 12th Meeting of the Conference of the Parties (COP12) to the Convention on Wetlands (Ramsar Convention) in Uruguay last June 1-2, 2015 (Fig. 8B) and adopted the COP12 Ramsar Resolution 13 re: Wetlands and Disaster Risk Reduction. Participation in the Training on Inland Wetlands Biodiversity Assessment and Monitoring was also executed (Fig. 8C).
Wetland assessments and validation/mapping of inland wetlands were also
reviewed and conducted; as well as, 3 Orientation-Workshops on GIS-Based Inventory and Geo-tagging of Philippine Wetlands and Caves Project.
A total of 789 wetlands were inventoried as of 2015, wherein, 175 inland wetlands were geo-tagged. The inventory of inland wetlands is still on-going.
The layout of the Atlas of Inland Wetlands and Caves is currently on-going while
the Pictorial Handbook on Peat Swamp Flora of Agusan Marsh, Mindanao, Philippines was finalized. The Wetlands Database has been enhanced and populated.
Figure 8. Participated/Conducted the following meetings/conferences/assessment in wetland
management and conservation: (A) 12th Meeting of the Conference of the Parties (COP12); (B) 1st
ASEAN Task Force on Peatland; and (C) Training on Inland Wetlands Biodiversity Assessment and
Monitoring
E. Conserving Caves and Cave Resources
Through the Cave Management and Conservation Program, the 15th Caving Congress (Fig. 9A) and 19th National Cave Committee Meeting (Fig. 9B) were conducted. CAWED
A B C
A B C
12
also monitored and geo-tagged priority classified caves in Regions 4B, 9, and 10. Moreover, an Orientation-Training on Cave Rescue Protocol was accomplished for Luzon cluster in Sagada, Mountain Province on November 10-12, 2015 (Fig. 9C).
Fifty-one (51) caves were classified and inventoried for 2015 (approved DMC 2015-
08), making a total of 415 caves classified since 2012, wherein 53 classified caves and 1 unclassified caves were geo-tagged.
Figure 9. Conducted the following meetings/trainings re caves and cave resources: (A) 15th Caving Congress;
(B) 19th National Cave Committee Meeting; and (C) Orientation-Training on Cave Rescue Protocol
Drafting of the Strategic Action Plan is still on-going and the database for caves are being finalized.
F. Information and Education on Biodiversity and Nature Conservation
Produced and distributed copies of the 2016 BMB Calendar and Planner (Fig. 10A). Facilitated the reprinting of the Coffee Table Book (Treasures of the Philippine Wild) (Fig. 10B), Cave Primer (Fig. 10C), Cave Handbook (Fig. 10D), National Ecotourism Strategy, Cave Act (RA 9072), and the Guidelines on Ecotourism Planning and Management in Protected Areas.
Figure 10. Produced the following IEC materials: (A) 2016 BMB Calendar; (B) Coffee Table Book; (C) Cave Primer; and (D)
Cave Handbook
Special events were also conducted, such as: World Wetlands Day, World Wildlife Day, International Day for Biological Diversity (IDBD), BMB’s 28th Anniversary, World Environment Day, National Statistics Month, and Tamaraw Month.
Lastly, launched the Biodiversity Advocacy Campaign last May 22, 2015 and 3 TV commercials about the said campaign which aired in CNN.
A
B
C
A B C D
13
G. Managing Ninoy Aquino Parks and Wildlife Center The Bureau continuously managed the 22.7 hectare Ninoy Aquino Parks and Wildlife
Center (NAPWC). The renovation of the Old PAWB Building No. 1 to house the Protected Area Gallery is still on-going; as well as the packet landscaping in selected areas at NAPWC.
Furthermore, a total of 471,600 visitors (male=239,609; female=231,991) were
recorded from January to December 2015 generating a total income of ₱4,325,787.00 from the entrance, parking, and rental fees of the park (see Annex A).
3. Foreign-Assisted and Special Projects Implemented
For CY 2015, below are some of the accomplishments of the Foreign-Assisted Projects (FAPs) that are being implemented by BMB:
A. National Biodiversity Strategy and Action Plan – Biodiversity Finance Initiative (NBSAP-
BIOFIN)
The PBSAP was prepared through regional and national stakeholder consultations. Final version is completed to include indicators, monitoring partnerships, timeline, agencies responsible and projected costs of actions.
The Project developed national targets in response to the global Aichi Targets.
Completed a supplement which focused on four (4) policies that may be potential financing sources for biodiversity conservation. These are: Energy Regulation 1-94, as amended; Malampaya Fund; Motor Vehicle User’s Tax; and, Mining Taxes, Fees, and Royalties from Mining.
B. Partnerships for Biodiversity Conservation : Mainstreaming in Local Agricultural Landscapes (BPP)
The BPP developed the frameworks, tools and manuals for mainstreaming biodiversity into the local land use plans and drafted ordinance declaring the municipalities of Alegria and Kitcharao as Local Conservation Areas (LCAs). Demonstration farms were also established in Quirino PL, Northern Negros NP, and Lake Mainit KBA. Moreover, 2 new conservation areas were delineated in Tubod and Mainit, Surigao Del Norte.
Reviewed/finalized the following policies: DMC Prescribing the Adoption of the
Manual of Procedures for the Biodiversity-focused Strategic Environmental Assessment for Assessing the Effects of Policies, Plans and Programs; DA-DENR JAO re: Mainstreaming Biodiversity-Friendly Agricultural Practices in and around PAs and KBAs and Promoting the Same in Wider Agricultural Landscapes and Promotion in wider agricultural landscapes; and, DENR-DTI-DOT JAO for the Adoption of the Biodiversity-Friendly Enterprise Framework.
Demonstrated biodiversity-friendly enterprises in the project sites with potentials for
scale-up and continually being supported by the project through market linkage and partnerships with private investors.
14
C. Small Grants Programme (SGP 5)
The Small Grants Programme (SGP 5) approved 9 Small Grants Projects for implementation aiming to establish and demonstrate community managed PAs, strengthening community protection areas, production of land/seascapes, community plans that incorporate biodiversity and ecosystem service valuation, and production of BD-friendly products.
Conducted partnerships with National Commission on Indigenous People (NCIP),
Philippine Association for Intercultural Development (PAFID), KASAPI, and CSO.
D. New Conservation Areas in the Philippines Project (NewCAPP)
The project continued providing support to BMB for the formulation of the PA System Master Plan. The ICCA Publication and the Proceedings of the 2nd National Conference on ICCA has been completed; as well as the ICCA and LCA Guide.
With UNDP and NCIP, the new project on ICCAs entitled “Strengthening National
Systems to Improve Governance and Management of Indigenous Peoples and Local Communities Conserved Areas and Territories” was approved by GEF last August 2015. This project aims to strengthen the conservation, protection, and management of key biodiversity sites in the Philippines by institutionalizing IP and ICCAs as a sustainable addition to the national PA estate.
E. Protected Area Management Enhancement (PAME) Project
The project staff and consultants presented the results of the Client Satisfaction
Survey, Assessment of Organizational Development and Training Needs of DENR-BMB along with the discussions on how the scores were gained, suggestions on how to improve, and problems encountered during the validation.
Participated in the Assessment of Inland Wetland Biological Diversity and Assessment
and Monitoring for Protected Areas Capacity Development Workshop for Terrestrial Ecosystems as part of the Capacity Development Workshop series for DENR personnel of the PAME Project of GIZ and BMB.
F. Removing Barriers to the Management of Invasive Species in Protection and Production Forest
Continuously implemented the Project “Removing Barriers to Invasive Species Management in the Production and Protection Forests in the Philippines”. Presence of Invasive Alien Species (IAS) in Bataan NP, Mt. Banahaw – San Cristobal PL, Agusan Marsh WS, and Samar Island NP. A series of meetings/workshops for the operationalization of IAS-Technical Working Group were conducted.
G. Marine Key Biodiversity Area (MKBA) Project
The project held its 1st Project Board Meeting last June 11, 2015 to discuss the roles and responsibilities of the Project Board Members and Responsibilities Partners.
15
The MKBA Project Management Unit (PMU) submitted the 2015 Annual Work Plan (AWP) to the UNDP Country Office. The PMU have formally documented partnership with 5 local RPs and 2 collaborating partners.
Facilitated the updating of MPA management plans.
H. Sulu-Sulawesi Marine Eco-region (SSME) Program
Conducted the 9th Meeting of the SSME Tri-National Sub-Committee on Marine
Protected Areas and Networks (SC-MPANs) last September 9-10, 2015. The GIZ-funded SSME Project also conducted the Vulnerability Assessment Training/Workshop which aims to deliver towards an Ecosystem-based Climate Change Adaptation Plan developed and incorporated in the TIWS management plan based on vulnerability assessment studies. The Bureau attended the 9th SSME Threatened, Charismatic, and Migratory Species Sub-Committee Meeting on October 12-13, 2015 in Bogor, West Java, Indonesia. The Project also conducted participative visioning and presentation of resources assessment results of ADB RETA 7813 to the communities of Brgy. Ramos and Brgy. Salang of Balabac, Palawan on October 24-29, 2015. Continuous collaboration with partner agencies for the establishment of MPAs are being maintained by the group to ensure coordinated efforts.
4. Gender and Development (GAD) Mainstreaming
Participated in the celebration of the 2015 National Women’s Month last March 8, 2015 (Fig. 11A) and the launching of the BMB-GAD logo last March 30, 2015 (Fig. 11B). Also, participated in the 18-Day Campaign to End Violence against Women from November 25 – December 12, 2015 (Fig. 11C).
Figure 11. Conducted the following GAD activities: (A) 2015 National Women’s Month and BMB-GAD logo
launching; (B) 18-Day Campaign to End Violence against Women; and (C) Gender Sensitivity Training
Figure 12. Conducted Learning event on Mainstreaming and Integrating Gender Tool in Biodiversity Conservation and Protected
Areas in the following: (A) Mt. Kitanglad Range NP; (B) Sagay MR; (C) Bataan NP; and (D) Upper Marikina River Basin (PL )
B
A C B
A D C B
16
Conducted Learning event on Mainstreaming and Integrating Gender Tool in Biodiversity
Conservation and Protected Areas in Mt. Kitanglad Range NP (Fig. 12A), Sagay MR (Fig. 12B),
Bataan NP (Fig. 12C), and Upper Marikina River Basin PL (Fig. 12D); as well as, the BMB Gender
Sensitivity Training last December 10, 2015 (Fig. 13).
Figure 13. BMB Gender Sensitivity Training
Furthermore, a Post Assessment Workshop was organized on the conduct of learning
events in the four (4) regions last August 6-7, 2015 (Fig. 14). And a GAD corner was created in
the BMB website.
Figure 14. Post Assessment Workshop on the conduct of learning events in the 4 regions
5. Other significant accomplishments/milestones/breakthroughs
Conducted Strategic Planning and Consultation Workshop on Biodiversity
Conservation held at Widus Hotel, Clarkfield, Pampanga last December 16-17, 2015
(Fig. 15);
Figure 15. Strategic Planning and Consultation Workshop on Biodiversity Conservation
Conducted Monitoring and Evaluation of Priority Sites under the Ecotourism
Development Program from October to December 2015 (Fig. 16).
17
Figure 16. Monitored and evaluated the following Priority Sites under the Ecotourism
Development Program: (A) Minalungao NP; (B) Sagat MR; (C) Allah Valley PL; (D) Saranggani
Bay; (E) Bataan NP (viewdeck); and (F) Aliwagwag PL
MINALUNGAO NP
A B
E F
C D
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 1: ECOSYSTEMS POLICY SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
MFO 1: ECOSYSTEMS POLICY SERVICES 11,279,000 9,824,000 87% 9,816,184 6,667,687 87% 68%
A.03.a FORMULATION AND MONITORING OF ENR SECTOR,
POLICIES, PLANS, PROGRAMS AND PROJECTS
1. Policy Formulation
1.1 Wildlife Resources Conservation Program meetings/consultation/workshop conducted 2 6 300% 1. 1st Meeting of the Philippine Red List Committee that included
1.1.1 Proposed DENR Administrative Order (DAO) updating the DAO drafted 1 1 100% initial discussions on DAO 2004-15 was held last April 8, 2015 at
Threatened Fauna List established under DAO No. 2004-15 BMB Conference Room;
2. Experts' Workshop to review the existing list of threatened wild
fauna was held last April 18-19, 2015 at the University of Eastern
Philippines, Catarman, Northern Samar;
3. 2nd Meeting of the Philippine Red List Committee for Wild
Fauna that included discussions and further review of the
threatened list was held last June 3, 2015 at BMB Conference
Room;
4. 3rd Meeting of the Philippine Red List Committee for Wild
Fauna for the continuous review of threatened list was held on last
July 3, 2015 at BMB Conference Room.
5. The First Philippine Red List Committee for Wild Fauna
Workshop for the assessment of the conservation status of
Philippine wild fauna and come up with initial updated list of
threatened species was held last September 1-3, 2015 in Clark,
Pampanga.
6. A workshop of the Technical Working Group of the Philippine
Red List Committee was held last 11-13 November 2015 in
Tagaytay City. The workshop aims to produce the draft list of
species to be considered in the National Red List of Threatened
Species pursuant to RA 9147.
1.1.2 Establishing certain areas as critical habitat DAO drafted and endorsed 3 3 100% Draft DAO Declaring certain parcels of Land of the Public
Domain situated at Purok 1-4 of Barangay Kandiis as Parcel 1,
and Purok 1-6 of Barangays San Isidro and Damoyohan as
Parcel II, All in the Municipality of Magsaysay Province of
Misamis Oriental as Critical Habitat for Hawksbill Turtle and to
be known as "Magsaysay Critical Habitat for Hawksbill
turtle
- The draft DAO incorporating the comments of the DENR-
PTWG was re-endorsed to the DENR on Dec. 2, 2015
Draft DAO Declaring portion of Lobo Watershed in Barangay
Sawang, Municipality of Lobo, Province of Batangas as Critical
Habitat for the Philippine Teak
REMARKAnnual Accomp. % Accomp. Disbursement
% Budget Utilization Rate (BUR)
PHYSICAL PERFORMANCE
Table 1: PHYSICAL AND FINANCIAL PERFORMANCE REPORT
CY 2015
PROGRAM/ACTIVITY/PROJECT Allotment Released
%
(Amt.
Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
FINANCIAL PERFORMANCE
Annual Target
Page 19
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 1: ECOSYSTEMS POLICY SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
REMARKAnnual Accomp. % Accomp. Disbursement
% Budget Utilization Rate (BUR)
PHYSICAL PERFORMANCE
PROGRAM/ACTIVITY/PROJECT Allotment Released
%
(Amt.
Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
FINANCIAL PERFORMANCE
Annual Target
- endorsed to the Regional Office for comments and/or
endorsement to the DENR Secretary for approval on Oct. 23,
2015
Draft DAO re: establishment of 22.67 ha of mangrove and coastal
areas in San Diego, Lian, Batangas as CH for Marine turtles and
Waterbirds
- endorsed to the Regional Office for comments and/or
endorsement to the DENR Secretary for approval on Dec. 29,
2015
1.1.3 List of Economically Important Plant Species meetings/consultation/ workshop 1 3 300% PPCC meetings conducted:
conducted • March 12, 2015, LOHAS Hotel, Clark, Pampanga.
• July 1-2, 2015, Hotel Dominique, Tagaytay City
• December 3-5, 2015, Kay Hotel & Residences, Tagaytay City
DAO drafted and endorsed 1 on-going 50% The draft list of Economically Important Plant Species was
discussed and reviewed during the PPCC workshop on
July 1-2, 2015 and December 2-4, 2015. A short list of EIPS has
been drafted.
1.1.4 Proposed policy on the registration of raw and/or workshop/ consultation conducted 2 2 100%
worked elephant ivory DAO drafted and endorsed 1 1 100% The draft DAO was endorsed to the DENR for approval on Dec.
18, 2015.
1.1.5 Additional guidelines on the local trasport of wildife, writeshop/workshop/ consultation 2 1 50%
wildlife by-products and/or derivatives for shows, conducted
exhibitions and educaitonal purposes DAO drafted and endorsed 1 1 100% The draft DAO was endorsed to the DENR for approval on Dec. 3,
2015
1.1.6 Proposed guidelines on the issuance of clearance writeshop/workshop conducted 1 1 100% The proposed guidelines was taken up during the NPD Workshop
for wildlife research within Protected Areas DAO drafted 1 1 100% on the Review of E-NIPAS Bill last July 22-24, 2015. The issuance
of clearances for wildlife researches within Protected Areas was
included in the PASU's responsibilities under the E-NIPAS Bill.
Thus, no separate guidelines is necessary.
1.1.7 Proposed DENR Administrative Order (DAO) updating the national consultation conducted 1 1 100%
Threatened Flora List established under DAO No. 2007-01 DAO endorsed 1 1 100%
1.1.8 Policy on Wildlife Emergency Response writeshop/workshop conducted 1 1 100% The draft Joint DA-DENR-DOH Administrative Order for the
DAO endorsed 1 1 100% operationalization of the Philippine Committee on Zoonoses which
includes provisions on reporting system as emergency response
protocol has been reviewed by the DENR-PTWG on 16 Sept 2015.
The draft will be revised to address the PTWG comments in a
joint meeting among representatives from the DA, DOH and
DENR-BMB. The schedule of the meeting is still being arranged
by BMB-WRD with concerned offices of DA and DOH.
The Avian Influenza Preparedness Plan was revised and
The draft DAO was endorsed to TRC for review and approval on
Dec. 29, 2015
Page 20
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 1: ECOSYSTEMS POLICY SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
REMARKAnnual Accomp. % Accomp. Disbursement
% Budget Utilization Rate (BUR)
PHYSICAL PERFORMANCE
PROGRAM/ACTIVITY/PROJECT Allotment Released
%
(Amt.
Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
FINANCIAL PERFORMANCE
Annual Target
updated through a series of consultations among various
agencies (representatives of BAI,BMB, poultry practitioners
and breeders). A public consultation was conducted and
representatives of wildlife breeders and facilities were invited.
The Plan is being circulated and presented in different
regions by BAI before finalization.
1.2 Cave Management Program Policies formulated
1.2.1 2015 List of Classified Caves 1 1 100% DMC 2015-08 signed by the Secretary on Nov 10, 2015 (51 caves
classified for 2015, a total of 415 caves have been classified since
2012.
1.2.2 Protocol on Cave Rescue 1 1 100% On-Site testing of Cave Rescue Protocol accomplished in Luzon
cluster in Sagada, Mt. Province on Nov 9-14, 2015
Cave safety and Rescue Protocol in its final stage of drafting,
incorporating comments from BMB and other concerned agencies.
1.3 Protected Area Management
1.3.1 Philippines National PA System Master Plan PA Master Plan prepared and 1 on-going Conducted refinement of National Protected Area Master Plan
submitted Log frame on 4-5 February 2015 at Brentwood Suites, Quezon City
DAO No. 2015-10 entitled “Guidelines for the Delineation and
Demarcation of PAs under the NIPAS” approved on 29 May 2015
Re-endorsed to Osec the proposed DAO on “Addendum to DENR
AO 2007-17 on the Rules and Regulations Governing Special
Uses within PAs” considering comments on 25 August 2015
1.3.2 Guidelines and Manual on Nature Interpretation Guidelines drafted 1 1 100% To be approved by BMB Director
1.3.3 Updating of Manual on Design of Structures, Facilites, and Guidelines drafted 1 1 100% To be approved by BMB Director
Markers in Protected Areas
1.4 Urban Biodiversity
1.4.1 Development of Urban Biodiversity Strategy and Action Plan Actin Plan drafted 1 1 100% Drafted Procedural Guidelines for Urban Biodiversity
Inventory/Assessment
1.4.2 Compilation /identification of Existing Management no. of documents reviewed/compiled updating/reviewing of existing list of partner institutions/offices
'Partnership Scheme in Priority Caves/Wetlands and other /agencies for caves completed; on-going for wetlands and
'Ecosystem other ecosystems
1.4.3 Training Needs analysis/assessment for Regional TNA reports submitted /trainings 2 2 100%
counterpart/ concerned division identfied/workshops/mtng held
2. Review of guidelines, policies, regulations, resolution,
bills, etc
2.1 Review of research/project proposals and preparation of
research permits/ implementation instruments
proposals on wildlife reviewed 4 8 200% Reviewed the following Wldlife proposals:
1) Proposals of Avilon Wildlife Conservation Foundation under its
Avilon Montalban Project: Biodiversity Survey of Pamitinan
Protected Landscape, Rizal, Philippines;
moving target
Page 21
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 1: ECOSYSTEMS POLICY SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
REMARKAnnual Accomp. % Accomp. Disbursement
% Budget Utilization Rate (BUR)
PHYSICAL PERFORMANCE
PROGRAM/ACTIVITY/PROJECT Allotment Released
%
(Amt.
Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
FINANCIAL PERFORMANCE
Annual Target
2) Proposals of Avilon Wildlife Conservation Foundation under its
Avilon Montalban Project: Biology and Ecology of Varanus
olivaceus in Pamitinan Protected Landscape, Rizal, Philippines;
3) Proposal of Malaysia for the downlisting of the State of
Sarawak’s population of Saltwater Crocodile/Indo-Pacific
Crocodile (Crocodylus porosus) from CITES App. I to App. II;
4) Proposed Executive Order - "Providing for the Exploration,
Conservation, Protection and Sustainable Use of Plant Genetic
Resources for Food and Agriculture, Appropriating Funds
Thereafter and For Other Purposes";
5) Proposal re: Exploratory Talk on Possible Collaboration with
Brunei on Environmental Protection;
6) Proposed Philippines-France Joint Economic Committee
Communique;
7) Proposed DA-DENR Joint AO re:Mainstreaming Biodiversity-
Friendly Agricultural Practices in and around Protected Areas &
Key Biodiversity Areas and Promoting the same in Wider
Agricultural Landscapes.
8) Proposal of South Africa re: Trade of Rhino Horn by CMA
South Africa
MOA/MOU concerning wildlife prepared 4 10 250% Prepared the following MOA/MOU:
1) Diversity, Ecology and Long-Term Population Dynamics of
Philippine Bat Communities
2) Investigations into the Taxonomy , Diversity and Ecology of
Mangrove Oomycetes in the Philippines
3) Scientific Investigation on Rice-Associated Wild Fauna and
Flora for Research Advancement and Biodiversity Conservation
4) Cultivation of Rafflesia for Ex-situ Conservation
5) Biodiversity Research, Education Outreach and Conservation
Genetics of Philippine Amphibians, Reptiles and Invertebrates
6) Comparative Biogeography and Conservation of Philippine
Vertebrates (renewal)
7) Scientific Survey of the Streaked Reed Warbler
(Arcrocephalus sorghophilus) and othe Bird Species in the
Philippines8) Collaborative Program for the Conservation of the Philippine
Cockatoo: The Singapore Project
9) Ecology and Biogeography of Southeast Savanna in the
Philippines
10) Philippine Crocodile conservation breeding and Public
Education Purposes
GP issued 4 17 425% Issued the following Gratuitous Permits:
Page 22
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 1: ECOSYSTEMS POLICY SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
REMARKAnnual Accomp. % Accomp. Disbursement
% Budget Utilization Rate (BUR)
PHYSICAL PERFORMANCE
PROGRAM/ACTIVITY/PROJECT Allotment Released
%
(Amt.
Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
FINANCIAL PERFORMANCE
Annual Target
1) Wildlife GP No. 237 approved Feb 3, 2015
Title of Research: Academic Research "Screening Mycelial
Extracts of Airborne Fungal Spores for Wound Healing and
Regeneration Properties of Schmidtea mediterranea "
2) Widlife GP No. 239 approved Feb 6, 2015
Title of Research: Conduct a nationwide benchmarking of all the
NGP Planting sites in 15 Regions for 2015 under the DENR-NGP
3) Wildlife GP No. 238 approved Feb 17, 2015
Title of Research: Field inventory of natural conservation of
Philippine land vertebrates: Training, Resource Development and
Research
4) Wildlife GP No. 240 approved Mar 16, 2015
Title of Research: Biodiversity Indicators for Sustainable LAnd
Use in Luzon, Philippines
5) Wildlife GP No. 241 approved May 5, 2015
Title of Research: Blood and Gastrointestinal Parasites of Captive
Long-Tailed Macaque 6) Wildlife GP No. 242 approved Jun 11, 2015
Title of Research: Cultivation of Rafflesia for Ex-situ conservation
7) Wildlife GP No. 243 approved Jun 15, 2015
Title of Research: Investigation into the Taxonomy, Diversity and
Ecology of Mangrove Oomycetes from the Philippines
8) Wildlife GP No. 244 approved Jul 20, 2015
Title of Research: Phylogeny of Philippine Guoia Cav.
(Sapindaceae): Inferred from Morphological and molecular
sequence data
9) Wildlife GP No. 245 approved Jul 27, 2015
Title of Research: PA Management Enhancement in the Phil.
10) Wildlife GP No. 246 approved Jul 30, 2015
Title of Research: Comparative Biogeography and Conservation
of Philippine Vertebrates
11) Wildlife GP No. 247 approved Jul 30, 2015
Title of Research: Biodiversity Research, Education Outreach,
and Conservation Genetics of the Philippine Amphibians, Reptiles
and Invertebrates
12) Wildlife GP No. 236 approved Nov 20, 2015 (amended per
letter dated Oct 15, 2015)
Title of Research: movement Ecology of Philippine Birds of Prey
13) Wildlife GP No. 238 approved Sep 1, 2015
Title of Research: Scientific investigation on Rice-associated wild
fauna and flora for research advancement and biodiversity
conservation
14) Wildlife GP No. 249 approved Oct 22, 2015
Title of Research: Sex Determination by Chromodomain-Helicase-
DNA (CHD) Binding Gene Detection in Africal Lovebirds
(Agapornis roseicollis) using blood and buccal swabs
15) Wildlife GP No. 250 approved Oct 23, 2015
Title of Research: Wildlife Forensics and DNA Barcoding of Native
Flora and Fauna of the Philippines
16) Wildlife GP No. 251 approved Nov 5, 2015
Title of Research: Enhancement of Philippines' research capability
in understanding the role of Mangrove ecosystem health in the
Adaptation and mitigation against natural disasters
17) Wildlife GP No. 252 approved Nov 16, 2015
Title of Research: Movement Ecology of Philippine Birds of Prey
2.2. Review of Wildlife policies/bills policies/bills drafted/reviewed 8 17 213%
Page 23
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 1: ECOSYSTEMS POLICY SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
REMARKAnnual Accomp. % Accomp. Disbursement
% Budget Utilization Rate (BUR)
PHYSICAL PERFORMANCE
PROGRAM/ACTIVITY/PROJECT Allotment Released
%
(Amt.
Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
FINANCIAL PERFORMANCE
Annual Target
2.3 Review/ evaluation of PA management policies/ bills Bills related to PA management 30 79 263%
reviewed
Resolutions on PA management 8 5 63% Provided comments on the ff. Senate Resolutions:
reviewed 1) Resolution No. 2015-15 of Anticala Tribal Council of Elders
and Leaders' Association requesting assistance for the
rehabilitation of its ancestral domain
2) SRN 109 - Resolution Directing Proper Senate Committee to
Conduct Inquiry on the Reported need to Protect and Preserve
Previously Declared Sanctuaries in the Country (LPPACHEA)
3) SRN 720 - Resolution Directing Conduct of Inquiry to Seek
Effective Protection Mechanisms for Tubbataha Reefs NP
4) Resolution No. 256, series of 2015, requesting the BMB thru
the Director Theresa Mundita S. Lim to Reconsider the Position
and Findings regarding the proposed Establishment of Engineered
Sanitary Landfill at Tapak, Ampucao, Itogon, Benguet
5) Sangguniang Panlalawigan Resolution No. 12007, S2015 -
urgently requesting DENR for the lifting of the suspension of
granting of Special Use Agreement in PA (SAPA) Specific Projects
in the Province of Palawan being Prime Ecotourism Destination
3. Programs/Projects Monitoring and Supervision
3.1 Supervision/Implementation and/or assistance in the No. of reports prepared/submitted
implementation of the following FAPs: No. of meetings attended
c.1 NewCAPP Submitted to UNDP 1st to 3rd Quarter Repot for CY 2015 and
requested downloading of the 4th Qtr. CY 2015 UNDP-GEF
Project Fund
c.2 PAME Attended the following workshops/meetings under PAME Project:
Luzon, Visayas and Mindanao Clusters Validation Workshop for
the assessment of Organizational Development and Training
Needs of DENR on Biodiversity Management;
3 - Project proposals reviewed;
9 - Meetings attended
d.3 BPP 5 - meetings attended
d.4 NBSAP/BIOFIN PBSAP finalized 1 1 100%
d.5 REDD+ (UN and GIZ) 7 - Meetings attended
d.6 B-WISER 3- TWG Mtg. & Mid Term Eval. Mtg.
1- B+WISER Training on SMART-Lawin
d.7 TEEB
d.8 WAVES Participated Training on CORVA
d.9 SGP5
d.10 MKBA
d.11 APFP-SEApeat
d.12 INREMP 2 - Orientation-Trainings attended
d. 13 PHILCAPP Attended/Co-organized the ff:
1) Presentation and review of the Penablanca PLS and Siargao Is.
PLS Management Plan held in February 2015;
2) Protected Area Conference held on 9-11 Nov. 2015 at Twin
Towers, Ortigas Center
as necessary
Page 24
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 1: ECOSYSTEMS POLICY SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
REMARKAnnual Accomp. % Accomp. Disbursement
% Budget Utilization Rate (BUR)
PHYSICAL PERFORMANCE
PROGRAM/ACTIVITY/PROJECT Allotment Released
%
(Amt.
Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
FINANCIAL PERFORMANCE
Annual Target
d.14 Forest Management Program 4 - Meetings/Workshops attended; conducted monitoring of FMP
site
d.15 National Wealth Creation Program
d.16 ASEAN Heritage Park 1 - Meeting attended
Nominated Mt. Timpoong Hibok hibok NM for the ASEAN Heritage
Parks Programme;
Reviewed WFPs of the Five (5) AHP sites for CY 2016; And Mt.
Makiling FR for 2015
Launching of Tubbataha as AHP (Nov 3-4,2015)
Transmitted to Regions 11 and 4-B the Certificates of Declaration
of Mt. Hamiguitan Range WS and Tubbataha Reefs NP as
ASEAN Heritage Parks.
3.2 Monitoring/assessment/implementation of Regions/sites visited 13 15 115%
PAWCZMS programs and projects Field Reports submitted 13 15 115%
4. Preparation/consolidation/review of work and Work and Financial Plan prepared 2 2 100%
financial plans and submitted to DENR/DBM
5. Review/evaluation and preparation of draft policies, Proposal/cases/policies/ MOA
cases, proposals, MOA, etc reviewed/prepared
Document prepared/submitted
6. Conduct of regular conference/meetings Conference/Meetings conducted
- PAWCZM Sectoral Conference/Meeting Minutes/Documents prepared/
- Assessment & Planning Workshops submitted 1 1 100%
- Senior Staff Meetings 7 7 100%
- Technical Review Committee Meetings 7 7 100%
7. Review and consolidation of accomplishment reports No. of bureau reports prepared/
a. Quarterly Reports submitted to DENR/DBM/COA 4 4 100%
b. Annual Report 1 1 100%
8. Participation to the following committees/ TWGs/bodies: Documents/reports prepared and
submitted
a. ASEAN Working Group on Nature Conservation and Meetigns attended
Biodiversity (AWGNCB)
b. ACB
c. DENR-NPC TWG
d. Mining Forest Program
e. National Greening Program TWG
f. Joint DENR-DOE TWG
g. Sub-Com on Land and Water under CCMRD-PCSD
h. DBM/Senate/Congress Budget Hearings
i. Planning Workshops
j. Others (BAC-TWG, GAD, UNDP, PCSD, etc)
moving target
moving target
as necessary
moving target
Page 25
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 1: ECOSYSTEMS POLICY SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
REMARKAnnual Accomp. % Accomp. Disbursement
% Budget Utilization Rate (BUR)
PHYSICAL PERFORMANCE
PROGRAM/ACTIVITY/PROJECT Allotment Released
%
(Amt.
Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
FINANCIAL PERFORMANCE
Annual Target
10. Capacity Building
a. Basic Skills on Photo and Video Documentation Training conducted 1 1 100%
b. In-house Education Program Number of sessions undertaken 25 Deferred due to delay in hiring of permanent employees
Number of pax 375 Deferred due to delay in hiring of permanent employees
c. Conduct of the "5th Training of Trainers on the
Application of the Wildlife Law Enforcement Training conducted (no.) 1 1 100%
Manual of Operations" Report prepared and submitted to
the agency head
1 1 100%
d. Training for PA Master Plan Training conducted 1 1 100% Conducted refinement of National Protected Area Master Plan
Log frame on 4-5 February 2015 at Brentwood Suites, Quezon
City
e. National PAMB Summit 1 1 100%
f. National PA Conference 1 National PA Conference moved to February 2016
g. Training on Management/Business Planning 1 1 100% Conducted Protected Area Business Planning Orientation-
Workshop held on 12-13 November 2015 at Icon Hotel, Quezon
City
h.Capacity Building on Basic Caving skills and Cave Rescue
(outsource)
1 1 100%
i. Cave Congress Congress facilitated
11. Provision of Technical Assistance on various programs Assistance rendered
projects on biodiversity cosnervation and management Institutions assisted
moving target
Conducted ToT5 on 7-11 September 2015 at the City State
Asturias Hotel, Puerto Prinsesa City, Palawan. A total of 69
participants composed of representatives from DENR Regionsn1
ti CAR, NBI, DOJ, Bureau of Customs, LGUs of Region 6, PPA,
PCSDS, PNP-CIDG in Palawan, Bantay Palawan Task Force,
PNP-AVSE Group, Puerto Prinsesa Subterranean River National
PArk, AFP-WESCOM and Philippine Navy attended the training.
National PAMB Summit held last July 13-14, 2015 at Ace Hotel,
Pasig City
Page 26
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 2: ECOSYSTEMS MANAGEMENT SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
MFO 2: ECOSYSTEMS MANAGEMENT SERVICES 69,724,000 65,009,850 93% 59,207,038 43,903,737 85% 74%
1. Protected Area Establishment and Management
1.1 NIPAS Establishment/Disestablishment No. of PAs endorsed 5 Moving Target. Reviewed reports on the proposed
withdrawal/disestablishment of the ff:
1) Mt. Data National Park (portion only);
2) Lower Agno WFR (CAR);
3) Roosevelt PL (proposed exclusion of Brgy.
Roosevelt)
Reviewed reports of proposed Presidential
Proclamation of the ff. PAs:
1) Bulabog-Putian NP;
2) Lake Buluan NP;
3) Koronadal Watershed Area;
4) Hinabian-Lawigan WFR;
5) Bantayan Island WA (portion)
No. of Bills endorsed for
filing/refiling
17 107 629% 107 HBs/SBs - Provided comments
(SBN 2712 - Expanded NIPAS Act (96 Protected
Areas and 1 Critical Habitat) approved in the 3rd
Reading of the Plenary at the Senate; HBN 4336 -
Enhanced NIPAS Act passed in Committee Level
(101 PAs);
1. Bataan-Subic (R-3) Including individual PA Bills: HB No. 1941 - Bantayan
2. Aurora Integrated PA HB No. 5041 - Liddlida-Banayoyo Protected
3. El Nido MRPA (R4-B) Landscape; HB No. 5785 - Mt. Calavite Wildlife
4. Malampaya PLS (R-4B) Sanctuary; HB No. 2713 re reversion of original area
5. Apo Reef (R-4B) of Biak-na-Bato NP
6. Mt. Guiting-Guiting NP (R4B)
7. Northwest Panay NP (R6)
8. Northern Negros NP (R6)
9. Samar Island NP (R-8)
10. Turtle Islands WS (R-9)
11. Tagub-Kampalili (R-11)
12. Mt. Balatukan Range NP (R10)
13. Mt. Hilong-Hilong Range (R13)
14. Siargao IPLS (R-13)
15. Agusan Marsh WS (R13)
16. Maulawin Spring PL (R4A)
17. Pamitinan PL (R4-A)
1.2 NIPAS Management
a. PAMB Organization and Strengthening Name of CAs processed 22 62 282% 39 CAs Endorsed to Osec;
23 approved CAs Forwarded to the Regional Offices
b. PAMB Operationalization No. of Resolutions 28 103 368%
reviewed
PROGRAM/ACTIVITY/PROJECT Released
%
(Amt. Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
PHYSICAL PERFORMANCE FINANCIAL PERFORMANCE
REMARKDisbursement
% Budget Utilization Rate (BUR)
Annual Target Annual Accomp. % Accomp. Allotment
Page 27
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 2: ECOSYSTEMS MANAGEMENT SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
PROGRAM/ACTIVITY/PROJECT Released
%
(Amt. Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
PHYSICAL PERFORMANCE FINANCIAL PERFORMANCE
REMARKDisbursement
% Budget Utilization Rate (BUR)
Annual Target Annual Accomp. % Accomp. Allotment
No. of Minutes of Meeting 74 25 34%
reviewed
c. IPAF Establishment/Operation No. of SBR endorsed 16 22 138%
No. of collection reports 24 33 138% IPAF collection reports:
reviewed - Mt. Malindang (2)
- TVPL (3)
- Initao
- Region 5 (2)
- Jose Rizal MPL (2)
- Turtle Island
- Apo Reef NP
- Mt. Guiting-Guiting
- including collection reports of PAs with SBR (20)
d. PA Management Plans prparation/updating No. of MPs reviewed 12 5 42% Reviewed Community Resource Management Plan
of:
- 1 brgy. Of Mr. Calavite WS;
- Ecotourism Management Plan of Marinduque WS;
- PAMP-Bantayan Island Wilderness Area;
- Penablanca PLS;
- Siargao Island PLS
No. of PAs with management 4 Moving target
zones delineation reports
reviewed
d,1 PA Business Plans preparation (outsource) No. of Business plan 3 on-going Conducted PA Business Planning Orientation-
prepared Workshop held on Nov. 12-13, 2015 at Icon Hotel,
a. Kalbario-Patapat NP QC (30++ PAs assisted)
b. Balinsasayao Twin Lakes NP
c. Agusan Marsh WS
d.2 Monitoring of Implementation of 20 BPs No. of reports submitted 21 on-going Requested Regional Offices updates on the adoption
of the BPs of the following PAs already presented to
their respective PAMBs:
- Mt. Banahaw-San Cristobal PL (R4A)
- Mt. Apo NP (R11)
- Naujan Lake (R4B)
Requested DENR CALABARZON Region updates on
the presentation of BPs of Mts. Palay-Palay/Mataas-
na-Gulod PL
No. of MEA reports 8
reviewed
e. PA Restoration No. Of accomplishment 15 on-going
reports reviewed
No. of PAs monitored/ 15
validated
Page 28
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 2: ECOSYSTEMS MANAGEMENT SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
PROGRAM/ACTIVITY/PROJECT Released
%
(Amt. Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
PHYSICAL PERFORMANCE FINANCIAL PERFORMANCE
REMARKDisbursement
% Budget Utilization Rate (BUR)
Annual Target Annual Accomp. % Accomp. Allotment
f. PA Community-Based Resource Management
Agreement (PACBRMA)
Reviewed PACBRMA applications of 31 People's
Organizations within the Municipalities of
Pantabangan-Carranglan, Nueva Ecija
g. Boundary delineation and demarcation
1. Field Monitoring No. of monitoring reports 20 4 20% Conducted validationof boundaries in the ff. PAs:
reviewed and validated 1) Baliangao PL - Dec. 1-5, 2015
2) Pasonanca NO - Dec. 7-11, 2015
3) Great and Little Sta. Cruz Island PLS - Dec. 7-11, 2015
4) Bantayan Island WA
2. Presentation of Field Monitoring
Results and Year-End Assessment No. of monitoring results 1 1 100%
of Accomplishments presented
3. Conversion (Digital) of PA/NIPAS Map
a) Scanning and Archiving No. of scanned Map 48
b) Plotting, Digitizing, and integration
c) Coordination/Meeting/consultaiton with
PAWB re results of validation
4. Salary of Contractuals Personnel hired 2 2 100% Contracted 2 personnel (GIS Specialist)
- 15 Personnel (for NAMRIA)
- 2 Personnel (for PAWB)
1.3 Monitoring of NIPAS Implementation No. of monitoring reports 28 5 18% Conducted monitoring of NIPAS Implementation in the
ff. Regions:
- DENR Region 4-A - Aug. 17-19, 2015; Sept. 17-19,
2015;
- DENR, Region 10 - December 1-5, 2015;
- DENR, Region 6 - December 7-11, 2015;
- DENR Region 9 - December 7-11, 2015
- DENR Region 11 – May 2015
1.4 Management of Local Conservation Areas (LCAs) *Activity not included in the budget ceiling
a. Strengthening of policy and institu- LGU Resolution/Ordinance of the Division
tional support for implementation of
LCA Management Plans
b. Initial implementation of LCA Business plans initially
Business Plans implemented
1.5 Management of Indigenous Communities
Conservation Areas (ICCAs) •Attended Consultation Meeting regarding ICCAs at
DSWD Central Office, Quezon City held on 27
a. Integration of CCPs in CLUPs, FLUPs CCPs integrated in CLUPs February 2015;
and other related Environmental FLUPs and other Envtl. •Organized the Philippine ICCA Inception Wokshop
Management Plans Plans held on Dec. 3-4, 2015 at Tagaytay Highlands
b. Initial implementation of CDP Business Business plans initially
Plans implemented
Page 29
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 2: ECOSYSTEMS MANAGEMENT SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
PROGRAM/ACTIVITY/PROJECT Released
%
(Amt. Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
PHYSICAL PERFORMANCE FINANCIAL PERFORMANCE
REMARKDisbursement
% Budget Utilization Rate (BUR)
Annual Target Annual Accomp. % Accomp. Allotment
2. Ecotourism Development Program
2.1 Development and maintenance of Makiling Site developed 1 1 100%
Forest Reserve
2.2 Monitoring of 2014 priority ecotourism sites PAs monitored 6 11 183% Monitored the following sites:
1) Olango Island Wildlife Sanctuary
2) Balinsasayao Twin Lakes NP
3) Siargao islands PLS
4) Paoay Lake NP
5) Central Cebu PL
6) Quezon NP
7) Alibijaban Island WA
8) Buenavista PL
9) Mt. Pulag NP
10) Kalbario-Patapat NP
11) Bataan NP
Dinagat Islands was also monitored as a potential
priority ecotourism site.
Reports submitted 6 9 150%
2.3 Hosting of Ecotourism Council meetings Meetings conducted 8 11 138% Meetings of the NESC (3) and ETWG (8)
conducted/participated in
3. Cave Management and Conservation Program
3.1 Conduct of National Caving Congress Congress facilititated 1 1 100% Conducted the 15th National Caving Congress last
April 20-25, 2015 at Surigao City
3.2 Operation of the National Cave Committee Meetings conducted 4 2 50% 19th NCC meeting w/ quorum held on Nov 24, 2015
19th NCC meeting w/o quorum last Aug 11, 2015
- overlap schedule among NCC members but NCC
agreements achieved (re-set to Nov. 24, 2015)
3.3 Monitoring of Selected/Priority Classified Caves Regions monitored 6 7 117% Priority classified caves geotagged and monitored in
the ff. regions:
Reports submitted 6 7 117% 1) Regions 4B (3)
2) Region 9 (1)
3) Region 10 (11)
4) Region 12
5) Region 3
6) Region 6
7) Region 11
3.4 Preparation of Strategic Action Plan Action Plan prepared 1 on-going Drafted action plan; presented during NCC meeting;
updating of actiohn plan conducted
4. Wetland Management and Conservation Program
4.1 Orientation-workshop on inland wetlands Workshop conducted 2 3 150%
Proceeding prepared 2 3 150%
1) Visayas (Regions 6 to 8)
Tied up with the Orientation and Consultation-
Workshop for the "GIS-Based Mapping and Geo-
tagging of Inland Wetlands and Caves" which were
conducted for:
Page 30
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 2: ECOSYSTEMS MANAGEMENT SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
PROGRAM/ACTIVITY/PROJECT Released
%
(Amt. Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
PHYSICAL PERFORMANCE FINANCIAL PERFORMANCE
REMARKDisbursement
% Budget Utilization Rate (BUR)
Annual Target Annual Accomp. % Accomp. Allotment
2) Mindanao (Regions 9 to ARMM)
3) Luzon Island Provinces
4.2 Assessement of NWAPP implementation Meetings /workshop conducted 4 2 50%
4.3 Philippine Wetlands Conservation Awards Announcmt
4.4 Review of wetland assessment reports no. of reports reviewed 4 5 125% Reviewed and acknowledged the submitted
assessment reports of the ff. regions:
1) Region 3 (Paitan Lake at Cuyapo, Nueva Ecija)
2) Region 4B (Walang Langit Falls in Gloria, Oriental
Mindoro)
3) Region 4A (Calibato Lake located in San Pablo
City and Rizal, Laguna)
4) Region 11 (Hagimit Falls at the Island Garden City
of Samal)
5) Region 4A (Tadlac Lake located at Los Baños,
Laguna)
4.5 Validation/mapping of inland wetlands Priority inland wetlands
mapped/validated
2 6 300% Completed/accomplished geotagging and
validation/mapping of inland wetland maps of selected
provinces in Visayas and Mindanao (Regions 7, 9, 10,
11, 13) and Region 4B (Palawan)
4.6 Operation of the Interim National Wetland Meetings /workshop conducted 4 1 25%
Conservation Committee
4.7 Monitoring of selected priority wetlands Regions monitored 6 7 117% Selected priority caves monitored in the ff. regions:
1) Regions 4B
2) Region 9
3) Region 10
4) Region 12
5) Region 3
6) Region 6
7) Region 11
Accomplished field monitoring of the proposed
Ramsar sites:
1) Negros Occidental Coastal Wetlands
2) Agusan Marsh Wildlife Sanctuary
4.8 Implementation of the Philippine component - Project monitoring report 4 4 100%
ASEAN-Peatland Forest Project-SEApeat submitted
4.9 Participation to Ramsar convention/workshops Report submitted 1 100% Participated in 12th Meeting of the Conference of
Contracting Parties of the Ramsar Convention on
Wetlands (COP12) in Uruguay on June 1-9, 2015;
report was submitted to Osec, USFO, and USPP.
5. Management of the Ninoy Aquino Parks and
Wildlife Center
5.1 Park Management and Administration
a. Park Maintenance Administration
1.1 Security Services (22 guards) Security Agency Hired 1 1 100%
1.2 Park Maintenance and other Allied Services Manpower Agency Hired 1 1 100%
Page 31
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 2: ECOSYSTEMS MANAGEMENT SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
PROGRAM/ACTIVITY/PROJECT Released
%
(Amt. Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
PHYSICAL PERFORMANCE FINANCIAL PERFORMANCE
REMARKDisbursement
% Budget Utilization Rate (BUR)
Annual Target Annual Accomp. % Accomp. Allotment
b. Maintenance of Park Facilities Facilities maintained
1.1 Animal Cages
1.2 Toilets
1.3 Fishing Village
1.4 Tea House
1.5 Amphitheatre
1.6 Roads/Pathwalks
5.2 Packet landscaping in selected areas at NAPWC Square Meter 1000 750 75%
5.3 Renovation of Old PAWB Building No.1 to house the Building renovated (no) 1 on-going
' Protected Area Gallery/Museum
MONITORING OF THREATENED SPECIES CONSERVATION
AND MANAGEMENT PROGRAMS
1. Monitoring of threatened species conservation Monitoring reports reviewed/evaluated 48 131 273% 1. Philippine Cockatoo Conservation Program (PCCP)
and management programs Highest Count of Phil. Cockatoo Sighting per area,
( Crocodile, Philippine Eagle, Tamaraw, Pawikan, May 2015:
Dugong, Phil Cockatoo, Phil Tarsier, Flying Fox) a) Omoi and Manambaling Cockatoo Reserves,
Dumaran, Palawan - 8 heads (Manambaling area)
b) Rasa Island, Narra, Palawan - 194 heads
c) Pandanan Island, Balabac, Palawan - 156 heads
- 14 reports were submitted as of June 2015
June 2015:
a) Omoi and Manambaling Cockatoo Reserves,
Dumaran, Palawan - 12 heads (Lagan area)
b) Pandanan Island, Balabac, Palawan - 213 heads
- 2 reports were submitted in September 2015
August 2015:
a) Pandanan sland, Balabac, Palawan - 228 heads
b) Omoi and Manambaling Cockatoo Reserves,
Dumaran, Palawan - 16 heads (Lagan area)
- 2 reports were submitted in October 2015
2. Tamaraw Conservation Program (TCP)
- Actual Tamaraw Population Count for CY 2015
405 heads
- 2 reports were submitted as of June 2015
- Provided assistance during 2ng Meeting for the
Preparation of the Tamaraw Month in Oct 2015 at
BMB Conference Rm., NWRRC Bldg., on
September 4, 2015.
3. Philippine Eagle (6 reports evaluated)
- Participated in the release of rehabilitated
Philippine eagle "Pamana" at Mt. Hamiguitan
Range Wildlife Sanctuary on June 11-12, 2015
4. Pawikan Conservation - 134 reports evaluated
5. Dugong Conservation - 1 report evaluated
Sites monitored 9 9 100% 1. Tamaraw
- Mts. Iglit-Baco Natural Park (1 report)
2. Philippine cockatoo
Page 32
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 2: ECOSYSTEMS MANAGEMENT SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
PROGRAM/ACTIVITY/PROJECT Released
%
(Amt. Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
PHYSICAL PERFORMANCE FINANCIAL PERFORMANCE
REMARKDisbursement
% Budget Utilization Rate (BUR)
Annual Target Annual Accomp. % Accomp. Allotment
- Dumaran, Palawan (1 report)
- Rasa Island, Narra, Palawan (1 report)
- Pandanan Island, Balabac, Palawan (1 report)
3. Marine turtles
- Morong, Bataan (Anvaya Cove) (1 report)
- Naic, Ternate, Rosario & Noveleta in Cavite
(4 reports)
Distribution maps updated 8 2 20%
Priority species' population status 8
updated
2. Updating of existing conservation plans Experts/consultations workshops
conducted
3 3 100% Experts' Meeting to Review the First Draft of the
"Conservation and Management Plan for the
Crocodilian Species in the Philippines" was held on
April 10, 2015 at BMB Conference, NWRRC Bldg.
NAPWC, QC
Stakeholders' Workshop to Review the Draft
"Conservation and Management Plan for the
Crocodilian Species in the Philippines" was held on
August 6-7, 2015 at ICON Hotel, QC. This workshop
was attended by participants from DENR-Regions 2,
11, and CARAGA, PCSDS, CPPI, Philippine National
Museum, PWRCC, Manila Zoo, Mabuwaya
Foundation, Avilon Zoo, SUAKCREM and University
of Southern Mindanao.
The Philippine Eagle Working Group Meeting was
held last Nov. 10, 2015 at BMB Conference, NWRRC
Bldg. The Meeting discussed the updates on the draft
Philippine Eagle Loan Protocol and PEWG Resolution
adopting the said Protocol and updates on Philippine
Eagle Conservation Program
Conservation plans printed/prepared 300
3. Development of Framework Plan for the Conservation and
Management of Threatenes Species
Consultation Workshops conducted 3 1 33% Conducted Training-Workshop on Flying Fox
Conservation and Management last August 18-20,
2015 in Subic, Zambales. A total of 30 participants
composed of technical personnel from the
Conservation and Development Division of DENR
Regional/Field Offices and 2 participants from SBMB-
Ecology Center attended the training. The output of
the training is the proposed action plan which was
cohesively prepared by the participants.
Framework Plan developed 1 1 100% Framework Plan for Flying Fox conservation and
management developed
4. Conduct of site and population assessments for
certain threatened species
Consultation Workshops conducted 1 1 100% Consultation with the experts was conducted during
the training-workshop held last August 18-20, 2015
Page 33
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 2: ECOSYSTEMS MANAGEMENT SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
PROGRAM/ACTIVITY/PROJECT Released
%
(Amt. Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
PHYSICAL PERFORMANCE FINANCIAL PERFORMANCE
REMARKDisbursement
% Budget Utilization Rate (BUR)
Annual Target Annual Accomp. % Accomp. Allotment
5. Asian Waterbird Census (AWC) National AWC report submitted to
Wetland International
1 1 100% National AWC report was submitted to Wetland
International November 2015
- Coordination of the conduct AWC and and consolidation of
Regional reports
6. Establishment and management of Critical Habitats (CH)
- Review of documents from the Region Propossals reviewed.evaluated 6 7 117% Reviewed/evaluated the documents submitted by the
following Regional Offices:
Region 4
- Brgy. Sawang Lobo, Batangas
Region 5
- Mt. Guinatungan in San Lorenzo Ruiz, Camarines
Norte (Oct 2015)
- Mt. Nagsurok Cave in Prieto Diaz, Sorsogon (Oct
2015)
Region 3
- migratory birds (August 3, 2015)
Region 4B
- Ilin Island, Occidental Mindoro as CH (Aug 3, 2015)
- Ambulong Island, Occidental Mindoro as CH (Aug 3,
2015)
- So. Ariston, Brgy. Poblacion, Malungon, Sarangani
Province CH
- Review of CH Management Plans CHMP reviewed/evaluated 2 on-going The proposed DAO for establishment of the two (2)
a. Hinatuan Bay CH areas as Critical Habitats are still at DENR Central
b. Golden-crowned Flying Fox and Giant Flying Fox CH Office for approval.
- Monitoring of established CH Reports submitted 5 5 100% 5 Critical Habitats monitored:
a. Rafflesia schandenbergiana CH - Malasi Tree Park and Wildlife Sanctuary CH
b.Cabusao Wetland CH Cabagan, Isabela
c. Malasi Tree Park and Wildlife Sanctuary - Carmen CH, Agusan del Norte
d. Carmen CH - Cabusao Wetlands, Camarines Sur
e. Adams Wildlife CH - Adams Wildlife CH
- Rafflesia schandenbergiana CH
7. Operation of Palawan Wildlife Rescue and Conservation
Center
No. of crocodiles maintained 1162 1640 141% Maintaining a total of 1,640 heads of Crocodile at
PWRCC, to wit:
C. mindorensis - 1,075 heads
C. porosus - 565 heads
Site and population assessments 3 4 133% Conducted monitoring in the ff:
conducted 1) Siargao Isldand PLS - Jul 27-30, 2015
2) Brgys. Taratak and Sumbiling, Bataraza, Palawan -
Oct 13-20, 2015
3) Brgys. Panalingaan and Canipaan, Rizal, Palawan
- Oct 13-20, 2015
4) Brgy. Maasin, Quezon, Palawan - Oct 13-20, 2015
No. of other animals maintained 458 730 159% For CY 2015, a total of 130 heads of thor animals are
being maintained at PRCC, such as:
Mammals - 35 heads
Avians - 218 heads
Reptiles - 477 heads
Page 34
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 2: ECOSYSTEMS MANAGEMENT SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
PROGRAM/ACTIVITY/PROJECT Released
%
(Amt. Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
PHYSICAL PERFORMANCE FINANCIAL PERFORMANCE
REMARKDisbursement
% Budget Utilization Rate (BUR)
Annual Target Annual Accomp. % Accomp. Allotment
8. Biodiversity Monitoring System (BMS)
- Review and evaluation of BMS reports submitted by Reports evaluated 58 35 60%
the Regional Office
- Field validation/monitoring of BMS sites Monitoring reports 16 16 100%
- Data validations and analysis through PAWB BMS Workshop/meetings organized 4 3 75% 3 Meetings/writeshops were conducted, to wit:
Core Group workshops/ reports submitted 4 3 75% 1) BMS Core Group Meeting, Jan 14, 2015 -
NWRRC Bldg. NAPWC
2) BMS Information Data Analysis and Consolidation
Writeshop, Feb 2-5, 2015 - Eurotel, Baguio
3) The Core Group met last May 20, 2015 at BMB
Conference Room, NWRRC re: updates on the
agreements during the BMS Data Analysis and
Consolidation Writeshop last Feb 2015
9. Wildlife Rescue Center (WRC)
- Captive animal management and maintenance no. of animals rehabilitated and 1000 2,982 298%
maintained
- Animal daignostic and forensic activities No. of laboratory exams conducted 60 120 200%
No. of forensic exams conducted 24 105 438%
no. of animals vaccinated 90 128 142%
- Disposition of rehabilitated animals No. of release sites assessed 6 1 25%
- Facility improvement (cages in public viewing and No. of animals released 82 82 100% 82 species released:
quarantine area) a) Released at Angat Watershed
- 5 Philippine eagle owls
b) Released at NAPWC
- 9 common wolf snake
- 10 Philippine scops owl
- 4 brown hawk owl
- 19 common rat snake
- 1 moorhen
- 2 white breasted swamphen
- 12 night heron
- 1 whiskered pitta
- 1 Red-billed pitta
- 1 Ruddy-breasted Crake
- 1 Slaty-legged Crake
- 3 yellow bittern
- 1 tokay gecko
- 1 barred rail
- 1 bush hen
- 3 night jar
- 3 blood sucker lizard
- 1 flying lizard
- 2 monitor lizard
c) Released at Nagbalayong, Morong, Bataan
- 1 hawksbill turtle
No. of cages repaired 24 16 67%
no. of cages/boxes purchased 30 30 100%
Page 35
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 2: ECOSYSTEMS MANAGEMENT SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
PROGRAM/ACTIVITY/PROJECT Released
%
(Amt. Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
PHYSICAL PERFORMANCE FINANCIAL PERFORMANCE
REMARKDisbursement
% Budget Utilization Rate (BUR)
Annual Target Annual Accomp. % Accomp. Allotment
- Pilot-testing of WRC Manual of Operations No. of assessment reports 1 Assessment report will be submitted at the end
generated of the year
- Preparation of Development Plan for wildlife Plan prepared 1 TOR was prepared but funds for WRD operations was
facilities at NAPWC (lay-out) reduced by Php 2M this year; will push if savings permit
- Monitoring of Regional Wildlife Rescue Centers and
other wildlife facilities holidng wildlife from WRC
Monitoring reports submitted 6 7 117% This includes the monitoring reports of the ff. WRCs/
other facilities holding wildlife from WRC:
1. Punta Amelita Farm
2. DENR Region 2-WRC
3. DENR CALABARZON-WRC
4. DENR Region 8-University of Eastern Phil.-WRC
5. Manila Ocean Park
6. DENR - Region 10 WRC
7. Xavier University Wildlife Sanctuary, Cagayan de
Oro
II. Implementation of Wildlife Special Projects
a. Invasive Alien Species (IAS)
1. Implementation of the Project "Removing Barriers Project implementation report prepared 4 4 100% June-July 2015 monthly report
to Invasive Species Management in the Production Jan-June 2015 bi-annual report
and Protection Forests in the Philippines" updates during TWG meetings
Aug-Oct 2015
2. Documentation of IAS presence in PAs Survey Report submitted 4 4 100% Jan 29 - Feb 12, 2015
- Bataan Natural Park Mar 19 - Apr 2, 2015
- Mt. Banahaw San Cristobal Protected Landscape Jul 12-29, 2015
- Agusan Marsh Wildlife Sanctuary Oct 7-22, 2015
- Samar Island Natural Park
3 .Operationalization of the IAS-Technical Working Meeting/wokshop organized/ 4 10 250%
Working Group conducted
Reports submitted 4 10 250%
III. Compliance with Regional and International
Commitments/Agreements/Partnerships
1. ASEAN-Wildlife Enforcement Network (WEN) Phil. report on cases filed in Court 1 1 100%
submitted
2. CITES-ASEAN Experts Group (AEG) National Report prepared and 1 2 200% Two reports (i.e. the 2015 Annual Report and the
submitted to CITES Secretariat 2013-2014 Biennial Report) have been prepared and
approved by the Direcctor for transmittal to the CITES
Secretariat as of October 30, 2015
3. Attendance to CITES Plants Committee Meeting and
other international events
4. TIHPA-Joint Management Committee (JMC) Report submitted BMB scheduled the 13th JMC-TIHPA Meeting on
Page 36
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 2: ECOSYSTEMS MANAGEMENT SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
PROGRAM/ACTIVITY/PROJECT Released
%
(Amt. Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
PHYSICAL PERFORMANCE FINANCIAL PERFORMANCE
REMARKDisbursement
% Budget Utilization Rate (BUR)
Annual Target Annual Accomp. % Accomp. Allotment
Meeting Sep 7-8, 2015 back to back with the SSME Tri-
National Sub-Committee Meeting on Marine
Protected Areas Network on Sep 9-10, 2015,
however, Sabah Parks requested that the Meeting be
moved to Nov 4-5, 2015. On Oct 16, 2015, Sabah
Parks begged off on said dates. BMB requested
Sabah Parks to schedule the Meeting at their
convenience. WRD and CMD jointly coordinated the
said Meeting.
5. Convention on Biological Diversity (CBD) Sub-Committee on Biological 2 2 100% Conducted 29th Meeting of th eSub-committee
Diversity meeting/workshop
conductedMeeting on Mar 11, 2015 at BMB Training Center,
NAPWC
The 30th Suc-Committee on Biological Diversioty
Meeting was held last Oct 23, 2015 at BMB
Conference Rm., NWRRC Bldg.
Phil. positions developed 1 8 800%
6. Convention on Migratory Species (CMS)
- Recognition of EAAF Network Sites Sites information sheet submitted 4to Flyway Secretariat
7. East Asia-Australia Flyway Partnership (EAAFP) National report submitted 1 1 100% National Report was submitted last January 2015
in time for the Meeting of Partners (MOP) on Jan 16-
21, 2015
MANAGEMENT OF COASTAL AND MARINE
RESOURCES/AREAS
A. Plans, Policies and Standards Developed, Promoted, Monitored and Evaluated
A1. Plans , Policies, Standards Developed
A.1.1 Technical Bulletin on a) implementation of SCREMP
and b) implementation of ICM
Tech. Bulletins dev./finalized (no.) 2 on-going Partially achieved. Draft Policy on for the
Implementation/Operationalization of National
Integrated Coastal Management (ICM) Strategy for
the Sustainable Development of the Coastal and
Marine Biodiversity in the Philippines has been
finalized and to be submitted to BMB Technical
Review Committee for their review
A.1.2 Policies and plans developed on MPAs, Mangroves,
Seagrass, Planktons, etc.
Policy drafted and finalized (no.) 1 1 100% A comprehensive program for the management of
coastal and marine ecosystems (to include coral
reefs, seagrass, mangroves, soft-bottom/mudflats,
plankton) has been developed and finalized. The said
program is entitled, "MarineEcosystems Recovery
and Rehabilitation Program". This was recently
presented during the 8th Regional Director's Meeting
conducted in Tuguegarao, Cagayan
A.1.3 Policy for the Adoption of Coastal and Marine
Environment Comprehensive Management Program
(CMECMP)
policy adopted (no.) 1 1 100% A draft policy on the adopting the "Coastal and Marine
Environment Comprehensive Program" has been
finalized and submitted to BMB TRC for their review
and approval
Page 37
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 2: ECOSYSTEMS MANAGEMENT SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
PROGRAM/ACTIVITY/PROJECT Released
%
(Amt. Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
PHYSICAL PERFORMANCE FINANCIAL PERFORMANCE
REMARKDisbursement
% Budget Utilization Rate (BUR)
Annual Target Annual Accomp. % Accomp. Allotment
A.1.4 Adoption of Capacity building framework on ICM
program
framework adopted (no.) 1 on-going Partially achieved. Framework on MPA Capacity
Buidling Program developed and finalized.
A.1.5 Guidelines on mainstreaming of ICM into the local
and national development/investment plans
Policy Guideline 1 1 100% Achieved. Draft Policy on for the
Implementation/Operationalization of National
Integrated Coastal Management (ICM) Strategy for
the Sustainable Development of the Coastal and
Marine Biodiversity in the Philippines has been
finalized and to be submitted to BMB Technical
Review Committee for their review
A2. Database and Baseline Establishment
A.2.1 Establishment and management of a solid baseline,
secondary data for
Database Management System
established
3 3 100% Achieved. A coastal and marine database has been
developed under the SCREMP CoRVA project. This
database is currently hub at UP MSI and will be
managed by BMB CMD
A3. Plans, Policies and Standards Monitored and
Evaluated
A.3.1 Monitoring and Evaluation of the implementation Plans, Policies and Standards
monitored and evaluated (no.)
1 1 100%
of E.O. 533 (ICM)
A.3.2 Monitoring and Evaluation of the implementation of
SCREMP
Plans, Policies and Standards
monitored and evaluated (no.)
1 1 100% Achieved. Monitoring and evaluation of EO 533/ICM
implementation of the regional offices are done
through field visits and desk review of their reports.
(Sarangani Bay Protected Seascape, Taklong Island
PLS, etc.) The data gathered are incorporated in the
SCREMP database
A.3.3 Review of House and Senate Bills,Policies on coastal
and marine referred by other offices
Position papers submitted (no.) 1 1 100% Achieved. HB 2332 (ICM Bill), HB 5948 (National
Coastal Greenbelt Bill, etc.)
A.3.4 Review of Plans and programs on coastal and marine
referred by other offices
Comments submitted (no.) 1 1 100%
A4. Communication Plan Development
A.4.1 Development of Communication Plan on Coastal and
Marine Resources management
Communication plan developed
(no.)
1 1 100% Achieved. A communication plan for the coastal and
marine environment sector has been developed.
A5. Program Development and Review
Achieved. Monitoring and evaluation of EO 533/ICM
implementation of the regional offices are done
through field visits and desk review of their reports.
The data gathered are incorporated in the ICM
database
Page 38
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 2: ECOSYSTEMS MANAGEMENT SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
PROGRAM/ACTIVITY/PROJECT Released
%
(Amt. Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
PHYSICAL PERFORMANCE FINANCIAL PERFORMANCE
REMARKDisbursement
% Budget Utilization Rate (BUR)
Annual Target Annual Accomp. % Accomp. Allotment
A.5.1 Coastal and Marine Environment Comprehensive
Management Program
Prog.developed and finalized (no.) 1 1 100% Achieved. A comprehensive program for the
management of coastal and marine ecosystems (to
include coral reefs, seagrass, mangroves, soft-
bottom/mudflats, plankton) has been developed and
finalized. The said program is entitled,
"MarineEcosystems Recovery and Rehabilitation
Program". This was recently presented during the 8th
Regional Director's Meeting conducted in
Tuguegarao, Cagayan
A.5.2 Establishment of Pilot/Control sites exemplifying poor,
fair to good, and excellent conditions
Program pilot sites identified (no.) 3 3 100%
A.5.3 Review and finalization of the National ICM Program Program reviewed and finalized
(no.)
3 on-going A Draft National ICM Program has already been
developed. Based on the discussions with the House
of Representatives during the TWG meetings and
and the recently concluded Technical Workshop for
ICM Bill , the draft National ICM Program needs to be
further reviewed before finalizing it.
B. Database Management
B.1 Administration and Maintenance of an integrated
central repository of data on baseline information for coastal
and marine ecosystem
1 1 100% Please refer to A.2.1
C. Capacity Building
C.1 Capacity building on SCREMP, ICM and Marine
Spatial
MajorTrainings conducted (no.) 3 3 100%
Planning (MSP) for field implementers based on priority needs
D. Program Implementation
D.1 Support to the implementation of the Strengthening Technical support provided (no.) 1 1 100%
Marine Protected Areas to Conserve Marine Key Biodiversity
Areas (MKBAs) in the Philippines Project
D.2 Support to the implementation of the ACCCoast Technical support provided (no. ) 1 1 100%
Phase 2 Project
F. Program Review, Monitoring and Evaluation
F.1 ICM
F.1.1 Review of draft ICM plans/ MCEP profile
submitted
Plans reviewed and evaluated (no.) 4 4 100% Monitoring and evaluation of EO 533/ICM
implementation of the regional offices are done
through field visits and desk review of their reports.
The data gathered are incorporated in the ICM
database
Achieved. Pilot sites for the Marine Ecosystems
Recovery and Rehabilitation Program were identified
and finalized during the DENBR Budget presentation
with USec Gerochi.
Integrated central DB system
established and managed (no.)
Fundamentals of MPA Management Training
conducted on March 19-29, 2015. It was participated
by MPA managers and regional technical staff
Trainings under SCREMP CorVA Project
Open Water SCUBA Diving
Coral Reef and Reef Fish Assessment
Autonomous Rapid Reef Assessment (ARRAS)
Coastal Integrity and Vulnerability Assessment
Seagrass and Mangrove Habitat Assessment
Page 39
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 2: ECOSYSTEMS MANAGEMENT SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
PROGRAM/ACTIVITY/PROJECT Released
%
(Amt. Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
PHYSICAL PERFORMANCE FINANCIAL PERFORMANCE
REMARKDisbursement
% Budget Utilization Rate (BUR)
Annual Target Annual Accomp. % Accomp. Allotment
F.1.2 Monitoring of the implementation of ICM Plans status report of plans (no.) 4 4 100% Monitoring and evaluation of EO 533/ICM
implementation of the regional offices are done
through field visits and desk review of their reports.
The data gathered are incorporated in the ICM
database
F.2 Sustainable Coral Reef Ecosystems Management
ProgramF.2.1 Review on the implementation of the components of
SCREMP
operationalization plan developed 1 1 100% On going review and recommendations provion on
the submitted updates and progress report from
regional implementers re SCREMP per component
accomplishment (regions IVA and B).
F.2.2 Review of accomplishment reports submitted reports reviewed and evaluated
(no.)
4 4 100% On going review and recommendations provion on
the submitted updates and progress report from
regional implementers re SCREMP.
F.2.3 Field validation of the implementation of validation reports submitted (no.) 4 4 100%
SCREMP in selected NIPAS MPAs
G. Social Mobilization and Development
G.1 Implementation of Communication Plan Communication plan developed
(no.)
1 1 100%
G.2 Conduct of Awareness Campaigns (MOO, ICC, CT
day, CTI Roadshow, etc)
Special events organized (no.) 3 3 100% Organization and conduct of the international coastal
clean up last September 19, 2015. three major clean
up sites in Manila were organized and assisted other
LGUs that have their own localized cleanups;
Deployment of Autonomous Reef Monitoring System
(ARMS) Month of the Ocean
G.3. Production and dissemination of IEC materials IEC materials produced and
disseminated (no.)
2 2 100%
on coastal and marine program
G.4. Promotion of E.O. 533 (ICM) and SCREMP policy and
program
Policies, plans and standards
promoted (no. )
1 1 100% Program of the BMB CMD such as Integrated Coastal
Management (ICM) and Sustainable Coral Reef
Ecosystem Management Program (SCREMP) were
promoted/popularized by the Division during the
conduct of the workshops/trainings/seminars
G.5. Popularization of ICM and SCREMP Subjects for popularization 1 1 100%
H. Technical Support to International and
RegionalPrograms
H.1 Conduct of NCCC TWG Meetings Minutes of NCC and TWG meetings
prepared (no.)
4 4 100% NCC and TWG meetings were conducted.
H.2 Support and attendance to International, Regional and Attendance/travel reports submitted
(no)
1 1 100%
national meetings, workshops, conferences, trainings (CBD,
CMS, APEC, SSME, PEMSEA, CTI; JMC on TIHPA; etc)
H.3 Support to MSN/ conduct of MPA MEAT Assessment ; Activity reports submitted/reviewed
(no.)
2 2 100%
CECAM, etc .
Conducted field monitoring using drafted M&E Form
for SCREMP last October 2, 2015. But on going
monitoring thru online communication.
Development of IEC materials related to International
Coastal Cleanup Celebration and disseminated to
regional offices for the simultaneous celebration.
Support/Attendance to the following international
regional trainings/meetings/conferences were
provided by CMD (APEC, SSME, CTI, PEMSEA re:
ICM, etc.)
Comments/ inputs on MSN MPA database provided.
updating and support provided to Pare El Mar thru the
MSN Project.
Page 40
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 2: ECOSYSTEMS MANAGEMENT SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
PROGRAM/ACTIVITY/PROJECT Released
%
(Amt. Released/
Allot*100)
ObligationPERFORMANCE INDICATORS
PHYSICAL PERFORMANCE FINANCIAL PERFORMANCE
REMARKDisbursement
% Budget Utilization Rate (BUR)
Annual Target Annual Accomp. % Accomp. Allotment
I. Support to other ENR Programs
I.1 Manila Bay Rehabilitation Program for Critical Habitats
and Resources Management Component Achieved. Support to the accomplishment of Manila
Bay targets provided
I.2. Other ENR /BMB Programs ( PAME; PA Master Plan, Consultation meetings attended
(no.)
1 1 100%
Development of ACCoast Phase 2, etc.)
Provision of inputs to the development of PAME
Capacity Building Program and attendance to the on
going PAME initiated capacity building.
Policies and plans formulated or
implemented contributing to
improved water quality (no.) (pls.
refer to separate WFP)
Page 41
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 3: ECOSYSTEMS REGULATION SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
MFO 3: ECOSYSTEMS REGULATION SERVICES 450,000 450,000 100% 450,000 103,837 100% 23%
ENFORCEMENT OF LAWS AND REGULATIONS
I. Wildlife Trade Regulation
a. Processing/Issuance of CITES permits permits issued 1000 1,339 134% Processed and issued a total of one thousand three hundred
thirty nine (1,339) CITES permits (export=979; re-export=62;
import=298) generating a total income of ₱6,381,407.74.
b. Continuous operation & maintenance of CITES IT infrastructure maintained 1 1 100% Configuration of server has been completed
E-Permitting and Management Information System
c. Updating of database on wildlife crimes, list of WRCs/ database updated 1 1 100%
CWRs/WFP holders per region, production and
trade report of wildlife breeders
II. Wildlife Law Enforcement
1. Organization of the Philippine Operations Group on Ivory proceedings/minutes prepared 4 5 125% 1) Technical staff of Wr & Enforcement Group &
(POGI) and illegal wildlife trade meetings, including and submitted POGI members attended the year-end assessment
consultation meetings of POGI with partner-agencies meeting of all POGI Members (CIDG, NBI, PNP) held
& other stakeholders at Bldg. 1, NAPWC Quezon Ave, QC on Dec 18, 2015
2) Meeting of POGI members and Wildlife Regulation Section
Tech Staff with DENR-NCR Asst. Reg. Dir. Sofnio Quintana &
Asst. Reg. Dir. Gordove on Nov 5, 2015 re: accomplishment
report of POGI from July 2013 to Oct 2015
3) Meeting with POGI members with DENR-NCR Asst. Reg.
Dir Sofnio Quintana on Oct 15, 2015 re: surveillance activity in
San Gregorio Vill., Pasay City
4) Meeting with POGI members with DENR-NCR Asst. Reg.
Dir. Quintana on Sep 22, 2015 re: surveillance activity in
Novaliches, QC
5) Meeting with NCRPO Chief of Operations, Asupt.
Rhoderick Armamento, Chief of Police, Pasig City, Ssupt. Jose
Hidalgo in coordination with Pasig City Veterinary Office & Mr.
Lester Yu of the Office of the Presidential Adviser on
Environmental Protection on Aug 21, 2015
2. Provision of assistance to POGI in the conduct of enforcement report 4 7 175% POGI members organized and provided
intelligence-led surveillance and enforcement operations no. of seizure/confiscations made 4 7 175% assistance in the conduct of enforcement operations in the ff:
against individuals/juridical persons found violating the 1) Sitio Lusay, Brgy. Lawi, Jordan, Guimares on Feb 16, 2015
provisions of Republic Act 9147 (Wildlife Resources
Conservation and Protection Act)
2) Sazon Beach Resort, Talin-Talin, Libon, Albay on Apr 24,
2015
3) No. 276 Old Brgy. Sta. Cruz, Sta. Maria, Bulacan on May
22, 2015
4) Cartimar Shopping Center, Pasay City on Jul 25, 2015
5) Brgy. Capitolyo, Pasig City on Aug 22, 2015
6) 52 Baes St., San Gregorio Village, Pasay City on Oct 15,
2015
REMARKAnnual Target Annual Accomp. % Accomp. Allotment Released
%
(Amt. Released/
Allot*100)
Obligation Disbursement
% Budget Utilization Rate (BUR)PROGRAM/ACTIVITY/PROJECT PERFORMANCE INDICATORS
PHYSICAL PERFORMANCE FINANCIAL PERFORMANCE
Page 42
Department: DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAU
MFO 3: ECOSYSTEMS REGULATION SERVICES
(Oblig/Allot)*100 (Disb/Oblig)*100
REMARKAnnual Target Annual Accomp. % Accomp. Allotment Released
%
(Amt. Released/
Allot*100)
Obligation Disbursement
% Budget Utilization Rate (BUR)PROGRAM/ACTIVITY/PROJECT PERFORMANCE INDICATORS
PHYSICAL PERFORMANCE FINANCIAL PERFORMANCE
7) 172 Mt. Fairweather St., Filinvest Homes I, Batasan Hills,
QC
no. of wildlife confiscated moving target 2,100 100% Number of confiscated wildlife:
appropriate case filed & pursued 3 - Feb 16, 2015
in Court 1 - Apr 24, 2015
1 - May 22, 2015
65 - Jul 25, 2015
1,908 - Aug 22, 2015
103 - Oct 15, 2015
19 - Nov 3, 2015
3. Provision of assistance to POGI in the filing and Case reports submitted 4 6 150%
prosecution of criminal cases against violators of Court hearings attended 4 18 450%
wildlife laws and relevant policies
III. Protected Area Community Based Resouce Management
3.1 Monitoring of CPB implementation in protected area Site visited/PA monitored 2 4 200% Monitored CBP implementation in the following:
1) Plantation sites and nurseries of Federation of Vista Hills,
Kalongkong & Kakilingan Upland Farmers Inc. (FVHKKVFI)
2) Banila Agroforest Development Incorporation (BADI)
3.2 Review and evaluate submitted draft PACBRMA/SAPA Reports reviewed/ prepared 3) Palabotan Agroforest Dev't Association (PADA)
4) Carolotan Agroforest Dev't Association Inc. (CAFDAI)
Page 43
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAUTotal GAA of Agency : 136,092,000.00
(1) (2) (3) (4) (5) (6) (7) (8) (1) (10)A. CLIENT ‐ FOCUSEDLack of integration of gender policies in biodiversity conservation on previous approved policies
Gender concerns were not considered in the policy/guideline formulation
To mainstream gender issues and concerns in the formulation of policies/guidelines
MFO 1 Review of existing policies on biodiversity conservation
5% of approved policies in 2013 and 2014 reviewed/enhance
50,000 ‐
Holding of PAMB Conference
PAMB Conference conducted
Conducted PAMB Conference/Summit with Senator Loren Legarda and SENR Ramon J. Paje on July 12‐15, 2015.
600,000 721,484.00
Joint workshop on the enhancement of the draft ENIPAS Bill
ENIPAS Bill enhanced and endorsed to Senate
Conducted Joint writeshop for E‐NIPAS last July 22 ‐ 24, 2015 Shercon Resorts, Batangas
155,000 160,399.50
To integrate gender issues and concerns on the drafting of new policies/guidelines
MFO 1 Gender responsive Policy drafted
No. of GR policy drafted (cave rescue protocol)
10,000 ‐
Pilot testing/orientation of local conservation processess mainstreaming gender
At least 1 region per island group oriented on how to use the toolkit for GAD mainstreaming in local conservation processess
Conducted Learning Event on Mainstreaming and Integrating Gender Tool in Biodiversity Conservation in the following Protected Areas: June 16‐18, 2015 Upper Marikina, May 7‐8, 2015 Sagay, May 13‐16, 2015 Bataan, March 18‐21, 2015 Kitanglad
275,535.04 All divisions/units of PAWB are represented in the GFPS
Training on the toolkit for GAD mainstreaming in LCA
GFPS/NPD Desk Officers able to use the toolkit
Conducted Learning Event on Mainstreaming and Integrating Gender Tool in Biodiversity Conservation and Protected Areas last February 27‐28, 2015.
209,251.36
Post Assessment of Learning Event
Assesment Report prepared and submitted to FPS
Post Assessment Workshop on the Result of Learning Event on Mainstreaming and Integrating Gender Tool in Biodiversity Conservation and Protected Area Management on August 6 ‐ 7, 2015 in Clark Pampanga
180,000 311,292.00
Partners forum on LCAs and ICCAs
no. of Women Ips/Pos participated in the forum 400,000 395,501.00
GFPS and projects attended the workshop (PCP, ICRMP, CTI)
Training on Basic caving skills cum gender resposive cave rescue protocol
DENR local offices personnel trained on basic caving skills
Conduct of Orientation‐Training on Cave Rescue on November 9 ‐ 13, 2015 in Sagada, Mountain Province
400,000 842,191.00 Policy on BMS should be enhanced to include women concerns
Assessment of PASus on ecotourism development activities in priority protected areas
Assessment Report on ecotourism development program
May 4‐9, 2015 Cebu
450,000 ‐
GAD Mandate/ Gender Issue
Cause of the Gender Issue
GAD Result Statement / GAD Objective
Relevant Agency MFO/ PAP
GAD Program/ ActivityPerformance
Indicators/TargetActual (Outputs/ Outcomes)
Result
Total Agency Approved Budget
Expenditure/ Actual Cost
Variance/ Remarks
Gender and Development (GAD) Accomplishment ReportCY 2015
1,150,000
Page 44
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAUTotal GAA of Agency : 136,092,000.00
(1) (2) (3) (4) (5) (6) (7) (8) (1) (10)
GAD Mandate/ Gender Issue
Cause of the Gender Issue
GAD Result Statement / GAD Objective
Relevant Agency MFO/ PAP
GAD Program/ ActivityPerformance
Indicators/TargetActual (Outputs/ Outcomes)
Result
Total Agency Approved Budget
Expenditure/ Actual Cost
Variance/ Remarks
Gender and Development (GAD) Accomplishment ReportCY 2015
Trainors Training on wildlife enforcement
CapDev of DENR‐Regional Offices on wildlife enforcement
Conducted last September 6‐10 at Palawan 125,000 874,575.00
Inadequate gender responsive facilities
MFO 2 Construction of gender responsive rain shelters
Rain shelters constructed Rain shelters constructed1,275,000
Improvement of comfort rooms and other facilities at NAPWC
improved comfort rooms and other facilities 50,000
DBM‐NEDA‐PCW Joint Circular 2012‐01
Strengthening of the GFPS
GAAS Conduct of GFPS meetings
Quarterly reports prepared
40,000 9,590.00
STO Conduct of Planning workshop for FY 2017
1 WFP for 2017 approved and submitted
150,000 ‐
MFO 1 Conduct of Assessment of GAD WFP for 2015
1 Accomplishment Report assessed and submitted 100,000 ‐
MFO 1 Conduct of reprogramming workshop for FY 2016
1 WFP approved and submitted 100,000 ‐
GAAS Support to Women's Month celebration
No. of activities undertaken/No. of GFPS members participated in women's month celebration
Fun Run‐March 8, Launching of BMB GAD Logo and BMB womens day on March 30 200,000 196,280.28
road map International coastal cleanup
The International Coastal Clean up Recognition was conducted last November 23, 2015
400,000 395,501.00
GAAS Support to other GAD related programs/projects meetings, trainings, workshops, congress, symposia and conferences
No. of activities undertaken/participated
Participated in the 18‐Day Campaign to end Violenc Against Women last November 25, 2015 to December 12, 2015. Participated in the 4th National Women's Summit to be held at Miriam College on November 16‐17, 2015.
250,000 266,626.00
Hiring of Personnel 192,000 100,333.23
Page 45
Agency/Bureau/Office: BIODIVERSITY MANAGEMENT BUREAUTotal GAA of Agency : 136,092,000.00
(1) (2) (3) (4) (5) (6) (7) (8) (1) (10)
GAD Mandate/ Gender Issue
Cause of the Gender Issue
GAD Result Statement / GAD Objective
Relevant Agency MFO/ PAP
GAD Program/ ActivityPerformance
Indicators/TargetActual (Outputs/ Outcomes)
Result
Total Agency Approved Budget
Expenditure/ Actual Cost
Variance/ Remarks
Gender and Development (GAD) Accomplishment ReportCY 2015
Limited capacities of BMB personnel on gender mainstreaming
BMB decision makers, members of GAD focal point and TWG have limited skills to initiate and sustain gender mainstreaming
To increase awareness of BMB decision makers, members of GAD focal point system and TWG on mainstreaming gender concerns/issues in the activities/programs/project of BMB where appropriate
MFO 1 Conduct of GST for BMB decision makers
30% of decision makers participated in GST trainings
240,000 ‐
Continuing systematic capacity building for members of GFP and TWG
50% of GFP and TWG participated in trainings (gender‐fair language)
Gender Fair Language, Conducted by Ms. Miriam P. Garcia at Ninoy Aquino Parks and Wildlife Training Center last October 9, 2015.
100,000 33,850.00
Inadequate knowledge and skills on GAD concerns of newly hired BMB personnel
Newly hired personnel may not have background on gender mainstreaming
To capacitate and raise awareness of newly hired personnel on Gender and Development
MFO 1 Capacity development on GAD concerns in BMB processes
50% of newly hired personnel are capacitated/oriented on GAD policies and guidelines and other GAD
November 24, 2015 at Ninoy Aquino Parks and Wildlife Training Center, Building No. 1. conducted by Mr. Roy Stephen Tolentino of Planning Division, DENR Central Office.
35,000 27,500.00
Insufficient sex‐disaggregated data on the implementation of biodiversity programs/projects/activities
Insufficient standard template for data collection on sex disaggragated data
Sex‐disaggregated data develop e.g. governing bodies, task forces, committees, trainings, etc. on Pas, Coastal, Caves, Wetlands and Wildlife Conservation
STO Formulation/enhancement of standard template for collection. Analysis of sex‐disaggragated data in the programs and projects of BMB
Standard template for data collection/analysis to reflect sex disaggragated data established
Finalized all BMB forms into Sex disaggregated last September 17, 2015
Establish/Maintain sex disaggregated database on BMB priority programs/projects
Sex disaggragated data on BMB priority programs/projects maintained
Insufficient sex‐disaggregated data on the implementation of biodiversity activities
Lack of awareness of implementors to integrate gender concerns in biodiversity activities
Creation of sex‐disaggregated databases e.g. governing bodies, task forces, committees, trainings, etc. on PAs, Coastal, Caves and Wetlands and Wildlife Conservation
STO
To establish GAD webpage in the BMB Web portals
STO Posting of GAD activities and concerns in the BMB website
100% of GAD activities documented and showcased/shared in the BMB website
On Going
50,000 ‐
Total 6,277,000.00 4,758,559.41
10,000 77,526.00
B. ORGANIZATION ‐ FOCUSED
Page 46
47
ANNEX A: Number of Visitors and Income Generated at NAPWC for CY 2015
MONTH NUMBER OF VISITORS INCOME GENERATED
TOTAL Male Female Total Entrance Fee Parking Fee Rentals *Others
January 32,656 29,179 61,835 432,402.00 41,872.00 6,650.00 39,500.00 520,424.00
February 29,389 24,946 54,335 384,496.00 41,005.00 3,750.00 30,000.00 459,251.00
March 26,272 20,989 47,261 331,164.00 37,090.00 6,200.00 24,500.00 398,954.00
April 22,537 18,833 41,370 297,798.00 33,928.00 3,650.00 28,300.00 363,676.00
May 22,629 18,816 41,445 301,725.00 36,544.00 39,305.75 30,500.00 408,074.75
June 15,668 11,466 27,134 201,840.00 25,955.00 84,479.16 55,500.00 367,774.16
July 13,983 10,876 24,859 180,551.00 26,332.00 2,250.00 41,193.25 250,326.25
August 16,490 14,681 31,171 225,981.00 32,760.00 7,600.00 15,500.00 281,841.00
September 15,554 18,700 34,254 240,976.00 36,677.00 11,950.00 22,500.00 312,103.00
October 13,404 16,284 29,688 202,314.00 30,513.00 17,700.00 28,049.60 278,576.60
November 14,498 24,273 38,771 278,453.00 38,701.00 18,400.00 16,896.60 352,450.60
December 16,529 22,948 39,477 263,475.00 44,991.00 13,050.00 10,820.00 332,336.00
GRAND TOTAL 239,609 231,991 471,600 3,341,175.00 426,368.00 214,984.91 343,259.45 4,325,787.36