volumeVOLUME PEKERJAANKEGIATAN : PEMBANGUNAN KANTOR POS SEMARANG SELATANTAHUN ANGGARAN 2012

NoJenis PekerjaanPerhitungan

ALANTAI 1IPEKERJAAN PERSIAPAN1Pembersihan LahanVolume=Luas area=25x20=500m2

2Pembuatan Kantor Sementara Volume=Luas gudangdan Gudang=4x4=16m2

3Pengadaan Air KerjaVolume.=1ls

4Pembuatan Pagar SementaraVolume=Keliling gudang=2x (25+20)=90m'

5Pengadaan SkafoldingVolume.=1ls

6Pemasangan BouwplankVolume=Panjang=2x68=136m'

7DokumentasiVolume.=1ls

8Pembuatan Papan NamaVolume.=1ls

IIPEKERJAAN TANAH1Galian FootplatVolume=1.2x1.2x2.5x28=100.800m3

2Galian PondasiVolume=1x1.1x158.00

=173.800m3

3Galian RolagVolume=0.15x0.2x16=0.480m3

4Urugan pasir bawah pondasi t=10cmVolume=0.1x1x158=15.800m3

5Urugan pasir bawah lantai t=10cmVolume=0.10x247m2=24.700m3

6Urugan pasir bawah footplat t=3cmVolume=0.03x1.2x1.2x28=1.210m3

7Urugan pasir bawah rollag t=5cmVolume=0.05x0.2x32=0.320m3

8Urugan tanah rollagVolume=0.15x0.15x29.650=0.667m3

9Urugan tanah kembaliVolume=1x(100.80+173.800)3

=91.533m3

IIIPEKERJAAN PASANGAN & PLESTERAN1Pemasangan AanstampingVolume=0.20x1.00x158.000=31.600m3

2Pas Pondasi Batu kaliVolume=(0.3+0.8)x0.8x158.002=69.520m3

3Pas. Rolag batu bataVolume=0.15x0.15x32=0.720m3

4Pas. Bata camp 1 : 5Volume sb. X=58.650+5+44.813+80+7.421+14.013+14+7.421+22.2=253.018m2Volume sb.Y=47.55+10+37.608+9+4.229+21.144+14.013+10.659+47.7+5.863+11.421+11.59+12.736=243.513m2Total volume=253.018+243.513=496.531cm5Pas. Bata camp 1 : 3Volume sb. X=0.35:4x253.018=22.139075m2

Volume sb. Y=0.35:4x243.513=21.307m2Total volume=22.139+21.307=43.446cm6Plesteran camp 1 : 5Volume=2x(253.018+243.513)=993.062m2

7Plesteran camp 1 : 3Volume=2x(22.139+21.307)=86.892m2

8AcianVolume=2x(496.531+43.446)=1079.95m2

IVPEKERJAAN BETON 1Foot plat 120/120

Volume=1.20x1.20x0.3x28=12.096m3

2Lantai kerja footplat t=10cmVolume=1.20x1.20x0.1x28=4.032m3

3Sloof 20/25Volume=0.20x0.25x105=5.250m3

4Sloof 15/20Volume=0.15x0.20x53=1.590m3

5Kolom Pedestel 30/30Volume=0.30x0.30x2x28=5.317m3

6Kolom 30/30Volume=0.30x0.30x4x28=10.080m3

7Kolom 15/15Volume=0.15x0.15x4x28=2.520m3

8Balok 20/30Volume=0.20x0.30x134=8.040m3

9Balok 15/20Volume=0.15x0.20x50=1.500m3

10Pelat beton Lantai 2 t= 11 cmVolume=0.11x199m2=21.890m3

11Pelat dak beton t= 10 cmVolume=0.10x59.5m2=5.950m3

12Kantilever t= 10 cmVolume=0.10x1x3=0.300m3

13Tangga Beton t= 15 cmVolume=1.5x0.35x(3.77+4.26)+(0.15x3x1.23)=4.769m3

VPEKERJAAN KUSEN PINTU + JENDELA1Kusen dan daun pintu P1 , 4bhKusenVolume=0.06x0.12x7.24x4=0.209m3

2Kusen dan daun pintu P2, 1bhKusenVolume=0.06x0.12x6.04x1=0.043m3

Daun=0.80x2.50=2.000m3

Total volume=0.043+2.000=2.043cm

3Kusen dan daun pintu P3, 4bh

KusenVolume=0.06x0.12x6.04=0.043m3

Daun=0.80x2.50x4.00=8.000m3

Total volume=0.043+8.000=8.043cm

4Kusen dan daun pintu P4, 5bh

Volume.=5unit

5Kusen J1,1bh

KusenVolume=0.06x0.12x15.5x1=0.111m3

6Kusen J2

KusenVolume=0.06x0.12x15.6x1=0.113m3

7Kusen dan daun jendela J3, 2bh

KusenVolume=0.06x0.12x5.38=0.039m3

Daun= ((0.45x2.00) - (1.92x0.37)) x2= 0.379m3

Total volume=0.039+0.379=0.418cm

9Kusen BV

KusenVolume=0.06x0.12x2.48x5=0.089m3

VIPEKERJAAN PLAFOND & CAT1Gypsum BoardVolume=24.00+168.00+6.00+28.00+12=238m2

2List PlafondVolume=55.00+74.00+85.50+18.00=232.50m2

3Pengecatan tembokVolume=2x(496.531+43.446)=1079.95m2

4Pengecatan plafondVolume=24.00+168.00+6.00+28.00+12=238m2

VIIPEKERJAAN KUNCI, KACA & PENGGANTUNG1Kunci tanam biasaVolume=9bh2Kunci tanam pintu WCVolume=5bh3Engsel pintuVolume=30bh4Kaca P1, 4bhVolume=1x2.5x2x4=20.0m2

5Kaca J1Volume=0.50x3.5=1.8m2

6Kaca J2Volume=4.70x3=14.1m2

7Kaca J3Volume=1.92x0.37x2=1.4m2

8Kaca BVVolume=0.25x0.25x2x5=0.6m2

VIIIPEKERJAAN INSTALASI LISTRIK1Lampu TL 2x18 WVolume=14bh2Lampu SL 15 WVolume=29bh3Saklar tunggalVolume=5bh4Saklar gandaVolume=7bh5Stop kontakVolume=13bh6Box panel Volume=1unit7Instalasi titik lampuVolume=43bh

IXPEKERJAAN LANTAI 1Pasang Keramik granito 60 x 60Volume=28+20+2+32+12+4+3=101.00m2

2Pasang Keramik granito 40 x 40Volume=6+8+12=26.00m2

3Pasang Keramik lantai 30 x 30Volume=36+16=52.00m2

4Pasang Keramik lantai 30 x 30 (Tangga)Volume=10+3.69=14.04m2

5Pasang Keramik lantai 20 x 20 (KM/WC dan teras)Volume=15+6+2+9+4=36.00m2

XPEKERJAAN SANITASI1Closet jongkokVolume=5.0bh 2WastafelVolume=5.0bh 3Septictank & peresapanVolume=2.0unit4Kran airVolume=9.0bh 5Pipa PVC 1/2"Volume=24.7m'6Pipa Galvanis 3/4"Volume=87.5m'7Bak kontrolVolume=1.0bh 8Ground tankVolume=1.0bh 9Tandon airVolume=1.0bh 10Floor drainVolume=5.0bh

BLANTAI 2IPEKERJAAN PASANGAN 1Pas. Bata camp 1 : 5Volume sb. X=47.100+42.35+19.949+6.01+22.066+18.013+56+6.013=217.504m2Volume sb.Y=38.54+122.916+14.013+12.987+8.987+22.821+24.387=244.651m2Total volume=217.504+244.651=462.155cm2Pas. Bata camp 1 : 3Volume sb. X=0.35:4x217.504=19.032m2

Volume sb. Y=0.35:4x244.651=21.407m2Total volume=19.032+21.407=40.439cm3Plesteran camp 1 : 5Volume=2x(217.504+244.651)=924.31m2

4Plesteran camp 1 : 3Volume=2x(19.032+21.407)=80.877m2

5AcianVolume=2x(462.155+40.439)=1005.187m2

IIPEKERJAAN BETON 1Kolom 30/30Volume=0.30x0.30x4x27=9.720m3

2Kolom 15/15Volume=0.15x0.15x4x24=2.160m3

5Ring Balok 15/20Volume=0.15x0.20x134=4.020m3

6Kantilever t=10 cmVolume=0.10x2x51=10.200m3

IIIPEKERJAAN KUSEN PINTU + JENDELA1Kusen P1 , 2bh

KusenVolume=0.06x0.12x7.24x2=0.104m3

2Kusen dan daun pintu P2, 4bh

KusenVolume=0.06x0.12x6.04=0.043m3

Daun=0.80x2.50x4.00=8.000m3

Total volume=0.043+8.000=8.043cm

3Kusen P4 PVC, 5bh

Volume.=4unit

4Kusen dan daun jendela J3, 9bh

KusenVolume=0.06x0.12x5.38=0.039m3

Daun= ((0.45x2.00) - (1.92x0.37)) x9= 1.706m3

Total volume=0.039+1.706=1.745cm

5Kusen J5

KusenVolume=0.06x0.12x5.28x3=0.114m3

6Kusen J6

KusenVolume=0.06x0.12x11.6=0.084m3

7Kusen J7,2bh

KusenVolume=0.06x0.12x8.6x2.00=0.124m3

8Kusen BVKusenVolume=0.06x0.12x2.48x4=0.071m3

IVPEKERJAAN PLAFOND & CAT1Gypsum BoardVolume=36.0+40.0+9.0+40.0+25.0+6+28=184m2

2List PlafondVolume=4.00+85.55+18.00

=107.55m2

3Pengecatan tembokVolume=2x(462.155+40.439)=1005.187m2

4Pengecatan plafondVolume=36.0+40.0+9.0+40.0+25.0+6+28=184m2

VPEKERJAAN ATAP1NokVolume=0.08x0.12x12=0.1152m32Papan RuiterVolume=0.02x0.2x12=0.048m33Papan ListplankVolume=0.03x0.3x73=0.657m34Atap GentengVolume I=(4+18)x7.21x22=158.620m2

Volume II=1x12x7.21x22=86.520m2

Volume III=(4.19+8.15)x7.21x22=88.971m2

Volume IV=1x5x3.05x12=7.625m2

Volume V=2.5x3.05x2

=15.250m2

Volume total=158.620+86.520+88.971+7.625+15.250=356.986m25Rangka Atap Volume total=356.986m2

VIPEKERJAAN KUNCI, KACA & PENGGANTUNG1Kunci tanam biasaVolume=7bh2Kunci tanam pintu WCVolume=4bh3Engsel pintuVolume=33bh4Kaca J3, 9bhVolume=1.92x0.37x9=6.39m2

5Kaca J5Volume=0.40x2.00x3=2.40m2

6Kaca J6Volume=3.00x2.58=7.74m2

7Kaca J7Volume=3.00x1.08=3.24m2

8Kaca BVVolume=0.25x0.25x2x4=0.50m2

VIIPEKERJAAN INSTALASI LISTRIK1Lampu TL 2x18 WVolume=17bh2Lampu SL 15 WVolume=15bh3Saklar tunggalVolume=6bh4Saklar gandaVolume=5bh5Stop kontakVolume=6bh6Instalasi titik lampuVolume=32unit

VIIIPEKERJAAN LANTAI 1Pasang Keramik lantai 40 x40Volume=50+12+28+8+4.5+16.5=119.00m22Pasang Keramik lantai 30 x30Volume=32+6=38.00m2

3Pasang Keramik lantai 20 x 20 (KM/WC)=18+7+4=29.00m2

IXPEKERJAAN SANITASI1Closet jongkokVolume=4bh 2WastafelVolume=2.0bh 3Kran airVolume=10bh 4Pipa PVC 2"Volume=6.4m'5Pipa PVC 1/2"Volume=9.0m'6Floor DrainVolume=4bh

XPEKERJAAN RANGKA BAJA

Batang Tarik=51x2=102.0Batang Vertikal=14.9x2=29.78Batang Diagonal=16.4x2=32.80Batang Miring=74.3x2=148.53+Jumlah total=313.07046kg

Kuda-kuda Baja, 2bh=313.1x2=626.22Kg

Batang Tarik=51x1=51.0Batang Vertikal=14.9x1=14.89Batang Diagonal=16.4x1=16.40Batang Miring=74.3x1=74.26+Jumlah total=156.54kg

Kuda-kuda Baja, 2bh=156.55x2=313.1Kg

1Kuda-kuda BajaVolume=626.2Kg21/2 Kuda-kudaVolume=313.10Kg3JuraiVolume=148.53Kg4Gording CNP 125.50.20.3,2 mmVolume=835.213Kg5Baut 10mmVolume=160buah6Baut 12mmVolume=288buah

CINFRASTRUKTURIPEKERJAAN TANAH1Galian Pondasi Pagar

Volume=1x1.1x57.00

=62.700m3

2Urugan Pasir bawah pondasi, t=10cmVolume=0.1x1x57=5.700m3

3Urugan tanah kembaliVolume=1x(62.70)3

=20.900m3

IIPEKERJAAN PASANGAN 1Pemasangan AanstampingVolume=0.20x1.00x57.000=11.400m3

2Pas Pondasi Batu kaliVolume=(0.3+0.8)x0.8x57.002=25.080m3

3Pas. Bata camp 1 : 5Volume sb. X=1x0.15x (6+25+18+8)=8.550m2

IIIPEKERJAAN BETON 1kolom 15/15Volume=0.15x0.15x15=0.338m3

2sloof 15/20Volume=0.15x0.20x57=1.710m3

IVPEKERJAAN LANTAI 1Pasang paving blockVolume=25x20-242.9=257.100m3

VPEKERJAAN INSTALASI AC & VENT. MEKANIK1Pengadaan dan Pemasangan Unit AC Sentral - Type : Air cooled split ductVolume=9.0bh Kapasitas pendingin : 100.000,00 btu / h Karakteristik : 380 V, 1 Ph, 50 Hz- Refrigerant : R - 22Volume=2.0can- Dudukan out doorVolume=9.0bh- Ongkos PasangVolume=9.0bh

DPOS SATPAM 2 UNITIPEKERJAAN PERSIAPAN1Pembersihan LahanVolume=Luas area=2x2x2=8m2

2Pemasangan BouwplankVolume=Panjangx jumlah=2x4x2=16m'

IIPEKERJAAN TANAH1Galian PondasiVolume=1x1.1x8x2

=17.60