NO URAIAN HARGA SATUAN JUMLAH HARGA 1 Bongkar beton jembatan lama 0.75 m³ 350,000.00 262,500.00 2 Pembersihan saluran 10.00 m³ 35,000.00 350,000.00 3 Pembesian u/ jembatan baru 156.25 kg 15,000.00 2,343,750.00 4 Papan begisting 5.00 m² 150,000.00 750,000.00 5 Cor beton 1.10 m³ 1,150,000.00 1,265,000.00 JUMLAH 4,971,250.00 JASA 497,125.00 JUMLAH TOTAL 5,468,375.00 DIBULATKAN 5,468,000.00 catatan : Konstruksi full beton cor NO URAIAN HARGA SATUAN JUMLAH HARGA 1 Bongkar beton jembatan lama 0.75 m³ 350,000.00 262,500.00 2 Pembersihan saluran 10.00 m³ 35,000.00 350,000.00 3 Pembesian u/ jembatan baru 95.83 kg 15,000.00 1,437,500.00 4 Papan begisting 6.00 m² 150,000.00 900,000.00 5 Cor beton 0.98 m³ 1,150,000.00 1,127,000.00 6 Grill besi uk. 0.5x1 m (2bh) 84.78 kg 20,000.00 1,695,600.00 JUMLAH 5,772,600.00 JASA 577,260.00 JUMLAH TOTAL 6,349,860.00 DIBULATKAN 6,349,000.00 catatan : Konstruksi beton cor & grill besi PEKERJAAN JEMBATAN AKSES MASUK VOLUME PEKERJAAN JEMBATAN AKSES MASUK VOLUME

description

Rabat Beton Jembatan

Transcript of Rabat Beton Jembatan

Page 1: Rabat Beton Jembatan

NO URAIAN HARGA SATUAN JUMLAH HARGA1 Bongkar beton jembatan lama 0.75       m³ 350,000.00              262,500.00              2 Pembersihan saluran 10.00    m³ 35,000.00                350,000.00              3 Pembesian u/ jembatan baru 156.25  kg 15,000.00                2,343,750.00           4 Papan begisting 5.00       m² 150,000.00              750,000.00              5 Cor beton 1.10       m³ 1,150,000.00           1,265,000.00           

JUMLAH  4,971,250.00           JASA 497,125.00              JUMLAH TOTAL 5,468,375.00           DIBULATKAN 5,468,000.00           

catatan :Konstruksi full beton cor

NO URAIAN HARGA SATUAN JUMLAH HARGA1 Bongkar beton jembatan lama 0.75       m³ 350,000.00              262,500.00              2 Pembersihan saluran 10.00    m³ 35,000.00                350,000.00              3 Pembesian u/ jembatan baru 95.83    kg 15,000.00                1,437,500.00           4 Papan begisting 6.00       m² 150,000.00              900,000.00              5 Cor beton 0.98       m³ 1,150,000.00           1,127,000.00           6 Grill besi uk. 0.5x1 m  (2bh) 84.78    kg 20,000.00                1,695,600.00           

JUMLAH  5,772,600.00           JASA 577,260.00              JUMLAH TOTAL 6,349,860.00           DIBULATKAN 6,349,000.00           

catatan :Konstruksi beton cor & grill besi

PEKERJAAN JEMBATAN AKSES MASUK

VOLUME

PEKERJAAN JEMBATAN AKSES MASUK

VOLUME