  • PROGRAM :PEKERJAAN : Pembangunan Rumah Tipe 108 M2LOKASI : ArsoKABUPATEN : KeeromT.A : 2010

    REKAPITULASI

    No. URAIAN - PEKERJAAN

    1 2 6

    A

    I PEKERJAAN PENDAHULUAN 4,395,820.00 II PEKERJAAN TANAH DAN PONDASI 75,021,101.46 III PEKERJAAN LANTAI, DINDING & PLAFOND 154,386,502.03 IV PEKERJAAN KOZEN PINTU DAN JENDELA 38,934,133.00 V PEKERJAAN KAYU DAN ATAP 63,837,913.75 VI PEK. PENGGANTUNG DAN PENGUNCI 1,100,500.00 VII PEKERJAAN PENGECATAN 21,308,114.70 VIII PEKERJAAN SANITAIR 3,090,000.00 IX PEKERJAAN ELEKTRIKAL 2,863,000.00 X PEKERJAAN FINISHING 6,000,000.00

    REAL COST 1 UNIT ...R 370,937,084.94

    P P N 10 % ...RpBIAYA FISIK 370,937,084.94

    PEMBULATAN 370,937,000.00 BIAYA ADMINISTRASI PROYEK 17,700,000.00

    JUMLAH HARGA (Rp.)

  • C TOTAL A + B 388,637,000.00

  • RENCANA ANGGARAN BIAYA ( RAB )PROGRAM :PEKERJAAN : Pembangunan Rumah Tipe 108 M2LOKASI : ArsoKABUPATEN : KeeromT.A : 2010

    No. URAIAN - PEKERJAAN VOLUME STN HARGA JUMLAH SATUAN HARGA

    ( Rp. ) ( Rp. ) 1 2 3 4 5 6

    I. PEKERJAAN PENDAHULUAN1 Pembangunan Direksi Keet 1.00 Ls - - 2 Pembersihan Lokasi 108.00 M2 7,200.00 777,600.00 3 Pas. Bouwplank 29.00 M' 47,180.00 1,368,220.00 4 Foto Dokumentasi 3.00 Set 750,000.00 2,250,000.00

    JUMLAH 4,395,820.00 II. PEKERJAAN TANAH DAN PONDASI

    1 Galian Tanah Pondasi 40.32 M3 96,000.00 3,870,720.00 2 Urugan Kembali Bekas Galian 10.08 M3 12,000.00 120,960.00 3 Urugan Pasir dibawah Pondasi 5.04 M3 277,260.00 1,397,390.40 4 Urugan Peninggian Lantai 24.30 M3 277,260.00 6,737,418.00 5 Urugan Pasir dibawah Lantai 6.38 M3 277,260.00 1,767,532.50 6 Pasang Batu Kosong ( Anstamping Batu Kali ) 10.08 M3 409,800.00 4,130,784.00 7 Pasangan Pondasi Bt. Kali 1 : 3 25.20 M3 1,112,276.00 28,029,355.20 8 Sloof Beton Bertulang 20/30 5.04 M3 5,747,409.00 28,966,941.36

    JUMLAH 75,021,101.46 III. PEKERJAAN LANTAI, DINDING & PLAFOND

    1 Tiang Kolom beton bertulang 0.78 M3 5,747,409.00 4,482,979.02 2 Ring Balk beton bertulang 15/20 2.52 M3 5,747,409.00 14,483,470.68 3 Lantai Cor Beton Tumbuk 1 : 3 : 5 6.38 M3 141,420.50 901,555.69 4 Pas. Lantai Keramik 30 x 30 cm 117.00 M2 290,605.00 34,000,785.00 5 Pas. Porselin 20 x 20 cm 9.00 M2 187,793.86 1,690,144.74 6 Pas. Batu tela 1 : 4 249.00 M2 124,648.00 31,037,352.00 7 Pas. Plesteran 1 : 4 498.00 M2 63,202.65 31,474,919.70 8 Pas. Rabat Batu tela 1 : 3 8.60 M2 127,912.00 1,100,043.20 9 Pas. Saluran Parit batu tela 1 : 3 121.00 M' 127,912.00 15,477,352.00

    10 Plafond Tripleks + Rangka 117.00 M2 168,700.00 19,737,900.00 JUMLAH 154,386,502.03

    IV. PEKERJAAN KOZEN PINTU DAN JENDELA 1 Pas. Kozen Pintu Jendela dan Pintu Kayu Besi 1.90 M3 7,330,000.00 13,927,000.00 2 Pas. Murplat Kayu Klas I 5/10 0.54 M3 6,038,000.00 3,260,520.00 3 Pasang Pintu Panel Kayu Besi 11.18 M2 982,500.00 10,984,350.00 4 Pas. Pintu Dobel Tripleks - M2 658,750.00 - 5 Pas. Pintu Dobel Tripleks Lapis Seng Plat 2.94 M2 658,750.00 1,936,725.00 6 Pas. Daun Jendela Panil Kaca 7.94 M2 982,500.00 7,801,050.00 7 Jalusi Kayu Matoa 4.08 M2 251,100.00 1,024,488.00

    JUMLAH 38,934,133.00 V. PEKERJAAN KAYU DAN ATAP

    1 Kuda-Kuda Rangka Atap Kayu Klas I 3.81 M3 6,038,000.00 23,004,780.00 2 Pasang Gording Kayu Besi 5/10 cm 1.53 M3 5,488,000.00 8,396,640.00 3 Pasang Atap seng Gelombang BJLS 0.30 349.47 M2 80,675.00 28,193,492.25 4 Pasang Nok Atap seng Plat BJLS 0.30 47.30 M' 28,055.00 1,327,001.50 5 Lisplank 2x2/25 cm Kayu Klas I 10.00 M2 291,600.00 2,916,000.00

    JUMLAH 63,837,913.75 VI. PEK. PENGGANTUNG DAN PENGUNCI

    1 Kunci Pintu Yale 2 Slaag 5.00 Bh 115,000.00 575,000.00 2 Engsel Pintu 15.00 Bh 20,000.00 300,000.00 3 Engsel Jendela 18.00 Bh 6,500.00 117,000.00 4 Grendel Pintu 5.00 Bh 10,000.00 50,000.00 5 Grendel Jendela 9.00 Bh 6,500.00 58,500.00 6 Kait Angin 18.00 Bh 15,000.00 270,000.00 7 Handel Jendela 9.00 Bh 10,000.00 90,000.00

  • JUMLAH 1,100,500.00

  • VII. PEKERJAAN PENGECATAN 1 Cat Dinding Luar Dalam 498.00 M2 21,825.00 10,868,850.00 2 Cat Plafond 117.00 M2 36,675.00 4,290,975.00 3 Cat Kilat 86.73 M2 70,890.00 6,148,289.70

    JUMLAH 21,308,114.70 VIII. PEKERJAAN SANITAIR

    1 Bak Mandi 1.00 Bh 550,000.00 550,000.00 2 Kran Air 1/2" 2.00 Bh 20,000.00 40,000.00 3 Septiktank & Peresapan 1.00 Bh 2,500,000.00 2,500,000.00 4 Cloused Duduk 2.00 Ls 1,500,000.00 3,000,000.00

    JUMLAH 3,090,000.00 IX. PEKERJAAN ELEKTRIKAL

    1 Sekring Kas 1 Grop 1.00 Bh 40,000.00 40,000.00 2 Lampu TL 40 Watt 6.00 Ttk 458,000.00 2,748,000.00 3 Stop Kontak 5.00 Ttk 15,000.00 75,000.00

    JUMLAH 2,863,000.00 X. PEKERJAAN FINISHING

    1 Pekerjaan Pembersihan Akhir 1.00 Ls 1,000,000.00 1,000,000.00 2 Pekerjaan Gapura 3 unit 1.00 Ls 5,000,000.00 5,000,000.00

    JUMLAH 6,000,000.00 JUMLAH 370,937,084.94

  • DAFTAR HARGA SATUAN UPAH, BAHAN DAN ALAT

    PEKERJAAN : Pembangunan Rumah Tipe 108 M2LOKASI : ArsoKABUPATEN : Keerom

    T.A : 2010

    NO. U R A I A N SATUAN HARGA SATUAN(Rp.)

    I. DAFTAR UPAH1. Mandor H/O 120,000.002. Kepala Tukang H/O 100,000.003. Tukang H/O 95,000.004. Pekerja Tdk Terampil H/O 60,000.005. Pekerja Terampil H/O 70,000.006. Operator Terampil H/O 120,000.007. Pembantu Operator H/O 95,000.008. Sopir Terampil H/O 95,000.009. Pembantu Sopir H/O 95,000.00

    10. Tukang Listrik H/O 95,000.0011. Upah Instalasi Listrik Titik 95,000.0012. Upah Instalasi Air Titik 95,000.00

    NO. U R A I A N HARGA SATUAN(Rp. / Unit)

    II. HARGA BAHAN1. Batu Tela 2,750.00 BH2. Tanah Urug 215,050.00 M33. Pasir Urug 215,050.00 M34. Batu Kali 259,000.00 M35. Batu Kerikil 213,400.00 M36. Sirtu 233,200.00 M37. Pasir Pasang 258,500.00 M38. Pasir Beton 258,500.00 M39. Kerikil Sungai tdk Tersaring 223,200.00 M3

    10. Kerikil Sungai Tersaring 223,200.00 M311. Batu Pecah 3 - 5 cm 519,700.00 M312. Batu Pecah 2 - 3 cm 560,450.00 M313. Batu Pecah 1 - 2 cm 614,350.00 M314. A s p a l 4,817.50 M315. Minyak Bakar / Tanah 3,312.50 M316. Semen Putih 18,218.00 KG17. Semen PC ( @ 50 Kg ) 80,000.00 ZAK18. Semen PC ( @ 40 Kg ) 70,000.00 ZAK19. Tegel Porselin 11 x 11 CM 2,671.46 Bh20. Tegel Porselin 20 x 20 CM 4,687.50 Bh21. Tegel Keramik 10 x 20 CM 4,500.00 Bh22. Tegel Keramik 15 x 15 CM 4,068.82 Bh23. Tegel Keramik 20 x 20 CM 4,941.80 Bh24. Tegel Keramik 20 x 25 CM 5,708.50 Bh25. Tegel Keramik 30 x 30 CM 20,033.00 Bh26. Tegel Keramik 40 x 40 CM 23,767.20 Bh27. Tegel Mozaik 30 x 30 CM 14,275.43 BH28. Paving Blok 10,200.00 BH29. Conblok 22,023.50 BH30. Balok/Papan Kayu Matoa 2,000,000.00 M331. Balok/Papan Kayu Besi 2,500,000.00 M332. Balok/Papan Kayu Tinang 1,260,000.00 M333. Kayu List 30,000.00 M'34. Tripleks 3 MM 60,000.00 LBR35. Tripleks 4 MM 70,000.00 LBR

  • NO. U R A I A N HARGA SATUAN(Rp. / Unit)

    36. Teakwood 150,000.00 LBR37. Plywood 120,000.00 LBR38. Multipleks 15 MM 220,000.00 LBR39. Gypsum