  • REKAPITULASI RENCANA ANGGARAN BIAYA (RAB) PEMBANGUNAN RUMAH BERSALIN BAHAGIA

    PEKERJAAN : PEMBANGUNAN RUMAH BERSALIN BAHAGIASUMBER DANA : ANGGARAN : TAHUN 2010

    NO. JENIS PEKERJAAN TOTAL HARGA (Rp.)

    BANGUNAN A I. Pekerjaan Persiapan Rp. 43,400,000.00 II. Pekerjaan Tanah & Pondasi Rp. 79,798,756.40 III. Pekerjaan Struktur Beton Bertulang Rp. 162,935,346.09 IV. Pekerjaan Dinding dan Plesteran Rp. 96,471,253.80 V. Pekerjaan Pintu dan Jendela Rp. 106,433,819.75 VI. Pekerjaan Atap dan Plafond Rp. 252,579,633.33 VII. Pekerjaan Pengecatan Rp. 64,218,568.06 VIII. Pekerjaan Lantai Rp. 106,254,587.83 IX. Pekerjaan Instalasi Air Rp. 39,201,450.00 X. Pekerjaan Instalasi Listrik Rp. 52,795,500.00 XI. Pekerjaan Lain-lain Rp. 8,608,887.53

    Rp. 1,012,697,802.78 BANGUNAN B

    I. Pekerjaan Persiapan Rp. 1,500,000.00 II. Pekerjaan Tanah & Pondasi Rp. 78,428,875.99 III. Pekerjaan Struktur Beton Bertulang Rp. 166,667,495.96 IV. Pekerjaan Dinding dan Plesteran Rp. 14,474,608.89 V. Pekerjaan Atap dan Plafond Rp. 247,383,138.06 VI. Pekerjaan Pengecatan Rp. 29,210,587.23 VII. Pekerjaan Lantai Rp. 110,020,296.55 VIII. Pekerjaan Instalasi Air Rp. 30,044,100.00 IX. Pekerjaan Instalasi Listrik Rp. 15,001,850.00 X. Pekerjaan Lain-lain Rp. 12,568,423.94

    Rp. 705,299,376.63 Real Cost Rp. 1,717,997,179.41 Dibulatkan Rp. 1,717,990,000.00 Terbilang : Satu Milyar Tujuh Ratus Tujuh Belas Juta Sembilan Ratus Sembilan Puluh Ribu Rupiah,-

    Makassar, April 2010

    Perencana,

    Ir. H. Mursyid Mustafa, M.Si.

  • RENCANA ANGGARAN BIAYA (RAB) PEMBANGUNAN RUMAH BERSALIN BAHAGIA

    PEKERJAAN : PEMBANGUNAN RUMAH BERSALIN BAHAGIASUMBER DANA : ANGGARAN : TAHUN 2010

    NO. URAIAN PEKERJAAN VOL. SAT. HARGA SAT.

    BANGUNAN AI. Pekerjaan Persiapan1. Pembersihan Lokasi & Pas. Bowplank 1.00 Ls 5,000,000.00 2. Pembuatan Direksi Keet dan Gudang Sementara 1.00 Ls 8,400,000.00 3. Pengurusan Izin Mendirikan Bangunan (IMB) 1.00 Ls 30,000,000.00 II. Pekerjaan Tanah & Pondasi1. Galian Tanah Pondasi (1m) 211.53 m3 27,375.00 2. Galian Tanah Pondasi (2m) 9.72 m3 33,525.00 3. Urugan Kembali 52.88 m3 10,150.00 4. Pasir Urug Bawah Pondasi 21.80 m3 109,350.00 5. Pas. Batu Kosong 43.00 m3 255,495.00 6. Pondasi Batu Gunung 101.70 m3 466,215.00 7. Lantai Kerja Pondasi Poer; Rabat t=7cm 6.00 m2 40,799.22 8. Pondasi Poer P1

    ~Beton K225 1.46 m3 669,837.86 ~Besi Beton 212.16 Kg 10,330.00 ~BeKisting 2x Pakai 6.44 m2 78,805.00

    9. Pondasi Poer P2~Beton K225 0.62 m3 669,837.86 ~Besi Beton 79.39 Kg 10,330.00 ~BeKisting 2x Pakai 2.94 m2 78,805.00

    10. Stek Pondasi Poer P1~Beton K225 1.58 m3 669,837.86 ~Besi Beton 177.00 Kg 10,330.00 ~BeKisting 2x Pakai 14.52 m2 78,805.00

    11. Stek Pondasi Poer P2~Beton K225 0.59 m3 669,837.86 ~Besi Beton 66.57 Kg 10,330.00 ~BeKisting 2x Pakai 5.94 m2 78,805.00

    12. Pondasi Trassram Tangga Teras 1 Bata 2.16 m2 137,941.00 13. Pondasi Trassram Tangga Teras 1/2 Bata 16.39 m2 66,357.60 III. Pekerjaan Struktur Beton Bertulang1. Sloof S1 (20/30)

    ~Beton K225 13.72 m3 669,837.86 ~Besi Beton 1,806.52 Kg 10,330.00 ~BeKisting 2x Pakai 137.17 m2 84,055.00

    2. Kolom Praktis (14/14)~Beton K225 7.36 m3 669,837.86 ~Besi Beton 1,364.14 Kg 10,330.00 ~BeKisting 2x Pakai 210.42 m2 149,865.00

    3. Kolom K1 (30/80)~Beton K225 5.50 m3 669,837.86 ~Besi Beton 582.08 Kg 10,330.00 ~BeKisting 2x Pakai 50.42 m2 149,865.00

    4. Kolom K2 (30/80)~Beton K225 1.60 m3 669,837.86 ~Besi Beton 171.80 Kg 10,330.00 ~BeKisting 2x Pakai 16.02 m2 149,865.00

    5. Balok Ringbalk Rb1 (15/25)~Beton K225 8.70 m3 669,837.86 ~Besi Beton 1,408.70 Kg 10,330.00 ~BeKisting 2x Pakai 232.01 m1 46,547.50

    6. Pek. List Profil Beton 77.26 m1 250,000.00

  • NO. URAIAN PEKERJAAN VOL. SAT. HARGA SAT.IV. Pekerjaan Dinding dan Plesteran1. Pas. Dinding Tembok 1/2 Bata 625.00 m2 63,845.00 2. Plesteran Biasa (1:4) Dinding 1,219.63 m2 24,365.20 3. Plesteran Finishing Siar/Motif Garis (1:4) 93.95 m2 37,251.04 4. Plesteran Finishing Skoneng/Motif Kotak (1:4) 3.49 m2 37,251.04 5. Plesteran Beton (1:3) 175.56 m2 25,770.48 6. Pekerjaan Acian Semen 1,328.79 m2 14,071.00 V. Pekerjaan Pintu dan Jendela1. Pintu Type P1 =3 Unit

    ~Kusen Kayu Kls I 0.27 m3 10,363,500.00 ~Daun Pintu Panel Kayu Kls I 14.52 m2 517,250.00 ~Pas. Kaca Mati 5mm 3.52 m2 151,958.75 ~Engsel Pintu 24 Buah 33,600.00 ~Kunci Pintu 4 Buah 191,945.00 ~Expanyolet/Door Closer 6 Buah 165,000.00

    2. Pintu Type P2 = 8 Unit~Kusen Kayu Kls I 0.50 m3 10,363,500.00 ~Daun Pintu Panel Kayu Kls I 23.63 m2 517,250.00 ~Pas. Kaca Mati 5mm 5.70 m2 151,958.75 ~Engsel Pintu 48 Buah 33,600.00 ~Kunci Pintu 8 Buah 191,945.00 ~Expanyolet/Door Closer 8 Buah 165,000.00

    3. Pintu Type P3 = 7 Unit~Kusen Kayu Kls I 0.37 m3 10,363,500.00 ~Daun Pintu Panel Kayu Kls I 12.79 m2 517,250.00 ~Pas. Kaca Mati 5mm 3.18 m2 151,958.75 ~Engsel Pintu 21 Buah 33,600.00 ~Kunci Pintu 7 Buah 191,945.00 ~Expanyolet/Door Closer 7 Buah 165,000.00

    4. Pintu Type P4 = 7 Unit (Pintu PVC KM) 7 Unit 607,500.00 5. Jendela Type J1 = 4 Unit

    ~Kusen Aluminium 4" x 1 3/4" 58.52 m1 88,082.50 ~Pas. Kaca Mati 5mm 17.11 m2 151,958.75

    6. Jendela Type J2 = 3 Unit ~Kusen Aluminium 4" x 1 3/4" 35.48 m1 88,082.50 ~Pas. Kaca Mati 5mm 4.18 m2 151,958.75 ~Pas. Daun Jendela Kaca Rangka Aluminium (0.5x1.25)m2 6 Buah 357,589.71

    7. Jendela Type J3 = 1 Unit ~Kusen Aluminium 4" x 1 3/4" 9.90 m1 88,082.50 ~Pas. Kaca Mati 5mm 1.12 m2 151,958.75 ~Pas. Daun Jendela Kaca Rangka Aluminium (0.5x0.9) m2 2 Buah 290,958.98

    8. Jendela Type J4 = 1 Unit ~Kusen Aluminium 4" x 1 3/4" 14.08 m1 88,082.50 ~Pas. Kaca Mati 5mm 1.77 m2 151,958.75 ~Pas. Daun Jendela Kaca Rangka Aluminium (0.5x1.45) m2 2 Buah 395,664.41

    9. Jendela Type J5 = 1 Unit ~Kusen Aluminium 4" x 1 3/4" 14.52 m1 88,082.50 ~Pas. Kaca Mati 5mm 3.33 m2 151,958.75 ~Pas. Daun Jendela Kaca Rangka Aluminium (0.5x1.35) m2 2 Buah 376,627.06