    PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL

    LOKASI : BUMI PRESTASI KENCANA

    Harga Jumlah

    No. Sat Volume Satuan Harga

    ( Rp. ) ( Rp. )

    I PEKERJAAN PENDAHULUAN

    1 Pembersihan Lapangan m2

    280 4,050.00 1,134,000.00

    2 Pasangan Bowplank m' 52 16,915.00 879,580.00

    2,013,580.00

    II PEKERJAAN GALIAN / URUGAN

    1 Galian Tanah Pondasi m 20.610 27,570.00 568,217.70

    2 Urugan Tanah m 5.153 10,065.00 51,859.91

    3 Urugan Tanah Tambahan m 168.810 48,000.00 8,102,880.00

    4 Urugan Pasir Bawah Pondasi & Sloof t = 5 Cm m 3.825 108,000.00 413,100.00

    5 Urugan Pasir Bawah Lantai, t = 10 Cm m 5.627 108,000.00 607,716.00

    9,743,773.61

    III PEKERJAAN PONDASI

    1 Pekerjaan Pancang Ulin 10/10 - 400 ttk 134.000 126,810.00 16,992,540.00

    2 Pekerjaan Pondasi Roolag m 0.552 686,145.00 378,752.04

    17,371,292.04

    IV PEKERJAAN BETON

    1 Cor Lantai Kerja 1 : 3 : 5, t = 5 cm m 6.658 843,375.00 5,614,769.06

    2 Pondasi poer P1 m 3.308 3,220,726.00 10,652,551.25

    3 Pondasi poer P2 m 0.450 3,262,613.50 1,468,176.08

    4 Sloof ( 15 / 35 ) m 4.631 3,939,147.83 18,240,224.04

    5 Kolom K1 m 5.135 4,088,631.34 20,996,982.28

    6 Kolom K2 m 2.145 4,088,631.34 8,768,519.67

    7 Kolom K3 m 1.369 3,924,996.90 5,372,928.26

    8 Kolom Kp m 2.034 5,070,191.00 10,310,740.42

    9 Balok B1 (13 / 35) m 1.611 4,112,986.00 6,624,786.55

    10 Balok B2 (13 / 40) m 4.108 4,096,231.00 16,827,316.95

    11 Balok B3 (13 / 52) m 0.150 4,079,476.00 609,881.66

    12 Ring Balk (15 / 20) m 5.269 4,067,446.77 21,430,360.17

    13 Tangga beton bertulang m 1.880 4,036,077.20 7,587,825.14

    14 Plat Lantai, t=12cm m 14.400 4,036,077.20 58,119,511.6815 Dak Beton, t=10cm m 4.200 4,036,077.20 16,951,524.24

    16 Kanopi m 3.764 3,467,482.39 13,051,603.70

    222,627,701.13

    V PEKERJAAN DINDING / PLESTERAN

    1 Pasangan Batu bata 1 : 4 m 45.968 616,850.00 28,355,237.43

    2 Pasangan Batu bata 1 : 2 Trasram m 13.488 686,145.00 9,254,380.69

    3 Plesteran dinding bata 1 : 4 m 688.756 26,950.00 18,561,974.20

    4 Plesteran dinding bata 1 : 2 m 269.750 29,095.00 7,848,376.25

    64,019,968.57

    VI PEKERJAAN KAP / ATAP

    1 Pekerjaan kuda-kuda m 1.259 3,100,150.00 3,902,964.84

    2 Pekerjaan Rangka Atap Kayu Bengkirai m 120.630 116,025.00 13,996,095.75

    3 Pekerjaan Bout Angker Kuda - Kuda ls 1.000 500,000.00 500,000.00

    4 Pasangan Atap Genteng + Alumunium Foil (Moenir) m 120.630 132,480.00 15,981,062.405 Pekerjaan Lisplank papan 3/20 diloter m' 34.400 43,720.00 1,503,968.00

    35,884,090.99

    VII PEKERJAAN PLAFOND

    1 Plafond Gypsum polos + Rangka m 213.560 59,716.94 12,753,150.66

    2 Plafond Calsiboard + Rangka m 22.750 89,960.00 2,046,590.00

    3 List Plafond Gypsum m' 228.200 15,000.00 3,423,000.00

    18,222,740.66

    RENCANA ANGGARAN BIAYA

    Uraian Pekerjaan

    SUB TOTAL

    SUB TOTAL

    SUB TOTAL

    SUB TOTAL

    SUB TOTAL

    SUB TOTAL

    SUB TOTAL

    RAB halaman 1/ 3

  • 8/12/2019 RAB LENI

    2/3

    Harga Jumlah

    No. Sat Volume Satuan Harga

    ( Rp. ) ( Rp. )

    Uraian Pekerjaan

    VIII PEKERJAAN KUSEN, PINTU,JENDELA,PENGGANTUNG

    DAN KUNCI

    1 Pintu Tipe P1 Unit 9.000 1,655,650.00 14,900,850.00

    2 Pintu Tipe P2 Unit 2.000 1,085,250.00 2,170,500.00

    3 Pintu Tipe P3 Unit 1.000 1,016,250.00 1,016,250.00

    4 Pintu Tipe P4 Unit 1.000 986,250.00 986,250.00

    5 Jendela JX Unit 1.000 800,475.00 800,475.00

    6 Jendela J1 Unit 10.000 761,825.00 7,618,250.00

    7 Jendela J2 Unit 3.000 725,925.00 2,177,775.00

    8 Jendela J3 Unit 2.000 535,775.00 1,071,550.00

    9 Jendela J4 Unit 1.000 681,475.00 681,475.00

    10 Jendela J5 Unit 2.000 1,561,875.00 3,123,750.00

    11 Jendela J6 Unit 2.000 744,445.00 1,488,890.00

    12 BV1 Unit 3.000 1,253,725.00 3,761,175.00

    13 BV2 Unit 1.000 690,025.00 690,025.00

    40,487,215.00

    IX PEKERJAAN LANTAI

    1 Pas. Keramik Lt teras, Balkon, R.jemur (Roman Grez 33x33 KW1) m 55.980 104,884.13 5,871,413.32

    2 Pas. Keramik Lantai 60 x60 (Roman Motif KW 1) m 137.050 132,741.13 18,192,171.18

    3 Pas. Keramik Lantai Tangga 30 x 30 (Roman Motif KW 1) m 12.070 95,384.13 1,151,286.39

    4 Pas. Keramik Lantai km/wc 20 x 20 (Roman Motif KW 1) m 29.250 89,884.13 2,629,110.66

    5 Pas. Keramik Dinding km/wc 20x25 (Roman Motif KW 1) m 72.455 95,884.13 6,947,284.28

    6 Pas. Keramik Meja Pantry 20 x 20 (Roman Motif KW 1) m 3.000 89,884.13 269,652.38

    7 Pas. Keramik Dinding Pantry 20 x 20 (Roman Motif KW 1) m 6.500 89,884.13 584,246.81

    8 Pek. Plint Lantai Kayu m' 125.600 34,430.00 4,324,408.00

    39,969,573.01

    X PEKERJAAN PENGECATAN

    1 Pek. Cat dinding Luar (Mowilex Weather Coat) m 345.400 41,015.00 14,166,581.00

    2 Pek. Cat dinding Dalam (Mowilex) m 479.253 33,735.00 16,167,599.96

    3 Pek. Cat Plafond (Mowilex) m 236.310 33,735.00 7,971,917.85

    4 Pek. Polituran Plint Lantai Kayu (Ultran Lazur) m 12.560 80,920.00 1,016,355.20

    5 Pek. Melamic Kusen, P intu, dan Jendela, Ventilasi (Ultran Lazur) m 175.275 80,920.00 14,183,244.91

    6 Pek. Cat Minyak Lisplank m 6.880 37,797.75 260,048.52

    53,765,747.43

    XI PEKERJAAN PLUMBING / SANITAIR

    1 Pasang Pipa Air kotor PVC type AW 4" m' 45.000 36,750.00 1,653,750.00

    2 Pasang Pipa Air bekas PVC type AW 3" m' 70.000 26,250.00 1,837,500.00

    3 Pasang Pipa Instalasi Air Bersih type AW 3/4" m' 70.000 10,500.00 735,000.00

    4 Pasang Stop Kran 1/2" + instalasi (Setara Dupont) Bh 4.000 150,000.00 600,000.00

    5 Pasang Stop kran Leher angsa ut Kitchen Zinc + instalasi (Toto) Bh 1.000 250,000.00 250,000.00

    6 Pembuatan Septic Tank Dan Resapan Ls 1.000 2,000,000.00 2,000,000.00

    7 Closet Duduk (Toto) Bh 3.000 1,750,000.00 5,250,000.00

    8 Closet Jongkok (Toto) Bh - 350,000.00 -

    9 Wastafel (Toto) Bh 2.000 638,000.00 1,276,000.00

    10 Bathtub (Toto) Bh 1.000 2,500,000.00 2,500,000.00

    11 Shower u/. Closet duduk Bh 3.000 210,000.00 630,000.00

    12 Shower Screen Bh 1.000 450,000.00 450,000.00

    13 Tempat sabun tanam (Toto) Bh 3.000 80,000.00 240,000.00

    14 Pasang Roof Drain (Toto) Bh 5.000 50,000.00 250,000.00

    15 Pasang Floor Drain (Toto) Bh 3.000 75,000.00 225,000.00

    16 Reservoar Air / Tandon 2 ,5 m3 (dinding dan lantai dikeramikRoman 20/20 polos) Bh 1.000 1,500,000.00 1,500,000.00

    17 Reservoar /Tangki Air 650 Liter + dudukan Bh 1.000 1,100,000.00 1,100,000.00

    18 Pompa Air Dab 150 Watt Bh 1.000 1,250,000.00 1,250,000.00

    21,747,250.00

    XII PEKERJAAN LISTRIK

    1 Penyambungan daya listrik 3500 Watt Ls 1.000 2,000,000.00 2,000,000.00

    2 Pek. Pasang Stop kontak (Broco) + instalasi (Kabel Eterna) ttk 12.000 100,000.00 1,200,000.00

    3 Pek. Titik Lampu Biasa + instalasi ttk 17.000 125,000.00 2,125,000.00

    4 Pek. Titik Lampu Down Light (Crome)+ Instalasi (Kabel Eterna) ttk 27.000 150,000.00 4,050,000.00

    5 Pek. Pasang Saklar Tunggal dan Ganda ttk 24.000 100,000.00 2,400,000.00

    SUB TOTAL

    SUB TOTAL

    SUB TOTAL

    SUB TOTAL

    RAB halaman 2/ 3

  • 8/12/2019 RAB LENI

    3/3

    Harga Jumlah

    No. Sat Volume Satuan Harga

    ( Rp. ) ( Rp. )

    Uraian Pekerjaan

    6 Pek. Box + 3 MCB ttk 1.000 250,000.00 250,000.00

    7 Pek. Instalasi AC ttk 1.000 150,000.00 150,000.00

    8 Pasang Arde ttk 1.000 250,000.00 250,000.00

    9 Terminal TV Kabel + instalasi ttk 1.000 200,000.00 200,000.00

    10 Stop Kontak / Instalasi Telepon ttk 1.000 120,000.00 120,000.00

    11 Pek. Instalasi lampu taman (Kabel Eterna) ttk 1.000 175,000.00 175,000.00

    12 Pek. Instalasi lampu Spotlight (Kabel Eterna) ttk 2.000 150,000.00 300,000.00

    13 Pek. Instalasi lampu gantung (Kabel Eterna) ttk 1.000 150,000.00 150,000.00

    14 Box panel Listrik ttk 1.000 500,000.00 500,000.00

    13,870,000.00

    XIII PEKERJAAN LAIN - LAIN

    1 Pembuatan Meja Dapur + Kithcen Zinc Unit 15.000 1,800,000.00 27,000,000.00

    2 Pekerjaan parit keliling m' 34.000 66,225.00 2,251,650.00

    3 Ornamen, Profil Dinding, Benangan Ls 1.000 5,000,000.00 5,000,000.00

    4 Pek. Taman Standart pathway Ls 1.000 5,000,000.00 5,000,000.00

    5 Pekerjaan Water Proofing Dak m2 50.000 60,000.00 3,000,000.00

    6 Pek. Pas. Batu Alam m2 20.000 190,450.00 3,809,000.00

    7 Pekerjaan Carport (paving) m2 30.000 81,875.00 2,456,250.00

    8 Pekerjaan Railing Tangga, Balkon (Besi Hollow) m' 14.000 400,000.00 5,600,000.00

    9 Pekerjaan Kisi-kisi Kayu ut.Kanopi (Ulin 5/8) Ls - 200,000.00 -

    10 Pekerjaan Sunshadding (Besi Hollow) m' 15.000 300,000.00 4,500,000.00

    11 Pekerjaan Penangkal petir Bh 1.000 750,000.00 750,000.00

    - BC 16 mm2 penghantar

    - Ground pipa galvanis 1 " sedalam min 2.75 m

    - Pipa PVC 5/8 "

    59,366,900.00

    Samarinda, 25 September 2008

    SUB TOTAL

    SUB TOTAL

    ESTIMATOR

    Dibuat oleh,

    RAB halaman 3/ 3