1 | P a g e
DAFTAR ISI
I. Pengantar dari Panitia Pembangunan Gereja ……………………….. 2 II. Surat Keputusan Sinode ………………………………….......... 3
III. Sejarah GPIB Sawangan…………………………………………………. 6
IV. Disain Gereja .............................................................................................. 7 V. Rencana Anggaran Biaya ....................................................................................... 13
VI. Penutup ....................................................................................................... 20
VII. Lampiran a. Susunan Panitia Pembangunan Gereja ............................................... 21 b. Photo-photo Gereja Lama ................................................................... 23 c. Ijin Mendirikan Bangunan (IMB)…………………………………………… 26
2 | P a g e
PENGANTAR “Satu hal telah kuminta kepada TUHAN, itulah yang kuingini: diam di rumah TUHAN seumur hidupku, menyaksikan kemurahan TUHAN dan menikmati bait-Nya” Mazmur 27:4 Dua puluh tujuh tahun sudah jemaat GPIB Sawangan berdiri sebagai jemaat yang mandiri. Sejarah terwujudnya persekutuan orang-orang Kristen di daerah Sawangan dan sekitar telah melewati berbagai pergumulan dan tantangan. Namun oleh kasih Tuhan dan hanya atas kehendakNya berdirilah Persekutuan Jemaat GPIB “Bogor” Wilayah Pelayanan Sawangan sebagai cikal bakal terbentuknya jemaat Tuhan ini. Dia yang sudah memulai, Dia juga akan menjaga dan melanjutkan karya-Nya bagi pembangunan dan pertumbuhan gereja-Nya. Syukur kepada Tuhan karena dalam perkenananNya lah, tepat pada tanggal 13 Maret 1988 GPIB “Jemaat” Sawangan resmi berdiri sebagai lembaga Gereja yang mandiri. Namun demikian Seiring berjalan nya waktu yang membawa pertumbuhan jemaat secara signifikan menuntut kebutuhan akan ruang dan fasilitas ibadah yang lebih memadai sebagai jemaat yang missioner. Gedung Pertemuan Arco dan Gedung pendukung lainnya yang selama ini dipakai untuk kegiatan peribadahan dan kegiatan pelayanan lainnya saat ini, perlu dikembangkankan daya guna dan kapasitasnya untuk menjawab kbutuhan tersebut. Dalam rangka mewujudkan kerinduan ini kami Panitia Pembangunan GPIB Sawangan khususnya Team Asset telah melakukan daya dan upaya yang terus menerus. Kondisi status asset tanah dan bangunan yang masih belum dilegalisasi secara hukum mendorong Panitia khususnya team asset melakukan usaha merampungkan dokumen asset gereja tersebut. Lewat usaha gigih yang dilakukan dan atas pertolongan tangan Tuhan yang Maha Kuasa tentunya Panitia pembangunan berhasil menerbitkan dokumen penting antara lain 4 sertifikat Gereja dan Ijin Mendirikan Bangunan – IMB. Dengan telah terbitnya IMB tersebut makin memicu semangat kami untuk segera merealisasikan proses pembangunan yang menuntut untuk segera dilaksanakan. Oleh karena itu lewat Proposal permohonan dana Pembangunan Gedung gereja GPIB Sawangan ini kami ingin menyentuh pintu hati bapak/ibu saudara/I untuk turut ambil bagian dalam pembangunan fisik “Rumah Tuhan” ini sebagai sarana menunjang pertumbuhan pelayanan “Tubh Kristus” yang terikat menyatu dalam kasih untuk tetap mendatangkan berkat bagi orang banyak. Kami yakin dan percaya Tuhan telahlah yang berkehendak melibatkan bapak/ibu saudara/I semua untuk menjadi saluran berkat bagi kami. Sawangan, Maret 2015 Panitia Pembangunan Gedung Gereja GPIB Sawangan
3 | P a g e
4 | P a g e
5 | P a g e
6 | P a g e
Sejarah singkat
gpib sawangan Persekutuan Umat Kristen di ARCO Sawangan secara kronologis berawal dari sejumlah guru2 Inpres di Ciseeng tahun 1977 dan beberapa keluarga Kristen di Komplek ARCO Sawangan tahun 1978._ Persekutuan di ARCO ini kemudian disebut PUKAS (Persekutuan Umat Kristen ARCO Sawangan) yang terdiri dari anggota berbagai Denominasi termasuk umat Kristen Katolik. Namun umat Kristen Protestan dari Denominasi GPIB merupakan umat terbanyak yang pada akhir 1978 termasuk kedalam Persekutuan GPIB sebagai Wilayah Pelayanan GPIB Bogor (Zebaoth) di Bogor._ Ibadah Minggu rutinnya bertempat dirumah salah satu anggota Jemaat yang kemudian berpindah ke Gedung Pertemuan / Olahraga ARCO pada 1979._ Gedung Ibadah untuk PUKAS mulai dibangun 1984 dan digunakan akhir 1985. Karena izin resmi sebagai Gedung Ibadah belum diperoleh saat itu, maka Gedung berfungsi sebagai Gedung Serbaguna untuk aktifitas kerohanian Kristen dengan perubahan tampilan sebagaimana yang kita mikili saat ini. Pada 13 Maret 1988, Wilayah Pelayanan GPIB Bogor di Sawangan secara resmi dilembagakan menjadi Jemaat GPIB yang ke-184 dengan nama resmi “GPIB Jemaat Sawangan” dan tetap menggunakan Gedung Serbaguna ini sebagai sarana ibadah yang kemudian berproses menjadi 100% milik GPIB pada 1996._ Gedung ini mengalami sebuah renovasi total pada 1997 berupa penambahan ruang PELKAT dan Sekretariat menggunakan dana hasil usaha Panitia Pembangunan Pastori GPIB Sawangan yang berujung pada tukar guling gedung Pastori dengan lahan dibelakang Gedung Serbaguna/Gereja yang menghasilkan total dana sejumlah hampir Rp 500 juta pada awal semester ke-2 1997._Berkat ini dimanfaatkan juga untuk pembelian Pastori pengganti di jalan Manggis dan pembangunan Gedung Gereja Kartika Sejahtera (ex Sektor 2)._ Kita patut bersyukur kepada Allah didalam Yesus Kristus yang selalu menyertai dan memberkati Jemaat GPIB Sawangan. Oleh Panitia Pembangunan dan Renovasi Gedung Gereja GPIB Sawangan yang dibentuk pada Mei 2014 khusus tim asset nya yang melewati sebuah perjalanan panjang dan berliku telah berhasil memproses 4 (empat) sertifikat lahan dimana Gedung Serbaguna/Gereja berdiri dan juga pastori seluas total sekitar 3,200 M2 yang tadinya atas nama anggota Jemaat menjadi atas nama Gereja Protestan di Indonesia bagian Barat._Dan tepat di HUT GPIB Sawangan yang ke 27 izin Gedung Gereja ini diterbitkan setelah lebih 30 (tiga puluh tahun) digumuli._ Dan mengacu kalender kerja Panitia Pembangunan dan Renovasi Gedung Gereja GPIB Sawangan kegiatan dan upaya serta kerja keras tentu akan terus berlangsung untuk merealisasikan rancangan dan gambar yang sudah dicanangkan dan tentu merupakan bagian tak terpisahkan dari seluruh proses pengurusan izin-izin tersebut diatas._ Oleh karena itu Panitia mengharapkan Doa dan Bantuan seluruh Jemaat agar rencana Panitia yang sudah dicanangkan ini dapat direalisasikan dengan baik. Tuhan Memberkati kita sekalian._
7 | P a g e
disain bangunan
SITE PLAN – EXISTING
8 | P a g e
SITE PLAN – RENCANA
9 | P a g e
DENAH LANTAI DASAR & LANTAI 2
10 | P a g e
TAMPAK DEPAN &SAMPING
11 | P a g e
12 | P a g e
13 | P a g e
Rencana anggaran
Biaya (RAB)
Total biaya Rp 5.990.394.000 Lima Miliar Sembilan ratus Sembilan puluh juta tiga ratus Sembilan puluh empat ribu rupiah
NO. AMOUNT
I IDR 66,500,000
II STRUCTURE IDR 3,095,434,989
III ARCHITECTURE IDR 1,061,525,500
IV INTERIOR IDR 876,198,704
V MECHANICAL & ELECTRICAL IDR 890,735,000
SUB TOTAL IDR 5,990,394,193
ITEM
PRELIMINARY
ROUGHLY COST ESTIMATION
GRAND SUMMARY
Total area 1220 m² Biaya per m² : Rp 4.910.000,-
14 | P a g e
BIAYA PENDAHULUAN
UNIT PRICE TOTAL
A PRELIMINARIES
A.1 Preliminaries
1 Preparing works 1 ls 7,500,000IDR 7,500,000IDR
2 Safety equipment 1 ls 3,000,000IDR 3,000,000IDR
3 1 ls 12,000,000IDR 12,000,000IDR
4 1 ls IDR 3,000,000 3,000,000IDR
5 Temporary site office & other facil ities 1 ls 1,500,000IDR 1,500,000IDR
6 1 ls 1,000,000IDR 1,000,000IDR
7 Water for use of the contractors 1 ls 7,500,000IDR 7,500,000IDR
8 Lighting and power for use of the contractors 24 hours 1 ls 10,000,000IDR 10,000,000IDR
9 Equipment & transportation 1 ls ‐IDR
10 Protection of the works 1 ls 7,500,000IDR 7,500,000IDR
12 Final cleaning 1 ls 10,000,000IDR 10,000,000IDR
13 1 ls 3,500,000IDR 3,500,000IDR
a
TOTAL 66,500,000IDR
PRELIMINARIES
ROUGHLY COST ESTIMATION
contractor is fully responsibble of care and obtain the permits of relevant agencies
in connection with the implementation of activities in the project work and
implemantation activities into and out of transportation project,including debrish
removal permit.
AMOUNT
contractor must provide temporary power generation or article l ighting for night
work or day l ighting used
Preparing, submitting and revising shop drawings & 4 sets of closed out documents
(list material, warranty and as built drawings)
Contractor do site survey,Measurement with bowplank (using theodolite) Equipment
of P3K,and coordination with related parties,contarctor also must provide the
necessary equipment such as: optical measuring instrument,waterpass etc,and
experience surveyor who sometimes can be assigned to the measurement of as as
buildings (vertical and horizontal).
NO. ITEM QTY
Permits and removal of rubbish at regular intervals
Meeting & report
Conttractor responsible for the procurement of safety equipment such as: Helmet
works,field boots,raincoat,safety belt,safety net& other as needed for purpose of
workers & staff of contractor.
contractor must provide labors of the needs of water obtained from existing sources
or purchase of water works etc, contractor must make the connection as necessary
Crane or transport eguipment to the top
Contractor must provide the necessary facil ites include consumption for the
implementation of routine meeting with client,consultant & contarctor other
package
15 | P a g e
PEKERJAAN STRUKTUR
UNIT PRICE AMOUNT
I DEMOLITION WORK
‐IDR
II SOIL WORK
1 Cut, Fill & Compaction As 4'~0 / B'~K, As J~K / 2 197.362 M3 200,000IDR 39,472,400IDR
III FOUNDATION WORK
1 Bore Pile Ø300, Length=20m,84 Unit 1180 M1 330,000IDR 389,400,000IDR
2 PDA Test, 3 Unit 2 Unit 9,750,000IDR 19,500,000IDR
3 Pilecap K‐250, U‐39 43 M3 5,125,000IDR 220,375,000IDR
4 Tie Beam K‐250, U‐39 62 M3 5,150,000IDR 319,300,000IDR
5 Pedestal K‐250, U‐39 3.5 M3 5,150,000IDR 18,025,000IDR
6 Ground Floor Slab On Grade, t=150mm, K‐250, U‐39 46 M3 4,850,000IDR 223,100,000IDR
7 Slab Concrete, t=200mm, K‐250, U‐39 46 M3 4,850,000IDR 223,100,000IDR
1,412,800,000IDR
IV UPPER STRUCTURE WORK
1 Steel Column K1 HB.200x200x8x12 (incl plate and bolt) 650 kg 18,500IDR 12,025,000IDR
2 Steel Column K1‐K HB.200x200x8x12 (incl plate and bolt) 560 kg 18,500IDR 10,360,000IDR
3 Concrete For Column K1‐K(Composite), K‐250, U‐39 1.18163 M3 5,125,000IDR 6,055,844IDR
4 Steel Pipe Column K2 Ø250, t=9.3mm (incl plate and bolt) 6250 kg 22,300IDR 139,375,000IDR
5 Concrete For Column K2, K‐250, U‐39 6.235 M3 5,125,000IDR 31,954,375IDR
6 Steel Column K4 HB.30X300X10X15 (incl plate and bolt) 6200 kg 18,500IDR 114,700,000IDR
7 Steel Beam WF.150x75x5x7 (incl plate and bolt) 934.5 kg 18,500IDR 17,288,250IDR
8 Steel Beam WF.200x100x5.5x8 (incl plate and bolt) 6023 kg 18,500IDR 111,425,500IDR
9 Steel Beam WF.300x150x6.5x9 (incl plate and bolt) 15326 kg 18,500IDR 283,531,000IDR
10 Steel Beam WF.350x175x7x11 (incl plate and bolt) 7768 kg 18,500IDR 143,708,000IDR
11 Steel Beam WF.400x200x8x13 (incl plate and bolt) 4123 kg 18,500IDR 76,275,500IDR
12 Steel Ring Beam HB.200x200x8x12 (incl plate and bolt) 4629 kg 18,500IDR 85,636,500IDR
13 Steel Ring Beam WF.250X125X6X9 (incl plate and bolt) 663 kg 18,500IDR 12,265,500IDR
14 Purlin CNP.150x65x20x2.3 (incl plate and bolt) 2978 kg 17,540IDR 52,234,120IDR
15 Slab Concrete, t=100mm, K‐250, U‐39 78.4 M3 5,125,000IDR 401,800,000IDR
16 Bondek Plate, t=0.75mm ex‐BHP 256 M2 213,000IDR 54,528,000IDR
1,553,162,589IDR
V STAIRCASE WORK (2 units)1 Staircase Beam, Staircase Steps & Chequer Plate t=3mm 2 ls 45,000,000IDR 90,000,000IDR
Total 3,095,434,989IDR
AMOUNTNO. ITEM QTY
ROUGHLY COST ESTIMATION
STRUCTURE
16 | P a g e
PEKERJAAN ARSITEKTUR
UNIT PRICE AMOUNT
I DEMOLITION
1 Demolish existing Brick Wall Celcon (include window opening) 175 m² 25,000IDR 4,375,000IDR
2 Dismantle existing Exterior Glass window 23 unit 250,000IDR 5,750,000IDR
3 Demolish existing stair 1 lot 1,500,000IDR 1,500,000IDR
4 Dismantle existing terrace ceramic 63 m² 15,000IDR 945,000IDR
12,570,000IDR
II PARTITION & FAÇADE
1 Brick Wall Celcon , w/ cement plaster ‐ ready to receive wall finishes material on the inside 902 m² 265,000IDR 239,030,000IDR
2 Column concrete base 18 m¹ 680,000IDR 12,240,000IDR
‐ to cover all exposed column ‐ w/ stone coating finish 400mm x 400mm
251,270,000IDR
III DOOR & WINDOW
GROUND FLOOR
1 D1 Single aluminium door with glass panel (900x2800mm) 2 unit 5,100,000IDR 10,200,000IDR
‐ 50/100 mm aluminium door jamb anodize finish color ‐ black
‐ 40mm thk aluminium door with anodize finish, color ‐ black
‐ 8mm thk clear glass panel
‐ door ironmongery specification as describe in technical specification
‐ Selected door handle
‐ Selected door stopper
‐ Hinges, ex Simon werk K05/f13‐Zp
‐ Concealed door closer, ex Dorma TS 90/2‐4/Silver 2 unit 1,250,000IDR 2,500,000IDR
2 D2 Double aluminium door with glass panel (900x2800mm) 4 unit 9,200,000IDR 36,800,000IDR
‐ 50/100 mm aluminium door jamb anodize finish color ‐ black
‐ 40mm thk aluminium door with anodize finish, color ‐ black
‐ 8mm thk clear glass panel
‐ door ironmongery specification as describe in technical specification
‐ Selected door handle
‐ Selected door stopper
‐ Hinges, ex Simon werk K05/f13‐Zp
‐ Concealed door closer, ex Dorma TS 90/2‐4/Silver 8 unit 1,250,000IDR 10,000,000IDR
3 AW‐06 Aluminium window louver 2100x500mm 4 unit 1,540,000IDR 6,160,000IDR
‐ 50/100 mm aluminium door jamb anodize finish color ‐ black
‐ 40mm thk aluminium window with anodize finish, color ‐ black
‐ 8mm thk clear glass panel
4 AW‐10 Aluminium window 800x2800mm 10 unit 1,350,000IDR 13,500,000IDR
‐ 50/100 mm aluminium door jamb anodize finish color ‐ black
‐ 40mm thk aluminium window with anodize finish, color ‐ black , at the center module
‐ 8mm thk clear glass panel
5 AW‐11 Aluminium window 800x2000mm 20 unit 2,500,000IDR 50,000,000IDR
‐ 50/100 mm aluminium door jamb anodize finish color ‐ black
‐ 40mm thk aluminium window with anodize finish, color ‐ black , at the center module
‐ 8mm thk clear glass panel
1st FLOOR
6 AW‐10 Aluminium window 800x2800mm 10 unit 1,350,000IDR 13,500,000IDR
‐ 50/100 mm aluminium door jamb anodize finish color ‐ black
‐ 40mm thk aluminium window with anodize finish, color ‐ black , at the center module
‐ 8mm thk clear glass panel
7 AW‐11 Aluminium window 800x2000mm 35 unit 2,500,000IDR 87,500,000IDR
‐ 50/100 mm aluminium door jamb anodize finish color ‐ black
‐ 40mm thk aluminium window with anodize finish, color ‐ black , at the center module
‐ 8mm thk clear glass panel
230,160,000IDR
Total II
ROUGHLY COST ESTIMATION
ARCHITECTURE
QTYNo
Total III
AMOUNTItem
Total I
17 | P a g e
PEKERJAAN ARSITEKTUR
IV
1 Wall paint finish 1,010 m² 75,000IDR 75,750,000IDR
‐ ICI Dulux wether shield
75,750,000IDR
V
1 Water proof gypsum board ceil ing 9 mm ex jaya board/eq 210 m² 175,000IDR 36,750,000IDR
‐ CH 2800 w/paint finish ICI briliant white
2 Roof Metal roof blue scope ex Lysaght
‐ Metal roof sheet Trimdek 040TCT Zincalume 450 m² 495,000IDR 222,750,000IDR
‐ framming 450 m² 95,000IDR 42,750,000IDR
‐ Insulation 450 m² 115,000IDR 51,750,000IDR
3 Concrete roof
‐ Floor screed 20 m² 45,000IDR 900,000IDR
‐ Waterproofing 20 m² 125,000IDR 2,500,000IDR
357,400,000IDR
VI FLOOR FINISHES
1 CT‐03 Ceramic ti le for External Corridor 84.7 m² 165,000IDR 13,975,500IDR
2 CT‐03 Ceramic ti le for stair + Nosing 280 m² 190,000IDR 53,200,000IDR
67,175,500IDR
VII
2 Lanscape & hardscape 1 ls 12,000,000IDR 12,000,000IDR
3 Railing Stair & parimeter fence on the 1st floor
‐ Steel w/ duco pain finish 106 m' 450,000IDR 47,700,000IDR
‐ Slink
4 2 unit 1,500,000IDR 3,000,000IDR
‐ brick wall + screed
‐ paint finish
‐ including top w/plate 5 mm
5 Cat Ladder 1 unit 4,500,000IDR 4,500,000IDR
‐ Ø 2" st.steel w/Paint finish
67,200,000IDR
TOTAL 1,061,525,500IDR
Total VII
Garbage box 1500 height
CEILING & ROOF
WALL FINISHES
MISCELLANEOUS
Total VI
Total IV
Total V
18 | P a g e
PEKERJAAN INTERIOR
NO. AMOUNT
A
I PRELIMINARIES IDR 8,500,000
II DEMOLITION WORKS IDR ‐
III PARTITION WORKS IDR 148,603,700
IV DOORS IDR 91,250,000
V WALL FINISHES IDR 33,453,000
VI CEILING WORKS IDR 65,879,000
VII FLOOR FINISHES IDR 74,760,000
VIII FURNITURE WORKS IDR 121,250,000
XI TOILET & SANITARY IDR 61,256,000
XII MISCELLANEOUS IDR 24,600,000
Total A IDR 629,551,700
B
I PRELIMINARIES IDR 8,500,000
II DEMOLITION WORKS IDR ‐
III PARTITION WORKS IDR 3,861,000
IV DOORS IDR 5,000,004
V WALL FINISHES IDR 10,500,000
VI CEILING WORKS IDR 71,210,000
VII FLOOR FINISHES IDR 114,576,000
XII MISCELLANEOUS IDR 33,000,000
Total B IDR 246,647,004
GRAND TOTAL IDR 876,198,704
GROUND FLOOR
ITEM
LOWER GROUND
ROUGHLY COST ESTIMATION
INTERIOR
SUNMMARY
19 | P a g e
PEKERJAAN MEKANIKAL - ELEKTRIKAL
NO. AMOUNT
A.I MECHANICAL & ELECTRICAL, FIRE ALARM , SOUND SYSTEM 438,932,600IDR
AND PLUMBING WORKS LEVEL ‐ 1ST FLOOR
B.I MECHANICAL & ELECTRICAL, FIRE ALARM , SOUND SYSTEM 246,390,400IDR
AND PLUMBING WORKS LEVEL ‐ 2ND FLOOR
C.I ROOF TANK 27,000,000IDR
D.I HALOTRON WORKS ‐IDR
E.I RAIN WATER PIPE WORKS 110,562,000IDR
F.I UPS POWER SUPPLY ‐ SERVER ‐IDR
G.I LIGHTING PROTECTION 62,850,000IDR
H.I UPS POWER SUPPLY ‐ WORKING AREA ‐IDR
I.I TEST AND COMMISIONING WORKS ALL SYSTEM 2,500,000IDR
J.I AS ‐ BUILT DRAWING AND DOCUMENTATION HAND OVER 2,500,000IDR
TOTAL ALL ITEMS 890,735,000IDR
DESCRIPTION
MECHNICAL & ELECTRICAL
ROUGHLY COST ESTIMATION
SUMMARY
RENCANA PENGGALANGAN DANA Proyek Tahap 1 : Pekerjaan Struktur Rp 3.095.434.989,- Aksi Dana :
1. Aksi Janji Iman Jemaat – Kontribusi per m² proyek : a. Target 200 Kepala Keluarga x Rp 5.000.000,- = Rp 1.000.000.000,-
2. Proposal Keluar – 100 proposal x Rp 10.000.000,- = Rp 1.000.000,000,- 3. Dinner Charity = Rp 500.000.000,- 4. Aksi Dana Lainnya = Rp 595,434,989,-
__________________________________________________________________ Total Rp 3.095.434.989,-
20 | P a g e
PENUTUP
Kita patut mengucap syukur atas pemeliharaan Tuhan terhadap gerak pelayanan GPIB Sawangan yang terus terpelihara secara baik. Oleh karena itu melalui surat ini sekali lagi kami ingin mengajak bapak/ibu. Saudara/I untuk menyatakan syukur itu dengan membagikan berkat yang Tuhan beri dengan tulus dan ikhlas, guna menopang usaha dana ini sebagai aksi “ Janji Iman” kita kepada Tuhan. Namun demikian kami mengimani bahwa usaha dana yang gigih tanpa disertai oleh doa akan berakhir sia-sia. Oleh karena itu kami juga mohon dukungan doa seluruh jemaat atas segala usaha, dan daya upaya yang kami lakukan. Biarlah apa yang kita lakukan bersama ini berkenan bagi Tuhan, dan menjadi berkat bagi kita masing-masing dan bagi pertumbuhan jemaat GPIB Sawangan secara umum. Tuhan Yesus memberkati saudara dan pemberian saudara.
21 | P a g e
SURAT KESEDIAAN DONATUR
Yang bertanda tangan di bawah ini :
Nama : ______________________________________________
Alamat : ______________________________________________
______________________________________________
Bersedia menjadi donator Biaya PembangunanGPIB Sawangan
Jumlah donasi : Rp _______________
Terbilang : ____________________________________________
____________________________________________
____,_____________ 2015
[_____________________]
TANDA TERIMA
Telah terima dari : ________________________________________
Uang sebesar : ________________________________________
Terbilang : Rp _______________
Untuk pembayaran : ________________________________________
Panitia Pembangunan GPIB Sawangan
____,_____________ 2015
[_____________________]
22 | P a g e
LAMPIRAN 1 - IMB
23 | P a g e