  • REKAPITULASI AKHIR RENCANA ANGGARAN BIAYA (RAB)KEGIATAN BELANJA MODAL

    PENGADAAN KONSTRUKSI / PEMBELIAN GEDUNG KANTOR

    KEGIATAN : BELANJA MODAL PENGADAAN KONSTRUKSI / PEMBELIAN GEDUNG KANTORPEKERJAAN : TAMAN SYECH YUSUF DISCOVERYANGGARAN : 2008

    NO URAIAN PEKERJAAN TOTAL HARGA

    A PEK. PINTU GERBANG Rp 235,065,000.00

    B PEK. PAGAR KELILING DEPAN / SAMPING Rp 695,983,000.00

    C PEK. PAGAR PRECAST Rp 81,912,000.00

    A Real Cost + PPN 10 % Rp 1,012,960,000.00 B Dibulatkan Rp 1,012,960,000.00

    Sungguminasa, 11 Agustus 2008

    PenawarPT. BRAGAS CIPTA CORPORATION

    IR. ANDRIAS. P PARABANG Direktur

    Terbilang : SATU MILYAR DUA BELAS JUTA SEMBILAN RATUS ENAM PULUH RIBU RUPIAH,-

  • REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)TAMAN SYECH YUSUF DISCOVERY

    PEKERJAAN : TAMAN SYECH YUSUF DISCOVERYUNIT PEKERJAAN : PINTU GERBANGANGGARAN : 2008

    NO URAIAN PEKERJAAN TOTAL HARGA

    I PEK. PERSIAPAN Rp 3,859,520.00 II PEK. TANAH DAN PONDASI Rp 18,184,642.03 III PEK. STRUKTUR BETON Rp 43,786,188.67 IV PEK. DINDING DAN PLESTERAN Rp 13,383,529.22 V PEK. RANGKA KAP DAN ATAP Rp 103,901,057.71 VI PEK. PLAFOND Rp 9,350,194.60 VII PEK. PENGECETAN Rp 2,224,721.84 VIII PEK. PINTU PAGAR Rp 18,006,192.09 IX PEK. LAIN-LAIN Rp 1,000,000.00

    JUMLAH Rp 213,696,046.15 PPn 10% Rp 21,369,604.61 TOTAL Rp 235,065,650.76 DIBULATKAN Rp 235,065,000.00

    Terbilang : DUA RATUS TIGA PULUH LIMA JUTA ENAM PULUH LIMA RIBU RUPIAH,-

    Sungguminasa, 11 Agustus 2008

    PenawarPT. BRAGAS CIPTA CORPORATION

    IR. ANDRIAS. P PARABANGDirektur

  • RENCANA ANGGARAN BIAYA (RAB)TAMAN SYECH YUSUF DISCOVERY

    PEKERJAAN : TAMAN SYECH YUSUF DISCOVERYUNIT PEKERJAAN : PINTU GERBANGANGGARAN : 2008

    NO URAIAN PEKERJAAN Volume Satuan HARGA SAT. JUMLAH

    (Rp) HARGA (RP)

    A PEK. PINTU GERBANGI PEK. PERSIAPAN

    1 Direksikeet + P3K 1.00 ls 1,500,000.00 1,500,000.00 2 Papan Proyek 1.00 ls 450,000.00 450,000.00 3 Administrasi, Dokumentasi & Quality Kontrol 1.00 ls 1,500,000.00 1,500,000.00 4 Pek. Boeplank 20.00 m' 20,476.00 409,520.00

    Jumlah 3,859,520.00 II PEK. TANAH DAN PONDASI

    1 Pek. Galian Tanah 23.20 m3 12,720.00 295,104.00 2 Pek. Lantai Kerja, Tebal 5 cm 11.04 m2 52,443.50 578,976.24 3 Pek. Pondasi Poer K225 2.26 m3 2,514,831.27 5,683,518.67 4 Pek. Pondasi Batu Gunung 1:4 13.43 m3 341,370.00 4,584,599.10 5 Pek. Stek Poer 30/40 K225 2.20 m2 3,181,819.06 7,000,001.94 6 Pek. Urugan Kembali 6.96 m2 6,098.00 42,442.08

    Jumlah 18,184,642.03 III PEK. STRUKTUR BETON

    1 Pek. Sloef 20/30 K225 0.55 0.55 m3 2,704,762.08 1,487,619.14 2 Pek. Kolom 30/40 K225 8.30 8.30 m3 3,181,819.06 26,409,098.22 3 Pek. Balok Beton 20/30 K225 2.44 2.44 m3 3,484,145.73 8,501,315.57 4 Pek. Plat Beton Tebal 12 cm K225 1.82 1.82 m3 2,958,010.06 5,383,578.30 5 Pek. Kolom Praktis 12/15 1:2:3 0.50 0.50 m3 3,452,502.75 1,726,251.38 6 Pek. Ringbalok Praktis 12/15 1:2:3 0.08 0.08 m' 3,479,075.69 278,326.05

    Jumlah 43,786,188.67 IV PEK. DINDING DAN PLESTERAN

    1 Pek. Dinding Trasram 1 Batu 1:2 3.30 m2 109,470.00 361,251.00 2 Pek. Dinding 1 Batu 1:5 22.50 m2 92,082.00 2,071,845.00 3 Pek. Dinding 1 Batu 1:5 17.00 m2 92,082.00 1,565,394.00 4 Pek. Plesteran Trasram 1:2 3.30 m2 22,150.00 73,095.00 5 Pek. Plesteran 1:5 22.50 m2 18,775.00 422,437.50 6 Pek. Plesteran Beton 1:2 27.80 m2 22,150.00 615,770.00 7 Pek. Acian 53.60 m2 10,252.70 549,544.72 8 Pek. Les / Profil Kaki Tiang 59.20 m' 50,000.00 2,960,000.00 9 Pek. Les / Profil Kepala Tiang 16.80 m' 50,000.00 840,000.00 10 Pek. Les / Profil Setempat Tiang 24.00 m' 20,000.00 480,000.00 11 Pek. Batu Tempel Palimanan Uk. 15x15 - Kembang 24.00 m' 143,508.00 3,444,192.00

    Jumlah 13,383,529.22

  • NO URAIAN PEKERJAAN Volume Satuan HARGA SAT. JUMLAH

    (Rp) HARGA (RP)

    V PEK. RANGKA KAP DAN ATAP 1 Pek. Rangka Baja IWF 250.125.6,9 mm 911.10 kg 15,827.40 14,420,344.14 2 Pek. Rangka Baja Siku 70.70.7 132.29 m' 67,900.21 8,982,517.21 3 Pek. Plat Simpul Tebal 10/8 cm 104.50 m' 17,917.40 1,872,368.30 4 Pek. Rangka Atap Baja Ringan 98.50 m2 218,108.28 21,483,665.78 5 Pek. Atap Genteng Genteng Kramik (Ex. Kia) 98.50 m2 132,506.00 13,051,841.00 6 Pek. Nok Genteng Kramik 24.20 m' 101,532.00 2,457,074.40 7 Pek. Lisplank Woodplank (Lebar 38 cm) 60.15 m' 189,118.13 11,375,455.22 8 Pek. Portal Rangka Hollow 4/4, Tebal 2,3 mm + ACC 139.10 m' 57,507.67 7,999,316.43 9 Pek. Dinding GRC + Rangka Hollow 10.35 m2 139,920.25 1,448,174.59 10 Penutup Bidang Hollow 2/4, Tebal 1,5 mm + ACC 412.80 m' 50,412.55 20,810,300.64

    Jumlah 103,901,057.71 VI PEK. PLAFOND

    1 Pek. Plafond GRC + Rangka Hollow 59.20 m2 139,920.25 8,283,278.80 2 Pek. Les Plafond Kayu 4/4 104.40 m2 10,219.50 1,066,915.80

    Jumlah 9,350,194.60 VII PEK. PENGECETAN

    1 Pek. Cat Tembok (Ex. Mowilex) 53.60 m2 18,610.00 997,496.00 2 Pek. Cat Plafond + Les (Ex. Metrolite) 64.42 m2 10,744.00 692,128.48 3 Pek. Cat Besi Hollow (Ex. Glotex) 33.02 m2 16,205.25 535,097.36

    Jumlah 2,224,721.84 VIII PEK. PINTU PAGAR

    1 Pek. Pintu Pagar 14.00 m' 1,286,156.58 18,006,192.09 Terpasang Lengkap, Termasuk Rel, Tiang Penyanggah, Cat,

    Finishing Cat, Gembok, Accessories Dll

    Jumlah 18,006,192.09 IX PEK. LAIN-LAIN

    1 Pek. Pembersihan 1.00 ls 1,000,000.00 1,000,000.00 Jumlah 1,000,000.00

    213,696,046.15

  • REKAPITULASI RENCANA ANGGARAN BIAYA TAMAN SYECH YUSUF DISCOVERY

    PEKERJAAN : TAMAN SYECH YUSUF DISCOVERYUNIT PEKERJAAN : PAGAR KELILINGANGGARAN : 2008

    NO URAIAN PEKERJAAN TOTAL HARGA

    I PEK. PERSIAPAN Rp 5,192,416.33

    II PEK. PILAR PAGAR Rp 62,419,842.93

    III PEK. DINDING ANTARA PILAR PAGAR Rp 361,509,628.97

    IV PEK. PAGAR BESI Rp 202,590,284.50

    V PEKERJAAN LAIN-LAIN Rp 1,000,000.00

    JUMLAH Rp 632,712,172.73

    PPn 10% Rp 63,271,217.27

    TOTAL Rp 695,983,390.00

    DIBULATKAN Rp 695,983,000.00

    Sungguminasa, 11 Agustus 2008

    PenawarPT. BRAGAS CIPTA CORPORATION

    IR. ANDRIAS. P PARABANGDirektur

    Terbilang : ENAM RATUS SEMBILAN PULUH LIMA JUTA SEMBILAN RATUS DELAPAN PULUH TIGA RIBU RUPIAH,-

  • RENCANA ANGGARAN BIAYA (RAB)TAMAN SYECH YUSUF DISCOVERY

    PEKERJAAN : TAMAN SYECH YUSUF DISCOVERYUNIT PEKERJAAN : PAGAR KELILINGANGGARAN : 2008

    NO URAIAN PEKERJAAN Volume Satuan HARGA SAT. JUMLAH

    (Rp) HARGA (RP)

    B PEK. PAGAR KELILING DEPAN / SAMPINGI PEK. PERSIAPAN

    1 Pengukuran + Bouplank 69.44 M' 32,290.58 2,242,416.33 2 Direksikeet + P3K 1.00 ls 1,000,000.00 1,000,000.00 3 Papan Proyek 1.00 ls 450,000.00 450,000.00 4 Administrasi, Dokumentasi & Quality Kontrol 1.00 ls 1,500,000.00 1,500,000.00

    Jumlah 5,192,416.33 II PEK. PILAR PAGAR 48.00 Bh

    1 Pek. Galian Tanah 3.84 M3 12,720.00 48,844.80 2 Pek. Urugan Tanah Kembali 0.96 M3 6,098.00 5,854.08 3 Pek. Pondasi Bt.Gunung 13.44 M3 341,370.00 4,588,012.80 4 Pek. Pas. Bt. Kosong 1.92 M3 147,147.00 282,522.24 5 Pek. Pasir Urug Bawah Pondasi 0.96 M3 84,380.00 81,004.80 6 Pek. K