Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna...

18
PERENCANAAN LI POSITION WEIGHT (RA) GUNA M Fakultas Te Untuk A UNIVERSIT INE BALANCING DENGAN METO T (RPW) DAN METODE REGION A MENINGKATKAN OUTPUT PROD SKRIPSI Diajukan Kepada : eknik Universitas Muhammadiyah Malang k Memenuhi Salah Satu Persyaratan Akademik Dalam Menyelesaikan Program Sarjana Teknik Disusun Oleh : ABDUL ARIJAL TAUFIQ ( 02540018 ) JURUSAN INDUSTRI FAKULTAS TEKNIK TAS MUHAMMADIYAH MALA 2008 ODE RANK APPROACH DUKSI g ANG

Transcript of Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna...

Page 1: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi

PERENCANAAN LINE BALANCING DENGAN METODE RANK

POSITION WEIGHT (RPW) DAN METODE REGION APPROACH

(RA) GUNA MENINGKATKAN OUTPUT PRODUKSI

Fakultas Teknik Universitas Muhammadiyah Malang

Untuk Memenuhi Salah Satu Persyaratan

Akademik Dalam Menyelesaikan

UNIVERSITAS MUHAMMADIYAH MALANG

PERENCANAAN LINE BALANCING DENGAN METODE RANK

POSITION WEIGHT (RPW) DAN METODE REGION APPROACH

(RA) GUNA MENINGKATKAN OUTPUT PRODUKSI

SKRIPSI

Diajukan Kepada :

Fakultas Teknik Universitas Muhammadiyah Malang

Untuk Memenuhi Salah Satu Persyaratan

Akademik Dalam Menyelesaikan

Program Sarjana Teknik

Disusun Oleh :

ABDUL ARIJAL TAUFIQ

( 02540018 )

JURUSAN INDUSTRI

FAKULTAS TEKNIK

UNIVERSITAS MUHAMMADIYAH MALANG

2008

PERENCANAAN LINE BALANCING DENGAN METODE RANK

POSITION WEIGHT (RPW) DAN METODE REGION APPROACH

(RA) GUNA MENINGKATKAN OUTPUT PRODUKSI

Fakultas Teknik Universitas Muhammadiyah Malang

UNIVERSITAS MUHAMMADIYAH MALANG

Page 2: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi
Page 3: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi
Page 4: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi
Page 5: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi
Page 6: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi
Page 7: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi

ABSTRAKSI

ABDUL ARIJAL TAUFIQ, 2008, NIM.02540018, PERENCANAAN LINE BALANCING

DENGAN METODE RANK POSITION WEIGHT ( RPW ) DAN METODE REGION

APPROACH ( RA ) GUNA MENINGKATKAN OUTPUT PRODUKSI DI KOPERASI

INTAKO TANGGULANGIN SIDOARJO, Skripsi Jurusan Teknik Industri Fakultas Teknik

Universitas Muhammadiyah Malang. Pembimbing I : Ir. H. M. LUKMAN, MT. Pembimbing

II : ANNISA KESSY, G. ST. MT.

Permasalahan line balancing dalam aliran produksi terkadang masih diabaikan oleh

perusahaan, meskipun pada kenyataannya masalah line balancing merupakan salah satu yang

memegang peranan penting dalam pemenuhan target produksi yang telah direncanakan.

Koperasi INTAKO pada divisi pabrik yang terletak di tanggulangin sidoarjo merupakan

koprasi yang menghasilkan beraneka ragam jenis tas perempuan. Permasalahan yang

dihadapi koperasi INTAKO adalah sering kali adanya penambahan jam kerja (lembur) hal ini

diakibatkan tidak dapat memenuhi permintaan pasar yang disebabkan karena rendahnya

jumlah produksi akibat kurang seimbangnya lintasan produksi.

Dalam upaya menyelesaikan masalah tersebut digunakan metode rank position weight

dan region approach yang merupakan metode heuristic dengan pendekatan trial and error

untuk membandingkan kondisi awal dengan kondisi setelah perencanaan metode line

balancing pada koperasi INTAKO. Yang meliputi balance delay, efisiensi lintasan, dan

output produksi.

Berdasarkan hasil analisa ternyata dari kedua metode didapatkan hasil perhitungan

balance delay awal 23% berkurang menjadi 21% dengan metode rank position weight. Dan

17% dengan metode region approach. Sedangkan efisiensi lintasan dari kondisi awal sebesar

77% meningkat menjadi 79% dengan metode rank position wight, dan 83% dengan metode

region approach. Output produksi tas perempuan meningkat dari kondisi awal 1848

unit/bulan menjadi 2662 unit/bulan dengan metode rank position weight, dan 2464 unit/bulan

dengan metode region approach. Karena pada kasus ini yang lebih ditekankan adalah output

produksinya maka perencanaan line balancing dengan metode rank positional weight dapat

digunakan dalam pemecahan masalah pada koperasi INTAKO Tanggulangin Sidoarjo.

Kata Kunci : Line Balancing, Efisiensi Lintasan, Balance Delay, Output Produksi, RPW, RA.

Page 8: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi

ABSTRACT

ABDUL ARIJAL TAUFIQ, 2008, NIM.02540018, PLANNING OF LINE of BALANCING

WITH METHOD of RANK POSITION WEIGHT (RPW) AND METHOD of REGION

APPROACH (RA) UTILIZE TO IMPROVE OUTPUT PRODUCE IN CO-OPERATION of

INTAKO TANGGULANGIN SIDOARJO, Industrial Skripsi Majors Technique [of] Faculty

Of Technique University of Muhammadiyah Unlucky. Counsellor Of I : Ir. H. M. LUKMAN,

MT. Counsellor Of II : ANNISA KESSY, G. ST. MT.

Problems of line of balancing in stream of productions sometimes still disregarded by

company, though practically the problem of line of balancing represent one other playing a

part important in accomplishment of goals produce which have been planned. Co-operation

of INTAKO at factory division which located in sidoarjo tanggulangin represent co-operation

yielding is multifarious of woman bag type manner. Problems faced by co-operation of

INTAKO is frequently the existence of addition of office hours this matter overtime is

resulted cannot fulfill request of caused by market to lower him is amount of production

effect of less as well-balanced as production trajectory.

In the effort finishing the problem used by method of rank weight position and of

region approach representing method of heuristic with approach of error and trial for

comparing is condition of early with condition of after planning of line method of balancing

at co-operation of INTAKO. covering delay balance, trajectory efficiency, and production

output.

Pursuant to result of analysis in the reality from both method got by result of

calculation of delay balance early 23% decreasing to become 21% with method of rank

weight position. And 17% with method of region approach. While trajectory efficiency from

condition of early equal to 77% mounting to become 79% with method of rank wight

position, and 83% with method of region approach. Output produce woman bag mount from

condition of early 1848 unit / month become 2662 unit / month with method of rank weight

position, and 2464 unit / month with method of region approach. Because [at] this case which

more emphasized its production output hence planning of line of balancing with method of

rank weight positional can be used in trouble-shooting at co-operation of INTAKO

Tanggulangin Sidoarjo.

Keyword : Line of Balancing, Efficiency Trajectory, Balance Delay, Output Production,

RPW, RA.

Page 9: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi

KATA PENGANTAR

Syukur Alhamdulillah penulis ucapkan kehadirat Allah SWT yang maha dari segala

maha sehingga laporan tugas akhir dengan judul “PERENCANAAN LINE BALANCING

DENGAN METODE RANK POSITION WEIGHT (RPW) DAN METODE REGION

APPROACH (RA) GUNA MENINGKATKAN OUTPUT PRODUKSI” ini dapat

terselesaikan lewat pada waktu yang telah penulis rencanakan.

Teriring do’a sholawat serta salam semoga senantiasa melimpah kehariban nabi besar

MUHAMMAD SAW rosul akhir zaman, penutup para nabi yang membawa kesempurnaan

ajaran tauhid dan keutamaan budi pekerti. Dan semoga ditumpahkan do’a sholawat menetes

segenap keluarga sahabat dan seluruh ummatnya yang dengan tulus mencintai dan

menjunjung sunnahnya.

Skripsi ini merupakan salah satu persyaratan untuk menyelesaikan pendidikan di

Fakultas Teknik Jurusan Industri Universitas Muhammadiyah Malang. Skripsi ini dapat

terselesaikan karena banyak pihak yang telah membantu baik doa, maupun dengan tenaga.

Oleh karena itu pada kesempatan ini penulis ingin mengucapkan banyak terima kasih kepada

:

1 Keluargaku (emmak, bapak, alek anis, dan alek vera). Terutama emmakku ”bapak

kedua” yang tidak akan pernah kering akan do’a – do’anya yang tulus yang slalu

mendukung lahir maupun batin. Dan keluarga besar H.SATIMAN.

2. Ibu Dyah Retno P, MT, selaku Ketua Jurusan Teknik Industri.

3. Ir.M.Lukman, MT selaku dosen pembimbing I, yang telah meluangkan waktunya

untuk memberikan bimbingan hingga terselesaikannya Skripsi ini.

Page 10: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi

4. Annisa Kesy, G. ST. MT selaku dosen pembimbing II terima kasih atas kesabaran,

arahan dan bimbingannya hingga terselesaikannya Skripsi ini.

5. TU jurusan, terima kasih atas bantuannya.

6. Seluruh staf dan karyawan Koperasi INTAKO Tanggulangin Sidoarjo, yang telah

membantu selama penelitian.

7. Yang kusayangi dan aku hargai ”hanunah”.

8. Seluruh teman jurusan industri yang sudah maupun yang tertunda.

Penulis hanya bisa memberi ungkapan terima kasih dan doa tulus yang dapat

dipersembahkan, semoga segala yang mereka berikan kepada saya tercatat diperjalanan hidup

saya dan tercatat dalam catatan sang Roqib sebagai sebuah ibadah yang tiada ternilai, amiiiin.

Ya Allah terima kasih atas segalanya, terutama nikmat hidup yang engkau berikan,

dan ampuni hambamu ini yang sering melupakanmu dalam keseharianku. Hamba mohon

padamu untuk engkau, bawa hambamu kemanapun engkau ridhoi agar hambamu kelak bisa

menemukan kedamaian hidup dan hati yang sebenarnya dalam pelukan cinta sesungguhnya

dariMu.

Akhirnya penulis berharap semoga Skripsi ini dapat bermanfaat. Terima kasih.

Billahittaufiq wal hidayah

Malang, 29 November 2008

Penulis

Page 11: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi

DAFTAR ISI

Halaman Judul HALAMAN

Berita Acara Ujian Tugas Akhir

Lembar Pengesahan

Lembar Asistensi

Abstaraksi

Kata Pengantar

Daftar Isi

Daftar Tabel

Lampiran

BAB I : PENDAHULUAN

1.1. Latar Belakang............................................................................................................1

1.2. Rumusan Masalah.......................................................................................................2

1.3. Tujuan Penelitian........................................................................................................2

1.4. Manfaat Penelitian......................................................................................................3

1.5. Batasan Masalah.........................................................................................................3

1.6. Asumsi-Asumsi...........................................................................................................4

1.7. Sistematika Penulisan.................................................................................................4

BAB II : LANTASAN TEORI

2.1. Line Balancing.............................................................................................................6

2.1.1 Faktor Faktor Yang Mempengarihi Line Balancing...............................................7

2.1.2 Tipe Tipe Line Balancing.......................................................................................8

2.1.3 Tujuan Line Balancing……………………………………………….………...…9

2.1.4 Metode Dalam Penyeimbangan Lintasan Perakitan………………….…………..9

2.1.5 Metode Rank Position Weight…..……………………………………………....10

2.1.6 Metode Region Approach.....................................................................................11

2.2. Peta Proses Operasi....................................................................................................12

2.3 Precedence Diagram..................................................................................................14

2.4. Menentukan Waktu Siklus.........................................................................................27

2.5 Menentukan Jumlah Stasiun Kerja………………….……………………………….16

2.6 Menghitung Balance Delay…………………..………………………………………17

2.7 Menghitung Efisiensi Lintasan…………….……………………………………...…18

Page 12: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi

2.8 Menentukan Output Produksi………………………..………………………………18

2.9 Pengukuran Waktu Kerja Dengan Jam Henti………………………………………..19

2.9.1 Uji Kecukupan Dan Keseragaman Data…………………………………...…….22

2.9.2 Performance Rating……………………..……………………………………….23

2.9.3 Menentukan Allowance Time……………………….…………………………...32

2.9.4 Waktu Normal………………………...………………………………………….37

2.9.5 Waktu Baku…………………..………………………………………………….38

BAB III : METODOLOGI PENELITIAN

3.1 Diagram Alir Penelitian............................................................................................39

3.2 Diskripsi Diagram Alir Penelitian............................................................................40

3.2.1. Survey Perusahaan...............................................................................................40

3.2.2. Identifikasi Masalah.............................................................................................40

3.2.3. Study Literatur.....................................................................................................41

3.2.4. Pengumpulan Data…………………………………………………………...…41

3.2.5. Tes Keseragaman Data…………………………………………………………42

3.2.6 Tes Kecukupan Data............................................................................................43

3.2.7. Menghitung Waktu Normal.................................................................................44

3.2.8. Menghitung Waktu Baku.....................................................................................44

3.2.9. Pembuatan Precedence Diagram..........................................................................45

3.2.10. Perencanaan Keseimbangan Lintasan.................................................................45

3.2.11. Analisa Hasil.......................................................................................................49

3.2.12 Kesimpulan Dan Saran.......................................................................................49

BAB IV : PENGUMPULAN DAN PENGOLAHAN DATA

4.1. Sejarah Umum Perusahaan.........................................................................................50

4.2. Produk Koperasi Intako..............................................................................................51

4.3. Outlet Intako...............................................................................................................52

4.4. Layout Produksi..........................................................................................................53

4.5. Pengumpulan Data......................................................................................................53

4.5.1. Cara Mendapatkan Data........................................................................................53

4.5.2. Bahan Baku Yang Digunakan...............................................................................54

4.5.3. Mesin Dan Alat Yang Digunakan.........................................................................54

4.5.4. Proses Pembuatan Tas Perempuan........................................................................56

4.5.5. Peta Proses Operasi...............................................................................................59

4.5.6. Waktu Operasi Tiap Proses...................................................................................62

Page 13: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi

4.5.7. Jam Kerja Efektif..................................................................................................65

4.6. Pengolahan Data.........................................................................................................65

4.6.1. Uji Keseragaman Data………………………………………………….……….65

4.6.2. Uji Kecukupan Data …………………………….………………………………70

4.6.3. Menghitung Waktu Baku Tiap Proses…………………………………………..73

4.6.4. Pengelompokan Elemen Kerja Kedalam Stasiun Kerja Awal……………..........85

4.6.5. Perhitungan Tenaga Kerja Dan Output Sebelum Perencanaan……………...…..87

4.7. Perencanaan Keseimbangan Lintasan Dengan Metode RPW……………………...92

4.7.1. Precedence Diagram.............................................................................................93

4.7.2. Penentuan Bobot Posisi Masing-masing Operasi.................................................95

4.7.3. Penyusunan Ranking Bobot Posisi.......................................................................96

4.7.4. Penentuan Rank Waktu Siklus..............................................................................98

4.7.5.Pengelompokan Operasi Kedalam Stasiun Kerja..................................................99

4.7.5.1. Perencanaan I Dengan Waktu Siklus 226.42 detik.........................................99

4.7.5.2. Perencanaan II Dengan Waktu Siklus 244.81 detik......................................103

4.7.5.3. Perencanaan III Dengan Waktu Siklus 263.21 detik....................................106

4.7.5.4. Perencanaan IV Dengan Waktu Siklus 281.60 detik....................................109

4.8. Perencanaan Keseimbangan Lintasan Dengan Metode RA.....................................112

4.8.1. Precedence Diagram ..........................................................................................112

4.8.2 Pembagian Operasi Kedalam Beberapa Region.................................................112

4.8.3 Pengelompokan Operasi Kedalam Stasiun Kerja...............................................114

4.8.3.1. Perencanaan I Dengan Waktu Siklus 226.42 detik.......................................114

4.8.3.2. Perencanaan II Dengan Waktu Siklus 244.81 detik......................................118

4.8.3.3. Perencanaan III Dengan Waktu Siklus 263.21 detik....................................121

4.8.3.4. Perencanaan IV Dengan Waktu Siklus 281.60 detik....................................124

4.9. Analisa Perencanaan Line Balancing Dengan Metode RPW Dan RA....................127

4.10. Perhitungan Biaya Tenaga Kerja Sesudah Perencanaan.........................................128

4.10.1. Perhitungan Biaya Tenaga Kerja Dengan Metode RPW..................................128

4.10.2. Perhitungan Biaya Tenaga Kerja Dengan Metode RA.....................................131

4.12. Pemilihan Perencanaan Line Balancing Terbaik Berdasarkan Output Maksimal

Dengan Metode RPW dan RA.............................................................................133

BAB V : ANALISA PEMBAHASAN

5.1. Perbandingan Output Produksi Dan Biaya Tenaga Kerja, Sebelum Dan Sesudah

Perencanaan............................................................................................................139

Page 14: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi

5.1.1. Sebelum Perencanaan.........................................................................................139

5.1.2. Sesudah Perencanaan Keseimbangan Lintasan Dengan Menggunakan Metode RPW

dan RA........................................................................................................141

5.2. Perbandingan Perubahan Elemen Kerja Antara Stasiun Kerja Awal Dengan Stasiun

Kerja Usulan............................................................................................................143

BAB VI : KESIMPULAN

6.1. Kesimpulan..............................................................................................................149

6.2. Saran........................................................................................................................151

Page 15: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi

DAFTAR TABEL

Tabel 2.1 Westing House Performance Rating................................................................24

Tabel 2.2 Beasarnya Kelonggaran Faktortenaga yang dikeluarkan……………........ 33

Tabel 2.3 Besarnya Kelonggaran Berdasarkan Faktor Sikap Kerja................................33

Tabel 2.4 Besarnya Kelonggaran Berdasarkan Faktor Gerakan Kerja............................34

Tabel 2.5 Besarnya Kelonggaran Berdasarkan Faktor Kelelahan Mata..........................34

Tabel 2.6 Besarnya Kelonggaran Berdasarkan Faktor Keadaan Tempratur ….....……..35

Tabel 2.7 Besarnya Kelonggaran Berdasarkan Faktor Kadaan Atmosfer …………..…36

Tabel 2.8 Besarnya Kelonggaran Berdasarkan Faktor Kadaan Lingkungan...................36

Tabel 3.1 Tes Keseragaman Data....................................................................................42

Tabel 3.2 Tes Kecukupan Data........................................................................................43

Tabel 3.3 Perhitungan Waktu Normal.............................................................................44

Tabel 3.4 Perhitungan Waktu Baku.................................................................................44

Tabel 3.5 Pengelompokan Elemen Kerja Kedalam Stasiun Kerja..................................47

Tabel 4.1 Proses Pembuatan Tas Perempuan..................................................................56

Tabel 4.2 Data Waktu Pengamatan Pembuatan Tas Perempuan.....................................63

Tabel 4.3 Data Pengamatan Untuk Proses Operasi 1 (0-01)...........................................66

Tabel 4.4 Uji Keseragaman Data.....................................................................................68

Tabel 4.5 Uji Kecukupan Data........................................................................................72

Tabel 4.6 Waktu Siklus Tiap Operasi .............................................................................74

Tabel 4.7 Westinghause Performance Rating..................................................................75

Tabel 4.8 Performance Rating Operasi 1(0-01)………………………………………...76

Tabel 4.9 Penentuan Performace Rating..........................................................................77

Tabel 4.10 Waktu Normal Tiap Proses..............................................................................79

Tabel 4.11 Allowance Time Tiap Operasi.........................................................................81

Tabel 4.12 Waktu Normal Tiap Proses..............................................................................83

Tabel 4.13 Stasiun Kerja Awal………………………………………………………….85

Tabel 4.14 Data Permintaan………..……………... …………………………….....…..88

Tabel 4.15 Keterangan Stasiun Kerja Kondisi Awal..............……………………...…...91

Tabel 4.16 Penentuan Bobot Posisi Pada Tiap Opersi.....................................................95

Tabel 4.17 Penyusunan Ranking Bobot Opersi ...............................................................97

Tabel 4.18 Pengelompokan Stasiun Kerja Dengan Waktu Siklus 226.42 detik...............99

Tabel 4.19 Pengelompokan Stasiun Kerja Dengan Waktu Siklus 244.81 detik.............103

Page 16: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi

Tabel 4.20 Pengelompokan Stasiun Kerja Dengan Waktu Siklus 263.21 detik.............106

Tabel 4.21 Pengelompokan Stasiun Kerja Dengan Waktu Siklus 281.60 detik.............109

Tabel 4.22 Pembagian Operasi Kedalam Beberapa Region...........................................113

Tabel 4.23 Pengelompokan Stasiun Kerja Dengan Waktu Siklus 226.42 detik.............115

Tabel 4.24 Pengelompokan Stasiun Kerja Dengan Waktu Siklus 244.81 detik ............118

Tabel 4.25 Pengelompokan Stasiun Kerja Dengan Waktu Siklus 263.21 detik.............121

Tabel 4.26 Pengelompokan Stasiun Kerja Dengan Waktu Siklus 281.60 detik.............124

Tabel 4.27 Hasil Perencanaan Line Balancing Dengan Metode RPW dan RA..............127

Tabel 4.28 Perbandingan Hasil Line Balancing Dengan Metode RPW dan RA............134

Tabel 4.29 Keterangan Pengelompokan Elemen Kerja Waktu Siklus 207.46 Detik......136

Tabel 5.1 Data Historis Permintaan Tas Perempuan Perbulan......................................119

Tabel 5.2 Perbandingan Metode RPW dan RA.............................................................141

Tabel 5.3 Perbandingan Kriteria Sebelum Dan Sesudah Perencanaan .........................143

Tabel 5.4 Perbandingan Elemen Kerja Sebelum Dan Sesudah Perencanaan ...............144

Tabel 6.1 Perbandingan Sebelum dan Sesudah Perencanaan .....................................149

Tabel 6.2 Pengelompokan Elemen Kerja Dengan Metode RPW Dan RA Dengan Waktu

Siklus 207.46 Detik..........................................................................................................150

Page 17: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi

DAFTAR GAMBAR

Gambar 2.1 Sketsa Pembuatan Peta Proses Operasi ........................................................14

Gambar 2.2 Precedence Diagram ....................................................................................15

Gambar 2.3 Langkah Langkah Sistematis Dalam Kegiatan Pengukuran Kerja Dengan Jam

Henti...........................................................................................................................21

Gambar 2.4 Precedence Diagram.....................................................................................34

Gambar 3.1 Diagram Alir Penelitian................................................................................39

Gambar 3.2 Precedence Diagram.....................................................................................45

Gambar 4.1 Layout Lantai Produksi.................................................................................53

Gambar 4.2 Peta Proses Operasi.......................................................................................61

Gambar 4.3 Pengelompokan Stasiun Kerja Kondisi Awal...............................................90

Gambar 4.4 Precedence Diagram Pembuatan Tas Perempuan.........................................94

Gambar 4.5 Pengelompokan Stasiun Kerja Menggunakan metode RPW Dengan Waktu

Siklus 207.46 detik.....................................................................................135

Gambar 5.1 Pembagian Stasiun Kerja Sebelum Perencanaan........................................147

Gambar 5.2 Pembagian Stasiun Kerja Setelah Perencanaan..........................................148

Page 18: Perencanaan Line Balancing Dengan Metode Rank Position Weight Rpw Dan Metode Region Approach Ra Guna Meningkatkan Output Produksi

DAFTAR PUSTAKA

Baroto, Teguh, 2002, Pengantar Teknik Industri, Cetakan Pertama, UMM Press, Malang.

Sutalaksana, Iftikar Z. dkk, 1979, Teknik Tata Cara Kerja, Departemen Teknik Industri,

ITB, Bandung.

Purnomo, Hari Pengantar Teknik Industri, Graha Ilmu, Yogyakarta.

Wignjosoebroto, Sritomo, 2003, Ergonomi Studi Gerak dan Waktu, Edisi Pertama,

Cetakan Ketiga, PT. Guna Widya, Jakarta.

Wignjosoebroto, Sritomo, 1992, Teknik Tata Cara dan pengukuran Kerja, Edisi Kedua,

PT. Guna Widya, Jakarta.