A. REMUNERATION
A.I PROFESSIONAL STAFF
1 Dessi Irdina Provincial Team Leader 36 17,000,000 612,000,000 36 17,000,000 612,000,000 8.00 136,000,000 1.00 1.00 2.00 17,000,000 17,000,000 34,000,000 10.00 170,000,000 26.00 442,000,000
TASIKMALAYA DISTRICT :
2 Endi Sudiah, ST Water Supply Eng. (WSE) and Communal Sanit. Contr. (WSE)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 7.55 79,227,273 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 9.55 100,227,273 26.45 277,772,727
3 Creni Herliani Distric Health & Hygiene Spec. (HHS)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 7.55 79,227,273 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 9.55 100,227,273 26.45 277,772,727
SUMEDANG DISTRICT :
4 Hadi Siswanto, ST Water Supply Eng. (WSE) and Communal Sanit. Contr. (WSE)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 7.55 79,227,273 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 9.55 100,227,273 26.45 277,772,727
5 Juwita Sri Hidayati Distric Health & Hygiene Spec. (HHS)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 7.55 79,227,273 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 9.55 100,227,273 26.45 277,772,727
GARUT DISTRICT :
6 Esfrizal Water Supply Eng. (WSE) and Communal Sanit. Contr. (WSE)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 7.55 79,227,273 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 9.55 100,227,273 26.45 277,772,727
7 Eka Wahyu P. Distric Health & Hygiene Spec. (HHS)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 7.55 79,227,273 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 9.55 100,227,273 26.45 277,772,727
SUBANG DISTRICT :
8 Ratna Suminar,ST Water Supply Eng. (WSE) and Communal Sanit. Contr. (WSE)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 7.55 79,227,273 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 9.55 100,227,273 26.45 277,772,727
9 Dedi Kurniadi,Am.Kl / Nurul Aini
Distric Health & Hygiene Spec. (HHS)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 7.55 79,227,273 1.00 0.68 1.68 10,500,000 7,159,091 17,659,091 9.23 96,886,364 26.77 281,113,636
KUNINGAN DISTRICT :
10 Ahmad/M.Joko M Water Supply Eng. (WSE) and Communal Sanit. Contr. (WSE)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 7.55 79,227,273 0.30 1.00 1.30 3,195,652 10,500,000 13,695,652 8.85 92,922,925 27.15 285,077,075
11 Tatang Hidayat,SKM Distric Health & Hygiene Spec. (HHS)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 7.55 79,227,273 1.00 0.50 1.50 10,500,000 5,250,000 15,750,000 9.05 94,977,273 26.95 283,022,727
SERANG DISTRICT :
12 Ridansyah, ST. Water Supply Eng. (WSE) and Communal Sanit. 36 10,500,000 378,000,000 36 10,500,000 378,000,000 5.05 52,977,273 3.50 1.00 4.50 36,750,000 10,500,000 47,250,000 9.55 100,227,273 26.45 277,772,727
13 Nani Rahayu Distric Health & Hygiene Spec. (HHS)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 5.05 52,977,273 3.50 1.00 4.50 36,750,000 10,500,000 47,250,000 9.55 100,227,273 26.45 277,772,727
LEBAK DISTRICT :
14 Bambang S, ST. Water Supply Eng. (WSE) and Communal Sanit. 36 10,500,000 378,000,000 36 10,500,000 378,000,000 5.05 52,977,273 3.50 1.00 4.50 36,750,000 10,500,000 47,250,000 9.55 100,227,273 26.45 277,772,727
15 Sersani Wahyudi Distric Health & Hygiene Spec. (HHS)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 4.55 47,727,273 3.50 1.00 4.50 36,750,000 10,500,000 47,250,000 9.05 94,977,273 26.95 283,022,727
16 Nurhadi/Putra Adhari Coordinator Trainers 18 7,500,000 135,000,000 - - 8.57 1.00 9.57 64,239,130 7,500,000 71,739,130 9.57 71,739,130 8.43 63,260,870
17 Adang Baron Trainer 1 18 6,500,000 117,000,000 - - 9.00 1.00 10.00 58,500,000 6,500,000 65,000,000 10.00 65,000,000 8.00 52,000,000
18 Dayat Rachman Trainer 2 18 6,500,000 117,000,000 - - 9.00 1.00 10.00 58,500,000 6,500,000 65,000,000 10.00 65,000,000 8.00 52,000,000
19 Muhadjir Trainer 3 18 6,500,000 117,000,000 - - 6.00 1.00 7.00 39,000,000 6,500,000 45,500,000 7.00 45,500,000 11.00 71,500,000
20 Helena Listyarsih D Financial Management Specialist
12 10,500,000 126,000,000 - - 3.00 1.00 4.00 31,500,000 10,500,000 42,000,000 4.00 42,000,000 8.00 84,000,000
21 Hari Hermawan Asisten Management Data
12 7,500,000 90,000,000 - - 3.00 1.00 4.00 22,500,000 7,500,000 30,000,000 4.00 30,000,000 8.00 60,000,000
Sub total (A.I) JAWA BARAT + BANTEN 5,904,000,000 6,606,000,000 1,134,931,818 535,934,783 200,409,091 736,343,874 1,871,275,692 4,734,724,308
15-07-09
15-07-09
PROVINCIAL TRAINERS
1-07-09
BALANCEAMENDMENT 1
15-07-09
15-07-09
15-07-09
15-07-09
15-07-09
15-07-09
15-07-09
15-07-09
Mob. Mon Month Sub Total
01-07-09
BIMONTHLY INVOICEORIGINAL CONTRACT
1-07-09
1-07-09
1-07-09
ASMANDAT & FINANCIAL MS
15-07-09
15-07-09
15-07-09
15-07-09
2-01-10
2-01-10
- NOMOR : 05 BULAN : MARET & APRIL 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. NAMA POSISI Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. Mar-10 Apr-10 Total Mar-10 Apr-10 Total Rp. Rp.
A.II SUPPORTING STAFF
I. PROVINCIAL TEAM
1 Irriza Rosyid Database Manag/Comp. op
36 3,000,000 108,000,000 36 3,000,000 108,000,000 8.00 24,000,000 1.00 1.00 2.00 3,000,000 3,000,000 6,000,000 10.00 30,000,000 26.00 78,000,000
2 Panca Agusti Adm./Comp. Operator 36 2,000,000 72,000,000 36 2,000,000 72,000,000 8.00 16,000,000 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 10.00 20,000,000 26.00 52,000,000
3 Draftman 36 2,500,000 90,000,000 0 2,500,000 - - - - - - - - - - - - -
4 Agus Kartono Driver 36 1,000,000 36,000,000 36 1,000,000 36,000,000 8.00 8,000,000 1.00 1.00 2.00 1,000,000 1,000,000 2,000,000 10.00 10,000,000 26.00 26,000,000
II. DISTRICT
A. TASIKMALAYA
1 Totong Ahmad D. Adm/CompOperation 36 2,000,000 72,000,000 36 2,000,000 72,000,000 7.55 15,090,909 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 9.55 19,090,909 26.45 52,909,091
2 Deden Hermansyah Draftman 36 2,500,000 90,000,000 36 2,500,000 90,000,000 7.55 18,863,636 1.00 1.00 2.00 2,500,000 2,500,000 5,000,000 9.55 23,863,636 26.45 66,136,364
3 Risman Drivers 36 1,000,000 36,000,000 36 1,000,000 36,000,000 7.55 7,545,455 1.00 1.00 2.00 1,000,000 1,000,000 2,000,000 9.55 9,545,455 26.45 26,454,545
B. SUMEDANG
1 Sally Aditiawan Adm/CompOperation 36 2,000,000 72,000,000 36 2,000,000 72,000,000 7.00 14,000,000 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 9.00 18,000,000 27.00 54,000,000
2 Ari Andrian Draftman 36 2,500,000 90,000,000 36 2,500,000 90,000,000 4.91 12,272,727 1.00 1.00 2.00 2,500,000 2,500,000 5,000,000 6.91 17,272,727 29.09 72,727,273
3 Andrian Drivers 36 1,000,000 36,000,000 36 1,000,000 36,000,000 1.00 1,000,000 1.00 1.00 2.00 1,000,000 1,000,000 2,000,000 3.00 3,000,000 33.00 33,000,000
C. GARUT
1 Deni Ramahani Adm/CompOperation 36 2,000,000 72,000,000 36 2,000,000 72,000,000 6.75 13,500,000 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 8.75 17,500,000 27.25 54,500,000
2 Mohamad Riswan Draftman 36 2,500,000 90,000,000 36 2,500,000 90,000,000 6.75 16,875,000 1.00 1.00 2.00 2,500,000 2,500,000 5,000,000 8.75 21,875,000 27.25 68,125,000
3 Tatang Ahmad R Drivers 36 1,000,000 36,000,000 36 1,000,000 36,000,000 6.50 6,500,000 1.00 1.00 2.00 1,000,000 1,000,000 2,000,000 8.50 8,500,000 27.50 27,500,000
D. SUBANG
1 Hari Haryanto B Adm/CompOperation 36 2,000,000 72,000,000 36 2,000,000 72,000,000 7.00 14,000,000 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 9.00 18,000,000 27.00 54,000,000
2 Bagea Nugraha Draftman 36 2,500,000 90,000,000 36 2,500,000 90,000,000 7.00 17,500,000 1.00 1.00 2.00 2,500,000 2,500,000 5,000,000 9.00 22,500,000 27.00 67,500,000
3 Ono S Muchtar Drivers 36 1,000,000 36,000,000 36 1,000,000 36,000,000 1.48 1,476,190 1.00 1.00 2.00 1,000,000 1,000,000 2,000,000 3.48 3,476,190 32.52 32,523,810
E. KUNINGAN
1 Yussy Juliawati Adm/CompOperation 36 2,000,000 72,000,000 36 2,000,000 72,000,000 7.00 14,000,000 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 9.00 18,000,000 27.00 54,000,000
2 Lia Meilawati Draftman 36 2,500,000 90,000,000 36 2,500,000 90,000,000 7.00 17,500,000 1.00 1.00 2.00 2,500,000 2,500,000 5,000,000 9.00 22,500,000 27.00 67,500,000
3 Ucung Mulyadi Drivers 36 1,000,000 36,000,000 36 1,000,000 36,000,000 3.00 3,000,000 1.00 1.00 2.00 1,000,000 1,000,000 2,000,000 5.00 5,000,000 31.00 31,000,000
F. SERANG
1 Ucu Saiful/M.Yusro Adm/CompOperation 36 2,000,000 72,000,000 36 2,000,000 72,000,000 5.05 10,090,909 3.50 1.00 4.50 7,000,000 2,000,000 9,000,000 9.55 19,090,909 26.45 52,909,091
2 Supriyadi/Uus Draftman 36 2,500,000 90,000,000 36 2,500,000 90,000,000 5.05 12,613,636 3.50 1.00 4.50 8,750,000 2,500,000 11,250,000 9.55 23,863,636 26.45 66,136,364
3 Bhakti/Saman Drivers 36 1,000,000 36,000,000 36 1,000,000 36,000,000 4.67 4,671,591 3.50 1.00 4.50 3,500,000 1,000,000 4,500,000 9.17 9,171,591 26.83 26,828,409
G. LEBAK
1 Rochmatul Aliyah Adm/CompOperation 0 2,000,000 - 18 2,000,000 36,000,000 - - 7.24 1.00 8.24 14,476,190 2,000,000 16,476,190 8.24 16,476,190 9.76 19,523,810
2 Hafiz Rahman Draftman 0 2,500,000 - 36 2,500,000 90,000,000 - - 7.00 1.00 8.00 17,500,000 2,500,000 20,000,000 8.00 20,000,000 28.00 70,000,000
3 Opang Sopadi Drivers 0 1,000,000 - 18 1,000,000 18,000,000 - - 5.00 1.00 6.00 5,000,000 1,000,000 6,000,000 6.00 6,000,000 12.00 12,000,000
Sub total (A.II) JAWA BARAT + BANTEN 1,494,000,000 1,548,000,000 248,500,054 89,726,190 44,500,000 134,226,190 382,726,244 1,165,273,756
Total A (Remuneration) JAWA BARAT + BANTEN 7,398,000,000 8,154,000,000 1,383,431,872 625,660,973 244,909,091 870,570,064 2,254,001,936 5,899,998,064
15-07-09
15-07-09
15-07-09
15-07-09
01-08-09
01-08-09
01-08-09
01-08-09
25-08-09
01-09-09
01-11-09
01-07-09
Mob. Mon Month
05-10-09
10-08-09
10-08-09
18-08-09
15-07-09
15-07-09
15-07-09
01-08-09
BALANCEAMENDMENT 1
Sub Total
ORIGINAL CONTRACTBIMONTHLY INVOICE
01-07-09
01-07-09
01-07-09
-
NOMOR : 05 BULAN : MARET & APRIL 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. Mar-10 Apr-10 Total Mar-10 Apr-10 Total Rp. Rp.
B REIMBURSABLE EXPENSES
B.I MOBILIZATION / DEMOBILIZATION
I. PROVINCIAL TEAM
1 Provincial Team Leader 1 300,000 300,000 1 300,000 300,000 0.50 150,000 - - - - - 0.50 150,000 0.50 150,000
2 Financial Management Specilist RT 1 300,000 300,000 0.50 0.50 150,000 150,000 0.50 150,000 0.50 150,000
3 Asistant management Data RT 1 300,000 300,000 0.50 0.50 150,000 150,000 0.50 150,000 0.50 150,000
II. DISTRICT
A. TASIKMALAYA
1 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
2 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
B. SUMEDANG
1 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
2 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
C. GARUT
1 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
2 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
D. SUBANG
1 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
2 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
E. KUNINGAN
1 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
2 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
F. SERANG
1 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
2 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
G. LEBAK -
1 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
2 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
Sub total (B.I) JAWA BARAT + BANTEN 7,300,000 7,900,000 3,650,000 300,000 - 300,000 3,950,000 3,950,000
Distric Health & Hygiene Specialist (HHS) RT
Distric Health & Hygiene Specialist (HHS) RT
Water Supply Eng. (WSE) and CommunalSanitation Contruction (WSE)
RT
Water Supply Eng. (WSE) and CommunalSanitation Contruction (WSE)
RT
Distric Health & Hygiene Specialist (HHS) RT
Water Supply Eng. (WSE) and CommunalSanitation Contruction (WSE)
RT
Distric Health & Hygiene Specialist (HHS) RT
Water Supply Eng. (WSE) and CommunalSanitation Contruction (WSE)
RT
Distric Health & Hygiene Specialist (HHS) RT
Water Supply Eng. (WSE) and CommunalSanitation Contruction (WSE)
RT
Distric Health & Hygiene Specialist (HHS) RT
Water Supply Eng. (WSE) and CommunalSanitation Contruction (WSE)
RT
RT
Water Supply Eng. (WSE) and CommunalSanitation Contruction (WSE)
RT
Distric Health & Hygiene Specialist (HHS) RT
BIMONTHLY INVOICEBALANCE
DESCRIPTION Mon Month Sub Total
AMENDMENT 1ORIGINAL CONTRACT
NOMOR : 05 BULAN : MARET & APRIL 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. Mar-10 Apr-10 Total Mar-10 Apr-10 Total Rp. Rp.
B.II HOUSING ALLOWANCE
I. PROVINCIAL TEAM
1 Provincial Team Leader 36 1,000,000 36,000,000 36 1,000,000 36,000,000 8.00 8,000,000 1.00 1.00 2.00 1,000,000 1,000,000 2,000,000 10.00 10,000,000 26.00 26,000,000
2 Financial Management Specialist 12 1,000,000 12,000,000 3.00 1.00 4.00 3,000,000 1,000,000 4,000,000 4.00 4,000,000 8.00 8,000,000
3 Asistant Management Data 12 1,000,000 12,000,000 3.00 1.00 4.00 3,000,000 1,000,000 4,000,000 4.00 4,000,000 8.00 8,000,000
II. DISTRICT
A. TASIKMALAYA
1 36 800,000 28,800,000 36 800,000 28,800,000 7.55 6,036,364 1.00 1.00 2.00 800,000 800,000 1,600,000 9.55 7,636,364 26.45 21,163,636
2 36 800,000 28,800,000 36 800,000 28,800,000 7.55 6,036,364 1.00 1.00 2.00 800,000 800,000 1,600,000 9.55 7,636,364 26.45 21,163,636
B. SUMEDANG
1 36 800,000 28,800,000 36 800,000 28,800,000 7.55 6,036,364 1.00 1.00 2.00 800,000 800,000 1,600,000 9.55 7,636,364 26.45 21,163,636
2 36 800,000 28,800,000 36 800,000 28,800,000 7.55 6,036,364 1.00 1.00 2.00 800,000 800,000 1,600,000 9.55 7,636,364 26.45 21,163,636
C. GARUT
1 36 800,000 28,800,000 36 800,000 28,800,000 7.55 6,036,364 1.00 1.00 2.00 800,000 800,000 1,600,000 9.55 7,636,364 26.45 21,163,636
2 36 800,000 28,800,000 36 800,000 28,800,000 7.55 6,036,364 1.00 1.00 2.00 800,000 800,000 1,600,000 9.55 7,636,364 26.45 21,163,636
D. SUBANG
1 36 800,000 28,800,000 36 800,000 28,800,000 7.55 6,036,364 1.00 1.00 2.00 800,000 800,000 1,600,000 9.55 7,636,364 26.45 21,163,636
2 36 800,000 28,800,000 36 800,000 28,800,000 7.55 6,036,364 1.00 0.68 1.68 800,000 545,455 1,345,455 9.23 7,381,818 26.77 21,418,182
E. KUNINGAN
1 36 800,000 28,800,000 36 800,000 28,800,000 7.55 6,036,364 - 1.00 1.00 - 800,000 800,000 8.55 6,836,364 27.45 21,963,636
2 36 800,000 28,800,000 36 800,000 28,800,000 7.55 6,036,364 1.00 0.50 1.50 800,000 400,000 1,200,000 9.05 7,236,364 26.95 21,563,636
E. SERANG
1 36 800,000 28,800,000 36 800,000 28,800,000 5.05 4,036,364 3.50 1.00 4.50 2,800,000 800,000 3,600,000 9.55 7,636,364 26.45 21,163,636
2 36 800,000 28,800,000 36 800,000 28,800,000 5.05 4,036,364 3.50 1.00 4.50 2,800,000 800,000 3,600,000 9.55 7,636,364 26.45 21,163,636
E. LEBAK -
1 36 800,000 28,800,000 36 800,000 28,800,000 5.05 4,036,364 3.50 1.00 4.50 2,800,000 800,000 3,600,000 9.55 7,636,364 26.45 21,163,636
2 36 800,000 28,800,000 36 800,000 28,800,000 5.05 4,036,364 3.50 1.00 4.50 2,800,000 800,000 3,600,000 9.55 7,636,364 26.45 21,163,636
Sub total (B.II) JAWA BARAT + BANTEN 439,200,000 463,200,000 84,509,091 25,400,000 13,545,455 38,945,455 123,454,545 339,745,455
Distric Health & Hygiene Specialist (HHS) Months
Water Supply Eng. (WSE) and CommunalSanitation Contruction (WSE)
Months
Water Supply Eng. (WSE) and CommunalSanitation Contruction (WSE)
Months
Distric Health & Hygiene Specialist (HHS) Months
Water Supply Eng. (WSE) and CommunalSanitation Contruction (WSE)
Months
Distric Health & Hygiene Specialist (HHS) Months
Distric Health & Hygiene Specialist (HHS) Months
Water Supply Eng. (WSE) and CommunalSanitation Contruction (WSE)
Months
Distric Health & Hygiene Specialist (HHS) Months
Water Supply Eng. (WSE) and CommunalSanitation Contruction (WSE)
Months
Distric Health & Hygiene Specialist (HHS) Months
Distric Health & Hygiene Specialist (HHS) Months
Water Supply Eng. (WSE) and CommunalSanitation Contruction (WSE)
Months
Months
Water Supply Eng. (WSE) and CommunalSanitation Contruction (WSE)
Months
Months
Months
BIMONTHLY INVOICEBALANCE
DESCRIPTION Mon Month Sub Total
ORIGINAL CONTRACT AMENDMENT 1
- NOMOR : 05 BULAN : MARET & APRIL 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. Mar-10 Apr-10 Total Mar-10 Apr-10 Total Rp. Rp.
B.III DUTY TRAVEL
I. PROVINCIAL TEAM
1 Team Leader
a. Transportation Province to Jakarta (2 Trip/Year) 6 300,000 1,800,000 6 300,000 1,800,000 6.00 1,800,000 - - - - - - 6.00 1,800,000 - -
b. Transportation Prov. to District (2 Trip/Year/DIs 42 400,000 16,800,000 42 400,000 16,800,000 24.00 9,600,000 1.00 3.00 4.00 400,000 1,200,000 1,600,000 28.00 11,200,000 14.00 5,600,000
2 Provincial Trainer
a. Transp.District to Jakarta (54 Trip/Year x 4 Person) 16 300,000 4,800,000 - - 8.00 - 8.00 2,400,000 - 2,400,000 8.00 2,400,000 8.00 2,400,000
b. Transp.District to Province (8 Trip/Year x 4 person) 48 400,000 19,200,000 - - 40.00 8.00 48.00 16,000,000 3,200,000 19,200,000 48.00 19,200,000 - -
3 FMS and Asmandat
a. Transp.District to Jakarta (4 Trip/Year x 2 Person) 8 300,000 2,400,000 - - 3.00 3.00 6.00 900,000 900,000 1,800,000 6.00 1,800,000 2.00 600,000
b. Transp.District to Province (4 Trip/Year x 7 Dist/Year x 2 person) 56 400,000 22,400,000 - - 4.00 2.00 6.00 1,600,000 800,000 2,400,000 6.00 2,400,000 50.00 20,000,000
II. DISTRICT - - - - -
A. TASIKMALAYA
1
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 3.00 1,200,000 - 1.00 1.00 - 400,000 400,000 4.00 1,600,000 8.00 3,200,000
2
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 3.00 1,200,000 - 1.00 1.00 - 400,000 400,000 4.00 1,600,000 8.00 3,200,000
B. SUMEDANG -
1
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 3.00 1,200,000 - 1.00 1.00 - 400,000 400,000 4.00 1,600,000 8.00 3,200,000
2
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 2.00 800,000 - 1.00 1.00 - 400,000 400,000 3.00 1,200,000 9.00 3,600,000
C. GARUT
1
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 2.00 600,000 - - - - - - 2.00 600,000 1.00 300,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 5.00 2,000,000 - 1.00 1.00 - 400,000 400,000 6.00 2,400,000 6.00 2,400,000
2
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 5.00 2,000,000 - 1.00 1.00 - 400,000 400,000 6.00 2,400,000 6.00 2,400,000
D. SUBANG
1
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 5.00 2,000,000 - 1.00 1.00 - 400,000 400,000 6.00 2,400,000 6.00 2,400,000
2
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 4.00 1,600,000 - 1.00 1.00 - 400,000 400,000 5.00 2,000,000 7.00 2,800,000
E. KUNINGAN
1
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 4.00 1,600,000 - 1.00 1.00 - 400,000 400,000 5.00 2,000,000 7.00 2,800,000
2
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 4.00 1,600,000 - 1.00 1.00 - 400,000 400,000 5.00 2,000,000 7.00 2,800,000
Distric Health & Hygiene Specialist (HHS)
RT
RT
Water Sup. Eng.(WSE) & Communal Sanit.Cont.(WSE)
RT
RT
Distric Health & Hygiene Specialist (HHS)
RT
RT
RT
Distric Health & Hygiene Specialist (HHS)
RT
RT
Water Sup. Eng.(WSE) & Communal Sanit.Cont.(WSE)
RT
RT
Distric Health & Hygiene Specialist (HHS)
RT
RT
RT
RT
Distric Health & Hygiene Specialist (HHS)
RT
RT
Water Sup. Eng.(WSE) & Communal Sanit.Cont.(WSE)
RT
Water Sup. Eng.(WSE) & Communal Sanit.Cont.(WSE)
RT
RT
RT
RT
Water Sup. Eng.(WSE) & Communal Sanit.Cont.(WSE)
ORIGINAL CONTRACTBIMONTHLY INVOICE
BALANCE
DESCRIPTION Mon Month Sub Total
AMENDMENT 1
F. SERANG
1
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 1.00 400,000 - 1.00 1.00 - 400,000 400,000 2.00 800,000 10.00 4,000,000
2 - -
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 1.00 400,000 - 1.00 1.00 - 400,000 400,000 2.00 800,000 10.00 4,000,000
G. LEBAK
1
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 - - - 2.00 2.00 - 800,000 800,000 2.00 800,000 10.00 4,000,000
2 -
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 - - - 2.00 2.00 - 800,000 800,000 2.00 800,000 10.00 4,000,000
Sub total (B.III) JAWA BARAT + BANTEN 98,400,000 147,200,000 28,000,000 21,300,000 12,500,000 33,800,000 61,800,000 85,400,000
RT
RT
RT
Distric Health & Hygiene Specialist (HHS)
RT
Distric Health & Hygiene Specialist (HHS)
RT
RT
Water Sup. Eng.(WSE) & Communal Sanit.Cont.(WSE)
RT
RT
Water Sup. Eng.(WSE) & Communal Sanit. Cont.(WSE)
- NOMOR : 05BULAN : MARET & APRIL 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume TotalCost Rp. Cost Rp. Rp. Mar-10 Apr-10 Total Mar-10 Apr-10 Total Rp. Rp.
B.IV OUT OF STATION ALLOWANCE (OSA)
I. PROVINCIAL TEAM
1 Team Leader
a. OSA to Jakarta (2 Trip/Year @ 2 days) 28 850,000 23,800,000 28 850,000 23,800,000 11.00 9,350,000 - - - - - - 11.00 9,350,000 17.00 14,450,000
b. OSA to District (2Trip/Year/Dis. @ 2days) 84 500,000 42,000,000 84 500,000 42,000,000 40.00 20,000,000 5.00 5.00 10.00 2,500,000 2,500,000 5,000,000 50.00 25,000,000 34.00 17,000,000
2 Provincial Trainer
a. OSA to Jakarta (5 Trip/Year @ 2 days x 4 ) 32 850,000 27,200,000 - - 24.00 - 24.00 20,400,000 - 20,400,000 24.00 20,400,000 8.00 6,800,000
b. OSA to District (8Trip/Year/Dis. @ 2 x 4) 96 500,000 48,000,000 - - 96.00 - 96.00 48,000,000 - 48,000,000 96.00 48,000,000 - -
c. OSA Dis. to Vil. (6Trip/Year/Dis. @ 3 x 4) 180 50,000 9,000,000 - - - - - - - - - - 180.00 9,000,000
3 FMS and Asmandat
a. OSA to Jakarta (4 Trip/Year @ 2 days x 2) 16 850,000 13,600,000 - - 8.00 8.00 16.00 6,800,000 6,800,000 13,600,000 16.00 13,600,000 - -
b. OSA Dis.to Dist. (4Trip x 7Dis. @ 2 d x2 p) 112 500,000 56,000,000 - - 13.00 1.00 14.00 6,500,000 500,000 7,000,000 14.00 7,000,000 98.00 49,000,000
II. DISTRICT
A. TASIKMALAYA
1
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 9.00 4,500,000 - 4.00 4.00 - 2,000,000 2,000,000 13.00 6,500,000 23.00 11,500,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 97.00 4,850,000 14.00 14.00 28.00 700,000 700,000 1,400,000 125.00 6,250,000 379.00 18,950,000
2
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 9.00 4,500,000 - 4.00 4.00 - 2,000,000 2,000,000 13.00 6,500,000 23.00 11,500,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 94.00 4,700,000 14.00 14.00 28.00 700,000 700,000 1,400,000 122.00 6,100,000 382.00 19,100,000
B. SUMEDANG
1
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 9.00 4,500,000 - 4.00 4.00 - 2,000,000 2,000,000 13.00 6,500,000 23.00 11,500,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 98.00 4,900,000 14.00 14.00 28.00 700,000 700,000 1,400,000 126.00 6,300,000 378.00 18,900,000
2
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 9.00 4,500,000 - 4.00 4.00 - 2,000,000 2,000,000 13.00 6,500,000 23.00 11,500,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 98.00 4,900,000 14.00 14.00 28.00 700,000 700,000 1,400,000 126.00 6,300,000 378.00 18,900,000
C. GARUT
1
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 6.00 5,100,000 - - - - - - 6.00 5,100,000 - -
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 15.00 7,500,000 - 4.00 4.00 - 2,000,000 2,000,000 19.00 9,500,000 17.00 8,500,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 97.00 4,850,000 14.00 14.00 28.00 700,000 700,000 1,400,000 125.00 6,250,000 379.00 18,950,000
2
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 15.00 7,500,000 - 4.00 4.00 - 2,000,000 2,000,000 19.00 9,500,000 17.00 8,500,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 98.00 4,900,000 14.00 14.00 28.00 700,000 700,000 1,400,000 126.00 6,300,000 378.00 18,900,000
D. SUBANG
1
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 13.00 6,500,000 - 4.00 4.00 - 2,000,000 2,000,000 17.00 8,500,000 19.00 9,500,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 85.00 4,250,000 - 14.00 14.00 - 700,000 700,000 99.00 4,950,000 405.00 20,250,000
2
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 12.00 6,000,000 - 4.00 4.00 - 2,000,000 2,000,000 16.00 8,000,000 20.00 10,000,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 99.00 4,950,000 14.00 14.00 28.00 700,000 700,000 1,400,000 127.00 6,350,000 377.00 18,850,000
E. KUNINGAN
1
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 12.00 6,000,000 - 4.00 4.00 - 2,000,000 2,000,000 16.00 8,000,000 20.00 10,000,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 108.00 5,400,000 - 14.00 14.00 - 700,000 700,000 122.00 6,100,000 382.00 19,100,000
2
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 12.00 6,000,000 - 4.00 4.00 - 2,000,000 2,000,000 16.00 8,000,000 20.00 10,000,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 110.00 5,500,000 - - - - - - 110.00 5,500,000 394.00 19,700,000
F. SERANG
Water Sup. Eng.(WSE) & Communal Sanit.Cont.(WSE)
Man.Days
Water Sup. Eng.(WSE) & Communal Sanit. Cont.
Man.Days
Man.Days
Distric Health & Hygiene Specialist (HHS)
Distric Health & Hygiene Specialist (HHS)
Man.Days
Man.Days
Water Sup. Eng.(WSE) & Communal Sanit.Cont.(WSE)
Distric Health & Hygiene Specialist (HHS)
Man.Days
Man.Days
Man.Days
Distric Health & Hygiene Specialist (HHS)
Water Sup. Eng.(WSE) & Communal Sanit.Cont.(WSE)
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Water Sup. Eng.(WSE) & Communal Sanit.Cont.(WSE)
Man.Days
Man.Days
Man.Days
Man.Days
Distric Health & Hygiene Specialist (HHS)
BALANCEAMENDMENT 1
DESCRIPTION Mon Month Sub Total
BIMONTHLY INVOICEORIGINAL CONTRACT
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
1
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 1.00 500,000 - 5.00 5.00 - 2,500,000 2,500,000 6.00 3,000,000 30.00 15,000,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 27.00 1,350,000 12.00 10.00 22.00 600,000 500,000 1,100,000 49.00 2,450,000 455.00 22,750,000
2 -
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 1.00 500,000 - 5.00 5.00 - 2,500,000 2,500,000 6.00 3,000,000 30.00 15,000,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 27.00 1,350,000 12.00 10.00 22.00 600,000 500,000 1,100,000 49.00 2,450,000 455.00 22,750,000
G. LEBAK
1
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 - - - 6.00 6.00 - 3,000,000 3,000,000 6.00 3,000,000 30.00 15,000,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 19.00 950,000 15.00 - 15.00 750,000 - 750,000 34.00 1,700,000 470.00 23,500,000
2 -
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 - - - 6.00 6.00 - 3,000,000 3,000,000 6.00 3,000,000 30.00 15,000,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 19.00 950,000 15.00 - 15.00 750,000 - 750,000 34.00 1,700,000 470.00 23,500,000
Sub total (B.IV) JAWA BARAT + BANTEN 742,000,000 895,800,000 146,750,000 91,800,000 48,100,000 139,900,000 286,650,000 609,150,000
-
Distric Health & Hygiene Specialist (HHS)
Man.Days
Man.Days
Man.Days
Water Sup. Eng.(WSE) & CommunalSanit Cont (WSE)
Man.Days
Man.Days
Man.Days
Distric Health & Hygiene Specialist (HHS)
Man.Days
Man.Days
Man.Days
Water Sup. Eng.(WSE) & CommunalSanit.Cont.(WSE)
Man.Days
Man.Days
Man.Days
NOMOR : 05 BULAN : MARET & APRIL 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. Mar-10 Apr-10 Total Mar-10 Apr-10 Total Rp. Rp.
B.V CAR RENTAL
I. PROVINCIAL TEAM
Car Rental and O & M (1 unit x 36 Months) 36 7,500,000 270,000,000 36 7,500,000 270,000,000 8.00 60,000,000 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 10.00 75,000,000 26.00 195,000,000
II. DISTRICT
A. TASIKMALAYA
Car Rental and O & M (5 unit x 36 Months) 36 7,500,000 270,000,000 36 7,500,000 270,000,000 7.55 56,590,909 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 9.55 71,590,909 26.45 198,409,091
B. SUMEDANG -
Car Rental and O & M (5 unit x 36 Months) 36 7,500,000 270,000,000 36 7,500,000 270,000,000 7.55 56,590,909 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 9.55 71,590,909 26.45 198,409,091
C. GARUT -
Car Rental and O & M (5 unit x 36 Months) 36 7,500,000 270,000,000 36 7,500,000 270,000,000 7.55 56,590,909 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 9.55 71,590,909 26.45 198,409,091
D. SUBANG
Car Rental and O & M (5 unit x 36 Months) 36 7,500,000 270,000,000 36 7,500,000 270,000,000 7.55 56,590,909 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 9.55 71,590,909 26.45 198,409,091
E. KUNINGAN
Car Rental and O & M (5 unit x 36 Months) 36 7,500,000 270,000,000 36 7,500,000 270,000,000 7.55 56,590,909 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 9.55 71,590,909 26.45 198,409,091
F. SERANG
Car Rental and O & M (5 unit x 36 Months) 36 7,500,000 270,000,000 36 7,500,000 270,000,000 5.05 37,840,909 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 7.05 52,840,909 28.95 217,159,091
G. LEBAK
Car Rental and O & M (5 unit x 36 Months) 36 7,500,000 270,000,000 36 7,500,000 270,000,000 5.05 37,840,909 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 7.05 52,840,909 28.95 217,159,091
Sub total (B.V) JAWA BARAT + BANTEN 2,160,000,000 2,160,000,000 418,636,364 60,000,000 60,000,000 120,000,000 538,636,364 1,621,363,636
-
AMENDMENT 1ORIGINAL CONTRACT
DESCRIPTION
BIMONTHLY INVOICEBALANCE
Mon Month Sub Total
Car-Months
Car-Months
Car-Months
Car-Months
Car-Months
Car-Months
Car-Months
Car-Months
NOMOR : 05 BULAN : MARET & APRIL 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. Mar-10 Apr-10 Total Mar-10 Apr-10 Total Rp. Rp.
B.VI OFFICE EQUIPMENTS
I. PROVINCIAL TEAM
Provincial Office
a. Computer (Rental) 2 unit / Months 72 750,000 54,000,000 72 750,000 54,000,000 16.00 12,000,000 2.00 2.00 4.00 1,500,000 1,500,000 3,000,000 20.00 15,000,000 52.00 39,000,000
b. Computer (Rental) 1 unit/Month 12 750,000 9,000,000 - - 1.00 1.00 2.00 750,000 750,000 1,500,000 2.00 1,500,000 10.00 7,500,000
b. Printer (Rental) 1 Unit/Months 36 350,000 12,600,000 36 350,000 12,600,000 8.00 2,800,000 1.00 1.00 2.00 350,000 350,000 700,000 10.00 3,500,000 26.00 9,100,000
Provincial Trainers
a. Note Book (Rental) 3 unit / Months 54 750,000 40,500,000 27.00 3.00 30.00 20,250,000 2,250,000 22,500,000 30.00 22,500,000 24.00 18,000,000
b. Printer (Rental) 1 Unit/Months 18 350,000 6,300,000 9.00 1.00 10.00 3,150,000 350,000 3,500,000 10.00 3,500,000 8.00 2,800,000
c. Digital Camera (Rental) 1 Unit/Month 18 200,000 3,600,000 9.00 1.00 10.00 1,800,000 200,000 2,000,000 10.00 2,000,000 8.00 1,600,000
II. DISTRICT
A. TASIKMALAYA
a. Computer (Rental) 2 unit / District / Months 72 750,000 54,000,000 72 750,000 54,000,000 15.09 11,318,182 2.00 2.00 4.00 1,500,000 1,500,000 3,000,000 19.09 14,318,182 52.91 39,681,818
b. Printer (Rental) 1 Unit/Months 36 350,000 12,600,000 36 350,000 12,600,000 7.55 2,640,909 1.00 1.00 2.00 350,000 350,000 700,000 9.55 3,340,909 26.45 9,259,091
c. Digital Camera (Rental) 1 Unit/Month/Distric 36 200,000 7,200,000 36 200,000 7,200,000 7.55 1,509,091 1.00 1.00 2.00 200,000 200,000 400,000 9.55 1,909,091 26.45 5,290,909
B. SUMEDANG
a. Computer (Rental) 2 unit / District / Months 72 750,000 54,000,000 72 750,000 54,000,000 15.09 11,318,182 2.00 2.00 4.00 1,500,000 1,500,000 3,000,000 19.09 14,318,182 52.91 39,681,818
b. Printer (Rental) 1 Unit/Months 36 350,000 12,600,000 36 350,000 12,600,000 7.55 2,640,909 1.00 1.00 2.00 350,000 350,000 700,000 9.55 3,340,909 26.45 9,259,091
c. Digital Camera (Rental) 1 Unit/Month/Distric 36 200,000 7,200,000 36 200,000 7,200,000 7.55 1,509,091 1.00 1.00 2.00 200,000 200,000 400,000 9.55 1,909,091 26.45 5,290,909
C. GARUT
a. Computer (Rental) 2 unit / District / Months 72 750,000 54,000,000 72 750,000 54,000,000 15.09 11,318,182 2.00 2.00 4.00 1,500,000 1,500,000 3,000,000 19.09 14,318,182 52.91 39,681,818
b. Printer (Rental) 1 Unit/Months 36 350,000 12,600,000 36 350,000 12,600,000 7.55 2,640,909 1.00 1.00 2.00 350,000 350,000 700,000 9.55 3,340,909 26.45 9,259,091
c. Digital Camera (Rental) 1 Unit/Month/Distric 36 200,000 7,200,000 36 200,000 7,200,000 7.55 1,509,091 1.00 1.00 2.00 200,000 200,000 400,000 9.55 1,909,091 26.45 5,290,909
D. SUBANG
a. Computer (Rental) 2 unit / District / Months 72 750,000 54,000,000 72 750,000 54,000,000 15.09 11,318,182 2.00 2.00 4.00 1,500,000 1,500,000 3,000,000 19.09 14,318,182 52.91 39,681,818
b. Printer (Rental) 1 Unit/Months 36 350,000 12,600,000 36 350,000 12,600,000 7.55 2,640,909 1.00 1.00 2.00 350,000 350,000 700,000 9.55 3,340,909 26.45 9,259,091
c. Digital Camera (Rental) 1 Unit/Month/Distric 36 200,000 7,200,000 36 200,000 7,200,000 7.55 1,509,091 1.00 1.00 2.00 200,000 200,000 400,000 9.55 1,909,091 26.45 5,290,909
E. KUNINGAN
a. Computer (Rental) 2 unit / District / Months 72 750,000 54,000,000 72 750,000 54,000,000 15.09 11,318,182 2.00 2.00 4.00 1,500,000 1,500,000 3,000,000 19.09 14,318,182 52.91 39,681,818
b. Printer (Rental) 1 Unit/Months 36 350,000 12,600,000 36 350,000 12,600,000 7.55 2,640,909 1.00 1.00 2.00 350,000 350,000 700,000 9.55 3,340,909 26.45 9,259,091
c. Digital Camera (Rental) 1 Unit/Month/Distric 36 200,000 7,200,000 36 200,000 7,200,000 7.55 1,509,091 1.00 1.00 2.00 200,000 200,000 400,000 9.55 1,909,091 26.45 5,290,909
D. SERANG - -
a. Computer (Rental) 2 unit / District / Months 72 750,000 54,000,000 72 750,000 54,000,000 5.05 3,784,091 12.04 2.00 14.04 9,030,000 1,500,000 10,530,000 19.09 14,314,091 52.91 39,685,909
b. Printer (Rental) 1 Unit/Months 36 350,000 12,600,000 36 350,000 12,600,000 5.05 1,765,909 3.50 1.00 4.50 1,225,000 350,000 1,575,000 9.55 3,340,909 26.45 9,259,091
c. Digital Camera (Rental) 1 Unit/Month/Distric 36 200,000 7,200,000 36 200,000 7,200,000 5.05 1,009,091 3.50 1.00 4.50 700,000 200,000 900,000 9.55 1,909,091 26.45 5,290,909
E. LEBAK
a. Computer (Rental) 2 unit / District / Months 72 750,000 54,000,000 72 750,000 54,000,000 5.05 3,784,091 12.04 2.00 14.04 9,030,000 1,500,000 10,530,000 19.09 14,314,091 52.91 39,685,909
b. Printer (Rental) 1 Unit/Months 36 350,000 12,600,000 36 350,000 12,600,000 5.05 1,765,909 3.50 1.00 4.50 1,225,000 350,000 1,575,000 9.55 3,340,909 26.45 9,259,091
c. Digital Camera (Rental) 1 Unit/Month/Distric 36 200,000 7,200,000 36 200,000 7,200,000 5.05 1,009,091 3.50 1.00 4.50 700,000 200,000 900,000 9.55 1,909,091 26.45 5,290,909
Sub total (B.VI) JAWA BARAT + BANTEN 583,200,000 642,600,000 105,259,091 59,960,000 19,750,000 79,710,000 184,969,091 457,630,909
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
BALANCE
DESCRIPTION Mon Month Sub Total
Unit-Months
Unit-Months
Unit-Months
AMENDMENT 1ORIGINAL CONTRACTBIMONTHLY INVOICE
-
NOMOR : 05 BULAN : MARET & APRIL 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. Mar-10 Apr-10 Total Mar-10 Apr-10 Total Rp. Rp.
B.VII OFFICE COST
I. PROVINCIAL TEAM
a. Office Supply 36 1,000,000 36,000,000 36 1,000,000 36,000,000 8.00 4,883,025 1.00 1.00 2.00 521,400 462,500 983,900 10.00 5,866,925 26.00 30,133,075
b. Comnputer/Printer Supply 36 750,000 27,000,000 36 750,000 27,000,000 8.00 3,661,000 1.00 1.00 2.00 590,000 560,000 1,150,000 10.00 4,811,000 26.00 22,189,000
II. DISTRICT
A. TASIKMALAYA
a. Office Supply 36.0 750,000 27,000,000 36.0 750,000 27,000,000 8.00 2,080,057 1.00 1.00 2.00 380,500 398,000 778,500 10.00 2,858,557 26.00 24,141,443
b. Comnputer/Printer Supply / Reproduction 36.0 500,000 18,000,000 36.0 500,000 18,000,000 7.00 2,907,900 1.00 1.00 2.00 277,500 400,500 678,000 9.00 3,585,900 27.00 14,414,100
c. Survey Equipments 12.0 1,200,000 14,400,000 12.0 1,200,000 14,400,000 - - - - - - - - 12.00 14,400,000
B. SUMEDANG
a. Office Supply 36.0 750,000 27,000,000 36.0 750,000 27,000,000 6.00 2,525,550 1.00 1.00 2.00 195,500 279,000 474,500 8.00 3,000,050 28.00 23,999,950
b. Comnputer/Printer Supply / Reproduction 36.0 500,000 18,000,000 36.0 500,000 18,000,000 5.00 2,324,400 1.00 1.00 2.00 277,400 282,000 559,400 7.00 2,883,800 29.00 15,116,200
c. Survey Equipments 12.0 1,200,000 14,400,000 12.0 1,200,000 14,400,000 - - - - - - - - 12.00 14,400,000
C. GARUT
a. Office Supply 36.0 750,000 27,000,000 36.0 750,000 27,000,000 6.00 2,147,450 1.00 1.00 2.00 207,200 220,600 427,800 8.00 2,575,250 28.00 24,424,750
b. Comnputer/Printer Supply / Reproduction 36.0 500,000 18,000,000 36.0 500,000 18,000,000 6.00 2,875,000 1.00 1.00 2.00 225,000 210,000 435,000 8.00 3,310,000 28.00 14,690,000
c. Survey Equipments 12.0 1,200,000 14,400,000 12.0 1,200,000 14,400,000 1.00 - - - - - 1.00 - 11.00 14,400,000
D. SUBANG -
a. Office Supply 36.0 750,000 27,000,000 36.0 750,000 27,000,000 6.00 1,482,800 1.00 1.00 2.00 173,000 202,600 375,600 8.00 1,858,400 28.00 25,141,600
b. Comnputer/Printer Supply / Reproduction 36.0 500,000 18,000,000 36.0 500,000 18,000,000 5.00 2,702,300 1.00 1.00 2.00 258,000 284,700 542,700 7.00 3,245,000 29.00 14,755,000
c. Survey Equipments 12.0 1,200,000 14,400,000 12.0 1,200,000 14,400,000 - - - - - - - 12.00 14,400,000
E. KUNINGAN -
a. Office Supply 36.0 750,000 27,000,000 36.0 750,000 27,000,000 6.00 2,603,100 1.00 1.00 2.00 290,000 327,100 617,100 8.00 3,220,200 28.00 23,779,800
b. Comnputer/Printer Supply / Reproduction 36.0 500,000 18,000,000 36.0 500,000 18,000,000 5.00 2,527,200 1.00 1.00 2.00 419,000 266,000 685,000 7.00 3,212,200 29.00 14,787,800
c. Survey Equipments 12.0 1,200,000 14,400,000 12.0 1,200,000 14,400,000 - - - - - - - 12.00 14,400,000
F. SERANG
a. Office Supply 36.0 750,000 27,000,000 36.0 750,000 27,000,000 3.00 559,800 3.50 1.00 4.50 786,300 166,500 952,800 7.50 1,512,600 28.50 25,487,400
b. Comnputer/Printer Supply / Reproduction 36.0 500,000 18,000,000 36.0 500,000 18,000,000 3.00 990,000 3.50 1.00 4.50 2,311,200 425,000 2,736,200 7.50 3,726,200 28.50 14,273,800
c. Survey Equipments 12.0 1,200,000 14,400,000 12.0 1,200,000 14,400,000 - - - - - - - - - - 12.00 14,400,000
G. LEBAK
a. Office Supply 36.0 750,000 27,000,000 36.0 750,000 27,000,000 3.00 753,400 3.50 1.00 4.50 1,417,900 166,500 1,584,400 7.50 2,337,800 28.50 24,662,200
b. Comnputer/Printer Supply / Reproduction 36.0 500,000 18,000,000 36.0 500,000 18,000,000 3.00 714,000 3.50 1.00 4.50 1,777,600 225,000 2,002,600 7.50 2,716,600 28.50 15,283,400
c. Survey Equipments 12.0 1,200,000 14,400,000 12.0 1,200,000 14,400,000 - - - - - - - - - - 12.00 14,400,000
Sub total (B.VII) JAWA BARAT + BANTEN 478,800,000 478,800,000 35,736,982 10,107,500 4,876,000 14,983,500 50,720,482 428,079,518
-
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
DESCRIPTION Mon Month Sub Total
Months
AMENDMENT 1ORIGINAL CONTRACTBIMONTHLY INVOICE
BALANCE
NOMOR : 05 BULAN : MARET & APRIL 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. Mar-10 Apr-10 Total Mar-10 Apr-10 Total Rp. Rp.
B.VIIITELECOMMUNICATION
I. PROVINCIAL TEAM
Telecommunication 36 1,000,000 36,000,000 36 1,000,000 36,000,000 7.00 3,733,392 1.00 1.00 2.00 656,472 568,103 1,224,575 9.00 4,957,967 27.00 31,042,033
II. DISTRICT
A. TASIKMALAYA
36 500,000 18,000,000 36 500,000 18,000,000 7.00 3,211,585 1.00 1.00 2.00 602,236 744,293 1,346,529 9.00 4,558,114 27.00 13,441,886
B. SUMEDANG
36 500,000 18,000,000 36 500,000 18,000,000 7.00 2,301,873 1.00 1.00 2.00 379,246 470,317 849,563 9.00 3,151,436 27.00 14,848,564
C. GARUT
36 500,000 18,000,000 36 500,000 18,000,000 7.00 1,678,351 1.00 1.00 2.00 322,456 336,704 659,160 9.00 2,337,511 27.00 15,662,489
D. SUBANG
36 500,000 18,000,000 36 500,000 18,000,000 7.00 2,174,787 1.00 1.00 2.00 352,751 279,543 632,294 9.00 2,807,081 27.00 15,192,919
E. KUNINGAN
36 500,000 18,000,000 36 500,000 18,000,000 7.00 1,592,139 1.00 1.00 2.00 301,672 176,700 478,372 9.00 2,070,511 27.00 15,929,489
F. SERANG
36 500,000 18,000,000 36 500,000 18,000,000 2.00 826,300 3.50 1.00 4.50 2,289,454 456,780 2,746,234 6.50 3,572,534 29.50 14,427,466
E. LEBAK
36 500,000 18,000,000 36 500,000 18,000,000 3.00 832,450 3.50 1.00 4.50 2,393,728 500,000 2,893,728 7.50 3,726,178 28.50 14,273,822
Sub total (B.VIII) JABAR + BANTEN 162,000,000 162,000,000 16,350,877 7,298,015 3,532,440 10,830,455 27,181,332 134,818,668
-
Telecommunication Months
Telecommunication Months
Telecommunication Months
Telecommunication Months
Telecommunication Months
Telecommunication Months
Months
Telecommunication Months
BIMONTHLY INVOICEBALANCE
DESCRIPTION Mon Month Sub Total
AMENDMENT 1ORIGINAL CONTRACT
NOMOR : 05 BULAN : MARET & APRIL 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. Mar-10 Apr-10 Total Mar-10 Apr-10 Total Rp. Rp.
B.IX REPORTS
1 Inceptions Report (15 copies)/district 75.0 50,000 3,750,000 75.0 50,000 3,750,000 - - - - - - - 75.00 3,750,000
2 Monthly Report (15 copies/Month)/district 3 FY 2,700.0 25,000 67,500,000 2,700.0 25,000 67,500,000 302.00 10,930,060 75.00 75.00 150.00 1,875,000 1,875,000 3,750,000 452.00 14,680,060 2,248.00 52,819,940
3 Quarterly Report (15 copies/ 3 Month)/district 900.0 75,000 67,500,000 900.0 75,000 67,500,000 - - - - - - - - - 900.00 67,500,000
4 Annual Report (15 copies/Year)/district 225.0 100,000 22,500,000 225.0 100,000 22,500,000 - - - - - - - - - 225.00 22,500,000
5 Special Report (15 copies/Years)/district 75.0 20,000 1,500,000 75.0 20,000 1,500,000 - - - - - - - - - 75.00 1,500,000
6 Draft Final Report (15 copies)/district 75.0 100,000 7,500,000 75.0 100,000 7,500,000 - - - - - - - - - 75.00 7,500,000
7 Final Report (15 copies)/district 75.0 100,000 7,500,000 75.0 100,000 7,500,000 - - - - - - - - - 75.00 7,500,000
8 MIS Input (5 copies/ 6 Month)/district 150.0 50,000 7,500,000 150.0 50,000 7,500,000 - - - - - - - - - 150.00 7,500,000
Sub total (B.IX) JAWA BARAT 185,250,000 185,250,000 10,930,060 1,875,000 1,875,000 3,750,000 14,680,060 170,569,940
1 Inceptions Report (15 copies)/district 30.0 50,000 1,500,000 30.0 50,000 1,500,000 - - - - - - - - 30.00 1,500,000
2 Monthly Report (15 copies/Month)/district 3 FY 1,080.0 25,000 27,000,000 1,080.0 25,000 27,000,000 2.00 1,205,550 75.00 30.00 105.00 1,875,000 750,000 2,625,000 107.00 3,830,550 973.00 23,169,450
3 Quarterly Report (15 copies/ 3 Month)/district 360.0 75,000 27,000,000 360.0 75,000 27,000,000 - - - - - - - - - 360.00 27,000,000
4 Annual Report (15 copies/Year)/district 90.0 100,000 9,000,000 90.0 100,000 9,000,000 - - - - - - - - - 90.00 9,000,000
5 Special Report (15 copies/Years)/district 30.0 20,000 600,000 30.0 20,000 600,000 - - - - - - - - - 30.00 600,000
6 Draft Final Report (15 copies)/district 30.0 100,000 3,000,000 30.0 100,000 3,000,000 - - - - - - - - - 30.00 3,000,000
7 Final Report (15 copies)/district 30.0 100,000 3,000,000 30.0 100,000 3,000,000 - - - - - - - - - 30.00 3,000,000
8 MIS Input (5 copies/ 6 Month)/district 60.0 50,000 3,000,000 60.0 50,000 3,000,000 - - - - - - - - - 60.00 3,000,000
9 Training Report (15 copies/reports) 120.0 50,000 6,000,000 - - - - - - - - - 120.00 6,000,000
10 Province Report
- Inception Report 15.0 50,000 750,000 - - - - - - - - - 15.00 750,000
- Monthly Report 180.0 25,000 4,500,000 - - - 15.00 15.00 - 375,000 375,000 15.00 375,000 165.00 4,125,000
- Quarterly Report 60.0 75,000 4,500,000 - - - - - - - - - 60.00 4,500,000
- Annual Report 15.0 100,000 1,500,000 - - - - - - - - - 15.00 1,500,000
Sub total (B.IX) BANTEN 74,100,000 91,350,000 1,205,550 1,875,000 1,125,000 3,000,000 4,205,550 87,144,450
Sub total (B.IX) JAWA BARAT + BANTEN 259,350,000 276,600,000 12,135,610 3,750,000 3,000,000 6,750,000 18,885,610 257,714,390
-
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
ORIGINAL CONTRACT
Copies
Copies
Copies
Copies
Copies
Copies
Copies
BALANCEAMENDMENT 1
DESCRIPTION Mon Month Sub Total
BIMONTHLY INVOICE
NOMOR : 05 BULAN : MARET & APRIL 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. Mar-10 Apr-10 Total Mar-10 Apr-10 Total Rp. Rp.
B.X OFFICE RENTAL & FURNITURE AND O & M
I. PROVINCIAL TEAM
36 2,500,000 90,000,000 36 2,500,000 90,000,000 8.00 20,000,000 1.00 1.00 2.00 2,500,000 2,500,000 5,000,000 10.00 25,000,000 26.00 65,000,000
II. DISTRICT
A. TASIKMALAYA
36 2,000,000 72,000,000 36 2,000,000 72,000,000 7.55 15,090,909 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 9.55 19,090,909 26.45 52,909,091
B. SUMEDANG
36 2,000,000 72,000,000 36 2,000,000 72,000,000 7.55 15,090,909 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 9.55 19,090,909 26.45 52,909,091
C. GARUT
36 2,000,000 72,000,000 36 2,000,000 72,000,000 7.55 15,090,909 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 9.55 19,090,909 26.45 52,909,091
D. SUBANG
36 2,000,000 72,000,000 36 2,000,000 72,000,000 7.55 15,090,909 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 9.55 19,090,909 26.45 52,909,091
E. KUNINGAN
36 2,000,000 72,000,000 36 2,000,000 72,000,000 7.55 15,090,909 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 9.55 19,090,909 26.45 52,909,091
F. SERANG
36 2,000,000 72,000,000 36 2,000,000 72,000,000 5.05 10,090,909 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 7.05 14,090,909 28.95 57,909,091
G. LEBAK
36 2,000,000 72,000,000 36 2,000,000 72,000,000 5.05 10,090,909 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 7.05 14,090,909 28.95 57,909,091
Sub total (B.X) JAWA BARAT + BANTEN 594,000,000 594,000,000 115,636,364 16,500,000 16,500,000 33,000,000 148,636,364 445,363,636
-
NOMOR : 05 BULAN : MARET & APRIL 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. Mar-10 Apr-10 Total Mar-10 Apr-10 Total Rp. Rp.
B.XI TRAINING
a. MIS Training for District Operators
a.1. Training Material (Asmandat + 7 Operator) 8 50,000 400,000 - - - - - - - - 8.00 400,000
a.2. Consumption
Meals 4 x 8 persons 32 20,000 640,000 - - - - - - - - 32.00 640,000
Snack 3 x 8 persons 24 7,500 180,000 - - - - - - - - 24.00 180,000
b. Training for DMAC & District Facilitator Coordinator
b.1. Training Material (TL + FMS + 3 trainers + 14 DMAC + 7 DFC) 26 50,000 1,300,000 - - - - - - - - 26.00 1,300,000
b.2. Comsumption (2 days training)
Meals 4 x 26 persons 104 20,000 2,080,000 - - - - - - - - 104.00 2,080,000
Snack 3 x 26 persons 78 7,500 585,000 - - - - - - - - 78.00 585,000
5,185,000 - - - - 5,185,000
5,524,250,000 5,833,285,000 966,664,378 296,415,515 181,803,895 478,219,410 1,444,883,788 4,383,216,212
C. 142,144,798 48,600,000 - - - - - -
D. - 121,998
E. 103,363 -
13,064,394,798 14,036,006,998
103,363 - - - - - - -
Office Rental, Furniture and O & M Years
Total B (REIMBURSABLE EXPENSES) JAWA BARAT + BANTEN
MANAGEMENT FEE
CONTINGENCIES
PROVISIONAL SUM
TOTAL A + B + C + D + E
Office Rental, Furniture and O & M Years
Office Rental, Furniture and O & M Years
Office Rental, Furniture and O & M Years
Office Rental, Furniture and O & M
DESCRIPTION
ORIGINAL CONTRACT
Years
BIMONTHLY INVOICE
Office Rental, Furniture and O & M Years
Office Rental, Furniture and O & M Years
Office Rental, Furniture and O & M Years
BALANCE
Mon Month Sub Total
AMENDMENT 1
BALANCE
DESCRIPTION Mon Month Sub Total
BIMONTHLY INVOICEAMENDMENT 1ORIGINAL CONTRACT
PROVINCIAL MANAGEMENT ADVISORY CONSULTANT (PMAC) TO PROVINCIAL PROJECT MANAGEMENT UNIT (PPMU) JAWA BARAT DAN BANTEN (PAKET 9)
PENGEMBANGAN KINERJA PENGELOLAAN AIR MINUM JAWA BARAT
INVOICE NO. : 05 KONTRAK NO. : KU.08.08-PKPAM.JB/S-030BULAN : MARET 2010 - APRIL 2010 TANGGAL : 15 JUNI 2009
ORIGINAL AMENDMENT PREVIOUS THIS INVOICE UP TO THIS INVOICE BALANCENO. CONTRACT NO. 1
Rp. Rp. Rp. Rp. Rp. Rp.A. REMUNERATION
1 PROFESSIONAL STAFF 5,904,000,000 6,606,000,000 1,134,931,818 736,343,874 1,871,275,692 4,734,724,308
2 SUPPORTING STAFF 1,494,000,000 1,548,000,000 248,500,054 134,226,190 382,726,244 1,165,273,756
SUB TOTAL A. 7,398,000,000 8,154,000,000 1,383,431,872 870,570,064 2,254,001,936 5,899,998,064 B. REIMBURSABLE EXPENSES
1 MOBILIZATION / DEMOBILIZATION 7,300,000 7,900,000 3,650,000 300,000 3,950,000 3,950,000
2 HOUSING ALLOWANCE 439,200,000 463,200,000 84,509,091 38,945,455 123,454,545 339,745,455
3 DUTY TRAVEL 98,400,000 147,200,000 28,000,000 33,800,000 61,800,000 85,400,000
4 OUT OF STATION ALLOWANCE (OSA) 742,000,000 895,800,000 146,750,000 139,900,000 286,650,000 609,150,000
5 CAR RENTAL 2,160,000,000 2,160,000,000 418,636,364 120,000,000 538,636,364 1,621,363,636
6 OFFICE EQUIPMENTS 583,200,000 642,600,000 105,259,091 79,710,000 184,969,091 457,630,909
7 OFFICE COST 478,800,000 478,800,000 35,736,982 14,983,500 50,720,482 428,079,518
8 TELECOMMUNICATION 162,000,000 162,000,000 16,350,877 10,830,455 27,181,332 134,818,668
9 REPORTS 259,350,000 276,600,000 12,135,610 6,750,000 18,885,610 257,714,390
10 OFFICE RENTAL & FURNITURE AND O & M 594,000,000 594,000,000 115,636,364 33,000,000 148,636,364 445,363,636
11 TRAINING 5,185,000 - - - 5,185,000
SUB TOTAL B. 5,524,250,000 5,833,285,000 966,664,378 478,219,410 1,444,883,788 4,388,401,212 MANAGEMENT FEE 142,144,798 48,600,000 48,600,000 CONTINGENCIES 121,998 121,998 TOTAL 13,064,394,798 14,036,006,998 2,350,096,250 1,348,789,474 3,698,885,724 10,337,121,274
Pengembalian Uang Muka 996,069,000 996,069,000 830,057,500 166,011,500 996,069,000 - 12,068,325,798 13,039,937,998 1,520,038,750 1,182,777,974 2,702,816,724 10,337,121,274
PPN 10% 1,303,993,800 152,003,875 118,277,797 270,281,672 1,033,712,127 Total 14,343,931,798 1,672,042,625 1,301,055,771 2,973,098,396 11,370,833,402
Terbilang :
Pejabat Pembuat Komitment Pembangunan Jakarta, Mei 2010
Prasarana dan Sarana Air Minum Masyarakat PT. PERENTJANA DJAJA Berpenghasilan Rendah Satuan Kerja Pengembangan Kinerja Pengelolaan Air Minum Jawa Barat
Oscar R.H.Siagian,ST IR. BAMBANG H.WIKANTA,MM,MT
NIP. 197505312002121001 DIREKTUR UTAMA
Ketut Ayu Ragil, ST.MT NIP.19781122200642001
DESCRIPTION
REKAPITULASI
Ketua Team Teknis Konsultan
PEKERJAAN : PROVINCIAL MANAGEMENT ADVISORY CONSULTANT (PMAC) TO PROVINCIAL PROJECT MANAGEMENT UNIT (PPMU)PROVINSI : JAWA BARAT DAN BANTEN (PAKET 9)SATUAN KERJA : PENGEMBANGAN KINERJA PENGELOLAAN AIR MINUM JAWA BARAT NOMOR : 06
BULAN : MEI 2010 & JUNI 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. NAMA POSISI Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. May-10 Jun-10 Total May-10 Jun-10 Total Rp. Rp.
A. REMUNERATION
A.I PROFESSIONAL STAFF
1 Dessi Irdina Provincial Team Leader 36 17,000,000 612,000,000 36 17,000,000 612,000,000 10.00 170,000,000 1.00 1.00 2.00 17,000,000 17,000,000 34,000,000 12.00 204,000,000 24.00 408,000,000
TASIKMALAYA DISTRICT :
2 Endi Sudiah, ST Water Supply Eng. (WSE) and Communal Sanit. Contr. (WSE)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 9.55 100,227,273 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 11.55 121,227,273 24.45 256,772,727
3 Creni Herliani Distric Health & Hygiene Spec. (HHS)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 9.55 100,227,273 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 11.55 121,227,273 24.45 256,772,727
SUMEDANG DISTRICT :
4 Hadi Siswanto, ST Water Supply Eng. (WSE) and Communal Sanit. Contr. (WSE)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 9.55 100,227,273 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 11.55 121,227,273 24.45 256,772,727
5 Juwita Sri Hidayati Distric Health & Hygiene Spec. (HHS)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 9.55 100,227,273 1.00 - 1.00 10,500,000 - 10,500,000 10.55 110,727,273 25.45 267,272,727
GARUT DISTRICT :
6 Esfrizal Water Supply Eng. (WSE) and Communal Sanit. Contr. (WSE)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 9.55 100,227,273 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 11.55 121,227,273 24.45 256,772,727
7 Eka Wahyu P. Distric Health & Hygiene Spec. (HHS)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 9.55 100,227,273 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 11.55 121,227,273 24.45 256,772,727
SUBANG DISTRICT :
8 Ratna Suminar,ST Water Supply Eng. (WSE) and Communal Sanit. Contr. (WSE)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 9.55 100,227,273 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 11.55 121,227,273 24.45 256,772,727
9 Nurul Aini Distric Health & Hygiene Spec. (HHS)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 9.23 96,886,364 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 11.23 117,886,364 24.77 260,113,636
KUNINGAN DISTRICT :
10 Ahmad/M Joko Y Water Supply Eng. (WSE) and Communal Sanit. Contr. (WSE)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 8.85 92,922,925 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 10.85 113,922,925 25.15 264,077,075
11 Tatang Hidayat,SKM Distric Health & Hygiene Spec. (HHS)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 9.05 94,977,273 - - - - - - 9.05 94,977,273 26.95 283,022,727
SERANG DISTRICT :
12 Ridansyah, ST. Water Supply Eng. (WSE) and Communal Sanit. Contr. (WSE)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 9.55 100,227,273 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 11.55 121,227,273 24.45 256,772,727
13 Nani Rahayu Distric Health & Hygiene Spec. (HHS)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 9.55 100,227,273 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 11.55 121,227,273 24.45 256,772,727
LEBAK DISTRICT :
14 Bambang S, ST. Water Supply Eng. (WSE) and Communal Sanit. Contr. (WSE)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 9.55 100,227,273 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 11.55 121,227,273 24.45 256,772,727
15 Sersani Wahyudi Distric Health & Hygiene Spec. (HHS)
36 10,500,000 378,000,000 36 10,500,000 378,000,000 9.05 94,977,273 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 11.05 115,977,273 24.95 262,022,727
16 Putra Adhari Coordinator Trainers 18 7,500,000 135,000,000 9.57 71,739,130 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 11.57 86,739,130 6.43 48,260,870
17 Adang Baron Trainer 1 18 6,500,000 117,000,000 10.00 65,000,000 1.00 1.00 2.00 6,500,000 6,500,000 13,000,000 12.00 78,000,000 6.00 39,000,000
18 Dayat Rachman Trainer 2 18 6,500,000 117,000,000 10.00 65,000,000 1.00 1.00 2.00 6,500,000 6,500,000 13,000,000 12.00 78,000,000 6.00 39,000,000
19 Muhadjir Trainer 3 18 6,500,000 117,000,000 7.00 45,500,000 1.00 1.00 2.00 6,500,000 6,500,000 13,000,000 9.00 58,500,000 9.00 58,500,000
20 Helena Listyarsih D Financial Management Specialist
12 10,500,000 126,000,000 4.00 42,000,000 1.00 1.00 2.00 10,500,000 10,500,000 21,000,000 6.00 63,000,000 6.00 63,000,000
21 Hari Hermawan Asisten Management Data 12 7,500,000 90,000,000 4.00 30,000,000 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 6.00 45,000,000 6.00 45,000,000
Sub total (A.I) JAWA BARAT + BANTEN 5,904,000,000 6,606,000,000 1,871,275,692 198,500,000 188,000,000 386,500,000 2,257,775,692 4,348,224,308
2-01-10
ASMANDAT & FINANCIAL MS
2-01-10
15-07-09
PROVINCIAL TRAINERS
1-07-09
1-07-09
15-07-09
15-07-09
15-07-09
15-07-09
15-07-09
15-07-09
15-07-09
1-07-09
1-07-09
15-07-09
15-07-09
15-07-09
15-07-09
ORIGINAL CONTRACT AMENDMENT 1
01-07-09
15-07-09
15-07-09
BALANCE
Mob. Mon Month Sub Total
BIMONTHLY INVOICE
- NOMOR : 06 BULAN : MEI 2010 & JUNI 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. NAMA POSISI Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. May-10 Jun-10 Total Jan-10 Feb-10 Total Rp. Rp.
A.II SUPPORTING STAFF
I. PROVINCIAL TEAM
1 Irriza Rosyid Database Manag/Comp. op 36 3,000,000 108,000,000 36 3,000,000 108,000,000 10.00 30,000,000 1.00 1.00 2.00 3,000,000 3,000,000 6,000,000 12.00 36,000,000 24.00 72,000,000
2 Panca Agusti Adm./Comp. Operator 36 2,000,000 72,000,000 36 2,000,000 72,000,000 10.00 20,000,000 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 12.00 24,000,000 24.00 48,000,000
3 Draftman 36 2,500,000 90,000,000 0 2,500,000 - - - - - - - - - - - - -
4 Agus Kartono Driver 36 1,000,000 36,000,000 36 1,000,000 36,000,000 10.00 10,000,000 1.00 1.00 2.00 1,000,000 1,000,000 2,000,000 12.00 12,000,000 24.00 24,000,000
II. DISTRICT
A. TASIKMALAYA
1 Totong Ahmad D. Adm/CompOperation 36 2,000,000 72,000,000 36 2,000,000 72,000,000 9.55 19,090,909 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 11.55 23,090,909 24.45 48,909,091
2 Deden Hermansyah Draftman 36 2,500,000 90,000,000 36 2,500,000 90,000,000 9.55 23,863,636 1.00 1.00 2.00 2,500,000 2,500,000 5,000,000 11.55 28,863,636 24.45 61,136,364
3 Risman Drivers 36 1,000,000 36,000,000 36 1,000,000 36,000,000 9.55 9,545,455 1.00 1.00 2.00 1,000,000 1,000,000 2,000,000 11.55 11,545,455 24.45 24,454,545
B. SUMEDANG
1 Sally Aditiawan Adm/CompOperation 36 2,000,000 72,000,000 36 2,000,000 72,000,000 9.00 18,000,000 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 11.00 22,000,000 25.00 50,000,000
2 Ari Andrian Draftman 36 2,500,000 90,000,000 36 2,500,000 90,000,000 6.91 17,272,727 1.00 1.00 2.00 2,500,000 2,500,000 5,000,000 8.91 22,272,727 27.09 67,727,273
3 Andrian Drivers 36 1,000,000 36,000,000 36 1,000,000 36,000,000 3.00 3,000,000 - 1.00 1.00 - 1,000,000 1,000,000 4.00 4,000,000 32.00 32,000,000
C. GARUT
1 Deni Ramahani Adm/CompOperation 36 2,000,000 72,000,000 36 2,000,000 72,000,000 8.75 17,500,000 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 10.75 21,500,000 25.25 50,500,000
2 Mohamad Riswan Draftman 36 2,500,000 90,000,000 36 2,500,000 90,000,000 8.75 21,875,000 1.00 1.00 2.00 2,500,000 2,500,000 5,000,000 10.75 26,875,000 25.25 63,125,000
3 Tatang Ahmad R Drivers 36 1,000,000 36,000,000 36 1,000,000 36,000,000 8.50 8,500,000 1.00 1.00 2.00 1,000,000 1,000,000 2,000,000 10.50 10,500,000 25.50 25,500,000
D. SUBANG
1 Hari Haryanto B Adm/CompOperation 36 2,000,000 72,000,000 36 2,000,000 72,000,000 9.00 18,000,000 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 11.00 22,000,000 25.00 50,000,000
2 Bagea Nugraha Draftman 36 2,500,000 90,000,000 36 2,500,000 90,000,000 9.00 22,500,000 1.00 1.00 2.00 2,500,000 2,500,000 5,000,000 11.00 27,500,000 25.00 62,500,000
3 Syamsudin Drivers 36 1,000,000 36,000,000 36 1,000,000 36,000,000 3.48 3,476,190 0.48 1.00 1.48 476,190 1,000,000 1,476,190 4.95 4,952,381 31.05 31,047,619
E. KUNINGAN
1 Yussy Juliawati Adm/CompOperation 36 2,000,000 72,000,000 36 2,000,000 72,000,000 9.00 18,000,000 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 11.00 22,000,000 25.00 50,000,000
2 Lia Meilawati Draftman 36 2,500,000 90,000,000 36 2,500,000 90,000,000 9.00 22,500,000 1.00 1.00 2.00 2,500,000 2,500,000 5,000,000 11.00 27,500,000 25.00 62,500,000
3 Oman Sulaeman Drivers 36 1,000,000 36,000,000 36 1,000,000 36,000,000 5.00 5,000,000 - 1.00 1.00 - 1,000,000 1,000,000 6.00 6,000,000 30.00 30,000,000
F. SERANG
1 Ucu Saiful/M.Yusro Adm/CompOperation 36 2,000,000 72,000,000 36 2,000,000 72,000,000 9.55 19,090,909 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 11.55 23,090,909 24.45 48,909,091
2 Supriyadi/Uus Draftman 36 2,500,000 90,000,000 36 2,500,000 90,000,000 9.55 23,863,636 1.00 1.00 2.00 2,500,000 2,500,000 5,000,000 11.55 28,863,636 24.45 61,136,364
3 Bhakti/Saman Drivers 36 1,000,000 36,000,000 36 1,000,000 36,000,000 9.17 9,171,591 1.00 1.00 2.00 1,000,000 1,000,000 2,000,000 11.17 11,171,591 24.83 24,828,409
G. LEBAK
1 Rochmatul Aliyah Adm/CompOperation 0 2,000,000 - 18 2,000,000 36,000,000 8.24 16,476,190 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 10.24 20,476,190 7.76 15,523,810
2 Hafiz Rahman Draftman 0 2,500,000 - 36 2,500,000 90,000,000 8.00 20,000,000 1.00 1.00 2.00 2,500,000 2,500,000 5,000,000 10.00 25,000,000 26.00 65,000,000
3 Opang Sopadi Drivers 0 1,000,000 - 18 1,000,000 18,000,000 6.00 6,000,000 1.00 1.00 2.00 1,000,000 1,000,000 2,000,000 8.00 8,000,000 10.00 10,000,000
Sub total (A.II) JAWA BARAT + BANTEN 1,494,000,000 1,548,000,000 382,726,244 41,976,190 44,500,000 86,476,190 469,202,435 1,078,797,565
Total A (Remuneration) JAWA BARAT + BANTEN 7,398,000,000 8,154,000,000 2,254,001,936 240,476,190 232,500,000 472,976,190 2,726,978,126 5,427,021,874
-
01-08-09
15-07-09
15-07-09
15-07-09
15-07-09
15-07-09
15-07-09
05-10-09
01-07-09
01-07-09
01-07-09
15-07-09
15-07-09
10-08-09
10-08-09
18-08-09
01-08-09
01-08-09
01-08-09
01-07-09
BIMONTHLY INVOICEORIGINAL CONTRACT
15-07-09
15-07-09
01-08-09
BALANCEAMENDMENT 1
Mob. Mon Month Sub Total
NOMOR : 06 BULAN : MEI 2010 & JUNI 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. May-10 Jun-10 Total Jan-10 Feb-10 Total Rp. Rp.
B REIMBURSABLE EXPENSES
B.I MOBILIZATION / DEMOBILIZATION
I. PROVINCIAL TEAM
1 Provincial Team Leader 1 300,000 300,000 1 300,000 300,000 0.50 150,000 - - - - - 0.50 150,000 0.50 150,000
-
2 Financial Management Specilist RT 1 300,000 300,000 0.50 150,000 - - - - - 0.50 150,000 0.50 150,000
3 Asistant management Data RT 1 300,000 300,000 0.50 150,000 - - - - - 0.50 150,000 0.50 150,000
II. DISTRICT
A. TASIKMALAYA
1 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
2 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
B. SUMEDANG
1 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
2 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
C. GARUT
1 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
2 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
D. SUBANG
1 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
2 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
E. KUNINGAN
1 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
2 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
F. SERANG
1 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
2 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
G. LEBAK -
1 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
2 1 500,000 500,000 1 500,000 500,000 0.50 250,000 - - - - - 0.50 250,000 0.50 250,000
Sub total (B.I) JAWA BARAT + BANTEN 7,300,000 7,900,000 3,950,000 - - - 3,950,000 3,950,000
Distric Health & Hygiene Specialist (HHS) RT
Distric Health & Hygiene Specialist (HHS) RT
Water Supply Eng. (WSE) and Communal SanitationContruction (WSE)
RT
Water Supply Eng. (WSE) and Communal SanitationContruction (WSE)
RT
Distric Health & Hygiene Specialist (HHS) RT
Water Supply Eng. (WSE) and Communal SanitationContruction (WSE)
RT
Distric Health & Hygiene Specialist (HHS) RT
Water Supply Eng. (WSE) and Communal SanitationContruction (WSE)
RT
Distric Health & Hygiene Specialist (HHS) RT
Water Supply Eng. (WSE) and Communal SanitationContruction (WSE)
RT
Distric Health & Hygiene Specialist (HHS) RT
Water Supply Eng. (WSE) and Communal SanitationContruction (WSE)
RT
RT
Water Supply Eng. (WSE) and Communal SanitationContruction (WSE)
RT
Distric Health & Hygiene Specialist (HHS) RT
BIMONTHLY INVOICEBALANCE
DESCRIPTION Mon Month Sub Total
ORIGINAL CONTRACT AMENDMENT 1
NOMOR : 06 BULAN : MEI 2010 & JUNI 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. May-10 Jun-10 Total Jan-10 Feb-10 Total Rp. Rp.
B.II HOUSING ALLOWANCE
I. PROVINCIAL TEAM
1 Provincial Team Leader 36 1,000,000 36,000,000 36 1,000,000 36,000,000 10.00 10,000,000 1.00 1.00 2.00 1,000,000 1,000,000 2,000,000 12.00 12,000,000 24.00 24,000,000
2 Financial Management Specialist 12 1,000,000 12,000,000 4.00 4,000,000 1.00 1.00 2.00 1,000,000 1,000,000 2,000,000 6.00 6,000,000 6.00 6,000,000
3 Asistant Management Data 12 1,000,000 12,000,000 4.00 4,000,000 1.00 1.00 2.00 1,000,000 1,000,000 2,000,000 6.00 6,000,000 6.00 6,000,000
II. DISTRICT
A. TASIKMALAYA
1 36 800,000 28,800,000 36 800,000 28,800,000 9.55 7,636,364 1.00 1.00 2.00 800,000 800,000 1,600,000 11.55 9,236,364 24.45 19,563,636
2 36 800,000 28,800,000 36 800,000 28,800,000 9.55 7,636,364 1.00 1.00 2.00 800,000 800,000 1,600,000 11.55 9,236,364 24.45 19,563,636
B. SUMEDANG
1 36 800,000 28,800,000 36 800,000 28,800,000 9.55 7,636,364 1.00 1.00 2.00 800,000 800,000 1,600,000 11.55 9,236,364 24.45 19,563,636
2 36 800,000 28,800,000 36 800,000 28,800,000 9.55 7,636,364 1.00 - 1.00 800,000 - 800,000 10.55 8,436,364 25.45 20,363,636
C. GARUT
1 36 800,000 28,800,000 36 800,000 28,800,000 9.55 7,636,364 1.00 1.00 2.00 800,000 800,000 1,600,000 11.55 9,236,364 24.45 19,563,636
2 36 800,000 28,800,000 36 800,000 28,800,000 9.55 7,636,364 1.00 1.00 2.00 800,000 800,000 1,600,000 11.55 9,236,364 24.45 19,563,636
D. SUBANG
1 36 800,000 28,800,000 36 800,000 28,800,000 9.55 7,636,364 1.00 1.00 2.00 800,000 800,000 1,600,000 11.55 9,236,364 24.45 19,563,636
2 36 800,000 28,800,000 36 800,000 28,800,000 9.23 7,381,818 1.00 1.00 2.00 800,000 800,000 1,600,000 11.23 8,981,818 24.77 19,818,182
E. KUNINGAN
1 36 800,000 28,800,000 36 800,000 28,800,000 8.55 6,836,364 1.00 1.00 2.00 800,000 800,000 1,600,000 10.55 8,436,364 25.45 20,363,636
2 36 800,000 28,800,000 36 800,000 28,800,000 9.05 7,236,364 - - - - - - 9.05 7,236,364 26.95 21,563,636
E. SERANG
1 36 800,000 28,800,000 36 800,000 28,800,000 9.55 7,636,364 1.00 1.00 2.00 800,000 800,000 1,600,000 11.55 9,236,364 24.45 19,563,636
2 36 800,000 28,800,000 36 800,000 28,800,000 9.55 7,636,364 1.00 1.00 2.00 800,000 800,000 1,600,000 11.55 9,236,364 24.45 19,563,636
E. LEBAK -
1 36 800,000 28,800,000 36 800,000 28,800,000 9.55 7,636,364 1.00 1.00 2.00 800,000 800,000 1,600,000 11.55 9,236,364 24.45 19,563,636
2 36 800,000 28,800,000 36 800,000 28,800,000 9.55 7,636,364 1.00 1.00 2.00 800,000 800,000 1,600,000 11.55 9,236,364 24.45 19,563,636
Sub total (B.II) JAWA BARAT + BANTEN 439,200,000 463,200,000 123,454,545 13,400,000 12,600,000 26,000,000 149,454,545 313,745,455
Water Supply Eng. (WSE) and Communal SanitationContruction (WSE)
Months
Distric Health & Hygiene Specialist (HHS) Months
Water Supply Eng. (WSE) and Communal SanitationContruction (WSE)
Months
Distric Health & Hygiene Specialist (HHS) Months
Distric Health & Hygiene Specialist (HHS) Months
Water Supply Eng. (WSE) and Communal SanitationContruction (WSE)
Months
Distric Health & Hygiene Specialist (HHS) Months
Water Supply Eng. (WSE) and Communal SanitationContruction (WSE)
Months
Distric Health & Hygiene Specialist (HHS) Months
Water Supply Eng. (WSE) and Communal SanitationContruction (WSE)
Months
Distric Health & Hygiene Specialist (HHS) Months
Water Supply Eng. (WSE) and Communal SanitationContruction (WSE)
Months
Distric Health & Hygiene Specialist (HHS) Months
Months
Months
Months
Water Supply Eng. (WSE) and Communal SanitationContruction (WSE)
Months
BIMONTHLY INVOICEBALANCE
DESCRIPTION Mon Month Sub Total
ORIGINAL CONTRACT AMENDMENT 1
- NOMOR : 06 BULAN : MEI 2010 & JUNI 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. Mei.10 Juni.10 Total Jan-10 Feb-10 Total Rp. Rp.
B.III DUTY TRAVEL
I. PROVINCIAL TEAM
1 Team Leader
a. Transportation Province to Jakarta (2 Trip/Year) 6 300,000 1,800,000 6 300,000 1,800,000 6.00 1,800,000 - - - - - - 6.00 1,800,000 - -
b. Transportation Prov. to District (2 Trip/Year/DIstrict) 42 400,000 16,800,000 42 400,000 16,800,000 28.00 11,200,000 - 7.00 7.00 - 2,800,000 2,800,000 35.00 14,000,000 7.00 2,800,000
2 Provincial Trainer
a. Transp.District to Jakarta (54 Trip/Year x 4 Person) 16 300,000 4,800,000 8.00 2,400,000 - - - - - - 8.00 2,400,000 8.00 2,400,000
b. Transp.District to Province (8 Trip/Year x 4 person) 48 400,000 19,200,000 48.00 19,200,000 - - - - - - 48.00 19,200,000 - -
3 FMS and Asmandat -
a. Transp.District to Jakarta (4 Trip/Year x 2 Person) 8 300,000 2,400,000 6.00 1,800,000 - - - - - - 6.00 1,800,000 2.00 600,000
b. Transp.District to Province (4 Trip/Year x 7 Dist/Year x 2 person) 56 400,000 22,400,000 6.00 2,400,000 - 7.00 7.00 - 2,800,000 2,800,000 13.00 5,200,000 43.00 17,200,000
II. DISTRICT - - - - -
A. TASIKMALAYA
1
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 4.00 1,600,000 1.00 2.00 3.00 400,000 800,000 1,200,000 7.00 2,800,000 5.00 2,000,000
2
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 4.00 1,600,000 - 1.00 1.00 - 400,000 400,000 5.00 2,000,000 7.00 2,800,000
B. SUMEDANG
1
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 4.00 1,600,000 1.00 1.00 2.00 400,000 400,000 800,000 6.00 2,400,000 6.00 2,400,000
2
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 3.00 1,200,000 - - - - - - 3.00 1,200,000 9.00 3,600,000
C. GARUT
1
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 2.00 600,000 - - - - - - 2.00 600,000 1.00 300,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 6.00 2,400,000 1.00 2.00 3.00 400,000 800,000 1,200,000 9.00 3,600,000 3.00 1,200,000
2
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - 1.00 1.00 - 300,000 300,000 1.00 300,000 2.00 600,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 6.00 2,400,000 - 1.00 1.00 - 400,000 400,000 7.00 2,800,000 5.00 2,000,000
D. SUBANG
1
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 6.00 2,400,000 1.00 1.00 2.00 400,000 400,000 800,000 8.00 3,200,000 4.00 1,600,000
2
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 5.00 2,000,000 - 1.00 1.00 - 400,000 400,000 6.00 2,400,000 6.00 2,400,000
E. KUNINGAN
1
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 5.00 2,000,000 1.00 1.00 2.00 400,000 400,000 800,000 7.00 2,800,000 5.00 2,000,000
2
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 5.00 2,000,000 - - - - - - 5.00 2,000,000 7.00 2,800,000
F. SERANG
1
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 2.00 800,000 - 1.00 1.00 - 400,000 400,000 3.00 1,200,000 9.00 3,600,000
2
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 2.00 800,000 - 1.00 1.00 - 400,000 400,000 3.00 1,200,000 9.00 3,600,000
G. LEBAK
1
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 2.00 800,000 - 1.00 1.00 - 400,000 400,000 3.00 1,200,000 9.00 3,600,000
2
a. Transportation District to Jakarta (1 Trip/Year) 3 300,000 900,000 3 300,000 900,000 - - - - - - - - - - 3.00 900,000
b. Transportation District to Province (4 Trip/Year) 12 400,000 4,800,000 12 400,000 4,800,000 2.00 800,000 - 1.00 1.00 - 400,000 400,000 3.00 1,200,000 9.00 3,600,000
Sub total (B.III) JAWA BARAT + BANTEN 98,400,000 147,200,000 61,800,000 2,000,000 11,500,000 13,500,000 75,300,000 71,900,000
- NOMOR : 06BULAN : MEI 2010 & JUNI 2010
RT
RT
Water Sup. Eng.(WSE) & Communal Sanit. Cont.(WSE)
RT
Distric Health & Hygiene Specialist (HHS)
RT
RT
RT
Distric Health & Hygiene Specialist (HHS)
RT
RT
Water Sup. Eng.(WSE) & Communal Sanit. Cont.(WSE)
RT
RT
Distric Health & Hygiene Specialist (HHS)
RT
RT
Water Sup. Eng.(WSE) & Communal Sanit.Cont.(WSE)
RT
Distric Health & Hygiene Specialist (HHS)
RT
RT
Water Sup. Eng.(WSE) & Communal Sanit. Cont.(WSE)
RT
RT
RT
RT
Distric Health & Hygiene Specialist (HHS)
RT
RT
Water Sup. Eng.(WSE) & Communal Sanit. Cont.(WSE)
RT
RT
RT
Distric Health & Hygiene Specialist (HHS)
DESCRIPTION
RT
RT
Water Sup. Eng.(WSE) & Communal Sanit. Cont.(WSE)
RT
Distric Health & Hygiene Specialist (HHS)
RT
Water Sup. Eng.(WSE) & Communal Sanit. Cont.(WSE)
RT
RT
BALANCE
Mon Month Sub Total
BIMONTHLY INVOICEORIGINAL CONTRACT AMENDMENT 1
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume TotalCost Rp. Cost Rp. Rp. May-10 Jun-10 Total May-10 Jun-10 Total Rp. Rp.
B.IV OUT OF STATION ALLOWANCE (OSA)
I. PROVINCIAL TEAM
1 Team Leader
a. OSA to Jakarta (2 Trip/Year @ 2 days) 28 850,000 23,800,000 28 850,000 23,800,000 11.00 9,350,000 - - - - - - 11.00 9,350,000 17.00 14,450,000
b. OSA to District (2Trip/Year/Dis. @ 2days) 84 500,000 42,000,000 84 500,000 42,000,000 50.00 25,000,000 - 9.00 9.00 - 4,500,000 4,500,000 59.00 29,500,000 25.00 12,500,000
2 Provincial Trainer -
a. OSA to Jakarta (5 Trip/Year @ 2 days x 4 ) 32 850,000 27,200,000 24.00 20,400,000 - - - - - - 24.00 20,400,000 8.00 6,800,000
b. OSA to District (8Trip/Year/Dis. @ 2 x 4) 96 500,000 48,000,000 96.00 48,000,000 - - - - - - 96.00 48,000,000 - -
c. OSA Dis. to Vil. (6Trip/Year/Dis. @ 3 x 4) 180 50,000 9,000,000 - - - 13.00 13.00 - 650,000 650,000 13.00 650,000 167.00 8,350,000
3 FMS and Asmandat -
a. OSA to Jakarta (4 Trip/Year @ 2 days x 2) 16 850,000 13,600,000 16.00 13,600,000 - - - - - - 16.00 13,600,000 - -
b. OSA Dis.to Dist. (4Trip x 7Dis. @ 2 d x2 p) 112 500,000 56,000,000 14.00 7,000,000 - 9.00 9.00 - 4,500,000 4,500,000 23.00 11,500,000 89.00 44,500,000
II. DISTRICT
A. TASIKMALAYA
1
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 13.00 6,500,000 1.00 5.00 6.00 500,000 2,500,000 3,000,000 19.00 9,500,000 17.00 8,500,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 125.00 6,250,000 14.00 14.00 28.00 700,000 700,000 1,400,000 153.00 7,650,000 351.00 17,550,000
2
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 13.00 6,500,000 - 1.00 1.00 - 500,000 500,000 14.00 7,000,000 22.00 11,000,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 122.00 6,100,000 14.00 14.00 28.00 700,000 700,000 1,400,000 150.00 7,500,000 354.00 17,700,000
B. SUMEDANG
1
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 13.00 6,500,000 1.00 6.00 7.00 500,000 3,000,000 3,500,000 20.00 10,000,000 16.00 8,000,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 126.00 6,300,000 14.00 14.00 28.00 700,000 700,000 1,400,000 154.00 7,700,000 350.00 17,500,000
2
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 13.00 6,500,000 - - - - - - 13.00 6,500,000 23.00 11,500,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 126.00 6,300,000 - - - - - - 126.00 6,300,000 378.00 18,900,000
C. GARUT
1
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 6.00 5,100,000 - - - - - - 6.00 5,100,000 - -
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 19.00 9,500,000 1.00 5.00 6.00 500,000 2,500,000 3,000,000 25.00 12,500,000 11.00 5,500,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 125.00 6,250,000 14.00 14.00 28.00 700,000 700,000 1,400,000 153.00 7,650,000 351.00 17,550,000
2
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 19.00 9,500,000 - 2.00 2.00 - 1,000,000 1,000,000 21.00 10,500,000 15.00 7,500,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 126.00 6,300,000 14.00 14.00 28.00 700,000 700,000 1,400,000 154.00 7,700,000 350.00 17,500,000
D. SUBANG
1
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 17.00 8,500,000 1.00 4.00 5.00 500,000 2,000,000 2,500,000 22.00 11,000,000 14.00 7,000,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 99.00 4,950,000 14.00 14.00 28.00 700,000 700,000 1,400,000 127.00 6,350,000 377.00 18,850,000
2
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 16.00 8,000,000 - 1.00 1.00 - 500,000 500,000 17.00 8,500,000 19.00 9,500,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 127.00 6,350,000 14.00 14.00 28.00 700,000 700,000 1,400,000 155.00 7,750,000 349.00 17,450,000
E. KUNINGAN
1
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 16.00 8,000,000 1.00 6.00 7.00 500,000 3,000,000 3,500,000 23.00 11,500,000 13.00 6,500,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 122.00 6,100,000 1.00 5.00 6.00 50,000 250,000 300,000 128.00 6,400,000 376.00 18,800,000
2
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 16.00 8,000,000 - - - - - - 16.00 8,000,000 20.00 10,000,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 110.00 5,500,000 - - - - - - 110.00 5,500,000 394.00 19,700,000
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Distric Health & Hygiene Specialist (HHS)
Man.Days
Man.Days
Man.Days
Water Sup. Eng.(WSE) & Communal Sanit. Cont.(WSE)
Man.Days
Man.Days
Man.Days
Distric Health & Hygiene Specialist (HHS)
Man.Days
Man.Days
Man.Days
Water Sup. Eng.(WSE) & Communal Sanit. Cont.
Man.Days
Man.Days
Distric Health & Hygiene Specialist (HHS)
Man.Days
Man.Days
Man.Days
Water Sup. Eng.(WSE) & Communal Sanit. Cont.(WSE)
Man.Days
Distric Health & Hygiene Specialist (HHS)
Man.Days
Man.Days
Man.Days
Water Sup. Eng.(WSE) & Communal Sanit. Cont.(WSE)
Man.Days
Man.Days
Distric Health & Hygiene Specialist (HHS)
Man.Days
Water Sup. Eng.(WSE) & Communal Sanit. Cont.(WSE)
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
Man.Days
BALANCE
DESCRIPTION Mon Month Sub Total
BIMONTHLY INVOICEORIGINAL CONTRACT AMENDMENT 1
F. SERANG
1
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 6.00 3,000,000 - 1.00 1.00 - 500,000 500,000 7.00 3,500,000 29.00 14,500,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 49.00 2,450,000 11.00 8.00 19.00 550,000 400,000 950,000 68.00 3,400,000 436.00 21,800,000
2 -
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 6.00 3,000,000 - 1.00 1.00 - 500,000 500,000 7.00 3,500,000 29.00 14,500,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 49.00 2,450,000 12.00 8.00 20.00 600,000 400,000 1,000,000 69.00 3,450,000 435.00 21,750,000
G. LEBAK
1
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 6.00 3,000,000 - 7.00 7.00 - 3,500,000 3,500,000 13.00 6,500,000 23.00 11,500,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 34.00 1,700,000 11.00 12.00 23.00 550,000 600,000 1,150,000 57.00 2,850,000 447.00 22,350,000
2 -
a. OSA to Jakarta (1 Trip/Year @ 2 days) 6 850,000 5,100,000 6 850,000 5,100,000 - - - - - - - - - - 6.00 5,100,000
b. OSA to Province (4 Trip/Year @ 3 days) 36 500,000 18,000,000 36 500,000 18,000,000 6.00 3,000,000 - 7.00 7.00 - 3,500,000 3,500,000 13.00 6,500,000 23.00 11,500,000
c. OSA District to Village (1 Trip/Year @ 14 days) 504 50,000 25,200,000 504 50,000 25,200,000 34.00 1,700,000 11.00 12.00 23.00 550,000 600,000 1,150,000 57.00 2,850,000 447.00 22,350,000
Sub total (B.IV) JAWA BARAT + BANTEN 742,000,000 895,800,000 286,650,000 9,700,000 39,800,000 49,500,000 336,150,000 559,650,000
-
B.V CAR RENTAL
I. PROVINCIAL TEAM
Car Rental and O & M (1 unit x 36 Months) 36 7,500,000 270,000,000 36 7,500,000 270,000,000 10.00 75,000,000 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 12.00 90,000,000 24.00 180,000,000
II. DISTRICT
A. TASIKMALAYA
Car Rental and O & M (5 unit x 36 Months) 36 7,500,000 270,000,000 36 7,500,000 270,000,000 9.55 71,590,909 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 11.55 86,590,909 24.45 183,409,091
B. SUMEDANG -
Car Rental and O & M (5 unit x 36 Months) 36 7,500,000 270,000,000 36 7,500,000 270,000,000 9.55 71,590,909 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 11.55 86,590,909 24.45 183,409,091
C. GARUT #REF!
Car Rental and O & M (5 unit x 36 Months) 36 7,500,000 270,000,000 36 7,500,000 270,000,000 9.55 71,590,909 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 11.55 86,590,909 24.45 183,409,091
D. SUBANG
Car Rental and O & M (5 unit x 36 Months) 36 7,500,000 270,000,000 36 7,500,000 270,000,000 9.55 71,590,909 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 11.55 86,590,909 24.45 183,409,091
E. KUNINGAN
Car Rental and O & M (5 unit x 36 Months) 36 7,500,000 270,000,000 36 7,500,000 270,000,000 9.55 71,590,909 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 11.55 86,590,909 24.45 183,409,091
F. SERANG
Car Rental and O & M (5 unit x 36 Months) 36 7,500,000 270,000,000 36 7,500,000 270,000,000 7.05 52,840,909 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 9.05 67,840,909 26.95 202,159,091
G. LEBAK
Car Rental and O & M (5 unit x 36 Months) 36 7,500,000 270,000,000 36 7,500,000 270,000,000 7.05 52,840,909 1.00 1.00 2.00 7,500,000 7,500,000 15,000,000 9.05 67,840,909 26.95 202,159,091
Sub total (B.V) JAWA BARAT + BANTEN 2,160,000,000 2,160,000,000 538,636,364 60,000,000 60,000,000 120,000,000 658,636,364 1,501,363,636
-
Car-Months
Car-Months
Man.Days
Man.Days
Man.Days
Car-Months
Car-Months
Car-Months
Car-Months
Car-Months
Car-Months
Man.Days
Man.Days
Man.Days
Distric Health & Hygiene Specialist (HHS)
Man.Days
Man.Days
Man.Days
Water Sup. Eng.(WSE) & Communal Sanit.Cont.(WSE)
Man.Days
Man.Days
Man.Days
Distric Health & Hygiene Specialist (HHS)
Water Sup. Eng.(WSE) & Communal Sanit.Cont.(WSE)
NOMOR : 06 BULAN : MEI 2010 & JUNI 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. May-10 Jun-10 Total May-10 Jun-10 Total Rp. Rp.
B.VI OFFICE EQUIPMENTS
I. PROVINCIAL TEAM
Provincial Office
a. Computer (Rental) 2 unit / Months 72 750,000 54,000,000 72 750,000 54,000,000 20.00 15,000,000 2.00 2.00 4.00 1,500,000 1,500,000 3,000,000 24.00 18,000,000 48.00 36,000,000
b. Computer (Rental) 1 unit/Month 12 750,000 9,000,000 2.00 1,500,000 1.00 1.00 2.00 750,000 750,000 1,500,000 4.00 3,000,000 8.00 6,000,000
b. Printer (Rental) 1 Unit/Months 36 350,000 12,600,000 36 350,000 12,600,000 10.00 3,500,000 1.00 1.00 2.00 350,000 350,000 700,000 12.00 4,200,000 24.00 8,400,000
Provincial Trainers
a. Note Book (Rental) 3 unit / Months 54 750,000 40,500,000 30.00 22,500,000 3.00 3.00 6.00 2,250,000 2,250,000 4,500,000 36.00 27,000,000 18.00 13,500,000
b. Printer (Rental) 1 Unit/Months 18 350,000 6,300,000 10.00 3,500,000 1.00 1.00 2.00 350,000 350,000 700,000 12.00 4,200,000 6.00 2,100,000
c. Digital Camera (Rental) 1 Unit/Month 18 200,000 3,600,000 10.00 2,000,000 1.00 1.00 2.00 200,000 200,000 400,000 12.00 2,400,000 6.00 1,200,000
II. DISTRICT
A. TASIKMALAYA
a. Computer (Rental) 2 unit / District / Months 72 750,000 54,000,000 72 750,000 54,000,000 19.09 14,318,182 2.00 2.00 4.00 1,500,000 1,500,000 3,000,000 23.09 17,318,182 48.91 36,681,818
b. Printer (Rental) 1 Unit/Months 36 350,000 12,600,000 36 350,000 12,600,000 9.55 3,340,909 1.00 1.00 2.00 350,000 350,000 700,000 11.55 4,040,909 24.45 8,559,091
c. Digital Camera (Rental) 1 Unit/Month/Distric 36 200,000 7,200,000 36 200,000 7,200,000 9.55 1,909,091 1.00 1.00 2.00 200,000 200,000 400,000 11.55 2,309,091 24.45 4,890,909
B. SUMEDANG
a. Computer (Rental) 2 unit / District / Months 72 750,000 54,000,000 72 750,000 54,000,000 19.09 14,318,182 2.00 2.00 4.00 1,500,000 1,500,000 3,000,000 23.09 17,318,182 48.91 36,681,818
b. Printer (Rental) 1 Unit/Months 36 350,000 12,600,000 36 350,000 12,600,000 9.55 3,340,909 1.00 1.00 2.00 350,000 350,000 700,000 11.55 4,040,909 24.45 8,559,091
c. Digital Camera (Rental) 1 Unit/Month/Distric 36 200,000 7,200,000 36 200,000 7,200,000 9.55 1,909,091 1.00 1.00 2.00 200,000 200,000 400,000 11.55 2,309,091 24.45 4,890,909
C. GARUT
a. Computer (Rental) 2 unit / District / Months 72 750,000 54,000,000 72 750,000 54,000,000 19.09 14,318,182 2.00 2.00 4.00 1,500,000 1,500,000 3,000,000 23.09 17,318,182 48.91 36,681,818
b. Printer (Rental) 1 Unit/Months 36 350,000 12,600,000 36 350,000 12,600,000 9.55 3,340,909 1.00 1.00 2.00 350,000 350,000 700,000 11.55 4,040,909 24.45 8,559,091
c. Digital Camera (Rental) 1 Unit/Month/Distric 36 200,000 7,200,000 36 200,000 7,200,000 9.55 1,909,091 1.00 1.00 2.00 200,000 200,000 400,000 11.55 2,309,091 24.45 4,890,909
D. SUBANG
a. Computer (Rental) 2 unit / District / Months 72 750,000 54,000,000 72 750,000 54,000,000 19.09 14,318,182 2.00 2.00 4.00 1,500,000 1,500,000 3,000,000 23.09 17,318,182 48.91 36,681,818
b. Printer (Rental) 1 Unit/Months 36 350,000 12,600,000 36 350,000 12,600,000 9.55 3,340,909 1.00 1.00 2.00 350,000 350,000 700,000 11.55 4,040,909 24.45 8,559,091
c. Digital Camera (Rental) 1 Unit/Month/Distric 36 200,000 7,200,000 36 200,000 7,200,000 9.55 1,909,091 1.00 1.00 2.00 200,000 200,000 400,000 11.55 2,309,091 24.45 4,890,909
E. KUNINGAN
a. Computer (Rental) 2 unit / District / Months 72 750,000 54,000,000 72 750,000 54,000,000 19.09 14,318,182 2.00 2.00 4.00 1,500,000 1,500,000 3,000,000 23.09 17,318,182 48.91 36,681,818
b. Printer (Rental) 1 Unit/Months 36 350,000 12,600,000 36 350,000 12,600,000 9.55 3,340,909 1.00 1.00 2.00 350,000 350,000 700,000 11.55 4,040,909 24.45 8,559,091
c. Digital Camera (Rental) 1 Unit/Month/Distric 36 200,000 7,200,000 36 200,000 7,200,000 9.55 1,909,091 1.00 1.00 2.00 200,000 200,000 400,000 11.55 2,309,091 24.45 4,890,909
D. SERANG - -
a. Computer (Rental) 2 unit / District / Months 72 750,000 54,000,000 72 750,000 54,000,000 19.09 14,314,091 2.00 2.00 4.00 1,500,000 1,500,000 3,000,000 23.09 17,314,091 48.91 36,685,909
b. Printer (Rental) 1 Unit/Months 36 350,000 12,600,000 36 350,000 12,600,000 9.55 3,340,909 1.00 1.00 2.00 350,000 350,000 700,000 11.55 4,040,909 24.45 8,559,091
c. Digital Camera (Rental) 1 Unit/Month/Distric 36 200,000 7,200,000 36 200,000 7,200,000 9.55 1,909,091 1.00 1.00 2.00 200,000 200,000 400,000 11.55 2,309,091 24.45 4,890,909
E. LEBAK
a. Computer (Rental) 2 unit / District / Months 72 750,000 54,000,000 72 750,000 54,000,000 19.09 14,314,091 2.00 2.00 4.00 1,500,000 1,500,000 3,000,000 23.09 17,314,091 48.91 36,685,909
b. Printer (Rental) 1 Unit/Months 36 350,000 12,600,000 36 350,000 12,600,000 9.55 3,340,909 1.00 1.00 2.00 350,000 350,000 700,000 11.55 4,040,909 24.45 8,559,091
c. Digital Camera (Rental) 1 Unit/Month/Distric 36 200,000 7,200,000 36 200,000 7,200,000 9.55 1,909,091 1.00 1.00 2.00 200,000 200,000 400,000 11.55 2,309,091 24.45 4,890,909
Sub total (B.VI) JAWA BARAT + BANTEN 583,200,000 642,600,000 184,969,091 19,750,000 19,750,000 39,500,000 224,469,091 418,130,909
-
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
Unit-Months
ORIGINAL CONTRACT
Unit-Months
Unit-Months
DESCRIPTION
Unit-Months
BALANCEAMENDMENT 1
Mon Month Sub Total
BIMONTHLY INVOICE
NOMOR : 06 BULAN : MEI 2010 & JUNI 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. May-10 Jun-10 Total May-10 Jun-10 Total Rp. Rp.
B.VII OFFICE COST
I. PROVINCIAL TEAM
a. Office Supply 36 1,000,000 36,000,000 36 1,000,000 36,000,000 10.00 5,866,925 1.00 1.00 2.00 412,400 522,100 934,500 12.00 6,801,425 24.00 29,198,575
b. Comnputer/Printer Supply 36 750,000 27,000,000 36 750,000 27,000,000 10.00 4,811,000 1.00 1.00 2.00 405,000 452,500 857,500 12.00 5,668,500 24.00 21,331,500
II. DISTRICT
A. TASIKMALAYA
a. Office Supply 36.0 750,000 27,000,000 36.0 750,000 27,000,000 10.00 2,858,557 1.00 1.00 2.00 226,300 256,600 482,900 12.00 3,341,457 24.00 23,658,543
b. Comnputer/Printer Supply / Reproduction 36.0 500,000 18,000,000 36.0 500,000 18,000,000 9.00 3,585,900 1.00 1.00 2.00 421,800 270,500 692,300 11.00 4,278,200 25.00 13,721,800
c. Survey Equipments 12.0 1,200,000 14,400,000 12.0 1,200,000 14,400,000 - - - - - - - - 12.00 14,400,000
B. SUMEDANG
a. Office Supply 36.0 750,000 27,000,000 36.0 750,000 27,000,000 8.00 3,000,050 1.00 1.00 2.00 412,500 257,500 670,000 10.00 3,670,050 26.00 23,329,950
b. Comnputer/Printer Supply / Reproduction 36.0 500,000 18,000,000 36.0 500,000 18,000,000 7.00 2,883,800 1.00 1.00 2.00 416,500 310,400 726,900 9.00 3,610,700 27.00 14,389,300
c. Survey Equipments 12.0 1,200,000 14,400,000 12.0 1,200,000 14,400,000 - - - - - - - - 12.00 14,400,000
C. GARUT
a. Office Supply 36.0 750,000 27,000,000 36.0 750,000 27,000,000 8.00 2,575,250 1.00 1.00 2.00 227,300 192,300 419,600 10.00 2,994,850 26.00 24,005,150
b. Comnputer/Printer Supply / Reproduction 36.0 500,000 18,000,000 36.0 500,000 18,000,000 8.00 3,310,000 1.00 1.00 2.00 125,000 325,000 450,000 10.00 3,760,000 26.00 14,240,000
c. Survey Equipments 12.0 1,200,000 14,400,000 12.0 1,200,000 14,400,000 1.00 - - - - - 1.00 - 11.00 14,400,000
D. SUBANG
a. Office Supply 36.0 750,000 27,000,000 36.0 750,000 27,000,000 8.00 1,858,400 1.00 1.00 2.00 556,000 221,000 777,000 10.00 2,635,400 26.00 24,364,600
b. Comnputer/Printer Supply / Reproduction 36.0 500,000 18,000,000 36.0 500,000 18,000,000 7.00 3,245,000 1.00 1.00 2.00 143,000 292,500 435,500 9.00 3,680,500 27.00 14,319,500
c. Survey Equipments 12.0 1,200,000 14,400,000 12.0 1,200,000 14,400,000 - - - - - - - 12.00 14,400,000
E. KUNINGAN
a. Office Supply 36.0 750,000 27,000,000 36.0 750,000 27,000,000 8.00 3,220,200 1.00 1.00 2.00 191,200 216,450 407,650 10.00 3,627,850 26.00 23,372,150
b. Comnputer/Printer Supply / Reproduction 36.0 500,000 18,000,000 36.0 500,000 18,000,000 7.00 3,212,200 1.00 1.00 2.00 394,000 404,000 798,000 9.00 4,010,200 27.00 13,989,800
c. Survey Equipments 12.0 1,200,000 14,400,000 12.0 1,200,000 14,400,000 - - - - - - - 12.00 14,400,000
F. SERANG
a. Office Supply 36.0 750,000 27,000,000 36.0 750,000 27,000,000 7.50 1,512,600 1.00 1.00 2.00 213,400 218,500 431,900 9.50 1,944,500 26.50 25,055,500
b. Comnputer/Printer Supply / Reproduction 36.0 500,000 18,000,000 36.0 500,000 18,000,000 7.50 3,726,200 1.00 1.00 2.00 275,000 425,000 700,000 9.50 4,426,200 26.50 13,573,800
c. Survey Equipments 12.0 1,200,000 14,400,000 12.0 1,200,000 14,400,000 - - - - - - - - - - 12.00 14,400,000
G. LEBAK
a. Office Supply 36.0 750,000 27,000,000 36.0 750,000 27,000,000 7.50 2,337,800 1.00 1.00 2.00 234,200 305,800 540,000 9.50 2,877,800 26.50 24,122,200
b. Comnputer/Printer Supply / Reproduction 36.0 500,000 18,000,000 36.0 500,000 18,000,000 7.50 2,716,600 1.00 1.00 2.00 420,000 300,000 720,000 9.50 3,436,600 26.50 14,563,400
c. Survey Equipments 12.0 1,200,000 14,400,000 12.0 1,200,000 14,400,000 - - - - - - - - - - 12.00 14,400,000
Sub total (B.VII) JAWA BARAT + BANTEN 478,800,000 478,800,000 50,720,482 5,073,600 4,970,150 10,043,750 60,764,232 418,035,768
-
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
DESCRIPTION
Months
Months
Months
Months
Months
Months
Months
Sub Total
BIMONTHLY INVOICEBALANCE
Months
Months
AMENDMENT 1ORIGINAL CONTRACT
Mon Month
NOMOR : 06 BULAN : MEI 2010 & JUNI 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. May-10 Jun-10 Total May-10 Jun-10 Total Rp. Rp.
B.VIIITELECOMMUNICATION
I. PROVINCIAL TEAM
Telecommunication 36 1,000,000 36,000,000 36 1,000,000 36,000,000 9.00 4,957,967 1.00 1.00 2.00 409,497 418,831 828,328 11.00 5,786,295 25.00 30,213,705
II. DISTRICT
A. TASIKMALAYA
36 500,000 18,000,000 36 500,000 18,000,000 9.00 4,558,114 1.00 1.00 2.00 500,000 500,000 1,000,000 11.00 5,558,114 25.00 12,441,886
B. SUMEDANG
36 500,000 18,000,000 36 500,000 18,000,000 9.00 3,151,436 1.00 1.00 2.00 388,307 424,981 813,288 11.00 3,964,724 25.00 14,035,276
C. GARUT
36 500,000 18,000,000 36 500,000 18,000,000 9.00 2,337,511 1.00 1.00 2.00 335,948 327,879 663,827 11.00 3,001,338 25.00 14,998,662
D. SUBANG
36 500,000 18,000,000 36 500,000 18,000,000 9.00 2,807,081 1.00 1.00 2.00 303,435 336,814 640,249 11.00 3,447,330 25.00 14,552,670
E. KUNINGAN
36 500,000 18,000,000 36 500,000 18,000,000 9.00 2,070,511 1.00 1.00 2.00 219,051 189,662 408,713 11.00 2,479,224 25.00 15,520,776
F. SERANG
36 500,000 18,000,000 36 500,000 18,000,000 6.50 3,572,534 1.00 1.00 2.00 321,627 328,513 650,140 8.50 4,222,674 27.50 13,777,326
E. LEBAK
36 500,000 18,000,000 36 500,000 18,000,000 7.50 3,726,178 1.00 1.00 2.00 542,096 418,130 960,226 9.50 4,686,404 26.50 13,313,596
Sub total (B.VIII) JABAR + BANTEN 162,000,000 162,000,000 27,181,332 3,019,961 2,944,810 5,964,771 33,146,103 128,853,897
-
Telecommunication Months
Telecommunication Months
Telecommunication Months
Telecommunication Months
Telecommunication Months
Months
Telecommunication Months
Telecommunication Months
BIMONTHLY INVOICEBALANCE
DESCRIPTION Mon Month Sub Total
ORIGINAL CONTRACT AMENDMENT 1
NOMOR : 06 BULAN : MEI 2010 & JUNI 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. May-10 Jun-10 Total May-10 Jun-10 Total Rp. Rp.
B.IX REPORTS
1 Inceptions Report (15 copies)/district 75.0 50,000 3,750,000 75.0 50,000 3,750,000 - - - - - 75.00 3,750,000
2 Monthly Report (15 copies/Month)/district 3 FY 2,700.0 25,000 67,500,000 2,700.0 25,000 67,500,000 - - 75.00 75.00 150.00 1,875,000 1,875,000 3,750,000 150.00 3,750,000 2,550.00 63,750,000
3 Quarterly Report (15 copies/ 3 Month)/district 900.0 75,000 67,500,000 900.0 75,000 67,500,000 452.00 14,680,060 - - - - - 452.00 14,680,060 448.00 52,819,940
4 Annual Report (15 copies/Year)/district 225.0 100,000 22,500,000 225.0 100,000 22,500,000 - - - - - - - - - 225.00 22,500,000
5 Special Report (15 copies/Years)/district 75.0 20,000 1,500,000 75.0 20,000 1,500,000 - - - - - - - - - 75.00 1,500,000
6 Draft Final Report (15 copies)/district 75.0 100,000 7,500,000 75.0 100,000 7,500,000 - - - - - - - - - 75.00 7,500,000
7 Final Report (15 copies)/district 75.0 100,000 7,500,000 75.0 100,000 7,500,000 - - - - - - - - - 75.00 7,500,000
8 MIS Input (5 copies/ 6 Month)/district 150.0 50,000 7,500,000 150.0 50,000 7,500,000 - - - - - - - - - 150.00 7,500,000
Sub total (B.IX) JAWA BARAT 185,250,000 185,250,000 14,680,060 1,875,000 1,875,000 3,750,000 18,430,060 166,819,940
1 Inceptions Report (15 copies)/district 30.0 50,000 1,500,000 30.0 50,000 1,500,000 - - - - - - - - 30.00 1,500,000
2 Monthly Report (15 copies/Month)/district 3 FY 1,080.0 25,000 27,000,000 1,080.0 25,000 27,000,000 107.00 3,830,550 30.00 30.00 60.00 750,000 750,000 1,500,000 167.00 5,330,550 913.00 21,669,450
3 Quarterly Report (15 copies/ 3 Month)/district 360.0 75,000 27,000,000 360.0 75,000 27,000,000 - - - - - - - - - 360.00 27,000,000
4 Annual Report (15 copies/Year)/district 90.0 100,000 9,000,000 90.0 100,000 9,000,000 - - - - - - - - - 90.00 9,000,000
5 Special Report (15 copies/Years)/district 30.0 20,000 600,000 30.0 20,000 600,000 - - - - - - - - - 30.00 600,000
6 Draft Final Report (15 copies)/district 30.0 100,000 3,000,000 30.0 100,000 3,000,000 - - - - - - - - - 30.00 3,000,000
7 Final Report (15 copies)/district 30.0 100,000 3,000,000 30.0 100,000 3,000,000 - - - - - - - - - 30.00 3,000,000
8 MIS Input (5 copies/ 6 Month)/district 60.0 50,000 3,000,000 60.0 50,000 3,000,000 - - - - - - - - - 60.00 3,000,000
9 Training Report (15 copies/reports) 120.0 50,000 6,000,000 - - - - - - - - - 120.00 6,000,000
10 Province Report
- Inception Report 15.0 50,000 750,000 - - - - - - - - - 15.00 750,000
- Monthly Report 180.0 25,000 4,500,000 15.00 375,000 15.00 15.00 30.00 375,000 375,000 750,000 45.00 1,125,000 135.00 3,375,000
- Quarterly Report 60.0 75,000 4,500,000 - - - - - - - - - 60.00 4,500,000
- Annual Report 15.0 100,000 1,500,000 - - - - - - - - - 15.00 1,500,000
Sub total (B.IX) BANTEN 74,100,000 91,350,000 4,205,550 1,125,000 1,125,000 2,250,000 6,455,550 84,894,450
Sub total (B.IX) JAWA BARAT + BANTEN 259,350,000 276,600,000 18,885,610 3,000,000 3,000,000 6,000,000 24,885,610 251,714,390
-
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
Copies
BALANCE
DESCRIPTION Mon Month Sub Total
BIMONTHLY INVOICEORIGINAL CONTRACT AMENDMENT 1
NOMOR : 06 BULAN : MEI 2010 & JUNI 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. May-10 Jun-10 Total May-10 Jun-10 Total Rp. Rp.
B.X OFFICE RENTAL & FURNITURE AND O & M
I. PROVINCIAL TEAM
36 2,500,000 90,000,000 36 2,500,000 90,000,000 10.00 25,000,000 1.00 1.00 2.00 2,500,000 2,500,000 5,000,000 12.00 30,000,000 24.00 60,000,000
II. DISTRICT
A. TASIKMALAYA
36 2,000,000 72,000,000 36 2,000,000 72,000,000 9.55 19,090,909 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 11.55 23,090,909 24.45 48,909,091
B. SUMEDANG
36 2,000,000 72,000,000 36 2,000,000 72,000,000 9.55 19,090,909 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 11.55 23,090,909 24.45 48,909,091
C. GARUT -
36 2,000,000 72,000,000 36 2,000,000 72,000,000 9.55 19,090,909 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 11.55 23,090,909 24.45 48,909,091
D. SUBANG
36 2,000,000 72,000,000 36 2,000,000 72,000,000 9.55 19,090,909 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 11.55 23,090,909 24.45 48,909,091
E. KUNINGAN -
36 2,000,000 72,000,000 36 2,000,000 72,000,000 9.55 19,090,909 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 11.55 23,090,909 24.45 48,909,091
F. SERANG
36 2,000,000 72,000,000 36 2,000,000 72,000,000 7.05 14,090,909 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 9.05 18,090,909 26.95 53,909,091
G. LEBAK
36 2,000,000 72,000,000 36 2,000,000 72,000,000 7.05 14,090,909 1.00 1.00 2.00 2,000,000 2,000,000 4,000,000 9.05 18,090,909 26.95 53,909,091
Sub total (B.X) JAWA BARAT + BANTEN 594,000,000 594,000,000 148,636,364 16,500,000 16,500,000 33,000,000 181,636,364 412,363,636
-
NOMOR : 06 BULAN : MEI 2010 & JUNI 2010
PREVIOUS THIS INVOICE UP TO THIS INVOICE
NO. Quantity Unit Total Quantity Unit Total Volume Total Volume Total Volume Total
Cost Rp. Cost Rp. Rp. May-10 Jun-10 Total May-10 Jun-10 Total Rp. Rp.
B.XI TRAINING
a. MIS Training for District Operators
a.1. Training Material (Asmandat + 7 Operator) 8 50,000 400,000 - - - - - - - - - 8.00 400,000
a.2. Consumption
Meals 4 x 8 persons 32 20,000 640,000 - - - - - - - - - 32.00 640,000
Snack 3 x 8 persons 24 7,500 180,000 - - - - - - - - - 24.00 180,000
b. Training for DMAC & District Facilitator Coordinator
b.1. Training Material (TL + FMS + 3 trainers + 14 DMAC + 7 DFC) 26 50,000 1,300,000 - - - - - - - - - 26.00 1,300,000
b.2. Comsumption (2 days training)
Meals 4 x 26 persons 104 20,000 2,080,000 - - - - - - - - - 104.00 2,080,000
Snack 3 x 26 persons 78 7,500 585,000 - - - - - - - - - 78.00 585,000
5,185,000 - - - - 5,185,000
5,524,250,000 5,833,285,000 1,444,883,788 132,443,561 171,064,960 303,508,521 1,748,392,309 4,084,892,691
C. 142,144,798 48,600,000 - - - - - 48,600,000
D. - 121,998 121,998
E. 103,363 - -
13,064,394,798 14,036,006,998 3,698,885,724 372,919,751 776,484,711 4,475,370,435 9,560,636,563
CONTINGENCIES
PROVISIONAL SUM
TOTAL A + B + C + D + E
Total B (REIMBURSABLE EXPENSES) JAWA BARAT + BANTEN
MANAGEMENT FEE
Office Rental, Furniture and O & M Years
ORIGINAL CONTRACT
Office Rental, Furniture and O & M Years
Office Rental, Furniture and O & M Years
BALANCEAMENDMENT 1
DESCRIPTION Mon Month Sub Total
BIMONTHLY INVOICE
Office Rental, Furniture and O & M Years
Office Rental, Furniture and O & M Years
Office Rental, Furniture and O & M Years
Office Rental, Furniture and O & M Years
DESCRIPTION Mon Month Sub Total
BIMONTHLY INVOICE
Office Rental, Furniture and O & M Years
BALANCEAMENDMENT 1ORIGINAL CONTRACT
PROVINCIAL MANAGEMENT ADVISORY CONSULTANT (PMAC) TO PROVINCIAL PROJECT MANAGEMENT UNIT (PPMU) JAWA BARAT DAN BANTEN (PAKET 9)
PENGEMBANGAN KINERJA PENGELOLAAN AIR MINUM JAWA BARAT
INVOICE NO. : 06 KONTRAK NO. : KU.08.08-PKPAM.JB/S-030BULAN : MEI 2010 - JUNI 2010 TANGGAL : 15 JUNI 2009
ORIGINAL AMENDMENT PREVIOUS THIS INVOICE UP TO THIS INVOICE BALANCENO. CONTRACT NO. 1
Rp. Rp. Rp. Rp. Rp. Rp.A. REMUNERATION
1 PROFESSIONAL STAFF 5,904,000,000 6,606,000,000 1,871,275,692 386,500,000 386,500,000 4,348,224,308
2 SUPPORTING STAFF 1,494,000,000 1,548,000,000 382,726,244 86,476,190 469,202,435 1,078,797,565 SUB TOTAL A. 7,398,000,000 8,154,000,000 2,254,001,936 472,976,190 855,702,435 5,427,021,874
B. REIMBURSABLE EXPENSES
1 MOBILIZATION / DEMOBILIZATION 7,300,000 7,900,000 3,950,000 - 3,950,000 3,950,000
2 HOUSING ALLOWANCE 439,200,000 463,200,000 123,454,545 26,000,000 149,454,545 313,745,455
3 DUTY TRAVEL 98,400,000 147,200,000 61,800,000 13,500,000 75,300,000 71,900,000
4 OUT OF STATION ALLOWANCE (OSA) 742,000,000 895,800,000 286,650,000 49,500,000 336,150,000 559,650,000
5 CAR RENTAL 2,160,000,000 2,160,000,000 538,636,364 120,000,000 658,636,364 1,501,363,636
6 OFFICE EQUIPMENTS 583,200,000 642,600,000 184,969,091 39,500,000 224,469,091 418,130,909
7 OFFICE COST 478,800,000 478,800,000 50,720,482 10,043,750 60,764,232 418,035,768
8 TELECOMMUNICATION 162,000,000 162,000,000 27,181,332 5,964,771 33,146,103 128,853,897
9 REPORTS 259,350,000 276,600,000 18,885,610 6,000,000 24,885,610 251,714,390
10 OFFICE RENTAL & FURNITURE AND O & M 594,000,000 594,000,000 148,636,364 33,000,000 181,636,364 412,363,636
11 TRAINING 5,185,000 - - - 5,185,000 SUB TOTAL B. 5,524,250,000 5,833,285,000 1,444,883,788 303,508,521 1,748,392,309 4,084,892,691 MANAGEMENT FEE 142,144,798 48,600,000 48,600,000 CONTINGENCIES 121,998 121,998 TOTAL 13,064,394,798 14,036,006,998 3,698,885,724 776,484,711 2,604,094,743 11,431,912,255
Pengembalian Uang Muka 996,069,000 996,069,000 996,069,000 - 996,069,000 - 12,068,325,798 13,039,937,998 2,702,816,724 776,484,711 1,608,025,743 11,431,912,255
PPN 10% 1,303,993,800 270,281,672 77,648,471 160,802,574 1,143,191,225 Total 14,343,931,798 2,973,098,396 854,133,183 1,768,828,318 12,575,103,480
Terbilang :
Pejabat Pembuat Komitment Pembangunan Jakarta, Mei 2010
Prasarana dan Sarana Air Minum Masyarakat PT. PERENTJANA DJAJA Berpenghasilan Rendah Satuan Kerja Pengembangan Kinerja Pengelolaan Air Minum Jawa Barat
Oscar R.H.Siagian,ST IR. BAMBANG H.WIKANTA,MM,MT NIP. 197505312002121001 DIREKTUR UTAMA
Ketut Ayu Ragil, ST.MT NIP.19781122200642001
REKAPITULASI
DESCRIPTION
Ketua Team Teknis Konsultan