Microsoft Office Project - PEMBANGUNAN JALAN R3 SECTION II (Network Planning)
-
Upload
yurisdal-bowie-azwan -
Category
Documents
-
view
215 -
download
0
Transcript of Microsoft Office Project - PEMBANGUNAN JALAN R3 SECTION II (Network Planning)
-
7/24/2019 Microsoft Office Project - PEMBANGUNAN JALAN R3 SECTION II (Network Planning)
1/3
Pek. Pengukuran Site
Start: 13/06/14 ID: 3
Finish: 23/06/14 Dur: 7 days
Res:
Pek. Mobilisasi dan Demobili
Start: 16/06/14 ID: 4
Finish: 03/07/14 Dur: 14 days
Res:
Pek. Direksi keet
Start: 16/06/14 ID: 5
Finish: 24/06/14 Dur: 7 days
Res:
Pek. Los Kerja/bahan
Start: 25/06/14 ID: 6
Finish: 03/07/14 Dur: 7 days
Res:
Pek. Papan Nama Proyek
Start: 17/06/14 ID: 7
Finish: 25/06/14 Dur: 7 days
Res:
Pek. Bouplank 3x pakai
Start: 18/06/14 ID: 8
Finish: 07/07/14 Dur: 14 days
Res:
Pek. Pengaturan lalu lintas d
Start: 16/06/14 ID: 9
Finish: 03/07/14 Dur: 14 days
Res:
Pek. Kisdam
Start: 25/06/14 ID: 10
Finish: 03/07/14 Dur: 7 days
Res:
Pek. Pembersihan Damija
Start: 25/06/14 ID: 11
Finish: 03/07/14 Dur: 7 days
Res:
Pek. Pembersihan Saluran
Start: 25/06/14 ID: 12
Finish: 03/07/14 Dur: 7 days
Res:
Pek. Pasangan bata
Start: 27/06/14 ID: 14
Finish: 07/08/14 Dur: 30 days
Res:
Pek. Plesteran + acian t=1,5 c
Start: 27/06/14 ID: 15
Finish: 07/08/14 Dur: 30 days
Res:
Pek. Saluran pipa beton bert
Start: 17/07/14 ID: 16
Finish: 25/07/14 Dur: 7 days
Res:
Pek. Siar dalam batu belah (a
Start: 24/07/14 ID: 17
Finish: 03/09/14 Dur: 30 days
Res:
Pek. Drainase Buis Beton Bu
Start: 28/07/14 ID: 18
Finish: 14/08/14 Dur: 14 days
Res:
Pek. Drainase Buis Beton Bu
Start: 28/07/14 ID: 19
Finish: 14/08/14 Dur: 14 days
Res:
Pek. Saluran Drainase Beton
Start: 22/07/14 ID: 20
Finish: 15/09/14 Dur: 40 days
Res:
Pek. Saluran pipa beton bert
Start: 22/07/14 ID: 21
Finish: 30/07/14 Dur: 7 days
Res:
DIVISI 3. PEKERJAAN TAN
Start: 19/06/14 ID: 22
Finish: 19/11/14 Dur: 110 days
Comp: 0%
Pek. Galian Tanah
Start: 19/06/14 ID: 23
Finish: 30/07/14 Dur: 30 days
Res:
Pek. Urugan tanah kembali b
Start: 16/09/14 ID: 24
Finish: 10/11/14 Dur: 40 days
Res:
Pek. Penyiapan badan jalan
Start: 31/10/14 ID: 25
Finish: 11/11/14 Dur: 8 days
Res:
Pek. Buangan tanah bekas g
Start: 11/11/14 ID: 26
Finish: 19/11/14 Dur: 7 daysRes:
DIVISI 5. PERKERASAN BE
Start: 23/10/14 ID: 27
Finish: 11/11/14 Dur: 14 days
Comp: 0%
Pek. Limestone tebal 30 cm
Start: 23/10/14 ID: 28
Finish: 11/11/14 Dur: 14 days
Res:
DIVISI 7. STRUKTUR
Start: 31/07/14 ID: 29
Finish: 05/03/15 Dur: 156 days
Comp: 0%
Pek. Beton K-250 (Ready mix
Start: 05/09/14 ID: 31
Finish: 16/09/14 Dur: 7 days
Res:
Pek. Beton K-225 (Ready mix
Start: 31/07/14 ID: 32
Finish: 24/09/14 Dur: 40 days
Res:
Pek. Besi tulangan ulir U32
Start: 27/08/14 ID: 37
Finish: 05/09/14 Dur: 7 days
Res:
Pek. Ceruc
Start: 12/11/1
Finish: 20/11/
Res:
Pek. Pasan
Start: 12/11/1
Finish: 01/12/
Res:
DIVISI 8. PEKERJAAN MIN
Start: 06/02/15 ID: 44
Finish: 19/03/15 Dur: 30 days
Comp: 0%
PEMBANGUNAN JALAN R3 S
Start: 13/06/14 ID: 1
Finish: 19/03/15 Dur: 200 days
Comp: 0%
DIVISI 1. UMUM
Start: 13/06/14 ID: 2
Finish: 07/07/14 Dur: 17 days
Comp: 0%
DIVISI 2. DRAINASE
Start: 27/06/14 ID: 13
Finish: 15/09/14 Dur: 57 days
Comp: 0%
Page 1
-
7/24/2019 Microsoft Office Project - PEMBANGUNAN JALAN R3 SECTION II (Network Planning)
2/3
Pek. Beton K-225 (site mix) ti
Start: 05/02/15 ID: 30
Finish: 16/02/15 Dur: 7 days
Res:
Pek. Beton Sikloop
Start: 21/11/14 ID: 33
Finish: 01/12/14 Dur: 7 days
Res:
Pek. Lantai kerja Ready mix
Start: 26/11/14 ID: 34
Finish: 04/12/14 Dur: 7 daysRes:
Pek. Bekisting (2x pakai)
Start: 29/01/15 ID: 35
Finish: 06/02/15 Dur: 7 days
Res:
Pek. Besi tulangan polos U2
Start: 28/11/14 ID: 36
Finish: 05/02/15 Dur: 50 days
Res:
uk dolken + 7 cm
1 4 I D: 3 8
14 Dur: 7 days
gan batu belah 1
1 4 I D: 3 9
14 Dur: 14 days
Pek. Sandaran (railing) pipa g
Start: 16/02/15 ID: 40
Finish: 24/02/15 Dur: 7 days
Res:
Pek. Bongkaran pas. batu
Start: 25/02/15 ID: 41
Finish: 05/03/15 Dur: 7 days
Res:
Pek. Beton Struktur FS-45 Tb
Start: 06/02/15 ID: 42
Finish: 13/02/15 Dur: 6 days
Res:
Pek. Wet lean concrete tebal
Start: 26/11/14 ID: 43
Finish: 04/12/14 Dur: 7 days
Res:
Pek. Kerb pracetak ukuran 60
Start: 06/02/15 ID: 45
Finish: 16/02/15 Dur: 7 days
Res:
Pek. Kerb inlet pracetak ukur
Start: 06/02/15 ID: 46
Finish: 25/02/15 Dur: 14 days
Res:
Pek. Pengecatan tiang railin
Start: 11/03/15 ID: 47
Finish: 19/03/15 Dur: 7 days
Res:
Page 2
-
7/24/2019 Microsoft Office Project - PEMBANGUNAN JALAN R3 SECTION II (Network Planning)
3/3
Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
Page 3
Project: PEMBANGUNAN JALAN R3 SDate: Tue 15/04/14