Microsoft Office Project - PEMBANGUNAN JALAN R3 SECTION II (Network Planning)

download Microsoft Office Project - PEMBANGUNAN JALAN R3 SECTION II (Network Planning)

of 3

Transcript of Microsoft Office Project - PEMBANGUNAN JALAN R3 SECTION II (Network Planning)

  • 7/24/2019 Microsoft Office Project - PEMBANGUNAN JALAN R3 SECTION II (Network Planning)

    1/3

    Pek. Pengukuran Site

    Start: 13/06/14 ID: 3

    Finish: 23/06/14 Dur: 7 days

    Res:

    Pek. Mobilisasi dan Demobili

    Start: 16/06/14 ID: 4

    Finish: 03/07/14 Dur: 14 days

    Res:

    Pek. Direksi keet

    Start: 16/06/14 ID: 5

    Finish: 24/06/14 Dur: 7 days

    Res:

    Pek. Los Kerja/bahan

    Start: 25/06/14 ID: 6

    Finish: 03/07/14 Dur: 7 days

    Res:

    Pek. Papan Nama Proyek

    Start: 17/06/14 ID: 7

    Finish: 25/06/14 Dur: 7 days

    Res:

    Pek. Bouplank 3x pakai

    Start: 18/06/14 ID: 8

    Finish: 07/07/14 Dur: 14 days

    Res:

    Pek. Pengaturan lalu lintas d

    Start: 16/06/14 ID: 9

    Finish: 03/07/14 Dur: 14 days

    Res:

    Pek. Kisdam

    Start: 25/06/14 ID: 10

    Finish: 03/07/14 Dur: 7 days

    Res:

    Pek. Pembersihan Damija

    Start: 25/06/14 ID: 11

    Finish: 03/07/14 Dur: 7 days

    Res:

    Pek. Pembersihan Saluran

    Start: 25/06/14 ID: 12

    Finish: 03/07/14 Dur: 7 days

    Res:

    Pek. Pasangan bata

    Start: 27/06/14 ID: 14

    Finish: 07/08/14 Dur: 30 days

    Res:

    Pek. Plesteran + acian t=1,5 c

    Start: 27/06/14 ID: 15

    Finish: 07/08/14 Dur: 30 days

    Res:

    Pek. Saluran pipa beton bert

    Start: 17/07/14 ID: 16

    Finish: 25/07/14 Dur: 7 days

    Res:

    Pek. Siar dalam batu belah (a

    Start: 24/07/14 ID: 17

    Finish: 03/09/14 Dur: 30 days

    Res:

    Pek. Drainase Buis Beton Bu

    Start: 28/07/14 ID: 18

    Finish: 14/08/14 Dur: 14 days

    Res:

    Pek. Drainase Buis Beton Bu

    Start: 28/07/14 ID: 19

    Finish: 14/08/14 Dur: 14 days

    Res:

    Pek. Saluran Drainase Beton

    Start: 22/07/14 ID: 20

    Finish: 15/09/14 Dur: 40 days

    Res:

    Pek. Saluran pipa beton bert

    Start: 22/07/14 ID: 21

    Finish: 30/07/14 Dur: 7 days

    Res:

    DIVISI 3. PEKERJAAN TAN

    Start: 19/06/14 ID: 22

    Finish: 19/11/14 Dur: 110 days

    Comp: 0%

    Pek. Galian Tanah

    Start: 19/06/14 ID: 23

    Finish: 30/07/14 Dur: 30 days

    Res:

    Pek. Urugan tanah kembali b

    Start: 16/09/14 ID: 24

    Finish: 10/11/14 Dur: 40 days

    Res:

    Pek. Penyiapan badan jalan

    Start: 31/10/14 ID: 25

    Finish: 11/11/14 Dur: 8 days

    Res:

    Pek. Buangan tanah bekas g

    Start: 11/11/14 ID: 26

    Finish: 19/11/14 Dur: 7 daysRes:

    DIVISI 5. PERKERASAN BE

    Start: 23/10/14 ID: 27

    Finish: 11/11/14 Dur: 14 days

    Comp: 0%

    Pek. Limestone tebal 30 cm

    Start: 23/10/14 ID: 28

    Finish: 11/11/14 Dur: 14 days

    Res:

    DIVISI 7. STRUKTUR

    Start: 31/07/14 ID: 29

    Finish: 05/03/15 Dur: 156 days

    Comp: 0%

    Pek. Beton K-250 (Ready mix

    Start: 05/09/14 ID: 31

    Finish: 16/09/14 Dur: 7 days

    Res:

    Pek. Beton K-225 (Ready mix

    Start: 31/07/14 ID: 32

    Finish: 24/09/14 Dur: 40 days

    Res:

    Pek. Besi tulangan ulir U32

    Start: 27/08/14 ID: 37

    Finish: 05/09/14 Dur: 7 days

    Res:

    Pek. Ceruc

    Start: 12/11/1

    Finish: 20/11/

    Res:

    Pek. Pasan

    Start: 12/11/1

    Finish: 01/12/

    Res:

    DIVISI 8. PEKERJAAN MIN

    Start: 06/02/15 ID: 44

    Finish: 19/03/15 Dur: 30 days

    Comp: 0%

    PEMBANGUNAN JALAN R3 S

    Start: 13/06/14 ID: 1

    Finish: 19/03/15 Dur: 200 days

    Comp: 0%

    DIVISI 1. UMUM

    Start: 13/06/14 ID: 2

    Finish: 07/07/14 Dur: 17 days

    Comp: 0%

    DIVISI 2. DRAINASE

    Start: 27/06/14 ID: 13

    Finish: 15/09/14 Dur: 57 days

    Comp: 0%

    Page 1

  • 7/24/2019 Microsoft Office Project - PEMBANGUNAN JALAN R3 SECTION II (Network Planning)

    2/3

    Pek. Beton K-225 (site mix) ti

    Start: 05/02/15 ID: 30

    Finish: 16/02/15 Dur: 7 days

    Res:

    Pek. Beton Sikloop

    Start: 21/11/14 ID: 33

    Finish: 01/12/14 Dur: 7 days

    Res:

    Pek. Lantai kerja Ready mix

    Start: 26/11/14 ID: 34

    Finish: 04/12/14 Dur: 7 daysRes:

    Pek. Bekisting (2x pakai)

    Start: 29/01/15 ID: 35

    Finish: 06/02/15 Dur: 7 days

    Res:

    Pek. Besi tulangan polos U2

    Start: 28/11/14 ID: 36

    Finish: 05/02/15 Dur: 50 days

    Res:

    uk dolken + 7 cm

    1 4 I D: 3 8

    14 Dur: 7 days

    gan batu belah 1

    1 4 I D: 3 9

    14 Dur: 14 days

    Pek. Sandaran (railing) pipa g

    Start: 16/02/15 ID: 40

    Finish: 24/02/15 Dur: 7 days

    Res:

    Pek. Bongkaran pas. batu

    Start: 25/02/15 ID: 41

    Finish: 05/03/15 Dur: 7 days

    Res:

    Pek. Beton Struktur FS-45 Tb

    Start: 06/02/15 ID: 42

    Finish: 13/02/15 Dur: 6 days

    Res:

    Pek. Wet lean concrete tebal

    Start: 26/11/14 ID: 43

    Finish: 04/12/14 Dur: 7 days

    Res:

    Pek. Kerb pracetak ukuran 60

    Start: 06/02/15 ID: 45

    Finish: 16/02/15 Dur: 7 days

    Res:

    Pek. Kerb inlet pracetak ukur

    Start: 06/02/15 ID: 46

    Finish: 25/02/15 Dur: 14 days

    Res:

    Pek. Pengecatan tiang railin

    Start: 11/03/15 ID: 47

    Finish: 19/03/15 Dur: 7 days

    Res:

    Page 2

  • 7/24/2019 Microsoft Office Project - PEMBANGUNAN JALAN R3 SECTION II (Network Planning)

    3/3

    Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical

    Page 3

    Project: PEMBANGUNAN JALAN R3 SDate: Tue 15/04/14