M.2.1LAPORAN KEMAJUAN PEKERJAANMINGGU KE :2 (DUA)PERIODE :06 AGUSTUS 2014 S/D 13 AGUSTUS 2014PEKERJAAN:PEMASANGAN PIPANISASI AIR BERSIH GP. ALUE RINDANG KEC. SEULIMEUM (DAU)PROGRESS1.55%LOKASI:KEC. SEULIMEUMKONTRAKTOR PELAKSANA:CV. TUAH BARUSARENCANAJANGKA WAKTU PELAKSANAAN:90 HariNO. KONTRAK:26/SPK/PL.P-PERKIM/BMCK/2014PROGRESS2.24%NILAI KONTRAK AWAL:Rp79,609,000TANGGAL KONTRAK:06 AGUSTUS 2014ACTUAL8/6/14SUMBER DANA:APBKKONSULTAN PENGAWAS:CV. SCALA DESIGNDEVIASI0.69%8/12/14TAHUNANGGARAN:2014NO. KONTRAK:8/18/14TANGGAL KONTRAK:ADVANCEON PROGRESSON PROGRESSON PROGRESS8/24/14DELAYEDON PROGRESSON PROGRESSON PROGRESS8/30/14NO.URAIANSAT.KONTRAK AWALMINGGU LALUMINGGU INIREALISASI PEKER. S/D MINGGU INIKET.9/5/149/11/14QTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotPrestasi9/17/14( Rp. )( % )( Rp. )( % )(Rp.)( % )( Rp. )( % )(%)9/23/14abcdefghijklm =(g+j)n =(h+k)o =(i+l)pq9/29/14IPEKERJAAN PERSIAPAN10/5/14$1Direksi Keet / Gudang (Sewa)Ls1.00Rp390,000.000.540.00.00.01.00Rp390,000.000.541.00Rp390,000.000.54100.00COMPLETED$2Papan Nama Proyek dan Rambu -RambuLs1.00Rp280,000.000.390.00.00.01.00Rp280,000.000.391.00Rp280,000.000.39100.00COMPLETED$3PembersihanLs1.00Rp450,000.000.620.00.00.01.00Rp450,000.000.621.00Rp450,000.000.62100.00COMPLETED$4Pematokan/pengukuran (setting out)Ls1.00Rp500,000.000.690.00.00.01.00Rp500,000.000.691.00Rp500,000.000.69100.00COMPLETED$5Mobilisasi dan DemobilisasiLs1.00Rp250,000.000.350.00.00.00.00.00.00.00.00.00.0DELAYEDRp1,620,000.00Rp2,870,000.00$6Administrasi Dokumentasi dan as built drawingLs1.00Rp1,000,000.001.380.00.00.00.00.00.00.00.00.00.0DELAYED0.0Rp48,251,993.000.00.0Rp15,215,649.88IIPENGADAAN PIPA DAN ACCESSORIES0.00.0Rp3,459,396.28$1Pengadaan Pipa0.0Rp2,574,832.02-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp33,734,800.0046.610.00.00.00.00.00.00.00.00.00.0DELAYEDRp72,371,871.18-Pipa GIP dia.100 mmPipa GIP dia.100 mmM'12.00Rp2,640,000.003.650.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.50 mmPipa GIP dia.50 mmM'5.00Rp620,000.000.860.00.00.00.00.00.00.00.00.00.0DELAYED$2Pengadaan Accessories-Bend All Socket PVC RRJ Dia. 100 x 90bh2.00Rp316,000.000.440.00.00.00.00.00.00.00.00.00.0DELAYED-Bend All Socket PVC RRJ Dia. 100 x 45bh1.00Rp145,300.000.200.00.00.00.00.00.00.00.00.00.0DELAYED-Flange Socket PVC RRJ Dia. 100 mmbh7.00Rp4,092,018.005.650.00.00.00.00.00.00.00.00.00.0DELAYED-Flange Socket PVC RRJ Dia. 50 mmbh2.00Rp349,000.000.480.00.00.00.00.00.00.00.00.00.0DELAYED-Tee All socket Dia 100 x 100 mmbh1.00Rp303,300.000.420.00.00.00.00.00.00.00.00.00.0DELAYED-Reducer Socket Dia 100 x 50 mmbh1.00Rp112,850.000.160.00.00.00.00.00.00.00.00.00.0DELAYED-Bend All Socket PVC RRJ Dia. 50 x 90bh1.00Rp50,550.000.070.00.00.00.00.00.00.00.00.00.0DELAYED-Dop PVC dia.100 mmbh1.00Rp171,175.000.240.00.00.00.00.00.00.00.00.00.0DELAYED-Bend GIP Dia 100 x 90 mmbh1.00Rp180,000.000.250.00.00.00.00.00.00.00.00.00.0DELAYED-Bend GIP Dia 100 x 45 mmbh4.00Rp620,000.000.860.00.00.00.00.00.00.00.00.00.0DELAYED-Bend GIP Dia 50 x 90 mmbh2.00Rp190,000.000.260.00.00.00.00.00.00.00.00.00.0DELAYED-Loss Flange GIP Dia 100 mmbh5.00Rp560,000.000.770.00.00.00.00.00.00.00.00.00.0DELAYED-Loss Flange GIP Dia 50 mmbh2.00Rp162,000.000.220.00.00.00.00.00.00.00.00.00.0DELAYED-Tee Gip 100 x 50 mmbh1.00Rp215,000.000.300.00.00.00.00.00.00.00.00.00.0DELAYED-Gate Valve 4"bh2.00Rp3,000,000.004.150.00.00.00.00.00.00.00.00.00.0DELAYED-Saringan/Besi Dia 4 "bh1.00Rp75,000.000.100.00.00.00.00.00.00.00.00.00.0DELAYED-Bautbh80.00Rp600,000.000.830.00.00.00.00.00.00.00.00.00.0DELAYED-Pakingbh10.00Rp115,000.000.160.00.00.00.00.00.00.00.00.00.0DELAYEDIIIPEKERJAAN PEMASANGAN PIPA DAN ACESSORIES$1Pekerjaan Tanah-Galian Tanah KerasM3108.24Rp4,663,520.406.440.00.00.00.00.00.00.00.00.00.0DELAYED108.24430854663520.4-Urugan KembaliM3104.60Rp1,384,062.571.910.00.00.00.00.00.00.00.00.00.0DELAYED104.59965132321384062.5688$2Pemasangan Pipa Termasuk Fitting dan Valve-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp8,392,208.0011.600.00.00.00.00.00.00.00.00.00.0DELAYED451186088392208-Pipa GIP dia.100 mmM'12.00Rp572,425.150.790.00.00.00.00.00.00.00.00.00.0DELAYED1247702.1572425.2-Pipa GIP dia.50 mmM'5.00Rp130,904.600.180.00.00.00.00.00.00.00.00.00.0DELAYED526180.92130904.6-Pengecatan permukaan baja secara manual sistem 2 lapisM24.55Rp72,529.150.100.00.00.00.00.00.00.00.00.00.0DELAYED4.55315929.9772529.1534115215649.92221IVPEKERJAAN LAIN-LAIN$1Crossing Pipa/ BoringM'6.00Rp900,000.001.240.00.00.00.00.00.00.00.00.00.0DELAYED$2Rekondisi Jalan/FinishingLs1.00Rp200,000.000.280.00.00.00.00.00.00.00.00.00.0DELAYED$3Rekondisi Jalan (Rabat Beton)M30.02Rp9,396.280.010.00.00.00.00.00.00.00.00.00.0DELAYED$4Uji Laboratorium Baku Mutu Kualitas Air BersihLs1.00Rp750,000.001.040.00.00.00.00.00.00.00.00.00.0DELAYED$5Street BoxLs2.00Rp1,600,000.002.210.00.00.00.00.00.00.00.00.00.0DELAYEDVPEKERJAAN REHAP INTAKE$1PEKERJAAN TANAH & PONDASIGalian Tanah PondasiM31.00Rp4,589.550.010.00.00.00.00.00.00.00.00.00.0DELAYEDUrugan Pasir Bawah PondasiM30.02Rp1,713.120.000.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu Gunung 1 : 3M31.00Rp277,037.340.380.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu KosongM32.00Rp6,419.820.010.00.00.00.00.00.00.00.00.00.0DELAYEDTanah TimbunanM31.00Rp1,088,542.181.500.00.00.00.00.00.00.00.00.00.0DELAYEDLantai Beton Cor 1Pc : 1,5Ps : 2,5Kr, T=10 cmM30.02Rp966,777.351.340.00.00.00.00.00.00.00.00.00.0DELAYEDPlasteran 1pc : 2 psM21.00Rp229,752.660.320.00.00.00.00.00.00.00.00.00.0DELAYEDJUMLAHRp72,371,871.18100.000.00.00Rp1,620,000.0002.24Rp1,620,000.002.24SISA PROGRESSPPn10%Rp7,237,187.120.0Rp162,000.000Rp162,000.00GRAND TOTALRp79,609,058.300.0Rp1,782,000.000Rp1,782,000.0097.76%DIBULATKANRp79,609,000.000.0Rp1,782,000.00Rp1,782,000.00Disetujui Oleh :Diperiksa Oleh :Dibuat Oleh :Pejabat Pelaksana Teknis Kegiatan (PPTK)Konsultan SupervisiKontraktor PelaksanaDinas Cipta Karya Aceh BesarCV. SCALA DESIGNCV. TUAH BARUSAMUHAMMAD IKHSAN,ST.MTHERI DERMAWAN,STIRSANNIP. 19740407 200212 1 007InspectorDirektur

M.2.1 (2)LAPORAN KEMAJUAN PEKERJAANMINGGU KE :2 (DUA)PERIODE :14 AGUSTUS 2014 S/D 20 AGUSTUS 2014PEKERJAAN:PEMASANGAN PIPANISASI AIR BERSIH GP. ALUE RINDANG KEC. SEULIMEUM (DAU)PROGRESS4.03%LOKASI:KEC. SEULIMEUMKONTRAKTOR PELAKSANA:CV. TUAH BARUSARENCANAJANGKA WAKTU PELAKSANAAN:90 HariNO. KONTRAK:26/SPK/PL.P-PERKIM/BMCK/2014PROGRESS3.27%NILAI KONTRAK AWAL:Rp79,609,000TANGGAL KONTRAK:06 AGUSTUS 2014ACTUALSUMBER DANA:APBKKONSULTAN PENGAWAS:CV. SCALA DESIGNDEVIASI-0.76%TAHUNANGGARAN:2014NO. KONTRAK:0.0TANGGAL KONTRAK:0.0DELAYEDON PROGRESSON PROGRESSON PROGRESSDELAYEDON PROGRESSON PROGRESSON PROGRESSNO.URAIANSAT.KONTRAK AWALMINGGU LALUMINGGU INIREALISASI PEKER. S/D MINGGU INIKET.QTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotPrestasi( Rp. )( % )( Rp. )( % )(Rp.)( % )( Rp. )( % )(%)abcdefghijklm =(g+j)n =(h+k)o =(i+l)pqIPEKERJAAN PERSIAPAN$1Direksi Keet / Gudang (Sewa)Ls1.00Rp390,000.000.541.00Rp390,000.000.540.00.00.01.00Rp390,000.000.54100.00COMPLETED$2Papan Nama Proyek dan Rambu -RambuLs1.00Rp280,000.000.391.00Rp280,000.000.390.00.00.01.00Rp280,000.000.39100.00COMPLETED$3PembersihanLs1.00Rp450,000.000.621.00Rp450,000.000.620.00.00.01.00Rp450,000.000.62100.00COMPLETED$4Pematokan/pengukuran (setting out)Ls1.00Rp500,000.000.691.00Rp500,000.000.690.00.00.01.00Rp500,000.000.69100.00COMPLETED$5Mobilisasi dan DemobilisasiLs1.00Rp250,000.000.350.00.00.01.00Rp250,000.000.351.00Rp250,000.000.35100.00COMPLETED$6Administrasi Dokumentasi dan as built drawingLs1.00Rp1,000,000.001.380.00.00.00.50Rp500,000.000.690.50Rp500,000.000.6950.00ON PROGRESSIIPENGADAAN PIPA DAN ACCESSORIES$1Pengadaan PipaPengadaan Pipa-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp33,734,800.0046.610.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.100 mmPipa GIP dia.100 mmM'12.00Rp2,640,000.003.650.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.50 mmPipa GIP dia.50 mmM'5.00Rp620,000.000.860.00.00.00.00.00.00.00.00.00.0DELAYED$2Pengadaan Accessories-Bend All Socket PVC RRJ Dia. 100 x 90bh2.00Rp316,000.000.440.00.00.00.00.00.00.00.00.00.0DELAYED-Bend All Socket PVC RRJ Dia. 100 x 45bh1.00Rp145,300.000.200.00.00.00.00.00.00.00.00.00.0DELAYED-Flange Socket PVC RRJ Dia. 100 mmbh7.00Rp4,092,018.005.650.00.00.00.00.00.00.00.00.00.0DELAYED-Flange Socket PVC RRJ Dia. 50 mmbh2.00Rp349,000.000.480.00.00.00.00.00.00.00.00.00.0DELAYED-Tee All socket Dia 100 x 100 mmbh1.00Rp303,300.000.420.00.00.00.00.00.00.00.00.00.0DELAYED-Reducer Socket Dia 100 x 50 mmbh1.00Rp112,850.000.160.00.00.00.00.00.00.00.00.00.0DELAYED-Bend All Socket PVC RRJ Dia. 50 x 90bh1.00Rp50,550.000.070.00.00.00.00.00.00.00.00.00.0DELAYED-Dop PVC dia.100 mmbh1.00Rp171,175.000.240.00.00.00.00.00.00.00.00.00.0DELAYED-Bend GIP Dia 100 x 90 mmbh1.00Rp180,000.000.250.00.00.00.00.00.00.00.00.00.0DELAYED-Bend GIP Dia 100 x 45 mmbh4.00Rp620,000.000.860.00.00.00.00.00.00.00.00.00.0DELAYED-Bend GIP Dia 50 x 90 mmbh2.00Rp190,000.000.260.00.00.00.00.00.00.00.00.00.0DELAYED-Loss Flange GIP Dia 100 mmbh5.00Rp560,000.000.770.00.00.00.00.00.00.00.00.00.0DELAYED-Loss Flange GIP Dia 50 mmbh2.00Rp162,000.000.220.00.00.00.00.00.00.00.00.00.0DELAYED-Tee Gip 100 x 50 mmbh1.00Rp215,000.000.300.00.00.00.00.00.00.00.00.00.0DELAYED-Gate Valve 4"bh2.00Rp3,000,000.004.150.00.00.00.00.00.00.00.00.00.0DELAYED-Saringan/Besi Dia 4 "bh1.00Rp75,000.000.100.00.00.00.00.00.00.00.00.00.0DELAYED-Bautbh80.00Rp600,000.000.830.00.00.00.00.00.00.00.00.00.0DELAYED-Pakingbh10.00Rp115,000.000.160.00.00.00.00.00.00.00.00.00.0DELAYEDIIIPEKERJAAN PEMASANGAN PIPA DAN ACESSORIES$1Pekerjaan Tanah-Galian Tanah KerasM3108.24Rp4,663,520.406.440.00.00.00.00.00.00.00.00.00.0DELAYED-Urugan KembaliM3104.60Rp1,384,062.571.910.00.00.00.00.00.00.00.00.00.0DELAYED$2Pemasangan Pipa Termasuk Fitting dan Valve-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp8,392,208.0011.600.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.100 mmM'12.00Rp572,425.150.790.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.50 mmM'5.00Rp130,904.600.180.00.00.00.00.00.00.00.00.00.0DELAYED-Pengecatan permukaan baja secara manual sistem 2 lapisM24.55Rp72,529.150.100.00.00.00.00.00.00.00.00.00.0DELAYEDIVPEKERJAAN LAIN-LAIN$1Crossing Pipa/ BoringM'6.00Rp900,000.001.240.00.00.00.00.00.00.00.00.00.0DELAYED$2Rekondisi Jalan/FinishingLs1.00Rp200,000.000.280.00.00.00.00.00.00.00.00.00.0DELAYED$3Rekondisi Jalan (Rabat Beton)M30.02Rp9,396.280.010.00.00.00.00.00.00.00.00.00.0DELAYED$4Uji Laboratorium Baku Mutu Kualitas Air BersihLs1.00Rp750,000.001.040.00.00.00.00.00.00.00.00.00.0DELAYED$5Street BoxLs2.00Rp1,600,000.002.210.00.00.00.00.00.00.00.00.00.0DELAYEDVPEKERJAAN REHAP INTAKE$1PEKERJAAN TANAH & PONDASIGalian Tanah PondasiM31.00Rp4,589.550.010.00.00.00.00.00.00.00.00.00.0DELAYEDUrugan Pasir Bawah PondasiM30.02Rp1,713.120.000.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu Gunung 1 : 3M31.00Rp277,037.340.380.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu KosongM32.00Rp6,419.820.010.00.00.00.00.00.00.00.00.00.0DELAYEDTanah TimbunanM31.00Rp1,088,542.181.500.00.00.00.00.00.00.00.00.00.0DELAYEDLantai Beton Cor 1Pc : 1,5Ps : 2,5Kr, T=10 cmM30.02Rp966,777.351.340.00.00.00.00.00.00.00.00.00.0DELAYEDPlasteran 1pc : 2 psM21.00Rp229,752.660.320.00.00.00.00.00.00.00.00.00.0DELAYEDJUMLAHRp72,371,871.18100.00Rp1,620,000.002.24Rp750,000.0001.04Rp2,370,000.003.27SISA PROGRESSPPn10%Rp7,237,187.12Rp162,000.00Rp75,000.000Rp237,000.00GRAND TOTALRp79,609,058.30Rp1,782,000.00Rp825,000.000Rp2,607,000.0096.73%DIBULATKANRp79,609,000.00Rp1,782,000.00Rp825,000.00Rp2,607,000.00Disetujui Oleh :Diperiksa Oleh :Dibuat Oleh :Pejabat Pelaksana Teknis Kegiatan (PPTK)Konsultan SupervisiKontraktor PelaksanaDinas Cipta Karya Aceh BesarCV. SCALA DESIGNCV. TUAH BARUSAMUHAMMAD IKHSAN,ST.MTHERI DERMAWAN,STIRSANNIP. 19740407 200212 1 007InspectorDirektur

M.2.1 (3)LAPORAN KEMAJUAN PEKERJAANMINGGU KE :2 (DUA)PERIODE :21 AGUSTUS 2014 S/D 31 AGUSTUS 2014PEKERJAAN:PEMASANGAN PIPANISASI AIR BERSIH GP. ALUE RINDANG KEC. SEULIMEUM (DAU)PROGRESS27.32%LOKASI:KEC. SEULIMEUMKONTRAKTOR PELAKSANA:CV. TUAH BARUSARENCANAJANGKA WAKTU PELAKSANAAN:90 HariNO. KONTRAK:26/SPK/PL.P-PERKIM/BMCK/2014PROGRESS26.58%NILAI KONTRAK AWAL:Rp79,609,000TANGGAL KONTRAK:06 AGUSTUS 2014ACTUALSUMBER DANA:APBKKONSULTAN PENGAWAS:CV. SCALA DESIGNDEVIASI-0.74%TAHUNANGGARAN:2014NO. KONTRAK:0.0TANGGAL KONTRAK:0.0DELAYEDON PROGRESSON PROGRESSON PROGRESSDELAYEDON PROGRESSON PROGRESSON PROGRESSNO.URAIANSAT.KONTRAK AWALMINGGU LALUMINGGU INIREALISASI PEKER. S/D MINGGU INIKET.QTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotPrestasi( Rp. )( % )( Rp. )( % )(Rp.)( % )( Rp. )( % )(%)abcdefghijklm =(g+j)n =(h+k)o =(i+l)pqIPEKERJAAN PERSIAPAN$1Direksi Keet / Gudang (Sewa)Ls1.00Rp390,000.000.541.00Rp390,000.000.540.00.00.01.00Rp390,000.000.54100.00COMPLETED$2Papan Nama Proyek dan Rambu -RambuLs1.00Rp280,000.000.391.00Rp280,000.000.390.00.00.01.00Rp280,000.000.39100.00COMPLETED$3PembersihanLs1.00Rp450,000.000.621.00Rp450,000.000.620.00.00.01.00Rp450,000.000.62100.00COMPLETED$4Pematokan/pengukuran (setting out)Ls1.00Rp500,000.000.691.00Rp500,000.000.690.00.00.01.00Rp500,000.000.69100.00COMPLETED$5Mobilisasi dan DemobilisasiLs1.00Rp250,000.000.351.00Rp250,000.000.350.00.00.01.00Rp250,000.000.35100.00COMPLETED$6Administrasi Dokumentasi dan as built drawingLs1.00Rp1,000,000.001.380.50Rp500,000.000.690.00.00.00.50Rp500,000.000.6950.00ON PROGRESSIIPENGADAAN PIPA DAN ACCESSORIES$1Pengadaan PipaPengadaan Pipa-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp33,734,800.0046.610.00.00.0225.50Rp16,867,400.0023.31225.50Rp16,867,400.0023.3150.00ON PROGRESS-Pipa GIP dia.100 mmPipa GIP dia.100 mmM'12.00Rp2,640,000.003.650.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.50 mmPipa GIP dia.50 mmM'5.00Rp620,000.000.860.00.00.00.00.00.00.00.00.00.0DELAYED$2Pengadaan Accessories-Bend All Socket PVC RRJ Dia. 100 x 90bh2.00Rp316,000.000.440.00.00.00.00.00.00.00.00.00.0DELAYED-Bend All Socket PVC RRJ Dia. 100 x 45bh1.00Rp145,300.000.200.00.00.00.00.00.00.00.00.00.0DELAYED-Flange Socket PVC RRJ Dia. 100 mmbh7.00Rp4,092,018.005.650.00.00.00.00.00.00.00.00.00.0DELAYED-Flange Socket PVC RRJ Dia. 50 mmbh2.00Rp349,000.000.480.00.00.00.00.00.00.00.00.00.0DELAYED-Tee All socket Dia 100 x 100 mmbh1.00Rp303,300.000.420.00.00.00.00.00.00.00.00.00.0DELAYED-Reducer Socket Dia 100 x 50 mmbh1.00Rp112,850.000.160.00.00.00.00.00.00.00.00.00.0DELAYED-Bend All Socket PVC RRJ Dia. 50 x 90bh1.00Rp50,550.000.070.00.00.00.00.00.00.00.00.00.0DELAYED-Dop PVC dia.100 mmbh1.00Rp171,175.000.240.00.00.00.00.00.00.00.00.00.0DELAYED-Bend GIP Dia 100 x 90 mmbh1.00Rp180,000.000.250.00.00.00.00.00.00.00.00.00.0DELAYED-Bend GIP Dia 100 x 45 mmbh4.00Rp620,000.000.860.00.00.00.00.00.00.00.00.00.0DELAYED-Bend GIP Dia 50 x 90 mmbh2.00Rp190,000.000.260.00.00.00.00.00.00.00.00.00.0DELAYED-Loss Flange GIP Dia 100 mmbh5.00Rp560,000.000.770.00.00.00.00.00.00.00.00.00.0DELAYED-Loss Flange GIP Dia 50 mmbh2.00Rp162,000.000.220.00.00.00.00.00.00.00.00.00.0DELAYED-Tee Gip 100 x 50 mmbh1.00Rp215,000.000.300.00.00.00.00.00.00.00.00.00.0DELAYED-Gate Valve 4"bh2.00Rp3,000,000.004.150.00.00.00.00.00.00.00.00.00.0DELAYED-Saringan/Besi Dia 4 "bh1.00Rp75,000.000.100.00.00.00.00.00.00.00.00.00.0DELAYED-Bautbh80.00Rp600,000.000.830.00.00.00.00.00.00.00.00.00.0DELAYED-Pakingbh10.00Rp115,000.000.160.00.00.00.00.00.00.00.00.00.0DELAYEDIIIPEKERJAAN PEMASANGAN PIPA DAN ACESSORIES$1Pekerjaan Tanah-Galian Tanah KerasM3108.24Rp4,663,520.406.440.00.00.00.00.00.00.00.00.00.0DELAYED-Urugan KembaliM3104.60Rp1,384,062.571.910.00.00.00.00.00.00.00.00.00.0DELAYED$2Pemasangan Pipa Termasuk Fitting dan Valve-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp8,392,208.0011.600.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.100 mmM'12.00Rp572,425.150.790.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.50 mmM'5.00Rp130,904.600.180.00.00.00.00.00.00.00.00.00.0DELAYED-Pengecatan permukaan baja secara manual sistem 2 lapisM24.55Rp72,529.150.100.00.00.00.00.00.00.00.00.00.0DELAYEDIVPEKERJAAN LAIN-LAIN$1Crossing Pipa/ BoringM'6.00Rp900,000.001.240.00.00.00.00.00.00.00.00.00.0DELAYED$2Rekondisi Jalan/FinishingLs1.00Rp200,000.000.280.00.00.00.00.00.00.00.00.00.0DELAYED$3Rekondisi Jalan (Rabat Beton)M30.02Rp9,396.280.010.00.00.00.00.00.00.00.00.00.0DELAYED$4Uji Laboratorium Baku Mutu Kualitas Air BersihLs1.00Rp750,000.001.040.00.00.00.00.00.00.00.00.00.0DELAYED$5Street BoxLs2.00Rp1,600,000.002.210.00.00.00.00.00.00.00.00.00.0DELAYEDVPEKERJAAN REHAP INTAKE$1PEKERJAAN TANAH & PONDASIGalian Tanah PondasiM31.00Rp4,589.550.010.00.00.00.00.00.00.00.00.00.0DELAYEDUrugan Pasir Bawah PondasiM30.02Rp1,713.120.000.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu Gunung 1 : 3M31.00Rp277,037.340.380.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu KosongM32.00Rp6,419.820.010.00.00.00.00.00.00.00.00.00.0DELAYEDTanah TimbunanM31.00Rp1,088,542.181.500.00.00.00.00.00.00.00.00.00.0DELAYEDLantai Beton Cor 1Pc : 1,5Ps : 2,5Kr, T=10 cmM30.02Rp966,777.351.340.00.00.00.00.00.00.00.00.00.0DELAYEDPlasteran 1pc : 2 psM21.00Rp229,752.660.320.00.00.00.00.00.00.00.00.00.0DELAYEDJUMLAHRp72,371,871.18100.00Rp2,370,000.003.27Rp16,867,400.00023.31Rp19,237,400.0026.58SISA PROGRESSPPn10%Rp7,237,187.12Rp237,000.00Rp1,686,740.000Rp1,923,740.00GRAND TOTALRp79,609,058.30Rp2,607,000.00Rp18,554,140.000Rp21,161,140.0073.42%DIBULATKANRp79,609,000.00Rp2,607,000.00Rp18,554,000.00Rp21,161,000.00Disetujui Oleh :Diperiksa Oleh :Dibuat Oleh :Pejabat Pelaksana Teknis Kegiatan (PPTK)Konsultan SupervisiKONTRAKTOR PELAKSANADinas Cipta Karya Aceh BesarCV. SCALA DESIGNCV. TUAH BARUSAMUHAMMAD IKHSAN,ST.MTHERI DERMAWAN,STIRSANNIP. 19740407 200212 1 007InspectorDirektur

b1LAPORAN KEMAJUAN PEKERJAANBULANKE :1 (SATU)PERIODE :06 AGUSTUS 2014 S/D 31 AGUSTUS 2014PEKERJAAN:PEMASANGAN PIPANISASI AIR BERSIH GP. ALUE RINDANG KEC. SEULIMEUM (DAU)PROGRESS27.32%LOKASI:KEC. SEULIMEUMKONTRAKTOR PELAKSANA:CV. TUAH BARUSARENCANAJANGKA WAKTU PELAKSANAAN:90 HariNO. KONTRAK:26/SPK/PL.P-PERKIM/BMCK/2014PROGRESS26.58%NILAI KONTRAK AWAL:Rp79,609,000TANGGAL KONTRAK:06 AGUSTUS 2014ACTUALSUMBER DANA:APBKKONSULTAN PENGAWAS:CV. SCALA DESIGNDEVIASI-0.74%TAHUNANGGARAN:2014NO. KONTRAK:0.0TANGGAL KONTRAK:0.0DELAYEDON PROGRESSON PROGRESSON PROGRESSDELAYEDON PROGRESSON PROGRESSON PROGRESSNO.URAIANSAT.KONTRAK AWALBULAN LALUBULAN INIREALISASI PEKER. S/D BULAN INIKET.QTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotPrestasi( Rp. )( % )( Rp. )( % )(Rp.)( % )( Rp. )( % )(%)abcdefghijklm =(g+j)n =(h+k)o =(i+l)pqIPEKERJAAN PERSIAPAN$1Direksi Keet / Gudang (Sewa)Ls1.00Rp390,000.000.540.00.00.01.00Rp390,000.000.541.00Rp390,000.000.54100.00COMPLETEDRp2,370,000.00$2Papan Nama Proyek dan Rambu -RambuLs1.00Rp280,000.000.390.00.00.01.00Rp280,000.000.391.00Rp280,000.000.39100.00COMPLETEDRp16,867,400.00$3PembersihanLs1.00Rp450,000.000.620.00.00.01.00Rp450,000.000.621.00Rp450,000.000.62100.00COMPLETED0.0$4Pematokan/pengukuran (setting out)Ls1.00Rp500,000.000.690.00.00.01.00Rp500,000.000.691.00Rp500,000.000.69100.00COMPLETED0.0$5Mobilisasi dan DemobilisasiLs1.00Rp250,000.000.350.00.00.01.00Rp250,000.000.351.00Rp250,000.000.35100.00COMPLETED0.0$6Administrasi Dokumentasi dan as built drawingLs1.00Rp1,000,000.001.380.00.00.00.50Rp500,000.000.690.50Rp500,000.000.6950.00ON PROGRESSIIPENGADAAN PIPA DAN ACCESSORIES$1Pengadaan PipaPengadaan Pipa-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp33,734,800.0046.610.00.00.0225.50Rp16,867,400.0023.31225.50Rp16,867,400.0023.3150.00ON PROGRESS-Pipa GIP dia.100 mmPipa GIP dia.100 mmM'12.00Rp2,640,000.003.650.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.50 mmPipa GIP dia.50 mmM'5.00Rp620,000.000.860.00.00.00.00.00.00.00.00.00.0DELAYED$2Pengadaan Accessories-Bend All Socket PVC RRJ Dia. 100 x 90bh2.00Rp316,000.000.440.00.00.00.00.00.00.00.00.00.0DELAYED66.67-Bend All Socket PVC RRJ Dia. 100 x 45bh1.00Rp145,300.000.200.00.00.00.00.00.00.00.00.00.0DELAYED43.36-Flange Socket PVC RRJ Dia. 100 mmbh7.00Rp4,092,018.005.650.00.00.00.00.00.00.00.00.00.0DELAYED-Flange Socket PVC RRJ Dia. 50 mmbh2.00Rp349,000.000.480.00.00.00.00.00.00.00.00.00.0DELAYED-Tee All socket Dia 100 x 100 mmbh1.00Rp303,300.000.420.00.00.00.00.00.00.00.00.00.0DELAYED-Reducer Socket Dia 100 x 50 mmbh1.00Rp112,850.000.160.00.00.00.00.00.00.00.00.00.0DELAYED-Bend All Socket PVC RRJ Dia. 50 x 90bh1.00Rp50,550.000.070.00.00.00.00.00.00.00.00.00.0DELAYED-Dop PVC dia.100 mmbh1.00Rp171,175.000.240.00.00.00.00.00.00.00.00.00.0DELAYED-Bend GIP Dia 100 x 90 mmbh1.00Rp180,000.000.250.00.00.00.00.00.00.00.00.00.0DELAYED-Bend GIP Dia 100 x 45 mmbh4.00Rp620,000.000.860.00.00.00.00.00.00.00.00.00.0DELAYED-Bend GIP Dia 50 x 90 mmbh2.00Rp190,000.000.260.00.00.00.00.00.00.00.00.00.0DELAYED-Loss Flange GIP Dia 100 mmbh5.00Rp560,000.000.770.00.00.00.00.00.00.00.00.00.0DELAYED-Loss Flange GIP Dia 50 mmbh2.00Rp162,000.000.220.00.00.00.00.00.00.00.00.00.0DELAYED-Tee Gip 100 x 50 mmbh1.00Rp215,000.000.300.00.00.00.00.00.00.00.00.00.0DELAYED-Gate Valve 4"bh2.00Rp3,000,000.004.150.00.00.00.00.00.00.00.00.00.0DELAYED-Saringan/Besi Dia 4 "bh1.00Rp75,000.000.100.00.00.00.00.00.00.00.00.00.0DELAYED-Bautbh80.00Rp600,000.000.830.00.00.00.00.00.00.00.00.00.0DELAYED-Pakingbh10.00Rp115,000.000.160.00.00.00.00.00.00.00.00.00.0DELAYEDIIIPEKERJAAN PEMASANGAN PIPA DAN ACESSORIES$1Pekerjaan Tanah-Galian Tanah KerasM3108.24Rp4,663,520.406.440.00.00.00.00.00.00.00.00.00.0DELAYED-Urugan KembaliM3104.60Rp1,384,062.571.910.00.00.00.00.00.00.00.00.00.0DELAYED$2Pemasangan Pipa Termasuk Fitting dan Valve-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp8,392,208.0011.600.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.100 mmM'12.00Rp572,425.150.790.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.50 mmM'5.00Rp130,904.600.180.00.00.00.00.00.00.00.00.00.0DELAYED-Pengecatan permukaan baja secara manual sistem 2 lapisM24.55Rp72,529.150.100.00.00.00.00.00.00.00.00.00.0DELAYEDIVPEKERJAAN LAIN-LAIN$1Crossing Pipa/ BoringM'6.00Rp900,000.001.240.00.00.00.00.00.00.00.00.00.0DELAYED$2Rekondisi Jalan/FinishingLs1.00Rp200,000.000.280.00.00.00.00.00.00.00.00.00.0DELAYED$3Rekondisi Jalan (Rabat Beton)M30.02Rp9,396.280.010.00.00.00.00.00.00.00.00.00.0DELAYED$4Uji Laboratorium Baku Mutu Kualitas Air BersihLs1.00Rp750,000.001.040.00.00.00.00.00.00.00.00.00.0DELAYED$5Street BoxLs2.00Rp1,600,000.002.210.00.00.00.00.00.00.00.00.00.0DELAYEDVPEKERJAAN REHAP INTAKE$1PEKERJAAN TANAH & PONDASIGalian Tanah PondasiM31.00Rp4,589.550.010.00.00.00.00.00.00.00.00.0DELAYEDUrugan Pasir Bawah PondasiM30.02Rp1,713.120.000.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu Gunung 1 : 3M31.00Rp277,037.340.380.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu KosongM32.00Rp6,419.820.010.00.00.00.00.00.00.00.00.00.0DELAYEDTanah TimbunanM31.00Rp1,088,542.181.500.00.00.00.00.00.00.00.00.00.0DELAYEDLantai Beton Cor 1Pc : 1,5Ps : 2,5Kr, T=10 cmM30.02Rp966,777.351.340.00.00.00.00.00.00.00.00.00.0DELAYEDPlasteran 1pc : 2 psM21.00Rp229,752.660.320.00.00.00.00.00.00.00.00.00.0DELAYEDJUMLAHRp72,371,871.18100.000.00.00Rp19,237,400.00026.58Rp19,237,400.0026.58SISA PROGRESSPPn10%Rp7,237,187.120.0Rp1,923,740.000Rp1,923,740.00GRAND TOTALRp79,609,058.300.0Rp21,161,140.000Rp21,161,140.0073.42%DIBULATKANRp79,609,000.000.0Rp21,161,000.00Rp21,161,000.00Disetujui Oleh :Diperiksa Oleh :Dibuat Oleh :Pejabat Pelaksana Teknis Kegiatan (PPTK)Konsultan SupervisiKONTRAKTOR PELAKSANADinas Cipta Karya Aceh BesarCV. SCALA DESIGNCV. TUAH BARUSAMUHAMMAD IKHSAN,ST.MTHERI DERMAWAN,STIRSANNIP. 19740407 200212 1 007InspectorDirektur

s1SERTIFIKAT KE - IKegiatan:PEMBANGUNAN SARANA DAN PRASARANA AIR BERSIH PEDESAAN (DAK)Kontraktor:CV. TUAH BARUSANama Paket:PEMASANGAN PIPANISASI AIR BERSIH GP. ALUE RINDANG KEC. SEULIMEUM (DAU)Konsultan Pengawas:CV. SCALA DESIGNNo. Kontrak/Tanggal:26/SPK/PL.P-PERKIM/BMCK/2014Tanggal:31 AGUSTUS 2014No. Addendum/Tgl:Sertifikat Ke:I (Satu)Tahun Anggaran:2014NOURAIAN PEKERJAANKONTRAK AWALJUMLAH PEMBAYARANS.D YANG LALUSAAT INIS.D SAAT INI(Rp)%(Rp)%(Rp)%(Rp)%127IPEKERJAAN PERSIAPAN2,870,000.003.970.00.02,370,000.003.272,370,000.003.27IIPENGADAAN PIPA DAN ACCESSORIES48,251,993.0066.670.00.016,867,400.0023.3116,867,400.0023.31IIIPEKERJAAN PEMASANGAN PIPA DAN ACESSORIES15,215,649.8821.020.00.00.00.00.00.0IVPEKERJAAN LAIN-LAIN3,459,396.284.780.00.00.00.00.00.0VPEKERJAAN REHAB. INTAKE2,574,832.023.560.00.00.00.00.00.0AJUMLAH72,371,878.18100.000.00.019,237,400.0026.5819,237,400.0026.5826.58PPN 10%7,237,187.820.01,923,740.001,923,740.00TOTAL79,609,066.000.021,161,140.0021,161,140.00DIBULATKAN79,609,000.000.021,161,000.0021,161,000.00BNILAI SERTIFIKAT S.D. BULAN INI21,161,000.0026.58CNILAI SERTIFIKAT S.D. BULAN LALU0.00.0DNILAI SERTIFIKAT BULAN INI (item B - item C)21,161,000.0026.58POTONGAN-POTONGANE1. JAMINAN PEMELIHARAAN (5% dari item D)0.0F2. PENGEMBALIAN UANG MUKA (30% dari item D)0.0GTOTAL POTONGAN (item E + item F)0.0HNILAI BERSIH SERTIFIKAT BULAN INI SEBELUM PAJAK (item D - item G)21,161,000.00INILAI BERSIH SERTIFIKAT S.D. BULAN INI DIPOTONG PAJAK ((100/110) x item H)19,237,272.73DIBULATKAN19,237,000.00Terbilang:Sembilan Belas Juta Dua Ratus Tiga Puluh Tujuh Ribu RupiahPROGRESS DICAPAIS.D. BULAN INI:26.58%S.D. BULAN LALU:0.0%BULAN INI:26.58%Aceh Besar, 31 Agustus 2014Mengetahui/Disetujui Oleh:Disetujui OlehDiperiksa Oleh:Diajukan Oleh:Kuasa Pengguna Anggaran Bidang PerumahanPejabat Pelaksana Teknis Kegiatan (PPTK)Konsultan SupervisiKontraktor PelaksanaAir Bersih dan Prasarana PermukimanDinas Cipta Karya Aceh BesarCV. SCALA DESAINCV. TUAH BARUSANAZARUL KHAIRI, ST.MT.MUHAMMAD IKHSAN,ST.MTFAKHRUDDIN, STIRSANNip. 19690601 200012 1 010NIP. 19740407 200212 1 007DirekturDirekturTerjemahan kedalam kalimat19,237,000.001satu dua tiga empat lima enam tujuh delapan sembilan sepuluhribu juta milyar triliyun000019237000basic @0001perhitungan @0angka @0sepuluh@00@0@00@0@@@2372@2tiga puluh@dua ratustujuh belas@3tujuh@7tiga puluh tujuh@tiga puluh tujuhtiga puluh tujuh@dua ratus tiga puluh tujuh ribu@@@0193@0@0sembilan belas@1sembilan@9sembilan@sembilan belassembilan belas@sembilan belas juta@@@0004@0@0sepuluh@00@0@00@0@@0001@0@0sepuluh@00@0@00@0@@@05800@sembilan belas juta dua ratus tiga puluh tujuh ribu rupiahsembilan belas juta dua ratus tiga puluh tujuh ribu rupiah@sembilan belas juta dua ratus tiga puluh tujuh ribu rupiah@Sembilan belas juta dua ratus tiga puluh tujuh ribu rupiah

M.2.1 (4)LAPORAN KEMAJUAN PEKERJAANMINGGU KE :4 (EMPAT)PERIODE :01 SEPTEMBER 2014 S/D 07 SEPTEMBER 2014PEKERJAAN:PEMASANGAN PIPANISASI AIR BERSIH GP. ALUE RINDANG KEC. SEULIMEUM (DAU)PROGRESS50.61%LOKASI:KEC. SEULIMEUMKONTRAKTOR PELAKSANA:CV. TUAH BARUSARENCANAJANGKA WAKTU PELAKSANAAN:90 HariNO. KONTRAK:26/SPK/PL.P-PERKIM/BMCK/2014PROGRESS49.89%NILAI KONTRAK AWAL:Rp79,609,000TANGGAL KONTRAK:06 AGUSTUS 2014ACTUALSUMBER DANA:APBKKONSULTAN PENGAWAS:CV. SCALA DESIGNDEVIASI-0.72%TAHUNANGGARAN:2014NO. KONTRAK:0.0TANGGAL KONTRAK:0.0DELAYEDON PROGRESSON PROGRESSON PROGRESSDELAYEDON PROGRESSON PROGRESSON PROGRESSNO.URAIANSAT.KONTRAK AWALMINGGU LALUMINGGU INIREALISASI PEKER. S/D MINGGU INIKET.QTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotPrestasi( Rp. )( % )( Rp. )( % )(Rp.)( % )( Rp. )( % )(%)abcdefghijklm =(g+j)n =(h+k)o =(i+l)pqIPEKERJAAN PERSIAPAN$1Direksi Keet / Gudang (Sewa)Ls1.00Rp390,000.000.541.00Rp390,000.000.540.00.00.01.00Rp390,000.000.54100.00COMPLETED$2Papan Nama Proyek dan Rambu -RambuLs1.00Rp280,000.000.391.00Rp280,000.000.390.00.00.01.00Rp280,000.000.39100.00COMPLETED$3PembersihanLs1.00Rp450,000.000.621.00Rp450,000.000.620.00.00.01.00Rp450,000.000.62100.00COMPLETED$4Pematokan/pengukuran (setting out)Ls1.00Rp500,000.000.691.00Rp500,000.000.690.00.00.01.00Rp500,000.000.69100.00COMPLETED$5Mobilisasi dan DemobilisasiLs1.00Rp250,000.000.351.00Rp250,000.000.350.00.00.01.00Rp250,000.000.35100.00COMPLETED$6Administrasi Dokumentasi dan as built drawingLs1.00Rp1,000,000.001.380.50Rp500,000.000.690.00.00.00.50Rp500,000.000.6950.00ON PROGRESSIIPENGADAAN PIPA DAN ACCESSORIES0.0$1Pengadaan PipaPengadaan Pipa-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp33,734,800.0046.61225.50Rp16,867,400.0023.31225.50Rp16,867,400.0023.31451.00Rp33,734,800.0046.61100.00COMPLETED-Pipa GIP dia.100 mmPipa GIP dia.100 mmM'12.00Rp2,640,000.003.650.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.50 mmPipa GIP dia.50 mmM'5.00Rp620,000.000.860.00.00.00.00.00.00.00.00.00.0DELAYED$2Pengadaan Accessories-Bend All Socket PVC RRJ Dia. 100 x 90bh2.00Rp316,000.000.440.00.00.00.00.00.00.00.00.00.0DELAYED-Bend All Socket PVC RRJ Dia. 100 x 45bh1.00Rp145,300.000.200.00.00.00.00.00.00.00.00.00.0DELAYED-Flange Socket PVC RRJ Dia. 100 mmbh7.00Rp4,092,018.005.650.00.00.00.00.00.00.00.00.00.0DELAYED-Flange Socket PVC RRJ Dia. 50 mmbh2.00Rp349,000.000.480.00.00.00.00.00.00.00.00.00.0DELAYED-Tee All socket Dia 100 x 100 mmbh1.00Rp303,300.000.420.00.00.00.00.00.00.00.00.00.0DELAYED-Reducer Socket Dia 100 x 50 mmbh1.00Rp112,850.000.160.00.00.00.00.00.00.00.00.00.0DELAYED-Bend All Socket PVC RRJ Dia. 50 x 90bh1.00Rp50,550.000.070.00.00.00.00.00.00.00.00.00.0DELAYED-Dop PVC dia.100 mmbh1.00Rp171,175.000.240.00.00.00.00.00.00.00.00.00.0DELAYED-Bend GIP Dia 100 x 90 mmbh1.00Rp180,000.000.250.00.00.00.00.00.00.00.00.00.0DELAYED-Bend GIP Dia 100 x 45 mmbh4.00Rp620,000.000.860.00.00.00.00.00.00.00.00.00.0DELAYED-Bend GIP Dia 50 x 90 mmbh2.00Rp190,000.000.260.00.00.00.00.00.00.00.00.00.0DELAYED-Loss Flange GIP Dia 100 mmbh5.00Rp560,000.000.770.00.00.00.00.00.00.00.00.00.0DELAYED-Loss Flange GIP Dia 50 mmbh2.00Rp162,000.000.220.00.00.00.00.00.00.00.00.00.0DELAYED-Tee Gip 100 x 50 mmbh1.00Rp215,000.000.300.00.00.00.00.00.00.00.00.00.0DELAYED-Gate Valve 4"bh2.00Rp3,000,000.004.150.00.00.00.00.00.00.00.00.00.0DELAYED-Saringan/Besi Dia 4 "bh1.00Rp75,000.000.100.00.00.00.00.00.00.00.00.00.0DELAYED-Bautbh80.00Rp600,000.000.830.00.00.00.00.00.00.00.00.00.0DELAYED-Pakingbh10.00Rp115,000.000.160.00.00.00.00.00.00.00.00.00.0DELAYEDIIIPEKERJAAN PEMASANGAN PIPA DAN ACESSORIES$1Pekerjaan Tanah-Galian Tanah KerasM3108.24Rp4,663,520.406.440.00.00.00.00.00.00.00.00.00.0DELAYED-Urugan KembaliM3104.60Rp1,384,062.571.910.00.00.00.00.00.00.00.00.00.0DELAYED$2Pemasangan Pipa Termasuk Fitting dan Valve-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp8,392,208.0011.600.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.100 mmM'12.00Rp572,425.150.790.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.50 mmM'5.00Rp130,904.600.180.00.00.00.00.00.00.00.00.00.0DELAYED-Pengecatan permukaan baja secara manual sistem 2 lapisM24.55Rp72,529.150.100.00.00.00.00.00.00.00.00.00.0DELAYEDIVPEKERJAAN LAIN-LAIN$1Crossing Pipa/ BoringM'6.00Rp900,000.001.240.00.00.00.00.00.00.00.00.00.0DELAYED$2Rekondisi Jalan/FinishingLs1.00Rp200,000.000.280.00.00.00.00.00.00.00.00.00.0DELAYED$3Rekondisi Jalan (Rabat Beton)M30.02Rp9,396.280.010.00.00.00.00.00.00.00.00.00.0DELAYED$4Uji Laboratorium Baku Mutu Kualitas Air BersihLs1.00Rp750,000.001.040.00.00.00.00.00.00.00.00.00.0DELAYED$5Street BoxLs2.00Rp1,600,000.002.210.00.00.00.00.00.00.00.00.00.0DELAYEDVPEKERJAAN REHAP INTAKE$1PEKERJAAN TANAH & PONDASIGalian Tanah PondasiM31.00Rp4,589.550.010.00.00.00.00.00.00.00.00.00.0DELAYEDUrugan Pasir Bawah PondasiM30.02Rp1,713.120.000.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu Gunung 1 : 3M31.00Rp277,037.340.380.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu KosongM32.00Rp6,419.820.010.00.00.00.00.00.00.00.00.00.0DELAYEDTanah TimbunanM31.00Rp1,088,542.181.500.00.00.00.00.00.00.00.00.00.0DELAYEDLantai Beton Cor 1Pc : 1,5Ps : 2,5Kr, T=10 cmM30.02Rp966,777.351.340.00.00.00.00.00.00.00.00.00.0DELAYEDPlasteran 1pc : 2 psM21.00Rp229,752.660.320.00.00.00.00.00.00.00.00.00.0DELAYEDJUMLAHRp72,371,871.18100.00Rp19,237,400.0026.58Rp16,867,400.00023.31Rp36,104,800.0049.89SISA PROGRESSPPn10%Rp7,237,187.12Rp1,923,740.00Rp1,686,740.000Rp3,610,480.00GRAND TOTALRp79,609,058.30Rp21,161,140.00Rp18,554,140.000Rp39,715,280.0050.11%DIBULATKANRp79,609,000.00Rp21,161,000.00Rp18,554,000.00Rp39,715,000.00Disetujui Oleh :Diperiksa Oleh :Dibuat Oleh :Pejabat Pelaksana Teknis Kegiatan (PPTK)Konsultan SupervisiKontraktor PelaksanaDinas Cipta Karya Aceh BesarCV. SCALA DESIGNCV. TUAH BARUSAMUHAMMAD IKHSAN,ST.MTHERI DERMAWAN,STIRSANNIP. 19740407 200212 1 007InspectorDirektur

M.2.1 (5)LAPORAN KEMAJUAN PEKERJAANMINGGU KE :5(LIMA)PERIODE :08 SEPTEMBER 2014 S/D 14 SEPTEMBER 2014PEKERJAAN:PEMASANGAN PIPANISASI AIR BERSIH GP. ALUE RINDANG KEC. SEULIMEUM (DAU)PROGRESS70.66%LOKASI:KEC. SEULIMEUMKONTRAKTOR PELAKSANA:CV. TUAH BARUSARENCANAJANGKA WAKTU PELAKSANAAN:90 HariNO. KONTRAK:26/SPK/PL.P-PERKIM/BMCK/2014PROGRESS69.95%NILAI KONTRAK AWAL:Rp79,609,000TANGGAL KONTRAK:06 AGUSTUS 2014ACTUALSUMBER DANA:APBKKONSULTAN PENGAWAS:CV. SCALA DESIGNDEVIASI-0.71%TAHUNANGGARAN:2014NO. KONTRAK:0.0TANGGAL KONTRAK:0.0DELAYEDON PROGRESSON PROGRESSON PROGRESSDELAYEDON PROGRESSON PROGRESSON PROGRESSNO.URAIANSAT.KONTRAK AWALMINGGU LALUMINGGU INIREALISASI PEKER. S/D MINGGU INIKET.QTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotPrestasi( Rp. )( % )( Rp. )( % )(Rp.)( % )( Rp. )( % )(%)abcdefghijklm =(g+j)n =(h+k)o =(i+l)pqIPEKERJAAN PERSIAPAN$1Direksi Keet / Gudang (Sewa)Ls1.00Rp390,000.000.541.00Rp390,000.000.540.00.00.01.00Rp390,000.000.54100.00COMPLETED$2Papan Nama Proyek dan Rambu -RambuLs1.00Rp280,000.000.391.00Rp280,000.000.390.00.00.01.00Rp280,000.000.39100.00COMPLETED$3PembersihanLs1.00Rp450,000.000.621.00Rp450,000.000.620.00.00.01.00Rp450,000.000.62100.00COMPLETED$4Pematokan/pengukuran (setting out)Ls1.00Rp500,000.000.691.00Rp500,000.000.690.00.00.01.00Rp500,000.000.69100.00COMPLETED$5Mobilisasi dan DemobilisasiLs1.00Rp250,000.000.351.00Rp250,000.000.350.00.00.01.00Rp250,000.000.35100.00COMPLETED$6Administrasi Dokumentasi dan as built drawingLs1.00Rp1,000,000.001.380.50Rp500,000.000.690.00.00.00.50Rp500,000.000.6950.00ON PROGRESSIIPENGADAAN PIPA DAN ACCESSORIES$1Pengadaan PipaPengadaan Pipa-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp33,734,800.0046.61451.00Rp33,734,800.0046.610.00.00.0451.00Rp33,734,800.0046.61100.00COMPLETED-Pipa GIP dia.100 mmPipa GIP dia.100 mmM'12.00Rp2,640,000.003.650.00.00.012.00Rp2,640,000.003.6512.00Rp2,640,000.003.65100.00COMPLETED-Pipa GIP dia.50 mmPipa GIP dia.50 mmM'5.00Rp620,000.000.860.00.00.05.00Rp620,000.000.865.00Rp620,000.000.86100.00COMPLETED$2Pengadaan Accessories-Bend All Socket PVC RRJ Dia. 100 x 90bh2.00Rp316,000.000.440.00.00.02.00Rp316,000.000.442.00Rp316,000.000.44100.00COMPLETED-Bend All Socket PVC RRJ Dia. 100 x 45bh1.00Rp145,300.000.200.00.00.01.00Rp145,300.000.201.00Rp145,300.000.20100.00COMPLETED-Flange Socket PVC RRJ Dia. 100 mmbh7.00Rp4,092,018.005.650.00.00.07.00Rp4,092,018.005.657.00Rp4,092,018.005.65100.00COMPLETED-Flange Socket PVC RRJ Dia. 50 mmbh2.00Rp349,000.000.480.00.00.02.00Rp349,000.000.482.00Rp349,000.000.48100.00COMPLETED-Tee All socket Dia 100 x 100 mmbh1.00Rp303,300.000.420.00.00.01.00Rp303,300.000.421.00Rp303,300.000.42100.00COMPLETED-Reducer Socket Dia 100 x 50 mmbh1.00Rp112,850.000.160.00.00.01.00Rp112,850.000.161.00Rp112,850.000.16100.00COMPLETED-Bend All Socket PVC RRJ Dia. 50 x 90bh1.00Rp50,550.000.070.00.00.01.00Rp50,550.000.071.00Rp50,550.000.07100.00COMPLETED-Dop PVC dia.100 mmbh1.00Rp171,175.000.240.00.00.01.00Rp171,175.000.241.00Rp171,175.000.24100.00COMPLETED-Bend GIP Dia 100 x 90 mmbh1.00Rp180,000.000.250.00.00.01.00Rp180,000.000.251.00Rp180,000.000.25100.00COMPLETED-Bend GIP Dia 100 x 45 mmbh4.00Rp620,000.000.860.00.00.04.00Rp620,000.000.864.00Rp620,000.000.86100.00COMPLETED-Bend GIP Dia 50 x 90 mmbh2.00Rp190,000.000.260.00.00.02.00Rp190,000.000.262.00Rp190,000.000.26100.00COMPLETED-Loss Flange GIP Dia 100 mmbh5.00Rp560,000.000.770.00.00.05.00Rp560,000.000.775.00Rp560,000.000.77100.00COMPLETED-Loss Flange GIP Dia 50 mmbh2.00Rp162,000.000.220.00.00.02.00Rp162,000.000.222.00Rp162,000.000.22100.00COMPLETED-Tee Gip 100 x 50 mmbh1.00Rp215,000.000.300.00.00.01.00Rp215,000.000.301.00Rp215,000.000.30100.00COMPLETED-Gate Valve 4"bh2.00Rp3,000,000.004.150.00.00.02.00Rp3,000,000.004.152.00Rp3,000,000.004.15100.00COMPLETED-Saringan/Besi Dia 4 "bh1.00Rp75,000.000.100.00.00.01.00Rp75,000.000.101.00Rp75,000.000.10100.00COMPLETED-Bautbh80.00Rp600,000.000.830.00.00.080.00Rp600,000.000.8380.00Rp600,000.000.83100.00COMPLETED-Pakingbh10.00Rp115,000.000.160.00.00.010.00Rp115,000.000.1610.00Rp115,000.000.16100.00COMPLETEDIIIPEKERJAAN PEMASANGAN PIPA DAN ACESSORIES$1Pekerjaan Tanah-Galian Tanah KerasM3108.24Rp4,663,520.406.440.00.00.00.00.00.00.00.00.00.0DELAYED-Urugan KembaliM3104.60Rp1,384,062.571.910.00.00.00.00.00.00.00.00.00.0DELAYED$2Pemasangan Pipa Termasuk Fitting dan Valve-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp8,392,208.0011.600.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.100 mmM'12.00Rp572,425.150.790.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.50 mmM'5.00Rp130,904.600.180.00.00.00.00.00.00.00.00.00.0DELAYED-Pengecatan permukaan baja secara manual sistem 2 lapisM24.55Rp72,529.150.100.00.00.00.00.00.00.00.00.00.0DELAYEDIVPEKERJAAN LAIN-LAIN$1Crossing Pipa/ BoringM'6.00Rp900,000.001.240.00.00.00.00.00.00.00.00.00.0DELAYED$2Rekondisi Jalan/FinishingLs1.00Rp200,000.000.280.00.00.00.00.00.00.00.00.00.0DELAYED$3Rekondisi Jalan (Rabat Beton)M30.02Rp9,396.280.010.00.00.00.00.00.00.00.00.00.0DELAYED$4Uji Laboratorium Baku Mutu Kualitas Air BersihLs1.00Rp750,000.001.040.00.00.00.00.00.00.00.00.00.0DELAYED$5Street BoxLs2.00Rp1,600,000.002.210.00.00.00.00.00.00.00.00.00.0DELAYEDVPEKERJAAN REHAP INTAKE$1PEKERJAAN TANAH & PONDASIGalian Tanah PondasiM31.00Rp4,589.550.010.00.00.00.00.00.00.00.00.00.0DELAYEDUrugan Pasir Bawah PondasiM30.02Rp1,713.120.000.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu Gunung 1 : 3M31.00Rp277,037.340.380.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu KosongM32.00Rp6,419.820.010.00.00.00.00.00.00.00.00.00.0DELAYEDTanah TimbunanM31.00Rp1,088,542.181.500.00.00.00.00.00.00.00.00.00.0DELAYEDLantai Beton Cor 1Pc : 1,5Ps : 2,5Kr, T=10 cmM30.02Rp966,777.351.340.00.00.00.00.00.00.00.00.00.0DELAYEDPlasteran 1pc : 2 psM21.00Rp229,752.660.320.00.00.00.00.00.00.00.00.00.0DELAYEDJUMLAHRp72,371,871.18100.00Rp36,104,800.0049.89Rp14,517,193.00020.06Rp50,621,993.0069.95SISA PROGRESSPPn10%Rp7,237,187.12Rp3,610,480.00Rp1,451,719.300Rp5,062,199.30GRAND TOTALRp79,609,058.30Rp39,715,280.00Rp15,968,912.300Rp55,684,192.3030.05%DIBULATKANRp79,609,000.00Rp39,715,000.00Rp15,968,000.00Rp55,684,000.00Disetujui Oleh :Diperiksa Oleh :Dibuat Oleh :Pejabat Pelaksana Teknis Kegiatan (PPTK)Konsultan SupervisiKontraktor PelaksanaDinas Cipta Karya Aceh BesarCV. SCALA DESIGNCV. TUAH BARUSAMUHAMMAD IKHSAN,ST.MTHERI DERMAWAN,STIRSANNIP. 19740407 200212 1 007InspectorDirektur

M.2.1 (6)LAPORAN KEMAJUAN PEKERJAANMINGGU KE :6 (ENAM)PERIODE :15 SEPTEMBER 2014 S/D 23 SEPTEMBER 2014PEKERJAAN:PEMASANGAN PIPANISASI AIR BERSIH GP. ALUE RINDANG KEC. SEULIMEUM (DAU)PROGRESS79.01%LOKASI:KEC. SEULIMEUMKONTRAKTOR PELAKSANA:CV. TUAH BARUSARENCANAJANGKA WAKTU PELAKSANAAN:90 HariNO. KONTRAK:26/SPK/PL.P-PERKIM/BMCK/2014PROGRESS79.51%NILAI KONTRAK AWAL:Rp79,609,000TANGGAL KONTRAK:06 AGUSTUS 2014ACTUALSUMBER DANA:APBKKONSULTAN PENGAWAS:CV. SCALA DESIGNDEVIASI0.50%TAHUNANGGARAN:2014NO. KONTRAK:0.0TANGGAL KONTRAK:0.0ADVANCEON PROGRESSON PROGRESSON PROGRESSDELAYEDON PROGRESSON PROGRESSON PROGRESSNO.URAIANSAT.KONTRAK AWALMINGGU LALUMINGGU INIREALISASI PEKER. S/D MINGGU INIKET.QTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotPrestasi( Rp. )( % )( Rp. )( % )(Rp.)( % )( Rp. )( % )(%)abcdefghijklm =(g+j)n =(h+k)o =(i+l)pqIPEKERJAAN PERSIAPAN$1Direksi Keet / Gudang (Sewa)Ls1.00Rp390,000.000.541.00Rp390,000.000.540.00.00.01.00Rp390,000.000.54100.00COMPLETED$2Papan Nama Proyek dan Rambu -RambuLs1.00Rp280,000.000.391.00Rp280,000.000.390.00.00.01.00Rp280,000.000.39100.00COMPLETED$3PembersihanLs1.00Rp450,000.000.621.00Rp450,000.000.620.00.00.01.00Rp450,000.000.62100.00COMPLETED$4Pematokan/pengukuran (setting out)Ls1.00Rp500,000.000.691.00Rp500,000.000.690.00.00.01.00Rp500,000.000.69100.00COMPLETED$5Mobilisasi dan DemobilisasiLs1.00Rp250,000.000.351.00Rp250,000.000.350.00.00.01.00Rp250,000.000.35100.00COMPLETED$6Administrasi Dokumentasi dan as built drawingLs1.00Rp1,000,000.001.380.50Rp500,000.000.690.00.00.00.50Rp500,000.000.6950.00ON PROGRESSIIPENGADAAN PIPA DAN ACCESSORIES$1Pengadaan PipaPengadaan Pipa-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp33,734,800.0046.61451.00Rp33,734,800.0046.610.00.00.0451.00Rp33,734,800.0046.61100.00COMPLETED-Pipa GIP dia.100 mmPipa GIP dia.100 mmM'12.00Rp2,640,000.003.6512.00Rp2,640,000.003.650.00.00.012.00Rp2,640,000.003.65100.00COMPLETED-Pipa GIP dia.50 mmPipa GIP dia.50 mmM'5.00Rp620,000.000.865.00Rp620,000.000.860.00.00.05.00Rp620,000.000.86100.00COMPLETED$2Pengadaan Accessories-Bend All Socket PVC RRJ Dia. 100 x 90bh2.00Rp316,000.000.442.00Rp316,000.000.440.00.00.02.00Rp316,000.000.44100.00COMPLETED-Bend All Socket PVC RRJ Dia. 100 x 45bh1.00Rp145,300.000.201.00Rp145,300.000.200.00.00.01.00Rp145,300.000.20100.00COMPLETED-Flange Socket PVC RRJ Dia. 100 mmbh7.00Rp4,092,018.005.657.00Rp4,092,018.005.650.00.00.07.00Rp4,092,018.005.65100.00COMPLETED-Flange Socket PVC RRJ Dia. 50 mmbh2.00Rp349,000.000.482.00Rp349,000.000.480.00.00.02.00Rp349,000.000.48100.00COMPLETED-Tee All socket Dia 100 x 100 mmbh1.00Rp303,300.000.421.00Rp303,300.000.420.00.00.01.00Rp303,300.000.42100.00COMPLETED-Reducer Socket Dia 100 x 50 mmbh1.00Rp112,850.000.161.00Rp112,850.000.160.00.00.01.00Rp112,850.000.16100.00COMPLETED-Bend All Socket PVC RRJ Dia. 50 x 90bh1.00Rp50,550.000.071.00Rp50,550.000.070.00.00.01.00Rp50,550.000.07100.00COMPLETED-Dop PVC dia.100 mmbh1.00Rp171,175.000.241.00Rp171,175.000.240.00.00.01.00Rp171,175.000.24100.00COMPLETED-Bend GIP Dia 100 x 90 mmbh1.00Rp180,000.000.251.00Rp180,000.000.250.00.00.01.00Rp180,000.000.25100.00COMPLETED-Bend GIP Dia 100 x 45 mmbh4.00Rp620,000.000.864.00Rp620,000.000.860.00.00.04.00Rp620,000.000.86100.00COMPLETED-Bend GIP Dia 50 x 90 mmbh2.00Rp190,000.000.262.00Rp190,000.000.260.00.00.02.00Rp190,000.000.26100.00COMPLETED-Loss Flange GIP Dia 100 mmbh5.00Rp560,000.000.775.00Rp560,000.000.770.00.00.05.00Rp560,000.000.77100.00COMPLETED-Loss Flange GIP Dia 50 mmbh2.00Rp162,000.000.222.00Rp162,000.000.220.00.00.02.00Rp162,000.000.22100.00COMPLETED-Tee Gip 100 x 50 mmbh1.00Rp215,000.000.301.00Rp215,000.000.300.00.00.01.00Rp215,000.000.30100.00COMPLETED-Gate Valve 4"bh2.00Rp3,000,000.004.152.00Rp3,000,000.004.150.00.00.02.00Rp3,000,000.004.15100.00COMPLETED-Saringan/Besi Dia 4 "bh1.00Rp75,000.000.101.00Rp75,000.000.100.00.00.01.00Rp75,000.000.10100.00COMPLETED-Bautbh80.00Rp600,000.000.8380.00Rp600,000.000.830.00.00.080.00Rp600,000.000.83100.00COMPLETED-Pakingbh10.00Rp115,000.000.1610.00Rp115,000.000.160.00.00.010.00Rp115,000.000.16100.00COMPLETEDIIIPEKERJAAN PEMASANGAN PIPA DAN ACESSORIES$1Pekerjaan Tanah-Galian Tanah KerasM3108.24Rp4,663,520.406.440.00.00.0108.24Rp4,663,520.406.44108.24Rp4,663,520.406.44100.00COMPLETED-Urugan KembaliM3104.60Rp1,384,062.571.910.00.00.030.00Rp396,960.000.5530.00Rp396,960.000.5528.68ON PROGRESS$2Pemasangan Pipa Termasuk Fitting dan Valve-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp8,392,208.0011.600.00.00.0100.00Rp1,860,800.002.57100.00Rp1,860,800.002.5722.17ON PROGRESS-Pipa GIP dia.100 mmM'12.00Rp572,425.150.790.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.50 mmM'5.00Rp130,904.600.180.00.00.00.00.00.00.00.00.00.0DELAYED-Pengecatan permukaan baja secara manual sistem 2 lapisM24.55Rp72,529.150.100.00.00.00.00.00.00.00.00.00.0DELAYEDIVPEKERJAAN LAIN-LAIN$1Crossing Pipa/ BoringM'6.00Rp900,000.001.240.00.00.00.00.00.00.00.00.00.0DELAYED$2Rekondisi Jalan/FinishingLs1.00Rp200,000.000.280.00.00.00.00.00.00.00.00.00.0DELAYED$3Rekondisi Jalan (Rabat Beton)M30.02Rp9,396.280.010.00.00.00.00.00.00.00.00.00.0DELAYED$4Uji Laboratorium Baku Mutu Kualitas Air BersihLs1.00Rp750,000.001.040.00.00.00.00.00.00.00.00.00.0DELAYED$5Street BoxLs2.00Rp1,600,000.002.210.00.00.00.00.00.00.00.00.00.0DELAYEDVPEKERJAAN REHAP INTAKE$1PEKERJAAN TANAH & PONDASIGalian Tanah PondasiM31.00Rp4,589.550.010.00.00.00.00.00.00.00.00.00.0DELAYEDUrugan Pasir Bawah PondasiM30.02Rp1,713.120.000.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu Gunung 1 : 3M31.00Rp277,037.340.380.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu KosongM32.00Rp6,419.820.010.00.00.00.00.00.00.00.00.00.0DELAYEDTanah TimbunanM31.00Rp1,088,542.181.500.00.00.00.00.00.00.00.00.00.0DELAYEDLantai Beton Cor 1Pc : 1,5Ps : 2,5Kr, T=10 cmM30.02Rp966,777.351.340.00.00.00.00.00.00.00.00.00.0DELAYEDPlasteran 1pc : 2 psM21.00Rp229,752.660.320.00.00.00.00.00.00.00.00.00.0DELAYEDJUMLAHRp72,371,871.18100.00Rp50,621,993.0069.95Rp6,921,280.4019.56Rp57,543,273.4079.51SISA PROGRESSPPn10%Rp7,237,187.12Rp5,062,199.30Rp692,128.040Rp5,754,327.34GRAND TOTALRp79,609,058.30Rp55,684,192.30Rp7,613,408.442Rp63,297,600.7420.49%DIBULATKANRp79,609,000.00Rp55,684,000.00Rp7,613,000.00Rp63,297,000.00Disetujui Oleh :Diperiksa Oleh :Dibuat Oleh :Pejabat Pelaksana Teknis Kegiatan (PPTK)Konsultan SupervisiKontraktor PelaksanaDinas Cipta Karya Aceh BesarCV. SCALA DESIGNCV. TUAH BARUSAMUHAMMAD IKHSAN,ST.MTHERI DERMAWAN,STIRSANNIP. 19740407 200212 1 007InspectorDirektur

M.2.1 (7)LAPORAN KEMAJUAN PEKERJAANMINGGU KE :7 (TUJUH)PERIODE :24 SEPTEMBER 2014 S/D 30 SEPTEMBER 2014PEKERJAAN:PEMASANGAN PIPANISASI AIR BERSIH GP. ALUE RINDANG KEC. SEULIMEUM (DAU)PROGRESS85.59%LOKASI:KEC. SEULIMEUMKONTRAKTOR PELAKSANA:CV. TUAH BARUSARENCANAJANGKA WAKTU PELAKSANAAN:90 HariNO. KONTRAK:26/SPK/PL.P-PERKIM/BMCK/2014PROGRESS82.63%NILAI KONTRAK AWAL:Rp79,609,000TANGGAL KONTRAK:06 AGUSTUS 2014ACTUALSUMBER DANA:APBKKONSULTAN PENGAWAS:CV. SCALA DESIGNDEVIASI-2.96%TAHUNANGGARAN:2014NO. KONTRAK:0.0TANGGAL KONTRAK:0.0DELAYEDON PROGRESSON PROGRESSON PROGRESSDELAYEDON PROGRESSON PROGRESSON PROGRESSNO.URAIANSAT.KONTRAK AWALMINGGU LALUMINGGU INIREALISASI PEKER. S/D MINGGU INIKET.QTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotPrestasi( Rp. )( % )( Rp. )( % )(Rp.)( % )( Rp. )( % )(%)abcdefghijklm =(g+j)n =(h+k)o =(i+l)pqIPEKERJAAN PERSIAPAN$1Direksi Keet / Gudang (Sewa)Ls1.00Rp390,000.000.541.00Rp390,000.000.540.00.00.01.00Rp390,000.000.54100.00COMPLETED$2Papan Nama Proyek dan Rambu -RambuLs1.00Rp280,000.000.391.00Rp280,000.000.390.00.00.01.00Rp280,000.000.39100.00COMPLETED$3PembersihanLs1.00Rp450,000.000.621.00Rp450,000.000.620.00.00.01.00Rp450,000.000.62100.00COMPLETED$4Pematokan/pengukuran (setting out)Ls1.00Rp500,000.000.691.00Rp500,000.000.690.00.00.01.00Rp500,000.000.69100.00COMPLETED$5Mobilisasi dan DemobilisasiLs1.00Rp250,000.000.351.00Rp250,000.000.350.00.00.01.00Rp250,000.000.35100.00COMPLETED$6Administrasi Dokumentasi dan as built drawingLs1.00Rp1,000,000.001.380.50Rp500,000.000.690.00.00.00.50Rp500,000.000.6950.00ON PROGRESSIIPENGADAAN PIPA DAN ACCESSORIES$1Pengadaan PipaPengadaan Pipa-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp33,734,800.0046.61451.00Rp33,734,800.0046.610.00.00.0451.00Rp33,734,800.0046.61100.00COMPLETED-Pipa GIP dia.100 mmPipa GIP dia.100 mmM'12.00Rp2,640,000.003.6512.00Rp2,640,000.003.650.00.00.012.00Rp2,640,000.003.65100.00COMPLETED-Pipa GIP dia.50 mmPipa GIP dia.50 mmM'5.00Rp620,000.000.865.00Rp620,000.000.860.00.00.05.00Rp620,000.000.86100.00COMPLETED$2Pengadaan Accessories-Bend All Socket PVC RRJ Dia. 100 x 90bh2.00Rp316,000.000.442.00Rp316,000.000.440.00.00.02.00Rp316,000.000.44100.00COMPLETED-Bend All Socket PVC RRJ Dia. 100 x 45bh1.00Rp145,300.000.201.00Rp145,300.000.200.00.00.01.00Rp145,300.000.20100.00COMPLETED-Flange Socket PVC RRJ Dia. 100 mmbh7.00Rp4,092,018.005.657.00Rp4,092,018.005.650.00.00.07.00Rp4,092,018.005.65100.00COMPLETED-Flange Socket PVC RRJ Dia. 50 mmbh2.00Rp349,000.000.482.00Rp349,000.000.480.00.00.02.00Rp349,000.000.48100.00COMPLETED-Tee All socket Dia 100 x 100 mmbh1.00Rp303,300.000.421.00Rp303,300.000.420.00.00.01.00Rp303,300.000.42100.00COMPLETED-Reducer Socket Dia 100 x 50 mmbh1.00Rp112,850.000.161.00Rp112,850.000.160.00.00.01.00Rp112,850.000.16100.00COMPLETED-Bend All Socket PVC RRJ Dia. 50 x 90bh1.00Rp50,550.000.071.00Rp50,550.000.070.00.00.01.00Rp50,550.000.07100.00COMPLETED-Dop PVC dia.100 mmbh1.00Rp171,175.000.241.00Rp171,175.000.240.00.00.01.00Rp171,175.000.24100.00COMPLETED-Bend GIP Dia 100 x 90 mmbh1.00Rp180,000.000.251.00Rp180,000.000.250.00.00.01.00Rp180,000.000.25100.00COMPLETED-Bend GIP Dia 100 x 45 mmbh4.00Rp620,000.000.864.00Rp620,000.000.860.00.00.04.00Rp620,000.000.86100.00COMPLETED-Bend GIP Dia 50 x 90 mmbh2.00Rp190,000.000.262.00Rp190,000.000.260.00.00.02.00Rp190,000.000.26100.00COMPLETED-Loss Flange GIP Dia 100 mmbh5.00Rp560,000.000.775.00Rp560,000.000.770.00.00.05.00Rp560,000.000.77100.00COMPLETED-Loss Flange GIP Dia 50 mmbh2.00Rp162,000.000.222.00Rp162,000.000.220.00.00.02.00Rp162,000.000.22100.00COMPLETED-Tee Gip 100 x 50 mmbh1.00Rp215,000.000.301.00Rp215,000.000.300.00.00.01.00Rp215,000.000.30100.00COMPLETED-Gate Valve 4"bh2.00Rp3,000,000.004.152.00Rp3,000,000.004.150.00.00.02.00Rp3,000,000.004.15100.00COMPLETED-Saringan/Besi Dia 4 "bh1.00Rp75,000.000.101.00Rp75,000.000.100.00.00.01.00Rp75,000.000.10100.00COMPLETED-Bautbh80.00Rp600,000.000.8380.00Rp600,000.000.830.00.00.080.00Rp600,000.000.83100.00COMPLETED-Pakingbh10.00Rp115,000.000.1610.00Rp115,000.000.160.00.00.010.00Rp115,000.000.16100.00COMPLETEDIIIPEKERJAAN PEMASANGAN PIPA DAN ACESSORIES$1Pekerjaan Tanah-Galian Tanah KerasM3108.24Rp4,663,520.406.44108.24Rp4,663,520.406.440.00.00.0108.24Rp4,663,520.406.44100.00COMPLETED-Urugan KembaliM3104.60Rp1,384,062.571.9130.00Rp396,960.000.5530.00Rp396,960.000.5560.00Rp793,920.001.1057.36ON PROGRESS$2Pemasangan Pipa Termasuk Fitting dan Valve-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp8,392,208.0011.60100.00Rp1,860,800.002.57100.00Rp1,860,800.002.57200.00Rp3,721,600.005.1444.35ON PROGRESS-Pipa GIP dia.100 mmM'12.00Rp572,425.150.790.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.50 mmM'5.00Rp130,904.600.180.00.00.00.00.00.00.00.00.00.0DELAYED-Pengecatan permukaan baja secara manual sistem 2 lapisM24.55Rp72,529.150.100.00.00.00.00.00.00.00.00.00.0DELAYEDIVPEKERJAAN LAIN-LAIN$1Crossing Pipa/ BoringM'6.00Rp900,000.001.240.00.00.00.00.00.00.00.00.00.0DELAYED$2Rekondisi Jalan/FinishingLs1.00Rp200,000.000.280.00.00.00.00.00.00.00.00.00.0DELAYED$3Rekondisi Jalan (Rabat Beton)M30.02Rp9,396.280.010.00.00.00.00.00.00.00.00.00.0DELAYED$4Uji Laboratorium Baku Mutu Kualitas Air BersihLs1.00Rp750,000.001.040.00.00.00.00.00.00.00.00.00.0DELAYED$5Street BoxLs2.00Rp1,600,000.002.210.00.00.00.00.00.00.00.00.00.0DELAYEDVPEKERJAAN REHAP INTAKE$1PEKERJAAN TANAH & PONDASIGalian Tanah PondasiM31.00Rp4,589.550.010.00.00.00.00.00.00.00.00.00.0DELAYEDUrugan Pasir Bawah PondasiM30.02Rp1,713.120.000.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu Gunung 1 : 3M31.00Rp277,037.340.380.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu KosongM32.00Rp6,419.820.010.00.00.00.00.00.00.00.00.00.0DELAYEDTanah TimbunanM31.00Rp1,088,542.181.500.00.00.00.00.00.00.00.00.00.0DELAYEDLantai Beton Cor 1Pc : 1,5Ps : 2,5Kr, T=10 cmM30.02Rp966,777.351.340.00.00.00.00.00.00.00.00.00.0DELAYEDPlasteran 1pc : 2 psM21.00Rp229,752.660.320.00.00.00.00.00.00.00.00.00.0DELAYEDJUMLAHRp72,371,871.18100.00Rp57,543,273.4079.51Rp2,257,760.0013.12Rp59,801,033.4082.63SISA PROGRESSPPn10%Rp7,237,187.12Rp5,754,327.34Rp225,776.000Rp5,980,103.34GRAND TOTALRp79,609,058.30Rp63,297,600.74Rp2,483,536.002Rp65,781,136.7417.37%DIBULATKANRp79,609,000.00Rp63,297,000.00Rp2,483,000.00Rp65,781,000.00Disetujui Oleh :Diperiksa Oleh :Dibuat Oleh :Pejabat Pelaksana Teknis Kegiatan (PPTK)Konsultan SupervisiKontraktor PelaksanaDinas Cipta Karya Aceh BesarCV. SCALA DESIGNCV. TUAH BARUSAMUHAMMAD IKHSAN,ST.MTHERI DERMAWAN,STIRSANNIP. 19740407 200212 1 007InspectorDirektur

B2LAPORAN KEMAJUAN PEKERJAANBULAN KE :2 (DUA)PERIODE :01 SEPTEMBER 2014 S/D 30 SEPTEMBER 2014PEKERJAAN:PEMASANGAN PIPANISASI AIR BERSIH GP. ALUE RINDANG KEC. SEULIMEUM (DAU)PROGRESS85.59%LOKASI:KEC. SEULIMEUMKONTRAKTOR PELAKSANA:CV. TUAH BARUSARENCANAJANGKA WAKTU PELAKSANAAN:90 HariNO. KONTRAK:26/SPK/PL.P-PERKIM/BMCK/2014PROGRESS82.63%NILAI KONTRAK AWAL:Rp79,609,000TANGGAL KONTRAK:06 AGUSTUS 2014ACTUALSUMBER DANA:APBKKONSULTAN PENGAWAS:CV. SCALA DESIGNDEVIASI-2.96%TAHUNANGGARAN:2014NO. KONTRAK:0.0TANGGAL KONTRAK:0.0DELAYEDON PROGRESSON PROGRESSON PROGRESSDELAYEDON PROGRESSON PROGRESSON PROGRESSNO.URAIANSAT.KONTRAK AWALBULAN LALUBULAN INIREALISASI PEKER. S/D BULAN INIKET.QTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotPrestasi( Rp. )( % )( Rp. )( % )(Rp.)( % )( Rp. )( % )(%)abcdefghijklm =(g+j)n =(h+k)o =(i+l)pqIPEKERJAAN PERSIAPAN$1Direksi Keet / Gudang (Sewa)Ls1.00Rp390,000.000.541.00Rp390,000.000.540.00.00.01.00Rp390,000.000.54100.00COMPLETED0.0$2Papan Nama Proyek dan Rambu -RambuLs1.00Rp280,000.000.391.00Rp280,000.000.390.00.00.01.00Rp280,000.000.39100.00COMPLETEDRp31,384,593.00$3PembersihanLs1.00Rp450,000.000.621.00Rp450,000.000.620.00.00.01.00Rp450,000.000.62100.00COMPLETEDRp9,179,040.40$4Pematokan/pengukuran (setting out)Ls1.00Rp500,000.000.691.00Rp500,000.000.690.00.00.01.00Rp500,000.000.69100.00COMPLETED0.0$5Mobilisasi dan DemobilisasiLs1.00Rp250,000.000.351.00Rp250,000.000.350.00.00.01.00Rp250,000.000.35100.00COMPLETED0.0$6Administrasi Dokumentasi dan as built drawingLs1.00Rp1,000,000.001.380.50Rp500,000.000.690.00.00.00.50Rp500,000.000.6950.00ON PROGRESSIIPENGADAAN PIPA DAN ACCESSORIES$1Pengadaan PipaPengadaan Pipa-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp33,734,800.0046.61225.50Rp16,867,400.0023.31225.50Rp16,867,400.0023.31451.00Rp33,734,800.0046.61100.00COMPLETED43.3766.67(23.31)-Pipa GIP dia.100 mmPipa GIP dia.100 mmM'12.00Rp2,640,000.003.650.00.00.012.00Rp2,640,000.003.6512.00Rp2,640,000.003.65100.00COMPLETED-Pipa GIP dia.50 mmPipa GIP dia.50 mmM'5.00Rp620,000.000.860.00.00.05.00Rp620,000.000.865.00Rp620,000.000.86100.00COMPLETED$2Pengadaan Accessories-Bend All Socket PVC RRJ Dia. 100 x 90bh2.00Rp316,000.000.440.00.00.02.00Rp316,000.000.442.00Rp316,000.000.44100.00COMPLETED48,251,993.00-Bend All Socket PVC RRJ Dia. 100 x 45bh1.00Rp145,300.000.200.00.00.01.00Rp145,300.000.201.00Rp145,300.000.20100.00COMPLETED-Flange Socket PVC RRJ Dia. 100 mmbh7.00Rp4,092,018.005.650.00.00.07.00Rp4,092,018.005.657.00Rp4,092,018.005.65100.00COMPLETED-Flange Socket PVC RRJ Dia. 50 mmbh2.00Rp349,000.000.480.00.00.02.00Rp349,000.000.482.00Rp349,000.000.48100.00COMPLETED-Tee All socket Dia 100 x 100 mmbh1.00Rp303,300.000.420.00.00.01.00Rp303,300.000.421.00Rp303,300.000.42100.00COMPLETED-Reducer Socket Dia 100 x 50 mmbh1.00Rp112,850.000.160.00.00.01.00Rp112,850.000.161.00Rp112,850.000.16100.00COMPLETED-Bend All Socket PVC RRJ Dia. 50 x 90bh1.00Rp50,550.000.070.00.00.01.00Rp50,550.000.071.00Rp50,550.000.07100.00COMPLETED-Dop PVC dia.100 mmbh1.00Rp171,175.000.240.00.00.01.00Rp171,175.000.241.00Rp171,175.000.24100.00COMPLETED-Bend GIP Dia 100 x 90 mmbh1.00Rp180,000.000.250.00.00.01.00Rp180,000.000.251.00Rp180,000.000.25100.00COMPLETED-Bend GIP Dia 100 x 45 mmbh4.00Rp620,000.000.860.00.00.04.00Rp620,000.000.864.00Rp620,000.000.86100.00COMPLETED-Bend GIP Dia 50 x 90 mmbh2.00Rp190,000.000.260.00.00.02.00Rp190,000.000.262.00Rp190,000.000.26100.00COMPLETED-Loss Flange GIP Dia 100 mmbh5.00Rp560,000.000.770.00.00.05.00Rp560,000.000.775.00Rp560,000.000.77100.00COMPLETED-Loss Flange GIP Dia 50 mmbh2.00Rp162,000.000.220.00.00.02.00Rp162,000.000.222.00Rp162,000.000.22100.00COMPLETED-Tee Gip 100 x 50 mmbh1.00Rp215,000.000.300.00.00.01.00Rp215,000.000.301.00Rp215,000.000.30100.00COMPLETED-Gate Valve 4"bh2.00Rp3,000,000.004.150.00.00.02.00Rp3,000,000.004.152.00Rp3,000,000.004.15100.00COMPLETED-Saringan/Besi Dia 4 "bh1.00Rp75,000.000.100.00.00.01.00Rp75,000.000.101.00Rp75,000.000.10100.00COMPLETED-Bautbh80.00Rp600,000.000.830.00.00.080.00Rp600,000.000.8380.00Rp600,000.000.83100.00COMPLETED-Pakingbh10.00Rp115,000.000.160.00.00.010.00Rp115,000.000.1610.00Rp115,000.000.16100.00COMPLETEDIIIPEKERJAAN PEMASANGAN PIPA DAN ACESSORIES$1Pekerjaan Tanah-Galian Tanah KerasM3108.24Rp4,663,520.406.440.00.00.0108.24Rp4,663,520.406.44108.24Rp4,663,520.406.44100.00COMPLETED-Urugan KembaliM3104.60Rp1,384,062.571.910.00.00.060.00Rp793,920.001.1060.00Rp793,920.001.1057.36ON PROGRESS$2Pemasangan Pipa Termasuk Fitting dan Valve-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp8,392,208.0011.600.00.00.0200.00Rp3,721,600.005.14200.00Rp3,721,600.005.1444.35ON PROGRESS-Pipa GIP dia.100 mmM'12.00Rp572,425.150.790.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.50 mmM'5.00Rp130,904.600.180.00.00.00.00.00.00.00.00.00.0DELAYED-Pengecatan permukaan baja secara manual sistem 2 lapisM24.55Rp72,529.150.100.00.00.00.00.00.00.00.00.00.0DELAYEDIVPEKERJAAN LAIN-LAIN$1Crossing Pipa/ BoringM'6.00Rp900,000.001.240.00.00.00.00.00.00.00.00.00.0DELAYED$2Rekondisi Jalan/FinishingLs1.00Rp200,000.000.280.00.00.00.00.00.00.00.00.00.0DELAYED$3Rekondisi Jalan (Rabat Beton)M30.02Rp9,396.280.010.00.00.00.00.00.00.00.00.00.0DELAYED$4Uji Laboratorium Baku Mutu Kualitas Air BersihLs1.00Rp750,000.001.040.00.00.00.00.00.00.00.00.00.0DELAYED$5Street BoxLs2.00Rp1,600,000.002.210.00.00.00.00.00.00.00.00.00.0DELAYEDVPEKERJAAN REHAP INTAKE$1PEKERJAAN TANAH & PONDASIGalian Tanah PondasiM31.00Rp4,589.550.010.00.00.00.00.00.00.00.00.00.0DELAYEDUrugan Pasir Bawah PondasiM30.02Rp1,713.120.000.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu Gunung 1 : 3M31.00Rp277,037.340.380.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu KosongM32.00Rp6,419.820.010.00.00.00.00.00.00.00.00.00.0DELAYEDTanah TimbunanM31.00Rp1,088,542.181.500.00.00.00.00.00.00.00.00.00.0DELAYEDLantai Beton Cor 1Pc : 1,5Ps : 2,5Kr, T=10 cmM30.02Rp966,777.351.340.00.00.00.00.00.00.00.00.00.0DELAYEDPlasteran 1pc : 2 psM21.00Rp229,752.660.320.00.00.00.00.00.00.00.00.00.0DELAYEDJUMLAHRp72,371,871.18100.00Rp19,237,400.0026.58Rp40,563,633.40356.05Rp59,801,033.4082.63SISA PROGRESSPPn10%Rp7,237,187.12Rp1,923,740.00Rp4,056,363.340Rp5,980,103.34GRAND TOTALRp79,609,058.30Rp21,161,140.00Rp44,619,996.743Rp65,781,136.7417.37%DIBULATKANRp79,609,000.00Rp21,161,000.00Rp44,619,000.00Rp65,781,000.00Disetujui Oleh :Diperiksa Oleh :Dibuat Oleh :82.63Pejabat Pelaksana Teknis Kegiatan (PPTK)Konsultan SupervisiKontraktor PelaksanaDinas Cipta Karya Aceh BesarCV. SCALA DESIGNCV. TUAH BARUSAMUHAMMAD IKHSAN,ST.MTHERI DERMAWAN,STIRSANNIP. 19740407 200212 1 007InspectorDirektur

s2SERTIFIKAT KE - IIKegiatan:PEMBANGUNAN SARANA DAN PRASARANA AIR BERSIH PEDESAAN (DAK)Kontraktor:CV. TUAH BARUSANama Paket:PEMASANGAN PIPANISASI AIR BERSIH GP. ALUE RINDANG KEC. SEULIMEUM (DAU)Konsultan Pengawas:CV SCALA DESAINNo. Kontrak/Tanggal:26/SPK/PL.P-PERKIM/BMCK/2014Tanggal:30 SEPTEMBER 2014No. Addendum/Tgl:Sertifikat Ke:II (Dua)Tahun Anggaran:2014NOURAIAN PEKERJAANKONTRAK AWALJUMLAH PEMBAYARANS.D YANG LALUSAAT INIS.D SAAT INI(Rp)%(Rp)%(Rp)%(Rp)%127IPEKERJAAN PERSIAPAN2,870,000.003.972,370,000.003.270.00.02,370,000.003.27IIPENGADAAN PIPA DAN ACCESSORIES48,251,993.0066.6716,867,400.0023.3131,384,593.0043.3748,251,993.0066.67IIIPEKERJAAN PEMASANGAN PIPA DAN ACESSORIES15,215,649.8821.020.00.09,179,040.4012.689,179,040.4012.68IVPEKERJAAN LAIN-LAIN3,459,396.284.780.00.00.00.00.00.0VPEKERJAAN REHAB. INTAKE2,574,832.023.560.00.0AJUMLAH72,371,878.18100.0019,237,400.0026.5840,563,633.4056.0559,801,033.4082.6382.63PPN 10%7,237,187.821,923,740.004,056,363.345,980,103.34TOTAL79,609,066.0021,161,140.0044,619,996.7465,781,136.74DIBULATKAN79,609,000.0021,161,000.0044,619,000.0065,781,000.00BNILAI SERTIFIKAT S.D. BULAN INI65,781,000.0082.63CNILAI SERTIFIKAT S.D. BULAN LALU21,161,000.0026.58DNILAI SERTIFIKAT BULAN INI (item B - item C)44,620,000.0056.05POTONGAN-POTONGANE1. JAMINAN PEMELIHARAAN (5% dari item D)0.0F2. PENGEMBALIAN UANG MUKA (30% dari item D)0.0GTOTAL POTONGAN (item E + item F)0.0HNILAI BERSIH SERTIFIKAT BULAN INI SEBELUM PAJAK (item D - item G)44,620,000.00INILAI BERSIH SERTIFIKAT S.D. BULAN INI DIPOTONG PAJAK ((100/110) x item H)40,563,636.36DIBULATKAN40,564,000.00Terbilang:Empat Puluh Juta Lima Ratus Enam Puluh Empat Ribu RupiahPROGRESS DICAPAIS.D. BULAN INI:82.63%S.D. BULAN LALU:26.58%BULAN INI:56.05%Aceh Besar, 30 September 2014Mengetahui/Disetujui Oleh:Disetujui OlehDiperiksa Oleh:Diajukan Oleh:Kuasa Pengguna Anggaran Bidang PerumahanPejabat Pelaksana Teknis Kegiatan (PPTK)Konsultan SupervisiKontraktor PelaksanaAir Bersih dan Prasarana PermukimanDinas Cipta Karya Aceh BesarCV. SCALA DESAINCV. TUAH BARUSANAZARUL KHAIRI, ST.MT.MUHAMMAD IKHSAN,ST.MTFAKHRUDDIN, STIRSANNip. 19690601 200012 1 010NIP. 19740407 200212 1 007DirekturDirekturTerjemahan kedalam kalimat40,564,000.001satu dua tiga empat lima enam tujuh delapan sembilan sepuluhribu juta milyar triliyun000040564000basic @0001perhitungan @0angka @0sepuluh@00@0@00@0@@@5642@5enam puluh@lima ratusempat belas@6empat@4enam puluh empat@enam puluh empatenam puluh empat@lima ratus enam puluh empat ribu@@@0403@0empat puluh@0sepuluh@40@0empat puluh@empat puluhempat puluh@empat puluh juta@@@0004@0@0sepuluh@00@0@00@0@@0001@0@0sepuluh@00@0@00@0@@@05600@empat puluh juta lima ratus enam puluh empat ribu rupiahempat puluh juta lima ratus enam puluh empat ribu rupiah@empat puluh juta lima ratus enam puluh empat ribu rupiah@Empat puluh juta lima ratus enam puluh empat ribu rupiah

M.2.1 (8)LAPORAN KEMAJUAN PEKERJAANMINGGU KE :8 (DELAPAN)PERIODE :01 OKTOBER 2014 S/D 07 OKTOBER 2014PEKERJAAN:PEMASANGAN PIPANISASI AIR BERSIH GP. ALUE RINDANG KEC. SEULIMEUM (DAU)PROGRESS91.67%LOKASI:KEC. SEULIMEUMKONTRAKTOR PELAKSANA:CV. TUAH BARUSARENCANAJANGKA WAKTU PELAKSANAAN:90 HariNO. KONTRAK:26/SPK/PL.P-PERKIM/BMCK/2014PROGRESS86.85%NILAI KONTRAK AWAL:Rp79,609,000TANGGAL KONTRAK:06 AGUSTUS 2014ACTUALSUMBER DANA:APBKKONSULTAN PENGAWAS:CV. SCALA DESIGNDEVIASI-4.82%TAHUNANGGARAN:2014NO. KONTRAK:0.0TANGGAL KONTRAK:0.0DELAYEDON PROGRESSON PROGRESSON PROGRESSDELAYEDON PROGRESSON PROGRESSON PROGRESSNO.URAIANSAT.KONTRAK AWALMINGGU LALUMINGGU INIREALISASI PEKER. S/D MINGGU INIKET.QTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotPrestasi( Rp. )( % )( Rp. )( % )(Rp.)( % )( Rp. )( % )(%)abcdefghijklm =(g+j)n =(h+k)o =(i+l)pqIPEKERJAAN PERSIAPAN$1Direksi Keet / Gudang (Sewa)Ls1.00Rp390,000.000.541.00Rp390,000.000.540.00.00.01.00Rp390,000.000.54100.00COMPLETED$2Papan Nama Proyek dan Rambu -RambuLs1.00Rp280,000.000.391.00Rp280,000.000.390.00.00.01.00Rp280,000.000.39100.00COMPLETED$3PembersihanLs1.00Rp450,000.000.621.00Rp450,000.000.620.00.00.01.00Rp450,000.000.62100.00COMPLETED$4Pematokan/pengukuran (setting out)Ls1.00Rp500,000.000.691.00Rp500,000.000.690.00.00.01.00Rp500,000.000.69100.00COMPLETED$5Mobilisasi dan DemobilisasiLs1.00Rp250,000.000.351.00Rp250,000.000.350.00.00.01.00Rp250,000.000.35100.00COMPLETED$6Administrasi Dokumentasi dan as built drawingLs1.00Rp1,000,000.001.380.50Rp500,000.000.690.00.00.00.50Rp500,000.000.6950.00ON PROGRESSIIPENGADAAN PIPA DAN ACCESSORIES0.0$1Pengadaan PipaPengadaan Pipa-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp33,734,800.0046.61451.00Rp33,734,800.0046.610.00.00.0451.00Rp33,734,800.0046.61100.00COMPLETED-Pipa GIP dia.100 mmPipa GIP dia.100 mmM'12.00Rp2,640,000.003.6512.00Rp2,640,000.003.650.00.00.012.00Rp2,640,000.003.65100.00COMPLETED-Pipa GIP dia.50 mmPipa GIP dia.50 mmM'5.00Rp620,000.000.865.00Rp620,000.000.860.00.00.05.00Rp620,000.000.86100.00COMPLETED$2Pengadaan Accessories-Bend All Socket PVC RRJ Dia. 100 x 90bh2.00Rp316,000.000.442.00Rp316,000.000.440.00.00.02.00Rp316,000.000.44100.00COMPLETED-Bend All Socket PVC RRJ Dia. 100 x 45bh1.00Rp145,300.000.201.00Rp145,300.000.200.00.00.01.00Rp145,300.000.20100.00COMPLETED-Flange Socket PVC RRJ Dia. 100 mmbh7.00Rp4,092,018.005.657.00Rp4,092,018.005.650.00.00.07.00Rp4,092,018.005.65100.00COMPLETED-Flange Socket PVC RRJ Dia. 50 mmbh2.00Rp349,000.000.482.00Rp349,000.000.480.00.00.02.00Rp349,000.000.48100.00COMPLETED-Tee All socket Dia 100 x 100 mmbh1.00Rp303,300.000.421.00Rp303,300.000.420.00.00.01.00Rp303,300.000.42100.00COMPLETED-Reducer Socket Dia 100 x 50 mmbh1.00Rp112,850.000.161.00Rp112,850.000.160.00.00.01.00Rp112,850.000.16100.00COMPLETED-Bend All Socket PVC RRJ Dia. 50 x 90bh1.00Rp50,550.000.071.00Rp50,550.000.070.00.00.01.00Rp50,550.000.07100.00COMPLETED-Dop PVC dia.100 mmbh1.00Rp171,175.000.241.00Rp171,175.000.240.00.00.01.00Rp171,175.000.24100.00COMPLETED-Bend GIP Dia 100 x 90 mmbh1.00Rp180,000.000.251.00Rp180,000.000.250.00.00.01.00Rp180,000.000.25100.00COMPLETED-Bend GIP Dia 100 x 45 mmbh4.00Rp620,000.000.864.00Rp620,000.000.860.00.00.04.00Rp620,000.000.86100.00COMPLETED-Bend GIP Dia 50 x 90 mmbh2.00Rp190,000.000.262.00Rp190,000.000.260.00.00.02.00Rp190,000.000.26100.00COMPLETED-Loss Flange GIP Dia 100 mmbh5.00Rp560,000.000.775.00Rp560,000.000.770.00.00.05.00Rp560,000.000.77100.00COMPLETED-Loss Flange GIP Dia 50 mmbh2.00Rp162,000.000.222.00Rp162,000.000.220.00.00.02.00Rp162,000.000.22100.00COMPLETED-Tee Gip 100 x 50 mmbh1.00Rp215,000.000.301.00Rp215,000.000.300.00.00.01.00Rp215,000.000.30100.00COMPLETED-Gate Valve 4"bh2.00Rp3,000,000.004.152.00Rp3,000,000.004.150.00.00.02.00Rp3,000,000.004.15100.00COMPLETED-Saringan/Besi Dia 4 "bh1.00Rp75,000.000.101.00Rp75,000.000.100.00.00.01.00Rp75,000.000.10100.00COMPLETED-Bautbh80.00Rp600,000.000.8380.00Rp600,000.000.830.00.00.080.00Rp600,000.000.83100.00COMPLETED-Pakingbh10.00Rp115,000.000.1610.00Rp115,000.000.160.00.00.010.00Rp115,000.000.16100.00COMPLETEDIIIPEKERJAAN PEMASANGAN PIPA DAN ACESSORIES$1Pekerjaan Tanah-Galian Tanah KerasM3108.24Rp4,663,520.406.44108.24Rp4,663,520.406.440.00.00.0108.24Rp4,663,520.406.44100.00COMPLETED-Urugan KembaliM3104.60Rp1,384,062.571.9160.00Rp793,920.001.1020.00Rp264,640.000.3780.00Rp1,058,560.001.4676.48ON PROGRESS$2Pemasangan Pipa Termasuk Fitting dan Valve-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp8,392,208.0011.60200.00Rp3,721,600.005.14150.00Rp2,791,200.003.86350.00Rp6,512,800.009.0077.61ON PROGRESS-Pipa GIP dia.100 mmM'12.00Rp572,425.150.790.00.00.00.00.00.00.00.00.00.0DELAYED-Pipa GIP dia.50 mmM'5.00Rp130,904.600.180.00.00.00.00.00.00.00.00.00.0DELAYED-Pengecatan permukaan baja secara manual sistem 2 lapisM24.55Rp72,529.150.100.00.00.00.00.00.00.00.00.00.0DELAYEDIVPEKERJAAN LAIN-LAIN$1Crossing Pipa/ BoringM'6.00Rp900,000.001.240.00.00.00.00.00.00.00.00.00.0DELAYED$2Rekondisi Jalan/FinishingLs1.00Rp200,000.000.280.00.00.00.00.00.00.00.00.00.0DELAYED$3Rekondisi Jalan (Rabat Beton)M30.02Rp9,396.280.010.00.00.00.00.00.00.00.00.00.0DELAYED$4Uji Laboratorium Baku Mutu Kualitas Air BersihLs1.00Rp750,000.001.040.00.00.00.00.00.00.00.00.00.0DELAYED$5Street BoxLs2.00Rp1,600,000.002.210.00.00.00.00.00.00.00.00.00.0DELAYEDVPEKERJAAN REHAP INTAKE$1PEKERJAAN TANAH & PONDASIGalian Tanah PondasiM31.00Rp4,589.550.010.00.00.00.00.00.00.00.00.00.0DELAYEDUrugan Pasir Bawah PondasiM30.02Rp1,713.120.000.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu Gunung 1 : 3M31.00Rp277,037.340.380.00.00.00.00.00.00.00.00.00.0DELAYEDPasangan Batu KosongM32.00Rp6,419.820.010.00.00.00.00.00.00.00.00.00.0DELAYEDTanah TimbunanM31.00Rp1,088,542.181.500.00.00.00.00.00.00.00.00.00.0DELAYEDLantai Beton Cor 1Pc : 1,5Ps : 2,5Kr, T=10 cmM30.02Rp966,777.351.340.00.00.00.00.00.00.00.00.00.0DELAYEDPlasteran 1pc : 2 psM21.00Rp229,752.660.320.00.00.00.00.00.00.00.00.00.0DELAYEDJUMLAHRp72,371,871.18100.00Rp59,801,033.4082.63Rp3,055,840.0014.22Rp62,856,873.4086.85SISA PROGRESSPPn10%Rp7,237,187.12Rp5,980,103.34Rp305,584.000Rp6,285,687.34GRAND TOTALRp79,609,058.30Rp65,781,136.74Rp3,361,424.001Rp69,142,560.7413.15%DIBULATKANRp79,609,000.00Rp65,781,000.00Rp3,361,000.00Rp69,142,000.00Disetujui Oleh :Diperiksa Oleh :Dibuat Oleh :Pejabat Pelaksana Teknis Kegiatan (PPTK)Konsultan SupervisiKontraktor PelaksanaDinas Cipta Karya Aceh BesarCV. SCALA DESIGNCV. TUAH BARUSAMUHAMMAD IKHSAN,ST.MTHERI DERMAWAN,STIRSANNIP. 19740407 200212 1 007InspectorDirektur

M.2.1 (9)LAPORAN KEMAJUAN PEKERJAANMINGGU KE :9 (SEMBILAN)PERIODE :08 OKTOBER 2014 S/D 14 OKTOBER 2014PEKERJAAN:PEMASANGAN PIPANISASI AIR BERSIH GP. ALUE RINDANG KEC. SEULIMEUM (DAU)PROGRESS93.20%LOKASI:KEC. SEULIMEUMKONTRAKTOR PELAKSANA:CV. TUAH BARUSARENCANAJANGKA WAKTU PELAKSANAAN:90 HariNO. KONTRAK:26/SPK/PL.P-PERKIM/BMCK/2014PROGRESS91.32%NILAI KONTRAK AWAL:Rp79,609,000TANGGAL KONTRAK:06 AGUSTUS 2014ACTUALSUMBER DANA:APBKKONSULTAN PENGAWAS:CV. SCALA DESIGNDEVIASI-1.88%TAHUNANGGARAN:2014NO. KONTRAK:0.0TANGGAL KONTRAK:0.0DELAYEDON PROGRESSON PROGRESSON PROGRESSDELAYEDON PROGRESSON PROGRESSON PROGRESSNO.URAIANSAT.KONTRAK AWALMINGGU LALUMINGGU INIREALISASI PEKER. S/D MINGGU INIKET.QTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotPrestasi( Rp. )( % )( Rp. )( % )(Rp.)( % )( Rp. )( % )(%)abcdefghijklm =(g+j)n =(h+k)o =(i+l)pqIPEKERJAAN PERSIAPAN$1Direksi Keet / Gudang (Sewa)Ls1.00Rp390,000.000.541.00Rp390,000.000.540.00.00.01.00Rp390,000.000.54100.00COMPLETED$2Papan Nama Proyek dan Rambu -RambuLs1.00Rp280,000.000.391.00Rp280,000.000.390.00.00.01.00Rp280,000.000.39100.00COMPLETED$3PembersihanLs1.00Rp450,000.000.621.00Rp450,000.000.620.00.00.01.00Rp450,000.000.62100.00COMPLETED$4Pematokan/pengukuran (setting out)Ls1.00Rp500,000.000.691.00Rp500,000.000.690.00.00.01.00Rp500,000.000.69100.00COMPLETED$5Mobilisasi dan DemobilisasiLs1.00Rp250,000.000.351.00Rp250,000.000.350.00.00.01.00Rp250,000.000.35100.00COMPLETED$6Administrasi Dokumentasi dan as built drawingLs1.00Rp1,000,000.001.380.50Rp500,000.000.690.00.00.00.50Rp500,000.000.6950.00ON PROGRESSIIPENGADAAN PIPA DAN ACCESSORIES$1Pengadaan PipaPengadaan Pipa-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp33,734,800.0046.61451.00Rp33,734,800.0046.610.00.00.0451.00Rp33,734,800.0046.61100.00COMPLETED-Pipa GIP dia.100 mmPipa GIP dia.100 mmM'12.00Rp2,640,000.003.6512.00Rp2,640,000.003.650.00.00.012.00Rp2,640,000.003.65100.00COMPLETED-Pipa GIP dia.50 mmPipa GIP dia.50 mmM'5.00Rp620,000.000.865.00Rp620,000.000.860.00.00.05.00Rp620,000.000.86100.00COMPLETED$2Pengadaan Accessories-Bend All Socket PVC RRJ Dia. 100 x 90bh2.00Rp316,000.000.442.00Rp316,000.000.440.00.00.02.00Rp316,000.000.44100.00COMPLETED-Bend All Socket PVC RRJ Dia. 100 x 45bh1.00Rp145,300.000.201.00Rp145,300.000.200.00.00.01.00Rp145,300.000.20100.00COMPLETED-Flange Socket PVC RRJ Dia. 100 mmbh7.00Rp4,092,018.005.657.00Rp4,092,018.005.650.00.00.07.00Rp4,092,018.005.65100.00COMPLETED-Flange Socket PVC RRJ Dia. 50 mmbh2.00Rp349,000.000.482.00Rp349,000.000.480.00.00.02.00Rp349,000.000.48100.00COMPLETED-Tee All socket Dia 100 x 100 mmbh1.00Rp303,300.000.421.00Rp303,300.000.420.00.00.01.00Rp303,300.000.42100.00COMPLETED-Reducer Socket Dia 100 x 50 mmbh1.00Rp112,850.000.161.00Rp112,850.000.160.00.00.01.00Rp112,850.000.16100.00COMPLETED-Bend All Socket PVC RRJ Dia. 50 x 90bh1.00Rp50,550.000.071.00Rp50,550.000.070.00.00.01.00Rp50,550.000.07100.00COMPLETED-Dop PVC dia.100 mmbh1.00Rp171,175.000.241.00Rp171,175.000.240.00.00.01.00Rp171,175.000.24100.00COMPLETED-Bend GIP Dia 100 x 90 mmbh1.00Rp180,000.000.251.00Rp180,000.000.250.00.00.01.00Rp180,000.000.25100.00COMPLETED-Bend GIP Dia 100 x 45 mmbh4.00Rp620,000.000.864.00Rp620,000.000.860.00.00.04.00Rp620,000.000.86100.00COMPLETED-Bend GIP Dia 50 x 90 mmbh2.00Rp190,000.000.262.00Rp190,000.000.260.00.00.02.00Rp190,000.000.26100.00COMPLETED-Loss Flange GIP Dia 100 mmbh5.00Rp560,000.000.775.00Rp560,000.000.770.00.00.05.00Rp560,000.000.77100.00COMPLETED-Loss Flange GIP Dia 50 mmbh2.00Rp162,000.000.222.00Rp162,000.000.220.00.00.02.00Rp162,000.000.22100.00COMPLETED-Tee Gip 100 x 50 mmbh1.00Rp215,000.000.301.00Rp215,000.000.300.00.00.01.00Rp215,000.000.30100.00COMPLETED-Gate Valve 4"bh2.00Rp3,000,000.004.152.00Rp3,000,000.004.150.00.00.02.00Rp3,000,000.004.15100.00COMPLETED-Saringan/Besi Dia 4 "bh1.00Rp75,000.000.101.00Rp75,000.000.100.00.00.01.00Rp75,000.000.10100.00COMPLETED-Bautbh80.00Rp600,000.000.8380.00Rp600,000.000.830.00.00.080.00Rp600,000.000.83100.00COMPLETED-Pakingbh10.00Rp115,000.000.1610.00Rp115,000.000.160.00.00.010.00Rp115,000.000.16100.00COMPLETEDIIIPEKERJAAN PEMASANGAN PIPA DAN ACESSORIES$1Pekerjaan Tanah-Galian Tanah KerasM3108.24Rp4,663,520.406.44108.24Rp4,663,520.406.440.00.00.0108.24Rp4,663,520.406.44100.00COMPLETED-Urugan KembaliM3104.60Rp1,384,062.571.9180.00Rp1,058,560.001.4624.60Rp325,502.570.45104.60Rp1,384,062.571.91100.00COMPLETED$2Pemasangan Pipa Termasuk Fitting dan Valve-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp8,392,208.0011.60350.00Rp6,512,800.009.00101.00Rp1,879,408.002.60451.00Rp8,392,208.0011.60100.00COMPLETED-Pipa GIP dia.100 mmM'12.00Rp572,425.150.790.00.00.012.00Rp572,425.150.7912.00Rp572,425.150.79100.00COMPLETED-Pipa GIP dia.50 mmM'5.00Rp130,904.600.180.00.00.05.00Rp130,904.600.185.00Rp130,904.600.18100.00COMPLETED-Pengecatan permukaan baja secara manual sistem 2 lapisM24.55Rp72,529.150.100.00.00.02.28Rp36,264.580.052.28Rp36,264.580.0550.00ON PROGRESSIVPEKERJAAN LAIN-LAIN$1Crossing Pipa/ BoringM'6.00Rp900,000.001.240.00.00.00.00.00.00.00.00.00.0DELAYED$2Rekondisi Jalan/FinishingLs1.00Rp200,000.000.280.00.00.00.00.00.00.00.00.00.0DELAYED$3Rekondisi Jalan (Rabat Beton)M30.02Rp9,396.280.010.00.00.00.00.00.00.00.00.00.0DELAYED$4Uji Laboratorium Baku Mutu Kualitas Air BersihLs1.00Rp750,000.001.040.00.00.00.00.00.00.00.00.00.0DELAYED$5Street BoxLs2.00Rp1,600,000.002.210.00.00.00.00.00.00.00.00.00.0DELAYEDVPEKERJAAN REHAP INTAKE$1PEKERJAAN TANAH & PONDASIGalian Tanah PondasiM31.00Rp4,589.550.010.00.00.01.00Rp4,589.550.011.00Rp4,589.550.01100.00COMPLETEDUrugan Pasir Bawah PondasiM30.02Rp1,713.120.000.00.00.00.02Rp1,713.120.000.02Rp1,713.120.00100.00COMPLETEDPasangan Batu Gunung 1 : 3M31.00Rp277,037.340.380.00.00.01.00Rp277,037.340.381.00Rp277,037.340.38100.00COMPLETEDPasangan Batu KosongM32.00Rp6,419.820.010.00.00.02.00Rp6,419.820.012.00Rp6,419.820.01100.00COMPLETEDTanah TimbunanM31.00Rp1,088,542.181.500.00.00.00.00.00.00.00.00.00.0DELAYEDLantai Beton Cor 1Pc : 1,5Ps : 2,5Kr, T=10 cmM30.02Rp966,777.351.340.00.00.00.00.00.00.00.00.00.0DELAYEDPlasteran 1pc : 2 psM21.00Rp229,752.660.320.00.00.00.00.00.00.00.00.00.0DELAYEDJUMLAHRp72,371,871.18100.00Rp62,856,873.4086.85Rp3,234,264.7314.47Rp66,091,138.1491.32SISA PROGRESSPPn10%Rp7,237,187.12Rp6,285,687.34Rp323,426.473Rp6,609,113.81GRAND TOTALRp79,609,058.30Rp69,142,560.74Rp3,557,691.204Rp72,700,251.958.68%DIBULATKANRp79,609,000.00Rp69,142,000.00Rp3,557,000.00Rp72,700,000.00Disetujui Oleh :Diperiksa Oleh :Dibuat Oleh :Pejabat Pelaksana Teknis Kegiatan (PPTK)Konsultan SupervisiKontraktor PelaksanaDinas Cipta Karya Aceh BesarCV. SCALA DESIGNCV. TUAH BARUSAMUHAMMAD IKHSAN,ST.MTHERI DERMAWAN,STIRSANNIP. 19740407 200212 1 007InspectorDirektur

M.2.1 (10)LAPORAN KEMAJUAN PEKERJAANMINGGU KE :10 (SEPULUH)PERIODE :15 OKTOBER 2014 S/D 23 OKTOBER 2014PEKERJAAN:PEMASANGAN PIPANISASI AIR BERSIH GP. ALUE RINDANG KEC. SEULIMEUM (DAU)PROGRESS96.44%LOKASI:KEC. SEULIMEUMKONTRAKTOR PELAKSANA:CV. TUAH BARUSARENCANAJANGKA WAKTU PELAKSANAAN:90 HariNO. KONTRAK:26/SPK/PL.P-PERKIM/BMCK/2014PROGRESS94.53%NILAI KONTRAK AWAL:Rp79,609,000TANGGAL KONTRAK:06 AGUSTUS 2014ACTUALSUMBER DANA:APBKKONSULTAN PENGAWAS:CV. SCALA DESIGNDEVIASI-1.91%TAHUNANGGARAN:2014NO. KONTRAK:0.0TANGGAL KONTRAK:0.0DELAYEDON PROGRESSON PROGRESSON PROGRESSDELAYEDON PROGRESSON PROGRESSON PROGRESSNO.URAIANSAT.KONTRAK AWALMINGGU LALUMINGGU INIREALISASI PEKER. S/D MINGGU INIKET.QTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotPrestasi( Rp. )( % )( Rp. )( % )(Rp.)( % )( Rp. )( % )(%)abcdefghijklm =(g+j)n =(h+k)o =(i+l)pqIPEKERJAAN PERSIAPAN$1Direksi Keet / Gudang (Sewa)Ls1.00Rp390,000.000.541.00Rp390,000.000.540.00.00.01.00Rp390,000.000.54100.00COMPLETED$2Papan Nama Proyek dan Rambu -RambuLs1.00Rp280,000.000.391.00Rp280,000.000.390.00.00.01.00Rp280,000.000.39100.00COMPLETED$3PembersihanLs1.00Rp450,000.000.621.00Rp450,000.000.620.00.00.01.00Rp450,000.000.62100.00COMPLETED$4Pematokan/pengukuran (setting out)Ls1.00Rp500,000.000.691.00Rp500,000.000.690.00.00.01.00Rp500,000.000.69100.00COMPLETED$5Mobilisasi dan DemobilisasiLs1.00Rp250,000.000.351.00Rp250,000.000.350.00.00.01.00Rp250,000.000.35100.00COMPLETED$6Administrasi Dokumentasi dan as built drawingLs1.00Rp1,000,000.001.380.50Rp500,000.000.690.00.00.00.50Rp500,000.000.6950.00ON PROGRESSIIPENGADAAN PIPA DAN ACCESSORIES$1Pengadaan PipaPengadaan Pipa-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp33,734,800.0046.61451.00Rp33,734,800.0046.610.00.00.0451.00Rp33,734,800.0046.61100.00COMPLETED-Pipa GIP dia.100 mmPipa GIP dia.100 mmM'12.00Rp2,640,000.003.6512.00Rp2,640,000.003.650.00.00.012.00Rp2,640,000.003.65100.00COMPLETED-Pipa GIP dia.50 mmPipa GIP dia.50 mmM'5.00Rp620,000.000.865.00Rp620,000.000.860.00.00.05.00Rp620,000.000.86100.00COMPLETED$2Pengadaan Accessories-Bend All Socket PVC RRJ Dia. 100 x 90bh2.00Rp316,000.000.442.00Rp316,000.000.440.00.00.02.00Rp316,000.000.44100.00COMPLETED-Bend All Socket PVC RRJ Dia. 100 x 45bh1.00Rp145,300.000.201.00Rp145,300.000.200.00.00.01.00Rp145,300.000.20100.00COMPLETED-Flange Socket PVC RRJ Dia. 100 mmbh7.00Rp4,092,018.005.657.00Rp4,092,018.005.650.00.00.07.00Rp4,092,018.005.65100.00COMPLETED-Flange Socket PVC RRJ Dia. 50 mmbh2.00Rp349,000.000.482.00Rp349,000.000.480.00.00.02.00Rp349,000.000.48100.00COMPLETED-Tee All socket Dia 100 x 100 mmbh1.00Rp303,300.000.421.00Rp303,300.000.420.00.00.01.00Rp303,300.000.42100.00COMPLETED-Reducer Socket Dia 100 x 50 mmbh1.00Rp112,850.000.161.00Rp112,850.000.160.00.00.01.00Rp112,850.000.16100.00COMPLETED-Bend All Socket PVC RRJ Dia. 50 x 90bh1.00Rp50,550.000.071.00Rp50,550.000.070.00.00.01.00Rp50,550.000.07100.00COMPLETED-Dop PVC dia.100 mmbh1.00Rp171,175.000.241.00Rp171,175.000.240.00.00.01.00Rp171,175.000.24100.00COMPLETED-Bend GIP Dia 100 x 90 mmbh1.00Rp180,000.000.251.00Rp180,000.000.250.00.00.01.00Rp180,000.000.25100.00COMPLETED-Bend GIP Dia 100 x 45 mmbh4.00Rp620,000.000.864.00Rp620,000.000.860.00.00.04.00Rp620,000.000.86100.00COMPLETED-Bend GIP Dia 50 x 90 mmbh2.00Rp190,000.000.262.00Rp190,000.000.260.00.00.02.00Rp190,000.000.26100.00COMPLETED-Loss Flange GIP Dia 100 mmbh5.00Rp560,000.000.775.00Rp560,000.000.770.00.00.05.00Rp560,000.000.77100.00COMPLETED-Loss Flange GIP Dia 50 mmbh2.00Rp162,000.000.222.00Rp162,000.000.220.00.00.02.00Rp162,000.000.22100.00COMPLETED-Tee Gip 100 x 50 mmbh1.00Rp215,000.000.301.00Rp215,000.000.300.00.00.01.00Rp215,000.000.30100.00COMPLETED-Gate Valve 4"bh2.00Rp3,000,000.004.152.00Rp3,000,000.004.150.00.00.02.00Rp3,000,000.004.15100.00COMPLETED-Saringan/Besi Dia 4 "bh1.00Rp75,000.000.101.00Rp75,000.000.100.00.00.01.00Rp75,000.000.10100.00COMPLETED-Bautbh80.00Rp600,000.000.8380.00Rp600,000.000.830.00.00.080.00Rp600,000.000.83100.00COMPLETED-Pakingbh10.00Rp115,000.000.1610.00Rp115,000.000.160.00.00.010.00Rp115,000.000.16100.00COMPLETEDIIIPEKERJAAN PEMASANGAN PIPA DAN ACESSORIES$1Pekerjaan Tanah-Galian Tanah KerasM3108.24Rp4,663,520.406.44108.24Rp4,663,520.406.440.00.00.0108.24Rp4,663,520.406.44100.00COMPLETED-Urugan KembaliM3104.60Rp1,384,062.571.91104.60Rp1,384,062.571.910.00.00.0104.60Rp1,384,062.571.91100.00COMPLETED$2Pemasangan Pipa Termasuk Fitting dan Valve-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp8,392,208.0011.60451.00Rp8,392,208.0011.600.00.00.0451.00Rp8,392,208.0011.60100.00COMPLETED-Pipa GIP dia.100 mmM'12.00Rp572,425.150.7912.00Rp572,425.150.790.00.00.012.00Rp572,425.150.79100.00COMPLETED-Pipa GIP dia.50 mmM'5.00Rp130,904.600.185.00Rp130,904.600.180.00.00.05.00Rp130,904.600.18100.00COMPLETED-Pengecatan permukaan baja secara manual sistem 2 lapisM24.55Rp72,529.150.102.28Rp36,264.580.052.28Rp36,264.580.054.55Rp72,529.150.10100.00COMPLETEDIVPEKERJAAN LAIN-LAIN$1Crossing Pipa/ BoringM'6.00Rp900,000.001.240.00.00.00.00.00.00.00.00.00.0DELAYED$2Rekondisi Jalan/FinishingLs1.00Rp200,000.000.280.00.00.00.00.00.00.00.00.00.0DELAYED$3Rekondisi Jalan (Rabat Beton)M30.02Rp9,396.280.010.00.00.00.00.00.00.00.00.00.0DELAYED$4Uji Laboratorium Baku Mutu Kualitas Air BersihLs1.00Rp750,000.001.040.00.00.00.00.00.00.00.00.00.0DELAYED$5Street BoxLs2.00Rp1,600,000.002.210.00.00.00.00.00.00.00.00.00.0DELAYEDVPEKERJAAN REHAP INTAKE$1PEKERJAAN TANAH & PONDASIGalian Tanah PondasiM31.00Rp4,589.550.011.00Rp4,589.550.010.00.00.01.00Rp4,589.550.01100.00COMPLETEDUrugan Pasir Bawah PondasiM30.02Rp1,713.120.000.02Rp1,713.120.000.00.00.00.02Rp1,713.120.00100.00COMPLETEDPasangan Batu Gunung 1 : 3M31.00Rp277,037.340.381.00Rp277,037.340.380.00.00.01.00Rp277,037.340.38100.00COMPLETEDPasangan Batu KosongM32.00Rp6,419.820.012.00Rp6,419.820.010.00.00.02.00Rp6,419.820.01100.00COMPLETEDTanah TimbunanM31.00Rp1,088,542.181.500.00.00.01.00Rp1,088,542.181.501.00Rp1,088,542.181.50100.00COMPLETEDLantai Beton Cor 1Pc : 1,5Ps : 2,5Kr, T=10 cmM30.02Rp966,777.351.340.00.00.00.02Rp966,777.351.340.02Rp966,777.351.34100.00COMPLETEDPlasteran 1pc : 2 psM21.00Rp229,752.660.320.00.00.01.00Rp229,752.660.321.00Rp229,752.660.32100.00COMPLETEDJUMLAHRp72,371,871.18100.00Rp66,091,138.1491.32Rp2,321,336.7673.21Rp68,412,474.9094.53SISA PROGRESSPPn10%Rp7,237,187.12Rp6,609,113.81Rp232,133.677Rp6,841,247.49GRAND TOTALRp79,609,058.30Rp72,700,251.95Rp2,553,470.444Rp75,253,722.395.47%DIBULATKANRp79,609,000.00Rp72,700,000.00Rp2,553,000.00Rp75,253,000.00Disetujui Oleh :Diperiksa Oleh :Dibuat Oleh :Pejabat Pelaksana Teknis Kegiatan (PPTK)Konsultan SupervisiKontraktor PelaksanaDinas Cipta Karya Aceh BesarCV. SCALA DESIGNCV. TUAH BARUSAMUHAMMAD IKHSAN,ST.MTHERI DERMAWAN,STIRSANNIP. 19740407 200212 1 007InspectorDirektur

M.2.1 (13)LAPORAN KEMAJUAN PEKERJAANMINGGU KE :11 (SEBELAS)PERIODE :24 OKTOBER 2014 S/D 31 OKTOBER 2014PEKERJAAN:PEMASANGAN PIPANISASI AIR BERSIH GP. ALUE RINDANG KEC. SEULIMEUM (DAU)PROGRESS98.35%LOKASI:KEC. SEULIMEUMKONTRAKTOR PELAKSANA:CV. TUAH BARUSARENCANAJANGKA WAKTU PELAKSANAAN:90 HariNO. KONTRAK:26/SPK/PL.P-PERKIM/BMCK/2014PROGRESS97.78%NILAI KONTRAK AWAL:Rp79,609,000TANGGAL KONTRAK:06 AGUSTUS 2014ACTUALSUMBER DANA:APBKKONSULTAN PENGAWAS:CV. SCALA DESIGNDEVIASI-0.57%TAHUNANGGARAN:2014NO. KONTRAK:0.0TANGGAL KONTRAK:0.0DELAYEDON PROGRESSON PROGRESSON PROGRESSDELAYEDON PROGRESSON PROGRESSON PROGRESSNO.URAIANSAT.KONTRAK AWALMINGGU LALUMINGGU INIREALISASI PEKER. S/D MINGGU INIKET.QTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotPrestasi( Rp. )( % )( Rp. )( % )(Rp.)( % )( Rp. )( % )(%)abcdefghijklm =(g+j)n =(h+k)o =(i+l)pqIPEKERJAAN PERSIAPAN$1Direksi Keet / Gudang (Sewa)Ls1.00Rp390,000.000.541.00Rp390,000.000.540.00.00.01.00Rp390,000.000.54100.00COMPLETED0.0$2Papan Nama Proyek dan Rambu -RambuLs1.00Rp280,000.000.391.00Rp280,000.000.390.00.00.01.00Rp280,000.000.39100.00COMPLETED0.0$3PembersihanLs1.00Rp450,000.000.621.00Rp450,000.000.620.00.00.01.00Rp450,000.000.62100.00COMPLETED0.0$4Pematokan/pengukuran (setting out)Ls1.00Rp500,000.000.691.00Rp500,000.000.690.00.00.01.00Rp500,000.000.69100.00COMPLETEDRp2,350,000.00$5Mobilisasi dan DemobilisasiLs1.00Rp250,000.000.351.00Rp250,000.000.350.00.00.01.00Rp250,000.000.35100.00COMPLETED0.0$6Administrasi Dokumentasi dan as built drawingLs1.00Rp1,000,000.001.380.50Rp500,000.000.690.00.00.00.50Rp500,000.000.6950.00ON PROGRESSIIPENGADAAN PIPA DAN ACCESSORIES$1Pengadaan PipaPengadaan Pipa-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp33,734,800.0046.61451.00Rp33,734,800.0046.610.00.00.0451.00Rp33,734,800.0046.61100.00COMPLETED-Pipa GIP dia.100 mmPipa GIP dia.100 mmM'12.00Rp2,640,000.003.6512.00Rp2,640,000.003.650.00.00.012.00Rp2,640,000.003.65100.00COMPLETED-Pipa GIP dia.50 mmPipa GIP dia.50 mmM'5.00Rp620,000.000.865.00Rp620,000.000.860.00.00.05.00Rp620,000.000.86100.00COMPLETED$2Pengadaan Accessories-Bend All Socket PVC RRJ Dia. 100 x 90bh2.00Rp316,000.000.442.00Rp316,000.000.440.00.00.02.00Rp316,000.000.44100.00COMPLETED-Bend All Socket PVC RRJ Dia. 100 x 45bh1.00Rp145,300.000.201.00Rp145,300.000.200.00.00.01.00Rp145,300.000.20100.00COMPLETED-Flange Socket PVC RRJ Dia. 100 mmbh7.00Rp4,092,018.005.657.00Rp4,092,018.005.650.00.00.07.00Rp4,092,018.005.65100.00COMPLETED-Flange Socket PVC RRJ Dia. 50 mmbh2.00Rp349,000.000.482.00Rp349,000.000.480.00.00.02.00Rp349,000.000.48100.00COMPLETED-Tee All socket Dia 100 x 100 mmbh1.00Rp303,300.000.421.00Rp303,300.000.420.00.00.01.00Rp303,300.000.42100.00COMPLETED-Reducer Socket Dia 100 x 50 mmbh1.00Rp112,850.000.161.00Rp112,850.000.160.00.00.01.00Rp112,850.000.16100.00COMPLETED-Bend All Socket PVC RRJ Dia. 50 x 90bh1.00Rp50,550.000.071.00Rp50,550.000.070.00.00.01.00Rp50,550.000.07100.00COMPLETED-Dop PVC dia.100 mmbh1.00Rp171,175.000.241.00Rp171,175.000.240.00.00.01.00Rp171,175.000.24100.00COMPLETED-Bend GIP Dia 100 x 90 mmbh1.00Rp180,000.000.251.00Rp180,000.000.250.00.00.01.00Rp180,000.000.25100.00COMPLETED-Bend GIP Dia 100 x 45 mmbh4.00Rp620,000.000.864.00Rp620,000.000.860.00.00.04.00Rp620,000.000.86100.00COMPLETED-Bend GIP Dia 50 x 90 mmbh2.00Rp190,000.000.262.00Rp190,000.000.260.00.00.02.00Rp190,000.000.26100.00COMPLETED-Loss Flange GIP Dia 100 mmbh5.00Rp560,000.000.775.00Rp560,000.000.770.00.00.05.00Rp560,000.000.77100.00COMPLETED-Loss Flange GIP Dia 50 mmbh2.00Rp162,000.000.222.00Rp162,000.000.220.00.00.02.00Rp162,000.000.22100.00COMPLETED-Tee Gip 100 x 50 mmbh1.00Rp215,000.000.301.00Rp215,000.000.300.00.00.01.00Rp215,000.000.30100.00COMPLETED-Gate Valve 4"bh2.00Rp3,000,000.004.152.00Rp3,000,000.004.150.00.00.02.00Rp3,000,000.004.15100.00COMPLETED-Saringan/Besi Dia 4 "bh1.00Rp75,000.000.101.00Rp75,000.000.100.00.00.01.00Rp75,000.000.10100.00COMPLETED-Bautbh80.00Rp600,000.000.8380.00Rp600,000.000.830.00.00.080.00Rp600,000.000.83100.00COMPLETED-Pakingbh10.00Rp115,000.000.1610.00Rp115,000.000.160.00.00.010.00Rp115,000.000.16100.00COMPLETEDIIIPEKERJAAN PEMASANGAN PIPA DAN ACESSORIES$1Pekerjaan Tanah-Galian Tanah KerasM3108.24Rp4,663,520.406.44108.24Rp4,663,520.406.440.00.00.0108.24Rp4,663,520.406.44100.00COMPLETED-Urugan KembaliM3104.60Rp1,384,062.571.91104.60Rp1,384,062.571.910.00.00.0104.60Rp1,384,062.571.91100.00COMPLETED$2Pemasangan Pipa Termasuk Fitting dan Valve-Pipa PVC RRJ S-12,5 Dia 100 mmM'451.00Rp8,392,208.0011.60451.00Rp8,392,208.0011.600.00.00.0451.00Rp8,392,208.0011.60100.00COMPLETED-Pipa GIP dia.100 mmM'12.00Rp572,425.150.7912.00Rp572,425.150.790.00.00.012.00Rp572,425.150.79100.00COMPLETED-Pipa GIP dia.50 mmM'5.00Rp130,904.600.185.00Rp130,904.600.180.00.00.05.00Rp130,904.600.18100.00COMPLETED-Pengecatan permukaan baja secara manual sistem 2 lapisM24.55Rp72,529.150.104.55Rp72,529.150.100.00.00.04.55Rp72,529.150.10100.00COMPLETEDIVPEKERJAAN LAIN-LAIN$1Crossing Pipa/ BoringM'6.00Rp900,000.001.240.00.00.00.00.00.00.00.00.00.0DELAYED$2Rekondisi Jalan/FinishingLs1.00Rp200,000.000.280.00.00.00.00.00.00.00.00.00.0DELAYED$3Rekondisi Jalan (Rabat Beton)M30.02Rp9,396.280.010.00.00.00.00.00.00.00.00.00.0DELAYED$4Uji Laboratorium Baku Mutu Kualitas Air BersihLs1.00Rp750,000.001.040.00.00.01.00Rp750,000.001.041.00Rp750,000.001.04100.00COMPLETED$5Street BoxLs2.00Rp1,600,000.002.210.00.00.02.00Rp1,600,000.002.212.00Rp1,600,000.002.21100.00COMPLETEDVPEKERJAAN REHAP INTAKE$1PEKERJAAN TANAH & PONDASIGalian Tanah PondasiM31.00Rp4,589.550.011.00Rp4,589.550.010.00.00.01.00Rp4,589.550.01100.00COMPLETEDUrugan Pasir Bawah PondasiM30.02Rp1,713.120.000.02Rp1,713.120.000.00.00.00.02Rp1,713.120.00100.00COMPLETEDPasangan Batu Gunung 1 : 3M31.00Rp277,037.340.381.00Rp277,037.340.380.00.00.01.00Rp277,037.340.38100.00COMPLETEDPasangan Batu KosongM32.00Rp6,419.820.012.00Rp6,419.820.010.00.00.02.00Rp6,419.820.01100.00COMPLETEDTanah TimbunanM31.00Rp1,088,542.181.501.00Rp1,088,542.181.500.00.00.01.00Rp1,088,542.181.50100.00COMPLETEDLantai Beton Cor 1Pc : 1,5Ps : 2,5Kr, T=10 cmM30.02Rp966,777.351.340.02Rp966,777.351.340.00.00.00.02Rp966,777.351.34100.00COMPLETEDPlasteran 1pc : 2 psM21.00Rp229,752.660.321.00Rp229,752.660.320.00.00.01.00Rp229,752.660.32100.00COMPLETEDJUMLAHRp72,371,871.18100.00Rp68,412,474.9094.53Rp2,350,000.0003.25Rp70,762,474.9097.78SISA PROGRESSPPn10%Rp7,237,187.12Rp6,841,247.49Rp235,000.000Rp7,076,247.49GRAND TOTALRp79,609,058.30Rp75,253,722.39Rp2,585,000.000Rp77,838,722.392.22%DIBULATKANRp79,609,000.00Rp75,253,000.00Rp2,585,000.00Rp77,838,000.00Disetujui Oleh :Diperiksa Oleh :Dibuat Oleh :Pejabat Pelaksana Teknis Kegiatan (PPTK)Konsultan SupervisiKontraktor PelaksanaDinas Cipta Karya Aceh BesarCV. SCALA DESIGNCV. TUAH BARUSAMUHAMMAD IKHSAN,ST.MTHERI DERMAWAN,STIRSANNIP. 19740407 200212 1 007InspectorDirektur

B3LAPORAN KEMAJUAN PEKERJAANBULAN KE :3 (TIGA)PERIODE :01 OKTOBER 2014 S/D 31 OKTOBER 2014PEKERJAAN:PEMASANGAN PIPANISASI AIR BERSIH GP. ALUE RINDANG KEC. SEULIMEUM (DAU)PROGRESS98.35%LOKASI:KEC. SEULIMEUMKONTRAKTOR PELAKSANA:CV. TUAH BARUSARENCANAJANGKA WAKTU PELAKSANAAN:90 HariNO. KONTRAK:26/SPK/PL.P-PERKIM/BMCK/2014PROGRESS97.78%NILAI KONTRAK AWAL:Rp79,609,000TANGGAL KONTRAK:06 AGUSTUS 2014ACTUALSUMBER DANA:APBKKONSULTAN PENGAWAS:CV. SCALA DESIGNDEVIASI-0.57%TAHUNANGGARAN:2014NO. KONTRAK:0.0TANGGAL KONTRAK:0.0DELAYEDON PROGRESSON PROGRESSON PROGRESSDELAYEDON PROGRESSON PROGRESSON PROGRESSNO.URAIANSAT.KONTRAK AWALBULAN LALUBULAN INIREALISASI PEKER. S/D BULAN INIKET.QTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotQTY.Jumlah HargaBobotPrestasi( Rp. )( % )( Rp. )( % )(Rp.)( % )( Rp. )( % )(%)abcdefghijklm =(g+j)n =(h+k)o =(i+l)pqIPEKERJAAN PERSIAPAN$1Direksi Keet / Gudang (Sewa)Ls1.00Rp390,000.000.541.00Rp390,000.000.540.00.00.01.00Rp390,000.000.54100.00COMPLETED0.0$2Papan Nama Proyek dan Rambu -RambuLs1.00Rp280,000.000.391.00Rp280,000.000.390.00.00.01.00Rp280,000.000.39100.00COMPLETED0.0$3PembersihanLs1.00Rp450,000.000.621.00Rp450,000.000.620.00.00.01.00Rp450,000.000.62100.00COMPLETEDRp6,036,609.48$4Pematokan/pengukuran (setting out)Ls1.00Rp500,000.000.691.00Rp500,000.000.690.00.00.01.00Rp500,000.000.69100.00COMPLETEDRp2,350,000.00$5Mobilisasi dan DemobilisasiLs1.00Rp250,000.000.351.00Rp250,000.000.350.00.00.01.00Rp250,000.000.35100.00COMPLETEDRp2,574,832.02$6Administrasi Dokumentasi dan as built drawingLs1.00Rp1,000,000.001.380.50Rp500,000.000.690