NO JENIS PEKERJAAN SATUAN KOEFISIEN HARGA JUMLAH HARGA 1 UPAH Pekerja Org 0.1000 30,000.00 3,000.00 Mandor Org 0.0500 50,000.00 2,500.00 TOTAL UPAH 5,500.00 2 PEKERJAAN PENGUKURAN DAN PEMASANGAN BOUWPLANK / M' UPAH Pekerja Org 0.0300 30,000.00 900.00 Tukang Org 0.0900 40,000.00 3,600.00 Kepala Tukang Org 0.0090 50,000.00 450.00 Mandor Org 0.0020 50,000.00 100.00 TOTAL UPAH 5,050.00 BAHAN Kayu papan borneo 0.0100 30,000.00 300.00 Paku 2" - 5" kg 0.0100 50,000.00 500.00 TOTAL BAHAN 800.00 3 PEKERJAAN GALIAN TANAH BIASA / M3 UPAH Pekerja Org 0.7500 30,000.00 22,500.00 Mandor Org 0.0250 50,000.00 1,250.00 TOTAL UPAH 23,750.00 4 PEKERJAAN URUGAN TANAH / M3 UPAH Pekerja Org 0.3000 30,000.00 9,000.00 Mandor Org 0.0100 50,000.00 500.00 TOTAL UPAH 9,500.00 BAHAN Tanah urug 1.2000 55,000.00 66,000.00 TOTAL BAHAN 66,000.00 5 PEKERJAAN URUGAN PASIR / M3 UPAH Pekerja Org 0.3000 30,000.00 9,000.00 Mandor Org 0.0100 50,000.00 500.00 TOTAL UPAH 9,500.00 BAHAN Pasir urug 1.2000 65,000.00 78,000.00 TOTAL BAHAN 78,000.00 6 PEKERJAAN PASANGAN BATU KALI 1:4 / M3 UPAH Pekerja Org 3.6000 30,000.00 108,000.00 Tukang Org 1.2000 40,000.00 48,000.00 Kepala Tukang Org 0.1200 50,000.00 6,000.00 PEKERJAAN PEMBERSIHAN LAHAN (LOKASI PEKERJAAN) / M 2 m 3 m 3 m 3

description

Latihan

Transcript of Kolam Renang Patra Jasa

Page 1: Kolam Renang Patra Jasa

NO JENIS PEKERJAAN SATUAN KOEFISIEN HARGA TOTAL

1

UPAHPekerja Org 0.1000 30,000.00 3,000.00 Mandor Org 0.0500 50,000.00 2,500.00

TOTAL UPAH 5,500.00 5,500.00

2 PEKERJAAN PENGUKURAN DAN PEMASANGAN BOUWPLANK / M'

UPAHPekerja Org 0.0300 30,000.00 900.00 Tukang Org 0.0900 40,000.00 3,600.00 Kepala Tukang Org 0.0090 50,000.00 450.00 Mandor Org 0.0020 50,000.00 100.00

TOTAL UPAH 5,050.00 5,050.00

BAHAN

Kayu papan borneo 0.0100 30,000.00 300.00 Paku 2" - 5" kg 0.0100 50,000.00 500.00

TOTAL BAHAN 800.00 800.00

3 PEKERJAAN GALIAN TANAH BIASA / M3

UPAHPekerja Org 0.7500 30,000.00 22,500.00 Mandor Org 0.0250 50,000.00 1,250.00

TOTAL UPAH 23,750.00 23,750.00

4 PEKERJAAN URUGAN TANAH / M3

UPAHPekerja Org 0.3000 30,000.00 9,000.00 Mandor Org 0.0100 50,000.00 500.00

TOTAL UPAH 9,500.00 9,500.00

BAHAN

Tanah urug 1.2000 55,000.00 66,000.00 TOTAL BAHAN 66,000.00 66,000.00

5 PEKERJAAN URUGAN PASIR / M3

UPAHPekerja Org 0.3000 30,000.00 9,000.00 Mandor Org 0.0100 50,000.00 500.00

TOTAL UPAH 9,500.00 9,500.00

BAHAN

Pasir urug 1.2000 65,000.00 78,000.00 TOTAL BAHAN 78,000.00 78,000.00

6 PEKERJAAN PASANGAN BATU KALI 1:4 / M3

UPAHPekerja Org 3.6000 30,000.00 108,000.00 Tukang Org 1.2000 40,000.00 48,000.00 Kepala Tukang Org 0.1200 50,000.00 6,000.00

JUMLAH HARGA

PEKERJAAN PEMBERSIHAN LAHAN (LOKASI PEKERJAAN) / M2

m3

m3

m3

Page 2: Kolam Renang Patra Jasa

Mandor Org 0.1800 50,000.00 9,000.00 TOTAL UPAH 171,000.00 171,000.00

BAHANBatu belah m3 1.2000 #REF! #REF!Semen 50 kg sak 3.2240 42,000.00 135,408.00 Pasir pasang m3 0.5220 75,000.00 39,150.00

TOTAL BAHAN #REF! #REF!

7 PEKERJAAN PASANGAN BATA 1:4 < 5 M / M3

UPAHPekerja Org 4.5000 30,000.00 135,000.00 Tukang Org 1.5000 40,000.00 60,000.00 Kepala Tukang Org 0.1500 50,000.00 7,500.00 Mandor Org 0.2250 50,000.00 11,250.00

TOTAL UPAH 213,750.00 213,750.00

BAHANBatu bata bh 450.0000 300.00 135,000.00 Pasir pasang m3 0.4220 75,000.00 31,650.00 Semen 50 kg Zak 2.1040 42,000.00 88,368.00

TOTAL BAHAN 255,018.00 255,018.00

8 PEKERJAAN PASANGAN BATA 1:4 > 5 M / M3

UPAHPekerja Org 7.5000 30,000.00 225,000.00 Tukang Org 2.5000 40,000.00 100,000.00 Kepala Tukang Org 0.2500 50,000.00 12,500.00 Mandor Org 0.3750 50,000.00 18,750.00

TOTAL UPAH 356,250.00 356,250.00

BAHANBatu bata bh 450.0000 300.00 135,000.00 Pasir pasang m3 0.4220 75,000.00 31,650.00 Semen 50 kg Zak 2.1040 42,000.00 88,368.00

TOTAL BAHAN 255,018.00 255,018.00

9 PEKERJAAN PLESTERAN 1:4 < 5 M / M2

UPAHPekerja Org 0.4000 30,000.00 12,000.00 Tukang Org 0.2000 40,000.00 8,000.00 Kepala Tukang Org 0.0200 50,000.00 1,000.00 Mandor Org 0.0200 50,000.00 1,000.00

TOTAL UPAH 22,000.00 22,000.00

BAHANPasir pasang m3 0.0209 75,000.00 1,567.50 Semen 50 kg Zak 0.1296 42,000.00 5,443.20

TOTAL BAHAN 7,010.70 7,010.70

10 PEKERJAAN PLESTERAN 1:4 > 5 M / M2

UPAHPekerja Org 0.6660 30,000.00 19,980.00 Tukang Org 0.3330 40,000.00 13,320.00 Kepala Tukang Org 0.0330 50,000.00 1,650.00 Mandor Org 0.0330 50,000.00 1,650.00

TOTAL UPAH 36,600.00 36,600.00

Page 3: Kolam Renang Patra Jasa

BAHANPasir pasang m3 0.0209 75,000.00 1,567.50 Semen 50 kg Zak 0.1296 42,000.00 5,443.20

TOTAL BAHAN 7,010.70 7,010.70

11 PEKERJAAN PASANG ROSTER / M2

UPAHPekerja Org 0.5000 30,000.00 15,000.00 Tukang Org 0.2500 40,000.00 10,000.00 Kepala Tukang Org 0.0250 50,000.00 1,250.00 Mandor Org 0.0250 50,000.00 1,250.00

TOTAL UPAH 27,500.00 27,500.00

BAHANRoster 20 x 20 cm bh 25.0000 #REF! #REF!Pasir pasang m3 0.0210 75,000.00 1,575.00 Semen 50 kg Zak 0.1620 42,000.00 6,804.00

TOTAL BAHAN #REF! #REF!

12 PEKERJAAN BEKISTING BETON / M2

UPAHPekerja Org 0.2000 30,000.00 6,000.00 Tukang Org 0.5000 40,000.00 20,000.00 Kepala Tukang Org 0.0500 50,000.00 2,500.00 Mandor Org 0.0100 50,000.00 500.00

TOTAL UPAH 29,000.00 29,000.00

BAHANKayu papan borneo m3 0.0400 3,000,000.00 120,000.00 Paku 2" - 5" kg 0.4000 10,000.00 4,000.00

TOTAL BAHAN 124,000.00 124,000.00

13 PEKERJAAN STEL BESI BETON / KG

UPAHTukang besi Org 0.0660 40,000.00 2,640.00

TOTAL UPAH 2,640.00 2,640.00

BAHANBesi beton kg 1.1000 7,000.00 7,700.00 Kawat beton kg 0.0200 10,000.00 200.00

TOTAL BAHAN 7,900.00 7,900.00

14 PEKERJAAN COR BETON 1 pc : 3 ps : 5 split / M3

UPAHPekerja Org 6.0000 30,000.00 180,000.00 Tukang Org 0.5000 40,000.00 20,000.00 Kepala Tukang Org 0.0500 50,000.00 2,500.00 Mandor Org 0.3000 50,000.00 15,000.00

TOTAL UPAH 217,500.00 217,500.00

BAHANSemen 50 kg sak 4.5400 42,000.00 190,680.00 Pasir beton m3 0.5400 75,000.00 Split 2/3 cm m3 0.9100 160,000.00 145,600.00

TOTAL BAHAN 336,280.00 336,280.00

15 PEKERJAAN COR BETON 1 pc : 2 ps : 3 split / M3

Page 4: Kolam Renang Patra Jasa

UPAHPekerja Org 6.0000 30,000.00 180,000.00 Tukang Org 1.0000 40,000.00 40,000.00 Kepala Tukang Org 0.1000 50,000.00 5,000.00 Mandor Org 0.3000 50,000.00 15,000.00

TOTAL UPAH 240,000.00 240,000.00

BAHANSemen 50 kg sak 6.8000 42,000.00 285,600.00 Pasir beton m3 0.5400 75,000.00 Split 2/3 cm m3 0.8100 160,000.00 129,600.00

TOTAL BAHAN 415,200.00 415,200.00

16 PEKERJAAN BONGKAR BEKISTING / M3

UPAHPekerja Org 0.4000 30,000.00 12,000.00

TOTAL UPAH 12,000.00 12,000.00

17 PEKERJAAN STEL KUDA-KUDA KAYU DOLKEN ø 10 CM BENTANG 5 - 7 M / M3

UPAHPekerja Org 8.0000 30,000.00 240,000.00 Tukang Org 24.0000 40,000.00 960,000.00 Kepala Tukang Org 2.4000 50,000.00 120,000.00 Mandor Org 0.4000 50,000.00 20,000.00

TOTAL UPAH 1,340,000.00 1,340,000.00

BAHANKayu dolken ø 10 cm @ 4 m m3 1.1000 #REF! #REF!Paku 2" - 5" kg 2.5000 10,000.00

TOTAL BAHAN #REF! #REF!

18 PEKERJAAN STEL GORDING KAYU DOLKEN ø 5 CM / M3

UPAHPekerja Org 5.0000 30,000.00 150,000.00 Tukang Org 15.0000 40,000.00 600,000.00 Kepala Tukang Org 1.5000 50,000.00 75,000.00 Mandor Org 0.2500 50,000.00 12,500.00

TOTAL UPAH 837,500.00 837,500.00

BAHANKayu dolken ø 10 cm @ 4 m m3 1.1000 #REF! #REF!Paku 2" - 5" kg 2.5000 10,000.00

TOTAL BAHAN #REF! #REF!

19 PEKERJAAN MEMBUAT DAN PASANG KUSEN KAYU JATI JAWA BARAT / M3

UPAHPekerja Org 12.0000 30,000.00 360,000.00 Tukang Org 36.0000 40,000.00 1,440,000.00 Kepala Tukang Org 3.6000 50,000.00 180,000.00 Mandor Org 0.6000 50,000.00 30,000.00

TOTAL UPAH 2,010,000.00 2,010,000.00

BAHANKayu balok jati Jabar m3 1.1000 #REF! #REF!Paku 2" - 5" kg 0.2000 10,000.00

TOTAL BAHAN #REF! #REF!

20 PEKERJAAN MEMBUAT DAN PASANG DAUN PINTU RANGKA KAYU BALAU LAPIS TEAKWOOD DOUBLE / M2

Page 5: Kolam Renang Patra Jasa

UPAHPekerja Org 0.7800 30,000.00 23,400.00 Tukang Org 2.4000 40,000.00 96,000.00 Kepala Tukang Org 0.2400 50,000.00 12,000.00 Mandor Org 0.0390 50,000.00 1,950.00

TOTAL UPAH 133,350.00 133,350.00

BAHANKayu papan balau m3 0.0135 - Lem Fox Kg 0.2500Teakwood lebar 90 cm Lb 1.2500

TOTAL BAHAN - -

21 PEKERJAAN MEMBUAT DAN PASANG DAUN PINTU PANEL KAYU JATI JAWA BARAT / M2

UPAHPekerja Org 2.0000 30,000.00 60,000.00 Tukang Org 6.0000 40,000.00 240,000.00 Kepala Tukang Org 0.6000 50,000.00 30,000.00 Mandor Org 0.1000 50,000.00 5,000.00

TOTAL UPAH 335,000.00 335,000.00

BAHANKayu papan jati Jabar m3 0.0440 -

TOTAL BAHAN - -

22 PEKERJAAN MEMBUAT DAN PASANG DAUN JENDELA KACA / M2

UPAHPekerja Org 0.6667 30,000.00 20,000.00 Tukang Org 2.0000 40,000.00 80,000.00 Kepala Tukang Org 0.2000 50,000.00 10,000.00 Mandor Org 0.0333 50,000.00 1,666.67

TOTAL UPAH 111,666.67 111,666.67

BAHANKayu papan balau m3 0.0330 - Lem Fox Kg 0.1000

TOTAL BAHAN - -

23 PEKERJAAN MEMBUAT DAN PASANG LISPLANK / M2

UPAHPekerja Org 0.2800 30,000.00 8,400.00 Tukang Org 0.8000 40,000.00 32,000.00 Kepala Tukang Org 0.0800 50,000.00 4,000.00 Mandor Org 0.0140 50,000.00 700.00

TOTAL UPAH 45,100.00 45,100.00

BAHANKayu papan balau m3 0.0360 - Paku 2" - 5" kg 0.1000

TOTAL BAHAN - -

24 PEKERJAAN MEMBUAT RANGKA PLAFOND / M2

UPAHPekerja Org 0.1000 30,000.00 3,000.00 Tukang Org 0.3000 40,000.00 12,000.00 Kepala Tukang Org 0.0300 50,000.00 1,500.00

M2

Page 6: Kolam Renang Patra Jasa

Mandor Org 0.0050 50,000.00 250.00 TOTAL UPAH 16,750.00 16,750.00

BAHANKayu borneo balok m3 0.0130 - Paku 2" - 5" kg 0.2500

TOTAL BAHAN - -

25 PEKERJAAN PASANG LAPISAN PLAFOND / M2

UPAHPekerja Org 0.0420 30,000.00 1,260.00 Tukang Org 0.1200 40,000.00 4,800.00 Kepala Tukang Org 0.0120 50,000.00 600.00 Mandor Org 0.0021 50,000.00 105.00

TOTAL UPAH 6,765.00 6,765.00

BAHANGRC t. 4 mm m2 1.0000 - Paku 2" - 5" kg 0.0200

TOTAL BAHAN - -

26 PEKERJAAN PASANG ATAP GENTENG / M2

UPAHPekerja Org 0.0420 30,000.00 1,260.00 Tukang Org 0.1200 40,000.00 4,800.00 Kepala Tukang Org 0.0120 50,000.00 600.00 Mandor Org 0.0021 50,000.00 105.00

TOTAL UPAH 6,765.00 6,765.00

BAHANGRC t. 4 mm m2 1.0000 - Paku 2" - 5" kg 0.0200

TOTAL BAHAN - -

Page 7: Kolam Renang Patra Jasa

BONGKAR TAMAN

Bongkar pasangan bata

Samping tangga

= 0.35 x 3.60 x 2.00 x 6.00 = 15.12 m2

Dekat kolam anak (besar)

= 0.35 x 17.00 x 1.00 x 1.00 = 5.95 m2

Dekat kolam anak (kecil)

= 0.35 x 7.00 x 1.00 x 1.00 = 2.45 m2

Dekat stopkran

= 0.40 x 20.00 x 1.00 x 1.00 = 8.00 m2

Dekat kolam dewasa

= 0.40 x 15.00 x 1.00 x 1.00 = 6.00 m2

Jumlah 37.52 m2

BONGKAR SHOWER

Bongkar pasangan bata

Batas keliling

= 0.25 x 9.00 x 1.00 x 1.00 = 2.25 m2

Tiang

= 2.60 x 0.22 x 0.22 / 0.12 = 1.05 m2

Jumlah 3.30 m2

BONGKAR BANGKU BETON

Bongkar pasangan bata

Kecil

= 2.00 x 0.60 x 0.10 x 4.00 = 0.48 m3= 0.30 x 0.60 x 0.15 x 12.00 = 0.32 m3

Besar

= 3.00 x 0.60 x 0.10 x 2.00 = 0.36 m3= 0.30 x 0.60 x 0.15 x 6.00 = 0.16 m3

B7
RIZAL: tinggi
D7
RIZAL: panjang
B11
RIZAL: tinggi
D11
RIZAL: panjang
B15
RIZAL: tinggi
D15
RIZAL: panjang
B19
RIZAL: tinggi
D19
RIZAL: panjang
B23
RIZAL: tinggi
D23
RIZAL: panjang
B34
RIZAL: tinggi
D34
RIZAL: panjang
Page 8: Kolam Renang Patra Jasa

Jumlah 1.33 m3

BONGKAR TEMBOK KELILING KURANGI KETINGGIAN

Bongkar pasangan bata

= 136.00 x 0.40 = 54.40 m2

Bongkar keramik

= 136.00 x 0.30 = 40.80 m2= 7.50 x 1.40 = 10.50 m2= 12.00 x 1.40 = 16.80 m2

Jumlah = 68.10 m2

BONGKAR PARIT KELILING

Bongkar pasangan bata

= 135.00 x 0.20 x 2.00 x 1.00 = 54.00 m2Jumlah 54.00 m2

Bongkar beton penutup parit

= 135.00 x 0.50 x 0.05 x 1.00 = 3.38 m3Jumlah 3.38 m3

BONGKAR TANGGA

Bongkar keramik (7 unit)= {(0.63+0.075)*2+3.4*1.2}*7 = 38.43 m2

Jumlah = 38.43 m2

Bongkar cor lantai (6 unit)

= 0.40 x 1.20 x 0.05 x 5.00 = 0.12 m3

Jumlah 6 x 0.12 = 0.72 m3

Bongkar pasangan bata (6 unit)

= 1.035 x 2.00 = 2.07 m2= 0.250 x 1.20 = 0.30 m2= 0.300 x 1.20 = 0.36 m2= 0.550 x 1.20 = 0.66 m2= 0.250 x 1.20 = 0.30 m2

Jumlah 3.69 m2

Jumlah 6 x 3.69 = 22.14 m2

Bongkar pasangan bata (6 unit)(asumsi semuanya dari pasangan bata)

B93
RIZAL: lebar
D93
RIZAL: panjang
F93
RIZAL: jumlah
Page 9: Kolam Renang Patra Jasa

= 1.035 x 1.20 / 0.12 = 10.35 m2Jumlah = 10.35 m2

Jumlah 6 x 10.35 = 62.10 m2

BONGKAR KERAMIK

= 1,100.00 m2 (luas seluruh area) (a) = 389.00 m2 (luas kolam dewasa) (b)= 38.00 m2 (luas kolam anak) (c )= 12.6 m2 (luas tangga) (d)= 55.4 m2 (luas taman dalam) (e)= 7.4 m2 (samping parit kolam dewasa) (f)= 2.5 m2 (samping parit kolam anak) (g)= 2.78 m2 (papan loncat) (h)

Jumlah (a-b-c-d-e+f+g) = 617.68 m2

Bongkar Cor untuk dudukan pipa 4"

Page 10: Kolam Renang Patra Jasa

CIPING LANTAI & DINDING(a) (luas luar kolam dewasa) = 425.00 m2(b) (luas dalam kolam dewasa) = 389.00 m2(c) (bagian dalam kolam dewasa) = 7.40 m2(d) (luas luar kolam anak) = 50.00 m2(e) (luas dalam kolam anak) = 38.00 m2(f) (bagian dalam kolam anak) = 2.50 m2(g) (tembok keliling) == 136.00 x 0.30 = 40.80 m2= 7.50 x 1.40 = 10.50 m2= 12.00 x 1.40 = 16.80 m2

Jumlah (a-b+c+d-e+f+g) = 126.00 m2

URUGAN TANAH= 4.4 m3= 2.75 m3

Jumlah 7.15 m3

URUGAN PASIR= 1100 x 0.1 (seluruh lantai) = 110 m3= 50 x 0.1 (luas kolam anak + parit) = 5 m3= 465 x 0.1 (luas kolam dewasa + parit) = 46.5 m3

Jumlah 161.50 m3

COR LANTAI 1:3:5= 1100 x 0.05 (seluruh lantai) = 55 m3= 50 x 0.05 (luas kolam anak + parit) = 2.5 m3= 465 x 0.05 (luas kolam dewasa + parit) = 23.25 m3

Jumlah 80.75 m3

PASANGAN BATA 1:4

= 136.00 x 0.40 = 54.40 m2

PASANG KERAMIK LANTAI

(a) (luas seluruh area) = 1,100.00 m2 (b) (luas kolam dewasa) = 389.00 m2(c ) (luas kolam anak) = 38.00 m2

Jumlah = 673.00 m2

PASANG KERAMIK DINDING

a (samping parit kolam dewasa) = 11.1 m2b (samping parit kolam anak) = 3.75 m2c (papan loncat) = 2.78 m2d Dinding samping= 136.00 x 0.40 = 54.40 m2= 7.50 x 1.40 = 10.50 m2= 12.00 x 1.40 = 16.80 m2e Tangga = 47 x 1.20 = 56.40 m2

Page 11: Kolam Renang Patra Jasa

= 1.20 x 2.00 = 2.40 m2Jumlah = 158.13 m2

Page 12: Kolam Renang Patra Jasa

DAFTAR HARGA UPAH PEKERJA

NO JENIS PEKERJA HARGA UPAH SATUAN1 Pekerja Rp 30,000 hari2 Tukang Rp 40,000 hari3 Kepala Tukang Rp 50,000 hari4 Mandor Rp 50,000 hari5 Tk.las Rp 50,000 hari6 Pekerja Las Rp 40,000 hari7 Sewa mesin las potong Rp 30,000 hari8 Sewa mesin las sambung Rp 85,000 hari

DAFTAR HARGA BAHAN BANGUNAN

NO JENIS BAHAN BANGUNAN HARGA BAHAN SATUAN1 Kayu papan borneo Rp 3,000,000

2 Kayu borneo balok Rp 3,000,000 3 Paku 2" - 5" Rp 10,000 kg4 Semen 50 kg Rp 42,000 sak5 Semen putih Rp 65,000 sak6 Pasir urug Rp 65,000

7 Pasir pasang Rp 75,000

8 Pasir beton Rp 75,000

9 Tanah urug Rp 55,000

10 Split 2/3 Rp 160,000 11 Besi beton Rp 7,000 kg12 Kawat beton Rp 10,000 kg13 Bata merah Rp 300 bh14 O2 Rp 10,000

15 Acetylene Rp 35,000 16 Kawat Las RB Rp 21,000 kg17 Pipa pvc ø 4" Rp 45,000 m'18 Sambungan pvc ø 4" Rp 6,000 bh19 Pipa pvc ø 6" Rp 95,000 m'20 Sambungan pvc ø 6" Rp 15,000 bh21 Lem Rp 7,000 bh22 Shower S361C san'ei Rp 240,000 bh23 Siltip Rp 2,000 bh24 Sambungan Rp 15,000 bh25 Saringan H-51 Rp 140,000 bh26 Pip.galv. Ø 1/2" Rp 14,000 m'27 Siltip Rp 2,000 bh28 Sambungan ø 1/2" Rp 5,000 bh29 Cat F-Talit Rp 34,000 kg30 Thinner Rp 12,000 ltr31 Keramik 20/20 Rp 2,500 bh32 Gembok Globe Rp 30,000 bh33 L 50.50.5 Rp 7,000 kg

m3

m3

m3

m3

m3

m3

m3

m3

m3

Page 13: Kolam Renang Patra Jasa

34 Besi pelat t. 5 mm Rp 7,600 kg35 Engsel Rp 15,000 bh

Page 14: Kolam Renang Patra Jasa

60000/24

Page 15: Kolam Renang Patra Jasa

NO JENIS PEKERJAAN SATUAN KOEFISIEN HARGA TOTAL

1 PEKERJAAN BONGKAR PASANGAN BATA / M2

UPAHPekerja Org 0.4800 30,000.00 14,400.00 Mandor Org 0.0480 50,000.00 2,400.00

TOTAL UPAH 16,800.00 16,800.00

2 PEKERJAAN BONGKAR PIPA AIR / M'

UPAHPekerja Org 0.0300 30,000.00 900.00 Mandor Org 0.0500 50,000.00 2,500.00

TOTAL UPAH 3,400.00 3,400.00

3 PEKERJAAN BONGKAR LANTAI KERAMIK/ M2

UPAHPekerja Org 0.1000 30,000.00 3,000.00 Mandor Org 0.0100 50,000.00 500.00

TOTAL UPAH 3,500.00 3,500.00

4 PEKERJAAN CIPING LANTAI & DINDING / M2

UPAHPekerja Org 0.2000 30,000.00 6,000.00 Mandor Org 0.0200 50,000.00 1,000.00

TOTAL UPAH 7,000.00 7,000.00

5 PEKERJAAN BONGKAR LANTAI BETON / M3

UPAHPekerja Org 2.0000 30,000.00 60,000.00 Mandor Org 0.2000 50,000.00 10,000.00

TOTAL UPAH 70,000.00 70,000.00

6 PEKERJAAN BONGKAR BETON BERTULANG / M3

UPAHPekerja Org 4.2000 30,000.00 126,000.00 Tukang I Org 3.0000 40,000.00 120,000.00 Tukang besi I Org 2.4750 40,000.00 99,000.00 Kepala Tukang Org 0.3000 50,000.00 15,000.00 Mandor Org 0.2000 50,000.00 10,000.00

TOTAL UPAH 370,000.00 370,000.00

7 PEKERJAAN MEMBERSIHKAN LANTAI BEKAS BONGKARAN / M2

UPAHPekerja Org 0.1500 30,000.00 4,500.00 Mandor Org 0.0075 50,000.00 375.00

TOTAL UPAH 4,875.00 4,875.00

8 PEKERJAAN SETEL BESI / KG

UPAHPekerja Org 0.0200 30,000.00 600.00 Tukang Org 0.0050 40,000.00 200.00

JUMLAH HARGA

Page 16: Kolam Renang Patra Jasa

TOTAL UPAH 800.00 800.00

BAHANBesi siku kg 1.1000 7,000.00 7,700.00

TOTAL BAHAN 7,700.00 7,700.00

BAHANBesi pelat kg 1.1000 7,600.00 8,360.00

TOTAL BAHAN 8,360.00 8,360.00

9 PEKERJAAN LAS POTONG / M'

UPAHPekerja Org 0.2500 30,000.00 7,500.00 Tukang Org 0.1250 40,000.00 5,000.00 Sewa las potong Org 0.1250 30,000.00 3,750.00

TOTAL UPAH 16,250.00 16,250.00

BAHANO2 m3 0.4760 10,000.00 4,760.00 1 m3 0.1600 35,000.00 5,600.00

TOTAL BAHAN 10,360.00 10,360.00

10 PEKERJAAN LAS SAMBUNG / M'

UPAHPekerja Org 0.2500 30,000.00 7,500.00 Tukang Org 0.1250 40,000.00 5,000.00 Sewa las sambung Org 0.1250 30,000.00 3,750.00

TOTAL UPAH 16,250.00 16,250.00

BAHANKawat Las RB kg 0.3000 21,000.00 6,300.00

TOTAL BAHAN 6,300.00 6,300.00

11 PEKERJAAN URUGAN TANAH / M3

UPAHPekerja Org 0.3000 30,000.00 9,000.00 Mandor Org 0.0100 50,000.00 500.00

TOTAL UPAH 9,500.00 9,500.00

BAHAN

Tanah urug 1.2000 55,000.00 66,000.00 TOTAL BAHAN 66,000.00 66,000.00

12 PEKERJAAN URUGAN PASIR / M3

UPAHPekerja Org 0.3000 30,000.00 9,000.00 Mandor Org 0.0100 50,000.00 500.00

TOTAL UPAH 9,500.00 9,500.00

BAHAN

Pasir urug 1.2000 65,000.00 78,000.00 TOTAL BAHAN 78,000.00 78,000.00

13 PEKERJAAN PASANGAN BATA 1:4 < 5 M / M3

UPAHPekerja Org 4.5000 30,000.00 135,000.00 Tukang Org 1.5000 40,000.00 60,000.00

m3

m3

Page 17: Kolam Renang Patra Jasa

Kepala Tukang Org 0.1500 50,000.00 7,500.00 Mandor Org 0.2250 50,000.00 11,250.00

TOTAL UPAH 213,750.00 213,750.00

BAHANBatu bata bh 450.0000 300.00 135,000.00 Pasir pasang m3 0.4060 75,000.00 30,450.00 Semen 50 kg Zak 2.5120 42,000.00 105,504.00

TOTAL BAHAN 270,954.00 270,954.00

14 PEKERJAAN PEMBUATAN BAK KONTROL / BH

UPAHPekerja Org 1.8500 30,000.00 55,500.00 Tukang Org 0.7710 40,000.00 30,840.00 Kepala Tukang Org 0.1055 50,000.00 5,277.00 Mandor Org 0.0810 50,000.00 4,050.00

TOTAL UPAH 95,667.00 95,667.00

BAHANPasir pasang m3 0.1110 75,000.00 8,325.00 Bata merah bh 105.0000 300.00 31,500.00 Semen zak 1.1900 42,000.00 49,980.00 split 2/3 cm. m3 0.1110 160,000.00 17,760.00 Besi beton kg 2.0000 7,000.00 14,000.00 Kawat beton kg 0.0360 10,000.00 360.00 Kayu terentang m3 0.0072 3,000,000.00 21,600.00 Paku kg 0.0720 10,000.00 720.00

TOTAL BAHAN 144,245.00 144,245.00

15 PEKERJAAN PASANG PIPA PVC / M'

UPAHPekerja Org 0.0375 30,000.00 1,125.00 Tukang Org 0.0625 40,000.00 2,500.00 Kepala Tukang Org 0.0063 50,000.00 315.00 Mandor Org 0.0017 50,000.00 85.00

TOTAL UPAH 4,025.00 4,025.00

BAHANPipa pvc ø 4" m' 1.0000 45000.0000 45,000.00 Lem bh 0.2500 7000.0000 1,750.00 Sambungan pvc ø 4" bh 0.2500 6000.0000 1,500.00

TOTAL BAHAN 48,250.00 48,250.00

BAHANPipa pvc ø 6" m' 1.0000 95000.0000 95,000.00 Lem bh 0.2500 7000.0000 1,750.00 Sambungan pvc ø 6" bh 0.2500 15000.0000 3,750.00

TOTAL BAHAN 100,500.00 100,500.00

16 PEKERJAAN SANITARY / BH

UPAHPekerja Org 0.1000 30,000.00 3,000.00 Tukang Org 0.1000 40,000.00 4,000.00

TOTAL UPAH 7,000.00 7,000.00

BAHANShower S361C san'ei bh 1.0000 240,000.00 240,000.00 Siltip bh 0.1000 2,000.00 200.00 Sambungan bh 1.0000 15,000.00 15,000.00

TOTAL BAHAN 255,200.00 255,200.00

Page 18: Kolam Renang Patra Jasa

BAHANSaringan H-51 bh 1.0000 140,000.00 140,000.00 Siltip bh 0.1000 2,000.00 Sambungan bh 1.0000 15,000.00 15,000.00

TOTAL BAHAN 155,000.00 155,000.00

17 PEKERJAAN PASANG PIPA PVC / M'

UPAHPekerja Org 0.1500 30,000.00 4,500.00 Tukang Org 0.2500 40,000.00 10,000.00 Kepala Tukang Org 0.0250 50,000.00 1,250.00 Mandor Org 0.0066 50,000.00 330.00

TOTAL UPAH 16,080.00 16,080.00

BAHANPip.galv. Ø 1/2" m' 1.0000 14,000.00 14,000.00 Siltip bh 0.1000 2,000.00 200.00 Sambungan ø 1/2" bh 1.0000 5,000.00 5,000.00

TOTAL BAHAN 19,200.00 19,200.00

18 PEKERJAAN CAT BESI / M2

UPAHPekerja Org 0.1000 30,000.00 3,000.00 Tukang Org 0.1500 40,000.00 6,000.00 Kepala Tukang Org 0.0150 50,000.00 750.00 Mandor Org 0.0050 50,000.00 250.00

TOTAL UPAH 10,000.00 10,000.00

BAHANCat F-Talit kg 0.0625 34,000.00 2,125.00 Thinner ltr 0.0060 12,000.00 72.00

TOTAL BAHAN 2,197.00 2,197.00

19 PEKERJAAN PASANG GEMBOK / BH

UPAHTukang Org 0.0625 40,000.00 2,500.00

TOTAL UPAH 2,500.00 2,500.00

BAHANGembok Globe bh 1.0000 30,000.00 30,000.00

TOTAL BAHAN 30,000.00 30,000.00

BAHANEngsel bh 1.0000 15,000.00 15,000.00

TOTAL BAHAN 15,000.00 15,000.00

20 PEKERJAAN PASANG KERAMIK LANTAI / M2

UPAHPekerja Org 0.5000 30,000.00 15,000.00 Tukang Org 0.2500 40,000.00 10,000.00 Kepala Tukang Org 0.0250 50,000.00 1,250.00 Mandor Org 0.0250 50,000.00 1,250.00

TOTAL UPAH 27,500.00 27,500.00

BAHANKeramik 20x20 roman bh 25.0000 2,500.00 62,500.00 Semen 50 kg Zak 0.2000 42,000.00 8,400.00 Pasir pasang m3 0.0330 75,000.00 2,475.00

Page 19: Kolam Renang Patra Jasa

Semen putih Zak 0.0200 65,000.00 1,300.00 TOTAL BAHAN 74,675.00 74,675.00

21 PEKERJAAN PASANG KERAMIK DINDING / M2

UPAHPekerja Org 0.6250 30,000.00 18,750.00 Tukang Org 0.3125 40,000.00 12,500.00 Kepala Tukang Org 0.0313 50,000.00 1,562.50 Mandor Org 0.0313 50,000.00 1,562.50

TOTAL UPAH 34,375.00 34,375.00

BAHANKeramik 20x20 roman bh 25.0000 2,500.00 62,500.00 Semen 50 kg Zak 0.2000 42,000.00 8,400.00 Pasir pasang m3 0.0330 75,000.00 2,475.00 Semen putih Zak 0.0200 65,000.00 1,300.00

TOTAL BAHAN 74,675.00 74,675.00

22 PEKERJAAN COR BETON 1 pc : 3 ps : 5 split / M3

UPAHPekerja Org 6.0000 30,000.00 180,000.00 Tukang Org 0.5000 40,000.00 20,000.00 Kepala Tukang Org 0.0500 50,000.00 2,500.00 Mandor Org 0.3000 50,000.00 15,000.00

TOTAL UPAH 217,500.00 217,500.00

BAHANSemen 50 kg sak 4.5400 42,000.00 190,680.00 Pasir beton m3 0.5400 75,000.00 Split 2/3 cm m3 0.9100 160,000.00 145,600.00

TOTAL BAHAN 336,280.00 336,280.00

Page 20: Kolam Renang Patra Jasa

RENCANA ANGGARAN BIAYA

RENOVASI KOLAM RENANG PATRA JASACIREBON

NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN

JUMLAH HARGA SATUAN

A PEKERJAAN BONGKARAN

1 Bongkar taman bagian dalama. Bongkar pasangan bata 37.52 m2 16,800.00 630,336.00 b. Bongkar tanaman dan tanah 1.00 ls 100,000.00 100,000.00

2 Bongkar fasilitas kolam (tangga besi, dll) 1.00 ls 50,000.00 50,000.00 3 Bongkar shower

a. Bongkar pasangan bata 3.30 m2 16,800.00 55,440.00 b. Bongkar sanitary 10.50 m' 3,400.00 35,700.00

4 Bongkar bangku beton 1.33 m3 370,000.00 490,620.00 5 Bongkar beton penutup parit 3.38 m3 70,000.00 236,250.00 6 Bongkar parit eksisting

a. Bongkar tutup beton 1.00 ls 100,000.00 100,000.00 b. Bongkar pasangan bata 54.00 m2 16,800.00 907,200.00

7 Bongkar tanggaa. Bongkar keramik 38.43 m2 3,500.00 134,505.00 b. Bongkar rabat beton 0.72 m3 70,000.00 50,400.00 c. Bongkar pasangan bata 22.14 m2 16,800.00 371,952.00

8 Bongkar keramik seluruh lantai 617.68 m2 3,500.00 2,161,880.00 9 Bongkar tembok keliling kurangi ketinggian.

a. Bongkar pasangan bata. 54.40 m2 16,800.00 913,920.00 b. Bongkar keramik bagian bawah. 68.10 m2 3,500.00 238,350.00

10 Bongkar beton untuk dudukan pipa 4" 0.76 m3 70,000.00 52,920.00 Jumlah 6,529,473.00

B PEKERJAAN RENOVASI

1 Urugan tanah 7.15 m3 75,500.00 539,825.00 2 Urugan pasir 161.50 m3 87,500.00 14,131,250.00 3 Cor lantai kerja 1:3:5 t. 5 cm 81.11 m3 553,780.00 44,917,095.80 4 22.14 m2 484,704.00 10,731,346.56

5 Pasang lantai keramik 20 cm x 20 cm 668.19 m2 102,175.00 68,272,057.81 6 Pasang dinding keramik 20 cm x 20 cm 158.13 m2 109,050.00 17,244,076.50 7 Pembuatan tempat shower.

a. Pasangan bata 1:4 untuk pembatas keliling & tiang 3.30 m2 484,704.00 1,599,523.20 b. Urugan pasir t. 10 cm 0.48 m3 87,500.00 42,109.38 c. Cor lantai kerja 1:3:5 t. 5 cm. 0.24 m3 553,780.00 133,253.31 d. Pasang lantai keramik muka kasar 20 cm x 2 cm 7.51 m2 109,050.00 819,238.13

8 Pembuatan tutup stop krana. Buat rangka tutup dari L 50.50.5 32.52 kg 8,500.00 276,420.00 b. Pasang pelat tutup t. 5 mm 21.89 kg 9,160.00 200,502.32 c. Pasang engsel 2.00 bh 17,500.00 35,000.00 c. Las potong 1.98 m' 26,610.00 52,687.80 d. Las sambung 1.98 m' 22,550.00 44,649.00 e. Pasang gembok Globe 1.00 bh 32,500.00 32,500.00 f. Cat Ftalit seluruh permukaan tutup 1.98 m2 12,197.00 24,150.06

Jumlah 159,095,684.87

Pasangan bata 1:4 untuk memperbaiki tembok keliling dan pinggir kolam.

Page 21: Kolam Renang Patra Jasa

RENCANA ANGGARAN BIAYA

RENOVASI KOLAM RENANG PATRA JASACIREBON

NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN

JUMLAH HARGA SATUAN

C PEKERJAAN SANITARY

1 Pembuatan bak kontrol 40 cm x 40 cm x 40 cm 31.00 unit 239,912.00 7,437,272.00 2 Pasang pipa PVC ø 4" untuk parit & shower 88.00 m' 52,275.00 4,600,200.00 3 Pasang pipa PVC ø 6" untuk parit 124.00 m' 104,525.00 12,961,100.00 4 Pasang pipa galvanis ø 1/2". 78.00 m' 35,280.00 2,751,840.00 5 Pasang shower 2.00 bh 262,200.00 524,400.00 6 Pasang beltraf 1.00 bh 162,000.00 162,000.00

Jumlah 28,436,812.00

D PEKERJAAN LAIN-LAIN

1 Pembuangan ex bongkaran 1.00 ls 2,500,000.00 2,500,000.00 2 Perapihan bekas kerja 1.00 ls 500,000.00 500,000.00

Jumlah 3,000,000.00

a Jumlah Keseluruhan 197,061,969.87 b Keuntungan dan resiko (15% x a) 29,559,295.48

Jumlah (a + b) 226,621,265.35

Dibulatkan 226,621,000.00

Terbilang :

Dua ratus dua puluh enam juta enam ratus dua puluh satu ribu 0 0 0 rupiah.