KAMPUS MEDAN

97
ANALISA HARGA SATUAN (DASAR) No Item Pekerjaan (Rp) 1 Pekerjaan Pasangan Bata Merah (1:2) : (per m2) Material : - Batu Bata Merah : 75 pcs @ Rp.220 /pcs 16,500 - Adukan (1 : 2) tebal 2 cm: Rp. 350000 /m3 atau Rp. 7000/ 7,000 Semen Rp. 37.000/sak ; 20 sak/m3 Pasir Rp. 155.000/m3 - Ongkos kirim material 5,000 - Ongkos Penurunan Material 5,000 Ongkos Pasang : Koefisien unit Harga - Tukang Batu 0.1 hr 50,000 5,000 - Knek / Pekerja 0.32 hr 35,000 11,200 - Kepala Tukang 0.01 hr 60,000 600 - Mandor Sipil (Supervisi) 0.015 hr 75,000 1,125 2 Pekerjaan Pasangan Bata Merah (1:3) : (per m2) Material : - Batu Bata Merah : 75 pcs @ Rp.220 /pcs 16,500 - Adukan (1 : 3) tebal 2 cm: Rp. 301250 /m3 atau Rp. 6.100 6,100 Semen Rp. 37.000/sak ; 20 sak/m3 Pasir Rp. 155.000/m3 - Ongkos Penurunan Material 5,000 - Ongkos kirim material 5,000 Ongkos Pasang : Koefisien unit Harga - Tukang Batu 0.1 hr 50,000 5,000 - Knek / Pekerja 0.32 hr 35,000 11,200 - Kepala Tukang 0.01 hr 60,000 600 - Mandor Sipil (Supervisi) 0.015 hr 75,000 1,125 3 Pekerjaan Pasangan Bata Merah (1:5) : (per m2) Material : - Batu Bata Merah : 75 pcs @ Rp.220 /pcs 16,500 - Adukan (1 : 5) tebal 2 cm: Rp. 252000 /m3 atau Rp. 5.100 5,100 Semen Rp. 37.000/sak ; 20 sak/m3 Pasir Rp. 155.000/m3 - Ongkos Penurunan Material 5,000 - Ongkos kirim material Rp. 5.000/m2 5,000 Ongkos Pasang : Koefisien unit Harga - Tukang Batu 0.1 hr 50,000 5,000 - Knek / Pekerja 0.32 hr 35,000 11,200 - Kepala Tukang 0.01 hr 60,000 600 - Mandor Sipil (Supervisi) 0.015 hr 75,000 1,125 4 Pekerjaan Plesteran & Aci ( 1 : 2) Material Adukan: - Adukan (1 : 2) tebal 1,5 cm: Rp. 350000 /m3 atau Rp. 530 5,300 Harga /m 2

Transcript of KAMPUS MEDAN

Page 1: KAMPUS MEDAN

ANALISA HARGA SATUAN (DASAR)

No Item Pekerjaan(Rp)

1 Pekerjaan Pasangan Bata Merah (1:2) : (per m2)Material :

- Batu Bata Merah : 75 pcs @ Rp.220 /pcs 16,500- Adukan (1 : 2) tebal 2 cm: Rp. 350000 /m3 atau Rp. 7000/m2 7,000

Semen Rp. 37.000/sak ; 20 sak/m3Pasir Rp. 155.000/m3

- Ongkos kirim material 5,000- Ongkos Penurunan Material 5,000

Ongkos Pasang : Koefisien unit Harga- Tukang Batu 0.1 hr 50,000 5,000- Knek / Pekerja 0.32 hr 35,000 11,200- Kepala Tukang 0.01 hr 60,000 600- Mandor Sipil (Supervisi) 0.015 hr 75,000 1,125

2 Pekerjaan Pasangan Bata Merah (1:3) : (per m2)Material :

- Batu Bata Merah : 75 pcs @ Rp.220 /pcs 16,500- Adukan (1 : 3) tebal 2 cm: Rp. 301250 /m3 atau Rp. 6.100/m2 6,100

Semen Rp. 37.000/sak ; 20 sak/m3Pasir Rp. 155.000/m3

- Ongkos Penurunan Material 5,000- Ongkos kirim material 5,000

Ongkos Pasang : Koefisien unit Harga- Tukang Batu 0.1 hr 50,000 5,000- Knek / Pekerja 0.32 hr 35,000 11,200- Kepala Tukang 0.01 hr 60,000 600- Mandor Sipil (Supervisi) 0.015 hr 75,000 1,125

3 Pekerjaan Pasangan Bata Merah (1:5) : (per m2)Material :

- Batu Bata Merah : 75 pcs @ Rp.220 /pcs 16,500- Adukan (1 : 5) tebal 2 cm: Rp. 252000 /m3 atau Rp. 5.100/m2 5,100

Semen Rp. 37.000/sak ; 20 sak/m3Pasir Rp. 155.000/m3

- Ongkos Penurunan Material 5,000- Ongkos kirim material Rp. 5.000/m2 5,000

Ongkos Pasang : Koefisien unit Harga- Tukang Batu 0.1 hr 50,000 5,000- Knek / Pekerja 0.32 hr 35,000 11,200- Kepala Tukang 0.01 hr 60,000 600- Mandor Sipil (Supervisi) 0.015 hr 75,000 1,125

4 Pekerjaan Plesteran & Aci ( 1 : 2)Material Adukan:

- Adukan (1 : 2) tebal 1,5 cm: Rp. 350000 /m3 atau Rp. 5300/m2 5,300

Harga /m2

C13
Sub Kontraktor Sipil : Rp. 15000 /m2
C27
Sub Kontraktor Sipil : Rp. 15000 /m2
C41
Sub Kontraktor Sipil : Rp. 15000 /m2
Page 2: KAMPUS MEDAN

Semen Rp. 37.000/sak ; 20 sak/m3Pasir Rp. 155.000/m3

- Ongkos Penurunan Material 5,000- Ongkos kirim material Rp. 5.000/m2 5,000- Semen Acian 2 kg 800 1,600

Ongkos Pasang : Koefisien unit Harga- Tukang Batu 0.15 hr 50,000 7,500- Knek / Pekerja 0.2 hr 35,000 7,000- Kepala Tukang 0.015 hr 60,000 900- Mandor Sipil (Supervisi) 0.01 hr 75,000 750

5 Pekerjaan Plesteran & Aci ( 1 : 5)Material :

- Adukan (1 : 5) tebal 1,5 cm: Rp. 252000 /m3 atau Rp. 3800/m2 3,800Semen Rp. 37.000/sak ; 20 sak/m3Pasir Rp. 155.000/m3

- Ongkos Penurunan Material 5,000- Ongkos kirim material Rp. 5.000/m2 5,000

Ongkos Pasang : Koefisien unit Harga- Tukang Batu 0.15 hr 50,000 7,500- Knek / Pekerja 0.2 hr 35,000 7,000- Kepala Tukang 0.015 hr 60,000 900- Mandor Sipil (Supervisi) 0.01 hr 75,000 750

6 Pekerjaan Lantai Homogeneus Tile 60x60 cmMaterial :

- Homogeneus Tile 60 x 60 cm 100,000Merk D'eurogres Type FHQ 6207 Abu-abu

- Plesteran tebal 4 cm (Adukan 1: 3) 12,050- Pemotongan Keramik 5,000- Pengisian sela-sela antar keramik dgn AM 53 2,000- Pembersihan dengan bahan G0-Getter, Johnson Wax 3,000- Ongkos kirim 5,000- Ongkos Penurunan Material 5,000- Ongkos pasang 25,000

6 Pekerjaan Lantai Homogeneus Tile 60x60 cm (include bongkar lantai existing)Material :

- Homogeneus Tile 60 x 60 cm 100,000Merk D'eurogres Type FHQ 6207 Abu-abu

- Plesteran tebal 4 cm (Adukan 1: 3) 12,050- Pemotongan Keramik 5,000- Pengisian sela-sela antar keramik dgn AM 53 2,000- Pembersihan dengan bahan G0-Getter, Johnson Wax 3,000- Bongkar & Buang puing floor tile existing 7,500- Ongkos kirim 5,000- Ongkos Penurunan Material 5,000- Ongkos pasang 25,000

6 Pekerjaan Lantai Ceramic Tile 40 x 40 cm

C55
Sub Kontraktor Sipil : Rp. 15000 /m2
C68
Sub Kontraktor Sipil : Rp. 15000 /m2
Page 3: KAMPUS MEDAN

Material :- Ceramic Tile 40 x 40 cm 40,000

ex. Roman Gress- Plesteran tebal 4 cm (Adukan 1: 3) 12,050- Pemotongan Keramik 2,500- Pengisian sela-sela antar keramik dgn AM 53 2,000- Ongkos kirim 5,000- Ongkos Penurunan Material 5,000- Ongkos pasang 25,000

6 Pekerjaan Lantai Ceramic Tile 40 x 40 cm (include bongkar lantai existing)Material :

- Ceramic Tile 40 x 40 cm 40,000ex. Roman Gress

- Plesteran tebal 4 cm (Adukan 1: 3) 12,050- Pemotongan Keramik 2,500- Pengisian sela-sela antar keramik dgn AM 53 2,000- Bongkar & Buang puing floor tile existing 7,500- Ongkos kirim 5,000- Ongkos Penurunan Material 5,000- Ongkos pasang 25,000

7 Pekerjaan Partisi Gypsum Standard 1 Muka ( Hollow 40x40 cm )Koefisien unit Harga

- Hollow 40x40 mm 0.8 mm 1.389 btg 28,000 38,900- Jaya Board 12 mm 0.347 lbr 57,000 19,800- Paper tape 0.096 rol 16,200 1,600- Finishing Compound 0.347 kg 2,850 1,000- Gypsum Screw 14 pcs 50 700- Phiser S8 2 pcs 25 50- Screw S8 2 pcs 50 100- Ongkos kirim 5,000- Ongkos Penurunan Material 5,000- Ongkos Pasang 25,000

8 Pekerjaan Partisi Gypsum Standard 2 Muka ( Hollow 40x40 cm )Koefisien unit Harga

- Hollow 40x40 mm 0.8 mm 1.389 btg 28,000 38,900- Jaya Board 12 mm 0.694 lbr 57,000 39,600- Paper tape 0.192 rol 16,200 3,200- Finishing Compound 0.694 kg 2,850 2,000- Screw 28 pcs 50 1,400- Phiser S8 2 pcs 25 50- Screw S8 2 pcs 50 100- Ongkos kirim 5,000- Ongkos Penurunan Material 5,000- Ongkos Pasang 25,000

9 Pekerjaan Pemasangan Plafon Gypsum Standard ( Hollow 40x40 cm )Koefisien unit Harga

C126
Length : 75 m
C127
UB 10 Rp. 57000 / sak=20 kg
C139
Length : 75 m
C140
UB 10 Rp. 57000 / sak=20 kg
Page 4: KAMPUS MEDAN

- Hollow 40x40 mm 0.8 mm 1.042 btg 28,000 29,200- Gantungan 0.25 btg 28,000 7,000- Connector / Hollow Clip 1.388 pcs 625 900- Suspension Bracket to Concrete 220 0.694 pcs 925 700- gun powder + nails 0.694 set 2,000 1,400- Jaya Board 9 mm 0.347 lbr 45,000 15,700- Lis Gypsum 10 cm 0.15 btg 17,500 2,700- Paper tape 0.096 rol 16,200 1,600- Finishing Compound 0.347 kg 2,850 1,000- Screw 14 pcs 50 700- Ongkos kirim 5,000- Ongkos Penurunan Material 5,000- Ongkos Pasang (include gypsum): 20,500

10 Pekerjaan Pemasangan Plafon Gypsum Standard (Metal Furing)Material (ex. Jaya Board) : Koefisien unit Harga

- Suspension clip PN 223 2.778 pcs 2,375 6,600- Suspension Rod PN 225 0.694 btg 7,600 5,300- Joiner PN 207 1.388 pcs 800 1,200- Connector PN 209 1.388 pcs 625 900- Top Cros Rail PN 200 0.694 btg 23,200 16,200- Furring Channel PN 204 0.694 btg 35,300 24,500- Suspension Bracket to Concrete 220 0.694 pcs 925 700- gun powder + nails 0.694 set 2,000 1,400- Jaya Board 9 mm 0.347 lbr 45,000 15,700- Lis Gypsum 10 cm 0.15 btg 17,500 2,700- Paper tape 0.096 rol 16,200 1,600- Finishing Compound 0.347 kg 2,850 1,000- Screw 14 pcs 50 700- Ongkos kirim 5,000- Ongkos Penurunan Material 5,000- Ongkos Pasang (include gypsum): 20,500

11 Pekerjaan Bore Pile K-250Koefisien unit Harga

- Mobilisasi & Demobilisasi- Pekerjaan persiapan - Pengeboran - Handling Beton

- Handling pembesian 1 445,500 445,500- Beton 250 kg 8,000 2,000,000

- Besi 1 36,000 36,000

12 Pekerjaan Pile Cap Beton K-250Koefisien unit Harga

- Adukan Beton K-250 (Ready mix) 1 445,500 445,500- Pembesian 250 kg 8,000 2,000,000

- Bekisting Batako 1 36,000 36,000

13 Pekerjaan Kolom Beton K-250

m3

m3

m3

m3

C156
Length : 2 m
C157
Length : 75 m
C158
UB 10 Rp. 57000 / sak=20 kg
C175
Length : 2 m
C176
Length : 75 m
C177
UB 10 Rp. 57000 / sak=20 kg
Page 5: KAMPUS MEDAN

Koefisien unit Harga

- Adukan Beton K-250 (Ready mix) 1 445,500 445,500- Pembesian 160 kg 8,000 1,280,000

- Bekisting kayu/multipleks 9 mm 1 141,100 141,100

14 Pekerjaan Balok Beton K-250Koefisien unit Harga

- Adukan Beton K-250 (Ready mix) 1 445,500 445,500- Pembesian 170 kg 8,000 1,360,000

- Perancah Kayu 1 332,900 332,900

- Bekisting kayu/multipleks 9 mm 1 141,100 141,100

15 Pekerjaan Pelat Lantai K-300 (Rigid driveway)Koefisien unit Harga

- Adukan Beton K-300 (Ready mix) 1 467,500 467,500- Pembesian 110 kg 8,000 880,000

- Bekisting Pelat Besi 1 423,300 423,300

m3

m3

m3

m3

m3

m3

m3

Page 6: KAMPUS MEDAN

(Rp) Pekerja 0.3200 hr 35000 11,20051,425 Tukang batu 0.1000 hr 50000 5,000

Mandor 0.0150 hr 75000 1,125Kepala Tukang 0.0100 hr 60000 600

220000

103333.333333333

246666.666666667350000

7000

50,525

0.048 129166.666666667 116250123333.333333333 185000

252500 301250

5050 6025

49,525

33,050

Pasir pasang 0.0170

Harga Satuan /m2

Page 7: KAMPUS MEDAN

Semen PC ( 50 kg ) 8.5200 Pekerja 0.2000 Tukang batu 0.1500 Mandor 0.0100 Kepala Tukang 0.0150

5250

29,9503780

157,050

Pekerjaan Lantai Homogeneus Tile 60x60 cm (include bongkar lantai existing)164,550

Page 8: KAMPUS MEDAN

91,550

99,050

97,150

120,250

91,400

Page 9: KAMPUS MEDAN

109,000

2,481,500

2,481,500

Page 10: KAMPUS MEDAN

1,866,600

2,279,500

1,770,800

Page 11: KAMPUS MEDAN

RESUME ANALISA TEKNIS

HARGA SATUAN PEKERJAAN TANAH

NO URAIAN KOEF. SAT.

TN : PEKERJAAN TANAH

Pekerja 0.0500 hrMandor 0.0050 hrAlat bantu 0.6000 set

JUMLAHDIBULATKAN

Pekerja 0.4000 hrMandor 0.0400 hr

JUMLAHDIBULATKAN

Pekerja 0.5260 hrMandor 0.0520 hr

JUMLAHDIBULATKAN

Pekerja 0.7350 hrMandor 0.0730 hr

JUMLAHDIBULATKAN

Pekerja 0.6250 hrMandor 0.0620 hr

JUMLAHDIBULATKAN

Pekerja 1.2500 hrMandor 0.1250 hr

JUMLAHDIBULATKAN

Pekerja 0.8230 hrMandor 0.0830 hr

JUMLAHDIBULATKAN

Pekerja 0.5160 hrMandor 0.5000 hr

JUMLAHDIBULATKAN

Pekerja 0.1920 hrMandor 0.0190 hr

JUMLAHDIBULATKAN

1 m3 - Perataan Tanah

1 m3 - Galian Tanah Biasa Kedalamn 1 m

1 m3 - Galian Tanah Biasa Kedalamn 1 m - 2 m

1 m3 - Galian Tanah Biasa Kedalamn 2 m - 3 m

1 m3 - Galian Tanah Keras

1 m3 - Galian Tanah Berbatu

1 m3 - Galian Tanah Lumpur

1 m3 - Angkutan Galian Jarak Max. 30 m

1 m3 - Urugan Kembali Galian Tanah

Page 12: KAMPUS MEDAN

Pekerja 0.5000 hrMandor 0.0500 hr

JUMLAHDIBULATKAN

Pekerja 0.5000 hrMandor 0.0500 hr

JUMLAHDIBULATKAN

Pasir urug 1.2000 m3Pekerja 0.3000 hrMandor 0.0100 hrAlat bantu 0.6000 set

JUMLAHDIBULATKAN

Pekerja 0.5000 hrMandor 0.0200 hrAlat bantu 0.6000 set

JUMLAHDIBULATKAN

Sirtu 1.2000 m3Pekerja 0.2500 hrMandor 0.0250 hrAlat bantu 0.6000 set

JUMLAHDIBULATKAN

Pekerja 2.3520 hrMandor 0.0388 hrAlat bantu 1.0000 set

JUMLAHDIBULATKAN

Pekerja 1.9600 hrMandor 0.0323 hrKompresor kap 400-6500 ltr/ mnt 0.1000 jamJack Hammer 0.1000 jam

JUMLAHDIBULATKAN

1 m3 - Pemadatan Tanah ( tiap 20 cm )

1 m3 - Pemadatan tanah ( tiap 20 cm ) dengan timbris

1 m3 - Urugan Pasir Bawah Lantai & Pondasi

1 m3 - Urugan tanah bekas galian pondasi ( manual )

1 m3 - Urugan Sirtu

1 m3 - Bongkaran / Galian Struktur Bangunan ( manual )

1 m3 - Bongkaran / Galian Struktur bangunan ( alat berat )

Page 13: KAMPUS MEDAN

RESUME ANALISA TEKNIS

HARGA SATUAN PEKERJAAN TANAH

HARGA SAT. JUMLAH

#REF! #REF!#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

Page 14: KAMPUS MEDAN

#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

104,500 125,400 #REF! #REF!#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

#REF! #REF!#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

104,500 125,400 #REF! #REF!#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

#REF! #REF!#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

#REF! #REF!#REF! #REF!

50,000 5,000 30,000 3,000

JUMLAH #REF!DIBULATKAN #REF!

Page 15: KAMPUS MEDAN

RESUME ANALISA TEKNIS

HARGA SATUAN PEKERJAAN PONDASI & BETON

NO URAIAN KOEF. SAT.

PDS : PEKERJAAN PONDASI BATU KALI

Pasir pasang 0.4270 m3Batu kali 1.1000 m3Semen PC ( 50 kg ) 267.0000 kgPekerja 1.5000 hrTukang batu 0.6000 hrMandor 0.0750 hrKepala tukang 0.0600 hr

JUMLAHDIBULATKAN

BTN : PEKERJAAN BETON

Pasir beton 0.5070 m3Split pecah mesin 2/3 0.7160 m3Semen PC 50 kg 5.0000 zakPekerja 1.8000 hrTukang batu 0.4750 hrmandor 0.2858 hrAlat bantu 2.5000 set

JUMLAHDIBULATKAN

Pasir beton 0.5070 m3Split pecah mesin 2/3 0.7160 m3Semen PC 50 kg 9.0000 zakPekerja 1.8000 hrTukang batu 0.4858 hrmandor 0.2608 hrAlat bantu 2.5000 set

JUMLAHDIBULATKAN

Pasir beton 0.5070 m3Split pecah mesin 2/3 0.7160 m3Semen PC 50 kg 11.0000 zakPekerja 1.8000 hrTukang batu 0.2608 hrmandor 0.5858 hrAlat bantu 2.5000 set

JUMLAHDIBULATKAN

Pasir beton 0.4000 m3Split pecah mesin 2/3 0.7400 m3Semen PC 50 kg 11.8000 zakPekerja 1.8000 hr

1 m3 - Pas. Pondasi batu kali 1 : 2

1 m3 - Cor beton K.125 ( manual )

1 m3 - Cor beton K. 175 ( manual )

1 m3 - Cor beton K. 225 ( manual )

1 m3 - Cor beton K. 250 ( manual )

Page 16: KAMPUS MEDAN

Tukang batu 0.2620 hrmandor 0.6270 hrAlat bantu 2.5000 set

JUMLAHDIBULATKAN

1 m3 - Cor beton K. 125 dengan readymixBeton readymix K. 125 1.0000 m3Pekerja 0.5508 hrTukang batu 0.1377 hrmandor 0.0688 hrAlat bantu 2.5000 set

JUMLAHDIBULATKAN

Beton readymix K. 225 1.0000 m3Pekerja 0.6885 hrTukang batu 0.1377 hrmandor 0.0688 hrConcrete vibrator 0.4819 jamAlat bantu 2.5000 set

JUMLAHDIBULATKAN

Beton readymix K. 250 1.0000 m3Pekerja 0.6885 hrTukang batu 0.1377 hrmandor 0.0688 hrConcrete vibrator 0.4819 jamAlat bantu 2.5000 set

JUMLAHDIBULATKAN

Beton readymix K. 300 1.0000 m3Pekerja 0.6885 hrTukang batu 0.1377 hrmandor 0.0688 hrConcrete vibrator 0.4819 jamAlat bantu 2.5000 set

JUMLAHDIBULATKAN

Beton readymix K. 350 1.0000 m3Pekerja 0.6885 hrTukang batu 0.1377 hrmandor 0.0688 hrConcrete vibrator 0.4819 jamAlat bantu 2.5000 set

JUMLAHDIBULATKAN

Beton readymix K. 400 1.0000 m3Pekerja 0.6885 hrTukang batu 0.1377 hrmandor 0.0688 hr

1 m3 - Cor beton K. 225 dengan readymix

1 m3 - Cor beton K. 250 dengan readymix

1 m3 - Cor beton K. 300 dengan readymix

1 m3 - Cor beton K. 350 dengan readymix

1 m3 - Cor beton K. 400 dengan readymix

Page 17: KAMPUS MEDAN

Concrete vibrator 0.4819 jamAlat bantu 2.5000 set

JUMLAHDIBULATKAN

1 kg - Pembesian ( besi polos )Kawat beton 0.0200 kgBesi beton polos 1.1000 kgPekerja 0.0150 hrTukang besi 0.0050 hrMandor 0.0050 hrAlat bantu 1.0000 set

JUMLAHDIBULATKAN

1 kg - Pembesian ( besi ulir )Kawat beton 0.0200 kgBesi beton pulir 1.1000 kgPekerja 0.0150 hrTukang besi 0.0050 hrMandor 0.0050 hrAlat bantu 1.0000 set

JUMLAHDIBULATKAN

Kayu papan terenteng 2/20-400 cm 0.0240 m3Kayu kaso terentang 5/7-400 cm 0.0280 m3Paku 0.2500 kgPekerja 0.1650 hrTukang kayu 0.3940 hrMandor 0.0270 hrAlat bantu 2.5000 set

JUMLAHDIBULATKAN

Triplex 9 mm 0.3500 lbrKayu kaso terentang 5/7-400 cm 0.0280 m3Paku 0.2500 kgPekerja 0.1650 hrTukang kayu 0.3940 hrMandor 0.0270 hrAlat bantu 2.5000 set

JUMLAHDIBULATKAN

Triplex 9 mm 3.1500 lbrKayu kaso terentang 5/7-400 cm 0.2520 m3Paku 2.2500 kgPekerja 1.4850 hrTukang kayu 3.5440 hrMandor 0.2430 hrAlat bantu 2.5000 set

JUMLAHDIBULATKAN

Triplex 9 mm 2.3500 lbr

1 m2 - Bekisting dengan papan + bongkaran dan penyiraman

1 m2 - Bekisting dengan triplex 9 mm + bongkaran dan penyiraman

1 m3 - Bekisting kolom beton struktur

1 m3 - Bekisting balok beton struktur

Page 18: KAMPUS MEDAN

Kayu kaso terentang 5/7-400 cm 0.1870 m3Paku 1.6680 kgPekerja 1.1010 hrTukang kayu 2.6260 hrMandor 0.1800 hrAlat bantu 2.5000 set

JUMLAHDIBULATKAN

Triplex 9 mm 2.9050 lbrKayu kaso terentang 5/7-400 cm 0.2320 m3Paku 2.0750 kgPekerja 1.3700 hrTukang kayu 3.2685 hrMandor 0.2245 hrAlat bantu 2.5000 set

JUMLAHDIBULATKAN

Kayu kaso terentang 5/7-400 cm 0.0608 m3Paku 0.3000 kgPekerja 0.6000 hrTukang kayu 0.4200 hrMandor 0.0300 hrAlat bantu 2.5000 set

JUMLAHDIBULATKAN

Kayu kaso terentang 5/7-400 cm 0.0851 m3Paku 0.4200 kgPekerja 0.8400 hrTukang kayu 0.5880 hrMandor 0.0420 hrAlat bantu 3.5000 set

JUMLAHDIBULATKAN

Kayu kaso terentang 5/7-400 cm 0.1094 m3Paku 0.5400 kgPekerja 1.0800 hrTukang kayu 0.7560 hrMandor 0.0540 hrAlat bantu 4.5000 set

JUMLAHDIBULATKAN

Kayu kaso terentang 5/7-400 cm 0.1398 m3Paku 0.6900 kgPekerja 1.3800 hrTukang kayu 0.9660 hrMandor 0.0690 hrAlat bantu 5.7500 set

JUMLAHDIBULATKAN

1 m3 - Bekisting lantai beton

1 m2 - Perancah kayu / stoot werk - tinggi s/d 2 m

1 m2 - Perancah kayu / stoot werk - tinggi s/d 3 m

1 m2 - Perancah kayu / stoot werk - tinggi s/d 4 m

1 m2 - Perancah kayu / stoot werk - tinggi s/d 5 m

Page 19: KAMPUS MEDAN

Adukan beton K.175 (konvensional) 1.0000 m3Pembesian besi polos 120.0000 kgBekisting dengan papan 5.0000 m2Alat bantu 4.2000 set

JUMLAHDIBULATKAN

Adukan beton K.175 (konvensional) 1.0000 m3Pembesian besi polos 150.0000 kgBekisting dengan papan 5.0000 m2Alat bantu 4.2000 set

JUMLAHDIBULATKAN

Adukan beton K.225 (konvensional) 1.0000 m3Pembesian besi polos 250.0000 kgBekisting triplex 9 mm 2.6670 m2

JUMLAHDIBULATKAN

Adukan beton K-225 (konvensional) 1.0000 m3Pembesian 170.0000 kgBekisting balok struktur 1.0000 m3

JUMLAHDIBULATKAN

Adukan beton K-225 (ready-mix) 1.0000 m3Pembesian 160.0000 kgBekisting kolom 1.0000 m3

JUMLAHDIBULATKAN

Adukan beton K-225 (ready-mix) 1.0000 m3Pembesian 160.0000 kgPerancah kayu/ stoot werk - tinggi s/d 4m 3.3330 m2Bekisting balok 1.0000 m3

JUMLAHDIBULATKAN

Adukan beton K-225 (ready-mix) 1.0000 m3Pembesian besi polos 170.0000 kgPerancah kayu/ stoot werk - tinggi s/d 4m 2.5000 m2Bekisting balok 1.0000 m3

JUMLAHDIBULATKAN

Adukan beton K-225 (ready-mix) 1.0000 m3Pembesian 160.0000 kgPerancah kayu/ stoot werk - tinggi s/d 4m 2.5000 m2Bekisting balok 1.0000 m3

JUMLAHDIBULATKAN

1 m3 - Balok beton praktis K.175

1 m3 - Kolom beton praktis K.175

1 m3 - Pondasi beton setapak K. 225

1 m3 - Sloof beton 20/35 K-225

1 m3 - Kolom beton 30/30 K. 225

1 m3 - Balok beton 20/30 K. 225

1 m3 - Balok beton 20/35 K. 225

1 m3 - Balok beton 20/40 K. 225

Page 20: KAMPUS MEDAN

Adukan beton K-225 (ready-mix) 1.0000 m3Pembesian 170.0000 kgPerancah kayu/ stoot werk - tinggi s/d 4m 2.2200 m2Bekisting balok 1.0000 m3

JUMLAHDIBULATKAN

Adukan beton K-225 (ready-mix) 1.0000 m3Pembesian 170.0000 kgPerancah kayu/ stoot werk - tinggi s/d 4m 2.0000 m2Bekisting balok 1.0000 m3

JUMLAHDIBULATKAN

Adukan beton K-225 (ready-mix) 1.0000 m3Pembesian 150.0000 kgPerancah kayu/ stoot werk - tinggi s/d 4m 3.3300 m2Bekisting balok 1.0000 m3

JUMLAHDIBULATKAN

Adukan beton K-225 (ready-mix) 1.0000 m3Pembesian 75.0000 kgPerancah kayu/ stoot werk - tinggi s/d 4m 1.0000 m2Bekisting pelat lantai 1.0000 m3

JUMLAHDIBULATKAN

Adukan beton K-225 (ready-mix) 1.0000 m3Pembesian besi polos 110.0000 kgPerancah kayu/ stoot werk - tinggi s/d 4m 6.2475 m2Bekisting pelat lantai 1.0000 m3

JUMLAHDIBULATKAN

1 m3 - Plat listplank beton K. 225Adukan beton K-225 (ready-mix) 1.0000 m3Pembesian besi polos 100.0000 kgPerancah kayu/ stoot werk - tinggi s/d 4m 1.0000 m2Bekisting balok 1.0000 m3

JUMLAHDIBULATKAN

1 m3 - Balok beton 20/45 K. 225

1 m3 - Balok beton 20/50 K. 225

1 m3 - Ring balok beton 25/35 K. 225

1 m3 - Beton plat canopy atas jendela t = 10 cm - K. 225

1 m3 - Plat lantai & tangga beton K. 225

Page 21: KAMPUS MEDAN

RESUME ANALISA TEKNIS

HARGA SATUAN PEKERJAAN PONDASI & BETON

HARGA SAT. JUMLAH

140,800 60,122 140,800 60,122 137,500 151,250 137,500 151,250 814 217,338 814 217,338

#REF! #REF! 33,000 49,500 #REF! #REF! 44,000 66,000 #REF! #REF! 71,500 42,900 #REF! #REF! 60,500 3,630

JUMLAH #REF! 590,740 DIBULATKAN #REF! 590,700

154,000 78,078 154,000 78,078 148,500 106,326 148,500 106,326 37,000 185,000 40,700 203,500

#REF! #REF! 33,000 59,400 #REF! #REF! 44,000 20,900 #REF! #REF! 71,500 20,435 #REF! #REF! 24,432 61,080

JUMLAH #REF! 549,719 DIBULATKAN #REF! 549,700

154,000 78,078 154,000 78,078 148,500 106,326 148,500 106,326 37,000 333,000 40,700 366,300

#REF! #REF! 33,000 59,400 #REF! #REF! 44,000 21,375 #REF! #REF! 71,500 18,647 #REF! #REF! 32,506 81,266

JUMLAH #REF! 731,392 DIBULATKAN #REF! 731,400

154,000 78,078 154,000 78,078 148,500 106,326 148,500 106,326 37,000 407,000 40,700 447,700

#REF! #REF! 33,000 59,400 #REF! #REF! 44,000 11,475 #REF! #REF! 71,500 41,885 #REF! #REF! 37,243 93,108

JUMLAH #REF! 837,972 DIBULATKAN #REF! 838,000

154,000 61,600 154,000 61,600 148,500 109,890 148,500 109,890 37,000 436,600 40,700 480,260

#REF! #REF! 33,000 59,400

Page 22: KAMPUS MEDAN

#REF! #REF! 44,000 11,528 #REF! #REF! 71,500 44,831 #REF! #REF! 38,375 95,939

JUMLAH #REF! 863,447 DIBULATKAN #REF! 863,400

410,000 410,000 410,000 410,000 #REF! #REF! 33,000 18,176 #REF! #REF! 44,000 6,059 #REF! #REF! 71,500 4,919 #REF! #REF! 21,958 54,894

JUMLAH #REF! 494,049 DIBULATKAN #REF! 494,000

462,000 462,000 462,000 462,000 #REF! #REF! 33,000 22,721 #REF! #REF! 44,000 6,059 #REF! #REF! 71,500 4,919

30,000 14,457 30,000 14,457 #REF! #REF! 25,508 63,769

JUMLAH #REF! 573,925 DIBULATKAN #REF! 573,900

467,800 467,800 467,800 467,800 #REF! #REF! 33,000 22,721 #REF! #REF! 44,000 6,059 #REF! #REF! 71,500 4,919

30,000 14,457 30,000 14,457 #REF! #REF! 25,798 64,494

JUMLAH #REF! 580,450 DIBULATKAN #REF! 580,400

485,100 485,100 485,100 485,100 #REF! #REF! 33,000 22,721 #REF! #REF! 44,000 6,059 #REF! #REF! 71,500 4,919

30,000 14,457 30,000 14,457 #REF! #REF! 26,663 66,657

JUMLAH #REF! 599,912 DIBULATKAN #REF! 599,900

490,900 490,900 490,900 490,900 #REF! #REF! 33,000 22,721 #REF! #REF! 44,000 6,059 #REF! #REF! 71,500 4,919

30,000 14,457 30,000 14,457 #REF! #REF! 26,953 67,382

JUMLAH #REF! 606,437 DIBULATKAN #REF! 606,400

542,900 542,900 542,900 542,900 #REF! #REF! 33,000 22,721 #REF! #REF! 44,000 6,059 #REF! #REF! 71,500 4,919

Page 23: KAMPUS MEDAN

30,000 14,457 30,000 14,457 #REF! #REF! 29,553 73,882

JUMLAH #REF! 664,937 DIBULATKAN #REF! 664,900

7,300 146 7,300 146 6,600 7,260 6,600 7,260

#REF! #REF! 33,000 495 #REF! #REF! 55,000 275 #REF! #REF! 71,500 358 #REF! #REF! 427 427

JUMLAH #REF! 8,960 DIBULATKAN #REF! 9,000

7,300 146 7,300 146 7,400 8,140 7,400 8,140

#REF! #REF! 33,000 495 #REF! #REF! 55,000 275 #REF! #REF! 71,500 358 #REF! #REF! 471 471

JUMLAH #REF! 9,884 DIBULATKAN #REF! 9,900

1,705,000 40,920 1,705,000 40,920 1,705,000 47,740 1,705,000 47,740 7,700 1,925 7,700 1,925

#REF! #REF! 33,000 5,445 #REF! #REF! 55,000 21,670 #REF! #REF! 71,500 1,931 #REF! #REF! 5,982 14,954

JUMLAH #REF! 134,584 DIBULATKAN #REF! 134,600

107,800 37,730 107,800 37,730 1,705,000 47,740 1,705,000 47,740 7,700 1,925 7,700 1,925

#REF! #REF! 33,000 5,445 #REF! #REF! 55,000 21,670 #REF! #REF! 71,500 1,931 #REF! #REF! 5,822 14,555

JUMLAH #REF! 130,996 DIBULATKAN #REF! 131,000

107,800 339,570 107,800 339,570 1,705,000 429,660 1,705,000 429,660 7,700 17,325 7,700 17,325

#REF! #REF! 33,000 49,005 #REF! #REF! 55,000 194,920 #REF! #REF! 71,500 17,375 #REF! #REF! 52,393 130,982

JUMLAH #REF! 1,178,836 DIBULATKAN #REF! 1,178,800

107,800 253,330 107,800 253,330

Page 24: KAMPUS MEDAN

1,705,000 318,835 1,705,000 318,835 7,700 12,844 7,700 12,844

#REF! #REF! 33,000 36,333 #REF! #REF! 55,000 144,430 #REF! #REF! 71,500 12,870 #REF! #REF! 116,796 291,991

JUMLAH #REF! 1,070,632 DIBULATKAN #REF! 1,070,600

107,800 313,159 107,800 313,159 1,705,000 395,560 1,705,000 395,560 7,700 15,978 7,700 15,978

#REF! #REF! 33,000 45,210 #REF! #REF! 55,000 179,768 #REF! #REF! 71,500 16,052 #REF! #REF! 48,286 120,716

JUMLAH #REF! 1,086,441 DIBULATKAN #REF! 1,086,400

1,705,000 103,664 1,705,000 103,664 7,700 2,310 7,700 2,310

#REF! #REF! 33,000 19,800 #REF! #REF! 55,000 23,100 #REF! #REF! 71,500 2,145 #REF! #REF! 7,551 18,877

JUMLAH #REF! 169,896 DIBULATKAN #REF! 169,900

1,705,000 145,096 1,705,000 145,096 7,700 3,234 7,700 3,234

#REF! #REF! 33,000 27,720 #REF! #REF! 55,000 32,340 #REF! #REF! 71,500 3,003 #REF! #REF! 10,570 36,994

JUMLAH #REF! 248,386 DIBULATKAN #REF! 248,400

1,705,000 186,527 1,705,000 186,527 7,700 4,158 7,700 4,158

#REF! #REF! 33,000 35,640 #REF! #REF! 55,000 41,580 #REF! #REF! 71,500 3,861 #REF! #REF! 13,588 61,147

JUMLAH #REF! 332,913 DIBULATKAN #REF! 332,900

1,705,000 238,359 1,705,000 238,359 7,700 5,313 7,700 5,313

#REF! #REF! 33,000 45,540 #REF! #REF! 55,000 53,130 #REF! #REF! 71,500 4,934 #REF! #REF! 17,364 99,842

JUMLAH #REF! 447,117 DIBULATKAN #REF! 447,100

Page 25: KAMPUS MEDAN

#REF! #REF! 731,400 731,400 #REF! #REF! 6,600 792,000 #REF! #REF! 134,600 673,000 #REF! #REF! 54,910 230,622

JUMLAH #REF! 2,427,022 DIBULATKAN #REF! 2,427,000

#REF! #REF! 731,400 731,400 #REF! #REF! 6,600 990,000 #REF! #REF! 55,000 275,000 #REF! #REF! 49,910 209,622

JUMLAH #REF! 2,206,022 DIBULATKAN #REF! 2,206,000

462,000 462,000 462,000 462,000 #REF! #REF! 6,600 1,650,000 #REF! #REF! 35,933 95,834

JUMLAH #REF! 2,207,834 DIBULATKAN #REF! 2,207,800

462,000 462,000 462,000 462,000 #REF! #REF! 6,600 1,122,000

141,100 141,100 141,100 141,100 JUMLAH #REF! 1,725,100 DIBULATKAN #REF! 1,725,100

462,000 462,000 462,000 462,000 #REF! #REF! 7,400 1,184,000

141,100 141,100 141,100 141,100 JUMLAH #REF! 1,787,100 DIBULATKAN #REF! 1,787,100

462,000 462,000 462,000 462,000 #REF! #REF! 7,400 1,184,000 #REF! #REF! 8,800 29,330

141,100 141,100 141,100 141,100 JUMLAH #REF! 1,816,430 DIBULATKAN #REF! 1,816,400

462,000 462,000 462,000 462,000 #REF! #REF! 6,600 1,122,000

8,800 22,000 8,800 22,000 141,100 141,100 141,100 141,100

JUMLAH #REF! 1,747,100 DIBULATKAN #REF! 1,747,100

462,000 462,000 462,000 462,000 #REF! #REF! 7,400 1,184,000

8,800 22,000 8,800 22,000 141,100 141,100 141,100 141,100

JUMLAH #REF! 1,809,100 DIBULATKAN #REF! 1,809,100

Page 26: KAMPUS MEDAN

462,000 462,000 462,000 462,000 #REF! #REF! 7,400 1,258,000

8,800 19,536 8,800 19,536 141,100 141,100 141,100 141,100

JUMLAH #REF! 1,880,636 DIBULATKAN #REF! 1,880,600

462,000 462,000 462,000 462,000 #REF! #REF! 7,400 1,258,000

8,800 17,600 8,800 17,600 141,100 141,100 141,100 141,100

JUMLAH #REF! 1,878,700 DIBULATKAN #REF! 1,878,700

462,000 462,000 462,000 462,000 #REF! #REF! 7,400 1,110,000

8,800 29,304 8,800 29,304 141,100 141,100 141,100 141,100

JUMLAH #REF! 1,742,404 DIBULATKAN #REF! 1,742,400

462,000 462,000 462,000 462,000 #REF! #REF! 6,600 495,000

8,800 8,800 8,800 8,800 141,100 141,100 141,100 141,100

JUMLAH #REF! 1,106,900 DIBULATKAN #REF! 1,106,900

462,000 462,000 462,000 462,000 #REF! #REF! 6,600 726,000

8,800 54,978 8,800 54,978 141,100 141,100 141,100 141,100

JUMLAH #REF! 1,384,078 DIBULATKAN #REF! 1,384,100

462,000 462,000 462,000 462,000 #REF! #REF! 6,600 660,000

8,800 8,800 8,800 8,800 141,100 141,100 141,100 141,100

JUMLAH #REF! 1,271,900 DIBULATKAN #REF! 1,271,900

Page 27: KAMPUS MEDAN

RESUME ANALISA TEKNIS

HARGA SATUAN PEKERJAAN ATAP

NO URAIAN KOEF. SAT.

PA : PEKERJAAN ATAP1 kg - Konstruksi baja H - beam / WF ( termasuk plat simpul, las & zinkchromate)

Zinkcromate 0.0400 m2Besi WF ex. DN SII 1.0500 kgPekerja 0.0600 hrTukang besi 0.0045 hrMandor 0.0025 hrErection 1.0000 kg

JUMLAHDIBULATKAN

1 kg - Konstruksi besi siku ( termasuk plat simpul, las & zinkchromate)Zinkcromate 0.0400 m2Besi WF ex. DN SII 1.0500 kgPekerja 0.0600 hrTukang besi 0.0045 hrMandor 0.0025 hrErection 1.0000 kg

JUMLAHDIBULATKAN

1 kg - Konstruksi gording besi ( termasuk plat simpul, las & zinkchromate)Zinkcromate 0.0400 m2Besi WF ex. DN SII 1.0200 kgPekerja 0.0600 hrTukang besi 0.0045 hrMandor 0.0025 hrErection 1.0000 kg

JUMLAHDIBULATKAN

MP deck zinc Allme gelombang t= 0.5 mm 1.0500 lbrPaku Sumbat berikut ring 15 cm 0.0200 kgPekerja 0.1500 hrMandor 0.0060 hrTukang kayu 0.7500 hrKepala tukang 0.0080 hr

JUMLAHDIBULATKAN

1 m¹ - Pekerjaan nok zinc AllumeNok standar 40cm 8, swg 22 1.2000 lbrPaku Sumbat berikut ring 15 cm 0.0200 kgPekerja 0.1500 hrMandor 0.0060 hrTukang kayu 0.7500 hrKepala tukang 0.0080 hr

JUMLAHDIBULATKAN

Alumunium foil 1.0500 m2

1 m2 - Pekerjaan Atap Zinc Allume Gelombang t = 0.55 mm

1 m2 - Allumunium foil/ insulation

Page 28: KAMPUS MEDAN

Pekerja 0.1500 hrTukang kayu 0.0080 hrKepala tukang kayu 0.0050 hrMandor 0.0500 hr

JUMLAHDIBULATKAN

1 m¹ - Talang datar / jurai seng tebal 0.3 mmPapan kayu meranti 2 / 30 0.0096 m3Plat seng lebar 90 cm, tebal 0.3 mm 1.0250 Paku 0.0150 kgPekerja 0.0500 hrTukang kayu 0.1200 hrMandor 0.0120 hr

JUMLAHDIBULATKAN

Page 29: KAMPUS MEDAN

RESUME ANALISA TEKNIS

HARGA SATUAN PEKERJAAN ATAP

HARGA SAT. JUMLAH

2,500 100 7,125 7,481

#REF! #REF!#REF! #REF!#REF! #REF!

1,000 1,000 JUMLAH #REF!DIBULATKAN #REF!

2,500 100 7,125 7,481

#REF! #REF!#REF! #REF!#REF! #REF!

1,000 1,000 JUMLAH #REF!DIBULATKAN #REF!

2,500 100 7,125 7,268

#REF! #REF!#REF! #REF!#REF! #REF!

1,000 1,000 JUMLAH #REF!DIBULATKAN #REF!

42,600 44,730 8,000 160

#REF! #REF!#REF! #REF!#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

29,300 35,160 8,000 160

#REF! #REF!#REF! #REF!#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

5,000 5,250

Page 30: KAMPUS MEDAN

#REF! #REF!#REF! #REF!#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

2,750,000 26,400 44,000 45,100 7,700 116

#REF! #REF!#REF! #REF!#REF! #REF!

JUMLAH #REF!DIBULATKAN #REF!

Page 31: KAMPUS MEDAN

RESUME ANALISA TEKNIS

HARGA SATUAN PEKERJAAN KAYU

NO URAIAN KOEF. SAT.

KY : PEKERJAAN KAYU

kayu balok kamper samarinda 1.1000 m3Paku 3.0000 kgAngkur 10.5600 kgPekerja 7.2000 hrTukang kayu 25.2000 hrMandor 1.5600 hr

JUMLAHDIBULATKAN

kayu balok kamper banjar 1.1000 m3Paku 3.0000 kgAngkur 10.5600 kgPekerja 7.2000 hrTukang kayu 25.2000 hrMandor 1.5600 hr

JUMLAHDIBULATKAN

kayu balok kamper kruing 1.1000 m3Paku 3.0000 kgAngkur 10.5600 kgPekerja 7.2000 hrTukang kayu 25.2000 hrMandor 1.5600 hr

JUMLAHDIBULATKAN

Rangka papan kamper banjar 0.0150 m3Teakwood 4 mm ukuran pintu 0.7200 lbrLem putih 0.0500 kgPaku triplek 0.5000 kgPekerja 0.6600 hrTukang kayu 2.3100 hrMandor 0.1133 hr

JUMLAHDIBULATKAN

Rangka papan kamper banjar 0.0150 m3Teakwood 4 mm ukuran pintu 0.7200 lbrFormika 0.7200 lbrLem putih 0.0500 kgPaku triplek 0.5000 kgPekerja 0.6600 hrTukang kayu 2.3100 hrMandor 0.1133 hr

1 m3 - Kusen kayu kamper samarinda

1 m3 - Kusen kayu kamper banjar

1 m3 - Kusen kayu kamper kruing

1 m2 - Daun pintu double teakwood

1 m2 - Daun pintu double teakwood lapis formika ( untuk KM/WC )

Page 32: KAMPUS MEDAN

JUMLAHDIBULATKAN

Rangka papan kamper banjar 0.0280 m3Lem putih 0.4000 kgPaku 0.6000 kgKaca polos 5 mm 0.9000 m2Pekerja 0.1300 hrTukang kayu 3.5500 hrMandor 0.2250 hr

JUMLAHDIBULATKAN

Rangka papan kamper banjar 0.0280 m3Lem putih 0.4000 kgPaku 0.6000 kgKaca rayben 5 mm 0.9000 m2Pekerja 1.1300 hrTukang kayu 3.5500 hrMandor 0.2250 hr

JUMLAHDIBULATKAN

Rangka papan kamper banjar 0.0280 m3Lem putih 0.4000 kgPaku 0.6000 kgKaca es 5 mm 0.9000 m2Pekerja 1.1300 hrTukang kayu 3.5500 hrMandor 0.2250 hr

JUMLAHDIBULATKAN

Rangka papan kamper samarinda 0.0440 m3Lem putih 0.6000 kgPekerja 2.5000 hrTukang kayu 7.8750 hrMandor 0.5000 hr

JUMLAHDIBULATKAN

Rangka papan kamper banjar 0.0440 m3Lem putih 0.6000 kgPekerja 2.5000 hrTukang kayu 7.8750 hrMandor 0.5000 hr

JUMLAHDIBULATKAN

Rangka papan kamper samarinda 0.0640 m3Lem putih 0.6000 kgPekerja 2.0000 hrTukang kayu 6.3000 hrMandor 0.4000 hr

1 m2 - Daun pintu kaca polos

1 m2 - Daun pintu kaca rayben

1 m2 - Daun pintu kaca es

1 m2 - Daun pintu panel kayu samarinda

1 m2 - Daun pintu panel kayu banjar

1 m2 - Daun pintu / jendela krepyak (jalusi) kamper samarinda

Page 33: KAMPUS MEDAN

JUMLAHDIBULATKAN

Rangka papan kamper banjar 0.0640 m3Lem putih 0.6000 kgPekerja 2.0000 hrTukang kayu 6.3000 hrMandor 0.4000 hr

JUMLAHDIBULATKAN

1 m2 - Daun pintu / jendela krepyak (jalusi) kamper banjar

Page 34: KAMPUS MEDAN

RESUME ANALISA TEKNIS

HARGA SATUAN PEKERJAAN KAYU

HARGA SAT. JUMLAH

4,950,000 5,445,000 4,950,000 5,445,000 7,700 23,100 7,700 23,100 7,500 79,200 7,500 79,200 33,000 237,600 33,000 237,600 55,000 1,386,000 55,000 1,386,000 71,500 111,540 71,500 111,540

JUMLAH 7,282,440 7,282,440 DIBULATKAN 7,282,400 7,282,400

3,850,000 4,235,000 3,850,000 4,235,000 7,700 23,100 7,700 23,100 7,500 79,200 7,500 79,200 33,000 237,600 33,000 237,600 55,000 1,386,000 55,000 1,386,000 71,500 111,540 71,500 111,540

JUMLAH 6,072,440 6,072,440 DIBULATKAN 6,072,400 6,072,400

3,850,000 4,235,000 3,850,000 4,235,000 7,700 23,100 7,700 23,100 7,500 79,200 7,500 79,200 33,000 237,600 33,000 237,600 55,000 1,386,000 55,000 1,386,000 71,500 111,540 71,500 111,540

JUMLAH 6,072,440 6,072,440 DIBULATKAN 6,072,400 6,072,400

4,180,000 62,700 4,180,000 62,700 54,500 39,240 54,500 39,240 22,000 1,100 22,000 1,100 7,700 3,850 7,700 3,850 33,000 21,780 33,000 21,780 55,000 127,050 55,000 127,050 71,500 8,101 71,500 8,101

JUMLAH 263,821 263,821 DIBULATKAN 263,800 263,800

4,180,000 62,700 4,180,000 62,700 54,500 39,240 54,500 39,240 49,500 35,640 49,500 35,640 22,000 1,100 22,000 1,100 7,700 3,850 7,700 3,850 33,000 21,780 33,000 21,780 55,000 127,050 55,000 127,050 71,500 8,101 71,500 8,101

Page 35: KAMPUS MEDAN

JUMLAH 299,461 299,461 DIBULATKAN 299,500 299,500

4,180,000 117,040 4,180,000 117,040 22,000 8,800 22,000 8,800 7,700 4,620 7,700 4,620 93,500 84,150 93,500 84,150 33,000 4,290 33,000 4,290 55,000 195,250 55,000 195,250 71,500 16,088 71,500 16,088

JUMLAH 430,238 430,238 DIBULATKAN 430,200 430,200

4,180,000 117,040 4,180,000 117,040 22,000 8,800 22,000 8,800 7,700 4,620 7,700 4,620 68,800 61,920 68,800 61,920 33,000 37,290 33,000 37,290 55,000 195,250 55,000 195,250 71,500 16,088 71,500 16,088

JUMLAH 441,008 441,008 DIBULATKAN 441,000 441,000

4,180,000 117,040 4,180,000 117,040 22,000 8,800 22,000 8,800 7,700 4,620 7,700 4,620 95,700 86,130 95,700 86,130 33,000 37,290 33,000 37,290 55,000 195,250 55,000 195,250 71,500 16,088 71,500 16,088

JUMLAH 465,218 465,218 DIBULATKAN 465,200 465,200

5,390,000 237,160 5,390,000 237,160 22,000 13,200 22,000 13,200 33,000 82,500 33,000 82,500 55,000 433,125 55,000 433,125 71,500 35,750 71,500 35,750

JUMLAH 801,735 801,735 DIBULATKAN 801,700 801,700

4,180,000 183,920 4,180,000 183,920 22,000 13,200 22,000 13,200 33,000 82,500 33,000 82,500 55,000 433,125 55,000 433,125 71,500 35,750 71,500 35,750

JUMLAH 748,495 748,495 DIBULATKAN 748,500 748,500

5,390,000 344,960 5,390,000 344,960 22,000 13,200 22,000 13,200 33,000 66,000 33,000 66,000 55,000 346,500 55,000 346,500 71,500 28,600 71,500 28,600

Page 36: KAMPUS MEDAN

JUMLAH 799,260 799,260 DIBULATKAN 799,300 799,300

4,180,000 267,520 4,180,000 267,520 22,000 13,200 22,000 13,200 33,000 66,000 33,000 66,000 55,000 346,500 55,000 346,500 71,500 28,600 71,500 28,600

JUMLAH 721,820 721,820 DIBULATKAN 721,800 721,800

Page 37: KAMPUS MEDAN

RESUME ANALISA TEKNIS

HARGA SATUAN PEKERJAAN SANITARI

NO URAIAN KOEF. SAT.

SNT : PEKERJAAN SANITER1 unit - Closet jongkok standar ex. TOTO

Pasir pasang 0.0100 Semen PC 50 kg 6.0000 kgcloset jongkok standar 1.0000 bhPekerja 1.0000 hrTukang batu 1.5000 hrKepala tukang 0.3000 hrMandor 0.1600 hr

JUMLAHDIBULATKAN

1 unit - Closet duduk ex. TOTOCloset duduk standar 1.0000 bhPerlengkapan 6% harga closet 0.0600 -Pekerja 3.3000 hrTukang batu 1.1000 hrKepala tukang 0.0010 hrMandor 0.1600 hr

JUMLAHDIBULATKAN

1 Buah - Shower spray Toto type TB 19 CSNCR ex. TOTOShower spray toto 1.0000 bhPekerja 2.3421 hrMandor 0.2000 hrTukang ledeng 0.8000 hr

JUMLAHDIBULATKAN

1 Unit - Pemasangan Urinoar totoPasir pasang 0.0100 m³Semen PC 50 kg 6.0000 kgUrinoar toto 1.0000 bhPerlengkapan 30% harga urinoar 0.3000 -Pekerja 1.0000 hrTukang batu 1.0000 hrKepala tukang batu 0.1000 hrMandor 0.1000 hr

JUMLAHDIBULATKAN

1 Unit - Bak air fiber glass kap. 200 ltrPasir pasang 0.3500 m³Semen PC 50 kg 0.5000 ZakBak air fiber glass kap. 200 ltr 1.0000 bhPekerja 1.2000 hrTukang batu 1.0000 hrMandor 0.7000 hr

JUMLAHDIBULATKAN

1 unit - Pemasangan Kaca cermin ( t=6 mm )

Page 38: KAMPUS MEDAN

Cermin 6 mm Lengkap 1.0000 bhPekerja 0.9825 hrMandor 0.4142 hr

JUMLAHDIBULATKAN

Page 39: KAMPUS MEDAN

RESUME ANALISA TEKNIS

HARGA SATUAN PEKERJAAN SANITARI

HARGA SAT. JUMLAH

140,800 1,408 140,800 1,408 40,700 244,200 40,700 244,200 1,760,000 1,760,000 1,760,000 1,760,000 33,000 33,000 33,000 33,000 44,000 66,000 44,000 66,000 60,500 18,150 60,500 18,150 71,500 11,440 71,500 11,440

JUMLAH 2,134,198 2,134,198 DIBULATKAN 2,134,200 2,134,200

1,837,000 1,837,000 1,837,000 1,837,000 110,220 6,613 110,220 6,613 33,000 108,900 33,000 108,900 44,000 48,400 44,000 48,400 60,500 61 60,500 61 71,500 11,440 71,500 11,440

JUMLAH 2,012,414 2,012,414 DIBULATKAN 2,012,400 2,012,400

465,000 465,000 465,000 465,000 33,000 77,289 33,000 77,289 71,500 14,300 71,500 14,300 50,000 40,000 50,000 40,000

JUMLAH 596,589 596,589 DIBULATKAN 596,600 596,600

140,800 1,408 140,800 1,408 40,700 244,200 40,700 244,200 1,020,600 1,020,600 1,020,600 1,020,600 306,180 91,854 306,180 91,854 33,000 33,000 33,000 33,000 44,000 44,000 44,000 44,000 60,500 6,050 60,500 6,050 71,500 7,150 71,500 7,150

JUMLAH 1,448,262 1,448,262 DIBULATKAN 1,448,300 1,448,300

140,800 49,280 140,800 49,280 40,700 20,350 40,700 20,350 121,000 121,000 121,000 121,000 33,000 39,600 33,000 39,600 44,000 44,000 44,000 44,000 71,500 50,050 71,500 50,050

JUMLAH 324,280 324,280 DIBULATKAN 324,300 324,300

Page 40: KAMPUS MEDAN

192,500 192,500 192,500 192,500 33,000 32,423 33,000 32,423 71,500 29,615 71,500 29,615

JUMLAH 254,538 254,538 DIBULATKAN 254,500 254,500

Page 41: KAMPUS MEDAN

RESUME ANALISA TEKNIS

HARGA SATUAN PEKERJAAN LAIN-LAIN

NO URAIAN KOEF. SAT.

PL : PEKERJAAN LAIN-LAIN1 m' - Saluran buis beton 1/2 dia. 30 cm

Buis beton dia 30 1.0500 m'Pasir urug 0.4200 m³Pasir Pasang 0.0250 m³Semen PC 50 kg 0.0270 zakPekerja 0.0750 hrTukang batu 0.0500 hrMandor 0.0188 hr

JUMLAHDIBULATKAN

1 m2 - Paving block t = 6 cmPaving block t = 6 cm K. 250 1.0250 Pasir pasang 0.0250 m³Pekerja 0.1500 hrTukang batu 0.0500 hrMandor 0.0030 hr

JUMLAHDIBULATKAN

1 m2 - Paving block t = 8 cmPaving block t = 8 cm K.250 1.0250 Pasir pasang 0.0250 m³Pekerja 0.1500 hrTukang batu 0.0500 hrMandor 0.0030 hr

JUMLAHDIBULATKAN

1 m' - Kanstin abu-abu 10.20.40 - K. 175Kanstin abu-abu 10.20.40 - K. 175 1.0000 Adukan 0.0100 m³Pekerja 0.0500 hrTukang batu 0.0175 hrMandor 0.0087 hr

JUMLAHDIBULATKAN

1 m2 - Partisi double gypsum 9 mm + rangka kayu meranti + list kayu papan diprofil + finish catKayu Meranti 0.0200 m³Gypsum 9 mm 0.7656 lbrPaku 0.3500 kgList papan diprofil 1.6 x 9 cm ( atas partisi 3 muka bwh 2 muka ) 3.5714 Cat dinding partisi (cat tembok) 2.0000 Cat kayu 0.3571 Pekerja 0.2200 hrTukang kayu 0.3500 hrmandor 0.0460 hrAlat bantu 1.0000 set

JUMLAHDIBULATKAN

m¹m²m²

Page 42: KAMPUS MEDAN

1 m' - Kanstin abu-abu 10.20.40 - K. 300Kanstin abu-abu 10.20.40 - K. 300 1.0000 Adukan 0.0100 m³Pekerja 0.0500 hrTukang batu 0.0175 hrMandor 0.0087 hr

JUMLAHDIBULATKAN

Page 43: KAMPUS MEDAN

RESUME ANALISA TEKNIS

HARGA SATUAN PEKERJAAN LAIN-LAIN

HARGA SAT. JUMLAH

93,500 98,175 93,500 98,175 104,500 43,890 104,500 43,890 140,800 3,520 140,800 3,520 40,700 1,099 40,700 1,099 33,000 2,475 33,000 2,475 44,000 2,200 44,000 2,200 71,500 1,344 71,500 1,344

JUMLAH 152,703 152,703 DIBULATKAN 152,700 152,700

40,700 41,718 40,700 41,718 140,800 3,520 140,800 3,520 33,000 4,950 33,000 4,950 44,000 2,200 44,000 2,200 71,500 215 71,500 215

JUMLAH 52,602 52,602 DIBULATKAN 52,600 52,600

46,800 47,970 46,800 47,970 140,800 3,520 140,800 3,520 33,000 4,950 33,000 4,950 44,000 2,200 44,000 2,200 71,500 215 71,500 215

JUMLAH 58,854 58,855 DIBULATKAN 58,900 58,900

12,100 12,100 12,100 12,100 430,000 4,300 430,000 4,300 33,000 1,650 33,000 1,650 44,000 770 44,000 770 71,500 622 71,500 622

JUMLAH 19,442 19,442 DIBULATKAN 19,400 19,400

1 m2 - Partisi double gypsum 9 mm + rangka kayu meranti + list kayu papan diprofil + finish cat 1,915,700 38,314 1,915,700 38,314 49,600 37,974 49,600 37,974 49,500 17,325 49,500 17,325 95,000 339,283 95,000 339,283 41,800 83,600 41,800 83,600 42,900 15,320 42,900 15,320 33,000 7,260 33,000 7,260 55,000 19,250 55,000 19,250 71,500 3,289 71,500 3,289 84,242 84,242 84,242 84,242

JUMLAH 645,857 645,857 DIBULATKAN 645,900 645,900

Page 44: KAMPUS MEDAN

9,900 9,900 9,900 9,900 430,000 4,300 430,000 4,300 33,000 1,650 33,000 1,650 44,000 770 44,000 770 71,500 1,251 71,500 1,251

JUMLAH 17,871 17,871 DIBULATKAN 17,900 17,900

Page 45: KAMPUS MEDAN

RESUME ANALISA TEKNIS

HARGA SATUAN PEKERJAAN M & E

NO URAIAN KOEF. SAT.

IL : PEK. INSTALASI PENERANGAN dan STOP KONTAK1 Ttk - Instalasi Penerangan & Stop Kontak

Fiting keramik 125 watt 0.0274 bhNYM 3 x 2.5 mm2 10.0000 Klem 1.0000 bhSaklar 0.0041 bhPipa Conduit PVC klas D 5.0000 Pekerja 0.3714 hrTukang listrik 0.1065 hrPembantu instalator 0.2306 hr

JUMLAHDIBULATKAN

1Bh - Lampu TL 2 x 36 watt (TKO)Rumah lampu + lampu TL 2 x 36 watt ( grill ) 1.0000 bhPekerja 0.3123 hrTukang listrik 0.1045 hrPembantu instalatir 0.2326 hr

JUMLAHDIBULATKAN

1Bh - Lampu Baret 40 wattLampu baret 40 watt 1.0000 bhPekerja 0.1045 hrTukang listrik 0.1050 hrPembantu instalatir 0.2274 hr

JUMLAHDIBULATKAN

1Bh - Lampu Down Light isi PL 2 x 9 wattLampu down light isi PL 2 x 9 watt 1.0000 bhPekerja 0.1045 hrTukang listrik 0.1050 hrPembantu instalatir 0.2321 hr

JUMLAHDIBULATKAN

1Bh - Lampu PL 2 x 9 wattlampu PL 2 x 9 watt 1.0000 bhPekerja 0.1045 hrTukang listrik 0.1050 hrPembantu instalatir 0.2321 hr

JUMLAHDIBULATKAN

1Bh - Stop kontak 3 (phase)Stop kontak 25A, 3 phase Brocco 1.0000 bhPekerja 0.1052 hrTukang listrik 0.1055 hrPembantu instalatir 0.2336 hr

JUMLAHDIBULATKAN

1Bh - Saklar hotel Brocco

Page 46: KAMPUS MEDAN

Saklar hotel 1.0000 bhPekerja 0.1052 hrTukang listrik 0.1055 hrPembantu instalatir 0.2336 hr

JUMLAHDIBULATKAN

1Bh - Saklar tunggal BroccoSaklar tunggal 1.0000 bhPekerja 0.1052 hrTukang listrik 0.1055 hrPembantu instalatir 0.2336 hr

JUMLAHDIBULATKAN

1Bh - Saklar double BroccoSaklar double 1.0000 bhPekerja 0.1052 hrTukang listrik 0.1055 hrPembantu instalatir 0.2336 hr

JUMLAHDIBULATKAN

1 unit - Pasang Box Panel pembagiPHB induk uk. 80 x 60 x 40 1.0000 bhNFB 100 A 1.0000 bhKabel scunt (sepatu kabel) Cu 25, 35 mm 4.0000 bhKabel scunt (sepatu kabel) Cu 50 mm 8.0000 bhMCB 32 A 1.0000 bhNH Fuse 50 A 6.0000 bbHolder fuse 6.0000 bhFiting keramik 250 watt 1.0000 bhSaklar 1.0000 bhKabel 10 m 4.0000 m¹Lampu indikator 1.0000 setPlat tembaga 0.5 m 1.0000 setPas. Ground 1.0000 bhPekerja 0.5000 hrMandor 0.0500 hrInstalatur/ Tukang listrik 0.5000 hr

JUMLAHDIBULATKAN

IA PEK. INSTALSI AIR BERSIH & PEMBUANGAN1 M' - Instalasi Pipa PVC type AW dia. 1/2 "

Pipa PVC 1.2000 m¹Perlengkapan 35 % harga pipa 0.3500 -Pekerja 0.0360 hrmandor 0.0018 hrTukang pasang pipa 0.0600 hrKepala tukang pipa 0.0060 hr

JUMLAHDIBULATKAN

1 M' - Instalasi Pipa PVC type AW dia. 3/4 "Pipa PVC 1.2000 m¹Perlengkapan 35 % harga pipa 0.3500 -Pekerja 0.0360 hrmandor 0.0018 hr

Page 47: KAMPUS MEDAN

Tukang pasang pipa 0.0600 hrKepala tukang pipa 0.0060 hr

JUMLAHDIBULATKAN

1 M' - Instalasi Pipa PVC type AW dia. 1 "Pipa PVC 1.2000 m¹Perlengkapan 35 % harga pipa 0.3500 -Pekerja 0.0360 hrmandor 0.0018 hrTukang pasang pipa 0.0600 hrKepala tukang pipa 0.0060 hr

JUMLAHDIBULATKAN

1 M' - Instalasi Pipa PVC type AW dia. 1 1/2 "Pipa PVC 1.2000 m¹Perlengkapan 35 % harga pipa 0.3500 -Pekerja 0.0360 hrmandor 0.0018 hrTukang pasang pipa 0.0600 hrKepala tukang pipa 0.0060 hr

JUMLAHDIBULATKAN

1 M' - Instalasi Pipa PVC type AW dia. 2 "Pipa PVC 1.2000 m¹Perlengkapan 35 % harga pipa 0.3500 -Pekerja 0.0540 hrmandor 0.0027 hrTukang pasang pipa 0.0900 hrKepala tukang pipa 0.0090 hr

JUMLAHDIBULATKAN

1 M' - Instalasi Pipa PVC type AW dia. 2 1/2 "Pipa PVC 1.2000 m¹Perlengkapan 35 % harga pipa 0.3500 -Pekerja 0.0540 hrmandor 0.0027 hrTukang pasang pipa 0.0900 hrKepala tukang pipa 0.0090 hr

JUMLAHDIBULATKAN

1 M' - Instalasi Pipa PVC type AW dia. 3 "Pipa PVC 1.2000 m¹Perlengkapan 35 % harga pipa 0.3500 -Pekerja 0.0810 hrmandor 0.0041 hrTukang pasang pipa 0.1350 hrKepala tukang pipa 0.0135 hr

JUMLAHDIBULATKAN

1 M' - Instalasi Pipa PVC type AW dia. 4 "Pipa PVC 1.2000 m¹Perlengkapan 35 % harga pipa 0.3500 -Pekerja 0.0810 hrmandor 0.0041 hr

Page 48: KAMPUS MEDAN

Tukang pasang pipa 0.1350 hrKepala tukang pipa 0.0135 hr

JUMLAHDIBULATKAN

1 M' - Instalasi Pipa PVC type AW dia. 6 "Pipa PVC 1.2000 m¹Perlengkapan 35 % harga pipa 0.3500 -Pekerja 0.0810 hrmandor 0.0041 hrTukang pasang pipa 0.1350 hrKepala tukang pipa 0.0135 hr

JUMLAHDIBULATKAN

Page 49: KAMPUS MEDAN

RESUME ANALISA TEKNIS

HARGA SATUAN PEKERJAAN M & E

HARGA SAT. JUMLAH

2,200 60 2,200 60 7,100 71,000 7,100 71,000 500 500 500 500 14,500 59 14,500 59 2,000 10,000 2,000 10,000 33,000 12,256 33,000 12,256 55,000 5,858 55,000 5,858 33,000 7,610 33,000 7,610

JUMLAH 107,343 107,343 DIBULATKAN 107,300 107,300

273,400 273,400 273,400 273,400 33,000 10,306 33,000 10,306 55,000 5,748 55,000 5,748 33,000 7,676 33,000 7,676

JUMLAH 297,129 297,129 DIBULATKAN 297,100 297,100

353,040 353,040 353,040 353,040 33,000 3,449 33,000 3,449 55,000 5,775 55,000 5,775 33,000 7,504 33,000 7,504

JUMLAH 369,768 369,768 DIBULATKAN 369,800 369,800

70,720 70,720 70,720 70,720 33,000 3,449 33,000 3,449 55,000 5,775 55,000 5,775 33,000 7,659 33,000 7,659

JUMLAH 87,603 87,603 DIBULATKAN 87,600 87,600

49,504 49,504 49,504 49,504 33,000 3,449 33,000 3,449 55,000 5,775 55,000 5,775 33,000 7,659 33,000 7,659

JUMLAH 66,387 66,387 DIBULATKAN 66,400 66,400

125,000 125,000 125,000 125,000 33,000 3,472 33,000 3,472 55,000 5,803 55,000 5,803 33,000 7,709 33,000 7,709

JUMLAH 141,983 141,983 DIBULATKAN 142,000 142,000

Page 50: KAMPUS MEDAN

22,300 22,300 22,300 22,300 33,000 3,472 33,000 3,472 55,000 5,803 55,000 5,803 33,000 7,709 33,000 7,709

JUMLAH 39,283 39,283 DIBULATKAN 39,300 39,300

10,500 10,500 10,500 10,500 33,000 3,472 33,000 3,472 55,000 5,803 55,000 5,803 33,000 7,709 33,000 7,709

JUMLAH 27,483 27,483 DIBULATKAN 27,500 27,500

14,500 14,500 14,500 14,500 33,000 3,472 33,000 3,472 55,000 5,803 55,000 5,803 33,000 7,709 33,000 7,709

JUMLAH 31,483 31,483 DIBULATKAN 31,500 31,500

1,375,000 1,375,000 1,375,000 1,375,000 2,090,000 2,090,000 2,090,000 2,090,000 1,700 6,800 1,700 6,800 2,800 22,400 2,800 22,400 29,000 29,000 29,000 29,000 25,000 150,000 25,000 150,000 16,500 99,000 16,500 99,000 2,200 2,200 2,200 2,200 21,500 21,500 21,500 21,500 109,900 439,600 109,900 439,600 232,050 232,050 232,050 232,050 93,500 93,500 93,500 93,500 203,500 203,500 203,500 203,500 33,000 16,500 33,000 16,500 71,500 3,575 71,500 3,575 55,000 27,500 55,000 27,500

JUMLAH 4,812,125 4,812,125 DIBULATKAN 4,812,100 4,812,100

3,400 4,080 3,400 4,080 1,190 417 1,190 417 33,000 1,188 33,000 1,188 71,500 129 71,500 129 49,500 2,970 49,500 2,970 60,500 363 60,500 363

JUMLAH 9,146 9,146 DIBULATKAN 9,100 9,100

5,100 6,120 5,100 6,120 1,785 625 1,785 625 33,000 1,188 33,000 1,188 71,500 129 71,500 129

Page 51: KAMPUS MEDAN

49,500 2,970 49,500 2,970 60,500 363 60,500 363

JUMLAH 11,394 11,394 DIBULATKAN 11,400 11,400

7,200 8,640 7,200 8,640 2,520 882 2,520 882 33,000 1,188 33,000 1,188 71,500 129 71,500 129 49,500 2,970 49,500 2,970 60,500 363 60,500 363

JUMLAH 14,172 14,172 DIBULATKAN 14,200 14,200

11,000 13,200 11,000 13,200 3,850 1,347 3,850 1,348 33,000 1,188 33,000 1,188 71,500 129 71,500 129 49,500 2,970 49,500 2,970 60,500 363 60,500 363

JUMLAH 19,197 19,197 DIBULATKAN 19,200 19,200

14,200 17,040 14,200 17,040 4,970 1,740 4,970 1,740 33,000 1,782 33,000 1,782 71,500 193 71,500 193 49,500 4,455 49,500 4,455 60,500 545 60,500 545

JUMLAH 25,754 25,754 DIBULATKAN 25,800 25,800

21,000 25,200 21,000 25,200 7,350 2,572 7,350 2,573 33,000 1,782 33,000 1,782 71,500 193 71,500 193 49,500 4,455 49,500 4,455 60,500 545 60,500 545

JUMLAH 34,747 34,747 DIBULATKAN 34,700 34,700

28,000 33,600 28,000 33,600 9,800 3,430 9,800 3,430 33,000 2,673 33,000 2,673 71,500 293 71,500 293 49,500 6,683 49,500 6,683 60,500 817 60,500 817

JUMLAH 47,495 47,495 DIBULATKAN 47,500 47,500

46,425 55,710 46,425 55,710 16,249 5,687 16,249 5,687 33,000 2,673 33,000 2,673 71,500 293 71,500 293

Page 52: KAMPUS MEDAN

49,500 6,683 49,500 6,683 60,500 817 60,500 817

JUMLAH 71,862 71,862 DIBULATKAN 71,900 71,900

105,950 127,140 105,950 127,140 37,083 12,979 37,083 12,979 33,000 2,673 33,000 2,673 71,500 293 71,500 293 49,500 6,683 49,500 6,683 60,500 817 60,500 817

JUMLAH 150,584 150,584 DIBULATKAN 150,600 150,600

Page 53: KAMPUS MEDAN

ANALISA HARGA SATUAN (SNI)

NO URAIAN PEKERJAAN

HARGAKOEFISIEN SATUAN

(Rp.)

1 2 3 4I PEKERJAAN PERSIAPAN

1M2 PEMBESIHAN LOKASI 0.1 Rp 70,587.00 _ pekerja 0.005 Rp 95,296.00 _ mandor

JUMLAH

DIBULATKAN

1 1 M' PENGUKURAN DAN PEMASANGAN BOWPLANKSNI 03-2835-2002(6.4)BAHAN :

- Kayu Papan meranti Kls III 0.0120 3,800,000

- Paku Biasa 2"-5" 0.0200 kg Rp 12,840.00 - Kayu Kaso Kls III 0.0070 3,800,000

UPAH :

- Pekerja 0.0100 org/hr Rp 70,587.00 - Tukang Kayu 0.0100 org/hr Rp 83,145.00 - Kepala Tukang 0.0010 org/hr Rp 95,726.00 - Mandor 0.0050 org/hr Rp 95,296.00

JUMLAH

DIBULATKAN2 1 M2 MEMBERSIHKAN LAPANGAN DAN PERALATAN

SNI 03-2835-2002(6.8)UPAH :

- Pekerja 0.0750 org/hr Rp 70,587.00 - Mandor 0.0025 org/hr Rp 95,296.00

JUMLAH

DIBULATKANII PEKERJAAN TANAH1 1 M3 GALIAN TANAH (TANAH BIASA) SEDALAM 1 M

SNI 03-2835-2002(6.1)UPAH :

- Pekerja 0.4000 org/hr 70,587- Mandor 0.0400 org/hr 95,296

JUMLAH

DIBULATKAN2 1 M3 URUGAN TANAH KEMBALI

SNI 03-2835-2002(6.9)UPAH :

- Pekerja 0.1920 org/hr 70,587- Mandor 0.0190 org/hr 95,296

JUMLAH

DIBULATKAN3 1 M3 URUGAN TANAH

SNI 03-2835-2002(6.9a)BAHAN :

m3

m3

Page 54: KAMPUS MEDAN

- Tanah Urug 1.2000 135,000UPAH :

- Pekerja 0.1920 org/hr 70,587- Mandor 0.0192 org/hr 95,296

JUMLAH

DIBULATKAN4 1 M3 URUGAN PASIR

SNI 03-2835-2002(6.11)BAHAN :

- Pasir Urug 1.2000 135,000UPAH :

- Pekerja 0.3000 org/hr 70,587- Mandor 0.0100 org/hr 95,296

JUMLAH

DIBULATKAN5 1 BTG PAS. CERUCUK KAYU DIA. 10-15 CM

SNI 03-2837-2002BAHAN :

- Kayu Perancah/Kayu Cerucuk 1.0000 btg 267,750UPAH :

- Pekerja 0.2300 org/hr 70,587- Tukang Batu 0.1540 org/hr 83,145- Kepala Tukang 0.0030 org/hr 95,726- Mandor 0.0030 org/hr 95,296

JUMLAH

DIBULATKAN

6 1 M3 PASANGAN BATU MANGGA

SNI 03-2837-2002BAHAN :

- Batu Mangga/Kali 0.6600 131,250

- Pasir pasang 0.3300 185,000- Semen PC ( 50 kg ) 139.0000 kg 61,793

UPAH :- Pekerja 0.8000 org/hr 70,587- Tukang Batu 0.6000 org/hr 83,145- Kepala Tukang 0.0600 org/hr 95,726- Mandor 0.0750 org/hr 95,296

JUMLAH

DIBULATKANIII PEKERJAAN DINDING1 1 M2 PAS. BATA TEBAL 1 BATA 1 PC : 2 PS

SNI 03-2837-2002(6.2)BAHAN :

- Batu Bata 160.0000 bh 500- Semen Type I 43.5000 kg 61,793

- Pasir Pasang 0.0800 185,000UPAH :

- Pekerja 0.6500 org/hr 70,587- Tukang Batu 0.2000 org/hr 83,145- Kepala Tukang 0.0200 org/hr 95,726- Mandor 0.0300 org/hr 95,296

JUMLAH

m3

m3

m3

m3

m3

Page 55: KAMPUS MEDAN

DIBULATKAN2 1 M2 PAS. BATA TEBAL 1/2 BATA 1 PC : 2 PS

SNI 03-2837-2002(6.9)BAHAN :

- Batu Bata 80.0000 500- Semen Type I 18.9500 kg 61,793

- Pasir Pasang 0.0380 185,000UPAH :

- Pekerja 0.3200 org/hr 70,587- Tukang Batu 0.1000 org/hr 83,145- Kepala Tukang 0.0100 org/hr 95,726- Mandor 0.0150 org/hr 95,296

JUMLAH

DIBULATKAN3 1 M2 PAS. BATA TEBAL 1/2 BATA 1 PC : 4 PS

SNI 03-2837-2002(6.11)BAHAN :

- Batu Bata 80.0000 500- Semen Type I 11.5000 kg 61,793

- Pasir Pasang 0.0430 185,000UPAH :

- Pekerja 0.3200 org/hr 70,587- Tukang Batu 0.1000 org/hr 83,145- Kepala Tukang 0.0100 org/hr 95,726- Mandor 0.0150 org/hr 95,296

JUMLAH

DIBULATKANIV PEKERJAAN PLESTERAN1 1 M2 PLESTERAN 1 PC : 2 PS (TEBAL 20 MM)

SNI 03-2837-2002(6.13)BAHAN :

- Semen Type I 14.2800 kg 61,793

- Pasir Pasang 0.0230 185,000UPAH :

- Pekerja 0.2500 org/hr 70,587- Tukang Batu 0.2000 org/hr 83,145- Kepala Tukang 0.0200 org/hr 95,726- Mandor 0.1250 org/hr 95,296

JUMLAH

DIBULATKAN2 1 M2 PLESTERAN 1 PC : 3 PS (TEBAL 20 MM)

SNI 03-2837-2002(6.14)BAHAN :

- Semen Type I 10.8000 kg 61,793

- Pasir Pasang 0.0260 185,000UPAH :

- Pekerja 0.2500 org/hr 70,587- Tukang Batu 0.2000 org/hr 83,145- Kepala Tukang 0.0200 org/hr 95,726- Mandor 0.1250 org/hr 95,296

JUMLAH

DIBULATKAN

m3

m3

m3

m3

m3

m3

Page 56: KAMPUS MEDAN

3 1 M2 PLESTERAN 1 PC : 4 PS (TEBAL 20 MM)SNI 03-2837-2002(6.15)BAHAN :

- Semen Type I 8.6800 kg 61,793

- Pasir Pasang 0.0280 185,000UPAH :

- Pekerja 0.2500 org/hr 70,587- Tukang Batu 0.2000 org/hr 83,145- Kepala Tukang 0.0200 org/hr 95,726- Mandor 0.1250 org/hr 95,296

JUMLAH

DIBULATKAN4 1 M2 PLESTER BETON 1 PC : 3 PS (TEBAL 15 MM)

SNI 03-2837-2002(6.30)BAHAN :

- Semen Type I 6.4800 kg 61,793

- Pasir Pasang 0.0190 185,000UPAH :

- Pekerja 0.2000 org/hr 70,587- Tukang Batu 0.1500 org/hr 83,145- Kepala Tukang 0.0150 org/hr 95,726- Mandor 0.0100 org/hr 95,296

JUMLAH

DIBULATKANV PEKERJAAN KAYU1 1 M3 PASANG KUSEN PINTU DAN JENDELA

SNI 03-3434-2002(6.1)BAHAN :

- Broti/ papan kayu keras/kamper 1.1000 Rp 6,120,989.00 - Paku Biasa 2"-5" 0.0230 kg 12,840

UPAH :- Pekerja 6.0000 org/hr 70,587

- Tukang Batu 20.0000 org/hr 83,145- Kepala Tukang 2.0000 org/hr 95,726- Mandor 0.3000 org/hr 95,296

JUMLAH

DIBULATKAN

2 1 M3 PASANG KONSTRUKSI KUDA-KUDA KAYUSNI 03-3434-2002(6.29)BAHAN :

- Broti/ papan kayu keras/kamper 1.1000 Rp 6,120,989.00 - Besi Strip 15.0000 kg 9,000- Paku Biasa 2"-5" 0.8000 kg 12,840

UPAH :- Pekerja 4.0000 org/hr 70,587- Tukang Kayu 12.0000 org/hr 83,145- Kepala Tukang 1.2000 org/hr 95,726- Mandor 0.2000 org/hr 95,296

JUMLAHDIBULATKAN

3 1 M3 PASANG RANGKA ATAP (GORDING)

m3

m3

m3

m3

Page 57: KAMPUS MEDAN

SNI 03-3434-2002BAHAN :

- Broti/ papan kayu keras/kamper 1.1000 6,120,989- Paku Biasa 2"-5" 0.5000 kg 12,840

UPAH :- Pekerja 2.0000 org/hr 70,587- Tukang Kayu 6.0000 org/hr 83,145- Kepala Tukang 1.2000 org/hr 95,726- Mandor 0.2000 org/hr 95,296

JUMLAHDIBULATKAN

4 1 M2 PASANG RANGKA ATAP (KASO + RENG KAYU)SNI 03-3434-2002(6.31)BAHAN :

- Broti/ papan kayu keras/kamper 0.0120 6,120,989- Paku Biasa 2"-5" 0.1500 kg 12,840

UPAH : Broti/ papan kayu keras/kamper- Pekerja 0.1000 org/hr 70,587- Tukang Kayu 0.1000 org/hr 83,145- Kepala Tukang 0.0100 org/hr 95,726- Mandor 0.0050 org/hr 95,296

JUMLAH

DIBULATKAN5 1 M2 PASANG RANGKA LANGIT-LANGIT

SNI 03-3434-2002(6.38)BAHAN :

- Broti/ papan/balok kayu keras/kamper 0.0120 6,120,989- Paku Biasa 2"-5" 0.1000 kg 12,840

UPAH :- Pekerja 0.1500 org/hr 70,587- Tukang Kayu 0.2500 org/hr 83,145- Kepala Tukang 0.0250 org/hr 95,726- Mandor 0.0750 org/hr 95,296

JUMLAH

DIBULATKAN6 1 M' PASANG LISPLANK KAYU UK. 2 (3X20) CM

SNI 03-3434-2002(6.51)BAHAN :

- Broti/ papan kayu keras/kamper 0.0145 6,120,989- Paku Biasa 2"-5" 0.0600 kg 12,840

UPAH :- Pekerja 0.1500 org/hr 70,587- Tukang Kayu 0.2500 org/hr 83,145- Kepala Tukang 0.0250 org/hr 95,726- Mandor 0.0750 org/hr 95,296

JUMLAH

DIBULATKAN7 1 UNIT PEMASANGAN PINTU PANIL

BAHAN :

- Broti/ papan kayu keras/kamper 0.0000 6,120,989- Paku Biasa 2"-5" 0.0000 kg 12,840- Lem Kayu 0.0000 kg 20,000

m3

m3

m3

m3

m3

Page 58: KAMPUS MEDAN

UPAH :- Pekerja 2.0000 org/hr 70,587- Tukang Kayu 4.0000 org/hr 83,145- Kepala Tukang 0.4000 org/hr 95,726- Mandor 0.2000 org/hr 95,296

JUMLAH

DIBULATKAN8 1 UNIT PEMASANGAN PINTU PANIL 2 DAUN

BAHAN :

- Broti/ papan kayu keras/kamper 0.0000 6,120,989- Paku Biasa 2"-5" 0.0000 kg 12,840- Lem Kayu 0.0000 kg 20,000

UPAH :- Pekerja 2.0000 org/hr 70,587- Tukang Kayu 6.0000 org/hr 83,145- Kepala Tukang 0.6000 org/hr 95,726- Mandor 0.3000 org/hr 95,296

JUMLAH

DIBULATKANVI PEKERJAAN BETON1 1 M3 BETON TUMBUK 1 PC : 3 PS : 5 KR

SNI 03-2495-1991(6.1)BAHAN :

- Semen Type I 218.0000 kg Rp 69,550.00 - Pasir Cor 0.5200 kg 189,390

- kerikil 0.8700 162,000UPAH :

- Pekerja 1.6500 org/hr 70,587- Tukang Batu 0.2500 org/hr 83,145- Kepala Tukang 0.0250 org/hr 95,726- Mandor 0.0800 org/hr 95,296

JUMLAH

DIBULATKAN2 1 M2 LANTAI KERJA 1 PC : 3 PS : 5 KR TEBAL 5 CM + PLASTER

Beton Tumbuk 1 PC : 3 PS : 5 KR 0.0500 15548594.43

Plaster 1 PC : 4 PS 1.0000 589600

JUMLAH

DIBULATKAN3 1 M3 BETON BERTULANG

A. 1 M3 STAMP BETON 1 PC : 2 PS : 3 KRSNI 03-2495-1991(6.13)BAHAN :

- Semen Type I 388.0000 kg 69550- Pasir Cor 0.6500 kg 189390

- kerikil 0.6500 162000UPAH :

- Pekerja 6.0000 org/hr 70,587- Tukang Batu 1.0000 org/hr 83,145- Kepala Tukang 0.1000 org/hr 95,726- Mandor 0.3000 org/hr 95,296

JUMLAH

DIBULATKAN

m3

m3

m3

m2

m3

Page 59: KAMPUS MEDAN

B. 1 KG PEMBESIANSK SNI 04-1989-F(6.25)BAHAN :

- Besi Beton 1.0500 kg 9,363- Kawat ikat beton 0.0150 kg 12,840

UPAH :- Pekerja 0.0070 org/hr 70,587- Tukang Besi 0.0070 org/hr 83,145- Kepala Tukang 0.0007 org/hr 95,726- Mandor 0.0003 org/hr 95,296

JUMLAH

DIBULATKANC1. 1 M2 PASANG BEKISTING UNTUK PONDASISNI 03-2445-1991(6.28)BAHAN :

- Kayu Papan/kaso meranti Kls III 0.0400 3,800,000- Paku Biasa 2"-5" 0.3000 kg 12,840- Minyak Bekisting 0.1000 liter 11,000

UPAH :- Pekerja 0.3000 org/hr 70,587- Tukang Kayu 0.2600 org/hr 83,145- Kepala Tukang 0.0260 org/hr 95,726- Mandor 0.0050 org/hr 95,296

JUMLAH

DIBULATKANC2. 1 M2 PASANG BEKISTING UNTUK SLOOFSNI 03-2445-1991(6.29)BAHAN :

- Kayu Papan meranti Kls III 0.0450 3,800,000- Paku Biasa 2"-5" 0.3000 kg 12,840- Minyak Bekisting 0.1000 liter 11,000

UPAH :- Pekerja 0.3000 org/hr 70,587- Tukang Kayu 0.2600 org/hr 83,145- Kepala Tukang 0.0260 org/hr 95,726- Mandor 0.0050 org/hr 95,296

JUMLAH

DIBULATKANC3. 1 M2 PASANG BEKISTING UNTUK KOLOMSNI 03-2445-1991(6.29)BAHAN :

- Kayu Papan meranti Kls III 0.0450 3,800,000- Paku Biasa 2"-5" 0.3000 kg 12,840- Minyak Bekisting 0.1000 liter 11,000

- Kayu Kaso Kls III 0.0150 950,000- Kayu Perancah/Kayu Cerucuk 2.0000 btg 8,500

UPAH :- Pekerja 0.3000 org/hr 70,587- Tukang Kayu 0.3300 org/hr 83,145- Kepala Tukang 0.0330 org/hr 95,726- Mandor 0.0060 org/hr 95,296

JUMLAH

DIBULATKAN

m3

m3

m3

m3

A312
F.X. Agus Priyo A.S.,ST:
Page 60: KAMPUS MEDAN

C4. 1 M2 PASANG BEKISTING UNTUK BALOKSNI 03-2445-1991(6.31)BAHAN :

- Kayu Papan meranti Kls III 0.0400 3,800,000- Paku Biasa 2"-5" 0.4000 kg 12,840- Minyak Bekisting 0.2000 liter 11,000

- Kayu Kaso meranti Kls III 0.0180 950,000- Triplek 6 mm 0.3500 lbr 52,855- Kayu Perancah/Kayu Cerucuk 2.0000 btg 8,500

UPAH :- Pekerja 0.3200 org/hr 70,587- Tukang Kayu 0.3300 org/hr 83,145- Kepala Tukang 0.0330 org/hr 95,726- Mandor 0.0060 org/hr 95,296

JUMLAH

DIBULATKANC5. 1 M2 PASANG BEKISTING UNTUK LANTAISNI 03-2445-1991(6.31)BAHAN :

- Kayu Papan meranti Kls III 0.0400 3,800,000- Paku Biasa 2"-5" 0.4000 kg 12,840- Minyak Bekisting 0.2000 liter 11,000

- Kayu Kaso meranti Kls III 0.0150 3,800,000- Triplek 6 mm 0.3500 lbr 52,855- Kayu Perancah/Kayu Cerucuk 6.0000 btg 8,500

UPAH :- Pekerja 0.3200 org/hr 70,587- Tukang Kayu 0.3300 org/hr 83,145- Kepala Tukang 0.0330 org/hr 95,726- Mandor 0.0060 org/hr 95,296

JUMLAH

DIBULATKAN4 1 M3 BETON BERTULANG 1 : 2 : 3, UNTUK PONDASI ; BESI 125 KG

BETON 1 PC : 2 PS : 3 KR (A1) 1.0000 Rp 4,722,315.20 PEMBESIAN (B1) 125.0000 kg Rp 9,363.00 BEKISTING (C1) 5.0000 Rp 1,686,590.40

JUMLAH

DIBULATKAN5 1 M3 BETON BERTULANG 1 : 2 : 3, UNTUK BETON SLOOF ; BESI 100 KG

BETON 1 PC : 2 PS : 3 KR (A1) 1.0000 4,722,315PEMBESIAN (B1) 100.0000 kg 9,363

BEKISTING (C2) 6.0000 221,700

JUMLAH

DIBULATKAN6 1 M3 BETON BERTULANG 1 : 2 : 3, UNTUK BETON KOLOM ; BESI 100 KG

BETON 1 PC : 2 PS : 3 KR (A1) 1.0000 4,722,315PEMBESIAN (B1) 100.0000 kg 9,363

BEKISTING (C3) 10.0000 259,500

JUMLAH

m3

m3

m3

m3

m3

m2

m3

m2

m3

m2

Page 61: KAMPUS MEDAN

DIBULATKAN7 1 M3 BETON BERTULANG 1 : 2 : 3, UNTUK BETON KOLOM PRAKTIS ; BESI 180 KG

BETON 1 PC : 2 PS : 3 KR (A1) 1.0000 4,722,315PEMBESIAN (B1) 180.0000 kg 9,363

BEKISTING (C3) 10.0000 259,500

JUMLAH

DIBULATKAN8 1 M3 BETON BERTULANG 1 : 2 : 3, UNTUK BETON RING BALOK ; BESI 100 KG

BETON 1 PC : 2 PS : 3 KR (A1) 1.0000 4,722,315PEMBESIAN (B1) 100.0000 kg 9,363

BEKISTING (C3) 8.0000 259,500

JUMLAH

DIBULATKANVII PEKERJAAN PENUTUP ATAP1 1 M2 PASANG ATAP SENG GELOMBANG

SNI 03-3436-2002(6.38)BAHAN :

- Seng Gel. Bjls 20 k 0.7000 lbr 67,635- Paku Atap Seng 0.0200 kg 17,976

UPAH :- Pekerja 0.1200 org/hr 70,587- Tukang Atap 0.0600 org/hr 83,145- Kepala Tukang 0.0060 org/hr 95,726- Mandor 0.0060 org/hr 95,296

JUMLAH

DIBULATKAN2 1 M' PASANG PERABUNG SENG

SNI 03-3436-2002(6.39)BAHAN :

- Kayu Papan meranti Kls III 0.0170 950,000- Perabung Seng Plat 0.5000 lbr 13,000- Paku biasa 2"-5" 0.2000 kg 12,840

UPAH :- Pekerja 0.4000 org/hr 70,587- Tukang Atap 0.1500 org/hr 83,145- Kepala Tukang 0.0150 org/hr 95,726- Mandor 0.0200 org/hr 95,296

JUMLAH

DIBULATKAN3 1 M' PASANG BOLA-BOLA ATAP

SNI 03-3436-2002(6.40)BAHAN :

- Seng Plat 0.5000 lbr 34,500- Paku atap seng 0.0360 kg 17,250

UPAH :- Pekerja 0.1500 org/hr 70,587- Tukang Atap 0.0700 org/hr 83,145- Kepala Tukang 0.0080 org/hr 95,726- Mandor 0.0060 org/hr 95,296

JUMLAH

m3

m2

m3

m2

m3

Page 62: KAMPUS MEDAN

DIBULATKANVIII PEKERJAAN PENUTUP ATAP1 1 M2 LANGIT-LANGIT PLYWOOD (60 X 120) CM, TEBAL 3.6 MM

SNI 03-2838-2002(6.10)BAHAN :

- Triplek 3.6 mm 0.3750 lbr 52,855- Paku Triplek 0.0300 kg 10,400

UPAH :- Pekerja 0.0700 org/hr 70,587- Tukang Kayu 0.1000 org/hr 83,145- Kepala Tukang 0.0100 org/hr 95,726- Mandor 0.0035 org/hr 95,296

JUMLAHDIBULATKAN

2 1 M2 LANGIT-LANGIT PIRI-PIRI + RANGKASNI 03-2838-2002(6.14)BAHAN :

- Kayu Papan meranti Kls III 0.0240 lbr 3,800,000- Kayu Kaso meranti Kls III 0.0060 kg 3,800,000- Paku Biasa 2"-5" 0.1000 kg 12,840

UPAH :- Pekerja 0.0700 org/hr 70,587- Tukang Kayu 0.1000 org/hr 83,145- Kepala Tukang 0.0100 org/hr 95,726- Mandor 0.0035 org/hr 95,296

JUMLAHDIBULATKAN

3 1 M' LIST LANGIT-LANGIT KAYU PROFILSNI 03-2838-2002(6.19)BAHAN :

- List Profil Kayu 1.1000 lbr 50,000- Paku Biasa 2"-5" 0.0100 kg 12,840

UPAH :- Pekerja 0.0500 org/hr 70,587- Tukang Kayu 0.0500 org/hr 83,145- Kepala Tukang 0.0050 org/hr 95,726- Mandor 0.0030 org/hr 95,296

JUMLAH

DIBULATKANIX PEKERJAAN KUNCI1 1 BH PASANG KUNCI TANAM 2 X PUTAR

SK SNI -1989-F(6.2)BAHAN :

- Kunci Tanam 2 x Putar 1.0000 bh 97,500UPAH :

- Pekerja 0.0100 org/hr 70,587- Tukang Kayu 0.5000 org/hr 83,145- Kepala Tukang 0.0100 org/hr 95,726- Mandor 0.0050 org/hr 95,296

JUMLAH

DIBULATKAN2 1 BH PASANG ENGSEL PINTU

SK SNI -1989-F(6.5)

Page 63: KAMPUS MEDAN

BAHAN :- Engsel 4" Pintu 1.0000 bh 46,300

UPAH :- Pekerja 0.0150 org/hr 70,587- Tukang Kayu 0.1500 org/hr 83,145- Kepala Tukang 0.0150 org/hr 95,726- Mandor 0.0008 org/hr 95,296

JUMLAH

DIBULATKAN3 1 BH PASANG GRENDEL PINTU

SK SNI -1989-F(6.5)BAHAN :

- Grendel 4" Pintu 1.0000 bh 55,250UPAH :

- Pekerja 0.0150 org/hr 70,587- Tukang Kayu 0.1500 org/hr 83,145- Kepala Tukang 0.0150 org/hr 95,726- Mandor 0.0008 org/hr 95,296

JUMLAH

DIBULATKANX PEKERJAAN PENGECATAN1 1 M2 MENDEMPUL DAN MENGGOSOK KAYU

SNI-03-2408-1991(6.6)BAHAN :

- Plamir/Dempul 0.0900 bh 8,500- Minyak Cat/Thiner 0.0200 ltr 9,000- Amplas 0.1000 lbr 3,250

UPAH :- Pekerja 0.0400 org/hr 70,587- Tukang Cat 0.0400 org/hr 83,145- Kepala Tukang 0.0040 org/hr 95,726- Mandor 0.0025 org/hr 95,296

JUMLAH

DIBULATKAN2 1 M2 PENGECATAN DGN CAT MINYAK (1 LPS PLAMIR, 1 LPS CAT DASAR, 2 LPS CAT PENUTUP)

SNI-03-2408-1991(6.8)BAHAN :

- Plamir/Dempul 0.1500 kg 8,500- Cat dasar 0.1700 kg 82,789- Cat minyak 2 x 0.2600 kg 82,789

UPAH :- Pekerja 0.0700 org/hr 70,587- Tukang Cat 0.0090 org/hr 83,145- Kepala Tukang 0.0060 org/hr 95,726- Mandor 0.0025 org/hr 95,296

JUMLAH

DIBULATKAN3 1 M2 PENGECATAN RESIDU

SNI-03-2408-1991(6.12)BAHAN :

- Residu 0.3500 kg 18,000UPAH :

- Pekerja 0.1000 org/hr 70,587

Page 64: KAMPUS MEDAN

- Mandor 0.0060 org/hr 95,296

JUMLAH

DIBULATKAN4 1 M2 PENGECATAN DGN CAT AIR (1 LPS PLAMIR, 1 LPS CAT DASAR, 2 LPS CAT PENUTUP)

SNI-03-2408-1991(6.14)BAHAN :

- Plamir/Dempul 0.1000 kg 8,500- Cat dasar 0.1000 kg 82,789- Cat Air 0.2600 kg 82,789

UPAH :- Pekerja 0.0200 org/hr 70,587- Tukang Cat 0.0630 org/hr 83,145- Kepala Tukang 0.0063 org/hr 95,726- Mandor 0.0025 org/hr 95,296

JUMLAH

DIBULATKAN5 1 M2 PENGECATAN PERMUKAAN KAYU DENGAN MENIE

SNI-03-2408-1991(6.20)BAHAN :

- Cat Menie Kayu 0.1000 kg 85,000- Kuas Biasa 0.0100 bh 17,711

UPAH :- Pekerja 0.0200 org/hr 70,587- Tukang Cat 0.2000 org/hr 83,145- Kepala Tukang 0.0200 org/hr 95,726- Mandor 0.0100 org/hr 95,296

JUMLAH

DIBULATKANXI PEKERJAAN BAJA1 1 UNIT VENTILASI BESI BAJA uk. 1.00 x 1.61 m

BAHAN :- Besi Siku L.3.40.40 9.9000 kg 9,000- Besi Strip tebal 3 mm lebar 3 cm 22.0000 kg 9,000- Mata Las besi 0.1227 kg 75,000

UPAH :- Pekerja 2.0000 org/hr 70,587- Tukang Las/besi 1.0000 org/hr 83,145- Kepala Tukang 0.1000 org/hr 95,726- Mandor 0.0500 org/hr 95,296

JUMLAH

DIBULATKAN2 1 M2 VENTILASI GRILL BESI

XII PEKERJAAN LISTRIK1 1 TITIK INSTALASI PENERANGAN (Termasuk Lampu TL 2x20 watt, saklar dan MCB 2A)

BAHAN :- Kabel NYM 3 x 1.5 mm2 5.0000 m 10,100- 20 mm 3 ways round junction box c/w Lid + Bolt 1.0000 bh 3,600- 20 mm corrugated conduit 1.0000 m 4,800- 20 mm joining coupling 2.0000 bh 1,250- 20 mm saddle 8.0000 bh 1,250- Sekrup/paku 1.0000 ls 2,000- Isolasi listrik 0.2000 bh 3,000- Pipa Conduit PVC klas D 5.0000 m 1,550

Page 65: KAMPUS MEDAN

- Saklar ganda standard 0.5000 bh 78,217- Inbow dus MK 1.0000 bh 2,600- Armature Lampu TL 2 x 20 watt 1.0000 bh 33,000- Lampu TL 20 watt 2.0000 bh 8,500- Starter 1.0000 set 5,000- Fitting Lampu TL 1.0000 set 5,000- Ballast 40 watt 1.0000 bh 30,000

- 0.5000 m 500- MCB 2 A 0.2500 bh 28,675

UPAH :- Pekerja 0.7500 org/hr 70,587- Tukang Listrik 0.6000 org/hr 83,145- Kepala Tukang 0.3000 org/hr 95,726- Mandor 0.1500 org/hr 95,296

JUMLAH

DIBULATKAN2 1 TITIK INSTALASI STOPKONTAK (Termasuk Stopkontak dan MCB 6 A)

BAHAN :- Kabel NYM 3 x 2.5 mm2 5.0000 m 12,800- Inbow dus MK 1.0000 bh 2,600- 20 mm 3 ways round junction box c/w Lid + Bolt 1.0000 bh 3,600- 20 mm corrugated conduit 1.0000 m 4,800- 20 mm joining coupling 2.0000 bh 1,250- 20 mm saddle 8.0000 bh 1,250- Sekrup/paku 1.0000 ls 2,000- Isolasi listrik 0.2000 bh 3,000- Pipa Conduit PVC klas D 5.0000 m 1,550

UPAH :- Pekerja 0.7500 org/hr 78,217- Tukang Listrik 0.6000 org/hr 83,145- Kepala Tukang 0.3000 org/hr 33,000

- Mandor 0.1500 org/hr 8,500

JUMLAH

DIBULATKAN

ANALISA TAMBAHAN

Anl. L.7

10.200 Pekerja × Rp 70,587.00 0.100 Mandor × Rp 95,296.00

Anl. L.9

10.250 tukang kayu × Rp 83,145.00 0.025 kepala tukang × Rp 95,726.00 1.000 pekerja × Rp 70,587.00 0.050 mandor × Rp 95,296.00

Anl. L.12

1 pembongkaran kusen pintu dan jendela

Kabel 1x0.9 mm2

m2 pembongkaran dan penurunan atap 10m²

m2 pembongkaran dan penurunan rangka atap 10m²

m3

Page 66: KAMPUS MEDAN

Anl. L.12

6.000 tukang kayu × Rp 83,145.00 0.600 kepala tukang × Rp 95,726.00 4.000 pekerja × Rp 70,587.00 0.200 mandor × Rp 95,296.00

(2/3)

Anl. L.5

12.000 pekerja × Rp 70,587.00 0.100 mandor × Rp 95,296.00

Anl. L.4

1 pembongkaran dinding 2.000 pekerja × Rp 70,587.00 0.100 mandor × Rp 95,296.00

m2 pembongkaran lantai lama 10M²

m3

Page 67: KAMPUS MEDAN

ANALISA HARGA SATUAN (SNI)

JUMLAH HARGA JUMLAHMATERIAL UPAH HARGA

(Rp.) (Rp.) (Rp.)

5 6 7

Rp 7,058.70

Rp 476.48

0 Rp 7,535.18 Rp 7,535.18

Rp 7,535.18

45,600

257

26,600

Rp 705.87

Rp 831.45

Rp 95.73

Rp 476.48

72,457 Rp 2,109.53 74,56674,500

5,294

238

5,532 5,5325,532

28,2353,812

32,047 32,04732,047

13,5531,811

15,363 15,36315,300

Page 68: KAMPUS MEDAN

162,000

13,5531,830

162,000 15,382 177,382177,300

162,000

21,176953

162,000 22,129 184,129184,129

267,750

16,23512,804

287286

267,750 29,612 297,362297,362

86,625

61,0508,589,158

19686556,47049,8875,7447,147

8,933,698 119,247 9,052,9459,052,945

80,0002,687,974

14,800

45,88216,6291,9152,859

2,782,774 67,284 2,850,058

Page 69: KAMPUS MEDAN

2,850,058

40,0001,170,968

7,030

22,5888,315

9571,429

1,217,998 33,289 1,251,2871,251,200

40,000710,614

7,955

22,5888,315

9571,429

758,569 33,289 791,858791,800

882,397

4,255

17,64716,6291,915

11,912

886,652 48,102 934,754934,700

667,359

4,810

17,64716,6291,915

11,912

672,169 48,102 720,271720,200

Page 70: KAMPUS MEDAN

536,359

5,180

17,64716,6291,915

11,912

541,539 48,102 589,641589,600

400,415

3,515

14,11712,4721,436

953

403,930 28,978 432,908432,900

6,733,088295

423,522

1,662,900191,452

28,589

6,733,383 2,306,463 9,039,8469,039,800

6,733,088135,000

10,272

282,348997,740114,871

19,059

6,878,360 1,414,018 8,292,3788,292,378

Page 71: KAMPUS MEDAN

6,733,0886,420

141,174498,870114,871

19,059

6,739,508 773,974 7,513,4827,513,482

73,4521,926

7,0598,315

957476

75,378 16,807 92,18592,100

73,4521,284

10,58820,7862,3937,147

74,736 40,915 115,651115,651

88,754770

10,58820,7862,3937,147

89,525 40,915 130,439130,400

000

Page 72: KAMPUS MEDAN

141,174332,580

38,29019,059

0 531,104 531,104531,100

000

141,174498,870

57,43628,589

0 726,068 726,068726,000

15,161,90098,483

140,940

116,46920,7862,3937,624

15,401,323 147,272 15,548,59415,548,594

777,430

589,600

1,367,030 1,367,0301,367,000

26,985,400123,104

105,300

423,52283,1459,573

28,589

27,213,804 544,828 27,758,63227,758,632

Page 73: KAMPUS MEDAN

9,831193

494.109582.01567.008228.5888

10,024 1171.721 11,19511,100

152,0003,8521,100

21,17621,6182,489

476

156,952 45,759 202,711202,700

171,0003,8521,100

21,17621,6182,489

476

175,952 45,759 221,711221,700

171,0003,8521,100

14,25017,000

21,17627,4383,159

572

207,202 52,345 259,547259,500

Page 74: KAMPUS MEDAN

152,0005,1362,200

17,10018,49917,000

22,58827,4383,159

572

211,935 53,756 265,692265,600

152,0005,1362,200

57,00018,49951,000

22,58827,4383,159

572

285,835 53,756 339,592339,500

4,722,315

1,170,375

8,432,952

14,325,64214,325,642

4,722,315936,300

1,330,200

6,988,8156,988,815

4,722,315936,300

2,595,000

8,253,615

Page 75: KAMPUS MEDAN

8,253,615

4,722,3151,685,340

2,595,000

9,002,6559,002,655

4,722,315936,300

2,076,000

7,734,6157,734,615

47,344360

8,4704,989

574572

47,704 14,605 62,30962,300

16,1506,5002,568

28,23512,4721,4361,906

25,218 44,048 69,26669,266

17,250621

10,5885,820

766572

17,871 17,746 35,617

Page 76: KAMPUS MEDAN

35,600

19,821312

4,9418,315

957334

20,133 14,546 34,67934,600

91,20022,8001,284

4,9418,315

957334

115,284 14,546 129,830129,800

55,000128

3,5294,157

479286

55,128 8,451 63,58063,580

97,500

70641,573

957476

97,500 43,712 141,212141,212

Page 77: KAMPUS MEDAN

46,300

1,05912,4721,436

76

46,300 15,043 61,34361,300

55,250

1,05912,4721,436

76

55,250 15,043 70,29370,200

765180325

2,8233,326

383238

1,270 6,770 8,0408,000

1,27514,07421,525

4,941748574238

36,874 6,502 43,37643,300

6,300

7,059

Page 78: KAMPUS MEDAN

572

6,300 7,630 13,93013,900

8508,279

21,525

1,4125,238

603238

30,654 7,491 38,14538,100

8,500177

1,41216,6291,915

953

8,677 20,908 29,585 11 kg/btg29,500 4 kg/btg

1 btg = 30 cm ; 1 kg = 50 btg las

89,100198,000

9,200

141,17483,1459,5734,765

296,300 238,656 534,956534,900333,000

50,5003,6004,8002,500

10,0002,000

6007,750

Page 79: KAMPUS MEDAN

39,1092,600

33,00017,0005,0005,000

30,000

2507,169

52,94049,88728,71814,294

220,877 145,839 366,717366,700

64,0002,6003,6004,8002,500

10,0002,000

6007,750

58,66349,8879,900

1,275

97,850 119,725 217,575

217,575

ANALISA TAMBAHAN

= Rp 14,117.40 = Rp 9,529.60

Jumlah = Rp 23,647.00 Dibulatkan = Rp 23,647.00

= Rp 20,786.25 = Rp 2,393.15 = Rp 70,587.00 = Rp 4,764.80

Jumlah = Rp 98,531.20 Dibulatkan = Rp 98,531.20

pembongkaran kusen pintu dan jendela

Page 80: KAMPUS MEDAN

= Rp 498,870.00 = Rp 57,435.60 = Rp 282,348.00 = Rp 19,059.20

Jumlah = Rp 857,712.80 Dibulatkan = Rp 571,808.53

= Rp 141,174.00 = Rp 9,529.60

Jumlah = Rp 150,703.60 Dibulatkan = Rp 150,703.60

pembongkaran dinding = Rp 141,174.00 = Rp 9,529.60

Jumlah = Rp 150,703.60 Dibulatkan = Rp 150,703.60

Page 81: KAMPUS MEDAN

PEMBONGKARAN DAN PEMBERSIHAN BANGUNAN EXISTING

NO. ITEM PEKERJAAN ANALISA SATUAN VOLUME1 2 3 4 5

I. PEMBONGKARAN DAN PENURUNAN ATAP

1 Anl. L.7 874.80

II. PEMBONGKARAN DAN PENURUNAN RANGKA ATAP

1 Anl. L.9 425.25

III. PEMBONGKARAN KUSEN PINTU DAN JENDELA

1 Membongkar Kusen pintu Anl. L.12 0.19

2 Membongkar Kusen Jendela Anl. L.12 1.69

IVPEMBONGKARAN DINDING LAMA

1 Pembongkaran dan penurunan dinding Anl. L.4 3.87

V. PEMBONGKARAN RING BALOK

1 pembongkaran ring balok Anl. L.4 1.12

5.00

REHAB BANGUNAN LAMA

RENCANA ANGGARAN BIAYA PEMBONGKARAN DAN REHAB BANGUNAN GEDUNG LEMBAGA PENDIDIKAN PERKEBUNAN KAMPUS MEDAN

Menurunkan Penutup Atap (10M²) M2

Menurunkan 10M² Rangka atap dari kayu M2

M3

M3

M3

M2

Page 82: KAMPUS MEDAN

I. PEKERJAAN PERSIAPAN, GALIAN DAN URUGAN

1 Pekerjaan persiapan (perbersihan lokasi pekerjaan) Dih 1,018.00

2 Pekerjaan pengukuran dan pemasangan bowplank Dih 0.00

3 Pekerjaan galian tanah untuk pondasi A. 1 0.00

4 Timbunan tanah kembali ke bekas galian pondasi 0.00

5 Pekerjaan urugan pasir / urugan tanah A. 18 0.00

II. PEKERJAAN PONDASI DAN BETON

1 Pondasi batu kali camp 1pc :4ps 0.00

2 Pas.timbrisan batu kosong G.1 0.00

3 Balok sloof camp.1pc :2ps:3kr Supl. V 0.00

4 Kolom camp.1pc :2ps:3kr 0.72

5 Ring balk camp.1pc :2ps:3kr 0.38

6 Pengecoran plat lantai camp.1pc :2ps:3kr Supl. V 0.00

7 Pengecoran lantai camp.1pc :2ps:5kr 13.00

III. PEKERJAAN PASANGAN DINDING DAN PLESTERAN

1 Pasangan dinding camp.1pc :2ps 0.00

2 Pasangan dinding camp.1pc :4ps 3.87

3 Pasangan Rollag bata camp.1pc:4ps 0.00

4 Plesteran dinding camp.1pc :2ps 12.90

5 Plesteran dinding camp.1pc :4ps 45.57

IV. PEKERJAAN LANTAI

1 Pasangan keramik uk.60X60 Spul. V 260

2 Pasangan keramik uk.20x20 Spul. IV 0.00

3 Pasangan keramik uk.30x30 Spul. III 0.00

VI. PEKERJAAN PLAFOND

1 Memasang rangka plafond 2.46

M2

M1

M3

1/4 A. 1 M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M2

M2

M2

M2

M2

M2

M2

M3

A73
Corporate Edition:
Page 83: KAMPUS MEDAN

2 Memasang plafond triplek 3.5MM 1,228.00

VII. PEKERJAAN KUSEN PINTU DAN JENDELA

1 Pasangan kusen pintu type PJ1= 1 set 0.00

2 Pasangan kusen type P1 = 10 set 0.16

3 Pasangan kusen typeJ1 = 8 set 0.19

4 Pasangan kusen type J3= 1 set 0.00

5 Pasangan kusen type J6 = 1 set 0.00

67

VII. PEKERJAAN DAUN PINTU DAN JENDELA

1 Daun pintu type PJ1= 2 set F.34 20.90

2 Daun pintu type P1= 1 set F. 36 0.00

3 Daun Pintu type P2= 3 set F. 34

4 Daun Pintu type P3= 2 set F. 34

5 Daun Pintu type P4=2 set F. 36

6 Daun jendela type J1 = 8 set F. 36 24.66

7 Daun jendela type J2 = 2 set F. 36

8 Daun jendela J3 =1 set F. 36 0

9 Daun jendela type J4 =1 set F. 36

10 Daun jendela J5 = 1 set F. 36

11 Daun jendela type J6 =1 set F. 36 0

VIII. PEKERJAAN PENGECATAN

1 Pengecatan dinding 3x sapu K. 16 961.33

2 pengecatan kusen pintu dan jendela Supl.IX 83.86

IX. PEKERJAAN PERLENGKAPAN PINTU DAN JENDELAIX Kunci pintu Dih bh 10.002 Engsel pintu Dih bh 18.003 handel pintu Dih bh 94 Engsel jendela Dih bh 86.005 Grendel pintu Dih bh 10.006 Grendel jendela Dih bh 16.007 Hak angin jendela Dih bh 0.00

M2

M3

M3

M3

M3

M3

M2

M2

M2

M2

M2

M2

M2

M2

M2

M2

M2

M2

M2

Page 84: KAMPUS MEDAN

8 Tarikan jendela Dih bh 0.00

X. PEKERJAAN SANITASI1 Klosek duduk Dih bh 8.002 Kran air Dih bh 14.003 Kran meja dapur Dih bh 0.004 Floor drain Dih bh 0.005 Kitchen sink Dih bh 0.006 kompor Dih bh 07 spingker Dih bh 15.00

8 Pipa pvc air kotor cair 3" Dih 102.72

9 Pipa pvc air kotor padat 4" Dih bh 20.60

10 Pipa pvc air bersih 3/4" Dih 20.60

XI. PEKERJAAN INSTALASI LISTRIK1 kabel NYM Dih Glg 68.662 lampu TL Dih bh 84.003 lampu side box Dih bh 0.004 sklar tunggal Dih bh 15.005 saklar ganda Dih bh 37.006 saklar triple Dih bh 07 stop kontak Dih bh 37.008

XI. PEKERJAAN ATAP

1 Rangka kuda - kuda+reng 874.80

2 Seng bjls gelombang 874.80

3 Rabung seng 82.00

4 Papan lisplank H.10

5 Atap kaca 0

6 Besi Holo 0

XIII. PEMBERSIHAN LAHAN1 Pembersihan puing puing bangunan Dih ls 1,228.002 foto documentasi dan administrasi Dih ls 5,000,000.00

M1

M1

M2

M2

M2

M1

M2

M2

Page 85: KAMPUS MEDAN

PEMBONGKARAN DAN PEMBERSIHAN BANGUNAN EXISTING

HARGA SATUAN (Rp) JUMLAH (Rp)6 7

Rp 23,647.00 Rp 2,068,639.56

Jumlah Rp 2,068,639.56 Dibulatkan Rp 2,068,639.56

Rp 98,531.20 Rp 41,900,392.80

Jumlah Rp 41,900,392.80 Dibulatkan Rp 41,900,392.80

Rp 571,808.00 Rp 107,214.00

Rp 571,808.00 Rp 966,355.52

Jumlah Rp 1,073,569.52

Dibulatkan Rp 1,073,569.52

Rp 150,703.00 Rp 583,220.61

Jumlah Rp 583,220.61 Dibulatkan Rp 583,220.61

Rp 150,703.00 Rp 168,787.36

Jumlah Rp 843,936.80 Dibulatkan Rp 843,936.80

REHAB BANGUNAN LAMA

RENCANA ANGGARAN BIAYA PEMBONGKARAN DAN REHAB BANGUNAN GEDUNG LEMBAGA PENDIDIKAN PERKEBUNAN KAMPUS MEDAN

Page 86: KAMPUS MEDAN

I. PEKERJAAN PERSIAPAN, GALIAN DAN URUGAN

Rp 7,535.18 Rp 7,670,813.24

Rp 10,000.00 Rp -

Rp 39,625.00 Rp -

Rp 39,625.00 Rp -

Rp 117,850.00 Rp -

Jumlah Rp 7,670,813.24 Dibulatkan Rp 7,670,813.24

Rp - Rp -

Rp - Rp -

Rp - Rp -

14,325,642 Rp 10,314,462.24

Rp 14,325,642.00 Rp 5,372,115.75

Rp - Rp -

Rp 1,367,000.00 Rp 17,771,000.00

Jumlah Rp 33,457,577.99 Dibulatkan Rp 33,457,577.99

Rp - Rp -

Rp 1,251,200.00 Rp 4,842,144.00

Rp - Rp -

Rp 934,700.00 Rp 12,057,630.00

Rp 589,600.00 Rp 26,868,072.00

Jumlah Rp 43,767,846.00 Dibulatkan Rp 43,767,846.00

Rp 95,000.00 Rp 24,700,000.00

Rp - Rp -

Rp - Rp -

Jumlah Rp 24,700,000.00 Dibulatkan Rp 49,400,000.00

Rp 129,800.00 Rp 319,308.00

Page 87: KAMPUS MEDAN

Rp 34,600.00 Rp 42,488,800.00

Jumlah Rp 42,808,108.00 Dibulatkan Rp 42,808,108.00

Rp 7,347,750.00 Rp -

Rp 7,347,750.00 Rp 1,146,249.00

Rp 7,347,750.00 Rp 1,359,333.75

Rp 7,347,750.00 Rp -

Rp 7,347,750.00 Rp -

Jumlah Rp 2,505,582.75 Dibulatkan Rp 2,505,582.75

Rp 877,222.50 Rp 18,333,950.25

Rp 502,250.00 Rp -

Rp 877,222.50 Rp -

Rp 877,222.50 Rp -

Rp 502,250.00 Rp -

Rp 502,250.00 Rp 12,385,485.00

Rp 502,250.00 Rp -

Rp 502,250.00 Rp -

Rp 502,250.00 Rp -

Rp 502,250.00 Rp -

Rp 502,250.00 Rp -

Jumlah Rp 30,719,435.25 Dibulatkan Rp 30,719,435.25

Rp 27,945.00 Rp 26,864,450.69

Rp 29,500.00 Rp 2,473,870.00

Jumlah Rp 29,338,320.69 Dibulatkan Rp 29,338,320.69

Rp 141,212.00 Rp 1,412,120.00 Rp 61,300.00 Rp 1,103,400.00 Rp 95,000.00 Rp 855,000.00 Rp 61,300.00 Rp 5,271,800.00 Rp 15,000.00 Rp 150,000.00 Rp 20,000.00 Rp 320,000.00 Rp - Rp -

Page 88: KAMPUS MEDAN

Rp - Rp - Jumlah Rp 9,112,320.00

Dibulatkan Rp 9,112,320.00

Rp 1,200,000.00 Rp 9,600,000.00 Rp 25,000.00 Rp 350,000.00 Rp - Rp - Rp - Rp - Rp - Rp - Rp - Rp - Rp 35,000.00 Rp 525,000.00

Rp 75,000.00 Rp 7,704,000.00

Rp 35,000.00 Rp 721,000.00

Rp 40,000.00 Rp 824,000.00

Jumlah Rp 19,724,000.00 Dibulatkan Rp 19,724,000.00

Rp 65,000.00 Rp 4,462,900.00 Rp 75,000.00 Rp 6,300,000.00 Rp - Rp - Rp 15,000.00 Rp 225,000.00 Rp 39,103.00 Rp 1,446,811.00 Rp - Rp - Rp 217,575.00 Rp 8,050,275.00

Jumlah Rp 20,484,986.00 Dibulatkan Rp 20,484,986.00

Rp 38,630.00 Rp 33,793,524.00

Rp 62,300.00 Rp 54,500,040.00

Rp 69,266.00 Rp 5,679,812.00

Rp 69,266.00 Rp -

0 Rp -

0 Rp - 0 Rp -

Jumlah Rp 93,973,376.00 Dibulatkan Rp 93,973,376.00

Rp 7,535.18 Rp 9,253,201.04 Jumlah 5,000,000.00

Dibulatkan Rp 14,253,201.04

Page 89: KAMPUS MEDAN

REKAPITULASI BIAYA

NO. URAIAN PEKERJAAN

I. PEMBONGKARAN BANGUNAN EXISTINGI. Menurunkan penutup atap

II. Menurunkan rangka atap dari kayu

III. Pembongkaran kusen pintu dan jendela

IV. Pembongkaran dinding lama

V. Pembongkaran ring balok

JUMLAH

Dibulatkan

II. REHAB DAN PERBAIKAN BANGUNAN LAMA

I. PEKERJAAN PERSIAPAN,GALIAN DAN URUGAN

II. PEKERJAAN PONDASI DAN BETON

III. PEKERJAAN PASANGAN DINDING DAN PLESTERA

IV. PEKERJAAN LANTAI

V. PEKERJAAN PLAFOND

VI. PEKERJAAN KUSEN PINTU DAN JENDELA

VII. PEKERJAAN DAUN PINTU DAN JENDELA

VIII. PEKERJAAN PENGECATAN

IX. PEKERJAAN PERLENGKAPAN PINTU DAN JENDEL

X. PEKERJAAN SANITASI

XI. PEKERJAAN INSTALASI LISTRIK

XII. PEKERJAAN ATAP

XIII. PEMBERSIHAN LAHAN

JUMLAH

Dibulatkan

JUMLAH PEKERJAAN I DAN II

JUMLAH Rp 418,985,260.96

- TOTAL -

PEMBANGUNAN GEDUNG LEMBAGA PENDIDIKAN PERKEBUNAN KAMPUS MEDAN

JASA PELAKSANAAN 10%

Page 90: KAMPUS MEDAN

DIBULATKAN -

MEDAN 19 APRIL 2012

MAT ARCHITECT TEAM

TERBILANG : Empat ratus delapan belas juta sembilan ratus delapan puluh lima ribu dua ratus enampuluh rupiah

Page 91: KAMPUS MEDAN

REKAPITULASI BIAYA

HARGA SATUAN

Rp 2,068,639.56

Rp 41,900,392.80 Rp 1,073,569.52 Rp 583,220.61 Rp 843,936.80 Rp 46,469,759.29 Rp 46,469,700.00

Rp 7,670,813.24 Rp 33,457,577.99 Rp 43,767,840.00 Rp 24,700,000.00 Rp 42,808,108.00 Rp 2,505,582.75 Rp 30,719,435.25 Rp 29,338,320.69 Rp 9,112,320.00 Rp 19,724,000.00 Rp 20,484,986.00 Rp 93,973,376.00 Rp 14,253,201.04 Rp 372,515,560.96 Rp 372,515,560.96

Rp 418,985,260.96

PEMBANGUNAN GEDUNG LEMBAGA PENDIDIKAN PERKEBUNAN KAMPUS MEDAN

Page 92: KAMPUS MEDAN

TERBILANG : Empat ratus delapan belas juta sembilan ratus delapan puluh lima ribu dua ratus enampuluh rupiah