DNV RP A205 Offshore Commissioning

58
8/20/2019 DNV RP A205 Offshore Commissioning http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 1/58 RECOMMENDED PRACTICE The electronic pdf version of this document found through http://www.dnv.com is the officially binding version DNV-RP-A205 Offshore Classification Projects - Testing and Commissioning MARCH 2012

Transcript of DNV RP A205 Offshore Commissioning

Page 1: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 1/58

RECOMMENDED PRACTICE

The electronic pdf version of this document found through http://www.dnv.com is the officially binding version

DNV-RP-A205

Offshore Classification Projects -Testing and Commissioning

MARCH 2012

Page 2: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 2/58

FOREWORD

DET NORSKE VERITAS (DNV) is an autonomous and independent foundation with the objectives of safeguarding life, property and the environment, at sea and onshore. DNV undertakes classification, certification, and other verification andconsultancy services relating to quality of ships, offshore units and installations, and onshore industries worldwide, and

carries out research in relation to these functions.DNV service documents consist of among others the following types of documents:

 —  Service Specifications. Procedual requirements.

 —  Standards. Technical requirements.

 —   Recommended Practices. Guidance.

The Standards and Recommended Practices are offered within the following areas:

A) Qualification, Quality and Safety Methodology

B) Materials Technology

C) Structures

D) Systems

E) Special Facilities

F) Pipelines and Risers

G) Asset Operation

H) Marine Operations

J) Cleaner Energy

O) Subsea Systems

Page 3: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 3/58

  Recommended Practice DNV-RP-A205, March 2012

Changes – Page 3

CHANGES

General

This is a new document.

Page 4: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 4/58

  Recommended Practice DNV-RP-A205, March 2012

Contents – Page 4

CONTENTS

1. Introduction............................................................................................................................................ 5

1.1 Preamble ...................................................................................................................................................51.2 General ......................................................................................................................................................51.3 Objective ...................................................................................................................................................51.4 Scope and Application..............................................................................................................................51.5 Structure of this document........................................................................................................................51.6 How to use this document.........................................................................................................................51.7 References.................................................................................................................................................51.8 Abbreviations............................................................................................................................................6

2. Commissioning Process and Definition of Various Stages................................................................. 7

2.1 Detailed design..........................................................................................................................................72.2 Mechanical Completion............................................................................................................................7

3. Pre-commissioning................................................................................................................................. 83.1 Commissioning .........................................................................................................................................83.2 Integration testing .....................................................................................................................................83.3 Marine sea trial .........................................................................................................................................93.4 Delivery.....................................................................................................................................................93.5 Hook up.....................................................................................................................................................93.6 Operation...................................................................................................................................................9

4. Commissioning Procedures................................................................................................................... 95. DNV Involvement in Commissioning................................................................................................. 11

Appendix A. DNV Typical Survey Categorization for Drillships during Mechanical Completion

and Commissioning of Marine and Drilling Systems ................................................................................. 12

Appendix B. DNV Typical Survey Categorization for Semi-submersible Units during Mechanical

Completion and Commissioning of Marine and Drilling Systems ........................................................... 16

Appendix C. DNV Typical Survey Categorization for “Jack-up” Units during Mechanical

Completion and Commissioning of Marine and Drilling Systems ........................................................... 20Appendix D. DNV Typical Survey Categorization for FPSO Units during Mechanical

Completion and Commissioning of Marine and Production Systems ...................................................... 24

Appendix E. DNV Typical Survey Categorization for FSO Units during Mechanical

Completion and Commissioning of Marine and Production Systems....................................................... 25

Appendix F.DNV Requirements Related to Marine, Utility and Safety Systems ................................... 26

Appendix G. Survey Scope for Specific Class Notations ............................................................................ 52

Page 5: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 5/58

  Recommended Practice DNV-RP-A205, March 2012

Sec.1. Introduction – Page 5

1. Introduction

1.1 Preamble

This Recommended Practice (RP) outlines the general best practices that lead to effective testing andcommissioning of marine and industrial systems onboard mobile offshore units in newbuilding projects. For convenience, an extract of all DNV rules related to testing and commissioning of marine and industrial systemshave been included in this document. It should be noted that for more accurate applicable statutory and classrequirements related to testing and commissioning, applicable versions of the statutory and class rules asspecified in the contract shall be referred to. System categorizations included in the appendix are general innature and may not include all applicable systems that are specific to particular newbuilding projects and so,this document should be used only as a guide. This document currently includes requirements related to drillingunits with the intention to include requirements related to other object types at a later stage.

1.2 GeneralDNV has recognized that the technical complexity of modern Offshore Installations is increasing due tosystems becoming more complex, more automated and more tightly integrated. This evolution providesdesigners, shipyards, owners and other involved parties challenges in the management of testing andcommissioning equipment and systems onboard offshore units successfully.

1.3 Objective

This RP outlines recommended work processes for the testing and commissioning activities on offshorenewbuild units. This document shall be read as a  guide to testing and commissioning equipment ad systems

onboard Offshore Units. The document will help users in preparing or carrying out witnessing of testing andcommissioning activities to satisfy the requirements of classification and applicable statutory regulations whereDNV has delegation from such authorities. It should be noted that final acceptance of commissioning is theowner’s responsibility.

1.4 Scope and Application

This guide is applicable to testing and commissioning activities onboard classed Mobile Offshore Units e.g.,Drilling, Accommodation and FPSO’s.

1.5 Structure of this document

This document contains

 — a general overview of testing and commissioning activities together with samples of typical contents of testing and commissioning procedures including the ones for integration testing and commissioning

 — Extract of applicable DNV Service Specifications and DNV standards related to preparation, testing andcommissioning of various marine, utility and industrial systems

 — Categorization of marine, utility and industrial systems that can be used to decide on the extent of involvement from various stakeholders.

The RP can be used as a check list for reviewing Commissioning procedures to assist preparation of 

requirements related to class and applicable statutory regulations.

1.6 How to use this document

The main function of the RP is to ensure that the commissioning procedures contain all the relevant informationrequired by the applicable DNV Service Specifications and DNV Offshore Standards.

If the commissioning procedures are reviewed against this document, they should contain all the requiredinformation to ensure compliance with the various offshore standards thus ensuring that testing and

Page 6: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 6/58

  Recommended Practice DNV-RP-A205, March 2012

Sec.1. Introduction – Page 6

1.8 Abbreviations

 Abbreviation Description

AC Alternating CurrentBOP Blow Out Preventer  

CSG Casing

DAT Digital Audio Tape

DB Distribution Board

DC Direct Current

DFMA Design for Manufacture and Assembly

DP Dynamic Positioning System

ESD Emergency Shut DownF&G fire & gas (systems)

FPSO Floating Production, Storage and Offloading (Unit)

FSO Floating Storage and Offloading (Unit)

FW Fresh Water  

HP High Pressure

HPU Hydraulic Power Unit

HVAC Heating, Ventilation & Air Conditioning

ICCP Impressed Current Cathodic ProtectionICMS Integrated Control and Management System

LER Local Electrical Room

LIR Local Instrument Room

LMRP Lower Marine Riser Package

LP Low Pressure

LQ Living Quarter  

LV Low Voltage

MC Mechanical CompletionMCC Main Control Center  

MGPS Marine Growth Protection System

P & ID Piping & Instrument Diagram

PA/GA Public Address / General Alarm

PMS Power Management System

PSD Process Shut Down

QA Quality Assurance

QC Quality ControlQSP Quality Survey Plan

SIT System Integration Test

SWBD Switchboard

UPS Uninterruptable Power Supply

VDU Visual Display Unit

i bl i

Page 7: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 7/58

  Recommended Practice DNV-RP-A205, March 2012

Sec.2. Commissioning Process and Definition of Various Stages – Page 7

2. Commissioning Process and Definition of Various Stages

Commissioning of an offshore unit is a time consuming and complex process. A structured approach is anecessity for a successful commissioning phase of the newbuilding projects. While the requirements for thetesting and commissioning are clearly specified in various applicable DNV standards, how exactly thecommissioning activities should be carried out is largely left to the Builder/Owners of the mobile offshoreunits. For instance, there will be dependencies between the different packages. It is, however, a DNVrequirement to see that the testing requirements mentioned in our rules are carried out during commissioning.It is often required by DNV offshore standards that the equipment is to be tested in “as installed” condition. So,

though similar tests have already been carried out during a factory acceptance test (FAT), a new test in installedcondition would be required., A typical example could be the offshore cranes. They will probably be overloadtested during FAT, but they will still be required to have an overload test in installed condition.

Before commissioning starts the responsible DNV surveyor and all stakeholders involved in preparing andcarrying out the testing and commissioning should also have an idea as to what activities are considered mostimportant to DNV and also what activities are not within the DNV scope. During commissioning it is alsoimportant to be aware that the owner’s and the yard’s viewpoint as to what is DNV’s scope of work may not

 be in harmony with the scope required by the DNV Offshore standards. It is also important to recognize thatowner/yard may have additional requirements e.g., related to performance or additional functionality, that may

 be over and above the classification requirements of DNV.

2.1 Detailed design

When entering into the final stages of any project, the detailed design is expected to be fully completed,reviewed and approved. Failure to complete the design in a satisfactory manner may undermine alreadycompleted testing and commissioning, especially comments that may result in redesigning component or systems. Any duplication in redoing testing and commissioning is not very efficient and will result in loss of 

Page 8: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 8/58

  Recommended Practice DNV-RP-A205, March 2012

Sec.3. Pre-commissioning – Page 8

cabling, electrical equipment, etc. have been demonstrated as physically complete. Dynamic tests are limitedto non-energised tests like cold alignment of shafting for motors, engines and generators. Further megger tests,flushing and drying of piping systems, cleaning, etc. is included in this milestone. Typically, the MC will result

in a number of punches that must be rectified before any actual pre-commissioning, testing and commissioningcan commence. Normal findings typically include missing electrical equipment grounding, lack of proper shielding of fuel pipes or hot surfaces, insufficient nozzle coverage for deluge systems, etc. The evidence of the required certification of equipment should be verified during mechanical completion stage so that there areno surprises before commencing pre-commissioning, testing and commissioning stages. Failure to do so may

 jeopardize the safety of such activities.

3. Pre-commissioning

Pre-commissioning is the stage before commissioning which involves the verification of functional operabilityof the equipment part or full systems. This stage of testing requires energising of equipment and introduction of fluids in fluid piping systems. This is the stage where the vendor and/or the yard are carrying out independenttesting of the equipment/system. This is a “trial and error” phase where class normally do not attend. Duringreview and approval of commissioning procedures, it is important for the DNV surveyor to make sure that testsrequired by the rules are carried out during the commissioning phase. It may be a challenge when the testsrequired by the rules are carried out during pre-commissioning but not attended by a DNV Surveyor. This should

 be highlighted during the review of the commissioning procedures. Pre-Commissioning would typically include:

 — Loop testing. — Motor no load runs.

 — Equipment final alignments.

3.1 Commissioning

The phase after mechanical completion, pre commissioning and testing is often referred to as thecommissioning phase. The “commissioning of an an offshore unit” is a very wide term and for the purpose of classification, it refers to equipment or system commissioning. Typically equipment/system commissioning

will consist of: — Functional testing of systems by start-up priority.

 — Testing of ESD/PSD and F&G.

 — Load tests and other equipment performance testing.

In the commissioning phase it will be verified that the installed equipment and system are working as intendedand that the rule requirements for the various equipment/system functionality are met. The rules will haverequirements for “performance”, e.g. number of starts for starting air receivers and “functionality”, e.g. safetyfunctions of boilers and incinerators.

For effective commissioning, it is important that the testing and commissioning of the different skids/packagesare given the right priority so that they happen in the right sequence/order. Very little commissioning can be

 performed without the hydraulic ring line, power system, cooling water, pneumatic systems and other utilities being functional and working properly, Typically, temporary arrangements should not be accepted for commissioning. It should also be a general principle that commissioned equipment is not dismantled or modified after testing and commissioning of the equipment/system is completed. Once the equipment/system

Page 9: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 9/58

  Recommended Practice DNV-RP-A205, March 2012

Sec.4. Commissioning Procedures – Page 9

3.3 Marine sea trial

The marine sea trials typically focuses on propulsion, steering and utility systems functioning under normal

operating conditions. A prerequisite for sea trials is that the major safety systems like fire fighting, life-saving

appliances, PA/GA, HVAC, etc. are satisfactorily commissioned ahead of sea trials. In addition, the inclining

test should be completed prior to taking the unit out on sea trial.

Sea trials are conducted to test a vessels performance and general seaworthiness. Testing of a vessels speed,

manoeuvrability, equipment and safety features are usually conducted during sea trial. However, this

demonstration of speed and manoeuvrability, etc. is normally more important for a merchant vessel than an

offshore unit. A merchant vessel will typically have a contract speed as part of the contract between the builder 

and the owner. That is seldom the case for an offshore unit. The marine sea trial will typically consist of but

not limited to:

 — Testing of Dynamic Positioning System.

 — Final commissioning of Ballast systems, Cooling water, Lube oil, Fuel Oil, HVAC, Thrusters, etc.

 — Speed test.

 — Crash stop.

 — Turning test.

 —  E0 test.

 — Endurance test.

The marine sea trial is normally not relevant for fixed units or units without propulsion.

3.4 Delivery

Depending on type of unit, the successful completion of all testing and commissioning activities will trigger 

the delivery of the unit. The level of completion will however vary from project to project. Typically a project

with a contract in place and a long transit to the operation area, the owner may prefer an early delivery with the

intention to close some of the outstanding items in transit. If a unit does not have a project in place, the owner 

will typically aim for a higher level of completion before they will accept the unit. Equipment subject to classapproval that is not readily commissioned in accordance with approved testing and commissioning procedures

should be identified in the delivery documentation by issuance of relevant conditions of class. It should be

evaluated prior to delivery whether the outstanding class and statutory systems are minor in nature and does

not affect the safety and integrity of the unit that will allow the Class Society to issue appropriate Class and

Statutory Certificates. If critical systems e.g., fire fighting/detection, propulsion and steering, life-saving

appliances, navigational aids, etc. are not commissioned, Class and Statutory Certificates are not typically

issued.

3.5 Hook up

Hook up is mostly relevant for fixed units like FPSO’s and other units that will stay on the same location for a

number of years, however some drilling units may require some testing of systems on first location. Typically

it means the hook up of risers to the unit and preparations required prior to first oil. Many of the vital

commissioning activities for such units will have to take place at location and cannot be completed during the

i f h i H k i i ll i l d d i h l b if f d i i f h

Page 10: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 10/58

  Recommended Practice DNV-RP-A205, March 2012

Sec.4. Commissioning Procedures – Page 10

Figure 4-1Typical content for a system commissioning procedure

SYSTEM COMMISSIONING PROCEDURE

1 SYSTEM DESCRIPTION1.1 Commissioning Package1.2 System Integration Description1.3 Pre-requisites

2 OBJECTIVE

3 GENERAL

3.1 Safety requirements and precautions3.2 Regulatory and project specific requirements

3.3 Participants (e.g. Owner / Vendor / Class Representative / Builder)3.4 Kick-off meeting3.5 Special / Temporary Tools / Equipment, Spare & Consumables3.6 Traceability of documents & records3.7 Punch list system

4 PRE-COMMISSIONING 4.1 Each package listed

5 OPERATIONAL MULTI-DISCIPLINE COMMISSIONING

5.1 Detailed test procedure with acceptance criteria

APPENDIXES

I.  Equipment Data Sheet / InformationII.  Commissioning Test Results / Running LogsIII.  Single Line Diagram / Block DiagramIV.  P & ID 

INTEGRATION TEST PROCEDURE

1 SYSTEM DESCRIPTION

1.1 Commissioning Package1.2 System Integration Description1.3 Pre-requisites

2 OBJECTIVE

3 GENERAL

3.1 Safety Requirements and precautions3.2 Sequence of Events3.3 Participants (e.g. Owner / Vendor / Class Representative / Builder)3 4 Ki k ff ti

Page 11: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 11/58

  Recommended Practice DNV-RP-A205, March 2012

Sec.5. DNV Involvement in Commissioning – Page 11

 — Ad. Item 1.1 Commissioning PackageA generic description of the unit and its systems:

- Marine System xxxx

- Topside – Service System xxxx — Ad item 1.2 System integration testing

The integral system is controlling several systems and their functions from a common operating systemVDU. The Integrated Control and Monitoring (ICMS) system is built for the specified type of vessel whichis a distributed monitoring and control system which, due to its flexibility and modular architecture can beextended to cover a wide range of applications and types of vessels.Integration testing is defined as testing of more than one system, i.e. testing that extends the work 

 performed in a single commissioning procedure and typically involves systems or equipment covered inanother commissioning procedures.

 — Ad item 1.3 Pre-requisitesDescribe the systems required to be completed prior to start activities as listed in this procedure. — Ad item 2.0 Objectives

The objective of an integrated test procedure is to verify the necessary check and pre-requisites areaccordingly carried out and that the system is in accordance with design specification and regulatoryrequirements.

5. DNV Involvement in Commissioning

DNV’s involvement in testing and commissioning is limited to the requirements of statutory and class rules.DNV surveyor will attend testing and commissioning to the extent specified in applicable Quality SurveyProgram (QSP).

Survey scope shall be categorized as follows:

 — Survey Category 1 - Statutory and Essential Systems for Safety (normally increased attendance by DNV). — Survey Category 2 - Main Systems / Functionally Important (For Main and Additional Class Notations,

extent is based on the yard’s experience and the effectiveness of Yard’s QA/QC system). — Survey Category 3 – Normally limited or no attendance required by surveyor.

The tables attached in the following appendices detail the “survey categorization during MechanicalCompletion and Commissioning of Marine and Drilling Systems” (based on Project System / Sub System List).

Drillships Appendix A

Semi-Submersible units Appendix B

Jack Ups Appendix C

FPSO Appendix D

FSO Appendix E

Page 12: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 12/58

  Recommended Practice DNV-RP-A205, March 2012

 App.A DNV Typical Survey Categorization for Drillships during Mechanical Completion and Commissioning of Marine andDrilling Systems – Page 12

APPENDIX ADNV TYPICAL SURVEY CATEGORIZATION FOR DRILLSHIPS DURING

MECHANICAL COMPLETION AND COMMISSIONING OF MARINE ANDDRILLING SYSTEMS

A.1 Category 1 Systems for Commissioning (for Integration)

A.2 Category II Systems for Commissioning (for Integration)

No. Name of the System Integrated with

1 Fire Main System F&G/Deluge/control

2 Inergen System F&G/HVAC/PA

3 Fire Water Deluge System F&G4 Main Diesel Generator PMS&S/T&DP

5 Sea Water Cooling System Consumer Capacity Test

6 Thruster S.W. Cooling System S/T

7 Thruster S/T

8 11Kv Switchboard (or equivalent) PMS

9 690V HPU MCC (or equivalent) SIT

10 690V Drilling VFD Switchboard (or equivalent) SIT

11 690V Thruster VFD Switchboard (or equivalent) DP/PMS12 230V AC UPS (or equivalent) ESD

13 230V AC UPS Battery (or equivalent) ESD

14 230V AC UPS Main Distribution Board (or equivalent) ESD

15 230 AC UPS DB (or equivalent) ESD

16 ICMS, Fire And Gas, ESD & DPWith Sensor And Reference System

ESD/HVAC

17 Telecom System ESD

18 Electrical And Auxiliary Machinery Rooms Ventilation Systems ESD

19 Engine Rooms Ventilation Systems ESD

20 Port/Stbd/Aft Machinery Rooms Ventilation Systems ESD

21 LQ HVAC ESD

22 Power Management System DRILL/DP

23 Dynamic Positioning System Test (DPS) CONTROL

24 Machinery Unmanned Test E0

No. Name of the System Integrated with

1 Ballast System Semi Recovery Test

2 Aux. Cooling F.W. System S/T & SIT

3 460V LV Switchboard S/T

4 230V LV Switchboard S/T

5 PA C M t N l O ti

Page 13: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 13/58

  Recommended Practice DNV-RP-A205, March 2012

 App.A DNV Typical Survey Categorization for Drillships during Mechanical Completion and Commissioning of Marine andDrilling Systems – Page 13

A.3 Category I Systems for Commissioning (as independent systems)

A.4 Category II Systems for Commissioning (as independent systems)

No. Name of the System

1 Lifeboat & Launch System2 Mob Boat Launch Device System

3 Deck Crane

4 Emergency bilge system

5 Emergency Shut Off System (Quick closing valves)

6 Drill Floor Elevator  

7 Escape Chute

8 Watertight Doors

9 Helideck Fire-Fighting System10 Emergency Generator  

11 Emergency Switchboard

12 Cement unit

13 230V AC UPS

14 230V AC UPS Battery

15 230V AC UPS Main Distribution Board

16 230 AC UPS DB

17 Dynamic Positioning System Test (DPS)

No. Name of the System

1 Misc.Lifesaving Equipment

2 Helicopter Refueling System

3 Ballast System

4 Dirty Drain System

5 Fire Main System6 Inergen System

7 Fire Water Deluge System

8 Main Diesel Generator  

9 Steam Generating System

10 Sea Water Cooling System

11 Starting Air System For Main Engine

12 Thruster S.W. Cooling System

13 Sewage & Gray Water Discharge System14 Anchor Winches

15 Thruster

16 Bilge System

17 Diesel Gen. F.W Cooling System

18 11Kv Switchboard (or equivalent)

R d d P ti DNV RP A205 M h 2012

Page 14: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 14/58

  Recommended Practice DNV-RP-A205, March 2012

 App.A DNV Typical Survey Categorization for Drillships during Mechanical Completion and Commissioning of Marine andDrilling Systems – Page 14

34 Tong Lift System

35 LIR / HVAC Room, HVAC

36 DDM-1000-HY-RR/DDM-650-HY-RR (or equivalent)

37 Rotary Table Main/Aux.(Including Power Slips)

38 DAT System

39 Guideline Winch & Tensioner System

40 LP/HP Nitrogen System

41 Mud Bucket

42 Bulk Powder Handling System

43 Mud Storage And Transfer System

44 Mud Mixing And Additive System

45 Mud Supply System

46 Mud Return And Treatment System

47 Mud, Brine, Oil Storage & Transfer System System

48 BOP Package

49 Diverter Package

50 Tubular and Riser Feeding Machine/Shuttle, Main Rig

51 Lower Guiding Arm including Heads and Rail, Main/Aux

52 Trolley For Riser Guiding53 Riser Chute

54 DP/DC, Casing & Riser Fingerboard

55 Direct Lift Bridge Crane DP/DC/CSG, Main Rig/Aux. Rig

56 Hydraulic Roughneck MH 1899

57 Multi Scope Arm(Casing Modem)

58 Hydraulic Cathead, Brake Out, including Wire

59 Tail in Arm

60 Multi Manipulator Arm(DFMA)61 Piperack Gantry Crane

62 Riser Handling Crane (w/ Rail)

63 BOP Skid/X-Mas/ LMRP Transportation/Handling

64 Miscellaneous Guides

65 Access Basket

66 BOP Overhead Crane/X-mas Tree Overhead Crane

67 Overhull Guiding

68 Utility Winch & Manrider Winch69 Burner Boom

70 Ringline HPU And Distribution System

71 Ramrig HPU And Distribution System

72 Dual Derrick Simultaneous Operation

73 Integrated BOP & Riser Handling System

No. Name of the System (Continued)

Recommended Practice DNV RP A205 March 2012

Page 15: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 15/58

  Recommended Practice DNV-RP-A205, March 2012

 App.A DNV Typical Survey Categorization for Drillships during Mechanical Completion and Commissioning of Marine andDrilling Systems – Page 15

A.5 Category III Systems for Commissioning (as independent system)

A.6 Category I Systems for Commissioning (Class NotationCRANE)

Guidance note:

Additional systems based on the choice of additional class notations should be added in addition to the above.

---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e--- 

No. Name of the System

1 Monorail System2 Air Winches & Towing Equipment

3 Drill Water System

4 Deck Bilge System

5 Service Air System

6 Steam & Drain System

7 Seawater Service System

8 Aux. Cooling F.W. System

9 Diesel Oil Transfer & Drain System10 Lub. Oil Storage, Transfer & Drain System

11 Distilled & Make-Up Water System

12 Potable & Sanitary Supply System

13 Cold Starter Generator  

14 MGPS (Marine Growth)

15 Heat Trace System

16 460V LV Switchboard

17 230V LV Switchboard18 Small Power DB

19 Lighting And Small Power  

20 Shore Connection Box

21 Column And Pontoon Machinery Rooms Ventilation Systems

22 Electrical And Auxiliary Machinery Rooms Ventilation Systems

23 Engine Rooms Ventilation Systems

24 Port/Stbd/Aft Machinery Rooms Ventilation Systems

25 HVAC Duck Air Leak Test Procedure for Hull & Topside26 ICCP

27 Pneumatically Operated Door  

28 Provision Cold Store & Freezer System

29 Noise Level Measurement

30 Vibration Level Measurement

31 Helideck Drains

No. Name of the System

1 Deck Crane

Recommended Practice DNV RP A205 March 2012

Page 16: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 16/58

  Recommended Practice DNV-RP-A205, March 2012

 App.B DNV Typical Survey Categorization for Semi-submersible Units during Mechanical Completion and Commissioningof Marine and Drilling Systems – Page 16

APPENDIX BDNV TYPICAL SURVEY CATEGORIZATION FOR SEMI-SUBMERSIBLE

UNITS DURING MECHANICAL COMPLETION AND COMMISSIONING

OF MARINE AND DRILLING SYSTEMS

B.1 Category I Systems for Commissioning (for integration)

B.2 Category II Systems for Commissioning (for integration)

No. Name of the System Integrated with

1 Fire Main System F&G/Deluge/control

2 Inergen System F&G/HVAC/PA

3 Fire Water Deluge System F&G4 Main Diesel Generator PMS&S/T&DP

5 Sea Water Cooling System Consumer Capacity Test

6 Thruster S.W. Cooling System S/T

7 Thruster S/T

8 11Kv Switchboard (or Equivalent) PMS

9 690V HPU MCC (or Equivalent) SIT

10 690V Drilling VFD Switchboard (or Equivalent) SIT

11 690V Thruster VFD Switchboard (or Equivalent) DP/PMS

12 230V AC UPS (or equivalent) ESD

13 230V AC UPS Battery (or equivalent) ESD

14 230V AC UPS Main Distribution Board (or equivalent) ESD

15 230 AC UPS DB (or equivalent) ESD

16 ICMS , Fire And Gas, ESD & DPWith Sensor And Reference System

ESD/HVAC

17 Telecom System ESD

18 Column And Pontoon Machinery Rooms Ventilation Systems ESD

19 Electrical And Auxiliary Machinery Rooms Ventilation Systems ESD

20 Engine Rooms Ventilation Systems ESD

21 Port/Stbd/Aft Machinery Rooms Ventilation Systems ESD

22 LQ HVAC ESD

23 Power Management System DRILL/DP

24 Dynamic Positioning System Test (DPS) CONTROL

25 Machinery Unmanned Test E0

No. Name of the System Integrated with

1 Anchor Winches If Posmoor, TA/ATA

2 PA Coverage Measurement Normal operation

3 Ballast System Semi recovery test

4 A ili C li F h W t S t (#2) S/T & SIT

Recommended Practice DNV-RP-A205 March 2012

Page 17: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 17/58

  Recommended Practice DNV RP A205, March 2012

 App.B DNV Typical Survey Categorization for Semi-submersible Units during Mechanical Completion and Commissioningof Marine and Drilling Systems – Page 17

B.3 Category I Systems for Commissioning (as independent systems)

B.4 Category II Systems for Commissioning (as independent systems)

No. Name of the System

1 Lifeboat & Launch System2 Mob Boat Launch Device System

3 Deck Crane

4 Emergency Bilge System

5 Emergency Shut Off System (Quick closing valves)

6 Drill Floor Elevator  

7 Escape Chute

8 Column Room Elevators

9 Water Tight Doors10 Helideck Fire-Fighting System

11 Inclining Experiment & Light Weight Measurement Procedure

12 Emergency Generator  

13 Emergency SWBD

14 Cement Unit

No. Name of the System1 Misc. Lifesaving Equipment

2 Helicopter Refueling System

3 Dirty Drain System

4 Ballast System

5 Fire Main system

6 Inergen system

7 Fire Water Deluge system

8 Main Diesel Generator  9 Steam Generating System

10 Sea Water Cooling System

11 Starting Air System for Main Engine

12 Thruster S.W. Cooling System

13 Sewage & Gray Water Discharge System

14 Anchor Winches

15 Thrusters

16 Bilge System17 Diesel Generator Fresh Water Cooling System

18 11Kv Switchboard (or equivalent)

19 Navigation and Signal Light

20 690V HPU MCC (or Equivalent)

21 690V Drilling VFD Switchboard (or Equivalent)

Recommended Practice DNV-RP-A205, March 2012

Page 18: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 18/58

  Recommended Practice DNV RP A205, March 2012

 App.B DNV Typical Survey Categorization for Semi-submersible Units during Mechanical Completion and Commissioningof Marine and Drilling Systems – Page 18

37 DAT System

38 Guideline Winch & Tensioner System

39 LP/HP Nitrogen System40 Mud Bucket

41 Bulk Powder Handling System

42 Mud Storage & Transfer System

43 Mud Mixing & Additive System

44 Mud Supply System

45 Mud Return & Treatment System

46 Pontoon Mud, Brine, Oil Storage & Transfer System

47 BOP Package48 Diverter Package

49 Tubular & Riser Feeding Machine/Shuttle, Main Rig

50 Lower Guiding Arm Includes Heads & Rail, Main & Auxiliary

51 Trolley For Riser Guiding

52 Riser Chute

53 DP/DC, Casing & Riser Fingerboard

54 Direct Lift Bridge Crane DP/DC/CSG, Main Rig / Auxiliary Rig

55 Hydraulic Roughneck MH 189956 Multi Scope Arm (Casing Modem)

57 Hydraulic Cathead, Brake Out, Including Wire

58 Tail in Arm

59 Multi Manipulator Arm (DFMA)

60 Piperack Gantry Crane

61 Riser Handling Crane (with Rail)

62 BOP Skid / X-Mas / LMRP Transportation / Handling

63 Miscellaneous Guides64 Access Basket

65 BOP / X-Mas Tree Overhead Crane

66 Underhull Guiding Main / Auxiliary

67 Overhull Guiding

68 Utility Winch & Manrider Winch

69 Burner Boom

70 Ringline HPU & Distribution System

71 Ramrig HPU & Distribution System (or equivalent)72 Dual Derrick Simultaneous Operation (if Fitted)

73 Integrated BOP & Riser Handling System

74 Integrated Drill String Test (Simulated Spud-in Mode)

75 Sludge System

76 Loop Check  

No. Name of the System (Continued)

  Recommended Practice DNV-RP-A205, March 2012

Page 19: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 19/58

,

 App.B DNV Typical Survey Categorization for Semi-submersible Units during Mechanical Completion and Commissioningof Marine and Drilling Systems – Page 19

B.5 Category III Systems for Commissioning (as independent system)

No. Name of the System

1 Monorail System2 Air Winches & Towing Equipment

3 Drill Water System

4 Deck Bilge System

5 Service Air System

6 Steam & Drain System

7 Seawater Service System

8 Aux. Cooling FW system

9 Diesel Oil Transfer & Drain System10 Lub Oil Storage, Transfer & Drain System

11 Distilled & Make-Up Water System

12 Potable & Sanitary Supply System

13 Cold Starter Generator  

14 MGPS (Marine Growth)

15 Heat Trace System

16 460V LV Switchboard (or equivalent)

17 230V LV Switchboard (or Equivalent)

18 Small Power Distribution Boards

19 Lighting and Small Power  

20 Shore Connection Box

21 Column and Pontoon Machinery Rooms Ventilation Systems

22 Electrical and Auxiliary Machinery rooms ventilation systems

23 Engine room ventilation systems

24 Port/ Stbd/Aft machinery rooms ventilation systems

25 HVAC Duct Air Leak Test Procedure for Hull & Topside

26 ICCP

27 Pneumatically Operated Door  

28 Provision Cold Store & Freezer System

29 Noise Level Measurement

30 Vibration Level Measurement

31 Helideck Drains

  Recommended Practice DNV-RP-A205, March 2012

Page 20: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 20/58

 App.C DNV Typical Survey Categorization for “Jack-up” Units during Mechanical Completion and Commissioning of Marineand Drilling Systems – Page 20

APPENDIX CDNV TYPICAL SURVEY CATEGORIZATION FOR “JACK-UP” UNITS

DURING MECHANICAL COMPLETION AND COMMISSIONING OF

MARINE AND DRILLING SYSTEMS

C.1 Category I Systems for Commissioning (for integration)

C.2 Category II Systems for Commissioning (for integration)

No. Name of the System Integrated with

1 Fire Main System F&G/Deluge/control

2 Inergen System F&G/HVAC/PA

3 Fire Water Deluge System F&G

4 Main Diesel Generator PMS&S/T&DP

5 Sea Water Cooling System Consumer Capacity Test

6 11Kv Switchboard PMS

7 690V HPU MCC SIT

8 690V Drilling VFD Switchboard SIT

9 230V AC UPS ESD

10 230V AC UPS Battery ESD

11 230V AC UPS Main Distribution Board ESD

12 230 AC UPS DB ESD

13 ICMS, Fire And Gas and ESDWith Sensor And Reference System

ESD/HVAC

14 Telecom System ESD

15 Electrical And Auxiliary Machinery Rooms Ventilation Systems ESD

16 Engine Rooms Ventilation Systems ESD

17 Port/Stbd/Aft Machinery Rooms Ventilation Systems ESD

18 LQ HVAC ESD

19 Power Management System DRILL/DP

20 Machinery Unmanned Test E0

21 Jacking motors Jacking trial

22 Jacking control system Jacking trial

No. Name of the System Integrated with

1 Fire water lift with submerged pumps

2 PA Coverage Measurement Normal operation

3 Auxiliary Cooling Fresh Water System (#2) S/T & SIT

4 460V LV Switchboard S/T

5 230V LV Switchboard S/T

  Recommended Practice DNV-RP-A205, March 2012

Page 21: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 21/58

 App.C DNV Typical Survey Categorization for “Jack-up” Units during Mechanical Completion and Commissioning of Marineand Drilling Systems – Page 21

C.3 Category I Systems for Commissioning (as independent systems)

C.4 Category II Systems for Commissioning (as independent systems)

No. Name of the System

1 Lifeboat & Launch System2 Mob Boat Launch Device System

3 Deck Crane

4 Emergency Bilge System

5 Emergency Shut Off System (Quick closing valves)

6 Drill Floor Elevator  

7 Escape Chute

8 Water Tight Door  

9 Helideck Fire-Fighting System

10 Inclining Experiment & Light Weight Measurement Procedure

11 Emergency Generator  

12 Emergency SWBD

13 Cement Unit

14 Cantilever  

15 Rack Chocking Device

16 Accommodation Unit Gangway Test

17 230V AC UPS

18 230V AC UPS Battery

19 230V AC UPS Main Distribution Board

20 230 AC UPS DB

No. Name of the System

1 Misc. Lifesaving Equipment

2 Helicopter Refueling System3 Dirty Drain System

4 Fire Main System

5 Inergen System

6 Fire Water Deluge System

7 Main Diesel Generator  

8 Steam Generating System

9 Sea Water Cooling system (including Buffer Tank alarms if Fitted)

10 Starting Air System for Main Engine11 Sewage & Gray Water Discharge System

12 Bilge System

13 Diesel Generator Fresh Water Cooling System

14 11Kv Switchboard or Equivalent

15 690V HPU MCC (or Equivalent)

  Recommended Practice DNV-RP-A205, March 2012

A C DNV T i l S C t i ti f “J k ” U it d i M h i l C l ti d C i i i f M i

Page 22: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 22/58

 App.C DNV Typical Survey Categorization for “Jack-up” Units during Mechanical Completion and Commissioning of Marineand Drilling Systems – Page 22

31 Bulk Powder Handling System

32 Mud Storage & Transfer System

33 Mud Mixing & Additive System34 Mud Supply System

35 Mud Return & Treatment System

36 Mud, Brine, Oil Storage & Transfer System

37 BOP Package

38 Diverter Package

39 Lower Guiding Arm Includes Heads & Rail, Main & Auxiliary

40 Direct Lift Bridge Crane DP/DC/CSG, Main Rig / Auxiliary Rig

41 Hydraulic Roughneck MH 189942 Multi Scope Arm (Casing Modem)

43 Hydraulic Cathead, Brake Out, Including Wire

44 Tail in Arm

45 Multi Manipulator Arm (DFMA)

46 Piperack Gantry Crane

47 BOP Skid / X-Mas / Transportation / Handling

48 Miscellaneous Guides

49 Access Basket50 BOP / X-Mas Tree Overhead Crane

51 Utility Winch & Manrider Winch

52 Burner Boom

53 Ringline HPU & Distribution System

54 Ramrig HPU & Distribution System

55 Dual Derrick Simultaneous Operation

56 Integrated Drill String Test (Simulated Spud-in Mode)

57 Sludge System58 Loop Check  

59 Smart Zone System

60 Drilling Control

61 Mud & Cement Manifolds

62 Navigation Equipment

63 Anchor Test (if fitted for temp and emergency mooring)

64 Ballast System/ Pre Load System

65 Spud can HP water injection

No. Name of the System (Continued)

  Recommended Practice DNV-RP-A205, March 2012

App C DNV Typical Survey Categorization for “Jack up” Units during Mechanical Completion and Commissioning of Marine

Page 23: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 23/58

 App.C DNV Typical Survey Categorization for Jack-up Units during Mechanical Completion and Commissioning of Marineand Drilling Systems – Page 23

C.5 Category III Systems for Commissioning (as independent system)

No. Name of the System

1 Monorail System

2 Air Winches & Towing Equipment

3 Drill Water System

4 Deck Bilge System

5 Service Air System

6 Steam & Drain System

7 Seawater Service System

8 Diesel Oil Transfer & Drain System

9 Lube Oil Storage, Transfer & Drain System

10 Distilled & Make-Up Water System

11 Potable & Sanitary Supply System

12 Cold Starter Generator  

13 MGPS (Marine Growth) (if fitted for spud cans)

14 Heat Trace System

15 Small Power DB

16 Lighting and Small Power  

17 Shore Connection Box

18 HVAC Duct Air Leak Test Procedure for Hull & Topside

19 Pneumatically Operated Door  

20 Provision Cold Store & Freezer System

21 Noise Level Measurement

22 Vibration Level Measurement

23 Helideck Drains

  Recommended Practice DNV-RP-A205, March 2012

App D DNV Typical Survey Categorization for FPSO Units during Mechanical Completion and Commissioning of Marine

Page 24: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 24/58

 App.D DNV Typical Survey Categorization for FPSO Units during Mechanical Completion and Commissioning of Marineand Production Systems – Page 24

APPENDIX DDNV TYPICAL SURVEY CATEGORIZATION FOR FPSO UNITS DURING

MECHANICAL COMPLETION AND COMMISSIONING OF MARINE AND

PRODUCTION SYSTEMS

(Pending)

  Recommended Practice DNV-RP-A205, March 2012

App.E DNV Typical Survey Categorization for FSO Units during Mechanical Completion and Commissioning of Marine and

Page 25: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 25/58

 App.E DNV Typical Survey Categorization for FSO Units during Mechanical Completion and Commissioning of Marine andProduction Systems – Page 25

APPENDIX EDNV TYPICAL SURVEY CATEGORIZATION FOR FSO UNITS DURING

MECHANICAL COMPLETION AND COMMISSIONING OF MARINE AND

PRODUCTION SYSTEMS

(Pending)

Page 26: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 26/58

Page 27: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 27/58

Page 28: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 28/58

Page 29: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 29/58

Page 30: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 30/58

Page 31: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 31/58

Page 32: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 32/58

 

R e c  omm en d  e d P r  a c  t  i   c  eDNV -RP -A 2  0  5  ,M ar  c h 2 

 0 1 2 

A  p

 p.F DNV R e q ui  r  em en t   s R el   a t   e d  t   oM ar i  n e , U t  i  l  i   t   y  an d  S  af   e t   y  S  y  s  t   em s 

P  a g e

 3 2 

DE T  N OR S KE  VE R

I  T A S A S 

Use of Gas andCrude Oil forAuxiliary Boilers andTurbines

DNV-OS-D101Ch.2 Sec.4L311

 — Confirm the following fault conditions shall release alarm and automatic shutdown of gas and crude oil supply:

- Detected gas of maximum 20% of the lower explosive limit (LEL) in the ventilated duct. For crude oil fired units, detection of liquid

at all low points in the ventilated duct may be accepted as an alternative;- Detected gas of maximum 20% of the LEL in engine and boiler room. This requirement may be dispensed with if the ducting hasno opening (e.g. hood) into the machinery space;

- Loss of ventilation in the duct;- Abnormal pressure variation in the fuel supply line;- Detected fire in the engine and boiler room.

General MarineEquipment

DNV-OS-D101Ch.2 Sec.5B200

 — Confirm that a space is pressurized to make it non-hazardous, and is provided the following minimum requirements:

- Pressurization air is taken from a safe area;- An alarm system is fitted to indicate loss of air pressure;- An air-lock system with self-closing doors are fitted;

- An exhaust outlet is located in a non-hazardous area;- A combustion air inlet is located in a non-hazardous area.

 — Automatic shutdown is arranged to prevent overspeeding in the event of ingestion of flammable gas.

Jacking GearMachinery

DNV-OS-D101Ch.2 Sec.5C1100

 — Confirm that the following control and monitoring arrangements are present:

- Remote indication and alarm if a brake is not released when power applied to the motors. The brake alarm shall be given by anindependent mechanical sensor;

- Remote indication and alarm for overheating of an electric motor;- A permanent remote indication of loads during jacking and retrieval is provided. For a lattice leg unit, the load per chord is as a

minimum to be presented. Confirm that an alarm signal is given when the maximum load is exceeded.

DNV-OS-D101Ch.2 Sec.5C1200

 — Confirm that a spin test and contact pattern test is carried out according to accepted methods.

DNV-OS-D101Ch.2 Sec.5C1400

 — Confirm that jacking machinery is tested with the highest specified lifting and descending load. The duration shall reflect one operatingcycle.

 — Confirm that the interlock is tested.

System / EquipmentDescription

DNV OS /Rule Reference

DNV Surveillance Focus (Continued)

Page 33: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 33/58

Page 34: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 34/58

Page 35: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 35/58

Page 36: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 36/58

Page 37: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 37/58

Page 38: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 38/58

Page 39: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 39/58

Page 40: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 40/58

Page 41: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 41/58

 

S t / E i t DNV OS / DNV S ill F (C ti d)

Page 42: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 42/58

R e c  omm en d  e d P r  a c  t  i   c  e

DNV -RP -A 2  0  5  ,M ar  c h 2  0 

1 2 

A  p p.F DNV R e q ui  r  em en t   s R e

l   a t   e d  t   oM ar i  n e , U t  i  l  i   t   y  an d 

 S  af   e t   y  S  y  s  t   em s 

P  a g e

4 2 

DE T  N OR S KE  VE RI  T A S A S 

Electric Propulsion(Continued)

DNV-OS-D201Ch.2 Sec.12A600

(Continued)

 — Fuses for filter units or for other components where fuse failures are not evident. — Confirm that a temperature indicator for directly reading the temperature of the stator windings of generators and propulsion motors

is located in the control room.

 — Confirm that the following values are displayed in the control room or on the applicable converter:- Stator current in each motor;- Field current in each motor (if applicable).

 — Confirm the following values are displayed in the control room for each generator: A power factor meter or kVAr meter. — Confirm that instruments are provided for indication of consumed power and power available for propulsion on the bridge and in the

control room. — Confirm at each propulsion control stand, indications, based on feedback signals, are provided for pitch or direction of rotation, speed,

and azimuth, if applicable. — Confirm indications as listed for control stands, are arranged in the engine control room, even if no control means are provided.

DNV-OS-D201Ch. 2 Sec. 12B100

 — Upon completion as well as satisfactory tests of all subsystems, the electric propulsion system shall be confirmed during sea trial wherethe propulsion plant shall be tested in normal and abnormal conditions.

 — Confirm that start-up and stop sequences as controlled by the power management system, when relevant. — Confirm safety functions, alarms and indicators. — Confirm all control modes from all control locations. — Confirm required level of redundancy by verification through tests.

System / EquipmentDescription

DNV OS /Rule Reference

DNV Surveillance Focus (Continued)

Page 43: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 43/58

Page 44: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 44/58

 

System / Equipment DNV OS / DNV Surveillance Focus (Continued)

Page 45: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 45/58

R e c  omm en d  e d P r  a c  t  i   c  e

DNV -RP -A 2  0  5  ,M ar  c h 2  0 

1 2 

A  p p.F DNV R e q ui  r  em en t   s R e

l   a t   e d  t   oM ar i  n e , U t  i  l  i   t   y  an d 

 S  af   e t   y  S  y  s  t   em s 

P  a g e

4  5 

DE T  N OR S KE  VE RI  T A S A S 

On-board Testing(Continued)

DNV-OS-D202Ch.2 Sec.6F100

 — Drilling Unit / Production and Storage Unit

- Confirm back-up means of operation contains the most important action functions and alarm indications related to emergencyrelocation (if required), gas detection, including activation of active fire protection devices;

- This will typically include release of foam systems and indication of foam system status, if applicable; gas detection statusindication (flammable and toxic); facilities for emergency relocation, if applicable; activation of BOP release sequence (normallylocated in BOP control panel).

DNV-OS-D202Ch.2 Sec.7B100

 — Production and Storage Unit

- Confirm power to the relevant parts of the safety system is not be tripped by the emergency shutdown (ESD) system.

System / EquipmentDescription

DNV OS /Rule Reference

DNV Surveillance Focus (Continued)

Page 46: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 46/58

Page 47: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 47/58

 

System / Equipment DNV OS / DNV Surveillance Focus (Continued)

Page 48: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 48/58

R e c  omm en d  e d P r  a c  t  i   c  e

DNV -RP -A 2  0  5  ,M ar  c h 2  0 

1 2 

A  p p

.F DNV R e q ui  r  em en t   s R el   a t   e d  t   oM ar i  n e , U t  i  l  i   t   y  an d 

 S  af   e t   y  S  y  s  t   em s 

P  a g e

4  8 

DE T  N OR S KE  VE RI  

T A S A S 

Fire Protection – LNG Import andExport Terminals

and Production Units(Continued)

DNV-OS-D301Ch.2 Sec.8D100

 — Confirm that fixed fire fighting systems, including deluge valve and fire water distribution pipework, provide effective fire water protection within 20 seconds of the demand.

 — Confirm the deluge valve system is activated by a signal from the fire and gas detection system and has a local energy source for the

valve actuator.DNV-OS-D301Ch.2 Sec.8G100

 — Confirm that fire detection in areas containing gas and LNG processing facilities results in an automatic shut-down of hydrocarbonflow and ventilation for the area.

 — Confirm automatic shutdown of ventilation upon detection of fire in enclosed spaces or smoke detection in ventilation air inlets. — Confirm that fire detection in the wellhead, turret, oil production or crude oil tank areas initiates an automatic shutdown of wellhead

valves and oil production facilities.

DNV-OS-D301Ch.2 Sec.8H100

 — Confirm that gas detection results in an automatic shutdown all hydrocarbon flow. — Confirm that a gas concentration of 25% lower explosion limit (LEL) in the air results in an automatic shutdown of all air inlets to

non-hazardous areas. — Confirm 60% LEL gas detection in the area of wellhead, turret, production facilities and storage tanks result in the wellhead valves

and production facilities shutdown.DNV Ship RulesPt.5 Ch.3 Sec.9F and G

 — Confirm that gas detection not higher than 10% LEL in product pump rooms and double hull spaces on floating installations resultsin an audible and visual alarm signal which is automatically initiated in the pump-room, engine control room and navigation bridge,to alert personnel to the potential hazard.

 — For ships with inert gas systems, confirm that two instruments for measuring O2-content, two instruments for measuring hydrocarboncontent in the range of 0 to 20% hydrocarbon gas by volume and two instruments for measuring low hydrocarbon gas content 0 to100% LEL are present. Confirm that alarms (visual and audible) on the bridge and in the cargo control room are triggered if safe levelsare exceeded.

 — For ships without inert gas system, confirm that two instruments for measuring low hydrocarbon gas content 0 to 100% LEL are provided and that alarms (visual and audible) on the bridge and in the cargo control room are triggered if safe levels are exceeded.

Description Rule Reference

Page 49: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 49/58

Page 50: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 50/58

 

System / EquipmentDescription

DNV OS /Rule Reference

DNV Surveillance Focus (Continued)

Page 51: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 51/58

R e c  omm en d  e d P r  a c  t  i   c  e

DNV -RP -A 2  0  5  ,M ar  c h 2  0 1 2 

A  p p

.F DNV R e q ui  r  em en t   s R el   a t   e d  t   oM ar i  n e , U t  i  l  i   t   y  an d 

 S  af   e t   y  S  y  s  t   em s 

P  a g e

 5 1 

DE T  N OR S KE  VE RI  T A S A S 

Other Installationsfor Boil-off GasHandling

(Continued)

DNV Ship RulesPt.6 Ch.3 Sec.5C300

 — Confirm the flame fault detection system by closing fuel supply to burner while in operation. — With burners in operation, confirm the automatic shutoff valve for fuel oil by shielding the flame detector. — With boiler in operation, confirm automatic stop of the combustion air fan.

 — Confirm that fuel oil supply is shut off after reducing water level below safety limit. — Confirm remaining boiler alarms and safety actions by simulating failures as realistically as practicable.

Dynamic Positioning DNV Ship RulesPt.6 Ch.7 Sec.1E100

 — Confirm power systems and thruster systems have been completed as per main class test requirement and no major pending issuesremaining before commencing any dynamic positioning (DP) test activity.

- Main class test requirements will at least include:- Load test according to main class;- Transfer of thruster control;- Manual override of thruster control;- Emergency stop;- Communication systems;

- Main alarm system as for main class and E0 (if applicable);- Integrated automation systems (if applicable).

DNV Ship RulesPt.6 Ch.7 Sec.1E600

 — Confirm dynamic positioning (DP) functional test as per approved test programme. — Confirm DP duration test for at least eight (8) hours with the complete automatic system in operation. — Confirm DP failure modes and effects analysis (FMEA) as per approved test programme.

Description Rule Reference

Page 52: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 52/58

Page 53: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 53/58

Page 54: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 54/58

Page 55: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 55/58

Page 56: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 56/58

Page 57: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 57/58

Page 58: DNV RP A205 Offshore Commissioning

8/20/2019 DNV RP A205 Offshore Commissioning

http://slidepdf.com/reader/full/dnv-rp-a205-offshore-commissioning 58/58