DAFTAR HARGA SATUAN PEKERJAAN WINNER T. F KEGIATAN : PROYEK PEMBANGUNAN RUMAH 20307046 PEKERJAAN : KONSTRUKSI RUMAH 3 TB 01 LOKASI : JAKARTA TAHUN ANGGARAN : 2008 NO URAIAN PEKERJAAN SATUAN INDEKS BAHAN DAN UPAH (Rp) JUMLAH (Rp) I PEKERJAAN PERSIAPAN 1 PEMBERSIHAN LAHAN Pekerja 10m² 0.75 55,798.00 41,848.50 Mandor 10m² 0.025 85,607.00 2,140.18 TOTAL 43,988.68 2 PEMASANGAN BOUWPLANK Papan dan Pancang m 0.01 8,050,000.00 80,500.00 Paku m 0.1 15,000.00 1,500.00 Tukang Kayu m 0.8 65,734.00 52,587.20 Kepala Tukang Kayu m 0.08 75,671.00 6,053.68 Pekerja m 0.28 55,798.00 15,623.44 Mandor m 0.014 85,607.00 1,198.50 TOTAL 157,462.82 3 GALIAN TANAH U/ PONDASI Pekerja 0.75 55,798.00 41,848.50 Mandor 0.025 85,607.00 2,140.18 TOTAL 43,988.68 4 URUGAN PASIR BWH PONDASI Pasir 1.2 180,000.00 216,000.00 Pekerja 0.3 55,798.00 16,739.40 Mandor 0.01 85,607.00 856.07

description

Unit Price Work

Transcript of Daftar Harga Satuan Pekerjaan

DAFTAR HARGA SATUAN PEKERJAAN

DAFTAR HARGA SATUAN PEKERJAANWINNER T. F

KEGIATAN : PROYEK PEMBANGUNAN RUMAH20307046

PEKERJAAN : KONSTRUKSI RUMAH3 TB 01

LOKASI : JAKARTA

TAHUN ANGGARAN : 2008

NOURAIAN PEKERJAANSATUANINDEKSBAHAN DAN UPAH (Rp)JUMLAH (Rp)

IPEKERJAAN PERSIAPAN

1PEMBERSIHAN LAHAN

Pekerja10m0.7555,798.0041,848.50

Mandor10m0.02585,607.002,140.18

TOTAL43,988.68

2PEMASANGAN BOUWPLANK

Papan dan Pancangm0.018,050,000.0080,500.00

Pakum0.115,000.001,500.00

Tukang Kayum0.865,734.0052,587.20

Kepala Tukang Kayum0.0875,671.006,053.68

Pekerjam0.2855,798.0015,623.44

Mandorm0.01485,607.001,198.50

TOTAL157,462.82

3GALIAN TANAH U/ PONDASI

Pekerjam0.7555,798.0041,848.50

Mandorm0.02585,607.002,140.18

TOTAL43,988.68

4URUGAN PASIR BWH PONDASI

Pasirm1.2180,000.00216,000.00

Pekerjam0.355,798.0016,739.40

Mandorm0.0185,607.00856.07

TOTAL233,595.47

5URUGAN PASIR BWH LANTAI

Pasirm1.2180,000.00216,000.00

Pekerjam0.355,798.0016,739.40

Mandorm0.0185,607.00856.07

TOTAL233,595.47

6URUGAN TANAH KEMBALI SISI PONDASI

Pekerjam0.7555,798.0041,848.50

Mandorm0.02585,607.002,140.18

TOTAL43,988.68

7URUGAN TANAH PENINGGIAN LANTAI

Pekerjam0.7555,798.0041,848.50

Mandorm0.02585,607.002,140.18

TOTAL43,988.68

NOURAIAN PEKERJAANSATUANINDEKSBAHAN DAN UPAH (Rp)JUMLAH (Rp)

IIPEKERJAAN PONDASI

1PONDASI BATU KALI

Batu Kalim1.2160,000.00192,000.00

Semenm4.2652,000.00221,520.00

Pasir Pasangm0.34160,000.0054,400.00

Tukang Batum0.665,734.0039,440.40

Kepala Tukang Batum0.0675,671.004,540.26

Pekerjam1.555,798.0083,697.00

Mandorm0.01585,607.001,284.11

TOTAL596,881.77

IIIPEKERJAAN BETON

1SLOOF BETON

Upah Pembesianm0.751,095,000.00821,250.00

Kepala tukang batum0.03975,671.002,951.17

Pekerja m0.78155,798.0043,578.24

Mandorm0.07885,607.006,677.35

TOTAL874,456.75

2KOLOM BETON

Upah Pembesianm0.751,095,000.00821,250.00

Kepala tukang batum0.03975,671.002,951.17

Pekerja m0.78155,798.0043,578.24

Mandorm0.07885,607.006,677.35

TOTAL874,456.75

3RING BALK BETON

Upah Pembesianm0.751,095,000.00821,250.00

Kepala tukang batum0.03975,671.002,951.17

Pekerja m0.78155,798.0043,578.24

Mandorm0.07885,607.006,677.35

TOTAL874,456.75

4MEJA DAPUR

Semenm8.552,000.00442,000.00

Pasir betonm0.54160,000.0086,400.00

Kerikilm0.82260,000.00213,200.00

Tukang batum165,734.0065,734.00

Pekerjam355,798.00167,394.00

Mandorm0.185,607.008,560.70

TOTAL983,288.70

5LIST PLANK

Semenm8.552,000.00442,000.00

Pasir betonm0.54160,000.0086,400.00

Kerikilm0.82260,000.00213,200.00

Tukang batum165,734.0065,734.00

Pekerjam355,798.00167,394.00

Mandorm0.185,607.008,560.70

TOTAL983,288.70

NOURAIAN PEKERJAANSATUANINDEKSBAHAN DAN UPAH (Rp)JUMLAH (Rp)

6TOPI TERAS

Semenm8.552,000.00442,000.00

Pasir betonm0.54160,000.0086,400.00

Kerikilm0.82260,000.00213,200.00

Tukang batum165,734.0065,734.00

Pekerjam355,798.00167,394.00

Mandorm0.185,607.008,560.70

TOTAL983,288.70

7LANTAI KERJA

Semenm8.552,000.00442,000.00

Pasir betonm0.54160,000.0086,400.00

Kerikilm0.82260,000.00213,200.00

Tukang batum165,734.0065,734.00

Pekerjam355,798.00167,394.00

Mandorm0.185,607.008,560.70

TOTAL983,288.70

IVPEKERJAAN PASANGAN DINDING DAN PLESTERAN

1PASANGAN DINDING BATA MERAH ( 1:2 )

Batu bata merahm80260.0020,800.00

Semenm0.5235,100.0018,252.00

Pasir pasangm0.042169,000.007,098.00

Tukang batum0.1665,734.0010,517.44

Kepala T. Batum0.01675,671.001,210.74

Pekerjam0.4855,798.0026,783.04

Mandorm0.04885,607.004,109.14

TOTAL88,770.35

2PASANGAN BATU ROLLAG ( 1:4 )

Batu bata merahm475260.00123,500.00

Semenm2.435,100.0084,240.00

Pasir pasangm0.416169,000.0070,304.00

Tukang batum1.565,734.0098,601.00

Kepala T. Batum0.1575,671.0011,350.65

Pekerjam355,798.00167,394.00

Mandorm0.1585,607.0012,841.05

TOTAL568,230.70

3PLESTERAN DAN ACI ( 1:2, TEBAL 15 mm )

Semenm0.236835,100.008,311.68

Pasir pasangm0.019169,000.003,211.00

Tukang batum0.21465,734.0014,067.08

Kepala T. Batum0.02175,671.001,589.09

Pekerjam0.455,798.0022,319.20

Mandorm0.0285,607.001,712.14

TOTAL51,210.19

NOURAIAN PEKERJAANSATUANINDEKSBAHAN DAN UPAH (Rp)JUMLAH (Rp)

VPEKERJAAN LANTAI DAN DINDING

1LANTAI KERAMIK ( 30X30 CM )

Ubin keramik 30x30m1.05150,000.00157,500.00

Pasir pasangm0.03169,000.005,070.00

Semenm0.235,100.007,020.00

Semen warnam0.072,210.00154.70

Tukang batum0.465,734.0026,293.60

Kepala T. Batum0.07575,671.005,675.33

Pekerjam0.255,798.0011,159.60

Mandorm0.0285,607.001,712.14

TOTAL214,585.37

LANTAI KERAMIK ( 20X20 CM)

Ubin keramik 20x20m1.0570,000.0073,500.00

Pasir pasangm0.03169,000.005,070.00

Semenm0.235,100.007,020.00

Semen warnam0.12,210.00221.00

Tukang batum0.465,734.0026,293.60

Kepala T. Batum0.07575,671.005,675.33

Pekerjam0.255,798.0011,159.60

Mandorm0.0285,607.001,712.14

TOTAL130,651.67

2DINDING KERAMIK ( 20X25 CM )

Ubin keramik 20x25m1.0570,000.0073,500.00

Pasir pasangm0.03169,000.005,070.00

Semenm0.235,100.007,020.00

Semen warnam12,210.002,210.00

Tukang batum0.565,734.0032,867.00

Kepala T. Batum0.175,671.007,567.10

Pekerjam0.2555,798.0013,949.50

Mandorm0.02585,607.002,140.18

TOTAL144,323.78

3PLIN KERAMIK

Plin keramikm1.0117,500.0017,675.00

Semenm0.02535,100.00877.50

Pasir pasangm0.03169,000.005,070.00

Tukang batum0.165,374.006,537.40

Kepala T. Batum0.0175,671.00756.71

Pekerjam0.1555,798.008,369.70

Mandorm0.0185,607.00856.07

TOTAL40,142.38

VIPEKERJAAN ATAP

1KUDA-KUDA ATAP RUMAH

Balok kayu bengkirai m 1.100 8,050,000.00 8,855,000.00

Paku kg 3.000 8,000.00 24,000.00

Besi strip kg 15.000 8,900.00 133,500.00

Tukang Kayu org/hr 15.000 65,374.00980,610.00

Kepala Tukang Kayu org/hr 1.500 75,671.00113,506.50

Pekerja org/hr 5.000 55,798.00278,990.00

Mandor org/hr 0.250 85,607.0021,401.75

10,407,008.25

2GORDING KAYU

Balok kayu bengkirai m 1.1000 8,050,000.00 8,855,000.00

Paku kg 2.900 8,000.00 23,200.00

Tukang Kayu org/hr 4.5000 65,374.00294,183.00

Kepala Tukang Kayu org/hr 0.4500 75,671.0034,051.95

Pekerja org/hr 1.5000 55,798.0083,697.00

Mandor org/hr 0.0750 85,607.006,420.53

9,296,552.48

3KASO DAN RENG

Kaso m 0.0120 6,900,000.00 82,800.00

Reng m 0.0053 6,900,000.00 36,570.00

Paku Rata-rata kg 0.1500 8,000.00 1,200.00

Tukang Kayu org/hr 0.1000 65,374.006,537.40

Kepala Tukang Kayu org/hr 0.0100 75,671.00756.71

Pekerja org/hr 0.1000 55,798.005,579.80

Mandor org/hr 0.0050 85,607.00428.04

133,871.95

4LISTPLANK KAYU 3/20

Papan kayu Samarinda m 0.0070 9,430,000.00 66,010.00

Paku Rata-rata kg 0.0500 8,000.00 400.00

Tukang Kayu org/hr 0.2000 65,374.0013,074.80

Kepala Tukang Kayu org/hr 0.0200 75,671.001,513.42

Pekerja org/hr 0.1000 55,798.005,579.80

Mandor org/hr 0.0050 85,607.00428.04

87,006.06

5 PASANG ATAP GENTENG PRESS BETON

Genteng Press Beton bh 11.100 3,300.00 36,630.00

Tukang Batu org/hr 0.100 65,374.006,537.40

Kepala Tukang Batu org/hr 0.010 75,671.00756.71

Pekerja org/hr 0.200 55,798.0011,159.60

Mandor org/hr 0.010 85,607.00856.07

55,939.78

6 PASANG NOK GENTENG PRESS BETON

Nok Genteng Press Beton bh 4.040 4,000.00 16,160.00

Semen zak 0.216 35,100.00 7,581.60

Pasir Beton m 0.032 130,000.00 4,160.00

Papan Ruiter Kamper m 0.003 6,900,000.00 20,700.00

Tukang Batu org/hr 0.200 65,374.0013,074.80

Kepala Tukang Batu org/hr 0.020 75,671.001,513.42

Pekerja org/hr 0.400 55,798.0022,319.20

Mandor org/hr 0.020 85,607.001,712.14

87,221.16

7 Pekerjaan Talang Datar Seng 0,3 mm + Alas Papan, tebal 2 Cm

Papan Kamper 2/20 m 0.008 6,900,000.00 55,200.00

Kaso m 0.002 6,900,000.00 16,560.00

Seng plat tebal 0,3 mm m' 1.050 20,000.00 21,000.00

Paku Rata-rata kg 0.150 8,000.00 1,200.00

Paku Seng kg 0.150 10,000.00 1,500.00

Timah kg 0.100 1,500.00 150.00

Tukang Besi org/hr 0.200 65,374.0013,074.80

Tukang Kayu org/hr 0.150 65,374.009,806.10

Kepala Tukang Besi org/hr 0.020 75,671.001,513.42

Pekerja org/hr 0.200 55,798.0011,159.60

Mandor org/hr 0.010 85,607.00856.07

132,019.99

VIIPEKERJAAN PLAFOND

1 Plafond Eternit/Asbes Ukuran eternit 60x120x0,5 cm

Eternit/asbes plat 60x120 lbr 1.400 27,600.00 38,640.00

Paku Rata-rata kg 0.030 8,000.00 240.00

Tukang Kayu org/hr 0.160 65,374.0010,459.84

Kepala Tukang Kayu org/hr 0.016 75,671.001,210.74

Pekerja org/hr 0.112 55,798.006,249.38

Mandor org/hr 0.006 85,607.00513.64

57,313.59

2 Rangka Plafond Kayu (Grid 60 x 60 Cm)

Balok kayu bengkirai m 0.005 8,050,000.00 40,250.00

Kaso Kayu m 0.020 6,900,000.00 138,000.00

Paku Rata-rata kg 0.200 8,000.00 1,600.00

Tukang Kayu org/hr 0.400 65,374.0026,149.60

Kepala Tukang Kayu org/hr 0.040 75,671.003,026.84

Pekerja org/hr 0.280 55,798.0015,623.44

Mandor org/hr 0.014 85,607.001,198.50

225,848.38

VIIIPEKERJAAN KUSEN, PINTU, JENDELA

1 Pekerjaan Kaca (tebal < 10 mm)

Kaca polos m 1.100 5,000.00 5,500.00

Tukang Kayu org/hr 0.240 65,374.0015,689.76

Kepala Tukang Kayu org/hr 0.024 75,671.001,816.10

Pekerja org/hr 0.080 55,798.004,463.84

Mandor org/hr 0.004 85,607.00342.43

27,812.13

2 Daun Pintu/ Jendela Jalusi/ Krepyak (Kayu Kamper, tebal 3,5 cm)

Papan kayu Samarinda m 0.064 9,430,000.00 603,520.00

Paku rata-rata kg 0.200 8,000.00 1,600.00

Lem kayu kg 0.300 8,000.00 2,400.00

List kayu m' 4.000 27,600.00 110,400.00

Tukang Kayu org/hr 5.4000 65,374.00353,019.60

Kepala Tukang Kayu org/hr 0.5400 75,671.0040,862.34

Pekerja org/hr 1.8000 55,798.00100,436.40

Mandor org/hr 0.0900 85,607.007,704.63

1,219,942.97

IXPEKERJAAN CAT

1 Cat Kayu (2 Lapis)

Termasuk Pekerjaan : Plamur, mengamplas

Plamur Kayu kg 0.150 9,750.00 1,462.50

Amplas lbr 0.500 2,000.00 1,000.00

Cat dasar kg 0.150 8,000.00 1,200.00

Cat Kayu kg 0.300 20,000.00 6,000.00

Thinner ltr 0.150 8,000.00 1,200.00

Kuas bh 0.050 6,500.00 325.00

Tukang Cat org/hr 0.250 65,374.0016,343.50

Kepala Tukang Cat org/hr 0.025 75,671.001,891.78

Pekerja org/hr 0.200 55,798.0011,159.60

Mandor org/hr 0.010 85,607.00856.07

41,438.45

2 Cat Dinding Interior (Dinding Baru, 3 Lapis)

Plamur Tembok kg 0.200 9,750.001,950.00

Amplas lbr 0.500 2,000.001,000.00

Cat dasar kg 0.100 50,000.005,000.00

Cat Tembok kg 0.200 50,000.0010,000.00

Kuas roll bh 0.015 9,000.00135.00

Tukang Cat org/hr 0.250 65,374.0016,343.50

Kepala Tukang Cat org/hr 0.025 75,671.001,891.78

Pekerja org/hr 0.200 55,798.0011,159.60

Mandor org/hr 0.010 85,607.00856.07

48,335.95

3 Cat Dinding Exterior (Dinding Baru, 3 Lapis) ICI

Alkali ICI sebelum pengecatan kg 0.125 50,000.00 6,250.00

Cat tembok ICI Wheathershield kg 0.200 20,000.00 4,000.00

Amplas lbr 0.500 2,000.00 1,000.00

Kuas roll bh 0.015 9,000.00 135.00

Tukang Cat org/hr 0.280 65,374.0018,304.72

Kepala Tukang Cat org/hr 0.030 75,671.002,270.13

Pekerja org/hr 0.160 55,798.008,927.68

Mandor org/hr 0.010 85,607.00856.07

41,743.60