  • RENCANA ANGGARAN BIAYA

  • REKAPITULASI RENCANA ANGGARAN BIAYA

  • REKAPITULASI RENCANA ANGGARAN BIAYA

    JENIS PEKERJAAN HARGA PEKERJAAN

    I. PEKERJAAN PONDASI Rp 99,650,647.21

    II. PEKERJAAN BETON Rp #NAME?

    III. PEKERJAAN DINDING Rp 105,312,309.78

    III. PEKERJAAN ATAP Rp 61,697,352.40

    IV. PEKERJAAN PLAFOND Rp 35,513,172.00

    V. PEKERJAAN PLASTERAN DAN ACIAN Rp 46,299,760.00

    VI. PEKERJAAN LANTAI Rp 57,325,133.20

    VII. PEKERJAAN PINTU DAN JENDELA Rp 111,546,786.37

    VIII. PEKERJAAN PENGECATAN Rp 31,935,811.44

    IX. PEKERJAAN INTERIOR HPL Rp 18,037,843.20

    X. PEK. INSTALASI LISTRIK DAN SANITASI Rp 129,305,363.20

    XI. PEK. PERLENGKAPAN LUAR Rp #NAME?

    JUMLAH Rp #NAME?

    DIBULATKAN Rp #NAME?

    Terbilang : " Sembilan Ratus Satu Juta Enam Ratus Enam Puluh Ribu Rupiah"

    Yogyakarta, 29 September 2015

    Disusun Oleh

  • kursi, walpaper, lukisan, dan material lepas lainnya.

    Keterangan: Harga di atas belum termasuk pekerjaan vegetasi (rumput, tanaman, pohon), Interior Meja,

  • RENCANA ANGGARAN BIAYA

  • RENCANA ANGGARAN BIAYA (RAB)

    NO URAIAN PEKERJAAN VOLUME SATHARGA SATUAN JUMLAH

    (Rp) (Rp)

    I. PEKERJAAN PONDASI

    1.1. Pekerjaan Persiapan

    1.1.1. Pembersihan Lapangan 200.00 8,000.00 1,600,000.00

    1.1.2. Pemasangan Bouplank/Pengukuran 60.00 79,683.33 4,781,000.00

    1.1.3. Pengadaan Air Kerja 1.00 Ls 8,000,000.00 8,000,000.00

    1.1.4. Pembuatan Gedung Semen dan Alat 15.00 197,700.00 2,965,500.00

    1.1.5.Direksi keet 10.00 197,700.00 1,977,000.00

    Jumlah 19,323,500.00

    Jasa Pelaksanaan + Overhead 4% 772,940.00

    Total Sub Pekerjaan 20,096,440.00

    1.2. Pekerjaan Galian

    1.2.1. Galian Tanah Biasa 1 Meter (kolam) 17.29 20,800.00 359,632.00

    1.2.2. Galian Tanah Biasa 2 Meter 205.34 30,640.00 6,291,740.16

    1.2.3. Galian Tanah Biasa 2.5 Meter 40.00 41,145.00 1,645,800.00

    1.2.4. Urugan Kembali Galian 231.32 13,330.00 3,083,455.61

    1.2.5. Pemadatan Tanah 100.00 26,000.00 2,600,000.00

    Jumlah 13,980,627.77

    Jasa Pelaksanaan + Overhead 4% 559,225.11

    Total Sub Pekerjaan 14,539,852.88

    1.3. Pemasangan Pondasi Batu Kali

    1.3.1. Urugan Pasir Bawah Pondasi 19.97 212,200.00 4,237,209.60

    1.3.2. Pasangan Pondasi Batu Kosong 29.95 M3 319,020.00 9,555,287.04

    1.3.3. Pasangan Pondasi Batu Kali 101.38 480,600.00 48,721,305.60

    Jumlah 62,513,802.24

    Jasa Pelaksanaan + Overhead 4% 2,500,552.09

    Total Sub Pekerjaan 65,014,354.33

    II. PEKERJAAN BETON

    2.1. Beton Bertulang

    2.1.1. Sloof 15 x 25 4.80 #NAME? #NAME?

    2.1.2. Pondasi Plat 5.00 #NAME? #NAME?

    M2

    M2

    M2

    M2

    M3

    M3

    M3

    M3

    M3

    M3

    M3

    M3

    M3

  • 2.1.3. Kolom 15 x 15 5.45 #NAME? #NAME?

    2.1.4. Kolom 15 x 30 6.00 #NAME? #NAME?

    2.1.5. Kolom 15 x 50 1.95 #NAME? #NAME?

    2.1.6. Balok 15 x 20 3.00 #NAME? #NAME?

    2.1.7. Balok 15 x 25 2.70 #NAME? #NAME?

    2.1.8. Balok 15 x 30 2.70 #NAME? #NAME?

    2.1.9. Balok 15 x 40 1.00 #NAME? #NAME?

    2.1.10. Balok 15 x 10 0.50 #NAME? #NAME?

    2.1.11. Balok 15 X 50 0.50 #NAME? #NAME?

    2.1.12. Plat Dag Beton 5.50 #NAME? #NAME?

    2.1.13. Plat Beton Kolam 7.00 #NAME? #NAME?

    2.1.14. Plat Beton Dudukan wastafel kitchen 0.36 #NAME? #NAME?

    2.1.15. Waterproofing 100.00 M2 100,000.00 10,000,000.00

    Jumlah #NAME?

    Jasa Pelaksanaan + Overhead 4% #NAME?

    Total Sub Pekerjaan #NAME?

    III. PEKERJAAN DINDING

    3.1. Dinding

    3.1.1. Pasangan Dinding 1/2 Bata (1:4) 482.55 91,530.00 44,167,801.50

    3.1.2. Pasangan Dinding Batu alam 50x20 (wall treatmen) 32.96 M2 421,800.00 13,902,528.00

    3.1.3. Pasangan Dinding Granite 60x60 127.02 M2 285,455.00 36,257,066.83

    3.1.4. Pasangan Roster 15x30 10.80 M2 422,216.67 4,559,940.00

    3.1.5. Pasangan mozaik 5.00 M2 474,900.00 2,374,500.00

    Jumlah 101,261,836.33

    Jasa Pelaksanaan + Overhead 4% 4,050,473.45

    Total Sub Pekerjaan 105,312,309.78

    IV. PEKERJAAN KAP DAN ATAP

    4.1. Kap dan Rangka Atap

    4.1.3. Pekerjaan Rangka Atap 187.55 141,950.00 26,622,722.50

    4.1.4. Pekerjaan Listplank 3/25 15.00 56,450.00 846,750.00

    4.1.5. Pekerjaan Papan Reuter 3/25 20.00 56,450.00 1,129,000.00

    Jumlah 28,598,472.50

    Jasa Pelaksanaan + Overhead 4% 1,143,938.90

    Total Sub Pekerjaan 29,742,411.40

    M3

    M3

    M3

    M3

    M3

    M3

    M3

    M3

    M3

    M3

    M3

    M3

    M2

    M2

    M1

    M1

  • 4.2. Atap

    4.2.1. Pemasangan Atap 187.55 M2 151,420.00 28,398,821.00

    4.2.2. Pemasangan Perabung 20.00 M3 177,806.00 3,556,120.00

    Jumlah 31,954,941.00

    Jasa Pelaksanaan + Overhead 4% 1,278,197.64

    Total Sub Pekerjaan 33,233,138.64

    V. PEKERJAAN PLAFOND

    5.1. Rangka Plafond

    5.1.1. Rangka Plafon 220.00 M2 84,975.00 18,694,500.00

    Jumlah 18,694,500.00

    Jasa Pelaksanaan + Overhead 4% 747,780.00

    Total Sub Pekerjaan 19,442,280.00

    5.2. Memasang Plafond

    5.2.1. Memasang Plafond Gypsum 220.00 M2 42,180.00 9,279,600.00

    5.2.2. Memasang Lis Plafond 180.00 M1 38,290.00 6,892,200.00

    Jumlah 16,171,800.00

    Jasa Pelaksanaan + Overhead 4% 646,872.00

    Total Sub Pekerjaan 16,818,672.00

    VI. PEKERJAAN PLASTERAN

    6.1. Plasteran

    6.1.1. Plasteran Dinding (1:4) 880.00 M2 34,850.00 30,668,000.00

    6.1.2. Acian 810.00 M2 17,100.00 13,851,000.00

    Jumlah 44,519,000.00

    Jasa Pelaksanaan + Overhead 4% 1,780,760.00

    Total Sub Pekerjaan 46,299,760.00

    VII. PEKERJAAN LANTAI

    7.1. Urugan Bawah Lantai

    7.1.1. Urugan Pasir 20.00 M3 230,200.00 4,604,000.00

    7.1.2. Urugan Tanah 60.00 M3 13,330.00 799,800.00

    Jumlah 5,403,800.00

    Jasa Pelaksanaan + Overhead 4% 216,152.00

    Total Sub Pekerjaan 5,619,952.00

  • 7.2. Pasangan Lantai

    7.2.1. Pasangan Lantai Kramik 40 x 40 76.00 M2 178,449.00 13,562,124.00

    7.2.2. Pasangan Lantai Granit 60 x 60 108.23 M2 261,345.00 28,286,414.73

    7.2.2. Pasangan Lantai Board Decking 9.80 M2 711,935.00 6,975,539.13

    7.2.2. Lantai keramik 15 x 120 3.48 M2 256,449.00 892,442.52

    Jumlah 49,716,520.38

    Jasa Pelaksanaan + Overhead 4% 1,988,660.82

    Total Sub Pekerjaan 51,705,181.20

    VIII. PEKERJAAN PINTU DAN JENDELA

    8.1 Kusen

    3.2.1. Kusen Pintu dan Jendela 1.10 23,511,000.00 25,862,100.00

    3.2.2. Bout-bout/Angker 5.00 Kg 139,510.00 697,550.00

    3.2.3. Kusen Aluminium 75 x 50 mm 33.00 m' 172,305.00 5,686,065.00

    3.2.4. Kusen Aluminium 60 x 40 mm 21.00 m' 172,305.00 3,618,405.00

    3.2.4. Kusen UPVC 5.80 m' 150,305.00 871,769.00

    Jumlah 36,735,889.00

    Jasa Pelaksanaan + Overhead 4% 1,469,435.56

    Total Sub Pekerjaan 38,205,324.56

    8.2 Pintu dan Jendela

    8.1.1. Pasangan Pintu Panel Pintu Jati 9.00 Bh 969,600.00 8,726,400.00

    Jumlah 8,726,400.00

    Jasa Pelaksanaan + Overhead 4% 349,056.00

    Total Sub Pekerjaan 9,075,456.00

    8.3 Kaca

    8.2.1. Pasangan Kaca Tebal 5 mm bening 7.56 M2 119,835.50 905,956.38

    8.2.1. Pasangan Kaca Tebal 10 mm tempert 37.44 M2 449,835.50 16,841,841.12

    8.2.1. Pasangan Kaca Tebal 10 mm bening 2.08 M2 262,835.50 547,354.93

    8.2.1. Pasangan Kaca Tebal 5 mm buram 3.75 M2 119,835.50 449,383.13

    Jumlah 18,744,535.55

    Jasa Pelaksanaan + Overhead 4% 749,781.42

    Total Sub Pekerjaan 19,494,316.98

    8.4 Penggantung/Kunci

    8.3.1. Pasangan Engsel Pintu 36.00 Bh 206,585.00 7,437,060.00

    M3

  • 8.3.2. Pasangan Engsel Jendela 12.00 Bh 206,585.00 2,479,020.00

    8.3.3. Pasangan Kunci Taman Antik 4.00 Bh 139,510.00 558,040.00

    Jumlah 10,474,120.00

    Jasa Pelaksanaan + Overhead 4% 418,964.80

    Total Sub Pekerjaan 10,893,084.80

    8.5 Pintu Besi

    8.4.1. Pintu Besi 32.20 M2 1,011,664.00 32,575,580.80

    Jumlah 32,575,580.80

    Jasa Pelaksanaan + Overhead 4% 1,303,023.23

    Total Sub Pekerjaan 33,878,604.03

    IX. PEKERJAAN PENGECATAN

    9.1. Mendempul dan Menggosok Kayu 45.00 M2 7,215.00 324,675.00

    9.2. Mengecat Kayu Baru 45.00 M2 57,990.00 2,609,550.00

    9.3. Mengecat Tembok Baru Interior 510.00 M2 20,668.00 10,540,680.00

    9.3. Mengecat Tembok Baru Exterior 300.00 M2 25,868.00 7,760,400.00

    9.4. Mengecat Besi 32.20 M2 117,430.00 3,781,246.00

    9.5. Mengecat Plafond 220.00 M2 25,868.00 5,690,960.00

    Jumlah 30,707,511.00

    Jasa Pelaksanaan + Overhead 4% 1,228,300.44

    Total Sub Pekerjaan 31,935,811.44

    IX. PEKERJAAN INTERIOR HPL

    9.1. Multiplek fin. HPL Ruang Kitchen 33.32 M2 490,500.00 16,343,460.00

    9.3. Multiplek fin. HPL Ruang Toilet 2.04 M2 490,500.00 1,000,620.00

    Jumlah 17,344,080.00

    Jasa Pelaksanaan + Overhead 4% 693,763.20

    Total Sub Pekerjaan 18,037,843.20

    X. PEK. INSTALASI DAN SANITASI

    10.1 Listrik

    10.1.1 Pemasangan Listrik Baru 1.00 Ls 52,860,000.00 52,860,000.00

    Jumlah 52,860,000.00

    Jasa Pelaksanaan + Overhead 4% 2,114,400.00

    Total Sub Pekerjaan 54,974,400.00

  • 10.2. Sanitair dan Instalasi Air

    10.2.1. Pemasangna Kloset Jongkok 1.00 Bh 3,820,500.00 3,820,500.00

    10.2.2. Pemasangan Kloset Duduk 2.00 Bh 4,036,260.00 8,072,520.00

    10.2.3. Pemasangan Floor Draine 8.00 Bh 506,900.00 4,055,200.00

    10.2.4. Pemasangan Bak Cuci Piring 2.00 Bh 634,905.00 1,269,810.00

    10.2.5. Pemasangan Wastafel Ex Toto LW542J 3.00 Bh 2,178,530.00 6,535,590.00

    10.2.5. Perlengkapan Sanitair Toilet 1.00 Ls 26,840,000.00 26,840,000.00

    10.2.6. Pem. Pipa Gip. Dia. 15 mm 20.00 M 59,400.00 1,188,000.00

    10.2.7. Pem. Pipa Gip. Dia. 20 mm 17.00 M 74,900.00 1,273,300.00

    10