Page : 1 PROYEK : Tenant KFC Food Avenue St Moritz Pekerjaan : Pekerjaan Plumbing Subject : Bill Of Quantity TANGGAL : 11 November 2015 NO DESCRIPTION UNIT QTY harga satuan Total SPK material upah material upah I Pekerjaan Air Bekas Drain 1 Instalasi pipa pvc aw dia 2 " ex Rucika ttk 6 180,000 45,000 1,080,000 270,000 2 Instalasi pipa pvc aw dia 3 " ex Rucika mtr 8 126,100 45,000 1,008,800 360,000 3 Fitting & accessories ( termasuk lem, sock, elbow dll ) ls 1 600,000 - 600,000 - 4 Testing & commissioning ls 1 - ### - 300,000 II Pekerjaan Air Bersih 1 Instalasi pipa PPR PN 10 dia 1/2" ex wavin tigris / setara mtr 28 15,000 15,000 420,000 420,000 2 Instalasi pipa PPR PN 10 dia 3/4" ex wavin tigris / setara mtr 12 22,500 15,000 270,000 180,000 3 Instalasi pipa PPR PN 10 dia 1" ex wavin tigris / setara mtr 12 37,500 22,500 450,000 270,000 4 Ball Valve dia 1/2" bh 7 157,500 15,000 1,102,500 105,000 5 Ball Valve dia 1" bh 4 375,000 30,000 1,500,000 120,000 6 Pompa dorong 125 w berikut pengkabelan dan control pressureswitch, ex shimitsh unit 1 ### ### 3,000,000 300,000 7 Meter Air dia 1 " bh 1 525,000 75,000 525,000 75,000 8 Fitting & accessories ls 1 600,000 - 600,000 - 9 Hanger & Support ls 1 300,000 - 300,000 - 10 Testing & commissioning ls 1 - ### - 300,000 SUB TOTAL ### ### TOTAL MATERIAL + UPAH 13,556,300 Jakarta, 11 Novemb Dibuat oleh KFC Food Avenue St Moritz Mengetahui / Menyetujui ( Prasetyo Uto ........................

description

s

Transcript of BQ Plumbing

Page 1: BQ Plumbing

Page : 1

PROYEK : Tenant KFC Food Avenue St MoritzPekerjaan : Pekerjaan PlumbingSubject : Bill Of QuantityTANGGAL : 11 November 2015

NO DESCRIPTION UNIT QTY harga satuan Total

REMARKS SPK material upah material upah

I Pekerjaan Air Bekas Drain1 Instalasi pipa pvc aw dia 2 " ex Rucika ttk 6 180,000 45,000 1,080,000 270,000 2 Instalasi pipa pvc aw dia 3 " ex Rucika mtr 8 126,100 45,000 1,008,800 360,000 3 Fitting & accessories ( termasuk lem, sock, elbow dll ) ls 1 600,000 - 600,000 - 4 Testing & commissioning ls 1 - ### - 300,000

II Pekerjaan Air Bersih1 Instalasi pipa PPR PN 10 dia 1/2" ex wavin tigris / setara mtr 28 15,000 15,000 420,000 420,000 2 Instalasi pipa PPR PN 10 dia 3/4" ex wavin tigris / setara mtr 12 22,500 15,000 270,000 180,000 3 Instalasi pipa PPR PN 10 dia 1" ex wavin tigris / setara mtr 12 37,500 22,500 450,000 270,000 4 Ball Valve dia 1/2" bh 7 157,500 15,000 1,102,500 105,000 5 Ball Valve dia 1" bh 4 375,000 30,000 1,500,000 120,000 6 Pompa dorong 125 w berikut pengkabelan dan control pressureswitch, ex shimitshu unit 1 3,000,000 ### 3,000,000 300,000 7 Meter Air dia 1 " bh 1 525,000 75,000 525,000 75,000 8 Fitting & accessories ls 1 600,000 - 600,000 - 9 Hanger & Support ls 1 300,000 - 300,000 -

10 Testing & commissioning ls 1 - ### - 300,000

SUB TOTAL ### ###TOTAL MATERIAL + UPAH 13,556,300

Jakarta, 11 November 2015Dibuat oleh,