Sheet1PEKERJAAN PRASARANA LINGKUNGAN - PAGARMemasang pagar beton pracetak tinggi 1,6 m tiap 1 m'

Analisis dipakai untuk pagar lingkungan.Tinggi pagar 1,6 m (4 panel 50x400x2130mm); tinggi kolom 2,4 m; jarak kolom = 2,25 m; cor kolom 0,25x0,25x0,8m.Galian pondasi untuk kolom = 0,25x0,25x0,8 = 0,05/2,25 = 0,022 m galian pondasi (SNI 2835:2008 An 6.1.).Cor pondasi kolom dengan beton B0 (1:3:5) = 0,05/2,25 = 0,022 m (An D.2)Satu kolom dipancang tiap 2,25 m atau 1/2,25 = 0,445 btg/m' pagar; 4 bh panel dipasang tiap 2,25 m atau 4/2,25 = 1,778 lbr/m' pagar.Upah tenaga memakai RSNI T-12-2002 Persiapan An 6.16.

Harga bahan:-Panel beton pracetak 50x400x2130lbr1.77895,420.00169,656.76-Kolom beton pracetak t = 2400 mmbtg0.445159,023.0070,765.24-Pasir betonm0.0103237,424.002,445.47-Batu pecah/split 2/3m0.0171230,946.003,949.18-Semen portlandkg4.891,258.006,151.62Jumlah Harga Bahan252,968.26Upah tenaga:-PekerjaOH0.37577,583.0029,093.63-Tukang batuOH0.12594,650.0011,831.25-Kepala tukangOH0.0125109,107.001,363.84-MandorOH0.01875123,971.002,324.46Jumlah Upah Tenaga44,613.17Jumlah Bahan & Tenaga297,581.43Biaya Umum & Keuntungan 10%29,758.14Dibulatkan327,339Memasang pagar beton pracetak tinggi 2 m tiap 1 m'

Analisis dipakai untuk pagar lingkungan.Tinggi pagar 2 m (5 panel 50x400x2130mm); tinggi kolom 3 m; jarak kolom = 2,25 m; cor kolom 0,25x0,25x0,8m.Galian pondasi untuk kolom = 0,25x0,25x0,8 = 0,05/2,25 = 0,022 m galian pondasi (SNI 2835:2008 An 6.1.).Cor pondasi kolom dengan beton B0 (1:3:5) = 0,05/2,25 = 0,022 m (An D.2)Satu kolom dipancang tiap 2,25 m atau 1/2,25 = 0,445 btg/m' pagar; 5 bh panel dipasang tiap 2,25 m atau 5/2,25 = 2,223 lbr/m' pagar.Upah tenaga memakai RSNI T-12-2002 Persiapan An 6.16.

Harga bahan:-Panel beton pracetak 50x400x2130lbr2.22395,420.00212,118.66-Kolom beton pracetak t = 2750 mmbtg0.445183,265.0081,552.93-Pasir betonm0.0103237,424.002,445.47-Batu pecah/split 2/3m0.0171230,946.003,949.18-Semen portlandkg4.891,258.006,151.62Jumlah Harga Bahan306,217.85Upah tenaga:-PekerjaOH0.37577,583.0029,093.63-Tukang batuOH0.12594,650.0011,831.25-Kepala tukangOH0.0125109,107.001,363.84-MandorOH0.01875123,971.002,324.46Jumlah Upah Tenaga44,613.17Jumlah Bahan & Tenaga350,831.02Biaya Umum & Keuntungan 10%35,083.10Dibulatkan385,914Membuat pagar dinding tinggi 2 m bata merah + plesteran + cat tembok tiap 1 m'

Analisis dipakai untuk pagar belakang/samping rumah & kantor.Metoda:1. Pekerjaan galian = 0,525 m/m' x (SNI 2835:2008 An 6.1); 2. Dasar galian dipadatkan dengan tamper/hand compactor 6 lintasan = 0,6 m/m' x An B.14.); 3. Pas. batu kosong = 0,093 m/m' x (SNI 2836:2008 An 6.9.); 4. Pasang batu belah 1 PC : 5 PP = 0,225 m/m' x (SNI 2836:2008 An 6.3.); 5. Urugan kembali = 0,207 m/m' x (SNI 2835:2008 An 6.9.);6. Pasang sloof beton bertulang 15 x 20 = 1 x (An D.40.);7. Pasang kolom 11 x 11 beton bertulang tinggi 2,6m' (tertanam 60 cm di batu kali) tiap 3m' = 2,6/3 m'/m' x (SNI 7394:2008 An 6.35.);8. Pasang ringbalk 10 x 15 beton bertulang = 1 m' x (SNI 7394:2008 An 6.36.);9. Pasang bata 1 PC : 5 PP = 1,65 m/m' x (SNI 6897:2008 An 6.10.); 10. Dinding diplester 2 sisi 1 PC : 5 PP tebal 15 mm = 4 m/m' x (SNI 2837:2008 An 6.5.);11. Pengecatan tembok baru dg plamir 1 m + 1 lps dsr + 2 lps Catylac = 4 m/m' x (Pt-T-38-2000-C/SNI 03-xxxx-2002 An 6.14.);

Harga bahan:-Batu belah 15/20m0.38225,090.0085,534.20-Batu pecah/split 2/3m0.047230,946.0010,854.46-Bata merahbh115.5528.0060,984.00-Semen portlandkg86.351,258.00108,628.30-Pasir urugm0.04216,193.008,647.72-Pasir pasangm0.3223,252.0066,975.60-Pasir betonm0.03237,424.007,122.72-Kayu Terentang balokm0.01371,849,574.0025,339.16-Paku biasa 2"-5"kg0.06215,949.00988.84-ResiduLtr0.041,614.0064.56-Besi beton poloskg10.649,224.0098,143.36-Kawat betonkg0.15318,007.002,755.07-Plamir tembokkg0.411,005.004,402.00-Cat tembok Catylackg0.427,500.0011,000.00-Cat tembok Catylackg1.0427,500.0028,600.00Jumlah Harga Bahan520,039.99Harga pemakaian alat:-TAMPER / VIBRATING RAMMERjam0.0347449,800.941,730.08Jumlah Harga Alat1,730.08Upah tenaga:-PekerjaOH3.2377,583.00250,593.09-Tukang kayuOH0.08596,049.008,164.17-Tukang besiOH0.0894,225.007,538.00-Tukang batuOH1.028694,650.0097,356.99-Tukang catOH0.25294,461.0023,804.17-Kepala tukangOH0.144109,107.0015,711.41-MandorOH0.16123,971.0019,835.36Jumlah Upah Tenaga423,003.19Jumlah Bahan & Tenaga & Alat944,773.26Biaya Umum & Keuntungan 10%94,477.33Dibulatkan1,039,250Membuat pagar dinding tinggi 3 m bata merah + plesteran + cat tembok tiap 1 m'

Analisis dipakai untuk pagar belakang/samping rumah & kantor.Metoda:1. Pekerjaan galian = 0,525 m/m' x (SNI 2835:2008 An 6.1); 2. Dasar galian dipadatkan dengan tamper/hand compactor 6 lintasan = 0,6 m/m' x An B.14.); 3. Pas. batu kosong = 0,093 m/m' x (SNI 2836:2008 An 6.9.); 4. Pasang batu belah 1 PC : 5 PP = 0,225 m/m' x (SNI 2836:2008 An 6.3.); 5. Urugan kembali = 0,207 m/m' x (SNI 2835:2008 An 6.9.);6. Pasang sloof beton bertulang 15 x 20 = 1 x (An D.40.);7. Pasang kolom 11 x 11 beton bertulang tinggi 3,6m' (tertanam 60 cm di batu kali) tiap 3m' = 3,6/3 m'/m' x (SNI 7394:2008 An 6.35.);8. Pasang ringbalk 10 x 15 beton bertulang = 1 m' x (SNI 7394:2008 An 6.36.);9. Pasang bata 1 PC : 5 PP = 2,65 m/m' x (SNI 6897:2008 An 6.10.); 10. Dinding diplester 2 sisi 1 PC : 5 PP tebal 15 mm = 6 m/m' x (SNI 2837:2008 An 6.5.);11. Pengecatan tembok baru dg plamir 1 m + 1 lps dsr + 2 lps Catylac = 6 m/m' x (Pt-T-38-2000-C/SNI 03-xxxx-2002 An 6.14.);

Harga bahan:-Batu belah 15/20m0.382225,090.0085,984.38-Batu pecah/split 2/3m0.05230,946.0011,547.30-Bata merahbh185.5528.0097,944.00-Semen portlandkg107.7361,258.00135,531.89-Pasir urugm0.04216,193.008,647.72-Pasir pasangm0.398223,252.0088,854.30-Pasir betonm0.0324237,424.007,692.54-Kayu Terentang balokm0.01441,849,574.0026,633.87-Paku biasa 2"-5"kg0.06515,949.001,036.69-ResiduLtr0.041,614.0064.56-Besi beton poloskg11.649,224.00107,367.36-Kawat betonkg0.16818,007.003,025.18-Plamir tembokkg0.611,005.006,603.00-Cat tembok Catylackg0.627,500.0016,500.00-Cat tembok Catylackg1.5627,500.0042,900.00Jumlah Harga Bahan640,332.77Harga pemakaian alat:-TAMPER / VIBRATING RAMMERjam0.0347449,800.941,730.08Jumlah Harga Alat1,730.08Upah tenaga:-PekerjaOH4.23277,583.00328,331.26-Tukang kayuOH0.09296,049.008,836.51-Tukang besiOH0.086694,225.008,159.89-Tukang batuOH1.43694,650.00135,917.40-Tukang catOH0.37894,461.0035,706.26-Kepala tukangOH0.2109,107.0021,821.40-MandorOH0.213123,971.0026,405.82Jumlah Upah Tenaga565,178.53Jumlah Bahan & Tenaga & Alat1,207,241.38Biaya Umum & Keuntungan 10%120,724.14Dibulatkan1,327,965Membuat pagar dinding tinggi 2 m bata hollow ekspos + kolom/ringbalk diplester & dicat tiap 1 m'

Analisis dipakai untuk pagar belakang/samping rumah & kantor. Tinggi pagar jadi 2 m'; sloof 15/20; kolom 15/15 tiap 3 m'; ringbalk 15/15.Metoda:1. Pekerjaan galian = 0,525 m/m' x (SNI 2835:2008 An 6.1); 2. Dasar galian dipadatkan dengan tamper/hand compactor 6 lintasan = 0,6 m/m' x An B.14.); 3. Pas. batu kosong = 0,093 m/m' x (SNI 2836:2008 An 6.9.); 4. Pasang batu belah 1 PC : 5 PP = 0,225 m/m' x (SNI 2836:2008 An 6.3.); 5. Urugan kembali = 0,207 m/m' x (SNI 2835:2008 An 6.9.);6. Pasang sloof beton bertulang 15 x 20 = 1 x (An D.40.);7. Pasang kolom 11 x 11 beton bertulang tinggi 2,6m' (tertanam 60 cm di batu kali) tiap 3m' = 2,6/3 m'/m' x (SNI 7394:2008 An 6.35.);8. Pasang ringbalk 10 x 15 beton bertulang = 1 m' x (SNI 7394:2008 An 6.36.);9. Pasang bata hollowblock HB.10 (batako pres berlubang) = 1,65 m/m' x (SNI 6897:2008 An 6.21.); 10. Sloof, kolom, ringbalk diplester 2 sisi 1 PC : 5 PP tebal 15 mm = (15+15+15+5)+(20+20+5)+((15+15+5+5)x1,65/3) = 1,17 m/m' x (SNI 2837:2008 An 6.5.);11. Pasangan dinding conblock finishing siar 2x1,65 x (SNI 2837:2008 An 6.25.);12. Pengecatan tembok baru dg plamir 1 m + 1 lps dsr + 2 lps Catylac = 1,17 m/m' x (Pt-T-38-2000-C/SNI 03-xxxx-2002 An 6.14.);

Harga bahan:-Batu belah 15/20m0.382225,090.0085,984.38-Batu pecah/split 2/3m0.047230,946.0010,854.46-Hollow block HB 10bh20.6251,675.0034,546.88-Semen portlandkg811,258.00101,898.00-Pasir urugm0.04216,193.008,647.72-Pasir pasangm0.217223,252.0048,445.68-Pasir betonm0.03237,424.007,122.72-Kayu Terentang balokm0.01371,849,574.0025,339.16-Paku biasa 2"-5"kg0.06215,949.00988.84-ResiduLtr0.041,614.0064.56-Besi beton poloskg11.10189,224.00102,403.00-Kawat betonkg0.15318,007.002,755.07-Plamir tembokkg0.11711,005.001,287.59-Cat tembok Catylackg0.11727,500.003,217.50-Cat tembok Catylackg0.304227,500.008,365.50Jumlah Harga Bahan441,921.06Harga pemakaian alat:-TAMPER / VIBRATING RAMMERjam0.0347449,800.941,730.08Jumlah Harga Alat1,730.08Upah tenaga:-PekerjaOH2.55777,583.00198,379.73-Tukang kayuOH0.08596,049.008,164.17-Tukang besiOH0.0894,225.007,538.00-Tukang batuOH0.7294,650.0068,148.00-Tukang catOH0.073794,461.006,961.78-Kepala tukangOH0.096109,107.0010,474.27-MandorOH0.122123,971.0015,124.46Jumlah Upah Tenaga314,790.41Jumlah Bahan & Tenaga & Alat758,441.55Biaya Umum & Keuntungan 10%75,844.16Dibulatkan834,285Membuat pagar dinding tinggi 1,5 m bata hollow ekspos + kolom/ringbalk diplester & dicat tiap 1 m'

Analisis dipakai untuk pagar antar rumah. Tinggi pagar jadi 1,5 m'; sloof 15/20; ringbalk 15/15.Metoda:1. Pekerjaan galian = 0,293 m/m' x (SNI 2835:2008 An 6.1); 2. Dasar galian dipadatkan dengan tamper/hand compactor 6 lintasan = 0,55 m/m' x An B.14.); 3. Pasang batu belah 1 PC : 5 PP = 0,158 m/m' x (SNI 2836:2008 An 6.3.); 4. Urugan kembali = 0,135 m/m' x (SNI 2835:2008 An 6.9.);5. Pasang sloof beton bertulang 15 x 20 = 1 x (An D.40.);6. Pasang kolom 11 x 11 beton bertulang tinggi 1,95m' (tertanam 45 cm di batu kali) tiap 3m' = 1,95/3 m' = 0,65m'/m' x (SNI 7394:2008 An 6.35.);7. Pasang ringbalk 10 x 15 beton bertulang = 1 m' x (SNI 7394:2008 An 6.36.);8. Pasang bata hollowblock HB.10 (batako pres berlubang) = 1,15 m/m' x (SNI 6897:2008 An 6.21.); 9. Sloof, kolom, ringbalk diplester 2 sisi 1 PC : 5 PP tebal 15 mm = (15+15+15+5)+(20+20+5)+((15+15+5+5)x1,15/3) = 1,103 m/m' x (SNI 2837:2008 An 6.5.);10. Pasangan dinding conblock finishing siar 2x1,15 x (SNI 2837:2008 An 6.25.);11. Pengecatan tembok baru dg plamir 1 m + 1 lps dsr + 2 lps Catylac = 1,103 m/m' x (Pt-T-38-2000-C/SNI 03-xxxx-2002 An 6.14.);

Harga bahan:-Batu belah 15/20m0.1896225,090.0042,677.06-Batu pecah/split 2/3m0.045230,946.0010,392.57-Hollow block HB 10bh14.3751,675.0024,078.13-Semen portlandkg63.0151,258.0079,272.87-Pasir pasangm0.159223,252.0035,497.07-Pasir betonm0.0291237,424.006,909.04-Kayu Terentang balokm0.01331,849,574.0024,599.33-Paku biasa 2"-5"kg0.059515,949.00948.97-ResiduLtr0.041,614.0064.56-Besi beton poloskg10.3129,224.0095,117.89-Kawat betonkg0.14318,007.002,575.00-Plamir tembokkg0.1111,005.001,210.55-Cat tembok Catylackg0.1127,500.003,025.00-Cat tembok Catylackg0.28727,500.007,892.50Jumlah Harga Bahan334,260.53Harga pemakaian alat:-TAMPER / VIBRATING RAMMERjam0.03184549,800.941,585.91Jumlah Harga Alat1,585.91Upah tenaga:-PekerjaOH1.91277,583.00148,338.70-Tukang kayuOH0.0896,049.007,683.92-Tukang besiOH0.075694,225.007,123.41-Tukang batuOH0.53494,650.0050,543.10-Tukang catOH0.06994,461.006,517.81-Kepala tukangOH0.0758109,107.008,270.31-MandorOH0.0927123,971.0011,492.11Jumlah Upah Tenaga239,969.36Jumlah Bahan & Tenaga & Alat575,815.80Biaya Umum & Keuntungan 10%57,581.58Dibulatkan633,397Membuat pagar BRC 1,2 m tinggi jadi 1,5 m (pondasi batu kali + sloof 15/20 + bata 30 cm + plester + cat) tiap 1 m'

Analisis dipakai untuk pagar depan rumah & kantor. Tinggi pagar jadi 1,5 m; pondasi batu kali 25/45 cm tinggi 45 cm; sloof 15/20 cm;pasangan bata tinggi 30 cm diplester 1 PC : 5 PP & dicat; pagar BRC 1,2 m; tiang BRC tiap 2,4 m.Metoda:1. Pekerjaan galian = 0,39 m/m' x (SNI 2835:2008 An 6.1); 2. Pas. batu kosong = 0,083 m/m' x (SNI 2836:2008 An 6.9.); 3. Pasang batu belah 1 PC : 5 PP = 0,158 m/m' x (SNI 2836:2008 An 6.3.);4. Urugan kembali = 0,147 m/m' x (SNI 2835:2008 An 6.9.);5. Pasang sloof beton bertulang 15 x 20 = 1 x (An D.40.);6. Pasang bata 1 PC : 5 PP = 0,3 m/m' x (SNI 6897:2008 An 6.10.); 7. Dinding diplester 2 sisi 1 PC : 5 PP tebal 15 mm = 1,15 m/m' x (SNI 2837:2008 An 6.5.);8. Pagar sepanjang 7,2 m perlu 4 bh tiang = 4/7,2 tiang/m = 0,555x1,05 = 0,583 bh tiang/m'9. Satu lembar pagar BRC lebar 2,4 m'; upah per m' SNI 03-2835-2002 An 6.15 = 0,042 pekerja; 0,004 kep.tukang; 0,042 tukang; 0,002 mandor.10. Pengecatan tembok baru dg plamir 1 m + 1 lps dsr + 2 lps Catylac = 1,15 m/m' x (Pt-T-38-2000-C/SNI 03-xxxx-2002 An 6.14.);

Harga bahan:-Batu belah 15/20m0.2892225,090.0065,096.03-Batu pecah/split 2/3m0.0243230,946.005,611.99-Bata merahbh21528.0011,088.00-Semen portlandkg40.43361,258.0050,865.47-Pasir urugm0.036216,193.007,782.95-Pasir pasangm0.1294223,252.0028,888.81-Pasir betonm0.0162237,424.003,846.27-Kayu Terentang balokm0.0091,849,574.0016,646.17-Paku biasa 2"-5"kg0.03315,949.00526.32-ResiduLtr0.041,614.0064.56-Besi beton poloskg4.449,224.0040,954.56-Kawat betonkg0.06418,007.001,152.45-Pagar BRC tinggi 1,2 m'm'1.05235,084.00246,838.20-Tiang pagar BRC tinggi 1,5 m'bh0.583159,806.0093,166.90-Plamir tembokkg0.11511,005.001,265.58-Cat tembok Catylackg0.11527,500.003,162.50-Cat tembok Catylackg0.29927,500.008,222.50Jumlah Harga Bahan585,179.23Upah tenaga:-PekerjaOH1.27977,583.0099,228.66-Tukang kayuOH0.034696,049.003,323.30-Tukang besiOH0.029694,225.002,789.06-Tukang batuOH0.494,650.0037,860.00-Tukang catOH0.0794,461.006,612.27-Kepala tukangOH0.0536109,107.005,848.14-MandorOH0.06123,971.007,438.26Jumlah Upah Tenaga163,099.68Jumlah Bahan & Tenaga & Alat748,278.91Biaya Umum & Keuntungan 10%74,827.89Dibulatkan823,106Membuat pagar BRC 0,9 m tinggi jadi 1,2 m (pondasi batu kali + sloof 15/20 + bata 30 cm + plester + cat) tiap 1 m'

Analisis dipakai untuk pagar depan rumah & kantor. Tinggi pagar jadi 1,2 m; pondasi batu kali 25/45 cm tinggi 45 cm; sloof 15/20 cm;pasangan bata tinggi 30 cm diplester 1 PC : 5 PP & dicat; pagar BRC 1,2 m; tiang BRC tiap 2,4 m.Metoda:1. Pekerjaan galian = 0,39 m/m' x (SNI 2835:2008 An 6.1); 2. Pas. batu kosong = 0,083 m/m' x (SNI 2836:2008 An 6.9.); 3. Pasang batu belah 1 PC : 5 PP = 0,158 m/m' x (SNI 2836:2008 An 6.3.);4. Urugan kembali = 0,147 m/m' x (SNI 2835:2008 An 6.9.);5. Pasang sloof beton bertulang 15 x 20 = 1 x (An D.40.);6. Pasang bata 1 PC : 5 PP = 0,3 m/m' x (SNI 6897:2008 An 6.10.); 7. Dinding diplester 2 sisi 1 PC : 5 PP tebal 15 mm = 1,15 m/m' x (SNI 2837:2008 An 6.5.);8. Pagar sepanjang 7,2 m perlu 4 bh tiang = 4/7,2 tiang/m = 0,555x1,05 = 0,583 bh tiang/m'9. Satu lembar pagar BRC lebar 2,4 m'; upah per m' SNI 03-2835-2002 An 6.15 = 0,042 pekerja; 0,004 kep.tukang; 0,042 tukang; 0,002 mandor.10. Pengecatan tembok baru dg plamir 1 m + 1 lps dsr + 2 lps Catylac = 1,15 m/m' x (Pt-T-38-2000-C/SNI 03-xxxx-2002 An 6.14.);

Harga bahan:-Batu belah 15/20m0.2892225,090.0065,096.03-Batu pecah/split 2/3m0.0243230,946.005,611.99-Bata merahbh21528.0011,088.00-Semen portlandkg40.43361,258.0050,865.47-Pasir urugm0.036216,193.007,782.95-Pasir pasangm0.1294223,252.0028,888.81-Pasir betonm0.0162237,424.003,846.27-Kayu Terentang balokm0.0091,849,574.0016,646.17-Paku biasa 2"-5"kg0.03315,949.00526.32-ResiduLtr0.041,614.0064.56-Besi beton poloskg4.449,224.0040,954.56-Kawat betonkg0.06418,007.001,152.45-Pagar BRC tinggi 0,9 m'm'1.05186,343.00195,660.15-Tiang pagar BRC tinggi 1,2 m'bh0.583135,237.0078,843.17-Plamir tembokkg0.11511,005.001,265.58-Cat tembok Catylackg0.11527,500.003,162.50-Cat tembok Catylackg0.29927,500.008,222.50Jumlah Harga Bahan519,677.46Upah tenaga:-PekerjaOH1.27977,583.0099,228.66-Tukang kayuOH0.034696,049.003,323.30-Tukang besiOH0.029694,225.002,789.06-Tukang batuOH0.494,650.0037,860.00-Tukang catOH0.0794,461.006,612.27-Kepala tukangOH0.0536109,107.005,848.14-MandorOH0.06123,971.007,438.26Jumlah Upah Tenaga163,099.68Jumlah Bahan & Tenaga & Alat682,777.13Biaya Umum & Keuntungan 10%68,277.71Dibulatkan751,054