EDISI SEPTEMBER 2009
HARGA SATUAN
(Rp)
1 P e k e r j a Hr 30,000.00
2 M a n d o r Hr 40,000.00
3 T u k a n g K a y u Hr 42,500.00
4 T u k a n g B a t u Hr 42,500.00
5 T u k a n g B e s i Hr 42,500.00
6 T u k a n g C a t Hr 42,500.00
7 T u k a n g L e i d e n g Hr 42,500.00
8 T u k a n g G a l i Hr 40,000.00
9 T u k a n g P l i t u r Hr 40,000.00
10 T u k a n g K e p a l a Hr 43,000.00
11 K e p . T u k a n g K a y u Hr 45,000.00
12 K e p . T u k a n g B a t u Hr 45,000.00
13 K e p . T u k a n g C a t Hr 45,000.00
14 K e p . T u k a n g P l i t u r Hr 45,000.00
15 K e p . T u k a n g G a l i Hr 45,000.00
16 M e k a n i k Hr 37,500.00
17 P e m b . M e k a n i k Hr 37,500.00
18 Operator alat berat Hr 43,000.00
19 P e m b . Operator Hr 35,000.0020 S o p i r Hr 40,500.00
21 P e m b . Sopir Hr 30,000.00
Rembang, Juli 2009
KEPALA DINAS PEKERJAAN UMUM
KABUPATEN REMBANG
Ir. MUJOKO, MT.NIP. 010 234 645 / 19620715 199011 1 002
DAFTAR HARGA SATUAN UPAH
NO. JENIS PEKERJAAN SATUAN KETERANGAN
DINAS PEKERJAAN UMUM KABUPATEN REMBANG
TAHUN 2010
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office
-
7/30/2019 Analis RAB Gedung 2010
2/44
EDISI SEPTEMBER 2009
HARGA
NO. SATUAN KET.
1 3 4 5
I B A H A N D A S A R1 BATU KALI Bulat Utuh m3 91,900
Bulat Belah m3 93,750
Pecah 5/7 m3 135,850
Pecah 3/5 m3 208,550
Tempel m2 68,750
Batu apung kg 6,050
2 KERIKIL Sawur / Koral m3 27,500
Beton 0,5 / 1 m3 261,250
Beton 1 / 1 m4 238,400
Beton 1 / 2 m3 248,950
Beton 2 / 3 m3 246,850
Biasa m3 28,450
3 BATU BATA Ex lokal I bh 425
4 PASIR Urug m3 61,950Pasang m3 125,000
Beton (Muntilan) m3 309,430
Beton (Cepu) m3 171,950
Sirtu (pasir batu) m3 106,600
Sirtu royalty m3 27,300
Grosok m3 103,200
Abu batu m3 116,950
Abu batu (Tayu) m3 211,200
Batu alam m2 90,100
5 TANAH Padas m3 33,650
Liat m3 55,000
Biasa m3 49,950
Pilihan m3 68,750
6 KAPUR Pasang (padam) m3 196,000Labor Kg 2,750
7 PORTLAND CEMENT
PC 50 kg zak 65,625
PC 40 kg zak 51,250
PC 50 kg Sm. Warna zak 89,450
Semen warna kg 11,250
7 BETON Adukan beton K 175 ready mix m3 897,850
Adukan beton K 225 ready mix m3 952,875
Adukan beton K 300 ready mix m3 994,250
II B A H A N P E N U T U P A T A P
1 SIRAP (100 lbr) pak 258,950
2 GENTENG BETON Genteng Beton Warna standard bh 2,750
Kerpus Beton Warna Standard bh 9,075
3 GENTENG TANAH LIAT
Mantili bh 1,000
Nok kerpus Mantili bh 2,900
Plentong Mantili besar bh 1,200
Genteng biasa bh 650
Genteng pres bh 1,000
Genteng Beton bh 4,400
Genteng keramik bh 11,100
Sirap bh 6,300
Genteng kerpus jatiwangi bh 10,550
Genteng kerpus lokal bh 3,200
Genteng kerpus Beton bh 9,075
Genteng kerpus keramik bh 19,350
Genteng Jatiwangi bh 3,8505 ASBES GELOMBANG
Asbes gelombang ( 80 x 210 ) cm bh 45,850
Asbes gel. Kecil 5 mm (90 x 180) lbr 53,850
Asbes gel. Kecil 5 mm (120 x 240) lbr 80,850
Asbes gel. Besar 5 mm (90 x 180) lbr 68,750
Asbes gel. Besar 5 mm (120 x 240) lbr 105,950
Asbes gel. Kecil 0,8 x 1,80 m lbr 47,750
Asbes gel. Kecil 0,8 x 2,40 m lbr 61,950
DAFTAR HARGA SATUAN BAHAN
2
J E N I S B A H A N
DINAS PEKERJAAN UMUM KABUPATEN REMBANG
TAHUN 2010
(Rp)
144824707.xls.ms_office
-
7/30/2019 Analis RAB Gedung 2010
3/44
HARGA
NO. SATUAN KET.
1 3 4 52
J E N I S B A H A N(Rp)
6 ASBES PLAT
- 100cm X 100 cm X 5 mm bh 19,050
- 100cm X 200 cm X 5 mm bh 52,800
- 100cm X 240 cm X 5 mm bh 67,750
Sekrup asbes bh 1,450
7 SENG PLAT
BJLS 0,30 panjang 180 cm m' 54,850
BJLS 0,30 panjang 240 cm m' 71,225
BWG 28 x 80 m' 42,075
BWG 28 x 90 m' 47,200
8 SENG GELOMBANG
Seng gel. Kecil 0,70 x 1,80 m lbr 54,700
Seng gel. Kecil 0,70 x 2,10 m lbr 63,150
BJLS 0,28 m' 81,200
BJLS 0,28 panjang 180 cm lbr 48,200
BJLS 0,28 panjang 240 cm lbr 64,700
9 SENG TALANG
Seng talang BJLS 26 lebar 0,60 m' 23,450
Seng talang BJLS 26 lebar 0,90 m' 33,450
Seng talang BJLS 26 lebar 1,20 m' 50,850
III . B A H A N K A Y U
1 JATI Papan m3 16,156,250
Balok/pesagen m3 16,156,250
2 KAMPER Papan m3 8,937,500
Balok/pesagen m3 8,937,500
3 KRUING Papan m3 6,531,250
Balok/pesagen m3 6,531,250
4 MERANTI Papan m3 3,437,500
Balok/pesagen m3 3,437,500
5 LANAN Papan m3 3,437,500
Balok/pesagen m3 3,437,500
6 BENGKIRAI Papan m3 8,937,500
Balok/pesagen m3 9,625,000
7 DOLKEN Kayu dolken sengon 8-10 cm,4m. bt 35,700
Kayu perancah m3 2,062,500
8 LAIN-LAIN
Kayu randu (papan) m3 631,300
Bambu bt 17,050
Bambu Apus bt 4,200
Kayu hutan lokal sekwalitas Kruing ( m3 4,855,125
Kayu hutan lokal sekwalitas Kruing ( m3 2,589,400
Glugu m' 206,250
Kayu lis 2/3 m' 6,500
IV . BAHAN PENUTUP DINDING / LANTAI
1 UBIN (TEGEL BIASA)
PC polos 30 X 30 cm m2 31,050
20 X 20 cm m2 23,900
20 X 20 cm Warna m2 28,750
2 KERAMIK
Keramik warna (KW-1) 30 X 30 cm m2 48,750
Keramik warna (KW-2) 30 X 30 cm m2 44,450
Keramik putih (KW-1) 30 X 30 cm m2 39,850
Keramik putih (KW-2) 30 X 30 cm m2 36,100
Keramik 10 x 20 cm m2 55,650
Keramik 20 x 20 cm m2 48,200
Keramik 20 x 25 cm m2 52,900
Keramik 10 x 20 cm m2 43,7003 MARMER
Marmer Tulung Agung m2 607,450
Marmer Kalimantan m2 1,019,425
Marmer Itali m2 1,381,100
144824707.xls.ms_office
-
7/30/2019 Analis RAB Gedung 2010
4/44
HARGA
NO. SATUAN KET.
1 3 4 52
J E N I S B A H A N(Rp)
4 GRANITO
Granito 40 x 40 polished (lokal) m2 462,825
Granito 40 x 40 polished (import) m2 505,000
Granito 60 x 60 polished (lokal) m2 461,000
Granito 60 x 60 polished (import) m2 481,250
5 GRANIT
Granit lokal m2 131,300
Granit import m2 241,800
Batu Tempel m2 67,375
V . B A H A N C E T A K
1 BUIS BETON O dan U
15 cm - 100 cm bh 39,050
20 cm - 100 cm bh 55,000
25 cm - 100 cm bh 58,550
30 cm - 100 cm bh 68,750
40 cm - 100 cm bh 86,600
50 cm - 100 cm bh 108,050
60 cm - 100 cm bh 128,600
80 cm - 100 cm bh 195,250
100 cm - 100 cm bh 321,450U 15 cm - 100 cm bh 54,000
U 20 cm - 100 cm bh 42,450
U 30 cm - 100 cm bh 52,250
VI . B A H A N B E S I
1 BESI BETON
Besi beton polos kg 11,100
Besi beton prestress kg 18,550
Besi beton ulir kg 15,200
2 BESI PLAT
Besi Strip kg 16,200
3 BAJA
Baja profil " L" dan "C" kg 18,500
Baja profil "IWF" kg 19,400
4 KAWAT
Kawat Ikat beton/bendrat kg 17,850
Kawat bronjong kg 18,550
Kawat las listrik kg 33,000
VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC. S. 12,5 1/2" m' 4,500
Pipa PVC. S. 12,5 3/4" m' 6,600
Pipa PVC. S. 12,5 1" m' 11,275
Pipa PVC. S. 12,5 1-1/4" m' 14,300
Pipa PVC. S. 12,5 1-1/2" m' 22,250
Pipa PVC. S. 12,5 2" m' 33,550Pipa PVC. S. 12,5 2-1/2" m' 48,125
Pipa PVC. S. 12,5 3" m' 68,900
Pipa PVC. S. 12,5 4" m' 102,900
Pipa PVC. S. 12,5 5" m' 169,800
Pipa PVC. S. 12,5 6" m' 220,450
Pipa PVC. S. 12,5 8" m' 348,300
Pipa PVC. S. 12,5 10" m' 549,450
Pipa PVC. S. 12,5 12" m' 875,700
Pipa PVC. S. 12,5 16" m' 1,476,250
2 Pipa Medium B Galvanis - SII
Pipa Galvanis ( 1" ) m' 119,300
Pipa Galvanis ( 1 1/2" ) m' 162,050
Pipa Galvanis ( 2" ) m' 303,700
VIII . B A H A N L A N G I T - L A N G I TPLY WOOD
- Teak wood
120 X 240 X 4 mm lbr 98,550
- Tripleks
120 X 240 X 3 mm lbr 55,800
120 X 240 X 4 mm lbr 72,300
120 X 240 X 6 mm lbr 91,950
- Multipleks
. 120 X 240 X 9 mm lbr 135,200
. 120 X 240 X 12 mm lbr 202,850
144824707.xls.ms_office
-
7/30/2019 Analis RAB Gedung 2010
5/44
-
7/30/2019 Analis RAB Gedung 2010
6/44
HARGA
NO. SATUAN KET.
1 3 4 52
J E N I S B A H A N(Rp)
XIV . ALAT PENGIKAT KAYU
1 Paku - ukuran 1" s/d 4" kg 16,750
2 Paku - payung kg 25,000
3 Paku - sekrup kg 22,800
4 Mur Baut 3/8 " buah 4,950
5 Lem kayu (fox) bh 18,3006 Tali Ijuk kg 13,700
7 Lem kuning (aica aibon) kg 50,200
XV . POMPA AIR DAN TANGKI AIR
1 POMPA AIR LISTRIK
Mesin pompa 1 lt / dt buah 2,651,350
Mesin pompa 1-1/2 lt / dt buah 4,639,150
Tangki air fiber glass 3.000 lt 5mm buah 6,797,175
X VI . PAVING BLOCK
1 Paving Blok Holland t: 6 cm (ALDAS) m2 59,500
2 Paving Blok Holland t: 6 cm (lokal) m2 36,750
3 Paving Blok Holland t: 8 cm (ALDAS) m2 102,100
4 Paving Blok Holland t: 8 cm (lokal) m2 18,200
5 Paving blok warna 6 cm (lokal) m2 51,800
6 Paving blok warna 8 cm (lokal) m2 55,0007 Kanstin 10/12,5 x 30 x 50 (ALDAS) bh 22,250
8 Paving Blok Hexagonal Kecil t: 6 cm, (ALDAS) m2 76,700
9 Paving Blok Hexagonal Kecil t: 8 cm, (ALDAS) m2 103,300
10 Kanstin 10 x 20 x 50 (ALDAS) bh 11,100
11 Kanstin 10/12,5 x 25 x 50 (ALDAS) bh 18,150
1 PUPUK
KCL, KS, ZK Kg 5,450
Pupuk Kandang Ton 302,500
Pupuk Kompos Ton 907,500
Pupuk Organik/Bokhasi Kg 2,450
Pupuk Phonska Kg 3,025
SP 36 Kg 3,025
Urea Kg 3,025
2 OBAT - OBATAN
Fastac 25 EC 50 mL 12,100
3 TANAMAN HIAS
Agape Batang 72,600
Angsana Batang 12,100
Apinika Buah 3,025
Bambu Hias Rumpun 29,050
Bambu Jepang Buah 19,950
Bougenville Biasa Batang 26,650
Bougenville Parigata Batang 39,950
Cemara Bola Buah 10,650
Cemara Buaya Buah 7,250
Cemara Gimbal Batang 60,500
Cemara Kipas Batang 29,300Cemara Non Flok/Ventris Batang 79,850
Daun Walisongo Buah 12,100
Glodogan Batang 79,850
Glodogan Pecut Batang 226,300
Jaranan Batang 7,250
Kamboja Jepang Batang 53,250
Ketapang Batang 36,300
Krokot Putih Rumpun 3,025
Lamtana Rebah Batang 3,025
Lamtana Tegak Batang 19,950
Mahoni 1 Meter Batang 11,200
Mimbo Batang 6,650
Mirten Buah 12,100
Palem Botol Batang 382,050
Palem Ekor Tupai Batang 189,750Palem Kuning Batang 25,300
Palem Merah Batang 30,800
Palem Raja/Putri Batang 126,500
Palem Wergu Batang 31,350
Pangkas Kuning Batang 4,400
Pangkas Merah Batang 4,400
Pinisium Batang 37,950
Rumput Jepang M2 5,050
Sawo Kecik Batang 55,650
Sikas Batang 632,500
Tanaman Taiwan Buah 3,850
Tanjung Batang 75,900
Teh - tehan Rumpun 15,400
XVII. RTH (JALUR HIJAU DAN TAMAN)
144824707.xls.ms_office
-
7/30/2019 Analis RAB Gedung 2010
7/44
HARGA
NO. SATUAN KET.
1 3 4 52
J E N I S B A H A N(Rp)
4 ALAT - ALAT PERTAMANAN
Ajir Tanaman Buah 550
Ajir Tanaman Mangrove Buah 800
Batu Asahan Buah 13,200
Bambu Usuk Buah 6,600Busi Mesin Potong Rumput Buah 12,100
Cetok Buah 23,000
Chain Saw 038 STIHL Buah 12,100,000
Chain Saw 070 STIHL Buah 15,125,000
Gunting Dahan Buah 137,950
Membran Karburator Chain Saw Buah 181,500
Membran Oli Chain Saw Buah 60,500
Mesin Potong Rumput Dorong Buah 7,260,000
Mesin Potong Rumput Gendong Buah 8,470,000
Mesin Pompa Air G x 160 + 2" Buah 3,932,500
Patok Batas Buah 6,050
Pisau M. Ptng Rmput Dorong/Gendong Buah 605,000
Piston Set Chain Saw Buah 726,000
Piston Set M. Ptng Rmpt Drong/Gndong Buah 726,000
Pot Tanaman Hias Buah 302,500Pot Tanaman Palem Buah 151,250
Rantai Chain Saw 038 STIHL Buah 302,500
Rantai Chain Saw 070 STIHL Buah 308,000
Seal Ker As Mesin M. Ptng Rmput Buah 66,550
Srumbung Bambu Buah 38,500
Srumbung Kayu Buah 24,200
Selang Biasa 2" Meter 15,400
Selang Lipat 2" Meter 6,600
Selang Spiral Meter 42,900
Tali Starter Chain Saw Buah 18,700
Trucuk Bambu Batang 7,700
5 BAHAN KEND. TDK. BERMOTOR
As Belakang Buah Buah 12,100
As Tengah Buah Buah 20,900
Ban Dalam Buah Buah 16,500
Ban Luar Buah Buah 55,000
Bos Samping Buah Buah 16,500
Laker Buah Buah 7,700
Pedal Buah Buah 13,200
Pelek Buah Buah 61,600
Per Buah Buah 38,500
Rantai Buah Buah 13,200
Ruji Buah Buah 550
Sadel Buah Buah 19,800
6 PERALATAN KEBERSIHAN DAN BHN. PEMBERSIH
Angkus Buah Buah 18,700
Bendo Buah Buah 24,200
Cangkul Buah Buah 33,900
Ekrak Buah Buah 9,700Ganco Buah Buah 36,300
Gunting Pangkas Buah Buah 115,500
Linggis Buah Buah 15,125
Sabit Buah Buah 21,175
Sapu Lidi Buah Buah 7,250
Skrap Buah Buah 6,050
XVIII. LAMPU PENERANGAN JALAN UMUM (LPJU)
1 Baut 3/8 Buah 1,100
2 Besi L Buah 66,000
3 Box KWH Meter 1 Phasa Buah 328,900
4 Box Trafo Buah 42,350
5 Conector Buah 6,875
6 Contactor SN 35 Buah 465,850
7 Cor Ornamen Tiang Listrik Buah 385,0008 Cup Piring Buah 27,500
9 Cupit Urang Buah 3,650
10 Fitting E 40 Buah 35,750
11 Fitting WD 27 Buah 19,250
12 Fotto cell 10 A Buah 137,950
13 Fotto cell 6 A Buah 93,200
14 Groundhing/ardhe Buah 25,300
15 Housing Lamp 125 W Buah 880,000
16 Housing Lamp 250 W Buah 1,694,000
17 Ignisitor Buah 57,200
18 Isolasi Buah 11,000
19 Kabel LVTC 2 x 10 mm Meter 71,500
20 Kabel LVTC 2 x 16 mm Meter 8,250
21 Kabel NYM 2 x 2,5 mm Meter 8,800
144824707.xls.ms_office
-
7/30/2019 Analis RAB Gedung 2010
8/44
HARGA
NO. SATUAN KET.
1 3 4 52
J E N I S B A H A N(Rp)
22 Kabel NYM 2 x 4 mm Meter 22,000
23 Kabel NYY 2 x 4 mm Meter 17,600
24 Kabel NYY 2 x 6 mm Meter 20,020
25 Kapasitor Buah 53,625
26 Konsul Besi 1,25" MG Batang 203,500
27 Konsul Besi 2" MG Batang 247,50028 Kotak APP/Double cover Buah 825,000
29 KWH Meter 20/60 A Buah 522,500
30 KWH Meter 50/20 A Buah 437,250
31 L Booh 1" Buah 2,200
32 Lampu HPIT 250 W Buah 264,550
33 Lampu Mercury 250 W Buah 96,250
34 Lampu Mercury 125 W Buah 46,750
35 Lampu Mercury 80 W Buah 44,000
36 Lampu Selang Meter 33,000
37 Lampu Son T 150 W Buah 107,800
38 Lampu Son T 250 W Buah 127,300
39 M C B 25 A Buah 34,100
40 M C B 63 A Buah 190,850
41 OK KWH Meter Buah 30,800
42 Pal Besi 2" dan 1" MG Buah 548,90043 Pal Besi 4 & 3 MG Buah 1,705,000
44 Pemasangan LPJU Unit 99,000
45 Pole Band 8,5 Buah 28,600
46 SJ. 5 Buah 46,650
47 Soket Lampu Selang Meter 14,850
48 T Does/Boxlit Buah 21,450
49 Terminal Box Meter Buah 28,600
50 Trafo Mercury 125 W Buah 125,950
51 Trafo Mercury 250 W Buah 207,350
52 Trafo BSN 150 W Buah 216,700
53 Trafo BSN 250 W Buah 258,500
54 Lampu Hias Christmas Unit 29,493,750
55 Lampu Hias Windmill Unit 23,100,000
56 Lampu Hias Cotton Rose Unit 22,756,250
57 Lampu Hias Number One Unit 22,343,750
58 Lampu Hias Dragon Phoenix Unit 21,587,500
59 Lampu Hias Hepla Unit 21,587,500
60 Tangga Besar 12 m Buah 9,418,750
61 Tangga Kecil 6 m Buah 4,812,500
62 Crystalite Buah 123,750
63 Lampu XL 18 Watt Buah 41,250
64 Sabuk Pengaman Buah 3,052,500
1 Selang Pemadam Kebakaran fire house Appron/Murata/ Yamato with Machino Working Pressure 10 Kg/cm2
- 1,5 x 30 m, W/Coupling roll 1,807,700
- 1,5 x 20 m, W/Coupling roll 1,478,125
- 2 x 30 m, W/Coupling roll 1,753,125
- 2 x 20 m, W/Coupling roll 1,519,375
- 2,5 x 40 m roll 2,915,550
- 2,5 x 30 m, W/Coupling roll 2,681,250- 2,5 x 20 m, W/Coupling roll 2,179,375
2 Without Coupling
- 1,5 x 20 m Tertera 368,300
- 1,5 x 30 m Tertera 553,100
- 2 x 20 m Tertera 553,100
- 2 x 30 m Tertera 842,150
- 2,5 x 20 m Tertera 673,200
- 2,5 x 30 m Tertera 1,024,350
- 2,5 x 40 m Tertera 1,363,550
3 Hydrant Box Kosong
- A1 (66 x 52 x 15 cm) Appron 858,000
- A1 (100 x 80 x 18 cm) Appron 2,334,450
- A1 (125 x 75 x 18 cm) Appron 2,797,750- A1 (95 x 66 x 20 cm) Appron 2,334,450
- A1KACA + Kunci, Tempered 5 mm Appron 1,586,000
- A2KACA + Kunci, Tempered 5 mm Appron 2,726,500
- B KACA + Kunci, Tempered 5 mm Appron 3,189,800
- C KACA + Kunci, Tempered 5 mm Appron 2,726,500
4 Fire Fighting Equipment Machino Coupling material Brass
- 1,5 Tertera 118,250
- 2 Tertera 144,375
- 2,5 Tertera 211,750
- 3 Tertera 335,500
5 Straight Nozzle (Machino Coupling) With Nozzle tip, Material Brass/ Branch pipa with straight Nozzle
XIX. ALAT PEMADAM KEBEKARAN
144824707.xls.ms_office
-
7/30/2019 Analis RAB Gedung 2010
9/44
HARGA
NO. SATUAN KET.
1 3 4 52
J E N I S B A H A N(Rp)
- 1,5 Seamless Tertera 462,000
- 2 Seamless Tertera 585,750
- 2,5 Seamless, Short, W/O Grip Tertera 640,750
- 2,5 Seamless, Long, W/O Grip Tertera 797,500
- 2,5 Seamless, Long, W/ Grip Tertera 820,875
- 1,5 Appron 46,475- 2 Appron 652,450
- 2,5 Appron 1,063,550
6 Hydrant Valve (Machino Coupling) 90
Material Brass. 10 K
- 1,5 Tertera 228,350
- 2 Tertera 319,000
- 2,5 Tertera 520,100
7 Hydrant Valve (Machino Coupling) 90
Material Brass. 20 K
- 1,5 Tertera 472,550
- 2 Tertera 732,875
- 2,5 Tertera 988,625
8 Hose Rack
- 1,5, 1,24 COMB Unit 589,875
- 2,5, 1,24 COMB Unit 643,500
9 Spray Nozzle Head
- 1,5 Tertera 284,625
- 2 Tertera 429,000
10 Hose Reel
- 1 Hose Reel, Swing Type Complete
With box Siamese Conention
4 x 2,5 x 2,5 Machino Coupling Tertera 2,046,000
11 Hydrant Pillar
- H14 AP 4 x 2,5 x 2,5 Tertera 6,345,250
- H13 AP 3 x 2,5 Tertera 3,392,650
12 On Trollen
- Type AC 15 kapasitas 6 kg buah 2,252,950
- Type AC 50 kapasitas 23 kg buah 6,413,550
13 Pemancar Pemadam Kebakaran
- 1,5 (Variable) Tertera 2,376,000
- 2,5 (Variable) Tertera 3,300,000
14 Noksel Foam buah 12,490,450
15 Foise Cabang 2 (dua) buah 4,900,500
16 Liquite kg 121,450
17 Pengisian Tabung Pemadam Kebakaran kg 79,200
18 Selang Isap 2,3 4 M unit 35,750,000
XX . L A I N - L A I N
1 Alat bantu (harga rata-rata) lot 13,750
2 Aspal kg 9,500
3 Minyak aspal ltr 2,200
4 Bensin ltr 4,500
5 Solar liter 4,500
6 Minyak tanah ltr 3,600
7 Olie (minyak pelumas) liter 34,450
8 Stempet Kg 20,050
9 Gebalan rumput m2 13,700
10 Wiremesh MS m2 72,600
11 Kayu bakar m3 97,100
12 Pintu Ronsel Doble 200 x 200 x 300 buah 41,250,000
13 Pintu Ronsel Doble 150 x 150 x 300 buah 34,375,00014 Pintu Ronsel Engkel 100 x 100 x 300 buah 17,187,500
15 Pintu Intake 100 x 100 x 300 buah 9,625,000
16 Pintu Intake 90 x 100 x 300 buah 7,562,500
17 Pintu Intake 80 x 80 x 300 buah 6,875,000
18 Pintu Intake 60 x 60 x 300 buah 6,187,500
19 Pintu Intake 50 x 50 x 300 buah 4,812,500
20 Pintu Intake 40 x 40 x 300 buah 4,468,750
21 Pintu Intake 30 x 40 x 300 buah 4,125,000
22 Nomenklatur Marmer ( 30 x 40 ) buah 543,950
23 Nomenklatur Marmer ( 15 x 20 ) buah 135,850
24 Pile Scale ( 20 x 100 ) buah 543,950
25 Pile Scale ( 12 x 100 ) buah 339,900
26 Lapisan kedap air kg 58,300
27 Nako lengkap daun 54,450
144824707.xls.ms_office
-
7/30/2019 Analis RAB Gedung 2010
10/44
HARGA
NO. SATUAN KET.
1 3 4 52
J E N I S B A H A N(Rp)
28 PAGAR BRC. Pagar BRC 90 A1 /lb 485,650
Pagar BRC 120 A1 /lb 566,500
Pagar BRC 150 A1 /lb 890,450
Pagar BRC 90 A2 /lb 404,250
Pagar BRC 120 A2 /lb 485,650
Pagar BRC 150 A2 /lb 809,050Pipa Tiang BRC 90 - 2" unit 202,400
Pipa Tiang BRC 120 - 2" unit 234,850
Pipa Tiang BRC 150 - 2" unit 251,350
29 Minyak Beton & bekisting ltr 22,000
30 Allumunium sheet 0,3 mm (90 x 180) lbr 130,680
31 Shear Connector kg 11,000
Rembang, Juli 2009
KEPALA DINAS PEKERJAAN UMUM
KABUPATEN REMBANG
Ir. MUJOKO, MT.NIP. 010 234 645 / 19620715 199011 1 002
144824707.xls.ms_office
-
7/30/2019 Analis RAB Gedung 2010
11/44
EDISI SEPTEMBER 2009
NO. KODE HARGA SATUAN
1 2 4
I A PEKERJAAN PERSIAPAN
A.1 1M' Pagar Sementara dari Seng Gelombang Tinggi 2,00 m 394,652.50
A.2 1M' Pengukuran dan Pemasangan Bouwplank 100,482.38
A.3 1M2 Pembuatan Kantor Sementara dg Lantai Plesteran 1,175,370.50
A.4 1M2 Pembuatan Gudang Semen dan Alat-alat 1,027,867.25
A.5 1M2 Membersihkan Lapangan dan Perataan 5,000.00
A.6 1M2 Pembuatan Steger dari Bambu Uk. 40 x 50 x 20 cm 35,342.00
A.7 1M3 Bongkaran Beton Bertulang 213,330.00
A.8 1M3 Bongkaran Dinding Tembok Bata Merah 201,330.00
A.9 1 M3 MEMBONGKAR DINDING BATA / BATU (Batu / bata dipakai lagi) 93,600.00A.10 1 M3 MEMBONGKAR DINDING BATA / BATU (bongkaran tidak dipakai lagi) 68,000.00
A.11 1M2 MEMBONGKAR PLESTERAN DINDING 4,250.00
A.12 1M2 MEMBONGKAR GENTENG / SIRAP (bongkaran tidak dipakai lagi) 3,400.00
A.13 1M2 MEMBONGKAR GENTENG / SIRAP (bongkaran dipakai lagi) 17,000.00
A.14 1M2 MEMBONGKAR RANGKA ATAP/RENG KASO (bongkaran tidak dipakai lagi) 8,625.00
A.15 1M2 MEMBONGKAR RANGKA ATAP / RENG KASO (bongkaran dipakai lagi) 11,500.00
A.16 1M3 MEMBONGKAR KUDA-KUDA GORDING/BALOK (bongkaran dipakai lagi) 418,000.00
A.17 1M3 MEMBONGKAR KUDA-KUDA GORDING/BALOK (bongkaran tidak dipakai lagi) 263,500.00
A.18 1M2 MEMBONGKAR PLAFOND (bongkaran dipakai lagi) 17,500.00
A.19 1M2 MEMBONGKAR PLAFOND (bongkaran tidak dipakai lagi) 5,100.00
II B PEKERJAAN TANAHB.1 1M3 Galian Tanah Biasa Sedalam 1 m 13,600.00
B.2 1M3 Galian Tanah Keras Sedalam 1 m 31,280.00
B.3 1M3 Galian Tanah Cadas Sedalam 1 m 47,400.00
B.4 1M3 Galian Tanah Lumpur Sedalam 1 m 37,800.00
B.5 1M2 Pekerjaan Striping Setinggi 1 m 1,700.00
B.6 1M3 Membuang Tanah Sejauh 30 m' 10,300.00
B.7 1M3 Urugan Kembali (dihitung 1/3 kali indeks pekerjaan galian) -
B.8 1M3 Pemadatan Tanah 17,000.00
B.9 1M3 Urugan Pasir 83,740.00
B.10 1M3 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL 149,380.00
B.11 1M2 Pemasangan Lapisan Ijuk tebal 10 cm 87,300.00
B.12 1M3 Urugan Sirtu 41,500.00
B.13 1 M3 Galian Tanah Biasa Sedalam 2 meter 17,860.00
B.14 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 3 M' TENAGA MANUSIA 25,657.50
B.15 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 4 M' TENAGA MANUSIA 32,767.50
B.16 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 5 M' TENAGA MANUSIA 39,877.50
B.17 1 M3 PEK. GALIAN TANAH BANYAK TERDAPAT BATU-BATU BUNDAR 50,437.50
MAX KEDALAMAN 1 M' TENAGA MANUSIA
B.18 1 M3 PEK. GALIAN TANAH BERBATU MAX KEDALAMAN 1 M' TNG MANUSIA 27,187.50
B.19 1 M3 PEK. GALIAN TANAH MAX KEDALAMAN 2 M' DENGAN ALAT EXAVATOR 0,7 M3 6,763.16
B.20 1 M3 PEK. GALIAN TANAH MAX KEDALAMAN 5 M' DENGAN ALAT EXAVATOR 0,7 M3 8,784.33
B.21 MENGANGKUT HASIL GALIAN DENGAN DUMP TRUCK . M3/KM. 4,904.36
B.22 1 M3. MENGANGKUT HASIL GALIAN EXAVATOR 0,7 M3 DENGAN DUMP TRUCK 6,688.05
KURANG DARI 1,5 KM.
B.23 1 M3. MENGANGKUT HASIL GALIAN EXAVATOR 0,7 M3 DENGAN DUMP TRUCK 11,146.74
JARAK ANTARA 1,5 S/D 3 KM.
B.24 1 M3. MENGANGKUT HASIL GALIAN EXAVATOR 0,7 M3 DENGAN DUMP TRUCK 15,605.44
JARAK ANTARA 3 S/D 5 KM.
B.25 1 M3 MERATAKAN TANAH 9,618.75
B.26 1 M3 PEK. URUGAN TANAH PILIHAN 93,275.00
B.27 1 M3 PEK. LAPISAN PUDEL 1 KP : 3 TL 148,100.00
B.28 1 M3 PEK. LAPISAN PUDEL 1 KP : 5 PS 218,100.00
B.29 1 M3 MERATAKAN TANAH DAN DITIMBRIS 9,618.75
B.30 1 M2 MENGAMBIL DAN PASANGAN GEBALAN 5,271.88
B.31 1 M' MENGANGKUT GEBALAN RUMPUT 1,871.88
B.32 1 M2 PEKERJAAN GEBALAN RUMPUT SAMPAI TUMBUH 23,211.88
B.33 1 M2 URUGAN PAKAI ALAT BESAR TANAH DARI LUAR DIPADATKAN (U/5000 M3) 92,912.50
3
URAIAN PEKERJAAN
D A F T A R H A R G A S A T U A N P E K E R J A A N
DINAS PEKERJAAN UMUM KABUPATEN REMBANG
TAHUN 2010
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 11
-
7/30/2019 Analis RAB Gedung 2010
12/44
NO. KODE HARGA SATUAN
1 2 43
URAIAN PEKERJAAN
III C PEKERJAAN PONDASI
C.1 1M3 Pasang Pondasi Batu Kali 1Pc : 3 Ps 514,450.00
C.1a 1 M3 PASANGAN BATU BELAH 1 : 4 458,262.50
C.2 1M3 Pasang Pondasi Batu Kali 1Pc : 5 Ps 435,200.00
C.3 1M3 Pasang Pondasi Batu Kali, 1 Pc : 3 Kp : 10 Ps 359,074.50
C.4 1M3 Pasang Pondasi Batu Kosong 180,152.40
C.5 1M3 Pasang Pondasi Siklop 60% Beton Camp. 1PC : 2PS : 3KR & 2,036,818.40
40% Batu Belah
C.6 1M3 Pasang Pondasi Sumuran diameter 100 cm 546,777.50
C.7 1M' Pembuatan Tiang Pancang (40x40) cm, Beton Bertulang 725,148.40
C.8 SEBUAH TIANG PANCANG DICINCIN DAN DILANCIPKAN (KAYU HUTAN) 10,912.50
C.9 1 M' TIANG DIPANCANGKAN DIDALAM TANAH LUNAK 57,737.50
C.10 1 M' TIANG DIPANCANGKAN DIDALAM TANAH BIASA 72,171.88
C.11 1 M' TIANG DIPANCANGKAN DIDALAM TANAH KERAS 86,606.25C.12 1 M' TIANG DIPANCANGKAN DIDALAM TANAH PASIR 115,475.00
C.13 1 M3 PASANGAN BATU BRONJONG UNTUK KAWAT 3 MM 356,263.33
C.14 1 M3 PASANGAN BATU BRONJONG UNTUK KAWAT 4 MM 484,763.33
C.15 1 M3 PASANGAN BATU BRONJONG UNTUK KAWAT 5 MM 645,596.67
IV D P E K E R J A A N D I N D I N G
D.1 1M2 Pasang Batu Merah Tebal 1/2 bata, 1 Pc : 2 Ps 73,671.88
D.2 1M2 Pasang Batu Merah Tebal 1/2 bata, 1 Pc : 3 Ps 67,910.63
D.3 1M2 Pasang Batu Merah Tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps 59,146.25
D.4 1 M2 PASANGAN 1/2 BATA MERAH 1 : 4 65,118.75
D.5 1 M2 PASANGAN 1/2 BATA MERAH 1 : 5 62,980.00
D.6 1 M2 PASANGAN BATU TEMPEL + SIARAN 133,301.25
D.7 1 M3 PASANGAN BATA MERAH 1 PC : 2 PS 738,842.50
D.8 1 M3 PASANGAN BATA MERAH 1 PC : 4 PS 643,965.00
D.9 1 M3 PASANGAN BATA MERAH 1 PC : 3 KP : 10 PS 556,142.50
V E PEKERJAAN P L E S T E R A N
E.1 1M2 Plesteran 1 Pc : 3 Ps Tebal 15 mm 25,902.50
E.2 1M2 Plesteran 1 Pc : 2 Kp : 8 Ps Tebal 15 mm 20,097.50
E.3 1M2 Plesteran 1 Pc : 3 Kp : 10 Ps Tebal 15 mm 18,183.50
E.4 1M2 Plesteran 1 Pc : 3 Ps Tebal 20 mm 35,183.00
E.5 1M2 Berapen 1 Pc : 5 Ps Tebal 15 mm 18,164.00
E.6 1M' Plesteran Skoning 1 Pc : 2 Ps lebar 10 mm 5,155.00
E.7 1M2 Plesteran Ciprat 1 Pc : 2 Ps 19,140.00
E.8 1M2 Finishing Siar Pas. Batu Kali Adukan 1 Pc : 2 Ps 26,001.25
E.9 1M2 Acian 13,785.63
VI F PEKERJAAN KAYU
F.1 1M3 Membuat Kosen Pintu & Jendela Kayu klas I 18,943,112.50
F.2 1M3 Membuat Kosen Pintu & Jendela Kayu Bengkirai 11,002,487.50
F.3 1M2 Membuat Pintu Klamp Standard Kayu Bengkirai 418,907.50
F.4 1M2 Membuat Daun Pintu Panel Kayu Bengkirai 507,915.00
F.5 1M2 Membuat Pintu & Jendela Kaca Kayu Bengkirai 437,902.50
F.6 1M2 Membuat Pintu & Jendela Jalusi Kayu Kelas I (Jati) 1,226,150.00
F.7 1M2 Membuat Pintu Plywood Rangkap rangka Kayu Bengkirai lbr s/d 90cm 445,240.00
F.8 1M2 Membuat Pintu Plywood rangkap, rangka expose kayu Bengkirai 456,602.50
F.9 1M2 Membuat Jalusi mati Kosen Kayu Kelas I (Jati) 1,081,887.50
F.10 1M2 Membuat Jalusi mati Kosen Kayu Bengkirai 648,762.50
F.11 1M2 Membuat Pintu Teakwood Rangkap Rangka Kayu Kelas I (jati) 628,048.75
F.12 1M2 Membuat Pintu Teakwood Rangkap Lapis Formika Rangka ekspose 593,304.00
Kayu Bengkirai
F.13 1 M2 DAUN PINTU TRIPLEK DOUBLE UKURAN PINTU LAPIS ALUMINIUM ( KM/WC ) 456,611.00
F.14 1 M2 DAUN PINTU TRIPLEK DOUBLE UKURAN PINTU LAPIS FORMIKA ( KM/WC ) 442,085.00
F.15 1M3 Memasang Konstruksi Kuda-kuda Konvensional Kayu Bengkirai 11,607,900.00
Bentang 6 M
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 12
-
7/30/2019 Analis RAB Gedung 2010
13/44
NO. KODE HARGA SATUAN
1 2 43
URAIAN PEKERJAAN
F.16 1M3 Memasang Konstruksi Kuda-kuda Ekspose Kayu Jati 19,240,675.00
F.17 1M3 Memasang Konstruksi Gording Kayu Bengkirai 10,539,700.00
F.18 1M2 Pasang Pintu Plywood & Formika Rangka Kayu Bengkirai 626,042.50
F.19 1M2 Pasang Pintu Formika Double, Rangka Kayu Jati 844,375.00
F.20 1M2 Memasang Rangka Atap Genteng Keramik, Kayu Bengkirai 129,512.50
F.21 1M2 Memasang Rangka Atap Genteng Beton, Kayu Bengkirai 136,442.50
F.22 1M2 Pasang Rangka Atap Sirap Kayu Bengkirai 1,600,955.00
F.23 1M' Pasang Listplank Uk. (3x20)cm Kayu Bengkirai 78,850.00
F.24 1M' Pasang Listplank Uk. (3x30)cm Kayu Bengkirai 111,750.00
F.25 1M' Pasang Listplank Uk. 2x(3x20)cm Kayu Bengkirai 148,656.25
F.26 1M2 Pasang Rangka Dinding Pemisah Kayu Bengkirai 281,612.50
F.27 1M2 Pas. Dinding Pemisah Teakwood Rangkap Rangka Kayu Bengkirai 373,733.50
F.28 1M2 Pasang Dinding Lambriziring dari Papan jati 221,988.75
F.29 1M2 Pasang Plywood tebal 4mm unt Dinding 52,122.00
F.30 1M2 Pasang Dinding Bilik, Rangka Kayu Klas III / IV 80,107.00
VII G PEKERJAAN BETON
G.1 1M3 Membuat Beton mutu f'c=7,4 Mpa (K100), slum (122)cm, w/c = 0,87 679,355.82
G.2 1M3 Membuat Beton mutu f'c=9,8 Mpa (K125), slum (122)cm, w/c = 0,78 735,932.22
G.3 1M3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum (122)cm, w/c = 0,72 742,299.65
G.4 1M3 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87 644,983.39
G.5 1M3 Membuat Beton mutu f'c=14,5 MPa (K175), slum (122)cm, w/c = 0,66 773,823.84
G.6 1M3 Membuat Beton mutu f'c=16,9 MPa (K200), slum (122)cm,w/c = 0,61 804,752.72
G.7 1M3 Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 828,562.75
G.8 1M3 Membuat Beton mutu f'c=21,7 MPa (K250), slum (122)cm,w/c = 0,56 911,379.90
G.9 1M3 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (122)cm, w/c = 0,53 936,109.66
G.10 1M3 Membuat Beton mutu f'c=26,4 MPa (K300), slum (122)cm,w/c = 0,52 943,719.83
G.11 1M3 Membuat Beton mutu f'c=28,8 MPa (K325), slum (122)cm,w/c = 0,49 991,870.82
G.12 1M3 Membuat Beton mutu f'c=31,2 MPa (K350), slum (122)cm, w/c = 0,48 1,001,923.14
G.13 1KG Pembesian dg Besi Polos 12,477.75
G.13a 110 KG Besi Beton Terpasang (polos) 1,372,552.50
G.13b 125 KG Besi Beton Terpasang (polos) 1,559,718.75
G.14 1KG Kabel Presstresed Polos/strand 20,053.00
G.15 1M2 Pasang Bekisting untuk Pondasi 118,585.00
G.16 1M2 Pasang Bekisting untuk Sloof 190,772.50
G.17 1M2 Pasang Bekisting untuk Kolom 346,918.75
G.18 1M2 Pasang Bekisting untuk Balok 310,825.00
G.19 1M2 Pasang Bekisting untuk Lantai 443,312.50
G.20 1M2 Pasang Bekisting untuk Dinding 352,775.00
G.21 1M2 Pasang Bekisting untuk Tangga 278,787.50
G.22 1 M2 Pasang Bekisting Jembatan Cor 89,520.00
G.23 1 M2 BEKESTING DENGAN PAPAN 138,762.50
G.24 1 M2 BEKESTING DENGAN MULTIPLEX 9 MM 130,776.90
G.25 1 M3 Membuat Pondasi Beton Bertulang (150 kg Besi + Bekisting) 3,273,255.50
G.26 1 M3 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting) 4,066,433.00
G.27 1 M3 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting) 7,375,933.00
G.28 1 M3 Membuat Balok Beton Bertulang (200 kg Besi + Bekisting) 5,740,743.00
G.29 1 M3 Membuat Balok Beton Bertulang (150 kg Besi + Bekisting) 5,509,225.50
G.30 1 M3 Membuat Dinding Beton Bertulang (150 kg Besi + Bekisting) 5,195,990.50
G.31 1 M3 Membuat Tangga Beton Bertulang (200 kg Besi + Bekisting) 5,253,870.50
G.32 1 M' Membuat Kolom Penguat Beton Bertulang (11 x 11) cm 62,837.95
G.33 1 M' Membuat Ring Balok Beton Bertulang (10 x 15) cm 73,827.55
G.34 1 M3 PAS. BETON K-175 READY MIX 6 M3 BERIKUT SLANG 988,993.75
G.35 1 M3 PAS. BETON K-225 READY MIX 6 M3 BERIKUT SLANG 1,044,018.75
G.36 1 M3 PAS. BETON K-300 READY MIX 6 M3 BERIKUT SLANG 1,085,393.75
G.37 1 KG PEK. ERECTION KONST. KUDA-KUDA BESI 906.30
G.38 1 KG PEKERJAAN BAJA IWF 44,140.00
G.39 1 KG PEKERJAAN KONSTUKSI BESI SIKU / PROFIL 43,150.00
G.40 1 CM PEK. PENGELASAN DENGAN LAS LISTRIK TEBAL KAWAT 4 MM 39,930.30
G.41 1 TITIK MELUBANG KONSTRUKSI BESI DENGAN BOR 40,025.00
G.42 1 M2 PEKERJAAN WIREMESH M8 83,213.50
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 13
-
7/30/2019 Analis RAB Gedung 2010
14/44
NO. KODE HARGA SATUAN
1 2 43
URAIAN PEKERJAAN
VIII H PEKERJAAN PENUTUP ATAP
H.1 1 M2 Pasang Atap Genteng Mantili Kecil 33,367.50
H.2 1 M2 Pasang Atap Genteng Mantili Besar 31,640.00
H.3 1 M' Pasang Genteng Bubung Mantili 50,480.00
H.4 1 M2 Pasang Atap Asbes Gelombang (80 x 210 cm) x 5 mm 38,577.50
H.5 1 M2 Pasang Atap Genteng Beton 41,852.50
H.6 1 M2 Pasang Atap Sirap 175,770.00
H.7 1 M' Pasang Nok Genteng Beton 72,975.00
H.8 1 M' Pasang Nok Sirap 58,457.93
H.9 1 M2 Pasang Atap Seng Gelombang 63,835.00
H.10 1 M' Pasang Atap Nok Seng 33,105.00
IX I PEKERJAAN LANGIT - LANGIT
I.1 1 M2 Langit-langit Asbes (1,00x1,00) m, tebal 4 mm, 5 mm & 6 mm 25,392.50I.2 1 M2 Memasang Langit-langit Tripleks Uk (120x240) cm, 34,575.00
Tebal 3 mm, 4 mm & 6 mm
I.3 1 M2 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm 299,311.25
I.4 1 M2 Langit-langit Gypsum Board, tebal 9 mm 38,088.00
I.5 1 M' List Langit-Langit Kayu Profil 12,117.50
I.6 1M2 Pasang Rangka Langit-langit (1,00x1,00) m, kayu Bengkirai 170,825.00
I.7 1M2 Pasang Rangka Langit-langit (60x60) cm, kayu Bengkirai 181,575.00
X J PEKERJAAN SANITASI, JALAN DAN SALURAN
J.1 1 UNIT Memasang Closet Duduk Porselin 736,645.00
J.2 1 UNIT Memasang Closet Jongkok 300,525.00
J.3 1 UNIT Memasang Wastafel 714,572.50
J.4 1 M' Memasang Pipa Beton, 15 cm - 20 cm 77,660.78
J.5 1 M' Memasang Pipa Beton, 30 cm - 100 cm 122,367.05
J.6 1 M' Memasang Pipa PVC type AW " 10,092.00
J.7 1 M' MEMASANG PIPA PVC type AW 3/4" 13,346.00
J.8 1 M' MEMASANG PIPA type AW PVC 1" 20,102.00
J.9 1 M' MEMASANG PIPA PVC type AW 11/4" 24,610.00
J.10 1 M' MEMASANG PIPA PVC type AW 11/2" 35,820.00
J.11 1 M' Memasang Pipa PVC type AW 2" 51,586.00
J.12 1 M' MEMASANG PIPA PVC type AW 21/2" 72,900.75
J.13 1 M' Memasang Pipa PVC type AW 3" 102,643.00
J.14 1 M2 PASANG PAVING BLOK 6 CM K : 300 94,382.50
J.15 1 M2 PASANG PAVING BLOK 6 CM K : 175 71,405.00
J.16 1 M2 PASANG PAVING BLOK 8 CM K ; 300 137,408.50
J.17 1 M2 PASANG PAVING BLOK 8 CM K: 175 52,669.50
J.18 1 M2 PASANGAN PAVING BLOK WARNA 6 CM K: 175 86,605.50
J.19 1 M2 PASANGAN PAVING BLOK WARNA 8 CM K: 175 89,837.50
J.20 1 M2 LAPISAN PENGISI / PENUTUP DENGAN ASPAL PANAS TEBAL 3 CM 44,630.05
J.21 MENGGILAS JALAN 1 HARI DIPERLUKAN 514,687.50
J.21a MENGGILAS 1 M2 LAPIS KULIT PENAHAN 3,431.25
J.21b MENGGILAS 1 M2 LAPIS KULIT PERTEGARAN 1,715.63
J.21c MENGGILAS LAPIS AUS ( PENETRASI ) 1,029.38
J.21d MENGGILAS RINGAN 1 M2 OPERPENTING 1,286.72
J.22 100 M2 PENGASPALAN SHEET (LATASIR) TEBAL 1 CM JERENG 1,752,590.00
J.23 1M2 ASPAL SAND SHEET TEBAL 2 CM JERENG ( 1 CM PADAT ) 41,206.18
J.24 1M2 ASPAL SAND SHEET TEBAL 3 CM JERENG ( 2 CM PADAT ) 58,732.08
XI K PEKERJAAN BESI & ALLUMUNIUM
K.1 1 Kg Memasang Besi Profil 26,981.00
K.2 1 Kg Memasang Rangka Kuda-kuda Baja IWF 27,050.00
K.3 1 M' Memasang Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm 244,148.75
K.4 1 M' Memasang Talang 1/2 Lingkaran 15 cm, Seng Plaat BJLS 30 84,740.00
Lebar 45 cm
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 14
-
7/30/2019 Analis RAB Gedung 2010
15/44
NO. KODE HARGA SATUAN
1 2 43
URAIAN PEKERJAAN
XII L PEKERJAAN KUNCI dan KACA
L.1 1 BUAH Pasang Kunci Tanam Biasa 87,550.00
L.2 1 BUAH Pasang Kunci Tanam Kamar Mandi 87,075.00
L.3 1 BUAH Pasang Engsel Pintu 14,680.00
L.4 1 BUAH Pasang Engsel Jendela Kupu-kupu 12,350.00
L.5 1 BUAH Pasang Engsel Angin 16,350.00
L.6 1 BUAH Pasang Kait Angin 27,030.00
L.7 1 BUAH Pasang Kunci Selot 20,490.00
L.8 1 BUAH Pasang Kunci Lemari 23,000.00
L.9 1 M2 Pasang Kaca tebal 5 mm 113,405.00
XIII M PEKERJAAN PENUTUP LANTAI & DINDING
M.1 1 M2 Pasang lantai Ubin PC Abu-abu Uk. 20 x 20 cm 55,441.50
M.2 1 M2 Pasang lantai Ubin Granito Uk. 40 x 40 cm 581,335.38M.3 1 M2 Pasang Lantai Keramik 30 x 30 cm 129,741.25
M.4 1 M2 Pasang Lantai Keramik 20 x 20 cm 121,950.00
M.5 1M2 Memasang Lantai Marmer ukuran 1.00x1.00 m 697,684.23
M.6 1 M2 Pasang Dinding Keramik 10x20 cm, 132,065.75
M.7 1 M2 Pasang Dinding Keramik 20x20 cm, 130,193.75
M.8 1M2 Memasang Dinding Marmer ukuran 1.00x1.00 m 727,264.35
M.9 1 M2 Pasang Dinding Batu Paros / Batu Tempel Hitam 131,671.88
M.10 1 M2 DINDING GRANIT IMPORT 498,012.50
M.11 1 M2 LANTAI GRANIT IMPORT 405,602.50
M.12 1 M2 LANTAI GRANITO UKURAN 60 X 60 POLISHED 562,117.50
M.13 1 M2 DINDING GRANITO UKURAN 60 X 60 POLISHED 566,587.50
M.14 1 M2 LANTAI MARMER ITALY 1,544,902.50
M.15 1 M2 DINDING MARMER ITALY 1,634,312.50
XIV N PEKERJAAN PENGECATAN
N.1 1 M2 Mendempul dan Menggosok Kayu 5,548.00
N.2 1 M2 Pengecatan Bidang Lama 14,788.00
N.3 1 M2 Pengecatan Bidang Kayu Baru (1 lap.Plamir) 32,530.00
1 lap.Cat Dasar & 2 lap.Cat Penutup
N.4 1 M2 Pengecatan Bidang Kayu Baru (1 lap.Plamir) 41,569.00
1 lap.Cat Dasar & 3 lap.Cat Penutup
N.5 1 M2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 11,292.00
2 lap. Cat Penutup)
N.6 1 M2 Pengecat Tembok Lama (1lap.Plamir, 2lap Cat Penutup) 7,352.00
N.7 1 M2 Pengecatan Permukaan Baja dg Meni Besi 11,428.00
N.8 1 M2 Pengecatan Permukaan Baja dg Meni Besi & Perancah 24,338.00
N.9 1 M2 Pengecatan Permukaan Baja lapis Seng (Galvanis) secara 88,696.00
manual sistem 3 lapis Cat Konvensional dg tebal 200 um
N.10 1 M2 PLITURAN BANGUNAN ( BIASA ) 35,650.50
N.11 1 M2 PLITURAN MEUBELAIR 70,973.50
Rembang, Juli 2009
KEPALA DINAS PEKERJAAN UMUMKABUPATEN REMBANG
Ir. MUJOKO, MT.
NIP. 010 234 645 / 19620715 199011 1 002
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 15
-
7/30/2019 Analis RAB Gedung 2010
16/44
EDISI SEPTEMBER 2009
No. KODE KOEF SAT. HARGA SAT. JUMLAH
Rp Rp
1 3 4 5 7 8 = ( 4 X 7 )
I A PEKERJAAN PERSIAPAN
A.1 1M' Pagar Sementara dari Seng Gelombang Tinggi 2,00 m 394,652.50
1.2500 Btg Kayu Dolken diameter 8 - 10 / 400 cm 35,700.00 44,625.00
2.5000 Kg Portalnd Semen 1,312.50 3,281.25
1.2000 Lbr Seng Gelombang 3" - 5" 54,850.00 65,820.00
0.0050 m3 Pasir Pasang 125,000.00 625.00
0.0090 m3 Koral Beton 261,250.00 2,351.25
0.0720 m3 Kayu 5/7X4m Kayu Meranti 3,437,500.00 247,500.00
0.0600 Kg Paku Biasa 2" - 5" 16,750.00 1,005.00
0.4500 Kg Meni Besi 16,100.00 7,245.00
0.2000 OH Tukang Kayu 42,500.00 8,500.00
0.4000 OH Pekerja 30,000.00 12,000.000.0200 OH Kepala Tukang 45,000.00 900.00
0.0200 OH Mandor 40,000.00 800.00
A.2 1M' Pengukuran dan Pemasangan Bouwplank 100,482.38
0.0120 m3 Kayu 5/7x 4m Kayu Kruing 4,855,125.00 58,261.50
0.0200 Kg Paku Biasa 2" - 5" 16,750.00 335.00
0.0070 m3 Kayu Papan 3/20 Kayu Kruing 4,855,125.00 33,985.88
0.1000 OH Tukang Kayu 42,500.00 4,250.00
0.1000 OH Pekerja 30,000.00 3,000.00
0.0100 OH Kepala Tukang 45,000.00 450.00
0.0050 OH Mandor 40,000.00 200.00
A.3 1M2 Pembuatan Kantor Sementara dg Lantai Plesteran 1,175,370.501.2500 Btg Kayu Dolken 8 - 10 / 4 m 35,700.00 44,625.00
0.1800 m3 Kayu 3,437,500.00 618,750.00
0.8500 Kg Paku Biasa 2" - 5" 16,750.00 14,237.50
1.1000 Kg Besi Strip 16,200.00 17,820.00
35.0000 Kg Portland Sement 1,312.50 45,937.50
0.2500 m3 Pasir pasang 125,000.00 31,250.00
0.1500 m3 Koral Beton 261,250.00 39,187.50
30.0000 buah Batu bata Merah 425.00 12,750.00
0.2500 Lbr Seng Plat 54,850.00 13,712.50
2.0000 daun Jendela Naco 54,450.00 108,900.00
0.0800 m2 Kaca Polos 96,250.00 7,700.00
0.1500 buah Kunci Tanam 65,350.00 9,802.50
0.3000 buah Engsel 5,950.00 1,785.00
0.0600 Lbr Plywood 4 mm 98,550.00 5,913.00
2.0000 OH Tukang Kayu 42,500.00 85,000.00
1.0000 OH Tukang Batu 42,500.00 42,500.00
2.0000 OH Pekerja 30,000.00 60,000.00
0.3000 OH Kepala Tukang 45,000.00 13,500.00
0.0500 OH Mandor 40,000.00 2,000.00
A.4 1M2 Pembuatan Gudang Semen dan Alat-alat 1,027,867.25
1.7000 Btg Kayu Dolken diameter 8 - 10 / 400 cm 35,700.00 60,690.00
0.2100 m3 Kayu 3,437,500.00 721,875.00
0.3000 Kg Paku Biasa 2" - 5" 16,750.00 5,025.00
10.5000 Kg Portland Semen 1,312.50 13,781.25
0.0300 m3 Pasir Beton (Cepu) 171,950.00 5,158.50
0.0500 m3 Koral Beton 261,250.00 13,062.50
1.5000 Lbr Seng Gelombang BJLS 32 54,850.00 82,275.00
2.0000 OH Tukang Kayu 42,500.00 85,000.00
1.0000 OH Pekerja 30,000.00 30,000.00
0.2000 OH Kepala Tukang 45,000.00 9,000.00
0.0500 OH Mandor 40,000.00 2,000.00
A.5 1M2 Membersihkan Lapangan dan Perataan 5,000.00
0.1000 OH Pekerja 30,000.00 3,000.00
0.0500 OH Mandor 40,000.00 2,000.00
A.6 1M2 Pembuatan Steger dari Bambu Uk. 40 x 50 x 20 cm 35,342.00
1.0000 Btg Bambu diameter 6 - 8 / 600 cm 17,050.00 17,050.00
0.2500 Kg Tali Ijuk 13,700.00 3,425.00
0.1700 OH Tukang Kayu 42,500.00 7,225.00
0.2500 OH Pekerja 30,000.00 7,500.00
0.0020 OH Kepala Tukang 45,000.00 90.00
0.0013 OH Mandor 40,000.00 52.00
TAHUN 2010
6
URAIAN PAKERJAAN
DAFTAR ANALISA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM KABUPATEN REMBANG
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 16
-
7/30/2019 Analis RAB Gedung 2010
17/44
A.7 1M3 Bongkaran Beton Bertulang 213,330.00
6.6670 OH Pekerja 30,000.00 200,010.00
0.3330 OH Mandor 40,000.00 13,320.00
A.8 1M3 Bongkaran Dinding Tembok Bata Merah 201,330.00
6.6670 OH Pekerja 30,000.00 200,010.00
0.0330 OH Mandor 40,000.00 1,320.00
A.9 1 M3 MEMBONGKAR DINDING BATA / BATU (Batu / bata dipakai lagi) 93,600.00
3.0000 Org Pekerja 30,000.00 90,000.00
0.0900 Org Mandor 40,000.00 3,600.00
A.10 1 M3 MEMBONGKAR DINDING BATA / BATU (bongkaran tidak dipakai lagi) 68,000.00
2.0000 Org Pekerja 30,000.00 60,000.00
0.2000 Org Mandor 40,000.00 8,000.00
A.11 1M2 MEMBONGKAR PLESTERAN DINDING 4,250.00
0.1250 Org pekerja 30,000.00 3,750.00
0.0125 Org Mandor 40,000.00 500.00
A.12 1M2 MEMBONGKAR GENTENG / SIRAP (bongkaran tidak dipakai lagi) 3,400.00
0.1000 Org pekerja 30,000.00 3,000.000.0100 Org Mandor 40,000.00 400.00
A.13 1M2 MEMBONGKAR GENTENG / SIRAP (bongkaran dipakai lagi) 17,000.00
0.5000 Org pekerja 30,000.00 15,000.00
0.0500 Org Mandor 40,000.00 2,000.00
A.14 1M2 MEMBONGKAR RANGKA ATAP/RENG KASO (bongkaran tidak dipakai lagi) 8,625.00
0.1500 Org Pekerja 30,000.00 4,500.00
0.0750 Org Tukang Kayu 42,500.00 3,187.50
0.0075 Org Kepala tukang kayu 45,000.00 337.50
0.0150 Org Mandor 40,000.00 600.00
A.15 1M2 MEMBONGKAR RANGKA ATAP / RENG KASO (bongkaran dipakai lagi) 11,500.00
0.2000 Org Pekerja 30,000.00 6,000.00
0.1000 Org Tukang Kayu 42,500.00 4,250.000.0100 Org Kepala tukang kayu 45,000.00 450.00
0.0200 Org Mandor 40,000.00 800.00
A.16 1M3 MEMBONGKAR KUDA-KUDA GORDING/BALOK (bongkaran dipakai lagi) 418,000.00
4.0000 Org Pekerja 30,000.00 120,000.00
6.0000 Org Tukang Kayu 42,500.00 255,000.00
0.6000 Org Kepala tukang kayu 45,000.00 27,000.00
0.4000 Org Mandor 40,000.00 16,000.00
A.17 1M3 MEMBONGKAR KUDA-KUDA GORDING/BALOK (bongkaran tidak dipakai lagi) 263,500.00
4.0000 Org Pekerja 30,000.00 120,000.00
3.0000 Org Tukang Kayu 42,500.00 127,500.00
0.4000 Org Mandor 40,000.00 16,000.00
A.18 1M2 MEMBONGKAR PLAFOND (bongkaran dipakai lagi) 17,500.00
0.1000 Org Pekerja 30,000.00 3,000.00
0.3000 Org Tukang Kayu 42,500.00 12,750.00
0.0300 Org Kepala tukang kayu 45,000.00 1,350.00
0.0100 Org Mandor 40,000.00 400.00
A.19 1M2 MEMBONGKAR PLAFOND (bongkaran tidak dipakai lagi) 5,100.00
0.1500 Org Pekerja 30,000.00 4,500.00
0.0150 Org Mandor 40,000.00 600.00
Keterangan :A.20 a K = Biaya
275.0000 a = Upah Pekerja
L = Jarak angkut
Keterangan :A.21 a K = Biaya
275.0000 a = Upah Pekerja
L = Jarak angkut
II B PEKERJAAN TANAH
B.1 1M3 Galian Tanah Biasa Sedalam 1 m 13,600.00
0.400 OH Pekerja 30,000.00 12,000.00
0.040 OH Mandor 40,000.00 1,600.00
( L + 75 ))Biaya setiap jarak pengangkutan/langsiran 1 m3 Material = K : (
( L + 75 ))/25Biaya setiap jarak pengangkutan / langsiran 1 zak semen = K : (
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 17
-
7/30/2019 Analis RAB Gedung 2010
18/44
B.2 1M3 Galian Tanah Keras Sedalam 1 m 31,280.00
1.000 OH Pekerja 30,000.00 30,000.00
0.032 OH Mandor 40,000.00 1,280.00
B.3 1M3 Galian Tanah Cadas Sedalam 1 m 47,400.00
1.500 OH Pekerja 30,000.00 45,000.00
0.060 OH Mandor 40,000.00 2,400.00
B.4 1M3 Galian Tanah Lumpur Sedalam 1 m 37,800.00
1.200 OH Pekerja 30,000.00 36,000.000.045 OH Mandor 40,000.00 1,800.00
B.5 1M2 Pekerjaan Striping Setinggi 1 m 1,700.00
0.050 OH Pekerja 30,000.00 1,500.00
0.005 OH Mandor 40,000.00 200.00
B.6 1M3 Membuang Tanah Sejauh 30 m' 10,300.00
0.330 OH Pekerja 30,000.00 9,900.00
0.010 OH Mandor 40,000.00 400.00
Suppl. B 6 1 M3 PEK. PEMBUANGAN LEBIH DARI RADIUS 30 M
Keterangan :
a K = Biaya
275 a = Upah PekerjaL = Jarak pembuangan
B.7 1M3 Urugan Kembali (dihitung 1/3 kali indeks pekerjaan galian)
B.8 1M3 Pemadatan Tanah 17,000.00
0.500 OH Pekerja 30,000.00 15,000.00
0.050 OH Mandor 40,000.00 2,000.00
B.9 1M3 Urugan Pasir 83,740.00
1.200 m3 Pasir Urug 61,950.00 74,340.00
0.300 OH Pekerja 30,000.00 9,000.00
0.010 OH Mandor 40,000.00 400.00
B.10 1M3 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL 149,380.00
0.400 m3 Pasir Urug 61,950.00 24,780.00
0.135 m3 Kapur Padam 196,000.00 26,460.00
0.948 m3 Tanah Liat 55,000.00 52,140.00
0.800 OH Pekerja 30,000.00 24,000.00
0.400 OH Tukang Batu 42,500.00 17,000.00
0.040 OH Kepala Tukang 45,000.00 1,800.00
0.080 OH Mandor 40,000.00 3,200.00
B.11 1M2 Pemasangan Lapisan Ijuk tebal 10 cm 87,300.00
6.000 kg Ijuk 13,700.00 82,200.00
0.150 OH Pekerja 30,000.00 4,500.00
0.015 OH Mandor 40,000.00 600.00
B.12 1M3 Urugan Sirtu 41,500.00
1.200 m3 Sirtu 27,500.00 33,000.00
0.250 OH Pekerja 30,000.00 7,500.00
0.025 OH Mandor 40,000.00 1,000.00
B.13 1 M3 Galian Tanah Biasa Sedalam 2 meter 17,860.00
0.526 OH Pekerja 30,000.00 15,780.00
0.052 OH Mandor 40,000.00 2,080.00
B.14 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 3 M' TENAGA MANUSIA 25,657.50
0.735 org Pekerja 30,000.00 22,050.00
0.073 org Mandor 40,000.00 2,920.00
0.050 lot Alat bantu 13,750.00 687.50
B.15 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 4 M' TENAGA MANUSIA 32,767.50
0.944 org Pekerja 30,000.00 28,320.00
0.094 org Mandor 40,000.00 3,760.00
0.050 lot Alat bantu 13,750.00 687.50
B.16 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 5 M' TENAGA MANUSIA 39,877.50
1.153 org Pekerja 30,000.00 34,590.00
0.115 org Mandor 40,000.00 4,600.00
0.050 lot Alat bantu 13,750.00 687.50
B.17 1 M3 PEK. GALIAN TANAH BANYAK TERDAPAT BATU-BATU BUNDAR
MAX KEDALAMAN 1 M' TENAGA MANUSIA 50,437.50
1.500 org Pekerja 30,000.00 45,000.000.050 org Mandor 40,000.00 2,000.00
0.250 lot Alat bantu 13,750.00 3,437.50
MENGGUNAKAN RUMUS = K : ( L + 75 )
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 18
-
7/30/2019 Analis RAB Gedung 2010
19/44
B.18 1 M3 PEK. GALIAN TANAH BERBATU MAX KEDALAMAN 1 M' TNG MANUSIA 27,187.50
0.625 org Pekerja 30,000.00 18,750.00
0.125 org Mandor 40,000.00 5,000.00
0.250 lot Alat bantu 13,750.00 3,437.50
B.19 1 M3 PEK. GALIAN TANAH MAX KEDALAMAN 2 M' DENGAN ALAT EXAVATOR 0,7 M 6,763.16
0.005 unit Excavator 0,7 m3 500,000.00 2,286.63
0.704 liter Solar 4,500.00 3,169.27
0.018 liter Olie (minyak pelumas) 34,450.00 630.19
0.005 Kg Stempet 20,050.00 91.69
0.005 org Operator Alat Berat 43,000.00 196.65
0.005 org Pemb. Operator Alat Berat 35,000.00 160.06
0.005 org Pekerja 30,000.00 137.20
0.002 org Mandor 40,000.00 91.47
B.20 1 M3 PEK. GALIAN TANAH MAX KEDALAMAN 5 M' DENGAN ALAT EXAVATOR 0,7 M 8,784.33
0.006 unit Excavator 0,7 m3 500,000.00 2,990.21
0.921 liter Solar 4,500.00 4,144.43
0.024 liter Olie (minyak pelumas) 34,450.00 824.10
0.006 Kg Stempet 20,050.00 119.91
0.006 org Operator Alat Berat 43,000.00 257.16
0.006 org Pemb. Operator Alat Berat 35,000.00 209.31
0.006 org Pekerja 30,000.00 179.41
0.001 org Mandor 40,000.00 59.80
B.21 MENGANGKUT HASIL GALIAN DENGAN DUMP TRUCK . M3/KM. 4,904.36
0.0101 buah Dump Truck 250,000.00 2,515.18
0.2515 liter Solar 4,500.00 1,131.83
0.0101 liter Olie (minyak pelumas) 34,450.00 346.59
0.0050 Kg Stempet 20,050.00 100.86
0.0101 org Sopir 40,500.00 407.46
0.0101 org Pekerja 30,000.00 301.82
0.0025 org Mandor 40,000.00 100.61
B.22 1 M3. MENGANGKUT HASIL GALIAN EXAVATOR 0,7 M3 DENGAN DUMP TRUCK
KURANG DARI 1,5 KM. 6,688.05
0.0137 buah Dump Truck 250,000.00 3,429.94
0.3430 liter Solar 4,500.00 1,543.47
0.0137 liter Olie 34,450.00 472.65
0.0069 Kg Stempet 20,050.00 137.540.0137 org Sopir 40,500.00 555.65
0.0137 org Pekerja 30,000.00 411.59
0.0034 org Mandor 40,000.00 137.20
B.23 1 M3. MENGANGKUT HASIL GALIAN EXAVATOR 0,7 M3 DENGAN DUMP TRUCK
JARAK ANTARA 1,5 S/D 3 KM. 11,146.74
0.0229 buah Dump Truck 250,000.00 5,716.57
0.5717 liter Solar 4,500.00 2,572.46
0.0229 liter Olie 34,450.00 787.74
0.0114 Kg Stempet 20,050.00 229.23
0.0229 org Sopir 40,500.00 926.08
0.0229 org Pekerja 30,000.00 685.99
0.0057 org Mandor 40,000.00 228.66
B.24 1 M3. MENGANGKUT HASIL GALIAN EXAVATOR 0,7 M3 DENGAN DUMP TRUCK
JARAK ANTARA 3 S/D 5 KM. 15,605.44
0.0320 buah Dump Truck 250,000.00 8,003.20
0.8003 liter Solar 4,500.00 3,601.44
0.0320 liter Olie 34,450.00 1,102.84
0.0160 Kg Stempet 20,050.00 320.93
0.0320 org Sopir 40,500.00 1,296.52
0.0320 org Pekerja 30,000.00 960.38
0.0080 org Mandor 40,000.00 320.13
B.25 1 M3 MERATAKAN TANAH 9,618.75
0.2500 org Pekerja 30,000.00 7,500.00
0.0100 org Mandor 40,000.00 400.00
0.1250 lot Alat bantu 13,750.00 1,718.75
B.26 1 M3 PEK. URUGAN TANAH PILIHAN 93,275.00
1.2000 m3 Tanah pilihan 68,750.00 82,500.00
0.3000 org Pekerja 30,000.00 9,000.00
0.0100 org Mandor 40,000.00 400.00
0.1000 lot Alat bantu 13,750.00 1,375.00
B.27 1 M3 PEK. LAPISAN PUDEL 1 KP : 3 TL 148,100.00
0.2000 m3 Kapur padam 196,000.00 39,200.00
1.0000 m3 Tanah liat 55,000.00 55,000.00
1.0000 org Pekerja 30,000.00 30,000.00
0.5000 org Tukang batu 42,500.00 21,250.00
0.0500 org Kepala tukang batu 45,000.00 2,250.00
0.0100 org Mandor 40,000.00 400.00
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 19
-
7/30/2019 Analis RAB Gedung 2010
20/44
-
7/30/2019 Analis RAB Gedung 2010
21/44
C.4 1M3 Pasang Pondasi Batu Kosong 180,152.40
1.200 m3 Batu Belah 15/20 93,750.00 112,500.00
0.432 m3 Pasir Urug 61,950.00 26,762.40
. 0.700 OH Pekerja 30,000.00 21,000.00
0.390 OH Tukang Batu 42,500.00 16,575.00
0.039 OH Kepala Tukang 45,000.00 1,755.00
0.039 OH Mandor 40,000.00 1,560.00
C.5 1M3 Pasang Pondasi Siklop 60% Beton Camp. 1PC : 2PS : 3KR & 2,036,818.40
40% Batu Belah
0.480 m3 Batu Belah 15/20 93,750.00 45,000.00
126.000 Kg Besi Beton 11,100.00 1,398,600.00
194.000 Kg Portland Semen 1,312.50 254,625.00
0.312 m3 Pasir Beton (Cepu) 171,950.00 53,648.40
0.468 m3 Koral Beton 261,250.00 122,265.00
1.800 Kg Kawat Beton 17,850.00 32,130.00
3.000 OH Pekerja 30,000.00 90,000.00
0.850 OH Tukang Batu 42,500.00 36,125.00
0.085 OH Kepala Tukang 45,000.00 3,825.00
0.015 OH Mandor 40,000.00 600.00
C.6 1M3 Pasang Pondasi Sumuran diameter 100 cm 546,777.50
0.450 m3 Batu Belah 15/20 cm 93,750.00 42,187.50194.000 Kg Portland Semen 1,312.50 254,625.00
0.312 m3 Pasir Pasang 125,000.00 39,000.00
0.468 m3 Koral Beton 261,250.00 122,265.00
2.380 OH Pekerja 30,000.00 71,400.00
0.300 OH Tukang Batu 42,500.00 12,750.00
0.030 OH Kepala Tukang 45,000.00 1,350.00
0.080 OH Mandor 40,000.00 3,200.00
C.7 1M' Pembuatan Tiang Pancang (40x40) cm, Beton Bertulang 725,148.40
0.019 m3 Pasir Urug Darat 61,950.00 1,177.05
0.094 m3 Pasir Beton (Cepu) 171,950.00 16,163.30
0.150 m3 Koral Beton 261,250.00 39,187.50
60.500 Kg Portland Semen 1,312.50 79,406.25
45.000 Kg Besi Beton 11,100.00 499,500.000.900 Kg Kawat beton 17,850.00 16,065.00
0.032 m3 Kayu Kaso 5/7 48,415.49 1,549.30
0.120 Kg Paku 16,750.00 2,010.00
0.090 Lt Minyak Bekisting 22,000.00 1,980.00
0.240 Kg Plamuur Tembok 19,250.00 4,620.00
1.000 OH Pekerja 30,000.00 30,000.00
0.670 OH Tukang Batu 42,500.00 28,475.00
0.067 OH Kepala Tukang 45,000.00 3,015.00
0.050 OH Mandor 40,000.00 2,000.00
C.8 SEBUAH TIANG PANCANG DICINCIN DAN DILANCIPKAN (KAYU HUTAN) 10,912.50
0.1250 org Tukang Kayu 42,500.00 5,312.50
0.0125 org Kepala Tukang 45,000.00 562.50
0.1500 org Pekerja 30,000.00 4,500.00
0.0100 org Mandor 40,000.00 400.00
0.0100 lot alat bantu 13,750.00 137.50
C.9 1 M' TIANG DIPANCANGKAN DIDALAM TANAH LUNAK 57,737.50
0.0400 org Tukang Kayu 42,500.00 1,700.00
0.0040 org Kepala Tukang 45,000.00 180.00
1.8000 org Pekerja 30,000.00 54,000.00
0.0430 org Mandor 40,000.00 1,720.00
0.0100 lot alat bantu 13,750.00 137.50
C.10 1 M' TIANG DIPANCANGKAN DIDALAM TANAH BIASA 72,171.88
0.0500 org Tukang Kayu 42,500.00 2,125.00
0.0050 org Kepala Tukang 45,000.00 225.00
2.2500 org Pekerja 30,000.00 67,500.00
0.0538 org Mandor 40,000.00 2,150.000.0125 lot alat bantu 13,750.00 171.88
C.11 1 M' TIANG DIPANCANGKAN DIDALAM TANAH KERAS 86,606.25
0.0600 org Tukang Kayu 42,500.00 2,550.00
0.0060 org Kepala Tukang 45,000.00 270.00
2.7000 org Pekerja 30,000.00 81,000.00
0.0645 org Mandor 40,000.00 2,580.00
0.0150 lot alat bantu 13,750.00 206.25
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 21
-
7/30/2019 Analis RAB Gedung 2010
22/44
C.12 1 M' TIANG DIPANCANGKAN DIDALAM TANAH PASIR 115,475.00
0.0800 org Tukang Kayu 42,500.00 3,400.00
0.0080 org Kepala Tukang 45,000.00 360.00
3.6000 org Pekerja 30,000.00 108,000.00
0.0860 org Mandor 40,000.00 3,440.00
0.0200 lot alat bantu 13,750.00 275.00
C.13 1 M3 PASANGAN BATU BRONJONG UNTUK KAWAT 3 MM 356,263.33
1.2000 m3 Batu kali 91,900.00 110,280.008.3333 kg Kawat bronjong 18,550.00 154,583.33
0.6667 org penganyam 42,500.00 28,333.33
2.0333 org Pekerja 30,000.00 61,000.00
0.0517 org Mandor 40,000.00 2,066.67
C.14 1 M3 PASANGAN BATU BRONJONG UNTUK KAWAT 4 MM 484,763.33
1.2000 m3 Batu kali 91,900.00 110,280.00
15.0000 kg Kawat bronjong 18,550.00 278,250.00
0.7333 org penganyam 42,500.00 31,166.67
2.1000 org Pekerja 30,000.00 63,000.00
0.0517 org Mandor 40,000.00 2,066.67
C.15 1 M3 PASANGAN BATU BRONJONG UNTUK KAWAT 5 MM 645,596.67
1.2000 m3 Batu kali 91,900.00 110,280.00
23.3333 kg Kawat bronjong 18,550.00 432,833.33
0.8333 org penganyam 42,500.00 35,416.67
2.1667 org Pekerja 30,000.00 65,000.00
0.0517 org Mandor 40,000.00 2,066.67
IV D P E K E R J A A N D I N D I N G
D.1 1M2 Pasang Batu Merah Tebal 1/2 bata, 1 Pc : 2 Ps 73,671.88
70.0000 Buah Bata Merah 5 x 11 x 22 425.00 29,750.00
18.9500 Kg Portland Semen 1,312.50 24,871.88
0.0380 m3 Pasir Pasang 125,000.00 4,750.00
0.3000 OH Pekerja 30,000.00 9,000.00
0.1000 OH Tukang Batu 42,500.00 4,250.00
0.0100 OH Kepala Tukang 45,000.00 450.00
0.0150 OH Mandor 40,000.00 600.00
D.2 1M2 Pasang Batu Merah Tebal 1/2 bata, 1 Pc : 3 Ps 67,910.63
70.0000 Buah Bata Merah 5 x 11 x 22 425.00 29,750.00
14.3700 Kg Portland Semen 1,312.50 18,860.63
0.0400 m3 Pasir Pasang 125,000.00 5,000.00
0.3000 OH Pekerja 30,000.00 9,000.000.1000 OH Tukang Batu 42,500.00 4,250.00
0.0100 OH Kepala Tukang 45,000.00 450.00
0.0150 OH Mandor 40,000.00 600.00
D.3 1M2 Pasang Batu Merah Tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps 59,146.25
70.0000 Buah Bata Merah 5 x 11 x 22 425.00 29,750.00
4.5000 Kg Portland Semen 1,312.50 5,906.25
0.0500 m3 Pasir Pasang 125,000.00 6,250.00
0.0150 m3 Kapur Padam 196,000.00 2,940.00
0.3000 OH Pekerja 30,000.00 9,000.00
0.1000 OH Tukang Batu 42,500.00 4,250.00
0.0100 OH Kepala Tukang 45,000.00 450.00
0.0150 OH Mandor 40,000.00 600.00
D.4 1 M2 PASANGAN 1/2 BATA MERAH 1 : 4 65,118.75
70.0000 bh Bata merah 425.00 29,750.00
11.5000 kg P C (50 kg) 1,312.50 15,093.75
0.0430 m3 Pasir pasang 125,000.00 5,375.00
0.3200 org Pekerja 30,000.00 9,600.00
0.1000 org Tukang batu 42,500.00 4,250.00
0.0100 org Kepala tukang batu 45,000.00 450.00
0.0150 org Mandor 40,000.00 600.00
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 22
-
7/30/2019 Analis RAB Gedung 2010
23/44
-
7/30/2019 Analis RAB Gedung 2010
24/44
-
7/30/2019 Analis RAB Gedung 2010
25/44
-
7/30/2019 Analis RAB Gedung 2010
26/44
F.12 1M2 Membuat Pintu Teakwood Rangkap Lapis Formika Rangka ekspose 593,304.00
Kayu Bengkirai
0.0250 m3 Kayu Bengkirai, papan 8,937,500.00 223,437.50
0.0300 Kg Paku Biasa 1/2" - 1" 16,750.00 502.50
0.0800 Kg Lem Kayu 18,300.00 1,464.00
1.0000 Lbr Teakwood tebal 4 mm 98,550.00 98,550.00
0.5000 Lbr Formika 252,500.00 126,250.00
0.8000 OH Pekerja 30,000.00 24,000.00
2.5000 OH Tukang Kayu 42,500.00 106,250.00
0.2500 OH Kepala Tukang 45,000.00 11,250.00
0.0400 OH Mandor 40,000.00 1,600.00
F.13 1 M2 DAUN PINTU TRIPLEK DOUBLE UKURAN PINTU LAPIS ALUMINIUM ( KM/WC 456,611.00
0.0150 m3 Rangka kayu bengkirai (ram pintu) 9,625,000.00 144,375.00
1.0000 lbr Triplek 4 mm 72,300.00 72,300.00
1.2000 m2 Aluminium sheet 0,3 mm 130,680.00 156,816.00
0.2000 kg Paku triplek 16,750.00 3,350.00
0.5000 kg Lem putih ( FOX ) 18,300.00 9,150.00
0.3000 org Pekerja 30,000.00 9,000.00
1.3000 org Tukang kayu 42,500.00 55,250.00
0.1300 org Kepala tukang kayu 45,000.00 5,850.00
0.0130 org Mandor 40,000.00 520.00
F.14 1 M2 DAUN PINTU TRIPLEK DOUBLE UKURAN PINTU LAPIS FORMIKA ( KM/WC ) 442,085.00
0.0150 m3 Rangka kayu bengkirai (ram pintu) 9,625,000.00 144,375.00
1.0000 lbr Triplek 4 mm ukuran pintu 72,300.00 72,300.00
0.5000 lbr Formika 252,500.00 126,250.00
0.2000 kg Paku triplek 16,750.00 3,350.00
0.5000 kg Lem putih ( FOX ) 18,300.00 9,150.00
0.2000 kg Lem kuning ( aica aibon ) 50,200.00 10,040.00
0.5000 org Pekerja 30,000.00 15,000.00
1.3000 org Tukang kayu 42,500.00 55,250.00
0.1300 org Kepala tukang kayu 45,000.00 5,850.00
0.0130 org Mandor 40,000.00 520.00
F.15 1M3 Memasang Konstruksi Kuda-kuda Konvensional Kayu Bengkirai 11,607,900.00
Bentang 6 M1.1000 m3 Kayu Bengkirai, balok 9,625,000.00 10,587,500.00
15.0000 Kg Besi Strip 16,200.00 243,000.00
0.8000 Kg Paku Biasa 2" - 5" 16,750.00 13,400.00
4.0000 OH Pekerja 30,000.00 120,000.00
12.0000 OH Tukang Kayu 42,500.00 510,000.00
1.2000 OH Kepala Tukang 45,000.00 54,000.00
2.0000 OH Mandor 40,000.00 80,000.00
F.16 1M3 Memasang Konstruksi Kuda-kuda Ekspose Kayu Jati 19,240,675.00
1.1000 m3 Kayu Jati, balok 16,156,250.00 17,771,875.00
15.0000 Kg Besi Strip 16,200.00 243,000.00
5.6000 Kg Paku Biasa 2" - 5" 16,750.00 93,800.00
6.0000 OH Pekerja 30,000.00 180,000.00
20.0000 OH Tukang Kayu 42,500.00 850,000.00
2.0000 OH Kepala Tukang 45,000.00 90,000.00
0.3000 OH Mandor 40,000.00 12,000.00
F.17 1M3 Memasang Konstruksi Gording Kayu Bengkirai 10,539,700.00
1.1000 m3 Kayu Bengkirai, balok 8,937,500.00 9,831,250.00
15.0000 Kg Besi Strip 16,200.00 243,000.00
3.0000 Kg Paku Biasa 2" - 5" 16,750.00 50,250.00
2.4000 OH Pekerja 30,000.00 72,000.00
7.2000 OH Tukang Kayu 42,500.00 306,000.00
0.7200 OH Kepala Tukang 45,000.00 32,400.00
0.1200 OH Mandor 40,000.00 4,800.00
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 26
-
7/30/2019 Analis RAB Gedung 2010
27/44
F.18 1M2 Pasang Pintu Plywood & Formika Rangka Kayu Bengkirai 626,042.50
0.0196 m3 Kayu Bengkirai, papan 8,937,500.00 175,175.00
0.0300 Kg Paku Biasa 1/2" - 1" 16,750.00 502.50
0.3000 Kg Lem Kayu 18,300.00 5,490.00
0.5000 Lbr Plywood tebal 4 mm 98,550.00 49,275.00
1.0000 Lbr Formika 252,500.00 252,500.00
0.8000 OH Pekerja 30,000.00 24,000.00
2.5000 OH Tukang Kayu 42,500.00 106,250.00
0.2500 OH Kepala Tukang 45,000.00 11,250.00
0.0400 OH Mandor 40,000.00 1,600.00
F.19 1M2 Pasang Pintu Formika Double, Rangka Kayu Jati 844,375.00
0.0196 m3 Kayu Jati, papan 16,156,250.00 316,662.50
0.0300 Kg Paku Biasa 1/2" - 1" 16,750.00 502.50
1.2000 Kg Lem Kayu 18,300.00 21,960.00
1.0000 Lbr Plywood tebal 4 mm 98,550.00 98,550.00
1.0000 Lbr Formika 252,500.00 252,500.00
1.0000 OH Pekerja 30,000.00 30,000.00
2.6000 OH Tukang Kayu 42,500.00 110,500.00
0.2600 OH Kepala Tukang 45,000.00 11,700.00
0.0500 OH Mandor 40,000.00 2,000.00
F.20 1M2 Memasang Rangka Atap Genteng Keramik, Kayu Bengkirai 129,512.50
0.0086 m3 Kayu Klas II (Bengkirai), Kaso-kaso (5x7) cm 9,625,000.00 82,775.00
0.0036 m3 Reng (2x3) cm 9,625,000.00 34,650.00
0.2500 Kg Paku Biasa 2" - 5" 16,750.00 4,187.50
0.1000 OH Pekerja 30,000.00 3,000.00
0.1000 OH Tukang Kayu 42,500.00 4,250.00
0.0100 OH Kepala Tukang 45,000.00 450.00
0.0050 OH Mandor 40,000.00 200.00
F.21 1M2 Memasang Rangka Atap Genteng Beton, Kayu Bengkirai 136,442.50
0.0086 m3 Kayu Bengkirai Kaso-kaso (5x7) cm 9,625,000.00 82,775.00
0.0043 m3 Reng (2x3) cm 9,625,000.00 41,580.00
0.2500 Kg Paku Biasa 2" - 5" 16,750.00 4,187.50
0.1000 OH Pekerja 30,000.00 3,000.00
0.1000 OH Tukang Kayu 42,500.00 4,250.00
0.0100 OH Kepala Tukang 45,000.00 450.00
0.0050 OH Mandor 40,000.00 200.00
F.22 1M2 Pasang Rangka Atap Sirap Kayu Bengkirai 1,600,955.00
0.1650 m3 Kayu Bengkirai, balok 9,625,000.00 1,588,125.00
0.2000 Kg Paku Biasa 2" - 5" 16,750.00 3,350.00
0.1200 OH Pekerja 30,000.00 3,600.00
0.1200 OH Tukang Kayu 42,500.00 5,100.00
0.0120 OH Kepala Tukang 45,000.00 540.00
0.0060 OH Mandor 40,000.00 240.00
F.23 1M' Pasang Listplank Uk. (3x20)cm Kayu Bengkirai 78,850.00
0.0072 m3 Kayu Bengkirai, papan 8,937,500.00 64,350.00
0.1000 Kg Paku Biasa 2" - 5" 16,750.00 1,675.00
0.1000 OH Pekerja 30,000.00 3,000.00
0.2000 OH Tukang Kayu 42,500.00 8,500.00
0.0250 OH Kepala Tukang 45,000.00 1,125.00
0.0050 OH Mandor 40,000.00 200.00
F.24 1M' Pasang Listplank Uk. (3x30)cm Kayu Bengkirai 111,750.00
0.0110 m3 Kayu Bengkirai, papan 8,937,500.00 98,312.50
0.0500 Kg Paku Biasa 2" - 5" 16,750.00 837.50
0.1000 OH Pekerja 30,000.00 3,000.00
0.2000 OH Tukang Kayu 42,500.00 8,500.000.0200 OH Kepala Tukang 45,000.00 900.00
0.0050 OH Mandor 40,000.00 200.00
F.25 1M' Pasang Listplank Uk. 2x(3x20)cm Kayu Bengkirai 148,656.25
0.0145 m3 Kayu Bengkirai, papan 8,937,500.00 129,593.75
0.1500 Kg Paku Biasa 2" - 5" 16,750.00 2,512.50
0.1500 OH Pekerja 30,000.00 4,500.00
0.2500 OH Tukang Kayu 42,500.00 10,625.00
0.0250 OH Kepala Tukang 45,000.00 1,125.00
0.0075 OH Mandor 40,000.00 300.00
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 27
-
7/30/2019 Analis RAB Gedung 2010
28/44
F.26 1M2 Pasang Rangka Dinding Pemisah Kayu Bengkirai 281,612.50
0.0280 m3 Kayu Bengkirai, balok 8,937,500.00 250,250.00
0.1500 Kg Paku Biasa 2" - 5" 16,750.00 2,512.50
0.1500 OH Pekerja 30,000.00 4,500.00
0.4500 OH Tukang Kayu 42,500.00 19,125.00
0.0450 OH Kepala Tukang 45,000.00 2,025.00
0.0800 OH Mandor 40,000.00 3,200.00
F.27 1M2 Pas. Dinding Pemisah Teakwood Rangkap Rangka Kayu Bengkirai 373,733.50
0.0280 m3 Kayu Bengkirai, balok 8,937,500.00 250,250.00
0.1500 Kg Paku Biasa 2" - 5" 16,750.00 2,512.50
0.8600 Lbr Teakwood tebal 4mm 98,550.00 84,753.00
0.5600 Kg Lem kayu 18,300.00 10,248.00
0.1500 OH Pekerja 30,000.00 4,500.00
0.4500 OH Tukang Kayu 42,500.00 19,125.00
0.0450 OH Kepala Tukang 45,000.00 2,025.00
0.0080 OH Mandor 40,000.00 320.00
F.28 1M2 Pasang Dinding Lambriziring dari Papan jati 221,988.75
0.0070 m3 Kayu Jati, balok 16,156,250.00 113,093.75
0.1000 Kg Paku Biasa 2" - 5" 16,750.00 1,675.00
0.1500 Kg Paku Sekrup 3,5" 22,800.00 3,420.00
0.6000 OH Pekerja 30,000.00 18,000.00
1.8000 OH Tukang Kayu 42,500.00 76,500.00
0.1800 OH Kepala Tukang 45,000.00 8,100.00
0.0300 OH Mandor 40,000.00 1,200.00
F.29 1M2 Pasang Plywood tebal 4mm unt Dinding 52,122.00
0.4000 Lbr Plywood tebal 4mm 98,550.00 39,420.00
0.5000 Kg Paku Biasa 1/2" - 1" 16,750.00 8,375.00
0.0250 OH Pekerja 30,000.00 750.00
0.0750 OH Tukang Kayu 42,500.00 3,187.50
0.0075 OH Kepala Tukang 45,000.00 337.50
0.0013 OH Mandor 40,000.00 52.00
F.30 1M2 Pasang Dinding Bilik, Rangka Kayu Klas III / IV 80,107.00
1.5000 m2 Bilik Bambu 17,050.00 25,575.00
0.0140 m3 Kayu Klas III (Meranti) 3,437,500.00 48,125.00
0.0500 Kg Paku Biasa 1/2" - 1" 16,750.00 837.50
0.0030 m' List Kayu 2/4 6,500.00 19.50
0.1000 OH Pekerja 30,000.00 3,000.00
0.0500 OH Tukang Kayu 42,500.00 2,125.00
0.0050 OH Kepala Tukang 45,000.00 225.00
0.0050 OH Mandor 40,000.00 200.00
VII G PEKERJAAN PERKERASAN DAN BETON
G.1 1M3 Membuat Beton mutu f'c=7,4 Mpa (K100), slum (122)cm, w/c = 0,87 679,355.82
247.0000 Kg Portland Semen 1,312.50 324,187.50
0.6207 m3 Pasir Beton (Cepu) 171,950.00 106,731.82
0.7400 m3 Kerikil (maksimum 30 mm) 246,850.00 182,669.00
1.6500 OH Pekerja 30,000.00 49,500.00
0.2750 OH Tukang Batu 42,500.00 11,687.50
0.0280 OH Kepala Tukang 45,000.00 1,260.00
0.0830 OH Mandor 40,000.00 3,320.00
G.2 1M3 Membuat Beton mutu f'c=9,8 Mpa (K125), slum (122)cm, w/c = 0,78 735,932.22
276.0000 Kg Portland Semen 1,312.50 362,250.00
0.5914 m3 Pasir Beton (Cepu) 171,950.00 101,696.14
0.7496 m3 Kerikil (maksimum 30 mm) 246,850.00 185,046.07
1.6500 OH Pekerja 30,000.00 70,125.000.2750 OH Tukang Batu 42,500.00 12,375.00
0.0280 OH Kepala Tukang 45,000.00 1,120.00
0.0830 OH Mandor 40,000.00 3,320.00
G.3 1M3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum (122)cm, w/c = 0,72 742,299.65
299.0000 Kg Portland Semen 1,312.50 392,437.50
0.5707 m3 Pasir Beton (Cepu) 171,950.00 98,134.32
0.7533 m3 Kerikil (maksimum 30 mm) 246,850.00 185,960.33
1.6500 OH Pekerja 30,000.00 49,500.00
0.2750 OH Tukang Batu 42,500.00 11,687.50
0.0280 OH Kepala Tukang 45,000.00 1,260.00
0.0830 OH Mandor 40,000.00 3,320.00
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 28
-
7/30/2019 Analis RAB Gedung 2010
29/44
G.4 1M3 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,8 644,983.39
230.0000 Kg Portland Semen 1,312.50 301,875.00
0.6379 m3 Pasir Beton (Cepu) 171,950.00 109,679.54
0.7607 m3 Kerikil (maksimum 30 mm) 246,850.00 187,788.85
1.2000 OH Pekerja 30,000.00 36,000.00
0.2000 OH Tukang Batu 42,500.00 8,500.00
0.0200 OH Kepala Tukang 45,000.00 900.00
0.0060 OH Mandor 40,000.00 240.00
G.5 1M3 Membuat Beton mutu f'c=14,5 MPa (K175), slum (122)cm, w/c = 0,66 773,823.84
326.0000 Kg Portland Semen 1,312.50 427,875.00
0.5429 m3 Pasir Beton (Cepu) 171,950.00 93,344.29
0.7622 m3 Kerikil (maksimum 30 mm) 246,850.00 188,154.56
1.6500 OH Pekerja 30,000.00 49,500.00
0.2500 OH Tukang Batu 42,500.00 10,625.00
0.0250 OH Kepala Tukang 45,000.00 1,125.00
0.0800 OH Mandor 40,000.00 3,200.00
G.6 1M3 Membuat Beton mutu f'c=16,9 MPa (K200), slum (122)cm,w/c = 0,61 804,752.72
352.0000 Kg Portland Semen 1,312.50 462,000.00
0.5221 m3 Pasir Beton (Cepu) 171,950.00 89,782.46
0.7637 m3 Kerikil (maksimum 30 mm) 246,850.00 188,520.26
1.6500 OH Pekerja 30,000.00 49,500.00
0.2500 OH Tukang Batu 42,500.00 10,625.00
0.0250 OH Kepala Tukang 45,000.00 1,125.00
0.0800 OH Mandor 40,000.00 3,200.00
G.7 1M3 Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 828,562.75
371.0000 Kg Portland Semen 1,312.50 486,937.50
0.4986 m3 Pasir Beton (Cepu) 171,950.00 85,729.36
0.7756 m3 Kerikil (maksimum 30 mm) 246,850.00 191,445.89
1.6500 OH Pekerja 30,000.00 49,500.00
0.2500 OH Tukang Batu 42,500.00 10,625.00
0.0250 OH Kepala Tukang 45,000.00 1,125.00
0.0800 OH Mandor 40,000.00 3,200.00
G.8 1M3 Membuat Beton mutu f'c=21,7 MPa (K250), slum (122)cm,w/c = 0,56 911,379.90
384.0000 Kg Portland Semen 1,312.50 504,000.00
0.4943 m3 Beton (Muntilan) 309,430.00 152,946.83
0.7696 m3 Kerikil (maksimum 30 mm) 246,850.00 189,983.07
1.6500 OH Pekerja 30,000.00 49,500.00
0.2500 OH Tukang Batu 42,500.00 10,625.00
0.0250 OH Kepala Tukang 45,000.00 1,125.00
0.0800 OH Mandor 40,000.00 3,200.00
G.9 1M3 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (122)cm, w/c = 936,109.66
406.0000 Kg Portland Semen 1,312.50 532,875.00
0.4886 m3 Beton (Muntilan) 309,430.00 151,178.66
0.7600 m3 Kerikil (maksimum 30 mm) 246,850.00 187,606.00
1.6500 OH Pekerja 30,000.00 49,500.00
0.2500 OH Tukang Batu 42,500.00 10,625.00
0.0250 OH Kepala Tukang 45,000.00 1,125.00
0.0800 OH Mandor 40,000.00 3,200.00
G.10 1M3 Membuat Beton mutu f'c=26,4 MPa (K300), slum (122)cm,w/c = 0,52 943,719.83
413.0000 Kg Portland Semen 1,312.50 542,062.50
0.4864 m3 Beton (Muntilan) 309,430.00 150,515.59
0.7563 m3 Kerikil (maksimum 30 mm) 246,850.00 186,691.74
1.6500 OH Pekerja 30,000.00 49,500.00
0.2500 OH Tukang Batu 42,500.00 10,625.00
0.0250 OH Kepala Tukang 45,000.00 1,125.00
0.0800 OH Mandor 40,000.00 3,200.00
G.11 1M3 Membuat Beton mutu f'c=28,8 MPa (K325), slum (122)cm,w/c = 0,49 991,870.82
439.0000 Kg Portland Semen 1,312.50 576,187.50
0.4786 m3 Beton (Muntilan) 309,430.00 148,084.36
0.7452 m3 Kerikil (maksimum 30 mm) 246,850.00 183,948.96
2.1000 OH Pekerja 30,000.00 63,000.00
0.3500 OH Tukang Batu 42,500.00 14,875.00
0.0350 OH Kepala Tukang 45,000.00 1,575.00
0.1050 OH Mandor 40,000.00 4,200.00
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 29
-
7/30/2019 Analis RAB Gedung 2010
30/44
-
7/30/2019 Analis RAB Gedung 2010
31/44
-
7/30/2019 Analis RAB Gedung 2010
32/44
G.26 1 M3 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting) 4,066,433.00
0.2700 m3 Kayu Terentang 2,062,500.00 556,875.00
2.0000 Kg Paku Biasa 2" - 5" 16,750.00 33,500.00
0.6000 Ltr Minyak Bekisting 22,000.00 13,200.00
210.0000 Kg Besi Beton Polos 11,100.00 2,331,000.00
3.0000 Kg Kawat Beton 17,850.00 53,550.00
336.0000 Kg Portland Semen 1,312.50 441,000.00
0.5400 m3 Pasir Beton (Cepu) 171,950.00 92,853.00
0.8100 m3 Koral Beton 261,250.00 211,612.50
5.6500 OH Pekerja 30,000.00 169,500.00
0.2750 OH Tukang batu 42,500.00 11,687.50
1.5600 OH Tukang Kayu 42,500.00 66,300.00
1.4000 OH Tukang Besi 42,500.00 59,500.00
0.3230 OH Kepala Tukang 45,000.00 14,535.00
0.2830 OH Mandor 40,000.00 11,320.00
G.27 1 M3 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting) 7,375,933.00
0.4000 m3 Kayu Terentang 2,062,500.00 825,000.00
4.0000 Kg Paku Biasa 2" - 5" 16,750.00 67,000.00
2.0000 Ltr Minyak Bekisting 22,000.00 44,000.00
315.0000 Kg Besi Beton Polos 11,100.00 3,496,500.00
4.5000 Kg Kawat Beton 17,850.00 80,325.00
336.0000 Kg Portland Semen 1,312.50 441,000.00
0.5400 m3 Pasir Beton (Cepu) 171,950.00 92,853.00
0.8100 m3 Koral Beton 261,250.00 211,612.50
0.1500 m3 Kayu Balok 3,437,500.00 515,625.00
3.5000 Lbr Plywood 9 mm 135,200.00 473,200.00
20.0000 Btg Dolken diameter 8 / 4mm 35,700.00 714,000.00
7.0500 OH Pekerja 30,000.00 211,500.00
0.2750 OH Tukang batu 42,500.00 11,687.50
1.6500 OH Tukang Kayu 42,500.00 70,125.00
2.1000 OH Tukang Besi 42,500.00 89,250.00
0.4030 OH Kepala Tukang 45,000.00 18,135.00
0.3530 OH Mandor 40,000.00 14,120.00
G.28 1 M3 Membuat Balok Beton Bertulang (200 kg Besi + Bekisting) 5,740,743.00
0.3200 m3 Kayu Terentang 2,062,500.00 660,000.00
3.2000 Kg Paku Biasa 2" - 5" 16,750.00 53,600.00
1.6000 Ltr Minyak Bekisting 22,000.00 35,200.00
210.0000 Kg Besi Beton Polos 11,100.00 2,331,000.00
3.0000 Kg Kawat Beton 17,850.00 53,550.00
336.0000 Kg Portland Semen 1,312.50 441,000.00
0.5400 m3 Pasir Beton (Cepu) 171,950.00 92,853.00
0.8100 m3 Koral Beton 261,250.00 211,612.50
0.1400 m3 Kayu Balok 3,437,500.00 481,250.00
2.8000 Lbr Plywood 9 mm 135,200.00 378,560.00
18.0000 Btg Dolken diameter 8 / 4mm 35,700.00 642,600.00
6.3500 OH Pekerja 30,000.00 190,500.00
0.2750 OH Tukang batu 42,500.00 11,687.50
1.6500 OH Tukang Kayu 42,500.00 70,125.001.4000 OH Tukang Besi 42,500.00 59,500.00
0.3330 OH Kepala Tukang 45,000.00 14,985.00
0.3180 OH Mandor 40,000.00 12,720.00
G.29 1 M3 Membuat Balok Beton Bertulang (150 kg Besi + Bekisting) 5,509,225.50
0.3200 m3 Kayu Terentang 2,062,500.00 660,000.00
3.2000 Kg Paku Biasa 2" - 5" 16,750.00 53,600.00
1.6000 Ltr Minyak Bekisting 22,000.00 35,200.00
157.5000 Kg Besi Beton Polos 11,100.00 1,748,250.00
2.2500 Kg Kawat Beton 17,850.00 40,162.50
336.0000 Kg Portland Semen 1,312.50 441,000.00
0.5400 m3 Pasir Beton (Cepu) 171,950.00 92,853.00
0.8100 m3 Koral Beton 261,250.00 211,612.50
0.1200 m3 Kayu Balok 3,437,500.00 412,500.002.8000 Lbr Plywood 9 mm 135,200.00 378,560.00
32.0000 Btg Dolken diameter 8 / 4mm 35,700.00 1,142,400.00
5.3000 OH Pekerja 30,000.00 159,000.00
0.2750 OH Tukang batu 42,500.00 11,687.50
1.3000 OH Tukang Kayu 42,500.00 55,250.00
1.0500 OH Tukang Besi 42,500.00 44,625.00
0.2650 OH Kepala Tukang 45,000.00 11,925.00
0.2650 OH Mandor 40,000.00 10,600.00
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 32
-
7/30/2019 Analis RAB Gedung 2010
33/44
-
7/30/2019 Analis RAB Gedung 2010
34/44
G.35 1 M3 PAS. BETON K-225 READY MIX 6 M3 BERIKUT SLANG 1,044,018.75
1.0000 m3 Adukan K-225 Ready Mix 952,875.00 952,875.00
2.5000 org Pekerja 30,000.00 75,000.00
0.2500 org Tukang batu 42,500.00 10,625.00
0.1000 org Kepala tukang batu 45,000.00 4,500.00
0.0100 org Mandor 40,000.00 400.00
0.0450 lot Alat bantu (Slang + Tes Lab.) 13,750.00 618.75
G.36 1 M3 PAS. BETON K-300 READY MIX 6 M3 BERIKUT SLANG 1,085,393.75
1.0000 m3 Adukan K-300 Ready Mix 994,250.00 994,250.00
2.5000 org Pekerja 30,000.00 75,000.00
0.2500 org Tukang batu 42,500.00 10,625.00
0.1000 org Kepala tukang batu 45,000.00 4,500.00
0.0100 org Mandor 40,000.00 400.00
0.0450 lot Alat bantu (Slang + Tes Lab.) 13,750.00 618.75
G.37 1 KG PEK. ERECTION KONST. KUDA-KUDA BESI 906.30
0.0010 org Pekerja 30,000.00 30.00
0.0010 org Tukang besi profil 42,500.00 42.50
0.0002 org Kepala tukang besi profil 45,000.00 9.00
0.0001 org Mandor 40,000.00 4.00
0.0002 org Operator alat berat 43,000.00 8.60
0.0200 org Pembantu operator 35,000.00 700.00
0.0002 ls Sewa alat 150,000.00 30.000.0100 lt Bahan Bakar solar 4,500.00 45.00
0.0010 lt Pelumas 34,450.00 34.45
0.0002 lot Alat bantu 13,750.00 2.75
G.38 1 KG PEKERJAAN BAJA IWF 44,140.00
1.1000 kg Besi IWF 19,400.00 21,340.00
0.0600 org Pekerja 30,000.00 1,800.00
0.0300 org Tukang besi profil 42,500.00 1,275.00
0.0150 org Kepala tukang besi profil 45,000.00 675.00
0.0075 org Mandor 40,000.00 300.00
0.1250 lot Peralatan (oksigen,solar,elpiji,kawat las) 150,000.00 18,750.00
G.39 1 KG PEKERJAAN KONSTUKSI BESI SIKU / PROFIL 43,150.00
1.1000 kg Besi profil/besi siku 18,500.00 20,350.00
0.0600 org Pekerja 30,000.00 1,800.000.0300 org Tukang besi profil 42,500.00 1,275.00
0.0150 org Kepala tukang besi profil 45,000.00 675.00
0.0075 org Mandor 40,000.00 300.00
0.1250 lot Peralatan (oksigen,solar,elpiji,kawat las) 150,000.00 18,750.00
G.40 1 CM PEK. PENGELASAN DENGAN LAS LISTRIK TEBAL KAWAT 4 MM 39,930.30
0.0400 kg Kawat las listrik 33,000.00 1,320.00
0.0300 lt Bahan bakar solar 4,500.00 135.00
0.0040 lt Pelumas 34,450.00 137.80
0.0100 org Pekerja 30,000.00 300.00
0.0050 org Tukang besi profil 42,500.00 212.50
0.0050 org Kepala tukang besi profil 45,000.00 225.00
0.0025 org Mandor 40,000.00 100.00
0.2500 lot Alat bantu (mesin las listrik) 150,000.00 37,500.00
G.41 1 TITIK MELUBANG KONSTRUKSI BESI DENGAN BOR 40,025.00
0.0500 org Pekerja 30,000.00 1,500.00
0.0200 org Tukang besi profil 42,500.00 850.00
0.0030 org Kepala tukang besi profil 45,000.00 135.00
0.0010 org Mandor 40,000.00 40.00
0.2500 lot Alat bantu (mesin bor listrik) 150,000.00 37,500.00
G.42 1 M2 PEKERJAAN WIREMESH M8 83,213.50
1.0100 m2 Wiremesh M8 72,600.00 73,326.00
0.1000 kg Kawat las listrik 33,000.00 3,300.00
0.1000 org Pekerja 30,000.00 3,000.00
0.0750 org Tukang besi profil 42,500.00 3,187.50
0.0100 org Mandor 40,000.00 400.00
VIII H PEKERJAAN PENUTUP ATAP
H.1 1 M2 Pasang Atap Genteng Mantili Kecil 33,367.50
25.0000 Buah Genteng mantili 1,000.00 25,000.00
0.1500 OH Pekerja 30,000.00 4,500.00
0.0750 OH Tukang Kayu 42,500.00 3,187.50
0.0080 OH Kepala Tukang 45,000.00 360.00
0.0080 OH Mandor 40,000.00 320.00
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 34
-
7/30/2019 Analis RAB Gedung 2010
35/44
H.2 1 M2 Pasang Atap Genteng Mantili Besar 31,640.00
20.0000 Buah Genteng Mantili Besar 1,200.00 24,000.00
0.1500 OH Pekerja 30,000.00 4,500.00
0.0600 OH Tukang Kayu 42,500.00 2,550.00
0.0060 OH Kepala Tukang 45,000.00 270.00
0.0080 OH Mandor 40,000.00 320.00
H.3 1 M' Pasang Genteng Bubung Mantili 50,480.00
5.0000 Buah Genteng Bubung Mantili 2,900.00 14,500.00
8.0000 Kg Portland Semen 1,312.50 10,500.00
0.0320 m3 Pasir Pasang 125,000.00 4,000.00
0.4000 OH Pekerja 30,000.00 12,000.00
0.2000 OH Tukang Batu 42,500.00 8,500.00
0.0200 OH Kepala Tukang 45,000.00 900.00
0.0020 OH Mandor 40,000.00 80.00
H.4 1 M2 Pasang Atap Asbes Gelombang (80 x 210 cm) x 5 mm 38,577.50
0.6000 Lbr Asbes Gelombang 45,850.00 27,510.00
0.1200 Kg Paku Pancing 60 x 230 25,000.00 3,000.00
0.1400 OH Pekerja 30,000.00 4,200.00
0.0750 OH Tukang Kayu 42,500.00 3,187.500.0080 OH Kepala Tukang 45,000.00 360.00
0.0080 OH Mandor 40,000.00 320.00
H.5 1 M2 Pasang Atap Genteng Beton 41,852.50
11.0000 bh Genteng Beton Standrad 2,750.00 30,250.00
0.0300 Kg Paku Biasa 2" - 5" 16,750.00 502.50
0.2000 OH Pekerja 30,000.00 6,000.00
0.1000 OH Tukang Kayu 42,500.00 4,250.00
0.0100 OH Kepala Tukang 45,000.00 450.00
0.0100 OH Mandor 40,000.00 400.00
H.6 1 M2 Pasang Atap Sirap 175,770.00
60.0000 Lbr Genteng Sirap 2,589.50 155,370.00
0.2000 Kg Paku Biasa 1/2" - 1" 16,750.00 3,350.00
0.1660 OH Pekerja 30,000.00 4,980.00
0.2500 OH Tukang Kayu 42,500.00 10,625.00
0.0250 OH Kepala Tukang 45,000.00 1,125.00
0.0080 OH Mandor 40,000.00 320.00
H.7 1 M' Pasang Nok Genteng Beton 72,975.00
3.5000 Buah Nok Genteng Beton 9,075.00 31,762.50
0.0500 Kg Paku Biasa 2" - 5" 16,750.00 837.50
10.8000 Kg Portland Semen 1,312.50 14,175.00
0.0320 m3 Pasir Pasang 125,000.00 4,000.00
0.4000 OH Pekerja 30,000.00 12,000.00
0.2000 OH Tukang Batu 42,500.00 8,500.00
0.0200 OH Kepala Tukang 45,000.00 900.00
0.0200 OH Mandor 40,000.00 800.00
H.8 1 M' Pasang Nok Sirap 58,457.93
0.4000 Lbr Seng Plaat 3" x 6" BJLS 28 81,200.00 32,480.00
0.0600 Kg Paku Biasa 1/2" - 1" 16,750.00 1,005.00
0.5000 Kg Paku Biasa 2" - 5" 16,750.00 8,375.00
0.0040 m3 Kayu Bengkirai Papan Tebal 3 cm 214,482.84 857.93
0.1250 OH Pekerja 30,000.00 3,750.00
0.2500 OH Tukang Kayu 42,500.00 10,625.00
0.0250 OH Kepala Tukang 45,000.00 1,125.00
0.0060 OH Mandor 40,000.00 240.00
H.9 1 M2 Pasang Atap Seng Gelombang 63,835.000.7000 Lbr Seng Gelombang 3" x 6" BJLS 28 81,200.00 56,840.00
0.0200 Kg Paku Biasa 1/2" - 1" 16,750.00 335.00
0.1200 OH Pekerja 30,000.00 3,600.00
0.0600 OH Tukang Kayu 42,500.00 2,550.00
0.0060 OH Kepala Tukang 45,000.00 270.00
0.0060 OH Mandor 40,000.00 240.00
\\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 35
-
7/30/2019 Analis RAB Gedung 2010
36/44
-
7/30/2019 Analis RAB Gedung 2010
37/44
J.2 1 UNIT Memasang Closet Jongkok 300,525.00
1.0000 Buah Kloset Jongkok 123,750.00 123,750.00
6.0000 Kg Portland Semen 1,312.50 7,875.00
0.0100 m3 Pasir Pasang 125,000.00 1,250.00
1.0000 OH Pekerja 30,000.00 30,000.00
1.5000 OH Tukang Batu 42,500.00 63,750.00
1.5000 OH Kepala Tukang 45,000.00 67,500.00
0.1600 OH Mandor 40,000.00 6,400.00
J.3 1 UNIT Memasang Wastafel 714,572.50
1.0000 Buah Wastafel 501,950.00 501,950.00
0.3000 - Perlengkapan 30% Harga Wastafel 501,950.00 150,585.00
6.0000 Kg Portland Semen 1,312.50 7,875.00
0.0100 m3 Pasir Pasang 125,000.00 1,250.00
1.2000 OH Pekerja 30,000.00 36,000.00