    (Rp)

    1 P e k e r j a Hr 30,000.00

    2 M a n d o r Hr 40,000.00

    3 T u k a n g K a y u Hr 42,500.00

    4 T u k a n g B a t u Hr 42,500.00

    5 T u k a n g B e s i Hr 42,500.00

    6 T u k a n g C a t Hr 42,500.00

    7 T u k a n g L e i d e n g Hr 42,500.00

    8 T u k a n g G a l i Hr 40,000.00

    9 T u k a n g P l i t u r Hr 40,000.00

    10 T u k a n g K e p a l a Hr 43,000.00

    11 K e p . T u k a n g K a y u Hr 45,000.00

    12 K e p . T u k a n g B a t u Hr 45,000.00

    13 K e p . T u k a n g C a t Hr 45,000.00

    14 K e p . T u k a n g P l i t u r Hr 45,000.00

    15 K e p . T u k a n g G a l i Hr 45,000.00

    16 M e k a n i k Hr 37,500.00

    17 P e m b . M e k a n i k Hr 37,500.00

    18 Operator alat berat Hr 43,000.00

    19 P e m b . Operator Hr 35,000.0020 S o p i r Hr 40,500.00

    21 P e m b . Sopir Hr 30,000.00

    Rembang, Juli 2009

    KEPALA DINAS PEKERJAAN UMUM

    KABUPATEN REMBANG

    Ir. MUJOKO, MT.NIP. 010 234 645 / 19620715 199011 1 002

    DAFTAR HARGA SATUAN UPAH

    NO. JENIS PEKERJAAN SATUAN KETERANGAN

    DINAS PEKERJAAN UMUM KABUPATEN REMBANG

    TAHUN 2010

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office

  • 7/30/2019 Analis RAB Gedung 2010

    2/44

    EDISI SEPTEMBER 2009

    HARGA

    NO. SATUAN KET.

    1 3 4 5

    I B A H A N D A S A R1 BATU KALI Bulat Utuh m3 91,900

    Bulat Belah m3 93,750

    Pecah 5/7 m3 135,850

    Pecah 3/5 m3 208,550

    Tempel m2 68,750

    Batu apung kg 6,050

    2 KERIKIL Sawur / Koral m3 27,500

    Beton 0,5 / 1 m3 261,250

    Beton 1 / 1 m4 238,400

    Beton 1 / 2 m3 248,950

    Beton 2 / 3 m3 246,850

    Biasa m3 28,450

    3 BATU BATA Ex lokal I bh 425

    4 PASIR Urug m3 61,950Pasang m3 125,000

    Beton (Muntilan) m3 309,430

    Beton (Cepu) m3 171,950

    Sirtu (pasir batu) m3 106,600

    Sirtu royalty m3 27,300

    Grosok m3 103,200

    Abu batu m3 116,950

    Abu batu (Tayu) m3 211,200

    Batu alam m2 90,100

    5 TANAH Padas m3 33,650

    Liat m3 55,000

    Biasa m3 49,950

    Pilihan m3 68,750

    6 KAPUR Pasang (padam) m3 196,000Labor Kg 2,750

    7 PORTLAND CEMENT

    PC 50 kg zak 65,625

    PC 40 kg zak 51,250

    PC 50 kg Sm. Warna zak 89,450

    Semen warna kg 11,250

    7 BETON Adukan beton K 175 ready mix m3 897,850

    Adukan beton K 225 ready mix m3 952,875

    Adukan beton K 300 ready mix m3 994,250

    II B A H A N P E N U T U P A T A P

    1 SIRAP (100 lbr) pak 258,950

    2 GENTENG BETON Genteng Beton Warna standard bh 2,750

    Kerpus Beton Warna Standard bh 9,075

    3 GENTENG TANAH LIAT

    Mantili bh 1,000

    Nok kerpus Mantili bh 2,900

    Plentong Mantili besar bh 1,200

    Genteng biasa bh 650

    Genteng pres bh 1,000

    Genteng Beton bh 4,400

    Genteng keramik bh 11,100

    Sirap bh 6,300

    Genteng kerpus jatiwangi bh 10,550

    Genteng kerpus lokal bh 3,200

    Genteng kerpus Beton bh 9,075

    Genteng kerpus keramik bh 19,350

    Genteng Jatiwangi bh 3,8505 ASBES GELOMBANG

    Asbes gelombang ( 80 x 210 ) cm bh 45,850

    Asbes gel. Kecil 5 mm (90 x 180) lbr 53,850

    Asbes gel. Kecil 5 mm (120 x 240) lbr 80,850

    Asbes gel. Besar 5 mm (90 x 180) lbr 68,750

    Asbes gel. Besar 5 mm (120 x 240) lbr 105,950

    Asbes gel. Kecil 0,8 x 1,80 m lbr 47,750

    Asbes gel. Kecil 0,8 x 2,40 m lbr 61,950

    DAFTAR HARGA SATUAN BAHAN

    2

    J E N I S B A H A N

    DINAS PEKERJAAN UMUM KABUPATEN REMBANG

    TAHUN 2010

    (Rp)

    144824707.xls.ms_office

  • 7/30/2019 Analis RAB Gedung 2010

    3/44

    HARGA

    NO. SATUAN KET.

    1 3 4 52

    J E N I S B A H A N(Rp)

    6 ASBES PLAT

    - 100cm X 100 cm X 5 mm bh 19,050

    - 100cm X 200 cm X 5 mm bh 52,800

    - 100cm X 240 cm X 5 mm bh 67,750

    Sekrup asbes bh 1,450

    7 SENG PLAT

    BJLS 0,30 panjang 180 cm m' 54,850

    BJLS 0,30 panjang 240 cm m' 71,225

    BWG 28 x 80 m' 42,075

    BWG 28 x 90 m' 47,200

    8 SENG GELOMBANG

    Seng gel. Kecil 0,70 x 1,80 m lbr 54,700

    Seng gel. Kecil 0,70 x 2,10 m lbr 63,150

    BJLS 0,28 m' 81,200

    BJLS 0,28 panjang 180 cm lbr 48,200

    BJLS 0,28 panjang 240 cm lbr 64,700

    9 SENG TALANG

    Seng talang BJLS 26 lebar 0,60 m' 23,450

    Seng talang BJLS 26 lebar 0,90 m' 33,450

    Seng talang BJLS 26 lebar 1,20 m' 50,850

    III . B A H A N K A Y U

    1 JATI Papan m3 16,156,250

    Balok/pesagen m3 16,156,250

    2 KAMPER Papan m3 8,937,500

    Balok/pesagen m3 8,937,500

    3 KRUING Papan m3 6,531,250

    Balok/pesagen m3 6,531,250

    4 MERANTI Papan m3 3,437,500

    Balok/pesagen m3 3,437,500

    5 LANAN Papan m3 3,437,500

    Balok/pesagen m3 3,437,500

    6 BENGKIRAI Papan m3 8,937,500

    Balok/pesagen m3 9,625,000

    7 DOLKEN Kayu dolken sengon 8-10 cm,4m. bt 35,700

    Kayu perancah m3 2,062,500

    8 LAIN-LAIN

    Kayu randu (papan) m3 631,300

    Bambu bt 17,050

    Bambu Apus bt 4,200

    Kayu hutan lokal sekwalitas Kruing ( m3 4,855,125

    Kayu hutan lokal sekwalitas Kruing ( m3 2,589,400

    Glugu m' 206,250

    Kayu lis 2/3 m' 6,500

    IV . BAHAN PENUTUP DINDING / LANTAI

    1 UBIN (TEGEL BIASA)

    PC polos 30 X 30 cm m2 31,050

    20 X 20 cm m2 23,900

    20 X 20 cm Warna m2 28,750

    2 KERAMIK

    Keramik warna (KW-1) 30 X 30 cm m2 48,750

    Keramik warna (KW-2) 30 X 30 cm m2 44,450

    Keramik putih (KW-1) 30 X 30 cm m2 39,850

    Keramik putih (KW-2) 30 X 30 cm m2 36,100

    Keramik 10 x 20 cm m2 55,650

    Keramik 20 x 20 cm m2 48,200

    Keramik 20 x 25 cm m2 52,900

    Keramik 10 x 20 cm m2 43,7003 MARMER

    Marmer Tulung Agung m2 607,450

    Marmer Kalimantan m2 1,019,425

    Marmer Itali m2 1,381,100

    144824707.xls.ms_office

  • 7/30/2019 Analis RAB Gedung 2010

    4/44

    HARGA

    NO. SATUAN KET.

    1 3 4 52

    J E N I S B A H A N(Rp)

    4 GRANITO

    Granito 40 x 40 polished (lokal) m2 462,825

    Granito 40 x 40 polished (import) m2 505,000

    Granito 60 x 60 polished (lokal) m2 461,000

    Granito 60 x 60 polished (import) m2 481,250

    5 GRANIT

    Granit lokal m2 131,300

    Granit import m2 241,800

    Batu Tempel m2 67,375

    V . B A H A N C E T A K

    1 BUIS BETON O dan U

    15 cm - 100 cm bh 39,050

    20 cm - 100 cm bh 55,000

    25 cm - 100 cm bh 58,550

    30 cm - 100 cm bh 68,750

    40 cm - 100 cm bh 86,600

    50 cm - 100 cm bh 108,050

    60 cm - 100 cm bh 128,600

    80 cm - 100 cm bh 195,250

    100 cm - 100 cm bh 321,450U 15 cm - 100 cm bh 54,000

    U 20 cm - 100 cm bh 42,450

    U 30 cm - 100 cm bh 52,250

    VI . B A H A N B E S I

    1 BESI BETON

    Besi beton polos kg 11,100

    Besi beton prestress kg 18,550

    Besi beton ulir kg 15,200

    2 BESI PLAT

    Besi Strip kg 16,200

    3 BAJA

    Baja profil " L" dan "C" kg 18,500

    Baja profil "IWF" kg 19,400

    4 KAWAT

    Kawat Ikat beton/bendrat kg 17,850

    Kawat bronjong kg 18,550

    Kawat las listrik kg 33,000

    VII . B A H A N P I P A

    1 Pipa PVC SII SCJ , S - 12,5 (10 bar)

    Pipa PVC. S. 12,5 1/2" m' 4,500

    Pipa PVC. S. 12,5 3/4" m' 6,600

    Pipa PVC. S. 12,5 1" m' 11,275

    Pipa PVC. S. 12,5 1-1/4" m' 14,300

    Pipa PVC. S. 12,5 1-1/2" m' 22,250

    Pipa PVC. S. 12,5 2" m' 33,550Pipa PVC. S. 12,5 2-1/2" m' 48,125

    Pipa PVC. S. 12,5 3" m' 68,900

    Pipa PVC. S. 12,5 4" m' 102,900

    Pipa PVC. S. 12,5 5" m' 169,800

    Pipa PVC. S. 12,5 6" m' 220,450

    Pipa PVC. S. 12,5 8" m' 348,300

    Pipa PVC. S. 12,5 10" m' 549,450

    Pipa PVC. S. 12,5 12" m' 875,700

    Pipa PVC. S. 12,5 16" m' 1,476,250

    2 Pipa Medium B Galvanis - SII

    Pipa Galvanis ( 1" ) m' 119,300

    Pipa Galvanis ( 1 1/2" ) m' 162,050

    Pipa Galvanis ( 2" ) m' 303,700

    VIII . B A H A N L A N G I T - L A N G I TPLY WOOD

    - Teak wood

    120 X 240 X 4 mm lbr 98,550

    - Tripleks

    120 X 240 X 3 mm lbr 55,800

    120 X 240 X 4 mm lbr 72,300

    120 X 240 X 6 mm lbr 91,950

    - Multipleks

    . 120 X 240 X 9 mm lbr 135,200

    . 120 X 240 X 12 mm lbr 202,850

    144824707.xls.ms_office

  • 7/30/2019 Analis RAB Gedung 2010

    5/44

  • 7/30/2019 Analis RAB Gedung 2010

    6/44

    HARGA

    NO. SATUAN KET.

    1 3 4 52

    J E N I S B A H A N(Rp)

    XIV . ALAT PENGIKAT KAYU

    1 Paku - ukuran 1" s/d 4" kg 16,750

    2 Paku - payung kg 25,000

    3 Paku - sekrup kg 22,800

    4 Mur Baut 3/8 " buah 4,950

    5 Lem kayu (fox) bh 18,3006 Tali Ijuk kg 13,700

    7 Lem kuning (aica aibon) kg 50,200

    XV . POMPA AIR DAN TANGKI AIR

    1 POMPA AIR LISTRIK

    Mesin pompa 1 lt / dt buah 2,651,350

    Mesin pompa 1-1/2 lt / dt buah 4,639,150

    Tangki air fiber glass 3.000 lt 5mm buah 6,797,175

    X VI . PAVING BLOCK

    1 Paving Blok Holland t: 6 cm (ALDAS) m2 59,500

    2 Paving Blok Holland t: 6 cm (lokal) m2 36,750

    3 Paving Blok Holland t: 8 cm (ALDAS) m2 102,100

    4 Paving Blok Holland t: 8 cm (lokal) m2 18,200

    5 Paving blok warna 6 cm (lokal) m2 51,800

    6 Paving blok warna 8 cm (lokal) m2 55,0007 Kanstin 10/12,5 x 30 x 50 (ALDAS) bh 22,250

    8 Paving Blok Hexagonal Kecil t: 6 cm, (ALDAS) m2 76,700

    9 Paving Blok Hexagonal Kecil t: 8 cm, (ALDAS) m2 103,300

    10 Kanstin 10 x 20 x 50 (ALDAS) bh 11,100

    11 Kanstin 10/12,5 x 25 x 50 (ALDAS) bh 18,150

    1 PUPUK

    KCL, KS, ZK Kg 5,450

    Pupuk Kandang Ton 302,500

    Pupuk Kompos Ton 907,500

    Pupuk Organik/Bokhasi Kg 2,450

    Pupuk Phonska Kg 3,025

    SP 36 Kg 3,025

    Urea Kg 3,025

    2 OBAT - OBATAN

    Fastac 25 EC 50 mL 12,100

    3 TANAMAN HIAS

    Agape Batang 72,600

    Angsana Batang 12,100

    Apinika Buah 3,025

    Bambu Hias Rumpun 29,050

    Bambu Jepang Buah 19,950

    Bougenville Biasa Batang 26,650

    Bougenville Parigata Batang 39,950

    Cemara Bola Buah 10,650

    Cemara Buaya Buah 7,250

    Cemara Gimbal Batang 60,500

    Cemara Kipas Batang 29,300Cemara Non Flok/Ventris Batang 79,850

    Daun Walisongo Buah 12,100

    Glodogan Batang 79,850

    Glodogan Pecut Batang 226,300

    Jaranan Batang 7,250

    Kamboja Jepang Batang 53,250

    Ketapang Batang 36,300

    Krokot Putih Rumpun 3,025

    Lamtana Rebah Batang 3,025

    Lamtana Tegak Batang 19,950

    Mahoni 1 Meter Batang 11,200

    Mimbo Batang 6,650

    Mirten Buah 12,100

    Palem Botol Batang 382,050

    Palem Ekor Tupai Batang 189,750Palem Kuning Batang 25,300

    Palem Merah Batang 30,800

    Palem Raja/Putri Batang 126,500

    Palem Wergu Batang 31,350

    Pangkas Kuning Batang 4,400

    Pangkas Merah Batang 4,400

    Pinisium Batang 37,950

    Rumput Jepang M2 5,050

    Sawo Kecik Batang 55,650

    Sikas Batang 632,500

    Tanaman Taiwan Buah 3,850

    Tanjung Batang 75,900

    Teh - tehan Rumpun 15,400

    XVII. RTH (JALUR HIJAU DAN TAMAN)

    144824707.xls.ms_office

  • 7/30/2019 Analis RAB Gedung 2010

    7/44

    HARGA

    NO. SATUAN KET.

    1 3 4 52

    J E N I S B A H A N(Rp)

    4 ALAT - ALAT PERTAMANAN

    Ajir Tanaman Buah 550

    Ajir Tanaman Mangrove Buah 800

    Batu Asahan Buah 13,200

    Bambu Usuk Buah 6,600Busi Mesin Potong Rumput Buah 12,100

    Cetok Buah 23,000

    Chain Saw 038 STIHL Buah 12,100,000

    Chain Saw 070 STIHL Buah 15,125,000

    Gunting Dahan Buah 137,950

    Membran Karburator Chain Saw Buah 181,500

    Membran Oli Chain Saw Buah 60,500

    Mesin Potong Rumput Dorong Buah 7,260,000

    Mesin Potong Rumput Gendong Buah 8,470,000

    Mesin Pompa Air G x 160 + 2" Buah 3,932,500

    Patok Batas Buah 6,050

    Pisau M. Ptng Rmput Dorong/Gendong Buah 605,000

    Piston Set Chain Saw Buah 726,000

    Piston Set M. Ptng Rmpt Drong/Gndong Buah 726,000

    Pot Tanaman Hias Buah 302,500Pot Tanaman Palem Buah 151,250

    Rantai Chain Saw 038 STIHL Buah 302,500

    Rantai Chain Saw 070 STIHL Buah 308,000

    Seal Ker As Mesin M. Ptng Rmput Buah 66,550

    Srumbung Bambu Buah 38,500

    Srumbung Kayu Buah 24,200

    Selang Biasa 2" Meter 15,400

    Selang Lipat 2" Meter 6,600

    Selang Spiral Meter 42,900

    Tali Starter Chain Saw Buah 18,700

    Trucuk Bambu Batang 7,700

    5 BAHAN KEND. TDK. BERMOTOR

    As Belakang Buah Buah 12,100

    As Tengah Buah Buah 20,900

    Ban Dalam Buah Buah 16,500

    Ban Luar Buah Buah 55,000

    Bos Samping Buah Buah 16,500

    Laker Buah Buah 7,700

    Pedal Buah Buah 13,200

    Pelek Buah Buah 61,600

    Per Buah Buah 38,500

    Rantai Buah Buah 13,200

    Ruji Buah Buah 550

    Sadel Buah Buah 19,800

    6 PERALATAN KEBERSIHAN DAN BHN. PEMBERSIH

    Angkus Buah Buah 18,700

    Bendo Buah Buah 24,200

    Cangkul Buah Buah 33,900

    Ekrak Buah Buah 9,700Ganco Buah Buah 36,300

    Gunting Pangkas Buah Buah 115,500

    Linggis Buah Buah 15,125

    Sabit Buah Buah 21,175

    Sapu Lidi Buah Buah 7,250

    Skrap Buah Buah 6,050

    XVIII. LAMPU PENERANGAN JALAN UMUM (LPJU)

    1 Baut 3/8 Buah 1,100

    2 Besi L Buah 66,000

    3 Box KWH Meter 1 Phasa Buah 328,900

    4 Box Trafo Buah 42,350

    5 Conector Buah 6,875

    6 Contactor SN 35 Buah 465,850

    7 Cor Ornamen Tiang Listrik Buah 385,0008 Cup Piring Buah 27,500

    9 Cupit Urang Buah 3,650

    10 Fitting E 40 Buah 35,750

    11 Fitting WD 27 Buah 19,250

    12 Fotto cell 10 A Buah 137,950

    13 Fotto cell 6 A Buah 93,200

    14 Groundhing/ardhe Buah 25,300

    15 Housing Lamp 125 W Buah 880,000

    16 Housing Lamp 250 W Buah 1,694,000

    17 Ignisitor Buah 57,200

    18 Isolasi Buah 11,000

    19 Kabel LVTC 2 x 10 mm Meter 71,500

    20 Kabel LVTC 2 x 16 mm Meter 8,250

    21 Kabel NYM 2 x 2,5 mm Meter 8,800

    144824707.xls.ms_office

  • 7/30/2019 Analis RAB Gedung 2010

    8/44

    HARGA

    NO. SATUAN KET.

    1 3 4 52

    J E N I S B A H A N(Rp)

    22 Kabel NYM 2 x 4 mm Meter 22,000

    23 Kabel NYY 2 x 4 mm Meter 17,600

    24 Kabel NYY 2 x 6 mm Meter 20,020

    25 Kapasitor Buah 53,625

    26 Konsul Besi 1,25" MG Batang 203,500

    27 Konsul Besi 2" MG Batang 247,50028 Kotak APP/Double cover Buah 825,000

    29 KWH Meter 20/60 A Buah 522,500

    30 KWH Meter 50/20 A Buah 437,250

    31 L Booh 1" Buah 2,200

    32 Lampu HPIT 250 W Buah 264,550

    33 Lampu Mercury 250 W Buah 96,250

    34 Lampu Mercury 125 W Buah 46,750

    35 Lampu Mercury 80 W Buah 44,000

    36 Lampu Selang Meter 33,000

    37 Lampu Son T 150 W Buah 107,800

    38 Lampu Son T 250 W Buah 127,300

    39 M C B 25 A Buah 34,100

    40 M C B 63 A Buah 190,850

    41 OK KWH Meter Buah 30,800

    42 Pal Besi 2" dan 1" MG Buah 548,90043 Pal Besi 4 & 3 MG Buah 1,705,000

    44 Pemasangan LPJU Unit 99,000

    45 Pole Band 8,5 Buah 28,600

    46 SJ. 5 Buah 46,650

    47 Soket Lampu Selang Meter 14,850

    48 T Does/Boxlit Buah 21,450

    49 Terminal Box Meter Buah 28,600

    50 Trafo Mercury 125 W Buah 125,950

    51 Trafo Mercury 250 W Buah 207,350

    52 Trafo BSN 150 W Buah 216,700

    53 Trafo BSN 250 W Buah 258,500

    54 Lampu Hias Christmas Unit 29,493,750

    55 Lampu Hias Windmill Unit 23,100,000

    56 Lampu Hias Cotton Rose Unit 22,756,250

    57 Lampu Hias Number One Unit 22,343,750

    58 Lampu Hias Dragon Phoenix Unit 21,587,500

    59 Lampu Hias Hepla Unit 21,587,500

    60 Tangga Besar 12 m Buah 9,418,750

    61 Tangga Kecil 6 m Buah 4,812,500

    62 Crystalite Buah 123,750

    63 Lampu XL 18 Watt Buah 41,250

    64 Sabuk Pengaman Buah 3,052,500

    1 Selang Pemadam Kebakaran fire house Appron/Murata/ Yamato with Machino Working Pressure 10 Kg/cm2

    - 1,5 x 30 m, W/Coupling roll 1,807,700

    - 1,5 x 20 m, W/Coupling roll 1,478,125

    - 2 x 30 m, W/Coupling roll 1,753,125

    - 2 x 20 m, W/Coupling roll 1,519,375

    - 2,5 x 40 m roll 2,915,550

    - 2,5 x 30 m, W/Coupling roll 2,681,250- 2,5 x 20 m, W/Coupling roll 2,179,375

    2 Without Coupling

    - 1,5 x 20 m Tertera 368,300

    - 1,5 x 30 m Tertera 553,100

    - 2 x 20 m Tertera 553,100

    - 2 x 30 m Tertera 842,150

    - 2,5 x 20 m Tertera 673,200

    - 2,5 x 30 m Tertera 1,024,350

    - 2,5 x 40 m Tertera 1,363,550

    3 Hydrant Box Kosong

    - A1 (66 x 52 x 15 cm) Appron 858,000

    - A1 (100 x 80 x 18 cm) Appron 2,334,450

    - A1 (125 x 75 x 18 cm) Appron 2,797,750- A1 (95 x 66 x 20 cm) Appron 2,334,450

    - A1KACA + Kunci, Tempered 5 mm Appron 1,586,000

    - A2KACA + Kunci, Tempered 5 mm Appron 2,726,500

    - B KACA + Kunci, Tempered 5 mm Appron 3,189,800

    - C KACA + Kunci, Tempered 5 mm Appron 2,726,500

    4 Fire Fighting Equipment Machino Coupling material Brass

    - 1,5 Tertera 118,250

    - 2 Tertera 144,375

    - 2,5 Tertera 211,750

    - 3 Tertera 335,500

    5 Straight Nozzle (Machino Coupling) With Nozzle tip, Material Brass/ Branch pipa with straight Nozzle

    XIX. ALAT PEMADAM KEBEKARAN

    144824707.xls.ms_office

  • 7/30/2019 Analis RAB Gedung 2010

    9/44

    HARGA

    NO. SATUAN KET.

    1 3 4 52

    J E N I S B A H A N(Rp)

    - 1,5 Seamless Tertera 462,000

    - 2 Seamless Tertera 585,750

    - 2,5 Seamless, Short, W/O Grip Tertera 640,750

    - 2,5 Seamless, Long, W/O Grip Tertera 797,500

    - 2,5 Seamless, Long, W/ Grip Tertera 820,875

    - 1,5 Appron 46,475- 2 Appron 652,450

    - 2,5 Appron 1,063,550

    6 Hydrant Valve (Machino Coupling) 90

    Material Brass. 10 K

    - 1,5 Tertera 228,350

    - 2 Tertera 319,000

    - 2,5 Tertera 520,100

    7 Hydrant Valve (Machino Coupling) 90

    Material Brass. 20 K

    - 1,5 Tertera 472,550

    - 2 Tertera 732,875

    - 2,5 Tertera 988,625

    8 Hose Rack

    - 1,5, 1,24 COMB Unit 589,875

    - 2,5, 1,24 COMB Unit 643,500

    9 Spray Nozzle Head

    - 1,5 Tertera 284,625

    - 2 Tertera 429,000

    10 Hose Reel

    - 1 Hose Reel, Swing Type Complete

    With box Siamese Conention

    4 x 2,5 x 2,5 Machino Coupling Tertera 2,046,000

    11 Hydrant Pillar

    - H14 AP 4 x 2,5 x 2,5 Tertera 6,345,250

    - H13 AP 3 x 2,5 Tertera 3,392,650

    12 On Trollen

    - Type AC 15 kapasitas 6 kg buah 2,252,950

    - Type AC 50 kapasitas 23 kg buah 6,413,550

    13 Pemancar Pemadam Kebakaran

    - 1,5 (Variable) Tertera 2,376,000

    - 2,5 (Variable) Tertera 3,300,000

    14 Noksel Foam buah 12,490,450

    15 Foise Cabang 2 (dua) buah 4,900,500

    16 Liquite kg 121,450

    17 Pengisian Tabung Pemadam Kebakaran kg 79,200

    18 Selang Isap 2,3 4 M unit 35,750,000

    XX . L A I N - L A I N

    1 Alat bantu (harga rata-rata) lot 13,750

    2 Aspal kg 9,500

    3 Minyak aspal ltr 2,200

    4 Bensin ltr 4,500

    5 Solar liter 4,500

    6 Minyak tanah ltr 3,600

    7 Olie (minyak pelumas) liter 34,450

    8 Stempet Kg 20,050

    9 Gebalan rumput m2 13,700

    10 Wiremesh MS m2 72,600

    11 Kayu bakar m3 97,100

    12 Pintu Ronsel Doble 200 x 200 x 300 buah 41,250,000

    13 Pintu Ronsel Doble 150 x 150 x 300 buah 34,375,00014 Pintu Ronsel Engkel 100 x 100 x 300 buah 17,187,500

    15 Pintu Intake 100 x 100 x 300 buah 9,625,000

    16 Pintu Intake 90 x 100 x 300 buah 7,562,500

    17 Pintu Intake 80 x 80 x 300 buah 6,875,000

    18 Pintu Intake 60 x 60 x 300 buah 6,187,500

    19 Pintu Intake 50 x 50 x 300 buah 4,812,500

    20 Pintu Intake 40 x 40 x 300 buah 4,468,750

    21 Pintu Intake 30 x 40 x 300 buah 4,125,000

    22 Nomenklatur Marmer ( 30 x 40 ) buah 543,950

    23 Nomenklatur Marmer ( 15 x 20 ) buah 135,850

    24 Pile Scale ( 20 x 100 ) buah 543,950

    25 Pile Scale ( 12 x 100 ) buah 339,900

    26 Lapisan kedap air kg 58,300

    27 Nako lengkap daun 54,450

    144824707.xls.ms_office

  • 7/30/2019 Analis RAB Gedung 2010

    10/44

    HARGA

    NO. SATUAN KET.

    1 3 4 52

    J E N I S B A H A N(Rp)

    28 PAGAR BRC. Pagar BRC 90 A1 /lb 485,650

    Pagar BRC 120 A1 /lb 566,500

    Pagar BRC 150 A1 /lb 890,450

    Pagar BRC 90 A2 /lb 404,250

    Pagar BRC 120 A2 /lb 485,650

    Pagar BRC 150 A2 /lb 809,050Pipa Tiang BRC 90 - 2" unit 202,400

    Pipa Tiang BRC 120 - 2" unit 234,850

    Pipa Tiang BRC 150 - 2" unit 251,350

    29 Minyak Beton & bekisting ltr 22,000

    30 Allumunium sheet 0,3 mm (90 x 180) lbr 130,680

    31 Shear Connector kg 11,000

    Rembang, Juli 2009

    KEPALA DINAS PEKERJAAN UMUM

    KABUPATEN REMBANG

    Ir. MUJOKO, MT.NIP. 010 234 645 / 19620715 199011 1 002

    144824707.xls.ms_office

  • 7/30/2019 Analis RAB Gedung 2010

    11/44

    EDISI SEPTEMBER 2009

    NO. KODE HARGA SATUAN

    1 2 4

    I A PEKERJAAN PERSIAPAN

    A.1 1M' Pagar Sementara dari Seng Gelombang Tinggi 2,00 m 394,652.50

    A.2 1M' Pengukuran dan Pemasangan Bouwplank 100,482.38

    A.3 1M2 Pembuatan Kantor Sementara dg Lantai Plesteran 1,175,370.50

    A.4 1M2 Pembuatan Gudang Semen dan Alat-alat 1,027,867.25

    A.5 1M2 Membersihkan Lapangan dan Perataan 5,000.00

    A.6 1M2 Pembuatan Steger dari Bambu Uk. 40 x 50 x 20 cm 35,342.00

    A.7 1M3 Bongkaran Beton Bertulang 213,330.00

    A.8 1M3 Bongkaran Dinding Tembok Bata Merah 201,330.00

    A.9 1 M3 MEMBONGKAR DINDING BATA / BATU (Batu / bata dipakai lagi) 93,600.00A.10 1 M3 MEMBONGKAR DINDING BATA / BATU (bongkaran tidak dipakai lagi) 68,000.00

    A.11 1M2 MEMBONGKAR PLESTERAN DINDING 4,250.00

    A.12 1M2 MEMBONGKAR GENTENG / SIRAP (bongkaran tidak dipakai lagi) 3,400.00

    A.13 1M2 MEMBONGKAR GENTENG / SIRAP (bongkaran dipakai lagi) 17,000.00

    A.14 1M2 MEMBONGKAR RANGKA ATAP/RENG KASO (bongkaran tidak dipakai lagi) 8,625.00

    A.15 1M2 MEMBONGKAR RANGKA ATAP / RENG KASO (bongkaran dipakai lagi) 11,500.00

    A.16 1M3 MEMBONGKAR KUDA-KUDA GORDING/BALOK (bongkaran dipakai lagi) 418,000.00

    A.17 1M3 MEMBONGKAR KUDA-KUDA GORDING/BALOK (bongkaran tidak dipakai lagi) 263,500.00

    A.18 1M2 MEMBONGKAR PLAFOND (bongkaran dipakai lagi) 17,500.00

    A.19 1M2 MEMBONGKAR PLAFOND (bongkaran tidak dipakai lagi) 5,100.00

    II B PEKERJAAN TANAHB.1 1M3 Galian Tanah Biasa Sedalam 1 m 13,600.00

    B.2 1M3 Galian Tanah Keras Sedalam 1 m 31,280.00

    B.3 1M3 Galian Tanah Cadas Sedalam 1 m 47,400.00

    B.4 1M3 Galian Tanah Lumpur Sedalam 1 m 37,800.00

    B.5 1M2 Pekerjaan Striping Setinggi 1 m 1,700.00

    B.6 1M3 Membuang Tanah Sejauh 30 m' 10,300.00

    B.7 1M3 Urugan Kembali (dihitung 1/3 kali indeks pekerjaan galian) -

    B.8 1M3 Pemadatan Tanah 17,000.00

    B.9 1M3 Urugan Pasir 83,740.00

    B.10 1M3 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL 149,380.00

    B.11 1M2 Pemasangan Lapisan Ijuk tebal 10 cm 87,300.00

    B.12 1M3 Urugan Sirtu 41,500.00

    B.13 1 M3 Galian Tanah Biasa Sedalam 2 meter 17,860.00

    B.14 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 3 M' TENAGA MANUSIA 25,657.50

    B.15 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 4 M' TENAGA MANUSIA 32,767.50

    B.16 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 5 M' TENAGA MANUSIA 39,877.50

    B.17 1 M3 PEK. GALIAN TANAH BANYAK TERDAPAT BATU-BATU BUNDAR 50,437.50

    MAX KEDALAMAN 1 M' TENAGA MANUSIA

    B.18 1 M3 PEK. GALIAN TANAH BERBATU MAX KEDALAMAN 1 M' TNG MANUSIA 27,187.50

    B.19 1 M3 PEK. GALIAN TANAH MAX KEDALAMAN 2 M' DENGAN ALAT EXAVATOR 0,7 M3 6,763.16

    B.20 1 M3 PEK. GALIAN TANAH MAX KEDALAMAN 5 M' DENGAN ALAT EXAVATOR 0,7 M3 8,784.33

    B.21 MENGANGKUT HASIL GALIAN DENGAN DUMP TRUCK . M3/KM. 4,904.36

    B.22 1 M3. MENGANGKUT HASIL GALIAN EXAVATOR 0,7 M3 DENGAN DUMP TRUCK 6,688.05

    KURANG DARI 1,5 KM.

    B.23 1 M3. MENGANGKUT HASIL GALIAN EXAVATOR 0,7 M3 DENGAN DUMP TRUCK 11,146.74

    JARAK ANTARA 1,5 S/D 3 KM.

    B.24 1 M3. MENGANGKUT HASIL GALIAN EXAVATOR 0,7 M3 DENGAN DUMP TRUCK 15,605.44

    JARAK ANTARA 3 S/D 5 KM.

    B.25 1 M3 MERATAKAN TANAH 9,618.75

    B.26 1 M3 PEK. URUGAN TANAH PILIHAN 93,275.00

    B.27 1 M3 PEK. LAPISAN PUDEL 1 KP : 3 TL 148,100.00

    B.28 1 M3 PEK. LAPISAN PUDEL 1 KP : 5 PS 218,100.00

    B.29 1 M3 MERATAKAN TANAH DAN DITIMBRIS 9,618.75

    B.30 1 M2 MENGAMBIL DAN PASANGAN GEBALAN 5,271.88

    B.31 1 M' MENGANGKUT GEBALAN RUMPUT 1,871.88

    B.32 1 M2 PEKERJAAN GEBALAN RUMPUT SAMPAI TUMBUH 23,211.88

    B.33 1 M2 URUGAN PAKAI ALAT BESAR TANAH DARI LUAR DIPADATKAN (U/5000 M3) 92,912.50

    3

    URAIAN PEKERJAAN

    D A F T A R H A R G A S A T U A N P E K E R J A A N

    DINAS PEKERJAAN UMUM KABUPATEN REMBANG

    TAHUN 2010

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 11

  • 7/30/2019 Analis RAB Gedung 2010

    12/44

    NO. KODE HARGA SATUAN

    1 2 43

    URAIAN PEKERJAAN

    III C PEKERJAAN PONDASI

    C.1 1M3 Pasang Pondasi Batu Kali 1Pc : 3 Ps 514,450.00

    C.1a 1 M3 PASANGAN BATU BELAH 1 : 4 458,262.50

    C.2 1M3 Pasang Pondasi Batu Kali 1Pc : 5 Ps 435,200.00

    C.3 1M3 Pasang Pondasi Batu Kali, 1 Pc : 3 Kp : 10 Ps 359,074.50

    C.4 1M3 Pasang Pondasi Batu Kosong 180,152.40

    C.5 1M3 Pasang Pondasi Siklop 60% Beton Camp. 1PC : 2PS : 3KR & 2,036,818.40

    40% Batu Belah

    C.6 1M3 Pasang Pondasi Sumuran diameter 100 cm 546,777.50

    C.7 1M' Pembuatan Tiang Pancang (40x40) cm, Beton Bertulang 725,148.40

    C.8 SEBUAH TIANG PANCANG DICINCIN DAN DILANCIPKAN (KAYU HUTAN) 10,912.50

    C.9 1 M' TIANG DIPANCANGKAN DIDALAM TANAH LUNAK 57,737.50

    C.10 1 M' TIANG DIPANCANGKAN DIDALAM TANAH BIASA 72,171.88

    C.11 1 M' TIANG DIPANCANGKAN DIDALAM TANAH KERAS 86,606.25C.12 1 M' TIANG DIPANCANGKAN DIDALAM TANAH PASIR 115,475.00

    C.13 1 M3 PASANGAN BATU BRONJONG UNTUK KAWAT 3 MM 356,263.33

    C.14 1 M3 PASANGAN BATU BRONJONG UNTUK KAWAT 4 MM 484,763.33

    C.15 1 M3 PASANGAN BATU BRONJONG UNTUK KAWAT 5 MM 645,596.67

    IV D P E K E R J A A N D I N D I N G

    D.1 1M2 Pasang Batu Merah Tebal 1/2 bata, 1 Pc : 2 Ps 73,671.88

    D.2 1M2 Pasang Batu Merah Tebal 1/2 bata, 1 Pc : 3 Ps 67,910.63

    D.3 1M2 Pasang Batu Merah Tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps 59,146.25

    D.4 1 M2 PASANGAN 1/2 BATA MERAH 1 : 4 65,118.75

    D.5 1 M2 PASANGAN 1/2 BATA MERAH 1 : 5 62,980.00

    D.6 1 M2 PASANGAN BATU TEMPEL + SIARAN 133,301.25

    D.7 1 M3 PASANGAN BATA MERAH 1 PC : 2 PS 738,842.50

    D.8 1 M3 PASANGAN BATA MERAH 1 PC : 4 PS 643,965.00

    D.9 1 M3 PASANGAN BATA MERAH 1 PC : 3 KP : 10 PS 556,142.50

    V E PEKERJAAN P L E S T E R A N

    E.1 1M2 Plesteran 1 Pc : 3 Ps Tebal 15 mm 25,902.50

    E.2 1M2 Plesteran 1 Pc : 2 Kp : 8 Ps Tebal 15 mm 20,097.50

    E.3 1M2 Plesteran 1 Pc : 3 Kp : 10 Ps Tebal 15 mm 18,183.50

    E.4 1M2 Plesteran 1 Pc : 3 Ps Tebal 20 mm 35,183.00

    E.5 1M2 Berapen 1 Pc : 5 Ps Tebal 15 mm 18,164.00

    E.6 1M' Plesteran Skoning 1 Pc : 2 Ps lebar 10 mm 5,155.00

    E.7 1M2 Plesteran Ciprat 1 Pc : 2 Ps 19,140.00

    E.8 1M2 Finishing Siar Pas. Batu Kali Adukan 1 Pc : 2 Ps 26,001.25

    E.9 1M2 Acian 13,785.63

    VI F PEKERJAAN KAYU

    F.1 1M3 Membuat Kosen Pintu & Jendela Kayu klas I 18,943,112.50

    F.2 1M3 Membuat Kosen Pintu & Jendela Kayu Bengkirai 11,002,487.50

    F.3 1M2 Membuat Pintu Klamp Standard Kayu Bengkirai 418,907.50

    F.4 1M2 Membuat Daun Pintu Panel Kayu Bengkirai 507,915.00

    F.5 1M2 Membuat Pintu & Jendela Kaca Kayu Bengkirai 437,902.50

    F.6 1M2 Membuat Pintu & Jendela Jalusi Kayu Kelas I (Jati) 1,226,150.00

    F.7 1M2 Membuat Pintu Plywood Rangkap rangka Kayu Bengkirai lbr s/d 90cm 445,240.00

    F.8 1M2 Membuat Pintu Plywood rangkap, rangka expose kayu Bengkirai 456,602.50

    F.9 1M2 Membuat Jalusi mati Kosen Kayu Kelas I (Jati) 1,081,887.50

    F.10 1M2 Membuat Jalusi mati Kosen Kayu Bengkirai 648,762.50

    F.11 1M2 Membuat Pintu Teakwood Rangkap Rangka Kayu Kelas I (jati) 628,048.75

    F.12 1M2 Membuat Pintu Teakwood Rangkap Lapis Formika Rangka ekspose 593,304.00

    Kayu Bengkirai

    F.13 1 M2 DAUN PINTU TRIPLEK DOUBLE UKURAN PINTU LAPIS ALUMINIUM ( KM/WC ) 456,611.00

    F.14 1 M2 DAUN PINTU TRIPLEK DOUBLE UKURAN PINTU LAPIS FORMIKA ( KM/WC ) 442,085.00

    F.15 1M3 Memasang Konstruksi Kuda-kuda Konvensional Kayu Bengkirai 11,607,900.00

    Bentang 6 M

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 12

  • 7/30/2019 Analis RAB Gedung 2010

    13/44

    NO. KODE HARGA SATUAN

    1 2 43

    URAIAN PEKERJAAN

    F.16 1M3 Memasang Konstruksi Kuda-kuda Ekspose Kayu Jati 19,240,675.00

    F.17 1M3 Memasang Konstruksi Gording Kayu Bengkirai 10,539,700.00

    F.18 1M2 Pasang Pintu Plywood & Formika Rangka Kayu Bengkirai 626,042.50

    F.19 1M2 Pasang Pintu Formika Double, Rangka Kayu Jati 844,375.00

    F.20 1M2 Memasang Rangka Atap Genteng Keramik, Kayu Bengkirai 129,512.50

    F.21 1M2 Memasang Rangka Atap Genteng Beton, Kayu Bengkirai 136,442.50

    F.22 1M2 Pasang Rangka Atap Sirap Kayu Bengkirai 1,600,955.00

    F.23 1M' Pasang Listplank Uk. (3x20)cm Kayu Bengkirai 78,850.00

    F.24 1M' Pasang Listplank Uk. (3x30)cm Kayu Bengkirai 111,750.00

    F.25 1M' Pasang Listplank Uk. 2x(3x20)cm Kayu Bengkirai 148,656.25

    F.26 1M2 Pasang Rangka Dinding Pemisah Kayu Bengkirai 281,612.50

    F.27 1M2 Pas. Dinding Pemisah Teakwood Rangkap Rangka Kayu Bengkirai 373,733.50

    F.28 1M2 Pasang Dinding Lambriziring dari Papan jati 221,988.75

    F.29 1M2 Pasang Plywood tebal 4mm unt Dinding 52,122.00

    F.30 1M2 Pasang Dinding Bilik, Rangka Kayu Klas III / IV 80,107.00

    VII G PEKERJAAN BETON

    G.1 1M3 Membuat Beton mutu f'c=7,4 Mpa (K100), slum (122)cm, w/c = 0,87 679,355.82

    G.2 1M3 Membuat Beton mutu f'c=9,8 Mpa (K125), slum (122)cm, w/c = 0,78 735,932.22

    G.3 1M3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum (122)cm, w/c = 0,72 742,299.65

    G.4 1M3 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87 644,983.39

    G.5 1M3 Membuat Beton mutu f'c=14,5 MPa (K175), slum (122)cm, w/c = 0,66 773,823.84

    G.6 1M3 Membuat Beton mutu f'c=16,9 MPa (K200), slum (122)cm,w/c = 0,61 804,752.72

    G.7 1M3 Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 828,562.75

    G.8 1M3 Membuat Beton mutu f'c=21,7 MPa (K250), slum (122)cm,w/c = 0,56 911,379.90

    G.9 1M3 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (122)cm, w/c = 0,53 936,109.66

    G.10 1M3 Membuat Beton mutu f'c=26,4 MPa (K300), slum (122)cm,w/c = 0,52 943,719.83

    G.11 1M3 Membuat Beton mutu f'c=28,8 MPa (K325), slum (122)cm,w/c = 0,49 991,870.82

    G.12 1M3 Membuat Beton mutu f'c=31,2 MPa (K350), slum (122)cm, w/c = 0,48 1,001,923.14

    G.13 1KG Pembesian dg Besi Polos 12,477.75

    G.13a 110 KG Besi Beton Terpasang (polos) 1,372,552.50

    G.13b 125 KG Besi Beton Terpasang (polos) 1,559,718.75

    G.14 1KG Kabel Presstresed Polos/strand 20,053.00

    G.15 1M2 Pasang Bekisting untuk Pondasi 118,585.00

    G.16 1M2 Pasang Bekisting untuk Sloof 190,772.50

    G.17 1M2 Pasang Bekisting untuk Kolom 346,918.75

    G.18 1M2 Pasang Bekisting untuk Balok 310,825.00

    G.19 1M2 Pasang Bekisting untuk Lantai 443,312.50

    G.20 1M2 Pasang Bekisting untuk Dinding 352,775.00

    G.21 1M2 Pasang Bekisting untuk Tangga 278,787.50

    G.22 1 M2 Pasang Bekisting Jembatan Cor 89,520.00

    G.23 1 M2 BEKESTING DENGAN PAPAN 138,762.50

    G.24 1 M2 BEKESTING DENGAN MULTIPLEX 9 MM 130,776.90

    G.25 1 M3 Membuat Pondasi Beton Bertulang (150 kg Besi + Bekisting) 3,273,255.50

    G.26 1 M3 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting) 4,066,433.00

    G.27 1 M3 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting) 7,375,933.00

    G.28 1 M3 Membuat Balok Beton Bertulang (200 kg Besi + Bekisting) 5,740,743.00

    G.29 1 M3 Membuat Balok Beton Bertulang (150 kg Besi + Bekisting) 5,509,225.50

    G.30 1 M3 Membuat Dinding Beton Bertulang (150 kg Besi + Bekisting) 5,195,990.50

    G.31 1 M3 Membuat Tangga Beton Bertulang (200 kg Besi + Bekisting) 5,253,870.50

    G.32 1 M' Membuat Kolom Penguat Beton Bertulang (11 x 11) cm 62,837.95

    G.33 1 M' Membuat Ring Balok Beton Bertulang (10 x 15) cm 73,827.55

    G.34 1 M3 PAS. BETON K-175 READY MIX 6 M3 BERIKUT SLANG 988,993.75

    G.35 1 M3 PAS. BETON K-225 READY MIX 6 M3 BERIKUT SLANG 1,044,018.75

    G.36 1 M3 PAS. BETON K-300 READY MIX 6 M3 BERIKUT SLANG 1,085,393.75

    G.37 1 KG PEK. ERECTION KONST. KUDA-KUDA BESI 906.30

    G.38 1 KG PEKERJAAN BAJA IWF 44,140.00

    G.39 1 KG PEKERJAAN KONSTUKSI BESI SIKU / PROFIL 43,150.00

    G.40 1 CM PEK. PENGELASAN DENGAN LAS LISTRIK TEBAL KAWAT 4 MM 39,930.30

    G.41 1 TITIK MELUBANG KONSTRUKSI BESI DENGAN BOR 40,025.00

    G.42 1 M2 PEKERJAAN WIREMESH M8 83,213.50

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 13

  • 7/30/2019 Analis RAB Gedung 2010

    14/44

    NO. KODE HARGA SATUAN

    1 2 43

    URAIAN PEKERJAAN

    VIII H PEKERJAAN PENUTUP ATAP

    H.1 1 M2 Pasang Atap Genteng Mantili Kecil 33,367.50

    H.2 1 M2 Pasang Atap Genteng Mantili Besar 31,640.00

    H.3 1 M' Pasang Genteng Bubung Mantili 50,480.00

    H.4 1 M2 Pasang Atap Asbes Gelombang (80 x 210 cm) x 5 mm 38,577.50

    H.5 1 M2 Pasang Atap Genteng Beton 41,852.50

    H.6 1 M2 Pasang Atap Sirap 175,770.00

    H.7 1 M' Pasang Nok Genteng Beton 72,975.00

    H.8 1 M' Pasang Nok Sirap 58,457.93

    H.9 1 M2 Pasang Atap Seng Gelombang 63,835.00

    H.10 1 M' Pasang Atap Nok Seng 33,105.00

    IX I PEKERJAAN LANGIT - LANGIT

    I.1 1 M2 Langit-langit Asbes (1,00x1,00) m, tebal 4 mm, 5 mm & 6 mm 25,392.50I.2 1 M2 Memasang Langit-langit Tripleks Uk (120x240) cm, 34,575.00

    Tebal 3 mm, 4 mm & 6 mm

    I.3 1 M2 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm 299,311.25

    I.4 1 M2 Langit-langit Gypsum Board, tebal 9 mm 38,088.00

    I.5 1 M' List Langit-Langit Kayu Profil 12,117.50

    I.6 1M2 Pasang Rangka Langit-langit (1,00x1,00) m, kayu Bengkirai 170,825.00

    I.7 1M2 Pasang Rangka Langit-langit (60x60) cm, kayu Bengkirai 181,575.00

    X J PEKERJAAN SANITASI, JALAN DAN SALURAN

    J.1 1 UNIT Memasang Closet Duduk Porselin 736,645.00

    J.2 1 UNIT Memasang Closet Jongkok 300,525.00

    J.3 1 UNIT Memasang Wastafel 714,572.50

    J.4 1 M' Memasang Pipa Beton, 15 cm - 20 cm 77,660.78

    J.5 1 M' Memasang Pipa Beton, 30 cm - 100 cm 122,367.05

    J.6 1 M' Memasang Pipa PVC type AW " 10,092.00

    J.7 1 M' MEMASANG PIPA PVC type AW 3/4" 13,346.00

    J.8 1 M' MEMASANG PIPA type AW PVC 1" 20,102.00

    J.9 1 M' MEMASANG PIPA PVC type AW 11/4" 24,610.00

    J.10 1 M' MEMASANG PIPA PVC type AW 11/2" 35,820.00

    J.11 1 M' Memasang Pipa PVC type AW 2" 51,586.00

    J.12 1 M' MEMASANG PIPA PVC type AW 21/2" 72,900.75

    J.13 1 M' Memasang Pipa PVC type AW 3" 102,643.00

    J.14 1 M2 PASANG PAVING BLOK 6 CM K : 300 94,382.50

    J.15 1 M2 PASANG PAVING BLOK 6 CM K : 175 71,405.00

    J.16 1 M2 PASANG PAVING BLOK 8 CM K ; 300 137,408.50

    J.17 1 M2 PASANG PAVING BLOK 8 CM K: 175 52,669.50

    J.18 1 M2 PASANGAN PAVING BLOK WARNA 6 CM K: 175 86,605.50

    J.19 1 M2 PASANGAN PAVING BLOK WARNA 8 CM K: 175 89,837.50

    J.20 1 M2 LAPISAN PENGISI / PENUTUP DENGAN ASPAL PANAS TEBAL 3 CM 44,630.05

    J.21 MENGGILAS JALAN 1 HARI DIPERLUKAN 514,687.50

    J.21a MENGGILAS 1 M2 LAPIS KULIT PENAHAN 3,431.25

    J.21b MENGGILAS 1 M2 LAPIS KULIT PERTEGARAN 1,715.63

    J.21c MENGGILAS LAPIS AUS ( PENETRASI ) 1,029.38

    J.21d MENGGILAS RINGAN 1 M2 OPERPENTING 1,286.72

    J.22 100 M2 PENGASPALAN SHEET (LATASIR) TEBAL 1 CM JERENG 1,752,590.00

    J.23 1M2 ASPAL SAND SHEET TEBAL 2 CM JERENG ( 1 CM PADAT ) 41,206.18

    J.24 1M2 ASPAL SAND SHEET TEBAL 3 CM JERENG ( 2 CM PADAT ) 58,732.08

    XI K PEKERJAAN BESI & ALLUMUNIUM

    K.1 1 Kg Memasang Besi Profil 26,981.00

    K.2 1 Kg Memasang Rangka Kuda-kuda Baja IWF 27,050.00

    K.3 1 M' Memasang Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm 244,148.75

    K.4 1 M' Memasang Talang 1/2 Lingkaran 15 cm, Seng Plaat BJLS 30 84,740.00

    Lebar 45 cm

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 14

  • 7/30/2019 Analis RAB Gedung 2010

    15/44

    NO. KODE HARGA SATUAN

    1 2 43

    URAIAN PEKERJAAN

    XII L PEKERJAAN KUNCI dan KACA

    L.1 1 BUAH Pasang Kunci Tanam Biasa 87,550.00

    L.2 1 BUAH Pasang Kunci Tanam Kamar Mandi 87,075.00

    L.3 1 BUAH Pasang Engsel Pintu 14,680.00

    L.4 1 BUAH Pasang Engsel Jendela Kupu-kupu 12,350.00

    L.5 1 BUAH Pasang Engsel Angin 16,350.00

    L.6 1 BUAH Pasang Kait Angin 27,030.00

    L.7 1 BUAH Pasang Kunci Selot 20,490.00

    L.8 1 BUAH Pasang Kunci Lemari 23,000.00

    L.9 1 M2 Pasang Kaca tebal 5 mm 113,405.00

    XIII M PEKERJAAN PENUTUP LANTAI & DINDING

    M.1 1 M2 Pasang lantai Ubin PC Abu-abu Uk. 20 x 20 cm 55,441.50

    M.2 1 M2 Pasang lantai Ubin Granito Uk. 40 x 40 cm 581,335.38M.3 1 M2 Pasang Lantai Keramik 30 x 30 cm 129,741.25

    M.4 1 M2 Pasang Lantai Keramik 20 x 20 cm 121,950.00

    M.5 1M2 Memasang Lantai Marmer ukuran 1.00x1.00 m 697,684.23

    M.6 1 M2 Pasang Dinding Keramik 10x20 cm, 132,065.75

    M.7 1 M2 Pasang Dinding Keramik 20x20 cm, 130,193.75

    M.8 1M2 Memasang Dinding Marmer ukuran 1.00x1.00 m 727,264.35

    M.9 1 M2 Pasang Dinding Batu Paros / Batu Tempel Hitam 131,671.88

    M.10 1 M2 DINDING GRANIT IMPORT 498,012.50

    M.11 1 M2 LANTAI GRANIT IMPORT 405,602.50

    M.12 1 M2 LANTAI GRANITO UKURAN 60 X 60 POLISHED 562,117.50

    M.13 1 M2 DINDING GRANITO UKURAN 60 X 60 POLISHED 566,587.50

    M.14 1 M2 LANTAI MARMER ITALY 1,544,902.50

    M.15 1 M2 DINDING MARMER ITALY 1,634,312.50

    XIV N PEKERJAAN PENGECATAN

    N.1 1 M2 Mendempul dan Menggosok Kayu 5,548.00

    N.2 1 M2 Pengecatan Bidang Lama 14,788.00

    N.3 1 M2 Pengecatan Bidang Kayu Baru (1 lap.Plamir) 32,530.00

    1 lap.Cat Dasar & 2 lap.Cat Penutup

    N.4 1 M2 Pengecatan Bidang Kayu Baru (1 lap.Plamir) 41,569.00

    1 lap.Cat Dasar & 3 lap.Cat Penutup

    N.5 1 M2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 11,292.00

    2 lap. Cat Penutup)

    N.6 1 M2 Pengecat Tembok Lama (1lap.Plamir, 2lap Cat Penutup) 7,352.00

    N.7 1 M2 Pengecatan Permukaan Baja dg Meni Besi 11,428.00

    N.8 1 M2 Pengecatan Permukaan Baja dg Meni Besi & Perancah 24,338.00

    N.9 1 M2 Pengecatan Permukaan Baja lapis Seng (Galvanis) secara 88,696.00

    manual sistem 3 lapis Cat Konvensional dg tebal 200 um

    N.10 1 M2 PLITURAN BANGUNAN ( BIASA ) 35,650.50

    N.11 1 M2 PLITURAN MEUBELAIR 70,973.50

    Rembang, Juli 2009

    KEPALA DINAS PEKERJAAN UMUMKABUPATEN REMBANG

    Ir. MUJOKO, MT.

    NIP. 010 234 645 / 19620715 199011 1 002

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 15

  • 7/30/2019 Analis RAB Gedung 2010

    16/44

    EDISI SEPTEMBER 2009

    No. KODE KOEF SAT. HARGA SAT. JUMLAH

    Rp Rp

    1 3 4 5 7 8 = ( 4 X 7 )

    I A PEKERJAAN PERSIAPAN

    A.1 1M' Pagar Sementara dari Seng Gelombang Tinggi 2,00 m 394,652.50

    1.2500 Btg Kayu Dolken diameter 8 - 10 / 400 cm 35,700.00 44,625.00

    2.5000 Kg Portalnd Semen 1,312.50 3,281.25

    1.2000 Lbr Seng Gelombang 3" - 5" 54,850.00 65,820.00

    0.0050 m3 Pasir Pasang 125,000.00 625.00

    0.0090 m3 Koral Beton 261,250.00 2,351.25

    0.0720 m3 Kayu 5/7X4m Kayu Meranti 3,437,500.00 247,500.00

    0.0600 Kg Paku Biasa 2" - 5" 16,750.00 1,005.00

    0.4500 Kg Meni Besi 16,100.00 7,245.00

    0.2000 OH Tukang Kayu 42,500.00 8,500.00

    0.4000 OH Pekerja 30,000.00 12,000.000.0200 OH Kepala Tukang 45,000.00 900.00

    0.0200 OH Mandor 40,000.00 800.00

    A.2 1M' Pengukuran dan Pemasangan Bouwplank 100,482.38

    0.0120 m3 Kayu 5/7x 4m Kayu Kruing 4,855,125.00 58,261.50

    0.0200 Kg Paku Biasa 2" - 5" 16,750.00 335.00

    0.0070 m3 Kayu Papan 3/20 Kayu Kruing 4,855,125.00 33,985.88

    0.1000 OH Tukang Kayu 42,500.00 4,250.00

    0.1000 OH Pekerja 30,000.00 3,000.00

    0.0100 OH Kepala Tukang 45,000.00 450.00

    0.0050 OH Mandor 40,000.00 200.00

    A.3 1M2 Pembuatan Kantor Sementara dg Lantai Plesteran 1,175,370.501.2500 Btg Kayu Dolken 8 - 10 / 4 m 35,700.00 44,625.00

    0.1800 m3 Kayu 3,437,500.00 618,750.00

    0.8500 Kg Paku Biasa 2" - 5" 16,750.00 14,237.50

    1.1000 Kg Besi Strip 16,200.00 17,820.00

    35.0000 Kg Portland Sement 1,312.50 45,937.50

    0.2500 m3 Pasir pasang 125,000.00 31,250.00

    0.1500 m3 Koral Beton 261,250.00 39,187.50

    30.0000 buah Batu bata Merah 425.00 12,750.00

    0.2500 Lbr Seng Plat 54,850.00 13,712.50

    2.0000 daun Jendela Naco 54,450.00 108,900.00

    0.0800 m2 Kaca Polos 96,250.00 7,700.00

    0.1500 buah Kunci Tanam 65,350.00 9,802.50

    0.3000 buah Engsel 5,950.00 1,785.00

    0.0600 Lbr Plywood 4 mm 98,550.00 5,913.00

    2.0000 OH Tukang Kayu 42,500.00 85,000.00

    1.0000 OH Tukang Batu 42,500.00 42,500.00

    2.0000 OH Pekerja 30,000.00 60,000.00

    0.3000 OH Kepala Tukang 45,000.00 13,500.00

    0.0500 OH Mandor 40,000.00 2,000.00

    A.4 1M2 Pembuatan Gudang Semen dan Alat-alat 1,027,867.25

    1.7000 Btg Kayu Dolken diameter 8 - 10 / 400 cm 35,700.00 60,690.00

    0.2100 m3 Kayu 3,437,500.00 721,875.00

    0.3000 Kg Paku Biasa 2" - 5" 16,750.00 5,025.00

    10.5000 Kg Portland Semen 1,312.50 13,781.25

    0.0300 m3 Pasir Beton (Cepu) 171,950.00 5,158.50

    0.0500 m3 Koral Beton 261,250.00 13,062.50

    1.5000 Lbr Seng Gelombang BJLS 32 54,850.00 82,275.00

    2.0000 OH Tukang Kayu 42,500.00 85,000.00

    1.0000 OH Pekerja 30,000.00 30,000.00

    0.2000 OH Kepala Tukang 45,000.00 9,000.00

    0.0500 OH Mandor 40,000.00 2,000.00

    A.5 1M2 Membersihkan Lapangan dan Perataan 5,000.00

    0.1000 OH Pekerja 30,000.00 3,000.00

    0.0500 OH Mandor 40,000.00 2,000.00

    A.6 1M2 Pembuatan Steger dari Bambu Uk. 40 x 50 x 20 cm 35,342.00

    1.0000 Btg Bambu diameter 6 - 8 / 600 cm 17,050.00 17,050.00

    0.2500 Kg Tali Ijuk 13,700.00 3,425.00

    0.1700 OH Tukang Kayu 42,500.00 7,225.00

    0.2500 OH Pekerja 30,000.00 7,500.00

    0.0020 OH Kepala Tukang 45,000.00 90.00

    0.0013 OH Mandor 40,000.00 52.00

    TAHUN 2010

    6

    URAIAN PAKERJAAN

    DAFTAR ANALISA SATUAN PEKERJAAN

    DINAS PEKERJAAN UMUM KABUPATEN REMBANG

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 16

  • 7/30/2019 Analis RAB Gedung 2010

    17/44

    A.7 1M3 Bongkaran Beton Bertulang 213,330.00

    6.6670 OH Pekerja 30,000.00 200,010.00

    0.3330 OH Mandor 40,000.00 13,320.00

    A.8 1M3 Bongkaran Dinding Tembok Bata Merah 201,330.00

    6.6670 OH Pekerja 30,000.00 200,010.00

    0.0330 OH Mandor 40,000.00 1,320.00

    A.9 1 M3 MEMBONGKAR DINDING BATA / BATU (Batu / bata dipakai lagi) 93,600.00

    3.0000 Org Pekerja 30,000.00 90,000.00

    0.0900 Org Mandor 40,000.00 3,600.00

    A.10 1 M3 MEMBONGKAR DINDING BATA / BATU (bongkaran tidak dipakai lagi) 68,000.00

    2.0000 Org Pekerja 30,000.00 60,000.00

    0.2000 Org Mandor 40,000.00 8,000.00

    A.11 1M2 MEMBONGKAR PLESTERAN DINDING 4,250.00

    0.1250 Org pekerja 30,000.00 3,750.00

    0.0125 Org Mandor 40,000.00 500.00

    A.12 1M2 MEMBONGKAR GENTENG / SIRAP (bongkaran tidak dipakai lagi) 3,400.00

    0.1000 Org pekerja 30,000.00 3,000.000.0100 Org Mandor 40,000.00 400.00

    A.13 1M2 MEMBONGKAR GENTENG / SIRAP (bongkaran dipakai lagi) 17,000.00

    0.5000 Org pekerja 30,000.00 15,000.00

    0.0500 Org Mandor 40,000.00 2,000.00

    A.14 1M2 MEMBONGKAR RANGKA ATAP/RENG KASO (bongkaran tidak dipakai lagi) 8,625.00

    0.1500 Org Pekerja 30,000.00 4,500.00

    0.0750 Org Tukang Kayu 42,500.00 3,187.50

    0.0075 Org Kepala tukang kayu 45,000.00 337.50

    0.0150 Org Mandor 40,000.00 600.00

    A.15 1M2 MEMBONGKAR RANGKA ATAP / RENG KASO (bongkaran dipakai lagi) 11,500.00

    0.2000 Org Pekerja 30,000.00 6,000.00

    0.1000 Org Tukang Kayu 42,500.00 4,250.000.0100 Org Kepala tukang kayu 45,000.00 450.00

    0.0200 Org Mandor 40,000.00 800.00

    A.16 1M3 MEMBONGKAR KUDA-KUDA GORDING/BALOK (bongkaran dipakai lagi) 418,000.00

    4.0000 Org Pekerja 30,000.00 120,000.00

    6.0000 Org Tukang Kayu 42,500.00 255,000.00

    0.6000 Org Kepala tukang kayu 45,000.00 27,000.00

    0.4000 Org Mandor 40,000.00 16,000.00

    A.17 1M3 MEMBONGKAR KUDA-KUDA GORDING/BALOK (bongkaran tidak dipakai lagi) 263,500.00

    4.0000 Org Pekerja 30,000.00 120,000.00

    3.0000 Org Tukang Kayu 42,500.00 127,500.00

    0.4000 Org Mandor 40,000.00 16,000.00

    A.18 1M2 MEMBONGKAR PLAFOND (bongkaran dipakai lagi) 17,500.00

    0.1000 Org Pekerja 30,000.00 3,000.00

    0.3000 Org Tukang Kayu 42,500.00 12,750.00

    0.0300 Org Kepala tukang kayu 45,000.00 1,350.00

    0.0100 Org Mandor 40,000.00 400.00

    A.19 1M2 MEMBONGKAR PLAFOND (bongkaran tidak dipakai lagi) 5,100.00

    0.1500 Org Pekerja 30,000.00 4,500.00

    0.0150 Org Mandor 40,000.00 600.00

    Keterangan :A.20 a K = Biaya

    275.0000 a = Upah Pekerja

    L = Jarak angkut

    Keterangan :A.21 a K = Biaya

    275.0000 a = Upah Pekerja

    L = Jarak angkut

    II B PEKERJAAN TANAH

    B.1 1M3 Galian Tanah Biasa Sedalam 1 m 13,600.00

    0.400 OH Pekerja 30,000.00 12,000.00

    0.040 OH Mandor 40,000.00 1,600.00

    ( L + 75 ))Biaya setiap jarak pengangkutan/langsiran 1 m3 Material = K : (

    ( L + 75 ))/25Biaya setiap jarak pengangkutan / langsiran 1 zak semen = K : (

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 17

  • 7/30/2019 Analis RAB Gedung 2010

    18/44

    B.2 1M3 Galian Tanah Keras Sedalam 1 m 31,280.00

    1.000 OH Pekerja 30,000.00 30,000.00

    0.032 OH Mandor 40,000.00 1,280.00

    B.3 1M3 Galian Tanah Cadas Sedalam 1 m 47,400.00

    1.500 OH Pekerja 30,000.00 45,000.00

    0.060 OH Mandor 40,000.00 2,400.00

    B.4 1M3 Galian Tanah Lumpur Sedalam 1 m 37,800.00

    1.200 OH Pekerja 30,000.00 36,000.000.045 OH Mandor 40,000.00 1,800.00

    B.5 1M2 Pekerjaan Striping Setinggi 1 m 1,700.00

    0.050 OH Pekerja 30,000.00 1,500.00

    0.005 OH Mandor 40,000.00 200.00

    B.6 1M3 Membuang Tanah Sejauh 30 m' 10,300.00

    0.330 OH Pekerja 30,000.00 9,900.00

    0.010 OH Mandor 40,000.00 400.00

    Suppl. B 6 1 M3 PEK. PEMBUANGAN LEBIH DARI RADIUS 30 M

    Keterangan :

    a K = Biaya

    275 a = Upah PekerjaL = Jarak pembuangan

    B.7 1M3 Urugan Kembali (dihitung 1/3 kali indeks pekerjaan galian)

    B.8 1M3 Pemadatan Tanah 17,000.00

    0.500 OH Pekerja 30,000.00 15,000.00

    0.050 OH Mandor 40,000.00 2,000.00

    B.9 1M3 Urugan Pasir 83,740.00

    1.200 m3 Pasir Urug 61,950.00 74,340.00

    0.300 OH Pekerja 30,000.00 9,000.00

    0.010 OH Mandor 40,000.00 400.00

    B.10 1M3 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL 149,380.00

    0.400 m3 Pasir Urug 61,950.00 24,780.00

    0.135 m3 Kapur Padam 196,000.00 26,460.00

    0.948 m3 Tanah Liat 55,000.00 52,140.00

    0.800 OH Pekerja 30,000.00 24,000.00

    0.400 OH Tukang Batu 42,500.00 17,000.00

    0.040 OH Kepala Tukang 45,000.00 1,800.00

    0.080 OH Mandor 40,000.00 3,200.00

    B.11 1M2 Pemasangan Lapisan Ijuk tebal 10 cm 87,300.00

    6.000 kg Ijuk 13,700.00 82,200.00

    0.150 OH Pekerja 30,000.00 4,500.00

    0.015 OH Mandor 40,000.00 600.00

    B.12 1M3 Urugan Sirtu 41,500.00

    1.200 m3 Sirtu 27,500.00 33,000.00

    0.250 OH Pekerja 30,000.00 7,500.00

    0.025 OH Mandor 40,000.00 1,000.00

    B.13 1 M3 Galian Tanah Biasa Sedalam 2 meter 17,860.00

    0.526 OH Pekerja 30,000.00 15,780.00

    0.052 OH Mandor 40,000.00 2,080.00

    B.14 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 3 M' TENAGA MANUSIA 25,657.50

    0.735 org Pekerja 30,000.00 22,050.00

    0.073 org Mandor 40,000.00 2,920.00

    0.050 lot Alat bantu 13,750.00 687.50

    B.15 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 4 M' TENAGA MANUSIA 32,767.50

    0.944 org Pekerja 30,000.00 28,320.00

    0.094 org Mandor 40,000.00 3,760.00

    0.050 lot Alat bantu 13,750.00 687.50

    B.16 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 5 M' TENAGA MANUSIA 39,877.50

    1.153 org Pekerja 30,000.00 34,590.00

    0.115 org Mandor 40,000.00 4,600.00

    0.050 lot Alat bantu 13,750.00 687.50

    B.17 1 M3 PEK. GALIAN TANAH BANYAK TERDAPAT BATU-BATU BUNDAR

    MAX KEDALAMAN 1 M' TENAGA MANUSIA 50,437.50

    1.500 org Pekerja 30,000.00 45,000.000.050 org Mandor 40,000.00 2,000.00

    0.250 lot Alat bantu 13,750.00 3,437.50

    MENGGUNAKAN RUMUS = K : ( L + 75 )

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 18

  • 7/30/2019 Analis RAB Gedung 2010

    19/44

    B.18 1 M3 PEK. GALIAN TANAH BERBATU MAX KEDALAMAN 1 M' TNG MANUSIA 27,187.50

    0.625 org Pekerja 30,000.00 18,750.00

    0.125 org Mandor 40,000.00 5,000.00

    0.250 lot Alat bantu 13,750.00 3,437.50

    B.19 1 M3 PEK. GALIAN TANAH MAX KEDALAMAN 2 M' DENGAN ALAT EXAVATOR 0,7 M 6,763.16

    0.005 unit Excavator 0,7 m3 500,000.00 2,286.63

    0.704 liter Solar 4,500.00 3,169.27

    0.018 liter Olie (minyak pelumas) 34,450.00 630.19

    0.005 Kg Stempet 20,050.00 91.69

    0.005 org Operator Alat Berat 43,000.00 196.65

    0.005 org Pemb. Operator Alat Berat 35,000.00 160.06

    0.005 org Pekerja 30,000.00 137.20

    0.002 org Mandor 40,000.00 91.47

    B.20 1 M3 PEK. GALIAN TANAH MAX KEDALAMAN 5 M' DENGAN ALAT EXAVATOR 0,7 M 8,784.33

    0.006 unit Excavator 0,7 m3 500,000.00 2,990.21

    0.921 liter Solar 4,500.00 4,144.43

    0.024 liter Olie (minyak pelumas) 34,450.00 824.10

    0.006 Kg Stempet 20,050.00 119.91

    0.006 org Operator Alat Berat 43,000.00 257.16

    0.006 org Pemb. Operator Alat Berat 35,000.00 209.31

    0.006 org Pekerja 30,000.00 179.41

    0.001 org Mandor 40,000.00 59.80

    B.21 MENGANGKUT HASIL GALIAN DENGAN DUMP TRUCK . M3/KM. 4,904.36

    0.0101 buah Dump Truck 250,000.00 2,515.18

    0.2515 liter Solar 4,500.00 1,131.83

    0.0101 liter Olie (minyak pelumas) 34,450.00 346.59

    0.0050 Kg Stempet 20,050.00 100.86

    0.0101 org Sopir 40,500.00 407.46

    0.0101 org Pekerja 30,000.00 301.82

    0.0025 org Mandor 40,000.00 100.61

    B.22 1 M3. MENGANGKUT HASIL GALIAN EXAVATOR 0,7 M3 DENGAN DUMP TRUCK

    KURANG DARI 1,5 KM. 6,688.05

    0.0137 buah Dump Truck 250,000.00 3,429.94

    0.3430 liter Solar 4,500.00 1,543.47

    0.0137 liter Olie 34,450.00 472.65

    0.0069 Kg Stempet 20,050.00 137.540.0137 org Sopir 40,500.00 555.65

    0.0137 org Pekerja 30,000.00 411.59

    0.0034 org Mandor 40,000.00 137.20

    B.23 1 M3. MENGANGKUT HASIL GALIAN EXAVATOR 0,7 M3 DENGAN DUMP TRUCK

    JARAK ANTARA 1,5 S/D 3 KM. 11,146.74

    0.0229 buah Dump Truck 250,000.00 5,716.57

    0.5717 liter Solar 4,500.00 2,572.46

    0.0229 liter Olie 34,450.00 787.74

    0.0114 Kg Stempet 20,050.00 229.23

    0.0229 org Sopir 40,500.00 926.08

    0.0229 org Pekerja 30,000.00 685.99

    0.0057 org Mandor 40,000.00 228.66

    B.24 1 M3. MENGANGKUT HASIL GALIAN EXAVATOR 0,7 M3 DENGAN DUMP TRUCK

    JARAK ANTARA 3 S/D 5 KM. 15,605.44

    0.0320 buah Dump Truck 250,000.00 8,003.20

    0.8003 liter Solar 4,500.00 3,601.44

    0.0320 liter Olie 34,450.00 1,102.84

    0.0160 Kg Stempet 20,050.00 320.93

    0.0320 org Sopir 40,500.00 1,296.52

    0.0320 org Pekerja 30,000.00 960.38

    0.0080 org Mandor 40,000.00 320.13

    B.25 1 M3 MERATAKAN TANAH 9,618.75

    0.2500 org Pekerja 30,000.00 7,500.00

    0.0100 org Mandor 40,000.00 400.00

    0.1250 lot Alat bantu 13,750.00 1,718.75

    B.26 1 M3 PEK. URUGAN TANAH PILIHAN 93,275.00

    1.2000 m3 Tanah pilihan 68,750.00 82,500.00

    0.3000 org Pekerja 30,000.00 9,000.00

    0.0100 org Mandor 40,000.00 400.00

    0.1000 lot Alat bantu 13,750.00 1,375.00

    B.27 1 M3 PEK. LAPISAN PUDEL 1 KP : 3 TL 148,100.00

    0.2000 m3 Kapur padam 196,000.00 39,200.00

    1.0000 m3 Tanah liat 55,000.00 55,000.00

    1.0000 org Pekerja 30,000.00 30,000.00

    0.5000 org Tukang batu 42,500.00 21,250.00

    0.0500 org Kepala tukang batu 45,000.00 2,250.00

    0.0100 org Mandor 40,000.00 400.00

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 19

  • 7/30/2019 Analis RAB Gedung 2010

    20/44

  • 7/30/2019 Analis RAB Gedung 2010

    21/44

    C.4 1M3 Pasang Pondasi Batu Kosong 180,152.40

    1.200 m3 Batu Belah 15/20 93,750.00 112,500.00

    0.432 m3 Pasir Urug 61,950.00 26,762.40

    . 0.700 OH Pekerja 30,000.00 21,000.00

    0.390 OH Tukang Batu 42,500.00 16,575.00

    0.039 OH Kepala Tukang 45,000.00 1,755.00

    0.039 OH Mandor 40,000.00 1,560.00

    C.5 1M3 Pasang Pondasi Siklop 60% Beton Camp. 1PC : 2PS : 3KR & 2,036,818.40

    40% Batu Belah

    0.480 m3 Batu Belah 15/20 93,750.00 45,000.00

    126.000 Kg Besi Beton 11,100.00 1,398,600.00

    194.000 Kg Portland Semen 1,312.50 254,625.00

    0.312 m3 Pasir Beton (Cepu) 171,950.00 53,648.40

    0.468 m3 Koral Beton 261,250.00 122,265.00

    1.800 Kg Kawat Beton 17,850.00 32,130.00

    3.000 OH Pekerja 30,000.00 90,000.00

    0.850 OH Tukang Batu 42,500.00 36,125.00

    0.085 OH Kepala Tukang 45,000.00 3,825.00

    0.015 OH Mandor 40,000.00 600.00

    C.6 1M3 Pasang Pondasi Sumuran diameter 100 cm 546,777.50

    0.450 m3 Batu Belah 15/20 cm 93,750.00 42,187.50194.000 Kg Portland Semen 1,312.50 254,625.00

    0.312 m3 Pasir Pasang 125,000.00 39,000.00

    0.468 m3 Koral Beton 261,250.00 122,265.00

    2.380 OH Pekerja 30,000.00 71,400.00

    0.300 OH Tukang Batu 42,500.00 12,750.00

    0.030 OH Kepala Tukang 45,000.00 1,350.00

    0.080 OH Mandor 40,000.00 3,200.00

    C.7 1M' Pembuatan Tiang Pancang (40x40) cm, Beton Bertulang 725,148.40

    0.019 m3 Pasir Urug Darat 61,950.00 1,177.05

    0.094 m3 Pasir Beton (Cepu) 171,950.00 16,163.30

    0.150 m3 Koral Beton 261,250.00 39,187.50

    60.500 Kg Portland Semen 1,312.50 79,406.25

    45.000 Kg Besi Beton 11,100.00 499,500.000.900 Kg Kawat beton 17,850.00 16,065.00

    0.032 m3 Kayu Kaso 5/7 48,415.49 1,549.30

    0.120 Kg Paku 16,750.00 2,010.00

    0.090 Lt Minyak Bekisting 22,000.00 1,980.00

    0.240 Kg Plamuur Tembok 19,250.00 4,620.00

    1.000 OH Pekerja 30,000.00 30,000.00

    0.670 OH Tukang Batu 42,500.00 28,475.00

    0.067 OH Kepala Tukang 45,000.00 3,015.00

    0.050 OH Mandor 40,000.00 2,000.00

    C.8 SEBUAH TIANG PANCANG DICINCIN DAN DILANCIPKAN (KAYU HUTAN) 10,912.50

    0.1250 org Tukang Kayu 42,500.00 5,312.50

    0.0125 org Kepala Tukang 45,000.00 562.50

    0.1500 org Pekerja 30,000.00 4,500.00

    0.0100 org Mandor 40,000.00 400.00

    0.0100 lot alat bantu 13,750.00 137.50

    C.9 1 M' TIANG DIPANCANGKAN DIDALAM TANAH LUNAK 57,737.50

    0.0400 org Tukang Kayu 42,500.00 1,700.00

    0.0040 org Kepala Tukang 45,000.00 180.00

    1.8000 org Pekerja 30,000.00 54,000.00

    0.0430 org Mandor 40,000.00 1,720.00

    0.0100 lot alat bantu 13,750.00 137.50

    C.10 1 M' TIANG DIPANCANGKAN DIDALAM TANAH BIASA 72,171.88

    0.0500 org Tukang Kayu 42,500.00 2,125.00

    0.0050 org Kepala Tukang 45,000.00 225.00

    2.2500 org Pekerja 30,000.00 67,500.00

    0.0538 org Mandor 40,000.00 2,150.000.0125 lot alat bantu 13,750.00 171.88

    C.11 1 M' TIANG DIPANCANGKAN DIDALAM TANAH KERAS 86,606.25

    0.0600 org Tukang Kayu 42,500.00 2,550.00

    0.0060 org Kepala Tukang 45,000.00 270.00

    2.7000 org Pekerja 30,000.00 81,000.00

    0.0645 org Mandor 40,000.00 2,580.00

    0.0150 lot alat bantu 13,750.00 206.25

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 21

  • 7/30/2019 Analis RAB Gedung 2010

    22/44

    C.12 1 M' TIANG DIPANCANGKAN DIDALAM TANAH PASIR 115,475.00

    0.0800 org Tukang Kayu 42,500.00 3,400.00

    0.0080 org Kepala Tukang 45,000.00 360.00

    3.6000 org Pekerja 30,000.00 108,000.00

    0.0860 org Mandor 40,000.00 3,440.00

    0.0200 lot alat bantu 13,750.00 275.00

    C.13 1 M3 PASANGAN BATU BRONJONG UNTUK KAWAT 3 MM 356,263.33

    1.2000 m3 Batu kali 91,900.00 110,280.008.3333 kg Kawat bronjong 18,550.00 154,583.33

    0.6667 org penganyam 42,500.00 28,333.33

    2.0333 org Pekerja 30,000.00 61,000.00

    0.0517 org Mandor 40,000.00 2,066.67

    C.14 1 M3 PASANGAN BATU BRONJONG UNTUK KAWAT 4 MM 484,763.33

    1.2000 m3 Batu kali 91,900.00 110,280.00

    15.0000 kg Kawat bronjong 18,550.00 278,250.00

    0.7333 org penganyam 42,500.00 31,166.67

    2.1000 org Pekerja 30,000.00 63,000.00

    0.0517 org Mandor 40,000.00 2,066.67

    C.15 1 M3 PASANGAN BATU BRONJONG UNTUK KAWAT 5 MM 645,596.67

    1.2000 m3 Batu kali 91,900.00 110,280.00

    23.3333 kg Kawat bronjong 18,550.00 432,833.33

    0.8333 org penganyam 42,500.00 35,416.67

    2.1667 org Pekerja 30,000.00 65,000.00

    0.0517 org Mandor 40,000.00 2,066.67

    IV D P E K E R J A A N D I N D I N G

    D.1 1M2 Pasang Batu Merah Tebal 1/2 bata, 1 Pc : 2 Ps 73,671.88

    70.0000 Buah Bata Merah 5 x 11 x 22 425.00 29,750.00

    18.9500 Kg Portland Semen 1,312.50 24,871.88

    0.0380 m3 Pasir Pasang 125,000.00 4,750.00

    0.3000 OH Pekerja 30,000.00 9,000.00

    0.1000 OH Tukang Batu 42,500.00 4,250.00

    0.0100 OH Kepala Tukang 45,000.00 450.00

    0.0150 OH Mandor 40,000.00 600.00

    D.2 1M2 Pasang Batu Merah Tebal 1/2 bata, 1 Pc : 3 Ps 67,910.63

    70.0000 Buah Bata Merah 5 x 11 x 22 425.00 29,750.00

    14.3700 Kg Portland Semen 1,312.50 18,860.63

    0.0400 m3 Pasir Pasang 125,000.00 5,000.00

    0.3000 OH Pekerja 30,000.00 9,000.000.1000 OH Tukang Batu 42,500.00 4,250.00

    0.0100 OH Kepala Tukang 45,000.00 450.00

    0.0150 OH Mandor 40,000.00 600.00

    D.3 1M2 Pasang Batu Merah Tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps 59,146.25

    70.0000 Buah Bata Merah 5 x 11 x 22 425.00 29,750.00

    4.5000 Kg Portland Semen 1,312.50 5,906.25

    0.0500 m3 Pasir Pasang 125,000.00 6,250.00

    0.0150 m3 Kapur Padam 196,000.00 2,940.00

    0.3000 OH Pekerja 30,000.00 9,000.00

    0.1000 OH Tukang Batu 42,500.00 4,250.00

    0.0100 OH Kepala Tukang 45,000.00 450.00

    0.0150 OH Mandor 40,000.00 600.00

    D.4 1 M2 PASANGAN 1/2 BATA MERAH 1 : 4 65,118.75

    70.0000 bh Bata merah 425.00 29,750.00

    11.5000 kg P C (50 kg) 1,312.50 15,093.75

    0.0430 m3 Pasir pasang 125,000.00 5,375.00

    0.3200 org Pekerja 30,000.00 9,600.00

    0.1000 org Tukang batu 42,500.00 4,250.00

    0.0100 org Kepala tukang batu 45,000.00 450.00

    0.0150 org Mandor 40,000.00 600.00

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 22

  • 7/30/2019 Analis RAB Gedung 2010

    23/44

  • 7/30/2019 Analis RAB Gedung 2010

    24/44

  • 7/30/2019 Analis RAB Gedung 2010

    25/44

  • 7/30/2019 Analis RAB Gedung 2010

    26/44

    F.12 1M2 Membuat Pintu Teakwood Rangkap Lapis Formika Rangka ekspose 593,304.00

    Kayu Bengkirai

    0.0250 m3 Kayu Bengkirai, papan 8,937,500.00 223,437.50

    0.0300 Kg Paku Biasa 1/2" - 1" 16,750.00 502.50

    0.0800 Kg Lem Kayu 18,300.00 1,464.00

    1.0000 Lbr Teakwood tebal 4 mm 98,550.00 98,550.00

    0.5000 Lbr Formika 252,500.00 126,250.00

    0.8000 OH Pekerja 30,000.00 24,000.00

    2.5000 OH Tukang Kayu 42,500.00 106,250.00

    0.2500 OH Kepala Tukang 45,000.00 11,250.00

    0.0400 OH Mandor 40,000.00 1,600.00

    F.13 1 M2 DAUN PINTU TRIPLEK DOUBLE UKURAN PINTU LAPIS ALUMINIUM ( KM/WC 456,611.00

    0.0150 m3 Rangka kayu bengkirai (ram pintu) 9,625,000.00 144,375.00

    1.0000 lbr Triplek 4 mm 72,300.00 72,300.00

    1.2000 m2 Aluminium sheet 0,3 mm 130,680.00 156,816.00

    0.2000 kg Paku triplek 16,750.00 3,350.00

    0.5000 kg Lem putih ( FOX ) 18,300.00 9,150.00

    0.3000 org Pekerja 30,000.00 9,000.00

    1.3000 org Tukang kayu 42,500.00 55,250.00

    0.1300 org Kepala tukang kayu 45,000.00 5,850.00

    0.0130 org Mandor 40,000.00 520.00

    F.14 1 M2 DAUN PINTU TRIPLEK DOUBLE UKURAN PINTU LAPIS FORMIKA ( KM/WC ) 442,085.00

    0.0150 m3 Rangka kayu bengkirai (ram pintu) 9,625,000.00 144,375.00

    1.0000 lbr Triplek 4 mm ukuran pintu 72,300.00 72,300.00

    0.5000 lbr Formika 252,500.00 126,250.00

    0.2000 kg Paku triplek 16,750.00 3,350.00

    0.5000 kg Lem putih ( FOX ) 18,300.00 9,150.00

    0.2000 kg Lem kuning ( aica aibon ) 50,200.00 10,040.00

    0.5000 org Pekerja 30,000.00 15,000.00

    1.3000 org Tukang kayu 42,500.00 55,250.00

    0.1300 org Kepala tukang kayu 45,000.00 5,850.00

    0.0130 org Mandor 40,000.00 520.00

    F.15 1M3 Memasang Konstruksi Kuda-kuda Konvensional Kayu Bengkirai 11,607,900.00

    Bentang 6 M1.1000 m3 Kayu Bengkirai, balok 9,625,000.00 10,587,500.00

    15.0000 Kg Besi Strip 16,200.00 243,000.00

    0.8000 Kg Paku Biasa 2" - 5" 16,750.00 13,400.00

    4.0000 OH Pekerja 30,000.00 120,000.00

    12.0000 OH Tukang Kayu 42,500.00 510,000.00

    1.2000 OH Kepala Tukang 45,000.00 54,000.00

    2.0000 OH Mandor 40,000.00 80,000.00

    F.16 1M3 Memasang Konstruksi Kuda-kuda Ekspose Kayu Jati 19,240,675.00

    1.1000 m3 Kayu Jati, balok 16,156,250.00 17,771,875.00

    15.0000 Kg Besi Strip 16,200.00 243,000.00

    5.6000 Kg Paku Biasa 2" - 5" 16,750.00 93,800.00

    6.0000 OH Pekerja 30,000.00 180,000.00

    20.0000 OH Tukang Kayu 42,500.00 850,000.00

    2.0000 OH Kepala Tukang 45,000.00 90,000.00

    0.3000 OH Mandor 40,000.00 12,000.00

    F.17 1M3 Memasang Konstruksi Gording Kayu Bengkirai 10,539,700.00

    1.1000 m3 Kayu Bengkirai, balok 8,937,500.00 9,831,250.00

    15.0000 Kg Besi Strip 16,200.00 243,000.00

    3.0000 Kg Paku Biasa 2" - 5" 16,750.00 50,250.00

    2.4000 OH Pekerja 30,000.00 72,000.00

    7.2000 OH Tukang Kayu 42,500.00 306,000.00

    0.7200 OH Kepala Tukang 45,000.00 32,400.00

    0.1200 OH Mandor 40,000.00 4,800.00

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 26

  • 7/30/2019 Analis RAB Gedung 2010

    27/44

    F.18 1M2 Pasang Pintu Plywood & Formika Rangka Kayu Bengkirai 626,042.50

    0.0196 m3 Kayu Bengkirai, papan 8,937,500.00 175,175.00

    0.0300 Kg Paku Biasa 1/2" - 1" 16,750.00 502.50

    0.3000 Kg Lem Kayu 18,300.00 5,490.00

    0.5000 Lbr Plywood tebal 4 mm 98,550.00 49,275.00

    1.0000 Lbr Formika 252,500.00 252,500.00

    0.8000 OH Pekerja 30,000.00 24,000.00

    2.5000 OH Tukang Kayu 42,500.00 106,250.00

    0.2500 OH Kepala Tukang 45,000.00 11,250.00

    0.0400 OH Mandor 40,000.00 1,600.00

    F.19 1M2 Pasang Pintu Formika Double, Rangka Kayu Jati 844,375.00

    0.0196 m3 Kayu Jati, papan 16,156,250.00 316,662.50

    0.0300 Kg Paku Biasa 1/2" - 1" 16,750.00 502.50

    1.2000 Kg Lem Kayu 18,300.00 21,960.00

    1.0000 Lbr Plywood tebal 4 mm 98,550.00 98,550.00

    1.0000 Lbr Formika 252,500.00 252,500.00

    1.0000 OH Pekerja 30,000.00 30,000.00

    2.6000 OH Tukang Kayu 42,500.00 110,500.00

    0.2600 OH Kepala Tukang 45,000.00 11,700.00

    0.0500 OH Mandor 40,000.00 2,000.00

    F.20 1M2 Memasang Rangka Atap Genteng Keramik, Kayu Bengkirai 129,512.50

    0.0086 m3 Kayu Klas II (Bengkirai), Kaso-kaso (5x7) cm 9,625,000.00 82,775.00

    0.0036 m3 Reng (2x3) cm 9,625,000.00 34,650.00

    0.2500 Kg Paku Biasa 2" - 5" 16,750.00 4,187.50

    0.1000 OH Pekerja 30,000.00 3,000.00

    0.1000 OH Tukang Kayu 42,500.00 4,250.00

    0.0100 OH Kepala Tukang 45,000.00 450.00

    0.0050 OH Mandor 40,000.00 200.00

    F.21 1M2 Memasang Rangka Atap Genteng Beton, Kayu Bengkirai 136,442.50

    0.0086 m3 Kayu Bengkirai Kaso-kaso (5x7) cm 9,625,000.00 82,775.00

    0.0043 m3 Reng (2x3) cm 9,625,000.00 41,580.00

    0.2500 Kg Paku Biasa 2" - 5" 16,750.00 4,187.50

    0.1000 OH Pekerja 30,000.00 3,000.00

    0.1000 OH Tukang Kayu 42,500.00 4,250.00

    0.0100 OH Kepala Tukang 45,000.00 450.00

    0.0050 OH Mandor 40,000.00 200.00

    F.22 1M2 Pasang Rangka Atap Sirap Kayu Bengkirai 1,600,955.00

    0.1650 m3 Kayu Bengkirai, balok 9,625,000.00 1,588,125.00

    0.2000 Kg Paku Biasa 2" - 5" 16,750.00 3,350.00

    0.1200 OH Pekerja 30,000.00 3,600.00

    0.1200 OH Tukang Kayu 42,500.00 5,100.00

    0.0120 OH Kepala Tukang 45,000.00 540.00

    0.0060 OH Mandor 40,000.00 240.00

    F.23 1M' Pasang Listplank Uk. (3x20)cm Kayu Bengkirai 78,850.00

    0.0072 m3 Kayu Bengkirai, papan 8,937,500.00 64,350.00

    0.1000 Kg Paku Biasa 2" - 5" 16,750.00 1,675.00

    0.1000 OH Pekerja 30,000.00 3,000.00

    0.2000 OH Tukang Kayu 42,500.00 8,500.00

    0.0250 OH Kepala Tukang 45,000.00 1,125.00

    0.0050 OH Mandor 40,000.00 200.00

    F.24 1M' Pasang Listplank Uk. (3x30)cm Kayu Bengkirai 111,750.00

    0.0110 m3 Kayu Bengkirai, papan 8,937,500.00 98,312.50

    0.0500 Kg Paku Biasa 2" - 5" 16,750.00 837.50

    0.1000 OH Pekerja 30,000.00 3,000.00

    0.2000 OH Tukang Kayu 42,500.00 8,500.000.0200 OH Kepala Tukang 45,000.00 900.00

    0.0050 OH Mandor 40,000.00 200.00

    F.25 1M' Pasang Listplank Uk. 2x(3x20)cm Kayu Bengkirai 148,656.25

    0.0145 m3 Kayu Bengkirai, papan 8,937,500.00 129,593.75

    0.1500 Kg Paku Biasa 2" - 5" 16,750.00 2,512.50

    0.1500 OH Pekerja 30,000.00 4,500.00

    0.2500 OH Tukang Kayu 42,500.00 10,625.00

    0.0250 OH Kepala Tukang 45,000.00 1,125.00

    0.0075 OH Mandor 40,000.00 300.00

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 27

  • 7/30/2019 Analis RAB Gedung 2010

    28/44

    F.26 1M2 Pasang Rangka Dinding Pemisah Kayu Bengkirai 281,612.50

    0.0280 m3 Kayu Bengkirai, balok 8,937,500.00 250,250.00

    0.1500 Kg Paku Biasa 2" - 5" 16,750.00 2,512.50

    0.1500 OH Pekerja 30,000.00 4,500.00

    0.4500 OH Tukang Kayu 42,500.00 19,125.00

    0.0450 OH Kepala Tukang 45,000.00 2,025.00

    0.0800 OH Mandor 40,000.00 3,200.00

    F.27 1M2 Pas. Dinding Pemisah Teakwood Rangkap Rangka Kayu Bengkirai 373,733.50

    0.0280 m3 Kayu Bengkirai, balok 8,937,500.00 250,250.00

    0.1500 Kg Paku Biasa 2" - 5" 16,750.00 2,512.50

    0.8600 Lbr Teakwood tebal 4mm 98,550.00 84,753.00

    0.5600 Kg Lem kayu 18,300.00 10,248.00

    0.1500 OH Pekerja 30,000.00 4,500.00

    0.4500 OH Tukang Kayu 42,500.00 19,125.00

    0.0450 OH Kepala Tukang 45,000.00 2,025.00

    0.0080 OH Mandor 40,000.00 320.00

    F.28 1M2 Pasang Dinding Lambriziring dari Papan jati 221,988.75

    0.0070 m3 Kayu Jati, balok 16,156,250.00 113,093.75

    0.1000 Kg Paku Biasa 2" - 5" 16,750.00 1,675.00

    0.1500 Kg Paku Sekrup 3,5" 22,800.00 3,420.00

    0.6000 OH Pekerja 30,000.00 18,000.00

    1.8000 OH Tukang Kayu 42,500.00 76,500.00

    0.1800 OH Kepala Tukang 45,000.00 8,100.00

    0.0300 OH Mandor 40,000.00 1,200.00

    F.29 1M2 Pasang Plywood tebal 4mm unt Dinding 52,122.00

    0.4000 Lbr Plywood tebal 4mm 98,550.00 39,420.00

    0.5000 Kg Paku Biasa 1/2" - 1" 16,750.00 8,375.00

    0.0250 OH Pekerja 30,000.00 750.00

    0.0750 OH Tukang Kayu 42,500.00 3,187.50

    0.0075 OH Kepala Tukang 45,000.00 337.50

    0.0013 OH Mandor 40,000.00 52.00

    F.30 1M2 Pasang Dinding Bilik, Rangka Kayu Klas III / IV 80,107.00

    1.5000 m2 Bilik Bambu 17,050.00 25,575.00

    0.0140 m3 Kayu Klas III (Meranti) 3,437,500.00 48,125.00

    0.0500 Kg Paku Biasa 1/2" - 1" 16,750.00 837.50

    0.0030 m' List Kayu 2/4 6,500.00 19.50

    0.1000 OH Pekerja 30,000.00 3,000.00

    0.0500 OH Tukang Kayu 42,500.00 2,125.00

    0.0050 OH Kepala Tukang 45,000.00 225.00

    0.0050 OH Mandor 40,000.00 200.00

    VII G PEKERJAAN PERKERASAN DAN BETON

    G.1 1M3 Membuat Beton mutu f'c=7,4 Mpa (K100), slum (122)cm, w/c = 0,87 679,355.82

    247.0000 Kg Portland Semen 1,312.50 324,187.50

    0.6207 m3 Pasir Beton (Cepu) 171,950.00 106,731.82

    0.7400 m3 Kerikil (maksimum 30 mm) 246,850.00 182,669.00

    1.6500 OH Pekerja 30,000.00 49,500.00

    0.2750 OH Tukang Batu 42,500.00 11,687.50

    0.0280 OH Kepala Tukang 45,000.00 1,260.00

    0.0830 OH Mandor 40,000.00 3,320.00

    G.2 1M3 Membuat Beton mutu f'c=9,8 Mpa (K125), slum (122)cm, w/c = 0,78 735,932.22

    276.0000 Kg Portland Semen 1,312.50 362,250.00

    0.5914 m3 Pasir Beton (Cepu) 171,950.00 101,696.14

    0.7496 m3 Kerikil (maksimum 30 mm) 246,850.00 185,046.07

    1.6500 OH Pekerja 30,000.00 70,125.000.2750 OH Tukang Batu 42,500.00 12,375.00

    0.0280 OH Kepala Tukang 45,000.00 1,120.00

    0.0830 OH Mandor 40,000.00 3,320.00

    G.3 1M3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum (122)cm, w/c = 0,72 742,299.65

    299.0000 Kg Portland Semen 1,312.50 392,437.50

    0.5707 m3 Pasir Beton (Cepu) 171,950.00 98,134.32

    0.7533 m3 Kerikil (maksimum 30 mm) 246,850.00 185,960.33

    1.6500 OH Pekerja 30,000.00 49,500.00

    0.2750 OH Tukang Batu 42,500.00 11,687.50

    0.0280 OH Kepala Tukang 45,000.00 1,260.00

    0.0830 OH Mandor 40,000.00 3,320.00

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 28

  • 7/30/2019 Analis RAB Gedung 2010

    29/44

    G.4 1M3 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,8 644,983.39

    230.0000 Kg Portland Semen 1,312.50 301,875.00

    0.6379 m3 Pasir Beton (Cepu) 171,950.00 109,679.54

    0.7607 m3 Kerikil (maksimum 30 mm) 246,850.00 187,788.85

    1.2000 OH Pekerja 30,000.00 36,000.00

    0.2000 OH Tukang Batu 42,500.00 8,500.00

    0.0200 OH Kepala Tukang 45,000.00 900.00

    0.0060 OH Mandor 40,000.00 240.00

    G.5 1M3 Membuat Beton mutu f'c=14,5 MPa (K175), slum (122)cm, w/c = 0,66 773,823.84

    326.0000 Kg Portland Semen 1,312.50 427,875.00

    0.5429 m3 Pasir Beton (Cepu) 171,950.00 93,344.29

    0.7622 m3 Kerikil (maksimum 30 mm) 246,850.00 188,154.56

    1.6500 OH Pekerja 30,000.00 49,500.00

    0.2500 OH Tukang Batu 42,500.00 10,625.00

    0.0250 OH Kepala Tukang 45,000.00 1,125.00

    0.0800 OH Mandor 40,000.00 3,200.00

    G.6 1M3 Membuat Beton mutu f'c=16,9 MPa (K200), slum (122)cm,w/c = 0,61 804,752.72

    352.0000 Kg Portland Semen 1,312.50 462,000.00

    0.5221 m3 Pasir Beton (Cepu) 171,950.00 89,782.46

    0.7637 m3 Kerikil (maksimum 30 mm) 246,850.00 188,520.26

    1.6500 OH Pekerja 30,000.00 49,500.00

    0.2500 OH Tukang Batu 42,500.00 10,625.00

    0.0250 OH Kepala Tukang 45,000.00 1,125.00

    0.0800 OH Mandor 40,000.00 3,200.00

    G.7 1M3 Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 828,562.75

    371.0000 Kg Portland Semen 1,312.50 486,937.50

    0.4986 m3 Pasir Beton (Cepu) 171,950.00 85,729.36

    0.7756 m3 Kerikil (maksimum 30 mm) 246,850.00 191,445.89

    1.6500 OH Pekerja 30,000.00 49,500.00

    0.2500 OH Tukang Batu 42,500.00 10,625.00

    0.0250 OH Kepala Tukang 45,000.00 1,125.00

    0.0800 OH Mandor 40,000.00 3,200.00

    G.8 1M3 Membuat Beton mutu f'c=21,7 MPa (K250), slum (122)cm,w/c = 0,56 911,379.90

    384.0000 Kg Portland Semen 1,312.50 504,000.00

    0.4943 m3 Beton (Muntilan) 309,430.00 152,946.83

    0.7696 m3 Kerikil (maksimum 30 mm) 246,850.00 189,983.07

    1.6500 OH Pekerja 30,000.00 49,500.00

    0.2500 OH Tukang Batu 42,500.00 10,625.00

    0.0250 OH Kepala Tukang 45,000.00 1,125.00

    0.0800 OH Mandor 40,000.00 3,200.00

    G.9 1M3 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (122)cm, w/c = 936,109.66

    406.0000 Kg Portland Semen 1,312.50 532,875.00

    0.4886 m3 Beton (Muntilan) 309,430.00 151,178.66

    0.7600 m3 Kerikil (maksimum 30 mm) 246,850.00 187,606.00

    1.6500 OH Pekerja 30,000.00 49,500.00

    0.2500 OH Tukang Batu 42,500.00 10,625.00

    0.0250 OH Kepala Tukang 45,000.00 1,125.00

    0.0800 OH Mandor 40,000.00 3,200.00

    G.10 1M3 Membuat Beton mutu f'c=26,4 MPa (K300), slum (122)cm,w/c = 0,52 943,719.83

    413.0000 Kg Portland Semen 1,312.50 542,062.50

    0.4864 m3 Beton (Muntilan) 309,430.00 150,515.59

    0.7563 m3 Kerikil (maksimum 30 mm) 246,850.00 186,691.74

    1.6500 OH Pekerja 30,000.00 49,500.00

    0.2500 OH Tukang Batu 42,500.00 10,625.00

    0.0250 OH Kepala Tukang 45,000.00 1,125.00

    0.0800 OH Mandor 40,000.00 3,200.00

    G.11 1M3 Membuat Beton mutu f'c=28,8 MPa (K325), slum (122)cm,w/c = 0,49 991,870.82

    439.0000 Kg Portland Semen 1,312.50 576,187.50

    0.4786 m3 Beton (Muntilan) 309,430.00 148,084.36

    0.7452 m3 Kerikil (maksimum 30 mm) 246,850.00 183,948.96

    2.1000 OH Pekerja 30,000.00 63,000.00

    0.3500 OH Tukang Batu 42,500.00 14,875.00

    0.0350 OH Kepala Tukang 45,000.00 1,575.00

    0.1050 OH Mandor 40,000.00 4,200.00

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 29

  • 7/30/2019 Analis RAB Gedung 2010

    30/44

  • 7/30/2019 Analis RAB Gedung 2010

    31/44

  • 7/30/2019 Analis RAB Gedung 2010

    32/44

    G.26 1 M3 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting) 4,066,433.00

    0.2700 m3 Kayu Terentang 2,062,500.00 556,875.00

    2.0000 Kg Paku Biasa 2" - 5" 16,750.00 33,500.00

    0.6000 Ltr Minyak Bekisting 22,000.00 13,200.00

    210.0000 Kg Besi Beton Polos 11,100.00 2,331,000.00

    3.0000 Kg Kawat Beton 17,850.00 53,550.00

    336.0000 Kg Portland Semen 1,312.50 441,000.00

    0.5400 m3 Pasir Beton (Cepu) 171,950.00 92,853.00

    0.8100 m3 Koral Beton 261,250.00 211,612.50

    5.6500 OH Pekerja 30,000.00 169,500.00

    0.2750 OH Tukang batu 42,500.00 11,687.50

    1.5600 OH Tukang Kayu 42,500.00 66,300.00

    1.4000 OH Tukang Besi 42,500.00 59,500.00

    0.3230 OH Kepala Tukang 45,000.00 14,535.00

    0.2830 OH Mandor 40,000.00 11,320.00

    G.27 1 M3 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting) 7,375,933.00

    0.4000 m3 Kayu Terentang 2,062,500.00 825,000.00

    4.0000 Kg Paku Biasa 2" - 5" 16,750.00 67,000.00

    2.0000 Ltr Minyak Bekisting 22,000.00 44,000.00

    315.0000 Kg Besi Beton Polos 11,100.00 3,496,500.00

    4.5000 Kg Kawat Beton 17,850.00 80,325.00

    336.0000 Kg Portland Semen 1,312.50 441,000.00

    0.5400 m3 Pasir Beton (Cepu) 171,950.00 92,853.00

    0.8100 m3 Koral Beton 261,250.00 211,612.50

    0.1500 m3 Kayu Balok 3,437,500.00 515,625.00

    3.5000 Lbr Plywood 9 mm 135,200.00 473,200.00

    20.0000 Btg Dolken diameter 8 / 4mm 35,700.00 714,000.00

    7.0500 OH Pekerja 30,000.00 211,500.00

    0.2750 OH Tukang batu 42,500.00 11,687.50

    1.6500 OH Tukang Kayu 42,500.00 70,125.00

    2.1000 OH Tukang Besi 42,500.00 89,250.00

    0.4030 OH Kepala Tukang 45,000.00 18,135.00

    0.3530 OH Mandor 40,000.00 14,120.00

    G.28 1 M3 Membuat Balok Beton Bertulang (200 kg Besi + Bekisting) 5,740,743.00

    0.3200 m3 Kayu Terentang 2,062,500.00 660,000.00

    3.2000 Kg Paku Biasa 2" - 5" 16,750.00 53,600.00

    1.6000 Ltr Minyak Bekisting 22,000.00 35,200.00

    210.0000 Kg Besi Beton Polos 11,100.00 2,331,000.00

    3.0000 Kg Kawat Beton 17,850.00 53,550.00

    336.0000 Kg Portland Semen 1,312.50 441,000.00

    0.5400 m3 Pasir Beton (Cepu) 171,950.00 92,853.00

    0.8100 m3 Koral Beton 261,250.00 211,612.50

    0.1400 m3 Kayu Balok 3,437,500.00 481,250.00

    2.8000 Lbr Plywood 9 mm 135,200.00 378,560.00

    18.0000 Btg Dolken diameter 8 / 4mm 35,700.00 642,600.00

    6.3500 OH Pekerja 30,000.00 190,500.00

    0.2750 OH Tukang batu 42,500.00 11,687.50

    1.6500 OH Tukang Kayu 42,500.00 70,125.001.4000 OH Tukang Besi 42,500.00 59,500.00

    0.3330 OH Kepala Tukang 45,000.00 14,985.00

    0.3180 OH Mandor 40,000.00 12,720.00

    G.29 1 M3 Membuat Balok Beton Bertulang (150 kg Besi + Bekisting) 5,509,225.50

    0.3200 m3 Kayu Terentang 2,062,500.00 660,000.00

    3.2000 Kg Paku Biasa 2" - 5" 16,750.00 53,600.00

    1.6000 Ltr Minyak Bekisting 22,000.00 35,200.00

    157.5000 Kg Besi Beton Polos 11,100.00 1,748,250.00

    2.2500 Kg Kawat Beton 17,850.00 40,162.50

    336.0000 Kg Portland Semen 1,312.50 441,000.00

    0.5400 m3 Pasir Beton (Cepu) 171,950.00 92,853.00

    0.8100 m3 Koral Beton 261,250.00 211,612.50

    0.1200 m3 Kayu Balok 3,437,500.00 412,500.002.8000 Lbr Plywood 9 mm 135,200.00 378,560.00

    32.0000 Btg Dolken diameter 8 / 4mm 35,700.00 1,142,400.00

    5.3000 OH Pekerja 30,000.00 159,000.00

    0.2750 OH Tukang batu 42,500.00 11,687.50

    1.3000 OH Tukang Kayu 42,500.00 55,250.00

    1.0500 OH Tukang Besi 42,500.00 44,625.00

    0.2650 OH Kepala Tukang 45,000.00 11,925.00

    0.2650 OH Mandor 40,000.00 10,600.00

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 32

  • 7/30/2019 Analis RAB Gedung 2010

    33/44

  • 7/30/2019 Analis RAB Gedung 2010

    34/44

    G.35 1 M3 PAS. BETON K-225 READY MIX 6 M3 BERIKUT SLANG 1,044,018.75

    1.0000 m3 Adukan K-225 Ready Mix 952,875.00 952,875.00

    2.5000 org Pekerja 30,000.00 75,000.00

    0.2500 org Tukang batu 42,500.00 10,625.00

    0.1000 org Kepala tukang batu 45,000.00 4,500.00

    0.0100 org Mandor 40,000.00 400.00

    0.0450 lot Alat bantu (Slang + Tes Lab.) 13,750.00 618.75

    G.36 1 M3 PAS. BETON K-300 READY MIX 6 M3 BERIKUT SLANG 1,085,393.75

    1.0000 m3 Adukan K-300 Ready Mix 994,250.00 994,250.00

    2.5000 org Pekerja 30,000.00 75,000.00

    0.2500 org Tukang batu 42,500.00 10,625.00

    0.1000 org Kepala tukang batu 45,000.00 4,500.00

    0.0100 org Mandor 40,000.00 400.00

    0.0450 lot Alat bantu (Slang + Tes Lab.) 13,750.00 618.75

    G.37 1 KG PEK. ERECTION KONST. KUDA-KUDA BESI 906.30

    0.0010 org Pekerja 30,000.00 30.00

    0.0010 org Tukang besi profil 42,500.00 42.50

    0.0002 org Kepala tukang besi profil 45,000.00 9.00

    0.0001 org Mandor 40,000.00 4.00

    0.0002 org Operator alat berat 43,000.00 8.60

    0.0200 org Pembantu operator 35,000.00 700.00

    0.0002 ls Sewa alat 150,000.00 30.000.0100 lt Bahan Bakar solar 4,500.00 45.00

    0.0010 lt Pelumas 34,450.00 34.45

    0.0002 lot Alat bantu 13,750.00 2.75

    G.38 1 KG PEKERJAAN BAJA IWF 44,140.00

    1.1000 kg Besi IWF 19,400.00 21,340.00

    0.0600 org Pekerja 30,000.00 1,800.00

    0.0300 org Tukang besi profil 42,500.00 1,275.00

    0.0150 org Kepala tukang besi profil 45,000.00 675.00

    0.0075 org Mandor 40,000.00 300.00

    0.1250 lot Peralatan (oksigen,solar,elpiji,kawat las) 150,000.00 18,750.00

    G.39 1 KG PEKERJAAN KONSTUKSI BESI SIKU / PROFIL 43,150.00

    1.1000 kg Besi profil/besi siku 18,500.00 20,350.00

    0.0600 org Pekerja 30,000.00 1,800.000.0300 org Tukang besi profil 42,500.00 1,275.00

    0.0150 org Kepala tukang besi profil 45,000.00 675.00

    0.0075 org Mandor 40,000.00 300.00

    0.1250 lot Peralatan (oksigen,solar,elpiji,kawat las) 150,000.00 18,750.00

    G.40 1 CM PEK. PENGELASAN DENGAN LAS LISTRIK TEBAL KAWAT 4 MM 39,930.30

    0.0400 kg Kawat las listrik 33,000.00 1,320.00

    0.0300 lt Bahan bakar solar 4,500.00 135.00

    0.0040 lt Pelumas 34,450.00 137.80

    0.0100 org Pekerja 30,000.00 300.00

    0.0050 org Tukang besi profil 42,500.00 212.50

    0.0050 org Kepala tukang besi profil 45,000.00 225.00

    0.0025 org Mandor 40,000.00 100.00

    0.2500 lot Alat bantu (mesin las listrik) 150,000.00 37,500.00

    G.41 1 TITIK MELUBANG KONSTRUKSI BESI DENGAN BOR 40,025.00

    0.0500 org Pekerja 30,000.00 1,500.00

    0.0200 org Tukang besi profil 42,500.00 850.00

    0.0030 org Kepala tukang besi profil 45,000.00 135.00

    0.0010 org Mandor 40,000.00 40.00

    0.2500 lot Alat bantu (mesin bor listrik) 150,000.00 37,500.00

    G.42 1 M2 PEKERJAAN WIREMESH M8 83,213.50

    1.0100 m2 Wiremesh M8 72,600.00 73,326.00

    0.1000 kg Kawat las listrik 33,000.00 3,300.00

    0.1000 org Pekerja 30,000.00 3,000.00

    0.0750 org Tukang besi profil 42,500.00 3,187.50

    0.0100 org Mandor 40,000.00 400.00

    VIII H PEKERJAAN PENUTUP ATAP

    H.1 1 M2 Pasang Atap Genteng Mantili Kecil 33,367.50

    25.0000 Buah Genteng mantili 1,000.00 25,000.00

    0.1500 OH Pekerja 30,000.00 4,500.00

    0.0750 OH Tukang Kayu 42,500.00 3,187.50

    0.0080 OH Kepala Tukang 45,000.00 360.00

    0.0080 OH Mandor 40,000.00 320.00

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 34

  • 7/30/2019 Analis RAB Gedung 2010

    35/44

    H.2 1 M2 Pasang Atap Genteng Mantili Besar 31,640.00

    20.0000 Buah Genteng Mantili Besar 1,200.00 24,000.00

    0.1500 OH Pekerja 30,000.00 4,500.00

    0.0600 OH Tukang Kayu 42,500.00 2,550.00

    0.0060 OH Kepala Tukang 45,000.00 270.00

    0.0080 OH Mandor 40,000.00 320.00

    H.3 1 M' Pasang Genteng Bubung Mantili 50,480.00

    5.0000 Buah Genteng Bubung Mantili 2,900.00 14,500.00

    8.0000 Kg Portland Semen 1,312.50 10,500.00

    0.0320 m3 Pasir Pasang 125,000.00 4,000.00

    0.4000 OH Pekerja 30,000.00 12,000.00

    0.2000 OH Tukang Batu 42,500.00 8,500.00

    0.0200 OH Kepala Tukang 45,000.00 900.00

    0.0020 OH Mandor 40,000.00 80.00

    H.4 1 M2 Pasang Atap Asbes Gelombang (80 x 210 cm) x 5 mm 38,577.50

    0.6000 Lbr Asbes Gelombang 45,850.00 27,510.00

    0.1200 Kg Paku Pancing 60 x 230 25,000.00 3,000.00

    0.1400 OH Pekerja 30,000.00 4,200.00

    0.0750 OH Tukang Kayu 42,500.00 3,187.500.0080 OH Kepala Tukang 45,000.00 360.00

    0.0080 OH Mandor 40,000.00 320.00

    H.5 1 M2 Pasang Atap Genteng Beton 41,852.50

    11.0000 bh Genteng Beton Standrad 2,750.00 30,250.00

    0.0300 Kg Paku Biasa 2" - 5" 16,750.00 502.50

    0.2000 OH Pekerja 30,000.00 6,000.00

    0.1000 OH Tukang Kayu 42,500.00 4,250.00

    0.0100 OH Kepala Tukang 45,000.00 450.00

    0.0100 OH Mandor 40,000.00 400.00

    H.6 1 M2 Pasang Atap Sirap 175,770.00

    60.0000 Lbr Genteng Sirap 2,589.50 155,370.00

    0.2000 Kg Paku Biasa 1/2" - 1" 16,750.00 3,350.00

    0.1660 OH Pekerja 30,000.00 4,980.00

    0.2500 OH Tukang Kayu 42,500.00 10,625.00

    0.0250 OH Kepala Tukang 45,000.00 1,125.00

    0.0080 OH Mandor 40,000.00 320.00

    H.7 1 M' Pasang Nok Genteng Beton 72,975.00

    3.5000 Buah Nok Genteng Beton 9,075.00 31,762.50

    0.0500 Kg Paku Biasa 2" - 5" 16,750.00 837.50

    10.8000 Kg Portland Semen 1,312.50 14,175.00

    0.0320 m3 Pasir Pasang 125,000.00 4,000.00

    0.4000 OH Pekerja 30,000.00 12,000.00

    0.2000 OH Tukang Batu 42,500.00 8,500.00

    0.0200 OH Kepala Tukang 45,000.00 900.00

    0.0200 OH Mandor 40,000.00 800.00

    H.8 1 M' Pasang Nok Sirap 58,457.93

    0.4000 Lbr Seng Plaat 3" x 6" BJLS 28 81,200.00 32,480.00

    0.0600 Kg Paku Biasa 1/2" - 1" 16,750.00 1,005.00

    0.5000 Kg Paku Biasa 2" - 5" 16,750.00 8,375.00

    0.0040 m3 Kayu Bengkirai Papan Tebal 3 cm 214,482.84 857.93

    0.1250 OH Pekerja 30,000.00 3,750.00

    0.2500 OH Tukang Kayu 42,500.00 10,625.00

    0.0250 OH Kepala Tukang 45,000.00 1,125.00

    0.0060 OH Mandor 40,000.00 240.00

    H.9 1 M2 Pasang Atap Seng Gelombang 63,835.000.7000 Lbr Seng Gelombang 3" x 6" BJLS 28 81,200.00 56,840.00

    0.0200 Kg Paku Biasa 1/2" - 1" 16,750.00 335.00

    0.1200 OH Pekerja 30,000.00 3,600.00

    0.0600 OH Tukang Kayu 42,500.00 2,550.00

    0.0060 OH Kepala Tukang 45,000.00 270.00

    0.0060 OH Mandor 40,000.00 240.00

    \\vboxsrv\conversion_tmp\scratch_6\144824707.xls.ms_office 35

  • 7/30/2019 Analis RAB Gedung 2010

    36/44

  • 7/30/2019 Analis RAB Gedung 2010

    37/44

    J.2 1 UNIT Memasang Closet Jongkok 300,525.00

    1.0000 Buah Kloset Jongkok 123,750.00 123,750.00

    6.0000 Kg Portland Semen 1,312.50 7,875.00

    0.0100 m3 Pasir Pasang 125,000.00 1,250.00

    1.0000 OH Pekerja 30,000.00 30,000.00

    1.5000 OH Tukang Batu 42,500.00 63,750.00

    1.5000 OH Kepala Tukang 45,000.00 67,500.00

    0.1600 OH Mandor 40,000.00 6,400.00

    J.3 1 UNIT Memasang Wastafel 714,572.50

    1.0000 Buah Wastafel 501,950.00 501,950.00

    0.3000 - Perlengkapan 30% Harga Wastafel 501,950.00 150,585.00

    6.0000 Kg Portland Semen 1,312.50 7,875.00

    0.0100 m3 Pasir Pasang 125,000.00 1,250.00

    1.2000 OH Pekerja 30,000.00 36,000.00